COPYRIGHT AND CITATION CONSIDERATIONS FOR THIS THESIS/ DISSERTATION

o Attribution — You must give appropriate credit, provide a link to the license, and indicate if changes were made. You may do so in any reasonable manner, but not in any way that suggests the licensor endorses you or your use.

o NonCommercial — You may not use the material for commercial purposes.

o ShareAlike — If you remix, transform, or build upon the material, you must distribute your contributions under the same license as the original.

How to cite this thesis

Surname, Initial(s). (2012) Title of the thesis or dissertation. PhD. (Chemistry)/ M.Sc. (Physics)/ M.A. (Philosophy)/M.Com. (Finance) etc. [Unpublished]: University of Johannesburg. Retrieved from: https://ujcontent.uj.ac.za/vital/access/manager/Index?site_name=Research%20Output (Accessed: Date). Building the Grid: The Electrification of , 1882-2000

by

Mark Hackney

920208125

Submitted in fulfilment of the requirements for the degree

Master of Arts

in the

Department of Historical Studies

of the

Faculty of Humanities

at the

University of Johannesburg

supervised by

Dr S. Sparks

January 2018

ABSTRACT

The analysis of South Africa’s state-run enterprises, also known as the parastatals, has typically focused on the relationship between capital and labour, with especial attention to the ways in which the country’s racial segregation and capitalism created and entrenched a system of racial capitalism. These analyses have been influenced by Neo-Marxist trends in South African historiography, which intended to critique the overarching racial social engineering of apartheid through case studies of the systems and organisations that were created to foster the growth of industry and a “modern” South African state. Central to the establishment of secondary industries was the development of a national electrical grid that could provide the cheap electricity to drive industrial growth. Far from being a simple process of building and connecting a series of power stations, the Electricity Supply Commission had to engage and compete with existing suppliers, including municipalities and private companies, in order to construct a nation-wide, interconnected electrical grid. This research examines the process of building Escom’s National Grid from a ‘systems building’ perspective, which takes a non-deterministic view of how social factors and technology influence each other to construct a large, complex technological system. By introducing the systems building theoretical and methodological framework, this dissertation seeks to determine what factors, aside from the relationship between capital and labour, shaped the formation of the National Grid. TABLE OF CONTENTS

LIST OF ILLUSTRATIONS AND FIGURES ...... i ACKNOWLEDGEMENTS ...... ii ABBREVIATIONS AND TERMINOLOGY ...... iii INTRODUCTION ...... - 1 - 1. Literature Review ...... - 2 - 1.1 Systems, Systems Building, and Socially Constructed Artefacts...... - 6 - 1.2 The Apartheid State, Modernisation, and Technopolitics ...... - 14 - 2. Research Aims and Objectives ...... - 17 - 3. A Note on Units and Currency ...... - 18 - CHAPTER ONE – POWERING THE RAND: THE ELECTRIFICATION OF THE JOHANNESBURG MUNICIPALITY...... - 20 - 1. Gas Power, Failed Stations, and Trams: Early Electrification in Johannesburg ...... - 24 - 2. A Colonial Commission and a Colonial Law: Johannesburg, the Power Companies Commission, and the Transvaal Power Act of 1910 ...... - 29 - 3. Interwar Changes, Post-War Integrations: From the Electricity Act of 1922 Onwards ...... - 33 - CHAPTER TWO – “HARNESSING THE FALLS”: THE VICTORIA FALLS AND TRANSVAAL POWER COMPANY, 1906 – 1948 ...... - 42 - 1. “A Six Million Scheme”: Starting the Victoria Falls (and Transvaal) Power Company, 1906 – 1922 ...... - 45 - 2. Witbank’s Coal for Johannesburg’s Gold: The VFP after the 1922 Electricity Act, 1922 – 1948 ...... - 49 - 3. After Witbank: The Rand Extension Undertaking, Klip Power Station, and Vaal Power Station ...... - 54 - 4. Integration into the System: Escom’s Purchase of the VFP in 1948 ...... - 56 - CHAPTER THREE – RAILWAYS, COOKING RANGES, AND RURAL SUPPLIES: ELECTRICITY OUTSIDE OF MINING AND SECONDARY INDUSTRY ...... - 62 - 1. The Cape Railways: Electrification in and around Cape Town ...... - 67 - 2. Railways in Natal: The SAR&H, Escom, and the Colenso Power Station ...... - 68 - 3. The Cape Rural Supply System ...... - 72 - 4. Requesting Rural Electricity Supply: The Boere-Lig-en-Krag (Ko-Operatief) Beperk and the Electricity Control Board ...... - 74 - 5. Electricity and the Domestic Sphere: Appliance Hire-Purchase Plans and Advertising ...... - 77 - CHAPTER FOUR – “RESOURCE CONSTRAINTS AND THE NATIONAL INTEREST”: NUCLEAR POWER, BANTUSTANS, TOWNSHIPS, AND LINKING THE NATIONAL GRID, 1960 – 2000...... - 84 - 1. Completing the Interconnections: Connecting the National Grid ...... - 86 - 2. “Thousands of Experts”: Escom’s Nuclear Power Projects, 1960 – 1990 ...... - 92 - 3. Electrifying Non-White Areas: Electricity in Townships and Bantustans ...... - 99 - CHAPTER FIVE – THE NATIONAL GRID AS A HUGHESIAN LARGE TECHNOLOGICAL SYSTEM . - 102 - CONCLUSION ...... - 113 - 1. Conclusions on the Research Aims and Objectives ...... - 113 - 2. Limitations and Associated Recommendations for Future Research ...... - 114 - BIBLIOGRAPHY ...... - 116 - LIST OF ILLUSTRATIONS AND FIGURES

Figure 1 - Map of Escom's Areas of Supply in 1929 ...... - 9 - Figure 2 - Map of Escom's Areas of Supply in 1944 ...... - 10 - Figure 3 - Organisational Diagram of the VFP and Related Entities ...... - 44 - Figure 4 - Electricity Sales to Category of Consumer in 1930 ...... - 63 - Figure 5 - Electricity Sales to Category of Consumer in 1940 ...... - 64 - Figure 6 - Electricity Sales to Category of Consumer in 1950 ...... - 64 - Figure 7 - Traction Consumer Sales, 1927-2000 ...... - 65 - Figure 8 – Domestic and Streetlighting Sales, 1927-2000 ...... - 83 - Figure 9 - Total Electricity Sales per Annum, 1926-2000 ...... - 107 - Figure 10 - Map of 's Operational Power Stations, 2017 ...... - 111 -

i

ACKNOWLEDGEMENTS

Firstly, to my family. Thanks for the support, love, and willingness to operate an extra camera during archive visits over the past five years. We’ve laughed, cried, despaired together for years, but the fact that most of it has been laughter is fantastic. Mom, for the coffee and staying cool while I was freaking out about finding sources or meeting deadlines. Dad, for feeding the pigeons so that they would sit next to my window during the day and keep me from having to only stare at my computer screen. Graeme, for the countless episodes of our favourite animated shows that we’ve watched while eating or just taking a break – I think we’ve discovered that there really is a Simpsons quote for every situation!

To my exceedingly patient supervisor, Stephen Sparks, thank you for the nudges (and occasional shoves) in the right direction. The periodic emails with recommended articles and books have been a boon and the pithy replies to my queries and comments have always been greatly appreciated. I’m sure that “don’t worry, you’ll get there” has become something of a mantra for you since you first took me on as an MA student.

Likewise, to everyone at the Department of Historical Studies at UJ, your encouragement and support have been a constant reminder that I have been in the right place since the early days of my Honours degree.

Thanks to my old friends at Good News Church. Your love and encouragement over the years have been treasured. Of course, Deo Gratias.

ii

ABBREVIATIONS AND TERMINOLOGY

AC – Alternating Current, see DC AEB – Atomic Energy Board AEG – Allegemeine Elektricitäts-Gesellschaft ANC – African National Congress BLK – The Boere-Lig-en-Krag (Ko-Operatief) Beperk BSAC – British South Africa Company CGU – Central Generating Undertaking DC – Direct Current, see AC Distribution Power System – Any power system that operates at or below 132kV. ECB – Electricity Control Board, also referred to as “the Board” EdF - Électricité de France Escom – The Electricity Supply Commission, also known as the Commission. The abbreviated form taken from Afrikaans was Evkom (from Elektrisiteitsvoorsieningkommissie). After 1986, the organisation’s name was officially changed to Eskom IDC – Industrial Development Corporation MK – Umkhonto we Sizwe NP – National Party RCEW – Rand Central Electric Works Limited RMPS – Rand Mines Power Supply Company SAR&H – South African Railways and Harbour Administration SWAWEK – Suid-Wes Afrika Water en Elektrisiteitskorporasie (South-West Africa Water and Electricity Corporation) Transmission Power System – Any power system that operates above 132kV. Unit – The ECB specified that a unit of consumed electricity would be equivalent to a kilowatt- hour. 1 VFP – Between 1906 and 1909, the Victoria Falls Power Company. After 1909, the Victoria Falls and Transvaal Power Company. Watt (W) – A unit of power used to measure the quantity of generated electricity used. A watt is the amount of power that would move an object of one kilogram over a distance of one metre in one second. Increasing quantities are designated by a prefix to denote the size of the increase in increments of one thousand. For instance, a kilowatt (kW) is 1 000 W; a megawatt (MW) is 1 000 000 W; and a gigawatt (GW) is 1 000 000 000 W.2

1 "Fourth Sitting," National Archives of South Africa (SAB), MNW 634, ref. MM 2879/22. 2 U. S. Department of Commerce, The International System of Units (SI), National Bureau of Standards Special Publication 330 (Washington D.C.: U.S. Government Printing Office, 1977), p. 17; Bureau International du Poids et Mesures, The International System of Units (SI), 8th ed. (Sèvres Cedex: Organisation Intergouvernementale de la Convention du Mètre, 2014), pp. 7, 144, https://www.bipm.org/utils/common/pdf/si_brochure_8_en.pdf.

iii

INTRODUCTION

Electricity has long held a special role in human societies around the world – whether it is in the form of natural phenomena, like the spectacular discharge of lightning in a storm, or in the concerted efforts to control and direct electricity from storage batteries and power stations.

Especially in the religious sphere, socio-cultural myths endowed heroic figures with the ability to control phenomena associated with electrical discharges, from Zeus’ thunderbolts to Thor’s hammer that could destroy mountains with a single blow. 1 The importance of electricity, and the ability to control it, has also transferred across into contemporary popular culture, and these abilities are typically conferred upon the most powerful of characters.

Villains, such as the evil Emperor in The Return of the Jedi (1983), have the ability to create and direct bolts of electricity at will; while characters like the titular character in DC Comics’

Static are heroes who use their electric superpowers to fight against their nemeses. It is not only the use of electricity that has importance, but the lack of electricity has been used as a narrative device in popular films and video games. In Jurassic Park (1993), Close Encounters of the Third

Kind (1977), Super 8 (2011), and The Division (2016), the lack of electricity signifies a fracture in the structure of the manmade world in which these stories take place. In the case of Jurassic Park and The Division, the events that destroyed the local power supplies were as much creations of the characters in the story as the electrical grids, whereas Close Encounters of the Third Kind and

Super 8 both use disruptions in the electricity networks to show that unusual and potentially frightening events are about to occur to the story’s characters.

The underlying concept throughout these stories is that electricity has tremendous power, and it is only something or someone truly exceptional who has the ability to generate, control, disrupt, or restore the flow of current. However, the social importance of electricity does not come

1 "Thunderbolts and Lightning," Wellcome Collection, last modified March 29, 2017, accessed October 23, 2017, https://wellcomecollection.org/articles/thunderbolts-and-lightning; Hank Campbell, "Is Thor Mighty or Just Magic?," Science 2.0 (blog), October 14, 2013, http://www.science20.com/science_20/thor_mighty_or_just_magic- 104019.

- 1 - directly from pop culture and popular narratives. It is instead the oft unspoken importance of and reverence for electricity that informs the use of electricity in these stories. Likewise, the plots about the adventures of superheroes and interactions with extra-terrestrials reinforce the cultural and social importance of electricity.

When this cultural and social importance is considered alongside the advent of electricity generation and use in industry, business, and domestic contexts, it is easier to understand the role that electricity (as both a force of nature and as a tool) plays in developed and developing nations.

While this research does not aim to understand or discuss the use of electricity in the global context, or to discuss the civil rights aspects of twenty-first century electrification, it is important to remember that South Africa has had, and still has, communities that could be nominally characterised as either “developed” or “developing” within its borders. It is this heterogeneity that simultaneously reflects and is reflected by the establishment of the National Grid.

1. Literature Review

Central to this research are the works of Renfrew Christie and Thomas Hughes, two historians who wrote two foundational texts in the study of electrification, albeit in vastly different contexts. Christie wrote Electricity, Industry, and Class in South Africa, which studied the electrification of South Africa from the late 1800s onwards, while Hughes’ Networks of Power examined the process of electrification in North America and Europe between the 1880s and

1930s.2

The periods covered by the two authors are fairly similar, but their methodological considerations were vastly different. Christie’s book is a critique of how the electricity grid was established and maintained by the segregationist and apartheid governments in order to support

2 Renfrew Christie, Electricity, Industry and Class in South Africa (London: The Macmillan Press Ltd, 1984); Thomas P. Hughes, Networks of Power: Electrification in Western Society, 1880-1930 (Baltimore, MD: Johns Hopkins University Press, 1983).

- 2 - state capitalism. As such, it is heavily influenced by Marxist socioeconomic theory, and examines the role played by Escom in the functioning of South Africa’s racialised capitalist economy. 3 The core argument in Electricity, Industry and Class is that electricity and electrical technologies were used throughout the eras of segregation and apartheid to aid in the establishment and continuation of capitalist economic forms that had close ties to racial domination.

For the historians writing during the phase in which South African academic historiography was shifting from more top-down forms of Marxist analyses to radical revisionism, much of the discussion focused on the interplay between racial control and capitalism. More specifically,

Renfrew Christie was critical of Escom’s claims that electricity was being used in the “Spirit of

Progress.” This comes through clearly in Christie’s emphasis on the introduction of “labour- saving” mechanisation in South African mining and industry, particularly in relation to the effect that mechanisation had on black labour and the relationship between black and white labour in the country.

The same emphasis on the interaction between capital and the racial hegemony in South

Africa runs through Nancy Clark’s Manufacturing Apartheid, although Clark’s study looks at the broader history of the country’s parastatals, not just Escom.4 This look at the wider context helps to place Escom within the larger economic and social strategies behind the formation of the parastatals. The addition of socioeconomic factors, especially by introducing the analytical category of socioeconomic class into South African history, helped to highlight the ways in which racial issues had influenced the formation of the South African capitalist state. Christie’s main argument is also focused on how cheap labour made cheap electricity easily available, which facilitated interwar industrialisation.

3 A short, but clear, discussion of the main tenets and criticisms of Marxist theory in South African historiography is Michael MacDonald and Wilmot James, "The Hand on the Tiller: The Politics of State and Class in South Africa," Journal of Modern African Studies 31, no. 3 (September, 1993): pp. 387-405. For the placement of Marxist and radical histories in the larger context of South African historiographies, see Robert Ross, Anne Kelk Mager and Bill Nasson, "Introduction," in The Cambridge History of South Africa, vol. 2, eds. Robert Ross, Anne Kelk Mager and Bill Nasson (Cambridge: Cambridge University Press, 2012), pp. 1-16. 4 Nancy L. Clark, Manufacturing Apartheid: State Corporations in South Africa (New Haven, CT: Yale University Press, 1994).

- 3 -

In the context of South African historiography during the 1970s and 1980s, it was necessary to bring race and class to the fore in historical analyses to counterpoint the predominant state- endorsed narrative. For revisionist historians, it was essential to demonstrate how the statements of the benefits that a parastatal such as Escom claimed to offer to a wide group of South Africans were not reflected in reality. For instance, while townships were still denied access to national or municipal reticulation grids, visitors to the Hall of Achievement at Escom House in Johannesburg were greeted with a mural which claimed that the exhibits (and by extension, Escom) were

“dedicated to the ideal of cementing together by common endeavour for achievement all the people of South Africa regardless of race or creed into a brotherhood of mutual trust and goodwill…” 5

Neo-Marxist historians made a valuable contribution to the study of South African history by focusing on the interplay between race and socioeconomic class. However, the use of Marxist theories of political economy neglects some other important aspects of the development of technological systems. The idea of racial capitalism, for example, can be used to explain why the grid stayed outside of the large urban townships for decades and the impact of cheap electricity on the relations between black and white labour, but does little to help understand the choices that were made in the process of constructing the Koeberg Nuclear Power Plant in Cape Town. The intent in shifting analytic focus away from the labour-capital dynamic is to analyse how other socio-political forces affected these processes.

An examination of the construction of the Koeberg plant would necessarily refer to the relationship between Escom, the apartheid government, and the much-studied links between capital and labour but would also need to rely on discussions about the various reactor designs that could have been used; the decision to use nuclear power instead of coal; and the wider international context that affected South Africa’s nuclear ambitions. It is in the hopes of helping to expand the discussion on the growth of the South African National Grid that this research will include the theoretical and methodological tools introduced by Science and Technology Studies (STS).

5 Escom, Escom House (Johannesburg: Escom, 1936), p. 11.

- 4 -

Hughes’ Networks of Power offers an alternative methodological and theoretical stance to neo-Marxist political economy, one which emphasises the systemic nature of electrical grids. Not only are electrical grids systems, according to Hughes, but they are socially constructed systems.

Technology is not seen as a monolithic intrusion into society, nor does society dictate to system designers and builders what forms and uses technology should have. Instead, the flow of influence between technology and society works in both directions in the same way that classical Newtonian physics states that “for every action, there is an equal and opposite reaction”. The forces that society and technology exert upon each other may not always be equally balanced, as specific historical, sociological, political, economic, or material facets of a particular technology or particular society begin to affect these interactions.

The Marxian trend in South African studies of electricity persisted after the transition from apartheid to democracy as scholars worked to understand how the parastatal would fit into the post-apartheid context.6 Largely, these studies have a significant focus on the application of how changes in the organisation, as well as changes in wider societal contexts, have affected the parastatal, whether from the perspectives of socio-economic problems, environmental issues, or service delivery. These researchers have tended to ask why the grid was built, not how it was built.

That does not mean, however, that such research is without value in the context of this dissertation.

These researchers tend to look for underemphasised or ignored aspects of electrification that systems theory or STS researchers might not have studied, such as gender or environmental issues.7

Yet, it is the work done by researchers who have combined Marxian concerns about the nature of the relationships between state enterprise, capital, and labour with a focus on the themes

6 For instance, see David A. McDonald, ed. Electric Capitalism: Recolonising Africa on the Power Grid (Cape Town: HSRC Press, 2009). 7 For example, Wendy Annecke, "Still in the Shadows: Women and Gender Relations in the Electricity Sector in South Africa," in Electric Capitalism: Recolonising Africa on the Power Grid, ed. David A. McDonald (Cape Town: HRSC Press, 2009), pp. 288-320; David Fig, "A Price Too High: Nuclear ," in Electric Capitalism: Recolonising Africa on the Power Grid, ed. David A. McDonald (Cape Town: HSRC Press, 2009), pp. 180-201; Liz McDaid, "Renewable Energy: Harnessing the Power of Africa?," in Electric Capitalism: Recolonising Africa on the Power Grid, ed. David A. McDonald (Cape Town: HSRC Press, 2009), pp. 202-28.

- 5 - and methodologies of STS. While the influence of Marxist analysis is visible within these studies, such work has helped to refocus research on the country’s parastatals from heavily focusing on the interrelationships between labour and capital towards examining these relationships as one of many factors that worked in tandem to influence South African industrialisation. In the vein of the research undertaken by Faeeza Ballim, Stephen Sparks, and Antina von Schitzler on state-owned enterprise it is the intention of this dissertation to examine the growth of the South African National

Grid through an STS-focused approach.8

1.1 Systems, Systems Building, and Socially Constructed Artefacts

Within the field of STS research, the literature published on the Social Construction of

Technology (SCOT) and the Social History of Technology (SHOT) creates the possibility of filling in some of the gaps that remain in existing historical literature. The foundational text in this regard is the book The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology. 9 Based on the proceedings of a workshop held in the Netherlands at the University of Twente in 1987, the book brings together research on the history and sociology of technologies as diverse as Bakelite and Intercontinental Ballistic Missile guidance systems.

What makes this a valuable source in methodological terms is not just its primacy amongst the works on SCOT/SHOT research, but also that many of the ideas used to study the wide-range of technologies across a significant span of history are applicable to the study of South African

8 Faeeza Ballim. "The Evolution of Large Technical Systems in the Waterberg Coalfield of South Africa: From Apartheid to Democracy," (PhD Thesis, University of the Witwatersrand, 2017); Stephen John Sparks. "Apartheid Modern: South Africa's Oil from Coal Project and the History of a South African Company Town," (PhD Thesis, University of Michigan, 2012); Stephen Sparks, "Between 'Artificial Economics' and the 'Discipline of the Market': Sasol from Parastatal to Privatisation," Journal of Southern African Studies 42, no. 4 (2016): pp. 711-24; Antina von Schnitzler, "Citizenship Prepaid: Water, Calculability, and Techno-Politics in South Africa," Journal of Southern African Studies 34, no. 4 (2008): pp. 899-917; Antina von Schnitzler, "Traveling Technologies: Infrastructure, Ethical Regimes, and the Materiality of Politics in South Africa," Cultural Anthropology 28, no. 4 (November, 2013): pp. 670-93; Antina von Schnitzler, Democracy's Infrastructure: Techno-Politics and Protest after Apartheid (Princeton, NJ: Princeton University Press, 2016). 9 Wiebe E. Bijker, Thomas P. Hughes and Trevor Pinch, eds., The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology (Cambridge, MA: MIT Press, 2012).

- 6 - electrification. These chapters are also not only methodological discussions, but also integrate the discussion of methodology with relevant case studies.

For his part, Thomas Hughes did not only apply a systems-oriented view from an engineering perspective to his work on the history of electricity, but also brought some of the language of sociology into his analysis. This combination of engineering and sociological terms turns all the parts of a technological system into artefacts, whether they are technological, organisational, legislative, or infrastructural in nature. 10 Using the notion of artefacts in the study of a technological system emphasises the interaction between technology and society, rather than viewing systems as a series of impenetrable “black boxes.” Turning towards sociological understandings of technology helps to counteract the effects of technological determinism – if systems and their components are socially constructed, then the final form of a system cannot be said to have been set in place before the system is built.

The idea of “looking inside the black box” is a vital part of the sociological history of technology. In this metaphor, the “content” of the system’s artefacts contained within an opaque box. Before the advent of SCOT/SHOT studies, the designs and workings of systems and their artefacts were either marginalised or entirely ignored. By examining the way in which the artefacts are designed and constructed to work together in the overall system, it becomes possible to not only see the system as socially constructed, but to also see how the artefacts within the system are socially constructed. Ignoring the inner workings of a technological system tends to lead to linear models of development and construction, which suggests that the system did not also have the ability to fail. 11

10 Thomas P. Hughes, "The Evolution of Large Technological Systems," in The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology, eds. Wiebe E. Bijker, Thomas P. Hughes and Trevor Pinch (Cambridge, MA: MIT Press, 2012), p. 45. 11 Trevor J. Pinch and Wiebe E. Bijker, "The Social Construction of Facts and Artifacts: Or How the Sociology of Science and the Sociology of Technology Might Benefit Each Other," in The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology, eds. Wiebe E. Bijker, Thomas P. Hughes and Trevor Pinch (Cambridge, MA: MIT Press, 2012), pp. 15-18.

- 7 -

The notion that society and technology push and pull against each other can offer insight into the development of the electrical grid in South Africa. The process of building generating stations, transmission networks, substations, and distribution grids did not unfold smoothly from one side of the country to the other. The establishment of these systems and their associated subsystems did not take place in political, economic, or social vacuums, nor were these aspects of the South African nation-state left untouched by technological changes. This is best illustrated by

Hughes’ use of the term “reverse salient” to describe the growth of a system.

Adapted from military parlance, a reverse salient is any part of an advancing front that is still attached to the front, but that has fallen behind the rest of the advancing line. In technological terms, this occurs when the progress of building a new system is inhibited by social, economic, political, or technological factors, thereby preventing or restricting the future growth of the system.

An advancing front is an apt metaphor for the extension of large, infrastructure-intensive technological projects like the electrical grid, especially when looking at the maps that Escom published that showed the progress of the grid on a national scale. The first of these maps, from the 1929 Annual Report, simply shows the areas in which each of Escom’s Undertakings had been licenced to supply power, so each Undertaking is demarcated by a circle centred on the power station relevant to that Undertaking (Figure 1).

By the next time that such a map was published in 1944, these shapes had started to change as the areas of supply were being slowly extended (Figure 2). The outline of each area no longer took the form of a perfectly geometric shape but looked remarkably like the line of an advancing front on a military map. There are parts of each area that have extended further than others, while some regions closer to the centre of the Undertaking have yet to receive electricity. In particular, the area surrounding Cape Town has a series of branches growing out from the centre that showed how the electrification of the railways was helping to extend the grid.

- 8 -

Figure 1 - Map of Escom's Areas of Supply in 1929 12

12 Electricity Supply Commission, 1929 Annual Report, p. 4, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1929%20Annual%20Report.pdf.

- 9 -

Figure 2 - Map of Escom's Areas of Supply in 1944 13

13 Electricity Supply Commission, 1944 Annual Report, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1944%20Annual%20Report.pdf.

- 10 -

Consumers in the system need to be considered in relation to which artefact(s) they are consuming, and by the socioeconomic variables that affect their choice of artefacts. This helps to isolate which variables affect their behaviour in relation to the system, which is not particularly useful for understanding how the artefacts are created, invented, or developed. It is useful, however, for understanding the diffusion of these technologies throughout the system. 14 This is especially applicable to the study of issues such as the hire-purchase schemes that Escom and the municipalities established to encourage the use of domestic appliances (see Chapter Three).

The concept of relevant social groups is taken from Trevor Pinch and Wiebe Bijker’s chapter in The Social Construction of Technological Systems. 15 This idea was put forward as means of refining the understanding of how artefacts are rejected or adopted as newer technological forms are introduced to consumers. Pinch and Bijker state that by defining the social groups who are involved in producing, selling, or consuming the artefact, it can be determined which factors in the system are causing reverse salients and critical problems that need to be solved. 16

Pinch and Bijker studied the development of the bicycle and examined the multitude of ways in which the design changed as various social groups found their own reasons for accepting or rejecting specific design choices. Hughes wrote about the battle between the companies founded by George Westinghouse and Thomas Edison over whether electric distribution systems would use Alternating Current (AC) or Direct Current (DC). In the case studies of the bicycle and electrical grids, there were advantages and disadvantages inherent to the design of components or

14 Ruth Schwartz Cowan, "The Consumption Junction: A Proposal for Research Strategies in the Sociology of Technology," in The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology, eds. Wiebe E. Bijker, Thomas P. Hughes and Trevor Pinch (Cambridge, MA: MIT Press, 2012), pp. 253-6. 15 Pinch and Bijker, "Social Construction of Facts and Artifacts," in Bijker, Hughes, and Pinch, Social Construction of Technological Systems, pp. 11-44. 16 Pinch and Bijker, "Social Construction of Facts and Artifacts," in Bijker, Hughes, and Pinch, Social Construction of Technological Systems, pp. 22-28.

- 11 - subsystems that affected how the technology was perceived and/or utilised by various social groups. 17

Analysing the electrical grid as a system constructed and shaped through the interaction of society and technology widens the scope of the study to account for aspects external to the system itself, but that helped or hindered the construction of the system. Hughes states that a combination of systems analysis and sociological analysis can help identify the “geographical, economic, organisational, legislative, contingent historical, and entrepreneurial conditions” that shaped the design and use of cultural artefacts. 18

The work done by Charles Perrow on the nature of technological systems and accidents highlights the way that the interactions between the components in a system can produce unexpected, and even catastrophic, results. Perrow examined the accidents in specialised, complex systems in the fields of nuclear power, aeronautics, civil engineering, chemical and petrochemical manufacturing, and marine shipping to understand how these systems can still fail. According to

Perrow’s book, Normal Accidents: Living With High-Risk Technologies, it is the same complexity that these systems rely on to function correctly that also result in their failure.

Even components or entire subsystems that are introduced to make the overall system safer or more efficient add extra layers of complexity that increase the likelihood of something going wrong, and may be responsible for the accident in the first place.19 This theory about the way in which components and subsystems interact to produce unintended results can be seen in the later history of Escom, especially when the various regional undertakings established during Escom’s first four decades were first starting to show signs of interdependence in the early 1960s.

Related to the systems building perspective introduced by Hughes and the risk-based systems analysis of Perrow is the work done by David E. Nye on electrification in the United

17 Pinch and Bijker, "Social Construction of Facts and Artifacts," in Bijker, Hughes, and Pinch, Social Construction of Technological Systems, pp. 21-33; Hughes, Networks of Power, pp. 108-9. 18 Hughes, Networks of Power, p. 405. 19 Charles Perrow, Normal Accidents: Living With High Risk Technologies (Princeton, NJ: Princeton University Press, 1984).

- 12 -

States. In particular, the influence of Thomas Hughes and the sociological turn in the history of technology can be seen in Nye’s Electrifying America: Social Meanings of a New Technology, while When the Lights Went Out: A History of Blackouts in America reflects Perrow’s notion of the fragility of highly complex technological systems. 20

Electrifying America concerns the adoption of electrical technologies by Americans during roughly the same period that Hughes covered in Networks of Power but examines the processes by which electricity became rapidly integrated into Western lifestyles. Rather than looking how the electrical grid grew in the United States by looking at the people who built the grid, Nye examines how the technology was used and shaped by the consumers. These are both important points about the development of new technologies – Thomas Hughes wrote about how the electrical grid was created by relatively small groups of people who perceived the need for engineering, political, and financial expertise in their work, while David Nye wrote about how the technology was integrated into society to become such a fundamental part of modern lifestyles.

This point about the importance of electricity is continued in When the Lights Went Out.

Nye’s central argument is that electricity has become an intrinsic part of contemporary lifestyles in the developed world, yet it is simultaneously a part of life that few people give much thought to while the system is working. Electricity has become so much a part of modern conceptions of time that a blackout is seen as something exceptional. However, as Nye states, blackouts are typically viewed only as technical or engineering phenomena, not as something that is also a social phenomenon. 21

In this analysis, electricity and electrical grids become “infrastructure” in the sense of the term that is used by Paul Edwards. Edwards states that technological infrastructure cannot be viewed only as the physical aspect of a technological system, infrastructure must be seen as

20 David E. Nye, Electrifying America: Social Meanings of a New Technology (Cambridge, MA: MIT Press, 1990); David E. Nye, When the Lights Went Out: A History of Blackouts in America (Cambridge, MA: MIT Press, 2010). 21 Nye, When the Lights Went Out: A History of Blackouts in America, pp. 1-6.

- 13 - simultaneously technical and social. There is a distinct separation between notions of infrastructure in the developed and developing world, since technological implementation into society needs to be reliable and stable if it is to reach the point where people no longer give it frequent thought. 22

1.2 The Apartheid State, Modernisation, and Technopolitics

There seemed to be an inherent contradiction in the apartheid government’s modernising goals and the concerted efforts to keep the country as racially segregated as possible, but the formation of a technologically “modern” state formed a large part of government policy. 23 This modernising drive was exemplified in Escom’s frequent statements that electrification was being done under the “Spirit of Progress,” so much so that the concept makes an anthropomorphised appearance in the organisation’s official history, A Symphony of Power. 24 While the book serves as a starting point for finding out the essential basic information about the parastatal, such as constructing a chronology of important events, it also tries to present the parastatal as a nominally progressive and positive organisation.

The theme of modernising the public and private spheres of South African lifestyles is tied to the theme of progress, despite the fact that these processes of modernisation and progress were unfolding rather unevenly across the country. Problematically, the dual themes of progress and modernity have often been accompanied by the goals implicit in the drive to “civilise” colonial and former colonial nations. In portraying Escom, and in later sections Eskom, as the group of people who brought light and technology to dispel the darkness, the book links back to the idea of lighting up “darkest Africa,” even if these connotations are subconscious.

22 Paul N. Edwards, "Infrastructure and Modernity: Force, Time, and Social Organization in the History of Sociotechnical Systems," in Modernity and Technology, eds. Thomas J. Misa, Philip Brey and Andrew Feenberg (Cambridge, MA: MIT Press, 2003), pp. 186-225. 23 Deborah Posel, "The Apartheid Project, 1948-1970," in The Cambridge History of South Africa, vol. 2, eds. Robert Ross, Anne Kelk Mager and Bill Nasson (Cambridge: Cambridge University Press, 2012), pp. 319-68. 24 S. R. Conradie and L. J. M. Messerschmidt, A Symphony of Power: The Eskom Story (Johannesburg: Chris van Rensburg Publications, 2000).

- 14 -

The overall tone of the book is one of harmonious interaction between the parts of the system, a tone that sometimes confers a pseudo-religious importance on the organisation’s work.

The opening passage describes the narrative as the story of an organisation “…that says: let there be light where there was darkness.” 25 This heavy-handed allusion to a biblical passage ties back to the theme of exceptionalism in social understandings of electricity – if electricity is exceptional, then the use of electrical illumination must also be exceptional. By making the organisation capable of bringing light to a place where there was only darkness before, Eskom becomes the organisation that technologically triumphed over the natural order.

The final chapter in the book takes the form of a semi-Dickensian tale about the conversation between a fictional future manager of “uEskom,” the Spirit of Progress, and the Spirit of Ubuntu. The two spirits take the new head of uEskom through the organisation’s history to celebrate the achievements of men such as Hendrik van der Bijl, while ignoring or glossing over controversial or difficult issues that the parastatal has faced in the past. 26

Renfrew Christie’s counter-argument is that the apartheid system used electricity for the benefit of white South Africans, and that the notion of technological progress was an effective cover for the state’s broader goal of maintaining the racial status quo. While he admits that there were some benefits to electrification, Christie’s point is that the new technology was largely used by the government and industrialists to further marginalise black labour. 27 This is related to the function of all systems as problem-solving or goal-oriented organisations, especially when they are regarded as solving problems specifically for the system designers or the consumers. 28 In the

South African context, the electrical grid was designed to offer maximum availability to mining, secondary industry, and white residential areas.

25 Conradie and Messerschmidt, Symphony of Power, p. 7. 26 Conradie and Messerschmidt, Symphony of Power, pp. 349-65. 27 Christie, Electricity, Industry and Class, p. 2. 28 Hughes, "Evolution of Large Technical Systems," in Bijker, Hughes, and Pinch, Social Construction of Technological Systems, p. 47.

- 15 -

The intersection between the post-1948 government’s politics and modernising plans created a socio-political system of “technopolitics” that proved to be useful for both enforcing apartheid norms and for generating prestige for the state. The state’s interactions with other nations on the global stage, as well as the government’s domestic affairs, was based on the formation of white Afrikaner ethnic identity around a set of values that was traced back to European and African origins. Gabrielle Hecht and Paul Edwards argue that this brand of South African exceptionalism was instrumental in the choices and policies made regarding large-scale technological projects.29

This contributes to the “technological style” of the system – the way in which local and regional socio-political factors influence the shape and growth of the overall system. 30

The technopolitics of electricity supply by Eskom have been examined recently by Sylvy

Jaglin and Alain Dubresson in Eskom: Electricity and Technopolitics in South Africa, but this book has a much more contemporary focus than this dissertation.31 In this book, the discussion of events before the late-1980s is restricted to fewer than fifteen pages in the first chapter, and the later chapters are examinations of post-apartheid policies on the supply of electricity after 1994. This is helpful in understanding the effect of policy changes, such as a shift away from racial capitalism, have affected the parastatal since the mid-1990s. However, this contemporary focus does little to help explain how Eskom had become the largest supplier of electricity to South Africans at the point of the apartheid/democracy changeover.

Deborah Posel warns of the dangers inherent in characterising the apartheid state as founded solely on the basis of racial segregation, stating that by focusing only the state’s racial ideology, historians run the risk of creating a superficial and inaccurate picture of the nature of the state. Racial politics were an exceptionally large part of government policy between 1948 and

29 Paul N. Edwards and Gabrielle Hecht, "History and the Technopolitics of Identity: The Case of Apartheid South Africa," Journal of Southern African Studies 36, no. 3 (September, 2010): pp. 619-39. 30 Hughes, "Evolution of Large Technical Systems," in Bijker, Hughes, and Pinch, Social Construction of Technological Systems, pp. 61-64. 31 Sylvy Jaglin and Alain Dubresson, Eskom: Electricity and Technopolitics in South Africa (Cape Town: UCT Press, 2016), translated from Électricité et pouvoir en Afrique du Sud (Paris: Éditions Karthala, 2015).

- 16 -

1994, but it is also important to remember that the history of racially delineated segregation goes further back in time than 1948. 32 This makes is important to not only concentrate on the racial aspects of the government’s policy regarding electrification, but to also consider economic and socio-political factors. There were certainly overlaps between the racial, political, social, and economic aspects of electrification, but the focus should be split between these facets, rather than emphasising only a single factor.

In expanding the focus to include a larger range of socio-economic factors, there is a subtle shift from using the state-owned enterprises as case studies in critiques of larger social issues to examining these organisations themselves. This allows for such research to show how state-owned enterprise was also instrumental in other key aspects of South African social and political life. For instance, Saul Dubow has written about the expansion of the railways in South Africa as both a unifying force and a forum for promoting the ideals associated with modernity. Such an analysis helps to portray the parastatals as organisations that not only reflected the existing status quo, but that were used for political purposes other than entrenching and reinforcing racial segregation.33

2. Research Aims and Objectives

As already stated above, the question of why the South African National Grid was established as already been fairly well answered. Instead, the aim of this dissertation is to examine how the grid was established, moving beyond the emphasis on labour in the neo-Marxist revisionist literature. The answers to these two questions are closely linked – the reasons for electrification will have an impact on the way in which the electrical grid could (or could not) grow and change over time. However, the emphasis placed on the final uses of electricity in South Africa during the

32 Posel, "Apartheid Project," in Cambridge History of South Africa, vol. 2, pp. 319-20; Harold Wolpe, "Capitalism and Cheap Labour-Power in South Africa: From Segregation to Apartheid," Economy and Society 1, no. 4 (1972): pp. 425-6. 33 Saul Dubow, A Commonwealth of Knowledge: Science, Sensibility, and White South Africa 1820-2000 (Oxford: Oxford University Press, 2006), pp 180-82.

- 17 - twentieth century has restricted much of the discussion to the ways in which technological change was driven and used by the government to enforce the continuation of racial segregation.

It is true that the eras of segregation and apartheid both relied on the use of race as a key descriptor for the formation of policy. However, South Africa should not be viewed in isolation throughout the period under discussion. The country was part of a larger global network of trade, politics, and ideas that had an effect on the course of events. There were times in which international politics and alliances played a role in the process of electrification, just as there were times when local politics and alliances played their role.

Keeping the existing literature on the electrification of South Africa in mind, supplemented by the scholarship on the social construction of technology and technopolitics discussed above, the following themes are points of interest:

• The development of the South African National Grid was neither teleological nor entirely

uninterrupted by other economic and social factors. What were these “reverse salients”

that affected electrification?

• How were the reverse salients corrected, whether by consumers, municipalities, private

companies, or national government intervention?

• Since much of the focus in the past has been on urban electrification, how did rural

electrification proceed?

3. A Note on Units and Currency

In the primary and secondary sources on electricity, a variety of units of measurement and currencies have been used, which are usually specific to a period in time. The standard unit of measurement for generated and sold electricity throughout South Africa has always been derived from the watt, which is the amount of energy required to move a one-kilogram mass over a distance

- 18 - of one metre in one second. 34 All larger measurements are denoted by an added prefix that shows whether thousands or millions of watts are being measured. One thousand watts is a kilowatt (kW), while a million watts is a megawatt (MW).

In cases where physical quantities are being measured, such as the amount of coal consumed by a power station, the units used in the original source have been used throughout, rather than converting such measurements. Where the original sources have used imperial values for physical measurements, the conversion into metric units is specified in parentheses after the original quantity. Conversions have used the conversion factors specified by the National Institute of Standards and Technology at the U.S. Department of Commerce. 35

Similarly, monetary quantities are also given in the original denomination, but are not converted into contemporary values. Unlike the units used for physical quantities and measurements, currency values change constantly, and are capable of changing rapidly. This makes any currency conversions outdated within days, or even hours, of the conversion being made. This issue could be worked around by stating the date on which the conversion was valid, thereby allowing for future conversions to be made based on records of currency changes.

However, this does introduce a second problem with converting currencies, namely the issue of adjusting values to compensate for fluctuations due to inflation and the buying power of the currency. For these reasons, all monetary amounts are given in the original denomination and are left unconverted.

In all cases where numerical amounts have decimals, as would be the case for most currencies and where units have been converted, a decimal point has been used instead of the usual

South African practice of using decimal commas.

34 U. S. Department of Commerce, The International System of Units (SI), p. 17; Bureau International du Poids et Mesures, The International System of Units (SI), p. 144. 35 Ambler Thompson and Barry N. Taylor, Guide for the Use of the International System of Units (SI), NIST Special Publication 811 (Gaithersburg, MD: National Institute of Standards and Technology, 2008), pp. 40-69, http://ws680.nist.gov/publication/get_pdf.cfm?pub_id=200349.

- 19 -

CHAPTER ONE – POWERING THE RAND: THE ELECTRIFICATION OF THE JOHANNESBURG MUNICIPALITY

The Electricity Act of 1922 brought much-needed standardisation and centralised control to the electricity industry across South Africa, but the legislation arrived at an awkward time in the country’s electrification process. Electrification had started in the 1880s, but the growth of local grids had been sporadic and uneven. Industrial concerns, mines, and municipalities operated highly localised and low capacity systems. As the needs of secondary industry and mining groups increased, electricity was becoming more widespread, but the lack of central control meant that design decisions were left up to each company or organisation, which resulted in an overall inability to interconnect these localised networks.

The Electricity Control Board’s enforcement of standards was vital for the growth of the

National Grid – standardisation ensures that any generating station can provide power to any portion of the grid without the added engineering challenges of changing voltages or converting between frequencies. The head-start that the municipal councils around the country had in generating and supplying electricity means that the story of South Africa’s municipal suppliers is closely linked to the 1922 Electricity Act and the ensuing development of a national electricity network.

Before the Electricity Bill was enacted by the Union’s Parliament in late 1922, most of the country’s electricity was generated by municipalities and private companies. 36 With these disjointed grids spread in clusters across urban areas, factors such as the frequency and voltage of the electricity supply were determined by the equipment used in the generating facilities – if one area of supply suffered an outage, it was extremely complicated to obtain temporary supply from other areas until local faults were identified and fixed. In emergencies, such as when the

Johannesburg Municipality’s power station was struck by lightning in February 1922, residents

36 Conradie and Messerschmidt, Symphony of Power, p. 13.

- 20 - were asked to reduce the demand on the station for “two or three days” while maintenance engineers performed emergency repairs to the station. 37

Although this chapter does not deal directly with the process of standardisation across the

National Grid, the establishment of such a country-wide system requires centralised control over laws, generating capability, and infrastructure. The fragmented systems of municipal suppliers were not conducive to standardisation, interconnection, or improved service delivery. As electricity consumers found out in the early 1900s, relying on municipal supply in a non- standardised grid could result in unexpected inconveniences and financial costs when the municipality decided to upgrade or replace their generating station. 38

Technical standardisation is often seen as a simplification of the processes, materials, and working methodologies used to manufacture products or services, but the implementation of standards also has the potential to add extra layers of technical difficulty to the working process.39

In the case of electrification, standards have greater potential to simplify the generation, transmission, and distribution of electricity than to add complexity. Unified voltages, frequencies, and materials allow for more cost-efficient operation of generating plants and distribution networks. Logistically, consolidated control also offers technicians and engineers easier access to stockpiles of components, thereby improving worker efficiency and working costs. Despite these advantages, it is possible that regulation of the industry adds extra layers of complexity to the process, even if it is only because the system’s complexity grows with each new addition to the overall network.

Engineering entrepreneurs found that during the electrification of the United States imposing standards and specifications onto a system that already has some developmental

37 "Power Station Trouble: Lightning Causes a "Surge"," Rand Daily Mail, February 22, 1921. 38 X. Y. Z. [pseud.], "The New Lighting Plant," The Star, March 3, 1906; "Lighting Regulations," Rand Daily Mail, May 11, 1906; "The Electric Light: Increase of Voltage," Rand Daily Mail, May 11, 1906; Property Owner [pseud.], "Electric Installation: A Strong Protest," Rand Daily Mail, May 11, 1906; J. R. C. [pseud.], "Lighting Regulations," Rand Daily Mail, May 17, 1906. 39 Amy Slaton and Janet Abbate, "The Hidden Lives of Standards: Technical Prescriptions and the Transformation of Work in America," in Technologies of Power: Essays in Honor of Thomas Parke Hughes and Agatha Chipley Hughes, eds. Michael Thad Allen and Gabrielle Hecht (Cambridge, MA: MIT Press, 2001), pp. 94- 95.

- 21 - momentum can introduce extra complications that engineers and investors did not foresee. In the case of the United States, the choice between Alternating Current and Direct Current distribution, as eschewed by George Westinghouse and Thomas Edison respectively, resulted in a “War of

Currents” between the two engineering magnates. The battle for supremacy in the American electrical industry was characterised by grandstanding and fearmongering as engineers and entrepreneurs fought to convince decision-makers and consumers alike of the relative merits of their systems. 40 Even though the highly publicised Westinghouse-Edison battles reached more grotesque and controversial heights than the arguments about South African electrification, the introduction of standards and legislation offers a glimpse into the nature of electricity generation and consumption during the embryonic stages of the national South African grid. 41

The process of drafting and enacting legislation also helps to show how the municipalities viewed themselves in relation to their ratepayers, as well as showing how they viewed themselves in relation to larger governmental groups at the provincial and national level. For many of

Johannesburg’s residents, the issue of electrification centred on the municipal government’s responsibility to provide a certain level of service delivery to ratepayers. For some of the city’s residents, however, electrical service delivery was not so straightforward. David Nye wrote that people in the United States at the start of the twentieth century saw electricity as “…a political issue, an element of spectacle, a means of transportation, a motive force, and a source of profit.”42

Even though Nye was writing about American electrification, it is also possible to see these themes appearing in the electrification of Johannesburg.

40 Tom McNichol, AC/DC: The Savage Tale of the First Standards War (San Francisco, CA: Jossey-Bass, 2006), pp 77-94. 41 Hughes, Networks of Power, pp. 108-9; Jennifer L. Lieberman, Power Lines: Electricity in American Life and Letters, 1882-1952 (Cambridge, MA: MIT Press, 2017), pp 51-90; Jürgen Martschukat, ""The Art of Killing by Electricity": The Sublime and the Electric Chair," Journal of American History 89, no. 3 (December, 2002): pp. 900-921; Roger Neustadter, "The "Deadly Current": The Death Penalty in the Industrial Age," Journal of American Culture 12, no. 3 (September, 1989): pp. 79-87; Terry S. Reynolds and Theodore Bernstein, "Edison and "the Chair"," IEEE Technology and Society Magazine 8, no. 1 (March, 1989): pp. 19-28 describe the macabre history behind one of the most infamous attempts to discredit Westinghouse’s use of Alternating Current. 42 Nye, Electrifying America, p. 138.

- 22 -

Johannesburg serves as a prime candidate for the study of municipal power supply in South

Africa. Aside from the city’s relative prominence in South African history during the twentieth century, the residents of early Johannesburg were amongst the first city-dwellers in Southern

Africa to receive electricity through municipal supply. The first South African town to install electric streetlighting had been the mining town of Kimberley in February 1882. The attempt to illuminate the town’s streets had been a disappointing failure, since many of the streetlights had been damaged en route to Kimberley. The lights underperformed so poorly that they were said to be no brighter than “a glowing coal”.43 Johannesburg’s status as an early adopter of the relatively new generation and distribution technologies means that it is possible to show how changes in political, technological, and social factors affected – and were affected by – the process of electrifying the city.

Running throughout the history of Johannesburg’s electrification are the connected themes of municipal socialism and municipal ownership of infrastructure. The municipal socialism seen in Johannesburg was similar to that which Daniel Rodgers wrote about in his study of the transfer of ideas between the United States and Western Europe at the end of the nineteenth century. It is a form of socialism which Rodgers calls “…the socialism of the business classes.”44 In

Johannesburg, as was the case throughout South Africa, municipal socialism was affected less by social class than by race, but it was crucial to the ways in which municipal, provincial, and national governments interacted.

Tied to this is the idea of municipal ownership, which Rodgers called the

“municipalisation” of infrastructure – the best way in which municipalities could offer services to their ratepayers, while still ensuring that there was a certain level of “rate relief,” was to own the infrastructure through which the services were delivered. In some cases, especially during the interwar period, the Johannesburg Municipality had to choose between allowing other electricity

43 Christie, Electricity, Industry and Class, pp. 5-6; Conradie and Messerschmidt, Symphony of Power, p. 13. 44 Daniel T. Rodgers, Atlantic Crossings: Social Politics in a Progressive Age (Cambridge, MA: Belknap Press, 2000), p. 123.

- 23 - distributors to supply the city’s residents and forgoing the municipal commitment to providing electricity.

1. Gas Power, Failed Stations, and Trams: Early Electrification in Johannesburg

In June 1893, eleven years after the first streetlamps were turned on in Kimberley, and four years before Johannesburg was granted official municipal status, a gas turbine at the municipally- owned station in President Street was used to power the town’s electric streetlamps. 45 The streetlights in Johannesburg were less of an outright anti-climax than those in Kimberley, but there were still complaints about supply shortages, poor quality service delivery, and changes that accompanied the replacement of existing systems. 46 These problems plagued the municipal power supply for more than the first decade after the station at President Street went online, with complaints about the quality of service delivery extending well past the turn of the century. In

1903, ten years after the municipality began delivering electricity, staff at the Post Office reported that they needed to deploy oil-burning lanterns to supplement the electric lights, since they found that the under-performing lighting system made their work extremely difficult.47

There were several factors that played a role in the problems encountered by the municipality in their early electrification efforts. Firstly, the Anglo-Boer War between 1899 and

1902 interfered with all industry and supporting services across the Transvaal. Not only were the usual wartime shortages of personnel, raw materials, and spare parts to blame, but sabotage by

Boer commandos at the New Kleinfontein and Brakpan stations in December 1900 and January

1901 affected the ability of the respective mining companies to supply their consumers. 48 The sabotage at these two power stations would not have directly impacted the growth of the municipal grid, but output at the Witwatersrand’s gold mines had already been curtailed by conditions

45 John R. Shorten, The Johannesburg Saga (Johannesburg: John R. Shorten, 1979), p. 599. for the President Street station. Charles van Onselen, New Babylon, New Nineveh: Everyday Life on the Witwatersrand 1886 - 1914 (Johannesburg: Jonathan Ball Publishers, 2001), p. 17. for the granting of municipal status 46 "Public Lighting," Transvaal Leader, July 17, 1902. 47 "Untitled," Transvaal Leader, August 24, 1903. 48 Christie, Electricity, Industry and Class, p. 13; Conradie and Messerschmidt, Symphony of Power, p. 24.

- 24 - imposed by the outbreak of war. The welfare of the city was closely tied to that of the gold mines, making any decrease in mining production a potentially serious economic blow to the city.

Secondly, the disjointed design of the grid made the system relatively inefficient. Not only was electricity generated and distributed from smaller, less productive stations, but the municipality had established multiple grids that acted as subsystems within the larger municipal electricity system. These three subsystems provided electricity to different areas of the city for different purposes and used a variety of technical standards that kept each “mini-grid” separated from the others in the overall system. The layout of the grid was further complicated by the choice to separate the two mini-grids that ran to non-tramway customers into separate voltages, depending on whether the electricity was used for lighting or other purposes. These three subsystems split electricity distribution amongst municipal customers as follows:

• The electric tramways ran on their own system that used 575 V Direct Current;

• Inner city consumers received 460 V Direct Current electricity, with a step-down system

converting the power to 230 V for lighting purposes;

• Suburban consumers received 400 V Alternating Current electricity, with step-down

transformers converting to 200 V for lighting consumers. 49

In July 1904, the Municipal Council, acting on advice given by the engineering firm of

Mordey and Dawbarn, decided to upgrade the President Street Power Station with eight gas- powered internal combustion engines. The generators would be installed by Stewart and Company, who would also be responsible for running the plant during its first year of operations. Most of the reasons for the gas-powered plant’s failure were evident from before the start of the project, but the council and both engineering firms that they hired ignore these warning signs. Most problematically, the gas engines were relatively unproven in large systems like the Johannesburg municipal power system, and the tender specified that the large generators would only be tested

49 J. H. Dobson, "The Distribution Plant of the Johannesburg Municipal Electric Supply System," Transactions of the South African Institute of Electrical Engineers 6, (November, 1915): p. 280.

- 25 - for the first time after they were installed at President Street. The engines had also been designed to use gas produced as a by-product of processing anthracite, but the Johannesburg engines would use gas manufactured from bituminous coal, 50 which increased the unreliability of the generating equipment. 51

The delays involved in the installation of the gas engines and the equipment required to produce the gas from coal meant that the first engine at the upgraded power station only started up for the first time on May 1, 1906. 52 In the meantime, the city had continued to use the older steam- powered generators at the President Street Power Station, while also bringing extra capacity in from Bertrams and Brakpan power stations. 53

These problems in upgrading the power station were compounded by the decision to build the three separate subsystems that supplied different areas of the city. The largest problem arising from the implementation of the subsystems was the change in voltages that would accompany the completion of the gas-powered equipment, since voltage changes would require changes in the fixtures used by existing consumers. The municipal council’s position was that the voltage change would be made for economic reasons, since the same generators could be used to power residential and business premises, while still putting enough power into the system to run the tramways. 54

The situation was exacerbated even further by the decision on the part of the Rand’s insurance firms to insist that their policyholders would need to have their premises inspected, and possibly rewired. This decision was made after a spate of electrical fires in Johannesburg had been shown to be the result of poor quality work when the original wiring was done, but the combination of the decisions made by the municipality and the insurers arrived at an inopportune time for their

50 Bituminous coal is a form of coal that becomes a “cohesive, binding, sticky mass” when it is heated. It produces more energy when burned than anthracites, and contains high levels of volatile matter, which is suitable for coal-to-gas production, H. Wayne Beaty and Donald G. Fink, Standard Handbook for Electrical Engineers, 16th ed. (New York, NY: McGraw-Hill Professional, 2013), chap. 5. 51 Shorten, Johannesburg Saga, pp. 600-601. 52 Shorten, Johannesburg Saga, p. 602. 53 "The New Lighting Plant," The Star, March 3, 1906. 54 "The Electric Light: Increase of Voltage," Rand Daily Mail, May 11, 1906.

- 26 - customers. To the municipality and insurance firms, the changes were caused by two related, but distinctly separate issues – one was a pragmatic necessity arising from the much-needed upgrades, one was an issue of safety. To many of the ratepayers and policyholders, however, the two issues were part of one larger, overriding concern – the short-term economic effects of replacing equipment that had already been installed. 55

The concerns over poor workmanship were not new to the residents of Johannesburg. Even before the insurance companies noticed the correlations between poor interconnections and fire hazards, there were complaints from ratepayers and electrical tradesmen alike on the matter of electrical work. These earlier moments in which the issue had been raised were less related to the safety aspect, and more related to race. Writing under the pseudonym of “Linesman” in July 1902, a resident suggested that the city should ensure that all electrical work should be done by qualified workers with the best quality tools and materials and questioned why the municipality placed “too much faith in natives.”56

Likewise, laypeople expressed their discontent with the town council’s policy on allowing black labourers to work in semi-skilled positions for the Electricity Department – a resident wrote that “the state of the electrical trade is not very bright just now, and if natives are to do the work I don’t see any chance of it improving…” after seeing a team of workers where the white supervisors allowed black labourers to work on the electrical installation.57 A Belgrave resident bemoaned the lack of white supervisors overseeing the streetlight repairs in the area, stating that they had only seen black workers performing the work. 58 The same racial themes continued in 1910, when the

Power Companies Commission in the Transvaal was investigating the state of electrification in the

Colony, and persisted even after the Power Companies Commission had filed its report. In August

1913, a severe storm had hit Johannesburg, resulting in difficulties throughout the Municipality in

55 "The New Lighting Plant," The Star, March 3, 1906; "Electric Installation: A Strong Protest," Rand Daily Mail, May 11, 1906; "Lighting Regulations," Rand Daily Mail, May 11, 1906; "The Electric Light: Increase of Voltage," Rand Daily Mail, May 11, 1906. 56 "Linesmen and Reform," Transvaal Leader, July 25, 1902. 57 F. E. Oliver, "The Electrical Trade," The Star, September 21, 1906. 58 "Belgravia and Lights," The Star, August 28, 1906.

- 27 - keeping services running. In compensation for their extra work, a local resident suggested that the entire town should give thanks to the staff who had kept the station operational during the storm, taking pains to mention that every white member of staff “…from the chief downwards…” should receive bonus cheques equivalent to a month’s pay. 59

Once the initial installation problems had been solved, the gas-powered engines were a remarkable failure – the first generator was started on May 1, 1906 and the plant seemed to have overcome the initial difficulties that had so drastically delayed the construction and installation phases of the upgrades, but the untested technology in the power plant soon started becoming increasingly unreliable. During 1906, the station’s chief engineer, J. A. McMullen, resigned, claiming that conflict between the general manager and the station’s departmental supervisors was inhibiting the efficiency and productivity of the operating staff. 60

The plant was further hobbled when a backfiring engine destroyed two of the eight gas engines in March 1907, thereby removing a quarter of the power plant’s capacity. 61 Workers at the municipal station also started to complain that working conditions in the vicinity of the gas engines had started to deteriorate once all engines were running, particularly after the engines started to develop chronic leakages. White workers who lodged complaints about the continual health hazards presented by the gas leaks were fired and promptly replaced with black workers, one of whom was killed in an on-site accident. 62 The combination of lowered total capacity, undependable equipment, and underperforming components caused Stewart and Company to end their contract with the municipality on May 15, 1907, barely a year after the first generator had been started. The gas-powered plant was scrapped after the city’s council voted against taking over the operations from Stewart and Company on June 30, 1907. 63

59 Citizen [pseud.], "Public Indebtedness," The Star, August 15, 1913. 60 J. A. McMullen, "Those Gas Engines: Why McMullen Resigned," Rand Daily Mail, September 4, 1906. 61 Shorten, Johannesburg Saga, p. 602. gives March 28 as the date of the explosion, but Christie, Electricity, Industry and Class, p. 33. gives an alternative date of March 26. 62 Christie, Electricity, Industry and Class, pp. 33-34. 63 Shorten, Johannesburg Saga, pp. 600-602; Christie, Electricity, Industry and Class, p. 34.

- 28 -

After the problems with the gas-powered plant had become evident, the city’s residents began to question the decision to use the untested technology in the municipality’s power plant.

Following the failure of the gas-powered plant, the municipality was facing a critical shortage of electricity. The municipality approached privately-owned companies, which mostly provided electricity for the city’s mines, to negotiate contracts for emergency electricity supplies. The city also contracted with the engineering firm of Reunert and Lenz to replace the defunct gas engines with steam-powered engines.

2. A Colonial Commission and a Colonial Law: Johannesburg, the Power Companies Commission, and the Transvaal Power Act of 1910

In 1909, the Earl of Selbourne, in his capacity as Governor of the Transvaal Colony, appointed the Commission of Inquiry into the Power Companies to investigate the extent of electrification in the region. The four members of the Commission were charged with determining the effects of large-scale, centralised electricity generation on the mining industry; secondary manufacturing industries; agriculture; the Central South African Railways (CSAR); labour; and

“the Country generally”. 64

The Commission found that the four largest electricity undertakings in the Transvaal were the Municipalities of Pretoria and Johannesburg, the Rand Mines Power Supply Company

(RMPS), and the Victoria Falls and Transvaal Power Company (VFP). The section on the

Johannesburg Municipal power supply is perhaps the shortest in the Commission’s report, managing to reach a total of five sentences that briefly mention the original concession granted to the Johannesburg Gas Company in 1889; the deals between the city and private suppliers to obtain emergency supplies of electricity during shortfalls; and the installed and forecasted generating

64 "Report of the Power Companies Commission," National Archives of South Africa (TAB), CT 155, ref. T39/56.

- 29 - station capacities. In what seems to be almost an afterthought, the report mentions that the municipal grid did not provide any power to the mining industries on the Rand. 65

For the Johannesburg Municipality, the concerns of the colonial government and mining interests were of lesser importance than the implications of allowing privatised electricity supply.

The Mayor of Johannesburg told the Commission that the city’s council believed that a privatised supply of electricity within municipal borders would be “injurious” to the city’s interests. In explaining the council’s views on non-municipal suppliers, Chudleigh said that the city officials believed that all private suppliers should be restricted from operating within municipal boundaries without the city’s permission, since competition over an area of supply would negatively affect the council’s ability to use the income from business and residential consumers to offset the high costs of installing streetlights. It had also been municipal policy to place all high voltage cables in underground trenches, and that granting any other supplier to install their own overhead cables would prove too dangerous for Johannesburg’s residents.66

Professor Dobson, who had taken over the post of Town Electrical Engineer during the failed attempt at running the gas-powered plant, gave evidence that the city would suffer a financial loss if private supply was allowed. The city offered all residents and businesses equal tariffs across the entire area of supply, based on the principle that a larger area of supply equates to overall lower tariffs. The counter-argument to the city’s official testament against privatisation hinged on the idea that lack of competition could negatively affect the city’s residents – without proper oversight, the Commissioners believed, a Municipality could over-charge consumers for the service. 67

65 "Report of the Power Companies Commission," National Archives of South Africa (TAB), CT 155, ref. T39/56, pp. 17-18. 66 "Power Commission: Municipal Witnesses," Transvaal Leader, August 27, 1909. 67 "Power Commission: Municipal Witnesses," Transvaal Leader, August 27, 1909; "Power Commisison: Electrical Engineers' Evidence," Transvaal Leader, August 28, 1909; "Report of the Power Companies Commission," National Archives of South Africa (TAB), CT 155, ref. T39/56, pp. 50-51.

- 30 -

The Commission’s findings led to the drafting of the Transvaal Power Bill in early 1910, for presentation to the Transvaal Parliament shortly before the formation of the Union. 68 The Bill was enacted as the Transvaal Power Act of 1910 on May 28, 1910, less than two months after the

Power Commission had presented its final report to the colonial government. 69 The municipal objections to the Power Bill were similar to those brought before the Power Companies

Commission, and focused on what the city’s officials saw as an infringement of municipal rights.70

For Johannesburg’s Town Council, there was more at stake than the loss of exclusive rights to supply electricity to ratepayers. Partly, the municipal councillors were concerned that the city would lose the income from residents who switched over to private electricity suppliers, as their representatives had stated to the Power Companies Commission. The city also had to consider the economic effects of the failed gas plant, as well as the expenditure that would be required to complete the installation of the new coal-burning equipment at the President Street Station.

The representatives from the Johannesburg Municipality were not the only ones to publicly speak out against the legislation. A newspaper editorial published by the Rand Daily Mail in mid-

April 1910 portrays the Transvaal Power Bill as a stand-off between the municipal service providers and private generation companies to determine who had the legitimate rights to supply electricity within municipal boundaries. This editorial column favours the municipality rather openly – the writer stating that “the municipality must insist upon nothing less than the absolute right to distribute power within the municipal area — save to the mines.”71

Throughout the process of reading the Power Bill before the Transvaal’s parliament, the colonial government had attempted to present the Bill as important to the mining industry. During the first day of the public readings of the Bill, the parliamentarians in favour of the Bill had even tried to reassure the opposition that the legislation would not adversely affect white labourers at

68 "Power Propositions: State Control," Rand Daily Mail, April 5, 1910.;"Power Companies: The Commission's Report," The Star, April 8, 1910; "Power Propositions: State Control," Rand Daily Mail, April 5, 1910. 69 "Power Companies Commission," The Star, May 15, 1909; Conradie and Messerschmidt, Symphony of Power, pp. 44-45. 70 "Power Bill: How it Affects the City," Rand Daily Mail, April 14, 1910. 71 "The Power Bill," Rand Daily Mail, April 18, 1910.

- 31 - municipal power stations. They went on record to state that the enactment of the Power Bill would favour the use of large power stations, which could result in a decline in the demand for firemen and engine-drivers required to operate the stations as power generation became increasingly centralised. The hope expressed before the parliamentary gathering was that this decrease in labour requirements would be followed by a commensurate increase in the number of electrical mechanics needed to keep the stations running. 72

The point of concern was not the total expected decrease in jobs that would result from the centralisation of power supply, but rather in the way that changes in energy supply would affect the ratios of different job positions in the power stations. The South African Engine Drivers’ and

Firemen’s Association objected to the use of electricity on the Rand’s mines, because of the fears that the use of electricity would reduce the need for white labourers on the mines that still used steam power. By extension, the Association was concerned that this would shift the racial balance too far away from what they believed to be favourable. The Commission reported that the shifts in one type of skilled work would be counter-balanced by the increase in the demand for other skilled workers. Instead, the report stated, “the cheap power is likely to lead to the replacement of manual work by mechanical contrivances, and the Native is not generally capable of adequately supervising the latter in a suitable manner.” 73

As the Municipal Council in Johannesburg would do again in the early 1920s, it presented itself as the legitimate provider of electricity to the businesses, industry, and residents of the growing city. Some of these fears about the Power Act were founded on the existing threat that the VFP and RMPS already presented to the Johannesburg Electricity Department. The Municipal

Council wanted the Transvaal government to change the provisions that would allow non- municipal suppliers to use municipal roads and pavements for setting up their privately-owned infrastructure. 74

72 "Power Bill," Rand Daily Mail, April 14, 1910. 73 "Report of the Power Companies Commission," National Archives of South Africa (TAB), CT 155, ref. T39/56, pp. 43-45. 74 "Power Bill: How it Affects the City," Rand Daily Mail, April 14, 1910.

- 32 -

3. Interwar Changes, Post-War Integrations: From the Electricity Act of 1922 Onwards

The chronic shortages that had started before the misguided purchase of the gas-powered engines, and that had been worsened by their failure, continued to affect Johannesburg a decade after the gas-powered scheme had been scrapped. In November 1915, the Mayor of Johannesburg, speaking at a gathering of the Association of Municipal Electrical Engineers of South Africa, stated that the Johannesburg power plant “was second to none in the world.”75 Within two months of this statement, the VFP put forward an offer to supply the city with bulk power purchases at lower rates than the city could generate the power at its own station.76

Politicians, journalistic editors, and the ratepayers were split on the issue of whether to accept the VFP’s offer, and not necessarily according to those three categories. A spat between the

Rand Daily Mail and the Evening Chronicle dailies started when the former made accusations of journalistic impropriety against the latter publication after the Chronicle urged the city to accept the VFP’s offer. The Daily Mail’s position on the contract offer should have been clear enough from their initial article’s title, which warned Johannesburg’s residents of “The Cloven Hoof.” The

Chronicle responded in kind, with the statement that such accusations could only have come from a “journalistic pervert”. 77

The point did not need to be laboured any further, but the Daily Mail published a series of editorial cartoons on the debate around the VFP’s offers. In one cartoon, an exasperated homeowner sees a stray cat climbing over his wall and exclaims, “Good gracious, I thought I drowned that beastly thing five years ago.”78 In another cartoon, a travelling salesman offers to help a domestic worker in exchange for “just getting his foot in the door,” to which she replies,

“I’ve seen that trick played before.”79 The message behind the cartoons was clear – the VFP was more than a minor irritation, the company’s interference in municipal affairs was seen as an

75 "Municipalities and Electricity," Rand Daily Mail, November 16, 1915. 76 "Municipal Electric Supply (Report)," Evening Chronicle, February 7, 1916. 77 "Municipal Electric Supply (Report)," Evening Chronicle, February 7, 1916; "The Cloven Hoof," Rand Daily Mail, February 8, 1916; "Municipal Electric Supply (Opinion)," Evening Chronicle, February 8, 1916. 78 ""The Cat Came Back"," Rand Daily Mail, February 9, 1916. 79 "Trying to Get His Foot In," Rand Daily Mail, February 17, 1916.

- 33 - unwelcome intrusion that simply would not desist. For those who were in favour of accepting the

VFP’s offer, the economic benefits of cheaper power from a non-municipal source made more sense than the costlier option of upgrading the city’s existing power plant to meet expected demand increases.

The economic arguments in favour of the VFP’s suggested contract gained further traction when the state of local and global manufacturing industries during World War I was factored into the debate. Wartime shortages of personnel, finances, and raw materials had caused British companies and municipalities to impose restrictions on the availability of capital and labour, restrictions which would have conceivably had an impact on the availability of new equipment for

Johannesburg’s power station. It was also stated that the interconnection of the two networks would be beneficial for the engineers at both the VFP and Johannesburg power stations, since a combined network would allow them to more easily balance the changes in demand over the course of each 24-hour period. 80

To the dissatisfaction of ratepayers, not to mention the VFP, the municipal councillors voted against entering into negotiations with the Company. The town’s electrical engineers believed that greater benefits could be derived from upgrading the existing municipal station than from co-operation with an external entity. 81

The 1910 Transvaal Power Act had helped to lay the foundation for the nationalisation of electricity generation and distribution. The efficacy of centralised electricity generation from larger stations had been proven by the start of the 1920s, especially by the success that the VFP and RMPS enjoyed in supplying electricity to large swathes of the Rand, including the municipalities of Boksburg, Germiston, Roodepoort-Maraisburg, and Springs. 82 It should follow

80 "Town Finance: Power Station Plant," The Star, February 9, 1916; H. A. Wyndham, "Johannesburg and the V.F.P.," Rand Daily Mail, February 11, 1916; "Town Council and the V.F.P.C.," The Star, February 14, 1916. 81 "Power Supply: Victoria Company's Offer," The Star, February 14, 1916; "Power Supply," The Star, February 16, 1916; "V. Falls Power: Town Council Turn Down Offer," Evening Chronicle, February 16, 1916; "Town Council and Power Plant," The Star, February 17, 1916; "Nothing Doing for the V.F.P.," Rand Daily Mail, February 17, 1916; "The V.F.P. Co.'s Offer," Evening Chronicle, February 18, 1916; Bernard Price, "Town and V.F.P.," Rand Daily Mail, February 18, 1916. 82 "V.F.P. Handbook," University of Cape Town Libraries Special Collections Manuscripts, BC697, A15.1.

- 34 - then, that the establishment of a national system of control over the generation and sales of electricity would be a logical step in the process of electrification. When the first drafts of the

Electricity Bill were read before Parliament in 1921, the municipalities of South Africa once again felt that their political and economic welfare was at risk.

Municipal councils presented a threat to the centralisation of electricity that the Electricity

Act was designed to secure. In turn, the municipal bodies saw the passing of such legislation as a threat to their function as suppliers of electricity to their residents and ratepayers, and therefore insisted on taking part in the drafting of the Bill that would be presented to parliament. 83 These political concerns stemmed from the fear that they would be supplanted as service providers in their areas of jurisdiction. In the initial form of the Electricity Bill, the ECB would be allowed to determine which generating stations and networks would be integrated into combined networks, without needing to consider who owned the infrastructure. Under this arrangement, a less productive municipal station would face closure if a governmental or private station in the same area proved to be more productive. 84

For their part, municipal groups felt that the Electricity Bill offered too much leeway to the governmental and corporate power stations. Municipalities had been informed that non-municipal power stations would have the right to install infrastructure without having to consult with municipal authorities first. This clause gave governmental stations the right to install underground cables without municipal approval – in particular, the Johannesburg Municipal Council found this problematic because labourers working for the national government would be digging trenches along municipal pavements and roadways. 85

83 Christie, Electricity, Industry and Class, p. 82. 84 "Town Council Acts: New Electricity Bill," Rand Daily Mail, April 2, 1921; "Manufacture of Electricity: Important Draft Bill," Rand Daily Mail, April 4, 1921; "Electricity Bill Dangers: Municipalities Alert," The Star, April 18, 1921. 85 "Manufacture of Electricity: Important Draft Bill," Rand Daily Mail, April 4, 1921; "Electricity Bill Dangers: Municipalities Alert," The Star, April 18, 1921.

- 35 -

In the earlier phases of municipal electrification, urban distribution networks in cities like

Johannesburg were almost exclusively subterranean. 86 Allowing construction engineers to work on municipal roadways and pavements without requiring any consultation with the city council created a credible threat to the longevity of the existing roadworks infrastructure. The companies that were responsible for laying distribution cables in the early 1900s in Johannesburg had already earned a reputation for not keeping thorough maps of their installed cables, making troubleshooting a somewhat lengthy and laborious process, even when the Municipal Council had been involved at any stage. 87

Economically, the municipalities were afraid of the implications of revised tariff structures that would be introduced under the Electricity Act. Municipal suppliers created tariff schemes that would get the highest possible profit margin from business and industrial consumers, with the intent to use these profits as “rate relief” for residential consumers. Should the tariff structures be standardised at a governmental level, the municipalities feared that they would lose this economic freedom, thereby handicapping their ability to offer lower rates to residential areas. 88

The municipal councils were concerned that an organisation running at a national level would develop their own infrastructure and consumer base, thereby leaving the municipalities with unused infrastructure that had been developed at great cost to their ratepayers. The draft Bill also gave large businesses and industry the right to request that their electricity supply be provided by either government or corporate stations, thereby creating a further threat to the rate relief that municipalities wished to provide to residential customers. 89 Losing these industrial consumers could be problematic for municipalities, since a considerable portion of the income from these larger consumers went to rate relief. In 1955, the Electricity Department in Johannesburg

86 Shorten, Johannesburg Saga, p. 604. 87 Shorten, Johannesburg Saga, p. 605. 88 Christie, Electricity, Industry and Class, pp. 54, 82. 89 "Electricity Bill Dangers: Municipalities Alert," The Star, April 18, 1921.

- 36 - contributed £630,000 towards residential rates from the department’s gross annual income of

£4,000,000. 90

Municipalities across South Africa countered these perceived threats by sending a deputation of councillors to Cape Town in order to meet with F. S. Malan, the Minister of Mines and Industry during the drafting of the Electricity Bill. The deputation presented Malan with a petition, which requested that the Bill be withdrawn, so that municipal representative could consult with the drafting committee before any legislation was enacted. They requested that the ECB be comprised of members who were not directly linked to any specific existing parliamentary portfolio, to ensure that no single MP could exercise undue influence over the Board. The deputation also requested that the Bill be drafted to give them the authority to decide on who was allowed to install infrastructure, and even requested that the city councils be given the opportunity to work as sub-contractors during the installation of underground cables. 91

The deputation to Cape Town managed to secure a place for municipal representatives in the drafting committee’s next series of meetings. The mayors of Johannesburg and Pretoria were invited to attend the committee’s sessions in Johannesburg, accompanied by a representative of the Municipal Association. 92 After municipal representatives had commented on the Bill, corporate and government suppliers would have to notify municipalities of any plans to establish electricity stations or infrastructure within the council’s area of supply. 93 Municipal stations that had been in operation for longer than thirty-eight years were eligible for appropriation by the

Electricity Supply Commission, which required the Commission to purchase the station and its

90 Seventy Golden Years, 1886-1956, (Johannesburg: Municipal Public Relations Bureau, n.d.), p. 339. 91 "Town Council Acts: New Electricity Bill," Rand Daily Mail, April 2, 1921; "Manufacture of Electricity: Important Draft Bill," Rand Daily Mail, April 4, 1921; "Draft Electricity Bill: Delegation for Capetown," Rand Daily Mail, April 6, 1921; "Electricity Bill: Council's Deputation Leaving," The Star, April 8, 1921; "The Electricity Bill: Deputation Leaving for Capetown," Rand Daily Mail, April 11, 1921; "The Electricity Bill: Proposed Amendments," The Star, April 11, 1921; "Electricity Bill Dangers: Municipalities Alert," The Star, April 18, 1921; "Live Question for Local Bodies: Electricity Bill," The Star, April 20, 1921; "The Electricity Bill," Rand Daily Mail, April 22, 1921. 92 "The Electricity Bill: A Local Conference," The Star, April 16, 1921; "The Electricity Bill: Effect of Municipal Representations," Rand Daily Mail, April 18, 1921. 93 Government Gazette of 24 July, 1922, vol. 44, no. 1256, p. lxxix.

- 37 - supply network at a value that took the type, number, and condition of the station’s assets into consideration. 94

Municipalities presented their opposition to the Bill as a concern for the wellbeing of their electricity consumers, basing their arguments on ideas about who had “legitimate” authority to provide services to municipal customers. Problematically, businesses within the Johannesburg

Council’s area of supply had been reporting declines in productivity and income following the end of the First World War. This was partly caused by the decrease in generating capacity that had started during war rationing, and partly because equipment manufacturers were not able to restore their pre-war supply networks immediately after the 1918 Armistice.95 Urban electricity demand had continued to grow during the war, but the city’s generation capacity had not grown to the same extent. Orders that had been placed in 1915 to upgrade the city’s power station were not filled until

1921, thereby worsening the city’s supply problem, since the new and upgraded equipment required further upgrades to keep pace with the continuing increases in demand. 96

Once the shortage had made itself increasingly apparent, members of the Johannesburg

Municipal Council had been in consultation with the VFP to begin the first steps towards the purchase of emergency electricity supplies to compensate for the shortfall – a move that did not earn favour with many Johannesburg residents. There were some in the city who felt that their monthly rate payments should not be used to pay another organisation for a service that the municipality was already delivering. Councillors countered this argument by pointing out that the municipality needed to conduct emergency renovations on the city’s existing power station to repair and upgrade equipment, but that the city could not afford to continue running at minimum capacity while the renovations were in progress. Residents in the newer areas of Johannesburg stated that the Municipal Council should attempt to make any and all necessary arrangements to

94 Government Gazette of 24 July, 1922, vol. 44, no. 1256, p. lxxxii. 95 "Be Sparing with Electric Light," Rand Daily Mail, December 24, 1920; "Electric Current Shortage: Appeal to Customers," Rand Daily Mail, November 2, 1919; "Pressure on Municipal Plant," Rand Daily Mail, October 28, 1919. 96 Shorten, Johannesburg Saga, p. 606.

- 38 - meet the needs of the city. Houses built during and after World War I were not supplied with electricity because of the lack of capacity, even when a house had been built in an area that already received electricity. 97

It is likely that the Municipality was not only interested in who had the right to supply electricity to ratepayers but was also concerned about who owned the infrastructure through which the electricity was supplied. Contracts between municipalities and third party suppliers had been a feature of Johannesburg’s electricity supply since the start of the twentieth century, when the municipality contracted with the Robinson Deep Gold Mining Company to buy bulk electricity shortly after the end of the South African War in 1902 and had to purchase roughly 60% of its power from the RCEW following the failure of the gas engines in 1906.98 The rationale used by the city’s electrical engineers in opposition to the VFP’s contract offer in 1916 did not still hold true in the era after World War II. By the mid-1950s, the Johannesburg Electricity Department boasted that interconnection with Escom’s grid have saved the city roughly £7 million pounds, money that would otherwise have been spent on new equipment. The Electricity Department also stated that the interconnection of the city’s local grid and Escom’s regional grid allowed for engineers on both sides to better manage the peaks and dips in demand. 99

In 1923, demand had increased to the point that the station at President Street could no longer meet the needs of the city, and new extensions could not add enough generating capacity to keep up with future growth in demand. As specified by the Electricity Act, the city requested that Escom write a report on the state of the local grid for when the time came to submit an application to the ECB for changes to the municipal grid. However, throughout much of 1923,

Escom was engaged in negotiations with the ECB and the VFP over the licence application for the

Witbank Power Station (see Chapter Two).

97 "Johannesburg's Power Shortage: The Inadequate Supply of Lighting," Rand Daily Mail, September 23, 1921. 98 Shorten, Johannesburg Saga, pp. 599-600. 99 Seventy Golden Years, p. 343.

- 39 -

From Escom’s point-of-view, it would be unnecessary to construct a new power station in

Witbank, which was close enough to Johannesburg to offer a reliable supply of electricity to the

Municipality, and for the Municipality to build its own local power station. Instead, Escom suggested that the Municipality wait until construction at Witbank was completed, either by the

VFP or the Commission, and purchase bulk power from the new station. The Municipality declined the offer of power from Witbank, instead preferring to wait until a formal decision could be made by the Provincial Administrator on whether a new municipal power station could be built. The

Municipality had to wait until January 1928 before receiving final approval for the new power station.100

Once the plans for a new power station had been approved, construction started on the new power station in Jeppe Street, roughly 200 metres from the President Street station. By 1932, the

Jeppe Street Power Station had taken over the majority of the load from the old President Street station, which then started to act as a peak load station for periods of high demand. The Jeppe

Street Power Station was fully functional in 1939, but demand had grown to the extent that the city had needed to start construction on another power station in Orlando in 1937. 101

The Orlando Power Station took longer to build than expected, mostly due to the outbreak of World War II during the plant’s construction. Aside from the widespread difficulties that Escom experienced in getting machinery and parts during the War, the Orlando construction project also suffered a setback when the ship transporting casings and bearings for one of the generators sank due to enemy action. 102 Most of these parts were replaced relatively quickly, but further equipment losses and wartime delays meant that the station was not fully functional until 1946.103 Further growth in demand required the construction of another municipal power plant between the late

100 "The Application of the Victoria Falls and Transvaal Power Company and Its Relation to the Future Power Supply in the Transvaal," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6, pp. 14-15; Shorten, Johannesburg Saga, pp. 606-7. 101 Shorten, Johannesburg Saga, pp. 606-7. 102 "Sinking of Ship Affects City," Rand Daily Mail, November 1, 1940. 103 Shorten, Johannesburg Saga, p. 609.

- 40 -

1950s and early 1960s. The Kelvin ‘A’ plant was completed in May 1960 and additional generating capacity at the adjacent Kelvin ‘B’ plant was completed on February 14, 1964. 104

The compromises that Escom and the Johannesburg Municipality reached with each other benefited both parties by letting them retain a measure of control over their own infrastructure, while also allowing them to balance their respective loads more easily than if the two networks remained entirely isolated. This was an important step in the functioning of the National Grid, because the final agreement meant that the Municipality and Escom could continue to function as interdependent entities that could both fulfil their commitments to their respective consumers. It also alleviated the need for Escom to supply electricity to municipal customers, who purchased relatively small numbers of units each year, and gave the parastatal the opportunity to apportion more of the country’s nationalised power stations to generating electricity for mining and industrial customers.

104 Shorten, Johannesburg Saga, p. 616.

- 41 -

CHAPTER TWO – “HARNESSING THE FALLS”: THE VICTORIA FALLS AND TRANSVAAL POWER COMPANY, 1906 – 1948

Electrification and electrical technologies added extra momentum to the already vigorous growth of mining activities on the Rand at the turn of the century, and the Victoria Falls and

Transvaal Power Company (VFP) played a central role in providing this electricity between 1906 and 1948. Within seventeen years of the Company’s founding, the VFP was generating more electricity “than was consumed in the cities of London, Birmingham and Sheffield combined,” largely due to the power that was being sold to the mines. 105 Even though the first plans for the organisation were soon abandoned, the VFP would become the largest electricity producer in the

British Empire and was a key element in the development of the National Grid.

Founded in 1906, the VFP was a subsidiary of the African Concessions Syndicate (ACS), which was itself a subsidiary of Cecil Rhodes’ British South Africa Company (BSAC). The

Company was formed with the original intention of generating hydroelectric power on the Zambesi

River to supply electricity to the Witwatersrand’s mines, roughly 1 100 kilometres to the south.

The scheme was highly impractical, given the large transmission losses that would occur on such long high-voltage power lines, the extreme costs of transmitting power over such long distances, and the annual shortfall in electricity production that would occur during the dry season. 106

Renfrew Christie has discussed much of the history of the VFP, but most of the discussion in his book focuses on the intricate network of associations, contracts, concessions, and subsidiaries that were required to establish the Company. The narrative of the VFP’s politics and economics is a tangled, overlapping network of international deals made to secure generating equipment, expertise, and capital from a variety of sources across Europe amidst the increasing nationalism at the turn of the century (Figure 3). Aside from the challenges faced by the

Company’s founders, it is also important to understand the VFP’s contribution to the formation of

105 Christie, Electricity, Industry and Class, p. 6. 106 "Rand Power: Problems Generated Some Notable Achievements," University of Cape Town Libraries Special Collections Manuscripts, BC697, A15.3; Christie, Electricity, Industry and Class; Conradie and Messerschmidt, Symphony of Power.

- 42 - the National Grid – the purchase of the VFP’s assets by Escom in 1948 increased the Electricity

Supply Commission’s total generating capacity by almost a third.

In building a regional grid around the Witwatersrand, the VFP was drawn into a series of negotiations, compromises, and agreements with local municipalities, the gold mines, and private consumers, but it is the Company’s interactions with Escom that were most important for the establishment of the National Grid. When the Electricity Act was signed in 1922, Escom was charged with providing electricity that was both cheap and abundant; however, as the early annual reports acknowledged, the parastatal was not responsible for beginning the process of electrification, since other entities were already involved in generating and selling electricity. In order to construct the National Grid, Escom would therefore have to negotiate agreements and contracts with the owners of these other systems, whether to appropriate existing infrastructure or to begin anew with establishing local and regional grids.

- 43 -

Figure 3 - Organisational Diagram of the VFP and Related Entities

- 44 -

1. “A Six Million Scheme”: Starting the Victoria Falls (and Transvaal) Power Company, 1906 – 1922

Once it became evident that the plan to generate hydroelectric power at the Victoria Falls was impractical, the Company changed its name to the Victoria Falls and Transvaal Power

Company. As Renfrew Christie has noted, the Rand of the early twentieth century was proving to be an ideal testing ground for the theory of centralised electricity generation and distribution.

Before the start of the Boer War, electrification in the Transvaal had not progressed much further than streetlighting in the urban areas, and the mining companies had preferred the use of steam engines to run machinery. By the eve of the First World War, the Witwatersrand’s gold mines were the largest consumers of electricity in the country, and each of the largest gold mines demanded more electricity than the entire coal mining industry. The differences in energy requirements may be attributed to variables in the working conditions at gold and coal mines, such as the type of rock in which the raw materials are found, but the vast differences in the needs of the two industries does help to explain why the gold mines were responsible for consuming so much of the electricity generated on and near the Witwatersrand. 107

In October 1906, the VFP had requested permission to build a power station on the East

Rand. The Johannesburg and Boksburg municipalities objected to the application, on the grounds that municipalities should be granted priority in supplying electricity to residential consumers. The exact role played by the municipal objections in the government’s final decision is not entirely clear, but the official rationale was that the Rand Central Electric Works Limited (RCEW) had filed a protest against the VFP’s operations on the East Rand. The RCEW stated that the VFP was not involved in mining operations, and therefore did not have the legal rights to construct or operate any public services within the area. 108

The VFP had encountered the first critical problem in supplying electricity to the Rand – competition from the individuals, companies, and government groups who had already established

107 Christie, Electricity, Industry and Class, p. 21. 108 "Rand Power Scheme: The Jupiter Site," Transvaal Leader, November 4, 1906.

- 45 - their hold on resources and areas of supply. The VFP’s solution to this was relatively efficient and simple. They engaged in a series of negotiations, payments, and buy-outs that cost the company dearly in short-term financial costs but ensured that the Company had a dominant role in the supply of electricity to the major gold mines until after World War II.

Within six months of the East Rand application being rejected, the VFP had bought the assets and licenses owned by the RCEW and the General Electric Power Company Limited

(GEPC) for a combined total of £500, 000. These two purchases made the VFP the single largest, and almost exclusive, provider of electricity to the Transvaal’s gold mines. 109

During the problems with Johannesburg’s power supply after the failure of the gas-powered municipal power plant, the city had made an emergency agreement with the RCEW in March 1906 to provide supplies of electricity to municipal customers. Once the RCEW was integrated into the

VFP’s business holdings, the VFP took over the responsibility for the emergency bulk supply to the city until June 30, 1908. 110 This contract gave the Company the opportunity to consolidate its hold on the supply of power on the Rand, but also gave the city a convenient scapegoat when the chronic problems at the Johannesburg Lighting Department caused the department to suffer a large financial loss for the year 1907/1907. The town council announced that the city was facing an increasingly large deficit in the lighting budget, and promptly blamed the VFP for causing the situation.111 The contract between the Company and the city expired in June 1908, but the municipality opted to wait for the municipal power plant to be repaired, instead of allowing the

VFP to continue supplying ratepayers with electricity.

The Company made further gains in creating a monopoly over electricity generation when the Rand Mines Power Supply Company Limited (RMPS) was formed as a subsidiary of the VFP

109 Christie, Electricity, Industry and Class, p. 32; Clark, Manufacturing Apartheid, p. 26. 110 Shorten, Johannesburg Saga, p. 603. 111 Willliam Bickell, "Municipal Electric Supply: The Council and the Power Supply," Transvaal Leader, March 21, 1908.

- 46 - to supply electricity and compressed air to the Rand Mines Limited group. 112 Up until the VFP subsumed the RMPS in 1924, they were considered as separate legal entities.113 The VFP was registered as a company in Southern Rhodesia, but all its operations were governed by the laws of

Southern Rhodesia, South Africa, and England. The RMPS, on the other hand, was registered in

South Africa and was subject to South African laws only. 114 The legal wrangling necessary to coordinate the activity of two legal entities that owned property, employed staff, and conducted business across three countries was largely down to the payment of taxes – any tax incurred by the

VFP would be paid to the country in which the Company was registered. By registering the VFP in Southern Rhodesia, the Company ensured that taxes were funnelled back to the BSAC. 115

Even before the RMPS had started supplying power, engineers had already calculated that the combined capacity of the VFP and RMPS would exceed that of the London Metropolitan area.

This system of amalgamating companies and establishing subsidiaries make it easy to understand why a town councillor from Ophirton told the Power Companies Commission that the VFP wanted

“to have the run of Johannesburg, then of the Transvaal, next of the world, and finally of Heaven itself.”116 This might be an overstatement of the VFP’s aims, but it is reflective of the tensions between the VFP and local government.

Primarily, the objections raised by politicians outside of the greater Johannesburg area related to the use of land by private electricity companies. The Transvaal’s farmers were concerned that the private power companies would not need permission to obtain wayleaves for running high- voltage power lines across farmland, and that the power companies would want to use any of the coal reserves that might be found on agricultural land in the future. The coal industry was also worried that centralised electricity generation would affect their returns on mining investment, and

112 "Compressed Air Supply on the Rand," University of Cape Town Libraries Special Collections Manuscripts, BC697, A15.5; Christie, Electricity, Industry and Class, p. 32. 113 "Souvenir of the Visit to the Rosherville Generating Station," University of Cape Town Libraries Special Collections Manuscripts, BC697, A15.2. 114 "V.F.P. Handbook," University of Cape Town Libraries Special Collections Manuscripts, BC697, A15.1. 115 Christie, Electricity, Industry and Class, p. 36. 116 "Electric Power Schemes: Strong Opposition," Transvaal Leader, May 28, 1909.

- 47 - that the railways would lose revenue if coal was sent to the Transvaal instead of being transported across the country.

Rather, the Witbank Colliery’s consulting mechanical engineer suggested to the Power

Companies Commission that the coal should be mined and transported by rail over long distances, and that the Rand’s mines should invest in hydroelectric stations on the Crocodile River. The

VFP’s argument for privatised electricity generation was that a large company, such as themselves, would be better suited to generating and transmitting electricity over longer distances, while allowing smaller intermediaries to then distribute the electricity to individual consumers within a specified area.

The Transvaal’s parliament had already drafted a bill to regulate the supply of electricity in the colony before the Power Companies Commission had begun its hearings, but once the

Commission had started its work the reading of the draft was put on hold until the Commission’s official report could offer recommendations on further legislation. When the Power Bill was presented to the colonial parliament in April 1910, responses were largely determined by organisational loyalty to either municipal suppliers or the VFP. For those loyal to the municipality, the Power Bill was nothing but a ruse to hide the VFP’s attempts at establishing a monopoly in the

Transvaal – a “Power Plot” that threatened the city’s established right to supply services. 117 For ratepayers who felt somewhat marginalised by the lack of service delivery in their areas of

Johannesburg, the Power Bill offered an opportunity to frighten the city into improving services.

A municipal ratepayer complained that the municipality had only contacted him about receiving electricity after their customer base had been threatened by the impending Power Bill.118

The Power Companies Commission reported to the Transvaal colonial government that large and centralised generating stations would prove to be more cost effective in the long-term

117 "The Power Plot: City in Danger," Rand Daily Mail, April 16, 1910; "The Power Plot: Rousing the People," Rand Daily Mail, April 18, 1910; "Power Plot: Great Meeting of Citizens," Rand Daily Mail, April 19, 1910; "The Power Plot: Pretoria's Disapproval," Rand Daily Mail, April 23, 1910. 118 "Letters to the Editor: Power Bill — First Result," Transvaal Leader, May 12, 1910.

- 48 - than a network comprised of isolated stations that each covered their own small area of the grid, and “…that undertakings of this nature should be left to private enterprise.” 119 The report recommended that municipal and government suppliers refrain from investing their own capital in the construction of new power stations, since the upgrading or installation of new technologies carried financial risks. Municipal ratepayers, according to the Commission, would be better off if their municipalities refrained from investing large sums of money in establishing new power stations, as technological improvements could make even the newest machinery redundant.

2. Witbank’s Coal for Johannesburg’s Gold: The VFP after the 1922 Electricity Act, 1922 – 1948

Once the Electricity Bill was enacted in the second half of 1922, the VFP’s undertakings took on national importance. As the largest supplier of electricity to the Rand’s mines, the

Company had been important to the Union’s economy after 1910, but the VFP was now going to be involved in the electrification of all four provinces. While the Company had worked for the preceding two decades to secure their customer base on the Witwatersrand, Escom also wanted the coal mines in the Witbank region to have access to a supply of cheap electricity. Witbank presented an ideal site for the construction of a large power station to supply the Rand’s mines because the region had the combination of fuel supply from the coal mines; water from the Olifants

River; and the power station’s proximity to the Rand made high voltage transmission lines feasible.

Shortly after being established in March 1923, Escom had started to investigate whether it would be feasible to construct a new power station in Witbank, but their inquiries were somewhat truncated by the VFP’s application for a license to build their own station and provide power to the Rand and Witbank areas in May 1923. The Company had already been granted a license soon after the signing of the Transvaal Power Act, but the license had expired when the Electricity Act was passed in 1922.

119 "Report of the Power Companies Commission," National Archives of South Africa (TAB), CT 155, ref. T39/56.

- 49 -

The rationale given by the VFP for choosing to construct a new station at Witbank – instead of adding to the capacity at their existing station in Vereeniging – rested on the idea that they would not be able to supply the gold mines forever, because the “Gold Mining Industry is a wasting industry and must sooner or later fall away.” It would be in the best interests of the VFP and the

Railways Administration, according to General Manager Bernard Price, if the Company would assist in the electrification of railways and the growing industries in Witbank. 120 Price was forced to retract his offer of a cooperative agreement between the VFP and Escom two months after writing this letter, because the Company’s directors in London felt that there was not sufficient time to negotiate with the South African government before the mines required extra power. Escom believed that this meant that the VFP had reconsidered the construction of the Witbank station, but the Company had instead decided to proceed with their plans for Witbank without government assistance. 121

On May 11, 1923, the ECB received notification from the VFP that the latter wished to apply for a licence to establish a new power station at Witbank, with objections from the Railways

Administration and Escom being lodged on June 14 and June 15, 1923, respectively. 122 The VFP was concerned that future demand on the Rand would outstrip the available capacity in local power stations, since the Company only had two spare generator sets that could be used to supply peak loads. Engineers predicted that by June 1924, the Company would only have a single surplus generator set that could be used for peak load supply. 123

The Electricity Control Board was required to convene a hearing on the license application, since objections were received from the Electricity Supply Commission; the South African

Railways & Harbours Administration (SAR); Government Gold Mining Areas, Limited; several mining houses; and the Johannesburg Municipality. The mining houses based their objection to

120 "Bernard Price to Robert Kotze, January 26, 1923," National Archives of South Africa (SAB), ECB 10, ref. 56/8/1. 121 "Application of the Victoria Falls and Transvaal Power Company," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6, p. 5. 122 "Sixteenth Meeting," National Archives of South Africa (SAB), MNW 634, ref. MM 2879/22, pp. 1-2. 123 "Sixteenth Meeting," National Archives of South Africa (SAB), MNW 634, ref. MM 2879/22, p. 2.

- 50 - the initial licence application, because the VFP had not given all of the information required by the Electricity Act. The Act specified that all licence applications needed to give estimates of tariffs, minimum monthly consumption quotas, the classes of consumers that were expected to use generated power, and the cost price of generating electricity at the new station.124

The complaints from gold mining companies were largely withdrawn in the later stages of the Board’s hearings regarding the licence application, after the VFP agreed to offer better tariffs and rebates to the mines once operating costs decreased when the Witbank station was fully operational. 125 In exchange for withdrawing Escom’s objections to the licence application, the

VFP had to agree to offer a rebate to all consumers who received power directly from the Witbank station.

The Electricity Act of 1922 stated that in cases where an undertaking made a “surplus” profit in the course of a financial year, all customers were to be granted a pro-rata rebate equivalent to twenty-five percent of the profit. The VFP’s agreement with Escom was that all customers receiving power from the Witbank station would be granted a rebate to the value of fifty percent of annual profits accrued from the Witbank undertaking. In addition to this rebate, the Company agreed to give all mining consumers a discount of 15 percent, which would be applied retroactively from January 1, 1923. This discount would then increase to 17½ percent once the power station was in full commercial operation. 126

The Mayor of Johannesburg voiced his objections to the ECB’s decision that allowed the

VFP to consult with its head offices in London on a provisional license agreement without first consulting the Johannesburg councillors. The Council claimed that their application for an extension to the municipal power station was pending, while the ECB’s hearings on the Witbank

124 Government Gazette of 24 July, 1922, vol. 44, no. 1256, pp. lxxvii-lxxviii.; "Petition of the Government Gold Mining Areas (Modderfontein) Consolidated Limited," National Archives of South Africa (SAB), MNW 682, ref. MM2990/23, pp. 10-11. 125 "Million Pound Power Station," Rand Daily Mail, December 4, 1923. 126 Government Gazette of 24 July, 1922, vol. 44, no. 1256, pp. lxxix-lxxx; Electricity Supply Commission, 1923 Annual Report, p. 6, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1923%20Annual%20Report.pdf.

- 51 - station were in progress. The city’s councillors felt that if the VFP was allowed to establish a successful station in Witbank, it would allow the Company to monopolise electricity sales in the city, thereby making the municipal station defunct – a power station that the Mayor called “our very birthright,” 127 and for which the City Council promised to fight “tooth and nail.”128

A report written by the Municipal Council in 1925 stated that the Town Council’s stubbornness in dealing with the VFP, and especially towards the Witbank Power Station, was based on fears that the Company’s power supply was prone to regular interruptions. Most of all, the Council stated that the ubiquitous thunderstorms that occur during summer on the Highveld presented too great a threat to the safety of the VFP’s transmission lines.129

This animosity between the Johannesburg Municipality and the VFP was hardly new, and the acrimony lasted well after the Witbank station had already been completed. In 1930, General

Manager and Chief Engineer of the VFP, Bernard Price, told the Empire Mining and Metallurgical

Congress that Johannesburg was the only major municipality on the Rand that did not take electricity from the Company. 130 Escom saw the council’s objections to the VFP’s Witbank application as an attempt to restore the Labour Party’s public image after municipal employees who had participated in the Rand Revolt had been fired. According to an internal memo, Escom believed that many of these civil servants were “rank socialists and bolschevists [sic]” who had been employed at the power station before the uprising and that the Labour Party wanted to regain its lost credibility by forcing the city to reinstate those workers. 131

The VFP’s representatives managed to establish an interim agreement with Escom that amended the Company’s original application, which helped to settle most of the objections that the Supply Commission had brought to the hearings. The VFP and Escom created an unusual set

127 "The Town and the VFP: Mayor's Strong Criticism," Rand Daily Mail, October 30, 1923. 128 "A Corner in Power?," Rand Daily Mail, October 20, 1923. 129 "Report on the New Power Station of the Gas and Electric Supply Department " National Archives of South Africa (SAB), MNW 717, ref. MM1288/24, pp. 2-7. 130 "Power Supply on the Rand," University of Cape Town Libraries Special Collections Manuscripts, BC697, A15.6. 131 "Untitled Memo," National Archives of South Africa (SAB), MNW 687, ref. MM3396/23.

- 52 - of rules for building and operating the prospective Witbank Power Station that would stay in place for more than two decades after the station was constructed. Under these terms, the VFP would be allowed to apply for a license to construct and operate a power station in the vicinity of Witbank but would not be allowed to supply electricity directly to customers in Witbank itself. Instead, ownership of the station would rest with both the VFP and Escom, thereby allowing Escom to sell some of the generated electricity to their consumers in Witbank.132

The VFP had to also agree to amend the licence application to change the proposed area of supply that would be covered under the licence. Instead of being granted control over transmission and distribution of power from Witbank, the Company had to allow Escom to apply for local distribution rights to supply the Witbank area from the new station, while maintaining control over the high-voltage lines that would connect Witbank and the Rand. 133 In the final agreement, Escom would not be allowed to request supply in any areas that were already supplied by the VFP, except in cases where the Railways Administration requested electricity supply along sections of their rail lines.134

In exchange for these concessions, Escom would recompense the Company for their share of the station’s construction costs and would pay for a percentage of the monthly operating costs once the station was completed. During months when Escom’s share of the station generated more power than was needed, they reserved the right to deduct the costs of generating power from their monthly payment to the VFP, effectively forcing the Company to buy the surplus electricity generated for the commission’s customers. 135 When the final agreement between the two organisation was completed, the VFP had also agreed to apply the same scheme that offered lower rates to the mining companies to all their customers taking supply from Witbank.136 The ECB

132 "Draft Heads of Agreement," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6. 133 "Twenty-Second Meeting," National Archives of South Africa (SAB), MNW 634, ref. MM 2879/22, p. 1. 134 "Draft Heads of Agreement," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6, pp. 1-2. 135 "Draft Heads of Agreement," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6. 136 "Agreement Relating to the Generating Station at Witbank Transvaal," National Archives of South Africa (SAB), MNW 717, ref. MM1367/24.

- 53 - granted the Company the license to start construction at Witbank on July 21, 1924 and Escom was given permission to supply their consumers in the area on April 6, 1925.137 By the end of 1926, the Company had invested £1 299 054 in construction, which included materials, land purchases, machinery, and interest. 138

Charles Merz wrote to Jan Smuts that these arrangements would ensure that “…the

Commission will not before the work proceeds have to make arrangements for finance…” and that the VFP’s participation in the construction and operation of the station would protect Escom against potential financial losses if electricity demand proved to be lower than expected. 139 While

Escom was investigating the feasibility of operating a station from Witbank before the first public hearings in front of the ECB, the parastatal did express some concern about the demand for electricity in the area surrounding Witbank. The load in the immediate surroundings were not high enough to guarantee that the station would be profitable, since secondary industry in the area was still relatively undeveloped and the collieries did not use as much power as the gold mines. There were two suggested solutions to this problem – either electrify the railway lines running from the western edges of the Reef in Germiston and Springs to the Eastern Transvaal or convince the VFP to buy a large bulk supply from the Commission on a monthly basis. 140

3. After Witbank: The Rand Extension Undertaking, Klip Power Station, and Vaal Power Station

Even with the massive Witbank Power Station running, Escom and the VFP still needed to continue adding to the available generating capacity in the Transvaal. Interwar electrical demand had increased so rapidly that the station had already required the installation of extra generators in

137 "Report of the Commission on the Establishment of an Electrical Undertaking at Witbank (Transvaal)," National Archives of South Africa (SAB), MNW 717, ref. MM1367/24; Electricity Supply Commission, 1924 Annual Report, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1924%20Annual%20Report.pdf. 138 Electricity Supply Commission, 1926 Annual Report, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1926%20Annual%20Report.pdf. 139 "Charles H. Merz to J. C. Smuts, November 2, 1923," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6. 140 "Application of the Victoria Falls and Transvaal Power Company," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6.

- 54 -

1929 and 1930. 141 After the fifth set of generators had been installed in 1930, the site in Witbank could not be extended any further, because the Olifants River could not supply enough extra water for a sixth set of generators and boilers. The Company also needed to decommission its power station at Simmerpan, which was only useful for generating extra power to boost capacity during peak hours. 142

In March 1934, the Commission applied for permission for a new power station that would be built near to Vereeniging and permission to begin supply from a new undertaking in the region of the Rand. Once the ECB approved these licence applications, the permits were ceded to the

VFP as a continuation of the cooperation between Escom and the VFP in building and operating power stations. 143 Electricity for the Rand Extension Undertaking was taken from Escom’s power stations at Witbank and the new Klip Power Station near Vereeniging, as well as from the VFP’s

Rosherville, Brakpan, Simmerpan, and Vereeniging Power Stations.144

Klip Power Station needed large quantities of water for cooling, and there was no guarantee that enough water would available to meet the needs of future expansions in generating capacity.

To ensure that the power station had an adequate supply of water for the foreseeable future, Escom made a deal with the government to give £81 000 towards the cost of the Vaalbank Dam. In exchange, Escom was given the rights to use an extra 12 million gallons (approximately 54.5 million litres) of water per day from the Vaal River. 145 Once construction on the Vaal Power

Station started in early 1939, Escom’s contribution to the Vaalbank Dam increased to £124 875.

The extra contribution to the dam’s construction gave Escom the right to take 18.5 million gallons

141 Electricity Supply Commission, 1928 Annual Report, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1928%20Annual%20Report.pdf; Commission, 1929 Annual Report; Electricity Supply Commission, 1930 Annual Report, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1930%20Annual%20Report.pdf. 142 "Rand Power: Problems Generated Some Notable Achievements," University of Cape Town Libraries Special Collections Manuscripts, BC697, A15.3. 143 Electricity Supply Commission, 1933 Annual Report, p. 5, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1933%20Annual%20Report.pdf. 144 Electricity Supply Commission, 1935 Annual Report, p. 31, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1935%20Annual%20Report.pdf. 145 Electricity Supply Commission, 1936 Annual Report, p. 33, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1936%20Annual%20Report.pdf.

- 55 -

(roughly 84.1 million litres) of water per day from the Vaal. 146 The negotiations between the VFP and Escom were yet again mediated by Charles Merz, much to the consternation of the VFP’s

Chairman, Arthur Hadley. 147 This was probably the last significant Escom project with which

Merz was directly involved – he and both of his children were killed in an air raid during the Blitz in October 1940. 148

In March 1939, while construction work was still in progress on the Klip Power Station, work started on another new power station near Heilbron in the Orange Free State. This station, which was designated the Vaal Generating Station Undertaking, was designed to have a capacity of up to 400 000kW, and required cooling towers that could handle twice the hourly throughput of the towers at the Klip station.149 The last two generating sets at the Klip Power Station were synchronised to the grid and put into commercial service in January and July 1940. 150 Construction at the Vaal Power Station was slowed by wartime shortages after September 1939, especially since the main turbines had been ordered from Sweden, but could not be exported to South Africa after the outbreak of hostilities. However, the overall electricity requirements on the Rand decreased as mining demands dropped, which gave the Commission some extra time in which to complete construction. 151

4. Integration into the System: Escom’s Purchase of the VFP in 1948

The co-operative agreements between Escom and the VFP had been tremendously beneficial to both parties – Escom financed the construction of new power stations between the

146 Electricity Supply Commission, 1943 Annual Report, p. 12, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1943%20Annual%20Report.pdf. 147 Christie, Electricity, Industry and Class, p. 127. Hadley disliked Merz so much that even in correspondence with Bernard Price, who had maintained a close relationship with Merz for several years, he referred to Merz as Escom’s “yard dog”. 148 "Charles H. Merz, D.Sc.," Journal of the Institution of Electrical Engineers 87, no. 528 (December, 1940): p. 708. 149 Electricity Supply Commission, 1938 Annual Report, p. 45, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1938%20Annual%20Report.pdf. 150 Electricity Supply Commission, 1940 Annual Report, p. 20, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1940%20Annual%20Report.pdf. 151 Commission, 1943 Annual Report, p. 12; Commission, 1944 Annual Report, p. 47.

- 56 - early 1920s and the outbreak of World War II, while the VFP had been responsible for staffing and operating these stations. This arrangement meant that the VFP did not need to accumulate the substantial capital necessary for building the power stations, and the Commission did not need to worry about the rapid expansion of trade unions and industrial strikes that were taking hold amongst South African workers during the interwar period. It was easier for Escom to find financing for new power stations because of its standing as a state institution, while also selling power indirectly to the mining industry. 152

However, as Nancy Clark has stated, Escom had been given a mandate to supply electricity at low cost and in abundance. Lowering costs through economies of scale was difficult, if not outright impossible, if the parastatal was functioning almost exclusively as “a wholesale producer.”153 In 1947, the last full year in which the VFP was acting as an independent company,

Escom’s bulk sales for mining and municipal resale accounted for 85.1% of the total sales during the year. Of these bulk sales, almost 88% was being sold to the VFP for resale to mining consumers

(see Table 1). The fact that the VFP was the sole bulk mining sales consumers is evident from the

1949 Escom Annual Report, which states that the bulk mining group of consumers was no longer active after July 1, 1948. 154 In essence, almost three quarters of the total electricity generated by

Escom was being sold to consumers at higher prices than if the same number of units had been purchased directly from the parastatal. To shift Escom’s role from that of wholesaler to that of retailer, the Commission needed to eliminate as many intermediaries as possible.155

152 Christie, Electricity, Industry and Class, pp. 114-15. 153 Clark, Manufacturing Apartheid, p. 84. 154 Electricity Supply Commission, 1949 Annual Report, p. 11, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1949%20Annual%20Report.pdf. 155 Christie, Electricity, Industry and Class, pp. 145-7; Clark, Manufacturing Apartheid, p. 84.

- 57 -

Consumer Class Units Sold % of Total

Bulk Sales

Bulk Mining 3 819 269 018 74.7

Bulk Municipal 534 161 654 10.4

Bulk Sales Subtotal 4 353 430 672 85.1

Direct Sales

Traction 454 255 098 8.8

Direct Mining 70 105 747 1.3

Direct Industrial 196 178 295 3.8

Domestic and Street Lighting 40 504 912 0.7

Direct Sales Subtotal 761 044 052 14.6

Total 5 114 474 724 100

Table 1 - Electricity Sales to Classes of Consumer in 1947 156

The Electricity Act of 1922 had given Escom the right to give notice of their intention to expropriate the VFP in 1948, which would allow the parastatal to take ownership of the Company in 1950. Hendrik van der Bijl, the President of the Chamber of Mines, and the Minister of

Economic Development decided instead to give notice of Eskom’s wishes to begin negotiations with the VFP in February 1947. By beginning the negotiations earlier than the Electricity Act allowed, Escom would be purchasing the VFP’s assets, not expropriating the Company outright.157

Van der Bijl had been preparing for the expected expropriation since the VFP and Escom had been planning the construction of the Klip Power Station in 1937. As part of the final

156 Electricity Supply Commission, 1947 Annual Report, p. 17, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1947%20Annual%20Report.pdf. The figures given in the third column add up to 0.3% less than 100, because the individual amounts specified for each class of consumer have been rounded up or down for the sake of readability. 157 "Report of the Commission Upon the Establishment of an Electricity Undertaking: Acquisition of the Undertaking of the Victoria Falls and Transvaal Power Company Limited, and The Rand Mines Power Supply Company Limited," National Archives of South Africa (SAB), HEN 3387, ref. 508.

- 58 - agreement between the two organisations, the Klip station would be the last power station that the

Company would be allowed to operate until expropriation and the installed capacity at existing stations had to remain at 1937 levels. 158

There was a measure of uncertainty about whether Escom could expect to be able to expropriate the VFP in 1945 or 1948, which was caused by the differences between the Transvaal

Power Act of 1910 and the Electricity Act of 1922. The Power Act granted the government permission to expropriate privately owned generating stations and associated infrastructure thirty- five years after the company’s licence had been issued. The Electricity Act of 1922 had changed this time limit to thirty-eight years after the licence was granted, but also specified that the terms governing any licences which had been granted under the previous law were to remain unchanged. 159

To work around this problem, a tripartite series of negotiations were undertaken with representatives from the VFP, Escom, and the Gold Producers’ Committee (GPC) to establish the conditions and amount for which Escom would purchase the VFP. After a protracted process of discussions and compromises that lasted from 1945 until May 1948, the three parties concluded that Escom would pay £14 500 000 for a complete buy-out of the VFP. 160

This purchase added the power stations at Rosherville, Simmer Pan, Vereeniging, and

Brakpan to Escom’s generating system, which granted a cumulative total of 297 600 kW of electrical generating capacity and 117 600 kW of compressed air capacity to the grid. There were also 41 miles (65.9 km) of compressed air pipeline; 711 miles (1 144 km) of power and telephone lines; 1 309 miles (2106.6 km) of transmission power lines; 18 distribution substations; and 918 transformers that were added to Escom’s total generating and transmission system (see Table 2 for a comparison of the size of the national transmission network in 1947 and 1949). 161

158 "H. J. van der Bijl to J. C. Smuts, November 24, 1944," National Archives of South Africa (SAB), HEN 3398, ref. 508. 159 "Expropriation of the Victora Falls and Transvaal Power Company, Ltd," National Archives of South Africa (SAB), HEN 3387, ref. 508. 160 Christie, Electricity, Industry and Class, pp. 145-6. 161 Commission, 1947 Annual Report, p. 9.

- 59 -

Perhaps more noteworthy than what the purchase of the VFP added to the rapidly growing grid is what the purchase signified in political and economic terms. Buying out the assets of the

VFP gave Escom direct access to the vast consumer base of the gold mines in the Witwatersrand and northern Orange Free State. This was important because it allowed Escom to begin reaching its objective of supplying abundant power at low cost to all classes of consumers, and because it meant that the large revenue from selling electricity to the mining houses was no longer going to a foreign company.

Voltages 1947 1949

132kV — 255.05

88kV 957 2 156.82

66kV 0 115.46

40kV 140 576.57

33kV 458 493.19

20/21/22kV 257 475.47

10/11/12kV 372 758.82

2.0/2.2/3.3/6.6kV 523 —

6.6kV — 566.42

3.3kV — 81.14

2.0/2.1/2.2kV — 77.24

480/230V 457 —

525V — 127.52

380/220V — 640.51

Street Lights — 169.24

Totals 3 164 6 508.45

Table 2 - Comparison of Transmission Network Lines and Cables in Miles between 1947 and 1949162

162 Commission, 1947 Annual Report, p. 98; Commission, 1949 Annual Report, pp. 84-88.

- 60 -

Tim Cross states that the purchase of the VFP in 1948 was the defining moment in which

Escom gained a true monopoly over electricity supply in South Africa. It certainly dramatically increased the generating capacity of the parastatal, but Escom was still far from having “complete control over the electricity industry”. 163 In 1958, a decade after the sale, roughly 18 billion units of power were sold throughout the Union, of which Escom had sold about 13½ billion units.164

Escom was definitely generating and selling the lion’s share of power in South Africa, but other suppliers were still generating a quarter of the electricity sold each year.

163 Tim Cross, "The Afrikaner Takeover: Nationalist Politics and the Colonization of South Africa's Parastatals, 1948 to 1960," Institute of Commonwelth Studies' Collected Seminar Papers 48, (1994): p. 125. 164 Electricity Supply Commission, 1958 Annual Report, p. 67, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1958%20Annual%20Report.pdf.

- 61 -

CHAPTER THREE – RAILWAYS, COOKING RANGES, AND RURAL SUPPLIES: ELECTRICITY OUTSIDE OF MINING AND SECONDARY INDUSTRY

When Charles Merz presented the South African government with the 1920 Merz Report on the potential for future electrification, he proposed that the development of local and regional grids should develop alongside the electrification of local railways. The Merz Report recommended that centralised control over the generation of electricity would allow for fewer, more efficient power stations to supply electricity to more than one class of consumer simultaneously. This would, in turn, allow the power stations and their consumers to take advantage of the economies of scale that result from supplying goods and services to a large group of customers. It would also provide opportunities for industry and rural consumers in areas outside of the major metropolitan centres to be supplied with electricity, because the local distribution lines could be linked to the nearby electrified railways.

Figures 4, 5, and 6 show the importance of railway electrification, especially in the earlier phases of Escom’s national electrification plans. For the sake of clarity, any contribution less than

10% of the total is shown in the bar to the side of the pie chart. This makes is easier to see the smaller consumer classes, such as domestic and streetlighting sales. The first aspect of these charts that is noticeable is the dramatic differential in the relative sizes of the contributions by each consumer class, especially between mining, industry, and domestic consumers before 1950.

However, this does not mean that domestic electricity usage was necessarily small during these years, since a portion of the bulk sales was comprised of large purchases by municipalities, who acted as intermediaries between Escom and the ratepayers. In Figure 6, the bulk category exclusively contains municipal bulk purchases, which made up 17% of the electricity sales in 1950.

In 1930, the largest portion of sales went to bulk consumers, with the most significant bulk consumers being the VFP and the municipality of Durban. These two consumers purchased almost

90% of the 701 285 627 units that Escom provided to bulk customers. 165 Traction sales made up

165 Commission, 1930 Annual Report, p. 4.

- 62 - just over 14% of the total sales for 1930, more than direct sales to mining, industrial, municipal, and residential consumers combined.

However, this relative proportion of traction sales in comparison to total sales did not remain as high as these early values. As Figure 7 shows, the percentage that traction sales contributed to Escom’s annual totals declined significantly after the mid-1940s. On this graph, the yellow blocks represent the total number of units sold for railway traction each year, while the black line is the percentage of traction sales relative to the annual total. Even though the number of units sold each year increased steadily, the ratio of traction to total sales declined rapidly after the middle of the century.

Electricity Sales by Category of Consumer, 1930

Domestic and Lighting

Bulk Supplies

Other

Railway Traction Industrial and Mining

Domestic and Lighting Industrial and Mining Railway Traction Bulk Supplies

Figure 4 - Electricity Sales to Category of Consumer in 1930 166

166 Commission, 1930 Annual Report.

- 63 -

Electricity Sales by Category of Consumer, 1940

Domestic and Lighting

Municipal Bulk Industrial Direct Mining Bulk Other Mining Direct

Railway Traction

Domestic and Lighting Mining Bulk Municipal Bulk Industrial Direct Mining Direct Railway Traction

Figure 5 - Electricity Sales to Category of Consumer in 1940 167

Electricity Sales by Category of Consumer, 1950

Domestic and Lighting Bulk Supplies

Other

Mining Direct Industrial Direct Railway Traction

Domestic and Lighting Industrial Direct Mining Direct Railway Traction Bulk Supplies

Figure 6 - Electricity Sales to Category of Consumer in 1950 168

167 Commission, 1940 Annual Report. 168 Electricity Supply Commission, 1950 Annual Report, p. 101, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1950%20Annual%20Report.pdf.

- 64 -

Traction Consumer Sales, 1927-2000 5 000 000 000 25

4 500 000 000

4 000 000 000 20

3 500 000 000

3 000 000 000 15

2 500 000 000

2 000 000 000 10

1 500 000 000

1 000 000 000 5

500 000 000

0 0 1927 1929 1931 1933 1935 1937 1939 1941 1943 1945 1947 1949 1951 1953 1955 1957 1959 1961 1963 1965 1967 1969 1971 1973 1975 1977 1979 1981 1983 1985 1987 1989 1991 1993 1995 1997 1999

Traction (kWh) Traction (%)

Figure 7 - Traction Consumer Sales, 1927-2000 169

Periodic outbreaks of industrial unrest that had extended from the mid-1910s until the Rand

Revolt in 1922 meant that the South African Railways (SAR) were also eager to ensure that private companies were excluded from railway electrification as much as possible, in order to prevent higher charges for power and to have more control over the labourers who were working in the power stations. 170 General Manager of the SAR, William Hoy, was especially interested in taking control of the power stations away from the municipalities, since the staff at municipal power stations had proved more problematic during strikes and other industrial actions than their counterparts at privately owned stations. 171

Electrification of small sections of railways, especially along sections with steep gradients, had already been investigated in 1902, 1904, and 1908, but technology and generating capacity had to catch up to the point where these plans were feasible. Electric traction over these sections

169 Escom Annual and Statistical Reports, 1927-2000. 170 Christie, Electricity, Industry and Class, pp. 75-6. 171 Christie, Electricity, Industry and Class, p. 82; "Electricity Bill," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6, pp. 1-2.

- 65 - was theoretically more powerful and cheaper than steam locomotives, although the purported savings were on labour costs, not on the costs of running the trains. 172 The SAR had already started to implement their plans to electrify the railways between Durban and Volksrust after 1912, but the outbreak of World War I in 1914 meant that the resources intended for this project had to be diverted to wartime production.173

Electrification of the railways also presented the solution to the problem of transporting coal from the mines to power stations for the furnaces and to the harbours for export. According to Escom, coal represented the largest cost involved in generating electricity, thereby making thermal efficiency and fuel transportation costs vital for the economical functioning of a power station.174 The need to balance thermal efficiency and transportation costs was reflected in the design decisions and operational requirements of Escom’s power stations. The coal found in the

Eastern Transvaal typically had a lower caloric value than would have been optimal for use in power stations, since more fuel would have to be burned at the station to produce each unit of electricity, thereby pushing transportation costs up. 175

Escom solved this problem by constructing the power stations in the Rand Undertaking as close to the mines as possible. For power stations that could not be constructed near to the coalface, the coal was sorted according to caloric value, so that these stations would receive coal of sufficient quality. 176 The reality was that these stations, particularly in Natal and the Western Cape, did not always receive the required amount or quality of coal that was required for generating power.

This chapter looks particularly at the early work on electrifying the Natal main line and the railway lines surrounding Cape Town, since these were the first two lines to be electrified after

172 Conradie and Messerschmidt, Symphony of Power, pp. 46-47; Nancy Clark, "South African State Corporations: 'The Death Knell of Economic Colonialism'?," Journal of Southern African Studies 14, no. 1 (October, 1987): p. 182n34. 173 Conradie and Messerschmidt, Symphony of Power, pp. 46-47. 174 "Electrification of Rural Towns and Farms, With Special Reference to the Proposed Sale of the Zwartkops Power Station by the Electricity Supply Commission," National Archives of South Africa (SAB), HEN 3370, ref. 507/1/1, p. 2. 175 The caloric value of a fuel is the amount of energy produced when a fuel is burned in the presence of oxygen, James G. Speight, The Chemistry and Technology of Coal, 3rd ed. (Boca Raton, FL: CRC Press, 2012), p. 49. 176 "Electrification of Rural Towns and Farms," National Archives of South Africa (SAB), HEN 3370, ref. 507/1/1, pp. 2-3.

- 66 -

1922. A report on the proposed electrification of the country’s main railway lines was submitted to Parliament by Merz and McLellan in June 1919, which suggested that the first lines to be electrified should be centred on Cape Town, Witbank, and Glencoe Junction. From this report, the

SAR&H decided to electrify the Natal main line between Durban and Pietermaritzburg and the suburban railway between Cape Town and Simonstown. The decision to electrify the Durban-

Pietermaritzburg section was changed to a scheme to use electricity on the Pietermaritzburg-

Glencoe line, since large amounts of coal were being transported along that section of the Natal main line.177

1. The Cape Railways: Electrification in and around Cape Town

At roughly the same time that Escom and the VFP were negotiating the terms of the

Witbank licence application, the South African Railways and Harbours Administration (SAR) approached Escom to discuss the construction of a new power station in Cape Town to assist with electrifying railway lines in and around the city. The municipality seems to have initially resisted attempts by the fledgling parastatal to build the new power station in the city, but this opposition started to recede during a series of meetings between the Capetown Corporation and Charles Merz, who was one of the official Consulting Engineers to both the city and Escom.

In his dealings with the city, Merz was of the opinion that the city council would reject any plans for Escom to supply electricity to the local railway lines, since this would deprive the municipality of the income that could potentially come from the SAR. 178 It is also possible that the municipality would resist any plans that Escom or the SAR would have suggested for the same reasons that the Johannesburg municipality objected to the VFP’s and Escom’s proposals – namely, that the town council wished to protect its existing contracts with its ratepayers. In either case, Merz was the ideal person to arbitrate between the Cape Town municipality and Escom – the

177 "Report of the Railways and Harbours Board on the Electrification of the Capetown-Simonstown, Monument- Sea Point and Monument-Table Bay Docks (Passenger Service) Lines," National Archives of South Africa (SAB), MNW 785, ref. MM1711/25, p. 2. 178 "Merz to Smuts, November 2, 1923," National Archives of South Africa (SAB), PM 1/2/56, ref. 15/6.

- 67 - report that he had submitted to the South African government in 1920 led to the drafting of the

Electricity Bill in 1921/1922 and had espoused the idea of railway electrification breaking the ground for industrial, mining, and domestic consumption.

Hendrik van der Bijl, as Chairman of the Electricity Supply Commission agreed with the idea that railway electrification should take priority over mining and industry, so much so that he placed higher priority on concluding the negotiations with the Cape Town municipality than he did on finalising agreements with the Rand’s municipal groups. 179 The negotiations with Escom and Merz meant that by April 1924, the Capetown Corporation had granted the parastatal permission to build and operate a new power station on the Salt River, with the express purpose of supplying power to the local railway lines. A year later, in April 1925, when the ECB granted

Escom the licence to operate the Salt River power station, the conditions specified that the station would be allowed to supply all properties and railways within a radius of 110 miles, as well as any customers within 5 miles of the electrified railways. This provision thereby allowed the Salt River power station to supply consumers outside of Cape Town’s municipal borders. 180

2. Railways in Natal: The SAR&H, Escom, and the Colenso Power Station

The SAR&H had started construction on the Colenso Power Station before the establishment of Escom to electrify the main line running between the Rand and Durban. William

Hoy, as General Manager of the Railways Administration, was keen to electrify the country’s railways, because he believed that the electrification of railway lines would encourage the electrification of nearby towns and rural areas. 181 The Natal main line was selected to be one of the first main railway lines in the country to be electrified, because railway traffic in Natal was

179 Clark, Manufacturing Apartheid, p. 79. 180 Commission, 1924 Annual Report, pp. 22-27. 181 Conradie and Messerschmidt, Symphony of Power, pp. 76-77.

- 68 - exceeding the available capacity, and because electrification was believed to be the best available option for upgrading the line.182

Once the Commission had been officially founded in 1923, Escom and the Railways

Administration decided that Escom should expropriate the station from the SAR&H, but only once construction was complete and the station was in full commercial service. This decision was reached at a meeting between the Minister of Mines and Harbours, representatives from Escom and the Railway Board, the General Manager of the SAR&H, and Charles Merz in September

1923. 183

Before the discussions about the terms under which the station would be handed over to

Escom had taken place, customers along the planned railway route were already requesting electricity. Escom felt that these customers should be connected to the grid as soon as possible, because several of the requests were from municipalities that had delayed the necessary upgrades to their local grids while appealing to Escom and the Railways Administration for power. Escom was also of the opinion that these customers should be supplied by the Commission from the outset, stating that customers would not want to enter into initial contracts with one supplier and then have to enter into new contracts at a later stage. 184 The permit to supply these consumers was granted by the ECB in June 1925, but it would take until March 1928 for the plant to reach the stage where

Escom could take over operations. 185 Based on advice from the Consulting Engineers, Escom and

182 "Reports on the Electrification of the Pietermaritzburg-Glencoe Section of the Natal Main Line," National Archives of South Africa (SAB), MNW 785, ref. MM1711/25.@1 183 Commission, 1923 Annual Report, p. 8; "Report of the Commission Upon the Supply of Electricity From the Colenso Power Station (Natal)," National Archives of South Africa (SAB), MNW 785, ref. MM1711/25, pp. 3-4; "W. W. Hoy to Messrs. Merz and McLellan, October 11, 1924," National Archives of South Africa (SAB), SAS 19, ref. ELEC274/12; "Report of the Commission Upon the Acquisition of an Electricity Undertaking at Colenso (Natal)," National Archives of South Africa (SAB), MNW 785, ref. MM1711/25, p. 4. 184 "Report of the Commission Colenso," National Archives of South Africa (SAB), MNW 785, ref. MM1711/25, p. 4. 185 "Forty-First Meeting," National Archives of South Africa (SAB), MNW 634, ref. MM 2879/22, pp. 1-2; "Minutes of the Forty-Seventh Meeting of the Board," National Archives of South Africa (SAB), HEN 3370, ref. 507/1/1, p. 1.

- 69 - the SAR&H agreed that the Commission should not only take over plant operations, but that all employees at the power station would be transferred to Escom at the same time.186

By the end of 1925, it was clear that the installed equipment along the section of rail between Pietermaritzburg and Glencoe Junction was already being overwhelmed with the demand imposed by railway traffic. The Pietermaritzburg-Glencoe section of the Natal main line had been designed to handle a maximum of 30 000 tons of rail traffic per day along the southbound parts of the line, and it was expected that traffic on that section of the railway line in 1926 would reach an average of 27 000 tons per day. 187 These figures were based on year-long estimates of average railway usage, during which the expected traffic would remain relatively steady between January and July, increase during the annual maize harvest season between August and November, and then decrease back to pre-harvest levels for December.

From the estimates given by the SAR&H, it was likely that the average load would only increase above the 30 000 tons per day mark in late 1928. However, the Administration also cautioned that estimates of daily averages could be deceptive, because the load could increase substantially above average during the course of a single day. 188 Calculations by the Railways

Administration showed that these once-off increases in daily traffic during the peak season could push the system past its limits as early as 1927. 189

Merz and McLellan, as the Consulting Engineers working on the construction of the

Colenso Power Station, recommended that relatively minor alternations be made to the power plant to meet the increased railway traffic. The alterations would include two extra boilers at the power station, one extra substation along the section of railway line, and one transmission line to

186 "Merz and McLellan to William W. Hoy, January 27, 1924," National Archives of South Africa (SAB), SAS 19, ref. ELEC274/12; "A. C. McColm to W. W. Hoy, January 23, 1924," National Archives of South Africa (SAB), SAS 19, ref. ELEC274/12; "W. W. Hoy to A. C. McColm, February 27, 1924," National Archives of South Africa (SAB), SAS 19, ref. ELEC274/12. 187 "Merz and McLellan to General Manager South African Railways and Harbours, November 5, 1925," National Archives of South Africa (SAB), SAS 19, ref. ELEC170/1; "W. W. Hoy to Assistant General Manager, December 10, 1925," National Archives of South Africa (SAB), SAS 19, ref. ELEC170/1. 188 "J. R. More (Assistant General Manager) to W. W. Hoy, January 27, 1926," National Archives of South Africa (SAB), SAS 19, ref. ELEC170/1. 189 "J. R. More (Assistant General Manager) to Messrs. Merz and McLellan, May 12, 1926," National Archives of South Africa (SAB), SAS 19, ref. ELEC170/1.

- 70 - link the new substation to the transmission network that powered the Pietermaritzburg-Glencoe line. This recommendation was based on lower estimates of average daily traffic, not on the higher estimates that the SAR&H had given for the maximum expected daily traffic during peak season.

The Chief Mechanical Engineer suggested that the renovations suggested by Merz and McLellan should proceed, but that the buildings at Colenso should be retrofitted to make space for extra boilers that could then be added to the station after Escom had taken control of the station. 190

Escom agreed with these proposals and decided to upgrade the power plant at Colenso.

Extra space was added for up to four new boilers in the boiler house; two new boilers were installed to increase the station’s generating capacity; and the Willbrook substation between

Pietermaritzburg and Glencoe was upgraded to increase the capacity of the transmission network. 191

In June 1931, the Colenso Power Station, with Escom’s blessing, embarked on a scheme to replace unskilled black workers with roughly half the number of white workers. 192 With this plan,

Escom faced the problem that white labourers were typically expected to earn higher wages, but the plan was ostensibly designed to ensure that operating costs at the power station did not increase with the addition of extra white workers. 193 The need to balance operational costs with higher wages is, in all likelihood, the reason for Escom’s choice to employ fewer white workers in these unskilled roles. From the outset, Escom stated that the experiment (and any similar labour policies) would depend on the economic viability of white labour. 194

For their part, some of the white workers objected to the types of jobs that they were expected to perform, which required the plant’s managers to take “…strong disciplinary action”

190 "Messers. Merz and McLellan to General Manager, May 6, 1926," National Archives of South Africa (SAB), SAS 19, ref. ELEC170/1; "F. R. Collins (Chief Mechanical Engineer) to General Manager, July 12, 1926," National Archives of South Africa (SAB), SAS 19, ref. ELEC170/1. 191 Commission, 1926 Annual Report, pp. 8-9. 192 "White Labour Policy: Colenso Power Station," National Archives of South Africa (SAB), TES 7996, ref. F103/13. 193 "H. J. van der Bijl to A. P. J. Fourie, May 16, 1932," National Archives of South Africa (SAB), TES 7996, ref. F103/13. 194 Commission, 1930 Annual Report, p. 15.

- 71 - by firing two workers who refused to do the work. The station’s manager was pleased to report that this had seemed to change the remaining workers’ attitudes towards the nature of their jobs, but also stated that he felt that the Commission should not replace all black labourers with white counterparts, because the local climate in Natal “…during the summer may preclude white men from doing work such as boiler cleaning, ash handling, etc.”195

3. The Cape Rural Supply System

Rural areas in the Cape Western Undertaking were supplied by the same power station at

Salt River that supplied electricity to the SAR&H. The Salt River Power Station had been built to supply the SAR&H, as had been recommended by Charles Merz, but also included another design that Merz had suggested during his discussions with the Capetown Corporation – Escom’s Salt

River power station and the Cape Town municipal station at Dock Road were to be interconnected to share a common distribution network. Rather than the piecemeal system which existed on the

Rand, where conflict between Escom, the VFP, and municipalities slowed the process of interconnection, the system in Cape Town allowed both power stations to supply their own consumers, while also offering backup capacity during times of high demand at either station.196

This interlinked system would also provide Escom the benefit of taking on new consumers, even while the Salt River station was under construction. Any power supplied by Escom before the station was in commercial operation was purchased from the Dock Road power station and resold to Escom’s consumers.

By the start of 1925, the demand for electricity in the areas surrounding Cape Town’s municipal area of supply had risen sufficiently to allow Escom to begin investigating the possibility of supplying electricity outside of the municipal borders. In order to receive supply of

195 "White Labour Policy," National Archives of South Africa (SAB), TES 7996, ref. F103/13, p. 2. 196 Commission, 1924 Annual Report, p. 25. Conradie and Messerschmidt state that the interconnection between the two stations was only functional in 1934, see Conradie and Messerschmidt, Symphony of Power, pp. 87-88, however the link seems to have been established well before that date. Escom’s annual reports had stated that the interconnection had been in operation since at least 1929, see Commission, 1929 Annual Report, p. 29.

- 72 - electricity, these consumers had to agree to minimum monthly quotas, so that the scheme would remain economically viable. A large percentage of the decisions that Escom made regarding consumers outside of municipal areas were guided by a condition in the Electricity Act of 1922, which stated that “…undertakings shall, as far as practicable, be carried on neither at a profit nor at a loss.” The financial implications of having to continually break-even were further complicated by the following section, which said that the finances of all undertakings had to be calculated separately, thereby making it impossible to use the profit made by one undertaking to write off the loss of another. 197

The parastatal was given some leeway by the clause that said that the finances had to balance “as far as practicable,” but in practice, the Commission was generally unwilling to take on electrification schemes that could have caused a loss. Despite this, the risk that Escom took on the

Cape’s rural supply grid certainly paid off. In 1926, the first year that the Cape Rural Supply

Scheme sent power to industrial and municipal consumers, they sold 280 242 units; by 1928, the rural consumers used 9 767 699 units annually; and demand in 1929 reached 11 231 658 units.198

The Cape Rural Supply Scheme benefitted from the higher population density in the areas outside of Cape Town compared to similar regions in the Transvaal and Orange Free State. The larger populations had larger demands for electricity, and the industrial consumers in the south- western Cape were willing to use relatively large quantities of electricity. The region also had the advantage that several smaller municipalities, such as Wellington and Somerset West were applying to Escom for electricity but could not be supplied by the Capetown Corporation’s Dock

Road power station.

197 Government Gazette of 24 July, 1922, vol. 44, no. 1256, p. lxxiii. 198 Commission, 1929 Annual Report, p. 31.

- 73 -

4. Requesting Rural Electricity Supply: The Boere-Lig-en-Krag (Ko-Operatief) Beperk and the Electricity Control Board

The Boere-Lig-en-Krag (Ko-Operatief) Beperk (BLK) approached Escom and the Pretoria

Municipality in July 1948 to request that either of the government bodies allow farmers and households in the region of Brits, to the north-east of Pretoria, to interconnect with the regional grid. The city of Pretoria and Escom had both given provisional approval to the scheme, on the condition that the BLK was given official permission by the ECB. 199 The BLK was not the only organisation requesting a supply of electricity to a rural area after World War II, but their process of applying for the rights to interconnect with the local Escom grid is better documented than most applications of the time. The remaining surviving letters and documents in the South African

National Archives in Pretoria offer a look at the procedure that such organisations had to follow, as well as allowing for an examination of the reasons why the Electricity Control Board chose to reject or approve these requests.

In the period during and after World War II, Escom was increasingly constrained by materials and labour shortages, while the demand for electricity amongst all categories of consumers was increasing dramatically – the total installed capacity of all Escom’s power stations had doubled during the decade immediately after the War’s end, while ongoing construction projects were still adding extra capacity. 200 Despite the fact that Escom had built seven new power stations between 1945 and 1955, the parastatal was still having difficulty in keeping up with demand. 201 Aside from these difficulties, Escom also displayed an overall reticence to supply electricity to “sub-economic” electrification schemes, which were plans that would not be able to adhere to the principle of making neither profits nor losses on electricity sales.

199 "Minutes of the 198th Meeting of the Electricity Control Board," National Archives of South Africa (SAB), HEN 3371, ref. 507/1/1, p. 6; "W. H. Milton to Electricity Control Board, July 5, 1948," National Archives of South Africa (SAB), ECB 4, ref. 24. 200 Electricity Supply Commission, 1955 Annual Report, pp. 7-10, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1955%20Annual%20Report.pdf. 201 Electricity Supply Commission, 1954 Annual Report, p. 7, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1954%20Annual%20Report.pdf.

- 74 -

Mostly, the electrification of rural areas would involve lengthy transmission lines and expensive transformers on farms and in towns to convert the high-voltage electricity into useable current for mechanisation and domestic use. Escom was unwilling to subsidise these types of plans, even when under political pressure from figures such as Jan Smuts.202 As such, the BLK had assurances from the Pretoria Municipality that would include a loan of £100 000, in order to assist the organisation in setting up a small grid around Brits. Agriculture in the area to the south of Brits focused mainly on the growing of tobacco, which needed to be dried before the produce was marketable. On farms without electricity, the drying of tobacco was performed using the heat generated by burning coal, which the local farmers’ associations felt was “…injurious and wasteful…” and that using so much coal for the drying process was “damaging to soul, mind and body.” 203

In the case of the rural areas around Brits and Rustenburg, electricity was being presented as more than a technological change. Part of the argument was that the technological change from heat generated via combustion to heat generated by electricity would make the work on these farms less labour-intensive and more cost efficient, but there was also the implication that the working environment itself would be profoundly more wholesome. Even though the “injurious and wasteful” coal will still have to be burned at the power station to generate the electricity, it seems that there is a connotative difference, at least for the farmers’ associations, between the rural and urban environments.

The ECB reviewed the initial request from the BLK, and gave provisional approval for the scheme, providing that the city of Pretoria, Escom, and the BLK gave further details on the costs and statistics involved in establishing the scheme. Pretoria, however, was having difficulty in being able to justify the £100 000 loan to the farmers, since the Provincial Ordinance of 1939 prevented them from being able to use municipal funds for public works projects outside of their municipal

202 Clark, Manufacturing Apartheid, p. 158. 203 "Explanation of the Objects of the Proposed Boere-Lig-en-Krag (Ko-Op) Beperk," National Archives of South Africa (SAB), ECB 4, ref. 24, p. 2.

- 75 - borders. When informed about the Pretoria Municipality’s resolution to help the BLK, the

Provincial Administrator had queried the legality of the loan, leading the city to request that an amendment be made to the Provincial Ordinance that would allow the Town Council to provide this loan.204

When the report on the proposed scheme was submitted to the ECB, the Board voiced concern over the area of supply that the BLK intended to cover. The area demarcated by the scheme’s planners was problematic because it was partially within the area of supply covered by the Pretoria Municipal licence; partially within Escom’s licence for the Undertakings on the Rand, and partially outside of any licenced area. The councillors in Pretoria had already told the Board that they had no intent of supplying current directly to the consumers in the area, but instead would willing to sell bulk power to any organisation which wanted to supply power to these rural regions. 205

On the other hand, Escom was opposed to the suggestion that a piece of the Rand Extension

Undertaking be ceded to another organisation but stated that the Commission would be willing to allow the BLK to supply power within that small section of the Undertaking. The Board decided to notify the farmers’ associations of Escom’s conditions that would allow for the local grid to be built.206

At this point in May 1939, the BLK seems to have no further direct correspondence with the ECB about the licence application. It is not certain whether they opted to request direct supply as domestic consumers from the Pretoria Municipality, or whether they requested supply from

Escom through the Rand Extension Undertaking. It is possible that Escom would agree to supply the farms in the Brits area, since the 1949 Annual Report mentions that the Rand Undertaking was

204 "Proposed Bulk Supply of Electricity and Loan to Boere-Lig-en-Krag (Ko-Operatief) Beperk," National Archives of South Africa (SAB), ECB 4, ref. 24; "Borrowing Powers: £100, 000: For Loan to Boere-Lig-en-Krag (Ko-Operatief) Beperk," National Archives of South Africa (SAB), ECB 4, ref. 24. 205 "Minutes of the 200th Meeting of the Electricity Control Board," National Archives of South Africa (SAB), HEN 3371, ref. 507/1/1, pp. 3-4. 206 "Minutes of the 205th Meeting of the Board," National Archives of South Africa (SAB), HEN 3371, ref. 507/1/1, pp. 3-4.

- 76 - going to be extended in the direction of Rustenburg to offer supply to the South African Iron and

Steel Corporation (Iscor) in the vicinity of Thabazimbi.207

Not only do these microhistories, such as the story of the BLK, help to show more of the otherwise hidden processes that were taking place behind the visible appearance of electricity distribution networks, but they also show how the grid was taking shape. Each time that a community was granted or denied access to Escom’s network, the area of supply would slightly change shape. It is these small changes that turned the perfectly circular licenced areas in Escom’s

1929 map (Figure 1) into the amoebic blobs in the corresponding 1944 map (Figure 2).

5. Electricity and the Domestic Sphere: Appliance Hire-Purchase Plans and Advertising

The Johannesburg Municipality had been trying to encourage the use of domestic appliances since 1911 by adjusting tariffs to lower the rates paid by residential consumers – which the Star newspaper called “Good News For Housewives.” The problem with incentivising the use of domestic electricity in this manner was that the wiring in most houses could not handle the extra current required for cooking food. Early household connections had been designed and installed to supply power for domestic illumination, and the concurrent use of appliances and lighting fixtures would increase the amount of current flowing through the household wiring dramatically.

To avoid the potentially dangerous overloading of residential connections, people were advised to keep all lighting fixtures turned off while domestic appliances, such as stoves and irons, were in use. Residents were also required to inform the Electricity Department of the Municipality which extra appliances they intended to use or face the penalty of having their electricity supply disconnected. 208

Rural electrification across the country after 1930 was hindered by the Great Depression,

World War II, and post-war shortages of materials and labour. During the Depression, the annual

207 Commission, 1949 Annual Report, p. 42. 208 "Cheaper Current: Cooking by Electricity," The Star, June 26, 1911.

- 77 - growth in demand slowed slightly, but electricity was less affected by the economic downturn than other sectors in the economy. Escom attributed the continued increase in demand to the changing social norms, as it seemed that South Africans in both urban and rural environments were starting to see electricity as a key component of improving living conditions. This is attested to by the continued success of Escom’s hire-purchase schemes for domestic appliances. The undertakings at Witbank, Colenso, and Salt River had initiated a scheme whereby consumers who used power from those stations could purchase cooking ranges, refrigerators, water heaters, and small appliances 209 on credit through Escom.

The sale of domestic appliances was important enough for Escom to dedicate a permanent display of “approved appliances” in the Hall of Achievement at Escom House in central

Johannesburg. Customers interested in purchasing appliances would be able to browse through the appliances that Escom had deemed good examples of domestic appliances, which the Commission hoped would guide and promote the use of domestic electricity. 210 A municipal counterpart to this was opened by the Johannesburg Municipality on April 1, 1939. 211

By-and-large, the Cape Undertaking sold the most appliances on an annual basis, with cooking ranges being the most popular items on sale. Until December 31, 1940, the Cape

Undertaking had sold almost ten times more ranges than the Witbank Undertaking, but direct comparisons between the two undertakings are difficult to make, because of the vast differences in their consumer bases. In 1940, the power station in Witbank sold 1 593 028 units of generated power directly to consumers for lighting and domestic purposes, which equated to approximately one-tenth of one percent of the total power generated at the station. By comparison, the Salt River

Undertaking had sold 10 721 104 units to lighting and domestic consumers. 212

209 Escom did not specify which appliances were categorised as “miscellaneous small appliances,” although they were distinguished from washing machines, refrigerators, water heaters, and cooking ranges. 210 Commission, 1936 Annual Report, p. 13. 211 "Electricity Showroom Opened," Rand Daily Mail, April 1, 1939. 212 Commission, 1940 Annual Report.

- 78 -

Comparisons between the power stations are further complicated by the distinctions made between different classes of consumers. For instance, Escom typically did not distinguish between bulk purchases by companies like the VFP and those made by municipalities for domestic purchases – bulk purchases were typically consolidated as a single category in the yearly statistics before the late 1940s.

The hire-purchase schemes in larger urban areas were typically run by the individual municipalities, rather than by the Escom-owned undertakings in the region, but the principles behind these plans were the same. The split between Escom and the municipalities makes it difficult to assess how rapidly electrical appliances transferred into the domestic sphere, since the annual reports only gave the figures for appliances sold by Escom.

What can be ascertained is how social groups in Johannesburg related to the use of hire- purchase schemes to sell domestic appliances, as per the discussion on relevant social groups in

Pinch and Bijker. 213 The municipality comprises the first group as the electricity suppliers, who wanted to increase the demand for electricity by selling appliances to their consumers. The suppliers did not want to increase demand for the sole purpose of increasing income but were also interested in managing the load on their power stations by minimising the variations between peak and average demand on the stations.

Demand would typically increase during the working day, then decrease as businesses and industries closed during the night. By promoting the use of electricity in the home, especially during the evening hours, the suppliers hoped to increase the demand on their power stations, thereby negating at least some of the downturn in demand. Higher overall demand would also make the power stations more efficient, since the stations would be burning extra fuel to meet the increasing demand as the working day began again. The increase in the use of domestic appliances did result in a commensurate increase in the consumption of electricity – by the middle of World

War II, increased demand and the lack of machinery for power station upgrades meant that The

213 Pinch and Bijker, "Social Construction of Facts and Artifacts," in Bijker, Hughes, and Pinch, Social Construction of Technological Systems, pp. 22-28.

- 79 -

Cape Times had to publish an article telling housewives how to tell which appliances in the kitchen used the most electricity and how to conserve energy. 214

The second group is made up of appliance retailers who were not part of the hire-purchase plans, who objected to the financial terms of the agreements between the municipality and the hire- purchase customers. The hire-purchase customers form the third group; from their correspondence in the newspapers at the time, this group seems to have been mostly from lower income middle class and working-class households in the city who wanted to take advantage of the financial benefits of municipal hire-purchase plans.

The appliance retailers did not object to the principle of the hire-purchase scheme, since the municipalities had initially started off by purchasing the appliances wholesale from the retailers, which allowed the municipality to buy at reduced costs. The appliances were then resold to consumers within the municipality at lower rates than if they had purchased the goods in smaller quantities from the retailers. However, the friction between the retailers and Johannesburg

Municipality started to increase when retailers felt that their profits were being adversely affected by the hire-purchase plan rules. Initially, customers would select appliances in the stores operated by participating retailers; the retailers would sell these appliances to the municipality; the municipality would then resell the goods to the customers at a specified rate. The new rules that the municipality wanted to enforce from the middle of 1940 onwards stated that the municipality would buy all goods wholesale, then resell the appliances to their customers with a 10% mark-up that would cover administrative costs. 215

The Johannesburg Chamber of Commerce told the Municipality that this would cause a fundamental change in the relationship between the Municipality and the retailers, since they would no longer be cooperating, but would be in competition with each other. The Chamber believed that this would negatively affect businesses in the city, which would lead to reduced

214 "Anti-Waste in the Kitchen," Cape Times, February 3, 1942. 215 "Electrical Appliances: Council Scheme Opposed," The Star, December 19, 1940; "Municipal Trading," The Star, December 20, 1940; "Opposition to City Instalment Scheme," Rand Daily Mail, December 20, 1940.

- 80 - income in the form of rates from businesses; and that the plan could potentially ruin long-running businesses in the city. 216

A letter to the editor in the Star during December 1940 gave attention to one aspect of the new hire-purchase agreements that had not been previously discussed – the issue of where the

Municipality got the money to cover their overheads on the hire-purchase plans. The writer noted that businesses in Johannesburg needed to apply a 45% mark-up on electrical goods to cover their running costs, whereas the Municipality would only be applying a 10% mark-up on goods purchased through hire-purchase. This implied, stated the letter’s author, that the Municipality would be required to make up for this rather large 35% difference in pricing by using revenue accrued from other ratepayers. 217“Ratepayer” also asked why the Municipality was so intent on providing easier access to specific types of commodities.218 The Municipality had based their counter-argument to the Chamber of Commerce and the retailers on opposition to the prices of imported goods in the city’s shops. 219

In socio-economic terms, this represents a continuation of the municipal socialism evident in the fight for the “right to supply” that the Johannesburg Municipality had been engaged in with

Escom and the VFP since the turn of the century. In this case, the dispute was not over who would be providing the electricity, but who would be providing the means for the consumers to use the electricity. The Municipality had already gained the right to supply their ratepayers, despite their apparent inability to keep up with demand over time; the electrical retailers believed that the city wanted to take control of the domestic appliance market in 1940. 220

216 "Electrical Appliances: Council Scheme Opposed," The Star, December 19, 1940. 217 Ratepayer [pseud.], "Municipal Trading: Robbing Peter to Pay Paul," The Star, December 31, 1940. 218 Ratepayer [pseud.], "Municipal Trading: Robbing Peter to Pay Paul," The Star, December 31, 1940. 219 "Municipal Trading," The Star, December 20, 1940; Interested [pseud.], "Electrical Appliances," The Star, December 23, 1940; Working Man [pseud.], "Council's Hire-Purchase Scheme," The Star, December 23, 1940; Householder [pseud.], "City Trading: Domestic Electrical Appliances," The Star, December 24, 1940; Suspicious [pseud.], "Electrical Appliances," The Star, December 27, 1940. 220 "Municipal Trading," The Star, December 20, 1940; "Opposition to City Instalment Scheme," Rand Daily Mail, December 20, 1940; Veritas [pseud.], "Threat to Commerce: Council's Trading Scheme," The Star, December 28, 1940.

- 81 -

The use of electricity for lighting and cooking was advertised through the cooking demonstrations that Escom and the municipalities held in their appliance showrooms, and through public spectacles in large urban centres. Renfrew Christie mentions that labour recruiters for

Kimberley’s diamond mines in the early 1880s found that the installation of streetlights drew people in from rural areas, thereby making the recruitment of black labourers easier. When Durban held celebrations for Queen Victoria’s Diamond Jubilee in June 1897, the newly installed streetlights were turned on for the first time as part of the festivities. 221 The “Tower of Light,” which still stands on the Western Campus of Wits University, was built through the co-operative efforts of Escom, the VFP, and the Pretoria Portland Cement Company for the Empire Exhibition of 1936 in Johannesburg. 222

The provision of electricity to residential consumers highlights one of the obvious discrepancies in both the eras of segregation and apartheid, namely the uneven distribution of services amongst the country’s various racial groups. Provision of residential connections to all consumers would have meant greater overall loads and faster growth in the residential sector.

However, the fastidious commitment to separate development kept municipal and governmental services outside of the areas that were designed as “non-European” for far longer than even the nominally working class white areas. The expansion of the grid into the townships, especially after the end of the 1980s is seen clearly in Figure 8, which shows the relationship between the total sales in domestic sales and the relative percentage that these sales contributed to the overall annual total. Unlike Figure 7, which shows a decline in the contribution of traction sales each year, the domestic and streetlighting sales begins to increase rapidly and fairly consistently after 1990. This coincides with the beginning of Eskom’s first serious efforts to grant electricity supply to black residential consumers.

221 Vivian Bickford-Smith, The Emergence of the South African Metropolis: Cities and Identities in the Twentieth Century (Cambridge: Cambridge University Press, 2016), p. 70. 222 Commission, 1936 Annual Report, p. 11; Jennifer Robinson, "Johannesburg's 1936 Empire Exhibition: Interaction, Segregation and Modernity in a South African City," Journal of Southern African Studies 29, no. 3 (September, 2003): pp. 770-2.

- 82 -

The sales of electricity to domestic consumers constituted a relatively small, but vital, part of the growth of the National Grid. Between 1948 and 1994, electricity was an important signifier of racialised social status within the apartheid system. At the period of transition during the early

1990s, the expansion of electricity grids for domestic use into the townships and black rural households hinted at the shifts that were occurring in governance at the national level. Electrical lighting and appliances underwent a change from being signifiers of the inequalities in society to being signifiers of the level and pace of change. The provision of electricity to households has somewhat normalised electricity, so that it has become a key part of the list of services that the national and municipal governments are expected to provide to all South African citizens, on a par with running water and healthcare.

Domestic and Streetlighting Sales, 1927-2000 7 000 000 000 4

6 000 000 000 3.5

3 5 000 000 000

2.5 4 000 000 000 2 3 000 000 000 1.5

2 000 000 000 1

1 000 000 000 0.5

0 0 1927 1929 1931 1933 1935 1937 1939 1941 1943 1945 1947 1949 1951 1953 1955 1957 1959 1961 1963 1965 1967 1969 1971 1973 1975 1977 1979 1981 1983 1985 1987 1989 1991 1993 1995 1997 1999

Domestic and Lighting (kWh) Domestic and Lighting (%)

Figure 8 – Domestic and Streetlighting Sales, 1927-2000 223

223 Escom Annual and Statistical Reports, 1927-2000

- 83 -

CHAPTER FOUR – “RESOURCE CONSTRAINTS AND THE NATIONAL INTEREST”: NUCLEAR POWER, BANTUSTANS, TOWNSHIPS, AND LINKING THE NATIONAL GRID, 1960 – 2000

This final chapter is intended to cover the final forty years of the twentieth century, during which the Electricity Supply Commission took the final steps to completing the National Grid.

The early 1960s make an ideal starting point for examining the last phase in the process of nationalising the country’s electricity supply. Increasing local and international opposition to apartheid placed the South African government under increasing pressure to change the country’s political system, pressure from which state-owned organisations were not immune. Not for the first time, electricity infrastructure in South Africa was subject to sabotage attempts at various points between the 1960s and the early 1980s.

At the start of the decade, the six large regional areas of supply covered by Escom’s grid were not fully interconnected, especially in the country’s interior. Each of these large areas of supply consisted of a regional grid, known as an Undertaking, which pooled the power supply from Escom’s power stations in that region. There were particularly large gaps between the

Undertakings in the southern part of the Orange Free State and northern Cape provinces, and urban areas such as Bloemfontein and Port Elizabeth were not yet linked into the National Grid. Instead, these cities still relied entirely on the supply from municipal power stations.

The beginning of the 1960s also marks the period when Escom began to investigate the feasibility of nuclear energy for electricity generation. The Atomic Energy Board (AEB) had been established in 1948 with the passing of the Atomic Energy Act (Act 35 of 1948) and was given similar mandates to those handed to Escom and the Electricity Control Board in the Electricity Act of 1922. The powers granted to the AEB, however, were shaped by the nuclear nature of the board’s work. The AEB was charged with overseeing the mining, extraction, processing, sales,

- 84 - and use of nuclear materials in South Africa, as well as being granted the legal rights to supervise, approve, or restrict patent applications in the field of nuclear technology. 224

During the second half of the century, the political shifts in the country also required Escom to start planning to extend electricity supplies outside of the exclusively white urban areas. A report from 1961 states that in Natal,

“In so far as the consumption of electricity is concerned, Europeans are the

only significant consumers, although within the last ten years increasing

number [sic] of Indians and Coloureds within the Durban Borough have

become consumers. Native consumption for domestic purposes is virtually nil,

only one small township at Chesterville with 1, 200 houses, plus a small

number in Lamontville having been connected to the system.”225

The same report also mentions that the plans for electrification in the townships around

Johannesburg was expected to cost £2 500 000 over the next years, and the report notes, with a curious hint of optimism that the forced removals in areas such as Sophiatown would result in

“greatly increasing loading in an extensive area, hitherto electrically undeveloped.” 226 These plans for extending the grid outside of white-owned residential areas seem to have not been implemented for some time, since newspaper articles in the mid-1970s still reported that Soweto residents were trying to secure government approval and finances to establish the grid.

A large part of this chapter covers the nuclear aspect of the National Grid. It would be impossible to entirely extricate any writing about the Koeberg Nuclear Power Plant from the political or environmental aspects of the larger anti-/pro-nuclear debate. Likewise, there is a duality inherent in any discussion of nuclear power that links the ostensibly peaceful use of radiation for electricity generation or medicine to images of mushroom clouds over cities. These

224 Government Gazette of 9 September, 1948, vol. CLIII, no. 4022, pp. vi-xxxi. 225 Report of the Commission of Enquiry into the Application of Nuclear Power in South Africa, p. 8. 226 Report of the Commission of Enquiry into the Application of Nuclear Power in South Africa, p. 12.

- 85 - environmental, political, and military uses of nuclear energy are co-joined to the generation of electricity, but the discussion of Koeberg as a part of the National Grid is still somewhat lacking.

The existing published work on nuclear energy in South Africa focuses almost exclusively on the

South African bomb project, uranium enrichment, the Vela incident, speculation on the international origins of South Africa’s nuclear technology, and safety issues in nuclear power plants.227 Instead, this chapter is intended to present the Koeberg Nuclear Power Plant as a significant, although controversial, addition to the more mundane process of electrifying South

Africa.

1. Completing the Interconnections: Connecting the National Grid

At the start of the 1960s, Escom still had not established the full set of interconnections that would create the National Grid. The six Undertakings, mostly clustered around the northern half of the country, were not fully capable of sharing power. The Cape Western Undertaking, which had been the basis for the formation of the Cape Rural Supply System, was particularly worrisome for Escom. Haulage on coal accounted for large differences in the running costs at Escom’s power

227 David Albright, "South Africa Comes Clean," Bulletin of the Atomic Scientists 49, no. 4 (May, 1993): pp. 3-5; David Albright and Corey Gay, "A Flash from the Past," Bulletin of the Atomic Scientists 53, no. 6 (November/December, 1997): pp. 15-17; Edwards and Hecht, "History and the Technopolitics of Identity," pp. 619- 39; David Fig, Uranium Road: Questioning South Africa's Nuclear Direction (Johannesburg: Jacana, 2005); Fig, "Price Too High," in McDonald, Electric Capitalism, pp. 180-201; Verne Harris, Sello Hatang and Peter Liberman, "Unveiling South Africa's Nuclear Past," Journal of Southern African Studies 30, no. 3 (September, 2004): pp. 457- 75; Gabrielle Hecht, "Negotiating Global Nuclearities: Apartheid, Decolonization, and the Cold War in the Making of the IAEA," Osiris 21, no. 1 (2006): pp. 25-48; Gabrielle Hecht, Being Nuclear: Africans and the Global Uranium Trade (Cambridge, Massachusetts: MIT Press, 2012); Zondi Masiza, "A Chronology of South Africa's Nuclear Program," Nonproliferation Review 1, no. 1 (Fall, 1993): pp. 34-53; Jeffrey T. Richelson, Spying on the Bomb: American Nuclear Intelligence from Nazi Germany to Iran and North Korea (New York: W. W. Norton, 2007); Anna-Mart van Wyk, "South Africa's Nuclear Programme and the Cold War," History Compass 8, no. 7 (2010): pp. 562-72; Anna-Mart van Wyk, "Apartheid's Atomic Bomb: Cold War Perspectives," South African Historical Journal 62, no. 1 (2010): pp. 100-120; Jo-Ansie van Wyk and Anna-Mart van Wyk, "From the Nuclear Laager to the Non-Proliferation Club: South Africa and the NPT," South African Historical Journal 67, no. 1 (2015): pp. 32- 46; Jo-Ansie van Wyk, "Nuclear Terrorism in Africa: The ANC's Operation Mac and the Attack on the Koeberg Nuclear Power Station in Africa," Historia 60, no. 2 (November, 2015): pp. 51-67; Martha van Wyk, "Sunset over Atomic Apartheid: United States-South African Nuclear Relations, 1981-93," Cold War History 10, no. 1 (February, 2010): pp. 51-79; Martha S. van Wyk, "Ally or Critic?: The United States' Response to South African Nuclear Development, 1949-1980," Cold War History 7, no. 2 (May, 2007): pp. 195-225.

- 86 - stations – in 1960, a short ton (2 000 lbs., roughly 907 kilograms) of coal cost 10s. 7d. at Witbank, while Salt River in Cape Town was paying 48s. 4d. for the same quantity of fuel. 228

The Coalbrook Colliery shaft collapse in 1960 had also sent a stark reminder to the parastatal of how vital a consistent supply of coal was for the running of the power stations. In accordance with the existing policy of constructing power stations on or near to coalfields, the

Taaibos and Highveld stations had been built near to Sasolburg in the Orange Free State to make use of the nearby coalfields. On January 21, 1960, a shaft collapse at the Coalbrook North Colliery killed 437 miners and cut off all supplies of coal to the Taaibos Power Station.229 Operations at the South Colliery, which provided coal for the Highveld Power Station, were able to continue, but the North Colliery was closed until late February 1960. Escom had to start diverting the load on the Taaibos station to as many other stations as possible, while also making arrangements for emergency supplies of suitable coal.

The Coalbrook collapse resulted in the re-examination of working conditions in coalmines throughout the southern and eastern Transvaal areas. The investigation into mine safety led to the temporary closure of the Vierfontein Colliery’s East Shaft and both collieries at Coalbrook. The

Taaibos and Highveld stations were only able to resume normal operations after April 1960.230

Coal prices at the Highveld and Vierfontein stations were almost unaffected by the interruptions in coal mining during 1960, but the average price per pound of coal at Taaibos was double that of

1959. 231

This increase can be attributed to the way that organisational, technological, and design choices were made at Escom in the years leading up to the Coalbrook disaster. The power stations in the Transvaal and Orange Free State were typically placed as closely as possible to the

228 Electricity Supply Commission, 1960 Annual Report, p. 10, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1960%20Annual%20Report.pdf. 229 This disaster also helps to highlight the racial disparity in the subterranean workforce during this period. Of the 437 miners who were killed in the collapse, only 6 of the casualties were white, Conradie and Messerschmidt, Symphony of Power, p. 121. 230 Electricity Supply Commission, 1959 Annual Report, p. 9, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1959%20Annual%20Report.pdf; Christie, Electricity, Industry and Class, pp. 163-4. 231 Commission, 1960 Annual Report, p. 66.

- 87 - coalmines that were contracted to supply fuel. Such stations were also designed to work most efficiently with the specific grade and type of coal that would be supplied by the contracted mines, which made it extremely difficult to haul coal in from other areas when the fuel supply was interrupted.

Some of the features of the tragic mine collapse were beyond Escom’s control, such as the geological features of the northern Orange Free State that made the coal so easily available, while other factors were entirely within the organisation’s control, such as power station design. It is the way in which these environmental and organisational factors overlapped and interacted with each other that created a unique problem for Escom. If, for instance, the power stations had been capable of burning a wider variety of coal types, it would not have been as difficult to find suitable replacement fuel for the stations. After the Coalbrook mining disaster, Escom started to design newer power stations to be more impervious to similar environmental factors, and especially to make the plants harder to sabotage. 232

The shortfall in power output during the crisis at Coalbrook was somewhat ameliorated by the interconnections that were already in place throughout the Transvaal and Orange Free State.

The output at other stations in the two provinces could be increased to compensate for the decline in production at the Taaibos and Highveld stations. Escom had already started the process of interconnecting stations within the various undertakings and between undertakings before 1960.

In October 1954, the Commission applied to the ECB for permission to interconnect the Eastern

Transvaal Undertaking (the licenced area that was supplied by the Witbank Power Station) with the Rand and Orange Free State Undertaking (comprised of Brakpan, Klip, Rosherville,

Simmerpan, Vaal, Taaibos, Wilge, Vereeniging, and Vierfontein Power Stations).233

Escom had also applied during 1954 to make changes to the licences for the Cape Northern

Undertaking, which supplied the area around Kimberly, and the two licences for the stations

232 Christie, Electricity, Industry and Class, p. 164. 233 Commission, 1954 Annual Report, pp. 10-11.

- 88 - operating in Natal. The Colenso and Congella stations in Natal would cooperate in meeting the combined demand for Natal, which Escom estimated would save more than £4 million in equipment upgrades for the two stations between 1954 and 1959. For the Cape Northern

Undertaking, Escom was operating the power plant in Kimberley that had originally been owned by De Beers, but the old power station was struggling to keep up with load demand in the northern region of the Cape Province. Instead of upgrading at Kimberley to supply an increasing but relatively small load, Escom decided that extra generator sets would be added to some of the power stations in the Rand and Orange Free State Undertaking so that an interconnection could be established between the two areas. 234

In general, Escom had been finding the increase in demand after the late 1940s difficult to match. Despite having enough installed capacity, the Cape Northern Undertaking was also struggling in the years preceding 1954 to supply enough power to consumers in the area because of chronic water shortages. The stations in the Cape Western and Natal Central Undertakings had been experiencing problems throughout the early 1950s with ensuring adequate coal supplies, sometimes having less than a day’s worth of coal in stock at the stations. Even when there was enough coal to burn, the power stations in Cape Town had difficulty with the quality of the coal that was being supplied. In the 1951 Annual Report, Escom noted that the Cape Western

Undertaking had to implement a ration system, “whereby consumers in certain sections of the

Commission’s and the City Council’s areas were in rotation liable to disconnection at times which were notified in advance.”235

Power stations in the Transvaal and the Orange Free State needed help from the local municipalities in meeting demand, and customers in the Transvaal had to start using the available load more carefully. Even the often fiercely independent Johannesburg Municipality was willing to interconnect the city’s power grid to Escom’s regional grid so that the two systems would be

234 Commission, 1954 Annual Report, pp. 10-11. 235 Electricity Supply Commission, 1951 Annual Report, p. 8, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1951%20Annual%20Report.pdf.

- 89 - able to support each other during peak hours. This interconnection worked well because the two systems had their respective peak demand during different times of the day – Escom’s load was greatest in the late morning and early afternoon, while the city’s power stations experienced increased demand during the evenings.236

These interconnections then grew in the early and mid-1960s into a high voltage transmission system that would use a network of lines carrying power at 275kV and 400kV between the Cape Northern, Rand and Orange Free State, and Eastern Transvaal Undertakings.

Another high voltage line would transmit power at 275kV between the Ingagane Power Station in

Natal, which was due be competed in 1963, and the Georgedale distribution network. 237 By 1996,

Escom felt confident enough in the development of the technology used in transmission networks to begin discussions with other governments in southern Africa to interconnect grids beyond South

Africa’s borders. This included talks with the Portuguese colonial government in Mozambique about cooperating on the Cahora-Bassa project; to sign a supply agreement with Lesotho; and to begin investigating the possibility of building at least two new power stations South-West Africa.

As administrators over South-West Africa, South Africa would work in conjunction with the

Industrial Development Corporation (IDC) and Suid-Wes Afrika Water en Elektrisiteitskorporasie

(SWAWEK).238

The first tangible appearance of the fully interconnected National Grid appeared in October

1969, when the interconnection between the Eastern Transvaal and Cape Western Undertakings went into service. At the same time, Escom had finalised cooperative contracts for the construction of Cahora-Bassa and was contemplating an agreement with Swaziland to collaborate on a new power station near to recently discovered coalfields in Swaziland.239

236 Commission, 1950 Annual Report, pp. 45-47. 237 Electricity Supply Commission, 1962 Annual Report, p. 14, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1962%20Annual%20Report.pdf. 238 Electricity Supply Commission, 1967 Annual Report, p. 12; Conradie and Messerschmidt, Symphony of Power, p. 139. 239 Electricity Supply Commission, 1969 Annual Report, p. 8.

- 90 -

These interconnections were key parts of the foundation of the National Grid, but one of the largest steps in facilitating the national connections between power stations was the formation of the Central Generating Undertaking (CGU). The CGU was founded on January 1, 1972 after the Electricity Amendment Act 60 of 1971 altered the relationships between the Undertakings.

This turned all the former Undertakings, which had been tasked with the generation and distribution of electricity, into Distribution Undertakings and placed the control of the power stations solely under the CGU.240

This effectively centralised control over the individual power stations, thereby creating a shift in the role of each power station. No longer were stations important only in relation to their own Undertaking, but their output was integrated with all other Eskom-operated stations in the country. This meant that some of the less cost-efficient power stations would only be used during peak hours, thereby lowing total running costs. The creation and running of the CGU also created a fundamental shift in the economy of scale that Escom could leverage – the same logic that led to the interconnection of power stations within an Undertaking led to the interconnection of power stations across the country.241

It was this centralisation and the extent of control that was granted to the CGU that limited its lifespan to six years. By 1978, the CGU had started to become increasingly unpopular amongst

Eskom management and within the distribution Undertakings, largely due to perceived managerial and operational overreach. In September 1978, Escom reverted back to operating via Undertakings that controlled their own generation and distribution, but transferred managerial control to Escom head office.242

240 Conradie and Messerschmidt, Symphony of Power, p. 142. 241 Conradie and Messerschmidt, Symphony of Power, pp. 142-3. 242 Conradie and Messerschmidt, Symphony of Power, pp. 230-31.

- 91 -

2. “Thousands of Experts”: Escom’s Nuclear Power Projects, 1960 – 1990

South Africa was pulled into the international nuclear community by a request from the

Allied Powers during World War II, when the British government asked Jan Smuts to begin research on the availability of uranium ore in the country. 243 In 1947, Smuts followed up with a post-war project to get gold mines to assist in the process of adding uranium processing facilities to the existing gold extraction systems. 244 Throughout the 1950s and 1960s, the AEB was also involved in establishing international networks for civilian nuclear research and signed agreements with the United States and the United Kingdom, which included the eventual installation of the

South African Fundamental Atomic Research Installation (SAFARI-1) reactor in 1965.245

By the time that research was beginning to get underway at the SAFARI-1 reactor, the

South African government had already commissioned two reports on the future of nuclear energy for electricity generation. In both cases, the reports reached the same conclusion – the country could invest in at least one nuclear power station in the future, but any plans should be held off until nuclear energy could compete economically with traditional coal-fired power stations. The earlier of the two reports served as more of a preliminary study into the feasibility of nuclear power stations and nuclear energy research. As such, it offered fewer recommendations on potential technological and economic choices that would have to be made in the process of building a nuclear power station.246

In researching the 1968 report, the AEB considered four of Escom’s undertakings as potential sites for a nuclear power station. By the late 1960s, each undertaking did not consist of a single power station, as was the case shortly after the signing of the 1922 Electricity Act. Instead, an undertaking was comprised of several power stations that supplied a common area. For

243 Masiza, "Chronology of South Africa's Nuclear Program," p. 36. 244 A. R. Newby-Fraser, Chain Reaction: Twenty Years of Nuclear Research and Development in South Africa (Pretoria: The Atomic Energy Board, 1979), p. 24. 245 Masiza, "Chronology of South Africa's Nuclear Program," p. 36; Newby-Fraser, Chain Reaction, pp. 8,10-11. 246 Report of the Commission of Enquiry into the Application of Nuclear Power in South Africa (Pretoria: The Government Printer, c. 1961); Atomic Energy Board, Report on the Investigation into the Possible Introduction of Nuclear Power in the Republic of South Africa (1968).

- 92 - statistical and accounting purposes, the output and income for the stations within an undertaking were combined. As their borders expanded, these undertakings would become the building blocks of the expanding National Grid.

For their 1968 report, the AEB examined the Rand and Orange Free State; Eastern

Transvaal; Natal; and Cape Western Undertakings. The two inland undertakings were discounted fairly soon, as the costs of coal in the Transvaal and northern Orange Free State were low enough to make nuclear power uneconomical. The Natal and Cape provinces were also favoured as possible sites for nuclear power stations, largely because of the easy availability of seawater for cooling purposes.

All nuclear power reactors use the same basic physical processes to generate electricity; a controlled nuclear chain reaction generates heat, this heat is used to boil water, and the resulting steam powers the turbines that generate the electricity. The differences in between reactor designs are mostly determined by factors such as the type of fuel used, or which materials are used to moderate the nuclear fission reaction. In terms of technological choices, the AEB made the recommendation to use relatively small reactors of the CANada Deuterium Uranium (CANDU) design.

CANDU reactors use bundles of fuel rods that are placed inside tubes that run through a pressure vessel known as a calandria, and use heavy water as a moderator to control the nuclear reaction. 247 The investigators also researched the British Magnox and the more commonly used

Pressurised Water Reactor (PWR) types, but concluded that the CANDU design was more suitable for South African purposes because the uranium fuel used in the Canadian designs did not need to be enriched.248

The use of natural, or unenriched, uranium would have presented two advantages for the

South African government at the time the report was published. Enrichment processes are typically

247 "Nuclear Power Reactor Characteristics," World Nuclear Association, last modified May 2017, http://www.world-nuclear.org/getmedia/80f869be-32c8-46e7-802d-eb4452939ec5/Pocket-Guide-Reactors.pdf.aspx. 248 Board, Report on the Investigation into the Possible Introduction of Nuclear Power in the Republic of South Africa, p. 50.

- 93 - extremely costly, in terms of financial investments, the amount of time required to produce fuel that is sufficiently enriched to support a chain reaction, and the amount of available electricity that can be used to run the enrichment facility. Secondly, as Escom and the AEB discovered during the construction of the plant at Koeberg, relying on foreign sources of enriched fuel can present economic and political challenges that restrict the availability of the fuel.

When the time arrived for Escom to make the decision to proceed with a nuclear construction project, the parastatal opted to build the station in the Western Cape. The site for the

Koeberg Nuclear Power Plant was approximately thirty kilometres outside of Cape Town, in order to act as a baseload generating station for the city. The rationale for placing the station relatively close to a major urban settlement was that the Duynefontein area is relatively geologically inactive; the station would have easy access to the National Grid from that location; the seawater from the

Atlantic was well-suited to provide water for the cooling systems; and the nearest coal-fired power station was roughly 1 500 kilometres away from the city. 249

Escom sent out a request for tender applications for the nuclear power station construction project during February 1974. The original project schedule called for any successful tender applications to be ready for addition to the grid in September 1982. The initial applications were reviewed by Escom in October 1974, and three applications were selected for further investigation. 250 The three tender applications were submitted by groups of engineering and construction firms that represented international and local interests. None of the three applications proposed to use the CANDU reactor design that the AEB had recommended in 1968; two of the proposals advocated using a PWR design, while one recommended a Boiling Water Reactor

(BWR) design.251

249 "Nuclear Energy: Koeberg Power Station," Eskom, accessed July 7, 2015, http://www.eskom.co.za/AboutElectricity/FactsFigures/Documents/Nuclear.pdf. 250 Electricity Supply Commission, 1974 Annual Report, p. 10, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1974%20Annual%20Report.pdf. 251 Christie, Electricity, Industry and Class, pp. 194-97; Conradie and Messerschmidt, Symphony of Power, pp. 204-5.

- 94 -

The PWR and BWR designs both use light water to generate steam and to moderate the reaction in the core and, unlike the CANDU designs, both require enriched uranium as fuel. The key difference between the two design concepts is that the BWR design has only a single system to circulate the water for both the coolant and turbine systems, while a PWR design uses two separate systems. In a BWR, the water around the core turns into steam, which is pumped directly into the turbines, cooled back into liquid water, and sent back to the core. In a PWR design, water is circulated through a primary loop, which moves heated water from the reactor core into a steam generator to transfer the heat into pipes that comprise part of the secondary loop. The primary loop then carries water back to the reactor core to be reheated. The water in the secondary loop is turned into steam and pumped to the turbines.252

A suitable analogy for the two systems would be like cooking food in a pot of boiling water.

The BWR system would be akin to placing potatoes directly into the boiling water – there is direct contact between the coolant from the core and the generator turbines. A PWR system would be more like sealing the potato in a plastic bag before putting it into the pot – heat is transferred from the water to the potato, but the potato and the water are never directly in contact.

The eventual decision, announced officially in May 1976, was to tender the contract for the nuclear power station to the French-led consortium of Framatome, Alsthom, Spie-Batigonolles, and Framateg, who were contracted to construct two 1 000MW PWR reactors at Koeberg. There was some initial confusion over whether the contract had been granted to the United States or

France, since the American tenderers, headed by General Electric Technical Services Co, stated that they had been informed in April 1976 that they would be given the construction contracts.253

The final contracts were signed between the South African and French interests on August 5, 1976, and an agreement between the International Atomic Energy Agency (IAEA), South Africa, and

France was entered into on January 5, 1977. This agreement established safeguards and inspections

252 "Nuclear Power Reactor Characteristics," http://www.world-nuclear.org/getmedia/80f869be-32c8-46e7-802d- eb4452939ec5/Pocket-Guide-Reactors.pdf.aspx. 253 Christie, Electricity, Industry and Class, p. 196.

- 95 - protocols so that the IAEA would have regulatory jurisdiction over the Koeberg Nuclear Power

Plant.254

The apartheid state placed particular importance on the advancement of technology to create a modern state, even if the idea of continued institutionalised racism is discordant with the ideas behind modernity.255 This distinctly South African form of “technopolitics” can be seen in the construction of the Koeberg power plant. Firstly, the use of nuclear technology has a long history of being heavily politicised, even if the legal and diplomatic bodies charged with overseeing the use of such technology are ostensibly apolitical. Secondly, the very term “nuclear” is associated with specific connotations in the minds of diplomats, politicians, scientists, and laymen alike. Over time, these connotations have created a sort of nuclear exceptionalism that is transferred across into any discussion on the use of nuclear power. Associated with this nuclear exceptionalism is the idea that there is not necessarily a clear-cut line between what constitutes

“nuclear” technology, or even where to draw the line between “dangerous” and “safe” uses of this technology.256

These concepts of modernity, nuclear technology, and nuclear exceptionalism combined to confer a certain amount of prestige upon the Koeberg construction project. From the perspective of the South African government, the construction of Africa’s first nuclear power station would demonstrate the country’s mastery of a potentially dangerous form of energy for the apparently benevolent purpose of generating electricity.

As the first nuclear power plant, not just in South Africa, but on the African continent,

Koeberg provided a valuable opportunity for the country’s anti-apartheid movements to sabotage

254 International Atomic Energy Agency, Information Circular, INFCIRC/244, pp. 1-9. 255 Sparks, "Apartheid Modern," pp. 1-30. 256 For a historical overview of the development of nuclear exceptionalism in Western society, see Spencer R. Weart, The Rise of Nuclear Fear (Cambridge, MA: Harvard University Press, 2012). For the localised South African ideas surrounding nuclear technology, see Edwards and Hecht, "History and the Technopolitics of Identity," pp. 619-39; Hecht, Being Nuclear; Hecht, "Negotiating Global Nuclearities," pp. 25-48; Gabrielle Hecht, "The Power of Nuclear Things," Technology and Culture 51, no. 1 (January, 2010): pp. 1-30; Gabrielle Hecht, "On the Fallacies of Cold War Nostalgia: Capitalism, Colonialism, and South African Nuclear Geographies," in Entangled Geographies: Empire and Technopolitics in the Global Cold War, ed. Gabrielle Hecht (Cambridge, MA: MIT Press, 2011), pp. 75-99; Gabrielle Hecht, "An Elemental Force: Uranium Production in Africa, and What It Means to be Nuclear," Bulletin of the Atomic Scientists 68, no. 2 (March/April, 2012): pp. 22-33.

- 96 - a high-profile target, while still trying to ensure that casualties would be minimised. On the night of December 18/19, 1982, four modified limpet mines detonated at the Koeberg construction site, damaging the reactor heads for both reactors, part of a tunnel near the station’s pumphouse, and some of the cabling systems that had already been installed. The four mines had been planted by

Rodney Wilkinson, who had been working on the construction project while also aiding the ANC to plan the attack on the plant.

The Star reported the next day that the ANC office in Dar es Salaam claimed responsibility for the explosions, stating that the power station had been attacked in retribution for a recent incident, in which twenty-nine South Africans had been killed in Maseru during a South African- led raid. 257 It is most likely that the attack had not been carried out in response to the Maseru incident, since the timeline that Wilkinson later described to journalists suggests that the bombing had been in planning for at least a year beforehand. 258

The bombing did cause delays in the completion of the Koeberg construction project, but the project was already behind schedule – in July 1981, Framatome was trying to dispute claims that South Africa had responded to construction delays by threatening to withhold payment until the reactors had achieved a self-sustaining chain reaction. 259 By July 1982, Escom had changed the dates for the first unit to be ready for commercial operation from December 1982 to the less specific deadline of early 1983. 260 In any case, it may not be possible to calculate exactly how much of a delay was caused by the sabotage attack, since there had already been other construction problems before December 1982.

The construction on Unit-1 at the Koeberg Nuclear Power Plant was officially completed when the reactor achieved criticality, thereby being capable of maintaining a stable chain reaction.

The connection to the National Grid went online on April 4, 1984. Coincidentally, a blackout

257 "Koeberg: Doubts on Security," The Star, December 20, 1982. 258 David Beresford, "How We Blew Up Koeberg (... And Escaped on a Bicycle)," Mail & Guardian, December 15, 1995. 259 "Framatome Denies South Africa Can Withhold Payment For Its Koeberg Units," Nucleonics Week, July 30, 1981. 260 "Koeberg: Doubts on Security," The Star, December 20, 1982.

- 97 - affected central Cape Town on the same day, prompting further suspicion about the plant’s safety and efficacy. Escom later stated that the widespread blackout had been caused by a fault in one of the three main cables leading into the city’s local grid, which had caused the remaining two cables to overload. 261

Further problems during the final phases of construction on Unit-2 delayed the plant’s commissioning even more. During inspections on the water circulation systems, the plant’s engineers discovered iron impurities in the stainless-steel pipes in Unit-2’s secondary water loop.

Escom decided on January 21, 1985, that Unit-1 should be shut down so that the pipes in the reactor’s two water circulation loops could be fully inspected, a decision that further strained the tense relationship between the parastatal and Framatome. 262 After inspecting the primary and secondary water loops on Unit-1, Koeberg’s engineers decided that the presence of iron in the stainless-steel pipes did not present any significant threat to the system’s integrity, but the Atomic

Energy Corporation of South Africa (AEC), the governmental body that had been formed by a merger between the AEB and Uranium Enrichment Corporation of South Africa (Ucor) in 1982, wanted further proof that the pipes were safe.

Further inquiries into the iron impurities revealed that the company which had produced the stainless-steel for Framatome had allowed the iron identification tags that were used as labels on their ingots of stainless-steel to contaminate some of the ingot moulds. This resulted in the contamination of the materials used to cast the pipes that were used at Koeberg. 263 The additional delays caused by the extra pipe inspections meant that Unit-2 at Koeberg only achieved criticality on July 7, 1985 and was connected to the National Grid on July 25, 1985. 264

261 "Heat Caused Power Failure," Cape Times, April 5, 1984. 262 Ann MacLachlan and Stephanie Cooke, "Dispute Over Koeberg Shutdown Erupts Between Escom and Framatome," Nucleonics Week, February 28, 1985. 263 Stephanie Cooke, "Koeberg-1 Restart Delayed Because AEC Not Sure Steel Pipes are Sound," Nucleonics Week, May 16, 1985. 264 International Atomic Energy Agency, Operating Experience with Nuclear Power Stations in Member States in 2014, p. 567, http://www-pub.iaea.org/MTCD/Publications/PDF/OPEX_2015_CD_web.pdf.

- 98 -

3. Electrifying Non-White Areas: Electricity in Townships and Bantustans

Determining when and how electrification occurred in the areas of South Africa that were nominally reserved for African, Indian, and Coloured residences is complicated by a lack of consistency in government policy and nomenclature. Relatively late in the process of electrification as 1952, Escom still referred to areas reserved for white residents as “townships,” and some areas that the Group Areas Act of 1950 demarcated as exclusively non-white had already received some measure of electricity supply before the National Party electoral victory of 1948.

John Shorten makes a brief reference to the final stages of “…the reticulation of Orlando Bantu

Township…” in May 1938 and to the completion of municipal grid extensions into Soweto in 1956 but does not mention for how long these installations were active.

It is also difficult to determine to what extent the grid in Orlando would have electrified the township, since Shorten also does not mention whether it was meant for streetlighting, industrial, or residential use. 265 It is likely though, that the local distribution network in Orlando did not extend very far past the point it reached in 1938, because Renfrew Christie stated five years after

Shorten’s book was published that people living in the Orlando Power Station’s immediate surroundings still did not receive electricity from the station in their homes. 266

In any case, concerted efforts at electrifying the sprawling townships that lay in proximity to the major urban areas only started in the mid-1980s, and the 1990 Annual Report stated that there were still more than two million urban households that were not electrified. 267 Even in areas that had received some measure of electrification, the terms of supplying electricity were sometimes dependent on racial classification. For instance, permits to receive electricity in

Bophuthatswana in 1986 still specified that electricity would only be supplied to properties under white ownership, and that all such properties could only then be resold to what the permit euphemistically called “the qualified group.” It also seems that applicants were subject to

265 Shorten, Johannesburg Saga, pp. 609, 613. 266 Christie, Electricity, Industry and Class, p. 2. 267 Conradie and Messerschmidt, Symphony of Power, pp. 269-70; Eskom, 1990 Annual Report, p. 13, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1990%20Annual%20Report.pdf.

- 99 - screening process before permits were approved. A comment added by government officials at the end of a permit application states that the South African Police “…vind niks nadelig teen die karakter van die aansoeker nie.” (…found nothing objectionable about the applicant’s character…). 268

To electrify some of the larger townships in the country, Eskom needed to use its existing relationships with foreign firms to put together the resources and manpower to rapidly establish infrastructure in underdeveloped areas. The first of these collaborative efforts brought Eskom, the

Électricité de France (EdF), and East Midlands Electricity together in 1993 to supply roughly

43 000 households in Khayelitsha with electricity. 269

Despite these efforts, progress into the urban townships and former Bantustans was slow.

In an inversion of the conflict between the Electricity Supply Commission and municipalities over who had the right to supply ratepayers, Eskom often clashed with governments at the municipal, provincial, and national level over who should carry the responsibility for electrifying urban townships. In this later situation, the conflict was not over who would be granted the coveted right to supply municipal ratepayers. Instead, both parties believed that the right to supply the townships was more of burden and tried to convince each other to take on the responsibility. There had also been a certain amount of resistance to continued electrification from the parastatal’s management when consumers in townships and rural areas either engaged in rates boycotts or did not settle outstanding accounts.270 There was enough resistance, according to Conradie and Messerschmidt,

268 "Permit Issued in Terms of Section 21 of the Group Areas Act, 1966," National Archives of South Africa (SAB), VBW 565, ref. 13/1/4/4054/53; "Beslissing: Permit Aansoek," National Archives of South Africa (SAB), VBW 565, ref. 13/1/4/4054/53. 269 Conradie and Messerschmidt, Symphony of Power, pp. 300-1. 270 Prishani Naidoo and Ahmed Veriava, "From Local to Global (And Back Again?): Anti-Commodification Struggles of the Soweto Electricity Crisis Committee," in Electric Capitalism: Recolonising Africa on the Power Grid, ed. David A. McDonald (Cape Town: HSRC Press, 2009), pp. 321-37; Greg Ruiters, "Free Basic Electricity in South Africa: A Strategy for Helping or Containing the Poor?," in Electric Capitalism: Recolonising Africa on the Power Grid, ed. David A. McDonald (Cape Town: HSRC Press, 2009), pp. 248-63; Peter van Heusden, "Discipline and the New 'Logic of Delivery': Prepaid Electricity in South Africa and Beyond," in Electric Capitalism: Recolonising Africa on the Power Grid, ed. David A. McDonald (Cape Town: HSRC Press, 2009), pp. 229-47; von Schnitzler, "Citizenship Prepaid," pp. 899-917; von Schnitzler, "Traveling Technologies," pp. 670-93. Discuss the history of, and responses to, the rollout of prepayment meters in South Africa’s townships for electricity.

- 100 - that some members of Eskom’s board argued that “electricity for all” should not be given priority over other goals, such as starting work on the international southern African power grid.271

Eskom also had to contend with the overwhelming scope of electrification across South

Africa’s urban townships and former Bantustans – not only was the parastatal expected to supply electricity to households across the country, but businesses, schools, and clinics had to be added to the long list of properties that needed electricity. As of 2016, this monumental task was still in progress – Statistics South Africa stated that 84.2% of South African households had access to mains electricity, up from 77.1% in 2001. The remaining 15.8% utilise coal, wood, paraffin, gas, and other sources of energy.272 Despite the work that still needs to be done in electrifying more than a tenth of households across the country, the progress that has been made since the start of the 1990s is significant. The World Bank Sustainable Energy for All database states that household electrification in 1990 was only 56.5% and only reached the 75% mark during 2002.273

271 Ian McRae, The Test of Leadership: 50 Years in the Electricity Supply Industry of South Africa, (Johannesburg: EE Publishers, 2006); Conradie and Messerschmidt, Symphony of Power, p. 270. 272 Statistics South Africa, “General Household Survey,” Statistical Release P0318 (Pretoria: Stats SA, 2016), pp. 32-35, http://www.statssa.gov.za/publications/P0318/P03182016.pdf. The publication does not specify which fuel types are classified as “other” sources. 273 "Access to Electricity (% of Population)," last modified 2014, accessed January 29, 2018, https://data.worldbank.org/indicator/EG.ELC.ACCS.ZS?end=2014&locations=ZA&start=1990&view=chart.

- 101 -

CHAPTER FIVE – THE NATIONAL GRID AS A HUGHESIAN LARGE TECHNOLOGICAL SYSTEM

As a means of evaluating and summarising the progress of building the National Grid, it is perhaps best to use the factors that Thomas Hughes listed as important sociological features that give technological artefacts their particular localised style.274 There is, inevitably, some overlap between these factors, especially when examining the effects of a social system as pervasive as

South Africa’s segregation and apartheid had on the development of a technological system with a national scope. Even so, it is still possible to isolate some factors that fall distinctly within each of these categories that each played a role in the formation of the National Grid.

South Africa’s physical and social geographies affected the shape and form of the grid itself. Two of the most significant factors in South African physical geography were the mineralogy and rainfall patterns of the country’s interior. After the Mineral Revolution in the late

1800s, interior urban settlements started to accumulate around the diamond fields in the vicinity of Kimberley in the North-Western Cape and the gold veins in the Transvaal. This created a significantly larger demand for electricity in the northern half of the country, especially after the alluvial gold deposits had been depleted and the Rand’s mines needed to sink shafts ever deeper to reach the Reef.

The city of Cape Town, one of the most populous cities in the country, had grown around the site of the original settlement established by the Dutch East India Company after 1652. The mining centres of the country had been established around the diamond mines in the region of

Kimberley and the precious metals on the Witwatersrand. The straight-line distance from Cape

Town to Kimberley is slightly more than 830km, while Johannesburg is roughly 1 260km from

Cape Town. The focus on these three regions created uneven urban settlement patterns that left large swathes of the country in-between these three areas relatively sparsely populated. The localised nature of mining and settlement patterns created regional clusters of electricity demand.

274 Hughes, Networks of Power, p. 405.

- 102 -

Not only did the country’s mineralogy affect the geography of electricity demand, but also determined where supplies of fuel could be located. Coal reserves have typically been found most heavily clustered in the Eastern Transvaal/Mpumalanga region, with smaller deposits also available in the Free State, Natal, and Northern Transvaal/Limpopo provinces. If electricity was to be supplied as cheaply as possible, then Escom needed to keep fuel costs down. This problem was largely solved by the construction of power plants adjacent to the coal mines.

However, there were still power plants near large urban or industrial centres that required coal supplies, but that were too far away from the coal seams to make a pithead power station viable. Between the 1920s and the early 1950s, power transmission technology was still relatively undeveloped, making high voltage transmission from a pithead power station to the centre of demand impractical. These stations, most notably the stations in and around Cape Town, relied on the freighting of coal from the mines in the Transvaal and Natal to the site of the power station.

This solution vastly elevated the operating costs of these power stations because coal had to be regularly carried via railways to the power stations. For the Commission, this made the physical geography of the country and the economics of power generation and transmission overlap. In

1950, the average cost of coal per short ton at the Salt River Power Station in Cape Town was 32s

5d, while the cost for the same quantity of coal at Witbank was 4s 2d.275

In 1956, Escom reported that nuclear power would definitely be implemented into the grid at some point in the future, but that conditions in the 1950s did not warrant building such a facility at that point in time. The Annual Report for 1956 states that Escom believed that there were four factors that stood against construction of a nuclear power station:

1. The plentiful supplies of coal in the Transvaal and Natal kept fuel prices at South African

power stations low;

2. Areas in which coal needed to be regularly freighted by rail still had relatively small load

requirements, thereby helping to maintain low fuel prices;

275 Commission, 1950 Annual Report, pp. 23, 27.

- 103 -

3. Nuclear power was still proving to be more expensive in the long run than traditional

fuel sources;

4. Nuclear engineering was still experimental and needed much more development before

it was a viable alternative to fossil fuels.276

The high costs of coal transport from the Eastern Transvaal to the Western Cape, combined with security concerns about the safety of the high voltage transmission lines leading into the Cape from the 1960s onwards, presented Escom with the ideal opportunity to begin the planning and construction of the country’s first nuclear power plant.

The economics of power generation and distribution were particularly important for Escom for as long as the parastatal was mandated to supply electricity without making either a profit or a loss, as had been specified in the Electricity Act of 1922. Not only did the overall balance sheet for Eskom have to reflect as close to a zero balance as possible for each financial year, but each undertaking had to be treated as an individual entity in its own right – thereby making it impossible for the cumulative profits at some undertakings to be used to write off the losses incurred at others.

These financial restrictions affected urban regions somewhat less than rural electrification. Firstly, many of the towns and cities across South Africa had municipal power stations that generated and distributed electricity to local consumers. This made the electrification of these locales less urgent for Escom between 1922 and the 1950s.

Secondly, Escom had to consider the relative population density of a non-urban area before the residents could be offered electricity. This made it unlikely that larger farms would receive electricity during the interwar period, mostly because of the costs involved in establishing these local grids. In order to supply electricity to an agricultural region, Escom had to transmit the power at relatively high voltages, in the same way that power was transmitted from the power station at

Witbank to the Rand’s mining consumers. This required the construction of substations at the site of consumption to convert the current from higher transmission voltages down to the voltages that

276 Electricity Supply Commission, 1956 Annual Report, p. 6, http://www.eskom.co.za/sites/heritage/Annual%20Reports/1956%20Annual%20Report.pdf.

- 104 - were used for machinery and domestic appliances. Such substations were typically expensive, making it difficult for individual farmers to be able to afford the costs of electrifying their farms.

Escom was also not able to fund the construction of the substations, since the overall cost of the substation would be too great when compared to the amount of revenue that could be gained from the consumption of electricity on the farm.

This restriction was finally done away with when the Eskom Act 40 of 1987 was signed.

This legislation both renamed the organisation and changed the rules governing how the parastatal’s finances worked. After the Eskom Act in 1987, the parastatal was officially known as

Eskom – a portmanteau of the former English and Afrikaans abbreviations for the Electricity

Supply Commission.277 The new law also stated that Eskom’s role was to generate and sell electricity “…in the most cost-effective manner, subject to resource constraints and the national interest…”278 This effectively freed Eskom from having to maintain a nil balance over the course of each financial year, instead making the terms of supplying electricity to consumers more nebulous than under the previous laws.

There had been previous stopgap measures that had been signed into law to help Escom bypass some of the financial restrictions from the Electricity Act of 1922. In June 1947, the

Electricity Amendment Act 44 of 1947 provided the Minister of Mines and Industries some extra leeway in providing electricity to an area where power would have to be supplied at a loss. In this provision, the Minister had been granted the right to decide whether Escom should supply electricity to an area that would normally either require Escom to charge consumers more than a reasonable amount for electricity or to supply electricity at a loss. In these cases, the Minister was allowed to use annual funds that were granted by Parliament to make up the difference between the costs of supplying electricity and the income from these consumers. 279

277 Government Gazette of 4 September, 1987, vol. 267, no. 10893, p. 2. In English, the abbreviation “Escom” had been used to denote the Electricity Supply Commission, while the Afrikaans term “Evkom” was used as an abbreviation for Elektrisiteitsvoorsieningskommissie. 278 Government Gazette of 4 September, 1987, vol. 267, no. 10893, p. 4. 279 Government Gazette of June 18, 1947, vol. 148, no. 3834, pp. xc-xcii.

- 105 -

The most obvious political aspect of South African society that helped shape the National

Grid was the increasingly overarching role that racial segregation and control played throughout the twentieth century. Between 1910 and 1948, the government had remained committed to the idea of segregation, even if it was not as deeply ingrained in as many aspects of society and lifestyles as it became after 1948. The government led by the National Party became widely-known for passing laws like the Group Areas Act 41 of 1950, but the segregation-era cabinets had signed the Natives Land Act 27 of 1913 and the Immorality Act 5 of 1927 long before the advent of apartheid.

These overtures towards establishing a segregated South Africa make it difficult to determine what difference, if any, the defeat of the National Party in 1948 might have made on the progress of electrification. It is extremely difficult, even nigh impossible, to distinguish where the segregation government would have decided to draw the metaphorical line. In any case, such speculation is typically outside the scope of historical research, but it would be fair to say that no matter which party had won the critical 1948 national elections, black South Africans would have waited much longer for electrification than their white counterparts. Despite the focus on white consumers for much of the organisation’s history, the continued growth of the mining and industrial sectors helped to ensure continued, if slightly uneven, load growth between 1926 and

2000 (Figure 9).

- 106 -

Total Sales per Annum (kWh), 1926-2000 200 000 000 000

180 000 000 000

160 000 000 000

140 000 000 000

120 000 000 000

100 000 000 000

80 000 000 000

60 000 000 000

40 000 000 000

20 000 000 000

0

1926 1928 1930 1932 1934 1936 1938 1940 1942 1944 1946 1948 1950 1952 1954 1956 1958 1960 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 Figure 9 - Total Electricity Sales per Annum, 1926-2000 280

Figure 10 shows the state of the National Grid as of the time of writing at the end of 2017.

This map shows Eskom’s continued reliance on fossil fuels, especially coal. Fourteen of the fifteen baseload power stations in the country are still coal-burning stations, with Koeberg Power Station in Cape Town being the sole exception. Koeberg is also the only baseload station that is south of the Vaal River, all other power stations to the south of the Gauteng-Free State border are used for peak load or emergency supplies. This leaves all provinces southwards of Gauteng vulnerable to disruptions in power supply, especially in major urban centres like Cape Town. This weakness in the system was clearly demonstrated by events in the mid-2000s, when a series of equipment

280 Data from Escom/Eskom Annual and Statistical Reports, 1926-2000, http://www.eskom.co.za/sites/heritage/Pages/Annual-Reports.aspx.

- 107 - failures and maintenance-related mishaps between November 2005 and March 2006 resulted in multiple blackouts in the Western Cape. 281

The effects of these outages were worsened by the earlier closure of several of the older power stations in the Gauteng, Mpumalanga, and Free State region. These power stations had been constructed and commissioned between the mid-1930s and the late 1960s; many of these stations had relatively small installed capacities in comparison to the newer station designs and were decommissioned between 1987 and 1990. Commissioned in 1936, the Klip Power Station had an installed capacity of 424 MW, while the newer , commissioned in 1980, had

3 600 MW installed capacity.282

Jaglin and Dubresson believe that the key problem in the energy crisis that became evident after the problems at Koeberg was not a lack of supply, but that poor maintenance and a series of decisions made in the late 1990s meant that the overall system had deteriorated to the point where peak demand made the system too unstable.283 In particular, Eskom has been criticised for the decentralisation of electricity generation and distribution. This decentralisation started with the dismantling of the CGU in the late 1980s, and has been blamed for increasing system instability and therefore making the system less resilient against widespread failure.284

In effect, the National Grid had become an increasingly complex technological system, with components that were technological and sociological in nature. Smaller problems, which individually would not have created a nationwide electricity crisis, overlapped and interacted with each other to create a situation where the National Grid could not maintain stability when any of the major power plants experienced an interruption in generation. By comparison, the coal supply

281 Thembani Bukula and Smunda S. Mokoena, Investigation into the Electricity Outages in the Western Cape for the Period November 2005 to March 2006, http://www.sinetech.co.za/news/wcreport.pdf; K. L. Rodseth, et al., "Executive Report on the Koeberg "Bolt-in-the-Generator" Incident," Energize, September 6, 2006. 282 Commissioning dates, decommissioning dates, and installed capacity from Conradie and Messerschmidt, Symphony of Power, p. 114. 283 Jaglin and Dubresson, Eskom, pp. 62-75. 284 Stephen Greenberg, “Market Liberalisation and Continental Expansion: The Repositioning of Eskom in Post- Apartheid South Africa,” in Electric Capitalism: Recolonising Africa on the Power Grid, ed. David A. McDonald (Cape Town: HSRC Press, 2009), p. 101.

- 108 - problems faced by Salt River Power Station in the early 1950s resulted in problems that affected the stability of the Western Cape Undertaking, but the shortfalls in power generation from poor coal supply remained confined to that Undertaking.285

It is this type of problem experienced with the supply of electricity via the National Grid that highlights the value of the contributions made by STS research. Capital had played a role in the electricity crisis, in that investment in infrastructure had almost come to a standstill while the national government debated whether Eskom should remain nationalised. However, many of the factors that caused the slow breakdown of the National Grid were caused by worsening coal shortages, chronic maintenance problems at major power stations, a lack of experienced technicians, and the inability of the National Grid to handle high demand (even within the parameters of normal peak loading).286

The National Grid had grown since 1923 into a large and complex technological system.

The private companies, like the VFP and RMPS, had made way for the nationalisation of electricity supply during the 1930s and 1940s. Municipalities, such as Johannesburg, had been increasingly interconnected to the system, so that even those town councils that had tried to retain full independence after the signing of the Electricity Act in 1922 were integrated into Eskom’s system.

During the 1960s and 1970s, the disparate Undertakings that had been formed around the power stations were gradually interconnected as high voltage transmission technology advanced to allow for high voltages to be carried over ever larger stretches of the country. Legislative changes – such as the law that created the CGU – turned the formerly isolated Undertakings into a web of power stations, high voltage transmission lines, distribution cables, and control systems that could carry electricity from the point of generation in the northern Orange Free State to Cape

Town.

285 Commission, 1951 Annual Report, p. 8. 286 Jaglin and Dubresson, Eskom, pp. 65-68.

- 109 -

After the 1980s, Eskom was faced with the need to rapidly expand this web into areas that had been denied service delivery for decades. These changes in social and technological components of the system have allowed the parastatal to carry electricity into the vast majority of

South African households. Yet, it is also these changes that created a situation in which seemingly unrelated failures within the network worked in combination to create a nationwide crisis in electricity supply.

- 110 -

Figure 10 - Map of Eskom's Operational Power Stations, 2017287

287 Data on the locations of the power stations from "Power Station GPS Coordinates," accessed December 14, 2017, http://www.eskom.co.za/Whatweredoing/ElectricityGeneration/PowerStations/Pages/Power_Station_GPS_Coordina tes.aspx. Map produced using ArcGIS Pro.

- 111 -

Power Station Commissioned Decommissioned Location Coal-Fired Stations Arnot 1971 — Middelburg, Mpumalanga (Transvaal) Brakpan 1908 1970 Brakpan, Gauteng (Transvaal) Camden 1967 1990 290 Ermelo, Mpumalanga (Transvaal) Central 1904 1966 Kimberley, Northern Cape (Cape Province) Colenso 1924 1985 Colenso, KwaZulu-Natal (Natal) Congella A 1928 1973 Durban, KwaZulu-Natal (Natal) Congella B 1946 1978 Durban, KwaZulu-Natal (Natal) Duvha 1980 — Witbank, Mpumalanga (Transvaal) Grootvlei 1969 1990 Balfour, Mpumalanga (Transvaal) Hendrina 1970 — Middelburg, Mpumalanga (Transvaal) Hex River 1952 1988 Worcester, Western Cape (Cape Province) Highveld 1959 1995 Sasolburg, Free State (Orange Free State) Ingagane 1963 1990 Newcastle, KwaZulu-Natal (Natal) Kendal 1988 — Ogies, Mpumalanga (Transvaal) King William’s Town 1948 1972 King William’s Town, Eastern Cape (Cape Province) Klip 1936 1987 Vereeniging, Gauteng (Transvaal) Komati 1962 1990 Middelburg, Mpumalanga (Transvaal) Kriel 1976 — Kriel, Mpumalanga (Transvaal) Kusile — — Kriel, Mpumalanga Lethabo 1985 — Viljoensdrif, Free State (Orange Free State) Majuba 1996 — Volksrust, KwaZulu-Natal (Natal) Matimba 1987 — Ellisras, Northern Province (Cape Province) Matla 1979 — Kriel, Mpumalanga (Transvaal) Medupi 2015 — Lephalale, Limpopo (formerly Ellisras, Transvaal) Rosherville 1911 1966 Johannesburg, Gauteng (Transvaal) Salt River 1 1928 1979 Cape Town, Western Cape (Cape Province) Salt River 2 1955 1995 Cape Town, Western Cape (Cape Province) Simmerpan 1909 1957 Germiston, Gauteng (Transvaal) Taaibos 1954 1995 Sasolburg, Free State (Orange Free State) Tutuka 1983 — Standerton, Mpumalanga (Transvaal) Umgeni 1954 1988 Pinetown, KwaZulu-Natal (Natal) Vaal 1945 1989 Viljoensdrif, Free State (Orange Free State) Vereeniging 1912 1970 Vereeniging, Gauteng (Transvaal) Witbank 1927 1969 Witbank, Mpumalanga (Transvaal) West Bank 1292 1947 1978 East London, Eastern Cape (Cape Province) West Bank 2 1956 1988 East London, Eastern Cape (Cape Province) Wilge 1954 1995 Ogies, Mpumalanga Gas Turbine Stations Ankerlig 2007 — Atlantis, Western Cape Acacia 1976 — Cape Town, Western Cape (Cape Province) Port Rex 1976 — East London, Eastern Cape (Cape Province) Paratus/Kendal 1986 1986 Namibia/Kendal Hydroelectric Stations Colly Wobbles 291 1995 — Mbashe River, Eastern Cape (Former Transkei Bantustan) Gariep 1971 — Norvalspont, Eastern Cape (Cape Province) Ixopo 1956 1958 Ixopo, KwaZulu-Natal Malieveld 1925 1928 Sabie, Mpumalanga Ncora291 1995 — Ncora River, Eastern Cape (Former Transkei Bantustan) Sabie Gorge 1927 1970 Sabie, Mpumalanga (Transvaal) Umtata – First Falls291 1995 — Umtata River, Eastern Cape (Former Transkei Bantustan) Umtata – Second Falls291 1995 — Umtata River, Eastern Cape (Former Transkei Bantustan) Vanderkloof 1977 — Petrusville, Northern Cape (Cape Province) Nuclear Power Koeberg 1984 — Cape Town, Western Cape (Cape Province) Diesel Stations Alice 292 1948 1954 Alice, Eastern Cape (Cape Province) Caledon 1939 1943 Caledon, Western Cape (Cape Province) Margate 1938 1944 Margate, KwaZulu-Natal (Natal) Port Shepstone 1944 1969 Port Shepstone, KwaZulu-Natal (Natal) Volksrust 1939 1957 Volksrust, KwaZulu-Natal (Natal) Pumped Storage Schemes Drakensberg 1981 — Bergville, KwaZulu-Natal (Natal) Palmiet 1988 — Grabouw, Western Cape (Cape Province) Wind Turbines 2015 — Vredendal, Western Cape Table 3 - List of Commissioned and Commissioned Power Stations Owned by Escom/Eskom, 1923-2017293

290 Returned to commercial service in 2010. 291 Originally owned by the Transkei Electricity Supply Corporation (Tescor). Taken over by Eskom in 1998. 292 Taken over by Escom in the year listed in the “Commissioned” column. 293 Adapted from the table in Conradie and Messerschmidt, Symphony of Power, p. 114. - 112 -

CONCLUSION

1. Conclusions on the Research Aims and Objectives

As stated in the introductory chapter, the primary aim of this research was to examine the development of the South African National Grid from a viewpoint that relied heavily on the theories associated with sociological analysis of systems building. This perspective was chosen as an alternative to the more traditional Marxist influences in published writings on South African electrification. The Marxian trend in South African historiography had led to a labour-centric view of the development of the country’s parastatals, which allowed for scholars such as Renfrew

Christie and Nancy Clark to answer the question of why the National Grid was constructed and utilised. However, as also mentioned above, these published works had not sufficiently addressed the question of how the National Grid was constructed.294

In particular, the systems building perspective helped in addressing the effects of factors aside from capital-labour relationships and racial segregation in the growth of the National Grid.

In Chapter Two, the interactions between private and governmental capital were shown to have directed the growth of electricity in the Transvaal area, especially between 1922 and the late 1940s.

From a pragmatic perspective, the VFP and Eskom were constrained some of their choices by the distribution of the country’s mineral resources – power stations needed to be constructed in proximity to load centres, fuel resources, and water supplies.295

Chapter Three demonstrated the link between the electrification of railway lines and the country’s outlying rural areas. In the case of the railways, electrification was undertaken for reasons that were mostly economic, but also for the more practical reason of hauling freight up the steep escarpment that separates the country’s coastal regions from the Highveld.296 At the same time, rural and agricultural areas adjacent to the railway lines were receiving electricity. The

294 Cf. Introduction, pp 5-21. 295 Cf. Chapter Two. 296 Cf. Chapter Three, pp. 65-75.

- 113 - majority of the farms and households in these non-urban areas were in nominally “whites only” regions, but economic and technical considerations also played large roles in the development of the network through these areas.297

Lastly, the discussion on the development of nuclear power in Chapter Five showed the impact of sociological and political factors during the development of the National Grid from the early 1980s onwards. The gradual changes in governance before the mid-1990s were reflected in the uneven growth of the electrical network into the country’s townships and non-white rural areas.298 National identity, modernity, and apartheid governance worked in conjunction to add momentum to the addition of nuclear power to the South African National Grid. This was partly due to the prestige that was conferred upon large technical projects during the 1970s and 1980s, and partly due to increasing fears that the grid was susceptible to sabotage by anti-apartheid groups.299

2. Limitations and Associated Recommendations for Future Research

There is little focus on the interplay between gender and the establishment of the National

Grid in this research. Primarily, this can be attributed to the male-centric nature of Escom and the

ECB during most of the period discussed. In the discussion on the electrification of the domestic sphere, it also proved problematic to find records beyond those of the male engineers, politicians, and journalists. In the surviving records of events such as the cooking lessons held at Escom

House, all information has been mediated and edited either by Escom or newspaper editors – there seem to be no quotes, interviews, or articles that show any of these events from the perspective of the female participants. Likewise, there are also very few sources that show how black South

Africans acted and reacted in response to electrification. Many of these sources have also been shaped by the views of the writers and publishers, whether they are official parastatal publications,

297 Cf. Chapter Three, pp. 75-80. 298 Cf. Chapter Five, pp. 102-4. 299 Cf. Chapter Five, pp. 95-101.

- 114 - newspapers, or archival sources. Filling in these gaps would require access to sources such as the diaries and personal correspondence of these participants. It might be possible to conduct interviews with the people who participated in the more recent events, such as the construction of the Koeberg power plant and the electrification of the townships, but the decades since Escom’s early days would prevent similar interviews with early consumers. Whether such records remain in the Eskom corporate archive is difficult to determine, because multiple requests for access to these archives were declined at the start of the research process.

There is possible scope for more focused studies on the history of individual artefacts or sets of artefacts within the South African context, such as those by Fred Schroeder and Damon

Taylor on electrical plugs and sockets in the United States and Europe.300 Such studies are useful for examining the effect of more localised influences on the technological style of a system. This would rely on the ability to not only find sources pertaining to the development of a national system, but would also depend on the availability of sources on the choices (and the rationale for these choices) by the engineers and systems designers who made those choices.

300 Fred E. H. Schroeder, “More “Small Things Forgotten”: Domestic Electrical Plugs and Receptacle, 1881- 1931,” Technology and Culture 27, no. 3 (July 1986): pp. 525-43; Damon Taylor, “Plugging In: Power Sockets, Standards and the Valencies of National Habitus,” Journal of Material Culture 20, no. 1 (2015): pp. 59-75.

- 115 -

BIBLIOGRAPHY

National Archives of South Africa (SAB and TAB) National Archives of South Africa (SAB). ECB, Vol. 10, ref. 56/8/1. National Archives of South Africa (SAB). ECB, Vol. 4, ref. 24. National Archives of South Africa (SAB). HEN, Vol. 3370, ref. 507/1/1. National Archives of South Africa (SAB). HEN, Vol. 3387, ref. 508. National Archives of South Africa (SAB). MNW, Vol. 634, ref. MM 2879/22. National Archives of South Africa (SAB). MNW, Vol. 682, ref. MM2990/23. National Archives of South Africa (SAB). MNW, Vol. 687, ref. MM3396/23. National Archives of South Africa (SAB). MNW, Vol. 717, ref. MM1288/24. National Archives of South Africa (SAB). MNW, Vol. 717, ref. MM1367/24. National Archives of South Africa (SAB). MNW, Vol. 785, ref. MM1711/25. National Archives of South Africa (SAB). PM, Vol. 1/2/56, ref. 15/6. National Archives of South Africa (SAB). SAS, Vol. 19, ref. ELEC170/1. National Archives of South Africa (SAB). SAS, Vol. 19, ref. ELEC274/12. National Archives of South Africa (SAB). TES, Vol. 7996, ref. F103/13. National Archives of South Africa (SAB). VBW, Vol. 565, ref. 13/1/4/4054/53. National Archives of South Africa (TAB). CT, Vol. 155, ref. T39/56.

Historical Papers, William Cullen Library, University of the Witwatersrand Historical Papers, University of the Witwatersrand. Collection A1913, Box 32. Historical Papers, University of the Witwatersrand. Collection A1913, Box 34. Historical Papers, University of the Witwatersrand. Collection A1913, Box 35. Historical Papers, University of the Witwatersrand. Collection A1913, Box 434.

Manuscripts Collection, University of Cape Town (UCT) UCT Libraries Special Collections, Manuscripts, Collection BC697, Item A15.1. UCT Libraries Special Collections, Manuscripts, Collection BC697, Item A15.2. UCT Libraries Special Collections, Manuscripts, Collection BC697, Item A15.3. UCT Libraries Special Collections, Manuscripts, Collection BC697, Item A15.5. UCT Libraries Special Collections, Manuscripts, Collection BC697, Item A15.6.

- 116 -

Monographs Seventy Golden Years, 1886-1956. Johannesburg: Municipal Public Relations Bureau, n.d. Beaty, H. Wayne and Donald G. Fink. Standard Handbook for Electrical Engineers. 16th ed. New York, NY: McGraw-Hill Professional, 2013. Bickford-Smith, Vivian. The Emergence of the South African Metropolis: Cities and Identities in the Twentieth Century. Cambridge: Cambridge University Press, 2016. Christie, Renfrew. Electricity, Industry and Class in South Africa. London: The Macmillan Press Ltd, 1984. Clark, Nancy L. Manufacturing Apartheid: State Corporations in South Africa. Yale Historical Publications New Haven, CT: Yale University Press, 1994. Conradie, S. R. and L. J. M. Messerschmidt. A Symphony of Power: The Eskom Story. Johannesburg: Chris van Rensburg Publications, 2000. Dubow, Saul. A Commonwealth of Knowledge: Science, Sensibility, and White South Africa 1820-2000. Oxford: Oxford University Press, 2006. Escom. Escom House. Johannesburg: Escom, 1936. Fig, David. Uranium Road: Questioning South Africa's Nuclear Direction. Johannesburg: Jacana, 2005. Hecht, Gabrielle. Being Nuclear: Africans and the Global Uranium Trade. Cambridge, Massachusetts: MIT Press, 2012. Hughes, Thomas P. Networks of Power: Electrification in Western Society, 1880-1930. Baltimore, MD: Johns Hopkins University Press, 1983. Jaglin, Sylvy and Alain Dubresson. Eskom: Electricity and Technopolitics in South Africa. Cape Town: UCT Press, 2016. First printed as Eskom. Électricité et pouvoir en Afrique du Sud. Paris: Éditions Karthala, 2015. Lieberman, Jennifer L. Power Lines: Electricity in American Life and Letters, 1882-1952. Inside Technology, edited by Bijker, Wiebe E., W. Bernard Carlson and Trevor Pinch. Cambridge, MA: MIT Press, 2017. McNichol, Tom. AC/DC: The Savage Tale of the First Standards War. San Francisco, CA: Jossey-Bass, 2006. McRae, Ian. The Test of Leadership: 50 Years in the Electricity Supply Industry of South Africa. Johannesburg: EE Publishers, 2006. Newby-Fraser, A. R. Chain Reaction: Twenty Years of Nuclear Research and Development in South Africa. Pretoria: The Atomic Energy Board, 1979. Nye, David E. Electrifying America: Social Meanings of a New Technology. Cambridge, MA: MIT Press, 1990.

- 117 -

Nye, David E. When the Lights Went Out: A History of Blackouts in America. Cambridge, MA: MIT Press, 2010. Perrow, Charles. Normal Accidents: Living With High Risk Technologies. Princeton, NJ: Princeton University Press, 1984. Richelson, Jeffrey T. Spying on the Bomb: American Nuclear Intelligence from Nazi Germany to Iran and North Korea. New York: W. W. Norton, 2007. Rodgers, Daniel T. Atlantic Crossings: Social Politics in a Progressive Age. Cambridge, MA: Belknap Press, 2000. Shorten, John R. The Johannesburg Saga. Johannesburg: John R. Shorten, 1979. Speight, James G. The Chemistry and Technology of Coal. 3rd ed. Boca Raton, FL: CRC Press, 2012. Van Onselen, Charles. New Babylon, New Nineveh: Everyday Life on the Witwatersrand 1886 - 1914. Johannesburg: Jonathan Ball Publishers, 2001. Von Schnitzler, Antina. Democracy's Infrastructure: Techno-Politics and Protest after Apartheid. Princeton, NJ: Princeton University Press, 2016. Weart, Spencer R. The Rise of Nuclear Fear. Cambridge, MA: Harvard University Press, 2012.

Edited Collections and Book Chapters Annecke, Wendy. "Still in the Shadows: Women and Gender Relations in the Electricity Sector in South Africa." In Electric Capitalism: Recolonising Africa on the Power Grid, edited by David A. McDonald, p. 288-320. Cape Town: HRSC Press, 2009. Bijker, Wiebe E., Thomas P. Hughes and Trevor Pinch, eds. The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology. Cambridge, MA: MIT Press, 2012. Edwards, Paul N. "Infrastructure and Modernity: Force, Time, and Social Organization in the History of Sociotechnical Systems." In Modernity and Technology, edited by Thomas J. Misa, Philip Brey and Andrew Feenberg, pp. 186-225. Cambridge, MA: MIT Press, 2003. Fig, David. "A Price Too High: Nuclear Energy in South Africa." In Electric Capitalism: Recolonising Africa on the Power Grid, edited by David A. McDonald, p. 180-201. Cape Town: HSRC Press, 2009. Greenberg, Stephen. "Market Liberalisation and Continental Expansion: The Repositioning of Eskom in Post-Apartheid South Africa." In Electric Capitalism: Recolonising Africa on the Power Grid, edited by David A. McDonald, pp. 73-108. Cape Town: HSRC Press, 2009. Hecht, Gabrielle. "On the Fallacies of Cold War Nostalgia: Capitalism, Colonialism, and South African Nuclear Geographies." In Entangled Geographies: Empire and Technopolitics in

- 118 -

the Global Cold War, edited by Gabrielle Hecht, p. 75-99. Cambridge, MA: MIT Press, 2011. Hecht, Gabrielle, ed. Entangled Geographies: Empire and Technopolitics in the Global Cold War. Cambridge, MA: MIT Press, 2011. Hughes, Thomas P. "The Evolution of Large Technological Systems." In The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology, edited by Wiebe E. Bijker, Thomas P. Hughes and Trevor Pinch, pp. 45-76. Cambridge, MA: MIT Press, 2012. McDaid, Liz. "Renewable Energy: Harnessing the Power of Africa?" In Electric Capitalism: Recolonising Africa on the Power Grid, edited by David A. McDonald, p. 202-28. Cape Town: HSRC Press, 2009. McDonald, David A., ed. Electric Capitalism: Recolonising Africa on the Power Grid. Cape Town: HSRC Press, 2009. Misa, Thomas J., Philip Brey and Andrew Feenberg, eds. Modernity and Technology. Cambridge, MA: MIT Press, 2003. Naidoo, Prishani and Ahmed Veriava. "From Local to Global (And Back Again?): Anti- Commodification Struggles of the Soweto Electricity Crisis Committee." In Electric Capitalism: Recolonising Africa on the Power Grid, edited by David A. McDonald, p. 321-37. Cape Town: HSRC Press, 2009. Pinch, Trevor J. and Wiebe E. Bijker. "The Social Construction of Facts and Artifacts: Or How the Sociology of Science and the Sociology of Technology Might Benefit Each Other." In The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology, edited by Wiebe E. Bijker, Thomas P. Hughes and Trevor Pinch, pp. 11-44. Cambridge, MA: MIT Press, 2012. Posel, Deborah. "The Apartheid Project, 1948-1970." In The Cambridge History of South Africa, vol. 2, edited by Robert Ross, Anne Kelk Mager and Bill Nasson, pp. 319-68. Cambridge: Cambridge University Press, 2012. Ross, Robert, Anne Kelk Mager and Bill Nasson. "Introduction." In The Cambridge History of South Africa, vol. 2, edited by Robert Ross, Anne Kelk Mager and Bill Nasson, pp. 1-16. Cambridge: Cambridge University Press, 2012. Ross, Robert, Anne Kelk Mager and Bill Nasson. The Cambridge History of South Africa, vol. 2. Cambridge: Cambridge University Press, 2012. Ruiters, Greg. "Free Basic Electricity in South Africa: A Strategy for Helping or Containing the Poor?" In Electric Capitalism: Recolonising Africa on the Power Grid, edited by David A. McDonald, p. 248-63. Cape Town: HSRC Press, 2009.

- 119 -

Schwartz Cowan, Ruth. "The Consumption Junction: A Proposal for Research Strategies in the Sociology of Technology." In The Social Construction of Technological Systems: New Directions in the Sociology and History of Technology, edited by Wiebe E. Bijker, Thomas P. Hughes and Trevor Pinch, pp. 253-72. Cambridge, MA: MIT Press, 2012. Slaton, Amy and Janet Abbate. "The Hidden Lives of Standards: Technical Prescriptions and the Transformation of Work in America." In Technologies of Power: Essays in Honor of Thomas Parke Hughes and Agatha Chipley Hughes, edited by Michael Thad Allen and Gabrielle Hecht, pp. 95-143. Cambridge, MA: MIT Press, 2001. Van Heusden, Peter. "Discipline and the New 'Logic of Delivery': Prepaid Electricity in South Africa and Beyond." In Electric Capitalism: Recolonising Africa on the Power Grid, edited by David A. McDonald, p. 229-47. Cape Town: HSRC Press, 2009.

Journal Articles "Charles H. Merz, D.Sc.". Journal of the Institution of Electrical Engineers 87, no. 528 (December 1940): pp. 708-10. doi:10.1049/jiee-1.1940.0213. Albright, David. "South Africa Comes Clean." Bulletin of the Atomic Scientists 49, no. 4 (May 1993): pp. 3-5. Albright, David and Corey Gay. "A Flash from the Past." Bulletin of the Atomic Scientists 53, no. 6 (November/December 1997): pp. 15-17. Clark, Nancy. "South African State Corporations: 'The Death Knell of Economic Colonialism'?". Journal of Southern African Studies 14, no. 1 (October 1987): pp. 99-122. http://www.jstor.org/stable/2636698. Cross, Tim. "The Afrikaner Takeover: Nationalist Politics and the Colonization of South Africa's Parastatals, 1948 to 1960." Institute of Commonwelth Studies' Collected Seminar Papers 48 (1994): pp. 121-31. Dobson, J. H. "The Distribution Plant of the Johannesburg Municipal Electric Supply System." Transactions of the South African Institute of Electrical Engineers 6 (November 1915): pp. 279-324. Edwards, Paul N. and Gabrielle Hecht. "History and the Technopolitics of Identity: The Case of Apartheid South Africa." Journal of Southern African Studies 36, no. 3 (September 2010): pp. 619-39. doi:10.1080/03057070.2010.507568.

- 120 -

Harris, Verne, Sello Hatang and Peter Liberman. "Unveiling South Africa's Nuclear Past." Journal of Southern African Studies 30, no. 3 (September 2004): pp. 457-75. http://www.jstor.org/stable/4133904. Hecht, Gabrielle. "An Elemental Force: Uranium Production in Africa, and What It Means to be Nuclear." Bulletin of the Atomic Scientists 68, no. 2 (March/April 2012): pp. 22-33. doi:10.1177/0096340212440352. Hecht, Gabrielle. "Negotiating Global Nuclearities: Apartheid, Decolonization, and the Cold War in the Making of the IAEA." Osiris 21, no. 1 (2006): pp. 25-48. http://www.jstor.org/stable/10.1086/507134. Hecht, Gabrielle. "The Power of Nuclear Things." Technology and Culture 51, no. 1 (January 2010): pp. 1-30. http://www.jstor.org/stable/40646990. MacDonald, Michael and Wilmot James. "The Hand on the Tiller: The Politics of State and Class in South Africa." Journal of Modern African Studies 31, no. 3 (September 1993): pp. 387-405. http://www.jstor.org/stable/161202. Martschukat, Jürgen. ""The Art of Killing by Electricity": The Sublime and the Electric Chair." Journal of American History 89, no. 3 (December 2002): pp. 900-921. http://www.jstor.org/stable/3092345. Masiza, Zondi. "A Chronology of South Africa's Nuclear Program." Nonproliferation Review 1, no. 1 (Fall 1993): pp. 34-53. doi:10.1080/10736709308436523. Neustadter, Roger. "The "Deadly Current": The Death Penalty in the Industrial Age." Journal of American Culture 12, no. 3 (September 1989): pp. 79-87. doi:10.1111/j.1542- 734X.1989.1203_79.x. Reynolds, Terry S. and Theodore Bernstein. "Edison and "the Chair"." IEEE Technology and Society Magazine 8, no. 1 (March 1989): pp. 19-28. doi:10.1109/44.17683. Robinson, Jennifer. "Johannesburg's 1936 Empire Exhibition: Interaction, Segregation and Modernity in a South African City." Journal of Southern African Studies 29, no. 3 (September 2003): pp. 759-89. http://www.jstor.org/stable/3557441. Schroeder, Fred E. H. "More "Small Things Forgotten": Domestic Electrical Plugs and Receptacles, 1881-1931." Technology and Culture 27, no. 3 (July 1986): pp. 525-543. http://www.jstor.org/stable/3105384.Sparks, Stephen. "Between 'Artificial Economics' and the 'Discipline of the Market': Sasol from Parastatal to Privatisation." Journal of Southern African Studies 42, no. 4 (2016): pp. 711-24. doi:10.1080/03057070.2016.1186787. Taylor, Damon. "Plugging In: Power Sockets, Standards and the Valencies of National Habitus." Journal of Material Culture 20, no. 1 (2015): pp. 59-75. doi: 10.1177/1359183514557765.

- 121 -

Van Wyk, Anna-Mart. "Apartheid's Atomic Bomb: Cold War Perspectives." South African Historical Journal 62, no. 1 (2010): pp. 100-120. doi:10.1080/02582471003778367. Van Wyk, Anna-Mart. "South Africa's Nuclear Programme and the Cold War." History Compass 8, no. 7 (2010): pp. 562-72. doi:10.1111/j.1478-0542.2010.00699.x. Van Wyk, Jo-Ansie. "Nuclear Terrorism in Africa: The ANC's Operation Mac and the Attack on the Koeberg Nuclear Power Station in Africa." Historia 60, no. 2 (November 2015): pp. 51-67. doi:10.17159/2309-8392/2015/v60n2a3. Van Wyk, Jo-Ansie and Anna-Mart van Wyk. "From the Nuclear Laager to the Non- Proliferation Club: South Africa and the NPT." South African Historical Journal 67, no. 1 (2015): pp. 32-46. doi:10.1080/02582473.2014.977337. Van Wyk, Martha. "Sunset over Atomic Apartheid: United States-South African Nuclear Relations, 1981-93." Cold War History 10, no. 1 (February 2010): pp. 51-79. doi:10.1080/14682740902764569. Van Wyk, Martha S. "Ally or Critic?: The United States' Response to South African Nuclear Development, 1949-1980." Cold War History 7, no. 2 (May 2007): pp. 195-225. doi:10.1080/14682740701284124. Von Schnitzler, Antina. "Citizenship Prepaid: Water, Calculability, and Techno-Politics in South Africa." Journal of Southern African Studies 34, no. 4 (2008): pp. 899-917. doi:10.1080/03057070802456821. von Schnitzler, Antina. "Traveling Technologies: Infrastructure, Ethical Regimes, and the Materiality of Politics in South Africa." Cultural Anthropology 28, no. 4 (November 2013): pp. 670-93. doi:10.1111/cuan.12032. Wolpe, Harold. "Capitalism and Cheap Labour-Power in South Africa: From Segregation to Apartheid." Economy and Society 1, no. 4 (1972): pp. 425-56. doi:10.1080/03085147200000023.

Theses and Dissertations Ballim, Faeeza. "The Evolution of Large Technical Systems in the Waterberg Coalfield of South Africa: From Apartheid to Democracy." PhD Thesis, University of the Witwatersrand, 2017. Sparks, Stephen John. "Apartheid Modern: South Africa's Oil from Coal Project and the History of a South African Company Town." PhD Thesis, University of Michigan, 2012.

- 122 -

Newspapers Cape Times, 1984. Energize, 2006. Mail & Guardian, 1995. Nucleonics Week, 1981. Nucleonics Week, 1985. The Star, 1982.

Government Documents Government Gazette of 4 September, 1987, vol. 267, no. 10893. Government Gazette of 9 September, 1948, vol. CLIII, no. 4022. Government Gazette of 24 July, 1922, vol. 44, no. 1256. Government Gazette of June 18, 1947, vol. 148, no. 3834. Report of the Commission of Enquiry into the Application of Nuclear Power in South Africa. Pretoria: The Government Printer, c. 1961. Atomic Energy Board. Report on the Investigation into the Possible Introduction of Nuclear Power in the Republic of South Africa. 1968. Bukula, Thembani and Smunda S. Mokoena, Investigation into the Electricity Outages in the Western Cape for the Period November 2005 to March 2006. NERSA, n.d. http://www.sinetech.co.za/news/wcreport.pdf Eskom Annual and Statistical Reports, 1923-2000. http://www.eskom.co.za/sites/heritage/Pages/Annual-Reports.aspx. International Atomic Energy Agency. Information Circular, INFCIRC/244. Vienna: International Atomic Energy Agency, 1977. International Atomic Energy Agency. Operating Experience with Nuclear Power Stations in Member States in 2014. International Atomic Energy Agency, 2015. http://www- pub.iaea.org/MTCD/Publications/PDF/OPEX_2015_CD_web.pdf

Web Pages and Miscellaneous Sources "Thunderbolts and Lightning." Wellcome Collection. Last modified March 29, 2017. Accessed October 23, 2017. https://wellcomecollection.org/articles/thunderbolts-and-lightning. Bureau International des Poids et Mesures. The International System of Units (SI). 8th ed. Sèvres Cedex: Organisation Intergouvernemetale de la Convention du Mètre, 2014. https://www.bipm.org/utils/common/pdf/si_brochure_8_en.pdf.

- 123 -

Campbell, Hank. "Is Thor Mighty or Just Magic?" Science 2.0 (blog), Last modified October 14, 2013. http://www.science20.com/science_20/thor_mighty_or_just_magic-104019. Eskom. "Nuclear Energy: Koeberg Power Station." Eskom. Accessed July 7, 2015. http://www.eskom.co.za/AboutElectricity/FactsFigures/Documents/Nuclear.pdf. Eskom. "Power Station GPS Coordinates." Accessed December 14, 2017. http://www.eskom.co.za/Whatweredoing/ElectricityGeneration/PowerStations/Pages/Powe r_Station_GPS_Coordinates.aspx. Statistics South Africa. General Household Survey. Statistical Release P0318. Pretoria: Stats SA, 2016. http://www.statssa.gov.za/publications/P0318/P03182016.pdf. Thompson, Ambler and Barry N. Taylor. Guide for the Use of the International System of Units (SI). NIST Special Publication 811. Gaithersberg, MD: National Institute of Standards and Technology, 2008. http://ws680.nist.gov/publication/get_pdf.cfm?pub_id=200349. U.S. Department of Commerce. The International System of Units (SI). National Bureau of Standards Special Publication 330. Washington D.C.: U.S. Government Printing Office, 1977. World Bank. "Access to Electricity (% of Population)." Last modified 2014. Accessed January 29, 2018. https://data.worldbank.org/indicator/EG.ELC.ACCS.ZS?end=2014&locations=ZA&start= 1990&view=chart. World Nuclear Association. "Nuclear Power Reactor Characteristics." World Nuclear Association. Last modified May 2017. http://www.world-nuclear.org/getmedia/80f869be- 32c8-46e7-802d-eb4452939ec5/Pocket-Guide-Reactors.pdf.aspx.

- 124 -