Presenting PIANC The World Association for Waterborne Transport Infrastructure
Presentation by
James Andrew Smith BSc(Hons) MSc CEng CMarEng MICE MIMarEST Principal Engineer/ Head of Bristol Office Beckett Rankine at the occasion of AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
• Twelve Quays Terminal – Birkenhead
• Western Bank of the River Mersey
• North West England
Owned by:
Credit: Google Earth Operated by:
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
History
• Land part of interconnected docklands • Alfred Basin
• Great Float Rankine
• Designed by Transmarine Beckett :
• Terminal first opened in 2002 Credit
Arrangement
• Pontoon Ro-Ro Berth
• Two berths (North & South)
• Monopile Dolphins
• Fixed Bridge & Bankseat
• 4 Point Torsionally Flexible Linkspan
• Three lane HA/HRo AGA 2021 / 26 & 27 May 2021 Credit: David Byrne Twelve Quays – Two Levels Project
Credit: Stena Line Stena E-Flexer Class
• Longer and heavier than RoPax
• Double Deck: • Faster loading & Greater capacity • Slower sailing = lower emissions • Same Schedule
• Ships design/construction run in Credit: Farrans parallel with berth upgrade
Main Modifications Required
• Upper level loading ramp
• Berth Interface • Stern ramp wider and higher
• Berthing and mooring modifications
• Berth to remain operational!
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Concept & Feasibility Design & Build Contract
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Surveys and Studies
• Topographic & Bathymetric • Utilities & Services • Historical Boreholes • Desktop UXO (Basic and Advanced)
• Laser Scanning • Photographic Surveys • Internal and External UT surveys
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Pontoon Internal Surveys
• Peel Ports commissioned survey in 2016
• All compartments opened but berth remained operational
• Ballast tanks kept full limiting inspection
• Dry tanks fully inspected
• General conclusions:
• Ballasted Tanks: “…good condition and all coatings are showing no signs of significant deterioration.”.
• Dry Tanks: “…suffering from breakdown of coating...”.
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Weld and Joint Inspections
• Visual and MPI inspection of all welded joints on Linkspan
• Torsionally Flexible 4No. Point Support Linkspan
• All welds/joints were free of cracks – remarkable achievement
• Linkspan only required preparation and painting
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Constructability/Installation Assessments
• One berth to remain operational
• Upper Ramp required full possession
• Phase plans developed for each structure
• Lift plans assumed Lara 1 (Mersey Mammoth)
Credit: Jörn Prestien
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Credit: Farrans AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
AGA 2021 / 26 & 27 May 2021 Credit: Farrans Twelve Quays – Two Levels Project
Run-off – Single Level vs Double Level
• Single tier linkspans water runs to Bankseat or drainage points
• Runoff typically collected by interceptor or returns to River or Sea
• Two-tier linkspan water runs to seaward bearings - cascading onto lower deck
• Minor issue to drivers – Big issue to Operators!
• Issue simply resolved with collection trough and down pipe
Credit: Farrans AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Queensway Tunnel Interface
• Ø14m by 3.24km long tunnel – 4No. Lanes
• ~50m from new piles to tunnel
• Existing pile already closer to tunnel
• Plans shared with Mersey Travel (Operator)
• Bored socket piles suit geology and favourable vibration compared to Driving
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Ships Stern Ramp Modifications
• Revised Dwg’s issued during fabrication
• Ships ramp modifications:
• Length – Reduced from 2445mm to 2315mm
• Profile – From flat to new knuckles added
• Hinge – Relocated from top to bottom
• Width – Overall width increased
Implications
• Stop Fender – Already being relocated
• Existing Ramp – No longer compliant BS6349–8
AGA 2021 / 26 & 27 May 2021 Credit: Stena Line Twelve Quays – Two Levels Project
Ships Stern Ramp Modifications
• Options: • New pontoon ramp – High Cost / Delays
• Alter ships ramp – High Cost / Programme Delays
• Bespoke filler piece
• Conforms with BS 6349–8
• Relatively Low Cost
• Retro-fitted
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Upper Linkspan Tolerance and Point Loads
• Large point loads generated by new upper ramp columns
• Internal Stiffeners sufficient but tolerances required
• Ravestein opt for new over-sized 50mm landing plates
• Greater Tolerance
• Reduced confined space works
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
AGA 2021 / 26 & 27 May 2021 Credit: Farrans Twelve Quays – Two Levels Project
AGA 2021 / 26 & 27 May 2021 Credit: Farrans Twelve Quays – Two Levels Project
Pontoon Internal Painting and Fatigue Cracking
• Ballast Tanks drained to enable blasting and painting
• Discovery of large fatigue cracks – Flange and Webs
• Repairs carried out previously but unrecorded history
• Ongoing study to assess the root cause – Fatigue Modelling
• Temp repair using ‘Vee-and-Weld’ method.
Credit: Farrans AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Ramp Modification and Cracking
• Ramp removed for painting and modification
• Cracks to 4No. ‘Sniped’ stiffeners
• Ongoing study to assess the root cause
• Temp repair using ‘Vee-and-Weld’ method
Credit: Farrans
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
Credit: Farrans
AGA 2021 / 26 & 27 May 2021 Twelve Quays – Two Levels Project
AGA 2021 / 26 & 27 May 2021 Credit: Farrans THANK YOU
AGA 2021 / 26 & 27 May 2021 Q&A
AGA 2021 / 26 & 27 May 2021