M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 1

M6 JUNCTION 10 Design and Access Statement

August 2017 1 | M6 Junction 10 – Highways Improvements Design and Access Statement

Contents

1. Introduction 5. Design of Development

1.1. Purpose of the Document ... 2 5.1. Introduction ... 10 1.2. Background and Introduction to Development ... 2 5.2. Design / Scheme Evolution ... 10 Introduction to M6 and J10 ... 2 Do-nothing alternative ... 10 Brief introduction of the development ... 2 Do-minimum alternative ... 10 1.3. Application Material ... 3 Strategic alternatives ... 10 Local alternatives ... 10 Design Alternatives ... 11 Design Selection Process ... 12 5.3. Proposed Development ... 13 2. Site Context 5.4. Use and amount ... 13 Scale ... 13 2.1. Location and Description ... 4 Layout ... 13 2.2. Site Movement and Access ... 4 Highway Alignment ... 17 2.3. Surrounding Uses ... 4 Structures ... 17 2.4. Site Analysis ... 5 Junction Strategy and Traffic Signalling ... 19 Heritage ... 5 Lighting Gantries and Signage ... 19 Ecology and Vegetation ... 5 Drainage ... 20 Flood Risk ... 5 Construction Compounds ... 20 2.5. Site Photos ... 6 5.7. Site Visuals ... 21

3. Planning Policy Context 6. Landscaping

3.1. Introduction ... 7 6.1. Proposed Landscaping ... 24 3.2. Planning Policy Matrix ... 7 Highway Verges within the Roundabout ... 24 Motorway Approaches ... 24 Central Reservations ... 24 6.2. Landscape Plans ... 25 4. Consultation and Engagement 7. Access Statement 4.1. Introduction ... 9 4.2. Statement of Community Involvement ... 9 7.1. Introduction ... 29 Pre-Application Meetings with Local Planning Authority (LPA) ... 9 7.2. Vehicle Access ... 29 Public Consultation ... 9 7.3. Pedestrian and Cycle access ... 29 7.4. Public Transport ... 29

8. Summary and Conclusion

Summary and conclusion ... 30 M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 2

1. Introduction

1.1. Purpose of the Document This Design and Access Statement (DAS) has been The DAS is submitted as part of the planning throughout 2012 on the existing bridges of M6 J10 Brief introduction of the development prepared by Mott MacDonald to accompany a application and is split into 7 sections as set out which indicated signs of ongoing deterioration. The The proposed development seeks to improve planning application by Metropolitan below: resulting Inspection Report suggested replacement highway capacity and reduce vehicle delays Borough Council (WMBC) and Highways England of both bridges would be required within 3 to 4 years through the construction of new widened bridges, (the ‘Applicants’) for highway improvements to Section 1 – Introduction; of 2012. More recent inspections undertaken by HE, improvements to the junctions slip roads, Junction 10 of the M6 motorway (‘M6 J10’ hereafter). however have not indicated further appreciable Section 2 – Site and Local Context; installation of traffic signals, widening of the nearby The scheme is a response to the significant bridge deterioration of the infrastructure but there remains Bloxwich Lane Junction, modifications to part of replacement requirements, congestion issues and Section 3 – Planning Policy Context; a pressing need to replace the bridges to avoid the Black Country Route along with associated capacity constraints at M6 J10 which are impacting Section 4 – Consultation and Engagement; any future ad-hoc maintenance interventions landscaping and other complimentary works. The the strategic and local highway network. from impacting the operation of the highway main objectives of the scheme are to: Section 5 – Design of Development; infrastructure. The document is provided in accordance with Section 6 – Landscaping; • Provide a more free-flowing network; Section 62(5) of the Town and Country Planning Act Vehicle usage of the junction has developed Section 7 – Access Arrangements; and • Support economic growth; and 1990 (as amended) which requires that a statement M6 J10 into a strategic interchange between is provided regarding the design principles and Section 8 – Summary and Conclusions the M6 motorway, the Black Country Route and • Provide a safe and serviceable network with concepts that have been applied to the development Road West. improved access. and how issues relating to access have been dealt with. The DAS sets out the design process of the 1.2 Background and proposed development principles and how good Figure 1.1: Existing layout of M6 J10 quality design has been integral throughout the Introduction to Development schemes evolution. Introduction to M6 and J10 M6 J10 forms part of the Walsall to Stafford Link An application is submitted to Walsall Metropolitan and has experienced an increase in traffic flows and Borough Council as the Local Planning Authority and vehicle usage since the beginning of its operation. the full development descriptions is as follows: This is due to an increase in vehicle usage and the development and alteration of land uses in the “Planning application for two replacement wider locality which access the motorway via this junction. bridges over the M6 Motorway and a package of The Black Country Route opened in the early 1990s highway improvements comprising, enhanced and has assisted with unlocking development op- motorway slip roads, installation of traffic signals, portunities in Walsall and improving accessibility for widening of the Junction of A454 and Tempus local residents. Drive Bloxwich Lane, modifications to the Black Country Route, landscape works and associated This has led to further increased vehicle usage of infrastructure and engineering works.” the junction which has developed into a strategic interchange between the M6 motorway, the Black Country Route, and Wolverhampton Road West.

The junction now suffers from capacity issues resulting in vehicle congestion and delays along the strategic highway network. In tandem with this, the existing structures at the junction are in need of urgent repair. HE carried out a host of inspections Source: Highways England (2017) 3 | M6 Junction 10 – Highways Improvements Design and Access Statement

1.3. Application Material

Reference Title Much of the detailed analysis of the site and its constraints has been considered in the submitted Details Environmental Statement (ES). The ES reports the findings of an Environmental Impact Assessment (EIA) Site Location Plan MP/M6J10/LAND-04 Rev 9.0 1:2000 @ A1 of the scheme and provides analysis on topic areas including design alternatives, air quality, noise and vibration, landscape and visual impact, materials, and ecology and nature conservation. Existing Site Plan HE551484-MMSJV-GEN-000-DR-CH-00001 Rev P01.3 1:2500 @ A1

The full suite of documents comprising the application is as follows: Engineering Plans and Drawings Planning Application Detail Plan HE551484-MMSJV-HAC-000-DR-Z-00100 Rev P01.5 1.2500 @ A1 • Environmental Statement prepared by Mott MacDonald: – Layout Plan • Volume I: Main Statement Planning Application Detail Plan HE551484-MMSJV-HAC-000-DR-Z-00101 Rev P01.4 1:500 @ A1 (Sheet 1 of 7) • Volume II: Technical Appendices Planning Application Detail Plan HE551484-MMSJV-HAC-000-DR-Z-00102 Rev P01.4 1:500 @ A1 (Sheet 2 of 7) • Volumes II: Figures Planning Application Detail Plan HE551484-MMSJV-HAC-000-DR-Z-00103 Rev P01.4 1:500 @ A1 • Planning Statement prepared by Mott MacDonald; (Sheet 3 of 7) • Design and Access Statement prepared by Mott MacDonald; Planning Application Detail Plan HE551484-MMSJV-HAC-000-DR-Z-00104 Rev P01.4 1:500 @ A1 (Sheet 4 of 7) • Flood Risk Assessment prepared by Mott MacDonald; Planning Application Detail Plan HE551484-MMSJV-HAC-000-DR-Z-00105 Rev P01.4 1:500 @ A1 (Sheet 5 of 7) • Heritage Statement prepared by Mott MacDonald; Planning Application Detail Plan HE551484-MMSJV-HAC-000-DR-Z-00106 Rev P01.4 1:500 @ A1 • Health Impact Assessment prepared by Mott MacDonald; (Sheet 6 of 7) Planning Application Detail Plan HE551484-MMSJV-HAC-000-DR-Z-00107 Rev P01.4 1:500 @ A1 • Arboricultural Report prepared by Mott MacDonald; (Sheet 7 of 7) • Water Quality Report prepared by Mott MacDonald; Planning Application Typical HE551484-MMSJV-HAC-000-DR-CH-00001 Rev P01.5 1:2500 @ A1 Sections Plan Layout • Climate Change Risk Assessment prepared by Mott MacDonald; Planning Application Typical HE551484-MMSJV-HAC-000-DR-CH-00002 Rev P01.4 NTS @ A1 • Construction Management Strategy prepared by Mott MacDonald and Highways England; Sections (Sheet 1 of 4) Planning Application Typical HE551484-MMSJV-HAC-000-DR-CH-00003 Rev P01.4 NTS @ A1 • Application Plans and Drawings as shown adjacent: Sections (Sheet 2 of 4) Planning Application Typical HE551484-MMSJV-HAC-000-DR-CH-00004 Rev P01.3 NTS @ A1 Sections (Sheet 3 of 4) Planning Application Typical HE551484-MMSJV-HAC-000-DR-CH-00005 Rev P01.4 NTS @ A1 Sections (Sheet 4 of 4) Pedestrian and Cycle Routes HE551484-MMSJV-GEN-000-DR-CH-00002 Rev P01.3 NTS @ A1

Site Clearance HE551484-MMSJV-HSC-000-DR-CH-00001 Rev P01.8 1:2500 @ A1

Landscape Planting Plan (1) HE551484-MMSJV-ELS-RDBT-DR-LE-00001 Rev P01.8 1:1000 @ A1

Landscape Planting Plan (2) HE551484-MMSJV-ELS-RDBT-DR-LE-00002 Rev P01.8 1:1000 @ A1

Landscape Planting Plan (3) HE551484-MMSJV-ELS-RDBT-DR-LE-00003 Rev P01.9 1:1000 @ A1

Landscape Planting Plan (4) HE551484-MMSJV-ELS-RDBT-DR-LE-00004 Rev P01.9 1:1000 @ A1 M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 4

2. Site Context

2.1. Location and Description 2.2. Site Movement and Figure 2.1: Site Location Plan Access The M6 is a north-south motorway linking Rugby at Junction 19 of the M1, to Carlisle where the The M6 is a north-south motorway linking Rugby at motorway ends at the A74 (M). Junction 10 of the M6 Junction 19 of the M1, to Carlisle where the motorway has various connections comprising the A454 Black ends at the A74 (M). M6 J10 has various connections Country Route, A454 Wolverhampton Road, B4464 comprising the A454 Black Country Route, A454 Wolverhampton Road West and Bloxwich Lane. The Wolverhampton Road, B4464 Wolverhampton junction provides a primary access route between Road West and Bloxwich Lane. The junction Walsall, Wolverhampton, and the M6 Motorway, provides a primary access route between Walsall, forming a key interchange within the West Midlands Wolverhampton, and the M6 Motorway, forming a key region. interchange within the West Midlands region.

The application site is located wholly within the The M6 motorway is a strategic highway network, administrative boundary of Walsall Council and a carrying more than 100,00 vehicles each day. Since detailed red line plan illustrating the application site 2011 the M6 J8 to 10a (which includes the section boundary is provided at Figure 2.1. through junction 10) has operated as a smart motorway with all-lane running (four lanes in each The M6 motorway is a strategic highway network, direction). M6 J10a to 13 has subsequently also been carting more than 100,00 vehicles each day. Since upgraded to a similar operating regime. 2011 the M6 J8 to 10a (which includes the section through junction 10) has operated as a smart motorway with all-lane running (four lanes in each direction). M6 J10a to 13 has subsequently also been 2.3. Surrounding Uses upgraded to a similar operating regime. Surrounding uses in the immediate context of the scheme include a mixture of housing and hotel to At present the standards of the junction are varied. the north-west of the site whilst to the north-east To the west of the junction is the A454 Black Country is a row of dwellings along a truncated section of Route, a dual carriageway with grade separate Wolverhampton Road, a church, and the Maple junctions. To the east of the junction is the A454 Leaf and Bloxwich Lane Industrial Estates. Towards Source: Walsall Council (2017) Wolverhampton Road, a dual carriageway that the south-east, the surrounding uses comprise passes through residential areas of Walsall. Also hotels, two vacant development sites and Alumwell to the west of the junction is the B4464, a single Business and Enterprise College alongside playing lane road that passes through the residential fields. Land to the south-west includes retail outlets, area of Bentley. Bloxwich Lane feeds off the A454 industrial units at Longmore Avenue and housing Wolverhampton Road immediately east of the M6 J10 along Bentley Mill Lane. via a standard junction 5 | M6 Junction 10 – Highways Improvements Design and Access Statement

2.4. Site Analysis Landscape Character A Heritage Statement prepared by Mott MacDonald Ecology and Vegetation The majority of trees located on the site are situated The proposed site is located between the is submitted as part of the application and assesses Rough Wood Chase and Rough Wood Local Nature north-east of the roundabout. A Tree survey has settlements of Walsall (to the east) and Bentley (to the impacts on any heritage assets within a distance Reserves (LNRs) are statutory designated sites and been conducted by Mott MacDonald which confirms the west) and is approximately 12km to the north of 200m from the scheme area. The assessment are located 1.2km and 1.7km north of the application that the tree groups on site are mainly of low of west of Birmingham City Centre. This section of confirms that the heritage assets relevant to the site. They are connected to the scheme by plantation arboricultural value but may provide valuable the M6 is located within a green corridor and is scheme are the nearby of the Walsall and woodland along the motorway embankment. screening and landscape for the existing M6. lined with large scale industrial and commercial and the Bentley Canal (see Figures 2.2 and 2.3) However, due to the distance from the site, no direct units as well as a number of primary and secondary Both are non-designated heritage assets and or indirect adverse impacts are anticipated from the Flood Risk schools. Hotels are also located along, and accessed therefore have no statutory protection. However, scheme. A review of the Government’s flood risk tool ‘Flood via, the slip roads that lead of Junction 10. As part these have been identified as having a degree Map for Planning’ confirms that most of the site of the wider landscape, the area comprises 1950s significance meriting their consideration in planning There are four non-statutory designated sites which falls within Flood Zone 1 and therefore has a low- residential properties which are located both east decisions. are within, overlap or directly adjacent to the site. probability risk of flooding. However, part of A454 and west beyond the schools and commercial units. All four sites are of high conservation value and Wolverhampton Road, just east of the Bloxwich Lane The Anson Branch is currently disused. Shallow comprise: Junction, is situated in Flood Zone 3 and therefore The area predominantly consists of highways stretches of water remain in some parts of the has a high probability of flooding. infrastructure, which comprises the M6 motorway branch, but these stretches of water are interspersed • Anson Branch Canal SLINC and A454 Black Country Route. Mature deciduous by expanses of water reeds and abandoned refuse. • Anson Road SLINC A Flood Risk Assessment supporting the application tree planting provides extensive screening from the The majority of the branch has been left dry and is confirms that the scheme will upgrade the existing motorway for the surrounding settlements, and even overgrown by dense vegetation. • Wolverhampton Road SLINC water drainage system and the existing flood risk on when screen planting is considered, the site and its • Moorside Gardens SLINC site, from both fluvial and surface water, is expected environs lacks tranquillity. The Bentley Canal is also disused, having been to be reduced upon completion of the works. closed in 1960s and filled in along the entire route An Assessment on the Landscape and Visual Impact expect for a very short section in Wolverhampton. Figure 2.2: Bentley Canal filled in and used as allotments Figure 2.3: Anson Branch Canal to the immediate north-east is provided in Chapter 7 of the Environmental The part of the Bentley Canal which falls within the of M6 J10. Statement and confirms that the site consists of study area has been infilled and used as allotments a mixture of modern residential and urban fringe, or incorporated into open green spaces amongst large scale commercial. The landscape character residential streets and industrial estates. is therefore not rare locally nor nationally and can easily be replaced. The landscape condition The assessment confirms that, if present, any within the study area is also fragmented and mixed. remaining historic fabric would assign evidential Well-maintained housing and residential streets value to the canals. Combined with their historic are found adjacent to patches of derelict land value through the connection with the wider or highway infrastructure. For these reasons, the Birmingham Canal Network, this may conclude a landscape character is considered as having a low medium heritage significance being assigned to sensitivity to change. both assets. However, this is offset by the expansive development, comprising of the M6, and industrial Heritage and residential estates surrounding both. This A review of Historic England’s online listing tool has resulted in the historic and evidential value has been undertaken and confirms that there being compromised by poor preservation and non- no statutorily listed buildings within the site’s sympathetic development. As a result the Anson boundary. The site is also not located within any Branch and Bentley Canal have been assigned low designated sites such as a Conservation Area or heritage significance, and it is considered that their Historic Park and Garden. settings do not contribute to their significance.

Source: Mott MacDonald (2017) Source: Mott MacDonald (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 6

2.5. Site Photos

Source: Mott MacDonald (2017) 7 | M6 Junction 10 – Highways Improvements Design and Access Statement

3. Planning Policy Context

3.1. Introduction 3.2. Planning Policy Matrix Policy Description Walsall Unitary Development Plan (UDP) 2005 ‘Saved Policies (February 2011) Section 38(6) of the Planning and Compulsory The DAS has taken into consideration the relevant design and landscape policies. Policy ENV32 – Design and a) Poorly designed development or proposals which fail to Purchase Act (2004) requires that proposals are A summary of these are provided in the planning policy matrix below and further Development Proposals properly take account of the context or surroundings will not determined with the development plan unless detail relating to planning policy can be found in the accompanying Planning be permitted. This policy will be applied to all development but material considerations indicate otherwise. The Statement: will be particularly significant in the following, amongst others, development plan comprises those planning locations: documents which have been the subject of iv. Within or adjacent to transport corridors, including canals, examination in public or testing through public Policy Description railways, motorways and major roads. inquiry, and are adopted having been through due Black Country Core Strategy (February 2011) b) When assessing the quality of design of any development process. proposals the Council will use some or all of the following Policy ENV3 – Design Quality • Development proposals across the Black Country will deliver a criteria: successful urban renaissance through high quality design that The application site falls wholly within the stimulates economic, social and environmental benefits by i. The appearance of the proposed development; administrative boundary of Walsall Metropolitan demonstrating that the following aspects of design have been ii. The height, proportion, scale, and mass of proposed Borough Council and the relevant statutory addressed through Design and Access Statements reflecting buildings / structures; their particular Black Country Context: iii. The materials proposed for buildings, external spaces, and development plan comprises the following means of enclosure; documents: • Implementation of the principles of “By Design” to ensure the iv. The integration and co-ordination of buildings and external provision of a high-quality network of streets, buildings and space; • Black Country Core Strategy (February 2011); and spaces; v. Community safety and security; • Implementation of the principles of “Manual for Streets” to vi. The visual relationship of the proposed development • Walsall Unitary Development Plan (UDP) 2005 ensure urban streets and spaces are designed to provide with adjacent areas, the street and the character of the ‘Saved’ Policies (February 2011); a high quality public realm and an attractive, safe and surrounding neighbourhood; permeable movement network; vii. The effect on the local character of the area; viii. The proposed vehicular and pedestrian circulation In addition to the Statutory Development Plan, • Use of the Building for Life criteria for new housing patterns; developments, to demonstrate a commitment to strive for the ix. The integration of existing natural and built features of applications should be assessed against the highest possible design standards, good place making and value; National Planning Policy Framework which is a sustainable development, given local circumstances x. The maintenance requirements of the development. material consideration in any determination. • Meeting Code for Sustainable Homes Level 3 or above for Policy ENV33 – Landscape a) Good landscape design is an integral part of urban design and residential development and Building Research Establishment Design the Council will require, where appropriate, planning applications Environmental Assessment Method (BREEAM) Very Good or proposing development in the locations described in policy above for other development, or the national requirement at ENV32 to be supported by full details of external layout and the time of submitting the proposal for planning permission, landscape proposals to demonstrate a commitment to achieving high quality b) In addition, development proposals meeting any of the sustainable design; following criteria will also be required to be supported by full • Consideration of crime prevention measures and Secured By details of external layout and landscape proposals: Design principles. • Land which the Council is expected to adopt. • Including design features to reduce the urban heat island • Development sites containing natural and built features the effect such as tree cover, green roofs and the inclusion of Council requires to be retained or enhanced. green space in development. • Residential / nursing homes where residents would benefit from the sensory stimulation provided by a landscape scheme and who are not in a position to secure it for themselves. • Larger development proposals.

Policy ENV34 – Public Art The Council will require the provision of public art to enhance the quality and individuality of existing buildings, spaces or new development especially in the following locations: i. In public spaces and buildings ii. In important and prominent locations iii. In larger scale development or refurbishments M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 8

Policy Description

Policy Description National Planning Policy Framework (March 2012) Core planning principles Always seek to secure high quality design and a good standard Walsall Unitary Development Plan (UDP) 2005 ‘Saved Policies (February 2011) Section 7 – Requiring good of amenity for all existing and future occupants of land and Policy ENV32 – Design and a) Poorly designed development or proposals which fail to design (paragraphs 56 to 68) buildings; Development Proposals properly take account of the context or surroundings will not be permitted. This policy will be applied to all development but The government attaches great importance to the design of the will be particularly significant in the following, amongst others, built environment. Good design is a key aspect of sustainable locations: development, is divisible from good panning, and should contribute positively to aiming places better for people. iv. Within or adjacent to transport corridors, including canals, Planning Policies and decision should aim to ensure that railways, motorways and major roads. developments: b) When assessing the quality of design of any development a) will function well and add to the overall quality of the proposals the Council will use some or all of the following area, not just for the short term but over the lifetime of the criteria: development; i. The appearance of the proposed development; b) establish a strong sense of place, using streetscapes and ii. The height, proportion, scale, and mass of proposed buildings to create attractive and comfortable places to live, buildings / structures; work and visit; iii. The materials proposed for buildings, external spaces, and means of enclosure; c) optimise the potential of the site to accommodate iv. The integration and co-ordination of buildings and external development, create and sustain an appropriate mix of uses space; (including incorporation of green and other public space as v. Community safety and security; part of developments) and support local facilities and transport vi. The visual relationship of the proposed development networks; with adjacent areas, the street and the character of the d) respond to local character and history, and reflect the identity surrounding neighbourhood; of local surroundings and materials, while not preventing or vii. The effect on the local character of the area; discouraging appropriate innovation; viii. The proposed vehicular and pedestrian circulation patterns; e) create safe and accessible environments where crime and ix. The integration of existing natural and built features of disorder, and the fear of crime, do not undermine quality of life value; or community cohesion; and x. The maintenance requirements of the development. f) are visually attractive as a result of good architecture and Policy ENV33 – Landscape a) Good landscape design is an integral part of urban design and appropriate landscaping. Design the Council will require, where appropriate, planning applications Supplementary Planning Documents (SPDs) proposing development in the locations described in policy ENV32 to be supported by full details of external layout and Designing Walsall Supplementary Planning Document (February 2008 – amended July 2013) landscape proposals Policy DW1 – Sustainability New development should seek to simultaneously meet b) In addition, development proposals meeting any of the environmental, economic and community needs without following criteria will also be required to be supported by full comprising the needs of future generations. details of external layout and landscape proposals: Policy DW2 – Safe and All new development must contribute towards creating places • Land which the Council is expected to adopt. Welcoming Place that feel safe, secure and welcoming for everyone. • Development sites containing natural and built features the Policy DW3 – Character All new development must be designed to respect and enhance Council requires to be retained or enhanced. local identity. Policy DW5 – Ease of Movement All new development should contribute to creating place that • Residential / nursing homes where residents would benefit are well connected, easy to get to and save to move through. from the sensory stimulation provided by a landscape scheme and who are not in a position to secure it for themselves. Policy DW10 – Well Designed New development should make a positive contribution to Sustainable Buildings creating a comfortable, adaptable and sustainable built • Larger development proposals. environment.

Policy ENV34 – Public Art The Council will require the provision of public art to enhance the quality and individuality of existing buildings, spaces or new development especially in the following locations: i. In public spaces and buildings ii. In important and prominent locations iii. In larger scale development or refurbishments 9 | M6 Junction 10 – Highways Improvements Design and Access Statement

4. Consultation and Engagement

4.1. Introduction Public Consultation Figure 4.1: Visualisations of proposed scheme presented during February 2017 public consultation event. Walsall Council’s Strategic Transportation Team and During the preparation of the proposals for the M6 Highways England have jointly engaged with the J10 improvements, the Applicant has undertaken a Local Community throughout the design evolution robust programme of stakeholder and community of the project. A public consultation exercise was engagement. held during December 2015 and asked the public’s opinion on the two preferred options for the A series of public consultation events were scheme. undertaken during December 2015 which proposed the two preferred options for the scheme and the The first public consultation exercise was held other four options considered. In February 2017, during December 2015 and asked the public’s an additional three public exhibitions were held to opinion on the two preferred options for the demonstrate the preferred option taken forward. The scheme. The questionnaire, available at the events focus of the events was to communicate the scheme or to fill in on line, asked respondents to give their to the public and gather feedback which could be views on the potential effectiveness of each of the incorporated into the scheme as far as possible. preferred options, if they disagreed or agreed with any part of the scheme, and to state their reasons Figure 4.2: Public Consultation Event at Boundary Mill (25 February 2017) why. 4.2. Statement of Community When the respondents were asked which design is Involvement best for M6 J10, 65% felt that option 1a, 1b or either is most suitable. 21% said they didn’t know and 14% A Statement of Community Involvement (SCI) has felt that neither option or another would be more been prepared by WMBC and Highways England and suitable. The top five considerations when designing is submitted as part of the planning application. the scheme were ranked by respondents as: The SCI sets out the full detail consultation process including the consultation undertaken and various 1. Congestion is reduced; findings and feedback received. These are discussed 2. The safety of road users; in further detail below: 3. Disruption to road users during construction; 4. Ease of use / navigation; and Pre-Application Meetings with Local Planning 5. The time taken to complete the scheme. Authority (LPA) An Initial pre-application meeting was held with The M6 J10 Design Team recognises that congestion- Figure 4.3: Public Information Board Displaying Preferred Option Walsall MBCs Development Team on 30 June 2016 in reduction is the main aim of the scheme as this will which the M6 J10 project team presented the overall in turn promote economic growth for the region. objectives of the project and the options that were The results listed in the SCI conclude that the vast currently being considered. majority of respondents agree that an improvement is needed for M6J10, with congestion being the Ongoing discussions with the Local Planning primary concern for those who agreed. Authority (LPA) since the pre-application meeting have been undertaken to inform the LPA of design A subsequent public information exercise was changes to the scheme and to confirm the scope and undertaken during February 2017, which announced content of the application. Additional discussions the preferred option and shared the latest with the LPA have taken place to inform the information about the scheme. Details of the various technical studies required to accompany information used at the events is shown at Figures the submission and ensure that all matters are 4.1 to 4.3. addressed within the planning application. Source: Walsall Council (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 10

5. Design of Development

5.1. Introduction Do-minimum alternative Local alternatives The minimum works required to keep the existing bridge capacity would be a Local alternatives involve options to construct Design and Access Statements are required to explain the design principles like-for-like replacement of the current bridges, and this is the assessed Do- an additional motorway junction on the M6 in and concepts that have been applied to the development. This section sets out Minimum scenario for the Scheme. The Do-Nothing scenario would not achieve the vicinity of the current J10. Given the urban the design of the proposed development and how this has evolved through an this as the bridges would need to be closed (as described above). constraints of the current J10 and other highway optioneering and consultation exercise taking into account the context of the connections, there is little potential for moving the application site. This scenario would not increase the capacity of M6 J10 and does not meet the junction further north or south along the motorway, objectives of the scheme. The option was therefore rejected and not considered nor moving the motorway itself. It would require further. more works than at present, due to the need to move much of the junction infrastructure, and would 5.2. Statement of Community Involvement Strategic alternatives therefore result in more disruptive and expensive Strategic alternatives are options for the Scheme which look at other means works and potentially the need to change the use of A range of schemes have been considered in order to assess the most for meeting the objectives of the scheme, other than the construction of a new some land from residential or business to highway. appropriate solution for the purposes of the scheme. The section identifies the motorway in this vicinity. This could involve the diversion of traffic elsewhere, This would also have a greater environmental impact scheme options which have been considered and the reasons for their omission. construction of new infrastructure elsewhere or options to reduce demand in than the assessed scheme. Local alternatives were The options discussed include and are discussed in further detail below: this location and reducing congestion. therefore not considered.

• Do-nothing alternative; The current bridges are reaching the end of their serviceable lives and therefore • Do minimum alternative; there is a requirement for works to take place at M6 J10. Consequently, there is little scope for strategic alternatives which avoid the need for works to take • Strategic alternatives; place at this location. The junction is a busy intersection between the A454 Black • Local alternatives; and Country Route and the M6 Motorway, as well as local roads. Strategic alternatives would necessitate the wider re-routing of traffic elsewhere, which is difficult • Design alternatives. considering the urban nature of the area, with limited capacity for additional routes or diversions. This would also mean the Scheme does not meet the Do-nothing alternative objectives to unlock development land near M6 J10. The ‘Do-Nothing’ alternative would mean no works would be undertake at the junction, excluding standard maintenance works typically carried out on such Strategic alternatives which alter the wider West Midlands road network, infrastructure on the highway network to ensure the network keeps running. removing the demand for vehicles to use J10, are discounted due to the cost implications, the disruption, and the lack of available land on which to The Do-Nothing alternative is not a viable option as the existing bridges are realise them given the urban nature of the area. Furthermore, the potential approaching the end of their serviceable lives, and therefore they require environmental effects of such large-scale infrastructure alterations would be demolition. Without this, the bridges would become a safety risk, requiring greater due to the larger size of such development. There is already a current closure of the junction. This is not deemed an appropriate alternative due to the use of a motorway junction and highways established at the current location, need to divert vehicles on to alternative routes, causing congestion in the wider whereas this would not be the case for new locations area. This would result in potential adverse environmental effects associated with noise, air quality, human health, and effects on travellers, among others. It Is considered that the strategic alternatives options considered would not A Do-Nothing alternative was not considered an option and was therefore not address the objectives of the scheme and the diversion of traffic away from M6 considered in further detail. J10 to other areas has the potential to incur adverse impacts associated with noise, air quality, health, and effects on travellers. 11 | M6 Junction 10 – Highways Improvements Design and Access Statement

Design Alternatives Option 5: Two new straight two-lane bridges and retain existing structures Walsall MBC has been working with Highways England to develop possible This option is for the construction of two new two-span concrete bridges (two transport solutions to improve M6 J10 and the outcomes of which are lanes wide each) and retention of existing structures. This option was discounted documented in Walsall Council’s Major Transport Scheme Concept Design (2013) as the continued use of the existing infrastructure would require extensive report. As part of the design development, several alternatives were considered and ongoing investment due to the current condition of the structures as the for M6 J10 and the report sets out six possible options for improving M6 J10 and two existing bridges are reaching the end of their serviceable life. This would are detailed in the table below: require a long-term programme of interventions such as night closures, traffic management/diversion with resulting additional congestion, which the Scheme Option 1 Two new straight two-lane bridges and flyover, demolish aims to mitigate, not to increase. existing bridges Option 2 Two new straight two-lane bridges and hamburger, demolish existing bridges Figure 5.1: Option 3a – Two new straight four-lane bridges and existing bridges demolished Option 3a Two new straight four-lane bridges, demolish existing bridges Option 3b Two new curved four-lane bridges, demolish existing bridges Option 4 Four new straight two-lane bridges, demolish existing bridges Option 5 Two new straight two-lane bridges, retain existing structures

Of the above solutions, options 3a and 3b (see Figures 5.1 and 5.2) were taken forward for further consideration and assessed fully in the Environmental Assessment Report (EAR). The remaining four options were discounted and therefore were assessed only at a high level in the EAR. Further detail on the options and the reasons for their discontinuance are detailed below.

Option 1: Two new straight two-lane bridges and flyover and demolish existing bridges Option 1 features a central ‘flyover’ principle in its design above Junction 10 and was dismissed at the preliminary stage. This was due to the design being unable to meet the desirable maximum vertical gradient for the ramp to tie into Bloxwich Lane, also it cannot be constructed within the footprint of the junction.

Option 2: Two new straight two-lane bridges and hamburger and demolish existing bridges The design included the addition of a central bridge across the junction to form a ‘hamburger’ style junction, which introduced an additional signal stage on each side of the circulatory. Including the central bridge along with the lack of circulatory storage space resulted in the weakening of the required benefits to address the transport problem as it was not considered to provide the benefits of vehicle congestion relief when compared with other options.

Option 4: Four new straight two-lane bridges and demolish existing bridges Construction of four new two-span concrete bridges (two lanes wide each) and to demolish the existing structures. This option was discounted as the modelling suggested that this solution would have provided insufficient capacity between the A454 Black Country Route and the B4464 Wolverhampton Road to accommodate vehicles travelling around the circulatory. Furthermore, the construction of four new bridges increases costs and reduces the cost benefit. M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 12

Design Selection Process Figure 5.2: Option 3b – Two new curved four-lane bridges and existing bridges demolished During the optioneering process both Option 1 and Option 2 designs failed to provide significant benefits in future scenarios. The remaining four options which mirror the existing layout of the junction but increase capacity with larger bridges showed potentially significant benefits and were taken forward for design work.

The same design constraints were apparent for options 5 and 6 as neither can be constructed without departures from standard, as a Design Manual for Roads and Bridges compliant restraint system cannot be installed the existing structures.

The preferred option for the scheme was concluded as Option 3b comprising two new four-lane bridges with a circular build and demolition of the existing structures.

As stated above, many of the proposed options were discontinued at an early stage of the schemes development. However, options 3a and 3b were considered further in the EAR which examined the potential environmental effects for both scheme options. The EAR assessed each option based on various technical assessments including air quality, cultural heritage, landscape, nature conservation, geology and soils, materials, noise and vibration, people and communities, road drainage and the water environment, and effects on travellers.

The EAR therefore found that both options would have a comparable effect on the environment. Therefore, equal scoring for environmental factors was given for both Option 3a and Option 3b. Because of this, other factors considered in this process resulted in the selection of Option 3b.

Option 3b was subsequently chosen for the proposed scheme for improvements to M6 J10. 13 | M6 Junction 10 – Highways Improvements Design and Access Statement

5.3. Proposed Development Layout widened to accommodate the increase roundabout Scale The layout of the proposed scheme is illustrated on diameter. Whilst the southbound and northbound off The scale of the scheme has been carefully This subsection sets out the works which are the Planning Application Detail Plan – Layout Plan slips are to be widened into the verge to considered to ensure that, as far as possible, it is proposed for to improve M6 J10. In summary, the (Drawing No. HE551484-MMSJV-HAC-000-DR-Z-00100) accommodate an additional lane. An additional lane integrated into the wider area and has made use of works include: as shown in Figure 5.3. The plan illustrates the layout is to be added to the westbound Black Country Route appropriate mitigation to screen the development change from the previous structure in which the and the lane widths reduced to 3.5m from surrounding sensitive receptors. Figure 5.4 • Widening bridges over the M6 Motorway; existing straight two-lane bridges are to be replaced illustrate a series of sections from elements of by new curved four-lane bridges over the M6. The M6 the M6 J10 scheme and illustrates the scale of the • Enhancing the slip roads of the junction; southbound and northbound on slip roads are to be scheme in the context of the surrounding area. • Installation of traffic signals; • Widening of the junction of A454 and Tempus Drive Figure 5.3: Site Layout Plan and Bloxwich Lane; • Modifications to the Black Country Route; • Landscape works; and • Associated infrastructure and engineering works.

5.4. Use and amount The proposed development is for a package of highways improvements at M6 J10 and comprises the construction of new curved bridges to be replace the existing structures. The application does not seek to change the permanent use of the land and will continue to be used as a highway and motorway junction serving the M6 northbound and southbound carriageways, A454 Black Country Route, B4464 Wolverhampton Road West, and A454 Wolverhampton.

A temporary construction compound is required for the scheme and this will be located east of M6 J10 on land currently occupied by either Bloxwich Lane Industrial Estate or John Hill & Sons Moorside. Only one construction compound will be required and this will be chosen in the post-consent phase of the scheme.

Source: Mott MacDonald-Sweco (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 14

Figure 5.4: Typical Sections of the proposed M6 J10 15 | M6 Junction 10 – Highways Improvements Design and Access Statement

Figure 5.4: Typical Sections of the proposed M6 J10 (Continued) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 16

Figure 5.4: Typical Sections of the proposed M6 J10 (Continued) 17 | M6 Junction 10 – Highways Improvements Design and Access Statement

Highway Alignment Figure 5.5: Highway Layout of M6 J10 The overarching purpose of the scheme is to increase capacity of the M6 J10 roundabout. This is to be primarily achieved through increasing the amount of vehicle lanes from two to four on the overbridge widening the east quadrant from 2 to 5 lanes and widening at the west quadrant from 4 to 5 lanes (See Figure 5.5). In addition, it is proposed that other road lanes are increased at the following sections:

• The northbound M6 off-slip increases from four to five lanes at the approach to J10; • The westbound Black Country Route, going west from the J10 roundabout, increases from two to three lanes as far as the junction with Marshland Way; • Wolverhampton Road West, where the eastbound lane approaches J10, there will be an increase from two to three vehicle lanes; • The southbound M6 off-slip increases from four lanes to five where it meets the roundabout; • Where Wolverhampton Road meets J10 on the east side of the roundabout, there is a lane increase from three to five; and • At the junction between Bloxwich Lane and Wolverhampton Road, the overall road width will increase on Bloxwich Lane due to the installation of an enhanced pedestrian crossing, incorporating an island in the road.

Source: Mott MacDonald-Sweco (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 18

Structures Figure 5.6: Plan of proposed new bridges at M6 Junction 10 In order to expand the lane capacity of the roundabout the existing bridges are to be demolished and be replaced by two new bridges. The two-new concrete and steel bridges will be constructed on the outside of the existing bridges and will be single-span thus removing he need for a central pier at the M6 motorway central reservation underneath, as shown in Figure 5.6.

Retaining walls will be constructed in each of the four corners of the roundabout in the following locations as shown on Drawing No. HE551484-MMSJV-SRW-RDBT- DR-CB-00021:

• In the north-west corner of the roundabout, in the area where Wolverhampton Road West and the northbound on-slip road to the M6 adjoin the roundabout, the retaining wall will be approximately 11m in length and up to approximately 1.0 and 2.5m in height and located between the northwest pylon and footway between B4464 Wolverhampton Road West and M6 northbound slip road; • In the north-east corner of the roundabout, the area where the southbound off-slip from the M6 and Wolverhampton Road adjoin the roundabout, the retaining wall will be approximately 384m in length and up to approximately 0.7m and 6m in height. The retaining wall will be located between the M6 southbound slip road adjacent to the footpath and extends as far as the Bloxwich Lane junction; • In the south-east corner of the roundabout the retaining wall will be located between in where Wolverhampton Road and the southbound M6 on-slip adjoin the roundabout and adjacent to the southeast pylon and private land. The retaining wall will be approximately 203m in length, and up to approximately 0.7m and 2.1m in height; and • In the south-west corner of the roundabout the retaining wall will be located from the northbound slip road from the M6 to where the Black Country Route adjoins the roundabout, the retaining wall will be approximately 20m in length and up to approximately 0.7m and 4.4m in height.

On the west side of the junction, the southern side of the A454 Black Country Route, where the westbound lane leaves the M6 J10 roundabout (in the vicinity of the northern end of Bentley Mill Lane), one noise barrier will be installed. This will be at a height of 2m above the existing wall (which will be retained) for a length of approximately 87m. On the eastern end of this barrier, for a distance of 108m, it will be 3.8m high from the ground, as there is no existing wall to build it upon. The total length of the noise barrier will therefore be 195m.

In the north eastern corner of M6 J10, a second noise barrier will be installed, 4m high, for a length of 165m.

Source: Mott MacDonald-Sweco (2017) 19 | M6 Junction 10 – Highways Improvements Design and Access Statement

Junction Strategy and Traffic Signalling Lighting Gantries and Signage The M6 J10 roundabout will be fully-signalised and pedestrian crossings will be fully incorporated into the The lighting and gantry design for the proposed scheme is shown in Figure 5.7 and will be similar in nature signal phasing to ensure no additional driver delay. to the existing layout. However, additions are proposed in the form of new lighting columns will be removed. Lighting will be of a similar-strength to the present conditions. The junction between Wolverhampton Road and Bloxwich Lane will continue to be signal-controlled with the timing coordinated with those at the adjacent M6 J10. Up to nine gantries will be installed to provide signage for vehicle users as the wider highway widths necessitate some above-road signage to ensure visibility to all drivers. These have been located to minimise Additional lanes will be provided on the overbridges of the M6 J10 roundabout and on some approach roads the visual intrusion on residents as much as possible through the use of existing screening. to the roundabout. The lanes of the roundabout, and the approach roads, will be comprised of feeder lanes. Signage (including overhead gantries where appropriate) will inform road users of the correct lane to use. The proposed gantries will be at a height of approximately 8.5 metres (from ground level to the top of the signage) and are required to ensure visibility of directions to all road users, as necessitated by increasing the number of road lanes as road-side signage may be blocked from view by vehicles in neighbouring lanes.

The remaining road signage will be of a similar design to those at present with other signage located parallel to the roadway rather than above it.

Figure 5.7: llustrative proposed Signage and Gantry

Source: Mott MacDonald (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 20

Construction Compounds Drainage The application proposes two options for construction compound areas to be used during the construction The existing drainage around M6 J10 collects runoff from both impermeable and permeable areas and is discharged into Sneyd Brook [subject to confirmation]. The proposed layout intends to maintain the existing phase. Both compound options are east of M6 J10 and can be accessed via the existing highway. It is envis- discharge points while reducing the potential flood risk within the site itself as areas downstream of the aged at present that only one of the two options would be used, rather than both. However, the final selec- junction by increasing the system’s capacity (and storage) and reducing the discharge rate to Sneyd Brook. tion of the preferred option has not yet taken place. The location of the compounds is illustrated in Figure 5.9. The drainage proposed is designed to cover 1 in 100-year storm events with a 30% increase in rainfall intensity to allow for the effects of climate change during the junction’s design life. The peak runoff Bloxwich Lane Industrial Estate discharged from the proposed network to Sneyd Brook is to be reduced to 80% of the existing discharge rate, This compound option is located north-east of the junction is currently occupied by two large warehouses. providing a 20% betterment. This is to be achieved by storing some of the runoff within vegetated ponds Access and egress is obtained directly via Bloxwich Lane. located in the centre of the roundabout area and large diameter pipes located along the junctions slip roads as well as locations along the Black Country Route and Wolverhampton Road. The ponds (See Figure 5.8) will John Hill & Sons and Moorside also serve as run off filters that reduce the amount of pollutants and sediment by the runoff before being This compound option is located east of the junction and currently comprises a combination of released to the watercourse. hardstanding and bare ground. The site also accommodates several small buildings and is currently used as a scrapyard. Access to the site is currently via either Wolverhampton Road or combination of Wolver- hampton Road and Bloxiwch Lane.

Figure 5.8: Proposed Attenutation Ponds Figure 5.9: Location of Proposed Construction Compounds

Source: Mott MacDonald SWECO (2017) Source: Mott MacDonald (2017) 21 | M6 Junction 10 – Highways Improvements Design and Access Statement

5.7. Site Visuals

Figure 5.10: Visuals of Existing and Future Structure of M6 J10 Figure 5.11: View from bridge on the Black Country Route looking east towards Junction 10

Source: Highways England (Date) Source: Mott MacDonald (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 22

Figure 5.13: View from the end of Bentley Mill Lane looking north towards the Black Figure 5.12: View from Wolverhampton Road looking west towards Junction 10 Country Route

Source: Mott MacDonald (2017) Source: Mott MacDonald (2017) 23 | M6 Junction 10 – Highways Improvements Design and Access Statement

Figure 5.14: View from Junction looking west Figure 5.15: View from Junction 10 looking west

Source: Mott MacDonald (2017) Source: Mott MacDonald (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 24

6. Landscaping

6.1. Proposed Landscaping Figure 6.1: Site Clearance Plan

The scheme proposes significance clearance of the existing surrounding landscaping, as shown in the Site Clearance plan (Drawing No. HE551484-MMSJV-HAC-000-DR-CH-00001) at Figure 6.1.

Landscaping Plans have been prepared by Mott MacDonald are provided at Figure xxx and each element of the proposed landscaping is discussed in further detail below:

Highway Verges within the Roundabout The area within the roundabout will comprise a native woodland mix consisting of Betula Pendula 30%, Alnus Glutinosa 30%, Acer Campestre Prunus Spinosa Tilia Cordata and Quercus Robur planted as whips. It is proposed that scattered throughout the area are a number of more mature Pinus Sylvestris trees to provide a level of instant impact with the planting. The embankments to the central roundabout will be planted in a grass mix which should open up views of woodland planted mix at the centre of the roundabout.

Motorway Approaches A secondary woodland planting mix consisting of Populus Nigra 10%, Alnus Glutinosa 20%, Acer Campestre 30%, Crataegus Monogyna 20%, Rosa Canina 20% has been proposed along the northern and southern approaches to M6 J10 with more mature Pinus Sylvestris trees planted to form an avenue of trees on each side of the motorway.

Central Reservations The central reservation approaching from the south is planted with a mix of ornamental cherry trees and the eastern approach has a mix of Quercus Palustris and Liquidambar Styraciflua planted in a line within the central reservation. Both sets of trees will provide seasonal displays of colour and visual interest throughout the year. The western approach has screen planting for properties which are located in close proximity to the Site. Screen planting with larger trees has also been proposed for the north-eastern area adjacent to Wolverhampton Road to screen properties from the highway.

Source: Mott MacDonald (2017) 25 | M6 Junction 10 – Highways Improvements Design and Access Statement

6.2. Landscape Plans Figure 6.2: Proposed Landscaping

Source: Mott MacDonald SWECO (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 26

Figure 6.3: Proposed Landscaping

Source: Mott MacDonald SWECO (2017) 27 | M6 Junction 10 – Highways Improvements Design and Access Statement

Figure 6.4: Proposed Landscaping

Source: Mott MacDonald SWECO (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 28

Figure 6.5: Proposed Landscaping

Source: Mott MacDonald SWECO (2017) 29 | M6 Junction 10 – Highways Improvements Design and Access Statement

7. Access Statement

7.1. Introduction • Where Wolverhampton Road meets J10 on the east Primary Pedestrian routes will navigate through 7.4. Public Transport side of the roundabout, there is a lane increase the roundabout from east to west and vice versa. The proposed scheme has been designed in from three to five; and Pedestrians will be directed towards several The accessibility of the site via public transport controlled crossing points using tactile paving to a accordance with Design Manual for Roads and • At the junction between Bloxwich Lane and access remains the same as the existing route along the north roundabout bridge which will Bridges and has considered the needs and desires Wolverhampton Road, the overall road width will arrangements. The existing bus lanes will be retained terminate on B4464 Wolverhampton Road West at of all user groups including vehicles, pedestrians, increase on Bloxwich Lane due to the installation and will provide access for buses onto Junction 10 the west and the Bloxwich Lane junction at the east. cyclists and public transport. Each element of the of an enhanced pedestrian crossing, incorporating and another lane will provide an exit from Junction The M6 J10 roundabout will be fully-signalised and schemes access arrangements is discussed below. an island in the road, including Toucan crossings 10 for buses onto B4464 Wolverhampton Road West. pedestrian crossings will be incorporated into the (for pedestrian and cycle use). Segregated lanes No other access arrangements for public transport signal phasing. The crossings proposed comprise will be as follows: are proposed as part of the scheme. 7.2. Vehicle Access of Toucan Crossing to enable both cyclists and • A segregated turn right lane from Bloxwich pedestrians to use the crossing at the same time. Vehicular access to the site will remain the same. Lane on to the A454 Wolverhampton Road (for Access to Junction 10 will available via from the traffic heading towards M6 J10); and following routes: Figure 7.1: Pedestrian and Cycle Routes • A segregated turn left lane on the A454 • From the east via A454 Wolverhampton Road; Wolverhampton Road for traffic coming from M6J10 onto Bloxwich Lane • From the west via A454 Black Country Route and B444 Wolverhampton Road West; • From the north via the M6 southbound off-slip; 7.3. Pedestrian and Cycle and access • From the south via the M6 northbound off-slip. The route for pedestrian and cycle access onto the site is shown on the Pedestrian and Cycle Routes Whilst the access to M6 J10 remains the same, plan (Drawing No. HE551484-MMSJV-GEN-000-DR- the scheme introduces a series of works which CH-00002) and in Figure 7.1. Pedestrian and cycle increase the capacity of the junction. The is achieved facilities will be upgraded to ensure that users will primarily by increasing the number of vehicle lanes no longer have to cross at a non-signalised point of on the overbridge. In addition, a series of lane the M6 northbound on-slip road from the junction. enlargements and additions are proposed. These include: Pedestrian footpaths are to be upgraded from the current provision to ensure that users will no • The northbound M6 off-slip increases from four to longer need to cross a non-signalised point of the five lanes at the approach to J10; northbound M6 on-slip road from the junction. Pedestrians will instead be directed to the centre • The westbound Black Country Route, going west of the roundabout via signalled crossing points. from the J10 roundabout, increases from two to This removes the need for pedestrians to cross the three lanes as far as the junction with Marshland northbound slip road where it is difficult to protect Way; pedestrians from the safety risks attendant to mak- • Wolverhampton Road West, where the eastbound ing this particular crossing movement. lane approaches J10, there will be an increase from two to three vehicle lanes; The use of signalled points will also be required for vehicles hence no additional vehicle waiting time is • The southbound M6 off-slip increases from four required as pedestrians will be signalled to cross the lanes to five where it meets the roundabout; road when the vehicle traffic is stopped. Source: Mott MacDonald-Sweco (2017) M6 JUNCTION 10 - Highways Improvements Design and Access Statement | 30

8. Summary and Conclusion

Mott MacDonald has been instructed by Walsall Metropolitan Borough Council Figure 8.1: Visualisation of proposed works at M6 Junction 10 (WMBC) to prepare a Design and Access Statement in support of a Full Planning Application for series of highways improvement works to M6 Junction 10.

The proposed development seeks to improve highway capacity and reduce vehicle delays through the construction of new widened bridges, improvements to the junctions slip roads, installation of traffic signals, widening of the nearby Bloxwich Lane Junction, modifications to part of the Black Country Route along with associated landscaping and other complimentary works. The full development description is as follows:

“Planning application for two replacement wider bridges over the M6 Motorway and a package of highway improvements comprising, enhanced motorway slip roads, installation of traffic signals, widening of the Junction of A454 and Tempus Drive Bloxwich Lane, modifications to the Black Country Route, landscape works and associated infrastructure and engineering works.”

The junction suffers from capacity issues resulting in vehicle congestion and delays along the strategic highway network. In tandem with this the existing structures at the junction are in need of urgent repair. Highways England carried out a host of inspections throughout 2012 on the existing bridges of M6 J10 which indicated signs of ongoing deterioration. The resulting Inspection Report suggested replacement of both bridges would be required within 3 to 4 years of 2012. Further and more recent inspections were also undertaken by Highways England, however these did not indicate further appreciable deterioration. However, Highways England’s Professional and Technical Solutions have agreed to still replace the bridges to avoid any future maintenance interventions from impacting the capacity of the M6 and Junction 10.

The Design and Access Statement has set out the design concepts that have been applied to the development. It demonstrates that the proposed scheme represents the best design solution taking into account the sites surrounding and the need for an appropriate solution to solve the issues present with the existing arrangements of Junction 10.

The design of the works has been developed with due regard to the relevant planning policies in respect of the Statutory Development Plan, National Planning Policy, and Supplementary Planning Guidance. Particular regard has Source: Highways England (2017) been had to Policy ENV3 of the Black Country Core Strategy, Policies ENV32, ENV33, and ENV34 of the Walsall UDP and Section 7 of the National Planning Policy Framework.