The World Bank Report No: ISR14312

Implementation Status & Results Highway Project (P096920)

Operation Name: Ningxia Highway Project (P096920) Project Stage: Implementation Seq.No: 5 Status: ARCHIVED Archive Date: 07-Jun-2014 Country: China Approval FY: 2010

Public Disclosure Authorized Product Line:IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Ningxia Highway Construction Administration Bureau Key Dates Board Approval Date 13-May-2010 Original Closing Date 30-Jun-2015 Planned Mid Term Review Date Last Archived ISR Date 13-Dec-2013 Public Disclosure Copy Effectiveness Date 27-Oct-2010 Revised Closing Date 30-Jun-2015 Actual Mid Term Review Date

Project Development Objectives Project Development Objective (from Project Appraisal Document) The projec▼ s development objective is to provide high-capacity and quality transport connections between targeted development zones and urban areas, as well as develop all-weather road access in selected rural areas of Ningxia Autonomous Region. Has the Project Development Objective been changed since Board Approval of the Project?

Yes No Public Disclosure Authorized Component(s)

Component Name Component Cost A. Guyaozi- Expressway 224.17 B1. Road Network Improvements - Improvement of Local Roads 8.15 B2. Road Network Improvements - Improvement of National Highway G211 17.05 C.1 Institutional strengthening - Technical Assistance on Road safety, Maintenance, and Transport 0.40 and Logistics C.2 Institutional strengthening - Training 0.73 C.3 Institutional strengthening - Procurement of Road Maintenance Equipment 3.82

Public Disclosure Authorized Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Highly Satisfactory Highly Satisfactory Overall Risk Rating Low Low Public Disclosure Copy

Implementation Status Overview

Page 1 of 5 Public Disclosure Authorized The World Bank Report No: ISR14312

The project implementation progress continues to be satisfactory. All the local roads and most of the Guyaozi–Qingtongxia Expressway (GQE) funded by the project have been completed and opened to traffic. Environmental impact was kept in minimum during construction, and significant efforts have been put into site restoration and environmental protection. In addition, land acquisition and house demolition for the GQE had been completed with compensations being fully delivered to the affected people in compliance with the RAP. The project is on track to achieve its PDO.

Locations Country First Administrative Division Location Planned Actual China Ningxia Huizu Zizhiqu

China Ningxia Huizu Zizhiqu Wuzhong

Public Disclosure Copy China Ningxia Huizu Zizhiqu Qingtongxia Shi

China Ningxia Huizu Zizhiqu Shi

China Ningxia Huizu Zizhiqu Shi

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Traffic volume along GQE Number Value 9160.00 13170.00 Date 31-Dec-2013 30-Jun-2015 Comments Traffic volume along the existing roads Text Value Guyaozi-Lingwu 6967 Guyaozi-Lingwu 6750 Guyaozi-Lingwu 5500 Lingwu-Wuzhong 1548 Lingwu-Wuzhong 1401 Lingwu-Wuzhong 1400 Wuzhong-Qingtongxia 14254 Wuzhong-Qingtongxia 14333 Wuzhong-Qingtongxia 8600 Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Comments Increased number of rural people with access Number Value 0.00 240000.00 240000.00 to all-weather road in project affected areas Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Comments

Intermediate Results Indicators Public Disclosure Copy

Page 2 of 5 The World Bank Report No: ISR14312

Indicator Name Core Unit of Measure Baseline Current End Target Accident rate along GQE corridor Number Value Date Comments This set of indicator is listed as breakdown below. Lingwu-G307 Number Value 12.00 7.00 9.00 Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Wuzhong-Wulingqing Number Value 8.00 5.00 6.00 Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Public Disclosure Copy Breakdown Comments Traffic Volumes on selected rural roads Number Value Date Comments This indicator is broken down as follows Traffic volume on rural road 9 - Gaoxing- Number Value 300.00 380.00 460.00 Xinsheng Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Traffic volume on rural road 8 - S101 # Number Value 360.00 500.00 550.00 Yujialiang Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Traffic volume on rural road 7 - Hongxing- Number Value 220.00 312.00 340.00 Yangliu Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Traffic volume on rural road 6 - Liujiapu- Number Value 200.00 290.00 310.00 Lijiagou Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Traffic volume on rural road 5 - Nanliang- Number Value 340.00 490.00 520.00 Lizhuangzi Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Traffic volume on rural road 4 - Daodunzi # Number Value 180.00 260.00 280.00 Wangchaoling Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Public Disclosure Copy

Page 3 of 5 The World Bank Report No: ISR14312

Traffic volume on rural road 3 - Wanglejing- Number Value 400.00 590.00 640.00 Niumaojing Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Traffic volume on rural road 2 - Majiatanzhen- Number Value 180.00 269.00 280.00 dayangqicun Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Traffic volume on rural road 1 - Shabatou- Number Value 227.00 314.00 350.00 Nongchang2 Sub Type Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Breakdown Comments Value

Public Disclosure Copy Accident rates on NH G211 Number 13.00 8.00 6.00 Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Comments Establishment of Traffic safety improvement Text Value The report was reviewed by Actions applied in selected action plan and application in selected corridors the Bank corridors Date 28-Feb-2014 30-Jun-2015 Comments Establishment of Framework and action-plan to Text Value The studies was incorporated Framework and Action plan improve the efficiency of transport services in the Guidelines of the 12th established Five-Year Plan of Ningxia. Date 28-Feb-2014 30-Jun-2015 Comments Completion of Road Maintenance Assessment Text Value The study was completed and Will apply the strategy and and long-term Road Maintenance Strategy approved. provide continuous recommendations. Date 28-Feb-2014 30-Jun-2015 Comments Travel time on GQE Number Value 2.00 0.80 Date 30-Apr-2010 28-Feb-2014 30-Jun-2015 Comments

Data on Financial Performance (as of 05-Jul-2013)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date

Public Disclosure Copy P096920 IBRD-78800 Effective 13-May-2010 22-Jul-2010 27-Oct-2010 30-Jun-2015 30-Jun-2015

Disbursements (in Millions)

Page 4 of 5 The World Bank Report No: ISR14312

Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P096920 IBRD-78800 Effective USD 250.00 250.00 0.00 250.00 0.00 100.00

Disbursement Graph Public Disclosure Copy

Key Decisions Regarding Implementation N/A

Restructuring History There has been no restructuring to date.

Related Projects There are no related projects. Public Disclosure Copy