Push-fit Plumbing System Installer Guide
BS 7291
ED V T A RO C PP DU PRO
July 2009 Contents
Page Introduction 3 Introduction, Approvals 4 Features & Benefits, Installation 5 Performance, System Assembly Basics 6-7 Pipe Selection, Standard Pipe, Barrier Pipe, Pipe Specification, Straight Lengths, Coils 8-9 Pipe Cutting 10 Jointing Standard 11-12 Applications Sitework 13-15 Cabling through Joists 16-18 Pipe Support 18 Pipe Installation in Exposed Locations 18 Pipe Installation in Concealed Locations 19 Pipes through Walls and Floors 19 Laying of Pipe in Floor Screeds 19 Pipes Adjacent to Metalwork 19 Piping Noise Reduction 20 Manifolds/Microbore Plumbing 21 Underfloor Heating Pipe 22 Routabout 23 Conduit Systems 24-27 Installation Recommendations ® 28-29 Hep2O Within Dry Lined Walls ® 30 Hep2O Within Internal Drywall Systems ® 30-32 Hep2O Within Timber Framed and Steel Framed Buildings Compatability 33-41 Metric Copper Pipe, Using Compression, Fittings, Adjacent & Connections to Capillary Joints, Imperial Copper, Chrome Plated Copper or Stainless Steel Pipe, Incoming Service Pipe, Brass Spigots, Acorn System, Plastic Pipes, Steel pipes and Threaded Bosses, Connection to Appliances, Draw-off Taps, Ancillaries (Pumps, Valves, etc.), Storage Vessels and Radiators, Boilers and Heaters System 42-43 Fitting Detachment, Lubrication Modifications 44 Alterations General 45 Thermal Insulation Information 45 Freezing for Maintenance/System Modification ® 45 Painting Hep2O 45 Use of Corrrosion Inhibitors 45 Antifreeze 46 Electrical Safety 46 Woodworm/Timber Treatment Special 47 External Installations Precautions 47 Vermin 47 Chlorine Testing 48 Pressure Testing Special 49 Boats Applications 49 Caravans 49 Exhibitions 49 Portable Buildings (site cabins, toilets etc.) 50 Agricultural and Horticultural Use 50 Air Conditioning Systems ® 50 Where not to use Hep2O Handling & 51 Handling and Storage Storage Hints & Tips 52 Hints and Tips Fault Finding 53-54 Fault Finding Information 55 Advisory Service 55 Literature Service 55 Other Sources of Information Literature 2 ® The Hep2O Installer Guide for Flexible Push-Fit Plumbing Introduction The mark of a professional tradesman is that he understands and employs a wide 1 range of materials and systems to achieve the best possible solution to individual installation situations. The notes in this Installer Guide are intended to assist professional plumbers to obtain the best results from using flexible push-fit plumbing, enhancing good plumbing practice. It is not sufficient to simply replace item for item, pipe length for pipe length, as this approach will not derive the maximum benefit from the system. It is necessary to design the system from the outset, embracing the benefits the system offers to achieve maximum benefits. ® Enhanced Hep2O flexibility means an opportunity to develop further skills when planning and installing plumbing, offering a comprehensive range of pipes and fittings to meet plumbing requirements. Greater pipe flexibility, long coil lengths and guaranteed joint performance, enables installations to be completed with fewer joints minimising system costs. Pipes can be cabled into position avoiding the awkward manoeuvring ® associated with rigid straight lengths. Hep2O fittings are designed to ® accept copper as well as Hep2O pipe, enabling systems to be mixed if required.
® Hep2O is a tried and tested system, which has been in use in the UK for over 25 years. Approvals ® Hep2O is manufactured and kitemarked to Class S of BS 7291, Parts 1 and 2 and is manufactured within a BS 7291 Quality Management System which satisfies BSEN ISO9002 requirements.
® Hep2O Barrier Pipe is covered by Agrément Certificate 92/2823 to Class ‘S’ of BS 7291.
® Hep O Is listed in the Water Fittings and Materials ED 2 V T A RO C PP D U Directory - Listing Number 0112066. PRO
® Hep2O is suitable for use in domestic water distribution and central heating systems including pressurised systems and combination boilers in accordance with Table No. 1. It may also be used in buildings other than dwellings providing the service conditions are not exceeded.
Table No. 1 Peak Life Cycle Operating Temperatures/Pressures
20°C 30°C 40°C 50°C 60°C 70°C 80°C 95°C Short Malfunction at 114°C
Safe pressures:
Bar 12 11.5 11 10.5 9 8 7 6 3 psi 174 167 160 152 131 116 102 87 43.5
Head of water (m) 120 115 110 105 90 80 70 60 29
3 ® The Hep2O Installer Guide for Flexible Push-Fit Plumbing
® Hep2O has a minimum design life expectancy of 50 years provided the system is installed in accordance with the manufacturer’s recommendations. These recommendations include service temperatures and pressures. Peak life cycle operating temperatures / pressures are given in Table No. 1. As a result of its rigorous Quality Management Programme Wavin offer a 50 year guarantee ® against defects in materials or manufacturing of all Hep2O pipe and fittings. Features and Benefits ® Hep2O has evolved over 25 years to offer improved installation advantages, whilst maintaining proven long term performance benefits. ® Flexible pipe work and joint security are the key features of Hep2O . Pipe flexibility in conjunction with straight coils in SmartPackTM dispensers enables pipe to be cabled into position, with fewer joints, ® minimising system costs. The Hep2O fitting incorporates a high integrity grab wedge and robust pre-lubricated ‘O’ ring, offering the installer smoother pipe insertion and lower jointing forces. The re-usable grab wedge gives reliable jointing even when the fitting has been dismantled and reassembled. Installation ® Hep2O introduces a new flexibility for the professional to exploit during installation.
Cabling Ability Less Jointing Low Wastage
Measure and Cut High Resistance to Rotatable Fittings In-situ Impact
Easier Handling Less Risk Jointing, No Naked Flame 4 ® The Hep2O Installer Guide for Flexible Push-Fit Plumbing Performance ® Once installed Hep2O offers considerable benefits over traditional rigid systems. 1
No Scale Build-up No Burst Pipes Quieter
Cool to the Touch Solder Free Corrosion Free
System Assembly ® In skilled hands the flexible Hep2O plumbing system guarantees professional sitework.
5 Basics Pipe Selection ® Hep2O pipe is manufactured as two types, Standard and Barrier. Their correct applications are as follows:- Standard Pipe Standard pipe is suitable for domestic hot and cold water services and heating applications. As standard pipe may allow the ingress of minute amounts of oxygen molecules through the pipe wall when used for heating a suitable inhibitor (Sentinel or Fernox MB1) should be used. Barrier Pipe Barrier pipe is designed for central heating systems and incorporates an oxygen barrier to inhibit oxygen permeation. The use of inhibitors with barrier pipe is still recommended as corrosion can occur in all types of system regardless of pipe material. Barrier pipe may be used for domestic hot and cold water services. ® Both Hep2O Standard and Barrier Pipe is accepted by British Gas/ Scottish Gas Central Heating Care Contracts.
Note: ® Hep2O pipe is not suitable for the conveyance of gas.
Pipe Specification The 15mm, 22mm and 28mm pipe is available in straight lengths and coils. The 10mm pipe is only supplied in coils. Availability is clearly shown in Table 2 (see page 7). Straight Lengths ® Straight lengths of Hep2O are not rigid, and are as flexible as coiled pipe. Straight lengths are primarily for exposed pipework where neatness is important or for use where only short lengths are required. Coils ® Coiled Hep2O is primarily suited to ‘first fix’ work on site, where minimal pipe jointing is desirable. ® Hep2O is available in straight coils, in SmartPackTM dispensers. Unlike other forms of coiled plastic pipe, ® Hep2O does not tend to return to its coiled state when uncoiled for installation. ® Hep2O straight coiled pipe has a tendency to remain straight when uncoiled with no loss of flexibility. ® ® Hep2O Pipe in Pipe System incorporates Hep2O Barrier Pipe in a pre-sheathed conduit ready for underscreed installation, saving time, effort and complies with current regulations.
6 Basics
Table No. 2 Standard and Barrier Pipe Lengths 10mm 15mm 22mm 28mm Straight Lengths 3m 6m Coils 2 25m 50m 100m Pipe in Pipe 25m 50m
G Cut Length Standard and Barrier Straight Cut Lengths.
G Standard Straight Coiled Pipe Straight Coiled Lengths in SmartPackTM Dispenser.
G Barrier Straight Coiled Pipe Straight Coiled Lengths in SmartPackTM Dispenser.
G Pipe in Pipe System ® Hep2O Barrier Pipe in Blue or Red Conduit.
7 Basics
Pipe Cutting Basic Jointing/Pipe Cutting ® When cutting Hep2O pipe it is essential to use the correct tools. Only the recommended cutters as shown in the current trade price list (HD74, HD75, HD77 or HD78) should be used. Do not use a hacksaw. (Figure No. 1) Before making a joint ensure the pipe end is clean, cut square and free from burrs and surface damage. (Figure No. 2). Place the pipe in the jaws of the cutter and apply pressure, the pipe should be rotated whilst maintaining the pressure until the pipe is severed. (Figure No. 3) DON’T Figure No. 1 Do not use a hacksaw to cut ® Hep2O pipe.
DON’T Figure No. 2 Do not use damaged pipe. Ensure pipe is free from burrs
and surface damage. To ensure adequate insertion, essential for a secureV joint, cut the pipe square at one of the cutting/insertion marks ‘ ’. The distance between these marks indicates full socket depth (Figure No. 3).
Figure No. 3
When it may not be possible to use the ‘V ’ marks eg. badly lit areas, jointing copper pipe or where an exact length is required, mark the insertion depth on the pipe using a pencil or suitable marker pen. The correct insertion depth can be obtained by holding the pipe against the fitting or by measuring with a rule, as shown (Figure No. 4). The depth of insertion is shown in Table 3 at the end of this section.
8 Basics Pipe Cutting cont.
Figure No. 4
® ® Hep2O Hep2O SlimLine Fitting Demountable Fitting
Pipe depth 2 insertion marks
Insertion depth
Insertion depth
Pipe depth insertion marks
Support Sleeve ® ® ALWAYS insert a Hep2O support sleeve into the Hep2O pipe end. (Figure No. 5). It is essential to use a support sleeve in order to make a good joint. The support sleeve ensures that the pipe retains a circular section and provides a leading edge to the pipe for easier insertion (the only exceptions to this rule are when using copper pipe, or the open spigot ® end of a Hep2O fitting). Figure No. 5
Table No. 3 Correct insertion depths for ® Demountable and SlimLine Hep2O fittings Pipe size Nominal insertion Depth inc. sleeve 10mm 23mm 15mm 28mm 22mm 31mm 28mm 40mm
Note: Support sleeve is an integral part of the system and ® should NEVER be omitted when using Hep2O pipe.
9 Basics
Jointing Procedure - whichever type of fitting is used, the same jointing procedure should be used. All fittings are pre-lubricated.
Figure No. 6 Use only purpose designed pipe
cutters. (HD74, HD75, HD77 or HD78)V Cut the pipe at one of the ‘ ’ marks. Ensure the pipe end is free from burrs.
Figure No. 7
® Insert a Hep2O support sleeve (HX60) into the pipe end.
Figure No. 8 Push the pipe firmly into the fitting.
A secure joint has been made when the endV of the cap has reached the next ‘ ’ mark on the pipe.
Figure No. 9 Tug back on the pipe to ensure the grab wedge engages correctly.
DO G ®
Use only Hep2O cutters when cutting the pipe.
G Cut the pipe at the ‘V ’ marks wherever possible. G Mark the pipe if not possible to cut to a ‘ V ’. G When cutting rotate pipe whilst maintaining the pressure until the pipe is severed. G Cut the pipe squarely. G Ensure pipe end is clean, free from burrs & surface damage. G ® Always use a support sleeve into a Hep2O ‚ pipe end. G Push the pipe and fitting together firmly. DON’T G Use a hacksaw to cut the pipe. G Slacken the retaining cap prior to pipe insertion, this will not ease jointing. G Knock fittings onto pipe. G Undo retaining cap after pipe insertion.
10 Standard Applications
® Hep2O is suitable for most domestic and commercial plumbing applications.
® With it’s extensive range of fittings, Hep2O meets the requirements of modern systems ensuring secure connection.
Figure No. 10 Wash Hand Basin 15mm
3
Figure No. 11 Wash Hand Basin 10mm
Figure No. 12 Bath
Figure No. 13 W.C .
11 Standard Applications
Figure No. 14 Sink
Figure No. 15 Boiler Connections
Figure No. 16 Figure No. 17 Cylinder Cupboard Cylinder Cupboard
Figure No. 18 Washing Machine/Dishwasher
12 Sitework
Cabling through Joists The 1992 Building Regulations Approved Document A allows for pipework to be installed in joists by one of two methods, notching or drilling. Traditionally joists have been notched and the pipework laid in as the rigidity of the pipe does not easily allow for any other method of installation. This means that the pipework must be installed prior to the floorboards being laid. This has a number of disadvantages: G Plumber has to work on open joists increasing risk of accident or injury. G Plumber will have to return after floors are laid to connect radiators, etc. 4 G Plumber often finds that on his return, tails he left have been moved by other tradesmen thereby causing extra work to reposition pipework correctly for radiators. Cabling through joists means pipework can be installed by working from below allowing exact positioning of ‘tails’ through floor. Site safety is therefore enhanced and the plumber is not exposed to the danger of falling or the discomfort of kneeling on open joists. Other trades working below are protected from the dangers of falling tools, molten solder, gas bottles etc. As flooring can be laid prior to the plumber carcassing from below this will progress the building schedule as other trades can work on the floor above e.g. to form studwork etc. Carcassing at a later stage in the construction programme is also more pleasant as the building is likely to be weatherproof. Less Risk to Health and Site Safety ® The unique Hep2O fitting ensure effective, leak-free pipe jointing without the use of a naked flame. Safety from fire, especially in restricted spaces, is greatly increased and the working environment is improved. There is no need for flux and solder, thus eliminating any potential contamination of water supplies. Push-fit jointing also has the following advantages for the installer: G No naked flame means that precautions such as obtaining a ‘hot work’ permit, having a fire extinguisher readily available, and remaining on site for a while after jointing are not necessary. G No risk of infringement of Health and Safety recommendations applicable to some brands of flux. eg. means to control exposure to noxious fumes when working in a confined space, and use of eye protection (where appropriate). G After jointing the fitting is clean and safe to touch eg. after soldering joint, is hot and flux traces should be removed. G Joint is rotatable after installation.
13 Sitework Cabling through Joists cont. Summary Flexible plumbing means that the installer can cable pipework more easily utilising continuous runs of pipework. The flexibility does away with dry runs as the pipe can be cut and joints made in situ. As no solvents are used in jointing, the system can be tested as soon as the installation is finished. Exposed pipework should use the recommended clipping distances as shown in Table 4 (see page 17). Tails fitted through the floor for connections to sanitary ware can be left long enough for final connections. Straight connections and offset connections normally required for rigid connections are then unnecessary. ® Hep2O can be trimmed to length and the natural flexibility used to overcome any mis-alignment.
® The Hep2O system incorporates a comprehensive range of spigot tees. These can be used individually or in groups to give manifold arrangements with the benefit of 360 degree rotation. This facility means that systems based on conventional UK design can be enhanced by the addition of manifolds where beneficial. Joists can be drilled and pipework cabled through, rather than notched which is the normal practice with rigid pipework systems. (This is permitted by Building Regulations, NHBC Standards and several British Standards). This means that pipework no longer needs to be installed prior to floorboards being laid. The ability to install pipe through joists has specific advantages: Often eliminating the need for separate carcassing and second fix operations.
® When Hep2O is cabled through joists it can be easily positioned to allow for the installation of thermal insulation if required. Pipework can be exactly positioned for the radiators etc. avoiding the risk of being moved or damaged by other trades. Safer working environment for all trades as upstairs floors are already in place. It is safer for the plumbing installer as the drilling can be carried out from the floor below. There is less danger of puncturing the pipe with nails used for fixing the floorboards and there is no need to use protective devices such as ‘joist clips’.
Note: The Building Regulations 1992 Approved Document A gives exact instructions on the drilling of floor joists. Those regulations are detailed below: Hole diameters should be no greater than 0.25 of the depth of the joist and should be drilled at the neutral axis. They should be not less than 3 diameters (centre to centre) apart and should be located between 0.25 and 0.4 times the span from the support. These points are illustrated in Figure No. 19 (see page 15).
The value 0.25 is obviously one quarter and can easily be calculated on site. The value 0.4 is less obvious and can be obtained from Figure No. 20 (see page 15).
14 Sitework Cabling through Joists cont. Engineered Joists ® Hep2O is ideal in buildings incorporating timber ‘I’ joists. Piping can be properly installed through holes in the web section without damaging flange members (eg. TJI Joist system, Trus Joist MacMillan Ltd.) even where the pre-formed holes do not align on the plan. Pumps, Valves etc:
® Where Hep2O is connected to pumps, valves and similar devices consideration should be given to adequately supporting the item in question (bearing in mind the rotatability ® of the Hep2O joint). Equipment should not be suspended from the pipe without adequate support. 4 Figure No. 19 Explanation of Drilling Joists in Accordance with Building Regulations 1992 - Approved Document A
SPAN S
HOLES SHOULD BE LOCATED IN THIS ZONE & DRILLED AT THE NEUTRAL AXIS.
0.4 x ‘S’
0.25 x ‘S’ CENTRAL AXIS OF JOIST
DEPTH.
NOT LESS THAN 3 DIAMETERS APART CENTRE TO CENTRE.
MAX. DIAMETERS OF HOLES = 0.25 X DEPTH OF JOIST.
NB: The minimum distance between a hole and a notch in the same joist should not be less than 100mm.
Figure No. 20 Graph Showing Dimension of Joist Drilling Zone from Support Distance from Support (m) 2.0
1.5
1.0 Maximum Distance from Support
0.5 Minimum Distance from Support
1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 Span of Joist (m) Notes: This graph should be used in conjunction with Figure No. 19. Example of use: Joist span is 4.5m. Find value on horizontal scale and read-up to sloping line. Transfer point of intersection to the vertical scale and read 1.8m.
15 Sitework Pipe Support ® The Hep2O system includes two types of pipe clip, the screw fix type (HX85) and the nail type (HX65). The nail type is primarily designed for use on concealed pipework, and allows for rapid fixing to timber. The screw type may be used together with a spacer (HX86) which allows a greater spacing between the pipe and the fixing background. The spacer therefore allows different pipe fixing centres which can be used to facilitate pipe cross-overs or the installation of thermal insulation to the pipe (see Figure No. 22). A cold forming bend fixture (HX75) is available to allow the formation of a bend on 15mm and 22mm pipes for situations where secure fixing and neatness are important. (See Figure No. 23).
Figure No. 21 Pipe Clips Code Nominal Diameter HX65/10 10 HX65/15 15 HX65/22 22 Pipe Clip - Nail HX65/28 28
Code Nominal Diameter HX85/15 15 HX85/22 22 Pipe Clip - Screw HX85/28 28
Code Nominal Diameter HX86/15 15 HX86/22 22 Pipe Clip - Spacer NB: The HX86/22 spacer can be used with both the HX85/22 and HX85/28 clip.
Figure No. 22 Pipe Fixing Centres CL
CL B A
Pipe Clip Pipe Clip and Spacer
Note: Fixing hole size is 5mm diameter.
Nominal Diameter Dimension A Dimension B mm mm mm 15 17 40 22 21 43 28 24 46
16 Sitework Pipe Support cont. Figure No. 23 Cold Forming Bend Fixture Radii
Fixing hole size is 5mm. Suitable for a No. 10 woodscrew
A
Nominal Diameter mm Radius A mm 15 120 4 22 176
The recommended support distances for general purpose use are shown in Table No. 4. Where piping is adequately supported or is run within concealed spaces (eg. through suspended timber floors) clips can be reduced or omitted provided that: G Pipe does not form part of an open vent provided for safe operation of heat source. G Pipe does not form a distribution pipe or circuit where effective air venting might be impaired by poor pipe alignment. G Hot pipe will not touch cold pipe or vice versa. G There is no risk that pipes or fittings will come in contact with sharp, abrasive or other potentially damaging surfaces. G There is no risk pipe will come in contact with materials which may suffer damage or discoloration from transmitted heat. Table No. 4 Recommended Clipping Distances
Nominal Diameter Horizontal Runs Vertical Runs mm m 10 0.3 0.5 15 0.3 0.5 22 0.5 0.8 28 0.8 1.0
For improved visual appearance support distances of 300mm are ® suggested for Hep2O in exposed locations. NB: Where the pipe is concealed clipping may not be considered necessary. Cable ties may be used for restraint. ® The cabling ability of Hep2O enables easy installation through noggins, studs etc., and in internal plasterboard/studding walls. Simply carried out, with tails left exposed prior to the plasterboard being installed, this is especially useful for ‘microbore’ plumbing (see page 20).
17 Sitework Pipe Support cont. Partition systems on the market have the built-in facility for cabling ® electrical wiring and this can be utilised for Hep2O pipework. Bending Radius: ® Hep2O pipe can be easily manipulated by hand to form bends of any angle. In order to prevent any long term detrimental effect on the ® material, the curvature of Hep2O pipe should be not less than shown in Figure No. 24.
Figure No. 24 Minimum Bending Radii (8 x pipe diameter)
A
Nominal Diameter mm 10 15 16 20 22 28 A mm 80 120 128 160 176 224
Pipe Installation in Exposed Locations ® Hep2O pipe expands as temperature increases causing it to undulate along its length. This can be visually unacceptable in the case of long exposed runs. Long runs of exposed pipe are unusual in new build where pipework is generally concealed, but may occur in refurbishment. G If the pipework is exposed there are a number of options open to the installer to ensure that a neat, tidy job is achieved: G ® Hep2O pipework, if exposed, can be boxed in (PVC-U trunking or preformed plywood profiles are generally used). G ® Long runs of exposed Hep2O may be unsightly as a result of expansion and therefore the installer may choose to use copper pipe in this instance. Pipe Installation in Concealed Locations ® Hep2O pipework can easily be installed in concealed locations in floors, roof spaces etc. Any expansion which may occur will have little mechanical effect, this being absorbed within the pipe length as undulation which may be ® ignored. Undulation of Hep2O pipe which may occur naturally as a result of expansion, or installation through joists, will not lead to airlocks. ® Installation in difficult locations is aided by the cabling ability of Hep2O ® pipe. If adequately supported, Hep2O in concealed locations needs only to be clipped for system alignment e.g. at changes in direction. Where convenient, cable ties can be used to restrain pipes for system neatness (care should be taken not to overtighten the tie.) The pipe should be able to slide freely through the tie to facilitate thermal movement.
18 Sitework Pipes through Walls and Floors ® Whenever Hep2O passes through brickwork, stone or concrete the pipe should be sleeved. The annular gap between the pipe and the sleeve should be filled with a resilient material to provide effective fire stopping and prevention of noise transmission from one room to another. Laying of Pipe in Floor Screeds ® Unlike metal pipes Hep2O is not affected by cement, limes, mortars, concrete and general corrosion. However, account should be taken of the requirements of the Water Byelaws which require distribution pipework to be accessible - facilitating its removal and replacement. (See page 23 conduit system). Pipes Adjacent to Metalwork ® When running Hep2O adjacent to or through metalwork, it is important to ensure that the pipe cannot make contact with any sharp 4 edges as this could cause damage during thermal movement. Any of the following preventative measures would be acceptable: G For a pipe passing through a small hole drilled in metalwork, fix a resilient grommet in hole. G For a pipe passing through a large hole in metalwork or adjacent to a sharp edge, fix an extruded flexible profile to metalwork. G Provide sufficient local pipe clipping to prevent contact between pipe and metalwork. G Run pipe within a conduit. Piping Noise Reduction Problems with noise are frequently experienced with systems incorporating ® rigid pipes. Hep2O pipe does not transmit noise and with careful ® installation to reduce the source of noise to a minimum, Hep2O can be installed to run almost silently. For example: G Noise can be caused by friction between a pipe and an adjacent or surrounding material, this often occurs with rigid pipes installed beneath ® timber or chipboard flooring. The use of Hep2O can greatly reduce this effect. Holes should be drilled through joists (see this section page ® 13) of sufficient diameter to allow Hep2O pipe to slide freely. This will prevent any friction between underside of floor, and more importantly avoid ‘ticking’ and creaking normally associated with thermal movement of rigid pipes. G Noise can be caused by pipes knocking together or knocking on hard surfaces in close proximity. Unlike rigid pipes, the inherent elasticity of ® Hep2O would cushion the impact causing less impact noise and absorbing vibrations, preventing the transmission of any sound along pipe. G Similarly noise from ‘water hammer’ resulting from abrupt stoppage of water flow (typically by closure of quarter turn valves, solenoids and ® reverberating ball valves) is normally absorbed by Hep2O and is not transmitted along pipes. NB: Noise generated by central heating pumps is rapidly absorbed by pipes and can be significantly reduced when compared with rigid systems.
19 Sitework Manifolds/Microbore Plumbing ® Hep2O Manifolds are designed for use on microbore central heating systems and can also be used for hot and cold water.
® The Hep2O Manifold in one fitting brings together multiple 10mm pipe connections on the flow or return pipework to one area of a building, enabling easy access when used in ® conjunction with the Hep2O Routabout system. Thus providing instant access below sheet flooring installations for future system modifications or extension.
® A comprehensive range of Hep2O Manifolds is available (Figure No. 25) and these manifolds can be connected in series allowing any number of outlets. Installation and Performance Benefits G ® The Hep2O 2 Port and 4 Port Manifolds provide a cost effective way of connecting 22mm pipe to 10mm pipe as they reduce the number of fittings required. G Fewer fittings reduces installation time. G ® One of the main advantages of the new Hep2O Manifolds is that they are manufactured from polybutylene, an extremely robust yet lightweight material and are therefore, much easier to install. G ® The lightweight Hep2O polybutylene manifolds enable the pipe to be suspended between joists without fear of dragging the pipe down. G Blanking Pegs can be used to close off any unused sockets.
Figure No. 25
® Hep2O Manifold Range
20 Sitework Underfloor Heating Systems ® Hep2O Underfloor Heating Pipe is designed for use in underfloor central heating systems. It is supplied with an oxygen diffusion barrier offering maximum protection against oxygen ingress. The design of the barrier within the wall of the pipe offers significant advantages over underfloor pipes with an external coating. ® Hep2O Underfloor Heating Pipe is available in 16mm and 20mm diameters, in a variety of coil lengths (Table 5). ® Hep2O Underfloor Heating Pipe is manufactured principally from polybutylene (PB) which is more flexible than other materials commonly used for underfloor heating, such as crosslinked polyethylene (XLPE) or polypropylene (PP). The inherent flexibility of 4 polybutylene allows sub-floor heating circuits to be installed quickly ® and easily without the use of tools or heat sources. Hep2O Underfloor Pipe is available in a variety of coil lengths, enabling the installation of long continuous circuits, with minimal pipe wastage. ® Hep2O Underfloor Heating Pipe is corrosion resistant and unaffected by corrosion inhibitors when used as recommended by the manufacturer. ® For further information on Hep2O Underfloor Heating Systems visit www.hep2O.co.uk
Figure No. 26 Figure No. 27
Table No. 5 Underfloor Heating Pipe Lengths 16mm 60m 80m 100m 150m 200m 500m
21 Sitework Routabout ® Hep2O Routabout Hole Cutter This unique system solves the problem of underfloor access found by all builders, plumbers and other trades. A 250mm diameter opening can be cut and made good in minutes. Designed for use in new or existing 18mm & 22mm chipboard or similar floors, the Routabout cuts only the thickness of the board, thus leaving no waste and the piece cut out is used to make good the floor. You will also need: G 1 1 1 x /4 inch or /2 inch collet to fit a medium sized plunging type router (not supplied). G 1 x 30mm (outside dia) guide bush - fitted to router (not supplied). G Router (750 watts or above). G Routabout rotating template.
Figure No. 28 G Router G Tungsten router cutter G Routabout rotating template G Routabout spacer ring
Figure No. 29 G Routing the flooring sheet using the Routabout rotating template.
Figure No. 30 G The routabout spacer ring provides access in the floor sheet to the pipework.
Figure No. 31 G The chipboard cutout fits snuggly into the spacer ring, leaving a neat access.
22 Sitework Conduit Systems ® The Hep2O Conduit system allows pipe and fittings to be installed directly into concrete floors or into walls whilst complying with the requirements of the Water Regulations.
® The flexible conduit allows Hep2O to be withdrawn for inspection, and junction boxes allow maximum accessibility to fittings for inspection and possible removal. To allow pipework to be easily replaced or terminated in the future only ® Demountable fittings should be used within the junction boxes. Hep2O 22 x 10mm manifolds can be used in conjunction with spigot tees in 22 x 15mm and 15 x 10mm sizes to build up various manifold configurations. If any bent sections of conduit pipe are formed in an ® installation then future replacement of the Hep2O is likely to require 4 the use of a ‘draw cable’. In this event the draw cable should be attached to one end of the ® Hep2O before it is pulled out from the other end. Replacement of a ® new section of Hep2O pipe may require two operatives; one pulling the draw cable which is attached to the pipe end and the other person feeding-in the new length from the opposite end. Future replacement will be easier if conduit bends are kept to a minimum and any radius kept as large as practicable. The system consists of two sizes of flexible conduit, junction boxes with lids and terminal fittings. Holes can be cut in the sides of the junction box at the appropriate position to accommodate the conduit which simply clicks into position.
® Hep2O Conduit Pipe is available in the sizes shown in Table No. 6. Table No. 6 Conduit and Pipe in Pipe Lengths 10mm 15mm 22mm 28mm Conduit Pipe (Black Conduit) 25m 50m Pipe in Pipe (Red and Blue Conduit) 25m 50m
® ® Hep2O Pipe in Pipe System (Figure No. 32) incorporates Hep2O Barrier Pipe in a pre-sheathed conduit ready for underscreed installation, thus allowing the installer to save time and effort whilst complying with the ® current regulations. Hep2O Pipe in Pipe is available in the handy site managable coil lengths shown in Table No. 6. The Pipe in Pipe system is available in red and blue conduit to aid the identification of the pipe. Figure No. 32 Pipe in Pipe Coil
23 Sitework Installation Recommendations ® The Hep2O pipe should be fed into position at the same time as the conduit system is installed i.e. before screeding. The conduit system should not be installed on sub-floors a long time in advance of screeding as damage by site traffic could occur. The junction box is designed to gain access to pipe fittings, and to allow pipe cross-overs (which are normally undesirable within the floor screed material). Dimensions are shown in Figure No. 34. If required the junction box can be cut in half and installed up against a wall (Figure No. 35). The junction box should be drilled using a hole cutter or spade bit, to allow the conduit to fit snugly and click into position to protrude not less than 5mm inside the box. Conduit pipe OD’s are shown in Table No. 7. NB: The prevention of cold water becoming warm is a Water Regulations requirement.
Figure No. 33 Conduit Junction Box HX100
Note: Central heating pipework should not be run within the same junction box as cold water pipework unless there is sufficient space to fix adequate thermal insulation, in order to prevent the warming of cold water.
Figure No. 34 Figure No. 35 Junction Box Dimensions Cut Junction Box 377mm Plan Hep2O pipe to radiator or sanitary appliance 202mm Junction Box Lid 170mm
340mm Side Hep O elbow 75mm 2 Section 322mm
165mm 160mm End 75mm Section
150mm N.B: Junction Box cut in 1. All dimensions are nominal. half and secured to 2. Lid recess is designed for 8mm thick plywood. sub floor 24 Sitework Installation Recommendations cont. Table No. 7 Drill Size for Conduit Box Holes
Hep2O Size Conduit Code Conduit (mm) OD (mm) 10 & 15 HXC25/15 - HXC50/15 - HXXC50/10 - HXXC50/15 25 22 HXC25/22 - HXC50/22 - HXXC50/22 34 28 HXXC25/28 42
The junction box should be fixed to the sub-floor (in order to prevent movement or ‘floating’ during screeding) the fixings should be provided with suitable washers. The junction box should be fixed so that the lid (when fitted) will be level with the adjacent floor finish. For uneven sub-floors or where the screed depth exceeds the junction box height, the box should be provided with suitable packing support under the base. 4
Figure No. 36 Typical Section Showing Junction Box Installed on Hot and Cold Water Distribution Pipes at Tees
Small insulating Thermal insulation Finished Junction box lid, pad, cut and barrier formed floor drilled and secured placed to across junction box. level by fixing screws separate pipes (if necessary). at cross-over
Conduit Junction box Tee on cold Tee on hot Pipe secured to the water pipe water pipe sub-floor
Remember: No thermal insulation would be necessary where the junction box is used solely for central heating pipes.
® To facilitate the possible removal and replacement of Hep2O within the conduit system, conduit pipe should be installed without joints and should ideally run in straight lines between junction boxes. Where bends are unavoidable there should be not more than two changes of direction between adjacent junction boxes. Conduits carrying cold water pipes should not touch conduits carrying hot water or central heating pipes. When running conduits within floor screeds the recommended gap between such conduits should not be less than 50mm (see Figure No. 37, page 26) in order to prevent the warming of cold water. The conduit system should not contain unused water pipes which remain connected to water systems. Redundant pipework will result in water stagnation which would pose a risk to health.
25 Sitework Installation Recommendations cont. Figure No. 37 Minimum Spacing for Cold Water Conduit in Floor Screeds
50mm (min)
Conduit for cold water pipe Conduit for hot water or central heating pipe
Conduit pipes should be fixed to the sub-floor by using suitable straps to prevent movement. Conduit pipes for cold water systems should not be run in floor screeds which incorporate underfloor heating ‘loops’.
Figure No. 38 Conduit Terminal Fittings
HX101/15 HX103A HX103 15mm Conduit Terminal Terminal Fitting Plate Terminal Back Plate
For terminating the conduit pipe at wall and floor finish level for direct 15mm connections to appliances, a conduit terminal fitting is available (HX101/15). For floor terminations the plastic housing may be drilled through the base to allow fixing. Floor termination procedure is shown in Figure No. 39. Figure No. 39 HX101/15 Conduit Terminal Installation Procedure
26 Sitework Installation Recommendations cont. For wall terminations two alternative fixing plates are available. The HX102 Terminal Fitting Plate and HX103 Terminal Back Plate, shown in Figure No. 38. The HX103 can be used to mount two terminals side by side (Figure No. 40), or it can be easily split to form two single plates. The HX103 Terminal Back Plate can also be used to fix a maximum of four Wall Plate Elbows. (Figure No. 41).
Figure No. 40 Figure No. 41 HX101/15, 15mm Conduit Terminal HX103, Terminal Back Plate and and HX103 Terminal Back Plate HX6/15 Wall Plate Elbow
4
Figure No. 42 Installation of HX102 Terminal Fitting Plate and HX101/15, 15mm Conduit Terminal
27 Sitework
® Hep2O Within Dry Lined Walls Installers have found that feeds to radiators run in microbore copper can be accommodated behind ‘dot and dab’ plasterboard to give a pipe-free ® appearance within the room. Pipes run in 10mm Hep2O are equally suited to this application but will not be susceptible to damage such as dents or kinks which can be caused on ‘soft’ copper by following tradesmen. The penetration through the plaster board for a radiator connection can be achieved by using a 10mm SlimLine elbow (HX5/10) together with a Fitting Clip (HX84/10 see Figure No. 44) or alternatively a dry lining box can be used (see Figure No. 46).
® Another method when using 10mm Hep2O Pipe is to utilise the HX111 or HX113 Radiator Outlet Cover Plates. The Cover Plates (HX111 & HX113) and Radiator Outlet Back Box (HX109 Plastic, for stud wall; HX110 Metal, for solid wall) allow for a superior and easy to install method of connecting radiators. The box is fixed in a central position behind the radiator with the 10mm pipes dropping out to the radiator valves. This gives a smart professional finish where little or no pipe is seen and for new build provides an anchor point for the pipe work prior to plastering/boarding.
Figure No. 43 Installation procedure of HX111 Cover Plate
28 Sitework
® Hep2O Within Dry Lined Walls cont. The following is good practice for ‘first-fix’ pipework: G Radiator ‘drops’ should be run vertically, side by side, at one end of the radiator position. G Lateral pipes should be run horizontally in line with plasterboard penetrations. G Avoid running pipework along any obvious fixing zone ie. at skirting level.
Figure No. 44 10mm Fitting Clip (HX84/10)
Two 5mm fixing holes, one each side 4 For fixing pipework to lightweight blockwork the HX65 pipe clip is not suitable for fixing directly to such walls because of the low pull-out resistance of the nail. In such circumstances a more secure hold can be achieved by fixing wooden dowels at each clip position. The dowels should be the solid type with a serrated surface and of sufficient size (not less than M8 x 30mm). Holes should first be drilled in the blockwork using a drill bit size which provides a tight fitting hole for the dowel, taking care not to over- drill the hole depth. After tapping in the dowels the pipe clips can then be fixed by knocking the nail into the centre of each dowel.
® Figure No. 45 Radiator Pipework in 10mm Hep2O Within Dry Lined Walls
Thermostatic Radiator Valve (HX71/10)
90° M & F Elbow Pipe Clip (HX4/10) (HX84/10)
Skirting board 90° Elbow Radiator (HX5/10) Draincock (HX23/15) 90° M & F Elbows (HX4/10)
29 Sitework
® Hep2O Within Internal Drywall Systems ® Hep2O can easily be cabled within timber studwork and within wall systems (eg. Paramount Board) during construction. This method is often used for running feeds to radiators or where concealed plumbing is necessary eg. supplies to a recessed shower mixer. A connection for a radiator can be made by using a secured elbow in the wall and fixing a plastic snap-on escutcheon to neatly cover the hole through the wall surface. ® Alternatively for 10mm Hep2O a dry lining box can be used which gives the advantage of allowing minor alignment adjustment to the ‘tail’ during ‘second-fix’ (see Figure No. 46) and allowing access to the elbow. ‘First-fix’ pipework should follow the good practice advice in the text headed ® ‘Hep2O within Dry Lined Walls’ on this page, and ‘Pipes Adjacent to Metalwork’ on page 19.
® Figure No. 46 Radiator Connection using 10mm Hep2O and a Dry Lining Box within a Drywall
10mm Hep2O
Single socket elbow, use SlimLine type for neatness (HX4/10)
Dry lining box and cover plate (single gang electrical fitting)
Demountable elbow (HX5/10) Non-load bearing internal drywall system NB: This solution can also be used where the radiator is fed from below in which case the risers should be located directly under each box.
® Hep2O Within Timber Framed and Steel Framed Buildings ® Hep2O is ideal for use within both timber framed and steel framed buildings. For recommendations applicable to internal partition walls refer ® to the text headed Hep2O within Internal Drywall Systems’, on page 30. Running pipework of any material within the external wall of framed buildings should not be done without consideration of the following:- G If a leak occurred on a pipe it should be discovered without delay as seepage within a wall may damage the structural frame and affect the performance of insulating materials. G Water Byelaws require that pipes should not be fixed in a situation where leaks could be undetected for long periods. 30 Sitework
® Hep2O within Timber Framed and Steel Framed Buildings cont. G Where a pipe passes through a vapour control layer the installation method should allow possible future replacement of pipe without affecting the integrity of this layer. G Pipework should be installed on ‘warm’ side of thermal insulation layer. To comply with the foregoing criteria, pipework should be either run within a recessed duct designed by the Architect or run within a conduit system. Whichever method is used it is necessary to consider the detail at the junction between the wall and floor to avoid floor joist problems and to agree pipe penetrations at header rails/bottom rails. For radiator ® connections, 10mm Hep2O within conduit pipe may be used (see Figure No. 47) The suggested installation sequence is as follows: 4 1. Prepare sketches showing setting-out dimensions for each dry lining box including height and hole size. 2. Fix each conduit pipe to noggins using suitable straps or cable ties. Fixings at 1m centres are adequate for vertical conduit pipe. Horizontal runs and bends more than 45° should be avoided. 3. To allow future installation of dry lining boxes, each conduit pipe end should be left approximately 100mm longer than box position and should not be fixed closer than 600mm to the box. 4. Install the main ‘first-fix’ pipework leaving joints below floor access covers to allow connection to conduit pipework during ‘second fix’ work.
® Figure No. 47 Radiator Connection Using 10mm Hep2O Within Timber or Steel Framed External Wall
Plasterboard 10mm When cutting Hep2O vapour control plasterboard 15mm care should be (nominal) taken not to displace vapour Conduit Pipe control material The conduit should be firmly terminated within dry lining box
Demountable elbow Hep2O Single (HD5/10) Socket SlimLine Elbow (HX4/10) Dry Lining Box and Cover Plate (single gang electrical fitting)
Insulating material
31 Sitework
® Hep2O within Timber Framed and Steel Framed Buildings cont. 5. Using setting-out dimensions on sketches, holes in plasterboard can be cut to allow each conduit pipe to be pulled out through the surface during plasterboard fixing work. 6. During ‘second fix’ each dry lining box is installed by drilling a 26mm diameter hole for 15mm (nominal) conduit pipe. The conduit can then be inserted through hole in box and should ‘click’ into position leaving one or two conduit ‘ribs’ inside box. ® 7. Slide a length of 10mm Hep2O pipe through conduit pipe from the ® floor access above. Pull out enough Hep2O from dry lining box to allow a sufficient hand grip for jointing. Connect a demountable elbow to pipe then slide whole assembly through plasterboard hole and secure box into position. Conduit pipe should ‘snake’ within void to ® take up slack leaving Hep2O protruding out of box. ® 8. Pull Hep2O pipe backwards from floor access panel until elbow is central within dry lining box. Cut pipe to length and connect to ® Hep2O joint left during ‘first fix’. Timber or Steel Framed Buildings - General Advice: Holes through timber joists should be drilled in accordance with Figure No. 19 & 20, on page 15. Holes through timber studs should be drilled in accordance with Figure No. 48. Within steel framed buildings pipework should be routed through preformed holes in steelwork wherever practicable (and where provided). No holes should be formed in steelwork without the approval of the Architect. Pipework Figure No. 48 Limitations of Drilling passing through Studwork steelwork should be protected from damage
(refer to the text headed ‘Pipes Adjacent to Metalwork’ on page 19). Do not lay pipework in areas where plasterboard 0.25 x H
is likely to be fixed. 0.4 x H Services within Holes should compartment or party be located in walls should be avoided these zones D and drilled at so as not to impair fire centre of stud resistance or acoustic depth ‘H’ Stud Height properties. Care should be taken that pipework passing 0.4 x H through compartment walls or floors does not 0.25 x H impair the fire resistance of the property.