Public Works Department

Donald J. Theisen, P.E. Director

Wayne H. Sandberg, P.E. Deputy Director/County Engineer

July 16, 2021

REQUEST FOR QUOTE – CSAH 16 MEDIAN REPAIR

1. PURPOSE OF QUOTE 1.1 Washington County is interested in repairing two sections of a concrete median along County State Aid Highway (CSAH) 16 (Valley Creek Road) in the City of Woodbury, MN. The two sections to be repaired are located on the west and east side of the intersection of Interlachen Parkway. CSAH 16 is a four lane divided urban highway with an Average Daily Traffic (ADT) of 22,000.

Median Settlement on the west leg of County Highway 16 and Interlachen Parkway

2. SCOPE OF SERVICES 2.1 To complete this work, Washington County is requesting quotes for traffic control, removals, drainage structures, concrete paving, and pavement markings. This work shall consist of providing all material, equipment, labor, and cleanup to repair the medians in accordance with the following specifications and as directed by the Engineer. 2.2 Please refer to Plans (Appendix B) and Specifications (Appendix C) for work at each site. 3. GENERAL REQUIREMENTS 3.1 The 2018 Edition of the Minnesota Department of Transportation “Standard Specifications for Construction” shall govern. 3.2 All work must be completed to the attached Plans (Appendix B) and Specifications (Appendix C). 3.3 The work to be performed is not to exceed a specified amount. County authorized work completed outside the original scope may qualify for additional compensation. 3.4 Prospective Contractors should thoroughly read the REQUIRED CONTRACT TERMS AND CONDITONS attached hereto (Appendix A) as the Contractor to whom the contract is awarded shall be required to comply with the terms and conditions contained therein. Washington County RFQ – Median Repair July 2021

4. QUOTE CONTENT 4.1 The County is not responsible for costs incurred by anyone responding to this Request for Quotes. 4.2 Upon submission, all quotes become the property of the County, which retains the right to use any concept or idea presented in any quote submitted, whether or not that quote is accepted. 4.3 The County expressly reserves the right to amend or withdraw this Request for Quotes at any time and to reject any or all quotes. 4.4 The County is not bound to accept the lowest cost quote. 4.5 Contractors are held legally responsible for their quotes and quote budgets. Contractors are not to collude with other Contractors and competitors or take any other action which will restrict competition. Evidence of such activity will result in rejection of the quote. 4.6 The County reserves the right to negotiate contract terms contemporaneously and/or subsequently with any number of Contractors as the County deems to be in its best interests. 4.7 The County reserves the right to request any additional information at any stage of the Request for Quotes process. Compliance shall be at Contractor’s expense.

At a minimum, the Contractor’s Quote shall: 1. Be submitted on time, and signed by an officer of the company who can be accountable for all representations. 2. Include identification of additional tasks, not listed in the scope, which will be required to successfully complete this project. 3. Include completed Responsible contractor form (Attachment A, A1, A2) 4. Include completed Quote Submittal Form (Attachment B)

5. QUOTE SUBMISSION RFQ Questions: Contact Andrew Giesen at [email protected]. Questions will be accepted until 3:00 pm July 30, 2021. Questions will only be accepted via email.

Quotes are due no later than 3:00 pm, Friday, August 6, 2021.

Submit Quotes to: [email protected]

Any changes to the RFQ will be sent out via Addendum post on the county’s website.

6. QUOTE EVALUATION AND SELECTION 6.1 The County reserves the right to waive any minor irregularities in the Request for Quote process. 6.2 Quotes will be evaluated based on the following criteria: 1. Ability to meet RFQ requirements. 2. Cost.

Washington County RFQ – Median Repair July 2021

APPENDIX A

REQUIRED CONTRACT TERMS AND CONDITIONS

A contract will be prepared by Washington County upon selection of a Contractor. Appropriate language will be added to document the specific nature and scope of services, costs, responsibilities, and liabilities of each party. Additional areas of concern may be incorporated, subject to mutual agreement between parties.

The following provisions I through XXI must be included in any contract and are non-negotiable.

I. COST AND PAYMENT The Contractor will provide to the County a clear documentation of work performed, dates of work, and location of work. Contractor invoice will reflect charges in accordance with the Cost Proposal provided. Contractor invoices will be paid within 30 days of receipt of the invoices providing proper documentation is presented. Payments made under this Contract shall be in the form of Automated Clearing House (ACH) or check. The County may withhold payment for failure to provide service to comply with any of the provisions of this agreement; no interest penalty shall accrue against the County.

Charges such as but not limited to truck or vehicle charges; mileage reimbursement; fuel, trip or parking charges; consumable incidental materials; shop materials; and routine environmental charges, etc. shall be included in the Contractor’s overhead and shall be calculated as indicated on the Cost Proposal provided. These charges will not be reimbursed if labeled as “miscellaneous charges.”

II. SECURITY AND PRIVACY The Contractor is responsible to close, secure, and lock all doors in County facilities when services are performed after normal County hours and no County personnel are present. Washington County has a lockout/tagout program. Contractor shall abide by the lockout/tagout procedure. While service Contractors are working in Washington County buildings, Public Works Department requires a Contractor to sign in/out on a daily basis in addition to wearing a badge stating Contractor is under the direction of Public Works. Contractor should produce sufficient identification. The Contractor agrees to take any precautions necessary to maintain security of County buildings and privacy of data found throughout County buildings or on County premises. All questions concerning security issues will be reported to Public Works Department immediately upon discovery.

III. SAFETY The Contractor must comply with the laws governing employee right to know concerning all materials classified by OSHA as hazardous. All chemical dispensers/applicators will be clearly marked showing contents. All MSDS’ relating to all chemicals shall be displayed where chemicals are stored. Any chemicals used in Washington County buildings or in the performance of County projects shall have an MSDS which will be given to Public Works Department. Any spillage of chemicals shall be reported immediately to Public Works Department.

Contractor shall remove all supplies, chemicals, etc., from Washington County premises that were used to perform services. There will be no disposing on Washington County property. There will be no loaning of tools and/or equipment to Contractors from Washington County staff.

Drinking of alcoholic beverages, using of controlled substances (drugs) or being under the influence of drugs or alcohol is expressly prohibited. Refrain from smoking of any substance in or about County buildings. Report any problems, breakage, fires, etc., immediately to Public Works Department.

Washington County RFQ – Median Repair July 2021

IV. NONDISCRIMINATION The Contractor agrees to comply with the nondiscrimination provision set forth in Minnesota Statute 181.59. The Contractors failure to comply with section 181.59 may result in cancellation or termination of the agreement, and all money due or to become due under the contract may be forfeited for a second or any subsequent violation of the terms or conditions of this contract.

V. STANDARDS The Contractor shall comply with all applicable Federal law, State statutes, Federal and State regulations, and local ordinances now in effect or adopted during the performance of the services herein until completion of said services. Failure to meet the requirements of the above shall be a substantial breach of the agreement and will be cause for cancellation of this contract.

VI. POSSESSION OF FIREARMS ON COUNTY PREMISES Unless specifically required by the terms of this contract or the person it is subject to an exception provided by 18 USC§ 926B or 926BC (LEOSA) no provider of services pursuant to this contract or subContractors shall carry or possess a firearm on County premises or while acting on behalf of Washington County pursuant to the terms of this agreement. Violation of this provision is grounds for immediate suspension or termination of this contract.

VII. SUBCONTRACTING AND ASSIGNMENT The Contractor shall not enter into any subcontract for performance of any services contemplated under this agreement, nor novate or assign any interest in the agreement, without the prior written approval of the County. Any assignment or novation may be made subject to such conditions and provisions as the County may impose. If the Contractor subcontracts the obligations under this agreement, the Contractor shall be responsible for the performance of all obligations by the subContractors.

VIII. SUBCONTRACTOR PROMPT PAYMENT Pursuant to Minnesota Statute §471.425 subd. 4a., Contractor shall pay any subContractors within 10 days of the Contractor’s receipt of payment from the County for undisputed services provided by the subContractor. The Contractor shall pay interest of 1½ percent per month, or any part of a month, to the subContractor on any undisputed amount not paid on time to the subContractor. The minimum monthly interest penalty payment for an unpaid balance of $100 or more is $10. For an unpaid balance of less than $100, the prime Contractor shall pay the actual penalty due to the subContractor. The subContractor shall have third party rights under this agreement to enforce this provision.

IX. DATA PRACTICES All data collected, created, maintained or disseminated for any purposes by the activities of the Contractor because of this agreement is governed by the Minnesota Government Data Practices Act, Minnesota Statutes Chapter 13 (Act), as amended and the Rules implementing the Act now in force or as amended. The Contractor is subject to the requirements of the Act and Rules and must comply with those requirements as if it is a governmental entity. The remedies contained in section 13.08 of the Act shall apply to the Contractor.

X. AUDITS, REPORTS, RECORDS AND MONITORING PROCEDURES/RECORDS AVAILABILITY & RETENTION Pursuant to Minn. Stat. section 16C.05 subd. 5, the Contractor will: A. Maintain records which reflect all revenues, costs incurred and services provided in the performance of this agreement.

Washington County RFQ – Median Repair July 2021

B. Agree that the County, the State Auditor, or legislative authority, or any of their duly authorized representatives at any time during normal business hours, and as often as they may deem reasonably necessary, shall have access to and the right to examine, audit, excerpt, and transcribe any books, documents, papers, records, etc., and accounting procedures and practices and involve transactions relating to this agreement. The Contractor agrees to maintain these records for a period of six (6) years from the date of the termination of this agreement.

XI. JURISDICTION & VENUE This contract, amendments and supplements thereto, shall be governed by the laws of the State of Minnesota. All actions brought under this agreement shall be brought exclusively in Minnesota State Courts of competent jurisdiction with venue in Washington County.

XII. DAMAGE BY CONTRACTOR Any damage to the County’s property, building or equipment caused by the Contractor will be the Contractor’s responsibility to repair or pay for repairs/replacement of damaged items within a reasonable time frame established by the County.

XIII. INDEMNIFICATION The Contractor agrees it will defend, indemnify and hold harmless the County, its officers and employees against any and all liability, loss, costs, damages, and expenses which the County, its officers, or employees may hereafter sustain, incur, or be required to pay arising out of the negligent or willful acts or omissions of the Contractor in the performance of this agreement.

XIV. INSURANCE REQUIREMENTS The Contractor agrees that in order to protect itself, as well as the County, under the indemnity provisions set forth above, it will at all times during the term of this agreement, keep in force the following insurance protection in the limits specified: A. Commercial General Liability with contractual liability coverage in the amount of the County’s tort liability limits set forth in Minnesota Statute 466.04 and as amended from time to time. B. Automobile coverage in the amount of the County’s tort liability limits set forth in Minnesota Statute 466.04 and as amended from time to time. C. Worker’s Compensation in statutory amount.

Prior to the effective date of this agreement, the Contractor will furnish the County with a current and valid proof of insurance certificate indicating insurance coverage in the amounts required by this agreement. This certificate of insurance shall be on file with the County throughout the term of the agreement. As a condition subsequent to this agreement, Contractor shall ensure that the certificate of insurance provided to the County will at all times be current. The parties agree that failure by the Contractor to maintain a current certificate of insurance with the County shall be a substantial breach of the contract and payments on the contract shall be withheld by the County until a certificate of insurance showing current insurance coverage in amounts required by the contract is provided to the County.

Any policy obtained and maintained under this clause shall provide that it shall not be cancelled, materially changed, or not renewed without thirty days’ notice thereof to the County.

Washington County RFQ – Median Repair July 2021

XV. INDEPENDENT CONTRACTOR It will be agreed that nothing within the contract is intended or should be construed in any manner as creating or establishing the relationship of co-partners between the parties or as constituting the Contractor as the agent, representative, or employee of the County or the Public Works Department for any purpose or in any manner whatsoever. The Contractor is to be and shall remain an independent Contractor with respect to all services performed under this agreement.

The Contractor will secure, at its own expense, all personnel required in performing services under the agreement. Any and all personnel of the Contractor or other persons, while engaged in the performance of any work or services required by the Contractor under this agreement shall have no contractual relationship with the County or the Public Works Department and shall not be considered employees of the County or Public Works Department.

XVI. TERMINATION BY COUNTY FOR CONVENIENCE The County may terminate the contract at any time and for any reason by providing the Contractor written notice of such termination at least thirty (30) calendar days prior to the effective date of such termination. Upon such termination the Contractor shall be entitled to compensation for work activities in accordance with the contract which were incurred prior to the effective date of the termination.

XVII. DEFAULT Washington County shall have the right to cancel and annul this contract upon breach by Contractor of any covenant or condition herein.

XVIII. CHANGE IN SCOPE OF CONTRACT The County shall have the right to alter or cancel the contract due to area, task or budget changes subject to seven (7) calendar days written notice to the Contractor.

XIX. SERVICES BEYOND THE SCOPE OF THIS CONTRACT Any additional tasks added to this project must be by written amendment to this contract signed by both parties.

XX. MERGER It is understood and agreed that the entire agreement of the parties is contained here and that this contract supersedes all oral agreements and negotiations between the parties relating to this subject matter. All items referred to in this contract are incorporated or attached and deemed to be part of the contract.

XXI. CONTRACTOR DEBARMENT, SUSPENSION AND RESPONSIBILITY CERTIFICATION Federal Regulation 45 CFR 92.35 prohibits the County from purchasing goods or services with federal money from vendors who have been suspended or debarred by the federal government. Similarly, Minnesota Statutes, Section 16C.03, subdivision 2, provides the Commissioner of Administration with the authority to debar and suspend vendors who seek to contract with the County. Contractors may be suspended or debarred when it is determined through a duly authorized hearing process, that they have abused the public trust in a serious manner.

By signing this agreement, the Contractor certifies that it and its principals* and employees: A. Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from transacting business by or with any federal, state, or local governmental department or agency; and Washington County RFQ – Median Repair July 2021

B. Have not within a three year-period preceding this agreement: 1) been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain or performing a public (federal, state, or local government) transaction or contract, 2) violated any federal or state antitrust statutes, or 3) committed embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property; and C. Are not presently indicted or otherwise criminally or civilly charged by a governmental entity for: 1) commission of fraud or a criminal offense in connection with obtaining, attempting to obtain or performing a public (federal, state, or local government) transaction, 2) violating any federal or state antitrust statutes, or 3) committing embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property; and D. Are not aware of any information and possess no knowledge that any subContractor(s), that will perform work pursuant to this agreement, are in violation of any of the certifications set forth above; and E. Shall immediately give written notice to the contract manager should the Contractor come under investigation for allegations of fraud or a criminal offense in connection with obtaining or performing a public (federal, state, or local government) transaction, violating any federal or state antitrust statute, or committing embezzlement, theft, forgery, bribery, falsification of records, making false statements, or receiving stolen property.

*Principals, for the purpose of this certification, means officers, directors, owners, partners, and persons having primary management or supervisory responsibilities within a business entity (e.g., general manager, plant manager, head of subsidiary division or business segment, and similar positions)

XXII. PREVAILING WAGES It shall be a requirement of this contract that the Prime Contractor and his subs pay the State prevailing wage rate to workers utilized on this project. A copy of the Prevailing Wage rate is hereto attached and made part of the specifications.

Appendix B Removal Plan

Median on the west leg of County Highway 16 and Interlachen Parkway

Appendix B Construction Plan

Median on the west leg of County Highway 16 and Interlachen Parkway

Appendix B

Removal and Construction Plan

Median on the east leg of County Highway 16 and Interlachen Parkway Appendix B

For Information Only Appendix B DIRECTION OF TRAFFIC DIRECTION OF TRAFFIC

15.0' 15.0' 15.0' 15.0'

EDGE OF PAVEMENT B EDGE OF PAVEMENT C 1 R M E U ETE D M ' L I 6 CR L1TU, L2KTU, OR L2TU L1TU, L2KTU, OR L2TU 2018 AX - HOU ON M S C R P A - ' 4 12 : D E S I V E R 18'' MIN. NO. 4 TIE BARS AT 3' SPACING 18'' MIN.

/ L1TU L1TU

D < FOR t 10-1/2'' NO. 5 TIE BARS AT 3' SPACING TTE L

O FOR t 10-1/2'' A L C I P P Y T

L1TU L1TU '

W < 27

18'' MIN. NO. 4 TIE BARS AT 3' SPACING 18'' MIN. R

O FOR t 10-1/2''

'

' NO. 5 TIE BARS AT 3' SPACING 24 12 FOR t 10-1/2''

DOWEL BAR ASSEMBLIES SEE STANDARD PLAN 5-297.221 FOR DOWEL BAR DIAMETER L2KTU OR L2TU L2KTU OR L2TU

C1U-D C1U-D

dgn DOWEL BAR ASSEMBLIES .

pn SEE STANDARD PLAN 5-297.221 s FOR DOWEL BAR DIAMETER '

EDGE OF PAVEMENT 12 217_2_ B C1U-D C1U-D s \ s e i r e

S MAINLINE PAVEMENT WITH INSIDE CONCRETE SHOULDER 200_ \

r DOWELED e d

r EDGE OF PAVEMENT o C B

w e N

t\ MAINLINE PAVEMENT URBAN n

e <

m 6' 0'' MAX 13' 0'' 14' 0'' ( DRIVERS RIGHT ) 4 LANE DIVIDED - 27' WIDE DOWELED op l CONCRETE SHOULDER 12' 0'' 12' 0'' 2 WAY TRAFFIC - 24' WIDE e

v 13' 6'' 13' 6''

e 2 WAY TRAFFIC - 27' WIDE L1TU, D \

s L2KTU, L1TU 1/2'' R. PE SLOP d SLO E

r OR L2TU a

nd t a t < S TIE BAR t/2 ` 1'' 12' 0'' 12' 0" 12' 0" TIE BAR t/2 ` 1'' gn i s e D \ S pn

T L1TU L2KTU OR L2TU s SLOPE SLOPE 1/2'' R. O SECTION B-B SLOPE :

E t M 217_2_ s

NA GENERAL NOTES: TIE BAR t/2 ` 1'' TIE BAR t/2 ` 1'' : LE I E 1 CONTACT THE CONCRETE ENGINEER TO DISCUSS WHETHER

F SEE TYPICAL SECTIONS AND PLAN SHEETS FOR CROSS M

SLOPES AND PAVEMENT THICKNESS, t. TIE BARS AND SAWED JOINTS ARE NEEDED BASED ON & NA CONCRETE SHOULDER WIDTH AND DEPTH.

T H DOWEL BAR ASSEMBLIES, WHEN REQUIRED, SHALL BE SECTION C-C O T

L SIMILAR TO THOSE SHOWN ON STANDARD PLATE 1103. A P P I ALL REINFORCING BARS SHALL BE EPOXY COATED AND COMPLY WITH SPEC. 3301.

FOR SUPPLEMENTAL PAVEMENT REINFORCEMENT, SEE STANDARD PLATE 1070.

STANDARD PLAN 5-297.217 2 OF 2 CONCRETE MAINLINE PAVEMENT REVISION: APPROVED: 2-16-2016 15.0 FT. PANEL LENGTH APPROVED: FEBRUARY 16, 2016 REVISED: URBAN OR CONCRETE SHOULDERS

DEPARTMENT OF STATE PROJ. NO. (T.H. ) SHEET NO. OF SHEETS DIRECTOR, OFFICE OF MATERIALS AND ROAD RESEARCH TRANSPORTATION STATE DESIGN ENGINEER Appendix B Appendix B Appendix B

SEE WASHINGTON COUNTY STANDARD PLATE WC-403 FOR CASTING ASSEMBLY TYPE

HIGH DENSITY POLYETHYLENE (HDPE) ADJUSTMENT RINGS. TOP RING SHALL BE SOLID WITH NO VOIDS. PLACE A CONTINUOUS 1/2" BEAD OF BUTYL SEALANT AROUND THE BOTTOM OF THE FIRST RING PRIOR TO PLACING ON CONCRETE TOP SLAB AND CATCH BASIN AROUND THE BOTTOM OF EACH STRUCTURE WITH SUSBSEQUENT RING PRIOR TO TOP SLAB OR PLACEMENT. 2' X 3' BOX.

COLLAR TO BE ENCASED IN CONCRETE SEE WASHINGTON COUNTY STANDARD PLATE WC-403

SEE WASHINGTON COUNTY STANDARD PLATE WC-403 FOR CASTING ASSEMBLY TYPE

30 INCH ROUND HIGH DENSITY POLYETHYLENE (HDPE) ADJUSTMENT RINGS. TOP RING SHALL BE SOLID WITH NO VOIDS. PLACE A CONTINUOUS 1/2" BEAD OF BUTYL SEALANT AROUND THE BOTTOM OF THE FIRST RING PRIOR TO PLACING ON CATCH BASIN STRUCTURE WITH CONCRETE TOP SLAB AND TOP SLAB OR AROUND THE BOTTOM OF EACH 2' X 3' BOX. SUSBSEQUENT RING PRIOR TO PLACEMENT.

LAST REVISION:

CATCH BASIN ADJUSTMENT OCTOBER 2020 (HIGH DENSITY POLYETHYLENE RINGS) PLATE NO.

WC-400 Appendix B EXPANSION JOINT

C&G

ONE NO. 4 BY 5-FOOT LONG BAR PLACED THROUGH LUG HOLES.

CONCRETE COLLAR C&G TYPE TYPE OF CASTING

NEENAH R-3067-V, TYPE 'V' B418/B618 C&G GRATE OR APPROVED EQUAL

NEENAH R-3234-B1, TYPE 'R' B424/B624 EXPANSION GRATE OR APPROVED EQUAL JOINT

PLAN P

PAVEMENT SURFACE M U S

ONE NO. 4 BY 4" 5-FOOT LONG BAR PLACED 4" BUTYL SEALANT THROUGH LUG BETWEEN CASTING, HOLES. RINGS AND STRUCTURE 4" 4" 6" MAX.

CONCRETE COLLAR TO ENCASE CASTING AND HDPE ADJUSTING MANHOLE OR RINGS. USE CONCRETE CURB & CATCH BASIN GUTTER MIX, OR MORTAR MIX (SPEC. 2506.2B) FOR COLLAR. MORTAR MIX SHALL BE AIR-ENTRAINED OR REINFORCED. SECTION

LAST REVISION:

CONCRETE ENCASED OCTOBER 2020

HDPE ADJUSTING RINGS PLATE NO.

WC-403 Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page i

INDEX--SP2018BOOK

SP2018# ITEM# DATA PAGE

S-1 RESPONSIBLE CONTRACTOR ...... 4 SP2018-6 - MODIFIED ...... 4 S-2 COMPLIANCE WITH TAX LAW REQUIREMENTS ...... 4 SP2018-7 ...... 4 S-3 USE OF ADHESIVE ANCHORS ...... 5 SP2018-11 ...... 5 S-4 SUBMISSION OF PAYROLLS AND STATEMENTS ...... 5 S-5 (1103) DEFINITIONS ...... 6 SP2018-16 ...... 6 S-6 (1211) CONDITIONAL PROPOSALS ...... 6 S-7 (1302) AWARD OF CONTRACT ...... 6 SP2018-19 - MODIFIED ...... 6 S-8 (1306) EXECUTION AND APPROVAL OF CONTRACT ...... 6 SP2018-20 ...... 6 S-9 (2563) TEMPORARY TRAFFIC MANAGEMENT ...... 7 SP2018-20.1 - MODIFIED ...... 7 S-10 (2562) ADDITIONAL TRAFFIC CONTROL DEVICES AND EXTENDED USE OF TRAFFIC CONTROL DEVICES ...... 14 SP2018-20.2 ...... 14 S-11 (1505) COOPERATION BY CONTRACTORS ...... 17 SP2018-22 - MODIFIED ...... 17 S-12 (1507) UTILITY PROPERTY AND SERVICE ...... 17 SP2018-24 - MODIFIED ...... 17 S-13 (1508) CONSTRUCTION STAKES, LINES, AND GRADES ...... 18 SP2018-26 ...... 18 S-14 (1517) CLAIMS FOR COMPENSATION ADJUSTMENT ...... 18 S-15 (1606) STORAGE OF MATERIALS ...... 21 SP2018-33 ...... 21 S-16 (1701) LAWS TO BE OBSERVED (PROMPT PAY AND RETAINAGE) ...... 21 SP2018-33.1 ...... 21 S-17 (1701) LAWS TO BE OBSERVED (WET LANDS) ...... 22 SP2018-34 ...... 22 S-18 (1701) LAWS TO BE OBSERVED – CERTIFICATION OF NONDISCRIMINATION AGAINST ISRAEL ...... 22 SP2018-40 ...... 22 S-19 (1706) EMPLOYEE HEALTH AND WELFARE ...... 22 SP2018-41 ...... 22 S-20 (1707) PUBLIC CONVENIENCE AND SAFETY ...... 23 SP2018-42 - MODIFIED ...... 23 Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page ii

S-21 (1801) SUBLETTING OF CONTRACT ...... 23 SP2018-49 ...... 23 S-22 (1802) TRAINING FOR CONSTRUCTION TRUCK OPERATORS ...... 24 SP2018-50 ...... 24 S-23 (1803) PROGRESS SCHEDULES ...... 24 SP2018-51 - MODIFIED ...... 24 S-24 (1804) LIMITATION OF OPERATIONS - NIGHT CONSTRUCTION ...... 24 SP2018-53 ...... 24 S-25 (1806) DETERMINATION AND EXTENSION OF CONTRACT TIME ...... 25 SP2018-54 - MODIFIED ...... 25 S-26 (1807) FAILURE TO COMPLETE THE WORK ON TIME ...... 26 SP2018-56 ...... 26 S-27 (1902) SCOPE OF PAYMENT ...... 26 SP2018-56.1 ...... 26 S-28 (1906) OUT-OF-STATE CONTACTOR ...... 27 S-29 (1906) PARTIAL PAYMENTS ...... 27 S-30 (2104) REMOVING PAVEMENT AND MISCELLANEOUS STRUCTURES ...... 27 SP2018-76 ...... 27 S-31 (2104) REMOVING PIPE SEWERS AND CULVERTS ...... 27 S-32 (2104) ABATE ASBESTOS-CONTAINING PIPES OR CULVERTS ...... 27 SP2018-80 ...... 27 S-33 (2106) EXCAVATION AND EMBANKMENT ...... 29 SP2018-103 – MODIFIED ...... 29 S-34 (2211) AGGREGATE BASE ...... 32 SP2018-107.1 ...... 32 S-35 (2301) CONCRETE PAVEMENT ...... 32 SP2018-124 ...... 32 S-36 (2301) AND GROUT DOWEL BAR (EPOXY COATED) ...... 38 SP2018-125 ...... 38 S-37 (2461) STRUCTURAL CONCRETE ...... 38 SP2018-156 ...... 38 S-38 (2472) METAL REINFORCEMENT ...... 60 SP2018-158.1 ...... 60 S-39 (2503) CONNECT TO EXISTING STORM SEWER ...... 61 SP2018-171 ...... 61 S-40 (2506) MANHOLES AND CATCH BASINS ...... 61 S-41 (2521) WALKS ...... 62 SP2018-188.3 ...... 62 S-42 (2531) CONCRETE CURB AND GUTTER (ADA) ...... 62 SP2018-190 ...... 62 S-43 (2565) RIGID PVC LOOP DETECTOR ...... 63 S-44 (2582) PAVEMENT MARKINGS ...... 64 SP2018-250 - MODIFIED ...... 64 Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page iii

S-45 (3105) BAGGED PORTLAND CEMENT CONCRETE PATCHING MIX GRADE 3U18 AND 3U18M ...... 65 SP2018-251 ...... 65 S-46 (3131) INTERMEDIATE AGGREGATE FOR PORTLAND CEMENT CONCRETE ...... 67 SP2018-252 ...... 67 S-47 (3137) COARSE AGGREGATE FOR PORTLAND CEMENT CONCRETE ...... 68 SP2018-252.1 ...... 68 S-48 (3138) AGGREGATE FOR SURFACE AND BASE COURSES ...... 69 SP2018-252.2 ...... 69 S-49 (3149) GRANULAR MATERIAL ...... 71 SP2018-253.1 ...... 71 S-50 (3236) REINFORCED CONCRETE PIPE ...... 71 SP2018-255 ...... 71 S-51 (3301) REINFORCEMENT BARS ...... 71 SP2018-258 ...... 71 S-52 (3302) DOWEL BAR ...... 72 SP2018-259 ...... 72

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 4

DIVISION S

S-1 RESPONSIBLE CONTRACTOR SP2018-6 - MODIFIED The Department cannot award a construction contract in excess of $50,000 unless the bidder is a “responsible contractor” as defined in Minnesota Statutes §16C.285, subdivision 3.

A bidder must verify it meets the minimum criteria detailed in the law. A bidder must submit its verification electronically by completing the “Responsible Contractor Verification and Certification of Compliance”. A company officer must certify statements in that section. Bidders only need to complete the electronic verification; DO NOT email, fax, or send paper forms to the Department. The Department will not accept emailed, faxed or other paper submissions and will only accept electronic verifications.

A bidder must obtain a verification from each subcontractor it will have a direct contractual relationship with. A bidder must submit signed subcontractor verifications. A contractor or subcontractor must obtain an annual verification from each motor carrier it has a direct contractual relationship with. A motor carrier must give immediate written notice if it no longer meets the minimum responsible contractor criteria. The requirement for subcontractor verifications does not apply to:

• Design professionals licensed under Minnesota Statutes §326.06; and • A business or person that supplies materials, equipment, or supplies to a subcontractor on the Project, including performing delivering and unloading services in connection with the supply of materials, equipment, and supplies. But, a business or person must submit a verification if it delivers mineral aggregate such as sand, gravel, or stone that will be incorporated into the Work by depositing the material substantially in place, directly or through spreaders, from the transporting vehicle.

A bidder or subcontractor who does not meet the minimum criteria specified in the statute, or who fails to verify compliance with the criteria, is not a “responsible contractor” and is ineligible to be awarded the Contract for this Project or to work on this Project. Submitting a false verification makes the bidder or subcontractor ineligible to be awarded a construction contract for this Project. Additionally, submitting a false statement may lead to contract termination. If only one bidder submits a bid, the Department may, but is not required to, award a contract even if that bidder does not meet the minimum criteria.

S-2 COMPLIANCE WITH TAX LAW REQUIREMENTS REVISED 08/09/19 SP2018-7 The Department cannot make final payment to the Contractor until the Contractor demonstrates that it and all its subcontractors have complied with the Income Tax withholding requirements of Minnesota Statutes, section 290.92 for wages paid for work performed under the contract. To establish compliance, the Contractor must submit a “Contractor Affidavit” either online or in paper form (IC134) to the Minnesota Department of Revenue. The contractor will receive written certification of compliance when the Department of Revenue determines that all withholding tax returns have been filed and all withholding taxes attributable to the work performed on the contract have been paid. The Contractor must then provide this written certification to the Department to receive final payment.

Every subcontractor working on the Project must submit an approved “Contractor Affidavit” from the Minnesota Department of Revenue to the Contractor before the Contractor can file its own Contractor Affidavit. The Contractor is advised to obtain the certification from each subcontractor as soon as the subcontractor completes work on the Project. Experience has shown that waiting until the project is complete to obtain the forms from all subcontractors is likely to result in significant additional work for the Contractor as it will be difficult or impossible to collect all forms.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 5

The Department of Revenue, in association with the Department of Employment and Economic Development, offers a free seminar to help contractors understand tax law requirements. The Department strongly urges the Contractor and all subcontractors to attend the “Employment Taxes & Employer Responsibilities Seminar” or similarly offered classes.

Complying with this requirement is considered part of the Work under this contract. The Department will enforce this requirement equally with all other Contract requirements. Contractor delay in complying with this requirement will cause the Department to delay final payment and Contract Acceptance. The Department may also report non-compliance to the Department of Revenue, which may result in enforcement action by the Department of Revenue.

S-3 USE OF ADHESIVE ANCHORS SP2018-11 Do not use adhesive anchors in sustained tension. Contractor may use adhesive anchors, in a non- direct tensile application, such as metal rail attachment.

S-4 SUBMISSION OF PAYROLLS AND STATEMENTS These provisions govern: (1) how the Contractor and all subcontractors must submit all certified payroll reports; (2) how the Contractor must submit subcontractor data; and (3) how the Contractor and subcontractors will demonstrate compliance with payment requirements.

S-4.1 SUBMISSION REQUIREMENTS Paper copies of all Certified Payroll documentation, certified payroll reports (CPRs), EEO forms, Apprenticeship Certificates, and Month End Trucking Reports must be sent via mail or hand delivered to:

Washington County Public Works Attn: Rachelle Goodall 11660 Myeron Road North Stillwater MN, 55082

All submitted documentation must include the project number and/or project title.

Electronic submission, including email, will not be accepted and will be deleted by the County.

The Department will not provide additional compensation to ensure compliance with these provisions.

S-4.2 REQUEST TO SUBLET FORMS The Contractor must submit Request to Sublet data via mail or hand delivery and in accordance with MnDOT 1801.

Contractors are responsible for checking the status of all subcontractors, Multiple Trucking Operators (MTO), and Independent Trucking Operators (ITO) for possible suspension or disbarment before submitting Request to Sublet forms.

MTOs shall use the MTO Request to Sublet form, available at: http://www.dot.state.mn.us/const/labor/documents/forms/mtosubletform.pdf.

The Contractor is responsible to ensure that each subcontractor, MTO, and ITO is listed in the MnDOT vendor system, which is located at http://transport.dot.state.mn.us/reference/refvendor.aspx.

• If a subcontractor is not in MnDOT’s vendor system, the Contractor is responsible to have the subcontractor complete and submit the MnDOT Contractor/Vendor form to [email protected]. The form is located at https://edocs- public.dot.state.mn.us/edocs_public/DMResultSet/download?docId=12203526. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 6

• If an MTO or ITO is not in MnDOT’s vendor system the Contractor is responsible to have them complete and submit the Trucking Entity Vendor form to [email protected]. The form is located at http://www.dot.state.mn.us/const/labor/documents/forms/truckvendorform2016.pdf.

S-4.3 CERTIFIED PAYROLL & SUBCONTRACTOR DATA SUBMISSION

When identifying an employee on any payroll document, provide no more than the last four digits of that employee’s social security number. Documentation submitted with full social security numbers will be considered not received by the County and will be destroyed in accordance with the Minnesota Government Data Practices Act.

Provide hours worked on this project only on certified payroll reports.

The Engineer may at any time require, upon written demand, paper certified payroll reports from any contractor(s) working on the Project.

S-5 (1103) DEFINITIONS SP2018-16 The provisions of MnDOT 1103 are supplemented as follows:

S-5.1 The following definition is added to MnDOT 1103:

Unit Day. 12:00 AM to 11:59 PM (0000-2359) or any portion thereof.

S-6 (1211) CONDITIONAL PROPOSALS

S-6.1 Delete MNDOT 1211 and replace with the following:

Combination or Conditional Proposals are not allowed.

S-7 (1302) AWARD OF CONTRACT REVISED 09/12/19 SP2018-19 - MODIFIED Contract Award must be in accordance with the provisions of MnDOT 1302 and the following:

S-7.1 The first paragraph of MnDOT 1302 is deleted and replaced with the following:

Within 40 calendar days after opening Proposals, the Department will Award the Contract to the lowest responsible Bidder provided that the lowest responsible Bidder complies with the Proposal requirements. The Department may also decide not to make a Contract Award. The Department will notify the lowest responsible Bidder electronically, in writing, or by other means that the Department has accepted the Proposal subject to execution and approval of the Contract as required by law.

The Department and the lowest responsible Bidder may mutually agree to extend the time within which the Department makes the Award.

S-8 (1306) EXECUTION AND APPROVAL OF CONTRACT SP2018-20 The provisions of MnDOT 1306 are modified by substituting the following paragraph for the first paragraph of 1306:

The lowest responsible Bidder shall sign and return the Contract with the required Payment and Performance Bonds no later than three business days after Award.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 7

S-9 (2563) TEMPORARY TRAFFIC MANAGEMENT REVISED 02/14/20 SP2018-20.1 - MODIFIED

S-9.1 DESCRIPTION Furnish, install, maintain, and remove all traffic control devices required to provide safe movement of traffic and pedestrians through the Project at all times from commencement of the Work until Project Acceptance. Maintain roads and pedestrian facilities undergoing improvements in a condition that accommodates public traffic. Do not close roads or pedestrian facilities, except as authorized. The Engineer may modify the requirements for traffic control as deemed necessary.

The Department will maintain Detour Roads for through traffic diverted from the project unless otherwise indicated in the Plan.

The use of maintenance crossovers in or near the construction area is permitted if authorized by the Engineer.

All temporary traffic management must conform to and be installed in accordance with:

• the "Minnesota Manual on Uniform Traffic Control Devices" (MN MUTCD); • the "Minnesota Temporary Traffic Control Field Manual" (Field Manual); • the "Speed Limits in Work Zones Guidelines"; • the "Minnesota Flagging Handbook"; • the "MnDOT Standard Signs and Markings Manual"; • the Plan; • all applicable standard specifications and special provisions. Manuals listed above may be found at: http://www.dot.state.mn.us/trafficeng/publ/index.html

S-9.2 MATERIALS

A Temporary Signs and Devices Reflectorize all signs, paddles, and other traffic control devices including those used for daytime operations. Fabricate temporary rigid signs and devices with retroreflective sheeting material of the appropriate color listed on the Approved/Qualified Products List (APL/QPL) for either “Sheeting for Rigid Temporary Work Zone Signs, Delineators, and Markers (Type IX and XI)” or “Sheeting for Rigid Permanent Signs, Delineators, and Markers (Type IX and XI)”. The sheeting materials APL/QPL is located at the following link: http://www.dot.state.mn.us/products/signing/sheeting.html.

Inplace signs that still apply during temporary operations need no change in sign sheeting.

B Vehicle Conspicuity Tape The Approved Products List for “Conspicuity Vehicle Sheeting (Type VII)” is found at: http://www.dot.state.mn.us/products/signing/sheeting.html

C Truck/Trailer Mounted Attenuators The Approved Products List for “Mobile Crash Attenuators” is found at: http://www.dot.state.mn.us/products/temporarytrafficcontrol/mobilecrashattenuators.html

D Drum Sheeting On Projects requiring drums per MnDOT Standard Plate No. 8000J (Channelizers – Type B), provide all drums with six inch fluorescent orange and white sheeting material with no gap between sheeting layers.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 8

E Crashworthy Signs, Traffic Control Devices, and Ballast Signs and traffic control devices must be crashworthy and meet the crash testing requirements of the AASHTO Manual for Assessing Safety Hardware 2016 (MASH-16). The Department may require a letter of compliance stating that all signs and traffic control devices comply with MASH-16 requirements. The Letter of Compliance must include drawings of the different signs and devices along with a copy of the FHWA issued Letter of Eligibility or MnDOT MASH Crashworthy Evaluation.

See MnDOT Technical Memorandum No. 19-03-T-01 for information and timelines on the allowable use of crashworthy devices tested under NCHRP-350. https://techmemos.dot.state.mn.us/techmemo.aspx

The approved ballast system for signs and devices mounted on temporary portable supports is sandbags, unless it is designed, crash tested, and approved for the specific device. Add a deicer during freezing conditions to prevent the sand from freezing. Place sandbags at the base of the sign or traffic control device. Do not use any ballast that causes a sign or traffic control device to become hazardous to motorists or workers.

S-9.3 CONSTRUCTION REQUIREMENTS

A Traffic Control Plan, Maintenance, and Inspection

A.1 Submit a proposed traffic control plan to the Engineer for acceptance if traffic control is not present in the Plan, or if the Contractor modifies the traffic control plan. Submit the proposed traffic control plan at least seven days before implementation. If Field Manual layouts are used, specify layout number(s) but do not submit the layouts from the Field Manual. Do not implement the proposed traffic control modification until accepted by the Engineer.

A.2 Immediately repair or replace all traffic control devices that become damaged, moved or destroyed, and all ballasts that are damaged, destroyed, or otherwise fail to stabilize the device.

A.3 Meet the traffic control device quality standards as required in the Field Manual. Immediately replace unacceptable traffic control devices. Signs that are dirty and result in a noticeable loss of reflectivity at night are considered unacceptable and must be cleaned or replaced. Respond promptly to any call from the Engineer concerning the notification of unacceptable traffic control devices.

A.4 Provide the names, addresses, and phone numbers of at least three individuals responsible for placing and maintaining traffic control devices to the Engineer at the Pre-construction Conference. These individuals will be "on call" 24 hours per day, seven days per week during the times any temporary traffic control devices are in place.

A.5 Inspect all traffic control devices on a daily basis, including one nighttime inspection per week. Verify that the devices are placed in accordance with the Traffic Control Plan, these Special Provisions, and the MN MUTCD. Immediately correct discrepancies between the actual placement and the required placement. Respond immediately to any call from the Engineer concerning any request for improving or correcting traffic control devices.

A.6 Make a daily log of required inspections. This log must indicate the date and time any changes in the stages, phases, or portions go into effect. The log must identify the location and verify that the devices are placed as directed or corrected in accordance with the Plan. The person making the inspection must sign the log and include the date and time of the entry. Provide copies of the inspection logs on a weekly basis and at the request of the Engineer.

B Traffic Control Signs and Devices

B.1 Roll-up signs are not allowed unless authorized by the Engineer.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 9

B.2 Cover, modify, or remove all signs that are not consistent with traffic operations. Cover the entire sign or that part of the legend that is inappropriate. Sign covers must conform to the Typical Temporary Sign Covering Details Sheet found in the Plan or at the following link: http://www.dot.state.mn.us/trafficeng/workzone/wz-templets/pdf/layout%2020A.pdf

B.3 Maintain street identification signage at all times. Signs may be installed on temporary supports if the permanent sign structures are affected by operations. This is necessary to maintain the 911 emergency system.

B.4 Signs shall have an easily identifiable marking on the face to make the identification of approved retroreflective sign sheeting on temporary rigid signs in the field easier. This marking verifies that the sign sheeting has been approved for Rigid Signs. Temporary rigid signs four-square feet and under in size and all barricades and route markers will be exempt from this marking. The appropriate marking shall be used for each type of approved sheeting types. Refer to the instruction for the marking of temporary signs that are on the MnDOT Approved Products List or directly at the following link: http://www.dot.state.mn.us/products/signing/pdf/typelabel.pdf.

The retroreflective sheeting types and qualified products used for temporary signs and barricades are found in the MnDOT Approved Products List at http://www.dot.state.mn.us/products/signing/sheeting.html

B.5 Post mount all signs that will remain in the same location for more than 30 consecutive days. This does not include portable signs which are set up and taken down at the beginning and end of each work shift.

When the proper location of a sign is on pavement, do not core through the surface. If there is a conflict with underground utilities, attempt to move the sign while maintaining its visibility to traffic. If it is not possible to drive posts into the ground, mount signs on portable supports as approved by the Engineer.

When signs are removed, the sign posts and stub posts must also be removed from the right of way. Posts left in place for future use or removal at a later date must be properly delineated with tubular markers, flags, or other delineation as approved by the Engineer at no additional cost.

B.6 All in place signs and delineators that interfere with the Contractor's normal operation SHALL be temporarily relocated by the Contractor at the direction of the Engineer. Store salvaged signs in such a manner as to protect the sign from scratching, fading, or other harmful effects until the signs are reinstalled. After completing work at each sign location, or at the direction of the Engineer, replace the signs as near to their original locations as possible or to a location designated by the Engineer. Reinstall sign structures according to the Type C & D Sign Structural Details Sheet located at the following link: http://www.dot.state.mn.us/trafficeng/signing/plansheets/groundmounted.pdf

Signs and structures damaged by the Contractor shall be replaced at the Contractor’s expense.

All costs incurred to relocate, salvage, and reinstall in-place signing shall be incidental work.

C Traffic Safety

C.1 Do not suspend material, equipment, tools or personnel over lanes or pedestrian facilities open to traffic.

C.2 Do not place bridge deck concrete over lanes open to traffic or over active pedestrian facilities.

C.3 Protect traffic and pedestrians from excavations, drop-offs, falling objects, splatter or other potential construction hazards. This work shall be incidental.

C.4 Do not store materials or equipment in the work zone clear zone unless approved by the Engineer. If materials or equipment must be stored within the work zone clear zone, protect with temporary barrier. If the Engineer agrees that temporary barrier is not practical, delineate with Type B channelizers.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 10

C.5 Do not park vehicles or construction equipment in the clear zone or any location that obstructs traffic control devices. Workers are not allowed to park their private vehicles within the Project limits unless approved by the Engineer.

C.6 Do not load or unload material or equipment on the shoulders of any roadway without a full shoulder closure using signs and channelizing devices shown on Layout 8 in the Field Manual. Note 1 of Layout 8 of the Field Manual is hereby deleted. The contractor will not be allowed to load or unload material or equipment on the shoulders of the roadway without a full shoulder closure using appropriate signs, barricades, and channelizing devices.

C.7 Open excavation adjacent to the existing pavement will not be permitted on opposite sides of the roadway at the same time.

D High Visibility Apparel During night work or low light conditions, all workers must wear high visibility Class E long pants and retro-reflective headgear in addition to the ANSI Class 2 or 3 vest, , or jacket.

All high visibility apparel must be worn in the manner for which it was designed. All apparel worn on the torso must be closed in the front to provide 360 degree visibility. A worker’s high-visibility apparel must be removed from service and replaced if it becomes faded, worn, torn, dirty, or defaced, reducing the conspicuity of the apparel.

E Night Work Night work is not permitted on this project without prior approval of the Engineer.

F Vehicle Warning Light Specification All vehicles and equipment operating within the limits of the Project must have operable warning lights that are amber in color and meet the appropriate SAE specification. The SAE specification requirements are as follows:

• Optical Warning Devices for Authorized Emergency, Maintenance, and Service Vehicles- SAE Specification J845. • Directional Flashing Optical Warning Devices for Authorized Emergency, Maintenance, and Service Vehicles - SAE Specification J595.

Details on SAE Specification can be found at: http://www.dot.state.mn.us/const/wzs/lighting.html

G Lane Closure Requirements

G.1 Temporary lane closures or other traffic restrictions by the Contractor, during work hours and consistent with the time restrictions, will be permitted only during those hours and at those locations approved by the Engineer. Request temporary lane closures at least two business days prior to the closure.

G.2 If the Contractor fails to adhere to the established time schedules, the Department may assess a monetary deduction of $500.00 per hour for each hour or portion of an hour that the Engineer determines that the Contractor has not complied.

G.3 Place traffic control devices in any temporary lane closure that is adjacent to traffic and extends beyond 1000 feet as shown on Layout 61 of the Field Manual. When the lane closure is in place three days or longer, use only Type III barricades.

G.4 Use Drum Channelizers in all lane closure tapers and in any shifts in traffic alignment.

G.5 No center lane closures will be permitted. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 11

H Use of Road Closure Signage All signing for road closures and restrictions shall conform to the requirements of the MnMUTCD and the following:

H.1 “ROAD CLOSED” (R10-2) signs shall be placed only at locations where ALL public traffic is prohibited beyond the location of the sign, including all local traffic and residents within the project area. Only project staff and authorized emergency responders shall be permitted beyond R10-2 sign locations.

H.2 “ROAD CLOSED” (R10-2) signs shall not be installed at locations where traffic is shifted to the left side of an inplace median unless the median separating opposing directions of traffic is greater than 20-feet in width as measured from the edges of the lanes closest to the median.

H.3 “ROAD CLOSED TO THROUGH TRAFFIC” (R11-4) signs shall be placed only at location in advance of properly placed “ROAD CLOSED” (R10-2) signs, to inform motorists that travel beyond the R11-4 sign is allowed but that no lawful outlet beyond the sign exists.

H.4 “ROAD CLOSED / XX MILES AHEAD / LOCAL TRAFFIC ONLY” (R3-11a) signs may be placed at locations in advance of properly placed “ROAD CLOSED” (R11-4) signs beyond which through traffic is possible via other public streets not affected by the downstream closure.

H.5 “ROAD CLOSED AHEAD (W20-3) signs, when used, shall not be placed more than 700 feet in advance of properly placed “ROAD CLOSED” (R10-2) signs unless otherwise required by the project plans or as approved by the Engineer.

H.6 Black on Orange “NO OUTLET” (W14-2) signs may be installed beyond properly placed R11-4 or R11-3a signs as a supplementary warning to motorists that they are entering a road or road network from which there is no other exit.

Deviation from the requirements of this section are not permitted unless authorized by the Engineer.

I Truck/Trailer Mounted Attenuators (TMAs) For Mobile/Short Duration Operations Truck/Trailer Mounted Attenuators (TMA) must be used on all shadow and protection vehicles operating totally or partially in a traffic lane if any temporary traffic control zone is defined as “Mobile/Short Duration” by the Field Manual. All references to “should” in the Field Manual in regards to TMA use for Mobile/Short Duration layouts are hereby changed to “shall”. This requirement applies to all operations utilizing Field Manual layouts 9, 10, 12, 13, 36, 41, 49, 50, 51, 54, 55, 63, 76, 77, 78, and 79. Providing TMAs for “Mobile/Short Duration” work zones is incidental.

J Flagging Operations

J.1 Flaggers must attend a training session taught by a MnDOT-Qualified Flagger Trainer. The trainer must have completed a “MnDOT Flagger Train the Trainer Session” within the last five years and be on file as a qualified Trainer with MnDOT. Provide the Flagger Trainer’s name and qualification number at the pre- construction meeting. Provide all flaggers with the MnDOT Flagging Handbook. Flaggers must be in possession of the handbook while flagging on the Project. Furnish the signed “Checklist for Flagger Training” or “Flagger Qualification Card” to the Engineer any time a new flagger reports to work on the Project. The “Checklist for Flagger Training” and other forms and information is found at: http://www.dot.state.mn.us/const/wzs/flagger.html

J.2 The Contractor shall furnish flag persons as required to adequately control traffic. Flag persons shall conform to the requirements set forth in the MnMUTCD.

J.3 Flagging will not be permitted unless all requirements on this section are met, including signing, clothing, training, and radio communications. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 12

J.4 Flag persons shall wear high visibility retroreflective safety vests, pants, and hats at all times when actively flagging. High visibility apparel shall also comply with current Minnesota OSHA rules. Required flag persons clothing shall be considered incidental.

J.5 The Contractor shall keep the separation distance between the last sign in the “Flagger Ahead” signing sequence and the actual flagger to the amount shown in the Field Manual, whenever it is practical. The maximum separation distance allowed from the signs to the flagger shall be ½-mile. The Contractor shall use multiple flagger signing set-ups or continuously move the singing for moving flagging operations to keep within the distance limit.

J.6 All signs associated with the flagging operation must be removed or covered when flagging operations are not present.

J.7 Coordinate the flagging operations in a manner that causes minimum delay to the traveling public. The maximum delay time is 3 minutes. If the operation exceeds the maximum delay time, the operation must be discontinued until a new traffic control plan is developed which meets the maximum delay requirement.

J.8 Flaggers must be properly uniformed and have a STOP/SLOW sign with a five foot minimum staff. Multiple Flaggers must be able to see each other or be equipped with two-way radios.

J.9 Except as authorized by the Engineer, the maximum length of the flagging operations shall be no more than ½-mile.

J.10 Qualified flaggers will safely provide for traffic control in such numbers and for such work operations as determined by the Engineer. Furnish Flaggers in sufficient quantity to control each approach to the work area including intersecting crossroads that are open to traffic. Flaggers will not override a fully operating signal system. See the Minnesota Flagging Handbook for additional requirements and procedures.

L Signal Systems

L.1 Do not interfere with the operation of any traffic signal system, except as required by the Contract. Notify the Engineer at least 24 hours prior to beginning any work that will interfere with any traffic signal system or its detection system.

L.2 The in place signal system(s) must remain in operation until the new signal system(s) become operational.

M Street Lighting

M.1 The Contractor shall maintain street lighting by means of in-place lights, the newly constructed lights, or a combination thereof, except as otherwise authorized in writing by the Engineer.

N Maintenance and Staging of Traffic Control - General

N.1 Pedestrian traffic must be maintained and guided through the Project at all times to a degree that matches the level of accessibility of the pre-construction conditions.

Provide continuous temporary walkway surfaces that are smooth, stable and slip resistant in relevant weather conditions. Temporary walkway surfaces will allow the normal usage of wheelchairs, walkers, strollers, and other mobility devices.

N.2 The Contractor shall cover all signs that are not consistent with traffic operations. The cover shall be a plate of solid material covering the entire legend or all of that part of the legend that is inappropriate. Bolt the cover to the sign and place a minimum of 1/8-inch spacers (such as plastic or rubber) between the sign face and the cover. See the Typical Temporary Sign Framing and Installation Details Sheet found in the Plan. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 13

N.3 The Contractor shall notify the Engineer a minimum of five (5) working days in advance of installation of any permanent pavement markings.

The Engineer will provide striping target points.

N.4 The Contractor is responsible to notify, in writing, all affected property owners a minimum of 72- hours in advance of any changes or closures to access of their property, including road closures and driveway work. Contractor shall maintain written records documenting such efforts. Failure to comply with these requirements may result in suspension of the work ordered by the Engineer, which will be considered a non-excusable delay.

N.5 Maintain a minimum lane width of 12 feet on all roadways. Traffic must not be allowed or forced onto the shoulders without prior approval of the Engineer.

N.6 Access to and from the project site is subject to approval by the Engineer.

N.7 Keep the Right-of-Way fence closed during non-working hours.

O Maintenance and Staging of Traffic Control – Project Specific

O.1 The contractor shall submit a traffic control plan for this Work for the Owners review and approval. The contractor is allow to close the eastbound left turn lane, eastbound inside thru lane, and westbound inside thru lane for this Work. See special provision (1806) DETERMINATION AND EXTENSION OF CONTRACT TIME for allowable duration of closures.

S-9.4 METHOD OF MEASUREMENT All traffic control required to complete the Project as shown in the Plans and specified in these Special Provisions will be made as a lump sum payment under Item 2563.601 (Traffic Control). Payment includes all costs associated with furnishing, installing, maintaining, relocating and subsequently removing traffic control devices (including flaggers) as required. No additional measurement for payment will be made for individual activities and devices that constitute Traffic Control, except for other traffic control Bid items specifically listed in the Statement of Estimated Quantities.

Traffic Control layouts and devices not shown in the plan or stated in these Special Provisions, that are necessary to facilitate traffic switches or for transitioning traffic from one stage to another, are included in the lump sum traffic control item. If the Contractor requests a change in traffic control and these changes are implemented, there will be no increase or decrease in the lump sum payment for traffic control. If the Engineer orders a change in traffic control because of a Plan error, omission, changed condition or change of project scope, payment for such changes will be made as Extra Work.

The Contractor will be subject to a monetary deduction of $500 per incident per day that the Engineer determines that the Contractor has not adhered to any of the requirements in this section. The charges may be assessed equally, separately, and/or concurrently.

If the Contractor fails to properly provide, install, maintain, or remove any of the required traffic control devices, the Department may correct the deficiency and to deduct the costs from any moneys due or becoming due to the Contractor in accordance with MnDOT 1512, “Unacceptable and Unauthorized Work”.

S-9.5 BASIS OF PAYMENT All Traffic Control work will be paid in a single Lump Sum payment under Item 2563.601 (Traffic Control).

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 14

S-10 (2562) ADDITIONAL TRAFFIC CONTROL DEVICES AND EXTENDED USE OF TRAFFIC CONTROL DEVICES REVISED 11/14/19 SP2018-20.2

S-10.1 DESCRIPTION The Engineer is authorized to:

• Require extra traffic control devices in addition to the traffic control devices shown in the Traffic Control plan or in the Field Manual. • Require additional traffic control devices for EXTRA WORK. • Require extended use for all traffic control devices which are impacted by excusable and compensable delays, as defined in MnDOT 1806.2B.

S-10.2 MATERIALS Devices must meet contract requirements, quality standards detailed in the Field Manual, and be in functional and legible condition. Devices not meeting these requirements must be immediately replaced or repaired.

S-10.3 CONSTRUCTION REQUIREMENTS The Contractor must furnish the additional traffic control devices as ordered by the Engineer.

S-10.4 METHOD OF MEASUREMENT Total compensation for Additional Traffic Control Devices and the Extended Use of Traffic Control Devices will have a maximum payout allowance based on average lifespan as determined by the department.

The following devices will be paid by the UNIT DAY and have a 180 Day maximum pay out allowance:

• Type A Channelizer; • Surface Mounted Delineator; • Opposing Traffic Lane Divider; • Reflectorized Drum; • Flasher Type A (Low Intensity); • Flasher Type B (High Intensity); • Flasher Type C (Steady Burn).

The following devices will be paid by the UNIT DAY, SQUARE FOOT per day, LINEAR FOOT per day, or EACH per day, and have a 365 Day maximum pay out allowance:

• Type I Barricade; • Type II Barricade; • Type III Barricade; • Direction Indicator Barricade; • 48”X48” Sign; • 48”X48” Sign with Supports; • Standard Sign; • Portable Sign Support; • Temporary Plastic Barrier; • Impact Attenuator.

Driven post supports and all mounting hardware for 48”X48” signs and Standard Signs are incidental.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 15

Standard Signs with Portable Supports will be calculated and paid for as follows: Total Standard Sign Sq. Ft. + Portable Support Cost (listed in Table 2562-1) = Standard Signs with Portable Supports Cost per day.

Construction Sign-Special will be measured by the sign face area furnished, installed including supports, and removed.

Flaggers and Police Officers will be measured by the number of hours each is in service on the job. The Police Officer must be properly uniformed including a reflectorized high-visibility safety vest and fully equipped including police car.

S-10.5 BASIS OF PAYMENT The Department will not use the predetermined unit prices listed in Table 2562-1 if payment for a device is specifically provided for elsewhere in the Contract.

Devices, Flaggers and Police Officers: The Engineer and Contractor are authorized to negotiate the terms of compensation for additional traffic control devices and extended use of traffic control devices. If the Engineer and Contractor are unable to agree on compensation using contract unit prices or by negotiation, the Department will pay for traffic control devices according to the schedule of pre-determined prices in the following schedule:

Table 2562-1 ADDITIONAL TRAFFIC CONTROL DEVICES, FLAGGERS AND POLICE OFFICERS Item Pre-determined Item Unit Number Price 2562.602 Impact Attenuator1 Each $47.21 2562.603 Temporary Plastic Barrier1 Linear Foot $0.32 2562.603 Portable Precast Concrete Barrier Design 83371 Linear Foot $0.06 2562.610 Flagger2 Hour 3 2562.610 Police Officer Hour 2562.613 Type I Barricade Unit Day $0.37 2562.613 Type II Barricade Unit Day $0.34 2562.613 Type III Barricade Unit Day $1.89 2562.613 Direction Indicator Barricade Unit Day $0.49 2562.613 Flasher Type A (Low Intensity) Unit Day $0.32 2562.613 Flasher Type B (High Intensity) Unit Day $0.65 2562.613 Flasher Type C (Steady Burn) Unit Day $0.29 2562.613 Surface Mounted Delineator Unit Day $0.28 2562.613 Type A Channelizer Unit Day $0.17 2562.613 Opposing Traffic Lane Divider Unit Day $1.54 2562.613 Reflectorized Drum Unit Day $0.65 2562.613 Flashing Arrow Board Unit Day $8.43 2562.613 Portable Changeable Message Sign4 Unit Day $27.46 2562.613 Portable Radar Trailer Unit Day $26.13 2562.613 48”X48” Sign Unit Day $.92 2562.613 48”X48” Sign with Supports Unit Day $1.49 2562.613 Roll up Sign with Support Unit Day $1.53 Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 16

Table 2562-1 ADDITIONAL TRAFFIC CONTROL DEVICES, FLAGGERS AND POLICE OFFICERS Item Pre-determined Item Unit Number Price 2562.613 Portable Sign Support Unit Day $.56 2562.618 Standard Sign1 Square Foot $0.18 2562.618 Construction Sign-Special5 Square Foot $47.21 1. Item will be paid by the item unit per each day in use. 2. Will be paid in accordance with MnDOT 1904.4A. 3. Will be paid at the invoice price plus 10%. 4. Type C Trailer Mounted Message Sign. 5. Construction Sign-Special includes fabrication, installation, supports and removal as specified. Construction Sign-Special is not eligible for additional compensation due to extended use.

Labor and Equipment: The Engineer and Contractor are authorized to negotiate the terms of compensation for labor and equipment to furnish, install and remove additional traffic control devices listed in Table 2562-1. If the Engineer and Contractor are unable to agree on compensation by negotiation, the Department will pay for labor and equipment according to the following mileage-based method:

The Department will pay $500.00 for the first 30 miles for mobilization and installation of additional traffic control devices. The Engineer will determine mileage based on the distance from the Traffic Control Contractor’s closest office location to the project limits (most direct route) plus mileage from the project limits to the furthest location of the additional placement(s), round trip. The Department will pay a minimum of $500.00.

The Department will pay $2.40 per mile traveled over 30 miles. The Engineer will determine mileage based on the distance from the Traffic Control Contractor’s closest office location to the project limits (most direct route) plus mileage from the project limits to the furthest location of the additional placement(s), round trip.

The Department will pay $500.00 for the first 30 miles for de-mobilization and removal of additional traffic control devices. The Engineer will determine mileage based on the distance from the Traffic Control Contractor’s closest office location to the project limits (most direct route) plus mileage from the project limits to the furthest location of the additional removal(s), round trip. The Department will pay a minimum of $500.00.

The Department will pay $2.40 per mile traveled over 30 miles. The Engineer will determine mileage based on the distance from the Traffic Control Contractor’s closest office location to the project limits (most direct route) plus mileage from the project limits to the furthest location of the additional removal(s), round trip.

The Department will not pay for labor and equipment for the installation/removal of additional traffic control devices when additional traffic control work is combined with plan-provided traffic control devices installation/removal during the original contract period, unless a contract revision meets the requirements listed in MnDOT 1402.3 and the Plan does not contain Item 2563.601 (Traffic Control).

The Department will not pay for labor and equipment to inspect and maintain additional traffic control devices during the original contract period, unless a contract revision meets the requirements listed in MnDOT 1402.3 and the Plan does not contain Item 2563.601 (Traffic Control).

The Department will pay for labor and equipment to inspect and maintain all traffic control devices when an extension of contract time is due to an excusable and compensable delay in accordance with MnDOT 1806.2B.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 17

The Department will not pay for labor and equipment to remove existing traffic control devices, provided under Section S-2563 (TEMPORARY TRAFFIC MANAGEMENT) of these Special Provisions, when contract time is extended.

S-11 (1505) COOPERATION BY CONTRACTORS SP2018-22 - MODIFIED The provisions of MnDOT 1505 are supplemented as follows:

S-11.1 Information on other Washington County capital improvement projects can be found at the following location: https://www.co.washington.mn.us/474/Transportation-Projects

S-11.2 The Contractor shall be responsible to educate themselves on other projects that may impact their work, including projects by other government agencies and private improvements. There will be no changes to the contract due to impacts from other projects, including maintenance or emergency work.

S-11.3 The department is aware of the following projects being performed by others that are in the vicinity of this project. This list is not all inclusive. A) CSAH 16 Concrete Grind, from Bielenberg Drive to Radio Drive

S-11.4 The Contractor shall coordinate work and cooperate with the holders of those current and future separate contracts, as required by MnDOT 1505.

S-12 (1507) UTILITY PROPERTY AND SERVICE REVISED 10/18/18 SP2018-24 - MODIFIED Contractor shall perform construction operations near utility properties in accordance with the provisions of MnDOT 1507, except as modified below:

S-12.1 Add the following to MnDOT 1507.1:

The Contractor agrees that is shall use the Plan to identify the location of Washington County storm water drainage facilities in order to meet the requirements of Minnesota Statutes Ch. 216D and Minnesota Rules 7560.0250 which apply to Washington County storm water drainage facilities.

S-12.2 Add the following to MnDOT 1507.2:

(3) The Contractor shall acquire a Positive Response confirmation from MnDOT for all proposed excavations when the Gopher State One Call has indicated that proposed excavations may affect MnDOT utilities. The Contractor may call MnDOT Electrical Services Section (ESS) Dispatch Locating to confirm the status of MnDOT-owned Utility infrastructure. Contractor can contact MnDOT Electrical Services Section (ESS) Dispatch Locating at (651) 366 -5750 or (651) 366-5751. The Contractor shall be responsible for all damage to MnDOT owned Utility infrastructure if the Contractor did not acquire a Positive Response confirmation from MnDOT.

S-12.3 The following utility owners have existing facilities that may be affected by the work on this project:

Comcast 612-462-7911 Ben Ueland Lumen (Centurylink) 651-302-5319 Pat Slavik Xcel Energy Gas 651-302-1342 Justin Pinska MCI 612-919-1751 Andrew Frette Washington County Traffic 651-430-4347 Jake Eisinger City of Woodbury 612-717-3720 Doug French Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 18

S-12.4 At the completion of the Project, the Contractor shall remove all flags, lath, etc. used for locating utilities.

S-13 (1508) CONSTRUCTION STAKES, LINES, AND GRADES SP2018-26 The provisions of MnDOT 1508 are supplemented and modified as follows:

S-13.1 The following is added to the first paragraph of MnDOT 1508:

The Contractor must provide a prioritized written list of Project staking to the Engineer at the pre- construction conference. The Engineer will schedule staking according to the priority list as work progresses. When the Contractor requests a change in priority, the Contractor must provide at least 36 hours advance notice to the Engineer, excluding non-work days, to allow the Engineer to remobilize a survey crew to the revised priority staking segment.

The Engineer will mark all alignment and elevation control points with Department-furnished lath. The Department will furnish all survey stakes and hubs. However, the Contractor must furnish lath for any additional construction stakes where the Contractor desires increased visibility. The Engineer will place the Contractor's lath at the time of construction staking.

S-14 (1517) CLAIMS FOR COMPENSATION ADJUSTMENT The provisions of MnDOT 1517 are hereby supplemented with the following:

S-14.1 Notice of Claim At the time the Contractor gives written notice of the claim, the Contractor and the County shall immediately begin to keep and maintain complete and specific records to the extent possible. The records shall consist of, but are not limited to, cost and schedule records concerning the details of the perceived claim.

Unless otherwise agreed to in writing, the Contractor shall continue with and carry on the work and progress during the pendency of any claim, dispute, decision, or determination by the Engineer, and any arbitration proceedings.

S-14.2 Submission of Claims The Contractor shall submit the claim to the Engineer no later than 60 calendar days after receiving written notice from the Engineer that direct damages (money or time due) resulting from the claim has occurred in the opinion of the Engineer. IF, in the opinion of the Contractor, the direct damages have not fully occurred, the Contractor shall provide written justification detailing why the direct damages have not fully occurred. This written justification shall be submitted to the Engineer no later than 30 calendar days from receiving the notice from the Engineer. If proper justification is not given as required within the 30 calendar day requirement or the claim is not submitted to the Engineer within 60 calendar days after receiving notice from the Engineer that the direct damages have occurred, the Contractor waivers all claims for additional compensation in connection with the work already performed.

The contents of the claim shall be in accordance with MnDOT 1517 and shall also include all scheduling documentation related to the claim.

The Engineer shall have access to the Contractor’s records involved in the claim, and, when so requested, shall furnish the Engineer copies of claim documentation.

The Contractor shall promptly furnish any clarification and additional information or data requested in writing by the Engineer.

All claims shall be submitted through the Contractor. Submission of claims directly from subcontractors shall constitute a waiver of that portion of the claim. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 19

S-14.3 Decision on Claims The County intends to resolve claims at the lowest possible administrative level. Upon receipt of the claim, the Engineer will make a written decision in relation to any claim presented by the Contractor within the following time frames:

(A) For an adjustment in compensation, or other contractual dispute between the parties where the amount in controversy is $75,000 or less, 60 calendar days from the receipt of the Contractor’s claim.

(B) For an adjustment in compensation, or other contractual dispute between the parties where the amount in controversy is more than $75,000, 90 calendar days from the receipt of the Contractor’s claim.

Unless the Contractor and Engineer otherwise stipulate in writing to a later time, if the Engineer does not make a decision or determination within these time frames, the claim shall be deem denied.

When the Contract has established a dispute resolution process that moves the dispute through various levels of both organizations, this process shall also be completed within the above time period.

S-14.4 Mediation Notwithstanding the formal claims procedures set forth in this Special Provision, the parties may at any time enter into nonbinding mediation by mutual agreement. If the parties agree to mediation, then the time requirements set forth above in Section (1517) Decision On Claims (A) and (B) are suspended until the mediation is completed. The time and place for mediation, as well as selection of the mediator, shall be established by mutual agreement. The mediator’s costs shall be divided equally between the Contractor and the County. This payment shall be accomplished by the Contractor paying in full all costs and fees for the mediator and then submit the bill to the Engineer for 50 percent reimbursement. Either party may terminate mediation at any time.

S-14.5 Rights of Arbitration The decision of the Engineer in relation to the Contractor's claim shall be deemed final unless the Contractor commences a legal action within the time prescribed by law or unless the Contractor invokes arbitration as prescribed hereafter in these Special Provisions. Nothing herein contained shall be so construed as to preclude the Contractor from commencing a legal action in relation to claims for a single issue in excess of $75,000.00 but the Contractor's sole legal remedy in relation to claims of $75,000.00 or less shall be arbitration as prescribed hereafter in these Special Provisions. If the claim amount is in excess of $75,000, the Contractor and the County may mutually agree to arbitration.

If the Contractor seeks to arbitrate a claim of $75,000 or less, the Contractor shall submit a written request for arbitration to the Engineer within 30 Calendar Days after the Contractor’s receipt of the Engineer's decision. Failure to reasonably conform with this time requirement waives the right to arbitration. The scope of the arbitration proceeding shall be limited to the claim(s) that the Contractor previously presented to the Engineer for decision.

S-14.6 Arbitration of Claims and Disputes For purposes of this section, a claim for adjustment in compensation shall mean an aggregate of operative facts which give rise to the rights which the Contractor seeks to enforce. Stated another way, a claim is the event, transaction, or set of facts that give rise to a claim for compensation. Any Contractor having a claim in excess of $75,000.00 may waive or abandon the dollar amount in excess of $75,000.00 so as to bring the claim within the scope of this section. However, the arbitration award shall not exceed $75,000.00. Various damages claimed by the Contractor for a single claim may not be divided into separate proceedings to create claims within the $75,000.00 limit.

More than one separate claim may be presented at each arbitration hearing if agreed to by the County, the Contractor, and the Arbitrator

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 20

Selection of the Arbitrator/ Optional Use of the American Arbitration Association:

(A) Selection of the arbitrator shall be conducted by one representative of the County and one representative of the Contractor. A single person shall represent the prime and all subcontractors involved in the claim. Separate representation for subcontractors during the selection of the arbitrator is not allowed.

(B) The parties may mutually agree to have the arbitration process administered by the American Arbitration Association (“AAA”).

(C) The arbitration shall be administered by a single arbitrator.

(D) The parties shall select an arbitrator by mutual agreement, or, if the parties have agreed to use the AAA to administer the process, shall select an arbitrator from a list of arbitrators provided by the Association in accordance with the Association’s procedures.

Arbitration proceedings and decision:

(A) All arbitration of claims shall be conducted in Minneapolis, Minnesota, or another mutually agreed upon location.

(B) Regardless of whether the parties have agreed to use AAA to administer the process, the arbitration proceeding shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then in effect and in accordance with the requirements below. The arbitration procedures set-forth in this Special Provision shall take precedence over conflicting American Arbitration Association requirements.

(C) If mutually agreed to by both parties, the arbitration proceeding shall follow the Fast Track rules of the American Arbitration Association.

(D) Unless otherwise agreed to by the parties, the arbitration hearing shall be bifurcated into a liability phase and, if needed, a valuation phase. No evidence or testimony regarding the value of the claim shall be presented during the liability phase.

(E) The Contractor shall first present evidence to support the claim. The County will then present evidence supporting its defense. Witnesses shall submit to questions or examinations. The arbitrator has the discretion to vary this procedure and shall afford a full and equal opportunity to all parties to be heard. Exhibits, when offered by either party, may be received in evidence by the arbitrator.

(F) The arbitrator shall entertain motions, including motions that dispose of all or part of a claim or that may expedite the proceedings.

(G) There shall be no ex parte communication between any party and an arbitrator.

(H) When satisfied that the presentation of the parties is complete, the arbitrator shall declare the liability phase of the arbitration hearing closed. The arbitrator shall then determine whether the County is liable.

(I) If the County is found to be liable, the arbitration proceeding shall continue before the same arbitrator to resolve all damages issues. The proceedings for this portion of the arbitration shall follow the procedures outlined in Section (1517) Arbitration of Claims and Disputes d. and e. of this Special Provision.

(J) Within three Calendar Days after the close of the damages portion of the hearing, each party shall submit to the arbitrator their last best offers. The arbitrator shall be limited to awarding Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 21

only one of the two figures submitted. In no event shall a claim award in arbitration exceed $75,000.

(K) The decision or award of the arbitrator shall be:

a. In writing showing the basis for the decision or award. The arbitrator shall use the Contract and Minnesota law, or, in the absence of Minnesota law on the issue(s), other persuasive authority, as the basis for the decision.

b. Final and binding on both the County and the Contractor

Arbitration costs

(A) Each party to the arbitration shall bear its own costs and fees assessed by the American Arbitration Association or independent arbitrator which shall be divided equally between the parties to the arbitration. This payment will be accomplished by the Contractor paying in full all costs and fees for the arbitrator and then submit the bill to the Engineer for 50 percent reimbursement.

(B) Each party shall bear its own preparation costs.

Pre-Award Interest and Pre-Judgement Interest

Pre-award interest will commence on the date that a request for arbitration is made, in writing to the Engineer, following the submission of a claim that complies with the requirements of MnDOT 1517. Pre- judgment interest will commence on the date that an action is commenced following the submission of a claim that complies with the requirements of MnDOT 1517. Pursuant to Minnesota Statutes §549.09 this Contract expressly provides dates for the commencement of interest that may vary from the dates provided in statute.

S-15 (1606) STORAGE OF MATERIALS SP2018-33 The provisions of MnDOT 1606 are hereby supplemented with the following:

S-15.1 If the Contractor elects to crush excavated materials within the Project Limits, the quantity of crushed material will be limited to only the quantity required for this Project. Do not crush materials other than those found within the Project Limits, unless approved in writing by the Engineer. The Contractor may not remove crushed material from the Project Limits, unless approved in writing by the Engineer.

S-16 (1701) LAWS TO BE OBSERVED (PROMPT PAY AND RETAINAGE) REVISED 10/09/19 SP2018-33.1 The provisions of MnDOT 1701 are supplemented with the following:

S-16.1 Prompt payment of subcontractors is required by Minnesota Statutes 471.425, subd. 4a. The Contractor must pay a subcontractor no later than ten days after receiving payment from the Department for undisputed work provided by that subcontractor. If the Contractor fails to pay a subcontractor on time, then the Contractor must pay interest, at the rate of 1.5% per month, to the subcontractor on the undisputed amount not paid on time. For an unpaid amount under $100, the Contractor must pay the actual interest penalty (calculated at 1.5% per month). For an unpaid amount over $100, the Contractor must pay the actual interest penalty (calculated at 1.5% per month) or $10, whichever is greater.

Minnesota Statutes 471.425 subd. 4c also provides that a subcontractor who prevails in a civil action to collect interest penalties from a prime contractor must be awarded its costs and disbursements, including attorney’s fees, incurred in bringing the action.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 22

S-16.2 Payment of retainage for state projects is governed by Minnesota Statutes §337.10 and Minnesota Statutes §15.72. State law does not require retainage to be withheld. The contractor may not withhold more than 5% in retainage from a subcontractor, as provided by Minnesota Statutes §337.10 subd. 4 (b). The contractor must pay any retainage no later than 10 days after the Contractor receives payment of retainage from the Department, unless there is a dispute about the work under a subcontract. If there is a dispute about the work under a subcontract, the contractor must pay out retainage to any subcontractor whose work is not involved in the dispute, and must provide a written statement detailing the amount and reason for the withholding to the affected subcontractor.

S-17 (1701) LAWS TO BE OBSERVED (WET LANDS) REVISED 05/17/19 SP2018-34 The provisions of MnDOT 1701 are modified and/or supplemented with the following:

S-17.1 If the Contractor operations involve the excavation and/or disposal of material off Washington County Right of Way, the Contractor is advised of the following:

MN Statutes Sections 103G.2212 and 103G.241 stipulate that an agent or employee of another may not: 1) drain, excavate, or fill a wetland, wholly or partially; or 2) construct, reconstruct, remove, or make any change in any reservoir, dam, or the course, current, or cross-section of any public water. unless a signed statement from the property owner is obtained stating that any permit or wetland replacement plan required for the work is in place, or that a permit or replacement plan is not required; AND this statement is mailed to the appropriate office with jurisdiction over the wetland or public water prior to initiating the work.

The "Landowner Statement and Contractor Responsibility For Work in Wetlands or Public Waters" can be found at http://www.bwsr.state.mn.us/wca-forms-and-templates. The Contractor shall provide the Engineer with a copy of the completed "Landowner Statement and Contractor Responsibility for Work in Wetlands or Public Waters" for the excavation and/or disposal site prior to initiating the work.

S-18 (1701) LAWS TO BE OBSERVED – CERTIFICATION OF NONDISCRIMINATION AGAINST ISRAEL SP2018-40 By signing this Contract, Contractor certifies it does not engage in and has no present plans to engage in discrimination against Israel, or against persons or entities doing business in Israel, when making decisions related to operating the Contractor’s business. For purposes of this section, “discrimination” includes, but is not limited to, engaging in refusals to deal, terminating business activities, or taking other actions that are intended to limit commercial relations with Israel, or persons or entities doing business in Israel, when such actions are taken in a manner that in any way discriminates on the basis of nationality or national origin and is not based on a valid business reason.

S-19 (1706) EMPLOYEE HEALTH AND WELFARE SP2018-41 The provisions of MnDOT 1706 are supplemented with the following:

S-19.1 The Contractor must not use motor vehicle equipment that has an obstructed rear view unless:

(A) The vehicle has a reverse alarm that is audible above the surrounding noise level; or

(B) An observer signals to the operator that it is safe to reverse.

S-19.2 The Department may assess a monetary deduction $500 per incident for a violation of safety standards that could result in death or serious injury. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 23

S-19.3 The areas of special concern include, but are not limited to, excavation stability protection, fall protection, protection from overhead hazards, vehicle backup protection (see S-20.1 above), confined space safety, blasting operations, and personal safety devices.

S-19.4 The Contractor cannot avoid complying with safety standards by paying the deduction.

S-20 (1707) PUBLIC CONVENIENCE AND SAFETY SP2018-42 - MODIFIED The provisions of MnDOT 1707 are supplemented with the following:

Always use S-.1. S-20.1 Contractor shall conduct operations and perform the Work in a manner that causes the least possible obstruction to traffic. The Contractor shall provide for the safety of the general public and for the residents living beside the Highway.

The Contractor shall ensure that employees and Subcontractors do not display items such as, but not limited to, flags, banners, and symbols on the Project Site, that may disrupt the proper prosecution of the Work, impede public safety, or create a distraction for the traveling public.

Fall protection meeting AASHTO, OSHA, and International Building Code requirements shall be installed and maintained throughout construction. Fall protection shall be incidental.

S-20.2 If, for any reason, a street is closed or not passable for emergency vehicles, the Contractor shall immediately notify the following:

Washington County Public Works 651-430-4300 Washington County Sheriff’s Department 651-439-9381 Minnesota State Patrol 651-779-5900 Woodbury Police Department 651-439-9381 Woodbury Fire Department 651-714-3600

S-20.3 The Contractor is required to respond within two hours to any call from the Engineer concerning deficiencies relating to public safety and convenience. If the Contractor does not respond to these matters, a monetary deduction will be assessed at the rate of $250 per hour for the time period the Engineer determines the Contractor has not complied. In addition to the monetary deduction, the Department may complete the necessary work and deduct the cost of this work from future payments.

S-21 (1801) SUBLETTING OF CONTRACT SP2018-49 The provisions of MnDOT 1801 are modified as follows:

S-21.1 For Projects in excess of $50,000, the Contractor may sublet work only to subcontractors that meet the definition of “responsible contractor” in Minnesota Statutes §16C.285, subdivision 3. The Contractor shall obtain verifications of compliance with §16C.285 from subcontractors using a form provided by the Department. The Contractor must provide such verifications to the Department.

S-21.2 The third paragraph of MnDOT 1801 is modified to read:

On Contracts with Disadvantaged Business Enterprise (DBE), Targeted Group Business (TGB) or Veteran-Owned Small Business (VET) established goals, or any combination thereof, the Contractor's organization shall perform Work amounting to not less than 30 percent of the total original Contract Amount. The Department will deduct specialty items from the total original Contract Amount before calculating the amount of Work that the Contractor shall perform.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 24

S-22 (1802) TRAINING FOR CONSTRUCTION TRUCK OPERATORS SP2018-50 Construction truck operators that haul construction materials such as borrow, aggregate base, asphalt mixtures and concrete paving mixtures are encouraged to become trained in Construction Truck Operator Training (CTOT).

The CTOT course covers the Federal and State construction truck and driver requirements and regulations. The course also covers safe driving techniques. The course includes presenters from the Minnesota State Patrol, Minnesota Department of Transportation, and Hennepin Technical College.

For additional information, contact:

Hennepin Technical College Email: [email protected] Phone: 763-488-2721 Website: HennepinTech.edu/CTOT

Call 952-995-1330 to register and/or get location information for upcoming CTOT Classes.

S-23 (1803) PROGRESS SCHEDULES REVISED 01/24/20 SP2018-51 - MODIFIED The provisions of MnDOT 1803 are modified as follows:

S-23.1 This Contract allows for the use of a “Bar Chart Schedule” as the Progress Schedule for the Project.

S-23.2 MNDOT 1803.2.B.3 is deleted and replaced with the following:

The Contractor shall update the Bar Chart Schedule monthly and provide to the Engineer for review. At a minimum, updates will include the actual start and finish of each activity, percentage complete, remaining durations of activities started but not yet completed, and the addition of activities for any schedule impacts.

S-24 (1804) LIMITATION OF OPERATIONS - NIGHT CONSTRUCTION REVISED 03/09/18

SP2018-53 Modify MnDOT 1804.2, “Limitation of Operations”, with the following:

S-24.1 Night Construction means construction between the hours of 9:00 p.m. to 7:00 a.m. occurring within 500 feet of any sensitive areas such as:

• Hospitals; • Nursing homes; • Private residences including condos and apartments; • /motels.

The Contractor must not perform the following activities during Night Construction:

driving/removal; • Concrete pavement demolition; • Sawing for pavement removal; • Crushing operations; • Jack-hammering.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 25

The Engineer must approve any deviation from these prohibitions.

The Contractor must have a supervisor on site during Night Construction. The supervisor must have satisfactorily completed the “MnDOT Noise Mitigation for Night Construction” training within the past five years, as shown in the Department’s records. This free 30 minute training is available online at http://www.dot.state.mn.us/onlinelearning/construction/noisemitigation. The Contractor must provide the Engineer with the nighttime supervisor’s name and a copy of the current certification prior to beginning Night Construction.

In addition, the Contractor must:

• Notify owners or occupants of all buildings in sensitive areas (within 500 feet of the Night Construction). Notify owners or occupants of the type, location, and duration of the work. Provide notice in writing no later than five calendar days prior to beginning the work. Provide a copy of the notification to the Engineer and the City. • Provide a contact person who is on site to ensure that any issues related to Night Construction are immediately addressed. • Use only equipment having OSHA- approved ambient sound-sensing backup alarms or, as an alternative, use an observer may in accordance with OSHA standards. • Allow for equipment to turn-around in lieu of backing-up (this includes equipment entering/exiting the project). • Construct temporary noise mitigation enclosures or curtains around stationary equipment (e.g., generators, compressors) that are within 500 feet of sensitive areas. • Ensure that tailgates on trucks are not slammed. Truck drivers unable to control the tailgates from slamming must be removed from the project. • Ensure that all engines and engine driven equipment used for hauling or construction are equipped with an adequate muffler in constant operation and properly maintained to prevent excessive or unusual noise.

If the Engineer determines that the Contractor is not in compliance with the Night Construction requirements, the Engineer will suspend Night Construction. The suspension will remain in effect until the Contractor remedies the non-compliance or obtains the Engineer’s acceptance of an action plan that satisfactorily addresses the non-compliance. The suspension will be considered a non-excusable delay.

S-25 (1806) DETERMINATION AND EXTENSION OF CONTRACT TIME REVISED 11/14/19 SP2018-54 - MODIFIED The Department will determine Contract Time in accordance with the provisions of MnDOT l806 and the following:

S-25.1 Once lanes are closed to complete this Work, the Contractor has up to 14 Calendar Days to re- open lanes to traffic. Lane closures shall occur during one period of time, with exception of pavement striping.

S-25.2 Contractor must complete all Work to meet the requirements of MnDOT 1516.2, “Project Acceptance,” under this Contract in no more than 19 Calendar Days, and all Work shall be completed by October 1, 2021.

S-25.3 Contractor must complete all Work to meet the requirements of MnDOT 1516.3, “Completion of the Work,” under this Contract within 90 calendar days of receipt of the Semi-Final Estimate in accordance with MnDOT 1908.2.

S-25.4 Unless authorized in writing by the Engineer, the Contractor must not begin construction operations that impact, restrict, or interfere with traffic, before the Department’s acceptance of the Contractor’s Baseline Schedule. The Engineer will determine whether operations impact, restrict, or interfere with traffic in the Engineer’s sole discretion.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 26

S-25.5 The Contractor must not perform work that will restrict or interfere with traffic between 12:00 noon on the day before and 9:00 A.M. on the day after any consecutive combination of a Saturday, Sunday, and legal holiday. The Contractor may request exceptions to this requirement. Exceptions must be approved in writing by the Engineer.

S-25.6 Work is allowed between the hours of 7:00am and 7:00pm, Monday through Saturday. No work will be allowed outside of these hours, including loading and unloading of equipment, supplies, etc., unless approved in writing by the Engineer. Failure to comply with allowable working hours will result in a monetary deduction of $500 per hour rounded up to the next whole hour.

S-26 (1807) FAILURE TO COMPLETE THE WORK ON TIME REVISED 01/14/20 SP2018-56 The provisions of MnDOT 1807 are supplemented as follows:

S-26.1 The Department will deduct liquidated damages from money due the Contractor for each calendar day that the Work remains incomplete after expiration of the Contract Time, according to the completion requirements of MnDOT 1516.2, “Project Acceptance”. The Engineer will deduct liquidated damages based on the original Contract Amount and Table 1807-1.

S-26.2 The Department will assess the Contractor a monetary deduction in an amount equal to $100 for each Calendar Day that any work specified under MnDOT 1516.3, “Completion of the Work,” are not met after the expiration of the 90 day period of the Semi-Final Estimate requirements.

S-26.3 For informational purposes only, bidders are advised that in addition to the requirements of MnDOT 1807, other Sections of these Special Provisions, as shown below, contain requirements for assessment of monetary deductions to this Contract:

DIVISION SECTION TITLE S (2563) TEMPORARY TRAFFIC MANAGEMENT S (1701) LAWS TO BE OBSERVED (PROMPT PAYMENT AND RETAINAGE) S (1706) EMPLOYEE HEALTH AND WELFARE S (2461) STRUCTURAL CONCRETE

S-26.4 The liquidated damages set forth in MnDOT 1807 and any monetary deductions as set forth above may apply equally, separately, and may be assessed concurrently.

S-27 (1902) SCOPE OF PAYMENT NEW WRITE-UP 09/12/19 SP2018-56.1 MnDOT 1902 is deleted and replaced with the following:

The Contractor will receive compensation provided for in the Contract as full payment for providing Materials and performing Work in accordance with the Contract requirements. This includes compensation for all risk, loss, damage, and expense incurred by the Contractor for performing the Work required by the Contract. Payment is subject to 1720 “No Waiver of Legal Rights”. The Department prohibits the Contractor from accepting payment from any other party for performing the Work required by the Contract, including any incentive or bonus payment. The Department does not prohibit the following payments from third parties:

(1) Payments from sureties; (2) Quantity-based rebates or credits from suppliers; (3) Payments under another contract for excess material removed under this Contract. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 27

S-28 (1906) OUT-OF-STATE CONTACTOR For out-of-state contractors, payments shall be held pursuant to Minnesota State Section 290.9705 subdivision 1 unless a waiver of such withholding is procured from the Minnesota Department of Revenue under subdivision 3 of said statute.

S-29 (1906) PARTIAL PAYMENTS The provisions of MnDOT 1906.1 are hereby supplemented with the following:

Retainage will be withheld from Partial Payments in accordance with Minnesota Statute 15.72.

S-30 (2104) REMOVING PAVEMENT AND MISCELLANEOUS STRUCTURES SP2018-76 Abandoned structures and other obstructions shall be removed from the Right of Way and disposed of in accordance with the provisions of MnDOT 2104, except as modified below:

S-30.1 Measurement and payment for the removal and disposal of materials will be made only for those Items of removal work specifically included for payment as such in the Proposal and as listed in the Plans. The removal of any unforeseen obstruction requiring in the opinion of the Engineer equipment or handling substantially different from that employed in excavation operations, will be paid for as Extra Work as provided in MnDOT 1402.5.

S-31 (2104) REMOVING PIPE SEWERS AND CULVERTS

This work shall consist of removing and disposing of existing pipe sewers or culverts in accordance with the provisions of MnDOT 2104, except as supplemented below:

S-31.1 All excavation and embankment required for the removal of pipe sewer or culverts, including placing backfill to replace the volume that was occupied by the pipe or culvert, shall be incidental unless a pay item has been included. If pay items are included for one or more excavation or embankment items related to the removal of pipe sewers or culverts, payment will be made only for those items and all other excavation or embankment items related to pipe sewer or culvert removal shall remain incidental. Additional material required for trench backfilling following pipe sewer or culvert removal shall be incidental.

S-32 (2104) ABATE ASBESTOS-CONTAINING PIPES OR CULVERTS REVISED 07/17/20 SP2018-80 All asbestos-containing pipes or culverts found on the Project shall be handled according to the following provision unless otherwise directed by the Engineer. The Contractor shall comply with all applicable federal and state regulations. The Contractor shall file a project Health and Safety Plan with the Engineer at the Preconstruction Conference. Under this provision the disturbance or removal of the asbestos containing material (ACM) will be managed as regulated asbestos containing waste material. All wet soil from cutting operations will be considered ACM and must be removed immediately as asbestos containing waste material (ACWM).

S-32.1 ACM MANAGEMENT

(A) The Contractor shall use a MnDOT-certified abatement company for all ACM abatement-related activities as provided and described in MnDOT’s “Building & Bridge Demolition/Relocation” website http://www.dot.state.mn.us/environment/buildingbridge/index.html. Contact the Engineer to answer any questions.

(B) The Contractor shall provide a list of all Contractor personnel performing ACM abatement work and shall provide current proof of training (MDH Asbestos Hard Card) for each individual performing ACM abatement work to the Engineer and the State’s Asbestos Abatement Oversight Consultant prior to commencing any Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 28 abatement work at the site. The Contractor shall make sure all Contractor personnel performing ACM abatement work carry their MDH Asbestos Hard Cards at all times when actively performing abatement work.

(C) The Contractor shall complete and submit a MDH/MPCA asbestos abatement notification form in accordance with all MDH and MPCA requirements. The Contractor shall provide a copy of the completed form to the Engineer at the same time it is sent to the regulators. The Contractor shall provide proof to the Engineer that the MDH and MPCA have received notification of the asbestos abatement (either by facsimile receipt or certified mail) before commencing the ACM abatement.

(D) The pipe or culvert must be cut using either wet sawing, other wet operations, or a shearing technique. Torch cutting will not be allowed. Cutting debris must be maintained wet and transported in a leak tight container with proper labeling. The pipe shall be kept wet during removal operations and loading for transport. Saw-cut edges of the pipe shall be encapsulated immediately after cutting. Any pipe that is broken, or becomes broken during the handling of the material, must be wetted and kept wet until it is placed in the appropriate container for disposal. All wet soil from cutting operations or wetting of broken pipe must be removed immediately and managed as ACWM.

(E) The Contractor shall notify the Engineer a minimum of 48 hours prior to beginning ACM abatement to allow the Engineer time to arrange for the State’s Asbestos Abatement Oversight Consultant to be at the site to observe and document the abatement and handling of the ACM.

(F) No removal of ACM shall take place without the approval of the Engineer, nor shall any ACM abatement work of any sort be done unless the State’s Asbestos Abatement Oversight Consultant is present.

S-32.2 ACM DISPOSAL All ACM abated from the Project Limits shall be hauled to a MPCA-permitted Municipal Solid Waste (MSW) landfill or a MPCA-permitted Industrial Landfill facility or landfills listed under Landfills/Regulated Waste at http://www.dot.state.mn.us/environment/buildingbridge/index.html at the MnDOT Approved List of Waste Contractors link for disposal or a MnDOT approved landfill. Contact the Engineer, for a list of the MnDOT approved landfills. ACM WILL NOT BE DISPOSED AT A DEMOLITION LANDFILL.

(A) The Contractor shall be responsible for providing all required information to the landfill (typically waste profile forms) in order to obtain landfill acceptance of the material for disposal. If the ACM are in an area of soil contamination, the Contractor shall also provide soil analytical laboratory reports to the landfill in order to obtain acceptance of the material for disposal.

(B) The Contractor shall provide the completed landfill-required waste profile form(s) to the Engineer for review a minimum of two weeks prior to beginning excavation or as approved by the Engineer.

(C) ACM shall not be hauled to the landfill facility until the Engineer has a written approval (e-mail is acceptable) from the landfill accepting the material for disposal at the landfill facility.

(D) The Contractor shall haul all ACM directly from the project site to the landfill. There shall be no co-mingling of ACM from this Project with waste from other sites outside the Project prior to hauling to the landfill.

(E) The Contractor shall provide clear and legible copies of shipping papers (manifests) and landfill scale tickets (tipping receipts) for each load to the Department’s Environmental Consultant and Engineer daily while material is being hauled to the landfill, or as approved by the Engineer. The Contractor shall provide copies of the completed manifests signed by the landfill (third signature copies) to the Department’s Environmental Consultant and Engineer within 10 days after all material has been hauled to the landfill.

S-32.3 MEASUREMENT AND PAYMENT When asbestos-containing pipes or culverts are encountered during excavation, the Contractor shall notify the Engineer who shall suspend work. The Contractor shall furnish a documented inspection and evaluation by a MnDOT approved certified MDH contractor prior to the resumption of work. All testing and, if necessary, removal of Asbestos Containing Pipes or Culverts will be paid for as Extra Work. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 29

S-33 (2106) EXCAVATION AND EMBANKMENT REVISED 08/09/18 SP2018-103 – MODIFIED Modify MnDOT 2106 as follows:

S-33.1 MnDOT 2106.1.A.6, “Select Grading Material,” is deleted and replaced with the following:

A.6 Select Grading Material

Select grading materials are all mineral soils found in the Triaxial Chart in the Grading and Base Manual, excluding: organic soils per 2106.1.A.10, marl, and silt. Silt is defined as soils containing 80% or more silt-sized particles as determined by MnDOT Laboratory manual procedure 1302. Select Grading Material may contain up to 100% recycled materials composed of recycled concrete, asphalt, or glass meeting the following:

• no more than 10% glass, • no more than 75% concrete, and • with a bitumen content of 3.5% or less.

S-33.2 MnDOT 2106.2.A.1, “Common Excavation,” is deleted and replaced with the following:

A.1 Common Excavation Excavation not classified in any other category, except that 2106.2.A.7, “Topsoil Excavation” is included with common excavation, unless modified by the proposal.

S-33.3 MnDOT 2106.2.A.2, “Subgrade Excavation,” is deleted and replaced with the following:

A.2 Subgrade Excavation All excavation in the road core below the grading grade, exclusive of rock, muck, channel and pond, or rock channel excavation.

S-33.4 MnDOT 2106.3.B, “Contractor Quality Control (QC) Testing,” is deleted and replaced with the following:

B Contractor Quality Control (QC) Testing, Aggregate Certification, and Moisture Requirements

B.1 Contractor Quality Control (QC) Testing Perform Contractor QC testing as required in the 2019 SALT Schedule of Materials Control - Local Government Agency.

Correct areas represented by failing QC or Quality Assurance (QA) tests.

Submit test results to the Engineer within one business day.

B.2 Aggregate Certification Certify granular materials on Form G&B-104, and attach any required tests.

Material placed without certifications is unauthorized work in accordance with 1512, “Unacceptable and Unauthorized Work.”

B.3 Moisture Control Meet the moisture content requirements listed in Table 2106-2.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 30

Table 2106-2 Moisture Content Requirements

Compaction Requirement Relative Moisture Content Requirement *

Minimum of 100% maximum density 65% - 102%

Minimum of 95% maximum density 65% - 115%

Quality Compaction 65% - 102%

Penetration Index Method ≥ 65%

* As Determined on Form G&B-105

Correct moisture content in areas represented by failing moisture tests. Compaction tests taken in areas represented by failing moisture tests are not valid.

Note that optimum moisture content determination tests and moisture tests during compaction are required for all compaction requirements, including quality compaction, LWD, penetration index, and specified density.

The Department’s proctor test results are used to determine optimum moisture determination.

S-33.5 MnDOT 2106.3.G, “Agency Quality Assurance Testing (QA),” is deleted and replaced with the following:

G Agency Quality Assurance (QA) Test according to the Schedule of Materials Control.

G.1 Material Testing Sample granular materials from the road core after spreading, but before compaction.

Select crushing, aggregate quality, and bitumen samples using the random sampling method in the Grading and Base manual; additional samples and tests may be taken to delineate visually indicated material failures. Select gradation samples from locations that are at risk of not meeting the specification requirements.

G.2 Compaction Testing Test for compaction using:

Test for compaction in areas with the greatest rutting or deflection, and near structures.

After Contractor correction of areas represented by a failing test, perform additional tests in areas with the greatest rutting or deflection.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 31

Item Description Compaction Testing Method 2105 & 2106 Embankment - >3 Feet Below Grading Grade- Non- Specified Density (95% Standard Granular- Not Meeting 3149 Proctor) 2105 & 2106 Embankment - <3 Feet Below Grading Grade- Non- Specified Density (100% Standard Granular- Not Meeting 3149 Proctor) 2105 & 2106 Embankment - >3 Feet Below Grading Grade- Specified Density (95% Standard Granular- Meeting 3149 Proctor) 2105 & 2106 Embankment - <3 Feet Below Grading Grade- Penetration Index Granular- Meeting 3149 2105 & 2106 Trench Backfill and Within 3’ of Utility Structure- Specified Density (100% Standard >3 Feet Below Grading Grade Proctor) 2105 & 2106 Trench Backfill and Within 3’ of Utility Structure- Use Embankment Testing Method <3 Feet Below Grading Grade Specified Above 2105 & 2106 Embankment Outside of “Road Core”- Excluding Quality Compaction 2211 Aggregate Base Course Penetration Index ALL Temporary Work Quality Compaction 2105 & 2106 Bottom of Subcut Excavation Quality Compaction

All work must meet the requirements of Quality Compaction. Table above to be used for work within the roadway. See Special Provisions and Geotechnical Report for compaction and testing requirements for work adjacent to structures and other structural fills.

For granular materials with less than 6% passing the #200 sieve, the Engineer may elect to only use the Quality Compaction method, 2106.3.F.2.

The following method may be used in lieu of point testing (penetration index, specified density, or LWD) for material meeting Table 3149-1, 2 Select Granular Material, when the material thickness is 18 in or less and when not adjacent to Structures per 1103, “Definitions”.

The Engineer may elect, with the concurrence of the Contractor, to have the Contractor test roll per 2111, “Test Rolling”, material meeting the requirements of Table 3149-1, 2 Select Granular Material, in lieu of point compaction testing. If this method is adapted, the Contractor is required to first place 3 in of base on top of the material meeting Table 3149-1, 2 Select Granular Material, prior to test rolling. For areas failing test rolling, the Contractor is required to remove the base and recompact the material meeting Table 3149-1, 2 Select Granular Material, then place the base back, and retest roll. There is no additional compensation to the Contractor, if this method is adapted. Additionally, the material meeting Table 3149-1, 2 Select Granular Material, is not accepted, until acceptable test rolling has occurred.

Compaction tests taken in areas represented by failing moisture tests are not valid.

G.3 Moisture Testing Optimum moisture content determination tests and moisture tests during compaction are required for all compaction requirements, including quality compaction, LWD, penetration index, and specified density.

S-33.6 MnDOT 2106.5.K, “Contract Item Schedule,” is deleted and replaced with the following:

K Payment Schedule The Department will pay for excavation and embankment on the basis of the following schedule:

The Engineer will pay for Geotextile Fabric in accordance with 2105, “Excavation and Embankment.”

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 32

Item No. Item Unit 2106.507 Excavation – Common...... cubic yard 2106.507 Excavation – Rock ...... cubic yard 2106.507 Excavation – Muck ...... cubic yard 2106.507 Excavation – Subgrade ...... cubic yard 2106.507 Excavation – Channel and Pond ...... cubic yard 2106.507 Excavation – Rock Channel ...... cubic yard 2106.507 Granular Embankment (CV) ...... cubic yard 2106.507 Select Granular Embankment (1) (CV) ...... cubic yard 2106.507 Common Embankment (CV) ...... cubic yard 2106.507 Stabilizing Aggregate (CV) ...... cubic yard 2106.509 Stabilizing Aggregate ...... ton Notes: (1) Specify basis of percent modification (e.g. 5%, 7%, 10% etc.)

S-34 (2211) AGGREGATE BASE NEW WRITE-UP 08/09/18 SP2018-107.1 MnDOT 2211 is modified as follows:

S-34.1 MnDOT 2211.3.B, “Contractor Quality Control (QC) Testing,” is deleted and replaced with the following:

B Contractor Quality Control (QC) Testing If required by the Schedule of Materials Control, perform Contractor QC testing and submit results and all required forms to the Engineer within one business day.

Certify materials on Form G&B-104, and attach any required aggregate test results.

Correct base, which fails either QC or Quality Assurance (QA) testing. Correct failing material, before placing the next lift.

S-34.2 The following is added to MnDOT 2211.3.D, “Agency Quality Assurance (QA)”:

D.4 Moisture Testing Test for the moisture content in areas that appear least likely to meet specifications. Note that moisture tests during compaction are required for all compaction requirements, including quality compaction, LWD, penetration index, and specified density.

S-35 (2301) CONCRETE PAVEMENT REVISED 07/17/20 SP2018-124 MnDOT 2301 is hereby modified as follows:

S-35.1 Table 2301-4 of MnDOT 2301.2.L.1 shall be deleted and replaced with the following:

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 33

Table 2301-4 Concrete Mix Design Requirements Maximum w/c Estimated Maximum ratio Minimum Cementitious Minimum Concrete Air %SCM Concrete Cement Content Gradation Aggregate Slump 3137 Contract Mix Number Content (Fly Ash/ Grade Content (lbs/ yd3) Requirements Size Range Spec. Quantity Fly Slag/ % Slag/ (lbs/yd3) ║ Required (yd3) * Ash Ternary Ternary) †

3A21 0.40 0.42 Job Mix 1 1/2” ½ - 2” ‡ ≥ 3,500 385 530 – 615 7.0 33/35/40 2.D.3 3A41 0.40 0.42 Formula nominal 2 – 5” < 3,500 and 3126 and 3A21S 0.42 0.42 Table 3137-4 ½ - 2” ‡ Minor work 3/4” 385 530 – 615 7.0 Or 33/35/40 and fill-ins not nominal provided by the 3A41S 0.42 0.42 Job Mix 2 – 5” 2.D.3 A primary paving Formula plant 3A42 3126 and 3/4” 33/35/40 0.42 0.42 385 530 – 615 7.0 2 – 5” # § Table 3137-4 nominal § 3126 and Engineer 3A21HE 0.40 0.42 Table 3137-4 ½ - 2” ‡ Approved or ** 3/4” 385 > 615 – 750 7.0 Or 33/35/40 2.D.3 Plan Allowed nominal 3A41HE Job Mix High-Early 0.40 0.42 2 – 5” ** Formula * Determined by multiplying the planned pavement area by the planned pavement thickness. ║ Provide additional cementitious material to meet requirements in accordance with this section at no additional cost to the Department. † Refer to Table 2301-2 and Table 2301-3 for ASR mitigation requirements. ‡ Adjust slump in accordance with 2301.3.E.1, “Consistency.” # The 5th digit “S” indicate the concrete is for a small concrete paving project or delivered from a secondary concrete plant for minor work or fill-ins. The Concrete Engineer considers minor work or fill-ins as gaps in concrete pavement, turn lanes, intersections or other pavement sections as determined by the Engineer, in conjunction with the Concrete Engineer. § The Concrete Engineer will allow a non-project specific 3A42 mix design provided by a MnDOT certified ready-mix plant submitted in accordance with the first two paragraphs of 2461.2.F.3, “Submittal Requirements.” If the sand source requires mitigation with a minimum of 30% Class C fly ash in accordance with Table 2301-2, the Concrete Engineer will require a minimum of 30% Class C fly ash, 30% Class F fly ash or 35% slag for all 3A42 mixes. **The Contractor may use 100% Portland cement for High Early Concrete, provided no mitigation is required for the fine aggregate and intermediate aggregate in accordance with Table 2301-2 and coarse aggregate in accordance with Table 2301-3. If mitigation is required, the Contractor is required to use a minimum of 15% of any supplementary cementitious material when designing High Early Concrete. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 34

S-35.2 Add the following sentence to second paragraph of MnDOT 2301.2.L.2:

Always use the most current forms available from the MnDOT Concrete Engineering Website.

S-35.3 The third paragraph of MnDOT 2301.2.L.3.c and Table 2301-7 shall be deleted and replaced with the following:

If the gradation tests on any split sample from that day’s testing result in a variation between the Producer and the Engineer greater than that set forth in Table 2301-7, the Engineer will substitute the Agency test results into the moving average calculation to determine acceptance and the well-graded aggregate optional incentive.

Table 2301-7 Allowable Variations on Percent Passing Sieves Sieve Size Allowed Percentage 2 in – 1 in ± 8 ¾ in – ⅜ in ± 6 No. 4 – No. 30 ± 4 No. 50 ± 3 No. 100 ± 2 No. 200 ± 0.6

S-35.4 MnDOT 2301.2.M.2 and 2301.2.M.2.a shall be deleted and replaced with the following:

M.2 Water/Cement (w/c) Ratio Provide and place concrete with a water/cement ratio not to exceed 0.40 when using cement only or fly ash and 0.42 when using slag or ternary. Make any adjustments immediately when the water/cement ratio exceeds 0.40 when using cement only or fly ash and 0.42 when using slag or ternary.

The Engineer will not make incentive payments for water/cement ratio on high-early mixes.

The Engineer will determine the water/cement ratio for concrete hauled in dump or agitator trucks (concrete hauled in truck mixers are not eligible for w/c ratio incentives) in accordance with the following:

M.2.a Sampling and Determination of Lots The Engineer will sample, test, and record the individual results in accordance with 2301.2.M.2.b, “Water Content Determination,” and 2301.2.M.2.c, “Cementitious Content Determination,” at a rate defined in the Schedule of Materials Control. The Engineer will use the W/C Ratio Calculation Workbook for moisture testing and determining the incentive/disincentive.

The Engineer will base the statistical analysis of acceptance for water/cement ratio on a per lot basis representing one day’s paving. Each individual water/cement ratio determination is considered a sublot. The lot will represent the cumulative average of the sublot values. The Engineer will start a new lot and test if either of the following occur:

(1) Mix design change due to a water/cement ratio test result exceeding 0.40 when using cement only or fly ash and 0.42 when using slag or ternary, or (2) Supplementary cementitious type change from fly ash to slag or ternary mix design, or vice versa.

If the quantities of concrete produced results in no Engineer moisture testing for any given day, include the untested quantity of concrete into the next day’s production and include that quantity of concrete in the sampling rate. If the untested quantity is on the last day of production, add that quantity to the previous day’s production. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 35

S-35.5 MnDOT 2301.2.M.2.e shall be deleted and replaced with the following:

M.2.e W/C Ratio Incentive/Disincentive Do not place concrete mix not meeting the water/cement ratio requirements in accordance with Table 2301-4. The Engineer may accept inadvertently placed material not meeting the contract requirements in accordance with Table 2301-11.

Table 2301-11 W/C Ratio Incentive/Disincentive When using cement only or fly ash When using slag or ternary W/C Ratio Payment incentive/disincentive W/C Ratio Payment incentive/disincentive Lot Result per cu. yd Lot Result per cu. yd ≤ 0.37 +$3.00 ≤ 0.39 +$3.00 0.38 +$1.75 0.40 +$1.75 0.39 +$0.50 0.41 +$0.50 0.40 $0.00 0.42 $0.00 0.41 −$0.50 0.43 −$0.50 0.42 −$1.75 0.44 −$1.75 Determined by the Concrete Determined by the Concrete ≥ 0.43 ≥ 0.45 Engineer Engineer

The Contractor may remove and replace concrete represented by water/cement ratio results greater than 0.40 when using cement only or fly ash and 0.42 when using slag or ternary. If the Contractor elects to not remove the concrete and the level of payment is not defined in the Table 2301-11, the Engineer, in conjunction with the Concrete Engineer, will evaluate the concrete based on the adequacy for the use intended. Remove and replace unsatisfactory concrete as determined by the Engineer at no additional cost to the Department.

S-35.6 The first sentence of MnDOT 2301.2.M.3 shall be deleted and replaced with the following:

The Engineer will use the Contractor’s combined aggregate gradation (JMF) test results (QC and Verification Companion) documented in the JMF Concrete Aggregate Workbook, as verified by the Engineer in accordance with 2301.2.L.3.c, “Agency Verification of JMF,” to determine eligibility for the incentive.

S-35.7 Table 2301-12 shall be deleted and replaced with the following:

Table 2301-12 Well Graded Concrete Aggregate Gradation Band Sieve Size % Retained 2 in 0% 1½ in ≤ 5% 1 in ≤ 16% ¾ in ≤ 20% ½ in 4 – 20% ⅜ in 4 – 20% No. 4 4 – 20% No. 8 ≤ 12% Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 36

Table 2301-12 Well Graded Concrete Aggregate Gradation Band Sieve Size % Retained No. 16 ≤ 12% No. 30 4 – 20% No. 50 4 – 20% No. 100 ≤ 10% No. 200 ≤ 2% Coarse Sand % Retained > 15% (No. 8 to No. 30 Sieve) Fine Sand % Retained (No. 30 to No. 200 24% – 34% Sieve)

S-35.8 MnDOT 2301.3.B.3.b shall be deleted and replaced with the following:

3.B.3.b Paving Plant Sampling and Testing Provide the following personnel: (1) QC Plant Technician(s) to perform all testing and quality control requirements of 2301. The QC Plant Technician shall hold a current MnDOT Concrete Plant Certification. (2) Quality Control Supervisor responsible for oversight of all QC testing and daily paving batch plant operations. The Quality Control Supervisor shall hold a current MnDOT Concrete Plant Certification and is required to remain on-site during concrete production or have cellular phone availability. (3) Quality Control Manager responsible for oversight of the Quality Control Supervisor and all batch plant operations. The Quality Control Manager and Quality Control Supervisor can be the same person.

The Engineer will provide MnDOT Certified Concrete Plant Technician(s) to perform all testing in accordance with the requirements of 2301.

Perform testing in accordance with the Concrete Manual and determine testing rates in accordance with the requirements of the Schedule of Materials Control. The Engineer performs testing in accordance with the Concrete Manual and determines testing rates meeting the requirements of the Schedule of Materials Control.

S-35.9 MnDOT 2301.3.F.3.a(6) shall be deleted and replaced with the following:

(6) Adhere the geotextile to the underlying substrate using manufacturer recommended cylinder spray adhesive for geotextiles to attach the geotextile to the underlying concrete or asphalt. Apply a minimum 12 in wide adhesive bond to attach any edge of geotextile to the underlying substrate or to another piece of geotextile. Apply pressure to the geotextile to set the adhesive prior to placing the concrete. The Contractor may propose and demonstrate alternate methods for satisfactorily anchoring the geotextile to the Engineer for approval.

S-35.10 The first paragraph of MnDOT 2301.3.F.5 shall be deleted and replaced with the following:

Use any approved construction header method as shown in the MnDOT Standard Plate 1150 when constructing construction headers, temporary headers, and permanent headers as shown on the plans. The Contractor may propose and demonstrate alternate construction header methods to the Engineer for approval. In the plastic concrete, the Engineer may evaluate headers for vertical surface deviations with a 10 foot straight edge. Correct all high and low spots identified within the 10 foot straight edge. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 37

S-35.11 MnDOT 2301.3.F.6.b(3) shall be deleted and replaced with the following:

F.6.b(3) Non-Conforming Air Content After Consolidation If the Contractor or Engineer test results in an air content after consolidation of less than 4.5%, take the following action:

(1) Immediately retest and verify the ACF is correct. (2) If the results are still < 4.5%, make immediate adjustments to the concrete or the consolidation process, test any loads that have not been discharged or adjusted at the plant and apply the ACF to determine compliance. (3) Test every load of concrete until the air content after consolidation test results are ≥ 4.5%. (4) Test at least 3 additional trucks to ensure the concrete remains in compliance. (5) Perform additional testing on the hardened concrete as required by the Engineer in conjunction with the Concrete Engineer.

S-35.12 MnDOT 2301.3.I.2(3) shall deleted and replaced with the following:

(3) 2301.3.L.2, “Contractor Quality Control Probing.”

S-35.13 MnDOT 2301.3.K.1.a shall modified to include the following:

(4) For concrete roundabouts (not including the truck apron), perform a minimum of 3 texture tests

S-35.14 MnDOT 2301.3.K.1.b(3) shall be deleted and replaced with the following:

(3) Run additional tests at 100 ft intervals before and after the failing test location until an acceptable minimum texture of 1.00 mm is obtained.

S-35.15 The first paragraph of MnDOT 2301.3.N.2 shall be deleted and replaced with the following:

Provide joint sawing as shown on the plans. For concrete pavement 10 feet or less in width, the Concrete Engineer will allow tooling for initial joint establishment. Sawing of tooled joints is required.

Perform the sawing as soon as the concrete will support the joint sawing operation without raveling and before random cracking occurs. If raveling of joints occurs due to the sawing operations, review the sawing operation and make immediate correction to the sawing operations. The Engineer, in conjunction with the Concrete Engineer, will evaluate the raveled joints in accordance with 2301.3.Q, “Workmanship and Quality.”

S-35.16 MnDOT 2301.4.B.1(4) shall be deleted and replaced with the following:

(1) Apply incentives or disincentives based on the daily cubic yards batched of Structural Concrete as verified by the computerized batch ticket printouts from the plant, with consideration of any waste.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 38

S-36 (2301) DRILL AND GROUT DOWEL BAR (EPOXY COATED) NEW WRITE-UP 08/17/20 SP2018-125 This work shall consist of drilling, grouting, and inserting epoxy coated dowel bars as shown on the details in the Plan in accordance with the provisions of MnDOT 2301 and the following:

S-36.1 Furnish and install epoxy coated dowel bars meeting the requirements of MnDOT 3302. Anchor the dowel bars to the in place concrete by utilizing either a non-shrink grout or epoxy adhesive from the approved products list.

S-36.2 MEASUREMENT AND PAYMENT Measurement will be by the number of epoxy coated dowel bars that are furnished, installed, and grouted in place as specified. Payment will be under Item 2301.602 (Drill and Grout Dowel Bar (Epoxy Coated)) at the Contract bid price per each, which shall be payment in full for all work included under this section.

S-37 (2461) STRUCTURAL CONCRETE REVISED 04/09/20 SP2018-156 MnDOT 2461 is modified as follows:

S-37.1 MnDOT 2461.2.F.1.c shall be deleted and replaced with the following:

F.1.c Slump Designation The Department will designate the maximum slump as defined by the Grade Designation in accordance with Table 2461-6 and Table 2461-7.

S-37.2 Table 2461-3 of MnDOT 2461.2.F.1.d shall be deleted and replaced with the following:

Table 2461-3 Coarse Aggregate Gradation Designation for Concrete Designation Coarse Aggregate Gradation 1 2301, “Concrete” Pavement Only 2 ASTM #67 3 ASTM #7 4 ASTM #89 7 CA-70 8 CA-80

S-37.3 Table 2461-5 of MnDOT 2461.2.F.2.a(2) shall be deleted and replaced with the following:

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 39

Table 2461-5 Concrete Mix Design Requirements for Grout and Lean Mix Backfill Mixes Fine Coarse Minimum Water Cement Fly Ash Maximum Aggregate Aggregate %Air Slump 28-day Mix Number Content Content Content w/c ratio Calculation Calculation Content Range Compressive (pounds) (pounds) (pounds) (pounds) (pounds) Strength, f’c 1AGROUT 0.50 379 758 0 100% † 0 3.0% As needed 4000 psi * 3AGROUT 0.44 379 865 0 100% † 0 10.0% As needed 4000 psi * 10 inch ± Lean Mix ǁ 1.00 375 125 250 50% † 50% † ǂ N/A # 1 inch * Do not provide grout containing coarse aggregate or fly ash. ǁ Coarse Aggregate Quality meets requirements of 3137.2.D.1, “Coarse Aggregate for General Use.” † After adding the specified quantities of cement, fly ash, and water, provide the remaining aggregate to an absolute volume 27.00 – 27.27 cubic feet ǂ Meeting ASTM #67 gradation as shown in Table 3137-4 # Maximum 28-day compressive strength of 1500 psi

S-37.4 Table 2461-6 of MnDOT 2461.2.F.2.b(1) shall deleted and replaced with the following:

AppendixSPECIAL PROVISIONS C - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 40

Table 2461-6 Concrete Mix Design Requirements (Not applicable to Mass Concrete) OLD NEW Maximum Maximum Maximum %SCM Minimum 28-day Intended Use * Slump 3137 Concrete Grade Mix Mix w/c ratio Cementitious (Fly Ash/ Compressive Range Spec. Number Number ║ Content (lbs/yd3) Slag/Ternary) Strength, f’c B Abutment, stems, wingwalls, paving brackets, pier columns Bridge 3Y43 3B52 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.1 and caps, pier struts Substructure 3A22 3F32 Curb and gutter 0.42 750 30/35/0 ½ - 3” 4500 psi 2.D.1 3Y22 # F 3A32 3F52 Flatwork Sidewalk, curb and gutter, slope paving, median sidewalk, 3Y32 3F57EX † 0.45 750 25/30/0 2 - 5” 4500 psi 2.D.1 driveway entrances, ADA pedestrian sidewalk 3A34 3F52CO ‡ 1A43 1G52 Footings and pilecap 0.55 750 30/35/40 2 - 5” 4500 psi 2.D.1

G Footings, pilecap, walls, cast-in-place manholes and catch 3A43 General basins, fence posts, signal bases, light pole foundations, 3B42 3G52 0.45 750 30/35/40 2 - 5” 4500 psi 2.D.1 Concrete erosion control structures, cast-in-place box culverts, culvert 3Y43 headwalls, open flumes, cast-in-place wall stems

M 3Y12 3M12 Slipform barrier, Median barrier, non-bridge 0.42 750 30/35/40 ½ - 1” # 4500 psi 2.D.1 Median Barrier 3Y32 3M52 Barrier, Median barrier, non-bridge 0.45 750 30/35/40 2 - 5” 4500 psi 2.D.1 P 1A43 1P42 MSE and gravity wall leveling pad 0.63 750 30/35/40 2 - 4” 3000 psi 2.D.1 Piling 1C62 1P62 Piling, spread footing leveling pad 0.63 750 30/35/40 3 - 6” 3000 psi 2.D.1 R 3A32 Pavement 3R52 CPR - Full depth concrete repairs, concrete base 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.3 3B42 Rehabilitation 3Y16 3S12 Slipform bridge barrier, parapets, end post 0.42 750 30/35/40 ½ - 1” # 4000 psi 2.D.2 S 3A32 Bridge 3A42 Median barrier, raised median, pilaster, curb, sidewalk, Superstructure 3Y43 3S52 approach panel, formed bridge barrier, parapet, end post, 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.2 3Y46 collar 3Y46A 1X62 X 1X62 Cofferdam seals, rock sockets, drilled shafts 0.45 750 30/35/40 3 - 6” 5000 psi 2.D.1 Miscellaneous 1X46 Bridge 3X46 3X62 Drilled shafts above frost line 0.45 750 30/35/40 3 - 6” 5000 psi 2.D.1 3Y33 3Y33A 3Y42-M § Bridge decks, integral abutment diaphragms, pier continuity 0.45 750 30/35/40 2 - 4” 4000 psi 2.D.2 Y 3Y36 3Y42-S § diaphragms, expansion joint replacement mix Bridge Deck 3Y36A 3A37 3Y47 ** Deck patching mix 0.45 750 30/35/40 2 - 4” 4000 psi 2.D.2 3Y37 * If the intended use is not included elsewhere in the Specification or Special Provisions, use mix 3G52, unless otherwise directed by the Engineer. ║ The minimum water/cement (w/c) ratio is 0.30. † Mix 3F57EX requires the use of Coarse Aggregate Designation “7”, “2” or “3” for the 4th digit in accordance with Table 2461-3. ‡ Identify specific color used on the certificate of compliance. Colored concrete is only allowed when specified in the plans or the Contract. # Adjust slump in accordance with 2461.3.G.7.a for slipform concrete placement. § The “-S” indicates a bridge deck with a structural slab and “-M” indicates a monolithic bridge deck. ** Mix 3Y47 requires the use of Coarse Aggregate Designation “7” or “3” for the 4th digit in accordance with Table 2461-3.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 41

S-37.5 Table 2461-7 of MnDOT 2461.2.F.2.b(3) shall be deleted and replaced with the following:

Table 2461-7 High-Early (HE) Concrete Requirements (Not applicable to Bridge Superstructure or Mass Concrete) Maximum Minimum Minimum Concrete Minimum Mix Maximum Cementitious Slump Strength 28-day 3137 Grades Time to Number w/c ratio Content Range to Compressive Spec. Allowed Opening (lbs/ yd3) * Opening Strength, f’c 1PHE62 ║ P - 0.63 750 3 - 6” - 3000 psi 2.D.1

3HE32 F 48 hrs 0.42 750 1 – 3” † 3000 psi 4500 psi 2.D.1

3HE52 B, F, G 48 hrs 0.42 750 2 – 5” 3000 psi 4500 psi 2.D.1 Y 3YHE52 (Repairs 48 hrs 0.42 750 2 – 5” 3000 psi 4000 psi 2.D.2 Only) R 3RHE52 (Repairs 48 hrs 0.42 750 2 – 5” 3000 psi 4000 psi 2.D.3 Only) * Supplementary Cementitious Materials allowed. ║ Used only for placing concrete in piles during freezing temperatures, provide 30 percent additional cement to the concrete mix for concrete 10 feet below the ground line or water line in accordance with 2452.3.D.6, “Cast- in-Place Concrete Piles.” † Adjust slump in accordance with 2461.3.G.7.a,”Concrete Placed by the Slip-form Method.”

S-37.6 Table 2461-8 of MnDOT 2461.2.F.2.b(3) shall be deleted and replaced with the following:

Table 2461-8 Project Specific Contractor Designed Mixes Concrete Grade Intended Use Specification 3137 Spec. A Concrete Pavement 2301 2.D.3 M, V, W, Z Precast Concrete 2462 Varies HPC High Performance Concrete Special Provision 2401 2.D.2 MC Mass Concrete Special Provision 2401 Varies SCC Self-consolidating Concrete Special Provision 2401 Varies CLSM Cellular Concrete Grout 2519 None All concrete grades Delivery time is > 90 minutes 2461.3.G.3.a Varies

S-37.7 MnDOT 2461.2.F.3 shall be deleted and replaced with the following:

F.3 Submittal Requirements At least 21 calendar days before initial placement of the concrete, submit the appropriate General Concrete Mix Design Submittal form to the Engineer for approval. Always use the most current forms available from the MnDOT Concrete Engineering Website.

Design the concrete mix to an absolute volume of 27.00 – 27.27 cu. ft.

The Engineer will: (1) Provide specific gravity and absorption data using oven dry (OD) weights for mix design calculations. (2) Review the mix design submittal and approve the materials and mix design for compliance with the Specifications.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 42

Table 2461-9 defines the mix design submittal requirements for Level 1 and Level 2 Mixes.

S-37.8 Table 2461-9 of MnDOT 2461.2.F.3 shall be deleted and replaced with the following:

Table 2461-9 Mix Design Submittal Requirements SCM Preliminary Fine Aggregate Gradation Substitution Test Data Submittal Package Limit Requirements Limits Requirements Level 1 Fly Ash: 0 – 40 – 45% of General Concrete Mixes 15% total aggregate 3126 and 3137 None Mix Design * Slag: 0 – 35% by volume ║ Use Either: Use Either: Fly Ash: > • General Concrete Level 2 • 3126 and 3137 15% None 2461.2.F.3.a Mix Design Mixes • Job Mix Ternary: Any • General Concrete Formula (JMF) Mix Design (JMF) * High Early concrete in accordance with Table 2461-7 is defined as a Level 1 Mix. ║ Fine aggregate limit does not apply to exposed aggregate concrete mixes.

S-37.9 The second paragraph of MnDOT 2461.2.F.3.a(1) shall be deleted and replaced with the following:

The Engineer considers a suitable experience record to have the following characteristics as compared to the proposed mix:

(A) A required average strength (f’cr) no greater than 1000 psi above the required 28-day compressive strength, (B) Same type or grade of cementitious materials, (C) Same class of coarse aggregate, (D) Same supplementary cementitious proportion, (E) Individual aggregate weights within 10% of the proposed, (F) Water/Cement ratio no greater than 0.45, (G) Total cementitious weight within 5% of proposed, and (H) Batching conditions and testing procedures similar to those expected for the proposed work.

S-37.10 Table 2461-10 of MnDOT 2461.2.F.3.b shall be deleted and replaced with the following:

Table 2461-10 Required Average Strength (f’cr) Equations* Required Average Strength f’c ≤ 5000 psi* f’cr = f’c + 1.34S OR f’cr = f’c + 2.33S – 500 f’c > 5000 psi f’cr = 0.90f’c + 2.33S *When f’c ≤ 5000 psi, f’cr is the larger value computed from the equations.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 43

S-37.11 Table 2461-11 of MnDOT 2461.2.F.4 shall be deleted and replaced with the following:

Table 2461-11 Mix Design Adjustments Requirements Mix Design Resubmittal Type of Change or Adjustment Requirements • Cementitious Sources • Admixture Sources No resubmittal required • Admixture Dosage Rate Level 1 • Aggregate Sources Mixes • Aggregate Proportions Resubmittal of Mix Design • Any cementitious proportion (≤ 15% max fly ash) Resubmittal in accordance with • Any cementitious proportion (> 15% max fly ash) 2461.2.F.3.a • Cementitious Sources No resubmittal required • Admixture Dosage Rate • Aggregate Source, no change in Aggregate Class • ≤ 5% Total Cementitious Resubmittal of Mix Design Level 2 • ≤ 10% Individual Aggregate Weights Mixes • Aggregate Source and Class of Coarse Aggregate • Supplementary Cementitious Proportion Resubmittal in accordance with • > 5% Total Cementitious 2461.2.F.3.a • > 10% Individual Aggregate Weights • Admixture Sources * Only one (1) increase in total cementitious allowed per mix design, next adjustment requires resubmittal in accordance with 2461.2.F.3.a, “Preliminary Test Data Requirements for Level 2 Mixes”

S-37.12 MnDOT 2461.3.D shall be deleted and replaced with the following:

D Batching Requirements The Engineer will allow only Large Capacity Scale companies authorized by the Minnesota Department of Commerce, Weights and Measures Division to calibrate weighting equipment and meters for MnDOT projects. A list of authorized companies is available from the MnDOT Concrete Engineering Unit website.

Calibration of weighing equipment is required within three months prior to plant certification each calendar year. Calibrate weighing equipment and perform spot checks in accordance with the Concrete Manual.

S-37.13 The second paragraph of MnDOT 2461.3.D.1.c shall be deleted and replaced with the following:

Calibration of the water meter is required within three months prior to plant certification each calendar year. Calibrate the water meter and perform spot checks in accordance with the Concrete Manual.

S-37.14 MnDOT 2461.3.F through MnDOT 2461.3.F.5.f shall be deleted and replaced with the following:

F Certified Ready-Mix Concrete Provide concrete from a certified ready-mix plant listed on the MnDOT Concrete Engineering Unit website. Ensure the Producer performs quality control of concrete production and complies with the MnDOT Certified Ready-Mix Plant Program.

Provide batches for a delivered load of concrete in sizes of at least 1 cu. yd.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 44

The Engineer may reject ready-mix concrete delivered to the work site that does not meet the specified requirements for delivery time, consistency, quality, air content, or other properties, as unauthorized or unacceptable work in accordance with 1512, “Unacceptable and Unauthorized Work.”

F.1 Certified Ready-Mix Plant Program The Producer will perform Quality Control (QC) under the certification program for ready-mix concrete plants in accordance with 2461.3.F.4, “Contractor Quality Control.” The Engineer will perform Quality Assurance (QA) as part of the acceptance process in accordance with 2461.3.F.5, “Agency Quality Assurance.”

F.1.a Plant Certification Prior to the production of Department concrete each construction season, a MnDOT Certified Concrete Plant Technician, representing the Department, shall perform a thorough on-site inspection of the concrete plant with a MnDOT Certified Concrete Plant Technician, representing the Producer.

In order to obtain certification, complete the following:

(1) The Producer will complete MnDOT Form 2163, Concrete Plant Contact Report, prior to the on-site inspection with the Department Representative. (1.1) A MnDOT Certified Concrete Plant Technician, representing the Producer, signs the Concrete Plant Contact Report certifying compliance with the Certified Ready Mix requirements and continual maintenance of the plant to assure that the plant can produce concrete meeting MnDOT Specifications. (1.2) A MnDOT Certified Concrete Plant Technician, representing the Department, signs the Concrete Plant Contact Report signifying that the plant complies with all requirements prior to concrete production. (2) Identify persons responsible for testing and overseeing plant operations on MnDOT Form 2163, Concrete Plant Contact Report. Provide their email, cell phone number, and MnDOT Technical Certification number. (3) Include a site map showing stockpile locations identified with the MnDOT pit number. (4) Provide cementitious and admixture samples. (5) Provide a computerized batching system capable of meeting the requirements of 2461.3.F.2, “Certificate of Compliance.” (6) Provide continuous access on-site to the Concrete Manual available from MnDOT’s website. (7) Supply a working email address, including an active internet connection, at the certified ready-mix plant. (8) Provide calibrated electronic scales for weighing materials. (9) Provide facilities in accordance with 1604, “Plant Inspection – Commercial Facility,” for the use of the plant technician in performing tests.

The Department Representative will submit the completed Contact Report and current Certificate of Compliance to the MnDOT Concrete Engineer for final determination of certification.

F.1.b Maintaining Plant Certification The Producer will maintain plant certification by:

(1) Displaying the current Contact Report and site map in plain sight at all times. (2) Updating the Contact Report with any material or equipment changes and submitting to the Department. (3) Making Producer Plant QC Workbook and QC charts available electronically at all times. (4) Performing the responsibilities identified in 2461.3.F.4, “Contractor Quality Control.” (5) Supplying the following information at the request of the Engineer: (5.1) Approved mix design sheets, (5.2) Agency cementitious and admixture test results, (5.3) Agency verification gradation test results, Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 45

(5.4) Aggregate quality test results. (6) Keeping plant reports, charts, and supporting documentation on file at the plant site for 5 calendar years.

F.1.c Certified Ready-Mix Plant Decertification The Engineer may decertify the plant and halt production of concrete under any of the following conditions: (1) Unauthorized procedural, material, or equipment changes made after the completion of the Concrete Plant Contact Report, (2) Failure to meet the required testing rates, (3) Failure to complete required documents, (4) Failure to provide competent MnDOT Certified Plant Technicians, (5) Disregard of any of the requirements of 2461.3.F, “Certified Ready-Mix Concrete,” or (6) Falsification of test records or certificates of compliance.

F.2 Certificate of Compliance Provide a computerized Certificate of Compliance with each truckload of ready-mixed concrete at the time of delivery. The Department defines computerized to mean a document that records mix design quantities from load cells and meters.

If the computer that generates the Certificate of Compliance malfunctions, the Engineer may allow the Contractor to finish any pours in progress if the Producer issues a handwritten MnDOT Form 0042, Certificate of Compliance with each load. The Engineer will not allow the Producer to begin new pours without a working computerized Certificate of Compliance.

Provide a computerized Certificate of Compliance that includes all of the following information: (1) Name of the ready-mix concrete plant, (2) Name of the Contractor, (3) Date, (4) State Project Number (SP) or (SAP), (5) Bridge Number (if applicable), (6) Time concrete was batched, (7) Truck number, (8) Quantity of concrete in this load, (9) Running total of each type of concrete, each day for each project, (10) Type of concrete (MnDOT Mix Designation Number), (11) Cementitious materials using MnDOT Standard Abbreviations, (12) Admixtures using MnDOT Standard Abbreviations, (13) Aggregate sources using 5 digit State Pit Numbers, (14) Admixture quantity in fluid ounces per 100 lb of cementitious materials or ounces per cubic yard, (15) Batch weights in columns in accordance with Table 2461-12: (15.1) Print in order a through k. (15.2) Use formula to calculate weights. (15.3) Head columns with Standard Labels.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 46

Table 2461-12 Standard Certificate of Compliance Labels Formula Letter Formula Standard Label a Ingredients (aggregate, cementitious, water, admixture type) — Ingredient b Product Source (MnDOT Standard Abbreviation) — Source c Total Moisture Factor (in decimals to 3 places) — MCFac d Absorption Factor (in decimals to 3 places) — AbsFac e Mix design oven dry (OD) weights, lb/cu. yd — OD f Absorbed moisture in the aggregates, lb/cu. yd (e × d) Abs g Saturated surface dry (SSD) weights for aggregates, lb/cu. yd) (e + f) SSD h Free moisture, lb/cu. yd (c - d) × e Free Mst i Target weights for one cubic yard of concrete, lb/cu. yd (g + h) CY Targ (cu. yd × i) j Target batch weights, lb Target [cu. m × i] k Actual batch weights, lb — Actual NOTE: Actual cubic yards batched may vary due to differences in air content, weight tolerances, specific gravities of aggregates, and other variables.

(16) Total Water (Batch Water + Free Moisture) in pounds, (17) Water available to add [(Mix Design Water × Batch Size) – Total water] in gallons, (18) Space to note the water adjustment information, including: (18.1) Water in gallons added to truck at plant (filled in by Producer, enter zero if no water is added), (18.2) Water in gallons added to truck at the jobsite (filled in by Producer or Engineer, enter zero if no water is added), and (18.3) Total actual water in pounds (Total Water from Certificate of Compliance plus any additions). (19) The following information printed with enough room beside each item to allow the Engineer to record the test results: (19.1) Air content, (19.2) Air temperature, (19.3) Concrete temperature, (19.4) Slump, (19.5) Cylinder number, (19.6) Location or part of structure, (19.7) Time discharge, and (19.8) Signature of Inspector. (20) Location for the Producer signature, (21) For colored concrete, final color.

F.3 Definitions The Department defines ready-mix concrete as one of the following: (1) Central-mixed concrete proportioned and mixed in a stationary plant and hauled to the point of placement in revolving drum agitator trucks or a truck mixer, or (2) Truck-mixed concrete proportioned in a stationary plant and fully mixed in truck mixers.

Table 2461-13 defines commonly used certified ready-mix terms.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 47

Table 2461-13 Certified Ready-Mix Terminology Term Definition Mix design water The maximum allowable water content for 1 cu. yd of concrete. Total moisture Factor used to determine total amount of water carried by a given wet aggregate. factor Factor used to determine the water contained within the pores of the aggregate and Absorption factor is held within the particles by capillary force. The water that is carried on the surface of the aggregate that becomes part of the Free moisture total water. Water actually batched into the truck by the batcher. Batch water includes potable Batch water water and clarified water. Batch water added to free moisture. Total water may also include the water used Total water in diluting admixture solutions. Temper water Water added in mixer to adjust slump. The water in the concrete mixture at the time of placement from any source other than the amount absorbed by the aggregate. It includes all batch water placed in the Total actual water mixer, free moisture on the aggregate and any water added to the ready mix truck prior to placement. Ready-Mix Party that is producing the concrete for the Contract. It is understood that the Producer or Ready-Mix Producer is the agent of the Contractor. “Producer” Water/Cement (w/c) W/C ratio is defined as the ratio of the total water weight to the total cementitious Ratio weight, which includes cement and supplementary cementitious materials. Real time The actual time during which something takes place.

F.4 Contractor Quality Control (QC) The Producer’s daily responsibilities include the following: (1) Provide qualified personnel. (2) Maintain laboratory equipment within allowable tolerances. (3) Randomly spot check concrete batching to verify batch weights and tolerances. (4) Check the bins and piles for segregation, contamination, or interblending of the aggregates. (5) Check that mix trucks are clean, blades are not worn, and revolution counters are working properly.

F.4.a Personnel The Producer will provide the following personnel: (1) Quality Control Plant Technician(s) to perform all testing and QC requirements of 2461. The QC Plant Technician shall hold a current MnDOT Concrete Plant Certification. (2) Quality Control Supervisor responsible for oversight of all QC testing and daily plant operations. The Quality Control Supervisor shall hold a current MnDOT Concrete Plant Certification and is required to remain on-site during concrete production or have cellular phone availability. (3) Quality Control Manager responsible for oversight of the Quality Control Supervisor and the certified ready-mix plant program.

F.4.b Sampling and Testing Take aggregate, cementitious, and admixtures samples in accordance with ASTM D 3665, Section 5, at a rate defined in the Schedule of Materials Control. Perform sampling and testing in accordance with the Concrete Manual. The Engineer may oversee the QC sampling and testing process.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 48

Perform gradation and moisture testing at the certified ready-mix plant site. Use mechanical shakers for sieve analysis.

Provide equipment and perform calibrations meeting the requirements of the following: (1) AASHTO T 27, “Sieve Analysis of Fine and Coarse Aggregates,” (2) AASHTO T 255, “Total Moisture Content of Aggregate by Drying,” (3) AASHTO M 92, “Wire-cloth Sieves for Testing Purpose,” and (4) AASHTO M 231, “Weighing Devices Used in the Testing of Materials.”

F.4.c Aggregate Gradations Complete the Concrete Aggregate Worksheet for each aggregate size and source.

If a QC gradation fails, retest immediately documenting both results. If an additional QC test is required for that week, the Engineer will not allow a retest gradation as a substitute for a QC gradation. The Engineer will not allow a verification companion gradation as a substitute for a QC gradation.

Identify QC companion samples with the following information: (1) Date (2) Test number (3) Time (4) Type of material (5) Plant (6) Sampling location

F.4.d Moisture Content Determine the moisture content using the oven-dry method in the Concrete Manual. Moisture probes to determine moisture content in the aggregates are not allowed without the approval of the Engineer.

Complete the Batching Report for each aggregate size and source.

Observe the batch person enter moisture contents into the batching system. Verify the moisture contents were entered correctly on the Certificate of Compliance.

F.4.e Concrete Ready-Mix Plant QC Workbook Complete the Concrete Ready-Mix Plant QC Workbook which includes all of the following documents: (1) Diary (2) Batching Report (3) Concrete Aggregate Worksheet (4) Weekly Concrete Aggregate Report (5) JMF Concrete Aggregate Worksheet (6) JMF Weekly Concrete Aggregate Report

The Producer will maintain the Concrete Ready-Mix Plant QC Workbook in real time using their full name for the diary and each test performed.

The Producer’s designated Quality Control Supervisor will review and submit to the Engineer and the MnDOT Concrete Engineering Unit by the Tuesday immediately following the previous week’s production.

F.4.f Aggregate Gradation Control Charts and Sample Log Complete the Aggregate Gradation Control Charts in real time for each aggregate size and aggregate source by recording Producer QC gradation and Verification Companion gradation results. These results are included in the moving average calculation.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 49

Complete Sample Log in real time for all samples taken as follows: (1) Record all aggregate samples taken by the Agency. (2) Record cementitious and admixture samples taken by the Producer and picked up by the Agency.

F.4.g Signing the Certificate of Compliance The Producer’s MnDOT Certified Concrete Plant Technician will: (1) Review the first Certificate of Compliance for each mix type, each day, for accuracy; and (2) Legibly hand sign the Certificate of Compliance at a location designated for Producer signature signifying agreement to the terms of this program and to certify that the materials comply with the requirements of the Contract; and (3) Print their name and write their MnDOT Technical Certification Number next to their signature.

F.5 Agency Quality Assurance (QA) The Engineer’s responsibilities each time the plant is visited include the following: (1) Confirm the Concrete Ready-Mix Plant QC Workbook and Aggregate Gradation Control Charts are accurate and up-to-date. (2) Check Certificate of Compliance for completeness and accuracy. (3) Spot check concrete batching to verify batch weights and tolerances. (4) Check the bins and stockpiles for segregation, contamination, and interblending of the aggregates. (5) Obtain aggregate samples per Schedule of Materials Control. (6) Observe Producer’s Certified Technician obtain aggregate samples and run gradation and moisture tests when possible. (7) Verify cementitious and admixtures are certified and approved. (8) Collect cementitious and admixtures samples per the 2019 SALT Schedule of Material Control. (9) Provide the following Agency test results to the Producer in a timely manner: (a) Cementitious Materials (b) Admixtures (c) Gradations (d) Coarse Aggregate Quality (10) If any equipment malfunctions, testing procedures or test results are questionable, or unusual activity is occurring during the plant visit perform the following: (a) Continue monitoring at the plant and document observations in the diary. (b) Investigate to determine the origin of the concern and document the resolution. (c) Contact Independent Assurance Inspector, Project Engineer or Concrete Engineering Unit when necessary.

F.5.a Personnel The Department will provide MnDOT Certified Concrete Plant Technicians to perform all of the duties of 2461.3.F.5, “Agency Quality Assurance.”

F.5.b Sampling and Testing The Engineer will: (1) Take all samples randomly in accordance with ASTM D 3665, Section 5, at a rate defined in the Schedule of Materials Control. (2) Perform all sampling and testing in accordance with the Concrete Manual. (3) Use mechanical shakers for sieve analysis.

F.5.c Aggregate Gradations

The Engineer will: (1) Complete the Weekly Ready-Mix Plant Report for each aggregate size and source. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 50

(2) Compare the Agency results with the Producer’s companion gradation result for compliance with lab/field tolerance in accordance with 2461.3.F.6.b, Lab Field Tolerance.

F.5.d Batch Weight Verification Each time the Engineer visits the plant, they will observe the actual water batched in a single load of concrete in accordance with the following: (1) Watching the ready-mix truck reverse the drum after washing, (2) Verifying use of the current moisture test, (3) Verifying that any additional water added to adjust the slump is recorded, and (4) Validating water weights on the load batched and comparing the total water with the design water.

The Engineer will document the actual water batched on the Weekly Ready-Mix Plant Report.

F.5.e Concrete Ready-Mix Plant QA Workbook The Engineer will complete the Concrete Ready-Mix Plant QA Workbook in real time which includes all of the following documents: (1) Diary (2) Weekly Certified Ready-Mix Plant Report (3) Concrete Aggregate Worksheet if gradation testing performed in the field (4) JMF Concrete Aggregate Worksheet if gradation testing performed in the field

Submit to the Engineer and the Concrete Engineering Unit by the Thursday immediately following the previous week’s production.

F.5.f Non-compliance with Certified Ready-Mix Plant Program If the Engineer observes the Producer not complying with the requirements of the Certified Ready- Mix Plant Program, the Engineer will perform the following: (1) Verbally notify and promptly email the Producer and the Engineer the list of observed deficiencies and provide a deadline to correct the non-compliance. (2) If non-compliance is not corrected by the deadline, notify the Contractor and Producer that concrete production is unauthorized in accordance with 1512, “Unacceptable and Unauthorized Work.”

The Engineer will determine if the severity of the non-compliance results in decertification of the plant in accordance with 2461.3.F.1.c, “Certified Ready-Mix Plant Decertification.”

S-37.15 MnDOT 2461.3.G.3.a shall be deleted and replaced with the following:

G.3.a Delivery Time Beyond 90 Minutes If the haul time does not facilitate mixing and placing the concrete within 90 minutes, perform the following for each proposed concrete mix to extend the delivery time to 120 minutes. Extending the delivery time beyond 120 minutes will require additional testing at 30-minute intervals up to the maximum desired delivery time as directed by the Engineer.

The Engineer will allow trial batching at an AASHTO accredited laboratory to pre-qualify the concrete mix in accordance with 2461.3.G.3.a(1), “Lab Trial Batching.”

The Engineer may waive the lab trial batching requirement and allow only field trial batching of the proposed mix to extend the delivery time on an individual project in accordance with 2461.3.G.3.a(2), “Field Trial Batching.”

Upon completion of the trial batching, provide the trial batching test results and proposed mix design to the Concrete Engineer. Submit the Contractor mix design in accordance with 2461.2.F.2.b, Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 51

“Contractor Designed Concrete Mixes.” Final approval of the mixture is based on satisfactory field placement and performance.

G.3.a(1) Lab Trial Batching Contact the MnDOT Concrete Engineering Unit a minimum of 2 days before trial batching.

Ensure the admixture manufacturer’s technical representative is present during the trial batching.

Laboratory trial batch and test the proposed mix in accordance with the following: (1) After adding all admixtures to the concrete mixture, measure the slump, air content, unit weight, and temperature immediately after batching, at 90 minutes, and at 120 minutes (2) Fabricate concrete cylinders for compressive strength at 90 minutes and at 120 minutes (sets of 3). Test all of the cylinders for compressive strength at 28 days (3) Fabricate concrete cylinders for hardened air content testing at 90 minutes and at 120 minutes (sets of 5). Determine the hardened air content (ASTM C457) at a minimum of 7 days on 2 samples representing 90 minutes and 2 samples representing 120 minutes. Provide MnDOT with the other 6 samples for testing at their discretion. Retain any hardened concrete test specimens for a minimum of 90 days for MnDOT to examine at their discretion.

Once accepted by the Engineer, the Department will consider the laboratory trial batching acceptable for use for five (5) years; unless the Engineer determines the material sources have changed significantly since the initial laboratory testing and acceptance.

G.3.a(2) Field Trial Batching Submit a QC Plan for extending the delivery time beyond 90 minutes for review and approval to the Engineer a minimum of 2 days before field trial batching.

The QC plan includes the proposed materials, batching sequences, anticipated timeline for admixture and/or water adjustments at the project site, delivery method and anticipated typical travel time to project site.

The Contractor must demonstrate to the Engineer the ability to properly mix, control, and place the concrete in accordance with the proposed QC plan and the Contract.

Perform field trial batching on the proposed mix in the presence of the Engineer in accordance with the following: (1) Batch a minimum 5 cubic yards of concrete utilizing the same materials and methods intended for use when supplying concrete placed into the permanent work (2) Maintain the ready-mix truck in transit; by either driving around the yard or on the roadway; and maintain the drum speed at 5 to 7 revolutions per minute for the entire 120 minutes (3) Measure the slump, air content, unit weight and temperature after making all admixtures and water adjustments to the concrete mixture at 90 minutes and 120 minutes (4) Fabricate concrete cylinders for compressive strength at 90 minutes and at 120 minutes (sets of 3). Test all of the cylinders for compressive strength at 7 days

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 52

(5) Fabricate concrete cylinders for hardened air content testing at 90 minutes and at 120 minutes (sets of 2). Determine the hardened air content (ASTM C457) at a minimum of 7 days on 1 sample representing 90 minutes and 1 sample representing 120 minutes. Provide MnDOT with the other 2 samples for testing at their discretion. Retain any hardened concrete test specimens for a minimum of 90 days for MnDOT to examine at their discretion (6) Incorporate the trial batched concrete into other work with the approval of the Engineer

S-37.16 MnDOT 2461.3.G.5 through MnDOT 2461.3.G.5.d shall be deleted and replaced with the following:

G.5 Concrete Strength

G.5.a Concrete Cylinder Requirements The Contractor and Engineer will perform random sampling and testing in accordance with ASTM C172, C31, C39 and the Schedule of Materials Control.

Anyone performing concrete strength testing of cylinders is required to hold one of the following current certifications: (1) ACI Concrete Strength Testing Technician Certification (2) MnDOT Strength Testing Technician Certification (3) WisDOT Strength Testing Technician Certification

Anyone fabricating concrete cylinders or beams is required to hold either a current ACI Field 1 Technician Certification or a MnDOT Field 1 Technician Certification.

G.5.b Standard Strength Cylinders All standard strength cylinders have a minimum 28-day compressive strength requirement unless modified elsewhere in the Contract.

The Engineer will perform the following for standard strength cylinders: (1) Cast cylinders (sets of 3) for testing in accordance with the Schedule of Materials Control or as modified in the Contract (2) Mark cylinders for identification of the represented unit or section of concrete in accordance with the following: (1.1, 1.2, 1.3/ 2.1, 2.2, 2.3/ 3.1, 3.2, etc.). In order to differentiate between portions of a project, prefixes and suffixes are allowed (3) Complete the MnDOT Concrete Cylinder Identification Card including the results for air content, slump (if required), concrete, and air temperature testing from the same load

G.5.b(1) Curing Standard Strength Cylinders Properly cure standard strength cylinders during each specified curing period in accordance with the following: (1) Initial curing period as immediately after final for a period of up to 48 hours (2) Intermediate curing period as the time between specimen pickup from the initial curing site and delivery to the laboratory for final curing, Intermediate curing period is up to 7 days from the day of casting. Cure the standard strength cylinders in the Contractor provided moist curing environment (3) Final Curing Period as the time when cylinders are cured in the laboratory lasts a minimum of 21 days

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 53

G.5.b(2) Moist Curing Environment At least 24 hours before concrete placement, provide moist curing environment(s) of adequate size and number, including ancillary equipment and materials, necessary to maintain moist curing environment(s) in accordance with ASTM C31, 2031, “Field and Office Laboratory,” and the following:

For each separate moist curing environment: (1) Provide a calibrated waterproof digital temperature recording device that records the daily maximum and minimum ambient temperatures for the previous 7 days. (2) During the initial curing period, maintain the standard strength cylinders or beams in an ambient temperature range from 60°F to 80°F. (3) During the intermediate curing period, fully immerse the cylinders with lids in water maintained at a temperature from 60°F to 80°F. The Engineer will monitor the daily temperatures of the curing environments. Agency monitoring does not relieve the Contractor of the responsibility to maintain the water temperature as specified herein.

If the Contractor fails to comply with the requirements shown here-in, the Engineer may delay concrete placement and will consider any concrete incorporated into the work as unauthorized in accordance with 1512.2, “Unauthorized Work.” The Engineer will consider any delays to the Contract resulting from unauthorized work as non-excusable in accordance with 1806.2.C, “Non-Excusable Delays.”

All costs related to providing and maintaining moist curing environments is considered incidental.

G.5.b(3) Transporting Cylinders After the initial curing period, the Engineer will both transport and further cure the cylinders using intermediate curing or final curing conditions.

The Engineer will transport the cylinders from the initial curing site in accordance with the following: (1) Transport all grades of concrete except mass concrete (Grade MC) a minimum of 16 hours after casting (2) Transport mass concrete a minimum of at least 24 hours after casting (3) Transport high early strength concrete a minimum of at least 12 hours after casting (4) With securely placed tight fitting plastic caps on plastic molds, or by other methods to prevent moisture loss (5) Protected from jarring, bouncing, and freezing (6) No greater than 4 hours, unless cylinders are maintained in the moistened condition at ambient temperature of 60°F to 80°F

G.5.b(4) Testing Cylinders The Engineer will perform compressive strength testing on the standard strength cylinders in accordance with ASTM C39 during the Departments normal laboratory operating hours. The Department will report the results in accordance with the Laboratory Manual.

G.5.c Field Control Strength Cylinders The Engineer will use field control cylinders to determine when the sequence of construction operations is dependent upon the rate of concrete strength development. The Engineer will cast field control cylinders to determine when the concrete attains the required strength for desired field control limitations.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 54

In lieu of field control cylinders, the Engineer will allow the Contractor to submit a strength- maturity relationship curve for use in accordance with 2461.3.G.6, “Estimating Concrete Strength by the Maturity Method.”

The Engineer will perform the following for field control strength cylinders: (1) Cast up to 3 field control cylinders per structure; the Contractor is responsible for any additional field control cylinders (2) Mark field control cylinders for identification of the represented unit or section of concrete in accordance with 2461.3.G.5.b, “Standard Strength Cylinders,” Note (2) (3) Complete the MnDOT Concrete Cylinder Identification Card including the results for air content, slump (if required), concrete, and air temperature testing from the same load

G.5.c(1) Curing Field Control Cylinders Cure field control concrete cylinders in the same location and under the same conditions as the concrete structure or unit involved.

The Engineer will allow “Match Curing of Concrete Test Specimens” method in accordance with AASHTO R72 modified as follows: (1) Provide an apparatus that consist of a monitoring and heating system capable of maintaining concrete cylinders at a temperature no greater than 5°F above the temperature of the concrete at a specific location in the member. A satisfactory system to continually monitor the concrete temperatures may include a temperature sensor in the concrete structure or unit involved, a controller, special insulated cylinder molds with built-in heating systems, and a temperature sensor in the molds. (2) When the temperature exceeds 5°F or the temperature monitoring system fails, the Engineer will not accept field control cylinder results.

G.5.c(2) Testing Cylinders The Engineer will perform compressive strength testing on the field control cylinders in accordance with ASTM C39 during the Departments normal laboratory operating hours.

If Project scheduling requires testing outside of the Departments’ laboratories normal operating hours or the Department’s nearest laboratory is greater than 30 miles from the project; Provide certified and calibrated hydraulic cylinder-testing machine within 30 miles of the project and at a location approved by the Engineer. Test the field control cylinders in the presence of the Engineer in accordance with ASTM C39.

G.5.d Strength Specimens for Concrete Paving Use flexural beams to determine strength or provide cylinders approved by the Engineer.

Cast standard beams or cylinders for testing at 28 days.

Cast a sufficient number of field control beams or field control cylinders to determine when the concrete attains the required strength for desired control limitations.

Cure the standard beams or cylinders in accordance with 2461.3.G.5.b(1), “Curing Standard Strength Cylinders,” and 2461.3.G.5.b(2), “Moist Curing Environment,” except standard beams are cured in intermediate curing conditions until broken at 28 days.

Cure the field control beams or cylinders in the same location and under the same conditions as the concrete pavement.

The Engineer will test the flexural beams and record the results on MnDOT Form 2162, Concrete Test Beam Data.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 55

If using cylinders, the Engineer will submit cylinders and a completed identification card to the Department’s Laboratory.

S-37.17 MnDOT 2461.3.G.5.e shall be deleted and replaced with the following:

G.5.e Concrete Compressive Strength The Concrete Engineer defines a strength test as the average strength of three (3) cylinders fabricated from the same sample of concrete and cured in accordance with the 2461.3.5.a and 2461.3.G.5.d.

The maximum allowable range between the individual cylinders in a strength test is 350 psi. The Engineer will remove all individual cylinder strengths that are more than 350 psi below the highest individual cylinder strength and recalculate the strength.

The Engineer will review standard strength test results for acceptance in accordance with Table 2461-17 and 2461.3.G.5.f.

Table 2461-17 Acceptance Criteria for Standard Strength Cylinders Strength Test Moving average of 3 consecutive strength tests * f’c ≤ 5000 psi > (f’c – 500 psi) ≥ f’c f’c > 5000 psi > 0.90 * f’c ≥ f’c * If a project does not establish a moving average of 3 consecutive strength tests, use the average of 2 strength tests to determine acceptance. If there is only a single strength test, contact the Engineer for recommendation.

S-37.18 MnDOT 2461.3.G.5.f shall be deleted and replaced with the following:

G.5.f Non-Conforming Material If the Contractor places concrete not meeting the strength requirements of 2461.3.G.5.e, “Concrete Compressive Strength” into the work, the Engineer may not accept nonconforming concrete at the contract unit price. The Engineer will evaluate non-conforming strength results in accordance with the following:

G.5.f(1) Strength Test ≤ 500 psi Below f’c If any strength test result shows a strength ≤ 500 psi below f’c and is not deficient due to erroneous/invalid strength tests as defined in 2461.3.G.5.f(4), “Moving Average Below f’c”, no additional investigation will occur and the Engineer will include the low strength test result in the moving average.

G.5.f(2) Strength Test > 500 psi Below f’c If any strength test result shows a strength > 500 psi below f’c and is not deficient due to erroneous/invalid strength tests as defined in 2461.3.G.5.f(4), “Moving Average Below f’c”, the Engineer will investigate to determine if the concrete has attained the critical load-carrying capacity.

The investigation may consist of, but is not limited to reviewing the following:

(A) Sampling and testing plastic concrete (B) Handling of cylinders (C) Cylinder curing procedures (D) Compressive strength testing procedures (E) Certificate of Compliances (F) Evaluation using Rebound Hammer (ASTM C803), Penetration Resistance (ASTM C805), or other method approved by the Engineer (G) Review of the design calculations for the concrete in question

If it is determined that the concrete represented by the standard strength test has attained the critical load carrying capacity, the Engineer will include the strength test in the moving average calculation. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 56

If it is determined that the concrete has not attained the critical load carrying capacity, the Engineer will direct the Contractor to remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and 1512, “Unacceptable and Unauthorized Work.” The Contractor may dispute the remove and replace order within 7 days of written notification by the Engineer. If the Contractor disputes the order, follow the dispute resolution coring procedure in accordance with 2461.3.G.5.f(3), “Dispute Resolution Coring for a Strength Test Failure.”

G.5.f(3) Dispute Resolution Coring for a Strength Test Failure The Engineer and Contractor will mutually agree on an Independent Third Party to core and test the concrete in accordance with ASTM C42 and the following: (A) The Engineer will identify a minimum of three (3) locations for the Independent Third Party to core. (B) The Independent Third Party will take one (1) core at each location. (C) The Independent Third Party will complete all coring within 14 days of notification of the low strength concrete. (D) The Contractor is responsible for ensuring the core holes are repaired.

The Engineer will review the core test results and evaluate in accordance with Table 2461-18, providing all other concrete tests meet requirements.

Table 2461-18 Evaluation of Core Test Results Engineer Cost of Core (average of 3 considers Coring and Resolution: cores) Test Results: concrete: Testing: ≥ 85% of f’c and Acceptable to No monetary reduction for single No individual core is Agency remain in place strength test failure. < 75% of f’c Remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and < 85% of f’c Unacceptable Contractor 1512, “Unacceptable and Unauthorized Work,” as directed by the Engineer, in conjunction with the Concrete Engineer.

G.5.f(4) Moving Average Below f’c If the moving average of three (3) consecutive strength tests is less than the required f’c, the Engineer will review the strength test results and determine if a new mix design is required.

The Engineer will remove any strength test results from the moving average if the following occurs: (A) After investigation, the deficient concrete strength is found to be caused by improper handling, curing, or testing of the cylinder; (B) Cylinders kept in the field longer than 7 days that negatively impact the moving average calculation; (C) The suspect concrete was removed and replaced; (D) Dispute resolution coring identified the concrete acceptable to remain in place.

For the quantity of non-conforming concrete not meeting the moving average of three (3) consecutive strength tests, the Engineer will make determinations regarding the disposition, payment, or removal of the concrete in accordance with Tables 2461-19.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 57

Table 2461-19 All Concrete Grades Moving average of 3 Monetary Reduction for Moving Average Failure * consecutive strength tests No deductions for the materials placed as approved by the > 98.0% of f’c Engineer. $20.00 per cubic yard or 10% of the Contractor-provided 93.0% to 98.0% of f’c invoice for quantity represented by test that brought moving average into non-conformance $50.00 per cubic yard or 25% of the Contractor-provided 87.5% to < 93.0% of f’c invoice for quantity represented by test that brought moving average into non-conformance Remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and 1512, “Unacceptable and Unauthorized Work,” as directed by the Engineer. < 87.5% of f’c If the Engineer determines the concrete can remain in place, the Engineer will adjust the concrete at a reduction of $100.00 per cubic yard or 50% of the Contractor- provided invoice for quantity represented by test that brought moving average into non-conformance.

S-37.19 MnDOT 2461.3.G.6 through 2461.3.G.6.e shall be deleted and replaced with the following:

G.6 Estimating Concrete Strength by the Maturity Method The Engineer will allow the maturity method to determine development of concrete strength to open to traffic loading or form removal. Use of this method requires the establishment of a relationship between concrete strength and the computed maturity index (using the Nurse-Saul method) for a specific concrete mixture. Use this method, in accordance with this Specification and the “Estimating Concrete Strength by the Maturity Method” procedure available from the MnDOT Concrete Engineering website to estimate the in-place strength of the concrete.

G.6.a Development of Strength-Maturity Relationship The Engineer will allow development of the maturity curve in a laboratory, at the concrete plant or at the project site.

Determine the strength development criteria based on the type of concrete in accordance with the following: (1) For concrete pavement: 2301.3.O, “Opening Pavement to Traffic” (2) For concrete pavement repairs: 2302.3.B.4, “Opening to Construction Equipment and Traffic” (3) For concrete structures: 2401.3.G, “Concrete Curing and Protection” (4) For sidewalks, driveway entrances and curb and gutter, a minimum of 3000 psi is required

Until an acceptable strength-maturity relationship (maturity curve) is established and approved by the Engineer, use concrete beams or cylinders to open to traffic loading or form removal.

G.6.a(1) Procedure Develop the strength-maturity relationship (maturity curve) to estimate concrete strength in accordance the “Estimating Concrete Strength by the Maturity Method” procedure available from the MnDOT Concrete Engineering Website and the following: (A) Cast and cure 12 beams or 15 cylinders, plus 2 additional beams or cylinders to embed temperature sensors Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 58

(B) Establish the maturity curve using the Concrete Maturity-Strength Development form. (C) Test three (3) strength specimens at testing ages specified in Table 2461-20 for the type of concrete work.

Table 2461-20 Chronological Testing Ages of Strength Specimens Type of Concrete Testing Ages * Test at least two (2) sets of strength specimens before and the remaining Concrete Pavement as defined in 2301, “Concrete Pavement” sets after the anticipated opening strength Normal Strength Concrete as defined in 2461, “Structural 1, 3, 7, 14 and 28 days Concrete” High-Early (HE) Concrete as defined in 2461, “Structural 12 hours, 1, 2, 7 and 28 days Concrete” Ultra High-Early (UHE) Concrete per Contract 3, 4 and 8 hours, 1 and 14 days * The Contractor may adjust the testing ages if approved by the Engineer

G.6.a(2) Equipment Provide the following equipment for determining the maturity: (1) Maturity meter or temperature sensor and data logger with a secure means of collecting, measuring, recording and storing temperature data that is unalterable (2) Beam or cylinder molds for development of the maturity curve and other concrete making and testing equipment

G.6.a(3) Estimating In-Place Strength Using Maturity Place concrete maturity meters or temperature sensors within the concrete in accordance with Table 2461-21.

Table 2461-21 Maturity Meter or Temperature Sensor Placement and Frequency Maturity Placement Frequency Application Embed at approximately mid-depth and Place one for each day within the last Concrete Paving approximately 18 (but no less than 12) hour of placement. Place additional inches from the edge of the pavement. sensors as necessary. Full Depth Embed at approximately mid-depth and Place one for each day within the last Concrete Pavement approximately 18 (but no less than 12) hour of placement. Place additional Repairs inches from the edge of the pavement. sensors as necessary. Place one for each day within the last Partial Depth Embed at least 2 inches from the surface. hour of placement. Place additional Concrete Repairs sensors as necessary. Sidewalk, Embed at approximately mid-depth and Place one for each day within the last Driveway approximately 18 (but no less than 12) hour of placement. Place additional Entrances, Curb inches from the edge of the pavement. sensors as necessary. and Gutter Attach to the reinforcing steel near the edge Place at least two for each concrete Concrete Structures of the exposed surface using a non-metallic element. fastener.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 59

The computed maturity results from each sensor will only apply to concrete placed under the following conditions: (1) The same mix designation and the same project as the test location (2) Placed on the same day and on, before, or within 50 feet after placement of the sensor (3) Cured under conditions similar to those of the test location

Record the maturity index (or temperature readings and calculate the maturity index) on the Maturity-Field Data form or as approved by the Engineer.

G.6.b Opening to Traffic Loading or Form Removal Prior to opening the concrete to traffic loading or removal of the forms, submit the maturity index results to the Engineer. The Engineer will review and verify the maturity index has reached the required TTF of the maturity curve developed for that concrete mix.

G.6.c Validation of Strength-Maturity Relationship for Continued Use When utilizing the maturity method on the project, perform a strength-maturity test for each mix used to ensure the concrete strength correlates with the current maturity-strength relationship (maturity curve) as follows: (1) Notify the Engineer at least 24 hours in advance of the specimen casting for the validation testing. (2) The Contractor or their Representative is responsible for casting, curing and testing three (3) beams or cylinders plus one additional beam or cylinder to embed the sensor. Cast the validation specimens at the concrete plant or at the project site. (a) If the maturity curve was initially developed in a laboratory, perform a validation strength-maturity test on the first day of concrete placement. (b) For slipform concrete paving utilizing a dedicated portable batching plant, perform a validation strength-maturity test once every fifteen (15) calendar days during plant production. (c) For all other concrete, if the maturity curve was developed greater than thirty (30) calendar days before the start of construction or has not been validated for thirty (30) calendar days, perform a validation strength-maturity test on the first day of concrete placement. The Engineer will allow a single validation strength- maturity test fabricated at the concrete plant to validate a maturity curve used on multiple projects. Validation strength-maturity tests fabricated at the project site only validate the maturity curve for that project. (3) The Contractor or representative is responsible for providing the curing environment for the specimens in accordance with the “Estimating Concrete Strength by the Maturity Method” procedure available from the MnDOT Concrete Engineering website. (4) Perform the validation testing as close as practically possible to the maturity value determined to represent the opening, loading or form removal strength criteria. Record the results of the tests on the Concrete Maturity-Strength Validation form and provide to the Engineer within 24 hours of the test completion. (5) If a specimen is obviously defective (i.e., out of round, not square, damaged due to handling), discard the specimen. If an individual specimen is greater than 10 percent for cylinders or 15 percent for beams outside the average of three specimens, consider the specimen defective and discard. When two of the specimens are defective, evaluate a new batch, unless additional acceptable specimens are available.

The Engineer may direct additional validation testing as necessary.

The Engineer will review the validation strength-maturity test results and determine if the validation testing confirms the maturity curve in accordance with Table 2461-22.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 60

Table 2461-22 Evaluation of Validation Strength-Maturity Test Results If the actual strength- Result Action maturity test falls: Within the 10% limits of the Maturity curve verified Continue using the current maturity curve maturity curve The Department will not consider > 10% higher than the the maturity curve verified, but Develop a new maturity curve at the maturity curve will continue to allow use of the discretion of the Contractor. maturity curve. 1. Develop a new maturity curve. > 10% lower than the The maturity curve will no longer 2. The Engineer will not allow the maturity curve be acceptable. maturity method for that concrete mix until a new maturity curve is developed.

G.6.d Changes in Concrete Mixture Perform a validation strength-maturity test in accordance with 2461.3.G.6.c, “Verify Strength- Maturity Relationship,” if any of the following changes occur: (1) Change in mixture proportions greater than 5% by weight (2) Increase in the water-cementitious materials ratio by more than 0.02 (3) Change in the cementitious source (4) Change in the class of coarse aggregate material

Evaluate validation strength-maturity test results in accordance with Table 2461-22.

G.6.e Maturity Meter Calibration Calibrate maturity meters yearly to ensure proper operation and temperature sensing in accordance with the “Estimating Concrete Strength by the Maturity Method” procedure available from the MnDOT Concrete Engineering website.

S-37.20 The first paragraph of MnDOT 2461.3.G.8 has been deleted and replaced with the following:

Maintain the air content of Type 3 general concrete at the specified target of 6.5 percent (+2.0 percent and −1.5 percent) of the measured volume of the plastic concrete in accordance with 1503, “Conformity with Contract Documents,” unless otherwise modified in the Contract. Maintain the air content of Type 3AGrout at the specified target of 10.0 percent (-2.0 percent and no maximum).

S-38 (2472) METAL REINFORCEMENT REVISED 08/09/18 SP2018-158.1 The provisions of MnDOT 2472 are modified with the following:

S-38.1 Delete and replace MnDOT 2472.4A with the following:

A Reinforcement Bars The Engineer will measure Reinforcement Bars, including reinforcement in bar mats, by the weight incorporated into the structure in accordance with 2472-3. The Engineer will only include quantities for splices shown in the plans.

Reinforcement bars may be marked in either U.S. Customary or metric sizes. The conversion shall be made per the following table:

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 61

Table 2472-3 Reinforcement Bars Theoretical Weights Nominal Dimensions U.S. Metric Nominal Dimensions Customary Bar Bar Diameter, in Area Weight, lb/ft Size* Size [mm] in2 [mm2] [kg/m] 3 10 0.375 [9.5] 0.11 [71] 0.376 [0.560] 4 13 0.500 [12.7] 0.20 [129] 0.668 [0.994] 5 16 0.625 [15.9] 0.31 [199] 1.043 [1.552] 6 19 0.750 [19.1] 0.44 [284] 1.502 [2.235] 7 22 0.875 [22.2] 0.60 [387] 2.044 [3.042] 8 25 1.000 [25.4] 0.79 [510] 2.670 [3.973] 9 29 1.128 [28.7] 1.00 [645] 3.400 [5.060] 10 32 1.270 [32.3] 1.27 [819] 4.303 [6.404] 11 36 1.410 [35.8] 1.56 [1006] 5.313 [7.907] 14 43 1.693 [43.0] 2.25 [1452] 7.650 [11.380] 18 57 2.257 [57.3] 4.00 [2581] 13.600 [20.240] * Bar designation numbers approximate the nominal diameter of the bar in millimeters

S-39 (2503) CONNECT TO EXISTING STORM SEWER REVISED 05/28/20 SP2018-171 This work consists of constructing connections into existing storm sewers in accordance with the following:

S-39.1 The Contractor shall field verify the location, elevation, size and type of existing storm sewer pipes or culverts to be connected to, prior to fabricating any drainage structures. Any differences from the plan will be reported to the engineer on shop drawings or another written format.

S-39.2 Measurement will be by the number of connections constructed as specified. Locations where a proposed drainage structure will be connected to an existing storm sewer or culvert which will be maintained both upstream and downstream of the proposed drainage structure will be measured as a single Connect to Existing Storm Sewer. Payment will be under Item 2503.602 (Connect to Existing Storm Sewer) at the Contract bid price per each, which shall be compensation in full for all work included under this section

S-40 (2506) MANHOLES AND CATCH BASINS REVISED 04/09/20

S-40.1 Adjusting rings shall be manufactured from High Density Polyethylene (H.D.P.E). Any existing rings shall be replaced with High Density Polyethylene (H.D.P.E.) rings. Butyl caulk sealant, or engineer approved equal, shall be used between all adjusting rings, the adjusting and the catch basin, and the adjusting ring and the casting in accordance with manufacturer instructions, MnDOT Standard Plates, and the Plans.

S-40.2 All mortar shall be air-entrained and fiber-reinforced.

S-40.3 All castings shall be set to final elevation prior to placement of the final lift of bituminous pavement. The contractor shall maintain traffic until paving and shall pave within three (3) calendar days of raising castings. Raised castings shall be protected from traffic with a bituminous pavement taper. The bituminous pavement taper shall not be removed until immediately prior to paving. The bituminous pavement taper shall be incidental, which shall include all work under this section including placement, compaction, traffic control, and removal. If the Contractor does not comply with the provisions within this section, a monetary deduction of $1000 per calendar day will be assessed to the Contractor.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 62

S-40.4 MnDOT 2506.2.A shall be deleted and replaced with the following:

A Concrete

A.1 Structural Concrete ...... 2461 Use 3G52 concrete.

A.2 Precast Concrete ...... 2462 Use 3W8X concrete.

S-40.5 MnDOT 2506.3.C shall be supplemented with the following:

All top of castings shall not exceed a 3/8-inch depth below final wearing course, as measured with a 10- foot straight edge centered on the structure and in accordance with the plans.

S-40.6 MnDOT 2506.5 (4) shall be replaced with the following:

(4) The contract unit price for drainage structure construction by the structure as individual units complete in place or linear foot includes the cost of providing, i

S-41 (2521) WALKS REVISED 04/09/20 SP2018-188.3 MnDOT 2521 is modified with the following:

S-41.1 The second sentence of MnDOT 2521.3.G shall be deleted and replaced with the following:

Perform vibratory operations and backfilling 72 h after placing the concrete or after the concrete reaches a compressive strength of at least 2,000 psi.

S-42 (2531) CONCRETE CURB AND GUTTER (ADA) SP2018-190 This work shall consist of constructing Concrete Curb and Gutter and the necessary Aggregate Base in accordance with the provisions of MnDOT 2531, other Contract provisions, and the following:

S-42.1 CONSTRUCTION REQUIREMENTS

Concrete Curb and Gutter - The curb and gutter shall be constructed to meet the details in the Plan. The transition from the existing curb and gutter section to the new curb and 24 inch gutter section should occur between 5 feet – 10 feet of the zero height curb. Curb shall be poured at 3% inflow around the radius or at a minimum distance of 10 feet from any zero height curb section when machine placed. The gutter inslope shall be constructed as detailed in the Plans. The gutter inslope transitions shall occur outside of the zero height curb area. The proposed gutter width shall be modified as necessary so as not to protrude into the adjacent travel lane with approval from the Engineer.

At all locations where new curb and gutter meets existing curb and gutter, place saw cut to leave a minimum 3 feet of in place curb and gutter between an existing joint and the proposed saw cut. If the 3 foot minimum cannot be maintained, place the saw cut over the existing joint. If construction joints are utilized within a quadrant radius Reinforcement bars shall be installed per Standard Plans 5-297.250 (Sheet 6 of 6). When not accounted for in the Plan, payment for these bars will be made under Item 2301.602 (Drill & Grout Reinforcement Bar (Epoxy Coated)) by the Each at the Predetermined Price of $10.00 per bar furnished and installed.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 63

The Contractor must form, at a minimum, the top 1.5 inches of the gutter face. The Contractor shall not use the existing roadway edge as a form for the top 1.5 inches of the gutter face unless approved by the Engineer.

If the gutter flow line in front of the proposed curb ramp exceeds 2.0% slope, the flow line should be adjusted to 2% or less if feasible while following the roadway criteria as per Standard Plans 5-297.250 (Sheet 6 of 6). The bituminous patch in front of the truncated domes should be 1% minimum to 5% maximum measured perpendicular to the flow line. In no case shall a newly constructed curb and gutter flow line exceed 8% unless the roadway profile exceeds 8%.

The Contractor shall not alter any existing drainage patterns unless called for in the plans or approved by the Engineer.

The Contractor shall construct a contraction joint through the curb and gutter section at the bottom of the curb height transitions where the curb height equals zero inches. If any curb and gutter joints fall within the PAR, they shall meet MnDOT 2521.3C.

When constructing directional curb where truncated domes are placed perpendicular to the path of travel, the concrete between the grade break/edge of truncated domes and the gutter toe shall be constructed integral.

S-42.2 METHOD OF MEASUREMENT Measurement of Concrete Curb and Gutter will be by the linear foot measured at the face of the curb.

S-42.3 BASIS OF PAYMENT Payment will be under Item 2531.603 (Concrete Curb and Gutter) at the Contract bid price per linear foot, which shall be compensation in full for all costs of furnishing and installing the required material including Aggregate Base.

S-43 (2565) RIGID PVC LOOP DETECTOR This work shall consist of providing, installing, and making operational new loop detectors due to roadway construction in accordance with the applicable provisions of MnDOT 2565; Standard Plate 8132; with the current edition of the National Electrical Code; with the Plans; as directed by the Engineer; and as follows:

S-45.1 GENERAL

The intersection layouts indicating the affected loop detectors to be replaced are included in the Plans.

S-45.2 MATERIALS

A. Loop Detector Splices

The Contractor shall provide and install loop detector splice encapsulation kits.

MnDOT approved Splice Encapsulation Kits are listed on MnDOT’s Approved/Qualified Products List for Signals: http://www.dot.state.mn.us/products/index.html

S-45.3 CONSTRUCTION REQUIREMENTS

A. Loop Detector Installation

The Contractor shall install loop detectors in accordance with Standard Plate 8132; as marked by the Engineer; and with the applicable provisions of MnDOT 2565.3G.

The loop detector roadway conductors and the loop detector lead-in cable conductors shall be properly prepared and cleaned before splicing. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 64

Prior to installing the approved loop detector splice kit, the Contractor shall solder the ends of the loop detector lead- in conductors to the roadway loop detector conductors, and shall provide and install an appropriate sized wire nut to the soldered ends prior to installation of the splice kit.

Splice kits shall be installed in handholes in such a manner as to ensure that each splice kit is suspended and/or secured near the top of the handhole to the satisfaction of the Engineer.

Placing splice kits on top of the electrical cables and conductors is NOT acceptable.

Loop detectors shall be spliced using an approved splice kit as specified elsewhere in these Special Provisions.

Make all loops fully operational within one (1) day after installation.

A. Loop Detector Test Report

Provide a loop detector test report in accordance with MnDOT 2565.3G.3

S-83.4 MEASUREMENTS AND PAYMENTS

PREFORMED RIGID PVC CONDUIT LOOP DETECTOR 6' X 6'

Providing, installing, testing, and making operational loop detectors as specified herein at the locations indicated in the Plans will each be measured as an integral unit complete in place and operating and will be paid for separately under Item No. 2565.602 (RIGID PVC LOOP DETECTOR 6' X 6') at the Contract price per EACH, which price shall be compensation in full for all costs incidental thereto.

This item includes the following:

1. All required roadway pavement milling or removal as part of the loop detector installation.

2. Rigid PVC conduit and conduit fittings for loop detectors.

3. Roadway loop detector conductor.

4. Rigid PVC conduit from loop detector to handhole.

5. Splice in handhole using splice kit as specified herein.

6. Installing loop detector as detailed herein.

7. Loop detector testing and reporting.

8. Traffic Control.

S-44 (2582) PAVEMENT MARKINGS REVISED 01/14/20 SP2018-250 - MODIFIED The provisions of MnDOT 2582 are hereby modified and/or supplemented with the following:

S-44.1 MnDOT 2582.3.B.7 is supplemented with the following:

Do not construct a recess in new bituminous pavement within a minimum 10 days of the placement of the final course of pavement, unless otherwise directed by the Engineer.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 65

Where required as part of recessing operations, remove existing pavement markings in accordance with MnDOT 2102. Waste from installation, removed marking material, removed pavement, and removal media shall become property of the Contractor. Dispose of the water from installation, removed marking material, removed pavement, and removal of media off the right of way in accordance with 1701 Laws to be Observed.

S-44.2 MnDOT 2582.3.C.3 is supplemented with the following:

Table 2852-1 shall be supplemented with the following table:

Table 2852-1 Pavement Marking White Yellow PAINT - WET CONTINUOUS 150 mcd/sq. m/lux 125 mcd/sq. m/lux MULTI-COMPONENT - WET 150 mcd/sq. m/lux 125 mcd/sq. m/lux CONTINUOUS PREFORMED TAPE - WET 250 mcd/sq. m/lux 200 mcd/sq. m/lux CONTINUOUS

S-45 (3105) BAGGED PORTLAND CEMENT CONCRETE PATCHING MIX GRADE 3U18 AND 3U18M SP2018-251 MnDOT 3105 is deleted and replaced with the following:

3105 BAGGED PORTLAND CEMENT CONCRETE PATCHING MIX GRADE 3U18 AND 3U58M

3105.1 SCOPE Provide dry, bagged concrete patching mix 3U18 for repairing Portland cement concrete pavement and 3U58M for repairing portland cement concrete bridge decks, bridge deck overlays and approach panels.

3105.2 REQUIREMENTS

A Materials Provide materials for patching mix meeting the following requirements:

A.1 Cement ...... 3101

A.2 Fine Aggregate ...... 3126

A.3 Coarse Aggregate ...... 3137

A.4 Blank

A.5 Admixtures ...... 3113 Mix 3U58M utilizes air entraining and water reducing admixtures. Provide the manufacturer’s Technical Data Information Sheet and the Materials Safety Data Sheet (MSDS) for the proposed dry admixtures when submitting the Quality Plan for approval.

B Quality Control (QC) Program Prior to producing concrete patching mix each construction season, a Department Representative shall perform a thorough on-site inspection of the plant with a MnDOT Certified Plant Level 1 or Level 2 Technician representing the Producer.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 66

Maintain an approved Quality Control Program, including a Quality Plan, for the production of Bagged Portland Cement Concrete Patching Mix.

The Producer will perform Quality Control (QC) as part of the production of Grade 3U18 concrete.

The Engineer will perform Quality Assurance (QA) as part of the acceptance process.

B.1 Quality Plan Requirements Submit a quality control plan to the Concrete Engineer for review and approval prior to producing Grade 3U18 and Grade 3U58M. The Quality Plan includes the following QC Procedures: (a) Moisture Content (b) Batch Weight Verification (c) Aggregate Gradation Testing (d) Blending (e) Addition of dry admixtures to 3U58M (f) Documentation and Submittals

B.2 MnDOT Certified Personnel Provide a MnDOT Concrete Plant 1 or Concrete Plant 2 Technician to perform moisture content and aggregate gradation testing. Provide a MnDOT Concrete Plant Level 2 Technician to review batch tickets, test results, and oversee all quality control requirements of 3105 and the QC Program.

B.3 Daily Production Requirements Each day Grade 3U18 or 3U58M is produced: (a) Perform moisture content and gradation testing on all aggregates and complete MnDOT’s Bagged Mix Quality Control Worksheet. (c) The Producer’s Plant Level 1 or Plant Level 2 Technician will review and sign the Bagged Quality Control Worksheet. (d) Electronically submit all Bagged Quality Control Worksheets and batch tickets to MnDOT the day following production.

C Mix Proportioning Proportion the mix in accordance with Table 3105-1. Use of any other size bag requires approval of the Concrete Engineer.

Table 3105-1 Mix Proportions Weight, lb. Gradation Material 50 lb. bag 75 lb. bag 3000 lb. bag Requirements Type I Cement - 11.9 17.8 712 Coarse Aggregate CA-80 18.9 28.3 1132 Fine Aggregate MnDOT 3126 19.3 28.9 1156

D Blending Dry the coarse and fine aggregates as approved by the Engineer before blending with the cement. Blend all materials completely before bagging the mix.

Provide a blending device meeting the following characteristics and requirements: (1) Capable of producing the required mix proportions within ±2 percent, (2) Equipped with a warning device to indicate when the system is out-of-tolerance, (3) Capable of stopping the flow of cement to allow sampling of the blended coarse and fine aggregate, and Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 67

(4) Designed to allow cement and aggregate to discharge separately for checking material weights.

E Bags and Batch Identification Provide moisture-proof bags resistant to tearing.

Print the following on the bags: (1) The phrase, “MnDOT 3U18 CONCRETE PATCH MIX” or “MnDOT 3U58M CONCRETE PATCH MIX” (2) Weight of the bag in pounds [kilograms] (3) Mix date (4) Mixing instructions

3105.3 SAMPLING AND TESTING The Producer and Engineer will sample and test in accordance with the Schedule of Materials Control.

S-46 (3131) INTERMEDIATE AGGREGATE FOR PORTLAND CEMENT CONCRETE NEW WRITE-UP 04/09/20 SP2018-252 MnDOT 3131 is modified with the following:

S-46.1 MnDOT 3131.1 is deleted and replaced with the following:

Provide intermediate aggregate for use in portland cement concrete.

S-46.2 Delete the first sentence from MnDOT 3131.2.B and replace with the following:

The Concrete Engineer classifies intermediate aggregate as 100 percent of the material passing the 1/2 inch sieve meeting the requirements of 3137.2.B.

S-46.3 MnDOT 3131.2.D, 3131.2.D.1, 3131.2.D.2 and 3131.2.D.3 are deleted and replaced with the following:

D Quality Provide CIA in accordance with 3137.2.D.

Provide FIA, CS and FS in accordance with 3126.2.B.

S-46.4 MnDOT 3131.2.E is deleted and replaced with the following:

E Gradation Proportion intermediate aggregates with other aggregate fractions to comply with a specification requirement. Intermediate aggregates do not have individual sieve gradation requirements.

S-46.5 MnDOT 3131.3.B is deleted and replaced with the following:

B Intermediate Aggregate Test Methods When proportioning CIA with a coarse aggregate to meet the specified limits of ASTM #67 gradation, sample and test CIA in accordance with Table 3137-6 using a minimum sample size equivalent to CA-70 per the Schedule of Materials Control. Sample and test all other CIA intermediate aggregates in accordance with Table 3126-5.

Sample and test FIA, CS and FS in accordance with Table 3126-5. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 68

S-47 (3137) COARSE AGGREGATE FOR PORTLAND CEMENT CONCRETE REVISED 04/09/20 SP2018-252.1 MnDOT 3137 is modified as follows:

S-47.1 MnDOT 3137.2.D shall be deleted and replaced with the following:

D Quality Provide coarse and CIA intermediate aggregate in accordance with 3137.2.D.1, 3137.2.D.2 or 3137.2.D.3 and the following:

For fractions greater than or equal to 1 in, base quality requirements on the individual result for the intended use.

For fractions that have 100 percent passing the 1 in sieve: (1) When using a single aggregate, base quality requirements on the individual result for the intended use. (2) When proportioning aggregates from a single source, base quality requirements on the composite result for the intended use. (3) When proportioning aggregates from multiple sources, base quality requirements on the composite result for the intended use, except as modified by the following: (3.1) For 3137.2.D.1, each individual fraction must meet the requirements of 3137.2.D.1 (3.2) For 3137.2.D.2, each individual fraction must meet the requirements of 3137.2.D.1, except the percent absorption by weight of Class B aggregate is modified to a maximum of 1.75% and the percent carbonate by weight of the Class C aggregate is modified to a maximum of 30.0%. (3.3) For 3137.2.D.3, each individual fraction must meet the requirements of 3137.2.D.3, except the percent carbonate by weight of the Class C aggregate is modified to a maximum of 35.0%.

The Engineer may reject the proposed aggregate proportions if the composite result is of borderline quality in accordance with 1503, Conformity with Contract Documents.

Refer to Tables 2461-5, 2461-6, 2461-7, 2461-8 and 2462-4 to determine the coarse aggregate quality specification for the intended use.

S-47.2 Table 3137-4 shall be deleted and replaced with the following:

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 69

Table 3137-4 Coarse Aggregate Designation for Concrete, percent by weight passing square opening sieves Coarse Aggregate Designation

2 3 4 7 8 Sieve Sizes ASTM #67* ASTM #7* ASTM #89 CA-70 CA-80 2 in - - - - - 1½ in - - - - - 1 in 100 - - - - ¾ in 90 – 100 100 - - - 5/8 in - - - 100 - ½ in - 90 – 100 100 85 – 100 - ⅜ in 20 – 55 40 – 70 90 – 100 50 – 100 100 No.4 0 – 10 0 – 15 20 - 55 0 – 25 55 – 95 No.8 - - 5 – 30 - - No.16 - - 0 – 10 - - No.50 - - 0 - 5 - 0-5 *ASTM #67 and ASTM #7 Gradations are MnDOT Modified.

S-48 (3138) AGGREGATE FOR SURFACE AND BASE COURSES REVISED 12/05/18 SP2018-252.2 MnDOT 3138 is hereby modified as follows:

S-48.1 Replace Table 3138-1 with the following:

Table 3138-1 Quality Requirements for Virgin Materials Class Requirement 1 and 2 3 and 4 5 and 5Q 6 Max Shale, if No. 200 ≤ 7% by mass NA 10.0% 10.0% 7.0% Max Shale, if No. 200 > 7% by mass NA 7.0% 7.0% 7.0% Minimum Crushing Requirements * NA NA 10% 15% Maximum Rattler (LAR) 40% 40% 40% 35% loss from carbonate quarry rock Maximum Insoluble residue for the portion of quarried carbonate 10% 10% 10% 10% aggregates passing the No. 200 sieve Maximum amount of Brick 1.0% # Maximum amount of other objectionable materials including but not limited to: wood, plant matter, 0.3% # plastic, plaster, and fabric * Material crushed from quarries is considered crushed material. # The Contractor/Supplier may not knowingly allow brick and other objectionable material and must employ a QC process to screen it out, before it becomes incorporated into the final product.

S-48.2 Replace Table 3138-3 with the following:

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 70

Table 3138-3 Base and Surfacing Aggregate (containing less than 25 percent recycled aggregates) Total Percent Passing * Sieve Class 1 Class 2 Class 3 Class 4 Class 5 Class 5Q Class 6 Size (Surfacing £) (Surfacing β) (Subbase) (Subbase) (Base) (Base) (Base) 2 in — — 100 100 — 100 — 1½ in — — — — 100 — 100 1 in — — — — — 65 - 95 — ¾ in 100 100 — — 70 - 100 45 - 85 70 - 100 ⅜ in 65 – 95 65 - 90 — — 45 - 90 35 - 70 45 - 85 No. 4 40 – 85 35 - 70 35 - 100 35 - 100 35 - 80 15 - 52 35 - 70 No. 10 25 – 70 25 - 45 20 - 100 20 - 100 20 - 65 10 - 40 20 - 55 No. 40 10 – 45 12 - 35 5 - 50 5 - 35 10 - 35 5 - 25 10 - 30 No. 200 8.0 - 15.0 5.0 - 16.0 5.0 - 10.0 4.0 - 10.0 3.0 - 10.0 0.0 - 10.0 3.0 - 7.0 * If product contains recycled aggregate, add letters in parentheses for each aggregate blend designating the type of recycled products included in the mixture. (B) = Bituminous, (C) = Concrete, (G) = Glass (BC) = Bituminous and Concrete, (BG) = Bituminous and Glass (CG) = Concrete and Glass, (BCG) = Bituminous, Concrete, and Glass £ Recycled concrete when used for surfacing is only allowed for shoulders β Class 2 must be composed of 100% crushed quarry rock per 3138.2.B.2.

S-48.3 Replace Table 3138-4 with the following:

Table 3138-4 Base and Surfacing Aggregate (containing 25% or more recycled aggregates & 75% or less recycled concrete) Total Percent Passing * Sieve Class 1 Class 3 Class 4 Class 5 Class 5Q Class 6 Size (Surfacing £) (Subbase) (Subbase) (Base) (Base) (Base) 2 in — 100 100 — 100 — 1½ in — — — 100 — 100 1 in — — — 65 - 95 ¾ in 100 — — 70 - 100 45 - 85 70 - 100 ⅜ in 65 - 95 — — 45 - 90 35 - 70 45 - 85 No. 4 40 - 85 35 - 100 35 - 100 35 - 80 15 - 52 35 - 70 No. 10 25 - 70 20 - 100 20 - 100 20 - 65 10 - 40 20 - 55 No. 40 10 - 45 5 - 50 5 - 35 10 - 35 5 - 25 10 - 30 † 5 - 45 No. 200 5.0 - 15.0 0 - 10.0 0 - 10.0 0 - 10.0 0 - 10.0 0 - 7.0 † 0 - 15.0 * Add letters in parentheses for each aggregate blend designating the type of recycled products included in the mixture. (B) = Bituminous, (C) = Concrete, (G) = Glass (BC) = Bituminous and Concrete, (BG) = Bituminous and Glass (CG) = Concrete and Glass, (BCG) = Bituminous, Concrete, and Glass † Note: For Class 1, if the bitumen content is ≥ 1.5%, the gradation requirement is modified to 5-45% for the #40 sieve and 0 – 15.0% for the #200 sieve. £ Recycled concrete is only allowed for shoulders

S-48.4 Add the following to MnDOT 3138.2.E:

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 71

(6) The Contractor may substitute reclamation material (recycled bituminous and aggregate) for class 3, 4, 5, or 6, if used for base, subbase, stabilizing aggregate, or fine aggregate bedding. Meet the gradation in Table 3138-6, and the all other requirements of 3138.

Table 3138-6 Reclamation Material Permitted as a Substitute for Class 3, 4, 5, or 6 Total Percent Passing Sieve Size Class 3 Class 4 Class 5 Class 6 3” * 100 100 100 100 ¾” ------70 - 100 70 - 100 #3/8” ------45 - 90 45 - 85 #4 35 - 100 35 - 100 35 - 80 35 - 70 #10 20 - 100 20 - 100 20 - 65 20 - 55 #40 5 - 50 5 – 35 10 - 35 10 - 30 #200 0 - 10.0 0 - 10.0 0 - 10.0 0 - 7.0 * Note for bedding within 2 feet of plastic pipe the requirement is 100% passing the 1” sieve.

S-49 (3149) GRANULAR MATERIAL NEW WRITE-UP 01/14/20 SP2018-253.1 MnDOT 3149 is hereby modified as follows:

S-49.1 Replace Table 3149-3 with the following:

Table 3149-3 Structural Backfill Requirements % Passing ¾ in sieve 100% % Passing Ratio #40/#10 0 - 65% % Passing #200 Sieve 0 - 5.0% Maximum Clay % as determined by 1.5% MnDOT Test Method 1302

S-50 (3236) REINFORCED CONCRETE PIPE SP2018-255 The provisions of MnDOT 3236 are modified and/or supplemented with the following:

S-50.1 Manufacturers of reinforced concrete pipe may produce an alternate "offset joint" on the spigot end of the pipe. This type of offset joint is to be used with the profile or prelubricated pipe seal systems. See MnDOT Standard Plate 3006.

S-51 (3301) REINFORCEMENT BARS REVISED 05/17/19 SP2018-258 MnDOT 3301 is modified with the following:

S-51.1 The following is added to MnDOT 3301.2, “Requirements”:

Fabrication of epoxy-coated reinforcing steel delivered to projects in July 2020 and later is required to take place in plants participating in the CRSI Epoxy Coated Fabrication Certification Program and listed on CRSI’s website. Epoxy coated dowel bar and reinforcing to be used in concrete pavement is exempt from this fabrication requirement.

Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 72

S-52 (3302) DOWEL BAR NEW WRITE-UP 04/09/20 SP2018-259 MnDOT 3302 is hereby deleted and replaced with the following:

3302.1 SCOPE Provide dowel bars for use in Portland cement concrete pavements and other concrete applications as shown on the plans.

3302.2 REQUIREMENTS

A Epoxy Coated Steel Dowel Bars Provide Grade 40 or Grade 60 steel dowel bars meeting the requirements of AASHTO M 31.

Epoxy coat the steel dowel bars in accordance with AASHTO M254 and as modified: (1) Apply epoxy coating in a fusion bonded epoxy coating plant certified by the CRSI or another organization approved by the Materials Engineer. (2) Apply 7-13 mils epoxy coating thickness. (3) Do not epoxy coat the ends of the dowel bars unless required by the Manufacturer.

If cutting dowel bars to length by shearing, immediately repair all damaged epoxy coating and verify dowel bars have not exceeded the maximum deformation limits. Ensure that sheared dowel bars are not more than 0.04 in out of round, and that such damage does not extend more than 0.40 in from the end of the bar.

B Tubular Dowel Bars Provide welded carbon and alloy steel tubular dowel bar meeting the requirements of ASTM 513 and Table 3302-1.

Table 3302-1 Tubular Dowel Bar Requirements Specified Dowel Bar Required Tubular Dowel Bar Required Tubular Dowel Bar Diameter Outside Diameter Wall Thickness 1.25 in 1.3125 in or 1.375 in 0.120 in 1.50 in 1.625 in 0.120 in

Provide a galvanized coating providing a minimum 20 year life. Cap the ends of the tubular dowel bar in a way to prevent intrusion of concrete or other materials.

Galvanize the exterior and interior of the tubular steel dowel bars using G90 coverage zinc galvanized coating.

Epoxy coat the exterior of the galvanized tubular dowel bars in accordance with ASTM A1078 Type 2 coating (ASTM A934 Annex A1) and as modified: (1) Apply epoxy coating in a fusion bonded epoxy coating plant certified by the CRSI or another organization approved by the Materials Engineer. (2) Epoxy coating of the entire dowel bar assembly is not required. (3) Do not epoxy coat the ends of the dowel bars unless required by the Manufacturer.

C Bond Breaker Material Provide bond breaker material listed on the Approved/Qualified Products List.

Prior to delivery to the project site, coat the entire dowel bar assembly or dowel bar bundles with a bond breaker material in accordance with the Manufacturer’s recommendations. Appendix C

SPECIAL PROVISIONS - SP2018 BOOK Wash Co Div S – Rev 4 CSAH 16 Median Repair Page 73

D Certification of Dowel Bars Ensure the manufacturer’s plant quality control office maintains documentation containing the data required by certification, including test data and measurements taken at times and locations as required by the CRSI, the Materials Engineer, or both.

Include the following standardized statement with delivery invoices: “(insert company name) certifies that the dowel bars and basket assemblies are coated with a bond breaker material and meet the requirements of MnDOT Specification 3302.”

E Storage and Protection of Dowel Bars Do not store dowel bars in a manner that will cause, induce, or accelerate corrosion or contamination of the metal at any time. Locate timbers (dunnage) on the ground to support the bundles and keep them free of contamination.

Protect coated dowel bars before handling or shipping to prevent damage to the coating. Pad bundling bands and lift bundles using an OSHA-approved spreader bar, multiple supports, or platform bridge to prevent bar-to-bar abrasion from sags in the bar bundle. Do not drag or drop bars or bundles. Support bars or bundles in transit to prevent damage to the coating.

Store materials at the project site to allow the Engineer to visually inspect and check the various types of reinforcement for conformance to the dimensions as shown on the plans. Store bars of the same type together. Identify dowel bars with tags bearing the identification symbols as shown on the plans.

If the epoxy-coated steel is incorporated into the Project and is exposed to the weather or stored exposed to the weather for more than 60 calendar days, cover the steel to protect the material from sunlight, salt-spray and weather exposure. Provide for air circulation around the covered steel to minimize condensation under the protective covering.

3302.3 SAMPLING AND TESTING Sample and test dowel bars and dowel basket assemblies in accordance with the Schedule of Materials Control. The Department will visually inspect the bond breaker material coating on the dowel bars. Appendix C

MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY PREVAILING WAGES FOR STATE FUNDED CONSTRUCTION PROJECTS

THIS NOTICE MUST BE POSTED ON THE JOBSITE IN A CONSPICUOUS PLACE

Construction Type: Highway and Heavy

Region Number: 09

Counties within region:

• ANOKA-02 • CARVER-10 • CHISAGO-13 • DAKOTA-19 • HENNEPIN-27 • RAMSEY-62 • SCOTT-70 • WASHINGTON-82

Effective: 2020-09-28

This project is covered by Minnesota prevailing wage statutes. Wage rates listed below are the minimum hourly rates to be paid on this project.

All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at a rate of one and one half (1 1/2) times the basic hourly rate. Note: Overtime pay after eight (8) hours on the project must be paid even if the worker does not exceed forty (40) hours in the work week.

Violations on MnDOT highways and road projects should be reported to:

Department of Transportation Office of Construction Transportation Building MS650 John Ireland Blvd St. Paul, MN 55155 (651) 366-4209

All other prevailing wage violations and questions should be sent to:

Department of Labor and Industry Prevailing Wage Section 443 Lafayette Road N St Paul, MN 55155 (651) 284-5091 [email protected]

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE

LABORERS (101 - 112) (SPECIAL CRAFTS 701 - 730)

101 LABORER, COMMON (GENERAL 2020-09-28 34.05 21.24 55.29 LABOR WORK) 2021-05-01 35.50 21.84 57.34

102 LABORER, SKILLED (ASSISTING 2020-09-28 34.05 21.24 55.29 SKILLED CRAFT JOURNEYMAN) 2021-05-01 35.50 21.84 57.34

1 Appendix C

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE

103 LABORER, LANDSCAPING 2020-09-28 25.00 17.46 42.46 (GARDENER, SOD LAYER AND NURSERY OPERATOR) 2021-05-01 25.75 18.70 44.45

104 FLAG PERSON 2020-09-28 34.05 21.24 55.29 2021-05-01 35.50 21.84 57.34

105 WATCH PERSON 2020-09-28 30.65 20.69 51.34 2021-05-01 32.10 21.29 53.39

106 BLASTER 2020-09-28 22.08 6.87 28.95

107 PIPELAYER (WATER, SEWER AND 2020-09-28 37.05 21.24 58.29 GAS) 2021-05-01 39.00 21.84 60.84

108 TUNNEL MINER 2020-09-28 35.15 21.24 56.39 2021-05-01 37.00 21.84 58.84

109 UNDERGROUND AND OPEN DITCH 2020-09-28 35.15 21.24 56.39 LABORER (EIGHT FEET BELOW STARTING GRADE LEVEL) 2021-05-01 37.00 21.84 58.84

110 SURVEY FIELD TECHNICIAN 2020-09-28 34.05 21.24 55.29 (OPERATE TOTAL STATION, GPS RECEIVER, LEVEL, ROD OR RANGE POLES, STEEL TAPE MEASUREMENT; MARK AND DRIVE STAKES; HAND OR POWER DIGGING FOR AND IDENTIFICATION OF MARKERS OR MONUMENTS; PERFORM AND CHECK CALCULATIONS; REVIEW AND UNDERSTAND CONSTRUCTION PLANS AND LAND SURVEY MATERIALS). THIS CLASSIFICATION DOES NOT APPLY TO THE WORK PERFORMED ON A PREVAILING WAGE PROJECT BY A LAND SURVEYOR WHO IS LICENSED PURSUANT TO MINNESOTA STATUTES, SECTIONS 326.02 TO 326.15. 2021-05-01 35.50 21.84 57.34

111 TRAFFIC CONTROL PERSON 2020-09-28 34.05 21.24 55.29 (TEMPORARY SIGNAGE)

2 Appendix C

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE

2021-05-01 35.50 21.84 57.34

112 QUALITY CONTROL TESTER (FIELD 2020-09-28 16.28 4.07 20.35 AND COVERED OFF-SITE FACILITIES; TESTING OF AGGREGATE, ASPHALT, AND CONCRETE MATERIALS); LIMITED TO MN DOT HIGHWAY AND HEAVY CONSTRUCTION PROJECTS WHERE THE MN DOT HAS RETAINED QUALITY ASSURANCE PROFESSIONALS TO REVIEW AND INTERPRET THE RESULTS OF QUALITY CONTROL TESTERS. SERVICES PROVIDED BY THE CONTRACTOR.

SPECIAL EQUIPMENT (201 - 204)

201 ARTICULATED HAULER 2020-09-28 38.89 21.55 60.44 2021-05-03 40.04 22.55 62.59

202 BOOM TRUCK 2020-09-28 38.89 21.55 60.44 2021-05-03 40.04 22.55 62.59

203 LANDSCAPING EQUIPMENT, 2020-09-28 25.00 17.46 42.46 INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICALLY SEEDING, SODDING, OR PLANT, AND TWO-FRAMED FORKLIFT (EXCLUDING FRONT, POSIT-TRACK, AND SKID STEER LOADERS), NO EARTHWORK OR GRADING FOR ELEVATIONS 2021-05-01 25.75 18.70 44.45

204 OFF-ROAD TRUCK 2020-09-28 38.89 21.55 60.44 2021-05-03 40.04 22.55 62.59

205 PAVEMENT MARKING OR 2020-09-28 32.04 21.96 54.00 MARKING REMOVAL EQUIPMENT (ONE OR TWO PERSON OPERATORS); SELF-PROPELLED TRUCK OR TRAILER MOUNTED UNITS.

HIGHWAY/HEAVY POWER EQUIPMENT OPERATOR

3 Appendix C

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE

GROUP 2 2020-09-28 39.74 21.55 61.29 2021-05-03 40.89 22.55 63.44 302 HELICOPTER PILOT (HIGHWAY AND HEAVY ONLY) 303 CONCRETE PUMP (HIGHWAY AND HEAVY ONLY) 304 ALL CRANES WITH OVER 135-FOOT BOOM, EXCLUDING JIB (HIGHWAY AND HEAVY ONLY) 305 DRAGLINE, CRAWLER, HYDRAULIC BACKHOE (TRACK OR WHEEL MOUNTED) AND/OR OTHER SIMILAR EQUIPMENT WITH SHOVEL-TYPE CONTROLS THREE CUBIC YARDS AND OVER MANUFACTURER.S RATED CAPACITY INCLUDING ALL ATTACHMENTS. (HIGHWAY AND HEAVY ONLY) 306 GRADER OR MOTOR PATROL 307 PILE DRIVING (HIGHWAY AND HEAVY ONLY) 308 TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED (HIGHWAY AND HEAVY ONLY)

GROUP 3 2020-09-28 39.19 21.55 60.74 2021-05-03 40.34 22.55 62.89 309 ASPHALT BITUMINOUS STABILIZER PLANT 310 CABLEWAY 311 CONCRETE MIXER, STATIONARY PLANT (HIGHWAY AND HEAVY ONLY) 312 DERRICK (GUY OR STIFFLEG)(POWER)(SKIDS OR STATIONARY) (HIGHWAY AND HEAVY ONLY) 313 DRAGLINE, CRAWLER, HYDRAULIC BACKHOE (TRACK OR WHEEL MOUNTED) AND/OR SIMILAR EQUIPMENT WITH SHOVEL-TYPE CONTROLS, UP TO THREE CUBIC YARDS MANUFACTURER.S RATED CAPACITY INCLUDING ALL ATTACHMENTS (HIGHWAY AND HEAVY ONLY) 314 DREDGE OR ENGINEERS, DREDGE (POWER) AND ENGINEER 315 FRONT END LOADER, FIVE CUBIC YARDS AND OVER INCLUDING ATTACHMENTS. (HIGHWAY AND HEAVY ONLY) 316 LOCOMOTIVE CRANE OPERATOR 317 MIXER (PAVING) CONCRETE PAVING, ROAD MOLE, INCLUDING MUCKING OPERATIONS, CONWAY OR SIMILAR TYPE 318 MECHANIC . WELDER ON POWER EQUIPMENT (HIGHWAY AND HEAVY ONLY) 319 TRACTOR . BOOM TYPE (HIGHWAY AND HEAVY ONLY) 320 TANDEM SCRAPER 321 TRUCK CRANE . CRAWLER CRANE (HIGHWAY AND HEAVY ONLY) 322 TUGBOAT 100 H.P AND OVER (HIGHWAY AND HEAVY ONLY)

GROUP 4 2020-09-28 38.89 21.55 60.44 2021-05-03 40.04 22.55 62.59 323 AIR TRACK ROCK DRILL 324 AUTOMATIC ROAD MACHINE (CMI OR SIMILAR) (HIGHWAY AND HEAVY ONLY) 325 BACKFILLER OPERATOR 326 CONCRETE BATCH PLANT OPERATOR (HIGHWAY AND HEAVY ONLY) 327 BITUMINOUS ROLLERS, RUBBER TIRED OR STEEL DRUMMED (EIGHT TONS AND OVER) 328 BITUMINOUS SPREADER AND FINISHING MACHINES (POWER), INCLUDING PAVERS, MACRO SURFACING AND MICRO SURFACING, OR SIMILAR TYPES (OPERATOR AND SCREED PERSON) 329 BROKK OR R.T.C. REMOTE CONTROL OR SIMILAR TYPE WITH ALL ATTACHMENTS

4 Appendix C

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE

330 CAT CHALLENGER TRACTORS OR SIMILAR TYPES PULLING ROCK WAGONS, BULLDOZERS AND SCRAPERS 331 CHIP HARVESTER AND TREE CUTTER 332 CONCRETE DISTRIBUTOR AND SPREADER FINISHING MACHINE, LONGITUDINAL FLOAT, JOINT MACHINE, AND SPRAY MACHINE 333 CONCRETE MIXER ON JOBSITE (HIGHWAY AND HEAVY ONLY) 334 CONCRETE MOBIL (HIGHWAY AND HEAVY ONLY) 335 CRUSHING PLANT (GRAVEL AND STONE) OR GRAVEL WASHING, CRUSHING AND SCREENING PLANT 336 CURB MACHINE 337 DIRECTIONAL BORING MACHINE 338 DOPE MACHINE (PIPELINE) 339 DRILL RIGS, HEAVY ROTARY OR CHURN OR CABLE DRILL (HIGHWAY AND HEAVY ONLY) 340 DUAL TRACTOR 341 ELEVATING GRADER 342 FORK LIFT OR STRADDLE CARRIER (HIGHWAY AND HEAVY ONLY) 343 FORK LIFT OR LUMBER STACKER (HIGHWAY AND HEAVY ONLY) 344 FRONT END, SKID STEER OVER 1 TO 5 C YD 345 GPS REMOTE OPERATING OF EQUIPMENT 346 HOIST ENGINEER (POWER) (HIGHWAY AND HEAVY ONLY) 347 HYDRAULIC TREE PLANTER 348 LAUNCHER PERSON (TANKER PERSON OR PILOT LICENSE) 349 LOCOMOTIVE (HIGHWAY AND HEAVY ONLY) 350 MILLING, GRINDING, PLANNING, FINE GRADE, OR TRIMMER MACHINE 351 MULTIPLE MACHINES, SUCH AS AIR COMPRESSORS, WELDING MACHINES, GENERATORS, PUMPS (HIGHWAY AND HEAVY ONLY) 352 PAVEMENT BREAKER OR TAMPING MACHINE (POWER DRIVEN) MIGHTY MITE OR SIMILAR TYPE 353 PICKUP SWEEPER, ONE CUBIC YARD AND OVER HOPPER CAPACITY(HIGHWAY AND HEAVY ONLY) 354 PIPELINE WRAPPING, CLEANING OR BENDING MACHINE 355 POWER PLANT ENGINEER, 100 KWH AND OVER (HIGHWAY AND HEAVY ONLY) 356 POWER ACTUATED HORIZONTAL BORING MACHINE, OVER SIX INCHES 357 PUGMILL 358 PUMPCRETE (HIGHWAY AND HEAVY ONLY) 359 RUBBER-TIRED FARM TRACTOR WITH BACKHOE INCLUDING ATTACHMENTS (HIGHWAY AND HEAVY ONLY) 360 SCRAPER 361 SELF-PROPELLED SOIL STABILIZER 362 SLIP FORM (POWER DRIVEN) (PAVING) 363 TIE TAMPER AND BALLAST MACHINE 364 TRACTOR, BULLDOZER (HIGHWAY AND HEAVY ONLY) 365 TRACTOR, WHEEL TYPE, OVER 50 H.P. WITH PTO UNRELATED TO LANDSCAPING (HIGHWAY AND HEAVY ONLY) 366

5 Appendix C

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE

TRENCHING MACHINE (SEWER, WATER, GAS) EXCLUDES WALK BEHIND TRENCHER (HIGHWAY AND HEAVY ONLY) 367 TUB GRINDER, MORBARK, OR SIMILAR TYPE 368 WELL POINT DISMANTLING OR INSTALLATION (HIGHWAY AND HEAVY ONLY)

GROUP 5 2020-09-28 35.85 21.55 57.40 2021-05-03 37.00 22.55 59.55 369 AIR COMPRESSOR, 600 CFM OR OVER (HIGHWAY AND HEAVY ONLY) 370 BITUMINOUS ROLLER (UNDER EIGHT TONS) 371 CONCRETE SAW (MULTIPLE BLADE) (POWER OPERATED) 372 FORM TRENCH DIGGER (POWER) 373 FRONT END, SKID STEER UP TO 1C YD 374 GUNITE GUNALL (HIGHWAY AND HEAVY ONLY) 375 HYDRAULIC LOG SPLITTER 376 LOADER (BARBER GREENE OR SIMILAR TYPE) 377 POST HOLE DRIVING MACHINE/POST HOLE AUGER 378 POWER ACTUATED AUGER AND BORING MACHINE 379 POWER ACTUATED JACK 380 PUMP (HIGHWAY AND HEAVY ONLY) 381 SELF-PROPELLED CHIP SPREADER (FLAHERTY OR SIMILAR) 382 SHEEP FOOT COMPACTOR WITH BLADE . 200 H.P. AND OVER 383 SHOULDERING MACHINE (POWER) APSCO OR SIMILAR TYPE INCLUDING SELF-PROPELLED SAND AND CHIP SPREADER 384 STUMP CHIPPER AND TREE CHIPPER 385 TREE FARMER (MACHINE)

GROUP 6 2020-09-28 34.64 21.55 56.19 2021-05-03 35.79 22.55 58.34 387 CAT, CHALLENGER, OR SIMILAR TYPE OF TRACTORS, WHEN PULLING DISK OR ROLLER 388 CONVEYOR (HIGHWAY AND HEAVY ONLY) 389 DREDGE DECK HAND 390 FIRE PERSON OR TANK CAR HEATER (HIGHWAY AND HEAVY ONLY) 391 GRAVEL SCREENING PLANT (PORTABLE NOT CRUSHING OR WASHING) 392 GREASER (TRACTOR) (HIGHWAY AND HEAVY ONLY) 393 LEVER PERSON 394 OILER (POWER SHOVEL, CRANE, TRUCK CRANE, DRAGLINE, CRUSHERS, AND MILLING MACHINES, OR OTHER SIMILAR HEAVY EQUIPMENT) (HIGHWAY AND HEAVY ONLY) 395 POWER SWEEPER 396 SHEEP FOOT ROLLER AND ROLLERS ON GRAVEL COMPACTION, INCLUDING VIBRATING ROLLERS 397 TRACTOR, WHEEL TYPE, OVER 50 H.P., UNRELATED TO LANDSCAPING

6 Appendix C

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE TRUCK DRIVERS

GROUP 1 2020-09-28 31.25 17.50 48.75 601 MECHANIC . WELDER 602 TRACTOR TRAILER DRIVER 603 TRUCK DRIVER (HAULING MACHINERY INCLUDING OPERATION OF HAND AND POWER OPERATED WINCHES)

GROUP 2 2020-09-28 30.70 17.50 48.20 604 FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK

GROUP 3 2020-09-28 24.00 6.91 30.91 605 BITUMINOUS DISTRIBUTOR DRIVER 606 BITUMINOUS DISTRIBUTOR (ONE PERSON OPERATION) 607 THREE AXLE UNITS

GROUP 4 2020-09-28 30.35 17.50 47.85 608 BITUMINOUS DISTRIBUTOR SPRAY OPERATOR (REAR AND OILER) 609 DUMP PERSON 610 GREASER 611 PILOT CAR DRIVER 612 RUBBER-TIRED, SELF-PROPELLED PACKER UNDER 8 TONS 613 TWO AXLE UNIT 614 SLURRY OPERATOR 615 TANK TRUCK HELPER (GAS, OIL, ROAD OIL, AND WATER) 616 TRACTOR OPERATOR, UNDER 50 H.P.

SPECIAL CRAFTS

701 HEATING AND FROST INSULATORS 2020-09-28 47.10 24.40 71.50

702 BOILERMAKERS 2020-09-28 39.69 28.82 68.51 2021-01-01 41.39 28.82 70.21

703 BRICKLAYERS 2020-09-28 36.05 19.68 55.73

704 CARPENTERS 2020-09-28 39.01 25.03 64.04 2021-05-04 41.06 25.03 66.09

705 CARPET LAYERS (LINOLEUM) FOR RATE CALL 651-284-5091 OR EMAIL [email protected]

7 Appendix C

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE

706 CEMENT MASONS 2020-09-28 40.40 22.22 62.62 2021-05-01 42.45 22.22 64.67

707 ELECTRICIANS 2020-09-28 46.00 31.20 77.20

711 GROUND PERSON 2020-09-28 33.40 17.30 50.70

712 IRONWORKERS 2020-09-28 38.35 30.70 69.05 2021-05-02 40.45 30.70 71.15

713 LINEMAN 2020-09-28 47.71 21.53 69.24

714 MILLWRIGHT 2020-09-28 36.13 29.18 65.31 2021-05-01 38.23 29.18 67.41

715 PAINTERS (INCLUDING HAND 2020-09-28 37.70 24.63 62.33 BRUSHED, HAND SPRAYED, AND THE TAPING OF PAVEMENT MARKINGS) 2021-05-03 39.70 24.63 64.33

716 PILEDRIVER (INCLUDING 2020-09-28 38.96 25.03 63.99 VIBRATORY DRIVER OR EXTRACTOR FOR PILING AND SHEETING OPERATIONS) 2021-05-03 41.01 25.03 66.04

717 PIPEFITTERS . STEAMFITTERS 2020-09-28 50.19 27.75 77.94 2021-05-01 52.69 27.75 80.44

719 PLUMBERS 2020-09-28 50.87 25.33 76.20

721 SHEET METAL WORKERS 2020-09-28 44.46 29.17 73.63

723 TERRAZZO WORKERS FOR RATE CALL 651-284-5091 OR EMAIL [email protected]

724 TILE SETTERS 2020-09-28 34.76 23.29 58.05

725 TILE FINISHERS FOR RATE CALL 651-284-5091 OR EMAIL [email protected]

8 Appendix C

LABOR CODE AND CLASS EFFECT DATE BASIC RATE FRINGE RATE TOTAL RATE

727 WIRING SYSTEM TECHNICIAN 2020-09-28 41.42 18.16 59.58

728 WIRING SYSTEMS INSTALLER 2020-09-28 29.02 15.34 44.36

729 ASBESTOS ABATEMENT WORKER 2020-09-28 33.75 20.69 54.44 2021-01-01 34.85 21.64 56.49

730 SIGN ERECTOR FOR RATE CALL 651-284-5091 OR EMAIL [email protected]

9 Appendix C

Notice of truck rental rate certification and effective date

The Department of Labor and Industry (DLI) temporary commissioner has certified the minimum truck rental rates for state-funded highway projects effective Dec. 21, 2020. This certification follows the publication of the Notice of Truck Rental Rate Determination in the State Register on Nov. 30, 2020, and the informal conference held pursuant to Minnesota Rules, part 5200.1105, Dec. 11, 2020.

According to Minnesota Rules, part 5200.1105, the purpose of the informal conference was for DLI to obtain further input regarding the determined rates prior to the certification. No written input regarding the determination was received by DLI prior to the informal conference.

The truck rental rate is determined for each equipment type by adding the average hourly cost of operating the vehicle to the certified prevailing wage rate for the driver. The average hourly operating costs are determined by voluntary survey of truck owner operators, trucking contractors and trucking firms.

The determination of the minimum truck rental rates by region are as follows.

Three-axle units

Region Effective date 607 driver rate Operating cost Truck rental rate

Region 1 Certification date $55.68 $37.35 $93.03

Region 2 Certification date $46.75 $37.35 $84.10

Region 3 Certification date $45.02 $37.35 $82.37

Region 4 Certification date $46.75 $37.35 $84.10

Region 5 Certification date $34.91 $37.35 $72.26

Region 6 Certification date $44.70 $37.35 $82.05 Appendix C

Region Effective date 607 driver rate Operating cost Truck rental rate

Region 7 Certification date $44.70 $37.35 $82.05

Region 8 Certification date $43.25 $37.35 $80.60

Region 9 Certification date $30.91 $37.35 $68.26

Region 10 Certification date $44.45 $37.35 $81.80

Four or more axle units

Region Effective date 604 driver rate Operating cost Truck rental rate

Region 1 Certification date $53.05 $45.89 $98.94

Increase May 1, 2021 $54.55 $45.89 $100.44

Region 2 Certification date $41.51 $45.89 $87.40

Region 3 Certification date $38.51 $45.89 $84.40

Region 4 Certification date $37.80 $45.89 $83.69

Region 5 Certification date $32.46 $45.89 $78.35

Region 6 Certification date $39.40 $45.89 $85.29

Region 7 Certification date $43.00 $45.89 $88.89

Region 8 Certification date $28.41 $45.89 $74.30

Region 9 Certification date $48.20 $45.89 $94.09

Region 10 Certification date $26.00 $45.89 $71.89

Appendix C

Tractor

Region Effective date 602 driver Operating cost Tractor Only Plus Tractor rate Truck Rental Trailer Trailer Rate Operating Rental Cost Rate

Certification Region 1 $53.60 $54.96 $108.56 $11.46 $120.02 date Increase $55.10 $54.96 $110.06 $11.46 $121.52 May 1, 2021 Certification Region 2 $42.02 $54.96 $96.98 $11.46 $108.44 date Certification Region 3 $46.55 $54.96 $101.51 $11.46 $112.97 date Certification Region 4 $48.75 $54.96 $103.71 $11.46 $115.17 date Certification Region 5 $37.65 $54.96 $92.61 $11.46 $104.07 date Certification Region 6 $41.40 $54.96 $96.36 $11.46 $107.82 date Certification Region 7 $41.40 $54.96 $96.36 $11.46 $107.82 date Certification Region 8 $28.91 $54.96 $83.87 $11.46 $95.33 date Certification Region 9 $48.75 $54.96 $103.71 $11.46 $115.17 date

Region 10 Certification $38.75 $54.96 $93.71 $11.46 $105.17 date

The minimum truck rental rate for these four types of trucks in the state’s 10 highway and heavy construction areas will be effective for all Minnesota Department of Transportation (MnDOT) highway construction work financed in whole or part with state funds advertised for bid on or after the day the notice of certification is published in the State Register.

Roslyn Robertson DLI temporary commissioner ATTACHMENT A PRIME CONTRACTOR RESPONSE

RESPONSIBLE CONTRACTOR VERIFICATION AND CERTIFICATION OF COMPLIANCE

STATE PROJECT NUMBER: ______This form includes changes by statutory references from the Laws of Minnesota 2015, chapter 64, sections 1-9. This form must be submitted with the response to this solicitation. A response received without this form, will be rejected.

Minn. Stat. § 16C.285, Subd. 7. IMPLEMENTATION. … any prime contractor or subcontractor or motor carrier that does not meet the minimum criteria in subdivision 3 or fails to verify that it meets those criteria is not a responsible contractor and is not eligible to be awarded a construction contract for the project or to perform work on the project…

Minn. Stat. § 16C.285, Subd. 3. RESPONSIBLE CONTRACTOR, MINIMUM CRITERIA. "Responsible contractor" means a contractor that conforms to the responsibility requirements in the solicitation document for its portion of the work on the project and verifies that it meets the following minimum criteria:

(1) The Contractor: (i) is in compliance with workers' compensation and unemployment insurance requirements; (ii) is in compliance with Department of Revenue and Department of Employment and Economic Development registration requirements if it has employees; (iii) has a valid federal tax identification number or a valid Social Security number if an individual; and (iv) has filed a certificate of authority to transact business in Minnesota with the Secretary of State if a foreign corporation or cooperative.

(2) The contractor or related entity is in compliance with and, during the three-year period before submitting the verification, has not violated section 177.24, 177.25, 177.41 to 177.44, 181.03, 181.101, 181.13, 181.14, or 181.722, and has not violated United States Code, title 29, sections 201 to 219, or United States Code, title 40, sections 3141 to 3148. For purposes of this clause, a violation occurs when a contractor or related entity: (i) repeatedly fails to pay statutorily required wages or penalties on one or more separate projects for a total underpayment of $25,000 or more within the three-year period, provided that a failure to pay is “repeated” only if it involves two or more separate and distinct occurrences of underpayment during the three-year period; (ii) has been issued an order to comply by the commissioner of Labor and Industry that has become final; (iii) has been issued at least two determination letters within the three-year period by the Department of Transportation finding an underpayment by the contractor or related entity to its own employees; (iv) has been found by the commissioner of Labor and Industry to have repeatedly or willfully violated any of the sections referenced in this clause pursuant to section 177.27; (v) has been issued a ruling or findings of underpayment by the administrator of the Wage and Hour Division of the United States Department of Labor that have become final or have been upheld by an administrative law judge or the Administrative Review Board; or (vi) has been found liable for underpayment of wages or penalties or misrepresenting a construction worker as an independent contractor in an action brought in a court having jurisdiction. Provided that, if the contractor or related entity contests a determination of underpayment by the Department of Transportation in a contested case proceeding, a violation does not occur until the contested case proceeding has concluded with a determination that the contractor or related entity underpaid wages or penalties;*

Revised 2/3/2021 Page 1 of 5 (3) The contractor or related entity is in compliance with and, during the three-year period before submitting the verification, has not violated section 181.723 or chapter 326B. For purposes of this clause, a violation occurs when a contractor or related entity has been issued a final administrative or licensing order;* (4) The contractor or related entity has not, more than twice during the three-year period before submitting the verification, had a certificate of compliance under section 363A.36 revoked or suspended based on the provisions of section 363A.36, with the revocation or suspension becoming final because it was upheld by the Office of Administrative Hearings or was not appealed to the office;* (5) The contractor or related entity has not received a final determination assessing a monetary sanction from the Department of Administration or Transportation for failure to meet targeted group business, disadvantaged business enterprise, or veteran-owned business goals, due to a lack of good faith effort, more than once during the three-year period before submitting the verification;* * Any violations, suspensions, revocations, or sanctions, as defined in clauses (2) to (5), occurring prior to July 1, 2014, shall not be considered in determining whether a contractor or related entity meets the minimum criteria. (6) The contractor or related entity is not currently suspended or debarred by the federal government or the state of Minnesota or any of its departments, commissions, agencies, or political subdivisions that have authority to debar a contractor; and (7) All subcontractors and motor carriers that the contractor intends to use to perform project work have verified to the contractor through a signed statement under oath by an owner or officer that they meet the minimum criteria listed in clauses (1) to (6).

Minn. Stat. § 16C.285, Subd. 5. SUBCONTRACTOR VERIFICATION. A prime contractor or subcontractor shall include in its verification of compliance under subdivision 4 a list of all of its first-tier subcontractors that it intends to retain for work on the project. Prior to execution of a construction contract, and as a condition precedent to the execution of a construction contract, the apparent successful prime contractor shall submit to the contracting authority a supplemental verification under oath confirming compliance with subdivision 3, clause (7). Each contractor or subcontractor shall obtain from all subcontractors with which it will have a direct contractual relationship a signed statement under oath by an owner or officer verifying that they meet all of the minimum criteria in subdivision 3 prior to execution of a construction contract with each subcontractor. If a prime contractor or any subcontractor retains additional subcontractors on the project after submitting its verification of compliance, the prime contractor or subcontractor shall obtain verifications of compliance from each additional subcontractor with which it has a direct contractual relationship and shall submit a supplemental verification confirming compliance with subdivision 3, clause (7), within 14 days of retaining the additional subcontractors. A prime contractor shall submit to the contracting authority upon request copies of the signed verifications of compliance from all subcontractors of any tier pursuant to subdivision 3, clause (7). A prime contractor and subcontractors shall not be responsible for the false statements of any subcontractor with which they do not have a direct contractual relationship. A prime contractor and subcontractors shall be responsible for false statements by their first-tier subcontractors with which they have a direct contractual relationship only if they accept the verification of compliance with actual knowledge that it contains a false statement. Subd. 5a. Motor carrier verification. A prime contractor or subcontractor shall obtain annually from all motor carriers with which it will have a direct contractual relationship a signed statement under oath by an owner or officer verifying that they meet all of the minimum criteria in subdivision 3 prior to execution of a construction contract with each motor carrier. A prime contractor or subcontractor shall require each such motor carrier to provide it with immediate written notification in the event that the motor carrier no longer meets one or more of the minimum criteria in subdivision 3 after submitting its annual verification. A motor carrier shall be ineligible to perform work on a project covered by this section if it does not meet all the minimum criteria in subdivision 3. Upon request, a prime contractor or subcontractor shall submit to the contracting authority the signed verifications of compliance from all motor carriers providing for-hire transportation of materials, equipment, or supplies for a project.

Revised 2/3/2021 Page 2 of 5 Minn. Stat. § 16C.285, Subd. 4. VERIFICATION OF COMPLIANCE.

A contractor responding to a solicitation document of a contracting authority shall submit to the contracting authority a signed statement under oath by an owner or officer verifying compliance with each of the minimum criteria in subdivision 3, with the exception of clause (7), at the time that it responds to the solicitation document. A contracting authority may accept a signed statement under oath as sufficient to demonstrate that a contractor is a responsible contractor and shall not be held liable for awarding a contract in reasonable reliance on that statement. A prime contractor, subcontractor, or motor carrier that fails to verify compliance with any one of the required minimum criteria or makes a false statement under oath in a verification of compliance shall be ineligible to be awarded a construction contract on the project for which the verification was submitted. A false statement under oath verifying compliance with any of the minimum criteria may result in termination of a construction contract that has already been awarded to a prime contractor or subcontractor or motor carrier that submits a false statement. A contracting authority shall not be liable for declining to award a contract or terminating a contract based on a reasonable determination that the contractor failed to verify compliance with the minimum criteria or falsely stated that it meets the minimum criteria. A verification of compliance need not be notarized. An electronic verification of compliance made and submitted as part of an electronic bid shall be an acceptable verification of compliance under this section provided that it contains an electronic signature as defined in section 325L.02, paragraph (h).

CERTIFICATION

By signing this document I certify that I am an owner or officer of the company, and I certify under oath that: 1) My company meets each of the Minimum Criteria to be a responsible contractor as defined herein and is in compliance with Minn. Stat. § 16C.285, and 2) if my company is awarded a contract, I will submit Attachment A-1 prior to contract execution, and 3) if my company is awarded a contract, I will also submit Attachment A-2 as required.

Authorized Signature of Owner or Officer: Printed Name:

Title: Date:

Company Name:

NOTE: Minn. Stat. § 16C.285, Subd. 2, (c) If only one prime contractor responds to a solicitation document, a contracting authority may award a construction contract to the responding prime contractor even if the minimum criteria in subdivision 3 are not met.

Revised 2/3/2021 Page 3 of 5 ATTACHMENT A-1

FIRST-TIER SUBCONTRACTORS LIST

SUBMIT PRIOR TO EXECUTION OF A CONSTRUCTION CONTRACT

STATE PROJECT NUMBER: ______

Minn. Stat. § 16C.285, Subd. 5. A prime contractor or subcontractor shall include in its verification of compliance under subdivision 4 a list of all of its first-tier subcontractors that it intends to retain for work on the project. Prior to execution of a construction contract, and as a condition precedent to the execution of a construction contract, the apparent successful prime contractor shall submit to the contracting authority a supplemental verification under oath confirming compliance with subdivision 3, clause (7). Each contractor or subcontractor shall obtain from all subcontractors with which it will have a direct contractual relationship a signed statement under oath by an owner or officer verifying that they meet all of the minimum criteria in subdivision 3 prior to execution of a construction contract with each subcontractor.

FIRST TIER SUBCONTRACTOR NAMES* Name of city where company (Legal name of company as registered with the Secretary of home office is located State)

*Attach additional sheets as needed for submission of all first-tier subcontractors.

SUPPLEMENTAL CERTIFICATION FOR ATTACHMENT A-1

By signing this document I certify that I am an owner or officer of the company, and I certify under oath that: All first-tier subcontractors listed on attachment A-1 have verified through a signed statement under oath by an owner or officer that they meet the minimum criteria to be a responsible contractor as defined in Minn. Stat. § 16C.285.

Authorized Signature of Owner or Officer: Printed Name:

Title: Date:

Company Name:

Revised 2/3/2021 Page 4 of 5 ATTACHMENT A-2

ADDITIONAL SUBCONTRACTORS LIST

PRIME CONTRACTOR TO SUBMIT AS SUBCONTRACTORS ARE ADDED TO THE PROJECT

STATE PROJECT NUMBER: ______

This form must be submitted to the Project Manager or individual as identified in the solicitation document.

Minn. Stat. § 16C.285, Subd. 5. … If a prime contractor or any subcontractor retains additional subcontractors on the project after submitting its verification of compliance, the prime contractor or subcontractor shall obtain verifications of compliance from each additional subcontractor with which it has a direct contractual relationship and shall submit a supplemental verification confirming compliance with subdivision 3, clause (7), within 14 days of retaining the additional subcontractors. …

ADDITIONAL SUBCONTRACTOR NAMES* Name of city where company (Legal name of company as registered with the Secretary of home office is located State)

*Attach additional sheets as needed for submission of all additional subcontractors.

SUPPLEMENTAL CERTIFICATION FOR ATTACHMENT A-2

By signing this document I certify that I am an owner or officer of the company, and I certify under oath that: All additional subcontractors listed on Attachment A-2 have verified through a signed statement under oath by an owner or officer that they meet the minimum criteria to be a responsible contractor as defined in Minn. Stat. § 16C.285.

Authorized Signature of Owner or Officer: Printed Name:

Title: Date:

Company Name:

Revised 2/3/2021 Page 5 of 5 Public Works Department

Donald J. Theisen, P.E. Director

Wayne H. Sandberg, P.E. Deputy Director/County Engineer

ATTACHMENT B QUOTE SUBMITTAL FORM The undersigned agrees that if awarded the contract for services, to commence said services upon full execution of contract. Contractor must fill out the below Schedule of Prices to have a complete quote. LEGAL NAME OF PERSON, FIRM OR CORPORATION

Official Name and Address:

By: Title:

Phone #: Email:

Signature: Date:

Washington County RFQ – Misc Concrete June 2021

Schedule of Prices

ITEM TOTAL UNIT TOTAL ITEM DESCRIPTION UNIT NUMBER QTY. COST COST

2021.501 MOBILIZATION LS 1

2104.502 SALVAGE SIGN TYPE C EACH 2

2104.502 REMOVE CASTING EACH 2

2104.502 REMOVE DRAINAGE STRUCTURE EACH 2

2104.503 REMOVE CURB AND GUTTER LIN FT 120

2104.503 REMOVE SEWER PIPE (STORM) LIN FT 7

2104.503 SAWING CONCRETE PAVEMENT LIN FT 176

2104.504 REMOVE CONCRETE PAVEMENT SQ YD 76

2104.518 REMOVE CONCRETE MEDIAN SQ FT 208

2106.507 EXCAVATION - COMMON CU YD 75

2106.507 SELECT GRANULAR EMBANKMENT (CV) CU YD 40

2211.507 AGGREGATE BASE (CV) CLASS 5 CU YD 50

2301.504 CONCRETE PAVEMENT 8.0" SQ YD 76

2301.602 DRILL AND GROUT DOWEL BAR (EPOXY COATED) EACH 150

2503.602 CONNECT TO EXISTING STORM SEWER EACH 1

2503.503 12" RC PIPE SEWER DES 3006 LIN FT 7

2506.502 CONSTRUCT DRAINAGE STRUCTURE DESIGN H EACH 2

2506.502 CASTING ASSEMBLY EACH 2

2521.518 4" CONCRETE WALK SQ FT 208

2531.503 CONCRETE CURB AND GUTTER DESIGN B618 LIN FT 120

2545.502 ADJUST HANDHOLE EACH 2

2563.601 TRAFFIC CONTROL LS 1

2564.518 INSTALL SIGN TYPE C EACH 1

2565.602 RIGID PVC LOOP DETECTOR 6'X6' EACH 4

2573.502 STORM DRAIN INLET PROTECTION EACH 7

2582.503 4" SOLID LINE MULTI COMP GR IN (WR) LIN FT 72

2582.503 24" SOLID LINE MULTI COMP GR IN (WR) LIN FT 12

Total Quote: $______