Capitol Boulevard Plan Infrastructure Projects Update Chat Ribbon and Poll

2

City of Tumwater Foundation To Build On

 Corridor Plan  Feasibility Study • 2011 to 2014 • 2013 to 2019 • Cost - $235,000 • Cost - $745,000

3

City of Tumwater Transportation Projects Derived from Plan

 Feasibility Study  Interstate 5 / Trosper Rd / Capitol Blvd Reconfiguration  Capitol Blvd, M St to Israel Rd Design  N-S Connector  T  X Street Roundabout  Dennis Street Roundabout  Access Control, Mutlimodal Improvements, and Calming

4

City of Tumwater Interstate 5 / Trosper Rd / Capitol Blvd

 Total project cost - $14 million  Funds . State - $6.6 million . Transportation CFP - $6 million . Utilities - $1.4 million  Schedule . Design – 2018 to 2021 . Right of Way – 2019 to 2021 . Construction – 2021 to 2023

5

City of Tumwater It is going to be frustrating…

6

City of Tumwater Capitol Blvd, M St to Israel Rd Design

 Design Cost - $1.5 million  Five separate “bite-sized” projects: • N-S Connector Road • T Street Roundabout • X Street Roundabout • Dennis Street Roundabout • Access Control, Mutlimodal, and  Funds • State Grant - $1,032,000 • Transportation CFP - $168,500 • Utilities - $252,000  Schedule - 2021 to 2022 7

City of Tumwater North-South Connector Road

 Total project cost - $2.5 million  Funds • Transportation CFP - $950,000 • Unfunded - $1,550,000  Schedule • Design – 2021 to 2022 • Right of Way – 2019 to unknown • Construction – 2026

8

City of Tumwater T Street Roundabout

 Total project cost - $4.9 million  Funds • Unfunded - $4.9 million  Schedule • Design – 2021 to 2022 (60%) • Right of Way – To be determined • Construction – To be determined

9

City of Tumwater X Street Roundabout

 Total project cost - $4.7 million  Funds • Federal - $866,000 • Transportation CFP - $1,640,000 • Unfunded - $2,000,000  Schedule • Design – 2018 to 2021 • Right of Way – 2023 to 2025 • Construction – 2026 10

City of Tumwater Dennis Street Roundabout

 Total project cost - $2.9 million  Funds • Unfunded  Schedule • Design – 2021 to 2022 (60%) • Right of Way – To be determined • Construction – To be determined

11

City of Tumwater Access Control, Multimodal Improvements, and Traffic Calming

 Total project cost - $9.2 million  Funds • To be determined  Schedule • Design – 2021 to 2022 (60%) • Right of Way – To be determined • Construction – To be determined

12

City of Tumwater Summary

13

City of Tumwater Thank You Brandon Hicks, PE, Director Transportation & Engineering (360) 754-4140 [email protected]

Bill Lindauer, PE, Engineering Services Manager Transportation & Engineering (360) 754-4140 [email protected]

Mike Matlock, AICP, Director Community Development (360) 754-4180 [email protected] 14

City of Tumwater Coming Soon… Old Hwy 99 Corridor

E Street Connection

Tumwater Blvd

15

City of Tumwater Everywhere! Why?

 According to the Insurance Institute of Safety, there are many safety benefits associated with the modern roundabout: • 90 percent reduction in fatal crashes • 75 percent reduction in injury crashes • 30-40 percent reduction in pedestrian crashes • 10 percent reduction in bicycle crashes • 30-50 percent increase in traffic capacity  There are other benefits to roundabouts, including • reduction in fuel use and pollution • no signal equipment to install and repair quieter neighborhoods 16 •

City of Tumwater