- July, 19, 2012 The Republic ofTajikislan Municipal Infrastructure Development Project Procurement Plan for the third phase Part l. Works and Goods = ..., C> - = = ".= E C> ~ E ~ C. Public Disclosure Authorized E c B :g~ C>= E C> C> "0 No. Contract (Description) "0 Z .. (J E E .. a:I .5 ;;=" :;;= ~:g (J "0 0; .;; 0; "0 0; ., WORKS Component A. Municipal Infrastructure Rehabilitation Plan 290 733 IS.02.20 II March 20 II March 20 II April 20 II April 20 II April 20 II Apri l 2011 luly 20 11 1 MIDP 040 Construction of overhead transmission line of 10 kV in lstaravshan city NCB Fae. 29041S IS .02.2011 04.03 .20 11 10.03 .2011 11.04.20 11 06.0S .201 1 16.0S .201 1 01.06.2011 April2012 y Completed Plan 3SS 000 08.02.2010 N/A February 2010 March 2010 March 2010 N/A March 2010 May 20 II 2 MIDP 04 1 Water supply system rehabilitation-Vose NCB Fae. 249 323 08.02.20 I 0 NI A 16.03 .20 10 26.04.20 10 28.04.2010 N/A 0 1. 07.2010 27.12.2011 N Completed Plan 970000 29.03 .2010 February 2010 February 2010 March 2010 March 20 10 March 2010 March 2010 May 2011 3 MIDP 042 Water supplv system rehabilitation - Kulob NCB Fae. 87S 12S 29.03 .2010 06.04.2010 13 .04.2010 13 .0S .2010 17.0S .2010 10.06.2010 30.06.2010 30.07.20 11 y Completed Plan 190600 IS .02.2011 March 20 11 March 2011 April 2011 April 2011 April 2011 April 2011 Jul 2011 4 MlDP 043 Co nstruction of overhead transmission line of 10 kV in Vahdat town NCB Fae. 183 126 IS.02.20 11 04.03 .20 11 10.03 .20 11 12.04.20 11 06.0S .20 11 IS.OS .20 11 01.06.2011 2S .02.2012 y Comple.ed Plan 66123S 29.03.2010 February 2010 March 2010 April 2010 April 20 10 April2010 April 2010 lui 20 11 5 MIDP 044 Water supply system rehabilitation - Qurghon Teppa NCB F.c' 706 803 29.03 .20 10 06.04.20 10 21.04.2010 24.0S .2010 31.0S .2010 29.06.2010 01.07.20 10 22.12.20 11 y Completed Plan 63000 IS .02.2011 March2011 March2011 April2011 April2011 April 20 11 April2011 lui 2011 6 MIDP 044A "Construction of overhead transmission line of 10 kV in Kurgan-Tube" NCB Fae. 6S 003 IS.02.2011 10.03 .20 11 IS.03 .20 11 IS.04.20 11 06.0S.20 11 16.0S.201 1 01.06.20 11 22.12.20 11 y Completed Plan 30000 N/A February 20 10 February 20 10 March 2010 March 20 10 N/A March 20 10 April 2010 7 MIDP 027 (a) Water supply system rehabilitation-Vase Shopping f-;F;."'ct'--l-.....,,29~4So;9~--::N"'/A7---P""'N"'/::A='-"t-'-'2::':S,..,. 0;;:2:-:. 2::0"1:;0"-!--'71 ':'0 ."'0"'3 ."2::07:10:'-+--'71 71 "'. 0'03."2::07:1OC--!--7.N:;'IAc--+-"276 ."'0"'3 ."2::07:1Oc--!--=0~4 ."'0~7.~20~1~O--j N Comple.ed Public Disclosure Authorized MIDP 048 Additional works for water supply system rehabilitation - Istaravshan and Shopping~P~la~n'--l_~40~000~_~N~/ A~_r-~N~/~A~-+~M~ar~ch~20~1~1~~A~prri~I~20~1~1-+~A~\p~rn~· 1~20~1~1~ __N~ /A~-+~A~prri~l~2~0~11~_~I~u~IIY~2~0~1~1--1 8 Kanibad am Fae. SO 318 N/A N/A 20.04.2011 OS .OS .20 11 10.OS .20 11 N/A 06.06.20 11 22.10.2011 N Completed ShoPP in g~P~la~n'--l_~I~I~000~_~N~/ A~_r-~N~/~A~-+~M~ar~ch~20~1~1~~A~prri~I ~20~1~1-+~A~\p~rn~· 1~20~1~1~ __N~ / A~-+~A~prri~1~2~0~11~_~I~u~IIY~2~0~1~1--1 MIDP 049 Additional works for water supply system rehabilitation - Vase, Kulob 9 Fae. 13473 N/A N/A IS.04.2011 02.0S .2011 04.0S .2011 N/A 13.0S .2011 13 .08.2011 N Completed MIDP 053 Additi onal works for water supply system rehabilitation - Qurghon-Teppa Shopping~P;la~n'--l_-7S0~00~0~_~N",/A~_r-~N~/~A~-+~M~ar~ch~20~171~~A~prri71~2071~1-+~A7\p~rn7· 1~2071~1~_~N:;.I A~-+~A~prri71~270~11~_~17u~~1~2~0~1~1--1 10 Fac. 4929S N/A N/A 19.04.20 11 03 .0S .20 11 OS .OS .20 11 N/A 10.OS .20 11 06.03 .2012 N Completed 11 MIDP 054 Additional works for water supply system rehabilitation - Garm, Vakhdat S hoppin g~P~I~an~r-~4~S ~000~r--7N~/~A~-+ __N~ / A~~~M~~7C~h~2~0~11~~A~~p~rn~· 1~2~0711~~A~\p~rn~· 1~2~0~11~r--7N",/A~~~A~prri~I~2~0~1~1 ~~I~u~lly~2~0~1~1~ Fact 4S 29S N/A N/A 30.03.2011 IS .04.2011 20.04.2011 N/A 26.04.20 11 09.09.2011 N Completed N Completed MIDP OS9 Additional works in Rehabilitation wa.er conduit lines in wa.er intake #3 - Qurghon ShoPPingf-'P,-,I~an~f---"S~O-"OOO-""j_~N"I,-,A~-+ __N~ / A~~-,D",ec=em=be::.r-=2~0~1I,+I,-,an=ua=ry.=.20"-1,-,2+!!la",n",ua=ry.=.20"-1,-,2+_-"N,,,/A,,-~~I,-,an,,,u",Jary=.=.20,,-1,-,2+---,M=ayL.:2~0~ 1",2~ 13 Teppa Fact 4S 807 N/A N/A 06.01.2012 23 .01.2012 26.01.2012 N/A 16.02.2012 April 2012 N Comple.ed Plan SO 000 N/A N/A March 20 12 April 20 12 Apri l 20 12 N/A April 2012 luly 2012 14 MIDP 60 Additional works fo r water supply system rehabilitation - Vose Shopping Fae. 32490 N/A N/A 04 .04.20 12 19.04.20 12 24.04.2012 N/A 02.0S .20 12 N Under implementation Subtotal \Vorks for Component A Plan 2 856 568 Fac. 2684858 Component C Pro "eet Implementation Support Plan 10000 N /A N/A June 2012 l uly 2012 l ui 2012 N/A luly 2012 August 2012 N IS MIDP 61 PMU Office Panial Repair Shop pin. I Fae. 9 96S N/A N/A 03 .07.2012 17.03 .2012 18.03.2012 N/A 19.07.2012 Under implementation r.ooos Public Disclosure Authorized Com onent A. Mu nicipalln/rastructure Rehabilitation 16 MIDP 045 Procurement of equipment for laboratory of Vose Vodokanal Shopping Plan 7000 N/A N/A February 2011 March 2011 March 201 1 N/A March 2011 April 2011 N Fae. 9920 N/A N/A 21.02.2011 03 .03 .2011 09.03.2011 N/A 26.03.2011 May 20 11 Completed 17 MIDP 050 Protective clothing for Kulob, Oanghara, Vase, Qurghon Teppa, Vakhdat, r-P~I~an~r-__~ 9 ~000-""j ___~ N I/A~ __t- __ N~/ A~~ __~ A~prri~12~0~1~1 __r-A~'p~rn~ · 1 ~2~0~11~~A~\P~rn~· 1 ~2~0~11~r-~N~/A~-i~A~\P~rn~· 1~2~0~11~r-~I~u~IIY~·2~0~1~1-4 Istara vshan and Konibadam and ralated training Shopping Fae. 12249 N/A N/A 26.04.2011 12.0S .2011 02.06.2011 N/A 10.06.2011 October 2011 Completed Plan 49000 N/A N/A April 20 11 April 20 11 April 2011 N/A April 2011 luly 2011 18 MID? 05 I Procurement of solid waste containers for Kulob and Danghara Shopping r-F'-'a"e"t +-"':4~S-"6.::c33"t--~NII '-'A--+--N~/ A~~-':"2"'1.04=. 2"'0'-'1~1-t-'1"'0~. 0~S~. 2~0~1 '-I +~1C!6"'. 0~S "::. 2~0~11:""";f--=N I/A"--i---'1"'9 .~0~S .-=2"-0'-'1I~f-~2~2 .~09~.~20~1~1-4 N Completed ShoPpingr-P_I_an__ r---, 4~4-,,000-""j ___~N II~A__ -t ___ N~I/ A~~ ___I_ ul.:..y_2_0_12__ ~_A ~ugu~s_t2_0_1_2+_A_ug~u~s_t2_0_1_2+ __-" N~/A~-i~A~u~gu~st~2~0~1 ~2+~A~u~gu~st~2=0~12~ 19 MIDP 064 Procurement of solid waste containers for Kulob, Qurghon Teppa and Danghara N Fact Pl an 109000 Subto.al Goods for Componen. A · rF~a::e:;-t-t--';:67:;;8;;;0;;2'-1-----r----t------t------j----r-r----+-----+-----t---+-----------1 Public Disclosure Authorized The Republic ofTajikislan Municipal Infrastructure Development Project Procurement Plan for the third Dhase Part 1 \Vorks and Goods Com onent B. Technical and Institutional Strenxthenin MIDP 036 Procurement of equipment and sofware for SUE KMK and local subsidiary Plan 40000 NIA NIA March 2010 March 2010 March 2010 NIA March 2010 April 2010 N Shopping 20 enterprises Fad 30529 NIA NIA 16.06.2010 05.07.2010 09.07.2010 NIA 19.07.2010 20.08.2010 Completed Plan 20555 NIA NIA April 2011 April2011 April2011 NIA A ril2011 Julv 2011 N Advertising services for Customer Service Support Centers in Istaravshan and Qurgonteppa MlDP 039 (01) Shopping Fact 08.06.2011 21.06.2011 23 .06.2011 07.07.2011 August 2011 MlDP 039 (02) 21 14871 NIA NIA NIA Completed Plan 9000 NIA NIA September 20 II October 20 II October 20 II NIA October 20 II November 2011 N MIDP055 Partial replacement of PMU windows frames Shopping 22 Fact 7890 NIA NIA 27.09.2011 13.10.2011 17.10.2011 NIA 20.10.2011 November 20 II Completed Plan 69555 Subtotal Goods for Component B.