Technical Assistance Consultant’s R eport
Project Number: 48030-001 February 2020
Mongolia: S trategy for Northeast Asia Power S ystem Interconnection (Cofinanced by the Climate Change Fund, the People’s R epublic of China R egional Cooperation and Poverty R eduction Fund, and the R epublic of Korea e-Asia and Knowledge Partnership Fund)
Prepared by E lectricite de France Paris, France
For the Ministry of E nergy, Mongolia
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents.
TA 9001-MON: Strategy for Northeast Asia Power S ystem Interconnections
EDF References: CIST – DCO – PhL – 18 - 208
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents.
Module 4 report on Mongolia Energy Sector Profile and Projections
FOREWORD The project Team would like to thank:
- The Ministry of Energy of Mongolia for easing direct discussions with the National Dispatching Center, TRANSCO and Public Entities in Mongolia
- The ADB’s Country Coordinators of Mongolia, People’s Republic of China, Republic of Korea, Japan for their support: Mongolia: Mr. Byambasaikhan PRC: Ms. Geng Dan (Danna) ROK: Mr. Jung-Hwan Kim Japan: Mr. Omatsu Ryo and Mr. Shota Ichimura
Here is a reminder of the place of the Module 4 in the Project organization:
1
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
TABLE OF CONTENTS EXECUTIVE SUMMARY ...... 14 1 OVERVIEW OF MODULE 4 ...... 19 2 MONGOLIA CURRENT POWER GENERATION ...... 20
2.1 CONVENTIONAL EXISTING POWER PLANTS ...... 21 2.1.1 Coal power plants ...... 22 2.1.2 Heat generation ...... 23 2.1.3 Current Mongolia transmission grid ...... 24
2.2 Renewable existing power plants ...... 26 2.2.1 Hydro power plants ...... 26 2.2.2 Wind farms ...... 27 2.2.3 Ground mounted solar PV farm ...... 28
2.3 PIPELINE OF CURRENT POWER DEVELOPMENTS ...... 30 2.3.1 Conventional plants ...... 30 2.3.2 Renewables ...... 31 2.3.2.1 Hydro ...... 31 2.3.2.2 Wind ...... 32 2.3.2.3 Ground mounted solar PV ...... 33 2.3.2.4 Biomass ...... 34 2.3.2.5 Other renewables ...... 36 Geothermal energy resources ...... 36 3 MONGOLIA STRATEGY ON POWER DEVELOPMENT...... 38 4 MONGOLIA EXISTING ENERGY POLICY (2030) ...... 40
4.1 Organizations of Mongolian power sector ...... 40
4.2 Regional energy system ...... 42
4.3 Single Buyer Model ...... 48 5 IMPACT ON MONGOLIAN CONVENTIONAL FLEET WITH ENERGY POLICY 2030 ...... 49
5.1 Targets ...... 49
5.2 Analysis of Existing Generation In Mongolia ...... 52
5.3 Heat forecast in mongolia ...... 52
5.4 Planned Generation Development ...... 53
5.5 Conclusion of Generation Analysis ...... 62 6 DEVELOPMENT OF RENEWABLE ENERGY IN MONGOLIA FOR EXPORTATION ...... 64
6.1 RENEWABLES DEVELOPMENT scenarios FOR MONGOLIA ...... 64
2
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
6.1.1 Scenario 0 « MINGW » in 2020 ...... 64 6.1.2 Scenario 1 « +5GW » in 2026 ...... 65 6.1.3 Scenario 2 « +10GW » in 2036 ...... 65 6.1.4 Scenario 3 « +100GW » in the long term ...... 65
6.2 Wind and solar PV resource assessment ...... 65 6.2.1 Previous renewables resource assessment ...... 66 6.2.2 Methodology – GIS tool ...... 70 6.2.3 Hypotheses – Key environmental and regulation constraints ...... 72 6.2.4 Regulatory and land use constraints ...... 72 6.2.5 Wind technology characteristics ...... 75 6.2.6 Solar PV characteristics ...... 80
6.3 gis ranking methodology ...... 84 6.3.1 Multi-criteria decision analysis (MCDA) ...... 85 6.3.2 Weighing of criteria for the different scenarios ...... 86 6.3.3 Multi-criteria decision analysis for the different scenarios ...... 88
6.4 wind power potential ...... 92 6.4.1 Wind resource data ...... 92 6.4.2 Gross wind potential ...... 93 6.4.3 Technical wind potential ...... 94 ...... 94 6.4.4 Scenario 0 – Wind potential ...... 95 6.4.5 Scenario 1 to 3 – Wind potential ...... 98
6.5 solar pv potential ...... 100 6.5.1 Solar resource data ...... 100 6.5.2 Gross solar potential ...... 101 6.5.3 Technical solar potential ...... 102 ...... 102 6.5.4 Scenario 0 – Solar potential ...... 102 6.5.5 Scenario 1 to 3 – Solar potential ...... 106
6.6 wIND AND solar pv potential –Synthesis ...... 108 6.6.1 Wind and solar technical potential ...... 108 6.6.2 Wind and solar ranked potential – Scenario 0 ...... 109 6.6.3 Wind and solar ranked potential – Scenario 1 to 3 ...... 110
6.7 wIND AND solar pv Cost assessment - LCOE ...... 113 6.7.1 100MW wind farm costs ...... 113 6.7.2 50MW solar farm costs ...... 115
6.8 CONCLUSIONS of wIND AND solar pv assessment ...... 118 7 IMPACT OF RENEWABLES DEVELOPMENT ON MONGOLIA POWER SYSTEM ...... 119
7.1 METHODOLOGY ...... 120
3
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
7.1.1 Methodology for analyzing impact on transmission system ...... 120
7.2 impact of scenario 0 on current power network ...... 122
7.3 IMPACT OF SCENARIO 1&2 ...... 124 7.3.1 Impact of Scenario 1 & 2 on conventional power on economy, politics & regulation and society & environment ...... 124 7.3.2 Impact of scenario 1 & 2 on current power network ...... 126
7.4 impact of scenario 3 ...... 128 7.4.1 Impact of Scenario 3 on economy, politics & regulation and society & environment ...... 128 7.4.2 Impact of Scenario 3 on current power network ...... 129 APPENDIX 1: SOURCE OF KEY CONSTRAINTS FOR RES ASSESSMENT (GIS TOOL) ...... 132
4
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
LIST OF TABLES Table 1. CHPs in operation 21 Table 2. CHPs in operation 22 Table 3. Heat generation by plant 23 Table 4.Hydropower plants (in operation) 26 Table 5. Wind power plants (in operation) 27 Table 6.Wind-diesel power plants (in operation) 28 Table 7.Solar power station (in operation) 28 Table 8.Solar-Wind-diesel hybrid power plants (in operation) 29 Table 9.Power plant construction and enhancement plan are shown in the following table. Some of them are under way. 30 Table 10.Projects of Hydropower plant construction 31 Table 11.Projects of Wind power plant construction 32 Table 12.Projects of Solar power plant construction 33 Table 13.Mongolia strategy on power development 39 Table 14. Functions of related organizations 41 Table 15.The electricity prices for ordinary household 44 Table 16.The electricity prices for enterprises 44 Table 17. Tariffs for the electricity from Renewable Energy plants 47 Table 18. Heat demand forecast in Mongolia (Upscaling Energy Sector Development Plan, ADB report, medium scenario) 53 Table 19. Generation Development in Target 1 (2020) 54 Table 20.Generation Development in Target 2 (2020) 56 Table 21. Impact on Conventional Generation in 2030 58 Table 22. Impact on Conventional Generation in 2036 60 Table 23. Comparison of Generation Analysis Results 62 Table 24. 220kV Substations & Connection capacity 64 Table 25. Wind energy potential of Mongolia (good to very good wind resource at 30 m height) Source: NREL & NREC 66 Table 26. Solar energy resource of Mongolia. Source NREC 2006 68 Table 27. Mongolia solar resource estimate. Source IRENA 69 Table 28. Main constraints for wind and solar – Key hypotheses – Source EDF EIFER 73 Table 29. Wind power density – Source EDF 77
5
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Table 30. Wind turbine Power Curve – Source: Vestas – EDF 79 Table 31. Load factor calculation – Source EDF 80 Table 32 Solar PV load factor – Source EDF 84 Table 33 Scenario 0 – Ranking & Scores. Source EDF 86 Table 34 Scenarios 1 to 3 – Ranking & Scores. Source EDF 87 Table 35. Scenario 0-Wind resource scores. Source EDF 95 Table 36. Scenario 0-Wind resource within 200km substations buffers-All scores. Source EDF 96 Table 37. Scenario 0-Total wind resource within 200km substations buffers. Source EDF 97 Table 38. Scenario 0-Score 4 wind resource within 20-50km substations buffers. Source EDF 97 Table 39. Scenario 1 to 3-Wind resource Scores. Source EDF 98 Table 40. Scenario 1 to 3-Score 4 wind potential areas per Aimag. Source EDF 99 Table 41. Scenario 1 to 3-Score 5 wind potential areas per Aimag. Source EDF 99 Table 42. Scenario 1 to 3-Score 4 wind potential areas within 200km substations buffers. Source EDF 100 Table 43. Scenario 0-Solar resource scores. Source EDF 103 Table 44. Scenario 0-Solar resource within 200km substations buffers-All scores. Source EDF 104 Table 45. Scenario 0-Total solar resource within 200km substations buffers. Source EDF 105 Table 46. Scenario 0-Score 4 solar resource within 20-50km substations buffers. Source EDF 105 Table 47. Scenario 1 to 3-Solar resource Scores. Source EDF 106 Table 48. Scenario 1 to 3-Score 4 solar potential areas per Aimag. Source EDF 107 Table 49. Scenario 1 to 3-Score 4 solar potential areas within 200km substations buffers. Source EDF 107 Table 50. 2020 Wind CAPEX. Source EDF 113 Table 51. 2020 Wind OPEX. Source EDF 114 Table 52. 2020-2026-2036 Wind CAPEX. Source EDF 114 Table 53. 2020-2026-2036 Wind OPEX. Source EDF 115 Table 54. 2020-2026-2036 Wind LCoE. Source EDF 115 Table 55. 2020-Solar CAPEX. Source EDF 116 Table 56. 2020 Solar OPEX. Source EDF 116 Table 57. 2020-2026-2036 Solar CAPEX. Source EDF 117
6
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Table 58. 2020-2026-2036 Solar OPEX. Source EDF 117 Table 59. 2020-2026-2036 Solar LCoE. Source EDF 118 Table 60. Mongolian GDP and renewable energy investment under Scenario 1 124 Table 61. Mongolian GDP and renewable energy investment under Scenario 2 125 Table 62. Mongolian GDP and renewable energy investment under Scenario 3 128
7
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
LIST OF FIGURES Figure 1 Installed capacity and Electricity generation in Mongolia in 2016 ...... 20 Figure 2 Transmission line in South Gobi ...... 25 Figure 3 Big Hydropower plants (in operation) ...... 27 Figure 4. Existing wind power plants ...... 27 Figure 5 Bid scale Solar power station (in operation) ...... 29 Figure 6 Mongolian forest resources ...... 36 Figure 7. Location of Mongolian hot springs, Source: Study conducted by REC ...... 37 Figure 8. Overview of related organizations in Mongolian Power sector ...... 40 Figure 9. Four Energy System in Mongolia ...... 42 Figure 10. Procedure for Approval of Tariffs ...... 46 Figure 11. Participants of Single Buyer Model in CES ...... 48 Figure 12. Existing Conventional Generation by Region and Unit Size ...... 52 Figure 13. Monthly RE Curtailment and Energy Not Supplied...... 56 Figure 14. Monthly RE Curtailment and CENS in 2026 ...... 58 Figure 15. Monthly RE Curtailment and EENS in 2030 ...... 60 Figure 16. Monthly RE Curtailment and EENS in 2036 ...... 61 Figure 17. Mongolia – 5000m resolution elevation map. Source: Vaisala ...... 65 Figure 18. Wind resource map of Mongolia. Source NREL & NREC 2004 ...... 67 Figure 19. Map of wind capacity in Mongolia. Source IRENA ...... 67 Figure 20. Annual global solar radiation, kWh/m2/year. Source Energy Authority of Mongolia 2009 ...... 69 Figure 21. Potential assessment phases. Source EDF ...... 71 Figure 22. GIS methodology – Source EDF EIFER ...... 71 Figure 23. GIS methodology & steps – Source EDF EIFER ...... 72 Figure 24. Examples of possible Vestas turbines, suitable in Mongolia (IEC II & I) – Source Vestas ...... 76 Figure 25. Wind farm layout – Source EDF ...... 77 Figure 26. Weibull wind distribution – average wind speed 8 & 9 m/s – Source EDF ...... 78 Figure 27. Turbines Power Curve – Source Vestas & EDF ...... 78 Figure 28. Canadian Solar “Diamond CS6X-315/320/325/330P-FG” module-Source Canadian Solar ...... 81 Figure 29. SunBrush PV panel brushing system (Seih Al-Dahal farm – Dubai) – Souce SunBrush ...... 82
8
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Figure 30. PV module cleaning robot – Source Miraikikai ...... 83 Figure 31. Ground mounted tilted PV panels – Layout and shading - Source Schettler Gmbh ...... 83 Figure 32. Procedure for ranking suitable areas. Source EDF EIFER ...... 88 Figure 33. Wind speed-Value scores. Source EDF EIFER ...... 89 Figure 34. Solar GHI-Value scores. Source EDF EIFER ...... 89 Figure 35. Proximity to roads-Value scores. Source EDF EIFER ...... 90 Figure 36. Proximity to railways (only for Solar)-Value scores. Source EDF EIFER ...... 90 Figure 37. Proximity to cities/villages-Value scores. Source EDF EIFER ...... 91 Figure 38. Terrain slope (only for Solar)-Value scores. Source EDF EIFER ...... 91 Figure 39. Proximity to 220kV substations (only Scenario 0). Value scores. Source EDF EIFER ...... 92 Figure 40. 30-year (1987-2016) mean wind speed at 100m – Source Vaisala ...... 93 Figure 41. Wind resource in Mongolia. Source EDF EIFER ...... 93 Figure 42. Wind resource in non-excluded areas. Source EDF EIFER ...... 94 Figure 43. Scenario 0 – Wind ranked potential areas – All scores. Source EDF EIFER ...... 95 Figure 44. Scenario 1 to 3-Wind ranked potential areas – All scores. Source EDF EIFER .. 98 Figure 45. Solar resource (GHI) in Mongolia. Source SolarGis ...... 101 Figure 46. Wind resource in Mongolia. Source EDF EIFER ...... 101 Figure 47. Solar resource in Mongolia (non-excluded areas). Source EDF EIFER ...... 102 Figure 48. Scenario 0 – Solar ranked potential areas – All scores. Source EDF EIFER .... 103 Figure 49. Scenario 1 to 3-Solar ranked potential areas – All scores. Source EDF EIFER 106 Figure 50. Wind and Solar potential areas (non-excluded areas). Source EDF EIFER ...... 108 Figure 51. Scenario 0-Wind & Solar potential areas-All scores. Source EDF EIFER ...... 109 Figure 52. Scenario 0-Wind & Solar potential areas-All scores-220kV grid. Source EDF EIFER ...... 109 Figure 53. Scenario 0-Wind & Solar potential areas-Score 4. Source EDF EIFER ...... 110 Figure 54. Scenario 1 to 3. Wind and Solar potential areas. Score 4 only. Source EDF EIFER ...... 111 Figure 55. Scenario 1 to 3. Wind and Solar potential areas. Score 4 only. 220kV grid. Source EDF EIFER ...... 111 Figure 56. Scenario 1 to 3. Best Provinces for wind and solar development (Score 4)-220kV grid. Source EDF EIFER ...... 112 Figure 57. Schematic Diagram of Quarantined VSC-HVDC Transmission Scheme ...... 121
9
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Figure 58.Schematic Diagram of Integrated HVDC Transmission System Design ...... 121 Figure 59. Scenario 1 – Impact on Mongolian Transmission System ...... 122 Figure 60. Schematic Single Line Diagram of Mongolian Transmission System ...... 123 Figure 61. Scenario 2 Quarantined HVDC Transmission Scheme ...... 127 Figure 62. Scenario 2 – Integrated HVDC transmission scheme ...... 127 Figure 63. Scenario 3 – Quarantined HVDC Transmission Scheme ...... 130 Figure 64. Scenario 3 – Integrated HVDC Transmission Scheme ...... 130 Figure 65. Scenario 3 – Integrated AC Transmission Scheme ...... 131
10
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
PHYSICAL UNITS AND CONVERSION FACTORS bbl barrel (1t = 7.3 bbl) cal calorie (1 cal = 4.1868 J) Gcal Giga calorie GWh Gigawatt-hour h hour km kilometer km² square kilometer kW kilo Watt kWp kilo Watt peak (solar PV) kWh kilo Watt hour (1 kWh = 3.6 MJ) MBtu Million British Thermal Units (= 1 055 MJ = 252 kCal) one cubic foot of natural gas produces approximately 1,000 BTU MJ Million Joule (= 0,948.10–3 MBtu = 238.8 kcal) MW Mega Watt m meter m3/d cubic meter per day mm millimeter mm3 million cubic meter Nm3 Normal cubic meter, i.e. measured under normal conditions, i.e. 0°C and 1013 mbar (1 Nm3 = 1.057 m3 measured under standard conditions, i.e. 15°C and 1013 mbar) pu per unit sqm Square meter t ton toe tons of oil equivalent tcf ton cubic feet °C Degrees Celsius
11
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
ABBREVIATIONS AND ACRONYMS
ADB Asian Development Bank AUES Altai-Uliastai Energy System BNEF Bloomberg New Energy Finance BTB Back To Back CAPEX Capital Expenditure CCGT Combined Cycle Gas Turbine CEPRI China Electric Power Research Institute CES Central Energy System CHP Combined Heat Power COD Date of commission EES Eastern Energy System EENS Expected of Energy Not Supplied ERC Energy Regulatory Commission ESRI Environmental Systems Research Institute GDP Gross Domestic Product GE General Electric GESP Generation Expansion Simulation Programme GHI Global horizontal irradiation GIS Geographical Information System GTI Global Tilted Irradiation/Irradiance GTM Green Tech Media HPP Hydro Power Plant HV High Voltage HVAC High Voltage Alternative Current HVDC High Voltage Direct Current IEA International Energy Agency IEC International Electrotechnical Commission IRENA International Renewable Energy Agency LCoE Levelized Cost of Electricity MCDA Multi-criteria decision Analysis MoE Ministry of Energy (Mongolia) MNT Mongolian NDC National Dispatching Center (Mongolia) NEA North East Asia NREC National Renewable Energy Corporation (Mongolia) NREL National Renewable Energy Laboratory of the USA NTPG National Power Transmission Grid (Mongolia) NWP Numerical Weather Prediction O&M Operation and Maintenance OCGT Open Cycle Gas Turbine OPEX Operational expenditure PRC People’s Republic of China PV Photovoltaic RES Renewable Energy Source SES Southern Energy System
12
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
TL Transmission Line TPP Thermal Power Plant UA Unit of Account UNESCAP United Nations Economic and Social Commission for Asia and the Pacific USD United States Dollar VSC Voltage Source Converter WACC Weighted Average Cos of Capital WLC Weighted linear combination
13
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
EXECUTIVE SUMMARY
The Module 4 report is focused on Mongolia. The report presents the Strategy on Power de- velopment with the analysis of the electricity sector and the assessment of Renewable poten- tial. The report starts with the descriptions of the current conventional and renewable Power gen- eration fleet, the pipeline of current Power development and the Mongolian existing Energy Policy for 2030. Three planning years are considered for the study presented in the report: 2020 (Target 1), 2026 (Target 2) and 2036 (Target 3). 2030 is added because it corresponds to the target of the “State Policy on Energy 2015-2030. IMPACT ON CONVENTIONAL FLEET WITH ENERGY POLICY (2030) Development of renewable generation has two major impacts on Mongolia power system. Firstly, development of renewable generation will greatly relieve the current tight generation margin and improve power supply reliability. On the other hand, renewable generation, due to its inherent variability and intermittency, will exacerbate the difficulties and increase the com- plexity in operating the power system in Mongolia, extra flexible generation is required to ena- ble the operability of Mongolian power system. Secondly, the development of renewable gen- eration will require significant development and upgrade in Transmission network in Mongolia. This report considers the impact of renewable generation development on conventional gen- eration and also transmission system in Mongolia. In order to assess the impact of renewable generation development on conventional plant under various scenarios, we used the model Generation Expansion Simulation Programme (GESP). GESP is a generation expansion planning tool that minimizes total generation sys- tem costs over the planning horizon taking into consideration of capital investment, emis- sions, renewable energy curtailment, reliability and production costs, as well as technical constraints of different types of generation and also heat demand requirements. Based on the assumption over the next 20 years shown in Module 3 report, Power demand in Mongolia is likely to treble and reach over 4330MW and heat demand to double to 5694Gcal/hour by 2036. The report presents the Power fleet sizing study run assuming no export/import of electricity considering Mongolian Power fleet self-sufficient for the internal de- mand. In the frame of the State Policy on Energy 2015-2030, for meeting government renewable energy target, Renewable generation for Mongolian market consumption will reach 1800MW by 2030, corresponding to 30% of total generation capacity. CO2 intensity falls from 0.40tCO2e/MWh in 2020 to 0.33 tCO2e/MWh in 2036. Significant amount of flexible genera- tion is required to manage renewable generation intermittency and variability as well as in- flexibility of conventional generation as shown in the following table:
14
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
DEVELOPMENT OF RENEWABLE ENERGY IN MONGOLIA FOR EXPORTATION Four scenarios are envisaged for the future development of Renewables in Mongolia focused on both onshore wind power and ground mounted solar photovoltaic (PV): Scenario 0: “minGW” capacity in 2020, connected to Mongolian 220kV power grid, only for Mongolia electricity consumption. The “minGW” capacity refers to the availa- ble connection capacity to current 220kV substations. Scenario 1: + 5GW in 2026, mainly for exportation to neighbouring countries. Scenario 2: + 10GW in 2036 (therefore + 5GW between 2026 and 2036) for exporta- tion to neighbouring countries as well. Scenario 3: +100GW in the long term.
WIND AND SOLAR POWER - POTENTIAL ASSESSMENT
A comprehensive Wind and Solar power potential assessment has been carried out, using accurate wind and solar resource data and robust Geographic Information System (GIS) tool, so as to select suitable sites. In particular, key environmental and regulation constraints have been taken into account in order to remove excluded areas incompatible with future Wind or Solar PV development.
Due to the vast wind and solar resource, a dedicated ranking methodology has been implemented in the GIS tool in order to help select preferred potential areas. The ranking methodology is based on a multi-criteria analysis (Ranking applied only to minimum 10 MW Wind farm (10 km2) and 5 MW Solar PV farm (0, 25 km2) :
. Resource (wind speed and Global Horizontal Irradiation): minimum wind speed 6.5 m/s and GHI 1500 kWh/m2.
. Location of potential development areas (cost driver for installation & O&M):
– Proximity to existing roads (paved or unpaved): access to future sites
– Proximity to cities/villages…: key factor for future Operation & Maintenance (Accommodation of O&M staff)
15
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
– Proximity to railways/train station for Solar PV equipment supply (Wind equipment supply only by trucks)
• Proximity to existing 220 kV substations for Scenario 0 only (maximum 200 km): reduction of grid connection costs (transmission line length)
• Slope of suitable terrains for PV panel installations < 20° The GIS-based Multi Criteria Analysis using Weighted Linear Combination has provided 5 Scores for Wind and Solar PV potential areas. Preferred areas for future development have the highest score (best resource and best location).
Score 5 is only related for 3GW of wind in Western Mongolia and consequently is not appropriate for exportation toward South East of Mongolia. The main results are for Score 4 Wind and Solar preferred areas:
Wind Capacity Solar Capacity
Score 4 Score 4
Scenario 0 Scenario 1 to 3 Scenario 0 Scenario 1 to 3 Capacity GW 21.7 191.6 483.7 1,165.7 2 Area km 4,340 38,324 12,092 29,142 Number of areas 38 223 599 2,574
Score 4 areas in Scenario 0 are located within 20-50km to existing 220kV substations but their available connection capacity is limited to 350-550MW only. In Scenario 1 to 3, the distance to existing 220kV substations is not a criteria because new grid will be required for the massive Transmission of exportation. The study has confirmed the huge potential for both Wind and Solar Power not only for Mon- golia own Renewables development but also for future exportation. For exportation, Umnugovi, Dundgovi and Dornogovi are the best Aimags. Using efficient and reliable technologies (Wind turbines and solar PV modules) able to cope with harsh site conditions, a cost assessment has been carried out (CAPEX & OPEX) only for preferred sites (Score 4) in order to assess 2020, 2026 and 2036 Levelized Cost of Electricity (LCoE).
16
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Cost assessment for Wind Power:
Cost assessment for Solar Power:
Due to the outstanding resource, Wind power is likely to be cheaper than Solar PV in the short and medium term but PV modules and Balance of System improvements expected could bring down Solar PV LCoE in the long term at the same level as Wind power.
IMPACT OF RENEWABLES DEVELOPMENT ON MONGOLIA POWER SYSTEM The impact of renewable generation will also depend on Transmission network configuration and design for large scale renewable generation bases. This report proposed two different design frameworks: quarantined and integrated configurations:
- Under quarantined scheme, renewable generation will be developed in both concentrated and distributed manner. The distributed renewable generation will be connected to the main Mongolian Transmission network, and the large scale renewable energy base
17
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
would be collected and transmitted by dedicated network to the neighboring countries, which are physically segregated from the Mongolian main transmission system. - The integrated scheme is where the renewable generation base is physically connected with the main Mongolian Transmission system.
The renewable generation base will have minimal impact on the Mongolian main system under the quarantined scheme but significant impact under the integrated configuration. This report presented different network configurations for 2020, 2026, 2030 and 2036, including quaran- tined HVDC, and integrated HVDC and HVAC schemes.
18
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
1 OVERVIEW OF MODULE 4
The Module 4 report is focused on Mongolia. The report presents the Strategy on Power de- velopment with the analysis of the electricity sector and the assessment of Renewable poten- tial. The report presents:
- The descriptions of the current conventional and renewable Power generation fleet, the pipeline of current Power development and the Mongolian existing Energy Policy for 2030. - The impact on conventional fleet with energy policy (2030) - The development of renewable energy in Mongolia for exportation - - The wind and solar power - potential assessment The impact of renewables development on Mongolia power system Three planning years will be considered for the study: 2020 (Target 1), 2026 (Target 2) and 2036 (Target 3). 2030 is added because it corresponds to the target of the “State Policy on Energy 2015-2030. Four scenarios will be envisaged for the future development of Renewables in Mongolia fo- cused on both onshore wind power and ground mounted solar photovoltaic (PV): Scenario 0: “minGW” capacity in 2020, connected to Mongolian 220kV power grid, only for Mongolia electricity consumption. The “minGW” capacity refers to the availa- ble connection capacity to current 220kV substations. Scenario 1: + 5GW in 2026, mainly for exportation to neighbouring countries. Scenario 2: + 10GW in 2036 (therefore + 5GW between 2026 and 2036) for exporta- tion to neighbouring countries as well. Scenario 3: +100GW in the long term.
19
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
2 MONGOLIA CURRENT POWER GENERATION
The overwhelm majority of electricity in Mongolia has been generated by coal fired power plant and the remaining by Hydroelectric Power Plants (HPP), diesel, solar and wind power stations. All Mongolian coal fired power plant are Combined and Heat Power Plants (CHPs).
Figure 1 Installed capacity and Electricity generation in Mongolia in 20161
The total installed capacity is 1,245MW in 2016; 84.26 per cent of the capacity is in CHPs, 2.25 per cent is Hydro, 3.69 per cent is diesel and 1.73 per cent is Solar and 8.06 percent is Wind. The installed capacity of Renewable Energy sources (RE), which include Hydro, Solar and Wind, are only 12.3 per cent of the total. CHPs generated 95.75 per cent of a total elec- tricity generated in 2016 and electricity generated by RE remained 4.18 per cent2. Following elements constitute impediment to promote utilization of RE in Mongolia.
Wind: difficulty in raising money, cubs on electricity buying at night time and oth- ers Solar: Low tariffs and others
1 ERC “Statistic book of energy sector” 2017 2 ERC “Statistic book of energy sector” 2017 20
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
2.1 CONVENTIONAL EXISTING POWER PLANTS
Whether the technical analysis will be performed in Module 5: « Grid », this part is assessing the as- sumptions on the technology that would be integrated in the financial business case in order to assess the financial feasibility. On installed-capacity basis, 95.9% of CHPs are located in CES area.
Table 1. CHPs in operation 3
Installed Ca- Available Ca- Location COD pacity (MW) pacity (MW) Grid
CHP #2 21 18 UB CES 1961
CHP #3 198 155 UB CES 1968
CHP #4 683 575 UB CES 1983
Erdenet CHP 36 21 Erdenet CES 1987
Darkhan CHP 48 39 Darkhan CES 1965
Dalanzadgad CHP 9 4.5 South Gobi CES 2000 (South Gobi)
Ukhaakhudag 18 16 Ukhaakhudag CES 2011 CHP (South Gobi)
Sub Total CES 1013 915
Dornod CHP 36 29 Dornod EES 1969
TOTAL 1049 944
Power plants of CHPs are getting older and its efficiency is low. Furthermore, because the coal quality is much below the quality of the design coal for their boilers, most CHPs operate with de-rated capacity4. The CES is unable to generate enough electricity meets the daily demand with its power plants due to their poor peaking capability5. The CES imports electricity from Russia to fill a gap between the demand and electricity generated.
3 ERC, “Statistic of energy sector” 4 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sector of Mongolia” 2013, p.63. 5 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sector of Mongolia” 2013, p.61. 21
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Rehabilitation projects on CHPs have been carried out. Some rehabilitation projects have been implemented on CHP #4 by Japan. Thus facilities of CHP#4 have been improved. However, few rehabilitation projects seem to have been implemented on other CHPs. Power plant con- struction and enhancement plan shown in 3 and some of them are under way.
2.1.1 Coal power plants
On installed-capacity basis, 95.9 per cent of CHPs are located in CES area.
Table 2. CHPs in operation 6
Installed Ca- Available Ca- Location COD pacity (MW) pacity (MW) Grid
CHP #2 21 18 UB CES 1961
CHP #3 198 155 UB CES 1968
CHP #4 683 575 UB CES 1983
Erdenet CHP 36 21 Erdenet CES 1987
Darkhan CHP 48 39 Darkhan CES 1965
Dalanzadgad 9 4.5 South Gobi CES 2000 CHP (South Gobi)
Ukhaakhudag 18 16 Ukhaakhuda CES 2011 CHP g (South Gobi)
Sub Total CES 1013 915
Dornod CHP 36 29 Dornod EES 1969
TOTAL 1049 944
6 ERC, “Statistic of energy sector” p.2. 22
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
2.1.2 Heat generation
There are 11 major heat generation plants. In 2016, total generation amounted up to 8,727.0 thousand Gcal.
Table 3. Heat generation by plant
Name Generated heat % of total (planned site) (thou. Gcal) generation
Dalanzadgad CHP 26.9 0%
Thermal power station in Nalaikh JSC (TPSND) 123.1 1%
CHP #3 196.0 2%
Baganuur Thermal Power Plant JSC (BNTP) 155.8 2%
Amgalan thermal plant state owned Ltd. (ATP) 374.7 4%
Dornod CHP 36 4%
Dalanzadgad CHP 504.8 6%
License Holder in Rural Areas (LH-RA) 646.6 7%
Darkhan CHP 570.0 7%
CHP #2 2,287.6 26%
CHP #4 3532.3 40%
Total 8,727.0 100%
From the above generated heat, 94% (7676.2 thou. Gcal) is distributed as water while the remaining 6% (496.1 thou.Gcal) is distributed as steam7.
7 Energy Regulatory Commission of Mongolia “2016 Statistics on Energy performance” 2016, p. 17
23
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Heat end users are concentrated in major urban areas, such as Ulaanbaatar, Darkhan and Erdenet. These cities consume up to 97.4% of heat generated8. As for consumer classification, Residential consumers use 885 of total generated heat.
2.1.3 Current Mongolia transmission grid
Transmission Line (TL)
Mongolia power network comprises:
4,026 kilometers of Transmission Lines (TLs) of which 1,044 km are 220kV TLs and 2,982km are 110kV TLs. 220kV TLs have been only laid in east part of CES area. 5,824km of Distribution Lines which have been laid in CES area9.
TL between EES and Altai-Uliastai energy system has a capacity of 110kV. TL between CES and Russian is of 220kV.
TL from Ulaanbaatar to Oyutolgoi via Baganuur, Choir and Mandalgobi is made for high- voltage transmission (220kV). TL from Choir to Oyutolgoi is operated in 110kV due to facilities at substations. MOE plans to construct TL with 330kV from Ulaanbaatar to Mandalgobi directly.
TL with 110kV (single circuit, capacity of 80MW) has been laid between Dalanzadgad and Tavantolgoi10.
8 Energy Regulatory Commission of Mongolia “2016 Statistics on Energy performance” 2016, p. 30 9 Energy Charter Secretariat “In-depth review of the investment climate and market structure in the energy sector of Mongolia” 2013, p.61. 10 Our hearing survey
24
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Figure 2 Transmission line in South Gobi 11 Electricity losses
The electricity transmission and distribution losses of CES reached 17.3 per cent12. Because the electricity transmission losses reached approximately 3 per cent, it is seems that the elec- tricity distribution losses were large. In addition to these losses, Power plants of CES use 22 per cent of gross generation for their own use in winter13. The electricity transmission losses of WES reached 21.9 per cent and the distribution losses of WES 17-37 per cent. Total electricity losses in Dornod region in EES reached 8.7 per cent and the losses of Altai-Uliastai energy system are estimated 12 per cent14.
Tariffs and its system
This subsection covers the tariff structure for conventional power source, tariffs for renewa- ble energy sources, Single Buyer Model and the structure of electricity transaction market.
11 National Power Transmission Grid, “NATIONAL POWER TRANSMISSION GRID STATE OWNED STOCK COM- PANY”; Our hearing survey
12 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sector of Mongo- lia” 2013, pp.63-64. 13 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sector of Mon- golia” 2013, p.63. 14 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sector of Mongo- lia” 2013, p.64.
25
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
The movement which considers reduction of and new setting of electricity prices in night time for the purpose of demand boosting in night time, and the movement which increase consumer price for the purpose of subsidy reduction applied to the power sector widely are seen in recent years.
2.2 RENEWABLE EXISTING POWER PLANTS
2.2.1 Hydro power plants
There are nine hydropower plants that are in operation in Mongolia.
Table 4.Hydropower plants (in operation) 15
Name Capacity Grid COD kW
Bogdiin gol 2000 1989
Mankhan 150 1998
Guulin 400 1998
Taishir 11’000 WES 2008
Durgun 12’000 WES 2008 Tsetsen uul 250 2008
Zavkhanmandal 110 2009
Erdenebulgan 200 2006
Tosontsengel 375 2006
Munkhkhairkhan 150
Undurkhangai 200 1989
Uyench 960 2005
Kharkhorin 600
15 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sector of Mongolia” 2013, p.71. 26
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Figure 3 Big Hydropower plants (in operation)
2.2.2 Wind farms
Two wind power plants are in operation in Mongolia.
Table 5. Wind power plants (in operation)
Name Capacity Grid COD MW
Salhkit 50 CES 2013
Tsetsii 50 CES 2017
Four small wind-diesel power plants are in operation.
Figure 4. Existing wind power plants
27
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Table 6.Wind-diesel power plants (in operation)16
Name Capacity Grid COD kW
Erdenetsagaan 100 - 2004
Bogd 80 - 2008
Sevrei 80 - 2008
Khatanbulag 150 - 2008
2.2.3 Ground mounted solar PV farm
Some small ground mounted solar power stations and solar-wind-diesel hybrid power plants are in operation in Mongolia.
Table 7.Solar power station (in operation) 17
Name Capacity Grid COD kW
Noyon 200 - 2004
Tsetseg 100 - 2008
Bugat 140 - 2009
Urgamal 150 - 2010
Durvuljin 150 - 2010
Bayantooroi 100 - 2010
Altai 52.4 - 2010
Matad 60 - 2010
Bayantsagaan 200 - 2011
16 T.TSERENPUREV and J.OSGONBAATAR, “INTRODUCTION OF RENEWABLE ENERGY SECTOR IN MON- GOLIA AND THEIR POLICY ENVIRONMENT”,2012.4
28
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Chinggis Khaan International Airport 443.52 CES 2012
Solar Power International 10,000 CES 2016
Everyday farm 10,000 CES 2017
Table 8.Solar-Wind-diesel hybrid power plants (in operation) 18
Name Capacity Grid COD kW
Manlai 150 - 2008
Tseel 150 - 2008
Shinejist 150 - 2008
Bayan-Undur 150 - 2008
Nalaikh 110 - 2009
Mandakh 200 - 2010
Figure 5 Bid scale Solar power station (in operation)
18 T.TSERENPUREV and J.OSGONBAATAR, “INTRODUCTION OF RENEWABLE ENERGY SECTOR IN MON- GOLIA AND THEIR POLICY ENVIRONMENT”,2012.4
29
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
2.3 PIPELINE OF CURRENT POWER DEVELOPMENTS
2.3.1 Conventional plants
Power plant construction and enhancement plan are shown in the following table. Some of them are under way. Table 9.Expansion projects on CHPs 19 Name Capacity MW Grid COD Status Remarks
Telmen TPP 100 - - Plan Darkhan CHP 35 CES - Construction Extension
Erdenet CHP 35 CES - Plan Extension
CHP #3 2x125 CES - Plan Extension
CHP #5 450 CES - Plan
Baganuur TPP 700 - - Plan
Chandgana TPP 600 - - Plan East region Dornod 50 EES - Plan Extension CHP
Ulaan Ovoo TPP 100 CES 2020 Plan
Tavan tolgoi TPP 450 CES - Plan
Khushuut TPP 12-24 - - Plan
Khotgor TPP 60 WES - Plan
Aduunchuluun TPP 100 EES 2020 Plan
Tevshiin Gobi TPP 600 CES 2020 Plan
Shivee Ovoo TPP 700 CES 2019 Plan
Buuruljuut TPP 600 CES 2020 Plan
19 Ministry of Energy, “Mongolian National Energy Agenda and Policy Measures: Scope for subregional coopera- tion” 2013.4, p.13
30
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Erdenetsogt TPP 600 CES 2020 Plan
Tsaidan TPP 300 CES 2020 Plan
2.3.2 Renewables
2.3.2.1 Hydro
Some construction projects of hydropower plants have been planned. All the project are de- layed and the scheduled starting commercial operation is unclear.
Table 10.Projects of Hydropower plant construction 20
Name Capacity Grid COD Status (planned site) MW
MOE /Egiin HPP 315 CES - F/S done (Khutag-Undur soum, Bulgan)
Tuul-Songinо HPP 100 CES - Planning (Ulaanbaatar City) (pumped storage)
MOE /Shuren HPP (Tsagaannuur 300 CES - Conducting F/S soum, Selenge)
MOE Orkhon HPP (Orkhontuul soum, 100 CES - - Orkhon)
MOE Erdeneburen HPP 64 WES - - (Erdeneburen soum, Khovd)
20 Ministry of Energy, “Existing and planned renewable energy project in Mongolia” 2013.12, pp.24-25; Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sector of Mongolia” 2013, p.71; Our hearing survey with ERC 31
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
2.3.2.2 Wind
These projects of construction of wind power plants have been already planned, excluding Qleantech project21.
Table 11.Projects of Wind power plant construction22
Name Capacity Grid COD Status (planned site) MW
Qleantech 250 CES:102MW - Construction license (since 2008, until 2017) (Khanbogd soum, Umnugovi) China:148MW PPA signed *basic part (102MW)
Sainshand salkhin park 52 CES 2018 Construction license (since 2011, until 2019) (Sainshand soum, Dornogovi) PPA signed *basic part
AB solar wind (Dalanjargalan 100 CES - Construction license (since 2011, until 2016) soum, Dornogovi) PPA signed *basic part
Aydiner Global (Sumber soum, 50.4 CES - Construction license (since 2011, until 2016) Govisumber) PPA signed *basic part
21 Qleantech splits its project into2 stages. Qleantech plans to construct a 102 MW wind power plant as its first step. 22 Ministry of Energy, “Existing and planned renewable energy project in Mongolia” 2013.12, pp.22,34-25; The Japan research Institute, “Global Warming Mitigation Technology Promotion Project Report”, 2014.8., pp.31,49. (in Japanese); Our hearing survey with ERC
32
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
2.3.2.3 Ground mounted solar PV
Some construction projects of solar power stations have been planned23.
Table 12.Projects of Solar power plant construction 24
Capacity Name (planned site) Grid COD Status (MW)
Monwatt (Baganuur) 20 CES
G Power (Baganuur) 15 CES
Uni-Solar (Tuv, Bayandelger) 30 CES
Moshia Eco Energy (Tuv, Sergelen) 50 CES
Tenuungerel Construction (Tuv, 15 CES Sergelen)
Sergelen Solar Power Plant 50 CES
Solaris Solution (Tuv, Sergelen) 10 CES
Luxtium (Tuv, Zuunmod) 9 CES
Infra Structure Network (Tuv, 50 CES Bayanchandman)
Solar Energy Chandmani (Tuv, Bay- 21 CES anchandman)
Sun Step (Govisumber, Choir) 50 CES 2019
ESB Solar Energy (Govisumber, 10 CES 2018 Choir)
Taij Group (Arkhangai) 30 CES
Soldan Energy (Arkhangai) 20 CES
Mon-Korea Engineering(Uvurkhan- 8 CES gai)
Erchis Undarga (Uvurkhangai) 30 CES
Baruun-urt Energy (Sukhbaatar) 10 CES
Khuvsgul Power (Khuvsgul) 3 CES
23 NDC had known only the project of Sainshand Shalkhin Park (our hearing survey with NDC) 24 Ministry of Energy, “Existing and planned renewable energy project in Mongolia” 2013.12, pp.24-25; Our hear- ing survey with ERC
33
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
under cons- Naranteeg (Dornogobi, Zamiin uud) 15 CES 2018 truction
Desert Solar Power One 30 CES (Sainshand)
Smart (Dornogobi, Airag) 20 CES
Sky Natural Energy (Dornogobi, Ai- 30 CES rag)
Solar Ilch (Omnogobi, Khanbogd) 50 CES
More Green (Omnogobi, Khanbogd) 10 CES
Gobi Electric Power (Omnogobi, 50 CES Manlai)
Khuduugiin Tsahilgaan (Gobi-Altai, 4 WES Taishir)
Saisan My Climate LLC (Gobi-Altai, 10 WES Yusunbulag)
MoE (Khovd, Myangad) 10 WES
MOE(Uvs, umnugovi) 10 WES
Durgun Solar Plant (Khovd, Myan- 10 WES gad
Durgun 10 WES
2.3.2.4 Biomass
Use of forest, saksaul, shrubby plant resources for fuel Biomasses are the accumulated and converted forms of energy derived from the sun and are considered to be one type of renewable energy resources. In addition, they are known as natural resources that can produce energy by burning wood, animal droppings, plants, vege- tation etc. Research findings suggest that about 15.2 million hectares of the total territory of Mongolia are covered with forest; and the resource of standing trees equals to 1.2 x 109, cubic meters of which, 80 percent are represented by coniferous and 20 percent - by broadleaved forests. The Gobi region has abundant resources of saksaul, shrubs, and bushes. The family of fuel- producing plants includes all kinds of woody plants, namely, the saksaul, caragana, saltwart wormwood, ceratoides, willows etc. The saksaul occupies a special place among the others.
34
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
It is estimated that 11.3 million hectares or 74.2 percent of the above-mentioned total forest reserves of Mongolia are represented by tree forests, and 3.9 million hectares or 25.8 per- cent – by saksaul forests. The average annual resource of forests per one hectare of trees is approximately 1.32 cubic meters, and that of saksauls - only 0.001 cubic meters. Therefore, it was concluded that there is a very limited possibility of using the Gobi saksauls and shrubs for fuel production purposes. In 2014, the Government of Mongolia approved the Forest Cleaning program25 which is de- signed to clear the forests of fallen and dead trees. Of the tree forested area, 16% or 1.8 mil- lion hectares have fallen and dead trees for a total resource of 64.2 million cubic meters. The aim of the program is to decrease frequency of forest fires and facilitate regeneration and growth of the forested areas. As part of program, the government will support capability building to process the dead and fallen trees into compressed wood boards, compressed wood fuel, constructions materials and other end products. According to government research, there is annual demand of 3.2 million cubic meters of wood and wood materials of which 2.06 million cubic meters is for fuel needs, 0.95 million cubic meters of dried and processed wood are for household usage and 0.18 million cubic meters for compressed wood fuel. Based on the current resource of 64.2 million cubic meters and barring any major increase in demand for wood fuel, Mongolia could potentially source its wood fuel for a period of 20 years on the household level. However, to date there has been no extensive study done to assess the viability of biomass in Mongolia.
Resources from agricultural waste and livestock dung Mongolia has preserved its nomadic lifestyle and ancient tradition to use biomass fuel origi- nated from livestock. It can be considered as a type of renewable energy resources, such as dried cow or horse dung, pellets, and hardened dung or urine of sheep and goats urine, and other types such as straws, woods, shrubs, and biomass waste of urban settlements as the key sources of fuel, especially in the regions with limited or no forest reserves. Dried cow dung is inexpensive fuel source that is easily available all year round in any region of Mongo- lia.
25 Government of Mongolia Resolution #30 of February 7, 2014
35
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Figure 6 Mongolian forest resources
As of 2017, Mongolia had 66.2 million heads of livestock, in other words, she has a consider- able amount of biomass resources originated from livestock. These resources were as- sessed in 2003 as sources of renewable energy. Dried cow dung, the main source of fuel used by households living in the steppe and Gobi desert area of Mongolia is significantly decreasing due to the massive loss of livestock en- countered in recent years. The heat emission capacities of dried cow dung, pellets, horse-dung, and hardened dung and urine of sheep and goats vary subject to seasonal and regional features. The minimum heat emission of dried cow dung is 10800-13300 kJ/kg, horse-dung - 8800 kJ/kg, pellets - 16700 kJ/kg, and hardened dung and urine of sheep and goats - 12500-14600 kJ/kg. (Source: Feasibility study on energy production using biomass resources. TU, 1997) Mongolians call the hardened dung and urine of sheep and goats accumulated over a long period of time as khurzun and it has a good and consistent heat emission capacity.
2.3.2.5 Other renewables
Geothermal energy resources
At present, there are about 43 hot springs in Mongolia, and some of them are utilized in pub- lic health sector. No thorough studies have been undertaken so far in this direction, thus these are only identified and exposed geothermal energy resources of Mongolia hidden in the depth of earth. Mongolians are accustomed to call a hot water fount a hot spring; there- fore we used this term in this document. The resources of hot springs are mostly located in the Altai, Khangai, and Khentii mountain ridges, where infrastructure is poorly developed.
36
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
The priority use of hot springs is a non-drug health treatment. Relevant studies need to be undertaken to explore the potential use of hot springs for the purposes of heating the sanato- riums established around the springs; and for building greenhouses and geothermic power stations based on solar and hot spring energy resources. It can be said that almost no re- search were undertaken so far for the above purposes. According to hydrogeology surveys conducted in hot spring basins, the actual reserves can contain enormous amounts of energy resources. The use of underground hot water as a source of energy is becoming one of the applicable practices across the globe. Experts say that the heat of hot springs can be used for heating purposes with no harm to nature and the environment.
Figure 7. Location of Mongolian hot springs, Source: Study conducted by REC
The central facility of Shargaljuut sanatorium is heated by the surface-exposed fount of the Shargaljuut hot spring. The Shargaljuut hot spring is one of the largest hot springs in Mongo- lia; its exposed water temperature and the speed of its fount flow reaches up to 92oC and 25 l/s, respectively. The Shargaljuut sanatorium operates all year round as it uses the natural flow of the hot spring without relying on any special equipment for its heating. This is a practical example of how the natural energy could be used for producing heat without causing harm to the envi- ronment as well as saving fuel costs. Other sanatoriums in the rural areas operate only during summer as they are based on coal and firewood, which are expensive. This proves the fact that renewable energy resources can be beneficial if used properly and effectively for relevant purposes.
37
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
3 MONGOLIA STRATEGY ON POWER DEVELOPMENT
The State Policy on Energy 2015-203026 is a policy document for implementing measures to improve the legal environment, optimize organizational structure of the sector, utilization of energy resources, constituting fuel reserve, electricity and heat generation and its supply ac- tivities, develop public-private partnership, transform the sector into a regulated competitive market and the capability development of the industry personnel. The policy document sets six different strategic goals for the Mongolian energy sector: 1. Create an integrated energy system that is reliable and flexible with sufficient generat- ing capacity reserve to serve the domestic demand 2. Establish a fair long term agreement on power export and import agreement with neigh- boring countries and implement capability to export wind and solar power to the North- east Asian countries on a large scale 3. Improve the quality of local training for engineers and technicians to match international standards and develop an institution focused on energy economy, energy production, testing and adjustment studies 4. Establish a regulated and competitive market where tariff and pricing system is based on real cost which will allow an appropriate profit level to ensure financial soundness of the sector and encourage private investment in the sector 5. Utilize advanced technology in controlling and supervising energy generation, trans- mission distribution and supply activities and reducing the loss thereof and create a nationwide energy efficiency and savings measures. 6. Reduce adverse environmental impacts of conventional power generation, through le- gal and tax measures, by promoting renewable energy investments to increase the share of renewable energy in total installed capacity up to 20% in 2020 and 30% in 2030. Solar, wind, biomass, liquid and gas fuel, geothermal, fuel cell and other new sources should be utilized for power generation while creating a system where surplus energy could be supplied to the grid.
26 Parliament resolution #63 of June 19, 2015
38
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
The above policy is to be implemented in two stages as summarized below:
Criteria 2014 (baseline) 1st stage: by 2023 2nd stage: by 2030 Reserve margin of -10% No less than 10% No less than 20% electricity generation installed capacity Reserve margin of 3% No less than 10% No less than 15% heat generation in- stalled capacity in ma- jor cities Level of profit in -16.22% 0% 5% electricity tariff of Cen- tral region of Mongolia Own usage of 14.4% 11.2% 9.14% thermal power plants Transmission and 13.7% 10.8% 7.8% distribution loss (ex- cluding Oyu Tolgoi) Share of renewa- 7.62% 20% 30% ble energy capacity of total installed capacity Emission of green- Equal to 0.52 ton Equal to 0.49 ton Equal to 0.47 ton house gases for per CO2 CO2 CO2 Gcal energy genera- tion Amount for reduc- 0% 20% 40% ing building heat loss Introduction of High pressure Subcritical tech- Supercritical and technological advance- technology nology, usage of natu- ultra-supercritical tech- ment ral gas, large capacity nology, hydrogen us- battery storage sys- ing technology, tech- tem, pumped storage nology using solar plant thermal energy Table 13.Mongolia strategy on power development
39
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
4 MONGOLIA EXISTING ENERGY POLICY (2030)
The Mongolian Electricity sector has been unbundled into generation, distribution, transmis- sion and dispatching companies. Electricity is supplied through four regional energy systems. The electricity transaction market is operated in the Central Energy System which is the larg- est energy system in Mongolia and covers Ulaanbaatar and 13 aimags or provinces. In 2015, the Mongolian parliament passed the State Policy on Energy, setting the target for the coun- try’s energy sector goals. Coal-fired power plants generate approximately 90 per cent of total electricity generated in Mongolia but they have many problems; low efficiency due to the facilities aging, large elec- tricity losses in a power plant and poor peaking capability. On the other hand, Renewable en- ergy sources including hydro, wind and solar power sources generated 8 per cent of total electricity. In recent years, many projects to construct renewable energy power plants have been advanced. However, the progress has been generally slower than expected. Coal-fired power plants have sold electricity at a lower tariff than real generation cost follow- ing the guidance of government and the national government has been subsidizing the over- all power sector from the national budget every year.
4.1 ORGANIZATIONS OF MONGOLIAN POWER SECTOR
Figure 8. Overview of related organizations in Mongolian Power sector
40
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
The Ministry of Energy (MOE) is in charge of policy making for this sectors and Energy Reg- ulatory Commission (ERC) is of the regulation of the generation, transmission, distribution, dispatching, and supplying energy. This sector has been unbundled into generation, distribu- tion, transmission and dispatching companies and facilitated privatization of them since new energy law was approved in 2001. And generation, distribution, transmission and dispatching companies have been converted to joint stock corporations. The functions of related organizations are indicated below.
Table 14. Functions of related organizations MOE ● In charge of policy making for energy sector ● The policy area includes the development of energy resources, energy use, the import and export of energy, the construction of power plants, lines and networks, energy conservation, the use of renewable energy sources, the monitoring of the sector, the ap- proval of rules and regulations for the sector and international co- operation ERC ● ERC is an independent regulation authority, self-funded by the li- cense fees and in charge of the regulation of the generation, transmission, distribution, dispatching, and supplying energy ● The main functions are to issue the operational licenses, to re- view and approve the tariffs of the licensees, to protect equally the rights of the consumers and licensees as well as to create condition for fair competition among the generators and suppliers Dispatching ● National Dispatching Center (NDC) is in charge of dispatching ● NDC has been granted a dispatching license by ERC. The Func- tions are permanent control, operative coordination and regula- tion of the voltage in the grid, temperature and pressure of indus- trial stream and water distribution lines ● NDC operates the electricity wholesale market on “Single Buyer Model” monopolistic basis Transmission ● National Power Transmission Grid (NPTG) is in charge of trans- mission ● NPTG is a state-owned stock company conducting the activity in electricity transmission among generators and distribution com- panies, export and import from neighboring country, serves of maintenance, installation, testing, calibration and incidental ser- vices of transmission lines and substations Generation and ● There are 10 electricity generation companies including 2 wind Distribution farm, 2 solar PV and 16 distribution companies ● Even privatization of generation and distribution companies has been facilitated, only Darkhan-Selenge Electricity Distribution Network has been privatized
41
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
4.2 REGIONAL ENERGY SYSTEM
Electricity is supplied through four regional energy systems; Central Energy System (CES), Western Energy System (WES), Eastern Energy System (EES) and Altai-Uliastai Energy System (AUES).
Figure 9. Four Energy System in Mongolia27 CES is the largest energy system in Mongolia. CES covers 13 aimags including big cities such as Ulaanbaatar, Eldenet, and Darkhan. Umnugobi aimag where our site is located is also included in CES. CES has an electricity demand of around 729MW which is equivalent to approximately 95% of the total electricity demand in Mongolia. The total generation capac- ity in CES area is 1049MW28 and the shortage is covered by electricity import from Russia. In this area, developments of Tavantolgoi coal mine and Oyutolgoi copper mine in south Gobi region lead to a larger increase in a demand of electricity29. WES covers Uvs aimag, Bayan-Ulgiy aimag and Khovd aimag with a total electricity demand of 20MW30. EES covers two aimags in eastern part of Mongolia with a total demand of 36MW14. Altai-Uliastai energy system covers Gobi-Altai in Zavkhan Province with a total demand of 13MW14.
27 National Power Transmission Grid, “NATIONAL POWER TRANSMISSION GRID STATE OWNED STOCK COMPANY” 28 ERC “Statistic book of energy sector” 2017. 29 World Bank, “SOUTHERN MONGOLIA INFRASTRUCTURE STRATEGY” 2010, p.56. 30 Energy Charter Secretariat ,“In-depth review of the investment climate and market structure in the energy sec- tor of Mongolia” 2013, p.61.
42
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
CES has been connected with EES, Altai-Uliastai energy system and Russian electricity net- work. Transmission Line (TL) between EES and Altai-Uliastai energy system is a capacity of 110kV31. TL between CES and Russian is of 220kV.WES is also connected Russian electric- ity network32. About 7.4 per cent of the electricity is imported from Russia. One industrial mine in south part of Mongolia directly imports electricity from China33. Because CES has approximately 95% of the total electricity demand in Mongolia and Um- nugobi aimag where our site is located is also included in CES, Power generation, transmis- sion and, Tariffs and its system in CES are described as follows.
Tariffs
Tariff structure for conventional power source
Tariffs are determined separately for each licensed activity by ERC; generation, transmis- sion, distribution, dispatch and supply. The law of Mongolia on energy regulates the following principles for setting tariffs34.
● tariffs should be based on real costs of operations ● costs should be allocated to different consumer categories to their requirements on elec- tricity and heat supply ● tariffs should enable regulation of energy consumption ● tariffs should ensure price stability ● tariffs should ensure that revenues of licensees are sufficient to support their financial viability ● the tariff structure for electricity and heat should be clear and understandable for consum- ers
The Consumer prices are shown below.
31 National Power Transmission Grid, “NATIONAL POWER TRANSMISSION GRID STATE OWNED STOCK COMPANY” 32 CEA, “THE ENERGY SECTOR IN MONGOLIA” p.2. 33 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sec- tor of Mongolia” 2013 34 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sec- tor of Mongolia” 2013, pp.55-56.
43
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Table 15.The electricity prices for ordinary household35 Type Unit Price (VAT excluded)
1. Single A Monthly usage within 150 kWh MNT/ kWh 110.3 meter B Monthly usage over 150 kWh MNT/ kWh 130.1
2. Double A Daytime (06:00-21:00) MNT/ kWh 116.2 meter (hourly) B Night time, midnight (21:00- MNT/ kWh 89.0 06:00)
C Basic charge MNT/month 2,000.00 Type Unit Usage
3. Fixed Ordinary household kWh Avg. monthly usage price (no meter) within 350
Table 16.The electricity prices for enterprises36 Type Unit Price (VAT excluded)
1. Mine, processing plant
(mining and processing/ refinement of coal, petroleum, gas, iron, other mineral)
1.1 Normal meter MNT/kWh 167.8
1.2 Triple meter (hourly)
a Daytime (06:00-17:00) MNT/kWh 167.8
b Nighttime (17:00-22:00) MNT/kWh 287.9
c Midnight (22:00-06:00) MNT/kWh 89.0
2. Ordinary corporation, factory, legal entity
2.1 Normal meter MNT/kWh 140.4
2.2 Triple meter (hourly)
35 Energy Regulatory Commission tariff set as of July 31, 2017 36 Energy Regulatory Commission tariff set as of July 31, 2017
44
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
a Daytime (06:00-17:00) MNT/kWh 140.4
b Nighttime (17:00-22:00) MNT/kWh 221.7
c Midnight (22:00-06:00) MNT/kWh 89.0
2.3 Electric trolleybus MNT/kWh 89.00
3. Street and public area lighting in Ulaanbaatar or aimag center
3.1 October-March
a Daytime (06:00-19:00) MNT/ kWh 140.4
b Night-time (19:00-06:00) MNT/ kWh 89.0
3.2 April-September
a Daytime (06:00-22:00) MNT/ kWh 140.4
b Nighttime, midnight(22:00-06:00) MNT/ kWh 89.0
ERC reviews and approves the tariffs of the licensees, and develop and publish tariff deter- mination methodology and procedures for review and examination of tariffs37. According to the law of Mongolia on energy, the tariffs shall be based on the real cost of operation. However, it is pointed out that CHPs have sold electricity at a lower tariff than real generation cost following the guidance of government38. Subsidy from government applied to the power sector widely (method of determination of subsidy is shown in figure below). In the 2015 Gov- ernment Budget, subsidies amount 200.5 billion MNT which is equivalent to 46.8% of total expenditures in energy sector (428.5 billion MNT). There was a plan to introduce a so-called “indexation” method for tariff setting to take into ac- count inflation of cost component39. Mongolian energy sector will start to operate under mar- ket prices from 2014 based on parliament regulation N72 approved in 2010. However, noth- ing started in 2014. The movement which considers reduction of and new setting of electricity prices in night time for the purpose of demand boosting in night time, and the movement which increase con- sumer prices for the purpose of subsidy reduction applied to the power sector widely are seen in recent years40.
37 The Law of Mongolia on Energy, Article 9.1.4 38 The Japan research Institute, “Global Warming Mitigation Technology Promotion Project Report”, 2014.8., p.23. (in Japanese) 39 Asian Development Bank, “ENERGY SECTOR POLICY REVIEW”, Mongolia: Updating the Energy Sector De- velopment Plan, 2013.9., p.18.
45
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Figure 10. Procedure for Approval of Tariffs 41
Tariffs for renewable energy sources
Tariffs for renewable energy sources have been regulated by the Law on Renewable Ener- gies. ERC shall set tariffs of energy generated and supplied by renewable energy source connected to a grid within the tariff range shown in the following table. For energy of gener- ated and supplied by independent renewable energy power source, regulatory boards of aimags and the capital city shall also set tariffs within the tariff range shown in the following table. The Mongolian government revised the Law on Renewable Energies in July 2015, but the tariffs for the electricity from renewable energy sources remain the same.
41 Source: prepared by author base on various materials
46
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
Table 17. Tariffs for the electricity from Renewable Energy plants42
Source Type Capacity Tariff range (USD/kWh)
~ Solar Grid-connected 0.150 0.180 ~ Independent 0.200 0.300 ~ Wind Grid-connected 0.080 0.095 ~ Independent 0.100 0.150 Hydro Grid-connected ~ 5,000kW 0.045~0.060
Independent ~ 500kW 0.080~0.100
501 ~ 0.050~0.060 2,000kW
2,001 ~ 0.045~0.050 5,000kW
According to the Law on Renewable Energies, a transmission licensee shall purchase elec- tricity supplied by a generator at tariffs approved43. In Salhkit wind farm case, however, NDC sometimes restricted supply of electricity for the purpose of mitigation a negative impact on CES in nighttime44.
42 The Law on Renewable Energies
43 The Law on Renewable Energies, Article8 44 In the CES, a nighttime electricity demand is often smaller than a nighttime electricity generation. In that case, NPTG sells electricity to the Russian network at 1.5cent/kWh which is lower than generators’ tariffs. Continu- ous purchase of electricity generated from renewable energy sources will only compound NPTG’s losses dur- ing night-time.(our hearing survey)
47
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
4.3 SINGLE BUYER MODEL
In the CES, the electricity transaction market is operated with Single Buyer Model (SBM) in which one organization buys electricity from generators and sells to distributors45. SBM has been implemented since 2002. In the CES, the Single Buyer is NPTG, which purchases electricity from 10 generating com- panies at regulated tariffs and through imports from Russia and sells it to 16 electricity distri- bution companies at the regulated tariff46.
Figure 11. Participants of Single Buyer Model in CES47
The Special condition of SBM in the CES is that ERC approved the Cash flow regulation as a main principal of SBM48. In the CES, payments from consumers are collected into the “Zero balance” account of distribution companies and further collected into the “Zero balance” ac- count of NTPG. Then according to the predefined formula and coefficients, payments are dis- tributed to generating companies49. Spot and auction market also have been in place in the CES since 2005 and 2007. The regu- lator is NDC.
45 SBM has been in place in developing countries. Ganjuur Radii et al., “EVOLUTION OF THE POWER MAR- KET STRUCTURE IN MONGOLIA” 2005, p.8. 46 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sec- tor of Mongolia” 2013, p.64.; Ganjuur Radii et al., “EVOLUTION OF THE POWER MARKET STRUCTURE IN MONGOLIA” 2005, p.5. 47 National Power Transmission Grid Web site
48
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
SBM is a transition operational model for Mongolia. ERC plans to develop necessary rules and regulations to transit to a new electricity market structure50.
5 IMPACT ON MONGOLIAN CONVENTIONAL FLEET WITH EN- ERGY POLICY 2030
5.1 TARGETS
Four planning years are considered for the study. They are: 2020 (Target 1), 2026 (Target 2), 2030 and 2036 (Target 3). 2030 is related to “State Policy on Energy 2015-2030. We assume the Mongolia na- tional peak demand will reach 3470MW (total consumption 20000GWh, see Module 3 report: Assump- tions for studies §2.2.2) and renewable generation increases to 30% of installed generating capacity.
The study is run assuming no export/import of electricity considering Mongolian Power fleet self-suffi- cient for the internal demand.
For each planning year, GESP is run twice to assess the impact on conventional generation and identify requirements of conventional and also flexible generation. Results are described below.
Methodology for analyzing Mongolian generation system with GESP model In order to assess the impact of renewable generation development on conventional plant un- der various scenarios, we used Generation Expansion Simulation Programme (GESP) which is used by State Grid Corporation of China for generation expansion planning purposes. GESP is a generation expansion planning tool that minimizes total generation system costs over the planning horizon taking into consideration of technical constraints of different types of generation. It can be used to study the expansion planning of coal, gas, nuclear, hydro and renewable generation.
Firstly, GESP is used to assess the conventional generation requirement assuming 100% of renewable generation integration from economic and security of supply point of view. This will identify the amount of conventional plant that needs to be built in order meet rising demand with assumed amount of renew- able generation. Secondly, using the results obtained in the above step, GESP is re-run, considering operational and technical constraints of existing and new conventional plant, such as ramp rate, minimal on-grid time and minimal off-grid time, minimal output, etc. This will identify requirements of additional flexible gen- eration required to operate the system with intermittent renewable generation.
The optimisation objectives and constraints factos are given below : Objective function of GESP. The objective of GESP is to minimize total costs over the period of the planning horizon. Its objective function is described as follows
50 Energy Charter Secretariat, “In-depth review of the investment climate and market structure in the energy sector of Mongolia” 2013, pp.66. 49
EDF ELECTRICITE DE FRANCE – with a capital of 1 006 625 696.50 euros – TA-9001 MON: Strategy for Northeast Asia Power System Interconnection
552 081 371 R.C.S. Paris EDF References: CIST – DCO – PhL – 18 - 208 www.edf.fr
Module 4 report on Mongolia Energy Sector Profile and Projections
(1) Where � : ∑ = � + ∑ = ∑ = � + ∑ = ∑ = � + ∑ = � +