NORTH-SOUTH GREENWAY GAP CLOSURE PROJECT FUTURE CENTRAL MARIN FERRY CONNECTOR TO THE GREENBRAE PEDESTRIAN OVERCROSSING

CENTRAL MARIN FERRY CONNECTOR

HIGHWAY 101

GREENBRAE PEDESTRIAN OVER- CROSSING

N CORTE MADERA CREEK PATHWAY SLOPE AT BRIDGE OVER CORTE MADERA CREEK 35"

EXISTING ROADWAY PROFILE EXISTING ROADWAY PROFILE (6% GRADE) (8.5% GRADE)

NEW PATHWAY PROFILE (MAX. 5% GRADE)

24" EXISTING BENT CAPS

SOUTH SIDE NORTH SIDE

BOTTOM OF CHANNEL

VERTICAL SCALE 10 TIMES HORIZONTAL SCALE

ADA Ramp Requirements

·0,1 /$1',1* !6/23( ·0$; ,192.(6$'$5$035(48,5(0(176 5,6( Ramp to Overcrossing | 1:12 Chengdu, China

”6/23( 127$´5$03µ3(5$'$

Berkeley 1-80 Bridge Ramp | 1:20 Berkeley, CA PROJECT EXTENTS NORTH-SOUTH GREENWAY GAP CLOSURE PROJECT: CMFC TO GREENBRAE POC SEGMENT

Lucky Drive Sandra Marker Trail

Sir Frances Drake Blvd

Tamal Vista Blvd

Wornum Drive

Fifer Avenue Fifer

GREENBRAE Nellen Avenue POC CMFC SMART Old Redwood Highway Bridge

Sir Frances Drake Blvd Connection Location TBD

Railroad Right of Way LARKSPUR FERRY TERMINAL

NORTH-SOUTH GREENWAY Existing Bike/Ped Pathways GAP CLOSURE PROJECT Bike Routes CMFC to Greenbrae POC Segment Railroad Right of Way Segment 8. VISIBILITY OF PATHWAY USERS BY MOTORISTS 10. EXAMPLES OF LIGHTING FEATURES

GROUND-LEVEL LIGHTING STANDARD STREET LIGHTS MID-LEVEL LIGHTING ON A PATHWAY ON A PATHWAY A C FH

B D G

E 11. EXAMPLES OF PATHWAY WIDTHS

San Mateo Bridge Pathway | San Mateo, CA Pathway | Vallejo, CA Pathway | San Francisco, CA Wooden Bridge Pathway | Larkspur CA 8’ Wide 12’ Wide 10’ Wide 10’ Wide

Northbound Off-Ramp Pathway | Larkspur, CA Cal Park Tunnel Pathway | San Rafael, CA Greenbrae Pedestrian Overcrossing | Larkspur, CA Berkeley 1-80 Bridge Pathway | Berkeley, CA 4’ Wide 11.5’ Wide 8’ Wide 15.5’ Wide 12. PATHWAY ACCESS POINTS

Greenbrae CMFC POC a c Bridge b d e Stairs

NORTH-SOUTH GREENWAY ACCESS a Greenbrae Pedestrian Overcrossing Existing Bike/Ped Pathways GAP CLOSURE PROJECT POINTS: b Somewhere Along Old Redwood Highway Bike Routes c North End of Old Redwood Highway CMFC to Greenbrae POC Segment d Wooden Bridge/Stairs Railroad Right of Way Segment e Central Marin Ferry Connector Bridge 15.OPPORTUNITIES FOR IMPROVEMENT ALONG OLD REDWOOD HWY 16.ADD SIDEWALK ON 17. BIKE LANE VS. SHARED OLD REDWOOD HIGHWAY? USE PATHWAY?

EAST SIDE

VIEW OF EXISTING OLD REDWOOD HIGHWAY LOOKING SOUTH 18. BRIDGE VIEWING SPOTS?

VIEW FROM EXISTING PATHWAY LOOKING NORTH

VIEW FROM EXISTING PATHWAY LOOKING EAST VIEW FROM EXISTING PATHWAY LOOKING NORTH 19. & 20. EXAMPLES OF RAILINGS

I-90 Bridge Merced Island Bike Path | Seattle, WA Bay Farm Island Bridge Bike Path | Oakland, CA Benicia-Martinez Bridge Bike-Ped Path | Benicia, CA

New East Span Bay Bridge | Oakland, CA Cooper River Bridge Replacement | Charleston Harbor, SC Carquinez Bridge Bike Path | Vallejo, CA

Golden Gate Bridge Bike-Ped Path | San Francisco, CA Bicycle Pedestrain Bridge | Duquesne, PA Dumbarton Bridge Bike Path | Menlo Park, CA 21. CHARACTER OF NEW PATHWAY ON BRIDGE? PROJECT SCHEDULE & OPPORTUNITIES FOR PUBLIC INPUT

ENVIRONMENTAL REVIEW PROCESS February - December 2015

PRELIMINARY ENGINEERING & DESIGN FINAL DESIGN February - October 2015 Winter 2015 - Winter 2016 CONSTRUCTION Spring 2017 - Summer 2018

2015 2016 2017 2018 SPRING SUMMER FALL WINTER SPRING SUMMER FALL WINTER SPRING SUMMER FALL WINTER SPRING SUMMER FALL WINTER

SECOND PUBLIC WORKSHOP CONSTRUCTION BIDDING OPENING Summer 2015 Winter 2016 Summer 2018

FIRST PUBLIC WORKSHOP April 2015

WEB www.tam.ca.gov | PHONE 415.226.0815

A second public workshop will be held in summer 2015 to receive community input on potential design alternatives.