Resettlement Plan

July 2009

NEP: Energy Access and Efficiency Improvement Project

Prepared by: Electricity Connectivity and Energy Efficiency Project I

This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

i NEPAL ELECRICITY AUTHORITY Durbarmarg,

Draft Final LAND ACQUISITION AND RESETTLEMENT PLAN

Prepared For

Construction of 132 kV New T/L and Related Sub-station Works

in Dumre-Damauli-New Marsyangdi Sub-station Section;

Construction of 30 MVA, 132 kV/11 kV Sub-station at Chapali;

and

Construction of Eight New 33/11 kV, 6/8 MVA Sub-stations; and 3 New 11 kV Switching Sub-stations in Different Districts

Prepared By: Nepal Electricity Connectivity and Energy Efficiency Project I NEA/ADB SSTA 7176: NEP

Kathmandu, Nepal

July 2009

ii Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Glossary of the Terms

Bigha There are three major units (Bigha, Kattha, and Dhur) used to measure and keep official record of land in Southern plain of Nepal known as . One Bigha is equivalent to about 6869 sq.m. (Twenty Dhur makes one Kattha, and twenty Kattha makes on Bigha) Chief District Officer (CDO) There are 75 administrative districts in Nepal. Chief District Officers (CDO) are the Chief Administrative Officers of these districts. Among others, the responsibilities of the CDOs also include managing and maintaining district administration, law and order situation in the district, and implementing Land Acquisition and Resettlement Plan for the development projects to be implemented in the districts. Dalit (Minor Caste Group) Dalit is commonly known as untouchable in traditional Nepalese society. They belong to occupational and artisan group. Dalit Commission has defined dalit as, “the community discriminated on the basis of caste and marginalized in terms of social, economic, educational, political and religious sectors.”

The Dalit caste, has further been divided into different groupings in accordance with socially prescribed type of works. For example, communities traditionally engaged in tailoring, or playing musical instruments, making shoes or communities involved in washing clothes, are given different family names in accordance to the type of traditional occupation they are involved with. District Development Committee There is one District Development Committee (DDC) in each administrative districts of Nepal to be headed by elected district level political leader. Janajati (Ethnic/Indigenous People) In broad, Nepalese indigenous population consist two major groups, the Indo-Nepalese, whose ancestors migrated into the country from the south and the Tibeto-Nepalese, whose ancestors entered Nepal from the north. There exist cultural, linguistic, and religious differences both between and within the two groups. Differences within the Indo-Nepalese grouped are marked more by caste (a system of social hierarchy) than by ethnicity. The Tibeto- Nepalese group comprises several different ethnic groups including Bhutia, Sherpa, Gurung, Magar, Tamang, Rai, and

iii` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Limbu people. The Tibeto-Nepalese are concentrated in hill and mountain and the Indo- Nepalese are concentrated in the Terai plain and inner Terai.

As defined by Nepal indigenous/nationalities/tribal, Act defines; “People having their own mother tongue, distinct traditional values, and cultural identities, including social structure and written/non-written history are Indigenous and nationalities population.” Land Acquisition and Compensation The committee to be formed under the Fixation Committee chairmanship of CDO for acquiring and compensating land and properties based on Land Acquisition Act of Nepal (2034) 1977 and Electricity Rule 1993. Permanent Acquisition Land and other assets permanently acquired for the construction of sub-stations, transmission towers and other associated works related to the project in accordance with the prevailing Acts. Permanently acquired land and other assets are paid compensation on replacement cost based on current market rate. All the permanently acquired land are transferred in the name of Executing Agency. Permanent loss of Crops Long term loss of crops production in the cultivating land permanently acquired for the project. Restriction to Use of Land Land not acquired permanently but used to maintain the RoW of the transmission lines. Ownership of such land will not be transferred and the owners will be allowed to cultivate their land. However, there will be restrictions to construct structures and for plantation of trees within the specified zone of influence of the transmission lines (e.g. 9m both sides for 132 kV T/L) subject to be compensated under the prevailing law as provisioned in Land Acquisition Act 1977 and Electricity Rule 1993. Ropani Land measurement unit, practices in the hilly regions of the country. One Ropani of land is equivalent to approximately 508.74 sq. ft. There are three sub-units under the Ropani. They are; (a) Aana (342.25 sq.ft.), (b) paisa (85.56 sq.ft), and (c) Daami (29.39 sq.ft) Temporary effect on land Land temporarily affected due to use by the contractors during the construction phase. Compensation for the temporary use of land to be paid by the contractors to the land owners in accordance to the agreed terms and conditions to be signed between the two parties. Temporary loss of Crops One time loss of crops likely to occur during the

iv` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

construction period of new transmission line or second circuit stringing on the existing double circuit towers. Village Development Committee VDC is the local level administrative unit to be (VDC) represented by locally elected political leaders in rural areas with certain geographical boundary, number of households and population. Ward Ward is the lowest level administrative unit to be represented by elected local political leaders. As per the existing administrative system, each municipal local administrative area contains up-to 35 numbers of wards whereas the number of ward is only up-to 9 in the case of Village Development Committees (VDC).

v` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

ACRONYMS

ADB - Asian Development Bank AH - Affected Households AP - Affected Persons CDO - Chief District Officer CFC - Compensation Fixation Committee CRO - Chief Resettlement Officer CRO - Chief Resettlement Officer DDCs - District Development Committee GON - Government of Nepal GRC - Grievance Redress Committees Ha - Hectare Km - Kilometer LARP - Land Acquisition and Resettlement Plan MRM - Management Review Mission NEA - Nepal Electricity Authority NGO - Non Government Organization NRs - Nepalese Rupees PIU - Project Implementation Unit PM - Project Manager PM - Project Manager PO - Project Office/Officer PPTA - Project Preparation Technical Assistance RoW - Right of Way RP - Resettlement Plan S/S - Sub-station SAARC - South Asian Association for Regional Co-operation SLC - Sub-Project Level Committee T/L - Transmission Line VDC - Village Development Committee

vi` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Executive Summary

I. The Project Introduction

1. The proposed Nepal Electricity Connectivity and Energy Efficiency Project consist of six investment components and one component on provision of expert services. The Investment component supported by the ADB grant covers six main outputs each consisting of several activities. The first four major investment outputs are; (i) Transmission System Augmentation; (ii) Distribution System Enhancement; (iii) Distribution Loss Reduction; and (iv) Generation Plant Improvement. The investment components have been proposed by Nepal Electricity Authority (NEA) based on its generation and rehabilitation plan, transmission system master plan and short-term distribution augmentation plan. The other two investment outputs are (v) Energy Efficient Lighting and (vi) Solar Power based Street lighting. The final component is to provide (viii) Expert Services assisting Public Private Partnerships (PPP) in distribution.

II. Scope of Land Acquisition and Resettlement Planning

2. This Land Acquisition and Resettlement Plan (LARP) has been prepared for (a) Dumre- Damauli-New Marsyangdi Transmission Line (T/L) section under the Middle Marshyangdi - Dumauli – Marshyangdi 132 kV transmission line and related Sub-station works, (b) Construction of Chapali Sub-station, and (c) Constructing Distribution and Switching Sub- stations in different ten districts.

3. Land acquisition and resettlement planning however, may not require for; (i) Stringing of 132 kV second circuit between Middle Marsyangdi-Marsyangdi (44 km), (ii) Expansion, reinforcement and construction of new sub-stations at Damauli, Middle- Marsyangdi, and Marsyangdi (Aanbu Khairini) under the Middle Marsyangdi-Damauli-Marsyangdi New Marsyangdi 132 kV transmission line and sub-station construction components, (iii) Second circuit stringing between Butwal-Kohalpur (200 km,), (iv) Construction of distribution sub- stations and switching centers at Swyambhu, Synaja, Mahottari, (v) Expansion of Matatirtha sub-station at Kathmandu, (vi) 66 kV underground cabling from Chabahil to Lainchaur (7.5 km) and associated sub-station upgrading works, and (vi) Installation of 220 MVAR capacitor banks to reactive power compensation at eight transmission existing sub-stations. Project activities under these components will be carried out on the available Government/NEA land or existing RoW. However, taking into account to likely losses of crops and trees during second circuit stringing the LARP has provisioned compensation for the same. Similarly, land acquisition and resettlement plan also may not require for the investment component of (i) clean energy plant development, (ii) supply side energy efficiency improvement, (iii) public private partnership in distribution, and (iv) energy efficiency in lighting, and renewable energy for street-lighting as the activities are basically related to the replacement of available technical equipment/appliances and management aspects. Table 1 provides land acquisition requirement for different investment components under the project.

Table 1: Land Acquisition Requirement for the Project

S.N Project Component Permanent Restriction to Total Acquisition Use for RoW (in ha) 1, New Transmission Line and 1.90 19.35 21.25 Transmission Sub-station Construction 2. Construction of Distribution Sub-station 2.76 2.04 4.74 and Switching Centers Total Estimated Area of Affected Land 4.66 21.39 25.95 Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design.

vii` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

4. As shown in the table above, an estimated area of 26.05 ha of land is required to implement the project activities. Out of which, about 4.66 ha to be acquired permanently and another 21.39 ha of land will be restricted to use except for agriculture purpose. As the land restrict for RoW will not be acquired permanently, the cultivator will be allowed to use the land for agriculture purpose. The Land Acquisition and Resettlement Plan (LARP) prepared under the Technical Assistance (TA) ensures; (i) types and extent of losses due to the project (ii) Principles and legal framework applicable for mitigation of losses, (iii) Entitlement matrix for compensation and other assistance based on the inventory of losses, (iv) Provisions for relocation assistance and restoration of house/businesses/income, (v) Budgets, and institutional framework for the implementation of the plan, and (vi) Responsibilities for monitoring of the LARP measures.

III. Impacts

5. A total of 314 households and 1654 persons likely to be affected due to the proposed Project. The major impacts include permanent acquisition of land, restriction to use land (except to use for agriculture purpose), and acquisition of residential/commercial structures along the proposed T/L RoW (Table 2).

Table 2: Affected Households and APs

S.N. Type of Effect Affected HHs (No.) Total A P (No) 1. Effect on Land 294 1551 2. Effect on Structures 20 103 Total 314 1654 Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design.

6. Of the total (314) affected households, 22 households likely to have significant impact (2 households due to effect on residential land and 20 households due to effect on their residential/commercial structures).

7. The project may also cause loss of crops in 146.55 ha of land and private trees in the affected land.

8. The LARP has devised mechanism of addressing likely resettlement issues at local and project levels as much as possible through the Grievance Readdressal Committees (GRC) to ease the LARP implementation before going to the court.

9. All the project-affected households will be paid compensation at full replacement cost (market price) based on prevailing Acts/Rules, ADB Guidelines, and NEA practices. In addition to the compensation, the LARP has also provisioned different types of financial assistance (e.g. shifting, cost, transitional allowance, compensation for loss of business etc). In accordance to the Government’s policy, and ADB guidelines at least, one family member from each project affected vulnerable people will also be enrolled in income restoration and improvement program to be implemented as a part of resettlement plan in Dumre-Damauli 132 kV T/L construction section, as the number of vulnerable households is comparatively higher in this project section.

IV. Project Locations

10. The Project activities will cover 14 administrative districts of all-five development regions of the country (Table 3). As per the technical design, construction and

viii` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP expansion/strengthening of transmission sub-stations (Chapali, Matatirtha, and Lainchaur including underground cabling) and two switching centers (Mulpani and Swyambhu) will be implemented at Kathmandu. The New 132 kV T/L will be implemented in Tanahu and Gorkha districts, and nine distribution sub-stations will be constructed in different districts across the country.

Table 3: Locations of Investment Components

S.N. Development Region Districts Investment Component Type T/Line and Distribution S/S S/S and S/ Centers 1. Eastern Development Region Jhapa & Siraha  2. Central Development Region Kathmandu,   3. Western Development Region Gorkha, Lamjung,   Tanahu, Synaja, Kaski, Parbat 4. Mid-western Development Region Banke & Bardiya   5. Far-western Development Region Kailali and   Kanchanpur Source: NEA, Technical Design and Census Survey Feb. 09 –Apr. 2009

V. Resettlement Principles, Policy, and Legal Frameworks

11. Land acquisition principles adopted for this project recognize the Land Acquisition Act 1977, Electricity Act 1992, Electricity Rule 1993, and ADB Policy on Involuntary Resettlement 1995. Besides, other relevant Acts, Government policies and applicable NEA practices and experiences will also to be considered, while implementing this Land Acquisition and Resettlement Plan. The resettlement principles adopted in this Project will provide compensation and resettlement assistance to all affected persons and businesses, irrespective of titles and extent of impact, in accordance with ADB’s Policy on Involuntary Resettlement and Government’s Act. Based on the above policy features, the principles of R&R for this Project will entail the following:

Negative impact on persons affected by the Project would be avoided or minimized as much as possible;

Where the negative impacts are unavoidable, the Project-affected persons will be assisted in improving or regaining their standard of living. Vulnerable groups will be identified and assisted to improve their standard of living;

Land replacement1/or cash compensation at replacement costs based on current market rate to the households affected by the loss of land. ;

Cash compensation will be paid for residential/commercial/residential-cum-commercial and other structures affected by the Project at current market price;

Assistance should be provided to the owners of structures and non-titleholders, who may incur loss of ability to maintain livelihood during relocation and resettlement;

1 There is also provision of land for land compensation to the APs having complete loss of their land only if government land is available in the area (Land Acquisition Act 1977, Clause 14)

ix` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Rehabilitation assistance i.e.; compensation for lost business and workdays (including employees) due to relocation and disruption of business enterprise.

Before taking possession of the acquired lands and properties, compensation and Resettlement & Rehabilitation (R&R) assistance will be provided in accordance with this policy.

Appropriate grievance redress mechanism will be established at the district, and local level to ensure speedy resolution of disputes.

All activities related to resettlement planning, implementation, and monitoring would ensure involvement of women, vulnerable groups and APs.

VI. Consultation and Stakeholder Participation

12. Stakeholders at different level were consulted during Resettlement Plan preparation process. The consulted stakeholders also include representatives of relevant line agencies (e.g. NEA officials, CDO, Land Measurement Office, District Forest Office, and Local NGOs etc), local people and project-affected families including the vulnerable groups, forest users groups, local level social workers, representatives of political parties, businesspersons, and other resource persons. The stakeholder consultations was found effective on disseminating information about the project, conducting socio-economic and census survey, and soliciting other relevant information/data to prepare the resettlement plan.

VII. Institutional Framework

13. NEA will be the Executing Agency (EA) of the project. Managing Director will be the Chief In-charge for the implementation of all components under the project. Under the Managing Director, a project implementation team will be formed for the Transmission and Distributions Departments. NEA will assign Project Managers (PM) for the components under Directors of both Transmission and Distribution Departments. The PM will act as Project Implementation Unit (PMU) and report to the respective Directors (Transmission and System Operation Department and Distribution and Consumer Service Department) of Executing Agency. Technical, administrative and account sections will support in the overall project and LARP implementation activities to be carried out by the Project Office (PO).

14. Four Project Managers (PM) will be assigned under the Transmission and System Operation Department to implement the project activities under: (i) Butwal - Kohalpur Second Circuit Stringing; (ii) Middle-Marsyangdi–Damauli–Marsyangdi; (iii) Chapali-substation Construction and Chapahil-Lainchaur Underground Cabling and Sub-station Enhancement; and (iv) Expansion of Matatirtha Sub-station. Similarly, two Project Managers (one for eastern and one for central and western districts) will be assigned to implement the distribution components in 10 different districts including Kathmandu. The PM to be assigned for Eastern districts will be stationed at Dhanusha will implement the project in Eastern districts (Jhapa, Siraha, Dhanusha, Mahottari and Sarlahi). The PM to be assigned for Central and Western districts will be stationed at and implement project activities in Western (Kathmandu, Kaski, Syanja, Parbat, and Bardiya) districts. These PMs will also be supported by technical, administration and account sections.

15. The PM will regularly update the EA on the progress of LARP implementation activities. The PM will coordinates with the Chief District Officers (CDOs) and formally request for the formation of Land Acquisition and Compensation Fixation Committee (LACFC) for the project. All land acquisition and resettlement related documents prepared for

x` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP the project will be handed over to the CDO. The PM to assist CDO on the valuation, verification and finalization affected assets. The PM also to involve local NGO wherever applicable, to implement the LARP. The PM will coordinate with CDO to establish Grievance Redressal Committee in accordance to Clause 11 of Land Acquisition Act 2034 (1977). The PM will update and report the EA on the progress of LARP implementation.

VIII. Monitoring and Evaluation

16. The implementation of Land Acquisition and Resettlement activities will be monitored internally and externally. Generally, internal monitoring will be conducted by Project Office and external agencies or independent consultants undertake the task of external monitoring. An external monitoring agency or consultant will be engaged by NEA to carry out independent monitoring on bi-annual basis that also include post Project evaluation. External monitoring will be carried out through outside researcher or consulting agency or NGOs, or through independent consultants.

IX. Budget

17. An estimated budget amounting NRs. 425,795,500.7 (US$ 5,322,444)have been calculated to implement the proposed Land Acquisition and Resettlement Plan.

xi` Table of Contents

Glossary of Terms List of Acronyms Executive Summary

I. THE BACKGROUND ...... 1 1.1 Introduction ...... 1 1.2 Scope of Land Acquisition and Resettlement Plan ...... 3 1.3 Projects Benefit and Impact ...... 4 1.3.1 The Benefits ...... 4 1.3.2 The Impacts ...... 4 1.4 Measures to Minimize the Impact ...... 5 1.5 Objective of the Land Acquisition and Resettlement Plan ...... 5

II. THE PROJECT LOCATION ...... 6 2.1 Locations of Transmission Line /Sub-station Components ...... 6 2.1.1 Middle Marsyangdi – Damauli-Marsyangdi ...... 6 2.1.2 Chapali Sub-station ...... 6 2.2 Locations of Distribution Components ...... 7

III. SOCIOECONOMIC SURVEY AND CENSUS ...... 9 3.1 Socio-economic Information ...... 9 3.2 Affected Families and Assets ...... 10 3.3 Effect on Land ...... 11 3.3.1 Ownership Type of the Affected Land ...... 11 3.3.2 Extent of Effect on Land ...... 12 3.4 Effect on Structures ...... 13 3.4.1 Ownership of the Affected Structures ...... 13 3.5 Loss of Agricultural Crops and Trees ...... 14 3.5.1 Loss of Crops ...... 14 3.5.2 Loss of Provate Trees ...... 15 3.6 Impact on Indigenous/Ethnic and Minor Caste Households ...... 15 3.7 Impact on Other Socially Vulnerable Groups ...... 16 3.8 Loss of Common Property Resources ...... 17

IV. RESETTLEMENT PRINCIPLES, POLICY, AND LEGAL FRAMEWORKS ...... 19 4.1 ADB Resettlement Policy ...... 19 4.2 Policy and Legal Frameworks ...... 20 4.3 Difference between ADB Policy and GON Resettlement Framework ...... 21 4.4 NEA Practices on Land Acquisition and Resettlement ...... 22 4.5 Resettlement Principles & Assistance of the Proposed Project ...... 22 4.6 The Entitlements ...... 23 4.6.1 Compensation for Land ...... 23 4.6.2 Compensation for Loss of Crops and Trees ...... 24 4.6.3 Compensation for Structures (residential/ residential-cum-commercial) ...... 24 4.6.4 Compensation for the Loss of Community Forest ...... 24 4.6.5 Financial Assistance to Tenants ...... 24 4.6.6 Shifting/Transportation Allowance ...... 25 4.6.7 Land Replacement Cost ...... 25 4.6.8 Compensation for Loss of Business and Shifting Allowance ...... 25

xii Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

4.6.9 Transitional Allowance to the Affected Structures Owners ...... 25 4.6.10 Income Restoration and Improvement ...... 25

V. CONSULTATION AND STAKEHOLDER PARTICIPATION ...... 34 5.1 The Approach ...... 34 5.2 Disclosure of RP ...... 34 5.3 Further Consultation & Community Participation ...... 34

VI. INSTITUTIONAL FRAMEWORK ...... 35 6.1 The Setup ...... 35 6.1.1 Transmission and System Operation Department ...... 35 6.1.2 Distribution and System Operation Department ...... 35 6.2 Roles and Responsibilities ...... 35 6.2.1 The Executing Agency (EA) ...... 35 6.2.2 The Project Office ...... 39 6.2.3 Grievance Redress Committee (GRC) ...... 36 6.2.4 Non-Government Organizations (NGOs) ...... 37 6.3 Role and Responsibilities ...... 38 6.4 Implementation Schedule ...... 40 6.5 Staff Training on Resettlement Implementation ...... 40 6.6 Resettlement Data Bank ...... 40

VII. COMPENSATION ACQUISITION AND RESETTLEMENT BUDGET ...... 42 7.1 Valuation of Affected Assests and Fixation of Compensation Rate ...... 37 7.2 Valuation Basis of Affected Assets and Associated Costs ...... 42 7.2.1 Valuation of Land ...... 42 7.2.2 Valuation of Structures ...... 42 7.2.3 Valuation of for the Loss of Crops ...... 43 7.2.4 Valuation of Affected Private Trees ...... 43 7.2.5 Valuation of Shifting/Transportation Allowances ...... 43 7.2.6 Valuation of Land Required for Replacement ...... 43 7.2.7 Valuation of Affected Business and Shifting Cost...... 43 7.2.8 Estimation for Income Restoration and Improvement Activities ...... 43 7.3 Cost Estimated for Compensation and Other Financial Assistance ...... 43

VIII. MONITORING AND EVALUATION ...... 48 8.1 Need for Monitoring ...... 48 8.2 Internal Monitoring ...... 48 8.3 External Monitoring ...... 49 8.4 Reporting Requirements ...... 50

List of Tables:

Table 1-1: Land Acquisition Requirement for the Project ...... 4 Table 1-2: Affected Households and APs ...... 5 Table 2-1: Locations of Investment Components ...... 6 Table 3-1: No of Project Affected Households Interviewed ...... 9 Table 3-2: Summary of Project Impact ...... 10 Table 3-3: Households Likely to have Significant Impact ...... 110 Table 3-4: Effect on Land by Purpose of Acquisition ...... 11 Table 3-5: Land Ownership Status ...... 11 Table 3-6: Extent of Impact on Land ...... 12

xiii` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Table 3-7: HHs Likely to have Significant Effect on Residential Land…………………..13 Table 3-8: Types of Affected Structures ...... 13 Table 3-9: Ownership Status of the Affected Structures ...... 14 Table 3-10: Estimated Loss of Crops ...... 14 Table 3-11: Loss of Private Trees ...... 15 Table 3-12: Indigenous/Ethnic and Minor Caste HHs Likely to be Affected ...... 15 Table 3-13: Impact on Other Vulnerable and Socially Disadvantaged Households ...... 16 Table 3-14: Community Forest Likely to be Affected in Dumre – Damauli Section ...... 17 Table 4-1: Difference between ADB and GON Policy on Resettlement Framework ..... 22 Table 4-3: Vulnerable HHs Requiring Income Restoration & Improvement Activities ... 26 Table 4-2: Entitlement Matrix ...... 28 Table 6-1: Schedule of Implementing Land Acquisition and Resettlement Plan ...... 40 Table 7-1: Compensation for Land ...... 44 Table 7-2: Compensation for Structures ...... 44 Table 7-3: Compensation for Loss of Crops ...... 44 Table 7-4: Compensation for Loss of Private Trees ...... 44 Table 7-5: Compensation for Loss of Business ...... 45 Table 7-6: Transitional Allowance to APs having Loss of Structures ...... 45 Table 7-7: Shifting Allowances for the Affected Residential/Commercial Structures .... 45 Table 7-8: Land Replacement Cost ...... 45 Table 7-9: Income Restoration and Improvement ...... 45 Table 7-10: NGO Mobilization Cost ...... 46 Table 7-11: External Monitoring and Evaluation ...... 46 Table 7-12: Summary of Resettlement Budget and Cost Estimate ...... 47

APPENDICES :

APPENDIX A-1 : Information on land acquisition requirement by investment components APPENDIX A-2 : Details on land acquisition impact by locations. APPENDIX B-1 : Key socio-economic characteristics of the project districts APPENDIX B-2 : A brief descriptions of the locations of each investment component APPENDIX B-3 : Proposed locations for the distribution sub-stations and switching centers APPENDIX C-1 : Key socio-economic characteristics of the affected households. APPENDIX C-2 : Breakdown of the impacts by locations. APPENDIX C-3 : List of landowners APPENDIX C-4 : Description of the affected structures by construction types and other details APPENDIX C-5 : Details on permanent and temporary loss of crops APPENDIX C-6 : List of Indigenous/Ethnic and Minor Caste HHs likely to have significant impact APPENDIX D-1 : A synopsis of NEA’s practices on implementing resettlement plan APPENDIX E-1 : consultation matrix APPENDIX F-1 : The Terms of Reference (ToR) of NGO APPENDIX G-1 : The current market rate of the affected land at Dumre-Damauli APPENDIX H-1 : Details on Land Compensation Cost APPENDIX I -1 : Terms of Reference for External Monitoring Agency

xiv` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

I. THE BACKGROUND

1.1 Introduction

1. Government of Nepal aims to expand electricity to rural areas by providing quality services at a low cost, to adopt hydro-electricity as the foundation of overall economic development, and develop it as an exportable item.2 The proposed Nepal Electricity Connectivity and Energy Efficiency Project consist of six investment components and one component on provision of expert services. The investment component supported by the ADB grant covers six main outputs each consisting of several activities. The first four major investment outputs are; (i) Transmission System Augmentation; (ii) Distribution System Enhancement; (iii) Distribution Loss Reduction; and (iv) Generation Plant Improvement. NEA proposed investment components based on its generation and rehabilitation plan, transmission system master plan and short-term distribution augmentation plan. The other two investment outputs are (v) Energy Efficient Lighting and (vi) Solar Power based Street lighting. The final component is to provide (vii) Expert Services assisting Public Private Partnerships (PPP) in distribution

(i) Facilitation of Access to Clean Energy (Component 1): The following activities have been included under this components:

a. Middle Marshyangdi - Dumauli – Marshyangdi 132 kV transmission line and related substation works: This component is to improve the security of power evacuation from the newly constructed 70 MW Middle Marshyangdi hydropower station, and will provide general reinforcement through the important Damauli sub-station. Work will include construction of 19 km new double circuit 132 kV transmission line in Dumre-Damauli-New marsyangdi section, second circuit stringing on an existing 44 km 132 kV transmission line from Middle Marsynagdi to Marsyangdi, construction of a new 15 MVA, 132 kV/33 kV sub-station at Marshyandi, reinforcement of Damauli sub-station with construction of two 132 kV line bays, and extension of 132 kV line bays at Middle Marshyandi and Marshyandi switchyards.

b. Butwal-Kohalpur 132 kV second circuit transmission line: This 200 km line is used to transfer power imported from India to Mahendranagr to the west and centre of the country. The project involves stringing of the second circuit of an existing 132 kV line built on double circuit towers, increasing the power import capacity by up to 100MW.

c. Construction of Chapali Substation: This sub-project includes construction of a new 30 MVA, 132 kV/11 kV sub-station, installation of 15 km of underground 11 kV distribution line for 6 feeders at Chapali, and extension of two 66 kV GIS line bays at Lainchaur sub-station and installation of 7.5 km, 66 kV underground cable form Lainchaur to Chabahil.

d. Expansion of Matatirtha Substation: The western part of Kathmandu Valley is relatively well served with 132 kV transformer capacity. However, the area experiences poor power supply due to the loading imposed on and length of

2 Three – Year Interim Plan, Approach Paper (2064/65-2066/67), National Planning Commission, July 2007

1` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

11 kV feeders, resulting in frequent feeder tripping and high losses. The project will reduce average 11 kV feeder length by converting the Matatirtha 132 kV switching station into a full 132 kV sub-station. It involves constructing additional 132 kV bays, installing two transformers, and constructing 33 kV and 11 kV lines to connect to existing circuits.

e. Installation of Capacitor Banks: This project involves installation of approximately 220 MVAR of capacitor banks for reactive power compensation at eight transmission sub-stations.

(ii) Energy Access Quality Enhancement (Component 2): In order to improve distribution system reliability, quality of supply, and reduction of technical losses, NEA has proposed to construct eight new 33/11 kV, 6/8 MVA sub-stations at (i) Kusma, (ii) Burahathwa, (iii) Mainapokhar, (iv) Dhanusha/Dharampani, (v) Paraul; (vi) Baniyani; (vii) Mirchaiya; (viii) Dhikurpokhari/Banskot, and three new 11 kV switching substations at (i) Swoyambhu, (ii) Mulpani, and (iii) Mirmi, taking into account the technical urgency and optimization of revenue generation. This will reduce the incidence of scheduled and unscheduled supply interruptions, reduce losses, and improve supply quality.

(iii) Clean Energy Plant Improvement (Component 3): Under this component Marsyangdi (69 MW) Gandak (15 MW) hydropower plants will be partially rehabilitated. This work will increase availability at both power stations and will reduce self-consumption at Lower Marshyangdi, providing an estimated additional 4 GWh of energy per year. This component is composed of (a) replacement of weir control system and modernization of excitation system at Marshyangdi; and (b) installation of trash rack cleaning system at Gandak for the improvement of plant availability. NEA is contemplating engagement of individual consultants to support it during the bidding process.

(iv) Supply-side Energy Efficiency Improvement (Component 4): This component is proposed to address high technical and non-technical losses in medium voltage and low voltage distribution networks in Kathmandu Valley. A series of pilot project have been prepared by NEA; 16 11 kV feeders and downstream low voltage networks with unacceptably high losses have been identified and are to be rebuilt from the 11 kV feeder circuit breaker down to the customer service connection and revenue meter. These pilot projects will become “model networks” that can be replicated across Nepal. They will incorporate best international practice with respect to design, construction and commercial operation. To ensure that best practice is adopted, Individual consultants will be engaged to provide technical advice and support NEA for detailed design and implementation.

(v) Public Private Partnership in Distribution (Component 5): NEA is committed for introducing a franchising modality for the management and operation of selected distribution areas. NEA will identify three cities in which it will form strategic partnerships with private sector entities for management and operation of the urban electricity supply systems. ADB is presently supporting development of a franchising model, bidding guidelines, and related legal and bidding documentation. Loan proceeds will be used for expert services required to support the bidding process.

(vi) Energy Efficiency in Lighting (Component 6): Presently NEA has a pilot CFL program targeting about 250,000 domestic consumers within 21 identified areas. This

2` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

investment component involves scaling-up of this program to nationwide program with an estimated 1 million high quality CFLs of capacities 9W, 12W and 20W. The Project will target phase-wise domestic consumers in all electrified areas with emphasis on high impact areas. It is expected that this program will free up a minimum of 10MW of power plant and a potential reduction of 23 GWh of consumption. Also, assistance will be provided for a public awareness campaign and for an implementation consultant (local) and other resources required for the Demand-side Management (DSM) cell to be established by NEA.

(vii) Renewable Energy for Street-Lighting (Component 7): This component will facilitate the promotion of solar-powered street lighting in urban areas of Nepal and will fund a pilot project involving Bhaktapur, Kathmandu and Lalitpur areas. The identified areas are durbar squares in all three municipalities, areas around Pashupati Nath temple, Swyambhu and Boudha Nath Stupas, Thamel and New Road/Indra Chowk. The Project includes purchase of solar-powered street lighting systems, replacement/installation and setting up a system to ensure proper maintenance system. It is estimated that around 1,200 street lights will be replaced with solar which will reduce peak load demand of about 0.2 MW and save about 700 MWh per year.

1.2 Scope of Land Acquisition and Resettlement Plan

2. Resettlement-planning document is required to both Government and ADB in the development projects having scope of affecting and acquiring individuals/ community assets. In line with the policy guidelines of the Asian Development Bank (ADB), and Government’s Land Acquisition Act (LAA) 1977, this Land Acquisition and Resettlement Plan (LARP) has been prepared for the project activities under the investment components of (a) Dumre- Damauli-New Marsyangdi Transmission Line (T/L) section under the Middle Marshyangdi - Dumauli – Marshyangdi 132 kV transmission line and related Sub-station works, (b) Construction of Chapali Sub-station, and (c) Constructing Distribution and Switching Sub- stations in different nine districts (Fig 1).

Figure 1: Scope of Land Acquisition Resettlement Planning

Dumre-Damauli- Construction of 30 Distribution and Marsyangdi 132 kV MVA Chapali Sub- Switching Sub- T/L station station Construction Construction

3. Land acquisition and resettlement planning however, may not require for (i) Stringing 132 kV second circuit between Middle Marsyangdi-Marsyangdi (44 km), (ii) Expansion, reinforcement and construction of new sub-stations at Damauli, Middle, Marsyangdi, and Marsyangdi (Aanbu Khairini),(iii) 132 kV second circuit stringing between Butwal-Kohalpur (aprox 200 km,), and (iv) Construction of distribution sub-stations and switching centers at Swyambhu, Synaja, Mahottari, (v) Expansion of Matatirtha sub-station at Kathmandu, and (vi) Installation of 220 MVAR of capacitor banks for reactive power compensation at eight existing transmission sub-stations.

3` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

4. These project activities will be carried out on the available Government/NEA land or existing RoW. However, taking into account to likely losses of crops and trees the LARP has also provisioned compensation for the same. Similarly, land acquisition and resettlement plan also may not require for the investment component of (i) clean energy plant development, (ii) supply side energy efficiency improvement, (iii) public private partnership in distribution, and (iv) energy efficiency in lighting, and renewable energy for street-lighting as the activities are basically related to the replacement of available technical equipment/appliances and management aspects. Table 1-1 provides land acquisition requirement to implement the project activities. Detailed information on land acquisition and restriction requirement by investment components is included in Appendix A-1.

Table 1-1: Land Acquisition and Restriction Requirement for the Project

S.N Project Components Permanent Restriction to Use Total Acquisition for RoW (in (in ha) (in ha) ha.) 1, New Transmission Line and Transmission Sub- 1.90 19.35 21.25 station Construction 2. Construction of Distribution Sub-station and 2.76 2.04 4.80 Switching Centers Total Estimated Area of Affected Land 4.66 21.39 26.05 Source: NEA, Technical Design and Census Survey Feb-Apr, 09 and census, Feb-Mar, 2009

Note A: One Bigha = 6918.86 sq.m., 1 ropani=508.74 sq.m, 1 ha = 9920.43 sq.m. Note B: The data presented in the table is based on preliminary census data which need to be updated during detail Design

5. As shown in the table above an estimated area of 26.05 ha of land is required to implement the project activities. Out of which, about 4.66 ha to be acquired permanently and another 21.39 ha of land will be restricted to use except for agriculture purpose. The land restrict for RoW will not be acquired permanently, and the cultivator will be allowed to use the land within the RoW only for agriculture purpose. The LAND Acquisition and Resettlement Plan is to ensure; (i) Types and extent of losses due to the project (ii) Principles and legal framework applicable for mitigation of losses, (iii) Entitlement matrix for compensation and other assistance based on the inventory of losses, (iv) Provisions for relocation assistance and restoration of house/businesses/income, (v) Budgets, and institutional framework for the implementation of the plan, and (vi) Responsibilities for monitoring of the LARP measures.

1.3 Projects Benefit and Impact

1.3.1 The Benefits

6. Opportunity for hydropower development, reduction of outage in the distribution network, and total network loss, supply of efficient and reliable energy are some of the key expected benefits of the Project. Implementation of the Project may also bring several positive impacts in the socio-economic scenario of the Project districts thereby contributing towards poverty reduction through enhancing economic activities in the area through creation of employment opportunities in the production sectors due to reliable and efficient electricity supply, and even employment opportunity during construction period.

1.3.2 The Impacts

7. A total of 314 households and 1654 persons likely to be affected by the proposed Project. The major impacts include permanent acquisition of land, restriction to use land (except to use for agriculture purpose), and acquisition of residential/commercial structures

4` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP along the proposed T/L RoW (Table 1-2). Appendix A-2 provides details on land acquisition and resettlement impact by investment component and locations.

Table 1-2: Affected Households and APs

S.N. Type of Effect Affected HHs (No.) Total Affected Persons (No) 1. Effect on Land 294 1551 2. Effect on Structures 20 103 Total 314 1654 Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design.

1.4 Measures to Minimize Impact

8. Appropriate measures have been taken by the project design in order to minimize acquisition and resettlement impact by using the available Government/NEA lands, wherever feasible and even by changing alignment route of the 132 kV new transmission lines. NEA has changed its design drawing of 132 kV new Middle Marsyangdi-Dumre-Damauli section from Angle Point 0 – 7 in order to avoid the settlement area and valuable land. 3 Likewise, Government/NEA land have also been identified and proposed for the implementation of some distribution sub-stations and switching centers in different districts (e.g. construction of switching stations at Mirmi- Syanja, Swyambu-kathmandu, and distribution sub-stations at Mahottari, Dhanusha, Mainapokhar, and transmission sub-station at Marsyangdi). NEA further aims to minimize the alignment route of the transmission line in critical sections based on community demand4 as far as technically feasible and carrying out the construction- erection of towers and stringing transmission lines during off seasons.

1.5 Objective of the Land Acquisition and Resettlement Plan

9. The Resettlement Plan (RP) also mentioned in this document as Land Acquisition and Resettlement Plan (LARP), is guided by ADB Policy on Involuntary Resettlement, Land Acquisition Act of Nepal 1977, and other relevant Acts, Rules (e.g. Electricity Act 1992, Electricity Rule 1993) and Government policies, and guidelines related T/L construction. The main objective of LARP is to identify impact and to plan measures for mitigating various losses likely to occur due to the Project. It further aims to provide guidelines to address the identified acquisition and resettlement impact and to ensure compensation and other assistances to the affected households and people under the prevailing legal norms of GON in keeping with the ADB guidelines. The LARP is based on the general findings of field reconnaissance, socio-economic, and census survey of the Project affected household and their affected assets. The plan to be up-dated and finalized during the detailed design based on changes in technical design and verification of affected persons and their assets.

3 Transmission and System Operation, Transmission Line/Sub-station Construction Department, Project Development Department (i) Final Report on Detailed Feasibility of Dumre-Damauli 132 kV Transmission line February 2006, and (ii) Dumre- Damauli 132 kV Transmission Line (Alternative Route Alignment No.III)

4 In Dumre-Damauli Section, some of the community forest users groups, and local community have requested NEA to consult with them while fixing the alignment route during detail design and construction phase in order to further minimize the impact.

5` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

II. THE PROJECT LOCATION

10. The proposed Project activities will cover 14 administrative districts of all-five development regions of the country (Table 2-1). Key socio-economic characteristics of the project districts are included in Appendix B-1.

11. Construction and expansion/strengthening of transmission sub-stations (Chapali, Matatirtha, and Lainchaur including underground cabling) and two switching centers (Mulpani and Swyambhu) will be implemented at Kathmandu. The New 132 kV T/L will be implemented in Tanahu and Gorkha districts, and nine distribution sub-stations will be constructed in different districts across the country. A brief descriptions on the locations of each investment component is given in Appendix B-2.

Table 2- 1: Locations of Investment Components

S.N. Development Region Districts Investment Component Type T/Line and Distribution S/S S/S and Switching Construction Centers 1. Eastern Development Region Jhapa & Siraha  2. Central Development Region Kathmandu,   3. Western Development Region Gorkha, Lamjung,   Tanahu, Synaja, Kaski, Parbat 4. Mid-western Development Region Banke & Bardiya   5. Far-western Development Region Kailali and Kanchanpur   Source: NEA, Technical Design and Census Survey Feb. 09 –Apr. 2009

2.1 Locations of Transmission Line /Sub-station Components

2.1.1 Middle Marsyangdi – Damauli-Marsyangdi

12. New 132 kV T/L will be constructed in Dumre-Damauli (18 km) section and for New Marsyangdi Sub-station (1 km) under Middle Marsyangdi-Damauli-Marsyangdi T/L and sub- station construction component. The proposed Dumre-Damauli T/L starts at Angle Point (AP) 0, located inside the compound of Damauli sub-station and passes through ward No. 1,3.5,6, and 11 of , ward No. 1 and 9 of VDC, Ward No. 1,2,3,4,6,7, and 8 of VDC (Tanahu District), and get connected with the tapping point (known as AP 39 of MMHEP T/L tower) located at Ward No. 8 of Chynagli VDC in . As per the technical design, most of the alignment route of Dumre-Damauli new T/L covers Tanahu district except from AP 21 to the tapping point (known as AP 39) located in Chyangli VDC of Gorkha. The proposed T/L mostly passes through the community forest and cultivating land. Similarly, the new T/L for proposed New Marsyangdi sub-station (approx 1 km) starts from the proposed sub-station location at Markichowck, Ward No. 3 of Aanbu Khairini VDC (Tanahu district) and crosses the agricultural land towards south and get connected at existing Marsyangdi Tower near Raudi Khola.

2.1.2 Chapali Sub-station

13. Chapali sub-station site is located at Chapali Bhadrakali VDC; ward No. 8, Bhangal, approximately 10 km north from the center of Kathmandu. As per the National Census 2001,

6` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP there are 903 households in the VDC with the total population of 4544 (comprising 2278 male and 2268 female). Over the last few years, urbanization within this vicinity has been increasing rapidly. Many new residential buildings have come up in this area and this area is of potential importance from distribution expansion viewpoint. The likely impacts associated with this sub-station construction appears to be less as the proposed sub-station area is already occupied with 132 kV and 66 kV transmission line Right of Way (ROW). About 35 ropani (approx 1.79 ha) of land will be required for the proposed sub-station and about 500 meters of existing access road from main road to the substation site shall be improved.

14. Another three project activities under the transmission components (expansion of existing Matatirtha S/S and Improvement of existing Chabahil sub-station and 33 kV underground cabling) will be implemented in Kathmandu.

2.2 Locations of Distribution Components

15. Project activities under the distribution component covers 10 administrative districts of the country. Out of them, two distribution switching center (Swyambhu and Mulpani) will be implemented in Kathmandu and rest of the project activities will be implemented in different nine districts. For this component, NEA had identified locations prior to the mobilization of the TA team. However, some of the locations were confirmed during the project preparation phase. While doing so, it was also approached to identify alternative locations for some of the sub-stations. NEA will construct distribution sub-stations in one of the proposed locations of each project district. Information on the proposed locations for the distribution sub-stations and switching centers is given in Appendix B-3.

7` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

8` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

III. SOCIOECONOMIC SURVEY AND CENSUS

3.1 Socio-economic Information

16. ADB guidelines require a complete socio-economic survey and census of project affected families early in the Project preparation phase to identify all losses from acquisition due to the project. Accordingly, approach was made to collect socio-economic information from the affected households and census of their affected assets and to solicit other relevant information/records from different sources (APs, Land Measurement Office and community) in between February - May 2009). Of the total households likely to have Project impact, about 77 % households form Dumre-Damauli T/L section were contacted and interviewed to collect socio-economic information and information on their affected assets. Interview from the households likely to have project impact in Chapali sub-station and distribution sub- stations/switching centers (from different 10 districts), could not be carried out as the affected households from these locations were found absentee and residing in other locations (Table 3-1). However, information on affected land, number of affected households and APs for these project locations were collected through the records of Land Measurement Office and the local community. A set of cadastral map containing information on the affected land parcels in Dumre-Damauli T/L and Chapali sub-station project is included in separate volume as Supplementary Appendix in the report submitted to NEA.

Table 3-1: No. of Project Affected HHs Interviewed s

S. Sub-projects Effect on Land Effect on Total Affected and Structures Interviewed HHs

N.

d s

HHs HHs HHs HHs HHs HHs HHs HHs % of Total Affected Affected Affected Absentee Absentee Interviewed Interviewe Interviewed interviewed Transmission Sub-projects 1 Middle Marsyangdi-Damauli- 207 133 74 18 15 3 225 175 77.77 Marsyangdi 132 kV T/L construction 2 Chapali Sub-station [a] 74 - 74 2 2 - 76 2 5.26 Sub-toil of Transmission Projects 281 133 74 20 17 3 301 177 62.98 Distribution Sub-projects [b] 3 Distribution S/S, Jhapa 1 - 1 - - - 1 - - 4 Distribution S/S, Siraha 1 - 1 - - - 1 - - 5 Distribution S/S Dhanusha (RoW) 2 - 2 - - - 2 - - 6 Distribution S/S Sarlahi 1 - 1 - - - 1 - - 7 Switching S/S, Mulpani 2 - 2 - - - 2 - - 8 Distribution S/S Kaski 10 - 3 - - - 3 - - 9 Distribution S/S Parbat 2 - 2 - - - 2 - - 10 Distribution S/S Bardiya (RoW) 1 - 1 - - 1 - - Sub-total of Distribution 20 - 13 - - - 13 - - All Total 301 133 87 20 17 3 314 177 55.14 [a] Interview of rest of the Affected Households was not possible as they were found residing in other locations [b] Interview of the Affected HHs was not possible as the S/S locations were selected by NEA after the field visit in April 09

17. Corridor of 18 meters (nine meters both sides for 132 kV T/L was taken as a standard benchmark to collect socio-economic information from the affected households. For the transmission and distribution sub-station components, information was collected through technical design prepared by NEA, cadastral maps and land records and affected

9` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP communities in the project locations. Key socio-economic characteristics of the affected households is incorporated in Appendix C-1.

3.2 Affected Families and Assets

18. A total of 314 households likely to be affected due to the project. Among them 301 households will have effect on their land and another 20 households will have effect on their residential/commercial structures (Table 3-2). Appendix C-2 provides breakdown of the impacts by locations.

Table 3-2: Summary of Project’s Impact

S.N Investment Effect on Land Effect on Residential Total Components /Commercial /Structure Affected No. of Affected No. of Affected No. of HHs (No) APs HHs (No) APs HHs (No) APs 1 Transmission Line /Sub- 281 1441 20 103 301 1544 station Components 2 Construction of New 13 110 - - 13 110 Distribution/Switching Sub-stations Total 294 1551 20 103 314 1654 Source: Census Feb-APR, 2009 Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design.

19. Compared to the total number of affected households (314) the number of significantly affected households is quite low. Based on the census data, there are only 22 (7%) households likely to have significant impact due to the project. Among them, 2 households will have significant impact on their residential land, and another 20 households likely to have affect on their residential/commercial structures. Table 3-3 provides the number of households likely to have significant impact due to the proposed project.

Table 3-3: Households Likely to have Significant Impact

S.N Descriptions Affected HHs (No) 1 Households having significant impact on land 2 2 Households having significant impact on 20 residential/commercial structures Total 22 Source: Census Feb-APR, 2009 Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design.

10` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

3.3 Effect on Land

20. An estimated area of 26.05 ha of land will have effect due to construction of sub-stations, towers, and due to restriction of land except to use for agriculture to maintain RoW for new 132 kV transmission lines. Of the total affected land, a significant proportion (about 82%) of land will have effect only due restriction of land except to use for agriculture for RoW. As per the NEA practice in other T/L Projects, the restricted land except to use for agriculture to maintain RoW will not be acquired permanently. Ownership of such land remains to the usual owners. The owners/tenants will be allowed to cultivate the land and just be restricted to use for constructing structures and plantation of trees. For such effect, NEA will provide compensation to the APs based on the total market value of the affected land subject to be fixed by the Compensation Fixation Committee (CFC). As being practiced, in most of the transmission line projects NEA is providing 10% compensation to such land out of the total market value subject to be fixed by CFC. However, the Project will have to acquire an estimated area of only 4.66 ha of land permanently. Table 3-4 provides estimated area of land likely to be acquired (permanently and restricted for RoW).

Table 3-4: Effect on Land by Purpose of Acquisition

S.N Purposed of Acquisition Approx Area Approx Area % (in sq.m.) (in ha) 1. Permanent Acquisition 46389.17 4.66 18.60 2. Restriction to Use of land except for Agriculture to 213500.00 21.39 82.11 maintain the RoW of newly constructed 132 kV T/L Total 259889.17 26.05 100 Source: NEA Technical Design and Census Feb-APR, 2009

3.3.1 Ownership Type of the Affected Land

21. Of the total identified households having effect on their land, 102 were titleholders of Dumre-Damauli-New Marsyangdi section, 13 were absentee titleholders of the proposed land for Distribution sub-stations across the country, and another 74 were absentee titleholders of Chapali sub-station location. Table 3-5 provides breakdown of the ownership of the affected land from different sub-project. List of landowners is given in Appendix C-3.

Table 3-5: Land Ownership Status

S.N. Type of Ownership Ownership of Land (No.) % Middle Marsyangdi-Dumre –Damauli Section 1. Titleholders having ownership certificate 102 44.93 2. Titleholders without having updated ownership certificate 55 24.23 3. Absentee Titleholders 27 11.89 4. Encroachers 43 18.94 Dumre –Damauli Section 227 100% Distribution Sub-station 5. Absentee Titleholders 13 % Chapali Subs-Project 6. Absentee Titleholders 74 100 Total 314 100 Source: Census Feb – Apr 2009 Note: The figure to be up-dated during the detail design

11` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

22. NEA will approach all the affected households/persons including the absentees through the Compensation Fixation Committee to be formed under the Land Acquisition Act 1977 and they will be notified, and contacted from the beginning of acquisition process as per the prevailing Acts.5

3.3.2 Extent of Effect on Land

23. The extent of impact due to effect on land could not be assessed from the locations of all investment components as the project affected households in Chapali sub-station and distribution sub-stations/switching centers (from different 10 districts), were found to be absentee (Ref. chapter 3.1). Therefore, the analysis on extent of impact on land is limited to 102 project-affected households having land ownership certificates in the location of Dumre- Damauli –New Marsyangdi 132 kV Transmission Line construction section.

24. Of the total (102) affected titleholders (having ownership certificate), 87 (85.29%) households will have effect on their land only up-to 10% out of their total owned land and there are only 15 (14.70%) households having more than 10% effect on their land out of their total ownership (Table 3-6). Effect on land by (i) total land ownership, and (ii) affected plot is included in Appendix C-3.

Table 3-6: Extent of Impact on Land Out of Total Ownership

S.N. Effect on Land in Ranges (ha) No. of HHs Percentage 1. Up – to 5% 84 82.35 2. 5 – 10 % 3 2.94 3. 10 – 20 % 5 4.90 4. 20 – 30 % 2 1.97 5. 30 – 40% 3 2.94 5. 40 – 100 % 5 4.90 Total 102 100 Source: Census Feb – Apr 2009 Note: The figure to be up-dated during the detail design

25. In resettlement planning, households loosing more than 10% land out of their total ownership are considered as significantly affected. In Nepal, land under the transmission line is not acquired permanently for maintaining the RoW. The owners will be allowed to cultivate them as usual. However, the RoW affected land will be restricted to construct buildings and plantation of trees within the corridor of influence (e.g. both sides 9 meters for 132 kV T/L) as provisioned by Electricity Rule 1993. In such cases, affected households/APs will be paid compensation based on current market price to be fixed by the Compensation Fixation Committee (CFC). Thus, generally, in the transmission line projects, households having more than 10% effect on their cultivating land due to restriction for RoW are not considered as significantly affected. Accordingly, significant impact due to effects on land have been expected to be low even in the proposed project. It is in the sense that the project requires

5 As provisioned in the Land Acquisition Act 1977, information about acquisition plan to be publicly notified as a part of land acquisition and resettlement process. As stipulated in Clause 9 (1) of the Act, such notification, also include information on several aspects such as: (a) Purpose of acquiring land; (b) Whether to acquire land only or also the structures (residence, wall etc); (c) Name of place and ward number of the location; (d) Parcel numbers of land plots to be acquired or their remarkable boundary, if parcel numbers are not available; (e) Area of land to be acquired; and, (f) Other relevant information. Such information are disseminated through the notice boards of relevant central, district and local level government offices. These days, it is also being practiced to notify about the acquisition plan even from the national and local newspapers and radio program. Furthermore, there is also provision notifying individually if needed (Land Acquisition Act 1977, Clause 9, Sub-clause 2).

12` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP only about 4.66 ha of land for permanent acquisition and 21.39 ha of land for RoW (Ref. Table 1-1, and Appendix A-1 for details).

26. However, exceptionally 2 households in Dumre-Damauli T/L section likely to have significant impact (75%-87% of the total plot area) on their residential land causing restriction to construct houses in the affected land for maintaining the RoW of the proposed Dumre- Damauli 132 kV new transmission line (Table 3-7). As both of these households have been found owning only the affected land plots. The area of affected land plots is four Aana (127.18 sq.m.)6 of each affected household. The LARP has provisioned compensation to such households at full replacement cost for the effect on their land. Details on total land ownership status of APs and extent of project’s impact is included in Appendix C-3.

Table 3-7: HHs Likely to have Significant Impact on their Residential Land

S.N. AP No. No. of HHs Total Land Affected Area % Angle Point of Owned Due to RoW Tower) (sq.m) (sq.m.) 1. 2 – 3 1 124.18 95.37 75 2. 3– 4 1 127.18 111.28 87.50 Source: Census Feb – Apr 2009 Note: The figure to be updated during the detail design

3.4 Effect on Structures

27. The project also likely to affect 23 residential/commercial structures and associated utilities) in Dumre-Damauli-New Marsyangdi T/L and Chapali Sub-station sections. Of the total affected structures, 19 are residential, one is residential cum commercial and three are toilets of the affected residential structures (Table 3-8). Description of the affected structures by construction types and other details is included in Appendix C-4.

Table 3-8: Types of Affected Structures

S.N. Type of Structures No. Percentage (%) 1. Residential structures 17 73.91 Marsyangdi-Dumre –Damauli T/L Section 2. Residential cum Commercial Structures 1 4.35 3. Toilets of the Affected Residential Structures 3 13.04 Chapali Sub-station Section Residential structures 2 8.69 Total 23 100 Source: Census Feb – Mar 2009 Note: The figure to be up-dated during the detail design

3.4.1 Ownership of the Affected Structures

28. Twenty structures are owned by either titleholders encroachers or squatters and only five (about 25%) households are owned by titleholders. The titleholder encroachers are the owners of affected structures having land in the area, but having their houses constructed in Government land. Similarly, the squatters are those who have constructed their houses temporarily in the NEA land near to the tapping point of proposed New Marsyangdi sub- station area along the bank of Raudikhola (a river) of Aanbu Khairini VDC, Tanahu district (Table 3-9).

6 As reported by the APs they do not have any alternative land to construct their house except the affected plot

13` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Table 3-9: Ownership of the Affected Structures

S.N. Ownership Types of Affected Structures Number of Owners of the Affected Residential/Commercial Structures[a] In Numbers Percent Dumre-Damauli- Dome section 1. Titleholders 3 15% 2. Titleholder Encroachers [b] 12 60% 3. Squatters 3 15% Chaplain Sub-station project 4 Titleholders 2 10% Total 20 100% Source: Census Survey, Feb-Mar 2009 Note: The figure to be up-dated during the detail design [a] The number of toilets is not included in the ownership status of residential/commercial structures as they are part of affected residential/commercial structures [b] The titleholder encroachers are the owners of affected structures having land in the area, but having their houses constructed in Government land.

29. The affected residential/commercial structures may not require relocation sites as the owners of the affected structures having been reported owning alternative land to shift their house in the same location. The squatters residing in the NEA land near the tapping point for proposed New Marsyangdi sub-station may also be temporarily shifted in the nearby land acquired by NEA early during the construction of Marsyangdi Hydroelectricity Project. The squatters have been found migrated from the adjoining district (Lamjung) to the project location for employment/better earnings and being involved in small-scale income generating activities (e.g. wage earning, making and selling bamboo baskets etc) in the vicinity.

3.5 Loss of Agricultural Crops and Trees

3.5.1 Loss of Crops

30. Implementation of the Project may also cause temporary and permanent loss of agriculture crops in an estimated area of 291.26 ha of land. Based on the technical design, an estimated area of 4.66 ha of permanently acquired agriculture land will have permanent loss of crop production and another 286.60 ha. of land along the corridor of transmission line will have temporary loss of crops during the construction phase. Table 3-10 provides the estimated quantity of permanent and temporary loss of crops due to the Project. Details on estimated quantity of permanent and temporary loss of crops, and cultivation area is included in Appendix C-5.

Table 3-10: Estimated Loss of Crops

S.N Types of Loss Ropani Sq.m. ha. % 1. Permanent Loss 90.87 46389.17 4.66 1.36 2. Temporary Loss[a] 5438 2865995 286.60 98.64 All total 5528.87 2912348.17 291.26 100 Source: Census Survey, Feb-Mar 2009 and Statistical Information of Nepalese Agriculture 207/2008, Ministry of Agriculture

[a] The area calculated to estimate impact on land (permanent acquisition and Restriction to use) may vary with the area calculated to estimate the loss of crops as the latter on also include even the area not likely to be acquired but having effect on crops (e.g. the second circuit stringing).

14` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

3.5.2 Loss of Private Trees

31. Implementation of the Project may also likely to affect private trees existing along the proposed RoW corridor in different project locations. Table 3-11 provides the estimated number of trees likely to be affected in different Project locations.

Table 3-11: Loss of Private Trees

S.N Sub-projects Affected Trees (No.)[a] 1 Dumre-Damauli 132 kV New T/L Construction 2,888[a] 2 Middle Marsyangdi- Marsyangdi 132 kV T/L second Circuit Construction 500 [b] 3 Baniyani-Chandragadhi new 33 kV stringing 200[b] 4 Siraha Mirchiya new 33 kV stringing 150[b] Total Estimated 3739 Source: Census Survey, Feb-Mar 2009; Note: The figure to be updated during the detail design [a] Estimated based on census survey, and [b] Estimated based on census survey field observation

3.6 Impact on Indigenous/Ethnic and Minor Caste Households

32. For ADB assisted development projects that affect indigenous people adversely and significantly, an Indigenous People Development Plan (IPDP) to be prepared. ADB Handbook on resettlement mentions, if more than fifty people experiencing resettlement effects are particularly vulnerable, for example; hunter-gatherers the impact to indigenous people is considered significant.

33. In line with the ADB guidelines, the numbers of Indigenous/Ethnic and Minor Caste households likely to have significant impact due to the project were also enumerated during the census. As revealed by the census data only few (17) indigenous/ethnic and minor caste household likely to have significant project impact in Dumre-Damauli-New Marsyangdi T/L construction and Chapali sub-station sections (Table 3-12).

34. However, the Indigenous/Ethnic people in the Project locations has been found assimilated with the main social stream sharing common social and cultural values and norms as well as languages and benefiting from the similar economic opportunities. The IP and minors in the project location are neither hunter nor pastoralist groups. They were not found having district language, culture and other traditional or cultural livelihood (like, fishing, hunting, collecting herbal plants) sources. Rather they were also found involved in different occupation in private and even in Government jobs. The LARP has made provisions of compensation and other assistance to such affected IP based on Government and ADB policy. In addition, Income Restoration and Improvement Program (IRIP) have also been incorporated in the LARP for project affected indigenous/ethnic/minor caste groups and other socially vulnerable households in order to ensure project’s benefits to such households.

Table 3-12: Indigenous/Ethnic and Minor Caste HHs Likely to be Affected

S.N. Type of Effects No of HHs % Dumre-Damauli-New Marsyangdi Sub-project 1. Significantly Affected due to ROW 1 18.75 2. Effect on Residential/Commercial Structures due to RoW 14 68.75 Chapali Sub-project 3. Effect on Residential Structure due to permanent acquisition 2 12.50 Total Affected Indigenous/Ethnic and Minor Caste HHs 17 100.00 Source: Census Feb-APR, 2009 Note: The figure to be updated during the detail design

15` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

35. During the census the project affected indigenous HHs have opted for compensation at replacement rate and other financial assistance as per the provisions in the project. List of Indigenous/Ethnic and Minor Caste HHs likely to have significant Project impact is included in Appendix C-6.

3.7 Impact on Other Socially Vulnerable Groups and Below Poverty Households

36. ADB policy also specifies about the need of adequate attention to vulnerable groups in designing and implementing land acquisition and resettlement plan. The vulnerable groups for ADB guidelines are (i) the poorest without legal title to assets, (ii) household headed by women, (iii) indigenous peoples, (iv) ethnic minority and pastoralist, (v) minority groups, disable and those unable to work. Here it is to be noted that these categories of people are also equally considered as vulnerable by the Government and have given priority to consider them as the target groups focusing to improve their socio-economic status while planning and implementing development projects. The provision of income restoration and improvement in the LARP aligns with the Government’s Three Interim Plan, Millennium Development Goal, and other policies and guidelines. In line with the Government policy and ADB guidelines, it was also approached to identify socially vulnerable groups having project’s impact through socio-economic survey and census while preparing the LARP. Based on the census data 205 vulnerable households (single women headed households 14, households headed by aged person 44, households having disabled persons 6, Dalit or traditional occupational caste households 30, indigenous households 93, and below poverty households 4) have been identified in the location of Dumre-Damauli-New Marsyangdi section (Table 3-13).

Table 3-13: Impact on Other Vulnerable and Socially Disadvantaged Households

S. Vulnerability Category Vulnerable HHs by Project Districts (No.) N Tanahu Gorkha Total 1. Single Women Headed Households 14 1 15 2. Households Headed by Aged Person 44 3 47 3. HHs having Disabled Persons in the Family 6 1 7 4 Dalit (minor caste) Households 30 1 31 5. Indigenous People’s Households 93 8 101 6. Below Poverty Level Households 4 - 4 Total Vulnerable Households 191 14 205 Source: Census, May – June 2005

37. As shown on the table above the project also likely to affect 4 Below Poverty Level (BPL) households in terms of per capita cash income require to maintain subsistence level. Major reasons of better household income of the project affected households have been reported due to migration of family members from a majority of households (84.02% HHs) to India, overseas, and other parts of country - mostly for job. Ref Appendix C-1 for details). The provisions of compensation, other financial assistance and income restoration and livelihood improvement program made under the LARP will support the affected BPL and other vulnerable household to maintain their living condition. In addition, the employment opportunity likely to be generated during the construction phase further support them on enhancing their household income. The above number of vulnerable households however, needs to be finalized based on sensitivity analysis during the detail design or implementation phase for effective implementation of income restoration and improvement program. Some of the indicators to select vulnerable households for income restoration as suggested in ADB guidelines are:

16` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

How will the project affect sources of income and livelihood?

What are the income levels of APs?

Are there other non-monitory sources of livelihood?

What are the constraints and opportunities for income generation

Is replacement of land available?

Will it be possible to continue with agricultural activities?

How many of the APs cannot be reabsorbed back into their previous occupations?

What are the existing skills of APs?

What type of training do APs need and is there capacity to provide it?

How many APs would like to start their own business?

3.8 Loss of Common Property Resources

38. Seven community forests in Dumre-Damauli projects likely to be significantly affected due to construction of new 132 kV transmission line. Based on walkover survey across the Angle Points (from AP 0 – AP 39) of the proposed T/L alignment route the following community forests likely to be affected by the project (Table 3-14).

Table 3-14: Community Forest Likely to be Affected in Dumre – Damauli Section

S.N. Angle Points of Name of Community Forest Area in No. of Users Towers ha.[a] Households [b] 1. 0 – 1 Bagbhanjyang Community Forest 30.42 383 2. 2 – 3 Birata Community Forest 37.50 406 3. 3 – 4 Ranipani Community Forest 35.04 145 4. 17 – 18 Basudev Community Forest 42.50 148 5. 18 – 19 Nidhiswara Community Forest 44.13 69 6. 19 – 20 Baghmare Community Forest 39.52 120 7. 20 - 21 Chandi Sthan Community Forest 35.75 400 Total 261.86 1671 Source: NEA, Technical Design and Census Feb. 09 –Apr. 2009

[a] Community Forest users Groups, Follow-up and Evaluation Report, District Forest Office, Tanahu 2008 (in Nepali) [b] Forest users groups at different locations

39. The Government owns community forests in the project locations. They are just handed over to the community for better management, conservation, and rational utilization of forest products. As reported by the community in different locations of Dumre-Damauli section, before 1990 the forests in the project locations used to be managed by the Government and were in degraded conditions due to extensive smuggling and irrational exploitation. However, after 90s the forests gradually handed over to the community in different locations. The community also started to replant the forest in some areas. Norms for the rational utilization of forest resources (e.g. by forming forest users groups, scheduling harvesting seasons for wood and timber, keeping watchers in the forest to prevent wood stealing, restricting the cattle for grazing especially the regenerating seasons in order to avoid the loss of new generation plants etc) were developed, which ultimately helped to protect the forest better than before.

1`7 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

40. The consulted community forest user groups were found supportive to the proposed project and also opted for compensation and other supports as per the Government rule for the likely impact. Some of the community forest users groups, particularly between AP 0-7 and AP-17 (Basudev Community Forest) and local community have requested NEA to consult with them while fixing the final alignment route in order to further minimize the impact. It is also to be note that the Basudev Community Forest Users groups have requested to push back the existing location of AP 17 (about 100 meters), towards north, in order to avoid the concentrated impact. The users group between AP 3-4 has opined their view to avoid the commercial land from RoW impact by pushing back toward to forest. Similarly forest users’ community between AP 0-2 have also requested to finalize the alignment only after consulting the group as they have plan of making a Martyrs Memorial Park in the forest located between AP 0-2.

18` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

IV. RESETTLEMENT PRINCIPLES, POLICY, AND LEGAL FRAMEWORKS

41. Land acquisition principles adopted for this project recognize the Land Acquisition Act 1977, Electricity Act 1992, Electricity Rule 1993, and ADB Policy on Involuntary Resettlement 1995. Other relevant Acts, Government policies and NEA practices and experience on implementing acquisition and resettlement plan will also be considered while implementing this Land Acquisition and Resettlement Plan under the project.

4.1 ADB Resettlement Policy

42. It is mandatory for all ADB assisted Projects to follow specific ADB safeguard guidelines on environmental and social issues. The Bank Policy recognizes and addresses the Resettlement and Rehabilitation (R&R) impacts of all the affected persons irrespective of their titles and requires for the preparation of an appropriate land acquisition and resettlement plan in the case of where involuntary resettlement exists. These ADB policies are the guiding rule to identify impacts and to plan measures to mitigate various losses likely to occur due to the project. The key objectives and principles of the ADB Involuntary Resettlement Policy are:

Involuntary resettlement should be avoided where feasible.

Where population displacement is unavoidable, it should be minimized by exploring all viable project options.

People unavoidably displaced should be com pensated and assisted, so that their economic and social future would be generally as favorable as it would have been in the absence of the project.

People affected should be informed fully and consulted on resettlement and compensation options.

Existing social and cultural institutions of resettles and their hosts should be supported and use to the greatest extent possible, and resettles should be integrated economically and socially into host communities.

The absence of formal legal title to land by some affected groups should not be a bar to compensation; particular attention should be paid to hou seholds headed by women, and other vulnerable groups, such as indigenous people and ethnic minorities, and appropriate assistance provided to help them improve their status as a part of the project.

As far as possible, involuntary resettlement should be conceived and executed as a part of project.

The full cost of resettlement and compensation should be included in the project cost.

Cost of resettlement and compensation may be considered for inclusion in Bank Loan for the project

19` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

4.2 Policy and Legal Frameworks

43. Land acquisition, compensation and resettlement in Nepal is still considered as project based activity. As there is no na tional policy to d eal on the matters related to l and acquisition and resettlement issues, it is guided by Land Acquisition Act 1977, and various sectoral Acts (e.g. Immovable Property Acquisition Act 1956, Land Reform Act 1963, Water Resources Act 1992, Electricity Act 1992/Rule 1993, Civil Aviation Authority Act 1997, Environmental Projection Act 1997 etc). At present, hydro-electricity, irrigation, roads, civil aviation and industrial projects are some of the main sectors requiring land acquisition. Since 1980 development projects in Nepal have been guided by their respective policies on case- to-case basis, which have resulted in v ariations in criteria on compensation for land and assets acquired for the project. Among others, such inconsistencies have been considered one of the factors affecting the project adversely. In consideration to this issue and the underlying policy gaps on land acquisition and resettlement activities, the Government of Nepal have drafted a National Policy on Land Acquisition, Compensation and Resettlement in Development Projects in 2004 with the technical assistance of ADB TA 4422 NEP. The policy however, yet to be implemented.

44. At present, Land Acquisition Act 1977, is considered as the core legal document to guide the tasks related to land acquisition and resettlement activities in Nepal. The Act seems insufficient to c over a wide range of resettlement issues that may emerge while implementing resettlement activities in different sectors (like; hydroelectricity, transmission lines etc). Therefore, the Act also use to be supplemented by different sectoral Acts and rules (e.g. electricity acts and rules) and even the guidelines of dif ferent funding agencies (e.g. ADB, WB etc) while implementing land acquisition and resettlement plan in different sectors (e.g. road, electricity, urban development, drinking water, irrigation etc). Some of the key provisions of Land Acquisition Act and other related Acts/Rules are as follows:

A. Land Acquisition Act:

Government can acquire land for any public purpose (Clause 3&4 of the Land Acquisition Act).

Land Acquisition Officer (LAO) shall be responsible to identify, survey, and notification to the concerned parties and other works related to acquisition (Clause 5&6)

The LAO shall determine the amount of compensation for the damaged property (house, wall, trees, etc) while conducting initial survey works (Clause 7).

Within 15 days after the preliminary actions the LAO has to confirm the required land and submit other details of the required property to the Chief District Officer (CDO).

The CDO to publish public notification with details of the affected property after receiving the report of the preliminary activities (Clause 9)

Any grievances to disable land and property acquisition could be reported to Home Ministry within 7 days of public notification to CDO. Home Ministry is to decide on the grievances within 15 days as a capacity of district court (Clause 11)

Upon addressing the grievances CDO can hold the land for acquisition for the purpose of project (Clause 12)

20` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Compensation for the acquired land / property to be d ecided by a compensation fixation committee comprising of Chief District Officer, Land Revenue Officer, Project Manager, and representatives of the District Development Committee. The compensation to be paid in cash and separate compensation rates could be fixed for the partially affected land or completely affected land (Clause 13).

Official tenant to be paid compensation as per the prevailing laws (Clause 20).

Unpaid Government tax could be deducted from the compensation amount (Clause 21).

Preliminary hearing of grievances/cases related to the Act shall be done by CDO. Appeal to such hearing could be made to the appeal court within 35 days (Clause 40).

B. Electricity Act and Rule

Government can acquire any private land through standard process in order to utilize for water resources development including electricity generation, transmission, and distribution (Electricity Act, Clause 33).

Government can prohibit use of land in th e places of generation, transmission or distribution infrastructures or, other structures, for other specific purpose in and around them through publication/dissemination of public notice in Government Gazette from time to time (Electricity Rule 66).

Land and property owners of acquired or restricted property shall be paid full compensation amount as determined by compensation fixation committee (Electricity Rule 87).

A compensation fixation committee under the Chairmanship of Government appointed person, and representatives (concerned person or representative of the project, an expert appointed by the Government in the field of e lectricity, fixed property owners or representative, representative of Land /revenue Office, VDC representative) shall decide the compensation of affected land and property (Electricity Rule 88).

4.3 Difference between ADB Policy and GON Resettlement Framework

45. Both Government Acts and ADB aim to compensate the APs having acquisition and resettlement impacts. However, there are some differences between ADB guidelines and GON legal framework on the issues related to land acquisition and resettlement matters. Some of the key difference is briefly summarized on Table 4-1.

21` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Table 4-1: Difference between ADB and GON Policy on Resettlement Framework

S.N. ADB Policy GON Policy 1. Compensation to land irrespective of Legal ownership required ownership 2. Compensation to all affected assets as per Subject to be determined by Compensation Fixation prevailing market rate Committee 3. Provision of relocating land to Aps Only if Government land is available 4. Have own guidelines Have only draft guidelines (awaiting for Government approval) 5. Provision of hundred percent compensation NEA have been pay ing only 10% compensation for the affected loss based on the market value to the RoW effected land restricted to use except for agriculture in most of its projects outside the capital 6. Previsions of multiple options for Moe focused on cash compensation compensation 7. Provision of full compensation without any Government tax and loan can be deducted (LA Act deduction 1977, Clause -21)

4.4 NEA Practices on Land Acquisition and Resettlement

46. NEA has been implementing Land Acquisition and Resettlement Plan (LARP) for several projects. Such projects also include the projects financed by different funding agencies (e.g. world bank, ADB, KfW etc) having their own land acquisition and resettlement guidelines. Therefore, in addition to the prevailing Acts, Government guidelines and ADB Policy, NEA will also consider its past experiences and practices while implementing this LARP. Appendix D-1 provides a synopsis of NEA’s practices on implementing resettlement plan in its completed and ongoing projects.

4.5 Resettlement Principles & Assistance of the Proposed Project

47. The resettlement principles adopted in this Project will provide compensation and resettlement assistance to all affected persons and businesses, in accordance with ADB’s Policy on I nvoluntary Resettlement and Government’s Act. Based on the above policy features, the principles of R&R for this Project will entail the following:

The negative impact on persons affected by the Project would be avoided or minimized as much as possible;

Where the negative impacts are unavoidable, the Project-affected persons will be assisted in improving or regaining their standard of living. Vulnerable groups will be identified and assisted to improve their standard of living;

Land replacement7/or cash compensation at replacement costs based on current market rate to the households affected by the loss of land.

Cash compensation will be paid for structure residential/commercial/residential-cum- commercial and other structures) affected by the Project at replacement cost

Assistance should be provided to the owners of structures and non-titleholders, who may incur loss of ability to maintain livelihood during relocation and resettlement

7 There is also provision of land for land compensation to the APs having complete loss of their land only if government land is available in the area (Land Acquisition Act 1977, Clause 14)

22` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Rehabilitation assistance i.e.; compensation for lost business and workdays (including employees) due to relocation and disruption of business enterprise.

Before taking possession of the acquired lands and properties, compensation and Resettlement & Rehabilitation (R&R) assistance will be made in accordance with this policy.

Appropriate mechanism will be established at the district level to ensure speedy resolution of grievance and disputes.

All activities related to resettlement planning, implementation, and monitoring would ensure involvement of women, other vulnerable and APs.

4.6 The Entitlements

48. The entitlements for this Project are based on Land Acquisition Act, 2034 (1977), Nepal Electricity Act 1992 and Rule 1993, ADB guidelines and NEA past practices and experiences from the T/L projects. The LARP has provisioned compensation for all ty pes of losses (land, structures, business / employment, and workday wages etc). All affected persons under the project will be compensated at full replacement cost based on current market price. The APs will also receive other cash grants and resettlement assistance such as shifting allowance, compensation, for loss of workdays / income due to dislocation, income restoration and improvement assistance, and other financial assistances to vulnerable groups in addition to the compensation for the loss of affected assets.

49. In the Resettlement Plan, compensation and assistance provisions have been made to cover compensation for lost assets and restore or enhance the livelihoods of all categories of affected people. Table 4-2 (Entitlement Matrix) provides further details regarding application of the principles, definition of entitled persons, and entitlements. As mentioned in Clause 9 Sub-clause 3 of the Land Acquisition Act 1977, the duration of compensation days will be determined by Compensation Fixation Committee (CFC). Further, Clause 37 of the Act illustrates that the Committee may extend the period of additional three months, if those affected not collect compensation. After termination of extended three months’ period, the amount will be deposited to the Government account. Any grievances and objections will be referred to the Grievances Redress Committee (GRC). Description on compensation provisions made for different items are discussed in the following sub-chapter.

4.6.1 Compensation for Land

50. There are two types of project’s effect on land; (i) permanent acquisition for the construction work, and (ii) restriction to used certain portion of land except for agriculture purpose to maintain RoW of the new transmission line (9 meter both side for 132 kV). Ownerships of the permanently acquired land will be transferred to NEA after compensation whereas it will not be transferred in the case of land restricted to maintain the RoW. Similarly, the permanently acquired land will not be allowed for cultivation but the land restricted to maintain RoW will be allow for cultivation. The LARP has made following provisions to compensate for the effect on land: 51. The LARP provisions for cash compensation to the APs at replacement cost for the permanently acquired land (agricultural, residential, commercial, forestry and others) to construct T/L structures, or sub-stations, and other associated works.

52. However, the land restricted to use except for agriculture will not be acquired permanently. The owners will be allowed to cultivate but restricted to use such land for the

23` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP purpose of constructing structures and plantation of trees. Such restricted land for RoW will be paid compensation for the affect based on current market prices subject to be fixed by Compensation Fixation Committee (CFC) as being practiced in most of the NEA’s T/L projects. NEA in most of the T/L projects has been paying 10% compensation to the land restricted to maintain RoW based on current market price to be fixed by CFC.

53. If the remaining land parcel after the permanent acquisition is too small, and that cannot be made as a separate parcel by breaking from the existing parcel8 and AP does not own adjoining plot and is willing to dispose the land, the entire plot shall be acquired at the replacement cost.

54. If the APs with small sized residential land have been restricted to maintain RoW for the new transmission line and the APs do not have alternative lands to construct their house (subject to be confirmed by CFC) such land will be acquired at replacement cost based on current market price. However, this provision may not be applicable to the APs having adequate area of land to build their house in the remaining portion of affected land or having other alternative land.

4.6.2 Compensation for Loss of Crops and Trees

55. One time compensation will be paid to the APs having temporary (one time) loss of standing crops/plants and trees due to construction activities at current market price based on average production. The provision will also applicable to the encroachers and squatters. For the APs having permanent loss of crop production in their cultivating land due permanent acquisition will be paid compensation for a period of 15 years at current market rate based on the average production on their acquired land.

4.6.3 Compensation for Structures (residential/ residential-cum-commercial)

56. Compensation for the affected structures used as residential, commercial and other utilities (e.g. toilet, well, cattle shed etc) shall be paid to APs at full replacement costs. The squatters/encroachers will also be eligible for assistance for the loss of structures/assets at full replacement costs. Owners of the affected structures will be allowed to take/reuse all the salvageable materials for rebuilding/rehabilitation of the structures without any deduction from the compensation amount.

4.6.4 Compensation for the Loss of Community Forest

57. The new 132 kV T/L in Dumre-Damauli section likely to have significant impact on seven-community forests. The community forest users groups shall be compensated in consultation with respective forest users groups and District Forest Office (DFO). Compensation cost for the Community Forests have been incorporated in Environmental report as being practiced in other transmission line projects implemented by NEA.

4.6.5 Financial Assistance to Tenants

58. Registered tenants of the affected land will be entitled to get 50% compensation for the affected plot as per the prevailing law.

8 As practiced by Land Measurement Office in Nepal, land piece less than 2 Aana 2 paisa (79.49 sq.m.) cannot be broken from the existing plot.

24` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

4.6.6 Shifting/Transportation Allowance

59. Households having affect on their residential/commercial structures will be paid transfer/shifting allowance @ NRs 25,000 per household to cover the cost of moving structures (transport plus loading and unloading). The shifting costs have been estimated in consultation with the APs having affect on their structures.

4.6.7 Land Replacement Cost

60. Based on the census survey two households in Dumre-Damauli new T/L section likely to have 75% to 87.5% affect on their residential land. The area of both residential land is 129.18 sq,m. The RP has provisioned land replacement costs @ NRs. 500,000 per households. The cost required to purchase equivalent land (124.18 sq.m.) in the location have been estimated based on the current local market rate assessed during the census survey.

4.6.8 Compensation for Loss of Business and Shifting Allowance

61. Households having affect on their business will be provided one time financial assistance @ NRs 25,000 to meet the cost require to shift the business premises plus compensation for the loss of business for the transitional period. The amount has been estimated in consultation with APs assuming one month as the average time that may require to find/shift to the alternative premises in consultation with the AP. The cost was calculated based on average per month income from the affected business, including transportation costs required to shift the business.

4.6.9 Transitional Allowance to the Affected Structure Owners

62. Households having affect on their residential/commercial structures will be paid one time financial assistance @ NRs 24,000 per each affected household to meet the rental cost for alternative/temporary accommodation for the period of six months (NRs. 6,000 per month) plus associated management cost to be require during the transitional period.

4.6.10 Income Restoration and Improvement

63. Land acquisition and resettlement activities in Dumre – Damauli-New Marsyangdi section likely to lead several issues on the regular income and livelihood of the APs having effect on their residential/commercial structures and assets. The vulnerable affected households considered in the LARP are; (i) households having affect on residential/commercial structure, (ii) households having significant loss of land; and (iii) other vulnerable project affected households (e.g. indigenous, ethnic, minor caste households, women headed households, below poverty level households etc).

64. The LARP has provisioned income restoration and improvement activities to the project affect vulnerable households having significant impacts as well as other socially vulnerable households (e.g. indigenous, ethnic, minor caste households, women headed households, below poverty level households etc). Here, it may be noted that the Government of Nepal aims to improve the living conditions of poor and vulnerable people also by involving them on different income generating activities and providing them skill trainings. Based on the socio-economic survey and census data there are 223 number of vulnerable households in Dumre-Damauli T/L and Chapali sub-projects. Table 4-3 provides the breakdown of vulnerable households likely to have project effect.

25` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP

Table 4-3: Vulnerable HHs Requiring Income Restoration and Improvement Activities

S.N. Categories of Vulnerable HHs No. of HHs Dumre-Damauli Sub-project 1. Households having affect on residential /Commercial Structures 20 2. Households having significant impact on land 2 3. Other project affected vulnerable households (poor, indigenous, minor 201 caste, ethnic, women headed households etc) Sub-Total 223 Chapali Sub-project 4. Households having affect on residential Structures Sub-Total 2 Total 225 Source: Socio-economic and census Feb-April 2009

65. As shown in table above most of the vulnerable households (except two households in Chapali sub-station area) are the residents of different locations within the corridor of Dumre-Damauli-New Marsyangdi T/L section. As Dumre-Damauli-New Marsyangdi section is located along the Kathmandu-Pokhara highway (aprox 200 km) there are several scopes of income generation along the highway corridor through small scale enterprises ( e.g. tea and snack shop, other shops fruits and vegetable shops, automobile repairing center, restaurant and hotel business etc). Therefore, consulted family members of the vulnerable households were found interested on skill training or to initiate small enterprise development activities (e.g. cattle farming, vegetable farming, keeping small shops etc) for their livelihood improvement.

66. In the location of Dumre-Damauli-New Marsyangdi section, there are several Government, non-Government and private sources including NGOs,9 involved on imparting skill trainings to different target groups. Some of the potential skill training options available in the location are related to agribusiness activities (e.g. vegetable and fruit farming, cattle farming, pig farming, fishery, bee farming), ready made and fast food production, auto mechanic, driving, beauty parlor, tailoring, hotel and restaurant business, house wiring, electric and electronic good repairing, radio-TV repairing, carpentry, metal works etc. Different NGOs are also available in the district to facilitate on organizing skill-training and enterprise development program under the project.

67. The LARP has provisioned small scale skill training and enterprise development program to the vulnerable groups based on consultation with the targeted population and local market in Dumre-Damauli-New Marsyangdi section. In order to implement the program, local NGO to be hired by NEA to support on implementing LARP will also be assigned to play facilitators’ role on implementing income restoration and improvement program. The project office will provide a list of project affected vulnerable households to the NGOs with the key selection criteria (e.g. households having affect on residential/commercial structures, household with significant impact on land, below poverty level households, Indigenous/ethnic minor caste/women headed household etc). With the support of project office, the NGO will identify potential candidates for skill training or enterprise development activities from the vulnerable project affected households with special priority to women. NGO will also facilitate the candidates on the selection of appropriate training or enterprise development packages. The land Acquisition and Resettlement Plan (LARP) have allocated budget for skill training/small scale enterprise development activities @ NRs. 15,000 per person (on lump

9 Some of the active NGOs in Tanahu district are Gramin Sanskritan Samaj, Hoste Haiste Baal Bikas, Fulbari Sewa Kendra, Samaj Sewa Samuha, Tanahu Sewa Samiti, Seto Gunras, Saichik Samaj, NGO Net etc

26` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP sum basis) based on consultation with the local NGOs and some private sources involved on providing skill trainings in the project location.

68. The NGO will be responsible to monitor the income restoration and livelihood improvement program and to report the project. However, the vulnerable project affected households in Chapali, Kathmandu will directly be paid financial allowance @ NRs. 15,000 to enroll their family members in small-scale skill training or to initiate small scale enterprise development activities as there are just two number of vulnerable households in the project section.

27` Table 4-2: Entitlement Matrix Nature of Loss Application Definition of AP Entitlements Actions Responsibility

A. Land Acquisition (Applicable in case of fresh acquisition and / or legally confirmed ownership on the ROW Permanent acquisition Land and other assets Person(s) with land titles Cash compensation at replacement cost Full compensation for NEA and CDO of agricultural/ permanently acquired for the based on current market price. Provision the loss of land at Residential/ Project of land for land compensation will be made replacement cost commercial and other for those APs having complete loss of land private lands by in accordance to the prevailing Act10 landowners

Land restricted to use Portion of land used to Person(s) with land titles One time cash compensation for the land Compensation for land NEA and CDO except for cultivation maintain the RoW of newly restricted to maintain RoW of the new restricted to maintain along the RoW of constructed T/L under the transmission lines, except to use for RoW of the newly transmission lines project and restricted to use agriculture purpose. constructed except for agriculture purpose transmission lines The rate of compensation to be fixed by Ownership of such land will Compensation Fixation Committee (CFC) remain to the titleholders and to be formed under the prevailing Acts. will have full right to utilize the land for cultivation except to built structure and plantation of trees within the area of RoW Permanent acquisition Land and other assets Registered tenant(s) Fifty percent cash amount as Compensation for the NEA and CDO or restriction to use of permanently acquired or compensation to the tenants out of the tenants of affected agricultural/ restricted to use except for total compensation fixed for the land Residential/other agriculture due to RoW impact permanently acquired land or land private commercial restricted to use except for agriculture to and other private lands maintain the RoW of new transmission except for cultivation lines. by Tenants The remaining fifty percent compensation amount will be given to the titleholders of the affected land as provisioned in the prevailing law of Nepal

10 There is also provision of land for land compensation to the APs having complete loss of their land only if government land is available in the area (Land Acquisition Act 1977, Clause 14)

28 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Significant impact on Those having small size of Person(s) having Cash compensation at replacement cost Compensation to those NEA and CDO residential land due to residential land within the significant RoW impact of based on current market rate subject to be who will have significant restriction to use due restricted RoW area of new new transmission line on confirmed by the CFC that the AP(s) don’t impact on their to RoW of new transmission line and also not their residential land have any alternative land to build their residential land due to transmission line or having alternative land to causing restriction to house RoW causing restriction restriction to use land construct their house (subject construct residential to built residential for the construction of to be confirmed by CFC). building structure residential building due to ROW impact

Temporary effect on Land temporarily acquired by Person(s) owning land Contract to be signed between the APs Compensation for the NEA and land due to use by the the contractors during the and property owner for temporary temporarily acquired Contractor contractors during implementation phase use/acquisition of land/assets. The land/assets by the construction phase contract to confirm rental contractors rate/compensation and mode of payment. Project Office and the Contractor to ensure compensation for the land/assets temporarily acquired during the construction phase.

B. Loss of Residential /Commercial Structures (Applicable to the owners of the structures)

29` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Loss of residential / Residential/commercial and Owners of the affected Cash compensation for the loss of built–up Compensation for the CDO/NEA commercial and other other associated structures residential/commercial structures at full replacement costs based residential/commercial structures by (e.g. toilets, cattle shed etc) and associated on current market price. structures titleholders acquired for the project structures The land occupied by the affected structure within the RoW will not be acquired permanently. However, the portion of land coming under the RoW will be restricted to use except for agriculture and the owners will be paid compensation for the restricted portion of land subject to be fixed by the CFC

Owners of affected structures will be allowed to take/reuse their salvageable materials

The APs will be provided one time shifting allowances to move the household effects and materials. The allowance will be paid @ NRs 25,000 per affected households as estimated based on consultation with the APs on current market price.

The APs will also be provided transitional allowance to meet to cost of renting accommodation and other management cost for a period of 4 months (estimated time to rebuilt the house) @ NRs 5,000 per month (Total NRs 20,000 per affected household)

30` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Loss of residential / Structure on ROW / Govt. land Owners of Structure Cash compensation for the loss of built–up Compensation for lost NEA, CDO, commercial structures structures at full replacement costs. assets to the squatters and NGO by squatters The land occupied by the affected structure within the RoW if owned by titleholders, the portion of land coming under the RoW will be restricted to use except for agriculture and the owners will be paid compensation for the restricted portion of land subject to be fixed by the CFC

Owners of affected structures will be allowed to take/reuse their salvageable materials

The APs will be provided one time shifting allowances to move the effects and materials. The allowance will be paid @ NRs 25,000 per affected households as estimated based on consultation with the APs on current market price.

The APs will also be provided transitional allowance to meet to cost of renting accommodation and other management cost for a period of 4 months (estimated time to rebuilt the house) @ NRs 5,000 per month (Total NRs 20,000 per affected household) C. Loss of Income Generating Activities (Whether or not land is legally occupied)

31` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Loss of agricultural - Loss of crops from the land Owner of crops or trees One time cash compensation for the Cash compensation for CDO,NEA, crops, fruit and wood permanently acquired for the temporary loss of agricultural crops along the District Forest trees project, the corridor of RoW due to stringing of T/L temporary/permanent Office, District at current market price based on average loss of crops/trees Agriculture Office - Loss for crops likely to occur production of the affected area. and Contractor during the construction phase from the land restricted to use Titleholders having loss of crops due to except for agriculture to permanent acquisition of land will be paid maintain the RoW of new compensation for 15 years, equivalent to transmission line, and the average production of the acquired area to be computed at their current market - Loss for crops likely to occur price. on the agriculture land along the existing RoW corridor while One time compensation for loss of fruit stringing transmission the trees for average fruit production for next 15 transmission line including years to be computed at current market second circuit. value.

One time compensation for loss of wood- trees at current market value of wood (timber or firewood, as the case may be). Loss of income by Business affected by Owner of business / One-time lump sum cash grant; minimum Short-term NEA and CDO, commercial structure transmission line / sub-station business tenants one-month’s (assuming one month as the compensation for loss of NGO owner / tenants construction operating business on minimum time required to shift and restart income. conducting businesses rented premises the affected business) income based on from rented premises / the nature of business and type of losses to land be assessed on a case-to-case basis. Loss of business Business structure on acquired Owner /renter of Shifting allowance will be paid to the Removal /relocation NEA and CDO, premises land and/or legally confirmed business premise affected businesspersons on actual cost assistance and NGO ownership rights on ROW basis. Loss of wages by Income reduced during period Employees of One-time financial assistance equivalent to Short-term NEA and CDO employees of readjustment businesses 30 days wages (assuming 30 days as the compensation for loss of required time to restart the affected income. business/work or to find new employment by the wage employee) to be computed at local wage rates.

32` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP: LARP Income restoration and Households having significant Households having Enrollment of the family members on Involvement of NEA, CDO, livelihood improvement impact on land /structures and significant impact and income generation or skill training activities vulnerable households and NGO of the significantly other vulnerable households project affected for the improvement of household income. on livelihood affected households (e.g. indigenous/ethnic/ vulnerable project Each family members to be involved in the improvement activities and other vulnerable minority caste group, female affected households (e.g. livelihood improvement activities will be Households (e.g. headed etc) Female headed house, provided NRs 15.000 to get enroll in the indigenous/ethnic/ old and disable head of skill training or to start other livelihood minority caste group, households without any improvement activities (e.g. cattle farming, female headed etc) earning members, Dalits, keeping small shops etc) indigenous, minor caste, below poverty level The cost is estimated based on consultation households etc) with the NGO and affected families and local market to start small income generating activities. Loss of cultural & Community/cultural/religious Temple/Monastery/Religi Complete rehabilitation/restoration by the Replacement NEA, CDO, community structures/resources affected ous tree/Graveyard etc Project; or, cash compensation for /restoration of NGO, and local structures by the project restoring/reestablishment of the affected religious/cultural/commu Community /facilities/resources cultural/community structures and nity structure /facilities installations, to the recognized patron/custodian. Unanticipated adverse The EA and Project implementation authorities will deal with any unanticipated consequence of the Project during and after the implementation in the light impact due to Project and spirit of the principle of the entitlement matrix. intervention or associated activity

33` Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

V. CONSULTATION AND STAKEHOLDER PARTICIPATION

5.1 The Approach

69. Stakeholders were consulted at different levels during the Resettlement Plan preparation process. The consulted stakeholders also include representatives of relevant line agencies (e.g. NEA officials, CDO, Land Measurement Office, District Forest Office, and Local NGOs etc), local people and project-affected families including the vulnerable groups, forest users groups, local level social workers, businesspersons, and other resource persons. The stakeholder consultation was found effective on disseminating information about the project, conducting socio-economic and census survey, and soliciting other information/data required to prepare the resettlement plan. A detailed consultation matrix is included in Appendix E-1.

70. Some of the major feedbacks derived from the consultation with the affected people are:

Involvement of local people in project design finalization: Being the primary stakeholders and the population directly affected by the Project, local people are eager to be kept informed and consulted with regard to finalizing Project design and implementation the resettlement plan;

Employment opportunity for local people: As far as possible local people should be encouraged and prioritized to get them involved in the Project construction activities as skilled and unskilled labors;

Fair and timely compensation: The community is positive towards the project and had no reservations provided they are consulted while finalizing the project alignment route, adequately compensated for all their losses whether partial, complete, agricultural, residential or commercial and there will not be descriptions on compensation for similar types of losses of similar value.

Special consideration: The Project should either change the technical design or provide compensation at replacement cost based on current market price and other assistance to the vulnerable households likely to have significant impact on their land/structures;

Regular monitoring: The Project office to ensure technical quality of work and compliance of contractors liability to the affected people and the Project; and

Project to support on address grievances: There should be provision of a separate unit in the Project Office to listen to the suggestions and grievances and to address them;

5.2 Disclosure of LARP

71. Disclosure of LARP to the local people could be helpful on informing them about the Project and provisions of compensations and other assistance made for the losses due to the project. NEA endorsed the LARP and they are disclosing translated (in Nepali) version of Summary Resettlement Plan to the affected households through respective District Development Committees (DDCs) or other sources/media. The approved LARP will be posted on ADB web site.

5.3 Further Consultation & Community Participation

72. Several additional rounds of consultations with the APs need to be carried out during the detail design and Project implementation phase for the effective implementation of the LARP. Such consultation should be collaborated with the district level line agencies, NGOs to be hired by the Project and local people including the APs and vulnerable groups.

34 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

VI. INSTITUTIONAL FRAMEWORK

6.1 The Setup

73. NEA will be the Executing Agency (EA) of the proposed project. The Managing Director (MD) of NEA will be the Chief In-charge for the implementation of all components under the project including the Land Acquisition and Resettlement Plan. The MD will form a project implementation team headed by the Directors of Transmission and Distributions Departments. NEA will assign Project Managers (PM) for the each project components under the respective Departments (Transmission and Distribution). The PM will act as Project Implementation Unit (PMU) and report to the respective Directors (Transmission and System Operation Department and Distribution and Consumer Service Department) of Executing Agency. Technical, administrative and account sections will support each Project Office headed by PM to implement the LARP. Land Acquisition Officers under the NEA or in house social scientist will also support the PM on initiating and implementing the land acquisition and compensation distribution activities as and when required.

6.1.1 Transmission and System Operation Department

74. Four Project Managers (PM) will be assigned under the Transmission and System Operation Department to implement the project activities of (i) Kohalpur-Mahendranagar Second Circuit Stringing; (ii) Middle-Marsyangdi–Damauli–Marsyangdi; (iii) Chapali-substation Construction and Chabahil-Lainchaur Underground Cabling and Sub-station Enhancement; and (iv) Expansion of Matatirtha Sub-station. Among them, PM for Kohalpur-Mahendranagar Second Circuit Middle-Marsyangdi–Marsyangdi second circuit and Dumre-Damauli-New Marsyangdi new T/L and sub-station activities will be stationed at project locations and the other PM will be stationed at the central level as these project locations are located in . The PMs will be supported by technical, administration and account sections during the overall implementation process of LARP.

6.1.2 Distribution and System Operation Department

75. Though apparently, the distribution sub-stations and switching centers to be constructed under the distribution components are scattered across the country the scale of project activities in these sub-stations/switching centers are small. In this sense, only two Project Managers (one for eastern and one for central and western districts) will be assigned to implement the distribution components in 10 different districts including Kathmandu. The PM assigned for Eastern districts will be stationed at Dhanusha to implement the project activities in Eastern districts (Jhapa, Siraha, Dhanusha, Mahottari and Sarlahi). Similarly, the PM assigned for Central and Western districts will be stationed at Pokhara and implement the project activities in Central and Western (Kathmandu, Kaski, Syanja, Parbat, and Bardiya) districts. These PMs will also be supported by technical, administration and account sections.

6.2 Roles and Responsibilities

6.2.1 The Executing Agency (EA)

76. Executing Agency (EA) will be responsible for the overall implementation of project activities and the implementation of LARP. The EA also mobilizes NEA’s Land Acquisition and Resettlement Officers11 or in-house social scientist to support, and supervise the LARP implementation activities under the project as needed. Similarly, the EA will engage local NGO/s

11 As provisioned in Land Acquisition Act 1977, NEA will recommend Government to select Land Acquisition Officer(s) to initiated and pursue acquisition related for different components as needed. 35 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP to assist PM on implementing LARP and other associated activities (e.g. HIV/AIDS, Trafficking, income restoration and improvement etc.) as per the scope of land acquisition and resettlement impact and requirement to implement other associated activities (e.g. information awareness campaign to AP, HIV/AIDS, income restoration etc).

6.2.2 The Project Office

77. Project Managers (PM) will head the project Office. The PM will regularly update EA on the progress of LARP implementation activities. The PM will coordinates with the Chief District Officers (CDOs)12 and formally request for the formation of Land Acquisition and Compensation Fixation Committee (LACFC) to pursue the verification, valuation and compensation distribution activities of the project. Land acquisition and resettlement related documents prepared for the project will be handed over to the CDO. The PM to assist CDO on the valuation, verification and finalization affected assets and APs. The PM also to involve local NGO, wherever applicable to implement the LARP, and associated activities. The PM will also coordinate with the CDO to establish Grievance Redressal Committee in accordance to Clause 11 of Land Acquisition Act 2034 (1977) (see chapter 6.2.3). The PM will update and report the EA, district level line agencies and form a local level committee as per the need and scope of resettlement activities of the projects.13

6.2.3 Grievance Redress Committee (GRC)

78. There are provisions under the Land Acquisition Act of Nepal – 2034 (1977) to allow unsatisfied persons (i.e. APs) to file or represent their cases to the CDO and raise objection against acquisition by a notice to Ministry of Home and get redressal under the LA Act Clause 11 Section 1,2, and 3. 79. As stipulated in Clause 11 of the Land Acquisition Act 1977, CDO is responsible to give decisions on the grievances related to land acquisition and resettlement issues. In order the facilitate the process, the PM will coordinate and support the CDO as a member secretary on addressing the grievances. With the view to reduce the pressure of grievances in LARP implementation process, general issues, such as; family members share on the amount received from compensation, demands of other financial grants and assistance. etc will be handled and addressed by PM, or also with the help of other district / local level, stakeholders (e.g. district level line agencies, local people, representatives of local level political parties, APs etc). The organized form of such stakeholder groups on deciding such general issues is also known as Grievance Readdressal Committee (GRC), and use to be represented by different stakeholders depending upon the scope and complexities. The other members to be included in the GRC includes representatives from the district level line agencies (Land Revenue Office, Land Measurement Office, Municipality or Village Development Committee, District Development Committee, District Agriculture Office, District Forest Office, etc), Community Based Organizations (CBOs)/NGOs in the districts, representatives of affected/ vulnerable households including women, local representatives (eg. school techers, health workers, businessmen, local resource persons etc), local leaders and other relevant persons. Figure 2 provides an organogram of the GRC.

12 There are 75 administrative districts in Nepal. Chief District Officers (CDO) are the Chief Administrative Units of the districts. As per the Land acquisition Act 1977, CDO the legally authorized person to implement the land acquisition activities under respective districts. 13 For example; PM involved in implementing land acquisition activities for distribution sub-station or switching centres may not require to involve NGOs as the area of land to be acquired for such project activities is maximum about 0.70 ha of land

36 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Figure 2: Organogram of the GRC

Chief District Officer

Project Manager

Representatives of Representatives of Independent Line Agencies CBOs/NGOs Representation of Affected including households including Municipality/VDC Vulnerable Groups and Women

80. However, there could be several other issues that may also be emerged and may go up-to the level of CDO and even up-to court. As provisioned in the Land Acquisition Act, issues related to APs objection on the acquisition and the compensation rate may also be formally complained to the Ministry of Home through Chief District Officer (CDO). Clause 11 and 18 of Land Acquisition Act illustrates that, the Ministry of Home, seeking the view of CDO (if necessary), decides on such grievances and the decision is considered as of the decision of District Court. However, complains and cases related to the issues on ownerships, will be forwarded to the court and compensation will be given as per the court decision.

6.2.4 Non-Government Organizations (NGOs)

81. ADB guidelines, suggests to involve local NGO/CBOs as local partners while implementing the LARP. It is in the sense that local NGOs with experience, knowledge of, and contact with APs can assist a resettlement-implementing agency in many ways. It is anticipated that involvement of NGOs in land acquisition and resettlement activities is considered useful with respect to:

o Identifying the APs and updating land acquisition and resettlement record o Planning compensation distribution activities o Coordinating with the APs and local level institutions o Developing information campaigns and community participation; o Strengthening local institutions and community self-reliance, and o Gathering and sharing information and avoiding potential problems; o Planning and implementing income generation schemes and awareness program against HIV/AIDS and Human/Drugs Trafficking o Delivering services to hard-to-reach communities in a more efficient and cost effective manner. 82. However, involvement of NGOs in land acquisition and resettlement activities may be determined by several factors, that also include; (i) scope of resettlement activities and extent of impact, (ii) complexities of tasks (iii) project locations, (iii) scope of incorporating other associated programs (e.g. income restoration, HIV/AIDS, information and awareness campaign etc). In consideration to such factors, there appears scope of involving local NGO on implementing LARP in Dumre-Damauli-New Marsyangdi new T/L and sub-station construction component. As shown by the census data an estimated number of 225 households likely to be directly affected due to

37 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP land acquisition and resettlement activities in the location of this investment component. The affected households also include vulnerable households (irrespective of the type and extent of loss). As a Transmission Sub-station is also be going to be constructed under the component there is scope of implementing awareness program against HIV/AIDS, Human & Drug trafficking and so on.

6.3 Role and Responsibilities

83. NGOs will assist the Project Office on informing people about the likely resettlement effects and solicit their views regarding compensation and relocation options, and facilitate both the APs and Project Office. NGO with the support of Project Office also launch information and awareness program on health safety and hazard related to electricity and transmission line and HIV/AIDS and Human Trafficking in the settlements along the corroder of Dumre-Damauli new transmission line and sub-station construction areas. The NGOs will also be responsible for execution and monitoring the progress of the works related to implementation of LARP. A Sample Terms of Reference (ToR) of the NGO is incorporated in Appendix F-1.

84. Institutional frameworks to implement the Land Acquisition and Resettlement Activities have also been prepared in consultation with the NEA Officials in Distribution and Transmission Departments. The figure of institutional framework is given in Figure 3.

38 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Figure 3: Institutional Framework to Implement Land Acquisition and Resettlement Plan

Nepal Electricity Asian Development Bank Authority

Managing Director

General Manager General Manager Transmission and System Operation Distribution and System Operation

Director Director Transmission and System Operation Distribution and System Operation Department Project Managers Project Manager Project Manager (Eastern Districts) Project Managers for each (Central and Western

of the following projects will Districts) A Project Manager will be be stationed at: stationed at Pokhara to A Project Manager will be Implement following stationed at Pokhara to 1. Butwal-Kohalpur second Distribution Sub-stations in Implement following circuit stringing Central and Western Distribution Sub-stations in 2. Middle Marsyangdi- Districts: Central and Western Damauli- Marsyangdi Districts: transmission lines and 1. Baniyani S/S, Jhapa 1. Mulpani Switching Center, sub-station works 2. Siraha S/S 3. Chapali Sub-station, and Kathmandu 3. Dhanusha S/S 2. Swyambhu S/S, Kathmandu Chabahil-Lainchair 4. Mahottari S/S 3. Dhikur pokhari/Banskot S/S underground cabling 5. Sarlahi S/S 4. Syanja Switching Center 4. Matatirtha S/S 5. Kusma S/S, Parbat 6. Mainapokhar S/S, Bardiya

Project Managers stationed for each Transmission and Distribution projects to be Supported by following NEA sections to pursue project and LARP Activities on regular basis

1. Technical Section 2. Account Section 3. Administration Section

Project Managers will coordinate with central/district level line agencies including NEA as needed and form local level committees as needed during LARP implementation process:

Grievance Readdress Committee District Level Line Agencies DDC Representatives VDC Representatives NGOs Representatives APs and Vulnerable Groups

39

Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

6.4 Implementation Schedule

85. The Land Acquisition and Resettlement Plan (LARP) is expected to be implemented from the Third quarter of 2009 immediately after the loan negotiation. In order to meet the targets set- forth, advance actions such as; establishment of the Project Office (PO), formation of Land Acquisition and Compensation Fixation Committee (LACFC) under the CDOs and hiring NGO will be carried out in the early stage immediately after the loan negotiation. The Project will provide adequate advance notification to the APs and will pay their due resettlement benefits, including shifting and income restoration/assistance prior to start of construction work. Table 6-1 provides tentative schedule to implement the Land Acquisition and Resettlement Plan prepared based on project implementation schedule as envisaged in the Aide Memories circulated by ADB on 27 March 2009. Contractors for civil works to be mobilized only after the completion of compensation, land acquisition and resettlement activities.

Table 6-1: Schedule of Implementing Land Acquisition and Resettlement Plan

S.N Activities 2009 2010 J A S O N D J F Months 1 2 3 4 5 6 7 8 1. Formation of PIU, institutional arrangement and mobilization 2. Updating of Land Acquisition and Resettlement Plan 3. Submission of LARP to CDO and verification 4. Formation of Compensation Fixation Committee (CFC) 5. Notification to APs by CDOs 6. Complain and Grievances by APs 7. Decision of Complains and Grievances by CDO 8. Publication of revised list of APs 9. Compensation Distribution 10. Transfer of ownership and Land Acquisition 11. Income Restoration 12. Monitoring and Evaluation of the implementation of LARP and Associated Activities (e.g. income restoration, human trafficking and HIV/AIDS etc) 13. Site Clerance Note: The LARP implementation schedule in tentative and may be changed in accordance to the project implementation schedule.

6.5 Staff Training on Resettlement Implementation

86. Staffs to be involved in land acquisition and resettlement activities, including officials of land revenue office of the Project districts and NGO staff will be provided a brief orientation and training in ADB’s resettlement policy, Land Acquisition Act, Electricity Act/Regulation and other relevant Act, regulation and policies. The training session will focus on (i) public consultation and participation, (ii) Entitlements and compensation & assistance disbursement mechanisms; (iii) grievance redressal; (iv) income restoration and improvement (v) HIV/AIDS and Trafficking (vi) Resettlement data-base management; and (vii) monitoring of resettlement operations.

6.6 Resettlement Data Bank

87. A detail measurement survey of the affected assets will be carried out during the detail design in order to prepare an updated inventory of affected assets and persons. All this information will be collected by the respective Project offices, and NGOs and computerized by the Project Office. This data bank will form a basis for implementation, monitoring and reporting of the LARP implementation. 40 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

41 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

VII. COMPENSATION ACQUISITION AND RESETTLEMENT BUDGET

88. All the costs required to implement this land acquisition and resettlement plan for Nepal Electricity Connectivity and Energy Efficiency Project to be borned by GON/NEA. Both the Government as well as NEA is committed to set aside and provide the respective amounts of funds to implement the LARP for the Project and guarantee to meet unforeseen obligations in excess budget estimates, if required.

7.1 Valuation of Affected Assets and Fixation of Compensation Rate

89. Compensation Fixation Committee (CFC) to be formed under the Land Acquisition Act 1977 and Electricity Act 1993 to determine compensation for the acquired/restricted assets and associated loss due to the project. According to Clause 13 (2) of Land Acquisition Act, and Electricity Rule 1993 Clause 88, the other members to be included in the committee are (i) Chief of the District Land Administration Office or Land Revenue Office, (ii) Chief of the Project, (iii) Representative of District Development Committee (DDC). The Land Acquisition Act 1977 also ensures separate compensation rate for those having complete loss of land, and those having partial affect and also land for land compensation (if Government land is available in the project area/VDC) in Clause 14. Clause 16 the Land Acquisition Act, further stipulates to consider; (i) Government guidelines, and policies published in different time; (ii) likely losses to be beared by the affected people; (iii) current market value of acquired land; (iv) value of affected structures, crops, land etc, and (v) losses caused due to relocation/shifting of the affected people, while fixing the compensation rate. In line with the Land Acquisition Act, Electricity Act/Rule and ADB policy, this preliminary land acquisition and resettlement cost has been calculated with a view to estimate the likely cost to implement the land acquisition and resettlement plan prepared for the project. The estimated cost includes compensation for the affected assets including land and structures and other financial assistance/support to be provided to the APs and vulnerable groups and other associated costs.

7.2 Valuation of Affected Assets and Associated Costs

7.2.1 Valuation of Land

90. Cost for land has been calculated based on the current market price derived through socio- economic survey of project affect families, prevailing land transaction rate in the project locations, and consultation with NEA officials at central and district level and local key informants in project locations.

91. The principle adopted while estimating compensation for land are; (i) hundred percent compensation based on local market price for permanent acquisition, and (ii) ten percent of the total value of affected land based on current market price for the land restricted to maintain the RoW of new transmission line as being practiced by NEA while compensating in previous projects. However, considering the social sensitivity on restricting land for RoW, an additional amount (10 % of the compensation cost) has also been calculated as contingency in the total estimated compensation cost to meet the other unanticipated compensation cost and administrative expenses required to implement the LARP. The current market rate of the affected land as responded by the APs during census and socio-economic survey is given in Appendix G-1.

7.2.2 Valuation of Structures

92. The rate determined by Government of Nepal, Department of Housing has been taken as a basis to estimate the cost of affected structures. The Department of Housing is the authorized

42 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Government body for the valuation of costs for structures through the Government Gazette (Nepal Rajpatra, Section IV, number 50, Date 2045/12/6 (1988). The Department annually updates its rate based on current market price.

7.2.3 Valuation of Affected Crops

93. The average quantity of crop loss has been estimated based on technical design and estimated land area to be acquired and affected due to the project. Compensation for the affected crops has been calculated based on Government standard rate14 taking into account of major crops, average production and value of produced crops on market rate.

7.2.4 Valuation of Affected Private Trees

94. The number of affected trees and costs for compensation for affected trees for Dumre- Damauli- New Mrsyangdi section has been calculated based on socio-economic data. For other project the same is estimated during the field investigation and cost has been calculated in lump- sum basis assuming NRs 1,000 per tree in average as recommended by local people.

7.2.5 Valuation of Shifting/Transportation Allowances

95. Shifting/transportation allowances to the households having affect on their structures to move the household goods and materials of demolished house has been estimated to be NRs 20,000 per affected structure based on consultation with APs.

7.2.6 Valuation of Land Required for Replacement

96. The resettlement plan has also provisioned land replacement compensation at market price to the households having significant RoW impact on the residential land causing complete restriction to built residential house in the affected land, and if the APs don’t have alternative land to built their house (subject to be confirmed by compensation fixation committee).

7.2.7 Valuation of Affected Business and Shifting Cost

97. Compensation for the loss of business and shifting allowances to the affected business has been calculated based on the estimate made by affected persons. The estimated cost covers the average monthly income from the affected business, time require to find the alternative premises, and shifting/transportation cost.

7.2.8 Estimation for Income Restoration and Improvement Activities

98. The average cost for income restoration and improvement have been calculated based on consultation with the APs asking minimum amount required to get involved in small scale skill training at least up-to three months, or to initiate small enterprise development activities like; cattle farming, fish farming, keeping small shops etc.

7.3 Cost Estimated for Compensation and Other Financial Assistance

99. Compensation cost and other financial assistance estimated to implement this Land Acquisition and Resettlement Activities is given in the following tables:

14 Statistical Information of Nepalese Agriculture 2007/2008, a publication of Ministry of Agriculture, Nepal 43 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Table 7-1: Compensation for Land (Ref. Chapter 3.3) S.N. Types of Compensation Amount (NRs) 1. Cost for Permanent Acquisition 330,512,955.56 2. Compensation for Restriction to Used for RoW 15,025,995.19 Total Compensation for Land (NRs) 345,538,950.75 (Details given in Appendix H-1) Table 7-2: Compensation for Structures (Ref. Chapter -3.4) S.N. Construction Types of Structure Structures No. Estimated Compensation (NRs) Dumre – Damauli – New Marsyangdi Section Residential Structures 1. Cement Block 4 1,570,496.29 2 Thatched 3 845501.75 3 Stone/Brick 10 7,845,699.77 4 Mud Mortar RCC 1 327,946.02 Sub-total 10,589,643.83 Utilities (Toilets of the affected Structures) 5 Cement Mortar 1 32,416.97 6 Mud Mortar 2 18,219.22 Sub-total 3 50,636.19 Sub-total of Dumre – Damauli-New Marsyangdi Section 21 10640280.02 Chapali Sub-station Residential Structures 1 Stone/Brick 2 888316.33 Sub-total of Chapali Sub-station 2 888316.33 Total Estimated Compensation for All Affected Structures (NRs) 23 11528596.02 Source: Census, Feb-April, 2009 (Appendix C-4 provides further details on the affected structures) Table 7-3: Compensation for Loss of Crops (Ref. Chapter -3.5.1) S.N. Type of Loss Ropani Sq.m. ha. Value of Affected Crops (in NRs) 1 Sub-total of Permanent Loss 78 39470 3.95 314,539.24 2 Sub-total of Temporary Loss 2608 1425995 142.60 11,359,764.02 All total / in NRs 2685 1465465 146.55 11,674,303.27 Note: Compensation for the loss of crops is calculated based on the Average Cost, Return and Net Profit of Some Major Crops, Government of Nepal, Ministry of Agriculture and Co-operatives, Argo-Business Promotion and Statistics Division, Nepal, 2007/2008

100. Compensation for the loss of crops also include the cost required to compensate those having permanent loss of crops for a period of 15 years at current market rate based on the average production on their acquired land as provisioned on entitlement matrix. A Detailed calculation on loss of crops is included in Appendix C-5.

Table 7-4: Compensation for Loss of Private Trees (Ref. Chapter 3.5.2) S.N Project Sections Affected Trees Estimated Compensation (No.) Rate per Tree (NRs) 1 Dumre-Damauli-New Marsyangdi T/L 2,888 1,000 2,888,000 2 Middle Marsyangdi- Marsyangdi II Circuit 500 1,000 500,000 3 Baniyani-Chandragadhi 33 kV stringing 200 1,000 200,000 4 Siraha Mirchiya 33 kV stringing 150 1,000 150,000 5 Butwal-Kohalpur 132 kV second circuit 1000 1,000 1,000,000 Total Cost in NRs 4,738,000 Source: Census, Feb-April, 2009

44 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Table 7-5: Compensation for Loss of Business (Ref. Chapter -3.4) S.N. Project Sections No. of HHs Rate (NRs) Total 1 Dumre-Damauli- New Marsyangdi S/S 1 20,000 20,000 Total Cost in NRs 20,000 Source: Census, Feb-April, 2009

Table 7-6: Transitional Allowance to APs having Loss of Structures (Ref. Chapter -3.4) S.N. Project Sections No of Rate (NRs) Duration Total HHs (months) (NRs) 1 Dumre-Damauli- New Marsyangdi 18 4,000 6 432.000 2 Chapali Sub-station 2 4,000 6 48,000 Total Cost in NRs 400,000 Source: Census, Feb-April, 2009

Table 7-7: Shifting Allowances for the Affected Residential/Commercial Structures (Ref. Chapter -3.4) S.N. Project Sections No Rate (NRs) Total 1 Dumre-Damauli- New Marsyangdi S/S 18 20,000.00 360,000.00 2 Chapali Sub-station 2 20,000.00 40,000.00 TotalCost in NRs 400,000 Source: Census, Feb-April, 2009

Table 7-8: Land Replacement Cost (Ref. Table 3-6) S.N. Project Sections No of HHs Rate Per HH (NRs) Total

1 Dumre-Damauli- New Marsyangdi S/P 2 500,000 1,000,000 TotalCost in NRs 1,000,000 Source: Census, Feb-April, 2009

Table 7-9: Income Restoration and Improvement Cost (Ref. Chapter - 3.6 & 3.7) S.N. Vulnerability Types Vulnerable HHs by Rate (NRs) Estimated Project Districts Cost (NRs) Tanahu Gorkha Total No. No. No. 1 Single Women Headed HHs 14 1 15 15,000.00 225,000.00 2 HHs Headed by Aged Person 44 3 47 15,000.00 705,000.00 3 HHs having Disabled Persons 6 1 7 15,000.00 105,000.00 4 Dalit (minor caste) Households 30 1 31 15,000.00 465,000.00 5 Indigenous People’s Households 93 8 101 15,000.00 1,515,000.00 6 Below Poverty Level Households 4 - - 15,000.00 60,000.00 Total Estimated Vulnerable Households 181 14 201 Total Estimated Cost in NRs 3,015,000.00 Source: Census, Feb-April, 2009

45 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

7-10: NGO Mobilization Cost (Ref. Chapter - 6) S.N. Items Rate Duration Amount Remarks (NRs. Per (Months/No.) (NRs.) Month/Activity) 1 Team Leader 40,000 2 80,000 Intermittent Input 2 Local Social Scientist 40,000 2 80,000 Intermittent Input 3 Local Overseer 25,000 3 75,000 Intermittent Input 4 Field Coordinators/ Mobilizers 15,000 8 120,000 Full Time 5 Video Show for information awareness 3000 15 (shows) 45,000 Intermittent against different social evils (e.g. Activity Human/drug trafficking, HIC/AIDS, Gamble, Alcoholism etc) and income restoration and improvement 6 Information Awareness Program on (i) LS LS 200,000 Intermittent Land Acquisition and Resettlement Activity Plan, (ii) Health Safety, (iii) HIV/AIDS, Human/Drugs Trafficking, Gambling and Alcoholism 7 Facilitation to income restoration and LS LS 50,000 Intermittent improvement program Activity 8 Equipment and material purchase LS LS 50,000 9 Administrative Cost 20,000 20,000 10 Transportation LS LS 25,000 11 Stationeries LS LS 25,000 Total 770,000 Contingency (10%) 77,000 Total Cost 847,000

Table 7-11: External Monitoring and Evaluation (Ref. Chapter - 3.6 & 3.7) S.N. Items Rate Duration Amount (NRs. Per Month) (Months) (NRs.) 1 Independent M&E Expert 150,000 2 300,000 2. Engineer 100,000 2 200,000 3 Mobilizers/Field Worker 30,000 1 30,000 4 Field Allowance LS LS 50,000 5 Vehicle LS LS 50,000 6 Stationeries LS LS 25,000 Sob-total Total 475,000 Contingency 47,500 All Total 522,500 Source: Census, Feb-April, 2009

15 Altogether an estimated amount of NRs. 425,795,500.7 (US$ 5,322,444 ) is required to implement the Land Acquisition and Resettlement Plan (LARP). The summary of the resettlement cost also including other associated and administrative cost is given in Table 7-12.

15 Exchange rate: 1 USD = NRs 80.00 46 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Table 7-12: Summary of Resettlement Budget and Cost Estimate

S Descriptions Unit Total Qty Total Value of Compensation Amount Ref. N Cost (sq.m./no./ Land (NRs) (Exchange Rate: 1 USD = Table (NRs) %) Applicable NRs 80.00) only for Row Effect in NRs. In USD 1 Compensation for the 7-1 permanently acquired land (100%) 7124.78 46389.17 NA 330,512,955.60 4131412 2 Compensation for the 7-1. restricted land within the RoW of proposed new Transmission Line (10%) 26.54 213500 150,259,951.90 15,025,995.20 187824.9 3 Compensation for the 501243. 7-2. Structures 3 23 (no.) NA 11,528,596.00 144107.5 4 Compensation for the 7-3. permanent loss of crops 5.67 831470 NA 4,718,088.00 58976.1 5 Compensation for the 7-3. temporary loss of crops 11.15 1456465 NA 16,246,684.02 203083.6 6 Compensation for the 7-4. loss of private trees 601.52 4738 NA 2,850,000.00 35625 7 Compensation for 7-5. Loss of Business 20000 1 20,000.00 250 8 Transitional 7-6. allowance to the households having complete loss of residential/commercia l structures 20000 20 NA 400,000.00 5000 9 Shifting allowance to 7-7. affected residential/commercia l structures 20000 20 NA 400,000.00 5000 10 Land 7-8. replacement/purchasi ng cost for the AP having complete loss of residential land 500000 2 NA 1,000,000.00 12500 11 Income Restoration 7-9 and Improvement 15000 201 NA 3,015,000.00 37687.5 12 NGO mobilization 7.10 cost LS LS NA 847,000.00 10587.5 13 External Monitoring 7-11. and Evaluation Ls LS NA 522,500.00 6531.25 14 Sub-total 387,086,818.80 4838585 15 Contingency for compensation and administrative expenses 10% NA 38,708,681.90 483858.5 All Total Nepalese Rupees (NRs) 425,795,500.70 5322444

47 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

VIII. MONITORING AND EVALUATION

8.1 Need for Monitoring

101. Monitoring is required as the back-up support for the successful implementation of Land Acquisition and Resettlement Plan (LARP). ADB guideline suggests to involve local NGOs to play key role on implementing LARP. The LARP implementation activities will be monitored internally and externally. Generally, internal monitoring is conducted by Project Office and external agencies or independent consultants undertake the task of external monitoring.

8.2 Internal Monitoring

102. The Project Office and NGO will be responsible for internal monitoring. The LARP includes indicators and benchmarks for achievement of the objectives under the resettlement program, which can be categorized as follows:

Process indicators: Includes project inputs, expenditures, staff deployments, etc.;

Output indicators: Results in terms of numbers of affected persons compensated and resettled, incomes restored, additional assistance provided etc; and

Impact indicators: Relates to the long-term effect/impact of the project on people’s lives in the project-affected area.

103. The first two types of indicators, related to process and immediate outputs and results, will be monitored internally by the Project Office. The Project Office will collect this information from the project site and assimilate in the form of a monthly progress report to assess the progress and results of LARP implementation, and adjust the work program, where necessary, in case of any delays or problems. Specific activities under RP implementation that will be monitored internally by Project Office are the following:

o Information campaign and consultation with APs o Status of land acquisition and payments on land compensation o Compensation for affected land, structures and other assets o Relocation/shifting of APs o Payments for loss of income o Income restoration activities

104. The Project Office will also be responsible for monitoring day-to-day resettlement activities with the support of NGO. Baseline socio-economic census and the land acquisition data provides the necessary benchmark for field level monitoring. Field level monitoring will be carried out through (i) review of census information; (ii) consultation and informal interviews with the APs; (iii) in-depth case studies; (iv) informal sample survey of APs; (v) key informant interviews; and (vi) public meetings at community level.

105. A performance data sheet will be developed to monitor the project at the field level. Quarterly reports will be received from the field offices and Project Office will be responsible for

48 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP overall project level monitoring. Also, Resettlement Officer or the NEA in-house social scientist will monitor the LARP implementation and report on a quarterly basis to EA on the progress.

8.3 External Monitoring

106. An external monitoring agency will be engaged by NEA to carry out independent monitoring on bi-annual basis that also include post Project evaluation. External monitoring is carried out through outside researcher or consulting agency or NGOs, or through independent consultants. The external monitoring will be focused on:

- Evaluating social and economic impact of land acquisition and economic rehabilitation of the APs;

- Verifying the objective of enhancement or at least restoration of income levels and standard of living of the APs have been met;

- Suggesting modifications in land acquisition and economic rehabilitation, where necessary, to achieve the principles and objectives as set before; and

- Making final ex-post evaluation to ensure all resettlement and Land acquisition activities have been completed; any problem issues identified are followed-up (including recommendation of mitigation measures for the budget); and learning lesson for such Projects must be recorded.

- More specifically following activities will be required to be performed by the External Monitoring Agency:

Verification of internal monitoring – to ensure the appropriateness of activities being carried out by PIU and the field offices;

Demographic baseline and biannual household surveys – to monitor progress from a pre- Project, pre-resettlement benchmark.

Evaluation of delivery and impacts of entitlements – to determine if they are as per the approved Resettlement Plan.

Evaluation of consultation and grievance procedures - especially levels of public awareness of grievance procedures, access by AP’s and households to information and rapid conflict resolution.

Evaluation of actual operations of grievance committee - assisting APs as required and acting as observers.

Declaration of successful implementation – summing up the outcome of activities on completion of all entitlements distribution and resettlement activities.

Recommend follow-up actions for the EA - relating to outstanding actions required to complete achievement of objectives of the RP and resettlement policies, additional mitigation measures for APs, if required, and timing and budget of these additional measures.

107. Such external monitoring will be carried out on a biannual basis throughout the Project period. The external agency will directly report their findings to both NEA and ADB. The ToR of External Monitoring is included in Appendix I-1.

49 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

8.4 Reporting Requirements

108. The Project Managers responsible for supervision and implementation of LARP will prepare monthly progress reports on resettlement activities and submit to the EA, and quarterly reports to EA and ADB. The external monitoring agency will submit bi-annual reviews directly to ADB and determine whether or not resettlement goals have been achieved, more importantly analysis of whether livelihoods and living standards have been restored/enhanced is mandatory and suggestion of suitable recommendations for improvement must be made. The external monitoring agency will also carry out a final ex-post evaluation to ensure that all resettlement and Land acquisition activities have been completed. Any problems or issues identified are followed-up (including recommendation of mitigation measures and supplementary budget); and learning from such issues must be recorded which would help to deal with issues such as these more effectively.

50 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

APPENDICES

1 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix A-1:

Land Acquisition Requirements for Different Investment Components

S.N. Name of Sub-project Required Available Estimated Area to be Land Government Acquired Land/Forest (sq.m) (sq.m.) In sq.m. In In Ropani ha A. Middle Marshyangdi- Dumauli – Marshyangdi 132 kV T/L and Related Sub-station Works 1 Construction of 51 no. of (8x8) towers for Dumre- 3264 2496 768 1.52 Damauli 132 kV New T/L 0.08 RoW for Dumre – Damauli ( 9m both side) 18 km 324000 148500 175500 347.02 17.8 0 Tower construction (11.25) for 15 MVA, 132kV/33kV 635.8 190.74 445.06 0.88 New Marsyangdi Sub-station Construction at Markichock (5 nos) 0.05 RoW for New Marsyangi Sub-station (1km) 18000 - 18000 35.59 1.83 Sub-total 345900 151186.74 194713.1 385.01 19.7 4 B. Construction of a new 30 MVA, 132 kV/11kV Sub-station at Chapali 2 Construction of Chapali Substation (approx 35 ropani) 17805.9 - 17805.9 35 1.79 Sub-total 17805.9 - 17805.9 35 1.79 C. Energy Access Quality Enhancement 3 Construction of distribution sub-station at Baniyani 6918.86 - 6918.86 13.60 0.70 4 Construction of distribution sub-station at Mrchiya 6918.86 - 6918.86 13.60 0.70 5 Construction of distribution sub-station at Dharampani, 6918.86 6918.86 0.00 0 Dhanusha (1 Bigha) 6 RoW for 33 kV line (2 m both side) for Dharampani, 12000 12000 23.59 Dhanusha (3 km) 1.21 7 RoW for 33 kV line (2 m both side) for Mainapokhar 8000 8000 15.73 S/S (2 km) 0.81 8 Construction of distribution sub-station at Paraul, 6918.86 6918.86 0.00 Mahottari (1 Bigha) 0 9 Construction of distribution sub-station at Barthawa, 6918.86 6918.86 13.60 0.70 Sarlahi (1 Bigha) 10 Construction of switching substations at Mirmi (6 3052.44 3052.44 0.00 ropani) 0 11 Construction of distribution sub-station at 3052.44 - 3052.44 6.00 Dhikurpokhari/Banskot, Kaski, (6 ropani) 0.31 12 Construction of distribution sub-station at Kusma, 3052.44 - 3052.44 6.00 Parbat, (6 ropani) 0.31 13 Construction of distribution sub-station at 6772.41 6918.86 0.00 Mainapokhar, Bardiya 0.00 14 Construction of switching substations at Swyambhu, 1526.16 1526.16 0.00 Kathmandu (6 ropani) 0.00 15 Construction of switching sub-station at Mulpani (1 508.74 - 508.74 1.00 0.05 ropani) Sub-Total 72558.9 25335.18 47370.2 93.11 4.78 All Total 436265 176521.92 259742.71 510.56 26.1 8 Area by Type of Acquisition a. Permanent Acquisition for tower, transmission sub-station and distribution sub-stations 46389.16 91.18 4.68 b. Restriction to Use except for Agriculture for Maintaining RoW (sq.m.) 213500 419.66 21.5 2 Total Estimated Area of Land to be Acquired (sq.m) 259889.16 510.85 26.2 0 Source: NEA, Technical Design and Census Survey Feb. 09 and census, Feb-Mar, 2009 Note A: One Bigha = 6918.86 sq.m., 1 ropani=508.74 sq.m, 1 ha = 9920.43 sq.m.

2 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Note B: The data presented in the table is based on preliminary census data which need to be updated during detail Design

3 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix A-2 Land Acquisition by Locations

S.N Acquisition Effect Effect on Land Effect on Total Affected Structures

Affected No. of Affected No. of Affected No. of APs HHs (No) APs HHs (No) APs HHs (No) A. Transmission Line /Sub-station Components 1 Middle Marsyangdi-Dumre-Damauli 207 1056 18 92 225 1148 and New Marsyangdi 132 kV Transmission Lines 2 Construction of Chapali Substation 74 385 2 11 76 396 Sub-total 281 1441 20 103 301 1544 B. Construction of New Distribution/Switching Sub-stations (11 No) 3 Distribution S/S at Jhapa 1 10 - - 1 10 4 Distribution S/S at Siraha 1 14 - - 1 14 5 Distribution S/S at Sarlahi 1 14 - - 1 14 6 Distribution S/S at Dhanusha 2 2 12 7 Distribution S/S at Kaski 10 60 - - 3 26 8 Distribution S/S at Kusma, Parbat 2 2 10 9 Distribution S/S at Bardiya 1 1 12 10 Switching S/S at Mulpani 2 12 - - 2 12 Kathmandu Sub-total 20 110 - - 20 110 All Total (A+B) 301 1551 20 103 314 1654 Source: Census Feb-APR, 2009

4 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix B-1

Key Socio-economic Characteristics of the Project Districts

B-1-1 Population and Households

Nine districts are located in the Southern Terai plain in the Indian bordering area, and the remaining six districts are located in hill. The overall population of the Project district is 7367441 comprising 3727683 (50.59%) male and 3639759 (49.41%) female. Kathmandu is the most densely populated district with a majority of households and Parbat is the most least populated district. The household distribution population of the Project districts and population by gender is given in following Table:

Table 1: Population and Household Size of the Project Districts

S.N. District Geographical Total Total Male Female Average HH Households Population Population Population Size 1 Jhapa Terai 125947 633042 314627 318415 5.03 2 Siraha Terai 98754 569880 292679 277201 5.77 3 Dhanusa Terai 117417 671364 349422 314942 5.72 4 Mahottari Terai 94229 553481 287905 265576 5.87 5 Sarlahi Terai 111076 635701 329182 306519 5.72 6 Kathamndu Hill 235387 1081845 576010 505835 4.6 7 Gorkha Hill 58923 288134 134407 153727 4.89 8 Tanahu Hill 62898 315237 146788 168449 5.01 9 Kaski Hill 85075 380527 184995 195532 4.47 10 Syanja Hill 64746 317320 143619 173701 4.9 11 Parbat Hill 32731 157825 72942 84884 4.9 12 Banke Terai 67269 385840 198231 187609 5.7 13 Bardiya Terai 59569 382649 192655 189994 6.42 14 Kalalai Terai 94430 616697 312311 304386 6.53 15 Kanchanpur Terai 60158 377899 191910 185989 6.28 Overall 1368609 7367441 3727683 3639759 Source: Central Bureau of Statistics, Statistical Year Book of Nepal, 2007

B-1-2 Economic Characteristics

About 49% population of the project districts is economically active or they are engaged in some income generation activities. The proportion of economically active population appears to the highest in and lowest in Dhanusha district. The proportion of economically active population ranges from 40% to 50% in ten districts and it is more than 50% in five districts (Parbat, Gorkha, Tanahu, Syanja, and Bardiya). The percentage of economically active age group population involved in income generation activities in the Project district is given following Table:

5 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Table 2: Economically Active Population of the Project Areas

S.N. Districts Economically Active Age Involved in Income Generation % Group All Nepal 16770295 8901400 53.07 1 Jhapa 493896 241870 48.97 2 Siraha 407981 190436 46.68 3 Dhanusha 479563 208184 43.41 4 Mahottari 395536 182190 46.06 5 Sarlahi 453228 215361 47.52 6 Kathmandu 892987 407749 45.66 7 Gorkha 215988 129454 59.94 8 Tanahu 235096 127049 54.04 9 Kaski 297070 140517 47.3 10 Synaja 234880 131490 55.98 11 Parbat 117245 72763 62.06 12 Banke 280624 124047 44.2 13 Bardiya 275985 139555 50.57 14 Kailali 441679 212133 48.03 15 Kanchanpur 272328 131143 48.16 Overall 5494086 2653941 49.9 Source: Central Bureau of Statistics, Statistical Year Book of Nepal, 2007

B-1-3 Poverty Status

As indicated in Nepal Human Development Indicators-2004, poverty status in seven project districts (Siraha, Dhanusha, Mahottari, Sarlahi, Tanahu, Gorkha, and Bardiya) is lower than the national level. Following Table provides a description on the development indicator including poverty index in the sub- project districts. Table 3: Development Indicators of the Project Area

S.N. Districts Geographical Region HDI (Rank) HPI (Rank) All-Nepal 0.471 39.6 1 Jhapa Terai 0.494 (18) 29.2 (4) 2 Siraha Terai 0.427 (51) 46.1 (50) 3 Dhanusa Terai 0.449 (43) 41.4 (31) 4 Mahottari Terai 0.407 (59) 50.6 (58) 5 Sarlahi Terai 0.408 (58) 49.8 (57) 6 Kathamndu Hill 0.652(1) 25.8 (3) 7 Tanahu Hill 0.524 (9) 42.0 (35) 8 Gorkha Hill 0.454 (40) 41.7(34) 9 Kaski Hill 0.593 (3) 24.9 (1) 10 Syanja Hill 0.535 (10) 35.3 (17) 11 Parbat Hill 0.504 (14) 35.5 (18) 12 Banke Terai 0.479 (29) 34.4 (14) 13 Bardiya Terai 0.429 (50) 43.2 (38) 14 Kalalai Terai 0.442(46) 39.5 (24) 15 Kanchanpur Terai 0.463 (39) 35.2 (15) Source: UNDP: Nepal Human Development Report 2004

6 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

B-1-4 Gender Status

The Gender Development Indicators (GDI) in the most of the Project district is lower than the national average. Of the 14 Project districts, Gender Development Indicators (GDI) in eight districts is less than the national average. Table 4 provides the GDI rank of the project districts

Table 4: Gender Development Indicators of the Project Districts

Districts GDI (Rank) S.N. All-Nepal 0452 1 Jhapa 0.482 (17) 2 Siraha 0.388 (55) 3 Dhanusa 0.416 (46) 4 Mahottari 0.368 (61) 5 Sarlahi 0.377 (59) 6 Kathamndu 0.635 (1) 7 Tanahu 0.516 (8) 8 Gorkha 0.445 (38) 9 Kaski 0.578 (3) 10 Parbat 0.492 (15) 11 Syanja 0.518 (7) 12 Banke 0.463 (30) 13 Bardiya 0.411 (48) 14 Kalalai 0.428 (41) 15 Kanchanpur 0.442 (39) Source: UNDP: Nepal Human Development Report 2004

7 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix B-2 Table 3: Locations of Investment Components

S.N Districts Municipality/VDC Ward No. Village/Name of Place A. Transmission Line /Sub-station Components 1. Middle Marsyangdi-Dumre-Damauli and New Marsyangdi 132 kV Transmission Lines 1. Gorkha Chyangli 8 Majhgaun, Nayagaun, Purnepipal, Kumalgaun 2. Tanahu' Bhanu 5, 8 Nayan Basti, Giran, NEANEAe, Thantitar/Tulitar, Sajbote, Baluwa, Bhansar, Dimrebas Ghasikuwa 1,2,3,4,6,7,8 Bhedatar, Archale, Deurali, Kamalbari, Khanigaura, Chirkini, Paling, Sehara, Kurlung, Chhabise, Ramthumki, Raikar, Kathare, Tatopani, Ghartigaun, Simletar, Nahala, Vardan, Thanigaira, Boodar,Dolekhet Barbhanjyang 1,9 Nagnagini, Thamdanda, Maidandanda Byas Municipality 1,3, 5,6,11 Sewar, Bagbhyanjyang, Tatopani, Chyuri, Ranigaun, Nibar, Ratmata, Polyang, Dihigaun, Bedvyas Tole, Samidanda, Darai Tole, Birta Tole, School Tole, Nibuwa Gahira, Talghare Aanbu Khairini 3 Anbu Khairini, Raudikhola, Markichowck, Eklephant , Patani 2. Middle Marsyangdi-Marsyangdi 132 kV Second Circuit Stringing (44 km) 3 Lamjung Barter, Bhoteodhar, - - Sundarbazar, and Trekughar 4. Gorkha Chyangli, palungtar, Deurali, - - Manakamana 5. Tanahu Aanbu khairini, Chock - - Chisapani, , Bandipur, and Bhanu 3. Butwal-Kohalpur–132 kV Second Circuit Transmission Line Construction 6. Banke Kohalpur, Mahadevpur Khas - Kohalpur , Sumshergunj, Upri, Kusum, Kusma Jidigaun, Mankhola 7. Dang Amiliya, Satbairiya, - Chanauta, Basantapur, Gorusinge, Jayanagar, Gangai, Banskatti, Chapargaun, 8. Kapilbastu Shivapur - Chanauta, Basantapur, Gorusinge, Jayanagar, Gangai, Banskatti 9. Rupandehi Butwal Municipality, Pipra - Tamnagar, Pipra ,Gajedi, Jogikuti, 4. Construction of Chapali Sub-station 10. Kathmandu Chapali VDC 8 Bhangal 4.1 Underground Cabling from Chabahil-Lainchaur 11. Kathmandu Kathmandu Chabahil, Sukedhara, Dhumbarahi, Narayangopal Chock, Maharajgunj, Panipokhari, Lazimpat, lainchaur 5. Expansion of Matatirtha Sub-station 12. Kathmandu Matatirtha 4 Bauthali B. Construction of New Distribution/Swithing Sub-stations (11 No.s) 13 Jhapa Baniyani sub-station 2 Lahure Chock, Dhukdhuki 14 Siraha Mirchaya sub-station - Mirchya VDC 3, Rampur Brta -4 15 Dhanusa Dhanush sub-station 1 Dhanushadham 16. Mahottari Paraul sub-station 2,8,4,5 Balwa 17. Sarlahi Barathahawa sub-station 7,8 Barthwa 18. Kathmandu Mulpani S/sub-station 5 Thapa Gaun 19. Kathmandu Swyambhu S/sub-station - Paduka Sthan 20 Synaja Mirmi S/ub-station 1 Mirmi 21. Kaski Dhikurpokhari sub-station 6 Banskot 22 Parbat Kusma sub-station 9,7 Sivalaya VDC, Kusma 23. Bardiya Mainapokhar sub-station 1 Mirmi Source: NEA, Technical Design

8 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix B-3

Proposed Locations for the Distribution Sub-stations/ Switching Centers

S.N Districts Location 1 or Location 2 or Location 3 1. Jhapa Private cultivating land area located at Baniyani VDC, Ward No. 2, Lahurechock (south to Kunzibari), X X about 1 km ahead to Banyan Bazaar along the Baniyani road. 2. Siraha Private land located at Ram Birta Private land located at Mirchiya VDC VDC Ward No. 3, along the highway, Ward No. 6, along the highway, about 1 km west from the Jiba bridge about 2 km East (north to squatters X (South to mango orchid) residence) from the Jiba bridge 3. Dhanusa[a] Government land (District Forest Office) at VDC Ward X X No. 1

(Land acquisition may not require) 4. Mahottari Government land having Hazma Government land having Private land owned by Pokhari at Balwa VDC, Ward No. 2 Shivamandir Pokhari and Cremating Ram Paswan located at yard at Balwa VDC, Ward No. 8 Paraul VDC, Ward No.4, (Land acquisition May not require) along -Paraul road. 5. Sarlahi Private land along the road to Private land near to dairy , long the Private land near to dairy, Hazariya from Bazarbank Chock Manuswara road from Barthwa long the Manuswara road (west to BIP secondary school, (approx 1 km) from Barthwa (approx 1 Barthwa VDC, ward No. 7 (East side of the Road) km) (West side of the Road) 6. Kathmandu NEA land, X X (Land acquisition May not require) 7. Kathmandu Private land near to the existing 33 Private land near to the existing 33 kv ring main, located in between kv ring main , located in the Ward No. 2 and 4 of Mulpani bordering area of Mulpani and X Gothatar. 8. Synaja NEA compound used for staff Government land north side to Private land near between quarter during Kaligandaki project- existing NEA/Kaligandaki Office the NEA/ Kaligandaki known as Italy camp, Krishna Krishna Gandaki VDC-1, Mirmi office compound and Gandaki VDC-1, Mirmi , hospital, Krishna Gandaki VDC-1, Mirmi (Land acquisition May not require) 9. Kaski Private land (having Modi tower) Private land in Baskot of Hemja located at the turning of Lewade on VDC-6. The location is along the way to Dhikurpokhar VDC- 2. The highway and north side of X land is in hill. Ghattekhola 10. Parbat Shivalaya VDC Ward No.9 = Two Shivalaya VDC Ward No.7 = Three X Private Plots Private Plots 11. Bardiya Government (VDC) land located at Private land along the Nepalgunj- Private land along the north side of Mainapokhar bazaar Gulariya highway near Bholagauda Nepalgunj-Gulariya (approx q km) , Bazaar of Sorahawa VDC ward no. 9 highway between Simara Chock to Bholagauda (Land acquisition May not require) Bazaar of Sorahawa VDC – 7 Source: NEA, Technical Design and Census Survey Feb. 09 –Apr. 2009 [a]During the site verification by TA team only one site (government land) was shown by NEA Officials at Dhanushadham. Later NEA suggested alternative area at Dharampani but the location yet to be identified by NEA.

9 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix C-1 Key Socio-economic Characteristics of the Affected Households

C-1-1 Households by Family Types

Of the total affected household interviewed 147 (about 84%) households are headed by male and about 30.46% affected household have joint family system followed by 68.87% nuclear, and 0.66% Single family. The proportion of Ethnic/Indigenous and Dalits (Minor Caste) groups seems to be higher (66, 86%) of out of the total project affected households. However, the extent of impact to such groups appears to be negligible as only 67406 (132.50 ropani) of land likely to be permanently acquired for the construction work. Moreover, the Indigenous/Ethnic people in the sub-project area are assimilated with the main social stream sharing common social and cultural norms and values as well as language and benefiting from the similar economic opportunities. Consultation with some of the indigenous/ethnic people in the study area has shown that are also found involved in different occupation and job as the advantage caste groups (e.g. police, army, civil servant, owners of boarding schools, business etc). Table 1 provides distribution of households by family types.

Table 1: Distribution of Affected Households by Family Type

Gender Gorkha Tanahu Total S.N. Descriptions No. % No. % No. % 1 Male Headed Households 147 84.00 7 87.50 154 84.15 2 Male Headed Households 28 16.00 1 12.50 29 15.85 Total Households 175 100 8 100 183 Family Types 1 Joint Family 46 30.46 70 40 116 35.58 2 Nuclear Family 104 68.87 104 59.43 208 63.80 3 Single Family 1 0.66 1 0.57 2 0.61 Total Households 151 100 175 326 100.00 Caste and Ethnicity 1 Brahmin, Cherries, Shah, 58 33.14 0 0 58 31.69 Thakuri (Advantage Caste)

2 Ethnic/Indigenous 88 50.29 7 87.5 95 51.91 3 Dalits (Minor Caste) 29 16.57 1 12.5 30 16.39 Total Households 175 100 8 100 183 100.00 Census Survey Feb. 09 –Apr. 2009

C-1-2 Population and Age Groups

The total population of the household is 960 (522 male and 467 female). Of the total population about 72.29% are of economically active age group (11-60 years). It is to be noted that in Nepal, population aged 11-60 is considered as economically active age groups. Table 2 provides summary of the population of sampled household by gender and age groups.

10 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Table 2: Population and Age Groups of the Affected Households

Population by Gender Tanahu Gorkha Total S.N Description No. % No. % No. % 1 Male Population 493 52.56 29 56.86 522 52.78 2 Female Population 445 47.44 22 43.14 467 47.22 Total 938 100.00 51 100 989 100.00 Population by Age Groups 1 0-5 Years 88 9.38 3 13.64 91 9.48 2 6-10 Years 83 8.85 1 4.55 84 8.75 3 11-60 Years (economically 679 72.39 15 68.18 694 72.29 active age group)

4 Above 60 Years 88 9.38 3 13.64 91 9.48 Total 938 100.00 22 100.00 960 100.00 Source: Socio-economic Survey, Feb-March 2009

C-1-3 Literacy and Education

About 23.5% population of the affected households are illiterate (nether can read or write) and the rest 76.5 % is literate. Among the literate population about 12.08% populations is just literate, and rest of the population have been found attended different level of educational degree.

Table 3: Literacy and Educational Status of the Affected Households

S.N. Description Both (Tanahu & Gorkha+ Male+ Female) No. % Literacy Status of Young and Adult Population 1 Cannot Read and Write 202 23.5 2 Can Read and Write 659 76.5 Total Young/Adult Population 861 100 Educational Status by Grade 1 Just Literate (read&write) 80 12.08 2 Class 1-5 pass 217 32.8 3 Class 6-7 pass 126 19.0 4 Class 8-SLC Pass 172 26.0 5 Intermediate (+12) 45 6.8 6 Graduated 17 2.6 7 Post graduated 5 0.8 Total Literate Population 662 100.0 Source: Socio-economic Survey, Feb-March 2009

C-1-4. Land Ownership

All of the interviewed households likely to be affected by the project have been found owning land. Among them, about 28.56% households have one ha to 1.25 ha of land, 28.57-affected household owns 0.5 to 1 ha. The remaining 42.86% households own up-to 0.5 ha of land. Average land holding size of the affected households is given in Table 4.

11 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Table 4: Land Ownership of the Affected Households

S.N. Holding by Land Size in Range (ha) No of HHs %

1 Up-to 0.5 ha 75 42.86 2 0.5- 1 ha 50 28.57 3 1- 1.5 ha 29 16.57 4 1.5-2 ha 13 7.43 5. More than 2 Ha 8 4.57 Total 175 100.00 Source: Socio-economic Survey and Census, Feb-March 2009

C-1-5 Economically Active Age Groups and Main Occupation

Of the total 960 population of the affected households, about 47% (709) population falls under the economically active age groups. Among them about 66% are economically active population. Cultivation is widely practiced by the affected households. Paddy, pulses, fruits and vegetables are the main products agricultural products. Besides, fruits and vegetables are also grown. The economically active age group populations are also engaged in other occupation (wage labor- 8.53%, business - 6.18%, cottage industry- 0.64, and service – 29.85% including private job and overseas employment. Table 5 provides classification of economically active age-group population by type of occupation and proportion of involvement in different occupation. Table 5: Economically Active Age Groups and Major Occupation of Affected Households

S.N Descriptions Male Female Total No. % No. % No. % Economically Active Age Group Population 372 52.47 337 47.53 709 100 Involvement in Income Generation Activities 1 Agriculture 62 24.80 195 89.041 257 54.80 2 Wage Labor 33 13.20 7 3.196 40 8.53 3 Business 22 8.80 7 3.196 29 6.18 4 Cottage Industry 3 1.20 0 0.000 3 0.64 5 Service (including private and overseas 130 52.00 10 4.566 140 29.85 employment) Total 250 100.00 219 100.00 469 100.00 HHs Involved in Income Generation 35.26 30.89 66.15 Source: Socio-economic Survey, Feb-March 2009 [a] Some household have more than one occupation (e.g. agriculture as well business etc.)

C-1-6 Household Income

The average cash income of the affected households is NRs. 141,103, which is higher than that of national average (NRs. 8,011).16 As the data reveals, agriculture, remittance and other sources of income (e.g. remittance, land transaction commission, operating rental vehicle, selling of fruits and vegetables) are the main sources of household income. Table 6 provides breakdown of the average household income of the affected households based on last 12 months income.

16 Nepal Living Standard Survey, Vol. II, Central Bureau of Statistics, Government of Nepal

12 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Table 6: Average Annual Income of the Affected Households from Different Sources

S.N. Sources of Income No. of HHs having Average Annual Income % Income (NRs) 1 Selling of agricultural products 159 28,220 20.00 2 Selling of livestock 72 4,819 3.42 3 Selling of livestock products 29 3,805 2.70 Selling of Fish 2 328 2.32 5 Other business 25 15,754 11 6 Agricultural Labor 5 1,071 0.76 7 Local casual labor 42 11,442 8.11 8 Remittance 56 32,706 23.18 9 Renting Bull stock or Breeding 2 1,106 7.84 Services 10 Selling of firewood - - 0.00 11 Local skill (tailoring, Panditayain or 1 148 0.10 performing rituals ) etc 12 Loan received 11 7,486 5.31 13 Seasonal migration 3 399 0.28 14 Other 72 33,819 23.97 Overall 173 141,103 100 Source: Socio-economic Survey, Feb-March 2009

C-1-7 Poverty Status

In Nepal, poverty is defined in absolute term based on the requirement of minimum subsistence level rather than per capita income. CBS has calculated National Poverty Line (NPL) to be NRs. 7695.70 per person per year based on the Basic Minimum Need (BMN) required for the minimum subsistence of an individual As revealed by the socio-economic data of the total affected households, only 2 (2.28%) household have been identified as Below Poverty Level (BPL) households with per capita income, less than NRs. 7695.70 per person per year (Table 7). The lower percentage of BPL households is due to availability of better economic opportunities and remittance in the project area. Table 7: Below Poverty Line Affected Households

S.N. Average Income (NRs) No. of HHs % 1 Below 7,695.70 4 2.28 2 7,695.70 – 15,000 53 30.28 3 15,001 - 30,000 64 36.57 4 30001 – 60000 44 25.14 5 60,001 – and above 12 6.86 Total 175 100.00 Source: Socio-economic Survey, Feb-March 2009

Migration to India, overseas, and other parts of country - mostly for job is on the major reasons of better household income in the project location. As the data shows, family members from about 84% household have their family members migrated mostly for employment and education.

Table 8: Migration Status of the Family Members of Affected Households

S.N. Description Male Female Total No. % No. % No. % 1 Total HH Population 522 52.78 467 47.22 989 100 2 HHs having Migrated 391 47.05 440 52.95 831 84.02 Members Source: Socio-economic Survey, Feb-March 2009

13 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

C-1-8 Gender Role on Decision Making

Women’s role on decision making on the household matters have been found almost confined in the matters related to household chores and limited on property ownership, property selling, cash keeping and transaction. The census data shows that women are solely responsible for deciding on Household Chores whereas it is only about 10.7 percent on the matters related to owning property and 8.7%, on cash transaction. Table 9 provides gender role on decision making on different household matters. Table: 9: Gender Role on Decision Making

S.N. Activities Male Female Both No. % No. % No. % 1 Farming 3 1.4 54 38.0 115 60.6 2 Household Chores 2 1.3 170 96.0 9 2.7 3 House/Child/Old Care 3 3.5 97 67.4 76 29.2 4 Children Education 22 9.1 58 39.9 88 51.1 5 Livestock Care 10 0.0 69 51.9 93 48.2 6 Participation in Community Dev. 73 59.2 47 17.0 58 23.8 Activities 7 Social Work 69 54.4 44 14.8 68 30.9 8 Income Generation 138 72.8 8 4.1 31 23.1 9 Ownership of Property 125 77.2 32 10.7 20 12.1 10 Sale of Property 114 53.3 22 6.7 44 40.0 11 Keeping Cash 61 37.3 82 25.3 38 37.3

12 Cash Transaction 81 41.3 21 8.7 78 50.0 Overall 701 34.7 704 31.4 718 33.8 Source: Socio-economic Survey, Feb-March 2009

C-1-9 Use of Electricity

All hundred percent project affected households are connected to electricity. Among them about 50% households are using electricity also for entertainment followed by education and communication (21.7%), fan cooler (18%), cloth pressing (18%) and others (Table 10). Here it may be interesting to note that use of electricity for cooking have been reported only by 1.7% households for which job women are solely responsible. As reported, high electricity tariff, and inefficient services are some of main reasons for not using electricity for cooking. Supply of improved and reliable electricity in a way affordable to the community may significantly contribute on reducing women’s drudgery especially associated with cookery on smoky environment.

Table 10: Use of Electricity for Different Purposes in Affected Households

S.N. Purpose of Use No. % Interviewed Households 175 100 1 Lighting 11 6.3 2 Cooking 3 1.7 4 Cloth Pressing 25 14.3 5 Fan /Cooler 33 18.9 6 Income Generation Activities 3 1.7 7 Entertainment 88 50.3 8 Education/Communication 38 21.7 9 Irrigation 1 0.6 10 Not Applicable 28 16.0 Source: Socio-economic Survey, Feb-March 2009

14 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix C-2

Breakdown of the Project Impact by Investment Components and Locations . S.N Investment Components Effect on Land Effect on Residential Total /Commercial /Structure Affected No. of Affected No. of Affected No. of APs HHs (No) APs HHs (No) APs HHs (No) A. Transmission Line /Sub-station Components 1 Middle Marsyangdi-Dumre- 207 1056 18 92 225 1148 Damauli and New Marsyangdi 132 kV Transmission Lines 2 Construction of Chapali 74 385 2 11 76 396 Substation Sub-total 281 1441 20 103 301 1544 B. Construction of New Distribution/Switching Sub-stations (11 no) 3 Distribution S/S at Jhapa 1 10 - - 1 10 4 Distribution S/S at Siraha 1 14 - - 1 14 5 Distribution S/S at Sarlahi 1 14 - - 1 14 6 Distribution S/S at Dhanusha 2 2 7 Distribution S/S at Kaski 3 60 - - 3 60 8 Distribution S/S at Kusma, 2 2 Parbat 9 Distribution S/S at Bardiya 1 1 10 Switching S/S at Mulpani 2 12 - - 2 12 Kathmandu Sub-total 13 110 - - 13 110 All Total (A+B) 301 1551 20 103 314 1654 Note: The data presented in the table is based on preliminary census data and estimation and will be updated during detail Design.

15 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix C-3

Details on Land Ownership of the Affected Households and Proportion of Loss on Total Land Ownership

Nepal Electricity Connectivity and Energy Efficiency Project I Nepal Electricity Authority / ADB TA 7176 Inventory of Affected Parcels Interviewed with Owners

Dumre – Damauli- Marsyangdi 132 kV New T/L Construction

Total Total Affected % of Loss Land Land in Area in sq.m in Total Owned sq.m Ownership (Sq. Total Feet) Affecte Land d Area Affected S.N Former Plot Owners Remark Owned Parcel Area Area (Ropan Area . Name Recent Plot Owner’s Name s (Ropani) No. (Ropani) (sq.ft) i) (sq.ft.)

AP 0-1: Vyas Municipality, Bagbhyangyang

Bagbhanjyang Community Forest

AP1-2: Vyas Municipality, Bagbhyangyang

Bagbhanjyang and Birta Community Forest

AP 2-3: Bhagbhanjyang, Vyas Municipality 11, 0-4-0- 0-3-0- 1 Mr. Purna Bahadur Gurung 0-4-0-0 1369 127.18 1256 0 1369 0 1026.75 95.37 74.99 0-8-1- 0-4-3- 2 Mr. Gun Bahadur Darai 0-8-1-1 2852.95 265.04 1257 1 2852.95 0 1625.68 151.03 56.98 0-5-1- 0-2-2- 3 Mr. Bhuvan Darai 6-6-0-0 34909.5 3243.09 1038 1 1826.2 0 855.62 79.49 2.45 23302.3 4-1-0- 0-9-1- One 4 Mr. Khun Bahadur Darai 4-4-0-1 9 2164.79 669 1 22275.64 2 2069.4 192.25 8.88 househo 0-3-0- 0-3-0- lds Mr. Chet Bahadur Darai 661 0 1026.75 0 1026.75 95.39 4.41 Sub-total 5800.10 613.52 AP 3-4: Vyas 11, Bagbhanjyang,School Tole, Birta, Nibuwa Gahira, Vyas Tole 35481.6 3-8-3- 1-3-2- 1 Mr.Chitra Bahadur Khadka 6-7-2-2 5 3296.25 575 1 19452.07 0 6673.87 620.003 18.81 1-4-1- 0-2-0- 2 Mr. Bam Bahadur Adhikari 1-4-1-0 6930.56 643.85 578 0 6930.56 0 684.5 63.590 9.88

16 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

24385.3 4-7-1- 1-7-3- 3 Ms. Uma Devi Thapa 4-7-1-0 1 2265.40 579 0 24385.31 1 8157.82 757.861 33.45 0-4-0- 0-1-0- 4 Ms. Laxmi Pradhan 1-1-0-0 5818.25 540.52 1422 0 1369 0 342.25 31.795 5.88 16342.4 2-15- 1-5-1- 5 Ms. Lalu Maya Pariyar 2-15-3-0 3 1518.21 1423 3-0 16342.43 2 7331.59 681.105 44.86 37305.2 2-4-3- 0-6-0- One 6 Ms. Nanu Maya Giri 6-13-0-0 5 3465.66 587 0 12577.68 0 2053.5 190.770 5.50 househo 4-8-1- 0-6-1- lds Ms. Nanu Maya Giri 788 0 24727.56 0 2139.06 198.719 5.73 0-2-0- 0-2-0- 7 Mr. Aita Singh Nepali 1-0-0-0 5476 508.72 1084 0 684.5 0 684.5 63.590 1.16 15401.2 0-9-1- 0-8-2- One 8 Mr Sul Bahadur Gurung 2-13-0-0 5 1430.78 1404 2 3224.59 2 2967.9 275.718 19.27 househo 0-3-0- 0-0-2- lds Mr Sul Bahadur Gurung 1408 0 1026.75 0 171.12 15.897 1.11 0-4-0- 0-3-2- 9 Ms. Madhu Maya Rokka 0-4-0-0 1369 127.18 1402 0 1369 0 1197.87 111.282 87.50 0-4-0- 0-1-3- 10 Ms. Juna Gurung 0-8-0-0 2738 254.36 1407 0 1369 0 598.93 55.641 21.87 31859.6 3-4-3- 1-2-3- 11 Mr. Krishna Bahadur B.K. 5-13-0-1 4 2959.76 591 1 18083.07 3 6505.35 604.347 20.42 2-5-1- 0-12- Ms.Mina B.K. 590 0 12748.81 1-3 4280.73 397.680 13.44 Have effect on plots but the AP do not know the plot no. and area of affected plat. Interviewed 0-2-2- based on T/L alignment 12 Ms. Shova Pariyar 0-2-2-0 855.62 79.49 1400 0 7016.12 Sub-total 4067.997 AP 4-5: Vyas Municipality-5, Dihi Gaun, Vyas Tole, Talghare, Shanti Nagar 11-10-3- 63944.5 8-6-0- 0-4-1- 1 Mr. Surya Bahadur Darai 1 7 59404.51 834 1 45890.89 0 1454.56 135.13 0.23 17200.6 2-7-2- 1-8-1- 2 Mr. Gore Darai 3-2-0-3 7 15979.42 846 3 13607.04 0 8299.56 771.03 4.83 Ms Kamini 3-0-0- 2-0-0- 3 Maya/Bam Bahadur Mr. Bhoj Bahadur Darai 3-0-0-0 16428 15261.61 783 0 16428 0 648.5 60.25 0.39 88645.3 0-10- 0-0-1- 4 Laxmi Prasad Neupanie 16-2-3-3 5 82351.53 805 0-0 3422.5 0 85.56 7.95 0.01 Mr. Harka Bahadur 33882.7 2-3-0- 1-9-3- One 5 Darai Mr. Bhim Bahadur Darai 6-3-0-0 5 31477.07 17 3 12066.92 0 8812.93 818.72 2.60 househol 3-15- 1-14- ds Mr. Bhim Bahadur Darai 912 3-2 21877.21 1-0 10353 961.79 3.06 107068. 0-15- 0-1-1- 6 Mr. Chitra Bahadur Darai 19-8-3-1 07 99466.24 16 2-0 5304.87 0 427.81 39.74 0.04 Mr.Bhim Bahadur 111717. 103785.8 5-5-1- 1-14- 7 Darai Ms. Dhani Maya Darai 20-6-1-2 84 7 466 0 29176.81 1-0 10353.06 961.80 0.93

Have effect on plots but the AP do not know the plot no. and area of affected plat. 8 Mr. Vishnu Bahadur B.K. 1-3-2-0 6673.87 6200.03 Interviewed based on T/L alignment 15572.3 9 Mr. Singha Bahadur Darai 2-13-2-0 7 14466.73

17 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

33-15-1- 185927. 172726.4 10 Mr. Padam Bahadur Darai 0 31 7

11 Ms.Rita Gurung 0-8-0-0 2738 2543.60 40043.2 12 Ms Uma Baruwal 7-5-0-0 5 37200.18 53677.0 Have effect on plots but the AP do not know the plot no. and area of affected plat. 13 Mr. Yam Bahadur Darai 9-12-3-1 7 49866.00 Interviewed based on T/L alignment 14 Mr. Hari Kumar Shrestha 0-8-0-0 2738 2543.60

Mr.Khadga Bahadur Thapa 63120.7

15 Magar 11-8-1-3 3 58639.16

48773.2

16 Mr.Bhoj Bahadur Darai 8-14-1-3 3 45310.33

88742.6 17 Mr. Arjun Ale 0-4-3-3 8 82441.95 18 Ms Nari Maya Darai 4-15-2-1 27238.2 25304.34 6

Sub-total 12.08

AP 5-6: Vyas Municipality 5, Sewer, Ratmata, Dihi Gaun,Rani Gaun

Ms. Him Kumari 101744.0 0-13-0- One 1 Koirala Mr. Baburam Koirala 20-0-0-0 109520 8 151 7-6-2-2 40615.4 0 4449.25 40456.58 39.76 househol Mr. Rudra Prasad 2-13-0- 15401.2 ds Koirala Mr. Baburam Koirala 0.00 499 8-0-0-0 43808 0 5 1430.776 1.40 Mr. Devendra Raj 90182.8 4-11-2- 25839.8 2 Hamal Mr. Amar Bahadur Kunwar 16-7-2-0 7 83779.89 159 0 7 1-4-1-3 7018.73 652.040 0.77 One 13091.0 househol Mr.Yem Bahadur Mr. Amar Bahadur Kunwar 0.00 390 2-6-1-0 6 0-5-0-0 1711.25 158.975 0.19 ds 19652.5 1-10-1- Mr. Amar Bahadur Kunwar 0.00 401 3-9-1-2 9 2 9042.84 840.080 1.003 Mr. Sam Bahadur 13-11-3- 168330. 156379.3 22502.9 3 Darai Mr.Jas Bahadur Darai 1 82 3 579 4-1-3-0 3 1-9-2-0 8728.37 810.866 0.519 Mr. Ishwari Prasad 279796.2 0-11-0- 4 Paudel Ms Surya Maya Paudel 55-0-0-0 301180 2 614 1-9-2-2 8786.15 0 3764.75 349.745 0.125 One Mr. Rika Ram 11465.3 househol Gharti Ms Surya Maya Paudel 0.00 237 2-1-2-0 7 0-8-0-0 2738 254.360 0.091 ds Mr. Rika Ram 3-12-1- 20708.7 Gharti Ms Surya Maya Paudel 0.00 235 3 3 2-0-0-0 10952 1017.441 0.364 Mr. Amrit Bahadur 66455.2 0-13-3- 5 Adhikari Ms. Maiya Devi Adhikari 12-2-0-2 8 61736.96 613 2-6-2-2 13235.4 2 4764.71 442.642 0.717 Mr.Khagu Prasad 57899.0 One 6 Paudel Mr.Kedar Nath Paudel 10-9-0-2 3 53788.20 260 1-9-3-0 8812.93 0-6-1-0 2139.06 198.719 0.369 househol Mr. Tika Ram 1-11-1- ds Gharti Mr.Kedar Nath Paudel 0.00 261 0 9326.31 0-4-2-0 1540.12 143.077 #DIV/0! 83252.3 0-12-2- 7 Mr. Hari Dutta Paudel 15-3-1-0 1 77341.40 434 0 4278.12 0-2-1-0 770.06 71.539 0.092 55273.3 1-12-3- 8 Mr.Durga Dutta Ms.Chandra Maya Paudel 10-1-2-0 7 51348.96 435 3 9927.85 0-7-1-2 2540.09 235.974 0.460 Mr.Rishi Ram One 178052.1 28722.2 9 Paudel Ms. Govinda Raj Paudel househol 35-0-0-0 191660 4 258 5-3-3-2 1 1-7-0-0 7871.75 731.286 0.411

18 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Mr.Rishi Ram ds 51139.5 Paudel Ms. Govinda Raj Paudel 0.00 421 9-5-1-2 9 0-5-0-0 1711.25 158.975 0.089

10 Ms. Devika Mishra 15-0-0-0 82140 76308.06

50396.3 11 Mr. Chhabi Lal Darai 9-3-1-0 1 46818.17 34339.9 12 Mr.Gan Bahadur Darai 6-4-1-1 5 31901.81 121728. 113085.9 Have effect on plots but the AP do not know the plot no. and area of affected plat. 13 Mr.Krishna Bahadur Darai 22-3-2-2 65 2 Interviewed based on T/L alignment 29492.2 14 Mr.Chitra Bahadur Darai 5-6-0-2 8 27398.33 24329.1 15 Mr. Jun Bahadur Darai 4-7-0-1 4 22601.77 17141.8 16 Mr.Ghan Bahadur Darai 3-2-0-1 9 15924.82 Sub-total

AP 6-7: Vyas Municipality 3, Polyang, Kokle, Chyuri, Samidanda, Darai Tole

38930.9 36166.8 5-1-3- 0-2-0- 1 Mr.Janga Bahadur Darai 7-1-3-0 3 3 7 0 27978.93 0 684.5 63.59 0.18 199561. 185392. 23-1- 126549.5 2-0-0- 2 Mr. Khanga Bahadur Darai 36-7-0-1 14 30 14 2-3 4 0 10952 1017.44 0.55 28-12-3- 157750. 146550. 0-8-1- 0-8-1- 3 Mr.Bal Bahadur Darai 2 46 18 115 3 2911.73 3 2911.73 270.50 0.18 16-13-0- 92065.2 85528.6 2-5-2- 0-13- 4 Mr. Dhan Bahadur Darai 0 5 2 248 1 12863.76 0-3 4537.42 421.53 0.49 40697.6 2-7-3- 0-4-3- 5 Mr.Som Bahadur Darai 8-0-0-0 43808 3 119 2 13663.21 0 1625.68 151.03 0.37 45784.8 0-12- 0-0-1- 6 Mr.Jeet Bahadur Darai 9-0-0-0 49284 4 275 0-3 4195.17 0 85.65 7.96 0.02 13-12-3- 75639.8 70269.4 0-12- 0-2-2- 7 Mr.Bir Bahadur Darai 3 5 2 274 0-3 4195.17 2 914.4 84.95 0.12 81395.2 0-12- 0-2-0- 8 Mr. Lila Bahadur Darai 16-0-0-0 87616 6 273 0-3 4195.17 0 684.5 63.59 0.08 49029.9 45548.8 1-4-1- 0-0-2- 9 Mr. Tul Bahadur Darai 8-15-0-3 2 0 281 0 6930.56 0 171.12 15.90 0.03 0-12- 0-0-1- Mr. Tul Bahadur Darai 0.00 272 0-3 4195.17 0 86.56 8.04 0.02 10 Mr.Nara Bahadur B.K 9-10-2-0 52877.6 49123.3 2 1

Have effect on plots but the AP do not know the plot no. and area of affected plat. Interviewed based on T/L alignment

19139.2 17780.3 11 Mr. Pratap Tamang 3-7-3-2 1 3 81395.2 12 Mr.Man Bahadur Tamang 16-0-0-0 87616 6

19 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

112372. 104394. 13 Mr. Indra Bahadur Darai 20-8-1-1 95 47 46829.4 43504.5 14 Mr. Krishna Bahadur Darai 8-11-3-0 3 4 36107.3 33543.7 15 Mr. Lal Bahadur B.K. 6-9-2-0 7 5 Ms. Ram Kumari 101744. 16 KhadaMagar 20-2-0-0 109520 08 50872.0 17 Mr. Akal Bahadur Tamang 10-0-0-0 54760 4

45784.8

18 Mr. Tirtha Raj Poudel 9-0-0-0 49284 4

22-10-2- 124153. 115338.

19 Mr.Man Bahadur Darai 3 79 87

12718.0 20 Mr.Som Bahadur B.K 2-8-0-0 13690 1 111918. Government Land “Ailani” 21 Mr.Lal Bahadur Tamang 22-0-0-0 120472 49 35610.4 22 Mr.Bir Bahadur Tamang 7-0-0-0 38332 3 15261.6 23 Mr.Tika Ram Tamang 3-0-0-0 16428 1 10174.4 24 Mr.Pancha Bahadur B.K 2-0-0-0 10952 1 81395.2 25 Mr.Ram Bahadur Tamang 16-0-0-0 87616 6 76308.0 26 Mr.Bam Bahadur Tamang 15-0-0-0 82140 6 Mr.Chandra Bahadur 228924. 27 Tamang 45-0-0-0 246420 18 57070.1 53018.2 28 Mr. Ran Bahadur Darai 10-6-3-0 8 0 49398.9 45891.6 29 Mr. Man Bahadur Darai 9-0-1-1 5 2 38930.9 36166.8 30 Mr.Ganga Bahadur Tamang 7-1-3-0 3 3 Sub-total AP 7-8: Ghansi Kuwa 6, Tatopani, Sehara, Polyang, Vyas Municipality - 3, 6 Ms.Dambar Devi 31-10-1- 173322. 161016.9 9497.4 1 Kaini Mr. Murali Raj Kaini One 2 84 18 52 3-0-0-0 16428 1-11-3-0 3 882.31 0.55 Mr. Murali Raj Kaini househol 50 5-0-0-0 27380 0-1-2-0 513.37 47.69 0.03 ds 3080.2 Mr. Narayan Dutta Mr. Murali Raj Kaini 53 4-8-0-0 24642 0-9-0-0 5 286.16 0.18 148793. 138228.8 One 2 Dambar Dhoj Kaini Mr. Rudra Raj Kaini 27-2-3-0 18 64 80 5-13-0-0 31829.25 1-8-2-2 8443.9 784.44 0.57 househol 10155. ds Dambar Dhoj Kaini Mr. Rudra Raj Kaini 33 11-2-3-2 61235.96 1-13-2-2 15 943.41 0.68 Mr. Harka Bahadur 148996. 138417.5 11722. 3 Gurung Mr. Tul Bahadur Gurung 27-2-4-4 3 63 25 3-14-1-1 21334.45 2-2-1-0 06 1088.98 0.79 One 11-11-1- 64145.0 59590.78 4 Mr. Man Bahadur Damai househol 2 9 86 16 2-14-2-2 15973.4 0-12-2-2 4336.9 402.90 0.68

20 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

ds 4080.2 Mr. Man Bahadur Damai 19 8-12-3-0 48171.68 0-11-3-2 1 379.05 0.64 6835.925 2197.8 5 Mr. Bir Bahadur Darai 1-5-2-0 7358.37 73 90 1-5-2-0 7358.37 0-6-1-2 4 204.18 2.99 26707.82 6 Mr. Dhan Bahadur Darai 5-4-0-0 28749 1 91 1-5-2-0 7358.37 0-12-2-1 4336.9 402.90 1.51 One 3596.2 househol Mr. Dhan Bahadur Darai 111 1-8-1-3 8387.73 0-10-1-3 3 334.09 1.25 ds 2139.0 Mr. Dhan Bahadur Darai 122 2-10-2-2 14604.4 0-6-1-0 6 198.72 0.74 119549.2 2339.5 One 7 Mr. Ganesh Raj Adhikari 23-8-0-0 128686 94 123 5-5-3-2 29406.71 0-6-3-1 7 217.35 0.18 househol 1911.7 ds Mr. Ganesh Raj Adhikari 149 2-3-2-0 12149.87 0-5-2-1 6 177.60 0.15 115397. 107203.8 5647.1 8 Mr. Purna Bahadur Gurung 21-1-0-2 03 41 26 7-11-3-3 44331.6 1-0-2-0 2 524.62 0.49 24-14-0- 136303. 126626.1 9 Mr. Mr. Lal Bahadur Darai 3 67 09 91569.67 10 Mr.Shiva Lal Thami 18-0-0-0 98568 2 152616.1 11 Mr.Bhairab Raj Kaini 30-0-0-0 164280 2 28722.2 26682.93 12 Mr.Akeshari Bastola 5-3-3-2 1 31 41969.43 Have effect on plots but the AP do not know the plot no. and area of affected plat. 13 Mr. Krishna Raj Adhikari 8-4-0-0 45177 3 Interviewed based on T/L alignment

66133.65

14 Mr. Man Bahadur Dura 13-0-0-0 71188 2

Mr. Buddhi Bahadur 42096.7 39107.88

15 Parajuli 7-11-0-0 5 08 Mr.Chandra Bahadur 48257.2 44830.98 16 Parajuli 8-13-0-0 5 53 160343. 148959.5 17 Ms.Chheese Maya Khanal 29-2-3-2 96 39 Mr. Basanta Bahadur 110891. 103018.2 18 Parajuli 20-3-3-3 6 96 Sub-total AP: 8-9: Ghansikuwa -6, Tatopani

Government Land “Ailani” AP 9-10: Ghansikuwa -6, Tatopani

Any registered or unregistered plot owners could not be identified during the census. The District Land Measurement Office also do not have any record of land owners between AP 9-10 AP 10-11: Ghansikuwa 3,4,6, Paling, Chha Bise, Vardan, Kurlung, Kamalbari, Khanigaira, Kathhare, Deurali, Ghansikuwa-2, Ramthumki,Ghansikuwa 7, Raikar 4-7-3- 8328.9 1 Mr. Tul Bahadur Thapa 32-3-3-2 176574.21 164037.441 69 0 24556.43 1-8-1-1 5 773.76 0.47 Mr.Khanga Bahadur Mr. Purna Kanta/Jyoli 2-13- 2 Thapa Nagila 9-13-1-2 53848.2 50024.9778 70 3-0 15657.93 0-2-1-0 770.06 71.54 0.14 22-15-3- 3-2-3- 0-12-1- 4165.7 3 Mr. Padam Raj Panta 3 125950.6 117008.107 104 3 17457.35 2 8 387.00 0.33 Mr. Dil Bahadur 2-4-3- 2141.6 4 Rimal Mr. Hasta Bahadur Rimal 10-3-0-1 55816.14 51853.1941 112 3 12665.58 0-6-0-3 7 198.96 0.38

21 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

1-9-1- 2339.5 One 5 Mr. Krishna Prasad Pant 29-5-3-2 160830.71 149411.73 111 1 8671.2 0-6-3-1 7 217.35 0.15 househol 1-11- ds Mr. Krishna Prasad Pant 166 0-3 9328.92 0-2-3-1 970.57 90.17 0.06 6-4-3- 17855. 6 Devi Prasad Pant Mr. Rudra Nidihi Pant 32-0-0-0 175232 162790.528 109 3 34569.85 3-4-0-2 78 1658.80 1.02 4-12- 6732.6 Devi Prasad Pant Mr. Rudra Nidihi Pant One 123 2-1 26211.51 1-3-2-2 5 625.46 0.38 househol 0-7-1- Devi Prasad Pant Mr. Rudra Nidihi Pant ds 176 0 2482.31 0-0-2-0 171.12 15.90 0.01 Ms Chuna Kumari 21-15-3- 3-7-0- 7 Pant Mr.Chandra Kanta Pant 1 120415.82 111866.297 165 0 18823.75 0-2-1-2 828.84 77.00 0.07 Ms Chuna Kumari 1-4-1- 3310.1 Pant Mr.Chandra Kanta Pant 175 3 7018.73 0-9-2-2 5 307.51 0.27 0-9-1- 2224.6 One 8 Mr. Ravi Lal Pant Mr.Tej Prasad Pant 32-4-0-0 176601 164062.329 170 3 3253.98 0-6-2-0 2 206.67 0.13 househol 0-4-3- ds Mr. Ravi Lal Pant Mr.Tej Prasad Pant 171 0 1625.68 0-2-0-0 684.5 63.59 0.04 9-0-2- 12064. 9 Mr. Bal Singh Ale Ms. Bhoti Maya Ale 14-7-0-1 79089.14 73473.8111 72 3 49543.29 2-3-1-0 31 1120.77 1.53 5-8-0- 0-12-2- 4366.2 10 Mr.Dambar Bahadur Gharti 5-8-0-0 30118 27979.622 14 0 30118 3 9 405.63 1.45 11 Ms.Janak Kumari Naharki 5-0-0-0 27380 25436.02 12 Mr. Basanta Panta 40-0-0-0 219040 203488.16 Have effect on plots but the AP do not know the plot no. and area of affected Mr. Tara Nath Pant plat. Interviewed based on T/L alignment

13 Mr. Bharda Nidhi Pant 15-1-2-1 82682.76 76812.284 17-10-1- 14 Mr.Krishna Raj Kaini 0 127600.06 118540.456 AP 11-12: Ghansikuwa-7, Dolekhet 13350.3 1 Mr.Tika Nidhi Lohini Ms. Subhadra Lohani Misra 5-5-3-1 29377.32 27291.5303 3 2-6-3-3 5 1-4-1-2 6989.34 649.31 2.38 AP 12-13: Ghansikuwa 2, Kamalbari, Deurali 80201.4 0-12-2- 1 Mr. Balkoti Sarki Ms Krishna Kumari Sarki 17-0-0-0 93092 86482.47 1 14-10-1-1 5 3 4366.29 405.63 0.47 45548.6 1-13-0- 2 Mr. Babu Ram Kami 15-0-0-0 82140 76308.06 2 8-5-0-1 4 0 9925.25 922.06 1.21 30548.4 3 Mr. Jangal Paling Mr. Bam Bahadur Kami 9-0-0-0 49284 45784.84 3 5-9-0-3 2 1-9-1-0 8641.81 802.82 1.75 4 Mr. Ramji Lohani 16-0-0-0 87616 81395.26

Have effect on plots but the AP don’t know the plot no. and area of affected plat. Interviewed based on T/L alignment

AP 13, 14, 15, 16, 17: Community Forest and Government Land “Ailani”

22 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

AP 17-18: Ghansikuwa 1 &8, Archale, Chirkini, Mr. Katak Bahadur 49626. 1 Rawal Mr. Arjun Bahadur Rawal 25-6-0-0 138953.5 129087.802 5 9-1-0-0 25 2-3-3-0 12235.43 1136.67 0.88 Mr Krishna Bahadur 16776. 2 Sahani Mr. Durga Bahadur Sahani 10-8-0-0 57498 53415.64 15 3-1-0-0 25 0-1-3-1 628.32 58.37 0.11 Mr. Krishna Bahadur 16-12-2- 16770. 3 Sahani 3 91982.29 85451.55 16 3-1-0-0 25 1-5-0-2 7246.03 673.16 0.79 Mr. Katak Bahadur Raut (1 4 of 3 Plots) 16-0-0-0 87616 81395.26 Mr. Katak Bahadur Raut (2 of 3 Plots) Mr. Katak Bahadur Raut (3 Have effect on plots but the AP do not know the plot no. and area of affected of 3 Plots) plat. Interviewed based on T/L alignment

Ms. Chandra Kumari Raut

5 Mr. Dhan Bahadur Adhikari 64-5-2-1 352375.76 327357.08 AP 18-19: Ghansikuwa 1, Archale and Nahala & Barghanjyang , Basudev, Nidhiswara and Baghmare Community Forest AP 19-20: Bhanu VDC 5, Ghansikuwa 1, : Bhodatar, Bhansar, Nagnagini, Sajbote, Salbise Mr. Chandra 28037. 1 Bahadur Sarki Mr. Lure Sarki 7-3-3-2 39674.21 36857.34 23 5-1-3-2 71 0-8-3-1 3024.07 280.94 0.76 72559. 2-15-2- 2 Mr. Sansare Sarki Mr. Shyam Ser Sarki 13-3-3-2 72530.21 67380.57 20 13-3-3-3 6 0 16256.87 1510.26 2.24 Mr. Vishnu Prasad 3 Neupane 11-0-0-0 60236 55959.24 28 2-0-0-0 10952 0-0-1-0 85.56 7.95 0.01 4 Mr.Shyam Kaji Nepali 5-0-0-0 27380 25436.02 63 1-7-3-3 8216.6 0-2-2-0 855.62 79.49 0.31 5 Mr. Ramji Nepali 4-14-0-0 26695.5 24800.12 64 1-8-0-0 8214 0-3-2-2 1256.65 116.74 0.47 6 Mr. Hira Bahadur Nepali 9-11-0-0 53048.75 49282.29 20-15-2- 7 Mr.Nitya Nanda Neupane 3 114913.04 106754.21 8 Mr. Bhim Bahadur Nepali 3-0-0-0 16428 15261.61 9 Ms. Basundhari Pant 5-0-0-0 27380 25436.02 10 Mr.Sambhu Lal Shrestha 10-0-0-0 54760 50872.04

11 Mr. Som Bahadur Nepali 8-10-0-0 47230.5 43877.13 Sub-total AP 20- 21: Bhanu VDC 5, : Nayabasti, Giran, Bhansar, Thulitar, Dordore, Baluwa, Dimrebas, Bhanu VDC 8, Sajbote Mr.Chandra Bahadur 12-11-1- 16542. 1 Kumal 0 69562.31 64623.39 85 3-0-1-1 95 1-1-2-0 5989.37 556.41 0.86 2 Mr. Bisaya Kumal Mr. June Kumal 15-4-0-0 83509 77579.86 241 3-0-0-0 16428 0-4-1-0 1454.56 135.13 0.17 3 Mr. Aite Kumal Mr. Dil Bahadur Kumal 15-0-0-0 82140 76308.06 116 0-11-3-3 4109.6 0-3-2-0 1197.87 111.28 0.15 14291. 4 Mr. Janak Kumal Mr. Biba Maya Tamang 5-0-0-0 27383 25438.81 118 2-9-2-3 54 1-0-1-0 5561.56 516.67 2.03 16599. 5 Mr. Lok Bahaduur Mr. Gore Nepali 3-0-2-0 16599.12 15420.58 275 3-0-2-0 12 0-8-0-3 2826.17 262.55 1.70

23 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

16542. 6 Mr. Ram Bahadur Acharya 5-0-2-1 27580.51 25622.29 276 3-0-1-1 95 1-2-3-2 6475.96 601.62 2.35 11037. Mr. Ram Bahadur Acharya 273 2-0-1-0 56 0-1-2-0 513.37 47.69 0.19

Mr Sabmhu Adhikari/As 11037. 0-11-2- 7 Mr. Lek Bahadur Bahadur Lama 10-2-0-0 55444.5 51507.94 274 2-0-1-0 56 0 3935.87 365.64 0.71 12550. 8 Mr. Ram Prasad Pant 6-0-0-0 32856 30523.22 173 2-4-2-2 9 0-8-0-0 2738 254.36 0.83 19254. 9 Mr. Purab Kumal Ms Suni Maya Gurung 22-8-0-3 123298.17 114544.00 168 3-8-0-3 17 0-4-2-2 1598.9 148.54 0.13 37650. 10 Mr. Asare Kumal Ms. Reuli Kumal 14-4-1-1 78147.95 72599.45 199 6-13-3-3 1 0-2-1-0 770.06 71.54 0.10 39644. One 11 Mr. Juthe Kumal Ms. Biba Kumalni 26-2-2-0 143231.62 133062.17 195 7-3-3-1 82 1-8-0-0 7529.5 699.49 0.53 househol 28893. 1-13-3- ds Mr. Juthe Kumal Ms. Biba Kumalni 208 5-4-1-2 34 2 10240.71 951.36 0.71 Mr. Prem Kumar 9727.3 12 Piya Msrs/Gopal/Mangali Sunar 3-6-3-0 18738.18 17407.77 209 1-12-1-2 4 0-2-1-2 828.84 77.00 0.44 Mr.Dil Bahadur Thapa 25527. One 13 Magar 32-0-0-0 175232 162790.53 8 4-10-2-1 01 1-9-1-3 8729.98 811.02 4.66 househol Mr.Dil Bahadur Thapa 18882. ds Magar 12 3-7-0-2 53 0-1-3-0 598.93 55.64 0.03 Mr. Thir Bahadur Thapa 3109.6 14 Magar 9-6-1-1 51623.57 47958.30 11 0-9-0-1 4 0-7-1-1 2510.7 233.24 0.49 Mr. Krishna 78204. 0-10-0- 15 Bahadur Gole Ms Man Kumari Garju 35-0-0-0 191660 178052.14 100 14-4-2-0 12 3 3510.67 326.14 0.18 Mr.Um Bahadur Thapa One 16 Magar 17-5-0-0 94803.25 88072.22 30 0-10-0-0 3422.5 0-4-0-2 1427.78 132.64 0.15 househol Mr.Um Bahadur Thapa 7730.0 ds Magar 61 1-6-2-1 1 0-1-2-0 513.37 47.69 0.05 Mr. Bam Bahadur Thapa 6074.9 17 Magar 14-0-0-0 219040 203488.16 32 1-1-3-0 3 0-1-1-0 427.81 39.74 0.02 Padam Bahadur 13521. 18 Thapamagar 35-2-3-0 192601.18 178926.50 63 2-7-1-3 48 0-2-0-0 684.5 63.59 0.04 19 Ms. Ogle Kumalnee 3-5-3-3 18484.1 17171.73 20 Ms. Sanu Maya Acharya 1-8-2-1 8414.51 7817.08 Have effect on plots but the AP do not know the plot no. and area of affected Mr. Ambar Bahadur plat. Interviewed based on T/L alignment 21 Gurung 9-0-0-0 49284 45784.84 AP 21-39: Gorkha district, Chyangli VDC 8, Kumalgaun, Purnepipla, Majhgaun, Nayangaun 96428. 5-3-0- 1 Mr. Surya Bahadur Kumal 4-0-0-0 21904 20348.82 755 17-9-3-0 93 0 28406.75 2638.99 12.97 0-10- 2 Mr. Aite Kumal 1-9-0-0 8556.25 7948.76 421 5-4-0-0 28749 0-0 3422.5 317.95 4.00 8556.2 0-9-3- One 3 Ms. Sundari Kumal 16-2-0-0 88300.5 82031.16 431 1-9-0-0 5 0 3336.93 310.00 0.38 househol 0-7-2- ds Ms. Sundari Kumal 429 0-14-0-0 4791.5 1 2596.26 241.19 0.29 4165.7 0-6-3- 4 Mr. Purne Kumal 25-0-0-0 136900 127180.10 428 0-12-0-2 8 2 2368.96 220.08 0.17

24 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

5 Ms Ila Kumal 87-6-2-1 478666.01 444680.72 Have effect on plots but the AP do not know the plot no. and area of 6 Mr.Govinda Bahadur Kumal 3-0-0-0 16428 15261.61 affected plat. Interviewed based on T/L alignment 7 Mr.Gaine Kumal 8-0-0-0 43808 40697.63 8 Mr Madan Bahadur Kumal 15-2-0-0 82824.5 76943.96 New Marsyangdi Sub-station: Aanbukhairini -3, Markichock, Raudi Khold, Ekle Phant Mr. Dhok Raj Ms. Popi Maya Chitaure 35678. 1 Gurung Magar 26-2-3-2 143375.96 133196.267 169 6-8-1-0 56 0-9-2-0 3251.37 302.05 0.23 Mr. Lil Bahadur Mr. Rup Bahdaur Chitaure 27524. 2 Chitaure Magar Magar 17-4-3-0 49717.68 46187.7247 334 5-0-1-2 34 1-4-0-2 6903.78 641.36 1.39 3 Mr. Krishna Mani Pant 35-0-0-0 191660 178052.14 422 6-12-0-0 36963 0-6-1-0 2139.06 198.72 0.11 Mr.Suk Bahadur Chitaure 14-15-1- 7957.3 4 Mr. Gobardhan Pant Magar 3 81971.48 76151.5049 174 1-7-1-1 1 1-0-0-0 5476 508.72 0.67 Mr. Khil Prasad 11807. 5 Pant Ms. Punyawati Pant 22-6-0-0 122525.5 113826.19 175 2-2-2-0 62 0-2-3-1 970.57 90.17 0.08 17688 1295.8 6 Mr. Raj and other Ms. Mina Gurung 83-8-3-1 457532.07 425047.293 635 32-4-3-1 7.07 2-8-2-3 13949.29 9 0.30 62032. 1716.9 7 Ms. Suni Maya Magar 22-3-1-3 121672.48 113033.734 392 11-5-1-0 81 3-6-0-0 18481.5 3 1.52 Mr. Chandra Bahadur Gurung Mr. Takp Bahadur Magar 0 253 5-4-0-1 28749 0-6-2-1 2254.01 209.40 0.19 Ms. Dadhi Maya 33-11-1- 1134.1 8 Pudel Mr. Sher Bahadur Magar 1 184587.7 171481.973 420 5-0-0-0 27380 2-3-2-2 12208.65 8 0.66 Mr.Chabi Lal Mr. Tek Bahadur Thapa 51366. 1-14-2- 9 Naharki Magar 24-0-0-0 131424 122092.896 609 9-8-3-3 85 0 10438.62 969.75 0.79 Mr.Chabi Lal Msrs. Padam Maya/Sumitra 52193 10 Naharki Magar 9-3-1-0 50396.31 46818.172 613 0-15-1-0 1 0-4-2-0 1540.12 143.08 0.31 11 Mr. Ishwar Thapa 8-12-3-3 48259.85 44833.4007 12 Mr. Megh Nath Naharki 4-0-1-2 22048.34 20482.9079 Mr. Lekh Bahadur Sumi 13 Magar 10-0-3-0 55016.68 51110.4957 14 Mr. Jabar Singh Gurung 29-3-2-3 160090.04 148723.647

Have effect on plots but the AP do not know the plot no. and area of affected plat. Interviewed based on T/L alignment 15 Mr. Ratna Man Shrestha 15-0-0-0 82140 76308.06

Chapali Sub-station

Total Land Total Land Affecte % of Owned (Sq. in sq.m d Loss in Feet) Areain Total sq.m Ownershi Total Affecte p Land Parcel d Area Affected S.N Former Plot Owners Remark Owned No. Area Area (Ropan Area . Name Recent Plot Owner’s Name s (Ropani) (6Ga) (Ropani) (sq.ft) i) (sq.ft.) 1-5-0-0- - 1. X Ms. Jamuna Shrestha x x X X 770 x - 2. X Ms. Suntali Karki x x X X 771 1-0-0-0 -

25 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

3. X NEA x x X X 845 0-3-0-0 - 4. X Ms. Putali Pariyar x x X X 865 0-5-0-0 - 5. X Ms. Shatya Maya Shrestha x x X X 866 0-5-0-0 - 6. Ms. Maya Devi Pathak x x X X 889 0-1-0-1 - 7. X Ms. Maiya Devi Pathak x x X X 891 0-1-3-1 8. X Mr. Govinda Prasad Pathak x x X X 892 0-6-0-0 9. X Mr. Niban Kumag Gurung x x X X 893 0-12-0-0 Ms. Punya Kumari Pathak 10. X Ms. Govinda Pathak x x X X 911 0-2-2-0 11. X Ms. Maya Devi Pathak x x X X 912 0-1-2-0 Ms Satya Narayan 12 X Manandhar x x X X 913 2-8-2-0 13. X Mr. Radhya Khadka x x X X 1160 0-7-0-0 Ms. Shanta Thapa 14. X Ms. Maili Thapa x x X X 161 1-11-2-0 15 X Ms. Puspa Maya Mahat x x X X 1861 0-5-0-0 16 X Ms. Radhika Nibat x x X X 1865 0-4-0-0 17 X Record yet to be identified x x X X 1870 1-3-0-0 18. X Ms. Sunia Pariyar x x X X 1885 0-4-0-0 19. X Govt. Access x x X X 1887 0-0-3-0

20 X Mr. Sadhu Ram Tamang x x X X 1936 1-0-0-0 21 X Ms. Kanda Shrestha x x X X 1941 0-9-0-0 22 X Ms.Sharda Kumari Shresths x x X X 1943 0-2-2-0 23. X Govt. Access x x X X 1944 0-0-1-0 24 X Record yet to be identified x x X X 1945 0-2-2-0 25 X Ms. Viwa Khanal x x X X 2037 0-4-0-0 26 X Govt. Access x x X X 2038 0-1-1-0 27. X Ms. Jasoda Sitaula x x X X 2040 0-3-0-0 28 X Record yet to be identified x x X X 2041 0-2-3-2 29 X Record yet to be identified x x X X 2081 0-0-1-0 30 X Ms. Maiya Khadka x x X X 2096 0-5-0-0 31 X Ms. Parbvati Gurung x x X X 2099 0-3-0-0 32 X Mr. Vishnu Rai x x X X 2100 0-4-0-0 32 X Govt. Access x x X X 2102 0-2-1-0 33 X Mr. Indra Bahadur Tamang x x X X 2133 0-5-2-0 34 X Mr. Pancha Shrestha x x X X 2135 0-6-2-0 35 X Ms. Bimala Rai x x X X 2136 0-3-0-0 36 X Ms. Kamala Tamang x x X X 2137 0-4-4-0 38 X Ms. Bimala Rai x x X X 2138 0-2-3-0

39 X Mr. Jagat Bahadur Tamang x x X X 2141 0-3-0-0 40 X Jeshu Pyakurel x x X X 2143 0-9-0-0 41 X Mr. Pancha Shrestha X x X X 2144 0-0-3-0 42 X Ms. Dil Maya Tamang X x X X 2152 0-3-0-0

43 X Record yet to be identified X x X X 2153 0-1-2-0 44. X Mr. Ram Gurung X x X X 2154 0-0-1-1 45 X Mr. Ram Gurung X x X X 2156 0-2-2-3 46 X Ms. Ganesh Maya Prajapati X x X X 2170 0-0-3-1 47 X Govt. Access X x X X 2171 0-0-2-0

26 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

48 X Record yet to be identified X x X X 2172 1-3-2-0 Ms. Ganesh Maya Prajapati 49 X (3 persons) x x X X 2173 0-5-0-3 50 X Govt. Access x x X X 2174 0-3-0-0 51 X Govt. Access x x X X 2177 0-0-3-2 52 X Record yet to be identified x x X X 2178 2-12-0-2 53 X Indu Khadka x x X X 2183 0-1-2-0 54 X Ms. Sukhulbati Prajapati x x X X 2184 0-5-0-0 55 X Govt. Access x x X X 2185 0-6-2-1 56 X Record yet to be identified x x X X 2186 0-9-2-0 57 X Ms. Sabita Koirala x x X X 2188 0-6-0-0 58 X Record yet to be identified x x X X 2189 0-6-3-0 59 X Chiring Lama x x X X 2192 0-5-2-1 Rajendra Shrestha and 60 X Chiring Devi x X X X 2193 0-5-0-1 61 X Nimi paudel x X X X 2194 0-4-0-0 62 X Mr. Dhan Bahadur Khadka x X X X 2195 0-8-1-2 63 X Record yet to be identified x x X X X 64 X Record yet to be identified x x X X X 65 X Record yet to be identified x x X X X 66 X Record yet to be identified x x X X X 67 X Record yet to be identified x x X X X 68 X Record yet to be identified x x X X X 69 X Record yet to be identified x x X X X 70 X Record yet to be identified x x X X X 71 X Record yet to be identified x x X X X 72 X Record yet to be identified x x X X X 73 X Record yet to be identified x x X X X 74 X Record yet to be identified x x X X X Source: Census Feb. 09 –Apr. 2009 (to be updated during detail design)

27 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix C-4 Description of the Affected Structures by Construction Types and Other Details Dumre- Damauli –Marsyangdi 132 kV New Transmission Line Construction

S.N Name of Structur AP No. Owners’ Name District floor

. Place e Types Ward No. Type of structure VDC/Municipality Length in ft. Breadth in ft. Height in ft. Total Floor Area (sq.m.) Rate per (sq.m.) in NRs. Compensation cost (NRs) 1 Cement 1 82.76 4970 3-4. Ms. Rama Khadka Residential Tanahu Vyas Muni. 1 School Tole Block 20 12 12 411,336 Thatche 2 68.17 4300 6-7, Mr. Suppe Tamang Residential Tanahu Byas Muni. 3 Kokle Danda d house 18 11.4 12 293,122 Mr. Ganga Bahadur Cement 124.8 3 4970 6-7, Tamang Residential Tanahu Byas Muni. 3 Kokle Danda Block 31 15.8 9 1 620,296 Stone built+M 219.2 4 4680 Mr. Akal Bahadur ud 5 6-7. Tamang Residential Tanahu Byas Muni. 3 Kokle Danda Mortar 22 16 22 1,026,107 Stone built+M 313.9 5 4680 Mr. Man Bahadur ud 3 6-7. Tamang Residential Tanahu Byas Muni. 3 Kokle Danda Mortar 32 16 22 1,469,198 Stone built+M 6 91.17 4680 2 ud .7-8 Mr. Ganesh Raj Adhikari Residential Tanahu Byas Muni. 3 Sewar Mortar 23 14 10 426,661 Stone built+M 7 79.23 4680 ud 19-20 Mr. Bal Bahadur Sarki Residential Tanahu Bhanu 5 Thuletar Mortar 22 10.6 12 370,798 Cement 8 2.46 19-20 Mr. Bal Bahadur Sarki Toilet Tanahu Bhanu 5 Thuletar Mortar 3.5 3.1 8 4680 11,501 Stone built+M 9 80.86 4680 ud 20-21 Mr. Maite Nepali Residential Tanahu Bhanu 5 Thuletar Mortar 17 14 12 378,430 Stone built+M 174.7 10 4680 Mr. Singha Bahadur ud 2 20-21 Thapa Residential Tanahu Bhanu 5 Thuletar Mortar 51 11 11 817,679 Stone 11 Mr. Ambar Bahadur built+M 76.70 4680 20-21 Acharya Residential Tanahu Bhanu 5 Thuletar ud Mortar 17 13.6 12 358,968

28 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Stone built+M 12 70.03 4680 Mr. Ambar Bahadur ud 20-21 Acharya Residential Tanahu Bhanu 5 Thuletar Mortar 20 11.3 11 327,757 Stone built+M 192.8 13 4680 Mr. Ram Bahadur ud 4 20-21 Acharya Residential Tanahu Bhanu 5 Thuletar Mortar 24 12.9 22 902,507 Mr. Ram Bahadur Cement 14 4.47 20-21 Acharya Toilet Tanahu Bhanu 5 Thuletar Mortar 5.5 4.1 7 4680 20,916 Stone built+M 377.6 15 4680 ud 9 20-21 Mr. Gopi Acharya Residential Tanahu Bhanu 5 Thuletar Mortar 29 23 20 1,767,596 Stone built+M 16 3.89 4680 ud 20-21 Mr. Gopi Acharya Toilet Tanahu Bhanu 5 Thuletar Mortar 5 5.5 5 18,219

17 .Markich Mr. Dhan Bahadur Resi/Comm Anbu Cement 69.95 ck Gurung ercial Tanahu Khairini 3 Markichock Block 18 13.5 10 4970 347,634 .Markich Mr. Dhan Bahadur Anbu Cement 18 38.48 ck Gurung Residential Tanahu Khairini 3 Markichock Block 15 9 10 4970 191,230 Mud 19 .Markich Anbu Mortar 70.07 ck Mr. Sante Chhetri Residential Tanahu Khairini 3 Raudikhola RCC 15 15 11 4680 327,946 .Markich Anbu Thatche 20 63.53 ck Mr. Buddhi Ram Lama Residential Tanahu Khairini 3 Raudikhola d House 17 11 12 4300 273,195 .Markich Anbu Thatche 21 64.93 ck Mr. Shyam Lama Residential Tanahu Khairini 3 Raudikhola d house 15 13 12 4300 279,185 Sub-total of Dumre-Damauli-Marsyangdi Sub-project: NRs. 10,640,280 Chapali Sub-Station Stone brick 122.2 1. Mr. Krishna Bahadur Pariyar Residential Chapali 8 Bhangal built+M 10 4680 5 Kathmand ud u Mortar 34 12.7 572149.8 Stone brick 2 Residential Chapali 8 Bhangal built+M 67.56 4680 Kathmand ud 22. Ms. Sunita Pariyar u Mortar 3 10.7 10 316166.46 Sub-total of Chapali Sub-project: NRs. 888316.33 Note: The rate for different types of houses have been derived based on recently updated rate of MPPW, Dept. of Urban Development and Housing FY: 065/66

29 Appendix C-5 Details on Permanent and Temporary Loss of Crops (Ref. Table 3-20.) Loss of Crops

Estimated Land Area Likely to Effect on Crops Descriptions Compensation for 15 One Time Compensation Years Crops Value Ropani sq.m. ha. Rate NRs/ha for Temporary Loss of S.N for Permanent Loss Crops (NRs)[A] A. Transmission Line and Sub-station Construction of Land(NRs) Permanent Loss of Crops

Loss of Crops due to Permanent Acquisition for the construction of 8x8 towers (12 nos) for 132 kV T/L in 1 Dumre - Damauli Section (18 km) 1.51 768 0.08 20236.00 1566.68 23500.24615

Loss of Crops due to Permanent acquisition for the construction of 11.25x11.25 towers for New 2 Marsyangdi Section 0.87 445 0.04 20236.00 902.84 13,542.55 Loss of Crops due to Permanent Acquisition for Sub- 3 station construction at Chapali, Kathmandu 35 17806 1.78 20236.00 36,321.03 544,815.38

Sub-total 37.38 19019 1.90 38,790.55 581858.1846 Temporary Loss of Crops 581858.1846 Loss of Crops along the RoW Corridor of Dumre- 4 Damauli during Construction Phase 34.50 17550 1.76 20236.00 35,514.18

Loss of Crops along the RoW Corridor of New 5 Marsyangdi S/S 0.87 445 0.04 20236.00 907.72 Loss of Crops along the RoW Corridor of Middle Marsyangdi-Marsyangdi Second Circuit Stringing (44 6 km) 1544.40 792000 79.20 20236.00 1,602,691.20 Loss of Crops due to Butwal-Kohalpur 132 kV second circuit stringing (estimated to be affected 75 km 7 cultivating land) 3538.15 1800000 180.00 185291.00 33,352,380.00 Sub-total 5117.92 2609995 261.00 34,991,493.10 2865995

B Distribution Sub-stations Permanent Loss of Crops Loss of Crops due to Permanent Acquisition for the Construction of Distribution Sub-station at Baniyani, 1 Jhapa 14 6919 0.69 185291.00 133,029.44 1,995,441.54 Loss of Crops due to Permanent Acquisition for the Construction of Distribution Sub-station at Mirchiya, 2 Siraha 13.6 6919 0.69 185291.00 129,228.59 1,938,428.92 Loss of Crops due to Permanent Acquisition for the Construction of Distribution Sub-station at Dhikur 4 Pokhar/Banskor, Kaski 6 3052 0.31 20236.00 6,226.46 93,396.92 Loss of Crops due to Permanent Acquisition for the Construction of Distribution Sub-station at Kusma, 5 Parbat 6 3052 0.31 20236.00 6,226.46 93,396.92 Loss of Crops due to Permanent Acquisition for the 6 Construction of Switching Sub-station at Mulpani 1 509 0.05 20236.00 1,037.74 15,566.15 Sub-total 40 20451 2.05 275,748.70 4,136,230.46 Temporary Loss of Crops

Loss of Crops in the RoW corridor during 33kV 1 stringing for Baniyani S/S 118 60000 6.00 1,121,248.10 Loss of Crops in the RoW Corridor during 33 kV 2 stringing for Dhanushadham S/S 24 12000 1.20 228,050.46

Loss of Crops in the RoW corridor during 33kV 3 stringing for MIrchiya S/S 14 100000 10.00 133,029.44

30 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Loss of Crops in the RoW corridor during 33kV 4 stringing for Mahorati S/S 157 80000 8.00 1,491,830.10

Loss of Crops in the RoW corridor during 33kV 5 stringing for Mainapokhar S/S 8 4000 0.40 76,016.82 Sub-total 320 256000 25.60 3,050,174.92 Sub-total of Permanent Loss 78 39470 3.95 314,539.24 4,718,088.65 Sub-total of Temporary Loss 5438 2865995 286.60 38,041,668.02 All total 5528.87 2912348.17 291.66 38,356,207.27 [A] Compensation for the loss of crops is calculated based on the Average Cost, Return and Net Profit of Some Major Crops, Government of Nepal, Ministry of Agriculture and Co- operatives, Argi-Business Promotion and Statistics Division, Nepal, 2007/2008

31 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix C-6

List of Interviewed Indigenous/Ethnic, and Minor Households Having Major Impact

S.N. Name Type of Effects Location

Dumre-Damauli Sub-project

1. Mr. Purna Bahadur Gurung Residential Land AP-2-3

Residential /commercial Structures 2 Mr. Suppe Tamang 6-7, Residential /commercial Structures 3 Mr. Ganga Bahadur Tamang 6-7, 4 Residential /commercial Structures Mr. Akal Bahadur Tamang 6-7. Residential /commercial Structures 5 Mr. Man Bahadur Tamang 6-7. Residential /commercial Structures 6 Mr. Bal Bahadur Sarki 19-20 Residential /commercial Structures 7 Mr. Bal Bahadur Sarki 19-20 Residential /commercial Structures 8 Mr. Bal Bahadur Sarki 20-21 Residential /commercial Structures 9 Mr. Bal Bahadur Sarki 20-21 Residential /commercial Structures 10 Mr. Maite Nepali .Markichck Residential /commercial Structures 11 Mr. Singha Bahadur Thapa .Markichck Residential /commercial Structures 12 Mr. Dhan Bahadur Gurung .Markichck Residential structure 13 Mr. Dhan Bahadur Gurung .Markichck 14 Residential structure Mr. Buddhi Ram Lama 6-7, 15 Mr. Shyam Lama Residential structure 6-7,

Chapali Sub-project

16 Residential structure Mr. Krishna Bahadur Pariyar

Residential structure 17 Ms. Sunita Pariyar

Total Indigenous and Ethnic household likely to have significant Impact 17

32 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix D-1 NEA’s Resettlement planning Implementing Experiences

S.N Projects NEA Practices 1. Transmission Line Projects Compensation in cash to the legal APs (owners and tenants) only prior to 1993 for house structures under the RoW and land occupied by tower structures as per Land Acquisition Act 1977 No compensation to other land restricted for land use under ROW. No resettlement provisions No provision for rehabilitation/livelihood assistance to APs No provisions for compensation to the trees and standing crops. No provision of compensation and rehabilitation /livelihood assistance to APs other than titleholders 2. Kathmandu Valley High Inclusion of representatives of the APs and Village Development Voltage Reinforcement Committee (VDC) in the Compensation Fixation Committee (CFC). Project (1993-1997), 100% cash compensation to legal APs for the land occupied by the financed under the World Permanent structures. The land is registered to NEA. bank 10% cash compensation to the legal APs for the house structures under the RoW and 90% cash compensation to the land occupied By the house structures. The land is restricted for structure and tree plantation. The land ownership remains to AP. 100% cash compensation to the planted trees, fruit trees and crops Cash compensation for land is based on the district evaluation norms. Depreciation was accounted. Cash compensation for crops and trees based on the District Forest Officer’s evaluation. The structure owner was entitled for salvaged materials. Additional 10% of the structure cost was compensated in cash to APs for the transportation of salvaged materials. 3. Khimti- Bhaktapur – Balaju All provisions similar to Kathmandu Valley Reinforcement Project 132 kV Transmission Line (1993-1997) with flowing instructions: Project (1995 -1999), 100% cash compensation for utility facilities such as water supply, under NEA and GON power supply, telephone, toilets, bio-gas plants and cowsheds to legal APs of the house structures on RoW. 4. Lalpur-Gaddachauki 132 kV All provisions similar to Khimti- Bhaktapur – Balaju 132 kV Transmission Line Project Transmission Line Project (1995 -1999), with flowing instructions: (1977-1999) under NEA and GON 5. Chilime-Trishuli-Devighat All provisions similar to Khimti- Bhaktapur – Balaju 132 kV 66 kV Transmission Line Transmission Line Project (1995 -1999) Project (1997-1999) under NEA and GON 6. Lower Marsyangdi- Middle All provisions similar to Khimti- Bhaktapur – Balaju 132 kV Marsyangdi 132 kV T/L Transmission Line Project (1995 -1999) Construction under NEA and KfW 7. Thankot-Chapagaun- Provisions as in Kathmandu Valley High Voltage Reinforcement Bhaktapur 132 kV T/L Project (1993-1997), financed under the World bank Project Source: Resettlement Plan: Thankot- Chapagaun-Bhaktapur 12 kV T/L Project, May 2004

33 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix E-1 Stakeholder Consultation Matrix

Consultation Issues Strategies to A the Issue Middle Marsyangdi-Dumre-Damauli and New Marsyangdi 132 kV Transmission Lines AP 1 – 2: The Users Committee (UC)of the Bagbhanjyang Community NEA will consult the users’ committee and considers Bagbhanjyang Community Forest Users Forest (30.42 ha) is planning to establish a jungle park in the suggestion as much as practicable during the Groups the community forest with mini zoo, martyrs’ park, temples implementation phase. and shrines of different cast and ethnic groups, picnic spot, Location: Byas Municipality-11 swimming pool etc. A construction committee has also been formed and registered under the District Development Groups Meeting Committee. The master plan of the park has been designed by Town Development Fund of the district. The users committee . has requested NEA to finalize the Project design and alignment route and tower location in close consultation with the forest users’ community for the successful implementation of the Project in a way not hampering the Project. AP: 2- 4 As per the existing alignment a residential structure (L = 20.3 NEA will consult the users’ committee and considers ft, B=12 ft, H=12) of a single headed women (separated with the suggestion as much as practicable during the Birata Community Forest Users Committee husband) likely to be affected. In addition, there is also implementation phase. Location: Byas Municipality-11 commercial (homestead) land likely to be affected due to RoW. The community and the AP has requested NEA to push back Groups Meeting the proposed alignment route towards forest from the residential and commercial land area to minimize the acquisition and resettlement impact.

AP: 4-5 The plot owners likely to have acquisition of NEA will consult the users’ committee and considers -Byas Municipality, Ward No. 5, Sewer, Dihi his has due to tower construction has the suggestion as much as practicable during the Gaun requested to shift the location of AP 5 just 5 implementation phase. -Local Affected Households meters ahead fn his next land plot to avoid the RoW impact in him homestead land. AP:11 Based on Government land record the land selected for AP 11 NEA will consult the Land Acquisition and at Ghansikuwa VDC ward No. 4 is Government land. However, Compensation Fixation Committee to address such during the census, the local community mentioned that the land issues. is being occupied by a Government primary school (Deurali Primary School) since long to construct school building. The process of transforming the ownership of the land is under process. Thus, the school should be provided compensation for the land to be acquired to locate AP 11. AP: 5-6 Originally, some of the land parcels likely to have Project’s The Land acquisition and Resettlement Plan ensures impact in this location are owned by Government (known as the compensation for the loss of crops and tree for Ailani). However, 4-5 years back, Government (Commission its owners/cultivators. for Landless) provided some land to the landless households (Sukumbasis) residing in the district (migrated from other districts). In addition, they were given conditional authority (without formal ownership) to use such land for cultivation

34 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

and settlement. As per the existing route alignment of this section, about 15-20 such households will have effect on their land. As per prevailing legal provision of Nepal they are not entitled to get compensation for the effect on their land due to lack of formal ownership AP: 18 Basudev community forest will have major impact, if the tower is constructed on the existing proposed location. As per the This method may reduce the extent of loss solely Basudev Community Forest Users Group existing alignment route most of the trees in the forest are Saal concentrated in Basudev community forest. Pushing (regenerated) and of small size. The committee has requested back the alignment may be helpful to reduce the Ghansikuwa 1, Nahala to push back this AP 18 approximately 100 meter north from extent of Project impact, as it will be shared between the existing point. This method may reduce the extent of loss Basudev Community Forest and Ramite Community Meeting with Forest Users Group solely concentrated in Basudev community forest as pushing Forest (which exist in the bordering area of Basudev back the alignment route will would be helpful on sharing the Community Forest). Project’s impact between Basudev Community Forest and Ramite Community Forest (which exist in the bordering area of Basudev Community Forest). AP:21 NEA should clear all due compensation for the loss caused by NEA is always positive on timely payment of the Local community affected by Middle (MMHEP) compensation with the support of local community Marsyangdi Hydroelectricity Project (MMHEP) and Project affected families Chyangli VDC, Ward No. 2, Kumal Gaun Chapali Sub-station Local Community Compensation for the acquired land to be paid on current local The LARP has made provision of compensating the market acquired property on the current market value The residential structures around the proposed sub-station area The technical design has avoided the scope of to be protected acquiring any residential structures Compound wall of the proposed sub-station to be constructed The technical design have considered the need of ensuring adequate space for the existing community access providing adequate while fencing the compound of sub-station Employment opportunity for the local community to be ensured Clauses for encouraging local skill and non-skill during the construction phase workforce in the contractor’s contract The access form the main road to the sub-station location to Necessary improvement work will be done as per be improved need during the construction phase. NEA to monitor the implementation activities regularly NEA will assign a Project Manager to monitor the Project activities Distribution Substation at Different Districts Local Community NEA should provide reliable electricity supply and reduce the The community were informed the construction of load shading hours the sub-station will provide better and reliable energy supply NEA should pay adequate compensation for the land purchased NEA will pay current market rate for the land to be from the private party purchased from the private /individuals land owners Employment opportunity to be ensured to the local people NEA will do necessary arrangement to encourage during the construction local level employment for semi-skilled and non- skilled work) Source: Census Feb. 09 –Apr. 2009

35 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix F-1 Terms of Reference for NGOs

Background

Nepal Electricity Authority is implementing a Project, Nepal Electricity Connectivity and Energy Efficiency Project consists of six investment components and one component on provision of expert services. The investment components are; (i) Transmission network capacity augmentation, (ii) Distribution network capacity augmentation, (iii) Generation rehabilitation, (iv) Distribution network loss reduction, (v) Assistance for public private partnership (PPP) in distribution, (vi) Energy efficient lighting, and (vii) Solar-powered street lighting. The Project Preparation Technical Assistance (PPTA) to prepare feasibility studies to improve; (i) grid connectivity (ii) efficiency of electricity distribution, and (iii) demand-side management, through appropriate interventions to ease the supply and shortage constraints in the proposed Project locations and even in other different parts of the country. The proposed Projects studied under the TA to be funded by ADB loan and implemented by Nepal Electricity Authority (NEA).

The Project is expected to enhance the opportunity for hydropower development in the region, reduction of outage in the distribution network, and reduction of total network loss, supply of efficient and reliable energy are some of the key expected benefits of the Project. In addition, it is also anticipated that implementation of the Project may bring several positive impacts in the socio-economic scenario of the Project districts thereby contributing towards poverty reduction in the area, for example; creation of employment opportunities in the production sectors due to reliable and efficient electricity supply, and employment opportunity during construction period, are some of the other tangible benefits of the Project. Scope of Work

The NGO or the implementing developmental organization will be responsible for the effective, execution of the Land Acquisition and Resettlement Plan (LARP) of the Project. Following is the work scope of the NGO or the developmental organization: On Implementing Land Acquisition and Resettlement Plan

Information Campaign about the Land Acquisition and Resettlement Plan

Design, plan and implement an information campaign in the Project affected areas to inform the Project affected households about the entitlement policy and how to avail their respective entitlements. The campaign would include measures such as distribution of information booklets, leaflets, notices and other materials among the APs, community meetings, public announcements, and any other measures necessary to provide information to all the APs. The NGO or the developmental organization will undertake a public information campaign in the Project areas to inform the affected persons regarding: . The need for Land Acquisition (LA), wherever necessary; . The likely consequences of the Project on the communities; . The Resettlement and Rehabilitation (R&R) policy and entitlements; . Assist APs in getting the compensation for their land and properties acquired for the Project; . Ensure proper utilization by the APs of various grants available under the R&R package.

The NGO or developmental organization will be responsible for advising the APs on how best to utilize any cash that may be provided under the LARP, with emphasis placed on using such funds in sustainable way e.g. purchasing replacement land for that acquired.

36 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Identification and Confirmation of the APs

The developmental organization will identify and verify APs, based on the Census carried out and other relevant record. This work will include identification of APs based on a Census, updating the list and distributing ID cards, if required.

The NGO or developmental organization shall prepare a list of APs, enlisting the losses and the entitlements as per the LARP, after field verification. During the identification and verification of the eligible APs, it should be ensure that each of the APs are contacted and consulted either in groups or individually. The NGO/developmental organization shall specially ensure consultation with the vulnerable group and women from the affected households especially female-headed households. Creation/Computerization of Database and AP Files

A database containing the data on land, structure, trees and other affected properties of the APs have to be computerized to prepare AP files and entitlements cards (EC). The database will contain information from land records and census data. The AP and EC files will be used for making payments of entitlements to the APs and monitoring the progress of resettlement work. Participation in Grievance Redress

The developmental organization will act as an in-built grievance redress body and shall assist in finding solutions to any dispute over resettlement benefits. The APs can call upon the support of NGO to assist them in presenting their grievances or queries to the Grivance Readressal Committee (GRC). Relocation & Rehabilitation Assistance

The Project will adversely affect residential structures and residential land at some sections thereby entailing their relocation. The development organization shall facilitate the process of relocation & rehabilitation of the affected communities and households as per/in keeping with the framework of the LARP.

Information and Awareness Program on Hazard and Safety

With the support of PIU the NGO will design, plan and implement information and awareness campaign about the likely health hazard and safety measures along the corridor of proposed new transmission line, sub-station construction areas, and construction material storing areas. The campaign will include measures such as distribution of information booklets, leaflets, notices and other relevant materials. The information and awareness include the following components:

. Information about the Project activities and implementation schedule; . Equipments and materials used by the Project; . The likely hazard and accidents due to the Project and mitigation measures; . Precautions to be taken to keep protected from such likely accidents and emergency management , in case of any unanticipated accidents (e.g. breakdown of high voltage transmission line etc)

Information - Awareness Program on HIV/AIDS, Drugs/ Human Trafficking, Gamble and Alcoholism

The NGO will also design and implement program in HIV/AIDS and Drugs/Human Trafficking in different project locations particularly new transmission line route and sub-station construction sites. Some of the key suggested method of implementing information awareness program also to include:

. Organize public meeting in different Project location and distribution of information and awareness material on HIV/AIDS and Drugs/Human Trafficking;

. Organize information dissemination session targeting to the risk group population on the different topics of HIV AID and Drugs/Human Trafficking and likeliness of grooming sex trade and human trafficking activities due to the influx of outsiders in construction Projects and likeliness of increasing the extravagant activities like; alcoholism and gabling due t cash flow from the Project;

. Video show on related to HIV/AIDS and Human Trafficking and other social evils (alcoholism and gambling)

37 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Income Restoration Improvement Program

The NGO to support PIU on implementing income restoration and Improvement program to the project affected vulnerable groups. The key activities to be carried by the NGO on income restoration and improvement activities also include:

. Screen and identify the eligible households and candidates (with special focus to women) for income restoration and livelihood improvement program based on the list to be provided by the Project office; . Assess the priority and need of targeted beneficiaries for income restoration and improvement program . Identify and coordinate with different agencies to implement appropriate program and ensure the involvement of beneficiaries in the program as per their choice and competency . Monitor the income restoration and improvement program and report to project office

Selection Criteria, Staffing, Implementation Plan

The NGO/development organizations to be selected for the tasks must have experience in resettlement implementation, carrying out information and awareness and livelihood improvement program. Specifically, key quality criteria include:

. Experience in direct implementation of programs in local, similar and/or neighboring districts; . Availability of trained staff capable of including APs and target groups into the programs; . Competence, transparency and accountability based on neutral evaluations, internal reports, and audited accounts; and . Integrity to represent vulnerable groups against abuses, and experience in representing vulnerable groups, demonstrable mandate to represent local groups. . Demonstrated experience in computerizing database, . Experience in resettlement survey, planning, monitoring and evaluation including different social problems (e.g. HIV/AIDS and Drugs/Human Trafficking, Alcoholism and Gambling).

The developmental organization or the NGO chosen will have to agree to the terms and conditions of the executing agency and must be an established organization registered with GON Nepal. The following staffing provision may be necessary for smooth and effective implementation of the RP within the time frame:

(i) Team Leader/Coordinator ; (ii) Local Social Scientist (iii) Local Engineers (iv) Field coordinators/ mobilizers ; (v) Social mobilizers

Interested Developmental Organizations should submit proposal for the work with a brief statement of the approach, methodology, and field plan to carry out the tasks. The proposal should also include Relevant information reflecting previous experiences.

Full CVs (2-3 pages) of key personnel must be submitted along with the proposal. The Team Leader must have degree in social science (preferably sociology, anthropology, rural development).

Budget and Logistics:

Three copies of the proposal - both technical and financial - should be submitted. The budget should include all expenses such as staff salary, training, computer/database, transport, field and any other logistics necessary for resettlement implementation. Additional expense claims whatsoever outside the budget will not be entertained.

38 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Cost Estimate for NGO Mobilization

S.N. Items Rate Duration Amount Remarks (NRs. Per (Months/No.) NRs. Month/Activity) 1 Team Leader 40,000 2 80,000 Intermittent Input 2 Local Social Scientist 40,000 2 80,000 Intermittent Input

3 Local Overseer 25,000 3 75,000 Intermittent Input

4 Field Coordinators/ Mobilizers 15,000 8 120,000 Full Time 5 Video Show on information 3000 15 (shows) 45,000 awareness against different social evils (e.g. Human/drug trafficking, HIC/AIDS, Gamble, Alcoholism etc) and livelihood improvement Intermittent Activity 6 Information Awareness Program LS LS 200,000 on (i) Land Acquisition and Resettlement Plan, (ii) Health Safety, (iii) HIV/AIDS, Human/Drugs Trafficking, Gambling and Alcoholism

Intermittent Activity 7 Facilitation to income restoration LS LS 50,000 and improvement program Intermittent Activity 8 Equipment and material purchase LS LS 50,000

9 Administrative Cost 20,000 20,000

10 Transportation LS LS 25,000 11 Stationeries LS LS 25,000

Total 770,000 Contingency (10%) 77,000 Total Cost 847,000

39 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix G-1 List of Price of all Affected Land as Reported by Plot Owners Dumre-Damauli-New Marsyangdi S/S Section

ID AP Name of Household Head District VDC Ward Village/Tole Price of Affected Land (SRs/Ropani)

1001 AP7-AP8 Bhairav Nath Thainai Tanahun Bayang 3 Polyang 80,000 1002 AP7 -AP8 Lal Bahadur Darai Tanahun Bayash 3 Polyang 80,000 1003 AP7-AP8 Devendra Bastola Tanahun Bayash 6 Tatopani 50,000 1004 AP7-AP8 Shiva Lal Thami Tanahun Bayash 3 Polyang 70,000 1005 AP10-AP11 Krishna Pradad Pantha Tanahun Ghashi Kuwa 6 Bardan 60,000 1006 AP7-AP8 Tul Bahadur Gurung Tanahun Ghashi Kuwa 6 Sera 40,000 1007 AP-AP11 Tej Prashad Pantha Tanahun Ghashi Kuwa 3 Tharlung 100,000 1008 AP10-AP11 Moti Maya Ale Tanahun Ghashi Kuwa 6 Chabise 60,000 1009 AP10-Ap11 Rudra Nidhi Pantha Tanahun Ghashi Kuwa 4 Paling 50,000 1010 AP17-Ap18 Durga Bahadur Sahani Tanahun Ghashi Kuwa 1 Archale 100,000 1011 Ap17-AP18 Dhan Bahadur Adhikari Tanahun Ghashi Kuwa 8 Chirkani 100,000 1012 AP20-Ap21 Man Kumari Garanja Tanahun Bandipur 6 Bimalnagar 15,000 1013 AP19-AP20 Neetyananda Neupane Tanahun Bhanu 5 Bhansar 50,000 1014 AP19-Ap20 Heera Bahadur Nepali Tanahun Ghashikuwa 1 Bhudatar 50,000 1015 AP20-AP21 Uma Bahadur Thapa Tanahun Bandipur 6 Bimalnagar 10,000 1016 Ap20-Ap21 Shima Bahadur Thapa Tanahun Bhanu 5 Thulitar - 1017 Ap20-Ap21 Gale Kumalli Tanahun Bhanu 5 Dordor 150,000 1018 Ap20-Ap21 Shiva Gurung Tanahun Bhanu 5 Nayabasti 50,000 1019 AP20-Ap21 AMbar Bahadur Accharya Tanahun Bhanu 5 Thulitar 150,000 1020 AP7-AP8 Bashanta Bahadur Parajuli Tanahun Bayash 3 Polyang 150,000 1021 Ap10-AP11 Dambar Bahadur Gharti Tanahun Ghashi Kuwa 4 Khani Gaun 30,000 1022 AP12-AP13 Bam Bahadur Kami Tanahun Ghashi Kuwa 2 Deurali 75,000 1023 AP10-Ap11 Krishna Raj Kaine Tanahun Ghashi Kuwa 3 KamalBari 120,000 1024 AP10-Ap11 Til Bahadur Thapa Magar Tanahun Ghashi Kuwa 3 Kamalbari 150,000 1025 AP12-AP13 Baburam Kami Tanahun Ghashi Kuwa 2 Deurali 150,000 1026 Ramji Lohani Tanahun Tanahun 0 150,000

40 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

1027 AP17-AP18 Reshi Bahadur Rauta Tanahun Ghashi Kuwa 1 Archale 200,000 1028 AP20-AP21 Dhir Bahadur Thapa Magar Tanahun Bhanu 5 Tallo Baluwa 25,000 1029 AP19-Ap20 Ramji Nepali Tanahun Barbhangyang 1 Naagnagina 125,000 1030 AP19-AP20 Shyam Kaji Nepali Tanahun Ghashi Kuwa 1 Bhodatar 125,000 1031 AP20-AP21 Dil Bahadur Thapa Magar Tanahun Bhanu 5 Baluwa 100,000 1032 AP19-AP20 Shom Bahadur Nepali Tanahun Ghashi Kuwa 1 Bhodatar 125,000 1033 AP20-AP21 Maite Nepali Tanahun Bhanu 5 Thulitar 100,000 1034 AP20-AP21 Man Bahadur Tamang Tanahun Bhanu 5 Thulitar 150,000 1035 Ap20-AP21 Reauli Kumal Tanahun Bhanu 5 Nayabasti 150,000 1036 Ap20-Ap21 June Kumal Tanahun Bhanu 5 Thorthor 100,000 1037 AP20-AP21 Ambar Bahadur Gurung Tanahun Bhanu 5 Nayabasti 100,000 1038 AP20-AP21 Dev kumari panta Tanahun Bhanu 5 Nayabasti 100,000 1039 AP20-AP21 Dil Bahadur Kumal Tanahun Dordar 5 Bhansar 40,000 1040 AP20-AP21 Ram Bahadur Aacharya Tanahun Bhanu 5 Thuletar 195,000 1041 AP19-AP20 Kali Maya Sarki Tanahun Ghasikuwa 1 Bhudabari 60,000 1042 AP19-AP20 Bhim Bahadur Nepali Tanahun Bar Bhanjying 1 Nagpani 125,000 1043 AP20-AP21 BivahaMaya Kumal Tanahun Bhanu 5 Nayabasti 100,000 1044 AP20-AP21 Bom Bahadur Magar Tanahun Bandipur 6 Bimalnagar 10,000 1045 AP10-AP11 Basanta panta Tanahun Ghasikuwa 2 Deurali 50,000 1046 AP19-AP20 Sambhu Lal shrestha Tanahun Bhanu 5 Sajbore 400,000 1047 AP19-AP20 Basundhari Panta Tanahun Bhanu 5 Salbise 150,000 1048 AP10-AP11 Birbhadra Naharki Tanahun Dhasikuwa 4 Parling 100,000 1049 AP10-AP11 Krishna Kumari Sarki Tanahun Ghasikuwa 7 Deurali 30,000 1050 AP19-AP20 Bishnu prasad Neupane Tanahun Bhanu 5 Sajbore 50,000 1051 AP7-AP8 Samser Pariyar Tanahun Ghasikuwa 6 Tatopani 50,000 1052 AP10-AP11 Chandra kanta panta Tanahun Ghasikuwa 6 Katahare 40,000 1053 AP10-ap11 Padma raj panta Tanahun Ghasikuwa 3 Kamalabari 50,000 1054 AP10-AP11 Bhadra nidhi panta Tanahun Ghasikuwa 5 Kamalabari 100,000 1055 Ap7-AP8 Lalsubba Dura Tanahun Tanahu 9 Samdada 100,000 1056 AP7-AP8 Krishna raj Adhikari Tanahun Tanahu 3 Sehera 100,000

41 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

1057 AP7-Ap8 Dhan Bahadur Darai Tanahun Ghasikuwa 6 Tatopani 100,000 1058 Ap7-AP8 Bir Bahadur darai Tanahun Ghasikuwa 6 Tatopani 100,000 1059 AP7-AP8 Hira madi khanal Tanahun Bas 3 POlang 300,000 1060 AP7-AP8 Ganash raj Adhikari Tanahun Basa 3 Polang 400,000 1061 AP7-AP8 Muraai raj Kaini Tanahun GHasikuwa 6 Chabise 400,000 1062 AP7-AP8 Chandra bahadur Parajuli Tanahun Basa 3 Sera 300,000 1063 AP7-AP8 Budhhi Bahadur Parajuli Tanahun Basa 3 Paolang 320,000 1064 AP20-Ap21 Indra bahadur Kumal Tanahun Bhanu 5 Thimarobas 100,000 1065 AP-AP21 Sambhu Adhikari Tanahun Bhanu 5 Sajbote 150,000 1066 AP20-AP21 Gopi Bhadur Aacharya Tanahun Bhanu 5 Thuletar - 1067 AP20-AP21 Gopal Sunuwar Tanahun Bhanu 5 Nayabasti 100,000 1068 AP20-AP21 Padma Bahadur Thapa Tanahun Dordor 7 Baluwa 150,000 1069 AP19-AP20 Lure Sarki Tanahun Ghasikuwa 1 Bharatar 50,000 1070 AP17-AP18 Kishna Bahadur Sahani Tanahun Ghasikuwa 1 Bharchale 100,000 1071 AP17-AP18 Arjun Bhadur Rawol Tanahun Ghasikuwa 1 Archale 100,000 1072 AP10-AP11 Purna kanta Nagila Tanahun Ghasikuwa 6 Ramathunki 40,000 1073 AP10-Ap11 Hasta Bahadur Rimal Tanahun Ghasikuwa 6 Raikar 50,000 1074 AP10-AP11 Rudra raj Kaini Tanahun Ghasikuwa 3 Kamalabari 150,000 1075 AP7-AP8 Purna Bahadur Guring Tanahun Ghasikuwa 6 Sera 100,000 1076 AP2-AP3 Guna Bahadur darai Tanahun Bayash 2 Ganeshman Chock 1,600,000 1077 AP2-AP3 Purna Bahadur Gurung Tanahun Bayash 11 Sital Chock 1,600,000 1078 Ap3-AP4 Krishna Pariyar Tanahun Bayash 11 Bagbhangyang 600,000 1079 Madhu Maya Roka Sarki Tanahun Bayash 0 600,000 1080 AP2-AP3 Bhuvan Bahadur Darai Tanahun Bayash 11 Judi Pani 1,600,000 1081 Ap2-Ap3 Chet Bahadur Darai Tanahun Bayash 11 Gudapani 1,600,000 1082 AP4-Ap5 Ambar Bahadur Kuwar Tanahun Bayash 5 Dihi Gaun 1,600,000 1083 AP4-AP5 Bhoj Bahadur Darai Tanahun Bayash 5 Dihi Gaun 800,000 1084 AP4-AP5 Dhani Maya Darai Tanahun Bayash 5 Dihi Gaun 400,000 1085 AP5-AP6 Surya Maya Paudel Tanahun Bayash 3 Sewar 60,000 1086 Ap5-Ap6 Balram Misra Tanahun Bayash 5 Sewar 200,000

42 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

1087 AP5-AP6 Govinda Raj Poudel Tanahun Bayash 1 Armenu 50,000 1088 Ap6-Ap7 Pratap Tamang Tanahun Bayash 3 Kokal Dada - 1089 AP6-Ap7 Ram Bahadur Tamang Tanahun Bayash 3 Kokal Dada 30,000 1090 Ap6-Ap7 Chandra Bahadur Tamang Tanahun Bayash 3 Kokal Dada 50,000 1091 Ap6Ap7 Bam Bahadur Tamang Tanahun Bayash 3 Kokal Dada 50,000 1092 Ap6-Ap7 Ran Bahadur Darai Tanahun Bayash 3 Darai Padhera - 1093 Ap6-AP7 Man Bahadur Darai Tanahun Bayash 3 Kokal Dada - 1094 AP6-AP7 Ganga Bahadur Tamang Tanahun Bayash 3 Kokale Dada - 1095 AP6-AP7 Jang Bahadur Darai Tanahun Bayash 3 Kokal Dada 40,000 1096 AP3-AP4 Maite Maya BK Tanahun Bayash 11 Nibuwa Gairo 640,000 1097 Ap3-AP4 Aaita C Nepali Tanahun Bayash 11 School Tol 640,000 1098 Ap3AP4 Sula Bahadur Gurung Tanahun Bayash 11 School Tol 600,000 1099 Ap3Ap4 Nanu Maya Giri Tanahun Bayash 11 Birata tol - 1100 AP5-AP6 Babu Ram Koirala Tanahun Bayash 5 Sewar 2,000,000 1101 AP6-AP7 Tirtha Raj Poudel Tanahun Bayash 3 Kokale Dada 50,000 1102 Ap6AP7 Mana Bahadur Darai Tanahun Bayash 3 Parobari 80,000 1103 Ap6Ap7 Shom Bahadur Bk Tanahun Bayash 3 Shwami Dada 80,000 1104 Ap5Ap6 Hari Datta Poudel Tanahun Bayash 3 Ranigaun 120,000 1105 AP5-AP6 Kedar Nath poudel Tanahun Bayash 3 Gaun 120,000 1106 Ap3-Ap4 Bam Bahadur Adhikari Tanahun Bayash 11 Bhagbhangyang 240,000 1107 AP3-Ap4 Santa Ram Pradhan Tanahun Bayash 11 Baghbhangyang 320,000 1108 Ap5-Ap6 Mayia devi Adhikari Tanahun Bayash 3 Ranigaun 600,000 1109 Ap3-Ap4 Rama Khadka Tanahun Bayash 11 Bhagbhangyang 1,000,000 1110 Ap3Ap4 Juna Gurung Tanahun Bayash 11 Bhagbhangyang 240,000 1111 Ap3-AP4 Lalu Maya Pariyar Tanahun Bayash 11 Bhagbhangyang 160,000 1112 Ap4-AP5 Chitra Bahadur Darai Tanahun Bayash 3 Shantinagar 960,000 1113 AP4-AP5 Jash Bahadur darai Tanahun Bayash 3 Sewar 120,000 1114 AP4-AP5 Laxmi Prashad Neupane Tanahun Bayash 3 Ranigaun 128,000 1115 Ap4-Ap5 Bhim Bahadur Darai Tanahun Bayash 5 Dihegaun 960,000 1116 AP5-AP6 Chandra maya Poudel Tanahun Bayash 3 Ranigaun 90,000

43 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

1117 Ap5-AP6 Krishna Bahadur Misra Tanahun Bayash 3 Ratmata 320,000 1118 Ap6-Ap7 Dhan Bahadur darai Tanahun Bayash 3 Daraipadhera 17,000 1119 Ap6AP7 Lal Bahadur tamang Tanahun Bayash 3 Kokale dada 480,000 1120 Ap6-Ap7 Pancha Bahadur Bk Tanahun Bayash 3 Kokaldada 30,000 1121 AP6-AP7 Tika ram Tamang Tanahun Bayash 3 Kokaldada 80,000 1122 Ap6-Ap7 Bir Bahadur Tamang Tanahun Bayash 3 Kokaledada 90,000 1123 Ap6-AP7 Shom Bahadur Darai Tanahun Bayash 3 Daraitol 50,000 1124 Ap6-Ap7 LIl Bahadur Darai Tanahun Bayash 3 Daraitol 50,000 1125 Ap6-Ap7 Jeet Bahadur Darai Tanahun Bayash 3 Daraitol 50,000 1126 Ap6-AP7 Bir Bahadur Darai Tanahun Bayash 3 Daraitol 50,000 1127 AP6-AP7 Tul Bahadur darai Tanahun Bayash 3 Daraitol 50,000 1128 Ap6-Ap7 Aakal Bahadur Tamang Tanahun Bayash 3 Kokaledada 170,000 1129 AP6-AP7 Ram Kumar Khadka Tanahun Bayash 3 Kokaledada 170,000 1130 AP6-AP7 Khanga Bahadur Darai Tanahun Bayash 3 Simidada 240,000 1131 AP6AP7 Lal Bahadur Bk Tanahun Bayash 3 Samidanda 250,000 1132 AP6-AP7 Krishna Bahadur darai Tanahun Bayash 3 Samidanda 288,000 1133 Ap6-Ap7 Indra Bahadur Darai Tanahun Bayash 3 Samidanda 288,000 1134 AP3AP4 Uma Devi Thapa Tanahun Bayash 11 Bedhbayash tol 115,000 1135 AP4-AP5 Gore Darai Tanahun Bayash 5 Hidigaun 1,600,000 1136 Ap4-Ap5 Surya Bahadur Darai Tanahun Bayash 5 Dehigaun 700,000 1137 Ap6-AP7 Man Bahadur tamang Tanahun Bayash 3 Kokale Danda 70,000 1138 Ap11AP12 Subhadra Lohani Tanahun Ghashi Kuwa 7 Dolekhet 2,400,000 1139 Markichock Ratna Man Shrestha Tanahun Aabu Khaireni 3 Markichock 4,000,000 1140 Markichock Leka Badhur Sumi Magar Tanahun Aabu Khairani 3 Pateni 150,000 1141 Markic Cho Ishwor Thapa Tanahun Aabu Khaireni 3 Marki Chock 125,000 1142 Marko Choc Meghnath Naharki Tanahun Aabukhaireni 3 Markichock 150,000 1143 Markichock Sante Cheetri Tanahun Aabu Khaireni 3 Naubise - 1144 Markichock Shyam Lama Tanahun Aabukhaireni 3 Yakalefaat - 1145 Markichock Dhan Bahadur gurung Tanahun Aabukhaireni 3 Markichock 2,500,000 1146 Markichock Buddhi Ram Lama Tanahun Aabukhaireni 3 Rudi Khola -

44 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

1147 Markichock Jawar Sing Gurung Tanahun Aabukhaireni 3 Markichock 200,000 1148 Markichock Meena Gurung Tanahun Aabukhaireni 3 Yaklefaat 200,000 1149 Markichock Sher Bahadur Magar Tanahun Aabukhaireni 3 Markichock 150,000 1150 Markichock Padam maya magar Tanahun Aabukhaireni 3 Markichock 2,400,000 1151 Markichock Tek Bahadur Magar Tanahun Aabukhaireni 3 Markichock 225,000 1152 Markichock Punthawati Pant Tanahun Aabukhaireni 3 Markichock 100,000 1153 Markichock Tek Bahadur Chumi Magar Tanahun Aabukhaireni 3 Yaklefaat 3,000,000 1154 Markichock Suk Bahadur Chitaure Magar Tanahun Aabukhaireni 3 Markichock 200,000 1155 AP4-AP5 Nari Maya darai Tanahun Bayash 5 Dihigaun - 1156 Markichock Pobimaya Chitaure Magar Tanahun Aabu 3 Markichock 150,000 1157 Markichock Lil Bahadur Chitaure magar Tanahun Aabukhaireni 3 Markichock 150,000 1158 Markichock Krishna Mani Pant Tanahun Aabukhaireni 3 Markichock 300,000 1159 Ap4-AP5 Arjun Ale Tanahun Bayash 5 Dihigaun 900,000 1160 AP4-AP5 Padam Bahadur darai Tanahun Bayash 5 Dihigaun 960,000 1161 AP4-AP5 Purna Bahadur gurung Tanahun Bayash 1 Taalghare 960,000 1162 AP4-AP5 Mekhraj Baruwal Tanahun Bayash 5 Sewar 2,800,000 1163 AP4-AP5 Yam Bahadur Darai Tanahun Bayash 5 Dihigaun 960,000 1164 AP-AP7 Bal Bahadur darai Tanahun Bayash 3 Polyang 180,000 1165 AP5-AP6 Chitra Bahadur darai Tanahun Bayash 5 Dihigaun 320,000 1166 AP5-AP6 Jun Bahadur Darai Tanahun Bayash 5 Dihigaun 320,000 1167 AP5-AP6 Dhan Bahadur Darai Tanahun Bayash 5 Dihigaun 320,000 1168 AP4-AP5 Khadak Bahadur thapa Tanahun Bayash 5 Dihigaun 800,000 1169 AP4-Ap5 Bhoj Bahadur darai Tanahun Bayash 5 Dihigaun 1,280,000 1170 Ap4-AP5 Hari Kumar shrestha Tanahun Bayash 5 Dihigaun 220,000 1171 AP5AP6 Gana Bahadur darai Tanahun Bayash 5 Dihi Gaun 320,000 1172 Ap5-AP6 Chabilal darai Tanahun Bayash 5 Dihi Gaun 320,000 1173 AP_AP7 Nar Bahadur Bk Tanahun Bayash 3 Polyang 180,000 1174 AP4-AP5 Bishnu Bahadur Bk Tanahun Bayash 5 Dihi Gaun 1,200,000 1175 AP4-AP5 Singa Bahadur darai Tanahun Bayash 5 Dihi Gaun 1,200,000 2001 AP21-AP39 Dhan Bahadur Kumal Gorkha Chyangli 8 Pudne Pipal 90,000

45 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

2002 AP21-AP39 Govinda Bahadur Kumal Gorkha Chyangli 8 Magha Gaun 80,000 2003 AP21-AP39 Purne Kumal Gorkha Chyangli 8 Naya Gaun 100,000 2004 AP21-AP39 Santa Bahadur Kumal Gorkha Chyangling 8 Purna Pipal Nayagaun 100,000 2005 AP21-AP39 Baburam Kumal Gorkha Chyangli 8 Nayagaun Purna Pipal 100,000 2006 AP21-AP39 Bhakta Bahadur Kumal Gorkha Chyangli 8 Purne Pipal 80,000 2007 AP21-AP39 Madan Bahadur Kumal Gorkha Chyangli 8 Thatitar 100,000 2008 AP21AP39 Sundari Kumal Gorkha Chyangli 8 Kumal Gaun 100,000 Number HH Reporting 172 Average Price (Rs/Ropani) 371,081

46 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix H-1 Details on Land Compensation Cost

A: Cost Estimate of Permanent Acquisition of Land

Estimated Land Area to be Rate Per Compensation S.N. Descriptions Acquired Ropani Cost (NRs) (NRs)

In In In sq.m. Ropani ha. Transmission and Sub-station Construction 1 Permanent Acquisition for the construction of 8x8 towers (12 no) for 132 kV T/L in Dumre Damauli Section (18 km) 1.51 768 0.08 371,081.00 560,332 2 Permanent acquisition for the construction of 11.25x11.25 towers for New Marsyangdi Section 0.87 445.06 0.04 371,081.00 324,632 3 Permanent Acquisition for Sub- station construction at Chapali, 8,800,000.0 Kathmandu 35 17805.90 1.78 0 308,000,000 Sub-total 37.38 19018.96 1.90 X 308,884,964 Distribution Sub-stations 1 Permanent Acquisition for the Construction of Distribution Sub- station at Baniyani, Jhapa 13.6 6918.86 0.69 147,059.00 2,000,002 2 Permanent Acquisition for the Construction of Distribution Sub- station at Mirchiya, Siraha 13.6 6918.86 0.69 355,000.00 4,828,000 3 Permanent Acquisition for the Construction of Distribution Sub- station at Barthawa, Sarlahi 13.6 6918.86 0.69 147,058.00 1,999,989 4 Permanent Acquisition for the Construction of Distribution Sub- station at Dhikur Pokhari/Banskot, Kaski 6 3052.44 0.31 600,000.00 3,600,000 5 Permanent Acquisition for the Construction of Distribution Sub- station at Kusma, Parbat 6 3052.44 0.31 600,000.00 3,600,000 6 Construction of Switching Sub-station 5,600,000.0 at Mulpani 1 508.74 0.05 0 5,600,000 Sub-total 53.8 27370.21 2.74 X 21,627,9912 All Total 91.18 6,389.17 4.64 X 330,512,955

47 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

B: Cost Estimate for RoW Affected Land

S.N. Descriptions Estimated Land Area to be Rate Per Total Value Compensation Acquired Ropani of Land for the RoW (NRs) Under the Effect (10% of RoW the Total Land Value) In In sq.m. in ha. Ropani

Transmission and Sub-station Construction

Restriction on Use of Land Except for Agriculture to Maintain RoW (9m both side) 17.5 1 for 132 kV Dumre-Damauli T/L 344.97 175500 5 371081 128,011,785 12,801,178 Restriction on Use of Land Except for Agriculture to Maintain RoW (9m both side) for 132 kV New Marsyangdi Sub-station section of Dumre- 2 Damauli T/L (approx 1 km) 35.38 18000 1.80 371081 13,129,413 1,312,941 19.3 Sub-total 380.35 193500 5 742162 141,141,198 14,114,119 Distribution Sub-stations Restriction on Use of Land Except for Agriculture to Maintain RoW (2 m both side) for 33 kV – 1 Dhanusha T/L 23.59 12000 1.20 150000 3,538,153 353,815 Restriction on Use of Land Except for Agriculture to Maintain RoW (2 m both side) for 33 kV Dhalkebar – 2 Dhanusha T/L 15.72 8000 0.80 355000 5,580,600 558,060 Restriction on Use of Land Except for Agriculture to Maintain RoW (2 m both side) for 33 kV Maina Pokhar 33 kV 3 T/L 13.6 6918.9 0.69 5000000 3,459,430 345,943

Sub-total 39.31 20000 2.00 5505000 9,118,753 911,875 21.3 All Total 419.66 213500 5 6247162 150,259,951 15,025,995

48 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Appendix I - 1

Nepal Electricity Connectivity and Energy Efficiency Project I Terms of Reference for External Monitoring Agency

Background

Nepal Electricity Authority is implementing a Project, Nepal Electricity Connectivity and Energy Efficiency Project consists of six investment components and one component on provision of expert services. The investment components are; (i) Transmission network capacity augmentation, (ii) Distribution network capacity augmentation, (iii) Generation rehabilitation, (iv) Distribution network loss reduction, (v) Assistance for public private partnership (PPP) in distribution, (vi) Energy efficient lighting, and (vii) Solar-powered street lighting. The Project Preparation Technical Assistance (PPTA) to prepare feasibility studies to improve; (i) grid connectivity (ii) efficiency of electricity distribution, and (iii) demand-side management, through appropriate interventions to ease the supply and shortage constraints in the proposed Project locations and even in other different parts of the country. The proposed Projects studied under the TA to be funded by ADB loan and implemented by Nepal Electricity Authority (NEA).

The Project is expected to enhance the opportunity for hydropower development in the region, reduction of outage in the distribution network, and reduction of total network loss, supply of efficient and reliable energy are some of the key expected benefits of the Project. In addition, it is also anticipated that implementation of the Project may bring several positive impacts in the socio- economic scenario of the Project districts thereby contributing towards poverty reduction in the area, for example; creation of employment opportunities in the production sectors due to reliable and efficient electricity supply, and employment opportunity during construction period, are some of the other tangible benefits of the Project.

Scope of work- General

. To review and verify the progress in resettlement implementation as outlined in the Land Acquisition and Resettlement Plan (LARP); . To monitor the effectiveness and efficiency of Implementing Agency & NGO in RP implementation. . To assess whether resettlement objectives, particularly livelihoods and living standards of the Affected Persons (APs) have been restored or enhanced; . To assess resettlement efficiency, effectiveness, impact and sustainability, drawing both on policies and practices and to suggest any corrective measures, if necessary.

Scope of work- Specific

An Independent monitoring agency or individual consultant will be involved in ongoing monitoring of the resettlement efforts by the EA. The major tasks expected from the external monitor are:

. Review results of internal monitoring and verify claims through random checking at the field level to assess whether land acquisition/resettlement objectives have been generally met. Involve the affected people and community groups in assessing the impact of land acquisition for monitoring and evaluation purposes. . Identify the strengths and weaknesses of the land acquisition/resettlement objectives and approaches, implementation strategies. . To review and verify the progress in land acquisition/resettlement implementation of sub- projects on a sample basis and prepare bi-annual reports for the GON and ADB. . To assess the effectiveness and results achieved for livelihood restoration program, quality of relocation sites.

49 Nepal Electricity Connectivity and Energy Efficiency Project SSTA 7176 NEP:LARP

Time Frame and Reporting

The independent monitoring agency or consultant will be responsible for overall monitoring of both the Government and will submit biannual review directly to ADB and determine whether resettlement goals have been achieved, more importantly whether livelihoods and living standards have been restored/ enhanced and suggest recommendations for improvement.

Qualifications

The monitoring agency will have significant experience in resettlement policy analysis. Further, work experience and familiarity with all aspects of resettlement operations would be desirable. Candidates with degrees in anthropology, sociology, and development studies will be preferred.

Interested agencies/consultants should submit proposal for the work with a brief statement of the approach, methodology, and relevant information concerning previous experience on Monitoring of resettlement implementation and preparation of reports. The profile of agency along with full CV of monitors to be engaged must be submitted along with the proposal. The agency must be an established organization registered with Government of Nepal.

Budget and Logistics

Three copies of the proposal - both technical and financial - should be submitted and the budget should include all cost and any other logistics details necessary for resettlement monitoring. Additional expense claims whatsoever outside the budget will not be entertained.

Cost Estimate for External Monitoring and Evaluation

S.N. Items Rate Duration Amount (NRs. Per Month) (Months) NRs. 1 Independent M&E Expert 150,000 2 300,000 2. Engineer 100,000 2 200,000 3 Mobilizers/Field Worker 30,000 1 30,000 4 Field Allowance LS LS 50,000 5 Vehicle LS LS 50,000 6 Stationeries LS LS 25,000 Total 475,000 Contingency (10%) 47,500 522,500

50