Initial Environmental Examination

Document Stage: Draft Project Number: 42486-016 February 2016

IND: Urban Services Improvement Program – Water Supply Improvement in Amla, Betul-Bazar and Sarni Towns

Package No: MPUSIP-1B

Prepared by Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Initial Environmental Examination

Project No.: 42486

IND: Madhya Pradesh Urban Services Improvement Program – Subproject of Water Supply Improvement in Betul-Bazar, Amla and Sarni Towns (Package 1B)

1

CURRENCY EQUIVALANCE (As on 1 Feb, 2016)

Currency Unit - Conversion

INR 1.00 = $ 0.015

$ 1.00 = INR 66.00

Abbreviations

ADB – Asian Development Bank AP – Affected Person ASO – Assistant Safeguards Officer CFE – Consent for Establishment CFO – Consent for Operation CMO – Chief Municipal Officer CWM – Construction waste management EC – Environmental Clearance EAC – Environment Expert Committee EHS – Environmental Health & Safety EIA – Environmental Impact Assessment EMP – Environmental Management Plan; GOMP – Government of Madhya Pradesh GRC – Grievance Readdressed Committee GRM – Grievance Redress Mechanism IEE – Initial Environmental Examination; KL – Kilo Liter KM – Kilo Meter LARRA – Land Acquisition, Rehabilitation and LPCD – Liters per Capita per Day MCM – Million Cubic Meter MFF – Multi-tranche Financing Facility MLD – Million Liters per Day MOEF – Ministry of Environment & Forest MPPCB – Madhya Pradesh Pollution Control Board MPUDC – Madhya Pradesh Urban Development Company MSL – Mean Sea Level NAAQS – National Ambient Air Quality Standards NGO – Non-Government Organization NOC – No Objection Certificate PDMC – Project Design and Management Consultant PHED – Public Health Engineering Department PIU – Project Implementation Unit; PMU – Project Management Unit PHED – Public Health Engineering Department PIU – Project Implementation Unit; 2

PMU – Project Management Unit TM – Traffic Management SEIAA – State Environment Impact Assessment Authority SPS – Safeguard Policy Statement,2009 ToR – Term of Reference UDED – Urban Administration & Environment Department UFW – Unaccounted for Water ULB – Urban Local Body WRD – Water Resource Department WTP – Water Treatment Plant WSS Water Supply Scheme

3

WEIGHTSAND MEASURES

˚C Degree Celsius km kilometer LPCD Liter per capita per day mm Millimeter m meter MLD Million liter per day MCM Million Cubic Meter Nos Number

sq.km Square Kilometer

TABLE OF CONTENT

4

I. EXECUTIVE SUMMARY ...... 9 II. INTRODUCTION ...... 15 A. Background ...... 15 B. Purpose of this IEE Report ...... 17 C. Report Structure...... 17 III. DESCRIPTION OF THE PROJECT ...... 18 A. Project Area ...... 18 B. Existing Water Supply Situation ...... 20 1.Betul-Bazar ...... 20 2.Amla…...... 20 3.Sarni . 21 C. Proposed Project components ...... 22 IV. POLICY, LEGAL & ADMINISTRATIVE FRAMEWORK ...... 35 A. ADB Policy ...... 35 B. National Environmental Laws ...... 35 V. DESCRIPTION OF THE ENVIRONMENT ...... 39 A. Methodology Used for Baseline Study ...... 39 B. Baseline Environmental Profile ...... 48 C. Subproject Site Environmental Features ...... 49 VI. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 61 A. Introduction ...... 61 B. Pre-Construction Impacts – Design & Location ...... 62 C. Construction Impacts ...... 72 D. Operation and Maintenance Impacts ...... 77 VII. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ...... 78 A. Overview ...... 78 B. Public Consultation ...... 78 C. Information Disclosure ...... 78 VIII.GRIEVANCE REDRESS MECHANISM ...... 80 A. Project Specific Grievance Redress Mechanism ...... 80 IX. ENVIRONMENTAL MANAGEMENT PLAN ...... 84 A. Environmental Management Plan ...... 84 B. Implementation Arrangement ...... 110 C. Safeguard Compiances Responsibilities ...... 110 D. Training Needs ...... 112 E. Monitoring And Reporting ...... 114 F. EMP Implementation Cost ...... 115 X. CONCLUSION AND RECOMMENDATION ...... 116 5

LIST OF TABLES

Table 1: Summary for proposed WSS component of Package 1B Town ...... 23 Table 2: ApplicableEnvironmental Regulations ...... 36 Table 3: WHO Ambient Air& Noise Quality Guidelines ...... 38 Table 4: Baseline Characteristics of Package 1B Town ...... 40 Table 5: Site Environmental Features of Betul Bazar ...... 49 Table 6: Site Environmental Features of Amla ...... 51 Table 7: Site Environmental Features of Sarni...... 53

Table 8: Ground water quality Amla………...... 66

Table 9: Environmental component to be affected ...... 73 Table 10:DesignStageEnvironmentalManagementPlan ...... 86 Table 11:EnvironmentalManagement PlanofAnticipatedImpactsduringPre-Construction .....88 Table 12:EnvironmentalManagement PlanofAnticipatedImpactsduring Construction ...... 93 Table 13: Environmental Management Plan of Anticipated Impacts during Operation ...... 104 Table 14:Environmental Monitoring Plan ofAnticipatedImpactsduring Construction ...... 107 Table 15:Environmental Monitoring Plan ofAnticipatedImpactsduring Operation ...... 108 Table 16:Outline capacity Building program on EMP Implementation...... 113 Table17:Cost Estimates toImplementtheEMP ……………………………………………..115

LIST OF FIGURES

Figure 1: Location Map of Towns ...... 19 Figure 2: Base Map of Betul Bazar WSS ...... 26 Figure 3: Flow diagram of WTP Betul Bazar ...... 27 Figure 4: Elevation Plan for Betul Bazar WSS ...... 28 Figure 5: Distribution Map of Amla WSS ...... 29 Figure 6: Cross Section of Proposed Weir Amla town ...... 30 Figure 7: Flow diagram of WTP Amla town ...... 31 6

Figure 8: Base Map of Sarni WSS ...... 32 Figure 9: Key Elevation of Sarni Water Supply Scheme ...... 33 Figure 10: Schematic Flow Diagram of WTP for Sarni WSS ...... 34 Figure 11: Project WSS Component of Betul Bazar on Toposheet ...... 57 Figure 12: Project WSS of Baitulbazar on Toposheet …………………………………..….. 58 Figure 13: Project WSS Component of Amla on Toposheet ...... 59 Figure 14: Project WSS Component of Sarni on Toposheet ...... 60 Figure 15: Ground Water Table Betul Bazar ...... 64 Figure 16: Google Map showing Upstream and downstream area ...... 68 Figure 17: Contour Survey of Bel River at the Proposed Weir Location ...... 69 Figure 18: Ground Water Table Sarni……………………………………………………………71

LIST OF APPENDIX

Appendix 1: Stakeholder Consultations of Betul Bazar ...... 119 Appendix 2: Stakeholder Consultations of Amla ...... 120121 Appendix 3: Stakeholder Consultations of Sarni ...... 120123 Appendix 4: Rapid Environment Assessment Checklist for Betul Bazar ...... 125 Appendix 5: Rapid Environment Assessment Checklist for Amla...... 129 Appendix 6: Rapid Environment Assessment Checklist for Sarni...... 133

Appendix 7: Water Analysis Report of Amla ...... 138 Appendix 8: Water Analysis Report of Sarni ...... 139

Appendix 9: Salient features of satpura Reservoir...... 140

Appendix 10: Toposheet BetulBazar ...... 141 Appendix 11: Toposheet Amla ...... 142 Appendix 12: Toposheet Sarni ...... 143 Appendix 13:NationalAmbientAirQualityStandards ...... 144 Appendix 14:NationalAmbientAirQualityStandards inRespect ofNoise ...... 145 Appendix 15:VehicleExhaust Emission Norms ...... 145

7

Appendix 16:DrinkingWaterStandards ...... 146 Appendix 17: Extract from construction and demolition management rules , 2016 ...... 149 Appendix 18: Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works ...... 155 Appendix 19:SampleGrievance RegistrationForm ...... 165 Appendix 20: Sample Environmental Site inspection Report ...... 167 Appendix 21 : Quarterly Reporting Format for Assistant Safeguards Officer ...... 169

I.EXECUTIVE SUMMARY 8

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as the Project. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns

• Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central ; and • Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening

• Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; • Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and • Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

4. Subproject Details: This Initial Environmental Examination report deals with water supply scheme of Package 1B towns contains three towns- Betul Bazar, Amla and Sarni in in Madhya Pradesh. Improvement of water supply in towns is one of the projects proposed under the program. TownsBetul Bazar, Amla and Sarni are situated in Betul District.Betul Bazar is very small town with population 10631 as per 2011 census and of area 5 Sq Km, the present population of Amla as per last census is 30215 .The total 9

municipal area of the town is approximately6.38 Sq. Km.The Sarni is comparatively large town with population of 86141as per 2011 census and with area of 35.42 SqKms.

A. Betul Bazar Theprojectincludefollowing(i)construction of Raw Water Sump & Pump House at junction point (ii) raw water pumping mains of length 5500m and dia 150mm (iii) Water treatment plant of 1.15 MLD capacity;(iv) clear water feeder mains of length 800m of dia 100mm and 475 m of dia 150mm (v) Construction of one new OHT of 200 KL and using of existing 300 KL OHT (v) 16157 m of distribution lines proposed in Betul Bazar.

B. Amla Theprojectincludefollowing(i). Construction of weir having length of 70 m and 8.0 m total height including 2 m foundation at Bel River, (ii). Construction of intake well having diameter of 5.00 and height of 12.0 m for drawl of 3.60 MLD raw water (iii). Raw Water Transmission Providing, laying & jointing 200mm diameter DI K-9 class pipe having 150 m length (iv). Construction of Rapid Gravity Treatment plant of 3.60 MLD capacity (v). Construction of Clear water sump well and pump house having capacity for supplying 3.40 MLD clear water (vi). Providing, laying & jointing 200 mm diameter DI K- 9 pipe from Treatment plant to J1 near Police Station at Amla having length of 5924 m (vii). Providing, laying & jointing of Feeder network for feeding the existing & Proposed OHTs of 150-200 mm diameter and 4086 m length of DI K-7 class (viii). Construction of 1no. OHT having capacity of 200 KL and (ix). Providing, laying & jointing 58423.00 m of Distribution network comprising of HDPE PN 10 pipe of 110 mm to 200 mm diameter.

C. Sarni: The Project include following (i) proposal of intake cum jack well at Satpura reservoir(ii) Raw water main from Satpura reservoir of length 6700m and dia 500mm(iii) Water treatment plant of 20.0 MLD capacity; (iv) Clear water rising mains of total length of 5000m (2250m of 150mm dia, 300m of 400mm dia and 2450m of 250mm dia) (v) Construction of five no. of new OHT of capacity 1500 KL, 1500 KL, 1500 KL, 1000 KL and 300 KL capacity ; using of existing 500 KL OHT in ward-1 (v) 101107 m of distribution lines proposed in Sarni 5. screening and assessment of potential impacts. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB‟s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre-construction, construction and operation of the improved infrastructure.

6. The subproject is unlikely to cause significant adverse impacts because: (i) the components will involve straightforward construction and operation, so impacts will be mainly localized; (ii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements; and (iii) being located mainly in an existing built-up area, will not cause direct impact on terrestrial biodiversity values. Potential negative impacts mainly arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts, 10

and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation of these impacts to acceptable levels.

7. Categorization. Based on results of the assessment and ADB SPS, the subproject is classified as environmental Category B, i.e., the subproject is judged to be unlikely to have significant adverse environmental impacts. An initial environmental examination (IEE) is required to determine whether significant environmental impacts warranting an environmental impact assessment are likely.

8. This IEE aims to (i) provide critical facts, significant finding, and recommended actions; (ii) present the national and local legal and institutional framework within which the environmental assessment has been carried out; (iii) provide information on existing geographic, ecological, social and temporal context including associated facilities within the subproject’s area of influence; (iv) assess the subproject’s likely positive and negative direct and indirect impacts to physical, biological, socioeconomic, and physical cultural resources in the subproject’s area of influence; (v) identify mitigation measures and any residual negative impacts that cannot be mitigated; (vi) describe the process undertaken during project design to engage stakeholders and the planned information disclosure measures and the process for carrying out consultation with affected people and facilitating their participation during project implementation; (vii) describe the subproject’s grievance redress mechanism for resolving complaints about environmental performance; (viii) present the set of mitigation measures to be undertaken to avoid, reduce, mitigate, or compensate for adverse environmental impacts; (ix) to describe the monitoring measures and reporting procedures to ensure early detection of conditions that necessitate particular mitigation measures; and (x) identify indicative costs and who is responsible for carrying out the mitigation and monitoring measures.

9. Description of Environment: Proposed subproject component area under the Betul Bazar, Amla and Sarni in Betul District. For Betul -Bazar, water supplied in subproject area will be taken by the trapping raw water feeder mains for Betul City. Betul Bazar is also situated around 10 km from Satpura forest reservoir, so there will not be any negative impact on forest reservoir due to construction in Betul Bazar. For Betul Bazar, water supplied in subproject area will be taken by the trapping raw water feeder mains for Betul City from Tapti River. Water sustainability of Tapti River was analyzed for supplying water to Betul Bazar. Tapti River is found sustainable to supply the water in Betul in terms of quality as well as quantity. All the proposed structure like WTP and OHT will be constructed on Revenue land that is vacant and no any ecological and environmental feature is present on that siteany of the project components will not fall under the boundary.The proposed intake structure for Sarni is situated in Satpura reservoir. The sarni town is surrounded and enter locked by Satpura forest reservoir. But none of any proposed structure under Sarni WSS is coming under forest and restricted area.Construction o f W T P islocatedonMunicipalownedbarrenlandwithnonotabletreecover.Project activitiesare confined toidentifiedsites,anddo notencroachintoforests.In Amla Intake well is to be built in Bel river which is under the control of WRD GOMP and the WTP site is proposed on govt. land , there is no involvement of forest land and no tree cutting is required.The ground water availability in these areas comes under Safe Zone as per Central Ground Water Board (CGWB) report.

11

10. Potential environmental impacts. The subproject is unlikely to cause significant adverse impacts because: (i) relatively small scale as the population and water demand is minimal, (ii) the components will involve straightforward construction and operation, so impacts will be mainly localized; and (iii) predicted impacts are site-specific and likely to be associated with the construction process and are produced because the process is invasive, involving excavation and earth movements.

11. Environmental impacts as being due to the project design or location are not significant. The proposed water supply schemes include design of new water sources nearest surface water bodies,that include construction of Weir (for Amla). Considering good water availability and very small demand, it is assessed to be unlikely to have any significant issue of source sustainability. Given that Weir is small structure with have limited & fixed height and submergence confined to river course with no direct water withdrawals, the impacts on downstream and ecosystem are likely to be insignificant. Water quality is good and there are no potential pollution sources in the vicinity that could affect the water quality. Although none of the components are located within the forest, conduct of construction works and presence of workers, vehicles may damage /disturb the sensitive areas. Necessary precautionary measures are suggested to avoid any impacts.

12. During construction, potential negative impacts mainly arise from disturbance of residents, businesses, increase in traffic, increase in noise level and dusts, and the need to dispose moderate quantities of waste soil during construction phase and generation of sludge from the WTP during operation and maintenance phase. However, there are well-developed methods for mitigation, minimization to acceptable levels. Operation phase impacts are likely to be insignificant.

13. Environmental Management Plan. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels. Locations and sitting of the proposed infrastructures were considered to further reduce impacts. These include (i) locating facilities on government-owned land to avoid the need for land acquisition and relocation of people; and (ii) laying of pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on livelihoods specifically in densely populated areas of the town.

14. The EMP includes design measures such as (i) design of small Weir; (ii) wash water recovery for the WTP to reduce effluent to be discharged and safe sludge disposal (iii) energy efficient pumping equipment and (iv) quick leak detection and rectification to save the resources, etc. During construction, the EMP includes mitigation measures such as (i) implementation of traffic management plan in coordination with local traffic police to minimize traffic impacts; (ii) awareness campaigns and consultations to inform residents and businesses of potential disturbances; (iii) provision of walkways and planks over trenches to ensure access will not be impeded; (iv) use of noise-dampening measures in areas with sensitive receptors such as hospitals, schools, places of worships and other silence-zones; (v) use of dust-suppression methods such as watering and/or covering of stockpiles; and (vi) finding beneficial use of excavated materials to extent possible to reduce the quantity that will be disposed off. As for the O&M phase, facilities will need to be repaired from time to time, but environmental impacts will be much less than those of the construction period as the work will be infrequent, affecting small areas only. The design of the WTP includes dewatering and drying areas as part of sludge management. 12

15. The EMP will guide the environmentally sound construction of the subproject and ensure efficient lines of communication between Madhya Pradesh Urban Development Company (MPUDC), project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non- detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries.

16. The contractor will be required to submit to PMU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

17. Consultation, disclosure and grievance redress mechanism. The stakeholders were involved in developing the IEE through discussions on-site and public consultation at several places in the town, after which views expressed were incorporated into the IEE and in the planning and development of the project. The IEE will be made available at public locations and will be disclosed to a wider audience via the ADB, MPUDC and PMU websites. The consultation process will be continued and expanded during project implementation to ensure that stakeholders are fully engaged in the project and have the opportunity to participate in its development and implementation. A grievance redress mechanism is described within the IEE to ensure any public grievances are addressed quickly.

18. Implementation Arrangements. Urban Development and Environment Department (UDED) of Government of Madhya Pradesh will be the Executing Agency. Implementing Agency will be Madhya Pradesh Urban Development Company (MPUDC), A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs). Several teams of Design Consultants, and a Program Management Consultant (PMC) centrally located in PMU and with field teams, will support PMU & PIUs. Infrastructure will be designed, built, and operated (DBO) by contractor for 10 years, after which it will be transferred to the ULB. Project Officer (Environment) at PMU and Assistant Safeguard Officer (ASO) at each of the PIU will be responsible for environment safeguards tasks, and will be supported by Environment Specialist of PMC Team. Contractor personnel will include an Environment, Health and Safety (EHS) supervisor and an Archaeological Supervisor.

13

19. Monitoring and Reporting.The PMU and PMDC will be responsible for monitoring. The PMDC will submit quarterly and semi-annual monitoring reports to PMU, and the PMU will review and send the semi-annual monitoring reports to ADB. ADB will post the environmental monitoring reports on its website.

20. Conclusions and Recommendations.The proposed project is therefore unlikely to cause significant adverse impacts. The potential impacts that are associated with design, construction and operation can be mitigated to standard levels without difficulty through proper engineering design and the incorporation or application of recommended mitigation measures and procedures. Based on the findings of the IEE, there are no significant impacts and the classification of the project as Category “B” is confirmed. No further special study or detailed environmental impact assessment (EIA) needs to be undertaken to comply with ADB SPS (2009) or GOI EIA Notification (2006). Project will require following government permission/approvals: (i) permission of WRD, GOMP for water abstraction from Bel River and construction of Anicut on Bel river for Amla townand for abstraction from Satpura Reservoir for Sarni town iii) permission /approvals of water Resources Department (WRD) ,GOMP for water abstraction from Satpura reservoir (iv)consent for construction of WTP in government land and establishment and consent for operation for WTP from Madhya Pradesh Pollution Control Board. These permissions/approvals shall be obtained prior to invitation of bids.This IEE will be updated during the detailed design stage.by the DBO contractor to reflect any changes, amendments and will be reviewed and approved by PMU.

14

II. INTRODUCTION A. Background

1. Government of Madhya Pradesh with loan funding from Asian Development Bank (ADB) has proposed to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP), herein after referred as ‘the Project’. Madhya Pradesh Urban Development Company Limited (MPUDC) shall be the Implementing Agency and the State Urban Development and Housing Department (UDHD) shall be the executing agency for the Project.

2. The Project components are as follows:

(i) Component 1: Improvements to water supply and sewerage services in identified towns ➢ Continuous, pressurized, safe and sustainable drinking water through private household metered connections to 350,000 households with about 1.7million population resident in sixty-four towns in the State of Madhya Pradesh in Central India; and ➢ Sewage and storm water collection and treatment services proposed initially in two (2) identified towns (Khajuraho and Rajnagar) servicing about 42,000 population resident in 8000 households;

(ii) Component 2: Institutional Strengthening ➢ Capacity Building of implementing agencies (IAs), participating Urban Local Bodies (ULBs) and service utilities in contract management and service delivery for ensuring long term sustainability of services; ➢ Setting up of geographic information system (GIS) based water and sanitation asset management and service delivery monitoring; and ➢ Structured behavioral change campaigns to ensure the improvement in public health and cost recovery of service delivery.

(iii) Component 3: Project Management and Administration Support. This component will support the smooth and effective implementation and operation of the Project which includes expert support in Project design and implementation (design, procurement and Contract and Project Management, safeguards etc.), and project administration through Executing and Implementing Agencies.

3. The key outcome envisaged from the project is “effective urban water service delivery model rolled out in selective urban clusters of the State with the objective of achieving the following performance indicators by the year 2022.

(i) Access to piped water supply coverage increased to 95% of the households from 33% in 2015 in 64 towns; 15

(ii) Women's drudgery for fetching water reduced by 80% (from spending an average of 55 minutes in 2015 to 10 minutes); (iii) Coverage of households with access to improved sanitation systems increased to 80% from 30% in 2015; (iv) Wastewater collection and/or safe sanitation service coverage increased to at least 80% of the households from 0% in 2015 in two towns; (v) Incidence of water logging/flooding reduced to two incidents per annum in four towns; and (vi) Women access to functioning sanitation systems increased to 95% from 25% in 2015 (in poor settlements) in four towns

4. The key outputs envisaged from the project are:

(i) Output 1: Water supply infrastructure improved in 64 project towns and flood and sanitation infrastructure improved in two project towns with the following measurable indicators: ➢ Improved water supply capacity of 186ml/day installed in 64 towns; ➢ 4,000 km water supply networks installed in 64 towns; ➢ 350,000 households provided with metered house connections including 100 government schools; ➢ 8 MLD sewage or septage treatment plants constructed; and ➢ Installation of 120 km sewer and drainage mains and networks.

(ii) Output 2: Sustained urban infrastructure operation and management

➢ 23 performance-based contract (PBC) operation and maintenance (O&M) water supply contracts for 64 ULBs signed and operated; ➢ ULBs institute volumetric water charges for recovery of water service O&M costs ➢ ULBs’ water tariff collection ratio improved to 90% from 50% in 2014 based on the water meters’ readings ➢ 100% operating cost recovery (excluding debt service) achieved; ➢ GIS system established for effective O&M of water services

5. The subproject towns Betul Bazar , Amla and Sarni of package 1B are located in Betul District and improvement of water supply in these three towns is one of the subprojects proposed under MPUSIP The objectives of proposed Water Supply System are to supply safe wholesome water in adequate quantity at convenient points and at reasonable cost to the users. In order to encourage personal and household hygiene, proper planning is necessary in the formulation and implementation of scheme. The objectives of proposing new Scheme for town are: (i) Long term sustainability and equity of water service provision (ii) Maintaining a balance between supply and demand (iii) Financing the rehabilitation of existing infrastructure and expansion of new infrastructure (iv) Appropriate institutional structures to provide autonomy, accountability and incentives (v) Operations & Maintenance (O&M), Cost Recovery and tariffs (vi) Human 16

resources, systems, and equipment capacity building for efficient working environment.

B. Purpose of this IEE Report

6. ADB requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for environmental assessment are described in ADB‟s Safeguard Policy Statement (SPS), 2009. The potential environmental impacts of the subproject have been assessed using ADB Rapid Environmental Assessment Checklist for Water Supply. Then potential negative impacts were identified in relation to pre- construction, construction and operation of the improved infrastructure, and results of the assessment show that the subproject is unlikely to cause significant adverse impacts. Thus, this initial environmental examination (IEE) has been prepared in accordance with ADB SPS‟s requirements for environment category B projects.

7. This IEE is based on the detailed engineering report prepared by the Designed Consultant team and will be finalized during implementation stage by DBO contractor to reflect any changes and latest subproject designs. The IEE was based mainly on field reconnaissance surveys and secondary sources of information. No field monitoring (environmental) survey was conducted however, the environmental monitoring program developed as part of the environmental management plan (EMP) will require the contractors to establish the baseline environmental conditions prior to commencement of civil works. The results will be reported as part of the environmental monitoring report and will be the basis to ensure no degradation will happen during subproject implementation. Stakeholder consultation was an integral part of the IEE.

8. This Report contains the following nine (9) sections, besides the executive summary: (i) Introduction (ii) Description of the project (iii) Policy, legal and administrative framework (iv) Description of the environment; (v) Anticipated environmental impacts and mitigation measures; (vi) Public consultation and information disclosure; (vii) Grievance redress mechanism; (viii) Environmental management plan, and, (ix) Conclusion and recommendation

17

III. DESCRIPTION OF THE PROJECT

A. PROJECT AREA

9. Subproject for improvement of water supply system in the four towns Betul-Bazar, Amlaand Sarni is proposed under Tranche 1, MPUSIP. Subproject towns are located in Betul district in around 100 km distance .Population of all the three towns as per 2011 census is; Betul-Bazar- 10631,Amla-30215and Sarni-86141.

10. Betul Bazar is twin city of Betul city. The district derives its name from this town of Betul Bazar about 5 km South of Badnur, the headquarters of the district. During the Maratha regime also, in the beginning of the British rule, Betul or Betul Bazar was the district headquarters. In 1822 the district headquarters was shifted to Badnur, after which the village came to be known as ‘Badnur Dhana’, meaning Badnur village in the local dialect. Now, even after such a long time, not only the district retains the old name, but the name of the new Headquarters town, Badnur, has also been superimposed by "BETUL". The total area of Betul Bazar is 5 Sq KM and population as per 2011 census is 10631.

11. Amla is a town which lies in southern part of Madhya Pradesh. The Municipal area is being divided in 18 wards for civil administration. Amla geographically lies at 21.92°N Latitude&78.13°ELongitude. It is situated 40 kms from District Headquarter Betul.The total municipal area of the town is approximately6.38Sq.Kms and out of that 3.28 sq.km comes under developed area and remaining area is under agriculture, water bodies and unorganized open spaces of the city.

12. Sarni is located in an area that is known as a part of the Gondwana tract after the Gond Tribe, who chiefly inhabited in this area and practice shifting cultivation. It is situated in Betul district. The total area of the town 35.42 Sq Kms and population as per 2011 census is 86141.

18

Figure 1: Location Map of Towns

BETUL-BAZAR SARNI

AMLA

19

B. EXISTING WATER SUPPLYSITUATIONS

1. BETUL BAZAR

13. Present water supply of the Betul-Bazar town is mostly depend on ground water i.e. on 8 tube wells (7 working), 36 numbers of hand pumps (28 working) and 3 open wells. Water from the tube wells and open wells are pumped to two OHT’s of capacity 300 KL and 500 KL. Total 85 Hp (10 Hp on each tube well and 7.5 Hp on each open well) capacity pumps are installed at 7 tube wells and 3 open wells. Both the OHT’s are filled only once in a day. It takes approximately 12 hours to fill the 300 KL OHT and approximately 14 – 16 hours to fill 500 KL OHT. Then the water is distributed with the help of 7 km of distribution system having ACP pipes from 100 to 300 mm diameter and GI pipes having diameter 50 mm to 80 mm laid in the town. Thus the total water supplied to the Betul Bazar town at present is 0.40MLD i.e. 38 LPCD.

2. AMLA

14. The maximum available water at present from groundwater sources is upto 1.00 MLD, from which the average water supply is only 33 liters per capita per day in comparison to 70 lpcd.

15. The piped water supply scheme of Amla town was first introduced in 1983.Total installed capacity of the present water supply based on underground sources is almost 1.00 MLD. The inhabitants of the Town receive water at a maximum rate of 33lpcd. Presently town is getting water from the 29Tube wells, 24 Wells and 140 hand pumps. There is no water treatment plant & intake well. The underground water table is at a depth of approximately 80-100 M which is further decreasing every year as a result of drawl of water from the tube wells. The increasing depth of water table is resulting in high pumping cost and also the possibility of presence of heavy metals in water.

16. Presently Amla is having 4 nos. of Overhead Tanks, 1 having capacity of 165 KL at Nagar Palika, 1 having capacity of 200 KL at Bada Park & 2 having capacity of 310 KL; 1 at Govind Colony & 1 at Bodkhi School & all are in good conditions. The water is supplied by directly pumping water from the tubewells to the OHTs.

17. The water is supplied on alternate day basis. In some pockets water is supplied at an interval of 2-days (for 30 to 45 minutes). The water from wells and tube wells are pumped into the OHTs and supplied after adding bleaching powder. The existing system is not sufficient to cover piped water supply of whole town. In the absence of 100% piped water supply system people are relying upon Public Taps and Municipal

20

council has made necessary arrangements of water tankers to provide water to the community during the summer seasons and in case of emergency.

18. The existing distribution system comprises of GI pipes having diameters of 50 mm-150 mm & total length of existing distribution system is approximately 45.00 Kms. The pipes are not in a good condition; hence it has been discarded in the proposed project.

3. SARNI

19. Present water supply of the Sarni town is mostly depends on water from Satpura Reservoir. Actually existing water supply scheme of Sarni was executed and operated by MPEB and WCL.

20. Scenario of Water Supply Scheme by Western Coalfield Limited: Ward numbers 14 to 29 of Pathakheda and 30 to 35 of Shobhapur is coming under WCL area. Intake well was constructed in the Satpura Reservoir. Water will be pumped to WTP at Pathakheda having cumulative capacity 7.70 MLD. Then the water will be pumped to 10 numbers of OHT’s having cumulative capacities 1868 KL. All these OHT’s were constructed from year 1975 to 2000. After that the water will be distributed to wards numbers 14 to 30 with the help of approximately 40 km of distribution system. Mainly CI pipes having diameter 300 mm & 200 mm and GI Pipes having diameter 100 mm & 50 mm were used to distribute the water. The entire scheme was executed more than 30 years back and hence augmentation is required.

21. Scenario of Water Supply Scheme by MPEB: Ward numbers 1 to 13 of Sarni is coming under MPEB area. Intake well was constructed in the Satpura Reservoir. Water will be pumped to WTP at Sarni near Thermal Power Plant having approximate capacity 4 MLD. Then the water will be pumped to 2000 KL OHT in Ward No 7. After that the water will be distributed to wards numbers 1 to 13 with the help of approximately 30 km of distribution system. Mainly CI pipes having diameter 300 mm & 200 mm and GI Pipes having diameter 100 mm & 50 mm were used to distribute the water. The entire scheme was executed around year 1980 and hence augmentation is required.

22. Present water supply arrangements are not adequate and since the water supply infrastructure was constructed more than 30 years back that leads to heavy water losses, therefore water scarcity conditions are arising. Water supply losses during transmission are also very high i.e. more than50%, that leads to a high energy consumption and loss of ULB.Presently water is supplied only for 45 min on daily.

21

C. Proposed Project Components

1. BETUL-BAZAR

23. For Betul Bazar WSS, the most appropriate water source considered is Tapti River. A bringwater supply scheme is proposed for Betul town from Tapti River. Barrage proposed to beconstructed on Tapti River for Betul town and water will be to pump to WTP from TaptiRiver. Barrage was designed considering the water demand of Betul Town. It is proposed to tap raw water from 400 mm DI K-9 Raw Water Rising Main at Multai Road inBetul. Also, Raw Water Sump& Pump House at junction point are proposed to construct. From Junction Point water is pumped to WTP with the help of Centrifugal Pumps and 150mm DI K9 RWRM having length 5500 m.WTP capacity is of 1.15 MLD is proposed to be constructed at Khasra No – 84/1 in Ward No1 on Betul Road. The ownership of land is verified and is in possession of RevenueDepartment, Govt. of Madhya Pradesh and considered land is ensured for the purposed ofwater supply scheme.Presently two OHT’s are available in Betul Bazar having capacities 300 KL in Ward No 3 &500 KL in Ward No 7. The 500 KL OHT was constructed in 1990. The present condition of500 KL is not good and hence proposed not to use this OHT in new scheme. The 300 KL wasconstructed in 2004 and proposed to be used in new scheme. In addition to this 200 KL OHTis proposed to be constructed in Ward No 8 at Khasra No 475 to cater the water demand of Betul Bazar town till year 2033 new water supply scheme is needs to be implemented for population for the of 13000 souls for a year 2048 (Ultimate Year of Design) considering 70 LPCD water supply and source as surface source to ensure adequate quantity, quality and desired pressure at doorstep of each household as per the Guidelines of MPUSIP.As Betul Bazar is tapping raw water from town Betul where the Bids are in final process and project is likely to be completed in 6 months.

2. AMLA

24. As per the proposed augmentation project, it is proposed to augment the capacity of existing Amla water supply so as to suit the drinking water needs of the probable population of Amla for next 30 years taking net supply rate as 70 lpcd. The population of Amla for next 30 years (upto 2048) i.e., taking 2 year as execution period and 30 years as service period has been estimated as 43,500 i,e., design population. Taking 70 lpcd as per capita demand, the net water requirement shall be 3.05 MLD. After accounting for 15% Transmission and Treatment losses, the raw water required shall be 3.60 MLD. This augmentation project has been designed for augmenting the capacity of water supply system up to 3.60 MLD from Bel River. (a) Weir Construction having length of 70 m and 8.0 m total height including 2 m foundation at Kajli Village on Bel River.

22

3. SARNI

22. A new water supply scheme is needs to be implemented for population for the of 135100souls for a year 2048 (Ultimate Year of Design) considering 135 LPCD water supply and source as surface source to ensure adequate quantity, quality and desired pressure at doorstep of each household as per the Guidelines of MPUSIP. The design base year for the proposed WSS is taken as 2018, in which population is likely to be reached 95500 and water demand will be 16.30 MLD.

23. For the Sarni town, the demand of water supply for the year 2018, 2033 & 2048 are estimated to the tune of 16.30 MLD, 19.70 MLD &23.10 MLD respectively. Thus maximum of 23.10 MLD intake form the source per annum i.e. 8431 ML (8.43 MCM) of drawl of water is to be ensured. Annual average recoupment of water in the tank every year is around 75.43 MCM. While the recoupment of water during rainy season is 75.43 MCM which is 10 times than the annual water demand of Sarni town

24. Following Table 1 shows the proposed water supply systems along with natureand size of components in foursubproject towns.Figure 2 to Figure 10 shows the proposed water systems, component layouts etc

25. Project benefits. The subproject aims to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The subproject will provide continuous, pressurized and safe drinking water services to entire population of the towns (100% coverage). Besides achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency, the subproject will improve the overall environmental quality of the town. It will reduce the reduced time and costs of households in accessing alternative sources of water, and will lead to better public health particularly reduction in waterborne and infectious diseases.

23

Table 1: Summary for proposed WSS component of Package 1B Town

Particulars Betul-Bazar Amla Sarni I. Water demand 1 Base year (2018) 0.95 MLD 2.60 MLD 16.30 MLD 2 Intermediate year 1.05 MLD 3.00 MLD 19.70 MLD (2033) 3 Design year (2048) 1.10 MLD 3.40 MLD 23.10 MLD II. Source 1 Alternatives • Extracting Ground Water • Bel river • Extracting Ground Water • Sapana River • sasundra Dam and sapana • Satpura Reservoir • Sapana Dam Dam • Constructing Dam on Tawa • Tapti River – Tapping on Raw • Narmada River River at Tiliyadoh Water Rising Main of Betul • Tapti River WSS • Machana River Other than these three options, there is Other than these four options, Other then these five options, there is no water body present nearby vicinity there is not water body nearby no water body present nearby vicinity of the Sarni town to consider as a the Betul Bazar town to consider of the town. water source for proposed Water as a water source for proposed Supply Scheme of town. For the Water Supply Scheme of town. A proposed water supply scheme, water supply scheme for Betul Satpura Reservoir is found adequate city is under construction. for the water supply in Sarni town after analyzing all the tree water sources. The location of Satpura dam is in the reachable scratch from the core Sarni town and located in Tehsil – Sarni, Dist - Betul. The dam is around 7.00 km away from Sarni town

2 Selected source Tapti river is taken as water The Bel River is most suitable Satpura Reservoir is selected as water source in this scheme. The raw dependable/sustainable surface source source. water feeder mains for Betul city of water supply because of the less will cross through Betul Bazar. distance and pumping cost. So, trapping of this raw water rising mains of Betul city WSS is found economical for supplying water in Betul Bazar.

III. Proposed system

1 From source to Tapping on Raw Water Rising Raw water abstraction from Open well Intake arrangement at Satpura consumer supply Main of Betul WSS - sump well → raw water transmission (pumping) reservoir - Pump house- Raw water cum pump house -WTP - Clear → treatment → clear water feeder Mains-WTP - Clear Water Water Feeder Mains - OHTs transmission (pumping) → storage → Feeder Mains - OHTs - Distribution - Distribution network - distribution → house connections with network - Household Connection Household Connection meters 2 Head Works RW Sump having Diameter - 4.0 Construction of intake well having Intake well cum jack room (Dia 8.00 m arrangement for water m and Height 4.5 m and Pump diameter 5.00m and height 12.0m & Height 15.50 m), transformer source House 5.0 m High over RW Sump, transformer 63KVA, Location:Intake well will be built in Bel 300KVA, HT/LT line 2.5km. HT/LT line 2.0km River, under the control of Water Resources Department, 3 Raw water pumping Centrifugal Pumps Supply and installation of 2 nos. 10 KW Vertical Turbine Pumps station Discharge 12.68LPS pumps along with all necessary Discharge 118.96LPS Motor 13Hp electrical installation for drawl and Motor 130Hp Head 43m pumping of 3.15 MLD raw water from Head 55m 2 Nos ( 1 Working / 1 Standby Intake well to Treatment plant. 4 Nos ( 2 Working / 2 Standby 4 Raw water RW Rising Main Providing, laying & jointing 200mm RW Rising Main transmission DI K-9 diameter DI K-9 class pipe having 150 DI K-9 150mm dia pipe m length from Intake well at Bel to 500mm dia pipe 5500m length Treatment plant 6700 m length 5 WTP Capacity:1.15 MLD Capacity: 3.60 MLD Capacity: 20 MLD Location: On a government Location: Site located near bank of bel Location: Pathakheda (ward no 28 owned vacant land (0.18 ha) on river, On a government owned vacant land ) near WCL WTP Betul Road near Old Naka (0.67 ha) near secondary school within the town 6 Clear water pumping Pump house within WTP. 2 nos. 49 KW pumps Split case Centrifugal Pumps station Centrifugal pumps - 2 Nos(1 CWPM-I 70m head, 115 Hp motor, Working / 1 Standby) 13Hp each. 74.96 LPS Discharge.

24

CWPM-II 41m head, 13 Hp motor, 12.68 LPS Discharge. CWPM-III 30m head, 25 Hp motor, 37.54 LPS Discharge. 2 Nos for each OHT ( 1 Working / 1 Standby)

7 Clear Water CWFM-I 800m length, 100mm CWPM-200mm dia DI Pipe length 5924m CWFM-I 8150m length, 300mm dia transmission from WTP to JI near police station. DI K9 dia. CWFM-II 300m length 400mmdia. Pipe. CWFM-II 475m length 15mmdia. CWFM-III 2450m length 250mmdia. DI K9 pipe. DI K9 pipe. CWGM-I DI K-7 300mm dia , 4055 m length. CWGM-II DI K-7 150mm dia, 1200 m length.

8 Reservoirs / tanks Overhead tank – 1 No. OHTs- 1 Overhead tank – 6 No. Capacity: 200 KL 1- 200KL at krishi mandi 1. Capacity: 1500 KL- 3 1 existing 300 KL considered in 2. 1000 KL-1 new scheme 3. 300KL-1 4. 1 existing 300 KL considered in new scheme 9 Distribution network 16143m – 75 to 200 mm dia Providing, laying & jointing 58423.00 m of 101107m -75mm to 400mm HDPE HDPE pipe Distribution network comprising of HDPE pipe. Location: Along the public roads PN 10 pipe of 110 mm to 200 mm Location: Along the public roads in in the entire town. diameter the entire town Location: Along the public roads in the entire town

10 Bulk flow meters Electromagnetic Bulk flow meter Electromagnetic Bulk flow meter will be Electromagnetic Bulk flow meter will be installed to monitor the installed to monitor the bulk flow in the will be installed to monitor the bulk bulk flow in the main components main components i.e. at the inlet of the flow in the main components i.e. at i.e. at the inlet of the raw water raw water mains to know the quantity of the inlet of the raw water mains to mains to know the quantity of water coming to the WTP, outlet of the know the quantity of water coming water coming to the WTP, outlet clear water sump to know the quantity of to the WTP, outlet of the clear of the clear water sump to know water going for the distribution, outlet of water sump to know the quantity of the quantity of water going for the the service reservoirs to know the quantity water going for the distribution, distribution, outlet of the service of water going in the distribution zone outlet of the service reservoirs to reservoirs to know the quantity of know the quantity of water going in

water going in the distribution the distribution zone zone

11 2418 no,s – at each house in the 6612 no,s – at each house in the town 21663 no,s – at each house in the Consumer connects town town with meters

25

Figure 2. Base Map of Betul-Bazar WSS

26

Figure 3: Flow diagram of WTP Betul-Bazar

27

Figure 4: Elevation Plan for Betul Bazar WSS

28

Figure 5: Distribution Map of Amla Water Supply Scheme

29

Figure 6: Cross Section of Proposed Weir Amla town

30

Figure 7- Flow Diagram of WTP Amla

31

Figure 8:Base map of Sarni WSS

32

Figure 9- Key Elevation Plan of Sarni Water Supply Scheme

33

Figure 10: Schematic flow diagram of WTP for Sarni WSS

34

IV. POLICY, LEGAL &ADMINISTRATIVE FRAMEWORK

A.ADB POLICY

30. ADB requires the consideration of environmental issues in all aspects of ADB’s Operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all ADB investments.

31. Screening and categorization. The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories: (i) CategoryA.Projectscould have significant adverseenvironmental impacts. An EIA isrequiredtoaddresssignificantimpacts. (ii) CategoryB.Projectscould have some adverseenvironmental impacts, but oflesserdegreeorsignificance thanthosein category A.AnIEE isrequired to determine whether significantenvironmental impactswarranting an EIAare likely.Ifan EIA isnot needed, theIEE isregarded asthefinal environmental Assessment report. (iii) CategoryC.Projectsare unlikelyto have adverse environmental impacts. No EIA orIEEis required, although environmental implications arereviewed. (iv) CategoryFI.Projectsinvolve acreditlinethrough afinancial intermediaryor an equity investment in afinancial intermediary. Thefinancial intermediary mustapplyan environmental managementsystem, unless all projectswill resultininsignificantimpacts.

32. Environmental management plan. An EMP, which addresses the potential impacts and risks identified by the environmental assessment, shall be prepared. The level of detail and complexity of the EMP and the priority of the identified measures and actions will be commensurate with the project’s impact and risks.

B.NATIONAL ENVIRONMENTALLAWS 33. The GoI EIA Notification of 2006 (replacing the EIA Notification of 1994), sets out the requirement for Environmental Assessment in India. This states that Environmental Clearance (EC) is required for specified activities/projects, and this must be obtained before any construction work or land preparation (except land acquisition) may commence. Projects are categorized as A or B depending on the scale of the project and the nature of its impacts.

34. Category A projects requires EC from the central Ministry of Environment and Forests (MoEF). The proponent is required to provide preliminary details of the project in the prescribed manner with all requisite details, after which an Expert Appraisal Committee (EAC) of the MoEF prepares comprehensive Terms of Reference (ToR) for the EIA study. On completion of the study and review of the report by the EAC, MoEF considers the recommendation of the EAC and provides the EC if appropriate.

35. Category B projects require environmental clearance from the State Environment Impact Assessment Authority (SEIAA). The State level EAC categorizes the project as either B1 (requiring EIA study) or B2 (no EIA study), and prepares ToR for B1 projects within 60 days. On

35

completion of the study and review of the report by the EAC, the SEIAA issues the EC based on the EAC recommendation. The Notification also provides that any project or activity classified as category B will be treated as category A if it is located in whole or in part within 10 km from the boundary of protected areas, notified areas or inter-state or international boundaries.

36. None of the component of this water supply sub project under the ambit of the EIA Notification 2006, and therefore, EC is not required for the subproject.

37. Besides EIA Notification 2006, there are various other Acts, Rules, Policies and Regulations currently in force in India that deal with environmental issues that could apply to infrastructure Development. The specific regulatory compliance requirements of the subproject are shown in Table 2.

Table 2:ApplicableEnvironmental Regulations

Law Description Requirement MadhyaPradesh Preparedinaccordancewiththe Permission of WRD, StateWater NationalWaterPolicy,itstatesthat“for GoMP for, Policy,2003 environmentalbalance,skillfuland plannedmanagementof alltypesof • Construction developmentalactivities,economicuse of weir and onequitablebasisandin viewofthe intake (Amla). primeimportanceofwaterforallhuman andotherlivingbeings,aneffectiveand • abstracting soundwaterpolicyis necessary”. water from Policyis detailedin17sectionsdealing Satpura withdifferentaspectsofwater resources.No.7 Reservoir for dealswithWater Sarni town AllocationPriorities,andaccordingto whichdrinkingwatersupplyshallhavThehighest priorityfollowedbyirrigation, power,tourism,etc. WaterResourceDepartmentis nodal departmentforpermittingdifferentuses ofwaterresources.Policyalsostates that“clearprovisionforreservationof drinkingwatershallbemadein irrigation projects”

36

Water(Prevention Actwasenactedtoprovideforthe Watertreatmentplant(W AndControlof preventionandcontrolofwaterpollution TP) Pollution)Actof andthemaintainingorrestoringof RequiresCFEandCFOfr 1974,Rulesof wholesomenessofwater,byCentral om 1975,and andStatePollutionControlBoardsand MPPCB. amendments forconferringonandassigningto CPCB/SPCBspowersandfunctions Applicationhastobesub relatingtowaterpollutioncontrol. Controlofwaterpollutionis achieved mitted onlineat throughadministeringconditions http://www.mppcb.nic.i imposedinconsentissuedundertothis n/xgn.html Act.Theseconditionsregulatethe quantityandquantityofeffluent,the location of discharge and the frequency of monitoring of effluents. Any component of the subproject having the potential to generate sewage or trade effluent will come under its purview. Such projects have to obtain Consent For Establish (CFE) under Section 25 of the Act from Madhya Pradesh Environment Emissionsanddischargesfrom the Appendix13 (Protection)Act, facilitiestobecreatedor refurbished providesapplicable 1986andCPCB oraugmentedshallcomplywiththe Standardsforambientair Environmental notifiedstandards quality. Standards. NoisePollution Rule3oftheActspecifiesambientair Appendix (Regulationand Qualitystandardsinrespectofnoisefor 14providesapplicable Control)Rules, differentareas/zones. Noisestandards. 2000amende d upto2010.

LaborLaws Thecontractorshallnotmake Providesapplicable employmentdecisionsbasedupon laborlaws including personalcharacteristicsunrelatedtojob amendmentsissuedfro requirements.Thecontractorshallbase m timeto theemploymentrelationshipuponequal timeapplicableto opportunityandfairtreatment,andshall establishmentsengaged notdiscriminatewithrespecttoaspects in oftheemploymentrelationship, constructionofcivilworks Includingrecruitmentandhiring, . compensation(includingwagesand benefits),workingconditionsandterms ofemploymentorretirement,and discipline.Thecontractorshallprovide equalwagesandbenefitstomenand womenfor work of equal value or type. The Municipal These rules apply to every municipal This rule will be Solid waste authority responsible for collection, applicable as there will (Management & segregation, storage, transportation, be generation of solid Handling) Rules, processing and disposal of Municipal solid waste due to daily 2000 waste. activity of workers and labours during construction works.

37

Construction and The rule shall apply to everyone who Rule will be applicable demolition waste generates construction and demolition waste as construction and management such as building materials, debris, rubble demolition waste will rules, 2016 waste resulting from construction, re- be generated during modeling, repair and demolition of any civil excavation and structure of individual and organization. construction work.

38. ADB SPS Requirements. During the design, construction, and operation of the project the PMU and PIUs are required to apply pollution prevention and control technologies and practices consistent with international good practice, as reflected in internationally recognized standards such as the World Bank Group’s Environment, Health and Safety Guidelines. These standards contain performance levels and measures that are normally acceptable and applicable to projects. When Government of India regulations differ from these levels and measures, the PMU and PIUs will achieve whichever is more stringent. If less stringent levels or measures are appropriate in view of specific project circumstances, the PMU and PIUs will provide full and detailed justification for any proposed alternatives that are consistent with the requirements presented in ADB SPS. International acceptable air and noise quality guidelines are provided below:

Table 3: WHO Ambient Air& Noise Quality Guidelines

38

V. DESCRIPTION OF THE ENVIRONMENT

A. METHODOLOGY USED FOR BASELINE STUDY 39. Data collection and stakeholder consultations. Data for this study has been primarily collected through literature survey, discussion with stakeholder agencies, and field visits to the proposed subproject sites.

40. The literature survey broadly covered the following: I. Project details, reports, maps, and other documents prepared by technical experts of design consultant team II. Discussions with technical experts, municipal authorities, relevant government agencies like WRD, Forest Department, MPPCB, etc. III. Secondary data from previous project reports & published articles, if any, and IV. Literature on land use, soil, geology, hydrology, climate, socioeconomic, and planning documents collected from Government agencies and websites.

41. Ocular inspection. Several visits to the project sites were made during IEE preparation period in 2016 to assess the existing environment (physical, biological, and socioeconomic) and gather information with regard to the proposed sites and scale of the proposed project. A separate socioeconomic study was conducted to determine the demographic information, existing service levels, stakeholder needs and priorities.

B. BASELINE ENVIRONMENTAL PROFILE

42. Following Table 4, presents the baseline environmental profile of subproject towns of Betul Bazar ,Amla and Sarni.It is organized in terms of physical, ecological, economical, and socio cultural resources. A relevant data table, further information, if any, is provided in appendices for further reference.

39

Table 4: Baseline Characteristics of Package 1B Town Sr Particulars Betul Bazar Amla Sarni . 1 Location Located in Betul District Located in Betul District Located in Betul Distri Latitude- 21° 51' 23.36” N 21.92°N Latitude &78.13°E Latitude- 21° 51' 23.36”N Longitude- 77° 55' 39.85”E Longitude. Longitude - 77°55' 39.85” E

2 Connection NH-69 is the major road Amla is a town which lies in Sarni is linked to the other passing through the southern part of Madhya parts of the Madhya Pradesh town. There is no direct Pradesh. The Municipal area is state and India, by road and rail connectivity to the being divided in 18 wards for civil through Rail. Nearest railway town. Betul Bazar town administration.Amla station to the Sarni is can be approached from geographically lies at. It is Ghodadongri Railway Station Betul through National situated 40 kms from District which is around 18 km from Highway–69. It is located Headquarter Betul.The total Sarni. This station is located at a distance of 9.00 kms municipal area of the town is at Delhi – Chennai broad from district headquarter approximately 6.38Sq.Kms and gauge railway line. National Betul. There is bus out of that 3.28 sq.km comes Highway NH 69 near Baretha service from Betul to the under developed area and village 32 Km from Sarni. town. The nearest remaining area is under Nearest airport are at railway station is Betul agriculture, water bodies and & Bhopal both almost 180 km town. unorganized open spaces of the from Sarni. city.

3 Area and Area 5 Sq Km Area 6.38 Sq. Km Area 35.01 Km Population Population 10631 as per Population 30215 as per 2011 2011 Population 86141 as per 2011

4 Topography Town of Betul Bazar is Amla is located in the Satpura Topographical features of the situated on firm ground. hill range. There exits beautiful town explain the variations Topographical features small hillocks in this region. The from RL 465 m to RL 423 m. of the town explain the slope of the cityis from North to The elevation differences variations from RL 651 m South direction. from highest of 465 m to 423 to RL 662 m. The m accounted a maximum elevation differences difference of 42 m in the from highest of 662 m to town. Studies are conducted 651 m accounted a to understand densely maximum difference of populated areas on hill locks 11 m in the town. Due to and other areas. Due to topographical variation, topographical variation it is study would be done on studied that how water 40

how water supply supply services are to be services are to be given given to all areas uniformly to all areas uniformly with with desired water quality, desired water quality, quantity &adequate quantity & adequate pressures. pressures.

5 Soil and Available in the town: Available in the town: Soils in The soil strata in the town are Geology Soils in the district are the district are generally of three mostly Murom and a Black generally of three types types Viz., black cotton soil, Cotton Soil. Sarni is Viz., black cotton soil, sandy loam soil and clayey loam represented by a sequence sandy loam soil and soils. Black Cotton soil is found of Volcano-sedimentary clayey loam soils. Black in Amla town. rocks. Cotton soil is found in Betul Bazar.

6 Climate The climate of Betul is Climate is pleasant and except The climate of Sarni and characterized by a hot monsoon season it remains dry. Betul is characterized by a summer and general Winters starts from the month of hot summer and general dryness except rainfall November and extends up to the dryness except rainfall during during the south- west month of February. Summer the south- west monsoon monsoon season. The seasons. remains from month of season. The year can be year can be divided into March till mid of June. There is divided into four seasons. four seasons. The cold drastic fall in temperature after The cold season, December season, December to the month of October and to February is followed by hot February is followed by January. From March, the season from March to about hot season from March temperature starts rising. The first week of June is the to about first week of month of May is the hottest. The summer season. The period June is the summer average maximum and minimum from the middle June to season. The period from temperatures varies from 460c to September is the south- west the middle June to 110c where as in winter season monsoon season. May is the September is the south- temperature falls down up to hottest month of the year with west monsoon season. 50c. average temperature of May is the hottest month 39.3°C. The minimum during of the year with average the December is 10.3°C. The temperature of 39.3°C. normal annual mean The minimum during the maximum and minimum December is 10.3°C. The temperature are 30.7°C and normal annual mean 17.9° C respectively. maximum and minimum

41

temperature are 30.7°C and 17.9° C respectively.

7 Surface Sapana River: Sapana There are five water body Satpura Reservoir: This is a Water River is not a perennial situated in the municipal power project, located in river. A Sapana Dam boundary, Bel river is 5kms from Betul district of Madhya was constructed on the town. Pradesh. It is an gravity dam Sapana River. This river The irrigation tanks at Sasundra with a maximum height of flows mostly during the Dam and Sapna Dam having 120 feet above deepest rainy season and capacity of 4.60 MCM looking to foundation. It is constructed remains dry almost 8 the water required for irrigation on Tawa River a tributary months of a year. There and the Full tank capacity the of Narmada River. The is no assurance to tanks cannot spare any water construction was started in getting the 100% water quantity for water supply of the year 1964 and completed demand of Betul Bazar Amla. in the year 1967. Its live town during the entire Narmada river is 100kms from storage capacity is 110.37 year. town.Looking to the large MCM while the revised Sapana Dam: This is an distance and high pumping, capacity is 75.43 MCM. irrigation project, located bringing water from Narmada in Betul district will be not only very high in of Madhya Pradesh. It is terms of Capex but also in Opex. an earthen dam with a Tapti is 50kms from the town maximum height of 21.94 which is not perennial. m above deepest Machana river is 2okms, the foundation. It is entire flow of river is being constructed on Sapana tapped and used by municipal river, a tributary council betul hence any of Narmada River. The additional water quantity for WS construction was started from river is not possible. in the year 1952 and completed in the year 1956. Its live storage capacity is 14.31MCM.

8 Ground The underground water The maximum available water at The groundwater level of water level of Betul is also present from groundwater Sarni town I depleted very depleting rapidly. It sources is upto 1.00 MLD, from rapidly. It reduces from 2m to downs from 2m to 6m which the average water supply 4m just from 2013 to 2014. from 2013 to 2014.The is only 33 liters per capita per The groundwater samples groundwater samples are day in comparison to 70 lpcd as are being collected from each being collected from per as per the standards set out monitoring wells during the

42

different wells of Betul in CPHEEO Manual of Ministry month of May every year by Bazar wells during the of Urban Development GOI,for CGWB. The quality of ground month of May every year. the towns not having sewerage water in district is being The quality of ground system.Ground water is not a described by the analysis of water in district is being dependable source of water groundwater samples from described by the analysis supply for longer period & 23 ground water monitoring of groundwater samples presently also the yield of wells. The analysis of water from 23 ground water ground water reduces after rainy samples for year 2012 monitoring wells. The season.The underground water indicate that, the electrical analysis of water table is at depth of approx 80- conductivity (EC) values samples for year 2012 100m which is further were found in the range of indicate that the electrical decreasing every year as a 262 and 16700 us/cm at conductivity (EC) values result of drawl of water from tube 25°C. The nitrate in ground were found in the range wells. The increasing depth of water of Betul district is of 262 and 16700 us/cm water table is resulting in high varying between 1.3-156 mg/l at 250C. The nitrate in pumping cost and also Nitrate more than 100 mg/l ground water of Betul possibility of presence of heavy was found in only one village district is varying metals in water. namely Nimpani (145 mg/l). between 1.3-156 mg/l. The higher concentration of Nitrate more than NO3 may be due to 100mg/l was found in excessive use of fertilizer and only one village namely localized pollution. Nimpani(145 mg/l). The higher concentration of

NO3 may be due to excessive use of fertilized and localized pollution.

9 Air Quality Air Quality data is not Air Quality data is not available Air Quality data is not available available

43

10 Ecology The project area – There are no ecologically Most part of Betul district is municipal area of Betul sensitive area comes under the under thick forest and Sarni Bazar Nagar Parishad, proposed subproject. Streams Municipal area is landlocked comprises the habital are seasonal, so there is no from all sides these protected area of Betul Bazar town. noticeable aquatic life. Flora and forest. These reserve forest There is no ecological fauna found in the area is of limits the growth of Sarni sensitive feature like local species municipal area and it future forest in the project area. outgrowth. But under the Flora and fauna found in boundary of Sarni municipal the area is of local corporation, there is no species. Aquatic life in ecological and environmental the project areas is not sensitive flora and fauna. notable. None of proposed water supply component is comes under forest area.

Satpura National Park is around 91 Km away from the municipal boundary limits of Sarni town and Source.

Source Satpura Reservoir is touching the boundary limits of Sarni town and around 6.70 Km away from the town.

Hence both Sarni town and source Satpura Reservoir is not coming in the Satpura National Park area.

11 Economic Out of total area 60% Over the last decade the The total area of Sarni as Development (100.8 Ha) was under industrial development has given in the records of MCS Land Use residential land use in shown a declining graph, due to is 3541.822 hectares. Out and 2011. Around 2% (3.36 thievery fact that there is of these 3541.822 hectares Agriculture Ha) of total town area is declining share of land for of land, 1207.030 hectares of and under commercial use, industrial development. A major land is available Industry which is inadequate as emphasis was given to promote for development; most of recommended under the industrial area in Amla.But which falls under Forest and UDPFI Guidelines (3-4 % the industrial base in the city Revenue jurisdiction. Out of of the total land should could not be developed as the total developed land of be under commercial expected due to shortage of 1921.241 hectares, 720 use). Commercial electricity and Water. There hectares (37.48 per cent) is 44

activities are mainly exists no large-scale industry in residential, 2.00 hectares is concentrated along the the city. The main industrial units commercial while only 6.00 major roads of the city in Amla are:- hectares of land is and in the form of • Stone crushers under recreational use. informal activities spread • Gur Preparation There is no agricultural over the city. In 2011, • Saw Mill city lacks in industrial activity in the boundary of area. Only 1% (1.68 ha) Sarni town. Satpura Power of the town is under Station is in Sarni town of industrial use which is MPPGCL and coalfield mines very less as compared to is also in Sarni named the UDPFI guidelines. Western Coalfield Limited. 4% (6.72 Ha) area of the

city is covered under public-semi-public uses while 8% (13.44 ha) of land is under Public Utilities and Facilities.There are not any large or small scale industries in the town. The town has been generating its economy from its agricultural resources. The economic base of the town is predominantly agriculture and agro based products, though it is changing into tertiary sector (mainly shops, market based activities) with declining Household units. The cash crops which thrive in agriculture sector are Sugarcane and Cotton

45

12 Infra- The town is well Traffic & Transportation: The Sarni has developed along structure connected to surrounding road network system of Amla is Ghoradongri-Sarni road with and areas andrest of the radial in nature. The Density of all major roads and regional Transport country by State roads in Amla is 4.185 km/ sq. linkages in a perpendicular Highway 26 (Alirajpur- km. pattern to Ghoradongri-Sarni Chindwara) & National road in the past. The Highway 69(Bhopal- commercial activity Nagpur). Settlements predominantly have neighboring the town are developed along the connected through major Ghoradongri-Sarni road (the district roads (MDRs). major artery of the city), beginning at the Ghoradongri Station and end at Satpura Thermal Power station.

The main streets of the town are in working condition but it often leads to frequent choking due to growing traffic in Sarni. Absence of other infrastructure viz. footpaths, road marking, rotary, railing etc. leads to reduction in traffic speed. A Traffic Volume Count Survey has been conducted in the city to understand the characteristics of the traffic at critical locations. The detailed road map of Sarni has been developed from satellite imagery for better understanding of land use and road density. The traffic speed on the main road is very slow particularly during the peak hours as per the survey. Width of the main artery and roads in the city is 10 to 25 meters and the width of other major roads is 5 to 10 meters

46

13 Sewerage/ There is no proper There is no proper sewerage There is no proper sewerage Sanitation/ sewerage network in network in amla. The drainage network in Sarni. The Drainage Betul Bazar. network of this area is controlled drainage network of this area Only 10% area of the by Tawa river and its tributary is controlled by Tawa river town is covered with Phopas river and its tributary Phopas river. drainage network which includes both pucca and kutcha drains. Drainage network of length 7.65 km has been laid along major roads in the form of open drains. Flooding occurs in all the low lying areas near Sapna River 14 Solid Waste There is no practice of There is no practice of The MCS, MPPGCL & WCL Management segregation of recyclable segregation of recyclable waste is responsible for collection, waste at source, evading at source, evading possibility of transportation and disposal possibility of reduction in reduction in quantity of waste of solid waste in their part of quantity of waste generation at source. Such city generation at source. waste on streets or in the bins of Such waste on streets or town goes to disposal sites un- in the bins of Betul Bazar segregated. In the absence of town goes to disposal practice of segregation of waste sites un-segregated. In at source, rag pickers pick up the absence of practice part of this waste in soiled of segregation of waste condition. Currently, there is no at source, rag pickers system of door to door collection pick up part of this waste of waste. in soiled condition. Currently, there is no system of door to door collection of waste. 15 Demography The population of Betul The population of Amla from The population of sarni from Bazar from 1991 to 2011 1991 to 2011 is given below: 1981 to 2011 is given below is given below: 1981: 46500 1991: 84543 2001: 95012 2011: 86141 1991: 9974 1991: 9605 2001: 10573 Literacy Ratio: 79%, 2001: 9646 2011: 32500 Male 82% Female 75 % 2011: 10631 Sex Ratio: 904

Literacy Ratio: 69%,

47

Literacy ratio: 76% Male 56%, Sex ratio: 970 Female 44% Sex Ratio: 957

16 History and Betul Bazar town came There are no protected or One of the most conspicuous culture and into existence first but notable historical, cultural or sites of Sarni is tourism couldn’t develop due to tourism places in the town. a Shiva temple overlooking the local farmer’s the town from Mathardev resistance for railway line peak, which is the highest across the town. Hence, point, approximately 3,500 ft Betul was opted for rail (1,100 m) (from sea level), link in the district among neighboring hills of which caused faster Satpura ranges. The peak as development due to well as the temple are named increase in trade and after a legendary tribal chief commerce. It has named Mathardev. The become a Mandi town. legendary chief commands strong following among the local and neighboring population.

48

C. Subproject Site Environmental Features

Table 5: Site Environmental Features of Betul-Bazar Components Location Site Photograph Raw water sump cum RW Sump having pump house Diameter - 4.0 m and Height 4.5 m and Pump House 5.0 m High over RW Sump is proposed store the raw water after trapping the raw water feeder mains for Betul city. The water will be pumped to proposed STP. The land is vacant and under custody of Revenue department. Raw water rising mains Raw water rising mains (5500m length and is proposed from sump 150mm diameter) cum pump house to WTP. The rising mains will be laid aling RoW of road. The road is under the custodian of PWD. There are no tress in the alignment. There is agricultural area on both sides of road. Water Treatment Plant Water treatment plant is constructed at Khasra No – 84/1 in Ward No – 1 on Betul Road. The ownership of land is verified and is in possession of Revenue Department, Govt. of Madhya Pradesh and considered land is ensured for the purposed of water supply scheme. The land has no any environmental and ecological sensitive features.

49

Clear water feeder Clear water feeder mains mains (total length are proposed to rise the 1275 m of dia 100mm water from WTP to and 150mm OHTs. The clear water feeder mains will be laid along the RoW of road. The roads are under the custody of Nagar Parishad.There is residential area on both sides of road. Over Head Tank An overhead tank of 200 KL is proposed to be constructed in Ward No 8 at Khasra No 475. The land is of revenue department and has no any environmental and ecological sensitive features. Site is currently vacant.There is agricultural land adjacent to proposed structure.

Distribution network Distribution network are (Total length is 16157 proposed to convey the and diameter is 75mm water from OHTs to to 200mm. households. The clear water feeder mains will be laid along the RoW of road. The roads are under the custody of Nagar Parishad.

50

Table 6: Site Environmental Features Amla town Component Location Site Photograph Anicut and Intake well will be built in Bel River, Intake well under the control of Water Resources Department, GoMP. At proposed site, the tree cutting activity is also not involved during construction.

Water Treatment 3.60 MLD WTP site is located near plant and the bank of Bel river and CWS Construction of Clear water sump well and pump house having capacity for supplying 3.40 MLD clear water. The site is proposed on Govt. land. There is no involvement of forest land. No tree cutting is required.

51

Transmission Transmission pipelines will be mostly Line laid along the main roads. Pipes will be laid underground.

Pipes will be laid along the roads/streets in the towns within the road right of way (ROW). In wider roads pipes/sewers will be laid in the road shoulder, and in narrow roads, where there is no space, pipes/sewers will be laid in the road carriage. There is residential area on both sides of road.

Proposed OHT with capacities 200 KL at Krishi OHT Mandi

52

Table 7: Site Environmental Features of Sarni Town Satpura Reservoir Satpura reservoir was constructed in 1967. Catchment area of the dam is 213.58 Sq. Miles. Total length of the dam 1685 feet and height of the dam is 110 feet.

Intake well Intake well is proposed near Satpura reservoir. The land is under ownership of WRD. Diameter and height of proposed intake well is 8.00 m & 15.50 m respectively.

Raw water rising mains The raw water rising mains is proposed from (Length 6700m and dia intake well to water 500m) treatment plant. The rising mains will be laid

aling RoW of road. The road is under the custodian of PWD.

Water Treatment Plant A WTP is proposed at Pathakheda near existing WCL water treatment plant in ward-28. The ownership of the land is with Forest Department (WCL). There is no any tree in the proposed premises. The land is vacant and Khasra no. is 341.

53

Clear water feeder Clear water feeder mains mains are proposed to rise the water from WTP to OHTs. (total length of 5000m The clear water feeder and diameter of 150mm, mains will be laid along 400mm and 250mm) the RoW of road. The roads are under the custody of Nagar Parishad, MPPGCL and WCL. There is agricultural land adjacent to structure,

1500 KL OHT An overhead tank of 1500 KL is proposed in Ward no – 28, The land ownership is with MPPGCL (Madhya Pradesh). There is no specific environmental feature at site.

1500 KL OHT An overhead tank of 1500 KL is proposed in Ward no – 7, near existing 2000 KL OHT. The land ownership is with MPPGCL (Madhya Pradesh). There is no specific environmental feature at site. Khasra number of the land is 1. There is agricultural land adjacent to structure,

54

1000 KL OHT An overhead tank of 1000 KL capacity is proposed in Ward no – 15, near Gayatri Mandir at Pathakheda. The land is under custody of Forest (WCL). There is no specific environmental feature at site. Khasra number of land is Comp No. : 345. There is agricultural land adjacent to structure,

1500 KL OHT An overhead tank of 1500 KL OHT is proposed in Ward no – 35, in WCL substation area at Shobhapur. The land is under the custody of WCL. There is no sensitive environmental and ecological feature in the campus. Khasra number of land is 150/2. There is agricultural land adjacent to structure,

300 KL OHT An OHT of 300 KL OHT is proposed in Ward no – 36, near existing WCL OHT at Bagdona. The land is under the custody of WCL. There is no sensitive environmental and ecological feature in

the campus. The Khasra number of land is 62/5. There is agricultural land adjacent to structure,

55

Distribution network of Distribution network are total length 101107m of proposed to convey the dia from 75mm to water from OHTs to 350mm households. The clear water feeder mains will be laid along the RoW of road. The roads are under the custody of Nagar Parishad,

MPPGCL and WCL. There is residential area on both sides of road.

56

Figure 11: Project WSS Component of Betul Bazar on Toposheet

57

Figure 12: Project WSS Component of Betul Bazar on Toposheet.

58

Figure 13: Survey of India Toposheet showing proposed Amla Subproject Environs

59

Figure 14: Proposed WSS components of Sarni Town on the toposheet

60

VI ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

A. INTRODUCTION 43. Potential environmental impacts of the proposed infrastructure components arepresented in this section. Measures to minimize/mitigate negative impacts, if any, are recommended along with the agency responsible for implementation. Monitoring actions to be conducted during the implementation phase is also recommended.

44. Screening of potential environmental impacts are categorized into four categories considering subproject phases: location impacts and design impacts (pre-construction phase), construction phase impacts and operations and maintenance phase impacts.

a. Location impacts include impacts associated with site selection and include loss of on-site biophysical array and encroachment either directly or indirectly on adjacent environments. It also includes impacts on people who will lose their livelihood or any other structures by the development of that site. b. Design impacts include impacts arising from Investment Program design, including technology used, scale of operation/throughput, waste production, discharge specifications, pollution sources and ancillary services. c. Construction impacts include impacts caused by site clearing, earthworks, machinery, vehicles and workers. Construction site impacts include erosion, dust, noise, traffic congestion and waste production. d. O&M impacts include impacts arising from the operation and maintenance activities of the infrastructure facility. These include routine management of operational waste streams, and occupational health and safety issues.

45. Screening of environmental impacts has been based on the impact magnitude (negligible/moderate/severe – in the order of increasing degree) and impact duration (temporary/permanent).

46. This section of the IEE reviews possible project-related impacts, in order to identify issues requiring further attention and screen out issues of no relevance. ADB SPS (2009) require that impacts and risks will be analyzed during pre-construction, construction, and operational stages in the context of the project’s area of influence.

47.The ADB Rapid Environmental Assessment Checklist in http://www.adb.org/documents/guidelines/environmental_assessment/eaguidelines002.aspis used to screen project for environmental impacts and to determine the scope of the IEE.

48. In the case of this project (i) most of the individual elements are relatively small and involve straightforward construction and operation, so impacts will be mainly localized and not greatly significant;(ii) proposed water abstraction from the sources is very small compared to overall water availability, and necessary water allocations are being made from Water Resources Department(iii) most of the predicted impacts are associated with the construction process, and are produced because that process is invasive, involving excavation and earth movements; and some works are located in the reservoir and (iv) being mostly located in an urban area, will not cause direct impact on biodiversity values. The project will be in properties held by the local government and access to the project location is through public rights-of-way and existing roads hence, land acquisition and encroachment on private property will not occur.

61

B. PRE-CONSTRUCTIONIMPACTS–DESIGN &LOCATION 49. Design of the Proposed Components. Technical design of the (i) intake facilities, (ii) water treatment plant; (iii) raw water and clear water mains, (iv) storage reservoirs, and (v) distribution network, connections, flow meters, etc., follows the relevant national planning and design guidelines, focusing on providing a robust system which is easy to operate, sustainable, efficient and economically viable. Besides, the project also included the following environmental considerations:

(i)Discontinuation ofcurrentunsustainablegroundwater sourceandcreatinga newcomprehensive watersupplysystembasedon a nearestsurfacewater source

(ii) Recoveringwash water from treatment process.

(iii) Treatment andreuseof sludgefrom treatment process

(iv)Minimizingwaterlossesfrompipelinesbyperfect jointingandalignments usingappropriatetechniques(HDPE pipesupto150 mmdiajoined byelectro fusion couplers usingon-site electrofusion welding,andall higherdia pipes byon site butt welding) (v) Minimizingoverall resource usebycombining bulkwater facilitiesfor towns. (vi)Designing theentire system tomaintainoptimalflowand terminal pressure, and optimizing the overall energyusage (vii) Reducing the incidenceofwaterbornediseasesbyproviding100% Population includingurban poorwith potable watersupplies (viii) Improve wateruse efficiencyand reducewaterwastage athousehold level by recordingandmonitoring thewaterusage,andchargingtheconsumers as perusage;dueconsideration tourbanpoor (ix) Minimize unaccountedforwater (UFW) lossesusing district metered area approach withflow meter and pressurelogging arrangementstoidentifyand rectifythe leaks,andunauthorized connections (x)Usinglow-noise and energyefficient pumpingsystems

50. Water Source Selection and SustainabilityAs the subproject towns are located far from each other there was no possibility of a combined source/ bulk water scheme. Therefore, independent water supply schemes are proposed for 4 towns separately based on the most feasible water source considering techno-economic and environmental considerations as elucidated below .

A. BETUL-BAZAR 51. Present water supply arrangements are not adequate and ground water source level is depleting day by day, therefore water scarcity conditions are arising. Water supply losses during transmission are also very high i.e. more than 46%, that leads to a high energy consumption and loss of ULB. Presently water will be supplied only for 45 min on alternate days.

52.Water Source: For the water supply of Betul Bazar town, water source studies done. There appears to be three optional sources: (i) Extracting Ground Water (ii) Sapana River (iii) Sapana Dam (iv) Tapti River – Tapping on Raw Water Rising Main of Betul WSS

62

53. Presently only 0.40MLD of water is being supplied through ground sources like 7 nos of tube wells, 28 nos of Hand Pumps & 3 nos of open well.These entire sources are giving very less yield. Based on the available data the present tube wells may supply water to the town at the tune of maximum 0.24 MLD. Below data / graphs from the Central Ground Water Board, Ministry of Water Resources and The groundwater samples are being collected from each monitoring wells during the month of May every year. The quality of ground water in district is being described by the analysis of groundwater samples from 23 ground water monitoring wells. The analysis of water samples for year 2012 indicate that the electrical conductivity (EC) values were found in the range of 262 and 16700 us/cm at 250C. The nitrate in ground water of Betul district is varying between 1.3-156 mg/l. Nitrate more than 100mg/l was found in only one village namely Nimpani (145 mg/l). The higher concentration of NO3 may be due to excessive use of fertilized and localized pollution.

54. Sapna River and Sapna Dam. Sapana River is not a perennial river. A Sapana Dam was constructed on the Sapana River.This river flows mostly during the rainy season and remains dry almost 8 months of a year.There is no assurance to getting the 100% water demand of Betul Bazar town during the entire year..Since water quality test for deciding source to be taken as water source, it is proved to be good source based on the water sample test reports obtained from recognized PHED Laboratory, Bhopal .The basic parameters of quality of raw water are proved to be good since pH is 7.62 which is well within the permissible limit of 6.5 to 8.5 (said to Excellent Source), total Chlorides found is 10 mg/ltr which is around 50 mg/lit (said to Excellent Source) and Fluoride is 0.0 mg/ltr which is less than 1 mg/ltr (said to Excellent Source), Nitrates found is 1.0 mg/ltr which is much less than the permissible limitsof 45 mg/ltr (said to Excellent Source). Due to the non availability of water in Sapana Dam, it is not selected as source for Betul-Bazar WSS.

55. Other than these four options, there is not water body nearby the Betul Bazar town to consider as a water source for proposed Water Supply Scheme of town. A water supply scheme for Betul city is under construction. Tapti river is taken as water source in this scheme. The raw water feeder mains for Betul city will cross through Betul Bazar. So, trapping of this raw water rising mains of Betul city WSS is found economical for supplying water in Betul Bazar.

56. Tapti River is flowing from the south- west direction of the Betul Bazar and is approximately 25 km from the town. It is proposed to construct barrage on Tapti River on Betul – Amravati Road. The designed storage capacity of the weir will be 1.50 MCM. On the upstream to this weir i.e. 56 Kms, a dam near Parasdoh is under construction. Apart from this 5 MCM water shall be regulated from the dam to be constructed on upstream side of Tapti River near Parasdoh and will be available at proposed weir site. A commitment has been obtained to get 5 MCM water from Parasdoh Dam. Thus the total water availability at barge is 6.50 MCM.

57. The approximate catchment area of Tapti River upto the proposed weir is 800 Sq Km. The approximate runoff for average rainfall of 1132 mm works out 1000 Cumecs. The height of barge is being proposed as 9.0 m, having foundation depth of 2.0 m and height above bed level 7.00 m with length of weir as 170 m.

58. After losses, 5 MCM water is available in the weir to be supplied to Betul. In this weir 1.10 MLD (for Ultimate Stage of Design) is allocated for Betul Bazar. For drawl of 14.30 MLD (Cumulative water demand of Betul and Betul Bazar) an Intake Well having diameter 6.00 m and height of 15.0 m shall be

63

constructed near proposed weir at Tapti River.Average Water Resource Potential is 14880 (MCM) and Utilizable Surface Water Resource 14500 (MCM)

59. Water Quantity Security:-For the Betul Bazar town, the demand of water supply for the year 2018, 2033 & 2048 are estimated to the tune of 0.95 MLD, 1.05 MLD & 1.10 MLD respectively. Thus maximum of 1.10 MLD intake form the source per annum i.e. 402 ML (0.40 MCM) of drawl of water is to be ensured. Annual average recoupment of water in the tank every year is around 6.50 MCM. While the recoupment of water during rainy season is 6.50 MCM which is 16 times than the annual water demand of Betul Bazar town.

60. The tapping location is in the reachable scratch from the core Betul Bazar town and located in Tehsil – Betul, Dist - Betul. The location is around 5.50 km away from Betul Bazar town. Hence Tapping raw water from tapti river has taken as water sustainable source for proposed water supply system.

Figure 15: Ground water TableBetul-Bazar

64

B. AMLA TOWN

69. Source Identification The design population of Amla for the year 2048 is 43,500. Presently Amla is getting 1.00 MLD water from Tube Wells & Well. In a longer period ground water sources cannot be considered dependable and economical for urban water supply. It is therefore proposed to supply water from the surface sources. For supplying potable water from the surface source, the various water sources in and around the project vicinity has been examined. Following are the possible source.

70. Sources available in the vicinity of project area

(a) Bel River: - Flowing in south east direction of the town. The is a sub tributary of Kanhan River which is a tributary of Weinganga River. The river is the approximately 5 km from the town. It is not a perennial source. Due to small catchment, flow creases by the end of March every year.In the absence of flow station on the banks of River, no flow data is available. The details of flow have been verified from the local residents. For drawing of 3.60 MLD raw water from the river, a storage structure shall be required having sufficient capacity for storing water for the period of 5 months in a year. Thus the storage capacity required shall be 0.90Mcum.

(b) The irrigation tanks at Sasundra Dam and Sapna Dam having capacity of 4.60 MCMand 16.90 MCM respectively. Looking to the irrigation area. The irrigation area (CCA) attached to Sasundra and Sapna Dam is 500Ha. And 2200Ha. respectively. The wastewater required for irrigation purposes is 3.80 MCM and 14.30 MCM. Thus looking to the water required for irrigation and the Full tank capacity the tanks cannot spare any water quantity for water supply of Amla.

(c) The perennial River like Narmada which is approximately 100 km from Amla. Looking to the large distance and high pumping, bringing water from Narmada will be not only very high in terms of Capex but also in Opex.

(d) Tapti is the most prominent river in the vicinity of project area and is approximately 50 kms from the town. The river is not perennial and some storage structure shall be required to be constructed for drawl of water for water supply to Amla.

(e) Machana River is approximately 20 km. The entire flow of the river is being tapped and used by Municipal Council Betul for water supply of Betul. Hence getting any additional water quantity for the water supply of Amla from Machana will not be possible.

71. Most Suitable source of water supply: Looking to the above, Bel River is most suitable dependable /sustainable surface source of water supply because of the water availability to Amla. Since the river is not perennial & the river flow crease by the month of February-March every year, it is proposed to construct a Barrage of 5.0 m height from average bed level near Lalawadi Road on Bel River for supplying water all the year round. For this reconnaissance survey is being carried out from 07/03/2016 to 11/03/2016 in the river. Looking to the banks and approachability, the most appropriate location for construction of barrage is near Lalawadi Road. The maximum capacity of barrage at FTL 714 m above MSL is coming as 0.88Mcum.

65

The catchment area upto the proposed weir site is 200 km2approximately. With the annual average rainfall of 1212.275 mm (Betul district) & taking coefficient of runoff as 0.20 (for average catchment and average rainfall, no continuous downpore), the yield at Barrage point is 48.48Mcum. Looking to the yield, the gross capacity of Barrage of 0.88Mcum is 100% assured.

72. Out of the available gross capacity of proposed Barrage on Bel River, taking 35-40% losses on account of evaporation, seepage and pilferage the net useful capacity shall be 0.54Mcum which will be sufficient for supplying water @ 70lpcd to the design population of Amla, for 150 days in a year

73. Source water sustainability and environmental considerations. In Amla, water is proposed to be sourced from the nearest Bel River. To ensure water availability during the no-flow period, a weir is proposed. Water quality is good. Therefore, no negative impacts envisaged on existing water uses or ecosystem. The catchment area upto the proposed weir site is 200 sqkms. With the annual average rainfall of 1212.275 mm & taking coefficient of runoff as 0.20, the yieldat weir point is 48.48 MCum. Looking to the yield, the gross capacity of weir of 0.88 MCum is assured. There is no storage structure on the downstream of the weir and the aquatic life is least in the river which results in no major negative impact on ecosystem and aquatic life. Its water quality report is given in table 8, which suggests that the water is according to the standard of drinking.

Table 8:Groundwater Quality Amla town (2016) Parameter Bel River Drinking water standards*

Temperature, oC 28 - Turbidity, NTU Turbid 5-10 Color, Hazen units Nil 5-25 pH 7.5 6.5-8.5 Total dissolved solids (mg/l) 500-2000 520 Total alkalinity (mg/l) 260 - Chlorides as Cl (mg/l) 40 250-1000 Total hardness as CaCO3 (mg/l) 300-600 240 Calcium (mg/l) 72 75-200 Magnesium (mg/l) 14.4 30-100 Iron (mg/l) Nil 0.3 – 1 Fluoride (mg/l) 0.21 1-1.5 Nitrate (mg/l) Nil 45 Sulphates (mg/l) Nil 200-400 Total Coliform / 100ml Nil 10 Thermo tolerant coliform / 100 ml Nil - Source: Sampling survey 5/10/ 2015 by design consultant Team; sample collected from Bel River (proposed weir site) * standards prescribe lower and higher values for parameters, except pH; lower value is the ‘desirable limit’ while higher value is the ‘permissible limit in the absence of alternate source’; there is only lower value for parameters which have no relaxation

66

74. This is a weir, with a height of just 6 m above the river bed level (same as depth of river banks), thus confining the submergence to river course itself. The main purpose of this weir is to recharge the riverbed, and not for direct abstraction from the storage, and will ensure adequate water availability to meet the demand of no-flow period (4-5) months in summer. There is no gauging station on the proposed river by the WRD, but after consultation with local people it is concluded that flow of river ceases in the month of December- January.

75. Impacts due to Weir on downstream users and ecosystem:There is one existing dam of Railways which is in abandoned stage. Its is approx 6000 m downstream from the proposed weir from Amla.Weir will be solid structure (built in RCC) and will have no arrangements to increase/decrease the height (such as operable gates) or release or hold water beyond/below the fixed dam height. Given very small storage, weir will be filled at the first monsoon flow itself, and will continue to be full throughout (as no abstraction, except for the evaporation and infiltration losses), and the water coming from the upstream will overflow freely. Therefore the change in flow regime due to this small dam will be negligible on downstream users and river eco system.The proposed impoundment, in fact, is likely to benefit the environment through groundwater recharge and propagating aquatic life. Water quality is suitable for drinking water after conventional treatment and disinfection, and there are no notable pollution sources. No negative impacts thus envisaged. If we talk about upstream, there is one weir which is 6.5 kms away from the proposed weir. Hence there is no encouragement of water from any weir present in upstream and downstream. It is a good location as it is easy approachable and the cross section of river is suitable for the construction of a weir.

67

Figure 16 ;Google map showing upstream and downstream area

68

Figure 17: Contour Survey of Bel River at the proposed Weir Location

69

C. SARNI

76. A new water supply scheme is needs to be implemented for population for the of 135100souls for a year 2048 (Ultimate Year of Design) considering 135 LPCD water supply and source as surface source to ensure adequate quantity, quality and desired pressure at doorstep of each household as per the Guidelines of MPUSIP. The design base year for the proposed WSS is taken as 2018, in which population is likely to be reached 95500 and water demand will be 16.30 MLD.

77. Selection of water source for the water supply of Sarni town, water source studies done. There appears to be three optional sources:

✓ Extracting Ground Water ✓ Satpura Reservoir ✓ Constructing Dam on Tawa River at Tiliyadoh

78. The groundwater level of Sarni town I depleted very rapidly. It reduces from 2m to 4m just from 2013 to 2014. The groundwater samples are being collected from each monitoring wells during the month of May every year by CGWB. The quality of ground water in district is being described by the analysis of groundwater samples from 23 ground water monitoring wells. The analysis of water samples for year 2012 indicate that, the electrical conductivity (EC) values were found in the range of 262 and 16700 us/cm at 25°C. The nitrate in ground water of Betul district is varying between 1.3-156 mg/l Nitrate more than 100 mg/l was found in only one village namely Nimpani (145 mg/l). The higher concentration of NO3 may be due to excessive use of fertilizer and localized pollution.Therefore it is not the suitable source.

79. Quality Assurance of Satpura Reservoir:Presently entire water supply of entire Sarni town is based on Satpura Reservoir. The quality of water is already assured since it is already being used as a water source. Still water sample from Satpura reservoir was collected and submitted in PHE Laboratory for testing purpose. Test report is found adequate for drinking water purpose. Water quality test of Satpura reservoir has been done as per drinking water standard and it was found that all the parameter comes under the permissible limit. The water analysis report of Satpura reservoir is given in Appendix – 12.

80. Water Quantity Security: For the Sarni town, the demand of water supply for the year 2018, 2033 & 2048 are estimated to the tune of 16.30 MLD, 19.70 MLD &23.10 MLD respectively. Thus maximum of 23.10 MLD intake form the source per annum i.e. 8431 ML (8.43 MCM) of drawl of water is to be ensured. Annual average recoupment of water in the tank every year is around 75.43 MCM. While the recoupment of water during rainy season is 75.43 MCM which is 10 times than the annual water demand of Sarni town.

81. Other than these three options, there is no water body present nearby vicinity of the Sarni town to consider as a water source for proposed Water Supply Scheme of town. Ground water level in Sarni is very low to supply the water in Town. Tawa river is generally dry in summer season, so found not adequate to as water source. For the proposed water supply scheme, Satpura Reservoir is found adequate for the water supply in Sarni town after analyzing all the tree water sources. The location of Satpura dam is in the reachable scratch from the core Sarni town and located in Tehsil – Sarni, Dist - Betul. The dam is around 7.00 km away from Sarni town. Satpura reservoir is found adequate source for Sarni Water Supply Scheme due to

70

its adequacy in terms of quality as well quantity. After water analysis of Satpura Reservoir, it is found that all the parameter is beyond the drinking water standard.

Figure 18: Ground water table Sarni

82. Use of Chlorine as disinfectant. It is proposed to use chlorine at WTP to disinfect the water prior to supply to consumers. There is invariably a safety risk when chlorine is handled. Although facilities are not located close to habitations, safety precautions are necessary to ensure the safety of workers and citizens. To avoid any risk, the chlorination facility will be provided with the following:

• Chlorine neutralization pit with a lime slurry feeder • Proper ventilation, lighting, entry and exit facilities • Facility for isolation in the event of major chlorine leakage • Personal protection and safety equipment for the operators in the chlorine plant • Provide training to the staff in safe handling and application of chlorine; this shall be included in the contract of Chlorinator supplier

71

• Supplier of Chlorinator equipment shall provide standard operating manual for safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Hindi Languages

72

83. Utilities Telephone lines, electric poles and wires, water lines within the proposed project locations may require to be shifted in few cases. To mitigate the adverse impacts due to relocation of the utilities, the contractor, in collaboration with ULBs will (i) identify the locations and operators of these utilities to prevent unnecessary disruption of services during construction phase; and (ii) instruct construction contractors to prepare a contingency plan to include actions to be done in case of unintentional interruption of services.

84. Site selection of construction work camps, stockpile areas, storage areas, and disposal areas: Priority is to locate these near the project location. However, if it is deemed necessary to locate elsewhere, sites to be considered will not promote instability and result in destruction of property, vegetation, irrigation, and drinking water supply systems. Residential areas will not be considered for setting up construction camps to protect the human environment (i.e., to curb accident risks, health risks due to air and water pollution and dust, and noise, and to prevent social conflicts, shortages of amenities, and crime). Extreme care will be taken to avoid disposals near forest areas, water bodies, or in areas which will inconvenience the community.

85. Site selection of sources of materials. Significant quantities of coarse aggregate and fine aggregate will be required for construction works. Requirement of gravel is limited. Contractor should procure these materials only from the quarries permitted/licensed by Mines and Geology Department. Contractor should, to the maximum extent possible, procure material from existing quarries, and creation of new quarry areas should be avoid as far as possible. It will be the construction contractor’s responsibility to verify the suitability of all material sources and to obtain the approval of Department of Mines & Geology and local revenue administrat.

C, CONSTRUCTION IMPACT

86. The construction work is expected not to cause major negative impacts, mainly because: (i) most of the activities will be on the built-up areas of towns and/or existing RoWs thus could be constructed without causing impacts to biodiversity; (ii) most of the sites are located on government-owned land which is not occupied or used for any other purpose; (iii) overall construction program will be relatively short and is expected to be completed in 24 months with activities to conducted by small teams and specifiedlocation so most impacts will be localized and short in duration; and (i) Most of the predicted impacts associated with the construction process are produced because the process is invasive, such as involving excavation. However, the routine nature of the impacts means that most can be easily mitigated and the impacts are clearly a result of the construction process rather than the design or location, as impacts will not occur if excavation or other ground disturbance is not involved.

73

87. As a result, there are several aspects of the environment which are not expected to be affected by the construction process and these can be screened out of the assessment at this stage as required by ADB procedure. These are shown in following Table8. These environmental factors are screened out presently but will be assessed again before starting the construction activities.

Table9: Environmental component to be affected Field Rationale Topography, Soils, and Geology Activities are not large enough to affect these features.

Climate Activities are not large enough to affect this feature. Air Quality Short-term production of dust is the only effect on atmosphere Groundwater Activities will not be large enough to affect these features

Flora and Fauna No rare or endangered species in the landfill site. Economic Development Activities are not large enough to permanently affect this feature. Land Use No change in land use.

Socio-economic Subproject site is located entirely on government- owned land so there is no need to acquire land from private owners

Commerce, Industry, and Agriculture Activities are not large enough to affect these features Population Activities are not large enough to affect this feature.

Health and education facilities Activities are not large enough to affect this feature.

88. Anticipated Impacts and Mitigation Measures Although construction of the subproject components involves quite simple techniques of civil work, the invasive nature of excavation and the subproject locations in the built-up areas of towns. Where there are a variety of human activities, will result to impacts to the environment and sensitive receptors such as residents, businesses, and the community in general. These anticipated impacts are temporary and for short duration. Physical impacts will be reduced by the method of working and scheduling of work, whereby the project components will be (i) constructed by small teams working at a time; (ii) any excavation done near sensitive area like school,religious places and house will be protected as per standard norms. (iii)Busy street and bazaar area will require night work. For night work Contractor will ensure lights not focusing on houses, (iv) Use of low noise generator. (v) Proper sinages and barricades. (vi)Prior noticed before construction work of a particular stretch to residences/shops etc. 74

89. Sources of Materials. Significant amount of gravel, sand, and cement will be requiredfor this subproject. The construction contractor will be required to: • Use quarry sites and sources permitted by government; • Verify suitability of all material sources and obtain approval of UAED and ULB; and • Submit to UAED on a monthly basis documentation of sources of materials.

90. Air Quality. It is most certain that work will be conducted during the dry season, so there is potential for creating dust from the excavation of dry soil, backfilling, transportation to disposal, and from the import and storage of sand/gravel for bedding. Emissions from construction vehicles, equipment, and machinery used for excavation and construction will also induce impacts on the air quality in the construction sites. Anticipated impacts include dusts and increase in concentration of vehicle-related pollutants such as carbon monoxide, sulfur oxides, particulate matter, nitrous oxides, and hydrocarbons) but temporary and during construction activities only. To mitigate the impacts, construction contractors will be required to: • Consult with PMU/PIU on the designated areas for stockpiling of clay, soils, gravel, and other construction materials; • Excavate the SRs foundations at the same time as the access roads (if needed) are built so that dug material is used immediately, avoiding the need to stockpile on site; • Damp down exposed soil and any stockpiled on site by spraying with water when necessary during dry weather; • Bring materials (aggregates) as and when required; • Use tarpaulins to cover sand and other loose material when transported by vehicles; • Fit all heavy equipment and machinery with air pollution control devices which are operating correctly; and • Clean wheels and undercarriage of vehicles prior to leaving construction site.

91. Landscape and Aesthetics. The construction work is likely to generate significant quantities of waste soil and debris. This activity will generate wood, metal and concrete debris. Indiscriminate disposal of the soil and waste may affect the local environment at the disposal location. These impacts are negative but short-term and reversible by mitigation measures. The construction contractor will be required to: • Prepare and implement Waste Management Plan; • Avoid stockpiling of excess excavated soils; • Avoid disposal of any debris and waste soils in the forest areas and in or near water bodies/rivers; • Coordinate with ULB for beneficial uses of excess excavated soils or immediately dispose to designated areas; • Recover wood, metal, used oil, and lubricants and reuse or remove from the sites; • Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas;

75

• Remove all wreckage, rubbish, or temporary structures which are no longer required; and • Request UAED/PMU to report in writing that the necessary environmental restoration work has been adequately performed before acceptance of work.

92. Accessibility. Transport infrastructure will be affected as in the narrower streets there is not enough space for excavated soil to be piled off the road. The road itself may also be excavated in places where there is no available land to locate pipes alongside. Traffic will therefore be disrupted, and in some very narrow streets the whole road may need to be closed for short periods. Potential impact is negative but short term and reversible by mitigation measures. The construction contractor will be required to:(i)Plan pipeline work in consultation with the traffic police; (ii) Conduct work during light traffic;(iii) Plan work such that trench excavation, pipe laying, and refilling including compacting, at a stretch is completed in a minimum possible time;(iv) Provide for immediate consolidation of backfilling material to desired compaction to avoid future settlement risk - this will allow immediate road restoration and therefore will minimize disturbance to the traffic movement;(v) Do not close the road completely, ensure that work is conducted onto edge of the road; allow traffic to move on one line;(vi) In unavoidable circumstances of road closure, provide alternative routes, and ensure that public is informed about such traffic diversions;(viii) At all work sites public information/caution boards shall be provided – information shall inter-alia include: project name, cost and schedule; executing agency and contractor details; nature and schedule of work at that road/locality; traffic diversion details, if any; entry restriction information; competent official’s name and contact for public complaints.

93. Socio-Economic – Income. Excavation will obstruct access to residences/commercial building. Disruption of access to commercial establishments may affect livelihood. Since many of the roads are narrow, construction activities may also obstruct traffic. The potential impacts are negative and moderate but short-term and temporary. The construction contractor will be required to: (i) Leave space for access between mounds of excavated soil; (ii) Provide wooden planks/footbridges for pedestrians and metal sheets for vehicles to allow access across trenches to premises where required;Consult affected businesspeople to inform them in advance when work will occur; 94. Socio-Economic – Employment. Manpower will be required during the 24 months construction stage. This can result to generation of contractual employment and increase in local revenue. Thus potential impact is positive and long-term. The construction contractor will be required to: • Employ at least 50% of the labour force, or to the maximum extent, local persons within the 2-km immediate area if manpower is available; and • Secure construction materials from local market.

95. Occupational Health and safety. Workers need to be mindful of the occupational 76

hazards which can arise from working in height and excavation works. Potential impacts are negative and long-term but reversible by mitigation measures. The construction contractor will be required to: (i) Develop and implement site-specific Health and safety (EHS) Plan which will include assures such as: (a) excluding public from the site; (b) ensuring all workers are provided with and use Personal Protective Equipment; (c) EHS Training for all site personnel; (d) documented procedures to be followed for all site activities; and (e) documentation of work-related accidents; (ii) Ensure that qualified first-aid can be provided at all times. Equipped first-aid stations shall be easily accessible throughout the site; (iii) Provide medical insurance coverage for workers; (iv) Secure all installations from unauthorized intrusion and accident risks; (v) Provide supplies of potable drinking water; (vi) Provide clean eating areas where workers are not exposed to hazardous or noxious substances; (vii) Provide EHS orientation training to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; (viii) Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; (ix) Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; (x) Ensure moving equipment is outfitted with audible back-up alarms; (xi) Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and (xii) Disallow worker exposure to noise level greater than 85 dBA for duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively.

96. Noise Levels. The construction and excavation activities will certainly generate noise and vibrations. The sensitive receptors are the general population in these areas. Noise will be for a short term (about 2-3 days at each location) thus impact is negative, short-term, and reversible by mitigation measures. The construction contractor will be required to:

• Plan activities in consultation with PMU/PIU so that activities with the greatest potential to generate noise are conducted during periods of the day which will result in least disturbance;

• Provide prior information to the local public about the work schedule; 77

• Require horns not be used unless it is necessary to warn other road users or animals of the vehicle’s approach; • Ensure that there are no old and sensitive buildings that may come under risk due to the use of pneumatic drills; if there is risk • Minimize noise from construction equipment by using vehicle silencers, fitting jackhammers with noise-reducing mufflers, and portable street barriers the sound impact to surrounding sensitive receptor; and • Maintain maximum sound levels not exceeding 80 decibels (dbA) when measured at a distance of 10 m or more from the vehicle/s.

D. Potential Environmental Impacts and Mitigation Measures: Operation And Maintenance Impacts

97. Operation and Maintenance of the water supply system will be carried out by Amla Nagar Parishad directly or through an external operator. During the system design life (15/30 years for mechanical/civil components) it shall not require major repairs or refurbishments and should operate with little maintenance beyond routine actions required to keep the equipment in working order. The stability and integrity of the system will be monitored periodically to detect any problems and allow remedial action if required. Any repairs will be small-scale involving manual, temporary, and short-term works involving regular checking and recording of performance for signs of deterioration, servicing and replacement of parts.

98. Recurrence of pipe bursting and leakage problems can be manage by the leak detection and water auditing surveys. The ULB will be required to ensure that the leak detection and rectification time is minimized.

99. Water treatment process will generate sludge from sedimentation of particulate matter in raw water, flocculated and precipitated material resulting from chemical coagulation, residuals of excess chemical dosage, plankton etc; and waste from rinsing and back washing of filter media containing debris, chemical precipitates, straining of organic debris and plankton. Following are included in the subproject design to dispose the sludge and back wash:

100. Provision for recirculation system for filter backwash water from filter beds will be sent to a storage tank, and after allowing adequate time for settlement of solids, clarified water will be pumped to WTP inlet. This arrangement will avoid pollution and also minimize wastage of water.

101. Accumulated sludge from Tube Settler, filter backwash etc., will be disposed-off at sludge drying beds for natural drying. Dried sludge will be disposed off in a land fill or used as soil conditioner if it is suitable.

102. Project benefitDuring the construction phase, there are likely to be positive impacts through employment generation, increase in local revenue from the project activities. During 78

the operation phase also, there is potential for employment generation, though limited, as the improved and expanded water infrastructure requires additional workforce.

103. The citizens of Betul-Bazar, Amla and Sarni will be the major beneficiaries of the improved water supply system, as they will be provided with a constant supply of better quality water, piped into their homes at an appropriate pressure. The project will improve the over-all health condition of the towns as water borne diseases will be reduced, so people should spend less on healthcare and lose fewer working days due to illness, so their economic status should also improve, as well as their overall health. This should also improve the environment of these areas, should deliver major improvements in individual and community health and well-being.

79

VII.PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

A. OVERVIEW

104. The active participation of stakeholders including local community, NGOs, and the media in all stages of project preparation and implementation is essential for successful implementation of the project. It will ensure that the subprojects are designed, constructed, and operated with utmost consideration to local needs, ensures community acceptance, and will bring maximum benefits to the people. Public consultation and information disclosure is a must as per the ADB policy.

105. Most of the main stakeholders have already been identified and consulted during preparation of this IEE, and any others that are identified during project implementation will be brought into the process in the future. Primary stakeholders of the subproject are: residents, shopkeepers and businesspeople who live and work alongside the roads in which network improvements will be provided and near sites where facilities will be built (WTP and water tanks), and government and utility agencies responsible for provision of services in Sarni, (Forest Department, and Madhya Pradesh Pollution Control Board). Secondary stakeholder are: NGOs and CBOs working in the area, community representatives, beneficiary community in general, government agencies, the executing and implementing agencies (UAED, PMU and PIUs), Government of India and the ADB.

106. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

B. PUBLIC CONSULTATION 107. The public consultation and disclosure program is a continuous process throughout the project implementation, including project planning, design and construction.

108. Consultation during ProjectPreparation:Institutional consultations were conducted with the Governmental Departments such as PMU, Pollution Control Board, Public Health Engineering Department, Water Resourced Department, ULB and Forest Department etc. The project proposal is formulated in consultation with ULBs and suit the requirements of the ULBs.

109. Focus-group discussions with affected persons and other stakeholders were conducted to learn their views and concerns. A socio economic household survey has been conducted in the town, covering sample households, to understand the household characteristics, health status, and the infrastructure service levels, and also the demand for infrastructure services. General public and the people residing along the 80

project activity areas were also consulted during visits to the project sites. Details of stakeholder meeting is given in Appendix-1

110. It was observed that people are willing to extend their cooperation as the proposed activities are proposed to enhance the infrastructure service levels and the living standard of the public. The public expressed their concern regarding the nuisance and disturbance (dust, road closure and traffic management activities).

111. Consultation duringconstruction:P r i o r to start of construction, ULB and PIU with the assistance of PDMC will conduct information dissemination sessions at various places and solicit the help of the local community, leaders/prominent for the project work. At each ward/neighborhood level, focus group meetings will be conducted to discuss and plan construction work with local communities to reduce disturbance and other impacts.

112. A constant communication will be established with the affected communities to redress the environmental issues likely to surface during construction phases and also regarding the grievance redress mechanism. ULB/PIU and PDMC will organize public meetings and will appraise the communities about the progress on the implementation of EMP. Meeting will also be organized at the potential hotspots/sensitive locations before and during the construction.

C. INFORMATION DISCLOSURE

113. Executive summary of the IEE will be translated in Hindi and made available at the offices of PMU, PIU, Nagar Parishad offices, and also displayed on their notice boards. Hard copies of the IEE will be accessible to citizens as a means to disclose the document and at the same time creating wider public awareness. Electronic version of the IEE in English and Executive Summary in Hindi will be placed in the official website of the UAED, PMU after approval of the IEE by Government and ADB. Stakeholders will also be made aware of grievance register and redress mechanism.

114. Public information campaigns to explain the project details to a wider population will be conducted. Public disclosure meetings will be conducted at key project stages to inform the public of progress and future plans. Prior to start of construction, the PMU/PIU will issue Notification on the start date of implementation in local newspapers A board showing the details of the project will be displayed at the construction site for the information of general public.

115. Local communities will be continuously consulted regarding location of construction camps, access and hauling routes and other likely disturbances during construction. The road closure together with the proposed detours will be communicated via advertising, pamphlets, radio broadcasts, road signage, etc. 81

VIII .GRIEVANCE READRESSMECHANISM

A. Project Specific Grievance Redress Mechanism

116. A program-specific grievance redress mechanism (GRM) shall be established to receive, evaluate, and facilitate the resolution of AP’s concerns, complaints, and grievances about the social and environmental performance at the level of the project. The following GRM provides a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project.

117. A common GRM will be in place for social, environmental, or any other grievances related to the project. The GRM will provide an accessible and trusted platform for receiving and facilitating resolution of affected persons’ grievances related to the program. The multi- tier GRM for the project is outlined below, each tier having time-bound schedules and with responsible persons identified to address grievances and seek appropriate persons’ advice at each stage, as required. ULB-wide public awareness campaigns will ensure that awareness on grievance redress procedures is generated through the campaign.

118. Who Can Complain A complaint may be brought by persons who are, or could be, “directly, indirectly, materially, and adversely” affected by the project. A complaint can be submitted on behalf of the affected person/people by a representative, provided that he or she identifies the affected person/people and includes evidence of the authority to act on their behalf.

119. What the Grievance/Complain Should Contain Any concerns pertaining to safeguard compliance - environment, involuntary resettlement, and indigenous people, design related issues, compensation, service delivery or any other issues or concerns related to the project. The complaint must contain name, date, address/contact details of the complainant, location of the problem area, along with the problem.

120. Where to File a Complaint Complainants will have the flexibility of conveying grievances/suggestions by dropping grievance redress/ suggestion forms in complaints/suggestion boxes to be installed by project at respective Nagar Parishad offices, PIU offices or by e-mail or by writing in a complaints register in the PIU offices or at construction site offices.

121. How to File a Complaint The application should be precise and specific. The application can be sent either by post or through electronic means or deliver personally. A sample grievance form is at Appendix 21.

82

(i) OfflineSystem- Theapplicationcanbe madeon theapplication formavailableat allaccessibleplaces(NPs/OfficeofPIUs/construction siteoffices). The application should have the nameandcompletepostal addressof the applicant. (ii) OnlineSystem-Grievancespertainingtotheimplementationoftheprojectcan also befiled online at thewebsite ofUAHD/PMU orby e-mails.

122. Documentation: Documentation of the complaints is important and must contain name of the complainant, date of receipt of the complaint, address/contact details of the person, location of the problem area, and how the problem was resolved. PMU with the support of PIU will have the overall responsibility for timely grievance redress, and for registration of grievances, related disclosure, and communication with the aggrieved party. All the documents made available to the public at the community level (at ward offices) and will include information on the contact number, address and contact person for registering grievances, and will be disseminated throughout the project area by the PIU.

123. Grievance/problem redress through participatory process: Efforts must be made by the PIU with the support of safeguard consultants to resolve problems amicably, conflicts through participatory process with the community and the Nagar Parishads. In case of grievances that are immediate and urgent in the perception of the complainant, the Contractor, and supervision personnel from the PIU will provide the most easily accessible or first level of contact for the quick resolution of grievances. Contact phone numbers and names of the concerned staff and contractors, will be posted at all construction sites at visible locations.

124. Following process will be followed:

(i) 1stlevelgrievance: Incaseofgrievancesthatareimmediateandurgentinthe perceptionof the complainant,PMCsupervisingstaffwilldirect the contractorto and ensuresthat itis resolved. Ifthegrievance is notunder thecontractor scope, butundertheprogram, PMC (fieldoffice) will resolve thisissue. All thegrievances should be resolved within 3daysof receiptof a complaint/grievance.The complaints/grievances received in the CM helpline that are related to MPUSIP will be referred to project GRM at this first level. CM helpline staff will be included in the GRM training so that they can identify the related grievances and forward to this project GRM.

(ii) 2ndlevelgrievance: Allgrievancesthatcannot beredressedatfirstlevelwithin3 dayswillbebroughtto thenoticeofPIUand PMCAssistantEnvironmental Specialist. PIUwillreviewthegrievanceandactappropriatelytoresolveitwithin 10 daysofreceipt.

83

(iii) 3rdlevelgrievance: Allthegrievancesthatarenotaddressedat2ndlevelbyPIU withinin10daysofreceiptwillbebroughtto the noticeofnoticeofthe Grievance ReaddressedCommittee(GRC). GRCwillmeettwiceamonthanddeterminethe meritofeach grievancebroughtto thecommittee. The GRCwillresolvethe grievancewithin1monthofreceivingthecomplaint.Alldecisionstakenbythe GRC will be communicated tocomplainantbytheNodal Officer.

125. In case of any inter-departmental or inter-jurisdictional coordination required for resolution of specific grievances, the PIU will refer the matter directly to the PMU for state-level or inter-departmental coordination and resolution, instead of the town- level GRC .The project GRM notwithstanding, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. Alternatively, if the grievance is related to land acquisition, resettlement & rehabilitation4, the APs can approach the Land Acquisition, Rehabilitation and Resettlement Authority (LARRA) of Madhya Pradesh, established under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation, and Resettlement Act, 2013.

126. Record-keeping: PIU will keep records of grievance received, corrective actions taken and final outcome. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PIU office, ULB offices, and on the web.

------

7 Grievance redress committee (GRC) will be formed at town-level with members composed of: ULB Chairperson, ULB CMO, Environmental Specialist of PMC, PIU Dy.PM and PIU Community Development Officer. In case of any complaints by IP or members of scheduled tribes, the PIU will include as special member, a representative of an independent local NGO involved in tribal welfare. Special invitees to hearing of IP complaints will include two representatives from affected IP community and the project IP NGO, if appointed for IPP implementation. 8 the Authority admits grievance only with reference to the LA and R&R issues under the new Act

84

IX. ENVIRONMENTAL MANAGEMENT PLAN

A. Environmental Management Plan

127. An environmental management plan (EMP) has been developed to provide mitigation measures to reduce all negative impacts to acceptable levels.

128. The EMP will guide the environmentally-sound construction of the subproject and ensure efficient lines of communication between MPUDC, project management unit (PMU), project implementing unit (PIU), consultants and contractors. The EMP will (i) ensure that the activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active, feasible and practical working tool to enable the measurement and monitoring of environmental performance on site; (ii) guide and control the implementation of findings and recommendations of the environmental assessment conducted for the subproject; (iii) detail specific actions deemed necessary to assist in mitigating the environmental impact of the subproject; and (iv) ensure that safety recommendations are complied with. The EMP includes a monitoring program to measure the environmental condition and effectiveness of implementation of the mitigation measures. It will include observations on- and off-site, document checks, and interviews with workers and beneficiaries

129. The contractor will be required to submit to PIU, for review and approval, a site environmental plan (SEP) including (i) proposed sites/locations for construction work camps, storage areas, hauling roads, lay down areas, disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following the approved EMP; (iii) monitoring program as per SEP; and (iv) budget for SEP implementation. No works are allowed to commence prior to approval of SEP.

130. A copy of the EMP/approved SEP will be kept on site during the construction period at all times. The EMP included in the bid and contract documents. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the approved SEP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and SEP. The contractor shall allocate budget for compliance with these SEP measures, requirements and actions.

130. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring.

131. The purpose of the environmental management plan (EMP) is to: ensure that the activities are undertaken in a responsible, non-detrimental manner following the measures and recommendations of the environmental assessment conducted for the project, monitor and report the on-site environmental performance; and to ensure that safety recommendations are complied with.

133. A copy of the EMP must be kept at work sites at all times. This EMP will be included in 85

the bid documents and will be further reviewed and updated during implementation. The EMP will be made binding on all contractors operating on the site and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document constitutes a failure in compliance.

134. For civil works, the contractor will be required to (i) carry out all of the mitigation and monitoring measures set forth in the EMP; and (ii) implement any corrective or preventative actions set out in safeguards monitoring reports that the employer will prepare from time to time to monitor implementation of this IEE and EMP. The contractor shall allocate budget for compliance with these EMP measures, requirements and actions.

135. The following tables show the potential environmental impacts, proposed mitigation measures and responsible agencies for implementation and monitoring

86

Table10:DesignStageEnvironmentalManagementPlan Responsible Cost and Area Anticipate Mitigation Measures Agency for Source of d Impact Implementation Funds

Impact • Discontinuation of current unsustainable Project Design due to groundwater source and creating new These Costs of water site water supply system based on a nearest measures are supply selection surface water sources (Tapti river for already included for Betulbazar, Bel river for Amla town also system in the propose Satpura reservoir for sarni ) preliminary d • Recovering wash water from treatment structure process designs. • Treatment and reuse of sludge from

treatment process • Minimizing water losses from pipelines by DBO Contractor perfect jointing and alignments using (DBOC)to appropriate techniques (HDPE pipes up to 150 mm dia joined by electro fusion follow, enhance couplers using on-site electro fusion where possible. welding, and all higher dia pipes by on site butt welding) • Designing the entire system to maintain optimal flow and terminal pressure, and PMU to ensure optimising the overall energy usage compliance. • Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies • Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage; due consideration to urban poor • Minimize unaccounted for water (UFW) losses using district metered area approach with flow meter and pressure logging arrangements to identify and rectify the leaks, and unauthorized connections • Using low-noise and energy efficient pumping systems.

87

Water Project • Obtain permission from Water resources PMU & No costs; scope of abstracti sustainability department, GoMP respective IA on from & water use o Bel river for Amla town-permission / Nagar • Satpura conflicts water allocation for water abstraction Parishads • Reservo from dams and construction of (process ir for intakes. already Sarni initiated) Town • Waste Environment Obtain consent from MPPCB for WTPs PMU / Nagar No costs; scope of generatio al pollution atBetulbazar Amla and sarni prior to start of Parishad; IA & DB n from construction. DBOC to WTP prepare operation application, and s assist as required

Chlorine Chlorine Provide the following measure at the chlorine These Project usage as handling & application unit: measures are Costs disinfecta application (i) Chlorine neutralization pit with a lime slurry already included nt at WTP risk feeder – in the and ESR health & (ii) Proper ventilation, lighting, entry and exit safety risk facilities preliminary to workers (iii) Facility for isolation in the event of major designs. and chlorine leakage general (iv) Personal protection and safety equipment public for the operators in the chlorine plant (v) Provide training to the staff in safe DBOC to follow, handling and application of chlorine; this shall enhance where be included in the contract of Chlorinator possible. supplier (vi) Supplier of Chlorinator equipment shall PMU to ensure provide standard operating manual for safe compliance. operation and as well as maintenance and repairs; preferably these shall beprovided both in English and Hindi Languages

88

Table11:EnvironmentalManagement PlanofAnticipatedImpactsduringPre-Construction Field Anticipated Mitigation Measures Responsible Cost and Impact for Source of Implementation Funds

EMP Unsatisfactory • Appoint EHS DBO contractor Cost for Implementation compliance to supervisor and implementation & reporting EMP designate 1 EHS of mitigation coordinator (among measures the technical staff) in responsibility each town • Ensure that all pre- of contractor. construction activities are complete prior to start of construction work • Ensure timely submission of monitoring reports Utilities Damage/ • Identify and include DBOCwith PIU Project costs – disturbance to locations of utilities collaboration. general telephone in the detailed construction lines, electric designs/drawings to PMU to ensure practice prevent unnecessary lines, water compliance disruption of lines in project services area • Prepare a contingency plan to include actions to be taken in case of unintentional interruption of services. Construction Disturbance / • No construction DBOC with PIU Project costs – works near damage to material collaboration. general forest areas forest areas, storage/ancillary construction wildlife works shall be practice conducted in the forest area; this shall PIU/ PMU to be limited to actual ensure construction area compliance and the access roads • No labour camps shall be located near forests (maintain minimum 1km 89

Field Anticipated Mitigation Measures Responsible Cost and Impact for Source of Implementation Funds

buffer) • Limit the work to daylight hours only; no work after sunset • No workers /personnel shall enter forest areas; it is the DBOC responsibility to take necessary precautions & prevent workers removing/damaging trees/vegetation, hunting animals • Create awareness among workers on environment & safety • No high noisy works shall be conducted • Barricade the construction area properly so that no wild animals entre the work area Construction Degradation of • Schedule the works DBOC to follow Project costs – works in dam water quality – during summer general construction where there is construction work at Dam no/low water at the practice location PIU/ PMU to • Select a construction ensure methodology that is compliance least disturbing, and appropriate for the in-situ soil condition, and able to complete the construction work prior to onset of monsoon • Erect temporary barriers, if work is constructed in water, to form enclosed construction area 90

Field Anticipated Mitigation Measures Responsible Cost and Impact for Source of Implementation Funds

with least disturbance • Allow adequate time to settle the distributed solids to prior to pumping out water; only clear/clarified water shall be pumped back into the reservoir; any silt laden water should be pumped to a silt pond • Avoid/minimize use of fuels, chemicals and lubricants; ensure no spillage Construction Conflicts with • Prioritize barren, DBOCto identify Part of project work camps, local waste,infertile, locations costs stockpile community; vacant lands within following the areas, storage disruption to the area, criteria • Shall not be located areasand traffic flow and in productive waste disposal sensitive agricultural lands, areas receptors water bodies, natural PIU to ensure drainage channels, compliance and flood plains & approve groundwater recharge areas, forests, vegetative lands, etc. • Locate at sites that will not promote instability, flooding and result in destruction of natural drainage, vegetation, irrigation, & drinking water supply; • For private lands, obtain land owner’s (not lessees) written consent; indicate the 91

Field Anticipated Mitigation Measures Responsible Cost and Impact for Source of Implementation Funds

requirement for reinstatement to original • Site should have a minimum buffer of 0.5 – 1 km from all socially, environmentally sensitive areas (eg., residential, socio- cultural areas&water bodies (0.5 km), forests (1km), etc.,) • Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community. • Document site’s pre- project conditions Sources of Extraction of • Obtain material only DBOC to Part of project Materials materials can existing borrow identify sources costs disrupt natural sites/quarries that have all land contours already permitted by permits, if the Department of and vegetation required, obtain Mines and Geology; resulting in • If new quarries permits, and accelerated sites/quarries are submit to PIU erosion, necessary, disturbance in contractor shall be obtain all necessary natural PIU to check drainage permissions as per the law in force. and approve patterns, • Contractor to obtain ponding and construction water logging, materials only after and water written permission / pollution. approval of PIU for respective sources • Maintain a construction material register at the site Consents, Failure to • Obtain all necessary PMU / PIU to Part of project consents, permits, 92

Field Anticipated Mitigation Measures Responsible Cost and Impact for Source of Implementation Funds permits, obtain clearance, NOCs, obtain project costs clearances, necessary etc required for the clearances; NOCs, etc. consents, project prior to DBOC to award of contact or permits, provide start of civil works, NOCs, etc. as necessary. necessary can result to • Include in detailed assistance design designs, drawings revisions and documents all and/or regulatory conditions DBOCto obtain stoppage of and provisions, where required construction works • Contractor to identify permits & & obtain all necessary PIU to ensure approvals, including in compliance with labour laws, before start of construction; • Contractor to acknowledge in writing to PIU and provide copies of all obtained permits, clearance, NOCs, etc. Asbestos Health risk • Obtain details from DBOC in Part of project Cement Pipes due to PHED/NPson coordination costs exposure to location with PIU and asbestos ofunderground AC ULB pipes materials • Locate the new piper carefully to avoid encountering AC pipes • Leave the AC pipes undisturbed in the ground.

Table12:EnvironmentalManagementPlanofAnticipatedImpactsduring Construction 93

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

EMP Irreversible • Project manager and DBOC Cost of EMP Implementatio impact to the all key workers will be Implementatio n Training environment, required to undergo n Orientation workers, and training on EMP Training to implementation PMC community contractor is including spoils/waste Construction responsibility management, and Standard operating Environmental of PMU. procedures (SOP) for Specialists to construction works; occupational health conduct the and safety (OH&S), training Other costs core labor laws, responsibility applicable of contractor. environmental laws, etc. Air Quality Emissions • Control dust by water DBOContracto Cost for from sprinkling on exposed r implementation construction soil, stock stockpiled of mitigation vehicles, material on site measures • Barricade area, equipment, responsibility provide wind sheets and • Use tarpaulins to of contractor. machinery cover sand and other

used for loose material when transported by trucks; installation of Air quality pipelines • Clean wheels and monitoring undercarriage of haul resulting to costs are dusts and trucks prior to leaving construction site included in the increase in • Prevent entry of traffic, EMP costs of concentration public in construction project of vehicle- area related • Fit all heavy pollutants equipment, and such as machinery with air carbon pollution control devices which are monoxide, operating correctly; all sulfur oxides, the vehicle shall meet particulate the emission norms matter, and shall have valid pollution under control 94

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

nitrous (PUC) certificate oxides, and (Appendix 3) hydrocarbons. • Conduct air quality monitoring as per the monitoring plan

Surface water Mobilization • Avoid earthworks DBO Cost for quality of settled silt during the rainy Contractor implementation materials, and season of mitigation chemical • Avoid stockpiling of measures earth fill especially contamination responsibility during the monsoon from fuels and season unless of contractor. lubricants covered by tarpaulins during or plastic sheets; • Reuse excess spoils & installation of Water quality pipelines can materials in the monitoring contaminate construction as far a possible costs are nearby • Identify disposal sites included in the surface water prior to construction & EMP costs of quality. dispose construction project waste only at designated areas • Install temporary silt traps basins along the drainage leading to the water bodies; • Place storage areas for fuels and lubricants away from any drainage leading to water bodies; • Conduct surface quality inspection according to the Environmental Management Plan (EMP). Noise Levels Increase in • Conduct noise DBOContracto Cost for noise level generating activities r implementation due to earth- (eg, cc road cutting) of mitigation moving and during day time measures • Minimize noise from 95

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

excavation construction responsibility equipment, equipment (by using of contractor. and the vehicle silencers, fitting jackhammers transportation with noise-reducing of equipment, mufflers, and use materials, and portable street barriers people to minimise sound impact to surrounding sensitive receptor; • Maintain maximum sound level not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s. • Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity; • Consult local communities in advance to avoid working at sensitive times, such as religious and cultural festivals. Landscape Impacts due • Prepare and DBO Cost for and aesthetics to excess implement a Contractor implementation excavated Construction Waste of mitigation earth, excess Management measures Plan(Appendix 22) construction responsibility • Stockpiles, lubricants, materials, and fuels, and other of contractor. solid waste materials should be such as located away from removed steep slopes and concrete, water bodies; wood, • Avoid stockpiling any excess spoils; dispose packaging immediately to materials, designated areas 96

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

empty • Domestic solid waste containers, generated at spoils, oils, construction camps lubricants, and work sites shall be properly managed and other (collected, segregated, similar items. disposed properly); waste should not burned • Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposedthrough approved recyclers • Environmentallyrestor e the work sites to at least pre-project conditions; PIU to approve in writing that site is restored Ecological Loss of • Avoid removal of DBOContracto Cost for Resources – vegetation vegetation / tree r implementation Terrestrial and tree cutting of mitigation cover • If unavoidable, measures minimize as far as responsibility possible, and obtain tree-cutting permit of contractor.

Land use Environmenta • The impact due to Not applicable Not applicable l Issues due change in land use will to land use be negligible due to change this project.

Accessibility Traffic • Confine work areas DBO Cost for problems and along the roads to the Contractor implementation conflicts near minimum possible of mitigation project extent; all the measures activities, including locations and responsibility material & haul road waste/surplus soil of contractor. stocking should be confined to this area. Proper barricading 97

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

should be provided; avoid material/surplus soil stocking in congested areas – immediately remove from site/ or brought to the as and when required • Leave spaces for access between mounds of soil; • Provide walkways and metal sheets where required to maintain access across for people and vehicles; • Plan transportation routes so that heavy vehicles do not use narrow local roads, except in the immediate vicinity of delivery sites; • Schedule transport and hauling activities during non-peak hours; • Keep the site free from all unnecessary obstructions; • Drive vehicles in a considerate manner; • Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids • Prepare and implement Traffic Management Plan where required (template is provided in Appendix 23) • Notify affected area by public information 98

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

notices, providing sign boards informing nature and duration of construction works and contact numbers for concerns/complaints. • For works in very narrow roads o Inform the affected local population 1- week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Provide pedestrian access in all the locations until normalcy is restored. Provide wooden/metal planks over the open trenches at each house to maintain the access. Socio- Impede the • Do not obstruct DBO Cost for Economic – access of access; provide Contractor implementation Income. residents and temporary access, by of mitigation customers to leaving spaces in measures excavation, provide nearby shops responsibility walkways and metal sheets for people and of contractor. vehicles where necessary to continue business • Increase workforce in the areas with predominantly institutions, place of 99

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

worship, business establishment, hospitals, and schools; • Consult businesses and institutions regarding operating hours and factoring this in work schedules Socio- Generate • Employ local persons DBOContracto Cost for Economic – temporary in construction work if r implementation Employment employment manpower is available of mitigation and increase measures in local responsibility revenue of contractor.

Occupational Occupational • Comply with all DBOContracto Cost for Health and hazards national, state and r implementation Safety which can local core labor laws of mitigation arise during (see Appendix 6of this measures IEE) work responsibility • Implement site-specific occupational health of contractor. and safety (OH&S) measures, such as the following • Provided personal protective equipment (PPE) to workers(like helmet, gumboot, safety belt, gloves, nose musk and ear plugs), and ensure that they are used • Conduct OH&S training workers/staff • Do no employ ad-hoc work procedures, follow best & acceptable work practices • Document work- related accidents • Provide qualified & easily accessible first- 100

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

aid facilities all times at all sites • Secure all installations from unauthorized intrusion and accident risks; • Provide potable drinking water; • Provide clean eating areas where workers are not exposed to hazardous or noxious substances; • Provide H&S orientation training to all workers to ensure that they are apprised of the basic site rules of work at the site, PPEs, and preventing injuring to fellow workers; • Ensure that visitor/s do not enter hazard areas unescorted • Ensure the visibility of workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; • Ensure moving equipment is outfitted with audible back-up alarms; • Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and 101

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; and • Disallow worker exposure to noise level greater than 85 dBA for a duration of more than 8 hours per day without hearing protection. The use of hearing protection shall be enforced actively. Community Traffic • Plan routes to avoid DBOContracto Cost for Health and accidents and times of peak- r implementation Safety. vehicle pedestrian activities of mitigation collision with and high risk areas. measures • Prevent public entry in pedestrians responsibility to work areas through during barricading and of contractor. material and security guards waste • Maintain regularly the transportation vehicles and minimize potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn of on-going trenching activities. • In very narrow streets, conduct work section- wise (~100 m), and complete excavation, pipe laying and backfilling in minimum possible time (1 day preferably) 102

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

Work Camps Temporary air • Establish camps only DBOContracto Cost for and worksites and noise after site approval r implementation pollution from • Avoid cutting of trees/ of mitigation machine clearing bushes measures operation, • Provide adequate responsibility drinking water, water water for other uses, and of contractor. pollution from sanitation facilities storage and • Ensure conditions of use of fuels, livability at work oils, solvents, camps are maintained and lubricants at the highest standards possible at all times; • Prohibit employees Unsanitary from poaching wildlife and poor and cutting of trees for living firewood; • Train employees in the conditions for storage and handling workers of materials which can potentially cause soil contamination; • Recover used oil and lubricants and reuse or remove from the site; • Manage solid waste according to the preference hierarchy: reuse, recycling and disposal to designated areas; • Ensure unauthorized persons specially children are not allowed in any worksite Post- Damage due • Remove all spoils DBOContracto Cost for construction to debris, wreckage, rubbish, or r implementation clean-up spoils, excess temporary structures of mitigation construction (such as buildings, measures shelters, and latrines) materials responsibility which are no longer required of contractor. • All excavated roads 103

Field Anticipated Mitigation Measures Responsible Cost and Impact for Mitigation Source of Funds

shall be reinstated to original condition. • All disrupted utilities restored • All affected structures rehabilitated/compens ated • The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. • All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be topsoiled and regrassed • The contractor must arrange the cancellation of all temporary services. • Restore the work sites to pre-project conditions; PIU to approve in writing that site is restored

104

Table 13: Operation Stage Environmental Management Plan

Field Anticipated Mitigation Responsible Monitoring Cost and Impact Measures for of Source of Mitigation Mitigation Funds

Check for Loss of water, • Effective leak DBO PIU and Operating blockage and increased detection and Contractor respective costs leakage demand and water auditing Nagar problems inconvenience to reduce the Parishads water losses reducing the to consumers water losses & general public

Water Impacts on • Ensure Respective PMU in Operating contamination public health protection of Nagar coordination costs – raw water water source Parishads with WRD contamination quality, any entry of at source and wastewater treated water into the CCI DBO PIU and during pond at Contractor respective transmission Nayagaon Nagar should be checked Parishads • Contamination

of treated water during transmission and distribution should be prevented by quickly identifying, isolating and repairing the leak section. Develop a system of leak 105

Field Anticipated Mitigation Responsible Monitoring Cost and Impact Measures for of Source of Mitigation Mitigation Funds

detection and rectification. • Conduct regular monitoring of raw & treated water and ensure that water supplied at all times meets the drinking water standards (Appendix 24) Discharge the Pollution of • Backwash DBO PIU and Operating impurities and streams water will be Contractor respective costs other solids /drains recirculate so Nagar collected due no wastewater Parishads generated from to filtration WTPs and back • Maintain the wash mechanical parts as per the maintenance plan to avoid any hazards Sludge Land and • Collect the DBO PIU and Operating generation water sludge from Contractor respective costs pollution, WTP units, dry Nagar impacts on in sludge Parishads drying beds, health & and reuse / environment dispose safely as per the design Increased in Water • Sanitation Respective PMU To be sewage pollution, and facilities needs Nagar identified generation impacts on to be improved Parishads - public health at community respective level and at the and NPs town level to environment meet the increased sewage 106

Field Anticipated Mitigation Responsible Monitoring Cost and Impact Measures for of Source of Mitigation Mitigation Funds

demand Generation of Impacts on • Collect solid DBO PIU and Operating waste public health wastes and Contractor respective costs materials and dispose to Nagar environment approved Parishads disposal yards Occupational Health, social • Provide DBO PIU and Operating health and and economic appropriate Contractor respective costs safety impacts on the PPE to Nagar workers workers& Parishads training on its proper use • Use fall protection equipment when working at heights. • Maintain work areas to minimize slipping and tripping hazards. • Implement a training program for operators who work with chlorine regarding safe handling practices and emergency response procedures. • Prepare escape plans from areas where there might be a chlorine emission. • Install safety showers and

107

Field Anticipated Mitigation Responsible Monitoring Cost and Impact Measures for of Source of Mitigation Mitigation Funds

eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used. • Prohibit eating, smoking, and drinking except in designated areas.

Table 14: Construction Stage Environmental Monitoring Plan Monitoring Monitoring Monitoring Frequency Responsibility Cost & field location parameters Source of Funds

Construction All work sites Implementation Regularly as Supervising Part of TOR of disturbances, of dust control, required staff and PIU, PMC and nuisances, noise control, during safeguards PMU public & traffic construction; specialists worker management, & checklist to be safety, safety filled monthly measures. once Site inspection checklist to review implementation is appended at Appendix 25 Ambient air 6 locations • PM10, PM2.5 Once before DBO Cost for quality NO2, SO2, start of Contractor implementation CO construction of monitoring 2 locations in and then measures each town: (i) Quarterly responsibility at WTP site, (yearly 4- of (ii) distribution work site) times) during construction contractor (2 year period (54samples x 108

considered) 5000 per sample = INR 270,000)

Ambient 6locations • Day time and Once before DBO Cost for noise night time start of Contractor implementation noise levels construction of monitoring 2 locations in (24 hours) and then measures each town: (i) Quarterly responsibility at WTP site, (yearly 4- of (ii) distribution work site) times) during construction contractor (2 year period (54 samples x considered) 1500 per sample = INR 81,,000)

Surface 3 locations (down • pH, Oil & Once before DBO Cost for water quality Stream of work) grease, Cl, start of Contractor implementation F, NO3, TC, construction& of monitoring 3 locations (one monthly FC, measures lake/pond/stream Hardness, during responsibility in each town) Turbidity construction BOD, COD, (3 months of DO, Total period Alkalnity considered) in contractor river Once before (12 samples x start of 4000 per construction& sample = Quarterly 48,000) during (27samples x construction 4000 per (24) sample = 108,000)

Table15:Environmental Monitoring Plan ofAnticipatedImpactsduring Operation

Monitoring Monitoring Monitoring Frequency Responsibility Cost & field location parameters Source of Funds

Source water Near intake pH, Cl, F, NO3, TC, Yearly DBO O&M quality point at all FC, Hardness, twice (pre Contractor costs Turbidity ,COD, DO, & post 109

Monitoring Monitoring Monitoring Frequency Responsibility Cost & field location parameters Source of Funds

sources Total Alkalnity monsoon)

heavy metals & pesticides

Monitoring of Consumer pH, Nitrite, Nitrate, Monthly DBO O&M quality of end- random Turbidity BOD, Total once Contractor costs water sampling in Alkalnity, Total supplied to all zones coliform and Feacal consumers coliform

110

B. IMLEMENTATION ARRANGEMENT

132. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh will be the Executing Agency for the Program, responsible for management, coordination and execution of all activities funded under the loan. Implementing Agency will be the recently established Madhya Pradesh Urban Development Company (MPUDC), a wholly owned subsidiary of GoMP. A central Project Management Unit (PMU) attached to MPUDC will be responsible for implementing the MPUSIP. The PMU will be supported by Program Implementation Units (PIUs) with a flexibility to redeployment depending upon the implementation requirements.

133. The PMU and PIUs will be supported by several teams of Design Consultant inpreparation of preliminary engineering designs.

134. Water Resource Review Committee (WRRC) is constituted to undertake a thorough review of the source when recommended by the Design Consultant in regard to techno-economic feasibility and sustainability especially ensuring climate change resilience, and Technical Review Committee (TRC) to review and approve the preliminary designs developed by the Design Consultants.

135. Program Management Consultant (PMC) centrally located in PMU and with field teams located in PIUs shall be responsible for implementation of the Program. All infrastructure contracts will be procured through performance-based contracts (PBCs) and include build-operate (BO) framework. Based on the preliminary designs prepared by Design Consultants, the DBO (design-build-operate) Contractor will design, construct, commission and operate for 10 years, after which it will be transferred to the respective ULB.

136. Two Committees - an Empowered Committee cum Executive Committee and a Technical Clearance and Tender Committee have been constituted by the Government to be responsible for effective and timely implementation of the Program.

C. SAFEGUARDS COMPLIANCE RESPONSIBILITIES 137. At PMU, there will be two safeguard specialists: (i) Project Officer (Environment) and (ii) Social & Gender Officer, who will responsible for compliance with the environmental and social safeguards in program implementation. PO (Environment) will have overall responsibility in implementation of the investment program as per the Environmental Assessment & Review Framework (EARF) agreed between ADB and the government. At individual subproject level, PO will ensure that environmental assessment is conducted, and a project-specific is prepared and implemented, and the compliance, and corrective actions, if any are reported as required.

111

138. PMU Responsibilities:PO (Environment) will be supported by PDMC, which will be staffed with an Environmental Specialist, and Environmental Coordinators. Key tasks and responsibilities of the PO (Environment) for this subproject include the following:

139. Bidding stage (i) Priorto invitation ofbidsforcivilworkscontract,ensurethat ✓ WaterResourcesDepartment(WRD)permissionisobtainedforsourcingwater fromReservoirs ✓ Consent for establishment(CFE) is obtained fromMPPCBfor WTP construction (ii) Ensurethat EMPsareincludedin biddingdocumentsandcivilworkscontracts (iii) Ensurethatthebid/contractdocumentsincludespecificprovisionsrequiringcontractors to complywith all applicable laborlawsand corelaborstandardsincluding: ✓ Labourwelfaremeasuresand provision ofamenities ✓ prohibitionofchildlaborasdefined innationallegislation forconstructionand maintenanceactivities ✓ equal payfor equal workofequal value regardlessof gender,ethnicity,or caste ✓ elimination offorced labor ✓ Therequirementtodisseminateinformationon sexually transmitteddiseases, includingHIV/AIDS,toemployeesandlocalcommunitiessurroundingthe project sites. (iii) EnsurethatstaffrequiredforimplementationofEMP(EHSofficerforTownsis included in thebidrequirements (iv) Ensurethat EMP costis included in the project cost (v) Inthepre-bidmeeting,provideinsightintotheEMPmeasures,andoverallcompliance requirementstothebidders

140. Construction stage (i) Facilitateandensurethatallnecessaryenvironmentalclearances/permissions,including that ofcontractor’s are inplace prior to startof construction (ii) Organizeaninductioncourse forthetrainingofcontractors,preparingthemonEMP implementation,environmentalmonitoring,and ontakingimmediateactiontoremedy unexpectedadverseimpactsorineffectivemitigationmeasuresfoundduringthecourse ofimplementation. (iii) provideoversightonenvironmentalmanagementaspectsofsubprojectsandensure EMPsareimplementedbyPIU andcontractors (iv) Superviseandprovide guidance to thePIUstoproperlycarryoutthe environmental monitoring asper theEMP (v) Overseegrievanceredressmechanismtoaddressanygrievancesbroughtaboutina timelymanner;ensurethat recordsareproperlymaintained (vi) Consolidatemonthlyenvironmentalmonitoringreports fromPIUandsubmitsemi-annual monitoring reportstoADB (vii) Overseesiteclosurestoensurethatallwork/facilitysitesarerestoredproperlypriorto issuingworkcompletioncertificatetothecontractor 112

141. Operationstage Ensureandconsentforoperation(CFO)isobtainedfromMPPCBforWTPpriortostart ofoperation

142. PIU Responsibilities: PIU will be headed by a Project Manager and supported by PDMC. An Assistant Project Manager of PIU will be given additional responsibilities of safeguard tasks and will be designated as Assistant Environmental Officer (ASO). ASO will be supported by PDMC Environmental Specialist and Environmental Coordinator. Key tasks and responsibilities of the ASO for this subproject include the following: • Provide necessarysupport toPIU and Nagar Parishads in obtaining permissionfromWRD and MPPCB;liaisonwithPMU and regulatoryagencies • Overseeday-to-dayimplementationofEMPsbycontractors,includingcompliancewithall government rules andregulations, take necessaryactionforobtaining rightsofway • Overseeenvironmentalmonitoring bycontractors • Takecorrective actionswhen necessaryto ensure noenvironmental impacts • Submit monthly environmentalmonitoring reports toPMU • Conductcontinuouspublicconsultationand awareness • Addressanygrievancesbroughtaboutthroughthegrievanceredressmechanisminatimelymanner asper the EMP

Contractor’s responsibilities

(A) Bidding stage • Understandthe EMP requirementsandallocate necessaryresources(budget, staff, etc • Understand theregulatorycompliance requirementsrelatedtolabour welfare, safety, environmentetc., (B) Constructionstage: • Obtainallnecessarypermissions/approvals(labour,pollutioncontrol,quarries,rightof ways,etc.)priortostartofwork • Mobilize EHS officer. • Prepareand Submit: ✓ Construction wastemanagement (CWM). ✓ Trafficmanagement (TM)plan • Implement themitigation measuresas per the EMPincludingCWM&TMPlans • Conductenvironmentalmonitoring asper the EMP • UndertakeimmediateactionassuggestedbyPIU/PMU/PDMCtoremedyunexpected adverse impacts or ineffective mitigation measures found during the course of implementation • Submit monthlycompliance reportson EMP implementation • Actpromptly on publiccomplaintsandgrievances related toconstructionworkandredress in a timelymanner in coordination with PIU

D. Training Needs

113

144. The following Table 16presents the outline of capacity building program to ensure EMP implementation. The estimated cost IS Rs 275,000 (excluding trainings of contractors which will be part of EMP implementation cost during construction) to be covered by the project’s capacity building program. The detailed cost and specific modules will be customized for the available skill set after assessing the capabilities of the target participants and the requirements of the project by the ES of PDMC.

Table 16: Outline Capacity Building Program on EMP Implementation

Description Target Estimate Cost and Participants& (INR) Source of Venue Funds 1. Introduction and Sensitization to All staff and - Included in the Environmental Issues (1 day) consultants involved overall program - ADB Safeguards Policy Statement in the project cost - Government of India and Madhya Pradeshapplicable safeguard laws, At PMU, Bhopal regulations and policies including but (combined program not limited to core labor standards, for all subprojects) OH&S, etc. - Incorporation of EMP into the project design and contracts - Monitoring, reporting and corrective action planning 2. EMP implementation (1/2 day) All PIU staff, - Part of overall - EMP mitigation & monitoring measures contractor staff and program costs – -Roles and responsibilities consultants involved PMC will conduct - Public relations, - Consultations in the subproject at PIU office - Grievance redress towns Betulbazar, - Monitoring and corrective action amla and sarni. Part of scope of planning work of PMU, - Reporting and disclosure At PIU PIU, PMC & - Construction site standard operating DBOC procedures (SOP) - AC pipe protocol - Traffic management plan - Waste management plan - Site clean-up & restoration 3. Contractors Orientation to Workers Once before start of - Contractors cost (1/2 day) work, and thereafter - Environment, health and safety in regular briefing project construction every month once. Daily briefing on safety prior to start of work

All workers (including unskilled 114

Description Target Estimate Cost and Participants& (INR) Source of Venue Funds laborers)

E. Monitoring and Reporting

E. Immediately after mobilization and prior to commencement of the works, the contractor will submit a compliance report to PIU that all identified pre-construction mitigation measures as detailed in the EMP are undertaken. Contractor should confirm that the staff for EMP implementation (EHS & Archeological supervisors) is mobilized. PMU with the assistance of the PDMC will review the report and permit commencement of works.

F. During construction, results from internal monitoring by the contractor will be reflected in their monthly EMP implementation reports to the PIU. ASO will review and advise contractors for corrective actions if necessary. Quarterly report summarizing compliance and corrective measures taken will be PMC field team at PIU and submitted to PMU (Appendix 13). During operation, the contractor will conduct management and monitoring actions as per the operation stage EMP, and submit to PMU and ULB a quarterly report on EMP implementation and compliance.

G. Based on monthly & quarterly reports and measurements, PMU will draft, review, and submit to ADB, 6-monthly semi-annual Environmental Monitoring Report (EMR). Once concurrence from the ADB is received the report will be disclosed in the MPUDC and PMU websites.

H. ADB will review project performance against the MPUSIP commitments as agreed in the legal documents. The extent of ADB‟s monitoring and supervision activities will be commensurate with the project's risks and impacts. Monitoring and supervising of social and environmental safeguards will be integrated into the project performance management system

F. EMP Implementation Cost

145. Most of the mitigation measures require the contractors to adopt good site practice, which should be part of their normal procedures already, so there are unlikely to be major costs associated with compliance. The costs which are specific to EMP implementation and are not covered elsewhere in the projects are given below.The total costs are estimated at INR 2.73 million, which are to be covered by contractor costs.

115

Table17:Cost Estimates toImplementtheEMP

Particulars Stages Unit Total Rate Cost Costs Numb (INR) (INR) Covered er By A. Implementation staff 1 Environmental Design & pre Per 0.5 150,00 75,000 DBO Specialist construction month 0 Contract 1 EHS Supervisor Construction per 24 50,000 1,200,000 DBO month contract Subtotal (A) 1,275,000

B. Mitigation Measures 1 Consent for Pre Lump 150,000 Project establishments & construction sum costs consent for operation from MPPCB

2 Provision for tree Construction Per tree 100 1,000 100,000 DBO cutting & contract compensatory plantation measures 3 Traffic management at Construction Lump - - 500,000 DBO work sites sum – 3 contract (Pavement Markings, towns Channelizing Devices, Arrow Panels and Warning Lights) Subtotal (B) 750,000

C. Monitoring Measures 1 Air quality monitoring Construction / sample 54 5,000 270,000 DBOC 2 Noise levels Construction / sample 54 1,500 81,000 DBOC monitoring 3 Surface water Construction / sample 39 4,000 156,000 DBOC monitoring 4 Water and sludge Operation LS / yr - - 200,000 DBO Subtotal (C) 707000 Subtotal (D) - Total (A+B+C) INR 2,732,000

This EMP is for all the three towns Betul-Bazar , Amla and Sarni respectively

116

X. CONCLUSIONAND RECOMMENDATION 146. The process described in this document has assessed the environmental impacts of all elements of the Package 1B towns water supply improvement subproject. All potential impacts were identified in relation to pre-construction, construction, and operation phases. Planning principles and design considerations have been reviewed and incorporated into the site planning and design process wherever possible; thus, environmental impacts as being due to the project design or location were not significant.

147. There are two important location and design aspects. First, the proposed water supply schemes include design of new water sources, that include construction of Weir (for Amla),and tapping raw water from Tapti River for Betul-Bazar town. Details of proposed components of Betul town is separately attached.

148. For Betul-Bazar WSS, the most appropriate water source considered is Tapti River. A bring water supply scheme is proposed for Betul town from Tapti River. weir proposed to be constructed on Tapti River for Betul town and water will be to pump to WTP from Tapti River. Weir was designed considering the water demand of Betul Town.

149. For Amla town there is only one important location and design aspects; i.e. the proposed water supply schemes include design of new water sources, that include construction of weir.No flow data available for these river as they are not gauged by WRD. Considering the low water requirement of town (3.60 MLD ), and almost perennial nature of river (flows for 7-8 months a year) with very high flows during monsoon, (as gathered from local information), it is assessed to be unlikely to have any issue of source sustainability. To cater to the no-flow period (3-4 months), small weir is proposed. These is small weir, with a height of just 6 m above the river bed level (same as depth of river banks), thus confining the submergence to river course itself. The main purpose of the weir is to recharge the riverbed/groundwater, and not for direct abstraction from the storage. Storage is small and there are no arrangements to change the height or gates to release or hold water, dam will be filled at the first monsoon flow itself, and will continue to be full throughout (as no abstraction, except the evaporation and infiltration losses), and the water coming from the upstream will overflow freely. Therefore the change in flow regime due to these small dams will be negligible on downstream users and on river eco system. The proposed impoundment in fact is likely to benefit the environment through groundwater recharge and propagation of aquatic life. Water quality is suitable for drinking water after conventional treatment and disinfection, and there are no notable pollution sources. No negative impacts thus envisaged.

150. For Sarni, Ground water level in Sarni is very low to supply the water in Town. Tawa river is generally dry in summer season, so found not adequate to as water source. Satpura reservoir is found adequate source for Sarni Water Supply Scheme due to its adequacy in terms of quality as well qu75.43antity. After water analysis of Satpura Reservoir, it is found that all the parameter is beyond the drinking water standard.Capacity of Reservoir is 75.43

117

MCM and our requirement is 8.43 MCM in ultimate Stage 2048. It is almost 9 times to the requirement of ultimate Stage hence it is sufficient enough.

151. Potential negative impacts were identified in relation to both construction and operation of the improved infrastructure. Mitigation measures have been developed in generic way to reduce all negative impacts to acceptable levels. These were discussed with specialists responsible for the engineering aspects, and as a result some measures have already been included in the outline designs for the infrastructure. These include: i. Locating all pipelines within the ROW of existing roads, to avoid the need to acquire land or relocate people; ii. Locating pipelines on unused land adjacent to roads wherever possible, to avoid damaging roads and disrupting traffic and other activities.

152. This means that the number of impacts and their significance has already been reduced by amending the design .

153. Water source sustainability ,for Tapping on Raw Water Rising Main of Betul WSSfor Betul Bazar has been reviewed based on the available data. Permission of water resources department for Amla and sarni town is a prerequisite for this project, and this needs to be obtained prior to invitation of bids for civil works. Water quality is appropriate for drinking water supply after treatment and disinfection.

154. During the construction phase, impacts mainly arise from the construction dust and noise, the need to dispose of large quantities of waste soil and import a similar amount of sand to support the sewer in the trenches; and from the disturbance of residents, businesses, traffic and important buildings by the construction work. The social impacts (access disruptions) due to construction activities are unavoidable, as the residential and commercial establishments exist along the roads where pipes will be laid. Avoidance of work during at important tourist place during the peak tourist season is suggested.

155. Anticipated impacts of water supply during operation and maintenance will be related to detection and repair of leaks, pipe bursts. These are, however, likely to be minimal, as proper design and selection of good quality pipe material shall mean that leaks are minimal. Leak repair work will be similar to the pipe-laying work. Application and handling of chlorine gas will involve certain risks, and appropriate measures are suggested for safe application.

156. The public participation processes undertaken during project design ensured stakeholders are engaged during the preparation of the IEE. The planned information disclosure measures and process for carrying out consultation with affected people will facilitate their participation during project implementation.

157. The project’s grievance redressal mechanism will provide the citizens with a platform for redressal of their grievances, and describes the informal and formal channels, time frame, and mechanisms for resolving complaints about environmental performance.

118

158. The EMP will assist the PMU, PIU, PDMC and contractors in mitigating the environmental impacts, and guide them in the environmentally sound execution of the proposed project.

159. A copy of the EMP shall be kept on-site during the construction period at all times. The EMP shall be made binding on all contractors operating on the site, and will be included in the contractual clauses. Non-compliance with, or any deviation from, the conditions set out in this document shall constitute a failure in compliance.

160. The project will benefit the general public by contributing to the long-term improvement of water supply and sewerage systems and community livability in towns. The potential adverse environmental impacts are mainly related to the construction period, which can be minimized by the mitigating measures and environmentally sound engineering and construction practices.

161. Therefore, as per ADB SPS, the project is classified as environmental category C and does not require further environmental impact assessment. However, to conform to government guidelines projects require (i) permission of WRD, GoMP for weirand Intake well construction and water abstraction from Bel river for Amla and water abstraction from reservoirs for BetulBazar and sarni town(ii) WTP requires Consent for Establishment (CFE) and Consent for Operation (CFO) from Madhya Pradesh Pollution Control Board. These permissions/approvals shall be obtained prior to invitation of bids for civil works.

162. The IEE shall be updated during design stage by DBO contractor to reflect any change and amendment and will be reviewed and approved by PMU.

119

Appendix 1. Stakeholder Consultations of Betul Bazar

List of ULB officials attended meeting and remained during site visit are given below:

120

Minutes of Meeting • In Betul Bazar Town, Stakeholders meeting was conducted for proposed water supply scheme in town. In this meeting Local representatives, ULB staffs and local people have participated. • During meeting, present water supply was found not adequate in terms of water quantity in town.

• All stakeholders express their happiness for upcoming water supply scheme as town has urgent need for this.

• All the existing water sources for Betul town have been discussed

• Some people requested to give priority of local people in employment during construction work.

• Some people complained about the delayed work during construction with their past experience. So they requested to appoint good contractor, so that constructed work will be finished in given timeline.

• People also requested to maintain the water pressure in households.

121

Appendix 2: Stakeholder consultation for Amla town

122

123

Appendix 3: Stakeholder Consultations of Sarni Town List of ULB officials attended meeting and remained during site visit are given below:

124

Minutes of Meeting • During stakeholders’ consultation meeting, local representatives, ULB officials and local people was informed about upcoming water supply project in Sarni.

• Existing scenario of water supply was discussed with stakeholders.

• All the stakeholders informed about the inadequate water supply in the town and stressed for need of the water supply scheme.

• Component of proposed water supply scheme was discussed with stakeholders.

• All available water sources for Sarni WSS were discussed and Satpura Reservoir was selected for water source unanimously.

• Some people requested to speed up of construction works to avoid problems during excavation of roads and construction works.

• The condition of components of existing water supply scheme has been discussed for reuse.

125

Appendix 4: Rapid Environment Assessment Checklist for Betul Bazar Country/ Project: India/ Madhya Pradesh Urban Service Improvement Program – Betul Bazar Water Supply Subproject

Sector/ Division: Urban Development and Environment Department/ UAED

SCREEINING QUESTION YES NO REMARKS A. Project Siting Is the project area ▪ Densely populated?  The average density of Betul Bazar is found 63.27 Person/ Hactare, that is considered very high. Only during construction phase, population would be affected adversely due to excavation, construction. But the impact would be very low. During operation, local of town would be more beneficiary ▪ Heavy with development activities?  No ▪ Adjacent to or within any  No environmentally sensitive areas? ▪ Cultural heritage site  No ▪ Protected Area  No ▪ Wetland  No ▪ Mangrove  No ▪ Estuarine  No ▪ Buffer zone of protected area  No ▪ Special area for protecting  No biodiversity ▪ Bay  No B. Potential Environmental Impacts

Will the Project cause… • Pollution of raw water supply  There are no significant water from upstream wastewater pollution sources in the catchment. discharge from Raw water quality is tested and • Communities, industries, found that it is suitable for Domestic agriculture, and soil erosion use. runoff? • Impairment of historical/cultural  Not applicable monuments/areas and loss/damage to these sites? • Hazard of land subsidence  Not applicable, subproject does not caused by excessive ground involve groundwater abstraction water pumping? • Social conflicts arising from  Project does not involve land displacement of communities? acquisition /displacement. No social

126

conflicts envisaged • Conflicts in abstraction of raw  No, the water will be abstracted water for water supply with other with due Permission of Water beneficial water uses for surface Resource Department. and ground waters? • Unsatisfactory raw water supply  Raw water Quality is tested and (e.g. excessive pathogens or found that it is suitable for Domestic mineral constituents)? use. • Delivery of unsafe water to  Water will be treated and distribution system? disinfected prior to supply. • Inadequate protection of intake  Construction of no intake well works or wells, leading to pollution of water supply? • Over pumping of ground water,  No Ground water pumping is leading to salinization and required as Surface water source is ground subsidence? selected for the project • Excessive algal growth in  Regular cleaning of storage tanks storage reservoir? will be conducted during operation. • Increase in production of  As per CPHEEO manual the rate of sewage beyond capabilities of water supply is 70lpcd for the town community facilities? where sewerage scheme is not anticipated • Inadequate disposal of sludge  Appropriate provision for sludge from water treatment plants? drying and disposal is included in the project • Inadequate buffer zone around  No pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities? • Impairments associated with  No transmission lines and access roads? • Health hazards arising from  Measures for safe handling of inadequate design of facilities Chlorine are included for receiving, storing, and handling of chlorine and other hazardous chemicals. • Health and safety hazards to  Measures for safe handling of workers from the management Chlorine are included of chlorine used for disinfection and other contaminants? • Dislocation or involuntary  There is no resettlement of people resettlement of people for project implementation. • Social conflicts between  The contractor will be utilizing the construction workers from other local labour forces as far as areas and community workers? possible; in case if it is unavoidable, labour camps and facilities will be provided

127

appropriately. No conflicts envisaged. • Noise and dust from  Dust suppression measures such construction activities? as water sprinkling will be employed • Increased road traffic due to  Excavation & Laying pipelines interference of construction along public road will interfere with activities? the traffic. Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. • Continuing soil erosion/silt runoff  Construction work during monsoon from construction operations? shall be carried out with due care so that silt run off due to construction operation is prevented. • Delivery of unsafe water due to  Appropriate O&M will be conducted poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to distribution  Not envisaged system, which is corrosive due to inadequate attention to feeding of corrective chemicals? • Accidental leakage of chlorine  Measures for safe handling of gas? chlorine are included. • Excessive abstraction of water  Water abstraction will be limited to affecting downstream water allocate quantity for Betul Bazar users? • Competing uses of water?  Water abstraction will be limited to allocate quantity for Betul Bazar. • Increased sewage flow due to  As per CPHEEO manual the rate of increased water supply water supply is 70lpcd for the town where sewerage scheme is not anticipated • Increased volume of sullage  No (wastewater from cooking and washing) and sludge from wastewater treatment plant ▪ Large population influx during project  Minimum influx of population during construction and operation that the construction and operation causes increased burden on social period. infrastructure and services (such as

128

water supply and sanitation systems)? ▪ Risks to community health and safety  No such materials are used in due to the transport, storage, and use project so no risk to community and/or disposal of materials such as health & safety explosives, fuel, and other chemicals during operation and construction? ▪ Community safety risks due to both  Proper safety measures would be accidental and natural hazards, ensured during the construction & especially where the structural operation and decommissioning. elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning?

ClimateChangeandDisaster Yes No Remarks RiskQuestions Thefollowingquestionsarenotfor environmental categorization.Theyareincluded inthischecklisttohelp identifypotentialclimate anddisaster risks. Is theProjectareasubjectto √ Semi-aridzone, unreliablerainfall, hazardssuchas earthquakes, lessvegetationcover. Promote floods,landslides,tropicalcyclonewinds,st moreefficientuseofwater by ormsurges, tsunamior volcanic reducinglossesandwastageto eruptionsandclimatechanges? counter increased demands due to highertemperatures. Couldchanges intemperature, √ Reductioninrainfallmayaffectthe precipitation,or extreme events patterns water availabilityfromdam.Given overtheProjectlifespan affecttechnicalor the priorityfordrinkingwater supply, financial dead storagewill beutilized sustainability(e.g.,changesinrainfallpatter incaseoflowrain fallyears nsdisruptreliability ofwater supply;sealevelrisecreatessalinity intrusion into Are thereanydemographicor socio- √ No economicaspects ofthe Project area that arealready vulnerable(e.g.,highincidenceof marginalized populations,rural- urbanmigrants,illegal Settlements, ethnicminorities,women or children)? CouldtheProject potentiallyincrease √ No theclimateor disaster vulnerability ofthesurroundingarea(e.g.,byusingwater from a vulnerable source thatisrelied upon by many user groups, or encouragingsettlementinearthquakezone

129

Appendix 5: Rapid Environment Assessment Checklist for Amla country/Project: India/Madhya Pradesh Urban Services Improvement program-Amla- Water Supply project Sector/Division: Urban Development & Environment Department/MPUDC

SCREEINING QUESTION YES NO REMARKS A. Project Siting Is the project area… Densely populated?  The Project covers entire town including old Amla towns densely populated areas. There are no major negative impacts envisaged because Distribution line will be located in unused Government lands alongside the existing roads and can be constructed without causing disturbance to houses and commercial establishments. Heavy with development activities?  No Adjacent to or within any  No environmentally sensitive areas? Cultural heritage site  No Protected Area  No Wetland  No Mangrove  No Estuarine  No Buffer zone of protected area  No Special area for protecting  No biodiversity Bay  No B. Potential Environmental Impacts

Will the Project cause… Pollution of raw water supply from  There are no significant water upstream wastewater discharge from pollution sources in the catchment. Communities, industries, agriculture, Raw water quality is tested and and soil erosion runoff? found that it is suitable for Domestic use. Impairment of historical/cultural  No monuments/areas and loss/damage to these sites? Hazard of land subsidence caused  subproject does not involve by excessive ground water pumping? groundwater abstraction Social conflicts arising from  Project does not involve land displacement of communities? acquisition / displacement..No

130

social conflicts envisaged Conflicts in abstraction of raw water  No, the water will be abstracted for water supply with other beneficial from Bel river with due permission water uses of Water Resource Department for surface and ground waters? Unsatisfactory raw water supply  Raw water Quality is tested and (e.g. excessive pathogens or mineral found that it is suitable for Domestic constituents)? use. ▪ Delivery of unsafe water to  Water will be treated and distribution system? disinfected prior to supply. Inadequate protection of intake  Water is abstracted from Bel river, works or wells, leading to pollution of as there are no major polluting water supply? sources in the catchment. Over pumping of ground water,  No Ground water pumping is leading to salinization and ground required as Surface water source is subsidence? selected for the project Excessive algal growth in storage  Regular cleaning of storage tanks reservoir? will be conducted during operation. Increase in production of sewage  As per CPHEEO manual the rate of beyond capabilities of community water supply is 70lpcd for the town facilities? where sewerage scheme is not anticipated Inadequate disposal of sludge from  Appropriate provision for sludge water treatment plants? drying and disposal is included in the project Inadequate buffer zone around  No pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities? Impairments associated with  No transmission lines and access roads? Health hazards arising from  Measures for safe handling of inadequate design of facilities for Chlorine are included receiving, storing, and handling of chlorine and other hazardous chemicals. Health and safety hazards to  Measures for safe handling of workers from the management of Chlorine are included chlorine used for disinfection and other contaminants? Dislocation or involuntary  There is no resettlement of people resettlement of people for project implementation. Social conflicts between  The contractor will be utilizing the construction workers from other local labour forces as far as areas and community possible; in case if it is workers? unavoidable, labour camps and facilities will be provided appropriately. No conflicts envisaged.

131

Noise and dust from construction  Dust suppression measures such activities? as water sprinkling will be employed Increased road traffic due to  Excavation & Laying pipelines interference of construction along public road will interfere with activities? the traffic. Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. Continuing soil erosion/silt runoff  Construction work during monsoon from construction operations? shall be carried out with due care so that silt run off due to construction operation is prevented. Delivery of unsafe water due to poor  Appropriate O&M will be conducted O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? Delivery of water to distribution  Not envisaged system, which is corrosive due to inadequate attention to feeding of corrective chemicals? Accidental leakage of chlorine gas?  Measures for safe handling of chlorine are included. Excessive abstraction of water  Water abstraction will be limited to affecting downstream water users? allocate quantity for Amla. competing uses of water?  Water abstraction will be limited to allocate quantity for Amla. Increased sewage flow due to  As per CPHEEO manual the rate of increased water supply water supply is 70lpcd for the town where sewerage scheme is not anticipated Increased volume of sullage  No (wastewater from cooking and washing) and sludge from wastewater treatment plant ▪ Large population influx during project  Minimum influx of population during construction and operation that the construction and operation causes increased burden on period. socialinfrastructure and services (such as water supply and sanitation systems)? ▪ Risks to community health and safety  No such materials are used in due to the transport, storage, and use project so no risk to community

132

and/or disposal of materials such as health & safety explosives, fuel, and other chemicals during operation and construction? ▪ Community safety risks due to both  Proper safety measures would be accidental and natural hazards, ensured during the construction & especially where the structural operation and decommissioning. elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning?

133

Appendix 6: Rapid Environment Assessment Checklist for Sarni

Country/ Project: India/ Madhya Pradesh Urban Service Improvement Program – Sarni Water Supply Subproject

Sector/ Division: Urban Development and Environment Department/ UAED

SCREEINING QUESTION YES NO REMARKS A. Project Siting Is the project area ▪ Densely populated?  The population density of Sarni town is high due to industrial development. It is foundaverage 24.3 Person/ Hectare as per 2011 census, ▪ Heavy with development activities?  No ▪ Adjacent to or within any  Adjacent to town, there is Satpura environmentally sensitive areas? forest area, that is limited the growth of the Sarni town. ▪ Cultural heritage site  No ▪ Protected Area  No ▪ Wetland  No ▪ Mangrove  No ▪ Estuarine  No ▪ Buffer zone of protected area  No ▪ Special area for protecting  No biodiversity ▪ Bay  No B. Potential Environmental Impacts

Will the Project cause… • Pollution of raw water supply  There are no significant water from upstream wastewater pollution sources in the catchment. discharge from Raw water quality is tested and • Communities, industries, found that it is suitable for Domestic agriculture, and soil erosion use. runoff? • Impairment of historical/cultural  Not applicable monuments/areas and loss/damage to these sites? • Hazard of land subsidence  Not applicable, subproject does not caused by excessive ground involve groundwater abstraction water pumping? • Social conflicts arising from  Project does not involve land displacement of communities? acquisition /displacement.No social conflicts envisaged • Conflicts in abstraction of raw  No, the water will be abstracted

134

water for water supply with other with due Permission of Water beneficial water uses for surface Resource Department. and ground waters? • Unsatisfactory raw water supply  Raw water Quality is tested and (e.g. excessive pathogens or found that it is suitable for Domestic mineral constituents)? use. • Delivery of unsafe water to  Water will be treated and distribution system? disinfected prior to supply. • Inadequate protection of intake  No works or wells, leading to pollution of water supply? • Over pumping of ground water,  No Ground water pumping is leading to salinization and required as Surface water source is ground subsidence? selected for the project • Excessive algal growth in  Regular cleaning of storage tanks storage reservoir? will be conducted during operation. • Increase in production of  As per CPHEEO manual the rate of sewage beyond capabilities of water supply is 70lpcd for the town community facilities? where sewerage scheme is not anticipated • Inadequate disposal of sludge  Appropriate provision for sludge from water treatment plants? drying and disposal is included in the project • Inadequate buffer zone around  No pumping and treatment plants to alleviate noise and other possible nuisances and protect facilities? • Impairments associated with  No transmission lines and access roads? • Health hazards arising from  Measures for safe handling of inadequate design of facilities Chlorine are included for receiving, storing, and handling of chlorine and other hazardous chemicals. • Health and safety hazards to  Measures for safe handling of workers from the management Chlorine are included of chlorine used for disinfection and other contaminants? • Dislocation or involuntary  There is no resettlement of people resettlement of people for project implementation. • Social conflicts between  The contractor will be utilizing the construction workers from other local labour forces as far as areas and community workers? possible; in case if it is unavoidable, labour camps and facilities will be provided appropriately. No conflicts envisaged.

135

• Noise and dust from  Dust suppression measures such construction activities? as water sprinkling will be employed • Increased road traffic due to  Excavation & Laying pipelines interference of construction along public road will interfere with activities? the traffic. Construction material transport will increase traffic within city and dumping construction material on road cause traffic congestion. Proper traffic & Construction planning will be ensured to minimize the interference. • Continuing soil erosion/silt runoff  Construction work during monsoon from construction operations? shall be carried out with due care so that silt run off due to construction operation is prevented. • Delivery of unsafe water due to  Appropriate O&M will be conducted poor O&M treatment processes (especially mud accumulations in filters) and inadequate chlorination due to lack of adequate monitoring of chlorine residuals in distribution systems? • Delivery of water to distribution  Not envisaged system, which is corrosive due to inadequate attention to feeding of corrective chemicals? • Accidental leakage of chlorine  Measures for safe handling of gas? chlorine are included. • Excessive abstraction of water  Water abstraction will be limited to affecting downstream water allocate quantity for Sarni users? • Competing uses of water?  Water abstraction will be limited to allocate quantity for Sarni. • Increased sewage flow due to  As per CPHEEO manual the rate of increased water supply water supply is 135 lpcd for the town where sewerage scheme is not anticipated • Increased volume of sullage  No (wastewater from cooking and washing) and sludge from wastewater treatment plant ▪ Large population influx during project  Minimum influx of population during construction and operation that the construction and operation causes increased burden on social period. infrastructure and services (such as water supply and sanitation systems)?

136

▪ Risks to community health and safety  No such materials are used in due to the transport, storage, and use project so no risk to community and/or disposal of materials such as health & safety explosives, fuel, and other chemicals during operation and construction? ▪ Community safety risks due to both  Proper safety measures would be accidental and natural hazards, ensured during the construction & especially where the structural operation and decommissioning. elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation, and decommissioning?

Climate Change and Disaster Risk Yes No Remarks Question s Thefollowingquestionsarenotfor environmentalcategorization.They areincludedinthischecklistohelp identifypotentialclimateanddisaster risks.

Is the Project area subject to hazards √ Semi-arid zone, unreliable rainfall, Suchasearthquakes,floods,landslides, Lessvegetationcover. tropicalcyclonewinds,stormsurges, Promotemore efficient use of water tsunamiorvolcaniceruptionsand by reducing climate changes? losses and wastage to counter increased demands due to higher Couldchangesintemperature,precipitatio √ Temperatures.Reduction inrainfal l may affect the n, wateravailabilityfromdam. Given orextremeeventspatternsovertheProject thepriorityfordrinkingwatersupply, lifespan affecttechnicalor financial deadstoragewillbeutilizedincaseof sustainability (e.g., changes in rainfall lowrain fallyears patterns disruptreliabilityof water supply; sealevelrisecreatessalinityintrusioninto proposed watersupplysource)? Arethereanydemographicorsocio- √ No economicaspectsoftheProjectareathat arealreadyvulnerable(e.g.,highincidence ofmarginalizedpopulations,rural-urban migrants,illegalSettlements,ethnic minorities,womenorchildren)?

137

Could the Projectpotentiallyincrease the √ No climate ordisastervulnerability of the surroundingarea (e.g., byusing waterfrom a vulnerable source thatisrelied upon by manyusergroups, orencouraging settlementin earthquake zones)?

138

Appendix 7: Details of Sample: Water sample collected for Bel River Amla town

139

Appendix 8 : Details of Sample: Water sample collected for Satpura Reservoir Sarni town

140

Appendix 9: Salient Features of Satpura Reservoir

1 Date of Commencement 2nd April 1964 2 Date of Completion 31st August 1967 3 Width of river at dam site 350 feet 4 Catchment area at dam site 213.58 Sq. Miles 5 Mean annual rain fall 60 inches 7 water spread area 2530 Acres 8 Maximum flood discharge 135000 Cu.Sec. 9 Designed flood discharge 170000 Cu.Sec. 10 Longitude 78011 ' E 11 Latitude 220 8' 30" N 12 Natural flood river bed level (+) 1336 F. T. 13 Deepest foundation level (+) 1313 F. T. 14 Spillway crest level (+) 1415 F. T. 15 Full reservoir level (+) 1430 F. T. 16 Revise F. R. L. (+) 1433 F. T. 17 Maximum flood level (+) 1436 F. T. 18 Road top level (+) 1445 F. T. 19 Total length at dam 1685 feet 20 Length of Earthen banks 685 feet 21 Maximum depth of water 95 feet 22 Height of dam 110 feet 23 Total nos. of gate 15 Nos. 29 Revised area of lack 2898 Acres 30 Old capacity 3900 M. Cu. Feet (110.37 M. Cum) 31 Revised capacity 2663.7856 M. Cu. Feet (75.43 M. Cum)

141

Appendix 10; Toposheet BetulBazar

142

Appendix 11; Toposheet Amla

143

Appendix 12: Toposheet Sarni

144

Appendix 13:NationalAmbientAirQualityStandards

SL Pollutants Time Concentrationinambient air NO: weighted Industrial, EcologicallySensitive average Residential, Areas Rural& Other 1 SulphurDioxide(SO2)µg Annual 50 20 /m3 24 hours 80 80 2 NitrogenDioxide(NO2) Annual 40 30 µg/m3 24 hours 80 80 3 ParticulateMatter(Size Annual 60 60 less than10µm) or 24 hours 100 100 4 ParticulateMatter(Size Annual 40 40 less than2.5µm) or 24 hours 60 60 PM2.5µg/m3

3 5 Ozone (O3) µg/m 8 hours* 100 100 1 hour** 180 180

6 Lead (Pb) µg/m3 Annual 0.5 0.5 24 hours 1.0 1.0 7 CarbonMonoxide (CO) 8 hours* 02 02 mg/m3 1 hour** 04 04 3 8 Ammonia (NH3) µg/m Annual* 100 100 24 hours 400 400 3 9 Benzene (C6H6) µg/m Annual* 5 5 10 Benzo(a)Pyrene (BaP)- Annual* 1 1 particulate phase only, 3 11 Arsenic(As),ng/m ng/m3 Annual* 6 6 12 Nickel (Ni), ng/m3 Annual* 20 20

145

Appendix 14:NationalAmbientAirQualityStandards inRespect ofNoise

Area code Categoryof area/zone LimitindB Daytim Night time A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silencezone 50 40

Appendix 15:VehicleExhaust Emission Norms

Norms CO(g/km) HC+ NOx(g/km) 1991Norms 14.3-27.1 2.0(OnlyHC) 1996 Norms 8.68-12.40 3.00-4.36 1998Norms 4.34-6.20 1.50-2.18 India stage 2000 norms 2.72 0.97 Bharatstage-II 2.2 0.5 BharatStage-III 2.3 0.35 (combined)

BharatStage-IV 1.0 0.18 (combined)

2.HeavyDieselVehicles

Norms CO(g/kmhr) HC(g/kmhr) NOx (g/kmhr) PM(g/kmhr) 1991Norms 14 3.5 18 - 1996 Norms 11.2 2.4 14.4 - India stage 2000 norms 4.5 1.1 8.0 0.36 Bharatstage-II 4.0 1.1 7.0 0.15 BharatStage-III 2.1 1.6 5.0 0.10 BharatStage-IV 1.5 0.96 3.5 0.02

146

Appendix 16:DrinkingWaterStandards

No. Substance or Requireme Undesirable Permissibl Remarks Characteristic nt Desirable effectoutside the e limit limit desirable inthe absenceof alternate EssentialCharacteristic 1. Colour Hazen 5 Above 5,consumer 25 Extendedto 25only Units,Max acceptancedecreases if toxicSubstance arenot suspect inabsence ofalternatesources

2. Odour Unobjection - - a) testcoldandwhen a ble heated b) test areseveral dilutions 3. Taste Agreeable - - Testto beconducted onlyaftersafelyhas beenestablished 4. Turbidity(NTU 5 Above 5,consumer 10 - ) Max acceptancedecreases

5. pH value 6.5 to8.5 Beyond thisrangethe Norelaxation - water will after themucous membraneand/or water supplysystem 6. Total 300 Encrustationinwater 600 - Hardnes supplystructure and s (mg/L) adverseeffectson CaCO3 domesticuse

7. Iron(mg/L,Fe) 0.3 Beyond thislimit 1.0 - Max taste/appearanceareaffe cted;has adverse effectsondomesticuses andwater supplystructure and promotesironbacteria

8. Chlorides250 250 Beyond effectsoutsidethe 1000 - (mg/L,Cl) desirable limit Max 9. Residual free 0.2 - - To be applicable only Chlorine(mg/L) whenwater , Max ischlorinated.Testeda t customer end.When protection againstviralinfectioni srequired, it

147

DesirableCharacteristics 10. Dissolvedsolid 500 Beyond this,palatability 2000 - s mg/L.Max decreasesandmaycause gastrointestinal irritation.

11. Calcium(mg/L 75 Encrustationinwater 200 - , Ca)Max. supplystructure and adverseeffectson domesticuse.

12. Magnesium(mg/ 30 Encrustationinwater 100 - L, Mg)Max supply structure and adverseeffectsondomesti cuse.

13. Copper 0.05 Astringenttastedis 1.5 - (mg/L,Cu) Max colorationandcorrosionof pipes fittingsandutensils will becausedbeyondthis.

14. Manganese 0.1 Beyond thislimit 0.3 - (mg/L,Mn)Max taste/appearanceare affected,hasadverse effecton domesticuseandwater supplystructure

15. Sulphate 200 Beyond thiscauses 400 Maybe extendedupto (mg/L,SO4) Max. gastro intestinal irritation 400 provided when magnesiumor magnesium(asMg sodiumare present ) doesnotexceed 30 16. Nitrate(mg/L 45 Beyondthis 100 - , NO3)Max. methaemoglobinemia takes place.

17. Fluoride(mg/L,F) 1.0 Fluoridemaybekeptas 1.5 - Max. lowas possible.High fluoridemaycause fluorosis.

18. Phenolic 0.001 Beyond this,itmaycause 0.002 - Compounds(mg/ objectionabletasteand L C6H5OH)Max. odour 19. Mercury(mg/LHg 0.001 Beyond thisthewater NoRelaxation. To be testedwhen ) Max becomes toxic pollutionissuspecte d 20 Cadmium 0.01 Beyond thisthewater NoRelaxation. To be testedwhen (mg/L,Cd) Max becomes toxic pollutionissuspecte d 21. Selenium 0.01 Beyond thisthewater NoRelaxation. To be testedwhen (mg/L,Se) Max becomes toxic. pollutionissuspecte d

148

22. Arsenic 0.05 Beyond thisthewater NoRelaxation To be testedwhen (mg/L,As) Max. becomes toxic pollutionissuspecte d 23. Cyanide 0.05 Beyond thisthewater NoRelaxation To be testedwhen becomes toxic pollutionissuspecte d 24. Lead(mg/LPb) 0.05 Beyond thisthewater NoRelaxation To be testedwhen Max. becomes toxic pollutionissuspecte d

25. Zinc(mg/L,Zn) 5 Beyond thislimititcan 15 To be testedwhen Max. causeastringenttasteand pollutionissuspecte an opalescence inwater d

26. Anionicdetergents 0.2 Beyond thislimititcan 1.0 To be testedwhen (mg/L,MBAS causealightfrothinwater pollutionissuspecte ) Max d 27. Chromium 0.05 Maybe - - (mg/L,Cr6+ carcinogenicabove thislimit 28. Polynuclear - Maybe carcinogenic - - Aromatic Hydrocarbons (mg/l,PAH)Max 29. Mineral oil 0.01 Beyond thislimit, 0.03 To be testedwhen (mg/L) undesirabletaste and pollutionissuspecte odourafterchlorination d takesplace

30. Pesticides(mg/L) Absent Toxic 0.001 - max Radioactivematerials 31. Alphaemitters - - 0.1 - Bq/LMax 32. Betaemitters - - 1.0 - Pci/LMax 33. Alkalinity(mg/L, 200 Beyond thislimit,taste 600 - ) Max becomes unpleasant

34. Aluminum(mg/L 0.03 Cumulative effectis 0.2 , Al) Max reported tocausedementia

35. Boron(mg/L) Max 1.0 - 5.0 -

149

Appendix17: EXTRACT FROM CONSTRUCTION & DEMOLITION MANAGEMENT RULES, 2016

150

151

152

153

154

155

Appendix 18: Salient Features of Major Labor Laws Applicable to Establishments Engaged in Construction of Civil Works

(i) Workmen Compensation Act, 1923 - The Act provides for compensation in case of injury by accident arising out of and during the course of employment. (ii) Payment of Gratuity Act, 1972 - Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years’ service or more or on death at the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees. (iii) Employees’ PF and Miscellaneous Provisions Act, 1952 - The Act provides for monthly contributions by the employer plus workers @10 % or 8.33 %. The benefits payable under the Act are: (a) Pension or family pension on retirement or death as the case may be; (b) deposit linked insurance on the death in harness of the worker; (c) payment of PF accumulation on retirement/death etc. (iv) Maternity Benefit Act, 1951 - The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc. (v) Contract Labour (Regulation and Abolition) Act, 1970 - The Act provides for certain welfare measures to be provided by the Contractor to contract labor and in case the Contractor fails to provide, the same are required to be provided by the Principal Employer by Law. The principal employer is required to take Certificate of Registration and the Contractor is required to take a License from the designated Officer. The Act is applicable to the establishments or Contractor of principal employer if they employ 20 or more contract labor. (vi) Minimum Wages Act, 1948 - The employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employment. (vii) Payment of Wages Act, 1936 - It lays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers. (viii) Equal Remuneration Act, 1979 - The Act provides for payment of equal wages for work of equal nature to Male and Female workers and not for making discrimination against Female employees in the matters of transfers, training and promotions etc. (ix) Payment of Bonus Act, 1965 - The Act is applicable to all establishments employing 20 or more workmen. The Act provides for payments of annual bonus subject to a minimum of 8.33 % of wages and maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The bonus to be paid to employees getting Rs. 2,500/- per month or above up to Rs.3,500/- per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act does not apply to certain establishments. The newly set up establishments are exempted 156

for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of the Act. (x) Industrial Disputes Act, 1947 - The Act lays down the machinery and procedure for resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment. (xi) Industrial Employment (Standing Orders) Act, 1946 - It is applicable to all establishments employing 100 or more workmen (employment size reduced by some of the States and Central Government to 50). The Act provides for laying down rules governing the conditions of employment by the employer on matters provided in the Act and get the same certified by the designated Authority. (xii) Trade Unions Act, 1926 - The Act lays down the procedure for registration of trade unions of workmen and employees. The trade unions registered under the Act have been given certain immunities from civil and criminal liabilities. (xiii) Child Labor (Prohibition and Regulation) Act, 1986 - The Act prohibits employment of children below 14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of child labor is prohibited in Building and Construction Industry. (xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of Service) Act, 1979 - The Act is applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The inter-state migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment and back, etc (xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 and the Cess Act of 1996 - All the establishments who carry on any building or other construction work and employ 10 or more workers are covered under this Act. All such establishments are required to pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the Government. The employer of the establishment is required to provide safety measures at the building or construction work and other welfare measures, such as canteens, first-aid facilities, ambulance, housing accommodation for workers near the workplace etc. The employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

157

Appendix 19: Sample Outline Spoils (construction waste) Management Plan • The Spoil Management Plan should be site specific and be part of the monthly Construction Management Plan. • The contractor, in consultation with the PIU, has to find out appropriate location/s for the disposal of the excess soil generated. The spoils should be deposited only at these sites. • Further precautions need to be taken in case of the contaminated spoils • The vehicle carrying the spoil should be covered properly. • The spoils generating from each site should be removed on the same day or immediately after the work is complete. The site / road should be restored to the original condition. I. Spoils information The spoil information contains the details like a) The type / material, b) Potential contamination by that type, c) Expected volume (site / component specific), d) Spoil Classification etc. II Spoils management The Spoil Management section gives the details of a) Transportation of spoil b) disposal site details c) Precautions taken d) Volume of contaminated spoil, if present, d) Suggested reuse of disposal of the spoil III. Documentation The volume of spoil generated (site specific, date wise), site disposed, reuse / disposal details should be documented properly.

Appendix20: Sample Outline Traffic Management Plan A. Principles for TMP around the Water Pipes Construction Sites 1. One of the prime objectives of this TMP is to ensure the safety of all the road users along the work zone, and to address the following issues: (i) the safety of pedestrians, bicyclists, and motorists travelling through the construction zone; (ii) protection of work crews from hazards associated with moving traffic; (iii) mitigation of the adverse impact on road capacity and delays to the road users; (iv) maintenance of access to adjoining properties; and (v) addressing issues that may delay the project.

B. Operating Policies for TMP 2. The following principles will help promote safe and efficient movement for all road users (motorists, bicyclists, and pedestrians, including persons with disabilities) through and around work zones while reasonably protecting workers and equipment. (i) Make traffic safety and temporary traffic control an integral and high-priority element of project from planning through design, construction, and maintenance.

158

(ii) Inhibit traffic movement as little as possible. (iii) Provide clear and positive guidance to drivers, bicyclists, and pedestrians as they approach and travel through the temporary traffic control zone. (iv) Inspect traffic control elements routinely, both day and night, and make modifications when necessary. (v) Pay increased attention to roadside safety in the vicinity of temporary traffic control zones. (vi) Train all persons that select, place, and maintain temporary traffic control devices. (vii) Keep the public well informed. (viii) Make appropriate accommodation for abutting property owners, residents, businesses, emergency services, railroads, commercial vehicles, and transit operations. 3. Figure A2 to Figure A6 illustrates the operating policy for TMP for the construction of water pipes and the sewers along various types of roads. C. Analyze the impact due to street closure 4. Apart from the capacity analysis, a final decision to close a particular street and divert the traffic should involve the following steps: (i) approval from the ULB/Public Works Department (PWD) to use the local streets as detours; (ii) consultation with businesses, community members, traffic police, PWD, etc, regarding the mitigation measures necessary at the detours where the road is diverted during the construction; (iii) determining of the maximum number of days allowed for road closure, and incorporation of such provisions into the contract documents; (iv) determining if additional traffic control or temporary improvements are needed along the detour route; (v) considering how access will be provided to the worksite; (vi) contacting emergency service, school officials, and transit authorities to determine if there are impacts to their operations; and (vii) developing a notification program to the public so that the closure is not a surprise. As part of this program, the public should be advised of alternate routes that commuters can take or will have to take as result of the traffic diversion. 5. If full road-closure of certain streets within the area is not feasible due to inadequate capacity of the detour street or public opposition, the full closure can be restricted to weekends with the construction commencing on Saturday night and ending on Monday morning prior to the morning peak period. Figure A1: Policy Steps for the TMP

159

• Review construction schedule and methods Review

Traffic Re- • Identify initial traffic recirculation and control policy Circulation

• Identify routes for traffic diversions Traffic • Analyse adverse impact & mitigation at the detours Diversions

• Begin community consultation for consensus Full Road • Finalise or determine alternate detours Colsures

• Identify temporary parking (on and off -street ) Temporary • Discuss with CMC, owner, community for use parking

• Coordinate with theTraffic Police to enforce traffic and diversions Police Coordination

• Install traffic control devices (traffic cones, sgns, lightings, etc) Install control devices

• Conduct campaigns, publicity, and notify public about street closure Awareness

Develop a mechanism to address public grievances regarding disruptons (traffic, utilities, and diversions) Public • Redress

D. Public awareness and notifications As per discussions in the previous sections, there will be travel delays during the constructions, as is the case with most construction projects, albeit on a reduced scale if utilities and traffic management are properly coordinated. There are additional grounds for travel delays in the area, as most of the streets lack sufficient capacity to accommodate additional traffic from diverted traffic as a result of street closures to accommodate the works. 6. The awareness campaign and the prior notification for the public will be a continuous activity which the project will carry out to compensate for the above delays and minimize public claims as result of these problems. These activities will take place sufficiently in advance of the time when the roadblocks or traffic diversions take place at the particular streets. The reason for this is to allow sufficient time for the public and residents to understand the changes to their travel plans. The project will notify the public about the roadblocks and traffic diversion through public notices, ward level meetings and city level meeting with the elected representatives.

7. The PIU will also conduct an awareness campaign to educate the public about the following issues: (i) traffic control devices in place at the work zones (signs, traffic cones, barriers, etc.); (ii) defensive driving behaviour along the work zones; and 160

(iii) reduced speeds enforced at the work zones and traffic diversions.

8. It may be necessary to conduct the awareness programs/campaigns on road safety during construction. 9. The campaign will cater to all types of target groups i.e. children, adults, and drivers. Therefore, these campaigns will be conducted in schools and community centres. In addition, the project will publish a brochure for public information. These brochures will be widely circulated around the area and will also be available at the PIU, and the contractor's site office. The text of the brochure should be concise to be effective, with a lot of graphics. It will serve the following purpose: (i) explain why the brochure was prepared, along with a brief description of the project; (ii) advise the public to expect the unexpected; (iii) educate the public about the various traffic control devices and safety measures adopted at the work zones; (iv) educate the public about the safe road user behaviour to emulate at the work zones; (v) tell the public how to stay informed or where to inquire about road safety issues at the work zones (name, telephone, mobile number of the contact person; and (vi) indicate the office hours of relevant offices. E. Install traffic control devices at the work zones and traffic diversion routes

10. The purpose of installing traffic control devices at the work zones is to delineate these areas to warn, inform, and direct the road users about a hazard ahead, and to protect them as well as the workers. As proper delineation is a key to achieve the above objective, it is important to install good traffic signs at the work zones. The following traffic control devices are used in work zones:

• Signs • Pavement Markings • Channelizing Devices • Arrow Panels • Warning Lights

11. Procedures for installing traffic control devices at any work zone vary, depending on road configuration, location of the work, construction activity, duration, traffic speed and volume, and pedestrian traffic. Work will take place along major roads, and the minor internal roads. As such, the traffic volume and road geometry vary. The main roads carry considerable traffic; internal roads in the new city areas are wide but in old city roads very narrow and carry considerable traffic. However,

161

regardless of where the construction takes place, all the work zones should be cordoned off, and traffic shifted away at least with traffic cones, barricades, and temporary signs (temporary “STOP” and “GO”).

12. Figure A2 to Figure A6 illustrates a typical set-up for installing traffic control devices at the work zone of the area, depending on the location of work on the road way, and road geometrics: • Work on shoulder or parking lane • Shoulder or parking lane closed on divided road • Work in Travel lane • Lane closure on road with low volume • Street closure with detour

13. The work zone should take into consideration the space required for a buffer zone between the workers and the traffic (lateral and longitudinal) and the transition space required for delineation, as applicable. For the works, a 30 cm clearance between the traffic and the temporary STOP and GO signs should be provided. In addition, at least 60 cm is necessary to install the temporary traffic signs and cones. 14. Traffic police should regulate traffic away from the work zone and enforce the traffic diversion result from full street closure in certain areas during construction. Flagggers/ personnel should be equipped with reflective jackets at all times and have traffic control batons (preferably the LED type) for regulating the traffic during night time. 16. In addition to the delineation devices, all the construction workers should wear fluorescent safety vests and helmets in order to be visible to the motorists at all times. There should be provision for lighting beacons and illumination for night constructions.

Figure A2 & A3: Work on shoulder or parking lane & Shoulder or parking lane closed on divided road

162

Figure A4 & A5: Work in Travel lane & Lane closure on road with low volume

163

Figure A6: Street closure with detour 164

165

Appendix19:SampleGrievance RegistrationForm Sample Grievance Registration Form शिकायत पंजीकरण फा्म न्नाू (ह ंदी और अंरजी मं उपल्ध) ...... पररयजना शिकायतं, सुझाव, र्नं, हि्पणियं और पररयजना क कायाा्वयन क संबंध मं ्वागत करता । म शिकायत क साथ लगं ्प्िीकरि और रततरिया क शलए आप क साथ संपका मं रा्त करन क शलए सषम करन क शलए उनक नाम और संपका जानकारी रदान करन क शलए र्साह त करत ं। आप अपनी ्य्ततगत जानकारी िाशमल करन क शलए चुनना चाह ए, लरकन उस जानकारी क गपनीय र ना चा त ं, कृ पया मं लखन / िाइपपंग * (गपनीय) * अपन नाम क ऊपर स सूचचत करं। ध्यवाद। The ______Project welcomes complaints, suggestions, queries, and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback. Should you choose to include your personal details but want that information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name. Thank you. दिनांक Place of registration Project Town पंजीकरण की जगह पररयोजना िहर Project: पररयोजना Contact information/personal details संपका जानकारी / ्य्ततगत पववरि Name Gender * Male * Female Age नाम शलंग पु्षमह ला आयु Home address घर का पता Place ्थान Phone no. फन नंबर E-mail ईमल Complaint/suggestion/comment/question Please provide the details(who, what,where, and how)ofyour grievance below: शिकायत / सुझाव / हि्पिी / सवाल पववरि (कन, तया, क ां, और कस) क नीच अपना शिकायत करं: If included as attachment/note/letter, please tick here: लगाव / हि्पिी / पर क ूप मं िाशमल ं, त य ां संकत करं:

How do you want us to reach you for feedback or update on your comment/grievance? आप कस मं रततरिया या अपनी हि्पिी / शिकायत पर अ्यतन क शलए आप तक प ुंचन क शलए रकस तर चा त ं? FOROFFICIALUSEONLY Registered by: (Name of official registering grievance) दजा: (आचधकाररक पंजीकरि शिकायत का नाम) Mode of communication: संचार क साधन: Note/letter नि / पर E-mail ईमल Verbal/telephonic मणखक / िलीफन 166

Reviewed by: (Names/positions of officials reviewing grievance) दजा: (आचधकाररक पंजीकरि शिकायत का नाम) Action taken: कारावाई की गई: Whether action taken disclosed: Yes ररिया का खुलासा: No Means of disclosure: रकिीकरि क साधन

167

Appendix 20: Sample Environmental Site Inspection Report

Project Name Contract Number

NAME: ______DATE: ______TITLE: ______DMA: ______LOCATION: ______GROUP: ______

WEATHER: Project Survey Activity Stage Design Implementation Pre-Commissioning Guarantee Period

Monitoring Items Compliance Compliance marked as Yes / No / Not applicable (NA) / Partially Implemented (PI) EHS supervisor appointed by contractor and available on site Archaeological Supervisor appointed by contractor and available on site Construction site management plan (spoils, safety, schedule, equipment etc.,) prepared Traffic management plan prepared Dust is under control Excavated soil properly placed within minimum space Construction area is confined; no traffic/pedestrian entry observed Surplus soil/debris/waste is disposed without delay Construction material (sand/gravel/aggregate) brought to site as & when required only Tarpaulins used to cover sand & other loose material when transported by vehicles After unloading , wheels & undercarriage of vehicles cleaned prior to leaving the site No AC pipes disturbed/removed during excavation No chance finds encountered during excavation Work is planned in consultation with traffic police Work is not being conducted during heavy traffic Work at a stretch is completed within a day (excavation, pipe laying & backfilling) Pipe trenches are not kept open unduly

168

Road is not completely closed; work is conducted on edge; at least one line is kept open Road is closed; alternative route provided & public informed, information board provided Pedestrian access to houses is not blocked due to pipe laying Spaces left in between trenches for access Wooden planks/metal sheets provided across trench for pedestrian No public/unauthorized entry observed in work site Children safety measures (barricades, security) in place at works in residential areas Prior public information provided about the work, schedule and disturbances Caution/warning board provided on site Guards with red flag provided during work at busy roads Workers using appropriate PPE (boots, gloves, helmets, ear muffs etc) Workers conducting or near heavy noise work is provided with ear muffs Contractor is following standard & safe construction practices Deep excavation is conducted with land slip/protection measures First aid facilities are available on site and workers informed Drinking water provided at the site Toilet facility provided at the site Separate toilet facility is provided for women workers Workers camps are maintained cleanly Adequate toilet & bath facilities provided Contractor employed local workers as far as possible Workers camp set up with the permission of PIU Adequate housing provided Sufficient water provided for drinking/washing/bath No noisy work is conducted in the nights Local people informed of noisy work No blasting activity conducted Pneumatic drills or other equipment creating vibration is not used near old/risky buildings

Signature ______

Sign off ______Name Name Position Position 169

Appendix 21: Quarterly Reporting Format for Assistant Safeguards Officer

1. Introduction • Overall project description and objectives • Description of sub-projects • Environmental category of the sub-projects • Details of site personnel and/or consultants responsible for environmental monitoring • Overall project and sub-project progress and status

Status of Sub-Project Sub-Project List of Progress No. Design Pre- Construction Operational Name Works of Works Construction Phase            

2. Compliance status with National/ State/ Local statutory environmental requirements No. Sub-Project Name Statutory Environmental Status of Action Required Requirements Compliance

3. Compliance status with environmental loan covenants No. (List schedule and Covenant Status of Compliance Action Required paragraph number of Loan Agreement)

4. Compliance status with the environmental management and monitoring plan • Provide the monitoring results as per the parameters outlined in the EMP. Append supporting documents where applicable, including Environmental Site Inspection Reports. • There should be reporting on the following items which can be incorporated in the checklist of routine Environmental Site Inspection Report followed with a summary in the semi-annual report send to 170

ADB. Visual assessment and review of relevant site documentation during routine site inspection needs to note and record the following: o What are the dust suppression techniques followed for site and if any dust was noted to escape the site boundaries; o If muddy water was escaping site boundaries or muddy tracks were seen on adjacent roads; o adequacy of type of erosion and sediment control measures installed on site, condition of erosion and sediment control measures including if these were intact following heavy rain; o Are their designated areas for concrete works, and refuelling; o Are their spill kits on site and if there are site procedure for handling emergencies; o Is there any chemical stored on site and what is the storage condition? o Is there any dewatering activities if yes, where is the water being discharged; o How are the stockpiles being managed; o How is solid and liquid waste being handled on site; o Review of the complaint management system; o Checking if there are any activities being under taken out of working hours and how that is being managed.

171

Summary Monitoring Table Impacts Mitigation Parameters Monitored Method of Location Date of Name of (List from Measures (As a minimum those Monitoring of Monitoring Person IEE) (List from identified in the IEE Monitoring Conducted Who IEE) should be monitored) Conducted the Monitoring Design Phase

Pre-Construction Phase

Construction Phase

Operational Phase

Overall Compliance with CEMP/ EMP No. Sub-Project EMP/ CEMP CEMP/ EMP Status of Implementation Action Proposed Name Part of Contract Being (Excellent/ Satisfactory/ and Additional Documents Implemented Partially Satisfactory/ Measures (Y/N) (Y/N) Below Satisfactory) Required

172

5. Approach and methodology for environmental monitoring of the project • Brief description on the approach and methodology used for environmental monitoring of each sub- project 6. Monitoring of environmental impacts on project surroundings (ambient air, water quality and noise levels) • Brief discussion on the basis for monitoring • Indicate type and location of environmental parameters to be monitored • Indicate the method of monitoring and equipment to be used • Provide monitoring results and an analysis of results in relation to baseline data and statutory requirements

As a minimum the results should be presented as per the tables below.

Air Quality Results Parameters (Government Standards) Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Parameters (Monitoring Results)

Site No. Date of Testing Site Location PM10 SO2 NO2 µg/m3 µg/m3 µg/m3

Water Quality Results Parameters (Government Standards) Site No. Date of Sampling Site Location pH Conductivity BOD TSS TN TP µS/cm mg/L mg/L mg/L mg/L

173

Parameters (Monitoring Results) Site No. Date of Sampling Site Location pH Conductivity BOD TSS TN TP µS/cm mg/L mg/L mg/L mg/L

Noise Quality Results

LAeq (dBA) (Government Standard) Site No. Date of Testing Site Location Day Time Night Time

LAeq (dBA) (Monitoring Results) Site No. Date of Testing Site Location Day Time Night Time

7. Summary of key issues and remedial actions • Summary of follow up time-bound actions to be taken within a set timeframe.

8. Appendixes • Photos • Summary of consultations • Copies of environmental clearances and permits • Sample of environmental site inspection report • Other

174