“Group Housing” at Village Purnapur & Kuantanda, -Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

ENVIRONMENT CLEARANCE APPLICATION

“Mega Green City & Mega Eco Park” (Group Housing)

At

Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Distt. Bareilly (UP)

Developed By Mega Infra Dreams LLP Consortium Add: C-2, Mega City, Sanjay Nagar Bypass, District Bareilly (UP)-243006

Prepared By

EARTH PROTECTION GROUP ENVIRONMENTAL CONSULTANT PVT. LTD.

(NABET Accredited Consultant, Certificate No: NABET/EIA/1619/IA0020 & S.No. in: 37)

4-D/620-B, SECTOR-4, GOMTI NAGAR EXTENSION, -226010 Contact No: 9839016959, 7570004689 E-mail: [email protected], [email protected] Website: www.epgec.com

Month/Year-December/2018

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 1

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

CONTENTS Particulars Page No. Contents 2 – 7

Enclosure-1: Form-1 & 1A 8 – 43

Enclosure-2: Conceptual Plan 44 – 52

2.1 INTRODUCTION 45 2.2 PROJECT COST 46 2.3 AMENITIES 46 2.4 SITE LOCATION 47 2.5 COORDINATES OF THE PROJECT SITE 48 2.6 TYPE OF THE PROJECT 48 2.7 PROJECT DETAILS 48 2.8 POPULATION DETAILS: 49 2.8.1 During Construction Phase 50 2.8.2 During Operation Phase 50 2.9 WATER REQUIREMENT 50 2.9.1 During Construction Phase 50 2.9.2 During Operation Phase 51 2.10 RAIN WATER COLLECTION & HARVESTING DETAILS 51 2.11 Power Requirement & Backup 51 2.11.1 During Construction Phase 51 2.11.2 During Operation Phase 51 2.12 Solid & Hazardous Waste Management 51 2.12.1 During Construction Phase 51 2.12.2 During Operation Phase 52 2.13 PARKING MANAGEMENT 52 2.13.1 During Construction Phase 52 2.13.2 During Operation Phase 52 2.14 Green Area Development 52

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 2

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Enclosure-3: Environment Assessment Report 53 – 89

3.1 EXECUTIVE SUMMARY OF THE PROJECT: 55 3.2 NATURE OF THE PROJECT: 57 3.3 LAND OWNERSHIP OF PROJECT LAND 57 3.4 SITE PREPARATION & LAND USE: 57 3.5 LOCATION & CONNECTIVITY OF THE PROJECT SITE 59 3.6 WATER RECOURSE MANAGEMENT 62 3.6.1 Water Requirement 62 3.6.2 Source of Water: 64 3.6.3 Reuse and Disposal of Treated Water: 64 3.7 ENERGY RECOURSE MANAGEMENT 66 3.7.1 During Construction Phase 66 3.7.2 During Operation Phase 66 3.7.3 Energy Conservation 66 3.8 SITE ANALYSIS 66 3.9 SOCIAL INFRASTRUCTURE 67 3.10 ENVIRONMENT MANAGEMENT PLAN 67 3.10.1 ENVIRONMENT MANAGEMENT PLAN (DURING CONSTRUCTION 68 PHASE) 3.10.1.1 Air Environment 68 3.10.1.2 Water Environment 69 3.10.1.3 Noise Environment 69 3.10.1.4 Solid Waste Management 70 3.10.2 ENVIRONMENT MANAGEMENT PLAN (DURING OPERATION PHASE) 70 3.10.2.1 Air Environment 70 3.10.2.2 Water Environment 70 3.10.2.2.a Waste Water Treatment System 71 3.10.2.2.b Schematic Diagram of STP: 73 3.10.2.2.c GROUND WATER STATUS OF THE PROJECT AREA 74 3.10.2.2.d RAIN WATER HARVESTING SYSTEM 75 3.10.2.3 Noise Environment 79 3.10.2.4 Parking Management 79 3.10.2.5 Waste Management 79

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 3

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

3.10.2.6 Green Belt/Plantation 80 3.10.2.7 Plantation Programme 81 3.10.3 COST OF ENVIRONMENT MANAGEMENT PLAN (EMP) 82 3.11 ANTICIPATED IMPACT & MITIGATION MEASURES 83 3.11.1 DURING CONSTRUCTION PHASE 83 3.11.2 DURING OPERATION PHASE 85 3.12 ENVIRONMENT MONITORING PROGRAMME 87 3.12.1 ENVIRONMENT MONITORING COST FOR CONSTRUCTION PHASE 88 3.12.2 ENVIRONMENT MONITORING COST FOR OPERATIONAL PHASE 89 Enclosure-4: Risk Assessment & Emergency Preparedness Plan 90 – 100

4.1 RISK ASSESSMENT 91 4.1.1 HAZARD IDENTIFICATION 91 4.1.2 VULNERABILITY ANALYSES 91 4.1.3 RISK ANALYSIS 91 4.1.4 EMERGENCY PREPAREDNESS PLAN 93 4.1.5 OFFSITE EMERGENCY PLAN 99 4.1.6 SECURITY PLAN 99 4.2 EVACUATION PLAN 100 Enclosure-5: Disclosure of Consultants 101 – 109

Enclosure-6: Other Maps & Documents 110 – 128

Enclosure-6.1 (Layout Plan) 111 Enclosure-6.2 (Location of STP & Vermicomposting in Self Owned Scheme) 112 Enclosure-6.3 (Location of STP & Vermicomposting in PMAY Scheme) 113 Enclosure-6.4 (Location of Rain Water Harvesting Pits in PMAY Scheme) 114 Enclosure-6.5 (Landscape Plan in Self Owned Scheme) 115 Enclosure-6.6 (Landscape Plan in PMAY Scheme) 116 Enclosure-6.7 (Fire Fighting System in PMAY Scheme) 117 Enclosure-6.8 (Consortium Resolution) 118 Enclosure-6.9 (Landuse Conversion) 119 Enclosure-6.10 (NOC from Tahsil) 124

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 4

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Enclosure-6.11 (NOC from Fire Department) 125 Enclosure-6.12 (NOC from PWD) 126 Enclosure-6.13.a (Khasra Map for Self Owned Scheme) 127 Enclosure-6.13.b (Khasra Map for PMAY Scheme) 128

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 5

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

LIST OF TABLES

Table Description Page No.

Table: 2.5 (Coordinates of the Project Site) 48 Table: 2.7 (Project Details) 48 Table: 2.8.2 (Estimated Population for Operation Phase) 50 Table: 3.1 (Project Details) 55 Table: 3.4 (Landuse details of both scheme) 57 Table: 3.5.a (Project Connectivity) 59 Table: 3.5.b (Coordinates of Project Site) 59 Table: 3.6.1.b.i (Water requirement in Operation Phase of Self Owned Scheme) 62 Table: 3.6.1.b.ii (Water requirement in Operation Phase of PMAY Scheme) 63 Table: 3.10.2.1 (Details of D.G. Set with Stack) 70 Table: 3.10.2.2.c.i (Ground Water Level of the Block) 74 Table: 3.10.2.2.c.ii (Average Ground Water Level of the Block) 75 Table: 3.10.2.2.d.i (Calculation of Rain Water Harvesting System of Self 77 Owned Scheme) Table: 3.10.2.2.d.ii (Calculation of Rain Water Harvesting System of PMAY 78 Scheme) Table: 3.10.3 (Cost of Environment Management Plan) 82 Table: 3.12 (Environment Monitoring Programme) 87 Table: 3.12.1 (Environment Monitoring Cost for Construction Phase) 88 Table: 3.12.2 (Environment Monitoring Cost for Operation Phase) 89

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 6

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

LIST OF FIGURES

Figure Description Page No.

Fig: 3.4.a (Land Use Details of Self Owned Scheme) 60 Fig: 3.4.b (Land Use Details of PMAY Scheme) 58 Fig: 3.5.a (Location Map in 2.5 Km Buffer) 60 Fig: 3.5.b (Location Map in 05 Km Buffer) 61 Fig: 3.6.1.b.i (Water Balance of Self Owned Scheme) 63 Fig: 3.6.1.b.ii (Water Balance of PMAY Scheme) 64 Fig: 3.6.3 (Map showing the Sewage Disposal Line in 2.5 Km Buffer) 65 Fig: 3.10.2.2.b (Schematic Flow Diagram of STP) 73

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 7

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Enclosure-1: Form-1 & 1A

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 8

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

I. Basic Information Sl.No. Item Details 1. Whether it is a violation case and No application is being submitted under Notification No. S.O.804 (E) dated 14.03.2017? 2. Name of the Project/s “Mega Green City & Mega Eco Park”

Project Cost (in lacs) 7000 Lacks ( For Both the Scheme i.e. Self Owned Scheme & PMAY Scheme) S. No. in the schedule 8 (a) Project Sector Building and construction projects- Sector 8 (a) 3. Proposed capacity/area/length/tonnage to Total plot area 101720 SQM be handled/command area/lease (Area for Road Widening, Nali, Chuck Road: area/number or wells to be drilled 1720 SQM + Area for Self Owned Scheme: 75000 SQM + Area for PMAY Scheme: 25000 SQM)

Total built-up area 77991.22 SQM (Self Owned Scheme: 34568.62 + PMAY Scheme: 43422.60 SQM) New/Expansion/Modernization New 4. MoEFCC file number (Previous EC) Not Applicable 5. Category of project i.e. 'A' or 'B' “B” Does it attract the general condition? If yes, Not Applicable please specify Does it attract the specific condition? If yes, Not Applicable please specify 6. Location of the project Village Purnapur & Kuantanda, Bareilly- Bisalpur Road, Distt. Bareilly (UP)

Coordinates of major four corners: 1st Corner: 28°21'6.47"N, 79°31'8.30"E, 174 m 2nd Corner: 28°21'9.30"N, 79°31'14.59"E, 174 m 3rd Corner: 28°21'18.55"N, 79°31'0.38"E, 175 m 4th Corner: 28°21'13.58"N, 79°30'56.24"E, 172 m 7. Shape of the project land Approx. Square Shape 8. Uploaded GPS file Incorporated in Environment Assessment Report

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 9

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Item Details 9. Uploaded copy of survey of Attached Toposheet 10. Plot/Survey/Khasra No. Khasra No: 19, 20, 26, 27, 29, 30, 33, 302, 303, 305, 306, 316, 322, 324 & 325 Town/ Village Purnapur & Kuantanda Tehsil Bareilly State of the project Nearest railway station along with distance Bareilly Junction: 10.5 Km WS in kms Railway Station: 10 Km WN Nearest airport along with distance in kms Air Force Station, Bareilly: 9.5 Km WN Chaudhary Charan Singh Airport: 260 Km ES NearestTown/City/District Headquarters Bareilly City ( Around 08 Km) along with distance in kms Village Panchayats, ZilaParishad, Muncipal Village Panchayat: Purnapur/Kuantanda Corporation, Local body (Complete postal address with telephone nos. to be given) 11. Registered Address Add: C-2, Mega City, Sanjay Nagar Bypass, District Bareilly (UP) -243006

Address for correspondance: Add: C-2, Mega City, Sanjay Nagar Bypass, District Bareilly (UP)-243006

12. Name (Company Name) Mega Infra Dreams LLP Consortium

13. Name of the Applicant Mr. Piyush Agrawal 14. Designation (Owner/ Partner/ CEO) Partner 15. Address Mega Infra Dreams LLP Consortium Add: C-2, Mega City, Sanjay Nagar Bypass, District Bareilly (UP) Pin code 243006 E-mail [email protected] [email protected] Telephone No. 9837074950, 9897225221 Fax No. - Copy of documents in support of the Annexure•Uploaded Copy of documents competence/authority of the person making (Consortium Resolution) in support of the this application to make application on competence/authority

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 10

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Item Details behalf of the User Agency 16. Details of Alternative Sites examined, if No alternative site has been examined any. Location of these sites should be shown on a toposheet 17. Whether part of Interlinked projects? No, it is not an interlinked project 18. Whether separate application of Interlinked Not Applicable project has been submitted? 19. If Yes, Not Applicable 20. Date of submission Not Applicable 21. If No, Reason Not Applicable 22. Whether the proposal involves Approval/ No Clearance under: if yes, details of the same and their status to be given (i) Whether the proposal involves Not Applicable approval/clearance under the Forest (Conservation) Act, 1980? (ii) Whether the proposal involves Not Applicable approval/clearance under the wildlife (Protection) Act,1972? (iii) Whether the proposal involves Not Applicable approval/clearance under the C.R.Z notification, 2011? 21. Whether there is any Government Not applicable Order/Policy relevent/relating to the site? Whether any Forest Land Involved? No Area of Forest land Involved (hectares) Whether there is any litigation pending No, affidavit enclosed against the project and/or land in which the project is proposed to be set up? (a) Name of the Court Not Applicable (b) Name of the Sub court Not Applicable (c) Case No. Not Applicable (d) Orders/directions of the court, if any and Not Applicable relevance with the proposed project

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 11

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

II. Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data 1.1 Permanent or temporary Yes This “Group Housing” project by the name of Mega change in land use, land Green City & Mega Eco Park is proposed at Village cover or topography Purnapur & Kuantanda, Bareilly-Bisalpur Road, including increase in Distt. Bareilly (UP). The project will be developed intensity of land use (with by Consortium Mega Infradreams LLP (Lead respect to local land use Member), Megaeco Project LLP, Qualitydream plan) Township LLP, ABPS Buildtech LLP, ABPS Realtech LLP, Quality Associates, Mega Infracity Pvt. Ltd., Nand Infradevelopers Pvt. Ltd. & Quality Brick Works. The required land for proposed project has been purchased by consortium. The proposal was submitted in Bareilly Development Authority (BDA) and same has been accepted and consent granted on 01.09.2018 for the development of this project. As per the direction of BDA (via letter No. 4547/B.D.A./2018- 19, dated: 05/09/18), the layout and building plans/drawings has been submitted in Bareilly Development Authority (BDA) for their approval. The approval of project plans from BDA is in advanced phase. Following NOC/approval has been granted:. a. Landuse Conversion, b. NOC from Tahsil, c. NOC from Fire Department d. NOC from PWD, 1.2 Clearance of existing No There is no building and distinct vegetation at site land, vegetation and except few bushes; hence, no clearance of existing buildings? land is required. 1.3 Creation of new land Yes The land will be change from vacant land to a uses? developed Group Housing.

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 12

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data 1.4 Pre-construction Yes Pre-construction geo-technical investigation shall be investigations e.g. bore submitted. houses, soil testing? 1.5 Construction works? Yes Construction work will be done as per the layout & buildings plans approved by Bareilly Development Authority. 1.6 Demolition works? No Proposed Site is vacant land, hence no demolition work will be required. 1.7 Temporary sites used for Yes Temporary rest rooms will be constructed for the construction works or labour & staff. housing of construction workers? 1.8 Above ground buildings, Yes The proposed site is flat, any basement is not structures or earthworks proposed, hence any excavation & demolition work including linear structures, is not required. cut and fill or excavations and fill or excavations The maximum height of the building will be 15 Meeter (In PMAY Scheme). 1.9 Underground works No It’s a Group Housing Project and hence no including mining or underground works are required except for tunneling? excavation of only for foundation. 1.10 Reclamation works? No Not applicable 1.11 Dredging? No Not applicable 1.12 Offshore structures? No Not applicable 1.13 Production and No It is a Group Housing project hence no production manufacturing or manufacturing processes shall be carried out. processes? 1.14 Facilities for storage of Yes Construction Phase goods or materials? • Separate raw material yard shall be made within the project site. • Cement shall be separately stored under cover in bales. • Sand Shall be stacked nearby under tarpaulin cover. • Bricks and steel shall be laid in open.

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 13

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data Operation Phase As the project is a Group Housing, the raw material will be food, stationary and other household items which will be stored in respective dwelling units only. 1.15 Facilities for treatment or Yes Construction Phase disposal of solid waste or Around 500 nos. manpower will be engaged in the liquid effluents? project and approx. 150 kg/day of Municipal solid waste shall be generated from the domestic activities of temporary labours rest rooms which shall be disposed off at Municipal Solid Waste site.

The excavated soil generated from excavation of foundation & Construction debris like Concrete generated from site shall be used in backfilling & leveling purposes on site Recyclable waste like aluminium, steel, wood pieces, cement bags, plastic containers, cartons, glass etc. will be sold to recyclers.

Approx. 20 KLD domestic sewage waste will be generated and discharge through septic tank followed by soak pits. Operaton Phase For 8740 persons, around 2622 kg/day of municipal solid waste will be generated from the both schemes.

Sewage Treatment Plant (STP) of Capacity 251 KLD & 450 KLD is proposed in Self Owned Scheme & PMAY Scheme respectively.

Details of Water Management and Solid Waste Management are given in Environment Assessment Report. 1.16 Facilities for long term No During Construction Phase housing of operational Only temporary rest rooms will be provided for

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 14

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data workers? staying labors.

During operation phase: As this is a Group Housing Staff will only be needed for maintenance. They will be from the nearby areas. Separate housing will not be provided. 1.17 New road, rail or sea No No new road, rail or sea traffic is proposed. Existing traffic during construction transportation facilities will be used during construction or operation? or operation phase. 1.18 New road, rail, air water No No new road, rail or sea traffic is proposed. borne or other transport The transportation measures already existing near site infrastructure including are as follows: new or altered routes and Satellite Bus Station, Bareilly: 7.5 Km W stations, ports, airports Bareilly Junction: 10.5 Km WS etc? Izzatnagar Railway Station: 10 Km WN Air Force Station, Bareilly: 9.5 Km WN Chaudhary Charan Singh Airport: 260 Km ES 1.19 Closure or diversion of No There will be no closure or diversion of existing existing transport routes transport routes or infrastructure leading to or infrastructure leading to changes in traffic movements will be made. changes in traffic movements? 1.20 New or diverted No No such closure or diversion of transmission lines transmission lines or is required. pipelines? 1.21 Impoundment, damming, No No impoundment, damming, culverting, culverting, realignment or realignment or other changes to the hydrology of other changes to the surface water courses is required. hydrology of watercourses or aquifers? 1.22 Stream crossings? No No stream crossing is involved 1.23 Abstraction or transfers of Yes The required water in construction phase as well water from ground or as in operation phase will be withdrawal from surface waters? proposed bore well. 1.24 Changes in water bodies No There will be no change in water bodies or the land or the land surface surface affecting drainage or run-off.

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 15

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data affecting drainage or run- off? 1.25 Transport of personnel or Yes During Construction phase: materials for construction, Materials during construction phase shall be operation or transported by truck, dumpher, tractor trolley etc. decommissioning? During Operation Phase: Car, two-wheeler, etc. will be used. 1.26 Long-term dismantling or No Not Applicable decommissioning or restoration works? 1.27 Ongoing activity during No Not Applicable decommissioning which could have an impact on the environment? 1.28 Influx of people to an area Yes During Construction Phase: in either temporarily or Temporary influx of people in the form of labours is permanently? envisaged. Around 500 nos., which will be engaged in both schemes (Self owned scheme & PMAY Scheme). Out of which 100 nos. skilled, 150 nos. semi skilled & 250 unskilled manpower.

During Operation Phase: As this is a Group Housing, total 8740 people (2275 residents, 200 commercial & 200 in school for Self Owned Scheme and 6000 residentsis & 65 commercials in PMAY Scheme) is envisaged. 1.29 Introduction of alien No Not applicable species? 1.30 Loss of native species or No No tree exists at the site. However, by planting genetic diversity? native plants within the project site, it will give positive impacts. 1.31 Any other actions? No Not Applicable

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 16

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data 2.1 Land especially Yes The land is undeveloped and has been purchased by undeveloped or the consortium. The land has been converted in agricultural land (ha) Residential from agriculture. Land use conversion is enclosed. 2.2 Water (expected source Yes During Construction Phase: & competing users) unit: During construction phase Around 25 KLD water will KLD be required for Domestic Purpose and 300 KL/Month water will be required for construction purpose. The demand of water requirement will be met by bore wells. The required bore wells will be constructed out of total proposed bore wells for operation phase of both schemes.

During Operation Phase: Total water requirement for the Self Owned Scheme is 364 KLD (Fresh Water 334 + Treated Water 30 KLD) and 02 nos. of Bore Wells are proposed to meet the total daily water demand.

Total water requirement for the PMAY Scheme is 542 KLD (Fresh Water 522 + Treated Water 20 KLD) and 05 nos. of Bore Wells are proposed to meet the total daily water demand.

Detailed water Management & water balance are given in Environment Assessment Report. 2.3 Minerals (MT) Yes Sand & Aggregates 2.4 Construction material – Yes The major materials required for construction of the stone, aggregates, sand / project ae steel, tiles, glass, cement, aggregates, soil (expected source – bricks, flooring tiles/stones, sanitary and hardware MT) items, electrical fittings etc. 2.5 Forests and timber Yes Plywood for doors and windows shall be used which (source – MT) shall be procured from local market. 2.6 Energy including Yes During Construction Phase: electricity and fuels 02 x 10 KW electric connection in each scheme will (source, competing be met by U.P. Power Corporation Limited. For the

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 17

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data users) Unit: fuel power backup one number of 65 KVA D.G. Set will (MT),energy (MW) be installed.

During Construction Phase: Electric connection of capacity 1750 KW (07 Transformer of 250 KW each) in each scheme will be met by U.P. Power Corporation Limited. In case of power failure, only for the operation of bore wells, 01 nos. D.G Set (40 KVA) & 01 nos. D.G. Set (65 KVA) are proposed in Self Owned Scheme & PMAY Scheme respectively. 2.7 Any other natural No Not Applicable resources (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data 3.1 Use of substances or Yes This is a Group Housing Project, no storage of materials, which are hazardous substances (as per MSIHC rules) will be hazardous (as per done apart from limited quantity of HSD storage (for MSIHC rules) to human DG sets). Used oil whenever generated from the DG health or the sets & construction machineries shall be kept in a environment (flora, secured place and in leak proof container and shall fauna, and water be sent to authorized vender. supplies 3.2 Changes in occurrence No Suitable drainage and waste management measures of disease or affect will be adopted to restrict stagnation of water & disease vectors (e.g. accumulation of waste. This will effectively restrict the insect or water borne reproduction and growth of disease vectors. diseases)

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 18

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data 3.3 Affect the welfare of Yes During Construction Phase: people e.g. by changing Employment opportunities provided due to the project living conditions? will lead to better quality of life and will also set a standard for future developments in the area. Moreover, this project will provide employment to local labours also during construction phase.

During Operation Phase: As it is a Group Housing, there shall be several services required which will generate direct and indirect employment for the people of nearby area. Commercial shops and one school are also proposed in the self owned scheme. 3.4 Vulnerable groups of No No vulnerable group of people will be affected by the people who could be project. affected by the project e.g. hospital patients, children, the elderly etc. 3.5 Any other causes No None

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data 4.1 Spoil, overburden or No Not Applicable mine wastes 4.2 Municipal waste Yes During Construction Phase (domestic and or Around 500 nos. manpower will be engaged in the commercial wastes) project and approx. 150 kg/day of Municipal solid waste shall be generated from the domestic activities of temporary labours rest rooms which shall be disposed off at Municipal Solid Waste site.

During Operation Phase For 8740 persons, around 2622 kg/day of municipal

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 19

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data solid waste will be generated from the both schemes.

4.3 Hazardous wastes (as Yes During Construction Phase per Hazardous Waste Used oil whenever generated from the DG sets & Management Rules) construction machineries shall be kept in a secured place and in leak proof container and shall be sent to authorized vender.

During Operation Phase Approx. 05 Lit/Month used oil generated from the DG sets shall be shall be collected in leak proof containers at isolated place and then it will be given to authorized vender of CPCB as per “The Hazardous and Other Waste (Management & Transboundary Movement) Rules, 2016” 4.4 Other industrial process No Not applicable wastes 4.5 Surplus product No Not applicable 4.6 Sewage sludge or other Yes About 18 Kg/day of dried sludge will be generated sludge from effluent from both STP of both schemes during operation treatment phase and this sludge will be passed through filter press where it will be dewatered/dried to form a cake and then will be used as manure in green areas. 4.7 Construction or Yes The excavated soil generated from excavation of demolition wastes foundation & Construction debris like Concrete generated from site shall be used in backfilling & leveling purposes on site Recyclable waste like aluminium, steel, wood pieces, cement bags, plastic containers, cartons, glass etc. will be sold to recyclers. 4.8 Redundant machinery or No Not Applicable equipment 4.9 Contaminated soils or No Not applicable other materials 4.10 Agricultural wastes No Not applicable 4.11 Other solid wastes No During Construction Phase: No e-waste shall be generated.

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 20

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data During operation Phase: E-Waste shall be collected in Black bin with label and Disposed as per “The E-Waste (Management) Rules, 2016. Battery waste will be generated from inverters & UPS, which shall be treated/disposed as per “The Batteries (Management & Handling) Rules, 2001.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data 5.1 Emissions from Yes During Construction Phase combustion of fossil DG set of capacity 65 KVA will be installed with fuels from stationary or acoustic enclosure with adequate stack height. And mobile sources movement of vehicles which carryout out the construction material will properly maintained to reduce the emission.

During Operation Phase The source of emission will be two numbers of D.G. Sets, one in Self Owned Scheme of capacity 40 KVA with 1.5 m (above roof) stack height and second in PMAY scheme of capacity 65 KVA with 2.0 m (above roof) stack height 5.2 Emissions from No Not Applicable production processes 5.3 Emissions from Yes Dust shall be generated during construction from the materials handling movement of transport vehicles and other construction including storage or activities. The effect will be restricted to construction transport phase only. Water sprinklers shall be used for dust suppression. Material will be stored under Tarpaulincover. 5.4 Emissions from Yes Dust and emissions are likely to be generated during construction activities construction activities which shall be reduced by including plant and sprinkling of water in a specific time interval and timely equipment maintenance schedule for machinery.

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 21

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data Also, the machines shall be shut down during idle period. 5.5 Dust or odours from Yes During loading and unloading of construction material handling of materials dust is likely to be generated during construction including construction phase. Water shall be sprinkled and tarpaulin cover materials, sewage and shall be provided over stored raw material to reduce waste dust emission. Temporary toilets during construction phase shall be provided and waste water shall be disposed off in septic tank followed by soak pits. 5.6 Emissions from No Not Applicable incineration of waste 5.7 Emissions from burning No Open burning of biomass/other material will be of waste in open air (e.g. prohibited. slash materials, construction debris) 5.8 Emissions from any No None other sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data 6.1 From operation of No During construction phase: equipment e.g. engines, DG set of capacity 65 KVA shall be installed ventilation plant, acoustically enclosed. The equipment such as mixer crushers machines, bulldozers, cranes, compactors and excavators shall be used which will be of highest standard of reputed make and adhere to international standards. Hence an insignificant impact due to construction machinery is envisaged and timely maintenance of machinery will be ensured. During operation phase: Source of noise in the operational phase will be 02 D.G. sets one Self Owned Scheme & one in PMAY Scheme. Both D.G. sets shall be installed with anti- vibration pads and acoustic enclosure and will be

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 22

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data used during Power failure only for bore wells operation. 6.2 From industrial or similar No Not applicable processes 6.3 From construction or Yes Due to the various activities, there are short-term demolition noise impacts in the construction phase. 6.4 From blasting or piling No No blasting or piling will be done 6.5 From construction or Yes Some amount of noise will be generated from operational traffic vehicular movement in the construction and operational phase. Proper road and parking space will be provided for control of traffic noise. As well as plantation around the boundary wall shall be provided to reduce noise from traffic. 6.6 From lighting or cooling No Not Applicable systems 6.7 From any other sources No None

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data 7.1 From handling, storage, No The hazardous waste generated will be used oil only use or spillage of shall be kept in a secured place and in leak proof hazardous materials container and shall be sent to authorized vender. 7.2 From discharge of No During operation phase 251 KLD & 450 KLD STP is sewage or other proposed in both schemes for treating the sewage effluents to water or the waste. 50 KLD treated water reuse in green belt and land (expected mode rest treated water disposed to Baigul River via under and place of discharge) groud sewage disposal line. 7.3 By deposition of Yes Only dust during construction phase. pollutants emitted to air into the land or into water 7.4 From any other sources No Not Applicable 7.5 Is there a risk of long No Not Applicable

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 23

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data term build up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

Sl.No. Information/Checklist Yes/ Details there of (with approximate confirmation No quantities/rates, wherever possible) with source of information data 8.1 From explosions, No During Construction Phase: spillages, fires etc. from Only HSD as hazardous material will be used in storage, handling, use or construction machineries and DG Set. All appropriate production of hazardous measures shall be taken to avoid accidents. substances During Operational Phase: Only HSD as hazardous material will be used in DG Sets. Proper Emergency Preparedness Plan and firefighting system will be installed at project site. 8.2 From any other causes No During construction phase: All the labours shall be provided with suitable personal protective equipment (PPE) as required under the health and safety norms. Training and awareness about the safety norms shall be provided to all supervisors and labours involved in construction activity. 8.3 Could the project be No The area under study falls in seismic zone-IV, affected by natural according to the Indian Standard Seismic Zoning disasters causing Map. Suitable seismic coefficients in horizontal and environmental damage vertical directions respectively, will be adopted while (e.g. floods, designing the structure. earthquakes, landslides, cloudburst etc)?

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 24

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Sl.No. Information/Checklist Yes/ Details there of (with approximate quantities/rates, confirmation No wherever possible) with source of information data 9.1 Lead to development of No Not Applicable supporting utilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: • Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.) • housing development • extractive industries • supply industries • Other 9.2 Lead to after-use of the No Not Applicable site, which could have an impact on the environment 9.3 Set a precedent for later Yes It will attract people to develop organized Group Housing. developments 9.4 Have cumulative effects No No impact due to proximity to other existing or planned projects with similar effects

III. ENVIRONMENTAL SENSITIVITY Sl.No Areas Name/ Identity Aerial distance (within 15 km.) Proposed project location boundary 1 Areas protected under international None Not Applicable

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 25

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No Areas Name/ Identity Aerial distance (within 15 km.) Proposed project location boundary conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive Water Bodies: for ecological reasons - Wetlands, Baigul River Approx. 01 Km N watercourses or other water bodies, Canal Approx. 0.3 Km W coastal zone, biospheres, mountains, forests 3 Areas used by protected, important or None Not Applicable sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or None Not Applicable underground waters 5 State, National boundaries No Not Applicable 6 Routes or facilities used by the public Bareilly Bypass (NH- 02 Km W for access to recreation or other 30) tourist, pilgrim areas Bareilly-Bisalpur Road Site Entry WS Satellite Bus Station, 7.5 Km W Bareilly Bareilly Junction 10.5 Km WS Izzatnagar Railway 10 Km WN Station Air Force Station, 9.5 Km WN Bareilly Chaudhary Charan 260 Km ES Singh Airport, Lucknow 7 Defence installations Bareilly Cantonment Around 7 Km

8 Densely populated or built-up area Village Purnapur Aprrox. 0.7 Km in WN Village Kuantanda Approx. 0.2 Km in WS 9 Areas occupied by sensitive man- In Bareilly City approx. 08 Km in W

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 26

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Sl.No Areas Name/ Identity Aerial distance (within 15 km.) Proposed project location boundary made land uses (hospitals, schools, places of worship, community facilities)

10 Areas containing important, high None Not Applicable quality or scarce resources. (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution None Not Applicable or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard Natural The proposed which could cause the project to project falls in present environmental problems Seismic Zone-IV. (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 27

“Group Housing” at Village Purnapur & Kuantanda, Bareilly-Bisalpur Road, Bareilly By Mega Infra Dreams LLP Consortium

Undertaking

Prepared By: M/s Earth Protection Group Environmental Consultant Pvt. Ltd. Page | 28