Cebu-Negros- 230 kV Backbone Project – Stage 3

Presentation to the 2019 Visayas 30 May 2019 Energy Investment Forum Outline

1. Project Components and Status 2. Other Transmission Projects Project Components and Status Cebu-Negros-Panay 230 kV Backbone Project

PANAY

BAROTAC VIEJO S/S

CADIZ S/S CNP 230 kV Backbone Project Stage 3 CADIZ MANAPLA CITY E.B. MAGALONA S/S CITY ETC: Dec 2020

E.B. MAGALONA CITY VICTORIAS CITY Cebu-Negros transfer CNP 230 kV Backbone capacity: 180 MW + 800 MW Project Stage 1

ETC: Dec 2019

Negros-Panay transfer NEGROS capacity: 2019: 90 MW + 240 MW CEBU 2020: 90 MW + 400 MW S/S

CALATRAVA S/S CALATRAVA CTS CNP 230 kV Backbone Project Stage 2 (Cebu 230 kV Substation) SAN CARLOS SWS ETC: Dec 2020

CEBU S/S

TALAVERA SWS

MAGDUGO S/S Project Components and Status Cebu-Negros-Panay 230 kV Backbone Project – Stage 3

PANAY BAROTAC VIEJO S/S (3x300 MVA)

CADIZ MANAPLA CITY CITY

E.B. MAGALONA CITY VICTORIAS CITY

NEGROS

CEBU

CALATRAVA CTS TALAVERA–CALATRAVA S/C, 29 km SAN CARLOS SWS (2x400 MW)

. Sites of the Barotac Viejo and Magdugo S/S are workable. CEBU S/S . Manufacturing of the Talavera– TALAVERA SWS MAGDUGO S/S Calatrava S/C is almost finished. (3x300 MVA) Project Components and Status Cebu-Negros-Panay 230 kV Backbone Project – Stage 3

PANAY

CADIZ S/S E.B. MAGALONA-CADIZ (2x150 MVA) 230 kV T/L, 45 km

CADIZ MANAPLA CITY CITY CADIZ-CALATRAVA 230 E.B. MAGALONA CITY VICTORIAS CITY kV T/L, 80 km

NEGROS BACOLOD S/S (2x300 MVA) CEBU CALATRAVA S/S (2x100 MVA)

CALATRAVA CTS . Substation Sites in are under

ROW negotiations. CEBU-MAGDUGO 230 kV . Ongoing Parcellary Survey for the E.B. Magalona– SAN CARLOS SWS T/L, 35 km Cadiz–Calatrava 230 kV OHTL. . ROW issues on the 230 kV Transmission lines in CEBU S/S Cebu. TALAVERA SWS . Difficulty in acquiring LGU permit in Cebu side. TALAVERA-MAGDUGO . Supply for the equipment is almost complete. 230 kV T/L, 6 km Other Transmission Projects Negros & Panay

NABAS-CATICLAN- BORACAY PANITAN - NABAS 138 kV T/L LINE 2 138 kV T/L PROJECT Dec 2019 STAGE 1 : Jun 2020 STAGE 2 : Aug 2021

BAROTAC VIEJO - NATIVIDAD 69 kV T/L PROJECT Oct 2022

PANAY - 138 kV SAN CARLOS - GUIHULNGAN INTERCONNECTION PROJECT 69 kV T/L PROJECT Jul 2021 Dec 2019

AMLAN - DUMAGUETE 138 kV T/L PROJECT FILED TO ERC Feb 2022 ONGOING Other Transmission Projects Cebu & Bohol VISAYAS SUBSTATION RELIABILITY PROJECT 2 VISAYAS VOLTAGE IMPROVEMENT Lapu-lapu S/S: 1x100 MVA PROJECT Mandaue S/S: 1x100 MVA Cebu S/S: 2x20 MVAR Sep 2019 Compostela S/S: 2x20 MVAR Corella S/S: 1x5 MVAR Dec 2019

LARAY 230 kV S/S May 2022

CEBU - BOHOL 230 kV INTERCONNECTION PROJECT MINDANAO–VISAYAS Dec 2021 INTERCONNECTION PROJECT Dec 2020

FILED TO ERC TAGBILARAN 69 KV ONGOING SUBSTATION PROJECT Jun 2020 TO Other Transmission Projects DAANBANTAYAN Metro Cebu

CEBU-NEGROS-PANAY 230 kV STAGE 3 Dec 2020 COMPOSTELA

TO NEGROS

CEBU-NEGROS-PANAY 230 kV CALONG-CALONG STAGE 2 Dec 2020

CEDC

MAGDUGO

TVI CEBU TOLEDO

MANDAUE LAPULAPU

MVIP CEBU - LAPULAPU Dec 2020 QUIOT 230 kV T/L PROJECT (energized at 138 kV) Dec 2020

NEW NAGA (COLON) SUBSTATION PROJECT (REMAINING WORKS) COLON Dec 2019 NAGA

NAGA S/S UPGRADING PROJECT Dec 2019 ONGOING Other Transmission Projects Leyte & Samar

CALBAYOG - ALLEN 138 kV T/L PROJECT (69 kV energized) Jul 2022

VISAYAS SUBSTATION RELIABILITY PROJECT 2 STA. RITA - QUINAPONDAN Sta. Rita S/S: 1x50 MVA 69 kV T/L PROJECT Sep 2019 Sep 2019

BABATNGON - PALO 230 kV T/L PROJECT VISAYAS SUBSTATION UPGRADING (138 kV energized) PROJECT 1 Feb 2022 Maasin S/S: 1x50 MVA Calbayog S/S: 1x50 MVA Tabango S/S: 1x50 MVA Daanbantayan S/S: 1x100 MVA Sep 2021

VISAYAS VOLTAGE IMPROVEMENT PROJECT Bobolosan LES: 1x5 MVAR Himayangan LES: 1x5 MVAR FILED TO ERC Tolosa LES: 1x5 MVAR Mar 2022 ONGOING