LARGE POWER USERS GUIDE
Large Power Users (LPU) Guide Large Power Users (LPU) Guide 20201 Who We Are
Uganda’s main electricity distribution company, listed on the Uganda Securities Exchange and cross listed on the Nairobi Securities Exchange. We operate a 20 year electricity distribution concession from the Government of Uganda. Following reforms in 1999, Uganda adopted a single buyer electricity sector model, where Uganda Electricity Transmission Company Limited (UETCL) is the System Operator, responsible for purchasing electricity from all Independent Power Producers, import and export of electricity. UETCL is our sole supplier.
As a distributor, we supply electricity to customers, involving operation, maintenance and upgrade of power infrastructure, electricity retail and provision of related services. The Electricity Regulatory Authority are responsible for sector regulation, with their mandate including setting operating standards and appropriate end user tariffs.
Our Our Values Vision Safety Powering communities, business Customer Service and industry for a prosperous Integrity Uganda Teamwork Innovation Our Mission To supply our customers with safe, reliable electricity through an efficient distribution network and with passionate people, while delivering sustainable shareholder value.
2 Large Power Users (LPU) Guide Large Power Users (LPU) Guide Who are Large Power Users? (LPUs)
These are categorised as below:
Supplied at 415V with maximum demand up Small and Medium Industrial to 500kVA
Supplied at 11kV or 33kV with maximum Large Industrial demand of 1500kVA Supplied at 11kV or 33kV with average Extra Large Industrial demand exceeding 1500kVA (dealing in Manufacturing)
**The electricity network operates at a frequency of 50Hz
Where to Apply Prospective customers should apply through the nearest Umeme Service Centre during the planning stages of the construction. The manager will organize a site visit within 3 working days and assess network capacity to support the intended business.
The full list of service centres is on Page 10.
Uganda Investment Authority One Stop Centre (OSC) – Umeme Office
OSC is located at Twed Plaza along Lumumba Avenue in Uganda Investment Authority Office. It was established to enable the local and foreign investors access the services to start up a business. Among the offices/agencies found at OSC is Umeme. Together with the area Umeme offices, the OSC forecasts the load requirements in Industrial parks and liaises with the Engineering teams across the energy sector chain to bridge the network gaps.
Call or Whatsapp us through 0313360050 for more details
Large Power Users (LPU) Guide Large Power Users (LPU) Guide 3 Requirements for a Connection
Type of Connection Requirements Small Industrial • Certificate of Completion of Internal Wiring • Copy of Certificate of Incorporation (Companies). • Customer identification documents (National ID). Medium Industrial Copy of Proof of Ownership or Tenancy (deeds or tenancy agreement) High Industrial Duly filled wayleaves consent form (where applicable)
**Customer can visit any of our service centers to obtain more information or visit our web site.
What are Wayleaves? Rights of way acquired by persons/entities who have applied for supply, provision and installation and maintenance of equipment necessary to supply electricity to their premises.
Where a site visit reveals the need for wayleaves, the applicant will be notified in writing. In response, the applicant must provide proof that wayleaves were acquired in writing from affected property owners before a connection can be effected.
Umeme will support the applicant with useful technical advice to aid this process. Procedure Prospective customers should notify their local Umeme Service Centre Manager during planning stages. The Service Centre Manager will organise a site visit within 3 working days and assess network capacity to support the intended business.
Following the outcome of the site assessment, the Customer will be advised on the next steps by the Service Centre Manager. An application for electricity by the customer should be addressed to the Service Centre Manager, with a copy sent to the Regional Manager.
Our Standard Charges for a Connection Item Amount Inspection Fees Small Industrial 88,500 Medium & Large Industrial 118,000 Security Deposit Small Industrial 200,000 Medium Industrial 1,000,000 Large Industrial 2,000,000 Cost of Works (incl Varies depending on material Labour and Transport) requirements.
All payments can be made through the following Banks. Do not make direct payments to any of our staff or contractors.
4 Large Power Users (LPU) Guide Large Power Users (LPU) Guide Our Partner Banks:
Standard Chartered, Bank Of Africa, KCB, DFCU Bank, Citi Bank, Housing Finance Bank, Stanbic Bank, Equity Bank, Post Bank, Diamond Trust Bank, Orient Bank, United Bank for Africa, Finance Trust Bank, Absa Bank, Centenary Bank and Bank Of Baroda, NC Bank
Our Commitment to You We promise to effect new connections without unnecessary delays to the following timelines:
Site Visit - 3 days
Detailed Survey and Drawings (If - 5 Days applicable)
Quotation - 1 Day
Invoice - 1 Day
Construction and Commissioning - 15 Days
**An invoice will be valid for 30 days from issuance
Large Power Users (LPU) Guide Large Power Users (LPU) Guide 5 Automated Meter Reading (AMR) for Large Power Users
The Automated Meter Reading (AMR) is a technology of remote collection of energy consumption and other meter data to a central location for billing, troubleshooting, and further analysis aimed at improving on the service delivery to its Large Power Users
Web Access
You can view your consumption and load profile data over the internet. Below are the steps through which you can obtain login details.
STEP Download the AMR Web Access Agreement Form from our 01 website.
Fill in the form and submit it to the STEP Umeme district office which covers your area. 02
STEP Your request will be reviewed by the district supervisor and if approved, you will be contacted 03 with your login details.
Log into the Online AMR System STEP and access your consumption data and load profiles. 04