Highways - Long Term Last Reviewed: Sep-20 Programme

Target Lead Scheme Description Priority Next steps Funding Funding Comments on site Status Driver

Separate capital Douglas Prom Wall Sea wall, first phase due this year Build 20/21 Climate A01 scheme Douglas Prom walkway Separate capital Renewal of existing surface and railings repair/replace Build 20/21 Regen A02 and railings scheme Gretch Veg culvert, On site 20/21 Climate change Climate A03 Kirk Michael village Separate capital Crossings, improved footways, traffic calming Tender 21/22 Regen A04 improvements scheme Separate capital Michael Street Regeneration with high quality paving. Tender 21/22 Regen A05 scheme Separate capital Structure Pulrose Bridge Tender award 21/22 A06 scheme s Motel to Fairy Separate capital A5 road reconstruction Design 21/22 Highway Design required. A07 Bridge scheme

Ballanass to dip Safety and carriageway improvements Design 21/22 SHM Highway A08

Eairy Dam Design 21/22 SHM Highway A09 Separate capital Saddle Road Reconstruct, re-design with cycle lane Funding 21/22 Highway Business case submitted. Await funding information. A10 scheme Separate capital Tromode Road Reconstruct, re-design with cycle lane Funding 21/22 Highway Business case submitted. A11 scheme Business case submitted. Dandara aiming to commence works winter Funding & 21/22. Priority in business case list. Systra doing further option testing on the Separate capital Balthane Junction DOI works at southern end to complete bypass. detailed 21/22 Highway signalised junction, before we commence detailed design. 4 properties scheme design being demolished, Aidan's team doing R&D surveys (with asbestos survey A12 external). Separate capital Peel East Quay Reconstruction with high quality material. Planning 21/22 Regen A13 scheme Review other Signals / footway / Rosemount junction Junction renewal 21/22 Signals Brief required, check with Matt for signals programme works carriageway A14 Separate capital Kirk Michael revetment Coastal erosion Funding 21/22 Climate Awaiting budgets, however coastal defence likely to be pushed back A15 scheme

Top of May Hill to Hairpin Full recon (before next TT) Brief / Design 21/22 SHM Highway A16 Funding / Expansion of the Raad ny Foillan in areas it veers away from Separate capital Coastal footpath progress 21/22 Paths Business case submitted. the coast or along roadside sections. scheme A17 legislation Funding / Heritage Trail - KM to Separate capital Continuation of the Heritage Trail scheme to Ramsey. design / land 21/22 Paths Business case submitted. Ramsey scheme A18 negotiations Requirement Financial waiver for existing system expires Dec 21. Very Separate capital Symology replacement s 21/22 IT Business case submitted. unlikely to be extended scheme A19 development

Separate capital Vehicle tracking Existing system obsolete Funding IT Ready to go to AGs, however requires confirmation of funding. scheme A20 Separate capital & Street Reconstruction of shopping areas with high quality materials. Funding 21/22 Regen Possible for SHM? A21 scheme

Ramsey Shipyard Slab A22 (West) 21/22 Harbours Slab next year? Check Rollout of ANPR to improve ticketing enforcement and car Business case submitted. #4 in business case priorities. Chester Street will ANPR for car parks Funding 21/22 Car Parks A23 park management. be done out of revenue if required. Separate capital Structure Laxey embankment Embankment stabilisation just past Laxey hairpin Funding 21/22 Business case submitted. A24 scheme s A25 Speed Cameras Proposal for trial sites for speed cameras. Funding 21/22 Traffic Business case submitted. Partially fund from active travel? TC to look at progressing. Systra have PERS implementation Design / scoping A26 done some work on this but very limited. village Develop Ballasalla sense of place following the bypass works. Feasibility enhancements Deferred to 24/25. Signals design needs reviewing. Grandstand / Design 22/23 Capital approved Highway Glencrutchery Rd Police also looking at potentially relocating. Include St Ninian's junction? A27 Cycleway also being looked at. Includes traffic signals renewals Laxey Sea Wall / Design & planning22/23 Climate change Climate A28 Harbour Wall Separate capital Needs considering in the round with Prospect Hill, Ridegeway Street, Bucks Victoria Street Following prom works. High quality materials. 3-5 years Brief 22/23 Regen scheme Road and movement study. Arrange internal workshop (TC) A29

Circular Road Footway enhancements Brief 22/23 Active travel have plans for this area (discuss wih Tim) A30

Port St Mary, Bay View Separate capital Reconstruct 22/23 Highway Likely to be deferred due to funding. Road scheme A31 A32 , Church Road 22/23 Highway Likely to be deferred due to funding. Mayhill to Parliament Full recon 22/23 SHM Highway Square A33 Roundabout Reconstruct 3-5 yearsBrief 22/23 SHM Highway A34 (Corkills)

Public requests for dedicated right turn lane. MUA have many services here Parliament Square Resurfacing & Traffic signals renewal Brief 22/23 Highway including the Litney. A35 Peel Promenade Separate capital Climate + Coastal erosion 22/23 Awaiting budgets, however coastal defence likely to be pushed back A36 revetment scheme revetment Regeneration works and tie-in with DBC for the Salvation Ridgeway Street Brief / workshop 23/24 Discuss with wider Douglas roads plans. Salvation Army scheme delayed. Army plans. A37

A38 North Quay Harbour wall and other works Brief 23/24 Climate change Climate Either replacement of existing or new link creating Concept Separate capital TT access road 3-5 years 23/24 Traffic Taken to P&S in January A39 connectivity over the road closure periods. design scheme Fenella bridge & fenella car park, and West Improvements to enhanced pedestrian facilities Brief 25/26 Regen Castle Quay needs structural works. A40 Quay. Bay ny Carrickey Separate capital Climate + Coastal erosion 23/24 Awaiting budgets, however coastal defence likely to be pushed back revetment scheme revetment A41 Check with estates on Chester Street Resizing / refurbing 23/24 Car ParksAwaiting parking review. Programme of electric charging points required. charging A42 points Johnny Watterson / Wider traffic review & resurfacing 23/24 Highway Subject to Police HQ review & 3rd party developments. Discuss with Kevin A43 Ballafletcher Road Castletown Prom Separate capital Climate + Coastal erosion 23/24 Awaiting budgets, however coastal defence likely to be pushed back A44 revetment scheme revetment Separate capital Split Parade Street into separate scheme, needs a crossing siting (active Lord Street & Fort Street Faciliate new crossings, roundabouts, junctions Study 24/25 Regen A45 scheme travel?). Separate capital Climate + Strathallan Rock armour Coastal erosion 3-5 years 24/25 Awaiting budgets, however coastal defence likely to be pushed back A46 scheme revetment Peel Promenade Brief, options Issue with fines washing out. Any prom works will follow the rock armour 10-15 years 24/25 Regen A47 refurbishment study scheme. Reneurling to Douglas Separate capital Reconstruction of carriageway Brief 24/25 A48 Road corner scheme Colby Level through to Separate capital Reconstruction with some overlay Brief 24/25 A49 Colby village scheme Improved cycle/pedestrian facilities. Carriageway also needs Regen / Would suit multiple palettes / standards across the length (asphalt / tegula Bucks Road into reconstructing (concrete slabs failing). Footways would suit Brief 25/26 Active /granite). Consider with the other main Douglas roads. Movement plan Woodbourne Road A50 higher quality than asphalt. Travel required for Douglas A51 Quarterbridge Junction study and reconfiguration Feasibility 25/26 Traffic Eastern plan Structure Tromode Bridge Re-align/widen, install parapets Brief 25/26 A52 s A53 North Quay Traffic/place review around new development Long term3rd party 25/26 Regen Dependent on 3rd Party Works

Separate capital Issue with a threshold for a gate - if landowner will agree to blocking this up Area of reconstruction TBC Brief 25/26 scheme scheme would be considerably easier. A54 Ramsey - Road Separate capital Climate + Coastal erosion. Following JBA report. Approx 1600 m 5-10 years Feasibility 26/27 May not be feasible based on assets saved. revetment scheme revetment A55 Castletown - traffic schemes around New recreational site proposed for King Williams or . 5-10 years 26/27 Traffic Awaiting 3rd party scheme KWC/Rushen Associated traffic improvements. A56 developments Separate capital Review wider options here. Areas with draiange issues. Has the potentail to King Edward Road Brief 26/27 A57 scheme ease traffic through Onchan village. Separate capital Structure Ballaleece Bridge Re-align, install parapets and reconstruct Brief 27/28 Parapet incursions rarer in recent times since moving of the speed limits. A58 scheme s Separate capital Area of SSSI which precludes works in this area. If this habtitat is damaged Ramsey - seawall Coastal overtopping. Following JBA report. Approx 1370 m 5-10 years Feasibility 27/28 Climate A59 scheme by natural forces scheme can follow. A60 Residential Roads Annual Residential Roads Highway Planning in progress (was discussions of withdrawing it, however it should Breakwater ? A61 remain in). Sprayed concrete is still the preferred solution

Glen Road, Laxey ? Climate change Gretch veg culvert, in progress. A62

Ramsey Crossroads Study Traffic Discuss with Kevin, see when Matt B has planned.

A63 A64 Parking Zones Review signage and areas Car Parks Linked to parking strategy Governor's roundabout TT course bypass at governor's 10-15 years Traffic May not be feasible. Dependent on TT access road also. A65 sliproad Albert Street & Awaiting 3rd party scheme which are both on hold (bus/tram interchange & A66 Parsonage Rd Marina scheme) Castletown - Alexander Brief Traffic A67 Road crossing Has been timing changes that have improved the situation. Longer term - Avondale Junction, Junction renewal Traffic consider redevelopment line for planning conditions. Following movement Onchan A68 strategy. A69 QE2 crossing Active travel Was this under Active Travel? A70 Airport gateway Traffic review of roundabout From Bircham Road to Borwing (past the bakery). Station Road, Ramsey SHM A71 Reconstruction needed - align with water main works.