Dissolved Gas Analysis (DGA) of Current Transformer (CT) Oil – a Reliable Tool to Identify Manufacturing Defects

Total Page:16

File Type:pdf, Size:1020Kb

Dissolved Gas Analysis (DGA) of Current Transformer (CT) Oil – a Reliable Tool to Identify Manufacturing Defects 1 Dissolved Gas Analysis (DGA) of Current Transformer (CT) oil – A reliable tool to identify manufacturing defects A.K. Datta, S.C. Singh, S.K. Mishra and S. Suresh Power Grid Corporation of India Limited ABSTRACT: Current Transformer (CT) and Capacitive Voltage Transformer (CVT) are important equipment in any electrical installation. The protection, metering and operation of the sub-stations are decided based on their inputs. In our past experience, it was found that many CTs and CVTs have failed during service and some time in a few months after the initial commissioning. Present paper discusses about prevention of failure of CTs by carrying out DGA of CT oil as a standard practice, after commissioning and also in case of violation of CT parameter such as C & Tan-Delta with respect to commissioning value during service life of CT. It also covers two case studies--- first case is related to generation of gases within 2 – 3 months after commissioning in some of CTs supplied in batch of 48 Nos. and the second is about CT with three years of service life found with increase in Tan-Delta value. Paper covers various measurements carried out at sites and subsequent shifting of CTs to respective manufacturer’s works, for detailed testing including high voltage insulation tests. In this paper, it is established that the DGA of CT oil indicates a clear sign of incipient fault in CTs, if not taken care of same, premature failure of CT is unavoidable. Keywords: DGA - Dissolved Gas Analysis CT - Current Transformer CVT - Capacitive Voltage Transformer PD - Partial Discharge 2 Nomenclature: Name Symbol Nitrogen N2 Oxygen 02 Hydrogen H2 Carbon monoxide CO Carbon dioxide CO2 Methane CH4 Ethane C2H6 Ethylene C2H4 Acetylene C2H2 INTRODUCTION: Power Grid Corporation of India (POWERGRID) is one of the largest 400 kV / 220 kV / 132 kV transmission utility in the world operating about 55000 circuit kms and 95 sub-stations having transformation capacity of 49500 MVA, with average availability of system on yearly basis more than 99%. POWERGRID is having stringent system for maintenance of high voltage switchyard equipment. All equipments are tested as per the standard pre- decided frequency and test results are analysed in detail, for identification of defects in the equipments. The population of 400 / 220 / 132 kV Current Transformers in POWERGRID network is approx. 3200, these include both Dead and Live tank design and majority of CTs are oil immersed. The paper discuss about the introduction of DGA test for CT oil as standard test apart from routine tests at site. Normally Tan delta & Capacitance, Thermography of CT are being carried out on yearly basis apart from other tests. Inspite of doing all the best possible maintenance, failure of CTs are observed at all voltage levels (400 / 220 / 132 kV). Failure status of CT is indicated at table- 1. 3 S.No Make Population No.of failure No.of failure Newly (3-15 yrs) commissioned 1 Manufacturer-1 695 74 5 2 Manufacture -2 1046 5 17 3 Manufacture -3 168 0 4 4 Manufacture -4 174 0 3 5 Manufacture -5 872 4 3 6 Manufacture -6 42 3 0 7 Manufacture -7 132 0 0 TOTAL 3129 86 32 Table-1 The cases of failure of CTs can be divided into two categories viz. failure of CT within a year of commissioning and failure of CTs after three years and more in service. Power Grid have established two nos. oil Lab for conducting various test as per IEEE-C57.104 and DGA of oil is being used as one of important tool, for identifying the fault of transformer and reactors since last 15 years. With successful interpretation of DGA results, failure of number of transformers and reactors were avoided in the past. As CT is also oil filled equipment, DGA of CT was also started since last 4 – 5 years on case to case basis. Initially, DGA of CT was opposed by the manufacturer with the pretext that CT has limited oil capacity and functioning of CT may deteriorate due to breakage of hermetically sealing of the CT. But with our experience, it was found that DGA is a very important tool, for identifying the manufacturing process defects or aging affect of CT at the very initial stage. The maximum admissible values for sealed instrument transformer without any action to be taken on the transformer are as below (as per IEC 60599) H2 CO CO2 CH4 C2H6 C2H4 C2H2 300 300 900 30 50 10 2 The paper discusses about two Case Studies, which correlates evolution of gases with inconsistency in manufacturing in CTs. 4 CASE STUDY – I: In one of the newly commissioned projects, 48 Nos. of 400 / 220 kV CTs were supplied in one manufacturing lot in the year 2004 – 05. The CTs were commissioned in July – Aug. 2005. One no. CT of 400 kV has failed after 51 days of charging of the CT. As all the test results both at factory and site were perfectly in order for all the CTs including that of failed CT, the manufacturer contended that it may be an isolated case and CT has failed due to lightening affect as the CT failed in rainy season under thunder storm. But it was decided that DGA of oil of all the CTs shall be carried out and accordingly DGA was carried out and results are tabulated as under: Sl. No. Sample TGC N2 O2 Total Date (%) (%) (%) H2 CH4 C2H4 C2H6 C2H2 CO CO2 Furans 1 30-Oct-05 3.35 2.24 0.84 83 1 0 0 0 63 184 0 2 30-Oct-05 3.37 2.2 0.71 156 2 0 0 0 54 216 0 3 30-Oct-05 3.65 2.37 0.8 223 1 0 0 0 53 243 0 4 30-Oct-05 2.91 1.98 0.7 65 1 0 0 0 53 153 0 5 30-Oct-05 4.37 2.91 1.04 88 1 0 0 0 86 197 0 6 30-Oct-05 2.91 2.02 0.66 69 1 0 0 0 84 169 0 7 30-Oct-05 2.77 1.84 0.74 216 2 0 0 0 26 198 0 8 30-Oct-05 3.35 2.29 0.85 79 1 0 0 0 53 181 0 9 9-Dec-05 7.48 5.35 1.69 741 35 6 2 46.8 49 1380 0 10 9-Dec-05 9.06 6.67 1.97 128 2 0 0 0 95 276 0 11 9-Dec-05 4.1 2.85 1.03 199 3 0 0 0 87 585 0 12 9-Dec-05 5.43 3.65 1.55 138 1 0 0 0 35 475 0 13 9-Dec-05 5.42 3.75 1.43 210 1 0 0 0 45 221 0 14 9-Dec-05 3.66 2.46 0.98 134 2 0 0 0 59 195 0 15 9-Dec-05 3.81 2.52 1.09 162 2 0 0 0 78 324 0 16 9-Dec-05 2.2 1.46 0.6 123 2 0 0 0 40 292 0 17 9-Dec-05 3.37 2.31 0.9 96 2 1 0 1.3 104 434 0 18 9-Dec-05 4.83 3.49 1.19 94 2 0 0 0 104 281 0 19 9-Dec-05 4.39 3.01 1.21 118 2 0 0 0 84 226 0 20 9-Dec-05 3.67 2.54 1.01 158 2 0 0 0 65 208 0 21 8-Dec-05 5.84 4.23 1.45 133 2 0 0 0 89 183 0 22 8-Dec-05 6.88 5.02 1.61 128 2 0 0 0 58 253 0 23 8-Dec-05 4.88 3.68 1.06 123 2 0 0 0 74 487 0 24 8-Dec-05 3.37 2.36 0.89 182 3 1 0 2.8 72 245 0 25 8-Dec-05 9.11 6.65 2.94 94 2 0 0 0 60 420 0 26 8-Dec-05 3.08 2.12 0.8 127 3 0 1 0.3 59 229 0 27 8-Dec-05 2.64 1.77 0.76 207 2 0 0 0 33 232 0 5 28 8-Dec-05 2.94 2.07 0.75 421 1 0 0 0 52 254 0 29 8-Dec-05 2.5 1.72 0.67 262 2 0 0 0 29 178 0 30 17-Dec-05 9.37 7.51 1.36 922 2 0 0 0 118 787 0 31 17-Dec-05 8.54 6.73 1.4 361 5 0 2 0 102 234 0 32 17-Dec-05 8.51 6.45 1.51 308 2 0 0 0 70 1113 0 33 17-Dec-05 8.89 6.62 1.74 343 1 0 0 0 105 1049 0 34 17-Dec-05 8.07 6.41 1.16 606 2 0 0 0 101 266 0 35 17-Dec-05 8.02 6.5 1.06 749 3 0 0 0 61 242 0 36 3-Jan-06 7.72 6.43 1.06 562 2 0 0 0 91 268 0 37 3-Jan-06 8.8 6.87 1.61 649 1 0 0 0 139 512 0 38 3-Jan-06 9.16 7.47 1.32 1143 2 0 0 0 149 785 0 39 3-Jan-06 7.55 6.25 0.98 749 2 0 0 0 110 174 0 40 3-Jan-06 8.68 7.34 1.15 533 2 0 0 0 132 601 0 41 3-Jan-06 10.5 8.26 1.96 187 2 0 0 0 96 381 0 42 3-Jan-06 9.95 8.43 1.16 518 2 0 0 0 125 534 0 43 3-Jan-06 9.62 8.12 1.14 482 2 0 0 0 121 545 0 44 3-Jan-06 9.37 7.97 1.17 466 1 0 0 0 113 241 0 45 3-Jan-06 9.06 6.98 1.58 427 2 0 0 0 100 1170 0 46 3-Jan-06 9.83 7.9 1.22 3053 80 0 8 0 224 642 0 47 3-Jan-06 9.08 7.12 1.63 578 2 0 0 0 151 357 0 48 3-Jan-06 9.62 7.83 1.23 3077 70 0 7 0 216 346 0 As can be seen from the results, in majority of the CTs, content of Hydrogen is comparatively high, even after only few days of charging of CT.
Recommended publications
  • Diploma in Electrical and Electronics Engineering PAGE 1
    ` DIPLOMA IN ELECTRICAL AND ELECTRONICS ENGINEERING COURSES OFFERED CODE COURSE CREDITS YEAR/SEMESTER 15O A) FOUNDATION COURSES : (49 CREDITS) (COMMON FOR ALL PROGRAMMES) 0101 Communicative English – I 5 I/ODD 0102 Engineering Mathematics-I 8 I/ODD 0103 Engineering Physics – I 5 I/ODD 0104 Engineering Chemistry – I 5 I/ODD 0105 Engineering Physics- I Practical 1 I/ODD 0106 Engineering Chemistry – I Practical 1 I/ODD 0107 Communicative English – II 4 I/EVEN 0108 Engineering Mathematics-II 5 I/EVEN 0109 Applied Mathematics 5 I/EVEN 0110 Engineering Physics – II 4 I/EVEN 0111 Engineering Chemistry – II 4 I/EVEN 0112 Engineering Physics – II Practical 1 I/EVEN 0113 Engineering Chemistry – II Practical 1 I/EVEN B) CORE TECHNOLOGY COURSES : ( 43 CREDITS) 0201A Workshop Practical 1 I/ODD 0202 Engineering Graphics-I 3 I/ODD 0203 Engineering Graphics-II 3 I/EVEN 0204 Computer Applications Practical – I 1 I/ODD 0205 Computer Applications Practical – II 1 I/EVEN 3201 Electrical Circuit Theory 6 II/ODD 3202 Electrical Machines - I 5 II/ODD 3203 Electronic Devices and Circuits 5 II/ODD 3204 Electrical Circuits and Machines Practical 3 II/ODD 3205 Electronic Devices and Circuits Practical 3 II/ODD 3206 Electrical Workshop Practical 2 II/ODD 3207 Life and Employability Skills Practical 2 II/ODD 3208 Digital Electronics 5 II/EVEN 3209 Integrated CircuitsPractical 3 II/EVEN Diploma in Electrical and Electronics Engineering PAGE 1 ` C) APPLIED TECHNOLOGY COURSES: (58 CREDITS) 3301 Electrical Machines – II 5 II/EVEN 3302 Measurements and Instruments 4 II/EVEN
    [Show full text]
  • THE ULTIMATE Tesla Coil Design and CONSTRUCTION GUIDE the ULTIMATE Tesla Coil Design and CONSTRUCTION GUIDE
    THE ULTIMATE Tesla Coil Design AND CONSTRUCTION GUIDE THE ULTIMATE Tesla Coil Design AND CONSTRUCTION GUIDE Mitch Tilbury New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore Sydney Toronto Copyright © 2008 by The McGraw-Hill Companies, Inc. All rights reserved. Manufactured in the United States of America. Except as permitted under the United States Copyright Act of 1976, no part of this publication may be reproduced or distributed in any form or by any means, or stored in a database or retrieval system, without the prior written permission of the publisher. 0-07-159589-9 The material in this eBook also appears in the print version of this title: 0-07-149737-4. All trademarks are trademarks of their respective owners. Rather than put a trademark symbol after every occurrence of a trademarked name, we use names in an editorial fashion only, and to the benefit of the trademark owner, with no intention of infringement of the trademark. Where such designations appear in this book, they have been printed with initial caps. McGraw-Hill eBooks are available at special quantity discounts to use as premiums and sales promotions, or for use in corporate training programs. For more information, please contact George Hoare, Special Sales, at [email protected] or (212) 904-4069. TERMS OF USE This is a copyrighted work and The McGraw-Hill Companies, Inc. (“McGraw-Hill”) and its licensors reserve all rights in and to the work. Use of this work is subject to these terms. Except as permitted under the Copyright Act of 1976 and the right to store and retrieve one copy of the work, you may not decompile, disassemble, reverse engineer, reproduce, modify, create derivative works based upon, transmit, distribute, disseminate, sell, publish or sublicense the work or any part of it without McGraw-Hill’s prior consent.
    [Show full text]
  • IEEE/PES Transformers Committee
    Transformers Committee Chair: Sue McNelly Vice Chair: Bruce Forsyth Secretary: Ed teNyenhuis Treasurer: Paul Boman Awards Chair/Past Chair: Stephen Antosz Standards Coordinator: Jim Graham IEEE/PES Transformers Committee Spring 2019 Meeting Minutes Anaheim, CA March 24 – 28, 2019 Unapproved (These minutes are on the agenda to be approved at the next meeting in Fall 2019) TABLE OF CONTENTS GENERAL ADMINISTRATIVE ITEMS 1.0 Agenda 2.0 Attendance OPENING SESSION – MONDAY MARCH 25, 2019 3.0 Approval of Agenda and Previous Minutes – Susan McNelly 4.0 Chair’s Remarks & Report – Susan McNelly 5.0 Vice Chair’s Report – Bruce Forsyth 6.0 Secretary’s Report – Ed teNyenhuis 7.0 Treasurer’s Report – Paul Boman 8.0 Awards Report – Stephen Antosz 9.0 Administrative SC Meeting Report – Susan McNelly 10.0 Standards Report – Jim Graham 11.0 Liaison Reports 11.1. CIGRE – Craig Swinderman 11.2. IEC TC14 – Phil Hopkinson 11.3. Standards Coordinating Committee, SCC No. 18 (NFPA/NEC) – David Brender 11.4. Standards Coordinating Committee, SCC No. 4 (Electrical Insulation) – Evanne Wang 11.5. ASTM D27 – Tom Prevost 12.0 Approval of Transformer Committee P&P Manual - Bruce Forsyth 13.0 Hot Topics for the Upcoming – Subcommittee Chairs 14.0 Opening Session Adjournment CLOSING SESSION – THURSDAY MARCH 28, 2019 15.0 Chair’s Remarks and Announcements – Susan McNelly 16.0 Meetings Planning SC Minutes & Report – Tammy Behrens 17.0 Reports from Technical Subcommittees (decisions made during the week) 18.0 Report from Standards Subcommittee (issues from the week) 19.0
    [Show full text]
  • SP0504 Power Transformer Testing
    POWER TRANSFORMER TESTING SWP • Hold current licences for any vehicles and equipment they 1. PURPOSE AND SCOPE may be required to operate. The purpose of this Standard Work Practice (SWP) is to Required Training standardise and prescribe the method for testing power transformers. Staff must be current in all Statutory Training relevant for the task. Testing of current transformers, voltage transformers or auxiliary transformers internal to the power transformer are not included in All workers must have completed Field Induction or have this SWP. recognition of prior Ergon Energy Field Experience. Contractors must have completed Ergon Energy's Generic 2. STAFFING RESOURCES Contractor Worker Induction. Adequate staffing resources with the competencies to safely complete the required tasks as per MN000301R165: 8 Level Field 3. DOCUMENTATION Test Competency CS000501F115 . Daily/Task Risk Management Plan These competencies can be gained from, but not limited to any or ES000901R102 . Health and Safety Risk Control Guide all of the following:- SP0504R01. Power Transformer Testing Job Safety Analysis • Qualifying as an Electrical Fitter Mechanic. SP0504C01R01. Power Transformer IR and DDF Temperature • Qualifying as a Technical Service Person. Correction • Training in the safe use of relevant test equipment. SP0504C04. Power Transformer No Load Loss Test Report Requirement for all live work: SP0504C05. Power Transformer Load Loss Test Report • Safety Observer (required for all “live work” as defined in SP0504C06. Power Transformer Load Loss and Impedance the ESO Code of Practice for Electrical Work). Calculation All resources are required to: SP0504C08. Power Transformer Testing Competency Assessment • Have appropriate Switching and Access authorisations for the roles they are required to perform and have the ability SP0504C13.
    [Show full text]
  • The Remote Calibration of Instrument Transformers
    The remote calibration of instrument transformers S. Rens orcid.org/0000-0001-8428-3893 Dissertation submitted in fulfilment of the requirements for the degree Master of Engineering in Electrical and Electronic Engineering at the North-West University Supervisor: Prof. A.P.J. Rens Co-supervisor: Prof. J.E.W. Holm Graduation ceremony: May 2019 Student number: 23509333 ABSTRACT Successful operation and control of a power system is dependent on the accurate measurement of field data. Each measurement received is the result of a chain of instrumentation and data handling processes, and with each process a certain amount of uncertainty is introduced in the measurement result. Instrument transformers, additional transducers, analog-to-digital (A/D) converters, scaling and conversion procedures, synchrophasor recorders and communication equipment all contribute to the uncertainty in measurement. Errors in this measurement chain can either be systematic, random or installation errors. Instrumentation transformers convert (and isolate) primary power system current and voltage waveforms into standardised instrumentation circuit values (i.e. 110 V and 5 A) for more convenient measurement purposes. Nominal conversion ratios, specified on nameplates, may differ from the actual conversion ratios due to manufacturing, drift over time and environmental conditions. To eliminate biased measurements received from instrument transformers, calibration of instrument transformers should be performed periodically. Traditionally this has been done by means field work creating an out-of-service condition. It is time-consuming, expensive and labour intensive. An opportunity exists due to the increased availability of synchronous data for the idea of remote calibration of instrument transformers. This idea estimates a ratio correction factor (RCF) for the instrument transformers using synchrophasor data over a transmission line.
    [Show full text]
  • Explore New Paths with the CT Analyzer – Extended Testing Benefits for Your Applications
    Presentation – 4.1 Explore new paths with the CT Analyzer – Extended testing benefits for your applications Florian Predl, OMICRON, Austria Ie excitation current IS secondary current 1. Introduction IP primary current Xm main inductivity of the core This paper describes on the one hand side the principal Rm magnetic losses of the core test procedure of the CT Analyzer and points out the NP,NS amount of turns of the ideal core advantages of this test method in regards to a RCT ohmic resistance of secondary turns conventional high current injection measurement EMF Electro-Motive Force – secondary core voltage method. On the other hand side it elucidates special US secondary terminal voltage current transformer testing applications and reveals RB ohmic part of complex burden attempts at solutions. Furthermore, the CT Analyzer PC XB inductive part of complex burden Tools are introduced and their advantages and φB phase angle of burden possibilities for the individual user are presented. Figure 2 shows the vector diagram of current and voltages for a linear main inductivity. 2. Principal Test Procedure of the CT Analyzer The CT Analyzer measures the losses of a current transformer according to the equivalent circuit diagram of the current transformer, in terms of the copper losses and the iron losses. The copper losses are described as the winding resistance RCT of the current transformer. The iron losses are described as the eddy losses as eddy resistance Reddy and the hysteresis losses as hysteresis resistance RH of the core. With this knowledge about the total losses of the core, the CT Analyzer is able to calculate the current ratio error and the phase displacement for any primary current and for any secondary burden.
    [Show full text]
  • IP 202-1 List of Materials
    Changes to the List of Materials August 3, 2021 1. Page be(2.3) a. Added Siemens i. CMR May 6, 2021 1. Page Ugn-2 a. Added Aluma-Form i. ENC Series April 27, 2021 1. Page Ugk-2.2 a. Added Prysmian i. PCT Series (15, 25, 35kV) February 9, 2021 1. Page be(4.3) a. Added Southern States single-phase SSR type recloser. February 4, 2021 1. Pages rp(1), rp(1.2) a. Revised “Cantega” to “Hubbell Power Systems”. b. Added trademark to Reliaguard. December 10, 2020 1. Page ap-2 a. Modified page number from “1.1” to “2”. November 18, 2020 1. Pages an-3 and an(3.1) a. Moved Virginia Transformer from page an(3.1) Conditional to page an-3 Full Acceptance. November 6, 2020 1. Page ae-1 a. Added Celeco i. Catalog Numbers: HSCEL, RPCEL October 26, 2020 1. Page Uhb-1.1 a. Added TE Connectivity i. Catalog Numbers: 25 kV, used with loadbreak connectors (without test point) - ELB-25- 200 series without jacket seal, ELB-25-200-ES series with jacket seal October 23, 2020 1. Page p(1) a. Added TE Connectivity (Raychem) i. Catalog number: TIL Series September 30, 2020 1. Pages a(3), ea(4), ea(5) – Added new Hendrix insulator models. a. Catalog Numbers: HPI-15VTC, HPI-15VTP, HPI-25VTC-02, HPI-35VTC-02, HPI-35VTP-02, HPI-LP-14FS/FA, HPI-LP-16F, HPI-CLP-15, HPI-CLP-17, HPI-CLP-20 July 7, 2020 1. Page cm-2 – Added Aluma-Form, Inc.
    [Show full text]
  • Outdoor Instrument Transformers
    Outdoor Instrument Transformers Buyer’s Guide Contents Table of Contents Chapter - Page Products Introduction A - 2 Explanations B - 1 Silicone Rubber (SIR) Insulators C - 1 Design Features and Advantages Current Transformers IMB D - 1 Inductive Voltage Transformer EMF E - 1 Capacitor Voltage Transformer CPA/CPB F - 1 Technical Technical Catalogues Information CT IMB G - 1 VT EMF H - 1 CVT CPA/CPB (IEC) I - 1 CVT CPA/CPB (ANSI) J - 1 Optional Cable Entry Kits - Roxtec CF 16 K - 1 Quality Control and Testing L - 1 Inquiry and Ordering Data M - 1 A-1 Edition 5, 2008-03 ABB Instrument Transformers — Buyer’s Guide Introduction Day after day, all year around— with ABB Instrument Transformers ABB has been producing instrument trans- All instrument transformers supplied by ABB formers for more than 60 years. Thousands are tailor-made to meet the needs of our of our products perform vital functions in customers. electric power networks around the world – An instrument transformer must be capable of day after day, all year round. withstanding very high stresses in all climatic Their main applications include revenue conditions. We design and manufacture our metering, control, indication and relay pro- products for a service life of at least 30 years. tection. Actually, most last even longer. Product range Type Highest Voltage for Equipment (kV) Current Transformer IMB Hairpin/Tank type IMB 36 - 800 36 - 765 Paper, mineral oil insulation, quartz filling Inductive Voltage Transformer EMF Paper, mineral oil insulation, quartz filling EMF 52 - 170 52 - 170 Capacitor Voltage Transformer CP CVD: Mixed dielectric polypropylene-film and synthetic oil.
    [Show full text]
  • Practices of Insulating Materials in Instrument Transformers
    500 NATIONAL POWER SYSTEMS CONFERENCE, NPSC 2002 Practices of Insulating Materials in Instrument Transformers A.Masood, M.U.Zuberi, M.S.Alam, E.Husain, M.Y.Khan I. INTRODUCTION TABLE I Type of Test Applied on The study of insulating material selection, behavior and Type Test CT PT performance are important aspects to be considered for Short Time Current Test Yes No designing any electrical instrument, machine or device. Temperature Rise Test Yes Yes Apart from conductors, insulator forms the backbone of Lightning Impulse Voltage Withstand Yes Yes any electrical system. Though insulators form the Test backbone, they are also the weakest link in the system. H.V.Power Frequency Wet Withstand Yes Yes Hence, maximum care and attention is needed while Test choosing insulating materials for a given application so Routine Test that it gives the desired performance under worst working conditions. This paper addresses the problem of selection H.V. Power Frequency Dry Withstand Yes Yes criteria, test specifications and material treatment to justify Test on Primary Winding the use of various dielectrics/insulating materials used for H.V. Power Frequency Dry Withstand Yes Yes insulating high voltage instrument transformers i.e. CTs Test on Secondary Winding and PTs. Over-Voltage Inter-turn Test While in use, insulating materials are subjected to Partial Discharge Test Yes No various electrical, mechanical, thermal stresses and partial Yes Yes discharges. Therefore, criteria for selection of these materials is, that, they must withstand these stresses The temperature rise of winding when subjected to without or with such rate of deterioration such that their continuous thermal current or voltage as applicable to performance is not affected throughout the life expectancy instrument transformer at the rated frequency and of the equipment, which is considered approximately 25- current/voltage output determines the class of insulation or 30 years.[1] dielectric surrounding the winding.
    [Show full text]
  • Theory and Technology of Instrument Transformers
    THEORY AND TECHNOLOGY OF INSTRUMENT TRANSFORMERS TRAINING BOOKLET: 2 The information in this document is subject to change. Contact ARTECHE to confi rm the characteristics and availability of the products described here. Jaime Berrosteguieta / Ángel Enzunza © ARTECHE Moving together CONTENTS 1. Instrument Transformers | 4 5. Other Instrument Transformers | 31 1.1. Defi nitions | 4 5.1. Combined Instrument 1.2. Objective | 4 Transformers | 31 1.3. General Points in 5.2. Capacitive Voltage Current Transformers | 5 Transformers (CVT) | 32 1.4 General Points in Voltage Transformers | 6 6. Dielectric insulation | 33 6.1. Insulation of instrument 2. Theory of Instrument Transformers | 7 transformers | 33 2.1. Basics | 7 6.2. Insulation Testing | 34 2.2. Equivalent Transformer | 8 2.3. Equivalent Transformer Standards | 35 circuit Diagram | 8 7. 7.1. Standards Consulted | 35 7.2. Insulation Levels | 35 3. Current Transformers | 9 7.3. Environmental Conditions | 35 3.1. General Equations | 9 7.4. Current Transformers | 36 3.2. Vectorial Diagram | 9 7.5. Voltage Transformers | 43 3.3. Current & Phase Errors | 10 3.4. Current Transformers for Measuring | 12 3.5. Current Transformers for Protection | 14 3.6. Current Transformers for Protection which Require Transient Regime Response | 16 3.7. Burden | 18 3.8. Resistance to Short-circuits | 19 3.9. Operation of an Open Circuit Current Transformer| 20 3.10. Special Versions of Current Transformers | 20 3.11. Choosing a Current Transformer | 21 4. Voltage Transformers | 22 4.1. General Equations | 22 4.2. Vectorial Diagram | 22 4.3. Voltage & Phase Errors | 23 4.4. Voltage Transformers for Measuring | 24 4.5.
    [Show full text]
  • Transformer Installation, Assembly & Testing
    Transformer Installation, Assembly & Testing W.J. (Bill) Bergman, M.Eng., P.Eng., LSMIEEE PowerNex Associates Inc. [email protected] [email protected] +1-403-288-2148 Intent •Provide explanations as to why certain process are important and should be followed •Describe some examples of what to do and what not to do •Comments on my personal experiences? •Provide references that you can study at your leisure •Answer questions 2019-02-11 / 2019-02-12 W.J. (Bill) Bergman, IEEE - Calgary / Edmonton 2 Format of Presentation •Ask questions •Encourage discussion and understanding (especially on topics where there may be more than one way or procedure to install a transformer). •Please add your experiences. •Please turn your cell phones OFF so we are not distracted by texting, email, etc. 2019-02-11 / 2019-02-12 W.J. (Bill) Bergman, IEEE - Calgary / Edmonton 3 2019-02-11 / 2019-02-12 W.J. (Bill) Bergman, IEEE - Calgary / Edmonton 4 Basis of Presentation •Industry Accepted Practices; •Based on IEEE and other consensus Guides •Practical processes that are based on physics, chemistry and logic •Based on others’ many years experience •Personal Experience •Have personally done this work on transformers from 10 to 750 MVA, 72 to 550 kV for 50 years (proving [to me] processes are possible & practical) 2019-02-11 / 2019-02-12 W.J. (Bill) Bergman, IEEE - Calgary / Edmonton 5 Topics 1. RECEIVING a transformer after transport to a substation site 2. ASSEMBLY and PROCESSING of a transformer at site 3. TESTING a transformer to verify its suitability for service 4. Discussion of integrating the transformer into the power system 2019-02-11 / 2019-02-12 W.J.
    [Show full text]
  • NIT NO Bid Document
    Bid Document NIT NO :- DGM /ED- I/2015-2016/04 Dated: 16/03/2016 Name of Work :- Implementation of R-APDRP (Part-B) Scheme under Agartala Project (Town Pratapgarh Area): Design, Engineering, Manufacturing, Supply, testing ,Delivery, Erection,Testing at site & commissioning of 33/11 KV, 2X7.5 MVA,Indoor Type Power Sub-Station at NSRCC, Netaji Chowmuhani, Agartala with associated 33KV Underground Rampur Substation- NSRCC S/C Line, 33 KV Bay at Rampur including Control room and boundary wall at NSRCC. (Balance Work). Estimated Cost :- Rs. 1,55,12,109.00 Earnest Money :- Rs. 3,10,242.00 Time for Completion :- 6(Six) Month. The document contain 240(Two Hundred Forty) pages excluding cover pages The document issued to: ___________________________________ Deputy General Manager. Electrical Division No - I Agartala, West Tripura. TRIPURA STATE ELECTRICITY CORPORATION LIMITED (A GOVT. OF TRIPURA ENTERPRIZE) SECTION-I Notice Inviting Tender for :Implementation of R-APDRP(Part-B) Scheme under Agartala Project(Pratapgarh Town Area): for the work: “Implementation of R- APDRP (Part-B) Scheme under Agartala Project: Design, Engineering, Manufacturing, Supply, testing, Delivery, Erection, Testing at site & commissioning of 33/11 KV, 2X7.5 MVA, Indoor Type Power Sub-Station at NSRCC, Netaji Chowmuhani, Agartala with associated 33KV underground “Rampur Sub-Station-NSRCC S/C Line”,33KV Bay at Rampur including construction of control room building and boundary wall at NSRCC. (Balance Work) The Ministry of Power, Government of India is providing financial assistance toTSECL under Re-structured Accelerated Power Development and Reforms Programme(R-APDRP). Projects under R-APDRP shall be taken up in two parts.
    [Show full text]