BID SET 4/27/16

EXHIBIT G: Specification Table of Contents by Rick Engineering Company, Verde Design

DIVISION 01 – GENERAL REQUIREMENTS

01 07 00 CONFORMANCE SURYEYING 01 11 50 ELECTRONIC DRAWINGS 01 11 50A ELECTRONIC REQUEST FORM 01 31 19 PROJECT MEETINGS 01 33 00 SUBMITTAL PROCEDURES 01 57 23 EROSION CONTROL/SWPPP IMPLEMENTATION 01 45 00 QUALITY CONTROL 01 71 13 MOBILIZATION 01 74 19 CONSTRUCTION AND DEMOLITION MATERIALS MANAGEMENT 01 77 10 PROJECT CLOSEOUT 01 78 00 PROJECT RECORD DOCUMENTS

DIVISION 02 – EXISTING CONDITIONS

02 41 00 DEMOLITION

DIVISION 10 – SPECIALTIES

10 43 10 SIGNAGE

DIVISION 12 – FURNISHINGS

12 93 00 ATHLETIC SITE FURNISHINGS

DIVISION 31 – EARTHWORK

31 11 00 CLEARING AND GRUBBING 31 22 00 GRADING 31 22 20 BIORETENTION BASINS 31 23 19 DEWATERING 31 23 33 TRENCHING, EXCAVATION, BACKFILLING AND COMPACTING

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 01 13 SLURRY SEAL 32 01 16 COLD MILLING ASPHALT PAVING 32 12 16 ASHPALT CONCRETE PAVING 32 12 16 ASHPALT CONCRETE PAVING – FOR TRACK SURFACING AREAS 32 13 13 CONCRETE PAVING 32 16 13 CONCRETE CURBS AND GUTTERS 32 17 23 PAVEMENT MARKINGS, STRIPING, AND SIGNS 32 18 00 MISCELLANEOUS PAVING & SURFACING 32 18 23 VULCANIZED RUBBER TRACK SURFACING 32 31 14 CHAIN LINK FENCES AND GATES 32 84 00 SYSTEM 32 90 00 LANDSCAPE PLANTING

DIVISION 33 – UTILITIES

33 05 16 UTILITY STRUCTURES 33 40 00 STORM DRAINAGE UTILITIES

SECTION 01 07 00 CONFORMANCE SURVEYING

PART 1 - GENERAL

1.01 SUMMARY

A. Conformance Surveying work shall be completed by a Licensed Surveyor and be based on established site bench marks, monuments, lines, and levels necessary for the work covered by this Contract.

B. Scope of work: Providing conformance surveying required for proper completion of the work may include, but may not be limited to: 1. Running track construction, including track paving, track surfacing, and all track edges / curbing.

C. Related sections can include, but may not be limited to the following: 1. Section 01 33 00 – Submittals 2. Section 01 71 23 – Field Engineering 3. Section 01 78 39 – Record Drawings 4. Section 32 12 16 – Asphaltic Concrete Paving 5. Section 32 13 13 - Portland Cement Concrete 6. Section 32 18 23 – Track Surfacing – Vulcanized Rubber

1.02 REFERENCES AND REGULATORY REQUIREMENTS

A. State of California Department of Transportation Standard Specifications, current edition.

B. California Building Code, current edition

C. NCAA Track and Field Facility Rule of Sport, Current Edition

1.03 SUBMITTALS

A. Contractor will be required to submit three (3) hard copies and one (1) electronic copy (in AutoCAD or scaled PDF image) of all conformance surveys for the project. The Contractor shall ensure that all survey data is completed with the supervision of a licensed surveyor. The District Representative shall provide a written response within two (2) working days of receipt of said drawings and identify any areas out of tolerance.

1.04 QUALITY CONTROL AND REWORK

A. Any portion of the survey that does not conform to the grading tolerance

01 07 00 - 1 CONFORMANCE SURVEYING requirements identified in this specification section will be corrected by the Contractor. Areas out of conformance will be resurveyed at the Contractor’s sole expense (following the identical procedure stated above) by the Surveyor, and these revised points shall be added to the original digital file for resubmittal, review and acceptance by the District Representative.

B. All delays and costs incurred due to grades out of conformance are the sole responsibility of the Contractor. At any point during construction following acceptance of any portion of the survey by the District, the District reserves the right to recheck the surface grades (at no cost to the Contractor) to verify it is still in conformance. It is the Contractor’s responsibility to protect the grading and compaction tolerances of the surveyed surface after conformance surveying operations are complete and accepted, and prior to installation of any subsequent materials. Any work identified by the survey that is outside of the acceptable tolerances shall be corrected by the Contractor at its sole expense.

PART 2 - PRODUCTS - Not Applicable

PART 3 - EXECUTION

3.01 LAYING OUT THE WORK

A. Contractor shall employ a Registered Civil Engineer or Licensed Land Surveyor (hereafter referred to as Surveyor) to perform any conformance surveying work required by the Contractor.

B. Prior to beginning work, Contractor shall secure the electronic grading plan from the District for use by the Surveyor. The surveyor shall provide all conformance survey drawings. The drawings shall provide both the design elevations and the as-constructed spot elevations. These elevations shall be for comparison to those on the contract documents for the same location. Contractor shall also show the difference in these two numbers. In addition, unique reference numbers shall be assigned to each point for reference purposes. For spacing requirements, refer to specific type of improvement identified in this specification section.

C. Accuracy of all surveys provided in this section shall be to 0.01 feet.

3.02 TRACK TOLERANCES AND CONFORMANCE SURVEYING REQUIREMENTS

A. PRE-TRACK PAVING AND SURFACING: Prior to the pouring of all track curbing, Contractor shall be responsible for verifying the proper horizontal and vertical controls of all concrete formwork. This quality control process

01 07 00 - 2 CONFORMANCE SURVEYING does not need to be completed by a licensed surveyor. However, the Contractor shall employ a licensed surveyor to determine finish surface grades of all track curbing upon completion of initial concrete curing process. The curb elevations shall be provided on a minimum 20-foot spacing, including points at all beginning, mid-, and end points of curve, as as all changes in direction (i.e. at the end of the chutes). Once the curbing is deemed to be within the tolerances required by the contract documents (no point along the curbing shall be greater than ¼ inch (0.02 feet) outside the design grades and no spot shall deviate more than ½” (0.04 ft.) from any other adjacent point within the 20-foot spaced curb survey), then the Contractor shall pave the track area with asphaltic paving. Upon completion of the asphalt paving, Contractor shall survey the track area utilizing all previous conformance survey data. The pre- track paving conformance survey shall be completed on a 20-foot longitudinal grid, with grades shot across the track (within the asphalt paving) in a minimum of 2 locations, at a distance of 10 feet and 20 feet from the center of the inside track curb. Grades shall include the curb grades inside and outside. Grades must be measured so that no point within the 20-foot grid deviates more than ¼” from any other point within the 20-foot grid. The track asphalt paving shall also undergo a flood test to inspect for birdbaths and low points that may not be identified by the conformance survey.

B. POST-TRACK SURFACING: Once the track surfacing is complete, finish surface grades shall be verified on a 20-foot grid using laser operation survey equipment. Grades at each point within the 20-foot grid must not deviate more than ¼” from any other point within the 20-foot grid. The finished track surface shall also undergo a flood test to inspect for birdbaths and low points that may not be identified by the conformance survey.

PART 4 - MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

01 07 00 - 3 CONFORMANCE SURVEYING SECTION 01 11 50

ELECTRONIC DRAWINGS

PART 1 GENERAL

1.01 SUMMARY

A. The Architect-Engineer, if requested, will provide the General Contractor with one electronic distribution of select sheets from the Contract Document Drawings for distribution to subcontractors and suppliers See Section 011150A ELECTRONIC DATA TRANSFER AGREEMENT

1.02 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. In the event of a conflict between the specifications and the Contract Documents, the Contract Documents shall govern.

B. The electronic copy will be provided electronic file transfer in AutoCAD 2014 format.

1.03 REFERENCES

A. Section 011150A ELECTRONIC DATA TRANSFER AGREEMENT

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.01 EXECUTION

A. Contractor shall provide signed agreement in full to the Engineer/Architect prior to receiving delivery of the electronic drawing files.

**END OF SECTION**

01 11 50 - ELECTRONIC DRAWINGS SECTION 01 11 50 A

ELECTRONIC DRAWINGS

ELECTRONIC DATA TRANSFER AGREEMENT

Company Requesting Files:

This Agreement is entered into by and between Rick Engineering Company (Engineer) and ______(“Requesting Party”) as of the most recent date set forth next to the signatures at the end of this Agreement. It is the intent of the parties that this agreement cover transfers of electronic data between the parties, and that the agreement and the covenants within the agreement continue for a period of one year from the date set forth below. This agreement shall automatically renew as of the day and month set forth below on each succeeding year unless specifically terminated in writing, receipt of which is actually received at least 60 days before the next expiration date.

It is understood and agreed that the calculations, drawings and specifications prepared by Engineer are to be transferred in an electronic and/or digital format to Requesting Party. It is understood between the parties that the calculations, drawings and specifications prepared pursuant to the agreement between Engineer, whether in hard copy or machine readable form, are instruments of professional service and are intended for one time use in the production of the project to which they relate. The calculations, drawings and specifications are and shall remain the property of Engineer. Requesting Party may retain copies, including copies stored on magnetic tape or disks or other electronic format, for information and reference purposes. It is understood that original drawings which may be on file with the approving agency are considered to be the original drawings of record and are not necessarily the same as any of the information set forth in the electronic or digital format that are being provided pursuant to this Agreement.

Because of the possibility that the information and data delivered in machine readable form may be altered, whether inadvertently or otherwise, Engineer reserves the right to retain the original tapes/disk or other electronic medium and to remove from copies provided to Requesting Party all identification reflecting the involvement of Engineer in the preparation of those calculations, drawings or specifications. Engineer also reserves the right to retain hard copy originals of all project documentation delivered to Requesting Party in machine readable form. It is agreed between Engineer and Requesting Party that the hard copy originals shall be referred to and shall govern in the event of any inconsistency between the hard copy originals and any electronic or machine readable calculations, drawings or specifications.

Requesting Party understands that the automated conversion of information and data from the system and format used by Engineer to an alternate system or format may result in the introduction of inexactitudes, anomalies and errors and that changes or modifications introduced to Engineer’s instruments of professional service introduced by anyone other than Engineer may result in adverse consequences which Engineer can neither predict nor control. Therefore, in consideration of Engineer’s agreement to deliver the instruments of professional service in machine readable

01 11 50 A ELECTRONIC DATA TRANSFER AGREEMENT form, Client’s Requesting Party agrees to indemnify, defend and hold Engineer, its officers, directors, principals, agents and employees harmless from and against any and all claims, damages, injury, actions and expense including attorney’s fees and costs of suit, including claims for indemnification by Client’s Consultant or Contractor relating to the design, the conversion of information and data from the system and format used by Engineer, and for any changes or modifications to Engineer’s instrument of professional services whether done on hard copy or machine readable form not specifically authorized and approved by Engineer excepting that arising from the sole negligence or willful misconduct of Engineer.

No representation or warranties, express or implied, are provided by transferring information in electronic or digital format. This includes any warranty of fitness for a particular purpose, warranty of merchantability or that of compatibility. The files are not warranted to be complete or accurate and are not considered “goods” as that term is defined under the Uniform Commercial Code as adopted in the state where the project is located, the Client is located, the Engineer is located and Client’s Requesting Party is located.

The recipient agrees that it has an independent duty to check and coordinate all information depicted by the electronic data, including but not limited to dimensions and details set forth in the digital or electronic media.

No modification of the information should be made without the express written consent of Engineer.

“ENGINEER”

RICK ENGINEERING COMPANY

By:______Date: ______

Title: ______

“REQUESTING PARTY”

By:______Date: ______

Title: ______

01 11 50 A ELECTRONIC DATA TRANSFER AGREEMENT

SECTION 01 31 19

PROJECT MEETINGS

PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions.

1.02 PROGRESS MEETINGS

A. The District will arrange and conduct progress meetings at such frequency as the District and Contractor may mutually agree.

B. Meeting minutes shall be prepared and distributed by the contractor. Meeting minutes shall be provided in Microsoft Word format 7 days or less after close of each progress meeting.

C. The purpose of the meetings will be to facilitate the Work of the Contractor and any subcontractor or other organization to coordinate and facilitate the execution of the Work, resolve conflicts and identify and resolve any potential delays or necessary changes in the Work.

D. The agenda of progress meetings shall include review of work progress, the latest construction schedule submittal, potential project delays, the status of key shop drawings, submittal reviews, information requests, safety concerns, record drawings, and extra work items.

E. The Engineer of Record, or appropriate representative will attend meetings on an as- needed basis determined by the District to aid in the resolution of design issues.

1.03 CONSTRUCTION SCHEDULE REVIEW AND NARRATIVE REPORT

A. The construction schedule will be reviewed weekly during the progress meeting to verify at a minimum:

1. Actual start and finish dates of completed activities since the last progress meeting.

2. Durations and progress of all activities not completed.

3. Critical submittals/materials delivery problems.

4. Potential project delays.

01 31 19 - 1 PROJECT MEETINGS

5. Any activity behind schedule and Contractor’s plan to bring it back on schedule.

6. Reason, logic, time, and cost data for change order work that is to be incorporated into the construction schedule or payment request form.

7. Payment due to the Contractor based on percentage complete of items in the submittal payment request form.

8. A three (3) week look ahead schedule for planning purposes.

B. The Contractor shall also submit a written narrative report to the District with the updated version of the construction schedule as a part of the weekly progress review and update, in a form agreed upon by the Contractor and the District.

C. The written narrative report shall describe at a minimum: the current and planned status of the Work for the ensuing week, identification of any problem areas and their estimated impact on performance of other activities and completion dates; and a discussion of corrective action taken or proposed.

D. If the construction schedule update is not acceptable to the District, the Contractor shall revise and resubmit the schedule to the District until an agreement is reached.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

PART 4 MEASUREMENT AND PAYMENT

4.01 PROJECT MEETINGS

A. Full compensation for conforming to the requirements of this Section, PROJECT MEETINGS including all labor, materials, equipment, tools, and incidentals will be considered included in the prices paid for various Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

01 31 19 - 2 PROJECT MEETINGS SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.01 GENERAL

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. In the event of a conflict between the specifications and the Contract Documents, the Contract Documents shall govern.

B. Contractor shall refer to section 00700 Article 44,45 of the Contract Documents.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

PART 4 MEASUREMENT AND PAYMENT

4.01 SUBMITTAL PROCEDURES

A. Full compensation for conforming to the requirements of this Section, SUBMITTALS, including all labor, materials, equipment, tools, and incidentals will be considered included in the prices paid for various Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

01 33 00 - 1 SUBMITTAL PROCEDURES SECTION 01 45 00

QUALITY CONTROL

PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. In the event of a conflict between the specifications and the Contract Documents, the Contract Documents shall govern.

B. Description: This section describes the quality control and inspection requirements that may affect the Work. These requirements and constraints are in addition to those appearing elsewhere in the Specifications.

1.01 RESPONSIBILITY

A. The District may conduct periodic independent quality assurance testing and inspection to verify compliance with the Contract Documents.

B. The District reserves the right to back charge the Contractor for retesting of deficient or defective work or products upon written notification. Compensation for retesting on behalf of the District will be made through deductions from the Contract Amount.

C. The Contractor is responsible for correcting all defective work discovered prior to final acceptance of the Contract, despite the failure of the Inspector(s) to discover it.

1.02 TESTS AND INSPECTIONS

A. Contractor shall be responsible for scheduling all required tests.

B. Contractor shall pay for all tests or re-inspections by the District, if required, and tests or inspections required due to Contractor error or lack of required identifications of material.

C. Contractor shall pay for any testing performed by the Contractor for his own quality control.

D. The District shall pay for:

1. Inspections, first-time tests of materials, and certifications requested by the District and not required by the Contract Documents.

01 45 00 - 1 QUALITY CONTROL E. Two (2) copies of the agency or laboratory report of each test or inspection specified in these Documents shall be submitted to the District. All tests of materials shall be made in accordance with the commonly recognized standards of national technical organizations, and such other special methods and tests as are prescribed in the Contract Documents.

F. One (1) copy of each of the Contractor’s purchase orders for materials forming a portion of the Work shall be submitted to the District, if requested. Each such purchase order shall contain a statement that the materials included in the order are subject to inspection by the District. Materials purchased locally will be inspected at the point of manufacture or supply, and materials supplied from points outside the San Diego Area will be inspected upon arrival at the job, except when other inspection requirements are provided for specific materials in other Sections of this Specification.

G. The Contractor shall submit such samples of materials as are required by the District, without charge. No material shall be used until the District has had the opportunity to test, examine and approve such materials. Samples will be secured and tested whenever necessary to determine the quality of the material. Samples and test specimens prepared at the job site, such as concrete test cylinders, shall be taken or prepared by the Engineer in the presence and with the assistance of the Contractor.

1.03 AUTHORITY AND DUTIES OF INSPECTOR

A. Inspectors employed by the District shall be authorized to inspect all work done and materials and equipment furnished to complement the contractor furnished independent inspector.

B. Such inspection may extend to all or any part of the Work, and to the preparation, fabrication, or manufacture of the materials and equipment to be used.

C. The Inspector shall not alter or waive the provisions of the Contract Documents.

D. The Inspector will keep the District informed as to the progress of the Work and the manner in which it is being done.

E. The Inspector will call the Contractor’s attention to nonconformance with the Contract Documents that the Inspector may have observed.

F. The Inspector will not be responsible for the adequacy or correctness of the Contractor’s means, methods, techniques, sequences, or procedures for construction.

G. The inspector will not approve or accept any portion of the Work, issue instructions contrary to the Contract Documents, or act as foreman for the Contractor.

H. The Inspector will not be responsible for:

01 45 00 - 2 QUALITY CONTROL

1. The Contractor’s quality control program. 2. The Contractor’s safety program.

3. Coordinating the work or activities of the Contractor or his subcontractor.

I. The Inspector may reject defective materials, equipment, or work when it is not in compliance with the Contract Documents.

J. The Contractor shall provide safe access to the Work for the inspector to perform his duties.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

PART 4 MEASUREMENT AND PAYMENT

4.01 QUALITY CONTROL

A. Full compensation for conforming to the requirements of this Section, QUALITY CONTROL, including all labor, materials, equipment, tools, and incidentals will be considered included in the Contract Lump Sum / Unit Price paid for the various items listed in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

01 45 00 - 3 QUALITY CONTROL SECTION 01 57 23 EROSION CONTROL/SWPPP IMPLEMENTATION

PART 1 – GENERAL

1.01 SUMMARY

A. This Section Includes the following:

Part 1.1 Summary Part 1.2 Scope of Work Part 1.3 Submittals Part 1.4 References Part 1.5 Regulations Part 1.6 Storm Water Pollution Prevention Plan

B. Description

This Section describes the temporary storm water pollution control requirements for construction sites that involve the disturbance of soil in an area that is one acre or greater. These requirements and constraints are in addition to those appearing elsewhere in the Specifications or any regulation, codes, certificates, notices, etc. that may be required by jurisdictions that have authority over the Work.

1.02 SCOPE OF WORK

A. It is assumed that this project is covered under the State Water Resources Control Board Order No. 2009-0009-DWQ, National Pollutant Discharge Elimination System (NPDES) General Permit for Storm Water Discharges Associated with Construction and Land Disturbing Activities (General Construction Storm Water Permit) and. Since the project is assumed to quality for the Rainfall Erosivity Waiver, he WPCP specification must be implemented. The Contractor is responsible for maintaining compliance with all activities described in this Section through completion of punch list activities. The work also includes the following. B. A (Water Pollution Control Plan (WPCP), shall be prepared by contractor for the project. The WPCP will then be reviewed and approved by the District. The Project Engineer will be responsible for preparing a Rainfall Erosivity Waiver on the Storm Water Multi-Application Report Tracking System (SMARTS). If construction extends beyond the dates of the assumed Rainfall Erosivity Waiver, a Storm Water Pollution Prevention Plan (SWPPP) may be required for the project

01 57 23 - 1 EROSION CONTROL/ SWPPP IMPLEMENTATION and the project may require converage under the California Construction General Permit. The contractor will be responsible for the preparation of the SWPPP and submitting the appropriate Permit Registration Documents (PRDs) on the SMARTS system if the construction completion date is extended.

C. Implementation, maintenance and updating the approved WPCP that is in conformance with the requirements of as specified in the General Construction Storm Water Permit. The WPCP and BMPs shall apply to all construction related areas and activities associated with the project as shown on the drawings and as specified in these documents, such as staging areas, equipment and material storage sites, waste management areas, temporary plant sites, and borrow pit operations which may be outside the construction limits, and shall remain and be maintained until the completion of all punch list items.

D. Implementation and maintenance of Storm Water Pollution Prevention Best Management Practices (BMPs) as described in the approved WPCP for the project.

E. Performance of storm water inspections that is in conformance with the requirements of, as specified in the General Construction Storm Water Permit.

F. Preparation and submittal of a close-out report.

1.03 SUBMITTALS

A. Water Pollution Control Plan

B. Amendments to the Water Pollution Control Plan

C. End of Project Storm Water Compliance Report, with copies of the inspection reports.

1.04 REFERENCES

The publication and guidance listed below form a part of this specification to the extent referenced. These items are referred to in the text by the basic designation only.

01 57 23 - 2 EROSION CONTROL/ SWPPP IMPLEMENTATION B. State Water Resources Control Board webpage – http://www.waterboards.ca.gov/water_issues/programs/stormwater/construction.s hmtl. Supplemental guidance on prepare of a California NPDES Construction Activities Storm Water General Permit SWPPP (General Construction Storm Water Permit).

C. Caltrans webpage – http://www.dot.ca.gov/hq/constrc/stormwater/stormwater1.htm. Supplemental guidance on the preparation of a WPCP found in the Storm Water Pollution Prevention Plan (SWPPP) and Water Pollution Control Program WPCP) Preparation Manual. BMP guidance and details are available in the Caltrans Storm Water Quality Handbooks, Construction Site Best Management Practices (BMPs) Manual. Guidance is also provided for construction storm water monitoring.

1.05 REGULATIONS

Comply with all applicable federal, state, and local regulations, including but not limited to air, water, environmental, transport and disposal regulations. Specific regulations applicable to discharges to storm water conveyance system for this project include the following:

A. State Water Resources Control Board (SWRCB) Order No. 2009-0009-DWQ, National Pollutant Discharge Elimination Systems (NPDES), General permit No. CAS000002, Waste Discharge Requirements (WDRs) for Discharges of Storm Water Runoff Associated with Construction Activity (General Construction Storm Water Permit) as amended, and/or modified.

B. Regional Water Quality Control Board (RWQCB) Order No. R9-2013-0001, NPDES Permit No. CAS0109266, Waste Discharge Requirements for discharges of Urban Runoff from the Municipal Separate Storm Sewer Systems (MS4s), Draining the Watersheds of the County of San Diego, the Incorporated Cities of San Diego County, and the San Diego Unified Port District (Municipal Storm Water Permit) as amended, and/or modified.

1.06 STORM WATER POLLUTION PREVENTION PLAN

Maintain and implement the Water Pollution Control Plan (WPCP) conforming to the requirements of this Section as part of the Technical Specifications. The Contractor shall submit the WPCP to the Engineer prior to the Pre-Construction Conference for approval. Work shall not be started until the WPCP has been approved by the District. Subsequent 01 57 23 - 3 EROSION CONTROL/ SWPPP IMPLEMENTATION modifications and amendments to the WPCP are subject to the review and approval of District.

A. WPCP: The Contractor shall complete any project-specific information in the providedWPCP as well as maintain and implement the WPCP for all applicable phases of construction, including but not limited to: clearing, grading, excavating, filling, construction, paving, and the installation of structures at water course. The WPCP includes, but not limited to, site information, identification of potential pollutants, and identification of appropriate storm water pollution prevention BMPs to be utilized by the Contractor throughout the duration of the Project, designed to prevent unauthorized discharges. If work conditions change, Contractor is required to update the WPCP to meet the conditions of the site.

1. WPCP amendments and certifications: Contractor is to have WPCM on the project team to amend and certify the project WPCP. A WPCM is defined in Section VII.B.1 of the General Construction Storm Water Permit. Documentation of WPCM qualifications is to be included in the.

2. Qualifications of the Contractor’s Storm Water Representative/Inspector: WPCMto oversee, document, and maintain all storm water compliance at the site. The WPCM is responsible for non-storm water and storm water visual observations, and any sampling and analysis. The WPCM must meet the qualifications of a “Qualified SWPPP Practitioner” as defined in Section VII.B.3 of the General Construction Storm Water Permit. The WPCM must have the authority to implement and make field decision to maintain compliance with the General Construction Storm Water Permit. Documentation of WPCM qualifications is to be included in the SWPPP.

PART 2 – PRODUCTS

2.01 MATERIALS

A. Materials shall be as shown and specified in the publications listed above.

B. The Contractor shall have adequate materials on site to deploy BMPs to protect the exposed portions of the site and to prevent sediment and pollutant discharges from the site.

PART 3 – EXECUTION

3.01 GENERAL

01 57 23 - 4 EROSION CONTROL/ SWPPP IMPLEMENTATION

A. The regulations listed in this Section prohibit degradation of water quality and require prevention or control of discharges from construction sites and construction activities for all District projects.

B. A copy of the current approved plan shall be maintained on site at all times.

C. The Contractor shall implement appropriate BMPs to prevent and/or control potential discharges and to protect the storm water conveyance system from any and all activities with the potential to release materials directly or indirectly into the storm water conveyance system.

D. If a selected BMP fails, it shall be repaired and modified, if necessary, or replaced with an acceptable alternate as soon as it is safe to do so.

E. Upon project completion, the Contractor shall prepare a storm water close-out report that satisfies the annual reporting requirements contained in Section XIV.D through E of the General Construction Storm Water Permit.

F. The Contractor is required to submit a complete copy of the approved and implanted SWPPP and any amendments along with the inspection reports at project completion.

3.02 AUTHORITY OF THE ENGINEER

A. The Engineer has the authority to limit the surface area of soils exposed by clearing and grubbing, excavation, borrow and fill operations, and to direct the Contractor to provide immediate, permanent, or temporary BMPs to minimize pollutant transport. The Engineer has the authority to require BMPs to be installed or maintained by the Contractor at any time and to stop or delay work that could result in pollutant transport, until such time as the Contractor provides adequate BMP protection.

3.03 BEST MANAGEMENT PRACTICES (BMPs)

A. The Contractor shall provide an effective combination of erosion and sediment control BMPs, Non-Storm Water Management BMPs, Materials and Waste Management BMPs.

01 57 23 - 5 EROSION CONTROL/ SWPPP IMPLEMENTATION B. Erosion control BMPs include but are not limited to: scheduling, slope roughening, preservation of existing vegetation, hydraulic mulches, temporary seeding, soil stabilizers and binders, bonded fiber matrix (BFM), erosion control blankets, and plastic covers. Temporary sediment control BMPs include but are not limited to linear sediment barriers (such as slit fence, fiber rolls, and gravel bag berms), sediment traps, storm drain inlet protection, tracking controls, and dust control.

C. Non-storm water management BMPs include but are not limited to: pavement cutting, vehicle and equipment cleaning, vehicle and equipment fueling and maintenance.

D. Materials and Waste Management BMPs include but are not limited to: material storage, stockpiles, spill prevention and control, clean up, and concrete waste management.

E. Routine storm water inspections are to be carried out by the WPCM as described in the approved WPCP. The site is to be inspected and BMPs are to be evaluated at least weekly and before, during and after a rain event. Required inspections are to be carried out for the duration of the project and through completion of punch list activities. The scheduled Inspections are to be documented and inspection reports are to be maintained on the site.

3.04 COORDINATION

A. Contractor shall coordinate with the District for the turnover of the WPCP. The Contractor shall work with the District in systematically implementing the Contractor BMPs as the District removes BMPs.

3.05 TRAINING

A. Contractor shall ensure that training on this special condition is given to all employees and subcontractors involved in construction activities. This training shall include, but not be limited to, the location of the storm drains on the job site; the direct link between the storm drain system and the bay; potential pollutants; and BMP installation, inspection, maintenance and repair.

3.06 UNAUTHROIZED DISCHARGES

A. No discharges of any material may enter the storm water conveyance system including process and wash waters, dust, petroleum products, soil or debris. The

01 57 23 - 6 EROSION CONTROL/ SWPPP IMPLEMENTATION rinsing of paint or cementitious products into storm drains in prohibited. The Contractor shall be responsible for clean-up, mitigation, and penalties resulting from failure to implement and maintain appropriate BMPs for pollution prevention.

3.07 NOTIFICATION

A. The Contractor shall notify the District immediately of any unauthorized releases to the storm drain. The Contractor shall immediately document all unauthorized releases including but not limited to the time, date and duration, material released, and action taken to stop discharge and prevent future discharges. Documentation shall be provided to the Engineer and included in the WPCP.

3.08 CLEAN UP

A. All temporary BMPs and unsalvageable materials used in the storm water pollution prevention program shall be removed and properly disposed of outside of the tidelands at the completion of work.

PART 4 – MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

4.02 EROSION CONTROL IMPLEMENTATION, ITEM NO. 3:

A. EROSION CONTROL IMPLEMENTATION will be paid at the Contract lump sum amount for EROSION CONTROL IMPLEMENTATION, which shall include full compensation for furnishing all labor, materials, equipment, tools, and incidentals for doing all the work of TEMPORARY STORM WATER POLLUTION CONTROL to complete in place, including but not limited to stabilization, maintenance and inspection of BMPs, replacement of BMPs, implementing, maintaining, updating and amending the WPCP, as shown on the Drawings and as specified in these Technical Specifications, and no additional compensation shall be allowed therefore.

**END OF SECTION**

01 57 23 - 7 EROSION CONTROL/ SWPPP IMPLEMENTATION SECTION 01 71 13

MOBILIZATION

PART 1 GENERAL

1.01 SUMMARY

A. Work Included: This section includes obtaining bonds, insurance, permits, and licenses; assembling and transporting employees and equipment, acquiring and posting notices and signs; and complying with work and regulatory restrictions for the project.

1.02 RELATED WORK SPECIFIED ELSEWHERE:

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. In the event of a conflict between the Specifications and the Contract Documents, the Contract Documents shall govern.

1.03 GENERAL

A. Mobilization shall include the obtaining of all bonds, insurance, permits, and licenses; moving onto the site, equipment, construction facilities; all as required for the proper performance and completion of the Work. Mobilization shall include, but not be limited to, the following principal items:

1. Moving on to the site of all Contractors’ equipment and signage.

2. Posting all EPA and CAL/OSHA required notices.

3. Post all required labor and EEOE notices.

4. Obtaining all bonds, insurance and licenses.

5. Demobilization and site clean-up.

6. Providing temporary construction facilities.

7. Meeting other project requirements as specified in the Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

PART 4 MEASUREMENT AND PAYMENT

01 71 13 - 1 MOBILIZATION 4.01 MOBILIZATION

A. The contract lump sum price paid for MOBILIZATION shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals, and for doing all the work involved in MOBILIZATION, complete in place, as shown on the drawings, as specified in these special provisions, and as directed by the District.

B. Partial payments for mobilization under this item will be made in accordance with the following provisions:

1. The total Mobilization cost provided by contractor in the Bid Schedule shall not exceed (3%) of the total project cost.

2. The first partial payment (included as part of the Contractor’s normal monthly pay request) for mobilization will be made at 50-percent of the lump sum price bid, at such time that the following has been submitted and approved by the District, which may include the following: (1) The project Construction schedule; (2) Health and Safety Plan; (3) The Injury and Illness Prevention Program; (4) Construction Site Security Plans (CSSP); (5) Work Access Plan; (6) Schedule of project submittals are provided to the satisfaction of the District.

3. The second partial payment (included as part of the Contractor’s normal monthly pay request) for mobilization will be made at 30-percent of the lump sum price bid when: (1) the District has determined that 50 percent of the Contract work has been completed by the Contractor.

4. The third and final payment (included as part of the Contractor’s normal monthly pay request) of the lump sum price for mobilization shall be 20 percent of the lump sum price bid and shall be included in the final payment request and when demobilization and clean-up are complete.

**END OF SECTION**

01 71 13 - 2 MOBILIZATION SECTION 01 74 19

CONSTRUCTION AND DEMOLITION MATERIALS MANAGEMENT

PART 1 GENERAL

1.01 DESCRIPTION

A. The Work includes the preparation and implementation of the Materials Management and Disposal Plan, including implementation of practices and procedures to manage demolition, and storage of materials, properly dispose of waste materials.

B. Storage of salvaged improvements such as benches, signs, concrete stops to be reused, parking lot lights, or other improvement to be reinstalled per the Construction Plans and Documents.

1.02 SUBMITTALS

A. Materials Management and Disposal Plan including the following components:

1. Personnel

2. Material Management and Disposal Methods

3. Stockpile, Storage and Staging Area Exhibit

4. Transportation

5. Receiving Facilities

6. Monthly Materials Management and Disposal Report

B. Landfill Disposal Types:

1. Class I Landfill: Class I landfill sites may accept hazardous and nonhazardous wastes as defined in the California Code of Regulations at the website listed below.

2. Class II Landfill: Class II landfill sites may accept “designated” and nonhazardous wastes as defined in the California Code of Regulations at the website listed below.

3. Class III Landfill: Class III landfill sites may accept nonhazardous wastes as defined in the California Code of Regulations.

01 74 19 - 1 CONSTRUCTION AND DEMOLITION MATERIALS MANAGEMENT 4. Land Disposal Site Locations: Classified waste requiring disposal should be delivered to an appropriate State-licensed landfill location. Descriptions of various waste classifications and locations for Class I, II, and III waste disposal sites can be found at the following State of California website: http://www.waterboards.ca.gov/water_issues/programs/land_disposa l/walist.shtml

C. Recycling: The process of sorting, cleaning, and reconstituting materials to use the material in the manufacture of a new product.

D. Reuse: Making use of a material without altering the material's basic form.

E. Solid Waste: Garbage, refuse, debris, sludge, or other discharged material, including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.

F. Waste classification: Waste classification should be determined using information found in the State of California website: http://waterboards.ca.gov/water_issues/programs/land_disposal/waste_cl ass.shtml

1.03 MATERIALS HANDLING

A. In general, asphalt concrete and portland cement concrete, demolished utilities, saturated soil, unsuitable materials, hazardous materials, and other miscellaneous demolition materials shall be segregated by Contractor, transported and stockpiled, and stored separately for further characterization, as specified in this Section.

1.04 MATERIALS SCREENING AND SEGREGATION

A. During the Contractor’s demolition, trenching and other earthwork activities, the District’s Geotechnical Consultant will evaluate removed soil, asphalt, and base for geotechnical suitability for recycle or reuse. The Contractor shall segregate and stockpile soils deemed to be geotechnically unsuitable, as directed by the Geotechnical Consultant.

B. The Contractor shall segregate and store all signs, lights, wheel stops, and other site furnishings as indicated to be salvaged and reinstalled per the Construction Documents into damaged or “suitable for reuse” storage areas for review by the District for reinstallation.

1.05 DISPOSAL

A. After further characterization of stockpiles and storage areas are performed by the District, or authorized District’s Representative, they will notify the Contractor in writing of the materials to be recycled, reused, or to be disposed.

01 74 19 - 2 CONSTRUCTION AND DEMOLITION MATERIALS MANAGEMENT

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.01 SITE MANAGEMENT

A. General:

1. Stockpiles and material containers shall be placed in accordance with the approved Materials Management and Disposal Plan.

2. Stockpiles, containers and bins shall be clearly labeled for each type of material.

3. Stockpile and container areas shall be maintained in a neat and clean manner.

4. Stockpile and material containers shall be managed to prevent intermixing with other materials.

3.02 COORDINATION

A. Notify the District/Inspector at least 72 hours prior to the start of any demolition, excavation or removal of soils from the Work Site. The District will notify the Geotechnical Consultant.

B. The Contractor shall provide safe access to the work area during demolition and earthwork activities to allow the District and Geotechnical Consultant to screen materials.

C. Use methods and equipment that result in minimal disturbance beyond the excavation limits.

3.03 STOCKPILE MANAGEMENT

A. Place material in stockpiles or containers, as directed by the District who may delegate such responsibility to the Geotechnical Consultant. Stockpile locations will be coordinated with the District and Contractor. Temporary stockpiles shall be located in the area shown on the Plans and shall be identified and marked as directed by the District and/or Geotechnical Consultant

B. Implement proper BMPs to divert water from the stockpile areas.

C. Cooperate with District on location and size of stockpiles. Stockpiles shall be documented by providing the District with a report and/or exhibit of the approximate original location of the material, the amount of material stockpiled, the date, stockpile

01 74 19 - 3 CONSTRUCTION AND DEMOLITION MATERIALS MANAGEMENT number and the approximate location of the stockpile. Stockpile information to be painted on the stockpile cover.

3.04 DISPOSAL

A. After the disposal determination and waste profiling is performed, materials may be transported and disposed of properly as mandated by statutes, and as formally reported to the District.

B. As required by the District, submit a Materials Management and Disposal Report, including current copies of the following:

1. Transport Log

2. Waste Disposal: Waste handling facilities' weight tickets. Prices paid or received need not be reported to the Engineer.

3. Waste Determination Documentation

4. Materials Management Site Drawing: Prepare an updated neatly made sketch approximately to scale showing areas being used for processing, sorting, loading and temporary stockpiling of materials. Site drawing will identify locations of stockpiles and the duration that each stockpile was located at the site. Identify location and date of transfer of responsibility to others.

PART 4 MEASUREMENT AND PAYMENT

A. Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid Item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

01 74 19 - 4 CONSTRUCTION AND DEMOLITION MATERIALS MANAGEMENT

SECTION 01 77 10

CLOSEOUT PROCEDURES

PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. In the event of a conflict between the Specifications and the Contract Documents, the Contract Documents shall govern.

**END OF SECTION**

01 77 10 – 1 CLOSEOUT PROCEDURES

SECTION 01 78 00

PROJECT RECORD DOCUMENTS

PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. In the event of a conflict between the Specifications and the Contract Documents, the Contract Documents shall govern.

B. Refer also to 00700 Article 55,56.

1.02 SUMMARY

A. This Section includes administrative and procedural requirements for Project Record Documents, including the following:

B. Record Drawings.

C. Record Specifications.

D. Record Product Data.

E. Record Specifications: Submit one copy of Project's Record Specifications, including addenda and contract modifications assumes one copy for Owner, and none for EOR.

F. Miscellaneous Record Submittals: Submit one as specified in Part 2.

PART 2 PRODUCTS

2.01 RECORD DRAWINGS

A. Record Prints: Maintain one set of prints of the Contract Drawings and Shop Drawings per the Contract documents 00700, Article 56.

B. Record data as soon as possible after actual work item has been completed. Record and check the markup before enclosing concealed installations.

C. Record drawings will be verified by Construction Manager for update status in conjunction with monthly pay applications. Record drawings must be updated to current status as a requirement for payment application approval.

01 78 00 - 1 PROJECT RECORD DOCUMENTS D. Content: Types of items requiring marking include, but are not limited to, the following:

1. Dimensional changes to Drawings.

2. Revisions to details shown on Drawings.

3. Locations and depths of underground utilities.

4. Sizes and invert elevations of piping below grade

5. Sizes of conduit below grade.

6. Exact locations and sizes of plugged wyes, tees, caps, and manholes.

7. Exact locations of valves, pull boxes, and pull boxes.

8. Specific conduit pathways for each type of cabling route from initial point of termination to the final point of termination.

9. Revisions to routing of piping and conduits.

10. Revisions to electrical circuitry.

11. Changes made by Engineer's Supplemental Instruction, Change Order, Construction Change Directive, Request for Information, or other written directive from Engineer. Note corresponding reference numbers for each item.

12. Details not on the original Contract Drawings.

13. Field records for variable and concealed conditions.

E. Record information on the Work that is shown only schematically.

1. Indicate location and layout of items by measured dimension to building corners or other permanent features.

2. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately.

3. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

4. Mark important additional information that was either shown schematically or omitted from original Drawings.

01 78 00 - 2 PROJECT RECORD DOCUMENTS 5. Note the following, where applicable: a. Addenda item numbers.

b. Alternate numbers.

c. Change Order numbers.

d. Construction Change Directive numbers.

e. Supplemental Instruction numbers

f. Request for Information numbers

F. Format: Identify and data each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.

G. Record Prints: Organize Record Prints into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

H. Identification: As follows:

1. Project name.

2. Date.

3. Designation "PROJECT RECORD DRAWINGS."

4. Name of Engineer and Construction Manager

5. Name of Contractor.

2.02 RECORD SPECIFICATIONS

A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications originally, including changes resulting from addenda and contract modifications.

B. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

C. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

D. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made

E. Note the following, where applicable:

01 78 00 - 3 PROJECT RECORD DOCUMENTS 1. Addenda item numbers.

2. Alternate numbers.

3. Change Order numbers.

4. Construction Change Directive numbers.

5. Supplemental Instruction numbers.

6. Request for Information numbers.

2.03 RECORD PRODUCT DATA

A. Preparation: Mark Product Data to indicate the actual product installation where installation varies substantially from that indicated in Product Data submittal.

B. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

C. Include significant changes in the product delivered to Project site and changes in manufacturer's written instructions for installation.

D. Note the following, where applicable:

1. Addenda item numbers.

2. Alternate numbers.

3. Change Order numbers.

4. Construction Change Directive numbers.

5. Supplemental Instruction numbers.

6. Request for Information numbers.

PART 3 EXECUTION

3.01 RECORDING AND MAINTENANCE

A. Record Prints: Maintain one set of prints of the Contract Drawings and Shop Drawings per the Contract documents 00700, Article 55,56.

B. Post changes and modifications to Project Record Documents as they occur; do not wait until the end of Project.

01 78 00 - 4 PROJECT RECORD DOCUMENTS C. Maintenance of Record Documents and Samples: Store Record Documents and Samples in the field office apart from the Contract Documents used for construction. Do not use Project Record Documents for construction purposes.

D. Maintain Record Documents in good order and in a clean, dry, legible condition, protected from deterioration and loss. Provide access to Project Record Documents for District’s and Construction Manager's reference during normal working hours.

E. Record documents are to be maintained continuously in a state of completion reflecting current progress of completed Work at all times. Applications for Payment as specified in Contract

F. Documents - Payment Procedures will not be processed until District has verified record documents are fully updated.

**END OF SECTION**

01 78 00 - 5 PROJECT RECORD DOCUMENTS

SECTION 02 41 00

DEMOLITION

PART 1 GENERAL

1.01 SUMMARY

A. The work of the demolition includes, but is not limited to, saw cutting, breaking, removing, loading, hauling, disposing, and placing temporary stockpiles for reuse, and storage for reinstallation (as directed for further characterization by the Owner) for the following items: AC paving, aggregate base, concrete curb and gutter, concrete sidewalk, storm drain pipe and structures, and other miscellaneous materials necessary to be removed to construct the Project and clearing and grubbing as specified in this Section - Demolition, and Section 31 11 00 - Clearing and Grubbing.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 31 11 00 Clearing and Grubbing

B. Section 01 57 23 Erosion Control Implementation

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

2. State of California, Department of Transportation, Standard Specifications, 2010.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

C. American National Standards Institute (ANSI)

1. ANSI AIO.G Safety Requirements for Demolition Operations

1.04 PERMITS

A. The Contractor shall obtain all special permits and licenses and give all notices required for performance and completion of the demolition and removal work, hauling, and disposal of debris.

02 41 00 - 1 DEMOLITION

1.05 SUBMITTALS

A. Permits: Submit copies of demolition, hauling, and debris disposal permits and notices for record purposes. Include description of proposed haul routes to the District/Owner for review and approval.

1.06 SITE CONDITIONS

A. Protection of Persons and Property:

1. Erect and maintain temporary bracing, shoring, lights, barricades, signs, and other measures as necessary to protect the public, workers, and adjoining property from damage from demolition work, all in accordance with applicable codes and regulations.

2. Open depressions and excavations occurring as part of this work shall be barricaded and posted with warning lights when accessible through adjacent property or through public access. Operate warning lights during hours from dusk to dawn each day and as otherwise required.

3. Protect utilities, pavements, and facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by demolition operations.

B. Protection of Existing Facilities and Utilities:

1. Contractor to pothole, confirm location of existing utilities, and notify the District of Conflicts.

2. Protect active sewer, water, gas, electric, groundwater monitoring , and other utilities; and drainage and irrigation lines indicated or, when not indicated, found or otherwise made known to the Contractor before or during demolition work. If utility is damaged, immediately notify the utility owner for corrective action.

3. Should the Contractor elect, for ease of construction, to temporarily turn off existing facilities and/or utilities, the contractor shall request in writing, to the Owner, and provide schedule and construction plan. With the appropriate authorizations, the Contractor shall also arrange with and perform work as required by utility companies for discontinuance or interruption of utility services due to demolition work with no cost to the Owner/District.

C. Unknown Conditions:

02 41 00 - 2 DEMOLITION

1. The Contract Drawings and related documents may not represent all surface conditions at the site and adjoining areas. The known surface conditions are as indicated, and shall be compared with actual conditions before commencement of work.

2. Existing utilities and drainage systems below grade are located from existing documents and from surface facilities such as manholes, valve boxes, area drains, and other such surface fixtures.

3. If existing active services encountered are not indicated or otherwise made known to the Contractor and interfere with the permanent facilities under construction, notify the Owner/District and the Engineer in writing, requesting instructions on their disposition. Take immediate steps to ensure that the service provided is not interrupted, and do not proceed with the work until written instructions are received from the District and/or Engineer.

4. Remove pavement, and existing ground to the required depth per the Geotechnical Consultant to the specified thickness as required to prepare the new subgrade, base and AC and/or PCC pavements

PART 2 MATERIALS

2.01 MATERIALS, EQUIPMENT, AND FACILITIES

A. The Contractor shall furnish all materials, tools, equipment, devices, appurtenances, facilities, and services as required for performing the demolition and removal work.

B. Materials used for backfill, or reuse in new pavement sections shall conform to the requirements for fill material of Section 31 22 00 – Grading, and shall be inspected by the Geotechnical Engineer of Record.

PART 3 EXECUTION

3.01 PRESERVATION OF REFERENCE MARKERS & SURVEY MONUMENTATION

A. Though it is not anticipated from existing records, should reference markers or monuments be encountered during demolition work, the Contractor shall, preserve, or survey locate and replace them upon completion of the work. Re-establish survey markers and monuments in conformance with the recorded reference points. Forward to the Engineer a letter verifying re-establishment of survey markers and monuments, signed by a licensed civil engineer or land surveyor currently registered in the State of California.

3.02 DEMOLITION

02 41 00 - 3 DEMOLITION

A. Perform demolition in accordance with the approved Demolition Plans Perform demolition work in accordance with ANSI A10.6 and the California Code of Regulations, Title 8 and Title 24, as applicable.

B. Storm Water Diversion Plan

1. Contractor shall be responsible for preparation and implementation of a Storm Water Diversion Plan prior to demolition of existing storm drain piping and/or structures and maintain operation of the storm water diversion system until the proposed storm drain system is constructed and accepted by the District. Storm water diversion plan shall be subject to approval by the District and the Engineer.

2. Contractor shall be responsible to monitor weather reports and prepare the storm drain diversion system for implementation prior to all storm events.

3.03 REMOVAL

A. Sawcut, break, and remove existing AC paving, aggregate base, concrete paving, concrete curb and gutter, storm drain pipe and structure and other miscellaneous materials, and site improvements, as shown on the construction plans and as necessary for construction of the project. The stockpile & storage management of the removed materials and their associated payment shall be in accordance with Section

3.04 STOCKPILING, STORAGE AND DISPOSAL OF REMOVED MATERIALS AND DEBRIS

A. The stockpile management and disposal of the removed materials and their associated payment shall be in accordance with Section 01 74 19 – Construction and Demolition Materials Management.

B. Contractor shall place in a storage area, coordinated with the District, all existing items as specified to be salvaged per the bid schedule and construction plans, including but not limited to signs and wheel stops in a location as approved by the Owner/District.

C. Burying or burning of trash and debris on the site will not be permitted. Burning of trash and debris at the site will not be permitted.

3.05 CLEANUP

A. Provide a clean and orderly site at all times, in accordance with Contract Documents Section 00700 Article 65.

PART 4 MEASUREMENT AND PAYMENT

02 41 00 - 4 DEMOLITION

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid Item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

4.06 REMOVAL AND SALVAGE SIGN, BID ITEM

A. Payment shall include all work to remove sign, pole and foundation, and to transport, and store signs to be reinstalled during later construction phase.

B. Damaged signs shall be reported to the Owner/District for storage or disposal as directed.

C. Signage damaged during removal or transport shall be replaced in kind at cost to the District/Owner.

**END OF SECTION**

02 41 00 - 5 DEMOLITION

SECTION 10 43 10

SIGNS PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. This Section includes the following:

1. Panel signs.

2. Dimensional characters (letters and numbers) for exterior use.

3. Signage accessories.

1.02 SUBMITTALS

A. Product Data: Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for each type of sign.

B. Shop Drawings: Include plans, elevations, and large-scale sections of typical members and other components. Show mounting methods, grounds, mounting heights, layout, spacing, reinforcement, accessories, and installation details.

1. Provide message list for each sign, including large-scale details of wording, lettering, and Braille layout.

C. Samples for Initial Selection: For each type of sign material indicated that involves color selection.

D. Qualification Data: For Installer.

E. Maintenance Data: For signage cleaning and maintenance requirements to include in maintenance manuals.

1.03 QUALITY ASSURANCE

A. Installer Qualifications: An employer of workers trained and approved by signage manufacturer.

B. Source Limitations: Obtain each sign type through one source from a single manufacturer.

C. Regulatory Requirements: Comply with the Americans with Disabilities Act (ADA) and with code provisions as adopted by authorities having jurisdiction. D. Interior Code Signage: Provide signage as required by accessibility regulations and requirements of authorities having jurisdiction. These include, but are not limited to, the following:

10431-1 SIGNS

1. Signs for Accessible Spaces

1.04 PROJECT CONDITIONS

A. Field Measurements: Where sizes of signs are determined by dimensions of surfaces on which they are installed, verify dimensions by field measurement before fabrication and indicate measurements on Shop Drawings.

1.05 COORDINATION

A. For signs supported by or anchored to permanent construction, advise installers of anchorage devices about specific requirements for placement of anchorage devices and similar items to be used for attaching signs.

1. For signs supported by or anchored to permanent construction, furnish templates for installation of anchorage devices.

PART 2- PRODUCTS

2.01 MANUFACTURERS

A. In other Part 2 articles where titles below introduce lists, the following requirements apply for product selection:

1. AvailableManufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the manufacturers specified.

2. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified.

3. Basis-of-Design Product: The design for each sign is based on the product named. Subject to compliance with requirements, provide either the named product or a comparable product by one of the other manufacturers specified.

2.02 PANEL SIGNS

A. General: Provide panel signs that comply with requirements indicated for materials, thicknesses, finishes, colors, designs, shapes, sizes, and details of construction.

B. Produce smooth panel sign surfaces constructed to remain flat under installed conditions within tolerance of plus or minus 1/16 inch measured diagonally.

C. Manufacturers:

1. American Graphics Inc.

2. Andco Industries Corp. 10431-1 SIGNS

3. APCO Graphics, Inc.

4. ASI Sign Systems, Inc.

5. Best Manufacturing Co.

6. Grimco, Inc.

7. Innerface Sign Systems, Inc.

8. Kaltech Industries Group, Inc.

9. Signature Signs, Inc.

10. Supersine Company (The).

D. Cast-Acrylic Sheet: Manufacturer's standard and as follows:

1. Color: As selected by Architect from manufacturer's full range.

E. Graphic Content and Style: Provide sign copy that complies with requirements indicated in the Sign Schedule for size, style, spacing, content, mounting height and location, material, finishes, and colors of signage.

F. Tactile and Braille Copy: Manufacturer's standard process for producing copy complying with ADA Accessibility Guidelines and ICC/ANSI A117.1. Text shall be accompanied by Grade 2 braille. Produce precisely formed characters with square cut edges free from burrs and cut marks.

1. Panel Material: Opaque acrylic sheet.

2. Raised-Copy Thickness: Not less than 1/32 inch.

2.03 DIMENSIONAL CHARACTERS

A. Manufacturers:

1. American Graphics Inc.

2. A.R.K. Ramos.

3. ASI Sign Systems, Inc.

4. Charleston Industries, Inc.

5. Gemini Incorporated.

10431-1 SIGNS

6. Grimco, Inc.

7. Innerface Sign Systems, Inc.

8. Kaltech Industries Group, Inc.

9. Metal Arts; Div. of L&H Mfg.

10. Signature Sign Signs, Inc.

B. Aluminum Castings: Provide aluminum castings of alloy and temper recommended by sign manufacturer for casting process used and for type of use and finish indicated.

C. Cast Characters: Form individual letters and numbers by casting. Produce characters with smooth flat faces, sharp corners, and precisely formed lines and profiles, free from pits, scale, sand holes, and other defects. Cast lugs into back of characters and tap to receive threaded mounting studs. Comply with requirements indicated for finish, style, and size.

1. Material: Aluminum.

2.04 PANEL SIGN TYPES

A. Room Signs:

1. Material: Cast-acrylic sheet.

2. Perimeter: Unframed.

3. Copy: Tactile and Braille.

4. Character Style: Helvetica

5. Text: As indicated in the Sign Schedule.

6. Message: Fixed.

B. Sizes:

1. Sign: Per Drawing T-3.

2. Character: Minimum 1-inch-high characters.

10431-1 SIGNS

C. Interior Signs:

1. Material: Cast-acrylic sheet.

2. Perimeter: Unframed.

3. Copy: Raised.

4. Character Style: Helvetica.

5. Text: As indicated in the Sign Schedule.

6. Message: Fixed.

7. Sizes:

a. Sign: Per Drawing T-3.

b. Character: Minimum 1-inch-high characters.

D. Toilet Room Signs

1. Material: Cast-acrylic sheet.

2. Perimeter: Unframed.

3. Copy: Raised.

4. Character Style: Helvetica.

5. Text :According to requirements in the California Title 24 or of authorities having jurisdiction, whichever are more stringent.

6. Message: Fixed

7. Sizes:

a. Sign: Per Drawing T-3.

E. Symbols of Accessibility: Provide 6-inch- high symbol fabricated from opaque nonreflective vinyl film, 0.0035-inch nominal thickness, with pressure-sensitive adhesive backing suitable for both exterior and interior applications.

2.05 ACCESSORIES

A. Mounting Methods: Use concealed mechanical fasteners, silicone adhesive fabricated from materials that are not corrosive to sign material and mounting surface. 10431-1 SIGNS

B. Anchors and Inserts: Provide nonferrous-metal or hot-dip galvanized anchors and inserts for exterior installations and elsewhere as required for corrosion resistance. Use toothed steel or lead expansion-bolt devices for drilled-in-place anchors. Furnish inserts, as required, to be set into concrete or masonry work.

C. Note Holders: Manufacturer's standard aluminum paper sheet holders.

2.06 FINISHES, GENERAL

A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes.

B. Protect mechanical finishes on exposed surfaces from damage by applying strippable, temporary protective covering before shipping.

C. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-half of range of approved Samples. Noticeable variations in same piece are not acceptable. Variations in appearance of other components are acceptable if they are within range of approved Samples and are assembled or installed to minimize contrast.

2.07 ALUMINUM FINISHES

A. Clear Anodic Finish: Manufacturer's standard clear anodic coating, 0.018 mm or thicker, over a satin (directionally textured) mechanical finish.

PART 3 EXECUTION

3.01 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of work.

B. Verify that items including anchor inserts, provided under other sections of Work are sized and located to accommodate signs.

C. Examine supporting members to ensure that surfaces are at elevations indicated or required to comply with authorities having jurisdiction and are free from dirt and other deleterious matter.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

3.02 INSTALLATION

A. General: Locate signs and accessories where indicated, using mounting methods of types described and in compliance with manufacturer's written instructions.

1. Install signs level, plumb, and at heights indicated, with sign surfaces free from distortion and other defects in appearance. 10431-1 SIGNS

2. Interior Wall Signs: Install signs on walls adjacent to latch side of door where applicable. Where not indicated or possible, such as double doors, install signs on nearest adjacent walls. Locate to allow approach within 3 inches of sign without encountering protruding objects or standing within swing of door.

B. Wall-Mounted Panel Signs: Attach panel signs to wall surfaces using methods indicated below:

1. Silicone-Adhesive Mounting: Use liquid-silicone adhesive recommended in writing by sign manufacturer to attach signs to irregular, porous, or vinyl- covered surfaces. Use double-sided vinyl tape where recommended in writing by sign manufacturer to hold sign in place until adhesive has fully cured.

2. Mechanical Fasteners: Use nonremovable mechanical fasteners placed through predrilled holes. Attach signs with fasteners and anchors suitable for secure attachment to substrate as recommended in writing by sign manufacturer.

3. Where panel signs are scheduled or indicated to be mounted on glass, provide matching plate on opposite side of glass to conceal mounting materials.

C. Dimensional Characters: Mount characters using standard fastening methods recommended in writing by manufacturer for character form, type of mounting, wall construction, and condition of exposure indicated. Provide heavy paper template to establish character spacing and to locate holes for fasteners.

1. Flush Mounting: Mount characters with backs in contact with wall surface.

2. Projected Mounting: Mount characters at projection distance from wall surface indicated.

3.03 CLEANING AND PROTECTION

A. After installation, clean soiled sign surfaces according to manufacturer's written instructions. Protect signs from damage until acceptance by Owner.

3.04 SIGN TYPES

A. Panel Sign

1. Room Identification.

2. Refer to details in construction drawings.

3. Sanitary facilities identification.

10431-1 SIGNS

4. These signs shall meet the requirements of CCR Title 24. Provide appropriate international symbol pictorials, and, where noted, written messages.

5. Men’s: An equilateral triangle ¼” thick with edges 12” long and a vertex pointing upward.

6. Women’s: A circle ¼” thick and 12” in diameter.

7. Unisex: An equilateral triangle ¼” thick extending to the edge of and mounted on a circle ¼” thick and 12” in diameter.

B. Individual Letters

1. Size: 12”

2. Letterstyle: Helvetica Medium Uppercase.

3. Braille equivalent to letters per?

4. Refer to E6/T3 in construction drawings for font compliance.

C. Exterior Sign

1. Disabled Access and Directional Signage.

2. These signs shall meet the requirements of Title 24, for disabled parking stalls and path of travel (10431.2.5.E).

3.05 SIGN SCHEDULE

All signage text is to be verified with by Contractor with College prior to submittal processing.

**END OF SECTION**

10431-1 SIGNS

SECTION 12 93 00 ATHLETIC SITE FURNISHINGS

PART 1 - GENERAL

1.01 SUMMARY

A. Furnish all labor, materials, miscellaneous hardware, foundations, miscellaneous appurtenances, facilities, transportation and services required for installation of all site furnishings and related work as shown on the Drawings and/or specified herein.

B. Scope of work: The general extent of work contained in this section is shown on the drawings and can include, but may not be limited to, installation of the following: 1. Discus Cage 2. Discus throw circle 3. Shot Put Ring 4. Shot Put Toe Board 5. Pole Vault Box & Cover 6. Long Jump/Triple Jump Sand Pit System 7. Long / Triple Jump Take off board / tray systems 8. Steeplechase Hurdle

C. Related sections can include, but may not be limited to: 1. Section 01 33 00 – Submittals 2. Section 01 71 23 – Field Engineering 3. Section 01 78 39 – Record Drawings 4. Section 32 12 16 – Asphaltic Concrete Paving 5. Section 32 13 13 - Portland Cement Concrete 6. Section 32 18 23 – Track Surfacing – Vulcanized Rubber

1.02 REFERENCES AND REGULATORY REQUIREMENTS

A. State of California Department of Transportation Standard Specifications, current edition.

B. California Building Code, current edition

C. NCAA Track and Field Facility Rule of Sport, Current Edition

D. American Sports Builders Association Track Construction Manual.

1.03 SUBMITTALS

A. Conform to Section 01300 Submittals and applicable Division One and

12 93 00 - 1 ATHLETIC SITE FURNISHINGS Division Two specifications, General Conditions and/or Special Provisions.

B. Product Data: Submit catalog cut sheets of all materials and equipment proposed to be furnished and/or installed under this portion of the work. Include the manufacturer and distributor name, sub-contractor as applicable. Insure that the cut sheets clearly describe the specific product by catalog number and that additional non-specified products that may appear on the same cut sheet are crossed out where applicable.

C. Samples: Submit samples of colors and finishes for all applicable products and furnishings for selection by District’s Representative.

D. Shop Drawings: Submit complete shop drawings for all materials or furnishings requiring field or shop fabrication.

1.04 QUALITY ASSURANCE

A. Review: All equipment shall be reviewed for conformance with the intent of the Contract Documents and accepted by the contractor prior to installation. All site furnishings shall be in a new, “first-class” condition, per the discretion of the District’s Representative, prior to Final Acceptance.

1.05 DELIVERY, STORAGE AND HANDLING

A. The contractor is responsible for coordination of the delivery, acceptance, handling and storage of all site furnishings.

B. Store and handle site furnishings as acceptable to the District’s Representative and so that work or access of others is not impeded.

C. The contractor shall protect all site furnishings from theft or damage at all times until such items have been accepted by the District.

PART 2 - PRODUCTS

2.01 SITE FURNISHINGS

Contact information: UCS: Michael Chappell, (704) 732-9922

12 93 00 - 2 ATHLETIC SITE FURNISHINGS

Description Brand Model # Finish/Color A. Discus Ring UCS 725-2565 Aluminum

B. Discus Cage UCS 570-0600R Aluminum

C. Shot Put Ring UCS 725-2575 Aluminum

D. Shot Put Toe Board UCS 716-1640 Aluminum

E. Long Jump/Triple UCS 519-3215 Track surfacing on Jump Pit Form, cover to be Sand Catcher and installed by track Pit Cover System surfacing contractor

F. Long / Triple Jump UCS 519-2100 Aluminum - Track Take off Boards / surfacing on cover Tray system to be installed by track surfacing contractor G. Cast Aluminum Pole UCS 711-1100 Track surfacing on Vault Box and Cover 711-1401 cover to be installed by track surfacing contractor H. Steeple Chase UCS 506-5413 N/A Adjustable Water Jump Barrier

PART 3 - EXECUTION

3.01 SEQUENCING AND SCHEDULING

A. Coordinate construction timing of installation of site furnishings in conformance with all other pertinent work.

B. Concrete footings shall conform to requirements of Section 32 13 13 - Portland Cement Concrete unless noted otherwise.

3.02 INSTALLATION

A. Concrete Footings: Install as shown in Drawings unless noted otherwise.

B. Equipment: Conform to layout shown on Drawings. Erect in strict

12 93 00 - 3 ATHLETIC SITE FURNISHINGS conformance with Details, accepted Shop Drawings, and manufacturer's instructions.

C. All bolts shall be cut back to within three threads of the nut. Relevant to benches, bleachers, and other materials with exposed bolts.

3.03 FIELD QUALITY CONTROL

A. All site furnishings shall be inspected and accepted upon delivery by the Contractor. Final acceptance of site furnishings and locations of site furnishings shall be per the discretion of the District’s Representative.

PART 4 - MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

12 93 00 - 4 ATHLETIC SITE FURNISHINGS

SECTION 31 11 00

CLEARING AND GRUBBING

PART 1 GENERAL

1.01 SUMMARY

A. This Section includes requirements for clearing and grubbing, and removal of other incidental existing improvements, undesirable plant growth within the limits of work within the project area that are not specifically identified by demolition plan. Remove rubbish and debris from the project site; do not allow accumulations. Store materials that cannot be removed daily in either area specified by the Owner/District or within the confines of the Contractor’s stockpile area(s).

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 57 23 – Erosion Control Implementation

B. Section 02 41 00 – Demolition

C. Section 31 22 00 - Grading

1.03 REFERENCES

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

1. Standard Specifications

a. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

2. Standard Drawings

b. San Diego Regional Standard Drawings (2012).

1.04 SITE INSPECTION AND LOCATION OF EXISTING ON-SITE UTILITIES:

A. Prior to all work of this Section, carefully inspect the entire site and all existing items to be cleared and removed or to be left intact, and determine an orderly sequence for the performance of this work. in hazardous or objectionable conditions such as, but not limited to, flooding, or pollution. Dust control shall be in conformance with Section 7-8 of the SSPWC.

PART 2 PRODUCTS (NOT USED)

31 11 00 - 1 CLEARING AND GRUBBING

PART 3 EXECUTION

3.01 GENERAL

A. Perform all clearing and grubbing in accordance with Section 300-1 of the SSPWC and as prescribed in this section.

B. Comply with all applicable Federal, State, and local hauling and disposal regulations, including air pollution and environmental regulations.

C. Comply with all applicable traffic control requirements required by the District and the City of National City for construction traffic.

D. Noise shall be kept at a reasonable level (in the opinion of Owner/District) as related to specific items of equipment used, and their hours of use.

E. Protect all facilities to remain.

F. Protect trees, plant growth, and features designated to remain.

G. Protect benchmarks, property corners, and other survey monuments from damage or displacement. If marker needs to be removed it shall be referenced by a licensed land surveyor and replaced, as necessary, in kind.

3.02 PREPARATION

A. Identify existing plant life that is to remain and verify with the Owner/District and Landscape Architect clearing limits are clearly tagged, identified, and marked in such a manner as to ensure their protection throughout construction operations

3.03 CLEARING

A. Construction of temporary erosion control systems and its associated payment shall be in accordance with Section 01 57 23 – Erosion Control Implementation, to protect adjacent properties and water resources from erosion and sedimentation.

B. Prevent the spread of dust and debris, and avoid the creation of a nuisance or hazard in the surrounding area.

C. Clear areas required for access to site and execution of work.

PART 4 MEASUREMENT AND PAYMENT

A. No measurement shall be made for this item.

B. CLEARING AND GRUBBING will be paid at the Contract lump sum amount for DEMOLITION AND REMOVAL, which shall include full compensation for

31 11 00 - 2 CLEARING AND GRUBBING

furnishing all labor, materials, equipment, tools, and incidentals for doing all the work of DEMOLITION AND REMOVAL

**END OF SECTION**

31 11 00 - 3 CLEARING AND GRUBBING

SECTION 31 22 00

GRADING

PART 1 GENERAL

1.01 SUMMARY

A. This section includes requirements for grading of the project including: excavating, preparing areas to be filled, placing, spreading, and compacting suitable fill materials, remedial grading, finish grading, and all other work necessary to conform with lines, grades, and slopes shown on the Drawings, as specified herein, and as needed for complete and proper excavation and grading operations.

B. The bioretention basin grading operation will commence upon completion of the rough grading and will be in accordance with Section 33 22 20, Bioretention Basins.

C. The trenching of utilities will commence upon completion of the rough grading operation and will be in accordance with Section 31 23 33, Trenching, Excavation, Backfilling, and Compacting.

D. During the excavation the soil will be evaluated for reuse by the Geotechnical Consultant as described in Section 01 74 19, Construction and Demolition Materials Management.

E. The excess suitable material shall be placed into a stockpile for future use or disposal and/or export as described in Section 01 74 19, Construction and Demolition Materials Management.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 74 19 - Construction and Demolition Materials Management

B. Section 31 11 00 - Clearing and Grubbing

C. Section 31 22 20 – Bioretention Basins

D. Section 31 23 33 - Trenching, Excavation, Backfilling and Compacting

1.03 REFERENCE STANDARDS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

B. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

C. Standard Drawings 31 22 00 - 1 GRADING

1. San Diego Regional Standard Drawings (2012).

D. American Society for Testing and Materials, referred to hereinafter as ASTM.

1.04 SUBMITALS

A. Submit representative samples of material proposed for use as compacted fill for testing and approval prior to incorporation into the work of this Section.

1.05 QUALITY ASSURANCE

A. Testing:

1. Soils testing for engineering control of the grading will be under the direction of the District's Representative. Grading shall be subject to field observation and testing.

2. District will retain the services of a Geotechnical Consultant/Testing firm. The Geotechnical Consultant will be afforded the opportunity to test representative samples of the stockpiled material and to identify the material that is approved to be used for fill, to insure compliance of the work to these Specifications. Initial tests and inspection costs will be incurred by the District. Costs of any re-testing and inspection made necessary by work not complying with the contract documents to be paid by Contractor

3. The Geotechnical Consultant and the Environmental Monitor shall be afforded the opportunity to take soil samples, monitor soil condition, and perform soil tests without interference from Contractor's forces and equipment.

4. District's Representative will advise Contractor if test results indicate unsatisfactory fill material or that the dry density of any layer of fill or portion thereof is below the specified dry density.

5. Contractor shall provide 48-hour advance notice for scheduling of soils compaction testing.

B. Certification: Upon completion of the Work, Contractor shall certify in writing that earthwork was performed in accordance with these Specifications, Soil’s Report recommendations, and as shown on Drawings.

1.06 PROTECTION

A. The contractor shall take precautionary measures to protect any existing facilities shown on the drawings, and any other which is not of record or not shown on the drawings.

31 22 00 - 2 GRADING

B. Protection and Restoration of Surface: Protect newly graded areas from traffic, erosion, and settlements. Repair and re-establish damaged or eroded slopes, elevations or grades and restore surface construction prior to acceptance. Provide erosion control to prevent water-borne soil from leaving the site using appropriate measures. The contractor shall be responsible to clean up any soil deposited in the public right-of-way or on adjacent property. The contractor shall be responsible to protect storm drain catch basins using appropriate measures and to prevent sediment from entering the storm drain system during construction.

C. Protection of Existing Improvements and Facilities: All surface and sub-surface existing improvements and facilities within the project limits which are to remain in place shall be protected from damage from Contractor operation, in accordance with the General Conditions and Contract Documents.

1. If such existing improvements and facilities within the project limits are damaged by reason of the Contractor's operation, they shall be replaced, reinstalled or reconstructed at no additional cost to the District.

1.06 SAFETY DURING CONSTRUCTION

A. The Contractor shall assume sole and complete responsibility for job site conditions during the course of construction of the project, including safety of all persons and property. This requirement shall be made to apply continuously and not be limited to normal working hours. Refer to Division 1 for additional requirements.

B. Where pedestrian and driver safety is endangered in the work of demolition and removal, and disposal of work, including protecting and restoring existing improvements, use traffic barriers with flashing lights and other approved safety devices. Notify the Engineer prior to beginning any such work.

C. Comply with all applicable federal, state, and local hauling and disposal regulations.

PART 2 PRODUCTS

2.01 FILL MATERIALS

A. In general, the soil generated during on-site excavations is suitable for reuse as fill and will be evaluated for suitability during the grading operation by the Geotechnical Consultant and the Environmental Monitor.

PART 3 EXECUTION

3.01 SITE CONDITIONS

A. General

1. Protect features, facilities, or items shown or designated on Drawings to remain.

31 22 00 - 3 GRADING

2. Protect benchmarks, property corners, and other survey monuments from damage or displacement. If a marker needs to be removed it shall be referenced by a licensed land surveyor and replaced, in kind, at no additional cost to District.

3. Prior to commencement of grading, a Geotechnical consultant (Consultant) will be employed for the purpose of observing earthwork procedures and testing the fills for substantial conformance with the recommendations of the Geotechnical Report and these specifications. The Consultant will provide adequate testing and observations services so that they may assess whether, in their opinion, the work is being performed in substantial conformance with these specifications. It shall be the responsibility of the Contractor to assist the Consultant and keep them apprised of work schedules and changes so that personnel may be scheduled accordingly.

4. Perform all excavations in accordance with the contract specifications and in conformance with Section 300-2 of the SSPWC and as prescribed in this section.

5. Perform all on site fill in accordance with the contract specifications and in conformance with Section 300-4 of the SSPWC and as prescribed in this section.

6. Comply with all applicable Federal, State, and local hauling and disposal regulations, and air pollution and environmental regulations.

7. Comply with all applicable traffic control requirements required by the District and the City of El Cajon.

8. After the major construction operations have been completed, the Contractor shall repair and clean staging and stockpile areas to match pre-construction condition.

B. Discrepancies

1. Verify existing grades and dimensions before starting grading operations. Notify the Engineer of Record if any discrepancy exists.

2. Do not proceed in areas of discrepancy until all such discrepancies have been fully resolved.

3.02 CLEARING AND REMOVAL

A. For initial site preparation, refer to Section 31 11 00 – Clearing and Grubbing and Section 02 41 00 – Demolition.

3.02 EXCAVATION

A. Make all cuts in long uniform passes using appropriate equipment.

31 22 00 - 4 GRADING

B. Edges of cut areas shall be benched so that the resulting overall slope does not exceed 2 horizontal and 1 vertical.

C. The Contractor's design and installation of vertical trenching, and/or shoring shall be consistent with the rules, orders, and regulations of CAL-OSHA and designed by a registered engineer, in the State of California.

D. Excavate existing material to plan and depth locations shown on drawings, and as described in the Soils Report. All bottoms of excavated surfaces shall be free of ruts, hummocks, and other uneven surface features.

E. All excavated surfaces shall be approved by the Geotechnical Consultant prior to proceeding with scarification and compaction, and prior to proceeding with fill placement.

F. Temporary stockpiling of the suitable soil that is cleared by the Engineer for reuse consists of the work involved to temporarily place the soil prior to reuse for the project with the location determined by the District and the Contractor.

3.04 UNSUITABLE OR EXCESS SOILS

A. Contractor shall manage geotechnically unsuitable, environmentally unsuitable, and excess soil that is suitable for reuse in accordance with the requirements of Section 01 74 19, Construction and Demolition Materials Management.

3.05 PLACING, SPREADING, AND COMPACTING FILL MATERIAL

A. Compact fill material near to slightly over optimum moisture conditions using equipment that is capable of producing a compacted product.

B. Prior to placing hardscape base materials within proposed pavement and exterior flatwork improvement areas, the upper twelve (12) inches of the subgrade soil shall be scarified, moisture conditioned as necessary, and recompacted to a dry density of at least 95% of the laboratory maximum dry density near to slightly above the optimum moisture content as determined by ASTM D 1557 and per the Soils Report.

C. Permanent slopes shall be inclined no steeper than 2:1 (horizontal to vertical). Fills over sloping ground shall be constructed in accordance with the recommendations of the Geotechnical Consultant.

D. The Contractor shall examine all areas designated to receive fill materials and shall immediately report in writing any condition that in his opinion, prevents the proper placement of the specified materials. Placement of the materials shall not be started until the contractor has received directions from the District's Representative and Geotechnical Consultant concerning any necessary corrections of the condition.

3.06 FINISH GRADING

31 22 00 - 5 GRADING

A. The finish grading operation will commence after completion of bioretention basin grading and utility trenching and backfill and will consist of completing the excavation, placement, spreading, and compacting of the existing suitable soil to the subgrade elevations for pavement and hardscape improvements and the final grade elevations of the bioretention basins, landscaped areas, and slopes as shown on the approved drawings to the tolerances as specified in these Specifications.

B. The suitable soil for reuse shall be placed, spread and compacted as specified in the Soils Report, Limited Geotechnical Invertigation – Cuyamaca College, Phase 1 Track and Field Surfacing, El Cajon, California, Dated January 29, 2016 Project No. G1930-32-01 and per any additional Geotechnical recommendations.

C. Payment for finish grading shall be included in the contract price paid for Earthworks, listed in the Bid Schedule, and no additional compensation will be allowed therefore.

3.07 OBSERVATION OF GRADING OPERATIONS

A. Geotechnical Consultant

1. The Geotechnical Consultant will be the District's representative to observe and perform tests during clearing, grubbing, filling, and compaction operations.

1. The Geotechnical Consultant will perform a sufficient distribution of field density tests of the compacted soil or soil-rock fill to provide a basis for expressing an opinion whether the fill material is compacted as specified.

3.08 PROTECTION OF WORK

A. During Grading

1. Grade the site to provide positive drainage away from structures and to prevent water from ponding adjacent to structures. Water shall not be allowed to damage adjacent properties or finished work on the site. Positive drainage shall be maintained until permanent drainage and erosion control facilities are installed in accordance with project Drawings.

2. Construct temporary ditches and siltation basins, as required, to prevent runoff of silt and debris off the site and erosion downstream of the site.

3.09 MAINTENANCE

A. After grading operations have been completed, maintain all excavated and filled areas until such time that the project is complete and accepted for maintenance by District or by whatever agency or association that will be responsible for maintenance.

31 22 00 - 6 GRADING

PART 4 MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid Item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

4.02 UNCLASSIFIED EXCAVATION & FILL ; BID ITEM:

A. UNCLASSIFIED EXCAVATION & FILL will be measured by the CY of soil to be excavated, transported, and stockpiled (for reuse or proper means of disposal), placement and compaction for reuse finish grades.

B. The contract unit price for UNCLASSIFIED EXCAVATION & FILL shall include full compensation for furnishing all labor, materials, equipment, tools, and incidentals, including but not limited to, excavating to removal depth determined by Geotechnical consultant, scarifying, excavation, transport, and stockpile for reuse or other proper means of disposal.

4.03 UNCLASSIFIED EXCAVATION & EXPORT; BID ITEM:

A. UNCLASSIFIED EXCAVATION & EXPORT will be measured by the CY of soil excavated, transported, and stockpiled for reuse or proper means of disposal, placement and compaction for reuse in meeting finish grades.

B. The contract unit price for UNCLASSIFIED EXCAVATION & EXPORT shall include full compensation for furnishing all labor, materials, equipment, tools, and incidentals, including but not limited to, excavating to removal depths determined by Geotechnical consultant, scarifying, moisture conditioning, placing, spreading, and compacting to finish grades, or disposing to an approved location as directed by the District.

4.04 MISC.. UNCLASSIFIED EXCAVATION IN EXISTING TURF AREAS; BID ITEM

4.05 PAYMENT

A. Payment shall be determined using the unit price and the quantity installed. The estimated bid quantity is for the purpose of establishing a Contract unit price for this item and the District reserves the right to adjust the actual quantity to 25% to 150% of the bid quantity at no change to the Contract unit price. Actual quantities for Payment should be diligently recorded per the Method determined by the District.

**END OF SECTION**

31 22 00 - 7 GRADING SECTION 31 22 20

BIORETENTION BASINS/SWALES

PART 1 GENERAL

1.01 SUMMARY

A. This section specifies bioretention basins and/or swales that detain runoff in a surface , filter it through plant roots and a biologically active soil and either infiltrate it into the ground (unlined bioretention basin/swale) or into the ground to an underdrain system which conveys treated runoff to the storm drain system or daylights to surface drainage (lined bioretention basin/swale).

B. Related Sections: Other Specification Sections which directly relate to the work of this Section include, but are not limited to, the following:

1. Section 02300 - Earthwork; Establishment of Subgrade 2. Section 02305 - Excavation and Backfill 3. Section 02630 - Storm Drainage 4. Section 02920 - Landscape

1.02 REFERENCE STANDARDS

A. American Society for Testing and Materials (ASTM) Latest Edition

1. D 422 Method for Particle Size Analysis

2. D 698 Test of Moisture Density Relations of Soils - Standard Proctor Method

3. ASTM D5126 / D5126M-90, Standard Guide For Comparison of Field Methods for Determining Hydraulic Conductivity in Vadose Zone.

4. D 2216 Laboratory Determination of Moisture Content of Soil

5. D 2487 Classification of Soils for Engineering Purposes

6. D 4318 Test for Plastic Limit, Liquid Limit, & Plasticity Index of Soils

7. D3034 Type PSM PolyVinyl Chloride (PVC) Sewer Pipe and Fittings

8. D3212 Joints for Drain and Sewer Plastic Pipes Using Elastomeric Seals

9. F477 Elastomeric Seals (Gaskets) for Joining Plastic Pipe

31 22 20-1 BIORETENTION BASINS

10. F794 PolyVinyl Chloride (PVC) Profile Gravity Sewer Pipe and Fittings Based on Controlled Inside Diameter

B. American Association of State Highway and Transportation Officials (AASHTO) latest edition:

1. T 88 Mechanical Analysis of Soils

2. M 43 Standard Sizes of Coarse Aggregate for Highway

1.03 QUALITY ASSURANCE

A. A geotechnical engineer familiar with the requirements of the geotechnical engineering study, selected and paid for by the District, shall be retained to perform construction inspection on site based on density testing, visual observation and judgment. This inspection will not relieve the Contractor from his responsibility to complete the Work in accordance with the drawings and specifications.

B. Visual field confirmation and density testing of subgrade preparation and fill placement procedures shall be performed by the field geotechnical engineer as part of the construction testing requirements. The Contractor shall be informed as soon as possible of the test results.

C. The geotechnical engineer shall prepare field reports that indicate compaction test location, elevation data, testing results and acceptability. The Owner and Contractor shall be provided with written copies of the results within 24 hours from the time the test was performed.

D. The geotechnical engineer shall prepare “In situ” percolation test(s) of the bioretention soil indicating initial rate of at least 8-10 inches per hour. Long term infiltration rates shall be at least 5 inches per hour. The Owner and Contractor shall be provided with written copies of the results within 24 hours from the time the test was performed.

E. All costs related to re-inspection due to failures shall be paid for by the Contractor at no additional expense to the Owner. The Owner reserves the right to require additional inspections that are deemed reasonably necessary, any inspection that is deemed necessary. Contractor shall provide free access to site for inspection activities.

1.05 SUBMITTALS

A. Product Data: Submit manufacturer’s product data and installation instructions. Include required substrate preparation, list of materials, application rate/testing and percolation rates.

B. Certifications: Manufacturer shall submit a letter of certification that the products

31 22 20-2 BIORETENTION BASINS

meet or exceed all physical property, endurance, performance and packaging requirements.

C. Submittals for Bioretention Soil: Tests must be conducted within 120 days prior to the delivery date of the bioretention soil to the project site.

D. Batch-specific test results and certification will be required for projects installing more than 100 cubic yards of bioretention soil.

E. The contractor must submit the following for approval:

1. A sample of mixed bioretention soil.

2. Grain size analysis results of the sand component performed in accordance with ASTM D 422, Standard Test Method for Particle Size Analysis of Soils.

3. Grain size analysis results of the sandy loam component performed in accordance with ASTM D 422, Standard Test Method for Particle Size Analysis of Soils.

4. Grain size analysis results of compost component performed in accordance with ASTM D 422, Standard Test Method for Particle Size Analysis of Soils.

5. Agricultural soil analysis of results for the Bioretention Soil as specified in Section 2.03 E.

6. Provide the following information about the testing laboratory(ies), including the name(S) of said laboratory(ies), as well as the following information: a. Contact person(s)

b. Address(es)

c. Phone contact(s)

d. Email address(es)

1.06 SITE OBSERVATION VISITS:

A. Site observation visits herein specified shall be made by the Civil Engineer or/and Landscape Architect. The Contractor shall request site observation a minimum of 24 hours in advance.

B. Site observation will be required for the following parts of the work:

1. Upon finish grading of subgrade of bioretention basin.

31 22 20-3 BIORETENTION BASINS

2. Upon completion of installation of the liner.

3. Upon completion of gravel storage layer, and subdrain system.

4. Upon completion of the placement of bioretention soil.

5. When planting, and all other indicated or specified work except the Maintenance Period has been completed, acceptance and written approval shall establish beginning of the Maintenance Period.

6. Final site observation visit at the completion of the Maintenance Period. This site observation visit shall establish the beginning date for the warranty period of plant material.

C. Acceptance: Upon completion of the final site observation visit and the work of this section, the Contractor will be notified in writing (1) whether the work is acceptable; OR (2) of any requirements necessary for completion and acceptance.

D. The Contractor or his authorized representative shall be on-site at the time of each site observation visit by the Civil Engineer or/and Landscape Architect.

PART 2 PRODUCTS

2.01 UNDERDRAINAGE SYSTEM

A. Rigid non-perforated Polyvinyl chloride (PVC) gravity pipe and fittings shall be SDR-35 pipe in accordance with ASTM D-3034. Size of pipe and fittings shall be a minimum of four (4) inches unless otherwise shown on the plans.

B. Perforated Polyvinyl Chloride Pipe (PVC) shall be SDR-35 pipe in accordance with ASTM D-3034. The pipe shall be furnished factory-perforated consisting of two longitudinal rows with a diameter of ¼ or ½ inch perforations, separated by 120 degrees with the flowline of the subdrain centered between the perforations. No perforation shall be performed on-site by the Contractor. Size of pipe and fittings shall be a minimum of four (4) inches unless otherwise shown on the plans.

C. Cleanout standpipe shall be rigid non-perforated Polyvinyl chloride (PVC) gravity pipe and fittings as specified above in section 2.01 A. Cleanout cap shall be PVC Schedule 40, ASTM D-1784, and Class 12454.

2.02 FILTER MATERIALS

A. Gravel stone shall be “Class 2 Permeable Material” per Caltrans specifications 68- 2.02F(3).

B. Pea gravel (if applicable) shall be clean and graded, washed river-run gravel meeting ASTM C33, Size 7 (3/4 inch).

31 22 20-4 BIORETENTION BASINS

C. Filter fabric (if applicable) shall be geotextile filter fabric which meets AASHTO M288-96 for specifications for Stabilization and Separation – Class 3, Mirafi 140N or approved equal.

2.03 LINERS

A. Liner shall be flexible 30 MIL VLDPE (Very Low Density Polyethylene) material or approved equal, as specified by the geotechnical engineer.

B. The materials will be delivered to the job site on a pallet or as a roll with protective Geotextile around the product to help protect the liner during transport. The Contractor shall visually inspect the liner as much as possible and contractor shall not accept obviously damaged materials.

C. When unloading at the job site, the pallet or rolled goods should be handled in a manner that does not cause damage to the liner.

D. For unloading and job site handling, a front-end loader with forks or a forklift capable of operating under job site conditions is recommended.

E. The liner should be stored in a dry area. When possible, the liner should be stored and covered to protect IT from unnecessary UV rays. The cover should be securely fastened to provide coverage and protection for both the top and the sides of the liner.

2.04 BIORETENTION SOIL

A. Bioretention soil shall achieve an initial infiltration rate of at least 8 inches per hour, and not more than 20 inches per hour in situ and a long-term, in-place infiltration rate of at least 5 inches per hour. Bioretention soil shall also support vigorous plant growth. Bioretention Soil shall be a mixture of fine sand and compost, measured on a volume basis:

65% Sand 20% Sandy Loam 15% Compost

Sand shall be free of wood, waste, coating such as clay, stone dust, carbonate, etc., or any other deleterious material. All aggregate passing the No. 200 sieve size shall be non-plastic.

Sand for bioretention Soil shall be analyzed by using #200, #100, #40, #30, #16. #8, #4, and 3/8 inch sieves (ASTM D 422 or as approved by municipality), and meet the following gradation:

Sieve Size Percent Passing (by weight)

3/8 inch 100

31 22 20-5 BIORETENTION BASINS

No. 4 90-100 No. 8 70-100 No. 16 40-95 No. 30 15-70 No. 40 5-55 No. 100 0-15 No. 200 0-5

Note: all sand(s) shall consist of natural sand, manufactured sand, or a combination thereof.

B. Sandy loam for bioretention Soil shall be free of wood, waste, coating such as stone dust, carbonate, etc., or any other deleterious material. All aggregate passing the No. 200 sieve size shall be non-plastic.

Sandy loam soil should comply with the following specifications on USDA soil textural classification scheme by weight:

50-74% sand 11-48% silt 2-15% clay

Note: all sandy loam shall consist of natural sand, manufactured sand, or a combination thereof.

C. Compost for bioretention Soil shall be a well decomposed, stable, weed free organic matter source derived from waste materials including yard debris, wood wastes or other organic materials. Compost shall have a dark brown color and a soil like odor. Compost exhibiting a sour or putrid smell, containing recognizable grass or leaves, or is hot (120F) upon delivery or rewetting is not acceptable. Compost shall be produced at a facility inspected and regulated by the Local Enforcement Agency for CalRecycle. The past 3 inspection reports shall be submitted verifying compliance with Title 14 requirements of the Process to Further Reduce Pathogens (PFRP), Fecal coliform and Salmonella testing and pathogen and EPA 40 CFR 503 regulations.

Compost Quality Analysis:

Property Method Requirement pH, Units Saturation Paste 6 to 8.5 EC, dS/m Saturation Extract 0 to 10 Boron, ppm Saturation Extract less than 2.5 Moisture content, % Gravimetric 30 to 60 Bulk Density, lbs/cubic yard 500 to 1100

31 22 20-6 BIORETENTION BASINS

Organic Matter, % of Dry Weight Loss on Ignition 35% to 75% Carbon to Nitrogen Ratio 15:1 to 25:1 Maturity Solvita 5 or above Stability Solvita 5 or above Particle Size Sieve Analysis Pass 1/2 inch sieve ≥80% Pass #200 sieve max 5% 503C Metals Title 14 Arsenic (As) 20 Cadmium (Cd) 15 Chromium (Cr) 100 Copper (Cu) 150 Lead (Pb) 300 Mercury (Hg) 10 Nickel (Ni) 100 Selenium (Se) 30 Zinc (Zn) 300 Pathogen Title 14 Salmonella < 3 MPN per 4 gms Fecal Coliform <1000 MPN per 1 gm Physical contaminants Plastic Metal and Glass, %> 4mm % by Weight < 1 Sharps, % > 4mm % by Weight 0

D. Bioretention Soil shall be free of roots, clods and/or stones larger than 1-inch in the greatest dimension, pockets of coarse sand, noxious weeds, sticks, lumber, brush and other litter. It shall not be infested with nematodes, or undesirable disease-causing organisms such as insects and plant pathogens. Bioretention soil mix shall be friable and have sufficient structure in order to give good tilth and aeration to the soil.

Gradation limits – The definition of the soil should be the following USDA classification scheme by weight:

31 22 20-7 BIORETENTION BASINS

Sand 85-92% Silt 14% maximum Clay 5% maximum

Permeability Rate - Hydraulic conductivity rate shall be not less the 8 inches per hour and not more than 20 inches per hour when tested in accordance with USDA Handbook Number 60, method 34b or other approved methods.

Analysis for pH, salinity and nutrient levels shall be submitted for approval prior to acceptance. Nutrient tests should include the testing laboratory recommendations for supplemental additions to the soil as calculated by the amount of material to be added per volume of soil for the type of plants to be grown in the soil.

Property Method Requirement pH, Units Saturation Paste 6.0 to 8.0 EC, dS/m Saturation Extract 0.5 to 2.5 Boron, ppm Saturation Extract less than 2.5 Chloride, ppm Saturation Extract less than 150 Sodium Adsorption Ratio less than 3.0 Carbon to Nitrogen Ratio 10 to 20 Organic Matter, % of Dry Weight Loss on Ignition 1.5 to 5 Ammonium Extractable Nutrients, Bicarbonate/DPTA dry weight basis Extraction phosphorus, ppm 10 to 40 potassium, ppm 100 to 200 iron, ppm 24 to 35 manganese, ppm 0.6 to 6 zinc, ppm 1 to 8 copper, ppm 0.3 to 5 magnesium, ppm 50 to 150 sodium, ppm 0 to 100 sulfur, ppm 25 to 500 molybdenum, ppm 0.1 to 2 aluminum, ppm less than 3.0

Bioretention Soil shall be analyzed by using #200, 1/4 inch, 1/2 inch, and 1 inch sieves (ASTM D 422 or as approved by municipality), and meet the following gradation:

Sieve Size Percent Passing (by weight)

1 inch 99-100 1/2 inch 90-100 1/4 inch 40-90 No. 200 Less than 5%

31 22 20-8 BIORETENTION BASINS

PART 3 EXECUTION

3.01 GENERAL

A. Prior to bidding of all Work within this Section, the Contractor shall become thoroughly familiar with the geotechnical engineering report and recommendations as well as the site, site conditions, and all portions of the Work falling within this Section.

B. The Contractor shall refer to the erosion control drawings for staging of earthwork operations and for erosion control measures to be implemented prior to commencement of earthwork.

C. Locate and identify existing utilities that are to remain and protect them from damage.

D. Notify utility companies to allow removal and/or relocation of any utilities that are in conflict with the proposed improvements.

E. Protect fences, structures, sidewalks, paving, curbs, etc., to remain from equipment and vehicular traffic.

F. Protect benchmarks, property corners and all other survey monuments from damage or displacement. If a marker needs to be removed/relocated it shall be referenced by a licensed land surveyor and replaced, as necessary, by the same at no additional cost to the Owner.

G. Remove from the site material encountered in grading operations that, in opinion of Owner or geotechnical engineer, is unsuitable or undesirable for backfilling.

H. Identify required lines, levels, contours and datum to bring site grades to the proposed subgrade conditions inferred from the drawings.

I. Do not perform any Work associated with this Section prior to completion of all required inspections, tests and approvals.

J. When performing grading operations during periods of prolonged wet or dry weather, provide adequate measures for surface drainage and ground water control, and moisture control of soils (e.g., wetting or drying, scarifying) so as to place and compact the soil within the moisture content range dictated in the project’s geotechnical report. Any disturbed areas should be proof-rolled at the end of each day.

K. Sloping, shoring, bracing and fencing shall be installed in accordance with Federal OSHA requirements as well as the requirements of all regulatory authorities having

31 22 20-9 BIORETENTION BASINS

jurisdiction.

L. Allow no debris to accumulate on-site. Haul debris away from the site and dispose of at no cost to the Owner.

M. Dispose of excess earth material from the site.

3.02 EXCAVATION AND SUBGRADE OF BIORETENTION BASIN/SWALE

A. Bioretention basin/swales shall be excavated/graded to the subgrades indicated on the grading plans and obtain at least the density required in the geotechnical engineering report.

B. Trench excavation for subdrain width requirements shall be as indicated and detailed on the plans.

C. Lined bioretention basin/swale subgrade shall be compacted to provide a smooth, firm, and unyielding foundation. All subgrade surfaces shall be free from angular rock, or other sharp objects. Surface deformations shall not exceed one (1) inch. Standing water and mud shall be removed prior to liner placement.

D. Unlined bioretention basins/swale subgrade shall be scarified to a six (6) inch depth prior to the installation of bioretention soil. It is very important to minimize compaction of the subgrade for unlined bioretention basins/swales, especially for applications without subdrains, as the intended purpose is to allow infiltration into the underlying native soil.

3.03 LINER

A. Liner shall be installed per manufacturer’s recommendations.

B. During the unfolding of the liner it should be visually inspected. Damage or suspect areas should be noted and manufacturer should be notified immediately. Liners that have been damaged in transit or in the manufacturing process will be repaired or replaced as quickly as possible at no cost to Owner.

C. The liner is folded in an accordion style. The contractor shall place the liner at one end of the basin and the liner shall then be pulled out lengthwise and crosswise across the perimeter of the basin area. The contractor shall pull the liner out over the basin area, secure areas of the basin with sandbags, etc., to help keep the liner down. Leave the liner loose fitting in the installation; do not pull it tight.

D. All seams shall be heat-welded or, as directed by the manufacturer, and water tight.

E. No penetration of the liner is allowed, such as for irrigation piping planting or for any other reason, unless otherwise detailed on plans. All liner penetrations should be sealed in accordance with the manufacturer’s recommendations.

31 22 20-10 BIORETENTION BASINS

3.04 UNDERDRAINAGE SYSTEM A. GENERAL

1. The Contractor shall install all drainage structures and pipe in the locations shown on the drawings and/or as approved by the Owner. Pipe shall be of the type and sizes specified on the drawings and shall be laid accurately to line and grade. Structures shall be accurately located and properly oriented.

2. Excavation and Backfill – The provisions in Section 31 23 33 - Trench Excavation and Backfill shall govern all work under this Section.

3. Storage and Handling of Pipe – All pipe shall be protected against impact, shock and free fall, and only equipment of sufficient capacity and proper design shall be used in the handling of the pipe. Storage of pipe on the job shall be in accordance with the pipe manufacturer’s recommendations.

4. Pipe which is defective from any cause, including damage caused by handling, and determined by the Owner’s representative as un-repairable, shall be unacceptable for installation and shall be replaced at no cost to the Owner and as directed by the Owner/Owner’s representative.

5. Pipe that is damaged or disturbed through any cause prior to acceptance of the work, shall be repaired realigned or replaced as directed by the Owner’s representative, at the Contractor’s expense.

B. PIPE INSTALLATIONS

1. Unloading and Handling: All pipes shall be unloaded and handled with reasonable care. Pipes shall not be rolled or dragged over gravel or rock during handling. The Contractor shall take necessary precautions to ensure the method used in lifting or placing the pipe does not induce stress fatigue in the pipe, and that the lifting device utilized uniformly distributes the weight of the pipe along its axis or circumference.

2. Each length of pipe shall be inspected for defects and cracks before being carefully lowered into the trench. Any damaged pipe, or any pipe that has had its grade disturbed after lying, shall be removed and replaced.

3. Lay pipe on prepared foundation starting at the downgrade end according to line and grade with the necessary drainage structures, fittings, bends and appurtenances as shown on the drawings. Rigid pipes shall be laid with the bell or groove ends upgrade with the spigot or tongue fully inserted.

4. Pipe sections shall be firmly joined together with appropriate gaskets, bands, or joint compound per manufacturer’s recommendations with joints made

31 22 20-11 BIORETENTION BASINS

watertight.

5. Perforations shall be placed closest to the invert of the pipe (bottom) to achieve maximum potential for draining the facility. No perforations are to be within 5’ of where the underdrain system connects to a storm drain structure.

C. CLEANOUT AND OVERFLOW INSTALLATIONS

1. Cleanouts and Overflow standpipe must consist of a rigid non-perforated PVC pipe, minimum of four (4) inches in diameter, unless otherwise indicated on plans. Connection to perforated PVC subdrain shall be with a WYE type fitting.

2. Cleanouts should be located at the upstream end of the underdrain (at a minimum, with others located along the system where specified on the plan), and be capped flush with the finish grade elevation of the basins as indicated on the plans. The top of the well shall be capped with a screw or flange-type cover to discourage vandalism and tampering.

3. Overflows shall be located along the system where specified on the plan and be located four (4) inches above the finish grade elevation of the basin, unless otherwise indicated on the plans.

D. GRAVEL PLACEMENT

1. Install four (4) inches, unless otherwise indicated on the plans, of gravel stone in trench prior to placement of subdrain.

2. Placement of the gravel over the underdrain must be done with care. Avoid dropping the gravel at high levels from a backhoe or front-end loader bucket. Spill directly over underdrain and spread manually.

3.05 BIORETENTION SOIL PLACEMENT

A. Imported backfill material for the bioretention zones should be placed in a relatively loose condition, no rolling or other heavy equipment, to promote the planned infiltration of water through the bioretention soil mix layer.

B. Bioretention soil shall be installed in six (6) to twelve (12) inch lifts and lightly watered to provide settlement and natural compaction. No mechanical compaction is allowed. After natural compaction has been completed, add, if needed, additional bioretention soil to proposed finish grade as indicated on the plans.

C. Rake bioretention soil as needed to level it out.

D. Vehicular traffic or construction equipment shall not drive-on, move onto, or disturb

31 22 20-12 BIORETENTION BASINS

the bioretention soil once placed and water compacted.

E. The geotechnical engineer shall perform one percolation test per Bioretention basin/swale in accordance with the County of San Diego Department of Environment Health Percolation Testing Criteria or other approved methods “in situ” prior to planting the Bioretention area (the engineer of work may require more than one “in situ” test depending on the size of the bioretention area). In situ percolation test(s) shall have an initial rate of at least 8-10 inches per hour to maintain a long term infiltration rate of at least 5 inches per hour. If percolation does not meet this rate, the contractor shall provide and submit corrective action to the geotechnical engineer for approval, such as rototilling or hand-cultivating to improve the percolation rate. Once the approved corrections are determined, the contractor will perform the required corrective action to improve the percolation rate and re-test at his expense.

F. Erosion and Sediment Control practices during construction shall be employed to protect the long-term functionality of the bioretention basin/swale. The following practices shall be followed for this reason:

1. Provide erosion control in the contributing drainage areas to the facility and stabilize upslope areas.

2. Facilities should not be used as sediment control facilities, unless installation of all bioretention-related materials are withheld toward the end of construction allowing the temporary use of the location as a sediment control facility, and appropriate excavation of sediment is provided prior to installation of bioretention materials.

3.06 BIORETENTION BASIN/SWALE MAINTENANCE PERIOD

A. The Maintenance Period begins on the first day after all landscape and irrigation work and all other indicated or specified work for the bioretention basin/swale is complete, checked, accepted and written approval from the Landscape Architect and Civil Engineer is given to begin the Maintenance Period.

B. The Contractor shall continuously maintain as indicated below all involved areas of the Contract during the progress of the work and during the Maintenance Period until the Final Acceptance of the work.

Typical Maintenance Indicator(s) Maintenance Actions Accumulation of sediment, Remove and properly dispose of accumulated materials, litter, or debris without damage to the vegetation. Poor vegetation establishment Re-seed, re-establish vegetation. Overgrown vegetation Mow or trim as appropriate, but not less than the design height of the vegetation (typically 4 to 6 inches for grass).

31 22 20-13 BIORETENTION BASINS

Erosion due to concentrated Repair/re-seed eroded areas and adjust the irrigation irrigation flow system. Erosion due to concentrated Repair/re-seed eroded areas and make appropriate stormwater runoff flow corrective measures such as adding erosion control blankets, adding stone at flow entry points, or re-grading where necessary (consult with the engineer of work). Standing water in swales or Make appropriate corrective measures such as adjusting strips irrigation system, removing obstructions of debris or invasive vegetation, or re-grading for proper drainage (consult with the engineer of work). Standing water in bioretention Make appropriate corrective measures such as adjusting areas or planter boxes for longer irrigation system, removing obstructions of debris or than 72 hours following a storm invasive vegetation, clearing underdrains (where event* applicable), tilling or aerating or repairing/replacing compacted bioretention soils. * Bioretention areas typically include a surface ponding layer as part of their function which may take 72 hours to drain. Obstructed inlet or outlet Clear obstructions. structure Damage to structural Repair or replace as applicable. components such as weirs, inlet or outlet structures

C. The maintenance period shall continue until final acceptance, but under no circumstances less than 1 year after substantial completion (unless otherwise stipulated in the contract documents).

**END OF SECTION**

31 22 20-14 BIORETENTION BASINS

SECTION 31 23 19

DEWATERING

PART 1 GENERAL

1.01 SUMMARY

A. Based on previous pavement and soils testing by GEOCON Inc. encountering ground water is not expected.

B. During construction, should the contractor encounter groundwater, the Contractor shall minimize dewatering in order to reduce the potential for lateral migration ground water during construction excavations, and grading. Such activities shall be performed in accordance, and evaluated by Geotechnical Consultant.

C. The work for Dewatering Operations includes but is not limited to, preparing a Dewatering Plan; preliminary testing, installation, operation, reporting, maintenance, and removal of the temporary dewatering operation system, and obtaining the applicable Local, State and Federal disposal regulation and discharge permits and payment of all permit fees related to the dewatering operations.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 31 22 00 – Grading

B. Section 31 23 33 – Trenching, Excavation, Backfilling and Compacting

1.03 DEWATERING PLAN

A. The Contractor shall submit the Dewatering Plan to the Engineer for review and acceptance 5 days prior to dewatering activities. The acceptance of the Dewatering Plan by the Geotechnical Engineer shall not relieve Contractor responsibility of the designed dewatering system performing for its intended purposes and complying with all applicable laws and regulations, and shall not relieve the Contractor of responsibility for the safety of all persons and protection of property on the job site or that may be affected by work under this Contract. The Engineer will have authority to accept or reject the Dewatering Plan, all other plans comprising the Dewatering Plan, and any proposed modifications to the Dewatering Plan requested by the Contractor. Any proposed changes or modifications to the approved Dewatering Plan or any Dewatering component plan shall be submitted to the Engineer for acceptance at least 5 working days prior to incorporation into the Dewatering Plan.

1. Dewatering Team: List name; business address and phone number; and certification, and registration or license type and license number of each

31 23 19 - 1 DEWATERING

Dewatering Team member including the Contractor's Competent Person(s). Contractor and/or Subcontractors doing the work shall have a minimum of five years of experience and have completed at least three construction projects within the last seven years that are substantially similar to this work, which includes the dewatering and treatment of contaminated groundwater.

2. General Requirements: List key regulations governing dewatering and any specific training, license or certification required.

3. Preliminary Testing: List testing planned to determine maximum flow rates, dewatering system requirements, and to characterize groundwater for disposal.

4. Work Methods and Sequence: List methods planned to carry out the dewatering work, the personnel required, the certified laboratory, equipment and materials needed, and steps necessary to protect the health and safety of personnel and the public for each area to be dewatered.

5. Dewatering System Description: Provide a Dewatering System Description including a complete description of the groundwater extraction and waste discharge disposal equipment and instrumentation to be used; map showing location of discharge point and treatment staging area, schematic of proposed operation and treatment systems, design calculations demonstrating adequacy of the proposed system and equipment; and installation, operation, maintenance, and spill prevention and response procedures.

6. Records and Reporting: List actions planned to document dewatering work and monitoring activities. List specific documents to be submitted to the Engineer. The Contractor shall submit a daily report that includes the following information:

a. The average dewatering pumping flow rate.

b. Water quality testing results as required by the disposal regulations.

c. The treated groundwater discharge flow rate

7. Permits: List dewatering related permits required for Site dewatering and disposal.

PART 2 – MATERIALS

2.01 MATERIALS AND EQUIPMENT

A. Materials and equipment for dewatering may include, but is not limited to, sump pumps, temporary pipelines for water disposal, rock or gravel placement, wells,

31 23 19 - 2 DEWATERING

observation wells; storage tanks, pumps, materials, filtration systems, and other materials and equipment required for treatment; standby pumping equipment maintained on the Site continuously, and other additional materials and equipment as required for execution of the work.

B. The Contractor shall provide other instruments and measuring devices as required.

PART 3 EXECUTION

3.01 GENERAL REQUIREMENTS

A. Install a dewatering system to lower and control groundwater in order to permit excavation, installation of structure, and placement of backfill materials to be performed under dry conditions. Make the dewatering system adequate to drain the water-bearing strata above and below the bottom of structure foundations, utilities and other excavations.

B. In addition, reduce hydrostatic pressure head in water-bearing strata below structure foundations, utility lines, and other excavations, to extent that water levels in construction area are a minimum of 1 foot below prevailing excavation surface at all times.

3.03 PREPARATION

A. Contractor shall prevent surface water and groundwater from entering excavations, from ponding on prepared subgrades, and from flooding Site and surrounding area.

B. Contractor shall protect subgrades and foundation soils from softening and damage by rain or water accumulation.

C. Contractor shall install dewatering system to ensure minimum interference with roads, streets, walks, and other adjacent occupied and used facilities.

D. Cooperate fully with other contractors, soil remediation contractors, utilities and public agencies or their contractors, other District contractors, and District personnel that may be working in the vicinity during the Project construction period.

3.04 RECORDS

A. Observe and record the average flow rate and time of operation of each pump used in the dewatering system, and the discharge flow rate. Where necessary, provide appropriate devices, such as flow meters, for observing the flow rates. Submit flow- rate data during the period that the dewatering system is in operation.

B. During initial period of dewatering, make required observations on at least a daily basis. If, after a period, dewatering operations have stabilized, reduce observations to

31 23 19 - 3 DEWATERING

longer intervals as appropriate, and as approved by the Geotechnical Engineer and as approved by the District.

3.05 DEWATERING TREATMENT AND DISPOSAL

A. Water and debris shall be disposed of in a suitable manner in compliance with permit requirements without damage to adjacent property. No water shall be drained into work built or under construction. Before disposal, water shall be treated in accordance with permit requirements.

B. Dispose of water removed from the excavations in such a manner as:

1. Shall not endanger portions of work under construction or completed.

2. Shall cause no inconvenience to District or to others working near site.

3. Shall comply with the stipulations of required permits for disposal of water.

4. The Contractor shall control runoff in all work areas including but not limited to: excavations, parking areas, lay down, and staging areas. The Contractor shall provide, operate, and maintain all ditches, basins, sumps, site grading, and pumping facilities to divert, collect, and remove all water from the work areas. All water shall be removed from the immediate work areas and shall be disposed of in accordance with applicable permits.

C. The contractor shall implement a basic treatment system design that may include, but not be limited to:

1. Retention of the influent raw groundwater in holding/settling tank to provide for suspended materials settling and downstream processes.

2. Process pumping system.

3. Sand Filtration; removal of suspended matter.

4. Mechanical filtration systems, which will effectively filter out fine- dispersed matter.

5. Granulated activated carbon filtration; for removal of organic constituents.

6. Ion exchange resin filtration; for removal of inorganic constituents.

31 23 19 - 4 DEWATERING

7. Flow meter to measure treated groundwater discharge flow.

3.06 DISCONTINUING OPERATION AND REMOVAL

A. Insure compliance with all conditions of regulating permits and provide such information to the Engineer. Obtain written acceptance from the Geotechnical Engineer and the District Inspector before discontinuing operation of the dewatering system.

B. When the dewatering system is no longer required dismantle and remove the system and all appurtenances from the site.

PART 4 MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

4.02 DEWATERING

Full compensation for conforming to the requirements of this Section, DEWATERING, including all labor, materials, equipment, tools, and incidentals will be considered included in the Contract Unit Price paid for the various items listed in the Bid Schedule, (ie. Earthwork, Grading, and Utility piping) and no additional compensation will be allowed therefore.

**END OF SECTION**

31 23 19 - 5 DEWATERING

SECTION 31 23 33

TRENCHING, EXCAVATION, BACKFILLING, AND COMPACTING

PART 1 GENERAL

1.01 SUMMARY

A. The scope of work includes all labor, materials, tools, equipment and incidentals necessary to construct utility trenches including backfill materials, testing, trench excavation, backfill and compaction and shoring for utility piping and structures, and all incidental work, as necessary to complete Contract work as shown on the drawings and as specified in these Special Provisions.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 31 22 00 – Grading

B. Section 31 23 19 – Dewatering

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2012 Edition (Green Book), including the Regional Supplement.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

C. Current American Society for Testing and Materials, referred to hereinafter as ASTM.

1. ASTM D 75 - Practice for Sampling Aggregates

2. ASTM D 1556 - Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method

3. ASTM D 1557- Test Method for Moisture-Density Relations of Soils Using a Modified Effort

4. ASTM D 2419 - Test Method for Sand Equivalent Values of Soil and Fine Aggregate

31 23 33 - 1 TRENCHING, EXCAVATION, BACKFILLING AND COMPACTING 5. ASTM D 6938 - Test Method for Density of Soil in Place by Nuclear Methods (Shallow Depth)

6. ASTM D 3017 - Test Method for Water Content of Soil and Rock in Place by Nuclear Methods

7. ASTM D 3776 - Test Method for Mass Per Unit Area (Weight) of Woven Fabric

D. California Occupational Safety and Health (CAL-OSHA)

1. Title 8 General Safety Orders

1.04 SUBMITTALS

A. Submit representative samples of material proposed for use as backfill material for testing and approval prior to the start of work of this section to the Geotechnical Engineer of Record

1.05 GEOTECHNICAL TESTING

A. The Owner/District will engage the services of a geotechnical engineering firm or individual licensed in the State of California to monitor soil conditions during earthwork, trenching, bedding, backfill and compaction operations. Sampling and testing procedures shall be performed in accordance with the Reference Standards and as follows:

B. The soils technician shall be present at the site during all backfill and compaction operations. Failure to have the soils technician present will subject such operations to rejection.

C. A report of all soils tests performed will be stamped and signed by the soils firm or individual and will be submitted by the Contractor prior to the filing of the Notice of Completion by the District. The report will document the sampling and testing of materials, the location and results of all tests performed, and will certify that materials and work are in compliance with this specification.

1.06 PROTECTION OF EXISTING UTILITIES AND FACILITIES

A. The Contractor shall be responsible for the care and protection of all existing utilities, facilities and structures that may be encountered in or near the area of the work in the Contract Documents and General Conditions.

1.07 PROTECTION OF EXISTING LANDSCAPING

31 23 33 - 2 TRENCHING, EXCAVATION, BACKFILLING AND COMPACTING A. The Contractor shall be responsible for the protection of all trees, shrubs, fences, and other landscape items adjacent to or within the work area in accordance with Section Contract Documents and General Conditions.

1.08 CHANGES IN LINE AND GRADE

A. In the event obstructions not shown on the plans are encountered during the progress of the work, and which will require alterations to the plans, the Contractor shall notify the Owner/District and Engineer. The Contractor shall not deviate from the specified line and grade without prior written approval by the Owner/District and/or Engineer.

PART 2 MATERIALS

2.01 GENERAL

A. The Contractor shall furnish bedding and backfill material as specified by the San Diego Regional Standard Drawings, and Standard Specifications for Public Works Construction (SSPWC), 2012 Edition (Green Book), including the Regional Supplement.

B. The Contractor shall request inspection from Geotechnical Engineer of Records of stockpiled materials, and receive confirmation that materials are adequate prior to reuse in trench bedding and backfill applications,

PART 3 EXECUTION

3.01 GENERAL

A. The Contractor shall trench, and install bedding, and backfill material, and mechanically compact backfill as specified by the San Diego Regional Standard Drawings, and Standard Specifications for Public Works Construction (SSPWC), 2012 Edition (Green Book), including the Regional Supplement.

B. The trench bottom shall be graded to provide a smooth, firm, and stable foundation that is free from rocks and other obstructions

3.02 DEWATERING

A. Though groundwater is not anticipated per the current soils report, dewatering of the soil shall be executed per 31 23 19, and included in the bid item for each applicable bid item.

3.03 COMPACTION REQUIREMENTS

A. Compaction shall be accomplished by mechanical means, in compliance with the soils report, and to the satisfaction of the Geotechnical Engineer.

31 23 33 - 3 TRENCHING, EXCAVATION, BACKFILLING AND COMPACTING

B. If the backfill fails to meet the specified relative compaction requirements; the backfill shall be reworked until the requirements are met. All necessary excavations for density tests shall be made as directed by the Geotechnical Engineer, and as acceptable to the District. The requirements of the Agency having jurisdiction shall prevail on all public roads.

C. All backfilled excavations are subject to compaction tests.

PART 4 MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid Item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

31 23 33 - 4 TRENCHING, EXCAVATION, BACKFILLING AND COMPACTING SECTION 32 01 13

SLURRY SEAL

PART 1 GENERAL

1.01 SUMMARY OF WORK

A. The scope of work includes all labor and equipment necessary to seal existing Asphalt Concrete (AC) pavement and shall include mixing asphaltic emulsion, crack sealing aggregate, set-control additives and water and spreading the mixture on a surfacing or pavement where shown on the plans, as necessary to complete contract work as specified in these technical specifications.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 33 00 – Submittal Procedure

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

2. State of California, Department of Transportation, Standard Specifications, July, 2010.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

C. American Society for Testing and Materials, referred to hereinafter as ASTM

1.04 SUBMITTALS

A. Contractor shall submit Slurry Seal Type II mix design for approval

PART 2 PRODUCTS

2.01 GENERAL

A. Slurry Seal shall be Type II as per Caltrans Standard Specifications Section 37-2.

32 01 13 - 1 SLURRY SEAL B. Products to be used under this Section shall conform to CALTRANS ‘Section 37: Bituminous Seals’, and shall conform to the provisions in latest federal, state, and local codes and regulations.

C. Crack sealant material shall conform to ASTM D6690.

PART 3 EXECUTION

3.01 GENERAL

A. All work of placing the slurry mixture shall conform to CALTRANS Section 37-2.03 and this section.

B. Within the areas to receive Slurry Seal, existing pavement markers shall be removed and existing pavement striping and pavement markings shall be removed by sandblasting prior to Slurry Seal application.

C. Contractor shall remove all loose materials, clean and seal pavement cracks with hot poured joint sealant material conforming to ASTM D6690 prior to slurry seal operation.

D. Contractor shall cover and protect all surface utility boxes, manholes, catch basins, gate valves, and any other surface appurtenances prior to applying slurry seal. Contractor shall cover existing surface appurtenances with secured, protective plastic sheeting that is fitted to align with the edges of the surface appurtenance being protected.

E. Contractor shall replace all existing pavement markers with new pavement markers, as shown on the plans.

3.02 SEALING/FILLING PAVEMENT CRACKS

A. Prior to sealing or filling pavement cracks, Contractor shall grout cracks such that of appropriate shape and dimension are produced. Immediately prior to pouring sealant or asphalt mix materials in these cracks, all cracks shall be cleaned by compressed air to remove all residue and foreign materials. Crack surfaces shall be dry at the time the sealant or fine grades asphalt mix material is poured. All cracks shall then be sealed with sealant material in accordance with the manufacturer’s written instructions. The Contractor shall assure that all cracks are fully filled with sealant material that will produce a complete bond between the sealant material and the crack faces. Cured sealant shall be flush with pavement surface; excess sealant material shall be striked off. There shall be no separation or opening between the sealant material and the crack faces.

B. All work of sealing cracks shall be completed prior to beginning slurry seal operation.

32 01 13 - 2 SLURRY SEAL PART 4 MEASUREMENT AND PAYMENT

4.01 SLURRY SEAL, BID ITEM:

A. SLURRY SEAL will be measured by the square foot of application area as shown on the plans and as determined by the Engineer from field verification.

B. The Contract unit price for SLURRY SEAL shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals for doing all the work of SLURRY SEAL to complete in place, including but not limited to, testing for and furnishing the mixed design, cleaning the surface, removing and replacing pavement markers, asphalt crack sealing, furnishing added water and set-control additives, mixing water with asphaltic emulsion for coating the pavement, and protecting the seal until it has set, as shown on the Drawings and as specified in these Technical Specifications.

C. Payment shall be determined using the unit price and the quantity installed. The estimated bid quantity is for the purpose of establishing a Contract unit price for this item and the District reserves the right to adjust the actual quantity to 75% to 150% of the bid quantity at no change to the Contract unit price.

**END OF SECTION**

32 01 13 - 3 SLURRY SEAL SECTION 32 01 16

COLD MILLING ASPHALT PAVEMENT

PART 1 GENERAL

1.01 SUMMARY OF WORK

A. The scope of work includes the cold milling and removal of asphalt paving, and providing a variable (3-inch” maximum) asphalt concrete overlay with slurry seal as necessary for existing pavement located as shown on the drawings and as specified in these technical specifications.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 33 00 – Submittal Procedure

B. Section 32 01 13 – Slurry Seal

C. Section 32 12 16 – Asphalt Concrete Paving

D. Section 32 01 13 - Slurry Seal

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

2. State of California, Department of Transportation, Standard Specifications, July, 2010.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

PART 2 PRODUCTS (NOT USED)

See Section 32 12 16 for Asphalt Paving

PART 3 EXECUTION

3.01 GENERAL

32 01 16 - 1 COLD MILLING ASPHALT PAVEMENT A. All work of Cold Milling Asphalt Pavement shall conform to Section 302-1 ”Cold Milling Asphalt Concrete Pavement” of the SSPWC, and CALTRANS Section 42 ‘Groove and Grind Pavement’ as shown on the drawings and as specified in these specifications.

B. All work of overlay shall be placed to a depth of one to three inches (1”-3”) and shall conform to Section 302-5 “Asphalt Concrete Pavement” of the SSPWC as shown on the drawings and as specified in these specifications.

C. Contractor shall be responsible for the removal and disposal of all removed roadway material.

D. Contractor shall allow the new asphalt pavement to cure for at least 30 days before placing slurry seal.

E. Placement of slurry seal shall be in accordance with Section 31 01 13 - Slurry Seal.

PART 4 MEASUREMENT AND PAYMENT

4.01 COLD MILLING ASPHALT PAVEMENT AND OVERLAY

A. The Contract unit price for AC GRIND AND OVERLAY (VARIES) shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals for doing all the work of AC GRIND & OVERLAY, including but not limited to, testing for and furnishing the mixed design, removal and disposal of existing roadway material, replacement of asphalt concrete pavement, complete in place as shown on the Drawings and as specified in these Technical Specifications.

B. Payment shall be determined using the unit price and the quantity installed. The estimated bid quantity is for the purpose of establishing a Contract unit price for this item and the District reserves the right to adjust the actual quantity to 75% to 125% of the bid quantity at no change to the Contract unit price.

**END OF SECTION**

32 01 16 - 2 COLD MILLING ASPHALT PAVEMENT SECTION 32 12 16

ASPHALT CONCRETE PAVING

PART 1 GENERAL

1.01 SUMMARY OF WORK

A. The scope of work includes all labor, materials and equipment to provide and place asphalt concrete pavement, aggregate base, PaveGrid (or Equivalent), asphalt concrete berm, furnishing mix design, spreading, compacting where shown on the Drawings, as specified herein, and as needed for the complete and proper installation.

B. Spot Repairs/Additional Removal and Replacement: In 2” Overlay lots (3, 4 A) additional spot demolition including asphalt concrete pavement, aggregate base, furnishing mix design, spreading, compacting where shown on the Drawings, as specified herein, and as needed for the complete and proper installation shall be coordinated with the District at the time of Construction. See Bid Schedule for Allowance Quantity.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

B. Section 01 33 00 – Submittal Procedure

C. Section 32 01 16 – Cold Milling Asphalt Pavement

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

2. State of California, Department of Transportation, Standard Specifications, July, 2010.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

C. American Society for Testing and Materials, referred to hereinafter as ASTM

1.04 DEFINITIONS

32 12 16 - 1 ASPHALT CONCRETE PAVING

A. Geotechnical Consultant - the Geotechnical Engineering and Engineering Geology consulting firm retained by the District will provide technical services for the project. Observations by the Geotechnical Consultant include observations by the Soil Engineer, Geotechnical Engineer, Engineering Geologist and those performed by persons employed by and responsible to the Geotechnical Consultant.

B. Finish Grade - the ground surface configuration at which time the surface elevations conform to the approved Drawings.

1.05 SUBMITTALS

A. Materials List: Submit complete list of all proposed materials. Identify material source, quality, and characteristics.

B. Mix Designs: Accompanying the materials list, submit proposed asphalt concrete mix designs, including aggregate gradation, asphalt content, and asphalt type for the various types of work specified to the District for review and approval.

1.06 PRODUCT HANDLING

A. Protection

1. Deliver, store and handle all products in a manner to prevent damage and deterioration. Refer also to Section 01 74 19 Construction Demolition Materials Management.

2. Use all means necessary to protect the installed work and materials of all other trades.

B. Replacements: In the event of damage, immediately make all repairs and replacements necessary to the approval of the Architect and at no additional cost to the Owner.

C. PaveGrid (or Equivalent) shall be stored, and installed per Geotechnical, and Manufacturer recommendations.

PART 2 MATERIALS

2.01 ASPHALT CONCRETE

A. Asphalt and Asphaltic Emulsion: Conforming to the requirements of Subsections 203-1, "Paving Asphalt," and 203-3, "Emulsified Asphalt," of the SSPWC. Emulsified asphalt shall be type SS-1h.

B. Asphalt Concrete Surfacing: Asphalt concrete surfacing shall consist of a mixture of mineral aggregate and paving grade asphalt, mixed at a central mixing plant.

32 12 16 - 2 ASPHALT CONCRETE PAVING

1. Class of asphalt concrete shall conform to section Subsection 203-6 of the SSPWC, and conform to the recommendations in the Soils report, and the Geotechnical Consultant.

2.02 AGGREGATE BASE

A. Class 2 Aggregate Base: Conforming to requirements of Section 26-1.02B of CALTRANS, and conform to the recommendations in the Soils report, and the Geotechnical Consultant.

2.03 PAVEGRID (OR EQUIVALENT)

A. Shall be a material that conforms to the physical properties in the Greenbook (2013 Supplement) Multi-Axial Geogrid Table Section 213-5.2 (E) Type R3, and complies with Geotechnical Recommendations.

PART 3 EXECUTION

3.01 VERIFICATION OF CONDITIONS

A. Inspection

1. Prior to performing the work of this Section, carefully inspect the installed work of all other trades and verify that all such work is complete to the point where work may properly commence. B. Discrepancies

1. In the event of discrepancy, immediately notify the Engineer.

2. Do not proceed in areas of discrepancy until all such discrepancies have been fully resolved.

C. Acceptance of Surface Conditions

1. Provide Engineer with written acceptance of surface conditions, certifying that all surfaces are suitable for work of this Section to proceed.

3.02 PREPARATION

A. Prepare subgrade for placement of asphalt concrete as specified in the SSPWC, and per Soils Report by Geocon Updated Pavement Study (February 2, 2015) including but not limited to the following:

1. Upper 12 inches of pavement subgrade shall be scarified immediately prior to constructing the pavement section, brought to about optimum moisture

32 12 16 - 3 ASPHALT CONCRETE PAVING content, and compacted to at least 95 percent of the maximum dry density as determined by ASTM D1557.

B. Base Course

1. Place, spread and compact aggregate base in conformance with the requirements of Subsection 26-1.03 of CALTRANS Specifications, and in accordance with Geotechnical Engineer recommendations.

2. Each layer of base course shall be tested and approved by the testing laboratory prior to the placement of successive layers.

3. Compacted base thickness shall be as indicated on Drawings, or as determined in the field by the Geotechnical Consultant.

C. PaveGrid (or Equivalent)

1. Pre-Construction Conference: Prior to installation of the stress-relieving interlayer, the contractor shall arrange a meeting at the site with the manufacturer representative and, where applicable, the Pavegrid (or Equivalent) installer. The District shall be notified at least 3 days in advance of the time of the meeting.

2. A manufacturer representative shall be present, at minimum, for the first day of installation of the Pavegrid (or equivalent) and available thereafter upon request by the engineer.

D. Asphalt Concrete Surfacing

1. Conform to the applicable portions of Section 302-5, "Asphalt Concrete Pavement," of the SSPWC.

2. No paving course shall be placed when the atmospheric temperature is below 50 degrees F.

3. The pavement surface, when completed, shall be smooth, dense, well bonded, and of uniform texture and appearance.

4. Pavement compacted thickness shall be flush with adjacent surface, and as detailed on the SDRSD.

5. All areas shall drain and be free of standing water.

6. Compacted thickness of paving shall be as indicated on Drawings, as specified or as determined in the field by the Geotechnical Consultant.

32 12 16 - 4 ASPHALT CONCRETE PAVING E. Asphalt berm shall be placed in accordance with the Standard Drawings.

PART 4 MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid Item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

4.02 (3-4)” AC PAVEMENT ON (5-11.5)” AGGREGATE BASE

A. AC PAVEMENT ON AGGREGATE BASE will be measured by the square foot of application area as shown on the plans and as determined by the Engineer from field verification.

B. The Contract unit price paid for AC PAVEMENT ON AGGREGATE BASE shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals, and for doing all the work involved in AC PAVEMENT ON AGGREGATE BASE complete in place, including but not limited to, preparing the subgrade, testing for and furnishing the mixed design, weed control, placing and compacting aggregate base, asphalt concrete paving as shown on the Drawings and as specified in these Technical Specifications.

C. Payment shall be determined using the unit price and the quantity installed. The estimated bid quantity is for the purpose of establishing a Contract unit price for this item and the District reserves the right to adjust the actual quantity to 85% to 125% of the bid quantity at no change to the Contract unit price.

4.03 2” AC OVERLAY

A. 2” AC OVERLAY will be measured by the square foot of application area as shown on the plans and as determined by the Engineer from field verification.

B. The Contract unit price paid for 2” AC OVERLAY shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals, and for doing all the work involved in 2” AC OVERLAY to complete in place, including but not limited to, preparation of existing AC furnishing the gradation design and placing and compacting as shown on the Drawings and as specified in these Technical Specifications.

C. Furnishing, and placement of the stress reliever interlayer, (Pavegrid, or Equivalent) shall be per separate bid item, and square foot unit price.

D. Payment shall be determined using the unit price and the quantity installed. The estimated bid quantity is for the purpose of establishing a Contract unit price for this

32 12 16 - 5 ASPHALT CONCRETE PAVING item and the District reserves the right to adjust the actual quantity to 85% to 125% of the bid quantity at no change to the Contract unit price.

**END OF SECTION**

32 12 16 - 6 ASPHALT CONCRETE PAVING SECTION 32 12 17 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS

PART 1 - GENERAL

1.01 SUMMARY

A. The following recommendations are offered as guideline information in order to assist the Owner/GC/Design Team in the preparation of the base for the outdoor installation of Mondo Track Surfaces. The recommendations are general in nature and may require adaptation in order to suit local climatic conditions, expected loads and soil conditions.

B. Furnish all labor, materials, equipment, facilities, transportation, and services to complete all asphalt paving, and related work as shown on the Drawings and/or specified herein

1.02 INTRODUCTION

A. The extremely strict tolerances for gradients and flatness, which are stipulated by the NCAA and/or IAAF for the synthetic surfaces, mean that the construction of an adequate base is of supreme importance. Tolerances are required to be met not only by the newly completed facility, but also over its life, which might be two or three times the expected life of the synthetic surface.

B. The finished appearance of any resilient synthetic surface will be determined in part by the base over which it is installed. Rough, uneven bases, of substandard construction, with non-recommended materials, can reduce the life and impair the appearance of the synthetic surface. Therefore, proper construction and preparation utilizing recommended materials are important for a durable, good quality flooring installation.

C. The base should be designed to meet the following criteria: 1. It should be capable of supporting and transmitting to the existing ground the loads of all vehicles, machines and materials to be used in the construction, without causing deformation of the site, or exceeding the ground-bearing capacity. 2. It should be capable of supporting and transmitting all the loads on the synthetic surface from athletes and maintenance equipment, without permanent deformation of the base. 3. It should be sufficiently flexible to provide protection to the synthetic surface from the effects of sub-soil movement and frost heave. 4. It should be sufficiently impermeable to provide total protection to the synthetic surface from ground water.

32 12 17 - 1 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS 5. It should ensure that the above criteria are maintained throughout the life of the installation.

D. The procedure adopted for the construction of a new asphalt base will normally consist in the following operations: 1. A comprehensive geotechnical investigation should be carried out to accurately determine the sub-soil conditions: it is important to ascertain the strata at depths down to approx. 8 feet (2.5m). 2. Excavation to remove vegetable matter, soil, loose or frost susceptible material down to firm, load-bearing sub-soil. 3. An adequate sub-drain system shall be provided since adequate surface and subsurface drainage is essential for a stable base. 4. Compaction of the sub-soil, graded to falls within the tolerances specified for accuracy of finished level. 5. Laying and compacting of ordinary fill to create the sub-base layer (the minimum thickness of the layer to be determined based on the Geotechnical characteristics of the sub-soil and on the expected loads), graded to falls within the tolerances specified for accuracy of finished level and thickness. 6. Laying and compacting of 4” – 8” (10 – 20 cm) thick crushed stone to create the base under layer, graded to falls within the tolerances specified for accuracy of finished level, straightness and thickness. Actual specifications for the thickness and composition of the base under layer should be approved by a registered engineer to ensure suitability to local conditions. 7. Laying and compacting of 3” or 31/2” thick hot mix asphalt pavement in two layers. 8. The bottom layer, Asphalt Binder Course, shall be a minimum of 2” (60 mm) thick, graded to falls and checked for accuracy of finished level, straightness and thickness within the tolerances specified. 9. A Tack Coat is applied just prior to placing subsequent pavement layers. 10. The top layer, Asphalt Top Coat, shall be a minimum of 1” or 1.5” as indicated on plans (40mm) thick, graded to falls and checked for accuracy of finished level, straightness and thickness within the tolerances specified.

PART 2 PRODUCTS

2.01 ORDINARY FILL (as applicable)

A. Ordinary Fill shall be natural soil, well graded and free from all organic or other weak or compressible materials and of any frozen materials. Fill shall contain no stone larger than 4’’ (10 cm) in any dimensions.

B. It shall be of such nature and character that it can be dried and compacted 32 12 17 - 2 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS in a reasonable length of time which shall not unduly interfere with the progress of construction.

C. It shall be free of all expansive materials such as highly plastic clays, of all materials subject to decay, decomposition or dissolution and of cinders or other unsuitable material.

D. It shall have a maximum dry density of not less than 115 pounds per cubic foot as determined by ASTM D1557, Method D.

2.02 BASE UNDER LAYER MATERIAL

A. The base under layer material shall be Virgin material “crushed stone” conforming to Class Two Aggregate Base as specified in the Standard Specifications. The crushed stone shall be washed stone or gravel free of organic materials. Gradation and durability shall conform to requirements of Section 02230 – Base Courses. No recycled aggregate materials allowed.

2.03 HOT MIX ASPHALT

A. Hot mix asphalt for surface courses shall consist of virgin coarse and fine aggregates and mineral filler plant-mixed with bitumen binder.

B. All hot mix asphalt shall be in accordance with applicable provisions of State or Provincial Department of Transportation “Standard Specifications for Road and Bridge Construction”, except as herein modified.

C. The hot mix asphalt shall be plant-mixed and the bituminous material for mixture shall be AC-1, 85 – 100 penetration grade or 60 – 70 penetration grade where required in warm climates. The asphaltic cement (AC-1) content shall be 4.0 % - 6.0% (by weight) of the total composite mixture.

D. Coarse aggregate (material retained on the 4.75mm sieve) shall be sound, angular crushed stone or gravel (shale is not recommended).

E. Fine aggregate (material passing the 4.75mm sieve and retained on the # 200 (0.075mm) sieve) shall be sand, stone sand and stone screening Class B quality or better and gradation FA - 3.

F. Mineral filler (Material passing the # 200 (0.075mm) sieve) shall be dry limestone or dust.

G. The aggregate shall have the following maximum limits of detrimental substances:

32 12 17 - 3 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS  Soft fragments, AASHO T189: 2.00%  Coal and lignite, AASHO T113: 0.25%  Clay lumps, GHD 1: 0.25%  Flat or elongated pieces (length greater than five times average thickness): 10.00%  Sulfur content computed as sulfide sulfur, ASTM E30: 0.01%  Other local detrimental Substances: 2.00%

H. The gradation of the composite aggregate for the Asphalt Binder Course shall conform to or near the following: Sieve Total % Passing 3/4” 100 1/2’’ 90 - 100 3/8” 80 # 4 45 - 70 # 8 25 - 55 # 30 (19) # 50 5 - 20 (12) # 100 5 - 16 (6.5) # 200 2 - 9 (3)

Note: The aggregate grain should be as close as possible to the figures in brackets to give maximum density to the asphalt mixture.

I. The gradation of the composite aggregate for the Asphalt Top Coat shall conform to or near the following: Sieve Total % Passing 1/2’’ 100 3/8” 90 - 100 (100) # 4 60 - 90 (70) # 8 35 - 65 (49) # 30 (22) # 50 6 - 25 (14) # 100 (8) # 200 2 - 10 (3)

Note: The aggregate grain should be as close as possible to the figures in brackets to give maximum density to the asphalt mixture. A majority of the minus 200 material should consist of mineral filler. The increase in the amount of mineral filler has, in many instances, increased the toughness of the asphalt. This can be accomplished by using a resultant mineral aggregate having a minus 200 content of about 7% - 8%.

32 12 17 - 4 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS J. The asphalt “Binder Course” and “Top Coat” mixtures are the type IV mixes recommended by the Asphalt Institute. Asphaltic concrete mixtures may differ from the above provided specifications, meet or exceed the present specifications. Mondo must be informed about proposed changes/deviations to the present specifications. Determination of the job mix formula shall be based on attaining a mix having a Marshall Stability (ASTM D1559, 75 blows each Side) of 750 lbs. or greater.

K. Samples of the job mix from the asphalt plant shall be laboratory tested for Marshall Stability. A compacted specimen shall be retained for density (ASTM D2726) comparison with core samples from the installed pavement.

2.04 PRIME COATS AND TACK COATS

A. The primer for application on crushed stone base under layers (prime coat) shall be waived based on previously accepted District projects. Contractor shall confirm the lack of prime coat requirement in writing to architect prior to paving.

B. Tack Coat: Asphaltic emulsion to be penetration type conforming to the SS-1 requirements of Section 94 of the Standard Specifications.

PART 3 EXECUTION

3.01 SUB-GRADE

A. The excavation levels should be determined to allow paving, pits, etc. to rest on firm, load bearing, undisturbed sub-soil, also capable of properly supporting the paving equipment and haul trucks.

B. The sub-soil shall be excavated and compacted to a surface parallel to the theoretical finished surface of the pavement and at a depth below it equal to the compacted thickness of the subsequent layers.

C. The excavation shall proceed in such a manner that disturbance of soils below the excavation level by equipment is avoided.

D. Surface shape of the sub-grade shall be such that water can not accumulate at any point. If this is not possible, it is important to provide all necessary equipment, including automatically operated pumps and piping to run-off facilities, to maintain the excavations, pits, depressions free from accumulated water during the entire period of construction.

E. Excavation may encounter soft, non-bearing soils below the excavation 32 12 17 - 5 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS level over some of the area. When the nature at the soil is such that appropriate load bearing cannot be achieved at the excavation levels originally designed, additional excavation to good bearing is necessary. The non-bearing material will be replaced with suitable ordinary fill as will permit rough grades to be as specified.

F. When encountered in the work and indicated on the drawings, all existing active sewer, water, gas, electric, steam, irrigation and other utility services and structures shall be protected at all times and, if required for the proper execution of the work, shall be relocated.

G. The sub-soil shall be rolled and compacted by a roller to a minimum density at ninety-five percent (95 %) as determined by the Modified Proctor Test (AASHO T99).

H. Should a section of the work be not acceptable on the basis of inadequate compaction, further compaction effort shall be applied until the specified standard is achieved.

I. If the moisture content varies outside the specified limits, add water or allow drying as necessary; before commencing rolling mix mechanically for a minimum depth of mm 300 to ensure uniform distribution of moisture.

J. Surface shape of the sub-grade shall comply with the tolerances itemized in the following table:

ITEM CHARACTERISTIC TOLERANCE Sub-grade Level +20mm / -20mm Thickness Unspecified

K. Should a section of the work be not acceptable on the basis of level, high areas shall be graded off, low areas shall be corrected by adding and compacting material similar to that already in place.

L. If the sub-grade has dried and becomes loose and dusty due to construction traffic, it should be watered, lightly bladed and rolled prior to placement of the sub-base layer.

M. The placement of the sub-base layer shall not be commenced until the sub-grade has been approved following inspection and/or testing.

3.02 SUB BASE AND BASE UNDER LAYER

A. Each layer of the pavement shall be completed to a surface parallel to the theoretical finished surface of the pavement and at a depth below it equal to the compacted thickness of the subsequent layers. 32 12 17 - 6 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS

B. Surface shape of each layer shall be such that water cannot accumulate at any point. If this is not possible, it is important to provide all necessary equipment, including automatically operated pumps and piping to run-off facilities, to maintain the excavations, pits, depressions free from accumulated water during the entire period of construction.

C. All fill material and crushed stone shall be spread evenly by direct tipping from suitable vehicles or by the use of a mechanical spreader above the approved sub-grade. Care should be taken to avoid segregation of granular material during tipping and spreading.

D. Layers of pavement material shall be not less than 4” (10 cm) in compacted thickness. Maximum layer thickness shall be limited to that which will allow compaction to specified densities by the equipment in use.

E. Ordinary fill material and crushed stone, when delivered, shall have a moisture content within +/- 2% of the modified optimum moisture content. During compaction moisture content shall be maintained in the correct range. If the fill material or crushed stone does not contain the proper moisture content for compaction, it shall be wetted or dried as required before rolling. Water spraying equipment used for this purpose shall be capable of uniformly distributing water in controlled quantities over uniform lane widths.

F. Each layer of the ordinary fill material shall be disked whenever necessary to break down clods, thoroughly mix the different materials, secure a uniform moisture content and ensure uniform density and proper compaction.

G. When the moisture content and condition of each spread layer is satisfactory, the area shall be rolled by an approved type roller to a minimum density of ninety-five (95%) as determined by the Modified Proctor Test (AASHO). The final rolling shall be accomplished with a tandem steel roller. Rollers of variable mass shall receive ballast to the greatest mass that can be supported without distress to the pavement or subgrade.

H. Surfaces of fine crushed rock shall be constructed slightly higher than the specified levels and cut to profile by power grader towards the end of the compaction process. Rolling shall then continue to specified density to produce a tight, even surface without loose stones or slurry of fines.

I. Should a section of the work be not acceptable on the basis of inadequate compaction, further compaction shall be applied until the specified standard is achieved. If the moisture content varies outside the specified 32 12 17 - 7 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS limits, add water or allow drying as necessary. Before commencing rolling mix mechanically for the full depth of the layer to ensure uniform distribution of moisture.

J. Pavement base under layer courses shall comply with the tolerances itemized in the following table:

ITEM CHARACTERISTIC TOLERANCE Base under layer Level +5mm / - 5mm Straightness 6 mm maximum deviation from 4m straight-edge in all directions Thickness +15mm / -15mm

Sub-base Level +10mm / -10mm Thickness +30mm / -30mm

K. Should a section of the work be not acceptable on the basis of elevation, flatness or depth, high areas shall be graded off, low areas shall be scarified to the full layer depth, built up as necessary and re-compacted as specified.

L. Each successive layer shall not be commenced until the underlying layer has been approved following inspection and/or testing.

M. The base under layer must be firm, non-yielding and not pumping under the travel of haul trucks and other construction equipment at the time of the laying of the hot mix asphalt. Base under layers that show movement under trucks or construction equipment will need additional compaction work or other remedial work to repair the substandard installation.

3.03 HOT MIX ASPHALT PAVEMENT INSTALLATION

A. Mixing of hot mix asphalt should be undertaken in a mixing plant capable of effectively drying and heating the aggregate to the specified temperature, accurately proportioning and uniformly mixing coarse and fine aggregate, filler and binder to meet the specified requirements at all times. In general, batch-mixing plants are preferable to drum mixing plants, because of their greater capability to fine-tune the aggregate gradation. For all types of mixing facilities:  Cold aggregates must be handled and stored in a manner that avoids contamination and minimizes degradation and segregation.  Filler shall be stored and handled in a separate system from that which handles aggregate

32 12 17 - 8 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS  The bitumen storage and handling shall be arranged so that contamination of the bitumen by flushing liquids or other materials cannot occur.  The bitumen storage tanks shall be capable of holding at least sufficient bitumen for one day’s production.  Heating of bitumen shall be accomplished by steam coils, electricity or other means that will allow no direct flame to come into contact with the heating tank.  Discharge from the plant shall be so arranged as to minimize segregation.  Asphalt, which has been stored for more than twenty-four hours or produced at temperatures not in accordance with those specified, shall not be used.  The mix shall leave the mixing facility at a temperature between 285°F (140°C) and 325°F (163°C).

B. The hot mix asphalt must be kept clean during hauling and covered if necessary during transit with canvas or other material that will retain the desired pavement temperatures. The mixtures must not be hauled in such a manner that segregation of the ingredients takes place or that a crust is formed on the surface, or that mixture will crumble or flatten out when dumped. Trucks that transport the mixture must have metal beds, and the beds must be clean, smooth and free of holes. Before loading, the truck bed is coated with a thin film of a release agent (oil or soap solution) that assists in preventing fresh hot mix asphalt from sticking to the surface of the bed. After the bed is coated, any excess release agent must be drained from the bed.

C. The hot mix asphalt shall be spread with a self-propelled machine spreader having a floating screed assembly controlling the elevation of the strike-oft. The use of road graders or towed spreaders will not be allowed. Means shall be provided to heat the screed uniformly over its full width. The screed shall be equipped with automatic screed controls to adjust automatically to place a uniform mat of desired thickness, grade and shape.

D. Typical members of the paving crew should be: paving superintendent, paver operator, dump person, two screed people, and two people to lute and take care of joints and mat repairs. Co-ordination of the entire crew with the paving superintendent and screed people is essential to achieve all the desired goals.

E. Self-propelled rollers are required as compaction equipment. Towed-type rollers should not be used. Hand-held or vibrating plate compactors can be used in small, inaccessible areas. Steel-wheeled non-vibrating rollers shall have a mass of 10 tons (9 metric tons). 32 12 17 - 9 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS Steel wheeled vibrating rollers shall have a mass of 5 tons (4.5 metric tons). Pneumatic tired multi-wheeled rollers shall not be used.

F. The hot mix asphalt shall be placed with a minimum delay after delivery. On no account shall hot mix asphalt be reheated.

G. The day’s work shall be organized so that each layer spread covers the full width of the pavement.

H. Hot mix asphalt shall be spread to a depth consistent with the specified compacted thickness. Each layer shall be completed to a surface parallel to the finished surface of the pavement and at a depth below it equal to the compacted thickness of the subsequent layer or layers specified.

I. Hot mix asphalt shall not be placed during rain, or when the air temperature in the shade and away from artificial heat is 40°F (5°C) or less, or while the surface is wet or when the pavement temperature does not comply with the Table below.

Pavement surface temp. Minimum Laying Temps. Minimum Laying Temps.

40°F - 50°F (5°C - 10°C) 302°F (150°C) 293°F(145°C) 50°F - 60°F (10°C - 15°C) 293°F (145°C) 284°F(140°C) 60°F - 77°F (15°C - 25°C) 284°F (140°C) 275° (135°C) Over 77°F (Over 25°C) 275°F (135°C) 266°F (130°C)

J. Maximum laying temperature of the mixture shall be 325°F (163°C)

K. The temperature of the mix shall be measured in the truck just prior to discharging into the paver hopper. A suitable stem type thermometer shall be used. The stem shall be inserted into the mix to a depth of approximately 8" (200mm) at a location at least 12" (300mm) from the side of the truck body. An average of at least two readings shall be adopted as the temperature of the mix.

L. There are three acceptable types of sensing devices used with the automatic screed control system:  The Wand Sensor  The Ultra Sonic Sensor  The Laser Sensor

M. The grade reference used with the above listed sensing devices can be either a fixed string line tied between graded iron pins or on an existing surface, a previously placed surface, a curb line, etc. A string line can be erected that will include roll down factors for true grade. The roll down is estimated to be about 25% of the non-compacted mat thickness. To 32 12 17 - 10 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS calculate the exact position of the string line, a survey crew is used to determine the existing grade at approximate intervals of 9 meters (30 feet). The existing grade is subtracted from the theoretical grade for calculation of lift thickness. A roll down factor of 25% of this thickness is added for the string line grade. Once the string line is erected, intermediate points of support may be placed under the string line, especially on curves or in sudden changes of grade. Graded iron pins and intermediate supports should be placed so that they will not interfere with the travel of the machine spreader, but close enough to each other and to the path of the machine spreader that they can hold the string in a convenient position to be reached by the electronic sensors and by a short straight edge placed on the newly laid pavement to visual check on its level.

N. The reference system that is best for the job depends on the existing pavement surface on which the mat is to be placed. If the surface on which the mat is to he placed has an appropriate longitudinal grade, so that the finished pavement is expected to have a constant thickness, then the surface on which the mat has to be placed, an adjoining existing surface, a previously placed surface, a curb line, etc. can be used as the reference system, since a constant roll down is expected. If the longitudinal grade is erratic, so that the finished pavement is expected to have a variable thickness, a string line should be used as the reference system, to take in account the variable roll down.

O. To maintain proper transverse grade, automatic screed controls use:  a dual sensing systems on both sides of the paver, using two grade references, one on each side of the paver or  a single sensing system on a single side of the paver, using a single grade reference on a single side of the paver, in association with an automatic slope control system: in using the transverse slope control, no specific roll down factors can be applied to grade calculations for slope transfer. The Control System that is best for the job depends on the existing pavement surface on which the mat is to be placed. Dual Grade Control System is preferable if the surface on which the mat has to be placed has an unsatisfactory transverse grade. Single Grade Control System transfers the roll- down factors of the grade control side to the opposite side as equal factors, which may or may not be equal. Single Grade Control System is acceptable in situations where the surface on which the mat is to be placed has an appropriate transverse grade.

P. The area to be surfaced with hot mix asphalt shall be cleared of all foreign or loose material with power blowers, power brooms or hand brooms.

32 12 17 - 11 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS Q. Crushed stone or asphalt surfaces shall be primed prior to the installation of the binder course and top coat. Prime crushed stone surfaces at the rate of 0.3 gallons per square yard. Prime asphalt surfaces at the rate of 0.05 gallons per square yard. Sprayers shall be capable of spraying the tack coat uniformly through jets in a spray bar at the desired rate of application. Each sprayer shall be fitted with a hand lance. Tack Coat shall be applied, not less than thirty (30) minutes nor more than two (2) hours before asphaltic concrete is placed. When spraying the tack coat, shields shall be used and all necessary precautions taken to protect curbs, gutters, channels, adjoining structures, surfaces and grassed areas. Any pools of tack coat which may form in small depressions or surface irregularities shall be brushed out over the adjacent area with brooms or rubber squeegees before the emulsion breaks. In dusty conditions, every precaution shall be taken to prevent freshly coated surfaces from being contaminated by dust or other foreign material.

R. Uniformity of operations is essential in hot mix asphalt paving. Uniform, continuous operation of the paver produces the highest quality pavement. Paving too fast can result in the paver stopping frequently to wait for trucks to bring more mix. The smoothness of the pavement will suffer when the paver stops and starts up again. The paver speed should he matched to the quantity of HMA being delivered to the project to provide a uniform paver speed. The paver must be continuously supplied with enough mix, and at the same time, trucks should not have to wait a long time to discharge their loads into the paver hopper.

S. Starting blocks equal to 1.25 times the thickness of the non-compacted mat are required to set the thickness and to null the screed. By using starting blocks the grade can be very close at the beginning of the operation.

T. Blocks equal to 25% of the non-compacted thickness are used to start from a joint. The 25% additional thickness allows for proper roll-down or compaction while maintaining proper grade. Extended screeds will require multiple shims for each extension area.

U. The screed must be initially heated at the start of each new paving operation. If not, the mix will tear and the texture will look open and coarse, as if the mix were too cold.

V. If the mat being placed is uniform and satisfactory in texture, and the thickness is correct, no screed adjustments are required. But when adjustments are required, they should be made in small increments. Time should he allowed between the adjustments to permit the paver screed to complete reaction to the adjustments sequentially.

32 12 17 - 12 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS W. The minimum non-compacted thickness of a hot mix asphalt course is equal to 1.25 times its minimum compacted thickness, which is equal to three times the nominal maximum size aggregate. When the mat falls below this thickness, it pulls, tears, cools rapidly and generally will not be able to achieve the proper density and pavement smoothness.

X. There are places on many projects where spreading with a paver is either impractical or impossible. In these cases, hand spreading may he required. Placing and spreading by hand should be done very carefully and the material distributed uniformly so there will be no segregation of the mix. When the HMA is dumped in piles, it should be placed upon arrival on steel dump sheets outside the area in which it is to be spread and shall then be immediately laid to the required depth. The material should be deposited from the shovels into small piles and spread with lutes. In the spreading process, all material should be thoroughly loosened and evenly distributed. Any part of the mix that has formed into lumps and does not break down easily should be discarded. After the material has been placed and before rolling starts, the surface should be checked with templates or straightedges and all irregularities corrected.

Y. Asphaltic concrete shall be spread in such a manner as to minimize the number of transverse and longitudinal joints in the pavement.

Z. Transverse joints shall be constructed where the spreading operation is stopped for longer than 20 minutes. Transverse joints in adjoining spreader runs shall be offset by not less than 8 feet (2.44m). Transverse joints shall be offset from layer to layer by not less than 8 feet (2.44m). Transverse joints shall be constructed at right angles to the direction of spreading and be cut to a straight vertical face for the full depth of the layer.

AA. When the construction is ready to stop for the end of the day or for a period longer than 20 minutes, the following procedure is used to form a suitable transverse joint: 1. When the paver is placing the last load, it is shifted into low gear as it approaches the location of the proposed joint. 2. As the hopper empties and the amount of material in the screed chamber decreases below normal operating level, the paver is stopped. 3. The screed is raised and the paver moved out of the way. 4. The mix is then removed from the end of the mat to form a clean, vertical edge. 5. Heavy wrapping paper is placed on the existing surface along the edge of the joint. 6. New material is finally placed on top of the paper and used to form a ramp, from the new surface to the existing surface. 32 12 17 - 13 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS

BB. When construction is ready to resume, the following procedure is used to form a suitable transverse joint: 1. The ramp of material is removed along with the board or paper. 2. A straightedge is used to check the longitudinal grade of the mat. Because the paver was running out of material as it laid the last few feet of mat, it is possible that those last few feet taper slightly from the specified level of the mat. If this is the case, a new transverse edge must be cut behind the point where the taper begins. 3. The vertical face of the mat is tack-coated. 4. The paver is backed up to the edge of the mat and the screed rested on the mat surface. 5. The screed is heated while it rests on the mat. This provides some heat to the material at the edge of the mat. 6. The heated screed is raised and shims as thick as the difference between the compacted and the non-compacted mat (approximately 25% of the compacted thickness) are positioned under its ends. 7. The truck with the first load of HMA is backed carefully to the hopper. During discharge of the mix from the truck bed to the paver, it is essential that the truck not bump the paver and cause it to move. 8. The paver starts forward in a low gear. 9. Once the paver has moved away, excess asphalt is cleaned off the surface of the mat and the smoothness of the joint is checked with a straightedge. 10. If the joint is satisfactory, a 6" (150mm) width of the fresh mix is rolled transversely and the joint checked for smoothness. If the joint is satisfactory, transverse rolling is continued in 6" to 12" (150 to 300mm.) increments until the entire width of the roller is on the new HMA. If straight edging shows an uneven joint, the surface of the new mat must he scarified while still warm and workable. Scarification is done with the fine side of the lute. Excess material can then be removed or additional material added, and the joint rolled. During rolling, timbers should he placed along the edges of the mat to prevent the roller from driving off the longitudinal edge and distorting it.

CC. Longitudinal joints shall be offset from layer to layer by not less than 6" (150mm). Longitudinal joints shall be parallel to the center line of the pavement. Alignment of the mat is dependent on the accuracy of the guideline provided for the paver operator and his alertness in following it. Attention to this detail is vital to the construction of a satisfactory longitudinal joint, since only a straight edge can be properly matched to make the joint

32 12 17 - 14 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS DD. Hot joints are formed by two payers operating in echelon. The screed of the rear paver is set to match the grade or thickness of the unrolled edge of the first mat placed. The advantages of a hot joint are that the two mats are automatically matched in thickness, the density on both sides of the joint is uniform because both sides are compacted together, and the hot mats form a solid bond. The disadvantage is that traffic cannot move in one of the lanes while the other is being paved. Both lanes are blocked simultaneously.

EE. In building a cold joint, one lane is placed and compacted. At a later time, after the HMA in the first lane has cooled, the companion lane is placed against it and compacted. Special precautions must be followed to ensure a joint of good quality.

FF. The following procedure is used to form a suitable longitudinal joint: 1. The exposed edge of the first lane shall be formed while hot to a straight line with a dense face, which shall lie between vertical and 45° to the vertical for the full depth of the layer. 2. The unsupported longitudinal edges of spread material should be side tamped to raise the level of the asphaltic concrete slightly to secure maximum edge compaction from subsequent rolling 3. While placing the companion lane, the paver screed should be set to overlap the first mat by 1" to 2" (25 to 50 mm). 4. The elevation of the screed above the surface of the first mat should he equal to the amount of roll-down expected during compaction of the new mat. 5. The coarse aggregate in the material overlapping the cold joint should be carefully removed and wasted. This leaves only the finer portion of the mixture to be pressed into the compacted lane at the time the joint is rolled.

GG. The placing of hot mix asphalt against abutting structures such as curbs, gutter manhole or adjoining pavement shall be carried out in the same manner as for longitudinal and transverse joints. Any spaces left unfilled between the spreader run and abutting edges shall be filled with sufficient material to the proper height prior to compaction.

HH. After the paving mixture has been property spread, it shall be thoroughly and uniformly compressed by rolling with power rollers.

II. Hot mix asphalt shall be compacted uniformly to the standard specified as soon as it will support rollers without undue displacement. All rolling shall be completed while the mix is at a temperature above 185°F (85°C)

32 12 17 - 15 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS JJ. The pavement shall be compacted to 97% or more of the density (ASTM F2726) obtained on a retained job mix specimen by the seventy-five blow Marshall procedure (ASTM D1559), Marshall stability (ASTM D1559) shall be 750 lbs. or greater.

KK. The exact number of passes of a roller that will be required to obtain adequate density will be determined on a test strip using a nuclear density gauge to measure the density of the mat after each pass, until maximum achievable density is indicated by the test results. The rolling pattern used on the test strip should be the same that will be used on the remainder of the job. The number of rollers and/or the rate of production will be adjusted accordingly.

LL. The speed of rollers at all times shall be slow enough to avoid displacement of the mix and shall not be greater than 3 miles/h (5km/h). 3.3.39 Steel wheel rollers shall be operated with minimum wetting of rollers.

MM. The driving roll shall be nearer the spreader.

NN. Vibratory mechanisms shall be disengaged before stopping or reversing direction.

OO. Rollers shall not remain stationary on asphaltic concrete while it is still warm. Roller shall be kept free from any build-up.

PP. The roller shall pass over the unprotected end of the freshly laid mixture only when a transverse joint has to be made.

QQ. Initial (breakdown) rolling shall be performed with a static steel-wheeled roller. Transverse joints shall be rolled first, then the longitudinal joint and the outside edge. Breakdown rolling shall continue longitudinally, commencing on the lower side and proceeding to the higher side of the spreader run. The roller shall overhang the unsupported edges of the run by about 4-inch (100mm). Each longitudinal pass shall overlap the previous pass by about 4-inch (100mm) and adjacent passes of the roller shall be of different lengths.

RR. Secondary rolling to obtain required density before the mixture cools to 185°F (85°C) shall be performed as soon as possible after initial rolling and shall be performed with a static or a vibratory steel wheeled roller. Rolling shall be carried out longitudinally commencing on the lower side and proceeding to the higher side of the spreader run. Each roller pass shall overlap the previous pass and adjacent passes shall be of different lengths.

32 12 17 - 16 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS SS. Final rolling for the improvement of the surface while the mixture is still warm enough to permit removal of any roller marks shall be performed with static steel wheeled roller.

TT. When paving in echelon, the edge of the run common to adjacent spreaders shall be left unrolled for a width of 8 inch (200mm) until the longitudinal joint has been constructed. This strip shall be rolled together with the edge of the adjacent spreader run. Rolling shall commence before the temperature of the material along the edge of the first spreader run has fallen below 95°C (203°F)

3.04 ACCEPTANCE OF PAVING WORK – REMEDY WORK

A. Each successive layer shall not be commenced until the underlying layer has been approved following inspection and/or testing.

B. Acceptance of paving work as far as compaction and Marshall Stability specifications is concerned will be based on tests to be performed on core samples taken from each layer shortly after application. Test results shall be submitted to Mondo.

C. Should a section of the work be not acceptable on the basis of inadequate compaction and/or the mixture became loose and broken, mixed with dirt or in any way defective, it shall be removed and replaced with fresh mixture which shall be immediately compacted to conform with the surrounding area.

D. On completion of placement and compaction, pavement courses shall comply with the tolerances itemized in the following table.

ITEM CHARACTERISTIC TOLERANCE Top Coat Level +2mm / -2mm from design levels Thickness +5mm / -0 mm from design thickness Flatness 3mm maximum departure from a 3m straight-edge in all directions Binder Course Level +4mm / -4mm from design levels Thickness +5mm / -0mm from design thickness Flatness 4mm maximum departure from a 3m straight-edge in all directions

E. Surface shape of each layer of pavement shall be such that water cannot accumulate at any point and the surface shall free drain to drainage channels.

32 12 17 - 17 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS F. The whole surface of each layer of pavement should be checked for levels by a local surveyor, and for flatness with a 10 foot straightedge in all directions; the surface shall also be flooded and inspected for ponding, ‘‘bird baths”, ridges, etc. After testing, all high and low areas shall be marked on the leveling course surface.

G. Areas of one (1) square inch or more showing excess of bitumen shall be removed and replaced.

H. Asphalt infrared repair techniques: high and low asphalt sections can be remedied using infrared asphalt heaters that allow continuous, uniform re- heating of the asphalt to the same temperature that new asphalt is manufactured at the plant. The softened asphalt can be scarified to mix in fresh hot mixture, or to remove and dispose the excess. The repaired area shall be thoroughly compacted to the specified tolerance. Infrared repair techniques are typically 25% faster than conventional remove and replace repair techniques since they eliminate saw cutting, jack hammering, removal, loading, and trucking and they do not leave a joint around the perimeter of a repair.

I. Asphalt removal and replacement: high and low asphalt sections, sections that became loose and broken because of localized cohesive failure, or mixed with dirt or mud, or showing excess of bitumen, or contaminated by oil spills that penetrated deep into the asphalt can be remedied by cutting out the top course to full depth - or to a minimum depth of 1” - and replacing with new hot mixtureat the correct elevation. First the area must be tack coated. The repaired area shall be thoroughly compacted to the specified tolerance. Areas affected by cracks and fissures generated by instability of the subbase shall be cut out to the full depth of the stone base and replaced. First the defective subbase shall be remedied or replaced.

J. Asphalt profile milling: minor profile deficiencies of asphalt pavements can be remedied through profile milling. Profile milling equipment is typically used to provide roughened texture to an existing asphalt pavement. Prior to the installation of the synthetic track surfacing, the grooved surface resulting from profile milling shall be leveled using Mondo’s 2-component polyurethane adhesive as a leveling compound. No urethane products other than Mondo’s 2-component polyurethane adhesive shall be used as a leveling compound. No personnel other than Mondo’s certified outdoor installers shall perform leveling work with Mondo’s 2-component polyurethane adhesive.

K. Additional finish rolling of asphalt in warm weather, when pavement temperature is equal to or above 85°C (185°F), can be performed to remedy minor profile deficiencies and to remove tire marks and roller 32 12 17 - 18 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS marks. Additional finish rolling shall be immediately interrupted in the event of over-compaction.

L. Asphalt leveling with Mondo’s 2-component polyurethane adhesive: shallow, low asphalt sections can be leveled using Mondo’s 2-component polyurethane adhesive as a leveling compound. The depth of the leveling layer must be limited to ¼” or less. Extensive use of polyurethane adhesive as leveling compound is no substitute for proper installation and/or repair of the base. No urethane products other than Mondo’s 2- component polyurethane adhesive shall be used as a leveling compound. Mondo’s 2-component polyurethane adhesive must be applied on fully oxidized asphalt (minimum 30 day curing time). No personnel other than Mondo’s certified outdoor installers shall perform leveling work with Mondo’s 2-component polyurethane adhesive. If leveling is performed to correct drainage problems, the Owner/GC shall supply adequate means to flood the track throughout the duration of the installation.

M. All contaminants must be removed from the base via mechanical abatement such as power washing, sanding, wet grinding, scarifying or shot-blasting. The degree of aggressivity required will vary with the type and depth of penetration of the compound on the surface.

N. Never use chemical abatement methods as residual chemicals on or penetrating the surface of the base can lead to failures.

O. No open flames shall be applied to soften the asphalt since open flames would burn bitumen and reduce the internal cohesion of the mixture.

P. No filling of low spots with sand mixes shall be allowed. Sand mixes lack sufficient internal cohesion.

Q. No tar emulsions shall be applied to the surface. Nor shall any other type at asphalt or tar leveling or sealing product (hot or cold) be coated on the surface.

R. No asphalt milling shall be performed to remedy profile deficiencies since the texture resulting from milling is too rough to be leveled using Mondo’s 2-component polyurethane adhesive as a leveling compound.

3.05 CURING OF HOT MIX ASPHALT INSTALLATIONS

A. The asphalt leveling course will have to cure a minimum of thirty (30) days prior to installation of the Mondo surface in order to allow the escape of surface volatiles, oils. etc. and to maximize resin adhesion of the Mondo flooring to the asphalt pavement.

32 12 17 - 19 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS

PART 4 - MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

32 12 17 - 20 ASPHALTIC CONCRETE PAVING – FOR TRACK SURFACING AREAS

SECTION 32 13 13

CONCRETE PAVING

PART 1 GENERAL

1.01 SUMMARY OF WORK

A. The scope of work in this section includes, but is not necessarily limited to PCC vehicular paving, ribbon and cross-gutter pavement and related concrete improvements as shown on drawings and specified below.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 33 00 – Submittal Procedure

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

2. State of California, Department of Transportation, Standard Specifications, July, 2010.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

2. State of California, Department of Transportation, Standard Plans, 2010.

C. American Society for Testing and Materials, referred to hereinafter as ASTM

1.04 SUBMITTALS

A. Materials List/Samples

1. Provide complete list of proposed materials to the District’s Submittals shall include but are not limited to mix design, air- entraining admixtures and related product data.

PART 2 MATERIALS

2.01 DESIGN CRITERIA

32 13 13 - 1 CONCRETE PAVING

A. Where criteria shown on drawings or specified in this specification exceed that of the referenced standards, and the work involves non-public improvements, the more stringent criteria shall apply.

B. The following shall be the minimum concrete strengths for concrete paving work:

1. Vehicular Paving/ Comm. Dwy: 520-C-3250 (SDRSD)

2. Cross-gutters, and ribbon Gutters: 560-C-3250 (SDRSD)

2.02 PORTLAND CEMENT CONCRETE

A. Concrete shall consist of Portland cement, concrete aggregates, water, and when specified or approved for use, chemical admixtures, and/or SCMs, fibers, color, and/or reclaimed concrete material. Concrete shall be specified by class, alternate class, special exposure, or compressive strength, and shall be per Section 201-1 of the SSPWC.

2.03 JOINT SEALANT MATERIAL

A. Joint sealant material shall be per Section 201-3 of the SSPWC.

2.04 OTHER MATERIALS

A. All other materials, not specifically described but required for complete and proper installation of this work, shall be selected by the Contractor and subject to the approval of the Owner/District

PART 3 EXECUTION

3.01 SURFACE CONDITION

A. Inspection:

1. Prior to all work of this section, carefully inspect the installed work of all other trades and verify that all such work is complete to the point where this installation may properly commence.

2. Portland Cement Concrete paving and concrete finishes shall be stable, firm, and slip resistant, and shall comply with CBC Sections 11B-302 and 11B-403.

32 13 13 - 2 CONCRETE PAVING

3. Verify that concrete pavement may be installed in strict accordance with the original design, all pertinent codes and regulations, and all pertinent portions of the referenced standards.

B. Discrepancies:

1. In the event of discrepancy, immediately notify the Engineer, and the District

2. Do not proceed with installation in areas of discrepancy until all such discrepancies have been fully resolved.

3. Do not remove support forms or shoring until concrete has sufficient strength to carry its own weight and other loads upon it.

4. Remove forms only after concrete has properly set and without damaging concrete.

3.02 CONCRETE PAVING INSTALLATION

A. Preparation

1. Verify sub-grade, conduit and all other embedded items are properly located in relation to concrete paving. Verify all grades for pitch and fall prior to pouring pavements.

B. Placement

1. Install all curbing, cross gutters, and related improvements per Section 303-5 of the SSPWC, as specified herein, and as shown on drawings. Where machine formed curbing is provided, tolerances and joint control specified for fixed form construction shall be met.

C. Joint Treatment

1. Provide construction, expansion, and weakened plane joints as required by SDRSD for concrete pavement areas.

2. Properly prepare edges of joints prior to proceeding with subsequent operations. Remove all contaminants laitance, oil and other deleterious substances prior to installing joint sealant.

3. Evaluate surfaces for grade and drainage. Correct all non-conforming surfaces, ponds and other irregularities to the satisfaction of the Owner.

32 13 13 - 3 CONCRETE PAVING

PART 4 MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

4.02 PCC PAVEMENT W/ BASE; BID ITEM

A. PCC PAVEMENT W/ BASE will be measured by the square foot of area completed as shown on the plans and as determined by the Engineer from field verification.

B. The Contract unit price for PCC PAVEMENT W/BASE shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals, and for doing all the work involved in PCC PAVEMENT W/BASE to complete in place, including but not limited to, preparing the subgrade, testing for, and furnishing the mixed design, weed control, placing and compacting aggregate base, pouring PCC paving, as shown on the Drawings and as specified in these Technical Specifications.

C. Payment shall be determined using the unit price and the quantity installed. The estimated bid quantity is for the purpose of establishing a Contract unit price for this item and the District reserves the right to adjust the actual quantity to 85% to 125% of the bid quantity at no change to the Contract unit price.

4.01 CROSS GUTTER/RIBBON GUTTER; BID ITEM

A. CROSS GUTTER/RIBBON GUTTER will be measured by the square foot of area completed as shown on the plans and as determined by the Engineer from field verification.

B. The Contract unit price for CROSS GUTTER/RIBBON GUTTER shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals, and for doing all the work involved in CROSS GUTTER/RIBBON GUTTER to complete in place, including but not limited to, preparing the subgrade, testing for, and furnishing the mixed design, weed control, placing and compacting aggregate base, pouring PCC paving, as shown on the Drawings and as specified in these Technical Specifications.

C. Payment shall be determined using the unit price and the quantity installed. The estimated bid quantity is for the purpose of establishing a Contract unit price for this item and the District reserves the right to adjust the actual quantity to 85% to 125% of the bid quantity at no change to the Contract unit price.

32 13 13 - 4 CONCRETE PAVING

**END OF SECTION**

32 13 13 - 5 CONCRETE PAVING SECTION 32 16 13

CONCRETE CURBS AND GUTTERS

PART 1 GENERAL

1.01 SUMMARY OF WORK

A. The scope of work in this section includes concrete curbs and gutters, including but not limited to the deepend curbs, cutoff walls, curb transitions, addition of curb cut openings adjacent to the bioretention areas, preparation of subgrade, forms, joints, finishing, curing, and other appurtenant work as shown on the drawings and specified herein.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 33 00 – Submittal Procedure

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

2. State of California, Department of Transportation, Standard Specifications, July, 2010.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

C. American Society for Testing and Materials (ASTM):

1. ASTM A53 Specification for Pipe, Steel, Black and Hot-Dipped, Zinc- Coated, Welded and Seamless

2. ASTM A615 Specification for Deformed and Plain Billet-Steel Bars for Concrete Reinforcement

3. ASTM A663 Specification for Steel Bars, Carbon, Merchant Quality, Mechanical Properties

4. ASTM C260 Specification for Air-Entraining Admixtures for Concrete

32 16 13 - 1 CONCRETE CURBS AND GUTTERS 5. ASTM C309 Specification for Liquid Membrane-Forming Compounds for Curing Concrete

6. ASTM C881 Specification for Epoxy-Resin-Base Bonding Systems for Concrete

D. American Concrete Institute (ACI):

1. ACI 117 Standard Specification for Tolerances for Concrete Construction Materials

2. ACI 301 Standard Specifications for Structural Concrete

3. ACI 318 Building Code Requirements for Reinforced Concrete

1.04 SUBMITTALS

A. General: Refer to Section 01 33 00 - Submittal Procedures for submittal requirements and procedures.

B. Product Data: Submit the respective manufacturer's product data for manufactured products.

C. Shop Drawings:

1. Submit drawings that indicate the section profile of curb and gutter, and the locations of joints in concrete, including construction joints, expansion joints, isolation joints, and contraction joints.

2. Submit drawings of extruded curbs and gutters, if proposed, and any modification of the indicated section profile required by the extrusion process.

PART 2 MATERIALS

2.01 MATERIALS

A. Materials for concrete curb and gutters shall be per Section 201 of the SSPWC and the applicable Regional Standard Drawings and as detailed on the Drawings.

B. Concrete strength for concrete curb and gutter and median curb shall be 520-C-2500 minimum (SDRSD)

PART 3 EXECUTION

3.01 TYPES OF CONSTRUCTION

32 16 13 - 2 CONCRETE CURBS AND GUTTERS A. Provide cast-in-place concrete construction, plain or reinforced as indicated. Curbs and gutters shall be formed accurately to indicated in the section profile, and SDRSD.

B. Extruded curbs and gutter, placed by an extrusion machine, may be provided where site conditions are suitable and the extrusion process is appropriate for the purpose.

3.02 CURING AND PROTECTION

A. Comply with the applicable requirements of Section 303-5 of the SSPWC.

PART 4 MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

4.02 CONCRETE CURB AND GUTTER, BID ITEM

A. CONCRETE CURB AND GUTTER will be measured as linear feet as shown on the plans and as determined by the Engineer.

B. The Contract unit price paid for CONCRETE CURB AND GUTTER shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals for doing all the work of CONCRETE CURB AND GUTTER to complete in place, including but not limited to forms, placing, the addition of curb cut openings, transitions, deepened curb in areas adjacent to the bioretention area as shown on the Drawings and specified in these Technical Specifications.

**END OF SECTION**

32 16 13 - 3 CONCRETE CURBS AND GUTTERS SECTION 32 17 23

PAVEMENT MARKINGS, STRIPING AND SIGNS

PART 1 GENERAL

1.01 DESCRIPTION

A. This section includes materials and installation of pavement striping, lettering, and marking for parking, vehicular traffic control and direction on asphalt and concrete surfaces.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 33 00 – Submittal Procedure

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2012 Edition (Green Book), including the Regional Supplement.

2. State of California, Department of Transportation, Standard Specifications, July, 2010.

3. California Manual on Uniform Traffic Control Devices (FHWA's MUTCD, 2012 Edition, as amended for use in California).

4. California Building Code (2013) Code of California Regulations Title 24, Part 2.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

2. State of California, Department of Transportation, Standard Plans, 2010.

1.04 SUBMITTALS

A. Submit in accordance with Section 01 33 00.

1.05 ENVIRONMENTAL CONDITIONS

32 17 23 - 1 PAVEMENT MARKINGS, STRIPING AND SIGNS

A. Striping and Legends: Apply paint to clean, dry surfaces and unless otherwise approved, only when air and pavement temperatures are above 40 degrees F for oil- based materials, 50 degrees F for water-based materials, and are less than 95 degrees F. Maintain paint temperatures within these same limits.

1.06 EQUIPMENT

A. Use a stripe painting machine capable of producing marking and striping indicated. Provide equipment having a compressor capacity of at least 105 cubic feet and capable of operating at an air pressure of 125 psi. Provide striping machine with a pointer so the machine will hold exactly to alignment. Provide propelling vehicle with a speedometer or tachometer, and with a suitable device for determining quantity of paint in the container. Mechanically agitate paint while equipment is in operation. Clean paint container and spray nozzles on machine before starting work each day.

1.07 SAFETY DURING CONSTRUCTION

A. The Contractor shall assume sole and complete responsibility for job site conditions during the course of construction of the project, including safety of all persons and property. This requirement shall be made to apply continuously and not be limited to normal working hours. Refer to Part Three of this Section and Division 1 for additional requirements.

PART 2 MATERIALS

2.01 PAVEMENT MARKING PAINT

A. Product Characteristics

1. Provide paint specifically formulated for use as pavement marking in automobile and pedestrian traffic areas, and as required by the District.

2. Provide striping in size and multiple colors as shown on the construction drawings.

3. Paint products shall comply with Section 210-1.6.3 of the "Standard Specifications," for "rapid-dry" type paints. Paint manufacturer shall provide written certification of conformance to standard.

4. Reflective material shall consist of glass beads added to the surface of the final coat of paint and shall comply with Section 210-1.6.5.

PART 3 EXECUTION

3.01 SURFACE CONDITIONS

32 17 23 - 2 PAVEMENT MARKINGS, STRIPING AND SIGNS

A. Inspection

1. Prior to all work of this section, carefully inspect the installed work of all other trades and verify that all such work is complete to the point where this installation may properly commence.

2. Verify pavement may be installed in strict accordance with the original design, all pertinent codes and regulations, and all pertinent portions of the referenced standards.

3. In the event of discrepancy, immediately notify the Engineer.

4. Do not proceed with installation in areas of discrepancy until all such discrepancies have been fully resolved.

3.02 PREPARATION

A. Secure the Engineer's, and the Owner’s approval of graphics design and layout prior to start of application, including compliance with accessibility standards of Title 24.

B. Secure Fire Marshal approval of all striping and marking of curbs, pavement, and related signage.

C. Accessible and Van Accessible parking spaces shall be marked according to CBC Section 11B-502.

D. Verify that concrete curing compound and asphalt seal coat compound has become completely inert prior to painting. Remove by approved means for those areas where compound is still active.

3.03 INSTALLATION

A. Using proper masking, stencils, and application equipment recommended for the purpose by the manufacturer of the approved paint, apply the approved paint in strict accordance with its manufacturer's recommendations and Section 314-4.3.4 of the "Standard Specifications".

B. Provide minimum of two coats of paint at all striping, curbing, and related markings, in dry mil thickness as defined in Section 314-4.3.5. Vary color of first coat slightly.

C. Coatings installed on asphalt paving shall be applied in thin, light coats to avoid peeling.

32 17 23 - 3 PAVEMENT MARKINGS, STRIPING AND SIGNS

D. A minimum of ten (10) days shall elapse between seal coat application and pavement marking on asphaltic concrete.

E. Repaint markings damaged by construction traffic.

F. Install fire lane curb markings at locations required by Fire Marshal or at 20 feet on center, whichever is more restrictive.

G. Install markings within 1/2 inch tolerance. Maintain width to a tolerance of plus/minus 1/4 inch.

PART 4 MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

4.02 STRIPING

A. No measurement shall be made for this item.

B. PAVEMENT STRIPING will be paid for at the Contract lump sum amount for STRIPING which shall include full compensation for furnishing all labor, materials, equipment, tools and incidentals and for doing all the work of striping and lettering, including but not limited to, striping, as shown on the drawings and as specified in the Technical specifications, and no additional compensation shall be allowed.

C. PAVEMENT MARKINGS: a. ACCESSIBLE PARKING SPACES SERVING A PARTICULAR BUILDING OR FACILITY SHALL BE LOCATED, AND DISPERSED IF SERVING MORE THAN ONE ACCESSIBLE ENTRANCE, ON THE SHORTEST ACCESSIBLE ROUTE TO AN ENTRANCE OR TO MULTIPLE ACCESSIBLE ENTRANCES. CBC SECTIONS 11B-208.3.1 b. ACCESSIBLE PARKING SPACES IN A PARKING FACILITY NOT SERVING A PARTICULAR BUILDING OR FACILITY SHALL BE LOCATED ON THE SHORTEST ACCESSIBLE ROUTE TO AN ACCESSIBLE PEDESTRIAN ENTRANCE OF THE PARKING FACILITY. CBC SECTIONS 11B-208.3.1 c. MINIMUM NUMBER OF REQUIRED ACCESSIBLE PARKING SPACES SHALL BE PROVIDED IN ACCORDANCE WITH CBC TABLE 11B-208.2 FOR EACH PARKING FACILITY PROVIDED. d. FOR EVERY SIX OR FRACTION OF SIX ACCESSIBLE PARKING SPACES, AT LEAST ONE SHALL BE AN ACCESSIBLE VAN PARKING SPACE. CBC SECTION 11B-208.2.4 32 17 23 - 4 PAVEMENT MARKINGS, STRIPING AND SIGNS

e. ACCESSIBLE PARKING SPACES AND ACCESS AISLES SHALL COMPLY WITH CBC SECTION 11B-502 AND SHALL BE DIMENSIONED TO THE CENTERLINE OF THE MARKED LINES AS FOLLOWS: f. PARKING SPACES AND ACCESS AISLES SHALL BE MARKED ACCORDING TO CBC FIGURES 11B-502.2, 11B-502.3, AND 11B 502.3.3. THEIR SURFACES SHALL COMPLY WITH CBC SECTION 11B-302 AND SHALL BE AT THE SAME LEVEL WITH SLOPES NOT STEEPER THAN 1:48 IN ANY DIRECTION. CBC SECTION 11B-502.4 g. PARKING SPACES SHALL BE 9’X18’ MINIMUM AND VAN PARKING SPACES SHALL BE 12’X18’ MINIMUM WITH AN ADJACENT ACCESS AISLE OF 5’X18’ MINIMUM. ACCESS AISLES SHALL BE PLACED ON EITHER SIDE OF THE PARKING SPACES EXCEPT BE LOCATED ON THE PASSENGER SIDE FOR VAN PARKING SPACES. VAN PARKING SPACES SHALL BE PERMITTED TO BE 9’X18’ MINIMUM WHERE THE ACCESS AISLE IS 8’X18’ MINIMUM. h. ACCESS AISLES SHALL BE MARKED BY A BLUE PAINTED BORDERLINE AROUND THEIR PERIMETER. THE AREA WITHIN THE BLUE BORDERLINES SHALL BE MARKED WITH HATCHED LINES A MAXIMUM OF 36” ON THE CENTER IN A COLOR CONTRASTING WITH THAT OF THE AISLE SURFACE, PREFERABLY BLUE OR WHITE. ACCESS AISLE MARKINGS MAY EXTEND BEYOND THE MINIMUM REQUIRED LENGTH. CBC SECTION 11B-502.3.3 i. ACCESS AISLES (PARKING SPACES AS WELL – SIMILAR APPLICATION) SHALL NOT OVERLAP THE VEHICULAR WAY. CBC SECTION 11B-502.3.4 j. A VERTICAL CLEARANCE OF 8’-2” MINIMUM SHALL BE PROVIDED FOR ACCESSIBLE PARKING SPACES, ACCESS AISLES, AND VEHICULAR ROUTES SERVING THEM. CBC SECTION 11B-502.5

**END OF SECTION**

32 17 23 - 5 PAVEMENT MARKINGS, STRIPING AND SIGNS

SECTION 32 18 00 MISCELLANEOUS PAVING & SURFACING

PART 1 - GENERAL

1.01 SUMMARY

A. Furnish all labor, materials, equipment, facilities, transportation, and services to install and complete all miscellaneous paving and surfacing and related work as shown on the Drawings and/ or specified herein.

B. Scope of work: The general extent of the miscellaneous paving surfacing is shown on the Drawings and may include, but is not limited to: 1. Sand in Long/Triple jump pits 2. Decomposed Granite Paving at shot put landing sector

C. Related sections can include, but may not be limited to: 1. Section 12 93 00 - Site Furnishings 2. Section 31 20 00 - Earthwork 3. Section 32 11 00 - Base Courses

1.02 REFERENCES AND REGULATORY REQUIREMENTS

A. State of California Department of Transportation Standard Specifications, Current Edition.

1.03 SUBMITTALS

A. Conform to applicable Division One and/or Division Two specifications, General Conditions and Special Provisions.

B. Submit two (2) (unless noted otherwise) one quart samples of the following: 1. Decomposed granite 2. Landing Pit Sand

C. Submit product cut sheets, including source information and recent (within 90 days) gradation testing for the materials outlined in this specification section.

1.04 QUALITY ASSURANCE

A. Materials Source: Sources of materials specified herein shall not be changed during course of work without review and written acceptance by the Owner’s Representative.

32 18 00 - 1 MISC. PAVING & SURFACING

1.05 SEQUENCING AND SCHEDULING

A. Coordinate all applicable subgrade preparations, installations of base course materials and all other work with work of this section to insure a proper, timely installation.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Sand for long / triple jump pits shall be washed sand and #1 plaster sand. Generally, the material shall meet the following gradation and materials properties:

Sieve Size ASTM 144-91 % Passing Spec #4 100 100 #8 95-100 98 #16 70-100 91 #30 40-75 71 #50 10-35 21 #100 2-15 4 #200 0.9

B. Decomposed granite: 1. California Gold fines to be minimum 10% passing #100 sieve and 5% passing #200 sieve. 2. California Gold 3/8” fines for drainage edge at shot put.

C. The above materials can be obtained from FST Sand & Gravel, Corona, California tel.(951) 277-8440, or approved equivalent source.

PART 3 - EXECUTION

3.01 SAND

A. Spread sand to depth specified on Drawings.

B. Rake then roll sand with water roller to establish firm, even surface at specified elevation.

D. Allow material to dry, then spike and mat drag to establish finish grade at

32 18 00 - 2 MISC. PAVING & SURFACING specified elevations.

E. Water to settle.

F. Finish grade of infield and warning track fines shall be flush with concrete edgebands. If edge condition is a tall curb set finish grade to finish grade established on grading plans.

3.02 DECOMPOSED GRANITE

A. Install moisture conditioned granite materials per drawings.

B. Spread evenly and compact in 2 inch lifts in designated areas.

C. Water lightly and compact with roller.

D. Spread additional material, roll and compact to establish even finished grade at specified elevation.

3.03 TOLERANCES

A. Vertical deviation from specified lines, grades, and detail cross sections shall not exceed 0.04 foot for all surfacing specified in this section.

PART 4 - MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

32 18 00 - 3 MISC. PAVING & SURFACING SECTION 32 18 23 VULCANIZED RUBBER TRACK SURFACING

PART 1 - GENERAL

1.01 SUMMARY

A. Furnish all labor, materials, equipment, facilities, transportation, and services to install and complete all miscellaneous paving and surfacing and related work as shown on the Drawings and/ or specified herein.

B. Scope of work: The general extent of the miscellaneous paving surfacing is shown on the Drawings and may include, but is not limited to: 1. “All weather” vulcanized rubber track surface.

C. Related sections can include, but may not be limited to: 1. Section 01 33 00 – Submittals 2. Section 01 78 39 - Project Record Drawings 3. Section 31 20 00 - Earthwork 4. Section 32 11 00 - Base Courses 5. Section 32 12 16 - Asphalt Concrete Paving 6. Section 32 13 13 - Portland Cement Concrete

1.02 REFERENCES AND REGULATORY REQUIREMENTS

A. State of California Department of Transportation Standard Specifications, Current Edition.

B. The work hereunder shall be done and conform to the standards for track construction as described in the following track design and construction guidelines: 1. The NCAA Track and Field Facility Specifications. 2. The American Sports Builders Association Track Construction Manual.

1.03 SUBMITTALS

A. Conform to applicable Division One and/or Division Two specifications, General Conditions and Special Provisions.

B. Submit cut-sheets on all products to be used in this section, including all products’ Material Safety Data Sheets (MSDS). Provide ISO9001 and ISO14001 from the manufacturing facility where the track surface is manufactured.

32 18 23 - 1 TRACK SURFACING C. The Contractor shall prepare a set of computerized calculations and diagrams that shall verify the accurate distance around the track for each lane and each race. All calculations should conform to the NCAA Track and Field Facility Specifications. All standard collegiate races shall be included in the striping. The Contractor shall consult with the District prior to the start of his calculations for determination of the finish line, events to be run, location of lane numbers and additional paint markings. A scaled digital colored drawing showing all track markings shall be provided to the District prior to construction as a submittal for approval. In addition, the approved scaled drawing shall be provided to the District as part of the closeout documents.

D. Submit printed specifications of the synthetic surfacing system that is being installed. Including a required five- (5) year manufacturer's warranty against workmanship, installation and materials on the synthetic surface.

E. Submit four (4) minimum size one quarter square foot (1/4 sq. ft.) sample of the following: 1. Synthetic track surfacing product as specified (including specified colors)

F. Submit an affidavit attesting that the surfacing material to be installed meets the requirements defined in the manufacturers currently published specifications and any modifications outlined in these technical specifications prior to the commencement of any work.

G. A letter signed by an authorized representative of the track surfacer that the track and field surfacing has no measurable traces of heavy metals, leachable mercury, and any other hazardous materials identified by the EPA.

H. Upon completion of all line Markings, the track surface shall submit to the District a certification of accuracy submitted by a Registered Engineer or Surveyor. This document shall state that the track markings and layout meets the NCAA requirements and the requirements of these bid documents.

1.04 QUALITY ASSURANCE

A. The track surface will be applied by a licensed firm, which has successfully installed at least fifteen vulcanized rubber 400 meter tracks as specified in these specifications during the past five (5) years. The contractor shall have a current California Contractor’s license and bond number.

32 18 23 - 2 TRACK SURFACING B. Track surfacing contractor will be required to provide references for a minimum of five (5) similar, successfully executed projects, including current appropriate District contact name and phone number. Successful contractor will provide proof of insurance as well as performance and payment bonds.

C. Installing foreman must have at least five years experience installing this type of track system.

D. All machinery and materials used must be only those approved by the District and the approved manufacturer of the selected synthetic surfacing material.

1.05 SEQUENCING AND SCHEDULING

A. Coordinate all applicable subgrade preparations, installations of base course materials and all other work with work of this section to insure a proper, timely installation.

1.06 SITE CONDITIONS

A. Weather: Surfacing shall not be done when the threat of freezing exists for the following 24 hours, rain is imminent or gusting winds are occurring. Do not apply rubberized topping when base surface temperature is less than 40 degrees F.

B. Site: While surfacing and striping are being done, sprinkler systems must be curtailed, shut off, or controlled so that no water falls on the track or event area surfaces. Other trades and District personnel must stay off the wet or curing surfaces.

C. Provide temporary barriers as required to prevent public entry to construction area and to protect adjacent properties from damage during construction operation. Security is responsibility of the Contractor. Damage that occurs after or before normal work hours is the responsibility of the contractor.

1.07 WARRANTY

A. Provide manufacturers standard 5 year warranty from the project’s Date of Acceptance.

B. The warranty is to be provided directly by the track-surfacing contractor to the District. It is to include the standard company warranty.

C. All material shall be guaranteed to the extent that the surfacing:

32 18 23 - 3 TRACK SURFACING 1. Has been manufactured and applied in accordance with these and the manufacturer's specifications. 2. Will hold fast and/or adhere to the asphalt, concrete, edging, filler and patches or overlay materials. 3. Will perform as specified in these specifications and the specifications of the product manufacturer in the current standard product information literature and specification sheets. 4. Is Ultra-Violet resistant and will not de-laminate, bubble, blister, fade, crack or wear excessively during the guarantee period.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCT AND MANUFACTURER – Shall be procured by the District through a CMAS contract (or equivalent procurement method) direct with the track surfacing company.

A. Product: MondoTrack SX Track Surfacing or equal (no known equal) Available through: Wall2Wall Flooring, an exclusive Mondo supplier Contact: Scott Bohrer, 619-550-7369

2.02 MATERIALS:

A. MINIMUM SURFACE THICKNESS, COLOR AND SHORE HARDNESS `A' MEASUREMENTS 1. Colors: To Be Determined by District 2. Minimum thickness - 13mm 3. Shore hardness A - top layer 50; bottom layer 40

B. The surface shall conform to all slopes and tolerances of the rules of the sport with no deviation in excess of 6mm under a 4m straightedge. The finished surface shall have a flat matte finish.

C. Track product shall be sheet goods material calendered and vulcanized with a base of natural and synthetic rubber, stabilizing agents and pigmentation. Material shall be factory-manufactured in two layers, of different durometer readings, which are vulcanized together.

D. Synthetic surfacing material to be of width and length to minimize joints in all areas. Use lane width synthetic material in lanes with side joints under lane markings and a minimum number of head joints. Use full width material with no side joints in runways. Material must be available in widths up to 6’ to minimize seams in all event areas.

32 18 23 - 4 TRACK SURFACING E. Surfacing material adhesive shall be a two-part polyurethane or epoxy adhesive as recommended and supplied by the synthetic surfacing material manufacturer.

F. Synthetic surfacing material shall conform to the following properties:

Physical Properties Standard Specification Hardness Shore A ASTM Top 50 ± 5 bottom D2240-05 35 ± 5 Tensile Properties IAAF test > 0.5 MPa Strength Elongation at IAAF test > 40% break Coefficient of Friction (wet) IAAF >0.5 V.O.C. Compliance ASTM D5116 Yes G. Synthetic surfacing material shall exhibit a high resistance to track spike traffic, cigarette burns and chemical agents.

H. Material for all cracks and patching shall be an approved material compatible with the specified surfacing. Specified material shall be per the manufacturer's specification.

I. General line markings of the track and field events, shall be spray applied, using only paint, primers and finishes supplied and guaranteed by the approved manufacturer and/or supplier to last a minimum of one year.

PART 3 - EXECUTION

3.01 EXAMINATION & APPLICATION PROCEDURES

A. Prior to the start of installation, verify asphalt concrete paving for dimensional accuracy, strength, surface preparation and planarity. Notify District of any deficiencies.

B. Entire surface shall be clean and free of all dirt, oil, grease or any other foreign matter. It is the responsibility of the surfacing Contractor to thoroughly wash and/or pressure wash all area of the new /and existing asphalt base to ensure adhesion of the track surface.

C. Beginning installation stipulates track installer “accepts” existing conditions. Adhesion to the existing asphalt is the Contractor’s responsibility.

D. Keep all personnel, other than employees of track installer, 300 feet from equipment and workers.

32 18 23 - 5 TRACK SURFACING E. Refer to Specification Section 01 07 00 for track pavement and surfacing tolerances and grade conformance requirements.

3.02 INSTALLATION REQUIREMENTS

A. Prior to track surfacing installation, all track field event in-ground equipment identified in the project documents shall be installed as per the manufacturer's specifications and IAAF / NCAA rules. Track surfacing material shall be installed on top of pole-vault box covers, sand pit covers and take-off boards.

3.03 TRACK INSTALLATION

A. Comply with manufacturer's written installation instructions.

B. Track and field surface to be unrolled and allowed to relax

C. Must use manufacturer approved adhesive to adhere synthetic track and field surface to sub-base.

D. Cut and adjust synthetic track and field surface prior to adhesion.

E. Width: Synthetic track and field surface material to be of width and length to minimize joints in all areas. 1. Use lane width synthetic track and field surface for running lanes with side joints under lane markings and a minimum number of head joints. Use full width material with no side joints in runways. 2. In D-area at throwing area and high jump use widest material available from manufacturer for the fewest number of seams possible. F. Use heavy objects such as bricks to hold seams in place until adhesive has fully cured.

3.04 TIMING, LIMITATIONS, AND CONDITIONS AFFECTING INSTALLATION

A. Weather and Climate: Comply with synthetic track and field surface manufacturer’s requirements for temperature, humidity and all other environmental conditions for storing and installing material. 1. If it is the opinion of the synthetic track and field surface manufacturer that weather and climatic condition have or will cause an adverse effect on installation work shall be delayed until conditions have improved.

B. Adjacent and Concurrent Construction: Installation shall not take place until the completion of adjacent or concurrent construction operations which generate dust, airborne abrasives, or any other by-product that, in

32 18 23 - 6 TRACK SURFACING the opinion of the Owner or synthetic track surfacing manufacturer, would be harmful to the track material.

3.05 CLEANING AND PROTECTING

A. Perform the following operations immediately after completing flooring installation: 1. Remove adhesive and other blemishes from flooring surfaces. 2. Sweep and vacuum flooring thoroughly. 3. Damp-mop flooring to remove marks and soil after time period recommended in writing by manufacturer.

B. Protect flooring from mars, marks, indentations, and other damage from construction operations and placement of equipment and fixtures during remainder of construction period. Use protection methods recommended in writing by manufacturer. 1. Do not move heavy and sharp objects directly over flooring. Protect flooring with plywood or hardboard panels to prevent damage from storing or moving objects over flooring.

3.06 LINE MARKINGS, STRIPING, AND RACE MONUMENTATION

A. General line markings of the track and field events shall be spray applied, using only paint, primers and finishes supplied and guaranteed by the approved manufacturer and/or supplier to last a minimum of one year.

B. All markings shall be spray applied under the direction of a qualified line marker, having marked a minimum of 20 track and field facilities, which meet the IAAF or NCAA rules and regulations. The line marker shall be approved by Mondo and experienced in the layout of track and field markings.

C. All markings shall be in accordance with the rules of the NCAA and shall be certified for accuracy.

D. The track surfacer shall submit a certification of accuracy prepared by a registered Engineer or Surveyor. The Engineer or Surveyor shall certify the actual line markings on the facility, not the line markers drawings or computations. Track markings and layout must meet NCAA requirements and the requirements of the drawings and specifications.

E. The track surfacer shall submit a certification of accuracy prepared by the registered Engineer or Surveyor. The Engineer or Surveyor shall certify the actual line markings on the facility, not the line markers drawings or

32 18 23 - 7 TRACK SURFACING computations. The track markings and layout must meet NCAA requirements and the requirements of the drawings and specifications.

F. Calculations shall be made to the nearest 1/100th of a foot.

G. Angles shall be set by using a transit or theodolite capable of reading direct to 20 seconds.

H. Measurement shall be made with a steel tape in engineering scale.

I. Markings shall be clearly identified and color-coded.

J. Track Surfacer shall provide the following markings to comply with NCAA event striping requirements: 1. All lane lines, start lines and common finish line, event markings, five sets of lane numbers, and runway borders, as noted below. 2. 100 meters One direction on home straight 3. 100 meter hurdles One direction on home straight 4. 110 meter hurdles One direction on home straight 5. 200 meters All in lanes, one turn 6. 400 meters All in lanes 7. 400 meter hurdles All in lanes 8. 800 meters Water fall start and 1-turn stagger 9. 1500 meters Water fall start 10. 3000 meters Water fall start 11. 3000 meter steeplechase Water fall start 12. 5000 meters Water fall start 13. 10 000 meters Water fall start 14. 400 meter relay (4 x 100 meters) All in lanes 15. 1600 meter relay (4 x 400 meters)All in lanes (3 turn stagger) 16. Shot Put and Discus events Paint Dividing lines 17. Shot Put, Discus, and Javelin Paint Sector lines (not circle or on runway) 18. Javelin Paint foul line, beginning of Sector lines, radius pt. 19. Pole vault, long jump, triple jump and Javelin Paint runway lines 20. Common Finish Line Paint to current NCAA rule book with intersections of lane lines and finish line painted black 21. Lane numbers Paint beyond the common finish line, facing timing camera/device 22. International Zones As per current NCAA rule book 23. Break lines for distance events At entry of back and main straights 24. Group starts for distance events Waterfall start lane 5 through 8 25. Assembly lines for waterfall starts Three meters before waterfall start

32 18 23 - 8 TRACK SURFACING 26. Sprint Medley Relay (200, 200, 400, 800 meters) 3 turn stagger 27. Distance Medley Relay (1200, 400, 800, 1600 meters) 28. 3200 meter relay (4 x 800 meters) 29. 6000 meter relay (4 x 1500 meters) 30. 1 mile run Waterfall start 31. Starting line (white): 100m, 100mh, 110mh, 200m, 400m, 1500m, 3000m, 3000m Steeplechase, 5000m, 10 000m 32. Starting line (white with green insert): 800m, one-turn stagger 33. Starting line (white with red insert): 800m relay, four-turn stagger 34. Starting line (white with blue insert): 1600m relay, three-turn stagger 35. Finish line (white): all 36. Relay exchange zones: 400m relay (yellow), 800m relay (red), 1600m relay (blue) 37. Hurdle locations: 100m (yellow), 110m (blue), 400m (green), 3000m steeplechase (black) 38. Break line: (green)

3.04 FINAL CLEANUP

A. Contractor shall be responsible for removing all discarded product containers, unused and excess material.

B. Paint over spray to adjacent surfaces outside the track dimensions shall be removed by the Contractor. All existing surfacing shall be returned to an as-was or better condition once the project site is vacated and prior to the Notice of Acceptance.

PART 4 - MEASUREMENT AND PAYMENT

4.01 Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

32 18 23 - 9 TRACK SURFACING SECTION 32 31 13

CHAIN LINK FENCES AND GATES PART 1 GENERAL

1.01 SUMMARY

A. Section Includes:

1. Chain link fences and gates as indicated.

B. Related Requirements:

1. Division 01 - General Requirements.

2. Section 31-22-00 - Grading.

3. Section 32-131-3 – Concrete Paving.

1.02 SUBMITTALS

A. Shop Drawings:

1. Submit plans and details indicating extent of fences, locations of gates, and details of attachment and footings. Indicate means and methods for surface preparation and finishing.

1.03 QUALITY ASSURANCE

A. Chain Link Fence Manufacturers Institute: CLFMI Product Manual.

B. ASTM A123: Specification for Zinc (Hot-Dipped Galvanized) Coatings on Iron and Steel Products.

C. ASTM A392: Specification for Zinc-Coated Steel Chain Link Fence Fabric. ASTM F567: Practice for Installation of Chain Link Fence.

D. ASTM F626: Specification for Fence Fittings.

E. ASTM F668: Specification for Poly(Vinyl Chloride) (PVC) and Other Organic Polymer- Coated Steel Chain Link Fence Fabric.

F. ASTM F900: Specification for Industrial and Commercial Swing Gates.

G. ASTM F1083: Specification for Pipe, Steel, Hot-Dipped Zinc-Coated (Galvanized) Welded, for Fence Structures.

32-31-13-1 CHAIN LINK FENCES AND GATES

H. ASTM F1184: Specification for Industrial and Commercial Horizontal Slide Gates.

I. ASTM F1553: Guide for Specifying Chain Link Fence.

PART 2 PRODUCTS

2.01 MATERIALS

A. Concrete Materials and Properties: Concrete to provide normal-weight, air-entrained concrete with a minimum 28-day compressive strength of 3,000 psi, 4-inch slump, and one inch maximum size aggregate. 1. Concrete may be provided in the following volumetric proportions: Portland Cement 1 part Fine Aggregate 2 parts Coarse Aggregate 4 parts (1/4 inch to 1-1/2 inches) Water 7 ½ gallons, maximum per sack of cement B. Chain Link Fence Fabric: Conforming to ASTM A 392, Class C2 zinc coating, 2.00 ounces minimum per square foot of uncoated wire surface, hot-dipped galvanized after , and top and bottom edges knuckled.

1. Fabric for perimeter fencing and interior fencing shall be 9 gage woven wire with 2 inch mesh, unless otherwise specified.

2. For perimeter fences 16 feet high, the upper 8 feet of fabric may be 11 gage.

3. Fences 12 feet high or less shall be furnished with single width fabric.

4. Installed fence fabric shall be free from barbs, icicles, or other projections and installed fence fabric with such defects will be deemed defective Work.

C. Posts, Top Rails, Brace Rails and Gate Frames: Standard weight, galvanized, welded or seamless steel pipe conforming to ASTM F 1083, with a minimum yield strength of 35,000 psi. Embed posts into footing 6 inches less than the depth of the footing unless noted otherwise on drawings.

D. Schedule of Posts and Footings:

Item Height Nomina Outside Weight Footings* l Pipe Diameter (pounds Diameter Depth Size (inches) per foot) (inches) (inches) (inches) Top Rail, Brace Rails Up to 10’-0” 1-1/4 1.660 2.27 N/A N/A and Transom Rails 10’-1” to 16’-0” 1-1/2 1.900 2.72 N/A N/A Up to 6’-0” 2 2.375 2.65 12 24 Line Posts 6’-1” to 8’-0” 2 2.375 2.65 12 36

32-31-13-2 CHAIN LINK FENCES AND GATES

Item Height Nomina Outside Weight Footings* l Pipe Diameter (pounds Diameter Depth Size (inches) per foot) (inches) (inches) (inches) 8’-1” to 10’-0” 2-1/2 2.875 5.79 12 36 10’-1” to 16’-0” 3 3.5 7.58 14 60 Up to 8’-0” 2-1/2 2.875 5.79 12 36 Terminal, Corner, 8’-0” to 10’-0” 2-1/2 2.875 5.79 14 42 Angle & Pull Posts 10’-1” to 16’-0” 3 3.5 7.58 14 60 Pedestrian Gate Posts Up to 8’-0” 2-1/2 2.875 5.79 14 36 Gate Frames Up to 8’-0” 1-1/2 1.900 2.72 N/A N/A

Up to17'-3-1/2" Up to 8’-0” 3 1/2 4 9.11 16 42 17'-4" to 20'-3-1/2" Up to 8’-0” 3-1/2 4 9.11 16 42 E. Post Caps: Malleable iron, ASTM F 626, , designed to fit snugly over posts with a minimum projection of 1-1/2 inches below top of posts. Post caps shall be manufactured with a curved top.

F. Eye Tops: Malleable iron, ASTM F 626, , designed to fit over line posts, and for through passage of top rail.

G. Expansion Sleeve Couplings for Top Rails: Steel, 6 inches long, designed to fit tightly on inside of rail, fitted with raised center.

H. Rail Ends for Top Rails and Brace Rails: Malleable iron, ASTM F 626, , with holes to receive 3/8 inch bolts for securing to rail end bands.

I. Tension Bands and Bands for Securing Rail Ends: Mild steel flats, at least 11 gage x one inch, tension bands in gates shall be 11 gage by 1 inch. Bolts for use with tension bands and rail end bands shall be 3/8 inch by 1 ½-inch.

J. Tension Bars: Mild steel flats at least 3/16 inch by 3/4 inch.

K. Tension Wire for Installation at Bottom of Fabric: 6 gage steel spring wire, conforming to requirements of AISI Steel Products Manual, Carbon Steel Wire, Section 16, merchant quality, galvanized, soft temper with Type I coating. Wavy type wire is not acceptable.

L. Turnbuckles for installation with Tension Wires: Eye and hook type, drop forged steel, right and left hand threads, at least 3/8 inch screw diameter with at least 4 ½-inches of take-up.

M. Tie Wire: Aluminum ties 6 gage for fastening fabric to posts, top rails and brace rails. At bottom tension wire 9 gage galvanized hog rings shall be installed.

N. Finish of Metal Parts: Post caps, couplings, rail ends, tension bands, tension bars, turnbuckles, rivets, bolts, and other metal parts and fittings shall be hot-dipped galvanized

32-31-13-3 CHAIN LINK FENCES AND GATES

after fabrication, except bolts, which may be galvanized or cadmium-plated. Galvanizing shall conform to ASTM A123 Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products, and ASTM F 626Specification for Fence Fittings.

O. Paints for Refurbishing Existing Fence Posts, Rails, and Accessories: As required to provide the galvanized color of a new installation.

PART 3 EXECUTION 3.01 INSTALLATION A. Install fences to heights indicated on Drawings.

B. Space fence posts at equal intervals between terminal, angle, corner, and gate posts, and not more than 10 feet apart measured from center to center of posts. In curved fence sections having a radius of 50 feet or less, space posts not more than 5 feet - 6 inches apart. Install posts so that top of eye of post caps are level with top of fabric.

C. Install angle or corner posts at each change in direction of 15 degrees or more, at change of 5 percent or more in grade of fencing, and at the beginning and end of curved fence sections.

D. Install terminal posts at ends of runs of fencing. Install gateposts on both sides of driveway and pedestrian gates. For double-leaf gates, net opening between gate posts shall be gate size as indicated on Drawings, plus 3 ½-inches; for single leaf gates, net opening shall be gate size plus 2 ½-inches.

E. Where a fence is to be installed on a curb, construct footings with top of footing level with the lower finish grade. Align posts, set plumb and true before placing footings. Remove splattered concrete from exposed pipe surfaces while concrete is still soft. In bituminous surfaced areas, install seal coat on top of concrete footings.

F. Install fences with top rail. Top rail shall pass through eye tops and be secured at ends with rail-end fittings and bands.

G. Install fences over 10 feet in height, in addition to top rail, with a full length horizontal mid- rail set at mid-height of fence and rigidly secured to posts with rail end fittings and bands.

H. In fences higher than 10 feet, install brace rails at angles, corners, and terminals at 1/4 and 3/4 of fence height. Provide one horizontal brace rail in panels adjacent to terminal, angle, corner, and gateposts, install at mid-height of fence and rigidly secured to posts with rail end fittings and bands. Provide horizontal brace rails, as specified, in panels of curved sections having a radius of 50 feet or less. Brace rails are not required in fencing 4 feet or less in height.

I. Provide a transom rail and fabric at top of pedestrian gate openings. Install transom rail 6 feet 8 inches above high point of grade at gate opening. Ends of transom rails shall be pinned or riveted to rail end fittings with 1/4 inch mild steel rivets. Pin or rivet must go through rail and peen. Welding on rail ends is not permitted.

32-31-13-4 CHAIN LINK FENCES AND GATES

J. Install bottom tension wire a minimum of 3 inches from grade for fencing, and provide a turnbuckle for each 150 feet of wire or fractional part thereof. Turnbuckles are not required in runs of 15 feet or less. Install ends of tension wires to posts in a manner to prevent slipping or loss of tension. Wrap should start from fence side of post. Turn end of wire around post tightly twisted at least three times around wire. At turnbuckles, wire through eye and tightly twist end at least three times around wire. Cut tail of bottom wire flush.

K. Install fence fabric on outward facing side of posts, except for tennis courts. Install fence fabric with top edge projecting above top rail of fence.

L. Install bottom of fence fabric to clear finish grades, except on bituminous surface install 3/4 inch above such surface. Locally shape and trench ground surfaces where necessary to provide uniform top and bottom alignment of fence.

M. Tightly stretch fabric and at terminal, pull corner, angle, and gateposts, secure with tension bars extending full height of fence. Secure tension bars to posts with bolted tension bands spaced not more than 14 inches apart.

N. Bands and Ties: Install bands and ties in accordance with following schedule:

15 bands on 16 feet fence 16 ties on 16 feet fence

11 bands on 12 feet fence 12 ties on 12 feet fence

7 bands on 8 feet fence 7 ties on 8 feet fence

6 bands on 6 feet fence 6 ties on 6 feet fence

4 bands on 4 feet fence 4 ties on 4 feet fence

O. Fasten fabric to line posts with wire ties spaced not more than 16 inches apart. Where 6 gage aluminum ties are furnished, hook the tie at both ends. Installation of hooked ties with links is not permitted. P. Fasten fabric to top rails, mid-rails, brace rails, with wire ties spaced not more than 18 inches apart. Bend back ends of tie wires so as not to be a hazard. At bottom tension wire, install hog rings spaced not more than 18 inches apart. Where 2 fabrics are furnished, lap the fabrics one mesh at mid-rail and tie both fabrics with 9 gage wire or 6 gage aluminum ties to midrails. Q. Grind all field welds smooth, clean off flux and spatter, damaged galvanizing removed, burrs and projections ground off, properly prepared, then heavily coated with galvanizing repair coating as specified in Section 05 5000; or equal product approved by Owner’s Office of Environmental Health and Safety. Install coating in accordance with written recommendations of manufacturer.

R. Fabrication of Gates:

32-31-13-5 CHAIN LINK FENCES AND GATES

1. Frames: Fabricate gate frames from steel pipe of size specified, with joints at corners miter cut and continuously welded to sides.

2. Fabric: Install fence fabric to side members with tension bars and tension bands as specified, spaced not more than 14 inches apart. Tension bars shall extend full height of gate. Install fence fabric to top and bottom members and to brace rail with wire ties as specified for top rails, spaced not more than 12 inches apart.

3. Latches: Gate latches and strikes will be furnished by the Contractor. Weld gate latches and strikes to gate posts and frames. Welding shall be performed before gate frames are galvanized, or welds shall be finished as specified for field welds.

4. Hinges: Install and adjust hinges; burr or center punch threads of gate hinge bolts to prevent removal of nuts. Install 3 hinges on each post for swing gates more than 16 feet wide. Hinges will be provided by the Contractor.

5. Grind welds flush and smooth. Hot-dip galvanize fabricated parts after welding, or finish weld as specified for field welds.

S. Gate Posts: Fabricate members from round hot-dipped galvanized steel pipe with inside dimension and weight according to Table 2 for the gate leaf widths required.

1. All gate posts shall be of sufficient strength so that the total deflection of the gate and the post at the end of the gate leaf shall not exceed the lesser of 2% of the gate leaf width or 4 inches.

2. When necessary to meet this requirement due to the total weight of the gate leaf, the next larger size posts required shall be used. Gates shall not be equipped with rollers or casters for support, unless indicated in the drawings.

Table 2 Swing gate member sizes Gate opening Nominal size lb/ft. Single leaf to 6 feet 2 1/2" 5.79 Double leaf to 12 feet opening Single leaf 6 to 13 feet 3 1/2" 9.11 Double leaf 12 to 26 feet opening Single leaf 13 to 18 feet 6" 18.97 Double leaf 26 to 36 feet opening

T. Hardware: Latches permitting operation from both sides of gate, heavy-duty offset hinges, center gate stops and, for each gate leaf more than 5 feet wide, keepers. Fabricate latches with integral eye openings for padlocking; padlock accessible from both sides of gate.

32-31-13-6 CHAIN LINK FENCES AND GATES

1. Provide means of padlocking gates in the open position where indicated that gate must be locked in open position during activity hours.

2. In addition to bolts, spotweld hinges and latches to posts.

3. All screws and bolts shall be tamper-proof.

4. Chains: Provide each gate with 3-foot length of chain to secure gate to fence with a padlock when open. Install ¾ inch round eye, cadmium plated harness snap on one end of chain. Secure chain and district supplied lock with spotweld.

5. Gates shall swing a minimum of 180 degrees.

6. Single latches shall be industrial gravity type gate latch with automatic stop.

7. Double latch shall be drop bar one-inch inside diameter by 1.68 lb/ft nominal pipe size securely bolted to gate frame and shall engage an iron gate stop. Drop bar shall engage 1-½” by 2.73 lb/ft. inside pipe diameter pipe sleeve set in concrete. Provide drop bar keeper on gate to secure it in lifted position.

a. Omit latch and make provisions to receive exit device hardware where gate is part of the egress system.

b. Provide 16 gage steel plate for mounting of exit device on gate and exit device latch on post. Size plate to protect against unauthorized operation of the exit device from the exterior as shown.

3.02 FENCING ADJUSTMENTS A. Where the finish grade is raised 6 inches or less, cut and re-knuckle the existing fence fabric. Adjust tension wire and tie to fabric. Bottom of fence fabric shall be installed ¾” above finish grade.

B. Where the finish pavement is lowered 6 inches or less, demolish the fence footing flush with the finish grade and adjust the fabric and its attachments. Bottom of fence fabric shall be installed ¾ inches above finish grade.

C. Post footings and fabrics that require readjustment after installation shall be entirely replaced. 3.03 INSTALLATION OF GATES A. Provide gates of the sizes indicated on Drawings. Allow clearance on gates of 1-1/2 inches at bottom and one inch at top. Construct gates installed in sloping areas to conform to the grade. Provide an opening in each gate for access to locking device or padlock. Knuckle ends of fabric cut for opening to eliminate hazards.

B. Sliding Gates and Swing Barricade Gates: Fabricate and install as indicated on Drawings. Wheel housing must be designed to fit tightly to roll track and prevent gate from rolling

32-31-13-7 CHAIN LINK FENCES AND GATES

over objects. Unsupported cantilever type roll gates are not acceptable. Install gate stops in accordance with the drawings. Both top and track stops are required. 3.04 COMPLETION A. Completed fencing shall form continuous units between points indicated with required parts, accessories, and fittings provided and installed. Clean exposed metal surfaces of cement, grout and other foreign substances.

B. Fill in holes left by removal of existing fence footings, except in areas where grading Work is indicated or specified, to existing grade with clean earth thoroughly compacted to at least same density as adjoining soil. 3.05 PROTECTION A. Protect the Work of this section until Substantial Completion. 3.06 CLEANUP A. Remove rubbish, debris and waste materials and legally dispose of off the Project site.

**END OF SECTION**

32-31-13-8 CHAIN LINK FENCES AND GATES

SECTION 32 81 00 IRRIGATION SYSTEM

PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections, apply to work of this section.

1.02 REQUIREMENTS:

A. All work and materials shall be in accordance with the uniform plumbing code published by the Western Plumbing officials association, all state and local codes and regulations. Should the construction documents or instructions be at variance with the aforementioned rules and regulations, notify the municipal water district and await their instructions before proceeding with the work effected.

B. Manufacturer's directions: Manufacturer's directions and detailed drawings shall be followed in all cases where the manufacturer or articles used in this contract furnish directions covering points not shown in the drawings and specifications.

C. Manufacturer's Warranties: Manufacturer's warranties shall not relieve liabilities under guarantee.

D. All work called for on the drawings by notes shall be furnished and installed whether or not specifically noted in the specifications. Do not willfully install the sprinkler system as indicated on the drawings when it is obvious in the field that unknown obstructions or grade differences exist that might not have been considered in the irrigation design, or if discrepancies in the construction details, legend, or specific notes are discovered. All such obstructions or discrepancies shall be brought to the attention of the Landscape Architect. In the event that this is not done, the Contractor shall assume full responsibility for the necessary revisions.

E. Due to the scale of drawings, it is not possible to indicate all offsets, fittings, sleeves, etc. which may be required. The Contractor shall carefully investigate the structural and finished conditions affecting all of his work and plan his work accordingly, furnishing such fittings, etc., as may be required to meet such conditions. Drawings are generally diagrammatic and indicative of the work to be installed. The work shall be installed in such a manner as to avoid conflicts between irrigation systems, planting and architectural features.

1.03 PROTECTION AND DAMAGE

A. Protect work and materials from damage during construction and storage. PVC pipe and fittings shall be protected from direct sunlight.

32 81 00 - 1 IRRIGATION SYSTEM B. Assume all responsibility for damage to existing construction and restore to its original condition should damage occur as a result of this work.

C. Contractor shall securely cover openings into system and cover apparatuses, equipment, and appliances both before and after being set in place to prevent obstruction in the pipes and prevent breakage, misuse, or disfigurement of the apparatuses, equipment or appliances.

1.04 DESCRIPTION OF WORK

A. The work consists of furnishing labor, tools, machinery, materials, and processes required to complete the sprinkler irrigation system described herein and shown on the drawings.

B. The intent of the drawings and specifications is to indicate and specify a complete sprinkler system, installed ready for use without further cost in labor or materials to the Owner.

1.05 QUALITY ASSURANCE

A. Subcontract work to a single firm specializing in irrigation work. Contractor shall possess all licenses and permits required to perform the work of this contract including a C-27 landscaping license.

1.06 SUBMITTALS

A. The Contractor shall furnish the articles, equipment, materials or processes specified by name in the drawings and specifications. No substitution will be allowed without prior written approval by the Landscape Architect, or the Owner's authorized representative.

B. The Contractor shall submit to the Landscape Architect catalog data and full descriptive literature for approval of items different than those specified.

C. Equipment or materials installed or furnished without the prior approval of the Landscape Architect may be rejected and the Contractor may be required to remove such materials from the site at his own expense.

D. Approval of any item, alternate or substitute indicates only that the product(s) apparently meet the requirements of the drawings and specifications on the basis of the information or samples submitted.

E. Manufacturer's warranties shall not relieve the Contractor of his liability under the guarantee. Such warranty shall only supplement the guarantee.

1.07 GUARANTEE:

32 81 00 - 2 IRRIGATION SYSTEM

A. Furnish guarantee in accordance with the General Conditions, for a period of one (1) year from the date of final acceptance - at the conclusion of the Maintenance Period - on complete water irrigation system, including non-settling of the backfill in trenches, which, if occurs, shall be corrected, including repairs and/or replacement of any material damaged thereby or there from.

B. Manufacturer's warranties shall not relieve the Contractor of his liability under the guarantee. Such warranty shall only supplement the guarantee.

PART 2 PRODUCTS

2.01 MATERIALS

A. Pressure Pipe: Comply with following:

B. PVC Plastic Pressure Lines: For piping upstream of remote control valves and quick couplers. All two (2) inches and larger shall be Class 315 Polyvinyl Chloride (PVC) Simpson or approved equal. All one and one-half (1-1/2) inches and smaller shall be Type I, Grade 2, designated as PVC 1220, Schedule 40.

C. Non-pressure Pipe: (downstream from remote control valves): Comply with following:

D. Plastic Non-Pressure Lines: For piping downstream of remote control valves, Type 1, Grade 2 (Impact Modified), as designated as PVC 1220, Class 200, (SDR21), conforming to Commercial Standards CS256-63.

E. Pipe sleeves shall be PVC schedule 40.

F. Identification: Furnish plastic pipe continuously and permanently marked with following information: Manufacturer's name or trade mark, size, class and type of pipe, working pressure at 73.4 degrees F., and National Sanitation Foundation (NSF) rating.

G. Pipe Fittings and Connections: Comply with following:

2.02 FITTINGS AND CONNECTIONS

A. Polyvinyl Chloride Pipe Fittings and Connections: Type II, Grade 1, Schedule 40, high impact molded fittings, manufactured from virgin compounds as specified for piping tapered socket or molded thread type, suitable for either solvent weld or screwed connections. Machine threaded fittings and plastic saddle and flange fittings are not acceptable. Furnish fittings permanently marked with following information: Nominal pipe size, type and schedule of material, and National Sanitation Foundation (NSF) seal of approval. PVC fitting shall conform to ASTM D2464 and D2466.

32 81 00 - 3 IRRIGATION SYSTEM

B. All PVC threaded nipples shall be standard weight Schedule 80 with molded threads and shall conform to ASTM D1785:

C. Triple Swing Assembly shall be made of hi-impact type II material with EPDM O’rings, pressured rated to 315 PSi. King Bros. or approved equal.

D. Solvent cements shall comply with ASTM D2564. Socket joints shall be made per recommended procedures for joining PVC plastic pipe and fittings with PVC solvent cement by the pipe and fitting manufacturer and procedures outlined in the Appendix of ASTM D2564.

E. Thread lubricant shall be Teflon ribbon-type, or approved equal, suitable for threaded installations as per manufacturer’s recommendations.

F. VALVES: Manufacturer’s standard, of type and size indicated, and as follows:

G. Remote control valves shall be of the manufacturer size, and type indicated on the plans. Valve shall be operable manually without electricity.

H. Ball and Gate valves shall be of the manufacturer size, and type indicated on the plans.

2.03 SPRINKLER HEADS

A. Sprinkler heads shall be of the types and sizes with diameter (or radius) of throw, pressure, nozzle discharge and/or other designations indicated on the drawings. All sprinkler heads of the same type and size shall be of the same manufacturer.

2.04 VALVE BOXES:

A. For remote control valves: green standard 12” nom. plastic valve box shall be manufactured by ARMOR (PART# 170106)

2.05 AUTOMATIC CONTROL WIRE:

A. Electric wiring runs from Timers to the automatic control valves shall be solid, single conductor, copperwire, 4/64 in. insulation, 4/64 in. neoprene jacket, Style DB (Direct Burial) or equal, color code wires to each valve, common wire shall be black. Wires shall conform to federal specification JC-30.

PART 3 EXECUTION

3.01 SYSTEM DESIGN

A. All scaled dimensions are approximate. The Contractor shall check and verify all

32 81 00 - 4 IRRIGATION SYSTEM

dimensions on the site prior to proceeding with work under this Contract.

B. The Contractor shall locate and mark all existing utilities such as power, telephone, domestic water, water, and tile drains. Extreme care shall be taken by the Contractor when excavating or working in these areas, and coordination and cooperation between the Owner's representative and the Contractor is required as the work progresses to the area. Contractor shall give 24 hours notice to representative as work progresses of underground utility areas. Contractor shall be responsible for damage to any utilities.

C. Should utilities not located or marked be found during excavation, the Contractor shall promptly notify the Owner and shall discontinue with work in the area, except for necessary emergency work, to repair or prevent damage until instructions are given to the Contractor by the Owner's representative.

D. Failure to notify the Owner of discovery of such utilities or damage thereto will result in the Contractor being liable for any and all damage caused to the utilities as a result of his actions.

E. The Contractor shall, before starting work on the sprinkler system, carefully note all finish grades in order to satisfy himself that he may proceed with the work, and to restore finish grades to original contours before completion.

F. The installation of all irrigation materials, including pipe, shall be coordinated with the landscape drawings to avoid interfering with the trees, shrubs, or other planting.

G. Lay out sprinkler heads and make any minor adjustments required due to difference between site and drawings. Any such deviations in layout shall be within the intent of the original drawings, and without additional cost to the Owner. When directed by the Owner, the layout shall be approved before installation.

H. Do not willfully install the irrigation system as indicated on the drawing when it is obvious in the field that previously unknown obstructions or grade differences exist, that might not have been considered in the engineering. Such obstructions or differences should be brought to the attention of the Landscape Architect.

I. Water Supply: The Contractor shall connect to the water source as indicated on the drawings. The Contractor shall verify static pressure as stated on the plans prior to beginning work. If static pressure or point of connection differ from that shown on the plans, the Contractor will promptly notify Landscape Architect before starting work.

J. Workmanship and Procedure: The routing of the pressure supply lines as indicated on the drawings is diagrammatic. Locate all pressure supply lines in planting areas. Cross perpendicular under pavement in a sleeve as described in these specifications.

32 81 00 - 5 IRRIGATION SYSTEM

3.02 INSTALLATION

A. General: Unless otherwise indicated, comply with requirements of Uniform Plumbing Code.

B. Excavation of Trenches: Excavate trenches, prepare subgrade, and backfill to line and grade with sufficient room for pipe fittings, testing and inspecting operations. Do not backfill until the pipe system has been subjected to a hydrostatic test as specified.

C. Depth of Trench:

Polyvinyl Chloride Pressure Line 18" min. Polyvinyl Chloride Non-Pressure Line 12" min.

D. Subsoil shall be free of all rocks over one (1) inch diameter, debris, and litter prior to use as backfill.

E. Repair any leaks and replace all defective pipe or fittings until lines meet test requirements. Do not cover any lines until they have been checked and approved for tightness, quality of workmanship and materials.

F. Backfill trenches, after approval of piping, with suitable and approved material, tamping soil around pipe and thoroughly compacting all trench fills until 90% compaction has been achieved.

G. Backfill material shall be an approved soil, free from rocks and clods. Provide backfill under, around and above top of pipe for PVC plastic pipe and brass piping.

H. Pipes installed in common trench shall have a 4” minimum space between pipes.

I. Installation of Polyvinyl Chloride Pipe:

1. Because of the nature of plastic pipe and fittings, exercise caution in handling, loading and storing, to avoid damage.

2. The pipe and fittings shall be stored under cover until using, and shall be transported in a vehicle with a bed long enough to allow the length of pipe to lay flat so as not be subjected to undue bending or concentrated external load at any point.

3. Any pipe that has been dented or damaged shall be discarded unless such dent or damaged section is cut out and pipe rejoined with a coupling.

4. Trench depth shall be as specified above from the finish grade to the top of the pipe. The bottom of the trench shall be free of rocks, clods, and other sharp-edged objects.

32 81 00 - 6 IRRIGATION SYSTEM

5. Pipe ends and fittings shall be wiped with "MEK" primer, or approved equal, before welding solvent is applied. Welded joints shall be given a minimum of 15 minutes to set before moving or handling. All field cuts shall be beveled to remove burrs and excess material before fitting and gluing together.

6. Pipe shall be snaked from side-to-side of trench bottom to allow for expansion and contraction.

7. Center load pipe with small amount of backfill to prevent arching and slipping under pressure. Leave joints exposed for site observation during testing.

8. No water shall be permitted in the pipe until site observation has been completed and a period of at least 24 hours has elapsed for solvent weld setting and curing.

9. Plastic to metal joints shall be made with plastic male adapters, metal nipple hand tightened, plus one turn with a strap wrench.

10. All threaded Plastic to Plastic connections shall be assembled using Teflon tape.

11. Solvent-Weld Joints: Assemble per manufacturer's recommendations.

12. Pipe sleeve under existing or future paving shall be installed prior to paving or re-paving and shall extend 12” beyond each side of paving edge. Sleeve shall be a minimum of two times than pipe or wire bundle it encloses. Install only one pipe per sleeve.

J. Remote Control Wiring:

1. Direct Burial Control Wire Sizes: As shown and specified herein before.

2. Provide one control wire and one common ground wire to service each valve in system. Provide 4 foot minimum expansion loop at each valve to permit removal and maintenance of valves.

3. Control Wire Splices: Allow only on runs of more than 300-feet, splices as follows:

a. Strip off minimum of 2-1/2" of insulation from each wire.

b. Twist on Scotchlok electrical spring connector, minimum four complete turns.

32 81 00 - 7 IRRIGATION SYSTEM

c. Seal connector in epoxy resin.

d. Tape completed splice with Scotch 33 electrical tape.

e. Numbering and Tagging: Identify direct burial control wires from automatic valves to terminal strips of controller at terminal strip by tagging wire with number of connected valves.

K. Remote Control Valves

1. Install remote control valves in locations approximately as shown on the drawings, with a cover of 8 inches minimum over top of flow control stem. Fit with plastic valve box and cover.

L. Valve Box

1. Install valve boxes as shown on detail. Install no more than one valve per box. Valve boxes shall be located in shrubs areas wherever possible.

M. Sprinkler Heads

1. All sprinkler heads shall be installed as per details shown.

2. Nozzle size of all heads shall be adjusted to suit any particular conditions of the area. This shall be done after the system has been thoroughly tested, immediately after written notification by the Landscape Architect to do so.

N. Ball and Gate Valves

1. Install approximately where shown and as detailed. Fit with plastic valve box and cover.

O. Check Valves

1. Unless designed as an integral part of the irrigation head, anti-drain valves will be installed under every head. The anti-drain valve will be the same diameter as the riser and integral to the riser assembly.

3.03 FLUSHING AND TESTING OF SYSTEMS:

A. After piping and risers are in place, but prior to the installation of the sprinkler heads, a full head of water shall be used to flush out the system. After system is thoroughly flushed, cap all risers:

32 81 00 - 8 IRRIGATION SYSTEM

B. Testing

1. General: Notify Landscape Architect in writing when testing will be conducted. Conduct tests in presence of Landscape Architect.

C. Pressure Test

1. All pressure lines shall be tested under hydrostatic pressure of 125 lbs. per square inch and all non-pressure lines shall be tested under the existing static pressure and both be proven watertight. (Contractor to supply all equipment needed for testing.) .

2. Pressure shall be sustained in the lines for not less than four hours. If leaks develop, the joints shall be replaced and the test repeated until the entire system is proven watertight.

3. Tests shall be observed and approved by the Landscape Architect and/or Owner prior to backfill. Backfilling trenches prior to inspection will not be allowed and all prematurely filled trenches shall be subject to reopening as directed by the Landscape Architect.

4. Coverage Testing: Perform operational testing after hydrostatic testing is completed, backfill is in place, and sprinkler heads adjusted to final position:

5. After completion of landscape work, carefully adjust heads so they will be flush with lawn areas or not more than 1/2" above finish grade or top of mulch in groundcover area.

3.04 SITE OBSERVATION VISITS BY THE ARCHITECT

A. In all cases where site observation visits of the irrigation system work is required and/or where portions of the work are specified to be performed under the direction and/or site observation of the Architect or his representative, the Contractor shall notify the Architect at least three (3) working days in advance of the time such site observation and/or direction is required:

B. Site observation will be required for the following parts of the work:

1. Upon installation and testing of main lines and lateral lines; when pipes are laid and are to be submitted to pressure tests. Do not cover any lines until they have been checked and approved.

2. Upon installation and testing of valves, quick couplers, devices, automatic controllers, and control valves and wires.

32 81 00 - 9 IRRIGATION SYSTEM

3. When the sprinkler system is completed prior to planting, the Contractor, in the presence of the Architect, shall perform a coverage test to determine if the coverage of water afforded the lawn and planting areas is complete and adequate. The Contractor shall furnish all materials and perform all work required to correct any inadequacies.

4. Final site observation visit by the Architect and performance test shall be at the same time as the final site observation of the specified landscape maintenance period work.

3.05 RECORD DRAWINGS

1. Before final acceptance of work, the Contractor shall provide a “redline” record set of drawings showing the sprinkler system work:

2. Any changes in location of items or type of installations from that shown on drawings shall be so indicated on the record drawings:

3. Valves shall be numbered and corresponding numbers shall be shown on the record drawings:

4. All remote control valves and shut-off valves shall be located by measured dimensions. Dimensions shall be given to permanent objects and shall be to the nearest one-half foot:

5. Immediately upon the installation of any buried pipe or equipment, the Contractor shall indicate on the drawings the locations of said equipment. Dimensions shall be given from permanent objects such as buildings, sidewalks, curbs and driveways:

**END OF SECTION**

32 81 00 - 10 IRRIGATION SYSTEM

SECTION 32 90 00

LANDSCAPE PLANTING

PART 1 GENERAL

1.01 SUMMARY

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.02 RELATED DOCUMENTS

A. This Section includes provisions for the following items:

1. Shrubs

2. Soil Amendments

3. Finish Grading

4. Maintenance Period

B. Related sections and reference documents: The following sections and reference documents contain requirements that relate to this section

C. Underground sprinkler system is specified in Division 2 Section 02810, "Irrigation System."

D. Reference Documents:

1. American Joint Committee on Horticulture Nomenclature (AJCHN), standardized plant names, Latest Edition.

2. American Association of Nurserymen, Inc. (AAN), American Standard for Nursery Stock, Latest Edition.

3. Standard Specifications for Public Works Construction.

4. Agricultural Code of California.

1.03 QUALITY ASSURANCE

A. Subcontract landscape work to a single firm specializing in landscape work. The Contractor shall possess all licenses and permits required to perform the work including a C-27 landscaping license. 32 90 00 - 1 LANDSCAPE PLANTING

B. Source Quality Control:

1. General: Ship landscape materials with certificates of inspection required by governing authorities. Comply with regulations applicable to landscape materials.

2. Do not make substitutions. If specified landscape material is not obtainable, submit proof of non-availability to Landscape Architect, together with proposal for use of equivalent material.

3. Analysis and Standards: Package standard products with manufacturer's certified analysis. For other materials, provide analysis by recognized laboratory made in accordance with methods established by the Association of Official Agriculture Chemists, wherever applicable.

4. Shrubs and Plants: Provide trees, shrubs, and plants of quantity, size, genus, species, and variety shown and scheduled for landscape work and complying with recommendations and requirements of ANSI Z60.1 "American Standard for Nursery Stock". Provide healthy, vigorous stock, grown in recognized nursery container sizes, in accordance with good horticultural practice and free of disease, insects, eggs, larvae, and defects such as knots, sun-scald, injuries, abrasions, or disfigurement.

5. Label each tree and shrub with securely attached waterproof tag bearing legible designation of botanical and common name.

6. Where formal arrangements or consecutive order of trees or shrubs are shown, select stock for uniform height and spread, and label with number to assure symmetry in planting.

7. Selection: The Landscape Architect may check trees and shrubs either at place of growth or at site before planting, for compliance with requirements for genus, species, variety, size, and quality. The Contractor shall submit photographs to Landscape Architect of typical trees (15 gal. and larger container sizes) for landscape work. Landscape Architect retains right to further check trees and shrubs for size and condition of root ball root systems, insects, injuries and latent defects, and to reject unsatisfactory or defective material at any time during progress of work. Contractor shall remove rejected trees or shrubs immediately from project site upon request.

1.04 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 1 Specification Sections.

B. Plant and Material Certifications:

32 90 00 - 2 LANDSCAPE PLANTING 1. Certificates of inspection as required by local municipality and/or governmental authorities.

2. Manufacturer's or vendor's certified analysis for soil amendments and fertilizer materials.

3. Label data substantiating that plants, trees, shrubs and planting materials comply with specified requirements.

1.05 DELIVERY, STORAGE AND HANDLING

A. Packaged Materials: Deliver packaged materials in containers showing weight, analysis, and name of manufacturer. Protect materials from deterioration during delivery and while stored at site.

B. Shrubs: Do not prune prior to delivery unless otherwise approved by Landscape Architect. Do not bend or bind-tie trees or shrubs in such manner as to damage bark, break branches, or destroy natural shape. Provide protective covering during delivery.

C. Do not remove container-grown stock from containers until planting time.

D. Contractor shall provide complete care to all on-site storage of container-grown stock. All container-grown stock found to be damage during storage shall be removed and replaced at no additional cost.

1.06 JOB CONDITIONS

A. Utilities: Determine location of underground utilities and perform work in a manner, which will avoid possible damage. Hand excavate, as required. Maintain grade stakes set by others until removal is mutually agreed upon by parties concerned.

B. Excavation: When conditions detrimental to plant growth are encountered, such as rubble fill, adverse drainage conditions, or obstructions, notify Landscape Architect before planting.

1.07 SEQUENCING AND SCHEDULING

A. Planting Time: Proceed with, and complete landscape work as rapidly as portions of site become available, and shall be performed during those periods when weather and soil conditions are suitable in accordance with locally accepted horticultural practice.

1.08 SPECIAL PROJECT WARRANTY

A. Warranty trees, for a period of one year after date of final acceptance against defects, including death, except for defects resulting from neglect by Owner, abuse or damage

32 90 00 - 3 LANDSCAPE PLANTING by others, or unusual phenomena or incidents, which are beyond Landscape Installer's control.

B. Warranty shrubs for a period of 90 days after date of final acceptance.

C. Contractor shall remove and replace trees, shrubs, or other plants found to be dead or in an unhealthy condition during warranty period. Make replacements within 14 calendar days. Replace trees and shrubs, which are in doubtful condition at end of warranty period; unless, in opinion of Landscape Architect, it is advisable to extend warranty period for a full growing season.

D. Another warranty site observation visit will be conducted at end of extended warranty period, if any, to determine acceptance or rejection. Replacement shall be the plants used for same kind and size as specified for landscape work. Replacements shall be furnished, and planted as originally specified by the contractor.

PART 2 PRODUCTS

2.01 SOIL AMENDMENTS

A. Commercial Fertilizer: Complete fertilizer of neutral character, with some elements derived from organic sources and containing the following percentages of available plant nutrients:

1. Pre-plant Fertilizer: Provide fertilizer with not more than 6 percent total nitrogen; and not less than 20 percent available phosphoric acid and 20 percent soluble potash.

2. Plant Tablets, agriform (20-10-5-) blue chip tablets 21 gram.

B. Soil Sulphur, shall be elemental sulphur (99.5%) commercially manufactured so that a pure sulphur product is used.

C. Organic Soil Conditioner, shall be a product that aids the structure of the soil consisting of rapidly decaying slowly decaying, and non-decaying material. Nitrogen (organic or ammonic) 0.5% to 0.8%, pH between 5.5 to 6.5 salinity (ECe x 103 at 25° C) = 2.5, organic matter more than 87% (dry weight basis). The commercial grade product used shall be Numex Lif, Loamex, or Forest Humus or approved equal by Landscape Architect.

D. Soil Conditioner, granular, Tri-C Humate Plus, shall contain 25% Humic Acids. It shall be free flowing, suitable for application with approved equipment and shall contain the minimum available percentages of 7% calcium and 5% sulphur.

2.02 PLANT MATERIALS

32 90 00 - 4 LANDSCAPE PLANTING A. Quality: Provide trees, shrubs, and other plants of size, genus, species, and variety shown and scheduled for landscape work and complying with recommendations and requirements of ANSI Z60.1 "American Standard for Nursery Stock."

B. Container stock (1 gal., 5 gal., 15 gal., boxes) shall have been grown in container for at least six months, but not over two years. No container plants that have cracked or broken balls of earth when taken from the container shall be planted, expect upon special approval. No trees with damaged roots or broken balls shall be planted.

C. Shrubs: Provide shrubs of the height and width shown or listed as required by ANSI Z60.1 for type and height of shrub required.

D. Rock Mulch: Shall be as specified on plans.

2.03 GROUNDCOVER MATERIALS

A. Bark Mulch: A 3-inch minus blend created from clean and landscape trimmings. Bark mulch shall be dark colored product recommended for mulching in shrub beds. Bark mulch shall be Plant Choice Brush Mulch, Organic Recycling West Brush Mulch, or AJ Ecology Ecohumus Compost or approved equal by Landscape Architect.

B. Sod: Provide strongly rooted sod, not less than 2 years old, free of weeds and undesirable native grasses, and machine cut to pad thickness of 3/4 inch (plus or minus 1/4 inch), excluding top growth and thatch. Provide only sod capable of vigorous growth and development when planted (viable, not dormant).

C. Provide sod of uniform pad sizes with maximum 5 percent deviation in either length or width. Broken pads or pads with uneven ends will not be acceptable. Sod pads incapable of supporting their own weight when suspended vertically with a firm grasp on upper 10 percent of pad will be rejected.

D. Provide sod type as indicated on plans.

E. Rock Cobble/Mulch: Shall be as specified on plans.

2.04 WEED CONTROL

A. Pre-planting herbicide: Roundup or equal

B. Pre-emergent weed control: Oxandiazon-2G-G, Treflan, Eptam, Vegitex, or equal, as recommended by licensed pest control applicator.

PART 3 EXECUTION

3.01 PREPARATION – GENERAL

32 90 00 - 5 LANDSCAPE PLANTING A. Lay out planting areas shall mean all areas to be planted with trees, shrubs, groundcovers and areas for multiple plantings. Stake locations and outline areas and secure Landscape Architect’s acceptance before start of planting work. Make minor adjustments as may be required.

B. All rock and other growth or debris accumulated during the duration of the project shall be removed from the site.

C. Grading and soil preparation work shall be performed only during the period when beneficial and optimum results may be obtained. If the moisture content of the soil should reach such a level that working it would destroy soil structure, spreading and grading operations shall be suspended until the moisture content is increased or reduced to acceptable levels and the desired results are likely to be obtained.

D. All scaled dimensions are approximate. Before proceeding with any work, carefully check and verify all dimensions and immediately inform the Landscape Architect of any discrepancy between the drawings and/or specifications and actual conditions.

E. Quantities for plant materials are shown for convenience only, and not guaranteed. Check and verify count and supply sufficient number to fulfill intent of drawings. Certify any clarifications with the Landscape Architect. Adequately stake, barricade, and protect all irrigation equipment, manholes, utility lines, and other existing property during all phases of the soil amending planting and grading operations.

F. Upon delivery of material and/or completion of all soil conditioning and grading but prior to initiating planting operations, the Landscape Architect with the heretofore specified signed copies of required certificates, trip slips, and invoices for soil preparation materials, shall invoice such material, comparing the total quantities of each material furnished against the total area to each operation. If the minimum rates of application have not been met, the Landscape Architect will require the distribution of additional quantities of these materials to fulfill the minimum application requirements specified at no cost to owner.

3.02 PREPARATION FOR SOD

A. Soil Conditioning, Fertilizing & Rototilling: After the planting areas have been graded, apply soil amendments and initial fertilizers as specified. Remove high areas and fill in depressions. Till to a depth of not less than 6 inches by rototilling a minimum of two (2) alternating passes. Till soil to a homogeneous

32 90 00 - 6 LANDSCAPE PLANTING mixture of fine texture, free of lumps, clods, stones, roots and other extraneous matter.

B. Prior to preparation of unchanged areas, remove existing grass, vegetation and turf. Dispose of such material outside of Owner's property.

C. Allow for sod thickness in areas to be sodded.

D. Apply specified soil amendment and commercial fertilizer at rates specified and thoroughly mix into upper 6 inches of planting areas. Delay application of fertilizer if lawn planting will not follow within a few days.

E. Schedule of planting soil mixture:

1. Organic Soil Conditioner: 6 cu. yd. per 1,000 sq. ft.

2. Soil Conditioner: 75 lbs per 1,000 sq. ft.

3. Pre-Plant Fertilizer: 20 lbs per 1,000 sq. ft.

3.03 FINISH GRADING

A. Finish Grading: Finish grades shall be as indicated on the Civil Engineer's drawings and landscape drawings.

B. Finish grades shall be measured as the final water compacted and settled surface grades; and shall be within plus or minus 0.1 foot of the spot elevations and grade lines indicated on the drawing.

C. Finish grades shall be measured at the top surface of surface materials.

D. Molding and rounding of the grades shall be provided at all changes in slope.

E. All undulations and irregularities in the planting surfaces resulting from tillage, rototilling and all other operations shall be leveled and floated out before planting operations are initiated.

F. The Contractor shall take every precaution to protect and avoid damage to sprinkler heads, irrigation lines, and other underground utilities during his grading and conditioning operations.

G. Final finish grades shall insure positive drainage of the site with all surface drainage away from buildings, walls, and toward roadways, drains and catch basins.

32 90 00 - 7 LANDSCAPE PLANTING

H. Final grades shall be acceptable to the Landscape Architect before planting operations will be allowed to begin.

I. Planting surfaces shall be graded with no less than 2 percent surface slope for positive drainage unless otherwise noted on plans.

3.04 DEEP WATERING AND WEED CONTROL:

A. Care shall be taken that the rate of application of water does not cause erosion or sloughing of soils.

B. All depressions, voids, erosion scars and settled trenches generated by the deep watering shall be filled with conditioned topsoil and brought to finish grade.

C. Weed Control:

1. Manually remove all existing weeds and grasses and remove from site.

2. Contractor shall obtain approval by the owner to apply any herbicide, insecticide, fungicide, or other chemicals to be used onsite. Contractor shall abide by all applicable governmental standards regulating the application of any chemicals, and shall follow all manufacturer's recommendations. All workers applying such chemicals shall be licensed if required by law.

3.05 EXCAVATION FOR SHRUBS

A. Container grown stock in cans shall be cut on two sides with an approved can cutter. Stock grown in boxes shall have bottoms removed. All used containers shall be removed to the storage areas or from the site. Each tree and shrub shall be placed in the center of the hole and shall be set plumb, remove sides of boxes where required, and held rigidly in position until the planting backfill has been tamped from around each root ball.

B. For container grown stock, excavate as specified for size of container width and depth.

C. Dispose of excess subsoil removed from planting excavations.

D. Fill excavations for trees and shrubs with water and allow water to percolate out prior to planting.

32 90 00 - 8 LANDSCAPE PLANTING 3.06 PLANTING SHRUBS

A. Set container grown stock as specified, cut cans on 2 sides with an approved can cutter; remove bottoms of wooden boxes after partial backfilling so as not to damage root balls. All used containers shall be removed to the storage areas or from the site. Each tree and shrub shall be placed in the center of the hole and shall be set plumb and held rigidly in position until the planting backfill has been tamped from around each root ball.

B. All plants shall be set at such a level that after settling, they bear the same relationship to the surrounding finish grade as they bore to the soil line grade in the container.

C. Planting tablets shall be placed in each tree planting hole at the following rate:

1. 1-21 gram tablet per 1 gallon container.

D. No plant will be accepted if the root ball is broken or cracked; either before, during or after the process of installation.

E. Water basin shall be formed around each tree and shrub per detail. All plants shall be thoroughly watered into the full depth of each plant hole immediately after planting.

F. Prune, thin out, and shape trees and shrubs in accordance with standard horticultural practice. Prune trees to retain required height and spread. Unless otherwise directed by Landscape Architect, do not cut tree leaders, and remove only injured or dead branches from flowering trees, if any. Prune trees and shrubs to retain natural character.

G. Remove and replace excessively pruned or malformed stock resulting from improper pruning.

3.07 SODDING NEW LAWNS

A. The contractor shall install approved sod after lawn areas which are to be sodded are rototilled, soil conditioners incorporated, fine graded and rolled for compaction, rock and debris removed.

B. Prior to placement of sod, the areas shall be finished graded smooth with uniform grade between walks, curbs, steps and buildings. The contractor shall obtain approval of finish grades prior to placement of sod.

32 90 00 - 9 LANDSCAPE PLANTING C. Lay sod within 24 hours from time of stripping. Do not plant dormant sod or if ground is frozen.

D. Lay sod to form a solid mass with tightly fitted joints. Butt ends and sides of sod strips; do not overlap. Stagger strips to offset joints in adjacent courses. Staggered rows shall follow grade elevations (do not lay sod perpendicular to slope of grades). Work from boards to avoid damage to sub-grade or sod. Tamp or roll lightly to ensure contact with sub-grade. Work sand into minor cracks between pieces of sod; remove excess to avoid smothering of adjacent grass.

E. Uniformly spread Tri – C Endo 120 @ 1 ½ lbs per 1,000 square foot on graded surface and lay sod directly on top.

F. Water sod thoroughly with a fine spray immediately after planting. Re-sod areas which do not show a prompt catch of grass within ten (10) days after installation

3.08 PLACEMENT OF BARK MULCH

A. Bark mulch shall be spread evenly throughout shrub beds as indicated on the plans. Contractor shall subgrade area adjacent to paving so that bark mulch will be flush with top of adjacent edge of paving. Provide not less than following thickness of bark mulch in planting areas specified.

B. Provide a 3-inch thickness of bark mulch.

3.09 PLACEMENT OF ROCK COBBLE/MULCH

A. Rock mulch shall be spread evenly throughout planting beds as indicated on the plans. Contractor shall subgrade area adjacent to paving so that decorative rock will be flush with top of adjacent edge of paving.

B. Provide a minimum 2 to 4-inch thickness of rock mulch to all areas to be covered.

C. Prior to spreading decorative rock, ensure all areas to be covered are free of rock and debris.

D. Prior to spreading decorative rock, apply pre-emergent weed control to all areas to be covered.

3.10 MAINTENANCE PERIOD

32 90 00 - 10 LANDSCAPE PLANTING

A. The Maintenance Period begins on the first day after all landscape and irrigation work and all other indicated or specified work on this project is complete, checked, accepted and written approval from the Landscape Architect is given to begin the Maintenance Period.

B. The Contractor shall continuously maintain all involved areas of the Contract during the progress of the work and during the Maintenance Period until the Final Acceptance of the work.

C. Regular planting maintenance operations shall begin immediately after each plant. Plants shall be kept in a healthy, growing condition and in a visually pleasing appearance by watering, pruning, mowing, rolling, trimming, edging, fertilizing, re-staking, pest and disease control, spraying, weeding, cleaning-up and any other necessary operation.

D. The maintenance period shall continue until final acceptance, but under no circumstances less than following period:

1. 30 days after substantial completion of planting.

E. The Contract completion date of the Contract Maintenance Period will be extended when in the opinion of the Landscape Architect, improper maintenance and/or possible poor or unhealthy condition of planted material at the termination of the scheduled Maintenance Period. The Contractor shall be responsible for additional maintenance of the work at no change in Contract price until all of the work is completed and acceptable.

F. The Contractor shall be responsible for maintaining adequate protection of the areas. Damaged areas shall be repaired immediately at the Contractor’s expense.

G. Maintain trees, shrubs, and other plants by pruning, cultivating, and weeding as required for healthy growth. Restore planting water basins. Tighten and repair stake and reset trees and shrubs to proper grades or vertical position as required. Spray as required to keep trees and shrubs free of insects and disease.

H. Permanent post construction BMP devices shall not be removed or modified without the approval of the Landscape Architect.

3.11 CLEANUP AND PROTECTION

A. During landscape work, keep pavements clean and work area in an orderly condition.

32 90 00 - 11 LANDSCAPE PLANTING

B. Protect landscape work and materials from damage due to landscape operations, operations by other Contractors and trades, and trespassers. Maintain protection during installation and maintenance periods. Treat, repair, or replace damaged landscape work as directed.

C. Contractor shall provide and incorporated all Best Management Practices (BMP), Storm Water Pollution Prevention Plan (SWPPP) and erosion and sediment control as described in the project conditions or required by local and state requirement.

3.12 SITE OBSERVATION VISITS:

A. Site observation visits herein specified shall be made by the Landscape Architect. The Contractor shall request site observation a minimum of 24 hours in advance.

B. Site observation will be required for the following parts of the work:

1. Incorporation of soil conditioner and fertilizer into the soil

2. Upon completion of finish grading prior to planting

3. Approval of plant materials

4. When shrubs are spotted in place for planting, but before planting holes are excavated.

5. When planting, and all other indicated or specified work, except the Maintenance Period, has been completed. Acceptance and written approval shall establish beginning of the Maintenance Period.

6. Final site observation visit at the completion of the Maintenance Period. This site observation visit shall establish the beginning date for the warranty period of plant material.

**END OF SECTION**

32 90 00 - 12 LANDSCAPE PLANTING SECTION 33 05 16

UTILITY STRUCTURES PART 1 GENERAL

1.01 SUMMARY

A. This section includes materials, construction, installation and testing for the construction of storm drain structures, including cast-in-place Standard Drawing concrete storm drain inlets, outlets, prefabricated inlets, clean-outs. This scope of work includes but is not limited to, material for structures, trenching, structure installation, placement, backfilling, and compacting of backfill material.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 33 00 – Submittal Procedures

B. Section 31 23 33 – Trenching, Excavation, Backfilling and Compacting

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

C. American Society for Testing and Materials (ASTM)

1.04 SUBMITTALS

A. General: Refer to Section 01 33 00 - Submittal Procedures, for submittal requirements and procedures.

PART 2 MATERIALS

2.01 CAST-IN-PLACE CONCRETE STORM DRAIN STRUCTURES

A. Materials: Comply with requirements of Section 201-1 – Portland Cement Concrete of the SSPWC, and SDRSD.

PART 3 EXECUTION

33 05 16 - 1 UTILITY STRUCTURES 3.01 INSTALLATION

A. Requirements: Construct cleanouts, catch basins, inlets, and outlets, utility boxes and vaults, and related utility structures in connection with the installation of pipe, conduits, duct banks, and utility trenches, as indicated in the Construction Plans and Standard Specifications, and San Diego Regional Standard Drawings (SDRSD).

B. Excavation and Backfill: Provide excavation, prepared subgrade and aggregate base, and backfill as specified in Section 31 23 33 – Trenching, Excavation, Backfilling and Compacting.

PART 4 MEASUREMENT AND PAYMENT

4.01 UTILITY STRUCTURES

A. Full compensation for work that is specified, shown on the drawings, or required per the Contract without a specific Bid item listed for such work shall be included in the prices paid for various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

B. Full compensation for conforming to the requirements of this Section, UTILITY STRUCTURES, including all labor, materials, equipment, tools, and incidentals will be considered included in the Unit Price paid for the various items listed in the Bid Schedule and no additional compensation will be allowed therefore.

33 05 16 - 2 UTILITY STRUCTURES SECTION 33 40 00

STORM DRAINAGE UTILITIES

PART 1 GENERAL

1.01 SUMMARY

A. This scope of work in this section is for the materials and installation of 66-inch to 12-inch perforated, and solid PVC storm drain pipe utilities, and includes but is not limited to, pipe material, trenching, pipe installation,; placement, backfilling, and compacting of pipe zone and trench zone material; handling, stockpiling, managing, and connection to existing, and proposed storm drain structures and facilities

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. Section 01 33 00 – Submittal Procedures

B. Section 31 23 33 – Trenching, Excavation, Backfilling and Compacting

C. Section 31 22 20 – Bioretention Basins

1.03 REFERENCE STANDARDS

A. Standard Specifications

1. Standard Specifications for Public Works Construction (SSPWC), 2015 Edition (Green Book), including the Regional Supplement.

B. Standard Drawings

1. San Diego Regional Standard Drawings (2012).

C. American Society for Testing and Materials (ASTM):

1.04 SUBMITTALS

A. General: Refer to Section 01 33 00 - Submittal Procedures, for submittal requirements and procedures.

B. Prior to construction Contractor to submit for review and approval a Stormwater Diversion Plan. See Section 02 41 00 DEMOLITION for submittal requirements.

PART 2 MATERIALS

2.01 PIPE SPECIFICATIONS

33 40 00 - 1 STORM DRAINAGE UTILITIES

A. PVC Pipe Specifications shall be per the Construction plans, SSPWC, and where located in Bioretenion Basins, in accordance with Section 31 22 20

B. Bedding and Backfill Material: Refer to Section 31 23 33 – Trenching, Excavation, Backfilling and Compacting for requirements.

PART 3 EXECUTION

3.01 INSTALLATION OF PIPE

A. Pipe installation shall conform to Section 306-1.2 of the SSPWC.

B. Excavation and Bedding:

1. Excavations:

a. Excavate trenches as specified in Section 31 23 33 – Trenching, Excavation, Backfilling and Compacting.

b. Bedding: Provide bedding as specified in Section 31 23 33 - Trenching, Excavation, Backfilling and Compacting for Utilities, as shown on the drawings, and SDRSD. C. Backfilling:

1. Piping shall not be covered with backfill material, until inspected, tested, and approved by the District.

2. After pipe has been installed, inspected, and approved, place and compact backfill as specified in Section 31 23 33 – Trenching, Excavation, Backfilling and Compacting.

3. Contractor shall complete concrete slurry backfilling promptly and efficiently in order to minimize the dewatering operations.

3.02 CONSTRUCTION ADJACENT TO AND/OR ACROSS EXISTING UTILITIES

A. Construction adjacent to and/or across existing utilities shall be in accordance with Section 31 23 33 – Trenching, Excavation, Backfilling and Compacting, Part 3.05. The cost for construction adjacent to and/or across existing utilities shall be included in the various corresponding Contract items of work in the Bid Schedule and no additional compensation will be allowed therefore.

PART 4 MEASUREMENT AND PAYMENT

4.01 UTILITY STRUCTURES

33 40 00 - 2 STORM DRAINAGE UTILITIES

A. Full compensation for conforming to the requirements of this Section, UTILITY STRUCTURES, including all labor, materials, equipment, tools, and incidentals will be considered included in the Unit Price paid for the various items listed in the Bid Schedule and no additional compensation will be allowed therefore.

**END OF SECTION**

33 40 00 - 3 STORM DRAINAGE UTILITIES