Construction Unit: Water Source Engineering Construction Management Department of Moba Gorge for City Water Supply of Cheng County Assessment unit: University

Public Disclosure Authorized May 2012

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

Cheng County Moba Gorge Water Source Engineering of Gansu Province

Engineering of Gansu Province

Project Name: Cheng County Moba Gorge Water Source Engineering of Gansu Province

Commissioned By: Water Source Engineering Construction Management Department of Moba Gorge for City Water Supply of Cheng County

Assessed By: Lanzhou University

Supervisor: Wu Junnian

Technical Director: Wu Junnian

Major Establishment Strength: Wu Junnian, Liu Guannan

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

Directory 1. General Instruction………………………………………………………………………….1 1.1 Project Brief…………………………………………………………………………………..1 1.2 Objectives of Environmental Management Plan………………………………………….2 1.3 Compilation of Environmental Management Plan…………………………………………3 1.4 Design of Environmental Management Plan………………………………………………3 1.5 Details of Compilation Technology………………………………………………………….3 2. Policy, Law and Administrative Management Framework…………………………….5 2.1 Environmental Policies and Regulations Document………………………………………5 2.2 Environmental Management Organizations and Responsibilities……………………. 10 3. Project Description…………………………………………………………………………15 3.1 Construction Objective of the Project……………………………………………………..15 3.2 Implementation Schedule of the Project………………………………………………….15 3.3 Project Overview ……………………………………………………………………………15 4. Environmental Impact of the Project and Mitigation Measures Summary ……….19 4.1 Environmental Impact Assessment………………………………………………………19 4.2 Public Participation…………………………………………………………………………46 5. Environmental Management Organization of the Project……………………………47 5.1 Introduction…………………………………………………………………………………..47 5.2 Environmental Organization of Construction Period……………………………………48 5.3 Environmental Management Organization in Operation Period……………………….51 5.4 Details of Environmental Management Organization of the Project…………………..51 6. Implementation of Environmental Management Plan...... 53 6.1 Project Environmental Management...... 53 6.2 Detailed Task for Implementation of Environmental Management Plan………………55 6.3 Contract Requirements of Environmental Management………………………………..57 6.4 Information Exchange and Resolution of Undesirable Condition………………………57 6.5 Training-- Necessary Capacity Building and Means Building…………………………..58 6.6 Land Acquisition Compensation and Resettlement Compensation……………………61 6.7 temporary Site Restoration………………………………………………………………...61 7. Environmental Monitoring Plan…………………………………………………………..63 7.1 Monitoring Purposes………………………………………………………………………..63 7.2 Environmental Monitoring Organization…………………………………………………..63 7.3 Detailed Environmental Monitoring Requirements………………………………………63 8. Acceptance Investigation Content of Environmental Protection Measures……...69 8.1 Investigation of Water Environmental Protection Measures……………………………69 8.2 Investigation of Atmospheric Environmental Protection Measures…………………….69 8.3 Investigation of Acoustic Environmental Protection Measures…………………………69 8.4 Investigation of Solid Waste Treatment Measures………………………………………69 8.5 Investigation of Ecological Protection Measures………………………………………...69 8.6 Investigation of Water Loss and Soil Erosion Control…………………………………..70 8.7 Investigation of Population Health Impact and Protection Measures………………….70 8.8 Investigation for Environmental Protection Measures of Resettlement Area…………70 8.9 Investigation of Risk Prevention Measures………………………………………………71 8.10 "Three Meantime" of Project Acceptance……………………………………………….71 9. Environmental Management Cost Budget and Capital Source…………………….73 9.1 Budget Distribution………………………………………………………………………….73 9.2 Capital Source and EMP Budget………………………………………………………….73 10. Information Management of Environmental Management Plan…………………..75 10.1 Environmental Management Plan……………………………………………………….75 10.2 Information Exchange…………………………………………………………………….76 10.3 Recording Mechanism…………………………………………………………………….77 10.4 Reporting Mechanism…………………………………………………………………….77 Appendix………………………………………………………………………………………...79 Appendix 1 Project Involves Environmental Standards...... 79 Appendix 2 Detailed Project Environmental Management Standards of Contractor……..83 Appendix 3 Detailed Project Environmental Management Standards of Project Operation Department………………………………………………………………………………………87 Appendix 4 Summary of Project Environmental Management Plan and Environmental Action Plan of Construction Period…………………………………………………………….89 Figure Figure 1 Environmental Protection Measures Layout Figure for Cheng County Moba Gorge Water Source Engineering of Gansu Province Figure 2 Water and Soil Conservation Measures Layout Figure for Cheng County Moba Gorge Water Source Engineering of Gansu Province Figure 3-1 Atmosphere and Noise Monitoring Points Figure in Construction Period of Moba Gorge Water Source Engineering of Gansu Province Figure 3-2 Environmental Monitoring Points Figure in Construction and Operation Period Cheng County Moba Gorge Water Source Engineering of Gansu Province Figure 4 Water and Soil Conservation Monitoring Points Figure for Cheng County Moba Gorge Water Source Engineering of Gansu Province

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

1. General Instruction 1.1 Project Brief Cheng County is located in City of the six parts in southern Gansu Province, and located in 105°24 '~ 105°57' of east longitude and 33°31'~ 34°02' of north latitude. The county is east to , west to , southwest to with interval of Western Han River, and the southeast is adjacent to the Lueyang County of Shaanxi Province. The length of north to south is 55 km, the width of east to west is 52 km, the area is about 1701 km2, the highest elevation within the county is 2377 m, the lowest elevation is 50 m, and the county is a relatively wide graben basin in West Qinling fold belt. Cheng County mainly comprises ―One water and three rivers‖, i.e. Western Han River, Qingni River, Nan River and Luo River, the total water resources of the whole county is 1,276 billion m3, in which the self-produced water is 0.331 billion m3. The total land area of the county is 1676.54 km2, the total population is 0.2652 million, of which the agricultural population is 0.218 million people. The benefited area of the project comprises 3 towns and 38 administrative villages, and the total population thereof is 0.103 million people. The county town of Cheng County is divided into Hedong District and Hexi District by taking the East River as the boundary. Hedong District is called as new town, Hexi District is called as old town, and the south of the Nan River is called as new Nanhe District. The population of the urban area is about 80,000. according to the ―Urban Master Plan of Cheng County (2008-2025)‖, the central city comprises Chengguan Town, Paosha Town and Chenyuan Town; to the recent 2015, the population of the central city planed is 130,000, the construction land area is 13 km2; to the forward 2025, the population is 220,000, and the construction land area is 22 km2; to the forward 2025, Chengnan water plant, Hedong water plant and Paosha water plant will be built, and the total amount of urban water supply will be reached to 65,000 m3/d. At present, Cheng County has two tap water supply units for supplying water to the urban area, namely County Tap Water Company and Gaofeng Water Supply Company; the water supply source of County Tap Water Company is the well located in West Bank of Qingni River in the Chengguan Shunjia Dam, the water of the well belongs to the quaternary gap sedimentary water and occurs in gravel layer, and the water is mainly supplied by the water of Qingni River and the atmospheric precipitation; however, the contents of lead and COD contained in the surface water of Qingni River exceed the standards of Class IV in the standard of water environmental quality, and due to the influence of Wenchuan earthquake of Sichuan, the turbidity of the well water in the water source is increased, odor and floaters are presented, and the health of urban residents is impacted seriously; the water supply source of Gaofeng Water Supply Company is Gaofeng water reservoir, and the actual daily water supply capacity of the company is 1000 m3 only as the drainage area of the water reservoir is less than 10 km2 and the spatial and temporal distribution of precipitation is uneven. According to the survey, the existing water supply project of the urban area cannot meet the urban water demand. In order to solve the contradiction of urban water supply, improve water quality, reduce cost of water supply, achieve the sustainable economic and social development of Cheng County and improve the physical health of urban residents, the Water Authority of Cheng County consults with the relevant personnel of the World Bank to build a new urban water supply dam by means of the loans of the World Bank, and the loan planned is 226.563 million Yuan. Cheng County Moba gorge water source project is located in the west of the Cheng County with 11 km, is apart from Paosha Town with 6 km and is located downstream the Nan River basin; the geographic location of the project is as follows: 33°45' -33°38 ' of northern latitude and 105°33'55" - 105°37'60" of east longitude, and the project belongs to Jialing River system upstream the Yangtze River. The content of project construction comprises project construction and management system and institutional capacity building. The project construction mainly comprises dams, water intake structures, water pipelines, and dam roads and etc. The content of management system institutional capacity building comprises water resources and comprehensive environmental management projects based on the concepts and methods of integrated river basin management. The content of institutional capacity building comprises water source engineering construction management department of Moba gorge for city water supply of Cheng County, monitoring and assessment, and management of information system; when the project is completed, the problem of difficult water supply in the urban area of Cheng County can be solved, so that the project has good social and economic benefits. The objectives of the project are as follows: comprehensively and effectively use the water resources of Cheng County, solve the problem that the domestic water of Cheng County after the disaster is difficult, and improve the water environment of Cheng County. 1.2 Objectives of Environmental Management Plan The compilation of EMP aims at developing a set of detailed, technically feasible, financially sustainable and workable environmental measures by targeting to the inevitable potential adverse impact of the project to the environment, clearing the environmental mitigation, environmental management and institution building measures to be implemented by project contractors, supervision side, operators, environment management department in the project construction and operation period, so as to eliminate or compensate the adverse environmental and social impact of the project, and reduce the adverse environmental and social impact to an acceptable level. The specific objectives are as follows: (1) Clear the environmental management obligations of the contractor and the operator The environmental protection bureau of Gansu Province, the environmental protection bureau of Longnan City, the environmental assessment unit and the design unit carry out detailed onsite check and confirmation to the environmental protection targets, and provide effective environmental mitigation measures, wherein the measures are incorporated into the project design and are taken as the contractual obligations of the contractor and the operator of the project construction. (2) Operational guidelines for environmental management The environmental monitoring plan of construction period and operation period provided in the environmental management plan can ensure the effective implementation of environmental mitigation measures, and the monitoring plan will be provided to the construction supervision unit, the environmental supervision unit and other relevant units as an environmental protection file, so as to clear the responsibilities and the roles of the relevant functional departments, and provide the various communication channels and methods among the departments. (3) Ensure the cost of environmental management action In the environmental management plan, the cost of environmental management, environmental supervision and capacity building are estimated, and the capital sources are described, so as to ensure the various environmental management activities can be implemented, wherein the management cost comprises staff salaries, office costs and transportation costs. The role of environmental management plan is in avoiding and controlling the adverse environment effect in the construction and operation process of the project, so that the impact mitigation measures, monitoring measures, legal regulatory means and safeguard measures of the measures above to be implemented are provided; at the same time, the environmental management plan is a critical link in connecting the impact mitigation measures and replacement measures for the assessment and detailed description in the environmental impact and environment assessment. For each environmental management measure, the environmental management plan provides the technical content, the investment estimation, the implementation plan, the functions of government agencies, the capital sources, and the monitoring schemes of the measure. In order to achieve reduction objective, the method involved by the environmental impact assessment report and the environmental management plan must be implemented. 1.3 Compilation of Environmental Management Plan The environmental management plan of the ―Cheng County Moba Gorge Water Source Engineering of Gansu Province‖ is compiled by the engineering environmental assessment unit, the environmental management plan is compiled by strictly complying with national and provincial environmental management regulations. Meanwhile, the environmental management plan particularly paid attention to the requirements of security regulations of the World Bank under the premise of meeting the requirements of 's environmental assessment, specifically refers to relevant provisions of the operation regulation 4.01. The information source for the environmental management plan of the project is as follows: (1) Feasibility evaluation report of the project (2) Preliminary design of the project (3) Environmental assessment of the project (4) Soil and water conservation scheme of the project 1.4 Design of Environmental Management Plan For the detailed description of environmental management, environmental supervision and environmental monitoring and other aspects, the environmental management plan compiled is a guiding document in the implementation process of the project, and the action plan thereof mainly includes the following four parts: Environmental impacts and mitigation measures: the main environmental impacts in project construction period and operation period, and project measures and management measures taken for preventing or mitigating the adverse environmental impact caused by the project. Environmental management and monitoring plan: environmental monitoring action taken for ensuring the synchronous implementation of environmental protection measures and the project construction. Environmental monitoring plan: environmental monitoring action taken for supervising whether the environment of construction period and operation period is standard and ensuring the safe operation of the project and the improvement of project condition in the project area. Capacity building plan (i.e. personnel training): knowledge and skills training of the management personnel, the environmental supervision personnel, full-time or part-time personnel in the project implementation process for ensuring the implementation of environmental management plan. 1.5 Details of Compilation Technology The environmental management plan is compiled by appropriately altering and replenishing on the basis of the ―Primary Design of Cheng County Moba Gorge Water Source Engineering of Gansu Province‖ and the ―Environmental Impact Assessment of Cheng County Moba Gorge Water Source Engineering of Gansu Province‖. As an independent file, the environmental management plan comprises all the environmental management activities to be implemented in the construction period and operation period of the project; and the plan further provides action guidelines and working framework to the adverse impact mitigation measures, environmental supervision, environmental management and environmental monitoring in the construction period and the operation period.

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

2. Policy, Law and Administrative Management Framework 2.1 Environmental Policies and Regulations Document 2.1.1 Overview Through the comprehensive analysis for the type, the size, the location, the environmental sensitivity and the characteristic and degree of potential environmental impact of the project, the main basis of the environmental assessment of the project and the revolved policies, laws and regulations and standards comprise: (1) Environmental protection laws and regulations; (2) Pollution control technology policy; (3) Socio-economic development and environmental protection plans and programs; (4) Overall urban planning; (5) Technical guidelines of environmental impact assessment; (6) Environmental quality standards; (7) Control of pollutant emission standards; (8) Safeguard policies of the World Bank. The policies, laws and regulations and standards above construct a frame for the policies, laws and regulations and standards in guiding and regulating the environmental assessment work of the project. In addition, the environmental assessment of the project takes the feasibility study report and the administrative examination and approval documents of the government administrative authorities and the relevant documents with specific embodiment and application of the policies, laws and regulations and standards above as one of the basis of environmental assessment. 2.1.2 Environmental protection Laws and Regulations (1) ―Environmental Protection Law of the People‘s Republic of China‖, (December 1989); (2) ―Air Pollution Prevention Law of the People‘s Republic of China‖, (September 2009); (3) " Water Pollution Prevention Law of the People‘s Republic of China", (June 1, 2008); (4) " Environmental Noise Pollution Prevention Law of the People‘s Republic of China", (March 1997); (5) "Solid Waste Pollution Prevention Law of the People‘s Republic of China", (April 2005); (6) "Environmental Impact Assessment Law of the People‘s Republic of China", (September 1, 2003); (7) "Cleaner Production Promotion Law of the People‘s Republic of China", (January 1, 2003); (8) " Water and Soil Conservation Law of the People‘s Republic of China", (June 1991); (9) "Forest Law of the People‘s Republic of China", (January 1998); (10) "Wildlife Protection Law of the People‘s Republic of China", (adopted by the fourth meeting of the Standing Committee of the Seventh National People's Congress on November 8, 1988, and implemented from March 1, 1989. The amendment for the ―Decision on the Amendments to the ‗Wildlife Protection Law of the People‘s Republic of China‘‖ in the eleventh meeting of the Standing Committee of the Tenth National People's Congress on August 28, 2004); (11) "Land Management Law of the People‘s Republic of China", (August 28, 2004); (12) "Flood Control Law of the People‘s Republic of China", (January 1, 1998). 2. 1.3 Environmental Protection Regulations, Ministries Rules and Protection List (1) "Implementation Regulations of Soil and Water Conservation Law of the People‘s Republic of China", (August 1, 1993); (2) " Wild Plant Protection Regulations of the People‘s Republic of China", (September 30, 1996); (3) " Regulations on the Nature Protection Regions of the People's Republic of China", (October 9, 1994); (4) "Regulations of the People's Republic of China Governing the Administration of River", (June 10, 1988); (5) "Regulations on the Administration of Construction Project Environmental Protection", (November 29, 1998); (6) "Outline of National Ecological Environmental Protection", (April 10, 2001); (7) "‘Eleventh Five-Year Plan‘ of National Eco-protection", (UNCED 2006 [158]); (8) "Regulations on Pollution Control of Drinking Water Source Protection Area‖, (July 10, 1989); (9) "Public Participation and Interim Measures of Environmental Impact Assessment", (UNCED 2006 [28]); (9) "Notice for Strengthening Environmental Impact Assessment Work of Loan Construction Projects of International Financial Organization‖ (four ministries, EM [1993] No. 324). (10) "Notice for Strengthening Environmental Protection Work of Hydropower Construction ―, (UNCED [2005] No. 13); (11) "Notice for Printing and Issuing ‗National Ecological Environmental Protection Program‘ of State Environmental Protection Administration of the State Council‖, (December 21, 2000); (12) ―UNCED [2005] No. 24‖ Document ―Suggestion for Strengthening Ecological Environment Protection Supervision Work of Resource Development‖ of the State Environmental Protection Administration; (13) "Notice for Strengthening Ecological Environment Management of Natural Resources Development and Construction Project‖ (National Environmental Protection Agency, December 1994); (14) "Case for Issuing the Meeting Summary of Water Environment and Aquatic Ecosystem Protection Technology Seminar Minutes of Water Conservancy and Hydropower Construction Project‖ (Environmental Office letter [2006] No. 11); (15) "Notice for Strengthening Environmental Impact Assessment Management and Environmental Risk Prevention‖, (UNCED [2005] No. 152); (16) "Construction Project Environmental Protection Classification Management List" (2008); (17) "List for National Nature Reserve of China", (2004) (18) "List of National Key Protected Wild Animals" (National Bureau of Forestry Decree No. 7 revised, February 2003); (19) " List of National Key Protected Wild Plants (the First Amendment)‖ (August 4, 2001). 2. 1.4 Local Environmental Protection Regulations and List (1) "Geological Environmental Protection Regulations of Gansu Province" (Gansu Provincial People's Congress Standing Committee); (2) "Basic Farmland Protection Regulations of Gansu Province" (Gansu Provincial People's Congress, September 29, 1997); (3) "Provisions (Amendments) for Implementation of Forest Law of Gansu Province‖ (Gansu Provincial People's Congress, July 30, 1997) (4) "Measures (Amendments) for Implementation of Water Law of Gansu Province" (Gansu Provincial People's Congress, May 28, 1997); (5) "Measures (Amendments) for Implementation of Land Administration Law of Gansu Province" (Gansu Provincial People's Congress, September 29, 1997) (6) "Measures for Implementation of Fisheries Act of Gansu Province" (Gansu Provincial People's Congress, September 29, 1997); (7) "Measures for Implementation of Water and Soil Conservation Law of Gansu Province" (amended by Gansu Provincial People's Congress in May 28, 1997); (8) "Decision on Environmental Protection Problems of People's Government of Gansu Province‖ (February 20, 1997). 2.1.5 Socio-economic Development and Environmental Protection Plan (1) "Overall Plan for Urban Area of Cheng County" (2001-2020); (2) "Eleventh Five-Year" Development Plan of Longnan City; (3) "Eleventh Five-Year" Development Plan of Cheng County; (4) Overall Plan for Restoration and Reconstruction of Cheng County after 5.12 Wenchuan Earthquake; (5) "Eleventh Five-Year" Plan for Reasonable Use of Water Resources and Water Resources Guarantee of Cheng County; (6) Security Guarantee Plan of Drinking Water Source for Area of Cheng County; (7) Special Plan for Prevention of Geological Disasters of Cheng County (2008 ~ 2015); (8) Planning Report for Geological Disaster Prevention of Cheng County of Gansu Province; (9) Overall Plan of Mineral Resources of Cheng County. 2.1.6 Technical Guidelines and Specifications of Environmental Impact Assessment (1) "Technical Guidelines of Environmental Impact Assessment--Master" (HJ/T2.1-2.3-1993); (2) "Technical Guidelines of Environmental Impact Assessment--Surface Water" (HJ/T2.3-93); (3) "Technical Guidelines of Environmental Impact Assessment--Acoustic Environment" (HJ2.4-2008); (4) "Technical Guidelines of Environmental Impact Assessment--Atmospheric Environment" (HJ2.2-2008); (5) "Technical Guidelines of Environmental Impact Assessment--Non-pollution Ecological Impact" (HJ/T19-1997); (6) "Technical Guidelines of Environmental Impact Assessment--Hydropower Project" (HJ/T88-2003); (7) "Technical Specification for Water and Soil Conservation of Development and Construction project‖ (GB50433-2008); (8) "Technical Guidelines for Environmental Risk Assessment of Construction Project‖ (HJ/T169-2004); (9) "Technical Specification for Management and Protection Infrastructure Construction of Nature Reserves‖ (HJ/T129-2003); (10) "Technical Specification for Water and Soil Conservation of Development and Construction Projects" (GB50433-2008); (11) "Technical Specification for Eco-environment Evaluation" (HJ/T192-2006); (12) "Technical Specification for Comprehensive Treatment of Soil and Water Conservation" (GB/T-16453-2008); (13) "Quality Standard of Surface Water Environment" (GB3838-2002); (14) "Quality Standard of Ambient Air" (GB3095-1996); (15) "Quality Standard of Acoustic environmental" (GB3-96-2008); (16) "Health Standards of Drinking Water" (GB5749-2006); (17) "Noise Limit of Construction Site Boundary" (GB12523-90); (18) "Quality Standard of Soil Environmental" (GB15618-1995); (19) "Integrated Wastewater Discharge Standard" (GB8978-1996); (20) "Technical Specification for Cleaning Solid Waste on the Bottom of Three Gorges Reservoir" (HJ85-2005); (21) "Technical Guidelines for Construction Waste of earthquake Area" (trial). 2.1.7 Environmental Quality Standard (1) "Surface Water Environmental Quality Standard" (GB3838-2002); (2) "Ambient Air Quality Standard" (GB3095-1996); (3) "Acoustic Environmental Quality Standards" (GB3096-2008); (4) "Soil Environmental Quality Standard" (GB15618-1996). The environmental quality assessment standards and the assessment factors used in the environmental impact assessment of the project are shown in Table 2.1-1. The relevant environmental quality standards are shown in the Appendix 1-1 to the Appendix 1-5. 2.1.8 Control Standards of Pollutant Discharge (1) "Integrated Wastewater Discharge Standard" (GB8978-1996); (2) "Integrated Discharge Standard of Air Pollutant" (GB16297-1996), wherein the concentration limit value of unorganized discharged should be monitored. (3) "Noise Limit of Construction Site Boundary" (GB12523-90). The control standards of pollutant discharge and the assessment factors used in the environmental impact assessment of the project are shown in Table 2.1-2. The relevant control standards of pollutant discharge are shown in the Appendix 1-6 to the Appendix 1-8. 2.1.9 Health Standards The water of water source of Moba gorge water supply project should meet the requirements of ―Drinking Water Health Standards" (GB-5749-2006) after treating, wherein the quality standards and assessment factors are shown in Table 2.1-3. The relevant control standards of pollutant discharge are shown in the Appendix 1-9. Environmental Quality Standards and Assessment Factors for Environmental Impact Assessment of the Project Table 2.1-1 No. Standard Name Level Assessment Factors pH, COD, NH3-N, total nitrogen, zinc, selenium, mercury, lead, cyanide, oil, sulfide, dissolved oxygen, BOD5, total "Surface Water phosphorus, copper, fluoride, arsenic, cadmium, Environmental Quality Class 1 chromium (hexavalent), volatile phenols, anionic Standards" II surfactants, fecal coliform, potassium permanganate (GB3838-2002) index, water temperature, sulfate (by SO42-), chloride (by Cl-), nitrate (by N), iron, manganese "Ambient Air Quality Grad 2 Standard" PM10, NO2, CO, SO2 e two (GB3095-1996) "Acoustic Environment Class 3 Quality Standard" Continuous equivalent sound level A (GB3096-2008) II 4 "Soil Environmental Grad Copper, zinc, cadmium, hexavalent chromium, lead, total Quality Standards" e one chromium, sulfur, mercury and arsenic (GB15618-1995)

Control Standards of Pollutant Discharge and Assessment Factors for Environmental Impact Assessment of the Project Table 2.1-2 No. Standard Name Level Assessment Factors 1 "Surface Water Environment Quality Grade pH, suspended solids, BOD5, Standard" (GB3838-2002) one CODcr, ammonia "Integrated Discharge Standard of Air Pollutant‖ (GB16297-1996), wherein the 2 Particulate matter concentration limit value of unorganized discharged should be monitored. 3 "Noise Limit of Construction Site Boundary" continuous equivalent sound level A (GB12523-90)

Health Standards and Assessment Factors for Environmental Impact Assessment of the Project Table 2.1-3 Standard Name Indexes Assessment Factors "Drinking Water Health Microbial index Total coliforms, heat-resistant coliform Standards" Toxicological index Arsenic, cadmium, chromium (hexavalent), (GB5749-2006) lead, mercury Sensory properties and Chromaticity, turbidity, smell and taste, PH, general chemical index aluminum, zinc Radioactive index Total alpha radioactivity, total beta radioactivity Note: the radioactive indexes are guide values 2.1.10 Security Policies of the World Bank (1) "Operational Manual of the World Bank—Program of the World Bank" (bp4.01-1999); (2) "Operational Manual of the World Bank—Operational Policies Environmental Impact Assessment" (OP4.01); (3) "Operational Manual of the World Bank—Operational Policies Involuntary Resettlement" (OP4.12); (4) "Operational Manual of the World Bank—Operational Policies Natural Habitat" (OP4.04); (5) "Operational Manual of the World Bank—Operational Policies Dam Safety" (OP4.37). The proposed project will not involve indigenous people, will not involve forest sector activities or have significant impact on forested areas, will not lead to purchase or use of any pesticides, will not have impact on any known physical cultural resources. It also does not involve international waters or disputed areas. Therefore, other Bank safeguards policies are not triggered. 2.1.11 Relevant Documents of the Project (1) Feasibility study report of the project; (2) Preliminary design of the project; (3) Environmental impact assessment report of the project; (4) Approval for environmental impact assessment report of the project; (5) Soil and water conservation program report of the project; (6) Approval for soil and water conservation program report of the project; (7) Water resources assessment report of the project. 2.2 Environmental Management Organizations and Responsibilities The Central People's Government and the people's governments of the provinces (municipalities and autonomous regions, the city (state), county (district) of China set up environmental authorities according to the laws, and fulfill the corresponding environmental management responsibilities according to the laws. The environmental management institution related to the project mainly comprises the Environmental Protection Bureau of Gansu Province, the Department of Water Resources of Gansu Province, the Environmental Protection Bureau of Longnan City, the Department of Water Resources of Longnan City, the Environmental Protection Bureau of Cheng County, and the Department of Water Resources of Cheng County and etc. (1) Environmental Protection Bureau of Gansu Province The environmental protection bureau of Gansu Province is responsible for the administration of the province's environmental and administrative law enforcement work, its main responsibilities include: A. Implement national environmental policies, laws, regulations, administrative rules and standards; draft environmental regulations across the region, administrative regulations, and supervise the implementation; B. Implement environmental impact assessment of province's major economic and technological policies, development programs and major economic development plans according to the commission of the Provincial People's Government. C. Develop environmental protection plan, organize and compile environmental function zoning plan and area and watershed pollution prevention plan and ecological conservation plan, and supervise the implementation; D. Participate in the compilation of the policies development plans of environmental protection industry; E. Be responsible for supervision and management of environmental protection area and ecological environmental construction project supervision and management; and organize plans and supervise the implementation of pollution control plan period; F. Develop the province's total pollutant discharge control program, be responsible for discharge application registration and permit management, and organize discharge fee collection and supervision work; G. Be responsible for administrative audit of environmental supervision and environmental protection; H. Organize the activities of international environmental protection treaties in the province; I. Be responsible for the international economic and technological cooperation and exchange activities of environmental protection; J. Deal relevant foreign environmental protection affairs according to the commission of the provincial government and etc. The environmental protection bureau of Gansu Province has an environmental impact assessment division specializing in the administrative work of environmental impact assessment of each project. (2) Department of Water Resources of Gansu Province The department of water resources of Gansu Province is responsible for the administration of the province's water and administrative law enforcement work, and the main responsibilities thereof include: A. Develop the strategies of provincial irrigation, hydropower and aquatic development, the plans of middle- and long-term water development, and the plans of middle- and long-term water supply of the whole province; B. Be responsible for organizing and compiling integrated river basin plan and professional plan; C. Organize the compilation, submission and approval works of front plan of key water conservancy and hydropower project, be responsible for organizing the review of the project proposal, feasibility study report and preliminary design of the province's water projects; D. Be responsible for the supervision and inspection of the plan and capital implementation and completion conditions of the water conservancy construction project; E. Organize review, submission and approval works for the application plan of the costs of flood control and drought protection, the cost of water conservancy construction and the water charges and other capitals; F. Research the regulation advices provided in water prices, taxes, fees and credit and etc.; G. Be responsible for organizing and guiding water resources and water environment protection works, organize water quality and water quantity monitoring and analysis work and dynamic monitoring work of groundwater and etc., organize the division of water function zoning and discharge control to the drinking water area and etc., view the assimilative capacity and the setting of the discharge port of the water area, provide the advice of total discharge amount, and supervise the implementation; H. Be responsible for the safety supervision and management of reservoir, hydropower and dam; I. Develop the province's soil and water conservation policies and regulations, compile soil and water conservation plan and annual implementation plan, and organize the implementation; J. Organize and guide the province's comprehensive management work of water and soil conservation, be responsible for organizing the pre-project and construction management work for the soil and water conservation of a small watershed and the comprehensive treatment of a small area; K. Organize dynamic monitoring of the province's water loss and soil erosion, and regularly publish; L. Organize he compilation, approval, test and acceptance work of the soil and water conservation program of the project; M. Be responsible for the enforcement and supervision work of relevant regulations in the "Water and Soil Conservation Law". The department of water resources of Gansu Province has a water and soil conservation bureau which is responsible for the guidance and supervision work of the province's water and soil conservation. (3) Environmental Protection Bureau of Longnan City The environmental protection bureau of Longnan City is responsible for the administrative management and administrative law enforcement work of local environment protection, and the main responsibilities thereof include: A. Implement national environmental policies, laws, regulations, administrative rules and standards; B. Draft environmental regulations and administrative regulations in the region, and supervise implementation work; implement environmental impact assessment for the major economic and technological policies, development programs and major economic development plan in the region according to the commission of the regional administrative office; C. Develop environmental protection plan, organize the compilation of river basin pollution control plan and ecological conservation plan, and supervise the implementation work; D. Be responsible for supervising and managing the natural ecological environmental protection work in the jurisdiction and the environmental protection, supervision and management work of the construction project; E. Organize, develop and supervise the implementation of pollution control plan period; F. Develop a total discharge amount plan of the region, be responsible for the discharge application registration and license management, and organize and implement discharge fee collection and supervision work; G. Be responsible for environmental supervision and environmental protection administrative inspection, and be responsible for international economic and technological cooperation and exchange activities of environmental protection; H. Handel the relevant environmental protection foreign affairs according to the commission of the local administrative office and etc. The environmental protection bureau of Longnan City generally has an environmental assessment management division (or pollution control division, regulatory division, natural ecology division), which is specifically responsible for the administrative management work of the local environmental impact assessment, and the main responsibilities of the division comprises: be responsible for the implementation of the environment impact assessment in the region and the unified supervision and management of the ―Three Meantime" system; implement national and regional laws, regulations, rules and policies about the environmental impact assessment and the ―Three Meantime" system; develop and implement environmental impact assessment and ―Three Meantime" and other regional laws, regulations and policies; supervise the implementation work; guide and supervise the environmental impact assessment approval work of the regional construction project; be responsible for the administrative license of environmental impact assessment documents of the construction project in the range of the local environment protection bureau; and be responsible for the administrative licensing and guidance of trial production (run) of the construction project in the right of the region and the completion environmental protection acceptance of the construction project and etc. (4) Department of Water Resources of Longnan City The department of water resources of Longnan City is responsible for the city's water administration and administrative law enforcement work, and the main responsibilities thereof include: A. Be responsible for organizing and compiling integrated river basin plan and professional plan; B. Be responsible for the supervision and inspection of the plan and capital implementation and completion conditions of the water conservancy construction project; C. Organize review, submission and approval works for the application plan of the costs of flood control and drought protection, the cost of water conservancy construction and the water charges and other capitals; D. Be responsible for organizing and guiding water resources and water environment protection works, organize water quality and water quantity monitoring and analysis work and dynamic monitoring work of groundwater and etc., organize the division of water function zoning and discharge control to the drinking water area and etc., view the assimilative capacity and the setting of the discharge port of the water area, provide the advice of total discharge amount, and supervise the implementation; E. Be responsible for the safety supervision and management of reservoir, hydropower and dam of the whole city; F. Organize and implement soil and water conservation policies and regulations, compile soil and water conservation plan and annual implementation plan. The department of water resources of Longnan City has a water conservation division, which is mainly responsible for organizing the implementation of regional water and soil conservation project plan, reviewing and reporting the work, and inspecting and supervising the soil and water conservation work of the whole region. (5) Environmental Protection Bureau of Cheng County The environmental protection bureau of Cheng County of the project is responsible for the administrative management and administrative law enforcement work, and the main responsibilities thereof include: A. Implement national environmental policies, laws, regulations, administrative rules and standards; B. Develop the environmental protection plan of the county, and supervise the implementation work; C. Be responsible for supervising the natural ecological environment protection work in the jurisdiction and the environmental protection supervision and management of the construction project; D. Organize, develop and supervise the implementation of the development plan pollution sources within the specified period; E. Develop a total pollutant discharge amount control plan of the county, be responsible for discharge application registration and license management, and organize and implement discharge fee collection and supervision work; F. Be responsible for environmental supervision and environmental protection administrative inspection and etc. (6) Department of Water Resources of Cheng County The department of water resources of Cheng County of the project is responsible for water administrative management and administrative law enforcement of the county. The department of water resources of Cheng County has a soil and water conservation agency with the main responsibilities as follows: A. Develop the soil and water conservation plan and annual implementation plan of the county, and organize the implementation work; B. Organize the comprehensive management works of the county soil and water conservation; C. Organize the dynamic monitoring of water loss and soil erosion in the county, and regularly publish; D. Organize the compilation and implementation work of the soil and water conservation scheme of the construction project; E. Guide to the soil and water conservation work of the whole county; F. Monitor water loss and soil erosion, specifically soil erosion surveys, water loss and soil erosion monitoring report, water loss and soil erosion notice data providing, integrated control of water loss and soil erosion, benefits investigation and analysis, information system construction and management of soil and water conservation; G. Propagandize and implement personnel training of soil and water conservation. The administrative framework of environmental management of China (and the relevant part of the project) is shown in Figure 2.2-1.

Environmental Protection Bureau of Gansu Province Department of Water Resources of Gansu Province Environmental Protection Bureau of Longnan City Department of Water Resources of Longnan City People's Government of Cheng County Relevant Institutions of Cheng County Government Department of Water Resources of Longnan City Water Source Engineering Construction Management Department of Moba Gorge for City Water Supply of Cheng County Figure 2.2-1 administrative framework for environmental management of China

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

3. Project Description 3.1 Construction Objective of the Project The construction objectives of the project are as follows: construction of a reservoir with a total capacity of 1.79 million m3 and an utilizable capacity of 1.04 million m3 in Moba gorge, wherein the maximum daily water supply of the reservoir is 47,500 m3, the average annual water supply capacity is 1.651 million m3, and the average daily water supply is 45,200 m3. So that the urban water supply contradiction can be solved, the water quality can be changed, the cost of water supply can be reduced, the sustainable economic and social development of Cheng County can be achieved, and the physical health of urban residents can be improved. 3.2 Implementation Schedule of the Project The total construction period of the project is 27 months, of which the construction preparation period is 11 months, the main construction period is 11 months, and the completion period of the project is 5 months. The preparation period of 6 months of the project is not included in the total construction period (1) Construction preparation period The construction preparation period is 11 months from the January of the first year to the November, the construction content of the contractors after entering into the field comprises field engineering, onsite traffic, construction tunnel, aggregate processing system, concrete mixing system, temporary housing and construction factories, diversion tunnel and excavation of dam abutments on the two banks which are implemented for the main construction project. The control project is the diversion tunnel which has over-current conditions in the October of the first year. (2) Main construction period The main construction period is 11 months from the December of the first to the October of the next year, i.e. from closure to concrete pouring of the dam, instillation of metal structure, and impletion of curtain grouting. The construction of the dam project is the control project in the main construction period. (3) Completion period of the project The completion period of the project is 5 months from the November of the second year to the March of the third year, and the content of the period comprises diversion tunnel closure, reservoir storage, and completion and acceptance. 3.3 Project Overview The project is a reservoir type project, and the characteristics are shown in Table 3.3-1. Characteristics Table of the Project Table 3.3-1 No. Name Unit Quantity Remark I Hydrology 1 Basin area Whole basin km2 401 Over the dam site km2 248.2 2 Age limit of used hydrological system Year 51 Actual measurement, 1959 – 2009 3 Average annual runoff of many years Ten 4352 thousand m3 4 Representative flow Average annual flow of many years m3/s 1.38 Normal use (design) of flood standard and m3/s 954 P=2% flow Abnormal use (check) of flood standards m3/s 1550 P=0.2% and flow Diversion standards and flow of diversion m3/s 544 P=10%, yearly tunnel m3/s 29.4 P=20%, October to May 5 Sediment Average amount of sediment suspended Ten 14.72 sediment of many years thousand t Average sediment concentration of many kg/m3 3.509 years Annual sediment amount of annual Ten 2.21 average bed load of many years thousand t II Project overview 1 Reservoir Checked flood level m 1098.52 Designed flood level m 1096.38 Normal water level m 1092.70 Dead water level m 1068.0 Total storage capacity Ten 1790 thousand m3 Utilizable capacity Ten 1040 thousand m3 Dead storage Ten 380 thousand m3 The maximum discharge capacity while m3/s 1410 checking flood level The maximum discharge capacity while m3/s 865 designing flood level 2 Urban water supply Average annual water supply Ten 1651 thousand m3 Guaranteed rate of water supply % 96.3 3 Water pipeline Length of the pipeline km 5.15 Number of the pipeline Pcs 0.65 Design water supply flow m3/s 0.65 Leakage loss rate % 10 III Flood damage and permanent area of the project 1 Backwater length km 3.5 2 Submerged land hm2 9.86 3 Flooded forest hm2 51.13 4 Relocation of population People 14 5 Residents of flooded area Family 3 6 Important special facilities in flood affected 10kv line km 1.2 7 Project area Mu 145.17 Arable land thereof Mu 36.17 IV Main building 1 Retaining building Type Roller compacted concrete gravity dam Ground characteristics Limestone Basic seismic intensity Degree 8 Crest height m 1099.8 Maximum dam height m 91.4 Crest length m 136.5 Crest width m 10 2 Discharge structure 2.1 Crest overflowiring Ground characteristics Limestone Crest height m 1092.7 Net width of overflow section m 39 Energy dissipation form Energy dissipation by trajectory jet Designed flow discharge flow m3/s 462 Checked flow discharge flow m3/s 1003 2.2 Flood discharge sand flushing hole Orifice size m 3.5x4.8 Hole length m 46.9 Maximum discharge capacity m3/s 107 3 Road over the dam Length m 2810 Road width m 7 V Construction Open excavation of earthwork Ten 43.16 thousand m3 Earthwork backfilling Ten 5.54 thousand m3 Rock hole dug Ten 2.31 thousand m3 Concrete Ten 25.28 thousand m3 Installation of metal structure t 186.5 Curtain grouting m 8580 Consolidation grouting m 3100 2 Number of major construction material Cement Ten 4.79 thousand t Fly ash Ten 2.66 thousand t Steel bar and steel material Ten 1.0 thousand t 3 Labor required Labor of construction period Day 100 4 Construction labor and resource Power supply km 12 35kv, Cheng County 5 External transportation Distance km 5 Reconstruction of existing rural road 6 Construction diversion Mode Cofferdam retaining water Type Tunnel division Dimension of diversion tunnel (length x mxm 6x7.5 Type of gate hole width) 7 Construction period Construction preparation period Month 11 Main construction period Month 11 Completion period Month 5 Total period Month 27 VI Economic Indicator 1 Static total investment Ten 22656.3 thousand Yuan Construction project Ten 17032.0 thousand 0 Yuan Mechanical and electrical equipment and Ten 920.22 installation thousand Yuan Metal structure equipment and installation Ten 1351.19 project thousand Yuan Temporary construction project Ten 3675.70 thousand Yuan Basic reserve fund Ten 1550.76 thousand Yuan Financing interest construction period Ten 458.50 thousand Yuan Compensation cost of reservoir Ten 3257.40 inundation treatment thousand Yuan Acquisition cost of construction and Ten 1355.95 construction site thousand Yuan Environmental protect engineering cost Ten 408.6 thousand Yuan Soil and water conservation cost Ten 1118.67 thousand Yuan 2 Comprehensive Economic Indicator Net economic present value Ten 7493 thousand Yuan Internal economic rate of return % 10.39 Ratio of economic benefit 1.22

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

4. Environmental Impact of the Project and Mitigation Measures Summary 4.1 Environmental Impact Assessment In the implementation process of environmental impact assessment, the layout of the project, the main environmental protection objectives in surrounding assessment range and the sensitive points are identified (see the Figure 4.1-1), the possible adverse environmental impacts caused by the project are as follows: 4.1.1 Impact on the hydrology and sediment 4.1.1.1 Hydrological changes 4.1.1.1.1 Impact on regional water resource In the Cheng County Moba gorge water supply project, water is stored in a reservoir, wherein the normal water level of the reservoir is 1092.70 m, the total capacity is1.79 million m3, the backwater length is about 3.5 km, and the designed reference water is 1.651 million m3/a. In running period, the downstream of the dam comprises a diversion effect river section of 4 km. 4.1.1.1.2 Ecological water of river and mitigation measures When the reservoir of Moba gorge is completed, the inflow of Nan River over the dam (the basin area is 248.2 km2) is retained, and the mean runoff of many years is 1.22 million m3 when the reliability is 95%. The ecological water use of the river is calculated according to the Tennant method recommended by the ―Environmental Impact Assessment Specification of River Basin Planning‖, in which the ecological water use of Nan River is the minimum, namely about 10% of the annual average flow as the minimum use of ecological water, and according to the calculation of the method, the minimum ecological water use of Nan River is 0.138 m3/s. Thus, the ecological water of the diversion effect river section is ensured, and the dam should be provided with permanent plug holes while construction. The plug hole should lower than the water inlet while higher than the flood discharge sand flushing port, specifically the elevation is 1024 m-1065 m, the discharge amount is 0.138 m3/s, thereby ensuring the minimum ecological water use of the diversion effect river section. 4.1.1.1.3 Impact on the diversion effect river section Due to the abouchement of Nan River from the Fengquan River downstream the dam of 4 km, and the normally annual runoff of the Fengquan River is 2.06 million m3, it can be determined that the diversion effect river section is 4 km. The section comprises eight villages, i.e. Zhuanwancun, Ganlushi, Majiaya, Jianjiagou, Xiaozhuang, Zhangjiashan, Luangoumen and Niujiaya. Zhuanwancun comprises about 900 people or more, Ganlushi comprises about 1000 people or more, Majiaya comprises about 300 people or more, Jianjiagou comprises about 350 people or more, Xiaozhuang comprises about 250 people or more, Zhangjiashan comprises about 600 people or more, Luangoumen comprises about 100 people or more, and Niujiaya comprises about 120 people or more. The water of the eight villages is mainly supplied from the local mountain spring and groundwater which are not the water in the river section, so that the impact of the project to the water source is controllable. The ecological water use can be ensured in case of the discharge flow ensured is 0.138 m3/s.

Erliang River

Plantatio

n Reservoir region Forest

Majiaya Along the river

Jianjiago

Xiaozhuangcun u

Zhuanwancun Zhangjiasha

n

Luangoumen Niujiaya Ganlushi

Legend

Sensitive point

Dam Scale

Figure 4.1-1 Location Diagram of Sensitive Points of the Project 4.1.1.2 Impact on Sediment Load and Mitigation Measures The factor impacts the bedload sediment is more. According to the current technology and the test means and equipment thereof, the accuracy of the test data is not high, the relation of push and suspension ratio of the sediment to the various hydrological factors is bad. In the project, the bedload sediment of the region is designed to the 15% of the suspended load sediment by combining with the general relation of the mountain stream push and suspension ratio of 10 to 20%. The annul bedload sediment of the hydrological station of Cheng County is 133,600 t, the average total sediment load of many years is 1.024 million t, and the average sediment load modulus of many years is 682 t/km2. According to the calculation, the average suspended load sediment of many years of Moba gorge dam is about 147,200 t, the annual bedload sediment is about 22,100 t, and the average total sediment load of many years is 169,000 t. After completion of the project, the speed of the water floor is reduced, which is conducive to sediment deposition, and thus sediment deposition speed in the reservoir can be accelerated. In order to ensure the capacity, the project should discharge sediment to the downstream irregularly. In the sediment discharge period, the flow of the diversion effect river section will be increased, the sediment concentration will be increased, but the impact to the downstream river is in the acceptable range. 4.1.2 Impact on Local Climate After running of the reservoir, the original undulating land of the submerged area is replaced by smooth water surface, so that the energy exchange method and intensity between the underlying surface and the air are changed. As the heat capacity of water is more than that of the land soil, the temperatures, before and after constructing the reservoir, of the same point in the submerged are different, the horizontal exchange is caused due to the temperature difference of land and water, and the temperature of the land around the reservoir is also changed. Due to the large-area water storage formed by the construction of the project, the evaporation capacity is increased and the rainfall is increased; due to the effect of lower temperature of the reservoir, the distribution of rainfall is changed, the rainfall of the protected areas over the reservoir and the coastal flow will be reduced, and the rainfall of the windward slope along the air flow direction will be increased; the underlying surface of the reservoir region is changed from a land surface into a water surface, and the energy exchange method and intensity thereof to the air are changed, so that the temperature is changed, the annual mean temperature is increased slightly, but the regional impact is in the acceptable range. 4.1.3 Impact on Water Environment and Mitigation Measures 4.1.3.1 Impact of Construction Period on Water Environment and Mitigation Measures 4.1.3.1.1 Foundation Pit Wastewater Treatment Measures The foundation pit drainage of the project is mainly composed of precipitation, seepage, concrete pouring and maintenance water, and foundation pit excavation drainage; the main pollutant is composed of SS, pH, and oil. According to the foundation pit wastewater treatment experience of some large-scale hydropower projects, the drainage of the foundation pit will not be provided with other treatment facilities, excepting the operation of adding flocculants into the foundation pit, the drainage will be extracted after placing for 2 h; part of the drainage is used for watering to prevent dust, the rest drainage is discharged to the nearby surrounding drains, and the sludge will be regularly removed by human. As the treatment effect of the mixture composed of green-vitriol and polyacrylamide to the wastewater with high SS, alkalinity and oil is good, it is recommended to use the flocculants of this kind. 4.1.3.1.2 Aggregate Washing Wastewater Treatment Measures A primary sedimentation tank and a coagulation sedimentation tank are arranged on the Xiaozhuang-Gumugou construction area of right bank, both the two tanks use concrete structure, and the sizes of the tanks are designed according to the largest wastewater discharge of 142 m3/h, wherein the residence time of the primary sedimentation tank is 1 h, the residence time of the coagulation sedimentation tank is 1.5 h; both the two tanks are flow settling tank, the flocculant thereof is polymeric aluminum, and the specific process is shown in the figure 4.1-2. The effective volume of the primary sedimentation tank is 142 m3, a tank is provided with a cell, the size of each cell is 18.9 m x 5.0 m x 2.3 m (length x width x height); the effective volume of the coagulation sedimentation tank is 213 m3, tank is provided with a cell, the size of each cell is 22.5 m x 6.3 m x 2.5 m (length x width x height). The supernatant treated is returned to production process and applied to site watering. Washing wastewater, primary sedimentation tank, adding a flocculant, coagulation sedimentation tank, supernatant, reusing or discharging, sludge transported outside, residues place Figure 4.1-2 Aggregate Washing Wastewater Treatment Process Flow 4.1.3.1.3 Alkaline Wastewater Treatment Measures The Gumugou construction area is equipped with a concrete mixing system, the washing water of the concrete mixing system is calculated as 6 m3 per shift and two shifts per day, the sand easy to be deposited can be deposited and removed by means of an intermittent natural sedimentation method, an appropriate amount of acid is added into the sedimentation tank to regulate the pH value to neutral, then the sand is placed and deposited, the clear solution can be returned to the mixing system for washing and further can be watering the construction road, and the sediment is regularly removed by human. The place close to the concrete mixing system is equipped with two sedimentation tanks, wherein the tank body is shown in a concrete structure, the inner wall is corrosion resistant, and the sizes of the tanks are designed according to the effective volume of 6.0 m3, the interior dimensions are 3 m (length) x 2 m (width) x 1.2 m (height), and the sedimentation time thereof is more than 7 h. 4.1.3.1.4 Oily Wastewater Treatment Measures According to the discharge and water quality of construction machinery and vehicle washing wastewater and the like, the oily wastewater is treated by means of a small-scale simple oil separation tank. The treatment method is featured with simple structure, low cost, convenient management, regular cleaning, and recyclable oil slick. The small-scale oil separation tank comprises two cells, the horizontal velocity is 0.005 m/s, the residence time is 10 min, the discharge cycle is 7 d, and the specific design is shown in Figure 4.1-3. The project is totally provided with 5 machinery parking areas, 95 sets of fuel construction machinery and vehicles to be regularly cleaned, wherein the water of maintaining and washing of each machine is 0.6 m3 / time and one time per day. In order to facilitate the collection, the machinery parking area is provided with a special washing site surrounded by catch drains so as to collect wastewater, and then the wastewater is entered into the oil separation tank and subsequently reused after reaching to the standard. At the same time, the oil leakage inspection of the machinery parking area is strengthened, and the treatment measures will be taken in time in case of oil leakage. See the Figure 4.1-1 for the size of the special oil separation tank.

Degreaser Activated carbon Water inlet

Water outlet

Figure 4.1-3 Design Diagram of Small Oil Separation Tank

List of Oil Separation Tank Size Table 4.1-1 Oily wastewater amount Size of oil Amount of oil separation tank Construction site separation (length x width x height) m tank Amount of Wastewater

construction quantity (m3/d)

machinery Majiaya Qiaotou machinery 15 9 3x0.38x1.3 1 parking area of left bank Bashang achinery parking 15 9 3x0.38x1.3 1 area of left bank Gumugou machinery parking 25 15 3x0.64x1.3 1 area of right bank Machinery parking area of 20 12 3x0.51x1.3 1 sand and gravel mining area Bashang achinery parking 16 9.6 3x0.41x1.3 1 area of right bank (5) Domestic wastewater treatment measures The construction site is provided with temporary pail latrine to collect domestic water, and the domestic water is regularly treated by the local villagers delegated. 4.1.3.2 Impact of Operation Period on Water Environment and Mitigation Measures 4.1.3.2.1 Impact on Water Temperature When the project is completed, the temperature of the water is very different to that of the natural river before constructing. The change of the water temperature will influence the vertical structure of the reservoir, so as to form water temperature stratification, according to the determination based on runoff-storage capacity ratio method, alpha=2.52, the reservoir is a stable layered reservoir; beta=0.2, and the impact of flood to the water temperature structure is basically free. 4.1.3.2.2 Impact on Water Quality and Mitigation Measures According to the survey, the upstream of the reservoir has a lead-zinc concentrator, a gold concentrator and a gold ore mine. The two concentrators has been closed by the Environmental Protection Bureau of Cheng County, and the gold ore mine will be closed down soon. In addition, the ambitus of the reservoir does not have pollution and industrial pollution enterprises, when the concentrators and the gold ore mine are closed, the impact on the water quality of the reservoir is mainly caused by regional soil and water loss and the organic matters of part soil are entered into the reservoir together with the sediment, so that the sediment in the reservoir is increased, and the contents of nitrogen and phosphorus are increased. However, the generation is relatively small, and the water quality of the reservoir will not be impacted basically; in order to ensure the water quality of the reservoir, the following measures should be taken when the project is completed, so as to prevent the impact of unexpected incidents on the water quality: (1) Strengthen water quality monitoring the reservoir area, complete the cleaning work well, and regularly fish the floating material on the water surface of the reservoir. (2) Draw a certain range with clear boundary as the water source protection area on the upper and lower basins of the water intake port and the deep land-based area, protect strictly, take practical and effective measures, and prevent water pollution. (3) In order to ensure standard discharge of the water source, the ―Moba gorge water source protection regulations‖ must be developed according to the relevant laws and regulations of the Country and Longnan City, so as to protect the water source effectively. (4) Strengthen natural vegetation protection and ecological construction, prohibit deforestation, protect natural vegetation and water source conservation, and reduce water loss and soil erosion. 4.1.3.2.3 Water Source Protection Measures (1) When the ―Moba gorge water supply project is completed, the water source engineering construction management department of Moba gorge for city water supply of Cheng County should divide a drinking water source protection area according to the requirements of ―Pollution Control Management Regulations of Drinking Water Source Protection Area‖ and manage by complying with the regulations completely. ① First-grade Protection Area Prohibit new construction and extension of the construction projects which are not related to the water supply facilities and water sources protection, prohibit the discharge to the basin, and remove the discharge port; Prohibit the wharf which is not related to the water supply requirements, and prohibit vessel callings; Prohibit the industrial waste, municipal waste, manure and other wastes from stacking and storing; Prohibit the construction of oil depot; Prohibit from engaging in cultivation and livestock restocking, and strictly control cage culture activities; Prohibit the tourist activities and other activities which may pollute the water source. ② Second-grade Protection Area Prohibit new construction and extension of the construction projects for discharging pollutant to the water. The discharge of pollutant in the reconstruction project must be reduced, the wastewater discharge of the original discharge port must be reduced, and the water quality in the protection area must be in line with the water quality standards provided; Prohibit the construction of the wharf for loading/unloading garbage, manure, oil and toxic substances. ③ Quasi-protection Area Wastewater directly or indirectly discharged to the basin must be in line with the national and regional wastewater discharge standards. When the total discharge amount of the protection area cannot be in line with the standards provided, the discharge load must be reduced. (2) The water source engineering construction management department of Moba gorge for city water supply of Cheng County should compile an ―Environment Protection Plan of Drinking Water Source of Cheng County‖ according to the ―Compilation Technical Specifications of the ‘Environment Protection Plan of National Drinking Water Source‘‖ (May 2006). (3) Strengthen the construction of water conservation area. In the protection area of Moba gorge water source, the vegetation construction should be strengthened, the forestation should be strengthened, the damage to the vegetation cover should be reduced, the forest coverage should be improved, and the ecological water source should be protected. (4) Strengthen the use management of farmland pesticide and fertilizer in the protection area. As the upstream of the Moba gorge water source has part of plantation, the large-scale use of pesticide and fertilizer will be entered into the surface water bodies together with the rainwater, so that the ammonia nitrogen, nitrate nitrogen and nitrite nitrogen in the water quality of water source are obviously exceeded the standards, which not only affect the water quality of the reservoir, but also affect people's health directly. Thus, the use of pesticide and fertilizer must be strengthened, and the agricultural non-point pollution should be reduced. (5) Order to close the two concentrators upstream the reservoir, and close the gold ore mine, treat the remaining issues, and develop perfect emergency plan. (6) Strengthen water quality monitoring of water source 4.1.3.2.4 Impact for Domestic Wastewater of Management Station and Mitigation Measures The wastewater discharged in the operation period mainly comprises the domestic wastewater of managerial personnel of the management station, wherein the fixed staff of the management station is 35 people, the maximum water consumption of the production and living area is about 3.5 m3/d on the basis of 100L/person/d. Accordingly, the domestic wastewater discharge is about 3.3 m3/d. In order to ensure that the pollution of the water source caused by the domestic wastewater generated by the managerial personnel of the management station is prevented from is prevented, the WSZ buried wastewater treatment equipment is recommended to treat the domestic wastewater generated by the managerial personnel, wherein the specific process is shown in Figure 4.1-4. After treating by the equipment, the discharge concentrations of CODcr, BOD5 and SS are 60 mg/L, 30 mg/L and 60 mg/L, respectively; so that the first-grade standard in the ―Integrated Wastewater Discharge Standard" (GB8978-1996) can be met, the domestic wastewater treated is used as the surrounding green water, and the sludge settled is used as agricultural fertilizer. See the Table 4.1-2 for the effects of WSZ buried wastewater treatment equipment. Wastewater, primary sedimentation tank, regulation tank, A-level biological tank, pump, fan, 0-level biological tank, secondary sedimentation tank, disinfection tank, discharge, sludge collection well, pump, sludge tank, nightcart Sinotrans or mud cake Sinotrans after dehydration Figure 4.1-4 Integrated Domestic Wastewater Treatment Flow Chart

List for Treatment Effect of Buried Wastewater Treatment Equipment Table 4.1-2 Project CODcr BOD5 SS Discharge Discharge Discharge Discharge Discharge Discharge concentration (t/a) concentration (t/a) concentration (t/a) (mg/L) (mg/L) (mg/L) Before 300 0.20 180 0.18 200 0.20 After 60 0.04 30 0.03 60 0.06 Treatment efficiency 80% 70% 83.3% 4.1.4 Impact on Atmospheric Environment and Mitigation Measures In the project, the atmospheric pollutant is mainly generated in construction period, the atmospheric pollution of operation period is basically free, and the impact on atmospheric environment and the mitigation measures are target to the construction period. 4.1.4.1 Construction Dust Impacts and Mitigation Measures Construction dust mainly comprises transport vehicles dust, natural wind dust, ground building materials stacking yard dust and construction process dust. In order to reduce the impact of dust on the environment and the construction workers, the following mitigation measures should be taken: (1) In the construction process, the construction site will be provided with blocks and envelope to reduce dust diffusion, the block and envelope play a significant role in reducing the pollution of the dust to the environment; when the wind speed is 2.5 m/s, the impact distance can be shortened by 40%. The surrounding space of the construction site is continuously equipped with the blocks of less than 2.5 m, and the blocks are firm and beautiful; (2) Assign the staff to water the construction site regularly to reduce dust emission on the construction site, wherein the time of watering is determined according to the weather, wherein the general frequency is 1 to 2 times per day, and the time can be appropriately increased in case of high wind or dry weather. The impact of watering operation on the construction site is large to the dust; after watering the dust can be reduced by 28 to 75%, and therefore the impact of the dust on the environment is reduced greatly; (3) Set a tarpaulin on the vehicle for transporting the building materials and the construction waste to reduce scatter. At the same time, the tires of the vehicle should be cleaned with water while accessing the site and loading and unloading on the site, and the traffic route of the vehicle should be prevented from the residential areas as much as possible. (4) In the application of commercial concrete, the construction work of windy weather should be prevented as much as possible. At present, it is determined that the earthwork and stonework construction is prohibited in wind of Category 4, the project can learn from the provision; (5) Assign a specially-assigned person who is specifically in charge of the treatment, cleaning and stacking of spoil, construction waste and building material on the construction site, wherein the stacking yard should be provided with a cloth cover or watered to prevent secondary dust; (6) The construction waste and spoil should be treated and cleaned in time, so as to reduce the space, prevent dust pollution, and improve the environment of construction site; (7) In the mechanical excavation process in the tunnel, the intermittent operation method is used, the ventilation should be in time, and the construction worker should wear a mask, if necessary. 4.1.4.2 Exhaust Gas Environmental Impact and Mitigation Measures In the construction process, the fuel exhaust gas generated by the construction machinery and the transport vehicles mainly comprises CO, NOx and THC. The total amount of the fuel consumed by the project is 1663.4 t, and the discharge of each pollutant is as follows: CO is 148.1 t, NOx is 95.78 t and THC is 27.5 t; the tail gas discharge port of the fuel machine is low, and the discharge belongs to low-point source disorder discharge, and the discharge mainly in the range of 100 m in relation to the discharge source. In the project, the environmental sensitive points in the range of 100 m in relation to the construction area are free, and the discharge mainly impacts the construction area. The impact of the transport vehicles on the environment along the route in the transportation process is relatively small. In order to mitigate the impact of exhaust gas on the environment, the management of large-scale fuel construction machinery and vehicles should be strengthened, the regular inspection and maintenance system should be implemented, and all the tail gas discharge of fuel machinery and vehicles of the contractor should implemented according to the ―Automobile Air Pollutants Discharge Standards‖, and the smoke and dust removal equipment must be provided in case of the purpose of standard discharge cannot be achieved. The construction machinery uses unleaded gasoline and other high-quality fuels. Strictly implement ―In-use Vehicle Rejection Standards‖, implement a mandatory retirement and update system, and update the old vehicle with more engine fuel consumption, low efficiency and seriously excessive exhaust gas discharge. 4.1.5 Impact on Acoustic Environment and Mitigation Measures The noise impact of the project is mainly presented in the construction period, the noise impact of the operation period on the environment is relatively small, so that the impact on acoustic environment and mitigation measures are mainly targeted to the construction period. The construction machinery used in the project mainly comprises rock drilling machines, bulldozers, excavators, mixers and drills and etc., and the noise source will have some impact on the surrounding acoustic environment without taking measures. The acoustic pressure level is shown in Table 4.1-3, and the prediction results are shown in Table 4.1-4. Acoustic Level Test Value and Range of Construction Mechanical Equipment Table 4.1-3 Unit: dB(A) No. Construction equipment Distance of the test point to the Maximum acoustic construction equipment/m level/dB 1 Rock drilling machine 5 100 2 Bulldozer 5 86 3 Excavator 5 84 4 Mixer 5 87 5 Drill 5 95

Prediction Value of Environmental Noise Impact of Construction Machinery Table 4.1-4 Acoustic level Distance (m) Standard value Standard dB(A) dB (A) distance Construction (m) machinery 10 20 40 60 80 100 150 Daytim Nightti Daytim Nightti e me e me Rock drilling 94.0 88.0 82 76.4 74.0 72.0 70.5 75 55 75 1250 machine Bulldozer 81.0 75.0 69.0 65.4 63.0 61.0 57.5 75 55 35 170 Excavator 80.0 74.0 68.0 64.4 62.0 60.0 56.5 75 55 18 177 Mixer 78.0 72.0 66.0 62.4 60.0 58.0 54.5 70 55 24 140 Drill 89.0 83.0 77.0 71.4 69.0 67.0 63.5 75 55 50 200 With analysis, the following conclusions can be obtained: (1) In case of the use of single construction machinery, the ―Noise Limit of Construction Site Boundary‖ GB12523-90 can be achieve in the place apart from the construction site with 75 m at daytime, and the standard limit can be achieve in the place apart from the construction site with 1250 m at nighttime. But in the actual construction process, variety of machines are always used simultaneously, the noise impact will be greater than the scope; (2) In the range with the distance about 5-35 m to the construction site boundary, the impact of construction noise on the surrounding acoustic environment is relatively large; (3) With the completion of the project, the construction noise will no longer exist, so that the adverse impact of construction noise on the environment is temporary and short-term. In order to mitigate the impact of noise in the construction period, the following mitigation measures should be taken: (1) Control from the acoustic source: construction units should require the main mechanical equipment used by the construction unit is low-noise mechanical equipment while signing the contract with the construction unit, meanwhile, the construction unit should appoint a specially-assigned person to regularly maintain and service the equipment in the construction process, and the construction unit should be responsible for training the on-site staff so as to use the various machines by complying with the operation specifications strictly. Reasonably arrange the service time of hammers, air hammers and rock drill machine and other high-noise construction machinery, reasonably arrange blasting time, and reduce the noise generated by the equipment in the abnormal operation process. As the distance of Majiaya construction site to the Majiaya is 400 mm, the distance of Xiaozhuang construction site to the Xiaozhuang is 650 m, the nighttime construction will have a greater impact on them, so that the high-noise construction machinery (such as rock drilling machine and drill) should be prohibited from night construction. (2) In the structure stage of construction, the exterior of the building should be equipped with a block, so as to reduce the impact of equipment noise on the surrounding environment. (3) Personal protective measures of construction workers: strengthen labor protection, and improve workers' working conditions. For the construction workers in the high-noise environment of the first production line, the consecutive working hours per day should not be more than 6 h; the construction workers with large noise impact should be provided with noise protective equipment; and the workers on the construction site should wear anti-noise cotton to reduce the impact of noise. 4.1.6 Impact of Solid Waste on Environment and Mitigation Measures Thereof 4.1.6.1 Impact of Solid Waste of Construction Period on Environment and Mitigation Measures Thereof 4.1.6.1.1 Impact of Construction Waste and Vegetation Cleaning on Environment and Mitigation Measures Reference to the ―Technical Specification for Cleaning Solid Waste on the Bottom of Three Gorges Reservoir" and the requirement of water source protection, the vegetation and the construction waste of submerged area in the project should be cleaned. According to the estimation, the vegetation to be cleaned is about 50,000 m3, and the construction waste cleaned is about 14.13 t. The part of the vegetation cleaned further can be restored, and the optional stacking of the vegetation not only has impact on the environment, but also wastes resources. The vegetation which can be restored is recommended to be given the farmers of the surrounding villages, and the vegetation which cannot be restored is transported to the landfill site of Cheng County. The construction waste cleaned is transported to the residues place of the project. 4.1.6.1.2 Impact of Household Wastes of Construction Workers on Environment and Mitigation Measures As the huge quantities of the project, the construction workers are more, the random storage of a lot of household wastes not only pollute the environment, but also easy to breed mosquitoes, which is harmful to human health. In order to mitigate the environmental impact of household wastes, each construction site should be equipped with two garbage cans, and the total number of the garbage can in the construction site is 28. The household wastes are uniformly stored in a sealed garbage can, regularly collected by a special car and subsequently transported to the landfill site of Cheng County to landfill. 4.1.6.2 Impact of Solid Waste of Operation Period on Environment and Mitigation Measures When the project is completed, the total establishment determined of the operation management personnel is 35 people. The household waste generated by each person per day is 0.8 kg, and the household waste generated by the 35 people per year is 10.22 t. In order to prevent the impact of household waste on the surrounding environment, the management station is provided with 2 garbage cans to collect that, and the household waste will be regularly transported to the landfill site of Cheng County to implement centralized treatment. 4.1.7 Impact of Environmental Geology and Mitigation Measures The dam area of Moba gorge water source project and the neighborhoods belong to east-west Qinling tectonic system and the composite part on the east of the Wudu epsilon structural system, the project is located in the northwest edge of the emblem basin. Both the north and south sides are composed of a series of curved folds and fractures of SWW ~ NEE direction. In the early Quaternary Pleistocene, the area also belongs to the general uplift phase of Qinghai-Tibet Plateau due to the impact of movement of the Himalaya, and accretion of 10 to 50 m thick of the Quaternary system is accumulated in the area. In the project area, the movement of the new construction is relatively active, and the movement mainly comprises differential uplift and subsidence, the movement is more prominent in the Quaternary; the valley terrace is developed, and the more active fractures are developed in the periphery of the project area. In the range of the project area, the active fracture is free, and the construction site is in a relatively stable tectonic area. The acceleration of peak ground motion of the construction site is 0.20 g, the basic earthquake intensity is VIII degree, and the ground motion response spectrum characteristic period is 0.40s. The distance of the latest active fracture to the dam is 6 km. In order to mitigate the impact of environmental geological disasters on the project, the purpose of protecting geological environment and preventing and reducing the loss of geological disasters should be achieved according to the principle of "prevention first, combining prevention with control", and the following recommendations of control measures are provided for the various types of geological disasters: (1) For the collapse of fat rock and soil and caving and other geological disasters which may be presented while excavating the abutment construction, temporary support or temporary bracing and other measures can be taken to ensure the security and stability of abutment construction, and the surface and groundwater discharge work should be simultaneously completed well. (2) For the collapse and caving-in and other geological disasters of slope break and weathered sediment layer which may be presented while excavating the inlet of the water tunnel, the outlet slope and the construction, temporary support or temporary bracing and other measures can be taken while combining with the permanent slope protection measures of the hole face slope, so as to ensure the security and stability of construction and operation, and the discharge and guide work of surface and groundwater should be simultaneously completed well. (3) When the tunnel through the broken belt or soft interlayer, the stability of surrounding rock is poor, the collapse, roof collapse and other geological disasters may be caused, the support should be provided in time while excavating, the support should be provided while excavating, and the waterproofing work of the tunnel should be made well. (4) For the lateral sliding of foundation pit geotechnical slope and collapse and other geological disasters which may be presented in the excavation process of dam foundation, temporary support or temporary bracing and other measures can be taken, the high slope formed after excavation should be shown in the form of cascade slope, so as to ensure the safety of the foundation pit slope in the construction period. (5) The earthwork and stonework construction should be subjected to the operating for filling with the excavation as far as possible, so that the unstable slope caused by stacking the residues can be reduced, the residues must be stacked should be provided with corresponding protective measures. 4.1.8 Impact on Ecological Environment and Mitigation Measures 4.1.8.1 Impact on Terrestrial Animals and Mitigation Measures 4.1.8.1.1 Impact of Construction Period on Terrestrial Animals and Mitigation Measures (1) Impact on mammals The interference of construction activities of the project to the mammals mainly in the hub, plant and tunnel construction areas, the impact on the mammals mainly comprises the drive of construction activities and construction noise to the mammals, namely the animals fled to other places after frightening, and the food debris and wastes left behind by human activity will attract rodents (mice) gather in the construction area. As mammals will avoid the harm caused by the project construction by means of migration, the total direct impact of the project construction to the mammals is small. With the completion of the construction activities and the restoration of the construction site and the nearby natural ecological environment, the animals will return to the original project area, so that the long-term impact of the project on the mammals is small. (2) Impact on birds The construction activities will cause disturbance and destruction in the habitat of the bird, so that the habitat of the bird will be directly or indirectly destroyed, the nests will be damaged, and the bird habitat in the shrub niche will be disturbed. Due to theses impacts, most of the birds will migrate to other places far from the construction site, and a small part of the bird with shrubs and forest-dwelling habitat will disappear from the project area due to the loss of the habitat; a part of the bird populations will be reduced as the nest destruction, particularly the construction period is in the bird breeding season (summer). The overall result is that the species and number of the bird in the project range are reduced. Since most birds will fly and make a short-distance migration to avoid the harm caused by the construction project, the impact of the project construction on the bird is small. The main indirection impact is the reduction of the foods such as rodents of the birds in the project area caused by the construction interference, thereby forcing the birds to prey in a greater range. With the completion of the construction activities and the restoration of the line construction site and the nearby natural ecological environment, the birds in the project area will return to the project area, so that the long-term of the project on the birds is small. In order to ease the impact of construction period on the terrestrial organisms, the education of ecological protection to the construction workers should be strengthened by means of notice, dissemination of brochures and other methods in the construction period of the project, the construction workers are strictly prevented from cutting the trees, outside the construction site, without permission by means of institutionalization, and the construction workers are prohibited from preying frogs, birds and snakes and other wild animals. The Majiaya Qiaotou construction site of the left bank, the construction site upstream the dam of left bank, the Xiaozhuang-Gumugou construction site of right bank, the dam construction site between the cofferdams, the construction site upstream the dam of right bank and water pipeline construction site and other sites are provided with 1 to 2 blocks of terrestrial vegetation and wildlife protection warning signs, and the total number of the warning sign is 15 blocks. The warning signs are thin steel plates with blue bottom and white words, the specification of the warning sign is 100 cm x 60 cm, (length x width), and the warning sign has the words of prohibiting vegetation destruction and wildlife hunting. The operation mode and time of the construction machinery should be reasonably arrange, the construction mechanical equipment should be the mechanical equipment with low acoustic level, and the time of whistle of the transport vehicle should be reduced, so as to reduce the disturbance of construction noise to the wildlife. 4.1.8.1.2 Impact of Operation Period on Terrestrial Animals and Mitigation Measures When the project is completed, the impact of the project on the local animals will not be significant while ensuring the discharge ecological water use. The habitat of the wildlife at the reservoir area will not be reduced as the water storage of the project, and the project will impact some species of the reservoir area; however, the impact is short, and the new habitat environment can be formed after a period of time, so that the impact of the project on the local wildlife is in an acceptable range. The damage of variety of vegetation and habitat types caused by the construction should be gradually restored by implementing ecological restoration measures in the operation period, and the wildlife habitat can be partially restored. 4.1.8.2 Impact on Aquatic Life and Mitigation Measures According to the ―Aquatic Life Status Monitoring of Environmental Impact Assessment of Cheng County Moba Gorge Water Source Engineering of Gansu Province and Apecial Report of Assessment‖ provided by the Fengyuan ecological counseling center of Gansu, the following analysis is provided: (1) Impact on fish and mitigation measures The construction of the project will change the position for the spawning ground and the wintering ground of Schizothorax subfamily in a short time, but due to the Schizothorax fish will soon find a new wintering ground and spawning ground as the same habitat upstream, so that the wintering and spawning process can be carried out. When the new wintering ground and spawning ground are found, the impact of the project is free. Thus, the impact of the project on the wintering and spawning of the Schizothorax fish is free while ensuring the discharge water. In order to mitigate the impact of the project on aquatic life, following measures should be taken: ① The most basic discharge flow for the growth, reproduction, habitat and wintering and other survival conditions of the aquatic life (especially fish) must be ensured, particularly the discharge should be increased in fish breeding and wintering season. ② Effectively implement the spirit of ―Chinese Aquatic Resource Conservation Platform for Action‖, implement the aquatic organisms maintenance system of "who develops protection, who benefits compensation, who damages restoration", and ensure the on-time and in-full funds for the various funds of aquatic life resources, particularly for the germplasm resources communication and aquatic biological monitoring. ③ The owners should increase the propaganda of the relevant laws and regulations for the protection of aquatic organisms, strictly crack down the illegal practices of poison fishing, electric fish, catch fish and excessive catch by coordinating the local fishery agencies, and resolutely implement the spirit for the notice of natural waters banned of Gansu Province, so as to ensure sustainable development of fish resources, and long-term use purpose. ④ Purchase Jialing Schizopygopsis Tajiri Schizothorax fish artificially bred to implement discharge proliferation. When the water project is finished and run, the discharge cycle is three years, the amount thereof is 2000 Jialing Schizopygopsis Tajiri Schizothorax fishes with the size of 3 to 4 cm, the discharge is a long-term work, and the discharge fees are included in the operation costs. (2) Impact on plankton After the completion of the dam, a reservoir of water is formed, and lots of land and vegetation are flooded; due to the nutrient leached from the flooded soil, the organic matter provided by the decomposition of flooded plants and the scouring effect of the runoff to the surface, a number of nutrients are provided for the growth of algae. At the same time, the growth of algae is convenient as the speed of water flow is reduced, the transparency is improved, and the algal blooms can be promoted. However, when phytoplankton blooms, the transparency of the water is reduced, the optical radiation condition of the water is changed, and the phytoplankton in the reservoir is stabilized after a period of time, so as to reach to a new dynamic equilibrium of algae number. The zooplankton of the reservoir mainly comprises rotifers, cladocerans and copepods. The existing volume and production level of the zooplankton are the impact on the existing volume and production capacity of algae, bacteria and other microorganisms, and the zooplankton is another biological resource in the water reservoir. The change for the geographical position, climate, water temperature and water level of the reservoir are closely related to the reproduction of the zooplankton. (3) Impact on zoobenthos The initial stage when the project is completed, the sediment is deposited on the upstream of the dam, the water surface is expanded, the types of zooplankton, the number of individuals and biomass are increased and improved, a good growing environment and food source are provided to the zoobenthos, so that the biomass and the density of the zoobenthos will be increased, and a rich food source is provided for many indigenous fishes; but as time goes on, the silt layer is thickened, the living environment of the zoobenthos is damaged, and there are some negative impacts on the growth and reproduction of the zoobenthos. If the normal ecological discharge downstream the dam is ensured, the adverse impacts to the zoobenthos are basically free. 4.1.8.3 Impact on Terrestrial Plant In the permanent land of the project, the occupation land of forest is 57.91 hm2 and the occupation land of cultivation is 15.33 hm2; according to the statistics of Cheng County, the local annual production of forest land per hectare is 3200 kg, the annual output of arable land per hectare is 2746.83 kg, the loss of the project to the local biomass is 234.37 t/a, and the details are shown in Table 4.1-5. List for Losses of Project Land to Local Biomass Table 4.1-5 Type Land area (hm2) Biomass loss (t/a) Forest 57.91 185.31 Plantation 15.33 49.06 Total 73.24 234.37 The basin area upstream the Moba gorge of Nan River is 248.2 km, the agricultural acreage is 3133.3 hm2, the forest area is 17133.3 hm2, grassland is 1800 hm2, and the vegetation coverage in the area is 69%. Although the project will have some impacts on the local plant, the impact on the plant of the whole area is in the acceptable range. 4.1.8.4 Impact on Whole Ecological Environment of the Area According to the existing data and the site investigation, the assessment range of Cheng County Moba gorge water source engineering is 1200 hm2. According to the calculation method provided in the ―Technical Regulations of Ecological Environment Status Assessment (Trail)‖ (HJ/T192-2006), the reference to the comprehensive evaluation for the ecological environmental quality of Nantong City provided by Shen Weimin and Qianzhen and others, the study for the environmental quality evaluation of Minjiang River provided by Zheng Shujuan and the combination of satellite remote sensing data, it can be obtained that the ecological quality index EI before completing the project is 61.89, and the ecological quality index EI after completing the project is 61.69, and both the indexes are good eco-environmental quality evaluation; the absolute value of delta EI is 0.2 <2, so that it can be proved that the environmental quality before and after the project construction has no significant change. 4.1.9 Impact on Water Loss and Soil Erosion and Mitigation Measures 4.1.9.1 Project Land Overview The total land of the project construction is95.36 hm2, in which the disturbance land of the project construction is 41.51 hm2, and the flooded area of the reservoir area is 53.85 hm2; according to the land type, the arable land is 12.92 hm2, the forest is 51.64 hm2, and the unused land is 30.81 hm2; according to the land nature, the land comprises a permanent land of 71.91 hm2 and temporary land of 23.45 hm2, and the details are shown in Table 4.1-6. Statistical Table of Project Land Table 4.1-6 Unit: hm2 Project Division Area Subtotal Plantation Forest Unused land

Permanent Main Dam of Land project Moba Gorge 5.13 1.27 6.4 Management 0.8 0.07 0.87 Station Road over 1.07 2.61 3.68 the dam Water 4.4 0.58 2.13 7.11 pipeline Land route of reservoir 7.45 45.13 1.27 53.85 submerged area Subtotal 12.92 51.64 7.35 71.91

Temporary Construction site and land office and living area 8.2 8.2 Residues place 10.9 10.9

Construction road 2.25 2.25

Quarry 2.1 2.1

Subtotal 23.45 23.45

Total 12.92 51.64 30.8 95.36 4.1.9.2 Earth-rock Overview The total excavation volume of the project is 453,600 m3 ((including cofferdam removal material of 3,200 m3), wherein the earthwork is 123,300 m3; the fill capacity is 386,300 m3, of which the earth fill is 44,200 m3, the gravel fill is 2,300 m3, the stone fill is 800 m3, the sand and gravel fill is 14,000 m3, and the artificial aggregate rock is 325,000 m3; the earthwork used is 61,300 m3; the residual earthwork is 467,300 m3 (including the residues of mining stripping layer of 75,000 m3), and the earthwork borrowed is 400,000 m3. 4.1.9.3 Material Intake Yard Profile and Rationality Analysis The material intake yard of natural material of the project is located in Xiaozhuang stock ground, wherein the stock ground is arranged on the right bank of the Nan River downstream the dam and the west side of Xiaozhuangcun, the linear distance of the stock ground to the dam is about 800, the distance to the Xiaozhuangcun is about 650 m, and there are footpaths and simple roads for communicating with the Xiaozhuangcun, so that the traffic is relatively convenient. The stock ground is shown in the form of a spur protruded to east part, the topography of the east side and the north side is high and steep and is shown in the form of an escarpment, the slope thereof is nearly vertical, and the rock is exposed; the elevation for the bottom of the slope of north side is about 1100 m, the bottom of the slope to the east direction is gradually lift up to 1125 ~ 1150 m, the slope height of north side is about 100 m, the slope height of east side is about 25 ~ 50 m; the south side is a colluvial product slope, of which the slope is smooth, the slope angle is 20 to 25 DEG; the topography of the west side is the highest, a wide and slow ridge is extended along east-west direction, the topography is shown in the form that the west part is high and the east part is low, the slope angles for the north and south sides of the ridge are 30 to 35 DEG, and the surface layer is colluvial product gravel soil, and the thickness thereof is 3 ~ 15 m. The engineering properties for the rock of the stock ground are good, the saturated compressive strength, the softening coefficient and the dry density of the rock are capable of meeting the requirements of the relevant specifications to the artificial coarse and fine aggregates, the top of the slope is provided with a colluvial product and residual product layer of 3 to 15 thick, so that the clean work is necessary. The mining length of north-south direction is 220 m, the mining length of east-west direction is 120 m, and the excavation area is about 26,000 m2, wherein the thickness of the useful layer excavated is 50 m, and the reserve thereof is about 1.30 million m3 by means of the calculation method of average thickness. The coarse and fine aggregates for the concrete of the RCC gravity dam are about 327,800 m3, so that the reserve is in line with the requirements of the regulation. The material intake yard is located in a mountainous area, the residents surround the material intake yard are basically free, the noise generated by means of daytime construction can be reached to the standard on the place outside the yard about 200 m, the nighttime construction is prevented, and the impact on the Xiaozhuangcun apart from the yard with 650 m is in the acceptable range; and the land type of the material intake yard belongs to unused land. Thus, the material intake yard has no environmental constraint factors. The detailed analysis is shown in Table 4.1-7. Rationality Analysis for Selection Environment of Stock Ground Table 4.1-7 Project material intake yard Environm ent rationality assessme nt Whether the project is in environmentally The yard is not in environmentally sensitive Reasonab sensitive areas (such as nature areas le reserves, scenic spots, cultural heritage and etc.) Whether the project is in an important The land type of the yard belongs to useful Reasonab resource ground (such as basic land le farmland, specialty sites and etc.) Whether the project is in environmental The geology of the yard is stable, and the Reasonab risk sections (such as avalanches, yard is not in the risk sections le landslides, mudslides, flood channel, wind tunnel and etc.) Whether the environment sensitive The surrounding places of the yard have no Reasonab objective will be impacted residential areas, rare vegetation and other le environmental sensitive targets. Whether the landscape restoration, The impact on the vegetation of the mining Reasonab vegetation restoration and land process of the yard is relatively small, and le restoration and the like of the project are the vegetation can be restored in a certain easy degree after mining. Whether the transportation pipeline is The two villages are avoided while designing Reasonab passed through the unsuitable area the yard, so that the yard did not be passed le ((such as urban, concentrated through the unsuitable area residential areas, schools and etc.) 4.1.9.4 Residues Place Overview and Rationality Analysis The project is primarily provided with 5 residues places, wherein the 1 # and the 2 # residues places are located in the construction site upstream the dam of left bank, the 3 # residues place is located in the construction site upstream the dam of right bank, and the 4 # and the 5 # residues places are located in the Xiaozhuang-Gumugou construction site of right bank. 1 # residues place: the final elevation of the residues place is 1060 m, the land area is 21000 m2; 2 # residues place: the final elevation of the residues place is 1060 m, the land area is 18000 m2; 3 # residues place: the final elevation of the residues place is 1056 m, the land area is 5000 m2; 4 # residues place: the final elevation of the residues place is 1165 m, the land area is 13000 m2; and 5 # residues place: the final elevation of the residues place is 1050 m, the land area is 52000 m2. As the residues of the project are mainly generated by the dam excavation and the primary residues places are too fragmented, the spoil of the dam is respectively sent to four residues places, and the earthwork allocation is unreasonable; after the optimization of the environment impact assessment, the primary 1 # and 2 # residues places are combined, the area is increased, and the optimized residues place is used as the 1 # residues place; the primary 3 # residues place is removed, the primary 4 # residues place is used as the 2 # residues place after optimization and the area thereof is maintained, the area of the primary 5 # residues place is reduced, descended to the height of the residues and used as the 3 # after optimization. The details are shown in Table 4.1-8. Residues Paces Overview Table 4.1-8 Final elevation Storage capacity Residues place Area (hm2) of the dam top (m) Earthwork (ten Stonework (ten thousand m3) thousand m3) Before 1# 2.1 1060 1.5 8.39 optimizatio n 2# 1.8 1060 0 1.6

3# 0.5 1056 2.19 4.02

4# 1.3 1165 0 7.5

5# 5.2 1050 4.22 17.31

Total 10.9 7.91 38.82

After 1# 6.5 1060 7.66 25.05 optimizatio n 2# 1.6 1165 0 7.5

3# 2.8 1040 0.25 6.27

After optimization, the influence area of the residues place does not have the distribution of rare wild animals and plants, and the surrounding places of the residues place do not have residents; from an environmental point of view, the selection scheme of the residues place is reasonable. However, the residues should be protected in the stacking process, so as to reduce water loss and soil erosion. 4.1.9.5 Amount of Water Loss and Soil Erosion and Mitigation Measures The total amount of water loss and soil erosion of the project is 18645.96 t, and the increased amount of water loss and soil erosion is 13342.71 t, wherein the increased amount of water loss and soil erosion in the construction period is 12609.27 t, and the increased amount of water loss and soil erosion in the natural recovery is 12.52 hm2. The division of water loss and soil erosion control is as follows: a dam hub building control area, a water pipeline control area, a residues place control area, a quarry control area, a road construction control area, and a construction enterprise and office and living control area. The soil and water conservation measures comprise 1640 m of slag wall, 1800 m of reinforced stone block, 600 m of dry stone pitching, 25140 m of drainage ditch, 2340 m of bag soil block, 96959 plants, 116 linear meters (the width is 1 m) of holly hedges, 4477 kg of grass seed, 21.88 hm2 of land reclamation, 17.16 hm2 of green space, and the detailed layout program is shown in Table 4.1-9. When the soil and water conservation program is implemented, the control rate of the disturbed ground in the early construction period is 98.67%, the control degree of water loss and soil erosion is 98.07%, block slag rate is 100%, the control ratio of water loss and soil erosion is 1.03, the vegetation restoration rate is 98.76%, the restore coverage is 41.3%, wherein all the indexes are reached to the, and the water conservation measures are reasonable and reasonable. Engineering Quantity of Water and Soil Conservation Measures Table 4.1-9 Constr Hub Water Constr Residu uction buildin Quarry pipelin uction es and No. Project name Unit g control e road Total control living control area control control area control area area area area I Project measures 1.1 Block project 1.1.1 Earthwork m3 825 2951 543 1177 5495 excavation 1.1.2 Earthwork m3 663 663 construction 1.1.3 Grouted stone m3 2930 300 3230 pitching 1.1.4 Reinforced stone m3 1980 990 1230 1200 5400 cage 1.1.5 Asphalt unlined 126 126 upper garment board 1.1.6 Hardcore bed m3 68 15 83 1.1.7 Phi 80mm PVC m 563 563 drainage pipe 1.1.8 Geotextile 88 88 1.2 Slope protection m 600 600 1.2.1 Earthwork m3 125 125 excavation 1.2.2 Dry stone pitching m3 7655 7655 1.2.3 Hardcore bed m3 957 957 1.3 Drainage work 1.3.1 Drainage ditch m 5160 240 5400 1.3.1.1 Earthwork m3 5973 267 6240 excavation 1.3.1.2 Earthwork m3 896 40 936 construction 1.3.1.3 Grouted stone m3 2449 181 2630 pitching 1.3.1.4 Dry stone pitching m3 1570 1570 1.3.1.5 DN500 circular culvert m 10 20 10 30 10 80 pipe of reinforced concrete (pipe of grade II) 1.3.1.6 Hardcore bed m3 830 38 868 1.4 Rock slope greening 1.4.1 ML2.0 x 6.0 nylon net m2 22572 22572 1.4.2 C25 reinforced m3 36 36 concrete panel Anchor rod(Phi 12 1.4.3 mm HRB335 grade m 438 438 steel) 1.5 Land renovation engineering 1.5.1 Land levelling 0.61 8 1 10 5 6 30.61 1.5.2 Topsoil stripping m3 15250 3000 36550 15200 7000 1.5.3 Covering m3 15250 3000 36550 15200 7000 1.5.4 Nutrient soil m3 2228 8880 11108 II Plant measures 2.1 Slope 2.1.1 Shrub 2.1.1.1 Lespedeza Plant 4288 2125 3700 10113 2.1.1.2 Amorpha fruticosa Plant 4288 2125 3700 10113 Extending seed 2.1.2 Blue grass 2.1.2.1 137 68 118 324 Lolium multiflorum 2.1.2.2 343 170 296 809 Festuca 2.1.2.3 206 102 178 485 arundinacea Plane 2.2 Shrub Plant 2.2.1 Lespedeza Plant 513 8350 9500 2.2.1.1 11525 1525 31413 Amorpha fruticosa Plant 513 8350 9500 2.2.1.2 11525 1525 31413 Holly hedges Linear 116 2.2.1.3 116 meter Boston ivy Plant 6841 2.2.1.4 6841 Honeysuckle Plant 6841 2.2.1.5 6841 Arbor 2.2.2 Deodar Plant 6 2.2.2.1 6 Juniperus Plant 100 2.2.2.2 100 formosana Spruce Plant 8 2.2.2.3 8 Salix babylonica Plant 100 2.2.2.4 100 Prunus triloba Plant 4 2.2.2.5 4 Sorbaria sorbifolia Plant 4 2.2.2.6 4 Rosa xanthina Plant 4 2.2.2.7 4 Grass seed 2.2.3 Poa annua 134 152 2.2.3.1 184 24 494 Lolium multiflorum 334 380 2.2.3.2 461 61 1236 Festuca 200 228 2.2.3.3 277 37 742 arundinacea Larix potaninii 149 184 2.2.3.4 540 873 Alfalfa 2.2.3.5 Temporary III measure Temporary drain m 420 3.1 19320 19740 Earthwork m3 364 118 3.1.1 5410 5891 excavation Earthwork fill m3 73 24 3.1.2 1082 1178 Temporary block m 1420 500 3.2 420 2340 measures Bag soil fill m3 710 250 3.2.1 210 1170 Bag soil removal m3 710 250 3.2.2 210 1170 Cover of fiber cloth 8800 4200 3.3 4980 17980 4.1.10 Impact on Human Health and Mitigation Measures 4.1.10.1 Impact of Construction Period on Human Health and Mitigation Measures The construction workers for the construction period of the project are from all sides, and the field personnel and local personnel form a construction community and frequently contact with each other in working and living. As the crowd is complex, the lifestyle is different, the physical conditions are different, the immunity is different, the kinds of pathogen carriers are possible, the susceptibility is enhanced, and a variety of diseases transmission method are coexistent. Thus, if the health protection work cannot be completed well, the infectious diseases can be lead (gastrointestinal, respiratory, and insect-borne), the cross-infection and epidemic spread are easy to be caused, the adverse impact on human health will be caused, so that the health protection work should be paid enough attention. In order to mitigate the impact of construction period on the construction workers, and the following measures should be taken: (1) Hygienic cleaning of construction living area and management area When the civil engineering works of the temporary construction living area and the management area are completed, the site should be cleaned. The garbage, human and animal feces and other contaminants in the site should be cleaned; the sewage pit and the refuse dump should be filled after sterilizing with lime, and the weeds should be cleaned up. (2) Drinking water source protection and drinking water disinfection The drinking water is purified and disinfected, wherein the specific methods are as follows: adding bleaching powder into the drinking water to disinfect after depositing and filtering, adding chlorine into the water for 30 min, so that the killing effect to the variety of intestinal infectious disease pathogens in the water is sufficient when the residual chlorine in the water is more than 0.3 mg/l, and the water purified can be used as drinking water. As the construction and living water is taken from the river and the water source is open, the water quality is easy to be impacted by the human actives around the construction site, so that the protection of the water source should be strengthened, and the protection measures are as follows: the range which is apart from the water source with 100 m should not be provided with temporary life area, management area and production area, and the latrines and seepage pits should be built in the range, and the garbage and other pollutants should not be stacked in the site. (3) Innocent treatment of garbage, manure and wastewater With the collection and treatment facilities arranged on the living area, management area and production area and applied to domestic wastewater, production wastewater and household waste and the like, the innocent treatment purposes of garbage, manure and wastewater are basically carried out. (4) Mosquito prevention, fly disinfestation and rodent control When the construction workers are entered into the site, a good breeding ground will be provided to a variety of animals and insects in case of poor sanitation, the density of mosquitoes and rodents and the like will be improved, and the opportunity of infectious diseases will be increased. Thus, the living area should be subjected into mosquito prevention, fly disinfestation and rodent control, the rodent prevention drugs should be provided regularly so as to cut off the disease source the transmission method. (5) Prevention and quarantine of population health Before entering into the construction site, all the dining room staff of the construction site should be quarantine, part of the construction worker should be subjected to prevention and quarantine by means of a sampling method, wherein the sampling ratio thereof is 15% of the construction workers. Through quarantine, the health status of the construction population can be controlled, and the occurrence of contagious disease in which the construction worker is the epidemic focus can be completely eradicated in time. (6) Crowd evacuation of blasting site The use of explosive on the blasting site is operated by a specially-assigned person, the places around the blasting site are provided with striped flags so as to define the risk area, and all the personnel in the blasting area should be evacuated, so that the casualties caused by blasting can be prevented. 4.1.10.2 Impact of Operation Period on Human Health As the river valley of the project is mainly shown in the form of a "U"-shaped valley, the mountains of the two banks are relatively symmetric, the river is deep, the bedrock of the riverbed is exposed, the falling head is large, and the submerged area does not have large-scale unleveled low-lying land and pond marshy with aquatic weeds and etc., and therefore the submergence for the operation period of the project will not cause the transfer of mosquitoes and the transmission of pathogenesis. 4.1.11 Impact on Reservoir Resettlement and Mitigation Measures The backwater length for the reservoir of the project is 3.5 km, the area of the submerged land is 53.85 km2, wherein in the land, the forest is 45.13 km2, the plantation is 7.45 km2 and the unused land is 1.27 hm2. The submerged area of the reservoir mainly comprises three towns, i.e. Shaba Town, Paosha Town and Chenyuan Town, part area of 6 administrative villages, and the total immigrants thereof is 3 families. In allusion to the special resettlement and compensation problems, the Water Authority of Cheng County develops ―Resettlement Plan of Water Source Project of Cheng County‖, the resettlement point is located in Baimashi Village of Chenyuan Town of Cheng County, wherein the distance of the village to the county is 6 km, the village comprises 8 cooperations, the existing residents is 391, the population is 1,600, the acreage under cultivation of the total village is 2800 Mu, and the net per capita income is 2200 Yuan/year. The distance of the village to the nearest road is about 0.5 km, so that the traffic is convenient. The distance to the post office, shops, schools, kindergartens, theaters and other places is about 1 km. The agricultural products produced therein mainly comprise wheat, corn, soybeans, canola and tobacco and etc. The settlement point planned comprises 20 rooms reconstructed from original farm buildings, the land area thereof is 13.5 Mu, the settlement point has a campus testing field of 76 Mu, wherein the irrigation project thereof is the Lugou reservoir water-saving irrigation project which has been implemented, the requirements of three families to the relocated of Chenyuan Town and Shaba Town can be met, and the irrigable land per capita ensured is about 2 Mu. The compensation measures for the resettlement are in line with the principle of ―ensuring the ‗feasible moving, stable settling, and feasible enriching‘ of the migrants‖, and the compensation measures are reasonable and feasible; the resettlement point has adequate houses for the live of the immigrants, sufficient arable land and good irrigation conditions to ensure the living and production need of the immigrants; the resettlement point has relatively complete municipal facilities, convenient transportation, and favorable new life of the migrants, and the resettlement point can meet the requirements of the resettlement compensation plan. 4.1.12 Dam Break Risk and Mitigation Measures 4.1.12.1 Dam Break Risk According to the research results for the dam safety at home and abroad, the reason for causing the dam break and the break is more and complex, and the reason comprises natural factors and human factors and their mutual relations and complex effects. With the probably analysis, the main reason comprises: (1) Violent earthquake Small earthquakes are not likely to cause the damage and break of the reservoir dam, but a strong earthquake (magnitude is not less than 7.0) is more likely to cause the damage and break of the reservoir dam. As the earthcrust of the place where the reservoir dam is located is relatively stable, the basic seismic intensity is grade VIII, the earthquake fortification of the reservoir dam project is implemented according to the same; furthermore, the reservoir is small (the height of the dam is less than 100), and the earthquake cannot be induced easily, so that the possibility for the large-scale and high-intensity damage of the reservoir dam caused by the earthquake is very unlikely. (2) Temperature change The local damage accident for the concrete arch dam of the reservoir dam due to the temperature change is relatively common, the reason thereof is the thickness of the arch dam is relatively thin, and the arch dam is a highly indeterminate space structure limited by the boundaries. In the operation period of the reservoir dam, the change of the ambient temperature is easy in causing temperature stress in the arch dam body, and the reservoir dam will be broken as the overstressing in certain conditions. However, the temperature change just can cause the local damage of the reservoir dam under normal circumstances, and the suddenly break of the dam can be prevented. (3) Landslides Large-scale instability and high-potential fast slope body will cause enormous swell, the flood downstream the reservoir dam and around the reservoir will be caused, and safety of the reservoir is endangered. Particularly, the large-scale landslides in the place close to the dam and the two sides upstream and downstream are easy to cause reservoir damage and break. Although the project has small-scale hidden danger of slope instability, the total geological conditions of the reservoir area, the dam and the site engineering are relatively good as the diastrophic activity of the place where the project is located are relatively stable, so that the possibility for causing huge surge flood and collapse due to the large-scale instability of the bank and the high-potential landslide is very unlikely. Here, it must be emphasized that the many small-scale instable geologic bodies presented in the slops on the two sides of the river section inside and outside the reservoir area should be strengthened, prevented and subjected to the treatment of embankment and supporting project, so as to prevent the large-scale reservoir banks instability caused by the small-scale reservoir instability can be prevented. In addition, the operation period for putting into production of the reservoir dam, the stone blasting and fish blasting and other blasting activities in the place close to the dam and around the dam should be prevented, and the a large number of materials optionally stacked on the slops of two banks on the place of the reservoir area and the place close to the river downstream the dam should be prevented, and the buildings on the places should be prevented to avoid slump. (4) Destruction of dam foundation The deformation, permeability and stability of the dam foundation are tightly related to the safety of the dam. The good dam foundation should have sufficient deformation resistance and bearing capacity, small permeability and complete and stable rock, so as to prevent the foundation damage caused by excessive deformation, the excessive uplift pressure and the unstable dam body or dam seat rock slide caused by excessive penetration water pressure. The dam foundation of the project can be prevented from the collapse accident caused by instability and deformation, cracking, sliding and water seepage just be strengthening and stabilizing to eliminate the hidden troubles completely through a scientific project processing technology and strict consolidation prevention measures, (6) War and terrorist attacks If the reservoir dam of the project is damaged instantaneously in case of war and terrorist attacks, the flood damage is severe, and the basin-wide disaster may be caused. However, from the military point of view, the possibility for taking the dam as a military target is very unlikely. (7) Extraordinary flood In case of extraordinary flood, the extraordinary flood is always accompanied by heavy rain. Due to the strong erosion effect of the heavy rain, the downstream dam surface will have scour holes. Although these local scour holes will not affect the stability of the dam, the opportunities of overflowing the top of the dam is increased while pushing by the winds and waves in the reservoir. Theses small scour holes will be rapidly expanded under the erosion effect of the flood padding through the dam. When the scour holes are reaches a certain size, the dam will be local instable, and then the dam break phenomenon can be presented. The engineering grade of the reservoir is grade III, the permanent main buildings are designed according to the grade 3, the permanent secondary buildings are designed according to the grade 4, and the temporary buildings are designed according to the grade 5. The concrete gravity dam is designed according to the flood per 50 years and is reviewed according the floor per 500 years, the energy dissipation and erosion prevention buildings are designed according to the flood per 30 years, and these buildings are in line with the requirements of ―Standard for Flood Control‖ (GB50201-94), so that the dam break risk caused by the extraordinary flood can be reduced effectively. (8) Error of survey design If the early work do not be completed well, the hydrographic survey and the geological survey are not detailed, the calculation of the water account is incorrect and the design consider is not thoughtful, the construction may be blind, the hidden danger for the safety of the reservoir will be caused, and the collapse accident of the reservoir is easy to be occurred. Thus, for the flood prevention safety of the dam, the correct survey design and reasonable dispatch application should be paid attention in addition to the reasonable selection of flood prevention standard. The project has done a lot of preliminary works, so that a scientific basis is provided to ensure the quality of design. (9) Quality defects of the dam During the construction process of the dam, the chance of quality defect is always existed due to the uncritical local quality control. The weak link is the place for the occurrence of concentrated seepage and piping, and the dam break can be occurred under the effect of adverse external dynamic loads. Thus, project supervision in the project should be strengthened, the supervision, inspection, evaluation and acceptance of the construction should be organized, and the left tail works should be completed well. (10) Mismanagement of operation In the management work of the dam, the probability of man-made omission and equipment failure is always existed, so that the real-time monitoring for the operation status of the dam will be influenced, the working status of the dam cannot be reflected in time, so that the dam will be dangerous and broken. Therefore, the technical management work of the reservoir should be strengthened, and the safety of the dam should be ensured. In summary, the main reason of dam break comprises low flood control standard of the reservoir, poor construction quality, poor management work and other human factors. But the safety of the reservoir dam can be ensured and the purpose of promoting benefit and abolishing harm can be achieved by seriously implementing the Decree [1991] No.77 ―Reservoir Dam Safety Management Regulations‖ of the State Council, carefully implementing survey design while strictly complying with the regulations, strengthening project quality and technical management work of the reservoir and complying with the provisions for the safe operation of the reservoir. 4.1.12.2 Risk and Result of Dam Break Once the dam is broken, the impacts on the upstream and downstream of the dam are large. In the upstream of the dam, the water of the reservoir area, particularly the water level before the dam will be sharply reduced due to the suddenly discharge, so that the bank of the reservoir dam is easy to be unstable, and the bank is easy to be collapsed. The dam break risk is mainly presented in the downstream, i.e. the dam break wave will be formed as the suddenly discharge of the water in the reservoir, and the damage to the human and property downstream the dam is serious. Thus, when the maximum flow of the dam broken is reached to the flow path L of the downstream dam according to the source strength of the broken dam, the maximum flow is calculated according to the following formula:

wherein, QLm represents the maximum flow (m3/s) for the controlled section of the broken dam apart from the dam with L (m); Vm represents the largest velocity (m/s) of the river section, the value of that in the assessment is 3.0 m/s; K represents the experience factor. The experience factor of the project is 1.2, and the other parameters are ditto. According to the topography downstream the project and the resident distribution condition, the cross-section of rivers of the eight downstream villages which may be impacted are estimated, wherein the details are shown in Table 4.1-10. List for Estimation of Cross-section of River of Each Village Table 4.1-10 village Local dam distance (m) Area of cross-section of river (m2) Majiaya 800 748.53 Jianjiagou 1600 394.63 Zhuanwancun 3500 186.19 Ganlushi 4500 144.81 Xiaozhuang 1300 471.05 Zhangjiashan 1800 350.78 Luangoumen 3300 197.47 Niujiaya 4300 151.55 According to the estimation results of 4.1-10, the households lived in the low-lying and the place close to the river of the eight villages will be submerged, and some villages will be submerged completely. 4.1.12.3 Management Measures of Dam Break Risk In order to ensure the safety of the dam, achieve the purpose of promoting benefit and abolishing harm, prolong the service life of the dam, play the efficiency fully and avoid the dam collapse disaster and risk, the project should take the various of effective protection measures and emergency measures in the whole process of survey, design, construction and operation, so as to take preventive measures and check erroneous ideas at the outset. According to the environmental risk analysis result of the reservoir dam of the project, the reference to the reservoir dam safety work research results at home and abroad, the following prevention and emergency measures are provided by targeting to the main reason which may cause dam damage and dam break. (1) Seriously implement the ―Reservoir Dam Safety Management Regulations‖ (State Council [1991] Decree No. 77). The Regulations clearly defines and strictly requires the construction, management and treatment of the reservoir dam with the height of more than 15 m or the capacity of more than 1 million m3. (2) Strictly handle affairs according to the hydropower project management procedures. In order to prevent damage and break of the dam, the survey, design, construction, acceptance, operation, identification and reinforcement works should be completed well in order. (3) Strengthen geology investigation work of the project. In the project, the geological conditions of the reservoir area, the dam site, and the plant site are relatively complicated, the detailed geological and groundwater survey work should be carried out, and the situation should be identified successively. (4) Carefully design by strictly complying with the specifications. (5) Enhance quality management of project construction. In order to ensure safe operation of the reservoir, the construction period for the construction of the reservoir dam should be provided with the concept of "long-term project, quality first", the supervision work of the project should be strengthened, the quality supervision, inspection, evaluation and acceptance works of the project should be organized, the specifications of construction technology should be carried out, the construction material should be reasonable, the construction work should be strict, and the left tail work should be treated well, so as to ensure the quality of the project and eliminate ―purple‖ project. (6) Strengthen the technical management of reservoir operation. In order to ensure safe operation of the reservoir, a complete reservoir operation schedule and a safe operation of technical system should be established in the operation period for putting into production of the reservoir dam, the level of technical management should be improved, the flood prevention program and schedule application plan should be compiled reasonably, the provisions for the safe operation of the reservoir should be complied; the safety monitoring and identification works of the dam should be emphasized, the dam protection on the bank of the reservoir and the maintenance of the gate crane should be strengthened, the facilities meeting the dam safety observation are set, the safety condition of the dam should be frequently inspected and regularly observed, the flood data should be rechecked, so as to achieve the purpose for finding the problems in time, taking measures in time and preventing the reservoir from adventure operation; the reliable forecasting of construction, early warning systems, transportation and communication facilities improvement should be paid attention, an emergency flood plan should be developed to achieve the purpose of preparing before the flood and responding while flooring; and the power supply and equipment which meet the requirements of gate starting and closing are set to ensure the timely drain. For the flood caused by extraordinary rainstorm, the extraordinary drain measures should be prepared, and the notice on the flood fighting work should be issued in advance. (7) Prohibit the slump in the reservoir area. In the operation period for putting the reservoir dam into production, the stone blasting and fish blasting and other blasting activities in the place close to the dam and around the dam should be prevented, and the a large number of materials optionally stacked on the slops of two banks on the place of the reservoir area and the place close to the river downstream the dam should be prevented, and the buildings on the places should be prevented to avoid slump. 4.1.12.4 Emergency Plan The emergency plan for the dam break risk of Moba gorge water source engineering is "APELL plan" (Awareness Preparedness for Emergencies at Local Level). The information and organizational flow chart of the "APELL plan" are shown in Figure 4.1-5. (1) Organization A coordination group of the "APELL plan" is composed of the leaders of the local government department and the water source engineering construction management department of Moba gorge for city water supply of Cheng County, and the local resident representatives. The responsibilities of the coordination group are shown in Figure 4.1-6. Meanwhile, the police, medical, rescue, environmental protection, transportation, Red Cross, communications and other departments of Cheng County should also be involved in the emergency rescue plan and should bear the corresponding responsibilities. (1) Emergency rescue plan ① In case of emergency, an emergency rescue headquarters is set up according to the "APELL plan" so as to effort to ensure people's lives and property and to reduce the loss to the minimum degree; ② Responsibilities for the onsite commander of the water source engineering construction management department of Moba gorge for city water supply of Cheng County: report quickly, convey the information about the accident and injury estimation, issue police information, organize quick evacuation and evacuate from the dangerous area; ③ Responsibilities of Moba gorge management station: be responsible for reporting the nature, intensity and consequences of the incident, be responsible for the emergency measures taken on the accident site to prevent the accident from expanding, reduce the risk and rescue the casualties of the accident; ④ Professional rescue team: organize evacuations, medical care and other rescue operations of the professional team; ⑤ Traffic control: control the traffic of diffusion area, effectively implement evacuation; ⑥ Transportation, supplies, communications, publicity and other supports; ⑦ Allocation of specially-assigned person, equipment and aid medicine; ⑧ Emergency restoration: including de-alerting, site cleaning, care-taking arrangement and accident investigation. (2) Plan practice In order to enhance the scientificity, pertinence, effectiveness and maneuverability of the plan, the anti-accident training is organized in the area may be impacted by the accident, wherein the training place comprises the enterprise, the village and the settlement point and the like in the area; at the same time, the relation to the environmental emergency response agencies of other reservoir construction project should be established, the local relief activities should be organized and involved, and the relevant communication and cooperation should be developed. The exercises are aimed at inspecting the plan, training the team and improving the capability, promoting the connection between the Moba gorge water supply project and the emergency plan of Cheng County and the continuous improvement of the corresponding emergency plan.

Aid Command, assistance

Starting the plan, aid

Comman

d Moba gorge Water authority Government of Cheng county management station of Cheng county Report Report Aid

Report Other enterprises Starting and villages in Report prevention the region Coordination group plan 1. Leader of Cheng county

government Non-governmental 2. Principal of Cheng county Water service organization Authority

3. Principal (police and emergency,

Notice etc.) of each enterprise Notice Local area public Prevention 4. Surrounding public representative

Public security bureau, hospital

Aid

Aid

Figure 4.1-5 APELL Information and Organizational Flow Chart Responsibilities of the enterprises and villages in the accident area: 1. Ensure safe operation; 2. Ensure personal security; 3. Establish safety procedures; 4. Protect onsite life and property; 5. Coordinate all the staff in the accident; 6. Develop plans and measures to meet emergencies. Effects of the coordination group: 1. Establish communication systems; 2. Share information; 3. Coordinate emergency plans and measures; 4. Communicate with other accident emergency agencies; 5. Joint education and training; 6. Solve the common problems; 7. Support bilateral assistance. Responsibilities of the government of Cheng County 1. Provide a safe area; 2. Protect the safety and welfare of the resident in the region and the outsider; 3. Establish public safety programs; 4. Protect life and public and private property; 5. Coordinate the accident emergency power in all accidents; 6. Develop emergency plans and measures; 7. Train and exercise the plan together with other emergency agencies in the region or the province. Figure 4.1-6 Responsibilities of Each Emergency Plan Group 4.2 Public Participation 4.2.1 Significance of Public Participation Public participation is an important component of environmental impact assessment and is an effective way in improving scientific decision. In the construction project, public participation is an important method for promoting the two-way communication among the construction unit, the environmental impact assessment unit and the public. By means of wide public participation, the public directly or indirectly impacted by the project construction can fully understand the possible environmental impacts, the environmental protection measures to be taken for mitigating the impacts and the economic and social benefits brought by the project construction; at the same time, the various views and suggestions can be fed back, the advices can be actively provided to the project construction, the solutions to problems can be jointly found out, the impact of the project construction on the environment can be minimized, the pollution disputes in the project construction and operation process can be prevented, and the development and environmental protection can be coordinated well. 4.2.2 Public Participation Form and Composition of Participants The project uses three forms, i.e. questionnaire, newspaper publicity and symposium, wherein the questionnaire is divided into two forms which are government agencies questionnaire and public questionnaire, and the content of the questionnaire is designed according to the characteristics, scales and possible impact degree and the like. (1) Composition of the public questionnaire The public opinion survey of the project is completed by issuing 100 copies of questionnaire in the whole range of the Cheng County, wherein the 10 copies are issued to the reservoir resettlement, the effective questionnaire reclaimed is 100 copies, the effective questionnaire is 100 copies, and the reclaiming rate is 100%. (2) Composition of government agencies questionnaire department The government agencies questionnaire of the project comprises Environmental Protection Agency of Cheng County, County Land Resources Bureau of Cheng County, Water Authority of Cheng County, Forestry Bureau of Cheng County, Transportation Department of Cheng County, people's congress committee of Cheng County, people's government of Cheng County, Development and Reform Bureau of Cheng County, Public Security Bureau of Cheng County, construction bureau of Cheng County, Planning Board of Cheng County, health bureau of Cheng County, tap water companies of Cheng County, People's Government of Chenyuan Town, People's Government of Shaba Town, finance bureau of Cheng County, Board of Education of Cheng County, County Office and Committee offices of Cheng County of the Chinese People's Political Consultative Conference and other 20 departments. (3) Publicity The project was subjected to publicity to solicit public comments on the project for 10 days in ―Longnan Daily‖ of January 9, 2011. (4) Composition of symposium According to relevant requirements of the World Bank, the symposium is held in Wujiashan Village of Chenyuan Town and Niuyao Village of Shaba Tow by the staff of the Water Authority of Cheng County, the overview of the project is introduced to the local people in the symposium, and the suggestions of the local people to the project are collected. 4.2.3 Summary of Public Participation Comments By means of the method above, local people understand the project and provide the following suggestions to the project: (1) Since the construction of the project has a greater impact on the local ecological environment, the relevant departments must strengthen the management of the construction and operation processes, restore the existing ecological damage, develop a detailed reservoir vegetation restoration plan and ensure the ecological function of the reservoir area plays its role. (2) Strengthen management and supervision, and ensure the resettlement compensation measures are in place, so that the immigrants can live and work. (3) Speed up the progress of the project, so that the project can play a role as soon as possible and problem of water supply of the resident of Cheng County can be solved. (4) Strictly manage to ensure the guaranteed of quality of water in the operation period. (5) Strengthen supervision inspections to prevent dam break accident.

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

5. Environmental Management Organization of the Project 5.1 Introduction According to the spirit of management authority of ―Environmental Protection Law of the People‘s Republic of China‖ and ―Regulations on the Administration of Construction Project Environmental Protection‖, the environment impact assessment report of the project is approved by the Provincial Environmental Protection Office of Gansu, and the soil and water conservation report is approved by the Department of Water Resources of Gansu Province. The Environmental Protection Bureau of Gansu Province, the Department of Water Resources of Gansu Province, the Environmental Protection Bureau of Longnan City and the Department of Water Resources of Longnan City are the environmental management agencies of the project, and the responsibilities thereof mainly comprise: providing environmental protection requirements according to the contents of the environment impact assessment report of the project and the contents of the soil and water conservation report, coordinating the environmental protection management among the various departments, and be responsible for organizing the "Three Meantime" acceptance inspection work of environmental protection facilities. In the overall administrative institution framework of the project, the implementation of the entire project is managed by the Loan Project Office of the World Bank, the project is led by the governments of Longnan City and Cheng County, and the project owner (the water source engineering construction management department of Moba gorge for city water supply of Cheng County) is responsible for the specific matters for the implementation of the project in the project management office. In order to ensure the smooth implementation of environmental management action of the project, a number of full-time or part-time environmental management personnel are set among the project office, project owner, contractor and operator, so as to implement the environmental management plan specifically. The Loan Project Office of the World Bank in Longnan City is responsible for project planning, design, environmental protection targeting to the project, supervision and management in the program, and the organization work for the skill training of the area-wide environmental management personnel of the project; the main responsibilities of the project office of Cheng County, the Environmental Protection Bureau of Cheng County and the Water Authority of Cheng County comprise: implementing the implementation plan of the project, implementing a variety of technical standards of the project, and implementing daily supervision for the environmental management of the project; according to the commission of the project owner, the environmental monitoring station of Cheng County is responsible for monitoring the environmental quality in the construction and operation period of the project; and the environmental supervision engineers and the water conservation engineer commissioned by the owner are responsible for the environmental supervision and the water and soil conservation supervision in the construction process of the project. The project owner plans to be set up specialized environmental managers who are responsible for the environmental management of all stages of the project, the implementation of environmental protection regulations and programs, the checking work for the implementation condition of environmental protection measures of the project, the promotion and application for the advanced environmental protection technology and experience, the organization of environmental protection technology training of the relevant personnel, and the improvement of personnel quality. As the large differences between the environmental management content of the construction period of the project and that of the operation period, the work times of the two periods are different in temporary and long-term properties, so that the organizations are established by the contractor and the operator according to the difference of the stage, and the responsibilities are staged. When the construction period is ended, the corresponding agencies are removed immediately, the management agencies of the operation period are in operation, and a certain of cross therebetween is allowable according to the specific circumstances of the work. The institutions establishment figure is shown in Figure 5.1-1. Provincial level: Department of Water Resources of Gansu Province, Environmental Protection Department of Gansu Province, the World Bank City level: water conservancy bureau of Longnan City, environmental protection bureau of Longnan City, Loan Project Office of the World Bank in Longnan City County level: environmental protection bureau of Cheng County, Water Authority of Cheng County Owners Enterprise level: environmental monitoring station of Cheng County, environment impact assessment unit, design unit, construction contractor, environmental supervision engineers, environmental monitoring station of Cheng County, owners 5.1-1 Diagram of Environmental Protection Organization of the Project 5.2 Environmental Organization of Construction Period 5.2.1 Organization Technology level: in the technical level of environmental management, the project office of Longnan City will employ 3 experts to participate in management of the project. Project office level: the project office of Longnan City will appoint a project environmental manager for supervising the implementation of environmental management plan, and all the problems related to the World Bank and environment are responsible by the person. The project office of Cheng County has an environmental manager who is responsible for supervising the implementation of environmental management plan in the jurisdiction and responsible for the communication to the project office of Longnan City on the environment-related issues. Contractor level: the contractor has 1 ~ 2 environmental manager coordinators who are responsible for the supervision of environmental protection measures implementation in the construction period, and responsible for the contact with the surrounding residents to solve the environmental issues and the communication with between the project office and the environmental supervision agency. Operator level: each enterprise establishes an environmental management department, the environmental management department is composed of two full-time environmental protection personnel, and the company's daily staff will assist the two engineers so as to complete the environmental management work in the operation stage of the company. The company will configure network, telephone and other communication facilities to maintain the communication to the environmental management institutions. Environmental supervision engineers and water conservation supervision engineer level: the project owner will hire an environmental supervising engineer and a water protection supervising engineer so as to carry out the onsite environmental management supervision in the construction process. 5.2.2 Positions and Responsibilities A. Technology environmental experts Technology environmental experts are technical support of local project office. In the first six months of the project, they will track the project completely and provide regular service in the 4 years after implementing the project, and the frequency thereof is two weeks quarterly. Technology environmental experts will ensure that all necessary requirements will be met in the beginning of the project and ensure that the environmental management system will be effectively implemented according to the environmental laws and regulations and the security requirements of the World Bank. ① For the environmental managers of the project office, the environmental management personnel and the environmental supervision engineers should be provided with necessary training by the contractors and operators. ② Provide expert advice to the project office, the owner, the contractor and the operator. ③ Help the environmental management personnel of the enterprise to organize monitoring activities. B. Project office: environmental manager The project office of Longnan City and the project office of Cheng County set an environmental manager, respectively, wherein the environmental manager of project office of Longnan City is an expert who is responsible for reporting to the World Bank and supervising the environment of the project; the environmental manager of project office of Cheng County is responsible for supervising the local project and reporting to the project office of Longnan City. The environmental Manager will assist land management agencies and resettlement agencies, so as to prevent these agencies from obstructing the implementation of the project, and the responsibilities of the environmental manager are as follows: ① Provide training for the environmental manager in the assistant's help. ② Develop monitoring plans in the assistant's help. ③ Communicate with environmental managers and construction workers, wherein the communication methods are as follows: - Provide monthly and regular monitoring report to the project office and the World Bank - Provide a special incongruent report in case of the second and the third conditions - Make oral communication with the construction unit and the operation unit if the solution of the problem is found, so as to reach a solution. - Jointly provide corrective measures with the environmental management engineers and the environmental managers in case of incongruent conditions. ④ Participate in the joint meeting of environment engineers of project office of the company, environmental managers, construction unit and operation unit. ⑤ Coordinate the communication and report of environmental management experts and the World Bank. C. Project owner: environmental manager coordinator The owner sets up an EMC who is responsible for monitoring environment and reporting the environmental protection implementation condition of the construction unit and the operation unit to the project office of Cheng County and the government agencies, and the detailed responsibilities of the environmental manager coordinator are as follows: ① Ensure the compilation of environmental protection rules of the construction unit and the operation unit under the help of the technical assistant in the initial stage of the project, monitoring details and environmental protection procedures of the construction unit and the operation unit, and the collection for the framework of project management personnel. ② Commission the project with special monitoring equipment, such as water environment quality monitoring. ③ Provide reports, implementation conditions and remedial measures of the project and feasibility to the project office monthly, and monthly hold a meeting with the project office to report the monitoring condition of the project and discuss the conformance of the project. ④ Provide training methodology and technology consulting by the experts and consultants selected from universities and institutions, wherein the training methodology and technology consulting are determined according to the requirements. ⑤ Organize the special studies and public surveys which are related to the specific construction requirements of the actual situation of the project or the necessary change. ⑥ Report the solutions and emergency measures for the conformance conditions of feasibility study to the environment manager of the project office and the environmental monitoring agency. ⑦ Disclosure the information bye mans of meetings and local media. D. Environmental supervision engineers and water conservation supervision engineers The environmental supervision engineers and water conservation supervision engineers are mainly responsible for the construction activities of the supervision party and other related activities such as land use and relocation, ensuring that the activities above are in line with environmental protection requirements, environmental protection investment and environmental objectives, and responsible for onsite coordination for the relation among the land management department, the migration department and the environmental monitoring and control department. The main responsibilities of the environmental supervision engineers and water conservation supervision engineers are as follows: ① Ensure all project permits and requirements, and the implementation of the environmental management plan before starting. ② Check that the environmental protection measures and the water conservation measures are implemented by all employees of the construction unit and the operation unit according to the contract. ③ Compile standard monthly report for the monthly pay which is in line with the qualification of the construction unit and the operation unit obtained according to the efforts and contributions for the environmental protection activities of the project. ④ Assembling file of environmental monitoring. ⑤ Identify the conditions required to be subjected to special studies and special activities, simultaneously communicate with EMC, and regularly and effectively implement special measures. ⑥ Communicate with construction workers to help the construction workers to explain the onsite environmental requirements, provide recommendations for remedial measures, provide remedial measures for the project which is not in line with the original intention of the project, and provide special formal guidelines to the construction unit and the operation unit according to the requirements. ⑦ Communicate with construction unit, operation unit and construction consultant to enhance the communication, get some other views on specific issues so as to quickly response some problems encountered in the construction process to the construction management engineers to help the engineers to solve the problem; if the project has potential damage to the sensitive objectives or the project has or relates to serious discrepancies, it should be stopped according to the application. ⑧ Communicate with construction supervision engineers and construction workers of the project, compile regular weekly monitoring publication, develop incongruent record, and provide remedial measures to the project designer, if necessary, in case of the difference to the project design. 5.3 Environmental Management Organization in Operation Period The operator of the project sets up a special project environmental management office which is responsible for the implementation of environment management plan of operation period. The detailed responsibilities of the environmental management office are as follows: (1) Manage the implementation of project environmental protection measures; (2) Coordination the relevant environment problem with the environmental supervision and management department and the surrounding residents; (3) Commission monitoring station of Cheng County to specifically monitor the three wastes discharged by the project facilities and the regional environmental quality; (4) Implement environmental risk emergency measures in case of environmental accidents; (5) Be responsible for timely reporting the relevant information of enterprise environmental management to the environmental protection bureau of Longnan City and Cheng County and the project office of Longnan City; (6) Record and file the environmental management files of the enterprise. 5.4 Details of Environmental Management Organization of the Project The setting conditions of the environmental management organization are shown in Table 5.4-1. Environmental Management Personnel Setting of the Project Table 5.4-1 Organization Environmental Manager Environmental expert Project office of Longnan City 1 3 Project office of Cheng County 1 1 Total 2 4

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

6. Implementation of Environmental Management Plan 6.1 Project Environmental Management 6.1.1 Overall Management The Environmental Protection Bureau of Longnan City is responsible for overall management of the entire project as the Loan Project Office of the World Bank is led and commissioned by the government of Longnan City. The project office of Cheng County is responsible for coordinating and supervising the project environmental management of the project, the owner is responsible for the implementation of relevant environmental management plan of the project, the environmental management plan is implemented under the assistance of the environmental supervision engineers, and the project office is provided with at least one environmental supervision engineer. The specific responsibilities of the environmental protection management agency are as follows: the project office of Longnan City is totally responsible for managing the environmental protection works, organizing the feasibility study of the project, developing the plan of environmental protection work of the project, coordinating the environmental management works among the management departments and the construction unit, guiding the construction unit in implementing the various management measures; the project office of Cheng County is responsible for coordinating project preparation and operation issues; the environmental protection manager of the project office is responsible for environmental protection plan and environmental management of design stage; the owner is responsible for the implementation and management of environmental protection measures in the construction period and operation period. The environmental protection bureau of each level is responsible for supervising the implementation of environmental management plan of the project. The specific implementing organization of the environmental management plan mainly comprises owners and project contractors, and the responsibilities thereof are shown in Table 6.1-1. Main Responsibilities of Project Implementing Organization Table 6.1-1 Organizatio Main responsibilities n name Subject the environmental protection to the supervision of environmental protection departments at all levels, project office and the World Bank; Commission the environment impact assessment unit with the relevant qualifications to develop the carry out environmental impact report and the environmental management plan; Design the tendering company according to the requirements, wherein the various environmental management measures of the environmental management plan are involved into the design and written into the statement specification, so as to Owner implement environmental protection laws and regulations, the environmental protection measures in the environment impact assessment report, and the plan of environmental protection work; Ensure the normal operation of environmental protection facilities, inspect by the environmental protection departments, establish environmental protection files and report to the project office and the environmental protection management departments of all levels; Sign a commissioned monitoring agreement (contract) with the environmental monitoring department, and implement environmental management plan; Provide funds of environmental protection inspection or sampling. In the construction process of the project, the contractor plays a key role in implementing environmental management, pollution control and prevention measures; Commission and implement the environmental supervision work, and write the environmental supervision plan to the establishment contract; Select contractor with strength and qualifications, and write the environmental management plan into the contract agreement so as to ensure the environmental management plan is implemented effectively. Subject the contractors and construction supervisors to relevant environmental protection and environmental management training before starting; The environmental impact mitigation measures during construction period should be included in the tender documents of the contractor and finally included in construction contract as the contract requirement to the contractor; Subject the contractor to environmental activities monitoring, regularly provide an environmental performance log for one time, and supervise and review these records Contractor by the project office and the construction supervision team; Contractor should provide a full-time environmental staff for the section, and the staff should receive the training of the training plan so as to be competent to their work; In the construction process, the contractor should communicate and coordinate with the masses of the project area, establish bulletin board in each construction unit to inform the public of specific construction activities and construction time, and simultaneously provide the contact and contact phone to provide complaints and advices of the masses to the construction activities. 6.1.2 Management Supervision The environmental supervision organization of environmental construction project of Gansu province is composed of the Environmental Protection Bureau of Gansu Province, the Environmental Protection Bureau of Longnan City and the Environmental Protection Agency of Cheng County. The management and supervision functions of the organization of each stage are shown in Table 6.1-2. Staged implementation of supervision organization: (1) Feasibility study stage: this stage is responsible by Environmental Protection Bureau of Gansu Province, Department of Water Resources of Gansu Province, Environmental Protection Bureau of Longnan City, Water Conservancy Bureau of Longnan City, Environmental Protection Bureau of Cheng County, and Water Authority of Cheng County. The Environmental Protection Bureau of Gansu Province guides the implementation of the various regulations of the Environmental Protection Bureau of Longnan City and the Environmental Protection Bureau of Cheng County and is responsible for the completion acceptance of environmental protection facilities. The Department of Water Resources of Gansu Province guides the implementation of the various regulations of the Water Conservancy Bureau of Longnan City and the Water Authority of Cheng County and is responsible for the completion acceptance of soil and water conservation facilities. The Environmental Protection Bureau of Longnan City is responsible for supervising and managing the environmental protection work of the project, organizing and coordinating the relevant organizations to service for the environmental protection work of the project, supervising the implementation of environmental action plan of the project, and is further responsible for completion acceptance of environmental protection facilities of the project and the guidance of the Environmental Protection Bureau of Cheng County to the environmental supervision and management of the construction period and operation period of the project. The Water Conservancy Bureau of Longnan City has a water conservation division which is responsible for supervising and managing soil and water conservation work of the project, organizing and coordinating the relevant organizations to service for soil and water conservation works, and is further responsible for the completion acceptance of soil and water conservation facilities and the guidance of the Environmental Protection Bureau of Cheng County to the supervision and management of water loss and soil erosion in the construction period and operation period of the project. (2) Design stage: the stage is responsible by the Loan Project Office of the World Bank in Longnan City and is supervised by the Department of Water Resources of Gansu Province in the preliminary design check. (3) Construction stage: the stage is responsible by the Environmental Protection Bureau of Longnan City. The Environmental Protection Bureau of Cheng County is subjected to the work guidance of the Environmental Protection Bureau of Longnan City and is responsible for supervising the implementation of environmental action plans of the construction unit and the implementation of the relevant environmental management regulations and standards. The Environmental Protection Bureau of Cheng County is responsible for the coordination of the environmental protection works along the departments, the construction, completion acceptance, operation inspection, and supervision management of the environmental protection facilities of the project. (4) Operation stage: the stage is responsible by the Environmental Protection Bureau of Longnan City, the Environmental Protection Bureau of Cheng County and the competent authority of the project. The competent authority of the project is responsible for the implementation of environmental protection regulations and standards, the development and implementation of environmental protection regulations and the understanding of environmental condition of the project, so as to check the environmental quality control objectives, provide control measures, submit to the higher authorities, the administrative departments and the water conservancy department, organize employment with certificates of the environmental protection personnel and personnel training, and be responsible for carrying out environmental protection and technological exchanges and scientific research. (5) The environmental monitoring works of construction period and operation period are implemented by the environmental monitoring station of Cheng County. The environmental supervision work is specifically implemented by the project supervision company of Cheng County. When the project is completed, an environmental management organization will be set, and full-time staff in charge of the project's environmental protection work will be set. Environmental Protection Supervision Plan of the Project Table 6.1-2 Stage Organization Supervision content Supervision purpose Environmental 1. Review environmental impact 1. Ensure that the environment Feasibil Protection Bureau report impact assessment is ity comprehensive, the feature set is of Gansu Province 2. Review EMP study proper, and the focus is stage Environmental 3. Review CEA outstanding; Protection Bureau 4. Review the feasibility study 2. Ensure that the significant of Longnan City report potential problems may be caused by the project have been The World Bank 5. Review soil and water reflected; Department of conservation plan 3. Ensure the specific and Water Resources feasible implementation plan for of Gansu Province the mitigation measures of environmental impact; 1. Strictly implement ―Three Meantime‖; 1. Review preliminary design of 2. Ensure that these sites are in Government of environmental protection and line with the environmental Gansu Province EAP protection requirements; Environmental 2. Check the reduction of 3. Reduce the impact of Protection Bureau construction temporary land construction on the surrounding of Gansu Province occupation, vegetation reduction, Prelimi environment, and implement the Department of and environmental rehabilitation nary relevant environmental Water Resources 3. Check the dust and noise design regulations and standards; of Gansu Province pollution control measures, and 4. Reduce the impact of Government of construction time decision constru construction on the surrounding Longnan City 4. Check the emission of air ction environment, and implement the pollutants phase Environmental relevant environmental 5. Check the discharge of Protection Bureau regulations and standards; domestic water of construction of Longnan City 5. Ensure that the river water is site and the treatment of waste Department of not contaminated; engine oil Water Resources 6. Ensure that the landscape and 6. Recovery and processing of of Longnan City the land resources are not being soil intake and spoil sites seriously damaged, and avoid water loss and soil erosion; 1. Check the implementation of Environmental EMP in operation period; Protection Bureau 2. Check the implementation of of Longnan City environmental monitoring plan; 3. Check the sensitive points to Environmental 1. Implement EMP and soil be provided with further Protection Bureau conservation programs; environmental protection of Cheng County 2. Implement monitoring program; Operati measures which may appear Water Conservancy 3. Effectively protect the onal environmental problems not Bureau of Longnan environment; stage estimated) City 4. Check whether the quality of 4. Strengthen environmental Water Authority of the environmentally sensitive management, and effectively Cheng County points is in line with the protect human health; Public Security and corresponding environmental Fire Department of quality standards; Cheng County 5. Check the implementation of soil and water conservation plan 6. Check the implementation of water loss and soil erosion monitoring program 7. Strengthen supervision to prevent incidents, pre-establish emergency plan in the event of an accident, and eliminate the hazard in time. 6.2 Detailed Task for Implementation of Environmental Management Plan The project has adverse environmental impacts during the construction period and operation period, in relation to the characteristics of adverse environmental impacts in the construction period and operation period, the corresponding environmental protection measures are taken, so that the various impacts are reduced to acceptable level. In order to ensure that environmental measures to be effective, environmental management and monitoring procedures are provided. The project office of the World Bank will track and report the monitoring conditions of environmental measures while carrying out its project management functions. This chapter describes the general environmental measures and the responsibilities of relevant units. In the project, the project office is responsible for tracking and reporting the implementation conditions of each measures of environmental monitoring. The list for the implementation management and monitoring activities of environmental measures is shown in Table 6.2-1. List for Detailed Activities of Environmental Management Organization Table 6.2-1 Plan Activities Responsibilities Remark Manageme Implementation Supervising nt organization organization organizatio n Earlier construction period 11 Establish an environmental management design team, and PMO Owner PMO Call the members, select office, months call the members purchase traffic equipment, and raise operating costs 11 Select or designate an environmental supervisor for each CSE EMD CSE months CSE 11 Implement the environmental supervisor training for each CSE EMD CSE months CSE 11 Compile and implement the training plan of EMO and PMO PMO (TA) Technical PMO Implement part of global training of months environmental manager assistant the project manager 11 Compile work plan of the EMO and the environmental PMO Technical PMO Including the operation for clearing months supervisor assistant the role and responsibilities of the manager EMO and the environmental supervisor 11 Develop working files: standards, onsite inspection table PMO EMD PMO Regulate the primary file in a months and different activities report format certain degree, regulate while using in site 11 Develop detailed steps of EMD by targeting to the PMO TA PMO months incongruent phenomenon found in the supervision and report 11 Provide appropriate evaluation for the environmental PMO 0 TA helps EMD PMO/WB months elements and the negotiations Ensure the consistency between Compile commission contract for the EMD for activities 11 the implementation of the process supervision (the specific supervision equipment such as PMO EMD months and the working plan and the land water quality and atmospheric monitoring is required) use Construction period 16 File and process for the discussion between the ― EMD/ PMO In order to improve the regulation months environmental supervisor and the EMD for the project environmental process of efficiency requirements adjustment and improvement supervisor Owner and 16 The contractor of each section must appoint a full-time staff Construction with rich environmental responsibility to work together with constructio PMO Enterprise licensing months unit the environmental supervisor and the EMD n unit Owner and EMD/ Introduce onsite management and 16 The construction unit of each section should organize its Construction constructio environment environmental problems by the months labor force to learn environment knowledge and measures unit n unit al supervisor EMD 16 Organize public communication and provide support PMO EMD Owner Establish exchange regulations months material and procedures, and establish exchange regulations and procedures through radio and television Operation period Confirm the procedures for reporting the environmental Owner Environment problems of operation period al Protection Bureau of Cheng County Confirm the solid waste generated by the project is Owner and Environment intensively stacked and stored and is treated safely sanitation al Protection department Bureau of Cheng County

6.3 Contract Requirements of Environmental Management In the project construction, the contractor plays a key role in environmental management, pollution control and prevention measure and other factors, and therefore the contractors should be required as follows: (1) Select the contractor with strength to ensure the effective implementation of environmental management plan; (2) The contractors and the construction supervisor must be subjected to the relevant environmental protection and environmental management training organized by the TA before starting; (3) The environmental impact mitigation measures during the construction period above should be included in the tender documents of the contractor and finally included in the construction contract as the contract requirements of the contractor of the project. (4) The environmental activities of the contractor should be monitored, provide a daily or weekly environmental performance record, and monitor and review these records by the project office and the construction supervision team. (5) The contractor should provide a full-time environmental staff for each section. These environmental staff should be subject to the training of the training plan so as to qualify their works. (6) In the construction process, the contractor should communicate and coordinate with the masses of the project area, establish bulletin board in each construction unit to inform the public of specific construction activities and construction time, and simultaneously provide the contact and contact phone to provide complaints and advices of the masses to the construction activities. (7) In the project contract funds, the contractors should obligate the deposit of environmental management and other factors according to the annual budget, wherein the amount of the proportion should be about 3% of the budget account. 6.4 Information Exchange and Resolution of Undesirable Condition In the environmental monitoring work, the information should be exposed to the onsite environmental supervisors, the environmental management managers of the enterprise and the project office, wherein the information is monthly exposed for one time, the monitoring report is developed by an environmental monitoring staff and is distributed to the onsite environmental supervisors, the environmental management managers of the enterprise and the direction of the project office. In order to focus on the most important issue of management, the importance of non-compliance basis of the project is divided into three different levels as following: Level 1 Definition: the condition of the non-compliance is defined as the project is incongruent to the original requirement, but the non-compliance will not cause immediate impact on the particularly important resource. If the recurring of the first level did not be paid attention, the second level will be caused. Measures: properly handle the situation of the first level by means of appropriate cooperation and regular exchange. For example, discussing with the staff of the construction unit and the operation unit, quickly implement remedial measures, wherein the typically formal communication from is a weekly case report from the environment supervision engineer to the environmental management manager of the enterprise and the onsite construction manager. Level 2 Definition: the non-compliance condition does not cause obvious damage and irreversible impacts on the sensitive and important resource, but the non-compliance condition should be remedied and treated immediately to prevent the impacts above. If the recurring of the second level did not be paid attention, the third level will be caused. Measures: in case of the discovery of the event of the second level, the event must be reported to the environmental manager of the project office and the onsite construction manager by the environmental management manager of the enterprise, so as to achieve remedial measures as soon as possible, and the remedial measures will be provided in a week after the discovery, generally. Level 3 Definition: the level includes the damage to the sensitive objectives paid special attention or foreseeable and coming damage. The particular behavior internationally prohibited is also divided into three levels. Measures: report the conditions to the environmental manager of the project office and the onsite construction manager by the environmental management manager of the enterprise once discovering, achieve remedial measures as soon as possible, and the remedial measures will be provided in three days after the discovery, generally. The time will be longer in case of special conditions. If necessary, the environmental management manager of the enterprise can require the construction manager to stop some special projects for protecting the resources before implementing the remedial measures. 6.5 Training-- Necessary Capacity Building and Means Building 6.5.1 Training Requirement The objective of environmental capacity building mainly comprises environmental management personnel and environmental supervisor, and the training thereof is one of the technical support parts of the project. In the construction process of the project, the training courses comprise construction party training and worker training. Before starting the construction of the project, all the construction units, operation units and construction supervision personnel should participate in the mandatory environment, health and safety training. 6.5.2 Training (1) Environmental management personnel and environmental supervision engineers The training is organized by the project office of Longnan City, the environmental manager of Cheng County project office, the environmental manager coordinators of the project and the environmental supervision engineers and other related personnel are subjected to centralized training before one year of starting the project in Longnan City, and the specific training is carried out by the technical experts of environment. The content of the training is shown in Table 6.5-1. (2) Contractors and construction workers The training is organized by the project office of Cheng County or the construction owners of the project in the place where the project is locate before starting the project, and the specific training can be carried out by the technical experts of environment or trained environmental managers of the enterprise. The specific training content and duration are shown in Table 6.5-2. Training of Environmental Managers and Environmental Supervision Engineers, Water Conservation Supervision Engineers Table 6.5-1 Problem Training content Duration Quick identification Word, Excel and PowerPoint hotkey Operation capability function to learn the security policy of the World Bank (environmental Reinforcement learning for the building-designated manager, environmental conditions, technical consultants after the environmental 4 days compilation of environmental details, wherein each detailed supervisor and water conservation detail should comprises a monitoring description. Learn the supervisor) environmental impacts on the project and the environmental projects required to be monitored. Compliance monitoring (environmental The onsite monitoring process of the training project comprises manager, organization, communication, roles and responsibilities, 1 day environmental decision-making process, and the observation procedures of supervisor and water report and standard. conservation supervisor) Onsite knowledge of hazardous materials Emergency response Potential leakage and overflow team (environmental Environmental and personal impact of leakage manager, and overflow environmental 1/2 day supervisor and water The emergency response process comprises conservation priority response supervisor) Location and use of response facilities, Communications and reporting facilities Emergency relief and medical assistance (environmental Process for finding medical assistance in emergency and manager, non-emergency state, and process for finding other related 1/2 day environmental medical aids. (For example, long-distance calls, medical supervisor and water advice) conservation supervisor) Correct use and storage process Hazardous materials Correct use process comprises fuel filling process, calculation and waste management, of use amount, and ensured effective use of the equipment including the disposal Correction treatment of used storage tank of explosive waste Storage process of hazardous waste 1/2 day (environmental Management of borrowed land and slash manager and Management of non-hazardous waste environmental Medical problems expose to hazardous waste supervisor) Emergency response process Health and safety inspection and reporting process Health and safety issues (environmental Health and safety requirements manager, How to implement health and safety 1 day environmental inspection supervisor and water Process of reporting and problem solving conservation supervisor) Traffic safety Traffic rule (environmental manager, Safe dive training environmental Vehicle maintenance process 1/2 day supervisor and water Fuel filling process conservation Emergency response process supervisor) Water quality monitoring and analysis (environmental The use of the equipment comprises standards, testing, manager, methods, sample transport, data quality control monitoring and 1/2 day environmental reporting requirements supervisor and water conservation supervisor)

Training of Construction Workers Table 6.5-2 Mode Training content Training period Description for the environmental impact factors and environmental protection measures related to the environment Description for particularly sensitive area of environment and problem in the construction area, and introduction of nearby General area in the construction area environmental Roles and responsibilities of environmental management Half-day knowledge of classes in design engineers, environmental supervisor and construction construction each venue workers supervisor, and key points of environmental report Waste management of construction camp and construction site Pollution control measures of construction site Illegal provisions, and fines of laws and regulations Transmission and protection methods, prevention of HIV/AIDS General health and STD. Half-day knowledge of Alcohol and drug prohibition classes in construction Process for finding medical assistance in emergency and each venue workers non-emergency state, and process for finding other related medical aids. (For example, STD detection, and counseling) Health and safety knowledge comprises some basic processes as follows: traffic safety, electrical safety, explosion, fire, hazardous waste management Use of personal protective equipment Fines for the violation of laws and regulations

(3) Operators Training of Environmental Management Personnel of Operator Table 6.5-3 Objective Training content Training period Environmental Project management process of the World Bank management Environmental information file, open, communication, and One day of classes personnel reporting mechanism held in Cheng Emergency response of environmental risk County Health and safety inspection and application process Investigation of Advanced technology and environmental management advanced domestic study municipal engineering The use of the equipment comprises standards, testing, methods, sample transfer and data quality control and reporting requirements Two-day of classes Environmental Environmental emergency response: potential leaks and held in Cheng staff spills, impact of potential leaks and spills on environment County and human, wherein the emergency response process comprises priority response, the location and use of the response facilities

6.5.3 Budget of Personnel Training Funds The budget for the capacity building of the project is shown in Table 6.5-4. Training Plan of Environmental Protection Personnel of the Project Table 6.5-4 Stage Type Number (people) Time Cost (ten thousand Yuan)) Environmental manager 1 2011 2 training Project manager coordinator 6 Before 6 implemtning the project Construction Environmental supervision 3 Before 3 period engineer operation Water conservation 3 Before 3 supervision engineer operation Subtotal 14 Environmental 3 Before 6 management enterprise personnel training operation Operation Environmental risk 3 Before 3 period emergency enterprise response personnel operation Subtotal 9 Total cost 23

6.6 Land Acquisition Compensation and Resettlement Compensation (1) In accordance with the national and local policies and compensation methods of land acquisition and resettlement, the villagers involved in land acquisition and resettlement are provided with reasonable compensation, the project office should carefully listen the views of immigrants and ensure that the working and living conditions immigrants are not less than the current level. (2) For the staged construction of pipeline and road sub, the excavation and backfill work should be completed as soon as possible, the temporary access roads close to the schools and other public facilities should be particularly paid attention and are provided with traffic warning signs, traffic police should be in a rush to ease and dispatch so as to pedestrians and vehicle flow; and materials transport should be avoided from traffic peak, so as to reduce urban traffic pressure. (3) Strengthen the training of the management and construction personnel in the conservation education and awareness, due to the large amount of earth excavation work of the project, the work should be taken seriously; in case of the discovery of cultural relics, ancient tombs and other signs, it should be immediately notified to the local cultural relic protection departments and excavated in a timely, and the construction can be continued after treating the cultural relics by the cultural relics department well. (4) If the stronger vibration works (such as pier compaction, vibration roller operation and etc.) are carried out in residential areas, the old houses close to the construction site should be monitored to prevent accidents. For the houses greatly impacted by the vibration construction for ensuring the project should be provided with necessary remedial measures. 6.7 temporary Site Restoration The contractor has the obligation to implement ecological restoration of the temporary land where the construction is completed in the construction period of the project, and implement the restoration works of all the temporary lands before completing the project completely.

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

7. Environmental Monitoring Plan 7.1 Monitoring Purposes According to the characteristics for the impacts of Moba gorge water source engineering on the environment, the main environmental factors of the project construction area and the reservoir area before and after the project construction are monitored, the change conditions of the various environmental factors in the impact range of the project and the effects after implementing the environmental protection measures are grasped, so that the basis for finding environmental issues in time, providing the corresponding measures, reducing the adverse effects of the project, strengthening environmental management and project completion and acceptance.. In different stages, the focuses of environmental monitoring tasks are different. In the earlier stage of project construction and water storage, the main monitoring objectives mainly comprise the change conditions of the environmental factors caused by the construction activities, the change of the environmental factors caused by dam construction and water pipeline pavement; when the project is completed and put into water storage operation, the monitoring objectives mainly comprise the change conditions of the environmental factors around the reservoir caused by water storage, scheduling and operation period, and the ecological change in the water pipeline pavement area. 7.2 Environmental Monitoring Organization The environmental monitoring work in the construction period and operation period is responsible by the Hydrographic Office of Cheng County, the environmental monitoring station and the water conservation monitoring center according to the commission of the project contractor or the operator, wherein all the responsible units are national environmental quality monitoring units and are featured with complete equipment, thick technical force, so that these units can carry out the environmental monitoring tasks well. According to the environmental impact prediction results, the sensitive concerns with obvious pollution are used as monitoring points so as to track and monitor the pollution condition of construction period and operation period of the project, wherein the monitoring content comprises the noise with large impact on the environment, air environment and surface water environment. The monitoring factors are determined according to the characteristic factors of project pollution. The monitoring analysis methods are the monitoring analysis methods for the corresponding items in the ―Environmental Monitoring Technical Specifications" and the ―Water and Soil Conservation Monitoring Technical Regulations" which are issued by the national environmental protection administration. The detailed and key steps required by the construction site and activities required by effective monitoring are listed in Table 7.2-1. 7.3 Detailed Environmental Monitoring Requirements The detailed environmental monitoring plan of the project is shown in Table 7.3-1 to 7.3-4, and the cost budget table 7.3-5. Key points of Monitoring Plan of Construction Period and Operation Period Table 7.2-1 Plan Activities Responsibility Remark Implement Supervision Financing ation Construction period 1 year Compile onsite environmental management Constructi EMC/PIU/EPB Owner Develop a plan in one month after signing (January to plan on unit the contract, finally complete the plan in two months, and approve and permit by the February) EMC Provide project implementation boundary of EMC/PIU/EPB Construction Compile a map by the construction unit and each project area by the project construction Owner the operation unit before constructing the period unit and the operation unit, and permission project 1 year Compile a pollution control plan, air pollution Owner EMC/PIU/EPB Owner Consult with relevant agencies and (January to and noise Department of residents, and approve and permit by the M)arch Water Resources of EMC Gansu Province Construction Atmospheric, noise and water monitoring Specific Part period The pollution control plan and all the pollution EMC/PIU/EPB control measures provided by the EMP must be Daily visit the construction camps and Construction implemented, all the delay measures should be Constructi facilities by CSEE and inspect the EMC2 period carried out by the construction unit, and all the on unit monthly construction camps and facilities should be inspected weekly Construction The environmental protection measures of the Constructi EMC/PIU/EPB The proposal of CSE is the basis of final period construction unit should be reported by filling in on unit payment of PIU/PMO monthly reports According to the different processed and EMC/PIU/EPB Construction Constructi Level one: EMC; level two: EMC and PIU; serious levels, observe and report the period on unit level three: EMC, PIU, PMO inconsistencies of the project Construction Decide whether to postpone or refuse to pay Owner EMC/PIU/EPB period for projects construction units Construction Ensure that the land acquisition process can Owner POIU and period meet the needs of the construction plan immigration office Construction Declare daily, weekly and monthly Constructi EMC/PIU/EPB Onsite weekly, SRS monthly period on unit Construction Quarterly report Constructi PIU If it is required by the organizations of the period on unit relevant projects, it should be declared Construction Semi-annual declarations Constructi EMC/PIU/EPB If it is required by the organizations of the period on unit relevant projects, it should be declared Completion When the temporary land is recovered, all the Constructi EMC/PIU/EPB Owner of building materials and equipments will be on unit construction removed period Operation period Restore the temporary land when the Owner EPB/Department of construction is completed Water Resources of Gansu Province EPB/Depar tment of Standardization process and organization Sum up the experience of the project for the Water for the training of intermediary agency, similar project Resources demonstration for the results and benefits of of Gansu the project Province

Water and Soil Conservation Fixed-point Monitoring Plan Table 7.3-1 Monitoring Monitoring area Monitoring point Monitoring content Monitoring method Monitoring time frequency Residues place control area Residues place top of ① Change of water The residues piling slope erosion amount Erosion gully measuring method place is Residues place top ① Change of water Erosion gully measuring method monitored for Project erosion amount one time per construction Surface soil pilling yard ③ Surface soil erosion Erosion gully measuring method day, and the period and Hub building control area Slope excavation, and ① Change of water Erosion gully measuring method other areas are natural temporary mound erosion amount monitored for recovery ② Erosion amount of Erosion gully measuring method one time per period temporary soil field 30 days, and Quarry control area Slope excavation ① Change of water Erosion gully measuring method the time will be erosion amount increased by Surface soil pilling yard ② Surface soil erosion Erosion gully measuring method one in case of Construction road control area Road excavation and ① Change of water Survey monitoring method and the rainfall of backfill surface erosion amount erosion gully measuring method 24 h is not less and etc. than 50 mm. Temporary residues ① Change of water Erosion gully measuring method erosion amount Water pipeline control area Road excavation and ① Change of water Survey monitoring method and backfill surface erosion amount erosion gully measuring method and etc. Temporary residues ① Change of water Erosion gully measuring method erosion amount Construction enterprises and Perturbation surface of ① Change of water Survey monitoring method and office and living control area the construction area in erosion amount erosion gully measuring method the site and etc.

Survey Monitoring Plan of Water and Soil Conservation Table 7.3-2 Monitoring Monitoring Monitoring content Monitoring method Monitoring frequency time area Before the Range of ① Characteristics of water loss and soil erosion impact factor, Remote sensing, census Survey the background constructio control quantity, quality and protective effect of soil and water survey method combined with value before the n responsibility conservation facilities, and status of water loss and soil erosion plots construction preparation preparatio and etc. period n period

② Background value of water loss and soil erosion Constructi Project on of Construction preparatio area n and ① Change of topography and vegetation of the construction constructio area, and number of damaged water loss and soil erosion Remote monitoring, inspection Inspection at any time after n period conservation facilities method starting ② Number of dug and filled earth and stone, amount of spoil 1 time in the construction Combination of the census and residues, location, land area, area of perturbation surface, period and the end, method and inspection area and degree of damaged vegetation respectively ③ Number and effect of project control measures implemented Screening method, inspection 1 time in the construction method period and the end, respectively ④ Hazards of water loss and soil erosion Combination of a sample 1 time in the construction survey and access period and the end, respectively Reservoir inundation ① Unstable slope and landslide and the like in the reservoir Combination of a sample 1 time in the construction area bank survey and access period ② Hazards of water loss and soil erosion Inspection method 1 time in the construction period and the end, respectively Natural Project ① Regional change condition of water erosion Census and sample survey 1 time before, during and recovery Construction method after the flood, respectively area ② Grass growth, survival rate, coverage and anti-erosion Quadrat survey 1 time before, during and effects and etc. after the flood, respectively ③ Number and effects of control measures implemented, the area of water loss and soil erosion, reduction for the amount of Sample survey 1 time before, during and water loss and soil erosion after the flood, respectively ① Unstable slope and landslide and the like in the reservoir Reservoir bank Survey method, sampling 1 time before, during and inundation area after the flood, respectively ② Hazards of water loss and soil erosion Survey method, sampling 1 time before, during and

after the flood, respectively

List for Environmental Monitoring Plan of Construction Period Table 7.3-3 Na Monitoring Monitoring point Monitoring frequency Monitoring item me content Wat Set a section on the er place apart from the qua Water quality upstream of the change Temperature, pH, dissolved lity intersection of the When the construction condition of the is began, the annual oxygen, chemical oxygen mo river and Erlang construction abundance, flat and demand, 8005, total nitrogen, nito site upstream River with 500 m, dry season will be total phosphorus, suspended ring and set a section in the monitored for one solids, ammonia nitrogen, downstream reservoir area, set a time, and the copper, zinc, arsenic, mercury, the river, section in the monitoring is cadmium, chromium pollution downstream point appropriately (hexavalent), lead, fluoride, increased for 1 to 2 condition of apart from the cyanide, volatile phenol, construction to times in the peak petroleum, anion surfactant and reservoir area with the water construction period sulfide and fecal coliform quality 100 m, and there are four monitoring sections totally. Atm When the construction osp is began, monitoring heri for one time per six c months, the Construction mo successive sampling and nito time of each time is 3 transportation Construction area SO2, TSP and NOx ring days, and sampling at impact on the 07:00, 12:00 and atmosphere 18:00; the monitoring will be appropriately increased in the peak construction period Noi In the construction se period, quarterly mo monitoring for one Noise time, the monitoring nito generated by Set a monitoring will be appropriately ring the point on the outer increased in the peak construction boundary of 1 m to construction period, Equivalent A sound level Leq machinery, the active the successive blasting and construction site sampling time of each transportation time is 3 days, and respectively sampling at daytime and nighttime for one time Ter Vegetation Processes involved Vegetation type, dominant rest type, dominant One time before and grass and woodland species, grass base height, rial species, grass after the construction area vegetation cover and etc. biol base height, ogic vegetation al cover and etc. mo nito ring Aqu Set two monitoring atic points on the biol Monitoring of upstream point Monitoring the species and ogic plankton, apart from the dam One time before and number of the plankton, al benthos and with 100 m, and the after the construction benthos, and indigenous fish mo indigenous fish downstream point nito apart from the dam ring with 300 m Hu man Construction camp heal Construction camp health, sanitation and th Construction camps Monthly physical health of construction health of mo workers construction nito workers ring

List for Environmental Monitoring Plan of Operation Period Table 7.3-4 Na Monitoring Monitoring point Monitoring Monitoring item me content frequency Wa Water quality Set monitoring Monitor the Temperature, pH, dissolved oxygen, ter monitoring of sections in the reservoir area for chemical oxygen demand, BOD5, total qua reservoir area reservoir area one time per nitrogen, total phosphorus, suspended and and the day, and monitor solids, ammonia nitrogen, copper, zinc, lity downstream downstream downstream arsenic, mercury, cadmium, chromium mo the reservoir point apart from reservoir for one (hexavalent), lead, fluoride, cyanide, nito area in the reservoir time in volatile phenol, petroleum, anion ring operation area with 100m abundance, dry surfactant and sulfide and fecal coliform period and flat-water period, respectively Aq Monitoring of Set two Every three Monitoring of plankton, benthic species uati plankton, monitoring points years is a cycle, and biomass changes, proliferation of c benthos and on the upstream there are five fish germplasm resources exchange point apart from monitoring biol indigenous changes, and indigenous fish growth, the dam with 100 cycles, and the ogi fish reproduction m, and the aquatic cal downstream organisms are mo point apart from monitored for nito the dam with 300 one time of each ring m quarter, per cycle Dis Discharge Downstream the Monthly Placement of water gauge card, monitor cha flow of outlet dam of 100 mm dam leakage of water meets the rge entrance of minimum ecological water mo the dam nito ring

Monitoring Investment Budget Table Table 7.3-5 Item Cost Remark Water quality monitoring Construction period Operation period 137000 Yuan 10300 Yuan/year

Atmospheric 216000 Yuan Construction period monitoring Noise monitoring 54000 Yuan Construction period Terrestrial biological 120000 Yuan Construction period monitoring Aquatic biological monitoring Construction period Operation period 100000 Yuan 60000 Yuan/3 years

Human health 64000 Yuan Construction period monitoring Water conservation 589100 Yuan Construction period monitoring Discharge monitoring 5000 Yuan/year Operation period

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

8. Acceptance Investigation Content of Environmental Protection Measures 8.1 Investigation of Water Environmental Protection Measures Investigate bottom cleaning condition of the reservoir, acceptance and conclusion. Investigate the water environmental protection measures for the domestic wastewater of operation period, effects and the corresponding investment by means of data collection, field survey and other methods while combining with the data provided by completion and acceptance monitoring. Focus on the investigation of wastewater treatment facilities and treatment processes, treatment capability and effects, and discharge direction and the like in the construction site of operation period, and the investment of all the facilities and operation cost and etc. 8.2 Investigation of Atmospheric Environmental Protection Measures Investigate the prevention, protection or management measures taken for reducing the impacts of dust, exhaust gas of construction machinery and tail has of transport vehicles and the like on the onsite construction workers. 8.3 Investigation of Acoustic Environmental Protection Measures Investigate the implementation condition and implementation effect of acoustic environmental protection measures by visiting the construction workers and checking data and other methods. The investigation content mainly comprises: whether the construction equipment is the mechanical equipment required by environmental protection, whether the noise management of construction period is strengthened, implementation of noise abatement measures for the high-noise machinery, and the prevention for the night work of high-noise construction equipment, whether the maintenance of the high-noise construction equipment is strengthened so as to ensure the normal operation, reduce the noise generated by means of abnormal operation of the equipment, whether the vehicle management is strengthened, and the vehicle noise is controlled and etc. 8.4 Investigation of Solid Waste Treatment Measures Investigate the location, size and capacity of waste soil and stone disposal place, and the implementation conditions for the project and measures which are taken after the treatment of the residues place. Investigate the amount of the residues place and the operation conditions. 8.5 Investigation of Ecological Protection Measures 8.5.1 Investigation of Terrestrial Ecological Protection Measures Mainly investigate the restoration condition of the temporary land, and the greening project condition taken on the living management area of the reservoir and etc. 8.5.2 Investigation of Aquatic Ecological Protection Measures Investigate the implementation condition for the safeguard measures of discharge ecological base flow, and whether the young fishes put according to the requirements. 8.6 Investigation of Water Loss and Soil Erosion Control 8.5.1.1 Water Loss and Soil Erosion Control Measures of Construction Period Investigate the condition of soil and stone transportation of the project in the construction period, the land position and the actual use condition of the residues place and protection conditions thereof, mainly comprising the amount of the residues place, the actual residues amount and the utilization ratio; the actual land area of planned residues place, the amount of residues and the stacking height; the construction condition of the residues place wall, the length and height of the wall, and the configuration conditions of surrounding drainage ditches and other draining facilities. Investigate the mining situation of the stock ground, the type of the original land, ecological restoration measures taken and restoration effects, and the setting conditions for the slope drainage ditches of the temporary roads and the quarry. 8.5.1.2 Investigation for Soil and Water Conservation Measures after Construction Investigate the restoration condition of temporary construction area when the construction is ended, investigate the land use type of the temporary construction road, two sides of the new road, exposed land caused by the damage of the vegetation within the temporary construction area, the temporary living and office area and the residues place and other slashes after restoring, the greening area and greening rate and etc. Mainly investigate whether the project measures and vegetation restoring measures of each project have been implemented according to the requirements of environment impact assessment and project design. Investigate the water and soil conversation protection condition after taking project, plant and management measures. 8.7 Investigation of Population Health Impact and Protection Measures Investigate the implementation conditions of environmental health management and epidemic disposal and others in the construction site of construction period. Investigate and understand the environmental health conditions of project construction area and reservoir area, comprising medical institutions setting, medical equipment configuration, file and regular inspection of health data of the construction workers and etc; the infectious diseases comprises main disease type, number of cases, infected, and epidemic control situation; drinking water purification and disinfection conditions; and other conditions of population health protective measures. According to the investigation results and the combination for the requirements of environment impact assessment, the implementation conditions of population health protection measures can be judges, the population health conditions in the construction period can be evaluated, so that the effect for the series of measures taken for protecting the population health can be analyzed. Investigate and understand the environmental health conditions of reservoir area in the operation period, and the conditions of other population health protection measures taken. 8.8 Investigation for Environmental Protection Measures of Resettlement Area Investigate the relocation and resettlement areas and resettlement areas of production distribution, environmental profile; population resettlement, resettlement method and resettlement profile; and whether the resettlement compensation is implemented actually and etc. 8.9 Investigation of Risk Prevention Measures Investigate the environmental risk factors presented in the construction period and the operation period of the project, whether there is a risk incident; investigate the situation, reason and caused environment impacts of environmental risk accident in the construction period and operation period; investigate the environment risk prevention measures of the project and the compilation condition of the emergency response plan, the implementation conditions of national, local and related industries in the accident prevention and emergency response, the necessary emergency facilities and training conditions of emergency response team; and investigate the environment risk prevention measures of the project and the setting conditions of emergency management agencies. 8.10 "Three Meantime" of Project Acceptance The water source engineering construction management department of Moba gorge for city water supply of Cheng County should timely provide completion acceptance application of environmental protection facilities to the environmental protection department according to the relevant requirements in the ―Completion Acceptance Management Regulations for Environmental Protection Facilities of Construction Project‖, so as to implement acceptance. The list for the completion acceptance of environmental protection facilities is shown in Table 8.9-1. List for "Three Meantime" Acceptance of Environmental Protection Facilities Table 8.9-1 Item Content Measures Acceptance standard Wastewater Treat the domestic The first level of wastewater by means "Integrated Domestic wastewater of WSZ buried Wastewater Discharge wastewater treatment Standard" equipment (GB8978-1996) Divide drinking water Reservoir water source protection areas quality meets the according to the standards of Class III requirements of the in the "Surface Water ―Regulations for Water source protection Environmental Quality Pollution of Prevention Standard" and the Control and threshold value of the Management of water source Drinking Water Source supplementary items Protection Area‖ Compile an ―Environmental

Protection Plan of

Drinking Water Source of Cheng County‖ Set 2 garbage barrels Proper disposal of Solid waste Household waste in the management household waste station Water loss and soil Implement land Project provided by Site regulation erosion formation on the stock water conservation yard, the construction program camps, the construction access road and the water pipeline when the construction is completed Protect the slope of the

Slope protection work stock yard and the

residues place Set drainage facilities in dam management Drainage work station, dam road and construction stock yard Green the dam management station, stock yard, construction camp, construction access roads, water Greening measures pipeline and two sides of the roadbed of the dam road when the construction is completed Place immigration Resettlement and properly, and Resettlement plan and ecological compensate flooded land compensation compensation farmland and forest plan land Pavement of the water pipeline should be hidden Prevent the damage of by the terrain as far as Landscape protection the landscape caused possible and should be by the water pipeline prevented from the residential area Release 2000 Jialing Release young fish in Schizopygopsis Tajiri Aquatic organism Young fish releasing April to June for every Schizothorax fish three years species with the size of 3 to 4 cm Set permanent outlet The discharge amount Discharge amount Ecological water discharge entrance on the dam is 0.138m3/s Environmental Normal operation monitoring and management

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

9. Environmental Management Cost Budget and Capital Source 9.1 Budget Distribution The implementation of EMP measures involves to many units, so that the capital sources are different. Most of environmental protection activities are project measures, and thereof the activities should be provided by the project construction unit and the operation unit and involved in project cost, wherein these costs will be cleared and listed in the tender of competitive bidding. The cost of EMP is mainly applied to the environmental management of the construction period and the operation period, and mainly comprises environmental monitoring cost, environmental supervision cost, training cost and the environmental management agency operation cost, and part of project further has risk prevention cost. The activities of EMC will be covered with the PMO and PIUS international project management costs, the monitoring of water quality, atmosphere and noise, the CSEE and EFSI are the same. The monitoring and surveillance activities of CSEE are part of the construction and supervision costs. The local environmental monitoring station will monitor water, atmosphere and noise in the operation process of the project according to the commission of the project owner, and the monitoring cost thereof will be paid by the project owner. If the normal monitoring of the local environmental protection department is synchronous with the project, the normal monitoring data of the environmental protection department can be used. 9.2 Capital Source and EMP Budget

Investments for various environmental protection measures proposed in the evaluation report are estimated as 15.2673 million RMB, which takes 6.74% of total investment cost. Please see table 9.2-1 for details.

Table 9.2-1 Environmental Protection Investment

Variety of Name of Content of Investment cost Expected effect measure measure measure (10,000RMB) Disposed by Relieve the Disposal for t6he toilet pit of influence on domestic each environment 6.54 sewage from construction caused by waste constructors Pollutant control site. water. during Relieve the Waste water influence on construction Add flocculating from the environment 40.2 agent. foundation pit caused by waste water. Waste water Oil separation Relieve the 5.32 containing oil tank influence on environment caused by waste water. Relieve the Waste water for influence on Sedimentation sand stone environment 25.89 tank materials caused by waste water. Sedimentation Relieve the tank and the influence on Alkaline waste agent for environment 6.37 water adjusting pH caused by waste value water. Relieve dust Watering Water raise in construction construction 8.1 construction area area. site. Relieve the influence on the Arrange 28 trash Household environment cans and waste from caused by 10.8 transport the constructor household waste in time. waste during construction. Relieve dust Barrier facilities Barrier facilities raise and noise around the are arranged influence 5 construction site around the site. caused by construction. Relieve the influence for the Preventive Mask, earplug constructor measures for 4 and so on caused by constructor construction process. Disinfect the construction area, implement Protect body Protection of deratization and health of 23.61 human health eradicate constructor. mosquito and fly. Standard LI Adopt WSZ (GB8979-1996) buried sewage of disposal Domestic Comprehensive equipment to 15.0 sewage Sewage dispose Discharge domestic Standard sewage.

Waste water Divide protection The water control zone for drinking quality in the water source reservoir area Protection of according to the reaches the III water source requirements of standard of 50.0 area ―Administrative ―Environmental

Regulations for Quality Standard Preventing of Surface Pollution of Water‖ Drinking Water (GB3838-2002) Source and the Protection boundary value Zone‖. of Compile supplementary ―Environmental items. Protection Plan for Cheng County Drinking Water Source Area‖. Arrange two trash cans for Properly dispose Household Household the household 0.04 waste wastes management wastes. station. After soil and water conservation scheme is implemented, by the final period of construction, treatment rate of disturbed land reaches 98.67%; treating Engineering degree for water Prevent and measures, loss and soil control the planting erosion reaches Soil and water region in which measures and 98.07% and slag 1118.67 conservation water loss and temporary blocking rate soil erosion engineering reaches 100%; occur. measures control rate for water loss and soil erosion reaches 1.03; vegetation recovery coefficient reaches 98.76% and coverage area of forest and grasses reaches 41.3%. Every 3 years is Schizopygopsis a releasing kialingensis and period and 2000 Schizothorax Schizopygopsis davidi which are kialingensis and bought and bred Schizothorax 10 Ecological via manual davidi in the protection domestication specification of are released to 3-4cm are breed. released every time.

Set ecological Warning signs 0.9 protection signs Water quality 137 monitoring Environmental 216.6 air monitoring Work normally Noise Environmental 5.4 monitoring monitoring Human health 6.4 monitoring Ecological survey and 22 monitoring Other charge 127.17 Total 1526.73

Within the above budget, the summary for the management cost of construction period of the project is shown in Table 9.2-2.

Budget Summary for Environmental Management Cost of the Project in Construction Period Table 9.2-2 No. Cots name Total cost of construction period of the project (10,000RMB) 1 EMD operation Salary 22.5 Office expense 9 Travelling expense 5.63 2 Environment monitoring cost 69.10 3 Environmental supervision cost 21.6 4 Personnel environmental protection training 23 5 Water and soil conservation monitoring cost 58.91 6 Water and soil conservation supervision cost 39.20 7 Total 248.94

10. Information Management of Environmental Management Plan 10.1 Environmental Management Plan 10.101 Environmental Management System Provincial level: Department of Water Resources of Gansu Province, Environmental Protection Department of Gansu Province, the World Bank City level: water conservancy bureau of Longnan City, environmental protection bureau of Longnan City, Loan Project Office of the World Bank in Longnan City County level: environmental protection bureau of Cheng County, Water Authority of Cheng County Owners Enterprise level: environmental monitoring station of Cheng County, environment impact assessment unit, design unit, construction contractor, environmental supervision engineers, environmental monitoring station of Cheng County, owners Figure 10.1-1 Chart of Environmental Management System

Organizational Chart of Environmental Management System Table 10.1-1 Organizational Organizational name Organizational task properties Management Project management office of Project management organization organization Longnan City Environmental management Project environmental management organization office of Longnan City Supervision Supervision and inspection the implementation of organization the World Bank environmental management plan Department of Environmental Government administrative supervision and Protection of Gansu Province, management organization Environmental Protection Agency of Longnan City, and Environmental Protection Agency of Cheng County Implementatio Contractor Implement the environmental protection measures n organization of construction period Consultation Implement environmental review, consultation and organization technical support according to the commission of Experts Group on the the project environmental management Environment organization Environmental supervisor Manage the environmental supervision of the contractor according to the commission of the project environmental management organization Project supervisor Sign and issue formal letters between the environmental supervisor and the contractor Environmental monitoring Undertake professional environmental monitoring organization task according to the commission of the project environmental management organization 10.1.2 Environmental Management Task of Each Stage of the Project (1) Feasibility study stage The main environmental management task of the feasibility study stage is environmental assessment of construction project, and mainly comprises the compilation of environmental assessment report and environmental management plan. (2) Design stage The main environmental management task of the project design stage comprises: inspecting the final design report of the project, ensuring the various environmental protection measures (environmental protection measures of project design, environmental protection measures of construction period, and environmental protection measures of operation period) proposed by the EA and included in the final design of the project. (3) Bidding stage The main environmental management task of the bidding stage of the project comprises: ensuring the environmental protection measures of construction period provided by the EA are included in the construction contract of the project. (4) Construction stage The main environmental management task of the bidding stage of the construction stage comprises: implementing the environmental protection measures of construction period provided by the EA and the monitoring plan of construction stage. The environmental protection measures of construction period are specifically implemented by the contractor, and the environmental supervisor is responsible for supervising and managing the onsite construction activities of the contractor. (4) Operational stage The main environmental management task of the operational stage comprises: implementing the environmental protection measures of construction period provided by the EA and the monitoring plan of operational stage. 10.2 Information Exchange Environmental management requirements necessary information exchange among the different departments and positions of the project office, the owner, the contractor and the operator of the organization, and simultaneously notices the relevant information to the outside (the relevant parties and social publics and etc.). The internal information exchange can be carried out in the form of meetings and internal briefings and other method, but there must be a formal monthly meeting, all the information exchanged should be recorded and archived. External information exchange is carried out for every six months or one year, and the information exchanged with the coordination unit should be formed into a summary and archived. 10.3 Recording Mechanism For the effective operation of environmental management system, a comprehensive recording system must be established, and the following contents should be recorded: (1) Legal and regulatory requirements; (2) Licensing; (3) Environmental factors and related environmental impacts; (4) Training; (5) Inspection, check and maintenance activities; (6) Monitoring data; (7) Effectiveness of corrective and preventive measures; (8) Information of related party; (9) Audit; (10) Review. In addition, the records of the various types above must also be necessary in controlling, and the records comprise identification, collection, cataloging, archiving, storage, management, maintenance, inquiry, retention period, disposal and other sectors. 10.4 Reporting Mechanism The contractors, operators, monitoring unit, environmental supervision engineers and project office should record the project progress, the EMP implementation conditions and the environmental monitoring results and the like in the project construction process, and report the information to the relevant department in time. The record mainly comprises the following six parts: (1) The project environment supervision engineers should monthly and detailedly record the implementation condition of the EMP in the month, timely provide the weekly and monthly to the project owners and project office of Cheng County, wherein the weekly and monthly reports should include the implementation of environmental protection measures, as well as implementation condition of environmental monitoring and monitoring data. (2) The contractor and operator should quarterly and detailedly record the project progress and the implementation condition of the EMP, timely submit the quarterly report to the project office, and simultaneously copy the quarterly report to the Environmental Protection Agency of Cheng County. (3) The monitoring unit should timely submit monitoring report to the contractor (carrier) and the environmental supervision engineer when the monitoring task is completed; (4) The project office of Cheng County should timely submit the project progress report of the project office of Longnan City, and copy the report to the Environmental Protection Bureau of Longnan City. The project progress report (such as monthly, quarterly, annual reports and etc.) prepared by the project office must comprises the content of EMP progress, e.g. the implementation progress and implementation effect of the EMP, particularly the environmental monitoring results and etc.; (5) In case of the special violation of environmental protection matter, environmental supervision engineer and the project office will inform the matter to the local environmental protection administration department, and report to the superior, if necessary. (6) The EMP implementation report of the project should be completed and submitted to the World Bank before March 31, and the EMP implementation report can comprise the following main contents: ① Implementation of training plan; ② Progress of projects, such as the diversion tunnel and road works on the dam, main project of the dam, water pipeline construction progress and etc.; ③ Implementation of project environmental measures, implementation condition of environmental monitoring and main monitoring results; ④ Public complaints, if there is a complaint, the main content of the complaint, the solution and the public satisfaction should be recorded; ⑤ EMP implementation plan of the next year.

Environmental Management Plan for Cheng County Moba Gorge Water Source Engineering of Gansu Province

Appendix Appendix 1 Project Involves Environmental Standards “Environmental Quality Standards for Surface Water” (GB3838-2002) Appendix 1 No. Project name Standard value Grade (mg/L) 1 p H ( non-dimensional) 6-9 2 COD <= 20 3 NH3-N <= 1.0 4 Total nitrogen <= 1.0 5 Zinc <= 1.0 6 Selenium <= 0.01 7 Mercury <= 0.0001 8 Lead <= 0.05 9 Cyanide <= 0.2 10 Petroleum <= 0.05 11 Sulphide <= 0.2 >= Standard of 12 Dissolved oxygen 3 Class III

13 BOD5 <= 4

14 Total phosphorus <= 0.2 15 Copper <= 1.0 16 Fluoride <= 1.0 17 Arsenic <= 0.05 18 Cadmium <= 0.005 19 Chromium (hexavalent) <= 0.05 20 Volatile phenol <= 0.005 21 Anionic surfactant <= 0.2 22 Dung escherichia coli (Pcs/L)) <= 10000 23 Potassium permanganate index <= 6 24 Water temperature (DEG C)

Threshold Value for Supplementary Item of Water Source Appendix 1-2 No. Item name Maximum allowable concentration (mg/L) 1 Sulphate (by SO42-) 250 2 Chloride (by Cl-) 250 3 Nitrate (by N) 10 4 Iron 0.3 5 Manganese 0.1

“Ambient Air Quality Standard” (GB3095-1996) Appendix 1-3 No. Item Pollutant concentration limit (mg/m3) Grade Hourly average Daily average

1 PM10 / 0.15 Secondary 2 NO2 0.24 0.12 standard 3 CO 10.00 4.00

4 SO2 0.5 0.15

"Sound Environmental Quality Atandards" (GB3096-2008) Appendix 1-4 Type Daytime dB (A) Nighttime dB (A) Class II 60 50

"Environmental Quality Standard for Soils” (GB15618-1995) Appendix 1-5 No. Item name Maximum allowable Grade concentration 1 Copper 35 2 Cadmium 0.20 3 Lead 35 4 Zinc 100 5 Mercury 0.15 Primary standard 6 Hexavalent chromium Lack of standard 7 Arsenic 15 8 Total chrome 90 9 sulphide Lack of standard Note: As the river sediment is no uniform standards currently, the environment impact assessment of the project is carried out by means of the "Environmental Quality Standards for Soil" (GB15618-1995).

“Integrated Draining Standard of Sewage” (Gb8978-1996) Appendix 1-6 No. Item name Unit Maximum allowable Grade concentration 1 pH value 6.0-9.0 2 Suspended matter mg/L 70

3 BOD5 mg/L 30 Primary standard 4 CODcr mg/L 100 5 Ammonia nitrogen mg/L 15

"Atmospheric Pollution Material Integrated Emission Standard" (GB16297-1996) Appendix 1-7 Item name Unit Controlled concentration limit Grade Particle mg/m3 The highest concentration of outer Fugitive emission concentration is 1.0

“Noise Limits for Construction Site” (GB12523-90) Appendix 1-8 Construction Main noise source period Noise limit (dB) Daytime Nighttime

Soil and stone Bulldozers, loader and excavator and etc. 75 55 Piling Various hammers and etc. 85 Prohibit construction Structure Concrete mixer, vibrating rod and electric saw 70 55 and etc. Fitment Crane and lift and etc. 65 55

“Sanitary Standard for Drinking Water” (GB5749-2006) Appendix 1-9 Index Unit Limit value 1. Microbiological index Total coliform MPN/100 ml Negative Thermotolerant MPN/100 ml Negative coliform 2. Toxicological index Arsenic mg/L 0.01 Cadmium mg/L 0.005 Chromium mg/L 0.05 (hexavalent) Lead mg/L 0.01

Mercury mg/L 0.001

3. Sensory properties and general Chromaticity Platinum cobalt 15 chemical index chromaticity Turbidity NTU 1

Smell and taste PH Without abnormal odor and peculiar smell PH Not less than 6.5 and not more than 8.5 Aluminium mg/L 0.2

zinc mg/L 1.0

4. Radioactive indexes Total alpha activity Bq/L 0.5 Total beta activity Bq/L 1

Note: the radioactive indexes are guide values

Appendix 2 Detailed Project Environmental Management Standards of Contractor In construction period, environmental protection is the responsibility of the contractor. The article 19.1 of the soil mold engineering evaluation Contract of the International Federation of Consulting Engineers (FIDIC) states that ―in the whole process of construction, completion and repair other defects, the contractor should take all reasonable steps to protect the site and its vicinity environment, so as to avoid the pollution, noise or other results caused by construction and prevent the injury or prejudice on human and property and other aspects.‖ 1. Control measures of air environmental pollution ① Implement civilized construction during the construction period, develop the measures for preventing dust pollution according to the construction plan, for example, adding baffles, watering and timely removing earthwork, wherein the transport vehicles should be covered with a canvas before leaving from the site to the road, meanwhile the material should be prevented from loading/unloading in wind as much as possible. ② For powdery materials, they are piled up intensively and provided with covering and sheltering measures to reduce the production of dust. ③ Regularly inspection the working site, subject the sensitive point to TSP monitoring, and reform the overweight phenomenon in a given time. ④ For the construction which is in violation to the provisions or the problem did not be reformed in time, administrative and financial penalties should be taken. 2. Control measures of water environmental pollution ① Production and living wastewater is strictly prohibited from discharging without treating, the construction site should be provided with a wastewater collecting and depositing tank, and the wastewater is used for watering to reduce the dust or used for concrete mixing and the like after treating simply. ② The management of the construction site should be strengthened to prevent earthwork and construction materials and the like from entering into the water close to the piling place. 3. Control measures of noise environmental pollution ① Replace behind high-noise construction process with advanced low-noise construction process. ② The speed of the bulldozers, excavators, loading and unloading vehicles should be limited will accessing the site, and the maintenance of the mechanical equipment and transport vehicles should be strengthened. ③ Reasonably arrange the schedule and construction time, and avoid the continuing impact of strong-noise operating machinery on the surrounding residents. ④ Operate the equipment according to the provision, and minimize the impact noise. ⑤ When the construction site through schools, residential and other sensitive points, the temporary noise barriers (walls) should be set, if necessary. ⑥ Regularly monitor the noise level of the sensitive point, and provide control measures to the excessive points. 4. Control measures of ecological environmental pollution ① For the land and forest and the like must be occupied in the construction process, the land acquisition must be completed before starting the project and must be in line with relevant domestic regulations and the security policy OP4.12 of the World Bank and the requirements of 4.20. ② For the temporary land occupation of construction, the mellow soil of cultivating in the original land surface should be stacked aside and leveled when the construction is completed, so as to restore the land surface. ③ Strengthen the education of the construction worker, promote civil construction, and protect the wildlife in the construction area. 5. Control measures of solid waste pollution ① The construction waste and residues should be uniformly treated according to the provisions of the relevant local department, the household waste will be subjected to landfill in the designated landfill of the sanitation department. ② The solid waste and waste oil and the like generated in the construction site should be intensively stacked in the designated place. When the construction is completed, the solid wastes are sent to a refuse landfill to subject to landfill, and for the waste oil, the leaked oil of construction machinery and the like will be collected by means of onsite leakage collection method. ③ The construction waste and abandoned soil should be promptly disposed so as to reduce the time for piling in the construction site. 6. Social environment safeguard measures ① According to the policies of land acquisition and resettlement and the compensation methods of Chinese government and the region, the villagers involved in land acquired will be provided with a reasonable compensation, and the suggestion of the villagers will be listened carefully. ② Implement staged construction of the pipeline, so as to complete the excavation and backfill work as soon as possible. 7. Environmental monitoring measures Compliance with environmental monitoring plan of the project, and commission the environmental monitoring station of Cheng County and the qualified soil and water conservation monitoring unit to monitor the major environmental impacts, the conditions of surrounding environmental quality and the soil and water conservation situation in the construction period according to the frequency and point distribution requirements of the monitoring plan. Detailedly record the results for the implementation of environmental monitoring and monitoring report, and involve that into monthly and quarterly reports, timely submit the reports to the local project office, and copy the records to the local Environmental Protection Agency. 8. Environmental supervision and water conservation supervision measures The environmental supervision and water conservation supervision work should run through the entire process of construction, so as to ensure the smooth development of environmental protection work in the construction period of the project and ensure the effective implementation of environmental protection measures and soil and water conservation measures. In order to ensure that the environmental protection measures and the soil and water conservation measures are completed according to the plan, and the quality of the environmental project is ensured, the supervisor should be entrusted by the owner and should have environmental project supervision qualification and water and soil conservation supervision qualification; due to the stage and period implementation characteristics of the project, three full-time supervisors and water conservation supervisors are primarily considered, the establishment of other environmental management personnel can be the staff of other departments in part-time according to the requirements, and the number of the worker is determined according to the requirements. 8.1 Working method of environmental supervisor and water conservation supervisor ① Environmental supervision and water conservation supervision are involved in the range of project supervision and are uniformly managed by the supervision management department of the construction headquarters. The environmental supervisor and water conservation supervisor will participate in monthly meeting of engineering director, and submit weekly and monthly and the like contents to the chief inspector office. ② Regularly convene environmental supervision and water conservation supervision conferences, solve the existing problems by combining with the recent environmental supervision and water conservation supervision work, and provide the working plan of the next stage. ③ The sub-departments of environmental supervision and water conservation supervision will regularly convene environment supervision meetings monthly. ④ Form a complete onsite environmental protection management system, establish an environmental protection lead group in each participation project department, wherein the group is responsible for the environmental protection and lead work of the project department, the organization is extended to the construction team and group, the responsibility area is divided, and the person in charge is determined. 8.2 Content of environmental supervision and water conservation supervision work ① Environmental supervision of project preparation period: Review the environmental protection articles in the "Construction Organization Plan" compiled by the construction unit, inspect whether the environmental protection system established by the construction unit is reasonable, participate, approve and submit the application of ―Unit Project Start Report‖, and implement project supervision for the construction of pollutant treatment project, and supervise the implementation. ② Environmental supervision and water conservation supervision of construction period: Design and compile "Environmental Protection Focus" according to the construction organization of each section, and propagandize environmental protection work to the construction unit, point out environmental pollution sensitive point for the construction unit, provide special environmental protection measures according to the main pollutant in the construction process, check the ―Environmental Protection Plan of Project Construction‖ provided by the construction unit, inspect whether the operation of environmental protection system of the construction unit is normal, and inspect the implementation condition of the environmental protection measures and etc., and supervise the construction of water and soil conservation measures. Supervise the implementation of environmental monitoring plan, and supervise the monitoring result. ③ Environment supervision and water conservation supervision of project operation period: Review the ―Summary Report of Environmental Protection Work of Project Construction‖ developed and reported by the construction unit, file environmental protection completed document and environmental protection acceptance inspection of the project item, and compile ―Environmental Supervision Summary Report" and ―Summary Report of Water Conservation Supervision Work‖ and etc. 8.3 Responsibilities of environmental supervision and water conservation supervision ① Supervisors should strictly carry out supervisory responsibilities, effectively play the role of the supervision and management, so as to effectively implement the environmental protection measures and soil and water conservation measures to be taken on the site, and ensure the effective implementation of environmental protection work. ② Implement the propagandizing and implementation work of environmental protection and soil and water conservation laws and regulations, improve the environmental protection consciousness of the whole personnel participating in the construction to consciously participate in and implement the environmental protection work well. ③ Develop staged environmental supervision and water conservation supervision plan, subject the completion of unit project to environmental supervision and water conservation supervision acceptance, and ensure the complete process of environmental protection and complete data when the project is completed. ④ Sign environmental protection contract in the agreement in relation to the construction project without bidding, review the content of environmental protection in the construction organization design, add environmental protection sections with detailed contents in the construction organization design. ⑤ Detailedly record the implementation of EMP of the project, compile weekly and monthly reports, and timely submit the reports to the local project office and the environmental protection agency.

Appendix 3 Detailed Project Environmental Management Standards of Project Operation Department The environmental management of operation period mainly comprises the following aspects: I. Management measures of operation technology ① Establish an operation management and operation responsibility system of treatment facilities; ② Train the management personnel and the operator, establish technical assessment files, and prohibit unqualified staff; ③ Hire an experienced professional and technical personnel who is responsible for technical management; ④ Strengthen the maintenance and management of equipment and facilities, wherein the key equipment should be provided with a standby machine; ⑤ Regularly visit the residents nearby the project, listen the suggestions, inform the relevant environmental information, and coordinate the relationship with nearby residents II. Environmental monitoring measures Comply with project environmental monitoring plan, and commission the environmental monitoring station of Cheng County and the qualified soil and water conservation monitoring unit to monitor the major environmental impacts, the conditions of surrounding environmental quality and the soil and water conservation situation in the construction period according to the frequency and point distribution requirements of the monitoring plan. Detailedly record the results for the implementation of environmental monitoring and monitoring report, and involve that into monthly and quarterly reports, timely submit the reports to the local project office, and copy the records to the local Environmental Protection Agency.

Appendix 4 Summary of Project Environmental Management Plan and Environmental Action Plan of Construction Period List for Environmental Management Plan of Construction Period Table 4-1 Task Schedule Imple Super Capita Item Content of Mitigation measures taken by menta vision l environmental the project tion organi source management organi zation zation

Water Aggregate Treat the wastewater with Completed ahead Constr In the In the quality washing sedimentation tanks of schedule while uction constr constr wastewater protecti using aggregate unit uction uction on management system period, period Oily wastewater Treat the wastewater with oil Completed while Constr the , the management separation tanks arranging the uction capital enviro construction site unit requir nment ed by Domestic Set pail latrine in the Completed Constr the construction camp to before the uction al wastewater enviro implement centralized approach of the unit mana nment wastewater collection and construction geme al treatment workers nt plan manag Control the operation time of Noise is ement Acousti high-noise equipment and generated by Simultaneous superv plan is c transportation, reduce the construction with the Constr ised obtain environ impact of the noise on the mechanical equipment while uction by the ed mental residential area, and equipment and putting into unit from quality strengthen personal labor Enviro traffic operation the control protection of the construction nment transportation invest workers al ment Select sealed sand producing Protec of the equipment to produce sand, Environ Simultaneous tion main use wet method operation mental Dust and tail with the Constr Agenc project while implementing air gas of fuel equipment while uction y and excavation and blasting quality machinery putting into unit operations, provide a dust the control operation Water collector for the concrete mixing system, transport concrete with a sealed Author container, and implement ity of sealed raw material and Cheng production transmission of Count port to port Solid Collection, Set garbage can and other Completed Constr y waste transportation household waste collection before entering uction disposa and treatment of devices in the construction the construction unit l household living area worker into the waste camp Completed before entering Regularly check the body of the construction People Health of the construction workers and worker into the Constr health construction disinfect the construction area camp, and uction protecti workers body so prevent infectious regularly unit on diseases implemented in the construction period Soil Timely restore construction Gradually Constr and slash, and take implemented by uction Water loss and water corresponding protection following the unit soil erosion conserv measures in the construction construction ation process. period Terresti Terrestrial The construction process Gradually Constr ral vegetation and should be avoided from the implemented by uction ecosyst animal local wildlife activities as following the unit em much as possible, strictly construction prohibit capturing activities, period and prevent the damage to the vegetation outside the project area Person Construction technology and Befoore Constr nel management requirements training construction uction training unit

List for Environmental Management Plan of Operation Period Table 4-2 Task Implementati Superv on ision Capital Schedule organization organiz source ation Item Content of Mitigation measures taken by the environme project ntal

managem ent Geolog Geological Implement slope protection and Before Water In the In the ical disaster foot protection of the section impoundi Authority of operati operati environ which is easy in occurring ng Cheng on on ment landslide of the reservoir bank, County period, period, protecti and strengthen the seismic the the on monitoring of the region environ capital Release mental require Maintain the discharge amount young fish manag d by the under the suitable living in April to Water ement environ Aquati conditions of the aquatic life, and c life June in Authority of plan is mental Aquatic life reasonably introduce foreign protecti the Cheng supervi manag species on the basis of scientific sed by ement on operation County argumentation so as to increase the plan is period of the value of fishery resources Enviro the each year nmenta income Completio l of water Water n before Water Protect supply Water Complete the cleaning work of quality completio Authority of ion in the quality the reservoir, and supervise the protecti n Cheng Agency operati change quality of water on acceptanc County of on e Cheng period County Completio Reasonably set garbage can in Solid the living area to collect garbage, n before Water waste Household regularly transport the garbage to completio Authority of dispos waste the household waste landfill field n Cheng al to implement centralized acceptanc County treatment e Water Person Environmental basic theories and monitoring Before Authority of nel methods, compilation of monitoring reports, reservoir Cheng training and job training operation County

List for Environmental Action of Construction Period Table 4-3 No. Monitoring Monitoring content Monitoring Implement Supervisio worksite time ation n organizatio organizati n on 1 Constructio Determine the construction area; set Before Constructi Environm n camp enclosing material around the construction on unit ental construction site, and set pail latrine in Protection the site, wherein each construction site Agency of is provided with two garbage cans; the Cheng Xiaozhuang-Gumugou construction site County is provided with a primary and sedimentation tank and flocculation Environm sedimentation tank, and the place close ental to the concrete mixing system is Protection equipped with two sedimentation tanks; Agency of the Majiaya Qiaotou machinery parking Longnan area of left bank, Bashang achinery City parking area of left bank, Gumugou machinery parking area of right bank, Machinery parking area of sand and gravel mining area and the Bashang achinery parking area of right bank are respectively provided with an oil separation tank; the Majiaya Qiaotou construction site of the left bank, the construction site upstream the dam of left bank, the Xiaozhuang-Gumugou construction site of right bank, the dam construction site between the cofferdams, the construction site upstream the dam of right bank and water pipeline construction site and other sites are provided with 1 to 2 blocks of terrestrial vegetation and wildlife protection warning signs; the drainage ditches are provided; and the grouted stone pitching wall and reinforced stone cage facilities In the process of high-noise Construction construction, construction workers period should wear ear muffs and ear plugs; in high-dust content construction process, construction workers should wear masks; water and dust are regularly swept and removed; straw bag retaining wall is set while implementing temporary stacking, and the stacked material will be covered Implement backfill of the topsoil, land After remediation and vegetation restoration construction 2 Constructio Determine the living area; the living Before n living area area is provided with toilets and construction garbage cans, drainage ditches, grouted stone pitching wall and reinforced stone cage facilities, wherein when the topsoil is stripped, the temporary stacking place should be provided with straw bag retaining walls and covered Regularly watering to reduce dust, Construction implement cleaning and disinfection for period every three months Implement backfill of the topsoil, land After remediation and vegetation restoration construction 3 Water Set grouted stone pitching wall, set Construction pipeline straw bag retaining wall in the period temporary stacking place after stripping the topsoil, and cover the stacking place Implement backfill of the topsoil, land After remediation and vegetation restoration construction 4 Road Grouted stone pitching wall and Construction reinforced stone cage facilities, period temporary stacking place should be provided with straw bag retaining walls and covered when the topsoil is stripped, and the intercepting drain is provided Implement backfill of the topsoil, land After remediation and vegetation restoration construction 5 Residues Determine the range of the residues Before place place; provide reinforced stone cage construction block; set surrounding intercepting drain; set straw bag retaining walls in temporary stacking place, and cover Dry stone pitching; straw bag retaining Construction wall; and coverage of the slag after the period daily construction Implement backfill of the topsoil, land After remediation and vegetation restoration; construction and set slag top drainage ditch 6 Quarry Determine the mining area around Before intercepting drain, set straw bag constructio retaining walls in the temporary n stacking place, and cover Spray mix bracing, bolting, slope Constructio drainage holes; n period

Implement backfill of the topsoil, land After remediation and vegetation constructio restoration; and set slag top drainage n ditch 7 Main Scoping; dam dredging; surrounding Before project of drainage ditches constructio the dam n Grouted stone pitching wall, reinforced Constructio stone cage facilities, slope bolting, and n period surface concrete spray Vertical green of excavated slope After constructio n 8 Flooded Flooded area dredging Before area constructio n 9 Diversion Spray mix bracing, bolting; scaffolding Constructio tunnel support of inlet/outlet side walls and n period roof arch. Framework composed of combined templates Lower gate blocking of the diversion Before tunnel project operation 10 Cofferdam Impermeable property of Constructio high-pressure spray wall and n period impermeable property of waistcoat curtain grouting Residues of cofferdam removal are After sent to the designated residue field constructio n 11 Ecological the Majiaya Qiaotou construction site Before measures of the left bank, the construction site constructio upstream the dam of left bank, the n Xiaozhuang-Gumugou construction site of right bank, the dam construction site between the cofferdams, the construction site upstream the dam of right bank and water pipeline construction site and other sites are provided with 1 to 2 blocks of terrestrial vegetation and wildlife protection warning signs; Strengthen management, implement Constructio regular inspection, prevent hunting n period and fishing activities of the construction workers Renovate disturbed land, and restore After vegetation constructio n Release young fish in April to June of Project each year operation period