ROAD SECTOR DEVELOPMENT PROJECT Additional Financing (IDA Credit No. 5002-NP) Implementation Review and Support Mission September 1-22, 2016 AIDE-MEMOIRE I. Introduction and Acknowledgment 1. A World Bank review team1 (see Annex-1a provides the team members’ list) led by Farhad Ahmed carried out an implementation review from September 1-22, 2016 on the Road Sector Development Project (RSDP). The review had following objectives: (i) assessing the project status and identify the key implementation issues, especially identify measures required to conclude few remaining activities; (ii) identifying and agreeing with the Government of (GON) on the future course of actions that will be necessary for achieving satisfactory results as envisaged in this project; (iii) assessing the readiness of the activities that will be undertaken under the forthcoming second additional financing of the project; and (iv) discussing and agreeing on the various activities linked to the preparation of an Implementation Completion and Results Report (ICR) of the Project. 2. The Team would like to thank GON for the hospitality extended to it, especially by counterpart agencies and officials (Annex-1b provides the list of persons met). This Aide-Memoire (AM) summarizes main review findings, agreements reached, and recommendations made. It also reflects discussions held in a wrap-up meeting chaired by Mr. Dhana Bahadur Tamang, Secretary, Ministry of Physical Infrastructure and Transport (MoPIT) on September 22, 2016. The Team has debriefed the Ministry of Finance on review findings on September 10, 2016. As per the Bank's Access to Information policy and the wrap-up meeting decision, this AM will be classified as a public document. II. Key Project Data 3. The following table provides the summary project data and the summary performance ratings: Project Data Project Performance Ratings Board Approval (original) December 6, 2007 Summary Ratings Last Now Trend Board Approval (AF) June 2, 2011 Review Effectiveness Date (original) February 21, 2008 Achievement of PDO MS MS ▲ Effectiveness Date (AF) July 8, 2011 Implementation Progress S S ◄► Closing Date (original) December 31, 2013 Project Management S S ◄► Closing Date (AF) June 30, 2017 Procurement S S ▲ Credit/Grant Amount SDR 76.1 million2 Financial Management MS MS ◄► Amount Disbursed (as of SDR 64.71 million Safeguards S S ▲ September 30, 2016)3 ($99.10 million; M&E S S ▲ approx. 90%) Counterpart Funding S S ◄►

Notes: AF-Additional Financing; S-Satisfactory; MS-Moderately Satisfactory; MU –Moderately Unsatisfactory; U-Unsatisfactory; ▲Improving Trends; ▼ Deteriorating Trends; ◄► Static. III. Achievement of Project Development Objective Status 4. RSDP is highly likely to achieve its Project Development Objective (PDO). The impact study report encompassing the five roads is now finalized. The studies assessed one of the outcome indicators: reduction in travel time. An analysis, that used the Geographic Information Systems (GIS), has already assessed another outcome indicator-increase in population to all-season roads. The final figures are now confirmed. Department of Roads (DOR) will assess the third outcome indicator-condition of strategic network roads-as part of its normal network monitoring activities. As reported earlier, a road condition survey carried out in November, 2012 showed that 11.27% of black-topped SRN roads were in poor condition (i.e. the end-project target is 15% has been achieved). The next report is expected soon. The

1Hereinafter referred as “The Team” 2 Excludes an amount of SDR 4.5m (US$ 6.75m) cancelled in January, 2015 through a restructuring process. 3 Credit 5002-NP Amount: SDR 13.0million; Amount Disbursed (as of September 30, 2016): SDR 6.28million (48%) Team has advised DOR to submit the latest road condition report as soon as it is finalized. Annex -2 provides the progress details on the achievement of results. The Team has retained the PDO achievement rating as “Moderately Satisfactory”. IV. Current Implementation Status 5. The overall implementation progress rating is retained as “Satisfactory”. Summary details are provided described below. Road Development Component 6. RSDP has achieved all its physical targets under this component. Therefore, the performance of this component has been rated as “satisfactory”. The table below provides the summary progress. All contracts under this component are now complete. DOR plans to take up further road safety related activities on RSDP roads to enhance road safety on these roads. The activities are being planned to be taken up from RSDP savings, owing to depreciation of Nepalese Rupees (NPR) against A completed Surkhet-Jumla road 4 United States Dollar (US$). These activities section would be undertaken as per recommendations of the road safety audit conducted on these roads in December 2013. These proposed activities will complement activities undertaken under the Road Safety Support Project (RSSP). However, DOR is yet to submit a detailed estimate of the savings and the full road safety proposal. It is understood that the savings could be in the region of US$11.0m and the proposed activities would cost roughly US$5.0m. Therefore, there could still be a saving of $6.0m. The Team has advised the DOR to urgently submit savings details and activities it plans to take up with the savings along with costs. Based on the merit of the proposal a decision will be taken. However, DOR was reminded that any potential activities require to be completed by end-June, 2017. It is expected that the project will require a restructuring in order to surrender the excess credit amount. Annex-3 provides the summary progress of the component. Item Rating and Key Points Trend - Accomplishments X- Concerns ☼- Information ☼ RSDP completed all upgrading contracts and upgrading target is Upgrading Satisfactory largely achieved (target -700km; achievement-690 km) Works ◄► ☼ No outstanding issues  Overachieved the periodic maintenance target (target-2,550 km; Periodic Satisfactory achievement-2,595km) Maintenance ◄►  No outstanding issues  All road safety related contracts completed  No outstanding issues Satisfactory Road Safety ☼ The Project is planning to take up more road safety works on ◄► project roads that will complement road safety activities undertaken under RSSP Institutional Strengthening and Policy Reform Component 7. All activities barring one under this component are now complete. The implementation progress under this component is rated as “Moderately Satisfactory” (following table provides key points and Annex-4 assessment details). The design of the road inventory software and collection of

4 Since 2012, NPR depreciated almost a third against the US$. A loan amount of Special Drawing Rights 4.5 million (approximately US$7.0m) was cancelled in early 2015 through a restructuring process.

2 basic road inventory data along the selected road corridor have been completed. However, some activities under a bridge design consultancy contract still remain incomplete (design of 14 bridges on Mugling– Narayanghat Highway section out of total 18). This is as DOR and the consultants could not agree on technical approaches to the design/capacity expansion of those bridges. DOR has agreed to close the bridge consultancy contract by end-October, 2016. It has been agreed that two bridge experts (one expert on bridge design and another expert on concrete prefabrication) will be hired by the DOR to support Bridge Branch in the implementation of Bridges Improvement and Maintenance Program (BIMP) and in the preparation of follow-up project activities. These consultants should possess specialized skills and they need to be hired quickly. Therefore, they could be hired using a Single Source Selection method. While Annex-5 provides status of the agreed actions from last review, Annex-6 presents agreed actions from this review. Item Rating and Key Points Trend -Accomplishments X- Concerns ☼- Information  All component activities are now complete barring one contract  Road inventory software developed and basic road inventory data Institutional Moderately on a sample road corridor collected Strengthening Satisfactory x Design of 14 road bridges on Mugling-Narayanghat road could not and Policy ◄► be completed under a consultancy contract Reform ☼ DOR intends to hire two bridge experts for supporting Bridge Branch Safeguards Performance 8. RSDP's safeguard implementation achievements have been good. The table below summarizes the safeguard performance while the subsequent sections discuss the social and environmental safeguard measures separately. Annex-7 provides details of the safeguard assessment. Item Rating and Key Points Trend - Accomplishments X- Concerns ☼- Information  Excellent overall achievements in social safeguards

Social implementation Satisfactory Safeguards ☼ DOR/division road offices to continue completion of few ▲ remaining works on deed transfer  Bio-engineering works completed in all roads including monsoon damaged roads  Compliance check in Khidkijyula-Manma-Jumla (KMJ) road Environmental Satisfactory completed as well as in Sitalpati-Musikot (SM) road Safeguards ▲ ☼ Mortality rate of plantation was roughly 20%. Necessary re- plantation will be done through contractors or through DOR division offices. Social Safeguards 9. RSDP has made outstanding achievements in implementation of social safeguard measures. It has been rated as ‘Satisfactory’. The project completed almost all of previous review’s agreed actions including those agreed for Sitalpati – Musikot (SM) road. 98% of compensations linked to Resettlement and Rehabilitation (R&R) and Support Allowance (SA) were paid to the project affected persons (PAFs). GON has been trying hard to complete the remaining compensation payments and deed transfer process by June 2017. However, it would be difficult to achieve 100% target given that the remaining PAFs are mainly absentee landowners. DOR has also agreed to prepare a safeguard related implementation completion summary report by mid-November, 2016. Annexes 5 and 6 provide the status of agreed actions during the last review and current review, respectively, while details on safeguard findings have been presented on Annex-7.

3

Environmental Safeguards 10. DOR has made excellent progress in the implementation of environmental safeguard actions. All previous review’s agreed actions have been implemented (see Annex-5). A Safeguard Specialist has joined the Geo-Environmental and Social Unit (GESU) from late-March 2016. DOR has to start re- plantation through contractors, for roads under Surkhet-Jumla road bio-engineering defects liability period, or division offices in the works case of remainder roads.

V. Governance, Accountability and Peace Filter 11. RSDP’s attention to Governance Accountability Action Plan (GAAP) actions continues to be satisfactory including the implementation of Grievance Redressal Mechanism (GRM). A department-wide IT-based grievance redressal system, with tracking and feedback mechanisms, has now been launched. This system is governed by a specific MoPIT approved policy instrument on grievance handling. Annex-9 and 10 provide the detail assessment and status of GAAP respectively. VI. Procurement and Financial Management 12. The Procurement performances have been judged as “Satisfactory”. The table below summarizes the procurement related key points. All contracts are procured and there are no significant issues. Annex-8 provides procurement review details. 13. The review has judged Financial Management performance as “Moderately satisfactory”. Table below summarizes the performance of fiduciary activities. The review has identified a few issues linked to the financial management including: (i) Contract Monitoring System (CMS) is not yet made operational, and (iii) retention money being claimed with IDA before payment to the contractors. Annex-8 provides review details on financial management. Item Rating and Key Points Trend - Accomplishments X- Concerns ☼- Information  RSDP has procured all the contracts and there are no issues Procurement Satisfactory ☼ DOR intends to procure road safety related civil works contracts on ▲ six RSDP roads at an approximate cost of US$5.0m  Project has maintained all required ledgers in required format and they are up-to-date  All statement of expenditure related records and documents are properly maintained and accounted at Project Central Unit (PCU) Financial Moderately  All Financial Management related trainings have been completed Management Satisfactory x Although not paid to contractors, retention money claimed from ◄► IDA x Contract Monitoring System (CMS) yet to be made operational. It has now been proposed to be made operational under RSDP second additional financing (AFII)/BIMP. VII. Key Issues in Implementation 14. Actions that are crucial in achieving project’s objectives are highlighted below: i. Closing the bridge design contract by end-October, 2016; and ii. Submitting saving details of the existing International Development Association credit (No. 5002-NP) and potential road safety related activity details by end-October, 2016 so that saved amount can timely be cancelled through a project restructuring.

4

VIII. Second Additional Financing 15. The World Bank Board has approved a second additional financing to RSDP on August 25, 2016. The total size of the second additional financing is US$65 million, of which the Bank’s and GON’s shares are US$55 million and US$10 million respectively. The financing agreement is expected to be signed as soon as the GON completes all formalities. The closing date of the second additional financing is July 15, 2019. IX. Implementation Completion and Results Report (ICR) 16. An Implementation Completion and Results Report (ICR) for the original RSDP and the first additional financing operations requires to be prepared by November 11, 2016. An ICR Task Team is currently working and has prepared a plan for the report delivery. The Team has also visited two RSDP roads (Surkhet –Khidkijhyula and Chinchu – Jajarkot roads) in the Mid-western Region. The following milestones have been established for the ICR delivery: (a) Receipt of Borrower's draft completion report by September 15, 2016; (b) Finalization of the 1st draft by September 28, 2016; (c) Decision meeting on October 19, 2016; and (d) Board submission on October 27, 2016. DOR has agreed to submit the borrower’s ICR within the agreed date. 17. ICR preliminary messages are: (i) the project had achieved its development objective of providing all-season access and thereby reducing travel time for the residents of the beneficiary districts – five main PDO indicators had either been achieved or exceeded; (ii) the strategic choices of low-cost intervention, and targeting of low-to-medium sized local contractors had both yielded notable results including low unit costs and increased capacity of the local construction industry; (iii) the road standards, the topography traversed, the weather patterns, and the rapid traffic growth dictate the need for special road maintenance arrangements – as noted during the field visit; and (iv) the capacity building component had not only enhanced technical skills in the management of the roads sector but it had also facilitated the institutionalization of other aspects (e.g. social and environmental compliance, and e-procurement). The ICR will take note of the existence of exchange-rate “savings” that would be expended over the period beyond the review cut-off date of June 30, 2016. X. Proposed timing and focus of the next review 18. The next review is planned in early-March, 2017. The review will focus on: (i) assessing the project status and identifying the final issues linked to the implementation of original financing and the first additional financing activities; and (ii) identifying and agreeing on actions that will be necessary for achieving project objectives. The project will require another restructuring to cancel the expected savings under Credit No. 5002-NP, which is expected to be completed before the next mission. A formal request from GON would, however, be required for such a cancellation.

5

ANNEXES

Annex-1a Implementation Review Team (in alphabetical order)

1. Annu Rajbhandari, Environmental Specialist 2. Bibash Shrestha, Team Assistant 3. Dhruba Raj Regmi, Consultant (Capacity Development) 4. Drona Raj Ghimire, Sr. Environmental Specialist 5. Dron Pun, Consultant (Environment) 6. Durga Prasad Khatri (KC), Consultant (Roads) 7. Farhad Ahmed, Sr. Transport Specialist & Task Team Leader 8. Govind Prasad Bhatt, Social Development Specialist (Consultant) 9. Jun Zeng, Sr. Social Development Specialist 10. Justin Runji, Sr. Transport Specialist & ICR Task Team Leader 11. Paul J. Kaiser, ICR Consultant 12. Pradeep Shrestha, Consultant (FM) 13. Prakash J Thapa, Consultant (FM) 14. Ramesh Raj Bista, Procurement Specialist 15. Shambhu Uprety, Sr. Procurement Specialist 16. Shubu Thapa, Professional Associate 17. Yogesh Malla, Financial Management Specialist

Annex P-1

Annex-1b List of Persons Met S. No. Name Position Ministry of Finance (MoF) 1. Dr. Baikuntha Aryal Joint Secretary 2. Mr. Tek Bahadur Khatri Under Secretary Ministry of Physical Infrastructure and Transport (MoPIT) 1. Mr. Dhana Bahadur Tamang Secretary 2. Mr. Bishnu Om Bade Shrestha Joint Secretary Department of Roads (DOR) 1. Mr. Devendra Karki Director General 2. Mr. Sanjaya Kumar Shrestha Deputy Director General, Foreign Cooperation Branch 3. Mr. Ajay Kumar Mull Project Coordinator, RSDP 4. Mr. Rajesh K. Das Unit Chief, GESU/RTU/HMIS-IT 5. Ms. Meera Joshi Environment Specialist, GESU 6. Ms. Rama Shrestha Sociologist 7. Ms. Shubha Shrestha Sociologist, GESU 8. Mr. Rajan Shrestha Environment Expert, GESU 9. Mr. Prabhakar Pandit SSE, GESU 10. Mr. Bibek Pandey Engineer 11. Ms. Sharmila Deshar Engineer 12. Mr. Nabraj K.C Engineer, GESU 13. Ms. Salina Dangol Engineer Supervision Consultant 1. Mr. Mukunda Dahal Highway Engineer SILT Consultants Pvt Ltd 1. Mr. Amresh Jha Consultant 2. Mr. Ajaya Mishra Consultant 3. Mr. Sandeep Chettri Consultant 4. Mr. P. R Pandey Consultant

Annex P-2

Annex-2 ROAD SECTOR DEVELOPMENT PROJECT Progress on the Achievement of Results Implementation Review September 1-22, 2016 PDO Project Outcome Indicators Progress Till Date (September, 2016) Remarks (i) To provide residents of 6 percent increase in population in A GIS analysis with the post-project situation has been beneficiary districts with all project districts to have all season conducted. The results of the analysis show that percent of season road access thereby road access within 20 minutes population in project districts to have all season road access reducing travel time and walking distance (in eight project increased by 6%. improving access to economic districts) centers and social services. 35 percent decrease in journey times A September-2015 socio-economic impact study results to key economic centers in the project show the following: area  50 percent decrease in journey times to key economic centers in the project area 25 percent decrease in journey times  52 percent decrease in journey times to key social to key social services in the project services in the project area area Reduce the percentage of black-top 11.27 % of black-top road in poor condition (report SRN in poor condition to 15 percent November 2012). The next report will be available by end- October, 2016. Intermediate Outcomes Intermediate Outcome Indicators Road Development: Component I (i) Targeted SRN is all weather 100 percent of 700km of target roads 690 km road length (295.00km road length under original sealed gravel road receiving upgrading works project plus 395km under AF) has been upgraded, as of end-December, 2015 (out of which approximately 644km road length upgraded in an Otta–seal standard and 36km in double-bituminous surface treatment (DBST) standard). (ii) Sustainable periodic 100 percent of 2550km of highways A total of 2,595km road length (Out of which 450 km of maintenance of targeted highways received periodic maintenance original financing; 1,728km of Additional Financing and and feeder roads executed 417km of GON funding) has been completed as of end- No backlog periodic maintenance June, 2015. within the project period. (iii) Road Safety Action Plan & Publication and implementation of Road Safety Action Plan has been approved. Plan physical works actions implementation is ongoing.

Annex P-3

PDO Project Outcome Indicators Progress Till Date (September, 2016) Remarks

Institutional Development: Component II (i) Improved staff capacity within HR policy updated and 3-year training Training activities are being undertaken as per the business DOR plan finalized. Domestic and plan. international training provided for DOR staff as per policy and plan (ii) Capacity building in Geo- a) Completion of geo-technical a) Geo-technical assessments have been carried out as technical, Environmental and assessments, b) EMAP and RAP recommended; b) Site specific EMAP and RAP monitoring Social aspects and create compliance monitoring and c) has been done; c) awareness programs on HIV/AIDS awareness on HIV/ AIDS performance in creating awareness among project construction workers and road users have among project construction workers been launched. and road users on HIV/AIDS (iii) DOR IT based MIS Completion of pilot installation of Web based system being adopted for FMIS, GRM, CMS operational wide area network (WAN) in DOR division offices in and satisfactory operation and maintenance of IT based management system (iv) Road asset management tools HDM4 used for bi annual road This indicator will not be achieved as envisaged. Road used for prioritization of road condition assessment and preparation Inventory Software has been developed and collection of maintenance and upgrading works of annual maintenance plan basic road inventory data on a sample road corridor has been completed. (v) Improved quality assurance Quality monitoring plan prepared The Central Road Lab has been carrying out internal quality each year and quality audit carried out audits of selected roads. Quality assurance has been by Central Road Lab monitored. (vi) Improved effectiveness of RBN Act amended and more training RBN has reinitiated to amend the Act. Earlier, the RBN Act Roads Board Nepal and logistics provided was tabled in the Parliament and under discussion in the

Government decision to benchmark Parliamentary sub-committee but was returned back for salaries to market rates resubmission. RBN has prepared five year business plan (2012-2017), and submitted to the Board. Human resource development (HRD) plan has been incorporated in RBN business plan

Annex P-4

PDO Project Outcome Indicators Progress Till Date (September, 2016) Remarks (vii) Third party technical audit Third party technical audit carried out Third Party Technical audit of upgrading and periodic for 20 percent of the project works maintenance works under RSDP has been carried on the each year selected contracts.

Annex P-5

Annex-3 Summary Progress of Road Development Component

Upgrading Sub-Component Contract Physical Financial Length Original Estimated Road Name Contract No. Amount Progress Progress Status (km) Cost (NPR) (NPR) (%) (%) Original Financing Satbanjh- RSDP/NCB/STJ/01 11.32 90,341,015 63,950,056 100 98 DLC issued Tripurasundari Road RSDP/NCB/STJ/02 11.15 92,473,660 76,996,094 100 98 DLC issued Satbanjh-Gokuleswor RSDP/NCB/SG/07 19.00 166,184,140 173,312,973 100 103 DLC issued Road RSDP/NCB/SG/8A 9.70 86,270,440 93,892,775 100 101 DLC issued RSDP/NCB/SG/8B 9.58 81,021,374 70,606,751 100 102 DLC issued RSDP/NCB/SG/16A 8.72 149,873,405 107,323,879 100 99 DLC issued RSDP/NCB/SG/16B 5.97 61,166,637 45,248,327 100 98 DLC issued Khodpe-Bajhang RSDP/NCB/KJC/09 19.90 183,861,969 182,719,819 100 101 DLC issued Road RSDP/NCB/KJC/10A 10.20 10,795,083 83,211,467 100 100 DLC issued RSDP/NCB/KJC/10B 9.80 81,396,150 68,019,339 100 102 DLC issued RSDP/NCB/KJC/11A(Re) 10.00 108,062,284 89,625,994 100 99 DLC issued RSDP/NCB/KJC/11B(Re) 10.42 125,004,162 110,566,198 100 98 DLC issued Surkhet- RSDP/NCB/SKM/3A(Re) 21.70 82,989,690 79,256,357 100 100 DLC issued KhidkijyulaRoad RSDP/NCB/SKM/3B(Re) 22.26 114,440,390 106,909,396 100 100 DLC issued RSDP/NCB/SKM/4 28.84 175,299,702 165,213,597 100 100 DLC issued RSDP/NCB/SKM/5A(Re) 13.40 83,897,217 90,345,941 100 100 DLC issued RSDP/NCB/SKM/5B(Re) 13.90 98,056,491 104,495,004 100 100 DLC issued RSDP/NCB/SKM/6A(Re) 14.00 102,782,543 92,441,613 100 101 DLC issued RSDP/NCB/SKM/6B(Re) 12.34 109,764,476 99,602,606 100 100 DLC issued Tallodhungeswor- RSDP/NCB/TSD/12 8.22 72,829,511 72,564,694 100 100 DLC issued Dailekh Road RSDP/NCB/TSD/13 11.86 84,075,182 87,707,608 100 98 DLC issued

Annex P-6

Contract Physical Financial Length Original Estimated Road Name Contract No. Amount Progress Progress Status (km) Cost (NPR) (NPR) (%) (%) RSDP/NCB/TSD/14 11.79 71,936,603 74,408,241 100 100 DLC issued RSDP/NCB/TSD/15(Re) 0.87 15,630,080 18,091,498 100 97 DLC issued Total (Original) 294.94 2,248,152,204 2,156,510,227 Additional Financing Gokuleshwor- RSDPAF-W-UP-ICB-GD- 18.50 176,216,312 150,101,017 96.68 96.37 Completed & Final Account is Darchula Road 1A settled. DLC is recommended for DOR’s approval. RSDPAF-W-UP-ICB-GD- 13.50 178,187,823 155,243629 98.89 98.35 Completed & Final Account is 1B settled. DLC is recommended for DOR’s approval. RSDPAF-W-UP-ICB-GD- 15.00 174,197,414 170,217,329 95.88 96.16 Completed & Final Account is 2A settled. DLC is recommended for DOR’s approval. RSDPAF-W-UP-ICB-GD- 25.00 195,010,653 184,593401 96.20 95.45 Completed & Final Account is 2B settled. DLC is recommended for DOR’s approval. Khodpe- Chainpur RSDPAF-W-UP-ICB-KC- 15.60 179,599,471 177,817,831 99.94 98.67 Completed & DLP is over. Road 3A Final account not submitted. RSDPAF-W-UP-ICB-KC- 15.50 166,344,499 141,636,605 99.55 99.25 Completed & DLP is over. 3B Final account not submitted. RSDPAF-W-UP-ICB-KC- 15.18 162,962,092 148,787,083 99.30 98.82 Completed & Final Account is 3C settled. DLC is recommended for DOR’s approval. Sitalpati-Musikot RSDPAF-W-UP-ICB-SM- 22.85 182,751,523 157,932,753 96.28 96.45 Completed & Final Account is Road 4A settled. DLC is recommended for DOR’s approval. RSDPAF-W-UP-ICB-SM- 22.5 184,782,778 180,485,979 100.00 99.65 Completed & Final Account is 4B settled. DLC is recommended for DOR’s approval. RSDPAF-W-UP-ICB-SM- 19.5 188,416,632 179,394,804 100.00 99.92 Completed & Final Account is 4C settled. DLC is recommended for DOR’s approval.

Annex P-7

Contract Physical Financial Length Original Estimated Road Name Contract No. Amount Progress Progress Status (km) Cost (NPR) (NPR) (%) (%) RSDPAF-W-UP-ICB-SM- 20.62 194,709,531 177,900,489 99.00 100.00 Completed & Final Account is 4D settled. DLC is recommended for DOR’s approval. Chhinchu-Jajarkot RSDPAF-W-UP-ICB-CJ- 20.00 151,058,590 134,038,244 100.00 94.14 Completed & Final Account is Road 5A settled. DLC is recommended for DOR’s approval. RSDPAF-W-UP-ICB-CJ- 24.60 171,945,318 153,083,967 100.00 97.13 Completed & Final Account is 5B settled. DLC is recommended for DOR’s approval. RSDPAF-W-UP-ICB-CJ- 16.00 194,166,098 174,254,646 95.42 95.90 Completed & Final Account is 5C settled. DLC is recommended for DOR’s approval. RSDPAF-W-UP-ICB-CJ- 20.01 201,006,071 183,895,797 96.22 96.50 Completed & Final Account is 5D settled. DLC is recommended for DOR’s approval. Khidkijyula-Jumla RSDPAF-W-UP-ICB-KJ- 14.56 193,595,644 179,685,073 86.75 95.05 Completed and DLP is Road 6A awarded with LD. RSDPAF-W-UP-ICB-KJ- 13.66 193,198,765 151,484,253 95.16 94.10 Completed and is under DLP. 6B RSDPAF-W-UP-ICB-KJ- 14.00 194,380,592 163,014,303 93.24 97.11 Completed and is under DLP. 6C RSDPAF-W-UP-ICB-KJ- 12.00 198,232,868 162,861,945 91.60 95.98 Completed and DLP is 6D awarded with LD. Khidkijyula-Jumla RSDPAF-W-UP-ICB-KJ- 12.00 182,746,724 174,009,212 96.72 96.49 Completed and is under DLP. Road 7A RSDPAF-W-UP-ICB-KJ- 14.00 201,686,219 192,011,48 96.75 98.33 Completed and is under DLP. 7B RSDPAF-W-UP-ICB-KJ- 14.00 194,613,809 168,149,452 78.83 97.57 Completed and is under DLP. 7C RSDPAF-W-UP-ICB-KJ- 15.98 193,611,531 182,598,587 96.80 98.61 Completed and is under DLP. 7D RSDPAF-W-UP-ICB- 18.61 240,159,643 202,610,335 96.64 95.86 Completed and is under DLP. SKM-8A (Re)

Annex P-8

Contract Physical Financial Length Original Estimated Road Name Contract No. Amount Progress Progress Status (km) Cost (NPR) (NPR) (%) (%) Monsoon-damaged RSDPAF-W-UP-ICB- 13.21 144,915,924 111,820,717 80.10 97.14 Completed and DLP is Sections TSD-8B (Re) awarded with LD. 2013 Monsoon RSDPAF-W-UP-NCB- 56.00 121,172,634 85,875,949 81.64 89.72 Completed and TOC is under damaged works in GD-MD-1 process. Baitadi-Darchula and RSDPAF-W-UP-NCB- 16.00 117,293,293 92,003,892 58.60 75.19 Completed and TOC is under Khodpe-Chainpur GD-MD-2 process. (Bajhang) Roads RSDPAF-W-UP-NCB- 46.28 145,518,647 98,073,015 74.11 73.69 Ongoing KC-MD-3 Contract completion date is 8th August, 2015. Although contractor has already completed structural works but due to lack of bituminous equipment he is unable to carry out pavement works. DOR reported that contractor has promised to mobilize bit equipment by 27 February, 2016. However, DOR is advised to take contractual actions urgently Notes: DLC – Defect Liability Certificate; DLP – Defects Liability Period; TOC – Taking-over Certificate; APG – Advance Payment Guarantee; LD – Liquidated Damage

Periodic Maintenance Sub-Component

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) RSDP Original (First Year) Nagarjun-Tandi RSDP-FYPM-NT-NCB-01 9.78 16,850,313 17,575,983 100 87 Completed Pipalbot-Naubise-Simle RSDP-FYPM-PNS-NCB-02 21.64 78,629,437 68,380,328 100 92 Completed

Annex P-9

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) Mugling Bridge-Anbukhaireni- RSDP-FYPM-MAG-NCB-03 31.91 45,320,309 36,403,630 100 93 Completed Gorkha -Kothi RSDP-FYPM-BK-NCB-04 22.54 31,001,373 23,958,949 100 90 Completed Hetauda-Pathlaiya-Birgunj- RSDP-FYPM-HPK-NCB-05 25.51 111,444,228 90,991,011 100 97 Completed Kaliya Biratnagar-Duhabi-Itahari RSDP-FYPM-BDI-NCB-06 23.46 48,311,435 41,141,451 100 94 Completed Kakarbhitta-Mawa RSDP-FYPM-KM-NCB-08 20.98 33,017,036 29,505,493 100 86 Completed RSDP Original (Second and Third Year) Fikkal-Pashupatinagar, FikKal- RSDP-STYPM-NCB-01 36.86 50,888,482 50,389,193 100 90 Under DLP Maikhola, Charali-Jamunabari Itahari-Dharan, Duhabi-Itahari RSDP-STYPM-NCB-02 36.62 59,462,186 50,122,681 100 86 Completed Bhedatar-Mughat-Hile RSDP-STYPM-NCB-03 22.38 33,709,362 29,952,755 100 90 Completed Chalnedhunga-Khawa, Hanumante-Sangha,Chovar- RSDP-STYPM-NCB-04(Re) 39.64 50,140,541 44,035,619 85 67 Completed Dashinkali, Mawa-Mugling- Mugling Bridge Tistung District Boarder, Gandak Canal-Junction Old RSDP-STYPM-NCB-05 41.10 52,192,564 44,575,667 100 95 Completed Alignment, Dhanushadham- Janakpur Aanbukhaireni-Dumre&Kotre- RSDP-STYPM-NCB-06 36.58 40,693,019 29,817,620 100 88 Completed Pokhara Tansen-Kaligandaki& MRM- Sakura, Bhairawa RSDP-STYPM-NCB-07 38.06 49,641,193 38,404,030 100 98 Completed of Siddartha Highway Nepalgunj- Kohalpur&NuwariKhola- RSDP-STYPM-NCB-08(Re) 21.38 42,584,745 35,420,001 100 70 Completed Surkhet Budar-Gaira RSDP-STYPM-NCB-09 22.08 25,674,247 19,961,480 100 89 Completed RSDP - Additional Financing (First-year Periodic Maintenance)

Annex P-10

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) (Chihanedanda RSDPAF-W-FYPM-NCB-ER- 10 23.56 34,146,861 25,382,209 20 Contract Terminated to Fikkal ) Ilam-1A Mechi Highway (Chureghanti RSDPAF-W-FYPM-NCB-ER- 32.14 46,599,131 34,172,940 11 10 Contract Terminated to Ranke ) Ilam-1B Birtamod- Chandragadhi Road RSDPAF-W-FYPM-NCB-ER- &Mechi Highway Charali – 26.31 39,464,911 34,017,948 100 99 Completed Damak-2A Buddhabare RSDPAF-W-FYPM-NCB-ER- East West Highway (MRM) 21.00 35,699,256 26,039,225 100 98 Completed Damak-2B Inaruwa-Kaptangunj-Sahebgunj RSDPAF-W-FYPM-NCB-ER- 7.00 10,499,402 9,497,887 100 90 Completed Road Biratnagar-2C RSDPAF-W-FYPM-NCB-CR- ARM (Lamidanda-) 13.75 32,920,149 22,141,385 100 100 Completed -1A –Punyamata- RSDPAF-W-FYPM-NCB-CR- Road, Sallaghari – Duwakot 25.32 39,232,329 34,246,031 100 100 Completed Bhaktapur-1B Road, &KhawaLamidanda, Galtchi Junction- Trishuli RSDPAF-W-FYPM-NCB-CR- 44.55 87,686,296 73,125,044 100 96 Completed Bridge –MawaKhola, Bharatpur-2A RSDPAF-W-FYPM-NCB-CR- Mungling- Narayanghat Road, 15.10 108,970,825 90,093,043 100 100 Completed Bharatpur-2B Lamidanda-Bhainse , Palung- RSDPAF-W-FYPM-NCB-CR- Symbhanjyang , Tistung 26.22 50,552,339 37,781,703 100 93 Completed Hetauda-3A (Kunchal)- Palung Bhaise-Bhimphedi and Bhaise- RSDPAF-W-FYPM-NCB-CR- 20.00 27,542,885 19,707,512 100 100 Completed Samari Hetauda-3B RSDPAF-W-FYPM-NCB-CR- Bardibas-Jaleshwor Road 13.70 35,341,650 19,578,886 100 97.50 Completed Janakpur-3C RSDPAF-W-FYPM-NCB-CR- Kakani- Tandi, 23.53 36,709,621 26,942,265 100 100 Completed Nuwakot-4A Banepa-Sindhuli-Bardibas RSDPAF-W-FYPM-NCB-CR- 18.00 31,053,257 23,868,009 100 100 Completed Road, Banepa-Sindhuli-4B Banepa-Sindhuli-Bardibas RSDPAF-W-FYPM-NCB-CR- 21.60 35,997,626 19,174,457 100 100 Completed Road, Banepa-Sindhuli-4C

Annex P-11

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) Contract terminated (Byas for Employer’s Municipality Border-Kotre) RSDPAF-W-FYPM-NCB- 17.83 24,851,240 19,318,413 78 75 convenience; Dumre-BesisaharRoad (District WR-Damauli-1A Completed Length Boundary -Besisahar) considered-12km. M.R.M Chandrauta-Dhankhola Road & M.R.M Chandrauta- RSDPAF-W-FYPM-NCB- 30.05 45,132,865 31,129,913 100 100 Completed Bahadurgunj-Krishnanagar WR-Shivapur-1B Road West Highway (i. Narayeni Bridge-Tiger mountain RSDPAF-W-FYPM-NCB- 30.91 39,879,559 27,255,415 100 100 Completed junction, ii. Tiger mountain WR-Butwal-2A junction-Arunkhola section East-West Highway (ArunKhola- Bardaghat&Sukaura-Butwal RSDPAF-W-FYPM-NCB- 24.93 47,622,063 34,474,680 100 100 Completed and Siddharth Highway And WR-Butwal-Palpa-2B BartungTansenRidiTamghas Road Pokhara- Baglung Road (Yamdi Bridge -Sandh Bridge RSDPAF-W-FYPM-NCB- 41.84 67,083,199 51,884,084 100 100 Completed Sector)and WR-Pokhara-3A PokharaSarankotRoad Pokhara- Baglung Road (Sandh RSDPAF-W-FYPM-NCB- Bridge -Kaligandaki Bridge 24.11 34,932,624 26,905,163 100 100 Completed WR-Pokhara-3B Sector) ( Walling -Syanja Sector)and Siddartha RSDPAF-W-FYPM-NCB- 39.71 66,623,745 48,688,639 100 99.4 Completed Highway ( Kuvinde - WR-Pokhara-3C Pokharamun_bdr Sector) East West Highway RSDPAF-W-FYPM-NCB- 38.90 58,103,246 37,220,343 100 100 Completed (DhanKhola to Lamahi ) MWR-Dang-1A

Annex P-12

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) Nepalgunj – Gulariya Feeder RSDPAF-W-FYPM-NCB- 35.22 75,855,534 44,665,271 100 95 Completed Road MWR-Nepalgunj-1B Mohan to RSDPAF-W-FYPM-NCB- Boradandi&Godawari to 61.10 51,159,692 36,334,579 100 94 Completed FWR-Mahendranagar-1A Faltude (Faltude- RSDPAF-W-FYPM-NCB- 42.20 49,815,624 33,618,506 100 100 Completed Budar&Gaira -Syaule) FWR-Doti-1B Total contracted length in Km. excluding terminated 662.88 Total FYPM Completed Length in Km 657.05 contracts RSDP Additional Financing(Second-year Periodic Maintenance) Birtamod (MRM)-Sanischare- RSDPAF-W-SYPM-NCB-ER- 12.16 19,447,706.52 16,541,779 100 100 Completed Budhbare Damak-1A(Re) Fikkal-Maikhola, Ranke- RSDPAF-W-SYPM-NCB-ER- 26.03 42,947,715.90 29,633,334 14 10 Contract terminated Phidim Ilam-1B Base Camp-Bhedetar, Urlabari (MRM)-AambariChowk, RSDPAF-W-SYPM-NCB-ER- 30.29 49,154,537.04 34,617,403 100 100 Completed AambariChowk-Bardanga, Biratnagar-2A Dharan-Chatara-Barahachhetra RSDPAF-W-SYPM-NCB-ER- Mulghat-PatleKhola 8.50 18,362,526.83 14,377,6212 100 100 Completed Dhankuta-2B Chauraharwa-Mirchaiya, RSDPAF-W-SYPM-NCB-ER- Siswari Bridge-Cement 26.77 35,748,205.11 27,942,123 100 95 Completed Lahan-3A Factory, Kanchanpur-Fattepur Army Camp-Nagarkot, (ARM)- PalanchowkBhagawati, RSDPAF-W-SYPM-NCB-CR- 18.00 28,800,422.69 28,306,443 100 100 Completed LankuriBhanjhyangPanauti- Bhaktapur-1A -DSRM, Bakhandol (ARM)-Bogatigaon Sinamangal-Manahora-Thimi- Sallaghari, Kausaltar-Balkot- RSDPAF-W-SYPM-NCB-CR- 9.59 40,858,635.95 38,062,878 100 100 Completed Sirutar-Biruwa, Thimi(ARM)- Bhaktapur-1B Bode-Karkigaun,

Annex P-13

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) Chyamasingh-Amaldol, Amaldol_nala-Banepa Sopyang District Boarder- Naubise, Naubise-Galchi, RSDPAF-W-SYPM-NCB-CR- Aanptari-Devghat, 41.99 57,665,618.83 46,821,815 98 60 Completed Bharatpur-2A Malekhu_Dhadingbesi, Bharatpur bypass Contract terminated for Employer’s RSDPAF-W-SYPM-NCB-CR- convenience. Thulokh- Kalanki 7.68 11,190,244.22 11,951,457 85 65 Nuwakot-2B Completed Length considered-6.82km.

Hetauda-Samari, lamidanda- Symbhanjhyang, RSDPAF-W-SYPM-NCB-CR- 27.93 56,305,244.15 39,306,984 31 Completed Syambhangjhyang-Palung, Hetauda-3A 100 Palung-Tistung Dharapani(MRM)- RSDPAF-W-SYPM-NCB-CR- Dhanushadham-Janakpur, 27.00 56,685,051.42 35,066,279 100 69 Completed Janakpur-3B Bardibas(MRM)-Jaleshwor Lamosangu-Ningaledanda, RSDPAF-W-SYPM-NCB-CR- 52.00 62,399,391.61 49,961,662 100 90 Completed Ningaledanda-Charikot Charikot-4A RSDPAF-W-SYPM-NCB-CR- Sindhuli-Khurkot 12.50 22,277,737.42 21,267,887 95 45 Completed Banepa-Sindhuli-4B Peeplamod-Naghdhunga, Kalanki-Tripureshwor, RSDPAF-W-SYPM-NCB-CR- Tripureshwor-Balaju, Balaju- 7.85 51,102,059.88 55,876,230 100 100 Completed Kathmandu-5A Balaju Bypass, Naghdhunga- Tankwshwor Baniyatar-Samakhushi- RSDPAF-W-SYPM-NCB-CR- Lainchor, Chhuchepati- 8.70 50,187,336.92 51,244,969 100 100 Completed Kathmandu-5B Mahankal-Kapan-Dandagaon Satdobato-Karmanas Bridge, RSDPAF-W-SYPM-NCB-CR- Karmanas Bridge-Godavari, 13.78 37,236,000.00 35,410,692 100 100 Completed Lalitpur-6A Godavari-Botanical Garden

Annex P-14

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) Junction, Thimi-Lokanthali- Tikathali-Manohara, Balkhu- Satdobato-Manohara Gwarko-Lubhu, Lubhu- RSDPAF-W-SYPM-NCB-CR- 8.72 50,576,000.00 37,819,289 100 100 Completed Lamatar Lalitpur-6B Narayani Bridge-Junction, RSDPAF-W-SYPM-NCB- Bardaghat-Pratappur, 33.38 31,998,356.81 34,575,404 100 100 Completed WR-Butwal-1A Bardaghat-Pratapur Gorusinghe-Chanauta, RSDPAF-W-SYPM-NCB- Patharkot-Kapilvastu district 32.81 49,214,144.77 38,042,923 100 100 Completed WR-Shivapur-1B border-ThadaJungen Bartung-Batasedanda-Harthok, RSDPAF-W-SYPM-NCB- 22.61 36,171,631.79 32,225,241 100 100 Completed Ghumti-Tamghas WR-Palpa-2A(Re) Kotre-BijayapurKhola, RSDPAF-W-SYPM-NCB- Kaligandaki-, Pokhara- 39.09 62,125,818.08 46,668,468 100 100 Completed WR-Pokhara-2B PrithibiChowk Dumre-Muse Khola, Dumre- RSDPAF-W-SYPM-NCB- Bandipur, Khairenitar-Bhimad- 17.78 24,419,932.10 25,104,757 100 100 Completed WR-Damauli-2C Ghumarighat Lamahi-Ameliya. Lamahi- RSDPAF-W-SYPM-NCB- Tribhuvannagar Municipality 30.00 59,998,854.74 47,087,450 100 100 Completed MWR-Dang-1A boundry Shiva Khola-KhaireKhola, RSDPAF-W-SYPM-NCB- 45.62 82,097,222.18 54,925,635 100 100 Completed KhairiKhola-Kohalpur MWR-Nepalgunj-1B Borandandi-Attariya, Attariya- RSDPAF-W-SYPM-NCB- 14.33 21,472,426.82 15,525,786 100 100 Completed Godavari Bridge FWR-Mahendranagar-1A Syaule-Bhalumara, Syaule RSDPAF-W-SYPM-NCB- Completed Bazar-Korayal, Silgadhi-Dist. 41.89 69,037,250.92 64,386,242 100 70 FWR-Doti-1B Boarder Anarkholi-Khodpe, Khodpe- RSDPAF-W-SYPM-NCB- 30.41 39,509,426.14 31,037,471 100 85 Completed Patan FWR-Baitadi-1C Total contracted length in Km. excluding terminated 621.38 Total SYPM completed Length in Km 620.34 contracts

Annex P-15

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) RSDP Additional Financing(Third-year Periodic Maintenance) Mechi Highway (Ho7), Ranke- RSDPAF-W-TYPM-NCB-ER- Phidim Sector (Chainage 15.36 30,717,968.55 22,753,991 100 100 Completed Ilam-1A 166+200km to 181+560km) Damak (MRM) – Beldangi RSDPAF-W-TYPM-NCB-ER- Refugee Camp Road (Ch. 7.00 18,680,209.49 13,238,145 100 100 Completed Damak-1B 0+000km to 7+000km) Mawa – Harichamode Road (Ch: 58+000km to 65+000km) RSDPAF-W-TYPM-NCB-ER- & Rani (IB) – Kanchanbari 12.20 46,108,754.04 30,327,765 100 100 Completed Biratnagar-1C Road (Ch. 0+000km to 5+200km) Mirchaiya – Kamala (H0119, Ch. 223+920km to RSDPAF-W-TYPM-NCB-ER- 237+240km) and Chauharwa – 31.53 77,523,426.17 46,250,496 100 100 Completed Lahan-2A (Re) Siraha (F00501, Ch. 0+000km to 18+210km) Jyamire (District Border)- RSDPAF-W-TYPM-NCB-ER- Katari Road (F05202,km 7+000 20.00 49,777,411.30 34,210,529 100 100 Completed Lahan-2B tokm 27+000) Contract terminated for Employer’s Nagdhunga – Kalanki (Ring RSDPAF-W-TYPM-NCB-CR- convenience. 4.50 31,679,337.97 25,924,830 56 43 Road) Kathmandu-3A Completed Length considered-2.30km.

Nagarjun - ThuloKhola, Halchow- Narayanthan Ongoing Balaju Nepal Sangla Bazar RSDPAF-W-TYPM-NCB-CR- 24.40 99,506,916.02 85,669,991 48 20 Completed length Jayanepal – Thapathali Kathmandu-3B considered- 8.60km. Kalimati – SitapailaJadibuti – Pepsikola – ManoharaThimi RSDPAF-W-TYPM-NCB-CR- Bhaktapur –Army Camp 11.60 58,006,045.16 45,248,212 100 100 Completed Bhaktapur-5A

Annex P-16

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) Sinamangal – Manohara – Thimi – Sallaghari Panchkhal – PalanchokBhagawati Sallaghari – Hanumante Culvert Contract terminated Barabise – Kodari, Barabise – for Employer’s Kodary, RSDPAF-W-TYPM-NCB-CR- convenience. 40.79 69,940,380.14 53,219,272 35 34 Dolalghat – Lamusangu– Charikot-5B Completed Length barasise consedered-9.10km.

Ramnagar – Mugling, RSDPAF-W-TYPM-NCB-CR- Mawakhola – Mugling 35.16 81,778,094.86 63,760,521 100 63 Completed Bharatpur-6A Bharatpur – Meghauli Airport Tadi – Gangate, Tadi – Labdhu RSDPAF-W-TYPM-NCB-CR- – Samundratar– 11.00 17,591,605.26 16,739,007 100 98 Completed Nuwakot-6B Golphubhanjyang Jitpur- Pathlaiya, Bhimphedi – RSDPAF-W-TYPM-NCB-CR- 21.80 40,415.198.10 26,536,312 100 49 Completed Kulekhani Hetauda-7A Bardibas – Jaleshwor, RSDPAF-W-TYPM-NCB-CR- Dharapani – Dhanusadham – 9.00 19,476,143.60 11,716,409 95 95 Completed Janakpur-7B Janakpur Surajpura – Harpur Border, Butwal Municipality Boundary – Milanchok, Mahendra Park- RSDPAF-W-TYPM-NCB- ChidiyaKhola, Bardaghat – 24.19 37,898,760.03 26,654,494 100 98 Completed WR-Butwal-8A Sunwal Mahakhola – Sukoura, Sunwal– Mahakhola Gorusinghe – Patharkot, AngureGhumti – RSDPAF-W-TYPM-NCB- Sandhakharkka 43.32 77,973,678.52 58,746,638 100 80 Completed WR-Shivapur-8B (Re) ThadaJukena- AngureGhumti, ThadaJukena- AngureGhumti

Annex P-17

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) Damauli – Jyamiretar (Byass RSDPAF-W-TYPM-NCB- Marg) (Ch. 0+000km to 8.73 17,400,000.00 12,029,307 100 100 Completed WR-Damauli-9A 8+730km) Syangja – Kuvinde Road (Ch. RSDPAF-W-TYPM-NCB- 41,195,951.76 18.84 27,051,530 100 100 Completed 148+165km to 167+000km) WR-Pokhara-9B Harthok – Ridi Bridge (Ch. 102,499,356.70 Ongoing. 15+480km to 35+660km) and RSDPAF-W-TYPM-NCB- 52.98 74,816,593 85 65 Completed Length Ridi Bridge – Ghumti (Ch. WR-Palpa-9C considered-43km. 65+660km to 68+460km) RSDPAF-W-TYPM-NCB- KhairiKhola – Kohalpur 23.00 50,849,394.38 32,118,717 100 90 Completed MWR-Nepalgunj-10A (Re) Mahakali Highway (H14) Patan RSDPAF-W-TYPM-NCB- – Satbanjh (Ch. 184+170km to 16.59 28,850,426.09 25,531,351 100 95 Completed FWR-Baitadi-11A 200+760km) Mahakali Highway (Ch. 147+360km to 153+800km ); , Syaule – Korayal (Ch. 12+000km to 25+000km) and Silgadhi – RSDPAF-W-TYPM-NCB- 102,843,829.54 45.93 95,459,388 97 65 Completed Sanfe Road, Silgadhi – FWR-Doti-11B Chaukhutte Bazar (Ch 14+510km to 41+000Km ) &Chaukhutte Bazar – Sanfe (Ch. 41+000km to 51+000km) , BoradadiSukhhadChoraha – Attariya (Ch. 957+400km to RSDPAF-W-TYPM-NCB- 76,115,015.54 44.18 57,294,499 100 100 Completed 967+500km) &Junga – FWR-Mahendranagar-11C SukhadChoraha (Ch. 915+230Km to 949+310km) Total contracted length in Km. excluding terminated contracts 522.10 Total TYPM completed Length in Km 462.43

Annex P-18

Contract Physical Financial Length Estimated cost Road Name Contract No. Amount Progress Progress Status (km) (NPR) (NPR) (%) (%) Total contracted length of Periodic Maintenance under RSDP Total completed length of Periodic Maintenance under 1,887.70 1,739.80 (WB Financing) RSDP (WB Financing) Emergency Maintenance (Monsoon damages)

Latest Physical Financi Name of the Length Estimated Contract Status/ Road Name/ Division Contract No. Progress al Contractor in Km. Cost in NPR Amount Remarks in % Progres in NPR s in % A. Eastern Region (Not Applicable) B. Central Region Bardibas-Sindhuli Bazaar Road Sherpa (T)- Rajav Section of Banepa-Sindhuli- BSBR-09-Per-2070/71 5.00 10,550,757.38 9,135,961 100 81 Completed J.V. Bardibas Road Sallaghari-Katunje-Sumlingtar SAP/ Gauri Ganesh/ DROBKT/337165/4-139 1.92 8,511,072.02 6,731,630 89 80 Completed Road Lama Pragati J.V. SAP/ Gauri Ganesh/ Panauti Road, Kavre DROBKT/337165/4-140 1.50 8,318,685.64 4,984,224 100 80 Completed Lama Pragati J.V. Lama Shrijana Chowk (ARM)- DRO DROBKT/337165/4-141 PragatiNirmaanSew 0.60 2,879,541.79 2,241,734 100 100 Completed Katunje Road a Gatthaghar ARM Thimi, Ghising/ Bright/ DROBKT/337165/4-142 1.00 10,299,577.89 8,220,383 100 100 Completed Chyamasing Amadol road Bijaya J.V. DROBKT/337165/4/ Saptapath Nirman Panauti Khopasi Road, Kavre 1.10 6,666,666.67 4,633,366 25 - Completed 070/71-196 Company Pvt. Ltd. Mangal Bazaar- Pulchowk Bajgain 070/71-135 0.55 4,278,094.19 - 58 58 Completed (Lalitpur) NirmaanSewa

Annex P-19

DROKTM/3371653/ Deshprem Manohara Bridge Shankhamul 1.50 4,606,043.06 3,747,045 100 100 Completed 070/71/208 NirmaanSewa DROKTM/3371653/ Sap Construction Swoyambhu Road 2.00 8,174,604.08 7,214,546 100 20 Completed 070/71/209 Pvt. Ltd. DROKTM/3371653/ Sap Construction Kirtipur 2.67 10,909,559.89 9,632,823 100 20 Completed 070/71/210 Pvt. Ltd. Teku National Trading DROKTM/3371653/ Gauriparbati/ 11,111,04 Sohrakhutte (Bishnumati Link 3.10 13,234,508.38 100 22 Completed 070/71/211 Deshprem J.V. 9 Road) Kesharmahal Thamel Durbar DROKTM/3371653/ Sap/ Gauri Ganesh 11,293,88 1.20 16,332,149.80 100 75 Completed Marg 070/71/212 J.V. 4 SunaulaKhimti Ratnapark Bhadrakali DROKTM/3371653/ 16,954,54 Construction Pvt. 1.45 19,816,000.56 100 95 Completed MaitigharThapathali 070/71/213 0 Ltd. Sunaula Khimti Gaushala Mitrapark Chabahil DROKTM/3371653/ 38,024,57 Construction Pvt. 8.00 44,392,487.23 100 50 Completed Maharajgunj Balaju Road 070/71/214 0 Ltd. MRM Pathlaiya- Bagmati 106,469,384.7 70,959,46 98/070/71 Raman Pappu 54.00 100 72 Completed Sector 1 5 21,660,53 MRM Lothar- Hetauda Sector 118/070/71 Elite/Shikhar 5.00 34,936,351.25 100 70 Completed 8 DROJKR/337165-4 Raman/ Pappu/ 140,886,307.6 119,283,2 MRM Kamala- Bagmati Sector 76.00 95 80 Completed /070/71-40 Roshan J.V. 5 02 Periodic Maintenance (Asphalt Overlay) East West Highway (MRM) Narayanghat-Lothar DROBHT/3371653/070/ 196,068,560.9 195,759,8 Raman -Ashish J.V. 23.85 100 100 Completed Section, Lothar- Tikauli (20.22 71-066 8 18 Km) and Hakim Chowk- Narayanghat (3.63 Km) C. Western Region DROPKR/3371653- Ashish/ NayaBato/ 35,012,84 Pokhara Urban Road 22.50 48,436,239.35 100 100 Completed PM/070/071 Fewa JV 4

Annex P-20

Kanchharam/ Om Pokhara- Baglung Road, DROPKR/ 3371653- 22,416,80 Construction Pvt. 4.85 29,367,924.53 100 95 Completed Baglung Sector Rehab /070/071-86 8 Ltd., Ktm

DROPKR/ 3371653- Kanchharam Prithvi Highway Kaski Sector 0.95 9,545,763.24 7,035,013 100 100 Completed Rehab /070/071-102 Construction DROPKR/ 3371653- 21,316,08 Prithvi Highway Kaski Sector Danfe Gauchan JV 1.70 21,174,622.00 100 100 Completed Rehab /070/071-219 0 Bajra guru- Siddhartha Highway (H10) DROPLP/ 3373354-108/ 38,798,25 Raymajhi- Daya JV, 27.50 47,764,836.39 90 75 Completed Chidiya KholaBanstari Sector 2070-071 (Re) 3 Rupandehi Prithvi Rajmarga (Muse Khola - Byas Municipality Boundary, DRODML/337165- Ashish/ naya Bato/ 43,910,00 Ch. 121+43- 126+75 and Byas 23.11 45,076,844.48 100 97 Completed 4/070/71-72 Fewa 0 Municipality Boundary- Kotre, Ch.126+75- 144+54) DROSPR/3371653/070/ Amar Construction 18,625,39 Jitpur- Gorusinghe- Chandrauta 16.00 23,572,637.90 100 100 Completed 71-61 Pvt. Ltd. 0 DROSPR/3371653/070/ Baijanath Jitpur- Gorusinghe 4.00 5,744,627.05 4,538,465 100 100 Completed 71-71 NirmaanSewa D. Mid-Western Region MRM (Rihar-Shivkhola 20,428,31 65-070/71 Diwa NirmaanSewa 20.00 30,102,185.95 100 91 Completed Sector) 6 MRM (Dhankhola-Shivkhola 104-070/71 Jaljala/Lumbini J.V. 0.18 9,376,691.77 9,078,572 100 41 Completed Sector) Nepalgunj- Gulariya Road DRONGJ/3371654/70/7 Amar Construction, 17,304,34 (Nandani Mill- Mankhola 11.80 100 73 Completed 1-040 Kathmandu 9 Section) Deuti Bajyai RRM (Kohalpur- Hattisar DRONGJ/3371654/70/7 Nirman Sewa, 2.60 4,613,480 100 100 Completed section) 1-062 Bardiya E. Far Western Region

Annex P-21

DROMNR-337165- Ashish Nirmaan 117,329,594.0 89,580,43 Mahendra Highway 84.00 100 100 Completed 3/070/71-013 Sewa, Chitwan 0 3 Seti Highway Korayal - Samuhagad (Ch. 24+960- 49+690), Samuhagad to Sanfe Completed DRODOT/3371653/070/ Lama Builders- 86,023,63 Junction (Ch. 49+690-57+460) 40.73 92,246,958.67 55 44 (length- 71-006 Biruwa J.V. 6 and Silgadhi Sanfe Road 10km) (Choukhutte to sanfe Section, Ch. 51+000 to 67+000) Total Contracted Length 450.36 Total Completed Length 418.60 Status of Fourth Year (2013/014) Periodic Maintenance contracts funded by RBN

Physical Financial Name of the Length Estimated Latest Contract Status/ Road Name/ Division Contract No. Progress Progress Contractor in Km. Cost in NPR Amount in NPR Remarks in % in % A. Eastern Region (Not Applicable) B. Central Region Bardibas-Sindhuli Bazaar BSBR-09-Per- Sherpa(T)- Rajav Road Section of Banepa- 5.00 10,550,757.38 9,135,961.11 100% 80.93% Completed 2070/71 J.V. Sindhuli-Bardibas Road SAP/ Gauri Sallaghari-Katunje- DROBKT/337165/4 Ganesh/ Lama 1.92 8,511,072.02 6,731,630.35 89% 80% Completed Sumlingtar Road -139 Pragati J.V. SAP/ Gauri Panauti Khopasi Road, Kavre DROBKT/337165/4 Ganesh/ Lama 1.50 8,318,685.64 4,984,223.78 100% 80% Completed -140 Pragati J.V.

Shrijana Chowk (ARM)- Lama Pragati DROBKT/337165/4 0.60 2,879,541.79 2,241,733.60 100% 100% Completed DRO Katunje Road Nirmaan Sewa -141

Annex P-22

Physical Financial Name of the Length Estimated Latest Contract Status/ Road Name/ Division Contract No. Progress Progress Contractor in Km. Cost in NPR Amount in NPR Remarks in % in %

Gatthaghar ARM Thimi, Ghising/ Bright/ DROBKT/337165/4 1.00 10,299,577.89 8,220,382.75 100% 100% Completed Chyamasing Amadol road Bijaya J.V. -142

Saptapath Nirman Panauti Khopasi Road, Kavre DROBKT/337165/4 1.10 6,666,666.67 4,633,365.84 25% Completed Company Pvt. Ltd. / 070/71-196 Mangal Bazaar- Pulchowk Bajgain Nirmaan 070/71-135 0.55 4,278,094.19 - 58% 58% Completed (Lalitpur) Sewa

Manohara Bridge Deshprem Nirmaan DROKTM/3371653 1.50 4,606,043.06 3,747,045.00 100% 100% Completed Shankhamul Sewa / 070/71/208

Sap Construction Swoyambhu Road DROKTM/3371653 2.00 8,174,604.08 7,214,546.20 100% 20% Completed Pvt. Ltd. / 070/71/209

Sap Construction Kirtipur Ring Road DROKTM/3371653 2.67 10,909,559.89 9,632,823.00 100% 20% Completed Pvt. Ltd. / 070/71/210 Teku National Trading Gauriparbati/ Sohrakhutte (Bishnumati DROKTM/3371653 3.10 13,234,508.38 11,111,049.00 100% 22% Completed Deshprem J.V. Link Road) / 070/71/211

Kesharmahal Thamel Durbar Sap/ Gauri Ganesh DROKTM/3371653 1.20 16,332,149.80 11,293,884.00 100% 75% Completed Marg J.V. / 070/71/212 Sunaula Khimti Ratnapark Bhadrakali DROKTM/3371653 Construction Pvt. 1.45 19,816,000.56 16,954,540.00 100% 95% Completed Maitighar Thapathali / 070/71/213 Ltd. Sunaula Khimti Gaushala Mitrapark Chabahil DROKTM/3371653 Construction Pvt. 8.00 44,392,487.23 38,024,570.00 100% 50% Completed Maharajgunj Balaju Road / 070/71/214 Ltd. MRM Pathlaiya- Bagmati 106,469,384.7 98/070/71 Raman Pappu 54.00 70,959,465.00 82% 72% Ongoing Sector 1 MRM Lothar- Hetauda 118/070/71 Elite/Shikhar 5.00 34,936,351.25 21,660,537.78 60% 57% Ongoing Sector

Annex P-23

Physical Financial Name of the Length Estimated Latest Contract Status/ Road Name/ Division Contract No. Progress Progress Contractor in Km. Cost in NPR Amount in NPR Remarks in % in %

MRM Kamala- Bagmati DROJKR/337165-4 Raman/ Pappu/ 140,886,307.6 76.00 119,283,202.49 40% 40% Ongoing Sector /070/71-40 Roshan J.V. 5 Periodic Maintenance (Asphalt Overlay) East West Highway (MRM) Raman -Ashish 196,068,560.9 Narayanghat-Lothar Section, DROBHT/3371653/ 23.85 195,759,818.38 100% 100% Completed J.V. 8 Lothar- Tikauli (20.22 Km) 070/71-066 and Hakim Chowk- Narayanghat (3.63 Km) C. Western Region

Ashish/ NayaBato/ Pokhara Urban Road DROPKR/3371653- 22.50 48,436,239.35 35,012,844.04 100% 100% Completed Fewa JV PM/070/071 DROPKR/ Kanchharam/ Om Pokhara- Baglung Road, 3371653-Rehab Construction Pvt. 4.85 29,367,924.53 22,416,808.36 100% 95% Completed Baglung Sector /070/071-86 Ltd., Ktm DROPKR/ Prithvi Highway Kaski Kanchharam 3371653-Rehab 0.95 9,545,763.24 7,035,013.00 100% 100% Completed Sector Construction /070/071-102 DROPKR/ Prithvi Highway Kaski 3371653-Rehab DanfeGauchan JV 1.70 21,174,622.00 21,316,080.00 100% 100% Completed Sector /070/071-219 Siddhartha Highway (H10) DROPLP/ Bajra guru- Chidiya Khola Banstari 3373354-108/ 2070- Raymajhi- Daya 27.50 47,764,836.39 38,798,253.11 20% 11.50% Ongoing Sector 071 (Re) JV, Rupandehi Prithvi Rajmarga (Muse Khola - Byas Municipality Boundary, Ch. 121+43- DRODML/337165- Ashish/ nayaBato/ 23.11 45,076,844.48 43,910,000.16 100% 97% Completed 126+75 and Byas 4/070/71-72 Fewa Municipality Boundary- Kotre, Ch.126+75- 144+54)

Annex P-24

Physical Financial Name of the Length Estimated Latest Contract Status/ Road Name/ Division Contract No. Progress Progress Contractor in Km. Cost in NPR Amount in NPR Remarks in % in % Amar Jitpur- Gorusinghe- DROSPR/3371653/ Construction Pvt. 16.00 23,572,637.90 18,625,389.63 100% 100% Completed Chandrauta 070/71-61 Ltd.

BaijanathNirmaanS Jitpur- Gorusinghe DROSPR/3371653/ 4.00 5,744,627.05 4,538,464.84 100% 100% Completed ewa 070/71-71 D. Mid-Western

Region MRM (Rihar-Shivkhola Diwa Nirmaan 65-070/71 20.00 30,102,185.95 20,428,316.07 100% 91% Completed Sector) Sewa MRM (Dhankhola- Jaljala/Lumbini 104-070/71 0.18 9,376,691.77 9,078,572.00 100% 41% Completed Shivkhola Sector) J.V. Nepalgunj- Gulariya Road Amar (Nandani Mill- Mankhola DRONGJ/3371654/ Construction, 11.80 17,304,349.06 100% 73% Completed Section) 70/71-040 Kathmandu Deuti Bajyai RRM (Kohalpur- Hattisar DRONGJ/3371654/ Nirman Sewa, 2.60 4,613,479.91 100% 100% Completed section) 70/71-062 Bardiya E. Far Western

Region DROMNR-337165- Ashish Nirmaan 117,329,594.0 Mahendra Highway 84.00 89,580,433.00 100% 100% Completed 3/070/71-013 Sewa, Chitwan 0 Seti Highway Korayal - Samuhagad (Ch. 24+960- 49+690), Samuhagad to

Sanfe Junction (Ch. 49+690- Lama Builders- DRODOT/3371653/ 40.73 92,246,958.67 86,023,636.42 45% 44% Ongoing 57+460) and Silgadhi Sanfe Biruwa J.V. 070/71-006 Road (Choukhutte to sanfe Section, Ch. 51+000 to 67+000) Total Contracted Length 450.36

Annex P-25

Physical Financial Name of the Length Estimated Latest Contract Status/ Road Name/ Division Contract No. Progress Progress Contractor in Km. Cost in NPR Amount in NPR Remarks in % in % Total Completed Length 243.56 Note: All figures indicated above are as of June 30, 2015. After this period RSDP has closed its sharing in Periodic Maintenance. Road Safety (Physical Works) Length Estimated cost (m Contract Physical Financial Road Name Contract No. Comments (km) NPR) Amount Progress (%) Progress (%) RS-NCB- Kath Valley (Pelican Signals) - 8,787,346.94 8,781,550.92 100 100 Completed RTU-2 3/RSDP/RTU PRM/MN/KT ( Safety Barrier) 195 5,800,012.00 4,852,281.92 100 100 Completed 10/11 4/RSDP/RTU PRM (Construction Of Bus Lay Bys) 125 12,011,571.00 9,968,613.21 100 100 Completed 10/11 Chabahil (Construction Of Bus Lay 5/RSDP/RTU - 3,108,590.00 1,798.136.57 100 100 Completed Bys) 10/11 ARM/KT/MN (Supply & Installation 6/RSDP/RTU 196 1,051,435.00 739,409.85 100 100 Completed of Traffic Signs) 10/11 Kathmandu Valley (Traffic Safety 7/RSDP/RTU - 8,959,220.00 8,181,105.31 100 100 Completed Works) 10/11 Kathmandu Valley(Traffic Safety 8/RSDP/RTU _ 8,870,552.00 8,279,990.25 100 100 Completed Works) 10/11 RS-NCB- Completed Road Safety Pilot Project 4 2,372,874,90.00 1,373,731.96 100 100 RTU-9 Footpath & Bus Lay Bys construction RS-NCB- Completed - 10,314,475.61 10,238,648.74 100 100 (PRM) at dumre- Malekhu RTU-10

Annex P-26

Annex-4 Summary Status of Institutional Strengthening and Policy Reform Component All the activities under institutional strengthening and policy reform component have been completed. Long awaited road inventory software development and collection of basic road inventory data on a sample road corridor (Birgunj-Hetauda-Narayanghat-Mugling-Kathmandu--Kodari) has been completed including making the software compatible for Geo-referencing and reconciliation with different activities at a time. However, detailed design of bridges on Mugling-Narayanghat Road could not be completed as planned. Design of only four out of 18 bridges on Mugling-Narayanghat Road could only be completed. Design of RSDP bridges, which include 33 new and 55 maintenance, has been completed. The design of additional four new bridges on earthquake affected districts has also been completed. DOR has been advised to close the contract with the consultant.

Annex P-27

Annex-5 Status of actions agreed during last review (March 2016) Activities Responsibility Deadline Status A. Road Development Component None B. Institutional Development and Capacity Building Component i. Software for DOR/HMIS End- The software for development of road data development of road October, management system for road inventory works data management 2015 developed earlier was made compatible for Geo- system for road referencing and reconciliation with different inventory works activities at a time. 1st phase work under the prepared and basic consultancy has been completed. road inventory data as sample in the selected roads (Birgunj- Hetauda- Narayanghat- Mugling- Kathmandu- Dhulikhel-Kodari) completed. ii. Design of Bridges on DOR/Consultant End- Design of bridges on RSDP roads including 4 RSDP roads and October, new bridges on earthquake affected districts Mugling - 2015 completed but the design of 14 bridges out of 18 Narayanghat planned on Mugling-Narayanghat road couldn’t be completed. C. Safeguards

a. Social Safeguard i. Disburse the PIC/DOR/Divisi February Almost all completed (accomplished 98 percent remaining on Office 2016 in aggregate) compensation, R& R and SA to the affected PAFs of all roads and complete deed transfer of compensated plots.

ii. Handover the unpaid PIC/DOR/Divisi February All grievances have been resolved and compensation on Office/Kalikot 2016 compensation disbursements made satisfactorily (including 1 remaining Humla Jumla in all roads including in the SM sub-project PAF of Khalangad Road Project Bridge in KMJ road) and other financial assistance including impending grievance to the respective Divisions road office with details on affected assets iii. GESU Social Achieved (GESU has made visits to the sub- Safeguard Specialist PIC/DOR/GESU November projects for the purpose) will carry out field 2015

Annex P-28

Activities Responsibility Deadline Status visit to project roads to assess the remaining social safeguard issues through consultation with PAF across the alignment and to address them if any b. Environmental Safeguard i. Compliance check in GESU Completed Compliance check visit was done in June, July KMJ Road and August 2016 ii. Environmental and Project Completed Specialist are recruited on 18 March 2016 Social Consultant at GESU available to support RSDP iii. Removal of Project/ Completed Achieved. Debris/ spoils removed from quarry remaining spoils/ contractor sites in KMJ and other roads(as well as protection debris from some measures such as retaining wall, benching, toe- quarry sites (See protection have been provided) Annex-7 for such quarry) iv. Complete Bio- Project/ GESU Completed Achieved. Tipping and tipping site protection engineering works in works completed in all roads except GD KMJ (Monsoon damages, MD -1 and 2) and KC (MD- 3) packages – where work is ongoing. v. Assessment of Project/ GESU Completed The verification indicates about 80% survival of performance of (use contractor the saplings (about 20% mortality). DOR/RSDP BEWs, need for re- for the roads that will accomplish replantation to compensate for planting, and are under DLP) the lost vegetation through the contractor in DLP replantation where and/or the Division Road Offices. necessary. vi. Enforce H & S, Project Completed Completed sanitation and labor- camp facilities at ongoing work sites in KMJ

D. Procurement

None

E. Financial Management i. Conducting FM December Not yet completed training for all cost 31, 2015 centers ii. Updating contract December Not yet completed Monitoring System 31, 2015 (CMS)

F. GAAP & Peace Filter i. A separate Action DOR See Annex-10 Plan prepared and attached in Annex-10

Annex P-29

Annex-6 Actions agreed during current review (September, 2016) Actions Responsibility Deadline Remarks A. Road Development Component i. Submit potential DOR/FCB End-Oct, 2016 Design, cost estimates and bidding documents linked to road safety saving details of IDA activities are being prepared Credit No. 5002-NP and a road safety activity proposal ii. Award of road safety DOR/FCB End-Dec, 2016 contracts (potentially seven in number comprising six RSDP roads), as agreed with the Bank B. Institutional Development and Capacity Building Component i. Hiring of 2 bridge DOR/FCB/BB End-Dec, 2016 TOR and cost estimates prepared experts for supporting Bridge Branch in preparing upcoming Bridge Project ii. Closure of DOR/FCB End-Oct, 2016  Design for new bridges on RSDP roads including designs for consultancy services maintenance works have been completed for Bridges on RSDP  Design options for 14 bridges on Narayanghat- Mugling road roads and couldn’t be completed Narayanghat- Mugling roads C. Safeguards

Annex P-30

Actions Responsibility Deadline Remarks

a. Social Safeguard i. Completion of the DOR/Division Office/GESU June 2017 DOR plans to accomplish the remaining works (mentioned in Annex remaining works on 7, table 2 below) mobilizing Division Road Office (DRO) teams in deed transfer, etc. as the project area. Required budget has been already allocated to the part of RAP concerned DROs for this purpose implementation ii. GESU/DOR to DOR/GESU Most of the data required for the purpose are available with prepare summarized Nov 15, 2016 GESU/DOR – which will need to be updated/completed including report on those on good practices to prepare the report (to be integrated with implementation of similar report on Environmental aspects) social safeguard measures in RSDP b. Environmental Safeguard i. BEWs replantation GESU/DOR/RSDP There has been about 20 % mortality of plantation done as part of to compensate for June 2017 bio-engineering works. DOR/ RSDP/ GESU plans to do necessary mortality ( through re-plantation contractors in the roads/ contracts Respective DRO will re-plant by June 2017. The contractor s will re- which are under DLP plant before DLP ends and through the respective DOR Re-plantation plan to be ready well in advance (tentatively by division offices in the December 2016) remaining roads) ii. Preparation of Final GESU/DOR Nov 15, 2016 For each RSDP Road, the status report will provide summary of Environmental and environmental and social mitigation works done in site specify Social Safeguard manner. Also highlight good practices, difficulties faced, failures, Implementation and lessons Summary Report Most of information are already available in scattered forms (in AM, in progress reports, in monitoring reports etc). This information may be updated during site visit, if any, carried out from now until October 2016 D. Procurement

Annex P-31

Actions Responsibility Deadline Remarks DOR/FCB Dec 31, 2016 Design, Cost estimates and Bidding documents are being prepared i. Procurement of road safety contracts on seven RSDP roads, as agreed with the Bank DOR/FCB/BB Dec 31, 2016 TOR and cost estimates are being prepared ii. Hiring of 2 bridge experts for supporting Bridge Branch in preparing upcoming Bridge Project

E. Financial Management i. Updating contract DOR June 30, 2017 Planned to update under RSDP AFII Monitoring System (CMS) ii. Calculate retention DOR Oct 30, 2016 money and deduct from next withdrawal application amount iii. Submit audited DOR Jan 15, 2017 Unaudited accounts which was due on October 15, 2016 has not yet financial statements been received. for FY2015/16 F. GAAP & Peace Filter i. A separate Action DOR See Annex-10 Plan prepared and attached in Annex-10

Annex P-32

Annex-7 Summary Findings on Safeguards Social Safeguards Impact and Progress Social safeguard measures in RSDP have been complied satisfactorily in each of the sub-projects. Impressive achievements have been marked in implementation of mitigation measures for adverse impacts while enhancing the beneficial impacts for the project communities in all the project areas (Annex 7b includes some of the good practices implemented by RSDP). Of the total of 3,382 families affected by various activities of the project, 5,458 land plots (807789 sq. m.), 359 structures and 2,546 trees have been recorded and verified as impacted assets as detailed in Table 15 below. Table 1: Impact Across the Project Roads

Losses as per RAP Road Name Losses as per Post Verification Land Land Land Land SN Struc- Tree/ HHs Struct- Trees HHs Plots Area / Area tures Crops ures Crops (m2) Plots (m2) Gokuleshwor 1 –Darchula 244 372 48296 12 2,063 276 440 136498 30 1,227 (GD) 2 GD (EFD)* 50 73 16151 6 478 49 71 16151 6 788 Kalinggard- 3 Chainpur 624 1,220 29057 19 499 624 1,220 92101 12 499 (KC) Khidkijyula- *1,39 4 Manma- 764 1,214 95550 45 206 840 2 286179 **117 0 Jumla(KMJ) Chhinchu- 5 26 30 1066 4 0 26 30 1083 4 0 Jajarkot (CJ) Sitalpati- 6 1,412 2,088 149965 152 435 1,567 2,305 275777 ***190 32 Musikot (SM) Total 3,120 4,997 340085 238 3,681 3,382 5,458 807789 359 2,546

Source: GESU (August, 2016) *EFD=Emergency Flood Damage *Note: six (6) additional land parcels acquired during implementation **Twelve (12) number of affected structures have been increased in this road due to acquisition of structures in bridge location and structures in additionally acquired land. *** The number of acquired structures have been reduced due to change in bridge location, and reduction acquisition scope. The current implementation status of various social safeguard measures has been presented in table 2 below:

5PIC has prepared and updated the list of families affected due to emergency flood damage in the 3 km stretch of GD road, hence, information about the PAF and their affected assets for this section has been categorized separately as GD (EFD)

Annex P-33

Table 2: Summarized Information on Social Safeguard Implementation (August 2016)

Resettlement & Supporting Loss as per verifications Compensation Distribution (Paid) Deed transfer Remaining works Rehabilitation Allowance

S Land Structure Tree/ Crops .

N Road

HHs

b

Plots

AHHs

Structures

Progress% Progress% Progress%

Compensated plot Compensated

Trees/ crops Trees/

Affected Plots Affected Affected Structures Affected Trees/croups DTP progress% HH Affected plots Land plots Land Structures crops Trees/ R R & SA transfer Deed

Total Paid Progress% no. Family Paid no. Progress%

1 276 440 30 1227 276 440 100 30 100 1227 100 30 30 100 13 13 100 440 440 100 0 0 0 0 0 0 0 GD

1. EFD N 49 71 6 788 47 67 94 6 100 788 100 6 6 100 NA NA NA 67 67 100 2 2 0 0 0 0 1 (GD) A

2 KC 624 1220 12 499 616 1189 97 12 100 466 93 12 12 100 58 58 100 1189 1189 100 8 31 0 33 0 0 0

3 KMJ 850 1392 117 0 767 1282 92 107 91 NA NA 117 82 70 95 79 83 1282 1282 100 83 110 10 0 35 16 0

N 4 CJ 26 30 4 0 26 30 100 4 100 NA NA 0 0 0 NA NA NA 30 30 100 0 - 0 0 0 NA A

5 SM 1567 2305 190 32 1285 2074 90 190 100 32 100 190 190 100 127 115 90 2074 1659 80 231 231 0e 0 0 12 415

Total 3392 5458 359 2546 3017 5082 349 2513 359 320 293 265 5082 4667 324 374 10 33 35 28 415

Total Average progress in (%) 96 99 98 94 93 96

Source: GESU, August 2016

Annex P-34

Following paragraphs summarize the status of various other aspects of social safeguard compliance as of August 2016: Local Consultative Forums (LCF) and Grievance Redress: GON approved Environmental and Social Management Framework (ESMF), applicable to RSDP, has provisions for public participation and consultations through formation of Local Consultative Forums (LCFs). Accordingly, LCFs have been formed in all roads. In all there are 30 LCFs in five project roads and so far there have been 60 meetings. It was agreed that for the roads that will be taken over by the project, social mobilizer along with the project staff will conduct a stakeholder meeting with the LCF representatives to inform them about the project closure. Table 3: Status of LCF in RSDP S.N. Project Roads Number of LCFs Formed Total meetings

1 Gokuleshwor-Darchula 3 7 2 GD (EFD)[a] - 3 3 Kalangagad-Chainpur 8 18 4 Sitalpati-Musikot 10 12 5 Khidkijula-Manma-Jumla 5 8 6 Chinchu-Jajarkot 4 2 Total 30 60 Source: GESU, Aug 2016 Table 4: Number of Grievances Registered and Resolved Project Roads Number of Grievances resolved Remaining Grievances S.N. Grievances (as of Nov 2014) (as of Feb, 2016) Registered 1 Gokuleshwor-Darchula 316 316 0 2 GD (EFD)* 57 57 0 3 Kalangagad-Chainpur 500 500 - 4 Khidkijula-Manma-Jumla 700 700 - 5 Chinchu-Jajarkot 0 0 - 6 Sitalpati-Musikot 1,101 1,101 - Total 2,674 2674 0 Source: GESU, Aug 2016 Table 5: Compensation Status of Bridges Being Constructed by DOR in KMJ Road Land (No) Structures (No) S.N Bridges Affected Paid Remaining Affected Paid Remaining Deed Plots Plots Transfer

1 Sherigad Bridge 4 4 7 7 0 4 2 Takulla Bridge - - - 1 1 0 - 3 Khalangad 5 5 0 2 2 0 4 Bridge Total 9 9 0 10 10 0 8 Source: GESU, Aug 2016 Table 6: R&R and SA Status of Bridges Being Constructed by DOR on KMJ Road S.N Bridges Resettlement and Rehabilitation Support Allowance (SA) (R&R) R&R Entitled Paid Remaining Affected Paid Remaining (No) (No) (N0) Structures (No) (No) 1 Sherigad Bridge 7 7 0 2 2 0 2 Takulla Bridge 1 1 0 NA NA NA 3 Khalangad Bridge 2 1 0 NA NA NA Total 10 10 0 2 2 0 Source: GESU, Aug 2016

Annex P-35

Environmental Safeguards Bio engineering works in KMJ including final verification and survival growth: Total bio engineering locations identified under KMJ road is 137 which is approx. 29391m2 (in 10 package of works). All these locations were planted. However, at the current stage on an average overall plantation mortality rate is observed as 20%. Replantation works will take place by respective DOR by June 2017. The contractor will re-plant before DLP ends. Re-plantation plan to be ready well in advance (tentatively by December 2016) Similarly, assessment of performance of BEWs for re-planting, and replantation where necessary i.e. in other road such as Chhinchun- Jajarkot (CJ) and Sitalpati – Musikot Road (SM) plantation survival growth is observed as 85 % and 90% respectively. Bio engineering works in all other RSDP sub projects have been completed. Chainage-wise breakdown of total BEWs identified and plantation done for KJM Road is presented in Annex-7a. BEWs good practices and status of before and after construction works is presented in Annex-– 7b and 7c respectively. Compliance Monitoring: GESU team and consultant has carried out compliance monitoring in KJM during June, July and August 2016 and at SM Road on August 2016. Goluleshwor – Darchula Road (GD- Monson damage MD1 and MD2): MD-1 protection work/reinstatement ie, gabion and masonry wall construction at quarry sites Ch: 82+420, 96+970 and BEWs at Ch: 102+830, 104+150 is complete. MD-2 work i.e. backfilling behind of RCC wall at Namiskar in Mahakali dam and back filling behind of RCC wall for road construction at Galphe is also complete. Similarly, Khodpe – Chainpur Road (KC-MD3), slope protection work is done. Compliance monitoring in all RSDP Road is complete. (Annex-7d) Except the above Bio engineering locations DOR/Consultant has identified 59 new other locations (Approx. 112081sqm) for BEWs in critical areas (landslides and curtail area) under KMJ. Reverification of quantity and location shall be done by DOR/consultant and this project has been transferred to RSDP- AF –II phase.

Annex P-36

Annex-7a Total identified bio engineering works in KMJ road SN Chainage Side S. No. Chainage no. 1 0+630 RHS 73 126+120 RHS h/s 2 0+930 RHS 74 126+120 RHS h/s 3 1+190 RHS 75 126+120 RHS h/s 4 1+250 RHS 76 126+850 RHS h/s 5 1+300 RHS 77 127+070 RHS h/s 6 2+580 RHS 78 127+740 RHS h/s 7 3+140 79 127+950 RHS h/s 8 5+240 RHS 80 128+230 RHS h/s 9 5+550 RHS 81 128+230 LHS h/s 10 6+510 RHS 82 128+300 LHS h/s 11 7+350 RHS 83 128+570 RHS h/s 12 43+884 LHS 84 132+800 RHS h/s 13 44+224 RHS 85 133+490 LHS h/s 14 44+644 RHS 86 134+500 RHS h/s 15 45+644 RHS 87 134+550 LHS h/s 16 49+050 RHS 88 134+550 RHS h/s 17 44+900 RHS 89 135+477 RHS h/s 18 47+650 RHS 90 142+840 V/S h/s 19 52+410 RHS 91 143+850 H/S h/s 20 54+480 RHS 92 144+650 V/S h/s 21 52+556 RHS 93 144+650 H/S h/s 22 52+630 LHS 94 144+700 H/S h/s 23 52+630 LHS 95 144+760 H/S h/s 24 54+430 RHS 96 144+790 H/S h/s 25 54+810 RHS 97 144+820 H/S h/s 26 54+900 RHS 98 144+860 H/S h/s 27 55+090 LHS 99 146+340 H/S h/s 28 57+700 RHS 100 149+640 H/S h/s 29 57+790 RHS 101 156+460.00 LHS h/s 30 57+900 LHS 102 155+470.00 LHS h/s 31 58+450 LHS 103 156+650.00 LHS h/s 32 58+520 RHS 104 156+980.00 LHS h/s 33 58+590 RHS 105 157+700.00 LHS h/s 34 58+855 RHS 106 158+990.00 LHS h/s 35 59+000 RHS 107 159+630.00 LHS h/s 36 59+280 RHS 108 160+120.00 LHS h/s 37 59+300 RHS 109 161+570.00 LHS h/s 38 59+350 RHS 110 164+150.00 LHS h/s 39 59+350 RHS 111 165+270.00 LHS h/s 40 59+855 RHS 112 168+580.00 LHS h/s 41 60+510 RHS 113 180+570 180+580 h/s 42 60+920 RHS 114 196+850.00 196+880.00 LHS 43 74+020 RHS 115 197+000.00 197+040.00 LHS 44 74+020 LHS 116 197+860.00 197+910.00 LHS 45 74+275 RHS 117 198+500.00 198+580.00 LHS 46 74+275 LHS 118 199+400.00 199+460.00 LHS 47 74+930 RHS 119 199+650.00 199+690.00 LHS 48 74+930 LHS 120 199+700.00 199+790.00 LHS 49 76+000 RHS 121 200+000.00 200+070.00 LHS 50 76+070 RHS 122 200+400.00 200+480.00 LHS

Annex P-37

51 76+070 LHS 123 202+700.00 202+740.00 LHS 52 76+310 RHS 124 203+000.00 203+025.00 RHS 53 76+340 RHS 125 203+150.00 203+250.00 RHS 54 76+420 RHS 126 204+300.00 204+600.00 RHS 55 77+950 RHS 127 204+700.00 204+850.00 LHS 56 81+955 RHS 128 205+350.00 205+400.00 LHS 57 82+055 RHS 129 205+500.00 205+550.00 LHS 58 82+780 RHS 130 205+850.00 205+890.00 LHS 59 83+090 RHS 131 205+950.00 206+050.00 LHS 60 83+370 RHS 132 206+150.00 206+200.00 LHS 61 83+550 RHS 133 204+300.00 204+600.00 RHS 62 83+670 RHS 134 204+700.00 204+850.00 LHS 63 85+150 RHS 135 205+350.00 205+400.00 LHS 64 85+350 RHS 136 205+500.00 205+550.00 LHS 65 85+820 RHS 137 205+850.00 205+890.00 LHS 66 85+840 RHS Total Locations: 137 67 87+160 RHS 68 115+040 RHS 69 115+220 RHS 70 126+120 RHS 71 126+120 RHS 72 126+120 RHS

Annex P-38

Annex-7b GOOD PRACTICES Jumla Road

Constructed steps for tatopani taps Constructed steps for access for local Reclaimed the spoil at private land at (religious place) (Jumla) people houses (Jumla) Jumla

KJ-7A, Drain cum wall and steps KJ-7A, Steps constructed for house way KJ-7A, Drain cum wall and Steps constructed for house protection and ch:186+100 at Bhainsegoda constructed for house protection and house way respectively at ch:185+390 house way ch:190+100 at Galje Purano Bali

KJ-7A, Pedestrian Steps constructed for 7B-Drain cum wall and Steps constructed KJ-7B, Drain cum wall and Steps for public way at Galje for house protection and house way house protection ch: 201+890 at ch:195+350 at Dhanada Bhigma

Annex P-39

Gokuleswor –Darchula Road

Ch: 92+800, Constructed gate at Ch:120+300, steps constructed at school Reclaimed the private land as per Ranibash Ama Temple (Pasti) (Janapriya Nimna Madhymik School demand of local people at Sakar

Ch:11+500, Reclaimed the private land Ch: 105+000, Galfai bazzar, increaseed Ch: 66+700, constructed as as per local people demand at Sakar road width 4,5m from 8.0m at district per people demand hospital area including slab cover about 200 to 300m

Ch: 94+400, access road constructed Ch: 66+600, Stockpile area converted into Ch:66+700, Contractor camp and about 100m for quarry owner agricultural land crusher plant yard (playground)

Annex P-40

Chhinchu Jajarkot

Ch:76+500, irrigational canal Chute constructed as per local people Dual purposes: Pipe Culvert & constructed for local people. Benifited demand in Jajarkot (5D)package Irrigation Canal as per public demand population 100 housholdrs (about 50,m) Jajarkot(5D) package

Donated construction materials for Consturucted Bushshed in Change in transprtation pattern in construction of Nageswor temple, 5D, Baluwasangrhi VDC, 5A package Chhinchu jajarkot road package in Jajarkot

Traffic safety parapet block use for dual Drain cover also being used for access Increased tea shops in Bheri purpose, for irrigation canal of length to private houses 5D package (Ferry crossing area) after the 50m,.in Evergad(5D) package in constructed road in Chhinchu technology change

Annex P-41

Annex-7c KMJ Road Bio-Engineering Photographs BEFORE AFTER

SURKHET JUMLA ROAD AT 85+840 SURKHET JUMLA ROAD AT 85+840

SURKHET JUMLA ROAD AT 54+480 SURKHET JUMLA ROAD AT 54+480

SURKHET JUMLA ROAD AT 66+480 SURKHET JUMLA ROAD AT 66+480

Annex P-42

SURKHET JUMLA ROAD AT 66+410 SURKHET JUMLA ROAD AT 66+480

SURKHET JUMLA ROAD AT 54+430 SURKHET JUMLA ROAD AT 54+430

SURKHET JUMLA ROAD AT 76+070 SURKHET JUMLA ROAD AT 76+070

Annex P-43

SURKHET-JUMLA ROAD 2+500 SURKHET-JUMLA ROAD 5+400

SURKHET-JUMLA ROAD 142+800 SURKHET-JUMLA ROAD 146+300

SURKHET-JUMLA ROAD 148+200 SURKHET-JUMLA ROAD 149+300

Annex P-44

Annex-7d The summary table shows the update status of environmental safeguard compliance till August 2016.

S.N Activities Name of Road GD KC SM CJ KMJ Observation 1 Reinstatement of Crusher All 4.no All 3,no All 5.no All 3.no All 15.no Completed Plant Reinstated Reinstated Reinstated Reinstated Reinstated 2 Reinstatement of Reinstated Reinstated Reinstated Reinstated Reinstated Completed stockpiling of construction materials 3 Reinstatement of Bitumen Reinstated Reinstated Reinstated Reinstated Reinstated Completed /chemicals toxic & nontoxic yard 4 Reinstatement of Reinstated Reinstated Reinstated Reinstated Reinstated Completed Labor/contract camps 5 Reinstatement of existing Reinstated Reinstated Reinstated Reinstated Reinstated Completed services public utilities/cultural utilities 6 Excess cut/fill materials All 14. no All 14.no All 15.no All 8.no All 19 no Completed and construction materials reclaimed reclaimed reclaimed reclaimed reclaimed /Spoil disposal (Designated (Designated (Designated (Designated (Designated place) place) place) place) place) 7 Disruption in natural Constructed Constructed Constructed Constructed Constructed Completed water flow managed by damaged damaged damaged damaged damaged construction of water structures structures structures structures structures related structure and cleared and cleared and cleared and cleared and cleared (culverts/causeway/irrigati the derbies in the derbies the derbies in the derbies in the derbies on canal/Hume pipe drain. in drain. drain. drain. in drain. crossing/water supply pipe) 8 Water Management Constructed Constructed Constructed Constructed Constructed Completed (drainage, cross drainage gully protection) 9 Existing Unstable Hill Constructed Constructed Constructed Constructed Constructed Completed Slopes managed by construction of gabion works, stone masonry, embankment, R.C.C pipes etc. 10 Work on quarry ,rock Provided Provided Provided Provided Provided break up etc. (safety gears) 11 Impact/damage on Compensated NA NA NA NA Compensate structures due to use of (1house) d pavement rolling machine managed properly 13 Vegetation removal (tree) NA Private(33n NA ( NA NA Compensate os) d 14 Bio- engineering Done Done Done Done Done Completed work(BEWs) 15 Influx of labor into the NA NA NA NA NA construction site. Disturbance to wild life 16 Illegal hunting & wild life NA NA NA NA NA trade

Annex P-45

17 Fuels for: Labor camp- Provided Provided Provided Provided Provided Provided kerosene, for operation of Kerosene Kerosene Kerosene Kerosene Kerosene crusher plant & bitumen heating-diesel, 18 Exerted pressure due to NA NA NA NA NA use of fuel wood, impacting as loss of forest 19 Slope instability, erosion Done Done Done Done Done 20 Safety measures against Provided Provided Provided Provided Provided Provided accident risks and health 21 Air, Noise, Water NA NA NA NA NA pollution 22 Depletion of Forest NA NA NA NA NA 23 Disturbance to wildlife NA NA NA NA NA movement 24 Blasting NA NA NA NA NA 25 Enhancement Done Done Done Done Done works/issues 26 Awareness/consultation Done Done Done Done Done 27 Road Builders ‘Capacity Done Done Done Done Done Building (workshop) 28 Grievance Redressed Done Done Done Done Done Mechanism Note: NA: Not Available

Annex P-46

Annex-8 Status of Procurement and Financial Management Procurement All goods, works and services contracts under RSDP according to the schedule have been procured. However, Procurement of (i) two bridge experts for supporting Bridge Branch and; (ii) seven road safety related civil works contracts on six RSDP roads are planned to be procured from the savings of RSDP-AF. Financial Management and Disbursement Budget and Expenditure of FY2016/17 The approved budget of FY2016/17 is NPR 4,111.09 million. The recurrent budget is NPR 12.64 million (code 3371423) and the capital budget is NPR 4,098.45million (code 3371424). Of the approved budget, NPR 220.02 million is allocated under the Government source and NPR 3,891.07 million from the IDA credit source. The budget authorizations from MoPIT were received on August 7, 2016 and annual work plan has now been approved by the NPC. However, there was no expenditure until the review date. The review team noted that the Government counterpart fund is sufficient as per information provided by the project. Disbursements Total disbursement as of September 30, 2016 is about USD 99.10 million. This includes designated account advance of USD 3.25 million under the IDA Credit 5002. Financial Management The review team noted that RSDP has maintained the required ledgers including the Designated Account Ledger, cash and bank book, budget sheet, main and subsidiary grant and credit register in required format and they are up-to-date. The review team reviewed supporting documents of statement of expenditures at PCU on sample basis and it was noted that all SOE related records and documents are properly maintained and accounted. The closing balance of Designated Account is tallied with the bank balance as per ledger as on August 29, 2016. The review team noted that the retention money deducted from the construction bills and not paid to the contractors has also been claimed with IDA. The team also reviewed the previous agreed action plans and noted that updating/ operationalizing Contract Monitoring System (CMS) to be completed by May 31, 2016 have not been completed. It has been proposed to implement the CMS under RSDP AFII. The internal audit of the FY2015/16 has been conducted but the reports have not been issued till the date of review. Trimester Implementation Progress Report There are no overdue Implementation Progress Reports (IPRs). The third trimester IPR of FY 2015/16 has also been received. Audit Report The audited project account of FY2014/15 was received with delays. The audit opinion provided by auditor is unqualified. The mission reminded that the audited accounts for FY2015/16 is due on January 15, 2017.

Annex P-47

Annex-9 Governance, Accountability and Peace Filter Governance and Accountability Plan Action (GAAP) An updated status GAAP matrix is presented in Annex-10. RSDP attention to GAAP actions continues to be satisfactory. An IT-based grievance handling system with tracking and feedback elements has now been launched at the Department level. A specific policy instrument on grievance handling approved at the Ministry level will govern the system. The system covers all units within the DOR, including its field-based offices. The performance of the system needs to be monitored adequately. In addition, DOR staff at different levels should be trained on managing the system. A study on the impact of the introduction of e- bidding in DOR is being supported by the Bank under a separate funding source. The impact study has enjoyed good cooperation from DOR in terms of the collection of procurement information since FY 2007/08. The final report of the study is expected to generate informed debates about how e-bidding that could further contribute to improved procurement practices. The National Vigilance Centre (NVC) continues to undertake technical audit of selected projects. The findings of audit and the non-compliance reports (NCRs) are discussed with all stakeholders. NVC also plans to monitor the NCRs. Engagement of social mobilizers in each of the upgrading road sections has been found to be helpful with regard to information dissemination, especially at the community level. An area that needs more management attention is M&E. First, capacity constraints at different levels have affected M&E performance. Whatever capacity is available with DOR needs to be fully used without distinguishing between sources of funds. This should happen within a consolidated framework for M&E procedures for all projects funded through GON sources or DP support. Second, and more important, the M&E framework should also capture project ‘outcomes’ going beyond the emphasis on inputs and outputs. Strengthening M&E efforts will require additional capacity which could be sourced through management innovation such as outsourcing. Peace Filter Policy dialogue: RSDP has opened up opportunities for policy dialogue on public investments in remote regions, which can be expected to contribute to inclusion and employment creation. Given that exclusion and poverty have been the major drivers of conflict in Nepal, RSDP interventions can be considered to be associated with peace. Implementation: RSDP undertakes pro-active communication through web-based, electronic, and print media. It has also carried out 'opinion surveys' which can be used as people's feedback on Project performance. The Project's social safeguard and grievance handling measures are other examples to promote peace and avoid conflict. E-bidding is another innovation, which has helped in preventing security threats during the award of contracts. Suggestions: RSDP should continue to respond to the needs of rural communities. Maintaining impartiality in the selection of projects is another important factor. Enhanced access to information based on information, education and communication (IEC) materials customized to community needs would also be of help.

Annex P-48

Annex-10 Status of Governance and Accountability Action Plan (GAAP)

Agency Issues Actions responsible Timeline Status Organizational Arrangements and Procedures Strengthening accountability Designate staff within PCT and PMUs to be DOR, PCT, By PCT: A K Mull within DOR and its field offices responsible for implementation of GAAP at the Project’s field effectiveness PMU (SKM Road): PM J respective central and field levels offices additional Chaudhary financing PMU (K-C Road): PM L J khanal PMU (BD Road): PM R K Deo PMU (S-M Road): PM SB Ghimire PMU (C-J Road): PM J Chaudhary

Designate staff with PCT and PMUs to be DOR, PCT, By PCT: A K Mull responsible for handling complaints received Project’s field effectiveness PMU (SKM Road): PM J from beneficiaries/road users and contractors offices additional Chaudhary and reporting on the progress of handling financing PMU (K-C Road): PM L J complaints khanal PMU (BD Road): PM R K Deo PMU (S-M Road): PM SB Ghimire PMU (C-J Road): PM J Chaudhary Submit trimester reports by PMUs to PCT and DOR, PCT, Trimester Information in PMR trimester reports by PCT to DG of DOR and WB Project’s field project team on implementation of GAAP offices Update and disseminate information disclosure DOR, PCT By appraisal Published in DOR website policy for DOR-Bank projects in accordance with RTI 2007 (see Appendix 1)

Annex P-49

Agency Issues Actions responsible Timeline Status Disclose annual progress report on GAAP DOR, PCT, Annually Published in DOR website implementation DOR website and at its Project Project’s field site offices offices Publicize the existence of the functioning complaint handling mechanism and venues of its DOR, PCT, By Done access for general public and bidders/contractors Project’s field effectiveness (with a description of the process of handling offices complaints) on DOR website and concerned project site offices Technical Improvement in design and cost Regularly update material prices and use the PCT/PMU Annually Estimation is done estimates updated prices in cost estimates accordingly

Update GON old works norms and develop DOR Periodically GON old norms has been another set for equipment based method of updated with equipment based construction method

Design reviews by Independent Technical Auditors (ITA) for conducting reviews of designs and cost estimates as required Maintain database of unit rates for civil works PCT/PMU Periodically Done major items Compare estimated cost with market price PCT/PMU Periodically Done established through competitive bidding Need for improvement in Establish several channels (text messages, hot Done quality of construction works line, on-line complaint box, in addition to written complaints) for beneficiaries/road users to communicate problems related to quality of By DOR/PCT contract works and condition of roads; advertise effectiveness those channels on the information boards at the project sites, concerned project site offices and DOR website

Annex P-50

Agency Issues Actions responsible Timeline Status QAP has been shared with the Strengthen internal quality controls: format of Bank and improved based on QA plan to be cleared by WB, and quality the suggestion/comment. reports to be made available to Independent Technical Auditors for review Enhance capacity building in QA for DOR and Training to DOR personnel field offices has been conducted and planned in future also Engage ITAs to check for 20% of contracts in NVC is carrying out technical compliance with QA Plan audit of selected subprojects Engage Ex-post ITAs for conducting audits on NVC is carrying out technical 20% sample of works including the audit of selected subprojects environmental and social safeguard aspects Use ITAs to review sample work done by NVC is carrying out technical supervising consultants (e.g., variation orders) audit of selected subprojects during implementation Safeguards Possible adverse impacts on the Apply the Environmental and Social Done communities and environment Management Framework (ESMF) in project documents to determine and mitigate possible adverse impacts of the project on the social and environmental aspects Conduct consultations with communities on DOR/PCT/PMU By Appraisal Done possible adverse impacts and proposed mitigation measures Define and agree on communities’ roles in Done monitoring of project safeguard implementation and procedures of grievance redress mechanism Weak grievance redress Set up (or improve where exist) a functional Done mechanism/complaint handling complaint handling mechanism as per ESMF By DOR/PMU mechanism effectiveness

Annex P-51

Agency Issues Actions responsible Timeline Status Inform communities of the functional role of this mechanism and its procedures Procurement Collusion among contractors, WB to hold a training for contractors in WB Bank’s INT, Completed Completed submission of fraudulent requirements for contract management, role of SASDT SARPS information, any other corrupt WB’s INT during preparation and behavior implementation of WB-funded projects During pre-bidding conference, carry out DOR/PCT Pre-bidding Done/ process awareness campaign about sanctions to be stage of each undertaken against contractors who will be contract found and proved involved in corrupt practices (collusion, bribery, fraud, etc.) Assess bidders’ capacity, maintain regular DOR/PCT As when Done/ process updates of schedule of rates and feedback from required participating contractors, and encourage proper “slicing and packaging” to match the contractor capacity Carry out an analysis of bids and verification in DOR/PCT Bidding stage In the process doubtful cases; PCT to seek WB’s advice for of each further actions if the cases are prevailing and contract take actions through PPMO. If collusive, fraudulent or any other corrupt DOR/PCT Immediately In the process behavior is found and proved, invoke relevant when needed provision of the law (anti-corruption Act and Procurement Act) recommend the respective contractors to PPMO for blacklisting Intimidation (and/or extortion) Continue using e-bidding for receiving bids from DOR Continued Done of contractors during bidding contractors and execution of works Inform all contractors of existence of and DOR Continued Done encourage to use (domestic and international) complaint handling mechanisms in the Instruction To Bidders

Annex P-52

Agency Issues Actions responsible Timeline Status In case of reports of intimidation (formal/ DOR/PCT/PMU Frequently In the process informal), conduct an awareness campaign among project stakeholders, including political parties present in respective districts, of potential threats and risks of possible intimidation to contractors during bidding and implementation periods to project implementation Cost variations and contract Establish and regularly update a database of As warranted In the process extensions material prices Encourage use of price adjustment clauses in the With each Done contracts contract In case of prior review, DOR to seek With each In the process concurrence for material extension of the contract stipulated time for performance of the contract DOR/PCT/PMU from the Bank. Continue performance evaluation system for With each In the process design and supervision consultants contract Disclose all variations to the awarded contracts With each In the process on the website contract Need in strengthening of Enhance the e-bidding system to include a DOR In the process transparency in procurement tracking option to alert DOR about delays of decision-making process process from bid opening until award Disclose bidding information, including DOR/PCT In the process summary of bid opening, name of the awarded Continuous contractor, engineer’s cost estimate and bid cost, etc., on the RSDP website and at respective --- project site offices within 15 working days of contract awards (see more details in Appendix 1) Contract Management and Execution Improvement needed incapacity Training on Project management and contract Continuous Done/process of Project Officials in managing administration to be organized for DOR officials DOR/MoPIT

Annex P-53

Agency Issues Actions responsible Timeline Status the contracts and supervising the Take departmental action against non-performer In the process Consultants and lack in in accordance with the country’s legal accountability framework applicable to government officials Timely Payment to contractors ITAs to verify physical and financial progress as DOR Continuous Technical Audit being carried well as verify contractual payments (financial out by NVC and procurement) in compliance with contractual requirements at the time of technical audit of 20% of the contracts.

Poor performance by contractors Maintain a database of contractors’ performance DOR/PCT In the process monitoring and analyze trends of contractors’ performance Recommend to agencies in charge of issuing MoPIT licenses to take action against the contractors as per the prevailing laws and regulations of Nepal Continued based on the results of the database of contractors performance monitoring Promptly invoke available contractual remedial DOR/PCT/MoPIT actions against non performing Contractors and Consultants Financial Management Operationalize Financial Submit FMIS based trimester report on a timely DOR/PCT Start from Partially done. The FMIS Management Information basis. December 31, needs to be upgraded due to System (FMIS) in DOR 2010. change in the project funding source, and to make it fully functional. Dissemination of progress Make publicly available reports on physical and DOR/PCT Trimester Done reports financial progress of all contracts on the DOR website, concerned project site offices s

Capacity building on financial Organize training program on financial DOR/PCT Semi-annual On the job training provided. management management to all cost centers at least once a year.

Annex P-54

Annex P-55