Highway 1 Climbing Lane Carmel River Bridge to Carmel Valley Road
1 Agenda
1. Welcome and Introductions
2. Project Overview
3. Communication Plan
4. Questions/Comments
2 Welcome and Introductions
Supervisor Mary L. Adams, Board of Supervisors – District 5
Neville Pereira, Acting Deputy Director of Public Works, Parks and Facilities County of Monterey – Resource Management Agency
Enrique Saavedra, Acting Chief of Public Works County of Monterey – Resource Management Agency
Billy Issa, Project Manager II County of Monterey - Resource Management Agency
Jonathan Pascua, Senior Civil Engineer County of Monterey – Resource Management Agency
Christine Poe, Management Analyst II County of Monterey – Resource Management Agency
3 Project Overview
4 Stage 1a
Approx. Duration: April to end of May
Construction site(s): • East side Highway 1 • South side Rio Road
Activities: • Traffic shifted to west side Highway 1 • Roadway excavation, grading, paving, and drainage
Expected Outcome: • New pavement and striping on south side Rio Road
5 Stage 1b Approx. Duration: Month of June
Construction site(s): • East side Highway 1 • North side Rio Road
Activities: • Traffic remains on west side Highway 1 • Roadway excavation, grading, paving, and drainage
Expected Outcomes: • Widened road, new paving and striping on east side of Highway 1
6 Stage 2 Approx. Duration: July to end of August
Construction Site: • West side Highway 1
Activities: • Traffic shifted to east side Highway 1 • Roadway excavation, grading, paving, and drainage • Remove temporary concrete barriers • Final paving and striping, activate new signal at Rio Rd • Landscaping
Expected Outcomes: • Project completion
7 Stage 2 Approx. Duration: July to end of August
Construction Site: • West side Highway 1
Activities: • Final paving and striping, activate new signal at Carmel Valley Rd
Expected Outcomes: • Project completion
8 Communications Plan How do I stay informed? Weekly Press Releases Project Webpage Social Media Text Alerts
What do you do with information from the public? Weekly Communications and Construction Meetings
9 Inquiries from Community Are there roundabout alternatives? Is County open to longer work days and night work to expedite project? Why don’t you move the k-rail when no work is going on over weekends? How will weekend traffic back-ups be addressed during construction? How much improvement will be seen in traffic once this project is completed?
10 Questions or Comments?
County website: http://www.co.monterey.ca.us/government/departments-i- z/resource-management-agency-rma-/public-works-facilities/current-major- projects/highway-1-climbing-lane
https://www.facebook.com/montereycountyRMA/
County Staff Contact: Christine Poe Email: [email protected]
11 13