<<

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

O:\41082-000\WPDOCS\TECH-MEMO\TM1

GUAYAQUIL WASTEWATER THE ENVIRONMENTAL AND SO EXECUTIVE SUMMARY OF March 15, 2015

MANAGEMENT PROJECT

CIAL ASSESCIAL

S MENT

(P151439)

Introduction

The proposed Ecuador Wastewater Management Project (“the Project”) involves four main components as follows: 1) Installation of Household Connections; 2) Rehabilitation of Sewerage Network; 3) Wastewater Treatment Plant and Disposal Facilities; and 4) Project management and administration, including communication plan and management of social, environmental, and safety issues. These components are described in more detail below.

The overall Project impact is expected to be positive due to the improved effluent quality that will be discharged into the Guayas and the reduction of untreated wastewater that is presently leaking from the existing sewer system and affecting shallow ground and surrounding surface water bodies, like the "Salado" Estuary.

The proposed Project has been classified by the World Bank, per OP/BP 4.01, as an Environmental Category A due to the type and size of the Project Component Three, the construction of the WWTP. This Component requires the expropriation of a 40.74ha area which is host to one resident, a radio antenna and a shrimp production facility. Because expropriation has been taking place prior to World Bank engagement a Remedial Resettlement Action Plan has been prepared, which when implemented, will ensure the expropriation process is in conformity with the World Bank’s policy on involuntary resettlement. Related to Component Three, an Environmental and Social Impact Assessment (ESIA) has been developed by an international consulting firm1 with the support of a local environmental consulting firm2, under supervision of the Empresa Municipal de Agua Potable y Alcantarillado de Guayaquil (EMAPAG EP). The remaining sections of this document present an executive summary of the March 2015 ESIA for Component Three prepared by the mentioned consulting firms.

Project financed works in Component Two have relatively moderate potential negative environmental impacts and can be readily mitigated with standard measures, and even less impacts are associated with works in Component One. For Components One and Two, an Environmental and Social Management Plan (ESMP) was developed for each component and includes an assessment of potential impacts and proposed mitigation and monitoring measures. Component One will finance the installation and rehabilitation of household connections in specific areas of the City of Guayaquil, where household toilets discharge directly to the estuary or to reportedly poorly constructed and maintained pits or septic tanks, which contributes to the degradation of the Estero Salado. The works involve establishing a connection from an existing sewer line on the street to a house, and the potential environmental impacts are relatively minor. Component Two involves the rehabilitation of the sewerage network in “La Chala” basin and will improve sewer efficiency by reducing infiltrations and contribute to the reduction of the contamination of the Salado estuary from domestic wastewater. The works should have relatively minor to moderate potential negative environmental impacts during construction (for example, generation of noise and dust, minor traffic disruption, disposal of waste) and can be readily mitigated with standard measures established in the ESMP. Even less impacts are associated with works in Component One. The ESMPs include a “chance finds” procedure and natural habitat protection measures to be used if needed given the proximity to the works and the Guayas River and the Salado Estuary. The draft ESMPs for Components One and Two were disclosed and consulted in January 2015, and

1 Hazen and Sawyer P.C. 2 Consultambiente Cía. Ltda. revised ESMPs have been prepared by EMAPAG EP and disclosed on February 27, 2015.

Project Components

1. Component One: Installation of household connections (US$18 million, with US$2.8 million of IBRD loan financing). This Component will finance the installation and rehabilitation of household connections in specific areas within the southern districts of the City of Guayaquil.3 These districts are equipped with a dense sewerage collection network which, although requiring rehabilitation of main collectors to reduce infiltration, reaches and could serve almost all inhabited areas. Nonetheless, despite a broad network coverage, just 82 percent of the households in the area are currently actually connected to the system. Most of the remaining 18 percent (around 30,000 families) are poor households located in Suburbio Oeste, Isla Trinitaria, Sector Guasmo and Casco Central sectors, which are riparian areas of the Estero Salado estuary, where household toilets discharge directly to the estuary or to reportedly poorly constructed and maintained pits or septic tanks, which contributes to the degradation of the Estero Salado.4 Although many houses have a sewer passing in front, these households have not been connected—despite a legal mandate to do so—mainly because of the cost of the connection fee.5 Under the Project, household connection costs—including the cost of required indoor works like piping, flooring, and others—will be partially subsidized and financed by EMAPAG EP (clients will pay EMAPAG EP the nonsubsidised segment in installments through the water bill). In parallel, a communication campaign will be launched to inform the beneficiaries about the initiative and its benefits and to promote improved hygiene and maintenance practices required to ensure the proper functioning of the condominial sewer system. The design of this Component has been developed based on previous successful experiences with connection campaigns led by EMAPAG EP, which managed to increase effective access to piped sanitation up to 98 percent in other districts of the city with high poverty rates.6

2. Component Two: Rehabilitation of sewerage network (US$37 million, 100 percent financed by IBRD). This Component will finance the rehabilitation of the sewerage network (including sections of the primary, secondary and tertiary network) in La Chala basin (Suburbio Oeste area), which, as stated above, is riparian to the Estero Salado estuary. The main collectors in this area have been identified to require urgent rehabilitation to reduce wastewater losses and enable their effective collection function. This Component of the Project aims at reducing

3 With regard to the potential minor expansion of the secondary and tertiary networks which might be required in specific neighborhoods within the area to enable the installation of household connections, EMAPAG EP has agreed to include these within Interagua’s annual network expansion targets. This will require coordinated planning with Interagua based on a plan for the connection of the different neighborhoods, which is already under preparation by EMAPAG. 4 To address the problem of domestic discharge coming from neighborhoods which are riparian to the estuary on the northern side, there are three ongoing projects managed by EMAPAG EP to connect around 25,000 households to the sewerage network currently under implementation. These projects, which combined the household connection component financed by the proposed project and the Guayaquil Ecológico program jointly financed by the GoE and the municipality of Guayaquil, are jointly expected to completely eliminate domestic discharge to the estuary. 5 This cost is US$500 and includes the cost of emptying and sealing of the septic tank or other on-site sanitation solution. 6 Once home owners in a specific neighborhood have agreed to be connected to the sewerage network, a contractor hired by EMAPAG EP will carry out the installation in close coordination and consultation with each home owner. Once the work is finished, the home owner will sign a certificate that they are satisfied with the works constructed and acknowledge their connection to the service. infiltrations in the south sewerage subsystem, thus contributing to reduction in the contamination of the Estero Salado estuary from domestic wastewater. It is estimated that of the total volume of wastewater collected and pumped in the pumping station of La Chala, approximately 25 percent corresponds to ground water infiltration,7 which also increases wastewater pumping and treatment costs. Also, some segments of the Suburbio Oeste sewer network that are meant to function as gravity mains get pressurized during periods of high tide, which again suggests a high infiltration rate.

3. Component Three: Wastewater treatment and disposal facilities (US$161 million, with US$58.5 million of IBRD loan financing). This Component will finance the construction of a new WWTP, called Las Esclusas WWTP, and associated pumping and transmission facilities to treat 100 percent of the wastewater collected in the southern districts of the city of Guayaquil within the design year of 2045. Wastewater generated in the south subsystem is currently collected in two sewer mains: (a) the Guasmo sewer main, which conducts an average flow in dry weather of 0.60 m3/s into the Guasmo H pumping station from where wastewater is pumped directly into the Guayas River through a 180 m long pipeline and an underwater outfall diffuser, and (b) the Parson’s Sur sewer main, which conducts 2.10 m3/s in dry weather into the La Pradera pre-treatment station (equipped with a mechanized pre-treatment, a disinfection system that is presently out of service and a underwater outfall diffuser). Therefore, wastewater is currently discharged into the Guayas River with very little or no treatment, failing to comply with the contaminants concentration thresholds established in the National Norm on Environmental Quality and Effluent Discharges (NCADE in its Spanish acronym).8 To address this situation, EMAPAG EP will construct, through this Project, a new WWTP, Las Esclusas WWTP, near the current point of discharge of the Guasmo sewer main, which will treat all the sewerage collected in the south subsystem.

4. Different technological alternatives for the wastewater treatment were analyzed by EMAPAG EP before the Bank’s involvement to develop the design of the treatment facility and these were discussed with the Bank during preparation. The Chemically Enhanced Primary Treatment (CEPT) option was retained after an alternative analysis was conducted since it will allow the municipality of Guayaquil to consistently meet the national regulatory authorized limits set for the Total Suspended Solids (TSS) below 100 percent and BOD below 100 percent and all other pollutant concentrations. CEPT is also considered a flexible technology which can easily be adapted to changes in influent operating characteristics or potential future stricter standards. The feasibility study commissioned by EMAPAG EP included a thorough analysis of 19 secondary treatment process alternatives, including aerobic and anaerobic processes,9 and there is sufficient area and several options to install secondary treatment in the future.

7 The storm drainage and sewerage systems are separate systems but there is infiltration of rainwater into the sewerage system due to the poor conditions of the network.

8 The NCADE sets the maximum limits for effluent quality standard at: BOD5 = 100 mg/L; SST = 100 mg/L; Total coliform =100 NMP/100 ml. The effluent discharged at Guasmo H does not comply with these limits as BOD and TSS concentration in the raw wastewater is very high. The effluent discharged at La Pradera does comply with the NCADE most of the time, given the high dilution of the water that arrives into the facility due to ground water infiltration into the sewerage system.

9 The secondary treatment alternatives analyzed had 19 processes, including aerobic and anaerobic solutions. The trickling filters process was selected as the most cost-effective and preferred option for secondary treatment. 5. Component 4: Project management and administration, including communication plan and management of social, environmental, and safety issues (US$5.4 million with US$4.2 million of IBRD loan financing). This Component will finance activities associated with overall project management by EMAPAG EP, including Project-related audits, monitoring and evaluation, equipment and training to strengthen the implementing entity, as well as individual consultants. It will also include support to EMAPAG EP related to the planning and management of environmental and social issues and safeguards. Specifically, this Component will fund: (a) a study to set up a system for the physiochemical, bacteriological, and limnologic monitoring of the Guayas River water quality;10 (b) a study to set up a system for the physical-chemical, bacteriological, and limnologic monitoring of the Estero Salado estuary water quality in relation with Project Components One and Two; (c) a master plan for the management and final disposal or reuse of the bio-solids which will be produced at the Las Esclusas WWTP and other planned WWTPs (Los Merinos, Asuncion City, and others); (d) communication campaigns and technical assistance for community development and training; (e) a Project Impact Evaluation (IE); and (f) an integrated urban water management study for the planning of development and infrastructure in a growing flood-prone area of the city of Guayaquil (Sistema Tres) which requires interventions in urban drainage and wastewater management.

10 The scope of this study is to be defined during project preparation and the objective is to enable monitoring of the Guayas River water quality at different points, which in turn will enable measuring of the benefits of the Las Esclusas WWTP and other future treatment plants on the water quality of the Guayas River. IMPACT ASSESSMENT ESCLUSASLAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1

Las EsclusasLas Waste Water Treatment MENTAL AND SOCIAL E nviro Hazen and sawyer, andP.C. C nm

ental ental and Social Impact Assessment Executive Summary March 2015

onsultambiente

HAZEN AND SAWYER, P. Plan ProjectPlan

C . | CONSULAMBIENTE

PAGE PAGE 1

EIA Executive Summary March 2015

Table of Contents 1. Project Background ...... 1 2. ESIA Objectives ...... 1 3. Background on Guayaquil’s Wastewater Management ...... 2 3.1 Sanitary Sewer Collection System 2 3.2 Treatment System 3 4. Project Description ...... 5 4.1 Main Components and Location 5 4.2 Dimensions and Characteristics of the Project 7 4.2.1 Pradera Pumping Station 7 4.2.2 Pradera - Las Esclusas WWTP Force main / Guasmo-Las Esclusas WWTP Force Main 8 4.2.3 Las Esclusas Treatment Plant: Analysis of Alternatives 9 5. Institutional and Legal Framework...... 13 5.1 Institutional Framework 13 5.2 Environmental Competent Authority 13 5.3 Ecuador Environmental Regulations 14 5.4 World Bank Polices 15 6. Environmental and Social Baseline ...... 15 6.1 General Environment 15 6.2 Physical Environment 16 6.3 Biotic Environment 20 6.4 Socioeconomic and cultural environment 22 7. Environmental and Social Impact...... 24 7.1 Identification and Assessment of Impacts 24 7.2 Description of Primary Project Phases 24 7.3 Environmental and Social Factors Considered in the Assessment 29 7.4 Assessment and categorization of impacts 30 7.5 Results of the Environment and Social Impact Assessment 30 7.6 Expected Project Benefits 33 EIA Executive Summary March 2015

8. Environmental and Social Management Plan (ESMP) ...... 36 8.1 ESMP Components 36 8.2 Measures of ESMP 37 8.3 ESMP Budget 42 9. The Project and Climate Change ...... 42 10. Social Participation ...... 42 10.1 Public Information Centers 43 10.2 Public Hearing and Information Meetings 46 10.3 Grievance Redress 469 11. Conclusions and Recommendations ...... 49

Tables Table 1. Boundaries of the Project Area ...... 7 Table 2. Characteristics of Pumping Stations ...... 8 Table 3. Characteristics of Force Main ...... 9 Table 4. Decision Criteria and Relative Weight Used to Select the Optimal Alternative ...... 10 Table 5. Characteristics of Las Esclusas WWTP ...... 11 Table 6. Environmental and Social Measures Proposed ...... 38 Table 7. Mechanism Applied in PPS ...... 43 Table 8. Participation Statistics at PIC ...... 44 Table 9. Number of Comments Recorded at PIC ...... 45 Table 10. Measures to Be Included in the EIA as a Result of PPS ...... 45 Table 11. Observations Obtained at Public Hearing ...... 47 Table 12. Observations Obtained at Information Meeting - Pradera ...... 48

Table 13. Observations Obtained at Information Meeting - Pablo Neruda ...... 48

Figures Figure 1. Sanitation Subsystems of Guayaquil ...... 4 Figure 2. Main Components and Location of South Subsystem ...... 5 Figure 3. Geographical Location of Las Esclusas WWTP ...... 7 EIA Executive Summary March 2015

Figure 4: Proposed Treatment Process for “Las Esclusas” WWTP ...... 12 Figure 5. Location of the Project...... 16 Figure 6. Lots affected by the WWTP ...... 33 Figure 7. Programs of Environmental Management Plan for Las Esclusas WWTP ...... 36 Figure 8. Location of Public Information Centers ...... 44 Figure 9. Number of Attendees of Public Hearing and Information Meetings ...... 47

Abbreviations and Acronyms

CEPT Chemically Assisted Primary Treatment (Tratamiento Primario Químicamente Asistido)

EIA Estudio de impacto ambiental (Environmental Impact Assessment)

EMAPAG EP Empresa Municipal de Agua Potable y Alcantarillado de Guayaquil

LBA Línea Base Ambiental (Environmental Foundation Baseline)

MAE Ministerio del Ambiente del Ecuador (Ministry of Environment of Ecuador)

MG Militamices Giratorios (Rotary Miliscreens)

PIC Public Information Centers (Centros de Información Pública)

PMA Plan de Manejo Ambiental (Environmental Management Plan)

SUMA Sistema Único de Manejo Ambiental (Unique Environmental Management System

MAE Ministerio del Ambiente (Ministry of Environment)

O:\41082-000\WPDOCS\TECH-MEMO\TM1 LASESCLUSAS ENVIRON I The followingare specific objectives E the ofthe policies. and design will project’s the ensure will Assessment impacts negative and to propose an Environmental Management Plan including measures needed to mitigate the objective The 2. outfall underwater system, disinfection diffuser production; of andconstruction a sludge hypochlorite (CEPT), digester. treatment primary enhanced chemically 2.7 of WWTP; Esclusas Las d a for in facility treatment new a facility WWTP, Esclusas Las treatment of construction new the to water pumped drive to pipeline a of treatment station pre Pradera La of decommissioning the WWTP; Esclusas Las in facility treatment new the to water pumped drive to pipeline new a of construction the and station pump H Guasmo the collect sewerage the all treat will (WWTP) plant treatment wastewater new a construct to plans EP EMAPAG situation, this address To Environmental on Quality and Di Effluent Norm National the in established thresholds concentration contaminants no with River Guayas the into presently service a underwate and outof pre the “Parson´s Sur” sewer main, which conducts on dry weather 2.10 m underwater an and pipeline long meters 180 a through River Guayas m average an conducts which main, sewer “Guasmo” the (i) mains: year of 2045. Wastewater generated in the south subsystem is currently collected of the wastewater collectedinthesouthern districts oftheCity ofGuayaquil within thedesign “Las Esclusas Th 1. EIAExecutiveSummary NTERAGUA

3 e Project involves Project e /s into the “Guasmo H” pump station from where wastewater is pumped directly into the into directly pumped is wastewater where from station pump H” “Guasmo the into /s - ● ● ESIA Project Background

treatment station (equipped with a mechanized pre mechanizeda (equippedwith station treatment allow the allow

m impacts situation existing To To determineareadirect of the andindirectinfluence ofthe project.

3

Obje in the proximity of the current point of discharge of the Guasmo sewer main, which main, sewer Guasmo the dischargeof of point current the proximitythe of in s n 3.5l5 and /s -

establish MT construction - 8 of the ESIA the of WWTP, andWWTP, associated pumping and transmission facilities to treat 100 percent ctives Owner

.

, theconstruction of a new pump thepremises,station in and theconstruction that

MENTALIMPACT ASSESS

the Environmental Baseline (LBA, as per its acronym in Spa in acronym its per as (LBA, Baseline Environmental the the construction of a new wastewater treatment plant (WWTP), called (WWTP), plant treatment wastewater new a of construction the to perform the processes required for required processes the perform to

m scharges (NCADE acronym).scharges Spanish inits h poet ol generate could project the . ,

3 t s Te aiiy il e qipd ih ehnzd pre mechanized with equipped be will facility The /s. h EI also ESIA The hat will a will hat is t is o establish the establish o , ed in the south subsystem and will require: the adaptation of adaptation the require: will and subsystem south the in ed

r ey little very or

llow an appropriate reference appropriate an llow compliance with national laws and local and laws national with compliance MENT r outfall diffuser).

opis ih plcbe ol Bn safeguard Bank World applicable with complies

e nvironmental ,

S treatment, IA: Te E The .

- treatment, a disinfection system that is systemthat disinfection a treatment, HAZENAND SAWYER, P. W nvironmental and the authorization the which astewater is currently discharged s

ocial flow in dry weather of 0.60 of weather dry in flow to

fail

esign dry and wet flow wet and dry esign 3 outfall diffuser; and (ii) (ii) and diffuser; outfall assess potential potential assess /s into the “La Pradera” i s mpact

o opy ih the with comply to n Social and C

. | . CONSULAMBIENTE

s ordinances, and and ordinances, of the of

of the of in two sewer nish) of the of nish) March 201 March - treatment, treatment, project’s P project Impact PAGE roject, 5 1

s -

IMPACTASSESSMENT LASESCLUSAS ENVIRON The mainnegativeaspects ofcontamination receiving ofthe bod O:\41082H into -000 water sewage raw of discharge the of effect greatest The river. the in levels oxygen dissolved \WPDOCS self an 500 between and dilution of effect large the to \TECHThereare -Mo MEMO\TM1pipelines upstream structures. ofcontrol for need a be cannot wastewater tide during high the of operation the influence meters, 4 to up fluctuations with river, the in tides Also, place. takes sewer sanitary the into groundwater of infiltration considerable and the the of location the to Due season. m genera Guayaquil Salado. Estero the into discharge Daule are into networks sewer discharge Sanitary to systems. designed drainage storm and sewer sanitary separate has city 70 to coverage provide that stations pumping wastewater Guayaquil 3.1 3. ESIAExecutive Summary

owever, sources along ofcontamination ofthese are thebasin diverse. 3 /s) of wastewater during the dry season, and 350,000 m 350,000 and season, dry the during wastewater of /s)

st of the of st B ● ● ● ● the

ackground on Guayaquil’s

Sanitary Sewer Collection System License.obtain therespective Environmental i may Promoter the which with influence, and of area the in community the requirementsof law relevant the by and comments forth Plan Management Environmental the in include to order set in regulations Process Participation Citizen the support To occupational training, monitoring, health and industrial safety. environmental contingencies, and eventualities and construction activities by operation impacted areas of rehabilitation and mitigation compensation, control, prevention, for measures of implementationtimely enable to phases operation the propose To of view. i in assist compare To of physical, socioeconomic and cultural environment environmental assess and identify To advanced age (estimated between 30 and years)50 and condition of existing pipelines, Guayas and Daule Rivers is aesthetic conta

2 discharges in Progreso However, Guasmodue outfall. and and discharges subfluvial Pradera, in 2 project

s aiay ee cleto sse cnit of consists system collection sewer sanitary ’s control valves and pumping stations, causing the storage of the wastewater in the the in wastewater the of storage the causing stations, pumping and valves control City’s wastewater receives wastewater City’s

d 2, d dentification of dentification

implementation 200 m 200 MENTALAND SOCIAL

basic design a design basic Environmental Management Plan to be applied in the construction and construction the in applied be to ManagementPlan Environmental 3 City in relation to the to relation in City /s in dry and rainy seasons), wastewater discharges do not degrade not do discharges wastewater seasons), rainy and dry in /s te ln il mhsz o te olwn apcs rsos to response aspects: following the on emphasize will Plan the ;

W the .

astewater -

lternatives uys ies wie h som riae s eind to designed is drainage storm the while Rivers, Guayas preferred

freely discharged by gravity into the rive the into gravity by discharged freely

pretreatment

- uiiain f uys ie (a River Guayas of purification M

anag design alternative from an environmental point environmental an from alternative design related to environmental an environmental to related n social and Daule mination mination and bacteriological contamination ement

tes approximately 280,000 m 280,000 approximately tes prior to discharge to prior - HAZENAND SAWYER, Guayas Rivers and the Estero Salado Estero the and Rivers Guayas

s

, associated w mat ta my cu o biotic, on occur may that impacts percent 3

/day (4.05 m (4.05 /day ,2 k o cletr ad 61 and collectors of km 3,926 ies

of the area of service. The service. of area the of

arerelated to: sewer system sewer into into ith ith the different stages P.C 3 eae lw ranges flow verage /s) during the rainy the during /s) d social aspects to aspects social d . | . CONSULAMBIENTE the

Guayas River Guayas r. This creates creates This r.

3 March 2015 March /day (3.24 /day . As such, As . PAGE 2 ts

. , .

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 below: General characteristics t of and Sewer Plan ofGuayaquil System Master preparedin2011 treatment of 100 100 city the provide to works including city, the in conditions sanitary improve to measures concrete the with deal to In order 3.2 ESIAExecutive Summary

2. 1. ● ● ● 3.

will Los Merinos described below stations pumping main and two (Pradera has basin this river); Guayas (the body receiving the in works disposal final and collectors stations, pumping several of consists and Census) of approximate mid scheduledfrom WWTP. Esclusas Las Treatment System due tothe growth ofaquatic plantsand floating materials. Guayaquil of front in stretches the in rivers the of appearance aesthetic the to Damage recreation. B ofaquaticContamination life (floraand fauna). start this yearstart this (2015 Wetlands Dry Azul Puerto

percent ceilgcl otmnto o rvr wih r ue fr eodr contact secondary for used are which rivers of contamination acteriological     

treatthe following thefrom water basins sanitary

ProgresoBasin Sanitary de stages the treatment system. of the on depending term, medium and/or short the in WWTP Flor de Bastion, which includes Systems 2 and 3 that will Pascuales, drain into Los Orquídeas, Merinos Norte, Inmaconsa Huancavilca Alamos, Los Norte, del Mirador Guayacanes I,Guasmo Guasmo E1,Guasmo B2, F, Guasmo Guasmo D, Guasmo stations: secondary the are following The Guayaquil. in existing currently Sector Southern for systemmanagement wastewater the complement above; described Station Pump H Guasmo 2 Trinitaria 6,TrinitariaLa 7, and B Guasmo Chala, Trinitaria 1, Trinitaria are: basin collection Pradera on converging Stations upstream. located stations pumping region Pradera Pump Station

percent coverage and connection to the sanitary sewer and plans to complement the complement to plans and sewer sanitary the to connection and coverage

MENTALAND SOCIAL

Guasmo H) that discharge wastewater into the Guayas the into wastewater discharge that H) Guasmo WWTP of of the City ly 5,913 hectares, will serve a population of 1 .

of wastewater produced by Guayaquil, according to the Potable Water above

,

he system - and Florida. )

- Samanes, Samanes, Sauces . 2015. The wastewaterThe 2015.

. The construction

Final designscurrently under are mentioned and collect to

in accordance in to the City’s drainage basins -

WWTP hs tto cneg svn eodr sain that stations secondary seven converge station this

The .

-

Guasmo H is a ma a is H Guasmo

situation, EMAPAG and INTERAGUA have taken taken INTERAGUA have and EMAPAG situation, Pradera pump station s

- wastewater wastewater from its own basin, Alborada, Garzota, Mucho ramn sn elns Impleme wetlands. using Treatment .

of this plant is for basin drainage ,

rntra , rntra , rntra 5, Trinitaria 4, Trinitaria 3, Trinitaria

HAZENAND SAWYER, in pumping station similar to thatto similar station pumping in .

.

planned development is

.

located in the south central , 077,948 inhabitants (2010

this plant covers an areacoversan plant this for J, Lote, Simón Bolívar, P.C

and Guasmo G 2018. This WWTP . | . CONSULAMBIENTE

as well as of River . Construction velopment by velopment

are , which are which , March 2015 March ntation to to ntation described PAGE

nine nine .

3 is

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082Source -000\WPDOCS\TECH-MEMO\TM1 the The main sewerage proposed Guayaquil. system(subsystems for North andSouth) Figure ESIAExecutive Summary

overall 6. 5. 4. proposed proposed :

Hazenand Sawyer Ltda. Cía. & Consulambiente 1 osn dvlpet I OE te osrcin f tetet ln fr lr del Flor for plant treatment Bastion basin planned. is a of construction the LOTE, MI development housing Mi Lote of Areas andof Daule some developments Road process. design under Currently contribution capacity. envisaged for this plant include treatment expand to lagoons systems type lagoons in Mucho Lote and Orquídeas, in order to con Lote Mucho is already available construction Road to t

shows the location of the WWTPs and the location of the main components of the of components main the of location the and WWTPs the of location the shows

Sanitation ProgramSanitation WWTP WWTP WWTP he Coast

MENTALAND SOCIAL

during the fifth year of the concession (2015), for which a 20 hectare lot hectare 20 a which for (2015), concession the of year fifth the during WWTP for . . In the premise the Figure Figure . WWTP

. South Subsystem South for of theCity hs rjc involves project This

1 .

. The regional Sanitation Subsystems of Guayaquil Subsystemsof Sanitation

where where currently there are found treatment lagoons for

Guayaquil .

(Las Esclusas) (Las Road to

the h rhbltto o eitn treatment existing of rehabilitation the

Inmaconsa Industrial sector, Pascuales HAZENAND SAWYER,

and the Coast

the subject of this ESIAthis subject of the

is an important component important an WWTP WWTP

P.C vert them in aerated is planned . | . CONSULAMBIENTE

March 2015 March .

to begin PAGE of of 4

,

IMPACTASSESSMENT LASESCLUSAS ENVIRON Management Project (P151439) O:11 \41082 -000\WPDOCS Source: \TECH-MEMO\TM1 pump H Guasmo this repowering as station. well as outfall, subfluvial the and Station H Guasmo The South Subsystem requires redirection and extension of the existing force main between the The Project 4.1 The overcomecontaminationenvironmental is it therefore increases, environment the contaminate which wastes organic and wastewater of volume the grows, Guayaquil of population urban the As 4. ESIAExecutive Summary

Throughout this document, “Project” refers Component to Three of Guayaquilthe Wastewater

● ● ● ● ● ● ● ● ● Project proposed Project will assist in helping in proposed assist will Project meeting these objectives.

Hazenand Sawyer Ltda. Cía. & Consulambiente Las WWTP Esclusas Fo La Station Pump Pradera Main Components and Location Prevent of navigational siltation channels industrialKeeptouristic, andagr potential water for Maintain waters for offish clean used propagationand survival Maintain waters bath clean for Prevent nuisances Prevent sickness andp Figure rce mainPradera Description (South Subsystem)(South 2

illustrates thethe area general project. ofSubsystem scheme ofSouth

Figure Figure MENTALAND SOCIAL

11

2 . Main Components and Location Location and Components . Main

-

Las EsclusasLas WWTP

rotect the population’shealth comprises three (3) maincomprises threecomponents: (3)

ing

and help thus t and other processes recreational

o: HAZENAND SAWYER,

of South Subsystem South of icultural uses icultural

O O H GUASM EB

important

and aquatic resourcesand aquatic

P.C

to take measures to measures take to

. | . CONSULAMBIENTE March 2015 March

PAGE 5

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 and ofthe respectiveassigned lot construction coordinates for of the Figure ESIAExecutive Summary 3

and and t able

1 MENTALAND SOCIAL

show show the specific location of Las Esclusas WWTP and demarcate the area

HAZENAND SAWYER, WWTP. P.C . | . CONSULAMBIENTE

March 2015 March PAGE 6

IMPACTASSESSMENT LASESCLUSAS ENVIRON of 800 belocated HPthat will at theof lowest dry level well. The capacity ofthe stationis Configuration of the proposed Pump Station comprises a wet/dry well with O:6 centrifuge pumps \410824.2.1 -000\Thethe maincomponents of WPDOCS4.2 \TECH-MEMO\TM1 areBoundariesLas of thoseshowninthefollowing WWTP Esclusas table: ESIAExecutive Summary

Source: Dimensions and Characteristics of the Project Pradera Pumping Station

Prepared by: by: Prepared Hazenand Sawyer Ltda. Cía. & Consulambiente

NORTHWEST SOUTHWEST NORTHEAST SOUTHEAST BOUNDARY MENTALAND SOCIAL

Figure Figure Hazenand Sawyer Ltda. Cía. &Consulambiente

3 South SubsystemSouth described are inthe followingsubsections. . Geographical Location of Las Esclusas WWTP LasEsclusas of Location Geographical . Table Table

1 .

Boundaries of the Project Area Project the of Boundaries

Celec DESCRIPTION Shrimp farms Shrimp farms Shrimp Termoguayas HAZENAND SAWYER, -

Transelectric

P.C

. | . CONSULAMBIENTE

March 2015 March PAGE

7

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO \TM1for tunneling. themain force ismicro As a result of the evaluation of the meth in whichthese every are required meters. hundreds activities are carried out in the total length of the trench as opposed to micro tunneling method installation the by followed whilst the open trench method requires to dig the trench, propping and casting the phreatic level roads and local residents because the working area is limited to launching and receiving wells, as systems tunne micro The analyzed. trenchwere installation of alternatives open and tunneling micro diameter, pipeline the of selection the Besides inpeak 2.44m/s flow flow conditions andbelow conditions. forcemains, both for selected diametersThe lengthand diameter. 900mm of1.6kmapproximately H Guasmo main force the while the from km 4.7 The Force Main 4.2.2 odors control be system to treated. Foul air will be extracted from the screens area and the wet well by fans and ducts towards the odors be will There pumping have The will units. installation 4screens and 5channels. to damages prevent to effort an in well, wet the reaching before screened be will inflow All inflow during 2040. conditionsto dry/wetseason 6,360 ESIAExecutive Summary Prepared by: Prepared Component Pumping Stations

wastewatercollector main L Pradera /s and is based on data of the projection of population to population of projection the of data on based is and /s

Hazenand Sawyer.

-

Pradera Pump Station to Las Esclusas WWTP, with a diameter of 1,800 mm;diameter 1,800 awith of LasWWTP, toEsclusasStation Pump Pradera Las Esclusas WWTP Force main / Guasmo

Guasmo “H” Guasmo MENTALAND SOCIAL

Pradera control units to mitigate possible odors associated with raw wastewater. wastewater. raw with associated odors possible mitigate to units control Name

Table Table of the pipeline and the corresponding filling/restoration, these these filling/restoration, corresponding the and pipeline the of

will havewill capacityL a 6,360 of

-

2 height of 22.5 height of m 1.4 flow HP 140 of pumps centrifugal vertical Five m 33.5 height of m 6.36 flow HP 800 of pumps centrifugal vertical Six Esclusas WWTP will convey a flow of 1,380 of flow a convey will WWTP Esclusas .

Characteristi

ods and their respective impacts, the method suggested assure maintenance speed above 0.61 m/s in low in m/s 0.61 above speed maintenance assure

m cs of PumpingStations cs of

HAZENAND SAWYER, Quantitative Description Quantitative ling method has a lower impact on on impact lower a has method ling -

Las Esclusas WWTP /s and an approximate length approximate /s andan of

gether with estimations of estimations with gether

P.C . | . CONSULAMBIENTE

3 3 /seg and and /seg /seg and dynamic and /seg March 2015 March L /s with a a with /s PAGE dynamic dynamic 8

IMPACTASSESSMENT LASESCLUSAS ENVIRON eight relativeassigned. importance was included O: which evaluation of \ process eachcrit to rigorous4), criteria (Table decision 41082 a to subject were alternatives These -000\WPDOCS\TECH-MEMO The phase. second the in followingalternativ were the3 detail greater into evaluated be to alternatives 3 select to order in \TM1the first consisted of a qualitative screening of 19 technological options available in the market alter optimal treatment secondary the of process selection The at andappropriate alltimes is for localconditions. requirements discharge wastewater current meets it as recommended was (CEPT) Treatment loca the Considering land. available the in urban settings, no experience of their use in a large scale, or no feasible implementation to for be suitable allocated not standards,within effluent meet to inability of because consideration As a result of the analysis, several of the above technologieslisted were exc physical various of viability stage, identification first treatmentwere technologies,evaluated.These were: technologies a in treatment, primary select To conducted. were options treatment wastewater secondary and primary appropriate During the development of the wastewater feasibility study, evaluations to determine the most appropriate most the is location for the treatment wastewater plant. Esclusas” “Las site the that concluding evaluated, were Guayaquil to WWTP a for options location 5 study, this In 2004). (August Guayaquil of Plan Master Sewage Sanitary the in established was WWTP Esclusas Las of location The 4.2.3 ESIAExecutive Summary Prepared by: by: Prepared Component Force Main Force ● ● ● ● ● ● ●

Trickling contact with solids chamber filters TricklingFilters Media withPlastic ConventionalSludge Activated Chemically assisted high Chemically air flotation (DAF) assisted dissolved Chemically EnhancedTreatment Primary(CEPT) Preliminary Las Esclusas Treatment Plant Hazenand Sawyer.

Pradera Pradera

Guasmo “H” Guasmo MENTALAND SOCIAL treatment with rotating milli treatment with Esclusas Name -

Esclusas

- es selected:

Table Table -

rateclarification

: 900 mm, peak flow 1.38 m mm, flow1.38 900 peak of diameter a with Pipeline GRP. material tunnels, micro of Installation mm, flow peak of1,800 diameter a micro of Installation

Analysis of Alternatives 3 eria a weighting factor or relative weight based on their their on basedweight relative or factor weighting eriaa .

l conditions, the use of Chemically Enhanced Primary Primary Enhanced Chemically of use the conditions, l Characteristics of Force Main of Characteristics

- screens

tunnels, reinforced fiber reinforced tunnels, HAZENAND SAWYER,

Quantitative description Quantitative

3 /seg, length 1.6 km. 1.6 length /seg,

native was done in two phases; two in done was native

6.36 m 6.36 3 /seg, length 4.7 km 4.7 length /seg, P.C - luded from further glass (GRP) pipeline with pipeline (GRP) glass . | . CONSULAMBIENTE serve the south of south the serve

March 2015 March - chemical chemical PAGE

9

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCSeach are process oftreatment inthe following detailed table. by required was Ecuadorean environmental regulations i it if treatment, secondary enable to WWTP \the of expansion TECH future the for mor -implemented at the WWTP to meet future regulation requirements. EMAPAG EP has planned becomesMEMO used regulation be will the future, environmental treatment the in if chemical Nevertheless, wastewater. the city’s the because of characteristics \ treatment, the on depending of TM1 type this of aspect important national environmental regulation were achieved with the p contributing basin, mainly its low concentration of organic material. Standards required by the if necessary. This treatment scheme was selected due to the characteristics of wastewater of the assisted chemically primary treatment treatment, preliminary for installations include will WWTP mentioned t capacity ItPraderaand Guasmo basins. designedan is for averageflow of2.67 m of waters combined treat will before, mentioned as Subsystem), (South WWTP Esclusas The WWTP. future for alternative optimal a included which evaluation, quantitative Alternative Filters concluded thattheTrickling criteria,was isthe sensitivity it the analysis of and alternative each of analysis detailed a After ESIAExecutive Summary

o manage peaks of up to 2 times the medium flow during rainy seasons. The The seasons. rainy during flow medium the times 2 to up of peaks manage o Prepared by: by: Prepared 8 7 Aspects Environmental 6 Supplies 5 4 3 Aspects Operational Criteria Technical 2 1 criteria Economic

Production of Biosolids ofBiosolids Production ofOdors Production ofExpansion Possibility Areaand of Necessity and/or Regulations in Changes Effluent. Affluent and of Concentrations Future to Adaptation Reliability Operational ofOperation Ease Costs Maintenance and Operation Costs Construction

,

and disinfection, with the option to add in the future a biological treatm MENTALAND SOCIAL

Hazenand Sawyer. Table Table

4

. Decision Criteria and Relative Weight Used Weight Relative and Criteria Decision .

mlmnain f h scnay ramn i te Esclusas the in treatment secondary the of implementation to Select the Optimal Alternativ the Select to

Criterion

n the future. The units with their respective features of

e demanding, a secondary treatment may be be may treatment secondary a demanding, e

HAZENAND SAWYER, roposed treatment. Flexibility is an

e

Relative Weight Weight Relative Las Esclusas LasEsclusas

WWTP 3 (%) 12.5 12.5 10.0 10.0 20.0 20.0 /s in dry with season P.C 7.5 7.5

. | . CONSULAMBIENTE

March 2015 March PAGE ent, 10

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary Prepared by: by: Prepared Water and sludge and Water Component Treatment Hazenand Sawyer.

MENTALAND SOCIAL

PrimaryTreatment Sludge Digesters Digesters Sludge Pretreatment Disinfection

Outfall Name Table Table

5

.

Characteristics of of Characteristics

4. time.Each Digesters. 3. mm. 2 2. Gravity thickeners 1. depth. Primary clarifiers 3. time. retention minutes Pre 2. seg 500 to 300 between time, retention seconds units,40 mixing, Rapid two 1. m 3.07 flow pick at units designed Three Chambers: Grit Vortex 3. mm).fine and (6 MM) (8 screens coarse channels, fourscreens Screeningchamber: 2. diffusers. bubble coarse mixingthrough chamber An aerated AiredChamber: 1. with side diffusers type “Tideflex” of 600 mm. of600 “Tideflex” type diffusers withside mm, 900 of sectiondiffusers vertical mm, 15 2,000 Diameter at with situ, retention in SodiumHypochlorite control odor for Biofilter 5. days. 5 for week, dewateredhours35 per be to are Solids

3.7 m 3.7 Solids dewatering Solids filtration. sludge for Finescreens -

aeration and flocculation tanks, two units with 17 with17 units two tanks, flocculation and aeration

3 /seg 3 /s. Las Esclusas LasEsclusas

volume unit of 5,000 m unit5,000 of volume .

-

Two operating tanks with 15 days retention daysretention with15 tanks Twooperating HAZENAND SAWYER, Quantitative Description Quantitative -

-

-

Three units 52.5 m diameter, 5 mm 5 diameter, units 52.5 Three

Two operating belt press 3 mwide. 3 press belt operating Two Two units of 13 m diameter. 13 units of Two - Mixers shall be mechanical. be shall Mixers

WWTP WWTP 1.

-

One unit of 4,400 m 4,400 Oneunit of

3 . -

P.C

Two units with slots of withslotsof units Two . | . CONSULAMBIENTE time 43 minutes 43 time

March 2015 March 2 .

PAGE

11

IMPACTASSESSMENT LASESCLUSAS ENVIRON the in work officials expected is It 2006. since its discharged currently and day a receives per O: of site waste optimization The solid Landfill”.\ of Iguanas 41082 tons “Las 4,500 as approximately known site, disposal waste solid -Guayaquil 000 term, medium and short the In \WPDOCS and conditioning, mixing, BS), in reduction composting. humidity \ (additional TECH processes dewatering - considered. MEMOis In the long term, incorporation of a \TM1 installed withallrequired auxiliarygas.methaneequipment of will be used as fuel to generate electricity to be used on site. included. be managementsystem process. thickening the from sludge primary stabilize will digester anaerobic The content, thusfulfilling thelandfill’s material criteria. acceptance the dewatering sludge primary in generated biosolids of process. reuse treatment beneficial or wastewater disposal final the is challenge main The Source: Figure ESIAExecutive Summary Hazenand Sawyer & 4

shows schematically proposed the treatment process for Las Esclusas WWTP.

h CD boois aaeet s fclt ta cmie al secondary all combines that facility a is management biosolids CMDN The

Figure Figure eann sco kon s etr , hr te oi waste solid the where D, sector as known sector remaining MENTALAND SOCIAL

Consulambiente Cía. Ltda. Cía. Consulambiente 4 : Proposed Treatment Process for “Las Esclusas” WWTP Esclusas” “Las for Process Treatment Proposed : .

Dewatered biosolids will will biosolids Dewatered

h dsg includes design The h pae eetd o icag te isld i te iy of City the is biosolids the discharge to selected place the

Methane gas produced fromgas produced Methane C enter for

that

the lifespan of the sanitary landfill sanitary the of lifespan the

M anagement and

be between 25 to 30 percent of dry TS TS dry of percent 30 to 25 between be HAZENAND SAWYER, hceig aarbc ieto, and digestion, anaerobic thickening,

New New cogeneration engines will be processdigestion anaerobic the

F

inal D isposal isposal (CMDN) of BS P.C . | . CONSULAMBIENTE

can be extended be can

March 2015 March

A biogas biogas A a been has PAGE 12

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000Process continueintheGuayas will the Directorate Environment. Ministry of Provincial of \therefo priority, national a considered was WPDOCS project the Las Esclusas WWTP” on November 19 and Main Force Station, Pumping Pradera La of Maintenance and Operation “Construction, \TECHEnvironmental the initiated INTERAGUA above, the to According -MEMOGuayaquil canton. Unique in Application \ Responsible of of Authority TM1 Environmental of seal category the acquired the Guayaquil use to right pu the and accreditation Environmental Management System the (SUMA, as per its acronym in Spanish), Guayaquil the provision was of Municipality m by Authority, Environmental National the purpose, this For Guayaquil. Municipalityof the to matters environmental of powers delegated Spanish) in acronym its per as (MAE, Ecuador of By means of the Auth the 5 of responsibility the be will system the in Concessionaire. included WWTP’s new of maintenance five next the in plants treatment wastewater future of and conveyance pumping, existing primary treatment maintain facilities; likewise will and be responsible operatefor planning, funding to and constr required is Concessionaire the t of 4.2.2.1 9 August on Concessionaire operations The commenced Guayaquil. Canton the for services drainage storm and sewer, sanitary (EMAPAG 11 April On 5 5. processe of sludge through theproduction of compost (using secondary dewateringstructuring and mix and should be completed by December 2017 wil WWTPs future other and this in disposal bio of management sludge the for study the Plan Master A of manner. continuation the allow will which authorities environmental la sanitary municipal new a of construction treatment facility, based on its current rate of exploitation. Plans for the future expansion or the the expected volume of sludge during the first eight to ten years environmental of operation of the wastewater required between all reached has been which permits landfill, to already receive this the waste. The has landfill running has the capacity agreement consortium to receive municipal wa the An and biosolids. EMAPAG and debris for the be site will future the disposal in which E, sector as known area adjacent an in years more 8 least at ESIAExecutive Summary .2 .1

eans of Resolution No. 002 on January 16, 2008, decided to approve and award the the award and approve to decided 2008, 16, January on 002 No. Resolution of eans blished in the Official Record R.O. 282 on February 26 February on 282 R.O. Record Official the in blished

Institutional and Legal Framework Environmental Institutional Framework s).

he Concession Agreement, “Collection, Treatment and Disposal of Wastewater”, Wastewater”, of Disposal and Treatment “Collection, Agreement, Concession he

EP ,

2001, the 2001, )

ind ih NEAU, h Cneso Areet o ptbe water, potable for Agreement Concession the INTERAGUA, with signed

MENTALAND SOCIAL

ority Transfer Agreement of April 12, 2002, the Ministry of Environment Competent Authority Empresa Municipal de Agua Potable y Alcantarillado de Guayaquil de Alcantarillado y Potable Agua de Municipal Empresa

l be financed under financed be l

,

2001 with a 30 year contract. According to Paragraph to According contract. year 30 a with 2001 ,

2012 before the Municipality of Guayaquil. However, ndfill are under discussion between municipal and and municipal between discussion under are ndfill . This study will look at options for the reutilization

the World Bank Project Bank World the re it was ordered that the Regularizationthe that ordered was it re HAZENAND SAWYER, - year investment plan. Operation and and Operation plan. investment year - solids generated from Las Esclusas Esclusas Las from generated solids ,

2008. Thus, the Municipality of Municipality the Thus, 2008.

Regularization Process of Process Regularization P.C - . | . CONSULAMBIENTE

Component Four Component ste, including March 2015 March PAGE uction uction 13

IMPACTASSESSMENT LASESCLUSAS ENVIRON management. environmental sustainable and adequate ensuring also contamination, and degradation prevent to order in programs and studies these O:authori \41082 relevant before authorization for applications with along them submit Environmental and Plan Management respective the and Assessment Impact Environmental an -of activities, 000these th \pollute or degrade WPDOCS could that activity susceptible any undertaking before instrument binding a establishes State Ecuadorian The “(…) states: which TULSMA, in forth set Ecuador of policies environmental \TECH engin all implementing for prerequisite -MEMO implementat The project the under \ expected TM1 activities natural environment. andsocial that allow environmentally feasible and sustainable will in the short, EIA The of construction, operation and removal as well as maximize the positive impacts of the project. stablishing removal, and implementation measures operation, construction, of environmental on stages project during the by factors caused impacts the properly assess and describe identify, regulat Ecuador Per the Ministry18 dated ofthe February Environment, ofLegislation Secondary of Text Unified the of VI Book IVof Title and I Title of reform the of Text Unified the of (SUMA) Reform the System Management Environmental to Unique the of I Title VI corresponding Book of Legislation Secondary 068 Agreement Ministerial the of The procedure d during construction, thestudy,preconstruction, The legal framework defined the basis on which every project activity should be founded, either project. These include: the in undertaken be to activities the to applicable regulationsother and rules laws, the within WWTP Esclusas Las and Main Force Station, Pumping The Environmental Impact Study for “Construction, Performance and Operation of La Pra 5 ESIAExecutive Summary .3

● ● ● ● ● ● ● ●

niomn Ipc Assmn ad niomna Mngmn Pa ae basic a are Plan Management Environmental and Assessment Impact Environment ties, who are obligate to make decisions about, and control compliance as provided by by provided as compliance control and about, decisions make to obligate are who ties, urn ad plcbe niomna agr environmental standards, environmental applicable and Current Environmental Management Act. the in forth set mechanisms participation social of implementation the for Regulation Safetyand Regulations Health for workersandworking environment improved Pollution Prevention and Environmental Environmental the for Secondary Act Management Environmental of the of Regulation Text Unified 3516: Legislation Decree Law, Organic Health Law Prevention and onPollution Control In of theRepublicThe Constitution ofEcuador Ecuador Environmental Regulations

of July 31 July of Environmental Managementternational Agreements Act to to prevent, mitigate or compensate any potential negative effects generated for phases eveloped in this Environmental Impact Study, is consistent with the provisions

, MENTALAND SOCIAL

i 2013, and as provided for by the Ministerial Agreement 006, concerning 006, Agreement Ministerial the by for provided as and 2013, n, the ons, e environment, the preparation by interested parties who will perform will who parties interested by preparation the environment, e

Control.

an ups of purpose main

eig rjcs a poie fr ril 1 n basic on 1 Article for provided as projects, eering

operation,

an ,

eet ad ue, s el s INEN as well as rules, and eements Environmental medium, 2014.

Both Environment Impact Ass Impact Environment Both HAZENAND SAWYER, - South Subsystem” has been framed been has Subsystem” South

and abandonment phases.and abandonment

and long term, without affecting

Social P.C . | . CONSULAMBIENTE seset s to is Assessment March 2015 March

o are ion essment PAGE

dera 14

IMPACTASSESSMENT LASESCLUSAS ENVIRON temperature varies fifteenand thirty between int the by marked O: clearly seasons two \41082Currently, Guayaquil has an approximate area of 34,500 hectares. The climate is tropical, with -000\Ecuadorian development. and economic social WPDOCSis Guayaquil \TECH Urdesa, in low slope hills Alborada, -MEMO4 meters above sea level and has a substantially flat topography. However, there are areas with name. It is located at latitude 2° 19' sout \TM1samethe of Gulf throughthe the PacificOcean to accesseasy citycoastalwith a is Guayaquil east, crossed while and encircled Salado by theEstero Ran the of vicinity the in located is Republic of Ecuador, a country located in northwestern . The The area of the study is in Santiago de Guayaquil, 6 6. The been proposed has considered Project Category an Environmental OP/BP Aunder 4.01. th for policies safeguards details these on policies): Bank L/0,,menuPK:584441~pagePK:64168427~piPK:64168435~theSitePK:584435,00.html World http://web.worldbank.org/WBSITE/EXTERNAL/PROJECTS/EXTPOLICIES/EXTSAFEPO applicable The 5 Reco the Regulation for implementation of mechanisms of social participation, published in Official to Instructions the of provisions the Also, System. Management EnvironmentalDecentralized t participation social Record Official R.O. No. 332 dated in May 8 published was which 1040, No. Decree Executive of provisions the account into So the of development the way, same the In most the achieving effectivethe most action”. of principle the through protected, on being resource or space respective the to performance based of level appropriate are Plan Management Environmental and ESIAExecutive Summary .1 .4

Environmental ● ● ● ● rd No. 15 July 036, dated General Environment Involuntary (OP/BP 4.12) Resettlement Physical CulturalResources (OP/BP 4.11) Natural 4.04) Habitats (OP/BP Environmental World Bank Polices one of the most important cities in Ecuador since the city is a major center of of center major a is city the since Ecuador in cities important most the of one

and Social MENTALAND SOCIAL

hat must be adopted by the authorities that comprise the National National the comprise that authorities the by adopted be must hat

Assessment (OP/BP 4.01) Assessment

Baseline , 2013 have been considered. been2013 have , 2008, 2008, wording establishing the criteria and mechanisms for Sauces,

h and longitude 79° 53' west at an average niy f anal dy n riy esn wee the where seasons rainy and dry rainfall, of ensity ge, surrounded by the Guayas river network in the the in network river Guayas the by surrounded ge,

cial Participation Process of the project has taken has project the of Process Participation cial and some sectorsand ofthe onnorth some area city. - five degrees Celsius throughout the year.degreesfive the throughout Celsius

the main district of Guayaquil canton, in the

on thewest HAZENAND SAWYER,

.

e

P.C rjc ae (see are Project . | . CONSULAMBIENTE elevation elevation March 2015 March PAGE

15 for of

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS6 \TECHSource -MEMO\TM1 potential for the city. resid Estero cross El and Salado River Guayas the Both found. are resource, environmental important an also forests, mangrove Salado Estero El of arms different the around areas vast In River. Guayas fisherie of source rich a is gulf The Ecuador. for importance tourist and economic great of ecosystem environmental rich a is and the on Due in toproximity directionflow tothe ocean, of the The city twomajor receiving by issurrounded bodies: ESIAExecutive Summary .2

:

Hazenand Sawyer Ltda. Cía. & Consulambiente tidal condition tidal Physical Environment b. a. the months of highest of months the i study of area the in temperature annual Average 26°C. and 23 between varies Temperature mm. 1,255.7 is study of area the in rainfall Climatology

The Estero Salado, on the west side, forming part of the estuary, up to the city center Ocean,and Pacific the of estuary an Guayaquil, of Gulf the into empties which side, east the and Daule of confluence the by (formed Rivers Guayas and Daule

ential areas and represent a resource of great recreational and aesthetic aesthetic and recreational great of resource a represent and areas ential MENTALAND SOCIAL

:

.

vrg ana rifl o 123 m wie h aeae aggregate average the while mm, 112.3 of rainfall annual Average The contains a mixture of marine and fresh water, fresh and marine of mixture a contains Guayaquil of Gulf The

sun exposure, with values of 150 and 166.9 hours, respectively. respectively. hours, 166.9 and 150 of values with exposure, sun Figure Figure s, particularly shrimp ponds located on the banks of the of banks the on located ponds shrimp particularly s,

5 . Location of the Project ofthe Location .

both HAZENAND SAWYER, s 25.5 s

receiving varies bodies depending

°C. August and September are are September and August °C. P.C . | . CONSULAMBIENTE

Babahoyo) on on ) March 2015 March PAGE 16

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary ● ● ● ●

the most important river system of the entire Pacific coast of South America. Rivers America. South of coast Pacific entire the of system river important most the of coast Pacific System Hydrographic LPGRepsol bottling by owned a and Petroecuador company State the by owned Salitral El Products Hydrocarbon of plants, generation power the to oxides (NOX), carbon monoxide (CO) and sulfur dioxide (SO concentrate sources fixed of area of particular number interest is located on large the a concentrate (industrial complexes) whichthat generate significant emissions of pollutants into areasthe air. One several has Guayaquil food and beverages processing contributes with 30 39 sources: mobile to corresponds significantly from all sectors evaluated, although it is noted that the highest percentage the in PM10 matter particulate of emissions 87 for account sources monoxide carbon of emissions that determined been year, per CO of tons 59,700 of emissions are there that determined been has it Also, city. the of vehicles tons of NOX per year have been identified, being the most important source the fleet of percent the city a air of Quality cohesive blows offriction and (N) non soils values of for and number stratig in the area are predominantly clay with a soft clay layer approximately 12 m thick. The Aridisoles, Alfisols, Mollisols, Inceptisols, Vertisols, Entisols, S acronymits Spanish); in Santa Elena Peninsula (PSE, as per its acronym in Spanish); Progreso Basin (CP, as per Spanish); in acronym its per as (CCO, Range Coastal Spanish); in acronym its per as morpho pres the by characterized mainly is which River, rhyolite, (granites), Chongón submarin of layer a of consists It Cretaceous. formation, on which is a sedimentary succession of the Upper, Geology northwest the southwest winds prevailing Annual km/h. 18.52 to km/h 4.00 from range speeds Wind Basin comprises the sub the comprises Basin where the influx of tides south, to until north run navigable, mostly are Basin, Hydrologic Guayas the comprising oil

characteri merging with merging ahc rfl dsrbs h tp o si wt srnt prmtr (u for (Su) parameters strength with soil of type the describes profile raphic

- of the total emissions. tectonic domains existing in the region are: Chong are: regionthe in existing domains tectonic : re the main source of emissions of sulfur dioxide

(NW) - h gooia fudto o te ein osiue te ió volcanic Piñón the constitutes region the of foundation geological The

d MENTALAND SOCIAL

ooce ag, f uasc g, opsd f ai inos rocks igneous basic of composed age, Jurassic of Range, Colonche in few sources, (SW) (SW) direction with 45.6 :

stics From an annual total of 21,600 tons, thermal generation companies in companies generation thermal tons, 21,600 of total annual an From South America. It has an area of 32,130 km 32,130 of area an has It America. South direction withafrequencydirection of2.9 the basalt,

:

n the In

Ecuadorian fluvial artery that empties in front of Puná Puná of front in empties that artery fluvial Ecuadorian percent :

of the

- and basins: Daule River, Vinces River, Macul River, , Macul River, Vinces River, Daule basins: the of basin largest the considered is Basin River Guayas

and andesite. The area of study is located along the Guayasthe along located is studyof area The andesite.and emit significant Manabi BasinManabi (CM)

td area study In the city of Guayaquil, emissions

hydrologic hydrologic basin can been observed. Guayas Hydrologic

- of total emissions of that pollutant. On the other hand, hand, other the On pollutant. that of emissions total of YPF is region the primarily due to the to due primarily

percent .

percent

hr ae odr ad 1 uodr o soil: of suborders 11 and orders 6 are there Road . The manufacturing industry, particularly industry, manufacturing The .

rates rates of Particulate Matter (PM), nitrogen also the location of the of location the also e volcanic material and is the core of the the of core the is and material volcanic e city

the the C frequency HAZENAND SAWYER,

ence of estuarine marine clays. The The clays. marine estuarine of ence reach 4,5 reach percent

perce oast. Thermoelectric power plants, City’s - nt

; and least prevalent . CO CO -

of total emissions of PM10.

00 tons per year and come and year per tons 00 o SO fleet vehicles fleet n 2 2

- Tertiary, - ) into the air. In addition across Colonche Range (CCC, (CCC, Range Colonche 2

and Associations and , trbtbe o mobile to attributable on which represents a 59 P.C

the order of 27,000

. | . CONSULAMBIENTE

Storage Terminal Storage 8 provinces. It is is It provinces. 8 - cohesive soils cohesive

and Quaternary .

on Also March 2015 March

the order order the are from PAGE , it has it , I . Soils. sland, from the 17

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary ● ● ●

te pluin ore ( sources pollution other wastewate several by affected is quality water its and saline is water cycle. tide a by affected consistently are solids suspended and salinity with associated Onlyparameters tide. the influenceof the with even day,one of span the in quantities large in discharged be must which substances toxic organic and metals heavy of case river the of quality the affect can discharges significant only conditions, reaching values above 10,000 m It is recognized that Daule high tide affecting the area of influence of the two water streams around Santay Islan during back conveyed are contaminants the of some but tide, low during downstream conveyed are Duran of discharges industrial and municipal words, other In influence. action flow back and flow because tide the of effect the to due is This Durán. of margin western the on developments urban of discharges water the by affected also is It of tides. by produced flow back and flow by salinity) (including quality and the by regulation affected dam is quality mining, the downstream river activities, Also margins. agricultural the in to populations due section the upstream of wastes and section of wastes interest (from La Toma to Las Esclusas) is affected agriculture by the quality of th wastes, solid industries. of Natural sources of pollution must be added to this. Water disposal quality of the river poor include sources Othe water. of body the of quality the affecting sources anthropogenic various the of of Estuary the in quality Water betweenIsland.and Verde de Punta Piedra 25 arecoefficient dispersion dispersion of values density in difference the and gradients velocity to due dispersion associ diffusion the determines only not coefficient dispersion The day. one than more for last may periods mixing and slower proces stratification in turbulencethe water column; while in the second, and the diffusion processes are much diffusion the case edges of Jambelí Channel, have values of 42 cm²/s and 6 cm²/s, respectively; outer in and the first inner The hour. one approximately takes and m 10 of depth a at completed 330 about of Channel Morro and Channel existence of strong turbulence processes found in the section corresponding to Cascajal season dry the during Guayaquil of Gulf the of estuary River Guayas of Dilution percent 60 between accountingfor contributor largest the is River m 230 seasonallyaccording torainfall: summer, in theaverage flow ofGuayas River isabout the confluence of Babahoyo and Daule Rivers 5 north km of Guayaquil; its flow varies Rive Yaguachi River, Current uses of water in the area of study and its area of influence margins the of alongwalkthroughs area its and study of area the in water of uses Current location withnoneor very treatment.limited 3 /s, while during while /s,

(rainythe flow of of season) Guayas River.

to detect MENTALAND SOCIAL

considered . For the above reason

,

r, Jujan Jujan r, concentrations of dispersed contaminant are greater. Values of of Values greater. are contaminant dispersed of concentrations

the rainy season increases to more than 1,500 m 1,500 than more to increases season rainy the o example for - Guayas River is a large body of water with actual flow rates :

section – The diffusion The 40 km²/ 40

River, 3

/s by the effect of tides with high dilution. Under these of rivers and bodies of water, the followi the water, of bodies and rivers of the , which is possible due to the drag of contaminants of drag the to due possible is which ,

and Minor Drainage. Guayas River is formed by formed is River Guayas Drainage. Minor and day in the stretch corresponding to Guayas River Guayas correspondingstretchto day the in som ae rnf) ptem f h Project the of upstream runoff) water storm , Guayas River Guayas ated with turbulent mixing, but also includes also but mixing, turbulent with ated ,

the the quality of most parameters do

coefficient in several stretches of the inner the of stretches several in coefficient e wl ls fr eea hus showing hours, several for last will ses cm²/s; this means that the mixture can be be can mixture the that means this cm²/s;

HAZENAND SAWYER,

: s

Wastewater discharges are one one are discharges Wastewater car has

percent ry

high values denoting the the denoting values high pollutants to the area the to pollutants . P.C

(dry season) and 66 and season) (dry T . | . CONSULAMBIENTE herefore at higher at herefore r discharges and discharges r 3 /s; Babahoyo /s; : n . This is the is This .

g extensiveg During the the During es March 2015 March

The river The

not vary PAGE e river 18 of of d. d.

r

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary ● ● ● ●

complexes based on housing projects with state or private investment. invasions, on based formed expansion area into zones G, H and I. GAD Trinitaria, v of consisting space man. by impacted open undeveloped presently is site Land of Use visibility, slopes, anthropogenic activity, accessibility, vegetation, configuration, functional Salado Estero River, Landscape system, fire chemicals, potable of breakage or installation water, sewerage and telephone supply systems, machinery, soil infiltration, handling and storage and of equipment of maintenance and and clearing activities of soil, earthmoving, excavation and land cleaningcompaction, wastes, solid of generation and gases combustion of generation generation, of particulate matter, spill of liquids, chemical substances and fuels on the ground, noise are: dispersi More scenarios severe operation, among others. performance, removal, Risks Endogenous as ahazard. “high” seismic plate, American South v highly sector this the making against plate tectonic Nazca of front in located is region susceptible to experience the effects of earthquakes and volcanic eruptions. The coastal lo is It world. the in volcanoes active of index highest the with countries the and of one earthquakes considered is Ecuador Regarding tsunamis Guamos. Popular; Bastión Sauces; Orquídeas; Las and winterassociatedwi season during floods by affected dramatically be may which River, Guayas of floodplain the Risks Exogenous Esclusas. Escl Las of discharge and River Guayas of beginning the BabahoyoRiver, meeting Merinos, Los of area discharge the 2 Stretch Guayaquil; of area consolidated Merinos, Los of site Interest is focus rivers water and of banks in that observed navigation is It use. industrial and thermoelectricity recreation; contact regulations); environmental of pre tourism; and landscape transport; (breach wastes liquid and solid of discharge found: were Guayas, and Daule bodies, receiving of waters of uses Miramar,Lorenzo Tous,Pablo Neruda, and Carlos Cevallos, comprising lower middle so the city, the of southeast pr the of (AIDA) influence land of uses current district, Ximena in located are - , Guayaquil divides the urban area into zones A, B, C, D, E and F, and in the the in and F, and E D, C, B, A, zones into area urban the divides Guayaquil

aes r salw n esl acsil fr h aoeetoe activities. aforementioned the for accessible easily and shallow are waters and

Guasmo, : MENTALAND SOCIAL

bad odors by thewater odors by bad treatment plant. T :

Las Esclusas WWTP is located so located is WWTP Esclusas Las Guayaquil of city he ed caused

:

on three str

The WWTP will r will WWTP The Guayaquil Canton is located on a flat relief area, which is part of part is which area, relief flat a on located is Canton Guayaquil :

and South Central system. The Regulatory Plan defined by the the by defined Plan Regulatory The system. Central South and eae t atvte o te rjc: osrcin maintenance, construction, project: the of activities to Related ,

by transformer’s short circuit, power outages in the the in outages power circuit, short transformer’s by n Sna Iln, adcp uis ht r ntd y their by noted are that units landscape Island, Santay and

ulnerable to natural disasters. The disasters. natural to ulnerable th El Niño. Sensitive areasLos Vergeles Niño.Sensitive th El flood risks are: of - called Guasmo Norte, which includes the cooperatives of of cooperatives the includes which Norte, Guasmo called residential and Guasmos denominated those them among jc icue 1 Rsdnil ad stlmns located (settlements land Residential 1) include: oject etches: Stretch 1

cated in a seismic region called Ring of Fire, an area area an Fire, of Ring called region seismic a in cated usas; Stretch 3 Stretch usas;

has the f the has quality, servation of aquatic life and wildlife; secondary wildlife; and life aquatic of servation eceive flows from pumping stations of Pradera, Pradera, of stations pumping from flows eceive Located in Zone A are

ollowing main natural resources: natural main ollowing and naturaland fragility. -

HAZENAND SAWYER, Daule River, upstream dischargefrom uth of Cobina estuary. Cobina of uth -

Guayas River, downstream of Las of downstream River, Guayas

in the area of environmental direct environmental of area the n presence and the sectors that have been

egeta project area is is area project -

Daule River between River Daule

P.C tion that has been been has that tion . | . CONSULAMBIENTE

All these sectors The proposed The

March 2015 March f water, of

classified operation electrical

PAGE Guayas 19 on on

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 6 ESIAExecutive Summary .3

● ●

Estero Salado. In the inne predominant species is Chaetoceros affinis is which located towards Guayas most Another crustaceans. and fish feeding for the phytoplankton important an is species this Among scarce. repre algae Cosmopolitan a are dominant, most the of one is flagellates which costatum Skeletonema is algae, representative and sillicoflagellates the cyanobacteria, mouth, the of area the in presence of di downstream, while coronalis, Polymyxus as known Neriumoleander, commonly Bacillariophyceae contains and kind Chrysophytas is (Prunusdulcis), River Guayas the in trees (Avicennia Mangle Almond germinans), Black White Mangle (Laguncularia racemosa). mangle), benjamina), (Rhizophora Mangle Red (Ficus Cordylineterminalis, Ficus sp, Acacia Robinapseudoacaia, glabra), (Bougainvillea Buganville Erythrinaespectabilis, plant Saman (Samanea saman), Banana oil (Musa paradisiaca), Coconut palm Castor indica), guachapele), (Albizia (Manguifera Guachapelí juliflora), (Prosopis Mango Mesquite communis), (Ricinus following: the are influence of area dry habit. deciduous the as known is duringwhich year, the of season leaves its losing by characterized is Vegetation representative. most the is m.a.s.l, 300 and 50 between ranging belt altitudinal an in forests, deciduous and G isin found those as formation bushes dry between such being by characterized lowlands, coastal of growth vegetal Forest deciduous semi the in is located project the areainfluenceof belts.Theof altitudinal subtropicaland tropical Flora: lose their leaves during dry season. 25 among that estimated is It forests. deciduous in than This formation occurs b zone corresponds to the semi life The days. 99 and 54 between fluctuate dry physiologically as considered daysand year covers from May to November, which may be extended to December, depending on the Annual rainfall registered in the area ranges between 750 and 1 m.a.s.l 500 and 0 Life zone (bioclimatic) Biotic non Environment 4) and River; Guayas and shrimp farms are located site the on al comprising area an land, development forest mangrove existing estuary, Port the of locks by the facilities of the controls and ANDEC Authority of Guayaquil are located; facilities metallurgy where northern Cobina estuary, a) sectors: distinct two by represented land, industrial 2) structure; class homes, mostly built of rei respectively. salinity, low and high watersof its in costatumSkeletonema and coronalisPolymyxus there River), . The number of. The mon number

Floral diversity in Guayaquil is the result of a variation of variation a of result the is Guayaquil in diversity Floral

MENTALAND SOCIAL

is atom Skeletonema costatum would increase. Dinoflagellates, tintinnines, a low phytoplankton diversity due to the abundance and dominance of of dominance and abundance the to due diversity phytoplankton low a ., Electrical

with an average annual temperature ranging between 20 and 32ºC. and 20 between ranging temperature annual average an with

etween 200 and 1,100 m in hilly areas where humidity is greater :

The project r estuary of the Guayaquil Gulf and its internal waters (Guayas eastbound ths senting estuarine waters with a temperature of 24 and 30ºC; 30ºC; and 24 of temperature a with waters estuarine senting

de Guayaquil; 3) development land, space between Cobina - considered as deciduous Forest ecologic formation of coastal lowlands.

nforced concrete and few houses built over reed or wood

. b) b) area located south of Cobina estuary, represented

area most the entire mangrove ecosystem. mangrove entire the most is located in the Subtropical Region, between ecologically dry6 months isapproximately HAZENAND SAWYER,

The type of dominant micro

– Terr 75

percent estrial flora species in the in species flora estrial , 000 mm. The dry eneral Villamil Playas Villamil eneral P.C

. | . CONSULAMBIENTE

of floral elements elements floral of forests within the within forests ( C ocos ocos nucífera), March 2015 March River PAGE S season season - everal algae algae

and 20

-

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary ●

Ioieoiai sioisms, ie hlbt Ahrs lzne) Tlpa fish Tilapia kluzinger), (Achirus halibut sp.), (Oreochromis river spinosissimus), (Rhamdia (Isorineloricaria Bearded ecuadoriensis), RaspabalsaBocachico(Ichthyoelephas(Pseudocurimata boulengeri),Dica humeralis), (Leporinus Guanch Mouse cinerascens), reported: are following (Nodilittorina Gastropod luteofasciatus), varia), (Theodocus Snail inflata), (Polymesoda Miona siliqua), (Macoma Bivalve siliqua), (Macoma Bivalve asperrima), (Protothaca Bivalve trawtuineana), (Mytilopsis Mussel strigata), (Mytella Mussels columbiensis), zone intertidal west the in diversity Guayas river. Many of least the dominating species the are: Large oyster and of Mangle (Crassostrea Bridge Portete in is species of to belong Brachionus longispinosus, identified: been have species zooplankton Alonaplicatilis, cambouei, Moina micrura, Mesocyclops longisetus, Pseudodiapto following The area. the in predominant estuaries of isopods, systems the to related are which prototozoeas of stage the in amphipods, observ be mysidaceans, can larvae peneid of presence The found. also are cladoceransare porcelanidos, anomuros, of the most abundant. Copepods cirripede larvae, zoeas of brachyuran and carideos, zoeas Bryozoa, Annelida, Nematoda, Porifera, Cnidaria, within such arthropods, copepods and estuary biomass of the Gulf comprises Zooplankton (Sciur Squiller as: such found, be will found, instead small mammals or mammals that live in close contact with human beings intervened, deeply areas in located represent are studyof areas the in reptiles found The mexicanus). (Himantopus cuellinegro Cigüeñelo similis), (Myiozetetes Cinnamomeus), (Furnarius Aestiva), (Dendroica Warbler (Brotogeris thula), tierrera dove buckleyi), (Columbina (Crotophaga Yellow Cowbird sulcirostris), parakeets coelestis), pyrrhopterus). The following (Forpus are the ornithology bodies identified: nivea heron (Egretta viviñas threaten only The pyrrhopterus). nubicola), (Glaucidium owl pigmy cinnamomeus), (Furnarius ovenbirds bernardi), (Sakesphorus collarejo batará Laridae, wren Anatidae, bandeado Ardeidae, groups: families the Fregatidae, Pelecanidae, Phalacrocoracidae, among others. Between endemic including birds are: basin, river Guayas Lowlands Western in located deciduous is study of area the (ornithology) birds of case the In altitude. in m 300 exceed not do relieves highest the where topography, coastal mo North the by interrupted only is which fromdistributed bay Caráquez forming toTúmbez a variable (20 width strip to50 Fauna: and many would adapt ofthese other orseek species housing places tosurvive. the Therefore, reproduce. and alteration of feedthe flora would cau that species fauna of number endless an houses level of flora, some species are endemic in the area and others are introduced; this flora n Gastropod and T he study area corresponds thesouthwest to tropical zoographic whichis belt;

Bivalve, untain range. This belt is characterized by a dry climate and a flat and waved forests. It is known that more than 80 species live in this location of the of location this in live species 80 than more that known is It forests. MENTALAND SOCIAL

in the project area project the in and Acartia and

Cmyohnhs acau) Plm terr (oub buckleyi), (Columba tierrera Paloma fasciatus), (Campylorhynchus

and 4 belong to Gastropods. The greatest abundance and diversity and abundance greatest The Gastropods. to belong 4 and and Millonaria and

ce Hpis irlps, i (troyu arenatuss), (Sternopygus Bio microlepis), (Hoplias iche (Cerithidea mazatlanica). Among the main fish species, the the species, fish main the Among mazatlanica). (Cerithidea

tonsa. Regarding malacofauna, 11 species are reported, 7 reported, are species 11 malacofauna, Regarding tonsa. ite cattle little

(Thraupis Episcopus), Jacanas (Jacana Jacana), Homer Jacana), (Jacana Jacanas Episcopus), (Thraupis se a direct affectation to the existing fauna of such area

ed species is the Grey the is species ed comprises

h that is the reason why large mammals will not be not will mammals large why reason the is that embra (Poecilia sp.). (Poecilia embra other biological groups such as us stramineus), domestic Cats (Felis silvestris). (Felis Cats domestic stramineus), us more than 50 ed by iguanas (iguana). The areas of study are study of areas The (iguana). iguanas by ed -

W ges Bblu ii) Sca Mosquero Social ibis), (Bubulcus egrets est belt extension that corresponds to the the to corresponds that extension belt est of of arthropods and protozoans. and arthropods HAZENAND SAWYER, Brachiopoda,

percent - cheeked parakeet. (Brotogeris parakeet. cheeked

The

in project area project arthropods. Inarthropods. addition,

and Chaetognata are are Chaetognata and P.C . | . CONSULAMBIENTE :

Appendicularia, Appendicularia, ostracods, followed

has a good a has March 2015 March The lower lower The ed mainly ed PAGE

mus km)

and 21 by of

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 6 ESIAExecutive Summary .4

● ● ● ● ● ●

in late afternoon and at n Huerta Pasaje 53 west, with permanent Popular Education and fiscal support; it operates Neruda Pablo 2) su fiscal and Education Avenue Huerta Clemente 1) WWTP: this Education satisfies needs alternatively. 73.2 percent 2.23 remaining the while places, the service. Coverage of electric power service reaches 97.77 96.4 serviceis garbage collection coverageof of level domestic of water through a public network, 7.7 water percent meter. 92.10 1.9 remaining the and meter water a have they states of 1.72 network, supply 97.77 which from service, Services Basic Cemetery, General Neighborhood, Peñas Library.Vicente andMunicipal Rocafuerte School, Las Hospital, Vernaza Luis mentioned: Heritage Cultural indoor and volleyball. indoor practice to practice court sport a with area green small a is there to Cooperative, Cooperative Neruda Recreation Andrés President). Rodríguez, “Miramar”“Carlos 3) Cooperative; Cooperative (Mr. Cevallos” Gámez, President); 2) WWTP, Esclusas Structure Community percent (50.52 men in divided is population The 659,399. = year) 2042 for Population Future and Current Socio it operatesit inthe morningan at southwest Coop. Pablo located Neruda east, with a regular Center, type of education and fiscal Education support; Basic 76 Number Cordero supply,

economic and cultural environment percent , it ,

). The average age is 45 years). The average is45 age has an electricity power meter. Coverage of fixed telephone service reaches service telephone fixed of Coverage meter. power electricity an has

f oss ae anae cleto srie Rgrig ipsl f se of disposal Regarding service. collection rainwater have houses of Suburban was evidenced that 92.1 that evidenced was

and 0.51 and : :

MENTALAND SOCIAL

T

26.8 . wastewater percent There is a green area green a is There hree educational establishments are identified in the area of influence of of influence of area the in identified are establishments educational hree

:

Pablo Neruda Basic Education and Literacy Center 2, located at Raúl at located 2, Center Literacy and Education Basic Neruda Pablo In the area of the project, 97.94 project, the of area the In

ai Euain n Ltrc Cne 1 lctd t al Clemente Raúl at located 1, Center Literacy and Education Basic their representatives are: “Lorenzo Tous” Cooperative (Mr. Rafael (Mr. Cooperative Tous” “Lorenzo are: representatives their

District Ximena of Guayaquil:

percent :

percent

of houses haveservices.Inof houses sewersystems sectors, 92.78 northern

percent mn t Among pport; it operates at night and is attended by men and women; and men by attended is and night at operates it pport;

: ights and is attended by women only; Lorenzo3) Tous Febres disposal by latrine was found, representing 0.2 representing found, was latrine by disposal

mn sca organizatio social Among

ubr Psj Southeast Pasaje 2 Number percent

ak ti srie hwvr te s o mbl telephone mobile of use the however, service; this lacks

is provided by tankers. 98.1 tankers. by provided is d is attended by men and women by men d isattended

is provided by a communal basin which is an alternative an is which basin communal bya provided is

e ot emblematic most he

: percent percent

with a sport court in good conditions in the Pablo the in conditions good in court sport a with The projection of population for the period period the for population of projection The percent public the by provided is water houses studied of .

of the researched sample evacuates sewage evacuates sample researched the of lacks this service. On the other hand, 99.2 hand, other the On service. this lacks

by the use of septic tanks and only one case - otal n vlebl. n Miramar In volleyball. and football HAZENAND SAWYER,

percent 2010

percent s dniid n IA f Las of AIDA in identified ns

percent places,

(base year) 546,254; 2042 (end

2 wt praet Popular permanent with 12A

of houses have potable potable have houses of percent

percent a Ecua 1, 3 alley 53 14, Esclusas Las

percent

reports they lack a water water a lack they reports

, while 3.6 while , h floig a be can following the

of researched ho researched of P.C ) and women (49.48 women and ) . | . CONSULAMBIENTE

of the considered

percent percent March 2015 March - football PAGE 2011

water . The . wage lacks lacks uses 22

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary ● ● ●

sanitation conditions. Once the project is constructed, services coverage will be be will coverage services constructed, is ge impacts environmental Regarding increased. project the Once conditions. environmental sanitation improving benefited, is Guayaquil of sector southern the and project t all high; are project the by generated thebenefits The populationconsiders eliminating inthe sector. contamination existing the population. Inhabitants consider that the construction of the new WWTP will allow emanate which Cooperative, Neruda Pablo the North Guasmo sector. Currently, there is a wastewater treatment plant located at the constructionLas projectinhabitants on WWTP Esclusas high is inthe Cooperatives of of interest and participation of Levels devaluation oftheir properties. 70 and condition this to due devalued be may lands their considers odors unpleasant to exposed population 16 and winter 84 environment, the in odors unpleasant perceive 14 barely From and night. at afternoon intensity greater the is in there indicated place takes odors such of level highest the 63 morning, the in intense more are odors such estimate area, the in happens weekly. 36 however, daily; place takes odors of perception indicates 64 hand, other the On intermittent. 30 whils arepermanently perceived, odors considers water. sewage to due 54 are that odors unpleasant determined was it population), the of th group human the From environment. the 67 remaining the area, 33 that pointed Odors of Perception windows. 2.41 prevails, iron which in others, percent follo the homes, of windows the in used materials cane and 17.53 43.13 hand, percent 1.55 properties with some kind of business. Regarding finishing of visited of houses, we find 94.6 residential, percent 75.26 city, 1.72 and housing 18.4 family, Housing otold o eue h efc o te eeomn o nor of development the on effect the reduce be to will and Plan, temporary controlled be Management will works Environmental of execution an the by applying caused troubles by therefore, mitigated be will these works,

percent

of houses has aluminum windows whilst 14.26 ceramic and 4.47 s nla ri ecag o aig aeo h os.Ms fhue are houses of Most house. the of care taking for exchange in or loan on is :

In the area of the project, 76.46 project, the of area the In

percent

MENTALAND SOCIAL

percent

of floors is ground, 44.67 ground, is floors of percent

percent percent percent

Twenty

percent percent

of families are owner of houses. 20.79 houses. of owner are families of

of doors is made of wood, 38.66 wood, of made is doors of

:

s osiue b dprmns 3.78 departments, by constituted is percent

The analysis of perc of analysis The corresponds ironcataloged to Regarding as inthe study others. percent the in areperceived odors unpleasantassures population the of

-

as hs apn i summer. in happens this says wie h rmiig 5.4 remaining the while ;

three percent percent lives in rooms, which house one fa one house which rooms, in lives

believe the presence of odors is not the cause for the the for cause the not is odors of presence the believe indicates they have not perceived unpleasant odors in odors unpleasant perceived not have they indicates another material

percent

percent

of people, wh

percent he population of the area of influence of the of influence of area the of population he the community the

s unpleasant odors and negatively impacts impacts negatively and odors unpleasant s percent at assures odors are perceived, (33 perceived, are odors assures at 2.06 and plastic eption of odors in the involved population involved the in odors of eption

of inhabitants of the surveyed sector, sector, surveyed the of inhabitants of

nerated by the construction process of of process construction the by nerated HAZENAND SAWYER, is cement, 13.92 cement, is

t 70 t percent percent corresponding to vinyl. On the other

population group which assures to assures which group population percent of houses is occupied by only one one only by occupied is houses of wing results were obtained: 70.79 obtained: were results wing o have perceived unpleasant odors

percent percent

percent percent

:

f naiat i te sector the in inhabitants of hry percent Thirty indicates population the of

percent

Willingness and interest of of interest and Willingness

believes these intensify in in intensify these believes percent

percent

mily. In the north of the of north the In mily.

indicates these odors are odors theseindicates has wood, 10.48 aluminum, 0.69 aluminum, shared is properties of

percent a atvte o the of activities mal

percent

P.C are renters and 3.95 and renters are

of homes has cane has homes of

. | . CONSULAMBIENTE

percent y multi by

expressed this this expressed

wood, 35.40 wood, f h total the of March 2015 March

considers considers

PAGE percent percent percent percent - family 23

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 The following wastewater forceand treatment plant, main, execute to required activities and steps includes phase This 7 be applied, pre developed, are actions T 7 Listed below is a detailed description 7 impa actions by The determination, 7.1 7. ESIAExecutive Summary .2.2 .2.1 .2. he phase where all where phase he

the

● ● ● ● ● Environmental ●

cts based on

project performed using the using performed project

of Foundation and the above levels finished recordedmaximum floodlevel. with platforms different create to installed be will matrix matrix in the terrain to improve its qualit columns gravel a building in consists which vibrosustitution, using improved be will terrain the location, WWTP the in soil the of characteristics geotechnical poor the and the to Duepreparation: andconditioning Terrain of works tobe performed. structures. performed Lay and Leveling workers providing construction, comfortableareas during activities administrative Install Description of Identifica pump for favorable is community forcestations, the by acceptance project the Thus, population. vcain of evacuation mechanical machine by Excavation to develop the project with environmental factors, to further define Staff hiring: refer hiring: Staff Construction Phase Pre soil stratasoil - Construction Phase ation - activities feasibility, among others. tion and Assessment of Impacts

assessment

considering and Social assessment, shovel, MENTALAND SOCIAL , of

construction construction administrative procedures administrative Primary Project Phases main, aeil rm xaain il etasotd y up rcs o sites to trucks dump by transported be will excavation from material

otatrs il ofc ad shop and office field contractor´s plus any other aspect related to related aspect other any plus p

are Pumping and for WWTP: scheduled Stations iling: . s

to hiring to front out: out:

and WWTP. and

Impact criteria and ofmagnitude importance.

t that that

he results of soil studies performed show that due to conditions and subsequent categorization of any impacts potential caused - : l

end

yn ot xs n srcue leveling structure and axis out aying of e the area of area the cause xcavation of soil using equipment such as as such equipment using soil of xcavation

foundation piles are slabs and required. professionals of of

loaders,

all actions related to

-

effect sub fluvial

and other type of of type other and

implementation of WWTP is a site with lifted with site a is WWTP of implementation before the execution of the of execution the before y. aAdditionally, compacted backfill over the analysis

and

workers HAZENAND SAWYER, outfall. the development of of development the

partial floodable condition of the site the of condition floodable partial method : the implementation of the project. a atto o sae t develop to spaces of daptation the project the

for execution and supervision and execution for road equipment required; equipment road , which

allow ti wr wl be will work this ;

P.C civil

the the consequence of w . | . CONSULAMBIENTE systems design to to design systems

orks and project and orks

with safe and and safe with ed w orks

interrelating March 2015 March , backhoe

PAGE such as such the 24

,

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary ● ● ● ● ● ● ● ● ● ● ● ● ●

systemsaccording be to the useddesigns. protection fire other and hydrantsincludes also plant, treatment to areas operating and for Installation hydro of power supply network, system electric of Installation the into filtration wastewater prevent ground. to chemicals using tanks: of Waterproofing Formworkand cast structures preventive ensure maintenance operation. proper to activities; other and compaction soil Maintenanceand of operation equipment on accessstructures. routesand various bed: concrete Placing vibratorycompactor plate or backfilling: Compacted an excavation activity until tosoil foundation related level. directly pre safety Constructi wastes for properortreatment. toqualifiedoperators transport Transport of hazardous wastes: includes activities transportation of non non of Transport Materials transport trucks the to Evacuation of excavated material to cannotexcavation. complete the used are tools to complementary small hand: by Excavation law. by approved storm water storm

caution and part of the retaining wall construction construction wall retaining the of part and caution

on MENTALAND SOCIAL

site Illustrious of sheet pile and perimeter walls:

conveyance, approved by Municipality. : - h ecvto b mcie n i promd hn h machine the when performed is and machine by excavation the aadu sld n lqi wse: opie dlvr and delivery comprises wastes: liquid and solid hazardous materials - - sanitary facilities sanitary hazardous wastesmanagementhazardous tomunicipal system s pilled of pumpab of pilled

lighting system, andtemporary ofsupply.lighting installation power Municipality of Municipality c mato o ntrl ol or soil natural of ompaction frog

: used in the work pipes for wastewater discharge from the administrative the from discharge wastewater for pipes : installation of electrical panel electrical of installation :

s pilled ofpilled ready

: .

the evacuation of this material is performed by dump

: includes the development of drainage developmentof : includes the such

Guayaquil, and the hours stated by applicable applicable by stated hours the and Guayaquil, le ready le : o peration ofperation machinery excavation, used for

machinery - s are mixed concretemixed structures. building for HAZENAND SAWYER, heet pilling with - mixed concrete to be used as coating as used be to concrete mixed

focused on the delivery of hazardous

transfer use.for tothe their site

om h wls ti atvt is activity this walls; the form

is

backfilling subject to corrective and and corrective to subject process of the slopes and slopes the of process s

for equipment control, equipment for metallic P.C

. | . CONSULAMBIENTE

material using using material

. element

March 2015 March facilities facilities PAGE s

is a 25

IMPACTASSESSMENT LASESCLUSAS ENVIRON and equipment. comprised is phase O:This \410827 -000\WPDOCS\TECH-MEMO\TM1 mentioned above of construction the During InForce the Main ESIAExecutive Summary .2.3 ● ● ● ● ● ● ● ● ● ● ● ● ● ● ●

waste for treatment toqualifiedand proper transport operators Transport of hazardous wastes system. non of transportation non of Transport evacuatedare and pipes submerged. points and Drag through D locationPipe purpose. outfall the the bottom of the water body, which are pre Development and transport main installation. Tr proper or transport treatment. wastes hazardous of Transport hazardous waste toMunicipality produced system. management Transport of approveddisposal site themunicipality. by excavation Remov others. among equipment, of maintenance e be tothis must made removal and entry site, such tasks for main force the of process construction Loadequipment o the to according pipes, the locate construction methods. to order in tunneling or trenching for machinery Install Open trenchexcavation along of theinstallationsite theflow pipe locatedof at different sites is performed at points of entry and exit of the above equipment including strategic sites Mechanical excavation of wells be performed: recommended methodologies for building force main, one of the following actions may trench of Excavation ead weights Operation and Maintenance Phase ansport and install ation of al eie acrig o studies to according defined

high The main actions beThe to developedare main described below: ,

immersion of pipes of immersion will be performed bewill : transport, construction

are collected are MENTALAND SOCIAL

- non

pressure fixing drilling and excavation equipment:

-

of the steps of flow of steps the of hazardous hazardous solid and liquid waste

perati -

aadu sld n lqi waste liquid and solid hazardous :

ation the n dsoa o waste of disposal and weights are located at the respective points and es and es

- air.

aadu waste hazardous

on on will start, will subfluvial outfall outfall subfluvial

with

of pipes

and the area ofimplementation of dead weight:

, wells

together with the with together : pipes are transported superficially using vessels to the to vessels using superficially transported are pipes :

: includes activities focused on the delivery of hazardous : delivery of hazardous waste hazardous deliveryof : equipment and equipment maintenance

for entry of drilling and driving equipmen : location of wastewater flow pipes at the site of force

under the support of specialized of support the under in natural ground or paved roads: paved or ground natural in quipment, asrequired.

and external services, flow and internal services, services, internal and flow services, external and

performed s

rdcd to produced it is expected that expected is it

-

developed developed and transported to the site where dead weights are used s :

this typethis equipment beused will of inthe rm excavation: from then following: HAZENAND SAWYER,

installation installation of equipment and drilling . s

: delivery and transportation of non Subsequently, the injected air is is air injected the Subsequently, transported

as area the force of main. the

s location of pipes in the right the in pipes of location

:

rvnie n corrective and Preventive uiiaiy man Municipality s

comprises to qualified operators for operatorsfor qualified to some common activities common some .

in dump trucks to the to trucks dump in wastes

s and routing water. s and P.C for for fixing the pipe at

equipment for this this for equipment the pipe is injected . | . CONSULAMBIENTE

a ccordin

eutn from resulting eiey and delivery t ; this activity March 2015 March

agement g to the the to g PAGE 26

-

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 In theWWTP In theWWTP In Station thePumping ESIAExecutive Summary ● ● ● ● ● ● ● ● ● ● ● ● ●

to metallic parts of the structures metallic of Maintenance maintenance integral piping including parts. replacement theof of consists structures: mechanical of Maintenance slud among others. blowers, as such units treatment primary the equipment in operating equipment of maintenance and Operation conducte wh unit, settling a to separation of particles. thesolid process and dosing Chemical particlessolid storage Chemical to m of Maintenance including parts. replacement of structures mechanical of Maintenance bewill collected and for deliveredtransport tothe municipal system and disposal. transportation and Collection to respectivegrit classifier. separatewill grit contained inthe particles which Chamber Grit Vortex a by performed process removal: grit and Classification in order toseparatecoarse thesolids. spoil of classification and Screening replacement maintenance piping for performed mechanical of Maintenance procedures both for performed includes equipment: of maintenance and Operation Removal of solid particle by settling:

metallic parts of the - -

will be perform be will PrimaryTreatment Pretreatment d

to the sludge treatment system. MENTALAND SOCIAL

of from wastewater.

parts. :

: etallic structures etallic a

ppropriate storage sites of chemical used for flocculation of the of flocculation for used chemical of sites storage ppropriate

:

r te upne sld atce wl peiiae ad hn are then and precipitate, will particles solid suspended the ere

influent mixing: influent screening flocculation andsettling ed

:

to the wastewater within the flocculat the within wastewater the to

of

structures:

preventivecorrective and maintenance.

and screening : : includes maintenance procedures to be performed be to procedures maintenance includes : includes maintenance procedures to procedures maintenance includes s the within embedded grit removal

:

a

includes actions aimed at aimed actions includes fter addition of floccula of addition :

c

s hs ciiy nlds l atos ht are that actions all includes activity this

nit f h ppn itga maintenance integral piping the of onsist flocculation, water be tr to : all material retained by the screening unit unit screening the by retained material all : includes maintenance procedures for for procedures maintenance includes : units HAZENAND SAWYER, units units .

pumping stations operating, and operating, stations pumping that comprise the pre

wastewater will be transported eated tion upn sain including station pumping , and then are transferredand thenare

substances screening P.C ion . | . CONSULAMBIENTE

tank to achieve to tank

b e performed e and mixing and wastewater - March 2015 March ge pumps, pumps, ge treatment. PAGE

27

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMOIn the \TM1 Inforce main the In the Inwastewater plant the treatment ESIAExecutive Summary ● ● ● ● ● ● ● ● ● ● ● ● ● ● ●

su WWTP oioig f icags cmrss h poeue fr h dvlpet f water of development the qu for procedures the comprises discharges: of Monitoring form the consists parts: mechanical of Maintenance maintenanceof the force proceduresmainand its the of Maintenance metallic parts of thesludge treatment units. maintenan structures Metallic consists including parts. replacement of structures: metallic of Maintenance sludge management belt including press. Operati landfill anddisposalinmonofill. disposal sludge and Transportation the addition ofpolymers. Dewatering process. Sludge storage cogenerate electric power. anaerobic digesters. In that process biogas will be also produced, which bewill used to Thickened SludgeAnaerobic the sludgewatercontent. and transported by pip evacuated be will units settling in sludge transportation: sludge and Thickening to metallic parts of the structures metallic of Maintenance including parts. replacement of consists structures: mechanical of Maintenance waterrequired concentrations; at dosingautomatically. the isperformed ( material Hipochlorite Sodium hazardous sites. and products generated of transportation H and Handling b y fluvial alityat monitoring outfall discharge subfluvial sitesof pochlorite

- on and maintenance of equipment of maintenance and on

Sludge treatment units

sub fluvial outfall :

and and eventually delivered by

MENTALAND SOCIAL of Digested Sludge: The process The Sludge: Digested of

) : : the the hypochlorite solution Digested Digested :

es

outfall includingoutfall diffusers. to dosing atwtr collection wastewater disinfection the

sludge will be stored before being subjected to the dewat

- sludge

Disinfection : Digestion: After thickening the sludge, it will pumped toDigestion: After thesludge, will it thickening Sodium Hipochlorite solution solution Hipochlorite Sodium ce: includes maintenance procedures to be performed to to performed be to procedures maintenance includes ce:

:

thickening : includes maintenance procedures to be performed be to procedures maintenance includes :

: units includes transportation of sludge to the municipal the to sludge of transportation includes

proper proper vehicles and :

used for treated water disinfection shall be

: includes equipment maintenance used for for used maintenance equipment includes :

of maintenance procedures of piping that piping of procedures maintenance of tanks

is performed with belt press. belt with performed is and and

HAZENAND SAWYER, f h ppn itga maintenance integral piping the of components.

f h ppn itga maintenance integral piping the of that, by the action of gravity, reduce transmission transmission . directly directly placed at the storage

will be supplied to treated to supplied be will

P.C comprises network: . | . CONSULAMBIENTE

It demands demands It March 2015 March Sodium PAGE ering ering site site 28

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 7 7 done: scenarios: different operation. during three of occurrence of event and construction; during abandonment construction; of end the the at abandonment in developed be to actions Includes 7 ESIAExecutive Summary .3 .3 .2.4 .1 ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ●

Fauna habitat Changes dynamics inthehydric Flow changes Variationconditions inthephysical water Groundwater quality Surfacewater quality Drainage network quality Soil Removal of topsoil Ground table water Vibrations Contamination Changesand topography interrain Odor intensity Noise Gas particlesSolid Environmental abandonment toqualifiedproper operators activities for and transport treatment. by generated waste hazardous of delivery the of consists transport: hazardous Waste delivered collection system tothe municipal the for non equipment, and facilities Transport of non pathother repaired elements along with thatwer Readjustment of roads metho filling Wells transported to the waste other and spoil materials, of Removal re machinery: machinery construction. used during and equipment of Removal the camp: Removal of work Biostability Migration of organisms Flora habitat Bio Abandonment field emissions -

Geophysical factors dology, be should oncefacilities refilled abandoned. havebeen office.

Generally, in any of the proposed scenarios the following activities may be be may activities following the scenarios proposed the of any in Generally,

MENTALAND SOCIAL

wls or wells :

(

runoff and Social

by waste liquid or solid

-

hazardous hazardous solid and liquid waste:

disposal site

)

:

once v trenches

Factors Considered acate, remov w -

hazardous solid waste can be produced which must be be must which produced be can waste solid hazardous ells and trenches have been re

xaae, codn t te eetd construction selected the to according excavated,

al and retirement of all elements that are of all part elementsretirement ofal that and s

in the s moving moving :

a HAZENAND SAWYER, e modified duringconstruction. e ll waste ll Assessment ir transport to the disposal site. ir transport tothe disposal a s a result of from s

produced are collected and and collected are produced filled, roads are paved and h ae eupet and equipment area the

the dismantling of the P.C . | . CONSULAMBIENTE

abandonment abandonment March 2015 March PAGE

29

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\410822. -000\WPDOCS\TECH-MEMO\TM1 1. Below the aof is description 7 werefollowingclassified the under categories: impacts environmental applied, approach to according and considerations these account into negative. or positive are they whether environment, the in incidence high of impacts impacts insignificant indicate 1 this to identify and assess environmental impacts according The impact assessment processwas perfo 7 7 ESIAExecutive Summary .5 .4 .3

.2

rud o cntutv proe, s well structures as purposes, constructive for ground during the construction stage due to activities aimed at improvement and preparation of the experienced existing and topsoil alm or of lower a construction main force removal During vegetation. the require will planned, are others among depositing, concrete fills, placementof excavations, as such tasks or topography preliminaryworks where ground and terrain in changes and topsoil of Removal ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● generatedwhich the of stages operation and construction during waste liquid or solid by Contamination approach

R Ben Insignificant Significa Highly significant Assessment and Energy consumption oflandsExpropriation D Communityurban services and facilities Road Health and Health and creationJob Revenuesexpenditures and Perception of theProject Inconveniences causedcongestion. byandurban traffic etc. Destruction or alteration of existing quality of life related to cultural, historical aspects, Destruction of Destruction or alteration esults of the Environment a Socio mages infrastructure tourban eficial

, infrastructure .

an impact can reach a maximum valuecanan impact reach of aof 10and maximum minimum 1,values close to e conomic Factors

nt u t te ra environment urban the to due

s s

MENTALAND SOCIAL

afety for residents afety for workers afety for

can n categorization of impacts atural systems caus

.

princip e

visual and visual

of landscape n o ls ifune t te otay vle oe 65 are 6.5 over values contrary, the to influence, less of and

and Social for thepublicsector a

l potential

r health health med Impact Asses

s by

I general, In .

: significant negative oftheproject: impacts

impacts. as the implementation of foundations for for foundations of implementation the as As a result of various activities performed performed activities various of result a As using p roject, different types of waste will be will waste of types different roject, their

HAZENAND SAWYER, cause

For this reason, this aspect becomes aspectbecomes this reason, Forthis sment

magnitude and importance. the - ost no ost effect matrix / Leop effect matrix /

ol rfl wl b affected be will profile soil : significant significant

T he preparation of the the of preparation he P.C . | . CONSULAMBIENTE effect will be will effect o March 2015 March ld Mat

PAGE Ta

Under king king r

30 ix, ix,

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 5. 4. 3. ESIAExecutive Summary

E protection safety. pedestrian implements and measures Plan Management Environment the extent the to “insignificant” drilling. and/or excavations during caused vibrations roads. these of condition Huerta sites specific at excavations vibrations. and and construction system the to related are they because “insignificant” as considered are damages such However, transportation waste of route main the along people of life congestion traffic and urban by caused Inconveniences odors. ha safe their with along achieved be will wastes process. treatment wastewater during produced sludge co the primary for of stabilization achieve to order allows in systems cogeneration and digesters anaerobic design project The area. industrial adjoining theWWTPor theimmediatewithin surrounding area as thesite locationin is an operation project during biofilters system treatment from removed wastes of disposal and transportation collection, equipment, and facilities Generation Odors operatio and earthmoving include undertaken be equipment andmachinery. to activities the because stage damages will be only temporary. althoug likewise, operation; their levels do not reach the values need project. the of stages different sound Increasing magnitudeand thereforerepresents impacts “insignificant” for theenvironment. combustion I factor.Management actionsthis monitor to shall implement Plan tempora a limited. be being would effects However, its dispersion, health. population’s the on effects cast works, construction of produce theproject, will particulatematter (dust) w preparation site’s works, gases, combustion dust, of Generation Management Plan. one ofthe important controlandtherefore points beconsidered should inthe Environment iial, n h oeain tg te rnpr o boois il ae n des effect adverse an have will biosolids because of transport the stage operation the in Similarly, t is t S MP includesMP traffic management. estimated

.

These works will temporarily alter the traffic around the sector and modify the the modify and sector the around traffic the alter temporarily will works These of

the the

of machinery and equipment and machinery of

cargo vehicles vehicles cargo that that MENTALAND SOCIAL During

.

(noise) (noise)

oee, dr wl b efcety contr efficiently be will odors However,

: during the construction phase gases phase construction the during

Odors could be generated during procedures of maintenance of of maintenance of procedures during generated be could Odors

the the are temporary are levels is considered is levels

Existing urban infrastructure could also be be also could infrastructure urban Existing construction stage the installation of force main force of installation the stage construction hge lvl wl b peetd uig osrcin stage, construction during presented be will levels higher h in the avenues the in which

However, it is classified as classified is it However,

In general, these activities will be te be will activities these general, In The The higher effect of this factor

.

transport these materials must pass through common through pass must materials these transport lo hr ae o eieta aes immediately areas residential no are there Also .

ed The impacts are related to the generation of noise of generation the to related are impacts The

noise,

t s ot mninn ta te Environmental the that mentioning worth is It to cause discomfort to the population during the used concrete, 14ª SE, Adolph Simmons Simmons Adolph SE, 14ª as the impact most likely to occur to likely most impact the as .

and vibrations and This impact has been considered of low of considered been has impact This ndling with a lower level of level lower a with ndling HAZENAND SAWYER,

n ecvtos eurd during required excavations and

oee, hs ipcs il be will impacts these However,

nsideration and and nsideration hs te tblzto o these of stabilization the Thus, will be will

: “insignificant” impact because impact “insignificant”

it is considered that considered is it le b oo etatr and extractor odor by olled could focuse :

generated as a result result a as generated Conducting preliminary Conducting y mat n o low of and impact ry hich can causehich can be adversely affected. adversely be mporary. P.C s

and on on the construction . | . CONSULAMBIENTE fetd y the by affected

osrcin of construction Raúl Clemente Raúl

w The Project Project The unpleasant March 2015 March

ill require ill quality of of quality

harmful harmful PAGE during n

31 of of

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-00012. \WPDOCS\TECH-MEMO11. \TM1 10. 9. 8. 7. 6. ESIAExecutive Summary

Expropriations of land: of Expropriations of technical, integrity the safeguard to measures proper establish shall Plan Management Environment as activities operational Health and urbanthe visual component environment of be will Destruction or alteration of landscape areas be will affected by occupied expansion, not urban certaingroups which organisms include b of of among habitat fills, others), piling,placement ofactivities and excavations, (foundation intervened. environment the of conditions biological the on cause “insignificant” impacts on terrestrial and aquatic flora, placement of fills during the construction habitat of structures and installing flora and fauna of Stability impact “insi is However, activities these of nature the sediment minimize removal. will which methods immersion other or dams type trunk temporary using considers outfall the of installation the for implemented be to method construction Cobina in especially materials, of transport and removal sediment to due River, Guayas of water quality to damages case Surface water quality signif system. adverselyWWTP,affectingtreatment the the to units. treatment the discharge in obstructions sites, possible population, by habits consumption water in changes I WWTP and force main can ca network Drainage effects byprocedures becontrolled construction should toavoi proper groundwater table. and ground affect would construction plant during performed excavations could table groundwater and quality Ground The truck route established will uponsafety for based transport issues also routes. transit which is dedicated to shrimp farming, while another lot of 1.5 hectares belongs to Radio to belongs hectares 1.5 of lot another while farming, shrimp to dedicated is which seven the of Two uses. residential or economic have not do ha) (21.5 acquired be to land the of Esclusas WWTP will affect seven (7) lots accounting for a total 40.74 ha of land. Over 50% t is estimated that some situations wil situations some that estimated is t

icant from anicant environmentalviewpoint. from maintena lots will be impacted, with the 16.74 lot ownedN companylotbythe 16.74 the bewith impacted, will lots While these impacts are not considered to be significant over a broad area, broad a over significant be to considered not are impacts these While be altered as a result of result a as altered be

E

this risk is minimized by the limited existence of groundwater bodies, and the and bodies, groundwater of existence limited the by minimized is risk this xcavations or dr or xcavations s administrative, afety for workersafety residents: and

gnificant”. Stabilization of sludge produced in the plant is planned to minimize odors minimize to planned is plant the in produced sludge of Stabilization nce of the pumping station or wastewater wastewater or station pumping the of nce MENTALAND SOCIAL

: The scenarios mentioned above cause some variation in the inlet flow inlet the in variation some cause above mentioned scenarios The

Excavations considered by the the by considered Excavations :

It is anticipated that operation of of operation

In terms of expropriation and resettlement, the project for project the resettlement, and expropriation of terms In illing to the land will be required to install force main force install to required be will land the to illing

and operational and personnel u hs may this se alterations and breakage to the existing drainage network. w estuary orks of foundations and piling. and foundations of orks

treatment plan treatment l

: : be present during present be as cnaiain ik b sdmn removal. sediment by risks contamination cause where the ou the where

It t s siae ta promn wrs uh as such works performing that estimated is It is anticipated that : that irds, edaphicamong fauna,butonlyirds, others, in

h normal The

the Construction activities as excavations and excavations Construction activities as HAZENAND SAWYER, slightly installation installation t

are risk are p tfall roject for both the construction of construction the both for roject .

These impacts are not consideredarenot impactsThese conveyance, operation of the project the of operation will shallow g

affected.

eneral population. and its magnitude will depend

y during the construction stage

As a result of construction of result a As

activities for workers. for activities be installed. be of the

It is considered that the that considered is It rud characteristics ground a

WWTP WWTP

P.C

d sub fluvial pipe will and maintenance of maintenance and

contamination. . | . CONSULAMBIENTE ATURISA (lot 7) (lot ATURISA .

However, the However, outfall could

March 2015 March .

PAGE

such as such D thes ue to ue

The The Las

32

e .

IMPACTASSESSMENT LASESCLUSAS ENVIRON the of benefits Treatment existing the Among ecosystem. receivingconstruction stages, due to execution this O: of deterioration \reducing 41082set forth under the environmental legislation, which will be discharged into Guayas River, thus the -project the 000of purpose production of a the treated effluent with physical, chemical or b being WWTP, the of operation \the and during magnitude WPDOCS occur higher importance of impacts positive the that shows performed analysis the Likewise, \TECH7.6 -MEMOWastewater Treatment System \TM1 and Operation “Construction, impac negative general, In 13. ESIAExecutive Summary

WWTP WWTP the land is the only impact on this shrimp farm as it is anticipated that the operations of the the affect adversely not will expropriat The operation. commercial large a retains expropriation who operator the of livelihood the Thus acquired. land the in operator the 7) above As mentioned will conform with the provisions of the World Bank’s Policy on Involuntary Resettlement. Remedial the Plan in Action outlined Resettlement measures the of implementation the With identified. gaps the address to taken has client the that measures additional the and Resettlement, Involuntary confo process expropriation the which to extent the secondary explaining prepared of been has Plan implementation Action Resettlement future Remedial separate the A for treatment. used be will and process expropriation an nece is It lots. the of distribution the shows below graphic CENIT (lot S.A. 4) which has an antenna and a house where a female guardian lives . The . The agreement to expropriate included compensation for all the investments made by by made investments the all for compensation included expropriate to agreement The . Expected Plant, will notadverselywill impact viability. its Source

Project Benefits and sub fluvialoutfall), theand “increase sub ishighlighted. ofjobopportunities”

MENTALAND SOCIAL

: EMAPAG. : ,

16.74 hectares of an adjacent shrimp farm will be expropriated willbe farm shrimp adjacent an of hectares 16.74

s u t atvte promd uig ifrn sae o project of stages different during performed activities to due ts

, Figure Figure

the land acquisitio land the - Performance

Las Esclusas South Subsystem”Las Esclusasare of“insignificant” South type

6 of works to be performed (Force Main, Pumping Station,

. Lots affected by the WWTP the by affected Lots . 7

f a rdr Pm Sain fre an and main force Station, Pump Pradera La of n and resettlement taking place on this site this on place taking resettlement and n

HAZENAND SAWYER, rms with the World Bank Policy on Policy Bank World the with rms iological parameters within ranges ssary to note that lot 7 is under under is 7 lot that note to ssary

P.C . | . CONSULAMBIENTE

March 2015 March PAGE ion of ion

(Lot 33 .

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\4. TECH-MEMO\TM1 3. 2. 1. significa In general, various activities included in the construction and operation phases would generate ESIAExecutive Summary

effluent that forth treated quality water river’s the to Improvement degradation. management proper Additionally, WWTP enable of equipment and structures of maintenance preventive hand, other the On contamination by waste liquid River Guayas the wastewater treatment system, effluent will as be such practices, management d of Control of noise and vibration. storage chamber the in Pumping Station will be less frequent, thus avoiding generationthe upstre capacity piping the therefore, conditions, tide to subject be not will Station Pumping The city the systemoverflow andwastewaterwould be therefore the avoid. of of sector southern the of population the from discharges global Likewise, season. in peak flow sanitary times (2) two to up and season dry in peaks sanitaryhandle to the of discharges of Reduction/Eliminat that they insummer. increase Eighty 14 and afternoon the in strongest are 64 morning; the in strongest are odors that believe residents of perception is daily and 36 percent the the system operation. biofilters tra collection, equipment, Reduc will be greater than 5 mg/l, if the WWTP is operating, value required for the development the forrequired operating,valueis WWTP the if mg/l, 5 than greaterbe will of Quality Environmental and receiv the of quality water the area of area nt, positive impacts, amongwhich impacts, thefollowing arent, positive highlighted. by am will be will am

system, because the new pumping station and WWTP will have sufficient capacity sufficient have will WWTP and station pumping new the because system, -

tion of odors of tion proper operation,proper avoiding incidental discharges

four percent four effluent

ad ht dr ae intermittent. are odors that said

envir and study determined that 30 that determined study

historically

raw odor extractors odor netl legislation onmental shre ad at generation waste and ischarges MENTALAND SOCIAL

whose

. This would This . greater implementation sewage Guayas into decrease River will considerablywith the operati

of residents ensure that odors increase odors that ensure residents of

o o overflo of ion

in La Pradera PS Pradera La in For this, it is worth mentioning that the opinion survey the opinion that isworthmentioning it For this,

physical, chemical or biological parameters biological or chemical physical,

has .

ns percent Having a higher capacity, pumping capacity, higher a Having portation and sludge disposal may generate odors. generate may disposal sludge and portation been discharged into the natural environment,

are planned to be installed installed be to planned are . ing

Duala comply with applicable law applicable with comply

said that the perception is weekly. body. f h project the of controlling illegal connections and implementing a a implementing and connections illegal controlling . w

of sludge is a basic factor to prevent environment environment prevent to factor basic a is sludge of

percent - This o wseae i te streets the in wastewater of s Guayas Rivers” indicate that DO of receiving body body receiving of DO that indicate Rivers” Guayas

percent

: Likewise, studies on “Hydrodynamic Simulation “Hydrodynamic on studies Likewise,

Activities such as such Activities Sixty il lo impro allow will

: of people perceive odors permanently and permanently odors perceive people of

of good condition Implementations of the project will result in result will project the of Implementations

- indicated that they are stronger at night. night. at stronger are they that indicated or percent four

enables : HAZENAND SAWYER,

t s assumed is It of water

in h mngmn o wast of management the

order to reduce this impact this reduce to order eet to vement in winter and 16 and winter in

maintenance of maintenance and reduce t reduce and f eiet si ta odors that said residents of and emptying and

before being discharged to percent without properwithout treatment.

,

Twenty are mrvn te sewer the improving

P.C

: by

the quality of of quality the . | . CONSULAMBIENTE The frequency of of frequency The believe that odors that believe within within

he he avoiding olwn best following - possibility of of possibility facilities and facilities

three percent conducted times of the of times percent

March 2015 March ranges However, PAGE ewater ewater losing rainy

said said will the 34 set set

on 70 in i

n

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-00010. \WPDOCS\TECH-MEMO\TM1 9. 8. 7. 6. 5. ESIAExecutive Summary

eeus n epniue fr h pbi sector public the for expenditures and Revenues be avoided. system and and treatment plant. operation of the Furthermore, the construction area. will and Health significant of arisingtheprofrom impact positive the development Government: Local the management of objectives main the facilities urban and services Community of the permanent Creation Job the sectorwith the agree quality of Guayas River for tourism and navigational uses. city. Guayaquil without treatment, which is reflected wastewater generated, improving health of conditions proj the of perception Citizen of contamination groundwater the prevent will others and tanks structures, concrete fills, contami compacted the avoiding on discharges of and possibility the surface limiting city, southern in population by generated conditions. physical c water ground and quality soil of Improvement stabilityand quality water in GuayasRiver. n Guayaquil will collection, proper goodquality Implement alsowill beavailable; notenter coliforms fecal intothe will receiving body aquaticcommunities. river of cancellation of specific require ompacted fill, cleaning, cleaning, fill, ompacted ormal development of the area’s flora. provide a safe a provide p roject. obtaining ation of and temporary employments sources employments temporary and

potential

, s

level level

afety for workers for afety whose of of all safety and security personal measures required measures personal security and safety all : ensure

MENTALAND SOCIAL p

n o te ot motn bnft o the of benefits important most the of One lo te rjc wl eal t rcvr adcp ad environmental and landscape recover to enable will project the Also, atwtr eeae by generated wastewater roject will be available various permissions and permissions various transportation, and an efficient treatment system will allow place

With these accidents accidents and discharge does not does discharge The operation of WWTP provides proper collection of wastewater of collection proper provides WWTP of operation The

effluent effluent delivery to the bodies of waterbodies

fees

p where all workers can perform their administrative tasks outside tasks administrative their perform can workers all where clearance roject. .

A dis A measures, : ain y iet infiltration. direct by nation ect

The i The

and unforeseen circumstances resulting infection system of the treated water prior to dischargeto treated waterpriorthe systemof infection : of debris of

in the improvement of quality of life The project will ensure will project The disposal of disposal in areas of in nstallation of work camp during construction stage stage construction during camp work of nstallation

The WWTP will have a direct benefit on the biotic represent risks represent in

high levels of production will be achieved the regularizationthe of all its components: pumping station, force : h p the

The project enable project The body body of water , etc. , during opulation.

implementation of theproject. implementation wastewater from the southern sector of of sector southern the from wastewater : ,

HAZENAND SAWYER, o provide to It is planned to perform tasks such as such tasks perform to planned is It in order to order in : population,

to the existing fauna.existingAdditionally,the to h pre The

construction and operation stages stages operation and construction In this regard, the inhabitants in the City to obtain

has has t s osdrd s h most the as considered is It an

p land use whichthe includeuse land right conditions permitting - s significantly poe mechanism proper a con Similarly, placement of of placement Similarly, oet s h ceto of creation the is roject

optimal treatment to the to treatment optimal

the fulfillment of one of of one of fulfillment the for the for and avoiding discharges ject. s rcin rcs will process truction P.C from the

. | . CONSULAMBIENTE construction and construction of of inhabitants of .

an effluent of improve project will March 2015 March

PAGE main, in the soil for 35

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH specifi - technical of eachbelow isprovided plan MEMO parties, responsible of indicators, means of verification, definition to \ refer TM1proposed operation, E compensating the environmental effects caused integrateby the execution of the that project during construction, programs or Components following figure: Assessment. obtained results on based safeguard Bank World applicable the forth The impacts oftheactivities relatedand tooperation maintenance ofthe WWTP impacts negative controlling plans, of series The 8 8. ESIAExecutive Summary .1

● Environmental ● Environmental Environmenta

in Prepared by Prepared mat o ec environment each on Impacts impacts of Mitigation operati and and administrative, Prevention for Plan E generation todisposal. i Wastes of Plan Management and Handling correcting oncegenerated. they them are mplemented in the in mplemented the Environment the S

MP Figure Figure n ipeetto sae o te project. the of stages implementation and

Environmental Management Plan Plan Management Environmental Component procedures, :

7

Hazenand Sawyer Ltda. Cía. &Consulambiente . Programs of Environmental Management Plan for Las Esclusas WWTP LasEsclusas for Plan Management Environmental Programs . of l Management Plan has been designed been has Plan Management l and Social MENTALAND SOCIAL

and Social and

Impact Assessment Subsystem of Subsystem Assessment Impact s

p n h p the in and actions focused on focused actions and roject to develop a correct and timely waste management from from management waste timely and correct a develop to roject Management Plan (E

soitd ih h Project the with associated :

Management Plan (EMP) is a management tool comprising a comprising tool management a is (EMP) Plan Management

deadlines, onal actions aimed at preventing and minimizing negative minimizing and preventing at aimed actions onal ir hpes f hs Environment this of chapters rior

’s policies.

opnn bfr te ocr ad iiaig or mitigating and occur, they before component

and costs.

S Therefore, each program has been designed designed been has program each Therefore,

has 9 programs which are detailed in the the in detailed are which programs 9 has P r amd t reducing, at aimed are MP S MP) .

preventing, eliminating, minimizing and minimizing eliminating, preventing,

nlds esrs n strategies and measures Includes A summarized description of the content

HAZENAND SAWYER,

niomna mtgto measures mitigation Environmental to take take to a wl a mxmzn positive maximizing as well as , .

the the nlds ehia, regulatory, technical, Includes Ministry of Environment of Ministry into account provisions provisions account into P.C ain, monitoring cations, n Social and . | . CONSULAMBIENTE .

correcting,

March 2015 March PAGE Impact

o be to

and and

36 set or or

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-are below: listed MEMOand 62 activities, while the operating stage (O) consists of 18 measures and 60 activities, which \activities 122 TM1th above, mentioned As 8 Resettlement, measuresgaps andthe toaddress additional required identified. to extent the the explaining which prepared been has Plan Action Resettlement Remedial separate A results Reference the has impacts environmental following of measure mitigation and/or prevention monitoring, Each ESIAExecutive Summary .2

● ● ● ● ● ● ● ●

, 8)Respons Measures of E to assess compliance Plan Monitoring Environmental structure, toreturn inorder including happen, if abandonment, Plan Abandonment and physical cultural resources environment health, to impacts minimize and prevent to order in event for Plan Contingency Environmental Managementand Plan various compliance topics relatedwith its contractors and Training Plan of all participants. the within located mechanism a Community Relations workers. work prevent to measures Plan Security and Health Occupational plan will operation. its and work a of impacts environmental adverse of result a as areas restorat for Plan of environmental caused changes by assurance compliance with environmental Plan regulations through periodic characterization Measurement and Monitoring

structure to develop: develop: to structure Documents mobilization, mobilization, xrpito poes ofrs ih h Wrd ak oiy n Involuntary on Policy Bank World the with conforms process expropriation ; the stages of stages the

set forth

ible for implementing ible for MENTALAND SOCIAL

. S that Includes a training program for the employees of the promoter company , 5) Re 5) , MP

ion e E e involved in all activities of the project on the implementation of of implementation the on project the of activities all in involved warning, .

the

area of of area enable the inter the enable The contingency plan is aimed at providing procedures and actions and procedures providing at aimed is plan contingency The

S . of of pre

MP MP of E of hip activities and actionsactivities required hs rga dsrbs st f cin fr h per the for actions of set a describes program This cords degraded - construction (P) and construction (C) consists of 18 measures 18 of consists (C) construction and (P) construction 1) Obje 1)

S has 9 programs 9 has Plan

influence -

MP accordingMP tothe established and coordination and related accidents and accidents related the , 6) ,

. . site to This program is

.

Verifiable indicators of implementation of indicators Verifiable

areas c , 9) This is a tool for environmental monitoring designed designed monitoring environmental for tool a is This tiv action between between action , and use them to them use and , e the development of theprojectthe development Cost of activity Cost . . s, 2) 2) s, its the the

It is a management tool management a is It . oioig n Maueet ln is to aims Plan Measurement and Monitoring

This program includes the implementation of implementation the includes program This initial conditions.initial that include that eprr ad emnn rmvl of removal permanent and temporary Potential impacts face impacts Potential

which shall be applied be shall which aimed aimed at HAZENAND SAWYER, issues in the occupational health of health occupational the in issues promoter for the ; cost of reach 36 environmental environmental 36 provid

area’s recovery execution schedule agreements

company and population and company measure

to restore the degraded degraded the restore to ing d P.C

, 3) Proced 3) , a guide to establish .

. | . CONSULAMBIENTE in .

, any emergency any

for the benefit the for infrastructure , 7) , measures and measures .

March 2015 March

Expected ures . PAGE manent .

This , 4) 4) , the the 37

, 9 Nº 10

3 2 1 8 7 6 5 4 IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary

Measure Measure Measure Measure Measure Measure Measure Measure Measure Measure ENVIRONMENTAL ENVIRONMENTAL 1 8 7 6 5 4 3 2 10 9

C C C C C C C C C C C C C C C C C C C F F F F F F F P P P

Effluents And OfControl Waste Management Effluent And Waste Hydrocarbons And Chemical Of Management Installed Of System Preventive Contamination Noise Control Measures To Machinery And OfEquipment PreventiveMaintenance Construction By Generated Waste Of Cleaning Camp Work Schedule Work Schedule Pre MENTALAND SOCIAL

- Construction MEASURES Table Table AND SOCIAL SOCIAL AND

Generated Generated

Maintenance Maintenance

6

.

Environmental Environmental

MITIGATION MITIGATION Activity Activity Activity Activity Activity Activity Activity Activity Activi Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity and Social Social and ty

Nº 5.1 Nº 4.1 Nº 3.4 Nº 3.3 Nº 3.2 Nº 3.1 Nº 2.1 Nº 1.2 Nº 1.1 Nº Nº 10.3 Nº 10.2 Nº 10.1 Nº 9.10 Nº 9.9 Nº 9.8 Nº 9.7 Nº 9.6 Nº 9.5 Nº 9.4 Nº 9.3 Nº 9.2 Nº 9.1 Nº 8.2 Nº 8.1 Nº 7.4 Nº 7.3 Nº 7.2 Nº 7.1 Nº 6.1 Nº

HAZENAND SAWYER, Measures Proposed Proposed Measures and machinery. and equipment to maintenance preventive Performing Dailycleaning Orde materials. ofbuilding warehouse ofthe storage Order O work camp. formthe that areas Define work schedule of Proper the for inspection Technical pre start Schedule to Proper Transport and disposal disposal and Transport Temporarystorage metal pan Colored units management Wastewater management waste special and Hazardous Transport management Debris Temporarystorage recycling and Reuse collection and Segregation inventory and Waste’scontrol management p General Obtaining of Storage ofchemicals. storage and Handling generators. electric emergency the to Maintenance maintenance. PumpingStation Updat WWTP. Esclusas Las maintenanceof corrective Preventiveand instruments. and ofInventoryequipment control vibration and Noise rder rder

area ofinfluence area

r and cleanof diningand room r

ing and maintenance of work camp maintenance and of

rovisions for a proper wasted proper a for rovisions of

and disposal disposal and

register as hazardous waste generators waste hazardous as register h

ydrocarbons (fuel and lubricants) lubricants) and (fuel ydrocarbons equipment equipment

of of

DESCRIP and preventive and corrective corrective and preventive and

construction area construction P.C

.

. | . CONSULAMBIENTE

inventory inventory s current assessment of assessment current . -

TION Portable Portable

- work. work. March 2015 March

s

of La Pradera LaPradera of PAGE

sanitation sanitation

38

21 20 19 18 17 16 15 14 13 12 11 Nº

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary

Measure Measure Measure 21 Measure 20 Measure 19 Measure Measure Measure Measure Measure Measure Measure ENVIRONMENTAL ENVIRONMENTAL 18 17 16 15 14 13 12 1 1

C C C C C C C F P P F F F F F F F F F F F F F C F F

Standards Safety Occupational Program Relationships Community Of Implementation Program Relationships Community Of Implementation Program Relationships Community Of Implementation Areas Affected Of Cleaning Areas Affected Of Restoration Bodies Receiving In Proliferation Algae OfControl Body Water Receiving For Plan Measurement And Monitoring Implemented. Structures Of Implementation And DuringOperation Plan Measurement And Monitoring Program Monitoring Management Waste Hazardous For Provisions General MENTALAND SOCIAL

MEASURES Table Table

AND SOCIAL SOCIAL AND

6

.

Environmental Environmental

MITIGATION MITIGATION

Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Activity Nº 21.4 ActivityNº 21.3 ActivityNº 21.2 ActivityNº 21.1 ActivityNº 20.1 ActivityNº 19.3 ActivityNº 19.2 ActivityNº 19.1 ActivityNº Activity Activity Activity Activity Activity Activity Activity Activity Activity and Social Social and

Nº 14.1 Nº 13.7 Nº 13.6 Nº 13.5 Nº 13.4 Nº 13.3 Nº 13.2 Nº 13.1 Nº 12.2 Nº 12.1 Nº 11.2 Nº 11.1 Nº 10.4 Nº Nº 18.2 Nº 18.1 Nº 17.2 Nº 17.1 Nº 16.2 Nº 16.1 Nº 15.1 Nº 14.3 Nº 14.2 Nº

HAZENAND SAWYER, Measures Proposed Proposed Measures Phytoplankton and Zooplankton monitoring Zooplankton and Phytoplankton monitoring parameters Weather monitoring quality air Environmental Monitoring gas Pollutant Monitoring and Control Noise monitoring Sludge discharge water waste monitoringof Quality monitoring Odors control vibration and Noise parti PM10 mattermonitoring particulate PM2.5 and Hazardous Identifica management Sewagesludge Rules for Rules Safetyrules Safetystandard safety rules Applicationof Relations sign Information environmental flyers and Brochure withthe community Meeting Informati with Meeting maintenance. Restoration WWTP ofthe activities maintenance corrective and bypreventive w of Cleaning Restoration installation. WWTP and activities byconstruction Cleaning event on Report monitoring water Surface M acro - Benthic organisms Monitoring Monitoring Benthicorganisms

hips on tion of hazardous waste hazardous of tion of w of t emporary electrical installations installations electrical emporary culate mattermonitoring culate

of of

for handling handling for sign

thec aste in aste in aste

with interested parties parties withinterested sites affected by force main force by sitesaffected construction by sitesaffected

special waste special DESCRIP for Manual load lifting Manualfor load

- -

P.C ommunity ommunity safety signs safety Safetysigns

- areas areas areas

. | . CONSULAMBIENTE occupational occupational .

- heavy machinery heavy fixed sources fixed

accidentally affected affected accidentally affected accidentally TION for handlingfor trucks

management

March 2015 March

PAGE

39

30 29 28 27 26 25 24 23 22 Nº

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary

Measure 22 Measure Measure 30 Measure 29 Measure 28 Measure 27 Measure 26 Measure 25 Measure 24 Measure 23 Measure ENVIRONMENTAL ENVIRONMENTAL

F C C C C F F F F

Station Pumping LaPradera For Plan Contingency Training Personnel Training Personnel Areas Of Work Signage Workers For Safety Occupational OfW Standards Safety Basic Areas Of Work Signage Workers Occupational MENTALAND SOCIAL

MEASURES WTP Table Table

AND SOCIAL SOCIAL AND

6 Safety For Safety .

Environmental Environmental

MITIGATION MITIGATION

Activity Nº 23.2 ActivityNº 23.1 ActivityNº 22.1 ActivityNº 21.5 ActivityNº Activity Nº 30.1 ActivityNº 29.8 ActivityNº 29.7 ActivityNº 29.6 ActivityNº 29.5 ActivityNº 29.4 ActivityNº 29.3 ActivityNº 29.2 ActivityNº ActivityNº y 28.3 28.4 28.2, 28.1, ActivityNº y 27.3 27.2 ActivityNº 26.1 ActivityNº 25.1 ActivityNº 24.1 ActivityNº and Social Social and

29.1 27.1,

HAZENAND SAWYER,

Measures Proposed Proposed Measures Application safetyplan Road sign Information equipment Entry protection Space Confined Earplugs Vests boots Rubber gloves Leather Anti glasses Protection helmet Protection base concrete and PVC of Post Safetycone Reflectivetape for Rules Final Contingency Plan Plan Contingency Final Disasters. ofNatural inActing case chemicals. fuels and of ofspillage inActing case Acting Drills emergency care for Brigades First numbers ofemergency Information plan finalcontingency of submitting and Developing Awareness Awareness sings Information equipment Entry protection Space Confined Earplugs Vests boots Rubber gloves Leather Anti glasses Protection helmet Protection and PVC of Post Safetycones WWTP StationPumpingand Pradera - - -

Dust d aid Kit aid

ust Masks ust

in case of fire of incase

order and cleaning and order

Masks meetings meetings s

of of

Safety rules for Safetyrules DESCRIP

- c

- oncrete base oncrete P.C

safety signs signs safety

Safety signs signs Safety

/ Environmental Training / Environmental Training / Environmental . | . CONSULAMBIENTE

TION

March 2015 March

operation of operation

PAGE

40

La

Prepared by: by: Prepared 36 35 34 33 32 31 Nº

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary

Measure 36 Measure 35 Measure 34 Measure 33 Measure 32 Measure 31 Measure ENVIRONMENTAL ENVIRONMENTAL Hazen and Sawyer and Hazen

C F C C F

Compensation Compensation Environment Monitoring Environment Monitoring Environmental Program Abandonment Program Abandonment Program Abandonment WWTP. The Stationand Pumping LaPradera For Plan Contingency MENTALAND SOCIAL

MEASURES Table Table . AND SOCIAL SOCIAL AND

6 .

Environmental Environmental

MITIGATION MITIGATION

Activity Nº 31.4 ActivityNº 31.3 ActivityNº 31.2 ActivityNº 31.1 ActivityNº 30.8 ActivityNº 30.7 ActivityNº 30.6 ActivityNº 30.5 ActivityNº 30.2 ActivityNº 30.3 ActivityNº 30.2 ActivityNº Activity Nº 36.1 ActivityNº Activity 35.1 ActivityNº 34.3 ActivityNº 34.2 ActivityNº 34.1 ActivityNº 33.6 ActivityNº 33.5 ActivityNº 33.4 ActivityNº 33.3 ActivityNº 33.2 ActivityNº ActivityNº 32.4 ActivityNº 32.3 ActivityNº 32.2 ActivityNº 32.1 ActivityNº and Social Social and

Nº 35.2 Nº 33.1

HAZENAND SAWYER, Measures Proposed Proposed Measures Cleaning and evacuation of waste and debris. debris. and waste of evacuation and Cleaning materials. construction for area storage and site contractor’s removal and Dismantling machinery, of Removal sitesafety. abandoned and fencing, Accessroads, Blocking Disasters. ofNatural inActing case ofspillages inActing case fire of inActing case numbers ofemergency Information First contingent and fireextinguishers of Implementation brigades Training Improvement of La Pradera Park LaPradera of Improvement authority competent to report compliance of Development Monitoring Environmental audit. environmental Compliance authority. competent to report compliance of Development monitoring Environmental Re debris. and waste of removal and cleaning Performing Building. of evacuation and Dismantling the WWTP. StationPumpingand Pradera of Removal Drain sitesafety. abandoned Fencingand removalof and debris and waste of evacuation and Cleaning site contractor’s removal and Dismantling likely Removal used machinery, of Removal s toration of the intervened site. site. intervened ofthe toration

- in works. in aid Kit aid ing to be reused. reused. be to

and seal and of

and emergency emergency and

portable toilets. portable

equipment unused construction materials and/or materialsand/or unusedconstruction

DESCRIP

ing - P.C

Training session Training

of force main and pipes. pipes. and main force of . | . CONSULAMBIENTE

and and tools tools, of the ofthe of the ofthe

equipment. equipment. TION

appurtenances of La of appurtenances

and equipment equipment and

and equipment equipment and March 2015 March area usedas area area usedas area

PAGE

41

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMOfollowing aspects were applied: \TM1published 1040, No. the for Th basic requirement for obtaining is The process of social participation (PPS, as per its acronym in Spanish) 10. annual avoid be will atmosphere the into gas methane gas. methane have studies of project The from the WWTP is a benefit that digesti anaerobic the by produced gas greenhouse Minimizing 9. the overall technical/engineering of part as included are maintenance and operations during measures environmental for Costs The resources for these costs will be included as part of the construction contract for the Project. following aspects: stage. operation the for year per 0.2 for accounting stages,construction US$ is measures estimated The 8 components, project’s each to forcestations, treatment main, and plant areshow applied be to quantities and Distribution ESIAExecutive Summary .3

an the calorific capacity of methane gas produced in the plant the in produced gas methane of capacity calorific the e methodology applied to the PPS comply theprovisions e tothe PPS with methodologyapplied

Social Participation The Project and ● ●

integra net savings Environmental monitoring period construction andforceStation of Pumping mainrespectively. Deadline for works execution, 24 months for WWTP E Implement S MP Budget includes cogeneration facilities cogeneration includes l estimated of 8,200 m 8,200 of estimated

part of of part Therefore, the direct emission of of emission direct the Therefore, total 483,011.66

ation

of MENTALAND SOCIAL

C b limate Change in approximately the the

de fr h ipeetto o environmental of implementation the for udget

of the environmental regulation process under the legislation of Ecuador, of legislation the under process regulation environmental

Mechanisms of Social Participation set forth by Executive by forth set Participation Social of Mechanisms

; Official from

the environmental licenseenvironmental forthe theproject.

helps costs for projcosts for 3

which This per day of biogas will be processed, be will biogas of day per

US Gazette

preserve preserve atmosphere and reduce global climate change. percent $242,000 b during annual operation, US de has udget

for the production of electricity taking advantage advantage taking electricity of production the for

$ No. 332 of May 8, 2008. 8, May of 332 No. ect operationect and maintenance. 326,324.55

ed based on work on based . approximately

n in energ in Thus the Thus

in the table above.

been HAZENAND SAWYER,

y consumption.

correspond to correspond rprd aig no con the account into taking prepared use of methane gas methane of use ’s ’s

s construction

total cost; total o digesters. 1.94 million cubic meters of of meters cubic million 1.94 n process of primary sludge primary of process n of (12 months). G

uidelines to uidelines

n sca mitigation social and

p In 65

pre P.C

ublic consultation and and

Project engineering Project , and 12 months for

general . | . CONSULAMBIENTE percent - ht is, that construction and and construction

US

could

$ Regulations 156,687.11

March 2015 March

terms, the terms,

of flow is flow of pumping produce PAGE Decree 42 —

Centers Centers Centers Centers AP, as per its as per AP, RI IMPACTASSESSMENT LASESCLUSAS ENVIRON below: Pumpin H and WWTP Pradera La to theparkadjacent consideredPraderaNeruda wasappropriate in the PIC it toinstall and Pablo The PIC are located inplaces ofmassive turnout fromtime 13:00. 08:00to explanations. necessary the provide to project the with The E 10 Mec ESIAExecutive Summary Information Information Information

O:\41082-000\WPDOCS\TECH-MEMO\TM1 inacronym inacronym Secondary Secondary meetings meetings Hearing Primary Spanish Spanish , as per its as per , .1 Public Public Public Public hanism

SIA - -

Public Information Centers PIC PIC PIC

-

-

was was made available to the public at a place of open access having personnel familiar Qty 2 2 1 2

Record to the AP to Record Means to verify verify to Means Record to the RI to Record ClosingMinutes ClosingMinutes and recording recording and the mechanism the MENTALAND SOCIAL

and recording recording and Opening and and Opening and Opening observations observations observations Attendance Attendance ofPIC of PIC

B. B. Table Table of

Recommended by Multilateral Banks by Recommended Multilateral

Neruda Neruda Huancavilca “Casitas del del “Casitas 7 Foundation La Pradera LaPradera La Pradera LaPradera Guasmo” Location .

Terminal Metrovía

g Mechanism A Mechanism Center Health Pablo Pablo Pablo

Park Park Station. Station. A.

Park Park Park

Reg

ulatory

L a 22 18 t ocation of the PIC can be seen in the map map the in seen be can PIC the of ocation 23 08 25 02 30 07 07 pplied in PPS pplied Metrovía Terminal andHealth Center. - - 09 09 ------

09 10 09 10 Date 09 10 10 - - to

2014 2014 HAZENAND SAWYER, ------Each PIC operated for two weeks at a at weeks two for operated PIC Each 2014 2014 2014 2014 2014 2014 2014

to to

Media used for used for Media Announcements Announcements Announcements by Megaphones by by

Press releases releases Press Flyers Flyers calls Private P Me osters the call the (42) g (5) (2) (4) aphones

(400) (600)

(6) P.C

. | . CONSULAMBIENTE

Means to verify to Means by megaphones by megaphones by announcements announcements announcements and deliveryof and and deliveryof and Posters photo Posters publications publication publication Register of Register Copies of Copies invitation March 2015 March Photo of Photo of Photo the call the Bill of Bill flyers flyers PAGE

For For

43 .

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 in 12main areas: The following table summarizes all comments (89) received 697. registerwas the signed who people of total the that Itnoted is followingtable. the in shown is PIC the at comments and questions made who people of number the on statistics Descriptive ESIAExecutive Summary

Average/day Max Min Total

imum imum MENTALAND SOCIAL

Descrip /day /day Comments made Comments

tion Figure Figure Table Table

8 8 . Location of Public Information Centers Public Information of . Location . Participation Statistics at PIC Statistics at Participation .

Metrovía 194 19 15 20 9

PIC Number of Question of Number PIC Guasmo 37 HAZENAND SAWYER, 236 21 23 20

at

PIC PIC which have been distributed

Pradera 26 148 10 13 3

P.C

. | . CONSULAMBIENTE P. Neruda P. 119 7 11 21 0

March 2015 March

PAGE 44

I IMPACTASSESSMENT LASESCLUSAS ENVIRON Based upon comments, t work 19 with odors monitoring the by percent followed overflows, prevent to system sewer sanitary of Approximately ESIAExecutive Summary

O:\41082-000\WPDOCS\TECH-MEMO\TM1 TEM I 12 11 10 tem 7 6 5 4 3 2 1 9 8 4 3 2 1

s

(12 ; another concern of the community is related to compliance with the with compliance to related is community the of concern another ; commercial claims commercial ofservice Good Sewer Sewer installation Meter TOTAL expropriation No Park Pradera to Improvements monitoring Odors inspectors Community of Organization project ofthe Acceptance workthe Compl management debris and roads to Damage investment of collection on Consultation claims ofservicecommercial Good installation Sewer maintenance Sewer installation Meter

Community Community percent Comment

installation maintenance iance iance

20

SUMMARY

); 8

with the deadlines of withthe deadlines percent

Table Table MENTALAND SOCIAL

percent

he 10 Table Table water. sewer the because agreed findbest the and case each of thearea M control body. control and regulation as a EP EMAPAG whichresponsible is for instance third isa claim, complaint or request, a raise followedto be community the to explaining Management, by supported socialization, Me for Measure EP. EMAPAG ofinfluencethe System Sewer ofSanitary Plan maintenance Preventive Me

of comments recorded are requests related to maintenance activities . following are measures recommended to be included in the Project. Application Method of comment in the Environmental Impact Assessment Assessment Impact Environmental in the ofcomment Method Application

easure Measures

asure: as the area of thearea

commented on ure 9

.

Number of Comments R Comments Numberof

: : :

the Concession Holder Holder Concession the EMAPAG EP EP EMAPAG E INTERAGUA Holder Concession the influence ofthe influence MAPAG EP EP MAPAG

to Be Included in the EIA as a R IncludedEIAa as the Be in to

influence of the project, within a term not exceeding two (2) years. (2) two notwithin exceeding term a project, ofthe influence

p Metrovía roject, which shall be implemented under strict control of the of control strict under implemented shallwhich be roject, service 19 3 1 1 6 5 3

d shall service sewer sanitary of universality managethe shall amage is charged as a percentage of consumption of ofconsumption percentage as a charged is

p its roject that have no water meter, in order to analyze to in order meter, water that have no roject

continue the activities related to to related activities the continue Social Communication Direct Communication Social C. Guasmo C. s INTERAGUA should contact the residents of theresidents contact should INTERAGUA

ecorded at PIC at ecorded to roads and debris management.and debristo roads option option HAZENAND SAWYER, 37 14 5 3 9 3 3

with the owners to install the meter, meter, theinstall to withowners the

, among other topics, the topics, other among , Pradera esult of PPS of esult shall submit annually a annually submit shall 26 12 10 a 2 1 1

nd informing them that there that informingnd them

, specific for thefor specific ,

P.C P. Neruda P. . | . CONSULAMBIENTE orate

deadlines of the of deadlines p roject 7 2 1 3 1

and and

processes March 2015 March ’s Community Community

potable PAGE area of area

Total

89 17 17 11 18 2 2 4 7 1 1 6 3 45

t

o

IMPACTASSESSMENT LASESCLUSAS ENVIRON InformationHearing Meetingare and opinions O:and comments \41082measures features of the project, expected -environmental 000Huancavilca. Foundation the of offices the at \WPDOCSThe E \TECH10 -MEMO\TM1 ESIAExecutive Summary I tem 12 11 10 .2 9 8 7 6 5

SIA was disclosed and a Public H Public Hearing and No expropriations No Park Pradera to Improvements monitoring Odors inspectors Community work ofthe deadline project ofthe Acceptance roads to Damage investment C ollection of ollection , and responses responses and , Community Community Comment

Table Table MENTALAND SOCIAL

of participants of 10 supported by its Social Communication and Community Management Management Community and Communication by Social its supported socialization, project’s to related activities continue shall EP EMAPAG Measure: ofthe vicinity in the living community with the ofGuayaquil. ofthe Municipality Works ofPublic Directorate Areas,the and Green and Parks Station, Pumping H Guasmo and LaPradera the future to near located park ofa rehabilitation the costs, project’s within the consider should EMAPAGEP Project the of Integral As part Measure: or eliminate to taken be to thewhich actions in socialization of campaigns by accompanied measures remedial immediate propose shall effectsit are there incase gases; detectable no of thelevel gases campaignsof monitoring perform shall INTERAGUA holder concession The Measure: the project. to linked function that canfulfillthey this in order Directorate, Management Community and Communication by Social its supported inspec as citizen leaders community to shall train EP EMAPAG Measure: informed. by for be law, provided implementation greater of mechanism underthe must, ofinfluence area particular the communityof ofterm the extensions require that situations ofunforeseen incase extensions; avoid to setforth contractually works termofwith the monitorcompliance closely shall EP EMAPAG Measure: the of community support ensure to the t community the to explaining Directorate, Management Community and Communication by Social its supported socialization, project’s to related activities the continue shall EP EMAPAG Measure: the and commu high also, roads); pedestrian (vehicle and roads on effect generatethe least to in order whereprovided, streets, M ofGuayaquil. Municipality the by granted annually allocation theby budget funded work will be the because charged will be not that investment general in community the to explaining Directorate, Management by Social its supported socialization, project’s to related activities the continue shall EP EMAPAG Measure: house located on a lot owned by Radio Cenit S.A. Cenit Radio by owned lot a on houselocated type any does notinvolve project that the community the explaining to Directorate, o lrf qetos and questions clarify to Information Meetings . Application Method of comment in the Environmental Impact Assessment Assessment Impact Environmental in the ofcomment Method Application

easure: The contractor shall schedule the activities related to breakage of breakage to related the activities schedule shall contractor easure:The Measures of expropriation or relocation of housing, except for the specific case ofa specific case the for except relocationofhousing, or ofexpropriation

to Be Included in the EIA as a R IncludedEIAa as the Be in to

shown in thefollowinggraphic.shown Design to be submitted for this rehabilitation should be socialized socialized be should rehabilitation this for submitted be to Design nity will be informed on this issue. this on informed will be nity earing was held on September 25 .

The number of people who attended both the Public Public the both attended who people of number The (hydrogen sulfide) and surveys campaigns in order to confirm to order in campaigns surveys and sulfide) (hydrogen

The meeting provided a summary of the the of summary a provided meeting The and and social

- risk areas should be signalized, both day and night night day both and signalized, be should areas risk

ocrs bu te project the about concerns under close coordination of the Department of ofthe Department coordination underclose HAZENAND SAWYER, Communication and Community and Communication

impact and the respective mitigation .

minimize odors are explained. minimizeare odors esult of PPS of esult park.

,

he benefits of the project project ofhethe benefits 2014, 2014, at 18:00 hours, P.C . | . CONSULAMBIENTE

ae upon based March 2015 March PAGE tors, tors,

main 46

completion? for theterm whichis and executed will be works Whenthe NATURISA) of byrepresentative the made(question farms? impactshrimp of of the area Which is odors? generate theproject of theoperation Will

IMPACTASSESSMENT LASESCLUSAS ENVIRON O: \41082-000\WPDOCS\TECH-MEMO\TM1 and Meetings Information and Hearing Public the at responses toeachquestion made questions the of summary A Two informationalalso Pr one meetings held; wereat ESIAExecutive Summary

Question

Figure Figure

9 MENTALAND SOCIAL

term for completion of two oftwo completion termfor has and a half2015 of thesecond in construction start to isplanned It wasindrawing). a area shown Esclusas Las premises of westofthe the on side located which is ha 16.5 approximately is by required Naturisa area The vicinities. the in community affectingthe avoid to in order odors treat to designed systems have Stations Pumping and Treatment Plant . Number of Attendees of P of Attendees Numberof . Table Table RI RI - are presented below:

P. NerudaP.

11

Answer . Observations Obtained at PublicHearing at Obtained Observations . ; 40

Data

(note: the (note: Source: EMAPAG Source: years. ublic Hearing and Information Meetings Information and ublicHearing

Pública Audiencia

; by law, be informed. by be law, mechani must,the under ofinfluence area theparticular of the community term of extensions thatrequire situations unforeseen of case in extensions; avoid to contractually setforth the terms monitoringof perform close should a EP EMAPAG Measure: notapply. does ofan action Implementation explained are odors minimize elim to taken be to thewhich actions in socialization of campaigns by accompanied measures remedial immediate shallpropose effectsit are there ingases; case ofdetectable no confirmlevel to the order in campaigns surveys and o monitoringcampaigns perform shall INTERAGUA Holder theConcession the project, of phase operation the During Measure: 11 aderaand Neruda. one at Pablor HAZENAND SAWYER,

sm of greater implementation provided for provided implementation greater sm of RI RI - Pradera ; 30

Measure f gases (hydrogen sulfide) sulfide) (hydrogen fgases P.C . | . CONSULAMBIENTE

inate or or inate March 2015 March

PAGE

47

in the houses? inthe cr worksappear of execution result ofthe as a if happens What odor generate theproject Will ofPremises? Relocation be there Will ofthe project? because expropriations be there Will untreated into the river? into untreated or discharged treated will wastewater be Do works? the sco Which is works? during impacts be there Will generateodors? theproject Will works? of completion for the term Which is

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary s?

the execution of theexecution Question

Question

pe of pe

acks Table Table

Table Table

MENTALAND SOCIAL

13 second half of 2015 and has termand a halfof2015 second from willexecuted be Works river. intothe discharged will be not wastewater untreated disinfection; and treatment advanced primary to pre subjected be will wastewater to discharge, Prior Plant. Las plant to Esclusas fromPradera willgo main force and Esclusas Las of the area in StationH, at Plant, Pump withinPradera worksperformed will be The havedesigned. been measures environmental these effects reduce to dust, noiseand suchas works, ofthe theduring construction willspecific impacts be There odors. by affected willnot be community therefore, treated; will be Stations the Pumping and Plant the inTreatment both theproject by willgenerated that be odors The years. oftwo completion for functions of a radio antenna. radio offunctionsa has surveillance who wherelady leaves a booth surveillance ofa case inthe except relocation, kind anyof notrepresent does project The H. stationGuasmo pumping expropriation kind anyof notrepresent does project The complied. will be willthis ensure EP EMAPAG appear, cracks inworks); case of execution the to (prior conditions better or same inthe leave houses to the is required contractor The vicinities in the community impacting the avoid to in order odors treat to designed systems have Stations Pumping and Treatment Plant . Observations Obtained at Information Meeting Meeting Information at Obtained Observations . 12

. Observations Obtained at Information Meeting Meeting Information at Obtained Observations .

Answer for the construction ofthe thefor construction - treatment, a treatment, Answer

the the

monitoringplan. the environmental willmonitor EMAPAG monitoringplan the environmental willmonitor EMAPAG participation. ofsocial process the during Acceptance participation. ofsocial process the during Acceptance monitoringplan the environmen willmonitor EMAPAG HAZENAND SAWYER, insurance. purchaseofthird and records ofproperty Preparation participation. ofsocial process the during Acceptance participation. ofsocial process the during Acceptance participation. ofsocial process the during Acceptance

.

-

Pablo Neruda Pablo -

Pradera Measure

P.C

Measure . | . CONSULAMBIENTE

party liability liability party

March 2015 March tal PAGE 48

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:12 \41082 -000\WPDOCS\TECH-MEMO\TM1 of following area the of environment human andact shocking influence, natural the of characterization the on information Esclusas Las Treatment Wastewater and Force E The 11. registeringcomplaints. and resolving dedicated specialist responsible for community relations who will be responsible for receiving, Du resolved. were they how and complaints of register a maintain will who someone by staffed be should reception This project. the to related complaints or concerns questions, have may who community adjacent project sub the handling complaints for system The system grievance the monitoring and managing (Dirección Social de Comunicación for EP EMAPAG within directorate and person responsible the as well as board), on are contractors before (also requests information pa affected potentially or members community for details all components and a description has been posted in EMAPAG’s website including project overall the for EP EMAPAG by up set been has system grievanceredress A 10.3 is conductingrelocation process a of the aspart theRecovery Estero of Salado. community of Pablo Neruda, are a result of the fact that in the sector the National Government t related Moreover,queries the by otherwise or Information consultant promoter ofthe project. and designer Hearing the the from technicians at by made answered questions were the Meetings, of each that emphasized be should It ESIAExecutive Summary

http://www.emapag

● ● ● Conclusions

S , Alternative WWTP force km 5 be will Construction of the project will involve an environmental disturbance on the site where although settlements, no are there where places remote in built be will these outfall fluvial sub the effects on the environment are minimized. In the case of the treatment plant and areas urban where inintervened thearea be within will performed the pumping station of improvement the and main force the of execution the for developed be to Activities Grievance R - IA for “construction, per “construction, for IA

plan for community relations within within relations community for plan the contractor will be obliged to maint obligedto be will contractor the :

located the WWTP andlocated the of indifferent a thecity, areasdue WWTP of tothe installation

and Recommendations

it will be will moreenvironment.it likelytoimpact the natural

sewer analysis edress MENTALAND SOCIAL

- ep.gob.ec/emapag/?page_id=731 ions and potential environmental impacts of the project, obtain project, the of impacts environmental potential and ions

main that will convey wastewater from the pumping stations to the to stations pumping the from wastewater convey will that main

o expropriation, relocation and title of lands that were made by the wereby madethat lands of title and relocation expropriation, o

helped identify the applicable WWTP technological WWTP identifyhelped applicable the process

ig h oeain f the of operation the ring formance and operation of Pradera Pumping Station, Main Station, Pumping Pradera of operation and formance -

regarding Component Three in particular in Three Component regarding

Gest

ión Comunitaria [DCS ión Comunitaria this this ain a reception area onsite areareception a ain -

South Subsystem” allowed the collection of collection the allowed Subsystem” South ESIA. During the implementation of the the of implementation the During ESIA. HAZENAND SAWYER,

WWTP, WWTP, rties to raise potential complaints or complaints potential raise to rties - GC]). GC]). neau wl as hv a have also will Interagua

12

P.C ,

. It for members of the of members for . | . CONSULAMBIENTE includes contact

is described in in described is March 2015 March PAGE ed

the the 49

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary ● ● ● ● ●

o o o o the inhabitants ofthesouth city. include: These en it as population the wastewater the of operation the of health the on benefits direct with systems from complementary from and plant treatment arise during observed impacts and positive population the of the Most to discomfort produce to construction required values the reach “ t during pressure sound of Increase discomfort in the area, in addition to alteration of vehicular traffic and high noise levels. involves work the country, Most the of the negative in impacts will occur force during the installation of in the main force laws because by regardingfinal thereceiving discharge allowed theinto body. standards the wit with effluent comply an to ensures conditions that system treatment a of implementation the and discharges, illegal of control greater allowing mains, force and stations pumping as: such Guayaquil, wastew of management proper for the strategies includes in project The component each for influence indirect construction and phases operation and direct of areas the establishing Studie o i

nsignificant”, because it is estimated that during the performance its levels will not will levels its performance the during that estimated is it because nsignificant”, nrae aiy noe n ipoe h qaiy f ie f h pplto of population the of life of quality the Guayaquil improve and income family increase to leading activities, recreational and tourism of increase an in reflected be would Recovery of the quality of the landscape and preservation of flora and f effluent and inbodies fecal ofwater. ofcoliformsColi theWWTP andE. Monit diseases. population the m general for and diseases gastrointestinal to due mortality healthcare of costs the benefiting from the in project. This suggests assessing the following indicators: infant reduction a allowing mortality, reflected be would pollution environmental gastrointestinal, of cases in Decrease flow inthe rainy season. into to manage sanitary peaks in water the dry season and up to sewage two (2) times the peak sanitary raw of discharges Guayas River of because the new pumping station frequency and the WWTP will the in decrease Significant control appropriate of implementation the includes measures ofodors. station pumping new the Decrease in current obnoxious odors around the existing pump recovery landscape ofquality of ofthe and flora preservation fauna species. and of Guayaquil. Likewise, the balance of the ecosystem will be recovered through the a front River Guayas of waters of pollution of reduction the through Guayaquil of city the of population the of sanitation of Improvement cnutd n te nlss f ehia ifrain f h poet allowed project the of information technical of analysis the and conducted s he different stages of the project. However, it was assigned to a category of of category a to assigned was it However, project. the of stages different he

MENTALAND SOCIAL

although higher levels will exist impactsalthough levels exist beonly higher will temporary

earthmoving and excavations in operating roads, which will cause will which roads, operating in excavations and earthmoving oring or control indicators are indicators control or oring

collection and collection by produced wastewater of disposal and treatment proper sures

(noise)

levels is considered the impact most likely to occur occur likelyto most impact the considered is levels conveyance of domestic wastewater by means of of means by wastewater domestic of conveyance parasitic, HAZENAND SAWYER, n dcesd obdt ad infant and morbidity decreased a in

fecal coliforms and E. Coli in the in Coli E. and coliforms fecal and skin diseases. The low risk of risk low The diseases. skin and

orbidity of gastrointestinal of orbidity nd downstream of the city city the of downstream nd P.C station in Pradera as ater in the city of of city the in ater . | . CONSULAMBIENTE have the ability acceptable h auna auna species March 2015 March .

PAGE 50

IMPACTASSESSMENT LASESCLUSAS ENVIRON O:\41082-000\WPDOCS\TECH-MEMO\TM1 ESIAExecutive Summary ● ●

ih h icesn pplto, as n rgltos oenn pluin and comfortable, pollution guaranteed be can governing adherence strict and regulations procedures and laws population, wastewater disposal arebecoming increasinglyOnlyessential. by these means legal of increasing the With o o o o o o volu the does to: essential measures tocounteract pollution environmental so grows, Guayaquil of city takeimperative to is it so environment, the pollute that wastes organic wastewaterand the of population urban the As

Prevent of navigational siltation channels Keeptouristic, potential water for species. Maintain Maintain Prevent nuisances topopulation. Preventand ofthe diseases protectthe health population.

MENTALAND SOCIAL

andenvironment. healthy clean clean water clean water for bathrooms andother recreationalwater for processes

used for propagation and survival of fish and other aquatic other and fish of survival and propagation for used

industrial,

HAZENAND SAWYER,

and agricultural uses.

o h etr pplto a clean, a population entire the to

P.C . | . CONSULAMBIENTE

March 2015 March PAGE e of me 51