Environmental Assessment Document
Due Diligence Report Environment
Loan Number: 2796 and Grant Number: 0267 NEP May 2013
Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing
Baglung-Kushmisera Road Subproject (Kathekhola-Tallo Sarange road section), Baglung
Prepared by the Government of Nepal
The Environmental Assessment is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
District Development Committee, Baglung District Technical Office, Baglung Decentralized Rural Infrastructure and Livelihood Project-Additional Financing (DRILP-AF) District Project Office, Baglung
Decentralized Rural Infrastructure and Livelihood Project-Additional Financing (DRILP-AF)
Detailed Project Report Baglung-Kushmisera Road Subproject (Kathekhola-Tallo Sarange road section)
Section III: Safeguards Volume I: Due Diligence Report-Safeguard (Environment)
May, 2013
Detail Project Report of Baglung- Kushmisera Road Subproject, Baglung Section III: Safeguard Vol .I Environment
Contents
1 Introduction ...... 1 2 Implementation Status ...... 1 3 Additional Requirements ...... 1 3.1 Grievance Redress Mechanism ...... 1 3.2 Establishment of Safeguard Desk ...... 1 3.3 Compensatory Plantation ...... 2 3.4 Public Disclosure ...... 2 3.5 Consideration of Climate Change Aspects ...... 2 3.6 Capacity Building ...... 3 4. Environmental Management Action Plan and Cost ...... 3 5. Outstanding Issues ...... 7 6. Environmental Monitoring and Reporting ...... 8 7. Conclusion and recommendation ...... 8
List of Tables
Table 1: Environmental Management Action Plan (EMAP) for Baglung-Kushmisera Road section ...... 4 Table 2: EMAP Cost Estimate...... 7 Table 3: Outstanding Activities with action plan...... 7
List of Appendices
Appendix I: Compensatory Plantation for Trees in Private Land Appendix II: Environmental Monitoring Format
Detail Project Report of Baglung- Kushmisera Road Subproject, Baglung Section III: Safeguard Vol .I Environment
1 Introduction
1. The initial environmental examination (IEE) report of Baglung-Kushmisera road subproject in Baglung district has already been approved by the present Ministry of Federal Affairs & Local Development (MoFALD) then the Ministry of Local Development (MLD) on 19th Shrawan 2067 BS (4th August 2010 AD) and concurrence has been given by the Asian Development Bank (ADB) on 27th April 2010 AD (14th Chaitra 2066 BS). Total length of the road is 21.52 km and this passes through Bhakunde, Paiyupata, Narayansthan & Amalachaur VDCs. Under DRILP, it has been proposed for the upgrading through gravelling of the existing road from fair weather to all weather road standard. However, the road construction work has not been started in DRILP. District Development Committee (DDC) Baglung intends to undertake the construction work in DRILP-AF from Kathe Khola Bridge to Tallo Sarangi (14.380 km length) within four VDCs namely Bhakunde, Paiyupata, Narayansthan & Amalachaur. Starting point is shifted to 620 m ahead from Maldhunga to Kathekola. However, present chainage of starting point Kathekhola is taken as Ch 0+620.
2. As per the Project Administration Manual (PAM) of DRILP-AF, additional requirements related to environmental safeguards have been included for Baglung-Kushmisera road subproject (Kathekhola - Tallo Sarange road section). 2 Implementation Status
3. Since construction of this section of the road has not been started yet, there is no implementation of any environmental safeguard activities.
3 Additional Requirements
4. Following additional requirements will be needed for the implementation of Baglung- Kushmisera road subproject according to PAM of DRILP-AF.
3.1 Grievance Redress Mechanism 5. A Grievance Redress Committee (GRC) has already been set-up for resettlement purpose. The same GRC has been reformed in order to address environmental related concerns and grievances of the local communities and affected parties as given in Due Diligence Report of Social Safeguards (resettlement). The GRC comprises of representatives from local authorities, affected parties and well-reputed persons as mutually agreed with the local authorities and affected persons. The chief of the Environmental and Social Unit of District Development Committee (DDC) represents the implementing agency in the GRC. This committee will address the subproject related grievances of the affected parties and will provide them a public forum to raise their concern or objections.
3.2 Establishment of Safeguard Desk 6. The safeguard desk has been established in DDC, Baglung comprising environment and social safeguard personnel with a focal person Mr. Yama Kant Pandey, Planning, Monitoring
1
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
& Administrative Officer has been assigned as coordinator of the safeguard desk. The desk will conduct regular monitoring of EMP compliance and record them as well as organize monthly safeguard meeting which will be participated by all technical, environment and social team of the District Project Office (DPO) and District Implementation Support Consultant (DISC). The meeting will discuss environmental performance in the subproject works, issues and problems being encountered, agree on their mitigation measures, prepare corrective action plan and ensure their implementation. The desk will also maintain coordination and networking with environmental and social units of DDC and environment section of MoFALD. The safeguard desk will maintain minutes of meeting of each safeguard meeting and through DPO will report all the safeguard matters along with copy of the minutes to the DRILP AF-Project Coordination Unit.
3.3 Compensatory Plantation 7. Though the road alignment passes through Tallo Sarangi Takuri (Ch 14+800 to 15+000) and Dandakharka (Ch 2+700 to 3+050 & 3+475 to 3+525) community forests, no trees need to be felled form these forests. However 1,256 trees from the private land will be removed. For the loss of 1,256 trees from the private land, plantation at the ratio of 1:1 trees will be done by the respective private land owners and seedling and plantation cost (NRs.46,522.24) will be provided to them (refer Appendix I for detail list).
3.4 Public Disclosure 8. Approved IEE report has been kept in the information center of DDC Baglung and uploaded in the websites of DRILP and ADB. Nepali translation of executive summary, identified impacts, recommended mitigation measures and EMP of approved IEE report has been prepared and will be publicly disclosed to the concern VDCs once the approval is obtained and will be reported during progress.
3.5 Consideration of Climate Change Aspects 9. Since this subproject is located in hilly and mountainous area of Nepal which is more vulnerable to environmental and climate change attributes, such as deforestation, cultivation on slopes and slope failure, change in precipitation patterns, higher rainfall intensity causing accelerated soil erosion and landslides, damaging causeways and bridges. Due consideration to climate change aspects have been included during design stage and any further changes in design will also be implemented.
10. Following climate change adaptation measures will be considered during the construction and operation of this road: Likely local effects of climate change will be assessed through observation and regular monitoring like drainage system, erosion control etc. Adequate and timely maintenance and early warning system will be done. Awareness raising activities will be conducted about climate change issues and adaptation and mitigation measures. No tree or vegetation will be removed unless absolutely necessary to reduce deforestation and plantation will be done to cut carbon per capita emissions. Improved Chulho (firewood stoves) will be promoted
2
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
3.6 Capacity Building 11. District level staff of DDC, DTO, DPO, DISC and BGs and contractors’ staff will be given awareness raising orientation training to increase their capacity in environmental safeguards. These trainings will be included in rural livelihood improved and capacity and decentralized local governance enhanced output as well as in Resettlement Plan.
4. Environmental Management Action Plan and Cost
12. There is an EMP in the IEE report of this project. However, environmental management action plan (EMAP) has been prepared to include practical mitigation measures that will be implemented during road construction along with the estimated cost. EMAP is given in Table 3 and estimated cost is given in Table 4.
3
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
Table 1: Environmental Management Action Plan (EMAP) for Baglung-Kushmisera Road section
Activity Impacts Benefit Augmentation/Mitigation Schedule Responsible Agency Measures Executing Supporting Road Employment Providing life skill training to workers for During DPO/DTO/ VWRCC/DDC/CISC constru Generation and income generation activities to improve construction ction Increase their livelihood. DISC Income
Road Change in Road side plantation along the road During DPO/DTO/ VWRCC/DDC/DFO constru Land Use as far as possible construction DISC ction Applying additional protective measures that the remaining land will not be lost due to erosion Road Slope Adoption of bio-engineering During DPO/DTO/ VWRCC/DDC/CISC constru Instability techniques to rehabilitate the construction DISC ction landslides and stabilize slopes Ensuring minimum damage of vegetation during construction Road Hazards due to Excess spoils will be disposed in During DPO/DTO/ VWRCC/DDC constru Spoil Disposal specified spoil disposal sites at Ch construction DISC ction 2+300 to Ch 2+350, Ch 3+100 to Ch 3+150, Ch 4+090 to Ch 4+160, Ch +200 to Ch 6+230, Ch 7+600 to Ch 7+620, Ch 10+990 to Ch 11+030, Ch 12+100 to Ch 12 +150 & Ch 14+500 to Ch 14+550 in a controlled manner and the sites will be covered by vegetation through bio- engineering techniques. Toe walls will be provided to manage spoil disposal Road Disruption of Drain water discharge into farmland or During DPO/DISC VWRCC/DDC constru Natural Water, risky locations will be avoided. construction ction Surface Water
4
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
Activity Impacts Benefit Augmentation/Mitigation Schedule Responsible Agency Measures Executing Supporting Flow and Drainage
Road Air Dust, Noise Use of face mask by the workers to During DPO/DTO/ VWRCC/DDC constru and Water minimize air pollution due to dust construction DISC ction Pollution generation Use of ear muffles to lessen noise pollution during rock breaking and quarrying Avoiding the disposal of excavated materials in the water bodies Road Impact due to After the extraction is completed, the During DPO/DISC/ VWRCC/DDC constru Quarrying quarry sites identified along the bank of construction DTO/BG/ ction Kaligandaki river, is 5 km far from the after Contractor road alignment. extraction is completed Road Impact due to Camp site will be located away from During DPO/DISC/ VWRCC/DDC constru campsite productive land and forest area. construction DTO/BG/ ction Potential sites are at Ch 4+100, Ch Contractor 8+300, Ch 12+800 & Ch 14 +700. Local houses will be used as labour camp and rent/compensation will be paid to land owner. Road Loss of Forest Compensatory plantation of 1,256 trees During DPO/DISC/ DFO/DDC/VWRCC constru Vegetation at the ratio of 1:1 trees will be done in construction DTO/Land ction private land. in rainy owner season
Road Loss of One farm house (Ch 4+300), four Before road DPO/DISC VWRCC/DDC/DADO constru Agricultural residence buildings (Ch 5+010, Ch construction /CDO ction Land & Private 5+100, Ch 5+120, Ch 5+050) two
Properties cowsheds (Ch 6+940, Ch 7+300)
5
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
Activity Impacts Benefit Augmentation/Mitigation Schedule Responsible Agency Measures Executing Supporting and one toilet/septic tank (Ch 12+740) will be affected and will be compensated. A separate Resettlement Plan has been prepared to address land acquisition and compensation issues. Road Disruption of One community building at Ch Before road DPO/DTO DDC/VWRCC constru Community 7+350 will be affected and will be construction DISC ction Infrastructures reinstated.
Road Occupational The workers will be provided with During road DPO/DTO/ VWRCC/DDC constru Health and helmets, masks, muffles, drinking construction DISC/Contr ction Safety water facility. Temporary pit latrine actor will be established at construction sites to control open defecation and pollution of water bodies by the workers. Workers will be provided with first aid and health facilities. Group accidental insurance will be done for the workers.
6
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
Table 2: EMAP Cost Estimate
SN Items Cost (NRs.) Remarks 1 Benefit augmentation cost 1.1 Capacity building (training) Included in rural livelihood improved and capacity and decentralized local governance enhanced output as well as in resettlement plan 2 Environmental mitigation cost
2.1 Spoil disposal and slope Included in civil works cost stabilization 2.2 Bioengineering Actual cost estimate and included in civil works cost 2.3 Compensatory plantation in 46,522.24 private land 2.4 Road side plantation 50,000.00 2.5 Insurance for workers Included in civil works cost 2.6 Occupational health and Included in civil works cost safety 3 Environmental monitoring 211,000.00 Including central level monitoring cost cost also 3.1 Information signboard 50,000.00 Total 357,522.24
5. Outstanding Issues
13. Following Table 3 shows outstanding activities according to approved IEE report.
Table 3: Outstanding Activities with action plan
SN Activity Plan Responsibility Remarks
1 Bio Detail estimate and design DPO supported by engineering will be done for the DISC team bioengineering activities
2 Compensatory Necessary plants will be DDC supported by Plantation cost will Plantation in identified and arranged in DTO/DPO/DISC be provided to land private land coordination with respective owner private land owners
3 Roadside Estimate will be done and DDC supported by plantation location will be identified for DTO/DPO/DISC the roadside plantation
7
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
6. Environmental Monitoring and Reporting
14. Regular subproject level environmental monitoring will be done through safeguards desk. The subproject specific monitoring plan contained in the IEE report will be followed. Monitoring will be done by using monitoring checklist (refer Appendix II). The safeguard desk will organize monthly safeguard meeting to discuss environmental performance. The desk will also maintain coordination and networking with environmental and social units of DDC and environment section of MoFALD.
15. Reporting on environmental safeguards in subprojects will be regular, and included as a separate section in the monthly project progress report. Periodic environment monitoring report will be submitted to ADB through PCU for all the subprojects in a trimester basis.
7. Conclusion and recommendation
16. Bio-engineering protection measures will be done to rehabilitate all bare surfaces and to stabilize slopes after the construction of road. Therefore, bioengineering cost has been estimated on actual basis and included in the total project cost. Compensatory plantation will be done in coordination with concerned land owner and DFO Baglung giving priority to local and multiple use species. Budget for compensatory plantation has been estimated based on district rate of current fiscal year according to Ministry of Forest and Soil Conservation Norms, 2060 BS. Basic health facilities and occupational safety gears will be provided in adequate number to all workers. For contractor’s package this will be specified in particular conditions of contract clause. Safeguard desk will be responsible for the implementation, monitoring and reporting of the environmental issues.
8
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
APPENDICES
9
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
Appendix I Compensatory Plantation for Trees in Private Land
Name of Land Owner Chainage Chainage No. of plants Cost/Plant Total From To to be (NRs.) (NRs.) removed Aatmaram Poudel 5+990 6+060 25 37.04 926.00 Asmita Lamsal 6+900 6+940 7 37.04 259.28 Bal B. Roka 6+420 6+460 10 37.04 370.40 Bam B Khatri 8+610 8+660 7 37.04 259.28 Bhabishawr Acharya 4+850 4+850 1 37.04 37.04 Bhadrakali Khatri 7+840 7+900 10 37.04 370.40 Bharat Khadka 2+310 2+360 15 37.04 555.60 Bhawadatta Subedi 11+480 11+500 4 37.04 148.16 Bhim Rijal 4+350 4+380 4 37.04 148.16 Bhim B. Roka 7+340 7+380 23 37.04 851.92 Bhim B. Roka Chettri 8+500 8+590 3 37.04 111.12 Bhim B. Shahi 3+675 3+675 2 37.04 74.08 Bir B. Roka 7+610 7+650 13 37.04 481.52 Bir B. Thapa 2+560 2+570 4 37.04 148.16 Bishnu Datta Padhya 12+600 13+280 6 37.04 222.24 Bishnu Kumari 4+800 4+820 11 37.04 407.44 Sharma Paudel Chabai Lal Dhakal 10+300 10+500 1 37.04 37.04 Chabu Khatri 7+840 7+900 11 37.04 407.44 Chandra B. Shrestha 8+100 8+160 12 37.04 444.48 Dammar B. Roka 6+120 7+000 6 37.04 222.24 Dantakali Roka 8+420 8+450 9 37.04 333.36 Devi Parsad Rijal 4+850 4+890 17 37.04 629.68 Devi Raj Khatri 7+800 7+820 9 37.04 333.36 Devidatta Padhya 13+720 13+730 2 37.04 74.08 Devikala Paudel 12+410 12+425 4 37.04 148.16 Devikala Sharma 12+240 12+260 6 37.04 222.24 Dhan B. Majhi 13+120 13+120 1 37.04 37.04 Dhananjaya Padhya 12+760 13+120 38 37.04 1,407.52 Dhanapati Padhya 12+720 13+490 19 37.04 703.76 Dhankali Upaddhya 7+480 7+500 8 37.04 296.32 Dhanrupa Padhyani 6+690 6+850 26 37.04 963.04 Dil Singh Roka 7+600 7+610 5 37.04 185.20 Durga D. Poudel 5+990 6+170 44 37.04 1629.76 Durga Kumari Rijal 6+850 6+900 9 37.04 333.36 Gajendra Roka 8+190 8+210 22 37.04 814.88
10
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
Name of Land Owner Chainage Chainage No. of plants Cost/Plant Total From To to be (NRs.) (NRs.) removed Ganga Roka 8+810 8+900 15 37.04 555.60 Gangadhar Subedi 11+420 11+460 53 37.04 1,963.12 Gokarna Subedi 11+280 11+640 30 37.04 1,111.20 Jabi Lal Subedi 11+240 13+095 15 37.04 555.60 Jagannath Paudel 13+095 13+100 2 37.04 74.08 Jagat B. Roka 6+230 8+240 19 37.04 703.76 Kalawati Padhya 13+020 13+040 5 37.04 185.20 Karna B. Khatri 4+380 4+00 5 37.04 185.20 Karna B. Roka 7+260 7+270 34 37.04 1,259.36 Karna Kumari Malla 1+280 0+340 4 37.04 148.16 Khagaraj Poudel 6+115 6+130 3 37.04 111.12 Khageshowri Subedi 11+370 11+460 77 37.04 2,852.08 Kramasa 5+680 5+870 2 37.04 74.08 Krishna Kumari 14+640 14+680 3 37.04 111.12 Lamichane Lakshman Thapa 2+660 2+720 31 37.04 1148.24 Lal B Roka/Bel B 7+380 7+390 5 37.04 185.2 Roka Laxmi Subedi 12+470 12+480 13 37.04 481.52 Man B. Roka Chettri 8+760 8+810 27 37.04 1000.08 Min B. Roka 8+340 8+380 12 37.04 444.48 Mina Kumari Roka 8+620 8+660 8 37.04 296.32 Mohan Poudel 6+480 6+530 10 37.04 370.40 Nandakali Jaisi 13+600 13+620 9 37.04 333.36 Nandakali Subedi 11+585 11+600 15 37.04 555.60 Nar B. Thapa 4+530 4+560 9 37.04 333.36 Om B. Roka Chettri 8+670 8+700 21 37.04 777.84 Padam B. Roka 8+320 8+390 19 37.04 703.76 Padam Kala Padhya 5+680 5+870 13 37.04 481.52 Padam Kumari Roka 8+020 8+050 2 37.04 74.08 Padamlal Shrestha 10+140 10+150 72 37.04 2,666.88 Parjapati Padhya 12+730 12+750 7 37.04 259.28 Patiram Thapa 4+480 4+500 16 37.04 592.64 Prem B Khatri 7+380 7+382 8 37.04 296.32 Prem B.Malla 1+680 1+880 15 37.04 555.60 Purnakala Padhya 12+410 12+425 10 37.04 370.40 Raju Khadka 2+00 2+240 13 37.04 481.52 Resham Kumari Khatri 8+240 8+250 8 37.04 296.32 Run B. Roka 7+970 7+980 13 37.04 481.52 Sakas B. Roka 6+190 6+220 3 37.04 111.12
11
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
Name of Land Owner Chainage Chainage No. of plants Cost/Plant Total From To to be (NRs.) (NRs.) removed Samar B. Roka 6+150 6+190 25 37.04 926 Shivalal Lamsal 7+050 7+150 9 37.04 333.36 Tarakhar Subedi 11+575 11+585 7 37.04 259.28 Tej B. Roka 8+470 8+500 8 37.04 296.32 Tika B. Khadka 2+260 2+300 10 37.04 370.40 Tikaram Sharma 13+550 13+560 4 37.04 148.16 Tikaram Upaddhya 7+425 7+480 23 37.04 851.92 Til B. Roka 6+250 7+520 4 37.04 148.16 Tilak B Roka Chettri 8+700 8+760 32 37.04 1185.28 Tilak Kumar GC 8+415 8+435 4 37.04 148.16 Tirtha B. Roka 8+435 8+925 17 37.04 629.68 Top B. Malla 0+340 0+360 9 37.04 333.36 Tul B. Roka 7+240 7+260 27 37.04 1000.08 Tulasi Padhya 12+440 12+450 6 37.04 222.24 Uma Kumari Roka 8+440 8+770 51 37.04 1889.04 Total 1,256 46,522.24
12
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
Appendix II Environmental Monitoring Format
Road Name:
Monitored by: Designation:
BG / Contractor Name: Date:
SN Activity Details Remarks
1.0 Employment generation and technical skill
1.1 Number of local labour employed in contractor package
1.2 Number of women in work force with BG
1.3 Number of child workers (if any)
1.4 Number of life skill training conducted and participants number
1.5 Number of technical training conducted and participants number
2.0 Trade and commerce
2.1 Number of shops increased or decreased
2.2 Rental of houses and land spaces increased or decreased
2.3 Volume of business increased/decreased
2.4 Establishment of cottage industries in the vicinity of project area
3.0 Accessibility by
13
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
SN Activity Details Remarks
transportation facilities
3.1 Saving of time and travel cost
3.2 Number of public vehicles increased/decreased
3.3 Cost of transportation
4.0 Land value
5.0 Cross drainage structure
6.1 Landslides or other forms of slope instability
6.1 Number and location of slope failure
6.2 Disturbed area due to lack of drainage
6.3 Presence of fresh gullies and erosion
6.4 Measures for landslide and erosion control
6.5 Application of bioengineering measures
6.6 Establishment of nursery (no. and location)
7.0 Disposal of spoils and construction wastes
7.1 Cut and fill balance maintained or not
7.2 Stockpiling of construction materials done properly or not
7.3 Care and safe storage of top soil for later use
7.4 Spoil falling or being washed on to forest and farm land
14
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
SN Activity Details Remarks
7.5 Compensation provided to land owner and measures to prevent further damage
7.6 Presence of toe walls for safe disposal of excavated materials and other construction wastes
7.7 Disposal of excavated materials and other construction wastes on hill slopes.
7.8 Spoil disposal locations
8.0 Water management/water quality
8.1 Disruption of drinking or irrigation water supplies and their restoration and rehabilitation status
8.2 Drain water discharge into farm land/risky areas
8.3 Diversion of water away from natural water course
8.4 Quality of surface water observed
9.0 Community infrastructures
9.1 Suitable reinstatement measures for disruption to community infrastructures
10.0 Air quality
10.1 Dust generation from construction work
11.0 Noise pollution
11.1 Noise from large work sites
12.0 Quarrying of construction materials
15
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
SN Activity Details Remarks
12.1 Pollution, disturbance and danger from quarry operations
12.2 Rehabilitation of abandoned quarry sites
13.0 Forest and vegetation
13.1 Number of stumps of cut trees
13.2 Pressure on nearby forest for firewood/timber use
13.3 Compensatory plantation and its survival rate in forest, private land and roadside
13.4 Sale of timber/NTFP increased/decreased
14.0 Wildlife
14.1 Cases of wildlife hunting by work force
14.2 Cases of trading of wildlife products
14.3 Stratification of habitat caused by road construction
15.0 Occupational health and safety matters
15.1 Types and no. of accident occurred
15.2 Adequacy of safety gadgets (helmet, facemasks, muffles, gloves etc)
15.3 Facility of first aid and emergency services provided or not
15.4 Compensation to the loss of life or disability
16
Detail Project Report of Baglung-Kushmisera Road Subproject, Baglung Section III: Safeguard Vol.I Environment
SN Activity Details Remarks
15.5 Accidental insurance for workers
16 Camp site and storage depot management
16.1 Location, material used for camp site construction
16.2 Water supply and sanitary condition (clean drinking water and temporary pit latrine at camp site)
16.3 Location of stockpile and storage depot
17 Sites for cultural and religious values
17.1 Protection of culturally and religiously sensitive spots (temple, mane, cremation sites, mela spot etc)
18 Change in migration pattern
18.1 No. of persons migrating to other places
18.2 No. of persons stopped migrating/return from outside
19 Tendency of encroaching within RoW
20 Grievances received in last month
21 Meeting convened by safeguard desk
22 Corrective action during safeguard meeting
17