Hunter Economic Infrastructure Plan

RDA Hunter in conjunction with Infrastructure NSW Economic analysis and business cases prepared by Hyder Consulting Released: October 2013

Context • Funded by the Commonwealth; • Focus on goods and freight transported by road; and • Mining communities impacted due to increasing levels of road freight.

Economic Infrastructure requirements considered • • Rail – Hunter Valley rail Corridor • Electricity • Road – future of freight • Water

Outcomes • Further investigation on roads and water • An integrated plan for the region; • Whole of supply chain view presented; • Improved export capacity; • Support for Hunter’s future economic growth.

2013 - 2020 Investment in the Hunter: $1,014,895,000

Status of projects in Hunter Economic Infrastructure Plan

Recommended projects Funding announced Date(s) Status

01. Duplication of Cwlth $51.9 million June 2018 Built & Open and approaches, Island NSW $51.9 million Cwlth $45 million 02. New England bypass of Scone March 2020 Built & Open NSW $45 million 03. Upgrade of two at Maitland NSW (HIIF)$45 million Sept 2016 Built & Open Restart NSW, 04. Construction of new bridge over the Great Construction progressing. Bridges for the Bush Feb 2020 Northern Railway at Girders above the rail line $62 million

05. Widening of Singleton Gowrie gates rail Rebuilding NSW July 2019 Built & Open underpass and approaches $29 million

06. Upgrade to dual April 2020 – Early stages of upgrade. carriageway Belford to & Rebuilding NSW utility grade separation of the Golden Final detailed planning $85 million relocation Highway/New England Highway intersection

07. Golden Highway Corridor Strategy, inc. NSW $1 million upgrades between NEHighway and Denman. Cwlth $23.795 m Sections being progressively NSW $23.795 m 2016 - 2022 08. And upgrades through Denman or upgraded construction of a Denman bypass, and Rebuilding NSW between Denman and Ulan $85 million

09. Bypass of the New England Highway around Rebuilding NSW Public comment on concept Feb 2020 Singleton – Central Corridor (6.5 km) $92 million & REF, closed

10. Bypass of the New England Highway around Rebuilding NSW Preferred Option released Mid-2020 Muswellbrook (8.5 km) $266 million for community feedback

11. Reconstruction of NEHighway Pavement in Rebuilding NSW June 2019 Built & Open parts from Aberdeen to Willow Tree $68 million 12. Bypass of the around Estimated cost 2013: 2020 – 2025 Long term planning $12 - $15 million NSW Budgets: Stalled. 2016- 17: $14 million; 13. Lower Hunter Freight Rail Corridor Project – 2017 -18: $11.8 million 2016 - 2025 Included 2017 IA: AIPlan – support preservation of corridor as a priority 2018-19: $14 million Omitted IA Infrastructure Priority List, 2020

14. Water Supply Assessment: The NSW Government to undertake an High Priority Initiatives, 2020 analysis of industry water requirements to Infrastructure Plan: Town support growth under various drought Office of Water (NSW) and City, as well as National scenarios, and provide industry with the Hunter to receive part of water security strategies. necessary up-to-date information to manage 2015 – 2020 $1bn reservation in NSW Nov 2018 risks associated with water supply & drought. Rebuilding NSW Build on studies of impact on mining to Greater Hunter regional include agribusiness and power generation. water strategy Also research delivery efficiency models.