Complex Segment Monitoring at Koralm Tunnel

Total Page:16

File Type:pdf, Size:1020Kb

Complex Segment Monitoring at Koralm Tunnel TJ_0513_OUTSIDE_FNT_COVER_PLUS_SPINE_001.qxd:cover 22/4/13 20:22 Page 1 www.tunnellingjournal.com April/May 2013 TTheunne international journal for the tunnelling industry llingjournal SEE PAGE 18 SEE PAGE 34 SEE PAGE 40 SEGMENTAL PROJECT JUBILEE INNOVATION POLITICS REPAIRS TJ LOOKS AT NEW THE COMPLEX A FASCINATING TECHNOLOGIES WORLD OF INSIGHT INTO AVAILABLE TO THE PROJECT POLITICS AN INTRIGUING SEGMENTAL LINING EXAMINED GROUTING SECTOR PROBLEM TUNNELLING JOURNAL SEGMENTAL LININGS IN FOCUS APRIL/MAY 2013 APRIL/MAY THE KORALM’S SEGMENT TRACKING SYSTEM TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:33 Page 10 SEGMENTAL LINING The Koralm Project at a glance Austria's new Koralm tunnel is one of the the west and the harder gneiss of the largest infrastructure projects in Europe outside mountains. Strabag did that work in 2005-07, of the three great Alpine pass crossings at making a small 45m2 cross-section bore. Brenner, the Swiss Gotthard and France's Fréjus. “It was thought this might be a difficult area At just under 33km long and with a maximum but in the end it was more straightforward than cover of nearly 1200m it is at least approaching thought,” says Lehner. the same kind of scale. The interface fixes two different types of The twin bores for high-speed rail trains will tunnelling for the project which uses form a critical link through Klagenfort in conventional excavation in hard clays to the southern Austria and on to the north east via west and switches to TBM for the longer hard Graz and Vienna. Another major tunnel, the rock. This is mainly gneiss, a layered form first, Semmering is also required and is currently with split planes - it is used locally for making under tender by the Austrian Federal Railways, roof tiles – and then solid older rock. which is also the client for the Koralm. The main contract, for some 600M, was The Austrian route section in turn is part of a begun in January 2011 with formation of two key trans-European route, the Axis 23 Adriatic-B deep access shafts and the conventional drives Baltic corridor which will eventually connect heading in both directions. They also saw the Gdansk on the Polish north coast with Venice in creation of two large parallel caverns for the north-east Italy. assembly of the TBMs. The Koralm tunnel has been split into three The Aker Wirth machines, each with a double main sections. A small southern contract has head, arrived on site late last year and the first already formed the portal and an initial began driving in February with the second conventionally excavated 2km of tunnel. It starting work just before Easter. They have an starts near the little town of Deutschlandsberg outside diameter of 9.93m. Swiss firm Rowa sited in the vine and farmland valley supplies the follow on back up train and countryside before the Koralm mountain range. segment delivery equipment. It is almost complete. They erect a six segment ring as they go, five Second and largest of the contracts, pieces plus a full size key element; inner underway since late 2011 is for the central diameter of the rings is 8.8m and the ring portion, with around 2km of conventionally segment thickness is 350mm leaving an annulus excavated tunnel required for each bore and of 200mm which is filled with pea gravel. then long TBM drives through the hard rock of Details of the tunnelling will be explored in a the Koralm mountains. These are slightly follow on article. different lengths, 17.1km on the north side and 15.7km on the south. Both machines have just begun work. Czech Republic The drive length difference is due to previous exploratory works on the third section and Germany Slovakia logistical issues which alter the breakthrough Vienna point on the southern bore, explains Wolfgang Lehner. He is project director for the joint A venture carrying out the work, formed from an I 80% majority of contractor Strabag with R T Austrian tunnel specialist Jägerbau. S “There was a shaft and fairly long exploratory U Hungary A Graz tunnel of around 10km done for the Lot three,” he says. The third contract, to be let shortly, is Klagenfurt for 12.8km of twin tunnel, most to be done by TBM. Italy Slovenia Croatia An exploratory tunnel was also done for the longest central section, to pin down the geology Above: plan map of the Koralm Tunnel as much as possible and particularly to find the location. Below: section showing the interface point between soft glacial ground in construction lots of the tunnel Main construction sections Koralm tunnel Percentage of the overall excavation Neogene sections: Styria East portal NATM 4.1km KAT I: 8% KAT II: 57% Crystalline KAT III: 35% Carinthia TBM 15.7km ult ttal Fa van NATM 5.1km La e/ en TBM 12.1km KAT I g o e N TBM 17.1km KAT II .6km el 10 tunn tory NATM 0.7km lora /exp TM A Shaft: 60m West portal N KAT III NATM: 4.4km TBM: 32.8km 10 TUNNELLING JOURNAL TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:33 Page 11 SEGMENTAL LINING KORALM TUNNEL SEGMENTS - complex monitoring and management Strict quality control and tracking requirements are being met with the SDS computerised production control system for the segments going into the new Koralm tunnel in Austria. Adrian Greeman visited the site and files this report DRIVES FOR THE MAIN sections of the segments have been set by the client ÖBB- Koralm high speed railway tunnel project Infrastruktur, the capital works division of began work at the beginning of this year, two Austrian state railways. As well as tight quality 9.9m diameter TBM hard rock bores of 15.7km assurances it wants full traceability of the and 17.1km length respectively form the lines components in the segments to allow for on the north and south sides of the alignment. easier trouble-shooting and investigation in the They will take around three years to complete event of damage or failure within the tunnels. their eastwards progress, meeting eventually The requirements arise particularly from with 12km and 10km drives coming the other caution about potential difficulties in the rock way by another contractor. and particularly in the first seven or so The Strabag-Jägerbau joint venture kilometres of the drives through striated gneiss contractor for the central and largest section of with significant slip surfaces in the rock. For this the project, Lot 2, is pleased with the start it section there is also a very unusual requirement has made on the TBM sections. The first for an in situ lining. machine began in February on the southern “The TBM will install a basic segmental lining bore and the second machine starting work and then we will follow on with a waterproof earlier than expected, just before Easter. drainage membrane and in situ inner shell cast Meanwhile in its first two years, the using a travelling formwork as you would in a contractor has already made some 4.4km of conventional tunnel,” says Strabag project tunnel by conventional methods in soft ground director for the joint venture Wolfgang Lehner. near the western end. But the hard rock drives In the later harder gneiss section the tunnel are the key part of its €600M contract. will use simply the plain segmental lining. A key element of its work in the initial period All these segments must be produced on of the contract has been setting up and site. The client ruled out segment production preparing for the segment production and elsewhere and delivery to site because of the delivery to the machines which will consume potential disruption it would cause. The area is eventually some 103,500 segments for the a pleasant rolling landscape of farmland, rings and another 17,250 larger invert vineyards and small townships. segments. These 13.4t pieces are for a flat floor “The delivery of so many segments by trucks which is installed immediately behind the over a three year period would have been machine and to which are bolted twin railway impossible,” says Andreas Lange, segment tracks for personnel carriers, logistics and production manager. He says that it would also machine supply of segments and grout. have been difficult to bring them in by rail, Strict requirements for quality of the because although there is a line to the site, TUNNELLING JOURNAL 11 TJ_0513_KORALM_010_016.qxd:Feature 22/4/13 20:35 Page 14 SEGMENTAL LINING installed as part of the mobilisation, it does not tolerances,” says Nod Clarke-Hackston, have sufficient capacity. “It is needed for international sales manager for VMT, “and supplies like the pea gravel, grout and so forth even a fraction of a millimetre can set it out.” and for removal of spoil,” he say. The system uses input from modern laser But producing so many segments on site has scanners, two of which in fixed positions can its own difficulties, most of all the space. be used either to scan the interior of a steel Within a tightly constrained area the contractor form or the final segments once removed. The must have not only its tunnel access and spoil factories at Koralm have a measuring space disposal handling but also two segment fitted with Faro scanners. factories and a storage area. “That is very These can work in minutes compared to small,” says Lange. For his purposes, he has a painstaking day long checking with total yard stretching approximately 150m in each stations required in the past. A 3-d best-fit direction from the central tunnel access shafts, volume model is produced.
Recommended publications
  • Koralm Tunnel
    KORALM TUNNEL – DEVELOPMENT OF TUNNEL SYSTEM DESIGN AND SAFETY CONCEPT Christof Neumann, Florian Diernhofer, ILF Consulting Engineers, Austria Gerhard Harer, Josef Koinig, OEBB Infrastruktur Bau AG 1 ABSTRACT The 32.8-km-long Koralm tunnel requires additional measures to guarantee a sufficient safety level. The methodology applied to define safety measures for this very long tunnel is on the one hand based on a set of guidelines and on the other hand based on the specific boundary conditions of this tunnel. These tunnel-specific conditions are considered by establishing customized safety targets. As a result of an investigation into the construction and operating phase, the tunnel system was determined to consist of two single-tube tunnels, an emergency station, no crossover and cross- passages every 500 m. The emergency station in the centre of the tunnel, which incorporates various considerations, was designed to accommodate staggered platforms and a refuge room with a length of 800 m. With a view to the incident management strategy to be adopted, characteristic operating scenarios were analysed to realistically reflect the sequence of events in case of an emergency. 2 THE KORALM TUNNEL PROJECT The Koralm tunnel is one of the key elements of the Koralm high-capacity railway line, which connects the cities of Graz and Klagenfurt in the south of Austria. The Koralm railway line is part of the Baltic-Adriatic Axis, which represents the easternmost crossing of the Alps and links several Eastern European countries Koralm line with Koralm tunnel and Vienna with southern Austria and northern Italy. The Koralm line is a 130- km-long high-capacity railway line engineered for a design speed of 200 km/h.
    [Show full text]
  • Southern Line Experience More
    SOUTHERN EXPERIENCE LINE MORE 80 km NEW TUNNELS AND UNDERPASSES 3,500,000 18 PEOPLE LIVING IN THE SOUTHERN NEWLY BUILT RAILWAY STATIONS, TRAIN LINE’S COMMUTER BELT STOPS, AND FREIGHT TRAFFIC FACILITIES 33 km KORALM TUNNEL, ONE OF THE LONGEST RAILWAY TUNNELS IN THE WORLD 1 h 20 min 250 km/h SHORTER TRAVEL TIME POSSIBLE MAXIMUM VIENNA – KLAGENFURT LINE SPEED WL 15,000 JOBS IN THE OPERATING STAGE AFTER 2026 50 min 2026 SHORTER TRAVEL NEW, MODERNISED TIME GRAZ - VIENNA FACILITIES PUT INTO OPERATION Experience more. > 5,000 EMPLOYED WORKERS When we say "experience more", we mean all the 200 km 14,000,000 many dimensions of human travel: arriving, living EXTENDED, MODERNISED TONS OF EXCAVATED AND RAILWAY LINE EXTRACTED MATERIAL and learning. 150 NEW BRIDGES AND In 2026, trains will speed from Vienna to Klagen- UNDERPASSES furt in just 2 hours and 40 minutes and from Graz to 170 km 210,000 NEW CONSTRUCTION ROUTE NEW SEGMENTS ARE BEING Klagenfurt in 45 minutes. Covering a total of 470 km, BUILT IN THE TUNNEL they will pass through numerous new railway stations ~90 and through the Semmering and the Koralpe moun- MODERNISED RAILWAY STATIONS AND TRAIN STOPS tains at the highest of speeds. And when it comes to more "experiences" - just wait until Austria’s new Southern Line opens! 4 The Benefits The Benefits 5 The future of traveling and transport SHORTER TRAVEL TIMES The Southern Line is one of the largest and most VIENNA – GRAZ 2017: from 2 h 35 min 2026: 1 h 50 min VIENNA – KLAGENFURT 2017: from 3 h 55 min 2026: 2 h 40 min spectacular infrastructure projects of the coming decade.
    [Show full text]
  • Baltic-Adriatic Corridor
    CEF support to Baltic-Adriatic Corridor Innovation and Networks Executive Agency Baltic-Adriatic FEBRUARY 2018 1 Table of Contents 1. Introduction ......................................................................................................................................................................... 3 2. Action portfolio: State of play ................................................................................................................................. 4 2.1. Operational Implementation ....................................................................................................................... 4 2.1.1. Maritime .................................................................................................................................................................. 5 2.1.2. Multimodal ............................................................................................................................................................ 5 2.1.3. Rail ............................................................................................................................................................................... 6 2.1.4. Road ......................................................................................................................................................................... 10 2.1.5. Financial implementation ...................................................................................................................... 13 3. Evolution of the Action portfolio
    [Show full text]
  • Eastern Alps)
    1661-8726/09/010031-11 Swiss J. Geosci. 102 (2009) 31–41 DOI 10.1007/s00015-009-1305-5 Birkhäuser Verlag, Basel, 2009 Stream profile analysis of the Koralm Range (Eastern Alps) GERD RANTITSCH 1, *, GERALD PISCHINGER 2 & WALTER KURZ 3 Key words: Eastern Alps, geomorphology, fluvial erosion, stream profiles, exhumation ABSTRACT The Koralm Range at the eastern margin of the Eastern Alps shows an asym- tilting of the Koralm Range as a consequence of a Miocene block rotation, metric topography. Steep slopes and short stream channels characterize the slope-area data from stream channels suggest a spatial differential uplift south-western segment, whereas gentle slopes and elongated catchments pattern. A north-to-south-increase of the steepness values might indicate incise the mountain range towards the east. The fluvial landscape dissecting faster uplift rates in the central Koralm Range. This trend is traced by Pa- this mountain range is characterized by stream long profiles and by ana- leogene low-temperature geochronological data and by the Late Cretaceous lyzing the power-law scaling between stream slope and drainage area. The metamorphic field gradient. Thus, it may be explained by a long-term spatial concave-up form of the stream long profiles suggests an equilibrium state pattern of exhumation and subsequent uplift which remained stable since of the fluvial landscape. In accordance with a tectonic model describing the the Late Cretaceous. Introduction morphometric analysis of a digital elevation model (Frisch et al. 2000b; Székely 2001), by a sediment budget of the Alps The interaction of climate, endogenous and exogenous pro- (Kuhlemann et al.
    [Show full text]
  • New Emission Data for Ventilation Design for Road Tunnels
    - 1 - DUST LOADS IN RAILWAY TUNNELS – RESULTS FROM IN-SITU MEASUREMENTS AND CONSEQUENCES FOR TUNNEL FACILITIES AND RAILWAY OPERATION 1Helmut Steiner, 2Peter Sturm, 2Daniel Fruhwirt, 1ÖBB Infrastruktur AG, A; 2Graz University of Technology, A ABSTRACT Several long railway tunnels are currently under construction in Austria (e.g. the Koralm Tunnel / KAT; Semmering Base Tunnel / SBT; Brenner Base Tunnel / BBT). The project KAT is now at the beginning stage of implementation with respect to technical railway equipment. In order to complete the detailed planning several very specific topics have to be examined in detail. The ÖBB (Austrian railway corporation) has thus begun detailed research in the relevant areas in order to grapple with problems at their root, and to allow for findings to be incorporated into ongoing projects. For example, it is known from cases in Switzerland, where several long railway tunnels have been in operation for years (Lötschberg Base Tunnel / LBT; Gotthard Base Tunnel / GBT), that technical equipment needs a lot of maintenance when it is exposed to high dust loads. The quantity and composition of the dust also play a key role here. To assess the nature of the problem, in-situ measurements were thus carried out in an ÖBB railway tunnel under full operation in Upper Styria. The knowledge gained from these measurements is to be integrated into current and future rail tunnel projects. Specific attempts were made to derive characteristic emission factors in relation to different train types. It should then prove possible to estimate total dust emissions in current and future projects, depending on the specific operating programs, timetables, train mix etc.
    [Show full text]
  • Öbb-Infrastruktur Aktiengesellschaft
    Supplement No. 2 dated 14 June 2013 to the Debt Issuance Programme Prospectus dated 27 June 2012 ÖBB-INFRASTRUKTUR AKTIENGESELLSCHAFT Euro 20,000,000,000 Debt Issuance Programme Guaranteed by the Republic of Austria (the "Programme") This supplement no. 2 to the Euro 20,000,000,000 Debt Issuance Programme Prospectus of ÖBB-Infrastruktur Aktiengesellschaft ("ÖBB-Infrastruktur AG" or the “Issuer”) dated 27 June 2012 (the "Supplement No. 2") is prepared in connection with the Programme for the issue of notes issued under this Programme (the "Notes") of ÖBB-Infrastruktur AG and is supplemental to, and should be read in conjunction with, the Debt Issuance Programme Prospectus dated 27 June 2012 (the "Original Prospectus") and the supplement no. 1 to the Original Prospectus dated 29 April 2013 (the "Supplement No. 1") in respect of the Programme. This Supplement No. 2 is a supplement in the meaning of article 13.1 of the Luxembourg Act on Securities Prospectuses (loi relative aux prospectus pour valeurs mobilières) which implements article 16 of the Prospectus Directive. Unless otherwise stated or the context otherwise requires, terms defined in the Original Prospectus have the same meaning when used in this Supplement No. 2. As used herein "Prospectus" means the Original Prospectus as supplemented by the Supplement No. 1 and this Supplement No. 2. The Supplement No. 2 is related to (i) recent changes relating to the description of the Issuer and (ii) the publication of the annual financial report for the business year 2012 containing the consolidated financial statements of the Issuer as of 31.12.2012.
    [Show full text]
  • Koralm Railway, Construction Stage KAT3 — World of PORR
    World of PORR 168/2016 PORR Projects Koralm railway, construction stage KAT3 Andreas Karlbauer Der zyklische Vortrieb in der Südröhre setzt sich aus folgenden Teilvortrieben zusammen: The Koralm railway line (Graz – Klagenfurt section) Together with the new Semmering base tunnel and the Aufweitung Neogen VT-SÜ (581 m) Vienna main train station, the Koralm railway line forms part of Aufweitung Neogen MI-SÜ (4.075 m) a key project along the Baltic-Adriatic Corridor. The objective Aufweitung Kristallin MI-SÜ (2.513 m) of the corridor is to connect the individual regions and Vollausbruch Kristallin MI-SÜ (2.728 m) emerging economies between the Baltic and Adriatic regions Demontagekaverne (40 m) together. Koralm tunnel overview Bench cutting south tube Image: ÖBB/Die Presse/HR Image: PORR AG The Koralm tunnel Dismantling cavern south tube The Koralm tunnel is 32.9km long and crosses the Koralpe The size of the dismantling cavern for the TBM from the KAT2 mountain massif at depths of up to 1,200m and connects construction stage was optimised together with the client Deutschlandsberg in Styria with Lavanttal in Carinthia. Two during construction. By using two hanging rails with hoists tunnel tubes run parallel to each other at a distance of about mounted in the transom, as an alternative to a gantry crane, 25 to 50m apart and are connected to each other every 500m the cross-section could be reduced from 354m² to 170m². with cross passages. Completion is expected in 2023. Trains will then be able to travel under the Koralpe at a top speed of Exploratory boreholes 250km/h.
    [Show full text]
  • Tunnel Safety Concept Koralm Tunnel
    Tunnel Safety Concept Koralm Tunnel Christof Neumann1, Florian Diernhofer1, Christian Sommerlechner2, Manuel Burghart3 1 ILF Consulting Engineers, Austria 2 ÖBB Infrastruktur Betrieb AG, Austria 3 ÖBB Infrastruktur Bau AG, Austria ABSTRACT The 32.8-km-long Koralm tunnel requires additional measures to guarantee a sufficient safety level. The methodology applied to define safety measures for this very long tunnel is on the one hand based on a set of guidelines and on the other hand based on the specific boundary conditions of this tunnel. These tunnel-specific conditions are considered by establishing customized safety targets. All aspects of safety are summarized in a specific tunnel safety concept. As a result of an investigation into the construction and operating phase, the tunnel system was determined to consist of two single-tube tunnels, an emergency station, cross-passages every 500 m and no crossover. The emergency station in the centre of the tunnel, which incorporates various considerations, was designed to accommodate staggered platforms and a combined refuge room with a length of 800 m. The physical structures of the emergency station (distance of escape tunnels, door configurations, etc.) were checked by application of an evacuation simulation. With a view to the incident management strategy to be adopted, characteristic operating scenarios were analysed to realistically reflect the sequence of events in case of an emergency. Keywords: tunnel safety, railway safety, emergency station INTRODUCTION The Koralm railway line is part of the so-called Pontebbana corridor, which represents the easternmost crossing of the Alps and links several Eastern European countries and Vienna with southern Austria and northern Italy (see figure 1).
    [Show full text]
  • The Koralm Connection
    EUROPE / SITE REPORT HEN AUSTRIA’S new Koralm high-speed railway line opens in December 2023 another piece THE KORALM ofW the Trans-European Transport Network (TEN-T) will be in place. The line is part of the 2,400km trans-European Baltic-Adriatic Corridor CONNECTION linking the Baltic and Adriatic coasts Austria’s Koralm tunnel is part of a new alpine link in and connecting 40 million people. It stretches from Gdansk and Gdynia on Europe. Keren Fallwell reports the northern coast of Poland to Bologna in northern Italy, crossing through the Czech Republic and Slovakia along the way and providing a direct link between the capital cities of Warsaw and Vienna. ❱ Aerial view of the job site with gantries visible in the distance Keren Fallwell Keren joins the Tunnels and Tunnelling team as a contributing editor this year www.tunnelsonline.info January 2016 | Tunnels | 33 033_036tun0116koralm.indd 33 22/12/2015 11:13 SITE REPORT / EUROPE The 130km-long Koralmbahn, being Above: Panorama Before the main excavation for the tunnel, 130 exploration built for ÖBB-Infrastruktur, will provide photograph wells and a 10km-long exploratory tunnel system were a direct rail link between the cities inside the tunnel excavated to carry out in-depth analysis of the geological and of Klagenfurt and Graz, the capitals hydrogeological conditions. of the states of Carinthia and Styria respectively, reducing the current travel CONTRACT DETAILS time of three hours to less than one The tunnel construction is divided into three main sections: hour. It will also allow heavy freight KAT1, KAT2 and KAT3.
    [Show full text]
  • Rescue, Evacuation and Fire Protection at the Koralm
    - 21 - INCIDENT TESTED: RESCUE, EVACUATION AND FIRE PROTECTION AT THE KORALM TUNNEL 2 A REVIEW OF THE FIRE EVENT IN 2015 AND THE PRACTICAL IMPLEMENTATION OF THE CONCEPT IN THE EVENT OF AN INCIDENT S. Fehleisen, ÖBB-Infrastruktur AG J. Frießnegg; ARGE KAT2, Austria 1. ABSTRACT As a new high-speed railway connection between Graz and Klagenfurt, the Koralm Railway represents a crucial component in the context of the Baltic-Adriatic Corridor. With a length of about 33 kilometres, the Koralm Tunnel--the centrepiece of this new line--will become one of the longest traffic tunnel constructions in the world. In the tunnel construction phase, the construction lot “Koralm Tunnel 2” represents the longest of the three main construction lots. Apart from excavator driving and drill-and-blast driving, two tunnel boring machines are also being used on this 20 kilometre length. The length as well as the complexity already pose specific challenges for the construction phase in terms of safety, rescue and evacuation, and fire prevention. With the starting of the construction in 2011, the implementation of the rescue, evacuation and fire protection concept specified in the tender was also initiated by the contractor in cooperation with the client and the emergency services. In February 2015, the emergency management had to be put into real action on account of a fire in an standby generator on one of the two tunnel boring machines. The fire could be brought under control successfully and all persons were rescued and evacuated from the tunnel unharmed. The professional and calm handling of the incident showed how significant prior emergency drills and coordination are.
    [Show full text]
  • POLITECNICO DI TORINO Repository ISTITUZIONALE
    View metadata, citation and similar papers at core.ac.uk brought to you by CORE provided by PORTO@iris (Publications Open Repository TOrino - Politecnico di Torino) POLITECNICO DI TORINO Repository ISTITUZIONALE Prediction of performance and cutter wear in rock TBM: Application to Koralm tunnel project Original Prediction of performance and cutter wear in rock TBM: Application to Koralm tunnel project / Brino, Gabriele; Peila, Daniele; Steidl, Arnold; Fasching, Florian. - In: GEAM. GEOINGEGNERIA AMBIENTALE E MINERARIA. - ISSN 1121- 9041. - 145:2(2015), pp. 37-58. Availability: This version is available at: 11583/2642312 since: 2016-09-29T11:28:53Z Publisher: Patron Editore S.r.l. Published DOI: Terms of use: openAccess This article is made available under terms and conditions as specified in the corresponding bibliographic description in the repository Publisher copyright (Article begins on next page) 04 August 2020 GEOINGEGNERIA E ATTIVITÀ ESTRATTIVA Gabriele Brino* Prediction of performance Daniele Peila* Arnold Steidl** and cutter wear in rock TBM: Florian Fasching** application to Koralm tunnel * DIATI, Politecnico di Torino **3G Gruppe Geotechnik Graz project 1. Introduction Excavation by Tunnel Boring Machines is the tunnelling method most frequently used nowadays in long infrastructural projects, in a wide range of geological conditions. In the last 40 years, many predic- Tunnel Boring Machines are tion models were developed to estimate TBM performance and cutter wear, using as input geological parameters. The research gives an overview of the existing penetration models for hard rock TBMs, nowadays a common and fruitful identifies the most frequently used input parameters and summarizes the characteristics of the da- option a tunnel designer can adopt, tasets on which the models are based on.
    [Show full text]
  • AGRUFLEX™ Tunnel Liner Protects Koralm Tunnel from Ground Water
    AGRUFLEX™ Tunnel Liner Protects Koralm Tunnel from Ground Water Scheduled to be operational in 2022, the Koralm Tunnel project, at 20 miles, will be Austria’s longest railway tunnel. The ambitious project is part of the Koralm Railway project, an 80 mile line that will link Graz with Klagenfurt. The new high speed line is expected to reduce travel time between the two cities from three hours to one. The Koralm Tunnel, which runs at depths of 4000 feet below the surface in the Koralpe mountain range, is comprised of two parallel tunnels, each with a single track, linked with crossways every 550 yards. Construction Challenges: The geomembrane used to seal the tunnel had to meet the strict 2012 Austrian Tunnel Sealing Guideline Koralm Tunnel, Austria (Österreichische Bautechnik Vereinigung or ÖBV). It also had to protect the new tunnel from groundwater. The Solution: Construction began in 2008 at the tunnel’s east entrance or the KAT 1, a section length totaling approximately 1.4 miles. To meet the ÖBV guideline and protect the tunnel from groundwater seepage, engineers chose 2.1 mm AGRUFLEX tunnel liner. Approximately 1,400,000 sq. ft. of the 80 mil. liner was installed between 2012 and 2013, along with an additional 40,000 feet of water stop profiles (AA 500/6.) The KAT 1 tunnel section was successfully completed in November 2013. Extensive testing has proven that the AGRUFLEX tunnel liner has met the ÖBV Guideline for chemical and water resistance and has minimal environmental impact. AGRUFLEX Tunnel Liner • A very low density polyethylene
    [Show full text]