Form – I for Residential Building Complex Dugar Housing Limited

FORM – I I. BASIC INFORMATION

S. No. Item Details 1 Name of the project Residential Building Complex - “Sky Dugar" 2 S. no. in the schedule 8 (a) Area Details: 3 Proposed area Total land area: 13,240 Sqm Total built-up area: 30,594 Sqm 4 New/Expansion/Modernization New 5 Existing capacity/Area etc - 6 Category of project i.e. ‘A’ or ‘B’ B Does it attract the general condition? If 7 No yes, please specify Does it attract the specific condition? If 8 No yes, please specify Plot/Survey/Khasra No S.Nos: 117/1 & 119 Village Ayanambakkam 9 Tehsil District Thiruvallur State Tamilnadu Railway station : Ambattur Railway Station Nearest railway station/airport along (5 km) 10 with distance in kms Airport : International Airport (19 km) Nearest town, city, district headquarters The project site falls within the developed 11 along with distance in kms Chennai City. Thiruverkadu Municipality, Village panchayats, Zilla parishad, No. 7, Vedapureswaram, municipal corporation, local body 12 Thiruverkadu, (Complete postal addresses with Chennai – 600077, telephone nos. to be given) Tel. No: (044) 26800437. 13 Name of the applicant Dugar Housing Limited New No. 34, Old No. 123 7th Floor, Dugar Towers, 14 Registered address Rukmani Lakshmipathi Road, , Chennai – 600008.

Eco Services Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

Address for correspondence: Mr. Pradeep Jangra Name Vice President Designation New No. 34, Old No. 123 Address 7th Floor, Dugar Towers, 15 Rukmani Lakshmipathi Road, Egmore, Chennai – 600008. Pin code 600 008. E-mail [email protected] Telephone No. / Fax No. (044) 28587676 Details of alternative sites examined, if 16 any, Location of these sites should be No shown on a topo sheet 17 Interlinked projects No interlinked projects Whether separate application of 18 No interlinked project has been submitted? 19 If yes, date of submission - 20 If no, reason - Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. (a) The forest (conservation) Act, 21 No 1980? (b) The wild life (Protection) Act, 1972? (c) The CRZ Notification 1991 Whether there is any government 22 No order/policy relevant/relating to the site 23 Forest land involved (hectares) No Whether there is any litigation pending against the project and/or land in which the project is propose to be set up? a) Name of the Court 24 No b) Case No c) Orders/directions of the court, if any and its relevance with the proposed project

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

II. ACTIVITY

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies etc.)

Details thereof (with approximate S. Information/Checklist Yes/No quantities /rates, wherever possible) with No. confirmation sources of information data Change in land use from vacant site to residential use. No change in topography as Permanent or temporary the existing land is a flat terrain. The Project change in land use, land site comes under General Industrial Zone cover or topography and the development of residential building 1.1 including increase in Yes complex is permitted under this zone. Also, intensity of land use (with the TNPCB concurrence has been obtained respect to local land use based on which the building plan approval is plan) given by CMDA. The documentary evidence of ownership and land use is enclosed as Annexure –II. The project site was vacant land without Clearance of existing land, 1.2 Yes trees and only clearance of ground shrubs vegetation and buildings? was carried out. The vacant land was converted into 1.3 Creation of new land uses? Yes residential building complex. Pre-construction Geo-technical investigations have been 1.4 investigations e.g. bore Yes carried out and the copy of the report is holes, soil testing ? enclosed as Annexure –III. Construction of residential building complex with following components:

Block 1 S + 4 Floors

Block 1 (LIG S + 4 Floors 1.5 Construction works? Yes Block) Block 2 S + 4 Floors

Block 3 S / G + 4 Floors

Block 4 S / G + 4 Floors

1.6 Démolition Works? No No Demolition works was carried out. Temporary sites used for No labour camps were proposed, since local 1.7 construction works or No laborers from nearby areas were hired for housing of construction the work. Adequate drinking water and

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

workers? sanitation facilities were provided for them at the project site. 1.8 Above ground buildings, Construction of residential building complex structures or earthworks with following components: including linear structures, Block 1 S + 4 Floors cut and fill or excavations Block 1 (LIG S + 4 Floors Yes Block) Block 2 S + 4 Floors

Block 3 S / G + 4 Floors

Block 4 S / G + 4 Floors

Underground works 1.9 including mining or No Nil tunneling? 1.10 Reclamation Works? No Nil 1.11 Dredging? No Nil 1.12 Offshore structures? No Nil Production and Nil 1.13 No manufacturing processes? Construction material storage/handling yard was located within the project site and Facilities for storage of separated by enclosures/barricades. Cement 1.14 Yes goods or materials? was stored under cover in bales. Sand wasbe stacked under tarpaulin cover. Bricks/blocks and steel was laid in the open. Solid Waste: Wastes generated in the project site during construction (debris) was used for backfilling and leveling within the site. Solid waste during operation phase is being collected and segregated. The biodegradable waste will be collected and treated through Facilities for treatment or Organic Waste Converter (OWC). Non bio 1.15 disposal of solid waste or Yes degradable waste will be segregated liquid effluents? according to its characteristics & handed over to recyclers for disposal. Liquid Effluent: During the construction phase, sewage from temporary toilets was disposed through septic tanks with soak pits. During the operation phase, the sewage generated will be treated in installed Sewage

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

Treatment Plant and reused within the premises.

Facilities for long term No No facilities for long term housing of 1.16 housing of operational operational workers are proposed. workers? New road, rail or sea traffic 1.17 during construction or No Existing infrastructure will be used. operation? New road, rail, air waterborne or other transport infrastructure 1.18 No Nil including new or altered routes and stations, ports, airports etc? Closure or diversion of existing transport routes or 1.19 infrastructure leading to No Nil changes in traffic movements? New or diverted Power Supply from TANGEDCO & Water 1.20 transmission lines or No Supply connection from local body will be pipelines? obtained prior to occupancy Impoundment, damming, culverting, realignment or 1.21 other changes to the No Nil hydrology of watercourses or aquifers? 1.22 Stream crossings? No Nil Abstraction or transfers of The private tanker water supply / through 1.23 water from ground or No local body connection available in the surface waters? project area. Changes in water bodies or 1.24 the land surface affecting No Nil drainage or run-off? Transport of personnel or materials for construction, There was movement of men and materials 1.25 Yes operation or during construction & operational phases. decommissioning? Long-term dismantling or 1.26 No - decommissioning which

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

could have an impact on the environment? Ongoing activity during decommissioning which 1.27 No - could have an impact on the environment? There will be a daily movement of people Influx of people to an area during the operation phase as the 1.28 in either temporarily or Yes development is a residential building permanently? complex. Introduction of alien 1.29 No - species? The existing land was devoid of trees. Only Loss of native species or No 1.30 ground shrubs exists was cleared during genetic diversity? construction. 1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of the Project (Such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Details thereof (with approximate quantities / S. Information/Checklist Yes/ rates, wherever possible) with sources of No. confirmation No information data Land especially undeveloped 2.1 No The land was vacant when it was acquired. or agricultural land (ha) 25-30 KLD of water was used during peak construction period. The daily fresh water requirement during operation phase is estimated Water (expected source & 2.2 Yes to be about 112 KLD upon full occupancy and competing users) Unit: KLD this is sourced from private tanker water supply system prevailing in the area / through the local body connection. Minerals like Limestone, Clay, Shale, Gypsum, 2.3 Minerals (MT) Yes Aggregate were used in construction materials Cement (10974 tons), Sand (783787 CFT). Construction materials were sourced from the Construction material – stone, 2.4 local market. Materials with good post industrial aggregates, and / soil (expected Yes recycle content like aerocon blocks (Fly ash), source- cum) steel etc. were used in the projects. Forests and timber (source– Plywoods (90 tons) with good recycled content 2.5 Yes MT) was used in the residential buildings.

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

The estimated power requirement during operation phase is about 2500 kVA and it will be Energy including electricity sourced from the nearby TNEB grid. For power and fuels (source, competing 2.6 Yes back-up during the failure of supply from TNEB users) Unit: fuel (litres/hour), grid, it is proposed to install 2 nos of 500 kVA energy (kVA) capacity DG sets. Low sulphur content HSD will be used as fuel for DG sets. Any other natural resources No 2.7 (use appropriate standard -

units)

3. Use, storage, transport, handling or production of substances or materials which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. Details thereof (with approximate quantities S. Information/Checklist Yes/ /rates, wherever possible) with sources of No. confirmation No information data Use of substance or materials, No Storage and handling of hazardous chemicals which are hazardous (as per (as per MSIHC) will be done apart from use of 3.1 MSIHC rules) to human health No diesel in DG Sets. Fuel used for the DG sets will or the environment (flora, be of Low Sulphur High Speed Diesel (Sulphur fauna, and water supplies) content< 0.005%). Suitable drainage and waste management Changes in occurrence of measures will be adopted to prevent stagnation of disease or affect disease 3.2 No water and restrict accumulation of waste. This vectors (e.g. insect or water will effectively restrict the reproduction and borne diseases) growth of disease vectors. The standard of living of the nearby locals will improve due to the employment opportunities created by the Residential Development. On completion of the project, it will improve not Affect the welfare of people only the infrastructure facility but will also 3.3 e.g. by changing living No improve the aesthetic looks of the surroundings. conditions? Socio economic conditions of nearby areas will improve due to local employment (direct and in direct) Moreover, this project will provide employment to local laborers during the construction and operational phases. Vulnerable groups of people who could be affected by the 3.4 No - project e.g. hospital patient’s children, the elderly etc.,

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

3.5 Any other causes No -

4. Production of solid wastes during construction or operation or decommissioning (MT/ month) Details thereof (with approximate quantities S. Information/Checklist Yes/ /rates, wherever possible) with sources of No. confirmation No information data The excavated earth and construction debris were Spoil, overburden or mine 4.1 Yes used for backfilling and level rising within the wastes project site. In the Residential Building complex, private sweepers are engaged for handling domestic waste and appropriate site will be identified for keeping bin / container for the collection of waste. Adequate number of colored collection bins separately for biodegradable and non biodegradable waste will be provided as per the Municipal Solid Waste (Management and Handling) Rule, 2000. All the collection bins will be properly maintained and cleared on regular basis.

Waste from such bins will be collected separately on daily basis and taken to a separate centralized collection facility. Final segregation of solid Municipal waste (domestic and 4.2 Yes waste into biodegradable, non bio degradable, or commercial wastes) and inert fraction will be done in the centralized collection facility. The biodegradable waste will be treated in Organic Waste Converter (OWC) and manure will be used for green belt development. The non biodegradable recyclable waste will be handed over to authorized recyclers.

Horticultural wastes: Leaves, grass and vegetative residues are collected at the secured location such that it will not hinder daily activity schedule or washed away by the surface run-off causing choking of drains, etc. and will be separately disposed off along with biodegradable waste.

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

The spent oil will be stored in HDPE drums in Hazardous wastes (as per isolated covered facility. This will be handed No 4.3 Hazardous Waste Management over to the TNPCB authorized recyclers. Care

Rules ) will be taken to avoid the spills/leaks of spent oil from storage facility. 4.4 Other industrial process wastes No - 4.5 Surplus product No - Sewage sludge or other sludge STP sludge will be dried and used as the manure 4.6 Yes from effluent treatment for the gardening. The excavated earth and construction debris were Construction or demolition 4.7 No be used for backfilling and level rising within the wastes project site. All machinery / equipment were installed as per Redundant machinery or the requirement during construction and were 4.8 No equipment removed by the contractors once the construction work had been completed. Contaminated soils or other 4.9 No - materials 4.10 Agricultural wastes No - 4.11 Other solid wastes No -

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Details thereof (with approximate quantities S. Information/Checklist Yes/ /rates, wherever possible) with sources of No. confirmation No information data

Pollutants like particulate matters, CO, SO 2 and NOx will be released into the atmosphere due to the operation of DG sets and other machineries of Emissions from combustion of construction which use fossil fuels. However the 5.1 fossil fuels from stationary or Yes DG sets will be operated only during power cuts. mobile sources Also the use of Low Sulphur HSD (Sulphur content< 0.05%) and dispersion of the DG flue gases through stacks having heights as per CPCB norms will minimize the impacts. Emissions from production 5.2 No - processes Emissions from materials There will not be major emission from material 5.3 handling including storage or Yes handling, storage and transport. Necessary steps transport will be taken to control vehicular emissions. 5.4 Emissions from construction Yes Emissions from construction activities were

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

activities including plant and reduced by using low sulphur content HSD for equipment the machineries operated with fossil fuels and the accumulation of particulate matter in the atmosphere were suppressed by sprinkling of water in the dust prone areas at regular intervals. Dust or odors from handling of Dust at construction site was suppressed by 5.5 materials including Yes sprinkling water at site. On-site sanitation construction materials, sewage facilities were provided. and waste. Emissions from incineration of 5.6 No - waste Emissions from burning of 5.7 waste in open air (e.g. slash No - materials, construction debris) Emissions from any other 5.8 No - sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat: Details thereof (with approximate quantities S. Information/Checklist Yes/ /rates, wherever possible) with sources of No. confirmation No information data Noise control systems such as equipment From operation of equipment foundation pads, dampers, silencers and acoustic 6.1 e.g. engines, ventilation plant, Yes enclosures were used for individual units to crushers minimize the noise & vibration. From industrials or similar 6.2 No - processes There was no construction activity during night From construction or hours. Noise during the construction activities 6.3 No demolition was kept minimum by proper and regular maintenance of construction machineries. No blasting was involved. Isolated footing was 6.4 From blasting or piling No used as a foundation structure therefore there is no significant impact of noise and vibration. During construction activities, care was taken as From construction or 6.5 Yes explained above to reduce the impacts due to operational traffic movement of heavy vehicles. Necessary care was taken at the time of selection From lighting or cooling of equipment to minimize the noise or heat. 6.6 Yes systems Proper preventive maintenance was adopted during the operation stage.

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

6.7 From any other sources No -

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: Details thereof (with approximate quantities S. Information /Checklist Yes/ /rates, wherever possible) with sources of No. confirmation No information data No hazardous materials were used during the construction phase. During the operation phase, From handling, storage, use or 7.1 No the used oil generated from DG sets are stored in spillage of hazardous materials drums and disposed to TNPCB authorized waste oil recyclers. From discharge of sewage or The excess treated waste water from Sewage other effluents to water or the Treatment Plant will be disposed to 7.2 Yes land (expected mode and place Thiruverkadu / STP after utilized for of discharge) toilet flushing, gardening,. By deposition of pollutants 7.3 emitted to air into the land or No Nil into water 7.4 From any other sources No - Is there a risk of long term build up of pollutants in the 7.5 No - environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human or the environment Details thereof (with approximate quantities S. Information/Checklist Yes/ /rates, wherever possible) with sources of No. confirmation No information data The project activity does not impose any From explosions, spillages, significant threat of explosions, spillages, fires fires etc from storage, handling, etc. During construction, all the labors were 8.1 use or production of hazardous No provided with personal protective equipment substances (PPE). Training and awareness about the safety norms were provided to all supervisors and labors involved in construction activity. 8.2 From any other causes No - Could the project be affected by 8.3 No Nil natural disasters causing

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activates in the locality Details thereof (with approximate quantities S. Information/Checklist Yes/ /rates, wherever possible) with sources of No. confirmation No information data Lead to development of supporting facilities, ancillary development or development stimulated by the project which The project may trigger the development of could have impact on the supporting and ancillary facilities, and further environment e.g.: may lead to other developments. This will not • Supporting infrastructure 9.1 Yes lead to any potential negative impacts on (roads, power supply, waste environment. or wastewater treatment,

etc.)

• Housing development • Extractive industries • Supply industries • Other Lead to after use of the site, 9.2 which could have impact on the No Not Applicable environment Set a precedent for later 9.3 No Not Applicable developments Have cumulative effects due to proximity to other existing or 9.4 No Not Applicable planned projects with similar effects

III. ENVIRONMENT SENSITIVITY

S. Yes/ Aerial distances (within 15 km.) Proposed Areas No. No project location boundary Areas protected under 1. international conventions, No Nil national or local legislation for

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

their ecological, landscape, cultural or other related values Areas which are important or sensitive for ecological reasons – Wetlands, water courses or 2. No Nil other water bodies, coastal zone, biospheres. Mountains, forests Areas used by protected, important or sensitive species 3. of flora or fauna for breeding, No Nil nesting, foraging, resting, over wintering, migration Thiruverkadu lake - 1.4 Km Ambattur Lake - 3.5 Km Inland, coastal, marine or 4. Yes Red hills Lake - 8 Km underground waters - 9.3 Km Bay of Bengal - 15 km 5. State, National boundaries No - Routes or facilities used by the Project site is located 700m from Bengaluru - 6. public for access to recreation Yes Highway which is used by the public for or other tourist, pilgrim areas access to pilgrim centre. 7. Defense installations No Nil Densely populated or built-up The project itself lies within the densely 8. Yes area populated Chennai City. A C S Medical College – 0.3 Km Areas occupied by sensitive Apollo Nursing College – 0.5 Km man-made land uses (hospitals, Raja Rajeswari Engineering College – 1.5 Km 9. Yes schools, places of worship, Dawn School – 1.8 Km community facilities) The Holy Cross Matriculation Higher Secondary School – 4.1 Km Areas containing important, high quality or scarce resources (Groundwater / 10. No - surface water resources, forestry, agriculture, fisheries, tourism, minerals) Areas already subjected to pollution or environmental 11. No - damage. (where existing leg al standards are exceeded)

Eco Services India Pvt. Ltd, Chennai – 600032 Form – I for Residential Building Complex Dugar Housing Limited

Areas susceptible to natural hazard which could cause the project to present The area under study falls in Zone-III, according environmental problems to the Indian Standard Seismic Zoning Map. 12. No (earthquakes, subsidence, Suitable structure design norms, will be adopted landslides, erosion, flooding or while designing the structures. extreme or adverse climatic conditions) “I hereby undertake that the data and the information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any, to the project will be revoked at our risk and cost.”

Date: Place: Chennai Authorized Signatory

Eco Services India Pvt. Ltd, Chennai – 600032