Initial Environment Examination

Project Number: 45224-003 January 2018 (Addendum) Part B: Annexures

IND: Renewable Energy Transmission Investment Program - Tranche 1

Submitted by

Rajasthan Rajya Vidyut Prasaran Nigam Limited, Jaipur

This Addendum to Initial Environment Examination(IEE) has been submitted to ADB by Rajasthan Rajya Vidyut Prasaran Nigam Limited, Jaipur and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This is an addendum to IEE posted in June 2012 available on https://www.adb.org/projects/documents/mff-rajasthan-renewable- energy-transmission-investment-program-facility-concept-iee. This Addendum to Initial Environment Examination Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

S.NO -111 S. No -112 Location No Latitude Longitude Location No Latitude Longitude AP 84/1 27° 9'40.27" 72°24'10.24" AP85/0 27º09ʼ50.7ˮ 72º24ʼ02.8ˮ

S. No -113 S. No -114 Location No Latitude Longitude Location No Latitude Longitude AP86/0 27º10ʼ04.1ˮ 72º23ʼ39.0ˮ AP87/0 27º10ʼ07.4ˮ 72º23ʼ24.8ˮ

S.NO -115 S. No -116 Location No Latitude Longitude Location No Latitude Longitude AP88/0 27º10ʼ05.0ˮ 72º23ʼ18.2ˮ AP89/0 27º10ʼ01.5ˮ 72º23ʼ12.0ˮ

S. No -117 S. No -118 Location No Latitude Longitude Location No Latitude Longitude AP89A/0 27º09ʼ56.5ˮ 72º23ʼ04.6ˮ AP89B/0 27º09ʼ59.8ˮ 72º22ʼ51.4ˮ

S.NO -119 S. No -120 Location No Latitude Longitude Location No Latitude Longitude AP90/0 27º10ʼ03.9ˮ 72º22ʼ42.4ˮ AP91/0 27º10ʼ13.5ˮ 72º21ʼ23.7ˮ

S. No -121 S. No -122 Location No Latitude Longitude Location No Latitude Longitude AP92/0 27º10ʼ19.2ˮ 72º21ʼ17.8ˮ AP93/0 27º11ʼ02.01ˮ 72º21ʼ00.27ˮ

S.NO -123 S. No -124 Location No Latitude Longitude Location No Latitude Longitude AP94/0 27º11ʼ05.5ˮ 72º20ʼ52.6ˮ AP95/0 27º11ʼ15.9ˮ 72º20ʼ37.2ˮ

S. No -125 S. No -126 Location No Latitude Longitude Location No Latitude Longitude AP96/0 27º11ʼ17.1ˮ 72º20ʼ31.7ˮ AP97/0 27º11ʼ51.3ˮ 72º19ʼ17.1ˮ

S.NO -127 S. No -128 Location No Latitude Longitude Location No Latitude Longitude AP98/0 27º12ʼ44.7ˮ 72º18ʼ05.5ˮ AP99/0 27º13ʼ07.0ˮ 72º17ʼ23.8ˮ

S. No -129 S. No -130 Location No Latitude Longitude Location No Latitude Longitude AP100/0 27º13ʼ54.5ˮ 72º15ʼ29.2ˮ AP101/0 27º14ʼ42.7ˮ 72º14ʼ30.8ˮ

S.NO -131 S. No -132 Location No Latitude Longitude Location No Latitude Longitude AP102/0 27º15ʼ12.3ˮ 72º13ʼ46.6ˮ AP103/0 27º15ʼ24.3ˮ 72º13ʼ11.5ˮ

S. No -133 S. No -134 Location No Latitude Longitude Location No Latitude Longitude AP103A/0 27º15ʼ32.6ˮ 72º13ʼ04.0ˮ AP104/0 27º16ʼ29.6ˮ 72º12ʼ31.0ˮ

S.NO -135 S. No -136 Location No Latitude Longitude Location No Latitude Longitude AP105/0 27°18'29.7" 72°10'28.2" AP106/0 27°19'08.9" 72°09'37.9"

S. No -137 S. No -138 Location No Latitude Longitude Location No Latitude Longitude AP107/0 27°19'43.4" 72°08'28.3" AP108/0 27°20'43.7" 72°07'19.3"

S.NO -139 S. No -140 Location No Latitude Longitude Location No Latitude Longitude AP109/0 27°20'52.3" 72°06'38.9" AP110/0 27°21'45.5" 72°05'58.2"

S. No -141 S. No -142 Location No Latitude Longitude Location No Latitude Longitude AP111/0 27º22'19.5" 72°05'37.8" AP112/0 27º24ʼ11.7ˮ 72º03ʼ27.2ˮ

S.NO -143 S. No -144 Location No Latitude Longitude Location No Latitude Longitude AP113/0 27º26ʼ02.6ˮ 72º01ʼ21.1ˮ AP113A/0 27º26ʼ56.2ˮ 71º58ʼ31.4ˮ

S. No -145 S. No -146 Location No Latitude Longitude Location No Latitude Longitude AP114/0 27º28ʼ08.1ˮ 71º56ʼ12.9ˮ AP114A/0 27º29ʼ04.8ˮ 71º54ʼ19.2ˮ

S.NO -147 S. No -148 Location No Latitude Longitude Location No Latitude Longitude AP115/0 27º29ʼ32.7ˮ 71º53ʼ52.0ˮ AP 115A/0 27º30ʼ40.1ˮ 71º54ʼ08.3ˮ

S. No -149 S. No -150 Location No Latitude Longitude Location No Latitude Longitude AP 116/0 27º31ʼ54.9ˮ 71º54ʼ35.8ˮ AP 117/0 27º32ʼ4.3ˮ 71º54ʼ36.4ˮ

# Angle Towers (Locations marked in Yellow) as per Revised route approved due to Decision of High Court Dated Oct 5, 2017 in the DB Civil Petition No. 14676/2016 attached in Annexure 7.

Photographs of New Tower Locations AP 79A/0 to AP 83D/0 in the Khichan Village With GPS coordinates

AP 79A/0 AP 79B/0 79B/1 Latitude Longitude Latitude Longitude Latitude Longitude 27° 07' 37.3531" 72° 26' 26.5960" 27° 07' 48.5140" 72° 26' 29.4277" 27° 07' 54.4165" 72° 26' 39.6041" N E N E N E

80/0 AP 80/1 AP 81/0 Latitude Longitude Latitude Longitude Latitude Longitude 27° 08' 01.0960" 72° 26' 51.4333" 27° 08' 12.4059" 72° 26' 55.3154" 27° 08' 22.0492" 72° 26' 58.6545"

N E N E N E

AP 82/0 82/1 AP 82A/0 Latitude Longitude Latitude Longitude Latitude Longitude 27° 08' 28.4517" 72° 26' 58.8359" 27° 08' 40.1170" 72° 26' 59.0430" 27° 08' 52.8226" 72° 26' 59.2990" N E N E N E

82A/1 82A/2 82B/1 Latitude Longitude Latitude Longitude Latitude Longitude 27° 09' 00.4388" 72° 26' 54.7685" 27° 09' 07.3478" 72° 26' 50.6534" 27° 09' 22.4800" 72° 26' 36.1105" N E N E N E

82B/2 AP 82C/0 82C/1 Latitude Longitude Latitude Longitude Latitude Longitude 27° 09' 31.0210" 72° 26' 25.3120" 27° 09' 39.6916" 72° 26' 14.5101" 27° 09' 46.2010" 72° 26' 02.7767" N E N E N E

AP 83/0 83/1 83/2 Latitude Longitude Latitude Longitude Latitude Longitude 27° 09' 52.6161" 72° 25' 51.2266" 27° 09' 54.0529" 72° 25' 37.4660" 27° 09' 55.3018" 72° 25' 24.1092" N E N E N E

AP 83A/0 83A/1 83A/2 Latitude Longitude Latitude Longitude Latitude Longitude 27° 09' 56.3036" 72° 25' 13.2276" 27° 09' 53.0279" 72° 25' 02.9164" 27° 09' 49.6811" 72° 24' 52.2803" N E N E N E

AP 83B/0 AP 83C/0 AP 83D/0 Latitude Longitude Latitude Longitude Latitude Longitude 27° 09' 45.8533" 72° 24' 40.2392" 27° 09' 34.9178" 72° 24' 33.8096" 27° 09' 30.0021" 72° 24' 20.9227" N E N E N E

AP’s IMAGES 400kV D/C Quad ACSR Moose Akal- Transmission Line Project (ICB-7) S.NO -1 S. No -2 Location No Latitude Longitude Location No Latitude Longitude AP 1/0 26°48'59.48"N 71° 3'58.40"E AP 1A/0 (,) 26°48'55.38"N 71° 4'1.31"E

S. No -3 S. No -4 Location No Latitude Longitude Location No Latitude Longitude AP 1B/0 26°48'54.92"N 71° 4'10.76"E AP 2/0 26°48'59.44"N 71° 4'17.56"E

S.NO -5 S. No -6 Location No Latitude Longitude Location No Latitude Longitude AP 3/0 26°49'03.42"N 71°05'04.89"E AP 4/0 26°49'05.72"N 71°05'10.29"E

S. No -7 S. No -8 Location No Latitude Longitude Location No Latitude Longitude AP 5/0 26°48'58.63"N 71°05'47.71"E AP 6/0 26°48'25.56"N 71° 7'53.47"E

S.NO -9 S. No -10 Location No Latitude Longitude Location No Latitude Longitude

Ap7/0 26°47'32.55"N 71° 9'5.38"E AP 7/0 26°47'32.55"N 71° 9'5.38"E

S. No -11 S. No -12 Location No Latitude Longitude Location No Latitude Longitude AP 8A/0 26°46'50.85"N 71°11'18.84"E AP 8B/0 26°46'31.08"N 71°11'50.63"E

S.NO -13 S. No -14 Location No Latitude Longitude Location No Latitude Longitude AP 8C/0 26°45'7.49"N 71°13'12.41"E AP 9/0 26°45'7.50"N 71°13'17.85"E

S. No -15 S. No -16 Location No Latitude Longitude Location No Latitude Longitude AP 10/0 26⁰43'50.73"N 71⁰16'18.64"E AP 10A/0 26°43'48.48"N 71° 17'24.01"E

S.NO -17 S. No -18 Location No Latitude Longitude Location No Latitude Longitude AP 10B/0 26°43'28.68"N 71° 17'51.53"E AP 11/0 26°43'34.7"N 71° 18'27.6"E

S. No -19 S. No -20 Location No Latitude Longitude Location No Latitude Longitude AP 11A/0 26°43'17.46"N 71°19'01.68"E AP 11B/0 26°42'23.69"N 71°20'33.96"E

S.NO -21 S. No -22 Location No Latitude Longitude Location No Latitude Longitude AP 12/0 26°41'52.39"N 71°21'49.31"E AP 12A/0 26°41'27.97"N 71°23'03.93"E

S. No -23 S. No -24 Location No Latitude Longitude Location No Latitude Longitude AP 13/0 26°41'23.00"N 71°23'30.25"E AP 14/0 26°40'47.66"N 71°24'57.93"E

S.NO -25 S. No -26 Location No Latitude Longitude Location No Latitude Longitude AP 15/0 26°40'5.0"N 71°26'21.36"E AP 16/0 26°39'2.16"N 71°28'20.09"E

S. No -27 S. No -28 Location No Latitude Longitude Location No Latitude Longitude AP 17/0 26°38'56.61"N 71°29'14.38"E AP 18/0 26°38'11.40"N 71°32'7.90"E

S.NO -29 S. No -30 Location No Latitude Longitude Location No Latitude Longitude AP 19/0 26°38'0.19"N 71°32'32.43"E AP 20/0 26°37'52.77"N 71°33'13.22"E

S. No -31 S. No -32 Location No Latitude Longitude Location No Latitude Longitude AP 21/0 26˚36'44.30"N 71˚35'24.08"E AP 22/0 26˚34'00.51"N 71˚40'23.71"E

S.NO -33 S. No -34 Location No Latitude Longitude Location No Latitude Longitude AP 22A/0 (, 26˚33'32.13"N 71˚41'00.05"E AP 23/0, (26°30'35.54"N 71°46'12.30"E

S. No -35 S. No -36 Location No Latitude Longitude Location No Latitude Longitude AP 23A/0 26°30'27.50"N 71°46'50.99"E AP 23AB/0 (26°30'01.90"N 71°47'55.80"E

S.NO -37 S. No -38 Location No Latitude Longitude Location No Latitude Longitude AP 24/0 AP 25/0 (26°28'28.65"N, (26˚27'47.73"N, 71°52'47.11"E 71˚53'50.01"E)

S. No -39 S. No -40 Location No Latitude Longitude Location No Latitude Longitude AP 25A/0 26°27'27.62"N 71°56'0.77"E AP 25B/0 26°27'4.32"N 71°56'30.98"E

S.NO -41 S. No -42 Location No Latitude Longitude Location No Latitude Longitude

AP 26/0 26°26'11.63"N 71°58'44.84"E AP 26A/0 26°26'4.41"N 71°59'10.85"E

S. No -43 S. No -44 Location No Latitude Longitude Location No Latitude Longitude AP 27/0 (, 26°25'56.28"N 71°59'21.29"E AP 28/0 26°25'53.40"N 71°59'34.31"E

S.NO -45 S. No -46 Location No Latitude Longitude Location No Latitude Longitude AP 29/0 26˚25’39.01"N 72˚00’11.16"E AP 30/0 26˚25'31.60"N 72˚00'22.87"E

S. No -47 S. No -48 Location No Latitude Longitude Location No Latitude Longitude AP 30A/0 26˚25'25.47"N 72˚00'33.45"E AP 30B/0 26°25'22.02"N 72° 0'43.61"E

S.NO -49 S. No -50 Location No Latitude Longitude Location No Latitude Longitude AP 31/0 26˚25'13.20"N 72˚01'10.50"E AP 32/0 26˚25'03.50"N 72˚02'02.60"E

S. No -51 S. No -52 Location No Latitude Longitude Location No Latitude Longitude AP 33/0 26˚24'41.80"N 72˚02'14.20"E AP 34/0 26˚24’13.60"N 72˚03’15.39"E

S.NO -53 S. No -54 Location No Latitude Longitude Location No Latitude Longitude AP 35/0 26°23'55.90"N 72° 3'43.19"E AP 36/0 26°23'18.74"N 72° 4'14.11"E

S. No -55 S. No -56 Location No Latitude Longitude Location No Latitude Longitude AP 37/0 26°23'21.69"N 72° 5'30.11"E AP 38/0 26°23'26.02"N 72° 5'42.34" E

S.NO -57 S. No -58 Location No Latitude Longitude Location No Latitude Longitude AP 39/0 26°23'19.20"N 72° 6'22.97"E AP 40/0 26°22'54.40"N 72° 9'6.40"E

S. No -59 S. No -60 Location No Latitude Longitude Location No Latitude Longitude AP 40A/0 26°22'54.80"N 72°11'42.30"E AP 41/0 26°22'54.85"N 72°11'53.45"E

S.NO -61 S. No -62 Location No Latitude Longitude Location No Latitude Longitude AP 42/0 26°22'47.60"N 72°12'24.90"E AP 42A/0 26°22'48.95"N 72°12'51.13"E

S. No -63 S. No -64 Location No Latitude Longitude Location No Latitude Longitude AP 43/0 26°22'47.61"N 72°13'30.91"E AP 44/0 26°22'45.49"N 72°15'17.18"E

S.NO -65 S. No -66 Location No Latitude Longitude Location No Latitude Longitude AP 45/0 26°22'04.2"N 72°16'53.2"E AP 45/1 26°22'02.19"N 72°17'01.90"E

S. No -67 S. No -68 Location No Latitude Longitude Location No Latitude Longitude AP 45A/0 26°21'52.5"N 72°17'43.3"E AP 45B/0 26°21'45.0"N 72°17'56.9"E

S.NO -69 S. No -70 Location No Latitude Longitude Location No Latitude Longitude AP 45B/1 26°21'40.83"N 72°18'9.81"E AP 45B/2 26°21'38.00"N 72°18'18.43"E

S. No -71 S. No -72 Location No Latitude Longitude Location No Latitude Longitude AP 45B/4 26°21'32.32"N 72°18'35.79"E AP 45B/5 26°21'29.38"N 72°18'44.58"E

S.NO -73 S. No -74 Location No Latitude Longitude Location No Latitude Longitude AP 46/0 26°21'24.93"N 72°18'58.86"E AP 47/0 26°21'27.90"N 72°19'26.36"E

S. No -75 S. No -76 Location No Latitude Longitude Location No Latitude Longitude AP 48/0 26°21'7.88"N 72°19'58.34"E AP 49/0 26°20'43.12"N 72°20'46.35"E

S.NO -77 S. No -78 Location No Latitude Longitude Location No Latitude Longitude AP 49A/0 AP 50/0 (26°20'24.00"N, (26°20'20.21"N, 72°21'36.44"E 72°22'2.71"E

S. No -79 S. No -80 Location No Latitude Longitude Location No Latitude Longitude AP 50A/0 26°20'4.64"N 72°22'22.87"E AP 51/0 26°20'0.30"N 72°22'49.40"E

S.NO -81 S. No -82 Location No Latitude Longitude Location No Latitude Longitude AP 51A/0 26°19'55.79"N 72°22'58.51"E AP 52/0 26°19'47.16"N 72°23'8.39"E

S. No -83 S. No -84 Location No Latitude Longitude Location No Latitude Longitude AP 52A/0 26°19'49.71"N 72°23'34.47"E AP 53/0 26°19'53.42"N 72°24'13.67"N

S.NO -85 S. No -86 Location No Latitude Longitude Location No Latitude Longitude AP 53A/0 26°19'38.34"N 72°24'33.78"N AP 54/0 26°19'22.63"N 72°24'53.99"N

S. No -87 S. No -88 Location No Latitude Longitude Location No Latitude Longitude AP 54/6 (TPT) 26°18'55.17"N 72°26'07.20"E AP 55/0 26°18'50.61"N 72°26'18.89"N

S.NO -89 S. No -90 Location No Latitude Longitude Location No Latitude Longitude AP 55A/0 26⁰18'22.00"N 72⁰27'18.08" E AP 56/0 26°18'14.00"N 72°27'54.46"E

S. No -91 S. No -92 Location No Latitude Longitude Location No Latitude Longitude AP 56A/0 26°17'35.77"N 72°28'25.11"E AP 57/0 26⁰17'18.28"N 72⁰28'39.25"E

S.NO -93 S. No -94 Location No Latitude Longitude Location No Latitude Longitude AP 58/0 26⁰16'44.36"N 72⁰29'48.48" E AP 59/0 26⁰16'48.61"N 72⁰30'43.51"E

S. No -95 S. No -96 Location No Latitude Longitude Location No Latitude Longitude AP 60/0 26⁰16'39.84"N 72⁰31'23.35"E AP 61/0 26⁰16'36.94"N 72⁰32'03.37"E

S.NO -97 S. No -98 Location No Latitude Longitude Location No Latitude Longitude AP 62/0 26⁰16'31.13"N 72⁰32'07.24"E AP 63/0 26⁰15'54.96"N 72⁰33'14.89"E

S. No -99 S. No -100 Location No Latitude Longitude Location No Latitude Longitude AP 64/0 26⁰15'34.33"N 72⁰34'04.52"E AP 65/0 26⁰15'28.65"N 72⁰34'42.50"E

S.NO -101 S. No -102 Location No Latitude Longitude Location No Latitude Longitude AP 66/0 26°14'49.25"N 72°36'05.18" E AP 67/0 26°14'06.44" N 72°37'58.36"E

S. No -103 S. No -104 Location No Latitude Longitude Location No Latitude Longitude AP 68/0 26°13'48.8"N 72°38'35.0"E AP 69/0 26°13'8.11"N 72°40'13.84"E

S.NO -105 S. No -106 Location No Latitude Longitude Location No Latitude Longitude AP 70/0 26°12'21.6" N 72°42'47.00" E AP 71/0 26°11'16.22"N 72°45'26.36"E

S. No -107 S. No -108 Location No Latitude Longitude Location No Latitude Longitude AP 72/0 26°10'50.4"N 72°47'10.4"E AP 73/0 26°10'31.0"N 72°48'25.9"E

S.NO -109 S. No -110 Location No Latitude Longitude Location No Latitude Longitude AP 74/0 26°10'34.13"N 72°48'51.06"E AP 75/0 26°09'33.84"N 72°49'59.90"E

S. No -111 S. No -112 Location No Latitude Longitude Location No Latitude Longitude AP 76/0 26°09'09.5"N 72°50'59.5"E AP 77/0 26°08'26.0"N 72°51'51.1"E

S.NO -113 S. No -114 Location No Latitude Longitude Location No Latitude Longitude AP 78/0 26°08'20.78"N 72°51'54.81"E AP 79/0 26°06'58.06"N 72°53'36.11"E

S. No -115 S. No -116 Location No Latitude Longitude Location No Latitude Longitude AP 80/0 26°06'54.6"N 72°53'42.6"E AP 81/0 26°05'17.9"N 72°56'52.52"E

S.NO -117 S. No -118 Location No Latitude Longitude Location No Latitude Longitude AP 82/0 26°05'8.70"N 72°58'17.30"E AP 83/0 26°05'14.74"N 72°59'10.85"E

S. No -119 S. No -120 Location No Latitude Longitude Location No Latitude Longitude AP 84/0 26°05'20.84"N 72°59'14.9"E AP 85/0 26°05'20.66"N 72°59'43.79"E

S.NO -121 S. No -122 Location No Latitude Longitude Location No Latitude Longitude AP 86/0 26°05'24.28"N 72°59'49.90"E AP 87/0 26°05'16.77"N 73°00'26.93"E

S. No -123 S. No -124 Location No Latitude Longitude Location No Latitude Longitude AP 88/0 26°05'16.23"N 73°00'34.09"E AP 89/0 26°05'09.91"N 73°01'43.86"E

S.NO -125 S. No -126 Location No Latitude Longitude Location No Latitude Longitude AP 90/0 AP 91/0 (26°05'12.71"N, (26°05'18.30"N, 73°01'49.66"E 73°02'16.80"E

S. No -127 S. No -128 Location No Latitude Longitude Location No Latitude Longitude AP 92/0 26° 5'5.03"N 73° 2'55.10"E AP 93/0 26° 5'5.70"N 73° 3'1.30"E

S.NO -129 S. No -130 Location No Latitude Longitude Location No Latitude Longitude AP 94/0 26° 4'52.44"N 73° 3'22.34"E AP 95/0 26° 4'30.28"N 73° 3'31.30"E

S. No -131 S. No -132 Location No Latitude Longitude Location No Latitude Longitude AP 96/0 26° 4'27.53"N 73° 3'44.22"E AP 97/0 26° 4'25.94"N 73° 3'47.23"E

S.NO - S. No - Location No Latitude Longitude Location No Latitude Longitude

S. No - S. No - Location No Latitude Longitude Location No Latitude Longitude

ANNEXURE - 6

MISCELLANEOUS WORKING PHOTOGRAPHS

ICB -5 400 kV D/C Twin ACSR Moose Ramgarh – Akal Transmission Line Project

400 KV D/C TWIN MOOSE BHADLA TO JODHPUR TRANSMISSION LINE (ICB 6) Photographs of the few Angle points and during the different stages of works.

1.1 Testing of Air Quality 1.2 Testing of Noise

1.3 Testing of Soil Quality 1.4 Testing of water Quality

1.5 Storage of equipment and material 1.6 Storage of ACSR Conductor Drums.

1.7 Usage of Safety Net during erection work. 1.8 Usage of adequate water for Foundation curing work

1.9 Tree plantation week celebrated at Store areas. 1.10 Labour Shelter Camp with sufficient water for Bathing, Drinking, cooking.

1.11 Laying of Counterpoise Earthing in ground 1.12 Temporary drinking water and camp site for day time

1.13 Use of LPG used instead of firewood collected from 1.14 Access Path towards tower foundation inside nearby areas agricultural land

1.15 Storage of equipment and material 1.16 Temporary camp at tower erection site for tools etc.

1.17 PPE and toilets at the stores/staff quarters 1.18 Drinking water at stores/workshop and site office

400kV D/C Quad ACSR Moose Akal-Jodhpur Transmission Line Project

Annexure-7

Khichan Bird Area – 1. High Court Orders 2. Expert Committee decision 3. New proposed change in alignment

1. High Court Order Dated 05 October 2017

2. Expert Committee Decision

3. New proposed change in alignment

Detailed Survey Tower Schedule (AP 79/2 to AP 84 (Based on detailed survey by EPC Contractor)

Sr. No. Tower Tower Span Section Latitude Longitude Name of Ownership of Name of Remarks / No of No of No. Type (M.) Length Village Land (Private crops Crossings trees trees for (M.) or under Trimming Government) cutting 1 AP 79/2 DA+O 27° 07' 72° 26' Khichan Existing Tower Existing Tower 0 0 31.5058" N 31.9206" E 232 2 AP 79/0 DD+0 27° 07' 72° 26' Khichan Mohan Ram S/o Jowar, bajra, 0 0 37.3531" N 26.5960" E Jeevan Ram moong 353 353 Cart Track 3 AP DD+0 27° 07' 72° 26' Khichan Government 0 0 79B/0 48.5140" N 29.4277" E 325 11kV line, Road 4 79B/1 DA+3 27° 07' 72° 26' Khichan Government 0 0 54.4165" N 39.6041" E 392 717 5 AP80/0 DD+0 27° 08' 72° 26' Khichan Government 0 0 01.0960" N 51.4333" E 370 6 80/1 DA+0 27° 08' 72° 26' Khichan Hukuma Ram Jowar, bajra, 0 0 12.4059" N 55.3154" E s/o Kola Ram moong 305 675 7 AP81/0 DD+0 27° 08' 72° 26' Khichan Kanha Ram Jowar, bajra, 0 0 22.0492" N 58.6545" E Katariya moong 195 195 State Highway 8 AP 82/0 DD+0 27° 08' 72° 26' Khichan Panna Lal Jowar, bajra, 0 0 28.4517" N 58.8359" E Ranga moong 360 Cart Track 9 82/1 DA+0 27° 08' 72° 26' Khichan Daulal Sharma Jowar, bajra, 0 0 40.1170" N 59.0430" E moong 390 Road 10 AP82A/0 DD+0 750 27° 08' 72° 26' Khichan Hari Singh Raj Jowar, bajra, 0 0 52.8226" N 59.2990" E Purohit moong 265 LT line, Cart Track 11 82A/1 DA+6 27° 09' 72° 26' Khichan Government 0 0 00.4388" N 54.7685" E 240 11 kV line Sr. No. Tower Tower Span Section Latitude Longitude Name of Ownership of Name of Remarks / No of No of No. Type (M.) Length Village Land (Private crops Crossings trees trees for (M.) or under Trimming Government) cutting 12 AP DA+6 27° 09' 72° 26' Khichan Ramu Ram Jowar, bajra, 0 0 82A/2 07.3478" N 50.6534" E moong 760 255 Benching required 13 AP DA+6 27° 09' 72° 26' Khichan Government 0 0 82B/0 13.8089" N 46.9115" E 399 11 kV line 14 82B/1 DA+3 27° 09' 72° 26' Khichan Government Jowar, bajra, 0 0 22.4800" N 36.1105" E moong 366 Cart Track, 11 kV line 15 82B/2 DA+3 27° 09' 72° 26' Khichan Jeetu Singh Raj Jowar, bajra, 0 0 31.0210" N 25.3120" E Purohit moong 400 LT line, Cart 1165 Track 16 AP DB+0 27° 09' 72° 26' Khichan Government 0 0 82C/0 39.6916" N 14.5101" E 380 17 82C/1 DA+3 27° 09' 72° 26' Khichan Government 0 0 46.2010" N 02.7767" E 377 Cart Track, 11 757 kV line 18 AP83/0 DC+0 27° 09' 72° 25' Khichan Government 0 0 52.6161" N 51.2266" E 370 19 83/1 DA+3 27° 09' 72° 25' Khichan Mage Singh s/o Jowar, bajra, 0 0 54.0529" N 37.4660" E Vijay Singh moong 380 20 83/2 DA+0 27° 09' 72° 25' Khichan Government 0 0 55.3018" N 24.1092" E 303 1053 Cart Track 21 AP DC+0 27° 09' 72° 25' Khichan Government 0 0 83A/0 56.3036" N 13.2276" E 300 22 3/10 DA+0 27° 09' 72° 25' Khichan Private Jowar, bajra, 0 0 53.0279" N 02.9164" E moong 310 Sr. No. Tower Tower Span Section Latitude Longitude Name of Ownership of Name of Remarks / No of No of No. Type (M.) Length Village Land (Private crops Crossings trees trees for (M.) or under Trimming Government) cutting 23 83A/2 DA+0 27° 09' 72° 24' Khichan Private Jowar, bajra, 0 0 49.6811" N 52.2803" E moong 355 965 Cart Track 24 AP DD+0 27° 09' 72° 24' Khichan Bhavar Ram s/o Jowar, bajra, 0 0 83B/0 45.8533" N 40.2392" E Heera Ram moong 383 383 25 AP DD+0 27° 09' 72° 24' Khichan Late Shri Jowar, bajra, 0 0 83C/0 34.9178" N 33.8096" E Magraj Singh moong 388 388 26 AP DD+0 27° 09' 72° 24' Khichan Murlidhar Jowar, bajra, 0 0 83D/0 30.0021" N 20.9227" E Sharma s/o moong 190 Triloka Ram 190 27 AP 84/0 DC+0 27° 09' 72° 24' Khichan EXISTING Existing Tower 0 0 33.0461" N 15.1510" E TOWER

* For this revised transmission line route alignment, the route survey works have been completed as intimated by RVPNL. However, the data regarding soil, topography, contour, land cutting and filling required, distance from water body and distance from major roads, details of forest/non-forest, fruit/non-fruit trees being affected, land details will be collected by RVPNL/EPC contractor during construction. Any supplementary information, if required by ADB, will be supplied for this subproject by RVPNL to ADB for prior approval before contract award as well as during monitoring period.

ANNEXURE-8

EMP AND DEVIATIONS FROM EMP

A. Environment Management Plan (EMP) for RREITP Tranche 1 Project Potential Environmental Mitigation Action Monitoring Scope Standards/ Institutional Implementati Activity Impact Measurement/ Responsibility on Schedule Frequency Pre-construction 1. Physical Resources Equipment Release of chemicals and Chloro Fluorocarbons (CFCs), including Transformers other Exclusion of PCBs, RRVPN Detailed specifications harmful gases in Halons not used in transformers, project equipment CFCs stated in design. and design receptors (air, water, facilities or any other equipment. specifications tender documents - parameters. land). compliance with GoI Once. rules/regulations & (International Electro- Technical Commission) IEC standards 2. Environment Resources Location of land Impact to the existing Construction facilities should be placed at Water and Air Quality. Air quality RRVPN Detailed for sub- surface water suitable distance from water bodies, natural Standards and design/Plannin stations/transmi environment. flow paths, important ecological habitats Water Quality g Stage. ssion towers and residential areas. standards – Once. Sub-station Noise generation Sub-station location/designed to ensure Expected noise Noise control RRVPN Detailed location and Exposure to noise, noise will not be a nuisance to emissions based on regulations design/Plannin design. Nuisance to neighbouring neighbouring properties. sub-station design, Noise levels to be g Stage properties. noise levels. specified in tender documents Location of Impact on water bodies / Consideration of site location to avoid water Site location, line Consultation with RRVPN Part of transmission land/ residences. bodies or agricultural land/orchards as alignment selection local authorities and detailed towers and much as possible. (distance to dwelling, land owners, water project siting transmission water and/or quality standards- and survey line alignment Careful site selection to avoid existing agricultural land). Once. and design. and design. settlements. Interference Temporary flooding Appropriate siting of towers to avoid Site location and line Consultation with RRVPN Detailed with drainage hazards/loss of channel interference. alignment selection. local authorities and alignment patterns/Irrigati agricultural production. design engineers. survey and on channels. design. 3. Ecological Resources Encroachment Loss of precious Avoid encroachment by careful site and Floral and faunal Enumeration of ESC of RRVPN. Detailed into precious ecological values/ alignment selection and reconnaissance habitats loss. flora and fauna at design/Plannin ecological damage to precious before final siting of activities. site. g Stage. areas. species. 4. Human Environment Involuntary Loss of lands and Compensation paid for temporary/ Public complaints Rates paid as per ESC of RRVPN Prior to resettlement or structures. permanent loss of productive land. the Resettlement construction land acquisition. plan/Frame work for phase/Land the project. Acquisition.

Project Potential Environmental Mitigation Action Monitoring Scope Standards/ Institutional Implementati Activity Impact Measurement/ Responsibility on Schedule Frequency Encroachment Loss of Avoid siting new towers on Tower location and line Consultation with ESC of RRVPN Part of into farmland. agricultural/horticultural farmland/orchards wherever possible. alignment selection local authorities and detailed productivity. Statutory approvals for design engineers in alignment tree trimming /removal consonance with survey and from competent RRVPN. design. authority. Farmers compensated for any permanent Implementation of crop loss of productive fruit trees that need to be and tree compensation trimmed removed along RoW. (based on affected area) Location and Disturbance to adjacent Maintain adequate clearance, construction Transformers and Technical RRVPN Detailed design of Sub- lands and the people due of retaining structures, minimise cut and fill specifications and specification- Once design/Plannin station. to cut and fill operations. operations adjoining to the dwellings. compliance with Measure setback g Stage. setback distances (“as- distances to nearest built” diagrams). house structures – Once. Location of Exposure to safety Setback of dwellings to overhead line route Tower location and line Setback distances RRVPN Part of tower transmission related risks. designed in accordance with permitted alignment selection to nearest houses – siting survey towers and level of power frequency and the regulation with respect to nearest Once. and detailed transmission of supervision at sites. dwellings. alignment line alignment survey and and design. design. Explosions/Fire Hazards to life Design of sub-stations to include modern Sub-station design Tender document to RRVPN Part of fire control systems/firewalls. compliance with fire mention detailed detailed sub- prevention and control specifications – station layout Provision of fire fighting equipment to be codes. Once. and design located close to transformers, switchgear. /drawings Construction A. Physical Resources Site clearance Soil erosion and surface Construction near seasonal rivers, erosion Soil erosion Visual inspection Contractor Construction runoff and flood-prone areas should be restricted (Turbidity and through contract period to the non-rainy season. sedimentation) provisions Provision and maintenance of drains and under retention ponds. supervision of Treat clearing and filling areas against flow RRVPN acceleration and construction work should be carefully designed to minimise obstruction or destruction to natural drainage. Removal or Public inconvenience Advance notice to the public about the time Disruption to other Technical RRVPN and Throughout disturbance to and the duration of the utility disruption commercial and public specification Contractor construction

Project Potential Environmental Mitigation Action Monitoring Scope Standards/ Institutional Implementati Activity Impact Measurement/ Responsibility on Schedule Frequency other public activities / Public through contract period utilities Use of well trained and experienced complaints provisions machinery operators to reduce accidental damage to the public utilities

Restore the utilities immediately to overcome public inconvenience Equipment SF6 leakage during Record of all sub-station switchgear, Switchgear casings As per RRVPN Throughout layout and storage and erection of cylinders located within secure casings and Sub-station (International Contractor construction/er installation Switchgear bounding Electro-technical through contract ection period Commission) IEC provisions standards Once in year Surplus Runoff to cause water Any excess material will only be used as fill Location and amount Appropriate fill Contractor Construction earthwork/soil pollution, solid waste material offsite when the owner's (m3) of fill disposal disposal and through contract period disposal agreement has been obtained and with the Soil disposal locations dispersal locations provisions disposal site restored in a manner that and volume (m3) quarterly under prevents erosion and does not block any supervision of drainage path RRVPN B. Environment Resources Equipment Noise and vibrations Selection of construction techniques and Construction Minimal ground Contractor Construction layout and machinery to minimise ground disturbance. techniques and disturbance through contract period installation machinery Monthly provisions under supervision of ESC, RRVPN Sub-station Loss of soil Cutting and filling for the sub-station Borrow area siting CPCB norms Contractor Construction construction foundations obtained by creating or (area of site in m2 and Quarterly through contract period improving local drainage system. estimated volume in provisions m3) under supervision of ESC, RRVPN Water pollution Minimize construction activities involving Water Quality (pH, GOI water quality Contractor Construction significant ground disturbance (i.e. sub- BOD/COD, Suspended standards, Timing through contract period station land forming) during the monsoon solids, other) during of major provisions season. Provide drains and retention ponds major earthworks disturbance under if required. activities - prior to supervision of start of construction ESC, RRVPN activities. Provision of Contamination of Construction workforce facilities to include Amenities for Presence of proper Contractor Construction facilities for receptors (land, water, proper sanitation, water supply and waste Workforce facilities. sanitation, water through contract period

Project Potential Environmental Mitigation Action Monitoring Scope Standards/ Institutional Implementati Activity Impact Measurement/ Responsibility on Schedule Frequency construction air). disposal facilities. supply and waste provisions workers disposal facilities - under Once. supervision of RRVPN Mechanised Noise, vibration and Construction equipment to be well Construction Technical Contractor Construction construction operator safety, efficient maintained. techniques and specifications, through contract period operation. equipment - estimated safety regulations, provisions noise emissions and Noise control under Noise, vibration, Construction techniques and Machinery operating schedules. regulations- supervision of equipment wear and tear. selection to minimize ground disturbance. Quarterly. RRVPN. Proper maintenance and turning off plant not in use. Construction of Increase in airborne dust Existing roads and tracks used for Access roads, routes Use of established Contractor Construction roads for particles. construction and maintenance access to (length and width of roads wherever through contract period accessibility for the site wherever possible. access roads). possible. provisions sub stations Increased land under requirement for New access ways restricted to a minimum Access restricted to supervision of temporary accessibility. of single carriageway width. a minimum of single RRVPN. carriageway width. C. Ecological Resources Site clearance. Vegetation. Marking of vegetation to be removed prior Vegetation marking Clearance strictly Contractor Construction to clearance, and strict control on clearing and clearance control limited to target through contract period activities to ensure minimal clearance. (area in m2). vegetation –Once. provisions under supervision of RRVPN. Trimming/cuttin Loss of vegetation and Trees that can survive pruning to comply Species-specific tree Presence of target RRVPN, Construction g of trees within deforestation. should be pruned instead of cleared. retention as approved species in RoW Contractor period RoW. by statutory authorities following vegetation through contract Felled trees and other cleared or pruned (average and maximum clearance. provisions vegetation to be disposed of as authorised tree height at maturity, under by the statutory bodies. in metres). supervision of forest Disposal of cleared department vegetation as approved by the statutory authorities (area cleared in m2). Wood/ Loss of vegetation and Construction workers prohibited from Illegal wood /vegetation Complaints by local RRVPN, Construction vegetation deforestation harvesting wood in the project area during harvesting (area in m2, people or other Contractor period harvesting, their employment. number of incidents evidence of illegal through contract

Project Potential Environmental Mitigation Action Monitoring Scope Standards/ Institutional Implementati Activity Impact Measurement/ Responsibility on Schedule Frequency cut and fill reported). harvesting . provisions operations Effect on fauna Prevent work force from disturbing the Habitat loss. Complaints by local RRVPN. Construction flora, fauna including hunting of animals people or other period and fishing in water bodies. evidence of illegal hunting. Proper awareness programme regarding conservation of flora, fauna including ground vegetation to all workers. D. Human Environment Construction Noise nuisance to Minimize construction activities undertaken Timing of construction Construction as per RRVPN, Construction schedules for neighbouring properties. during the night and local communities (noise emissions, dBA). Scheduled timings Contractor period. sub-station. informed of the construction schedule. only. through contract provisions. Acquisition of Loss of agricultural/ Avoid faming/harvesting season for field Land area of Loss of crops-work RRVPN / Throughout cultivable lands. horticultural productivity. crops wherever possible for the project agriculture loss. in post-harvest Contractor construction activities. period but before through contract period. next crop – Once provisions. Avoid construction/stringing during fruits Construction Schedule per site. season. in non-fruiting season.

Ensure existing irrigation facilities are Usage of existing maintained in working condition. utilities.

Protect /preserve topsoil and reinstate after Status of facilities construction completed. (earthwork in m3). Repair /reinstate damaged bunds etc. after construction completed. Implementation of crop Compensation for temporary loss in compensation (amount agricultural production. paid, dates, etc.). Temporary use Losses to neighbouring Contract clauses specifying careful Contract clauses Incorporating good Contractor Construction of land. land uses/ values. construction practices. Design basis and construction through contract period. layout. management, provisions As much as possible existing access ways Reinstatement of land design engineering under will be used. status (area affected, practices. supervision of m2). Consultation with RRVPN Productive land will be reinstated following Implementation of affected parties completion of construction. tree/crop compensation immediately after (amount paid). completion of Compensation will be paid for loss of construction and production, if any. after the first harvest.

Project Potential Environmental Mitigation Action Monitoring Scope Standards/ Institutional Implementati Activity Impact Measurement/ Responsibility on Schedule Frequency Transportation Nuisance to the general Transport loading and unloading of Water, Air Quality and CPCB Emission Contractor Construction and storage of public. construction materials should not cause Noise (dBA). standards and through contract period. materials. nuisance to the people by way of noise, Water Quality provisions vibration and dust. standards - under Quarterly. supervision of Avoid storage of construction materials RRVPN. beside the road, around water bodies, residential or public sensitive locations.

Construction materials should be stored in covered areas to ensure protection from dust, emissions and such materials should be bundled in environment friendly and nuisance free manner. Temporary Loss of power supply to Advance notice to the public about the time Power disruption to Regular monitoring Contractor Throughout outage of the the local community and the duration of the utility disruption. houses and during the period of through contract the electricity when distribution lines commercial premises. strengthening the provisions construction crossing the new Restore the utilities immediately to conductors under period. transmission line are overcome public inconvenience. supervision of switched off. RRVPN Health and Injury and sickness of Contract provisions specifying minimum Contract clauses RRVPN and ADB Contractor Construction safety workers and members of requirements for construction camps. (number of incidents Health and safety through contract period. the public. and total lost-work days standards - provisions Contractor to prepare and implement a caused by injuries and Monthly. under health and safety plan and provide workers sickness). supervision of with required PPE. RRVPN.

Contractor to arrange for health and safety awareness programmes including on AIDS and sexually transmitted diseases (STD). Capacity Improve standards of Training of RRVPN Environment and Social Training schedules. Number of training RRVPN. Construction Building implementation and Cell. program - period. monitoring. Yearly. Operation and Maintenance Phase A. Physical Resources Operation of Leakage of SF6 gas. Record of all sub-station switchgear located Switchgear casings Ozone Depleting RRVPN. Throughout Switchgear. within secure casings. and Sub-station substances. the operation. bounding – Monthly. B. Environmental Resources Soil Erosion at Removal of top soil. Planting of buffer zone species suitable for Turbidity of water Visual inspection RRVPN. Throughout tower base of hilly terrain. (Visual Inspection). (Turbidity and the operations

Project Potential Environmental Mitigation Action Monitoring Scope Standards/ Institutional Implementati Activity Impact Measurement/ Responsibility on Schedule Frequency transmission sedimentation). line. Oil spillage. Contamination of Sub-station transformers located within Sub-station bounding Hazardous Waste RRVPN. Throughout land/nearby water bodies. secure and impervious bundled areas with (“as-built” diagrams)- (Management, the operation a storage capacity of at least 100% of the Monthly. handling, Trans- capacity of oil in transformers and boundary associated reserve tanks. Movement) Rules 2009. C. Ecological Recourses Trimming/cuttin Fire hazards Trees allowed growing up to a height within Species-specific tree Presence of target RRVPN, with Operation g of trees within the RoW by maintaining adequate retention as approved species in RoW forest period. RoW. clearance between the top of tree and the by statutory authorities following vegetation department. conductor as per the regulations. (average and maximum clearance. tree height at maturity, Trees that can survive pruning should be in metres) – Quarterly. pruned instead of cleared. D. Human Environment Maintenance of Exposure to Transmission line design to comply with the Required ground Ground clearance, RRVPN. Throughout Transmission electromagnetic limits of electromagnetic interference from clearance (metres) – standards on EMF. the operation. line. interference. overhead power lines. Quarterly. Sub-station Exposure to Sub-station design to comply with the limits Required vibrations Technical RRVPN Throughout maintenance. electromagnetic of electromagnetic interference within floor level, instrumentation – specifications the operation interference. area. on public complaint. Noise Nuisance to the Provision of noise barriers near sub-station Noise level. Noise level (dbA)- RRVPN Throughout generation. community around the sites. Once a year. the operation site. Electric shock. Death or injury to the Security fences around sub-station Proper maintenance of Periodic RRVPN Throughout workers and public. Establishment of warning signs. fences and sign maintenance. the operation boards. Careful design using appropriate Number of technologies to minimise hazards. Usage of appropriate programmes and technologies (lost work percent of staff/ days due to illness and workers covered. injuries). Training for Rising of awareness for Training of RRVPN personnel. Training schedules. Number of training RRVPN Operation Electric safety. electric safety. program-Yearly.

ICB-2: EMP Measures at Pooling Substation Bhadla & augmentation works at GSS Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Follow- Institutional Environmental reporting period (incl. Progress to Actions up required Responsibility Impact corrective) date Required Pre-construction Temporary use of Impact to the Selection of lands water and air quality Village areas are very NA RRVPNL land existing adhering to local laws far away environment and regulations Construction facilities should be placed at least 500 m away from water bodies, natural flow paths, important ecological habitats and residential areas Substation location Noise generation Substation designed to Expected noise Village areas are very Digging of NIL RRVPNL and design Exposure to ensure noise will not be emissions based on far away foundations noise, a nuisance. substation design, mostly in soil Nuisance to noise levels and no rock is neighbouring there properties Disturbance to Maintained adequate Setbacks to houses the adjacent clearance, construction and other structures lands and the of retaining structures, people due to cut minimise cut and fill and fill operations operations adjoining to the dwellings Location of Exposure to Setback of dwellings to Tower location and House/dwelling area NA NA NA RRVPNL transmission safety related overhead line route line alignment very far away towers and risks designed in accordance selection with transmission line with permitted level of respect to nearest alignment and power frequency and dwellings design the regulation of supervision at sites. Impact on water Consideration of site Site location, line All the water NA - - RRVPNL bodies / land/ location to avoid water alignment selection bodies/dwellings are residences bodies or agricultural (distance to more than 500 mtrs land as much as dwelling, water away from the possible. and/or agricultural substation land land) Careful site selection to avoid existing settlements Equipment Release of PCBs free substation Transformers and Equipment Design for Design RRVPNL specifications and chemicals and transformers or other specifications and substation submitted to approved design parameters harmful gases in project facilities or compliance with RRVPNL for review receptors (air, equipment. setback distances water, land) (“as-built” diagrams) Encroachment into Loss of precious Avoid encroachment by Floral and faunal No ecological areas - - RRVPNL precious ecological ecological values/ careful site and habitats loss are involved in

9

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Follow- Institutional Environmental reporting period (incl. Progress to Actions up required Responsibility Impact corrective) date Required areas damage to alignment selection and substation. precious species reconnaissance before final siting of activities. Minimise the RoW wherever possible Involuntary Loss of lands and Compensation paid for Public complaints NA NA - RRVPNL resettlement or structures temporary/ permanent land acquisition loss of productive land Encroachment into Loss of Use existing tower Tower location and NA NA NA RRVPNL farmland agricultural footings/towers line alignment productivity wherever possible selection

Design of Implementation of Avoid siting new towers crop and tree on farmland wherever compensation possible (based on affected area)

Statutory approvals for tree trimming /removal Farmers compensated for any permanent loss of productive land and trees that need to be trimmed or removed along RoW. Interference with Temporary Appropriate sighting of Site location and line Substation foundations 278 - RRVPNL drainage flooding towers to avoid channel alignment selection are spotted beyond the patterns/Irrigation hazards/loss of interference boundaries of water channels agricultural channel. production Appropriate provision or excess soil dug up from the foundations/trenches

Explosions/Fire Hazards to life Design of substations to Substation design Design of substation Design RRVPNL include modern fire compliance with fire equipment approved by approved control prevention and RRVPNL systems/firewalls. control codes

Provision of firefighting equipment to be located close to transformers, power generation equipment. Construction

10

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Follow- Institutional Environmental reporting period (incl. Progress to Actions up required Responsibility Impact corrective) date Required Removal or Public Advance notice to the Disruption to other Advance notice will be - RRVPNL disturbance to inconvenience public about the time commercial and published into the local other public utilities and the duration of the public activities / newspaper for electric utility disruption Public complaints utility shutdown.

Use of well trained and experienced machinery operators to reduce accidental damage to the public utilities

Restore the utilities immediately to overcome public inconvenience Acquisition of Loss of Avoid faming season Land area of No work locations in - - RRVPNL cultivable lands agricultural wherever possible for agriculture loss any farming area productivity the project activities. Usage of existing Top soil will be Ensure existing irrigation utilities restored during the facilities are maintained back filling work. in working condition Status of facilities (earthwork in m3) Protect /preserve topsoil and reinstate after Implementation of construction completed crop compensation (amount paid, dates, Repair /reinstate etc.) damaged bunds etc. after construction completed

Compensation for temporary loss in agricultural production. Temporary outage Loss of power Advance notice to the Power disruption to Advance notice will be - RRVPNL of the electricity supply to the public about the time houses and published into the local local community and the duration of the commercial newspaper for electric when distribution utility disruption premises of power utility shutdown. lines crossing the disruption new transmission Restore the utilities line are switched immediately to off overcome public inconvenience Equipment layout Noise and Selection of construction Construction Construction activity - RRVPNL and installation vibrations techniques and techniques and carried out during in machinery to minimise machinery day.

11

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Follow- Institutional Environmental reporting period (incl. Progress to Actions up required Responsibility Impact corrective) date Required ground disturbance. SF6 leakage Record of all substation Switchgear casings No equipment supplied during storage switchgear, storage and substation currently and erection of cylinders located within bounding Switchgear secure casings Substation Loss of soil Fill for the substation Borrow area sighting Top soil retained inside construction foundations obtained by (area of site in m2 substation creating or improving and estimated local drain system. volume in m3) Interference in Removal of silt and Drains choked with None drainage of rain trash choking the rain/water due to silt and waste water drainage of the and trash at site substation land Water pollution Construction activities Water Quality (pH, Testing to be done as involving significant BOD/COD, per EMP requirement ground disturbance (i.e. Suspended solids, in March 2016 substation land forming) other) during major not undertaken during earthworks the monsoon season. Construction Noise nuisance Minimize construction Timing of Villages located very - - RRVPNL/Alstom schedules to neighbouring activities undertaken construction (noise far away properties during the night and emissions, [dB(a)]) local communities informed of the construction schedule. Provision of Nuisance to Restrict construction Timing of No wild life area - - - RRVPNL/Alstom facilities for wildlife if the line work during the known Construction involved construction construction period of migration by workers crosses their any wildlife in the area migratory path Contamination of Construction workforce Amenities for Covered and fence wall - - RRVPNL/Alstom receptors (land, facilities to include Workforce facilities around the worker water, air) proper sanitation, water living area. Worker supply and waste have sufficient waste disposal facilities. water collection system and septic camp. Surplus Runoff to cause Excess fill from tower Location and Excess soil is dumped - - RRVPNL/Alstom earthwork/soil water pollution, foundation excavation to amount (m3) of fill inside the substation solid waste be reused on site or disposal and then used for fill disposal disposed of next to Soil disposal inside. roads or around houses, locations and in agreement with the volume (m3) local community or landowners.

Air Pollution Loose dust might Damping of dust by Soil stacking Lack of water leading - - RRVPNL/Alstom blow in the area sprinkling of water within locations, access to no spraying of water

12

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Follow- Institutional Environmental reporting period (incl. Progress to Actions up required Responsibility Impact corrective) date Required causing dusty the work area and stack roads, tower to minimize dust conditions the loose soil and locations, substation releasing in case of contain it with covers if site windy and dry weather. required. Wood/ vegetation Loss of Construction workers Illegal wood Firewood used, - - RRVPNL/Alstom harvesting, vegetation and prohibited from /vegetation however LPG cylinder cut and fill deforestation harvesting wood in the harvesting (area in will be provided to operations project area during their m2, number of Labor. employment. incidents reported)

Effect on fauna Prevent work force from Habitat loss Training program to be - - RRVPNL/Alstom disturbing the flora, conducted to create fauna including hunting awareness among the of animal and fishing in workers and staff to water bodies. conserve the flora and funa. Proper awareness programme regarding conservation of flora, fauna including ground vegetation to all drivers, operators and other workers. Site clearance Vegetation Marking of vegetation to Vegetation marking Vegetation land not - - RRVPNL/Alstom be removed prior to and clearance involved at the clearance, and strict control (area in m2) substation line control on clearing activities to ensure minimal clearance. Soil erosion and Construction near Soil erosion No soil erosion involve - - RRVPNL/Alstom surface runoff seasonal rivers, erosion during the construction and flood-prone areas (if activity of substation. any) should be restricted to the dry season.

Provision and maintenance of drains and retention ponds. Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimise obstruction or destruction to natural drainage.

13

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Follow- Institutional Environmental reporting period (incl. Progress to Actions up required Responsibility Impact corrective) date Required Mechanised Noise, vibration Construction equipment Construction Construction - - RRVPNL/Alstom construction and operator to be well maintained. equipment - equipment is regularly safety, efficient estimated noise maintained. Pollution operation emissions and under control certificate Proper maintenance and operating schedules to be made available Noise, vibration, turning off plant not in equipment wear use. and tear Construction of Increase in Existing roads and Access roads, Existing road/path only - - RRVPNL/Alstom roads for airborne dust tracks used for routes (length and used for the accessibility particles construction and width of access construction activity. maintenance access to roads) Increased land the site wherever Any new access path requirement for possible. used is only one temporary carriageway width for accessibility New access ways tractor, JCB machine restricted to a single and other machines. carriageway width within the Row. Transportation and Nuisance to the Transport loading and Water and Air Dropping material in - - RRVPNL/Alstom storage of general public unloading of Quality the road collected. materials construction materials should not cause nuisance to the people by way of noise, Construction material vibration and dust stored at high level ground level at Avoid storage of construction site. construction materials beside the road, around Construction material – water bodies, residential sand will be covered at or public sensitive top to avoid air locations pollution and stacked top soil to be also Construction materials covered at top to avoid should be stored in blowing during windy covered areas to ensure conditions protection from dust, emissions and such materials should be bundled in environment friendly and nuisance free manner Trimming/cutting of Fire hazards Trees allowed growing Species-specific tree NA NA - - trees within RoW up to a height within the retention as Loss of RoW by maintaining approved by vegetation and adequate clearance statutory authorities

14

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Follow- Institutional Environmental reporting period (incl. Progress to Actions up required Responsibility Impact corrective) date Required deforestation between the top of tree (average and and the conductor as maximum tree per the regulations. height at maturity, in metres) Trees that can survive trimming to comply with Disposal of cleared statutory distance vegetation as should be lopped and approved by the not felled statutory authorities (area cleared in m2) Felled trees and other cleared or pruned vegetation to be disposed of as authorised by the statutory bodies. Health and safety Injury and Contract provisions Contract clauses Conducting training - - RRVPNL/Alstom ADD PPE sickness of specifying minimum (number of incidents courses and meeting workers and requirements for and total lost-work for the workers on members of the construction camps from days caused by safety and public water bodies, reserved injuries and environmental hygienic areas etc. sickness) Providing personal safety devices for Contractor to prepare workers safety boots, and implement a health helmet, gloves, mask and safety plan and and protective cloths provide workers with required personal protective equipment (PPE) at site. Contractor to arrange for health and safety awareness programmes Nuisance to nearby Losses to Contract clauses Contract clauses Excavated material will - - RRVPNL/Alstom properties neighbouring specifying careful Design basis and be used for filling land uses/ values construction practices. layout ground itself.

Reinstatement of As much as possible land status (area existing access ways affected, m2) will be used. Implementation of Tree/Crop Productive land will be compensation reinstated following (amount paid) completion of construction

15

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Follow- Institutional Environmental reporting period (incl. Progress to Actions up required Responsibility Impact corrective) date Required Compensation will be paid for loss of production, if any. Operation and Maintenance Phase Electric shock Death or injury to Security fences around Proper maintenance the workers and substation of fences and sign public boards Establishment of warning signs Usage of appropriate Careful design using technologies (lost appropriate technologies work days due to to minimise hazards illness and injuries) Noise generation Nuisance to the Provision of noise Noise level community barriers near substation around the site sites Soil Erosion Removal of top Planting of buffer zone Turbidity of water soil species suitable for arid (Visual Inspection) climate. Maintenance of Exposure to Transmission line Required ground Transmission line electromagnetic design to comply with clearance (metres) interference the limits of electromagnetic interference from overhead power lines

Substation Exposure to Substation design to Required vibrations maintenance electromagnetic comply with the limits of level, interference electromagnetic instrumentation interference within floor area Oil spillage Contamination of Substation transformers Substation bounding land/nearby located within secure (“as-built” diagrams) water bodies and impervious bundled areas with a storage capacity of at least 110% of the capacity of oil in transformers and associated reserve tanks. Operation of Leakage of SF6 Record of all substation Switchgear casings Switchgear gas switchgear located and Substation within secure casings bounding

ICB-2: Environment Monitoring Plan and Status on Implementation for Pooling Substation Bhadla & augmentation works at

16

Bikaner GSS Environment Project stage Parameter Sampling Monitoring Regulatory Agency Agency Test Observations/Com Actions Further al s to be Location Frequency Standards responsible for responsible Results ments for follow-up component monitored for implementation for Compli required parameter supervision ance Spot check RVPNL Baseline using field data portable available – A. Pre- PM10, instruments Annexure 3 construction PM2.5, SO2, Boundary stage NOx, SPM, of One time National Air (Baseline CO (Visible substation quality development) dust) standards of CPCB [PM10 or PM2.5] Spot check Alstom using field PM10, portable PM , SO , Every one instruments 1.Air Quality B. Construction 2.5 2 Boundary NOx, SPM, month of Stage of CO construction National Air substation (Visible period quality dust) standards of CPCB [PM10 or PM2.5 Spot check using field PM , portable C. Operation 10 PM , SO , One time instruments Stage 2.5 2 Boundary NOx, SPM, during (Testing and of CO commissioni National Air Commissionin substation (Visible ng quality g) dust) standards of CPCB [PM10 or PM2.5 EC, RVPNL Baseline TSS, National data A. Pre- Nearest DO, water available – construction H well near BOD, P One time quality Annexure 3 stage (Baseline substation Oil and standards development) s 2.Water grease, of CPCB Quality Pb, EC, TSS, Alstom Nearest National water B. Construction DO, BOD, One time H well near quality Stage P Oil and during cable substation standards of grease, laying s CPCB Pb, C. Operation EC, TSS, Nearest One time National water Stage DO, BOD, well near during quality

17

Environment Project stage Parameter Sampling Monitoring Regulatory Agency Agency Test Observations/Com Actions Further al s to be Location Frequency Standards responsible for responsible Results ments for follow-up component monitored for implementation for Compli required parameter supervision ance PH Oil and substation commissioning standards of grease, s CPCB Pb, CPCB RVPNL Baseline A. Pre- Boundary standards data construction Noise level of One time for Noise available – stage (Baseline [dB(A)] substation and Annexure 3 development) 3.Noise/ vibrations Every one CPCB Alstom Vibration B. Construction Boundary Noise level month of standards for Stage of [dB(A)] construction Noise and substation period vibrations CPCB C. Operation Boundary One time Noise level standards for Stage of during [dB(A)] Noise and substation commissioning vibrations Visible RVPNL Baseline A. Pre- spills Hazardous data 1 location construction and/or soil Waste available – inside One time stage (Baseline staining, Manageme Annexure 3 substation development) Oil & nt rules grease Visible Alstom spills Hazardous B. Construction 1 location and/or soil Waste 4. Soil Stage inside One time staining, Manageme substation Oil & nt rules grease Visible spills One time Hazardous C. Operation 1 location and/or soil during Waste Stage inside staining, commissioni Manageme substation Oil & ng nt rules grease Operation Volumetric Substatio Online As per Alstom Alstom at Stage loss from n monitoring Approved Testing SF6 GIS equipmen by data Specificatio and equipment t, circuit loggers ns of Commissio breakers Equipment ning Stage

Abbreviations: SO2- -Sulphur Dioxide; NO2- - Nitrogen Dioxide; CO- Carbon Monoxide; EC – Electric Conductivity; Pb – Lead; PM2.5 - Particulate Matter <2.5; PM10 - Particulate Matter <10; TSPM- Total suspended Particulate Matter;

18

EC - Electrical Conductivity; DO - Dissolved Oxygen; TSS - Total Suspended Solids; SF6 – Sulphur Hexafluoride gas BOD - Biological Oxygen Demand; ORP – Oxidation Reduction Potential NAAQS - National Ambient Air Quality Standards specified by CPCB, GoI; NWQS - National Water Quality Standards specified by CPCB, GoI.

19

B. ICB -5: EMP Measures for 400 kV D/C Moose Ramgarh – Akal Transmission Line Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required Pre-construction 1. Physical Resources Temporary use of Impact to the Selection of lands water and air Inventory activity 278 Excess soil after No. RRVPNL land existing adhering to local quality of tree, crop and foundation environment laws and regulations asset in the area Kept on bund. Construction facilities that may affected should be placed at by project least 500 m away implementation from water bodies, such as natural flow paths, excavation and important ecological material habitats and transportation was residential areas undertaken before construction activities. Compensation is implemented to damage crop. 2. Environment Resources Substation location Noise Substation designed Expected noise Not Applicable and design generation to ensure noise will emissions Exposure to not be a nuisance. based on noise, substation Nuisance to design, neighbouring noise levels properties Disturbance to Maintained adequate Setbacks to the adjacent clearance, houses and lands and the construction of other structures people due to retaining structures, cut and fill minimise cut and fill operations operations adjoining to the dwellings Location of Exposure to Setback of dwellings Tower location Tower Location on 199.151 km 46 Mtr corridor NO. RRVPNL transmission towers safety related to overhead line and line 26 Meter either from center of and transmission risks route designed in alignment side is away from tower is line alignment and accordance with selection with House/dwelling maintained design permitted level of respect to area. Line is during survey power frequency and nearest minimum 500 Mtr work to avoid the regulation of dwellings away from such house & for 500

20

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required supervision at sites. dwelling area. mtr for reserve.

Impact on water Consideration of site Site location, All the water Foundation- 46 Mtr corridor NO. RRVPNL bodies / land/ location to avoid line alignment bodies/dwellings 278 from center of residences water bodies or selection are more than 500 E – 277 Nos tower is agricultural land as (distance to mtrs away from Stringing – maintained much as possible. dwelling, water the Line 98.520 km during survey and/or work to avoid Careful site selection agricultural house & for 500 to avoid existing land) mtr for reserve settlements Equipment Release of PCBs free substation Transformers Not Applicable specifications and chemicals and transformers or other and design parameters harmful gases project facilities or specifications in receptors equipment. and (air, water, compliance land) with setback distances (“as- built” diagrams) 3. Ecologic Resources Encroachment into Loss of Avoid encroachment Floral and Route has Entire line None RRVPNL precious ecological precious by careful site and faunal habitats been selected passing away areas ecological alignment selection loss in a manner to from flora & funa values/ damage and reconnaissance avoid such & forest area / to precious before final siting of encroachment NOC had taken species activities. s. before starting of Minimize the RoW No ecological project. areas are involved in TL 4. Human Environment Involuntary Loss of lands Compensation paid Public Compensation Land acquisition Crop RRVPNL resettlement and and structures for temporary/ complaints is not required for compensatio acquisition permanent loss of implemented work. n provide to productive land for the crop affected damaged. person. Compensation shall be paid for the

21

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required cultivated crop damaged as measured jointly by RVPNL, Patwari and EPC contractor site site incharge Encroachment into Loss of Use existing tower Tower location Compensation Foundation- 278 None RRVPNL farmland agricultural footings/towers and line alignment is Erection- 277 productivity wherever possible selection implemented Stringing – for the 98.520 Km crop/tree damaged RVPNL has during Discuss with disturbed the RRVPNL construction owner compensatio activity. n to the Design of Affected Avoid siting new Implementation of Avoided, farmers towers on farmland crop and tree though some wherever possible compensation are None (based on unavoidable affected area)

Statutory Farmers approvals for tree During compensated for any trimming /removal Foundation permanent loss of and erection productive land and work no trees trees that need to be are not trimmed or removed involved. along RoW. Interference with Temporary Appropriate sighting Site location All towers are 278 None RRVPNL drainage flooding of towers to avoid and line spotted beyond patterns/Irrigation hazards/loss of channel interference alignment the boundaries of channels agricultural selection water channel. production Appropriate provision or excess soil dug up from the foundations/trenches

22

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required

Explosions/Fire Hazards to life Design of Substation Not Applicable substations to design include modern fire compliance control with fire systems/firewalls. prevention and control codes Provision of firefighting equipment to be located close to transformers, power generation equipment. Construction A. Physical Resource Removal or Public Advance notice to Disruption to Advance notice Foundation- Nil Advance RRVPNL disturbance to other inconvenience the public about the other published into the 278 notice public utilities time and the duration commercial local newspaper Erection-277 published in of the utility and public for electric utility Stringing – daily disruption activities / shutdown. 98.520 Km newspaper. Public Use of well trained complaints and experienced machinery operators to reduce accidental damage to the public utilities

Restore the utilities immediately to overcome public inconvenience Acquisition of Loss of Avoid faming season Land area of EPC contractor Foundation– None None RRVPNL cultivable lands agricultural wherever possible agriculture loss has avoided the 278 Nos productivity for the project work for the E – 277 Nos activities. locations where Stringing- there is farming 98.520 Km season. Ensure existing Usage of Compensation irrigation facilities are existing utilities provided to land maintained in owner against the

23

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required working condition crop damaged.

Protect /preserve Status of Top soil is topsoil and reinstate facilities restored during after construction (earthwork in the backfilling completed m3) work.

Repair /reinstate Implementation damaged bunds etc. of crop after construction compensation completed (amount paid, dates, etc.) Compensation for temporary loss in agricultural production. Temporary outage Loss of power Advance notice to Power Advance notice Erection-– 277 None None RRVPNL of the electricity supply to the the public about the disruption to published into the Advance local community time and the duration houses and local newspaper notice when of the utility commercial for electric utility published into distribution lines disruption premises of shutdown. newspapers. crossing the power new Restore the utilities disruption transmission immediately to line are overcome public switched off inconvenience B. Environment Resources Equipment layout Noise and Selection of Construction Construction Foundation - None None RRVPNL and installation vibrations construction techniques and activity carried out 278 techniques and machinery during in day. Erection – 277 machinery to Report are still Stringing- minimise ground awaited. 98.520 km disturbance. SF6 leakage Record of all Switchgear Not Applicable during storage substation casings and and erection of switchgear, storage substation Switchgear cylinders located bounding within secure casings Substation Loss of soil Fill for the substation Borrow area construction foundations obtained sighting (area Not Applicable

24

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required by creating or of site in m2 improving local drain and estimated system. volume in m3) Interference in Removal of silt and Drains choked Not Applicable drainage of rain trash choking the with rain/water and waste drainage of the due to silt and water at site substation land trash Water pollution Construction Water Quality Not Applicable activities involving (pH, significant ground BOD/COD, disturbance (i.e. Suspended substation land solids, other) forming) not during major undertaken during earthworks the monsoon season. Construction Noise nuisance Minimize Timing of All Construction Foundation– None None RRVPNL/TPL schedules to neighboring construction construction activity carried out 278 Nos properties activities undertaken (noise during day time. Erection-277 during the night and emissions, (Report shall be Nos local communities [dB(a)]) submitted Stringing – informed of the September -16 98.520 Km construction still awaited) EPC schedule. contractor has avoided the work for the locations where there is farming season. Provision of facilities Nuisance to Restrict construction Timing of No wild life area Foundation- None None RRVPNL/TPL for construction wildlife if the work during the Construction involved through 278 workers line known period of the TL Erection- 277 construction migration by any Stringing- crosses their wildlife in the area 98.520 Km migratory path Contamination Construction Amenities for Covered and RRVPNL/TPL of receptors workforce facilities to Workforce fence wall around (land, water, include proper facilities the worker living air) sanitation, water area. Worker have supply and waste sufficient waste disposal facilities. water collection system and septic

25

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required camp. Surplus Runoff to cause Excess fill from tower Location and Excess soil is Foundation– None None RRVPNL/TPL earthwork/soil water pollution, foundation amount (m3) of dumped on the 278 solid waste excavation to be fill disposal bound of field and Erection-– 277 disposal reused on site or Soil disposal also dumped to Stringing – disposed of next to locations and path after 98.520 km roads or around volume (m3) discussing with houses, in the local persons agreement with the as per local community or requirement. landowners. Air Pollution Loose dust Damping of dust by Soil stacking Sprayed water to Foundation- None None RRVPNL/T might blow in sprinkling of water locations, minimize dust 278 PL the area within the work area access roads, releasing in case Erection-– 277 causing dusty and stack the loose tower locations, of windy and dry Stringing – conditions soil and contain it substation site weather. 98.520 km with covers if Excavated earth is required. covered. Wood/ vegetation Loss of Construction workers Illegal wood LPG cylinder Always None None RRVPNL/TPL harvesting, vegetation and prohibited from /vegetation provided to Labor. cut and fill deforestation harvesting wood in harvesting operations. the project area (area in m2, during their number of employment. incidents reported)

Effect on fauna Prevent work force Habitat loss Training program Foundation– None None RRVPNL/TPL from disturbing the conducted to 278 flora, fauna including create awareness Erection-– 277 hunting of animal among the Stringing – and fishing in water workers and staff 98.520 km bodies. to conserve the flora and fun. Proper awareness programme regarding conservation of flora, fauna including ground vegetation to all drivers, operators and other workers.

26

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required Site clearance Vegetation Marking of Vegetation Vegetation land Always None None RRVPNL/TPL vegetation to be marking and not involve removed prior to clearance through the TL. clearance, and strict control (area in control on clearing m2) activities to ensure minimal clearance. Soil erosion and Construction near Soil erosion No soil erosion Always None None RRVPNL/TPL surface runoff seasonal rivers, involved during erosion and flood- the construction prone areas (if any) activity of tower should be restricted foundation. to the dry season.

Provision and maintenance of drains and retention ponds. Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimise obstruction or destruction to natural drainage. Mechanized Noise, vibration Construction Construction Construction Always Work carried out None. RRVPNL/TPL construction and operator equipment to be well equipment - equipment is with the safety, efficient maintained. estimated regularly standards operation noise maintained. norms. emissions and Pollution under Noise, vibration, Proper maintenance operating control certificate equipment wear and turning off plant schedules available and tear not in use. Construction of Increase in Existing roads and Access roads, Existing road/path Foundation– Only existing None RRVPNL/TPL roads for airborne dust tracks used for routes (length only used for the 278 path is used for accessibility particles construction and and width of construction Erection-– 277 construction maintenance access access roads) activity. Stringing- activity to the site wherever 98.520 km possible.

27

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required Any new access Increased land New access ways path used is only requirement for restricted to a single one carriageway temporary carriageway width width for tractor, accessibility within the Row. JCB machine and other machines. C. Ecological Resources Transportation and Nuisance to the Transport loading Water and Air Dropping material Always None None RRVPNL/TPL storage of materials general public and unloading of Quality in the road construction collected. materials should not cause nuisance to the people by way of noise, vibration and dust

Avoid storage of Construction construction material stored at materials beside the high level ground road, around water level at bodies, residential or construction site. public sensitive locations Construction Construction waste removed materials should be from the stored in covered construction site areas to ensure after work protection from dust, completion. emissions and such Construction materials should be material – sand bundled in will be covered at environment friendly top to avoid air and nuisance free pollution near manner houses, and stacked top soil to be also covered at top to avoid blowing during windy conditions Trimming/cutting of Fire hazards Trees allowed Species- The tree and Always Compensation RRVPNL/TPL -

28

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required trees within RoW growing up to a specific tree bushes coming Paid to affected Loss of height within the retention as within the 26 farmers. vegetation and RoW by maintaining approved by Meter either side deforestation adequate clearance statutory of central line has between the top of authorities to be trimmed up tree and the (average and height required for conductor as per the maximum tree the clearance. regulations. height at maturity, in No vegetation filed Trees that can metres) involved during survive trimming to the construction comply with statutory Disposal of activity. distance should be cleared lopped and not felled vegetation as approved by Felled trees and the statutory other cleared or authorities pruned vegetation to (area cleared in be disposed of as m2) authorised by the statutory bodies. Health and safety Injury and Contract provisions Contract Conducting Always All work is None RRVPNL/TPL ADD PPE sickness of specifying minimum clauses training courses carried out with workers and requirements for (number of and meeting for PPE members of the construction camps incidents and the workers on public from water bodies, total lost-work safety and reserved areas etc. days caused by environmental injuries and hygienic Contractor to sickness) Providing personal prepare and safety devices for implement a health worker’s safety and safety plan and boots, helmet, provide workers with gloves, mask and required personal protective cloths protective equipment (PPE) at site. Contractor to arrange for health and safety awareness programmes Nuisance to nearby Losses to Contract clauses Contract Excavated Completely NA RRVPNL/TPL

29

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required properties neighbouring specifying careful clauses material is used land uses/ construction Design basis for filling ground values practices. and layout itself.

As much as possible Reinstatement Access roads existing access ways of land status always used for will be used. (area affected, construction m2) activity. Productive land will Implementation Compensation be reinstated of Tree/Crop paid against the following completion compensation crop damaged to of construction (amount paid) farmers.

Compensation will be paid for loss of production, if any. Operation and Maintenance Phase Electric shock Death or injury Security fences Proper Not Applicable RRVPN to the workers around substation maintenance of and public fences and Establishment of sign boards warning signs

Careful design using Usage of appropriate appropriate technologies to technologies minimise hazards (lost work days due to illness and injuries) Noise generation Nuisance to the Provision of noise Noise level Not Applicable community barriers near around the site substation sites Soil Erosion Removal of top Planting of buffer Turbidity of Not Applicable soil zone species water suitable for arid (Visual climate. Inspection) Maintenance of Exposure to Transmission line Required Transmission line electromagnetic design to comply ground interference with the limits of clearance electromagnetic (metres)

30

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting period Progress to Actions Follow-up Responsibility Impact (incl. corrective) date Required required interference from overhead power lines Substation Exposure to Substation design to Required Not Applicable maintenance electromagnetic comply with the limits vibrations level, interference of electromagnetic instrumentation interference within floor area Oil spillage Contamination Substation Substation Not Applicable of land/nearby transformers located bounding water bodies within secure and (“as-built” impervious bundled diagrams) areas with a storage capacity of at least 110% of the capacity of oil in transformers and associated reserve tanks. Operation of Leakage of SF6 Record of all Switchgear Not Applicable Switchgear gas substation casings and switchgear located Substation within secure bounding casings

C. ICB-5 Environment Monitoring Plan and Status on Implementation for 400 kV D/C Moose Ramgarh – Akal Transmission Line Environme Project stage Paramet Samplin Monitoring Regulatory Agency Agency Test Observations/Co Actions Further follow-up ntal ers to be g Frequency Standards responsible for respon Results mments for required component monitore Locatio for implementatio sible Complia d n parameter n for nce supervi sion Spot check RVPNL using field PM , 10 portable A. Pre- PM , 2.5 Boundar instruments 1.Air construction SO , 2 y of Quality stage NOx, One time substatio National Air (Baseline SPM, CO n quality development) (Visible standards of dust) CPCB [PM10 or

31

PM2.5] Spot check TPL RRVPNL Testing has been using field conducted and testing PM10, portable report of same has PM , instruments been submitted in B. 2.5 Boundar Every one SO , January ’2017. Construction 2 y of month of NOx, National Air Stage substatio construction SPM, CO quality n period (Visible standards of dust) CPCB [PM10 or PM2.5 Spot check RVPNL PM10, using field C. Operation PM , portable 2.5 Boundar One time Stage SO , instruments 2 y of during (Testing and NOx, National Air substatio commissioni Commissionin SPM, CO quality n ng g) (Visible standards of dust) CPCB PM10 or PM2.5 EC, TSS, RVPNL A. Pre- DO, Nearest National construction H BOD, P well near water quality stage One time Oil and substatio standards of (Baseline grease, ns CPCB development) Pb, EC, TSS, TPL Testing has been B. DO, Nearest National conducted and 2.Water H One time Construction BOD, P well near water quality testing report of Quality during cable Stage Oil and substatio standards of same has been laying grease, ns CPCB submitted in January Pb, ’2017. EC, TSS, RVPNL DO, Nearest One time National C. Operation BOD, PH well near during water quality Stage Oil and substatio commissioni standards of grease, ns ng CPCB Pb, A. Pre- CPCB RVPNL 3.Noise/ Boundar construction Noise standards Vibration y of stage level One time for Noise substatio (Baseline [dB(A)] and n development) vibrations

32

TPL Testing has been conduct d and CPCB B. Boundar Every one testing Noise standards Construction y of month of report of level for Noise Stage substatio construction same [dB(A)] and n period has vibrations been submitte d in January ’2017. CPCB RVPNL Boundar One time C. Operation Noise standards y of during Stage level for Noise substatio commissioni [dB(A)] and n ng vibrations Visible RVPNL A. Pre- spills 1 Hazardous construction and/or location Waste stage soil inside One time Managemen (Baseline staining, substatio t rules development) Oil & n grease TPL Testing has been conduct Visible ed and spills 1 4. Soil B. Hazardous testing and/or location Construction Waste report of soil inside One time Stage Managemen same staining, substatio t rules has Oil & n been grease submitte d in January ’2017. Visible 1 One time Hazardous RVPNL C. Operation spills location during Waste Stage and/or inside commissioni Managemen soil substatio ng t rules

33

staining, n Oil & grease Operation Volumetri Substati Online As per Not Applicable Stage c loss on monitoring by Approved SF6 from GIS equipme data loggers Specification equipmen nt, circuit s of t breakers Equipment

D: ICB 5: Deviations from RRETIP EMP (Construction) for 400 kV D/C Moose Ramgarh – Akal Transmission Line Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) Construction A. Physical Resources Site clearance Soil erosion and Construction near seasonal rivers, erosion and Soil erosion Visual inspection No None surface runoff flood-prone areas should be restricted to the (Turbidity and non-rainy season. sedimentation) Provision and maintenance of drains and retention ponds. Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimize obstruction or destruction to natural drainage. Removal or Public Advance notice to the public about the time Disruption to Technical No None disturbance to other inconvenience and the duration of the utility disruption other specification public utilities commercial and Use of well trained and experienced public activities machinery operators to reduce accidental / Public damage to the public utilities complaints

Restore the utilities immediately to overcome public inconvenience Surplus Runoff to cause Any excess material will only be used as fill Location and Appropriate fill No None earthwork/soil water pollution, material offsite when the owner's agreement amount (m3) of disposal and solid waste has been obtained and with the disposal site fill disposal dispersal locations disposal restored in a manner that prevents erosion Soil disposal quarterly and does not block any drainage path locations and volume (m3) B. Environment Resources Equipment layout Noise and Selection of construction techniques and Construction Minimal ground No None and installation vibrations machinery to minimise ground disturbance. techniques and disturbance machinery Monthly

34

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) Provision of facilities Contamination of Construction workforce facilities to include Amenities for Presence of proper Yes Open defecation for construction receptors (land, proper sanitation, water supply and waste Workforce sanitation, water workers water, air). disposal facilities. facilities. supply and waste disposal facilities - Once. Mechanised Noise, vibration Construction equipment to be well maintained. Construction Technical No None construction and operator techniques and specifications, safety, efficient equipment - safety regulations, operation. Construction techniques and Machinery estimated noise Noise control selection to minimize ground disturbance. emissions and regulations- Noise, vibration, Proper maintenance and turning off plant not operating Quarterly. equipment wear in use. schedules. and tear. Construction of roads Increase in Existing roads and tracks used for Access roads, Use of established No Existing village for accessibility for airborne dust construction and maintenance access to the routes (length roads wherever roads and cart sub stations particles. site wherever possible. and width of possible. tracks used. access roads). Increased land New access ways restricted to a minimum of Access restricted to requirement for single carriageway width. a minimum of temporary single carriageway accessibility. width. C. Ecological Resources Site clearance. Vegetation. Marking of vegetation to be removed prior to Vegetation Clearance strictly No None clearance, and strict control on clearing marking and limited to target activities to ensure minimal clearance. clearance vegetation –Once. control (area in m2). Trimming/cutting of Loss of Trees that can survive pruning to comply Species- Presence of target No None trees within RoW. vegetation and should be pruned instead of cleared. specific tree species in RoW deforestation. retention as following vegetation Felled trees and other cleared or pruned approved by clearance. vegetation to be disposed of as authorised by statutory the statutory bodies. authorities (average and maximum tree height at maturity, in metres). Disposal of cleared vegetation as

35

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) approved by the statutory authorities (area cleared in m2). Wood/ vegetation Loss of Construction workers prohibited from Illegal wood Complaints by local No None harvesting, vegetation and harvesting wood in the project area during /vegetation people or other cut and fill operations deforestation their employment. harvesting evidence of illegal (area in m2, harvesting. number of incidents reported). Effect on fauna Prevent work force from disturbing the flora, Habitat loss. Complaints by local fauna including hunting of animals and fishing people or other in water bodies. evidence of illegal hunting. Proper awareness programme regarding conservation of flora, fauna including ground vegetation to all workers. D. Human Environment Acquisition of Loss of Avoid faming/harvesting season for field crops Land area of Loss of crops-work No None cultivable lands. agricultural/ wherever possible for the project activities. agriculture loss. in post-harvest horticultural period but before productivity. Avoid construction/stringing during fruits next crop – Once season. Construction per site. Schedule in Ensure existing irrigation facilities are non-fruiting maintained in working condition. season.

Protect /preserve topsoil and reinstate after Usage of construction completed. existing utilities.

Repair /reinstate damaged bunds etc. after Status of construction completed. facilities (earthwork in Compensation for temporary loss in m3). agricultural production. Implementation of crop compensation (amount paid,

36

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) dates, etc.). Temporary use of Losses to Contract clauses specifying careful Contract Incorporating good No None land. neighbouring construction practices. clauses construction land uses/ Design basis management, values. As much as possible existing access ways will and layout. design engineering be used. Reinstatement practices. of land status Consultation with Productive land will be reinstated following (area affected, affected parties completion of construction. m2). immediately after Implementation completion of Compensation will be paid for loss of of tree/crop construction and production, if any. compensation after the first (amount paid). harvest. Transportation and Nuisance to the Transport loading and unloading of Water, Air CPCB Emission No None storage of materials. general public. construction materials should not cause Quality and standards and nuisance to the people by way of noise, Noise (dBA). Water Quality vibration and dust. standards - Quarterly. Avoid storage of construction materials beside the road, around water bodies, residential or public sensitive locations.

Construction materials should be stored in covered areas to ensure protection from dust, emissions and such materials should be bundled in environment friendly and nuisance free manner. Temporary outage of Loss of power Advance notice to the public about the time Power Regular monitoring No None the electricity supply to the and the duration of the utility disruption. disruption to during the period of local community houses and strengthening the when distribution Restore the utilities immediately to overcome commercial conductors lines crossing public inconvenience. premises. the new transmission line are switched off. Health and safety Injury and Contract provisions specifying minimum Contract RRVPN and ADB No None sickness of requirements for construction camps. clauses Health and safety workers and (number of standards - members of the Contractor to prepare and implement a health incidents and Monthly. public. and safety plan and provide workers with total lost-work required PPE. days caused by

37

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) injuries and Contractor to arrange for health and safety sickness). awareness programmes including on AIDS and sexually transmitted diseases (STD). Capacity Building Improve Training of RRVPN Environment and Social Training Number of training No None standards of Cell. schedules. program - implementation Yearly. and monitoring.

38

E. ICB-6: EMP Measures for 400 kV D/C Moose Bhadla – Jodhpur (LILO at Merta) Transmission Line

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) Pre-construction 1. Physical Resources Temporary use of Impact to the Selection of lands water and air Route has been Foundation-547 Excess soil after No. RRVPNL land existing adhering to local quality selected in a foundation kept environment laws and regulations manner to avoid on bund of field, Construction facilities the interference same is regular should be placed at of such practice at site. least 500 m away amenities. from water bodies, natural flow paths, important ecological habitats and residential areas 2. Environment Resources Substation location Noise Substation designed Expected noise Not Applicable and design generation to ensure noise will emissions Exposure to not be a nuisance. based on noise, substation Nuisance to design, neighbouring noise levels properties Disturbance to Maintained adequate Setbacks to the adjacent clearance, houses and lands and the construction of other structures people due to retaining structures, cut and fill minimise cut and fill operations operations adjoining to the dwellings Location of Exposure to Setback of dwellings Tower location Tower Location 199.221 km 46 Mtr corridor NO. RRVPNL transmission towers safety related to overhead line and line on 26 Meter from center of and transmission risks route designed in alignment either side is tower is line alignment and accordance with selection with away from maintained design permitted level of respect to House/dwelling during survey power frequency and nearest area. Line is work to avoid the regulation of dwellings minimum 500 house & for 500 supervision at sites. Mtr away from mt for reserve. such dwelling area.

39

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) Impact on water Consideration of site Site location, All the water Foundation-547 46 Mtr corridor NO. RRVPNL bodies / land/ location to avoid line alignment bodies/dwellings Erection-– 547 from center of residences water bodies or selection are more than Nos tower is agricultural land as (distance to 500 mtrs away Stringing – maintained much as possible. dwelling, water from the Line 146.008 km during survey and/or work to avoid Careful site selection agricultural house & for 500 to avoid existing land) mtr for reserve settlements Equipment Release of PCBs free substation Transformers specifications and chemicals and transformers or other and Not Applicable design parameters harmful gases project facilities or specifications in receptors equipment. and (air, water, compliance land) with setback distances (“as- built” diagrams)

3. Ecologic Resources Encroachment into Loss of Avoid encroachment Floral and Route has been selected in a Entire line None RRVPNL precious ecological precious by careful site and faunal habitats manner to avoid such passing away areas ecological alignment selection loss encroachments. from flora & funa values/ damage and reconnaissance No ecological areas are & forest area / to precious before final siting of involved in TL NOC had taken species activities. before starting of Minimize the RoW project.

4. Human Environment Involuntary Loss of lands Compensation paid Public Compensation Land acquisition Crop RRVPNL resettlement and and structures for temporary/ complaints is implemented not required for compensatio acquisition permanent loss of for the crop work. n provide to productive land damaged. affected Compensation person. shall be paid for the cultivated crop damaged as measured jointly by RVPNL, Patwari and Tata project

40

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) site incharge Encroachment into Loss of Use existing tower Tower location Compensation Foundation- 547 None RRVPNL farmland agricultural footings/towers and line alignment is Erection- 547 productivity wherever possible selection implemented Stringing – for the 146.008 Km crop/tree damaged Discuss with during owner construction activity. Design of Avoid siting new Implementation of Avoided, RVPNL has RRVPNL towers on farmland crop and tree though some distributed wherever possible compensation are the (based on unavoidable compensatio affected area) n to the Affected farmers Farmers Statutory During Complete compensated for any approvals for tree Foundation removal of permanent loss of trimming /removal and erection stubs to productive land and work no trees suitable trees that need to be are not depths trimmed or removed involved. (undergroun along RoW. d concrete and steel legs) to ensure no loss to farmer where towers are dismantled/s hifted due to court orders. Interference with Temporary Appropriate sighting Site location Towers are 547 None RRVPNL drainage flooding of towers to avoid and line being patterns/Irrigation hazards/loss of channel interference alignment selected/spotted channels agricultural selection in a manner to production Appropriate provision avoid such or excess soil dug up channels

41

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) from the foundations/trenches Explosions/Fire Hazards to life Design of Substation Not Applicable substations to design include modern fire compliance control with fire systems/firewalls. prevention and control codes Provision of firefighting equipment to be located close to transformers, power generation equipment. Construction A. Physical Resource Removal or Public Advance notice to Disruption to Advance Foundation- 547 Nil Advance RRVPNL disturbance to other inconvenience the public about the other information Erection-547 notice public utilities time and the duration commercial published into Stringing – published in of the utility and public the local 146.008 Km daily disruption activities / newspaper for newspaper. Public electric utility complaints shutdown Use of well trained and experienced machinery operators to reduce accidental damage to the public utilities

Restore the utilities immediately to overcome public inconvenience Acquisition of Loss of Avoid faming season Land area of EPC contractor Foundation- 547 None None RRVPNL cultivable lands agricultural wherever possible agriculture loss has avoided the Erection-547 productivity for the project work for the Stringing – activities. locations where 146.008 Km there is farming season.

42

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) Ensure existing Usage of Compensation irrigation facilities are existing utilities provided to land maintained in owner against working condition the crop damaged.

Protect /preserve Status of Top soil is topsoil and reinstate facilities restored during after construction (earthwork in the back-filling completed m3) work.

Repair /reinstate Implementation damaged bunds etc. of crop after construction compensation completed (amount paid, dates, etc.) Compensation for temporary loss in agricultural production. Temporary outage Loss of power Advance notice to Power Advance notice Erection-– 547 None None RRVPNL of the electricity supply to the the public about the disruption to published into Advance notice local community time and the duration houses and the local published into when of the utility commercial newspaper for newspapers. distribution lines disruption premises of electric utility crossing the power shutdown. new Restore the utilities disruption transmission immediately to line are overcome public switched off inconvenience B. Environment Resources Equipment layout Noise and Selection of Construction Construction Foundation- 547 None None RRVPNL and installation vibrations construction techniques and activity carried Erection-547 techniques and machinery out during in Stringing – machinery to day. Report are 146.008 Km minimise ground still awaited. disturbance. SF6 leakage Record of all Switchgear Not Applicable during storage substation casings and and erection of switchgear, storage substation

43

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) Switchgear cylinders located bounding within secure casings Substation Loss of soil Fill for the substation Borrow area construction foundations obtained sighting (area by creating or of site in m2 Not Applicable improving local drain and estimated system. volume in m3) Interference in Removal of silt and Drains choked drainage of rain trash choking the with rain/water Not Applicable and waste drainage of the due to silt and water at site substation land trash Water pollution Construction Water Quality Not Applicable activities involving (pH, significant ground BOD/COD, disturbance (i.e. Suspended substation land solids, other) forming) not during major undertaken during earthworks the monsoon season. Construction Noise nuisance Minimize Timing of All Construction Foundation- 547 None None RRVPNL/TPL schedules to neighboring construction construction activity carried Erection-547 properties activities undertaken (noise out during day Stringing – during the night and emissions, time. (Report 146.008 Km local communities [dB(a)]) shall be informed of the submitted construction September -16 schedule. still awaited) EPC contractor has avoided the work for the locations where there is farming season. Provision of facilities Nuisance to Restrict construction Timing of No wild life area Foundation- 547 None None RRVPNL/TPL for construction wildlife if the work during the Construction involved through Erection-547 workers line known period of On Oct 5, the TL*. Stringing – construction migration by any 2017, High However 146.008 Km crosses their wildlife in the area court ordered Petition DB Civil Towers

44

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) migratory path shifting of Writ Petition No. between towers near 14676/2016 AP79/2 to AP Khichan Bird ordered shifting 84/0 to be Area of towers due to dismantled and (Annexure 7) Demoiselle shifted outward Cranes at to new Khichan Area. alignment RVPN/TPL to proposed in conduct detailed Annexure 7 survey and seek Court/GOR approval. ADB needs to be informed before start of construction. Contamination Construction Amenities for All workmen are Always Nil Nil RRVPNL/TPL of receptors workforce facilities to Workforce provided clean (land, water, include proper facilities water for air) sanitation, water drinking/cooking/ supply and waste bathing. disposal facilities. Proper rented/tent accommodation are provided for their shelter Proper sanitation facilities are provided for all the workmen. Surplus Runoff to cause Excess fill from tower Location and Excess soil is Foundation- 547 None None RRVPNL/TPL earthwork/soil water pollution, foundation amount (m3) of dumped on the Erection-547 solid waste excavation to be fill disposal bound of field Stringing – disposal reused on site or and also 146.008 Km disposed of next to Soil disposal dumped to path roads or around locations and after discussing houses, in volume (m3) with the local agreement with the persons as per local community or requirement.

45

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) landowners. Air Pollution Loose dust Damping of dust by Soil stacking Sprayed water Foundation- 547 None. None RRVPNL/T might blow in sprinkling of water locations, to minimize dust Erection-547 PL the area within the work area access roads, releasing in case Stringing – causing dusty and stack the loose tower locations, of windy and dry 146.008 Km conditions soil and contain it substation site weather. with covers if Excavated earth required. is covered. Wood/ vegetation Loss of Construction workers Illegal wood LPG cylinder Always None None RRVPNL/TPL harvesting, vegetation and prohibited from /vegetation provided to cut and fill deforestation harvesting wood in harvesting Labor for operations. the project area (area in m2, cooking during their number of purpose. employment. incidents reported) Effect on fauna Prevent work force Habitat loss Training Foundation- 547 None None RRVPNL/TPL from disturbing the program Erection-547 flora, fauna including conducted to Stringing – hunting of animal create 146.008 Km and fishing in water awareness bodies. among the workers and Proper awareness staff to conserve programme the flora and fun. regarding conservation of flora, fauna including ground vegetation to all drivers, operators and other workers. Site clearance Vegetation Marking of Vegetation Vegetation land Always None None RRVPNL/TPL vegetation to be marking and not involve removed prior to clearance through the TL. clearance, and strict control (area in control on clearing m2) activities to ensure minimal clearance. Soil erosion and Construction near Soil erosion No soil erosion Always None None RRVPNL/TPL surface runoff seasonal rivers, involved during erosion and flood- the construction

46

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) prone areas (if any) activity of tower should be restricted foundation. to the dry season.

Provision and maintenance of drains and retention ponds.

Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimise obstruction or destruction to natural drainage. Mechanized Noise, vibration Construction Construction Construction Always Work carried out None. RRVPNL/TPL construction and operator equipment to be well equipment - equipment is with the safety, efficient maintained. estimated regularly standards operation noise maintained. norms. emissions and Pollution under Noise, vibration, Proper maintenance operating control equipment wear and turning off plant schedules certificate and tear not in use. available Construction of Increase in Existing roads and Access roads, Existing Foundation- 547 Only existing None RRVPNL/TPL roads for airborne dust tracks used for routes (length road/path only Erection-547 path is used for accessibility particles construction and and width of used for the Stringing – construction maintenance access access roads) construction 146.008 Km activity to the site wherever activity. possible.

Increased land New access ways Any new access requirement for restricted to a single path used is only temporary carriageway width one carriageway accessibility within the Row. width for tractor, JCB machine and other machines.

47

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) C. Ecological Resources Transportation and Nuisance to the Transport loading Water and Air Dropping Always None None RRVPNL/TPL storage of materials general public and unloading of Quality material in the construction road collected. materials should not cause nuisance to the people by way of noise, vibration and dust

Avoid storage of Construction construction material stored materials beside the at high level road, around water ground level at bodies, residential or construction site. public sensitive locations Construction Construction waste removed materials should be from the stored in covered construction site areas to ensure after work protection from dust, completion. emissions and such Construction materials should be material – sand bundled in will be covered environment friendly at top to avoid and nuisance free air pollution near manner houses, and stacked top soil to be also covered at top to avoid blowing during windy conditions Trimming/cutting of Fire hazards Trees allowed Species- The tree and Always Compensation RRVPNL/TPL - trees within RoW growing up to a specific tree bushes coming Paid to affected Loss of height within the retention as within the 26 farmers. vegetation and RoW by maintaining approved by Meter either side deforestation adequate clearance statutory of central line

48

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) between the top of authorities has to be tree and the (average and trimmed up conductor as per the maximum tree height required regulations. height at for the maturity, in clearance. Trees that can metres) survive trimming to No vegetation comply with statutory Disposal of field involved distance should be cleared during the lopped and not felled vegetation as construction approved by activity. Felled trees and the statutory other cleared or authorities pruned vegetation to (area cleared in be disposed of as m2) authorised by the statutory bodies. Health and safety Injury and Contract provisions Contract Conducting Always All work is None RRVPNL/TPL ADD PPE sickness of specifying minimum clauses training courses carried out with workers and requirements for (number of and meeting for PPE members of the construction camps incidents and the workers on public from water bodies, total lost-work safety and reserved areas etc. days caused by environmental injuries and hygienic sickness) Contractor to Providing prepare and personal safety implement a health devices for and safety plan and worker’s safety provide workers with boots, helmet, required personal gloves, mask protective equipment and protective (PPE) at site. cloths Contractor to arrange for health and safety awareness programmes Nuisance to nearby Losses to Contract clauses Contract Excavated Completely NA RRVPNL/TPL properties neighbouring specifying careful clauses material is used land uses/ construction Design basis for filling ground

49

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) values practices. and layout itself.

As much as possible Reinstatement Access roads existing access ways of land status always used for will be used. (area affected, construction m2) activity. Productive land will Implementation Compensation be reinstated of Tree/Crop paid against the following completion compensation crop damaged to of construction (amount paid) farmers.

Compensation will be paid for loss of production, if any. Operation and Maintenance Phase Electric shock Death or injury Security fences Proper Not Applicable RRVPN to the workers around substation maintenance of and public fences and Establishment of sign boards warning signs Usage of Careful design using appropriate appropriate technologies technologies to (lost minimise hazards work days due to illness and injuries) Noise generation Nuisance to the Provision of noise Noise level Not Applicable community barriers near around the site substation sites Soil Erosion Removal of top Planting of buffer Turbidity of Not Applicable soil zone species water suitable for arid (Visual climate. Inspection) Maintenance of Exposure to Transmission line Required Transmission line electromagnetic design to comply ground interference with the limits of clearance electromagnetic (metres) interference from overhead power

50

Project Activity Potential Mitigation Action Standards Actions during Cumulative Corrective Further Institutional Environmental reporting Progress to Actions Follow-up Responsibility Impact period (incl. date Required required corrective) lines Substation Exposure to Substation design to Required Not Applicable maintenance electromagnetic comply with the limits vibrations level, interference of electromagnetic instrumentation interference within floor area Oil spillage Contamination Substation Substation Not Applicable of land/nearby transformers located bounding water bodies within secure and (“as-built” impervious bundled diagrams) areas with a storage capacity of at least 110% of the capacity of oil in transformers and associated reserve tanks. Operation of Leakage of SF6 Record of all Switchgear Not Applicable Switchgear gas substation casings and switchgear located Substation within secure bounding casings

F: ICB-6: Environment Monitoring Plan and Status on Implementation for 400 kV D/C Moose Bhadla – Jodhpur (LILO at Merta) Transmission Line Environme Project stage Paramet Samplin Monitoring Regulatory Agency Agency Test Observations/Co Actions Further follow-up ntal ers to be g Frequency Standards responsible for respon Results mments for required component monitore Locatio for implementatio sible Complia d n parameter n for nce supervi sion PM10, Spot check RVPNL A. Pre- PM , using field 2.5 Boundar 1.Air construction SO , portable 2 y of Quality stage NOx, One time instruments substatio (Baseline SPM, CO n development) (Visible National Air dust) quality

51

standards of CPCB [PM10 or PM2.5] Spot check TPL RVPNL Testing using field has been PM10, portable conducted PM , instruments and B. 2.5 Boundar Every one SO , testing Construction 2 y of month of NOx, National Air report of Stage substatio construction SPM, CO quality same has n period (Visible standards of been dust) CPCB submitted [PM10 or in January PM2.5 ’2017. Spot check PM10, using field C. Operation PM , portable RVPNL 2.5 Boundar One time Stage SO , instruments. 2 y of during (Testing and NOx, National Air substatio commissioni Commissionin SPM, CO quality n ng g) (Visible standards of dust) CPCB PM10 or PM2.5 EC, TSS, RVPNL A. Pre- DO, Nearest National construction H BOD, P well near water quality stage One time Oil and substatio standards of (Baseline grease, ns CPCB development) Pb, EC, TSS, TPL Testing has been B. DO, Nearest National conducted and 2.Water H One time Construction BOD, P well near water quality testing report of Quality during cable Stage Oil and substatio standards of same has been laying grease, ns CPCB submitted in January Pb, ’2017. EC, TSS, RVPNL DO, Nearest One time National C. Operation BOD, PH well near during water quality Stage Oil and substatio commissioni standards of grease, ns ng CPCB Pb, 3.Noise/ A. Pre- Noise Boundar CPCB RVPNL One time Vibration construction level y of standards

52

stage [dB(A)] substatio for Noise (Baseline n and development) vibrations TPL Testing has been conduct ed and CPCB B. Boundar Every one testing Noise standards Construction y of month of report of level for Noise Stage substatio construction same [dB(A)] and n period has vibrations been submitte d in January ’2017. CPCB RVPNL Boundar One time C. Operation Noise standards y of during Stage level for Noise substatio commissioni [dB(A)] and n ng vibrations Visible RVPNL A. Pre- spills 1 Hazardous construction and/or location Waste stage soil inside One time Managemen (Baseline staining, substatio t rules development) Oil & n grease TPL Testing has been conduct 4. Soil Visible ed and spills 1 B. Hazardous testing and/or location Construction Waste report of soil inside One time Stage Managemen same staining, substatio t rules has Oil & n been grease submitte d in January ’2017. C. Operation Visible 1 One time Hazardous

53

Stage spills location during Waste and/or inside commissioni Managemen RVPNL soil substatio ng t rules staining, n Oil & grease Operation Volumetri Substati Online As per Not Applicable Stage c loss on monitoring by Approved SF6 from GIS equipme data loggers Specification equipmen nt, circuit s of t breakers Equipment

G: ICB-6: Deviations from RRETIP EMP (Construction) for 400 kV D/C Moose Bhadla – Jodhpur (LILO at Merta) Transmission Line Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) Construction E. Physical Resources Site clearance Soil erosion and Construction near seasonal rivers, erosion and Soil erosion Visual inspection No None surface runoff flood-prone areas should be restricted to the (Turbidity and non-rainy season. sedimentation) Provision and maintenance of drains and retention ponds. Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimize obstruction or destruction to natural drainage. Removal or Public Advance notice to the public about the time Disruption to Technical No None disturbance to other inconvenience and the duration of the utility disruption other specification public utilities commercial and Use of well trained and experienced public activities machinery operators to reduce accidental / Public damage to the public utilities complaints

Restore the utilities immediately to overcome public inconvenience Surplus Runoff to cause Any excess material will only be used as fill Location and Appropriate fill No None earthwork/soil water pollution, material offsite when the owner's agreement amount (m3) of disposal and solid waste has been obtained and with the disposal site fill disposal dispersal locations disposal restored in a manner that prevents erosion Soil disposal quarterly and does not block any drainage path locations and volume (m3)

54

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) F. Environment Resources Equipment layout Noise and Selection of construction techniques and Construction Minimal ground No None and installation vibrations machinery to minimise ground disturbance. techniques and disturbance machinery Monthly Provision of facilities Contamination of Construction workforce facilities to include Amenities for Presence of proper Yes Open defecation for construction receptors (land, proper sanitation, water supply and waste Workforce sanitation, water workers water, air). disposal facilities. facilities. supply and waste disposal facilities - Once. Mechanised Noise, vibration Construction equipment to be well maintained. Construction Technical No None construction and operator techniques and specifications, safety, efficient equipment - safety regulations, operation. Construction techniques and Machinery estimated noise Noise control selection to minimize ground disturbance. emissions and regulations- Noise, vibration, Proper maintenance and turning off plant not operating Quarterly. equipment wear in use. schedules. and tear. Construction of roads Increase in Existing roads and tracks used for Access roads, Use of established No Existing village for accessibility for airborne dust construction and maintenance access to the routes (length roads wherever roads and cart sub stations particles. site wherever possible. and width of possible. tracks used. access roads). Increased land New access ways restricted to a minimum of Access restricted to requirement for single carriageway width. a minimum of temporary single carriageway accessibility. width. G. Ecological Resources Site clearance. Vegetation. Marking of vegetation to be removed prior to Vegetation Clearance strictly No None clearance, and strict control on clearing marking and limited to target activities to ensure minimal clearance. clearance vegetation –Once. control (area in m2). Trimming/cutting of Loss of Trees that can survive pruning to comply Species- Presence of target No None trees within RoW. vegetation and should be pruned instead of cleared. specific tree species in RoW deforestation. retention as following vegetation Felled trees and other cleared or pruned approved by clearance. vegetation to be disposed of as authorised by statutory the statutory bodies. authorities (average and maximum tree height at maturity, in

55

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) metres). Disposal of cleared vegetation as approved by the statutory authorities (area cleared in m2). Wood/ vegetation Loss of Construction workers prohibited from Illegal wood Complaints by local No None harvesting, vegetation and harvesting wood in the project area during /vegetation people or other cut and fill operations deforestation their employment. harvesting evidence of illegal (area in m2, harvesting. number of incidents reported). Effect on fauna Prevent work force from disturbing the flora, Habitat loss. Complaints by local fauna including hunting of animals and fishing people or other in water bodies. evidence of illegal hunting. Proper awareness programme regarding conservation of flora, fauna including ground vegetation to all workers. H. Human Environment Acquisition of Loss of Avoid faming/harvesting season for field crops Land area of Loss of crops-work No None cultivable lands. agricultural/ wherever possible for the project activities. agriculture loss. in post-harvest horticultural period but before productivity. Avoid construction/stringing during fruits Construction next crop – Once season. Schedule in per site. non-fruiting season.

Ensure existing irrigation facilities are Usage of maintained in working condition. existing utilities.

Status of Protect /preserve topsoil and reinstate after facilities construction completed. (earthwork in Repair /reinstate damaged bunds etc. after m3). construction completed. Implementation

56

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) Compensation for temporary loss in of crop agricultural production. compensation (amount paid, dates, etc.). Temporary use of Losses to Contract clauses specifying careful Contract Incorporating good No None land. neighbouring construction practices. clauses construction land uses/ management, values. As much as possible existing access ways will Design basis design, engineering be used. and layout. practices. Consultation with Productive land will be reinstated following Reinstatement affected parties completion of construction. of land status immediately after (area affected, completion of m2). construction and Compensation will be paid for loss of Implementation after the first production, if any. of tree/crop harvest. compensation (amount paid). Transportation and Nuisance to the Transport loading and unloading of Water, Air CPCB Emission No None storage of materials. general public. construction materials should not cause Quality and standards and nuisance to the people by way of noise, Noise (dBA). Water Quality vibration and dust. standards - Quarterly. Avoid storage of construction materials beside the road, around water bodies, residential or public sensitive locations.

Construction materials should be stored in covered areas to ensure protection from dust, emissions and such materials should be bundled in environment friendly and nuisance free manner. Temporary outage of Loss of power Advance notice to the public about the time Power Regular monitoring No None the electricity supply to the and the duration of the utility disruption. disruption to during the period of local community houses and strengthening the when distribution Restore the utilities immediately to overcome commercial conductors lines crossing public inconvenience. premises. the new transmission line are switched off. Health and safety Injury and Contract provisions specifying minimum Contract RRVPN and ADB No None

57

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) sickness of requirements for construction camps. clauses Health and safety workers and (number of standards - members of the Contractor to prepare and implement a health incidents and Monthly. public. and safety plan and provide workers with total lost-work required PPE. days caused by injuries and Contractor to arrange for health and safety sickness). awareness programmes including on AIDS and sexually transmitted diseases (STD). Capacity Building Improve Training of RRVPN Environment and Social Training Number of training No None standards of Cell. schedules. program - implementation Yearly. and monitoring.

58

H. ICB-7: Deviations from RRETIP EMP (Construction) for 400 kV D/C Moose Akal – Jodhpur (Kankani) Transmission Line

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) Construction A. Physical Resources Site clearance Soil erosion and Construction near seasonal rivers, erosion and Soil erosion Visual inspection No None surface runoff flood-prone areas should be restricted to the (Turbidity and non-rainy season. sedimentation) Provision and maintenance of drains and retention ponds. Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimise obstruction or destruction to natural drainage. Removal or Public Advance notice to the public about the time Disruption to Technical No None disturbance to other inconvenience and the duration of the utility disruption other specification public utilities commercial and Use of well trained and experienced public activities machinery operators to reduce accidental / Public damage to the public utilities complaints

Restore the utilities immediately to overcome public inconvenience Surplus Runoff to cause Any excess material will only be used as fill Location and Appropriate fill No None earthwork/soil water pollution, material offsite when the owner's agreement amount (m3) of disposal and solid waste has been obtained and with the disposal site fill disposal dispersal locations disposal restored in a manner that prevents erosion Soil disposal quarterly and does not block any drainage path locations and volume (m3) B. Environment Resources Equipment layout Noise and Selection of construction techniques and Construction Minimal ground No None and installation vibrations machinery to minimise ground disturbance. techniques and disturbance machinery Monthly Provision of facilities Contamination of Construction workforce facilities to include Amenities for Presence of proper Yes Open defecation for construction receptors (land, proper sanitation, water supply and waste Workforce sanitation, water workers water, air). disposal facilities. facilities. supply and waste disposal facilities - Once. Mechanised Noise, vibration Construction equipment to be well maintained. Construction Technical No None construction and operator techniques and specifications, safety, efficient equipment - safety regulations, operation. Construction techniques and Machinery estimated noise Noise control

59

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) selection to minimize ground disturbance. emissions and regulations- Noise, vibration, Proper maintenance and turning off plant not operating Quarterly. equipment wear in use. schedules. and tear. Construction of roads Increase in Existing roads and tracks used for Access roads, Use of established No Existing village for accessibility for airborne dust construction and maintenance access to the routes (length roads wherever roads and cart sub stations particles. site wherever possible. and width of possible. tracks used. access roads). Increased land New access ways restricted to a minimum of Access restricted to requirement for single carriageway width. a minimum of temporary single carriageway accessibility. width. C. Ecological Resources Site clearance. Vegetation. Marking of vegetation to be removed prior to Vegetation Clearance strictly No None clearance, and strict control on clearing marking and limited to target activities to ensure minimal clearance. clearance vegetation –Once. control (area in m2). Trimming/cutting of Loss of Trees that can survive pruning to comply Species- Presence of target No None trees within RoW. vegetation and should be pruned instead of cleared. specific tree species in RoW deforestation. retention as following vegetation Felled trees and other cleared or pruned approved by clearance. vegetation to be disposed of as authorised by statutory the statutory bodies. authorities (average and maximum tree height at maturity, in metres). Disposal of cleared vegetation as approved by the statutory authorities (area cleared in m2). Wood/ vegetation Loss of Construction workers prohibited from Illegal wood Complaints by local No None harvesting, vegetation and harvesting wood in the project area during /vegetation people or other cut and fill operations deforestation their employment. harvesting evidence of illegal (area in m2, harvesting.

60

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) number of incidents reported). Effect on fauna Prevent work force from disturbing the flora, Habitat loss. Complaints by local fauna including hunting of animals and fishing people or other in water bodies. evidence of illegal hunting. Proper awareness programme regarding conservation of flora, fauna including ground vegetation to all workers. D. Human Environment Acquisition of Loss of Avoid faming/harvesting season for field crops Land area of Loss of crops-work No None cultivable lands. agricultural/ wherever possible for the project activities. agriculture loss. in post-harvest horticultural period but before productivity. Avoid construction/stringing during fruits Construction next crop – Once season. Schedule in per site. non-fruiting Ensure existing irrigation facilities are season. maintained in working condition.

Protect /preserve topsoil and reinstate after Usage of construction completed. existing utilities.

Status of Repair /reinstate damaged bunds etc. after facilities construction completed. (earthwork in m3).

Implementation Compensation for temporary loss in of crop agricultural production. compensation (amount paid, dates, etc.). Temporary use of Losses to Contract clauses specifying careful Contract Incorporating good No None land. neighbouring construction practices. clauses construction land uses/ Design basis management, values. As much as possible existing access ways will and layout. design engineering be used. Reinstatement practices. of land status Consultation with Productive land will be reinstated following (area affected, affected parties completion of construction. m2). immediately after

61

Project Activity Potential Mitigation Action Monitoring Standards/ Improvement Deviation Environmental Scope Measurement/ required Impact Frequency (Yes/No) Implementation completion of Compensation will be paid for loss of of tree/crop construction and production, if any. compensation after the first (amount paid). harvest. Transportation and Nuisance to the Transport loading and unloading of Water, Air CPCB Emission No None storage of materials. general public. construction materials should not cause Quality and standards and nuisance to the people by way of noise, Noise (dBA). Water Quality vibration and dust. standards - Quarterly. Avoid storage of construction materials beside the road, around water bodies, residential or public sensitive locations.

Construction materials should be stored in covered areas to ensure protection from dust, emissions and such materials should be bundled in environment friendly and nuisance free manner. Temporary outage of Loss of power Advance notice to the public about the time Power Regular monitoring No None the electricity supply to the and the duration of the utility disruption. disruption to during the period of local community houses and strengthening the when distribution Restore the utilities immediately to overcome commercial conductors lines crossing public inconvenience. premises. the new transmission line are switched off. Health and safety Injury and Contract provisions specifying minimum Contract RRVPN and ADB No None sickness of requirements for construction camps. clauses Health and safety workers and (number of standards - members of the Contractor to prepare and implement a health incidents and Monthly. public. and safety plan and provide workers with total lost-work required PPE. days caused by injuries and Contractor to arrange for health and safety sickness). awareness programmes including on AIDS and sexually transmitted diseases (STD). Capacity Building Improve Training of RRVPN Environment and Social Training Number of training No None standards of Cell. schedules. program - implementation Yearly. and monitoring.

62

ANNEXURE-9

CONSULTATIONS HELD DURING IMPLEMENTATION BY EPC Contractors

A. Summary of Consultation at Transmission Tower Project Sites (Rajasthan)

CONSULTATION OF 400 KV D/C RAMGARH – AKAL TRANSMISSION LINE (ICB -5)

No. Issues Participants’ Opinion, Comments and Suggestions 1 General perception about the project and the awareness area is hub of wind generation, people aware about about the proposed project. of the project as so many projects are under construction and satisfied after interaction with RRVPN officials. 2 Support of local people for the proposed project? Villagers were engaged as local labor and vehicle placed on hire basis. 3 Any critical issue or concern by the local people No, Farmer have only one concern regarding crop regarding the project? compensation after construction activity. 4 Employment Potential in the project which is of benefit Labor for tower foundation work to village 5 Is the land Irrigated and what are the sources of Irrigation is dependent only upon the rain, major portion of the Irrigation? transmission line passing through the non-irrigated area. 6 Protected areas (national park, protected forest, None nearby, the transmission line. religiously sensitive sites, historical or archaeological sites), if any 7 Any key environmental issues such as dust, noise, No such environment issue arisen, dust generated only when water, land, visual pollution that villages are objecting to. the wind is very strong. 8 Will the project siting adversely impact the water or soil None resource in the locality 9 Loss of residential/commercial structures, if any due to A minimum distance of 400-500 m distance has been kept the project from any residential/agricultural structure from any tower foundations. 10 Loss of community life like any Market Places or None community activities to be affected 11 Perceived benefits/loss from the project No loss observed, local villagers get the employment. 12 What other organizations of a social nature There are no NGO/CBO or civil society working in these areas. (NGOs/CBOs/ Civil Society) active in the area? Name of these organizations. 13 What are the major crops and how many crops you Moong, Guwar is the major crop of the area, which are cultivate in a year. dependent on rain. Once a year. 14 What are the most type of trees/shrubs in the area Trees in area – Babul, Kejri etc. 15 What is the average yielding of each crop per bigha and Average yield of Guwar is 200 kg per Bigha and the market what is the market rate of the crop (per quintals rate of Rs 3400 per Quintal. 16 Will the project affect migration pattern (If any), inward No migration from the area due to the project. or outward 17 Any Other Issues you may want to share: Demand for power supply to be more regular in the area and drinking water supply to villagers.

B: 400KV D/C Twin ACSR MOOSE RAMGARH – AKAL TRANSMISSION LINE (ICB-5) S.NO Village Name of Occupation Date Locations Transcript participant 1 Akal Mr. Chandan Government 5-1-201 AP 3 1. Villagers asking land Service compensation instead of crop Ragunath Singh Farmer/Land owner AP 5 compensation. OM Puri Farmer/Land owner 5/1 2. Farmers asking to plan Nakat puri Farmer/Land owner 5/2 construction activity in non-crop Prag Singh 5/3 season. 3. Major concern of the participant was in which way are they are going to benefit in future. 2 Basnpeer/ Thiyat Mr. Harri Ram s/o Farmer/Land owner 6-1-2017 AP 7 1. Farmer asking to avoid the Pokkaram spotting of tower in land whose have already another tower. Parwati w/o Vijay Farmer/Land owner 11/6 2. Government Need to give Singh land compensation in place of Deen Singh S/O Farmer/Land owner 11/8 crop compensation. Sohan Singh Mul Singh S/O Government Service AP 12 Sohan Singh 3 Chadu Mr. Swarup Singh Politician 9-1-2017 17/3 1. Land owner demanding to Hamira Farmer/Land owner engage the tractor for the Mr. Khaniya Lal Farmer/Land owner 18/3 construction stage. S/O Madan Lal 2. Land owners asking, night Mr. Sagat Singh Farmer/Land owner AP 20 watchman job up to a specific S/O Sultan Singh length to get some benefit from the project. 4 Hadda Yaru Ram S/O Farmer/Land owner 11-1- 23/7 1. Major concern of the Bakat Ram 2017 participant was land Moti Kila ki Dhani Mohammmad Khan Farmer/Land owner 23/8 commendation in place of crop S/O JUsab Khan commendation because tower is Gemar Singh S/O Farmer/Land owner 27/7 fixed for lifetime in land. Ishwar Singh 27/87 2. Construction activity should Mangal Singh S/O be in non-crop season to avoid Jan Singh damage of crop. 5 Prewar Suraj Kanwar W/O Farmer/Land owner 12-1- 31/2 1. Local Villagers asking to Inder Singh Farmer/Land owner 2017 31/3 place a vehicle on hire basis to Padam Singh S/O Farmer/Land owner get employment. Amar Singh 2. Villagers asking land Govind Sngh S/O Farmer/Land owner 36/1 compensation instead of crop Sohan Singh compensation. Surat Singh S/O Farmer/Land owner 40/3 3. Construction activity should Prabhu Singh 40/4 be in non-crop season to avoid Chotu Singh S/O damage of crop. Pabhu Singh Bag Singh S/O Alsi Farmer/Land owner 13-1- 41/1 Singh 2017 Farmer/Land owner Padam Singh S/O 42/5 Bakhat Singh Farmer/Land owner Khet Singh S/O Baank Singh 45/5 Tirpal Singh S/O Peerdan Singh 45/6

400 kV D/C Moose Bhadla – Jodhpur (LILO at Merta) Transmission Line (ICB -6) C: Consultation at Transmission Tower Project Sites (Rajasthan) No. Issues Participants’ Opinion, Comments and Suggestions 1 General perception about the project and the From the day stub setting work started, the local land owners were awareness about the proposed project. aware of the project and have had interactions with EPC contractor and RRVPN officials. 2 Support of local people for the proposed project? Some persons were working as labor, vehicles and other machinery were hired from the local owners 3 Any critical issue or concern by the local people There has been always requests made for the payment of land. As regarding the project? no agricultural land being affected ,the payment for crop damage to be paid soon once the transmission line work is complete. 4 Employment Potential in the project which is of Labor for tower foundation work. benefit to village 5 Is the land Irrigated and what are the sources of Most of the land is rain fed (single season). Only about 20 kms in Irrigation? length has some bore well irrigation in entire route area. 6 Protected areas (national park, protected forest, Line selection has been done in a manner to avoid wild life. Line is religiously sensitive sites, historical or archaeological more than 1 Kms away from such wild life. sites), if any 7 Any key environmental issues such as dust, noise, We are adopting all type of preventive measures to avoid such water, land, visual pollution that villages are pollution. objecting to. Testing has been conducted at site and reports submitted with no effect of construction of Transmission Line in the area. 8 Will the project siting adversely impact the water or Not affected. soil resource in the locality 9 Loss of residential/commercial structures, if any due No. Transmission Line route has been selected in a manner to have to the project minimum distance of 400-500 m distance from any residential/commercial structure. 10 Loss of community life like any Market Places or Not affected. community activities to be affected 11 Perceived benefits/loss from the project No loss is foreseen. However if the tower falls on the land near the highway, the rate of land goes down. 12 What other organizations of a social nature There are no NGO/CBO or civil society active in these area. (NGOs/CBOs/ Civil Society) active in the area? Name of these organizations 13 What are the major crops and how many crops you Agriculture is mostly Bajra, Moong, Gwar, Raira, Moong, Moongfali cultivate in a year. which are dependent on rain. Once a year. 14 What are the most type of trees/shrubs in the area Trees in area – Babul, Kejri, Kankheda etc. 15 What is the average yielding of each crop per bigha Mostly for local consumption, almost nil is sold in market. and what is the market rate of the crop (per quintals 16 Will the project affect migration pattern (If any), With the construction of project, there shall not be any migration inward or outward from the area. However, there is some migration (05 % to 10% ) from the villages to the district headquarters for education, work and industries. 17 Any Other Issues you may want to share: Demand for power supply to be more regular in the area

D: 400KV D/C TWIN ACSR MOOSE BHADLA-JODHPUR LILO AT MERTA) TRANSMISSION LINE (ICB 6) Lists of the Participants and their occupation No Date of Location Village Name of Occupation Issues / Decisions / Comments discuss near Tower participant Agreements ion AP point s 1 25-Oct- AP 2/0 to Lordi Surata Farmer/Land owner Requested for RRVPNL has made clear to the land owner 16 AP 3A/0 Panditji Ram additional that there is no loss or damage of land during compensation for land the construction of Line. Land owner and damage of crop in understood and matter resolved. Budha Ram Farmer/Land owner access. RRVPNL confirmed the land owner that Compensation of Damage of crop in Way shall be paid. Loon Singh Farmer/Land owner Rajpurohit Gobar Ram Farmer/Land owner Tej Singh Farmer/Land owner 2 15-Nov- AP 4/0 to Melawas Chen Singh Farmer/Land owner Requested for Speedy RRVPNL has taken necessary steps to speed 16 AP 6A/0 process of up the crop compensation cheques, also compensation for informed the process cycle time. Madan Farmer/Land owner damage of crop in Singh Work and access. Gayad Farmer/Land owner Singh 3 10-Jan- AP 38/0 to Osian Chain Farmer/Land owner Demanding of Crop RRVPNL has discussed with the Farmer and 17 42A/0 Singh Compensation cheque make him aware about the process involved

No Date of Location Village Name of Occupation Issues / Decisions / Comments discuss near Tower participant Agreements ion AP point s before the work start. and made him assured that the crop compensation cheque shall be paid on time. Sumer Farmer/Land owner Singh Bhoma Farmer/Land owner Ram Koja Ram Farmer/Land owner Rewat Farmer/Land owner Singh 4 8-Jun-16 AP 79A/0 to Khichan Balwant Farmer/Land owner Whether consulted RRVPNL has taken the note to issue the check AP 85/0 Singh during final survey and and disburse compensation in a faster manner. tower foundation Gordhan Farmer/Land owner Requested to Divert RRVPNL has discussed with the Farmer and Singh the line route make them aware about the difficulties in line diversion. Ratan Farmer/Land owner Singh Kailash Farmer/Land owner Singh Tipu Singh Farmer/Land owner Swarup Farmer/Land owner Singh 5 17-Oct- AP 104/0 to Shekhasar Manohar Farmer/Land owner Compensation was not RRVPNL has taken the note to check the 16 AP 105/0 Singh paid during foundation matter with relevant revenue department Narpat Farmer/Land owner Compensation responsible for crop loss valuation. Singh was paid only during erection Gayad Farmer/Land owner Requested for Singh additional compensation Prem Singh Farmer/Land owner Sumer Farmer/Land owner Singh 6 15-Jan- AP 85/0 to Malhar Jai Prakash Farmer/Land owner Whether consulted RRVPNL has made clear to the land owner 16 AP 89B/0 Purohit during final survey and that there is no loss or damage of land during tower foundation the construction of Line. Land owner understood and matter resolved. Bhanwar Farmer/Land owner Views on RRVPNL confirmed the land owner that Lal compensation Compensation of Damage of crop in Way shall assessment for loss of be paid. crops Jaitu Giri Farmer/Land owner Requested for additional compensation for land and damage of crop in access. 7 15-Jan- AP 112/0 to Noore KI Kutub Deen Farmer/Land owner Survey was completed RRVPNL has taken the note to check the 16 AP 114/0 Burj in April, 2015 matter with relevant revenue department Mehar Din Farmer/Land owner Foundation was responsible for crop loss valuation. completed in June, 2015 Hasan Farmer/Land owner Erection completed in Khan December, 2015 Ishak Khan Farmer/Land owner Compensation as paid in October, 2015 Khan Farmer/Land owner There was no obstacle Mohhamad to receive the cheque Khuda Farmer/Land owner Compensation was not Baksh paid during foundation Attah Farmer/Land owner compensation was Mohhamad paid only during erection Sadik Khan Farmer/Land owner Requested for additional compensation 8 20-Jul- AP 114A/0 Bhadla Sakur Khan Farmer/Land owner Compensation was not RRVPNL has taken the note to check the 16 to AP 117/0 paid during foundation matter with relevant revenue department compensation was responsible for crop loss valuation. paid only during erection Meer Farmer/Land owner Requested for Mohhamad additional compensation

Environment Consultations after re-routing of the transmission line between AP79/2 and AP84/0 ICB-6) held on Jan 9, 2018

# Questions Summary Participants’ Opinion, Comments and Suggestions A. General area related 1 General perception about the Existing species in Bird area at the area between Transmission power project and the rerouted line from AP79/2-AP 84/0 (8.5 kms awareness about the proposed long) as raised by localities are protected project. 2 Type of agriculture/crops in the area Moong, Jeera, Bajara, Mustard, Vegetables. where towers are re-routed. 3 Number of households in the Government land - 10 locations area/village, population of ethnic Private Land – 15 locations minorities etc. affected by rerouting of line 4 Loss of residential/ commercial/ None, only crops once a season agricultural structures / huts, if any due to the rerouting of transmission line project 5 Type of trees in the re-routed area: None Fruit/non fruit/ commercial protected/rare/endangered species etc. 6 Will the project re-routing adversely No impact the water or soil resource in the area? B Birds 7 Distance of re-routed line from Approximately 2 km protected areas (conservation reserve, national park, protected forest, religiously sensitive sites, historical or archaeological sites), if any 8 Besides Khurja birds, any other None endemic, endangered birds/ mammals in the area. What type and numbers of rare/ endangered bird species and bats you have seen in the area. 9 Will the court order be an effective No deterrent to Khurja bird hits with the transmission line if implemented? 10 Will you be satisfied if the court order Yes is implemented fully by RVPN for the 400 kV line. C Ecotourism Potential at Khichan 11 Do you think that Khichan has enough Yes attractive eco-tourism potential for development? 12 Will the rerouted transmission line as No proposed by High Court still lead to any interference in scenic areas/nature 13 Which stakeholder do you think is the Government and related departments most important roles in the process of ecotourism development in Khichan?

# Questions Summary Participants’ Opinion, Comments and Suggestions A- Government and related departments B- Non-Profit organizations (i.e. environmental groups, NGOs) C- Business organizations (i.e. tour operators, travel agency) D- Local community and people E- Visitors F- Others D Others 14 What other organizations of an Civil Society environmental nature (NGOs/CBOs/ Civil Society) active in the area? Name of these organizations 15 Any critical other environmental issue No or concern by the local people regarding the project after its rerouting?

Details of Public Consultantions at Tower area AP79A/0 to AP 83D/0 at Khichan Area Date of Consultation 9 Jan 2018 Sl. Location Village/Tehsil/ GPS. Coordinate's Name of Farmer/ Occupation Male/ Information provided by- No. No. District Latitude Longitude Type of Land Female 1 79/2 Khichan/ 27° 07' 72° 26' Existing Tower / Jodhpur 31.5058" N 31.9206" E 2 AP79A/0 27° 07' 72° 26' Mohan Ram S/o Farmer Male 9785097563 37.3531" N 26.5960" E Jeevan Ram Self 3 AP79B/0 27° 07' 72° 26' Government 48.5140" N 29.4277" E 4 79B/1 27° 07' 72° 26' Government 54.4165" N 39.6041" E 5 AP80/0 27° 08' 72° 26' Government 01.0960" N 51.4333" E 6 80/1 27° 08' 72° 26' Hukuma Ram s/o Farmer Male 8769508560 12.4059" N 55.3154" E Kola Ram (Information provided by workers) 7 AP81/0 27° 08' 72° 26' Kanha Ram Katariya Farmer Male 999327787 22.0492" N 58.6545" E (Information provided by workers) 8 AP82/0 27° 08' 72° 26' Panna Lal Ranga Farmer Male Information provided by workers 28.4517" N 58.8359" E 9 82/1 27° 08' 72° 26' Daulal Sharma Farmer Male Information provided by workers 40.1170" N 59.0430" E 10 AP82A/0 27° 08' 72° 26' Hari Singh Raj Farmer Male 9414418410 52.8226" N 59.2990" E Purohit Information provided by workers 11 82A/1 27° 09' 72° 26' Government 00.4388" N 54.7685" E 12 82A/2 27° 09' 72° 26' Ramu Ram Farmer Male 99833844356 07.3478" N 50.6534" E 13 AP82B/0 27° 09' 72° 26' Government 13.8089" N 46.9115" E 14 82B/1 27° 09' 72° 26' Government 22.4800" N 36.1105" E 15 82B/2 27° 09' 72° 26' Jeetu Singh Raj Farmer Male 31.0210" N 25.3120" E Purohit 16 AP82C/0 27° 09' 72° 26' Government 39.6916" N 14.5101" E 17 82C/1 27° 09' 72° 26' Government 46.2010" N 02.7767" E 18 AP83/0 27° 09' 72° 25' Government 52.6161" N 51.2266" E 19 83/1 27° 09' 72° 25' Mage Singh s/o Vijay Farmer Male 9414760869

Sl. Location Village/Tehsil/ GPS. Coordinate's Name of Farmer/ Occupation Male/ Information provided by- No. No. District Latitude Longitude Type of Land Female 54.0529" N 37.4660" E Singh Information provided by workers 20 83/2 27° 09' 72° 25' Government 55.3018" N 24.1092" E 21 AP83A/0 27° 09' 72° 25' Government 56.3036" N 13.2276" E 22 83A/1 27° 09' 72° 25' Private Information not given 53.0279" N 02.9164" E 23 83A/2 27° 09' 72° 24' Private Information not given 49.6811" N 52.2803" E 24 AP83B/0 27° 09' 72° 24' Bhavar Ram s/o Farmer Male 7742458099 45.8533" N 40.2392" E Heera Ram 25 AP83C/0 27° 09' 72° 24' Late Shri Magraj Farmer Male Information provided by workers 34.9178" N 33.8096" E Singh 26 AP83D/0 27° 09' 72° 24' Murlidhar Sharma s/o Farmer Male 946277815 30.0021" N 20.9227" E Triloka Ram 27 AP84/0 27° 09' 72° 24' Existing Tower 33.0461" N 15.1510" E

400 kV D/C Moose Akal – Jodhpur (Kankani) Transmission Line (ICB -7) E: Consultation at Transmission Tower Project Sites (Rajasthan) No. Issues Participants’ Opinion, Comments and Suggestions 1 General perception about the project and the Since the towers were being erected, they were aware of awareness about the proposed project. the project and have had interaction with EPC contractor and RRVPN officials. 2 Support of local people for the proposed project? Some persons were working as labor. 3 Any critical issue or concern by the local people No agricultural land being taken away. However they want regarding the project? the payment for crop damage to be paid soon once the transmission line work is complete. 4 Employment Potential in the project which is of Labor for tower foundation benefit to village 5 Is the land Irrigated and what are the sources of Most land is rainfed (single season). Only some portion Irrigation? (16 km in length) has some borewell irrigation in Shergarh area. 6 Protected areas (national park, protected forest, None nearby, however some local deer in some areas etc. religiously sensitive sites, historical or archaeological sites), if any 7 Any key environmental issues such as dust, noise, Dust only when the wind is very strong. water, land, visual pollution that villages are objecting to. 8 Will the project siting adversely impact the water or None soil resource in the locality 9 Loss of residential/commercial structures, if any due A minimum distance of 400-500 m distance has been kept to the project from any residential/agricultural structure from any tower foundations. 10 Loss of community life like any Market Places or None community activities to be affected 11 Perceived benefits/loss from the project No loss is foreseen. However if the tower falls on the land near the highway, the rate of land goes down. 12 What other organizations of a social nature There are no NGO/CBO or civil society working in these (NGOs/CBOs/ Civil Society) active in the area? area. Name of these organizations 13 What are the major crops and how many crops you Agriculture is mostly Bajra, Moong, Gwar, which are cultivate in a year. dependent on rain. Once a year. 14 What are the most type of trees/shrubs in the area Trees in area – Ker, Babul, Kejri, Kankheda etc. 15 What is the average yielding of each crop per bigha Mostly for local consumption, almost nil is sold in market. and what is the market rate of the crop (per quintals 16 Will the project affect migration pattern (If any), No migration from the area due to the project. However, inward or outward there is some migration (05 % to 10% ) from the villages to the district headquarters for education, work and industries. 17 Any Other Issues you may want to share: Demand for power supply to be more regular in the area

F: 400KV D/C QUAD ACSR MOOSE AKAL (JAISALMER) - JODHPUR(KANKANI) TRANSMISSION LINE Lists of the Participants and their occupation No Village Name of participants Occupation Location near Tower AP point 1 Khudala Village Mrs. Andai Wife of land owner Mr. Dhanaram Chaudhary and AP 76/3 and AP 76/2 mother of Mr. Laxman Chaudhary 2 Loonavas Harishachandra Farmer/Land owner AP 72/5 Khara 3 Mangilal Farmer/Land owner AP 73A&B 4 Magli Devi Farmer/Land owner Viram Kuldeep Manglesh 5 Mr. Biddaram s/o Farmer/Land owner AP 73/0 Jaggaram 6 Mr. Narain SIngh Korna village Mr. Deepa Ram AP 66/3 Chaudhury Mr. Nema Ram Farmer/Land owner AP 66/2 Mr. Pukharam Farmer/Land owner AP 66/1 Mr. Sukharam Petty Sub-contractor of Tata Projects Limited Mr. Mana Ram Farmer/Land owner AP 66/6 Mr. Anup Chaudhary Farmer/Land owner AP 66/5 Mr. Lakshman Ram Farmer/Land owner AP 26/6 Mr. Khushala Ram Farmer/

No Village Name of participants Occupation Location near Tower AP point Mr. Sonaram Singh Farmer/ Mr. Poonaram Singh Farmer/ Achla New Mr. Khanim Ram Farmer/Land owner AP 23/2 Mr. Padma Ram Farmer/Land owner AP 23/1 Luna Kala Mr. Dham Singh Farmer/Land owner AP 20/0 village Mr. Swaroop Singh Farmer/Land owner AP 20/0 Mr. Narayan Singh Farmer/Land owner AP 20/0 Mr. Ram Singh Farmer/Land owner AP 20/1, 2, 3 Mr. Ashish Singh Farmer/Land owner AP 20/1, 2, 3 Mr. Mukesh Tomar Land owner, Labor AP 20/1, 2, 3 Farmer/Land owner Betina Mr. Ram Singh s/o Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Padam Singh Betina Mr. Duryodhan Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Betina Mr. Kunuj Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Betina Mr. Pradeep Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Betina Mr. Prem Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Betina Mr. Tanerao Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Betina Mr. Gayad Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Betina Mr. Than Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Betina Mr. Khaman Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Mr. Bhum Singht Farmer/Land owner Mehrajot Mr. Narayan Singh Farmer AP 14/3 Mr. Bhanwar Singh Farmer/Land owner AP 14/1 Mr. Gaj Singh Farmer/Land owner AP 13/6 Mr. Nag Singh Farmer/Land owner AP 13/6 Mr. Nathu Singh Farmer/Land owner AP 13/6

Annexure-10

Environment Safeguards Compliance Audit Report including Corrective Action Plan ICB-7 (Additional Component)

400 KV D/C RAMGARH – AKAL (TRANSMISSION LINE ICB-5)

400 kV Transmission line Jodhpur (Merta) to Bhadla GSS (ICB-6)

400 kV D/C Quad ACSR MOOSE AKAL (JAISALMER) to JODHPUR (KAKANI) TRANSMISSION LINE

Environment Planning Document (Scope Change)

Environment Safeguards Compliance Audit Report including Corrective Action Plan

Document Stage: Final Document for Disclosure Project Number: 45224 (IND) November 2015

India: Rajasthan Renewable Energy Transmission Investment Program

Prepared for Rajasthan Rajya Vidyut Prasaran Nigam Limited (RRVPNL), Government of Rajasthan.

The environment and social compliance audit is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

i Environmental Audit Report and Corrective Action Plan for RRVPNL

ABBREVIATIONS

AC – Alternating Current APs – Affected Persons ADB – Asian Development Bank CSR – Corporate Social Responsibility DC – Direct Current DP – Displaced Persons DPR – Detailed Project Report EHS – Environment Health and Safety EHV – Extra High Voltage EMP – Environmental Management Plan EMoP – Environmental Monitoring Plan GoI – Government of GRC – Grievance Redressal Committee GRM – Grievance Redress Mechanism IEE – Initial Environmental Examination IPP – Independent Power Producer JNNSM – Jawaharlal Nehru National Solar Mission MoEF&CC – Ministry of Environment, Forests and Climate Change, GOI NGOs – Non-Government Organizations RPO – Renewable Energy Purchase Obligation ROW – Right of Way SPCB – State Level Pollution Control Board SPS – Safeguard Policy Statement, 2009

WEIGHTS AND MEASURES

Bigha – Measurement of land area (1 Bigha =1618 sq m in western Rajasthan) Cusec – Measure of flow rate (28.317 litres per second) ha. (hectare) – 10,000 sq. m. GW – Giga watt km (kilometre) – 1,000 m kV – kilovolt (1,000 volts) kW – kilowatt (1,000 watts) kWh – kilowatt-hour MW – Mega Watt GW – Giga Watt Ppm – Parts per million

i Environmental Audit Report and Corrective Action Plan for RRVPNL

Table of Contents S.No. Section Page No.

1.0 INTRODUCTION 1 1.1 Purpose of the report 1 1.2 The Project 1 1.3 Methodology Followed 2 1.4 Compliance Audit Framework and Evaluation Criteria 2 1.5 Approach to the Environmental Compliance Audit 2

2.0 BRIEF PROJECT DESCRIPTION AND CONTEXT SETTING 3 2.1 Rajasthan Renewable Energy Transmission Investment Program 3 (RRETIP) 2.2 Institutional Arrangement and Responsibilities 3 2.3 Grievance Redress Mechanism (GRM) and Procedure 4

3.0 DUE DILIGENCE REVIEW OF ENVIRONMENTAL SAFEGUARD 8 COMPLIANCE 3.1 Environmental Policy Compliance requirements 8 3.2 Current Status of Transmission Project under review 9 3.3 Audit and site investigation procedure followed 9 3.4 Documents, Findings and Consultation 11

4.0 ENVIRONMENTAL MANAGEMENT PLAN (EMP) & BUDGET 14 4.1 Compliance with RRETIP EMP 14 4.2 Good Practices noticed during site visits 18 4.3 Improvements required noticed during site visits 18 4.4 EMP budget 19

5.0 CORRECTIVE ACTION PLAN, BUDGET WITH TIME FRAME 20 5.1 Corrective Action Plan (CAP) 20 5.2 Budget and Timeline 20

6.0 SUMMARY AND CONCLUSION 21 6.1 Summary Audit Findings and Corrective Action Plan 21 6.2 Output/Outcome 21

ANNEXURES Annexure 1 APPLICABLE ENVIRONMENTAL LAWS, REGULATIONS AND ADB SPS 2009 Annexure 2 ALTERNATE ANALYSIS FOR TRANSMISSION LINE Annexure 3 RAJASTHAN GAZZETTE NOTIFICATION FOR TRANSMISSION LINE CONSTRUCTION Annexure 4 FOREST CLEARANCE FOR TRANSMISSION LINE Annexure 5 DETAILS OF EPC CONTRACTOR EHS POLICY Annexure 6 TREE/CROP COMPENSATION Annexure 7 PHOTOGRAPHS FROM SITE VISIT TO TRANSMISSION LINE

ii Environmental Audit Report and Corrective Action Plan for RRVPNL

1.0 INTRODUCTION

1. Asian Development Bank (ADB) has extended a multi-tranche financing facility to the Rajasthan Rajya Vidyut Prasaran Nigam (RRVPNL), which is the state transmission utility (STU), of Government of Rajasthan under the Rajasthan Renewable Energy Transmission Investment Program (RRETIP). The project supports evacuation of power from Western Rajasthan including the facilities coming up at the 250 MW Phase 1 of the Bhadla solar park, , Rajasthan for which Rajasthan Renewable Energy Corporation (RREC) is the nodal agency. The RRETIP supports the addition of 4,240 MW of clean energy in the grid in Western Rajasthan. The RRETIP activities support solar power development in a cost-effective manner in Rajasthan.

2. RRVPNL is the Executing Agency (EA) along with the Energy Department, Government of Rajasthan. The project outcome is the development of a reliable evacuation system for power from various renewable energy projects coming up in western Rajasthan including projects at the Bhadla solar park. Physical outputs under the entire Investment Program includes the construction of three grid substations (400/220/132 kilo Volt) and associated facilities at Bhadla, Ramgarh and Jaisalmer; the construction of associated automation and control infrastructure, the construction of nine grid substations (9 220/132 kV) and associated facilities at Bap, Kanasar, Chhatrail, Pokaran, Kolayat, Ramdev Nagar, Badisid, Aau and Bajju; the augmentation of four 400 kilo Volt (kV) grid substations at Akal, Jodhpur, Barmer, Bikaner; the upgradation of 3 substations to 132 kV in Bhadla; and the construction of nearly 1850 km of 400 kV, 220 kV and 132 kV of transmission lines in Western Rajasthan by RRVPNL. Non-physical outputs include improving institutional capacity and effectiveness, including planning, project management, community involvement, financial management and improved monitoring and reporting.

1.2 Purpose of the report 3. The RRETIP’s Tranche 1 was assessed for technical aspects as well as for environmental and social impacts in 2012. Accordingly, the Environmental Assessment and Review Framework (EARF) for the entire RRETIP (including future tranches) and the initial environment assessment for tranche 1 were approved for implementation between RRVPNL and ADB.

4. The sub-project under consideration for this environmental compliance audit report (ECAR) for under construction 400 KV (Quad Moose) double circuit Akal-Jodhpur (new) transmission line will be funded under Tranche 1 as a scope change sub-project. Given the exigencies of the power evacuation needs in the state of Rajasthan, the transmission towers are being constructed using RRVPNL funds while the conductor (400 kV Moose Conductor) will be procured using RRETIP funds. Accordingly, for this compliance audit purposes, the transmission line towers have been considered as an associate facility while the conductor is the sub-project funded component.

1.3 Methodology Followed 5. The environmental assessment of current status of the implementation of project activities for the transmission lines under construction was done in August 2015. This included a review of the construction activities for environment, health and safety compliances, documentation of the status of compliance to RRETIP’s Environmental Management Plan (EMP) requirements by the Engineering, Procurement and Construction (EPC) contractor and review the procedure employed by the EPC contractor to document mitigation activities, if any.

6. Methodology used for field data collection were the following:  Assessment was based on reviewing status of all tower locations under construction by RRVPNL’s EPC contractor. 1 Environmental Audit Report and Corrective Action Plan for RRVPNL

 Interviewing representatives of the EPC contractor/sub-contractors engaged on the transmission tower erection along with the survey team and RRVPNL officials.  Interviewing Project Affected Households (PAHs), in particular, on whose land the tower is erected and any other severely affected persons or groups regarding their feedback on construction practices followed.  Review if any complaint has been received by RRVPNL; review the complaint redress process and its current redressal.  Comparing EARF/EMP of RRETIP with the applied work practices and the policy framework of the project by RRVPNL.

1.4 Compliance Audit Framework and Evaluation Criteria 7. The Environmental compliance audit that has been conducted has been evaluated against the following criteria:  Applicable Local and National environment, occupational safety, health and social legislations;  ADB Safeguard Policy Statement (2009);  All requirements and mitigating or monitoring measures specified in the Environmental Assessment and Review Framework (EARF) for RREIP 2012 as well as the IEE for Tranche 1.

1.5 Approach to the Environmental Compliance Audit 8. The Environmental Compliance Audit was broadly divided into four tasks:  Document review;  Site visit and consultation with RRVPNL officials and EPC contractor/sub-contractors;  Generic community, project affected people (PAPs) and workers consultations during the site visit;  Assessment of work practices followed, gaps and compliance analysis; and  Reporting.

2 Environmental Audit Report and Corrective Action Plan for RRVPNL

2. BRIEF PROJECT DESCRIPTION AND CONTEXT SETTING

2.1 Rajasthan Renewable Energy Transmission Investment Program (RRETIP)

9. The first project under the Program (Tranche 1 project) included physical and nonphysical investments. Physical investments included the construction of the transmission system, including two grid substations (400/220/132kV) and associated facilities at Bhadla and Ramgarh; two substations (220/132 kV) and associated facilities at Bap and Kanasar; and associated automation and control infrastructure. The investments also include the augmentation of two 400 kV grid substations at Akal and Bikaner, the upgradation of 3 substations to 132 kV in Bhadla, and the construction of nearly 600 km. of 400 kV, 220 kV, 132 kV transmission lines in Bhadla and Ramgarh. The non-physical outputs include project management, training and community outreach work.

10. Table 1 provides a list of ADB funded projects of Tranche-1 component. This also includes and highlights the saving component. The funding and implementation of tranche-1 subprojects has started in 2012. The proposed activity for additional scope change is listed in item number-7 of Table-1.

Table 1: ADB funded Investment Sub-Projects under RRETIP (Tranche 1) S No ADB Funded Sub-projects 1 Construction of 400/220 kV, 2 X 500 MVA Pooling Sub-Station GSS at Ramgarh (Jaisalmer) along with 400kV, 1x125 MVAR, 400kV Shunt Reactor (Bus type) and 2x50 MVAR Shunt Reactor (line type) for 400kV D/C Ramgarh-Bhadla line and Augmentation of 400kV GSS Akal by installation of 400/220 kV, 1 X500 MVA Transformer along with 400kV, 1x125 MVAR Bus Reactor and 400kV, 2x50 MVAR Shunt Reactor 2 Construction of 400/220 kV, 2 X 315 MVA Pooling Sub-Station GSS at Bhadla (Jodhpur) alongwith 400kV, 1x125 MVAR Shunt Reactor (Bus type) and 4x50 MVAR, 400kV Shunt Reactors (Line type) for Bhadla ends of 400kV D/C Bhadla- Bikaner line, 400kV LILO Jodhpur-Merta at Bhadla line and 400kV D/C Ramgarh-Bhadla line and Augmentation at 400kV GSS Bikaner along with 1x125 MVAR, 400kV Bus Reactor at 400kV GSS Bikaner and 400kV Bays for 400kV D/C Bhadla- Bikaner line and 400kV D/C Bikaner-Sikar (PGCIL) line at Bikaner end of the lines 3 Transformer Package for Ramgarh, and Bhadla. 4 Shunt Reactors Package for Ramgarh, Bhadla, Bikaner and Akal. 5 400 kV D/C Ramgarh (Jaisalmer district) to Akal (Jaisalmer district) line (Twin Moose conductor) - 100 km transmission line. 6 400 kV D/C transmission line from 400/220 kV grid substation Bhadla to LILO point at 400 kV S/C Jodhpur-Merta transmission line (Twin Moose conductor) – 160 km. 7 400 kV conductor for 400 kV lines - 400 kV D/C Akal-Jodhpur (New) line (Quad Moose). Proposed scope change sub-project GSS= Grid Substation

2.2 Institutional Arrangement and Responsibilities

11. RRVPNL has implemented World Bank program on power transmission in the past following an Environmental Social Management Framework (ESMF) developed for the project. The normal work practice of RRVPNL involves following all GOI and donor norms on environment and social safeguards compliances. The borrower has adequate in-house institutional capacity in implementing national laws and Asian Development Bank (ADB) requirements. The capacity development needs were identified and included in tranche 1. Some of the nonphysical investment include: improving institutional capacity and effectiveness, including planning, project management, community involvement, financial management and improved monitoring and reporting.

12. The RRVPNL is the Executing Agency (EA) along with the Energy Department, Government of Rajasthan for the project. RRVPNL has three divisions: i) Engineering and Projects Division (responsible for project design and implementation) ii) Accounts and Finance Division (responsible for accounts, funding arrangements) and iii) Development Division (responsible for energy sales, land identification and development).

13. The RRVPNL has constituted a Project Management Unit (PMU) shown in Figure 1 for implementing the ADB loan at the corporate level and the PMU will be supported for 3 Environmental Audit Report and Corrective Action Plan for RRVPNL

implementation activities through the RRVPNL field/zonal offices. The PMU is headed by the Chief Engineer (T&C) and the Superintending Engineer (Planning) is responsible for coordinating all external functions with ADB. GOI, DEA, GOR as well as the internal functions such as Environment and Social/R&R reporting, Legal, Finance and Accounts, Field Project offices, Procurement and Contracts etc. and other functions from within RRVPNL.

14. The field office of RRVPNL (Zonal office at Jodhpur for this project) has the overall responsibility to manage the site activities. The RRVPNL ensures that EPC contractor engaged for each project is involved in EMP monitoring and implementation. Further details on agencies responsible for EMP activities are in Table 2.

Table 2: Institutional Roles and Responsibilities for EMP Implementation Activities Activity Responsible Agency Project Initiation Stage Clearances/approvals from relevant GOI/GoR agencies- forest, roads, Field Office rivers, railways, telecom etc. Project Implementation Stage Meetings at community/household level with Aps Field Office/Contractor Implementation of proposed EMP mitigation measures Field Office/Contractor Consultations with APs during EMP mitigation measures implementation Field Office/Contractor Grievances Redressal Field Office /Sub-Divisional Administration Internal monitoring PMU ADB-Asian Development Bank; AP-Affected Persons; EA-Executing Agency; EMP-Environmental Management Plan; PMU- Project Management Unit

2.3 RRVPNL’s Grievance Redress Mechanism (GRM) and Procedure 15. RRVPNL does not have any specific Environment or Social Safeguards Policy currently. However, RRVPNL has agreed to follow the environmental principles listed in the EARF document of the RRETIP project. RRVPNL has established a Grievance Redressal Mechanism1 (GRM) that has suitable grievance redress procedure for the project affected persons. This GRM addresses affected persons’ concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to the affected persons at no cost. This GRM consists of a Grievance Redress Committee (GRC) headed by the Project Head. The committee consists of the following constitution as listed in Table 3:

Table 3: Constitution of Grievance Redress Committee 1 Project Head / CE (ADB Projects ), RRVPNL 2 Sub District Magistrate or nominee of SDM 3 Land acquisition officer / Secretary 4 Head of Finance wing at the project level 5 Representative of local Panchayat/ NGO 6 Representative of contractor 7 Executive Engineer, RRVPNL Source: EARF document 2012

16. This Grievance Redress Mechanism (GRM) provides an effective approach for resolution of complaints and issues of the affected person/community. Project Management Unit (PMU) shall formulate procedures for implementing the GRM. The Zonal Office of RRVPNL at Jodhpur is the Project Implementing Unit (PIU), which is the undertakes GRM’s initiatives that includes procedures of taking/recording complaints, handling of on-the-spot resolution of minor problems, taking care of complainants and provisions of responses to distressed stakeholders etc. paying particular attention to the impacts on vulnerable groups.

1 ADB requires that the borrower/client establish and maintain a grievance redress mechanism to receive and facilitate resolution of affected peoples’ concerns and grievances about the borrower's/client's social and environmental performance at project level. The grievance redress mechanism should be scaled to the risks and impacts of the project. It should address affected people's concerns and complaints promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to all segments of the affected people.

4 Environmental Audit Report and Corrective Action Plan for RRVPNL

17. Grievances of APs are first brought to the attention of the Project head of the Project Implementing Unit. Grievances not redressed by the PIU are brought to the Grievance Redress Committee (GRC) set up to monitor project Implementation for each project area. The GRC, if convened, determines the merit of each grievance, and resolve grievances within three months of receiving the complaint. The complainant has the right to seek grievances redressal directly through the appropriate courts of law. The field office keeps records of all grievances received including: contact details of complainant, date that the complaint was received, nature of grievance, agreed corrective actions and the date these were effected, and final outcome. The flow chart showing Grievance Redress Mechanism is presented in Figure 2.

5 Environmental Audit Report and Corrective Action Plan for RRVPNL

Figure 1: PMU structure of RRVPNL (From EARF document)

PMU STRUCTURE

ADB & HEAD PMU GOVT. OF INDIA

GOVT. OF RAJASTHAN Chief Engineer (ADB Projects) & DEA

PLANNING (Superintending Engineer, PMU) LEGAL UNIT HR UNIT

PROJECT IMPLEMENTING

UNITS & Monitoring Executive Engineers

(Each Contract) CONTRACT FINANCE ENVIRONMENT & PROCUREMENT & ACCOUNTS & SOCIAL UNIT UNIT CA, CS etc. Executive Engineer (1) Executive Engineer (2)

6 Environmental Audit Report and Corrective Action Plan for RRVPNL

Figure: 2: Flow chart showing Grievance Redress Mechanism (from EARF document)

Affected Persons

Grievances Head of Field Grievance Office/PIU of Addressed RRVPNL

Grievances

Not Addressed

Grievance Redress Committee

Grievance Addressed

Not Addressed

Court of Law

7 Environmental Audit Report and Corrective Action Plan for RRVPNL

3.0 DUE DILIGENCE REVIEW OF ENVIRONMENTAL SAFEGUARD COMPLIANCE

3.1 Environmental Policy Compliance requirements

18. As per Government of India’s (GoI) Environment Impact Assessment (EIA) Notification 2009, Power transmission projects are not listed as environmental sensitive projects and hence no clearance is required from Rajasthan State Pollution Control Board (RSPCB) or Ministry of Environment, Forests and Climate Change (MoEF&CC), GoI. Clearance from Rajasthan Forest Department is required only in cases where subproject is constructed on forest land or requires cutting of forest trees. The National Environmental Policy 2006 of Government of India (GoI) and Safeguard Policy Statement 2009 of ADB and other state level guidelines that apply to all subprojects funded by ADB are listed in Annexure 1. In addition, projects should comply with relevant international treaties to which India is a signatory such as the UN Declaration on the Rights of Indigenous Peoples, International Covenant on Economic, Cultural and Social Rights and International Labor Organisation (ILO) Core Conventions, and all other ILO Conventions ratified by the country.

19. For funding of existing facilities, ADB’s SPS 2009 states in clause, 12 below. 1. “For projects involving facilities and/or business activities that already exist or are under construction, the borrower/client will undertake an environment and/or social compliance audit, including on-site assessment, to identify past or present concerns related to impacts on the environment, involuntary resettlement, and Indigenous Peoples. The objective of the compliance audit is to determine whether actions were in accordance with ADB’s safeguard principles and requirements for borrowers/clients and to identify and plan appropriate measures to address outstanding compliance issues. Where noncompliance is identified, a corrective action plan agreed on by ADB and the borrower/client will be prepared. The plan will define necessary remedial actions, the budget for such actions, and the time frame for resolution of noncompliance. The audit report (including corrective action plan, if any) will be made available to the public in accordance with the information disclosure requirements of the Safeguard Requirements 1–3. For environment category A projects involving facilities and/or business activities that already exist or are under construction, the borrower/client will submit the audit report to ADB to disclose on ADB's website at least 120 days prior to ADB Board approval. If a project involves an upgrade or expansion of existing facilities that has potential impacts on the environment, involuntary resettlement, and/or Indigenous Peoples, the requirements for environmental and social impact assessments and planning specified in Safeguard Requirements 1-3 will apply in addition to compliance audit”.

20. RRVPNL projects are expected to comply with ADB’s Safeguard Policy Statement (SPS, 2009), Social Protection Strategy (2001), ADB Gender and Development Policy (1998), Public Communication Policy (2011), and other social requirements as well as with that of the Government of India and make it ready for possible financing by the ADB.

21. The EARF for RRETIP was developed and agreed between RRVPNL and ADB to ensure that the Program complies with the provisions of ADB's SPS 2009 and Indian laws (described in Annexure 1.) The EARF provisions guide RRVPNL in the selection, screening and categorization, environmental assessment, and preparation and implementation of safeguard plans (such as an environmental management plan or EMP) of all Tranche funded projects. Preparation of any environmental assessment documents by RRVPNL for funding of next Tranches or sub-projects in future must follow the procedures outlined in the EARF. Since the environmental assessment reports and environmental management plans to be prepared for subsequent tranches are the Borrower's documents, these documents shall be officially endorsed by RRVPNL and submitted to ADB.

8 Environmental Audit Report and Corrective Action Plan for RRVPNL

3.2 Current Status of Transmission Project under review

22. RRVPNL’s EPC contractor has started the erection of towers and therefore this report examines (i) the requirements of the RRETIP’s approved environmental documentation (EARF/IEE) and the extent to which these requirements have been satisfied by the subproject, (ii) compliance with national laws and regulations on environmental issues; and (iii) aspects where significant discrepancies exist between the observed outcomes of the sub-project implementation and objectives of the RRETIP’s approved EARF/IEE.

23. Accordingly an Environmental Compliance Audit including an on-site assessment for the project has been conducted while using RRTEIP Environment Assessment and Review Framework (EARF) and the Initial Environment Assessment (IEE) for Tranche 1 as the base documents. The Environmental Categorization for the ADB funded project on transmission lines and sub-stations is Category B. The IEE report conforms to regional and national environmental regulations and the ADB Safeguard Policy 2009.

24. The RRVPNL and the EPC contractor had conducted alternate analysis for the proposed tower line and also has conducted the final detailed survey as shown in Annexure 2. The Alternate analysis for three routes (Table 2A.1), the Plates 1-6 showing final line alignment from Akal substation to Jodhpur (new) substation showing all angle points (AP) between 1-95 (Route 1 – green line) and the tower profile with geographical coordinates are shown in Table 2A.2. The details of under-construction tower line by EPC contractor in Table 4 below:

Table 4: Summary Details of Towers for the under-construction transmission line (400 kV D/C Quad ACSR Moose Akal (Jaisalmer) – Jodhpur (New) Transmission Line) SNo Particulars Quantity 1 Total Length (Kilometers) 222.507 (Approx) 2 Total Number of Angle Points/Towers 110 3 Total Length for which final survey has been completed (Kilometers)* 200 KMs 4 Total number of Towers being or to be placed on Agricultural Land 600 Nos (Approximate) 5 Total number of Towers being or to be placed on Government land 10 Nos (Approximate) 6 Number of Towers for which survey has been completed 610 Nos 7 Number of Towers for which foundation has been completed 203 8 Number of Towers for which erection has been completed 120 9 Number of Towers for which assessment of crop compensation has 52 Nos been made 10 Date of award order to EPC 17-11-2014 11 Proposed date of closure of EPC award 16-05-2016 * Length of line between AP21/0-AP 25 in Shergarh area is irrigated agricultural area for which survey is ongoing/or approved where soil investigation is going on.

3.3 Audit and site investigation procedure followed: 25. This report is based on additional surveys undertaken between August 17-22, 2015 in the field and meetings with RRVPNL officials and EPC contractor personnel. It takes into account the findings and recommendations of the field survey, review of the environmental requisites highlighted in EMP and the corrective action plan prepared. This report summarizes these findings and recommendations, proposes a strategy for each issue and identifies the remaining outstanding issues.

9 Environmental Audit Report and Corrective Action Plan for RRVPNL

3.3.1 Request for Documents 26. The following documents were requested: - Tranche 1 IEE and EARF documents - Detailed Project Report - List of key corporate and site specific Project Managers and Staff - EPC contracts - Environmental and Social policy, reporting schedules and requirements - Site Maps and list of forms prepared for data collection. - Details for Transmission line between Akal to Jodhpur in Rajasthan (Topographic map for the ROW of the transmission line from the EPC contractor) – Tower schedules - Forest clearances - Compensation Details

3.3.2 Visit to the RRVPNL offices and Project sites 27. Site visits to project sites were held in August 2015

3.3.2.a Head Quarters at Jaipur - Introduction to the Project Team - Any other documents that are available.

3.3.2.b. Visit to Zonal Office (Jodhpur) - Meet Zonal Chief Engineer and the officials responsible for implementation of the project, - Ascertain the environmental and social issues they have faced while construction of towers, - Discuss the land availability issue and if there are any grievances from the villages in the vicinity of the tower line. - Discuss procedure followed by RRVPNL with State Forest Department for forest area/cutting of trees under tower construction sites.

3.3.2.c. For Under Construction Transmission line Project - Meet site in-charge and discuss the environmental and social issues at time of construction. - Meet EPC contractor (Tata Projects Limited) Consultants) to discuss the monitoring systems at site. - Observe the site for physical attributes – distance from road, power evacuation point, potential for dust, violations of any habitat/protected area, encroachments into village lands etc. - Observe normal construction processes for dust generation, spillage of any construction related raw material, disposal of construction waste. - Observe conditions of worker amenities, health and safety issues, and physical installations for any environmental issues. - Observe availability of drinking water and disposal of waste-water, waste at site, disposal of scrap procedures. - Observe labour camps and notice living conditions for hygiene, and safe disposal of toilets and kitchen waste etc. - Observe the workshop, storage of oil, spare parts, etc. - Discuss the constitution of the worker group – labour, technical etc. and their native places. - Discuss if any violations regarding labour laws etc. have occurred or any accidents have happened in the past. - Observe the work performed at site by local labour contracts – tower foundations, 10 Environmental Audit Report and Corrective Action Plan for RRVPNL

construction material, vehicles, etc. - Procedure followed for cutting of trees in the right of way of under-construction site tower-line. - Meet local village representatives to ascertain the environmental and social issues being faced daily, - Discuss the grievance procedure used by EPC contractor/RRVPNL representatives with affected persons.

3.3.2.d. Visit to EPC contractor facilities - Visit the site and observe the environmental and social issues before design. - Inquire about water availability and usage of water boring systems, power availability, labour, housing etc. for technical/labour staff in the general area.

3.4 Documents, Findings and Consultation.

3.4.1 Inputs 3.4.1.1 Documents Collected 28. The documentation was reviewed to evaluate the extent to which the potential environmental impacts of the project have been assessed and the consistency of these assessments with the guidance prescribed in the ADS’s SPS 2009. This included the following key documents:

1. RREIT IEE Tranche 1- 2012 2. RREIP Environmental Assessment and Review Framework (EARF)

Jodhpur region of Transmission line 1. Notification of Transmission line 2. Forest Clearance letter 3. Topographical Maps prepared by Tata Projects Limited 4. Transmission Line Tower Approved Profile 5. Land Allocation documents for Ramgarh village, District Jaisalmer, Rajasthan

Shergarh Region of Transmission line 1. Notification of Transmission line 2. Forest Clearance letter 3. Topographical Maps prepared by Tata Projects Limited 4. Tower profile sheet

Jaisalmer Region of Transmission line 1. Notification of Transmission line 2. Forest Clearance letter 3. Topographical Maps prepared by Tata Projects Limited 4. Tower Profile sheet

3.4.1.2. Discussions with Personnel at project sites Rajasthan Rajya Vidyut Prasan Nigam Limited Zonal Office-Jodhpur 1. Mr. M.C. Purohit, Zonal Chief Engineer 2. Mr. B.C. Meena, Superintending Engineer (400 kV GSS) 3. Mr. M. K. Soni, Executive Engineer, (O&M 400 kV & GSS) 4. Mr. Bishnoi, JEN, 400 kV line –Jodhpur, Shergarh site 11 Environmental Audit Report and Corrective Action Plan for RRVPNL

5. Mr. N.K. Dagar, JEN 400 kV line – Jaisalmer site

Tata Power Limited (EPC Contractor) 1. Mr. Saurav Jain, Planning Engineer-400 kV Jodhpur section 2. Mr. Mahendra Singh, Planning Engineer 3. Mr. Subhranshu Das, Planning Engineer – 400 kV Shergarh section 4. Mr. K. Suresh Kumar, Planning Engineer – 400 kV Jaisalmer section

Head Quarters-Jaipur 1. Mr. A.K. Sharma, Superintending Engineer

3.4.2. Consultations at Transmission Tower sites

29. Consultation at tower locations between Jodhpur-Akal in the state of Rajasthan was conducted. The details are listed in Table 5 below:

Table 5: Consultation at Transmission Tower Project Sites (Rajasthan) No. Issues Participants’ Opinion, Comments and Suggestions 1 General perception about the project and the Since the towers were being erected, they were aware of the awareness about the proposed project. project and have had interaction with EPC contractor and RRVPN officials. 2 Support of local people for the proposed project Some persons were working as labour. 3 Any critical issue or concern by the local people No agricultural land being taken away. However they want the regarding the project payment for crop damage to be paid soon once the transmission line work is complete. 4 Employment Potential in the project which is of Labour for tower foundation benefit to village 5 Is the land Irrigated and what are the sources of Most land is rainfed (single season). Only some portion (25 km Irrigation? in length) has some borewell irrigation in Shergarh area. 6 Protected areas (national park, protected forest, None nearby, however some local deer in some areas etc. religiously sensitive sites, historical or archaeological sites), if any 7 Any key environmental issues such as dust, noise, Dust only when the wind is very strong. water, land, visual pollution that villages are objecting to. 8 Will the project siting adversely impact the water None or soil resource in the locality 9 Loss of residential/commercial structures, if any A minimum distance of 400-500 m distance has been kept from due to the project any residential/agricultural structure from any tower foundations. 10 Loss of community life like any Market Places or None community activities to be affected 11 Perceived benefits/loss from the project No loss is foreseen. However if the tower falls on the land near the highway, the rate of land goes down. 12 What other organizations of a social nature There are no NGO/CBO or civil society working in these area. (NGOs/CBOs/ Civil Society) active in the area? Name of these organizations 13 What are the major crops and how many crops Agriculture is mostly Bajra, Moong, Gwar, which are dependent you cultivate in a year. on rain. Once a year. 14 What are the most type of trees/shrubs in the area Trees in area – Ker, Babul, Kejri, Kankheda etc. 15 What is the average yielding of each crop per Mostly for local consumption, almost nil is sold in market. bigha and what is the market rate of the crop (per quintal) 16 Will the project affect migration pattern (If any), No migration from the area due to the project. However, there is inward or outward some migration (05 % to 10%) from the villages to the district headquarters for education, work and industries. 12 Environmental Audit Report and Corrective Action Plan for RRVPNL

No. Issues Participants’ Opinion, Comments and Suggestions 17 Any Other Issues you may want to share: Demand for power supply to be more regular in the area

3.4.2.1. Lists of the Participants and their occupation 30. Participants of the informal discussion held at the project sites and their occupation at Rajasthan is listed in Table 6 below.

Table 6: 400KV D/C Quad ACSR Moose Akal (Jaisalmer) – Jodhpur (New) Transmission Line Lists of the Participants and their occupation No Village Name of participants Occupation Location near Tower AP point 1 Khudala Village Mrs. Andai Wife of land owner Mr. Dhanaram Chaudhary and AP 76/3 and AP 76/2 mother of Mr. Laxman Chaudhary 2 Loonavas Harishachandra Farmer/Land owner AP 72/5 Khara 3 Mangilal Farmer/Land owner AP 73A&B 4 Magli Devi Farmer/Land owner 5 Viram 6 Kuldeep 7 Manglesh 8 Mr. Biddaram s/o Farmer/Land owner AP 73/0 Jaggaram 9 Mr. Narain SIngh 10 Korna village Mr. Deepa Ram AP 66/3 Chaudhury 11 Mr. Nema Ram Farmer/Land owner AP 66/2 12 Mr. Pukharam Farmer/Land owner AP 66/1 13 Mr. Sukharam Petty Sub-contractor of Tata Projects Limited 14 Mr. Mana Ram Farmer/Land owner AP 66/6 15 Mr. Anup Chaudhary Farmer/Land owner AP 66/5 16 Mr. Lakshman Ram Farmer/Land owner AP 26/6 17 Mr. Khushala Ram Farmer/ 18 Mr. Sonaram Singh Farmer/ 19 Mr. Poonaram Singh Farmer/ 20 Luna Kala Mr. Dham Singh Farmer/Land owner AP 20/0 village 21 Mr. Swaroop Singh Farmer/Land owner AP 20/0 22 Mr. Narayan Singh Farmer/Land owner AP 20/0 23 Mr. Ram Singh Farmer/Land owner AP 20/1, 2, 3 24 Mr. Ashish Singh Farmer/Land owner AP 20/1, 2, 3 25 Mr. Mukesh Tomar Land owner, Labour AP 20/1, 2, 3 26 Farmer/Land owner 27 Betina Mr. Ram Singh s/o Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 Padam Singh 28 Mr. Duryodhan Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 29 Mr. Kunuj Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 30 Mr. Pradeep Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 31 Mr. Prem Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 32 Mr. Tanerao Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 33 Mr. Gayad Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 34 Mr. Than Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 35 Mr. Khaman Singh Farmer/Land owner AP 17/12, 18/0, 18/1, 19/0 36 Mr. Bhum Singht Farmer/Land owner 37 Mehrajot Mr. Narayan Singh Farmer AP 14/3 38 Mr. Bhanwar Singh Farmer/Land owner AP 14/1 39 Achla New Mr. Padma Ram Farmer/Land owner AP 13/1 40 Mr. Khanim Ram Farmer/Land owner AP 13/2 41 Mr. Gaj Singh Farmer/Land owner AP 13/6 42 Mr. Nag Singh Farmer/Land owner AP 13/6 43 Mr. Nathu Singh Farmer/Land owner AP 13/6

13 Environmental Audit Report and Corrective Action Plan for RRVPNL

4.0 ENVIRONMENTAL MANAGEMENT PLAN (EMP) & BUDGET

31. RRVPNL has followed the standard GOI procedure for notifying the public about the erection of the tower line between Akal and Jodhpur Grid substations by publishing Rajasthan state’s Gazette Notification for Transmission Line Construction in Annexure 3 and also procuring Forest clearance for Transmission Line as attached in Annexure 4.

32. Tata Projects Limited, the EPC contractor has a corporate Environment Health and Safety (EHS) policy that is followed by all its EPC projects. The details of EPC Contractor Environment Health and Safety (EHS) Policy is listed in Annexure 5.

33. Following the Rajasthan states/GOI established procedure, RRVPNL has calculated and disbursed the Crop Compensation directly to the affected persons. This procedure is followed for all utilities companies across India where the affected person is compensated for any crop or tree that is damaged by each stage of construction of the line. Sample sheets for crop compensation are shown in Annexure 6.

4.1 Compliance with RRETIP EMP 34. The EARF agreed between RRVPNL and ADB which specifies the compliance process with applicable national and local laws and ADB’s SPS 2009 (SR1 for Environment) including avoiding and mitigating the environmental impacts of their existing operations as listed in RRETIP tranche 1 EMP. This EMP includes mitigation measures related to impacts on solid waste management plan, wastewater management plan, pollution prevention and abatement plan, emergency management plan, waste management plan, storm water management plan, occupation health and safety management plan, and wildlife management. The EMP and its environmental monitoring plan is then monitored by RRVPNL and the EPC contractor.

35. Annexure 7 shows photographs from site visit to transmission line. Aspects such as transmission line construction stages, EPC store, sub-contractor camp, ROW - General Crops and terrain in area, trees etc. and consultations with affected persons are shown in various photographs.

36. The RRETIP Tranche 1 (from IEE document) has been used to compare all aspects assessed for audit. Table 7 shows only the “transmission line construction aspects” from RRETIP EMP as a baseline review any compliance related issues with this under construction project.

37. For this compliance audit purposes, the transmission line towers have been considered as an associate facility on which the RRETIP funded conductor will be strung.

38. Associated facilities, as defined by ADB's SPS 2009 (Appendix 1, para. 6, p.31), "are not funded as part of the project (funding may be provided separately by the borrower/client or by third parties), and whose viability and existence depend exclusively on the project and whose goods or service are essential for successful operation of the project…"

14 Environmental Audit Report and Corrective Action Plan for RRVPNL

Table 7: Deviations from RRETIP EMP (Construction) for 400 kV Line Project Potential Mitigation Action Monitorin Standards/ Improveme Deviation Activity Environme g Scope Measuremen nt required ntal Impact t/ Frequency (Yes/No) Construction A. Physical Resources Site clearance Soil erosion Construction near seasonal rivers, Soil Visual No None and surface erosion and flood-prone areas erosion inspection runoff should be restricted to the non- (Turbidity and rainy season. sedimentation Provision and maintenance of ) drains and retention ponds. Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimise obstruction or destruction to natural drainage. Removal or Public Advance notice to the public about Disruption Technical No None disturbance to inconvenien the time and the duration of the to other specification other public ce utility disruption commercia utilities l and public Use of well trained and activities / experienced machinery operators Public to reduce accidental damage to the complaints public utilities

Restore the utilities immediately to overcome public inconvenience Surplus Runoff to Any excess material will only be Location Appropriate fill No None earthwork/soil cause water used as fill material offsite when and disposal and pollution, the owner's agreement has been amount dispersal solid waste obtained and with the disposal site (m3) of fill locations disposal restored in a manner that prevents disposal quarterly erosion and does not block any Soil drainage path disposal locations and volume (m3) B. Environment Resources Equipment Noise and Selection of construction Constructio Minimal No None layout and vibrations techniques and machinery to n ground installation minimise ground disturbance. techniques disturbance and Monthly machinery Provision of Contaminati Construction workforce facilities to Amenities Presence of Yes Open facilities for on of include proper sanitation, water for proper defecation construction receptors supply and waste disposal Workforce sanitation, by workers (land, facilities. facilities. water supply subcontract water, air). and waste or labour disposal facilities - Once. Mechanised Noise, Construction equipment to be well Constructio Technical No None construction vibration maintained. n specifications, and techniques safety operator and regulations, safety, Construction techniques and equipment Noise control efficient Machinery selection to minimize - estimated regulations- operation. ground disturbance. Proper noise Quarterly. maintenance and turning off plant emissions Noise, not in use. and vibration, operating equipment schedules. wear and tear. Construction of Increase in Existing roads and tracks used for Access Use of No Existing roads for airborne construction and maintenance roads, established village 15 Environmental Audit Report and Corrective Action Plan for RRVPNL

Project Potential Mitigation Action Monitorin Standards/ Improveme Deviation Activity Environme g Scope Measuremen nt required ntal Impact t/ Frequency (Yes/No) accessibility for dust access to the site wherever routes roads roads and sub stations particles. possible. (length and wherever cart tracks width of possible. used. Increased New access ways restricted to a access land minimum of single carriageway roads). Access requirement width. restricted to a for minimum of temporary single accessibility carriageway . width. C. Ecological Resources Site clearance. Vegetation. Marking of vegetation to be Vegetation Clearance No None removed prior to clearance, and marking strictly limited strict control on clearing activities and to target to ensure minimal clearance. clearance vegetation – control Once. (area in m2). Trimming/cuttin Loss of Trees that can survive pruning to Species- Presence of No None g of trees within vegetation comply should be pruned instead specific target species RoW. and of cleared. tree in RoW deforestatio retention following n. Felled trees and other cleared or as vegetation pruned vegetation to be disposed approved clearance. of as authorised by the statutory by bodies. statutory authorities (average and maximum tree height at maturity, in metres). Disposal of cleared vegetation as approved by the statutory authorities (area cleared in m2). Wood/ Loss of Construction workers prohibited Illegal Complaints by No None vegetation vegetation from harvesting wood in the project wood local people harvesting, and area during their employment. /vegetation or other cut and fill deforestatio harvesting evidence of operations n (area in illegal m2, harvesting . number of incidents reported). Effect on Prevent work force from disturbing Habitat Complaints by No None fauna the flora, fauna including hunting of loss. local people animals and fishing in water or other bodies. evidence of illegal hunting. Proper awareness programme regarding conservation of flora, fauna including ground vegetation to all workers. D. Human Environment Acquisition of Loss of Avoid farming/harvesting season Land area Loss of crops- No None cultivable agricultural/ for field crops wherever possible of work in post- lands. horticultural for the project activities. agriculture harvest period 16 Environmental Audit Report and Corrective Action Plan for RRVPNL

Project Potential Mitigation Action Monitorin Standards/ Improveme Deviation Activity Environme g Scope Measuremen nt required ntal Impact t/ Frequency (Yes/No) productivity. loss. but before Avoid construction/stringing during next crop – fruits season. Once per site. Constructio Ensure existing irrigation facilities n Schedule are maintained in working in non- condition. fruiting season. Protect /preserve topsoil and reinstate after construction Usage of completed. existing utilities. Repair /reinstate damaged bunds etc. after construction completed. Status of facilities Compensation for temporary loss (earthwork in agricultural production. in m3).

Implement ation of crop compensat ion (amount paid, dates, etc.). Temporary use Losses to Contract clauses specifying careful Contract Incorporating No None of land. neighbourin construction practices. clauses good g land uses/ Design construction values. As much as possible existing basis and management, access ways will be used. layout. design Reinstatem engineering Productive land will be reinstated ent of land practices. following completion of status Consultation construction. (area with affected affected, parties Compensation will be paid for loss m2). immediately of production, if any. Implement after ation of completion of tree/crop construction compensat and after the ion first harvest. (amount paid). Transportation Nuisance to Transport loading and unloading of Water, Air CPCB No None and storage of the general construction materials should not Quality and Emission materials. public. cause nuisance to the people by Noise standards and way of noise, vibration and dust. (dBA). Water Quality standards - Avoid storage of construction Quarterly. materials beside the road, around water bodies, residential or public sensitive locations.

Construction materials should be stored in covered areas to ensure protection from dust, emissions and such materials should be bundled in environment friendly and nuisance free manner. Temporary Loss of Advance notice to the public about Power Regular No None outage of the power the time and the duration of the disruption monitoring electricity supply to utility disruption. to houses during the the local and period of community Restore the utilities immediately to commercia strengthening

17 Environmental Audit Report and Corrective Action Plan for RRVPNL

Project Potential Mitigation Action Monitorin Standards/ Improveme Deviation Activity Environme g Scope Measuremen nt required ntal Impact t/ Frequency (Yes/No) when overcome public inconvenience. l premises. the distribution conductors lines crossing the new transmissio n line are switched off. Health and Injury and Contract provisions specifying Contract RRVPN and No None safety sickness of minimum requirements for clauses ADB Health workers and construction camps. (number of and safety members of incidents standards - the public. Contractor to prepare and and total Monthly. implement a health and safety plan lost-work and provide workers with required days PPE. caused by injuries Contractor to arrange for health and and safety awareness programmes sickness). including on AIDS and sexually transmitted diseases (STD). Capacity Improve Training of RRVPN Environment Training Number of No None Building standards and Social Cell. schedules. training of program - implementat Yearly. ion and monitoring.

4.2 Good Practices noticed during site visits. 39. During the site visits, some of the good practices being engaged by the EPC contractor were noticed. Table 8 lists some details:

Table 8: Summary of Good Practices noticed in the field in line with the RRETIP Environment Monitoring Plan of Tranche 1 Sno. Type of Issue Good Practice noticed 1 Restoration of land temporarily Proper stacking of top soil and stacking of affected construction material at site. Removal of complete construction material after tower construction. 2 Improvement of facilities at labour Proper storage of raw material – steel, cement camps machinery etc. for towers 3 Least impact on surrounding area of Detailed survey conducted using proper three tower construction alternatives method. 4 Prior clearances from respective Avoidance of any forest land in consultation government authorities with forest department. Notifications and No-objection of local authorities taken prior to construction 5 Affected Persons Using affected persons in labour force. Ensure proper measurement of potential affected area before construction

4.3 Improvements required noticed during site visits

40. Table 9 below provides the details of the project activities where the deviations from the 18 Environmental Audit Report and Corrective Action Plan for RRVPNL

RRETIP’s EMP for construction aspects has been noted during the environmental compliance audit.

Table 9: Summary of Improvement measure identified during site visit vs the RRETIP‘s Environment Monitoring Plan SNo. Types of Issues Improvement measures required 1 Top soil at tower footing left Leveling of land (topsoil) under the tower footing partially loose to enable after stringing of conductor compaction by rain at some tower locations. 2 Open defecation at temporary Erection of temporary toilet facility by sub- labour camps used by sub- contractor contractor’s labour.

4.4 EMP Budget 41. According to the RRETIP EARF, the following costs towards environmental mitigation which are incurred by RRVPNL mainly constitutes of:  Direct payments to the APs for Tree and crop compensation for temporary damages.  Implementation of EMP by EPC contractor for all construction related activities; the cost of which is included in the construction contracts award.

19 Environmental Audit Report and Corrective Action Plan for RRVPNL

5.0 Corrective Action Plan, Budget with Time Frame

5.1 Corrective Action Plan (CAP) 42. A Corrective Action Plan (CAP) has been proposed that includes all findings of environmental compliance audit such as impacts and respective measures to be implemented, and the consecutive budget/finance required for any additional mitigation actions proposed.

43. The review in Table 9 above demonstrates improvement in impacts of some activities during construction that require corrective action to be undertaken. These measures include restoration of land (topsoil) under the tower footing after stringing of conductor and temporary toilet facility erection by sub-contractor.

44. A Corrective Action Plan (CAP) has been proposed (shown in Table 10 below) that includes all findings of environmental compliance audit such as impacts and respective measures to be implemented, and the consecutive budget/finance required for any additional mitigation actions proposed.

5.2 Budget and Timeline 45. Most of the proposed corrective actions fall under the existing EPC contract. The Correction Action Plan to be implemented by RRVPNL shall be implemented by the EPC contractor as they are site specific.

46. RRVPNL is required to undertake the corrective action plan (CAP), including specific actions to be completed by the EPC contractor/sub-contractor and within the required deadline for each action as shown in Table 10 (column 2 gives the Improvements required from Table 9, column 3 gives the “Corrective Action”, column 4 describes “who has to take action” and column 5 gives “by when the action has to be undertaken”). Column 6 gives the costs required to resolve the action.

Table 10: Final Corrective Action Plan Proposed with Budget

No Issue Improvements Corrective Action By whom By when Costs required from Table 9 above 1 2 3 4 5 6 1 Top soil at tower # 1 Leveling of topsoil Contractor After Under footing left partially under the tower completion contractor’s loose to enable footing of stringing current compaction by rain of contract in some tower conductor locations. 2 Open defecation at # 2 Dig pit and then Contractor Immediately Under temporary labour cover with soil contractor’s camps used by sub- before moving to current contractor’s labour. next camp site contract

20 Environmental Audit Report and Corrective Action Plan for RRVPNL

6.0 SUMMARY AND CONCLUSION 47. The environmental compliance audit of the associated facility 400 kV D/C Quad ACSR Moose Akal (Jaisalmer) – Jodhpur (New) Transmission Line (under construction) was conducted as per RRETIP’s EARF document which is an agreed framework between RRVPNL and ADB that conforms to Government’s rules, regulations and standards and ADB’s SPS 2009 guidelines.

6.1 Summary Audit Findings and Corrective Action Plan 48. The findings of audit conducted is documented in Table 7, while Table 8 and Table 9 give the best practices followed and improvements required respectively. Table 10 provides the CAP. Several photographs in Annexure 7 are attached that document the above observations.

49. Finally, the Compliance audit conducted identifies the following strengths and weaknesses of RRVPNL:

Strengths 50. RRVPNL has taken suitable steps for meeting environmental and social compliance as per Government of India, state government through their respective forest departments and the district revenue officials. It is therefore felt that ADB’s SPS 2009 requirements can be fully met by the company.

51. Engagement of RRVPNL and EPC contractor/sub-contractor with its community and affected persons in the immediate project area related to environmental aspects is satisfactory.

52. RRVPNL has an operational contracting system with its EPC contractor. Responsibilities of the EPC contractor/sub-contractors with regards to the mandatory EHS compliance requirements in their contracts with RRVPNL are proper. Furthermore, RRVPNL keeps sufficient monetary (fiscal) incentives/dis-incentives to ensure compliance with RRETIP’s EMP.

Weaknesses: 53. RRVPNL needs to hire one trained Environment and Social professional at PMU to assist in safeguard monitoring as per ADB requirements including monitoring and reporting on the environmental compliance with applicable national laws.

54. Documentation at the field office regarding compliance level environmental monitoring and audit of EMP activities needs to be maintained.

6.2 Output/outcome 55. Environment: The proposed scope change in RRETIP Tranche 1 of RRVPNL is expected to be classified as environment category B under the ADB’s SPS 2009.

56. Land-use: There are neither forestlands nor private lands that have been procured by the government within the identified tower sites. The land is mostly agricultural in nature that is not irrigated from canals; but rather based on rains in the area. The single season crops are mostly Bajra, Moong, Til and Gwar, etc. During the audit, it was confirmed with affected persons were consulted by RRVPNL, EPC contractor and district revenue officials during the measurements of crop damage and calculation of payable amounts to each of them.

57. Health and Safety: Proper health and safety systems are being followed by the EPC contractor which are documented in their corporate declarations.

21 Environmental Audit Report and Corrective Action Plan for RRVPNL

ANNEXURE-1

(APPLICABLE ENVIRONMENTAL LAWS, REGULATIONS AND ADB SPS 2009) Annexure 1

Summary of national, local, and any other applicable environmental laws, regulations, and standards and ADB SR 1 A1.1 Environmental Regulatory and Policy Framework Selection

9. Government of India, (GoI), State Governments, State Pollution Control Boards and ADB’s SPS 2009 policies and procedures apply to all projects. Solar Photovoltaic Power generation projects are normally classified by ADB as Category B, and distribution projects are normally classified as Category B or C. Category A may apply to projects located in environmentally sensitive areas1. For each major investment component, an Environment and Social Impact Assessment (ESIA) will be prepared by RRVPNL following ADB’s Safeguard Policy Statement, 2009, Environmental Assessment Guidelines, 2003 and applicable National environmental laws and regulations. Based on these ESIA reports, the environmental management plan (EMP) and a corresponding budget will be prepared for each sub-project.

A1.2. National/Local Government Environment Classification

10. Under the GoI’s Environment Impact Assessment (EIA) Notification 2009, the environmental classification of projects is determined by Ministry of Forest and Environment (MoEF),GoI and there are two possible outcomes:

 Category A: A project is classified as Category A if it is likely to have significant negative impacts and is thus one of the types of project listed in this category in the EIA Notification. Such projects require EIA, plus Environmental Clearance (EC) from MoEF;

 Category B: A project is classified as Category B if it is likely to have fewer negative impacts and is listed in this category in the EIA Notification. These projects require EC from the State Environment Impact Assessment Authority (SEIAA), who classify the project as B1 (requiring EIA) or B2 (no requiring EIA), depending on the level of potential impacts. Projects classified as B2 require no further study.

11. As per EIA Act 2009, Solar Photovoltaic Power Generation projects are not listed as environmental sensitive project and no clearance is required from State Pollution Control Board (PCB) or MoEF. Clearance from Forest department is required only in case where project is constructed on forest-land or requires cutting of any forest tree/trees or passes through buffer zone of a sanctuary and/or national park.

12. Some of the relevant GoI Regulations and Acts are as follows; (i) The Electricity Act, 2003 (ii) The Water (Prevention and Control of Pollution) Act, 1974, amended 1988 (iii) The Water (Prevention and Control of Pollution) Rules, 1975 (iv) The Air (Prevention and Control of Pollution) Act 1981, amended 1987 (v) The Air (Prevention and Control of Pollution) Rules, 1982 (vi) The Environment (Protection) Act, 1986, amended 1991 and including the following Rules/Notification issued under this Act.  The Environment (Protection) Rules, 1986, including amendments  The Municipal Solid Wastes (Management and Handling) Rules, 2000  The Hazardous Wastes (Management and Handling) Rules, 2003  The Hazardous Wastes (Management, Handling and Trans-boundary Movement) Rules 2009  The Bio-Medical Waste (Management and Handling) Rules, 1998

1 Environmentally-sensitive areas include National Parks, Wildlife Sanctuaries, Bio-reserve zones, Eco Sensitive Zones, or wetlands as declared by GoI and areas declared as heritage sites. Environment and wildlife Department’s approval is required for right-of-way and sites located in reserved forests, wildlife preserves, national parks, and other designated sensitive areas  Noise Pollution (Regulation and Control) Rules, 2000,  Wild Life (Protection) Amendment Act, 2002  Ozone Depleting Substances (Regulation & Control) Rules, 2000.  The Biological Diversity Act, 2002;  The Environment Impact Assessment Notification, 1994; amended up to 2009;  Batteries (Management & Handling) Rules, 2001  The Environmental Clearance Notification, 1994 (vii) Noise Pollution (Regulation and Control) Rules, 2000 (viii) The Indian Wildlife (Protection) Act, 1972, amended 1993 (ix) The Wildlife (Protection) Rules, 1995 (x) The Indian Forest Act, 1927 (xi) Forest (Conservation) Act, 1980, amended 1988 (National Forest Policy, 1988)  Forest (Conservation) Rules, 1981 amended 1992 and 2003  Guidelines for diversion of forest lands for non-forest purpose under the Forest (Conservation) Act, 1980 (xii) The National Environmental Appellate Authority Act, 1997 (xiii) The National Green Tribunal Act, 2010 (xiv) The Building and Other Construction Workers’ (Regulation of Employment and Conditions of Service) Act 1996 (xv) Central Electricity Authority (Safety Requirements for Operation, Construction and Maintenance of Electric Plants and Electrical Lines) Regulations 2008 (xvi) Workmen’s Compensation Act, 1923 & Rules 1924 (xvii) Employers’ Liability Act No. 24 of 1938 (xviii) The Contract Labor (Regulation and Abolition) Rules, 1971 (xix) CGWA Notification No.21-4/Guidelines/CGWA/2009-832 dated 14th October 2009

A1.3. Other Relevant Acts of Government of Rajasthan

 The Rajasthan Monuments, Archaeological Sites and Antiquities Act, 1961, Amended by Raj. Act No. 6 of 2006.  The Rajasthan Land Acquisition Act, 1953, Amended by Rajasthan Act Nos. 27 of 1957, 40 of 1960, 8 & 21 of 1962, 22 of 1966, 15 of 1981 and 8 of 1987.  The Rajasthan Religious Buildings and Places Act, 1954, Amended by Rajasthan Act Nos. 27 of 1957 and 8 of 1962.  The Rajasthan Irrigation and Drainage Act, 1954, Amended by Rajasthan Act Nos. 21 of 1960 and 8 of 1962.  The Rajasthan Agricultural Lands Utilization Act, 1954, Amended by Rajasthan Act Nos. 27 of 1957, 28 of 1960 and 8 of 1962.  The Rajasthan Forest Act, 1953, Amended by Rajasthan Act No.27 of 1957.  The Rajasthan Land Revenue Act, 2003.  Rajasthan Gazette Extraordinary Notification dated 24/6/2010 issued by Department of Environment.

A1.4 ADB Prohibited Investment Activities List (PIAL)

The following type of projects do not qualify for Asian Development Bank financing: (i) production or activities involving harmful or exploitative forms of forced labor2 or child labor3;' (ii) production of or trade in any product or activity deemed illegal under host country laws or regulations or international conventions and agreements or subject to international phase outs or bans, such as (a) pharmaceuticals4, pesticides, and

2 Forced labor means all work or services not voluntarily performed, that is, extracted from individuals under threat of force or penalty 3 Child labor means the employment of children whose age is below the host country's statutory minimum age of employment or employment of children in contravention of International Labor Organization Convention No. 138 "Minimum Age Convention" (www.ilo.org). 4 A list of pharmaceutical products subject to phaseouts or bans is available at http://www.who.int. herbicides5,(b) ozone-depleting substances6, (c) polychlorinated biphenyls7 and other hazardous chemicals8, (d) wildlife or wildlife products regulated under the Convention on International Trade in Endangered Species of Wild Fauna and Flora9, and (e) trans-boundary trade in waste or waste products10; (iii) production of or trade in weapons and munitions, including paramilitary materials; (iv) production of or trade in alcoholic beverages, excluding beer and wine11; (v) production of or trade in tobacco; (vi) gambling, casinos, and equivalent enterprises; (vii) production of or trade in radioactive materials12, including nuclear reactors and components thereof; (viii) production of, trade in, or use of unbonded asbestos fibers13; (ix) commercial logging operations or the purchase of logging equipment for use in primary tropical moist forests or old-growth forests; and (x) marine and coastal fishing practices, such as large-scale pelagic drift net fishing and fine mesh net fishing, harmful to vulnerable and protected species in large numbers and damaging to marine biodiversity and habitats.

A1.5 Asian Development Bank’s Environment Classification

13. The proposed project will be classified as one of the following categories on any of the three safeguards (environment, involuntary resettlement and indigenous peoples) as per ADB’s Safeguard Policy Statement 2009:

Category A: Environment - The project has potential significant adverse social or environmental impacts which may be diverse, irreversible or unprecedented. These impacts may affect an area larger than the sites or facilities subject to physical works.

Category B: Environment - The project has limited potential adverse social or environmental impacts that are few in number, generally site-specific, largely reversible, usually evident at the time of the assessment, and readily addressed through mitigation measures, which typically require a limited or focused environmental and/or social assessment, or straight- forward application of environmental siting, pollution standards, design criteria, or construction standards.

Category C: Environment - The project has minimal or no adverse social or environmental impacts, which are not generally subject to further assessment (beyond their identification as such) except for the requirements for customer certification/disclosure of compliance/non- compliance with local and national environmental, health and safety and labour laws and regulations.

14. Based on the category of the investment, the applicable requirements are summarized. For projects that are categorized as A or B with respect to environment (i)

5 A list of pesticides and herbicides subject to phaseouts or bans is available at http://www.pic.int. 6 A list of the chemical compounds that react with and deplete stratospheric ozone resulting in the widely publicized ozone holes is listed in the Montreal Protocol, together with target reduction and phaseout dates. Information is available at http://www.unep.org/ozone/montreal.shtml. 7 A group of highly toxic chemicals, polychlorinated biphenyls are likely to be found in oil-filled electrical transformers, capacitors, and switchgear dating from 1950 to 1985. 8 A list of hazardous chemicals is available at http://www.pic.int. 9 A list is available at http://www.cites.org. 10 As defined by the Basel Convention; see http://www.basel.int. 11 This does not apply to investee companies who are not substantially involved in these activities. Not substantially involved means that the activity concerned is ancillary to an investee company's primary operations. 12 This does not apply to the purchase of medical equipment, quality control (measurement) equipment, and any equipment for which ADB considers the radioactive source to be trivial and adequately shielded. 13 This does not apply to the purchase and use of bonded asbestos cement sheeting where the asbestos content is less than 20%. Safeguards Requirement (SR) 1 of the ADB Safeguard Policy Statement will apply, including preparation of an Environmental Impact Assessment (EIA)/Initial Environmental Examination (IEE) report. The safeguard requirements are summarized in Table 8 below.

Table 8: Safeguards Requirements Category Environmental Safeguards (Risk Rating) Category A (with potential Comply with (i) ADB’s PIAL and (ii) Safeguard Requirements 1 of the ADB Safeguard Policy a/ significant impacts) Statement, including EIA preparation & submission, and (iii) national laws Review and Web Disclosure Corporate Level: Procedures Submit to ADB for review Environmental Safeguards Compliance Audit and Corrective Action Plan and for disclosure on ADB website prior to disbursement. Submit the semi-annual monitoring report of projects to ADB for disclosure on ADB/RRVPNL website. Project Level Submit EIA to ADB for review and clearance, and for 120-day disclosure on ADB website prior to project approval. Category B (with less Comply with PIAL and (i) Safeguards Requirements 1 of the ADB Safeguard Policy Statement, significant impacts) including IEE preparation & submission, and (ii) compliance with national laws Review and Web Disclosure Corporate Level Procedures Submit to ADB for review Environmental Safeguards Compliance Audit and Corrective Action Plan and for disclosure on ADB website prior to disbursement. Submit to ADB the annual monitoring report of projects disclosed on ADB/RRVPNL for public disclosure. Project Level Submit the IEE to ADB for review and clearance, and disclosure of IEE prior to disbursement. Category C (with minimal Comply with national laws and ADB’s PIAL or no impacts) a/Typically RRVPNL investments are category B on environment. In case a project will be category A on environment, such investment will be not be financed under this ADB investment.

A1.7 Equivalence of ADB SPS 2009 with Government of India laws, regulations 15. As a normal business practise, RRVPNL follows the GOI, state government and local laws and regulations. Table 9A provides a brief write up on the equivalence of the current GoI Environmental Rules and Regulations and ADB Safeguard Policy Statement 2009. This equivalence table is taken from ADB’s document - TA 6285-REG: Strengthening Country Safeguard Systems - Preliminary Country Safeguard Review for India: Environmental Safeguard (February 2011). Table 9A: Equivalence of the GoI Environmental Rules and Regulations and ADB Safeguards Policy Statement 2009 N ADB’s SPS 2009 Indian Laws Equivalence Comments Changes recommended for o full equivalence 1 Use a screening process for each proposed The Environment (Protection) Act, Full The Environment (Protection) Act, 1986. project, as early as possible, to determine the 1986. National Environmental Policy 2006. appropriate extent and type of environmental National Environmental Policy The Environment Impact Assessment assessment, so that appropriate studies are 2006. Notification, 1994 and amended up to undertaken commensurate to the significance of The Environment Impact 2009. potential impacts and risks. Assessment Notification, 1994 and National Environmental (Ambient Air, amended up to 2009. Water Quality and Noise) Standards, National Environmental (Ambient CPCB. Air, Water Quality and Noise) Standards, CPCB. 2 Conduct an environmental assessment for each The Environment Impact Partial The EPA and EIA Notification do not The legal framework should proposed project to identify potential impacts and Assessment Notification, 1994 and require that an environmental be revised to require that the risks on physical, biological, socio-economic amended up to 2009. assessment address impacts on physical EIA process addresses (including health and safety), and physical cultural cultural resources, trans-boundary and impacts on physical cultural resources in the context of the project’s area of global impacts, including climate change. resources, trans-boundary influence. Assess potential trans-boundary and Nor are there any provisions for use of and global impacts, including global impacts, including climate change. Use strategic environmental assessment climate change and to use strategic environmental assessment where where appropriate. strategic environmental appropriate. assessment where appropriate. 3 Examine financially and technically feasible National Environmental Policy, Partial Although the EIA Notification requires The legal framework should alternatives to the project location, design, 2006. that the EIA document examine be revised to require technology and components, their potential The Environment Impact alternatives and provide an overall consideration of the no project environmental and social impacts, and document Assessment Notification, 1994 and justification for the project it does not alternative as part of the EIA the rationale for selecting the particular amended up to 2009. require consideration of the process and documentation. alternative(s) proposed, where relevant. The no environmental implications of the “no project alternative will be also considered. project” alternative. 4 Avoid and, where avoidance is not feasible, National Environmental Policy, Partial Although the EIA Notification requires The legal framework should minimize, mitigate and/or offset for adverse impacts 2006. that the EMP address the “administrative be revised to require that the and enhance positive impacts through aspects” of proposed that mitigative EMP address reporting environmental planning and management. Prepare measures, it does not require that the requirements, capacity an environmental management plan (EMP) or EMP address reporting requirements, development and training equivalent planning document(s) that includes the capacity development and training measures, implementation proposed mitigation measures, environmental measures, implementation schedule, cost schedule, cost estimates or monitoring and reporting requirements, related estimates or performance indicators performance indicators institutional or organizational arrangements, capacity development and training measures, implementation schedule, cost estimates and performance indicators. 5 Carry out free, prior and informed consultation with The Environment Impact Partial The EIA Notification is fully equivalent The legal framework should affected people and facilitate their informed Assessment Notification, 2006 and with this Policy Principle with the be revised to include specific participation. Ensure women’s participation in amended up to 2009. exception of any specific provisions to provisions to ensure women’s consultation. Involve stakeholders, including The National Environment ensure women’s participation in the participation in the EIA project-affected people and concerned NGOs early Appellate Authority Act, 1997 consultation process consultation process in the project preparation and ensure that their views and concerns are made known and understood by decision makers and taken into N ADB’s SPS 2009 Indian Laws Equivalence Comments Changes recommended for o full equivalence account. Continue consultations with stakeholders throughout project implementation as necessary to address environmental assessment-related issues. Establish a grievance mechanism to receive and facilitate resolution of the affected people’s concerns and grievances regarding the project’s environmental performance. 6 Disclose draft environmental assessments The Environment Impact Full Executing Agency to facilitate resolution (including EMP) before project appraisal, in a form, Assessment Notification, 1994 and of affected people’s concerns. manner and language(s) accessible to affected amended up to 2009. Component of IEE report. Grievance people and other stakeholders. redress mechanism-addressed in accordance with the ADB requirement. 7 Implement the EMP and monitor its effectiveness. Public consultation and disclosure Partial There is no requirement for public The legal framework should Document monitoring results, including as per Indian EIA Act 2006. disclosure of EMP monitoring results. be revised to include a development and implementation of corrective The Environment (Protection) Act, Public consultation and disclosure as per requirement for periodical actions, and disclose periodic progress reports. 1986 Indian EIA Act 2006. disclosure of monitoring ADB’s SPS 2009 requires disclosure of results EIA14, IEE, Environmental Assessment and Review Framework (EARF) and Environmental Monitoring Reports 8 Do not implement project activities that involve or Environmental Protection Rules Full ADB requires Environmental Monitoring are likely to result directly or indirectly in the 1986 (EPR) Plan for monitoring of mitigation of significant conversion or degradation of critical Indian Forest Act of 1927 (Forest environmental impacts. habitats. If a project is located within a legally Act) State Environmental Appraisal protected area, implement additional programs to The Forest (Conservation) Act, Committee (SEAC) releases guidelines promote and enhance the conservation aims of the 1980 and recommendations for the mitigating protected area. If the project has the potential to The Wild Life (Protection) Act, 1972 environmental impacts. adversely impact non-critical habitats, proceed only Biodiversity Act of 2002 if there are no technically and financially feasible The Biological Diversity Act, 2002 alternatives, overall benefits from the project substantially outweigh the environmental costs, and any conversion or degradation is appropriately mitigated. Use a precautionary approach to the use, development and management of renewable natural resources. 9 Application of pollution prevention and control The Water (Prevention and Control Full ADB requires Environmental Monitoring technologies of Pollution) Act, 1974 as amended; Plan for monitoring and mitigation of The Air (Prevention and Control of environmental impacts and risks. Pollution) Act, 1981 as amended SEAC releases specific guidelines and Environmental Standards published recommendations for the mitigation of by Central Pollution Control Board environmental impacts relevant to each (CPCB) and State Pollution Control project Board (SPCB) Water (Prevention And Control Of Pollution) Rules, 1975 Insecticide Act of 1968

14 a draft full EIA (including the draft EMP) at least 120 days prior to ADB Board consideration, and/or environmental assessment and review frameworks before project appraisal N ADB’s SPS 2009 Indian Laws Equivalence Comments Changes recommended for o full equivalence Ministry of Commerce and Industry (Department of Commerce) Directorate General of Foreign Trade Public Notice No 72 (Re-2003)/2002-2007, July 2004 10 Provide workers with safe and healthy working The Environment Impact Full Appropriate extent of workers safety and conditions, and prevent accidents, injury, and Assessment Notification, 1994 and the health discussed under the EMP disease. Establish preventive and emergency amended up to 2009. preparedness and response measures to avoid, National Policy on Safety, Health and where avoidance is not feasible, to minimize and Environment at Work Place the adverse impacts and risks to the health and The Public Liability Insurance Act, safety of the local communities. 1991 11 Conserve physical cultural resources (PCR) and Environmental Protection Rules Partial There are no provisions that require pre- The EIA Notification should be avoid their destruction or damage by using field 1986 approved procedures for “chance finds” revised to include a provision based surveys with qualified and experienced The Environment Impact for chance finds within the EIA or PCR requiring pre-approved expert(s) during environmental assessment. Assessment Notification, 1994 and legal framework. procedures for “chance finds” Provide for the use of “chance find” procedures that amended up to 2009. of PCR. include a pre-approved management and The Ancient Monument and conservation approach for materials that may be Archaeological Sites and remains discovered during project implementation. (Amendment and Validation) Act, 2010 ANNEXURE-2

(ALTERNATE ANALYSIS FOR TRANSMISSION LINE) Annexure 2:

Table 2A,1 Alternate Analysis of 400 kV D/C Moose Akal-Jodhpur Transmission Line Details of the Transmission Line Route from the Actual Survey SNo Description Alternative Route-1 Alternative Route-2 Alternative Route-3 1. Route Particulars i) Length(Km) 221.564 225.85 228.024 ii) Terrain 85 % Plain 80 % Plain 82 % Plain 15 % Undulations 20 % Undulations 18 % Undulations 2 Environment Details i) Name of District/District Detail Jodhpur, Barmer, Jodhpur, Barmer, Jodhpur, Barmer, (through which line passes) Jaisalmer Jaisalmer Jaisalmer ii) Town in alignment (nearby) Jodhpur, Luni, Jodhpur, Luni, Jodhpur, Luni, Baleser, Tena, Baleser, Tena, Baleser, Tena, Shergarh, Bhulsun, Shergarh, Bhulsun, Shergarh, Bhulsun, Bhainsra, Jaisalmer Bhainsra,Jaisalmer Bhainsra,Jaisalmer iii) Forest Involvement in Ha/kms NIL NIL NIL iv) Type of forest NIL NIL NIL v) Density of forest NIL NIL NIL vi) Type of Flora NIL NIL NIL vii) Type of fauna Camel, Cat, Dog, Camel, Cat, Dog, Cow, Camel, Cat, Dog, Cow, Cow, etc etc etc viii) Endangered species( if any) Nil Nil Nil ix) Historical/Cultural Monument Nil Nil Nil x) Any other relevant information Nil Nil Nil 3. Compensation Cost ( in Rs lakhs) i) Crop (Non-Forest) 1593.28 1751.79 1791.04 ii) Forest (CA+NPV) Nil Nil Nil 4. No. of Crossing (Nos.) i) Railway line 1 1 1 ii) Power Line 9 9 9 iii) River Crossing etc. 2 1 1 iv) Highway Crossing (NH/SH) 5 7 6 5. Construction Problem Easy approach. No Moderate Approach. Maximum forest forest Involvement. More forest Involvement. Moderate Less ROW Problems involvement. Moderate ROW problem. ROW problems. 6. O&M Problem O & M shall be O & M shall be difficult O & M shall be difficult relatively easier due due to more due to more to better approaches. undulations. undulations. 7. Overall Remarks Easy accessibility More forest Comparatively more less ROW problems involvement & forest involvement & & Nil forest moderate ROW moderate ROW involvement, problems, More problems, Maximum Minimum Crossings. Crossings. Crossings. 8. Number of towers planned 600 625 640 9. Will private land be required for No No No tower footing? If yes, how much?

 The three alignments have been shown in the following PLATES 1-6.  The Green Line (Route 1) is final line alignment used for the tower erection.  Table 2A.2 gives details of current state of construction  Table 2A.3 provides Tower schedule for the entire line. PLATE NO 1 – AKAL SUBSTATION TO AP 13 PLATE NO 2 – AP 14 - AP 22 PLATE NO 3 – AP 23 - AP 35 PLATE NO 4 – AP 31 - AP 60 PLATE NO 4 – AP 55 - AP 76 PLATE NO 4 – AP 73 – JODHUPUR (NEW) SS Table 2A.2 Inventorisation details of Power Transmission Line 230 km 400 kV (D/C) (Quad) double circuit RRVPNL (under Construction from Akal substation of RRVPNL to 400 kV Jodhpur (New) substation of RRVPNL Detail Survey Tower Schedule

Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 1 AP3/0 DD+6 155 26°49'17.61"N 71°04'43.53"E Akal NA 155 132KV S/C LINE 2 AP4/0 DD+3 26°49'20.11"N 71°04'48.47"E Akal NA 400 3888 3 4/1 DA+0 NA 355 4 4/2 DA+0 NA 350 FENCING 5 4/3 DA+0 NA 380 FENCING 6 4/4 DA+0 NA 325 7 4/5 DA+0 NA 360 8 4/6 DA+0 NA 360 9 4/7 DA+0 NA 360 10 4/8 DA+0 NA 310 33 KV LINE 11 4/9 DA+0 NA 340 CART TRACK 12 4/10 DA+0 NA 348 13 AP5/0 DB+0 1532 26°48'49.04"N 71°07'04.89"E Akal NA 355 33 KV LINE , NALA , CART TRACK 14 5/1 DA+0 NA 400 NALA , POND 15 5/2 DA+6 NA 399 33 KV LINE , 2 NO. CART TRACK 16 5/3 DA+3 NA 378 17 AP5A/0 DB+0 3016 26°48'41.80"N 71°07'59.80"E Akal NA 335 CART TRACK , 11 KV LINE 18 5A/1 DA+0 NA 338 33 KV LINE , CART TRACK 19 5A/2 DA+3 NA 370 20 5A/3 DA+0 NA 320 2 NO. CART TRACK 21 5A/4 DA+0 NA 295 CART TRACK 22 5A/5 DA+0 NA 300 FENCING 23 5A/6 DA+0 NA 365 11 KV LINE Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 24 5A/7 DA+0 NA 385 FENCING 25 5A/8 DA+0 NA 308 FENCING , CART TRACK 26 AP6/0 DC+0 2956 26°48'21.24"N 71°09'46.29"E Uggam Singh Deo Ki Dani NA 295 33 KV LINE , CART TRACK 27 6/1 DA+3 NA 390 28 6/2 DA+0 NA 360 FENCING 29 6/3 DA+0 NA 300 33 KV LINE , FENCING , 11 KV LINE, FENCING 30 6/4 DA+0 NA 330 FENCING 31 6/5 DA+0 NA 360 ROAD 32 6/6 DA+0 NA 350 33 6/7 DA+0 NA 355 34 6/8 DA+3 NA 216 35 AP7/0 DB+0 3670 26°47'20.50"N 71°11'08.93"E Badoda NA 360 36 7/1 DA+0 NA 390 37 7/2 DA+0 NA 350 38 7/3 DA+0 NA 370 39 7/4 DA+0 NA 370 40 7/5 DA+0 NA 370 41 7/6 DA+0 NA 365 42 7/7 DA+0 NA 365 43 7/8 DA+0 NA 365 44 7/9 DA+0 NA 365 45 AP8/0 DB+0 1871 26°45'48.59"N 71°12'34.31"E Badoda NA 380 46 AP8/1 DA+0 NA 370 FENCING 47 AP8/2 DA+0 NA 350 48 AP8/3 DA+0 NA 390 FENCING , CART TRACK Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 49 AP8/4 DA+0 NA 381 11 KV LINE , CART TRACK 50 AP9/0 DC+0 755 26°45'03.50"N 71°13'19.80"E Fatesar NA 355 51 09/1 DA+0 NA 400 52 9A/0 DD+18 2866 NA 299 53 9A/1 DA+0 NA 385 54 9A/2 DA+6 NA 285 55 9A/3 DA+0 NA 378 CART TRACK 56 9A/4 DA+0 NA 395 57 9A/5 DA+0 NA 360 11 KV LINE 58 9A/6 DA+0 NA 385 59 9A/7 DA+0 NA 379 60 AP9B/0 DB+0 1827 26°44'08.01"N 71°15'15.40"E Fatesar NA 370 61 9B/1 DA+0 NA 380 62 9B/2 DA+0 NA 360 63 9B/3 DA+0 NA 360 64 9B/4 DA+0 NA 357 11 KV LINE 65 AP10/0 DB+0 2907 26°43'50.73"N 71°16'18.64"E Sauta NA 380 66 10/1 DA+0 NA 380 67 10/2 DA+0 NA 360 68 10/3 DA+0 NA 340 69 10/4 DA+0 NA 350 70 10/5 DA+0 NA 365 71 10/6 DA+0 NA 350 72 10/7 DA+0 NA 382 NALA 73 AP11/0 DC+0 1841 26°43'47.03"N 71°18'03.66"E Rasla Village Grazing land-Gochur NA 375 CART TRACK 74 11/1 DA+0 Rasla Village NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 385 CART TRACK 75 11/2 DA+0 Rasla Village Grazing land-Gochur NA 400 NALI 76 11/3 DA+0 Rasla Village Grazing land-Gochur NA 284 77 11/4 DA+3 Rasla Village Grazing land-Gochur NA 397 78 AP11A/0 DB+0 3041 26°43'17.46"N 71°19'01.68"E Rasla Village Grazing land-Gochur NA 355 79 11A/1 DA+0 NA 365 80 11A/2 DA+0 NA 340 CART TRACK 81 11A/3 DA+0 NA 380 NALI 82 11A/4 DA+0 NA 300 KABRISTAN 83 11A/5 DA+0 NA 300 ROAD , 2 NO. 11 KV LINE 84 11A/6 DA+0 NA 340 CART TRACK 85 11A/7 DA+0 NA 330 86 11A/8 DA+0 NA 331 87 AP11B/0 DB+0 2295 26°42'23.69"N 71°20'33.96"E Rasla NA 385 88 11B/1 DA+0 NA 380 89 11B/2 DA+0 NA 390 WATER AREA , CART TRACK 90 11B/3 DA+0 NA 385 11 KV LINE , CART TRACK , ROAD , NALA 91 11B/4 DA+0 NA 390 CART TRACK 92 11B/5 DA+0 NA 365 93 AP12/0 DB+0 2193 26°41'52.39"N 71°21'49.31"E Achala NA 360 94 12/1 DA+0 NA 360 95 12/2 DA+0 NA 360 96 12/3 DA+0 NA 350 97 12/4 DA+0 NA 380 98 12/5 DA+0 NA 383 99 AP12A/0 DB+0 748 26°41'27.97"N 71°23'03.93"E Achala NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 370 100 12A/1 DA+0 NA 378 101 AP13/0 DB+0 26°41'23.00"N 71°23'30.25"E New Achala NA 385 102 13/1 DA+0 NA 385 CART TRACK 103 13/2 DA+0 NA 380 104 13/3 DA+0 NA 380 2 Nos. CART TRACK 105 13/4 DA+0 New Achala Private Bajra NA 380 106 13/5 DA+0 New Achala Private Bajra NA 375 107 13/6 DA+0 New Achala Private Bajra NA 375 CART TRACK 108 AP14/0 DB+0 2651 26°40'47.66"N 71°24'57.93"E Mehrajot,Moti Singh Ki Dani Private Bajra NA 370 109 14/1 DA+0 Mehrajot,Moti Singh Ki Dani Private Moong, Til Gwar NA 385 110 14/2 DA+0 Mehrajot,Moti Singh Ki Dani Private Moong, Til, Gwar NA 355 111 14/3 DA+0 NA 385 CART TRACK 112 14/4 DA+0 NA 390 113 14/5 DA+0 NA 385 114 14/6 DA+0 NA 381 CART TRACK 115 AP15/0 DB+0 3803 26°40'5.17"N 71°26'21.36"E Mehrajot,Sagad Singh Ki NA Dani 360 116 15/1 DA+0 NA 360 CART TRACK 117 15/2 DA+0 NA 355 118 15/3 DA+0 NA 355 119 15/4 DA+0 NA 395 2 Nos.CART TRACK 120 15/5 DA+3 NA 394 CART TRACK 121 15/6 DA+0 NA 389 CART TRACK 122 15/7 DA+3 NA 399 CART TRACK 123 15/8 DA+0 NA 399 124 15/9 DA+3 NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 397 CART TRACK 125 AP16/0 DC+0 1518 26°39'2.53"N 71°28'20.1"E Bhainsara,Khowaso Ki Dani NA 365 CART TRACK 126 16/1 DA+0 NA 365 FENCING 127 16/2 DA+0 NA 395 CART TRACK 128 16/3 DA+0 NA 393 CART TRACK 129 AP17/0 DB+0 4993 26°38'56.61"N 71°29'14.38"E Kajasar,Cheojir Ki Dani NA 385 130 17/1 DA+0 NA 385 CART TRACK 131 17/2 DA+0 NA 385 132 17/3 DA+0 NA 385 FENCING , CART TRACK 133 17/4 DA+0 NA 385 CART TRACK 134 17/5 DA+0 NA 385 135 17/6 DA+0 NA 385 CART TRACK 136 17/7 DA+0 NA 385 CART TRACK 137 17/8 DA+0 NA 385 138 17/9 DA+0 NA 375 CART TRACK , 33 KV LINE 139 17/10 DA+0 NA 385 CART TRACK , ROAD 140 17/11 DA+0 NA 385 141 17/12 DA+0 Betina Private Bajra NA 383 LT LINE 142 AP18/0 DB+0 759 26°38'11.25"N 71°32'7.81"E Betina Private Bajra NA 365 11 KV LINE 143 18/1 DA+3 Betina Private Bajra NA 394 144 AP19/0 DC+0 1151 26°38'0.19"N 71°32'32.43"E Betina NA 365 145 19/1 DA+0 NA 393 CART TRACK 146 19/2 DA+0 NA 393 147 AP20/0 DC+0 4193 26°37'52.77"N 71°33'13.22"E Luna NA 395 CART TRACK 148 20/1 DA+0 NA 385 149 20/2 DA+3 NA 390 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 150 20/3 DA+0 NA 340 CART TRACK 151 20/4 DA+0 NA 390 152 20/5 DA+0 NA 380 153 20/6 DA+0 NA 380 11 KV LINE 154 20/7 DA+0 NA 370 CART TRCAK , 33 KV LINE 155 20/8 DA+0 NA 390 156 20/9 DA+0 NA 380 157 20/10 DA+0 NA 393 CART TRACK 158 AP21/0 DC+0 755 26˚36'44.30"N 71˚35'24.09"E Khelana NA 375 159 21/1 DA+0 NA 380 160 AP21A/0 DD+0 2208 26˚36’38.08"N 71˚35’50.53"E Khelana NA 375 161 21A/1 DA+0 NA 375 162 21A/2 DA+0 NA 375 11 KV LINE 163 21A/3 DA+0 NA 333 164 21A/4 DA+0 NA 375 165 21A/5 DA+0 NA 375 166 AP21B/0 DB+0 1468 26˚35’47.31"N 71˚36’46.78"E Khelana NA 340 11 KV LINE 167 21B/1 DA+3 NA 300 168 21B/2 DA+3 NA 265 11 KV LINE 169 21B/3 DA+0 NA 255 170 21B/4 DA+3 NA 308 171 AP21C/0 DC+0 26˚35’11.73"N 71˚37’21.76"E Pratappura NA 360 11 KV LINE 172 21C/1 DA+0 NA 380 LT LINE , CART TRACK 173 21C/2 DA+0 NA 330 11 KV LINE 174 21C/3 DA+0 NA 340 11 KV LINE 175 21C/4 DA+0 NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 380 176 21C/5 DA+0 NA 380 11 KV LINE 177 21C/6 DA+0 NA 370 178 21C/7 DA+0 NA 350 179 21C/8 DA+0 NA 380 180 21C/9 DA+0 NA 370 181 21C/10 DA+0 NA 370 182 21C/11 DA+0 NA 370 183 21C/12 DA+0 NA 369 184 AP21D/0 DB+0 751 26˚34'07.50"N 71˚39'57.81"E Masooriya NA 376 185 21D/1 DA+0 NA 375 186 AP22/0 DC+0 1334 26˚34'00.51"N 71˚40'23.71"E Jagrajgarh NA 340 187 22/1 DA+0 NA 320 11 KV LINE 188 22/2 DA+0 NA 360 11 KV LINE 189 22/3 DA+0 NA 314 11 KV LINE 190 AP22A/0 DB+0 742 26˚33'32.13"N 71˚41'00.05"E Jagrajgarh NA 370 191 22A/1 DA+0 NA 372 LT LINE 192 AP22B/0 DB+0 2628 26˚33'21.11"N 71˚41'23.74"E Jagrajgarh NA 318 193 22B/1 DA+0 NA 380 11 KV LINE , CART TRACK 194 22B/2 DA+0 NA 370 CART TRACK 195 22B/3 DA+0 NA 390 196 22B/4 DA+0 NA 390 11 KV LINE 197 22B/5 DA+0 NA 400 CART TRACK 198 22B/6 DA+3 NA 380 2 NO. 11 KV LINE 199 AP22C/0 DC+0 26˚32'49.40"N 71˚42'51.90"E Rajmathai,Dhaulasar NA 380 200 22C/1 DA+0 NA 335 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 201 22C/2 DA+0 NA 385 CART TRACK 202 22C/3 DA+0 NA 380 CART TRACK 203 22C/4 DA+0 NA 357 11 KV LINE , CART TRACK 204 AP22D/0 DB+0 2930 26°32'06.35"N 71°43'37.84"E Rajmathai NA 330 TAR ROAD , 33 KV LINE , CART TRACK 205 22D/1 DA+0 NA 380 206 22D/2 DA+0 NA 340 LT LINE 207 22D/3 DA+0 NA 373 208 22D/4 DA+0 NA 360 11 KV LINE , CART TRACK 209 22D/5 DA+0 NA 370 210 22D/6 DA+0 NA 390 TAR ROAD 211 22D/7 DA+0 NA 387 LT LINE , 11 KV LINE 212 AP22E/0 DC+0 2222 26°31'05.74"N 71°44'59.49"E Dhaulasar NA 380 213 22E/1 DA+0 NA 355 2 NO. LT LINE 214 22E/2 DA+0 NA 375 215 22E/3 DA+0 NA 385 CART TRACK 216 22E/4 DA+0 NA 345 2 NO. LT LINE 217 22E/5 DA+0 NA 382 218 AP23/0 DB+0 1104 26°30'35.54"N 71°46'12.30"E Balar NA 365 219 23/1 DA+0 NA 360 220 23/2 DA+0 NA 379 221 AP23A/0 DB+0 4458 26°30'27.50"N 71°46'50.99"E Balar NA 275 222 23A/1 DA+0 NA 290 223 23A/2 DA+0 NA 355 224 23A/3 DA+3 NA 300 225 23A/4 DA+0 NA 345 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 226 23A/5 DA+6 NA 390 CART TRACK 227 23AB/0 DB+0 2503 NA 335 228 23AB/1 DA+0 NA 350 CART TRACK 229 23AB/2 DA+0 NA 355 CART TRACK , LT LINE , CART TRACK 230 23AB/3 DA+0 NA 365 231 23AB/4 DA+0 NA 375 2 NO. CART TRACK 232 23AB/5 DA+0 NA 365 11 KV LINE 233 23AB/6 DA+0 NA 358 3 NO. TAR ROAD 234 AP23B/0 DC+0 1086 26°29'29.68"N 71°49'18.61"E Bhikhorai NA 370 CART TRACK 235 23B/1 DA+0 NA Forest area avoided 375 236 23B/2 DA+0 NA Forest area avoided 341 237 AP23C/0 DD+0 756 26°29'27.34"N 71°49'57.71"E NA Forest area avoided 390 TAR ROAD 238 23C/1 DA+3 NA Forest area avoided 366 239 AP23D/0 DD+0 2222 26°29'10.67"N 71°50'17.58"E Bhikhorai Jooni NA 340 240 23D/1 DA+0 NA 375 241 23D/2 DA+0 NA 380 CART TRACK , LT LINE 242 23D/3 DA+0 NA 375 243 23D/4 DA+0 NA 389 CART TRACK 244 23D/5 DA+0 NA 363 245 AP23E/0 DC+0 1495 26°29'00.86"N 71°51'37.11"E Guraliya Gala NA 360 246 23E/1 DA+0 NA 390 CART TRACK 247 23E/2 DA+0 NA 355 248 23E/3 DA+0 NA 390 CART TRACK , LT LINE , CART TRACK 249 23EF/0 DB+6 680 NA 285 250 23EF/1 DA+9 NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 395 251 AP24/0 DB+0 2167 26°28'28.65"N 71°52'47.11"E Bhikhorai NA 255 252 24/1 DA+0 NA 394 CART TRACK 253 24/2 DA+3 NA 400 254 24/3 DA+0 NA 376 CART TARCK 255 24/4 DA+3 NA 380 CART TRACK 256 24/5 DA+0 NA 362 CART TRACK 257 AP25/0 DC+0 26°27'47.71"N 71°53'50.65"E Karada NA

258 AP25/0 ….. 26˚27'47.73"N 71˚53'50.01"E Karada NA 260 3657 259 25/1 DA NA 390 260 25/2 DA NA 380 261 25/3 DA NA 380 262 25/4 DA NA 380 263 25/5 DA NA 390 264 25/6 DA NA 390 265 25/7 DA NA 310 11 KV LINE , TAR ROAD 266 25/8 DA NA 380 267 25/9 DA NA 397 268 AP25A/0 DC 1104 26˚27’27.44"N 71˚56’00.73"E Phulasar NA 380 269 25A/1 DA NA 380 270 25A/2 DA NA 344 271 AP25B/0 DC 4046 26˚27’04.30"N 71˚56’31.06"E Phalsund NA 380 272 25B/1 DA NA 350 273 25B/2 DA NA 390 274 25B/3 DA NA 325 275 25B/4 DA NA 285 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 276 25B/5 DA NA 390 277 25B/6 DA NA 300 278 25B/7 DA NA 340 LT LINE , TAR ROAD 279 25B/8 DA NA 340 280 25B/9 DA NA 320 281 25B/10 DA NA 370 282 25B/11 DA NA 256 283 AP26/0 DB 756 26˚26'11.66"N 71˚58'44.92"E Padampura NA 375 284 26/1 DA NA 381 285 AP26A/0 DC 383 26˚26'04.47"N 71˚59'11.22"E Padampura NA 383 286 AP27/0 DC 370 26˚25'56.28"N 71˚59'21.29"E Bhurajgarh NA 370 287 AP28/0 DB 1115 26˚25'53.40"N 71˚59'34.31"E Mangaliyo Ki Dhani NA 365 288 28/1 DA NA 360 289 28/2 DA NA 390 TAR ROAD 290 AP29/0 DB 386 26˚25'39.01"N 72˚00'11.16"E Mangaliyo Ki Dhani NA 386 291 AP30/0 DB 1454 26˚25'31.52"N 72˚00'22.20"E Mangaliyo Ki Dhani NA 360 292 30/1 DA NA 300 11 KV LINE , TAR ROAD 293 30/2 DB NA 400 294 30/3 DA NA 394 295 AP31/0 DB 1469 26˚25'13.20"N 72˚01'10.50"E Phalsund NA 380 296 31/1 DA NA 400 LT LINE 297 31/2 DA NA 385 TAR ROAD, LT LINE , TAR ROAD 298 31/3 DA NA 304 299 AP32/0 DD 745 26˚25'03.50"N 72˚02'02.60"E Danasar NA 380 11 KV LINE , TAR ROAD 300 32/1 DA NA 365 301 AP33/0 DD 1917 26˚24'41.80"N 72˚02'14.20"E Danasar NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 380 302 33/1 DA NA 390 303 33/2 DA NA 400 304 33/3 DA NA 399 305 33/4 DA NA 348 LT LINE 306 AP34/0 DB 26˚24'13.45"N 72˚03'15.71"E Bhurajgarh NA 270 307 34/1 DB NA 405 CART TRACK 308 34/2 DB NA 472 309 AP35/0 DB 1893 26˚23’58.30"N 72˚03’53.70"E Tanasar NA 200 310 35/1 DB NA 325 311 35/2 DA NA 240 312 35/3 DB NA 375 313 35/4 DA NA 365 314 35/5 DA NA 388 315 AP36/0 DD 1155 26˚23’19.97"N 72˚04’46.99"E Bhumsagar NA 385 LT LINE , CART TRACK 316 36/1 DA NA 395 317 36/2 DA NA 375 318 AP37/0 DB 369 26˚23’22.18"N 72˚05’28.53"E Bhumsagar NA 369 319 AP38/0 DC 1167 26˚23’25.36"N 72˚05’41.30"E Bhumsagar NA 395 TAR ROAD , LT LINE 320 38/1 DA NA 400 321 38/2 DA NA 372 322 AP39/0 DB 4602 26˚23’19.20"N 72˚06’22.97"E Bhumsagar NA 330 323 39/1 DA NA 360 324 39/2 DA NA 360 CART TRACK 325 39/3 DA NA 360 326 39/4 DA NA 360 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 327 39/5 DA NA 380 CART TRACK 328 39/6 DA NA 350 TRA ROAD , LT LINE 329 39/7 DA NA 400 330 39/8 DA NA 300 331 39/9 DA NA 380 332 39/10 DA NA 380 333 39/11 DA NA 322 LT LINE 334 39/12 DA NA 320 335 AP40/0 DB 4787 26˚22’54.40"N 72˚09’06.4"E Janda Nagar NA 300 336 40/1 DA NA 380 337 40/2 DA NA 370 338 40/3 DA NA 390 LT LINE 339 40/4 DA NA 375 340 40/5 DA NA 295 CART TARCK 341 40/6 DA NA 400 CART TARCK 342 40/7 DA NA 380 343 40/8 DA NA 370 LT LINE 344 40/9 DA NA 400 345 40/10 DB NA 380 346 40/11 DA NA 400 347 40/12 DA NA 347 348 AP41/0 DC 747 26˚22’54.82"N 72˚11’59.06"E Gumansingh Pura NA 325 349 41/1 DB NA 422 350 AP42/0 DC 26˚22’47.60"N 72˚12’24.90"E Gumansingh Pura NA 370 351 42/1 DA NA 380 352 42/2 DA NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 370 ROAD 353 42/3 DA NA 360 LT LINE 354 42/4 DA NA 355 CART TRACK 355 AP43/0 DB 2945 26°22'47.61"N 72°13'30.91"E Guman Singh Pura NA 340 LT LINE , 11 KV LINE 356 43/1 DA NA 400 357 43/2 DA NA 380 CART TRACK 358 43/3 DA NA 375 359 43/4 DA NA 305 360 43/5 DA NA 390 361 43/6 DA NA 380 362 43/7 DA NA 375 363 AP44/0 DC 2947 26°22'45.78"N 72°15'16.99"E Narsingh Nagar NA 360 364 44/1 DA NA 400 365 44/2 DA NA 320 366 44/3 DA NA 400 367 44/4 DA NA 355 368 44/5 DA NA 350 2 NO. 11 KV LINE , ROAD 369 44/6 DA NA 380 LT LINE 370 44/7 DA NA 382 11 KV LINE 371 AP45/0 DB 26°22'04.2"N 72°16'53.2"E Shivala Ki Dhani Private Bajra NA 320 MEGA HIGHWAY 372 45/1 DA NA 330 373 45/2 DA NA 400 374 45/3 DA NA 395 375 AP45A/0 DC 443 26°21'45.0"N 72°17'56.9"E Ramnagar NA 443 LT LINE 376 AP45B/0 DB 1828 26°21'52.5"N 72°17'43.3"E Ramnagar NA 380 377 45B/1 DB NA 260 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 378 45B/2 DB NA 240 LT LINE 379 45B/3 DA NA 270 380 45B/4 DB NA 265 381 45B/5 DB NA 413 LT LINE 382 AP46/0 DC 774 26°21'24.93"N 72°18'58.86"E Tena NA 400 2 NO. CART TRACK 383 46/1 DA NA 374 384 AP47/0 DD 1084 26°21'27.90"N 72°19'26.36"E Tena NA 375 385 47/1 DA NA 320 LT LINE 386 47/2 DA NA 389 11 KV LINE , LT LINE 387 AP48/0 DB 1536 26°21'7.88"N 72°19'58.34"E Birad Nagar NA 340 LT LINE , 33 KV LINE 388 48/1 DA NA 397 389 48/2 DA NA 400 390 48/3 DA NA 399 391 AP49/0 DB 1508 26°20'43.12"N 72°20'46.35"E Birad Nagar NA 375 LT LINE 392 49/1 DA NA 380 ROAD , LT LINE 393 49/2 DA NA 360 LT LINE 394 49/3 DA NA 393 CART TRACK 395 AP49A/0 DC 742 26°20'24.00"N 72°21'36.44"E Jatawas NA 360 LT LINE 396 49A/1 DA NA 382 397 AP50/0 DD 742 26°20'20.21"N 72°22'2.71"E Siyanda NA 370 398 50/1 DA NA 372 2 NO. CART TRACK , FENCING 399 AP50A/0 ……. 26°20'4.64"N 72°22'22.87"E Siyanda NA

400 AP52/0 ……. 725 26°19'47.16"N 72°23'8.39"E Siyadhan Private Bajra NA 353 401 52/1 DA Siyadhan Private Bajra NA 372 2 NOS 11 KV LINE,LT LINE & CART TRACK 402 52A/0 DB 1092 Siyadhan Private Bajra NA 359 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 403 52A/1 DA Siyadhan Private Bajra NA 363 11 KV LINE 404 52A/2 DA Siyadhan Private Bajra NA 370 CART TRACK 405 AP53/0 DD 728 26°19'53.6"N 72°24'13.5"N Siyadhan Private Bajra NA Sand-dune 348 11 KV LINE 406 53/1 DA NA 380 CART TRACK 407 AP 53A/0 DB 742 26°19'38.6"N 72°24'33.9"N Siyadhan NA 386 11 KV LINE,LT LINE 408 53A/1 DA NA 356 CART TRACK 409 AP 54/0 DC 2552 26°19'22.6"N 72°24'53.8"N Bhandu Charnan NA 344 11 KV LINE 410 54/1 DA NA 368 LT LINE,CART TRACK 411 54/2 DA NA 400 11 KV LINE,CART TRACK 412 54/3 DA NA 348 413 54/4 DA NA 400 414 54/5 DA NA 344 LT LINE 415 54/6 DA NA 348 2 NOS 11 KV LINE 416 AP 55/0 DB 1865 26°18'50.7"N 72°26'18.8"N Bhandoo Jati NA 400 417 55/1 DA NA 370 418 55/2 DA NA 400 419 55/3 DA NA 325 420 55/4 DA NA 370 TAR ROAD,11 KV LINE 421 AP55A/0 DC 1040 26⁰18'22.12"N 72⁰27'17.96" E Jati Bhandu NA Avoiding forest area of Babul trees 330 ROAD , CART TRACK , LT LINE 422 55A/1 DA NA Avoiding forest area of Babul trees 400 2 NO. CART TRACK 423 55A/2 DA NA Avoiding forest area of Babul trees 310 424 AP56/0 DD 1455 26°18'14.19"N 72°27'54.34"E Devariyo Ki Dhani (Jati NA Bhandu) 380 425 56/1 DA NA 320 426 56/2 DA NA 355 ROAD , LT LINE 427 56/3 DA NA 400 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 428 56A/0 DB 668 NA 362 CART TRACK 429 56A/1 DA NA 306 LT LINE , ROAD , LT LINE , 11 KV LINE 430 AP57/0 DC 26⁰17'18.28"N 72⁰28'39.25"E Balau Jati, Pachpadra NA 365 431 57/1 DA 26°17'12.58"N 72°28'50.78"E Balau Jati, Pachpadra Private Moong, Bajra NA 400 ROAD , CART TRACK 432 57/2 DA 26°17'6.41"N 72°29'3.53"E NA 399 433 57/3 DA 26°17'0.23"N 72°29'16.22"E Balau Jati, Pachpadra Private Bajra NA 396 434 57/4 DA 26°16'54.09"N 72°29'28.80"E NA 265 435 57/5 DA 26°16'50.00"N 72°29'37.22"E NA 360 436 AP58/0 DD 1529 26°16'44.36"N 72°29'48.48"E Balau Jati NA 300 437 58/1 DA 26°16'45.29"N 72°29'59.34"E Balabiya, Pachpadra Private Bajra NA 310 438 58/2 DA 26°16'46.11"N 72°30'10.41"E NA 340 CART TRACK 439 58/3 DA 26°16'47.03"N 72°30'22.61"E NA 310 440 58/4 DA 26°16'47.76"N 72°30'33.84"E NA 269 441 AP59/0 DC 1137 26°16'48.61"N 72°30'43.51"E Narayanpur NA 395 11 KV LINE , ROAD 442 59/1 DA 26°16'45.36"N 72°30'57.29"E NA 370 2 NO. CART TRACK , 2 NO. LT LINE 443 59/2 DA 26°16'42.58"N 72°31'10.24"E NA 372 444 AP60/0 DB 26°16'39.84"N 72°31'23.35"E Narayanpur NA

445 AP60/0 DB+0 1123 26⁰16'39.72"N 72⁰31'23.34"E Narayanpur NA 380 2 NO. CART TRACK 446 60/1 DA+6 NA 375 447 60/2 DA+3 NA 368 ROAD , CART TRACK 448 AP61/0 DD+18 210 26⁰16'36.66"N 72⁰32'03.51"E Dandniya NA 210 400 KV TRANSMISSION LINE 449 AP62/0 DD+18 2181 26⁰16'31.04"N 72⁰32'07.27"E Dandniya NA 399 450 62/1 DA+0 Rodwa Kalan/Pachpadra Private Bajra NA 361 451 62/2 DA+3 Rodwa Kalan/Pachpadra Private Moong, Til NA 375 CART TRACK 452 62/3 DA+0 Rodwa Kalan/Pachpadra Private Moong, Til NA 345 STATE HIGHWAY -66 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 453 62/4 DA+0 NA 345 CART TRACK 454 62/5 DA+0 NA 356 455 AP63/0 DB+0 1517 26⁰15'54.95"N 72⁰33'14.90"E Manashar NA 380 456 63/1 DA+3 NA 399 CART TRACK 457 63/2 DA+0 NA 399 458 63/3 DA+0 NA 339 ROAD 459 AP64/0 DC+0 1068 26⁰15'34.34"N 72⁰34'04.44"E Jasti NA 330 460 64/1 DA+0 NA 370 461 64/2 DA+0 NA 368 462 AP65/0 DC+0 2600 26⁰15'28.63"N 72⁰34'42.46"E Jasti, Pachpadra NA 375 463 65/1 DA+0 Jasti, Pachpadra Private Bajra NA 375 464 65/2 DA+0 Jasti, Pachpadra Private Bajra NA 375 465 65/3 DA+0 Jasti, Pachpadra Private Moong, Til NA 375 KATCHA ROAD 466 65/4 DA+0 Jasti, Pachpadra Private Moong, Til NA 370 467 65/5 DA+0 Jasti, Pachpadra Private Moong NA 360 468 65/6 DA+0 Jasti, Pachpadra Private Moong NA 370 469 AP66/0 DB+0 3419 26°14'49.2"N 72°36'05.3" E Jasti NA 380 470 66/1 DA+0 NA 390 471 66/2 DA+0 Jasti, Pachpadra Private Moong NA 350 S.H.66 , 11 KV LINE 472 66/3 DA+0 Jasti, Pachpadra Private Moong NA 390 473 66/4 DA+0 NA 390 CART TRACK 474 66/5 DA+0 NA 390 475 66/6 DA+0 NA 390 476 66/7 DA+0 NA 355 ROAD , 11 KV LINE 477 66/8 DA+0 NA Tents of sub-contractor 384 478 AP67/0 DB+0 1137 26°14'06.3" N 72°37'58.8"E Palapura NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 390 CART TRACK 479 67/1 DA+0 NA 365 480 67/2 DA+3 NA 382 481 AP68/0 DB+0 3020 26°13'48.8"N 72°38'35.0"E Palapura NA 380 482 68/1 DA+0 NA 385 483 68/2 DA+0 NA 365 484 68/3 DA+0 NA 390 485 68/4 DA+0 NA 385 NALA 486 68/5 DA+0 NA 370 KATCHA ROAD 487 68/6 DA+0 NA 350 KATCHA ROAD 488 68/7 DA+6 NA 395 LT LINE , KATCHA ROAD 489 AP69/0 DB+0 4486 26°13'8.0"N 72°40'13.7"E Surani NA 375 490 69/1 DA+0 NA 385 491 69/2 DA+0 Chircharli, Luni Private Bajra NA 375 492 69/3 DA+3 Chircharli, Luni Private Bajra NA 375 493 69/4 DA+0 NA 380 11 KV LINE , CART TARCK 494 69/5 DA+0 NA 380 495 69/6 DA+0 NA 380 496 69/7 DA+0 NA 365 CART TRACK 497 69/8 DA+0 Chircharli, Luni Private Moong NA 365 498 69/9 DA+0 Chircharli, Luni Private Moong NA 375 LT LINE 499 69/10 DA+0 Chircharli, Luni Private Moong, Til NA 380 CART TRACK 500 69/11 DA+0 Chircharli, Luni Private Bajra NA 351 501 AP70/0 DB+0 4078 26°12'21.6" N 72°42'47.1" E Guman Singh Pura, Luni Private Bajra, Til NA 368 WATER PIPE LINE,TAR ROAD ,CART TRACK 502 70/1 DA+0 26°12'16.7"N 72°42'58.7"N Hingola, Luni Private Bajra NA 352 503 70/2 DA+0 26°12'11.9"N 72°42'10.5"N Hingola, Luni Private Bajra NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 340 504 70/3 DA+0 26°12'07.1"N 72°43'21.4"N Hingola, Luni Private Bajra NA 380 505 70/4 DA+0 26°12'02.0"N 72°42'33.9"N Hingola, Luni Private Bajra NA 380 506 70/5 DA+0 26°11'56.8"N 72°43'46.6"N Hingola, Luni Private Bajra NA 378 507 70/6 DA+0 26°11'51.8"N 72°43'58.7"N Hingola, Luni Private Bajra NA 370 508 70/7 DA+0 26°11'46.6"N 72°44'10.8"N Hingola, Luni Private Bajra NA 370 509 70/8 DA+0 26°11'41.6"N 72°44'22.9"N Hingola, Luni Private Bajra NA 370 510 70/9 DA+0 26°11'36.4"N 72°44'35.1"N Hingola, Luni Private Bajra NA 380 511 70/10 DA+3 26°11'31.4"N 72°44'47.4"N Hingola, Luni Private Bajra NA 390 LT LINE, TAR ROAD 512 AP 70A/0 DB+0 772 26°11'26.1"N 72°45'00.20"N Near Viil.Gulab Sagar NA 374 513 70A/1 DA+0 26°11'21.4"N 72°45'12.6"N NA 398 514 AP 71/0 DB+0 3012 26°11'16.22"N 72°45'26.36"N Near Viil.Gulab Sagar NA 380 515 71/1 DA+0 26°11'13.2"N 72°45'39.1"N Janadeshar, Luni Private Bajra NA 350 516 71/2 DA+0 26°11'10.1"N 72°45'51.1"N Janadeshar, Luni Private Bajra NA 400 2 NOS ROAD & LT LINE 517 71/3 DA+3 26°11'06.6"N 72°46'05.2"N Janadeshar, Luni Private Bajra NA 380 518 71/4 DA+0 26°11'03.2"N 72°46'18.3"N Janadeshar, Luni Private Bajra NA 372 LT LINE 519 71/5 DA+0 26°11'00.0"N 72°46'31.1"N NA 374 520 71/6 DA+3 26°10'56.8"N 72°46'44.2"N NA 386 ROAD 521 71/7 DA+0 26°10'53.5"N 72°46'57.5"N NA 370 522 AP 72/0 DB+0 2180 26°10'50.4"N 72°47'10.4"N Near Vill.Lunawas Khara NA 373 523 72/1 DA+0 26°10'47.1"N 72°47'23.3"N NA 363 524 72/2 DA+0 26°10'43.8"N 72°47'35.81"N NA 363 CART TRACK 525 72/3 DA+0 26°10'40.5"N 72°47'48.3"N NA 363 526 72/4 DA+0 26°10'37.4"N 72°48'00.9"N NA 383 527 72/5 DA+0 26°10'33.9"N 72°48'14.2"N Vill.Lunawas Khara Private Bajra NA 335 TAR ROAD, 11 KV LINE,LT LINE 528 AP 73/0 DC+0 710 26°10'31.0"N 72°48'25.9"N Near Vill.Lunawas Khara Private Bajra NA 355 TAR ROAD,CART TRACK Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 529 73/1 DA+0 26°10'32.4"N 72°48'38.5"N Janadeshar, Luni Private Bajra NA 355 LT LINE 530 AP 74/0 DD+0 2660 26°10'34.13"N 72°48'51.06"N Near Vill.Lunawas Khara Private Bajra NA 380 531 74/1 DA+0 26°10'25.6"N 72°49'01.0"N Near Vill.Lunawas Khara Private Bajra NA 380 2 NOS LT LINE, CART TRACK 532 74/2 DA+0 26°10'16.94"N 72°49'10.76"N Near Vill.Lunawas Khara Private Bajra NA 380 533 74/3 DA+0 26°10'08.4"N 72°49'20.5"N Near Vill.Lunawas Khara Private Bajra NA 380 534 74/4 DA+0 26°09'59.77"N 72°49'30.23"N Near Vill.Lunawas Khara Private Bajra NA 380 CART TRACK 535 74/5 DA+0 26°09'51.1"N 72°49'40.5"N NA 380 11 KV LINE 536 74/6 DA+0 26°09'42.5"N 72°49'50.2"N NA 380 CART TRACK 537 AP 75/0 DC+0 1820 26°09'33.84"N 72°49'59.90"N Near Vill. Jhanwar NA 370 538 75/1 DA+0 26°09'29.0"N 72°50'12.0"N NA 370 539 75/2 DA+0 26°09'23.92"N 72°50'24.12"N NA 380 11 KV LINE 540 75/3 DA+0 26°09'18.85"N 72°50'36.62"N NA 380 ROAD 541 75/4 DA+0 26°09'13.75"N 72°50'49.08"N NA 320 33 KV LINE 542 AP 76/0 DC+0 26°09'09.5"N 72°50'59.5"N Near Viil.Khudala NA 360 1958 11 KV LINE , LT LINE 543 76/1 DA+3 26°09'01.5"N 72°51'08.9"E NA 400 CART TRACK 544 76/2 DA+0 26°08'52.7"N 72°51'19.4"E NA 400 ROAD 545 76/3 DA+3 26°08'43.8"N 72°51'30.1"E NA 398 546 76/4 DA+0 26°08'34.8"N 72°51'40.5"E NA 400 11 KV LINE 547 AP77/0 DD+3 189 26°08'26.0"N 72°51'51.1"E Near Vill. Khudala NA 189 EXISTING 220 KV LINE XING 548 AP78/0 DD+0 3800 26°08'20.78"N 72°51'54.81"E Near Vill. Khudala NA 375 549 78/1 DA+0 26°08'12.85"N 72°52'4.9"E NA 390 550 78/2 DA+0 26°08'04.4"N 72°52'15.1"E Khudala NA 390 11 KV LINE 551 78/3 DA+0 26°07'55.8"N 72°52'25.5"E Khudala NA 360 552 78/4 DA+0 26°07'48.1"N 72°52'35.1"E NA 380 11 KV LINE , CART TRACK 553 78/5 DA+0 26°07'39.6"N 72°52'45.2"E NA 385 554 78/6 DA+0 26°07'31.3"N 72°52'55.6"E NA Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 375 CART TRACK 555 78/7 DA+0 26°07'23.1"N 72°53'05.6"E NA 380 556 78/8 DA+0 26°07'14.7"N 72°53'15.7"E NA 385 557 78/9 DA+0 26°07'06.4"N 72°53'26.0"E NA 380 CART TRACK 558 AP79/0 DC+0 221 26°06'58.06"N 72°53'36.11"E Near Vill. Bhandu Kallan NA 221 N.H.112 (JODHPUR-BARMER) , 11 KV LINE 559 AP80/0 DC+0 1163 26°06'54.6"N 72°53'42.6"E Near Vill. Bhandu Kallan NA Near Industrial area 400 NALA 560 80/1 DA+3 26°06'50.2"N 72°53'56.3"E NA Near Industrial area 384 NALA 561 80/2 DA+0 26°06'45.9"N 72°54'09.3"E NA Near Industrial area 379 CART TRACK 562 AP80A/0 DC+0 780 26°06'42.0"N 72°54'22.3"E Near Vill. Bhandu Kallan NA Near Industrial area 380 563 80A/1 DA+3 26°06'33.4"N 72°54'32.0"E NA Near Industrial area 400 564 AP80B/0 DC+0 4166 26°06'24.1"N 72°54'42.1"E Near Vill. Bhandu Kallan NA Near Industrial area 375 565 80B/1 DA+0 26°06'18.2"N 72°54'53.8"E NA Near Industrial area 395 566 80B/2 DA+0 26°06'11.9"N 72°55'06.2"E NA Near Industrial area 380 567 80B/3 DA+0 26°06'06.0"N 72°55'18.1"E NA Near Industrial area 385 568 80B/4 DA+0 26°05'59.9"N 72°55'30.2"E NA Near Industrial area 385 569 80B/5 DA+0 26°05'53.6"N 72°55'42.2"E NA Near Industrial area 365 LT LINE , CART TRACK 570 80B/6 DA+0 26°05'47.8"N 72°55'53.5"E NA Near Industrial area 375 571 80B/7 DA+0 26°05'41.8"N 72°56'05.3"E NA Near Industrial area 400 ROAD 572 80B/8 DA+0 26°05'35.4"N 72°56'17.9"E NA Near Industrial area 356 LT LINE 573 80B/9 DA+3 26°05'29.9"N 72°56'29.1"E NA Near Industrial area 398 ROAD , 11 KV LINE 574 80B/10 DA+3 26°05'23.5"N 72°56'41.4"E NA Near Industrial area 352 33 KV LINE 575 AP81/0 DC+0 2370 26°05'17.9"N 72°56'52.52"E Near Vill. Bhandu Kallan, Private Bajra, Moong NA Near Industrial area Nandwan, Luni 395 576 81/1 DA+3 26°05'16.4"N 72°57'06.7"E 91.001 NA 395 ROAD 577 81/2 DA+0 26°05'14.8"N 72°57'20.8"E 90.806 NA 390 578 81/3 DA+0 26°05'13.3"N 72°57'34.8"E 91.427 NA 398 Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 579 81/4 DA+3 26°05'11.7"N 72°57'48.9"E 92.943 NA 399 580 81/5 DA+3 26°05'10.3"N 72°58'03.1"E 92.65 NA 393 CART TRACK , 11 KV LINE , S.H. LT LINE 581 AP82/0 DB+3 1158 26°12'21.66"N 72°42'47.08"N Near Village Shivala Ki Private Bajra, Moong NA Dhani, Nandanwan, Luni 398 582 82/1 DA+0 26°12'16.7"N 72°42'58.7"N NA 364 LT Line 583 82/2 DA+0 26°12'11.9"N 72°42'10.5"N NA 396 ROAD 584 AP82A/0 DC+0 387 26°12'07.1"N 72°43'21.4"N Near Village Shivala Ki NA Dhani 387 585 AP83/0 DD+18 202 26°12'02.0"N 72°42'33.9"N Near Village Shivala Ki Private Bajra, Moong NA Dhani, Salawas, Luni 202 UNDER CONSTRUCTION 400KV D/C TWIN LINE (AGOLAI TO KANKANI) 586 AP84/0 DD+18 800 26°11'56.8"N 72°43'46.6"N Near Village Shivala Ki NA Dhani 400 587 84A/0 DB+0 26°11'51.8"N 72°43'58.7"N Salawas, Luni Private Moong NA 400 588 AP85/0 DD+9 200 26°11'46.6"N 72°44'10.8"N Salawas, Luni Private Bajra, Moong NA 200 220 KV D/C BARLI- JODHPUR UNDER CONSTRUCTION TL LINE 589 AP86/0 DD+9 1057 26°11'41.6"N 72°44'22.9"N Near Village Shivala Ki Private Bajra, Moong NA Dhani, Salawas, Luni 334 590 86/1 DA+0 26°11'36.4"N 72°44'35.1"N Near Village Shivala Ki Private Bajra, Moong NA 1.5 km from school Dhani, Salawas, Luni 350 LT LINE, ROAD 591 86/2 DA+0 26°11'31.4"N 72°44'47.4"N Near Village Shivala Ki Private Bajra, Moong NA Dhani, Salawas, Luni 373 592 AP87/0 DD+6 197 26°11'26.1"N 72°45'00.20"N Near Village Shivala Ki NA Dhani 197 RAILWAY LINE 593 AP88/0 DD+6 1953 26°11'21.4"N 72°45'12.6"N Near Village Shivala Ki NA Dhani 400 594 88/1 DA+0 26°11'16.22"N 72°45'26.36"N Near Viil.Gulab Sagar NA 359 2 NO. CART TRACK 595 88/2 DA+3 26°11'13.2"N 72°45'39.1"N Nandanwan, Luni Private Bajra NA 395 LT LINE 596 88/3 DA+0 26°11'10.1"N 72°45'51.1"N Nandanwan, Luni Private Bajra, Moong NA 399 PIPE LINE (IOCKBPL) AJMER- SALAWAS 597 88/4 DA+3 26°11'06.6"N 72°46'05.2"N Nandanwan, Luni Private Bajra, Moong NA 400 2 NOS .CART TRACK Tower Tower Span Section Latitude Longitude Name Of Village/Tehsil Ownership of land Name of Crops Name of Number of trees Remarks / Crossings SNo No. Type (M.) Length (private, Govt. Crops under cutting (M.) Forest)/ Use of Land 598 AP89/0 DD+0 180 26°11'03.2"N 72°46'18.3"N NA 180 132 KV S/C LINE 599 AP90/0 DD+6 777 26°11'00.0"N 72°46'31.1"N Kankani, Luni Private Bajra, Moong NA 393 11 KV LINE 600 90/1 DA+0 26°10'56.8"N 72°46'44.2"N Purohit ki Dhani, Luni Private Bajra, Moong NA 384 ROAD ,LT LINE 601 AP91/0 DD+0 1140 26°10'53.5"N 72°46'57.5"N Kankani, Luni Private Bajra, Moong NA 375 602 91/1 DA+0 26°10'50.4"N 72°47'10.4"N Kankani, Luni Private Til, Moong NA 365 11 KV LINE ,CART TRACK 603 91/2 DA+0 26°10'47.1"N 72°47'23.3"N Kankani, Luni Private Bajra, Moong NA 400 FENCING 604 AP92/0 DD+9 26°10'43.8"N 72°47'35.81"N NA AP 95 26°04'27"N 73°03'47"N Kankani, Luni Barren None Near the edge of Jodhpur (new) Dead end substation tower ANNEXURE-3

(RAJASTHAN GAZZETTE NOTIFICATION FOR TRANSMISSION LINE CONSTRUCTION)

ANNEXURE-4

(FOREST CLEARANCE FOR TRANSMISSION LINE)

ANNEXURE 5

(DETAILS OF EPC CONTRACTOR EHS POLICY)

ANNEXURE-6

(TREE/CROP COMPENSATION)

ANNEXURE-7

(PHOTOGRAPHS FROM SITE VISIT TO TRANSMISSION LINE) 1. Tower erection – various stages

Topographic sheet giving lcation of Final route selected (Green rectangle is the designated forest area that is avoided

Digging of Tower Foundations (Stacking of top soil) Steel reinforcing for tower leg 2 m deep

Spacing of tower legs using tower material, Labor using Personal Protective Equipment (PPE) Handling of Cement during construction etc. at tower foundation site.

Stacking of Construction Material near site Excess area for each tower foundation where crop compensation is paid

Access required for tower from Road for which compensation is paid After completion of tower foundation

Tower under erection Completed Tower – Portion at the base area

Completed row of towers Terminating Bay at 400 kV Akal Grid Substation

Location of terminating tower near boundary wall of Jodhpur (new) substation 2. EPC contractor Stores and equipment storage

Materials Store of EPC contractor at land rented from Farmer

Materials store of the EPC contractor at land rented from Farmer Equipment used for loading and unloading at materials store

Materials store of the EPC contractor Drum based Tensioner and Puller machines at Materials store 3. Sub- contractor labor camp

Tents at Sub-contractor labor camp (Tower foundation construction)

Inside living tents at Sub-contractor labor camp (Tower foundation construction) Kitchen used by sub-contractor (wood is purchased from market)

PPE used by Sub-contractor staff Manual foundation making casting frames and steel bending equipment at subcontractor camp 4. ROW - General Crops and terrain in area, trees etc.

Barren sand-dune area for tower locations

Moong dat being cultivated in some agricultural fields Horizon and road connectivity in most of the tower line path

Recently cultivated field after tower foundation erection Cattle grazing in area

Grazing land under recently erected tower line Wind farms in the area

Barren land in some areas Irrigated land (small portion 16 km of line)

Road and foundation area being used for tower foundation (Road access is also paid under crop compensation Bajra crop in some areas 5. Consultation with Affected Persons

Consultation with Affected Household Consultation with affected household along with RVPNL and EPC contractor/sub-contractor Consultation with Affected households Consultation with people in the area. Consultation with workers at tower foundation – also includes Affected persons working as labor and RRVPNL and EPC contractor/sub-contractor.