PROCUREMENT PLAN (Textual Part) Project information: [Maldives Clean Environment Project P 160739 Project Implementation agency: Ministry of Environment and Energy

Public Disclosure Authorized Date of the Procurement Plan: 23 August 2017 Period covered by this Procurement Plan: 23 August 2017 to 23 February 2019

Preamble

In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project.

This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan Public Disclosure Authorized for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP.

The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP.

When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Public Disclosure Authorized

Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Public Disclosure Authorized Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Maldives : Maldives Clean Environment Project PLAN General Information

Country: Maldives Bank’s Approval Date of the Original Procurement Plan: 2017-08-23 Revised Plan Date(s): (comma delineated, leave blank if none)2020-02-29 Project ID: P160739 GPN Date: 2017-08-23 Project Name: Maldives Clean Environment Project Loan / Credit No: IDA / D1990 Executing Agency(ies):Ministry of Environment and Energy

WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

MV-MEE-60158-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Canceled 2018-05-01 2018-05-10 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope

M.

MV-MEE-61003-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Canceled 2018-05-01 2018-05-10 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope

Madifushi,

MV-MEE-61004-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 78,000.00 0.00 Canceled 2018-05-01 2018-05-10 2018-05-03 2018-05-24 2018-06-07 2018-07-05 2018-11-02 Management Centre in Management Systems Envelope

Kinbidhoo, Thaa Atoll

MV-MEE-91835-CW-RFB / Upgrading of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 60,000.00 54,165.59 Signed 2018-12-17 2018-12-18 2018-12-18 2019-01-03 2019-01-13 2019-01-08 2019-01-17 2019-01-27 2019-02-06 2019-05-27 Management Centre at Lh. Management Systems Envelope

Kurendhoo

MV-MEE-92436-CW-RFQ / Provision of Three Phase Component 3: Island Waste Request for Single Stage - One IDA / D1990 Post Open - National 35,000.00 31,625.16 Signed 2018-12-25 2019-01-27 2019-02-20 2019-03-28 Electricity to IWMC of Management Systems Quotations Envelope

B. & N.

MV-MEE-98538-CW-RFB / Component 2: Regional Single Stage - One Construction of RO Plant IDA / D1990 Post Request for Bids Open - National 90,000.00 58,418.92 Signed 2019-02-06 2019-02-03 2019-02-10 2019-02-24 2019-02-26 2019-03-10 2019-04-15 2019-04-14 2019-05-23 2019-06-28 Waste Management Systems Envelope Building at RWMF

MV-MEE-98559-CW-RFB / Construction of a Store Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 140,000.00 120,502.66 Signed 2019-02-06 2019-02-04 2019-02-10 2019-02-24 2019-02-26 2019-03-10 2019-04-15 2019-04-14 2019-05-23 2019-06-28 Room and Guard House in Waste Management Systems Envelope

Vandhoo RWMF

MV-MEE-106513-CW-RFB / Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 60,000.00 53,673.20 Signed 2019-03-18 2019-03-19 2019-03-19 2019-04-04 2019-04-10 2019-04-09 2019-06-30 2019-04-28 2019-07-17 2019-08-26 Management Systems Envelope ,

MV-MEE-106522-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 135,000.00 135,036.52 Signed 2019-03-18 2019-03-17 2019-03-19 2019-04-04 2019-04-10 2019-04-18 2019-06-29 2019-05-16 2019-07-17 2019-10-13 Management Centre in B. Management Systems Envelope

Dhonfanu

MV-MEE-106524-CW-RFB / Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 135,000.00 112,173.96 Signed 2019-03-18 2019-03-19 2019-03-19 2019-04-04 2019-04-10 2019-04-18 2019-06-30 2019-05-16 2019-07-10 2019-09-13 Management Centre in B. Management Systems Envelope

Hithaadhoo

Page 1 MV-MEE-84075-CW-RFB / Component 2: Regional Single Stage - One Extension of Existing Utility IDA / D1990 Post Request for Bids Open - National 100,000.00 105,952.78 Signed 2019-05-21 2019-02-04 2019-05-22 2019-06-12 2019-02-26 2019-06-19 2019-04-15 2019-07-10 2019-05-20 2019-09-08 Waste Management Systems Envelope Building at Vandhoo RWMF

MV-MEE-101303-CW-RFB / Upgrading of Waste Storage Facilities and Extension Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 620,000.00 791,314.01 Signed 2019-05-10 2019-03-18 2019-05-13 2019-05-27 2019-04-08 2019-06-03 2019-06-15 2019-06-24 2019-07-17 2019-10-22 Works of the Existing Waste Management Systems Envelope

Vehicle Shed in Vandhoo RWMF

MV-MEE-121323-CW-RFB / Re-location of Existing Fuel Tanks, construction of new Component 2: Regional Single Stage - One fuel storage tank and pump IDA / D1990 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2019-06-27 2019-06-30 2019-06-30 2019-07-14 2019-07-30 2019-08-19 2019-08-29 2019-10-03 2020-03-31 Waste Management Systems Envelope room and construction of 200 CBM Water storage Tank at R.Vandhoo

MV-MEE-148349-CW-RFB / Under Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 110,000.00 0.00 Implementati 2019-12-15 2020-01-05 2019-12-18 2020-01-06 2020-01-08 2020-01-22 2020-02-19 2020-06-18 Management Systems Envelope , Raa Atoll on

MV-MEE-148353-CW-RFB / Under Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 130,000.00 0.00 Implementati 2019-12-15 2019-12-30 2019-12-18 2020-01-06 2020-01-08 2020-01-22 2020-02-19 2020-06-18 Management Systems Envelope , on

MV-MEE-64621-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 management Centre in Management Systems Envelope on , Thaa Atoll

MV-MEE-84206-CW-RFQ / Pending Rehabilitation of the Component 2: Regional Request for Single Stage - One IDA / D1990 Post Limited 50,000.00 0.00 Implementati 2020-06-04 2020-07-23 2020-09-21 Existing Landfill and Waste Management Systems Quotations Envelope on Leachate Pond (with pumps)

MV-MEE-148352-CW-RFB / Pending Component 3: Island Waste Single Stage - One Upgrading of IWMC in IDA / D1990 Post Request for Bids Open - National 130,000.00 0.00 Implementati 2020-03-05 2020-03-12 2020-04-02 2020-04-16 2020-05-14 2020-10-11 Management Systems Envelope , on

MV-MEE-64624-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope on Thimarafushi, Thaa Atoll

MV-MEE-64627-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope on , Thaa Atoll

MV-MEE-64630-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope on , Thaa Atoll

MV-MEE-65143-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope on ,

MV-MEE-65371-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope on ,

Page 2 MV-MEE-64620-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope on Buruni, Thaa Atoll

MV-MEE-65373-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope on , Meemu Atoll

MV-MEE-65374-CW-RFB / Pending Construction of Island Waste Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Implementati 2020-06-01 2020-06-04 2020-06-25 2020-07-09 2020-08-06 2020-12-04 Management Centre in Management Systems Envelope on , Meemu Atoll

MV-MEE-136387-CW-RFB / Re-location of Existing Fuel Tanks, construction of new Pending fuel storage tank and pump Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 650,000.00 0.00 Implementati 2020-02-09 2020-02-15 2020-03-16 2020-04-15 2020-05-20 2020-11-16 room and construction of Waste Management Systems Envelope on 200 CBM Water storage Tank at R.Vandhoo and construction of fuel trench

MV-MEE-158460-CW-RFB / Pending Upgrading of water network Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2020-02-27 2020-03-01 2020-03-22 2020-03-29 2020-04-26 2020-10-23 and storage capacity in Waste Management Systems Envelope on Vandhoo RWMF

MV-MEE-158461-CW-RFB / Upgrading of fuel Pending Component 2: Regional Single Stage - One distribution network and IDA / D1990 Post Request for Bids Open - National 300,000.00 0.00 Implementati 2020-02-27 2020-03-02 2020-03-23 2020-04-06 2020-05-04 2020-10-31 Waste Management Systems Envelope storage capacity in Vandhoo on RWMF

MV-MEE-158462-CW-RFB / Rehabilitation and Pending Component 2: Regional Single Stage - One Remediation of the Existing IDA / D1990 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2020-04-01 2020-04-08 2020-05-06 2020-05-20 2020-06-24 2020-12-21 Waste Management Systems Envelope Landfill and Leachate Pond on in Vandhoo

MV-MEE-158463-CW-RFB / Pending Road Construction and Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 400,000.00 0.00 Implementati 2020-03-01 2020-03-04 2020-03-25 2020-04-08 2020-05-06 2021-01-01 Landscaping of Vandhoo Waste Management Systems Envelope on RWMF

MV-MEE-159361-CW-RFB / Pending Component 3: Island Waste Single Stage - One Construction of New IWMC IDA / D1990 Post Request for Bids Open - National 1,820,000.00 0.00 Implementati 2020-05-05 2020-05-12 2020-06-09 2020-06-23 2020-07-28 2020-12-25 Management Systems Envelope in 14 Island on

MV-MEE-159362-CW-RFB / Pending Component 3: Island Waste Single Stage - One Upgrading of 16 IWMC in IDA / D1990 Post Request for Bids Open - National 1,600,000.00 0.00 Implementati 2020-08-01 2020-08-08 2020-09-05 2020-09-26 2020-10-31 2021-04-29 Management Systems Envelope Zone 4 & 5 on

MV-MEE-160654-CW-RFB / Upgrading of IWMC in Pending Component 3: Island Waste Single Stage - One Faafu , Thaa IDA / D1990 Post Request for Bids Open - National 230,000.00 0.00 Implementati 2020-03-05 2020-03-12 2020-04-09 2020-04-30 2020-06-04 2020-09-02 Management Systems Envelope Vandhoo and Dhaalu on Kudahuvadhoo

GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Page 3 MV-MEE-36104-GO-RFQ / Setting up Procurement and Component 4: Project Request for Single Stage - One Financial Management IDA / D1990 Post Limited 10,000.00 10,833.12 Signed 2017-11-21 2018-02-20 2017-12-26 2018-05-24 2018-01-25 2018-08-24 Management Quotations Envelope Systems including hardware and software

MV-MEE-31491-GO-RFB / Component 2: Regional Single Stage - One Procurement of an excavator IDA / D1990 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2017-11-09 2017-11-14 2017-12-26 2018-01-16 2018-02-20 2018-05-21 Waste Management Systems Envelope for Vandhoo RWMF

MV-MEE-31434-GO-RFB / Component 1: National Solid Open - Single Stage - One Monitoring and Research IDA / D1990 Waste Management Strategy Post Request for Bids 650,000.00 0.00 Canceled 2017-10-30 2017-11-02 2017-12-14 2018-01-13 2018-02-17 2018-10-15 International Envelope Vessel and Policy

MV-MEE-37121-GO-RFB / Component 1: National Solid Under Open - Single Stage - One Monitoring and Research IDA / D1990 Waste Management Strategy Post Request for Bids 650,000.00 1,256,000.00 Implementati 2017-11-26 2018-05-06 2017-12-03 2018-05-13 2018-01-14 2018-11-12 2018-02-04 2019-03-16 2018-03-18 2019-05-30 2019-03-18 International Envelope Vessel and Policy on

MV-MEE-37101-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of computer IDA / D1990 Post Limited 15,000.00 0.00 Canceled 2017-11-24 2017-11-29 2017-12-22 2018-01-05 Management Quotations Envelope systems for PMU

MV-MEE-37101-GO-RFQ-2 / Component 4: Project Request for Single Stage - One Desktop and Laptop IDA / D1990 Post Limited 18,000.00 19,109.48 Completed 2018-02-15 2018-03-11 2018-03-16 2018-04-29 2018-04-30 2018-05-21 Management Quotations Envelope Computers for PMU

MV-MEE-48442-GO-RFB / Component 4: Project Single Stage - One Speedboat for Intra-zone IDA / D1990 Post Request for Bids Open - National 200,000.00 223,120.50 Signed 2018-02-28 2018-07-11 2018-03-07 2018-04-04 2018-10-11 2018-04-25 2019-01-10 2018-05-23 2019-02-17 2018-12-19 Management Envelope travel

MV-MEE-83998-GO-RFB / Component 2: Regional Open - Single Stage - One Procurement of a Landing IDA / D1990 Post Request for Bids 750,000.00 0.00 Canceled 2018-11-06 2018-11-26 2018-11-11 2018-12-23 2019-02-11 2019-01-06 2019-02-10 2019-10-08 Waste Management Systems International Envelope Craft for Vandhoo RWMF

MV-MEE-88180-GO-DIR / Component 1: National Solid Mobile Stack Emission IDA / D1990 Waste Management Strategy Post Direct Selection Direct 25,000.00 25,149.23 Completed 2018-11-27 2018-11-27 2018-11-29 2018-11-28 2018-12-08 2018-12-06 2019-01-22 2019-02-10 Monitoring Equipment and Policy

MV-MEE-83258-GO-DIR / Component 1: National Solid Supply of Mobile Stack IDA / D1990 Waste Management Strategy Prior Direct Selection Direct 25,000.00 0.00 Canceled 2018-10-25 2018-10-28 2018-11-10 2018-12-10 Emission Monitoring and Policy Equipment

MV-MEE-96293-GO-RFB / Supply and Installation of Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 300,000.00 0.00 Canceled 2019-01-24 2019-01-31 2019-02-28 2019-03-14 2019-04-18 2019-07-17 Water and Fuel Storage Waste Management Systems International Envelope Tanks at Vandhoo RWMF

MV-MEE-83996-GO-RFB / Procurement of Reach Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2019-02-15 2019-02-18 2019-03-11 2019-03-25 2019-04-22 2019-06-21 Stackers (2 nos) for Vandhoo Waste Management Systems Envelope

RWMF

MV-MEE-81934-GO-RFB / Component 2: Regional Single Stage - One Procurement of a tractor IDA / D1990 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2019-02-14 2019-02-17 2019-03-17 2019-03-24 2019-04-21 2019-06-20 Waste Management Systems Envelope and trailer

MV-MEE-83997-GO-RFB / Procurement of Hooklift Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 150,000.00 0.00 Canceled 2019-02-14 2019-02-19 2019-03-12 2019-03-26 2019-04-16 2019-06-15 Trucks (2 nos.) for Vandhoo Waste Management Systems Envelope

RWMF

MV-MEE-83999-GO-RFB / Procurement of Generator Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 75,000.00 0.00 Canceled 2019-02-15 2019-05-19 2019-02-20 2019-05-20 2019-03-13 2019-06-02 2019-03-27 2019-04-24 2019-06-23 (300 KVA) for Vandhoo Waste Management Systems Envelope

RWMF

Page 4 MV-MEE-99932-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of Weighing IDA / D1990 Post Open - National 25,000.00 15,230.00 Signed 2019-02-11 2019-03-21 2019-06-04 2019-04-25 Management Quotations Envelope Scales

MV-MEE-110470-GO-RFQ / Component 3: Island Waste Request for Single Stage - One Purchase Glass Crusher N. IDA / D1990 Post Limited 6,500.00 6,449.27 Completed 2019-04-17 2019-03-25 2019-05-07 2019-05-21 2019-06-06 2019-05-22 Management Systems Quotations Envelope

MV-MEE-106471-GO-RFB / Component 2: Regional Open - Single Stage - One Landing craft for waste IDA / D1990 Prior Request for Bids 750,000.00 0.00 Canceled 2019-05-13 2019-05-16 2019-06-13 2019-06-23 2019-07-21 2020-02-16 Waste Management Systems International Envelope transfer in zone II

MV-MEE-115522-GO-RFB / Vandhoo Fire Fighting Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2019-05-20 2019-07-07 2019-05-25 2019-07-07 2019-06-15 2019-06-29 2019-07-27 2019-09-25 System - Immediate Waste Management Systems Envelope

Requirement

MV-MEE-60157-GO-RFQ / Component 4: Project Request for Single Stage - One Procurement of Tablet IDA / D1990 Post Limited 20,840.00 0.00 Canceled 2019-07-14 2019-07-30 2019-09-01 2019-10-01 Management Quotations Envelope Computers

MV-MEE-121944-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / D1990 Post Open - National 25,000.00 0.00 Canceled 2019-07-19 2019-09-13 2019-10-13 Office Furniture Management Quotations Envelope

MV-MEE-121947-GO-RFQ / Component 4: Project Request for Single Stage - One Purchase of Photography / IDA / D1990 Post Open - National 20,000.00 19,700.13 Completed 2019-07-23 2019-09-17 2019-11-04 2019-10-17 2019-11-07 Management Quotations Envelope Videography equipment

MV-MEE-121950-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / D1990 Post Open - National 15,000.00 17,598.33 Signed 2019-07-26 2019-09-20 2019-12-10 2019-10-20 Software Management Quotations Envelope

MV-MEE-124036-GO-RFB / Supply and Installation of Component 2: Regional Single Stage - One IDA / D1990 Post Request for Bids Open - National 50,000.00 64,366.10 Completed 2019-07-23 2019-07-31 2019-07-28 2019-08-04 2019-08-18 2019-08-25 2019-09-01 2019-10-13 2019-09-29 2019-11-19 2019-11-28 2019-12-09 Fire Fighting Equipment - Waste Management Systems Envelope

Immediate Requirement

MV-MEE-128581-GO-DIR / Upgrading of CEMS with Component 2: Regional IDA / D1990 Post Direct Selection 28,000.00 27,913.24 Completed 2019-08-22 2019-08-27 2019-08-25 2019-08-22 2019-09-08 2019-09-24 2019-11-07 2019-11-15 CO and NOx probes and Waste Management Systems larger analyzer control unit

MV-MEE-128582-GO-RFQ / Component 4: Project Request for Single Stage - One Desktops and Computer IDA / D1990 Post Limited 15,000.00 19,961.39 Completed 2019-08-28 2019-09-04 2019-10-16 2019-10-07 2019-11-15 2019-10-30 Management Quotations Envelope Accessories

MV-MEE-128583-GO-RFQ / Component 4: Project Request for Single Stage - One Laptops and Tablet IDA / D1990 Post Limited 20,000.00 24,848.77 Signed 2019-08-28 2019-09-04 2019-10-16 2020-01-06 2019-11-15 Management Quotations Envelope computers

MV-MEE-135475-GO-RFB / Component 2: Regional Single Stage - One Supply and Installation of IDA / D1990 Post Request for Bids Open - National 75,000.00 39,401.62 Signed 2019-09-24 2019-09-25 2019-09-29 2019-11-10 2019-10-10 2019-12-10 2019-12-01 2020-01-14 2020-02-02 2020-07-12 Waste Management Systems Envelope 300 KVA Generator

MV-MEE-84003-GO-RFB / Under Waste Collection Vehicles Component 3: Island Waste Open - Single Stage - One IDA / D1990 Prior Request for Bids 703,500.00 0.00 Implementati 2019-12-30 2020-01-06 2020-02-03 2020-02-17 2020-03-09 2020-05-08 with Trailers for Islands of Management Systems International Envelope on Zone 2 (Batch 1)

MV-MEE-81932-GO-RFB / Pending Procurement of 1 Backhoe Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 200,000.00 0.00 Implementati 2020-03-05 2020-03-08 2020-04-05 2020-04-12 2020-05-06 2020-09-03 Loader and 1 Wheel Loader Waste Management Systems International Envelope on for Vandhoo RWMF

MV-MEE-158423-GO-RFQ / Pending Component 4: Project Request for Single Stage - One Supply and Delivery of IDA / D1990 Post Limited 10,000.00 0.00 Implementati 2020-03-04 2020-04-22 2020-05-22 Management Quotations Envelope Office Printers on

Page 5 MV-MEE-158424-GO-RFQ / Pending Component 4: Project Request for Single Stage - One Supply and Delivery of IDA / D1990 Post Limited 7,500.00 0.00 Implementati 2020-03-18 2020-05-13 2020-06-12 Management Quotations Envelope tablets for surveying on

MV-MEE-158445-GO-RFB / Component 1: National Solid Pending Supply of Equipment for Open - Single Stage - One IDA / D1990 Waste Management Strategy Post Request for Bids 125,000.00 0.00 Implementati 2020-03-01 2020-03-06 2020-04-03 2020-04-24 2020-05-22 2020-10-19 Monitoring and Research International Envelope and Policy on Vessel

MV-MEE-158448-GO-RFB / Pending Component 2: Regional Single Stage - One Supply and Delivery of 1 IDA / D1990 Post Request for Bids Open - National 50,000.00 0.00 Implementati 2020-03-01 2020-03-06 2020-04-03 2020-04-17 2020-05-15 2020-09-12 Waste Management Systems Envelope Flat Bottom Whaler on

MV-MEE-158449-GO-RFB / Pending Supply and Installation of 2 Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 100,000.00 0.00 Implementati 2020-04-15 2020-04-18 2020-05-30 2020-06-13 2020-07-05 2020-11-02 static Cranes at Vandhoo Waste Management Systems International Envelope on Harbour

MV-MEE-158450-GO-RFB / Pending Supply, Installation and Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 150,000.00 0.00 Implementati 2020-03-01 2020-03-04 2020-04-01 2020-04-22 2020-05-20 2020-09-17 Commissioning of an RO Waste Management Systems International Envelope on Plant with Borehole Drilling

MV-MEE-158451-GO-RFQ / Pending Supply and Installation of Component 2: Regional Request for Single Stage - One IDA / D1990 Post Limited 20,000.00 0.00 Implementati 2020-03-04 2020-04-17 2020-07-16 Surface Aerators for Waste Management Systems Quotations Envelope on Leachate Pond

MV-MEE-158454-GO-RFB / Pending Supply and installation of a Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 50,000.00 0.00 Implementati 2020-06-15 2020-06-22 2020-07-20 2020-08-03 2020-08-31 2020-11-29 waste manifest system for Waste Management Systems International Envelope on Zone 2

MV-MEE-158459-GO-RFB / Pending Supply, Installation and Component 2: Regional Open - Single Stage - One IDA / D1990 Post Request for Bids 100,000.00 0.00 Implementati 2020-03-01 2020-03-06 2020-04-03 2020-04-24 2020-05-22 2020-10-19 Commissioning of a Weigh Waste Management Systems International Envelope on Bridge for Vandhoo RWMF

MV-MEE-158467-GO-RFB / Pending Supply and Delivery Component 3: Island Waste Open - Single Stage - One IDA / D1990 Post Request for Bids 430,000.00 0.00 Implementati 2020-04-01 2020-04-06 2020-05-18 2020-06-08 2020-07-06 2020-07-18 Autoclaves for Hospitals and Management Systems International Envelope on Health Centres of Zone 2

MV-MEE-158468-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Vehicles for Island Level IDA / D1990 Post Request for Bids 421,500.00 0.00 Implementati 2020-03-15 2020-03-20 2020-05-01 2020-05-15 2020-06-12 2020-11-09 Management Systems International Envelope Waste Collection Systems in on

Zone 2 (Batch 2)

MV-MEE-158469-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Additional equipment for IDA / D1990 Post Request for Bids 382,500.00 0.00 Implementati 2020-03-01 2020-03-06 2020-04-03 2020-04-17 2020-05-15 2020-09-12 Management Systems International Envelope Island Waste Management on

Centres of Zone 2

MV-MEE-158470-GO-RFB / Pending Supply and Delivery of Component 3: Island Waste Open - Single Stage - One IDA / D1990 Post Request for Bids 360,000.00 0.00 Implementati 2020-03-01 2020-03-06 2020-04-03 2020-04-17 2020-05-15 2020-10-12 Composting Equipment to Management Systems International Envelope on IWMCs of Zone 2

MV-MEE-158471-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Autoclaves for Hospitals and IDA / D1990 Post Request for Bids 430,000.00 0.00 Implementati 2020-08-01 2020-08-08 2020-09-19 2020-10-03 2020-10-31 2021-02-28 Management Systems International Envelope Health Centres of Zone IV on

& V

Page 6 MV-MEE-158472-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Vehicles for Island Level IDA / D1990 Prior Request for Bids 1,075,000.00 0.00 Implementati 2020-06-15 2020-06-22 2020-08-03 2020-08-24 2020-09-28 2021-07-25 Management Systems International Envelope Waste Collection Systems - on

Zone 4 & 5

MV-MEE-158474-GO-RFB / Supply and Delivery of Pending Component 3: Island Waste Open - Single Stage - One Waste Management IDA / D1990 Prior Request for Bids 700,000.00 0.00 Implementati 2020-06-15 2020-06-20 2020-08-01 2020-08-22 2020-09-19 2021-07-16 Management Systems International Envelope Equipment to Islands of on

Zone IV & V

MV-MEE-158475-GO-RFB / Pending Supply and Delivery of Component 3: Island Waste Single Stage - One IDA / D1990 Post Request for Bids Open - National 30,100.00 0.00 Implementati 2020-04-15 2020-04-20 2020-05-18 2020-06-08 2020-06-29 2020-10-27 Weighing Scales for IWMCS Management Systems Envelope on of Zone IV & V

MV-MEE-160637-GO-RFB / Pending Component 2: Regional Open - Single Stage - One Supply and Delivery of IDA / D1990 Prior Request for Bids 750,000.00 0.00 Implementati 2020-03-05 2020-03-08 2020-04-05 2020-04-15 2020-05-13 2020-12-09 Waste Management Systems International Envelope Landing Craft on

MV-MEE-160642-GO-RFB / Pending Supply, Installation and Component 2: Regional Open - Single Stage - One IDA / D1990 Prior Request for Bids 500,000.00 0.00 Implementati 2020-03-05 2020-03-08 2020-04-05 2020-04-15 2020-05-13 2020-11-09 Commissioning of a Waste Waste Management Systems International Envelope on Sorting line

Pending MV-MEE-160655-GO-RFQ / Component 4: Project Request for Single Stage - One IDA / D1990 Post Limited 5,000.00 0.00 Implementati 2020-03-08 2020-04-19 2020-05-19 Furniture for PMU Management Quotations Envelope on

NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

MV-MEE-153553-NC-DIR / Installation and Pending Component 2: Regional commissioning support of IDA / D1990 Post Direct Selection Direct 6,000.00 0.00 Implementati 2020-02-02 2020-02-07 2020-02-19 2020-03-04 Waste Management Systems CEMS and Analyzer and on delivery of training.

CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

MV-MEE-25845-CS-QCBS / Feasibility Study for a Regional Waste Management Component 3: Island Waste Quality And Cost- Open - IDA / D1990 Prior 200,000.00 265,200.34 Signed 2017-08-23 2017-08-24 2017-08-24 2017-08-24 2017-09-21 2018-01-23 2017-10-19 2018-03-12 2017-11-02 2017-12-07 2018-09-26 2018-01-04 2018-12-10 2018-09-01 System in Zone IV (Meemu, Management Systems Based Selection International Faafu and Dhaalu Atoll) and V (Thaa and )

MV-MEE-46609-CS-LCS / Component 4: Project Least Cost IDA / D1990 Post Open - National 15,000.00 0.00 Under Review 2018-02-12 2018-03-15 2018-02-26 2018-03-12 2018-06-03 2018-03-26 2018-06-24 2018-04-02 2018-07-05 2018-04-23 2018-07-14 2018-05-14 2024-01-08 Services of Internal Auditor Management Selection

MV-MEE-60156-CS-CQS / Institutional Needs Component 1: National Solid Consultant Assessment and Developing IDA / D1990 Waste Management Strategy Post Qualification Open - National 25,000.00 0.00 Canceled 2018-05-01 2018-05-15 2018-06-05 2018-06-12 2018-07-17 2018-10-15 a Capacity Building Plan for and Policy Selection Waste Management Corporation Ltd.

Page 7 MV-MEE-80796-CS-CQS / Preparation of Environmental and Social Impact Component 1: National Solid Consultant Assessment for the proposed IDA / D1990 Waste Management Strategy Post Qualification Limited 20,000.00 22,004.25 Signed 2018-10-04 2018-10-02 2018-10-11 2018-10-21 2018-10-17 2018-11-14 2018-11-01 2018-11-26 2018-12-25 upgrading of infrastructure and Policy Selection at Regional Waste Management Facility - Zone 2

MV-MEE-110477-CS-QCBS / Revision of Waste Component 1: National Solid Quality And Cost- Management Policy and IDA / D1990 Waste Management Strategy Post Open - National 75,000.00 0.00 Under Review 2019-04-16 2019-04-15 2019-04-30 2019-05-12 2019-06-02 2019-06-09 2019-06-19 2019-07-24 2019-12-21 Based Selection Preparation of Waste and Policy Management Strategy

MV-MEE-136399-CS-CQS / Selection of Consultant to undertake the preparation of Environmental and Social Consultant Management Plans for the Component 3: Island Waste IDA / D1990 Post Qualification Open - National 20,000.00 0.00 Canceled 2020-01-05 2020-01-10 2020-02-23 2020-03-24 2020-04-28 2020-10-25 establishment of Island Management Systems Selection Waste Management Centre in F. Feeali, M. Kolhufushi, Th. Guraidhoo & Th. Hirilandhoo

MV-MEE-136401-CS-CQS / Selection of Consultant to undertake the preparation of Environmental and Social Consultant Management Plans for the Component 3: Island Waste IDA / D1990 Post Qualification Open - National 20,000.00 0.00 Canceled 2020-01-05 2020-01-10 2020-02-23 2020-03-24 2020-04-28 2020-10-25 establishment of Island Management Systems Selection Waste Management Centre in Dh. Maaenboodhoo, M. Dhigarru, L. & L.

MV-MEE-128592-CS-CQS / Selection of a Consultancy Consultant Firm to prepare the detailed Component 2: Regional IDA / D1990 Post Qualification Open - National 50,000.00 0.00 Canceled 2019-08-25 2019-08-27 2019-09-15 2019-09-08 2019-10-29 2019-11-28 2020-01-02 2020-06-30 design for Fire Protection Waste Management Systems Selection System in R. Vandhoo and Supervision Consultancy

MV-MEE-142985-CS-CQS / Selection of a Consultant to Consultant prepare the detailed design Component 2: Regional Pending IDA / D1990 Post Qualification Open - National 50,000.00 0.00 2020-02-27 2020-03-19 2020-04-09 2020-04-16 2020-05-10 2021-02-04 for Fire Protection System Waste Management Systems Implementation Selection in R. Vandhoo and Supervision

MV-MEE-158432-CS-CQS / Component 1: National Solid Consultant Pending Designing of a National IDA / D1990 Waste Management Strategy Post Qualification Open - National 100,000.00 0.00 2020-02-26 2020-03-04 2020-04-15 2020-04-29 2020-05-20 2020-11-16 Implementation Solid Waste Tracking System and Policy Selection

MV-MEE-158433-CS-CQS / Augmentation of Curriculum Component 1: National Solid Consultant Pending for Bachelor of IDA / D1990 Waste Management Strategy Post Qualification Open - National 25,000.00 0.00 2020-02-25 2020-03-10 2020-03-24 2020-04-14 2020-05-05 2020-11-01 Implementation Environmental Management and Policy Selection Programme, MNU

MV-MEE-160554-CS-CQS / Component 1: National Solid Consultant Study on the Quantum and Open - Pending IDA / D1990 Waste Management Strategy Post Qualification 100,000.00 0.00 2020-03-15 2020-03-29 2020-04-21 2020-05-12 2020-06-02 2020-11-29 Collection of User-fee and International Implementation and Policy Selection Tariffs for SWM

MV-MEE-160547-CS-CQS / Component 1: National Solid Consultant Review of Nation SWM Open - Pending IDA / D1990 Waste Management Strategy Post Qualification 175,000.00 0.00 2020-02-27 2020-03-05 2020-04-09 2020-04-30 2020-05-28 2021-01-03 Policy and formulation of a International Implementation and Policy Selection National SWM Strategy

Page 8 MV-MEE-158446-CS-CQS / Consultant Detailed Design & Work Component 2: Regional Pending IDA / D1990 Post Qualification Open - National 150,000.00 0.00 2020-03-10 2020-04-07 2020-04-28 2020-05-12 2020-06-09 2022-12-26 Supervision of the RWMF - Waste Management Systems Implementation Selection Zone IV/V

MV-MEE-158447-CS-CQS / Consultant ESIA for the Proposed Component 2: Regional Pending IDA / D1990 Post Qualification Open - National 100,000.00 0.00 2020-04-15 2020-05-13 2020-06-03 2020-06-10 2020-07-08 2021-01-04 Regional Waste Management Waste Management Systems Implementation Selection System - Zone IV & V

MV-MEE-158464-CS-CQS / Consultant ESIAs/ ESMPs for Island Component 3: Island Waste Pending IDA / D1990 Post Qualification Open - National 99,000.00 0.00 2020-03-01 2020-03-22 2020-04-12 2020-04-26 2020-05-24 2020-11-20 Waste Management Centres Management Systems Implementation Selection of Zone IV & V

MV-MEE-158465-CS-CQS / Consultant Design and Works Component 3: Island Waste Pending IDA / D1990 Post Qualification Open - National 100,000.00 0.00 2020-03-01 2020-03-15 2020-03-29 2020-04-05 2020-04-26 2021-10-18 Supervision Consultant for Management Systems Implementation Selection IWMCs of Zone IV & V

MV-MEE-158466-CS-CQS / Consultant Development of Information, Component 3: Island Waste Pending IDA / D1990 Post Qualification Open - National 100,000.00 0.00 2020-03-01 2020-03-29 2020-04-19 2020-05-03 2020-05-31 2020-11-27 Education and Management Systems Implementation Selection Communication Toolkit

INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

MV-MEE-37124-CS-INDV / Component 1: National Solid Individual Consultancy for Preparing IDA / D1990 Waste Management Strategy Prior Consultant Direct 24,000.00 29,350.00 Under Review 2017-11-26 2018-01-21 2017-12-06 2018-02-26 2017-12-13 2018-03-21 2017-12-27 2018-03-21 2018-02-10 the Operations Plan of and Policy Selection Vandhoo RWMF (Zone 2)

MV-MEE-37110-CS-INDV / Individual Component 4: Project Financial Management IDA / D1990 Prior Consultant Direct 90,000.00 124,695.98 Signed 2017-11-21 2017-11-24 2017-11-27 2017-12-10 2017-12-04 2018-02-13 2017-12-16 2018-02-15 2020-12-15 Management Specialist for PMU Selection

Individual MV-MEE-39091-CS-INDV / Component 4: Project IDA / D1990 Post Consultant Open 90,000.00 90,000.00 Signed 2017-12-28 2018-02-01 2018-01-13 2018-03-04 2018-01-15 2018-03-04 2018-02-01 2018-03-19 2021-01-17 Civil Engineer for PMU Management Selection

MV-MEE-41149-CS-INDV / Individual Component 4: Project Monitoring and Evaluation IDA / D1990 Post Consultant Open 90,000.00 0.00 Under Review 2017-12-31 2018-08-01 2018-01-17 2018-01-22 2018-02-15 2021-01-30 Management Specialist for PMU Selection

MV-MEE-41150-CS-INDV / Individual Component 4: Project Communications Specialist IDA / D1990 Post Consultant Open 90,000.00 81,500.64 Signed 2018-01-04 2018-03-12 2018-01-28 2018-05-29 2018-01-31 2018-05-29 2018-02-15 2018-06-16 2021-01-30 Management for PMU Selection

MV-MEE-48404-CS-CDS / Component 4: Project Procurement Specialist for IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 Under Review 2018-02-14 2018-02-22 2018-02-28 2021-02-28 Management PMU

MV-MEE-48407-CS-CDS / Environmental and Social Component 4: Project IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 Canceled 2018-02-15 2018-02-26 2018-02-22 2018-02-28 2021-02-28 Safeguards Specialist for Management

PMU

MV-MEE-53309-CS-INDV / Component 1: National Solid Individual Preparation of EMPs for 6 IDA / D1990 Waste Management Strategy Post Consultant Open 15,000.00 11,966.36 Signed 2018-03-18 2018-04-10 2018-04-04 2018-05-15 2018-04-11 2018-05-15 2018-05-09 2018-06-11 2018-07-08 Selected Island Waste and Policy Selection Management Centres

Page 9 MV-MEE-53794-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-03-19 2018-08-06 2018-04-16 2018-10-04 2018-04-23 2018-10-17 2018-05-14 2018-10-21 2021-08-16 for PMU Component Selection

MV-MEE-54013-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-03-19 2018-08-06 2018-04-07 2018-11-22 2018-04-14 2018-12-12 2018-05-12 2018-12-16 2021-08-14 for PMU Component Selection

MV-MEE-64614-CS-INDV / Institutional Needs Component 1: National Solid Individual Assessment of Waste IDA / D1990 Waste Management Strategy Post Consultant Open 25,000.00 0.00 Under Review 2018-06-03 2018-06-06 2018-07-02 2018-07-16 2018-08-13 2018-10-12 Management Corporation and Policy Selection Ltd.

MV-MEE-79643-CS-INDV / Services of a Naval Individual Architect/Engineer for the Component 4: Project IDA / D1990 Post Consultant Limited 35,000.00 29,922.38 Signed 2018-09-28 2018-10-08 2018-09-30 2018-10-23 2018-10-15 2018-10-23 2018-11-01 2019-01-15 2019-12-31 supervision of marine vessel Management Selection construction projects under MCEP

MV-MEE-81147-CS-INDV / Individual Component 4: Project Financial Management IDA / D1990 Post Consultant Open 54,000.00 46,944.37 Signed 2018-10-08 2018-08-07 2018-10-14 2018-10-08 2018-10-21 2018-10-29 2018-11-01 2018-11-16 2021-10-31 Management Assistant Selection

MV-MEE-81381-CS-INDV / Preparation of the detailed master plan layout and Individual detailed design of required Component 2: Regional IDA / D1990 Post Consultant Limited 20,000.00 24,655.90 Signed 2018-10-18 2018-10-04 2018-10-21 2018-10-10 2018-10-28 2019-01-10 2018-11-18 2018-11-22 2019-01-02 additional infrastructure for Waste Management Systems Selection the Regional Waste Management Facility of Zone- 2

MV-MEE-87721-CS-INDV / Component 5: Contingent Individual Assistant Project Coordinator IDA / D1990 Emergency Response Post Consultant Open 54,000.00 46,944.37 Signed 2018-11-22 2018-08-06 2018-11-22 2018-11-22 2018-12-10 2018-12-11 2018-12-16 2019-01-16 2022-03-20 for PMU Component Selection

MV-MEE-48421-CS-CDS / Component 4: Project IDA / D1990 Prior Direct Selection Direct 108,000.00 0.00 Canceled 2018-02-15 2018-02-28 2018-02-23 2018-02-28 2021-02-28 Project Manager for PMU Management

Individual MV-MEE-93341-CS-INDV / Component 4: Project Under IDA / D1990 Post Consultant Open 48,000.00 0.00 2019-02-10 2018-11-14 2019-03-08 2019-03-22 2019-04-19 2021-04-19 Project Coordinator (Zone 2) Management Implementation Selection

MV-MEE-80820-CS-INDV / Individual Component 4: Project Project Coordinator (Zone IDA / D1990 Post Consultant Open 90,000.00 81,500.64 Signed 2019-05-17 2018-07-23 2019-05-30 2018-10-04 2019-06-02 2018-10-18 2019-06-19 2018-10-21 2022-06-18 Management 4&5) for PMU Selection

MV-MEE-83452-CS-CDS / Operations Specialist for Component 2: Regional IDA / D1990 Prior Direct Selection Direct 120,000.00 98,530.04 Signed 2019-05-10 2019-05-19 2019-05-15 2019-05-27 2019-06-01 2019-06-07 2020-05-31 Vandhoo RWMF (12 month Waste Management Systems assignment)

MV-MEE-83995-CS-CDS / Incinerator Specialist for Component 2: Regional IDA / D1990 Prior Direct Selection Direct 90,000.00 0.00 Canceled 2019-05-15 2019-05-25 2019-06-15 2020-04-10 Vandhoo RWMF (10 months Waste Management Systems period)

MV-MEE-113875-CS-INDV / Development of a Component 1: National Solid Individual Under Management Information IDA / D1990 Waste Management Strategy Post Consultant Limited 7,500.00 0.00 2019-05-10 2019-05-19 2019-05-13 2019-06-03 2019-05-16 2019-06-01 2019-07-01 Implementation System (MIS) Database for and Policy Selection Solid Waste Management

MV-MEE-113891-CS-INDV / Individual Consultancy Services for Component 4: Project IDA / D1990 Post Consultant Limited 15,000.00 14,961.19 Signed 2019-05-10 2019-05-19 2019-05-13 2019-05-24 2019-05-16 2019-05-29 2019-06-02 2019-06-18 2019-07-02 Undertaking an Independent Management Selection Evaluation of MCEP

Page 10 MV-MEE-115528-CS-INDV / Individual Component 2: Regional Fire Fighting Design and IDA / D1990 Post Consultant Limited 50,000.00 0.00 Canceled 2019-05-26 2019-06-30 2019-05-29 2019-07-31 2019-06-01 2019-06-18 2019-08-17 Waste Management Systems Supervision Consultant Selection

MV-MEE-126235-CS-INDV / Component 1: National Solid Individual Consultancy for Strategic IDA / D1990 Waste Management Strategy Post Consultant Open 4,000.00 4,527.81 Signed 2019-08-06 2019-08-20 2019-08-27 2019-09-01 2019-09-01 2019-09-02 2019-10-06 2019-09-15 2019-10-12 planning of Single use and Policy Selection plastic phase-out Plan

MV-MEE-133400-CS-INDV / Preparation of ESMP for Component 1: National Solid Individual upgrading of IWMCs in 2 IDA / D1990 Waste Management Strategy Post Consultant Open 10,000.00 0.00 Canceled 2019-12-15 2020-01-01 2020-01-08 2020-02-05 2020-04-05 selected islands of Zone 2 - and Policy Selection (B. Eydhafushi & R. Maakurathu)

MV-MEE-48441-CS-INDV / Augmentation of Curriculum Component 1: National Solid Individual Pending for Environmental IDA / D1990 Waste Management Strategy Post Consultant Open 25,000.00 0.00 2020-04-30 2020-06-11 2020-06-25 2020-07-23 2020-10-21 Implementation Management Diploma/Degree and Policy Selection Program of MNU

MV-MEE-158444-CS-INDV / Component 1: National Solid Individual International Advisor on Pending IDA / D1990 Waste Management Strategy Prior Consultant Open 400,000.00 0.00 2020-02-29 2020-04-16 2020-05-07 2020-06-04 2023-09-17 SWM (to be based in Waste Implementation and Policy Selection Department, MoE)

MV-MEE-159364-CS-INDV / Services of a Naval Individual Architect / Engineer for the Component 4: Project Pending IDA / D1990 Post Consultant Limited 30,000.00 0.00 2020-02-27 2020-03-05 2020-03-19 2020-04-05 2021-04-04 supervision of marine vessel Management Implementation Selection construction projects under MCEP

Page 11