Procurement Plan Community Development Program Support Project – Phase III (Programme National de Développement Participatif – Phase III) Public Disclosure Authorized I. General
1. Bank’s approval Date of the procurement Plan [Original: February 2016]: Revision of Updated Procurement Plan, May 05, 2017 2. Date of General Procurement Notice: February 15, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year January to December 2017
II. Goods and Works and non-consulting services.
1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as
Public Disclosure Authorized stated in Appendix 1 to the Guidelines for Procurement:
Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) None 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million 5. DC (Non-Consultant Services) none
2. Prequalification. Not applicable.
Public Disclosure Authorized 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Procurement (works, goods and services) for subprojects of communes, such as small infrastructure, social infrastructure, classrooms, health centers, community halls, , minor works or rehabilitation, will be procured on the basis of community participation in accordance with the clause 3.19 of the World Bank Procurement Guidelines (Community Participation in Procurement), and the Guidelines for Simplified Procurement and Disbursement for Community-Based Investments (March 3, 1998) detailed in the specific manual or guidelines to communes approved by the bank.
4. Reference to (if any) Project Operational/Procurement Manual: Guide des Acteurs intervenant dans le processus de passation et de l’exécution des marchés communaux financés par le PNDP – Juin 2010, révisé en Janvier 2016
Public Disclosure Authorized 5. Any Other Special Procurement Arrangements: 5 ICB works packages will be financed under - retroactive financing
6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced May 05, 2017 procurement)
1 2 3 4 5 6 7
Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of 2.328 2 No Prior the ICB (Goods) Summary of 0.700 1 No Post 1st contract for the NCB Prior Review (Goods)
III. Selection of Consultants
1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:
Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 Justification prior reviewed by bank 3. Individual Above US$ 200,000
2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
3. Any Other Special Selection Arrangements: not applicable
4. Consultancy Assignments with Selection Methods and Time Schedule
1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review by Expected Comments/ No cost (US$ method the Bank proposals completion equivalent) (prior/post) submission date date For the first 1 Support for the preparation Post year 20,000 IC 21/08/15 of Statutory Instruments 24/09/15 (30 days) 2 Study on the definition of a 40,000 Post CQS 22/04/16 planning methodology at 25/01/16 (03 months) regional level 3 Study on the planning 40,000 CQS Post 25/01/16 22/04/16 process in the communes and (03 months) urban communities
May 05, 2017 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review by Expected Comments/ No cost (US$ method the Bank proposals completion equivalent) (prior/post) submission date date 4 Study for the establishment 20,000 IC Post 19/02/16 24/03/16 of local public service in (30 days) communes 5 Study on the sustainability of 40,000 CQS Post 11/04/16 18/07/16 the PNDP (03 months) 6 Evaluation of the 40,000 CQS Post 13/07/16 18/10/16 decentralization process in (03 months) Cameroon/supports to the finalization of the national strategy for decentralization 7 Selection of a consultant to 20,000 IC Post 20/11/15 30/12/15 develop the practitioner's (30 days) manual for the 31 communes 8 Municipal staff training 100,000 SSS Prior NA Service provided by the CEFAM (Convention) 9 Training of procurement 100,000 SSS Prior NA Service commissions provided by ARMP (Convention) 10 Financial Audits of the 150,000 LCS Post 10/03/15 Contract for 2 project for the first 2 years years 11 legal advice 10,000 IC Post 28/12/15 Annual contract 12 Design and development of 90,000 CQS Post 12/02/16 22/08/16 an internet portal on the (06 months) PNDP and communes 13 Translation of documents 90,000 CQS Post 11/05/16 20/08/16 (03 months) 14 Technical audit 80,000 QCBS Post 16/02/16 31/08/16 (06 months) 15 Beneficiary assessment 50,000 QCBS Post 15/11/16 22/05/17 (06 months) 16 Environmental and Social 70,000 QCBS Post 13/12/16 26/06/17 Assessment (06 months) 17 Follow-up of training Service deployment and technical SSS Prior NA provided by 70,000 assistance to Sim_ba AIMF expert software in communes (Convention) 18 IC Post 27/05/15 Annual contract (the current 10,000 contract ends June 30, Insurance advice 2015) 19 Preparation of CDPs for the QCBS Post 01/12/16 16/04/16 80,000 31 communes (06 months)
May 05, 2017 May 05, 2017 PROCUREMENT Cameroon : Community Development Program Support Project-Phase III PLAN General Information Country: Cameroon Bank s Approval Date of the Original Procurement Plan: 2017-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-05-30 Project ID: P144637 GPN Date: Project Name: Community Development Program Support Project-Phase III Loan / Credit No: IDA / 57180 Executing Agency(ies):NATIONAL COMMUNITY DRIVEN DEVELOPMENT PROGRAM, CELLULE REGIONALE DE COORDONATION - EST, CELLULE REGIONALE DE COORDONATION - LITTORAL, CELLULE REGIONALE DE COORDONATION - SUD, CELLULE REGIONALE DE COORDONATION - SOUTH WEST, CELLULE REGIONALE DE COORDONATION - EXTREME NORD, CELLULE REGIONALE DE COORDONATION - OUEST, CELLULE REGIONALE DE COORDONATION - NORTH WEST, CELLULE REGIONALE DE COORDINATION - CENTRE, CELLULE REGIONALE DE COORDINATION - ADAMAOUA, CELLULE REGIONALE DE COORDONATION - NORD
WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
CM-CRC EXTREME NORD-8012- CW-RFQ / Petits travaux Component C: Coordination, d'aménagement des bureaux Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 5,600.00 0.00 2017-03-10 2017-05-05 2017-06-04 (cloisonnement des bureaux, Quotations Envelope Implementation evaluation and communication équipement étagères pour classement, etc...) à la CRC EN
CM-CRC EXTREME NORD-8013- CW-RFQ / Construct et équipt d'01 bloc de 02 de sc et d'un bloc de Lt à trois comparts à l'EP de Dogba, au lycée de Gayack et Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 154,638.00 0.00 2017-03-25 2017-05-20 2017-09-17 Construction de 01 bloc de development support Quotations Envelope Implementation hangar de 52 pces et d'un bloc de Lt à trois comparts au marché de Papata,Commune de Mra II
CM-CRC EXTREME NORD-8016- CW-RFQ / Constructde 6 forages équipés de PMH à Tchékéhi, Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 96,000.00 0.00 2017-03-25 2017-05-20 2017-08-18 Mbokouré, Magaldao Toupéo, development support Quotations Envelope Implementation
Soukkoungo Galdima, Bourango et Bandalaré, commune de Pétté
CM-CRC EXTREME NORD-8035- CW-RFQ / Construct d'un magasin de stockage à Kéné- Kéné, Construct d'un bloc de 02 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 82,609.00 0.00 2017-03-25 2017-05-20 2017-08-18 sc équipées à l'EP de Djafgué, development support Quotations Envelope Implementation et Construct d'un bloc de Lt à l'EP de Djafgué commune de Pétté
CM-CRC EXTREME NORD-8036- CW-RFQ / Constr d'un forage pastoral à énergie solaire équipé de 02 abreuvoirs à Balaza Component A: Local Request for Single Stage - One Pending Lawane (Tchalloudi mango) et IDA / 57180 Post Limited 82,196.00 0.00 2017-03-25 2017-05-20 2017-08-18 development support Quotations Envelope Implementation Constr d'un forage pastoral à énergie solaire équipé de 02 abreuvoirs à Kongola Saïd, Cne Maroua 3
CM-CRC EXTREME NORD-8037- CW-RFQ / Construct d'un bloc de 02 sc équipées et d'un bloc Component A: Local Request for Single Stage - One Pending de Lt à trois comparts à l'EP de IDA / 57180 Post Limited 136,106.00 0.00 2017-03-25 2017-05-20 2017-08-18 development support Quotations Envelope Implementation Mayel Béi, à l'EP de Bao Hosséré II et à l'EP de Palaoudi, commune Maroua 1
CM-CRC EXTREME NORD-8040- CW-RFQ / construction d'un bloc maternel à l'école Maternelle de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 57,421.00 0.00 2017-03-25 2017-05-20 2017-08-18 Zokok-Laddo et branchement au development support Quotations Envelope Implementation réseau d'alimentation en eau potable, commune de Maroua 1
CM-CRC EXTREME NORD-8042- CW-RFQ / Construction de trois forages équipés de pompe à Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 46,689.00 0.00 2017-03-25 2017-05-20 2017-08-18 motricité humaine à Ouro Dow, development support Quotations Envelope Implementation
Goni Bello et Yoldéo Guiziga, Commune Maroua 1
CM-CRC EXTREME NORD-8043- CW-RFQ / Construction de d'un bloc de 02 salles de classe Component A: Local Request for Single Stage - One Pending équipées et d'un bloc de latrines IDA / 57180 Post Limited 92,247.00 0.00 2017-03-25 2017-05-20 2017-08-18 development support Quotations Envelope Implementation à trois compartiments à l'EP Masfaï et au CES de Boula, commune de Mokolo
CM-CRC EXTREME NORD-8045- CW-RFQ / Construction de 2 Component A: Local Request for Single Stage - One Pending forages équipés de PMH un à IDA / 57180 Post Limited 33,787.00 0.00 2017-03-25 2017-05-20 2017-08-18 development support Quotations Envelope Implementation Ouro Kessoum et à Mounam, commune de Mokolo
CM-CRC EXTREME NORD-8047- CW-RFQ / Construction d'un ouvrage de franchissement et Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 87,751.00 0.00 2017-03-25 2017-05-20 2017-08-18 assainissement(radier-dalot) sur development support Quotations Envelope Implementation le Mayo Kwayaga, dans la commune de Mogodé
CM-CRC EXTREME NORD-8050- CW-RFQ / Construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One Pending et d'un bloc de latrines à trois IDA / 57180 Post Limited 90,443.00 0.00 2017-03-25 2017-05-20 2017-08-18 development support Quotations Envelope Implementation compartiments à l'EP de Saoudjo et au CES de Madaka, commune de Bogo
CM-CRC EXTREME NORD-8053- CW-RFQ / Construction d'un Component A: Local Request for Single Stage - One Pending forage équipé de PMH à IDA / 57180 Post Limited 32,294.00 0.00 2017-03-25 2017-05-20 2017-08-18 development support Quotations Envelope Implementation Dambaye et à Bagalaf commune de Bogo
CM-CRC EXTREME NORD-8054- CW-RFQ / construction d'un bloc de deux (02) salles de classe equipees et un (01) bloc latrine Component A: Local Request for Single Stage - One Pending a trois (03) compartiments a IDA / 57180 Post Limited 178,787.00 0.00 2017-03-25 2017-05-20 2017-09-17 development support Quotations Envelope Implementation l'EP de honkol, a l'EP de darsala, a l'EP de dabanga et l'equipement en meubles a l'ecole maternelle de logone birni
CM-CRC EXTREME NORD-8056- CW-RFQ / construction de trois forages équipés de pompe à Component A: Local Request for Single Stage - One Pending motricité humaines: un à l'EP de IDA / 57180 Post Limited 50,245.00 0.00 2017-03-25 2017-05-20 2017-08-18 development support Quotations Envelope Implementation Dabanga, un à l'EP de Honkol et un à l'EP de Darsala dans la Commune de Logone Birni
CM-CRC EXTREME NORD-8057- CW-RFQ / construction d'un forage pastoral équipé de pompe Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 45,860.00 0.00 2017-03-25 2017-05-20 2017-08-18 immergée à énergie development support Quotations Envelope Implementation photovoltaique à Sahaba 1 dans la Commune de Logone Birni
CM-CRC EXTREME NORD-8068- CW-RFQ / réhabilitation de la mare artificielle et la construction Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 114,601.00 0.00 2017-03-25 2017-05-20 2017-09-17 d'un forage pastoral à energie development support Quotations Envelope Implementation photovoltaique à Mogong dans la commune de Moutourwa
CM-CRC EXTREME NORD-8072- CW-RFQ / construction de 2 blocs de deux salles de classe Component A: Local Request for Single Stage - One Pending équipées et de 2 blocs de IDA / 57180 Post Limited 115,353.00 0.00 2017-03-25 2017-05-20 2017-08-18 development support Quotations Envelope Implementation latrines à trois compartiments EP NGré et EP Afadé dans la commune de Makary
01/T/CRC/CE/2017 / Petits Component C: Coordination, Request for Single Stage - One Pending travaux d'aménagement dans les IDA / 57180 management, monitoring and Post Limited 9,800.00 0.00 2017-07-25 2017-09-19 2017-10-19 Quotations Envelope Implementation nouveaux locaux Centre evaluation and communication
CM-CRC ADAMAOUA-8083-CW- RFQ / Aménagement du marché Kassouan-Dolé (Marché B) de Banyo par la construction de 32 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 176,700.00 0.00 2017-03-18 2017-05-29 2017-11-25 Boutiques Bloc A & B, 01 development support Quotations Envelope Implementation
Hangar de marché (48 comptoirs) Vivres frais et 01 Blocs de 03 Latrines, Commune de Banyo
CM-CRC ADAMAOUA-8090-CW- RFQ / Travaux de construction Component C: Coordination, d'un Pont de 8 m de long et de 5 Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 105,819.00 0.00 2017-03-18 2017-05-29 2017-11-25 m de large sur le Mayo-Soulabé, Quotations Envelope Implementation evaluation and communication Commune de Banyo, Région Adamaoua
CM-CRC NORTH WEST-8096- CW-RFQ / Construction of 2 equipped Classrooms, VIP toilet,H/M's office and extension Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 70,000.00 0.00 2017-06-10 2017-08-05 2018-02-01 of water to GS TUKU- development support Quotations Envelope Implementation
TABENKENin Nkambe council area, dans la Commune de nkambè Région du Nord Ouest
CM-CRC ADAMAOUA-8095-CW- RFQ / Travaux de construction d'un Pont de 8 m de long et de 5 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 77,184.00 0.00 2017-04-07 2017-06-18 2017-12-15 m de large sur le Mayo Mandjoa, development support Quotations Envelope Implementation
Commune de Banyo, Région Adamaoua
001/T/CE/ENDOM/2017 / Construction 02 hangars de 30 comptoirs avec bloc latrines 02 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 92,720.00 0.00 2017-04-28 2017-07-03 2017-10-31 compartiments dans 02 sites des development support Quotations Envelope Implementation marchés de Edjom et de Mengwa à d'Endom
002/T/CE/ENDOM/2017 / Travaux de Construction de deux (02) puits productifs équipés de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 24,000.00 0.00 2017-04-01 2017-05-27 2017-09-24 Pompe à Motricité Humaine dans development support Quotations Envelope Implementation deux (02) localités (Edjom, Mengwa) d'Endom
CM-CRC ADAMAOUA-8099-CW- RFQ / Travaux de construction Component A: Local Request for Single Stage - One Pending du parc vaccinogène à IDA / 57180 Post Limited 19,000.00 0.00 2017-03-18 2017-05-29 2017-11-25 development support Quotations Envelope Implementation Boudjounkoura, commune de Banyo, Région Adamaoua
CM-CRC ADAMAOUA-8104-CW- RFQ / Travaux de construction d'un pont de 12 m de portée sur 7 mètre de large en béton armé Component A: Local Request for Single Stage - One Pending sur le cours d'eau Baraya reliant IDA / 57180 Post Limited 123,669.00 0.00 2017-04-05 2017-06-16 2017-12-13 development support Quotations Envelope Implementation le quartier Marouaré à l'EP Annexé de Tignère, Commune de Tignère, Département du Faro et Déo, Région de l'Adamaoua
003/T/CE/AKOEMAN/2017 / Construction de 04 puits équipés de Pompes à Motricité Component A: Local Request for Single Stage - One Pending Humaine dans quatre localités IDA / 57180 Post Limited 48,000.00 0.00 2017-04-28 2017-06-18 2017-10-16 development support Quotations Envelope Implementation (Ngamba, Akoéman ville, Melen et Akoa Zolé) dans la Commune d'Akoéman, Région du Centre
CM-CRC ADAMAOUA-8106-CW- RFQ / Travaux de construction d'un bâtiment R+1 de 20 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 173,600.00 0.00 2017-03-18 2017-06-22 2017-12-19 boutiques avec bureau et latrines development support Quotations Envelope Implementation incorporées au Marché de Tignère, Région Adamaoua
40/T/CE/NANGA/2017 / Travaux de réhabilitation de deux (02) puits équipés de Pompe à Motricité Humaine au marché de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 12,000.00 0.00 2017-04-08 2017-06-03 2017-10-01 Essimeyong et au marché de development support Quotations Envelope Implementation
Biboa, dans la Commune de Nanga et Eboko, Région du Centre
004/T/CE/AKOEMAN/2017 / Travaux de Construction d'un hangar de 32 comptoirs et 01 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 80,406.00 0.00 2017-04-01 2017-05-27 2017-09-24 bloc de 04 latrines a Akoeman development support Quotations Envelope Implementation ville, dans la Commune d'Akoéman, Région du Centre
39/T/CE/NANGA/2017 / Travaux de Construction de deux (02) hangars avec comptoirs et Construction de deux (02) blocs Component A: Local Request for Single Stage - One Pending de latrines à trois (03) IDA / 57180 Post Limited 104,743.00 0.00 2017-04-08 2017-06-03 2017-10-01 development support Quotations Envelope Implementation compartiments dans 02 marchés à Essimeyong et à Biboa dans la commune de Nanga et Eboko dans la Région du Centre
38/T/CE/MINTA/2017 / Travaux de construction d'un puits équipé Component A: Local Request for Single Stage - One Pending de PMH à l'EP de Ndjombe, IDA / 57180 Post Limited 1,200.00 0.00 2017-04-08 2017-06-03 2017-10-01 development support Quotations Envelope Implementation dans la commune de Minta, Région du Centre
005/T/CE/MBANDJOCK/20177 / Travaux de Construction d'un abattoir avec latrines Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 56,000.00 0.00 2017-04-01 2017-05-27 2017-09-24 incorporées, au centre ville de development support Quotations Envelope Implementation
Mbandjock dans la Commune de Mbandjock, Région du Centre
CM-CRC ADAMAOUA-8113-CW- RFQ / Travaux de construction d'un forage équipe d'un système solaire pour l'approvisoinnement Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 36,100.00 0.00 2017-03-18 2017-05-29 2017-11-25 en eau et en électricité du d'un development support Quotations Envelope Implementation bâtiment R+1 du Marché de Tignère, Commune de Tignère, Région Adamaoua
006/T/CE/MBANDJOCK/20177 / Construction d'une mini AEP par raccordement au reseau CDE et construction d'un château d'eau Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 7,427.00 0.00 2017-04-01 2017-05-27 2017-09-24 avec un cubitenaire de 4000 litres development support Quotations Envelope Implementation au centre ville de Mbandjock dans la Commune de Mbandjock, Région du Centre
CM-CRC ADAMAOUA-8115-CW- RFQ / Travaux de construction Component A: Local Request for Single Stage - One Pending d'une case communautaire avec IDA / 57180 Post Limited 75,546.00 0.00 2017-03-18 2017-05-29 2017-11-25 development support Quotations Envelope Implementation bloc latrines à Galim-Tignére, Région Adamaoua
CM-CRC ADAMAOUA-8117-CW- RFQ / Travaux de construction d'un marché à bétail composé d'un Parc de contention, d'un Quai d'embarquement, d'un Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 93,948.00 0.00 2017-03-18 2017-05-29 2017-11-25 Hangar simple et d'un Bloc de development support Quotations Envelope Implementation deux latrines à Galim-Tignère, Commune de Galim Tignère, Département du Faro et Déo, Région de l'Adamaoua
37/T/CE/NANGA/2017 / Travaux de construction d'un bloc de 03 salles de classe équipées et Component A: Local Request for Single Stage - One Pending construction d'un bloc de trois IDA / 57180 Post Limited 50,000.00 0.00 2017-04-08 2017-06-03 2017-10-01 development support Quotations Envelope Implementation latrines à l'EP de Ndjombe dans la commune de Nanga et Eboko, Région du Centre
CM-CRC ADAMAOUA-8121-CW- RFQ / Travaux de construction Component A: Local Request for Single Stage - One Pending d'un abattoir avec latrines IDA / 57180 Post Limited 85,333.00 0.00 2017-03-18 2017-05-29 2017-11-25 development support Quotations Envelope Implementation incorporées à Galim-Tignére, Région Adamaoua
CM-CRC NORTH WEST-8098- CW-RFQ / Construction and equipping of a block of two classrooms, a block of VIP Component A: Local Request for Single Stage - One Pending latrine, H/M's office and IDA / 57180 Post Limited 70,000.00 0.00 2017-06-10 2017-08-05 2018-02-01 development support Quotations Envelope Implementation extension of potable water to GNS Njindom", dans la Commune de mbengwi Région du Nord O..
Page 1 CM-CRC ADAMAOUA-8124-CW- RFQ / Travaux de construction de 02 forages dont l'un équipé de PMH au Marché à bétail et l'autre équipé de pompe solaire avec Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 40,000.00 0.00 2017-03-18 2017-05-29 2017-11-25 support métalique et réservoire development support Quotations Envelope Implementation de 2 m3 à l'abattoir de Galim Tignère, Commune de Galim Tignère, Département du Faro et Déo, Région de
36/T/CE/NTUI/2017 / Travaux de Construction de deux (02) magasins de stockage de cacao et construction de 02 blocs Component A: Local Request for Single Stage - One Pending latrines à deux (02) IDA / 57180 Post Limited 125,749.00 0.00 2017-04-08 2017-06-03 2017-10-01 development support Quotations Envelope Implementation compartiments dans les localités de Nguila, et Ntui ville) dans la Commune de Ntui, Région du Centre
CM-CRC ADAMAOUA-8127-CW- RFQ / Travaux de construction d'un magasin de stockage et un Component A: Local Request for Single Stage - One Pending bloc de deux latrines à Ngouri IDA / 57180 Post Limited 40,048.00 0.00 2017-04-05 2017-04-26 2017-10-23 development support Quotations Envelope Implementation HAMAN, Commune de Galim Tignère, Département du Faro et Déo, Région de l'Adamaoua
007/T/CE/EBEBDA/2017 / Travaux de Construction de 02 hangars de 32 comptoirs avec 02 blocs latrines à 03 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 89,801.00 0.00 2017-04-01 2017-05-27 2017-09-24 compartiments au marché de development support Quotations Envelope Implementation
Nkog Edzen et au marché de Elig-Edouma dans la Commune d'Ebebda, Région du Centre
35/T/CE/BOT MAKA/2017 / Travaux de Construction d'un (01) puits équipés de pompes à Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 12,000.00 0.00 2017-04-08 2017-06-03 2017-10-01 motricité humaine à Ndjock development support Quotations Envelope Implementation
Bané, dans la Commune de Bot Makak, Région du Centre
008/T/CE/EBEBDA/2017 / Travaux de Construction d'un (01) forage équipé de Pompe à Component A: Local Request for Single Stage - One Pending Motricité Humaine sur le site du IDA / 57180 Post Limited 17,000.00 0.00 2017-04-01 2017-05-27 2017-09-24 development support Quotations Envelope Implementation marché de Elig-Edouma, dans la Commune d'Ebebda, Région du Centre
009/T/CE/NKOTENG/2017 / Travaux de Construction d'un abattoir avec un bloc latrine à Component A: Local Request for Single Stage - One Pending trois (03) compartiments à IDA / 57180 Post Limited 32,014.00 0.00 2017-04-01 2017-05-27 2017-09-24 development support Quotations Envelope Implementation l'abattoir de Nkoteng dans la Commune de Nkoteng, Région du Centre
CM-CRC NORTH WEST-8137- CW-RFQ / Rehabilitation of the Bafut main market (transformation of open markets Component A: Local Request for Single Stage - One Pending sheds to closed market sheds IDA / 57180 Post Limited 70,000.00 0.00 2017-06-10 2017-08-05 2018-02-01 development support Quotations Envelope Implementation and construction of fence) in Bafut council area, dans la Commune de bafut, Région du Nord Ouest
010/T/CE/NKOTENG/2017 / Travaux de Construction d'une mini adduction Component A: Local Request for Single Stage - One Pending d'approvisionnement en eau IDA / 57180 Post Limited 16,000.00 0.00 2017-04-01 2017-05-27 2017-09-24 development support Quotations Envelope Implementation potable sur le site de l'abattoir de Nkoteng dans la Commune de Nkoteng, Région du Centre
CM-CRC NORD-8659-CW-RFQ / Exécution des travaux de construction d'un bâtiment à Component B: Support to the Request for Single Stage - One Pending usage de bloc sanitaire et d'un IDA / 57180 Post Limited 104,000.00 0.00 2017-03-07 2017-04-18 2017-08-18 decentralization process Quotations Envelope Implementation bloc de latrines à quatre compartiments au Centre de Santé Intégré de Rey Bouba
CM-CRC NORD-8660-CW-RFQ / Exécution des travaux de Component B: Support to the Request for Single Stage - One Pending réalisation d'un forage équipé de IDA / 57180 Post Limited 17,000.00 0.00 2017-03-20 2017-05-02 2017-09-04 decentralization process Quotations Envelope Implementation PMH au Centre de Santé Intégré de Rey Bouba
CM-CRC LITTORAL-9509-CW- RFQ / Travaux de Construction de quatre forages positifs équipés d'une pompe à motricité Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Open - National 69,175.00 0.00 2017-03-25 2017-05-20 2017-11-16 humaine à Moukouda, Mbagna, development support Quotations Envelope Implementation
Nyamtam et Yabassi centre, dans la Commune de Yabassi, Région du Littoral
CM-CRC LITTORAL-9510-CW- RFQ / Travaux de Construction d'un pont mixte acier-béton sur la Component A: Local Request for Single Stage - One Pending rivière Mounè dans la localité de IDA / 57180 Post Open - National 80,757.00 0.00 2017-03-14 2017-05-09 2017-11-05 development support Quotations Envelope Implementation Mandjap sur une portée de 8,00m, dans la Commune de Ngambé, Région du Littoral
CM-CRC LITTORAL-9511-CW- RFQ / Travaux de Construction de deux blocs de boutiques, à raison de 10 boutiques chacun, Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Open - National 100,000.00 0.00 2017-03-25 2017-05-20 2017-11-16 au marché de Loum Centre, dans development support Quotations Envelope Implementation la Commune de Loum, dans la Commune de Loum, Région du Littoral
CM-CRC LITTORAL-9512-CW- RFQ / Travaux de Construction d'un bloc de 10 boutiques y compris bloc de 04 latrines et Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Open - National 92,834.00 0.00 2017-03-25 2017-05-20 2017-11-16 d'un hangar de marché de 16 development support Quotations Envelope Implementation comptoirs au marché de Missole, dans la Commune de Dibamba, Région du Littoral
CM-CRC LITTORAL-9513-CW- RFQ / Travaux de Construction d'un forage positif équipé d'une pompe électrique d'au moins 2 m3/h, alimentant un réservoir à Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Open - National 17,933.00 0.00 2017-03-25 2017-05-20 2017-11-16 cubitainer de 2000 litres monté development support Quotations Envelope Implementation sur un support en béton armé au marché de Missole, dans la Commune de Dibamba, Région du Littoral
CM-CRC LITTORAL-9514-CW- RFQ / Travaux de Construction et d'Equipement d'une Case Component A: Local Request for Single Stage - One Pending Communautaire et d'un bloc de IDA / 57180 Post Open - National 43,457.00 0.00 2017-03-25 2017-05-20 2017-09-17 development support Quotations Envelope Implementation deux latrines à Bisseng, dans la Commune de Ndom, Région du Littoral
001/T/SU/DJOUM/2017 / Travaux d'Extension du marché de vivres (aménagement du Component A: Local Request for Single Stage - One Pending hangar, construction de 03 blocs IDA / 57180 Post Limited 64,085.00 0.00 2017-04-11 2017-05-29 2017-09-26 development support Quotations Envelope Implementation de 05 boutiques et d'un bloc de 03 latrines avec local du gestionnaire) d'Ondodo
002/T/SU/MENGONG/2017 / Travaux de Réhabilitation du Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 1,046.00 0.00 2017-04-11 2017-05-29 2017-07-05 puits avec pompe à motricité development support Quotations Envelope Implementation humaine du marché d'Ondodo
004/T/SU/AKOM II/2017 / Travaux de construction de 03 puits positifs équipés des pompes à motricité humaine à Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 49,748.00 0.00 2017-04-11 2017-06-14 2017-10-12 BIBINDI, BIBOLE et MALOMBA development support Quotations Envelope Implementation et de 03 forages positifs équipés des pompes à motricité humaine NLOKENG, TOKO et FENDA
005/T/SU/OVENG/2017 / Travaux d'Aménagement du hangar en complexe commercial Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 26,185.00 0.00 2017-04-11 2017-06-14 2017-10-12 municipal et de Construction d'un development support Quotations Envelope Implementation bloc latrines à deux compartiments à Oveng-centre
006/T/SU/BIWONG BANE/2017 / Travaux d'extension du réseau électrique à travers la Component A: Local Request for Single Stage - One Pending construction d'une ligne BT de IDA / 57180 Post Limited 58,268.00 0.00 2017-04-11 2017-06-14 2017-09-12 development support Quotations Envelope Implementation 1,3 km et l'installation d'un transformateur monophasé au village Melangue II
010/T/SU/DJOUM/2017 / Travaux de construction d'un bloc Component A: Local Request for Single Stage - One Pending IDA / 57180 Prior Limited 36,375.00 0.00 2017-04-11 2017-06-14 2017-10-12 maternel à l'école maternelle development support Quotations Envelope Implementation d'Aboélon
011/T/SU/DJOUM/2017 / Component A: Local Request for Single Stage - One Pending Travaux d'extension du réseau IDA / 57180 Post Limited 31,520.00 0.00 2017-04-11 2017-06-14 2017-10-12 development support Quotations Envelope Implementation électrique vers le village Akak
012/T/SU/KYE OSSI/2017 / Travaux de construction de 02 blocs de 02 SDC équipées de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 58,744.00 0.00 2017-04-11 2017-06-14 2017-10-12 tables bancs et de 02 blocs de development support Quotations Envelope Implementation
02 latrines à l'EP de Mefoup et à l'EP de Mefou
015/T/SU/MEYOMESSALA/2017 / Transformation du marché de Meyomessala en campement touristique: (1)Travaux Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 84,100.00 0.00 2017-04-11 2017-06-14 2017-10-12 d'aménagement du bloc de 06 development support Quotations Envelope Implementation chambres modernes VIP et (2) Travaux d'aménagement des espaces verts et de la clôture
017/T/SU/MINTOM/2017 / Travaux de construction de la Component A: Local Request for Single Stage - One Pending clôture et d'aménagement des IDA / 57180 Post Limited 40,659.00 0.00 2017-04-11 2017-06-14 2017-10-12 development support Quotations Envelope Implementation aires de jeux des écoles maternelles de Mintom-centre
019/T/SU/MINTOM/2017 / Travaux de construction d'un Component A: Local Request for Single Stage - One Pending forage positif équipé d'une PMH IDA / 57180 Post Limited 10,194.00 0.00 2017-04-11 2017-06-14 2017-10-12 development support Quotations Envelope Implementation au complexe commercial de Mintom
022/T/SU/MVANGAN/2017 / Travaux de construction d'un Component A: Local Request for Single Stage - One Pending forage équipé d'une pompe à IDA / 57180 Post Limited 9,909.00 0.00 2017-04-11 2017-06-14 2017-10-12 development support Quotations Envelope Implementation motricité humaine à l'EP de Zoébefam (Zoéyevan)
023/T/SU/MVANGAN/2017 / Travaux de construction de 01 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 3,429.00 0.00 2017-04-11 2017-06-14 2017-10-12 bloc de 02 latrines à l'EP de development support Quotations Envelope Implementation
Mebemenko
024/T/SU/SANGMELIMA/2017 / Travaux de réalisation de 10 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 99,340.00 0.00 2017-04-11 2017-06-14 2017-10-12 forages équipés des pompes à development support Quotations Envelope Implementation motricité humaine
CM-CRC NORD-9682-CW-RFQ / réalisation d'un forage équipé de PMH au Centre de Santé Intégré Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 17,000.00 0.00 2017-03-20 2017-05-02 2017-07-03 de Rey Bouba, dans la decentralization process Quotations Envelope Implementation
Commune de Bouba Région du Nord
CM-CRC NORD-9683-CW-RFQ / construction d'un bâtiment à usage de bloc sanitaire et d'un Component B: Support to the Request for Single Stage - One Pending bloc de latrines à quatre IDA / 57180 Post Limited 102,000.00 0.00 2017-04-20 2017-05-25 2017-09-22 decentralization process Quotations Envelope Implementation compartiments au Centre de Santé Intégré de Dembo, dans la Commune de Dembo
CM-CRC NORD-9684-CW-RFQ / réalisation d'un mini AEP alimenté de Pompe à Energie Solaire au Centre de Santé Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 38,600.00 0.00 2017-04-20 2017-05-25 2017-09-22 Intégré de Dembo, et la decentralization process Quotations Envelope Implementation réalisation d'un forage équipé de PMH à l'EP de TAPAWA dans la Commune de DEMBO
CM-CRC NORD-9685-CW-RFQ / construction d'un bloc de deux (02) salles de classe équipées (de 60 tables bancs, de 02 bureaux d'enseignants, 02 Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 90,000.00 0.00 2017-04-20 2017-05-25 2017-09-22 placards) et d'un bloc de latrine à decentralization process Quotations Envelope Implementation trois compartiments dans les écoles publiques de Laindé Tchakoum, et Tapawa dans la Commune de Dembo
CM-CRC NORD-9686-CW-RFQ / construction d'un bloc de trois (03) salles de classe équipés ( de 90 tables bancs, de 03 bureaux d'enseignants, 03 Component B: Support to the Single Stage - One Pending IDA / 57180 Post Request for Bids Open - National 248,000.00 0.00 2017-04-17 2017-04-20 2017-05-11 2017-05-18 2017-06-22 2017-09-20 placards) et d'un bloc de latrine à decentralization process Envelope Implementation trois compartiments dans les établissement suivants : 'EP de Torroye, lycee de badjouma centre,(lot 1
CM-CRC NORD-9687-CW-RFQ / construction d'un bloc de 02 salles de classes équipées ( de 60 tables bancs, de 02 bureaux Component B: Support to the Request for Single Stage - One Pending d'enseignants, 02 placards) et IDA / 57180 Post Limited 98,000.00 0.00 2017-04-20 2017-06-15 2017-09-13 decentralization process Quotations Envelope Implementation d'un bloc de latrine à trois compartiments à l'EP DOGBA et au Lycée de GOP REY dans la Commune de Tcholliré
CM-CRC NORD-9688-CW-RFQ / construction d'un bâtiment à usage de bloc sanitaire et d'un Component B: Support to the Request for Single Stage - One Pending bloc de latrine à quatre IDA / 57180 Post Limited 108,000.00 0.00 2017-04-22 2017-06-17 2017-10-16 decentralization process Quotations Envelope Implementation compartiments au Centre de Santé Intégré à Mayo GALKE dans la Commune de Tcholliré
CM-CRC NORD-9690-CW-RFQ / réalisation d'un mini AEP alimenté de Pompe à Energie Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 28,000.00 0.00 2017-04-22 2017-06-17 2017-09-18 Solaire au Centre de Santé decentralization process Quotations Envelope Implementation
Intégré de de Mayo Galké dans la commune de tchollire
CM-CRC NORD-9692-CW-RFQ / Construction de un bloc de 03 salles équipés et d'un bloc de latrine à 04 compartiments de l'EP GII Rabingha, (LOT 1) Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 120,000.00 0.00 2017-04-22 2017-06-17 2017-09-18 Construction de 04 blocs de decentralization process Quotations Envelope Implementation latrines dans les Ecole Publique de Gounougou, Ouro Kessoum, Nelbi, Ecole Maternelle de Ngouna (LOT 2) et
CM-CRC NORD-9693-CW-RFQ / construction des 03 magasins de stockage des denrées agricoles Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 142,800.00 0.00 2017-04-22 2017-06-17 2017-09-18 à BADANKALI, MAYO BOCKI et decentralization process Quotations Envelope Implementation
DJALINGO KAPSIKI dans la Commune de Lagdo
CM-CRC NORD-9695-CW-RFQ / Electrification des quartiers Component B: Support to the Request for Single Stage - One Pending Mboum Aviation et Ouro bayel IDA / 57180 Post Limited 62,000.00 0.00 2017-04-22 2017-06-17 2017-09-18 decentralization process Quotations Envelope Implementation dans la Commune de Garoua 2, Région du Nord
CM-CRC NORD-9696-CW-RFQ / construction d'un bâtiment à usage de Centre de Santé Component B: Support to the Request for Single Stage - One Pending Intégré avec latrines à quatre IDA / 57180 Post Limited 106,000.00 0.00 2017-06-25 2017-08-20 2017-12-18 decentralization process Quotations Envelope Implementation Compartiments à DOUNDEHI dans la Commune de Touroua, Région du Nord
CM-CRC NORD-9698-CW-RFQ / construction d'un mini AEP à Component B: Support to the Request for Single Stage - One Pending Energie solaire au Centre de IDA / 57180 Post Limited 26,000.00 0.00 2017-06-25 2017-08-20 2017-12-18 decentralization process Quotations Envelope Implementation Santé de DOUNDEHI dans la commune de Touroua
Page 2 CM-CRC NORD-9699-CW-RFQ / construction et équipement d'un bloc de deux (02) salles de Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 96,000.00 0.00 2017-06-25 2017-08-20 2017-12-18 classe avec latrines EP decentralization process Quotations Envelope Implementation
BIYAOU,moudouk,dans la Commune de Madingring
CM-CRC NORD-9701-CW-RFQ / construction de deux forages Component B: Support to the Request for Single Stage - One Pending EPMH dans les villages de IDA / 57180 Post Limited 35,000.00 0.00 2017-06-25 2017-08-20 2017-12-18 decentralization process Quotations Envelope Implementation NBIEN DOLE et BALDJOUK dans la Commune de Madingring
CM-CRC NORD-9703-CW-RFQ / construction 2 blocs de 3 boutiques au marché de GOR et Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 60,000.00 0.00 2017-06-25 2017-08-20 2017-12-18 sorobéo et d'un bloc de latrines à decentralization process Quotations Envelope Implementation
6 compartiments dans la Commune de Madingring
CM-CRC NORD-9705-CW-RFQ / réalisation d'un forage au CES Bilingue de Bibémi, et exécution des travaux de la construction Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 39,000.00 0.00 2017-06-25 2017-08-20 2017-11-18 d'un forage de pastoral équipé de decentralization process Quotations Envelope Implementation
PMH et 04 abreuvoirs à BIDE HAMADICKO dans la commune de Bibémi,
CM-CRC NORD-9706-CW-RFQ / construction d'un bloc de 02 Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 46,000.00 0.00 2017-06-25 2017-08-20 2017-11-18 salles de classes avec latrines decentralization process Quotations Envelope Implementation au CES Bilingue de Bibémi
CM-CRC NORD-9707-CW-RFQ / travaux de l'aménagement de la Component B: Support to the Request for Single Stage - One Pending piste agricole BIBEMI-MBELLA IDA / 57180 Post Limited 80,000.00 0.00 2017-06-25 2017-08-20 2017-12-18 decentralization process Quotations Envelope Implementation (4Km) dans la Commune de Bibémi
CM-CRC NORD-9709-CW-RFQ / Construction de 04 forages EPMH à l'abattoir, municipal, Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 64,000.00 0.00 2017-06-25 2017-08-20 2017-12-18 Mbaou et Mbissiri et au lycée de decentralization process Quotations Envelope Implementation
GOP REY dans la Commune de Tcholliré
CM-CRC NORD-9710-CW-RFQ / construction d'un forage pastoral Component B: Support to the Request for Single Stage - One Pending équipé de Pompe à énergie IDA / 57180 Post Limited 30,000.00 0.00 2017-06-25 2017-08-20 2017-11-18 decentralization process Quotations Envelope Implementation solaire dans la commune de BASCHEO,
001/T/PNDP/EST/2017 / Component C: Coordination, Request for Single Stage - One Pending NORMALISATION DU COURANT IDA / 57180 management, monitoring and Post Limited 8,000.00 0.00 2017-08-01 2017-08-22 2017-09-21 Quotations Envelope Implementation ELECTRIQUE evaluation and communication
002/T/PNDP/EST/2017 / Component C: Coordination, Request for Single Stage - One Pending AMENAGEMENT SALLE IDA / 57180 management, monitoring and Post Limited 5,000.00 0.00 2017-04-11 2017-04-29 2017-05-29 Quotations Envelope Implementation D'ARCHIVAGE EN ETAGERE evaluation and communication
013/T/CE/ELIG MFOMO/2017 / Travaux de Construction de sept (07) forages productifs équipés de Pompe à Motricité Humaine dans sept (07) localités (Nkol- Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 113,854.00 0.00 2017-03-31 2017-05-26 2017-09-23 Obang, Ban Edouma 2, EP de development support Quotations Envelope Implementation
Mebomo, Lekoukoua, Bodo, Enobita et CES de Kokodo) dans la Commune d'Elig Mfomo, Région du Centre
014/T/CE/OBALA/2017 / Travaux de Construction d'un Component A: Local Request for Single Stage - One Pending puits equipe de PMH à nkol-Ekui IDA / 57180 Post Limited 12,000.00 0.00 2017-04-04 2017-05-30 2017-07-29 development support Quotations Envelope Implementation dans la Commune d'Obala, Région du Centre
015/T/CE/OBALA/2017 / Travaux de Construction d'un bloc de deux (02) salles de classes équipé de 60 table- Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 40,000.00 0.00 2017-04-04 2017-05-30 2017-08-28 bancs de niveau 2, de 02 development support Quotations Envelope Implementation bureaux pour enseignants à nkol- Ekui dans la Commune d'Obala, Région du Centre
016/T/CE/OBALA/2017 / Travaux d'extension du réseau Component A: Local Request for Single Stage - One Pending électrique à sur la route Elig IDA / 57180 Post Limited 84,221.00 0.00 2017-04-04 2017-05-30 2017-08-28 development support Quotations Envelope Implementation bodo- Yemsoa dans la commune d'Obala, Région du Centre
016/T/CE/MONATELE/2017 / Travaux de Construction deux (02) hangars de 32 comptoirs avec deux (02) blocs latrines à trois (03) compartiments aux Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 102,904.00 0.00 2017-04-04 2017-05-30 2017-09-27 marchés de deux (02) development support Quotations Envelope Implementation respectivement dans les localités de Ezezang et Lenouk, dans la Commune de Monatélé, Région de Centre
019/T/CE/OMBESSA/2017 / Travaux de Construction d'une mini AEP avec forage productif et Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 24,000.00 0.00 2017-04-05 2017-05-31 2017-06-30 construction d'un château à development support Quotations Envelope Implementation
Ombessa, dans la Commune de Ombessa, Région du Centre
017/T/CE/MONATELE/2017 / Travaux de Construction deux (02) hangars de 32 comptoirs avec deux (02) blocs latrines à trois (03) compartiments aux Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 102,904.00 0.00 2017-04-21 2017-06-10 2017-10-08 marchés de deux (02) development support Quotations Envelope Implementation respectivement dans les localités de Ezezang et Lenouk, dans la Commune de Monatélé, Région de Centre
020/T/CE/OLANGUINA/2017 / Travaux de Construction dun (01) hangar de 32 comptoirs au marché de Koltock et rehabilitation du marché Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 94,057.00 0.00 2017-04-21 2017-06-10 2017-10-08 d'Olanguina (10 boutiques) et development support Quotations Envelope Implementation
Construction de (02) bloc latrines à trois (03) compartiments, dans la Commune d'Olanguina, Région du Centre
021/T/CE/OLANGUINA/2017 / Travaux de Construction d'un (01) forage productif équipé d'une Component A: Local Request for Single Stage - One Pending pompe à motricité humaine au IDA / 57180 Post Limited 17,000.00 0.00 2017-04-21 2017-06-10 2017-10-08 development support Quotations Envelope Implementation marche de Koltock dans la Commune d'Olanguina, Région du Centre
022/T/CE/YAOUNDE 7/2017 / Travaux de Construction d'un magasin de stockage avec un Component A: Local Request for Single Stage - One Pending bloc latrines à deux (02) IDA / 57180 Post Limited 50,000.00 0.00 2017-04-21 2017-06-10 2017-10-08 development support Quotations Envelope Implementation Compartiments à Minkoameyos dans la commune de Yaoundé 7, Région du Centre
023/T/YAOUNDE 7/2017 / Travaux de rehabilitation d'un pont definitif de 06m de portee et 04m de large sur la riviere Angaha et de réhabilitation d'une Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 76,971.00 0.00 2017-04-21 2017-06-10 2017-10-08 piste agricole de 400m allant du development support Quotations Envelope Implementation carrefour nkolnkoumou au Centre de Promotion de la Femme, dans la commune de Yaoundé 7, Région
027/T/CE/MENGUEME/2017 / Travaux de Construction de deux (02) puits équipés de Pompes à Component A: Local Request for Single Stage - One Pending Motricité Humaine dans deux IDA / 57180 Post Limited 24,000.00 0.00 2017-04-21 2017-06-10 2017-10-08 development support Quotations Envelope Implementation (02) localités (Yeneassi et Mebemezoa) dans la commune de Mengueme, Région du Centre
026/T/CE/MFOU/2017 / Travaux de Construction d'un forage productif équipés d'une Pompe à Component A: Local Request for Single Stage - One Pending Motricité Humaine dans la IDA / 57180 Post Limited 17,000.00 0.00 2017-04-28 2017-06-17 2017-09-15 development support Quotations Envelope Implementation localité de Nkongoa dans la Commune de Mfou, Région du Centre
027/T/CE/MENGANG/2017 / Travaux de réalisation d'électrification rurale dans certaines localités, en 02 axes : Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 108,698.00 0.00 2017-04-21 2017-06-16 2017-10-14 lycée de Mengang-Meyo-Evoung development support Quotations Envelope Implementation et lycée de Menoa-Ekinguili- Bifembe, Commune de Mengang, Région du Centre
028/T/CE/ESEKA/2017 / Travaux de Construction de 02 forages equipes de pompes a Component A: Local Request for Single Stage - One Pending motricite humaine à l'hopital de IDA / 57180 Post Limited 31,923.00 0.00 2017-04-25 2017-06-14 2017-10-12 development support Quotations Envelope Implementation district et à l'EP G2 ABCD, dans la Commune d'Eséka, Région du Centre
029/T/CE/MAKAK / Travaux de Construction d'un (01) hangar de 48 comptoirs avec un (01) bloc Component A: Local Request for Single Stage - One Pending latrines à trois (03) IDA / 57180 Post Limited 59,835.00 0.00 2017-04-28 2017-06-17 2017-10-15 development support Quotations Envelope Implementation compartiments au marché de Makak centre, dans la Commune de Makak, Région du Centre
03/T/CE/MAKAK/2017 / Travaux de Construction d'un magasin de stockage avec un bloc latrines à Component A: Local Request for Single Stage - One Pending deux (02) compartiments dans la IDA / 57180 Post Limited 50,000.00 0.00 2017-04-28 2017-06-17 2017-10-15 development support Quotations Envelope Implementation localités de Mbeng dans la Commune de Makak, Région du Centre
031/T/CE/MAKAK/2017 / Travaux de Construction d'un (01) puits équipé de Pompe à Component A: Local Request for Single Stage - One Pending Motricité Humaine au marché de IDA / 57180 Post Limited 12,000.00 0.00 2017-04-28 2017-06-17 2017-10-15 development support Quotations Envelope Implementation Makak Centre, dans la Commune de Makak, Région du Centre
032/T/CE/DIBANG/2017 / Travaux de realisation d'une electrification rurale de 2700m Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 57,608.00 0.00 2017-04-21 2017-06-10 2017-10-08 dans le village Tamalong, development support Quotations Envelope Implementation
Commune de Dibang, Région du Centre
033/T/CE/DIBANG/2017 / Travaux de Construction d'un magasin de stockage avec un Component A: Local Request for Single Stage - One Pending bloc latrines à deux (02) IDA / 57180 Post Limited 50,000.00 0.00 2017-04-21 2017-06-10 2017-10-08 development support Quotations Envelope Implementation compartiments à Ndongo dans la Commune de Dibang, Région du Centre
034/T/CE/BOT MAKAK/2017 / Travaux de Construction de deux (02) forages productifs équipés de pompes à motricité humaine Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 29,803.00 0.00 2017-04-28 2017-06-17 2017-10-15 au CETIC et Centre Administratif development support Quotations Envelope Implementation de Bot-Makak, dans la Commune de Bot Makak, Région du Centre
035/T/BOT MAKAK/2017 / Travaux de Construction d'un (01) puits équipés de pompes à Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 12,000.00 0.00 2017-04-28 2017-06-17 2017-10-15 motricité humaine à Ndjock development support Quotations Envelope Implementation
Bané, dans la Commune de Bot Makak, Région du Centre
036/T/CE/NTUI/2017 / Travaux de Construction de deux (02) magasins de stockage de cacao et construction de 02 blocs Component A: Local Request for Single Stage - One Pending latrines à deux (02) IDA / 57180 Post Limited 125,749.00 0.00 2017-05-01 2017-06-20 2017-10-18 development support Quotations Envelope Implementation compartiments dans les localités de Nguila, et Ntui ville) dans la Commune de Ntui, Région du Centre
CM-CRC ADAMAOUA-11713- CW-RFQ / Travaux de réalisation d'une clôture de 19 KM linéaire en vue de sécuriser une zone agricole de 2 396 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 107,992.00 0.00 2017-04-10 2017-06-05 2017-12-02 hectares autour des villages Bola development support Quotations Envelope Implementation
Galé-Bello, Ba-Zaïre, Mbibale, Kanan et Gbawa, Commune de Tibati, Département du Djérem, Région de l'Adamaoua
CM-CRC ADAMAOUA-11716- CW-RFQ / Travaux de construction d'un pont long de 8 Component A: Local Request for Single Stage - One Pending m et large de 5 m sur le Mayo IDA / 57180 Post Limited 77,661.00 0.00 2017-04-10 2017-06-05 2017-12-02 development support Quotations Envelope Implementation Massim réliant le village Pangar à Ngaoundal, Département du Djérem, Région de l'Adamaoua
CM-CRC ADAMAOUA-11747- CW-RFQ / Travaux de construction de 02 dalots (01 dalot simple de section 1,50m x 2,00m et 01 dalot quatre de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 85,052.00 0.00 2017-04-10 2017-06-05 2017-12-02 section 1,50mx2,20m) sur la development support Quotations Envelope Implementation rivière Mbirim réliant l'Ecole Publique de Mbirim au Centre du Village Mbirim et 01 dalot simple de section 1,50mx2,00m
CM-CRC ADAMAOUA-11749- CW-RFQ / Travaux de construction de cinq (05) boutiques, quatres (04) blocs Component A: Local Request for Single Stage - One Pending sécrétariats bureautiques et un IDA / 57180 Post Limited 83,880.00 0.00 2017-04-05 2017-05-24 2017-11-20 development support Quotations Envelope Implementation bloc de deux latrines au Carrefour Malang, Commune de Ngaoundéré 3, Département de la Vina, Région de l'Adamaoua
CM-CRC ADAMAOUA-11751- CW-RFQ / Travaux de construction de cinq (05) buses et aménagement des rigoles sur Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 54,938.00 0.00 2017-04-05 2017-05-24 2017-11-20 les points crtiques de la route development support Quotations Envelope Implementation
Manwi - Mbella, Commune de Ngaoundéré 3, Département de la Vina, Région de l'Adamaoua
CM-CRC ADAMAOUA-11752- CW-RFQ / Travaux de construction d'une case communautaire et un bloc de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 72,697.00 0.00 2017-04-05 2017-05-24 2017-11-20 deux latrines à Martap, development support Quotations Envelope Implementation
Commune de Martap, Département de la Vina, Région de l'Adamaoua
CM-CRC ADAMAOUA-11753- CW-RFQ / Travaux de construction de deux Hangars de Marché de 32 comptoires chacun Component A: Local Request for Single Stage - One Pending en Beton Armés et un bloc de IDA / 57180 Post Limited 44,492.00 0.00 2017-04-05 2017-05-24 2017-11-20 development support Quotations Envelope Implementation deux latrines au Marché des Femmes de Tekel, Commune de Martap, Département de la Vina, Région de l'Adamaoua
CM-CRC ADAMAOUA-11754- CW-RFQ / Travaux de contruction d'une AEP à travers le captage d'une source d'eau et la construction d'un reservoir de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 131,119.00 0.00 2017-04-05 2017-05-24 2017-11-20 12 métres cubes, 04 bornes development support Quotations Envelope Implementation fontaines et 04 abreuvoirs à bétail dans le village Bawa, Commune de Martap, Département de la Vina, Région de l'Ada
CM-CRC ADAMAOUA-11756- CW-RFQ / Travaux de construction d'un bain détiqueur Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 67,572.00 0.00 2017-04-05 2017-05-24 2017-11-20 à Toumbouroum, Commune de development support Quotations Envelope Implementation
Martap, Département de la Vina, Région de l'Adamaoua
Page 3 CM-CRC ADAMAOUA-11758- CW-RFQ / Traveaux de réalisation d'une barrière (clôture en fils barbélés) de 13 196 métres linéaires pr la Component A: Local Request for Single Stage - One Pending sécurisation de 04 espaces IDA / 57180 Post Limited 76,407.00 0.00 2017-04-05 2017-06-02 2017-11-29 development support Quotations Envelope Implementation agropastoraux de 2 211,5 Hectares dans 04 villages : Boforo (1 589 ha), Malingara (381 ha), Bindiba (153 ha) et Kalaldi (8ha)
CM-CRC ADAMAOUA-11760- CW-RFQ / Travaux de construction d'une case Component A: Local Request for Single Stage - One Pending communautaire et un bloc de IDA / 57180 Post Limited 88,855.00 0.00 2017-04-05 2017-06-02 2017-11-29 development support Quotations Envelope Implementation deux latrines à Dir, Commune de Dir, Département du Mbéré, Région de l'Adamaoua
CM-CRC ADAMAOUA-11763- CW-RFQ / Travaux de construction de 02 blocs de 02 salles de classe équipés de 60 Component A: Local Request for Single Stage - One Pending tabales bancs et un bloc de 02 IDA / 57180 Post Limited 94,598.00 0.00 2017-04-05 2017-06-02 2017-11-29 development support Quotations Envelope Implementation latrines chacun au CETIC de Dir et à l'EP de DOBIRI, Département du Mbéré, Région de l'Adamaoua
CM-CRC ADAMAOUA-11764- CW-RFQ / Travux de construction d'un forage positif Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 17,148.00 0.00 2017-04-05 2017-06-06 2017-12-03 équipe de PMH au CETIC de Dir, development support Quotations Envelope Implementation
Département du Mbéré, Région de l'Adamaoua
CM-CRC ADAMAOUA-11765- CW-RFQ / Travaux de construction de deux blocs de 02 salles de classe équipés de 60 tables bancs et un bloc de deux Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 107,510.00 0.00 2017-04-05 2017-06-02 2017-11-29 latrines chacun à EP de Dilecti development support Quotations Envelope Implementation et à l'EP Bilingue de Gadjiwan, Commune de Mayo Baléo, Département du Faro et Déo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11766- CW-RFQ / Travaux de construction de trois forages positifs équipés des PMH dans les EP de Dilecti et Gadjiwan et Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 51,596.00 0.00 2017-04-05 2017-06-02 2017-11-29 au Centre de Promotion de la development support Quotations Envelope Implementation
Femme et de la Famille (CPFF) du Mayo Baléo, Département du Faro et Déo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11768- CW-RFQ / Travaux de construction et d'équipement d'un Centre de Promotion de la Component A: Local Request for Single Stage - One Pending Femme et de la Famille (CPFF) IDA / 57180 Post Limited 156,105.00 0.00 2017-04-05 2017-06-02 2017-11-29 development support Quotations Envelope Implementation avec latrines incorporées de Mayo Baléo, Commune de Mayo Baléo, Département du Faro et Déo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11769- CW-RFQ / Contruction de 02 forages Positifs équipés des PMH au Lycée de Béka Modibo et à l'EP de LIPAO et Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 66,399.00 0.00 2017-04-05 2017-06-06 2017-12-03 Réhabilitation de 04 forages: development support Quotations Envelope Implementation
Goungel Pastoral (Quartier Tola), Baringo, Mambéré Hassimi, Mayo Badji et 01 puits équipé de PMH à l'EP Goumgel Troua
CM-CRC ADAMAOUA-11770- CW-RFQ / Travaux de réalisation d'une mini adduction d'eau avec Component A: Local Request for Single Stage - One Pending sept (07) bornes fontaines à IDA / 57180 Post Limited 130,910.00 0.00 2017-04-05 2017-06-06 2017-12-03 development support Quotations Envelope Implementation Bandam, Commune de Bankim, Département du Mayo Banyo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11772- CW-RFQ / Travaux de réalisation d'une clôture de séparation de 5 750 métres des espaces agricoe (3 6168 Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 44,033.00 0.00 2017-04-09 2017-06-11 2017-12-08 Hectares) et pastoral (3 965 development support Quotations Envelope Implementation
Hectares) dans la localité de Bandam, Commune de Bankim, Département du Mayo Banyo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11773- CW-RFQ / Travaux de réhabilitation de quatre (04) forages dans quatre (04) Component A: Local Request for Single Stage - One Pending quartiers de la ville de Bankim IDA / 57180 Post Limited 22,811.00 0.00 2017-04-09 2017-06-11 2017-12-08 development support Quotations Envelope Implementation (Nguinklo, Chefferie Bankim, Newton et Tchim), Commune de Bankim, Département du Mayo Banyo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11774- CW-RFQ / Travaux de construction d'un parc Component A: Local Request for Single Stage - One Pending vaccinogène à Haïnaré, IDA / 57180 Post Limited 30,160.00 0.00 2017-04-09 2017-06-11 2017-12-08 development support Quotations Envelope Implementation Commune de Bankim, Département du Mayo Banyo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11775- CW-RFQ / Travaux de construction d'une case communautaire et un bloc de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 64,703.00 0.00 2017-04-09 2017-06-11 2017-12-08 deux latrines à Diéki, Commune development support Quotations Envelope Implementation de Bankim, Département du Mayo Banyo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11776- CW-RFQ / Travaux de construction d'une case communautaire et un bloc de Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 64,703.00 0.00 2017-04-09 2017-06-11 2017-12-08 deux latrines à YIMBERE, development support Quotations Envelope Implementation
Commune de Bankim, Département du Mayo Banyo, Région de l'Adamaoua
001/T/SW/MENJI/CRC/2017 / Travaux de construction et équipement d'un foyer communautaire et Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Open - National 60,000.00 0.00 2017-04-27 2017-05-18 2017-11-14 multifonctionnel et un bloc latrine development support Quotations Envelope Implementation
à trois compartiments à MBOEH dans la Commune de Menji, Région du Sud-Ouest
001/T/SW/BAMUSSO/CRC/2017 / Travaux de Construction d'un magasin de stockage et d'un Component A: Local Request for Single Stage - One Pending bloc latrine à deux (02) IDA / 57180 Post Open - National 54,967.00 0.00 2017-05-02 2017-06-27 2017-12-24 development support Quotations Envelope Implementation compartiments à Bekiri Beach dans la Commune de Bamusso, Région du Sud-Ouest
001/T/SW/MUYUKA/CRC/2017 / Travaux de construction d'un Component A: Local Request for Single Stage - One Pending grand hangar au marché de Yoke IDA / 57180 Post Open - National 63,558.00 0.00 2017-05-02 2017-06-27 2017-12-24 development support Quotations Envelope Implementation dans la Commune de Muyuka, Région du Sud-Ouest
001/T/SW/EKONDO TITI/CRC/2017 / Travaux de Construction de l'Ecole Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Open - National 55,020.00 0.00 2017-05-02 2017-06-27 2017-12-24 Maternelle de Funge dans la development support Quotations Envelope Implementation
Commune d'Ekondo Titi, Région du Sud-Ouest
001/T/SW/TOMBEL/CRC/2017 / Travaux de construction d'un grand Hangar, d'un bloc latrine à Component A: Local Request for Single Stage - One Pending trois compartiments et d'une IDA / 57180 Post Open - National 72,523.00 0.00 2017-05-02 2017-06-27 2017-12-24 development support Quotations Envelope Implementation borne fontaine au marché de Tombel dans la Commune de Tombel, Région du Sud-Ouest
002/T/SW/EKONDO TITI/CRC/2017 / Travaux de réalisation Réalisation d'un forage positif équipé d'une pompe Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Open - National 27,657.00 0.00 2017-05-02 2017-06-27 2017-12-24 électrique fonctionnant avec development support Quotations Envelope Implementation l'energie solaire à l'EM de Funge la Commune d'Ekondo Titi, Région du Sud-Ouest
001/T/SW/MBONGE/CRC/2017 / Travaux de réalisation de deux (02) forages productifs équipés de pompes à motricité humaine Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Open - National 34,135.00 0.00 2017-05-02 2017-06-27 2017-12-24 dans les écoles publiques de development support Quotations Envelope Implementation
Marumba et Kotto Barumbi dans la Commune de Mbonge, Région du Sud-Ouest
001/T/SW/MUNDEMBA/CRC/20 17 / Travaux de réalisation de trois (03) forages productifs équipés de pompes à motricité Component A: Local Request for Single Stage - One Pending humaine dans les écoles IDA / 57180 Post Open - National 59,575.00 0.00 2017-05-06 2017-07-01 2017-12-28 development support Quotations Envelope Implementation primaires de Ndian Estate, Besingi et Fabe dans la Commune de Mundemba, Région du Sud-Ouest
GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
CM-PNDP-2738-GO-RFQ / Fourniture des groupes Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Open - National 68,000.00 0.00 2017-02-17 2017-04-14 2017-10-11 électrogènes pour les communes decentralization process Quotations Envelope Implementation sim_ba
CM-PNDP-2739-GO-RFQ / Acquisition des fournitures de Component C: Coordination, Request for Single Stage - One Pending bureau, produits d'entretien, IDA / 57180 management, monitoring and Post Limited 80,000.00 0.00 2016-10-26 2016-12-21 2017-06-19 Quotations Envelope Implementation matériel et produits pause-café, evaluation and communication et consommables informatiques
Component B: Support to the CM-PNDP-2836-GO-UN / decentralization process Pending Acquisition de véhicules et IDA / 57180 Component C: Coordination, Prior UN Agencies (Direct) Direct 2,328,000.00 0.00 2016-10-27 2016-11-01 2016-12-06 2017-06-04 Implementation motos par UNOPS management, monitoring and evaluation and communication
Component C: Coordination, CM-PNDP-2839-GO-RFQ / Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 60,000.00 0.00 2016-11-01 2016-12-27 2017-06-25 Edition des documents à la CNC Quotations Envelope Implementation evaluation and communication
CM-PNDP-2835-GO-RFB / Component C: Coordination, Single Stage - One Under Fourniture du mobilier de bureau IDA / 57180 management, monitoring and Post Request for Bids Open - National 200,000.00 0.00 2016-12-11 2016-12-27 2016-12-16 2017-01-27 2017-01-27 2017-02-26 2017-04-02 2017-09-29 Envelope Implementation pour la CNC et les 10 CRC evaluation and communication
CM-PNDP-2736-GO-RFB / Component C: Coordination, Fourniture et installation du Single Stage - One Pending IDA / 57180 management, monitoring and Prior Request for Bids Open - National 490,000.00 0.00 2016-11-09 2016-11-14 2016-12-26 2017-01-25 2017-03-01 2017-08-28 matériel informatique et du Envelope Implementation evaluation and communication matériel didactique au PNDP
CM-PNDP-6227-GO-RFQ / Component C: Coordination, Fourniture des supports de Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 10,000.00 0.00 2017-02-09 2017-04-06 2017-10-03 communication dans le cadre du Quotations Envelope Implementation evaluation and communication lancement du PNDP III
CM-PNDP-2932-GO-RFB / Production du bulletin trimestriel Component B: Support to the Single Stage - One Pending de certaines communes (10 IDA / 57180 Post Request for Bids Open - National 360,000.00 0.00 2016-12-12 2016-12-17 2017-01-28 2017-02-27 2017-04-03 2017-09-30 decentralization process Envelope Implementation Agences de communications au niveau régional)
001/F/PNDP/EST / Fournitures Component C: Coordination, Request for Single Stage - One Pending de bureau, matériels d'entretien IDA / 57180 management, monitoring and Post Limited 9,000.00 0.00 2017-03-06 2017-05-01 2017-05-31 Quotations Envelope Implementation et divers evaluation and communication
001-F-LT-CRC-2017 / Component C: Coordination, Acquisition du Kit de l'ingénieur Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 1,500.00 0.00 2017-03-12 2017-05-07 2017-05-28 de la Cellule Régionale de Quotations Envelope Implementation evaluation and communication Coordination du Littoral
004/F/SU/CRC/2017 / Component C: Coordination, Request for Single Stage - One Pending Acquisition des consommables IDA / 57180 management, monitoring and Post Limited 7,240.00 0.00 2017-07-13 2017-08-14 2017-08-28 Quotations Envelope Implementation informatiques evaluation and communication
CM-CRC SOUTH WEST-7988- GO-RFQ / Acquisition des Component C: Coordination, Request for Single Stage - One Pending fournitures de bureau, du matérielIDA / 57180 management, monitoring and Post Limited 8,000.00 0.00 2017-04-14 2017-05-14 2017-05-31 Quotations Envelope Implementation d'entretien et divers à la CRC, evaluation and communication Région du Sud-Ouest
CM-CRC EXTREME NORD-7991- GO-RFQ / Acquisition des Component C: Coordination, fournitures de bureaux du Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 10,000.00 0.00 2017-03-10 2017-05-05 2017-05-19 matériels d'entretien et des Quotations Envelope Implementation evaluation and communication fournitures diverses à la CRC, Région de l'Extrême-Nord
002/F/PNDP/EST / Component C: Coordination, ACQUISITION DES Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 5,000.00 0.00 2017-03-06 2017-05-01 2017-05-31 FOURNITURES POUR Quotations Envelope Implementation evaluation and communication VEHICULE
001/F/CRCOU/2017 / Acquisition des fournitures de bureaux (Papier format, Chemises, Stylos, crayons, Component C: Coordination, Request for Single Stage - One Pending agraphes, trombones, etc...) pour IDA / 57180 management, monitoring and Post Limited 9,900.00 0.00 2017-03-25 2017-05-20 2017-11-16 Quotations Envelope Implementation le fonctionnement de la Cellule evaluation and communication Régionale de Coordination Ouest du PNDP, dans la Région de l'Ouest
003/F/PNDP/EST / ACQUISITION DES Component C: Coordination, Request for Single Stage - One Pending CONSOMMABLES IDA / 57180 management, monitoring and Post Limited 16,000.00 0.00 2017-03-06 2017-05-01 2017-05-31 Quotations Envelope Implementation INFORMATIQUES A LA CRC evaluation and communication EST
CM-CRC EXTREME NORD-8000- GO-RFQ / Acquisition des consomables Informatiques Component C: Coordination, Request for Single Stage - One Pending (Encres, clés internet, CD, 2 IDA / 57180 management, monitoring and Post Limited 10,000.00 0.00 2017-03-10 2017-05-05 2017-05-19 Quotations Envelope Implementation disques durs externes Tera, 9 evaluation and communication clés USB, antivirus) à la CRC, Région de l'Extrême-Nord
CM-CRC NORTH WEST-8002- Component C: Coordination, GO-RFQ / fournitures des Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 10,000.00 0.00 2017-03-18 2017-05-07 2017-05-22 services de gardiennage, la Quotations Envelope Implementation evaluation and communication CRC, Région du Nord-Ouest.
CM-CRC EXTREME NORD-8001- GO-RFQ / Acquisition des fournitures pour véhicules Component C: Coordination, ((5pneusX3véh), 3 boîtes à Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 10,000.00 0.00 2017-03-10 2017-05-05 2017-05-19 pharmacie, 3 extincteurs,3 Quotations Envelope Implementation evaluation and communication pelles, 6 paires de gants, 3machettes, 3manteaux...) à la CRC, Région de l'Extrême-Nord
CM-CRC EXTREME NORD-8003- Component C: Coordination, GO-RFQ / acquisition, Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 9,000.00 0.00 2017-03-10 2017-05-05 2017-07-04 aménagement et équipement de Quotations Envelope Implementation evaluation and communication 2 conteneurs de 40 pieds
CM-CRC EXTREME NORD-8006- Component C: Coordination, Request for Single Stage - One Pending GO-RFQ / aquisition et IDA / 57180 management, monitoring and Post Limited 6,000.00 0.00 2017-03-10 2017-05-05 2017-06-04 Quotations Envelope Implementation installation de 10 splits evaluation and communication
CM-CRC LITTORAL-8007-GO- RFQ / Acquisition de Component C: Coordination, Request for Single Stage - One Pending consommables informatiques et IDA / 57180 management, monitoring and Post Limited 7,240.00 0.00 2017-03-12 2017-05-07 2017-05-28 Quotations Envelope Implementation antivirus à la CRC, Région du evaluation and communication Littoral
CM-CRC EXTREME NORD-8008- GO-RFQ / acquisition du kit à Component C: Coordination, outils du CCI(scléromètre, Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 1,500.00 0.00 2017-03-10 2017-05-05 2017-06-04 lazermètre, odomètre, pi à Quotations Envelope Implementation evaluation and communication coulisse électronique, EPI, Gilets de sauvetage
Page 4 CM-CRC LITTORAL-8010-GO- RFQ / Acquisition de fournitures Component C: Coordination, d'Equipement de Protection Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 4,800.00 0.00 2017-03-12 2017-05-07 2017-05-21 Individuelle (EPI) et matériel Quotations Envelope Implementation evaluation and communication d'entretien à la CRC, Région du Littoral
CM-CRC EXTREME NORD-8009- GO-RFQ / fourniture des services Component C: Coordination, de maintenance électrique, Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 4,800.00 0.00 2017-03-10 2017-05-05 2018-05-05 climatiseurs, groupe électrogène, Quotations Envelope Implementation evaluation and communication plolmberie et menuiserie à la CRC, Région de l'Extrême-Nord
CM-CRC LITTORAL-8011-GO- RFQ / Acquisition de fournitures Component C: Coordination, pour véhicules (Pneus, pare Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 9,000.00 0.00 2017-03-12 2017-05-07 2017-06-06 buffles, pare chocs, alarmes, Quotations Envelope Implementation evaluation and communication tapis, boîte à pharmacie,...) de la CRC, Région du Littoral
CM-CRC NORTH WEST-8005- Component C: Coordination, GO-RFQ / Acquisition du Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 5,000.00 0.00 2017-03-18 2017-05-13 2017-05-29 materiel d'entretien et divers à la Quotations Envelope Implementation evaluation and communication CRC, Région du Nord-Ouest
CM-CRC LITTORAL-8014-GO- RFQ / Acquisition des fournitures Component C: Coordination, Request for Single Stage - One Pending de bureaux et divers à la Cellule IDA / 57180 management, monitoring and Post Limited 12,000.00 0.00 2017-03-12 2017-05-07 2017-05-22 Quotations Envelope Implementation Régionale de Coordination, evaluation and communication Région du Littoral
CM-CRC LITTORAL-8017-GO- RFQ / Acquisition du mobilier de bureau pour l'Assistant Régional chargé de la Passation des Component C: Coordination, Request for Single Stage - One Pending Marchés et de l'Archivage (01 IDA / 57180 management, monitoring and Post Limited 900.00 0.00 2017-03-12 2017-05-07 2017-05-28 Quotations Envelope Implementation chaise, 01 bureau avec retour et evaluation and communication 01 chaise de réception) de la Cellule Régionale de Coordination, Région du Littoral
01/F/CRC/CE/2017 / Acquisition Component C: Coordination, Request for Single Stage - One Pending du kit CCI à la CRC, Région du IDA / 57180 management, monitoring and Post Limited 4,500.00 0.00 2017-03-23 2017-05-07 2017-06-06 Quotations Envelope Implementation Centre evaluation and communication
02/F/CRC/CE/2017 / Acquisition Component C: Coordination, des fournitures de bureau et Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 19,600.00 0.00 2017-03-23 2017-05-07 2017-06-06 divers à la CRC, Région du Quotations Envelope Implementation evaluation and communication Centre
CM-CRC SOUTH WEST-8044- Component C: Coordination, GO-RFQ / Acquisition des Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 8,000.00 0.00 2017-04-09 2017-06-04 2017-12-01 consommables informatiques à Quotations Envelope Implementation evaluation and communication la CRC, Région du Sud-Ouest
CM-CRC NORTH WEST-8051- GO-RFQ / Acquisition de Component C: Coordination, Request for Single Stage - One Pending fournitures pour véhicules IDA / 57180 management, monitoring and Post Limited 8,690.00 0.00 2017-03-18 2017-05-13 2017-06-02 Quotations Envelope Implementation (pneus,pelles,...etc) à la CRC, evaluation and communication Région du Nord-Ouest
CM-CRC SOUTH WEST-8049- GO-RFQ / Acquisition des fournitures pour véhicules (pneus, Component C: Coordination, Request for Single Stage - One Pending boîte à pharmacie, extincteur de IDA / 57180 management, monitoring and Post Limited 9,998.00 0.00 2017-04-09 2017-06-04 2017-12-01 Quotations Envelope Implementation véhicule, petit matériel evaluation and communication (machette, lampe de poche ) Région à la CRC, du Sud-Ouest
002/F/CRCOU/2017 / Acquisition des fournitures pour véhicules (trousse de secours, tapis, Extincteur, Fournitures et Component C: Coordination, Request for Single Stage - One Pending montage des Pneus, etc...) pour IDA / 57180 management, monitoring and Post Limited 21,978.00 0.00 2017-04-06 2017-06-01 2017-07-17 Quotations Envelope Implementation leur fonctionnement à la Cellule evaluation and communication Régionale de Coordination Ouest du PNDP, dans la Région de l'Ouest
CM-CRC SOUTH WEST-8055- GO-RFQ / Fourniture des services de maintenance du parc Component C: Coordination, Request for Single Stage - One Pending et réseau informatique, IDA / 57180 management, monitoring and Post Limited 4,000.00 0.00 2017-03-11 2017-05-06 2017-11-02 Quotations Envelope Implementation téléphonique ainsi que du evaluation and communication matériel de reprographie à la CRC, Région du Sud-Ouest
CM-CRC NORTH WEST-8060- GO-RFQ / Acquisition du Component C: Coordination, materiel de classement et Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 8,000.00 0.00 2017-03-18 2017-05-13 2017-05-30 d'archivage (Communes,minmap Quotations Envelope Implementation evaluation and communication et CRC), à la CRC, Région du Nord-Ouest.
CM-CRC NORTH WEST-8063- Component C: Coordination, GO-RFQ / Acquisition du kit de Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 1,500.00 0.00 2017-04-01 2017-05-27 2017-06-26 l'Ingénieur, à la CRC, Région du Quotations Envelope Implementation evaluation and communication Nord-Ouest.
001/F/SU/CRC/2017 / Component C: Coordination, Acquisition des fournitures de Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 26,000.00 0.00 2017-03-06 2017-04-10 2017-10-21 bureaux, du matériel d'entretien Quotations Envelope Implementation evaluation and communication et divers
CM-CRC SOUTH WEST-8066- GO-RFQ / Fourniture des Component C: Coordination, Request for Single Stage - One Pending services de collecte, transport et IDA / 57180 management, monitoring and Post Limited 2,400.00 0.00 2017-03-11 2017-05-06 2017-11-02 Quotations Envelope Implementation distribution des courriers et colis evaluation and communication à la CRC, Région du Sud-Ouest
CM-CRC NORTH WEST-8069- Component C: Coordination, GO-RFQ / Acquisition de Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 7,450.00 0.00 2017-04-01 2017-05-27 2017-06-27 consommables informatiques à Quotations Envelope Implementation evaluation and communication la CRC, Région du Nord-Ouest
04/F/CRC/CE/2017 / Acquisition Component C: Coordination, des consommables Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 19,600.00 0.00 2017-03-23 2017-05-07 2017-06-06 informatiques à la CRC, Région Quotations Envelope Implementation evaluation and communication du Centre
CM-CRC SOUTH WEST-8070- Component C: Coordination, GO-RFQ / Fourniture des Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 7,200.00 0.00 2017-04-09 2017-06-04 2017-12-01 services de gardiennage à la Quotations Envelope Implementation evaluation and communication CRC, Région du Sud-Ouest
CM-CRC NORTH WEST-8073- Component C: Coordination, GO-RFQ / Acquisition du Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 5,000.00 0.00 2017-03-18 2017-05-13 2017-06-12 materiel d'entretien et divers à la Quotations Envelope Implementation evaluation and communication CRC, Région du Nord-Ouest
003/F/CRCOU/2017 / Acquisition et fourniture des Consomables Informatiques (Encre pour Copieurs (trois Component C: Coordination, copieurs), Encre pour huit Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 19,800.00 0.00 2017-03-30 2017-05-25 2017-06-08 imprimantes, CD vierges, etc...) Quotations Envelope Implementation evaluation and communication pour le fonctionnement de la Cellule Régionale de Coordination Ouest du PNDP, dans la Région de l'Ouest
002/F/SU/CRC/2017 / Component C: Coordination, Acquisition et installation d'un Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 30,000.00 0.00 2017-03-06 2017-04-10 2017-05-02 groupe électrogène complet de Quotations Envelope Implementation evaluation and communication 10 KVA
CM-CRC LITTORAL-8064-GO- RFQ / Fourniture de services d'assistance informatique et autres services de normalisation Component C: Coordination, Request for Single Stage - One Pending du courant électrique et entretien IDA / 57180 management, monitoring and Post Limited 17,200.00 0.00 2017-03-12 2017-05-07 2018-05-07 Quotations Envelope Implementation split, maintenance et entretien evaluation and communication matériel et réseau informatique, appui technique divers, à la CRC, région du Littoral
CM-CRC SOUTH WEST-8075- GO-RFQ / Acquisition de 12 boîtes étagères de rangement en Component C: Coordination, Request for Single Stage - One Pending bois massif 1,5x1,2x1) , une IDA / 57180 management, monitoring and Post Limited 7,900.00 0.00 2017-04-09 2017-06-04 2017-12-01 Quotations Envelope Implementation table en bois massif et 04 evaluation and communication chaises en bois massif à la CRC, Région du Sud-Ouest
05/F/CRC/CE/2017 / AcquisItion Component C: Coordination, Request for Single Stage - One Pending des fournitures pour véhicules à IDA / 57180 management, monitoring and Post Limited 16,070.00 0.00 2017-03-23 2017-05-07 2017-06-06 Quotations Envelope Implementation la CRC, Région du Centre evaluation and communication
CM-CRC ADAMAOUA-8079-GO- Component C: Coordination, RFQ / Acquisition caisse à outil Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 1,445.00 0.00 2017-05-03 2017-06-28 2017-12-25 de l'ingénieur de la CRC, Région Quotations Envelope Implementation evaluation and communication Adamaoua
CM-CRC NORD-8085-GO-RFQ / Component C: Coordination, Request for Single Stage - One Pending Acquisition de fournitures de IDA / 57180 management, monitoring and Post Limited 19,600.00 0.00 2017-03-20 2017-05-15 2017-05-29 Quotations Envelope Implementation bureaux et divers à la CRC Nord evaluation and communication
003/F/SU/CRC/2017 / Component C: Coordination, Acquisition du kit du CCI (Pied à Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 1,500.00 0.00 2017-07-13 2017-08-14 2017-08-28 coulisse électronique, Odomètre, Quotations Envelope Implementation evaluation and communication lasermètre, Scléromètre, EPI)
06/F/CRC/CE/2017 / Fourniture de service de maintenance du Component C: Coordination, Request for Single Stage - One Pending réseau informatique et IDA / 57180 management, monitoring and Post Limited 3,600.00 0.00 2017-03-23 2017-05-07 2017-06-06 Quotations Envelope Implementation téléphonique à la CRC, Région evaluation and communication du Centre
CM-CRC NORTH WEST-8077- Component C: Coordination, GO-RFQ / Acquisition des Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 12,000.00 0.00 2017-03-18 2017-05-13 2017-06-12 fournitures de bureaux, à la CRC, Quotations Envelope Implementation evaluation and communication Région du Nord-Ouest
CM-CRC LITTORAL-8084-GO- RFQ / Acquisition des fournitures Component C: Coordination, Request for Single Stage - One Pending pour assistance au classement IDA / 57180 management, monitoring and Post Limited 5,418.00 0.00 2017-03-12 2017-05-07 2017-05-21 Quotations Envelope Implementation et à l'archivage de 23 communes evaluation and communication dans la région du Littoral
07/F/CRC/CE/2017 / Fourniture Component C: Coordination, de service de maintenance des Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 2,400.00 0.00 2017-03-23 2017-05-07 2017-06-06 copieurs et imprimantes à la Quotations Envelope Implementation evaluation and communication CRC, Région du Centre
08/F/CRC/CE/2017 / Fourniture de service de transport des colis Component C: Coordination, Request for Single Stage - One Pending en vue de déménagement des IDA / 57180 management, monitoring and Post Limited 9,800.00 0.00 2017-03-23 2017-05-07 2017-06-06 Quotations Envelope Implementation locaux à la CRC, Région du evaluation and communication Centre
09/F/CRC/CE/2017 / Fourniture Component C: Coordination, Request for Single Stage - One Pending des services de gardiennage à la IDA / 57180 management, monitoring and Post Limited 9,600.00 0.00 2017-03-23 2017-05-07 2017-06-06 Quotations Envelope Implementation CRC, Région du Centre evaluation and communication
CM-CRC LITTORAL-8092-GO- Component C: Coordination, RFQ / Fourniture des services de Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 9,600.00 0.00 2017-03-12 2017-05-07 2018-05-07 gardiennage des locaux de la Quotations Envelope Implementation evaluation and communication CRC, région du Littoral
005/F/SU/CRC/2017 / Component C: Coordination, Request for Single Stage - One Pending Acquisition des fournitures pour IDA / 57180 management, monitoring and Post Limited 6,300.00 0.00 2017-07-13 2017-08-14 2017-08-28 Quotations Envelope Implementation véhicules (pneus, etc...) evaluation and communication
CM-CRC SOUTH WEST-8091- GO-RFQ / Acquisition du kit de Component C: Coordination, Request for Single Stage - One Pending l'Ingénieur (pied à coulisse, IDA / 57180 management, monitoring and Post Limited 1,500.00 0.00 2017-04-09 2017-06-04 2017-12-01 Quotations Envelope Implementation double deca metre,...) à la CRC, evaluation and communication Région du Sud-Ouest
CM-CRC NORD-8105-GO-RFQ / Component C: Coordination, Request for Single Stage - One Pending Acquisition de fournitures pour IDA / 57180 management, monitoring and Post Limited 19,600.00 0.00 2017-04-17 2017-06-12 2017-06-26 Quotations Envelope Implementation véhicules à la CRC NORD evaluation and communication
CM-CRC NORD-8116-GO-RFQ / Component C: Coordination, Request for Single Stage - One Pending Acquisition des consommables IDA / 57180 management, monitoring and Post Open - National 19,600.00 0.00 2017-03-20 2017-05-15 2017-05-29 Quotations Envelope Implementation informatiques à la CRC Nord evaluation and communication
CM-CRC NORD-8120-GO-RFQ / Component C: Coordination, Acquisition de matériels relatifs à Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 4,000.00 0.00 2017-04-17 2017-06-12 2017-06-26 l'archivage des documents dans Quotations Envelope Implementation evaluation and communication les 21 Communes du Nord
004/F/CRCOU/2017 / Fourniture des services de gardiennage des Component C: Coordination, Request for Single Stage - One Pending locaux à la Cellule Régionale de IDA / 57180 management, monitoring and Post Limited 9,600.00 0.00 2017-03-30 2017-05-03 2017-05-17 Quotations Envelope Implementation Coordination Ouest du PNDP, evaluation and communication dans la Région de l'Ouest
CM-PNDP-2737-GO-RFQ / Component B: Support to the Request for Single Stage - One Pending Fourniture de Kits solaires pour IDA / 57180 Post Open - National 52,000.00 0.00 2017-02-10 2017-04-07 2017-10-04 decentralization process Quotations Envelope Implementation les communes de sim_ba
CM-CRC NORD-8536-GO-RFQ / fourniture de service de transport Component C: Coordination, Request for Single Stage - One Pending pour collecte transport et IDA / 57180 management, monitoring and Post Limited 1,560.00 0.00 2017-03-20 2017-04-24 2017-12-31 Quotations Envelope Implementation distribution de courriers et colis evaluation and communication de la CRC NORD
CM-CRC NORD-8537-GO-RFQ / Component C: Coordination, Request for Single Stage - One Pending ACQUISITION KIT CCI CRC IDA / 57180 management, monitoring and Post Limited 1,500.00 0.00 2017-04-17 2017-05-29 2017-06-29 Quotations Envelope Implementation NORD evaluation and communication
CM-CRC NORD-8538-GO-RFQ / Component C: Coordination, Fourniture des services de Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 4,800.00 0.00 2017-04-17 2017-05-29 2017-12-31 maintenance du groupe Quotations Envelope Implementation evaluation and communication électrogène à la CRC Nord
CM-CRC NORD-8539-GO-RFQ / Fourniture du petit matériel médical et du mobilier en bois au Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 9,800.00 0.00 2017-03-20 2017-04-20 2017-05-22 au CSI de OURO ARDO dans la decentralization process Quotations Envelope Implementation
Commune de BARNDAKE, Région du Nord
CM-CRC NORD-8540-GO-RFQ / Fourniture du petit matériel médical et du mobilier en bois au Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 9,000.00 0.00 2017-06-20 2017-07-20 2017-09-18 CSI DE Rey-Bouba dans la decentralization process Quotations Envelope Implementation
Commune de Rey Bouba, Région du Nord
CM-CRC NORD-8541-GO-RFQ / Fourniture du petit matériel Component B: Support to the Request for Single Stage - One Pending médical et du mobilier en bois au IDA / 57180 Post Limited 9,000.00 0.00 2017-06-20 2017-07-20 2017-09-18 decentralization process Quotations Envelope Implementation CSI de Mayo Galké dans la Commune de Tcholliré,
CM-CRC NORD-8542-GO-RFQ / Fourniture du petit matériel Component B: Support to the Request for Single Stage - One Pending médical et du mobilier en bois au IDA / 57180 Post Limited 9,000.00 0.00 2017-06-20 2017-07-20 2017-09-18 decentralization process Quotations Envelope Implementation au CSI de DEMBO dans le Commune de Dembo
CM-CRC NORD-8543-GO-RFQ / Fourniture du petit matériel Component B: Support to the Request for Single Stage - One Pending médical et du mobilier en bois au IDA / 57180 Post Limited 9,000.00 0.00 2017-08-12 2017-09-11 2017-11-13 decentralization process Quotations Envelope Implementation au CSI de DOUNDEHI dans la Commune de Touroua
CM-CRC NORD-8544-GO-RFQ / Equipement en mobilier ( tables bancs, bureaux, chaises et Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 9,000.00 0.00 2017-03-20 2017-04-19 2017-06-19 armoires) aux lycée de decentralization process Quotations Envelope Implementation
FIGNOLE, Lycée technique de POLI
005/F/CRCOU/2017 / Fourniture des services de liaison et envoi Component C: Coordination, Request for Single Stage - One Pending du courrier à la Cellule Régionale IDA / 57180 management, monitoring and Post Limited 4,080.00 0.00 2017-03-30 2017-05-25 2017-12-31 Quotations Envelope Implementation de Coordination Ouest du PNDP, evaluation and communication dans la Région de l'Ouest
006/F/CRCOU/2017 / Fourniture des services de maintenance du Component C: Coordination, réseau et matériels informatiques Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 4,293.00 0.00 2017-04-11 2017-06-06 2017-12-28 à la Cellule Régionale de Quotations Envelope Implementation evaluation and communication Coordination Ouest du PNDP, dans la Région de l'Ouest
007/F/CRCOU/2017 / Fourniture des services de maintenance du réseau électrique, climatiseurs, Component C: Coordination, équipements sanitaires et groupe Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 6,440.00 0.00 2017-04-11 2017-06-06 2017-12-28 électrogène à la Cellule Quotations Envelope Implementation evaluation and communication Régionale de Coordination Ouest du PNDP, dans la Région de l'Ouest
007/F/SU/CRC/2017 / Fourniture Component C: Coordination, des services de maintenance du Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 620.00 0.00 2017-03-17 2017-04-21 2018-04-21 réseau électrique et de la Quotations Envelope Implementation evaluation and communication plomberie
Page 5 008/F/SU/CRC/2017 / Fourniture Component C: Coordination, des services de maintenance du Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 2,500.00 0.00 2017-03-17 2017-04-21 2018-04-21 groupe électrogène et des Quotations Envelope Implementation evaluation and communication climatiseurs
009/F/SU/CRC/2017 / Fourniture Component C: Coordination, des services de collecte, Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 1,342.00 0.00 2017-03-17 2017-04-21 2018-04-21 transport et distribution des Quotations Envelope Implementation evaluation and communication courriers et colis
CM-CRC LITTORAL-9508-GO- RFQ / Fourniture des services de Component C: Coordination, Request for Single Stage - One Pending collecte, transport et distribution IDA / 57180 management, monitoring and Post Open - National 1,200.00 0.00 2017-03-14 2017-05-09 2018-05-09 Quotations Envelope Implementation des courriers et colis à la CRC, evaluation and communication région du Littoral
010/F/SU/CRC/2017 / Fourniture Component C: Coordination, Request for Single Stage - One Pending des services de gardiennage à la IDA / 57180 management, monitoring and Post Limited 9,600.00 0.00 2017-03-17 2017-04-21 2018-04-21 Quotations Envelope Implementation CRC evaluation and communication
011/F/SU/CRC/2017 / Acquisition et installation de 03 Component C: Coordination, climatiseurs de 1,5CV, 01 Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 5,340.00 0.00 2017-03-17 2017-04-21 2017-05-05 climatiseur de 2,5CV et 06 Quotations Envelope Implementation evaluation and communication barbillards (tableau de liège de 150 x 90 cm)
012/F/SU/CRC/2017 / Component C: Coordination, Request for Single Stage - One Pending Acquisition des fournitures pour IDA / 57180 management, monitoring and Post Limited 5,418.00 0.00 2017-07-13 2017-08-14 2017-08-28 Quotations Envelope Implementation classement et archivage evaluation and communication
001/F/SU/DJOUM / Fourniture Component A: Local Request for Single Stage - One Pending IDA / 57180 Post Limited 8,100.00 0.00 2017-04-21 2017-05-18 2017-06-01 de médicaments au CSI de Mfem development support Quotations Envelope Implementation
002/F/SU/DJOUM/2017 / Component A: Local Request for Single Stage - One Pending Fourniture de tables-bancs à l'EP IDA / 57180 Post Limited 2,016.00 0.00 2017-04-21 2017-05-18 2017-06-17 development support Quotations Envelope Implementation d'Okweng
CM-PNDP-9661-GO-RFB / Acquisition du matériel Component B: Support to the Single Stage - One Pending informatique (ordinateurs et mini- IDA / 57180 Post Request for Bids Open - National 349,600.00 0.00 2017-03-22 2017-03-27 2017-04-26 2017-05-10 2017-05-24 2017-07-08 decentralization process Envelope Implementation réseau) pour SIM-BA dans les 184 communes
CM-PNDP-9664-GO-RFB / Fourniture des groupes électrogènes dans le cadre de la Component B: Support to the Single Stage - One Pending IDA / 57180 Post Request for Bids Open - National 480,000.00 0.00 2017-03-22 2017-03-27 2017-04-26 2017-05-10 2017-06-07 2017-07-22 mise en oeuvre du logiciel decentralization process Envelope Implementation
Sim_ba dans 187 communes ( Relance)
CM-PNDP-9665-GO-RFB / Fourniture des plaques solaires pour Sim_ba dans le cadre de la Component B: Support to the Single Stage - One Pending IDA / 57180 Post Request for Bids Open - National 440,000.00 0.00 2017-03-27 2017-04-01 2017-05-01 2017-05-15 2017-06-12 2017-07-27 mise en oeuvre du logiciel decentralization process Envelope Implementation
Sim_ba dans 40 commune ( deuxième vague)
CM-PNDP-9669-GO-RFQ / Fourniture de bureau (lot 1), Component C: Coordination, Request for Single Stage - One Pending produits d'entretien et matériel et IDA / 57180 management, monitoring and Post Limited 80,000.00 0.00 2017-10-28 2017-12-09 2018-12-04 Quotations Envelope Implementation produits pause-café ( lot 3) à la evaluation and communication CNC du PNDP
CM-PNDP-9671-GO-RFQ / Component C: Coordination, Fourniture des consommables Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 80,000.00 0.00 2017-10-28 2017-12-09 2018-12-04 informatiques à la CNC du PNDP Quotations Envelope Implementation evaluation and communication (LOT4)
CM-PNDP-9799-GO-RFQ / Component C: Coordination, Request for Single Stage - One Pending Acquisition des fournitures pour IDA / 57180 management, monitoring and Post Limited 19,600.00 0.00 2017-12-09 2018-01-13 2019-01-08 Quotations Envelope Implementation les véhicules de la CNC evaluation and communication
CM-PNDP-9806-GO-RFQ / Component C: Coordination, Request for Single Stage - One Pending Fourniture et installation du IDA / 57180 management, monitoring and Post Limited 60,000.00 0.00 2017-04-22 2017-06-03 2017-06-24 Quotations Envelope Implementation mobilier de bureau au PNDP evaluation and communication
CM-PNDP-9813-GO-RFQ / Acquisition des fournitures dans le cadre de l'appui au Ministère Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 4,000.00 0.00 2017-04-22 2017-06-03 2017-06-17 des Affaires Sociales pour la decentralization process Quotations Envelope Implementation
Journée Internationale des Peuples Autochtone (JIPA)
CM-PNDP-9817-GO-DIR / Souscription pour la participation du PNDP à la Journée Africaine Component B: Support to the Pending IDA / 57180 Post Direct Selection Direct 4,000.00 0.00 2017-03-30 2017-04-04 2017-04-25 2017-04-27 de la Décentralisation et du decentralization process Implementation
Développement Local (JADDEL 2017)
CM-PNDP-9820-GO-RFQ / Conception et pose d'affichettes Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 28,000.00 0.00 2017-06-23 2017-08-04 2017-08-25 sur les comportements souhaités decentralization process Quotations Envelope Implementation dans le cadre du PNDP III
CM-PNDP-9822-GO-RFB / Component C: Coordination, Fourniture et installation du Single Stage - One Pending IDA / 57180 management, monitoring and Post Request for Bids Open - National 322,730.00 0.00 2017-07-07 2017-07-12 2017-08-11 2017-08-25 2017-09-08 2017-10-23 matériel informatique et Envelope Implementation evaluation and communication didactique au PNDP
CM-PNDP-9825-GO-RFQ / Component C: Coordination, Fourniture du matériel de Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 9,600.00 0.00 2017-04-22 2017-06-03 2017-06-17 formation (paper board) pour la Quotations Envelope Implementation evaluation and communication CNC et les CRC
CM-PNDP-9828-GO-RFQ / Component C: Coordination, Fourniture de 182 téléphones Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 44,120.08 0.00 2017-04-22 2017-05-27 2017-06-03 portables pour le personnel du Quotations Envelope Implementation evaluation and communication PNDP
CM-PNDP-9833-GO-DIR / Convention de partenariat avec la CRTV poste nationale pour la Component B: Support to the Pending IDA / 57180 Post Direct Selection Direct 2,000.00 0.00 2017-03-14 2017-03-19 2017-04-09 2018-04-04 diffusion des messages dans decentralization process Implementation l'émission radio" Croissance Plus"
CM-PNDP-9838-GO-DIR / Convention de partenariat pour la diffusion de programmes sur les Component B: Support to the Pending IDA / 57180 Post Direct Selection Direct 2,400.00 0.00 2017-05-08 2017-05-13 2017-05-27 2018-05-22 stations réionales Extrême-nord, decentralization process Implementation
Nord, Adamaoua, et est de la CRTV
CM-PNDP-9840-GO-DIR / Convention de partenariat avec les radios communautaires pour Component B: Support to the Pending IDA / 57180 Post Direct Selection Direct 12,000.00 0.00 2017-05-08 2017-05-13 2017-05-27 2018-05-22 la difusion d'émissions sur les decentralization process Implementation thématiques chères au PNDP III dans les quatres régions
CM-PNDP-9843-GO-DIR / Acquisition des ouvrages sur la Component B: Support to the Pending IDA / 57180 Post Direct Selection Direct 10,000.00 0.00 2017-05-08 2017-05-13 2017-05-27 2017-06-03 décentralisation et le decentralization process Implementation développement local
CM-PNDP-2928-GO-RFB / Production des outils de Component C: Coordination, communication du PNDP 3 ( Single Stage - One Pending IDA / 57180 management, monitoring and Post Request for Bids Open - National 245,200.00 0.00 2017-04-03 2017-04-08 2017-04-29 2017-05-29 2017-06-19 2017-07-10 Plaquette, Kakemonos, agenda, Envelope Implementation evaluation and communication présentoires, pagnes, polos, t- shirts, casquette, etc)
CM-PNDP-2931-GO-DIR / Component C: Coordination, Pending Edition du Magazine Trimestriel " IDA / 57180 management, monitoring and Post Direct Selection Direct 50,000.00 0.00 2017-03-17 2017-03-22 2017-04-26 2018-04-21 Implementation LES ECHOS DU PNDP" evaluation and communication
CM-PNDP-2837-GO-RFB / Acquisition du petit équipement (GPS et supports pour le Component B: Support to the Single Stage - One Pending IDA / 57180 Post Request for Bids Open - National 150,000.00 0.00 2017-04-13 2017-04-18 2017-05-09 2017-06-08 2017-06-29 2017-08-13 Système d'Information decentralization process Envelope Implementation
Géographique) pour 75 communes
CM-PNDP-2929-GO-RFQ / Component C: Coordination, Production de la signalétique des Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 16,000.00 0.00 2017-03-31 2017-05-19 2017-07-03 11 sites du PNDP (agence de Quotations Envelope Implementation evaluation and communication communication)
CM-PNDP-11813-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending PNDP de la Région de IDA / 57180 Post Limited 22,222.00 0.00 2017-04-10 2017-06-05 2017-12-02 decentralization process Quotations Envelope Implementation l'Adamaoua dans l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11814-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending PNDP de la Région du Centre IDA / 57180 Post Limited 70,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 decentralization process Quotations Envelope Implementation dans l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11815-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 33,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 PNDP de la Région de l'Est dans decentralization process Quotations Envelope Implementation l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11817-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending PNDP de la Région de l'Extreme IDA / 57180 Post Limited 47,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 decentralization process Quotations Envelope Implementation Nord dans l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11818-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending PNDP de la Région du Littoral IDA / 57180 Post Limited 34,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 decentralization process Quotations Envelope Implementation dans l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11819-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 21,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 PNDP de la Région du Nord dans decentralization process Quotations Envelope Implementation l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11820-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending PNDP de la Région du Nord IDA / 57180 Post Limited 34,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 decentralization process Quotations Envelope Implementation Ouest dans l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11821-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending PNDP de la Région de l'Ouest IDA / 57180 Post Limited 40,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 decentralization process Quotations Envelope Implementation dans l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11824-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 29,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 PNDP de la Région du Sud dans decentralization process Quotations Envelope Implementation l'édition d'un bulletin trimestriel d'informations communal
CM-PNDP-11825-GO-RFQ / Accompagnement des communes d'intervention du Component B: Support to the Request for Single Stage - One Pending PNDP de la Région du Sud IDA / 57180 Post Limited 31,000.00 0.00 2017-04-10 2017-06-05 2017-12-02 decentralization process Quotations Envelope Implementation Ouest dans l'édition d'un bulletin trimestriel d'informations communal
CM-CRC ADAMAOUA-11965- Component C: Coordination, GO-RFQ / Acquisition des Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 19,000.00 0.00 2017-04-28 2017-06-16 2017-12-13 fournitures pour véhicules de la Quotations Envelope Implementation evaluation and communication CRC, Région Adamaoua
CM-CRC ADAMAOUA-11971- GO-RFQ / Acquisition et Component C: Coordination, Request for Single Stage - One Pending installation d'un groupe IDA / 57180 management, monitoring and Post Limited 30,000.00 0.00 2017-04-27 2017-06-22 2017-12-19 Quotations Envelope Implementation électrogène avec abri de la CRC, evaluation and communication Région Adamaoua
CM-CRC ADAMAOUA-11973- GO-RFQ / Achat d'autres Component C: Coordination, Request for Single Stage - One Pending fournitures (acquisition des IDA / 57180 management, monitoring and Post Limited 9,000.00 0.00 2017-04-28 2017-06-23 2017-12-20 Quotations Envelope Implementation consommables informatiques) de evaluation and communication la CRC, Région Adamaoua
CM-CRC ADAMAOUA-11975- GO-RFQ / Fourniture des Component C: Coordination, services de Collecte, transport et Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 2,852.00 0.00 2017-04-13 2017-06-08 2017-12-05 distribution des courriers et colis Quotations Envelope Implementation evaluation and communication de la CRC, Région de l'Adamaoua
CM-CRC ADAMAOUA-11978- GO-RFQ / Fourniture des Component C: Coordination, services de maintenance des Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 5,520.00 0.00 2017-05-05 2017-06-30 2017-12-27 matériels informatiques et Quotations Envelope Implementation evaluation and communication copieurs de la CRC, Région de l'Adamaoua
CM-CRC ADAMAOUA-11980- GO-RFQ / Acquisition d'un stand et production des supports de communication dans le cadre de Component B: Support to the Request for Single Stage - One Pending la participation à des foires et IDA / 57180 Post Limited 7,000.00 0.00 2017-04-28 2017-06-23 2017-12-20 decentralization process Quotations Envelope Implementation expositions sur la décentralisation (nationales et internationales), Région Adamaoua
006/F/SU/CRC/2017 / Fourniture Component C: Coordination, des services de maintenance du Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 2,880.00 0.00 2017-04-24 2017-06-01 2018-06-01 parc informatique, téléphonique Quotations Envelope Implementation evaluation and communication et matériels de reprographie
NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
CM-PNDP-2947-NC-DIR / Component C: Coordination, Insertion (souscription) dans le Pending IDA / 57180 management, monitoring and Post Direct Selection Direct 9,000.00 0.00 2016-11-04 2016-11-09 2016-12-14 2017-06-12 journal de l'édition 2016 des JEC Implementation evaluation and communication (Journées de l'Entrepreneuriat)
CM-PNDP-2838-NC-RFB / Component C: Coordination, Fourniture des services Single Stage - One Pending IDA / 57180 management, monitoring and Post Request for Bids Open - National 218,000.00 0.00 2016-11-09 2016-11-14 2016-12-26 2017-01-25 2017-03-01 2017-08-28 d'assurances automobiles, Envelope Implementation evaluation and communication maladies et responsabilité civile
CM-PNDP-2856-NC-DIR / Insertions et publi-reportages Component C: Coordination, Pending spéciaux dans le Magazine IDA / 57180 management, monitoring and Post Direct Selection Direct 13,000.00 0.00 2017-01-16 2017-01-21 2017-02-25 2017-08-24 Implementation international CAMEROUN ECO, evaluation and communication en 2017 (Convention)
CM-PNDP-2857-NC-DIR / Component C: Coordination, Insertions et publi-reportages Pending IDA / 57180 management, monitoring and Post Direct Selection Direct 6,000.00 0.00 2016-11-09 2016-11-14 2016-12-19 2017-06-17 spéciaux 1, dans le quotidien Implementation evaluation and communication "CAMEROUN TRIBUNE"
CM-PNDP-2858-NC-DIR / Component C: Coordination, Pending Insertions et publi-reportages IDA / 57180 management, monitoring and Post Direct Selection Direct 6,000.00 0.00 2016-12-17 2016-12-22 2017-01-26 2017-07-25 Implementation spéciaux dans d'autres journaux evaluation and communication
CM-PNDP-2860-NC-DIR / Component C: Coordination, Insertions et publi-reportages Pending IDA / 57180 management, monitoring and Post Direct Selection Direct 6,000.00 0.00 2016-12-17 2016-12-22 2017-01-26 2017-07-25 spéciaux dans les autres radios Implementation evaluation and communication et televisions
CM-PNDP-6228-NC-RFQ / Fourniture des services de Component C: Coordination, Request for Single Stage - One Pending maintenance préventive et IDA / 57180 management, monitoring and Post Limited 10,000.00 0.00 2017-02-09 2017-04-06 2017-10-03 Quotations Envelope Implementation curative du parc des machines evaluation and communication de la CNC du PNDP
CM-PNDP-6229-NC-RFQ / Component B: Support to the Fourniture des services de decentralization process Request for Single Stage - One Pending dédouanement et enlèvement IDA / 57180 Component C: Coordination, Post Limited 120,000.00 0.00 2017-04-05 2017-04-26 2017-10-23 Quotations Envelope Implementation des 31 motos et 28 véhicules management, monitoring and acquis par UNOPS evaluation and communication
Page 6 CM-PNDP-2851-NC-DIR / Participation du PNDP au SAGO Component C: Coordination, (Salon de l'Action Pending IDA / 57180 management, monitoring and Prior Direct Selection Direct 6,000.00 0.00 2017-06-08 2017-06-13 2017-07-04 2017-08-03 Gouvernementale) en 2017 Implementation evaluation and communication (Souscription d'une Convention avec "Mon Communicateur")
CM-PNDP-2849-NC-DIR / Participation du PNDP à Component C: Coordination, Pending PROMOTE 2017 (Souscription IDA / 57180 management, monitoring and Post Direct Selection Direct 10,000.00 0.00 2016-10-26 2016-10-31 2016-12-05 2017-06-03 Implementation d'une Convention avec INTER evaluation and communication PROGRESS)
CM-PNDP-2923-NC-DIR / Projection de films éducatifs dans les 10 régions sur la Component B: Support to the Pending décentralisation et le IDA / 57180 Post Direct Selection Direct 60,000.00 0.00 2017-05-07 2017-05-12 2017-06-16 2017-12-13 decentralization process Implementation développement local (Convention avec l'Association Cinéma Numérique Ambulant)
CM-PNDP-2861-NC-DIR / Co- production d'une émission de Component B: Support to the Pending télévision intitulée "Gouvernance IDA / 57180 Post Direct Selection Direct 36,000.00 0.00 2017-06-11 2017-06-16 2017-07-21 2018-01-17 decentralization process Implementation Locale" à diffusée à la CRTV (Convention avec Zenu Network)
CM-PNDP-2862-NC-DIR / Co- production d'une émission de télévision intitulée " Lumière sur Component B: Support to the Pending IDA / 57180 Post Direct Selection Direct 12,000.00 0.00 2017-06-18 2017-06-23 2017-07-28 2018-01-24 la décentralisation"à diffuser sur decentralization process Implementation
CANAL 2 (Convention avec Peace Communication)
CM-PNDP-2850-NC-RFQ / Component C: Coordination, Appui à l'aménagement et Request for Single Stage - One Pending IDA / 57180 management, monitoring and Post Limited 10,000.00 0.00 2016-12-10 2017-02-04 2017-08-03 animation du stand du PNDP à Quotations Envelope Implementation evaluation and communication PROMOTE 2017
CM-PNDP-2855-NC-RFQ / Appui à l'amménagement et Component B: Support to the Request for Single Stage - One Pending IDA / 57180 Post Limited 6,000.00 0.00 2017-05-19 2017-07-14 2018-01-10 annimation du stand du PNDP au decentralization process Quotations Envelope Implementation
SACO en 2017
CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
CM-PNDP-1203-CS-LCS / Audit Component C: Coordination, financier et comptable des IDA / 57180 management, monitoring and Prior Least Cost Selection Open - National 80,000.00 0.00 Canceled 2016-08-22 2016-09-12 2016-10-26 2016-11-23 2016-12-23 2017-01-27 2017-03-03 2017-08-30 exercices fiscaux 2016 et 2017 evaluation and communication du PNDP
CM-PNDP-3202-CS-CQS / Component C: Coordination, Consultant Gestion des doléances à travers Under IDA / 57180 management, monitoring and Post Qualification Open - National 44,000.00 0.00 2016-09-19 2016-10-13 2016-10-10 2016-10-24 2016-11-23 2016-12-23 2017-01-27 2017-07-26 un Centre d'Appel et un Numéro Implementation evaluation and communication Selection vert dans le cadre du PNDP III
CM-PNDP-3201-CS-CQS / Component C: Coordination, Consultant Under Migration de Pro-ADP vers une IDA / 57180 management, monitoring and Post Qualification Open - National 52,000.00 0.00 2016-09-19 2016-10-13 2016-10-10 2016-10-24 2016-11-23 2016-12-23 2017-01-27 2017-07-26 Implementation version Web.2.0 evaluation and communication Selection
CM-PNDP-2939-CS-CQS / Component C: Coordination, Consultant Pending Etude sur le marketing social IDA / 57180 management, monitoring and Post Qualification Open - National 30,000.00 0.00 2017-04-02 2017-04-23 2017-06-06 2017-07-06 2017-08-10 2018-02-06 Implementation dans le cadre du PNDP 3 evaluation and communication Selection
CM-PNDP-2944-CS-CQS / Sélection des experts (1 par région) en langues locales pour Consultant Component B: Support to the Pending la conception ou la traduction IDA / 57180 Post Qualification Open - National 20,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-02-07 decentralization process Implementation d'émissions sur les thématiques Selection chères au PNDP 3 à diffuser sur les radios communautaires
001/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DEVELLOPEMENT
002/C/OAL/PNDP/EST / Consultant ELABORATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 100,000.00 0.00 2017-07-02 2017-07-23 2017-09-05 2017-10-05 2017-11-09 2018-09-05 COMMUNAL DE development support Implementation Selection DEVELOPPEMENT
003/C/OAL/PNDP/EST / Consultant ÉLABORATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 100,000.00 0.00 2017-07-02 2017-07-23 2017-09-05 2017-10-05 2017-11-09 2018-09-05 COMMUNAL DE development support Implementation Selection DEVELOPPEMENT
004/C/OAL/PNDP/EST / Consultant Component A: Local Pending ACTUALISATION PLAN IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 development support Implementation COMMUNAL Selection
005/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DEVELLOPEMENT
006/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DÉVELOPPEMENT
007/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DÉVELOPPEMENT
008/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DÉVELOPPEMENT
009/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-02-07 COMMUNAL DE development support Implementation Selection DÉVELOPPEMENT
010/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-02-07 COMMUNAL DE development support Implementation Selection DÉVELOPPEMENT
011/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DEVELLOPEMENT
012/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DEVELLOPEMENT
013/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-02-07 COMMUNAL DE development support Implementation Selection DEVELLOPEMENT
014/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DÉVELOPPEMENT
CM-CRC EXTREME NORD-8076- CS-CQS / Sélection d'un Consultant Component B: Support to the Pending consultant pour l'actualisation du IDA / 57180 Post Qualification Open - National 63,060.00 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 decentralization process Implementation PCD de la commune de Guéré, Selection Région de l'Extrême-Nord
CM-CRC EXTREME NORD-8082- CS-CQS / Sélection d'un Consultant Component B: Support to the Pending consultant pour l'actualisation du IDA / 57180 Post Qualification Open - National 26,970.00 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 decentralization process Implementation PCD de la commune de Kalfou, Selection Région de l'Extrême-Nord
015/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DEVELLOPEMENT
016/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DEVELLOPEMENT
017/C/OAL/PNDP/EST / Consultant ACTUALISATION PLAN Component A: Local Pending IDA / 57180 Post Qualification Open - National 18,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2018-06-07 COMMUNAL DE development support Implementation Selection DÉVELOPPEMENT
CM-CRC EXTREME NORD-8089- CS-CQS / élection d'un Consultant consultant pour l'actualisation du Component B: Support to the Pending IDA / 57180 Post Qualification Open - National 26,460.00 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 PCD de la commune de decentralization process Implementation Selection Datcheka, Région de l'Extrême- Nord
CM-CRC EXTREME NORD-8088- CS-CQS / Sélection d'un Consultant Component B: Support to the Pending consultant pour l'actualisation du IDA / 57180 Post Qualification Open - National 63,060.00 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 decentralization process Implementation PCD de la commune de Mindif, Selection Région de l'Extrême-Nord
CM-CRC EXTREME NORD-8094- CS-CQS / Sélection d'un Consultant consultant pour l'actualisation du Component B: Support to the Pending IDA / 57180 Post Qualification Open - National 53,760.00 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 PCD de la commune de decentralization process Implementation Selection Gazawa., Région de l'Extrême- Nord
CM-CRC EXTREME NORD-8093- CS-CQS / Sélection d'un Consultant consultant pour l'actualisation du Component B: Support to the Pending IDA / 57180 Post Qualification Open - National 15,570.00 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 PCD de la commune de decentralization process Implementation Selection Guidiguis, Région de l'Extrême- Nord
CM-CRC EXTREME NORD-8097- CS-CQS / Sélection d'un Consultant Component B: Support to the Pending consultant pour l'actualisation du IDA / 57180 Post Qualification Open - National 57,600.00 0.00 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 decentralization process Implementation PCD de la commune de Dargala, Selection Région de l'Extrême-Nord
CM-CRC NORD-9365-CS-INDV / Consultant Elaboration du PCD de la Component B: Support to the Pending IDA / 57180 Post Qualification Open - National 101,000.00 0.00 2017-04-20 2017-05-11 2017-06-24 2017-07-24 2017-08-28 2018-06-24 Commune d'arrondissement de decentralization process Implementation Selection GAROUA Ier, Région du Nord
001/C/OAL/KOMBO ITINDI/SW/2017 / Sélection d'un Consultant Component A: Local Pending consultant pour l'actualisation du IDA / 57180 Post Qualification Open - National 32,580.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation PCD de la commune de Kombo Selection Itindi, Région du Sud-Ouest
001/C/OAL/IDABATO/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'actualisation du PCD de la IDA / 57180 Post Qualification Open - National 24,480.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Idabato, Région du Selection Sud-Ouest
001/C/OAL/KOMBO ABEDIMO/SW/2017 / Sélection Consultant d'un consultant pour Component A: Local Pending IDA / 57180 Post Qualification Open - National 21,510.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 l'actualisation du PCD de la development support Implementation Selection commune de Kombo Abedimo, Région du Sud-Ouest
001/C/OAL/MUYUKA/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'actualisation du PCD de la IDA / 57180 Post Qualification Open - National 23,490.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Muyuka, Région du Selection Sud-Ouest
001/C/OAL/IDENAU/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'actualisation du PCD de la IDA / 57180 Post Qualification Open - National 12,600.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Idenau, Région du Selection Sud-Ouest
001/C/OAL/KONYE/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'actualisation du PCD de la IDA / 57180 Post Qualification Open - National 34,620.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Konye, Région du Selection Sud-Ouest
001/C/OAL/MBONGE/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'actualisation du PCD de la IDA / 57180 Post Qualification Open - National 55,560.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Mbonge, Région du Selection Sud-Ouest
001/C/OAL/NGUTI/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'actualisation du PCD de la IDA / 57180 Post Qualification Open - National 42,960.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Nguti, Région du Selection Sud-Ouest
001/C/OAL/TINTO/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'actualisation du PCD de la IDA / 57180 Post Qualification Open - National 43,260.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Tinto, Région du Selection Sud-Ouest
001/C/OAL/TIKO/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'actualisation du PCD de la IDA / 57180 Post Qualification Open - National 22,500.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Tiko, Région du Selection Sud-Ouest
001/C/OAL/LIMBE I/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'élaboration du PCD de la IDA / 57180 Post Qualification Open - National 100,000.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Limbe I, Région du Selection Sud-Ouest
001/C/OAL/LIMBE II/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'élaboration du PCD de la IDA / 57180 Post Qualification Open - National 100,000.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Limbe II, Région Selection du Sud-Ouest
001/C/OAL/LIMBE III/SW/2017 / Sélection d'un consultant pour Consultant Component A: Local Pending l'élaboration du PCD de la IDA / 57180 Post Qualification Open - National 100,000.00 0.00 2017-03-08 2017-03-29 2017-05-12 2017-06-11 2017-07-16 2018-01-12 development support Implementation commune de Limbe III, Région Selection du Sud-Ouest
001/C/OAL/SU/EBOLOWA Consultant 1/2017 / Sélection d'un Component A: Local Pending IDA / 57180 Post Qualification Open - National 70,000.00 0.00 2017-05-04 2017-05-04 2017-06-15 2017-07-07 2017-07-21 2018-05-17 consultant pour l'élaboration du development support Implementation Selection PCD
002/C/OAL/SU/EBOLOWA Consultant Component A: Local Pending II/2017 / Sélection d'un OAL pour IDA / 57180 Post Qualification Open - National 70,000.00 0.00 2017-05-04 2017-05-04 2017-06-15 2017-07-07 2017-07-21 2018-05-17 development support Implementation l'élaboration du PCD Selection
003/C/OAL/SU/KRIBI I/2017 / Consultant Component A: Local Pending Sélection d'un OAL pour IDA / 57180 Post Qualification Open - National 70,000.00 0.00 2017-05-04 2017-05-04 2017-06-15 2017-07-07 2017-07-21 2018-05-17 development support Implementation l'élaboration du PCD Selection
004/C/OAL/SU/KRIBI II/2017 / Consultant Component A: Local Pending Sélection d'un OAL pour IDA / 57180 Post Qualification Open - National 70,000.00 0.00 2017-05-04 2017-05-04 2017-06-15 2017-07-07 2017-07-21 2018-05-17 development support Implementation l'élaboration du PCD Selection
CM-CRC NORD-9713-CS-CQS / Consultant élaboration du PCD de la Component B: Support to the Pending IDA / 57180 Post Qualification Open - National 101,000.00 0.00 2017-04-19 2017-05-10 2017-06-23 2017-07-23 2017-08-27 2018-06-23 Commune d'arrondissement de decentralization process Implementation Selection GAROUA II,
CM-CRC NORD-9714-CS-CQS / Consultant élaboration du PCD de la Component B: Support to the Pending IDA / 57180 Post Qualification Open - National 101,000.00 0.00 2017-04-20 2017-05-11 2017-06-24 2017-07-24 2017-08-28 2018-06-24 Commune d'arrondissement de decentralization process Implementation Selection GAROUA III,
CM-CRC NORD-9715-CS-CQS / Consultant Component B: Support to the Pending Elaboration du PCD de la IDA / 57180 Post Qualification Open - National 80,200.00 0.00 2017-04-20 2017-05-11 2017-06-24 2017-07-24 2017-08-28 2018-06-24 decentralization process Implementation Commune de TOUBORO, Selection
CM-CRC LITTORAL-9917-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 31,050.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Dizangue, Région du Littoral
Page 7 CM-CRC LITTORAL-9918-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 42,360.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Massok, Région du Littoral
CM-CRC LITTORAL-9919-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 26,970.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Mbanga, Région du Littoral
CM-CRC LITTORAL-9920-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 41,760.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Melong, Région du Littoral
CM-CRC LITTORAL-9921-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 12,600.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Mombo, Région du Littoral
CM-CRC LITTORAL-9922-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 31,050.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Mouanko, Région du Littoral
CM-CRC LITTORAL-9923-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 43,260.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Ndobian, Région du Littoral
CM-CRC LITTORAL-9924-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 40,230.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Nkondjock, Région du Littoral
CM-CRC LITTORAL-9925-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 40,230.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Nyanon, Région du Littoral
CM-CRC LITTORAL-9926-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 17,550.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Penja, Région du Littoral
CM-CRC LITTORAL-9927-CS- CQS / Sélection d'un Organisme Consultant d'Appui Local pour l'actualisation Component A: Local Pending IDA / 57180 Post Qualification Open - National 37,170.00 0.00 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-05-24 du Plan Communal de development support Implementation Selection Développement de la Commune de Yingui, Région du Littoral
CM-PNDP-10307-CS-CQS / Consultant Sélection des OAL pour l'appui à Component B: Support to the Pending IDA / 57180 Post Qualification Open - National 7,102.24 0.00 2017-04-11 2017-05-02 2017-06-15 2017-07-06 2017-08-03 2017-10-02 la mise en oeuvre du Scorecard decentralization process Implementation Selection par les OSC
CM-PNDP-10340-CS-INDV / Sélection d'un consultant pour la Consultant Component B: Support to the Pending création et la gestion d'une IDA / 57180 Post Qualification Open - National 37,600.00 0.00 2017-06-26 2017-07-17 2017-08-21 2017-09-04 2017-10-02 2017-11-16 decentralization process Implementation plateforme de présentation des Selection communes
CM-PNDP-3101-CS-QCBS / Component C: Coordination, Audit financier et comptable des Quality And Cost- Pending IDA / 57180 management, monitoring and Prior Open - National 80,000.00 0.00 2017-03-31 2017-04-21 2017-06-04 2017-07-02 2017-08-01 2017-09-05 2017-10-10 2018-10-10 exercices fiscaux 2016 et 2017 Based Selection Implementation evaluation and communication du PNDP
CM-PNDP-2846-CS-QCBS / Recrutement d'un consultant Consultant Component B: Support to the Pending pour l'élaboration des modèles de IDA / 57180 Post Qualification Open - National 100,000.00 0.00 2017-06-13 2017-07-04 2017-08-17 2017-09-16 2017-10-07 2018-04-05 decentralization process Implementation gestion et d'entretien des Selection ouvrages d'infrastructures
CM-PNDP-2847-CS-QCBS / Audit technique externe Component C: Coordination, Quality And Cost- Pending périodique de la cosommation IDA / 57180 management, monitoring and Prior Open - National 300,000.00 0.00 2017-07-03 2017-07-24 2017-09-06 2017-10-04 2017-10-18 2017-11-22 2017-12-27 2018-12-27 Based Selection Implementation des allocations par les evaluation and communication communes
CM-CRC ADAMAOUA-11781- CS-CQS / Suivi - contrôle des travaux de réalisation d'une mini Consultant adduction d'eau avec sept (07) Component A: Local Pending IDA / 57180 Post Qualification Open - National 5,236.00 0.00 2017-04-05 2017-04-16 2017-05-30 2017-06-29 2017-08-03 2018-01-30 bornes fontaines à Bandam, development support Implementation Selection Commune de Bankim, Département du Mayo Banyo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11791- CS-CQS / Suivi-controle des travaux d'Aménagement du marché Kassouan-Dolé (Marché Consultant B) de Banyo par la construction Component A: Local Pending IDA / 57180 Post Qualification Open - National 7,683.00 0.00 2017-04-06 2017-04-16 2017-05-30 2017-06-29 2017-08-03 2018-01-30 de 32 Boutiques Bloc A & B, 01 development support Implementation Selection Hangar de marché (48 comptoirs) Vivres frais et 01 Blocs de 03 Latrines, Commune de Banyo, Département du Mayo Banyo
CM-CRC ADAMAOUA-11872- CS-CQS / Suivi-contrôle des Travaux de construction d'un bâtiment R+1 de 20 boutiques Consultant Component A: Local Pending avec bureau et latrines IDA / 57180 Post Qualification Open - National 6,944.00 0.00 2017-04-06 2017-04-16 2017-05-30 2017-06-29 2017-08-03 2018-01-30 development support Implementation incorporées au Marché de Selection Tignère, Commune de Tignère, Département du Faro et Déo, Région de l'Adamaoua
CM-CRC ADAMAOUA-11876- CS-CQS / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Consultant environnementale du microprojet Component A: Local Pending IDA / 57180 Post Qualification Open - National 200,000.00 0.00 2017-04-06 2017-04-09 2017-05-24 2017-06-23 2017-07-28 2018-01-24 d'Aménagement d'un périmètre development support Implementation Selection irrigué des cultures maraichère + un réservoir d'eau dans la périphérie de la ville de Mayo- darlé
CM-CRC ADAMAOUA-11879- CS-CQS / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Consultant environnementale du microprojet Component A: Local Pending IDA / 57180 Post Qualification Open - National 200,000.00 0.00 2017-04-06 2017-04-07 2017-05-24 2017-06-23 2017-07-28 2018-01-24 de construction d'un ouvrage d'art development support Implementation Selection sur le Mayo-Yiel et réalisation d'une étude complémentaire pour viabiliser le pont sur le Mayo- Boumdo
CM-CRC ADAMAOUA-11882- CS-CQS / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Consultant Component A: Local Pending environnementale du microprojet IDA / 57180 Post Qualification Open - National 200,000.00 0.00 2017-04-06 2017-04-07 2017-05-24 2017-06-23 2017-07-28 2018-01-24 development support Implementation d'extension du réseau électrique Selection de Wourtababal I et II, dans la ville de Tibati, région de l'Adamaoua
CM-CRC ADAMAOUA-11888- CS-CQS / Sélection d'un consultant pour étude de faisabilité technique et environnementale du MP de Consultant Component A: Local Pending Réalisation de 6 barrières de la IDA / 57180 Post Qualification Open - National 200,000.00 0.00 2017-04-06 2017-04-07 2017-05-24 2017-06-23 2017-07-28 2018-01-24 development support Implementation sécurisation en fils barbelés et Selection en bois de 06 espaces agropastoraux dans les localités de Djohong (2 sites), Dawé, Zone, Laïndé-Ma
CM-CRC ADAMAOUA-11940- CS-CQS / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Consultant environnementale du MP de Component A: Local Pending IDA / 57180 Post Qualification Open - National 4,000.00 0.00 2017-04-06 2017-04-07 2017-05-24 2017-06-23 2017-07-28 2018-01-24 Réalisation d'un forage positif development support Implementation Selection équipé d'une pompe immergée alimentée par l'énergie solaire + un château + 04 bornes fontaines au marché Mayo Dar
CM-CRC ADAMAOUA-11942- CS-CQS / Etudes pour la const ruction de: -3 hangars de Marché (Tourni ngal, Bayara et Mayo Badji) Consultant -3 blocs de 2 salles de classe Component A: Local Pending IDA / 57180 Post Qualification Open - National 4,000.00 0.00 2017-04-06 2017-04-07 2017-05-24 2017-06-23 2017-07-28 2018-01-24 development support Implementation s (EP LIPAO, EP DJERKOKA 2 Selection et EP SINDERE), -r éhabilitation 2 blocs de 2 sa lles de classe (EP Tello et EP Ngaoudamdji) Commune de Bélel
CM-CRC ADAMAOUA-11945- CS-CQS / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Consultant environnementale des MP Component A: Local Pending IDA / 57180 Post Qualification Open - National 4,000.00 0.00 2017-04-06 2017-04-07 2017-05-24 2017-06-23 2017-07-28 2018-01-24 d'aménagement d'un complexe development support Implementation Selection sportif de Bélel (Terrain de Foot Ball, Hand Ball, Basket Ball, Volley Ball et une tribune de 2 à 5 000 places)
CM-CRC ADAMAOUA-11947- CS-CQS / Sélection d'un consultant pour l'élaboration de Consultant l'étude de faisabilité technique et Component A: Local Pending IDA / 57180 Post Qualification Open - National 4,000.00 0.00 2017-04-06 2017-04-07 2017-05-24 2017-06-23 2017-07-28 2018-01-24 environnementale du microprojet development support Implementation Selection d'électrification en énergie solaire des villages Djilougou et Didjawa, Commune de Bélel
INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
CM-PNDP-2933-CS-INDV / Etude d'audience des émissions Component C: Coordination, Individual Consultant Pending 'Gouvernance Locale (CRTV)" et IDA / 57180 management, monitoring and Post Limited 3,600.00 0.00 2017-01-02 2017-01-07 2017-01-28 2017-03-04 2017-08-31 Selection Implementation " Lumière sur la décentralisation evaluation and communication (CANAL 2)
CM-PNDP-2942-CS-INDV / Component C: Coordination, Conception des articles du Individual Consultant Pending IDA / 57180 management, monitoring and Post Limited 2,000.00 0.00 2016-12-11 2016-12-16 2017-01-06 2017-02-10 2017-08-09 Magazine trimestriel " LES Selection Implementation evaluation and communication ECHOS DU PNDP", en anglais
001/C/EF/CE/NDIKINIMEKI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité de construction d'un (01) hangar de marché avec bloc Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-03-07 2017-04-25 2017-05-16 2017-06-20 2017-08-19 de trois latrines à Etoundou 1 et development support Selection Implementation d'un (01) magasin de stockage avec bloc de deux latrines à Nebolen, Commune de Ndikinimeki
002/C/EF/CE/NDIKINIMEKI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du microprojet IDA / 57180 Post Open 1,000.00 0.00 2017-03-07 2017-04-25 2017-05-16 2017-06-20 2017-08-19 development support Selection Implementation de construction d'un 01 forage équipé d'une PMH au hangar de marché d'Etoundou 1 dans la commune de Ndikinimeki
001/C/EF/C/BAHAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,400.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 Construction d'un bloc de trois development support Selection Implementation
(03) salles de classe et d'un bloc administratif au Lycée Bilingue de Chengne dans la Commune de Baham, Région de l
018/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALE DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE MOLOUNDOU
019/C/EF/PNDP/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE DIANG
1/C/SC/CE/ENDOM/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction deux (02) hangars de 30 comptoirs avec bloc Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,709.00 0.00 2017-04-23 2017-06-03 2017-06-10 2017-07-02 2017-10-30 latrines deux (02) compartiments development support Selection Implementation dans 02 sites des marchés de Edjom et de Mengwa dans la Commune d'Endom, Région du Centre
002/C/EF/C/BAHAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 2,400.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction d'un bloc maternel à l'EPM de Demko dans la localité de Cheffou dans la Commune de Baham, Région de l'Ouest
2/C/SC/CE/ENDOM/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de deux (02) puits Component A: Local Individual Consultant Pending productifs équipés de Pompe à IDA / 57180 Post Open 960.00 0.00 2017-04-23 2017-05-31 2017-06-07 2017-06-29 2017-10-27 development support Selection Implementation Motricité Humaine dans deux (02) localités (Edjom, Mengwa) dans la Commune d'Endom, Région du Centre.
3/C/SC/CE/AKOEMAN/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de 04 puits Component A: Local Individual Consultant Pending équipés de Pompes à Motricité IDA / 57180 Post Open 1,056.00 0.00 2017-04-23 2017-06-14 2017-06-21 2017-07-13 2017-11-10 development support Selection Implementation Humaine dans quatre localités (Ngamba, Akoéman ville, Melen et Akoa Zolé) dans la Commune d'Akoéman, Région du Centre
003/C/EF/CE/BIYOUHA/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité de réhabilitation de la route bang sombi-Song Bayang- Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,400.00 0.00 2017-03-07 2017-04-25 2017-05-16 2017-06-20 2017-08-04 Song Nkoumondo (7,00 km) et development support Selection Implementation réfection de 02 ponts définitifs sur les rivières NGO NUMBA et KELLE, dans la Commune de BIYOUHA
003/C/EF/C/MALANTOUEN/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,400.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 environnemtale pour la development support Selection Implementation
Construction d'un dalot à Mandah dans la Commune de Malantouen, Région de l'Ouest
Page 8 CM-CRC EXTREME NORD-8103- CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques Component A: Local Individual Consultant Pending et environnementales de IDA / 57180 Post Limited 3,000.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-06-20 development support Selection Implementation Construction d'un bloc saitaire et d'un bloc de latrines au CSI de Djiddeo garre, commune de Maroua III
4/C/SC/CE/AKOEMAN/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un hangar de 32 Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,216.00 0.00 2017-04-23 2017-05-31 2017-06-07 2017-06-29 2017-10-27 comptoirs et 01 bloc de 04 development support Selection Implementation latrines a Akoeman ville, dans la Commune d'Akoéman, Région du Centre
5/C/SC/CE/MBANDJOCK/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un abattoir avec Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,240.00 0.00 2017-04-23 2017-06-03 2017-06-10 2017-07-02 2017-10-30 latrines incorporées, au centre development support Selection Implementation ville de Mbandjock dans la Commune de Mbandjock, Région du Centre
004/C/EF/CE/BIYOUHA/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales des IDA / 57180 Post Open 2,400.00 0.00 2017-03-07 2017-04-25 2017-05-16 2017-06-20 2017-08-04 development support Selection Implementation microprojets d'Electrification des axes Song Bayang-Song dibong, Tum-Ngog-Sindjap sur 06 Km, Commune de Biyouha
CM-CRC EXTREME NORD-8107- CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et environnementales de Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 2,600.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-06-20 Construction de 2 forages development support Selection Implementation
équipés de PMH, un à Dolddosewo et un Ngouroré et la construction d'un bief à Kossewa, commune Maroua II
6/C/SC/CE/MBANDJOCK/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Mini AEP par raccordement au reseau CDE et construction d'un Component A: Local Individual Consultant Pending IDA / 57180 Post Open 297.00 0.00 2017-03-24 2017-04-22 2017-05-07 2017-06-01 2017-09-29 château d'eau avec un development support Selection Implementation cubitenaire de 4000 litres au centre ville de Mbandjock dans la Commune de Mbandjock, Région du Centre
CM-CRC EXTREME NORD-8110- CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques Component A: Local Individual Consultant Pending et environnementales de IDA / 57180 Post Limited 3,000.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-06-20 development support Selection Implementation Construction d'un bloc sanitaire et d'un bloc de latrines au centre de santé de Rhumzou, dans la commune de Mogodé
004/C/EF/C/MALANTOUEN/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour l'Extension IDA / 57180 Post Open 2,000.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation du réseau électrique dans les localités de Njinga, Matagnum dans la Commune de Malantouen, Région de l'Ouest.
005/C/EF/CE/EBEBDA/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,200.00 0.00 2017-03-07 2017-04-25 2017-05-16 2017-06-20 2017-08-04 environnementales des development support Selection Implementation microprojets de Réhabilitation de la route rurale Ebebda 1 - Tsang, dans la commune d'Ebebda
CM-CRC EXTREME NORD-8112- CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et environnementales des MP de Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 2,400.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-06-20 Construction d'un bloc de deux development support Selection Implementation salles de classe équipées d'un bloc latrines a trois compartiements à l'EP de Sedek Ourogabdo et au CES de BOGO
005/C/EF/C/MALANTOUEN/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 2,400.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction d'un bloc maternel à EM de Malentouen Gr1 dans la Commune de Malantouen, Région de l'Ouest
7/C/SC/CE/EBEBDA/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de 02 hangars de 32 comptoirs avec 02 blocs Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,592.00 0.00 2017-04-23 2017-06-03 2017-06-10 2017-07-02 2017-10-30 latrines à 03 compartiments au development support Selection Implementation marché de Nkog Edzen et au marché de Elig-Edouma dans la Commune d'Ebebda, Région du Centre
CM-CRC EXTREME NORD-8114- CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité MP de Construction d 6 forage équipé Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 5,600.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-06-20 de pompe à motricité humaine et development support Selection Implementation e deux (02) forages équipé de pompe à motricité humaine et rehabilitation de deux forages exista commune de BOGO
006/C/EF/C/BAMENDJOU/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour IDA / 57180 Post Open 2,400.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation l'Electrification du village Bameya II et I en basse tension dans la Commune de Bamendjou, Région de l'Ouest
8/C/SC/CE/EBEBDA/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un (01) forage Component A: Local Individual Consultant Pending équipé de Pompe à Motricité IDA / 57180 Post Open 680.00 0.00 2017-04-23 2017-06-13 2017-06-20 2017-07-12 2017-11-09 development support Selection Implementation Humaine sur le site du marché de Elig-Edouma, dans la Commune d'Ebebda, Région du Centre
CM-CRC EXTREME NORD-8118- CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction et équipement d'01 bloc de 02 Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 6,186.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 salles de classe et d'un bloc de development support Selection Implementation latrines à trois compartiments à l'EP Dogba, Gayack dans Construction d1 hangar et d'un bloc de latrines A PAPATA
9/C/SC/CE/NKOTENG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un abattoir avec Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 1,281.00 0.00 2017-03-01 2017-03-06 2017-03-27 2017-05-01 2017-08-29 un bloc latrine à trois (03) development support Selection Implementation compartiments à l'abattoir de Nkoteng dans la Commune de Nkoteng, Région du Centre
006/C/EF/CE/EBEBDA/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du microprojet IDA / 57180 Post Open 1,000.00 0.00 2017-03-07 2017-04-25 2017-05-16 2017-06-20 2017-08-19 development support Selection Implementation de construction d'un (01) forage équipé de PMH au CETIC de Ngog Saa, dans la commune d'Ebebda
007/C/EF/C/BAMENDJOU/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour Construction IDA / 57180 Post Open 1,700.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation d'un hangar de 30 comptoirs + bloc latrines à 03 compartiments à Batchoum II dans la Commune de Bamendjou, Région de l'Ouest
CM-CRC EXTREME NORD-8122- CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un magasin de stockage à Kéné- Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 3,304.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 Kéné, Construction d'un bloc de development support Selection Implementation
02 salles de classe équipées à l'EP de Djafgué, et Construction d'un bloc de latrines à l'EP de Djafgué cne
008/C/EF/C/GALIM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 4,400.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction d'un hôtel communal R+1 à Galim dans la Commune de Galim, Région de l'Ouest
CM-CRC EXTREME NORD-8126- CS-INDV / sélection d'un consultant pour le sui/contrôle des travaux de réalisation de 6 Component A: Local Individual Consultant Pending forages équipés de PMH à IDA / 57180 Post Limited 3,840.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 development support Selection Implementation Tchékéhi, Mbokouré, Magaldao Toupéo, Soukkoungo Galdima, Bourango et Bandalaré dans la commune de Pétté
007/C/EF/CE/EBEBDA/2017 / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité de construction d'un Component A: Local Individual Consultant Pending bloc de deux salles de classes IDA / 57180 Post Open 2,400.00 0.00 2017-03-07 2017-04-25 2017-05-16 2017-06-20 2017-08-19 development support Selection Implementation équipés, bloc administratif, atelier de maçonnerie, salle informatique et bloc de 03 latrines au CETIC de Ngog Saa
CM-CRC EXTREME NORD-8130- CS-INDV / sélection d'un consultant pour le suivi/controle des travaux de Construction d'un Component A: Local Individual Consultant Pending forage pastoral à énergie solaire IDA / 57180 Post Limited 3,200.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 development support Selection Implementation Balaza Lawane (Tchalloudi mango) 1 forage pastoral à énergie solaire à Kongola Saïd, commune de Maroua 3
008/C/EF/CE/EBEBDA/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,740.00 0.00 2017-03-07 2017-04-25 2017-05-16 2017-06-20 2017-08-19 environnementale du microprojet development support Selection Implementation d'Extension du réseau électrique Lendong-Ebebda 1 (2500 m), dans la commune d'Ebebda
CM-CRC EXTREME NORD-8154- CS-INDV / sélection d'un consultant pour le suivi/controle des travaux de Construction d'un bloc de 02 salles de classe Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 5,544.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 équipées et d'un bloc de latrines development support Selection Implementation
à trois compartiments à l'EP de Mayel Béi, à l'EP de Bao Hosséré II et à l'EP de Palaoudi, commune Maroua 1
CM-CRC EXTREME NORD-8157- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de construction d'un Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 2,292.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 bloc maternel à l'école Maternelle development support Selection Implementation de Zokok-Laddo et branchement au réseau d'alimentation en eau potable, commune de Maroua 1
CM-CRC EXTREME NORD-8159- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de Construction de Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 1,840.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 trois forages équipés de pompe à development support Selection Implementation motricité humaine à Ouro Dow, Goni Bello et Yoldéo Guiziga, Commune Maroua 1
CM-CRC EXTREME NORD-8161- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de Construction d'un Component A: Local Individual Consultant Pending bloc de 02 salles de classe IDA / 57180 Post Limited 3,690.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 development support Selection Implementation équipées et d'un bloc de latrines à trois compartiments à l'EP Masfaï et au CES de Boula, commune de Mokolo
CM-CRC EXTREME NORD-8163- CS-INDV / sélection d'un consultant pour le suivi/contrôle Component A: Local Individual Consultant Pending des travaux de Construction de IDA / 57180 Post Limited 1,350.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 development support Selection Implementation 2 forages équipés de PMH un à Ouro Kessoum et à Mounam, commune de Mokolo
CM-CRC EXTREME NORD-8165- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de construction d'un Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 3,510.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 ouvrage de franchissement et development support Selection Implementation d'assainissement sur le mayo- kwayaga, dans la commune de Mogodé
CM-CRC EXTREME NORD-8166- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de Construction d'un Component A: Local Individual Consultant Pending bloc de 02 salles de classe IDA / 57180 Post Limited 3,618.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 development support Selection Implementation équipées et d'un bloc de latrines à trois compartiments à l'EP de Saoudjo et au CES de Madaka, commune de Bogo
CM-CRC EXTREME NORD-8246- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de Construction d'un forage équipé de PMH à Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 4,913.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 Dambaye et à Bagalaf development support Selection Implementation etAménagement d'un bas-fond avec un forage à énergie solaire à Ouro Mésséré pour les cultures maraichères, commune de Bogo
CM-CRC EXTREME NORD-8247- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux deconstruction d'un bloc de deux (02) salles de Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 7,152.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-09-03 classe equipees et un (01) bloc development support Selection Implementation latrine a trois (03) compartiments a l'EP de honkol, a l'EP de darsala, a l'EP de dabanga et l'equipement en me
CM-CRC EXTREME NORD-8248- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux deconstruction d'un forage équipé d'une pompe à Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 3,280.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-09-03 motricité humaine à l' EP de development support Selection Implementation
Darsala, l' EP de Dabanga, et un forage pastoral solaire au village Sahaba 1, l'EP groupe de Logone birni et à EP Ho
Page 9 CM-CRC EXTREME NORD-8249- CS-INDV / sélection d'un consultant pour le suivi/contrôle Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 4,584.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-09-03 des travaux de réalisation d'une development support Selection Implementation mare artificielle à Mogon dans la commune de Moutourwa
CM-CRC EXTREME NORD-8250- CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de construction d'un Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 4,614.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 bloc de deux salles de classe et development support Selection Implementation de deux blocs de latrines à l'EP de Afadé et à l'EP de NGré dans la commune de Makary
CM-CRC EXTREME NORD-8251- CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de 6 Component A: Local Individual Consultant Pending forages équipés de PMH à IDA / 57180 Post Limited 3,840.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-08-04 development support Selection Implementation Tchékéhi, Mbokouré, Magaldao Toupéo, Soukkoungo Galdima, Bourango et Bandalaré dans la commune de Pétté
CM-CRC EXTREME NORD-8252- CS-INDV / Sélection de 3 consultants pour l'appui du CCI Component A: Local Individual Consultant Pending dans la passation des marchés, IDA / 57180 Post Limited 27,632.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2018-05-06 development support Selection Implementation le suivi et l'exécution des projets à la CRC, Région de l'Extrême- Nord
009/C/EF/C/GALIM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 1,700.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction d'un hangar de 30 comptoirs au marché de Galim dans la Commune de Galim, Région de l'Ouest.
010/C/EF/C/BATCHAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour IDA / 57180 Post Open 2,600.00 0.00 2017-03-01 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation l'Electrification du village Bametim du groupement Batcham dans la Commune de Batcham, Région de l'Ouest.
011/C/EF/C/BATCHAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour l'Extension IDA / 57180 Post Open 2,400.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation et le Branchement électrique du CES de King Place de Batcham dans la Commune de Batcham, Région de l'Ouest.
012/C/EF/C/BANA/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 2,800.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction d'un atelier de menuiserie au Lycée Technique de Bana dans la Commune de Bana, Région de l'Ouest
013/C/EF/C/BANA/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 2,800.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction d'un atelier de mécanique automobile au Lycée de Bana dans la Commune de Bana, Région de l'Ouest.
014/C/EF/C/FOUMBAN/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,600.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 rehabilitation du pont sur la development support Selection Implementation manou desservant le bassin agricole de koupa ngagnou avec aménagement des voies d'accès dans la Commune de Foumban
015/C/EF/C/BAKOU/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,700.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 Construction d'un pont sur la development support Selection Implementation rivière Yodjeu dans le groupement Bankambé dans la Commune de Bakou, Région de l'Ouest
016/C/EF/C/BATIE/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour Etude de IDA / 57180 Post Open 4,000.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation faisabilité pour la construction d'une salle multifonctionnelle à Batié dans la Commune de Batié, Région de l'Ouest.
017/C/EF/C/BATIE/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour Etude de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,700.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 faisabilité pour la construction development support Selection Implementation d'un pont sur la rivière Nkuh reliant Bafamgoum I et Balagou II dans la Commune de Batié, Région de l'Ouest.
018/C/EF/C/BATIE/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour Etude de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,000.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 faisabilité pour la construction de development support Selection Implementation deux dalots sur les deux derniers cours d'eau à Nkomlom reliant Djeukouo à Bametchetcha dans la localité
019/C/EF/C/BANDJOUN/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending Construction d'un pont en IDA / 57180 Post Open 3,900.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation matériaux définitifs reliant DJA- TSEGHEM sur le cours d'eau GHECHIO dans la Commune de Pété Bandjoun, Région de l'Ouest.
020/C/EF/C/BAYANGAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,400.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 Construction et équipement d'un development support Selection Implementation bloc maternel à l'école Maternelle Publique de Famla - Batoufam dans la Commune de Bayangam, Région de l'Ouest
021/C/EF/C/BAYANGAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 1,200.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction des toilettes VIP à l'EP de Kagne - Batoufam dans la Commune de Bayangam, Région de l'Ouest.
022/C/EF/C/BAYANGAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,900.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 Réhabilitation de la route famla - development support Selection Implementation
Marché de Kaptche et famla - Wambo Piedjou dans la Commune de Bayangam, Région de l'Ouest.
023/C/EF/C/MAGBA/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour les Travaux IDA / 57180 Post Open 3,900.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation d'ouverture de la route mbakop - matetchit - koula dans la Commune de Magba, Région de l'Ouest.
024/C/EF/C/BATCHAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,900.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 l'electrification MT/BT triphasee development support Selection Implementation au lycee de nzindong et au quartier tsa'a dans le groupement bangang dans la Commune de Batcham, Région de l'Ouest.
025/C/EF/C/KOUTABA/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 2,400.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction et équipement d'un bâtiment abritant le CSI de Ngoundoup dans la Commune de Koutaba, Région de l'Ouest
026/C/EF/C/DSCHANG/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour IDA / 57180 Post Open 2,400.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation l'Electrification rural dans le village NDENKOP dans la Commune de Dschang, Région de l'Ouest.
027/C/EF/C/DSCHANG/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,600.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 Construction d'un forage avec un development support Selection Implementation système de réserve au CSI de Fotsem-Lessing dans la Commune de Dschang, Région de l'Ouest.
028/C/EF/C/DSCHANG/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 2,400.00 0.00 2017-03-04 2017-04-12 2017-05-03 2017-06-07 2017-08-06 development support Selection Implementation Construction d'un hangar au marché de FOTETSA dans la Commune de Dschang, Région de l'Ouest.
029/C/EF/C/SANTCHOU/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,600.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 environnemtale pour la development support Selection Implementation
Construction d'une plateforme multisports dans la Commune de Santchou, Région de l'Ouest.
030/C/EF/C/SANTCHOU/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour l'Ouverture IDA / 57180 Post Open 4,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 development support Selection Implementation de la piste agricole Bamia- Njinjang (08Km et 05 ouvrages d'art) dans la Commune de Santchou, Région de l'Ouest.
031/C/EF/C/FOUMBOT/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 l'Aménagement du stade development support Selection Implementation municipal de Foumbot (Clôture, tribune, terrains de volleyball, handball et Basketball, toilettes et salle d'équipement) dans l
032/C/EF/C/FOUMBOT/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 Construction d'un bloc de deux development support Selection Implementation salles de classe équipé de tables bancs à l'EP de NKOUONDJA dans la Commune de Foumbot, Région de l'Ouest.
033/C/EF/C/FOUMBOT/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 Construction d'un bloc de deux development support Selection Implementation salles de classe équipé de tables bancs à l'EP de FOSSET dans la Commune de Foumbot, Région de l'Ouest.
034/C/EF/C/BAFANG/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour IDA / 57180 Post Open 3,600.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 development support Selection Implementation l'Aménagement de la route Carrefour Baboutcheu-Axe Lourd dans la Commune de Bafang, Région de l'Ouest.
035/C/EF/C/BAFANG/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 1,800.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 development support Selection Implementation Construction d'un hangar au marché de Bankondji dans la Commune de Bafang, Région de l'Ouest.
036/C/EF/C/NJIMOM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 1,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 development support Selection Implementation Construction d'un hangar de 30 places au marché de Machoutvi- manki 2 dans la Commune de Njimom, Région de l'Ouest
037/C/EF/C/NJIMOM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 1,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 development support Selection Implementation Construction d'un hangar de 30 places au marché de Folap dans la Commune de Njimom, Région de l'Ouest.
038/C/EF/C/NJIMOM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 1,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 development support Selection Implementation Construction d'un hangar de 30 places au marché Makouetvu dans la Commune de Njimom, Région de l'Ouest.
039/C/EF/C/NJIMOM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 1,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 development support Selection Implementation Construction d'un hangar de 30 places au marché Makounvi dans la Commune de Njimom, Région de l'Ouest.
Page 10 040/C/EF/C/MASSANGAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,700.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 Construction d'un pont sur le development support Selection Implementation
NKOUH reliant le quartier NJIDEN MATEMBAIN dans la Commune de Massangam, Région de l'Ouest.
041/C/EF/C/MASSANGAM/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et Component A: Local Individual Consultant Pending environnemtale pour la IDA / 57180 Post Open 2,400.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 development support Selection Implementation construction de l'école maternelle à Massangam ville dans la Commune de Massangam, Région de l'Ouest.
042/C/EF/C/SANTCHOU/2017 / Sélection d'un consultant pour l'élaboration d'une etude de faisabilité technique et environnemtale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,600.00 0.00 2017-06-30 2017-08-11 2017-09-01 2017-10-06 2017-12-05 construction d'un hangar de 48 development support Selection Implementation comptoir, et d'un bloc latrine a quatre (04) compartiments et d'un point d'eau au marche central de santchou
CM-CRC LITTORAL-9515-CS- INDV / Elaboration des Etudes de faisabilité techniques et environnementales des travaux de construction d'un bloc de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,360.00 0.00 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2017-09-08 deux salles de classes avec development support Selection Implementation bureau du Directeur à l'école publique bilingue de Bare-centre et d'un bloc maternel à l'ecole publique d'Ebouh-Bare
CM-CRC LITTORAL-9516-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction de deux ouvrages de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,360.00 0.00 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2017-09-08 franchissements dans la localité development support Selection Implementation de Melong 2, un reliant le quartier Kouam et le carrefour chutes d'Ekom-Nkam et l'autre reliant Sambia aux plantation
CM-CRC NORD-9716-CS-INDV / Etude de faisabilité technique et socio-environnementale pour la Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 800.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 réhabilitation de la maison des decentralization process Selection Implementation jeunes de Gaschiga dans la commune de gaschiga
CM-CRC NORD-9717-CS-INDV / Etude de faisabilité technique et socio-environnementale pour la Component B: Support to the Individual Consultant Pending réhabilitation de la piste rurale IDA / 57180 Post Limited 1,600.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation NGOUTCHOUMI-TONTOGO (15 km) dans la commune de gaschiga,
CM-CRC NORD-9718-CS-INDV / Etude de faisabilité technique et socio-environnementale pour Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 3,600.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 laréhabilitation de la piste rurale decentralization process Selection Implementation
Bamanga Kolléré (30 km) dans la commune de gaschiga,
CM-CRC NORD-9719-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending environnementale pour la IDA / 57180 Post Limited 1,600.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation réhabilitation du Pont de Pomla Manga dans la commune de gaschiga,
CM-CRC NORD-9720-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending environnementale pour la IDA / 57180 Post Limited 3,000.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation réhabilitation de la mare artificielle de NGALABA dans la Commune de Gaschiga
CM-CRC NORD-9721-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending environnementale pour la IDA / 57180 Post Limited 1,900.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation réhabilitation du pont de OURO- IYA dans la Commune de Gashiga,
CM-CRC NORD-9722-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending environnementale pour la IDA / 57180 Post Limited 3,000.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation Construction d'un bloc de maternité au CMA de BEKA dans la Commune de Béka,
CM-CRC NORD-9723-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending environnementale pour la IDA / 57180 Post Limited 800.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation Construction d'une clôture à l'Ecole primaire de BEKA dans la Commune de BEKA
CM-CRC NORD-9724-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 5,000.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 environnementale pour la decentralization process Selection Implementation
Construction d'un campement Municipal à BEKA
CM-CRC NORD-9725-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 3,600.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 environnementale pour la decentralization process Selection Implementation
Construction et aménagement d'un stade à BEKA
CM-CRC NORD-9726-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 1,400.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 environnementale pour la decentralization process Selection Implementation
Construction d'un bloc maternel à l'Ecole Maternel Bilingue de POLI
CM-CRC NORD-9727-CS-INDV / réalisation de l'étude de faisabilité technique et socio- environnementale pour la Construction d'un bloc de deux Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 3,600.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 salles de classe équipé et d'un decentralization process Selection Implementation bloc de latrine à l'Ecole Publique de MARKA, CES de WATE, CES de POLI RURAL dans la commune de POLI
CM-CRC NORD-9729-CS-INDV / réalisation de l'étude de faisabilité technique et socio- Component B: Support to the Individual Consultant Pending environnementale pour la IDA / 57180 Post Limited 4,000.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation Construction d'un dalot quintuples sur le Mayo Zati dans la commune de POLI
CM-CRC NORD-9730-CS-INDV / réalisation de l'étude de faisabilité technique et socio- environnementale pour la Construction d'un bloc de trois Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 2,400.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 salles de classe équipé et d'un decentralization process Selection Implementation bloc de latrine à trois compartiments au lycée bilingue de Ngong, au lycée de Tchéboua, et au CES de langui
CM-CRC NORD-9731-CS-INDV / réalisation de l'étude de faisabilité technique et socio- environnementale pour la Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 3,000.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 Construction d'un centre de decentralization process Selection Implementation
Santé intégré et d'un bloc de latrine à ADAMAOUA et à ZERA dans la commune de NGONG
CM-CRC NORD-9732-CS-INDV / réalisation de l'étude de faisabilité technique et socio- environnementale pour la construction des hangars de 28 Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 2,400.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 places et d'un bloc de latrines à decentralization process Selection Implementation trois compartiments dans les marchés des localités de: Tcheboa, langui, laindé massa, et ZERA
CM-CRC NORD-9733-CS-INDV / réalisation de l'étude de faisabilité technique et socio- environnementale pour la construction des magasins de Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 3,600.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 stockage des produits agricoles decentralization process Selection Implementation dans les localités de DOUKA longo, Mafa tchéboa, laindé karewa dans la commune de NGONG,
CM-CRC NORD-9734-CS-INDV / réalisation de l'étude de faisabilité technique et socio- environnementale pour la Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 2,400.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 construction des forages decentralization process Selection Implementation pastoraux dans les localités de HURUM SABONGARI KALFAI 1 BAGADJI ET KALGUE
CM-CRC NORD-9735-CS-INDV / Etude de faisabilité pour Component B: Support to the Individual Consultant Pending l'électrification du quartier Mboum IDA / 57180 Post Limited 800.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation aviation dans la Commune de Garoua II
CM-CRC NORD-9736-CS-INDV / étude de faisabilité pour Component B: Support to the Individual Consultant Pending l'électrification du quartier ouro IDA / 57180 Post Limited 800.00 0.00 2017-05-05 2017-05-10 2017-05-31 2017-07-05 2017-09-04 decentralization process Selection Implementation Alahdji dans la Commune de Garoua II
CM-CRC NORD-9737-CS-INDV / contrôle des travaux de la Component B: Support to the Individual Consultant Pending construction d'un stade mltisport IDA / 57180 Post Limited 2,000.00 0.00 2017-03-13 2017-03-18 2017-04-08 2017-05-13 2017-09-10 decentralization process Selection Implementation à Rey Bouba dans la Commune de Rey Bouba,
CM-CRC NORD-9738-CS-INDV / contrôle des travaux de la construction d'un bâtiment à Usage du CSI, et d'un bloc de latrine à 6 compartiments à Rey Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 3,000.00 0.00 2017-03-13 2017-03-18 2017-04-08 2017-05-13 2017-09-11 Bouba et la réalisation d'un decentralization process Selection Implementation forage équipé de pompe à Motricité humaine au CSI de Rey Bouba dans la Commune de Rey Bouba
CM-CRC NORD-9740-CS-INDV / contrôle des travaux de la construction d'un centre de Santé Intégré avec bloc de latrines au Centre de Santé de Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 5,940.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-10-18 Dembo, et la construction d'un decentralization process Selection Implementation bloc de deux (02) salles de classe équipé et d'un bloc de latrines dans les écoles publique de Laindé Tchakou
CM-CRC NORD-9741-CS-INDV / contrôle des travaux de des travaux de la construction et équipement 04 bloc de trois (03) salles de classe avec latrines Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 19,840.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-09-18 dans les établissement suivants : decentralization process Selection Implementation
'EP de Torroye, lycee de badjouma centre, lycée bilingue Pitoa, EP badejengo loperé, EP djalingo
CM-CRC NORD-9742-CS-INDV / contrôle des travaux de la construction d'un bloc de 02 Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 3,920.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-10-18 salles de classes avec latrines à decentralization process Selection Implementation l'EP DOGBA et Lycée GOP REY dans la Commune de Tcholliré,
CM-CRC NORD-9743-CS-INDV / contrôle des travaux de la Component B: Support to the Individual Consultant Pending construction d'un centre de santé IDA / 57180 Post Limited 4,320.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-10-18 decentralization process Selection Implementation avec latrines à Mayo GALKE dans la Commune de Tcholliré
CM-CRC NORD-9744-CS-INDV / contrôle des travaux de la Component B: Support to the Individual Consultant Pending réalisation d'un forage équipé de IDA / 57180 Post Limited 1,120.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-12-17 decentralization process Selection Implementation Pompe à Energie Solaire au CSI de Mayo Galké
CM-CRC NORD-9745-CS-INDV / contrôle des travaux de des travaux de pour la construction des 03 magasins de stockage des denrées agricoles à Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 10,512.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-09-18 BADANKALI, MAYO BOCKI et decentralization process Selection Implementation
DJALINGO KAPSIKI et des travaux de la Construction de un bloc de 03 salles équipés et d'un bloc de latrine à 04 comp
CM-CRC NORD-9746-CS-INDV / contrôle des travaux des travaux de la construction d'un Centre de Santé Intégré avec latrines à Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 5,280.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-12-18 DOUNDEHI , construction d'une decentralization process Selection Implementation mini AEP équipé de Pompe à Energie solaire au Centre de Santé de DOUNDEHI
CM-CRC NORD-9747-CS-INDV / contrôle des travaux de la construction et équipement d'un Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 3,840.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-12-18 bloc de deux (02) salles de decentralization process Selection Implementation classe avec latrines EP BIYAOU,moudouk,
CM-CRC NORD-9748-CS-INDV / contrôle des travaux de la Component B: Support to the Individual Consultant Pending construction de deux forages IDA / 57180 Post Limited 1,400.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-12-18 decentralization process Selection Implementation EPMH dans les villages de nbien dolé et baldjouk frontière
CM-CRC NORD-9749-CS-INDV / construction 2 blocs de 3 boutiques au marché de GOR, Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 2,400.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-12-18 sorobéo et d'un bloc de latrines à decentralization process Selection Implementation
6 compartiments dans la Commune de Madingring
CM-CRC NORD-9750-CS-INDV / contrôle des travaux de réalisation d'un forage au CES Bilingue de Bibémi, et exécution Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 1,560.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-11-18 des travaux de la construction decentralization process Selection Implementation d'un forage de pastoral équipé de PMH et 04 abreuvoirs à BIDE HAMADICKO
CM-CRC NORD-9751-CS-INDV / contrôle des travaux de Component B: Support to the Individual Consultant Pending construction d'un bloc de 02 IDA / 57180 Post Limited 1,600.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-11-18 decentralization process Selection Implementation salles de classes avec latrines au CES Bilingue de Bibémi,
CM-CRC NORD-9752-CS-INDV / contrôle des travaux de Component B: Support to the Individual Consultant Pending l'aménagement de la piste IDA / 57180 Post Limited 3,200.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-12-18 decentralization process Selection Implementation agricole BIBEMI-MBELLA (4Km) dans la Commune de Bibémi
CM-CRC NORD-9753-CS-INDV / contrôle des travaux de Component B: Support to the Individual Consultant Pending Construction de 03 forages IDA / 57180 Post Limited 2,560.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-12-18 decentralization process Selection Implementation EPMH à l'abattoir municipal de Tcholliré, Mbaou et Mbissiri
Page 11 CM-CRC NORD-9754-CS-INDV / contrôle des travaux Component B: Support to the Individual Consultant Pending d'électrification des quartiers IDA / 57180 Post Limited 1,860.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-09-18 decentralization process Selection Implementation Mboum Aviation et Ouro hamayel dans la Commune de Garoua 2
CM-CRC NORD-9755-CS-INDV / contrôle des travaux de construction d'un Forage Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 1,200.00 0.00 2017-06-20 2017-06-25 2017-07-16 2017-08-20 2017-11-18 pastoral équipé de Pompe à decentralization process Selection Implementation
énergie solaire dans la commune de BASCHEO,
CM-CRC LITTORAL-9757-CS- INDV / Etudes de faisabilité techniques et environnementales Component A: Local Individual Consultant Pending des travaux de construction de IDA / 57180 Post Open 1,280.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation logements sociaux dans la ville de Bare, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9758-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux d'extension du Component A: Local Individual Consultant Pending réseau électrique de Mouanko IDA / 57180 Post Open 2,990.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation centre à Nkankazok (1,5km) et travaux d'éclairage public des villages Mbiako, Youné 1&2 par énergie photovoltaïque
CM-CRC LITTORAL-9759-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction d'un Component A: Local Individual Consultant Pending motel municipal à Mouanko IDA / 57180 Post Open 2,920.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation centre et des travaux d'extension du Complexe touristique communal dans la Commune de Mouanko
CM-CRC LITTORAL-9760-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction d'une Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,736.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 usine de transformation de development support Selection Implementation manioc à Bakwat et d'une unité de fabrication des pavés à Ebone dans la Commune d'Ebone
CM-CRC LITTORAL-9761-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux d'éclairage public par Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,460.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 panneaux photovoltaïque des development support Selection Implementation localités de Ndoungué, Ebone, Nkognine et Manengolé, dans la Commune de Ebone
CM-CRC LITTORAL-9763-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de réhabilitation du Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,880.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 réseau d'eau potable de Salmoa, development support Selection Implementation dans la Commune de Ebone, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9764-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux d'extension du réseau électrique dans les Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,920.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 localités de Logyamben et development support Selection Implementation
Nyahenden , dans la Commune de Nyanon, Département de la Sanaga Maritime, Région du Littoral
CM-CRC LITTORAL-9765-CS- INDV / tudes de faisabilité techniques et environnementales des travaux de construction d'un Component A: Local Individual Consultant Pending bloc de deux salles de classe et IDA / 57180 Post Open 1,180.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation un bloc latrines à l'EP de Maleke, dans la Commune de Bonaléa, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9768-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction d'un Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,280.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 poste agricole à Ndoulou, dans la development support Selection Implementation
Commune de Bonaléa, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9769-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de constructions de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,380.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 20 boutiques au Marché de development support Selection Implementation
Loum, dans la Commune de Loum, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9770-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux d'électrification du Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,460.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 village Mabombe, dans la development support Selection Implementation
Commune de Loum, Département du Moungo, Région du Littoral
001/C/SC/SU/MENGONG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Component A: Local Individual Consultant Pending d'Extension du marché de vivres IDA / 57180 Post Open 2,479.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-10-12 development support Selection Implementation d'Ondodo et d'un bloc de 03 latrines et Réhabilitation du puits avec pompe à motricité humaine
CM-CRC LITTORAL-9772-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction d'un Component A: Local Individual Consultant Pending hangar au marché de Nlohe et IDA / 57180 Post Open 2,760.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation d'une ecole matenelle à Boum dans la Commune de Manjo, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9774-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction d'un Component A: Local Individual Consultant Pending bloc maternel à l'école maternelle IDA / 57180 Post Open 1,380.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation de Tomel dans la Commune de Massok, Département de la Sanaga Maritime, Région du Littoral
CM-CRC LITTORAL-9775-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de réhabilitation de la route Muyuka-Mbandja et de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,480.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 réhabilitation du réseau routier de development support Selection Implementation la ville de Mbanga, dans la Commune de Mbanga, Département du Moungo, Région du Littoral
003/C/SC/SU/AKOM II/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de construction de 03 puits positifs équipés des pompes à motricité Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,492.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-10-12 humaine à BIBINDI, BIBOLE et development support Selection Implementation
MALOMBA et 03 forages positifs équipés des pompes à motricité humaine à NLOKENG, TOKO et FENDA
004/C/SC/SU/OVENG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux d'Aménagement du hangar en Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,047.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-10-12 complexe commercial municipal development support Selection Implementation et de Construction d'un bloc latrines à deux compartiments à Oveng-centre
002/C/SC/SU/OVENG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de six (06) forages Component A: Local Individual Consultant Pending productifs équipés des Pompes àIDA / 57180 Post Open 2,410.00 0.00 2017-05-26 2017-06-17 2017-07-04 2017-07-27 2017-11-24 development support Selection Implementation Motricité Humaine dans six (06) villages (Essamekou, Adjap, Andoung, Aboulou, Bikougou et Mebassa)
005/C/SC/SU/BENGBIS/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 910.00 0.00 2017-05-26 2017-06-17 2017-07-04 2017-07-27 2017-11-24 construction d'un bloc de deux development support Selection Implementation
(02) salles de classe équipées à l'école primaire de Mekas
006/C/SC/SU/BENGBIS/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Component A: Local Individual Consultant Pending réalisation de 06 forages équipésIDA / 57180 Post Open 2,065.00 0.00 2017-05-26 2017-06-17 2017-07-04 2017-07-27 2017-11-24 development support Selection Implementation des PMH à Metom, à Endam, à l'EM de Bengbis, à Kam, Mimbil et au Ly-Tech de Bengbis
007/C/SC/SU/DJOUM/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Component A: Local Individual Consultant Pending réalisation de 03 forages équipésIDA / 57180 Post Open 1,184.00 0.00 2017-05-26 2017-06-17 2017-07-04 2017-07-27 2017-11-24 development support Selection Implementation des pompes à motricité humaine dans les villages Aboelon (école publique), Minko'o Baka et Djop
008/C/SC/SU/DJOUM/2017 / Sélection d'un Consultant pour le Component A: Local Individual Consultant Pending Suivi/contrôle des Travaux de IDA / 57180 Post Open 1,273.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-10-12 development support Selection Implementation construction d'un bloc maternel à l'école maternelle d'Aboélon
009/C/SC/SU/KYE OSSI/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de construction de 02 blocs de 02 Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,762.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-09-12 salles de classe équipées de development support Selection Implementation tables bancs et de 02 blocs de 02 latrines à l'EP de Mefoup et à l'EP de Mefou
010/C/SC/SU/KYE OSSI/2017 / Sélection d'un Consultant pour le Suivi/contrôle des travaux de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 584.00 0.00 2017-05-26 2017-06-17 2017-07-04 2017-07-27 2017-11-24 réalisation de 02 forages équipés development support Selection Implementation des pompes à motricité humaine dans les EP de Mefoup et Mefou
011/C/SC/SU/MEYOMESSALA/ 2017 / Sélection d'un Consultant pour le Suivi/contrôle des Transformation du marché de Meyomessala en campement Component A: Local Individual Consultant Pending IDA / 57180 Post Open 6,033.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-09-12 touristique : travaux development support Selection Implementation d'aménagement et équipement d'un bloc administratif, d'une buanderie, du bloc de 06 chambres modernes VIP, etc
012/C/SC/SU/MINTOM/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Component A: Local Individual Consultant Pending construction de la clôture et IDA / 57180 Post Open 1,626.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-09-12 development support Selection Implementation d'aménagement des aires de jeux des écoles maternelles de Mintom-centre
013/C/SC/SU/MINTOM/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Component A: Local Individual Consultant Pending d'extension du complexe IDA / 57180 Post Open 3,492.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-09-12 development support Selection Implementation commercial de Mintom et construction d'un forage positif équipé d'une PMH
014/C/SC/SU/OLAMZE/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de construction de 02 blocs de 02 salles de classe équipées de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 23,970.00 0.00 2017-05-26 2017-06-17 2017-07-04 2017-07-27 2017-11-24 tables bancs et d'un bloc de development support Selection Implementation latrines dans les EP de Yos II et de Mindjo-Koumou et construction d'un forage à l'EP de Mindjo-Koumou
015/C/SC/SU/MVANGAN/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de construction de 01 bloc de 02 Component A: Local Individual Consultant Pending salles de classe équipées de IDA / 57180 Post Open 1,527.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-09-12 development support Selection Implementation tables bancs et de 01 bloc de 02 latrines à l'EP de Mebemenko et d'un forage à l'EP de Zoébefam (Zoéyevan)
CM-PNDP-9851-CS-INDV / Recrutement d'un consultant pour l'élaboration du Guide des Component B: Support to the Individual Consultant Pending IDA / 57180 Post Open 30,000.00 0.00 2017-05-17 2017-07-05 2017-07-12 2017-08-02 2017-09-01 autorités communales pour le decentralization process Selection Implementation suivi de l'exécution des microprojets
016/C/SC/SU/SANGMELIMA/20 17 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,490,106.00 0.00 2017-04-06 2017-05-05 2017-05-22 2017-06-14 2017-10-12 de réalisation de 10 forages development support Selection Implementation
équipés des pompes à motricité humaine
017/C/SC/SU/ZOETELE/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de réalisation de 02 forages équipés Component A: Local Individual Consultant Pending IDA / 57180 Post Open 975.00 0.00 2017-05-26 2017-06-17 2017-07-04 2017-07-27 2017-11-24 des pompes à motricité humaine development support Selection Implementation
à l' EP de Zoétélé Grpe II, à l'EM de Zoétélé-ville et 01 puits équipé à Bidoumba (quartier Mfegkot)
018/C/SC/SU/ZOETELE/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de construction d'un bloc de deux Component A: Local Individual Consultant Pending (02) salles de classe équipées IDA / 57180 Post Open 2,082.00 0.00 2017-05-26 2017-06-17 2017-07-04 2017-07-27 2017-11-24 development support Selection Implementation de tables bancs à l'école primaire de Zoétélé Groupe II et d'un bloc maternel équipé de tables et bancs à Zoétélé-ville
001/C/CC/SU/EBOLOWA I/2017 / Recrutement d'un Agent de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,600.00 0.00 2017-04-27 2017-06-13 2017-06-28 2017-07-11 2018-07-11 Développment pour la Commune development support Selection Implementation d'Ebolowa I
002/C/CC/SU/EBOLOWA I/2017 / Recrutement d'un Agent Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,880.00 0.00 2017-04-27 2017-06-13 2017-06-28 2017-07-11 2018-07-11 Financier pour la Commune development support Selection Implementation d'Ebolowa I
003/C/CC/SU/EBOLOWA II/2017 / Recrutement d'un Agent Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,600.00 0.00 2017-04-27 2017-06-13 2017-06-28 2017-07-11 2018-07-11 de Développment pour la development support Selection Implementation
Commune d'Ebolowa II
004/C/CC/SU/EBOLOWA II/2017 / Recrutement d'un Agent Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,880.00 0.00 2017-04-27 2017-06-13 2017-06-28 2017-07-11 2018-07-11 Financier pour la Commune development support Selection Implementation d'Ebolowa II
005/C/CC/SU/KRIBI I/2017 / Recrutement d'un Agent de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,600.00 0.00 2017-04-27 2017-06-13 2017-06-28 2017-07-11 2018-07-11 Développment pour la Commune development support Selection Implementation de Kribi I
006/C/CC/SU/KRIBI I/2017 / Recrutement d'un Agent Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,880.00 0.00 2017-04-27 2017-06-13 2017-06-28 2017-07-11 2018-07-11 Financier pour la Commune de development support Selection Implementation
Kribi I
Page 12 CM-CRC LITTORAL-9902-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux d'électrification rurale Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,460.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 des villages Kombe et Matouke, development support Selection Implementation dans la Commune de Mbanga, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9903-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction d'un Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,100.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 ouvrage de franchissement à development support Selection Implementation
Ekah, dans la Commune de Melong, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9904-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux d'aménagement Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,040.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 d'une source amenagée, dans la development support Selection Implementation
Commune de Melong, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9905-CS- INDV / Etudes de faisabilité techniques et environnementales ds travaux de reprofilage du Component A: Local Individual Consultant Pending tronçon routier Mbanga quartier 7- IDA / 57180 Post Open 3,480.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation Mombo en passant par Nkwangsi, dans la Commune de Mombo, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9906-CS- INDV / Etudes de faisabilité techniques et environnementales Component A: Local Individual Consultant Pending des travaux de construction d'un IDA / 57180 Post Open 560.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation bloc latrines dans la Commune de Penja, Département du Moungo, Région du Littoral
CM-CRC LITTORAL-9907-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction d'un Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,180.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 poste de quai à Nkolbong par development support Selection Implementation
Massoumbou, dans la Commune de Yabassi, Département du Nkam, Région du Littoral
CM-CRC LITTORAL-9908-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux d'extension du réseau électrique allant du Component A: Local Individual Consultant Pending carrefour Bimbe au CES de IDA / 57180 Post Open 1,380.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation Bambou (10km) et d'électrification du village Dikola dans la Commune de Dizangue, Département de la Sanaga Maritime
CM-CRC LITTORAL-9909-CS- INDV / Etudes de faisabilité techniques et environnementales de construction d'un Motel Component A: Local Individual Consultant Pending municipal et de construction de IDA / 57180 Post Open 2,760.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation logements sociaux dans la Commune de Ngambe, Département de la Sanaga Maritime, Région du Littoral
CM-CRC LITTORAL-9910-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux d'électrification Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,460.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 Etouha-Song Kollo sur 3 km development support Selection Implementation dans la Commune de Ngwei, Département de la Sanaga Maritime, Région du Littoral
CM-CRC LITTORAL-9911-CS- INDV / Etudes de faisabilité techniques et environnementales des travaux de construction d'un Component A: Local Individual Consultant Pending auberge municipal du PK 16, IDA / 57180 Post Open 3,796.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-09-01 development support Selection Implementation construction de la Maison de la femme à Makondo, construction du marché de Makondo dans la Commune de Ngwei
CM-CRC LITTORAL-9912-CS- INDV / Suivi/contrôle des travaux de quatre forages positifs équipés d'une pompe à motricité Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,767.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-10-31 humaine à Moukouda, Mbagna, development support Selection Implementation
Nyamtam et Yabassi centre, dans la Commune de Yabassi, Région du Littoral
CM-CRC LITTORAL-9913-CS- INDV / Suivi/contrôle des travaux de Construction de deux blocs de boutiques, à raison de 10 Component A: Local Individual Consultant Pending IDA / 57180 Post Open 400.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-10-31 boutiques chacun, au marché de development support Selection Implementation
Loum Centre, dans la Commune de Loum, dans la Commune de Loum, Région du Littoral
CM-CRC LITTORAL-9914-CS- INDV / Suivi/contrôle des travaux de Construction d'un bloc de 10 boutiques, d'un bloc de 04 Component A: Local Individual Consultant Pending latrines et d'un hangar de marché IDA / 57180 Post Open 3,845.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-10-31 development support Selection Implementation rural périodique de 16 comptoirs au marché de Missole, dans la Commune de Dibamba, Région du Littoral
CM-CRC LITTORAL-9915-CS- INDV / Suivi/contrôle des travaux de Construction d'un forage positif équipé d'une pompe électrique d'au moins 2 m3/h, Component A: Local Individual Consultant Pending IDA / 57180 Post Open 745.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-10-31 alimentant un réservoir à development support Selection Implementation cubitainer de 2000 litres monté sur un support en béton armé au marché de Missole, dans la Commune de Dibamba
CM-CRC LITTORAL-9916-CS- INDV / Suivi/contrôle des travaux de Construction et d'Equipement Component A: Local Individual Consultant Pending d'une Case Communautaire et IDA / 57180 Post Open 2,516.00 0.00 2017-03-20 2017-05-08 2017-05-29 2017-07-03 2017-12-30 development support Selection Implementation d'un bloc de deux latrines à Bisseng, dans la Commune de Ndom, Région du Littoral
001/C/EF/SU/CAMPO/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de l'Extension Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-03-21 2017-04-25 2017-05-02 2017-05-22 2017-06-21 du complexe commercial à development support Selection Implementation travers l'aménagement du hangar, la construction des blocs de 05 boutiques et d'un bloc de 03 latrines)
002/C/EF/SU/LOKOUNDJE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de l'Extension IDA / 57180 Post Open 2,862.00 0.00 2017-03-21 2017-04-25 2017-05-02 2017-05-22 2017-06-21 development support Selection Implementation du réseau électrique dans les localités de Bonguen, d'Elogbatindi (Mitende), d'Ebéa, Bipaga 2
003/C/EF/SU/LOKOUNDJE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,860.00 0.00 2017-03-21 2017-04-25 2017-05-02 2017-05-22 2017-06-21 development support Selection Implementation construction des lampadaires solaires dans les localités de Mabenanga, Bandévouri I, Makouré I, Bissiang et Bidou I
004/C/EF/SU/LOKOUNDJE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,278.00 0.00 2017-03-21 2017-04-25 2017-05-02 2017-05-22 2017-06-21 Construction d'un complexe development support Selection Implementation commercial, d'un bloc de 06 latrines et d'un point d'eau au marché de la Kienké / SOCAPALM
005/C/EF/SU/MVENGUE/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 1,880.00 0.00 2017-03-21 2017-04-25 2017-05-02 2017-05-22 2017-06-21 development support Selection Implementation environnementales de l'extension du réseau électrique MT/BT vers le village Atinzam
006/C/EF/SU/MVENGUE/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 1,880.00 0.00 2017-03-21 2017-04-25 2017-05-02 2017-05-22 2017-06-21 development support Selection Implementation environnementales de l'électrification par énergie solaire des villages Melondo et Ebayega
007/C/EF/SU/NYETE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 2,000.00 0.00 2017-03-21 2017-04-25 2017-05-02 2017-05-22 2017-06-21 development support Selection Implementation Construction d'un bloc de 02 salles de classe équipées et un bloc de latrines au CETIC d'Andjeck
008/C/EF/SU/AKOM II/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,100.00 0.00 2017-05-26 2017-06-16 2017-07-01 2017-07-04 2017-08-18 Réhabilitation / Construction d'un development support Selection Implementation bloc de 02 salles de classe, d'un bloc de latrines et d'un point d'eau posititif équipé d'une PMH au Lycée tech
009/C/EF/SU/AKOM II/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 1,741.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de la Mise en place d'une pépinière de 3 ha de bananiers plantain à Akok
010/C/EF/SU/AKOM II/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,719.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 06 puits équipés de PMH dans les EP de Assok 1, Biboulemem, Ndjabilobé, Enyankol, Elon, Akom II centre
011/C/EF/SU/AKOM II/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 1,200.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de la Construction d'une cité municipale à Akom II centre
012/EF/SU/AKOM II/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 1,240.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de la construction d'une auberge municipale à Akom II centre
013/C/EF/SU/BENGBIS/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,716.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de la Mise en development support Selection Implementation place d'une pépinière de 25 000 plants de cacao de nouvelle génération à Evindissi centre
014/C/EF/SU/BENGBIS/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,716.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de la Mise en development support Selection Implementation place d'une pépinière de 25 000 plants de cacao de nouvelle génération à Metom
015/C/EF/SU/BIPINDI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,642.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de la development support Selection Implementation
Construction d`un bloc de deux salles de classes et un bloc de latrines au CES de Grand Zambi
016/C/EF/SU/BIPINDI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,426.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 08 points d'eau development support Selection Implementation
équipé d'une PMH au CES de Grand Zambi, à Bifoum, Koambo, Mandoungou, Memel I, Nyaminkom, Assok et Tyango
017/C/EF/SU/BIWONG BANE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,642.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 et environnementales de la development support Selection Implementation
Construction d'un foyer communautaire et d'un bloc de latrines à Ating Bané
018/C/EF/SU/BIWONG BANE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques Component A: Local Individual Consultant Pending et environnementales de la IDA / 57180 Post Open 1,431.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 04 points d'eau équipé d'une PMH à Ofoumbi, Efoumlou Nselek, Ekout-Fong et Engogom
019/C/EF/SU/BIWONG BANE/2017 / Sélection d'un consultant pour l'élaboration des Component A: Local Individual Consultant Pending études de faisabilité techniques IDA / 57180 Post Open 1,770.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation et environnementales de la Construction de 15 logements sociaux à Biwong Bané centre
020/C/EF/SU/BIWONG BULU/2017 / Sélection d'un consultant pour l'élaboration des Component A: Local Individual Consultant Pending études de faisabilité techniques IDA / 57180 Post Open 2,242.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation et environnementales de la Réalisation d'une adduction d'eau à Biwong Bulu centre
021/C/EF/SU/BIWONG BULU/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,233.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 construction d'un bloc de 02 development support Selection Implementation salles de classe équipées de tables bancs, un bloc de latrines et un point d'eau à l'EP de Abiete Yendjok
022/C/EF/SU/BIWONG BULU/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,233.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 construction d'un bloc de 02 development support Selection Implementation salles de classe équipées de tables bancs, un bloc de latrines et un point d'eau dans l'EP de Nloupessa-Yevol
Page 13 023/C/EF/SU/CAMPO/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,746.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de la development support Selection Implementation
Construction d'un foyer communautaire et un bloc de latrines à Bouandjo
024/C/EF/SU/CAMPO/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,741.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de la development support Selection Implementation
Raccordement du marché de Campo aux réseaux d'électricité et d'eau
025/C/EF/CAMPO/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,313.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 03 points d'eau équipé d'une PMH à Afan- Essokié, Akak (Chefferie) et Bitandé Assoé
026/C/EF/SU/DJOUM/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,181.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 04 points d'eau équipé des PMH à Akombinyeng, Nkolenyeng, Miatta et Djouze
027/C/EF/SU/DJOUM/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 1,741.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de l'Extension du réseau électrifique vers le village Bidoumba
028/C/EF/SU/EFOULAN/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,003.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 07 points d'eau development support Selection Implementation
équipé des PMH à Bikoula, à l'EP de Mengale, EP de Mfalla, EP d'Adjap-Essawo, Ngalan II et à la SAR/SM d'Efoulan
029/C/EF/SU/EFOULAN/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,254.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction d'un bloc de 02 development support Selection Implementation salles de classe équipées de tables bancs et d'un bloc de latrines à l'EP d'Engomba et la Construction de 02 ateliers
030/C/EF/SU/KYE OSSI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,741.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation construction des lampadaires LED pour l'éclairage public de l'espace urbain de la ville de KYE- OSSI
031/C/EF/SU/KYE OSSI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 3,254.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction d`un bloc de 02 salles de classes équipées et un bloc de latrines dans les EP d'Ongozok et Kono-Fonossi
032/C/EF/SU/KYE OSSI/2017 / Sélection d'un consultant pour l'actualisation des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,600.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de la development support Selection Implementation
Construction des blocs de boutiques au marché de Kyé- ossi
033/C/EF/SU/KYE OSSI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,405.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 04 points d'eau équipé d'une PMH à l'EP d'Ongozok, EP de Kono-Fonossi, Nsamgbwang et Nkan
034/C/EF/SU/LOLODORF/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,575.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 04 points d'eau development support Selection Implementation
équipé des PMH à Sabally (quartier Biubvuri), Mvilé, EP de Koumbinzik et à l'EP de Melangue-Mvog
035/C/EF/SU/LOLODORF/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,254.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction d'un bloc de 02 development support Selection Implementation salles de classes équipées et d'un bloc de latrines dans les EP de Koumbinzik et Melangue- Mvog
036/C/EF/SU/MAAN/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,421.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 03 points d'eau development support Selection Implementation
équipé des PMH à l'école bilingue de Ma'an centre, au CETIC de Ma'an centre et à Meyos I
037/C/EF/SU/MAAN/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,053.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction d'un bloc de 02 development support Selection Implementation salles de classes équipées et d'un bloc de latrines à l'école bilingue de Ma'an centre et au CETIC de Ma'an centre
038/C/EF/SU/MAAN/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 1,523.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de l'Extension du marché municipal (30 boutiques) de Ma'an centre
039/C/EF/SU/MENGONG/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,354.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction d'un logement development support Selection Implementation d'astreinte et d'un bloc de latrines pour les enseignants de l'EP de Nnemeyong III et la Construction d'un bloc de 02 s
040/C/EF/SU/MENGONG/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 3,254.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction d'un bloc de 02 salles de classe équipées et un bloc de latrines dans les EM d'Endam I et d'Abiete
041/C/EF/SU/MENGONG/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,391.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 04 points d'eau development support Selection Implementation
équipé des PMH à l'EM de Ekouk, à l'EM d'Endam I, à l'EP de Nnemeyong III et à l'EM d'Abiete
042/C/EF/SU/MEYOMESSALA/ 2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,820.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction d'une ferme communale de production de poussins et d'un bloc de latrines à Meyomessala
043/C/EF/SU/MEYOMESSALA/ 2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,431.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 03 points d'eau development support Selection Implementation
équipé de PMH à la ferme communale de Meyomessala, au CETIC d'Endam et au CES de Ngoasse
044/C/EF/SU/MEYOMESSALA/ 2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,841.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction d'01 bloc de 2 development support Selection Implementation salles de classe équipées de tables bancs et d'un bloc de latrines au CETIC d'Endam et la Construction de la clôture d
045/C/EF/SU/MEYOMESSI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de l'Extension development support Selection Implementation du réseau électrique vers le village Essong-Ndonge et vers le village Mbilemvom
046/C/EF/SU/MEYOMESSI/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 2,000.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de la Mise en place d'une pépinière de 10 000 plants de cacaoyers à Mimbang
047/C/EF/SU/MEYOMESSI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 2,333.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction d`un bloc de deux salles de classes et d'un point d'eau équipé d'une PMH à l'EP de Ndjelle à l'EP de Ndjelle
048/C/EF/SU/MINTOM/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 2,200.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de la Construction et l'équipement d`une auberge municipale
049/C/EF/SU/MINTOM/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,904.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 04 points d'eau équipés des PMH à Mintom I, Odoumou, Zo`otou II et à l'EP de Bindom
050/C/EF/SU/MINTOM/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,626.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de la development support Selection Implementation
Construction d`un bloc de deux salles de classes et un bloc de latrines à l'EP de Bindom
051/C/EF/SU/MVENGUE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 2,400.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction d`une auberge municipale de 25 chambres dotée d`un restaurant à Mvengue- centre
052/C/EF/MVENGUE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,840.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 04 points d'eau positifs équipés des PMH au marché de Mvengue, Wom I, Okoga et à l'EP de Mvengue III
053/C/EF/SU/NGOULEMAKONG /2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 2,000.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de la Construction et équipement d'une cité communale à Ngoulemakong
054/C/EF/SU/NGOULEMAKONG /2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,526.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 environnementales de la development support Selection Implementation
Construction d`un hangar et magasin de stockage à Ngoulemakong
055/C/EF/SU/NGOULEMAKONG /2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales du IDA / 57180 Post Open 1,993.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Renforcement du système d`approvisionnement en eau (supresseur+forage) de la ville de Ngoulemakong
056/C/EF/SU/NYETE/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 1,741.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de l'Extension du réseau électrique BTvers Nyété
057/C/EF/SU/NYETE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,054.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction d`un foyer culturel development support Selection Implementation polyvalent à Nlozok la Construction de logements d`astreinte pour enseignants à l`EP de Bifa
058/C/EF/SU/NYETE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,325.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 03 points d'eau positif équipés des PMH à Bifa (EP), à Andjeck (CETIC) et à Nlozok (Foyer culturel
Page 14 059/C/EF/SU/OLAMZE/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité techniques et IDA / 57180 Post Open 2,000.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation environnementales de la Construction d'une cité municipale à OLAMZE centre
060/C/EF/SU/OLAMZE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 2,662.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction d`un bloc de deux salles de classe et d'un bloc de latrines dans les EP de MENGUIKOM et d'Engo Nlozock
061/C/EF/SU/OLAMZE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,430.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 04 points d'eau development support Selection Implementation positifs équipés des PMH à l`EP de MENGUIKOM, à l`EP d'Engo Nlozock, dans le village Bekué et dans le village Bind
062/C/EF/SU/OVENG/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 3,315.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction d`un bloc de 02 salles de classe et un bloc de latrines à l'EP d'Oveng-centre, d'Eboman et à l'EM de Medjeng
063/C/EF/SU/OVENG/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,015.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction d'01 bloc de 02 development support Selection Implementation salles de classe équipées et 01 bloc de latrines à l'EP d'Onon et la Construction des logements d`astreinte pour ense
064/C/EF/SU/OVENG/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,670.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 04 points d'eau development support Selection Implementation positifs équipés des PMH au CSI d'Akoabas, à Mvam I (chefferie), à l'EP d'Onon et à l'EP de Ngoudjen
065/C/EF/SU/SANGMELIMA/201 7 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,669.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 Construction de 08 points d'eau development support Selection Implementation positifs équipés d'une PMH à Akomedibi (quartier Etebele), à Akoolui (quartier Bilone), à Akoolui (quartier Nkoles
066/C/EF/SU/SANGMELIMA/201 7 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et environnementales de la Component A: Local Individual Consultant Pending Construction de 07 points d'eau IDA / 57180 Post Open 2,335.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation positifs équipés des PMH à l'EP de Bikobosaman, à Bizang (quartier Ngoa Ekele), à Eminemvom (quartier Mvog Zanga),
067/C/EF/SU/ZOETELE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 3,200.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction d`un bloc de deux salles de classe et d`un bloc de latrines dans les EP d'Adjap et d'Awout
068/C/EF/SU/ZOETELE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité techniques et Component A: Local Individual Consultant Pending environnementales de la IDA / 57180 Post Open 1,461.00 0.00 2017-05-26 2017-06-19 2017-07-07 2017-07-17 2017-08-31 development support Selection Implementation Construction de 04 points d'eau positifs équipés des PMH à l'EP d'Adjap, à l'EP d'Awout, à Woabete et à Otetek
CM-PNDP-10172-CS-INDV / Component C: Coordination, Recrutement d'un consultant Individual Consultant Pending IDA / 57180 management, monitoring and Post Limited 9,600.00 0.00 2017-03-29 2017-04-03 2017-04-17 2017-05-08 2017-12-29 pour le conseil en assurance au Selection Implementation evaluation and communication PNDP
CM-PNDP-10317-CS-INDV / Sélection d'un consultant en appui à la formation des acteurs Component B: Support to the Individual Consultant Pending IDA / 57180 Post Limited 4,000.00 0.00 2017-04-03 2017-04-08 2017-04-22 2017-05-06 2017-05-13 locaux à l'alignement du budget decentralization process Selection Implementation communal à la nomenclature du budget programme
CM-PNDP-10322-CS-INDV / Sélection d'un consultant pour la Component B: Support to the Individual Consultant Pending IDA / 57180 Post Open 30,000.00 0.00 2017-04-10 2017-05-20 2017-06-03 2017-07-01 2017-07-31 réalisation des études sur la decentralization process Selection Implementation fiscalité locale
CM-PNDP-10323-CS-INDV / Sélection d'un consultant pour la Component B: Support to the Individual Consultant Pending réalisation des études liées à la IDA / 57180 Post Open 20,000.00 0.00 2017-04-24 2017-06-03 2017-06-17 2017-07-15 2017-08-14 decentralization process Selection Implementation stratégie de décentralisation en cours de validation
CM-PNDP-10333-CS-INDV / Sélection d'un consultant en appui à la formation des TSP Component B: Support to the Individual Consultant Pending IDA / 57180 Post Direct 3,000.00 0.00 2017-04-24 2017-05-04 2017-05-11 2017-05-25 2017-06-01 (prestataires de services, decentralization process Selection Implementation consultants pour la mise en oeuvre des micropjets, etc
CM-PNDP-10337-CS-INDV / Sélection d'un consultant en Component B: Support to the Individual Consultant Pending appui au développement de IDA / 57180 Post Direct 12,000.00 0.00 2017-04-04 2017-04-14 2017-04-21 2017-05-05 2017-05-12 decentralization process Selection Implementation l'Economie Sociale et Solidaire (ESS)
CM-PNDP-10344-CS-INDV / Sélection d'un consultant pour la Component C: Coordination, Individual Consultant Pending production d'un film documentaire IDA / 57180 management, monitoring and Post Limited 19,200.00 0.00 2017-04-20 2017-04-25 2017-05-09 2017-05-30 2017-06-13 Selection Implementation sur le PNDP dans le septentrion evaluation and communication ( français/anglais)
CM-PNDP-10347-CS-INDV / Sélection d'un consultant pour la Component C: Coordination, Individual Consultant Pending conception de l'application IDA / 57180 management, monitoring and Post Open 6,000.00 0.00 2017-04-10 2017-05-13 2017-05-27 2017-06-17 2017-07-17 Selection Implementation mobile du site internet du PNDP evaluation and communication et mise en ligne
CM-PNDP-10348-CS-INDV / Sélection d'un consultant en appui à la participation du PNDP Component B: Support to the Individual Consultant Pending à la Journée Africaine de la IDA / 57180 Post Direct 6,000.00 0.00 2017-04-24 2017-05-04 2017-05-18 2017-06-01 2017-06-08 decentralization process Selection Implementation Décentralisation et du Développement Local (JADDEL 2017)
CM-PNDP-10358-CS-INDV / Component C: Coordination, Sélection d'un consultant pour Individual Consultant Pending IDA / 57180 management, monitoring and Post Open 20,000.00 0.00 2017-04-25 2017-06-04 2017-06-18 2017-07-02 2017-08-01 l'étude sur la prise en compte du Selection Implementation evaluation and communication genre dans le mode opératoire
Component C: Coordination, CM-PNDP-2842-CS-INDV / Individual Consultant Pending IDA / 57180 management, monitoring and Post Limited 10,000.00 0.00 2017-03-22 2017-03-27 2017-04-17 2017-05-15 2018-05-10 Conseil juridique au PNDP Selection Implementation evaluation and communication
CM-PNDP-2843-CS-CDS / Recrutement d'un consultant pour l'actualisation des données du système d'information Component B: Support to the Pending IDA / 57180 Post Direct Selection Direct 100,000.00 0.00 2017-05-15 2017-05-25 2017-07-06 2018-01-02 géographique dans les 31 decentralization process Implementation communes d'arrondissement (Convention avec l'Institut National de Cartographie)
CM-PNDP-2943-CS-INDV / Mise Component C: Coordination, en page du Magazine trimestriel Individual Consultant Pending IDA / 57180 management, monitoring and Post Limited 5,200.00 0.00 2017-03-17 2017-03-22 2017-04-05 2017-04-26 2017-10-23 " LES ECHOS DU PNDP" Selection Implementation evaluation and communication (infographie)
CM-PNDP-2941-CS-INDV / Component C: Coordination, Conception des articles du Individual Consultant Pending IDA / 57180 management, monitoring and Post Limited 3,600.00 0.00 2017-03-17 2017-03-22 2017-04-05 2017-05-03 2017-10-30 Magazine trimestriel " LES Selection Implementation evaluation and communication ECHOS DU PNDP", en français
CM-PNDP-2934-CS-INDV / Component C: Coordination, Individual Consultant Pending Formation de journalistes sur les IDA / 57180 management, monitoring and Post Limited 4,800.00 0.00 2017-04-24 2017-04-29 2017-05-20 2017-06-24 2017-12-21 Selection Implementation thématiques chères au PNDP 3 evaluation and communication
020/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE BELABO
021/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-05-08 2017-05-08 2017-05-29 2017-07-13 ENVIRONNEMENTALE DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE D'ABONG- MBANG
022/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENTS DANS LA COMMUNE DE BATOURI
023/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE GAROUA-BOULAI
024/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISIBILITES TECHNIQUES Component A: Local Individual Consultant Pending ET ENVIRONNEMENTALES IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation DES MICROPROJETS BATIMENT DANS LA COMMUNE DE KETTE
025/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE TECHNIQUES Component A: Local Individual Consultant Pending ET ENVIRONNEMENTALES IDA / 57180 Post Open 42,000.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation DES MICROPROJETS BATIMENT DANS LA COMMUNE DE MBANG
026/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT ET EQUIPEMENT DANS LA COMMUNE DE NGOYLA
027/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE SALAPOUMBE
028/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT ET EQUIPEMENT DANS LA COMMUNE DE YOKADOUMA
030/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET ENVIRONNEMENTALES DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,600.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
D'ELECTRIFICATION DU MARCHE D'ABONG-MBANG DANS LA COMMUNE D'ABONG- MBANG
031/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES Component A: Local Individual Consultant Pending TECHNIQUES ET IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation ENVIRONNEMENTALES DES MICROPROJETS BATIMENT DANS LA COMMUNE D'ATOK
032/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-02 2017-06-20 2017-07-11 2017-08-15 2017-09-29 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT ET EQUIPEMENT DANS LA COMMUNE DE MANDJOU
033/C/PNDP/EST/2017/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALE DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE MINDOUROU
034/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE TECHNIQUES Component A: Local Individual Consultant Pending ET ENVIRONNEMENTALES IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation DES MICROPROJETS BATIMENT DANS LA COMMUNE DE BETARE-OYA
035/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE LOMIE
036/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE NGOURA
037/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE DOUMAINTANG
Page 15 038/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNENTALES DES development support Selection Implementation
MICROPROJETS BATIMENT DANS LA COMMUNE DE GARI- GOMBO
039/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 42,000.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS HYDRAULIQUES DANS LA COMMUNE DE MOLOUNDOU
040/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS HYDRAULIQUES DANS LA COMMUNE DE BELABO
041/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-15 2017-07-03 2017-07-24 2017-08-28 2017-10-12 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS HYDRAULIQUES DANS LA COMMUNE DE DIANG
042/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDE DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending ENVIRONNEMENTALES DES IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation MICROPROJETS HYDRAULIQUES DANS LA COMMUNE D'ATOK
043/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS HYDRAULIQUES DANS LA COMMUNE DE MANDJOU
009/C/EF/CE/MAKENENE/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité technique et environnementale du microprojet Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,400.00 0.00 2017-04-10 2017-04-10 2017-04-10 2017-05-01 2017-06-30 de constructio d'un bloc maternel development support Selection Implementation
équipé et d'un bloc de trois latrines à l'Ecole Maternelle de Baloua, dans la commune de Makenene
010/C/EF/CE/MAKENENE/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du microprojet IDA / 57180 Post Open 1,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation de construction d'un forage équipé de PMH à l'école Maternelle de Baloua, dans la Commune de Makenene,
011/C/EF/CE/MAKENENE/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du microprojet IDA / 57180 Post Open 1,400.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation de construction d'une tribune de 1000 places assises à Makenene Centre, dans la Commune de Makenene
012/C/EF/CE/LOBO/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité des microprojets de construction d'un bloc de deux Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 (02) salles de classe équipées, development support Selection Implementation d'un bloc de 03 latrines à l'EP de Kelle et d'un hangar de marché à Lobo centre, commune de Lobo
013/C/EF/CE/LOBO/2017 / Sélection d'un consultant pour l'élaboration de l'Étude de faisabilité technique et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 environnementale du microprojet development support Selection Implementation de construction d'un forage au marché de Lobo centre, dans la commune de Lobo
014/C/EF/CE/OKOLA/2017 / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité pour la const de 02 blocs de 02 salles de classes Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 équipées, de 02 blocs de 03 lat development support Selection Implementation au CES de VOA et à d'okola Centre, d'un atelier de maçonnerie et d'un bloc 03 lat au CETIC d'Elig
015/C/EF/CE/OKOLA/2017 / Sélection d'un consultant pour les études de faisabilité de construction de (03) forages équipés de PMH au CES de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 VOA II, au CETIC d'ELIG ONANA development support Selection Implementation et à l'Ecole bilingue d'Okola Centre et réhabilitation d'une mini adduction d'Eau Potable derrière SOCCOPO
016/C/EF/CE/NANGA EBOKO/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité du Component A: Local Individual Consultant Pending microprojet de construction d'un IDA / 57180 Post Open 2,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation bloc de 02 salles de classe équipées et d'un bloc de trois latrines à l'EP de Ndjombe, dans la commune de Nanga Eboko
017/C/EF/CE/NANGA EBOKO/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du microprojet IDA / 57180 Post Open 1,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation de construction d'un forage équipé de PMH à l'EP de Ndjombe dans la commune de Nanga et Eboko
018/C/EF/CE/MAKAK/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité du microprojet Component A: Local Individual Consultant Pending d'éclairage à l'énergie solaire du IDA / 57180 Post Open 2,800.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation centre ville de Makak sur 6 km et électrification du village Mbeng sur environ 15 km, commune de Makak
019/C/EF/CE/MNTA/2017 / Sélection d'un consultant les études de faisabilité de construction d'un hangar de marché avec comptoirs et bloc Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,800.00 0.00 2017-04-23 2017-06-13 2017-06-20 2017-07-12 2017-11-09 latrine à (04) compartiments au development support Selection Implementation marché de Minta ville et d'un bloc de 02 salles de classes équipées avec 01 bloc de trois latrines à l'EP
020/C/EF/CE/MINTA/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité pour la construction Component A: Local Individual Consultant Pending de 05 forages équipés de PMH à IDA / 57180 Post Open 2,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation l'EP de ELOT, à l'EP d'Afan Oveng, à Mbargue, au marché de Minta ville et à Meba dans la commune de Minta
021/C/EF/CE/MBALMAYO/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du microprojet IDA / 57180 Post Open 2,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation de construction d'un hangar et de boutiques avec blocs de quatre latrines au marché Japon, dans la Commune de Mbalmayo
022/C/EF/CE/MBALMAYO/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et environnementale du Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,200.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 raccordement en eau potable au development support Selection Implementation réseau CDE et la construction de deux bornes fontaines au marché Japon, dans la Commune de Mbalmayo
023/C/EF/CE/NSEM/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité de construction d'un bloc de (02) salles de classe Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,800.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 équipées à l'EP de Mbenda, d'un development support Selection Implementation atelier d'électricité au CETIC de Nsem et de 02 bloc de 03 latrines à l'EP de Mbenda et au CETIC de
024/C/EF/CE/NSEM/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité pour la réhabilitations Component A: Local Individual Consultant Pending d'un puits équipé de PMH à l'EP IDA / 57180 Post Open 1,600.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation de Mbenda, du réseau CAMWATER et raccordement au CETIC de Nsem, dans la commune de Nsem
025/C/EF/CE/AWAE/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et environnementale du microprojet Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 de construction d'un parc à gros development support Selection Implementation porteur de 100 camions et d'un bloc latrines à deux compartiments à Ekiembie 1, commune d'Awae
044/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE MINDOUROU
045/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE BETARE-OYA
046/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE NGOURA
047/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE DOUMAINTANG
048/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE MESSAMENA
049/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE GARI-GOMBO
026/C/EF/CE/AWAE/2017 / Sélection d'un consultant pour l'élaboration de l'étude de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du microprojet IDA / 57180 Post Open 800.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation de construction d'un puits équipé de PMH au parc à gros porteur de 100 camions d'Ekiembie 1, commune d'Awae
050/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE LOMIE
027/C/EF/CE/AKONOLINGA/201 7 / Sélection d'un consultant pour l'élaboration des études de faisabilitédu microprojet de construction de deux hangars de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 36 comptoirs + un bloc latrines development support Selection Implementation de trois (03) compartiments au marché quartier Haoussa à Akonolinga, dans la Commune d'Akonolinga
051/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,600.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE D'ABONG-MBANG
052/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE BATOURI
028/C/EF/CE/AKONOLINGA/201 7 / Sélection d'un consultant pour l'élaboration des études de faisabilité technique et environnementale du microprojet Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 de construction d'un forage development support Selection Implementation
équipé de PMH à l'EM d'application GI, G2 du Centre administratif, commune d'Akonolinga
053/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE DES Component A: Local Individual Consultant Pending MICROPROJETS IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation HYDRAULIQUES DANS LA COMMUNE DE GAROUA- BOULAI
054/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE KETTE
029/C/EF/CE/NKOLAFAMBA/20 17 / Sélection d'un consultant pour l'élaboration des études de faisabilité du microprojet d'extension de 02 réseaux Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,400.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 électriques : 1 km de MT et development support Selection Implementation
300m de BT tryphasé de Mbe Ekom-Lycée technique-CSI d'Omvan-extension BT (900m), et 3,2km de MT et BT tryphasé de
Page 16 055/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 MICROPROJETS development support Selection Implementation
HYDRAULIQUES DANS LA COMMUNE DE MBANG
056/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE TECHNIQUES Component A: Local Individual Consultant Pending ET ENVIRONNEMENTALES IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation DES MICROPROJETS HYDRAULIQUES DANS LA COMMUNE DE NGOYLA
030/C/EF/CE/NGOUMOU/2017 / Sélection d'un consultant pour l'élaboration des étude de faisabilité technique et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,400.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 environnementale du microprojet development support Selection Implementation de réhabilitation de la route Nkolmen - Ovangoul sur 5 km, commune de Ngoumou
057/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE TECHNIQUES Component A: Local Individual Consultant Pending ET ENVIRONNEMENTALES IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation DES MICROPROJETS HYDRAULIQUES DANS LA COMMUNE DE SALAPOUMBE
031/C/EF/CE/NGOUMOU/2017 / Sélection d'un consultant pour l'élaboration des étude de faisabilité technique et environnementales du microprojet Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,800.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 d'extension du réseau électrique development support Selection Implementation
1,3Km de BT et MT d' Ovangoul - Tega Minboman et de Minlo Minzoa 2,3Km à Ofoumbi, commune de Ngoumou
058/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS HYDRAULIQUES DANS LA COMMUNE DE YOKADOUMA
032/C/EF/CE/MATOMB/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité du microprojet de construction de (02) hangars de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,800.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 marché avec comptoirs et development support Selection Implementation construction de (02) bloc de (04) latrines aux marchés de Mandoumba et Nkeng Likock, Commune de Matomb
059/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITES TECHNIQUES ET Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 ENVIRONNEMENTALES DES development support Selection Implementation
MICROPROJETS HYDRAULIQUES DANS LA COMMUNE DE MESSOK
033/C/EF/CE/MATOMB/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité technique et environnementales du microprojet Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,200.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 de construction de 02 forages development support Selection Implementation
équipés de PMH au marché de Mandoumba et au marché de Nkeng Likock, commune de Matomb
060/C/EF/PNDP/EST/2017 / ELABORATION DES ETUDES DE FAISABILITE TECHNIQUES Component A: Local Individual Consultant Pending ET ENVIRONNEMENTALES IDA / 57180 Post Open 4,200.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2017-10-05 development support Selection Implementation DES MICROPROJETS BATIMENTS DANS LA COMMUNE DE MESSAMENA
061/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE DE SOMALOMO
062/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE D'ANGOSSAS
063/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE DE MBOMA
064/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending MICROPROJETS DANS LA IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 development support Selection Implementation COMMUNE DE NGUELEMENDOUKA
065/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE DE DOUME
066/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE DE NGUELEBOK
067/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE DE OULI
068/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE DE KENTZOU
069/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE DE NDELELE
070/C/CT/PNDP/EST/2017 / SUIVI/CONTROLE DES Component A: Local Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-06-15 2017-08-03 2017-08-24 2017-09-28 2017-11-12 MICROPROJETS DANS LA development support Selection Implementation
COMMUNE DE DIMAKO
CM-PNDP-2938-CS-INDV / Component C: Coordination, Individual Consultant Pending Élaboration de la charte IDA / 57180 management, monitoring and Post Open 6,201.00 0.00 2017-03-05 2017-04-07 2017-04-21 2017-05-19 2017-11-15 Selection Implementation graphique et sonore du PNDP 3 evaluation and communication
CM-PNDP-2936-CS-INDV / Component C: Coordination, Revue mensuelle de la presse Individual Consultant Pending IDA / 57180 management, monitoring and Post Limited 4,000.00 0.00 2017-01-02 2017-01-07 2017-01-21 2017-02-11 2017-08-10 spécialisée et les notes Selection Implementation evaluation and communication conjoncturelles
CM-PNDP-2935-CS-INDV / Component C: Coordination, Individual Consultant Pending Revue de la quotidienne et IDA / 57180 management, monitoring and Post Limited 3,000.00 0.00 2017-01-02 2017-01-07 2017-01-28 2017-03-04 2017-08-31 Selection Implementation monitoring des médias evaluation and communication
CM-PNDP-2937-CS-INDV / Maintenance et animation du Component B: Support to the Individual Consultant Pending IDA / 57180 Post Open 8,000.00 0.00 2017-02-05 2017-03-26 2017-04-16 2017-05-21 2017-11-17 portail internet sur le PNDP et decentralization process Selection Implementation les communes
CM-PNDP-2841-CS-CDS / Formation, assistance technique Component B: Support to the Pending IDA / 57180 Post Direct Selection Direct 70,000.00 0.00 2016-12-03 2016-12-13 2017-02-16 2017-08-15 et déploiement du logiciel sim_ba decentralization process Implementation dans les communes
034/C/EF/CE/NGOG MAPUBI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité pour la construction de 04 forages Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,600.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 équipés de pompes à motricité development support Selection Implementation humaine à Mode chefferie, à l'EP de Ngog Mapubi, à Omog et à l'EP de Dibodi, dans la Commune de Ngog Mapubi
035/C/EF/CE/NGOG MAPUBI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du Microprojet IDA / 57180 Post Open 1,400.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation de réhabilitation de la station scan water de Ngog Mapubi, dans la Commune de Ngog Mapubi
036/C/EF/CE/NGOG MAPUBI/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité technique et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,400.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 environnementale du Microprojet development support Selection Implementation d'électrification rurale de Libengoï Bethel sur 4 km, dans la Commune de Ngog Mapubi
037/C/EF/CE/SAA/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité pour la construction Component A: Local Individual Consultant Pending d'un hangar avec comptoirs et IDA / 57180 Post Open 2,800.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation blocs de quatre latrines et de réhabilitation d'un hangar au marché municipal B de Sa'a, dans la Commune de Sa'a
038/C/EF/CE/SAA/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité pour la construction de Component A: Local Individual Consultant Pending 03 forages équipés de PMH au IDA / 57180 Post Open 1,200.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation marché municipal de Sa'a, au marché municipal B, au village NSAN MENDOUGA (Ayissi Elé), dans la Commune de SAA
039/C/EF/CE/SAA/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité technique et Component A: Local Individual Consultant Pending environnementale du microprojet IDA / 57180 Post Open 1,400.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation d'Extension de l'énergie électrique dans le quartier Engolo sur 2km à l'EST du village, dans la Commune de Sa'a
041/C/EF/CE/DIBANG/2017 / Sélection d'un consultant pour l'élaboration des études de faisabilité de construction de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,600.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 quatre (04) forages dans les development support Selection Implementation localités de Mapubi, Mahole, Ndoupe et Somapan, dans la commune de Dibang
042/C/EF/CE/MAKAK/2017 / Sélection d'un consultant pour l'élaboration des études de Component A: Local Individual Consultant Pending faisabilité de construction d'un IDA / 57180 Post Open 3,000.00 0.00 2017-04-10 2017-05-29 2017-06-19 2017-07-24 2017-09-22 development support Selection Implementation centre commercial de 100 boutiques multi standing à Makak, commune de Makak
010/C/SC/CE//NKOTENG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'une mini Component A: Local Individual Consultant Pending adduction d'approvisionnement IDA / 57180 Post Open 640.00 0.00 2017-04-16 2017-06-04 2017-06-25 2017-07-30 2017-11-27 development support Selection Implementation en eau potable sur le site de l'abattoir de Nkoteng dans la Commune de Nkoteng, Région du Centre
011/C/SC/CE/NKOTENG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un (01) hangar Component A: Local Individual Consultant Pending avec comptoirs et un bloc IDA / 57180 Post Open 1,760.00 0.00 2017-04-23 2017-06-11 2017-07-02 2017-07-31 2017-11-28 development support Selection Implementation latrines à quatre (04) compartiments au carrefour Ndoumba dans la Commune de Nkoteng, Région du Centre
012/C/SC/CE/NKOTENG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un (01) puits Component A: Local Individual Consultant Pending IDA / 57180 Post Open 480.00 0.00 2017-04-23 2017-06-11 2017-06-18 2017-07-17 2017-11-14 équipé de Pompe à Motricité development support Selection Implementation
Humaine au carrefour Ndoumba dans la Commune de Nkoteng, Région du Centre
013/C/SC/CE/ELIF MFOMO/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de sept (07) forages productifs Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,554.00 0.00 2017-04-23 2017-06-11 2017-07-02 2017-07-31 2017-11-28 équipés de Pompe à Motricité development support Selection Implementation
Humaine dans sept (07) localités (Nkol-Obang, Ban Edouma 2, EP de Mebomo, Lekoukoua, Bodo, Enobita et CES de Kokodo)
014/C/SC/CE/OBALA/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Component A: Local Individual Consultant Pending Construction d'un puits equipe de IDA / 57180 Post Open 480.00 0.00 2017-04-23 2017-06-02 2017-06-17 2017-07-16 2017-11-13 development support Selection Implementation PMH à nkol-Ekui dans la Commune d'Obala, Région du Centre
015/C/SC/CE/OBALA/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un bloc de deux Component A: Local Individual Consultant Pending (02) salles de classes équipé de IDA / 57180 Post Open 1,600.00 0.00 2017-04-23 2017-06-02 2017-06-17 2017-07-16 2017-11-13 development support Selection Implementation 60 table-bancs de niveau 2, de 02 bureaux pour enseignants à nkol-Ekui dans la Commune d'Obala, Région du Centre
016/C/SC/CE/OBALA / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Component A: Local Individual Consultant Pending d'extension du réseau électrique IDA / 57180 Post Open 3,369.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 development support Selection Implementation à sur la route Elig bodo- Yemsoa dans la commune d'Obala, Région du Centre
017/C/SC/MONATELE/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction deux (02) hangars Component A: Local Individual Consultant Pending de 32 comptoirs avec deux (02) IDA / 57180 Post Open 4,116.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 development support Selection Implementation blocs latrines à trois (03) compartiments aux marchés de deux (02) dans les localités de Ezezang et Lenouk, à monatélé
018/C/SC/CE/MONATELE/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un (01) forage Component A: Local Individual Consultant Pending IDA / 57180 Post Open 680.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 productif équipé d'une pompe à development support Selection Implementation motricité humaine au marché de Lenouk, dans la Commune de Monatélé, Région du Centre
019/C/SC/CE/OMBESSA / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'une mini AEP Component A: Local Individual Consultant Pending IDA / 57180 Post Open 960.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 avec forage productif et development support Selection Implementation construction d'un château à Ombessa, dans la Commune d'Ombessa Région du Centre
020/C/SC/CE/OLANGUINA/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction dun (01) hangar de 32 comptoirs au marché de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,762.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 Koltock et rehabilitation du development support Selection Implementation marché d'Olanguina (10 boutiques) et Construction de (02) bloc latrines à trois (03) comp
Page 17 021/C/SC/CE/OLANGUINA/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un (01) forage Component A: Local Individual Consultant Pending IDA / 57180 Post Open 680.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 productif équipé d'une pompe à development support Selection Implementation motricité humaine au marche de Koltock dans la Commune d'Olanguina, Région du Centre
022/C/SC/CE/YAOUNDE 7/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un magasin de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 stockage avec un bloc latrines à development support Selection Implementation deux (02) Compartiments à Minkoameyos dans la commune de Yaoundé 7, Région du Centre
023/C/SC/CE/YAOUNDE 7/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de rehabilitation d'un pont definitif de 06m de portee et 04m de large Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,079.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 sur la riviere Angaha et de development support Selection Implementation réhabilitation d'une piste agricole de 400m allant du carrefour nkolnkoumou au Centre de Promot
024/C/SC/CE/MENGUEME/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de deux (02) puits Component A: Local Individual Consultant Pending équipés de Pompes à Motricité IDA / 57180 Post Open 960.00 0.00 2017-04-23 2017-06-02 2017-06-09 2017-07-01 2017-10-29 development support Selection Implementation Humaine dans deux (02) localités (Yeneassi et Mebemezoa) dans la commune de Mengueme, Région du Centre
025/C/SC/CE/MENGUEME/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Réhabilitation des points Component A: Local Individual Consultant Pending IDA / 57180 Post Open 5,060.00 0.00 2017-04-24 2017-06-03 2017-06-17 2017-07-16 2017-11-13 critiques sur la piste agricole development support Selection Implementation
Nemeyong-benebelot dans la commune de Mengueme, Région du Centre
026/C/SC/CE/MFOU/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un forage productif Component A: Local Individual Consultant Pending IDA / 57180 Post Open 680.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 équipés d'une Pompe à Motricité development support Selection Implementation
Humaine dans la localité de Nkongoa dans la Commune de Mfou, Région du Centre
027/C/SC/CE/MENGANG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de réalisation d'électrification rurale Component A: Local Individual Consultant Pending dans certaines localités, en 02 IDA / 57180 Post Open 4,348.00 0.00 2017-04-24 2017-06-03 2017-06-10 2017-07-02 2017-10-30 development support Selection Implementation axes : lycée de Mengang-Meyo- Evoung et lycée de Menoa- Ekinguili-Bifembe, Commune de Mengang, Région du Centre
028/C/SC/CE/MAKAK/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un (01) hangar de Component A: Local Individual Consultant Pending 48 comptoirs avec un (01) bloc IDA / 57180 Post Open 2,393.00 0.00 2017-04-24 2017-06-03 2017-06-10 2017-07-02 2017-10-30 development support Selection Implementation latrines à trois (03) compartiments au marché de Makak centre, dans la Commune de Makak, Région du Centre
029/C/SC/CE/MAKAK/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un magasin de Component A: Local Individual Consultant Pending stockage avec un bloc latrines à IDA / 57180 Post Open 2,000.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 development support Selection Implementation deux (02) compartiments dans la localités de Mbeng dans la Commune de Makak, Région du Centre
030/C/SC/CE/MAKAK/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un (01) puits Component A: Local Individual Consultant Pending IDA / 57180 Post Open 480.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 équipé de Pompe à Motricité development support Selection Implementation
Humaine au marché de Makak Centre, dans la Commune de Makak, Région du Centre
031/C/SC/CE/DIBANG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Component A: Local Individual Consultant Pending realisation d'une electrification IDA / 57180 Post Open 2,304.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 development support Selection Implementation rurale de 2700m dans le village Tamalong, Commune de Dibang, Région du Centre
032/C/SC/CE/DIBANG/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un magasin de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 stockage avec un bloc latrines à development support Selection Implementation deux (02) compartiments à Ndongo dans la Commune de Dibang, Région du Centre
033/C/SC/CE/BOT MAKAK/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de deux (02) forages productifs Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,192.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 équipés de pompes à motricité development support Selection Implementation humaine au CETIC et Centre Administratif de Bot-Makak, dans la Commune de Bot Makak, Région du Centre
034/C/SC/CE/BOT MAKAK/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un Component A: Local Individual Consultant Pending IDA / 57180 Post Open 480.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 (01) puits équipés de pompes à development support Selection Implementation motricité humaine à Ndjock Bané, dans la Commune de Bot Makak, Région du Centre
035/C/SC/CE/NTUI/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de deux (02) magasins de stockage de cacao Component A: Local Individual Consultant Pending IDA / 57180 Post Open 5,030.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 et construction de 02 blocs development support Selection Implementation latrines à deux (02) compartiments dans les localités de Nguila, et Ntui ville) dans la Commune de Ntui,
036/C/SC/CE/NANGA EBOKO/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de construction d'un bloc de 03 salles de classe Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 équipées et construction d'un development support Selection Implementation bloc de trois latrines à l'EP de Ndjombe dans la commune de Nanga et Eboko, Région du Centre
037/C/SC/CE/MINTA/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Component A: Local Individual Consultant Pending construction d'un puits équipé de IDA / 57180 Post Open 480.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 development support Selection Implementation PMH à l'EP de Ndjombe, dans la commune de Minta, Région du Centre
038/C/SC/CE/NANGA EBOKO/2017 / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction de deux (02) hangars avec Component A: Local Individual Consultant Pending comptoirs et Construction de IDA / 57180 Post Open 4,190.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 development support Selection Implementation deux (02) blocs de latrines à trois (03) compartiments dans 02 marchés à Essimeyong et à Biboa dans la commune de Nanga et
039/C/SC/CE/NAGA EBOKO / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de réhabilitation de deux (02) puits équipés de Pompe à Motricité Component A: Local Individual Consultant Pending IDA / 57180 Post Open 480.00 0.00 2017-04-25 2017-06-04 2017-06-11 2017-07-03 2017-10-31 Humaine au marché de development support Selection Implementation
Essimeyong et au marché de Biboa, dans la Commune de Nanga et Eboko, Région du Centre
CM-PNDP-2840-CS-INDV / Sélection d'un consultant pour l'étude sur la définition d'une Component B: Support to the Individual Consultant Pending méthodologie de planification au IDA / 57180 Post Limited 30,000.00 0.00 2017-03-05 2017-03-10 2017-03-31 2017-05-05 2017-11-01 decentralization process Selection Implementation niveau des communes d'arrondissement et au niveau régional
CM-PNDP-11826-CS-INDV / Component C: Coordination, Traduction des documents et Individual Consultant Pending IDA / 57180 management, monitoring and Post Open 20,000.00 0.00 2017-09-03 2017-10-22 2017-11-12 2017-12-17 2018-06-15 autres supports du PNDP (année Selection Implementation evaluation and communication 2017)
CM-PNDP-11851-CS-INDV / Recrutement d'un consultant chargé d'accompagner le Component B: Support to the Individual Consultant Pending technique pour la proposition d'un IDA / 57180 Post Open 30,000.00 0.00 2017-04-05 2017-05-24 2017-06-14 2017-07-19 2018-01-15 decentralization process Selection Implementation dispositif d'entretien et de maintenance des ouvrages dans le cadre du PNDP
001/C/EF/NGUTI/CRC/2017 / Sélection d'un consultant pour l'élaboration d'une étude de faisabilité technique et environnementale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 4,000.00 0.00 2017-04-08 2017-04-13 2017-05-04 2017-06-08 2017-12-05 construction d'une case de development support Selection Implementation passage à Nguti, et la construction de dix boutiques, un bloc latrine à la gare routière de Manyemen, commune de Ngut
002/C/EF/NGUTI/CRC/2017 / Sélection d'un consultant pour l'élaboration d'une étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending IDA / 57180 Post Limited 4,000.00 0.00 2017-04-08 2017-04-13 2017-05-04 2017-06-08 2017-12-05 l'approvisionnement en eau de la development support Selection Implementation case de passage et la gare routière de Manyemen, communes de Nguti, Région du Sud Ouest
001/C/EF/TINTO/CRC/2017 / étude de faisabilité pour les travaux de construction d'un marché et un bloc latrine à Component A: Local Individual Consultant Pending Fumbe, la construction et IDA / 57180 Post Limited 4,000.00 0.00 2017-04-08 2017-04-13 2017-05-04 2017-06-08 2017-12-05 development support Selection Implementation l'équipement d'un bloc de deux salles de classe, la construction d'un bloc latrine à l'EP de SABES, commune de Tinto
002/C/EF/TINTO/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending l'approvisionnement en eau du IDA / 57180 Post Open 4,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation marché de Fumbe et l'EP de SABES, commune de Tinto, Région du Sud Ouest
001/C/EF/WABANE/CRC/2017 / étude de faisabilité technique et environnementale pour les travaux de construction des Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 boutiques, d'un hangar et un bloc development support Selection Implementation latrine à Mbecho, construction d'une case de passage à Bechati- Wabane, commune de Wabane
002/C/EF/WABANE/CRC/2017 / étude de faisabilité technique et environnementale pour les Component A: Local Individual Consultant Pending travaux de construction d'un IDA / 57180 Post Open 2,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation ouvrage de franchissement sur la rivière Meghop dans le village Folepi, commune de Wabane
003/C/EF/WABANE/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending l'approvisionnement en eau du IDA / 57180 Post Open 3,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation marché de Mbecho et la case de passage de Bechati dans la commune de Wabane
001/C/EF/BUEA/CRC/2017 / étude de faisabilité technique et environnementale pour la construction de dix hangars, un Component A: Local Individual Consultant Pending IDA / 57180 Post Open 5,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 bloc latrine au marché de development support Selection Implementation
Wotutu, cinq hangars et un bloc latrine au marché de Muea, commune de Buea
002/C/EF/BUEA/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 l'approvisionnement en eau des development support Selection Implementation marchés de Wotutu et Muea, commune de Buea
001/C/EF/MAMFE/CRC/2017 / étude de faisabilité technique et Component A: Local Individual Consultant Pending environnementale pour la IDA / 57180 Post Open 2,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation construction d'un hangar et un bloc latrine au marché de Mamfe
002/C/EF/MAMFE/CRC/2017 / étude de faisabilité technique et environnementale pour l'approvisionnement en eau du Component A: Local Individual Consultant Pending marché de Mamfe, la IDA / 57180 Post Open 6,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation réhabilitation du réseau d'AEP de Nfaitock et la réalisation d'un forage à Eyang Ntui, commune de Mamfe,
001/C/EF/ALOU/CRC/2017 / étude de faisabilité technique et environnementale pour les travaux de construction et Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,500.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 équipement des écoles development support Selection Implementation maternelles de Fonjumetaw et Mendia-M'mockmbie, commune d'Alou
002/C/EF/ALOU/CRC/2017 / étude de faisabilité technique et environnementale pour les travaux de réhabilitation de 12km Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 de routes rurales de Atulah à development support Selection Implementation
Menky, ouverture de la route rurale de Akung-Njenawung à la limite avec Wabane
003/C/EF/ALOU/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending l'approvisionnement en eau des IDA / 57180 Post Open 2,500.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation écoles maternelles de Fonjumetaw et Mendia- M'mockmbie, commune d'Alou,
001/C/EF/EYUMOJOCK/CRC/20 17 / étude de faisabilité technique et environnementale pour construction et l'équipement Component A: Local Individual Consultant Pending d'un bloc de deux salles de IDA / 57180 Post Open 4,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation classe, un bloc latrine dans les EP de Onaku, Bayenti et Ayukaba, construction d'un magasin de stockage à Ekok
002/C/EF/EYUMOJOCK/CRC/20 17 / étude de faisabilité pour l'approvisionnement en eau des écoles publiques de Onaku, Bayenti et Ayukaba, le site de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,009.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 construction du magasin de development support Selection Implementation stocage d'Ekok, réalisation de deux forages positifs équipés de pompes à motricité humaine à Agborkem et Ayaoke
Page 18 001/C/EF/TIKO/CRC/2017 / étude de faisabilité technique et Component A: Local Individual Consultant Pending environnementale pour IDA / 57180 Post Open 1,400.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation l'électrification du village Ombe Native, commune deTiko
002/C/EF/TIKO/CRC/2017 / étude de faisabilité technique et environnementale pour la construction d'un Centre de Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,600.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 Santé Intégré à Mondoni Native, development support Selection Implementation une case de passage et un restaurant municipal à Tiko, commune de Tiko
003/C/EF/TIKO/CRC/2017 / étude de faisabilité technique et environnementale pour l'approvisionnement en eau du Component A: Local Individual Consultant Pending IDA / 57180 Post Open 810.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 site de construction du CSI de development support Selection Implementation
Mondoni Native, la case de passage et le restaurant municipal de Tiko
001/C/EF/MUYUKA/CRC/2017 / étude de faisabilité technique et environnementale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 construction de l'Ecole development support Selection Implementation
Maternelle de Bafia, les marchés de Malende et Munyenge
002/C/EF/MUYUKA/CRC/2017 / étude de faisabilité technique et environnementale pour l'approvisionnement en eau des Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 site de constructrion de l'Ecole development support Selection Implementation
Maternelle de Bafia, les marchés de Malende et Munyenge, commune de Muyuka
001/C/EF/IDENAU/CRC/2017 / étude de faisabilité technique et environnementale pour la Component A: Local Individual Consultant Pending construction et l'équpiement d'un IDA / 57180 Post Open 4,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation foyer communautaire à Bakingili et une librairie à Idenau commune d'Idenau
002/C/EF/IDENAU/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending l'approvisionnement en eau du IDA / 57180 Post Open 4,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation site du foyer communautaire de Bakingili et de la librairie municipale d'Idenau
001/C/EF/MENJI/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending l'approvisionnement en eau du IDA / 57180 Post Open 2,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation site du foyer communautaire de Mbeuh dans la commune de Menji
002/C/EF/MENJI/CRC/2017 / étude de faisabilité technique et environnementale en vue des Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 travaux de construction des development support Selection Implementation boutiques et un bloc latrine au marché de Menji
001/C/EF/BAMUSSO/CRC/2017 / étude de faisabilité technique et environnementale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 construction d'une case de development support Selection Implementation passage à Bamusso commune de Bamusso
002/C/EF/BAMUSSO/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 l'approvisionnement en eau du development support Selection Implementation site de la case de passage de Bamusso,
003/C/EFBAMUSSO/CRC/2017 / étude de faisabilité technique et environnementale pourla Component A: Local Individual Consultant Pending construction d'un ouvrage de IDA / 57180 Post Open 2,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation franchissement à l'entrée de la case de passage d'Iloini, commune de Bamusso
001/C/EF/MUNDEMBA/CRC/201 7 / étude de faisabilité technique et environnementale pour la Component A: Local Individual Consultant Pending construction et l'équipement d'un IDA / 57180 Post Open 4,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation foyer communautire et une école maternelle à Mundemba, commune de Mundemba
002/C/EF/MUNDEMBA/CRC/201 7 / étude de faisabilité technique et environnementale pour l'approvisionnement en eau du Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 site de construction de la case development support Selection Implementation de passage et l'école maternelle de Mundemba, commune de Mundemba
001/C/EF/KONYE/CRC/2017 / étude de faisabilité technique et environnementale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 3,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 construction et l'équipement du development support Selection Implementation
Centre de Santé Intégré de Matondo II, commune de Konye
002/C/EF/KONYE/CRC/2017 / étude de faisabilité technique et environnementale pour l'approvisionnement en eau du Component A: Local Individual Consultant Pending IDA / 57180 Post Open 5,000.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 site de construction du Centre de development support Selection Implementation
Santé Intégré de Matondo II, l'alimentation en eau potable des villages Matoh et Koba
001/C/EF/TOMBEL/CRC/2017 / étude de faisabilité pour la construction et l'équipement de l'école maternelle d'Ebonji, d'un bloc de deux salles de classe Component A: Local Individual Consultant Pending IDA / 57180 Post Open 5,500.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 dans les Ecoles primaires de development support Selection Implementation
Mbabe et Ngab, d'un hanga au marché d'Ebonji, des bloc latrines dans les EP de Mbabe et Ngab
002/C/EF/TOMBEL/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending l'approvisionnement en eau des IDA / 57180 Post Open 2,500.00 0.00 2017-04-08 2017-05-27 2017-06-17 2017-07-22 2018-01-18 development support Selection Implementation Ecoles d'Ebonji, Mbabe et Ngab ainsi que le marché d'Ebonji, commune de Tombel,
001/C/EF/EKONDO TITI/CRC/2017 / étude de faisabilité technique et environnementale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,600.00 0.00 2017-05-16 2017-07-04 2017-07-25 2017-08-29 2018-02-25 construction et l'équipement des development support Selection Implementation
écoles maternelles de Iribanyange et Kumbe Balue, commune d'Ekondo Titi,
002/C/EF/EKONDO TITI/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending l'approvisionnement en eau des IDA / 57180 Post Open 1,600.00 0.00 2017-05-16 2017-07-04 2017-07-25 2017-08-29 2018-02-25 development support Selection Implementation sites de construction des écoles maternelles d'Iribanyange et Kumbe Balue, commune d'Ekondo Titi,
001/C/EF/KOMBO ITINDI/CRC/2017 / étude de faisabilité technique et environnementale pour la construction des logements Component A: Local Individual Consultant Pending IDA / 57180 Post Open 6,000.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-19 d'astreinte pour enseignants, d'un development support Selection Implementation block latrine et aménagement d'un passage piéton à Gold Coast, commune de Kombo Itindi,
001/C/EF/IDABATO/CRC/2017 / étude de faisabilité technique et environnementale pour la construction d'un marché et un Component A: Local Individual Consultant Pending bloc latrine à Kombo Amunja, IDA / 57180 Post Open 6,000.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-19 development support Selection Implementation construction de cinq bloc latrines à Shell Creek, Idabato II, Jabane et Kombo Amunja, commune d'Idabato
001/C/EF/KOMBO ABEDIMO/CRC/2017 / étude de faisabilité technique et environnementale pour la réhabilitation de l'Ecole Publique Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,000.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-19 bilingue et l'hôpital de district development support Selection Implementation d'Akwa, la consruction d'un magasin de stockage et un bloc latrine à Akwa Beach, commune de Kombo Abedimo
002/C/EF/KOMBO ABEDIMO/CRC/2017 / étude de faisabilité technique et environnementale pour Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,000.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-19 l'approvisionnement en eau du development support Selection Implementation site de construction du magasin de stockage d'Akwa, commune de Kombo Abedimo
001/C/EF/ISANGELE/CRC/2017 / étude de faisabilité technique et environnementale pour la Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,600.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-19 construction des logements development support Selection Implementation d'astreinte des enseignants à Isangele , commune d'Isangele
002/C/EF/ISANGELE/CRC/2017 / étude de faisabilité technique et environnementale pour l'approvisionnement en eau Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,400.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-19 potable du site de construction development support Selection Implementation des logements d'astreinte des enseignants à Isangele , commune d'Isangele
001/C/SC/BAMUSSO/CRC/2017 / Suivi/contrôle des Travaux de construction d'un magasin de Component A: Local Individual Consultant Pending stockage et d'un bloc latrine à IDA / 57180 Post Open 2,199.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 development support Selection Implementation trois compartiments à Bekery Beach dans la Commune de Bamusso
001/C/SC/MUYUKA/CRC/2017 / Suivi/contrôle des Travaux de construction des hangars au Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,542.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 marché de Yoke dans la development support Selection Implementation
Commune de Muyuka, Région du Sud-Ouest
001/C/SC/EKONDO TITI/CRC/2017 / Suivi/contrôle des Travaux de Construction et Component A: Local Individual Consultant Pending d'équipement en mobilier de IDA / 57180 Post Open 2,201.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 development support Selection Implementation l'Ecole Maternelle de Funge dans la Commune d'Ekondo Titi, Région du Sud-Ouest
002/C/SC/EKONDO TITI/CRC/2017 / Suivi/contrôle des Travaux de réalisation d'un forage productif équipé d'une Component A: Local Individual Consultant Pending IDA / 57180 Post Open 1,106.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 pompeà energie solaire à l'Ecole development support Selection Implementation
Maternelle de Fonge dans la Commune d'Ekondo Titi, Région du Sud-Ouest
001/C/SC/MENJI/CRC/2017 / Suivi/contrôle des Travaux de construction et d'équipement en Component A: Local Individual Consultant Pending mobilier d'un foyer IDA / 57180 Post Open 2,400.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 development support Selection Implementation communautaire dans le village Mbeuh de la Commune de Menji, dans la Région du Sud-Ouest
001/C/SC/MUNDEMBA/CRC/201 7 / Suivi/contrôle des Travaux de réalisation de trois (03) forages productifs équipés de pompes à Component A: Local Individual Consultant Pending motricité humaine dans les trois IDA / 57180 Post Open 2,383.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 development support Selection Implementation (03) écoles publiques de Ndian Estate, Fabe et Besingi, dans la Commune de Ndian, Région du Sud-Ouest
001/C/SC/TOMBEL/CRC/2017 / Suivi/contrôle des Travaux de construction d'un marché, un bloc latrine à trois (03) Component A: Local Individual Consultant Pending IDA / 57180 Post Open 2,902.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 Compartiments et une borne development support Selection Implementation fontaine à Tombel, dans la Commune de Tombel, Région du Sud-Ouest
001/C/SC/MBONGE/CRC/2017 / Suivi/contrôle des Travaux de réalisation de deux (02) forages productifs équipés de pompes à Component A: Local Individual Consultant Pending motricité humaine dans les IDA / 57180 Post Open 1,365.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 development support Selection Implementation écoles publiques de Marumba et Kotto Barumbi dans la Commune de Mbonge, Région du Sud- Ouest
001/C/CC/LIMBE II/CEC/2017 / Recrutement d'un agent financier Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,320.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 pour la commune de Limbe II, development support Selection Implementation
Région du Sud-Ouest
002/C/CC/LIMBE II/CEC/2017 / Recrutement d'un agent de Component A: Local Individual Consultant Pending développment pour la commune IDA / 57180 Post Open 5,400.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 development support Selection Implementation de Limbe II, Région du Sud- Ouest
001/C/CC/LIMBE III/CEC/2017 / Recrutement d'un agent financier Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,320.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 pour la commune de Limbe III, development support Selection Implementation
Région du Sud-Ouest
002/C/CC/LIMBE III/CEC/2017 / Recrutement d'un agent de Component A: Local Individual Consultant Pending développment pour la commune IDA / 57180 Post Open 5,400.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 development support Selection Implementation de Limbe III, Région du Sud- Ouest
001/C/CC/KUMBA I/CEC/2017 / Recrutement d'un agent financier Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,230.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 pour la commune de Kumba I, development support Selection Implementation
Région du Sud-Ouest
002/C/CC/KUMBA I/CEC/2017 / Recrutement d'un agent de Component A: Local Individual Consultant Pending développment pour la commune IDA / 57180 Post Open 5,400.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 development support Selection Implementation de Kumba I, Région du Sud- Ouest
001/C/CC/KUMBA II/CRC/2017 / Recrutement d'un agent financier Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,320.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 pour la commune de Kumba II, development support Selection Implementation
Région du Sud-Ouest
002/C/CC/KUMBA II/CEC/2017 / Recrutement d'un agent de Component A: Local Individual Consultant Pending développment pour la commune IDA / 57180 Post Open 5,400.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 development support Selection Implementation de Kumba II, Région du Sud- Ouest
001/C/CC/KUMBA III/CRC/2017 / Recrutement d'un agent Component A: Local Individual Consultant Pending IDA / 57180 Post Open 4,320.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 financier pour la commune de development support Selection Implementation
Kumba III, Région du Sud-Ouest
002/C/CC/KUMBA III/CRC/2017 / Recrutement d'un agent de Component A: Local Individual Consultant Pending développment pour la commune IDA / 57180 Post Open 5,400.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 development support Selection Implementation de Kumba III, Région du Sud- Ouest
Page 19