PART III
HYDRO-HYDRAULIC MODELLING
Vol. I: Main Report, Part III: Hydro-Hydraulic Modelling WUP-JICA, March 2004
PART III HYDRO-HYDRAULIC MODELLING
1. DEVELOPMENT OF HYDRO-HYDRAULIC MODEL FOR THE CAMBODIAN FLOODPLAINS
1.1 Background of Model Development
This Part III of the Main Report outlines all modelling activities carried out during the entire period of the WUP-JICA project/study including the model origin in the Mekong Basin and a similar improvement in the related project. In the initial stage of the study, some hydro-hydraulic simulation models were needed simultaneously with the monitoring activities to verify the observed data and to clarify the hydrological or hydraulic mechanisms in the basin. After a series of discussions with the MRCS due to the apprehension on overlapping of activities with the WUP-A and WUP-FIN projects, the WUP-JICA Team had decided to take over and further develop the model developed by the recently completed project of MRC.
A brief description of the first study on the Mekong where MIKE 11 has been applied applied and the link to the other project where the model was used simultaneously with the WUP-JICA study for detailed flood analysis is herein presented. The part also explains the concepts of the two model systems applied; namely, the rainfall-runoff model and the hydraulic river and floodplain model. The coupling of the two models was studied as well. A detailed description of the topographical and structural data used for model construction is herein given, the hydrological and hydraulic data applied for model calibration or verification is described, and the detailed layout of the models together with the calibration or verification results for the years 1998-2001 is presented.
The model established was used to derive the water balance in the Tonle Sap Lake for the years 1998-2001. The outcome of the water balance study is herein likewise presented.
1.2 Process of Model Development
1.2.1 Chaktomouk Project Model
The Chaktomouk Project was conducted from 1999 to 2000 as one of the MRCS projects funded by the Government of Japan(1). As part of the Chaktomouk Project, a MIKE 11 model was established for the Mekong-Tonle Sap-Bassac river system to provide boundary conditions for a detailed two-dimensional morphological river model (MIKE 21C) that was set up for the Chaktomouk junction. The two-dimensional model was thus the main modelling tool in the project, supported by the one-dimensional river model MIKE 11 with information that could not be obtained from data alone.
The MIKE 11 model, which includes the Tonle Sap and the Great Lake, was set up with its upstream boundary at Kratie on the Mekong and the downstream boundaries at Tan Chau on the Mekong and Chau Doc on the Bassac in Vietnam. The reasons for this wide coverage of the model were: (1) the four river branches close to the Chaktomuk junction had no record of water level and discharge; and (2) the boundaries of the MIKE 11 should be unaffected by changes in the junction caused by the various options studied with the two-dimensional model. Fig. III-1-1 shows the layout of the MIKE 11 model used in the Chaktomouk Project.
Given the above, the focus of the one-dimensional model was to obtain agreement between model results and observations in the four river branches close to the Chaktomuk junction as well as some distance away from the junction. The latter was because it has been recognised that the exchange
III - 1 Vol. I: Main Report, Part III: Hydro-Hydraulic Modelling WUP-JICA, March 2004 of water with the floodplains was significant and hence necessary to represent it in the model. However, since the details of flow on the floodplains were not a focus in the project, the floodplains were schematised in a relatively coarse manner. This approach was valid since the model philosophy implies that if the conditions near the junction as well as at some distance from the junction could be simulated by the model, then the overall exchange with the floodplains would implicitly be represented in the model.
Fig. III-1-1 One-Dimensional Model of the Chaktomouk Project (Links with floodplains and river courses are shown in red.)
The access to rainfall data has been limited in the study and, besides, there were no discharge measurements available at the tributaries to carry out a direct calibration of the rainfall-runoff model. The calibration of this part of the model was therefore implicitly part of the river model calibration. Altogether five rainfall stations were used for the rainfall-runoff simulation.
During the Chaktomouk Project an extensive measurement campaign was carried out to obtain bathymetry, as well as discharge and sediment data and information. Advanced technology such as ADCP for velocity and discharge measurement was applied. The data was employed in constructing the models and the calibration/verification of the models.
For calibration of the one-dimensional model, the ADCP discharge measurements at the junction and at far distance from the junction taken in the pre-flood, flood, and post-flood periods were used. This was the first time in recent years that discharge data were obtained simultaneously at a number of stations in Cambodia. It was also the first time in recent years that advanced modelling system was used by applying such data. Fig. III-1-2 shows the main output from the ADCP measurement campaign carried out during the Chaktomouk Project in the year 2000.
III - 2 Vol. I: Main Report, Part III: Hydro-Hydraulic Modelling WUP-JICA, March 2004
Fig. III-1-2 ADCP Survey Results during the Chaktomouk Project in 2000
1.2.2 WUP-JICA Model
The MIKE 11 model developed in this WUP-JICA Study takes offset in the model constructed for the Chaktomouk Project. This means that some of the model elements such as the schematisation of the main river branches were adopted from the Chaktomouk Model. However, extensive modifications/additions were made to meet the specific purposes of the WUP-JICA study. The improvement works to the model were made in a continuous process as data and information became available during the study. These modifications/additions for model improvement are thoroughly described in Section 1.3 of this Chapter.
The overall purposes of the modelling component of the WUP-JICA study were:
(1) Study on the flow regime in the Mekong river system in Cambodia including: