<<

Board and Information Services, Legal and Legislative Service Tel. 604-432-6250 Fax. 604-451-6686

Rise and Report (Items Released from Closed Meeting)

On April 28, 2017 the attached report was authorized by the Greater Water District (GVWD) Board of Directors to be released to the public:

Metro Vancouver Utilities within the Deep-Sea Shipping Channel

CLOSED MEETING

To: Finance and Intergovernment Committee

From: Andrew Wood, Director, Interagency Projects and Quality Control, Water Services Paul Lam, Division Manager, Major Projects and Programs, Liquid Waste Services

Date: April 3, 2017 Meeting Date: April 19, 2017

Subject: Metro Vancouver Utilities within the Fraser River Deep-Sea Shipping Channel

RECOMMENDATION That the Finance and Intergovernment Committee receive for information the report dated April 3, 2017, titled “Metro Vancouver Utilities within the Fraser River Deep-Sea Shipping Channel”.

PURPOSE The purpose of this report is to identify existing GVWD and GVS&DD marine crossings and outfalls located within the Fraser River Deep-Sea Shipping Channel and summarize the potential impact of deep-sea shipping channel dredging on these utilities.

This matter is being presented at a closed meeting pursuant to Community Charter provisions, Section 90 (2) (b):

“90(2) A part of a meeting must be closed to the public if the subject matter being considered relates to one or more of the following: (b) the consideration of information received and held in confidence relating to negotiations between the regional district and a provincial government or the federal government or both and a third party.”

BACKGROUND Over the past decade, a number of major transportation infrastructure projects have been completed along or crossing the Fraser River (e.g., Golden Ears Bridge, Port Mann Bridge/Highway 1 Project, South Fraser Perimeter Road). There are also a number of approved and proposed projects along the Fraser River such as the Replacement Project, Vancouver Airport Fuel Delivery Project, WesPac LNG Marine Jetty, Fraser Grain Terminal Export Facility and the Pattullo Bridge Replacement. These projects are shown on Attachment 1.

Capital projects that are planned or underway along the Fraser River have the potential to impact Metro Vancouver utility infrastructure and MVRD lands (such as parkland). In addition, dredging activities may also have an impact to utilities located in the Fraser River shipping channel. This report provides the Committee with an update on the utilities in the Fraser River shipping corridor and considers the potential impact of dredging on these utilities.

17106385 Metro Vancouver Utilities Within the Fraser River Deep-Sea Shipping Channel Finance and Intergovernment Closed Committee Meeting Date: April 19, 2017 Page 2 of 6

Fraser River Deep-Sea Shipping Channel Most of the approved and proposed projects are adjacent to a portion of the Fraser River Deep-Sea Shipping Channel, located in the south arm of the Fraser River, extending from the mouth of the river at Sand Heads to the Pattullo Bridge in . This navigation channel provides access for ocean-going vessels to current marine terminals such as Fraser Surrey Docks.

To support shipping activities, the Fraser River is currently dredged on a regular basis to maintain a navigational depth of 11.5 m. While the navigation channel is intended to allow two vessels to pass simultaneously, width restrictions at bends such as Steveston and Tilbury allow only single vessel passage. Two way traffic is possible on straight reaches of the river. The maintenance dredging program is managed by the Port of Vancouver.

The Port of Vancouver has indicated they have no plans to dredge the Fraser River shipping channel deeper than the current depth sustained through annual maintenance dredging. However, with the George Massey Tunnel Replacement Project and increasing development along the Fraser River, there has been expressed interest in deepening the channel for increased marine traffic movement.

GVWD and GVS&DD Infrastructure within the Fraser River Deep-Sea Shipping Channel As shown on Attachment 2, the Water and Liquid Waste utilities currently have a total of six crossings and one marine outfall within the Fraser River Deep-Sea Shipping Channel. GVWD’s Annacis Main No. 3 and GVS&DD’s North Surrey Interceptor are bundled together in a single combined crossing. These crossings are buried in relatively shallow trenches underneath the riverbed and have scour protection blankets in some areas. Metro Vancouver surveys these crossings annually to ensure that there is sufficient protection over the crossings. Select crossings, with high potential for scour, are surveyed twice each year.

The individual crossings, together with their size and date of construction, are shown in Table 1.

Table 1 – Existing GVWD and GVS&DD Infrastructure within the Fraser River Deep-Sea Shipping Channel Pipe Age Anticipated Construction Facility Name Diameter Utility (Years) Replacement Date (mm) Date2 Lulu Island - Delta Main 800 GVWD 1963 54 2060 - 2070

Tilbury Main 1200 GVWD 1980 37 2075 - 2085

Annacis Main No. 2 650 GVWD 1961 56 2055 - 2065

1Annacis Main No. 3 1200 GVWD 1963 54 2040 - 2050 1 - 1200 1North Surrey Interceptor GVS&DD 1 - 650 2 - 1200 South Surrey Interceptor GVS&DD 1974 43 2050 - 2060 1 - 900 Metro Vancouver Utilities Within the Fraser River Deep-Sea Shipping Channel Finance and Intergovernment Closed Committee Meeting Date: April 19, 2017 Page 3 of 6

Pipe Age Anticipated Construction Facility Name Diameter Utility (Years) Replacement Date (mm) Date2 WWTP 2 - 1650 GVS&DD 1974 43 2050 - 2060 Outfall 1 - 1200 1 Combined Crossing 2 Replacement dates are based on estimated life spans of 80 years and 100 years for GVS&DD and GVWD facilities, respectively.

As part of its growth and resiliency programs, GVWD is replacing several key crossings with deep, seismically secure, scour resistant crossings, sized for long term growth. For example, within this section of the Fraser River, plans are underway to construct the Annacis Water Supply Tunnel between New Westminster and Surrey, downstream of the Pattullo Bridge.

Infrastructure Upstream of the Fraser River Deep-Sea Shipping Channel In addition to the infrastructure listed in Table 1, the Water and Liquid Waste utilities have an additional four crossings and two marine outfalls upstream or outside of the Deep-Sea Shipping Channel. These crossings, together with their size and date of construction, are shown in Table 2. Staff did not analyze crossings outside of the deep-sea channel because of the lower potential for deeper dredging.

Table 2 – Existing GVWD and GVS&DD Infrastructure Upstream or Outside of the Fraser River Deep- Sea Shipping Channel

Pipe Age Anticipated Construction Facility Name Diameter Utility (Years) Replacement Date (mm) Date3 Port Mann Main 1 1200 GVWD 1975 42 N/A

Port Mann Water Supply 2100 GVWD 2017 New 2210 - 2220 Tunnel

Barnston Island Main 1350 GVWD 1990 27 2090 - 2100

Maple Ridge Forcemain 2 – 750 GVS&DD 1983 34 2060 - 2070

Lulu Island WWTP Outfall2 1700 GVS&DD 1992 25 2070 - 2080

Northwest Langley WWTP 900 GVS&DD 1978 39 2055 - 2065 Outfall

1 To be removed after the new Port Mann Water Supply Tunnel is in service. 2 Not situated within the deep-sea shipping channel. 3 Replacement dates are based on estimated life spans of 80 years and 100 years for GVS&DD and GVWD facilities, respectively.

Metro Vancouver Utilities Within the Fraser River Deep-Sea Shipping Channel Finance and Intergovernment Closed Committee Meeting Date: April 19, 2017 Page 4 of 6

DREDGING SCENARIOS With increasing development along the Fraser River Deep-Sea Shipping Channel, it is likely that there will be increased pressure to dredge and deepen/widen the channel to allow larger vessels and increase goods and materials movement.

The deeper the dredge cuts are to the river bed, the greater potential for impact to Metro Vancouver’s utilities. Staff have analyzed the potential impact of various dredging options on the marine crossings, specifically, impacts based on 12.8 m and 13.5 m Vessel Drafts.

The impacts on three GVWD crossings (Annacis Mains No. 2 and 3 and Lulu Island - Delta Main) and three GVS&DD facilities (South Surrey Interceptor, North Surrey Interceptor and Annacis Island Wastewater Treatment Plant Outfall) are summarized as follows:

12.8 m Vessel Draft For a 12.8 m Vessel Draft, both the Annacis Main No. 3 and Lulu Island – Delta Main will require modifications to the existing scour protection. While the Annacis Main No. 2 is not directly impacted by the dredge cut, its cover is reduced to the point where there is insufficient clearance to install adequate scour protection. The affected section of Annacis Main No. 2 is currently out of service and pending the recommendations of the GVWD’s Comprehensive Regional Water System Plan, may be removed and not be reinstated.

There is marginal clearance to install scour protection at the South Surrey Interceptor and the existing scour protection will need to be modified. Low profile scour protection may be used at this location, however, this is best determined when a dredge profile at this location can be confirmed based on a detailed design. The North Surrey Interceptor (bundled with the Annacis Main No. 3 crossing) will require modifications to the existing scour protection.

The existing Annacis Island WWTP Outfall will require extra protection. MV staff have started the preliminary design for a new outfall as part of the Annacis Island WWTP expansion and further assessment of the impact is required when the conceptual design is complete.

13.5 m Vessel Draft Impacts to Metro Vancouver infrastructure for a 13.5 m Vessel Draft would be similar to those for the 12.8 m Vessel Draft; however, the Lulu Island-Delta Main would need to be replaced with a new crossing as the dredging would expose the pipe and the South Surrey Interceptor would need to be replaced as there is also insufficient clearance to install scour protection.

While staff’s analyses are based on re-installation of current capacity, it should be noted that anticipated population growth in the areas served by these crossings will eventually require an increase in the capacity of these facilities. However, these capacity upgrades are not anticipated to occur within the current GVWD/GVS&DD Long Range Capital Plan. The expected remaining service life of these crossings generally ranges between 25 and 60 years.

ALTERNATIVES This is an information report. No alternatives are presented.

Metro Vancouver Utilities Within the Fraser River Deep-Sea Shipping Channel Finance and Intergovernment Closed Committee Meeting Date: April 19, 2017 Page 5 of 6

FINANCIAL IMPLICATIONS Based on preliminary estimates and as summarized in Table 3 below, the range of costs associated with these two vessel drafts is $40 million to $275 million, depending on a number of channel factors such as alignment and depth of dredge cut. Detailed engineering evaluations for each of the locations are required to determine specific detailed mitigation designs and more accurate cost estimates.

Table 3 – Financial Implications of Various Fraser River Deep-Sea Shipping Channel Dredging Depths

Facility Name Utility Range of Impacts Range of Costs

12.8 m 13.5 m 12.8 m Vessel 13.5 m

Vessel Draft Vessel Draft Draft Vessel Draft Lulu Island - Delta Modify Scour GVWD Replace Crossing $5,000,000 $65,000,000 Main Protection

Tilbury Main GVWD No Impact No Impact - - Remove and Remove and Annacis Main No. 2 GVWD Decommission Decommission $10,000,000 $10,000,000 Pipe Pipe

Annacis Main No. 3 GVWD Modify Scour Modify Scour Protection Protection $5,000,000 $5,000,000 North Surrey (Combined (Combined GVS&DD Interceptor Crossing) Crossing)

South Surrey Modify Scour GVS&DD Replace Crossing $5,000,000 $180,000,000 Interceptor Protection

Annacis Island Protect Existing Protect Existing GVS&DD $15,000,000 $15,000,000 WWTP Outfall Outfall Outfall

TOTAL $40,000,000 $275,000,000

With the exception of the Annacis Island WWTP Outfall and Annacis Main No. 2, none of the facilities that would be impacted by deepening the Fraser River Deep-Sea Shipping Channel are scheduled for replacement within the current GVWD/GVS&DD Long Range Capital Plan, nor are the costs of these impacts included in the plan.

If the Fraser River Deep-Sea Shipping Channel is deepened, Metro Vancouver may have to assume the costs associated with the dredging impacts, depending on the individual crossing permits and how the deepening is funded.

SUMMARY / CONCLUSION Recent transportation investments along the Fraser River were constructed to improve goods movement and mobility for transportation users. In addition, the George Massey Tunnel is proposed for replacement with a new 10-lane bridge. A number of significant projects are being proposed along the Fraser River Deep-Sea Shipping Channel that will take advantage of these transportation investments. Metro Vancouver Utilities Within the Fraser River Deep-Sea Shipping Channel Finance and Intergovernment Closed Committee Meeting Date: April 19, 2017 Page 6 of 6

While it has not been identified by the Port of Vancouver, it is foreseeable that the Fraser River Deep- Sea Shipping Channel could be deepened/widened to accommodate larger vessels in the future. This would affect six GVWD/GVS&DD pipe crossings, two of which are combined into a single crossing, and one GVS&DD outfall. Based on preliminary estimates for two possible dredging scenarios, the cost to address these impacts ranges from $40 million to $275 million.

Attachments: (Doc #: 19613554) 1. Proposed Major Fraser River Projects 2. Fraser River Deep Sea Shipping Channel and GVWD/GVS&DD Facilities 3. Fraser River GVWD/GVS&DD Facilities 4. Vancouver Airport Fuel Delivery Project - Overview 5. WesPac LNG Marine Jetty - Overview 6. Fraser Grain Terminal Export Facility – Information Sheet

17106385

Attachment 1 - Proposed Major Fraser River Projects Attachment 2 - Fraser River Deep Sea Shipping Channel and GVWD/GVS&DD Facilities City of City of Vancouver New Westminster

City of North Surrey Interceptor

99 Annacis Main No. 2

91

Annacis Main No. 3

17 Annacis WWTP City of Richmond Outfall

Tilbury Main South Surrey Interceptor

City of Surrey Lulu Island-Delta Main 91

Corporation of Delta 10 99

17A

17A

0 0.5 1 2 3 4 Legend Kilometers MV Waste Water Treatment Plant Tsawwassen First Nation 1:100,000 MV Water Main Source: Esri, DigitalGlobe,G:\PROJECTS\WA01\01\Mxds\ GeoEye, Earthstar Geographics, CNES/AirbusMV Sewer DS, Main USDA, USGS, AEX, Getmapping, Aerogrid,FraserLetter_April2017_ver2 IGN, IGP, swisstopo, and Apr the 2017 GIS User Community Attachment 3 - Fraser River GVWD/GVS&DD Facilities

City of Coquitlam City of Port Coquitlam ¨1 City of Pitt Meadows City of Burnaby City of Vancouver Port Mann Main Port Mann Water Supply Tunnel

City of City of Maple Ridge New Westminster Maple Ridge Force Main Barnston Island Main

Electoral Area A

Annacis Main No. 2 )" North Surrey Interceptor Northwest Langley ¨15 WWTP Outfall ¨91 Annacis Main No. 3

17 Annacis WWTP )" ¨ City of Richmond Outfall

Tilbury Main South Surrey Interceptor Township of Langley

Lulu Island-Delta Main

City of Surrey )" ¨91

Lulu Island WWTP Outfall

¨10 ¨99 Corporation of Delta ¨17A

17A¨

Tsawwassen First Nation 0 0.5 1 2 3 4 Legend µ Kilometers )" MV Waste Water Treatment Plant MV Water Main City of White Rock Source: Esri, DigitalGlobe,G:\PROJECTS\WA01\01\Mxds\ GeoEye, Earthstar Geographics, CNES/AirbusMV Sewer DS, Main USDA, USGS, AEX, Getmapping, Aerogrid,FraserLetter_Jan2017.mxd IGN, IGP, swisstopo, and Jan 2017the GIS User Community

Assessment

comprehensive

review environmental

Environmental with

consultation

of

the existing Vancouver

In

River ABOUT

includes constructing

comprehensive

December

airlines

WR.

and

requirements

industrial

a

an

THE

Airport

Marine

Act

at

by

underground

a

2013,

Vancouver

assessment

Assessment

new

VAFFC,

and

harmonized

PROJECT

planning,

sites

Terminal

Fuel

following

aviation

BC

of

the

Environmental

both

Facilities

on

International

the

pipeline

project

process,

Office

and fuel

federal/provincial

research,

the

more

South

Canadian

Fuel

delivery

Corporation

lEAD)

completed

than

connecting

with

Arm

Receiving

Assessment

review

Airport

a

coordinating

system

the

decade

Environmentat

of

the

and

BC

(VAFFC]

a

tYVR).

the

FaciLity

Fraser

to

Act.

facility

serve

It

the

is

at

delivery

risks

understood

and

practices and Agency,

On Vancouver,

of

& The

Oceans,

Natural Canada,

Gas

Environment,

a

will

Vancouver

assessment

stand-alone

of

Commission,

this

methods

Resources

be

Port

Canadian

Health

and

City

managed

and

project

Metro

technology.

Airport

of

Canada,

Ministry

proven

included

and

basis,

Richmond,

Coast

Canada,

Vancouver,

are

BC

to

infrastructure.

Authority.

far risk

Utilities

insignificant

the

of Department

Guard,

Environment On

A

Vancouver

less

Community,

Fuel

Canadian

management risks

PSM

Corporation

a 12

OROUP

comparative

than

Canadian

Commission,

Facilities

of

First Airport

M.’OcD

this

the

levels

of

Transportation

Nations,

Canada,

Fisheries

Sport

project current afORv11ou

Attachment

Wildlife

of

methods, Corporation

with

Delta,

basis,

BC

&

Transport

Metro

well

Culture

are

fuel

Ministry

and

Service,

BC

the

few

best Oil 4 of if The area fuel as vessel a using arrival arms deploy the using Pier trail. any safe perimeter water release flexibility upstream. deflection! to skimmers upon shore by automatically product contain the the dyke pile with to to be and collect offloading in a pre-deployed the unloading the further to standby will accompany Waterstone accidental with with on deployed exceeds vessel disconnected couplings protected vessels during booms booms along Response: an designed the will recover be be be be the of in systems to be process from and and articulated vessel will skimmers will will release complete equipped trail would will and event barriers the users and offloaded, around absorbent site movement be river, of arms is transfer vessels arms boats future the and water, wilt ship the transferred booming unlikely in possible system fuel connect emergency and vessel be landscape and Preparedness onto and Terminal as the positioned a the terminal will movement response in response will and be vessel terminal unloading tides a the the trail existing Marine required containment product quickly Before spill The of to Spilt will protection spilled permanent leak-free If stopped range, The Fuel hydraulically-operated for The • • • • • • • dyke fencing with The Emergency Operations: and the and be an class and of safety These small north unloading month, river pre couLd practice with zoned one a an tugboats pollution the upgrade be the at acceptance by best mooring Pollution Panamax on optimal handle An on barge with times will weeks a carry on already to Oil A for shipments. River, is tanker to few river. two pilots guided a a while located month based be the that a terminal be Fraser every only of be demand. designed overseas Shipboard will required marine hours, the area wiLl the once through be a hours. FaciLity state-of-the-art and will fuel once 12 of on an double-hulled and 36 large wilt in have be use, to sections YVR fuel vetted Terminat arm Receiving and 24 Plan, TerminaL expected calling will around will duration Fuet movements

and COMPONENTS wharf, in be insurance incorporate south deliver terminal and deepest Marine time

technologies. Terminat projected industrial to Marine the and vessels vessels between vessel vessels the short could and on shipments of Tecmina existing of LiabiLity Emergency program screened All government-certified at All All All marine be new heavy • • • • an Marine

Vessels: PROJECT unloading based time expected vessel barge offtoading designs wilt of The

for Marine The shore widest Rendering of Fuel ReceivingFacility— viewlookingnorth

Fuel Receiving Facility Emergency Preparedness and Response: The Fuel Receiving Facility will include six above- The Fuel Receiving Facility will be constructed to the ground vertical carbon steel single wall tanks, each NationaLBuilding Code and the B.C. Building Code. approximately 33.5 metres in diameter and 14.6 metres The facilitywill feature state-of-the-art fire detection and high, with an overall height of 21 metres above sea suppression systems including: Level.The tanks wiLtprovide a combined totaLcapacity of approximately 80 million litres. • Early detection systems inside tanks and in the piping/process area Operations: • Automatic fire valves on tanks in the process area • The Fuel Receiving FaciLitywiLloperate quietly with • Foam suppression system inside each fuel storage little noticeable activity tank • FueLwilt be moved through contained systems from • Foam/water monitors and tank cooling system pipes to tanks with pumps that will be housed to reduce operating noise levels • Fire hydrants at strategic and perimeter locations for access and operation by Richmond Fire Rescue • Tank systems will be equipped to reduce vapour emissions during fuel transfers and will be only • Auxiliaryand portable fire-fighting equipment locaLlynoticeable Environmental protection measures will include: • Lighting and security of the facility will use state- of-the-art LEDand motion detection to reduce the • Secondary containment and under-tank leak ambient leveLof light during night-time operation detection • Noise, air quality and traffic wilt be mitigated through • Redundant high level control to prevent tank overfill our comprehensive Operations Environmental • SCADAprocess monitoring system Management Plan which will include a telephone • Emergency shut-down devices and emergency shut information line down valves • Process equipment Locatedon concrete pads, with all drainage connected to an oil/water separator

• Drainage detection system to prevent a product release to ditches • 24/7 monitoring by operations staff, with on-site spill response equipment, including portable spill response kits, spill response trailer and a vacuum truck

- The tanks will have impermeably Linedsecondary containment areas

VAN CO U yE RAIRPO RTFU E L.CA PipeLine Operations: Modern pipeLinesystems have the benefit of precise • The pipeline wiLlbe controlled and monitored locating technologies, new materials and coatings, and by operations personnel during all fuel transfer high-tech instalLation techniques to reduce disturbances activities during construction. • It will be pressurized only during fueLtransfer operations between the Fuel Receiving Facility and The pipeline will be about 1%kitometres long, 355.6 YVR[it will not operate 24/7) millimetres in diameter and buried for its entire length approximately 2.5 metres underground. Emergency Preparedness and Response:

The pipeline wilt consist of specialty steel pipe and wiLl • Prior to construction, an emergency response in with other be installed to meet a minimum Canadian Standards plan will be deveLoped conjunction response plans Association (CSA)Standard Z245.1 Grade 359 for Oil municipal and regional emergency and Gas Pipeline Systems. The pipe[ine installation • The pipeline will inctude state-of-the-art corrosion and operation wilt be reguLated by the BC Oiland Gas protection and teak detection technologies Commission. • The pipeLinewill be equipped automatic emergency Prior to commissioning, the pipeline will be thoroughLy shutdown devices, and pressure and flow monitors tested and cLeaned in accordance with construction and that will transmit data to a Control Centre operational requirements, and clearly marked along • Any abnormalities in pressure or flow will trigger an length. SimiLarto all other utility installation, its entire alarm or shutdown location information will be provided to the City of Richmond and locator services. Ifthe unlikely event that an abnormal condition exists or a release of product occurs, the Control Room Operator will take the appropriate actions, such as shutting down or isolating the affected * pipeline segment, depressurizing the pipeline, and mobilizing a response team

/

LEGEND — Original Approved Route — Amended Route Options

I FRANCIS RD

WWAfl RD TERMINAL

Second

First The

spring

foLlowing

in

construction The

on the

witt

Fuel

and

materiats associated

winter

Most

anticipated Significant wilt

habitat

mooring

dock. The

of

tate

CONSTRUCTION

Marine

August/September

through the

pipe,

Port

by

mechanical

tuet

Localty foundations

the

In

some

materials

This

tanks

The

ground

Vancouver

Fuel

begin

project

components

be

2016,

Marine

phase

2016,

noticeable

road,

To

2016 facility,

Receiving

seasons,

marine

phase

undertaken

receiving

Authority

will

first

wilt

and

Receiving

meet

structures.

a

to

localized

wilt

being

supptied

beginning

technical

improvement Terminat

with

the

while

barge

construction

recently

until

and

withstand

be

lerminat

involve

phase

other

of

significant

be

Fraser

terminal

the

restored

and

Marine

the

and

the

consist

installed

activity

however

2017.

facility

transported

of

large-scale

owned

activity

bulk

seismic

ground

will

Facility

Fuel

to

electrical

heavy

structural the

materials

removal

received

Shoreline

review

with

Facility

2015.

Port

construction

altow

a

Terminal

involve

existing

materials

as

of

in

is

major

Receiving

will

land.

to

will

rehabilitation

in

no

machinery

moditications

expected

the

vibrations. 2016

Authority

construction

part

performance

provide

and construction

mid

significant

of

start

a

occur

tank

components

off-site.

such

This

following

site

steel

seismic

Project

and

unsuitable

of

and

dock

pubtic

to

are

the

on

steel

Facility

preparation

late

permit is

the

underwater

as

during

for

components

early

to

VA

movements

the

structure.

expected

Some

expected

devetopment.

New

concrete,

Permit

consultation

commence

event

stability of

2017.

delivery

pite

components, two

will

to

N

requirements

of

utilities,

the

2017

to

fill

was

CO will

the

the

structures

off-shore

driving

activity

key

begin

be

materials shoreline

from

U

existing

fall,

arrive

to

will

awarded

and

to

for

of

located

These

phases:

V

rebar,

of

and

start

arrive

bulk

and

in

E

the

be

is

the

at

held

R

Al

in

R

PORT

early

testing.

associated

applying

Pipeline

staking,

vehicle

pipeline

in

Construction

to

for

The

potentiat include

Pipeline

which

current

water

The

work

landscaping,

Tank

approximately

perimeter

pipeline

2017.

F

and

extensive

U

for

construction preparing

final

a

the

environmental

and

body

and

E

protective seismic

valves

installation

marine

L

pipeline

will

activities stage

foundation

welding

CA

road

crossings

be

including

and

use

the

one

design

vessel

of

works,

constructed

coat,

wilt

is

fittings,

construction

of

right-of-way,

will

year

tfitting

expected

impacts

directional

and

construction

be

standards.

traffic.

installing

include

paving,

screening

and

placed,

intersections)

covering

it

consist

to

with

and

to

fencing

surveying

the

will

drilling

begin

preparing

digging

the

avoid

Construction

resilient

vegetation

will

terrain)

the

include

pipeline mostly

in

take

and

pipeline

disruption

tparticularly

to

the

tate

and

materials

the

mitigate

and

of

trench

and

2016

crane

will

and

of or

on

on

and

a

and

WR

new

go

the

fuel

and

the

users

Canada’s

and

as

practices,

system,

capability ensure

as

investment

add

carry

remains

experienced

Washington

other

to

best

Mainland.

to

robust of

organizations,

role

response

Canada

that

YVR

all

construction

modelling

Richmond.

from -I

and

environmental

corporc

million

delivery

are

consultants

and

response Lower

that

needed

and

spilt

capacity

fuel [‘1

trucks

is

network

benefit

$110

infrastructure.

I

the

the

Rivet

quatified

for

month)

a

a

smaller

in

Delta

Columbia’s

fuel

to

Airport

F..\

will

a

ensure

help

standards

fuel

Facilities

Environment

tanker

:1

each

the

from management,

——

existing

prevention

preparation.

Fraser

jobs

by

that

hetp

also

have

enhance

the

‘J

British

Fuel

Vancouver

Surrey,

the

the

I

environmentat

the

have

spilt

facilities

1,200

of

industry

represents

all

IntoIdv&1courairportfuet.ca

aviation

604.638.7663

vancouverairportfueLca

will

will

will

will

River

to

for

its

and

II

in

incident

than

BENEFITS

expertise

state-of-the-art

part

Gateway.

of lover

.-

described

through

[a]

project

construction

beyond project

project

project

project

remove

projects is

contracts

Fraser river.

YVR

draws

and

Pacific

continues The

flights.

critical

The

State

to The

the tootprint

potential will

the The

current The

and

strategies

The well

.]

Phone:

Emait:

Website:

engineering

operation specializing

and

VAFFC

PROJECT

in

CORPORATION

to

an

most

w

and

1990s

It

to more

mm

one

a

shut

Refinery

north

which

avoid

through

are

facitity

on

late

Marine

wortd.

by

150

fuel

local

of

serving

to

only

require

airline

shipped

and

example,

experience

international

the

fuel

originates the

Point

pipeline,

Chevron

and

deliveries,

required

needs only

four

the

of

60%,

and

and

For

FACILITIES

them

refineries

is

is

owned

the that

depends

facitities

woutd

existing

representing

since YVR.

carriers

major

Westtidge

been

truck

Corporation

unsustainable.

Cherry

when

Burnaby

(YVRI.

Simitar

Morgan

at

years

the

YVR

storage

is

Asia

these and

airport

which

the

airports

fuel

the

BP

FUEL

at 20

These

have

to

of

throughout

time

Chevron

offloaded

NEEDED

to

pipeline

day.

of

allowing

remaining

of

airtines

tanker fuel

company

the

a

a

the

costs.

shipments.

is

Kinder

year.

crosses

IS

Airport

one

atL

of

at

it and

than

the

YVR.

Facitities

a

period,

via

reptace

because

40

flight

If

capacity

activities

jeopardized.

and pipeline,

at

the

is

at

barges

demand

to

and

truck

internationat

at

Morgan

sources be

40%

witi

built

deliveries

airLines,

Fuel

demand.

daily

more

up is

it

operating.

via

where

operates

trucks

20%

fuel AIRPORT

State.

fuet

minimize

and Canada

needed Inlet

two

supplies

the

was

commercial

extended in

one

fuel

Morgan

has

is

through

Burnaby

truck

operate

would

Kinder

800

total

handling

and

from

were

not-for-profit

facilities

of

PROJECT

and

an

only

in supplies

InternationaL

Airport

a

system

just

Point

shipped

operation.

can

across

fuet

YVRs is

on

diameter,

for

Burrard

is

among

Kinder growth

owns

in

pipeline

remaining tanker

project

airport

40-km

domestic

THE

in)

Washington

company

adding

cross-border additional

meet

(6

the Any

the The

refineries Cherry the which

Terminal,

stilt 40°h

Richmond.

near

Chevron

The

Refinery the

down

operations

relies in

delivery

The

the

airports aviation

The

corporations

duplication

shared

(VAFFC) distribution

of

consortium

VAFFC

Vancouver

Vancouver

VANCOUVER WHY

http://wespactilbury

Overview

development

links: disturbed

For

support for

The

with,

improve

industrial involve

• • size delivery The

WesPac navigating

LNG

LNG

Project

Overview

International

FortisBC

industrial

more

Project

purpose

of

or to

marine

I

WesPac

vessels

storage

barges

smaller

efficient

to

Description

the

is

marine

by

Information

the

both

Tilbury

proposing

site

ecology

jetty WESPAC

at

previous

marine

of

of

.caloverview/

Fraser

Group

that Tilbury

and

Tilbury

than,

or

the

new

local

was

movement

area

on

processing

LNG

will proposed

mid-size

functions

HOME

transportation

Tilbury

of

selected

and

other

River.

to

of activities.

that

the

about

use

Island

Plant

construct

Liquefied

offshore

already

existing

ships

of

the

Island

The

marine

— Project

of

because

as

LNG,

LNG

LNG

OVERVIEW

Jetty

Click

The

LNG.

Project

the

currently

and

Natural

markets.

contains

in

or

site

from

Natural

vessels

adjacency

former

is

Delta,

is

transmission

Here

operate

it

consistent

MARINE

by

to

will

the

is

transfer

Gas

restoring

on

The

marine

BC.

Weyerhaeuser

existing not

Gas,

for

FAQ

an

an

Importers

of

established

the

and

infrastructure.

jetties

the

Plant

proposed

PROJECT

FortisBC

shoreline

JETTY

(GIIGNL)

on

to Northwest

Rendering

marine

adjacent

shipping

Jetty

TIMELINE

Tilbury adjacent

vessels,

Click to

of

sites.

Hardwood route

Proposed

the

LNG

to

Here

FortisBC

and

The

the

minimizing

LOCATION Plant

site

is

Jetty

Mill. site Attachment 5

— located

Click

visit

Tilbury

was

The

where impacts

for

the

previously

Project in

Larger

LNG

ABOUT

12/13/2016

it

an

Page

following

was

existing

related

Plant will

View

1

WESI

of2

us€ ‘v

http

Location

://wespactilbury.callocation!

Location

The

WesPac

Project

WESPAC

at

Tilbury

Tilbury

site

is

HOME

located

Island

at

NGLMARINEJETY

OVERVIEW

Tilbury

Proposed

FortisBC

Island

FAQ

on

Tilbury

Project

the

Fraser

PROJECT

LNG

Location

River

Plant.

TIMELINE

in

Delta,

BC,

LOCATION

adjacent

to

the

ABOUT

12/13/2016

Page

existing

1

WES of3

3

16

of

2

12/13/20

Page

mouth

View

the

to

Larger

Tllbu,y

for

from Click —

IQ*ClJ route

‘;

Heads L

...,: L..

‘n

shipping

Sand

L

at

River

established

Fraser

the

showing

of

Chart

Tilbury

WesPac

://wespactilbury.ca!location!

http Location FRASER including companies more FGT in Fraser Paterson INFORMATION Fraser Surrey, than GRAIN Grain GlobalFoods British the 1 TERMINAL with Terminal 0,000 Grain Alliance Columbia. more Canadian Ltd. SHEET Grain than Inc. emnlExport Terminal is (PGF) P&H a 1 Terminal farmers 00 joint years and to venture construct n producers, and PGF located of experience are of Canadian a Parrish on grain the technology. niiae annual anticipated grain we of constraints for customers through for provide By today crops specialty residents Our on tions India design in modern (Mt/a). specialty grain port Fraser About industrial 11041 grain port consolidating Canadian ocargo to B.C. can they new in land handling and and south and upychain supply products — Grain Elevator The that workers industrial help agribusiness exports aiyondand family-owned limited a facility the facility grains and that will direct China lands Facility around new in market Heimbecker, iiie noise minimizes vessels. Terminal Preliminary oincrease to use the products. businesses replace getting shore has including Road have western will and with in facility and injection will becoming of bulk land Surrey, not facility the while indirect innovative receive It support minimize Project build increased a adjacent a proposes Canadian will grain for grain been throughput world. of and We derelict analysis Canada efficiency by becoming grain wheat, ofSlOO B.C. support and the strong want Attachment 6 increasingly grains contributions travelling handling eliminating used along and Canadian Since It Limited to local to and by handling. manufacturing to will grain Burrard rail indicates locations to dust barley, Fraser business for million over build more by and Canadian operated of safe help air 2014, be capacity, a more rail the shiploader 4 in ooverseas to better from quality sdto used farmers, reduce million technology. Surrey dust a a important oil than address and 40 to grain (P&H) exports state-of-the-art of that than relationships seeds, Fraser grain Inlet. the $40 neighbour and trade, countries. load 20 and and across tonnes Docks warehouse our bottlenecks trans-ship export increase local two per will million grain two handling noise customers of a pulses and the noise destinations Project Serving provide shortage River cent, grain years. have We details. your economy, e back See page on major agri-products per facility with Canada, to annually. with effects efficiency port and facility, bulk want with a annum and will on adjacent opera This in jobs input. modern modern for other the vacant at and ______

Our Project will have an annual throughput of 4 Mt/a. Following demolition of two existing buildings, new construction on the site will include: Unloadingstation and transfer tower with fullyenclosed conveying

equipment and a built-indust suppression system ‘

• 34 above-ground steel storage bins (24x 3,000t and 10 x 500 t) I • Travellingshiploader with telescopic cascading spout to reduce dust during vessel loading, replacing existing ship loader fitted with older technology

• Semi-loop railtrack and holding tracksto reduce shunting during unloading Container loading facIlItyand storage yards Railand truck loading facility AnadmInistration building and maintenance shop

Project Status

Weare in the preliminaryreviewphase of the VancouverFraserPortAuthority’sProjectand EnvironmentalReviewProcess and in earlydiscussionswith localand federalregulators.Weare committed to developing a sustainableproject that meets or exceeds environmentaland safetystandards,and providesbeneRtsfor localresidentsand businesses.We lookforward to sharing more informationwith the community as it becomes available,and we welcome questions at anytime. Technical Studies Aspart of the reviewprocess,technical studies are being undertaken in the followingareas:

AirQuality — Assesspotential environmental impacts fromair emissions resultingfrom proposed operations, which could affect airquality.

• Biophysical including Vegetation and Species-at-risk — • Spill — Prepare Assessspecies and habitats that have the potential to Prevention and Emergency Response spillprevention,containment and clean-up plans,including be affected by Projectactivities,includinga description proposed employee training, communications, of existingconditions,potential effectsand proposed procedures, mitigation measures. spilltracking and reporting.

• Stormwater Pollution Prevention — Planto mitigate any • Environmental Management — Preparean Environmental stormwater risksidentifiedin site inventory. Management Planto assess potential construction and the

demolition impacts and relevant mitigationmeasures. • Traffic — Reviewcurrent and future site traffic,including anticipated truckand railvolumes,patterns and potential • Hazardous Materials Management — Preparehazardous effectson local materialsinventoryand materialsreuse,removal,recycling roads,access/egress and parkingneeds.

and disposal plan forremovalof existingderelict structures. • Viewand Shade — Assessthe proposed Project’seffect on viewsor shading on the surrounding community and public • Noise -. Assesshow the proposed development willaffect areas,and proposed mitigation address these effects. noise levelsexperienced bythe adjacent community. to

• Lighting — Prepareplan forallproposed exteriorlighting includingthe location,type, orientation and levelof illumination. Community Engagement

How to Participate

Visit our Project website • Readmore about our Projectand technicalstudies

• Addyourselfto our database to receiveProjectupdates

• Complete our online feedbackform by Thursday, December 1, 2016

Contact us by phone 1-866-302-8872

Contact us by email [email protected]

The PreliminaryPublicComment Periodruns from November3 to December 1,2016.Wewillbe hosting two drop-in events.Join us fora tea or coffee,meet the Projectteam and bring yourquestions:

Trinity Lutheran Church, 11040RiverRoad,Delta Old Crow Coffee, 655 FrontStreet,NewWestminster

Wednesday,November16from4:00— 6:00p.m. Saturday,November26from2:00— 4:00p.m.

Next Steps The closing date for the Preliminary Public Comment Period is Thursday, December 7, 2076.

Followingthe completion ofthe publiccomment period a PreliminaryReviewPhaseConsultationSummaryReportand a PreliminaryReviewPhaseConsiderationReportwillbe prepared and, followingapproval byVancouverFraserPortAuthority, posted on the Projectwebsite and on the port authoritywebsite in preparationforthe PermitApplicationsubmission.

Aftersubmitting our permit applicationwe willhost a second phase of consultation,includinga community open house,to providefurther detailsabout the Projectand receiveinput on the resultsof our assessments.

THANKYOUFORYOURPARTICIPATION FraserGrainlerminal.ca