Major Mackenzie Drive Culvert Replacement

Total Page:16

File Type:pdf, Size:1020Kb

Major Mackenzie Drive Culvert Replacement MAJOR MACKENZIE DRIVE CULVERT REPLACEMENT PROJECT Successfully Planning, Executing, and Minimizing the Impacts of an eight-week, Double Culvert Construction Under a Major Urban Arterial Ontario Public Works Association Award Submissions 2019 Public Works Project of the Year The Regional Municipality of York Transportation Services TABLE OF CONTENTS Project Overview ........................................................................... 1 Project Background ...................................................................... 2 Construction Management and Schedule ............................ 4 Construction Safety ...................................................................... 6 Community Relations .................................................................. 8 Protecting the Environment ....................................................12 Accomplishments under Adverse Conditions ....................14 Why this Project is Important .................................................16 Conclusion ....................................................................................17 PROJECT OVERVIEW The Regional Municipality of York (York Region) recently undertook Given the various sensitivities surrounding the temporary road an emergency culvert replacement for a large 50-year old corrugated closure, York Region pre-qualified three top general contractors steel pipe arch (CSPA) culvert in the City of Vaughan. The culvert to bid on this project. Coco Paving Inc. was awarded the contract. conveys the West Don River under Major Mackenzie Drive, one of By working 24-hours a day, including weekends and holidays, Coco the busiest urban arterial roads in York Region. The condition of the Paving Inc. was able to re-open the road almost three weeks ahead existing culvert required a temporary full closure of Major Mackenzie of schedule, despite running into a number of complications. During Drive to safely and efficiently carry out the work, which had to be the eight-week construction period, the project team was able to: completed within a two month timeframe in order to comply with environmental in-water work timing restrictions. • Remove all impacted asphalt, granular material, curbs and sidewalk from the project site During consultations with the City of Vaughan, it was requested that the project incorporate critical pieces of city infrastructure. This • Excavate the existing 8 metre high earth fill embankment included a second perched culvert to facilitate pedestrian and cycling (approximately 10,000 cubic metres of soil, of which 5,800 cubic passage under Major Mackenzie Drive, a watermain connection metres required special disposal as it was contaminated) to to support the new Mackenzie Health Vaughan Hospital and new expose the CSPA culvert multi-use pathways. • Construct a temporary diversion of the West Don River to permit There were several technical and logistical challenges associated work “in the dry” with expanding the project scope to include the City’s infrastructure. However, it was also recognized that the temporary road closure • Secure a permit from the Ministry of Transportation of Ontario provided a unique opportunity to implement a piece of infrastructure (MTO) to allow overnight delivery of the 53 large precast culvert that could be enjoyed by the community for generations to come units on Highway 400. This was to further mitigate traffic impacts and therefore, the decision was made early in the process to include of having oversize loads delivered to the site during congested the City’s infrastructure as part of our project. daytime hours York Region’s engineering consultant, HDR Corporation, worked • Install the drainage and pedestrian culverts using a large 600 hard to expedite the detailed design, permit requirements and utility tonne crane conflict resolutions for the two new culverts. In order to meet some very constrained timelines, York Region pre-ordered the two new • Realign the West Don River to the new drainage culvert location concrete box culverts in early spring 2019 through a tender process from Decast Ltd. The first culvert was a 52 metre long, 6 metre by 3.5 • Install a new oil-grit separator unit to treat storm run-off prior to metre precast concrete structure that would convey the West Don entering the watershed River. The second culvert was a 44 metre long, 6 metre by 3 metre precast concrete box culvert that would serve as the pedestrian and • Install a new 5 metre high RSS wall and a new 2.7 metre high cast cycling underpass for the City of Vaughan. in-place retaining wall 1 • Install, test and commission a new 400 millimetre watermain connection within our project limits PROJECT BACKGROUND • Reinstate an existing sanitary sewer within our project limits The West Don River crosses Major Mackenzie Drive through a large CSPA culvert (4.7m x 2.9m x 58m), that was installed in 1968, just • Install a new and upgraded storm sewer system within our east of McNaughton/Avro Road in the City of Vaughan. During an project limits Environmental Assessment for Operational Improvements to Major Mackenzie Drive in 2018, it was found that the structural integrity • Reinstate the pavement structure for Major Mackenzie Drive of the culvert had deteriorated significantly over the last two years. based on geotechnical recommendations Inspections of all Regional structures are undertaken every two years. • Install new curbs and new multi-use paths on both sides of At the latest 2016 inspection, the culvert was observed to be stable the road and was rated as being in “fair to poor” condition. The intention was to review the culvert replacement as part of the ongoing Delivery of the project involved a tremendous amount of planning Environmental Assessment and plan the replacement accordingly. across various departments and agencies, construction coordination However, when the structure was inspected in spring 2018, it and public engagement. The project was a great success as the road was discovered that the culvert deterioration had significantly was reopened in eight weeks, well ahead of schedule. In order to accelerated, with severe buckling of the floor plates. achieve the eight-week delivery timeline, York Region implemented innovative procurement, construction management and public engagement techniques. We are pleased to submit this project for your consideration in the 2019 Public Works Project of the Year Awards. Culvert before 2 Structural engineers confirmed that the existing culvert was in A constructability review was carried out in February 2019 due to the immediate need of replacement due to significant structural culvert designs revealing a significant risk if a staged construction degradation. Failure of the culvert could result in the collapse of approach was attempted to complete this emergency work. The the structure, embankment and roadway. York Region decided to primary concern was the existing culvert might not withstand the proceed with the culvert replacement separately from the rest of pressure and vibration caused during installation of piles for the the recommendations of the Environmental Assessment study. temporary roadway protection system. Major Mackenzie Drive is a busy, four-lane arterial road in the heart of the City of Vaughan, A bi-weekly monitoring program was initiated in June 2018 to with average annual daily traffic of approximately 35,000 vehicles. monitor signs of any further culvert degradation. This was completed The risk of collapse would have been greatly compounded by the while a temporary bracing system to stabilize the structure and presence of workers and live traffic on Major Mackenzie Drive permanent culvert replacements were both being designed. during construction. Installation of the temporary bracing system was completed in To mitigate this risk, staff recommended a full closure of Major January 2019. While the bracing was substantial, it was designed to Mackenzie Drive, immediately east and west of the culvert location safely support live loads for a period of one-year from the time of to facilitate safe removal and replacement of the culvert. installation. Culvert temporary bracing Culvert temporary bracing 3 through logistical challenges (emergency medical services, transit, CONSTRUCTION MANAGEMENT AND SCHEDULE detour routes, signal timing adjustments, etc.), and having a strong community engagement plan and process in-place to deal with Timing was critical at all stages of this project, from planning to questions and concerns from local residents and business owners, as construction. While the delivery of this infrastructure in eight weeks well as frequent road users and daily commuters. is an impressive feat, there was a substantial amount of work that occurred prior to the contractor coming on board to make this It was imperative that the Region and our contractor maintained possible. good public relations and that we were doing everything we could to accelerate the construction work. In order to meet the delivery Once the Region learned of the precarious condition of the existing timeline, York Region facilitated the following: culvert, we arranged for the design, procurement and installation of a temporary bracing system inside the existing culvert to prevent it • Secured corporate and political backing for the project. It was from collapsing before it could be replaced. The temporary bracing expected that closing Major Mackenzie Drive in the heart was installed over the winter and was designed to carry live loads of Vaughan
Recommended publications
  • Cordova TH-1C • 1707 Sq
    Only you hold the powerFINELY CRAFTED TOWNHOMES to write your story THE ARTHUR CHAPTER ONE Unsurpassed in style, uncompromising in quality. - ARTHUR 02 THE ARTHUR CHAPTER ONE We can all have the life we have dreamed of – the life we have envisioned in our minds time This is a tale of a wonderful journey that is waiting to be yours, in the heart of a beautiful community in Maple. This is a neighbourhood where the homes are spectacular, the lifestyle after time. It all begins here. is captivating and the setting is absolutely endearing. This is the story of The Arthur. A TRADITIONAL TAKE 04 05 THE ARTHUR CHAPTER TWO A TALE OF CRAFTSMANSHIP timeless architecture Every great story begins with a pinch of inspiration. The Arthur emerged from a concept of bringing the community’s rich history and allure to the architecture and style of the project. This yields remarkable brilliance in the stylistic exteriors which showcase a traditional take on townhome design, finished off with state of the art craftsmanship. 07 THE ARTHUR CHAPTER TWO Family friendly The Arthur is perfectly positioned for families – set within an established community with architecturally controlled exteriors. This boutique collection of townhomes is immediately warm and inviting, complete with a community park exclusive for residents. WELCOMING STREETSCAPE 08 09 THE ARTHUR CHAPTER TWO CLASSICALLY INSPIRED INTERIORS Dwell in The Arthur highlights timeless grace throughout masterful interiors which are impeccably fashioned to deliver comfort and sophistication and ultimately create a feeling of effortless elegance and rustic flair Opulence. in each home. Successful design is determined by the details, and here the details truly are the design.
    [Show full text]
  • Programmed Projects 2020-2023
    West @ @ East Other Government Agencies/ Utilities Projects City of Vaughan City of Vaughan IDev Project Description Project # GTA WEST BOUNDARY (2020 Construction in red. Design, EA, Master/ Intergrated Plans, Studies in green, broken line includes watermain replacment) (2020 Construction in red. Design, EA, Master/ Intergrated Plans, Studies in green, broken line includes watermain replacment) Infrastructure Management Department, Infrastructure Delivery Department, Facility Management Department and Parks Delivery Department Infrastructure Management Department, Infrastructure Delivery Department, Facility Management Department and Parks Delivery Department York/ Peel Region Projects (Environmental Assessment, Design & Construction - in blue) 20-10 TP Ranch King-Vaughan Road transfered to York Region in 2018 IDev IDev Trail Project Description Project Description Major Mackenzie Drive Reconstruction Phase 2 - Islington Ave to Barons St (incl. Sidewalk, Active Transportation Facility, Watermain & LED Street Park an R ch T Project # Project # 18-25TP ra (Bathurst Street to Pine Valley Drive). i l R t Lighting by York Region on City's behalf). Construction on going. o e Y a e d tr R S S tallionsC ld Infrastructure Management Projects ou a Facility Management Major Projects A rt n Mill Road (COV) o D ) Highway 27 CPR Bridge Replacement & Road Widening (incl. Sidewalk, Streetlighting & LED Street Lighting upgrade by York Region on City's behalf). D c M 19-21TP R (! Construction on going. King-Vaughan Road (COV) N King-Vaughan Road (COV) King-Vaughan Road (YR) King-Vaughan Road (YR) 15-08MP Woodbridge Core Area Functional Servicing Strategy Study ×Ö 14-01BLD Woodbridge Operations Centre Ramp Improvements. Construction start anticipated in 2020. King-Vaughan Road (YR) Y (! U 25-03TP ( Major Mackenzie Drive Reconstruction Phase 1b - Pine Valley Dr to Islington Ave (incl.
    [Show full text]
  • Download Certificate
    FORM 9 CERTIFICATE OF SUBSTANTIAL PERFORMANCE OF THE CONTRACT UNDER SECTION 32 OF THE ACT Construction Act Corporation of the City of Vaughan, in the Regional Municipality of York , (County/District/Regional Municipality/Town/City in which premises are situated) 2141 Major Mackenzie Drive, Vaughan, Ontario L6A 1T1 , (street address and city, town, etc., or, if there is no street address, the location of the premises) This is to certify that the contract for the following improvement: T19-097 Safety Surfacing Replacements (short description of the improvement) to the above premises was substantially performed on October 9, 2020 . (date substantially performed) Date certificate signed: October 13, 2020 (payment certifier where there is one) (owner and contractor, where there is no payment certifier) City of Vaughan, Parks Delivery Name of owner: Department Address for service: City of Vaughan, 2141 Major Mackenzie Drive, Vaughan, Ontario, L6A 1T1 Name of contractor: Pine Valley Corp. Address for service: 125 Edilcan Drive, Concord, Ontario. L4K 3S6 Name of payment certifier (where applicable): Maxime Grandmaison Address: City of Vaughan, 2141 Major Mackenzie Drive, Vaughan, Ontario, L6A 1T1 (Use A or B, whichever is appropriate) A. Identification of premises for preservation of liens: City of Vaughan, Maple Airport Park, 121 Avro Road, Vaughan, Ontario, L6A 1Y7 (if a lien attaches to the premises, a legal description of the premises, including all property identifier numbers and addresses for the premises) B. Office to which claim for lien must be given to preserve lien: City of Vaughan, 2141 Major Mackenzie Drive, Vaughan, Ontario (if the lien does not attach to the premises, the name and address of the person or body to whom the claim for lien must be given) CA-9-E (2018/04) .
    [Show full text]
  • 2016 Annual Report
    2016 The Federal Gas Tax Fund Annual Report – Part II Table of Contents Compliance and Financial Audit Statements, Federal Gas Tax Fund ............. A 1-9 Audit Based Attestation .................................................................................................... B 1 Municipal Compliance Audit Reports ........................................................................... C 1-44 2016 to 2018 Federal Gas Tax Fund Allocations ....................................................... D 1-11 2016 Federal Gas Tax Fund Projects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
    [Show full text]
  • Major Mackenzie Drive Schedule 'C' Environmental Assessment Study
    Major Mackenzie Drive Schedule ‘C’ Environmental Assessment Study From McNaughton Road / Avro Road to Keele Street Regional Municipality of York December 20, 2018 From McNaughton Road / Avro Road to Keele Street east for the horizon year of 2020. A future EA study will assess long-term transportation needs, Executive Summary including capacity and multi-modal improvements to the corridor. In particular, the EA study: Introduction Reviewed existing conditions and operational challenges along this section of Major Mackenzie The Regional Municipality of York (York Region) has completed a Schedule “C” Municipal Class Drive Environmental Assessment (EA) study to review the short-term transportation operational needs Identified opportunities for improvement and possible solutions along Major Mackenzie Drive West (referred to as Major Mackenzie Drive for the purpose of this Investigated and recommended alternative designs for the preferred solution report), from McNaughton Road / Avro Road to Keele Street in the City of Vaughan. Collected, documented and assessed input and feedback from residents and affected groups York Region is responsible for monitoring its transportation network and implementing required within the study area improvements in a timely manner. Concerns raised regarding traffic operations on Major Mackenzie Drive within the study limits included challenging access to and from businesses, congestion, queuing Study Area and need for pedestrian crossings. These issues led York Region to investigate short-term (2020) The study area is 1.4 km long and is bounded by McNaughton Road/Avro Road to the west and operational improvements for the corridor. A future EA study will assess the long-term transportation Keele Street to the east, in the Village of Maple, located in the City of Vaughan.
    [Show full text]
  • Executive Committee Meeting #1/15
    INDEX TO EXECUTIVE COMMITTEE MEETING #1/15 Friday, February 6, 2015 MINUTES Minutes of Meeting #11/14, held on January 16, 2015 1 CORRESPONDENCE A letter dated February 3, 2015 from John D. Srebot, General Council re: 184448 Ontario Limited 1 LONG TERM OFFICE ACCOMMODATION PROJECT 5 LOWER DON 1D-2D FLOOD MODEL Request for Proposal #10000145 9 2015 BUDGET PROCESS Status Report 12 LANDSCAPE TRAINING PROGRAM 37 ONTARIO REGULATION 166/06, AS AMENDED CITY OF BRAMPTON 21 WEST OF MCVEAN DRIVE/NORTH OF COUNTRYSIDE DRIVE 21 CITY OF TORONTO 21 CITY OF TORONTO 22 184448 ONTARIO LIMITED 22 99 WAYMAR HEIGHTS 23 CORSICA DEVELOPMENT INC. C/O METRUS DEVELOPMENT INC. 23 CITY OF MISSISSAUGA 24 ROYAL LASER DEVELOPMENTS INC. 24 CITY OF TORONTO 25 ENBRIDGE GAS DISTRIBUTION INC. 26 35 HEATHERWOOD CRESCENT 26 84 SCIBERRAS ROAD 26 WEINS CANADA INC. 27 KEUNING CONSTRUCTION LTD. 27 375 ELLIS PARK ROAD 27 CITY OF TORONTO 27 ONTARIO REGULATION 166/06, AS AMENDED, CONT'D 87 VALECREST DRIVE 28 1044771 ONTARIO INC. 28 1044771 ONTARIO INC. (SUN HUNG KAI) 28 411 LAWRENCE AVENUE EAST 28 56 DON RIVER BOULEVARD 28 1313688 ONTARIO INC. 29 775 EASTERN AVENUE 29 CITY OF VAUGHAN 29 120 WOLF CREEK CRESCENT 30 136 WILLIS ROAD 30 REGIONAL MUNICIPALITY OF YORK 30 2964 SEABREEZE ROAD 31 8242 MAYFIELD ROAD 31 JOHN STREET AND HEMLOCK STREET 31 220 LAKELAND CRESCENT 32 CITY OF MARKHAM 32 CITY OF TORONTO 32 CITY OF TORONTO 33 ENBRIDGE GAS DISTRIBUTION INC. 33 10 RIPPLE STREET 34 3 PETUNIA STREET 34 2 GROVETREE ROAD 34 12 BAYSHILL DRIVE 35 7 COLCHESTER COURT 35 486 HIDDEN TRAIL 35 33 GARTHWOOD DRIVE 35 114 FERRIS ROAD 36 6 CONNABLE DRIVE 36 1 KAIA COURT 36 61 NAPANEE STREET 36 25 AUSTIN RUMBLE COURT 37 MEETING OF THE EXECUTIVE COMMITTEE #1/15 February 6, 2015 The Executive Committee Meeting #1/15, was held in Weston Room B, Black Creek Pioneer Village, on Friday, February 6, 2015.
    [Show full text]
  • Council Meeting 7 Pm
    Town of Whitchurch-Stouffville Council Agenda Tuesday March 6, 2018 7:00 PM Council Chambers 111 Sandiford Drive Please ensure cell phones are turned off or set to be silent. Council Meetings will be audio-recorded and made available online. Speakers may only register to speak to Staff Reports listed on the agenda. Chair: Mayor Altmann Page 1. Call to Order 2. Roll Call 3. Introduction of Addendum Items 1. Memorandum from Deputy Director, Development Services, re: Housekeeping Changes to By-law Number 2018-028-ZO and Staff Report DS-006-18 4. Confirmation of Agenda 1. To confirm the agenda That Council confirm the agenda, as circulated. 5. Declarations of Pecuniary Interest 6. Adoption of Minutes 8 - 14 1. To adopt the minutes That Council adopt the minutes from the regular meeting of Council on February 20, 2018, as circulated. 7. Recognitions 8. Delegations/Petitions Delegates may speak for up to 10 minutes of uninterrupted time and only on the matter indicated on your delegation request form. Page 1 of 226 Council Agenda March 6, 2018 As per the Town Procedural By-law, when addressing Council, the speaker shall be respectful of all persons and refrain from entering into cross debate with members of Council, Town Staff and members of the audience. Following the delegation, Council members may ask questions to obtain additional information or seek clarification from the speaker but shall not make statements to or enter into debate with the speaker. Once the question period is deemed complete by the Chair, Council members will deliberate the matter at hand without interruption.
    [Show full text]
  • Title Subtitle
    Parks Development Off Road Trail Updates June 2014 1 About Parks Development Role • Responsible for major capital park and open space projects (retrofits/redevelopments & new construction) • Projects often include significant planning with other departments and regulating authorities, such as Toronto and Regional Conservation Authority (TRCA), Ministry of Natural Resources (MNR) and York Region • Design development through to the construction stage of these off road projects can take several years to complete, pending level of approval required 2 Proposed Multi Use Community Trail Systems in the City of Vaughan (Planning Map ) 3 Existing Off Road Trail Systems in the City of Vaughan 4 Pedestrian Bridge Replacements Completed: Marita Payne Park, Thornhill : Galvanized Bridge, Winter 2014 (Don River) 5 Pedestrian Bridge Replacements Tender Ready Projects: Keffer Marsh Bridge, Mackenzie Glen Open Space Thornhill (Don River) Bridge, Maple (Don River) 6 Pedestrian Bridge Replacements 2014/2015 Projects Approved & Currently in Design and Development Stage: 1. Maple Airport Open Space: Metal Bridge (Don River) Concrete Bridge (Don River) 2. Marita Payne Park: 3. Pine Grove Bridge: Metal Bridge (Humber River) 4. Uplands Golf and Ski Centre: Metal Bridge (E. Don River) 5. West Don Valley Open Space: Metal Bridge (Don River) 7 Bartley Smith Greenway Trail Signage Improvements Scope: Adding new and enhanced signage from Steeles Avenue to Teston Road Purpose: Improve usability, accessibility, and safety of trail system Timeline: Completion Fall 2014
    [Show full text]
  • Proposed 2015 Budget and 2016-18 Plan
    SPECIAL COUNCIL APRIL 1, 2015 PROPOSED 2015 BUDGET AND 2016-18 PLAN Recommendation The Commissioner of Finance and City Treasurer and the Director of Financial Planning and Analytics, in consultation with the Interim City Manager and the Senior Management Team recommend: 1. That the presentation on the PROPOSED 2015 Budget and 2016-18 Plan be received; and 2. That the consolidated PROPOSED 2015 Budget as set out in this report, including the impact of excluding non-cash expenses as required by Ontario Regulation 284/09, be approved; and 3. That the 2016-18 Plan as set out in this report be recognized pending the findings of the Budget Task Force that has been created to study options to reduce the recognized plan to a maximum tax rate increase of not more the 3% annually. Contribution to Sustainability The City’s multi-year budget and financial plan contribute to sustainability by developing a longer term view of the resources required to achieve the City’s strategic objectives and established priorities. Responsible planning allocates resources in a way that balances needs and aspirations of the present without compromising the ability to meet those of the future. Economic Impact If adopted as presented, the current PROPOSED 2015 Budget and 2016-18 Plan would have the following economic impacts: Table 1: Economic Impact of PROPOSED 2015 Budget and 2016-18 Plan $M 2015 2016 2017 2018 Budget Recognized Plan Gross Operating Expenses 259.1 272.9 281.3 290.4 Less: Non-Tax Revenue -87.7 -84.8 -84.8 -85.1 Assessment Growth -3.2 -3.4 -3.8 -4.0 Levy Requirement 168.2 184.8 192.7 201.4 Budget Reduction Target -11.4 -13.9 -16.9 Net Levy Requirement 168.2 173.3 178.7 184.4 Incremental Levy 4.7 5.1 5.4 5.7 Tax Rate Increase 2.86% 9.65% 4.14% 4.25% Budget Reduction Target Required -6.65% -1.14% -1.25% Tax Rate Increase 2.86% 3.00% 3.00% 3.00% Tax Bill Change for the Average Home* $37 $39 $41 $42 Total Capital Program $92.7 $106.8 $104.5 $64.1 Note: some numbers may not add due to rounding.
    [Show full text]
  • Draft 2014 Budget and 2015-2017 Plan Update
    CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JANUARY 28, 2014 Item 1, Report No. 1, of the Finance, Administration and Audit Committee, which was adopted without amendment by the Council of the City of Vaughan on January 28, 2014. 1 DRAFT 2014 BUDGET AND 2015-2017 PLAN UPDATE This matter was deferred to the January 20, 2014, Finance, Administration and Audit Committee meeting to continue deliberations (see OTHER MATTERS CONSIDERED BY THE COMMITTEE, Item 2.1: DRAFT 2014 BUDGET AND 2015-2017 PLAN UPDATE) Draft 2014 Budget and 2015-2017 Plan UPDATE Finance, Administration & Audit Committee January 15, 2014 Financial Sustainability Always a Key Priority Presentation Agenda • Meeting purpose • The budget objective & key principles • Budget adjustments • Budget highlights • Ice Storm • Implications of reductions • Taxes in Perspective • Next steps 2 Draft 2014 Budget 2015-2017 Plan Meeting Purpose • Provide an update on the budget and plan • Receive public input • Obtain Committee direction on the budget • Schedule a date for Special Council (14 days public notice) (Further committee adjustments and/or direction will be incorporated in a consolidated report for this meeting) 2 Draft 2014 Budget 2015-2017 Plan Budget Objective “To balance the pressures of maintaining existing services and growth requirements against available future City funding and resources necessary to undertake and manage operations and initiatives” Key Principles • Guided by the City’s Strategic Plan • Financial sustainability • Planning for the future • Provide value for tax dollars 4 Draft 2014 Budget 2015-2017 Plan The Draft Budget Outcome Plan 2014 2015 2016 2017 Rate Incr. $ (m) Bill Incr. Rate Incr.
    [Show full text]
  • Maple Community Plan Amendment N0-150 to the Official Plan of the Vaughan Planning Area
    -MAPLE COMMUNITY PLAN AMENDMENT N0-150 TO THE OFFICIAL PLAN OF THE VAUGHAN PLANNING AREA -- KING :·I 1111111 I I I II I I }II II I I IIIIJ I I I IIIII Jill I 111111.,. 1111111111 IJ 11111,1111/11 1111111~1 111111 Ill i111111111 ~ H''~-< • ~~~~ ~l b '~~ ~ \\ \ \,:?s ~ ~ ; ) ~ ""'K~~~-\~:.'8'1--,jf--~:>----+-+~,---6-~>--~~: ; tO )( \ ~ ; ) I -·••••.. ~ •• ~~ I , ; METROPOUTAN TORONTO JULY 1984 > • .- MAPLE COMMUNITY PLAN Amendment Number 150 to the Official Plan of the Town of Vaughan Planning Area OPA 150 was approved in part by the Minister of Municipal Affairs and Housing with modifications on July 16th, 1984, save and except for the following which were deferred for further consideration pursuant to Section 14(3) of the Planning Act: 1. Maple Community Plan, Index, Page (iii) DEFERRAL No. 1 4.0 Special Use Areas 2. Section 4.0 Special Use Areas, pages 20 to 21 inclusive, DEFERRAL No. 2 3. Section 7.0 Rural Area, page 26 _.DEFERRAL No. 3 4. Schedule 'A' Maple Community Plan, lands outlined in blue - labelled DEFERRAL No. 4 5. Schedule 'A' Maple Community Plan, lands outlined in green - labelled DEFERRAL No. 5 6. Schedule 'A' Maple Community Plan, lands outlined in red - labelled DEFERRAL No. 6 7. Schedule 'A' Maple Community Plan, lands outlined in green - labelled DEFERRAL No. 7 8. Schedule 'A' Maple Community Plan, the boundary of the amendment area, outlined in red and labelled - DEFERRAL No. 8 9. Schedule 'A' Maple Community Plan, the lands outlined in red - labelled DEFERRAL No. 9 A further portion, namely "Schedule 'A' Maple Community Plan, the boundary of the amendment area, outlined in red and labelled DEFERRAL No.
    [Show full text]
  • Amendment No. 100 to the Official Plan of the Town of Vaughan Planning Area
    AMENDMENT NO. 100 TO THE OFFICIAL PLAN OF THE TOWN OF VAUGHAN PLANNING AREA THE MAPLE COMMUNITY PLAN AUGUST 8, 1978 < • AMENDMENT NO. 100 TO THE OFFICIAL PLAN OF THE TOWN OF VAUGHAN PLANNING AREA The following text, Key Map and Schedule including Part 2 entitled "The Official Plan for the Maple Community", the Key Map and Schedule "A" entitled "Land Use" constitute Amendment Number lOO to the Town Plan of The Town of Vaughan Planning Area. Attached hereto, but not constituting part of the Amendment are Part l entitled "Background and Con text" and Appendices l to 5. These con­ tain background and supportive data to the Amendment. I, ROBERT JOSEPH DOUGLAS, Deputy Clerk of The Corporation of the Town of Vaughan, in the Regional Muni­ cipality of York, do hereby certify that the attached is a true original copy of By-law Number 122-78 passed by the Council of the Town of Vaughan on the 8th day of August, 1978. l Dated at the Town of Vaughan this lst day of September, 1978. THE MAPLE COMMUNITY PLAN 1 PART 1 BACKGROUND AND CONTEXT 1.1 Purpose The purpose of this Amendment is to furnish development guidelines for the Maple Community in the Town of Vaughan. The Official Plan of the Vaughan Planning Area designates the general land use patterns to guide the future development of the municipality and sets the framework for the formulation of more detailed land use policies. The Official Plan designates the land in the general area of Maple as "Residential Area" and stipulates that the future de­ velopment of extensive residential areas will be controlled through secondary plans, passed as amendments to the Official Plan prior to rezoning.
    [Show full text]