Prepared For: Consultancy Contract C26157REV/JPNS- 2013-02-01 Kazakhstan Renewable Energy Financing Facility (KazREFF) - Strategic Environmental Review
Renewable Project Environmental Review Report - Wind
June 2014
ERM Japan Ltd. The Landmark Tower Yokohama 19th Floor, 2-2-1 Minatomirai, Nishi-ku YOKOHAMA 220-8119 Japan www.erm.com
The world's leading sustainability consultancy
Contents
1.0 INTRODUCTION 1
2.0 RESOURCE AVAILABILITY AND POTENTIAL 2
2.1 RESOURCE AVAILABILITY 2
2.2 RESOURCE POTENTIAL 6
2.3 TRANSMISSION CAPACITY AND CONSTRAINTS 6
2.3.1 Existing Conditions 7
2.3.2 Anticipated Development 10
2.4 EXISTING PROJECTS 11
2.5 KNOWN PROPOSED PROJECTS 11
3.0 AVAILABLE AND PRACTICAL TECHNOLOGIES 14
3.1 COMPONENTS 14
3.1.1 Met Mast/Towers 15
3.1.2 Wind Turbines and Foundations 16
3.1.3 Support Buildings 17
3.1.4 Access Roads 18
3.2 GRID CONNECTIVITY 18
3.3 SITE DESIGN AND CONFIGURATION 20
3.3.1 Wind Farm Layouts 22
3.3.2 Construction 23
3.3.3 Commissioning, Operation, and Maintenance 24
3.3.4 Decommissioning 24
3.4 DEVELOPMENT COSTS 25
3.5 SUPPLY CHAIN IN KAZAKHSTAN 25
4.0 ENVIRONMENTAL AND SOCIAL CONSTRAINTS 27
The world's leading sustainability consultancy
5.0 KAZREFF PROJECT APPRAISAL - ENVIRONMENTAL AND SOCIAL PERFORMANCE REQUIREMENTS 31
5.1 EBRD REQUIREMENTS 31
5.1.1 Category A 32
5.1.2 Category B 33
5.2 KAZAKHSTAN REQUIREMENTS 33
5.3 KAZREFF APPRAISAL PROCESS 35
5.3.1 Initial Screening 36
5.3.2 Documentation Review and Approval/Feedback 36
6.0 APPENDICES 38
The world's leading sustainability consultancy
1.0 INTRODUCTION
This Renewable Project Environmental Review (RPER) Report for Wind in Kazakhstan is one of four separate reports (other RPER reports were prepared for solar photovoltaic, small hydropower, and biogas) that have been prepared by Environmental Recourses Management (ERM) for the European Bank for Reconstruction and Development (EBRD). These RPER reports are prepared to support the Kazakhstan Renewable Energy Financing Facility (KazREFF) Strategic Environmental Review (SER) and provide a resource to provide guidance to developers and their consultants, as well as technical evaluators of proposed renewable projects, by identifying areas of good potential and the nature and scale of technologies that can be applied in different parts of Kazakhstan.
The source documents which have informed this RPER report are as follows:
• ERM KazREFF Strategic Environmental Review, Final Inception Report, 29 May 2013; • ERM KazREFF Strategic Environmental Review, Draft Scoping Report, 21 May 2013; • Mercados Energy Markets International, Kazakhstan Renewable Energy Market Study, Draft Final Report, July 2013 (ÅF-Mercados EMI (2013)); • United Nations Development Programme/Global Environment Facility, Kazakhstan- Wind Power Market Development Initiative, 2006 (UNDP 2006); • Black and Veatch, Renewable Energy in Ukraine Technical Report: Wind, 1 September 2011 (Black and Veatch 2011).
These sources have been supplemented by additional research carried out by ERM and additional sources of data identified in the text.
ERM 1 KazREFF RPER Report WIND – June 2014
2.0 RESOURCE AVAILABILITY AND POTENTIAL
This section of the report identifies the characteristics of the wind rich resource areas of the country and the regions of Kazakhstan where wind farm development is technically feasible. It also assesses the nature and extent of constraints to wind farm development.
2.1 RESOURCE AVAILABILITY
Kazakhstan is the world’s ninth largest country being some 2.7 million km2 in extent. Figure 1 shows the different oblasts of Kazakhstan. The western regions are dominated by extensive lowlands that include Aral and Caspian Seas, while the centre of the country is characterised by rolling hills with peaks up to 1,565 m. The south eastern and south western parts of the country are bordered by mountain ranges. Approximately 10 per cent of the country is occupied by mountains (Figure 2). The expanse of land and terrain within Kazakhstan indicates the potential wind resource that could be available for exploitation.
Figure 1 Location Map
ERM 2 KazREFF RPER Report WIND – June 2014
Figure 2 Topography Map
Kazakhstan is not wind resource limited (i.e. it will not be the availability of suitable wind regimes that will limit the amount of wind turbines deployed). Neither is it limited by available land. On the contrary, large swaths of the country have a very significant wind resource.
A wind atlas of Kazakhstan was developed as part of the United Nations Development Programme/Global Environment Facility (UNDP/GEF) Kazakhstan wind power market development initiative and is presented in Figure 3. The atlas shows the long-term average wind speed at 80 m above ground level, at 9 km resolution for much of the country, and at 100 m resolution for nine areas of particular interest. Green areas show areas of lower wind speeds and red areas show areas of high wind speed. It should be noted that the wind atlas shows the average wind speed of the various areas of Kazakhstan. Periods during which wind speed generation is higher are not taken into account. Studies have shown that wind speeds in Kazakhstan are higher in the winter months of December to January1.
A typical wind turbine can produce power at a minimum wind speed of 3.5 m/s, with the maximum wind speed for producing power being 25 m/s2. The optimum speed for power generation is typically 14 m/s. The UNDP/GEF atlas identifies that 50,000 km2 of territory across nine of the country’s 14 oblasts have a good wind resource (7—8 m/s). The north contains the highest wind power generation potential with Aqmola and North Kazakhstan oblasts averaging wind speeds of 8 m/s. Almaty Oblast
(1) Almaz Akhmetov (2012) Potential of Wind Power in Kazakhstan, LAP Lambert Academic Publishing AG & Co KG (2) http://webarchive.nationalarchives.gov.uk/+/http://www.berr.gov.uk/files/file17821.pdf
ERM 3 KazREFF RPER Report WIND – June 2014
(southern Kazakhstan) also contain areas of very good (8—9 m/s) wind speeds and contains exceptional wind speeds (>9 m/s) in mountainous areas. The atlas also identifies significant wind resources in west Kazakhstan with the areas with greatest potential located in Mangistau Oblast. The Eastern Oblast of Kazakhstan has the least potential for wind farm development with average wind speeds of 5 m/s. However, development is still possible in this oblast as a typical wind turbine can still operate in these conditions.
Table below highlights the wind power generating capacity of the three regions of Kazakhstan with the most potential for wind farm development. This potential in relation to transmission capacity and constraints is discussed in Section 2.3.
Table 1 Regional Wind Farm Potential
Transmission Region Wind Farm Potential (MW)3
West 2,200
North 11,878
South 3,162
Total 17,240
Source Åf-Mercados EMI (2013)
3 Unit of power equal to one million watts. (MBt in Russian)
ERM 4 KazREFF RPER Report WIND – June 2014
Figure 3 Wind Atlas for Kazakhstan Map
ERM 5 KasREFF SER RPER WIND – June 2014
2.2 RESOURCE POTENTIAL
Due to Kazakhstan’s wind energy potential and the increased demand for electricity in the country, a programme for wind farm development was created in by the Ministry of Energy and Mineral Resources (MEMR) with the support of United Nations Development Program (UNDP). The Kazakhstan – Wind Power Market Development Initiative” project began in December 2004 and finished in June 2011. The Project has been financed by the Global Environment Facility (GEF) with the Implementing Agency being the UNDP and the MEMR — now the Ministry of Industry and New Technology (MINT) — of the Government of the Republic of Kazakhstan (RoK) as the Executing Agency4.
This programme as well as other initiatives, was used by the RoK government as a basis for a series of actions and targets for wind development from 2015 to 2030 which encourages the construction of wind farms generating a capacity of 250-300 MW by 2015 and a capacity of up to 2,000 MW by 2030. If capacity is constructed according to these timescales the electricity generated would amount to 1TWh5 by 2015 and up to 5 TWh by 2030.
Kazakhstan has very large coal, oil, gas and uranium resources that are all being actively exploited. The country is the third largest producer of crude oil in Central Asia, behind Russia and China and has the third largest reserves outside of the OPEC member countries. One result of the abundance of energy resources has been the lack of a driver for developing wind energy on the basis of a scarcity of indigenous energy resources. Nevertheless, other drivers needed to be (and were) identified such as the need to reduce greenhouse gas emissions, to strengthen local power supply and to act as an economic stimulus6.
2.3 TRANSMISSION CAPACITY AND CONSTRAINTS
To realise the wind energy potential of Kazakhstan wind farm locations will need to be in proximity to existing transmission lines and the existing electricity grid will need to have adequate capacity to receive the power generated. Sites that are situated a great distance from load centres or major transmission lines face greater development costs and are generally less favourable than sites with better access to these facilities. Larger projects are able to locate farther away from transmission while smaller projects are
4 Lessons learnt from the UNDP-GEF project “Kazakhstan — Wind Power Market Development Initiative, UNDP Kazakhstan, 2011. 5 Unit of energy equal to 1000 watt hours. 6 Lessons learnt from the UNDP-GEF project “Kazakhstan — Wind Power Market Development Initiative, UNDP Kazakhstan, 2011.
ERM 6 KasREFF SER RPER WIND – June 2014
located closer to transmission, due to economies of scale of larger projects to absorb higher transmission costs7.
2.3.1 EXISTING CONDITIONS
The grid in Kazakhstan is state-owned and operated by the Kazakhstan Electricity Grid Operating Company (KEGOC). There are also 21 regional energy companies (RECs) that distribute electricity on a regional monopoly basis. Due to the size of Kazakhstan the network is characterised by long distance transmission. The Kazakhstan transmission network dates back to the Soviet era and has a history of underinvestment. However at present it has sufficient capacity and no voltage problems. The majority of the population is connected to the grid, less than 5 per cent of the population, located primarily in rural areas, are without electricity. However, in some areas power cuts or discontinuous supply are not uncommon due to grid capacity issues and a lack of local generation facilities. In addition, in some regions the industrial base has expanded and investment in power infrastructure has failed to keep pace. Figure 4 shows the areas of greatest population density and domestic energy demand in Kazakhstan.
Figure 4 Population Map by Oblast
The electricity grid is separated into three regions west, north and south (Figure 5). It has a general north-south split in generation and demand with approximately 80 per cent of the electricity being produced in the north near coal reserves and 70 per cent being used in the same industrialised region (UNDP/GEF 2011). The transmission system operates at 500 kV and 220 kV
7 Black & Veatch 2011
ERM 7 KasREFF SER RPER WIND – June 2014
and consists of 24,101 km of 35 - 1150 kV overhead transmission lines and 74 power substations with an installed capacity of 34,408 MVA (see Figure 6). A 1,100 km 500 kV electricity transmission system has connected the north and south regions since 2009. Due to demand growth in the southern zone the transmission lines connecting north and south are fully loaded, and in the period of peak demand (winter) they are reported to be occasionally overloaded.
The northern electricity grid contains links to Russia and Central Asia and the southern network contains links to Kyrgyzstan and Uzbekistan. The west of the grid is isolated from the remainder of the national electricity system and has interconnections with Russia.
From 2011 to 2013 power consumption significantly exceeded energy production, which, taken into account transmission losses has highlighted a deficit of approximately 800 MW. This deficit is currently overcome by importing electricity from neighbouring countries. Demand is projected to reach 145 TWh by 2030 from the current level (CAGR of 2.6 per cent) (Åf- Mercados EMI 2013).
Figure 5 Transmission Regions in Kazakhstan
658 209 700 1173 1180 390 3195 480 850 1720 1609 700 160 95 337 1823
348
90 1862 160
160 320 1020 860 1620 1020
Source Åf-Mercados EMI (2013)
The proximity of existing transmission lines to areas of high wind power potential and the good correlation between seasonal wind levels and the peak
ERM 8 KasREFF SER RPER WIND – June 2014
in demand for electricity (the winter months) create conditions that favour the successful integration of wind power development in Kazakhstan.
In particular developing wind power projects in the south could help solve the problem of the overload of the north-south transmission lines. The northern zone has an excess of generation, but development would still be an advantage in order to reduce the power imports from neighbouring Russia. The western grid operates separately and currently has a load shortage of about 100 MW, which is also covered by power import from Russia. Again wind power development would reduce Kazakhstan’s reliance on imports from Russia.
Figure 6 Transmission System Map
Table 2 below gives an overview of the distribution of potential wind power in Kazakhstan, the proposed scale of development by 2030 according to the MEMR and UNDP wind farm development plan and the grid capacity by region.
Table 2 Wind Farm Potential and Grid Capacity in Kazakhstan
(MW) Wind Farm Grid capacity* Wind Farm Potential proposed in 2030 (UNDP)
West 2,200 601 250
North 11,878 2,705 800
ERM 9 KasREFF SER RPER WIND – June 2014
South 3,162 718 950
Total 17,240 4,024 2,000
* Based on expert judgement, taking 20 per cent of installed capacity as the guiding rule of thumb. Source: Åf-Mercados EMI (2013)
The table shows that approximately 20 per cent of potential installed capacity in the three regions could currently be connected to the grid. In order for Kazakhstan to achieve its potential of 17,240 MW generated by wind power the grid would require upgrading. The proposed target of generating 2,000 MW generated by 2030 are achievable with the existing transmission grid.
Based on power demand and transmission connectivity all three regions have wind farm development potential. However, there are some other considerations that need to be taken into account which may present barriers to wind development.
The west, due to its isolation may have stability problems if no grid development projects are implemented. For a power grid to remain stable, the frequency and phase of all power generation units must remain synchronous within narrow operational limits. Wind power generation is not constant and as the western grid has limited connections it may not be able to handle small frequency changes. The north, however, has a balancing advantage, due to sufficient transmission capacity to the Russian grid, which has a relatively stable power system. This region also has the highest potential capacity and strong connections to the southern region.
2.3.2 ANTICIPATED DEVELOPMENT
The suitability of the above regions for development of wind power assumes that there is no investment in the electricity grid of Kazakhstan. However it should be noted that considerable network development both on-going and planned is being undertaken by Government of the RoK and KEGOC.
Projects planned, or currently being implemented, include:
• Modernization of the national electrical network (NEN) to be completed by 2016. The project comprises reconstruction of the majority of substations and construction of some new transmission lines; • Construction of a 500 kV substation "Alma" ( located in the area of Almaty) with connection to the NEN This will eliminate the overloading of existing "Almaty" substation and ensure the reliability of power supply to the Almaty region; and
ERM 10 KasREFF SER RPER WIND – June 2014
• Reconstruction of a 220 kV overhead line central main substation in Astana.
There are also plans for connecting the western grid to the national grid by 2030.
2.4 EXISTING PROJECTS
At present there is only one wind farm in operation in Kazakhstan. The Kordai wind farm has a capacity of 1.5 MW (two turbines of 750 kW) and is located in the south of Kazakhstan in Zhambyl Oblast. This project is scheduled to be expanded to a capacity of 20 MW by the end of 2013.
2.5 KNOWN PROPOSED PROJECTS
In addition to small-scale local wind farms, larger scale installations are planned. The 2006 UNDP/GEF identifies 26 potential large wind farm locations which could be developed due to their optimal conditions in terms of grid connections and wind speeds. Not all of these sites however are likely to be developed due to other technical development constraints. At present there are 10 sites identified for development in 2014 by the Ministry of Industry and New Technologies (MINT) (see Table 3 and Figure 7). Half of these sites are located in the northern grid with only two located in the western region.
Each of these projects should be evaluated against the technical constraints outline in Section 3.3 and the environmental social constraints outlined in Section 4.0. These projects are scattered throughout Kazakhstan and therefore, do not appear to contribute to adverse cumulative impacts issues.
Table 3 MINT Wind Farm Sites to be Developed by 2014
Site Number Site Geographic Grid Installed Region capacity, MW (MBt)
1 Shelek corridor Southern South 51 Kazakhstan
2 Djungar gates Eastern North 50 Kazakhstan
3 Upper Tainti, Eastern North 24 East Kazakhstan Kazakhstan
4 2 km to the East Central North 10 of Kargalinsk
ERM 11 KasREFF SER RPER WIND – June 2014
Site Number Site Geographic Grid Installed Region capacity, MW (MBt)
city, Karagandy Kazakhstan
5 2 km to the Central North 35 South-West of Kazakhstan Yermentau, (Mount Yermentau)
6 5 km to the Central North 40 West of Arkalyk Kazakhstan city, Kostanay, (Mount Arkalyk)
7 40 km to the Western West 40 North-East of Kazakhstan. Atyrau city (near Karabatan)
8 10 km South- Western West 40 West of Fort- Kazakhstan Shevchenko city, Mangistau
9 Zhysymndik South South 40 Kazakhstan
10 30 km South- Southern South 20 West of Qorday Kazakhstan Zhambyl
Source: (Åf-Mercados EMI (2013)
ERM 12 KasREFF SER RPER WIND – June 2014
Figure 7 Location of Proposed MINT sites for 2014
Source: MINT (2010) www.kazembassy.org.uk
ERM 13 KasREFF SER RPER WIND – June 2014
3.0 AVAILABLE AND PRACTICAL TECHNOLOGIES
This section looks at the type of technology that would be employed for wind farm development in Kazakhstan. It details the key activities and environmental and physical constraints to be taken into consideration for the construction, operation and decommissioning of a potential site. It also discusses the current status of the wind power supply chain in Kazakhstan.
3.1 COMPONENTS
Three types of wind project are presently being considered for wind power generation in Kazakhstan. These projects are as follows:
• Small wind farms with less than 20 MW of capacity; • Medium size wind farms with capacities ranging from 20 MW to 100 MW; and • Large wind farms with greater than 100 MW of capacity (see Table 4).
In general, a turbine’s generating capacity typically extends to 2.5 to 3 MW with 5 MW models currently under development.
The following sections detail the typical wind farm components required for these projects, the layout of these components and the performance and operation of a typical wind farm. Project costs and component availability in Kazakhstan are also discussed.
Table 4 Typical Wind Farm Sizes
System Size Small Medium Large
Capacity <20 20-100 >100
No. of Turbines 7-20 7-50 50+
Source: Black and Veatch 2011
There are four main wind farm components described in the sections below:
• Meteorological (met) masts (and occasionally also met mast foundations); • Wind turbine foundations and wind turbines; • Buildings housing electrical switchgear, supervisory control and data acquisition equipment, and possibly spares and maintenance facilities; and • Access roads.
ERM 14 KasREFF SER RPER WIND – June 2014
3.1.1 MET MAST/TOWERS
Once a potential wind farm site is identified a met tower is usually installed to monitor the wind conditions of the site and confirm its suitability. These towers typically measure the wind speed, wind direction, temperature, pressure and humidity at the site. This data is important in developing a robust template for site design. The number of towers required is linked to the terrain of the proposed site. Wind farms located in complex terrain are more likely to require more than one mast to give an adequate picture of the wind resource across the site.
Typically there are three types of tower used in wind farm development. An initial small mast of approximately 40 m is installed first which requires no foundations and can be secured by guy ropes. These towers are usually installed 1 to 3 years before site construction. The data collected from these towers is extrapolated to reveal the predicted wind speeds at full wind turbine height (80-100m).
If after this data is analysed, the site is considered suitable for development, then met towers of wind turbine hub height are installed (usually approximately 80 m), as necessary, to confirm the monitoring results. These towers are usually in situ for 2 to 3 months before turbine construction.
Usually full turbine height permanent met towers are installed to monitor wind resources for operating wind farms. These towers typically require foundations and help ensure the efficient performance of installed turbines as shown in Figure 8.
Figure 8 Typical Permanent Met Mast
ERM 15 KasREFF SER RPER WIND – June 2014
3.1.2 WIND TURBINES AND FOUNDATIONS
There are commonly two types of wind turbine, vertical and horizontal axis machines. The most common design is the horizontal three bladed axis turbines. Two bladed axis turbines are generally cheaper however they have a higher operational noise than three bladed axis turbines and, depending on the location of a proposed development this may affect their use. The main components of a utility-scale wind turbine are presented below:
Turbine - A wind turbine comprises of a tower that supports a nacelle, the main shell containing an electric generator and the turbine blades attached via a hub. The nacelle has an anemometer attached so that the direction in which the blades face can be altered to maximise wind capture. It also houses the mechanical machinery and a device known as "the yaw mechanism", which allows the machine to turn itself towards the prevailing wind (Figure 9).
Figure 9 Schematic of Wind Turbine
Images courtesy of http://www.boem.gov/Renewable-Energy-Program/Renewable-Energy- Guide/Offshore-Wind-Energy.aspx and http://www.intechopen.com/books/advances-in- wind-power/wind-turbine-generator-technologies
Blades - The majority of rotor blades are made of glass reinforced plastic or wood epoxy but can be of aluminium or steel. A turbine works by the movement of wind through the rotor blades creating energy which spins a shaft leading from the hub of the rotor to a generator. This process results in electricity generation. A typical 80 m high tower contains a rotor diameter of approximately 90 m giving an overall operating height of 125 m.
ERM 16 KasREFF SER RPER WIND – June 2014
Tower - The tower of a turbine is installed using prefabricated tubes. Tubular towers are preferred due to aesthetic qualities and the ability to use the base of the tower for the switchgear and controls. Such a design also makes access to the nacelle safer, as a ladder can be placed inside the tower. Tower height varies depending on the manufacturer and amount of power generated. Rotor length also determines the minimum height of the tower as an appropriate clearance is required for the blades to turn safely. Typical turbine towers range from 80 to 100 m in height.
Base/Foundation – The detailed design of foundations depends on the type of foundation used and the ground conditions of the site. Turbine towers are generally fixed to a concrete foundation up to 18 m in diameter and 4 m deep, dependent on the size of the turbine. A turbine foundation must support the weight of all of the turbine equipment as well as the thrust load produced by the rotors. The surface of the foundation is normally flush with the surrounding ground (see Figure 10). If a site is located in land normally used for agricultural purposes, agricultural use can continue up to the edge of and over the foundations. Specially designed foundations such as piled foundations can also be used to minimise ground disturbance. For example wind erosion is widespread in Kazakhstan in arid and semi-arid areas, special mitigation measures such as piled foundations could be utilised to minimise construction impacts.
Figure 10 Wind Turbine Foundation Schematic and Photograph
Photo courtesy of http://dnrc.mt.gov/Trust/Wind/JudithGap.asp
3.1.3 SUPPORT BUILDINGS
Wind farms require a central computerised monitoring system, which controls the operation of the turbines. As mentioned above, switch gear, transformer and control equipment can occasionally be located in the turbine tower, however sometimes an additional building is required adjacent to the turbines. This on-site equipment is linked electronically to an operations headquarters off-site. Most wind farms do not contain permanent onsite staff however some larger sites may require staff during operation.
ERM 17 KasREFF SER RPER WIND – June 2014
The control unit is used to manage the turbines to avoid damage to equipment and enable a complete shut down when wind speeds are too high. Turbines can also be shut down when wind speeds are too low to be commercially viable.
The transformer is used to increase low voltages produced by the wind turbines to a higher voltage which can then be collected by a substation.
3.1.4 ACCESS ROADS
During the construction and operation phases wind turbines will normally require adequate means of vehicular access, capable of supporting heavy goods vehicles (HGV) carrying machinery. Stone and aggregate for access tracks and hard standing, concrete and steel for foundations, and cabling to transfer electricity, for example, will all need to be transported to site.
Extra-long vehicles carrying wind turbine rotors and towers (abnormal loads) will also be required to access the site. This will require the development of access roads to the site and connections to exiting road networks. In Kazakhstan, roads are the main infrastructure for haulage. In Kazakhstan many rural roads are in poor repair. A Strategy of Transport Sector Development for works up to 2015 has been developed, however the strategy is primarily focused on major transport corridors. In rural areas roads may not currently be accessible to HGVs or be suitable for abnormal loads. An abnormal loads and HGV assessment would be necessary for any potential wind farm site. Potential wind farm areas in more rural areas may therefore be inaccessible for development without substantial road infrastructure costs.
3.2 GRID CONNECTIVITY
Wind turbines are induction generators that require reactive power, depending on the output power and power factor correction, which can cause self-excitation, thus increasing harmonic content. Increasing harmonic content can create stability concerns for an interconnection, especially within weaker power systems (e.g. radial distribution lines). Different padmount transformer configurations can also increase or decrease the amount of fault current onto the system, so it is important to design the system to keep the zero sequence impedance to a minimum, but still have a ground reference (so no overvoltage scenarios occur). Series neutral reactors or resistors can be added to the neutral connections of the collection system to increase the zero sequence impedance, thus decreasing the fault current. The on-site collection system is typically operated at voltages of 25 to 35 kV. Wind projects of different sizes have different interconnection concerns as discussed below.
Smaller interconnections (< 20 MW) are typically more feasible to interconnect at lower voltages due to the equipment necessary to build out an interconnection substation for the wind farm. These interconnections would
ERM 18 KasREFF SER RPER WIND – June 2014
be best suited at the lower transmission voltage and distribution levels. The other reason for this is that smaller wind farms will typically serve local load instead of delivering power across long high-voltage transmission lines. The only caveat is that intermittent resources should not be interconnected to radial distribution systems due to stability concerns at the local distribution level. Smaller scale wind farms can typically deliver the power through one medium voltage underground feeder which may tap directly into the distribution system at an interconnection substation Each individual wind turbine will require a low voltage to medium voltage step-up transformer, although some newer models have built-in transformers inside the nacelle. A step-up transformer from the medium voltage side of the wind turbine pad mount transformers may not be necessary if the feeder voltage is the same as the distribution voltage. Distribution interconnection codes vary and should be used to determine requirements.
Medium scale interconnections (20-100 MW) are more feasible to interconnect at the medium transmission voltages, such as 220 kV and 330 kV. These project substations require larger equipment, but are acceptable for medium scale wind farms. These wind farms may serve local load, but can also be delivered into key transmission substations which step up to higher voltages. It is also optimal to locate these at substations with multiple outlets to avoid curtailment and ensure delivery of power. Medium scale interconnections typically require two to four medium-voltage feeders that collect into enclosed switchgear within a new collector substation at the project site which then is connected via overhead transmission to an interconnection substation. The switchgear may also be located within an existing substation and interconnected to a built out bus within the fence.
Large scale interconnections (>100 MW) are injected at higher voltage substations that have multiple outlets. The reason for this is to allow for delivery dispersed between multiple transmission lines and to avoid curtailment.
Figure 11 shows an example of a wind turbine with connecting cables and sub station.
ERM 19 KasREFF SER RPER WIND – June 2014
Figure 11 Typical Grid Connection for Wind Turbine
Source: Black & Veatch 2011
3.3 SITE DESIGN AND CONFIGURATION
As a rough guide, the installed capacity of the wind farm is likely to be 18 to 48 hectares per MW8. Lower capacities relate to areas of forest land while higher capacities relate to areas of farmland. As a general rule grouped turbines need to be positioned to allow a separation distance of around 3-4 rotor diameters between turbines. This limits energy loss through wind shadowing from upstream machines. Due to this spacing not all land within a proposed site is impacted by development; only two to eight per cent of a site is typically impacted by development 9 . This affected land can be separated into permanent structures of turbines and access roads and temporary impacts of laydown areas and access routes. Typically, the existing land use activities can continue during operation (e.g. farming and grazing).
Several factors should be considered when selecting a site and designing its configuration. The quality of the resource is an obvious primary consideration; however, there are some other significant issues in Kazakhstan, identified in the SER that should be considered when siting power facilities:
• Ground slope – In general ground slopes of less than 20 per cent are optimal for wind power plants. While plants can be designed to work
8 Denholm, P. et al, “Land-Use Requirements of Modern Wind Power Plants in the United States.” National Renewable Energy Lab NREL/TP-6A2-45834, August 2009.
9 Black & Veatch 2011
ERM 20 KasREFF SER RPER WIND – June 2014
on more steeply slopes lands, it is more economical to work of flatter lands. Access roads are also needed within the facility during construction and later for routine maintenance, so minimal slope is optimal.
• Extreme weather – Kazakhstan has cold winters which can reach as low as -58 °C and hot summers which can reach as high as 53 °C. Much of the north of the country is affected by snow in the winter. Such extreme temperatures could impact upon turbine functionality and may require extra servicing or advanced specification equipment. This is particularly relevant since the north of Kazakhstan has a high potential for wind development which is in highest demand in the winter months. Areas in the west of the country have an arid desert climate which could have implications on turbine foundation construction and turbine functionality. This may also impact project economics and should be considered for projects in the northern and eastern oblasts. In addition, areas with winds that are extremely strong may require design modifications to prevent damage to the turbines.
• Flood prone areas – Construction of wind power facilities in areas prone to flooding could result in the damage of turbine foundations and associated infrastructure. In general, construction in flood prone areas should be avoided.
• Seismicity, mudflows, and landslides - Construction of wind power facilities in areas of high seismicity or in areas prone to mudflows and landslides could result in the damage of turbines and associated infrastructure. In general, construction in high risk areas for these hazards should be avoided.
• Contaminated lands – Construction of solar facilities on contaminated lands may be a beneficial use of these degraded areas; however, special consideration must be made to ensure the health of workers that could be exposed to contaminants at the surface (e.g. nuclear testing areas) or below ground during construction.
• Land use - Wind power facilities would not be economically feasible on open water, especially given the abundance of available land in Kazakhstan; therefore, it is unlikely any facilities would be water- based.
• Proximity to transmission grid and loading – In general, facilities should be located proximate to existing substations with capacity on the transmission grid. Wind power facilities become to become less economical at increasing distances from substations due to the costs
ERM 21 KasREFF SER RPER WIND – June 2014
associated with extending distribution or transmission lines to the wind power plant.
3.3.1 WIND FARM LAYOUTS
The layout of a wind farm is site specific; it looks at the most efficient placement of turbines combined with the landforms/landscape the turbines are set within. The landscape of Kazakhstan is extremely diverse therefore no generic layout will suit all sites.
The most common layouts are a single line and grid (see Figures 12 and 13). These layouts are generally suited to the two types of terrain commonly used for wind farm siting, hill ridges and flat land. Hill ridges typically use a single line layout as it generates the best wind exposure. In the case of a site on flat land, a grid layout enables the wind resource to be captured in all areas of the site.
Figure 12 Photograph of a Ridge Line Wind Farm Installation
Source : http://www.ostenergy.com/en/Wind
ERM 22 KasREFF SER RPER WIND – June 2014
Figure 13 Photograph of a Grid Layout Wind Farm Installation
Source: http://www.snh.gov.uk/docs/A337202.pdf
3.3.2 CONSTRUCTION
Construction of a wind farm site is site specific as it relates to the type, size and location of the proposed wind farm. In general however the construction of a typical wind farm site will consist of the following phases:
• Mobilisation, including demarcation of the site boundary if practical, erection of temporary fencing or other suitable measures to protect adjacent sensitive habitats, and creation of a construction compound for off-loading materials and components and to accommodate temporary site offices and welfare facilities; • Creation of suitable access to site boundary; • Site clearance including any tree/shrub felling to allow construction of new tracks, stripping of vegetation, top and subsoil, and creation of soil storage areas; • Construction of internal tracks for access to turbines, mast and switch building locations; • Excavation of cable trenches and laying of electricity and communications cables; • Construction of turbine foundations including necessary excavations; • The delivery and erection of turbine towers and installation of nacelles and blades; • Construction of the grid connection and operations and control building including the switchgear and metering;
ERM 23 KasREFF SER RPER WIND – June 2014
• Erection of the permanent met mast; and • Progressive site reinstatement and restoration.
3.3.3 COMMISSIONING, OPERATION, AND MAINTENANCE
Once construction is complete, the wind farm is commissioned. Commissioning involves standard tests for electrical infrastructure and turbines. It usually takes a period of six months for the wind farm to reach full operation with operational levels increasing from 80 per cent–90 per cent after commissioning to a long-term operational level of 97 per cent or more10.
Once in operation, the turbines will normally be automated and visits to the site by operations staff will only be required approximately once a week for scheduled services and visual inspection of the turbines.
Longer visits for servicing, typically every six months, will be required to check and inspect blades, fastenings and oil quality. An oil change should only be necessary if there is an indication of degradation in the oil quality following the six monthly inspections. The blade and main brake activation systems usually under hydraulic control will require hydraulic oil replacement every five years. Unscheduled maintenance may also be required if there are equipment problems. If this is required for equipment within the nacelle then a crane will need to be brought to the site.
3.3.4 DECOMMISSIONING
The projected operational lifetime of a typical wind farm is 25 years. After this period there are two options, repowering the site and replacing existing wind turbines or decommissioning the site, removing the wind turbines and other major structures and reinstating the site.
Prior to decommissioning, a decommissioning method statement, detailing or how the site will be restored is usually prepared and approved by the relevant authorities.
At present wind turbines and met masts are removed by crane and reused elsewhere if possible. In the case of the foundation works, upper sections are removed and the voids backfilled with appropriate materials to support the land use at that time. Underground cables and deep concrete foundations are usually left in place as removal is likely to cause more disruption than leaving them in-situ. However, if techniques exist at that time to allow sensitive removal then these will be appraised and considered. Surface vegetation or soil make-up is also to be restored. As with the turbines the electrical control
10 http://www.renewableenergyworld.com/rea/news/article/2009/04/wind-farm-design-planning-research-and- commissioning
ERM 24 KasREFF SER RPER WIND – June 2014
building and internal equipment is removed and reused or recycled where possible.
3.4 DEVELOPMENT COSTS
Wind farm costs are largely determined by the complexity of the site and the turbine loads. The site may be considered complex if the ground conditions are difficult, for example hard rock or very wet ground or poor accessibility. A very windy site with high turbine loads will result in the need for more sophisticated civil infrastructure as well as turbines with site specific specifications. Table 5 shows the costs associated with a typical wind farm for each size of project. Extreme site examples are not included.
Table 5 Typical Wind Farm Costs
Small Medium Large
Installation Cost 2300-2700 2000-2500 1900-2300 (US$/kW)
Maintenance Cost 50-60 40-50 40-50 (US$/kW)
Source: Black and Veatch 2011
3.5 SUPPLY CHAIN IN KAZAKHSTAN
At present there is little wind farm development in Kazakhstan and therefore the wind turbine components industry and its associated supply chain of goods and services is poorly developed. As a result, it is reasonable to assume in the short- to medium-term, that components for wind power technology will need to be supplied from external sources. However, it was noted during meetings with local university meetings, that extreme climatic conditions in Kazakhstan may be unsuitable for imported technology and that these conditions may provide an impetus for local development of this technology. Skills and equipment from the extractives sector may have the potential to be adapted to aspects of wind farm development.
The world’s leading manufacturer of wind turbines is Denmark's Vestas with just under 15 per cent of the market share in 2011, other leading manufacturers are located in China, Germany and India( ). Kazakhstan is placed to take advantage of these manufacturers especially China through importing turbines using road and rail links. Successful wind farm development would require the expansion of the industry to provide locally sourced specialist equipment. For example the erection of wind turbines will require special cranes to assemble the towers of approximately 80 m. These cranes at present may not be readily available. Typical wind farm
ERM 25 KasREFF SER RPER WIND – June 2014
components of foundations and towers however use basic construction materials and labour and therefore may be able to be sourced locally.
ERM 26 KasREFF SER RPER WIND – June 2014
4.0 ENVIRONMENTAL AND SOCIAL CONSTRAINTS
A detailed assessment of environmental and social constraints related to wind (and the other three RES evaluated) is provided in the SER Report. Environmental and social factors that could significantly impact the effectiveness, economic feasibility, and therefore, the siting of these facilities are addressed in Section 3.3 of this RPER. In addition, there are areas of high environmental and/or social sensitivity the proximity of which should also be strongly considered. These environmental and/or social high sensitivity areas are discussed in detail in the SER and are summarized in this section.
• Important Bird Areas/Migratory Birds - There is a significant potential for birds and bat mortality resulting from wind strikes with turbines. Therefore, the siting of wind facilities in Important Bird Areas (IBAs), near known bird migratory routes, or bat roosting habitat should be avoided to the greatest extent possible. In addition, due to the height of wind turbines and the flight paths of migratory birds, an additional protective buffer of 5km should be placed around IBAs. Where siting facilities within an IBA or the buffer area is unavoidable, a more detailed assessment of environmental effects and additional impact mitigation measures will be required.
• Forested Areas - Potential wind sites in forested areas would be discouraged given the relative lack of this habitat and the abundance of un-forested areas throughout the country. When siting facilities within a forested area is unavoidable, a more detailed assessment of environmental effects and additional impact mitigation measures will be required.
• Protected/Designated Lands - Potential wind sites in or near other areas afforded legal protection, including National Parks, and preserved lands would be discouraged given the relative lack of this habitat and the abundance of un-forested areas throughout the country. When siting facilities within a protected/designated area is unavoidable, additional impact mitigation measures will be required.
• Surface Water Quality - Due to clearing, grading, trenching and foundation construction for the wind power plant components, there is a potential for soil erosion during construction. Due to this potential, if wind power facilities are located within 1km of a surface water feature (e.g., intermittent or perennial stream, lakes, or ponds), a more detailed assessment of environmental effects and additional impact mitigation measures will be required.
• Cultural heritage - Special care should be taken to avoid siting wind facilities at or within the viewshed of known or tentative UNESCO
ERM 27 KasREFF SER RPER WIND – June 2014
World Heritage sites due to the global uniqueness of these areas. Special care should also be taken to avoid placing wind facilities on or near locally-registered cultural heritage sites. Given the height of potential wind turbines, the lack of obstructive forest cover over most of Kazakhstan, and the generally flat terrain, a viewshed buffer of 20km should be placed around known or tentative UNESCO and national heritage features. When siting facilities within a viewshed buffer is unavoidable, a more detailed assessment of environmental effects and additional impact mitigation measures will be required. Cultural heritage features themselves would be considered exclusion zones.
• Material Assets/Social - Airplane or helicopter pilots can become disoriented by potential flicker and reflection of light off spinning wind turbine blades. In addition, the height of these wind turbines can create a higher potential for crashes in poor visibility conditions near airports. Therefore, special measures should be taken to avoid siting facilities near airports. Given the height of potential wind turbines, a buffer of 5km should be placed around airports. When siting facilities within a buffer is unavoidable, a more detailed assessment of environmental effects and additional impact mitigation measures will be required. Airports themselves would be considered exclusion zones.
• Settlements/Social – When considering potential wind farm sites, the impact on nearby residents and communities should be taken into account. Wind farms can impact upon residents through noise generation, vibration, and visual impacts (including shadow flicker) and construction/ operation traffic. Appropriate distances away from built up areas should be taken into account when analysing a potential site; therefore, a buffer of 1km should be placed around settlements (e.g., villages, towns, cities). When siting facilities within a buffer is unavoidable, a more detailed assessment of environmental effects and additional impact mitigation measures will be required. Settlements themselves would be considered exclusion zones.
• Cumulative effects – Special consideration should be given to the impact of concentrating multiple wind farms in a tightly constrained wind resource area that is also used as a major migratory bird flyway or near an IBA. Potentially significant cumulative effects associated with wind are presented in Table 6. Guidance for cumulative impact assessment at the development-specific level is available for RES from a number of different sources. These will be used as required by the Project Implementation Unit to establish the methodology for specific financed projects where there are potential cumulative impacts. A list of the most recent and relevant guidance and research is provided below:
ERM 28 KasREFF SER RPER WIND – June 2014
o Scottish Natural Heritage (SNH). “Assessing the Cumulative Impact of Onshore Wind Energy Developments”, March 2012. Available at: http://www.snh.gov.uk/docs/A675503.pdf.
o Band, W., Madders, M., Whitfield, D.P. (2007). Developing field and analytical methods to assess avian collision risk at wind farms. In “Birds and Wind farms: Risk Assessment and Mitigation” Eds. Manuela de Lucas, Guyonne F. E. Janss and Miguel Ferrer. Quercus Books.
o Masden, E.A., Haydon, D.T., Fox, A.D., Furness, R.W., Bullman, R & Desholm, M. (2009). Barriers to movement: impacts of wind farms on migrating birds ICES J. Mar. Science. 66: 746-753.
o Maclean, I. & Rehfisch, M. (2008). Developing techniques for ornithological cumulative impact assessment. BTO Report 513.
o Pearce-Higgins, J.W., Stephen, L., Langston, R.H.W., Bainbridge, I.P. & Bullman, R (2009). The distribution of breeding birds around upland wind farms. Journal of Applied Ecology 46: 1323–1331.
ERM 29 KasREFF SER RPER WIND – June 2014
Table 6 Cumulative effect issues associated with wind power generation and mitigation measures
Valued Geographic Temporal Issue Potential Mitigation Measures Resources Boundary Boundary WIND Cumulative effects on bird migration by wind development because of the potential for large wind farms to be Evaluate cumulative effects of Areas of high concentrated near important specific wind farms near migratory Biodiversity – wind speed Project migratory bird routes or near an IBA. pathways and IBAs and implement A tight concentration of wind farms birds near migratory operation until siting/spacing limitations. Also, in a tightly constrained flyway or routes and demobilisation implement technology mitigation near IBAs, could have a significant IBAs mortality effect on migrating birds. measures, outlined in Table 8-38. This may be compounded during poor weather with low visibility. Areas of high wind speed Visual screening, limits on the Project Cumulative effects to aesthetics near number of facilities in a defined area, associated with siting multiple wind Landscape operation until settlements or and siting/design modifications to facilities in a single viewshed demobilisation recreational decrease visual impact. areas Regional planning to limit the Cumulative impacts to roads and number of wind facilities in a related infrastructure from the Material Areas of high Project sensitive area or contributions to a development of multiple wind assets - roads wind speed construction fund used to pay for regional road facilities in a concentrated area and infrastructure improvements.
ERM 30 KasREFF SER RPER WIND – June 2014
5.0 KAZREFF PROJECT APPRAISAL - ENVIRONMENTAL AND SOCIAL PERFORMANCE REQUIREMENTS
Wind projects funded under KazREFF will be subject to the following environmental and social requirements, as stipulated by EBRD:
• The EBRD’s Environmental and Social Policy (2008) and its associated Performance Requirements. • Applicable requirements of Kazakhstan, including but not limited to those related with environmental impact assessments, environmental permitting, labour, public consultation, resettlement and compensation, occupational health and safety, community health and safety, and emergency response. • Relevant European Union Directives and requirements • International best practices, including those promulgated by other international financial institutions, the International Labour Organisation, and others.
5.1 EBRD REQUIREMENTS
Projects would need to adhere to the EBRD Environmental and Social Policy and its associated Performance Requirements (PR), which cover the following areas:
• PR 1: Environmental and Social Appraisal and Management • PR 2: Labour and Working Conditions • PR 3: Pollution Prevention and Abatement • PR 4: Community Health & Safety and Security • PR 5: Land Acquisition, Involuntary Resettlement and Economic Displacement • PR 6: Biodiversity Conservation and Sustainable Resource Management • PR 7: Indigenous Peoples • PR 8: Cultural Heritage • PR 9: Financial Intermediaries (FI) • PR 10: Information Disclosure and Stakeholder Engagement
Depending upon the scale of KazREFF project, EBRD would require a series of environmental documents to be produced in order to gain EBRD funding. Projects are screened at an early stage and placed into one of the four following categories, depending on the level and type of environmental and social due diligence that is required:
ERM 31 KasREFF SER RPER WIND – June 2014
• Category A projects are those with potentially significant and diverse environmental and social impacts, requiring detailed impact assessments • Category B projects are those with environmental and social impacts that are site-specific and can be addressed through readily available management and mitigation techniques • Category C projects have minimal environmental or social impacts • FI projects are where the EBRD is investing in a Financial Intermediary, such as a bank or equity fund.
This categorization reflects: (i) reflect the level of potential environmental and social effects and issues associated with the proposed project; and (ii) determine the nature and level of environmental and social investigations, information disclosure and stakeholder engagement required for each project, taking into account the nature, location, sensitivity and scale of the project, and the nature and magnitude of its possible environmental and social effect and issues.
Due to the relatively small scale of the potential KazREFF projects, most would likely fall under Category B, as the potential adverse environmental and/or social effects that they may give rise to are typically site-specific, and/or readily identified and addressed through mitigation measures. However, the siting of wind facilities within or near sensitive/protected areas or in situations where impacts could be more severe may result in these being classified as Category A projects. This determination is made by EBRD and KazREFF in the initial project phases.
5.1.1 CATEGORY A
If a project is considered to be a Category A project, it is usual to expect that it would require the development and disclosure of an Environmental and Social Impact Assessment Package including:
• An ESIA; • A Non-Technical Summary (NTS); • An Environmental and Social Action Plan (ESAP); • A Stakeholder Engagement Plan (SEP); • A Land Acquisition Plan (if land acquisition is required); • A Resettlement Action Plan (if population displacement is required).
Disclosure of these documents generally allows for a 120 day public consultation period, after which the documents are finalized, published, and financing may be secured. In general, the timeframe for completing the environmental and social review process for a Category A project typically takes 9 to 12 months to complete.
ERM 32 KasREFF SER RPER WIND – June 2014
5.1.2 CATEGORY B
If categorized as a Category B project, there are less detailed documentation requirements due to the lesser potential for significant environmental and social impact. EBRD typically requires the development and disclosure of:
• A Project Summary Document; • A Project Fact Sheet or Non-Technical Summary (NTS);
For Category B projects, EBRD also typically reviews, but does not require disclosure of:
• An Environmental and Social Action Plan (ESAP); • A Stakeholder Engagement Plan (SEP); • An Environmental and Social Due Diligence (ESDD) document that demonstrates compliance with PR1
Disclosure of these required documents generally allows for a 30 day public consultation period, after which the documents are finalized, published, and financing may be secured. In general, the timeframe for completing the environmental and social review process for a Category B project typically takes 3 to 6 months to complete.
5.2 KAZAKHSTAN REQUIREMENTS
Specific requirements for EIA procedures for all categories of economic activity are established by the document “Instruction on Environmental Impact Assessment at the Development of Prior Planned, Planned, Prior Project, and Project Documentation”. This guide contains:
• A list of activities which require implementation of the EIA procedure in full;
• A list of activities for which the full EIA procedure is proposed to the State Environmental Expertize (SEE) on the basis of preliminary expertise or by applying a set of criteria determined in normative documents; and
• A list of activities with insignificant environmental impact, for which only the preparation of an "Environmental impact statement" is sufficient for submission to the SEE.
Projects in Kazakhstan are classified by the Sanitary and Epidemiological Services (SES) of MOH according to five danger levels with one being the highest as defined by norms and standards in relation to human health and safety. The sensitivities of projects are measured by the SES Danger/Sanitary Categories. The categories are:
ERM 33 KasREFF SER RPER WIND – June 2014
• Danger/Sanitary Categories 1 & 2 projects have levels of severity/danger that trigger a full EIA. • Danger/Sanitary Category 3 projects are considered to have lower levels of severity/danger and as such a lesser assessment is undertaken, although still referred to as an Environmental Assessment. • Danger/Sanitary Category 4 & 5 projects are considered to present considerably lower risks of severity/danger and generally do not warrant an assessment beyond the initial screening.
The SES Danger/Sanitary Categories relate to four categories of RoK EIA (Оценка воздействия на окружающую среду - OVOS). The EIA/OVOS Categories are:
• Category I - Sanitary Class/Danger Categories 1 and 2 plus investigations and extractions of minerals, except for common minerals. Risks are high and approval by MOEP is required. A Category I EIA/OVOS is categorically required obligatory for large scale including road construction project with four lanes or more. • Category II - Sanitary Class/Danger Category 3 plus extractions of ubiquitous minerals, forestry activities and special uses of water. Risks are ranked as Medium High and approval is required from TEPO(s). • Category III - Sanitary Class/Danger Category 4 Risks are ranked as Low and approval is required from TEPO(s). • Category IV - Sanitary Class/Danger Category 5 plus projects involving animals, except recreational fishing and hunting. Risks are ranked as Low and approval is required from local administrations.
SEE reviews are conducted at end of each stage in the process and before proceeding to the next stage. Reviews are conducted first at the Oblast level and then by MEWR and other agencies as appropriate to the nature of the Project and the level of EIA Categorization. Under Kazakhstan regulations, the EIA process has three stages:
• Preliminary EIA (Environmental Impact Assessment - Pre-OVOS)
• Preparation of the EIA (OVOS). EIAs are obligatory for large scale projects.
• Preparation of an "Environmental Protection Section". The Environmental Protection Section is prepared in the detailed design stage in the event that mitigation measures defined in the EIA (OVOS) are required.
ERM 34 KasREFF SER RPER WIND – June 2014
At each stage of the EIA process, the developer is required to prepare an "Environmental Impact Statement", which is a compulsory annex to each EIA document. The "Environmental Impact Statement" must be presented in the package of documents for submission to the SEE for consideration. Reviews are conducted at the end of each stage, first at the Oblast level and the by MEWR and other agencies as appropriate for the project and EIA Category.
Public hearings or public consultations are required at all stages of EIA. The detailed requirements for public participation are reflected in the Environmental Code, Articles 57 and 60-67 and the “Rules of access to environmental information relate dot EIA procedure and decision-making process on intended economic and other activity”. Minutes from these hearings are filed as part of the EIA documentation.
The process provides for a preliminary review period of two weeks and a final review period of up to 90 days after which the EIA authors are required to defend the EIA at a consultation session with all stakeholders in attendance (usually not the general public). Once complete, the EIA is revised; a final document is prepared; and a formal OVOS certificate is issued to the Proponent, but usually only after another 30-day waiting period, allowing for any additional comments. This certificate allows the project to proceed with other approvals that may be required. Based on this information, it may take up to a year to complete the EIA process in Kazakhstan.
Based on additional guidance provided in the RoK EIA regulations, it is likely that wind projects (and in fact, all RES projects) would be considered Category II and would require Category II EIA/OVOS documentation. However, the siting of wind facilities within or near sensitive/protected areas may result in these being classified as Category I projects. This determination is made by MoE at the preliminary EIA stage.
The OVOS process was evaluated against the EBRD Environmental and Performance Standards to identify gaps areas that may be not be satisfied by the OVOS process. This gap analysis is provided in Appendix A.
5.3 KAZREFF APPRAISAL PROCESS
All projects considered for financing through KazREFF will under a detailed appraisal process in order to:
• Determine each project’s ability to meet EBRD environmental and social performance requirements; • Determine each project’s ability to meet EBRD RoK EIA regulations • Ensure that projects are technically feasible (part of the technical due diligence)
ERM 35 KasREFF SER RPER WIND – June 2014
• Identify significant issues and constraints that may negatively impact KazREFF’s ability to finance each project from an environmental and social perspective • Provide simplified guidance and resources to project proponents (and their environmental consultants) in order to more easily comply with EBRD and Kazakh requirements
The appraisal process will be developed and implemented by the Project Implementation Unit.
5.3.1 INITIAL SCREENING
The appraisal process includes an initial screening of the project proposal against the criteria presented in this RPER, the SER report, and consideration of key environmental and social issues. This initial screening is conducted after the project proponent completes the Environmental and Social Issues Checklist – Wind provided in Appendix B. This checklist includes identification of key environmental and social issues related to wind (and cumulative impacts) and is reviewed by KazREFF’s environmental and social review team. Based on the review of the checklist, the project’s EBRD category will be determined and specific documentation requirements will be communicated to the project proponent.
Once the EBRD requirements have been identified, KazREFF environmental and social review team will provide support to project proponents to comply with the Kazakh EIA regulations. In general, information gathered through the initial screening process can be useful in developing the preliminary EIS documentation required for the initial stage of the Kazakhstan EIA.
5.3.2 DOCUMENTATION REVIEW AND APPROVAL/FEEDBACK
Based on the initial screening and categorisation, the project proponent will then be expected to complete the preparation of required documentation.
Templates for the typical documents expected to support wind projects (under Category B) are provided in Appendix C and include templates for the NTS (Appendix C.1), the SEP (Appendix C.2), and the ESAP (Appendix C.3). If a project is determined to be a Category A project, an ESIA would be required. Due to the very specialized nature of an ESIA, an ESIA template has not been provided. However, information in the SER report will be extremely useful to identify information necessary for the preparation of these documents. The information in the SER identifying the environmental baseline, the anticipated effects, and mitigation strategies should also be very useful to inform the Kazakh EIA.
All projects will be expected to comply with EBRD PR1 through 10. Important information for assessing the significant environmental and social
ERM 36 KasREFF SER RPER WIND – June 2014
effects and avoidance, minimization, and/or mitigation of those effects is provided in the SER.
The required documents will be submitted to, and reviewed by, KazREFF environmental and social review team. The KazREFF environmental and social review team will work with the developer to ensure submitted information is sufficient to demonstrate compliance with EBRD’s PRs.
In addition, KazREFF environmental and social review team will review the progress of the Kazakh EIA and can, if requested, provide technical input and guidance on the process and content. KazREFF environmental and social review team will request updates from the project proponent on the progress of the project through the Kazakh EIA stages until final approval is received.
Once the required environmental and social documentation for KazREFF review has been found to be in compliance with the EBRD and the final Kazakh EIA is approved, KazREFF environmental and social review team will reflect that in the Project Screening Report.
ERM 37 KasREFF SER RPER WIND – June 2014
6.0 APPENDICES
A – Gaps between EBRD PR for ESIA and Kazakhstan EIA Requirements
B – Environmental and Social Issues Checklist - Wind
C – Environmental and Social Templates
C.1 – Non-Technical Summary (NTS)
C.2 – Stakeholder Engagement Plan (SEP)
C.3 – Environmental and Social Action Plan (ESAP) – Wind
ERM 38 KasREFF SER RPER WIND – June 2014
Kazakhstan Renewable Energy Financing Facility (KazREFF) - Strategic Environmental Review
Appendix A – Gaps between EBRD PR for ESIA and Kazakhstan EIA requirements
ERM 39 KasREFF SER RPER WIND – June 2014
Appendix A: Gaps between EBRD PR for ESIA and Kazakhstan EIA requirements
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement PR 1: Environmental and All EBRD-financed projects undergo The EIA is obligatory for all sectors of None Social Appraisal and environmental and social appraisal economic and other activities that may Management directly or indirectly impact the environment and public health.
The EIA process is performed on the strength of commitment, integration (magnitude), alternative, adequacy, preservation, compatibility, flexibility, and public participation.
Categorization and EIA magnitude Economic activities subjected to the EIA None procedure are categorized as I, II, III, and IV, The EBRD categorizes proposed projects as “A”, of which categories I and II cause major “B”, and “C”. impacts on the environment. A project is classified as Category A when it could result in potentially significant and diverse According to the requirements, there is the adverse future environmental and/or social list of projects (economic activities) for impacts and issues which, at the time of which the EIA is recommended to be categorization, cannot readily be identified or performed in full (for example, oil industry assessed and which require a formalized and and crude oil refineries, thermal power participatory assessment process carried out by stations, chemical installations, pipelines independent third party specialists in accordance for transport of gas, oil or chemicals, etc.) with the PRs (Appendix 1 to the EBRD ESP). and the list of projects (economic activities) for which the requirements to carry out a A proposed project is classified as Category B comprehensive assessment are imposed by when the potential adverse environmental and / State review authorities on the basis of a or social impacts that it may give rise to are preliminary review or by applying
ERM 40 KasREFF SER RPER WIND – June 2014
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement typically site-specific, and/or readily identified thresholds defined by regulations and addressed through mitigation measures. (agriculture, forestry, mining industry, These impacts could be from past, current or power industry, wind farms, etc.). future activities. Due diligence requirements may vary depending on the project and will be agreed with the EBRD on a case-by-case basis, in accordance with PR 1.
A proposed project is classified as Category C when it is likely to result in minimal or no adverse environmental or social impacts and therefore requires no further environmental and social appraisal beyond categorization.
Based on the KazREFF SER, it is anticipated that most funded projects will fall within Categories B or C. EIA stages The EIA process comprises the following None stages: 1) preliminary EIA (stage 1); 2) EIA that is performed for a complete and comprehensive analysis of potential effects of the project or further economic and other activities, substantiation of alternatives, and development of an environmental management plan (programme) (stage 2); 3) “Environmental Protection” section that constitutes part of the design documentation and contains engineering solutions aimed at prevention of adverse
ERM 41 KasREFF SER RPER WIND – June 2014
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement impacts on the environment (stage 3).
The EIA format, completeness of studies, scope of used documents, levels and degree of detail of environmental scientific & design surveys depend on the design stage as well as on magnitude and intensity of impacts caused by projected economic and other activities on human health and environment.
EIA is an integral part of pre-design and design documents. Preliminary environmental and social assessment Through Pre-EIA activities, the potential None (Pre EIA) trends of changes in environmental and socioeconomic components as well as Through appraisal activities, the client will impacts on both the society and consider in an integrated manner the potential environment are identified. environmental and social issues and impacts associated with the proposed project. The No need in computations of the pollution appraisal process will be based on recent level for certain environmental information, including an accurate description components (air, soils, water, subsoil and delineation of the client’s business or the resources). project, and social and environmental baseline data at an appropriate level of detail. The Pre-EIA documents are disclosed for public appraisal should also identify applicable laws and by a project initiator. regulations of the jurisdictions in which the project operates that pertain to environmental Pre-design appraisal documents (business- and social matters, including those laws plans, feasibility studies) and main pre- implementing host country obligations under design documents such as “Investment international law (for example, commitments substantiation” and Pre-EIA documents are
ERM 42 KasREFF SER RPER WIND – June 2014
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement related to land use planning and protected area submitted to the State Environmental management). Review (SER).
A positive Conclusion issued by the SER in favour of the project initiator, serves as a guide for making decisions to initiate designing of specific facilities and structures in accordance with the most rational option selected in the course of Pre-EIA development. Environmental and Environmental and social impacts and issues will The EIA process comprises an assessment None social appraisal (EIA) be appraised in the context of the project’s area of impacts on: mechanism of influence. Environmental and social issues and impacts will also be analysed for the relevant • atmospheric air stages of the project cycle. These may include • water resources; preconstruction, construction, operations, and • subsoil resources; decommissioning or closure and reinstatement. • industrial and domestic waste; Where relevant, the appraisal will also consider • physical impacts; the role and capacity of third parties, such as • lands and soils; local and national governments, contractors and • flora; suppliers, to the extent that they may influence • fauna; the project, recognizing that the client’s ability to • socioeconomic environment; address these risks and impacts will depend on its • environmental risks from planned control and influence over the third party actions. activities in the region The appraisal will also consider potential trans-
boundary and global issues, such as impacts from A project initiator discloses EIA documents effluents and emissions, increased use or for the public. contamination of international waterways, greenhouse gas emissions, climate change mitigation and adaptation issues, and impacts on endangered species and habitats.
ERM 43 KasREFF SER RPER WIND – June 2014
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement
PR 2: Labour and At a minimum, the client’s human resources Labor relationship in the Republic of Labor relationship issues Working Conditions policies, procedures and standards shall be Kazakhstan is regulated by the Labor Code are not reflected in typical designed to: establish and maintain a sound and it does not constitute part of the EIA Kazakh EIA documents. This worker-management relationship; promote the process. would be a gap if not fair treatment, non-discrimination and equal addressed in a project- opportunity of workers; promote compliance Issues related to labor and working specific ESMP. with any collective agreements to which the conditions and safety are considered in the client is a party, national labour and employment “Environmental risk assessment in laws, and the fundamental principles and key connection with planned activities in the regulatory standards embodied in the ILO region” section. conventions that are central to this relationship; protect and promote the health of workers, especially by promoting safe and healthy working conditions.
PR 3: Pollution The client will avoid the release of pollutants or, Measures aimed at prevention and None Prevention and when avoidance is not feasible, minimize or abatement of environmental pollution are Abatement control their release. This applies to the release specified in EIA documents (“Atmospheric of pollutants due to routine, non-routine or Air”, “Water Resources”, and “Waste” accidental circumstances with the potential for sections). These measures provides for local, regional, or trans-boundary impacts. In introduction of low-waste and waste-free addition, the client should examine and technologies and special measures on i) incorporate in its operations energy efficiency prevention (abatement) of air emissions; ii) measures and measures to conserve water and adverse impact mitigation; iii) air quality other resources, consistent with the principles of monitoring; iv) amounts and chemical cleaner production. The client will avoid or composition of wastewater discharges; v) minimize the generation of hazardous and non- substantiation of the introduction of water hazardous waste materials and reduce its circulating systems and wastewater reuse harmfulness as far as practicable. systems, recycling of sludge from wastewater treatment facilities; vi)
ERM 44 KasREFF SER RPER WIND – June 2014
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement groundwater protection against pollution and depletion; and vii) recommendations related to recycling, treatment and disposal of all types of waste and waste recycling/waste disposal technologies. PR 4: Community Health Requirements relating to: infrastructure and EIA documents comprise a section titled None & Safety and Security equipment safety; hazardous materials safety; “Assessment of environmental risks for the community exposure to disease; emergency environment and community health in preparedness and response; and security connection with planned economic personnel requirements. These requirements are activities”. This section contains i) focused on avoidance or prevention of risks and recommendations on prevention of and impacts rather than their minimization and response to emergencies; ii) consideration mitigation. of emergency probability; sources and kinds of emergencies and frequency of their occurrence as well as forecasts of their impacts on the environment and community. PR 5: Land Acquisition, The following requirements are considered in the Issues related to land acquisition and Kazakhstan EIA regulations Involuntary course of project design: carrying out of involuntary resettlement are regulated by do not contain Resettlement and consultations; grievance mechanism; the Land Code of the Republic of requirements related to Economic Displacement resettlement planning and implementation; Kazakhstan. But the Pre-EIA documents to land acquisition, Resettlement Action Plan; livelihood restoration be submitted to the SER for reviewing involuntary resettlement framework; compensation and benefits for should contain a copy of document for the and economic displaced persons; displacement; physical right of land use in the subject territory. displacement. displacement; economic displacement; and loss of public amenities. PR 6: Biodiversity Through the environmental and social appraisal The EIA process also includes an None Conservation and process, the client will identify and characterize assessment of impacts on vegetation in the Sustainable Resource the potential impacts on biodiversity likely to be project influence area (the presence of Management caused by the project. The extent of due diligence medicinal herbs; rare, endemic and Red should be sufficient to fully characterize the risks Data Book-listed plat species), green space
ERM 45 KasREFF SER RPER WIND – June 2014
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement and impacts, consistent with a precautionary condition; forecasted changes of the approach and reflecting the concerns of relevant vegetation cover in the project stakeholders. The client will seek to avoid implementation area and impacts of these adverse impacts on biodiversity. changes on life and health of local communities; recommendations for conservation of vegetation communities, improvement of their condition, flora conservation and revegetation; recommendation for vegetation monitoring, etc.
Furthermore, the EIA documents contain a baseline assessment of aquatic and terrestrial fauna (the presence of rare, endangered and Red Data Book-listed fauna species); measure to conserve and reproduce the integrity of natural communities and species diversity of aquatic and terrestrial fauna; food potential improvement; a wildlife monitoring programme. In addition, the presence of natural territories and landmarks under special protection in the territory of potential construction operations is considered. PR 7: Indigenous In projects where Indigenous Peoples are likely to The Kazakhstan legislation does not specify The Kazakhstan EIA Peoples be affected, the client is required to carry out an requirements related to Indigenous procedure does not assessment of impacts on Indigenous Peoples. Peoples consider issues related to Depending upon the outcome of this, the client is Indigenous People. expected to first avoid adverse effects and where However, this is not this is not feasible, to prepare and Indigenous typically an issue in
ERM 46 KasREFF SER RPER WIND – June 2014
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement Peoples’ Development Plan so as to minimize Kazakhstan, where there is and/or mitigate any potential adverse impacts. no indigenous population. The client is also expected to implement a specific grievance mechanism and determine appropriate modalities for compensation and benefit-sharing.
PR 8: Cultural Heritage At an early stage of the environmental and social EIA documents contain a section devoted None appraisal, the client should identify if any cultural to territories, landmarks and sites under heritage is likely to be adversely affected by the special protection. Cultural heritage is project, and assess the likelihood of any chance regulated by the RK Law “On Protection finds. The client will ensure that provisions for and Use of Historical and Cultural Heritage managing chance finds, defined as physical Sites and Objects” dated July 2, 1992. cultural heritage encountered unexpectedly Companies, institutions, organizations, during project implementation, are in place. Such educational institutions, public provisions shall include notification of relevant organizations and individuals will support competent bodies of found objects or sites; an authorized relevant body in alerting project personnel to the possibility of implementation of measures aimed at chance finds being discovered; and fencing-off protection, preservation and use of the area of finds to avoid any further disturbance historical and cultural heritage sites. or destruction.
PR 9: Financial Not applicable Not applicable Not applicable Intermediaries (FI)
PR 10: Information “Information Disclosure and Stakeholder Public opinion is given proper weight in the Kazakhstan requirements Disclosure and Engagement” specifies requirements relating to process of EIA development. Public opinion do not specify a detailed Stakeholder stakeholder identification, development of a consideration format depends on the procedure for stakeholders Engagement Stakeholder Engagement Plan, information significance of planned economic activities identification and disclosure, meaningful consultations, and and the extent of project influence on the engagement or the grievance mechanism. environment and community health; much grievance mechanism
ERM 47 KasREFF SER RPER WIND – June 2014
EBRD Performance Issue Related Kazakhstan Gap Requirement/Issue OVOS Requirement depends on stakeholders. The procedure procedure. and dates of public consultations is regulated by environmental supervisory authorities.
Public opinion is mainly considered through public consultations. The results of public consultations are recorded in the form of a report where all key issues and disagreements between stakeholders and a client are recorded. Stakeholders’ comments and proposals are considered in design documents. Written proposals and comments from stakeholders (as an independent form of public opinion consideration) are collected for individual less significant projects of economic activities. At subsequent stages of project design, the procedure of public opinion consideration can be carried out through collection of written proposals and comments in respect of EIA findings for a certain industrial operation.
ERM 48 KasREFF SER RPER WIND – June 2014
Kazakhstan Renewable Energy Financing Facility (KazREFF) - Strategic Environmental Review
Appendix B – Environmental and Social Issues Checklist - Wind
ERM 49 KasREFF SER RPER WIND – June 2014
Please read this before completing the questionnaire: 1. This questionnaire is the first stage in the Bank’s environmental and social due diligence process. The more comprehensive the answers given, the less need will there be for the Bank to request further information. Please, therefore, try to answer the questions as fully and openly as possible. 2. The questionnaire makes reference to both “the Project”, the business activity for which EBRD funding is sought, and “the Company”, which is the corporate entity that is ultimately responsible for the Project. The Project may affect the whole Company or may only relate to one element within the Company. The Bank needs to understand both issues related to the Project being financed by the Bank and the impacts and issues associated with the Company as a whole. 3. There are a number of questions where further information is requested if a positive response is given. Additional information can be provided either in the questionnaire’s boxes or in separate documents.
PROJECT NAME: PROJECT LOCATION: Map Provided? Yes / No Company Name: Company Address: Country: Town/Location: Business Sector/Activities: Person completing questionnaire:
Name: Title: Date: Telephone: Mobile: E-mail:
Company authorised representative (e.g. Environmental Manager): I certify that, to the best of my knowledge and belief, the information contained in this questionnaire accurately represents current or future operations.
Signature:
Title: Date:
ERM 50 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE COMPANY PROFILE
A) Ownership: • Private ownership %: ______• Public ownership %: ______B) Year of foundation: ______
C) Sector of operation and main products: ______D) Describe the main activities of the Company and its holdings including any on-shore wind or other renewable energy projects (include a description of the corporate structures and controls that are used to manage/oversee individual projects, including this one):
PROJECT DESCRIPTION
A) Technical information: Start of construction (planned date) Start of operation (planned date) Installed capacity (MW) Annual net generation (MWh) Type of turbines / towers (height, turbine diameter, maximum and minimum rotation speeds, etc) Are data on wind resource available (yes/no) Wind resource measuring period (start date / end date) Mean wind power density at 80 metres (W/m2) Distance to interconnection grid (km): Voltage level of interconnection grid (kV): Voltage level of overhead line to interconnection point (kV): Is operation constrained by seasonal migratory bird routes? (yes/no)
B) Status of project development: yes no
ERM 51 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE The project is still in its conceptual phase (we have only a project idea)? Technical design has started? Technical design is completed? Quotations / proposals from equipment suppliers have been received?
C) Summary of information on Environmental Impact Assessment: Is Environmental Impact Assessment (EIA) required? (yes/no) Has EIA been completed? (yes/no) If EIA is available, has it observed any adverse environmental impacts? If yes, describe them and any associated mitigation measures in Section 1b. If EIA is required but not available, when will it be completed?
D) Siting, design and key environmental and social considerations:
1. Describe the Project and provide a map showing its components, including the turbine infrastructure, generating units and control-centre (and approximate layout), roads, transmission lines, grid connections and other required facilities (such as sub-stations). 2. How were environmental and social issues incorporated into the siting and design optimisation process (see also questions under PR1 and PR6 below)? 2.1 What studies have been completed relating to potential impacts on avian populations and migratory passage? 2.2 What measures have been incorporated into the design and operation-plans to minimise risks to birds? 3. Wind resource issues – please describe: 3.1 Understanding of the operational regime for each facility and for operations in tandem; 3.2 Wind resource measurements and other meteorological data and monitoring information; 4. How have climate-change related variables been accommodated? PR1 - Environmental and Social Appraisal & Management Environmental and Social Appraisal 1.a Has the Company made an assessment of the Yes: No: environmental and social impacts of its operations? If yes, please provide a summary of that assessment:
ERM 52 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE 1.b Has an Environmental and Social Impact Assessment Yes: No: (ESIA) been completed for this Project? If yes, please summarise the conclusions of the ESIA, including required/recommended mitigation, and send a copy/summary: 1.c Have relevant discussions been held with Yes: No: environmental regulators on the ESIA for the Project? If yes, please summarise: 1.d Is there an Environmental and Social Action Plan (ESAP) Yes: No: for the Project construction, operation and If yes, please summarise: decommissioning? 1.e Have any site investigations been performed to check Yes: No: the suitability of the site and characterise If yes, please provide a list of the studies: environmental and social baseline conditions, such as soil, water quality and groundwater testing, slope stability, survey for flora and fauna including bat, bird and water species, or the situation of nearby communities? 1.f What are the relevant Company’s Corporate Social Responsibility Standards? 1.g What processes are in place to manage environmental issues (such as the presence of sensitive species)? 1.h Will / does the Project involve significant excavations, Yes: No: demolitions, movement of earth, flooding or other If yes, please provide details: changes in the physical environment? 1.i What soil erosion/sedimentation mitigation/control procedures will be in place for the construction and operational phases of the Project? Environmental Management 1.j Who is responsible for environmental management at Name/title:
ERM 53 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE the Company? Phone/mobile: Email: Who is responsible for social management / community Name/title: relations at the Company? Phone/mobile: Email: Who is, or will be, responsible for environmental Name/title: management for the Project? Will that person be on- Phone/mobile: site during construction and operation? Email: Who is, or will be, responsible for social management / Name/title: community relations for the Project? Will that person Phone/mobile: be on-site during construction and operation? Email: 1.k Does the Company have an Environmental and Social Yes: No: Management System (ESMS)? If yes, is the ESMS compliant with any internationally Yes: No: recognised systems such as ISO 14,001, OHSAS 18,001, SA 8000 or EMAS? 1.l Does the Company periodically prepare a summary Yes: No: report on environmental performance (or If yes, please provide a copy of the most recent report(s) sustainability) for shareholders, stakeholders, or others? How often? 1.m Does the Company routinely provide environmental Yes: No: training for Company personnel? If yes, please describe the training provided: Will the Company train workers for the Project? For Yes: No: construction and/or operation? If yes, which workers will be trained? What kind of training? Contractor management 1.n Will the Company use contractors during the Yes No
ERM 54 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE construction and/or operational phases of the Project? If yes, please provide details: 1.o Are prospective contractors required to submit Yes No environmental, health and safety, and/or labour information with bid documents (that is, do solicitations for proposals require such information)? 1.p Is a contractor’s past EHS performance considered Yes No during evaluation of bids? If yes, please describe how (including whether it is used as a pass/fail factor or as part of the overall score: 1.q Does the Company monitor performance of its Yes: No: contractors regarding environmental, health and safety, If yes, how often? How does the Company deal with poor and labour/human resources? performance? 1.r How will the contractors be managed to ensure they have processes in place to anticipate and respond to emerging risks and opportunities, associated with the Project? PR 2 – Labour and Working Conditions 2.a Who is responsible for Human Resources (HR) Name/title management at the Company? Phone/mobile: Email: 2.b Does the Company have written HR policies setting out Yes: No: its approach to managing its workforce? 2.c Are all workers provided with written information Yes: No: about their terms and conditions of employment? 2.d Has the Company ever been found in violation of any Yes: No: country’s labour and/or social security laws? If yes, please describe the circumstances Have these resulted in any penalties, fines, major Yes: No: recommendations or corrective action plans? If yes, please describe:
ERM 55 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE 2.e Are employees free to form, or join, a workers’ Yes: No: organisation (e.g. a trade union) of their choosing? What percentage of the workforce belongs to such an organisation? 2.f Is the Company covered by a collective bargaining Yes: No: agreement? 2.g How does the Company interact with workers’ organisations and provide information to them? 2.h Does the Company have a grievance mechanism which Yes: No: allows employees to raise workplace concerns? If yes, please describe: How many grievances were received from employees Number: during the previous year? Please summarise the issues raised in grievances and how the company has addressed them: 2.i Have there been any strikes or other collective disputes Yes: No: related to labour and working conditions at the If yes, please describe the nature of the dispute and how it was Company in the past three years? resolved: Have there been any court cases related to labour Yes: No: issues? If yes, please summarise contested issues and outcome: Have there been any other significant labour issues Yes: No: raised by the media or by non-governmental organisations? If yes, please describe: 2.j Are there policies or terms and conditions covering Yes: No: employment of young persons under age 18? If yes, please describe What is the minimum legal working age? How does the Company verify the age of employees? Does the Company apply any restrictions to the tasks Yes: No:
ERM 56 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE that can be done by younger workers? If yes, please describe: 2.k Are employees free to leave the premises when they Yes: No: are not required to work or with appropriate due cause? Does the Company retain any identity documentation Yes: No: from the employees? If yes, please explain which documents and why: Are employees free to resign from their jobs? Yes: No: If yes, please describe the notice and other procedural requirements? 2.l Does the Company have a policy for setting wages? Yes: No: How do the Company’s wage levels compare to comparable employers in your sector? 2.m Does the Company anticipate any redundancies or Yes: No: retrenchment in the next three years? If yes, please describe and explain the reason(s): 2.n Does the Company have policies or terms and Yes: No: conditions covering non-discrimination and equal If yes, please describe: opportunities in employment? 2.o Are any criteria other than compliance with job Yes: No: requirements (e.g., gender, ethnicity, nationality, If yes, please specify those criteria: religion, political or trade union affiliation) applied for recruitment / promotion / access to training / benefits? 2.p How many workers does the Company employ? Please provide numbers for men and women separately. How many are...: Direct: Seasonal: Full-time: Part-time: How many sub-contractors does the Company employ and what is the role of these sub-contractors? 2.q Will there be employment opportunities for local Yes: No:
ERM 57 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE stakeholders? If yes, please describe these opportunities: How many non-skilled workers will be employed for the Construction: Operation: Project during construction and then operation? How many non-skilled workers are expected to be Near-by areas: Within the Country: recruited from nearby areas? From the country? What proportion of managers and skilled workers are Near-by areas: Within the Country: expected to be recruited from nearby areas? From the country? Occupational Health and Safety 2.r Who is responsible for health & safety management at Name/title: the Company and/or Project? Phone/mobile: Email: Is there an emergency response plan for dealing with Yes: No: natural disasters, such as earthquakes? (This is also relevant to PR-4 Community Health, Safety and If yes, please describe and provide a copy: Security) Is there sufficient information to confirm that Yes: No: construction will not result in land slips or other environmentally damaging incidents? (This is also If yes, please describe: relevant to PR-4 Community Health, Safety and Security) 2.s Does the Company have a Health & Safety Yes: No: Management System? Is the system compliant with an international health & Yes: No: safety standard such as OHSAS18001? 2.t Is the Company compliant with national requirements Yes: No: for health & safety? 2.u Is there a current Health & Safety Action Plan for the Yes: No:
ERM 58 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE Company? If yes, please provide a copy of the latest update. Do project-specific health and safety plans (typically) go Yes: No: beyond the requirements of host countries? If yes, please summarise (typical) differences: 2.v Does the Company keep any statistics on Yes: No: • Fatalities; If yes, please provide health and safety statistics for the last three • Lost time accidents; years of operations. • Lost workdays resulting from incidents; and/or • Total staff hours worked? 2.w Have any Company operations been cited for violations Yes: No: of national or other health and safety standards and If yes, please summarise the circumstances and the outcome procedures in the last 3 years? 2.x Is there (or will there be) a Health and Safety Plan for Yes: No: this Project? If yes, please describe what it covers (or will cover)?
Will workers be required to undergo health and safety Yes: No: training? If yes, please indicate how often and what type(s) of training 2.y How does the Company ensure that workers employed by its contractors, sub-contractors or labour agents are protected by the same labour and health and safety standards as those that apply to the Company’s own employees? PR 3 – Pollution Prevention and Abatement Environmental Compliance 3.a In the last 3 years, has the Company been cited for any Yes: No: violations of environmental permits or regulations? If yes, please describe circumstances and outcomes: 3.b Has the Company applied for, and/or received, the Yes: No: required environmental permits and licences to Please list required permits and licenses, and their status (issued, construct the Project? To operate? applied for, etc.)
ERM 59 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE Construction: Operation: 3.c Which agencies and authorities will be primarily responsible for overseeing environmental performance of the Project? Air Emissions 3.d Does the Company produce air emissions? Yes: No: If yes, please describe the main sources, types and quantities of air emissions produced by the company: 3.e Please describe any measures taken to reduce emissions and prevent air pollution. 3.f Please provide monitoring data for total air emissions. Water Use 3.g What will be the main sources of water for the Project during construction and operation? How much water will the Company use at each phase of the Project? Have permits been issued? Yes: No: Will any water require treatment prior to use? Yes: No: If yes, please describe use, amount to be treated and treatment method: Wastewater Discharges 3.h What are the sources, types and quantities of effluent discharges that will produced by the Company during the Project? 3.i How much wastewater will be generated during Construction: Operation: construction and operation? How will wastewater be managed and discharged?
ERM 60 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE Is any wastewater treatment required prior to Yes: No: discharge? If yes, please describe: Solid Waste Management 3.j What are the types and quantities of solid wastes produced by the Company? How are these wastes disposed of? 3.k Are any hazardous wastes produced and how are these Yes: No: stored and disposed of? If yes, please describe: 3.l Does the Company implement any measures to reduce Yes: No: / reuse / recycle any solid wastes at its facilities? If yes, please summarise: Are contractors required to implement these Yes: No: measures? Hazardous Material Management 3.m What hazardous materials will used by the Company in the Project (such as flammable, explosive, reactive, radioactive and toxic substances) and in what quantities? What measures and procedures are in place for the handling and storage of such materials? 3.n Has the Company suffered any environmental incidents Yes: No: or accidents (such as spills, tank ruptures, explosions, If yes, please describe: etc.) during the previous three years at any of its facilities? 3.o Does the Company prepare Environmental Incident Yes: No: Reports, or similar, when an environmental accident or If yes, please describe the reporting system and indicate the relevant incident occurs? authorities you report to:
ERM 61 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE 3.p Will fuel or other hazardous materials be stored and/or Yes No used for this Project? If yes, what materials will be used/stored? How much of each? How will they be used/stored? PR 4 - Community Health, Safety & Security 4.a How far are the nearest villages/towns/cities from the Please describe and include a map: Project site? How far from the Project site are the nearest occupied
houses and/or workplaces? 4.b Will the Company’s activities pose any material risks to, Yes: No: or have any significant impacts on, the health and If yes, please describe: safety of local communities or people? Yes: No: Has a public health assessment been undertaken? If yes, please describe:
4.c Has the Company developed measures to prevent Yes: No: and/or mitigate any such impacts? If yes, please describe:
4.d Has the Company consulted with locally affected Yes: No: community(ies) and stakeholders to discuss the Project If yes, please describe: and measures to be taken to reduce impacts, in order to understand any concerns and address issues associated with potential public health effects? How have impacts of the project on affected communities (if any) been identified and addressed? 4.e Will there be security guards to control entry to the Yes: No: Project site during construction and/or operation? If yes, will they be armed? How will they be trained?
ERM 62 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE Will security be outsourced to a separate company? Yes: No: If yes, what criteria did the Company use to select the security contractor? PR 5 - Land Acquisition, Involuntary Resettlement and Economic Displacement 5.a Does the Company have a person in charge of land Yes: No: acquisition and/or expropriation? Name: Title: Phone/mobile: Email: 5.b Have any structures or land already been acquired by Yes: No: the Company in connection to the Project? If yes, please provide details. 5.c How much land will need to be permanently acquired by the Company for the Project (including power- generating infrastructure, control centre, roads, transmission lines and other related facilities)? How much land will have to be temporarily occupied (e.g. for storage, access to construction sites, accommodation of workers)? 5.d Has the Company already identified owners and users Yes: No: of affected land and structures (for example, from Land If yes, please provide details: Books, Cadastre or through a field survey)? Have any negotiations with land/structure Yes: No: owners/users or any expropriation procedure been If yes, please provide details: initiated (including request for public interest)? What is the land currently being used for? Will land that is not needed by the Company continue Yes: No: to be used by others (such as land between buildings/generating infrastructure)?
ERM 63 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE 5.e Will any people need to be relocated to new houses, Yes: No: new farm land and/or lose access to other valuable If yes, please provide details. assets? 5.f Will the Company acquire land and/or pay for Yes: No: temporarily using it? If yes, how much land will be acquired and/or require payments for use? How will the amount to be paid for purchase or usage be determined? How will the Company proceed if agreement cannot be reached with owner(s)? Is there a written land acquisition plan for the Project? Yes: No: If yes, please provide details: 5.g Will any businesses / economic activities, both formal Yes: No: and informal, in the area be affected by construction If yes, please provide details: activities (e.g. tourism activities)? Does the Company have plans to compensate affected Yes: No: people for loss of business or economic activity? If yes, please provide details: 5.h Is there any resettlement required for this project? Yes No If yes, please provide details: If so, is there a Resettlement Action Plan? Yes No If yes, please provide details: PR 6 – Biodiversity Conservation & Sustainable Management of Living Resources 6.a How far is the Project from the nearest protected or Please provide a list with distances and provide a map showing the designated areas, or areas important for local Project and nearest protected/important areas. biodiversity, including Natura 2000 sites, national parks, Ramsar Sites (wetlands), etc.? 6.b Does the site provide habitat for any protected or Yes: No:
ERM 64 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE sensitive species of plants or animals? If yes, please provide details: 6.c What habitat mapping or species surveys have been completed? 6.d Which habitat areas/species would be impacted by ancillary works, transmission lines, construction access roads, other construction activities etc? 6.e Is there any other baseline environmental data on Yes: No: wildlife of the area not already covered above or in the If yes, please provide further details: Project Description section? 6.f Is there any further information on potential impacts to Yes: No: species or habitats that have not been covered above If yes, please provide further details: or in the Project Description section? PR 7 – Indigenous Peoples Are there any indigenous peoples likely to be impacted by the project? Yes: No: If yes, please provide details: PR 8 – Cultural Heritage 8.a Is the Project located in or near a cultural heritage site Yes: No: recognised by the country in which the project is If yes, please provide details: located, or where artefacts have been found in the past (including UNESCO World Heritage Sites and those on the tentative list, Registered cultural heritage sites, zones and settlements)? 8.b Is the Project located on or near to a place of worship, Yes: No: cemetery or other place of importance and value to a If yes, please provide details: community? 8.c Has the Company consulted with the national, regional, Yes: No: and/or local agency(ies) responsible for protecting If yes, please provide details: cultural resources? ERM 65 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE 8.d Has the risk to cultural heritage sites and areas of Yes: No: archaeological interest been assessed and managed? If yes, please describe: PR 9 – Financial Intermediaries Not relevant for KazREFF PR 10 – Information Disclosure & Stakeholder Engagement 10.a Who will be affected by the Project, including the workforce and local communities? How and to what extent? 10.b Does the Company have a person in charge of Yes: No: communications with local communities? Name: Title: Phone/mobile: Email: 10.c Has the Company established a mechanism through Yes: No: which members of the public can raise concerns or If yes, please provide details: grievances concerning the Company’s environmental and social practices? 10.d Has the Company established a regular means for Yes: No: communicating with affected community(ies)/people If yes, please describe: (e.g. newsletter, email, helpline, open day)? 10.e Is the Company aware of any issues, concerns or Yes: No: positive feedback brought to the Company’s attention If yes, please describe: by members of the community, non-governmental organisations (NGOs), or the media? 10.f Has the company undertaken any consultations with Yes: No: stakeholders – including national, regional, and local If yes, please describe: authorities, NGOs, businesses, citizens? 10.g Does the Company have plans to implement Yes: No: ERM 66 KasREFF SER RPER WIND – June 2014
ENVIRONMENTAL AND SOCIAL DUE DILIGENCE QUESTIONNAIRE community development activities (e.g. is there a If yes, please describe: corporate social responsibility plan)?
(end of questionnaire)
ERM 67 KasREFF SER RPER WIND – June 2014
Kazakhstan Renewable Energy Financing Facility (KazREFF) - Strategic Environmental Review
Appendix C – Environmental and Social Templates
ERM 68 KasREFF SER RPER WIND – June 2014
Kazakhstan Renewable Energy Financing Facility (KazREFF)
TEMPLATE - PROJECT NAME
DATE
Non Technical Summary of Environmental and Social Considerations
P
ERM 69 KasREFF SER RPER WIND – June 2014
CONTENTS
1 Introduction 71 2 Description of the Proposed Development 72 3 Environmental, Health, Safety and Social Review 72
ERM 70 KasREFF SER RPER WIND – June 2014
7.0 Introduction
Add summary of company proposing development – i.e private / public owned, company structure and operations Add summary of project proposals – i.e type of power plant, size and location Add summary of environmental studies undertaken to date – i.e an ESIA?, specialist surveys? (Company name XXX) has approached the European Bank for Reconstruction and Development (EBRD) for financing. The project is thus subject to EBRD’s 2008 Environmental and Social Policy and has been determined as a Category XXX project (add details of whether it is a category A or B project). EBRD has conducted an environmental and social due diligence assessment of the project and supported the development of applicable environmental and social documentation, namely a Stakeholder Engagement Plan, an Environmental and Social Action Plan, and this Non Technical Summary (also add reference to other relevant documents if appropriate eg an ESIA, specialist studies). This document provides in a non-technical manner an overview of the proposed development plans. The document also provides a summary of potential environmental and social impacts and other environmental and social issues relevant to the proposed activities. Appropriate measures to mitigate key adverse environmental and social effects that may arise during project construction and operation are also provided. This NTS document and other materials will be placed in the locations shown below on (add disclosure date XXX). During a 60 / 120 (delete as appropriate) -day period beginning on (add disclosure date XXX), anyone can provide comments and recommendations on the environmental, social and other aspects of the project. Comments can be made at public consultations to be held at the locations shown below, and may be submitted to the address below. Environmental and social documents will be available for review during normal business hours at the following location: XXXX (add details)
Meetings at which anyone can make comments will be held as follows: XXXX (add details) The dates and times of public meetings will be announced at least three weeks before the meeting(s), and advertised in local mass media. For further information on this project, or to provide comments on the project or the environmental and social documentation, please contact: Comments may be submitted to: Name Contact information Address: Complete all contact Phone: details Email:
ERM 71 KasREFF SER RPER WIND – June 2014
8.0 Description of the Proposed Development
Add project description – • prospective annual electricity generation, • equipment to be installed, • permitting requirements, • Location, size, (including location map(s)
9.0 Environmental, Health, Safety and Social Review
Key Environmental and Social Elements Several documents collectively make up the environmental and social documentation for the project. The Non Technical Summary is described above, while the other documents are described here. Environmental and Social Action Plan (ESAP) As part of the environmental and social due diligence evaluation, a wide review was conducted of corporate environmental, health, safety and social management arrangements. From the overall review, an Environmental and Social Action Plan (ESAP) has been developed which lists key actions to ensure areas for improvement can be implemented and include mitigation measures discussed above. This ESAP is being disclosed for public comment; key mitigation measures are described below. Stakeholder Engagement Plan (SEP) (Insert company name XXX) has prepared a Stakeholder Engagement Plan (SEP) for the Project. The SEP will guide (insert company name XXX) in communicating with people, institutions and any other stakeholders who may be affected by or interested in the implementation of Project. (Insert company name XXX) has assigned a social liaison officer, who will be responsible for keeping open dialogue with stakeholders groups and local public. This SEP is being disclosed for public comment. At any time before and during construction and operation, any stakeholder will have a chance to raise any concerns, provide comments and feedback about the Project. All such comments and grievances from people will be accepted, processed and answered by (insert company name XXX) in a timely manner.
Key Features Key environmental features and sensitive locations from a social perspective in relation to the site include:
XXX – add details
Potential Impacts and Mitigation Measures ERM 72 KasREFF SER RPER WIND – June 2014
The EBRD’s environmental and social diligence evaluation determined that the project could have negative impacts on environmental resources and on people if they are not controlled carefully. Therefore, the EBRD will require (insert company name XXX) to implement many actions (“mitigation measures”) to prevent, reduce, or mitigate impacts on people and the environment. A summary of key impacts and mitigation measures have been identified, and they are summarised in Appendix A.
ERM 73 KasREFF SER RPER WIND – June 2014
Overview of Potential Impacts and Mitigation
Resource Potential Impact / Issue of Concern Mitigation
For example … Climate and Air Quality
Geology, Geohazards and Soils
Surface Water & Groundwater
Water Supply
Ecosystems and Flora & Fauna Noise
Waste Management
Cultural Heritage Tourism
Visual Landscape
Socio-economics
Traffic Management
Occupational Health & Safety Public Health & Safety
ERM 74 KasREFF SER RPER WIND – June 2014
Others…
ERM 75 KasREFF SER RPER WIND – June 2014 Contents
Kazakhstan Renewable Energy Financing Facility (KazREFF)
TEMPLATE - PROJECT NAME
DATE
Stakeholder Engagement Plan
Prepared for:
ERM 76 KasREFF SER RPER WIND – June 2014
CONTENTS 1 Introduction 78 1.1 Background 78 1.2 Description of the Proposed Development 78 1.3 Overview of XXX (add company name) 78 1.4 Objectives of the Stakeholder Engagement Plan (SEP) 78 1.5 Structure of SEP 79 2 Regulatory Context 80 2.1 Kazakhstan requirements for stakeholder engagement/ public consultation 80 2.2 EBRD requirements for stakeholder engagement and public consultation 80 3 Summary of previous stakeholder engagement 82 3.1 EBRD previous stakeholder engagement and consultations in Kazakhstan 82 3.2 KazREFF SER Consultations 82 3.3 Public disclosure and consultations during project 83 3.4 Other consultations during the project 83 4 Stakeholder Identification and Communication Methods 84 5 Disclosure of Information and Stakeholder Engagement Programme 86 5.1 Disclosure of general information 86 5.2 Disclosure of information relevant to Project 86 5.3 Stakeholder engagement programme 86 6 Timetable 87 7 Public Grievance Mechanism 88 8 Roles and Responsibilities 89
ERM 77 KasREFF SER RPER WIND – June 2014
10.0 Introduction
10.1 BACKGROUND Add summary of company proposing development – i.e private / public owned, company structure and operations Add summary of project proposals – i.e type of power plant, size and location Add summary of environmental studies undertaken to date – i.e an ESIA?, specialist surveys? (Company name XXX) has approached the European Bank for Reconstruction and Development (EBRD) for financing. The project is thus subject to EBRD’s 2008 Environmental and Social Policy and has been determined as a Category XXX project (add details of whether it is a category A or B project). EBRD has conducted an environmental and social due diligence assessment of the project and supported the development of applicable environmental and social documentation, namely a Stakeholder Engagement Plan, an Environmental and Social Action Plan, and a Non Technical Summary of the environmental and social considerations (also add reference to other relevant documents if appropriate eg an ESIA, specialist studies). To meet EBRD requirements for stakeholder engagement and public consultation and disclosure (EBRD Performance Requirement PR10), a stakeholder and public engagement process with development of a Stakeholder Engagement Plan (SEP) will also be directly applied to this project. These details are laid out in this document, the SEP. EBRD considers stakeholder engagement as an essential part of good business practices and corporate citizenship, and a way of improving the quality of projects. In particular, effective community engagement is central to the successful management of risks and impacts on communities affected by projects, as well as to achieving enhanced community benefits.
10.2 DESCRIPTION OF THE PROPOSED DEVELOPMENT Add project description – • prospective annual electricity generation, • equipment to be installed, • permitting requirements, • Location, size, (including location map(s)
10.3 OVERVIEW OF XXX (ADD COMPANY NAME) Add summary of company proposing development – i.e private / public owned, company structure and operations
10.4 OBJECTIVES OF THE STAKEHOLDER ENGAGEMENT PLAN (SEP) This SEP has been developed with the aim of explaining how company name XXX will communicate with people and institutions who may be affected by or interested in the Project, at various stages of project preparation and implementation. The plan includes a
ERM 78 KasREFF SER RPER WIND – June 2014
grievance mechanism for stakeholders to raise any concerns related to the project for company name XXX attention. 10.5 STRUCTURE OF SEP The remainder of this SEP is organised as follows: • Chapter 2 briefly describes applicable regulations and requirements for stakeholder engagement and public consultations. • Chapter 3 summarises previous and on-going stakeholder engagement and public consultation activities. • Chapter 4 identifies stakeholders and describes communication methods with them. • Chapter 5 describes stakeholder engagement program and disclosure of information. • Chapter 6 describes roles and responsibilities for handling the consultation and information disclosure process. • Chapter 7 describes a grievance mechanism by which feedback, comments, concerns and complaints may be communicated to company name XXX and how these grievances and comments will be handled.
ERM 79 KasREFF SER RPER WIND – June 2014
11.0 Regulatory Context
11.1 KAZAKHSTAN REQUIREMENTS FOR STAKEHOLDER ENGAGEMENT/ PUBLIC CONSULTATION Kazakhstan is a signatory for Aarhus Convention on Access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters (UNECE)11. The convention is designed to improve the way ordinary people engage with government and decision-makers on environmental matters. Consequently, citizens of Kazakhstan are entitled to be informed about all environment related issues pertaining to the project and it is the responsibility of public authorities, local authorities, or government departments to reveal such environmental information. National legislation also foresees broad public involvement in decision-making process. Further details to be added….
11.2 EBRD REQUIREMENTS FOR STAKEHOLDER ENGAGEMENT AND PUBLIC CONSULTATION Since EBRD may be involved in funding the Project, the Project must meet the best international practices and requirements for stakeholder engagement and public consultations as specified in the EBRD Environmental and Social Policy of 2008.
The principles, requirements, methodological and procedural aspects of stakeholder engagement for EBRD Category A and B projects are described in detail in PR10 “Information Disclosure and Stakeholder Engagement 12 . PR10 outlines a systematic approach to stakeholder engagement that will help clients build and maintain over time a constructive relationship with their stakeholders, including the locally affected communities.
As required, the following important stages shall be implemented for the Project engagement and consultation process: - Identification of project stakeholder groups. Identification of stakeholders, including members of the public who could be affected by the Project construction and operation. - Stakeholder engagement process and information disclosure. During this step, company name XXX is to ensure that identified stakeholders are appropriately engaged on environmental and social issues that could potentially affect them through a process of information disclosure and meaningful consultation. - Meaningful consultation. The consultation process will be based on the disclosure of information relevant to the Project activities and operations. The consultation process will be undertaken in a manner that is inclusive and culturally appropriate for all stakeholders, including effected communities and vulnerable groups.
11 UNECE Aarhus Convention on access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters
12 EBRD Environmental and Social Policy 2008 (http://www.ebrd.com/downloads/about/sustainability/2008policy.pdf)
ERM 80 KasREFF SER RPER WIND – June 2014
- Grievance mechanism. Maintaining a grievance process by which the general public and other stakeholders can raise concerns, and which will be handled in a prompt and consistent manner.
The stakeholder engagement process and SEP preparation was also guided by the IFC Good Practice Handbook13 that defines the best practice approach to stakeholder engagement.
13 http://www.ifc.org/ifcext/enviro.nsf/AttachmentsByTitle/p_StakeholderEngagement_Full/$FILE/IFC_StakeholderEngagement.pdf
ERM 81 KasREFF SER RPER WIND – June 2014
12.0 Summary of previous stakeholder engagement
12.1 EBRD PREVIOUS STAKEHOLDER ENGAGEMENT AND CONSULTATIONS IN KAZAKHSTAN The European Bank for Reconstruction and Development (”EBRD” or the “Bank”) has made RES a key priority for investment in its countries of operation and has reviewed a number of early stage RES projects in Kazakhstan. The Bank has gained initial approval from the Clean Technology Fund (CTF) for concessional finance of up to $110 million to help create markets for power from RES in Kazakhstan. The Bank is now in the process of establishing dedicated financing facilities to enable it to provide finance to both larger and smaller RES projects in Kazakhstan (up to €10 million per project). This will be supported by funds from the CTF. The Bank has been active since 2008 in assisting the Government of Kazakhstan (the “Government”) through a technical cooperation programme in supporting the preparation of legislation to support RES development which has involved extensive stakeholder dialogue with the Ministry of Industry and New Technologies (MINT). In 2012, during the early stages of renewable energy programme development for Kazakhstan, the EBRD launched the assignment Kazakhstan Renewable Energy Development Framework and Regulatory Support (TCS number 34068). This assignment was to provide technical assistance in renewable energy regulatory support and institution building to the Kazakhstan Ministry of Industry and New Technologies (MINT; subsequently renamed the Ministry of Environment and Water Resources, or MEWR). Included in that assignment was a Renewable Energy Market Study, which included extensive stakeholder dialogue to establish the appropriate structure for renewable energy regulation in Kazakhstan. A number of key stakeholders and interested parties were identified at that stage, including local authorities and regulators at different levels, potential donor agencies, scientific and research institutes, and private developers. All targeted groups were contacted, and a series of individual meetings and workshops were organized and undertaken.
12.2 KAZREFF SER CONSULTATIONS
The Kazakhstan Renewable Energy Financing (KazREFF) undertook a large stakeholder engagement exercise alongside the Strategic Environmental Review (SER) of the potential effects of implementing renewable energy projects funded under KazREFF. The SER consultations were undertaken in three stages:
• Stage 1 (between April and July 2013). In Stage 1, the information about the KazREFF SER and SER Scoping Report was disclosed to with 30 representatives of various stakeholder groups; 13 of whom were individually interviewed. Representative stakholders included representatives of local authorities, manufacturers, developers and consultants involved in the development and implementation of renewable energy projects in Kazakhstan. The initial list of stakeholders resulting from stakeholder identification and analysis was expanded and amended where necessary. • Stage 2 (between July 2013 and September 2013). In Stage 2, the SER Environmental Scoping Report was published on the KazREFF SER website at http://www.kazreff-
ERM 82 KasREFF SER RPER WIND – June 2014
ser.com. EBRD conducted half-day scoping meetings on 16 and 18 July 2013 in Astana and Almaty, respectively, to encourage broad stakeholder participation in the development of the SER. Outreach activities, including mailing, emailing and telephoning contacts, were undertaken with 86 organizations representing a variety of stakeholders in the Astana and Almaty areas including government, developers, non- governmental organizations (NGOs), consultants, and advisory bodies. Eighteen organizations representing a variety of stakeholders participated in the meetings. • Stage 3 (June 2014 through October 2014). In Stage 3, the Draft SER report was disclosed and initiated formal 120-day public consultation period, where all stakeholders had an opportunity to provide comment on the disclosed Draft SER report. During this timeframe, two workshops were held to both inform and educate stakeholders about the SER and the KazREFF.
12.3 PUBLIC DISCLOSURE AND CONSULTATIONS DURING PROJECT Add details of any public disclosure / consultation undertaken to date as part of this project.
12.4 OTHER CONSULTATIONS DURING THE PROJECT Add details of any other consultation that may have occurred as part of the project, for example with authorities to obtain necessary permits.
ERM 83 KasREFF SER RPER WIND – June 2014
13.0 Stakeholder Identification and Communication Methods
In order to define a communication process in line with EBRD PR10, company name XXX has identified several stakeholder groups that may be interested and/or affected by the Project development and implementation. The stakeholders identified include: • Internal stakeholders, such as company name XXX employees and construction contractors’ workers
• External stakeholders, such as o governmental authorities, o non-governmental organisations and o local residents.
Others who wish to be included in the list can contact company name XXX and be put on the mailing list for information on reporting, meetings, or other consultation opportunities.
Table 1 describes the stakeholder engagement programme and communication process by providing contact details of certain stakeholders, and identifying communication methods and specific media that will be used to notify stakeholders of information. Any suggestions for improvement of proposed communication methods or media are welcomed and can be submitted via the contact information at the end of this document.
Table 1. Stakeholder engagement programme for the Project Stakeholder group Description Communication method / Proposed Media channel and contact information (where applicable) Internal Stakeholders Employees XXX For example… Company website?? - Internal newsletters www.kazreff.com?? - Emails - Grievance procedure - Bulletin boards - Union meetings - Inserts with payslips Temporary Construction XXX For example… XXX Workers, subcontractors - Internal newsletters - Emails - Grievance procedure - Bulletin boards - Union meetings - Inserts with payslips Unions: XXX For example… XXX • XXX - Official correspondence.
ERM 84 KasREFF SER RPER WIND – June 2014
Table 1. Stakeholder engagement programme for the Project Stakeholder group Description Communication method / Proposed Media channel and contact information (where applicable) - Union newsletter. - Information on request to union representatives. External Stakeholders Population in XXX XXX XXX Newspapers: XXX Radio: XXX Company website?? www.kazreff.com?? Local authorities and public enterprises: For example… XXX For example… XXX Water Company - Communication via official letters and meetings Public Health Institute XXX For example… XXX - Ongoing working linkages with the Institute County / city XXX For example… XXX administration - Ongoing working linkages with the authorities - Official correspondence - Meetings State level authorities: - Ukrainian Water XXX For example… XXX Authority - Official correspondence - Ministries - Meetings • XXX
Other relevant external stakeholders For example… XXX - Meetings (invitation to public Company website?? Local Tourist Board consultation meetings) www.kazreff.com?? Others..
ERM 85 KasREFF SER RPER WIND – June 2014
14.0 Disclosure of Information and Stakeholder Engagement Programme
14.1 DISCLOSURE OF GENERAL INFORMATION Provide details of general information disclosure – website, company reports etc
14.2 DISCLOSURE OF INFORMATION RELEVANT TO PROJECT To meet the environmental and social requirements and performance standards of EBRD and EU, company name XXX will develop, disclose to the public and then implement an Environmental and Social Action Plan (ESAP), which will identify mitigation measures to minimise, reduce, eliminate or control potential adverse impacts on environment and people.
The final version of ESAP will be published on company name XXX official website (or KazREFF website?) and printed copies will be available on request from XXX (contact information available in the table above).
The local population will receive timely information (through the local media listed in the table above and announcements regarding grievance management in relation to construction activities, safety measures in the vicinity of the construction site, traffic management, employment opportunities and opportunities for service provision (catering, accommodation of workers, laundry services, etc.) and any other information identified through the development of the ESAP.
Annual project progress reports, including environmental and social impacts, health and safety performance and implementation of the external grievance mechanism will also be disclosed on company name XXX official website (or KazREFF website?) and will be available on request XXX (contact information available in the table above).
14.3 STAKEHOLDER ENGAGEMENT PROGRAMME Consultations and disclosure of information for local public
Public consultations will be held after a draft Environmental and Social Action Plan has been developed. Add details of proposed consultation. For example - who will manage it, when will it take place, and with whom?
Other stakeholder engagement activities Add details of proposed consultation. For example - who will manage it, when will it take place, and with whom?
ERM 86 KasREFF SER RPER WIND – June 2014
15.0 Timetable
Stakeholder(s) and engagement Issues / documents Possible dates activity(ies) During the development of ESAP and NTS XXX XXX XXX XXX XXX XXX When the ESAP/SEP/NTS are completed All stakeholders Publish ESAP, SEP and NTS (in XXX English and Ukrainian) and inform all stakeholders through local media. Include responses to comments, suggestions which were not incorporated in the documents. Before construction Contractors / temporary workers Agree construction related XXX grievance management, inform all stakeholders; Code of conduct for temporary workers, trainings Local population Information on safety measures XXX Traffic Management Plan Employment opportunities and opportunities for service provision During construction and operation Public consultation meetings if Implementation of the ESAP, new XXX necessary (determined in cooperation impacts, revision of documents, with EBRD) implementation of SEP, processing and responding to grievances
After construction
Ongoing meetings and cooperation, throughout the life of the project, with the following external stakeholders: • XXX
ERM 87 KasREFF SER RPER WIND – June 2014
16.0 Public Grievance Mechanism
The objective of a grievance procedure is to ensure that all comments and complaints from any project stakeholder, including local/regional authorities, residents of nearby residential areas, company name XXX employees, company name XXX contractors’ staff and other interested parties, are considered and addressed in an appropriate and timely manner. All grievances will be acknowledged and responded to within a reasonable timeframe. company name XXX will accept all comments and complaints associated with the project. A sample of a Comments and Complaints Form is shown in Appendix A. The comments and complaints will be summarised and listed in a Complaints/Comments Log Book, containing the name/group of commenter/complainant, date the comment was received, brief description of issues, information on proposed corrective actions to be implemented (if appropriate) and the date of response sent to the commenter/complainant. Any person or organisation may send comments and/or complaints in person or via post, email, or facsimile using the contact information specified in Section 8.0 below.
All comments and complaints will be responded to either verbally or in writing, in accordance with preferred method of communication specified by the complainant in the Comments and Complaints Form. Comments will be reviewed and taken into account in the project preparation; however they may not receive an individual response unless requested.
All grievances will be registered and acknowledged within 5 days and responded to within 20 working days. Company name XXX will keep a grievance log and report on grievance management, as part of annual project progress reports, available at the company name XXX website and on request at add contact details.
Comments and concerns regarding the project can be submitted in writing in the following ways: • electronic form on company name XXX website or KazREFF website?: add details • email: XXX • by post or hand delivered to (see example grievance form attached): – XXX • by phone: – XXX
Provide contact person and specify contact details Individuals who submit their comments or grievances have the right to request that their name be kept confidential.
During construction, grievances in relation to construction activities will be managed by company name XXX and construction contractor. Local residents will be informed about the contractors contact information before construction begins, through the local media (listed in the table above) and announcements in public places.
ERM 88 KasREFF SER RPER WIND – June 2014
A separate grievance mechanism is available for workers, both employees of company name XXX and the contractors. 17.0 Roles and Responsibilities
Provide contact person and specify contact details will have the overall responsibility for handling the consultation and information disclosure process, including organisation of consultation process, communication with identified stakeholder groups, collecting and processing comments/complaints, and responding to any such comments and complaints. Depending on the nature of a comment/complaint, some comments or complaints will be provided to the appropriate person in the company for a response.
Name of the person and title Affiliation XXX Company: XXX Postal Address: XXX Telephone: XXX E-mail address: XXX Hotline: XXX
ERM 89 KasREFF SER RPER WIND – June 2014
APPENDIX A Comments and Complaints Sample Form FORM FOR COMMENTS, COMPLAINTS AND REPORTS OF INDIVIDUALS Reference No: Full Name
Contact Information By Post: Please provide mailing address: and Preferred method ______of communication ______
Please mark how you wish to be contacted By Telephone: ______(mail, telephone, e-
mail). By E-mail ______
Description of Incident or Grievance: What happened? Where did it happen? Who did it happen to? What is the result of the problem? Source and duration of the problem?
Date of Incident/Grievance