1 Bokaro 10 21.240 472.85 315.25 788.10 84.74 (0 , 2 , 5 , 18 , 25)

2 Chatra 2 6.005 167.23 111.50 278.73 32.71 (0 , 1 , 0 , 2 , 3)

3 6 14.800 430.41 286.93 717.34 63.98 (1 , 5 , 1 , 0 , 7)

4 3 7.880 247.35 164.91 412.26 33.38 (0 , 1 , 3 , 0 , 4)

5 East Singhbhum 13 31.280 863.24 575.47 1,438.71 132.96 (0 , 5 , 8 , 8 , 21)

6 Garhwa 10 33.546 1,012.57 675.04 1,687.61 337.58 (1 , 6 , 3 , 2 , 12)

7 1 2.100 54.24 36.16 90.40 9.39 (0 , 0 , 1 , 1 , 2)

8 11 23.680 568.41 378.93 947.34 98.80 (1 , 11 , 4 , 4 , 20)

9 Gumla 7 17.380 450.13 300.09 750.22 124.21 (1 , 1 , 3 , 14 , 19)

10 Hazaribagh 31 87.396 2,092.60 1,395.08 3,487.68 367.49 (1 , 3 , 19 , 11 , 34)

11 8 15.270 436.17 290.77 726.94 72.40 (0 , 5 , 3 , 0 , 8)

12 Khunti 6 13.496 351.68 234.47 586.15 63.97 (1 , 2 , 3 , 3 , 9)

13 Koderma 2 9.451 239.62 159.75 399.37 39.50 (0 , 1 , 2 , 4 , 7)

14 Latehar 7 57.400 1,422.48 948.32 2,370.80 234.90 (0 , 6 , 1 , 2 , 9)

15 3 6.920 201.23 134.17 335.40 35.91 (0 , 0 , 3 , 0 , 3)

16 Palamau 8 17.050 413.69 275.80 689.49 77.44 (0 , 2 , 4 , 5 , 11)

17 Ramgarh 2 2.896 84.45 56.30 140.75 11.25 (1 , 1 , 0 , 0 , 2)

18 4 7.955 210.58 140.40 350.98 34.18 (1 , 2 , 2 , 1 , 6)

19 5 12.720 350.92 233.95 584.87 44.20 (1 , 1 , 5 , 0 , 7)

20 Saraikela Kharsawan 3 6.787 149.28 99.52 248.80 23.43 (0 , 2 , 7 , 2 , 11)

21 Simdega 1 2.700 77.44 51.63 129.07 13.30 (0 , 0 , 1 , 1 , 2)

22 West Singhbhum 7 23.645 606.85 404.58 1,011.43 103.37 (0 , 1 , 10 , 4 , 15)

Roads Total 150 421.597 10,903.42 7,269.02 18,172.44 2,039.10 (9 , 58 , 88 , 82 , 237)

Long Span Bridge Proposals

1 Palamau 1 43.800 86.32 57.54 143.86 1.97 -

Bridges Total 1 43.800 86.32 57.54 143.86 1.97 -

Grand Total 151 Total Road 10,989.74 7,326.56 18,316.30 2,041.07 (9 , 58 , 88 , 82 , 237) Length:421.597 Kms Total LSB Length:43.800 Mtrs

Page 1 of 1 Generated On : 28/03/2017 11:58 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

State : Jharkhand Sanction Year : 2016-2017 Batch : 4 Collaboration : Regular PMGSY Note : All Costs are in Lakhs and Lengths are in Kms.

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Road Proposals

District- Bokaro

Block- Bermo

1 L074 L074-PWD Road to Manjhi New Zycosoil 1.160 3.750 Complete 2 28.41 18.94 47.35 4.45 (0 , 0 , 0 , 2 , 2) Tola Rajabera (VR74) Nanotechnolog y 2 L071 L071-Ganju Basti to New -- 1.698 3.750 Complete 4 38.90 25.94 64.84 6.93 (0 , 0 , 1 , 0 , 1) Nawatand (VR71) Block Bermo Total 2.858 6 67.31 44.88 112.19 11.38 (0 , 0 , 1 , 2 , 3)

Block- Chandankiyari

3 T09 T09-Mahal to Silphor Road Upgarde Roller 2.702 3.750 Complete 8 66.68 44.45 111.13 10.09 (0 , 1 , 3 , 2 , 6) Compacted Concrete Pavement Block Chandankiyari Total 2.702 8 66.68 44.45 111.13 10.09 (0 , 1 , 3 , 2 , 6)

Block- Gomia

4 L061 L061-Keri to Matakamtoli New Zycosoil 1.900 3.750 Complete 5 35.77 23.85 59.62 8.66 (0 , 0 , 0 , 6 , 6) (VR61) Nanotechnolog y Block Gomia Total 1.900 5 35.77 23.85 59.62 8.66 (0 , 0 , 0 , 6 , 6)

Block- Jaridhi

5 L050 L050-Dondra road Lipu more New Roller 1.500 3.750 Complete 4 36.84 24.56 61.40 7.44 (0 , 1 , 0 , 0 , 1) to Lipu gram (VR50) Compacted Concrete Pavement

Page 1 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

6 L051 L051-Banchas REO road to New Roller 2.700 3.750 Complete 6 49.32 32.88 82.20 8.85 (0 , 0 , 1 , 0 , 1) Pokharghati Simaldih (VR51) Compacted Concrete Pavement Block Jaridhi Total 4.200 10 86.16 57.44 143.60 16.29 (0 , 1 , 1 , 0 , 2)

Block- Kasmar

7 L042 L042-Bemrotanr REO road to New -- 1.500 3.750 Complete 2 24.53 16.35 40.88 5.71 (0 , 0 , 0 , 2 , 2) Ghirgarwa (VR42) 8 L040 L040-Dhadhakiya REO road New Roller 3.230 3.750 Complete 3 90.43 60.29 150.72 12.41 (0 , 0 , 0 , 2 , 2) to Kochagora (VR40) Compacted Concrete Pavement Block Kasmar Total 4.730 5 114.96 76.64 191.60 18.11 (0 , 0 , 0 , 4 , 4)

Block- Nawadih

9 L067 L067-Pilpilo Road to Khardin New -- 2.200 3.750 Complete 3 40.81 27.21 68.02 9.01 (0 , 0 , 0 , 2 , 2) Kathaldih (VR67) Block Nawadih Total 2.200 3 40.81 27.21 68.02 9.01 (0 , 0 , 0 , 2 , 2)

Block- Petarwar

10 L051 L051-Mayapur REO road New -- 2.650 3.750 Complete 2 61.16 40.78 101.94 11.20 (0 , 0 , 0 , 2 , 2) Sagarulta to Jillingtand (VR51) Block Petarwar Total 2.650 2 61.16 40.78 101.94 11.20 (0 , 0 , 0 , 2 , 2)

District Bokaro Total 21.240 39 472.85 315.25 788.10 84.74 (0 , 2 , 5 , 18 , 25) District- Chatra

Page 2 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Pathal Gadda

11 L025 L025-PATHALGADDA TO New -- 2.000 3.750 Complete 6 52.88 35.26 88.14 17.24 (0 , 0 , 0 , 2 , 2) SHEETALPUR (VR25) Block Pathal Gadda Total 2.000 6 52.88 35.26 88.14 17.24 (0 , 0 , 0 , 2 , 2)

Block- Pratappur

12 L026 L026-KODWARIA TO Upgarde -- 4.005 3.750 Complete 13 114.35 76.24 190.59 15.47 (0 , 1 , 0 , 0 , 1) ASHKUL Block Pratappur Total 4.005 13 114.35 76.24 190.59 15.47 (0 , 1 , 0 , 0 , 1)

District Chatra Total 6.005 19 167.23 111.50 278.73 32.71 (0 , 1 , 0 , 2 , 3)

District- Deoghar

Block- Karon

13 L035 L035-Madankatta to New Roller 3.500 3.750 Complete 7 92.55 61.70 154.25 13.75 (1 , 0 , 0 , 0 , 1) Birangariya Road Compacted Concrete Pavement Block Karon Total 3.500 7 92.55 61.70 154.25 13.75 (1 , 0 , 0 , 0 , 1)

Block- Madhupur

14 L039 L039-Rajdaha to Arjunka New -- 1.700 3.750 Complete 3 54.84 36.56 91.40 7.98 (0 , 1 , 0 , 0 , 1)

Block Madhupur Total 1.700 3 54.84 36.56 91.40 7.98 (0 , 1 , 0 , 0 , 1)

Block- Mohanpur

15 L054 L054-Khijuriya to Dumma New -- 2.350 3.750 Complete 9 68.60 45.73 114.33 11.38 (0 , 1 , 0 , 0 , 1)

Block Mohanpur Total 2.350 9 68.60 45.73 114.33 11.38 (0 , 1 , 0 , 0 , 1)

Page 3 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Palajori

16 L046 L046-Talgharha to New -- 1.575 3.750 Complete 2 45.88 30.59 76.47 7.63 (0 , 1 , 0 , 0 , 1) Chandnawadih 17 L039 L039-Khaga to Sirsa New -- 4.500 3.750 Complete 4 134.65 89.76 224.41 16.66 (0 , 1 , 1 , 0 , 2)

Block Palajori Total 6.075 6 180.53 120.35 300.88 24.29 (0 , 2 , 1 , 0 , 3)

Block- Sarwan

18 L047 L047-Beltekri to Ratura New -- 1.175 3.750 Complete 4 33.89 22.59 56.48 6.58 (0 , 1 , 0 , 0 , 1)

Block Sarwan Total 1.175 4 33.89 22.59 56.48 6.58 (0 , 1 , 0 , 0 , 1)

District Deoghar Total 14.800 29 430.41 286.93 717.34 63.98 (1 , 5 , 1 , 0 , 7)

District- Dumka

Block-

19 L093 L093-Latapakar More to New -- 1.410 3.750 Complete 4 49.55 33.04 82.59 6.27 (0 , 1 , 0 , 0 , 1) Latapakar (VR93) 20 L118 L118-Basbutiya to Amarpani New -- 2.320 3.750 Complete 4 74.07 49.38 123.45 9.65 (0 , 0 , 1 , 0 , 1) (VR118) Block Jarmundi Total 3.730 8 123.62 82.42 206.04 15.92 (0 , 1 , 1 , 0 , 2)

Block- Saraiyahaat

21 L025 L025-Ranga More to New -- 4.150 3.750 Complete 14 123.73 82.49 206.22 17.46 (0 , 0 , 2 , 0 , 2) Kairabani Block Saraiyahaat Total 4.150 14 123.73 82.49 206.22 17.46 (0 , 0 , 2 , 0 , 2)

District Dumka Total 7.880 22 247.35 164.91 412.26 33.38 (0 , 1 , 3 , 0 , 4)

District- East Singhbhum

Page 4 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Bahragora

22 T07 T07-NH33 Bahragora to New Roller 1.200 3.750 Complete 5 32.78 21.85 54.63 6.61 (0 , 0 , 1 , 0 , 1) Pathra Compacted Concrete Pavement 23 L077 L077-NH33 to Puranapani New -- 3.700 3.750 Complete 7 105.74 70.49 176.23 14.03 (0 , 0 , 1 , 0 , 1)

Block Bahragora Total 4.900 12 138.52 92.34 230.86 20.64 (0 , 0 , 2 , 0 , 2)

Block- Chakulia

24 L068 L068-Sardiha Road to New Roller 1.750 3.750 Complete 8 50.86 33.90 84.76 8.36 (0 , 1 , 0 , 1 , 2) Kashiya Compacted Concrete Pavement 25 L049 L049-Khandandih Road to New Roller 1.100 3.750 Complete 4 32.14 21.42 53.56 6.41 (0 , 1 , 0 , 2 , 3) Sunsuniya Compacted Concrete Pavement 26 L028 L028-Sisakhun to New Roller 1.900 3.750 Complete 5 45.71 30.47 76.18 8.67 (0 , 1 , 0 , 2 , 3) Raghunathpur Compacted Concrete Pavement 27 L050 L050-Pucca Road to New Roller 2.500 3.750 Complete 5 72.40 48.26 120.66 10.42 (0 , 1 , 0 , 1 , 2) Baranata Compacted Concrete Pavement 28 L027 L027-Luabera to Joram New -- 5.850 3.750 Complete 19 171.65 114.44 286.09 20.90 (0 , 0 , 1 , 0 , 1)

29 L075 L075-Dakui More to New -- 1.900 3.750 Complete 2 54.93 36.62 91.55 8.55 (0 , 0 , 1 , 0 , 1) Bartoliya Block Chakulia Total 15.000 43 427.69 285.11 712.80 63.32 (0 , 4 , 2 , 6 , 12)

Page 5 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Patamda

30 L035 L035-Sabartola Dadhudih Rd New Roller 1.800 3.750 Complete 4 46.52 31.02 77.54 8.36 (0 , 1 , 0 , 1 , 2) To Kulidih Compacted Concrete Pavement 31 L032 L032-Sabartola Dandudih New Roller 2.930 3.750 Complete 7 61.79 41.19 102.98 11.77 (0 , 0 , 1 , 1 , 2) Road to Raherdih Compacted Concrete Pavement Block Patamda Total 4.730 11 108.31 72.21 180.52 20.13 (0 , 1 , 1 , 2 , 4)

Block- Potka

32 L117 L117-S J ROAD TO SOSO New -- 1.500 3.750 Complete 4 37.21 24.80 62.01 7.44 (0 , 0 , 1 , 0 , 1) GUTTU (VR132) 33 L066 L066-T04 to Dungaridih New -- 2.150 3.750 Complete 6 63.50 42.34 105.84 9.44 (0 , 0 , 1 , 0 , 1)

34 L105 L105-Lailam to Dungraiah New -- 3.000 3.750 Complete 7 88.01 58.67 146.68 11.99 (0 , 0 , 1 , 0 , 1)

Block Potka Total 6.650 17 188.72 125.81 314.53 28.87 (0 , 0 , 3 , 0 , 3)

District East Singhbhum Total 31.280 83 863.24 575.47 1,438.71 132.96 (0 , 5 , 8 , 8 , 21) District- Garhwa

Block- Garhwa Sadar

35 L057 L057-T01 to Baghi (VR52) New -- 2.600 3.750 Complete 7 66.44 44.29 110.73 29.08 (0 , 1 , 0 , 0 , 1)

36 L041 L041-L041 Kalyanpur to New -- 3.746 3.750 Complete 17 115.06 76.71 191.77 36.27 (0 , 1 , 0 , 0 , 1) Nawadih 37 T02 T02-T02 to Dhangardiha New -- 3.000 3.750 Complete 14 88.68 59.12 147.80 31.72 (0 , 1 , 0 , 0 , 1) (VR49) 38 L046 L046-L046 to Bhaismarwa New -- 5.208 3.750 Complete 19 158.69 105.80 264.49 56.48 (0 , 0 , 1 , 2 , 3) Tola (VR38) 39 L024 L024-L024 to Bardaga New -- 2.533 3.750 Complete 8 76.20 50.80 127.00 26.94 (0 , 0 , 1 , 0 , 1) (VR45)

Page 6 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

40 L048 L048-L048 to Medhna Kalan New -- 1.250 3.750 Complete 5 35.63 23.75 59.38 5.20 (0 , 1 , 0 , 0 , 1) (VR40) 41 L060 L060-L021 to Bauliya (VR53) New -- 5.741 3.750 Complete 15 189.59 126.39 315.98 61.16 (0 , 1 , 0 , 0 , 1)

Block Garhwa Sadar Total 24.078 85 730.29 486.86 1,217.15 246.85 (0 , 5 , 2 , 2 , 9)

Block- Ramkanda

42 L021 L021-Sabane to Chapri New -- 3.930 3.750 Complete 17 115.86 77.24 193.10 44.17 (1 , 0 , 0 , 0 , 1)

43 L031 L031-Udaypur to Pundag New -- 2.315 3.750 Complete 6 70.21 46.80 117.01 10.63 (0 , 1 , 0 , 0 , 1) (VR20) Block Ramkanda Total 6.245 23 186.07 124.04 310.11 54.80 (1 , 1 , 0 , 0 , 2)

Block- Ramna

44 L042 L042-T02 TO CHAPARDAG New -- 3.223 3.750 Complete 8 96.21 64.14 160.35 35.93 (0 , 0 , 1 , 0 , 1) (VR23) Block Ramna Total 3.223 8 96.21 64.14 160.35 35.93 (0 , 0 , 1 , 0 , 1)

District Garhwa Total 33.546 116 1,012.57 675.04 1,687.61 337.58 (1 , 6 , 3 , 2 , 12) District- Giridih

Block- Deori

45 L061 L061-L021 to Maheshkishor New -- 2.100 3.750 Complete 8 54.24 36.16 90.40 9.39 (0 , 0 , 1 , 1 , 2) (VR61) Block Deori Total 2.100 8 54.24 36.16 90.40 9.39 (0 , 0 , 1 , 1 , 2)

District Giridih Total 2.100 8 54.24 36.16 90.40 9.39 (0 , 0 , 1 , 1 , 2)

District- Godda

Block-

46 L036 L036-Reo Road to Chhota Upgarde -- 2.100 3.750 Complete 1 53.30 35.53 88.83 7.49 (0 , 0 , 1 , 0 , 1) Malbhitha via Bara Pipra

Page 7 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

47 L037 L037-Ratanpur to Bara Kerlo Upgarde -- 4.150 3.750 Complete 7 105.52 70.35 175.87 17.39 (0 , 1 , 0 , 0 , 1)

48 L045 L045-Dumaria to Bara Telo Upgarde -- 4.600 3.750 Complete 6 98.02 65.34 163.36 17.87 (0 , 2 , 0 , 0 , 2) Road Block Boarijore Total 10.850 14 256.84 171.22 428.06 42.75 (0 , 3 , 1 , 0 , 4)

Block- Godda Sadar

49 L060 L060-PWD Sikatia to Dhodri New -- 2.400 3.750 Complete 6 65.12 43.42 108.54 7.94 (0 , 1 , 1 , 0 , 2)

Block Godda Sadar Total 2.400 6 65.12 43.42 108.54 7.94 (0 , 1 , 1 , 0 , 2)

Block-

50 L030 L030-Darighat to Madhuchak Upgarde -- 1.620 3.750 Complete 5 25.52 17.01 42.53 7.84 (0 , 1 , 1 , 0 , 2) road Block Mahagama Total 1.620 5 25.52 17.01 42.53 7.84 (0 , 1 , 1 , 0 , 2)

Block- Meharma

51 L031 L031-Muka Milik ti Singarpur Upgarde -- 1.150 3.750 Complete 3 27.89 18.59 46.48 5.25 (0 , 1 , 0 , 2 , 3)

52 L029 L029-Pratapur Block New -- 2.500 3.750 Complete 7 65.92 43.94 109.86 10.88 (1 , 2 , 0 , 2 , 5) Boundary to Rastikar 53 L036 L036-REO Road to Madhupur New -- 1.190 3.750 Complete 1 32.35 21.56 53.91 5.64 (0 , 1 , 0 , 0 , 1)

Block Meharma Total 4.840 11 126.16 84.09 210.25 21.76 (1 , 4 , 0 , 4 , 9)

Block- Poraihat

54 L027 L027-PWD Road Beltopa to New -- 0.970 3.750 Complete 2 27.79 18.53 46.32 3.58 (0 , 1 , 0 , 0 , 1) Panch ratan Road Block Poraihat Total 0.970 2 27.79 18.53 46.32 3.58 (0 , 1 , 0 , 0 , 1)

Block-

55 L041 L041-Damruhat to Potamdih New -- 1.600 3.750 Complete 2 43.85 29.24 73.09 7.72 (0 , 0 , 1 , 0 , 1) Road (VR42)

Page 8 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

56 L024 L024-Bara Puro to Chhota Upgarde -- 1.400 3.750 Complete 4 23.13 15.42 38.55 7.21 (0 , 1 , 0 , 0 , 1) Dhamni Block Sunderpahari Total 3.000 6 66.98 44.66 111.64 14.93 (0 , 1 , 1 , 0 , 2)

District Godda Total 23.680 44 568.41 378.93 947.34 98.80 (1 , 11 , 4 , 4 , 20) District- Gumla

Block- Bharno

57 L048 L048-Bharno Chatti to Cheto New -- 1.050 3.750 Complete 2 34.02 22.68 56.70 7.60 (0 , 1 , 0 , 0 , 1) (VR47) 58 L040 L040-BPDP Road Bharno New -- 1.560 3.750 Complete 3 48.11 32.08 80.19 15.60 (0 , 0 , 1 , 0 , 1) Chatti to Parsa (VR39) 59 L025 L025-Tongratoli To Kamalpur New -- 2.600 3.750 Complete 4 70.18 46.78 116.96 11.29 (0 , 0 , 1 , 2 , 3) kumbatoli Part B 60 L049 L049-T04 Dumba - Juriya rd New -- 0.600 3.750 Complete 1 11.63 7.75 19.38 2.48 (0 , 0 , 0 , 2 , 2) to Rawanotoli (VR48) Block Bharno Total 5.810 10 163.94 109.29 273.23 36.97 (0 , 1 , 2 , 4 , 7)

Block- Ghaghra

61 L053 L053-T04 to Jhariyatoli New -- 1.100 3.750 Complete 1 22.69 15.13 37.82 4.84 (0 , 0 , 0 , 3 , 3) (VR54) Block Ghaghra Total 1.100 1 22.69 15.13 37.82 4.84 (0 , 0 , 0 , 3 , 3)

Block- Gumla Sadar

62 L058 L058-Patya to Sikariyatoli New -- 3.010 3.750 Complete 8 79.34 52.90 132.24 10.44 (0 , 0 , 0 , 6 , 6) (VR64) 63 L024 L024-Kasitoli Khatua To Upgarde -- 7.460 3.750 Complete 10 184.16 122.77 306.93 71.96 (1 , 0 , 1 , 1 , 3) Sawariya part A Block Gumla Sadar Total 10.470 18 263.50 175.67 439.17 82.40 (1 , 0 , 1 , 7 , 9)

Page 9 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District Gumla Total 17.380 29 450.13 300.09 750.22 124.21 (1 , 1 , 3 , 14 , 19) District- Hazaribagh

Block- Barhi

64 L065 L065-GT ROAD TO TURI TOLA New -- 3.692 3.750 Complete 19 100.22 66.81 167.03 15.60 (0 , 0 , 1 , 1 , 2) VIA RANICHUWA (VR65) 65 L055 L055-NH31 TO PODAIYA Upgarde -- 2.633 3.750 Complete 3 58.61 39.07 97.68 10.35 (0 , 0 , 1 , 0 , 1) (VR55) Block Barhi Total 6.325 22 158.83 105.88 264.71 25.95 (0 , 0 , 2 , 1 , 3)

Block- Barkagaon

66 L057 L057-Baloder to Titahappa New Zycosoil 2.000 3.750 Complete 4 37.84 25.23 63.07 8.67 (0 , 0 , 0 , 1 , 1) Nanotechnolog y 67 L048 L048-L028 POTANGA TO New -- 2.000 3.750 Complete 4 54.37 36.24 90.61 9.04 (0 , 0 , 1 , 0 , 1) BHURKUNDWA (VR83) 68 L055 L055-jugra to pandanwa New Zycosoil 8.000 3.750 Complete 20 155.62 103.75 259.37 34.98 (0 , 0 , 0 , 1 , 1) tand Nanotechnolog y 69 L050 L050-L032 TO New -- 3.000 3.750 Complete 9 77.05 51.37 128.42 13.61 (0 , 0 , 1 , 0 , 1) CHARKAPATHAR VIA PANCHANDA (VR85) Block Barkagaon Total 15.000 37 324.88 216.59 541.47 66.30 (0 , 0 , 2 , 2 , 4)

Block- Barkatha

70 L072 L072-T06 TO SONDI TOLA New -- 1.035 3.750 Complete 3 29.95 19.97 49.92 4.07 (0 , 0 , 1 , 0 , 1) (VR72) Block Barkatha Total 1.035 3 29.95 19.97 49.92 4.07 (0 , 0 , 1 , 0 , 1)

Page 10 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Bishnugarh

71 T04 T04-SIRAIN TO KORIATAND Upgarde -- 2.243 3.750 Complete 2 48.60 32.40 81.00 6.08 (0 , 0 , 1 , 1 , 2)

Block Bishnugarh Total 2.243 2 48.60 32.40 81.00 6.08 (0 , 0 , 1 , 1 , 2)

Block- Chauparan

72 L078 L078-KARI PAHARI TO Upgarde -- 2.372 3.750 Complete 3 61.56 41.04 102.60 8.33 (1 , 0 , 0 , 0 , 1) BHATBIGHA (VR85) 73 L107 L107-Chapri Kala To Bela New Roller 3.567 3.750 Complete 4 77.47 51.65 129.12 13.12 (0 , 0 , 0 , 1 , 1) Tand Compacted Concrete Pavement 74 L073 L073-GOVINDPUR TO Upgarde -- 1.362 3.750 Complete 7 33.41 22.27 55.68 6.10 (0 , 1 , 0 , 0 , 1) DUMARI (VR80) 75 L060 L060-RAMPUR CHOWK TO Upgarde -- 1.473 3.750 Complete 3 34.72 23.15 57.87 5.56 (0 , 1 , 0 , 0 , 1) BARWADIH 76 L076 L076-REO ROAD SELHARA TO Upgarde -- 1.944 3.750 Complete 6 52.81 35.21 88.02 7.45 (0 , 0 , 1 , 0 , 1) RATANPUR (VR83) Block Chauparan Total 10.718 23 259.97 173.32 433.29 40.55 (1 , 2 , 1 , 1 , 5)

Block- Churchu

77 L067 L067-RABOD TO KUSUMDIH New -- 3.000 3.750 Complete 3 74.83 49.89 124.72 12.38 (0 , 0 , 1 , 0 , 1) (VR81) 78 L055 L055-CHARHI SARWAHA REO New -- 1.300 3.750 Complete 4 34.75 23.16 57.91 5.59 (0 , 0 , 1 , 0 , 1) ROAD TO BIRA KHAP (VR75) 79 L086 L086-TONGI TO KHAIRA TOLA New -- 4.000 3.750 Complete 9 110.02 73.35 183.37 18.40 (0 , 0 , 1 , 0 , 1)

80 L057 L057-HENDEGARHA TO New -- 2.000 3.750 Complete 3 50.63 33.75 84.38 8.58 (0 , 0 , 1 , 0 , 1) KOWAD (VR77) Block Churchu Total 10.300 19 270.23 180.15 450.38 44.94 (0 , 0 , 4 , 0 , 4)

Page 11 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Katkamsandi

81 L071 L071-T 01 18th km to Rajpur New Zycosoil 2.500 3.750 Complete 5 50.81 33.88 84.69 10.84 (0 , 0 , 0 , 1 , 1) Nanotechnolog y 82 L064 L064-T 05 23rd Km To New Zycosoil 1.500 3.750 Complete 4 29.39 19.59 48.98 6.57 (0 , 0 , 0 , 1 , 1) Borogara Nanotechnolog y 83 L086 L086-Sakarja to Dumri New Zycosoil 1.950 3.750 Complete 5 38.45 25.63 64.08 8.53 (0 , 0 , 0 , 1 , 1) Nanotechnolog y 84 L084 L084-Uridiri to Kharika New Zycosoil 1.200 3.750 Complete 3 20.85 13.90 34.75 5.24 (0 , 0 , 0 , 1 , 1) Nanotechnolog y 85 L088 L088-Kurhararha to Balia New -- 1.925 3.750 Complete 5 50.33 33.55 83.88 8.25 (0 , 0 , 1 , 0 , 1)

86 L087 L087-T06 Parsugwa to New Zycosoil 1.000 3.750 Complete 3 20.14 13.43 33.57 4.41 (0 , 0 , 0 , 1 , 1) Chirua Nanotechnolog y 87 L075 L075-T05 22nd km to New -- 2.000 3.750 Complete 4 50.27 33.52 83.79 8.27 (0 , 0 , 1 , 0 , 1) hatkona Block Katkamsandi Total 12.075 29 260.24 173.50 433.74 52.12 (0 , 0 , 2 , 5 , 7)

Block- Keredari

88 L049 L049-T01 MANATU TO New -- 5.000 3.750 Complete 6 118.92 79.28 198.20 20.26 (0 , 0 , 1 , 1 , 2) MASURIA (VR49) 89 L048 L048-T01 MANATU TO New -- 5.000 3.750 Complete 10 126.90 84.60 211.50 22.48 (0 , 0 , 1 , 0 , 1) PHUSARI (VR48) 90 L044 L044-L034 Slga to Barkitand New -- 3.000 3.750 Complete 4 77.32 51.55 128.87 13.42 (0 , 0 , 1 , 0 , 1)

91 L058 L058-GOPDA TO LOHARA New -- 5.500 3.750 Complete 8 134.95 89.97 224.92 22.02 (0 , 0 , 1 , 0 , 1) (VR58) 92 L051 L051-BUNDU TO KHAPIYA 2 New -- 2.300 3.750 Complete 5 55.26 36.84 92.10 9.32 (0 , 0 , 1 , 0 , 1) VIA CHARKAPATHAR (VR51)

Page 12 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

93 L056 L056-BANHE TO KARMATARN Upgarde -- 5.000 3.750 Complete 8 130.02 86.68 216.70 22.65 (0 , 0 , 1 , 0 , 1) (VR56) 94 L054 L054-T04 PATAL TO HOSIR New -- 3.900 3.750 Complete 5 96.53 64.35 160.88 17.33 (0 , 1 , 0 , 0 , 1) (VR54) Block Keredari Total 29.700 46 739.90 493.27 1,233.17 127.48 (0 , 1 , 6 , 1 , 8)

District Hazaribagh Total 87.396 181 2,092.60 1,395.08 3,487.68 367.49 (1 , 3 , 19 , 11 , 34) District- Jamtara

Block- Kundhit

95 L062 L062-Lakartanga to Keota New -- 1.660 3.750 Complete 3 48.70 32.47 81.17 8.18 (0 , 0 , 1 , 0 , 1)

96 L064 L064-Jagatdih to Dinari New -- 1.820 3.750 Complete 3 52.04 34.69 86.73 9.07 (0 , 0 , 1 , 0 , 1)

97 L069 L069-Simaldangal to New -- 1.770 3.750 Complete 3 52.46 34.97 87.43 9.36 (0 , 1 , 0 , 0 , 1) Belborai 98 L028 L028-Naudiha to Amdubi New -- 1.110 3.750 Complete 1 32.69 21.79 54.48 5.49 (0 , 1 , 0 , 0 , 1)

Block Kundhit Total 6.360 10 185.89 123.92 309.81 32.10 (0 , 2 , 2 , 0 , 4)

Block- Nala

99 L021 L021-Khuriam to Udaljori New -- 2.210 3.750 Complete 3 62.34 41.56 103.90 11.17 (0 , 1 , 0 , 0 , 1)

100 L021 L021-Udaljori to Saldahi New -- 1.910 3.750 Complete 3 54.35 36.23 90.58 9.68 (0 , 0 , 1 , 0 , 1)

Block Nala Total 4.120 6 116.69 77.79 194.48 20.85 (0 , 1 , 1 , 0 , 2)

Block- Narayanpur

101 L070 L070-Dhabakend to Dokidih New -- 1.340 3.750 Complete 1 37.92 25.28 63.20 6.08 (0 , 1 , 0 , 0 , 1) via Jagwadih 102 L060 L060-Dewalbari to Nayadih New -- 3.450 3.750 Complete 6 95.67 63.78 159.45 13.38 (0 , 1 , 0 , 0 , 1)

Block Narayanpur Total 4.790 7 133.59 89.06 222.65 19.46 (0 , 2 , 0 , 0 , 2)

Page 13 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District Jamtara Total 15.270 23 436.17 290.77 726.94 72.40 (0 , 5 , 3 , 0 , 8)

District- Khunti

Block- Karra

103 L048 L048-Chhata to Upgarde -- 0.930 3.750 Complete 3 23.24 15.50 38.74 3.34 (1 , 0 , 0 , 1 , 2) Brahmantoli Block Karra Total 0.930 3 23.24 15.50 38.74 3.34 (1 , 0 , 0 , 1 , 2)

Block- Rania

104 L028 L028-Golkara to Tumbatoli Upgarde -- 6.200 3.750 Complete 15 153.57 102.38 255.95 37.11 (0 , 0 , 1 , 2 , 3)

105 L043 L043-SODE KENBANKI ROAD New -- 1.653 3.750 Complete 5 48.56 32.37 80.93 7.75 (0 , 1 , 0 , 0 , 1) TO PAHARPUR MUNDATOLI (VR53) Block Rania Total 7.853 20 202.13 134.75 336.88 44.86 (0 , 1 , 1 , 2 , 4)

Block- Tamar

106 L072 L072-T06 TO New -- 0.917 3.750 Complete 3 25.43 16.96 42.39 2.35 (0 , 0 , 1 , 0 , 1) CHONGGAGUTU (VR145) Block Tamar Total 0.917 3 25.43 16.96 42.39 2.35 (0 , 0 , 1 , 0 , 1)

Block- Torpa

107 L067 L067-AMMA TO BANIYATOLI New -- 1.822 3.750 Complete 75 50.18 33.46 83.64 4.87 (0 , 0 , 1 , 0 , 1) (VR100) 108 L046 L046-Simla More to Simla Upgarde -- 1.974 3.750 Complete 5 50.70 33.80 84.50 8.55 (0 , 1 , 0 , 0 , 1)

Block Torpa Total 3.796 80 100.88 67.26 168.14 13.42 (0 , 1 , 1 , 0 , 2)

District Khunti Total 13.496 106 351.68 234.47 586.15 63.97 (1 , 2 , 3 , 3 , 9)

District- Koderma

Page 14 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Chandwara

109 L029 L029-Bhondo to Raghwatanr New -- 1.743 3.750 Complete 1 44.43 29.62 74.05 7.74 (0 , 1 , 0 , 1 , 2) (VR29) Block Chandwara Total 1.743 1 44.43 29.62 74.05 7.74 (0 , 1 , 0 , 1 , 2)

Block- Markacho

110 L045 L045-T01 to Tewari Tola New -- 7.708 3.750 Complete 8 195.19 130.13 325.32 31.76 (0 , 0 , 2 , 3 , 5) (VR45) Block Markacho Total 7.708 8 195.19 130.13 325.32 31.76 (0 , 0 , 2 , 3 , 5)

District Koderma Total 9.451 9 239.62 159.75 399.37 39.50 (0 , 1 , 2 , 4 , 7)

District- Latehar

Block- Balumath

111 L057 L057-Harhenj to Latu New -- 9.000 3.750 Complete 8 226.80 151.20 378.00 37.33 (0 , 1 , 0 , 0 , 1)

112 L053 L053-Heranj to Heranhopa New -- 22.000 3.750 Complete 10 560.78 373.85 934.63 88.76 (0 , 1 , 0 , 1 , 2)

113 L027 L027-PWD Road Bariyatu to New -- 7.000 3.750 Complete 10 177.05 118.03 295.08 27.97 (0 , 2 , 0 , 0 , 2) Hisri Block Balumath Total 38.000 28 964.63 643.08 1,607.71 154.06 (0 , 4 , 0 , 1 , 5)

Block- Barwaidih

114 L025 L025-PWD road to Rabdi New -- 5.000 3.750 Complete 8 123.76 82.51 206.27 20.16 (0 , 1 , 0 , 0 , 1)

Block Barwaidih Total 5.000 8 123.76 82.51 206.27 20.16 (0 , 1 , 0 , 0 , 1)

Block- Chandwa

115 L022 L022-Mahua Milan to Upgarde -- 4.400 3.750 Complete 12 108.04 72.03 180.07 18.73 (0 , 0 , 1 , 0 , 1) Deonadia Block Chandwa Total 4.400 12 108.04 72.03 180.07 18.73 (0 , 0 , 1 , 0 , 1)

Page 15 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Latehar Sadar

116 L055 L055-Bishrampur to Sohdag New -- 5.000 3.750 Complete 6 125.77 83.85 209.62 20.22 (0 , 1 , 0 , 0 , 1)

117 L021 L021-Murup to Datam New Zycosoil 5.000 3.750 Complete 10 100.28 66.85 167.13 21.73 (0 , 0 , 0 , 1 , 1) Nanotechnolog y Block Latehar Sadar Total 10.000 16 226.05 150.70 376.75 41.95 (0 , 1 , 0 , 1 , 2)

District Latehar Total 57.400 64 1,422.48 948.32 2,370.80 234.90 (0 , 6 , 1 , 2 , 9)

District- Pakur

Block-

118 L054 L054-Paderkera To Nonpara New -- 2.700 3.750 Complete 5 77.41 51.61 129.02 14.29 (0 , 0 , 1 , 0 , 1)

Block Amrapara Total 2.700 5 77.41 51.61 129.02 14.29 (0 , 0 , 1 , 0 , 1)

Block- Littipara

119 L049 L049-Kunjbona To Sakla New -- 1.610 3.750 Complete 3 45.98 30.66 76.64 7.26 (0 , 0 , 1 , 0 , 1)

120 L059 L059-PWD Road Jordiha To New -- 2.610 3.750 Complete 5 77.84 51.90 129.74 14.36 (0 , 0 , 1 , 0 , 1) Chhota Ghaghri part B Block Littipara Total 4.220 8 123.82 82.56 206.38 21.62 (0 , 0 , 2 , 0 , 2)

District Pakur Total 6.920 13 201.23 134.17 335.40 35.91 (0 , 0 , 3 , 0 , 3)

District- Palamau

Block- Chainpur

121 L086 L086-KUNDPANI CHORHAT New Zycosoil 4.100 3.750 Complete 8 66.83 44.55 111.38 15.29 (0 , 0 , 0 , 1 , 1) TO BIWABATHAN (VR80) Nanotechnolog y Block Chainpur Total 4.100 8 66.83 44.55 111.38 15.29 (0 , 0 , 0 , 1 , 1)

Page 16 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Chattarpur

122 L091 L091-PMGSY ROAD TO New -- 2.300 3.750 Complete 7 68.52 45.68 114.20 9.93 (0 , 0 , 1 , 0 , 1) KOHANPUR TO KARUPA (VR81) 123 L100 L100-PWD ROAD JAPLA New Roller 1.900 3.750 Complete 8 56.41 37.61 94.02 8.84 (0 , 0 , 1 , 0 , 1) ROAD TO PATSARA (VR89) Compacted Concrete Pavement Block Chattarpur Total 4.200 15 124.93 83.29 208.22 18.77 (0 , 0 , 2 , 0 , 2)

Block- Hussainabad

124 L108 L108-Sabanma to Tendua New Zycosoil 1.600 3.750 Complete 9 30.16 20.11 50.27 7.97 (0 , 0 , 0 , 1 , 1) Khure Nanotechnolog y 125 L107 L107-Bhajaniya to Poto New Zycosoil 1.600 3.750 Complete 4 32.47 21.64 54.11 7.74 (0 , 0 , 0 , 1 , 1) Nanotechnolog y Block Hussainabad Total 3.200 13 62.63 41.75 104.38 15.71 (0 , 0 , 0 , 2 , 2)

Block- Lesliganj

126 L044 L044-DARUDIH MAIN ROAD New -- 1.400 3.750 Complete 5 39.12 26.08 65.20 8.95 (0 , 0 , 2 , 0 , 2) TO MADHODIDRI (VR33) 127 L040 L040-NAWADIH TENAR TO New -- 1.850 3.750 Complete 5 55.16 36.78 91.94 8.52 (0 , 1 , 0 , 2 , 3) JOGIA SOHRI Block Lesliganj Total 3.250 10 94.28 62.86 157.14 17.47 (0 , 1 , 2 , 2 , 5)

Block- Patan

128 L059 L059-B.T ROAD GHORI GHAT New Roller 2.300 3.750 Complete 13 65.02 43.35 108.37 10.21 (0 , 1 , 0 , 0 , 1) TO MAJHAULI (VR50) Compacted Concrete Pavement Block Patan Total 2.300 13 65.02 43.35 108.37 10.21 (0 , 1 , 0 , 0 , 1)

Page 17 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District Palamau Total 17.050 59 413.69 275.80 689.49 77.44 (0 , 2 , 4 , 5 , 11) District- Ramgarh

Block- Mandu

129 L022 L022-SARAIPANI TO New -- 1.978 3.750 Complete 3 58.94 39.29 98.23 7.79 (1 , 0 , 0 , 0 , 1) TITIRMARWA ROAD Block Mandu Total 1.978 3 58.94 39.29 98.23 7.79 (1 , 0 , 0 , 0 , 1)

Block- Patratu

130 L063 L063-Lo36 to Bartua (VR61) New Fly Ash 0.918 3.750 Complete 1 25.51 17.01 42.52 3.46 (0 , 1 , 0 , 0 , 1) Subgrade Block Patratu Total 0.918 1 25.51 17.01 42.52 3.46 (0 , 1 , 0 , 0 , 1)

District Ramgarh Total 2.896 4 84.45 56.30 140.75 11.25 (1 , 1 , 0 , 0 , 2)

District- Ranchi

Block- Kanke

131 L033 L033-Ulatu to Upgarde Cold Mix 2.355 3.750 Complete 5 50.93 33.96 84.89 10.55 (0 , 1 , 0 , 1 , 2) Chotkidubaliya Technology Block Kanke Total 2.355 5 50.93 33.96 84.89 10.55 (0 , 1 , 0 , 1 , 2)

Block- Lapung

132 L025 L025-Kakaria to Bero Road New -- 1.350 3.750 Complete 3 36.99 24.66 61.65 6.47 (0 , 0 , 1 , 0 , 1) to Doranda 133 L055 L055-Dimba to Lodma Road Upgarde -- 2.150 3.750 Complete 3 63.40 42.27 105.67 9.47 (0 , 1 , 0 , 0 , 1)

Block Lapung Total 3.500 6 100.39 66.93 167.32 15.95 (0 , 1 , 1 , 0 , 2)

Page 18 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Mandar

134 L041 L041-Bishakakhatanga to New -- 2.100 3.750 Complete 5 59.26 39.51 98.77 7.68 (1 , 0 , 1 , 0 , 2) Darjijari and Bondo Block Mandar Total 2.100 5 59.26 39.51 98.77 7.68 (1 , 0 , 1 , 0 , 2)

District Ranchi Total 7.955 16 210.58 140.40 350.98 34.18 (1 , 2 , 2 , 1 , 6)

District- Sahebganj

Block- Burhait

135 L040 L040-PWD Road to Talbaria New -- 1.500 3.750 Complete 4 44.23 29.49 73.72 5.97 (0 , 0 , 1 , 0 , 1) Road 136 L026 L026-Petkhasa Doria New -- 2.650 3.750 Complete 9 71.27 47.51 118.78 10.96 (0 , 0 , 2 , 0 , 2) Santhali Road to Bastadih Block Burhait Total 4.150 13 115.50 77.00 192.50 16.93 (0 , 0 , 3 , 0 , 3)

Block- Burharwa

137 L029 L029-Salalpur to Belpahari Upgarde -- 1.940 3.750 Complete 5 53.99 35.99 89.98 8.22 (0 , 1 , 1 , 0 , 2)

Block Burharwa Total 1.940 5 53.99 35.99 89.98 8.22 (0 , 1 , 1 , 0 , 2)

Block-

138 L040 L040-Pindra to Khairbani Upgarde -- 2.991 3.750 Complete 3 75.30 50.20 125.50 9.93 (0 , 0 , 1 , 0 , 1)

Block Mandro Total 2.991 3 75.30 50.20 125.50 9.93 (0 , 0 , 1 , 0 , 1)

Block-

139 L021 L021-Udhwa Diara to Upgarde -- 3.639 3.750 Complete 9 106.13 70.76 176.89 9.13 (1 , 0 , 0 , 0 , 1) Amanat Block Udhwa Total 3.639 9 106.13 70.76 176.89 9.13 (1 , 0 , 0 , 0 , 1)

District Sahebganj Total 12.720 30 350.92 233.95 584.87 44.20 (1 , 1 , 5 , 0 , 7)

Page 19 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District- Saraikela Kharsawan

Block- Gamharia Adityapur

140 L035 L035-Chhota jamjora to Upgarde -- 3.050 3.750 Complete 6 62.90 41.93 104.83 6.62 (0 , 1 , 1 , 0 , 2) Bindapur Block Gamharia Adityapur Total 3.050 6 62.90 41.93 104.83 6.62 (0 , 1 , 1 , 0 , 2)

Block- Rajnagar Govindpur

141 L077 L077-Raniganj to Chhelkhani Upgarde -- 2.850 3.750 Complete 7 66.38 44.26 110.64 11.98 (0 , 1 , 2 , 2 , 5)

142 L047 L047-Raj Nagar to Block Upgarde -- 0.887 3.750 Complete 1 20.00 13.33 33.33 4.83 (0 , 0 , 4 , 0 , 4) Boundry via Chakradharpur Block Rajnagar Govindpur Total 3.737 8 86.38 57.59 143.97 16.81 (0 , 1 , 6 , 2 , 9)

District Saraikela Kharsawan Total 6.787 14 149.28 99.52 248.80 23.43 (0 , 2 , 7 , 2 , 11) District- Simdega

Block- Jaldega

143 L062 L062-T03 (Targa Khas) to New Zycosoil 2.700 3.750 Complete 5 77.44 51.63 129.07 13.30 (0 , 0 , 1 , 1 , 2) Bambariyapara Nanotechnolog y Block Jaldega Total 2.700 5 77.44 51.63 129.07 13.30 (0 , 0 , 1 , 1 , 2)

District Simdega Total 2.700 5 77.44 51.63 129.07 13.30 (0 , 0 , 1 , 1 , 2)

District- West Singhbhum

Block- Chaibasa

144 L053 L053-Bhuta to Mankisai Upgarde -- 2.730 3.750 Complete 5 77.47 51.65 129.12 12.01 (0 , 0 , 3 , 1 , 4)

145 L044 L044-Nimdih to Mundasai New -- 3.600 3.750 Complete 3 100.28 66.85 167.13 13.66 (0 , 0 , 1 , 0 , 1)

Block Chaibasa Total 6.330 8 177.75 118.50 296.25 25.67 (0 , 0 , 4 , 1 , 5)

Page 20 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Kurnardungi

146 L034 L034-Dirigo to Kasidih Road Upgarde -- 2.500 3.750 Complete 4 70.08 46.72 116.80 11.63 (0 , 0 , 2 , 2 , 4)

Block Kurnardungi Total 2.500 4 70.08 46.72 116.80 11.63 (0 , 0 , 2 , 2 , 4)

Block- Manjhari

147 L037 L037-Bidari to Ukamadkam Upgarde -- 1.500 3.750 Complete 2 41.58 27.72 69.30 6.61 (0 , 0 , 2 , 0 , 2) Pulbasa Road 148 L040 L040-Panga to Gitilpee Road Upgarde -- 7.515 3.750 Complete 23 176.71 117.81 294.52 34.18 (0 , 0 , 1 , 1 , 2)

Block Manjhari Total 9.015 25 218.29 145.53 363.82 40.79 (0 , 0 , 3 , 1 , 4)

Block- Manoharpur

149 L076 L076-DHIPA TO ICHAPIR New -- 1.000 3.750 Complete 3 19.52 13.02 32.54 7.39 (0 , 0 , 1 , 0 , 1)

Block Manoharpur Total 1.000 3 19.52 13.02 32.54 7.39 (0 , 0 , 1 , 0 , 1)

Block- Noamundi

150 L035 L035-Gundijhora to New -- 4.800 3.750 Complete 15 121.21 80.81 202.02 17.89 (0 , 1 , 0 , 0 , 1) Mundasai via Kudapi Road Block Noamundi Total 4.800 15 121.21 80.81 202.02 17.89 (0 , 1 , 0 , 0 , 1)

District West Singhbhum Total 23.645 55 606.85 404.58 1,011.43 103.37 (0 , 1 , 10 , 4 , 15) Road Proposals Total 421.597 968 10,903.42 7,269.02 18,172.44 2,039.10 (9 , 58 , 88 , 82 , 237) Long Span Bridge Proposals

District- Palamau

Page 21 of 22 Generated On : 28/03/2017 12:00 PM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Rs Lacs) (Rs Lacs) (Rs Lacs) 500+, 250+, Length <250, Total) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Patan

151 L061 H.L.BRIDGE IN 2ND KM New -- 43.800 0.000 Complete 0 86.32 57.54 143.86 1.97 (0 , 0 , 0 , 0 , 0)

Block Patan Total 43.800 0 86.32 57.54 143.86 1.97 (0 , 0 , 0 , 0 , 0)

District Palamau Total 43.800 0 86.32 57.54 143.86 1.97 (0 , 0 , 0 , 0 , 0)

Long Span Bridge Proposals Total 43.800 0 86.32 57.54 143.86 1.97 (0 , 0 , 0 , 0 , 0)

Grand Total Total Road Length:421.597 Kms 968 10,989.74 7,326.56 18,316.30 2,041.07 (9 , 58 , 88 , 82 Total LSB Length:43.800 Mtrs , 237)