PREFACE

This Distribution System Capability Statement (DSCS) is provided by Electricity Distribution Company (MEDC) to fulfil its regulatory obligations under Condition number 32 of the MEDC Distribution and Supply Licence as well as the Distribution Planning Code 4.4.

MEDC supplies electricity to customers throughout the Muscat Governate as the owner and operator of its electricity distribution system originating from the 33kV busbars of the Oman Electricity Transmission Company (OETC) 132/33kV grid substations down to the final customer’s point of connection; which incorporates 33kV, 11kV and Low Voltage (LV) distribution system voltage levels and associated assets.

The aim of this DSCS is to provide an up-to-date distribution system capability for the next three years (2021-2023) along with data to enable customers in identifying parts of the system; which offer opportunities for future connections or upgrading of existing connections to the MEDC system and where constraints currently exist or potentially could exist in future.

In addition to the required data made available annually as part of DSCS; MEDC additionally has provided improved detailed system connectivity and additional technical data of assets, impact analysis of Cost Reflective Tariff (CRT) on MEDC customers and an overview of the photovoltaic (PV) system penetration in the MEDC distribution system which is gaining momentum in our licenced area as well. These additions are expected to provide customers and other stakeholders with a transparent understanding of MEDC distribution system and operational overview, sufficient technical parameters to undertake initial system capabilities assessment and the overall distribution system development. Additionally, this year the world including MEDC customers and hence its network have experienced a force-majure event triggered due to the COVID-19 pandemic which has temporarily but significantly impacted electricity demand including future growth in the MEDC licenced area.

MEDC have determined this three-year plan to clarify and highlight MEDC’s key priorities over the DSCS planning period. The plan will form the basis for the company’s investments to provide economic and efficient system development along with serving to inform MEDC’s contributions to the Oman electricity sector.

Eng. Ala Hassan Moosa

Acting/MEDC Chief Executive Officer

TABLE OF CONTENTS

PREFACE 1

LIST OF TABLES 5

LIST OF FIGURES 6

LIST OF ABBREVIATIONS 7

1. INTRODUCTION 1 1.1. PURPOSE OF THE STATEMENT ...... 1 1.2. STRUCTURE OF THIS DSCS ...... 1

2. PLANNING PHILOSOPHIES AND PRACTICES 3 2.1. OBLIGATIONS OF THE DISTRIBUTION AND SUPPLY LICENCE (D&SL) ...... 3 2.2. REQUIREMENTS OF THE DISTRIBUTION CODE...... 4 2.3. DISTRIBUTION SYSTEM SECURITY STANDARD ...... 4 2.4. SYSTEM VOLTAGE LEVELS AND CONFIGURATION...... 5 2.5. FREQUENCY DEVIATIONS ...... 6 2.6. VOLTAGE WAVEFORM QUALITY ...... 6 2.7. VOLTAGE FLUCTUATIONS ...... 6 2.8. AUTO-RECLOSING AND SINGLE-PHASE PROTECTION OPERATION ...... 6 2.9. DESIGN FAULT LEVELS ...... 7 2.10. STANDARD EQUIPMENT SIZES ...... 7

2.11. TECHNICAL STANDARDS ...... 9 2.12. SPECIFICATION OF APPARATUS AND PLANT ...... 9 2.13. EARTHING ...... 9 2.14. VOLTAGE REGULATION AND CONTROL ...... 10 2.15. PROTECTION...... 10

3. PLANNING DRIVERS 11 3.1. BACKGROUND ...... 11 3.2. ZONE 1 – (THE EASTERN ZONE) ...... 13 3.3. ZONE 2 - (THE CENTRAL ZONE) ...... 15 3.4. ZONE 3 - (THE WESTERN ZONE) ...... 18

4. MEDC DISTRIBUTION SYSTEM 21 4.1. EXISTING DISTRIBUTION SYSTEM ...... 21 4.2. SYSTEM DEMAND AND LOAD DURATION ...... 22 4.3. COST REFLECTIVE TARIFF (CRT) ...... 25 4.4. DEMAND NOT SECURED (DNS) ...... 26 4.5. 11KV FEEDER LOADINGS ...... 27 4.6. SYSTEM DEMAND FORECAST ...... 27

4.7. GRID SUPPLY POINTS ...... 31 4.8. DISTRIBUTION SYSTEM MODELLING AND ANALYSIS ...... 34

MEDC Distribution System Capability Statement (2021-2023) – V2.0

4.9. CONTINUOUS IMPROVEMENT AREAS ...... 37 4.10. INFORMATION ON DISTRIBUTION NETWORK ASSETS ...... 38

5. CHALLENGES AND OPPORTUNITIES WITHIN THE SYSTEM 40 5.1. NEW CONNECTION APPLICATIONS ...... 40

5.2. SYSTEM CONSTRAINTS AND OPPORTUNITIES ...... 42

6. THE INVESTMENT PLAN 43 6.1. SYSTEM DEVELOPMENT PROJECTS DURING THE PERIOD 2021– 2023 ...... 43

APPENDIX A: DISTRIBUTION LICENCE CONDITION 32: DSCS 49

APPENDIX B: DSSS NON-COMPLIANCES 50

APPENDIX C: LIST OF 2020 PV SOLAR APPLICATIONS 51

APPENDIX D: SYSTEM STUDY RESULTS 54

MEDC Distribution System Capability Statement (2021-2023) – V2.0

APPENDIX E: INFORMATION ON DISTRIBUTION SYSTEM ASSETS 121 APPENDIX E1 – 33KV CIRCUITS/FEEDERS DATA ...... 121

APPENDIX E2 – PRIMARY SUBSTATION TRANSFORMER DATA ...... 132

MEDC Distribution System Capability Statement (2021-2023) – V2.0

MEDC Distribution System Capability Statement (2021-2023) – V2.0

LIST OF TABLE S

Table 1 : DSSS Classifications and Defined Restoration Times ...... 4

Table 2 : System Nominal Voltages and Tolerance ...... 5

Table 3 : Short Circuit Rating of Switchgear ...... 7

Table 4 : Standard 33kV Conductor Sizes and Ratings ...... 7

Table 5 : Standard 11kV Conductor Sizes and Ratings ...... 7

Table 6 : Standard LV Mains Conductor Sizes and Ratings ...... 8

Table 7 : Standard Switchgear Ratings ...... 8

Table 8 : Zone 1 - Grid and Primary Substations Connectivity ...... 14

Table 9 : Zone 2 - Grid and Primary Substations Connectivity6 ...... 17

Table 10 : Zone 3 - Grid and Primary Substations Connectivity6 ...... 19

Table 11 : Summary of Distribution System Assets ...... 21

Table 12 : Summary of Installed and Firm Capacities of MEDC Distribution System ...... 21

Table 13 : Area Wise Compound Annual Growth Rate[CAGR] % of MEDC Distribution System . 22

Table 14 : Maximum and Minimum System Demands ...... 23

Table 15 : 11kV Non-Compliant Feeders ...... 27

Table 16 : CAGR% Evaluation on the System Maximum Day ...... 28

Table 17 : Covid-19 summer load 2020 impact ...... 29

Table 18 : System Maximum Demand in MW [Historical and Forecast] ...... 30

Table 19 : Technical Losses ...... 37

Table 20 : Number of Connection Applications for Bulk Load Application, 11kV and LV Application ...... 40

Table 21 : PV Application and Connection Classification ...... 41

Table 22 : 2023 Projected Capacity Constraints in MVA ...... 42

Table 23 : Status of the Primary Substations at a Glance [2021-2023] ...... 43

Table 24 : Summary of Sponsored Projects ...... 43

Table 25 : Summary of Planned Projects in MEDC Distribution System to meet Summer 2021 Maximum Demand ...... 44

Table 26 : Summary of Planned Projects in MEDC Distribution System and OETC to meet Summer 2022 Maximum Demand ...... 44

Table 27 : Summary of Planned Projects in MEDC Distribution System and OETC to meet Summer 2023 Maximum Demand ...... 44

MEDC Distribution System Capability Statement (2021-2023) – V2.0

LIST OF FIGURES

Figure 1 : MEDC Distribution System with GSS ...... 12

Figure 2 : Zone 1 Distribution System with PSS ...... 13

Figure 3 : Zone 2 Distribution System with PSS ...... 16

Figure 4 : Zone 3 Distribution System with PSS ...... 18

Figure 5 : Hourly Demand – System Maximum Day Profile 2013-2020 ...... 23

Figure 6 : Load Duration Curve ...... 24

Figure 7 : Maximum & Minimum Demand with Customer Numbers Growth ...... 24

Figure 8 : MEDC 2019 CRT and Non-CRT Units Sold (MWh) ...... 25

Figure 9 : CRT Customer’s Profile on the System Peak Day for 2017 - 2020 ...... 26

Figure 10 : DNS Historical Data ...... 27

Figure 11 : System Historical and Forecast Maximum Demand (2007-2023) ...... 30

Figure 12 : 33kV Existing System (2020) ...... 32

Figure 13 : 33kV Expected System Development (2021 to 2023) ...... 33

Figure 14 : No. of Connection Applications (Bulk Load Application, 11kV and LV) Received in 2020 ...... 41

MEDC Distribution System Capability Statement (2021-2023) – V2.0

LIST OF ABBREVIATIONS

APSR Authority for Public Services Regulation (formerly known as AER - Authority for Electricity Regulation)

CAGR Compound Annual Growth Rate

CRT Cost Reflective Tariff

DCC Distribution Connection Code

DNS Demand Not Secured

DPC Distribution Planning Code

DSCS Distribution System Capability Statement

DSSS Distribution System Security Standard

D&SL Distribution & Supply Licence

GSS Grid Substation

IEC International Electro Technical Commission

MEDC Muscat Electricity Distribution Company

OES Oman Electrical Standards

OETC Oman Electricity Transmission Company

PCR-5 Price Control Review-5 (2018-2021)

PSS Primary Substation

PSS®SINCAL Power System Simulator®Siemens Network Calculation

PV Photovoltaic

SCADA Supervisory Control And Data Acquisition

MEDC Distribution System Capability Statement (2021-2023) – V2.0

Contact details for further info:

Request for a copy of this DSCS, the associated system studies or for any assistance in interpreting or clarifying any information contained within it; please contact:

MEDC Planning Manager P.O. Box: 1239 Hamriya P.C. 131 - Oman Phone: +968 24588514 Email: [email protected]

MEDC Distribution System Capability Statement (2021-2023) – V2.0

1. INTRODUCTION

1.1. Purpose of the Statement The information in the Distribution System Capability Statement (DSCS) is published annually to fulfil MEDC regulatory obligation under Condition 32 of its Distribution and Supply Licence (D&SL) and Distribution planning code 4.4 of the Oman Distribution Code.

This DSCS is intended to provide an understanding of MEDC’s 33kV, 11kV and LV distribution system along with presenting MEDC’s development plans for the 33kV and 11kV distribution system for the years 2021-2023. This statement includes power system data for the station loads, overhead lines, cable circuits, transformers, switchgear and capacitors which forms the MEDC distribution system and used in the preparation of distribution system models for the power system studies. The results of load flow, short circuit studies and system technical losses are presented thereby providing an assessment of the capability of the distribution system.

Implementation of the system development plans is necessary to meet future forecast demand growth, maintain and/or improve the capability in the distribution system to meet the system growth and to address the issues of actual or forecast non-compliance with the Distribution System Security Standard (DSSS). Implementation of these plans will enhance the available system capacity as well as potentially increase the number of 33/11.5kV primary substations (PSS) providing enhanced opportunities for new and increased customer connections.

The impact of MEDC’s forecast demand growth and distribution system development plans on the Transmission System, which is owned and operated by Oman Electricity Transmission Company (OETC), has been fully assessed in the development of MEDC’s development plans. Where appropriate 33kV load transfers from one 132/33kV grid substation (GSS) to another are feasible they have been considered and where this option is not feasible; applications for additional 132/33kV GSS capacity have been submitted to OETC, resulting in OETC plans to construct and build additional 132/33kV GSS capacity within the MEDC licence area.

1.2. Structure of this DSCS

The following summarises the structure of this Distribution System Capability Statement:

• Chapter 2 and Chapter 3 provide relevant information associated with MEDC’s licence obligations, technical standards and system planning drivers along with distribution system connectivity. • Chapter 4 provides a summary view of the distribution system, together with details of the 2020 demand profile along with projected demand forecast, CRT impact analysis of MEDC system, system constraints, update on continuous improvement areas on the system for the DSCS, template of the complete system asset data published this year and a summary of the required technical power system analysis of the distribution system. • Chapter 5 summarises the current levels of connection activity within the MEDC system and provides an overview of the opportunities/challenges new customers potentially could face whilst identifying the challenges that MEDC face currently along with measures to address them. It also details the Photovoltaic (PV) system penetration within the distribution system.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 1

• Chapter 6 provides detail of the MEDC and OETC development projects; proposed over the three- year period 2021 to 2023 to be undertaken within the MEDC licence area. • Appendices detail the summary of the estimated Distribution System Security Standard (DSSS) non-compliances, PV system connections; results of the associated power system studies and a complete set of technical data for the 33kV circuits and primary transformers.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 2

2. P L A N N I N G PHILOSOP H IES AND PRACTICES

MEDC recognise that it is fundamental to provide sufficient guidance to enable relevant stakeholders along with current and potential customers to understand the quality of supply that they may receive from the distribution system; also to enable any person seeking a connection to the system to be able to understand the distribution system at the intended point of connection.

The DSCS below briefly identifies relevant conditions of the Sector Law and the associated Planning Codes and Security Standards that MEDC as a regulated entity must adhere to. It further outlines the key technical standards to which MEDC distribution system is designed and constructed to.

Royal Decree 78/2004 promulgated the Law for the Regulation and Privatisation of the Electricity and Related Water Sector. Article 90 of the D&SL places an obligation on Distribution Companies to undertake financing, operation, maintenance, development and expansion of the distribution system in a safe, economic and efficient manner and in accordance with the relevant performance and security standards.

2.1. Obligations of the Distribution and Supply Licence (D&SL) Condition 4 of MEDC Distribution Licence as entitled ‘Implementation of and Compliance with the Distribution Code’; requires MEDC to become and remain a party to and comply with the provisions of the Distribution Code. It also requires MEDC to co-operate with other Licensed System operators in the maintenance and development of the Distribution Code.

Distribution Licence Condition 32 is titled ‘Distribution System Capability Statement’ and requires MEDC to:

‘On an annual basis, prepare a statement in a form approved by the Authority, showing in respect of each of the three succeeding financial years, circuit capacity, forecast power flows and loading on each part of its Distribution System and fault levels for each transmission node.’

Licence Condition 32 also describes further information that needs to be included within the DSCS relating to:

• Information on the status of the Distribution System, its capacity and envisaged future needs. • Advising potential customers on parts of the system that are best suited to new connections. • Information on the potential system constraints to development. • Provide an overview of current system developments. • Assessment of technical losses.

The full requirements of Licence Condition 32 are found in Appendix A of this document.

The intent of this DSCS is to provide the information as stated above in a form that is relevant and useful to its customers; Authority for Public Services Regulation (APSR) and other stakeholders.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 3

2.2. Requirements of the Distribution Code The Distribution Code covers all material technical aspects relating to connections to, and the operation and use of, the distribution system. The Distribution Code is structured into a number of specific sections.

The Distribution Planning Code (DPC) 2 states that its objectives include for:

‘the exchange of information and interaction between Licensed Distributors and Distribution System Users concerning any proposed development of Distribution System User Systems that are to be connected to the Distribution System’.

DPC 4.4 relates to the obligations of MEDC under its Distribution Licence to produce, on an annual basis, the Distribution System Capability Statement relating to the three succeeding years.

2.3. Distribution System Security Standard As part of maintaining an adequate electricity supply to our consumers; MEDC is obliged under its distribution licence to:

‘plan and develop its Distribution System in accordance with the approved Distribution System Security Standard’1 and to ‘operate and maintain a safe, efficient and economic Distribution System in accordance with the Security Standards’2.

Table 1 provides a summary of the DSSS classifications.

Table 1 : DSSS Classifications and Defined Restoration Times

Class Demand Group First Outage Second Outage

A Less than 2 MW Repair Time No Requirement

B 2MW to 6MW 3 Hours* No Requirement

C 6MW to 20MW Within 15 minutes Restoration time of planned outage

D 20MW to 100MW Immediately Restoration time of planned outage

E Greater than 100MW Immediately Immediately, 2/3 of demand**

*For 11kV networks in remote areas this restoration time may be extended by the time it reasonably takes for a repair crew to reach the area with the outage as long as the total restoration time will not exceed 6 hours

**Planned Outages area assumed to be restricted to non-summer periods when due to lower ambient temperatures demand is reduced and equipment ratings enhanced

The DSSS places an obligation on MEDC to restore supply following a circuit or transformer outage within maximum time limits determined by the total demand within a Demand Group as highlighted in Table 1.

1 Licence Condition 31 (4a) 2 Licence Condition 31 (4a) and (4b)

MEDC Distribution System Capability Statement (2021-2023) – V2.0 4

A first outage is a fault or planned outage occurring at any time of the year including the period of maximum demand. A second outage is a fault outage occurring when an integral part of the system under consideration is not available due to planned maintenance.

The MEDC 33kV system and 33/11.5kV primary substations fall into DSSS classes B to D with the majority being in Class C.

Primary substations in Class B have a maximum demand between 2MW and 6MW. Following a first outage the affected load must be re-supplied within 3 hours. This may be achieved by repair and restoration of the faulted circuit, manual switching at the 33/11.5kV primary substation with two or more transformers to re-supply customers from an alternative transformer or manual switching of the 11kV network feeders to re-supply customers from an alternative 33/11.5kV primary substation.

Substations in Class C have a maximum demand between 6MW and 20MW. Following a first outage the affected load must be re-supplied within 15 minutes. This is achieved by the system configuration and operational control, operating with parallel circuits and remotely operating the circuit breakers from the MEDC Distribution Control Centre via SCADA.

The majority of existing MEDC 33/11.5kV primary substations have 2 x 20 MVA transformers with a N-1 firm capacity of 20MVA. These substations fall into the DSSS Class C classification.

33/11.5kV primary substations in Class D have a maximum demand between 20MW and 100MW. Following a first outage, the affected load must be re-supplied immediately. Immediate restoration means allowing an adequate time for an interruption followed by restoration through an automated transfer switching scheme with restoration effected typically within 60 seconds and upto 3 minutes. Typically, all new primaries constructed are 33/11.5kV primary substations with 3x20MVA transformers which fall into the Class D classification.

2.4. System Voltage Levels and Configuration Distribution Connection Conditions Code (DCC) 4.1 states the following:

The voltage on the 33kV,11kV and LV sides of distribution transformers at connection sites with distribution system users shall normally be controlled within the limits of ± 6.0% of the nominal voltage.

The voltage at customer’s terminals shall not vary from the system nominal voltage +/- allowed tolerances as shown in Table 2.

Table 2 : System Nominal Voltages and Tolerance

Nominal Voltage Tolerance Level +6% -6% 33kV 34.98kV 31.02kV 11kV 11.66kV 10.34kV 415V 439.90V 390.10V 240V 254.40V 225.60V

MEDC Distribution System Capability Statement (2021-2023) – V2.0 5

2.5. Frequency Deviations Distribution Connection Conditions Code (DCC) 4.2 states the following:

During normal operating conditions, the nominal system frequency of the transmission and distribution systems is 50.00 Hz and normally will be controlled by OETC between 49.95 Hz and 50.05 Hz. During exceptional steady state conditions, frequency deviations will not exceed 49.90 Hz to 50.10 Hz unless disturbed circumstances prevail. Under disturbed conditions, System Frequency could rise transiently to 51.50 Hz or fall to 48.00 Hz.

2.6. Voltage Waveform Quality Distribution Connection Conditions Code (DCC) 4.3 states the following:

All apparatus and plant connected to the Distribution System and that part of the Distribution System at each connection point, must be capable of withstanding the distortions of the voltage waveform in respect of harmonic content and phase unbalance.

The maximum total levels of harmonic distortion on the Distribution System at 33kV and 11kV, from all sources under both normal, planned outage and fault outage conditions is required to not exceed a total harmonic distortion of 2.0%, with no individual harmonic greater than 1.5% unless abnormal conditions prevail. At Low Voltage (LV) the maximum total levels of harmonic distortion from all sources is required to not exceed a total harmonic distortion of 2.5%.

The maximum negative phase sequence component of the phase voltage on the Distribution System should remain below 1.0% unless abnormal conditions prevail.

A maximum value of 2.0% is permitted for phase unbalance.

2.7. Voltage Fluctuations Distribution Connection Conditions Code (DCC) 4.4 states the following:

Voltage fluctuations arising from disturbing or fluctuating loads connected at a connection point to the distribution system shall not exceed 1.0% of the voltage level for step changes that may occur repetitively. Any large voltage excursions other than step changes may be allowed up to a level of 3.0% provided that this does not constitute a risk to the distribution system or to any user.

2.8. Auto-reclosing and Single-Phase Protection Operation Distribution Connection Conditions Code (DCC) 4.5 states the following:

Users should be aware that MEDC may use auto-reclosing or automated sequential switching features on the distribution system. MEDC will on request provide details of the auto-reclosing or sequential switching features in order that the user may take this into account in the design of the user system and protection arrangements.

Distribution system users should be aware that the protection arrangements on some distribution systems may cause disconnection of one phase or two phases only of a three-phase supply for certain types of fault.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 6

2.9. Design Fault Levels The design fault levels for the 33kV, 11kV and LV distribution system are stated in OES 11- General Specifications for Electrical Materials and Equipment and is shown in Table 3.

Table 3 : Short Circuit Rating of Switchgear

Voltage Level Rated Short Circuit Capacity 33 kV 25kA (1429 MVA) for 3 sec 11 kV 18.4kA (350 MVA) for 3 sec 11kV (New)* 25kA (476 MVA) for 3 sec LV 40kA (29MVA) for 1 sec

*Note that MEDC has adopted the standard rating for new 11kV primary equipment to be 25kA for 3 seconds.

The 33kV system is earthed via a 12.5 ohm neutral earthing resistor connected to the neutral point of each grid transformer, thereby limiting the maximum prospective 33kV earth fault current to 1,500 A per transformer. The 11kV system is solidly earthed.

2.10. Standard Equipment Sizes Conductors The standard 33kV to LV feeder conductors along with continuous ampere ratings used by MEDC are as specified in OES 1-33kV and 11kV Overhead Lines and OES 2-33kV & Pilot,11kV & LT underground cable installations are shown in Table 4, Table 5 and Table 6.

The continuous ampere ratings shown in Table 4, Table 5 and Table 6 are based on typical manufacturers data and de-rated for the standard installation conditions mentioned in OES 2-33kV & Pilot,11kV & LT underground cable installations. These ratings ensure safe working on the MEDC distribution system given the high temperatures experienced during the summer maximum demand period.

Table 4 : Standard 33kV Conductor Sizes and Ratings

Rated De-rated Conductor Type Conductor Size Capacity Capacity 435 Amps 385 Amps 33kV Cable 300 sq.mm Cu XLPE (25 MVA) (22 MVA) 200 sq.mm ACSR 33kV Overhead 420 Amps (24 MVA) (Panther) *33kV Overhead 150 sq.mm ACSR (Wolf) 350 Amps (20 MVA) *33kV Overhead 100 sq.mm ACSR (Dog) 269 Amps (15.4 MVA)

* Existing overhead conductor present on system; new lines will typically be constructed of 200sq mm ACSR.

Table 5 : Standard 11kV Conductor Sizes and Ratings

Rated De-rated Conductor Type Conductor Size Capacity Capacity 431 Amps 351.6 Amps 11kV Cable 240 sq.mm Cu XLPE (8.2 MVA) (6.7 MVA) 374 Amps 304.4 Amps 11kV Cable 185 sq.mm Cu XLPE (7.1 MVA) (5.8 MVA) 11kV Overhead 150 sq.mm ACSR (Wolf) 350 Amps (6.7 MVA) 11kV Overhead 100 sq.mm ACSR (Dog) 269 Amps (5.1 MVA)

MEDC Distribution System Capability Statement (2021-2023) – V2.0 7

Table 6 : Standard LV Mains Conductor Sizes and Ratings

Conductor Type Conductor Size Rated Capacity LV mains Cable 240 sq.mm XLPE 455A LV mains Cable 185 sq.mm XLPE 394A LV mains Overhead 200 sq.mm ACSR 420A

Transformers Standard 33/11.5kV transformer sizes are specified in OES 6-33/11.5kV Transformers as being 1, 3, 6, 10MVA ONAN and 20MVA ONAF, although other sizes such as 5 and 16MVA do still exist on the system. The overload capability above the transformer name-plate rating has been confirmed through modelling3 and supported by a limited number of measurements. MEDC has standardized on 20MVA ONAF transformers in the urban areas.

MEDC is studying the feasibility of increasing the 33/11.5kV transformer rating for new substations in areas of high demand density to cope with the high demand growth and the limitation of available land in such areas.

Standard as a minimum 11/0.433kV ground mounted transformer sizes specified in OES 5-11kV/433V distribution transformers are 1000, 500, 315, 200 and 100kVA, whereas 1250,1600,2000,2500 and 3000kVA distribution transformers do exist in the network. The most commonly used distribution transformers in the network are the ground mounted 500, 1000 and 2000kVA units; which form circa 87% of the distribution transformers on the system. The system also has a range of pole mounted transformers from 50, 100, 200 and 250kVA to be used as required.

Switchgear Minimum 33kV and 11kV switchgear ratings are specified in accordance to OES 14-11kV Indoor Switchgear and OES 15-33kV Indoor Switchgear as shown in Table 7.

Table 7 : Standard Switchgear Ratings

Voltage Description Ratings 33kV Feeder 600 A 33kV Bus Section 1200 A 11kV TX Incomer 1200 A 11kV Bus Section 1200/1250* A 11kV Feeder 400/630* A

*MEDC have adopted and standardised to these based on market availability

Capacitors All new 125 MVA grid substations are designed with a single 20 MVAr capacitor bank connected to each 33kV busbar section. All new 20 MVA primary substations are designed with a single 5 MVAr capacitor bank connected to each 11kV busbar section.

3 Based on IEC 60076-7 calculations

MEDC Distribution System Capability Statement (2021-2023) – V2.0 8

The capacitor banks are as specified in OES 13-11.5kV 5MVAr Capacitor Banks and consist of 5 x 1MVAr units with one set of capacitor banks connected to each bus section. The aim of the capacitors is to ensure that MEDC maintains power factor and voltage to be within prescribed limits to start with at the 11kV busbars but certainly at the 33kV busbars in accordance to the Grid Code.

2.11. Technical Standards In order that MEDC can operate a safe and efficient electricity distribution system all apparatus and plant associated with the connection to the distribution system are required to comply with the following standards, as applicable:

(a) Health and Safety Rules;

(b) Oman Electrical Standards (OES), which are such national standards as may be approved by and amended by the APSR as necessary;

(c) Grid Code;

(d) Distribution Code;

(e) The standards and recommendations of the International Standards Organisation and the International Electro Technical Commission (IEC); and

(f) national standards and codes, which are accepted internationally.

2.12. Specification of Apparatus and Plant The specifications of all connected plant are required to allow the safe operation of the MEDC distribution system within its operational procedures. Details of this can be obtained by contacting MEDC directly.

Apparatus and Plant must be suitable to use at the operating frequency and within the intended operating voltage range. This associated equipment should also be suitable to operate to the maximum design short-circuit rating of the distribution system to which it is connected having due regard to fault carrying capabilities including making and breaking duties. As necessary MEDC will provide additional details of the system at the point at which a specific connection is to be made.

Apparatus and plant must be operated within the thermal rating conditions contained in the appropriate standards, specifications, and other relevant publications, taking into account its intended use. Upon request MEDC will provide this information .

2.13. Earthing MEDC will provide advice on the method of earthing of the distribution system, for example, whether it is connected solidly to earth or through impedance. The specification of associated apparatus and plant of the connected customer equipment must meet the voltages that will be imposed on the apparatus and plant as a result of the method of earthing. The method of earthing must comply with the requirements of Distribution Connections Code Cl 5.2.1.

Users should take precautions to limit the occurrence and effects of circulating currents in respect of the neutral points connected with Earth where there is more than one earthed neutral point.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 9

2.14. Voltage regulation and control Any extension or Connection to the distribution system should be designed so as to not adversely affect the voltage control employed by MEDC on the distribution system. MEDC will make information on the voltage regulation and control arrangements available if requested by the User.

2.15. Protection MEDC’s system and the system of any User must incorporate protective devices to ensure that apparatus and plant with electrical faults are disconnected from the system promptly and that the effects of faults on one system do not impose unreasonable risks to other systems.

To ensure satisfactory operation of the distribution system; protection systems, operating times, discrimination and sensitivity at the ownership boundary must be agreed between MEDC and the User during the process of application for Connection and may be reviewed from time to time by MEDC with the agreement of the User.

Back-up protection by operation of other circuit breakers or apparatus and plant having a similar function must normally be provided to safeguard the system against a circuit breaker, or apparatus and plant having a similar function, failing to operate correctly to interrupt the fault current on a high voltage system. During the process of application for Connection, MEDC will advise the User if back- up protection is not required.

Users must not use protection or associated equipment to limit the fault current infeed to the distribution system unless expressly permitted by MEDC to avoid protection operation malfunctioning loading to system assets exceeding short-circuit ratings.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 10

3. PLANNING DRIVERS

3.1. Background MEDC’s electricity distribution system serves around 413,367 customers (as of July 2020) over an approximate area of 3,900 sq.km and is divided into three geographic zones. Figure 1 represents an overview of the MEDC distribution system within the including the system boundaries, zones, the GSS and 33/11kV circuits. The characteristics of the distribution system within the MEDC licence areas differ mainly because of three major parameters:

1) The load density; 2) The type and usage pattern of the customer; 3) The majority type of feeder circuits (i.e. overhead or underground).

The 2020 maximum demand4 recorded for MEDC system was 2322.9 MW (2445.2 MVA on Sunday - 05th July 2020 at 14:51 Hrs).

As of July 2020 the total existing number of 132/33kV grid substations is 355, 33/11.5kV primary substations connected to the MEDC distribution system is 177 with a Total Installed Capacity of 6,828 MVA and a firm capacity of 3,903.5 MVA. The tables identifying each Primary Substation capacity and current demand can be found in the Appendix D.

The sections remaining from this chapter provide the following:

1) An indicative geographical view of the complete MEDC distribution system and zone wise view of the grid substations, primary substations, 33kV and 11kV circuits; 2) A summary of the individual zone built up and the planning drivers for each zone; 3) It also provides an overview of the complete current MEDC system connectivity including the area classification for the primaries.

Area name classification in Table 8 -Table 10 below refers to the area what that PSS falls under and hence the associated Compound Annual Growth Area (CAGR) % being applied to that PSS. The concept of CAGR % and the area classification are explained in detail in Section 4.1.

4 The 2020 OETC system maximum demand day was on a different date (17th June 2020;afternoon at 14:41 Hrs). 5 The summation of the GSS in the table 8-10 shows 33 as two GSS namely Airport Height and Misfah are duplicated due to the dual feeder arrangements.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 11

Figure 1 : MEDC Distribution System with GSS

MEDC Distribution System Capability Statement (2021-2023) – V2.0 12

3.2. Zone 1 – (The Eastern Zone) The Zone 1 region includes the capital city of Muscat, and an extensive rural network, which covers the wilayats of Amerat and Quriyat. The number of customers served in the Zone 1 region is 130,855 which is approximately 32% of the total customer population. Figure 2 below provides the geographical overview of the primary MEDC distribution system in Zone 1.

Figure 2 : Zone 1 Distribution System with PSS

Amerat has seen the highest demand growth for the last 5 years within the Zone 1 region validating for a significant demand growth forecasted for the current planning horizon.

The Muttrah Tourism Development project along with Yitti Tourism Development and Fins Project are the major upcoming development projects in the planning horizon of this DSCS as of yet. Table 8 below provides the GSS and primary distribution system connectivity for Zone 1.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 13

Table 8 : Zone 1 - Grid and Primary Substations Connectivity6

Installed Tx Firm Tx - S. No Grid Station [G-No] P-No Primary Station Name Capacity Capacity Area Name Config (MVA) (MVA)

1 P178 Falaj 2 x 16 32 16 Mutrah 2 P018 Darsait 2 x 20 40 20 Mutrah 3 P085 Mutrah Store 2 x 20 40 20 Mutrah Falaj[G23] 4 P041 Jibrooh 3 x 20 60 40 5 P086 Seaport 2 x 6 12 6 Private 6 P144 P.D.O 3 x 20 60 40 Private 7 P173 C.B.D 3 x 16 48 32 Mutrah 8 P108 Ruwi Office 2 x 20 40 20 Ruwi Mutrah[G21] 9 P142 Bait Al Falaj 3 x 20 60 40 Mutrah 10 P099 2 x 20 40 20 Muscat 11 P075 M.B.D. South 2 x 20 40 20 WadiKabir 12 P090 Qasr Al Alam 2 x 20 40 20 Muscat 13 P130 Waljah 2 x 20 40 20 Ruwi

14 Wadi Al Kabir[G19] - P119 2 x 6 12 6 WadiKabir 15 A P126 Wadi Al Kabir Workshop 2 x 6 12 6 WadiKabir 16 P127 Wadi Al Kabir Housing 1 x 6 6 0 WadiKabir 17 P125 Ali Shihani 2 x 20 40 20 WadiKabir 18 P066 Majlis Oman 2 x 20 40 20 WadiKabir 19 P174 Ruwi Valley 2 x 20 40 20 WadiKabir

20 Wadi Al Kabir[G19] - P076 Ruwi Market 2 x 20 40 20 Ruwi 21 B P107 Old Airport 2 x 20 40 20 Ruwi 22 P128 Wadi Al Kabir Height 2 x 20 40 20 WadiKabir 23 P005 Amerat 1 2 x 16 32 16 Amerat 24 P089 1 x 3 3 0 WadiKabir 25 P017 Al Bustan Palace 2 x 16 32 16 Private 26 P035 Al Hamryah 2 x 20 40 20 WadiAdai Wadi Adai[G22] 27 P175 Wadi Adai 2 x 20 40 20 WadiAdai 28 P131 Wattaya 2 x 20 40 20 WadiAdai 29 P132 Khoula Hospital 3 x 20 60 40 WadiAdai

30 P136 Al Mahaj 2 x 6 12 6 Amerat

31 P112 Sawaqim 1 2 x 6 12 6 Sawaqam-O/D 32 P113 Sawaqim 2 1 x 6 6 0 Sawaqam-O/D 33 P137 Tunis Heium 1 x 6 6 0 Hajir-O/D 34 P040 Jahloot 2 x 6 12 6 Jahloot-O/D Jahloot[G03] 35 P120 Siya 2 x 6 12 6 Jahloot-O/D 36 P044 Barr Al Jissah 2 x 20 40 20 Private 37 P068 Al Masarat 2 x 10 20 10 Private 38 P031 Al Hajir 2 x 20 40 20 Hajir-O/D

6 All single transformer primary substations firm capacity will be equivalent to the available 11kV transfer capacity on the distribution system; which is not added to the total firm capacity of the MEDC system due to the dynamic nature.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 14

Installed Tx Firm Tx - S. No Grid Station [G-No] P-No Primary Station Name Capacity Capacity Area Name Config (MVA) (MVA)

39 P129 Wadi Al Mayh 1 x 3 3 0 Hajir-O/D 40 P169 Hussan 2 x 6 12 6 Private 41 P114 Debah 1 x 6 6 0 Sawaqam-O/D 42 P162 ROP Al Saleel 2 x 6 12 6 Private 43 P182 Al Atkiya 1 x 6 6 0 Hajir-O/D 44 P193 Water Pumping 2 x 6 12 6 Private 45 P121 Arqi 1 x 3 3 0 Jahloot-O/D 1 x 6 + 1 46 P045 Al Khairan 9 3 Yiti-O/D x 3 1 x 1 + 1 47 P133 Yenket 4 1 Yiti-O/D x 3 48 Yiti[G08] P145 Saraya Bander 3 x 20 60 40 Private 49 P159 Jabal Al Sifah 3 x 20 60 40 Private 50 P134 Yiti 2 x 3 6 3 Yiti-O/D 51 P135 Al Salam Yiti 1 x 6 6 0 Yiti-O/D 52 P091 Quriyat 2 x 20 40 20 QuriyatGroup 53 P092 Al Shahbari 2 x 20 40 20 QuriyatGroup QuriyatGroup- 54 P021 Dhagmar 1 4 x 6 24 18 O/D QuriyatGroup- 55 P019 Dhabab 2 x 6 12 6 O/D QuriyatGroup- 56 Quriyat[G05] P036 Hail Al Ghaf 2 x 6 12 6 O/D QuriyatGroup- 57 P074 Al Mazara 2 x 6 12 6 O/D QuriyatGroup- 58 P124 Wadi Al Arbyeen 1 x 6 6 0 O/D 59 P020 Street Light 1 x 6 6 0 Private 60 P170 RoyalCamp 1 x 3 3 0 Private 61 P150 Post Office 3 x 20 60 40 Amerat 62 Amerat[G10]-A P152 Amerat Heights 3 x 20 60 40 Amerat 63 P179 Amerat 3 3 x 20 60 40 Amerat 64 P194 Al Jufaina 1 x 6 6 0 Amerat 65 P118 Seih Dhabi 2 x 16 32 16 Amerat Amerat[G10]-B 66 P006 Al Nahdah 3 x 20 60 40 Amerat 67 P065 Madinat Al Nahdah7 2 x 20 40 20 Amerat Dhagmar [GP11] It is a 132/11kV Grid Station. So, no PSS is connected in this Grid. 3.3. Zone 2 - (The Central Zone) The Zone 2 region covers the commercial and residential areas of Bousher, Al Khuwair, Al Ansab, Azaibah, Al Gubrah, Madinat Al-Sultan Qaboos (MSQ) and Qurum. The number of customers served in the Zone 2 region is 118,759 which is approximately 29% of the total customer population. Figure 3 below provides the geographical overview of the primary MEDC distribution system in Zone 2.

7 Madinat Al Nahdah – P065 is having split feeder source arrangement with Feeder 1 connected from Amerat B grid and Feeder 2 connected from Jahloot grid.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 15

Figure 3 : Zone 2 Distribution System with PSS

The Mall of Oman is the largest expected commercial project along with Intercontinental Hotel (Expansion), Sarooj area developments, ROP projects in Airport Height area, Madinat Al Irfan Development project to come in the planning horizon of this DSCS as of yet. Table 9 below provides the GSS and primary distribution system connectivity for Zone 2.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 16

Table 9 : Zone 2 - Grid and Primary Substations Connectivity6

Installed Capacity Tx Firm Capacity S. No Grid Station [G-No] P-No Primary Station Name Tx -Config Area Name (MVA) (MVA) 1 P012 Azaibah North 2 2 x 20 40 20 Azaibah 2 P014 Azaibah South 1-A 2 x 20 40 20 Azaibah 3 P149 Ghubrah North 2 3 x 20 60 40 Azaibah Ghubrah 2[G09] 4 P023 Ghubrah North 1 3 x 20 60 40 Azaibah 5 P022 Diplomatic City 3 x 20 60 40 Sarooj 6 P166 Ghubrah GPS 2 x 16 32 16 Private 7 P054 Al Khuwair North 3 x 20 60 40 Khuwair 8 GP06 MSQ Grid 2 x 20 40 20 MSQ 9 P097 Royal Office 2 x 20 40 20 Private MSQ[GP06]-A 10 P109 Intercontinental 2 x 20 40 20 Sarooj 11 P038 Information City 2 1 x 5 5 0 Private 12 P110 Sarooj -Shati Al Qurum 2 x 20 40 20 Sarooj 13 P053 Al Khuwair 25 2 x 20 40 20 Khuwair 14 P146 Al Khuwair School 3 x 20 60 40 Khuwair 15 MSQ[GP06]-B P083 MSQ 1 2 x 20 40 20 MSQ 16 P111 ROP -Shati Al Qurum 2 x 20 40 20 Sarooj 17 P039 Digital TV Studio 2 x 20 40 20 Private 18 P037 Information City 1 2 x 20 40 20 Sarooj 19 P093 Qurum 1 2 x 16 32 16 Qurum 20 P094 Qurum 2 2 x 20 40 20 Qurum Qurum[G06] 21 P095 Lulai 2 x 20 40 20 Qurum 22 P155 MSQ 2 3 x 20 60 40 MSQ 23 P096 Rabiat Al Qurum 2 x 20 40 20 Qurum 24 P147 Azaibah South 1-B 3 x 20 60 40 Azaibah 25 GP02 Bousher Grid 2 x 20 40 20 Bousher 26 Bousher[GP02]-A P052 Al Khuwair South 3 x 20 60 40 Khuwair 27 P050 Al Khuwair 17/1 2 x 20 40 20 Khuwair 28 P024 Royal Hospital 3 x 20 60 40 GhubrahSouth 29 P007 Al Ansab 1 2 x 20 40 20 Ansab 30 P011 Azaibah North 1 2 x 20 40 20 Azaibah 31 P026 Ghubrah South 1 3 x 20 60 40 GhubrahSouth 32 Bousher[GP02]-B P051 Holiday Inn 3 x 20 60 40 Khuwair 33 P084 Al Muna 2 x 20 40 20 Bousher 34 P163 Bousher 2 3 x 20 60 40 Bousher 35 P055 Tilal Al Khuwair 3 x 20 60 40 Khuwair 36 P008 Al Ansab 2 2 x 20 40 20 Ansab 37 P165 Oman Exhibition 3 x 20 60 40 Private 38 P156 Ghala 2 3 x 20 60 40 Ansab Ghala[G11] 39 P167 MOD Al Ansab 2 x 10 20 10 Private 40 P172 ROP Hospital 3 x 20 60 40 Private 41 P009 Al Ansab STP 2 x 20 40 20 Private 42 P015 Ghala 1 3 x 20 60 40 Azaibah 43 P002 Airport Height 2 2 x 20 40 20 Airport 44 P001 Airport Height 1 2 x 20 40 20 Airport 45 P013 Azaibah North 3 3 x 20 60 40 Azaibah Airport Height [G01] 46 P151 Airport Height 5 2 x 20 40 20 Airport 47 P003 Airport Height 3 2 x 20 40 20 Airport P172 ROP Hospital 1 x 6 6 0 Private 48 P004 Airport Height 4 2 x 20 40 20 Airport 49 Ghala Heights[G24] P171 Mall of Oman 3 x 20 60 40 Private 50 Misfah[G04] P139 Al Awabi 3 x 20 60 40 Misfah

MEDC Distribution System Capability Statement (2021-2023) – V2.0 17

3.4. Zone 3 - (The Western Zone) The Zone 3 region includes the Muscat International Airport, Rusail Industrial Area, , Mawalleh, Al Khoud, Al Hail and Mabelah areas. The number of customers served in the Zone 3 region is 163,753 which is approximately 39% of the total customer population. Figure 4 below provides the geographical overview of the primary MEDC distribution system in Zone 3.

Figure 4 : Zone 3 Distribution System with PSS

Mabelah area is one of the largest commercial and residential areas located within the Zone 3 region. These developments will be in the commercial and residential areas.

Rusail industrial area is earmarked for some significant development projects by Public Establishment for Industrial Estates(PEIE) and Knowledge Oasis Muscat(KOM), Al Mouj Expansion, Naseem A’Saba development and MOD-Al Bander within this planning horizon. Table 10 below provides the GSS and primary distribution system connectivity for Zone 3.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 18

Table 10 : Zone 3 - Grid and Primary Substations Connectivity6

Installed Tx Firm S. No Grid Station [G-No] P-No Primary Station Name Tx -Config Capacity Capacity Area Name (MVA) (MVA) 1 Airport Height[G01] P081 MOD Technical College 2 x 20 40 20 Airport 2 P080 Al Misfah 3 x 20 60 40 Misfah 3 Misfah[G04] P192 Orpic 2 x 6 12 6 Private 4 P079 Cement Factory 1 2 x 31.5 + 3x20 123 91.5 Private 5 P122 SQU 1 3 x 16 48 32 Private 6 P123 SQU 2 2 x 16 32 16 Private 7 P103 Rusail Industrial 1 2 x 16 32 16 Rusail Rusail 8 P104 Rusail Industrial 28 2 x 20 40 20 Rusail Industry[G13]-A 9 P042 Al Jifnain 1 x 6 6 0 Jifnain-O/D 10 P196 Al Jifnain 2 1 x 6 6 0 Jifnain-O/D 11 P088 Cement Housing 2 x 5 10 5 Private 12 P105 Rusail Industrial 3 2 x 20 40 20 Rusail 13 P056 Rusail Housing 2 x 20 40 20 Rusail 14 P106 Rusail Private Factory 2 x 20 40 20 Rusail 15 Rusail P164 Rusail08(KOM) 3 x 20 60 40 Rusail Industry[G13]-B 16 P161 ROP Al Khoud 2 x 20 40 20 Private 17 P158 Rusail Industrial 4 3 x 20 60 40 Rusail 18 P160 SQU 3 3 x 20 60 40 Private 19 P067 Manomah 2 x 20 40 20 Private 20 P061 Mabelah South 2 x 20 40 20 Mabelah Barka[G02] 21 P033 Palace Communication 1 x 6 6 0 Private 22 P034 RGO Camp 1 x 5 5 0 Private 23 GP04 Mabelah Grid 2 x 20 40 20 Mabelah 24 P063 Mabelah A 3 x 20 60 40 Mabelah 25 P116 Sur Al Hadid 2 x 20 40 20 Seeb 26 P059 Old Mabelah9 2 x 20 40 20 Mabelah Mabelah[GP04] 27 P016 Botanic Garden 2 x 20 40 20 Private 28 P141 Mabelah South PH-7 3 x 20 60 40 Mabelah 29 P183 ROP Dog Kennel 2 x 6 12 6 Private 30 P140 Mabelah STP 2 x 10 20 10 Private 31 P060 Mabelah Shabiya 3 x 20 60 40 Mabelah 32 P064 Mabelah C 3 x 20 60 40 Mabelah 33 Mabella 2[G12] P062 Mabelah South PH-4 3 x 20 60 40 Mabelah 34 P157 Mabelah South PH-8 3 x 20 60 40 Mabelah 35 P168 Palm Mall 3 x 20 60 40 Mabelah 36 P046 Al Khoud Shabiya 2 x 20 40 20 Khoud 37 P098 Wadi Bahayis (RGO) 2 x 20 40 20 Seeb 38 Seeb[GP08]-A P115 Wadi Al Aresh 2 x 20 40 20 Seeb 39 P117 Wadi Al Lawami 3 x 20 60 40 Seeb 40 P154 Al Khoud PH-7 3 x 20 60 40 Khoud 41 GP08 Seeb Grid 2 x 20 40 20 Seeb 42 P029 Sultan School 2 x 20 40 20 Hail 43 Seeb[GP08]-B P186 BoulevardMall(Seeb-5) 3 x 20 60 40 Seeb 44 P047 New Al Khoud 2 x 20 40 20 Khoud 45 P153 Al Hail South 2 3 x 20 60 40 Hail

8 Rusail Industrial 2 – P104 is having split feeder source arrangement with Feeder 1 connected from Rusail Industry Grid A and Feeder 2 connected from Rusail Industry Grid B. 9 Old Mabelah - P059 is having a split feeder source arrangement with Feeder 1 from Barka Grid and Feeder 2 from Mabelah 1 Grid.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 19

Installed Tx Firm S. No Grid Station [G-No] P-No Primary Station Name Tx -Config Capacity Capacity Area Name (MVA) (MVA) 46 P028 Al Hail North 2 2 x 20 40 20 Hail 47 GP05 Mawaleh South Grid 2 x 20 40 20 Mawaleh

48 Mawaleh P072 Mawaleh C 2 x 20 40 20 Mawaleh 49 South[GP05]-A P048 Al Khoud PH-3 2 x 20 40 20 Khoud 50 P101 Rusail B 2 x 10 20 10 Mawaleh 51 P100 Royal Flight 2 x 20 40 20 Private 52 P070 Mawaleh A10 3 x 20 60 40 Mawaleh 53 P071 Mawaleh B11 3 x 20 60 40 Mawaleh Mawaleh 54 P049 Al Khoud PH-6 2 x 20 40 20 Khoud South[GP05]-B 55 P030 Al Hail South 1 2 x 20 40 20 Hail 56 P148 Mawaleh South05 3 x 20 60 40 Mawaleh 57 P027 Al Hail North 1 2 x 20 40 20 Hail

58 Mawaleh North P069 Mawaleh North 2 x 20 40 20 Hail 59 [GP01] GP01 Mawaleh North Grid 3 x 20 60 40 Private 60 P073 City Centre 2 x 20 40 20 Mawaleh

10 Mawaleh A – P070 is having split feeder source arrangement with their Feeders 1&3 for each primary connected from Mawaleh South B Grid and Feeder 2 from Mawaleh South A grid. 11 Mawaleh B – P071 is having split feeder source arrangement with their Feeders 1&3 for each primary connected from Mawaleh South B Grid and Feeder 2 from Mawaleh South A grid.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 20

4. MEDC DISTRIBUTION SYSTEM

MEDC is authorized to undertake all regulated activities of electricity distribution and supply business at 33kV and below across the whole area of Muscat including Seeb, Bousher, Muscat, Muttrah, Amerat and Quriyat Wilayats.

The distribution system has three nominal voltages; i.e. 33kV, 11kV and 415V.

Most customers connect at LV (415 Volt) and there are bulk customers connected at 11kV and 33kV. Similarly there are 4 no. large customers connected on the OETC 132kV side but are MEDC customers for the purposes of energy supply and billing.

4.1. Existing Distribution System The existing MEDC distribution system asset statistics including the installed capacities are as shown in Table 11 (as of July 2020).

Table 11 : Summary of Distribution System Assets

33kV 11kV LV Overhead Line 963.9km 1119.3km 1789.2km Underground Cable 1391.9km 3650.1km 7847.0km GSS PSS DSS No. of Substations 35*12 17713 8891 No. of Transformers 71* 393 11,738 Installed MVA 8650* 6828 13,443

*Feeding MEDC Licence area; owned by OETC

Table 12 provides a summary of the existing 33/11.5kV primary power transformers installed and firm capacity, out-of-firm and max demand per zone (as of July 2020).

Table 12 : Summary of Installed and Firm Capacities of MEDC Distribution System

No of Installed Firm Max. Demand Out of Firm Zone PSS Capacity Capacity 202014 (MVA) (MVA) (MVA) (MVA) 1 67 1901 1029 14 679.3 2 50 2335 1362 0 883.8 3 60 2592 1512.5 32.4 1122.7 Total 177 6828 3903.5 46.415 2685.8

Figure 12 (later in this section) illustrates electrically the existing 33kV MEDC system (2020).Table 13 provides a summary of the historic demand growth providing the context for demand growth seen in the MEDC system. Over the previous 7 years, MEDC has seen significant growth in specific areas16. The Compound Annual Growth Rate [CAGR]% for the year 2013-2020 has been used to inform our demand

12 The GSSs with 4x125 MVA configuration are counted as two grids.

13 4 No. Outdoor PSS namely P190,P191,P143 and P177 have been dismantled compared to previous DSCS, reducing the total to 177 PSS.

14 Max.Load - based on summation of individual primary substation loads occurring at different times; hence is different from the MEDC system level maximum demand of 2445.2MVA which is summation of primary demands on the system maximum demand day/time. 15 Unaudited figure for 2020 as an indication only. 16 The areas are defined on geographical and electrical connectivity basis as ratified by the zonal teams.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 21

forecast going forward to 2023. In the below table a negative CAGR % indicates no growth in the past years hence for the purposes of load forecasting a zero load growth will be applied on those areas which have negative growth in the 2013-2020 period.

Table 13 : Area Wise Compound Annual Growth Rate[CAGR] % of MEDC Distribution System

CAGR (%) Zone Area 2013 -2020 2017 -2020

1 Amerat 10.9% 5.9%

1 QuriyatGroup 3.6% -0.2%

1 Ruwi -2.3% -4.7%

1 WadiAdai -1.9% -4.6%

1 WadiKabir -2.5% -0.8%

1 Muscat -2.2% -3.9%

1 Mutrah -1.6% -3.6%

1 QuriyatGroup-O/D 3.0% -5.9%

1 Yitti-O/D 5.5% 8.9%

1 Jahloot-O/D 9.8% 20.9%

1 Sawaqm-O/D 8.2% -3.3%

2 Bousher 9.3% 2.3%

2 Ansab 4.2% 0.5%

2 Airport 2.1% -5.0%

2 Khuwair 3.4% -2.3%

2 Azaiba 3.7% -4.4%

2 MSQ 1.9% 0.5%

2 Sarooj -2.0% -2.6%

2 GhubrahSouth 1.7% -0.3%

2 Qurum 1.6% -4.9%

3 Mabelah 10.3% 5.9%

3 Misfah17 6.2% 1.7% 3 Seeb 3.0% -2.2% 3 Khoud 5.4% -0.9%

3 Jifnain-O/D 6.2% 1.7%

3 Rusail 6.2% 1.7%

3 Mawaleh 2.5% -5.0%

3 Hail 2.6% -1.0%

4.2. System Demand and Load Duration The Maximum and Minimum Demand for the MEDC distribution system in 2020 is illustrated in Table 14 below. This shows that the 2020 minimum demand is circa 23.5% of the 2020 maximum demand for the MEDC system.

17 The CAGR% used for Misfah is based on an area with similar load characteristics as are created post 2014.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 22

Table 14 : Maximum and Minimum System Demands

System Date & Time Load (MW) Load (MVA) Demand Maximum 2322.9 2445.2 05th July 2020 @ 14:51 Hrs Minimum 545.3 574 13th January 2020 @ 04:00 Hrs

MEDC note that the date of system maximum demand has fluctuated throughout the years. System maximum demand has occurred generally between the summer months starting from May to July; although there seems to be no exact co-relation on the exact timing as expected. There are various parameters which affect the occurrence of the system maximum demand hence the future forecast; we expect more parameters in the upcoming future especially due to the macro-economic condition of the Oman economy and due to the developments in newer technologies. Few of the significant parameters which have impacted MEDC distribution system growth in 2020 and future are :

1) Temperature and Humidity; 2) Customer nos and types of customer growth; 3) Socio-economic factors like state of economy due to oil prices; 4) Implementation of CRT and the continuous effect; 5) Impact of COVID-19 pandemic.

This can result in a lack of consistent predictability as to the precise date of future system peaks; although provides a good indication in general of the period and pattern. For this reason; associated demand transfers are operationally planned to occur before May period each year to ensure MEDC are in the best position possible to meet regulatory requirements and ensure quality and security of supply to consumers.

Figure 5 below indicates that from the historical data [2013-2020]; the system maximum demand day load profile pattern is generally consistent with each other18. As it can be seen from Figure 7; the maximum demand % growth i.e. growth magnitude has been inconsistent especially between 2013 and 2020; due to the factors mentioned above.

Figure 5 : Hourly Demand – System Maximum Day Profile 2013-2020

System Peak Day Profile [2013-2020] 2500.0

2250.0

2000.0

1750.0

1500.0

1250.0

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MaximumDemand (MW) Time(Hours)

5-Jul-20 30-Jun-19 25-Jun-18 31-May-17 12-Jun-16 5-Jul-15 26-Jun-14 16-Jun-13

18 The 2013 hourly profile, compared with the previous capability statements; the data was verified and corrected in the 2018 DSCS to reflect reality.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 23

The maximum demand data is supplemented with the associated load duration curve shown in Figure 6. This graph below represents a period of last 9 months (Jan – Sept 2020). The peak demand was circa 63% of the firm capacity [3,903.5 MVA / pf (0.95) =3708.3 MW] and the system load is greater than 1500MW for circa 54% of the time during the measurement period as indicated in Figure 6 below along with the spread of load against the no of hours for the year. The associated distribution and utilisation of MEDC’s distribution assets are seen to be generally in line with common distribution utility practice.

Figure 6 : Load Duration Curve

Similar to the system maximum demand, the date of system minimum demand has fluctuated throughout the years. System minimum demand has occurred generally between the winter months starting from January to February between 03:00 AM to 05:00 AM. Figure 7 illustrates that the system maximum/minimum demand including grid connected customers and total customer nos. have generally grown year on year following a similar growth trend.

Figure 7 : Maximum & Minimum Demand19 with Customer Numbers Growth

Max/Min Demand and Customer Nos. growth Year 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 450,000 413,367 2600 2400 400,000 2322.9 2200 350,000 2000 300,000 1800

1600 Load(MW) 250,000 1400 200,000 1200 1000 150,000 545.3 800 100,000 600 Customer Customer Number 400 50,000 200 0 0 Number of Customers Maximum Load(MW) Minimum Load(MW)

19 Minimum Demand data available from 2009 onwards only and hence plotted starting 2009.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 24

4.3. Cost Reflective Tariff (CRT) In October 2016, The Regulator announced that the Council of Ministers had approved the introduction of a new tariff for high value customers called the Cost Reflective Tariff (CRT) and implemented fully in 2017. The new tariff is designed to more accurately reflect the actual costs of providing a supply of electricity to large government, commercial and industrial customers without government subsidy. The current approval for CRT implementation is for application only to the high value customers who consume 150 MWh and above in a year, for the above-mentioned customer categories.

As the full 2020 cycle hasn’t been completed yet an impact analysis was undertaken on 2019 MEDC customer base to understand the full year impact of CRT on the MEDC distribution system and described as below.

The number of CRT customers in 2019 was 5138, circa 1.3% of the total connected customers and as shown in Figure 8 this 1.3% of the CRT customers out of the MEDC total customer base consumed 39.3% of total energy distributed by MEDC in 2019.

Figure 8 : MEDC 2019 CRT and Non-CRT Units Sold (MWh)

2019 CRT & Non CRT Units Sold (MWh)

4,526,949 6,980,243 39% 61% CRT Non CRT

Post implementation of the CRT; the revenue realization per MWh for 2019 MEDC CRT customers was 26.01 OMR. The economic cost of electricity supply in MEDC was approximately 28.3 OMR per MWh in 2019; hence this results in a government subsidy of circa 2.3 OMR per MWh for CRT customers. As a total this resulted in a government subsidy of circa 10M OMR for CRT customers in 2019 compared to circa 22M OMR in 2018 resulting in net reduction for government subsidies.

The average realization rate across all customers (non-CRT to CRT from 2019) per MWh for MEDC in 2019 was 18.33 OMR/MWh compared to 17.73 OMR/MWh in 2018.

The effect of CRT implementation on the MEDC system maximum demand profile is quite evident in the form of peak shaving; especially due to the industrial customers.

From the observed 2020 load curve on the MEDC system maximum demand (05th July 2020); as an example two large industrial customers normally consuming circa 30MW of demand have reduced there load contribution to the MEDC system maximum demand during the peak hours (i.e. 1:00 pm to 5:00pm) of the week to effectively zero in comparisons to previous year’s as visible from the demand profile’s in Figure 9. As seen from Figure 9 Industrial customer no.1 load on the MEDC system reduced from the normal circa 7MW during the peak hours in 2017 to circa 0MW in 2018 ,2019 and 2020.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 25

Figure 9 : CRT Customer’s Profile on the System Peak Day for 2017 - 2020

4.4. Demand Not Secured (DNS) As per the licence condition; MEDC is obliged to comply with the DSSS and moreover one of our major investment drivers for the CAPEX programme is to meet the N-1 operational capability for each Primary Substation.

Figure 10 below provides a trend of the MEDC Demand Not Secured (DNS) MVA performance; as a measure to show DSSS compliance improvement along with number of Primary Substations contributing to the DNS. It can be seen that in the recent years the DNS performance in consistently improving and the unaudited 2020 DNS for MEDC realised is 46.4MVA which is a circa 74% reduction compared to 2019 DNS value of 178.1MVA.

MEDC distribution system predominantly is a urban dense interconnected network and as part of network design optimum effort is made to maintain that level of interconnection leading to majority of the 11kV feeders except minor rural feeders having not single but multiple interconnections. Hence majority of the 11kV feeders will come under the Class A and Class B categories. Typically with the assistance of these 11kV interconnections, the supply can be generally restored within the allowed DSSS time frame.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 26

Figure 10 : DNS Historical Data

4.5. 11kV Feeder Loadings As detailed in the Table 15 below six non-compliant 11kV feeders were observed in 2020 which exceeded the thermal loading limit under normal operational configuration; these will be solved by appropriate 11kV load transfers, reinforcement schemes and/or automation in 2021 itself.

Table 15 : 11kV Non-Compliant Feeders

PSS Name Feeder Name Load (Amps) Zone 1 Amerat 3 - P179 KLN08 377 Zone 2 Al Ansab 02 - P008 KLN07 368 Holiday Inn - P051 KLN13 356.3 Al Khuwair 25 - P053 KLN01 356.1 Zone 3 Mabelah South Ph 4-P062 KLN04 389.7 Al Misfah-P080 KLN12 353.6

4.6. System Demand Forecast Accurate and realistic load demand forecasting is critical for the effective operation of the distribution system and is the principal driver for capital expenditure. Realistic assumptions must be made for inherent uncertainties in forecasting and the underlying socio-economic factors, such as the sustained low oil price and exceptional events like the COVID-19 pandemic for 2020.

Load growth can vary from year-to-year and is not uniform across the whole system. It is not unusual to find parts of the system growing at significantly higher rates than for the system as a whole, while other parts of the system can experience periods of low growth or demand reduction.

MEDC high voltage distribution system operates at 33kV and 11kV, both voltages being standard IEC voltages. The 33kV system is normally operated with duplicated radial while the 11kV system is operated as a radial configuration, normally with interconnection through normally open points except

MEDC Distribution System Capability Statement (2021-2023) – V2.0 27

in the more remote areas. The system covers both urban and rural areas and the characteristics depend on the load density.

Distribution Load Forecasting MEDC considers the following features are necessary to produce an accurate demand forecast in line with best practice:

• Accurate and unbiased actual demand data – careful management of data and forecasting model construction based on sound theoretical grounds that closely fits the sample data. • Transparency and repeatability – as evidenced by good documentation, including documentation of the use of judgment, which ensures consistency and minimises subjectivity in forecasts.

MEDC also considers the following elements to be relevant to maximum demand forecasting:

• Independent forecasts – spatial (bottom up) forecasts should be validated by independent system level (top down) forecasts and both spatial and system level forecasts should be prepared independently of each other. The impact of macroeconomic and demographic trends is better able to be identified and forecast in system level data, whereas spatial forecasts are needed to capture underlying characteristics of specific areas within the system. Generally, the spatial forecasts should be constrained (or reconciled) to system level forecasts; • Adjusting for temporary transfers – spatial data is adjusted for historical spot loads arising from peak load sharing and maintenance, before historical trends are determined; • Adjusting for discrete block loads – large new developments, such as shopping centres and housing developments, are incorporated into the forecasts, taking account of the probability that each development might not proceed. Only block loads exceeding a certain size threshold are included in the forecasts, to avoid potential double counting, as historical demands incorporate block loads and general demand growth.

At the time of writing this DSCS, the volume of grid connected PV systems is expected to make minor impact at system level forecast (including future years as it stands); hence the impact of PV systems is not included in the forecast for this DSCS. With the development of our new regression-based Load Forecasting tool, MEDC will monitor the uptake of all low carbon technologies including PV and include the impact of these on forecast in future appropriately.

System Demand Growth Historical data indicates that the demand rate of growth across MEDCs distribution system has slowed in recent years. This is mainly attributed to the sustained low price, general macro-economic factors and exceptional events like the COVID-19 impact. Over the 2013 to 2020 period the CAGR % system- wide load growth was as shown in Table 16.

Table 16 : CAGR% Evaluation on the System Maximum Day

2013-2020 CAGR system load System Maximum Demand growth % Non-Grid connected customers 4.0% Grid connected customers 4.2% After the declaration of maximum and minimum load in 2020, the minimum to maximum load ratio % was calculated for each PSS. The calculated ratio % of each PSS was then applied in the maximum forecasted load [2021-2023] to forecast the minimum load.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 28

Table 18 and Figure 11 shows the historical trend in system maximum demand with the forecast maximum demand over the period 2021 to 2023. Despite the general slowing in demand growth at the system level, there are areas within the system where maximum demand is forecast to grow well beyond the system average level, while other parts of the system are forecast to experience no load growth or a small reduction in maximum demand. This particularly applies to Muscat and Muttrah (except any potential bulk load connections) where the geography of the area (city area predominantly domestic property) can be considered saturated with little room for property expansion. Significant demand growth is expected in the South of Zone 1 and Zone 3, largely due to new developments associated with urban sprawl towards the edge of the urban growth zone. As a result of this urban sprawl, we expect to see continued strong growth in the Amerat and Mabelah areas. Similarly as seen in Table 18 and Figure 11 the forecast includes the impact of COVID-19 on the future growth period as well, as it is expected to take few years before the normalisation to pre COVID levels is reached.

• COVID-19 Pandemic Impact

The maximum demand growth was significantly reduced by -6.3% in 2020 and the exceptional drop is majorly attributed as impact of the exceptional COVID-19 pandemic situation. The reduction in the growth due to the COVID-19 has mainly resulted from shutdown of commercial activities, Government institutions and Ministries with less occupancy, citizens returning to the interior during the working from home arrangements and closing of Mutrah Souqs impacted the load in Muscat/Muttrah area. Similarly as expected there is an increase in the residential loads during these period due to people working from home and complete families not able to travel outside during summer vacations.

As an indication only the Table 17 below highlights the significant impact on the last summer peak load of some large customers from the following customer categories as an impact of COVID-19.

Table 17 : Covid-19 summer load 2020 impact

Average Summer Load Impact Customer Category compared to last year Commercial -20%

Governmental -15%

Tourism -40%

Residential 20%

Especially, in the last three years the maximum demand year on year growth at system level has reduced and dropped to 0.8% in 2018 and 4.7% in 2019 and -6.3% in 2020 as seen in Table 18; MEDC shall closely monitor the growth for the remaining years of the PCR-5 period and reflect the effects in the coming years as necessary for the reasons below:

1) The period when the reduction is observed is very small to be confident to change the growth % for the upcoming years; especially that MEDC expect the % growth to change compared to recently observed in the coming years as the price of oil continues to improve as evident from the 2018 to 2019 maximum demand growth; 2) Secondly we expect additional parameters like new technologies; photovoltaics and electric- vehicles to impact the pattern of the growth; 3) Thirdly as also observed from the table below in periods 2010-2012 and 2013-2015 have seen drastic swings in the system growth percentage due to a multitude of factors in a very short period

MEDC Distribution System Capability Statement (2021-2023) – V2.0 29

of time i.e. MEDC believe that a larger period is required to determine the future growth percentage rather than last 2-3 years only and exceptional event impacts to be excluded. 4) Lastly MEDC believes that it will take some time before the growth reduction due to COVID-19 impact is normalised to pre-levels; hence no further growth reduction is expected.

Table 18 : System Maximum Demand in MW [Historical and Forecast]

Actual Demand [MW] Forecast Demand [MW]

System Maximum 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Demand

Excluding Grid Connected 1246 1342 1525 1567 1618 1763 1738 2014 2154 2254 2305 2323 2427 2280 2370 2426 2467 Customers (MW)

Yearly 8.7% 7.7% 13.6% 2.8% 3.3% 9.0% 1.4% 15.9% 7.0% 4.6% 2.3% 0.8% 4.5% -6.1% 4.0% 2.4% 1.7% Growth

Including Grid Connected 1246 1342 1525 1567 1618 1763 1738 2014 2184 2304 2349 2367 2479 2323 2412 2487 2538 Customers (MW)

Yearly 8.7% 7.7% 13.6% 2.8% 3.3% 9.0% 1.4% 15.9% 8.4% 5.5% 1.9% 0.8% 4.7% -6.3% 3.9% 3.1% 2.0% Growth

Figure 11 : System Historical and Forecast Maximum Demand (2007-2023)

2700

2400

2100

1800 MW 1500

1200

900

600 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Year Excluding Grid Connected Customers (MW) Including Grid Connected Customers (MW)

MEDC Distribution System Capability Statement (2021-2023) – V2.0 30

4.7. Grid Supply Points By 2023, it is forecasted that there will be 38 grid supply points within the MEDC licenced area. There are 2 new grid supply points(each GSS with 4x125 MVA TX ;Group A &B) currently in the construction phase. The investment drivers for grid supply points is to relieve existing overloaded (above the firm) grid supply points and to provide new 33kV connection points to accommodate new primary substations. MEDC provides annually a demand forecast for five years to OETC. The existing system (2020) and expected system development for the primary substations is updated in Figure 12 and Figure 13 [expansion for the next 3 years].

MEDC Distribution System Capability Statement (2021-2023) – V2.0 31

Figure 12 : 33kV Existing System (2020)

Muscat Electricity Distribution Company - 33kV Primary Substations (2020 Network Diagram) Sea of Oman

Manomah (P067) (2x20MVA) Barka[G02] 125 Mabelah STP (P140) (2x10MVA)

Mabelah South Mabelah South PH-8 (P061) 1 (2x20MVA) (P157) 1 (3x20MVA)

Palace Mabella 2 Communication (P033) Sea of Oman (1 x6MVA) Mabelah Shabiya (A Salam) (P060) (3x20MVA) 250 (A & B)[G12] RGO Halban Camp (P034) Palm Mall (1x5MVA) (P168) 1 Old Mabelah (3x20MVA) (P059) (2x20MVA) Mobella South PH06 Mabelah-C (P185) (P064) (3x20 MVA) (3x20MVA)

Off Mabelah-A Seeb 05(Boulevard) 1 (P063) (P186) Wadi Al (3x20MVA) Al Khoud Shabiya (3x20MVA) 1 Aresh (P046) (P115) (2x20MVA) (2x20MVA) Wadi Bahayis RGO) (P098) Al Khoud PH-7 Diplomatic City Mabelah South Seeb Grid (2x20MVA) (P154) (GP08) Ghubrah North-1 (P022) (P061) (3x20MVA) Wadi Al Lawami (3x20MVA) Off 1 (2x20MVA) (P023) (2x20MVA) (P117) Ghubrah GPS (3x20MVA) Sultan School (3x20MVA) (P166) (2x16MVA) (P029) Ghubrah North-2 (2x20MVA) Al Hail South-2 (P153) (P149) Mabelah Grid 125 Sur Al Hadid City Centre (3x20MVA) (3x20MVA) (GP04) (P116) 250 off (P073) (2x20MVA) Al Khoud PH-6 New Al Khoud (2x20MVA) (2x20MVA) (P049) (P047) Mabelah South PH-7 (2x20MVA) Mabelah[GP04] (2x20MVA) Hail North-1 (P141) Seeb A & B PDO Sea of Oman (3x20MVA) (P027) (2x20MVA) (P144) Mawaleh-C Mawalleh [GP08] Mawalleh (3x20MVA) Muttrah Store (P072) off Botanic Garden Al Hail South-1 North Grid (P085) (P016) (2x20MVA) South A & B (P030) (GP01) (2x20MVA) 125 Darsait (2x20MVA) (2x20MVA) (3x20MVA) Ghubrah 2[G09] (P018) 4 [GP05] Al Hail North-2 Mawaleh (2x20MVA) ROP Dog Mawalleh-B Jibrooh (P028) 125 Azaibah North-2 Kennel (P183) (P071) (P041) (3x20MVA) (2x20MVA) North[GP01] (P012) (2x6MVA) (3x20MVA) (2x20MVA) Mawalleh-A Mawalleh North (P070) off (P069) 250 Rusail-B (2x20MVA) (3x20MVA) Azaibah South1-A (P101) Azaibah North-3 Mawalleh South 5 (P014) (2x10MVA) (P013) Airport Height-1 Falaj Sea Port (P148) Royal Flight (3x20MVA) (2x20MVA) Azaibah North-1 (P086) (3x20MVA) (P001) (P178) (P100) (2x20MVA) (P011) 125 (2x6MVA) Mawaleh Airport Height-2 (2x16MVA) (2x20MVA) 1 (2x20MVA) South Grid (P002) (2x20MVA) Azaibah South 1-B (GP05) (P147) Al Khoud PH-3 (2x20MVA) Airport Height-3 (3x20MVA) (P048) (P003) (2x20MVA) 250 (2x20MVA) MOD Technical College Khuwair South Ruwi Office (P081) Airport Height-4 (P052) (P108) (3x20MVA) (2x20MVA) (2x20MVA) (P004) Bousher Grid SQU-1 SQU-3 (2x20MVA) (GP02) (P122) (P160) Private Factory Airport (2x20MVA) Bait Al Falaj (3x16MVA) (3x20 MVA) Al Khuwair 17/1 (P106) SQU-2 Airport Height-5 Ghala-1 (P050) (P142) CBD (3x20MVA) (2x20MVA) (P123) (P151) Height-A&B (P015) Tilal Al Khuwair (2x20MVA) (2x16MVA) (3x20MVA) (P173) 1 Rusail Industrial-1 (2x20MVA) (P055) 250 (3x20MVA) (3x16MVA) (P103) Rusail Industrial-2 [G01] Oman Exhibition ROP Al Khoud (2x16MVA) Bousher-A&B (P161) (P104) (P165) (2x20MVA) (2x20MVA) ROP (3x20MVA) Rusail Industrial-3 Hospital(P172) Al Ansab STP [GP02] Riyam (P104) (3x20 MVA) (P009) Muttrah (P099) (2x20MVA) (2x20MVA) (2x20MVA) Rusail08 250 125 (KOM) [G21] (P164) Rusail Industry (A&B) Ghala-A&B (3x20MVA) [G13] 250 Rusail Housing [G11] Al Ansab-2 (P056) (P008) (2x20MVA) Qurum-1 (2x20MVA) MOD Al Ansab (P093) (P167) Old Airport Qurum-2 (2x16MVA) Information City 1 Waljah Rusail Industrial-4 (2x10 MVA) (P094) (P037) (P107) (2x20MVA) (P130) (2x20MVA) (2x20MVA) Al Jifnain-2 (P158) (2x20MVA) (P196) (3x20 MVA) Lulai (1x6MVA) Qasr Al Alam Al Jifnain Ghala 02 (P095) (P090) (P042) Orpic (P156) (2x20MVA) M.B.D South (2x20MVA) (1x6MVA) (P192) (3x20 MVA) Wadi Al Misfah Holiday Inn (P075) 2x6 MVA (P051) Rabiat Al Qurum (2x20MVA) (3x20MVA) Kabir Sidab (P096) [G04] (P119) 125 1 (2x20MVA) 250 ROP -Shati Al A&B[G19] (2x6MVA) Cement Cement Factory MSQ-1 Qurum Sarooj-Shati Al Al Khuwair Northoff 125 Housing (P079) (P083) (P111) Qurum 3 (P054) MSQ 2 Ruwi Valley (P088) (2x31.5 MVA) (3x20 MVA) (3x20MVA) (2x20MVA) (P110) (P155) Majlis Oman (2x5MVA) off (2x20MVA) (2x20MVA) (P174) (P066) 1 Intercontinental (3x20 MVA) (2x20MVA) Al Khuwair 25 Qurum[G06] 250 (2x20MVA) (P053) (P109) Wadi Al Kabir Height Mall of (2x20MVA) (2x20MVA) Barr Al Jissa off Oman(P171) (P128) Ruwi Market (P044) Al Misfah (3x20MVA) Al Khuwair School (2x20MVA) (P076) (2x20MVA) (P080) (P146) (2x20MVA) (3x20MVA) (3x20MVA) Al Muna Wadi Al Kabir Workshop (P084) Royal Office Wattaya (P126) Saraya Bander (2x20MVA) 250 (P097) Khoula Hospital (P131) (2x6MVA) (P145) (2x20MVA) (2x20MVA) (3x20MVA) (P132) Ali Al Shihani Wadi Al Kabir Housing MSQ -A & B (3x20MVA) Digital TV Studio(P039) (P125) (P127) Al Awabi (2x20MVA) (1x6MVA) (2x20MVA) Al Bustan Palace Qantab (P139) [GP06] 1 Information City-2 (P017) (P089) (3x20MVA) MSQ Grid (P038) (2x16MVA) (1x3MVA) (1x5MVA) (GP06) 1 (2x20MVA) 1 Al Hamryah (P035) (2x20MVA) Legend 125 Wadi Adai 1 (P175) Hussan Yiti 125 (2x20MVA) 132/33kV Grid Station with Firm Capacity(MVA) Wadi Adai (P169) (2x6MVA) Amerat-1 Jabal Al Sifah Amerat Heights (P005) [G22] 125 (P159) 125 New 132/33kV Grid Station with Firm Capacity(MVA) (P152) (2x16MVA) 1 (3x20MVA) (3x20MVA) 1

125 Upgrading 132/33kV Grid Station with Firm Capacity(MVA) Yiti[G08] Post Office 1 1 (P150) (3x20MVA) 100 132/11kV Grid Station with Firm Capacity(MVA) 1 Al Nahdah 33/11kV Primary Station Amerat 250 (P006) Seih Dhabi (3x20MVA) (P118) Shifted 33/11kV Primary Station [G10] (2x16MVA) Quriyat (P091) (2x20MVA) Amerat 3 1 Upgrading 33/11kV Primary Station (P179) off Al Atkiya (3x20MVA) 1 (P182) Dhaghmar[GP11] New 33/11kV Primary Station Madinat Al Nahdah (1x6 MVA) (P065) Al Shahbari (2x20MVA) (132/11kV) (P092) 100 Private 33/11kV Primary Station (2x20MVA)

Private Shifted 33/11kV Primary Station Water Pumping Tunis Heium (P193) (P137) (2x6MVA) Dhaghmar 1 Private Upgrading 33/11kV Primary Station Al Jufaina (1x6MVA) (P194) (P021) 1 x6 MVA (4x6MVA) New Private 33/11kV Primary Station

off ABS ( existing Off Point) Jahloot 125 125 33kV RMU/ C.B ( proposed Off Point) ROP Al Saleel [P162] [G03] (2x6MVA) Direct Connected Transformer Royal Camp Debah (P170) Al Masarat (P114) Hail Ghaf (P036) (1x3MVA) 132 kV Line (P068) Sawaqim-2 (1x6MVA) (2x10MVA) Sawaqim-1 (P113) (2x6MVA) 1 (P112) Note: 1 (2x6MVA) (1x6MVA) New 132 kV Line All connection lines are either two circuits or three circuits Al Mazara Dhabab Prepared by Planning Department Arqi for 3 x20MVA except the single lines are indicated as one (P074) Wadi Al Arbyeen (P019) (P121) (2x6MVA) 33 kV Line This diagram only for planning purpose (2x6MVA) (1x6MVA) circuit or more. (1x3MVA) 1 New 33kV Lines

MEDC Distribution System Capability Statement (2021-2023) – V2.0 32

Figure 13 : 33kV Expected System Development (2021 to 2023)

Muscat Electricity Distribution Company - 33kV Primary Substations (2021-2023 Network Diagram) Sea of Oman

Manomah (P067) (2x20MVA) Barka[G02] 125 Mabelah STP (P140) (2x10MVA) Mabelah South PH-9 (P184) (3x20MVA) Mabelah South Mabelah South PH-8 (P061) (3x20MVA) (P157) Off Off (3x20MVA)

Palace Mabella 2 Communication (P033) Sea of Oman (1 x6MVA) Mabelah Industrial Mabelah Shabiya (A Salam) (P060) (3x20MVA) 250 (A & B)[G12] RGO Halban Camp 250 (P034) Palm Mall (1x5MVA) (P168) (3x20MVA) Off Old Mabelah (P059) (3x20MVA) Mobella South PH06 Mabelah-C Al Khoud Shabiya – B (P185) (P064) (3x20 MVA) (P187) (3x20MVA) (2x20 MVA)

Mabelah-A Seeb 05(Boulevard) (P063) (P186) Wadi Al (3x20MVA) Al Khoud Shabiya (3x20MVA) Aresh (P046) (P115) Al Khoud PH-7 (3x20MVA) (2x20MVA) Wadi Bahayis (P154) Mabelah South (3x20MVA) RGO) (P061) (P098) off Seeb Grid Diplomatic City (3x20MVA) (2x20MVA) (GP08) Ghubrah North-1 (P022) Wadi Al Lawami (3x20MVA) Off (2x20MVA) (P023) (P117) Ghubrah GPS (3x20MVA) Sultan School (3x20MVA) (P166) (2x16MVA) (P029) Ghubrah North-2 Al Khoud PH-6 (2x20MVA) Al Hail South-2 (P153) (P149) Mabelah Grid 125 Sur Al Hadid (P049) City Centre (2x20MVA) (3x20MVA) (3x20MVA) (GP04) (P116) 250 off (P073) (3x20MVA) New Al Khoud (2x20MVA) (2x20MVA) off (P047) Mabelah South PH-7 Mabelah[GP04] (2x20MVA) Hail North-1 (P141) Seeb A & B PDO Sea of Oman (3x20MVA) (P027) (3x20MVA) (P144) Mawaleh-C Mawalleh [GP08] Mawalleh (3x20MVA) Muttrah Store (P072) off Botanic Garden Al Hail South-1 North Grid (P085) (P016) (2x20MVA) South A & B (P030) (GP01) (2x20MVA) 125 Darsait (2x20MVA) (2x20MVA) (3x20MVA) Mawalleh-B Ghubrah 2[G09] (P018) 4 [GP05] Al Hail North-2 Mawaleh (2x20MVA) ROP Dog (P071) 125 Jibrooh Kennel (P183) (3x20MVA) Off (P028) Azaibah North-2 (2x20MVA) North[GP01] (P012) (P041) (2x6MVA) (3x20MVA) (2x20MVA) Mawalleh-A Off Mawalleh North (P070) off (P069) (3x20MVA) 250 Rusail-B (3x20MVA) ROP Airport Azaibah South1-A (P101) Mawalleh South 5 Height (P195) (P014) (2x10MVA) Airport Height-1 Falaj Sea Port (P148) (3x20MVA) (2x20MVA) (3x20MVA) Royal Flight Azaibah North-3 (P001) Azaibah North-1 (P178) (P086) (P100) (2x20MVA) (P011) 125 (2x6MVA) Mawaleh (P013) Airport Height-2 (2x16MVA) (2x20MVA) 1 (2x20MVA) (3x20MVA) (P002) South Grid Azaibah South 1-B Khoudh (2x20MVA) (GP05) (P147) Al Khoud PH-3 (2x20MVA) Airport Height-3 250 (3x20MVA) (P048) (P003) Al Bander (2021) (2x20MVA) (2x20MVA) (P197) MOD Technical College 250 Khuwair South Ruwi Office (3x20 MVA) (P081) Airport Height-4 (P052) (P108) (3x20MVA) (2x20MVA) (2x20MVA) (P004) Bousher Grid SQU-1 SQU-3 (2x20MVA) (GP02) (P122) (P160) Private Factory Airport (2x20MVA) Bait Al Falaj (3x16MVA) (3x20 MVA) Al Khuwair 17/1 (P106) SQU-2 Airport Height-5 Ghala-1 (P050) (P142) (P015) CBD (3x20MVA) (2x20MVA) (P123) (P151) Height-A&B Tilal Al Khuwair (2x20MVA) (2x16MVA) (3x20MVA) (P173) Rusail Industrial-1 (2x20MVA) (P055) 250 (3x16MVA) (P103) Rusail Industrial-2 [G01] Oman Exhibition (3x20MVA) ROP Al Khoud (2x16MVA) Bousher-A&B (P161) (P104) (P165) (2x20MVA) 1 (2x20MVA) ROP (3x20MVA) Rusail Industrial-3 Hospital(P172) Al Ansab STP [GP02] Riyam (P104) (3x20 MVA) (P009) Muttrah (P099) (2x20MVA) (2x20MVA) (2x20MVA) Rusail08 250 125 (KOM) [G21] (P164) Rusail Industry (A&B) Ghala-A&B (3x20MVA) [G13] 250 Rusail Housing [G11] Al Ansab-2 (P056) (P008) (2x20MVA) Qurum-1 (2x20MVA) MOD Al Ansab (P093) (P167) Old Airport Qurum-2 (2x16MVA) Information City 1 Waljah Rusail Industrial-4 (2x10 MVA) (P094) (P037) (P107) (2x20MVA) (P130) (2x20MVA) (2x20MVA) Al Jifnain-2 (P158) (2x20MVA) (P196) (3x20 MVA) Lulai (1x6MVA) Qasr Al Alam Al Jifnain Ghala 02 (P095) (P090) (P042) Orpic (P156) (2x20MVA) M.B.D South (2x20MVA) (1x6MVA) (P192) (3x20 MVA) Wadi Al Misfah Holiday Inn (P075) 2x6 MVA (P051) Rabiat Al Qurum (2x20MVA) (3x20MVA) Kabir Sidab (P096) [G04] (P119) 125 1 (2x20MVA) 250 ROP -Shati Al A&B[G19] (2x6MVA) Cement Cement Factory MSQ-1 Qurum Sarooj-Shati Al Al Khuwair Northoff 125 Housing (P079) (P083) (P111) Qurum 3 (P054) MSQ 2 Ruwi Valley (P088) (2x31.5 MVA) (3x20 MVA) (3x20MVA) (2x20MVA) (P110) (P155) Majlis Oman (2x5MVA) off (2x20MVA) (3x20MVA) (P174) (P066) 1 Intercontinental (3x20 MVA) (2x20MVA) Al Khuwair 25 Qurum[G06] 250 (2x20MVA) (P053) (P109) Wadi Al Kabir Height Mall of (2x20MVA) (2x20MVA) Barr Al Jissa off Oman(P171) (P128) Ruwi Market (P044) Al Misfah (3x20MVA) Al Khuwair School (2x20MVA) (P076) (2x20MVA) (P080) (P146) (2x20MVA) (3x20MVA) (3x20MVA) Al Muna Wadi Al Kabir Workshop (P084) Royal Office Wattaya (P126) Saraya Bander (2x20MVA) 250 (P097) Khoula Hospital (P131) (2x6MVA) (P145) (2x20MVA) (2x20MVA) (3x20MVA) (P132) Ali Al Shihani Wadi Al Kabir Housing MSQ -A & B (3x20MVA) Digital TV Studio(P039) (P125) (P127) Al Awabi (2x20MVA) (1x6MVA) (2x20MVA) Al Bustan Palace Qantab (P139) [GP06] 1 Information City-2 (P017) (P089) (3x20MVA) MSQ Grid (P038) (2x16MVA) (1x3MVA) (1x5MVA) (GP06) 1 (2x20MVA) 1 Al Hamryah (P035) (2x20MVA) Legend 125 Wadi Adai 1 (P175) Hussan Yiti 125 (2x20MVA) 132/33kV Grid Station with Firm Capacity(MVA) Wadi Adai (P169) (2x6MVA) Amerat-1 Jabal Al Sifah Amerat Heights Amerat 4 (P005) [G22] 125 (P159) 125 New 132/33kV Grid Station with Firm Capacity(MVA) (P152) (P180) (2x16MVA) 1 (3x20MVA) (3x20MVA) 1 (3x20MVA)

125 Upgrading 132/33kV Grid Station with Firm Capacity(MVA) Yiti[G08] Post Office 1 1 (P150) (3x20MVA) 100 132/11kV Grid Station with Firm Capacity(MVA) 1 Al Nahdah 33/11kV Primary Station Amerat 250 (P006) Seih Dhabi (3x20MVA) (P118) Shifted 33/11kV Primary Station [G10] (2x20MVA) Quriyat (P091) Amerat 3 (2x20MVA) Upgrading 33/11kV Primary Station (P179) off Al Atkiya (3x20MVA) 1 (P182) Dhaghmar[GP11] New 33/11kV Primary Station Madinat Al Nahdah (1x6 MVA) (P065) Al Shahbari (2x20MVA) (132/11kV) (P092) 100 Private 33/11kV Primary Station (2x20MVA)

Private Shifted 33/11kV Primary Station Water Pumping Tunis Heium (P193) (P137) (2x6MVA) Dhaghmar 1 Private Upgrading 33/11kV Primary Station Al Jufaina (1x6MVA) (P194) (P021) 1 x6 MVA (4x6MVA) New Private 33/11kV Primary Station

off ABS ( existing Off Point) Jahloot 125 125 33kV RMU/ C.B ( proposed Off Point) ROP Al Saleel [P162] [G03] (2x6MVA) Direct Connected Transformer Royal Camp Debah (P170) Al Masarat (P114) Hail Ghaf (P036) (1x3MVA) 132 kV Line (P068) Sawaqim-2 (1x6MVA) (2x10MVA) Sawaqim-1 (P113) (2x6MVA) 1 (P112) Note: 1 (2x6MVA) (1x6MVA) New 132 kV Line All connection lines are either two circuits or three circuits Al Mazara Dhabab Prepared by Planning Department Arqi for 3 x20MVA except the single lines are indicated as one (P074) Wadi Al Arbyeen (P019) (P121) (2x6MVA) 33 kV Line This diagram only for planning purpose (2x6MVA) (1x6MVA) circuit or more. (1x3MVA) 1

New 33kV Lines

MEDC Distribution System Capability Statement (2021-2023) – V2.0 33

4.8. Distribution System Modelling and Analysis MEDC maintains up-to-date models of its power system for assessing distribution system performance via power system studies, bulk loads modelling and undertaking customer connection studies where required; to ensure the distribution system operates in a safe and an efficient manner along with providing the required security of supply to its connected customers.

Power System Models The planning tool utilised for system modelling and studies is PSS®SINCAL (Power System Simulator® Siemens Network Calculation). The models for each grid substation with their respective connected primary substations are established by representing the 33kV system on an electrical connectivity basis. The system models contain network topology and details in terms of nameplate data for transformers and their tap changers, capacitor banks and their controllers, conductor types along with associated lengths and parameters and the non-coincident demand data on individual primary substations.

The load demands are modelled as lumped loads connected to the main 11kV bus bars and segregated into motoric and non-motoric load types for load flow and fault current calculations. The recorded maximum (summer) and minimum (winter) demands on each primary substation; derived from MEDC SCADA system as of 2020 have been used to update the power system models. Forecasting principles for load determination as mentioned in the previous sections have been adopted to forecast the future year (2021-2023) maximum and minimum demands.

Under minimum demand conditions; the reactive power support from primary substation and grid substation capacitor banks is switched off to avoid overvoltages.

Load Flow Analysis Load flow analysis is undertaken for maximum and minimum demand scenarios to define the performance of MEDC distribution system during these two-extreme loading scenarios. The analysis determines the active and reactive power flows in the system, percentage loadings for transformers and 33kV circuits along with the voltage profile at the 11kV and 33kV busbars of the primary substations under normal circuit operation. Simulations are carried out for the existing (2020) and future 3 years (2021-2023) for system maximum and minimum loadings.

From the studies of these extreme conditions it is possible to identify where the system is strong and has spare capacity and conversely, where additional mitigation and/or reinforcement, before new connections, potentially needs be considered. The maximum demand case for instance; identifies where there is a risk of overloading, of operation above firm capacity, or of system voltages falling below the voltage limits whereas the minimum demand case will recognize voltage excursions above statutory limits as defined in the Distribution Code.

The power factor values for maximum and minimum demand scenarios have been determined based on the actual available information from MEDC SCADA. For maximum demand conditions; the actual recorded power factor data is employed, where available, for 122 primary substations. For the remaining 55 substations; where power factor values are not available via SCADA, a calculated system average of 0.93 and 0.90 is considered for maximum and minimum demand scenario’s respectively in accordance to the company’s defined practice.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 34

The load flow study results are summarised in tabular form in Appendix D and available in a downloadable excel file that supplements this Distribution System Capability Statement.

The simulation result demonstrates the following:

• Voltage drop under maximum demand scenario remains within the statutory limits of - 6% on all 33kV busbars/nodes. • Voltage drop under maximum demand scenario remains within the statutory limits of - 6% on all 11kV busbars/nodes. • Voltage rise under minimum demand scenario remains within the statutory limits of + 6% on all 33kV busbars/nodes. • Voltage rise under minimum demand scenario remains within the statutory limits of + 6% on all 11kV busbars/nodes; in case of very minor excursions in 2020, the problem solves in forthcoming years. • 33kV circuit loadings assessed for the worst-case maximum demand scenario; across the system are within the acceptable circuit ratings.

From the results it can be observed that especially under minimum demand case, the 11kV buses at the primary substations are approaching the statutory limit of +/-6% in some of the primary substations and slightly exceeding +6% in one PSS (Madinat Al Nahdah – P065 - Bus B) for all the three future years cases. This is explained by the fact that our primary transformers are rated at 11.5kV secondary voltage and to represent the worst case scenario; the load flow calculations are performed with tapchangers switched off, which on the ground will otherwise regulate the voltage performance better and remain within statutory voltage limits.

Short Circuit Analysis MEDC carries out short circuit calculation studies to establish the capability of equipment to withstand three phase maximum prospective fault current levels.

The principal source of fault currents is the generation assets connected to the transmission system with the fault current contribution onto the MEDC distribution system via the 132/33kV GSS transformers. The fault current infeed from the OETC source have been updated in our power system models according to the data provided by the OETC’s 2020 Capability Statement which covers up the transmission system developments up to 2024.

The system configurations modelled for short circuit studies in each year, to represent the maximum prospective fault current levels, while also reflecting the realistic operational arrangement are based on the following principles:

• All existing and new 2x20 MVA PSSs are simulated for operation with the 11kV bus-section circuit breaker in the “normally closed” position20.

20 Except for few locations where the 33kV feeders for the individual transformers are connected from two different GSSs in which case, the 11kV bus-section circuit breaker is kept “normally open” for the respective year(s).

MEDC Distribution System Capability Statement (2021-2023) – V2.0 35

• All existing and new 3x20 MVA PSSs are simulated for operation with one 11kV bus-section circuit breaker as “normally closed” and one as “normally opened” (i.e. in N or N-1 scenario, it represents a 4 out of 5 ‘normally closed’ circuit breakers scenario) with an auto-changeover scheme 21. • All existing 2x20 MVA PSSs and 3x20 MVA PSSs are simulated for operation of 33kV bus-section circuit breakers within the PSSs (where ever present)22 as “normally open”.

The design short circuit breaking ratings of the 11kV switchgear components at new and upgraded primary substations have been revised to 25 kA to comply with system requirements23.

Currently, in the absence of accurate fault level contribution data from low voltage (LV) side, a worst- case allowance is made for LV motor fault contribution majorly due to the nature of the air conditioning load prevalent across the MEDC’s distribution system. A motoric to static load type ratio of 80/20 (in percentage) is considered using the system maximum demand values. System modelling for fault current calculations have been performed in accordance with the principles of the “IEC 60909-Short Circuit in 3 phase AC systems” standard.

The maximum prospective fault current values are tabulated in the tables in Appendix D. The calculation of maximum prospective fault current is compared against the rated breaking capability of the primary equipment.

The maximum prospective (initial symmetrical) fault current is calculated to be still under but approaching (i.e. >95% and <100% ) the rated breaking capacity of the primary 33kV equipment (switchgear) at the following primary substations:

• Wadi Adai Grid Primary – P175 (23.86 kA in 2022 and 2023) • Bousher Grid Primary - GP02 (24.38 kA in 2020 and then within 96% of 25kA rating) • Mabelah Grid Primary - GP04 (24.85 kA in 2021 and then within 95% of 25kA rating) • Seeb Grid Primary – GP08 (23.75 kA in 2022 and then within 95% of 25kA rating) • Mabelah South 9-A – P184 (23.94 kA in 2023)

However, at the following primary substation(s), minor excursions beyond the rated breaking capacity of the 33kV equipment (switchgear) are observed :

• MSQ Grid Primary – GP06 (25.54 kA in 2022 and 2023) where it marginally exceeds by +2.16% above the switchgear rating; hence MEDC shall monitor this PSS closely and create mitigation plans in form of operational restrictions if required based on the monitoring results.

It is to be noted that all the above primary substations are in close electrical vicinity of the grids substations where these results are based on non-coincident maximum demand fault contributions to represent worst case scenario’s of the connected PSSs.

21 If the fault levels are within limits for this worst case scenario’s then on bus-coupler open scenario’s of existing primaries the fault level’s will be even lower. 22 For new PSS, the 33kV configuration excludes the 33kV bus-section circuit breakers at the PSS. 23 For the older existing 11kV indoor type switchgear where applicable, the rated breaking short circuit current value is 18.4kA.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 36

The maximum prospective (initial symmetrical) fault current levels at 11kV busbars of all the primary substations are within their rated breaking capacities.

Technical Losses Assessment The technical losses in the MEDC distribution system are a factor of the configuration of the system, type and specification of equipment, percentage utilisation of assets and customer energy consumption. Technical losses are attributed to load and no-load losses in the 33kV feeders and 33/11.5kV primary transformers, 11kV feeders and distribution transformers and the LV distribution system. In line with standard international practice for utilities where the distribution system is not fully modelled, we calculate the losses for specific network elements (transformers, overhead lines and cables) across the different voltage levels (33kV, 11kV and LV) and then summate the total losses to obtain a percentage technical loss for each primary substation.

The percentage technical losses are then apportioned according to the proportion of total system energy supplied by each substation. A summation of all apportioned technical losses is then presented as the system percentage technical losses. The summated technical losses based on the 2020 distribution system operation is estimated to be 3.98%. The breakdown of technical losses by voltage level is shown in Table 19 below.

Table 19 : Technical Losses

System Component Loss Value 33kV Circuits 0.16% 33/11.5kV Primary Transformers 0.46% 11kV Circuits 0.59% 11/LV Distribution Transformers 1.77% LV network 1.00% Total 3.98% 4.9. Continuous Improvement Areas MEDC have progressed on previously identified areas of continuous improvement as listed below and is continuing its working on the same along with identifying new areas where required.

1) Bulk Load Details and Modelling

We are continuously collating the details of existing 33kV and 11kV bulk customers to incorporate in MEDC power system models as appropriate. Creation of processes and automation including a creation of a Bulk Load Database to record accurately point of connections, customer power system impact including short circuit contribution to MEDC distribution system and agreed capacities to consistently capture these for existing and new customers have been created to effectively progress in this area. This has led to continuously adding further bulk loads at 11kV with their more accurate fault current contributions added to our base master models.

2) 11kV System Modelling

In 2020 MEDC completed the creation of a robust methodology for achieving MEDC requirements for developing power system models for 11kV system up to the main LV bus bar along with Siemens. Siemens along with MEDC implemented the methodology on one typical GSS model and post that in 2020 MEDC staff have already completed the full detailed 11kV modelling on 11 GSSs (A & B groups counted as one) in house, aiming to finish the remaining GSSs before end of Q1 2021. The exports from GIS are based on up-to-date 11kV network information into PSS®SINCAL readable format. This

MEDC Distribution System Capability Statement (2021-2023) – V2.0 37

will not only enable us to improve our existing power system studies and technical losses calculations using PSS®SINCAL but also supportive in point of connection studies for load connections and grid impact studies for renewable energy connections as well. Point 3 below shows the initial progress for the 11kV system modelling as well to reflect the real scenarios on ground.

3) Improved and Updated Motoric Short Circuit Contribution

We aim to assess the motor fault contribution onto MEDC’s system at LV due to the connection of typical larger scale centralised commercial air-con units by obtaining typical details of such systems from our larger commercial customers and preparing sample equivalent connection impact studies.

We are undertaking assessment studies for MV motor fault contribution from larger industrial customers in relevant parts of the system to improve the fault current calculations. This is an ongoing actvitiy and to that effect since 2018, we have further enhanced our network models at 4 PSS already (namely Jibrooh-P041, Mawalleh North Grid-GP01, Al Khoudh Ph 06 – P049 and Mall of Oman - P171) and 2 dedicated customers (Ad-Dakhiliyah Water Pumping Station and Mall of Oman development representing a fault infeed of 2.84kA and 2.44kA at 11kV respectively) to appropriately reflect the expected fault current contribution onto our distribution systems.

MEDC recently in 2019 completed an innovative prospective fault level monitoring project; based on the actual measured network conditions which has given us initial answers around fault level contributions from upstream transmission grid as well as downstream motor loads onto LV and MV networks. We aim to do further monitoring trails to firm up the initial answers going forward and improve the mortoric short circuit contributions from different types of loads on the distribution system.

4) Technical Losses Calculation using Power System Models

As detailed in point 2, once all the 11kV network models are established which are already under progress in 2020, we plan to merge our 33kV and 11kV models and furnish them with annual load profiles to produce technical losses from the models using 8760 hourly annual measured loadings from the SCADA load profiles.

5) Voltage Control and Regulation Methodology

As an additional improvement item, MEDC is in process of developing an improved voltage regulation methodology at our primary substation 11kV busbars by assessing the SCADA data on present/typical transformer tap positions and capacitor banks during summer and winter times. We have made great progress on the 33 and 11kV existing capacitor bank availability and operation. This is ongoing to enable us to assess optimal target voltage requirements and the 33 and 11kV capacitor bank availability and operational philosophy improvement last year is helping in improvement of technical losses and better voltage profile on the extremities of the system. This will also create potential for further economic development of the system especially in the rural areas with additional extension possibilities provided by these solutions.

4.10. Information on Distribution Network Assets Appendix E presents the detailed data for distribution system 33kV circuits and 33/11.5kV power transformers used in power system models for the first year (2020) of the statement as shown in the sample templates:

MEDC Distribution System Capability Statement (2021-2023) – V2.0 38

Falaj[G23] GSS [Zone 1] Primary Substation 33kV Circuit Data

Network Resistance Reactance Capacitance Continuous Length Node 1 Node 1 Element Name Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps]

Example Data Al Falaj Grid HBB01 Mutrah Store-33A-P085 Mutrah Store-F1-P085 33 33kV UGC 300 3C Cu 1.8 0.062 0.103 260 0.385 Al Falaj Grid HBB02 Mutrah Store-33B-P085 Mutrah Store-F2-P085 33 33kV UGC 300 3C Cu 1.8 0.062 0.103 260 0.385 Al Falaj Grid HBB01 - 33 33kV UGC 300 3C Cu 3.1 0.062 0.103 260 0.385 - - Seaport-F1-P086 33 33kV OHL 200 Panther ACSR 2.4 0.137 0.333 10.9 0.385 - Seaport-33A-P086 33 33kV OHL 200 Panther ACSR 0.9 0.137 0.333 10.9 0.385

Falaj[G23] GSS [Zone 1] Primary Substation Transformer Data

Rated Additional Secondary Impedance Primary Substation Primary Side Apparent Minimum Tap Nominal Tap Maximum Tap Voltage per Side Voltage Vector Group Transformer ID [kV] Power (ONAF) Position Position Position Tap [kV] [%] [MVA] [%]

Example Data Jibrooh-Tx1-P041 33 11.5 20 12.4 Dyn11 3 12 15 1.67 Jibrooh-Tx2-P041 33 11.5 20 12.4 Dyn11 3 12 15 1.67 Jibrooh-Tx3-P041 33 11.5 20 12.3 Dyn11 3 12 15 1.67

MEDC Distribution System Capability Statement (2021-2023) – V2.0 39

5. CHALLENGES AND OPPORTUNITIES WITHIN THE SYSTEM

MEDC recognise that the nature of electricity generation and use is changing. We envisage that recent policy initiatives will result in an increase in photovoltaic (PV) generation on our distribution system. Unlike other utilities in different regions, Oman has not seen significant uptake in electric vehicle charging thus, the associated demand characteristics for electric vehicles (EV) are not considered to be a contributing factor to our system planning in the short term planning horizon. However; this will be closely monitored to check the penetration rate of EV and PV in general.

With the introduction of Sahim-I initiative by the APSR since May 2017 there has been an increasing uptake of small grid connected PV systems for households and business as evident from the PV connections list in Appendix C. Similarly with the recent 2019 launch of Sahim-II aimed at encouraging the small grid connected PV systems (circa 3-5kWp) for residential rooftops; MEDC expect even greater rate of uptake (APSR forecasting circa 10-30% residential premises24). With this great rooftop PV intiatives, MEDC does foresee challenges and opportunities in the way we will plan and operate our system. Whilst PV may have the impact of reducing transmission and distribution congestion; we do envisage that challenges in terms of power quality, reverse power flow and operating within voltage limits will need to be addressed if PV uptake is significant.

MEDC are responsible for ensuring power quality according to the regulations under which we operate. However; with the addition of intermittent, consumer-owned and non-dispatchable PV units, current standard procedures for guaranteeing power quality might not be as effective as they are without PV.

Overvoltage is one of the main reasons for limiting the capacity (active power) of non-dispatchable PV; that can be connected to a low voltage Distribution System. During high PV generation and low load periods; there is a possibility of reverse power flow and consequently voltage rise in the HV & LV feeder. We envisage that this will be most prominent during the winter period. For this reason; MEDC believe that if uptake is significant it will impact investment decision making for reinforcement and asset replacement. Consideration of tap range, optimum dispatch of capacitor banks and conductor sizing may be necessary should PV penetration become high.

5.1. New Connection Applications MEDC are responsible for the connection of customers for all levels of demand that our system supplies. We are also the initial point of connection request for customers seeking a 33kV or 132kV connection at an OETC grid supply point.In 2020, we have received 19 bulk connection requests with a combined total demand of 134.1MW. 11kV and lower voltages connection applications are identified in Table 20.

Table 20 : Number of Connection Applications for Bulk Load Application, 11kV and LV Application

S.No. Category Bulk Load Application 11kV and LV Application 1 Residential 1 3569 2 Commercial 9 483 3 Industrial 0 60 4 Government 5 97 5 Tourism 4 11 6 Agriculture 0 51 Total 19 4271

24 Forecast numbers estimated by APSR: https://www.aer.om/en/product-application-for-sahim2

MEDC Distribution System Capability Statement (2021-2023) – V2.0 40

Figure 14 : No. of Connection Applications (Bulk Load Application, 11kV and LV) Received in 2020

Photovoltaic (PV) connections With the global trend of renewable energy technologies and the reduction of using fossil fuels, MEDC continued to receive applications for connecting solar PV systems of various sizes. In 2020, MEDC received 38 new applications with total requested generation capacity of 1.083 MW. In 2020; 10 no. applications energized were connected equating to 817.4 kW, 12 no. applications are under construction (including applications from 2019 which are still under construction) equating to 1.368 MW. Table 21 below shows these customer classifications for the applications and connections along with the total connected generation to MEDC network equating to 4.08MW (as of October 2020 since the start of PV installations).

Appendix C has the complete details of the 2020 applications.

Table 21 : PV Application and Connection Classification

No. of Applications Connected Generation (kW) S.No. Category YTD 2020 As of Oct 2020 YTD 2020 As of Oct 2020

1 Commercial 5 27 749.4 1937.6

2 Government 0 11 0 1987.3

3 Residential 33 42 68 155.5

Total 38 80 817.4 4080.4

MEDC Distribution System Capability Statement (2021-2023) – V2.0 41

5.2. System Constraints and Opportunities Load related system constraints fall into one of two categories:

• Current constraints that can be considered DSSS obligations. • Load related constraints based on current load growth forecasts. MEDC will seek to address such constraints as part of its investment plan. Demand Not Secured (DNS) non-compliances are identified and documented within Appendix B.

Table 22 provides a list of projected capacity constraints at the end of the planning horizon in 2023. If the value is identified as negative, MEDC envisage there will be a deficit in spare capacity at that specific substation, thus it is less advantageous for a customer to consider a new connection in that area. Likewise, if there is spare capacity (positive), then this substation may be considered more advantageous as a point for new customer connection.

Table 22 : 2023 Projected Capacity Constraints in MVA

Area Name Forecast Load (MVA) Firm Capacity (MVA) Spare Capacity Available [MVA]

Airport 61 100 39 Amerat 229 262 33 Ansab 79 80 1 Azaibah 234 300 66 Bousher 77 80 3 GhubrahSouth 51 80 29 Hail 141 180 39 Khoud 123 160 37 Khuwair 174 240 66 Mabelah 364 440 76 QuriyatGroup 41 40 -1 Mawaleh 137 180 43 Misfah 71 80 9 MSQ 57 80 23 Muscat 31 40 9 Mutrah 83 128 45 Qurum 59 76 17 Rusail 142 176 34 Ruwi 85 120 35 Sarooj 88 140 52 Seeb 129 180 51 WadiAdai 63 100 37 WadiKabir 75 112 37

MEDC Distribution System Capability Statement (2021-2023) – V2.0 42

6. THE INVESTMENT PLAN

6.1. System Development Projects during the period 2021– 2023 Table 23 provides an overview of the status of primary substation projects by zone in the period 2021 to 2023.

Table 24 summarise the list of sponsored projects that are planned to be connected in the period 2021 to 2023.

Table 25, Table 26 and Table 27 summarise the projects planned for completion in the years 2021,2022 and 2023 respectively.

A summary description of each of the planned projects is provided by operating zone in Sections 6.1.1 to 6.1.3.

Table 23 : Status of the Primary Substations at a Glance [2021-2023]

Project Stage Zone1 Zone2 Zone3 Under Construction 2 - 3 Tendering - - - Design - 2 6 Planning - 1 - TOTAL 2 3 9

Table 24 : Summary of Sponsored Projects

Expected Zone Project Description Status Details Purpose Completion Date New Al Bandar [P197] 3 Q4’2021 Under Construction 3 x 20 MVA TX Government Primary Substation

MEDC Distribution System Capability Statement (2021-2023) – V2.0 43

Table 25 : Summary of Planned Projects in MEDC Distribution System to meet Summer 2021 Maximum Demand

Expected Zone Project Description Status Details Purpose Compl.Date New Amerat 4 [P180] Primary Under To relieve the load of adjacent 1 Q1’2021 3 x 20 MVA TX Substation Construction PSS & accommodate new loads Upgrading Sur Al Hadid Under To relieve the load of adjacent 3 Q4’2020 3 x 20 MVA TX [P116]PrimarySubstation Construction PSS & accommodate new loads To cater for the new demand in OETC Project: Khoudh Under 3 Q4’2020 4 x 125 MVA TX the area & Load transfer from 132/33kV grid station Construction nearby grid station Table 26 : Summary of Planned Projects in MEDC Distribution System and OETC to meet Summer 2022 Maximum Demand

Expected Zone Project Description Status Details Purpose Compl.Date To replace the assets and to Upgrading Seih Dhabi [P118] Under 1 Q4’2021 2 x 20 MVA TX meet the security of supply PrimarySubstation Construction standards. To relieve the load of adjacent Upgrading Mabelah South Under 3 Q4’2021 3 x 20 MVA TX PSS & accommodate new loads [P061] Primary Substation Construction & to replace the assets To cater for the new demand in OETC Project: Mabelah Under 3 Q3’2021 4 x 125 MVA TX the area & Load transfer from Industrial 132/33kV grid station Construction nearby grid station

Table 27 : Summary of Planned Projects in MEDC Distribution System and OETC to meet Summer 2023 Maximum Demand

Expected Zone Project Description Status Details Purpose Compl.Date Upgrading Sarooj-Shati Al To relieve the load of adjacent PSS 2 Qurum [P110] Primary Q1’2023 Design Stage 3 x 20 MVA TX & accommodate new loads Substation New Ghala3 [P189] To relieve the load of adjacent PSS 2 Q1’2023 Design Stage 3 x 20 MVA TX Primary Substation & accommodate new loads To accommodate new loads based New ROP Airport Height Planning 2 Q1’2023 3 x 20 MVA TX on bulk application of ROP and [P195] Primary Substation Stage Golden Tulip New Mabelah South PH 6 To relieve the load of adjacent PSS 3 Q2’2022 Design Stage 3 x 20 MVA TX [P185]PrimarySubstation & accommodate new loads. New Mabelah South PH To relieve the load of adjacent PSS 3 Q1’2023 Design Stage 3 x 20 MVA TX 9[P185]PrimarySubstation & accommodate new loads. Upgrading Al Khod To relieve the load of adjacent PSS 3 Shabiya [P046] Primary Q2’2022 Design Stage 3 x 20 MVA TX & accommodate new loads Substation New Al Khod Shabiya-B To relieve the load of adjacent PSS 3 Q2’2022 Design Stage 2 x 20 MVA TX [P187] Primary Substation & accommodate new loads Upgrading Al Hail North To accommodate new bulk loads 3 Q1’2023 Design Stage 3 x 20 MVA TX 1[P027]PrimarySubstation based on application UpgradingMawalehNorth To accommodate new bulk loads 3 Q1’2023 Design Stage 3 x 20 MVA TX [P069]Primary Substation based on application

MEDC Distribution System Capability Statement (2021-2023) – V2.0 44

Zone 1 – (The Eastern Zone)

The Zone 1 region includes the capital city of Muscat, Muttrah and an extensive rural network, which covers the wilayats of Amerat and Quriyat. The number of customers served in the Zone 1 region is 130,855 which is approximately 32 % of the total customer population.

The following primary projects are projected in the period 2021 to 2023.

Project 1: New Amerat-4 (P180) Primary Substation with 3 x 20 MVA Configuration

Amerat-4 primary substation is proposed in the Amerat Area to facilitate 11kV transfers and interlinks with nearby primary (Al Nahdah and Amerat Heights) and to accommodate the new loads. The expected completion date of the project is Q1’2021 and the 33kV connection point is from Amerat-B Grid.

Project 2: Upgrading Seih Dhabi (P118) Primary Substation with 2 x 20 MVA Configuration

Upgrading of Seih Dhabi primary substation in the Amerat area to upgrade the existing assets and improve the security of supply in the area. The expected completion date of the project is Q4’2021 and the 33kV connection point is from Amerat-B Grid.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 45

Zone 2 - (The Central Zone)

The Zone 2 region covers the commercial and residential areas of Bousher, Al Khuwair, Al Ansab, Azaibah and Qurum. This is largely an established area, which has seen high load growth in previous years. The Mall of Oman is the largest expected commercial projects in Zone 2 region.

The number of customers served in the Zone 2 region is 118,759 which is approximately 29 % of the total customer population.

The following primary projects are projected in the period 2021 to 2023.

Project 1: New Ghala 3 (P189) Primary Substation with 3 x 20 MVA Configuration

The new Ghala 3 primary substation is proposed in the Azaibah area to facilitate 11kV transfers and interlinks with nearby primary (Azaibah South 1-A and Azaibah South 1-B) and to accommodate the new loads. The expected completion date of the project is Q1’2023 and the 33kV connection point is from Ghala Heights GSS.

Project 2: Upgrading Sarooj-Shati Al Qurum (P110) Primary Substation with 3 x 20 MVA Configuration [Replacement project of New Sarooj 4-P181]

Upgrading Sarooj-Shati Al Qurum (P110) primary substation is proposed in the Sarooj Area to facilitate the connection of new multiple bulk loads rather than area growth and the transfer of 11kV loads from nearby loaded primary substations to ensure security of supply is maintained. The expected completion date of the project is Q1’2023 and the 33kV connection point is from MSQ-A GSS.

Project 3: New ROP Airport Height (P195) Primary Substation with 3 x 20 MVA Configuration

The new ROP Airport Height primary substation is proposed in the Airport Area to facilitate the connection of new bulk loads from ROP and Golden Tulip. The expected completion date of the project is Q1’2023 and the 33kV connection point is from Airport Height GSS.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 46

Zone 3 - (The Western Zone)

The Zone 3 region includes the Muscat International Airport, Rusail Industrial Area, Seeb, Mawalleh, Al Khoud and Mabelah areas. The number of customers served in the Zone 3 region is 163,753 which is approximately 39 % of the total customer population.

The following primary projects are projected in the period 2021 to 2023.

Project 1: Upgrading Sur Al Hadid (P116) Primary Substation with 3 x 20 MVA Configuration

Upgrading of Sur Al Hadid primary substation in the Seeb area is proposed to accommodate new loads and facilitate 11kV load transfers in that area whilst ensuring security of supply is maintained. The expected completion date of the project is Q4’2020 and the 33kV connection point is from Mabelah-A GSS.

Project 2: Upgrading Mabelah South (P061) Primary Substation with 3 x 20 MVA Configuration

Upgrading of Mabelah South primary substation in the Mabelah area to upgrade the existing assets and improve the security of supply in the area. The expected completion date of the project is Q4’2021 and the 33kV connection point is from Mabelah-2(A’Salam) GSS.

Project 3: Upgrading Al Khoud Shabiya (P046) Primary Substation with 3 x 20 MVA Configuration Upgrading of Al Khoud Shabiya primary substation in the Al Khoud area is proposed to accommodate new loads and facilitate 11kV load transfers in that area whilst ensuring security of supply is maintained. The expected completion date of the project is Q1’2023 and the 33kV connection point is from Seeb Main-B GSS.

Project 4: New Al Khoud Shabiya-B (P187) Primary Substation with 2 x 20 MVA Configuration The new Al Khoud Shabiya-B primary substation in the Al Khoud area is proposed to accommodate new loads and facilitate 11kV load transfers from nearby PSSs(New Al Khoud and Al Khoud PH-7) in that area whilst ensuring security of supply is maintained. The expected completion date of the project is Q1’2023 and the 33kV connection point is from Khoudh GSS.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 47

Project 5: New Mabelah South PH 6 (P185) Primary Substation with 3 x 20 MVA Configuration

The new Mabelah South PH 6 primary substation in the Mabelah area is proposed to accommodate new loads and facilitate 11kV load transfers from nearby PSSs(Mabelah Grid and Mabelah South PH- 4) in that area whilst ensuring security of supply is maintained. The expected completion date of the project is Q1’2023 and the 33kV connection point is from Mabelah-2(A’Salam) GSS.

Project 6: Upgrading Al Hail North 1 (P027) Primary Substation with 3 x 20 MVA Configuration Upgrading Al Hail North 1 primary substation in the Hail area is proposed to accommodate new bulk load request from Al Mouj and Naseem A’Sabaa. The expected completion date of the project is Q1’2023 and the 33kV connection point is from Mawaleh North GSS.

Project 7: Upgrading Mawaleh North (P069) Primary Substation with 3 x 20 MVA Configuration Upgrading Mawaleh North primary substation in the Hail area is proposed to accommodate new bulk load request from Al Mouj and Naseem A’Sabaa. The expected completion date of the project is Q1’2023 and the 33kV connection point is from Mawaleh North GSS.

Project 8: New Mabelah South PH 9 (P184) Primary Substation with 3 x 20 MVA Configuration

The new Mabelah South PH 9 primary substation in the Mabelah area is proposed to accommodate new loads and facilitate 11kV load transfers from nearby PSSs(Mabelah Grid,Mabelah South PH-7 and Mabelah South PH-8) in that area whilst ensuring security of supply is maintained. The expected completion date of the project is Q14’2023 and the 33kV connection point is from Halban(Mabelah South) GSS.

OETC Project: Khoudh 132/33kV grid Station with 4 x 125 MVA Configuration

Khoudh 132/33kV grid station is required to cater for the new demand in the area, to Load transfer from nearby grid station and to meet Transmission Security Standard. The expected completion date of the project is Q4’2020.

OETC Project: Mabelah Industrial 132/33kV grid Station with 4 x 125 MVA Configuration [Previously named as Halban GSS]

Mabelah Industrial 132/33kV grid station is required to cater for the new demand in the area, to Load transfer from nearby grid station and to meet Transmission Security Standard. The expected completion date of the project is Q3’2021.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 48

APPENDIX A: DISTRIBUTION LICENCE CONDITION 32 : D S C S

Distribution Licence Condition 32: Distribution System Capability Statement

1. The Licensee shall, within 12 months of the grant of this Licence, and thereafter, on an annual basis, prepare a statement, in a form approved by the Authority, showing, in respect of each of the three succeeding financial years, circuit capacity, forecast power flows and loading on each part of its Distribution System and fault levels for each transmission node, together with: a. Information on the status of distribution circuit capacity and the anticipated future requirements of such capacity, including (i) applications for new connections and (ii) applications to Connect Generation capacity to its Systems; b. A commentary prepared by the Licensee indicating the Licensee's views as to those parts of its Distribution System most suited to new Connections and Distribution of further quantities of electricity, including the prospective for Connection of Systems operated by the Rural Areas Electricity Company SAOC; c. Information on what constraints are foreseen on the Licensee's Distribution System and where; d. Information relating to progress of ongoing investment in its Distribution System; e. Such further information as shall be reasonably necessary to enable any Person seeking to Connect to or use the Licensee's Distribution System to identify and evaluate the opportunities for so doing; f. An assessment of technical losses from the Licensee's Distribution System; and g. Such other matters as shall be specified in directions issued by the Authority from time to time for the purposes of this Condition, provided that the Authority may, upon application of the Licensee, relieve the Licensee from the obligation to prepare any such statement in respect of any period and any part or parts of its Distribution System specified in directions issued to the Licensee by the Authority from time to time for the purposes of this Condition. 2. The Licensee shall include in every statement prepared in accordance with paragraph 1 above the information required by that paragraph except that the Licensee may with the prior consent of the Authority omit from any such statement any details as to the capacity, flows, loading or other information, disclosure of which would, in the view of the Authority, seriously and prejudicially affect the commercial interests of the Licensee or any third party. 3. The Licensee may periodically revise the information set out in and, with the approval of the Authority, alter the form of the statement prepared in accordance with paragraph 1 and shall, at least once in every year this Licence is in force, revise such statement in order that the information set out in the statement shall continue to be accurate in all material respects. 4. The Licensee shall, when preparing the statement referred to in paragraph 1 of this Condition, ensure that the statement takes due account of information required to be provided to it by Persons bound by the Distribution Code. 5. The Licensee shall send a copy of the statement prepared in accordance with paragraph 1 and of each revision of such statement in accordance with paragraph 3 to the Authority. Each such revision shall require to be approved by the Authority and shall not become effective until approved by the Authority. 6. The Licensee shall, subject to paragraph 6, give or send a copy of the statement prepared in accordance with paragraph 1 or (as the case may be) of the latest revision of such statement in accordance with paragraph 3 approved by the Authority pursuant to such paragraph to any Person who requests a copy of such statement. 7. The Licensee may make a charge for any statement given or sent pursuant to paragraph 4 of an amount reflecting the Licensee's reasonable costs of providing such a statement, which shall not exceed the maximum amount specified in directions issued by the Authority from time to time for the purposes of this Condition

MEDC Distribution System Capability Statement (2021-2023) – V2.0 49

APPENDIX B : D S S S NON - COMPLIANCES

Firm DNS Zone Primary Substation P-No. TX Config MW MVAr MVA (MVA)25 (MVA)15

1 Qasr Al Alam P090 2 x 20 15.4 15.9 6.9 17.3 2.6 1 Al Hamryah P035 2 x 20 0 9.2 4.4 10.2 10.2 1 Amerat 1 P005 2 x 16 15.4 14.7 5.3 15.6 1.2 3 Old Mabelah P059 2 x 20 15.4 21.8 9.0 23.6 8.7 3 Mabelah Grid GP04 2 x 20 22.0 22.8 7.6 24.0 4.2 3 Mabelah South P061 2 x 20 0 17.7 8.1 19.5 19.5

Total 46.4

25 For all >=20 MVA primary stations, APSR has allowed an additional 10% to the Firm Capacity [ie: For 2x20 MVA TX -22MVA Firm and for 3x20 MVA TX -44MVA Firm] for the DNS calculation purposes only and not system planning or development.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 50

APPENDIX C: LIST OF 2 0 2 0 PV SOLAR APPLICATIONS

Connection Point Details Requeste Customer S.No Location d Status Primary Category 11kV Feeder S/S Name Substation kW

1 Al Khoudh - - - 30 Commercial Under Construction

2 Al Mawaleh Mawaleh Mawaleh Main 8 Residential Connected South

3 Al Khoudh - - - 10 Residential Under Construction

4 Al Seeb Al Khoudh Ph- Fdr-01 Al Koudh S/S 10 Residential Connected 7 26

5 Bousher - - - 10 Residential Under Construction

6 Bousher Al Muna Al Fatah Fdr - 10 Residential Connected No. 2

7 Al Amerat - - - 11 Residential Awaited Application

8 Al Amerat - - - 10 Residential Under Construction

9 Ghala Ghubrah Al-Ansab Fdr. - 120 Commercial Connected South - P026 No: 9

10 Al Mawaleh - - - 50 Commercial Initial Application Submitted

11 Al Ansab - - - 50 Residential Initial Application Submitted

12 Al Ansab - - - 5.2 Residential Initial Application Submitted

13 Al Ansab - - - 5.2 Residential Initial Application Submitted

14 Al Mabelah - - - 16.9 Residential Initial Application Submitted

15 Al Qurum - - - 8 Residential Initial Application Submitted

MEDC Distribution System Capability Statement (2021-2023) – V2.0 51

Connection Point Details Requeste Customer S.No Location d Status Primary Category 11kV Feeder S/S Name Substation kW

16 Al Qurum - - - 8 Residential Initial Application Submitted

17 Al Qurum - - - 8 Residential Initial Application Submitted

18 Al Qurum - - - 8 Residential Initial Application Submitted

19 Al Qurum - - - 10 Residential Initial Application Submitted

20 Al Qurum - - - 10 Residential Initial Application Submitted

21 Al Qurum - - - 10 Residential Initial Application Submitted

22 Al Qurum - - - 10 Residential Initial Application Submitted

23 Al Qurum - - - 10 Residential Initial Application Submitted

24 Al Qurum - - - 10 Residential Initial Application Submitted

25 Rusail - - - 400 Commercial Initial Application Submitted

26 Bousher Msq Grid Technical Bousher S/S 10 Residential Connected College C15 238

27 AlMawaleh - - - 10 Residential Awaited South Application

28 Al Qurum Shati Quram ROP Shati Shati Quram 10 Residential Connected Quram Ring 40 SS NO 11 FDR

29 Al Amerat - - - 10 Residential Initial Application Submitted

30 Al Hail South Al Hail South 1 Out Going Fdr 6 Al Hail South 20 Residential Connected S-S No.61

31 Rusail - - - 120 Commercial Initial Application Submitted

MEDC Distribution System Capability Statement (2021-2023) – V2.0 52

Connection Point Details Requeste Customer S.No Location d Status Primary Category 11kV Feeder S/S Name Substation kW

32 Al Seeb Al Khoudh Al Khoud Ext-3 Al Khoudh S/S 9.75 Residential Under Shabiya Fdr 2 18 Construction

33 Al Seeb Al Khoud Ph-7 Out Going Fdr 6 Al Khoudh 9.75 Residential Under Shabiya 19 Construction

34 Al Seeb Al Khoudh Al Khoud Ext-3 Al Khoudh S/S 9.75 Residential Under Shabiya Fdr 2 18 Construction

35 Al Seeb Al Khoud Ph-7 Out Going Fdr 6 Al Khoudh 9.75 Residential Under Shabiya 19 Construction

36 Al Seeb Al Khoud Ph-7 Out Going Fdr 6 Al Khoudh 9.75 Residential Under Shabiya 19 Construction

37 Al Seeb Al Khoudh Al Khoud Ext-3 Al Khoudh S/S 9.75 Residential Under Shabiya Fdr 2 18 Construction

38 Madinat Al Iam Msq 2 Feeder-5 To Information 6.2 Residential Initial Application S/S No.18a City S/S-18 Submitted

MEDC Distribution System Capability Statement (2021-2023) – V2.0 53

APPENDIX D: SYSTEM STUD Y R E S U L T S

Appendix D presents the following series of tables, for each grid substation power system model, which show the expected performance of the distribution network under maximum and minimum demand scenarios for each year from 2020 to 2023.

1. Primary Substations Maximum Demand and Percentage Loading The maximum demand with real and reactive power loads at the PSS individual peak time in 2020 planning cycle and as accordingly forecasted for the period from 2021 to 2023. Percentage loading is calculated based on the Firm Capacity of the PSS. This data was used in the load flow and fault level studies for maximum demand scenario presented in this section of this DSCS.

2. Primary Substations Minimum Demand and Percentage Loading The minimum demand with real and reactive power loads at the PSS individual minimum time in 2020 planning cycle and as accordingly forecasted for the period from 2021 to 2023. This data was used in the load flow studies for minimum demand scenario presented in this section of this DSCS.

3. 33kV Feeder Loads The resulting maximum demand in MVA on 33kV circuits/feeders, calculated for the individual non- coincident maximum loads of the PSS(s) connected to these feeders for the period 2020 to 2023. Percentage loading is calculated based on the de-rated capacity of the circuits.

4. Primary Substations Bus Voltages The resulting voltage value (expressed in percentage of the nominal 33kV and 11kV) on the busbars of the PSSs, corresponding to maximum and minimum demand scenarios.

5. Primary Substation 3-Phase Fault Current Levels (kA) The resulting 3 phase maximum fault current level on the busbars of the PSSs, corresponding to maximum demand scenarios. The rated breaking fault ratings of the switchgear are also specified.

Explanatory Notes: a) 1TX in Firm Capacity means primary substation has single 33/11.5 kV transformer (i.e. zero N- 1 capacity and firm capacity equivalent to 11kV interconnection capacity); b) Standby PSS means primary substation having 33kV and 11kV busbars energized with 11kV outgoing feeders (i.e. loads) disconnected. The load on these PSSs is expected to be connected occasionally, depending on requirement.

In the above mentioned tables, a “-“ (dash) appears in relevant years due to any of the following reasons, as may be applicable:

− The primary substation is shifted (i.e. connected) to another grid substation; − The primary substation, or any of its capacity enhancement project, is planned to be energized/commissioned in the future; − There are no 11kV busbars (rather a different voltage level exists e.g. 6.9kV for a private customer, operated and maintained by the customer); − MEDC doesn’t have the information of the network below 33kV level.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 54 Falaj[G23] GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Darsait P018 20 13.9 4.4 14.6 73% 13.9 4.6 14.6 73% 13.9 4.6 14.6 73% 13.9 4.6 14.6 73% Falaj P178 16 9.8 3.9 10.5 66% 9.8 3.9 10.5 66% 9.8 3.9 10.5 66% 9.8 3.9 10.5 66% Jibrooh P041 40 23.4 10.0 25.5 64% 23.4 7.7 24.6 62% 23.4 7.7 24.6 62% 23.4 7.7 24.6 62% Mutrah Store P085 20 9.5 5.6 11.0 55% 9.5 5.6 11.0 55% 9.5 5.6 11.0 55% 9.5 5.6 11.0 55% P.D.O P144 40 20.7 8.3 22.3 56% 20.7 8.2 22.3 56% 20.7 8.2 22.3 56% 20.7 8.2 22.3 56% Seaport P086 6 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Darsait P018 20 2.1 1.4 2.5 13% 2.1 1.4 2.5 13% 2.1 1.4 2.5 13% 2.1 1.4 2.5 13% Falaj P178 16 1.5 1.3 2.0 13% 1.5 1.3 2.0 13% 1.5 1.3 2.0 13% 1.5 1.3 2.0 13% Jibrooh P041 40 4.4 2.1 4.9 12% 4.3 2.1 4.7 12% 4.3 2.1 4.7 12% 4.3 2.1 4.7 12% Mutrah Store P085 20 1.8 1.4 2.3 11% 1.8 1.4 2.3 11% 1.8 1.4 2.3 11% 1.8 1.4 2.3 11% P.D.O P144 40 3.6 1.8 4.0 10% 3.7 1.8 4.1 10% 3.7 1.8 4.1 10% 3.7 1.8 4.1 10% Seaport P086 6 0.5 0.2 0.5 9% 0.1 0.1 0.1 2% 0.1 0.1 0.1 2% 0.1 0.1 0.1 2% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Darsait-F1-P018 22.0 7.3 33.1 7.4 33.5 7.4 33.5 7.4 33.5 Darsait-F2-P018 22.0 7.4 33.6 7.5 34.0 7.5 34.0 7.5 34.0 Falaj-F1-P178 22.0 5.4 24.3 5.4 24.3 5.4 24.3 5.4 24.3 Falaj-F2-P178 22.0 5.3 24.2 5.3 24.1 5.3 24.1 5.3 24.1 Jibrooh-F1-P041 22.0 8.4 38.1 8.3 37.8 8.3 37.8 8.3 37.8 Jibrooh-F2-P041 22.0 8.4 38.1 8.3 37.7 8.3 37.7 8.3 37.7 Seaport-F1-P086 22.0 9.7 44.0 9.2 41.7 9.2 41.7 9.2 41.7 Mutrah Store-F1-P085 22.0 5.6 25.3 5.6 25.3 5.6 25.3 5.6 25.3 Mutrah Store-F2-P085 22.0 5.5 25.1 5.5 25.1 5.5 25.1 5.5 25.1 PDO-F1-P144 22.0 7.4 33.7 5.5 25.1 5.5 25.1 5.5 25.1 PDO-F2-P144 22.0 7.0 31.8 5.5 25.1 5.5 25.1 5.5 25.1 PDO-F3-P144 22.0 0.1 0.6 5.5 25.1 5.5 25.1 5.5 25.1 PDO-F4-P144 22.0 7.6 34.3 5.5 25.1 5.5 25.1 5.5 25.1 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Darsait-A P018 101.2 101.1 104.2 105.3 101.2 101.3 105.3 104.4 101.2 101.3 105.3 104.4 101.2 101.2 104.4 105.3 Darsait-B P018 101.2 101.1 104.2 105.3 101.2 101.3 105.3 104.4 101.2 101.3 105.3 104.4 101.2 101.2 104.4 105.3 Falaj-A P178 101.2 101.1 104.3 105.3 101.2 101.3 105.3 104.7 101.2 101.3 105.3 104.7 101.2 101.2 104.7 105.3 Falaj-B P178 101.2 101.1 104.3 105.3 101.2 101.3 105.3 104.7 101.2 101.3 105.3 104.7 101.2 101.2 104.7 105.3 Jibrooh-A P041 100.9 101.1 103.1 105.2 100.9 101.1 105.2 104.5 101.1 101.1 105.2 104.5 101.1 101.1 104.5 105.2 Jibrooh-B P041 100.9 101.1 103.1 105.2 100.9 101.1 105.2 104.5 101.1 101.1 105.2 104.5 101.1 101.1 104.5 105.2 Jibrooh-C P041 100.2 100.9 102.3 105.0 100.2 100.4 105.1 104.6 101.0 100.4 105.1 104.6 101.0 101.0 104.6 105.1 Mutrah Store-A P085 101.1 101.1 103.7 105.2 101.1 101.2 105.3 104.1 101.1 101.2 105.3 104.1 101.1 101.1 104.1 105.3 Mutrah Store-B P085 101.1 101.1 103.7 105.2 101.1 101.2 105.3 104.1 101.1 101.2 105.3 104.1 101.1 101.1 104.1 105.3 PDO-A P144 101.1 101.1 - - 101.1 101.2 - - 101.2 101.2 - - 101.2 101.2 - - PDO-B P144 101.1 101.1 - - 101.1 101.2 - - 101.2 101.2 - - 101.2 101.2 - - PDO-C P144 101.2 101.1 - - 101.2 101.2 - - 101.2 101.2 - - 101.2 101.2 - - PDO-D P144 101.1 101.1 - - 101.1 101.2 - - 101.2 101.2 - - 101.2 101.2 - - Seaport-A P086 100.4 100.9 104.9 105.2 100.4 100.5 105.6 105.5 101.0 100.5 105.6 105.5 101.0 101.0 105.5 105.6 Seaport-B P086 - - - - 100.4 100.4 105.6 105.5 101.0 100.4 105.6 105.5 101.0 101.0 105.5 105.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 55 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Darsait-A P018 25.0 18.4 20.7 14.0 21.0 14.1 21.8 14.2 21.8 14.2 Darsait-B P018 25.0 18.4 20.7 14.0 21.0 14.1 21.8 14.2 21.7 14.2 Falaj-A P178 25.0 18.4 21.4 13.3 21.7 13.3 22.6 13.4 22.5 13.4 Falaj-B P178 25.0 18.4 21.3 13.3 21.6 13.3 22.5 13.4 22.5 13.4 Jibrooh-A P041 25.0 20.0 15.8 13.9 15.9 13.9 16.4 14.0 16.4 14.0 Jibrooh-B P041 25.0 20.0 15.7 13.9 15.9 13.9 16.3 14.0 16.3 14.0 Jibrooh-C P041 25.0 20.0 8.9 7.1 9.0 7.1 9.1 7.1 9.1 7.1 Mutrah Store-A P085 25.0 18.4 17.9 13.5 18.2 13.6 18.8 13.7 18.7 13.7 Mutrah Store-B P085 25.0 18.4 17.9 13.5 18.2 13.6 18.8 13.7 18.7 13.7 PDO-A P144 25.0 - 19.2 - 19.4 - 20.1 - 20.1 - PDO-B P144 25.0 - 19.2 - 19.4 - 20.1 - 20.1 - PDO-C P144 25.0 - 19.1 - 19.4 - 20.1 - 20.0 - PDO-D P144 25.0 - 19.2 - 19.4 - 20.1 - 20.0 - Seaport-A P086 25.0 18.4 8.6 4.0 8.7 6.9 8.8 6.9 8.8 6.9 Seaport-B P086 25.0 18.4 - - 7.8 6.9 7.9 6.9 7.9 6.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 56 Mutrah[G21] GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % C.B.D P173 32 16.4 10.5 19.5 61% 16.4 10.6 19.5 61% 16.4 10.6 19.5 61% 16.4 10.6 19.5 61% Bait Al Falaj P142 40 25.5 13.1 28.7 72% 25.5 8.4 26.9 67% 25.5 8.4 26.9 67% 25.5 8.4 26.9 67% Riyam P099 20 14.0 3.7 14.5 73% 14.0 3.5 14.4 72% 14.0 3.5 14.4 72% 14.0 3.5 14.4 72% Ruwi Office P108 20 12.6 7.7 14.8 74% 12.6 4.1 13.3 66% 12.6 4.1 13.3 66% 12.6 4.1 13.3 66% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % C.B.D P173 32 3.4 2.1 4.0 12% 3.4 2.1 4.0 13% 3.4 2.1 4.0 13% 3.4 2.1 4.0 13% Bait Al Falaj P142 40 4.9 2.2 5.4 14% 4.6 2.1 5.1 13% 4.6 2.1 5.1 13% 4.6 2.1 5.1 13% Riyam P099 20 1.9 1.3 2.3 12% 1.9 1.3 2.3 11% 1.9 1.3 2.3 11% 1.9 1.3 2.3 11% Ruwi Office P108 20 1.6 1.2 2.0 10% 1.4 1.1 1.8 9% 1.4 1.1 1.8 9% 1.4 1.1 1.8 9% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Bait Al Falaj-F1-P142 22.0 10.2 46.0 9.1 41.2 9.1 41.2 9.1 41.2 Bait Al Falaj-F2-P142 22.0 10.2 46.1 9.1 41.3 9.1 41.3 9.1 41.3 Bait Al Falaj-F3-P142 22.0 9.1 41.2 9.1 41.2 9.1 41.2 9.1 41.2 C.B.D-F1-P173 22.0 7.4 33.5 6.7 30.4 6.7 30.4 6.7 30.4 C.B.D-F2-P173 22.0 7.3 33.2 6.6 30.2 6.6 30.2 6.6 30.2 C.B.D-F3-P173 22.0 5.3 24.3 6.7 30.3 6.7 30.3 6.7 30.3 Riyam-F1-P099 15.4 7.3 47.4 7.3 47.4 7.3 47.4 7.3 47.4 Riyam-F2-P099 15.4 7.4 47.7 7.3 47.7 7.3 47.7 7.3 47.7 Ruwi Office-F1-P108 22.0 7.6 34.3 6.7 30.4 6.7 30.4 6.7 30.4 Ruwi Office-F2-P108 22.0 7.6 34.3 6.7 30.4 6.7 30.4 6.7 30.4

MEDC Distribution System Capability Statement [2021-2023]-V2.0 57 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Bait Al Falaj-A P142 100.4 100.7 101.6 104.7 101.0 100.7 103.5 104.8 101.0 100.7 103.5 104.8 101.0 100.7 103.5 104.8 Bait Al Falaj-B P142 100.4 100.7 101.6 104.7 101.0 100.7 103.5 104.8 101.0 100.7 103.5 104.8 101.0 100.7 103.5 104.8 Bait Al Falaj-C P142 100.4 100.7 102.0 104.8 101.0 100.7 103.5 104.8 101.0 100.7 103.5 104.8 101.0 100.7 103.5 104.8 C.B.D-A P173 100.6 100.7 102.4 104.8 101.2 100.7 103.4 104.8 101.2 100.7 103.4 104.8 101.2 100.7 103.4 104.8 C.B.D-B P173 100.6 100.7 102.4 104.8 101.2 100.7 103.4 104.8 101.2 100.7 103.4 104.8 101.2 100.7 103.4 104.8 C.B.D-C P173 100.6 100.7 103.2 104.9 101.2 100.7 103.4 104.8 101.2 100.7 103.4 104.8 101.2 100.7 103.4 104.8 Riyam-A P099 99.2 100.5 102.2 104.6 99.8 100.5 102.9 104.6 99.8 100.5 102.9 104.6 99.8 100.5 102.9 104.6 Riyam-B P099 99.2 100.5 102.2 104.6 99.8 100.5 102.9 104.6 99.8 100.5 102.9 104.6 99.8 100.5 102.9 104.6 Ruwi Office-A P108 100.4 100.7 102.1 104.8 101.1 100.7 104.1 104.9 101.1 100.7 104.1 104.9 101.1 100.7 104.1 104.9 Ruwi Office-B P108 100.4 100.7 102.1 104.8 101.1 100.7 104.1 104.9 101.1 100.7 104.1 104.9 101.1 100.7 104.1 104.9 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Bait Al Falaj-A P142 25.0 25.0 18.5 14.5 18.7 14.4 19.3 14.5 19.3 14.5 Bait Al Falaj-B P142 25.0 25.0 18.5 14.5 18.7 14.4 19.3 14.5 19.3 14.5 Bait Al Falaj-C P142 25.0 25.0 18.4 8.0 18.6 8.0 19.3 8.0 19.2 8.0 C.B.D-A P173 25.0 18.4 22.4 14.6 22.7 14.5 23.7 14.7 23.6 14.7 C.B.D-B P173 25.0 18.4 22.5 14.6 22.7 14.5 23.7 14.7 23.7 14.7 C.B.D-C P173 25.0 18.4 22.4 8.0 22.7 8.1 23.6 8.2 23.6 8.2 Riyam-A P099 25.0 18.4 7.2 11.7 7.3 11.7 7.3 11.8 7.3 11.8 Riyam-B P099 25.0 18.4 7.2 11.7 7.3 11.7 7.4 11.8 7.4 11.8 Ruwi Office-A P108 25.0 18.4 19.2 13.9 19.4 13.8 20.1 14.0 20.1 14.0 Ruwi Office-B P108 25.0 18.4 19.2 13.9 19.4 13.8 20.1 14.0 20.1 14.0

MEDC Distribution System Capability Statement [2021-2023]-V2.0 58 Wadi Al Kabir[G19] - A GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Ali Shihani P125 20 10.3 5.3 11.6 58% 10.3 3.4 10.8 54% 10.3 3.4 10.8 54% 10.3 3.4 10.8 54% M.B.D. South P075 20 13.9 5.5 14.9 75% 13.9 4.6 14.6 73% 13.9 4.6 14.6 73% 13.9 4.6 14.6 73% Majlis Oman P066 20 4.9 1.4 5.1 26% 4.9 1.4 5.1 26% 4.9 1.4 5.1 26% 4.9 1.4 5.1 26% Qasr Al Alam P090 20 15.9 6.9 17.3 87% 15.9 5.2 16.7 84% 15.9 5.2 16.7 84% 15.9 5.2 16.7 84% Sidab P119 6 4.8 1.9 5.2 86% 4.8 1.9 5.2 86% 4.8 1.9 5.2 86% 4.8 1.9 5.2 86% Wadi Al Kabir Housing P127 1TX Standby PSS Wadi Al Kabir Workshop P126 6 4.0 1.6 4.3 72% 4.0 1.6 4.3 72% 4.0 1.6 4.3 72% 4.0 1.6 4.3 72% Waljah P130 20 14.9 6.8 16.3 82% 14.9 4.9 15.6 78% 14.9 4.9 15.6 78% 14.9 4.9 15.6 78% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity MVA MVA MVA MVA MW MVA % MW MVA % MW MVA % MW MVA % (MVA) r r r r Ali Shihani P125 20 1.0 0.8 1.3 7% 0.9 0.8 1.2 6% 0.9 0.8 1.2 6% 0.9 0.8 1.2 6% M.B.D. South P075 20 1.8 1.2 2.2 11% 1.8 1.2 2.2 11% 1.8 1.2 2.2 11% 1.8 1.2 2.2 11% Majlis Oman P066 20 0.8 0.1 0.8 4% 0.8 0.1 0.8 4% 0.8 0.1 0.8 4% 0.8 0.1 0.8 4% Qasr Al Alam P090 20 5.6 3.0 6.4 32% 5.4 2.9 6.2 31% 5.4 2.9 6.2 31% 5.4 2.9 6.2 31% Sidab P119 6 0.8 0.4 0.9 16% 0.9 0.4 0.9 16% 0.9 0.4 0.9 16% 0.9 0.4 0.9 16% Wadi Al Kabir Housing P127 1TX Standby PSS Wadi Al Kabir Workshop P126 6 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% Waljah P130 20 1.6 1.4 2.1 11% 1.5 1.3 2.0 10% 1.5 1.3 2.0 10% 1.5 1.3 2.0 10% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Ali Shihani-F1-P125 22.0 5.9 26.6 5.5 24.8 5.5 24.8 5.5 24.8 Ali Shihani-F2-P125 22.0 5.9 26.6 5.5 24.8 5.5 24.8 5.5 24.8 M.B.D. South-F1-P075 22.0 7.6 34.2 7.4 33.4 7.4 33.4 7.4 33.4 M.B.D. South-F2-P075 22.0 7.6 34.2 7.4 33.4 7.4 33.4 7.4 33.4 Majlis Oman-F1-P066 22.0 2.5 11.5 2.5 11.5 2.5 11.5 2.5 11.5 Majlis Oman-F2-P066 22.0 2.6 11.6 2.6 11.6 2.6 11.6 2.6 11.6 Qasr al Alam-F1-P090 15.4 9.0 58.4 8.7 56.3 8.7 56.3 8.7 56.3 Qasr al Alam-F2-P090 15.4 8.9 57.7 8.6 55.6 8.6 55.6 8.6 55.6 Muscat 01 Feeder for WK Workshop (P126), 22.0 9.7 40.3 9.7 40.2 9.7 40.2 9.7 40.2 Sidab (P119) & WK Housing Walja-F1-P130 22.0 8.4 38.0 8.0 36.2 8.0 36.2 8.0 36.2 Walja-F2-P130 22.0 8.3 37.6 7.9 35.8 7.9 35.8 7.9 35.8 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Ali Shihani-A P125 100.8 100.5 103.5 104.8 100.1 100.5 103.3 104.9 100.1 100.5 103.3 104.9 100.1 100.5 103.3 104.9 Ali Shihani-B P125 100.8 100.5 103.5 104.8 100.1 100.5 103.3 104.9 100.1 100.5 103.3 104.9 100.1 100.5 103.3 104.9 M.B.D. South-A P075 100.7 100.5 103.3 104.7 100.0 100.5 102.8 104.7 100.0 100.5 102.8 104.7 100.0 100.5 102.8 104.7 M.B.D. South-B P075 100.7 100.5 103.3 104.7 100.0 100.5 102.8 104.7 100.0 100.5 102.8 104.7 100.0 100.5 102.8 104.7 Majlis Oman-A P066 100.6 100.5 104.6 105.0 99.8 100.5 103.8 105.1 99.8 100.5 103.8 105.1 99.8 100.5 103.8 105.1 Majlis Oman-B P066 100.6 100.5 104.6 105.0 99.8 100.5 103.8 105.1 99.8 100.5 103.8 105.1 99.8 100.5 103.8 105.1 Qasr al Alam-A P090 99.5 100.0 101.4 103.5 98.8 100.1 101.3 103.6 98.8 100.1 101.3 103.6 98.8 100.1 101.3 103.6 Qasr al Alam-B P090 99.5 100.0 101.4 103.5 98.8 100.1 101.3 103.6 98.8 100.1 101.3 103.6 98.8 100.1 101.3 103.6 Sidab-A P119 100.3 100.4 103.6 104.7 99.6 100.4 102.8 104.8 99.6 100.4 102.8 104.8 99.6 100.4 102.8 104.8 Sidab-B P119 100.3 100.4 103.6 104.7 99.6 100.4 102.8 104.8 99.6 100.4 102.8 104.8 99.6 100.4 102.8 104.8 Wadi Al Kabir Housing P127 100.5 100.5 105.0 105.1 101.0 100.5 105.5 105.1 101.0 100.5 105.5 105.1 101.0 100.5 105.5 105.1 Wadi Al Kabir Workshop-A P126 102.8 104.6 104.3 104.9 102.9 104.6 103.3 104.9 102.9 104.6 103.3 104.9 102.9 104.6 103.3 104.9 Wadi Al Kabir Workshop-B P126 102.8 104.6 103.8 104.8 102.9 104.6 103.3 104.8 102.9 104.6 103.3 104.8 102.9 104.6 103.3 104.8 Walja-A P130 100.6 100.5 102.6 104.6 99.9 100.5 102.5 104.6 99.9 100.5 102.5 104.6 99.9 100.5 102.5 104.6 Walja-B P130 100.6 100.5 102.6 104.6 99.9 100.5 102.5 104.6 99.9 100.5 102.5 104.6 99.9 100.5 102.5 104.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 59 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Ali Shihani-A P125 25.0 20.0 20.5 13.8 20.7 13.8 21.4 13.9 21.4 13.9 Ali Shihani-B P125 25.0 20.0 20.5 13.8 20.7 13.8 21.4 13.9 21.4 13.9 M.B.D. South-A P075 25.0 20.0 18.5 14.2 18.7 14.2 19.3 14.3 19.3 14.3 M.B.D. South-B P075 25.0 20.0 18.5 14.2 18.7 14.2 19.3 14.3 19.2 14.3 Majlis Oman-A P066 25.0 20.0 7.9 11.1 8.0 11.1 8.1 11.2 8.1 11.2 Majlis Oman-B P066 25.0 20.0 7.9 11.1 8.0 11.1 8.1 11.2 8.1 11.2 Qasr al Alam-A P090 25.0 18.4 8.6 12.6 8.6 12.6 8.7 12.6 8.7 12.6 Qasr al Alam-B P090 25.0 18.4 8.6 12.6 8.6 12.6 8.7 12.6 8.7 12.6 Sidab-A P119 25.0 18.4 9.8 7.6 9.9 7.6 10.0 7.6 10.0 7.6 Sidab-B P119 25.0 18.4 9.8 7.6 9.9 7.6 10.0 7.6 10.0 7.6 Wadi Al Kabir Housing P127 25.0 18.4 15.3 4.4 15.4 4.4 15.8 4.4 15.8 4.4 Wadi Al Kabir Workshop-A P126 25.0 18.4 15.5 4.6 15.6 4.6 15.6 4.6 15.4 4.6 Wadi Al Kabir Workshop-B P126 25.0 18.4 15.5 4.4 15.6 4.4 15.6 4.4 15.4 4.4 Walja-A P130 25.0 20.0 17.0 13.8 17.2 13.8 17.7 13.9 17.7 13.9 Walja-B P130 25.0 20.0 16.5 13.8 16.6 13.8 17.1 13.9 17.1 13.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 60 Wadi Al Kabir[G19] - B GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Old Airport P107 20 14.1 8.5 16.5 83% 14.1 8.4 16.4 82% 14.1 8.4 16.4 82% 14.1 8.4 16.4 82% Ruwi Market P076 20 13.8 7.2 15.6 78% 13.8 7.1 15.5 78% 13.8 7.1 15.5 78% 13.8 7.1 15.5 78% Ruwi Valley P174 20 17.9 8.3 19.7 99% 17.9 8.2 19.7 98% 17.9 8.2 19.7 98% 17.9 8.2 19.7 98% Wadi Al Kabir Height P128 20 14.4 6.0 15.6 78% 14.4 4.7 15.2 76% 14.4 4.7 15.2 76% 14.4 4.7 15.2 76% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Old Airport P107 20 2.3 1.8 2.9 15% 2.3 1.8 2.9 14% 2.3 1.8 2.9 14% 2.3 1.8 2.9 14% Ruwi Market P076 20 1.8 1.6 2.4 12% 1.8 1.6 2.4 12% 1.8 1.6 2.4 12% 1.8 1.6 2.4 12% Ruwi Valley P174 20 2.8 2.4 3.7 19% 2.8 2.4 3.7 18% 2.8 2.4 3.7 18% 2.8 2.4 3.7 18% Wadi Al Kabir Height P128 20 2.3 1.6 2.8 14% 2.2 1.6 2.7 14% 2.2 1.6 2.7 14% 2.2 1.6 2.7 14% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Old Airport-F1-P107 22.0 8.3 37.4 8.3 37.4 8.3 37.4 8.3 37.4 Old Airport-F2-P107 22.0 8.4 38.2 8.4 38.2 8.4 38.2 8.4 38.2 Ruwi Market-F1-P076 22.0 7.9 35.7 7.9 35.7 7.9 35.7 7.9 35.7 Ruwi Market-F2-P076 22.0 7.9 35.9 7.9 35.9 7.9 35.9 7.9 35.9 Ruwi Valley-F1-P174 22.0 10.1 45.7 10.1 45.7 10.1 45.7 10.1 45.7 Ruwi Valley-F2-P174 22.0 10.2 46.1 10.2 46.1 10.2 46.1 10.2 46.1 Wadi Al Kabir Height 1-F1-P128 22.0 7.9 35.7 7.6 34.5 7.6 34.5 7.6 34.5 Wadi Al Kabir Height 1-F2-P128 22.0 7.9 35.7 7.6 34.5 7.6 34.5 7.6 34.5 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Old Airport-A P107 100.7 100.5 102.3 104.5 100.8 100.5 102.4 104.5 100.8 100.5 102.4 104.5 100.8 100.5 102.4 104.5 Old Airport-B P107 100.7 100.5 102.3 104.5 100.8 100.5 102.4 104.5 100.8 100.5 102.4 104.5 100.8 100.5 102.4 104.5 Ruwi Market-A P076 100.8 100.5 102.8 104.6 100.9 100.5 102.9 104.6 100.9 100.5 102.9 104.6 100.9 100.5 102.9 104.6 Ruwi Market-B P076 100.8 100.5 102.8 104.6 100.9 100.5 102.9 104.6 100.9 100.5 102.9 104.6 100.9 100.5 102.9 104.6 Ruwi Valley-A P174 100.9 100.5 102.5 104.3 101.0 100.6 102.6 104.3 101.0 100.6 102.6 104.3 101.0 100.6 102.6 104.3 Ruwi Valley-B P174 100.9 100.5 102.5 104.3 101.0 100.5 102.6 104.3 101.0 100.5 102.6 104.3 101.0 100.5 102.6 104.3 Wadi Al Kabir Height 1-A P128 100.6 100.5 102.8 104.5 100.7 100.5 103.4 104.5 100.7 100.5 103.4 104.5 100.7 100.5 103.4 104.5 Wadi Al Kabir Height 1-B P128 100.6 100.5 102.8 104.5 100.7 100.5 103.4 104.5 100.7 100.5 103.4 104.5 100.7 100.5 103.4 104.5 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Old Airport-A P107 25.0 18.4 17.3 14.2 17.5 14.3 18.0 14.4 18.0 14.4 Old Airport-B P107 25.0 18.4 17.3 14.2 17.5 14.3 18.0 14.4 18.0 14.4 Ruwi Market-A P076 25.0 18.4 18.7 14.2 18.9 14.2 19.5 14.3 19.5 14.3 Ruwi Market-B P076 25.0 18.4 18.7 14.2 18.9 14.2 19.5 14.3 19.5 14.3 Ruwi Valley-A P174 25.0 18.4 21.7 15.0 22.0 15.0 22.9 15.2 22.8 15.2 Ruwi Valley-B P174 25.0 18.4 21.6 15.0 21.9 15.0 22.8 15.2 22.7 15.2 Wadi Al Kabir Height 1-A P128 25.0 20.0 14.8 13.6 14.9 13.6 15.3 13.7 15.3 13.7 Wadi Al Kabir Height 1-B P128 25.0 20.0 14.8 13.6 15.0 13.6 15.4 13.7 15.3 13.7

MEDC Distribution System Capability Statement [2021-2023]-V2.0 61 Wadi Adai[G22] GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Bustan Palace P017 16 4.8 1.9 5.1 32% 4.8 1.9 5.1 32% 4.8 1.9 5.1 32% 4.8 1.9 5.1 32% Al Hamryah P035 20 9.2 4.4 10.2 51% 9.2 3.0 9.7 48% 9.2 3.0 9.7 48% 9.2 3.0 9.7 48% Al Mahaj P136 6 5.3 2.1 5.7 95% 5.9 2.3 6.3 105% 4.3 1.7 4.6 77% 4.6 1.8 5.0 83% Amerat 1 P005 16 14.7 5.3 15.6 98% 11.8 3.9 12.5 78% 13.1 4.3 13.8 86% 14.1 4.6 14.8 93% Khoula Hospital P132 40 17.9 6.0 18.9 47% 17.9 5.9 18.8 47% 17.9 5.9 18.8 47% 17.9 5.9 18.8 47% Qantab P089 1TX Standby PSS Wadi Adai P175 20 16.3 7.7 18.0 90% 16.3 7.9 18.1 91% 16.3 7.9 18.1 91% 16.3 7.9 18.1 91% Wattaya P131 20 15.3 6.0 16.4 82% 15.3 5.0 16.1 80% 15.3 5.0 16.1 80% 15.3 5.0 16.1 80% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Bustan Palace P017 16 0.3 0.2 0.4 2% 0.8 0.4 0.9 6% 0.8 0.4 0.9 6% 0.8 0.4 0.9 6% Al Hamryah P035 20 0.9 0.5 1.0 5% 0.8 0.5 0.9 5% 0.8 0.5 0.9 5% 0.8 0.5 0.9 5% Al Mahaj P136 6 0.9 0.4 1.0 17% 1.0 0.5 1.2 19% 1.2 0.6 1.3 21% 1.2 0.6 1.4 23% Amerat 1 P005 16 2.3 0.9 2.5 16% 2.6 1.0 2.7 17% 2.8 1.1 3.0 19% 3.0 1.2 3.3 20% Khoula Hospital P132 40 4.0 2.1 4.5 11% 4.0 2.0 4.5 11% 4.0 2.0 4.5 11% 4.0 2.0 4.5 11% Qantab P089 1TX Standby PSS Wadi Adai P175 20 2.7 2.1 3.4 17% 2.7 2.1 3.4 17% 2.7 2.1 3.4 17% 2.7 2.1 3.4 17% Wattaya P131 20 3.0 0.4 3.0 15% 2.9 0.4 2.9 15% 2.9 0.4 2.9 15% 2.9 0.4 2.9 15% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Bustan Palace-F1-P017 22.0 2.5 10.5 2.5 10.5 2.5 10.5 2.5 10.5 Al Bustan Palace-F2-P017 22.0 2.5 10.6 2.5 10.5 2.5 10.5 2.5 10.5 Al Hamryah-F1-P035 15.4 5.2 33.8 4.9 31.8 4.9 31.8 4.9 31.8 Al Hamryah-F2-P035 15.4 5.2 33.8 4.9 31.9 4.9 31.9 4.9 31.9 Al Mahaj-F1-P136 22.0 5.7 26.0 6.4 29.0 4.6 20.9 4.9 22.4 Amerat 1-F1-P005 15.4 8.0 52.2 6.3 41.1 7.0 45.7 7.6 49.3 Amerat 1-F2-P005 15.4 8.0 52.0 6.3 41.0 7.0 45.6 7.6 49.2 Khoula Hospital-F1-P132 22.0 6.5 29.5 6.3 28.5 6.3 28.5 6.3 28.5 Khoula Hospital-F2-P132 22.0 6.5 29.3 6.3 28.4 6.3 28.4 6.3 28.4 Khoula Hospital-F3-P132 22.0 5.9 26.8 6.3 28.5 6.3 28.5 6.3 28.5 Wadi Adai-F1-P175 22.0 9.3 42.3 9.3 42.3 9.3 42.3 9.3 42.3 Wadi Adai-F2-P175 22.0 9.3 42.3 9.3 42.3 9.3 42.3 9.3 42.3 Wattaya-F1-P131 22.0 8.4 38.0 8.2 37.1 8.2 37.1 8.2 37.1 Wattaya-F2-P131 22.0 8.3 37.7 8.1 36.8 8.1 36.8 8.1 36.8

MEDC Distribution System Capability Statement [2021-2023]-V2.0 62 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Bustan Palace-A P017 100.3 100.8 104.1 105.4 100.6 100.7 104.4 105.2 100.6 100.7 104.5 105.1 100.6 100.7 104.4 105.1 Al Bustan Palace-B P017 100.3 100.8 104.1 105.4 100.6 100.7 104.4 105.2 100.6 100.7 104.5 105.1 100.6 100.7 104.4 105.1 Al Hamryah-A P035 100.5 100.8 103.4 105.2 100.8 100.8 104.3 105.2 100.9 100.7 104.3 105.2 100.8 100.7 104.2 105.1 Al Hamryah-B P035 100.5 100.8 103.4 105.2 100.8 100.8 104.3 105.2 100.9 100.7 104.3 105.2 100.8 100.7 104.2 105.1 Al Mahaj-A P136 99.2 100.6 102.3 104.6 99.3 100.5 102.2 104.5 99.9 100.5 103.3 104.3 99.7 100.5 103.0 104.6 Al Mahaj-B P136 99.2 100.6 102.3 104.6 99.3 100.5 102.2 104.5 99.9 100.5 103.3 104.3 99.7 100.5 103.0 104.6 Amerat 1-A P005 99.0 100.6 101.3 104.8 99.8 100.5 102.7 104.7 99.6 100.5 102.4 104.6 99.4 100.4 102.0 104.5 Amerat 1-B P005 99.0 100.6 101.3 104.8 99.8 100.5 102.7 104.7 99.6 100.5 102.4 104.6 99.5 100.4 102.0 104.5 Khoula Hospital-A P132 100.7 100.8 103.7 104.8 101.0 100.7 104.1 104.8 101.0 100.7 104.1 104.8 101.0 100.7 104.0 104.8 Khoula Hospital-B P132 100.7 100.8 103.7 104.8 101.0 100.7 104.1 104.8 101.0 100.7 104.1 104.8 101.0 100.7 104.0 104.8 Khoula Hospital-C P132 100.7 100.8 103.8 104.9 101.0 100.7 104.1 104.8 101.0 100.7 104.1 104.8 101.0 100.7 104.0 104.8 Qantab P089 100.3 100.8 104.9 105.4 100.7 100.7 105.2 105.3 100.7 100.7 105.2 105.3 100.6 100.7 105.2 105.3 Wadi Adai-A P175 100.9 100.8 102.4 104.7 101.2 100.8 102.8 104.6 101.2 100.8 102.8 104.6 101.1 100.8 102.7 104.6 Wadi Adai-B P175 100.9 100.8 102.4 104.7 101.2 100.8 102.8 104.6 101.2 100.8 102.8 104.6 101.1 100.8 102.7 104.6 Wattaya-A P131 100.7 100.8 102.9 105.2 101.0 100.8 103.6 105.2 101.1 100.8 103.7 105.2 101.0 100.7 103.6 105.1 Wattaya-B P131 100.7 100.8 102.9 105.2 101.0 100.8 103.6 105.2 101.1 100.8 103.7 105.2 101.0 100.7 103.6 105.1 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Bustan Palace-A P017 25.0 18.4 5.2 9.3 5.2 9.3 5.2 9.4 5.2 9.4 Al Bustan Palace-B P017 25.0 18.4 5.2 9.3 5.2 9.3 5.2 9.4 5.2 9.4 Al Hamryah-A P035 25.0 18.4 12.5 12.9 12.6 12.9 12.9 13.0 12.9 13.0 Al Hamryah-B P035 25.0 18.4 12.6 12.9 12.7 12.9 13.0 13.0 13.0 13.0 Al Mahaj-A P136 25.0 16.0 4.0 5.4 4.0 5.5 4.0 5.4 4.0 5.4 Al Mahaj-B P136 25.0 16.0 4.0 5.4 4.0 5.5 4.0 5.4 4.0 5.4 Amerat 1-A P005 25.0 18.4 6.6 11.1 6.5 10.9 6.6 11.1 6.6 11.2 Amerat 1-B P005 25.0 18.4 6.6 11.1 6.6 10.9 6.7 11.1 6.7 11.2 Khoula Hospital-A P132 25.0 25.0 16.0 13.5 16.1 13.5 16.6 13.6 16.6 13.6 Khoula Hospital-B P132 25.0 25.0 16.0 13.5 16.1 13.5 16.6 13.6 16.6 13.6 Khoula Hospital-C P132 25.0 25.0 16.6 7.5 16.7 7.5 17.3 7.6 17.3 7.6 Qantab P089 25.0 16.0 4.5 3.5 4.5 3.5 4.5 3.5 4.5 3.5 Wadi Adai-A P175 25.0 18.4 22.5 14.3 22.8 14.4 23.8 14.5 23.8 14.5 Wadi Adai-B P175 25.0 18.4 22.6 14.3 22.8 14.4 23.9 14.5 23.9 14.5 Wattaya-A P131 25.0 20.0 18.5 14.0 18.7 14.0 19.4 14.1 19.4 14.1 Wattaya-B P131 25.0 20.0 18.5 14.0 18.7 14.0 19.3 14.1 19.4 14.1

MEDC Distribution System Capability Statement [2021-2023]-V2.0 63 Jahloot[G03] GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Atkiya P182 1TX 2.2 0.9 2.3 - 2.4 1.0 2.6 - 2.7 1.1 2.9 - 2.9 1.1 3.1 - Al Hajir P031 20 8.7 4.1 9.6 48% 9.6 3.2 10.2 51% 10.7 3.5 11.2 56% 11.5 3.8 12.1 60% Al Masarat P068 10 4.0 2.0 4.5 45% 4.0 1.3 4.2 42% 4.0 1.3 4.2 42% 4.0 1.3 4.2 42% Arqi P121 1TX 2.0 0.8 2.1 - 2.2 0.9 2.3 - 2.4 0.9 2.5 - 2.5 1.0 2.7 - Barr Al Jissah P044 20 6.4 2.5 6.9 35% 6.4 2.1 6.7 34% 6.4 2.1 6.7 34% 6.4 2.1 6.7 34% Debah P114 1TX 0.1 0.0 0.1 - 0.1 0.0 0.1 - 0.1 0.0 0.1 - 0.1 0.0 0.1 - Hussan Yiti P169 6 1.4 0.5 1.5 25% 1.4 0.5 1.5 25% 1.4 0.5 1.5 25% 1.4 0.5 1.5 25% Jahloot P040 6 5.4 2.1 5.8 96% 5.9 2.3 6.3 106% 6.5 2.6 7.0 116% 6.9 2.7 7.4 124% ROP Al Saleel P162 6 1.4 0.6 1.6 26% 1.4 0.6 1.6 26% 1.4 0.6 1.6 26% 1.4 0.6 1.6 26% Sawaqim 1 P112 6 4.5 1.8 4.8 80% 4.9 1.9 5.2 87% 5.1 2.0 5.5 91% 5.1 2.0 5.5 92% Sawaqim 2 P113 1TX 0.6 0.2 0.6 - 0.6 0.2 0.7 - 0.6 0.3 0.7 - 0.6 0.3 0.7 - Siya P120 6 4.1 1.6 4.4 74% 4.5 1.8 4.9 81% 5.0 2.0 5.3 89% 5.3 2.1 5.7 95% Tunis Heium P137 1TX 5.7 2.3 6.2 - 6.3 2.5 6.8 - 7.0 2.8 7.5 - 7.5 3.0 8.1 - Wadi Al Mayh P129 1TX 0.7 0.3 0.8 - 0.8 0.3 0.9 - 0.9 0.4 1.0 - 1.0 0.4 1.0 - Water Pumping P193 6 2.5 1.0 2.7 44% 2.5 1.0 2.7 44% 2.5 1.0 2.7 44% 2.5 1.0 2.7 44% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Atkiya P182 1TX 0.4 0.2 0.4 - 0.4 0.2 0.5 - 0.5 0.2 0.5 - 0.5 0.2 0.6 - Al Hajir P031 20 1.3 0.3 1.3 7% 1.3 0.3 1.4 7% 1.5 0.4 1.5 8% 1.6 0.4 1.6 8% Al Masarat P068 10 0.8 0.4 0.9 9% 0.7 0.4 0.8 8% 0.7 0.4 0.8 8% 0.7 0.4 0.8 8% Arqi P121 1TX 0.3 0.2 0.4 - 0.4 0.2 0.4 - 0.4 0.2 0.5 - 0.4 0.2 0.5 - Barr Al Jissah P044 20 1.3 0.4 1.4 7% 1.3 0.4 1.4 7% 1.3 0.4 1.4 7% 1.3 0.4 1.4 7% Debah P114 1TX 0.0 0.0 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 - 0.0 0.0 0.0 - Hussan Yiti P169 6 0.2 0.1 0.3 4% 0.2 0.1 0.3 5% 0.2 0.1 0.3 5% 0.2 0.1 0.3 5% Jahloot P040 6 0.9 0.5 1.0 17% 1.0 0.5 1.2 19% 1.1 0.6 1.3 21% 1.2 0.6 1.4 23% ROP Al Saleel P162 6 0.3 0.1 0.3 5% 0.3 0.1 0.3 5% 0.3 0.1 0.3 5% 0.3 0.1 0.3 5% Sawaqim 1 P112 6 1.1 0.5 1.3 21% 0.9 0.4 1.0 16% 0.9 0.4 1.0 17% 0.9 0.4 1.0 17% Sawaqim 2 P113 1TX 0.1 0.0 0.1 - 0.1 0.1 0.1 - 0.1 0.1 0.1 - 0.1 0.1 0.1 - Siya P120 6 0.7 0.3 0.8 13% 0.8 0.4 0.9 15% 0.9 0.4 1.0 16% 0.9 0.5 1.0 17% Tunis Heium P137 1TX 1.0 0.5 1.1 - 1.1 0.5 1.2 - 1.2 0.6 1.4 - 1.3 0.6 1.5 - Wadi Al Mayh P129 1TX 0.1 0.1 0.1 - 0.1 0.1 0.2 - 0.2 0.1 0.2 - 0.2 0.1 0.2 - Water Pumping P193 6 0.1 0.0 0.1 1% 0.4 0.2 0.5 8% 0.4 0.2 0.5 8% 0.4 0.2 0.5 8% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Hajir-F1-P031 (P031+P137) 22.0 10.9 49.3 11.8 53.4 13.1 59.6 14.2 64.5 Al Hajir-F2-P031 (P031+P182) 22.0 8.1 36.8 8.7 39.4 9.7 44.0 10.5 47.5 Al Masarat-F1-P068 22.0 2.3 10.5 2.2 9.8 2.2 9.8 2.2 9.8 Al Masarat-F2-P068 22.0 2.2 9.9 2.0 9.3 2.0 9.3 2.0 9.3 Bar Al Jissah-F1-P044 22.0 4.3 19.7 4.2 19.2 4.2 19.2 4.2 19.2 Bar Al Jissah-F2-P044 22.0 4.3 19.6 4.2 19.2 4.2 19.2 4.2 19.2 Debha-F1-P114-(Shehbari fdr) 22.0 0.1 0.6 0.1 0.6 0.1 0.6 0.1 0.6 Mazra Fdr - Jahloot (P040) + Siya (P120) + 22.0 12.8 57.8 14.1 63.7 15.5 70.4 16.6 75.3 Arqi (P121) Sawaqim 1-F1-P112-OD (Quriyat fdr1) 22.0 2.0 9.3 3.4 15.3 3.5 15.9 3.5 16.1 Sawaqim 2-F1-P112-OD (Quriyat 2 fdr) 22.0 4.0 18.1 3.2 14.6 3.4 15.3 3.4 15.5 Shehabari Feeder (Feeding ROP Saleel Tx 22.0 3.5 16.1 3.4 15.6 3.4 15.6 3.4 15.6 2+Waterpump) Wadi Al Mayh-F-P129-OD (Al Nahdha Fdr 22.0 0.8 3.4 0.8 3.8 0.9 4.2 1.0 4.6 1)

MEDC Distribution System Capability Statement [2021-2023]-V2.0 64 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Atkiya P182 97.6 100.7 100.8 105.0 97.8 100.6 100.9 104.9 97.2 100.5 100.1 104.8 96.7 100.4 99.5 104.7 Al Hajir-A P031 97.2 100.6 102.1 101.7 97.4 100.5 102.6 101.6 96.7 100.4 101.8 101.5 96.2 100.3 101.2 101.4 Al Hajir-B P031 97.7 100.7 102.1 101.7 98.0 100.6 102.6 101.6 97.4 100.5 101.8 101.5 96.9 100.5 101.2 101.4 Al Masarat-A P068 100.8 101.0 102.7 102.0 101.0 101.0 101.5 102.0 100.8 100.9 103.0 101.9 100.6 100.9 102.8 101.9 Al Masarat-B P068 100.8 101.0 102.7 102.0 101.0 101.0 101.5 102.0 100.8 100.9 103.0 101.9 100.6 100.9 102.8 101.9 Arqi P121 97.4 100.5 102.2 104.6 97.3 100.4 101.8 104.4 96.7 100.3 100.9 104.3 96.2 100.2 100.1 104.2 Bar Al Jissah-A P044 97.4 100.5 102.7 104.9 97.9 100.4 101.6 104.9 97.7 100.4 101.3 104.8 97.5 100.4 102.9 104.8 Bar Al Jissah-B P044 97.5 100.5 102.7 104.9 97.9 100.4 101.6 104.9 97.7 100.4 101.3 104.8 97.6 100.4 102.9 104.8 Debha P114 100.8 101.1 100.8 101.1 101.0 101.0 101.0 101.0 100.8 101.0 100.8 101.0 100.7 101.0 100.6 101.0 Hussan Yitti-A P169 98.0 100.6 102.1 102.5 98.4 100.5 102.5 102.5 98.2 100.5 102.3 102.4 98.0 100.5 102.1 102.4 Hussan Yitti-B P169 98.0 100.6 102.1 102.5 98.4 100.5 102.5 102.5 98.2 100.5 102.3 102.4 98.0 100.5 102.1 102.4 Jahloot-A P040 99.3 100.8 101.9 105.0 99.4 100.7 102.4 105.0 99.0 100.6 101.8 104.9 98.7 100.6 101.3 104.8 Jahloot-B P040 99.3 100.8 100.3 105.2 99.4 100.7 102.3 104.9 99.0 100.6 101.7 104.9 98.7 100.6 101.3 104.8 ROP Al Saleel-A P162 100.5 101.0 102.1 102.9 100.4 100.9 102.1 102.8 100.2 100.9 101.8 102.8 100.0 100.9 101.6 102.8 ROP Al Saleel-B P162 100.2 101.0 101.7 102.9 100.4 100.9 102.1 102.8 100.2 100.9 101.8 102.8 100.1 100.9 101.7 102.8 Sawaqim 1-A P112 100.0 100.8 99.2 100.6 99.5 100.7 98.1 100.5 99.2 100.7 97.8 100.4 99.0 100.7 97.6 100.4 Sawaqim 1-B P112 99.0 100.7 101.7 104.8 99.6 100.9 102.8 105.2 99.4 100.9 102.5 105.2 99.2 100.8 102.2 105.1 Sawaqim 2 P113 99.0 100.8 100.7 102.7 99.6 100.9 101.3 102.9 99.3 100.9 101.0 102.8 99.1 100.9 100.8 102.8 Siya 1-A P120 97.4 100.5 100.8 104.8 97.3 100.4 100.5 104.7 96.7 100.3 99.7 104.6 96.2 100.2 99.1 104.5 Siya 1-B P120 97.4 100.5 100.8 104.8 97.3 100.4 100.5 104.7 96.7 100.3 99.7 104.6 96.2 100.2 99.1 104.5 Tunis P137 97.6 100.6 101.5 104.6 97.8 100.5 101.2 104.4 97.1 100.4 103.0 104.2 96.6 100.4 102.1 104.1 Wadi Al Mayh P129 100.4 101.0 101.7 102.9 100.6 100.9 101.9 102.8 100.4 100.9 101.5 102.7 100.2 100.9 101.2 102.7 Water Pumping-A P193 98.3 101.0 - - 98.6 100.6 - - 98.3 100.6 - - 98.2 100.6 - - Water Pumping-B P193 98.3 101.0 - - 98.6 100.6 - - 98.3 100.6 - - 98.2 100.6 - - Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Atkiya P182 25.0 16.0 3.5 3.4 3.5 3.4 3.5 3.4 3.6 3.5 Al Hajir-A P031 25.0 25.0 4.1 8.8 4.1 8.9 4.2 9.0 4.2 9.1 Al Hajir-B P031 25.0 25.0 4.2 8.8 4.2 8.9 4.3 9.0 4.3 9.1 Al Masarat-A P068 25.0 18.4 17.6 10.8 17.8 10.8 18.0 10.8 18.1 10.8 Al Masarat-B P068 25.0 18.4 17.7 10.8 17.9 10.8 18.1 10.8 18.2 10.8 Arqi P121 25.0 16.0 2.4 2.1 2.4 2.1 2.5 2.1 2.5 2.1 Bar Al Jissah-A P044 25.0 18.4 2.5 5.9 2.5 5.9 2.5 5.9 2.5 5.9 Bar Al Jissah-B P044 25.0 18.4 2.5 5.9 2.5 5.9 2.5 5.9 2.5 5.9 Debha P114 25.0 16.0 1.5 2.6 1.5 2.6 1.5 2.6 1.5 2.6 Hussan Yitti-A P169 25.0 16.0 2.9 5.0 2.9 5.0 2.9 5.0 2.9 5.0 Hussan Yitti-B P169 25.0 16.0 2.9 5.0 2.9 5.0 2.9 5.0 2.9 5.0 Jahloot-A P040 25.0 16.0 7.9 4.3 7.9 4.3 8.0 4.3 8.0 4.4 Jahloot-B P040 25.0 16.0 7.9 4.1 7.9 4.2 8.0 4.2 8.0 4.3 ROP Al Saleel-A P162 26.3 26.3 5.2 3.8 5.3 3.8 5.3 3.8 5.3 3.8 ROP Al Saleel-B P162 26.3 26.3 5.2 3.8 5.2 3.8 5.3 3.8 5.3 3.8 Sawaqim 1-A P112 25.0 12.5 2.3 3.0 2.3 3.1 2.3 3.1 2.3 3.1 Sawaqim 1-B P112 25.0 12.5 2.6 3.1 2.6 3.0 2.6 3.0 2.6 3.0 Sawaqim 2 P113 25.0 12.5 2.1 2.7 2.1 2.7 2.1 2.7 2.1 2.7 Siya 1-A P120 25.0 16.0 3.2 4.9 3.2 4.9 3.2 4.9 3.2 5.0 Siya 1-B P120 25.0 16.0 3.2 4.9 3.2 4.9 3.2 4.9 3.2 5.0 Tunis P137 25.0 16.0 4.9 4.0 4.9 4.1 5.0 4.1 5.0 4.2 Wadi Al Mayh P129 25.0 16.0 2.3 2.0 2.3 2.0 2.3 2.0 2.3 2.0 Water Pumping-A P193 25.0 - 1.5 - 1.5 - 1.5 - 1.5 - Water Pumping-B P193 25.0 - 1.5 - 1.5 - 1.5 - 1.5 -

MEDC Distribution System Capability Statement [2021-2023]-V2.0 65 Yiti[G08] GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khairan P045 3 2.8 1.1 3.0 99% 2.9 1.2 3.1 104% 3.1 1.2 3.3 111% 3.2 1.3 3.4 114% Al Salam Yiti P135 1TX 1.1 0.4 1.2 - 1.2 0.5 1.3 - 1.2 0.5 1.3 - 1.3 0.5 1.4 - Jabal Al Sifah P159 40 3.8 1.2 4.0 10% 3.8 1.2 4.0 10% 3.8 1.2 4.0 10% 3.8 1.2 4.0 10% Saraya Bander P145 40 7.8 2.4 8.2 21% 7.8 2.3 8.1 20% 7.8 2.3 8.1 20% 7.8 2.3 8.1 20% Yenket P133 1 1.1 0.4 1.2 118% 1.2 0.5 1.2 125% 1.2 0.5 1.3 132% 1.3 0.5 1.4 136% Yiti P134 3 2.0 0.8 2.1 71% 2.1 0.8 2.3 75% 2.2 0.9 2.4 79% 2.3 0.9 2.5 82% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khairan P045 3 0.5 0.2 0.5 18% 0.5 0.3 0.6 19% 0.5 0.3 0.6 20% 0.6 0.3 0.6 21% Al Salam Yiti P135 1TX 0.2 0.1 0.2 - 0.2 0.1 0.2 - 0.2 0.1 0.2 - 0.2 0.1 0.3 - Jabal Al Sifah P159 40 0.9 0.2 0.9 2% 0.9 0.2 0.9 2% 0.9 0.2 0.9 2% 0.9 0.2 0.9 2% Saraya Bander P145 40 1.7 0.8 1.9 5% 1.7 0.8 1.9 5% 1.7 0.8 1.9 5% 1.7 0.8 1.9 5% Yenket P133 1 0.2 0.1 0.2 21% 0.2 0.1 0.2 23% 0.2 0.1 0.2 24% 0.2 0.1 0.2 25% Yiti P134 3 0.3 0.2 0.4 13% 0.4 0.2 0.4 14% 0.4 0.2 0.4 15% 0.4 0.2 0.4 15% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Jabal Al Sifah-F1-P159 22.0 1.2 5.0 1.2 5.0 1.2 5.0 1.2 5.0 Jabal Al Sifah-F2-P159 22.0 1.2 5.0 1.2 5.0 1.2 5.0 1.2 5.0 Jabal Al Sifah-F3-P159 22.0 1.6 6.5 1.6 6.5 1.6 6.5 1.6 6.5 Khayran Feeder for P133 & P045 22.0 4.2 17.4 4.4 18.3 4.7 19.4 4.8 20.1 Saraya Bander-F1-P145 22.0 1.3 5.6 1.3 5.6 1.3 5.6 1.3 5.6 Saraya Bander-F2-P145 22.0 1.3 5.6 1.3 5.6 1.3 5.6 1.3 5.6 Saraya Bander-F3-P145 22.0 5.5 22.9 5.5 22.9 5.5 22.9 5.5 22.9 Yitti Feeder for Yiti (P134) & Al Salam Yiti 22.0 3.3 13.9 3.5 14.8 3.8 15.6 3.9 16.1 (P135) Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Khairan-A P045 100.2 101.0 103.8 105.4 100.1 101.0 103.7 105.4 100.1 101.0 103.5 105.4 100.0 101.0 103.5 105.4 Al Khairan-B P045 100.2 101.0 103.8 105.4 100.1 101.0 103.7 105.4 100.1 101.0 103.5 105.4 100.0 101.0 103.5 105.4 Al Salam Yiti P135 100.5 101.1 104.5 105.6 100.5 101.1 104.5 105.6 100.5 101.1 104.4 105.6 100.5 101.1 104.4 105.6 Jabal Al Sifah-A P159 100.3 101.1 104.6 105.7 100.3 101.1 104.5 105.7 100.2 101.1 104.5 105.7 100.2 101.1 104.5 105.7 Jabal Al Sifah-B P159 100.3 101.1 104.3 105.6 100.3 101.1 104.3 105.6 100.2 101.1 104.3 105.6 100.2 101.1 104.3 105.6 Jabal Al Sifah-C P159 100.1 101.1 - - 100.1 101.1 - - 100.1 101.1 - - 100.1 101.1 - - Saraya Bander-A P145 100.5 101.1 104.7 105.7 100.4 101.1 104.7 105.7 100.4 101.1 104.7 105.7 100.4 101.1 104.7 105.7 Saraya Bander-B P145 100.5 101.1 102.8 105.0 100.4 101.1 102.8 105.0 100.4 101.1 102.8 105.0 100.4 101.1 102.8 105.0 Saraya Bander-C P145 99.5 100.8 - - 99.4 100.8 - - 99.4 100.8 - - 99.4 100.8 - - Yanket-A P133 100.4 101.1 105.0 105.7 100.4 101.1 103.8 105.4 100.3 101.1 103.7 105.4 100.3 101.1 103.6 105.4 Yenkit-B P133 100.4 101.1 104.1 105.5 100.4 101.1 104.5 105.6 100.3 101.1 104.4 105.6 100.3 101.1 104.4 105.6 Yiti-A P134 100.6 101.1 104.2 105.5 100.6 101.1 104.1 105.5 100.6 101.1 104.0 105.5 100.6 101.1 104.0 105.5 Yiti-B P134 100.6 101.1 104.2 105.5 100.6 101.1 104.1 105.5 100.6 101.1 104.0 105.5 100.6 101.1 104.0 105.5

MEDC Distribution System Capability Statement [2021-2023]-V2.0 66 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Khairan-A P045 25.0 12.5 5.7 5.3 5.7 5.3 5.7 5.3 5.7 5.4 Al Khairan-B P045 25.0 12.5 5.6 5.3 5.7 5.3 5.7 5.3 5.7 5.4 Al Salam Yiti P135 25.0 12.5 6.9 4.1 6.9 4.1 6.9 4.1 6.9 4.1 Jabal Al Sifah-A P159 25.0 25.0 3.2 7.2 3.2 7.2 3.2 7.2 3.2 7.2 Jabal Al Sifah-B P159 25.0 25.0 3.2 3.9 3.2 3.9 3.2 3.9 3.2 3.9 Jabal Al Sifah-C P159 25.0 - 2.5 - 2.5 - 2.5 - 2.5 - Saraya Bander-A P145 25.0 25.0 4.7 8.9 4.8 8.9 4.8 8.9 4.8 8.9 Saraya Bander-B P145 25.0 25.0 4.7 5.2 4.8 5.2 4.8 5.2 4.8 5.3 Saraya Bander-C P145 25.0 - 4.2 - 4.2 - 4.2 - 4.2 - Yanket-A P133 25.0 12.5 8.5 1.1 8.5 1.1 8.5 1.1 8.6 1.1 Yenkit-B P133 25.0 12.5 8.5 2.5 8.5 2.5 8.5 2.5 8.6 2.5 Yiti-A P134 25.0 12.5 11.5 4.5 11.6 4.5 11.6 4.5 11.8 4.5 Yiti-B P134 25.0 12.5 11.5 4.5 11.6 4.5 11.6 4.5 11.8 4.5

MEDC Distribution System Capability Statement [2021-2023]-V2.0 67 Quriyat[G05] GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Mazara P074 6 2.9 1.1 3.1 52% 3.0 1.2 3.2 53% 3.0 1.2 3.2 53% 3.0 1.2 3.2 53% Al Shahbari P092 20 16.8 6.1 17.9 90% 17.4 5.7 18.4 92% 17.4 5.7 18.4 92% 18.1 5.9 19.0 95% Dhabab P019 6 4.0 1.6 4.3 72% 4.1 1.6 4.4 74% 4.1 1.6 4.4 74% 4.1 1.6 4.4 74% Dhagmar 1 P021 18 4.6 1.8 4.9 27% 4.7 1.9 5.0 28% 4.7 1.9 5.0 28% 4.7 1.9 5.0 28% Hail Al Ghaf P036 6 4.7 1.9 5.1 84% 4.9 1.9 5.2 87% 4.9 1.9 5.2 87% 4.9 1.9 5.2 87% Quriyat P091 20 20.3 4.1 20.7 104% 21.0 4.3 21.5 107% 21.0 4.3 21.5 107% 21.8 4.4 22.3 111% RoyalCamp P170 1TX Standby PSS Street Light P020 1TX 2.9 1.1 3.1 - 2.9 1.1 3.1 - 2.9 1.1 3.1 - 2.9 1.1 3.1 - Wadi Al Arbyeen P124 1TX 1.2 0.5 1.2 - 1.2 0.5 1.3 - 1.2 0.5 1.3 - 1.2 0.5 1.3 - Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Mazara P074 6 0.5 0.2 0.6 9% 0.5 0.3 0.6 10% 0.5 0.3 0.6 10% 0.5 0.3 0.6 10% Al Shahbari P092 20 2.3 1.2 2.6 13% 2.4 1.2 2.7 13% 2.4 1.2 2.7 13% 2.4 1.3 2.8 14% Dhabab P019 6 0.7 0.3 0.8 13% 0.7 0.4 0.8 14% 0.7 0.4 0.8 14% 0.7 0.4 0.8 14% Dhagmar 1 P021 18 0.8 0.4 0.9 5% 0.8 0.4 0.9 5% 0.8 0.4 0.9 5% 0.8 0.4 0.9 5% Hail Al Ghaf P036 6 0.8 0.4 0.9 15% 0.9 0.4 1.0 16% 0.9 0.4 1.0 16% 0.9 0.4 1.0 16% Quriyat P091 20 2.9 0.0 2.9 15% 3.0 0.0 3.0 15% 3.0 0.0 3.0 15% 3.1 0.0 3.1 16% RoyalCamp P170 1TX Standby PSS Street Light P020 1TX 0.6 0.3 0.6 - 0.6 0.3 0.7 - 0.6 0.3 0.7 - 0.6 0.3 0.7 - Wadi Al Arbyeen P124 1TX 0.2 0.1 0.2 - 0.2 0.1 0.2 - 0.2 0.1 0.2 - 0.2 0.1 0.2 - 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Shahbari-F1-P092 22.0 17.2 77.7 17.6 79.9 17.6 79.9 18.0 81.7 Al Shahbari-F2-P092 22.0 9.3 42.3 9.6 43.3 9.6 43.3 9.9 45.0 Dhagmar 1-F1-P021 22.0 9.0 40.9 9.2 41.6 9.2 41.6 9.2 41.7 Quriyat-F1-P091 22.0 15.3 69.4 15.8 71.7 15.8 71.7 16.3 73.6 Quriyat-F2-P091 22.0 10.5 47.8 10.9 49.5 10.9 49.5 11.3 51.4 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Mazara-A P074 98.7 99.7 100.6 103.9 98.7 99.7 100.4 103.9 98.6 99.7 100.4 103.9 98.6 99.7 100.3 103.9 Al Mazara-B P074 98.7 99.7 100.6 103.9 98.7 99.7 100.4 103.9 98.6 99.7 100.4 103.9 98.6 99.7 100.3 103.9 Al Shahbari-A P092 99.1 99.9 101.4 104.1 99.1 99.9 101.5 104.0 99.1 99.9 101.5 104.0 99.0 99.9 101.3 104.0 Al Shahbari-B P092 99.6 100.0 101.4 104.1 99.6 100.0 101.5 104.0 99.6 100.0 101.5 104.0 99.5 100.0 101.3 104.0 Dhabab-A P019 98.2 99.7 100.4 103.9 98.2 99.7 100.3 103.9 98.0 99.7 100.3 103.9 98.0 99.7 100.2 103.9 Dhabab-B P019 98.2 99.7 100.4 103.9 98.2 99.7 100.3 103.9 98.0 99.7 100.3 103.9 98.0 99.7 100.2 103.9 Dhagmar 1-A P021 100.1 100.0 103.4 104.3 100.0 100.0 104.0 104.5 100.0 100.0 104.0 104.5 100.0 100.0 103.9 104.5 Dhagmar 1-B P021 100.4 100.1 103.8 104.4 100.3 100.1 104.0 104.5 100.2 100.1 104.0 104.5 100.2 100.1 103.9 104.5 Dhagmar 1-C P021 100.4 100.1 104.6 104.6 100.3 100.1 104.0 104.6 100.2 100.1 104.0 104.6 100.2 100.1 103.9 104.6 Dhagmar 1-D P021 100.4 100.1 101.1 104.6 100.3 100.1 100.9 104.6 100.2 100.1 100.6 104.6 100.2 100.1 100.6 104.6 Hayl Ghaf-A P036 99.8 99.9 101.0 103.9 99.8 99.9 101.1 104.0 99.7 99.9 101.1 104.0 99.7 99.9 101.0 104.0 Hayl Ghaf-B P036 99.8 99.9 101.5 104.0 99.8 99.9 101.1 104.0 99.7 99.9 101.1 104.0 99.7 99.9 101.0 104.0 Quriyat-A P091 99.6 100.0 102.3 104.5 99.5 100.0 102.2 104.5 99.5 100.0 102.2 104.5 99.4 100.0 102.0 104.5 Quriyat-B P091 99.6 100.0 102.3 104.5 99.6 100.0 102.2 104.5 99.6 100.0 102.2 104.5 99.5 100.0 102.0 104.5 RoyalCamp P170 98.9 99.9 103.4 104.5 98.9 99.9 103.4 104.5 98.9 99.9 103.4 104.5 98.8 99.9 103.3 104.5 Street Light P020 99.8 100.0 98.1 99.7 99.7 100.0 98.1 99.7 99.7 100.0 98.1 99.7 99.7 100.0 98.0 99.7 Wadi Al Arbyeen P124 99.1 100.0 103.0 104.4 99.1 100.0 102.9 104.4 99.1 100.0 102.9 104.4 99.0 100.0 102.9 104.4

MEDC Distribution System Capability Statement [2021-2023]-V2.0 68 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Mazara-A P074 25.0 12.5 2.3 4.0 2.3 4.0 2.3 4.0 2.3 4.0 Al Mazara-B P074 25.0 16.0 2.3 4.0 2.3 4.0 2.3 4.0 2.3 4.0 Al Shahbari-A P092 25.0 20.0 9.8 12.3 9.9 12.3 10.0 12.3 10.0 12.4 Al Shahbari-B P092 25.0 20.0 9.7 12.3 9.7 12.3 9.8 12.3 9.8 12.4 Dhabab-A P019 25.0 16.0 2.0 3.7 2.0 3.7 2.0 3.7 2.0 3.7 Dhabab-B P019 25.0 16.0 2.0 3.7 2.0 3.7 2.0 3.7 2.0 3.7 Dhagmar 1-A P021 25.0 12.5 13.5 4.4 13.7 4.4 13.7 4.4 13.8 4.4 Dhagmar 1-B P021 25.0 12.5 13.5 4.5 13.7 4.5 13.7 4.5 13.8 4.5 Dhagmar 1-C P021 25.0 12.5 13.5 4.2 13.7 4.3 13.7 4.3 13.8 4.3 Dhagmar 1-D P021 25.0 12.5 13.0 4.4 13.1 4.5 13.1 4.5 13.2 4.5 Hayl Ghaf-A P036 25.0 12.5 5.3 3.9 5.3 3.9 5.4 3.9 5.4 3.9 Hayl Ghaf-B P036 25.0 16.0 5.3 3.7 5.3 3.7 5.3 3.7 5.3 3.7 Quriyat-A P091 25.0 20.0 9.7 12.5 9.8 12.6 9.8 12.6 9.8 12.7 Quriyat-B P091 25.0 20.0 9.6 12.5 9.7 12.6 9.7 12.6 9.8 12.7 RoyalCamp P170 25.0 16.0 4.6 2.2 4.6 2.2 4.6 2.2 4.6 2.2 Street Light P020 25.0 16.0 9.9 4.9 10.0 4.9 10.0 4.9 10.0 4.9 Wadi Al Arbyeen P124 25.0 12.5 4.8 3.6 4.8 3.6 4.8 3.6 4.8 3.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 69 Amerat[G10] - A GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Amerat 3 P179 40 33.2 9.2 34.5 86% 36.8 10.7 38.3 96% 40.7 11.9 42.4 106% 43.8 12.8 45.6 114% Amerat Heights P152 40 24.5 7.5 25.7 64% 24.1 7.5 25.2 63% 26.6 8.3 27.9 70% 28.6 8.9 30.0 75% Post Office P150 40 27.6 11.9 30.7 77% 30.7 10.1 32.3 81% 33.9 11.1 35.7 89% 36.5 12.0 38.4 96% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Amerat 3 P179 40 5.3 0.0 5.3 13% 5.9 0.0 5.9 15% 6.5 0.0 6.5 16% 7.0 0.0 7.0 18% Amerat Heights P152 40 2.9 0.4 2.9 7% 2.3 0.3 2.3 6% 2.6 0.4 2.6 6% 2.7 0.4 2.8 7% Post Office P150 40 3.8 2.2 4.4 11% 4.0 2.4 4.6 12% 4.4 2.6 5.1 13% 4.7 2.8 5.5 14% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Amerat 3-F1-P179 22.0 12.3 55.7 13.0 59.1 14.5 65.7 15.7 70.9 Amerat 3-F2-P179 22.0 12.4 56.2 13.1 59.6 14.6 66.2 15.8 71.5 Amerat 3-F3-P179 22.0 10.6 47.9 13.1 59.3 14.6 65.9 15.7 71.2 Amerat Heights-F1-P152 22.0 8.1 36.8 8.5 38.3 9.4 42.6 10.2 46.0 Amerat Heights-F2-P152 22.0 8.1 36.9 8.5 38.5 9.4 42.7 10.2 46.2 Amerat Heights-F3-P152 22.0 9.7 43.9 8.5 38.4 9.4 42.7 10.2 46.1 Post Office-F1-P150 22.0 8.9 40.3 11.0 49.7 12.2 55.2 13.2 59.6 Post Office-F2-P150 22.0 8.9 40.5 11.0 49.9 12.2 55.4 13.2 59.8 Post Office-F3-P150 22.0 13.8 62.4 11.0 49.8 12.2 55.3 13.2 59.7 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Amerat 3-A P179 99.5 100.0 101.2 104.4 99.4 100.0 101.0 104.4 99.4 99.9 100.5 104.4 99.3 99.9 100.2 104.4 Amerat 3-B P179 99.5 100.0 101.2 104.4 99.4 100.0 101.0 104.4 99.4 99.9 100.5 104.4 99.3 99.9 100.2 104.4 Amerat 3-C P179 99.6 100.0 101.7 104.5 99.4 100.0 100.9 104.4 99.4 99.9 100.5 104.4 99.3 99.9 100.1 104.4 Amerat Heights-A P152 99.6 100.0 102.1 104.4 99.6 100.0 102.0 104.4 99.5 100.0 101.7 104.4 99.5 100.0 101.5 104.4 Amerat Heights-B P152 99.6 100.0 102.1 104.4 99.6 100.0 102.0 104.4 99.5 100.0 101.7 104.4 99.5 100.0 101.5 104.4 Amerat Heights-C P152 99.5 100.0 101.6 104.4 99.6 100.0 102.0 104.4 99.5 100.0 101.7 104.4 99.5 100.0 101.5 104.4 Post Office-A P150 99.8 100.0 101.4 104.1 99.7 100.0 101.5 104.0 99.7 100.0 101.2 103.9 99.7 100.0 100.9 103.9 Post Office-B P150 99.8 100.0 101.4 104.1 99.7 100.0 101.5 104.0 99.7 100.0 101.2 103.9 99.7 100.0 100.9 103.9 Post Office-C P150 99.7 100.0 99.7 103.8 99.7 100.0 101.6 104.0 99.7 100.0 101.2 104.0 99.7 100.0 101.0 103.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 70 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Amerat 3-A P179 25.0 25.0 14.3 14.3 14.5 14.5 14.9 14.8 15.0 15.0 Amerat 3-B P179 25.0 25.0 14.3 14.3 14.5 14.5 14.9 14.8 15.0 15.0 Amerat 3-C P179 25.0 25.0 14.1 7.8 14.4 8.0 14.7 8.1 14.8 8.2 Amerat Heights-A P152 25.0 25.0 13.2 13.6 13.4 13.7 13.7 13.9 13.8 14.1 Amerat Heights-B P152 25.0 25.0 13.2 13.6 13.4 13.7 13.7 13.9 13.8 14.1 Amerat Heights-C P152 25.0 25.0 12.9 7.7 13.1 7.6 13.4 7.7 13.5 7.7 Post Office-A P150 25.0 25.0 16.9 14.0 17.3 14.4 17.7 14.7 17.9 14.8 Post Office-B P150 25.0 25.0 16.9 14.0 17.2 14.4 17.7 14.7 17.9 14.8 Post Office-C P150 25.0 25.0 17.1 8.3 17.4 8.1 17.9 8.2 18.1 8.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 71 Amerat[G10] - B GSS [Zone 1] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Jufaina P194 1TX 1.1 0.4 1.2 - 1.2 0.5 1.3 - 1.4 0.5 1.5 - 1.5 0.6 1.6 - Al Nahdah P006 40 24.5 8.6 26.0 65% 31.6 10.4 33.3 83% 35.0 11.5 36.8 92% 37.6 12.4 39.6 99% Amerat 4 P180 40 - - - - 12.0 3.9 12.6 32% 13.3 4.4 13.9 35% 14.2 4.7 15.0 37% Madinat Al Nahdah P065 20 19.3 6.3 20.3 102% 12.5 4.1 13.2 66% 13.9 4.6 14.6 73% 14.9 4.9 15.7 79% Seih Dhabi P118 16 11.9 5.1 12.9 81% 13.2 4.3 13.9 87% Upgraded Seih Dhabi(upgrading) P118 20 ------16.8 5.5 17.7 88% 18.0 5.9 19.0 95% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Jufaina P194 1TX 0.2 0.1 0.2 - 0.2 0.1 0.2 - 0.2 0.1 0.3 - 0.3 0.1 0.3 - Al Nahdah P006 40 2.4 1.2 2.7 7% 2.2 1.1 2.5 6% 2.5 1.2 2.8 7% 2.7 1.3 3.0 7% Amerat 4 P180 40 - - - - 2.1 1.0 2.3 6% 2.3 1.1 2.6 6% 2.5 1.2 2.7 7% Madinat Al Nahdah P065 20 2.6 0.4 2.6 13% 2.9 0.4 2.9 14% 3.2 0.5 3.2 16% 3.4 0.5 3.4 17% Seih Dhabi P118 16 1.7 0.9 1.9 12% 1.8 1.0 2.0 13% Upgraded Seih Dhabi(upgrading) P118 20 ------2.0 1.1 2.3 11% 2.1 1.2 2.4 12% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Nahdah-F1-P006 22.0 8.8 39.9 11.4 51.8 12.7 57.6 13.7 62.2 Al Nahdah-F2-P006 22.0 8.8 39.8 11.4 51.6 12.7 57.4 13.7 61.9 Al Nahdah-F3-P006 22.0 8.9 40.4 11.3 51.1 12.5 56.8 13.5 61.2 Amerat 4-F1-P180 22.0 - - 4.1 18.6 4.6 20.7 4.9 22.3 Amerat 4-F2-P180 22.0 - - 4.1 18.6 4.6 20.7 4.9 22.3 Amerat 4-F3-P180 22.0 - - 4.1 18.6 4.6 20.7 4.9 22.3 Madinat Al Nahdah-F1-P065 22.0 11.8 49.1 8.1 33.8 9.0 37.6 9.7 40.5 Madinat Al Nahdah-F2-P065 22.0 11.0 45.6 6.7 28.1 7.5 31.2 8.1 33.7 Seih Dhabi-F2-P118 22.0 6.6 29.8 7.1 32.0 9.0 40.9 9.7 44.0 Seih Dhabi-F3-P118 22.0 6.6 29.8 7.0 31.9 9.0 40.9 9.7 44.0 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Jufaina-A P194 98.7 99.9 102.5 104.3 99.1 99.9 102.9 104.3 99.0 99.8 102.7 104.2 98.9 99.8 102.6 104.2 Al Nahdah-A P006 99.1 99.9 101.6 104.2 98.9 99.9 100.9 104.2 102.3 104.3 100.5 103.9 102.1 99.8 100.1 103.8 Al Nahdah-B P006 99.1 99.9 101.6 104.2 98.9 99.9 100.9 104.2 102.3 104.3 100.5 103.9 102.1 100.0 100.1 103.8 Al Nahdah-C P006 99.7 100.0 102.3 104.3 99.6 100.0 101.8 104.3 99.6 100.0 101.5 104.3 99.6 100.0 101.2 104.3 Amerat 4-A P180 - - - - 99.8 100.0 103.3 104.3 99.8 100.0 103.2 104.2 99.8 100.0 103.1 104.2 Amerat 4-B P180 - - - - 99.8 100.0 103.3 104.3 99.8 100.0 103.2 104.2 99.8 100.0 103.1 104.2 Amerat 4-C P180 - - - - 99.8 100.0 103.3 104.3 99.8 100.0 103.2 104.2 99.8 100.0 103.1 104.2 Madinat Al Nahdah-A P065 98.2 99.8 100.0 104.2 98.8 99.8 101.7 104.2 98.7 99.8 101.3 104.1 98.6 99.8 101.1 104.1 Madinat Al Nahdah-B P065 96.4 101.9 98.1 106.4 101.2 101.9 104.2 106.4 100.9 101.9 103.7 106.3 100.8 101.9 103.4 106.3 Seih Dhabi-A P118 100.0 100.0 102.5 104.2 100.0 100.0 102.7 104.3 100.0 100.0 102.3 104.3 100.0 100.0 102.1 104.3 Seih Dhabi-B P118 100.0 100.0 102.5 104.2 100.0 100.0 102.7 104.3 100.0 100.0 102.3 104.3 100.0 100.0 102.1 104.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 72 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Jufaina-A P194 25.0 16.0 7.6 4.0 7.6 4.0 7.7 4.1 7.7 4.1 Al Nahdah-A P006 25.0 18.4 9.5 13.6 9.7 14.0 9.8 14.3 9.9 14.5 Al Nahdah-B P006 25.0 18.4 9.5 13.6 9.7 14.0 9.8 14.3 9.9 14.5 Al Nahdah-C P006 25.0 25.0 15.7 8.7 16.0 8.9 16.4 9.1 16.5 9.1 Amerat 4-A P180 25.0 25.0 - - 12.2 12.4 12.4 12.5 12.4 12.6 Amerat 4-B P180 25.0 25.0 - - 12.2 12.4 12.4 12.5 12.4 12.6 Amerat 4-C P180 25.0 25.0 - - 12.0 7.0 12.2 7.0 12.2 7.0 Madinat Al Nahdah-A P065 25.0 18.4 6.4 6.3 6.4 6.0 6.4 6.1 6.4 6.1 Madinat Al Nahdah-B P065 25.0 18.4 2.6 4.4 6.5 6.1 6.5 6.2 6.5 6.2 Seih Dhabi-A P118 25.0 18.4 20.9 13.3 21.4 13.4 22.1 14.4 22.4 14.6 Seih Dhabi-B P118 25.0 18.4 20.9 13.3 21.4 13.4 22.1 14.4 22.4 14.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 73 Ghubrah 2[G09] GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Azaibah North 2 P012 20 14.8 4.1 15.4 77% 15.3 4.4 16.0 80% 15.5 4.4 16.1 80% 15.5 4.4 16.1 80% Azaibah South 1-A P014 20 15.3 5.9 16.4 82% Shifted to Ghala Heights GSS Diplomatic City P022 40 18.9 12.7 22.8 57% 18.9 6.2 19.9 50% 18.9 6.2 19.9 50% 18.9 6.2 19.9 50% Ghubrah GPS P166 16 6.5 2.6 7.0 44% 6.5 2.6 7.0 44% 6.5 2.6 7.0 44% 6.5 2.6 7.0 44% Ghubrah North 1 P023 40 29.4 13.5 32.4 81% 30.5 10.0 32.1 80% 30.7 10.1 32.3 81% 30.7 10.1 32.3 81% Ghubrah North 2 P149 40 30.1 11.0 32.0 80% 31.2 10.3 32.9 82% 31.5 10.3 33.1 83% 31.5 10.3 33.1 83% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Azaibah North 2 P012 20 2.6 1.0 2.8 14% 2.7 1.1 2.9 15% 2.7 1.1 2.9 15% 2.7 1.1 2.9 15% Azaibah South 1-A P014 20 2.2 1.4 2.6 13% Shifted to Ghala Heights GSS Diplomatic City P022 40 3.1 1.6 3.5 9% 3.2 1.7 3.6 9% 3.2 1.7 3.6 9% 3.2 1.7 3.6 9% Ghubrah GPS P166 16 1.0 0.4 1.1 7% 1.2 0.5 1.3 8% 1.2 0.5 1.3 8% 1.2 0.5 1.3 8% Ghubrah North 1 P023 40 4.7 2.7 5.4 14% 5.1 2.9 5.9 15% 5.1 2.9 5.9 15% 5.1 2.9 5.9 15% Ghubrah North 2 P149 40 5.5 2.6 6.1 15% 5.4 2.6 6.0 15% 5.5 2.6 6.1 15% 5.5 2.6 6.1 15% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Azaiba North 2-F1-P012 22.0 7.9 35.7 8.2 37.0 8.2 37.4 8.2 37.4 Azaiba North 2-F2-P012 22.0 7.6 34.6 7.9 35.9 8.0 36.3 8.0 36.3 Azaiba South 1A-F1-P014 20.0 8.4 42.0 ------Azaiba South 1A-F2-P014 20.0 8.3 41.3 ------Diplomatic City-F1-P022 22.0 7.2 32.9 6.7 30.3 6.7 30.3 6.7 30.3 Diplomatic City-F2-P022 22.0 7.4 33.8 6.6 30.1 6.6 30.1 6.6 30.1 Diplomatic City-F3-P022 22.0 8.1 36.7 6.7 30.2 6.7 30.2 6.7 30.2 Ghubra North 1-F1-P023 22.0 9.8 44.6 9.8 44.5 9.9 45.0 9.9 45.0 Ghubra North 1-F2-P023 22.0 9.8 44.5 9.8 44.5 9.9 44.9 9.9 44.9 Ghubra North 1-F3-P023 22.0 11.3 51.4 10.9 49.6 11.0 50.1 11.0 50.1 Ghubrah GPS-F1-P166 22.0 3.6 16.1 3.5 16.1 3.5 16.1 3.5 16.1 Ghubrah GPS-F2-P166 22.0 3.5 15.9 3.5 15.8 3.5 15.8 3.5 15.8 Ghubrah North 02-F1-P149 22.0 10.2 46.1 11.2 50.6 11.3 51.0 11.3 51.0 Ghubrah North 02-F2-P149 22.0 10.2 46.0 11.2 50.5 11.2 50.9 11.2 50.9 Ghubrah North 02-F3-P149 22.0 12.3 55.8 11.2 50.6 11.3 51.0 11.3 51.0 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Azaiba North 2-A P012 100.3 100.6 103.1 104.8 100.2 100.6 103.0 104.8 100.2 100.6 102.9 104.8 100.2 100.6 102.9 104.8 Azaiba North 2-B P012 100.3 100.6 103.1 104.8 100.2 100.6 103.0 104.8 100.2 100.6 102.9 104.8 100.2 100.6 102.9 104.8 Azaiba South 1A-A P014 99.5 100.5 101.6 104.6 ------Azaiba South 1A-B P014 99.4 100.5 101.6 104.6 ------Diplomatic City-A P022 100.4 100.6 102.0 104.8 100.4 100.6 103.3 104.8 100.4 100.6 103.3 104.8 100.4 100.6 103.3 104.8 Diplomatic City-B P022 100.4 100.6 102.0 104.8 100.4 100.6 103.3 104.8 100.4 100.6 103.3 104.8 100.4 100.6 103.3 104.8 Diplomatic City-C P022 100.4 100.6 101.9 104.8 100.4 100.7 103.4 104.9 100.4 100.7 103.4 104.9 100.4 100.7 103.4 104.9 Ghubra North 1-A P023 100.4 100.6 102.0 104.6 100.4 100.6 102.6 104.5 100.4 100.6 102.5 104.5 100.4 100.6 102.5 104.5 Ghubra North 1-B P023 100.4 100.6 102.0 104.6 100.4 100.6 102.6 104.5 100.4 100.6 102.5 104.5 100.4 100.6 102.5 104.5 Ghubra North 1-C P023 100.4 100.6 101.5 104.6 100.4 100.6 102.3 104.5 100.4 100.6 102.2 104.5 100.4 100.6 102.2 104.5 Ghubrah GPS-A P166 100.5 100.7 103.9 105.1 100.5 100.7 103.9 105.0 100.5 100.7 103.9 105.0 100.5 100.7 103.9 105.0 Ghubrah GPS-B P166 100.5 100.7 103.9 105.1 100.5 100.7 103.9 105.0 100.5 100.7 103.9 105.0 100.5 100.7 103.9 105.0 Ghubrah North 2-A P149 100.2 100.6 102.2 104.6 100.2 100.6 102.1 104.6 100.1 100.6 102.0 104.6 100.1 100.6 102.0 104.6 Ghubrah North 2-B P149 100.2 100.6 102.2 104.6 100.2 100.6 102.1 104.6 100.1 100.6 102.0 104.6 100.1 100.6 102.0 104.6 Ghubrah North 2-C P149 100.1 100.6 101.5 104.5 100.2 100.6 102.1 104.6 100.1 100.6 102.0 104.6 100.1 100.6 102.0 104.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 74 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Azaiba North 2-A P012 25.0 18.4 15.9 13.8 15.9 13.9 16.2 13.9 16.2 13.9 Azaiba North 2-B P012 25.0 18.4 15.9 13.8 15.8 13.9 16.2 13.9 16.1 13.9 Azaiba South 1A-A P014 25.0 18.4 9.0 12.5 ------Azaiba South 1A-B P014 25.0 18.4 8.5 12.5 ------Diplomatic City-A P022 25.0 25.0 18.7 13.8 18.6 13.7 19.1 13.8 19.0 13.8 Diplomatic City-B P022 25.0 25.0 18.7 13.8 18.6 13.7 19.1 13.8 19.0 13.8 Diplomatic City-C P022 25.0 25.0 20.1 8.1 20.0 8.0 20.5 8.0 20.5 8.0 Ghubra North 1-A P023 25.0 20.0 21.0 14.8 20.9 14.8 21.4 14.9 21.4 14.9 Ghubra North 1-B P023 25.0 20.0 20.9 14.8 20.9 14.8 21.4 14.9 21.4 14.9 Ghubra North 1-C P023 25.0 20.0 20.9 8.2 20.8 8.2 21.4 8.2 21.3 8.2 Ghubrah GPS-A P166 25.0 25.0 21.4 11.9 21.4 11.9 21.9 11.9 21.9 11.9 Ghubrah GPS-B P166 25.0 25.0 21.4 11.9 21.4 11.9 21.9 11.9 21.9 11.9 Ghubrah North 2-A P149 25.0 25.0 16.7 14.8 16.6 14.9 17.0 15.0 17.0 15.0 Ghubrah North 2-B P149 25.0 25.0 16.6 14.8 16.6 14.9 17.0 15.0 16.9 15.0 Ghubrah North 2-C P149 25.0 25.0 16.5 8.3 16.5 8.3 16.8 8.3 16.8 8.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 75 MSQ[GP06] - A GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khuwair North P054 40 16.2 6.4 17.4 44% 16.7 5.5 17.6 44% 17.2 5.7 18.1 45% 17.2 5.7 18.1 45% Information City 2 P038 1TX Standby PSS Intercontinental P109 20 10.8 5.0 11.9 60% 10.8 3.5 11.4 57% 10.8 3.5 11.4 57% 10.8 3.5 11.4 57% MSQ Grid GP06 20 18.1 7.6 19.6 98% 18.4 7.8 20.0 100% 18.5 7.8 20.1 101% 18.5 7.8 20.1 101% Royal Office P097 20 6.2 2.2 6.6 33% 6.2 2.0 6.5 33% 6.2 2.0 6.5 33% 6.2 2.0 6.5 33% Sarooj -Shati Al Qurum P110 20 16.3 8.7 18.5 92% 16.2 8.7 18.4 92% 21.2 11.3 24.0 120% Upgraded Sarooj -Shati Al Qurum(upgrading)P110 40 ------21.2 7.0 22.3 56% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khuwair North P054 40 2.7 1.3 3.0 8% 2.9 1.4 3.2 8% 3.0 1.4 3.3 8% 3.0 1.4 3.3 8% Information City 2 P038 1TX Standby PSS Intercontinental P109 20 3.1 1.1 3.3 17% 2.0 0.7 2.1 10% 2.0 0.7 2.1 10% 2.0 0.7 2.1 10% MSQ Grid GP06 20 2.8 1.1 3.0 15% 3.4 1.3 3.7 18% 3.4 1.3 3.7 18% 3.4 1.3 3.7 18% Royal Office P097 20 2.4 0.7 2.5 13% 1.1 0.3 1.2 6% 1.1 0.3 1.2 6% 1.1 0.3 1.2 6% Sarooj -Shati Al Qurum P110 20 3.0 1.1 3.2 16% 4.1 1.5 4.4 22% 5.1 1.9 5.5 27% Upgraded Sarooj -Shati Al Qurum(upgrading)P110 40 ------4.8 1.8 5.1 13% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Khuwair North-F1-P054 22.0 5.9 26.5 5.9 26.8 6.1 27.5 6.1 27.6 Al Khuwair North-F2-P054 22.0 5.9 26.9 6.0 27.1 6.2 27.9 6.2 27.9 Al Khuwair North-F3-P054 22.0 5.9 26.7 5.9 27.0 6.1 27.7 6.1 27.7 Intercontinental-F1-P109 22.0 5.9 26.8 5.7 25.7 5.7 25.7 5.7 25.7 Intercontinental-F2-P109 22.0 6.0 27.2 5.8 26.1 5.7 26.1 5.8 26.1 MSQ Grid-F1-GP06 22.0 10.0 45.5 10.2 46.4 10.3 46.7 10.3 46.7 MSQ Grid-F2-GP06 22.0 10.2 46.1 10.4 47.0 10.4 47.3 10.4 47.3 Royal Office-F1-P097 22.0 3.4 15.3 3.3 15.1 3.3 15.1 3.3 15.1 Royal Office-F2-P097 22.0 3.3 15.0 3.3 14.8 3.3 14.8 3.3 14.8 Sarooj Shati Al Qurum-F1-P110 22.0 9.5 43.1 9.5 42.9 12.5 56.5 9.4 42.8 Sarooj Shati Al Qurum-F2-P110 22.0 9.5 43.1 9.5 42.9 12.5 56.6 9.4 42.8 Sarooj Shati Al Qurum-F3-P110 22.0 ------9.4 42.8 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Khuwair North-A P054 101.8 101.3 105.0 105.6 100.0 101.3 103.2 105.6 101.5 101.3 104.8 105.6 100.3 101.5 103.5 105.8 Al Khuwair North-B P054 101.8 101.3 105.0 105.6 100.0 101.3 103.2 105.6 101.5 101.3 104.8 105.6 100.3 101.5 103.5 105.8 Al Khuwair North-C P054 101.8 101.3 105.0 105.6 100.0 101.3 103.2 105.6 101.5 101.3 104.8 105.6 100.2 101.5 103.5 105.8 Information City 2-- P038 101.7 101.3 106.3 105.9 100.2 101.3 104.7 105.9 100.8 101.3 105.4 105.9 100.0 101.3 104.6 105.9 Intercontinental-A P109 101.6 101.2 104.7 105.5 99.8 101.3 103.2 105.7 101.3 101.3 104.8 105.7 100.1 101.4 103.5 105.8 Intercontinental-B P109 101.6 101.3 104.7 105.5 99.8 101.3 103.2 105.7 101.4 101.3 104.8 105.7 100.1 101.5 103.5 105.8 MSQ Grid-A GP06 101.8 101.3 103.6 105.5 100.0 101.3 101.6 105.5 101.6 101.3 103.2 105.4 100.3 101.5 101.9 105.6 MSQ Grid-B GP06 101.8 101.3 103.6 105.5 100.0 101.3 101.6 105.5 101.6 101.3 103.2 105.4 100.3 101.5 101.9 105.6 Royal Office-A P097 101.7 101.3 105.5 105.6 99.9 101.3 103.7 105.8 101.5 101.3 105.3 105.8 100.2 101.5 104.0 106.0 Royal Office-B P097 101.7 101.3 105.5 105.6 99.9 101.3 103.7 105.8 101.5 101.3 105.3 105.8 100.2 101.5 104.0 106.0 Sarooj Shati Al Qurum-A P110 101.5 101.2 103.4 105.1 100.0 101.2 101.8 104.9 100.4 101.1 101.5 104.5 99.8 101.2 102.1 104.9 Sarooj Shati Al Qurum-B P110 101.5 101.3 103.4 105.1 100.0 101.3 101.8 104.9 100.4 101.3 101.5 104.5 99.8 101.3 102.1 104.9 Sarooj Shati Al Qurum-C P110 ------99.8 101.3 102.1 105.5

MEDC Distribution System Capability Statement [2021-2023]-V2.0 76 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Khuwair North-A P054 25.0 25.0 19.9 15.1 20.2 15.1 20.8 15.3 20.8 15.3 Al Khuwair North-B P054 25.0 25.0 19.9 15.1 20.2 15.1 20.8 15.3 20.8 15.3 Al Khuwair North-C P054 25.0 25.0 19.7 8.4 19.9 8.4 20.5 8.4 20.6 8.4 Information City 2-- P038 25.0 18.4 16.5 3.3 16.7 3.3 17.0 3.3 17.1 3.3 Intercontinental-A P109 25.0 18.4 14.4 15.3 14.5 15.3 14.8 15.4 14.8 15.5 Intercontinental-B P109 25.0 18.4 15.2 15.3 15.4 15.3 15.7 15.4 15.7 15.5 MSQ Grid-A GP06 25.0 18.4 24.2 15.0 24.6 15.1 25.5 15.2 25.5 15.2 MSQ Grid-B GP06 25.0 18.4 24.2 15.0 24.6 15.1 25.5 15.2 25.5 15.2 Royal Office-A P097 25.0 18.4 14.6 12.9 14.7 12.9 15.0 13.0 15.1 13.0 Royal Office-B P097 25.0 18.4 14.6 12.9 14.7 12.9 15.0 13.0 15.1 13.0 Sarooj Shati Al Qurum-A P110 25.0 18.4 16.0 16.0 16.2 16.0 16.6 16.6 16.5 14.2 Sarooj Shati Al Qurum-B P110 25.0 18.4 16.0 16.0 16.1 16.0 16.5 16.6 16.5 14.2 Sarooj Shati Al Qurum-C P110 25.0 25.0 ------16.4 7.8

MEDC Distribution System Capability Statement [2021-2023]-V2.0 77 MSQ[GP06] - B GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khuwair 25 P053 20 14.0 3.9 14.5 73% 14.5 3.9 15.0 75% 14.9 4.0 15.4 77% 14.9 4.0 15.4 77% Al Khuwair School P146 40 22.8 10.3 25.0 63% 23.6 7.7 24.8 62% 24.2 8.0 25.5 64% 24.2 8.0 25.5 64% Digital TV Studio P039 20 2.8 1.4 3.1 16% 2.8 0.9 2.9 15% 2.8 0.9 2.9 15% 2.8 0.9 2.9 15% MSQ 1 P083 20 14.7 5.0 15.5 78% 15.0 4.9 15.8 79% 15.1 5.0 15.9 79% 15.1 5.0 15.9 79% ROP -Shati Al Qurum P111 20 11.8 4.6 12.6 63% 11.8 4.4 12.6 63% 11.8 4.4 12.6 63% 11.8 4.4 12.6 63% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khuwair 25 P053 20 1.7 1.1 2.0 10% 2.3 1.4 2.7 14% 2.4 1.5 2.8 14% 2.4 1.5 2.8 14% Al Khuwair School P146 40 3.5 2.1 4.1 10% 3.9 2.4 4.5 11% 4.0 2.4 4.7 12% 4.0 2.4 4.7 12% Digital TV Studio P039 20 1.2 0.5 1.3 7% 0.5 0.2 0.5 3% 0.5 0.2 0.5 3% 0.5 0.2 0.5 3% MSQ 1 P083 20 3.2 1.4 3.5 18% 2.6 1.2 2.9 14% 2.7 1.2 2.9 15% 2.7 1.2 2.9 15% ROP -Shati Al Qurum P111 20 1.4 0.5 1.5 8% 2.1 0.8 2.3 11% 2.1 0.8 2.3 11% 2.1 0.8 2.3 11% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Khuwair 25-F1-P053 22.0 7.3 30.4 7.5 31.4 7.8 32.3 7.8 32.3 Al Khuwair 25-F2-P053 22.0 7.3 30.3 7.5 31.4 7.7 32.3 7.7 32.3 Al Khuwair School-F1-P146 22.0 6.8 30.7 8.4 38.1 8.6 39.2 8.6 39.2 Al Khuwair School-F2-P146 22.0 6.8 30.9 8.5 38.4 8.7 39.4 8.7 39.4 Al Khuwair School-F3-P146 22.0 12.2 55.3 8.4 38.3 8.7 39.3 8.7 39.3 Digital TV Studio-F1-P039 22.0 1.6 7.1 1.5 6.8 1.5 6.8 1.5 6.8 Digital TV Studio-F2-P039 22.0 1.6 7.2 1.5 6.8 1.5 6.8 1.5 6.8 MSQ 1-F1-P083 22.0 8.0 36.1 8.1 36.8 8.2 37.0 8.2 37.0 MSQ 1-F2-P083 22.0 7.8 35.5 8.0 36.2 8.0 36.4 8.0 36.4 ROP Shati Al Qurum-F1-P111 22.0 6.4 29.0 6.4 29.0 6.4 29.0 6.4 29.0 ROP Shati Al Qurum-F2-P111 22.0 6.3 28.7 6.3 28.7 6.3 28.7 6.3 28.7 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Khuwair 25-A P053 99.8 101.0 102.9 105.3 99.8 101.0 102.9 105.1 99.8 101.0 102.8 105.0 99.8 101.0 102.8 105.0 Al Khuwair 25-B P053 99.8 101.0 102.9 105.3 99.8 101.0 102.9 105.1 99.8 101.0 102.8 105.0 99.8 101.0 102.8 105.0 Al Khuwair School-A P146 101.7 101.3 104.3 105.5 99.8 101.3 102.3 105.4 101.4 101.3 103.9 105.3 100.1 101.4 102.6 105.5 Al Khuwair School-B P146 101.7 101.3 104.3 105.5 99.8 101.3 102.3 105.4 101.4 101.3 103.9 105.3 100.1 101.4 102.6 105.5 Al Khuwair School-C P146 101.5 101.3 102.4 105.2 99.8 101.3 102.3 105.4 101.4 101.3 103.9 105.3 100.1 101.4 102.6 105.5 Digital TV Studio-A P039 101.8 101.3 106.0 105.7 100.0 101.3 104.2 105.9 101.5 101.3 105.8 105.8 100.3 101.5 104.5 106.0 Digital TV Studio-B P039 101.8 101.3 106.0 105.7 100.0 101.3 104.2 105.9 101.5 101.3 105.8 105.8 100.3 101.5 104.5 106.0 MSQ 1-A P083 101.7 101.3 104.4 105.4 99.9 101.3 102.5 105.5 101.5 101.3 104.1 105.4 100.2 101.5 102.8 105.6 MSQ 1-B P083 101.7 101.3 104.4 105.4 99.9 101.3 102.5 105.5 101.5 101.3 104.1 105.4 100.2 101.5 102.8 105.6 ROP Shati Al Qurum-A P111 99.9 101.0 103.1 105.5 99.9 101.0 103.1 105.3 99.9 101.0 103.0 105.3 99.9 101.0 103.0 105.3 ROP Shati Al Qurum-B P111 99.9 101.0 103.1 105.5 99.9 101.0 103.1 105.3 99.9 101.0 103.0 105.3 99.9 101.0 103.0 105.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 78 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Khuwair 25-A P053 25.0 20.0 14.4 13.7 14.5 13.8 14.8 13.9 14.8 13.9 Al Khuwair 25-B P053 25.0 20.0 14.5 13.7 14.6 13.8 14.9 13.9 14.9 13.9 Al Khuwair School-A P146 25.0 25.0 17.9 14.0 18.2 14.3 18.7 14.4 18.7 14.4 Al Khuwair School-B P146 25.0 25.0 17.9 14.0 18.3 14.3 18.7 14.4 18.7 14.4 Al Khuwair School-C P146 25.0 25.0 17.9 8.1 18.2 7.8 18.6 7.9 18.6 7.9 Digital TV Studio-A P039 25.0 18.4 16.7 12.9 17.0 13.0 17.4 13.1 17.4 13.0 Digital TV Studio-B P039 25.0 18.4 16.7 12.9 17.0 13.0 17.4 13.1 17.4 13.0 MSQ 1-A P083 25.0 20.0 20.2 14.0 20.6 14.1 21.2 14.2 21.2 14.1 MSQ 1-B P083 25.0 20.0 20.3 14.0 20.7 14.1 21.3 14.2 21.2 14.1 ROP Shati Al Qurum-A P111 25.0 18.4 16.2 15.4 16.4 15.5 16.8 15.6 16.8 15.6 ROP Shati Al Qurum-B P111 25.0 18.4 16.2 15.4 16.4 15.5 16.8 15.6 16.8 15.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 79 Qurum[G06] GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Information City 1 P037 20 15.6 6.4 16.9 84% 15.6 5.1 16.4 82% 15.6 5.1 16.4 82% 15.6 5.1 16.4 82% Lulai P095 20 11.7 6.2 13.2 66% 11.9 3.9 12.5 63% 11.9 3.9 12.5 63% 11.9 3.9 12.5 63% MSQ 2 P155 40 19.5 7.9 21.1 53% 25.1 8.3 26.4 66% 25.3 8.3 26.6 67% 25.3 8.3 26.6 67% Qurum 1 P093 16 13.3 3.9 13.9 87% 13.5 4.1 14.1 88% 13.5 4.1 14.1 88% 13.5 4.1 14.1 88% Qurum 2 P094 20 19.0 5.3 19.7 99% 19.3 5.3 20.0 100% 19.3 5.3 20.0 100% 19.3 5.3 20.0 100% Rabiat Al Qurum P096 20 11.1 5.0 12.2 61% 11.3 3.7 11.9 59% 11.3 3.7 11.9 59% 11.3 3.7 11.9 59% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Information City 1 P037 20 3.1 1.6 3.5 18% 2.7 1.4 3.0 15% 2.7 1.4 3.0 15% 2.7 1.4 3.0 15% Lulai P095 20 1.7 1.1 2.0 10% 1.9 1.2 2.3 11% 1.9 1.2 2.3 11% 1.9 1.2 2.3 11% MSQ 2 P155 40 3.3 1.2 3.5 9% 3.6 1.3 3.8 10% 3.6 1.3 3.9 10% 3.6 1.3 3.9 10% Qurum 1 P093 16 4.0 1.6 4.3 27% 2.4 0.9 2.6 16% 2.4 0.9 2.6 16% 2.4 0.9 2.6 16% Qurum 2 P094 20 3.7 2.2 4.3 22% 3.2 1.9 3.7 18% 3.2 1.9 3.7 18% 3.2 1.9 3.7 18% Rabiat Al Qurum P096 20 1.9 0.6 2.0 10% 2.1 0.7 2.2 11% 2.1 0.7 2.2 11% 2.1 0.7 2.2 11% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Information City 1-F1-P037 22.0 8.6 38.9 8.3 37.6 8.3 37.6 8.3 37.6 Information City 1-F2-P037 22.0 8.6 39.2 8.3 37.8 8.3 37.8 8.3 37.8 Lulai-F1-P095 22.0 6.8 30.8 6.4 29.1 6.4 29.1 6.4 29.1 Lulai-F2-P095 22.0 6.6 29.9 6.3 28.3 6.3 28.3 6.3 28.3 MSQ 02-F1-P155 22.0 6.0 27.1 9.0 40.7 9.0 41.0 9.1 41.0 MSQ 02-F2-P155 22.0 6.0 27.1 9.0 40.8 9.1 41.0 9.1 41.1 MSQ 02-F3-P155 22.0 9.5 43.0 9.0 40.8 9.0 41.0 9.1 41.1 Qurum 1-F1-P093 22.0 6.8 30.9 6.9 31.4 6.9 31.4 6.9 31.4 Qurum 1-F2-P093 22.0 7.1 32.4 7.3 32.9 7.3 32.9 7.3 32.9 Qurum 2-F1-P094 22.0 10.0 45.1 10.1 45.8 10.1 45.8 10.1 45.8 Qurum 2-F2-P094 22.0 10.2 46.4 10.4 47.1 10.4 47.1 10.4 47.1 Rabiat Al Qurum-F1-P096 22.0 6.3 28.3 6.1 27.5 6.1 27.5 6.1 27.5 Rabiat Al Qurum-F2-P096 22.0 6.2 28.1 6.0 27.2 6.0 27.2 6.0 27.2

MEDC Distribution System Capability Statement [2021-2023]-V2.0 80 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Information City 1-A P037 100.4 100.7 102.6 104.7 100.7 100.8 103.4 104.9 100.7 100.8 103.4 104.9 100.7 100.8 103.4 104.9 Information City 1-B P037 100.5 100.7 102.6 104.7 100.8 100.8 103.4 104.9 100.8 100.8 103.4 104.9 100.8 100.8 103.4 104.9 Lulai-A P095 100.7 100.7 103.0 104.9 100.9 100.8 104.0 105.0 100.9 100.8 104.0 105.0 100.9 100.8 104.0 105.0 Lulai-B P095 100.6 100.7 103.0 104.9 100.9 100.8 104.0 105.0 100.9 100.8 104.0 105.0 100.9 100.8 104.0 105.0 MSQ 2-A P155 100.6 100.7 103.6 105.1 100.7 100.8 103.2 105.1 100.7 100.8 103.2 105.0 100.7 100.8 103.2 105.0 MSQ 2-B P155 100.6 100.7 103.6 105.1 100.7 100.8 103.2 105.1 100.7 100.8 103.2 105.0 100.7 100.8 103.2 105.0 MSQ 2-C P155 100.5 100.7 102.5 104.9 100.7 100.8 103.2 105.1 100.7 100.8 103.2 105.0 100.7 100.8 103.2 105.0 Qurum 1-A P093 100.4 100.6 103.4 104.6 100.6 100.8 103.6 105.0 100.6 100.8 103.6 105.0 100.6 100.8 103.6 105.0 Qurum 1-B P093 100.5 100.6 103.4 104.6 100.7 100.8 103.6 105.0 100.7 100.8 103.6 105.0 100.7 100.8 103.6 105.0 Qurum 2-A P094 100.4 100.7 102.7 104.5 100.6 100.7 102.9 104.7 100.6 100.7 102.9 104.7 100.6 100.7 102.9 104.7 Qurum 2-B P094 100.5 100.7 102.7 104.5 100.7 100.8 102.9 104.7 100.7 100.8 102.9 104.7 100.7 100.8 102.9 104.7 Rabiat Al Qurum-A P096 100.7 100.7 103.4 105.1 101.0 100.8 104.1 105.1 101.0 100.8 104.1 105.1 101.0 100.8 104.1 105.1 Rabiat Al Qurum-B P096 100.7 100.7 103.4 105.1 101.0 100.8 104.1 105.1 101.0 100.8 104.1 105.1 101.0 100.8 104.1 105.1 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Information City 1-A P037 25.0 20.0 14.0 14.1 14.2 14.1 14.5 14.2 14.5 14.2 Information City 1-B P037 25.0 20.0 16.6 14.1 16.8 14.1 17.2 14.2 17.2 14.2 Lulai-A P095 25.0 18.4 19.0 13.7 19.4 13.7 19.9 13.8 19.9 13.8 Lulai-B P095 25.0 18.4 17.4 13.7 17.7 13.7 18.2 13.8 18.1 13.8 MSQ 2-A P155 25.0 25.0 15.7 13.7 15.9 14.2 16.3 14.3 16.3 14.3 MSQ 2-B P155 25.0 25.0 15.6 13.7 15.9 14.2 16.3 14.3 16.2 14.3 MSQ 2-C P155 25.0 25.0 15.7 7.9 15.9 7.9 16.3 7.9 16.3 7.9 Qurum 1-A P093 25.0 20.0 12.4 12.9 12.5 13.0 12.8 13.1 12.7 13.1 Qurum 1-B P093 25.0 20.0 13.5 12.9 13.7 13.0 14.0 13.1 14.0 13.1 Qurum 2-A P094 25.0 20.0 14.4 13.9 14.5 14.0 14.8 14.1 14.8 14.1 Qurum 2-B P094 25.0 20.0 15.8 13.9 16.0 14.0 16.4 14.1 16.4 14.1 Rabiat Al Qurum-A P096 25.0 18.4 20.5 13.9 20.9 13.9 21.5 14.0 21.5 14.0 Rabiat Al Qurum-B P096 25.0 18.4 20.5 13.9 20.8 13.9 21.5 14.0 21.4 14.0

MEDC Distribution System Capability Statement [2021-2023]-V2.0 81 Bousher[GP02] - A GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khuwair 17/1 P050 20 14.3 5.9 15.5 78% 14.8 4.9 15.6 78% 15.2 5.0 16.0 80% 15.2 5.0 16.0 80% Al Khuwair South P052 40 31.6 11.6 33.7 84% 32.7 10.7 34.4 86% 33.6 11.0 35.3 88% 33.6 11.0 35.3 88% Azaibah South 1-B P147 40 36.0 7.7 36.8 92% Shifted to Ghala Heights GSS Bousher Grid GP02 20 15.8 4.6 16.5 83% 17.3 5.2 18.0 90% 18.4 5.5 19.2 96% 19.5 5.9 20.4 102% Royal Hospital P024 40 20.3 8.0 21.8 55% Shifted to Ghala Heights GSS Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khuwair 17/1 P050 20 3.1 1.1 3.3 17% 2.7 1.0 2.8 14% 2.8 1.0 2.9 15% 2.8 1.0 2.9 15% Al Khuwair South P052 40 5.7 2.7 6.3 16% 5.7 2.7 6.3 16% 5.9 2.8 6.5 16% 5.9 2.8 6.5 16% Azaibah South 1-B P147 40 5.4 2.4 5.9 15% Shifted to Ghala Heights GSS Bousher Grid GP02 20 4.1 1.6 4.4 22% 3.1 1.2 3.3 17% 3.3 1.3 3.5 18% 3.5 1.4 3.7 19% Royal Hospital P024 40 5.5 2.4 6.0 15% Shifted to Ghala Heights GSS 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Khuwair 17/1-F1-P050 22.0 7.8 35.4 7.8 35.4 8.0 36.4 8.0 36.4 Al Khuwair 17/1-F2-P050 22.0 7.9 35.8 7.9 35.8 8.1 36.9 8.1 36.9 Al Khuwair South-F1-P052 22.0 10.1 46.0 11.7 53.4 12.1 54.9 12.1 54.9 Al Khuwair South-F2-P052 22.0 10.1 45.7 11.7 53.1 12.0 54.6 12.0 54.6 Al Khuwair South-F3-P052 22.0 14.2 64.8 11.7 53.2 12.0 54.7 12.0 54.8 Azaiba South 1B-F1-P147 22.0 13.1 59.4 ------Azaiba South 1B-F2-P147 22.0 13.2 59.8 ------Azaiba South 1B-F3-P147 22.0 11.1 50.1 ------Bousher G-F1-GP02 22.0 8.4 38.1 9.2 41.7 9.8 44.5 10.4 47.3 Bousher G-F2-GP02 22.0 8.4 37.9 9.2 41.5 9.8 44.2 10.4 47.1 Royal Hospital-F1-P024 22.0 5.3 23.9 ------Royal Hospital-F2-P024 22.0 11.4 51.6 ------Royal Hospital-F3-P024 22.0 5.4 24.3 ------Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Khuwair 17/1-A P050 100.7 100.5 103.1 104.7 100.0 100.8 102.7 105.0 99.9 100.7 102.5 105.0 99.9 100.7 102.5 105.0 Al Khuwair 17/1-B P050 100.7 100.5 103.1 104.7 100.0 100.8 102.7 105.0 99.9 100.7 102.5 105.0 99.9 100.7 102.5 105.0 Al Khuwair South-A P052 100.8 100.6 103.2 104.6 100.1 100.8 102.2 104.8 100.0 100.8 102.0 104.8 99.9 100.7 102.0 104.8 Al Khuwair South-B P052 100.8 100.6 103.2 104.6 100.1 100.8 102.2 104.8 100.0 100.8 102.0 104.8 99.9 100.7 102.0 104.8 Al Khuwair South-C P052 100.7 100.5 102.2 104.4 100.1 100.8 102.2 104.8 100.0 100.8 102.1 104.8 99.9 100.8 102.0 104.8 Azaiba South 1B-A P147 100.3 100.5 102.5 104.5 ------Azaiba South 1B-B P147 100.3 100.5 102.5 104.5 ------Azaiba South 1B-C P147 100.4 100.5 103.0 104.6 ------Bousher G-A GP02 100.9 100.6 103.7 104.6 100.2 100.8 102.8 105.0 100.1 100.8 102.6 104.9 100.1 100.8 102.4 104.9 Bousher G-B GP02 100.9 100.6 103.7 104.6 100.2 100.8 102.8 105.0 100.1 100.8 102.6 104.9 100.1 100.8 102.4 104.9 Royal Hospital-A P024 100.7 100.5 103.8 104.5 ------Royal Hospital-B P024 100.5 100.5 101.9 104.5 ------Royal Hospital-C P024 100.7 100.5 ------

MEDC Distribution System Capability Statement [2021-2023]-V2.0 82 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Khuwair 17/1-A P050 25.0 18.4 17.9 14.4 17.2 14.3 17.6 14.4 17.6 14.4 Al Khuwair 17/1-B P050 25.0 18.4 17.9 14.4 17.2 14.3 17.6 14.4 17.6 14.4 Al Khuwair South-A P052 25.0 25.0 20.9 16.7 20.0 16.8 20.5 16.9 20.5 16.9 Al Khuwair South-B P052 25.0 25.0 20.8 16.7 20.0 16.8 20.5 16.9 20.5 16.9 Al Khuwair South-C P052 25.0 25.0 21.0 9.8 20.0 9.5 20.6 9.6 20.6 9.6 Azaiba South 1B-A P147 25.0 25.0 14.1 14.5 ------Azaiba South 1B-B P147 25.0 25.0 14.1 14.5 ------Azaiba South 1B-C P147 25.0 25.0 13.8 7.8 ------Bousher G-A GP02 25.0 20.0 24.4 15.1 23.2 15.1 23.9 15.2 23.9 15.3 Bousher G-B GP02 25.0 20.0 24.4 15.1 23.2 15.1 23.9 15.2 23.9 15.3 Royal Hospital-A P024 25.0 20.0 16.4 13.6 ------Royal Hospital-B P024 25.0 20.0 16.4 8.0 ------Royal Hospital-C P024 25.0 - 16.4 ------

MEDC Distribution System Capability Statement [2021-2023]-V2.0 83 Bousher[GP02] - B GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Ansab 1 P007 20 18.1 7.2 19.5 97% Shifted to Ghala Heights GSS Al Muna P084 20 17.4 6.9 18.7 94% 19.0 6.3 20.0 100% 20.3 6.7 21.3 107% 21.6 7.1 22.7 113% Azaibah North 1 P011 20 17.2 5.8 18.2 91% 17.8 5.9 18.8 94% 18.0 5.9 18.9 95% 18.0 5.9 18.9 95% Bousher 2 P163 40 26.0 8.3 27.3 68% 28.4 9.1 29.8 75% 30.2 9.7 31.7 79% 32.2 10.3 33.8 84% Ghubrah South 1 P026 40 27.1 11.8 29.6 74% Shifted to Ghala Heights GSS Holiday Inn P051 40 27.3 9.0 28.7 72% 28.2 9.2 29.7 74% 29.0 9.4 30.5 76% 29.0 9.4 30.5 76% Tilal Al Khuwair P055 40 27.9 11.3 30.1 75% 28.8 9.5 30.4 76% 29.6 9.7 31.2 78% 29.6 9.7 31.2 78% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Ansab 1 P007 20 2.5 1.0 2.7 14% Shifted to Ghala Heights GSS Al Muna P084 20 3.5 2.3 4.2 21% 3.1 2.0 3.7 18% 3.3 2.2 3.9 20% 3.5 2.3 4.2 21% Azaibah North 1 P011 20 2.9 0.8 3.0 15% 3.3 0.9 3.4 17% 3.3 0.9 3.5 17% 3.3 0.9 3.5 17% Bousher 2 P163 40 1.5 0.6 1.6 4% 5.1 1.9 5.5 14% 5.4 2.0 5.8 15% 5.8 2.2 6.2 15% Ghubrah South 1 P026 40 5.3 2.8 6.0 15% Shifted to Ghala Heights GSS Holiday Inn P051 40 6.2 3.5 7.1 18% 5.0 2.8 5.7 14% 5.1 2.9 5.9 15% 5.1 2.9 5.9 15% Tilal Al Khuwair P055 40 27.9 11.3 30.1 75% 28.8 9.5 30.4 76% 29.6 9.7 31.2 78% 29.6 9.7 31.2 78% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Ansab 1-F1-P007 22.0 11.8 53.7 ------Al Ansab 1-F2-P007 22.0 12.0 54.3 ------Al Muna-F1-P084 22.0 9.6 43.4 10.3 46.5 11.0 49.6 11.6 52.5 Al Muna-F2-P084 22.0 9.4 42.6 10.1 45.6 10.7 48.7 11.6 52.5 Azaiba North 1-F1-P011 22.0 9.1 41.4 9.5 42.9 9.6 43.3 9.6 43.3 Azaiba North 1-F2-P011 22.0 9.1 41.4 9.5 42.9 9.6 43.3 9.6 43.3 Bousher 2-F1-P163 22.0 7.8 35.5 10.2 46.2 10.9 49.2 11.6 52.5 Bousher 2-F2-P163 22.0 7.8 35.4 10.2 46.2 10.9 49.2 11.6 52.5 Bousher 2-F3-P163 22.0 12.4 56.0 10.2 46.2 10.9 49.2 11.6 52.5 Ghubrah South 1-F1-P026 22.0 8.8 39.8 ------Ghubrah South 1-F2-P026 22.0 8.7 39.4 ------Ghubrah South 1-F3-P026 22.0 12.5 56.5 ------Holiday Inn-F1-P051 22.0 9.0 40.8 10.7 48.5 11.0 49.9 11.0 49.9 Holiday Inn-F2-P051 22.0 8.9 40.3 10.6 47.9 10.9 49.2 10.9 49.2 Holiday Inn-F3-P051 22.0 13.0 59.0 10.6 48.2 10.9 49.6 10.9 49.6 Tilal Al Khuwair-F1-P055 22.0 9.2 41.8 10.5 47.6 10.8 49.0 10.8 49.0 Tilal Al Khuwair-F2-P055 22.0 8.9 40.3 10.1 46.0 10.4 47.3 10.4 47.3 Tilal Al Khuwair-F3-P055 22.0 12.7 57.4 10.3 46.8 10.6 48.2 10.6 48.2

MEDC Distribution System Capability Statement [2021-2023]-V2.0 84 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Ansab 1-A P007 99.4 100.3 100.6 104.5 ------Al Ansab 1-B P007 99.4 100.3 100.6 104.5 ------Al Muna-A P084 99.9 100.3 101.7 104.0 100.8 100.5 102.9 104.3 100.5 100.4 102.4 104.2 100.4 100.4 102.1 104.1 Al Muna-B P084 99.9 100.3 101.7 104.0 100.8 100.5 102.9 104.3 100.5 100.4 102.4 104.2 100.4 100.4 102.0 104.1 Azaiba North 1-A P011 99.9 100.3 102.2 104.6 100.8 100.5 103.1 104.7 100.5 100.4 102.8 104.7 100.4 100.4 102.7 104.7 Azaiba North 1-B P011 99.9 100.3 102.2 104.6 100.8 100.5 103.1 104.7 100.5 100.4 102.8 104.7 100.4 100.4 102.7 104.7 Bousher 2-A P163 100.2 100.3 102.9 104.8 101.1 100.5 103.3 104.6 100.9 100.5 102.9 104.6 100.7 100.5 102.5 104.5 Bousher 2-B P163 100.2 100.3 102.9 104.8 101.1 100.5 103.3 104.6 100.9 100.5 102.9 104.6 100.7 100.5 102.5 104.5 Bousher 2-C P163 100.2 100.3 101.8 104.7 101.1 100.5 103.3 104.6 100.9 100.5 102.9 104.6 100.7 100.5 102.5 104.5 Ghubrah South 1-A P026 100.0 100.3 102.4 104.4 ------Ghubrah South 1-B P026 100.0 100.3 102.4 104.4 ------Ghubrah South 1-C P026 99.9 100.3 101.4 104.1 ------Holiday Inn-A P051 100.2 100.3 102.5 104.2 101.1 100.5 103.1 104.4 100.8 100.5 102.7 104.4 100.7 100.5 102.6 104.3 Holiday Inn-B P051 100.2 100.3 102.5 104.2 101.0 100.5 103.1 104.4 100.8 100.5 102.7 104.4 100.7 100.4 102.6 104.3 Holiday Inn-C P051 100.1 100.3 101.4 103.8 101.1 100.5 103.0 104.4 100.8 100.5 102.7 104.4 100.7 100.5 102.5 104.3 Tilal Al Khuwair-A P055 100.2 100.3 102.3 104.3 101.1 100.5 103.2 104.6 100.9 100.5 102.9 104.6 100.7 100.5 102.8 104.6 Tilal Al Khuwair-B P055 100.2 100.3 102.3 104.3 101.1 100.5 103.2 104.6 100.9 100.5 102.9 104.6 100.7 100.5 102.8 104.6 Tilal Al Khuwair-C P055 100.1 100.3 101.1 104.0 101.1 100.5 103.2 104.6 100.9 100.5 102.9 104.6 100.7 100.5 102.7 104.6 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Ansab 1-A P007 25.0 20.0 12.4 14.3 ------Al Ansab 1-B P007 25.0 20.0 12.4 14.3 ------Al Muna-A P084 25.0 20.0 15.8 14.2 15.4 14.2 15.7 14.3 15.5 8.0 Al Muna-B P084 25.0 20.0 15.8 14.2 15.4 14.2 15.7 14.3 15.6 7.9 Azaiba North 1-A P011 25.0 20.0 14.8 14.3 14.5 14.3 14.7 14.4 14.8 14.4 Azaiba North 1-B P011 25.0 20.0 14.8 14.3 14.5 14.3 14.7 14.4 14.8 14.4 Bousher 2-A P163 25.0 25.0 22.3 14.8 21.5 15.1 22.1 15.3 22.2 15.4 Bousher 2-B P163 25.0 25.0 22.3 14.8 21.5 15.1 22.1 15.3 22.2 15.4 Bousher 2-C P163 25.0 25.0 22.3 8.6 21.5 8.4 22.1 8.4 22.1 8.5 Ghubrah South 1-A P026 25.0 18.4 17.6 16.2 ------Ghubrah South 1-B P026 25.0 18.4 17.7 16.2 ------Ghubrah South 1-C P026 25.0 18.4 17.5 9.3 ------Holiday Inn-A P051 25.0 20.0 20.7 14.6 20.0 14.7 20.5 14.8 20.6 14.9 Holiday Inn-B P051 25.0 20.0 20.5 14.6 19.8 14.7 20.4 14.8 20.4 14.9 Holiday Inn-C P051 25.0 20.0 20.7 8.3 20.0 8.1 20.5 8.1 20.6 8.1 Tilal Al Khuwair-A P055 25.0 25.0 21.5 14.9 20.7 15.0 21.3 15.1 21.3 15.1 Tilal Al Khuwair-B P055 25.0 25.0 21.5 14.9 20.7 15.0 21.3 15.1 21.3 15.1 Tilal Al Khuwair-C P055 25.0 25.0 21.5 8.4 20.7 8.2 21.3 8.2 21.3 8.2

MEDC Distribution System Capability Statement [2021-2023]-V2.0 85 Ghala Heights[G24] GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Ansab 1 P007 20 - - - - 18.9 6.2 19.9 99% 19.4 6.4 20.4 102% 19.7 6.5 20.8 104% Azaibah South 1-A P014 20 - - - - 15.9 5.2 16.7 84% 16.0 5.3 16.8 84% 16.0 5.3 16.8 84% Azaibah South 1-B P147 40 - - - - 37.3 12.3 39.3 98% 37.6 12.4 39.6 99% 37.6 12.4 39.6 99% Ghala 3 P189 40 ------16.1 5.3 16.9 42% Ghubrah South 1 P026 40 - - - - 27.6 9.1 29.0 73% 27.9 9.2 29.4 73% 27.9 9.2 29.4 73% Mall Of Oman P171 40 6.9 1.7 7.1 18% 6.9 1.7 7.1 18% 16.9 4.1 17.4 43% 16.9 4.1 17.4 43% Royal Hospital P024 40 - - - - 20.6 6.8 21.7 54% 20.9 6.9 22.0 55% 20.9 6.9 22.0 55% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Ansab 1 P007 20 - - - - 4.0 1.7 4.4 22% 4.1 1.7 4.5 22% 4.2 1.7 4.6 23% Azaibah South 1-A P014 20 - - - - 2.6 1.6 3.1 15% 2.6 1.6 3.1 15% 2.6 1.6 3.1 15% Azaibah South 1-B P147 40 - - - - 6.6 2.9 7.2 18% 6.6 2.9 7.2 18% 6.6 2.9 7.2 18% Ghala 3 P189 40 ------2.8 1.4 3.1 8% Ghubrah South 1 P026 40 - - - - 4.7 2.5 5.3 13% 4.7 2.5 5.4 13% 4.7 2.5 5.4 13% Mall Of Oman P171 40 1.2 0.5 1.3 3% 1.2 0.5 1.3 3% 3.0 1.2 3.2 8% 3.0 1.2 3.2 8% Royal Hospital P024 40 - - - - 3.6 1.6 4.0 10% 3.7 1.6 4.0 10% 3.7 1.6 4.0 10% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Ansab 1-F1-P007 22.0 - - 10.1 45.7 10.4 46.9 10.5 47.8 Al Ansab 1-F2-P007 22.0 - - 10.1 45.7 10.4 46.9 10.5 47.8 Azaiba South 1A-F1-P014 22.0 - - 8.5 38.3 8.5 38.6 8.5 38.6 Azaiba South 1A-F2-P014 22.0 - - 8.5 38.3 8.5 38.6 8.5 38.6 Azaiba South 1B-F1-P147 22.0 - - 13.4 60.9 13.5 61.4 13.5 61.4 Azaiba South 1B-F2-P147 22.0 - - 13.5 61.3 13.6 61.8 13.6 61.8 Azaiba South 1B-F3-P147 22.0 - - 13.5 61.1 13.6 61.6 13.6 61.6 Ghala 3-F1-P189 22.0 ------5.7 25.8 Ghala 3-F2-P189 22.0 ------5.7 25.8 Ghala 3-F3-P189 22.0 ------5.7 25.8 Ghubrah South 1-F1-P026 22.0 - - 9.8 44.5 9.9 45.1 9.9 45.1 Ghubrah South 1-F2-P026 22.0 - - 9.7 44.1 9.9 44.6 9.9 44.6 Ghubrah South 1-F3-P026 22.0 - - 9.8 44.3 9.9 44.8 9.9 44.8 Mall of Oman-F1-P171 22.0 2.1 9.6 2.3 10.6 9.6 43.3 9.7 43.9 Mall of Oman-F2-P171 22.0 2.1 9.6 2.3 10.5 9.5 43.3 9.7 43.9 Mall of Oman-F3-P171 22.0 2.7 12.4 2.3 10.6 9.6 43.4 9.7 44.0 Royal Hospital-F1-P024 22.0 - - 5.3 24.2 5.4 24.5 5.4 24.5 Royal Hospital-F2-P024 22.0 - - 11.1 50.2 11.2 50.8 11.2 50.8 Royal Hospital-F3-P024 22.0 - - 5.4 24.7 5.5 25.0 5.5 25.0

MEDC Distribution System Capability Statement [2021-2023]-V2.0 86 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Ansab 1-A P007 - - - - 99.6 99.9 101.6 103.9 99.5 99.9 101.6 103.9 99.5 99.9 101.5 103.9 Al Ansab 1-B P007 - - - - 99.6 99.9 101.7 103.9 99.5 99.9 101.6 103.9 99.5 99.9 101.5 103.9 Azaiba South 1A-A P014 - - - - 99.7 100.0 102.2 103.9 99.7 100.0 102.2 103.9 99.7 100.0 102.2 103.9 Azaiba South 1A-B P014 - - - - 99.7 100.0 102.2 103.9 99.7 100.0 102.2 103.9 99.7 100.0 102.2 103.9 Azaiba South 1B-A P147 - - - - 99.6 99.9 100.7 103.8 99.6 99.9 100.7 103.8 99.6 99.9 100.7 103.8 Azaiba South 1B-B P147 - - - - 99.6 99.9 100.7 103.8 99.6 99.9 100.7 103.8 99.6 99.9 100.7 103.8 Azaiba South 1B-C P147 - - - - 99.6 99.9 100.7 103.8 99.6 99.9 100.7 103.8 99.6 99.9 100.7 103.8 Ghala 3-A P189 ------99.9 100.0 103.1 104.2 Ghala 3-B P189 ------99.9 100.0 103.1 104.2 Ghala 3-C P189 ------99.9 100.0 103.1 104.2 Ghubrah South 1-A P026 - - - - 99.7 99.9 102.2 104.0 99.7 99.9 102.2 104.0 99.7 99.9 102.2 104.0 Ghubrah South 1-B P026 - - - - 99.7 99.9 102.2 104.0 99.7 99.9 102.2 104.0 99.7 99.9 102.2 104.0 Ghubrah South 1-C P026 - - - - 99.7 99.9 102.2 104.0 99.7 99.9 102.2 104.0 99.7 99.9 102.2 104.0 Mall of Oman-A P171 99.9 100.0 104.1 104.4 99.9 100.0 104.0 104.4 99.7 100.0 101.9 104.2 99.7 100.0 101.6 104.2 Mall of Oman-B P171 99.9 100.0 104.1 104.4 99.9 100.0 104.0 104.4 99.7 100.0 101.9 104.2 99.7 100.0 101.6 104.2 Mall of Oman-C P171 99.9 100.0 103.9 104.4 99.9 100.0 104.0 104.4 99.7 100.0 101.8 104.2 99.7 100.0 101.6 104.2 Royal Hospital-A P024 - - - - 99.8 100.0 103.0 104.2 99.8 100.0 103.0 104.2 99.8 100.0 103.0 104.2 Royal Hospital-B P024 - - - - 99.5 99.9 101.3 103.9 99.5 99.9 101.2 103.9 99.5 99.9 101.2 103.9 Royal Hospital-C P024 - - - - 99.8 100.0 - - 99.8 100.0 - - 99.8 100.0 - - Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Ansab 1-A P007 25.0 20.0 - - 14.7 7.9 15.0 7.9 14.8 7.9 Al Ansab 1-B P007 25.0 20.0 - - 14.7 8.0 15.0 8.0 14.8 8.0 Azaiba South 1A-A P014 25.0 18.4 - - 16.7 14.1 17.1 14.2 16.9 14.1 Azaiba South 1A-B P014 25.0 18.4 - - 16.7 14.1 17.1 14.2 16.9 14.1 Azaiba South 1B-A P147 25.0 25.0 - - 16.8 14.9 17.1 15.0 16.9 14.9 Azaiba South 1B-B P147 25.0 25.0 - - 16.8 14.9 17.1 15.0 16.9 14.9 Azaiba South 1B-C P147 25.0 25.0 - - 16.7 8.2 17.0 8.2 16.8 8.2 Ghala 3-A P189 25.0 25.0 ------20.3 13.9 Ghala 3-B P189 25.0 25.0 ------20.3 13.9 Ghala 3-C P189 25.0 25.0 ------20.3 7.7 Ghubrah South 1-A P026 25.0 18.4 - - 16.1 16.0 16.4 16.1 16.2 16.1 Ghubrah South 1-B P026 25.0 18.4 - - 16.1 16.0 16.4 16.1 16.2 16.1 Ghubrah South 1-C P026 25.0 18.4 - - 15.9 9.0 16.3 9.0 16.1 9.0 Mall of Oman-A P171 25.0 25.0 14.2 12.8 14.4 12.9 15.6 21.0 15.2 20.8 Mall of Oman-B P171 25.0 25.0 14.3 12.8 14.5 12.9 15.6 21.0 15.2 20.8 Mall of Oman-C P171 25.0 25.0 14.3 7.3 14.5 7.2 15.6 20.6 15.2 20.4 Royal Hospital-A P024 25.0 20.0 - - 14.9 13.4 15.2 13.5 15.0 13.4 Royal Hospital-B P024 25.0 20.0 - - 14.8 7.8 15.1 7.9 15.0 7.9 Royal Hospital-C P024 25.0 - - - 14.9 - 15.2 - 15.1 -

MEDC Distribution System Capability Statement [2021-2023]-V2.0 87 Ghala[G11] - A GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Ansab 2 P008 20 17.8 7.0 19.1 96% Shifted to Ghala-B GSS Al Ansab STP P009 20 9.8 3.9 10.6 53% 9.8 3.9 10.6 53% 9.8 3.9 10.6 53% 9.8 3.9 10.6 53% Ghala 1 P015 40 15.0 5.9 16.1 40% 26.5 8.7 27.9 70% 26.7 8.8 28.1 70% 26.7 8.8 28.1 70% Ghala 2 P156 40 29.2 13.0 32.0 80% Shifted to Ghala-B GSS MOD Al Ansab P167 10 8.3 3.3 8.9 89% 8.3 3.3 8.9 89% 8.3 3.3 8.9 89% 8.3 3.3 8.9 89% Oman Exhibition P165 40 10.7 2.6 11.0 28% 17.7 4.2 18.2 45% 17.7 4.2 18.2 45% 17.7 4.2 18.2 45% ROP Hospital P172 40 ------10.0 3.3 10.5 26% 10.0 3.3 10.5 26% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Ansab 2 P008 20 2.4 0.7 2.5 13% Shifted to Ghala-B GSS Al Ansab STP P009 20 0.1 0.1 0.1 1% 1.8 0.7 1.9 10% 1.8 0.7 1.9 10% 1.8 0.7 1.9 10% Ghala 1 P015 40 2.2 1.0 2.4 6% 4.5 2.0 4.9 12% 4.5 2.0 4.9 12% 4.5 2.0 4.9 12% Ghala 2 P156 40 4.6 2.6 5.3 13% Shifted to Ghala-B GSS MOD Al Ansab P167 10 1.0 0.4 1.1 11% 1.5 0.6 1.6 16% 1.5 0.6 1.6 16% 1.5 0.6 1.6 16% Oman Exhibition P165 40 1.7 0.0 1.7 4% 3.3 0.0 3.3 8% 3.3 0.0 3.3 8% 3.3 0.0 3.3 8% ROP Hospital P172 40 ------1.8 0.7 1.9 5% 1.8 0.7 1.9 5% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Ansab 2-F1-P008 22.0 9.6 43.7 ------Ansab 2-F2-P008 22.0 9.7 43.9 ------Ansab STP-F1-P009 22.0 5.3 24.0 5.3 24.0 5.3 24.0 5.3 24.0 Ansab STP-F2-P009 22.0 5.3 23.9 5.3 23.9 5.3 23.9 5.3 23.9 Ghala 1-F1-P015 22.0 5.2 23.5 9.3 42.2 9.4 42.5 9.4 42.5 Ghala 1-F2-P015 22.0 5.2 23.5 9.3 42.3 9.4 42.6 9.4 42.6 Ghala 1-F3-P015 22.0 5.3 23.9 9.4 42.5 9.4 42.8 9.4 42.8 Ghala 2-F1-P156 22.0 10.8 49.0 ------Ghala 2-F2-P156 22.0 10.8 49.0 ------Ghala 2-F3-P156 22.0 10.9 49.6 ------MOD Lansab-F1-P167 22.0 4.3 19.6 4.3 19.6 4.3 19.6 4.3 19.6 MOD Lansab-F2-P167 22.0 4.4 19.9 4.4 19.9 4.4 19.9 4.4 19.9 Oman Exhibition-F1-P165 22.0 5.9 26.9 9.3 42.1 9.3 42.1 9.3 42.1 Oman Exhibition-F2-P165 22.0 0.0 0.1 4.6 20.8 4.6 20.8 4.6 20.8 Oman Exhibition-F3-P165 22.0 5.3 23.8 4.6 20.9 4.6 20.9 4.6 20.9 ROP Hospital-F1-P172 22.0 - - - - 3.4 15.6 3.4 15.6 ROP Hospital-F2-P172 22.0 - - - - 3.4 15.6 3.4 15.6 ROP Hospital-F3-P172 22.0 - - - - 3.4 15.6 3.4 15.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 88 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Ansab 2-A P008 100.1 100.1 101.8 104.3 ------Ansab 2-B P008 100.0 100.1 101.8 104.3 ------Ansab STP-A P009 100.5 100.1 103.7 104.6 100.2 101.1 103.4 105.4 100.3 100.0 103.5 104.3 100.3 100.0 103.5 104.3 Ansab STP-B P009 100.5 100.1 103.7 104.6 100.2 101.1 103.4 105.4 100.3 100.0 103.5 104.3 100.3 100.0 103.5 104.3 Ghala 1-A P015 100.2 100.1 103.2 104.4 99.5 101.0 101.7 105.1 99.6 99.9 101.8 104.0 99.6 99.9 101.8 104.0 Ghala 1-B P015 100.2 100.1 103.2 104.4 99.5 101.0 101.7 105.1 99.6 99.9 101.8 104.0 99.6 99.9 101.8 104.0 Ghala 1-C P015 100.4 100.1 103.5 104.4 99.8 101.0 102.2 105.2 99.9 99.9 102.2 104.0 99.9 99.9 102.2 104.0 Ghala 2-A P156 99.9 100.0 101.1 104.0 ------Ghala 2-B P156 99.9 100.0 101.1 104.0 ------Ghala 2-C P156 99.9 100.0 101.0 104.0 ------MOD Lansab-A P167 100.4 100.1 103.4 104.5 100.1 101.1 103.1 105.4 100.2 100.0 103.2 104.2 100.2 100.0 103.2 104.2 MOD Lansab-B P167 100.4 100.1 103.4 104.5 100.1 101.1 103.1 105.4 100.2 100.0 103.2 104.2 100.2 100.0 103.2 104.2 Oman Exhibition-A P165 100.6 100.1 104.1 104.6 100.3 101.1 103.1 105.6 100.4 100.0 103.1 104.4 100.4 100.0 103.1 104.4 Oman Exhibition-B P165 100.6 100.1 104.2 104.6 100.3 101.1 104.0 105.6 100.4 100.0 104.1 104.5 100.4 100.0 104.1 104.5 Oman Exhibition-C P165 100.6 100.1 - - 100.3 101.1 - - 100.4 100.0 - - 100.4 100.0 - - ROP Hospital-A P172 ------100.3 100.0 104.0 104.4 100.3 100.0 104.0 104.4 ROP Hospital-B P172 ------100.3 100.0 104.0 104.4 100.3 100.0 104.0 104.4 ROP Hospital-C P172 ------100.3 100.0 104.0 104.4 100.3 100.0 104.0 104.4 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Ansab 2-A P008 25.0 20.0 12.4 13.4 ------Ansab 2-B P008 25.0 20.0 12.4 13.4 ------Ansab STP-A P009 25.0 18.4 16.9 13.7 16.9 13.7 17.9 13.9 17.9 13.9 Ansab STP-B P009 25.0 18.4 16.9 13.7 16.9 13.7 17.9 13.9 17.9 13.9 Ghala 1-A P015 25.0 20.0 10.3 12.3 10.4 12.9 10.7 13.1 10.7 13.1 Ghala 1-B P015 25.0 20.0 10.3 12.3 10.4 12.9 10.7 13.1 10.7 13.1 Ghala 1-C P015 25.0 25.0 12.6 7.4 12.6 7.7 13.1 7.8 13.1 7.8 Ghala 2-A P156 25.0 25.0 11.9 13.7 ------Ghala 2-B P156 25.0 25.0 11.8 13.7 ------Ghala 2-C P156 25.0 25.0 11.6 7.6 ------MOD Lansab-A P167 25.0 25.0 12.6 10.9 12.6 10.9 13.1 11.0 13.1 11.0 MOD Lansab-B P167 25.0 25.0 12.9 10.9 12.9 10.9 13.4 11.0 13.4 11.0 Oman Exhibition-A P165 25.0 25.0 20.5 7.9 20.5 8.1 22.1 8.2 22.0 8.2 Oman Exhibition-B P165 25.0 25.0 20.5 7.9 20.5 13.9 22.1 14.1 22.0 14.1 Oman Exhibition-C P165 25.0 25.0 20.5 - 20.5 - 22.1 - 22.0 - ROP Hospital-A P172 25.0 25.0 - - - - 15.6 13.0 15.6 13.0 ROP Hospital-B P172 25.0 25.0 - - - - 15.6 13.0 15.6 13.0 ROP Hospital-C P172 25.0 25.0 - - - - 15.5 7.2 15.5 7.2

MEDC Distribution System Capability Statement [2021-2023]-V2.0 89 Ghala[G11] - B GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Ansab 2 P008 20 - - - - 18.6 6.1 19.5 98% 19.0 6.3 20.0 100% 19.4 6.4 20.4 102% Ghala 2 P156 40 - - - - 30.5 10.0 32.1 80% 31.2 10.3 32.9 82% 31.8 10.5 33.5 84% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Ansab 2 P008 20 - - - - 3.4 1.0 3.6 18% 3.5 1.0 3.7 18% 3.6 1.0 3.7 19% Ghala 2 P156 40 - - - - 5.1 2.9 5.9 15% 5.2 3.0 6.0 15% 5.3 3.0 6.1 15% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Ansab 2-F1-P008 22.0 - - 9.8 44.6 10.1 45.7 10.3 46.6 Ansab 2-F2-P008 22.0 - - 9.9 44.9 10.2 46.0 10.4 46.9 Ghala 2-F1-P156 22.0 - - 10.8 49.0 11.1 50.2 11.3 51.3 Ghala 2-F2-P156 22.0 - - 10.8 49.1 11.1 50.3 11.3 51.3 Ghala 2-F3-P156 22.0 - - 10.8 49.0 11.1 50.3 11.3 51.3 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Ansab 2-A P008 - - - - 99.5 101.0 101.5 105.2 100.3 101.0 102.4 105.2 100.3 101.0 102.3 105.1 Ansab 2-A P008 - - - - 99.5 101.0 101.5 105.2 100.3 101.0 102.4 105.2 100.3 101.0 102.3 105.1 Ghala 2-A P156 - - - - 99.4 101.0 101.2 104.9 100.2 100.9 102.1 104.8 100.1 100.9 101.9 104.8 Ghala 2-B P156 - - - - 99.4 101.0 101.2 104.9 100.2 100.9 102.1 104.8 100.1 100.9 101.9 104.8 Ghala 2-C P156 - - - - 99.6 101.0 101.5 104.9 100.2 100.9 102.1 104.8 100.1 100.9 101.9 104.8 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Ansab 2-A P008 25.0 20.0 - - 12.2 13.3 12.9 13.6 12.9 13.6 Ansab 2-A P008 25.0 20.0 - - 12.2 13.3 12.9 13.6 12.9 13.6 Ghala 2-A P156 25.0 25.0 - - 11.7 13.6 12.2 13.9 12.2 14.0 Ghala 2-B P156 25.0 25.0 - - 11.7 13.6 12.2 13.9 12.2 14.0 Ghala 2-C P156 25.0 25.0 - - 11.6 7.6 12.0 7.7 12.0 7.7

MEDC Distribution System Capability Statement [2021-2023]-V2.0 90 Airport Heights [G01] - A GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Airport Height 1 P001 20 13.3 7.1 15.1 76% 13.6 4.5 14.3 71% 13.9 4.6 14.7 73% 13.9 4.6 14.7 73% Airport Height 2 P002 20 14.0 4.7 14.8 74% 14.3 4.7 15.0 75% 14.7 4.8 15.4 77% 14.7 4.8 15.4 77% Airport Height 3 P003 20 10.9 4.1 11.6 58% 11.1 3.7 11.7 59% 11.4 3.8 12.0 60% 11.4 3.8 12.0 60% Airport Height 4 P004 20 5.8 1.9 6.1 31% 5.9 1.9 6.2 31% 6.1 2.0 6.4 32% 6.1 2.0 6.4 32% Airport Height 5 P151 20 11.4 4.4 12.2 61% 11.6 3.8 12.2 61% 11.9 3.9 12.6 63% 11.9 3.9 12.6 63% Azaibah North 3 P013 40 29.0 9.6 30.5 76% Shifted to Airport Heights-B GSS MOD Technical College P081 20 7.9 3.0 8.5 43% 7.9 2.6 8.3 42% 7.9 2.6 8.3 42% 7.9 2.6 8.3 42% ROP Hospital P172 1TX 2.2 0.9 2.3 - 2.2 0.9 2.3 - The temporary supply will be dismantled Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Airport Height 1 P001 20 3.0 1.4 3.3 17% 2.4 1.1 2.6 13% 2.4 1.1 2.7 13% 2.4 1.1 2.7 13% Airport Height 2 P002 20 3.1 0.8 3.2 16% 2.7 0.7 2.8 14% 2.7 0.7 2.8 14% 2.7 0.7 2.8 14% Airport Height 3 P003 20 2.2 0.0 2.2 11% 2.1 0.0 2.1 11% 2.2 0.0 2.2 11% 2.2 0.0 2.2 11% Airport Height 4 P004 20 1.0 0.0 1.0 5% 1.1 0.0 1.1 6% 1.2 0.0 1.2 6% 1.2 0.0 1.2 6% Airport Height 5 P151 20 1.0 0.5 1.1 6% 2.0 0.9 2.2 11% 2.1 1.0 2.3 12% 2.1 1.0 2.3 12% Azaibah North 3 P013 40 5.1 1.8 5.4 14% Shifted to Airport Heights-B GSS MOD Technical College P081 20 1.1 0.5 1.2 6% 1.4 0.6 1.5 8% 1.4 0.6 1.5 8% 1.4 0.6 1.5 8% ROP Hospital P172 1TX 0.3 0.1 0.3 - 0.4 0.2 0.4 - The temporary supply will be dismantled 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Airport Height 1-F1-P001 22.0 7.6 34.5 7.2 32.5 7.4 33.4 7.4 33.4 Airport Height 1-F2-P001 22.0 7.6 34.5 7.2 32.5 7.4 33.4 7.4 33.4 Airport Height 2-F1-P002 22.0 7.5 33.9 7.7 34.7 7.9 35.6 7.9 35.6 Airport Height 2-F2-P002 22.0 7.4 33.3 7.5 34.1 7.7 35.0 7.7 35.0 Airport Height 3-F1-P003 22.0 5.8 26.4 5.9 26.7 6.1 27.4 6.1 27.4 Airport Height 3-F2-P003 22.0 5.7 25.8 5.8 26.1 5.9 26.8 5.9 26.8 Airport Height 4-F1-P004 22.0 3.1 14.1 3.1 14.2 3.2 14.6 3.2 14.6 Airport Height 4-F2-P004 22.0 3.0 13.6 3.0 13.7 3.1 14.1 3.1 14.1 Airport Height 5-F1-P151 22.0 6.1 27.6 6.1 27.6 6.3 28.4 6.3 28.4 Airport Height 5-F2-P151 22.0 6.1 27.5 6.1 27.5 6.2 28.3 6.2 28.3 Azaiba North 3-F1-P013 22.0 11.3 51.3 ------Azaiba North 3-F2-P013 22.0 11.6 52.7 ------Azaiba North 3-F3-P013 22.0 7.8 35.6 ------MOD Technical College-F1-P081 22.0 4.3 19.3 4.2 18.9 4.2 18.9 4.2 18.9 MOD Technical College-F2-P081 22.0 4.3 19.4 4.2 19.0 4.2 19.0 4.2 19.0 ROP Hospital--P172 22.0 2.3 10.4 2.3 10.4 - - - -

MEDC Distribution System Capability Statement [2021-2023]-V2.0 91 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Airport Height 1-A P001 100.5 99.9 102.4 103.5 100.6 101.0 102.4 104.8 100.6 100.8 103.4 104.0 100.6 101.0 103.4 104.8 Airport Height 1-B P001 100.5 100.0 102.4 103.5 100.6 101.1 102.4 104.8 100.6 100.9 103.4 104.0 100.6 101.1 103.4 104.8 Airport Height 2-A P002 100.6 100.0 103.3 103.9 100.6 101.1 103.3 105.1 100.6 100.9 103.2 104.5 100.6 101.1 103.2 105.1 Airport Height 2-B P002 100.6 99.9 103.3 103.9 100.6 101.0 103.3 105.1 100.6 100.8 103.2 104.5 100.6 101.0 103.2 105.1 Airport Height 3-A P003 100.5 100.0 103.7 104.5 100.6 101.1 103.7 105.6 100.6 100.9 103.8 105.3 100.6 101.1 103.8 105.6 Airport Height 3-B P003 100.5 100.0 103.7 104.5 100.6 101.1 103.7 105.6 100.6 100.8 103.8 105.3 100.6 101.1 103.8 105.6 Airport Height 4-A P004 100.7 100.0 104.5 104.5 100.8 101.1 104.5 105.7 100.8 100.9 104.6 105.4 100.8 101.1 104.6 105.6 Airport Height 4-B P004 100.7 100.0 104.5 104.5 100.8 101.1 104.5 105.7 100.8 100.9 104.6 105.4 100.8 101.1 104.6 105.6 Airport Height 5-A P151 100.5 100.0 103.3 104.2 100.5 101.1 103.3 104.9 100.5 100.9 103.5 104.2 100.5 101.1 103.5 104.9 Airport Height 5-B P151 100.5 100.0 103.3 104.2 100.5 101.0 103.3 104.9 100.5 100.7 103.5 104.2 100.5 101.0 103.5 104.9 Azaiba North 3-A P013 99.9 99.7 101.6 103.2 ------Azaiba North 3-B P013 99.8 100.1 101.6 103.2 ------Azaiba North 3-C P013 100.2 100.0 102.8 104.2 ------MOD Technical College-A P081 100.7 100.0 104.2 104.2 100.8 101.1 104.2 105.3 100.8 100.9 104.4 104.8 100.8 101.1 104.4 105.3 MOD Technical College-B P081 100.7 100.0 104.2 104.2 100.8 101.1 104.2 105.3 100.8 100.9 104.4 104.8 100.8 101.1 104.4 105.3 ROP Hospital-- P195 100.7 100.0 104.2 104.5 100.8 101.1 104.2 105.5 ------Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Airport Height 1-A P001 25.0 20.0 14.9 13.6 14.7 13.4 15.7 13.7 15.4 13.7 Airport Height 1-B P001 25.0 20.0 14.9 13.6 14.8 13.4 15.8 13.7 15.5 13.7 Airport Height 2-A P002 25.0 18.4 15.5 13.3 15.3 13.3 16.4 13.6 16.1 13.5 Airport Height 2-B P002 25.0 18.4 15.4 13.3 15.3 13.3 16.4 13.6 16.0 13.5 Airport Height 3-A P003 25.0 20.0 14.2 13.5 14.1 13.5 15.0 13.8 14.7 13.7 Airport Height 3-B P003 25.0 20.0 14.2 13.5 14.0 13.5 14.9 13.8 14.6 13.7 Airport Height 4-A P004 25.0 20.0 16.8 13.1 16.6 13.1 17.9 13.4 17.5 13.3 Airport Height 4-B P004 25.0 20.0 16.7 13.1 16.5 13.1 17.8 13.4 17.4 13.3 Airport Height 5-A P151 25.0 25.0 13.4 12.8 13.3 12.8 14.1 13.0 13.8 13.0 Airport Height 5-B P151 25.0 25.0 13.3 12.8 13.2 12.8 14.0 13.0 13.8 13.0 Azaiba North 3-A P013 25.0 20.0 10.9 13.5 ------Azaiba North 3-B P013 25.0 20.0 10.9 13.5 ------Azaiba North 3-C P013 25.0 20.0 10.5 7.3 ------MOD Technical College-A P081 25.0 18.4 18.6 13.4 18.4 13.4 19.9 13.6 19.4 13.5 MOD Technical College-B P081 25.0 18.4 18.7 13.4 18.4 13.4 20.0 13.6 19.5 13.5 ROP Hospital-- P195 25.0 12.5 17.3 4.6 17.1 4.6 - - - -

MEDC Distribution System Capability Statement [2021-2023]-V2.0 92 Airport Heights [G01] - B GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Azaibah North 3 P013 40 - - - - 30.1 9.9 31.7 79% 30.3 10.0 31.9 80% 30.3 10.0 31.9 80% ROP Airport Height P195 40 ------10.0 3.3 10.5 26% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Azaibah North 3 P013 40 - - - - 5.5 1.9 5.8 14% 5.5 1.9 5.8 15% 5.5 1.9 5.8 15% ROP Airport Height P195 40 ------1.7 0.8 1.9 5% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Azaiba North 3-F1-P013 22.0 - - 10.5 47.5 10.6 47.9 10.6 47.9 Azaiba North 3-F2-P013 22.0 - - 10.8 48.8 10.9 49.2 10.9 49.3 Azaiba North 3-F3-P013 22.0 - - 10.6 48.2 10.7 48.6 10.7 48.6 ROP Airport Height-F1-P195 22.0 ------3.6 14.8 ROP Airport Height-F2-P195 22.0 ------3.6 14.8 ROP Airport Height-F3-P195 22.0 ------3.6 14.8 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Azaiba North 3-A P013 - - - - 100.2 99.7 101.6 103.3 100.2 100.5 102.1 103.5 99.9 100.8 101.8 104.4 Azaiba North 3-B P013 - - - - 100.2 100.0 101.6 103.3 100.2 101.0 102.1 103.5 99.9 101.1 101.8 104.4 Azaiba North 3-C P013 - - - - 100.2 99.9 102.8 104.0 100.2 100.8 102.1 104.6 99.9 100.9 101.8 105.0 ROP Airport Height-A P195 ------100.4 100.9 104.1 105.1 ROP Airport Height-B P195 ------100.4 101.1 104.1 105.1 ROP Airport Height-C P195 ------100.4 101.0 104.1 105.4 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Azaiba North 3-A P013 25.0 20.0 - - 10.6 13.2 11.1 13.5 11.0 13.4 Azaiba North 3-B P013 25.0 20.0 - - 10.5 13.2 11.0 13.5 11.0 13.4 Azaiba North 3-C P013 25.0 20.0 - - 10.3 7.4 10.8 7.5 10.7 7.5 ROP Airport Height-A P195 25.0 25.0 ------8.8 11.5 ROP Airport Height-B P195 25.0 25.0 ------8.8 11.5 ROP Airport Height-C P195 25.0 25.0 ------8.3 6.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 93 Rusail Industry[G13]-A GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Jifnain P042 1TX 3.0 1.2 3.3 - 3.2 1.3 3.5 - 3.4 1.4 3.7 - 3.6 1.4 3.9 - Al Jifnain 2 P196 1TX 3.7 1.4 3.9 - 3.9 1.5 4.2 - 4.1 1.6 4.5 - 4.4 1.7 4.7 - Cement Housing P088 5 1.0 0.4 1.1 22% 1.0 0.4 1.1 22% 1.0 0.4 1.1 22% 1.0 0.4 1.1 22% Rusail Industrial 1 P103 16 12.7 6.2 14.1 88% 13.5 4.4 14.2 89% 14.4 4.7 15.2 95% 15.2 5.0 16.0 100% Rusail Industrial 2 P104 20 15.4 7.8 17.3 87% 16.4 5.4 17.2 86% 17.5 5.7 18.4 92% 18.4 6.0 19.4 97% SQU 1 P122 32 22.1 13.0 25.6 80% 22.1 12.9 25.6 80% 22.1 12.9 25.6 80% 22.1 12.9 25.6 80% SQU 2 P123 16 13.4 9.7 16.5 103% 13.4 10.1 16.8 105% 13.4 10.1 16.8 105% 13.4 10.1 16.8 105% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Jifnain P042 1TX 0.5 0.2 0.6 - 0.7 0.3 0.7 - 0.8 0.3 0.9 - 1.0 0.4 1.0 - Al Jifnain 2 P196 1TX 0.6 0.3 0.7 - 0.6 0.3 0.7 - 0.6 0.3 0.7 - 0.6 0.3 0.7 - Cement Housing P088 5 0.2 0.1 0.2 4% 0.2 0.1 0.2 4% 0.2 0.1 0.2 4% 0.2 0.1 0.2 4% Rusail Industrial 1 P103 16 1.9 0.0 1.9 12% 2.6 0.0 2.6 16% 2.8 0.0 2.8 17% 2.9 0.0 2.9 18% Rusail Industrial 2 P104 20 1.4 0.0 1.4 7% 3.2 0.0 3.2 16% 3.4 0.0 3.4 17% 3.5 0.0 3.5 18% SQU 1 P122 32 4.7 2.9 5.5 17% 4.0 2.4 4.7 15% 4.0 2.4 4.7 15% 4.0 2.4 4.7 15% SQU 2 P123 16 2.6 2.2 3.4 21% 2.3 2.0 3.1 19% 2.3 2.0 3.1 19% 2.3 2.0 3.1 19% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Cement Housing-F1-P088 22.0 4.0 16.6 4.3 17.7 4.5 18.9 4.8 19.9 Cement Housing-F2-P088 22.0 4.3 17.7 4.5 18.6 4.7 19.6 4.9 20.5 Rusail Industrial 1-F1-P103 22.0 7.3 33.2 7.4 33.3 7.9 35.6 8.3 37.6 Rusail Industrial 1-F2-P103 22.0 7.1 32.1 7.1 32.2 7.6 34.4 8.0 36.4 Rusail Industrial 2-F1-P104 22.0 9.2 41.7 8.8 39.7 9.4 42.4 9.9 44.8 Rusail Industrial 2-F2-P104 22.0 8.5 38.4 8.8 39.7 9.4 42.4 9.9 44.8 SQU 1-F1-P122 22.0 8.6 39.1 8.6 39.2 8.6 39.2 8.6 39.2 SQU 1-F2-P122 22.0 8.6 39.1 8.6 39.2 8.6 39.2 8.6 39.2 SQU 1-F3-P122 22.0 8.7 39.4 8.6 39.2 8.6 39.2 8.6 39.2 SQU 2-F1-P123 22.0 8.4 38.0 8.4 38.0 8.4 38.0 8.4 38.0 SQU 2-F2-P123 22.0 8.4 37.8 8.3 37.8 8.3 37.8 8.4 37.8 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Jifnain P042 100.1 100.8 102.6 105.0 100.2 100.8 102.6 105.0 100.1 100.8 102.3 105.0 100.0 100.8 102.1 105.0 Al Jifnain 2 P196 100.3 100.8 103.2 105.1 100.5 100.8 103.3 105.1 100.4 100.8 103.1 105.0 100.3 100.8 102.9 104.9 Cement Housing-A P088 100.2 100.7 99.9 100.4 100.4 100.8 100.1 100.4 100.3 100.7 100.0 100.4 100.2 100.7 99.9 100.4 Cement Housing-B P088 100.2 100.7 99.9 100.4 100.4 100.8 100.1 100.4 100.3 100.7 100.0 100.4 100.2 100.7 99.9 100.4 Rusail Industrial 1-A P103 100.6 100.9 98.4 100.9 100.8 100.9 99.1 100.9 100.7 100.9 98.9 100.9 100.6 100.9 98.7 100.9 Rusail Industrial 1-B P103 100.6 100.9 98.4 100.9 100.8 100.9 99.1 100.9 100.7 100.9 98.9 100.9 100.6 100.9 98.7 100.9 Rusail Industrial 2-A P104 100.3 100.2 101.8 104.8 100.6 100.1 103.0 104.6 100.3 100.0 102.6 104.5 100.1 100.0 102.2 104.5 Rusail Industrial 2-B P104 100.5 100.9 102.2 105.5 100.7 100.9 103.1 105.5 100.6 100.9 102.9 105.4 100.5 100.9 102.7 105.4 SQU 1-A P122 100.2 100.8 101.6 104.7 100.4 100.9 101.8 104.9 100.3 100.9 101.7 104.9 100.3 100.9 101.7 104.9 SQU 1-B P122 100.2 100.8 101.6 104.7 100.4 100.9 101.8 104.9 100.3 100.9 101.7 104.9 100.3 100.9 101.7 104.9 SQU 1-C P122 100.2 100.8 101.6 104.7 100.4 100.9 101.8 104.9 100.3 100.9 101.7 104.9 100.3 100.9 101.7 104.9 SQU 2-A P123 100.0 100.8 100.9 104.6 100.2 100.8 101.1 104.7 100.1 100.8 101.0 104.7 100.1 100.8 101.0 104.7 SQU 2-B P123 100.0 100.8 100.9 104.6 100.2 100.8 101.1 104.7 100.1 100.8 101.0 104.7 100.1 100.8 101.0 104.7

MEDC Distribution System Capability Statement [2021-2023]-V2.0 94 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Jifnain P042 25.0 12.5 6.6 3.8 6.6 3.8 6.6 3.8 6.6 3.8 Al Jifnain 2 P196 25.0 12.5 9.3 4.1 9.3 4.1 9.2 4.1 9.3 4.1 Cement Housing-A P088 25.0 12.5 4.8 4.9 4.8 4.9 4.7 4.9 4.8 4.9 Cement Housing-B P088 25.0 12.5 4.8 4.9 4.8 4.9 4.7 4.9 4.8 4.9 Rusail Industrial 1-A P103 25.0 18.4 20.2 14.1 20.2 14.1 19.9 14.1 20.5 14.2 Rusail Industrial 1-B P103 25.0 18.4 20.3 14.1 20.2 14.1 19.9 14.1 20.5 14.2 Rusail Industrial 2-A P104 25.0 20.0 17.8 7.2 17.8 7.2 17.5 7.2 18.0 7.2 Rusail Industrial 2-B P104 25.0 20.0 17.6 7.2 17.6 7.2 17.3 7.1 17.8 7.2 SQU 1-A P122 25.0 18.4 14.0 12.4 14.0 12.4 13.9 12.4 14.2 12.4 SQU 1-B P122 25.0 18.4 14.0 12.4 14.0 12.4 13.9 12.4 14.2 12.4 SQU 1-C P122 25.0 18.4 13.9 7.0 13.9 7.0 13.7 7.0 14.0 7.0 SQU 2-A P123 25.0 18.4 12.3 11.9 12.3 11.9 12.1 11.8 12.4 11.9 SQU 2-B P123 25.0 18.4 12.3 11.9 12.3 11.9 12.1 11.8 12.4 11.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 95 Rusail Industry[G13]-B GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % ROP Al Khoud P161 20 5.8 2.3 6.2 31% 5.8 1.9 6.1 30% 5.8 1.9 6.1 30% 5.8 1.9 6.1 30% Rusail Housing P056 20 9.3 3.8 10.0 50% 9.9 3.2 10.4 52% 10.5 3.5 11.1 55% 11.1 3.7 11.7 58% Rusail Industrial 3 P105 20 15.9 4.6 16.5 83% 16.9 4.9 17.6 88% 18.0 5.2 18.7 94% 19.0 5.5 19.7 99% Rusail Industrial 4 P158 40 28.5 11.9 30.9 77% 35.6 11.7 37.5 94% 38.0 12.5 40.0 100% 40.0 13.2 42.1 105% Rusail Private Factory P106 20 20.3 4.1 20.7 104% 16.3 3.3 16.6 83% 17.3 3.5 17.7 89% 18.3 3.7 18.7 93% Rusail08(KOM) P164 40 11.4 5.2 12.5 31% 12.1 4.0 12.8 32% 12.9 4.2 13.6 34% 13.6 4.5 14.3 36% SQU 3 P160 40 3.4 0.9 3.5 9% 3.4 0.9 3.5 9% 3.4 0.9 3.5 9% 3.4 0.9 3.5 9% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % ROP Al Khoud P161 20 1.0 0.5 1.1 6% 1.0 0.5 1.1 6% 1.0 0.5 1.1 6% 1.0 0.5 1.1 6% Rusail Housing P056 20 2.6 0.0 2.6 13% 1.9 0.0 1.9 10% 2.0 0.0 2.0 10% 2.1 0.0 2.1 11% Rusail Industrial 3 P105 20 0.8 0.4 0.9 5% 2.9 1.5 3.2 16% 3.0 1.6 3.4 17% 3.2 1.7 3.6 18% Rusail Industrial 4 P158 40 3.4 1.2 3.6 9% 5.5 1.9 5.8 15% 5.9 2.0 6.2 16% 6.2 2.2 6.6 16% Rusail Private Factory P106 20 2.9 0.0 2.9 15% 4.0 0.0 4.0 20% 4.3 0.0 4.3 21% 4.5 0.0 4.5 23% Rusail08(KOM) P164 40 1.7 0.0 1.7 4% 2.3 0.0 2.3 6% 2.5 0.0 2.5 6% 2.6 0.0 2.6 7% SQU 3 P160 40 0.2 0.0 0.2 1% 0.6 0.0 0.6 2% 0.6 0.0 0.6 2% 0.6 0.0 0.6 2% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading ROP Al Khoudh-F1-P161 22.0 3.0 13.4 2.9 13.2 2.9 13.2 2.9 13.3 ROP Al Khoudh-F2-P161 22.0 3.0 13.4 2.9 13.2 2.9 13.2 2.9 13.3 Rusail 08-F1-P164 22.0 4.1 18.8 4.2 18.9 4.5 20.2 4.7 21.4 Rusail 08-F2-P164 22.0 4.2 18.8 4.2 19.0 4.5 20.2 4.7 21.4 Rusail 08-F3-P164 22.0 3.9 17.7 4.2 19.0 4.5 20.2 4.7 21.4 Rusail Ind 4-F1-P158 22.0 10.8 48.8 12.9 58.6 13.8 62.7 14.6 66.3 Rusail Ind 4-F2-P158 22.0 10.6 48.2 12.8 58.0 13.7 62.0 14.5 65.5 Rusail Ind 4-F3-P158 22.0 10.5 47.7 12.9 58.3 13.8 62.3 14.5 65.9 Rusail Industrial 3-F1-P105 22.0 8.5 38.4 9.0 40.9 9.6 43.7 10.2 46.2 Rusail Industrial 3-F2-P105 22.0 8.2 37.4 8.8 39.8 9.4 42.5 9.9 44.9 Rusail Private Factory-F1-P106 22.0 10.5 47.7 8.4 38.1 9.0 40.6 9.5 42.9 Rusail Private Factory-F2-P106 22.0 10.6 47.9 8.4 38.2 9.0 40.8 9.5 43.1 Rusail05(Housing)-F1-P056 22.0 4.9 22.3 5.1 23.2 5.5 24.8 5.8 26.3 Rusail05(Housing)-F2-P056 22.0 5.0 22.6 5.2 23.6 5.6 25.3 5.9 26.7 SQU 03-F1-P160 22.0 0.6 2.9 1.2 5.3 1.2 5.3 1.2 5.3 SQU 03-F2-P160 22.0 0.6 2.9 1.2 5.5 1.2 5.5 1.2 5.5 SQU 03-F3-P160 22.0 2.6 11.9 1.2 5.4 1.2 5.4 1.2 5.4

MEDC Distribution System Capability Statement [2021-2023]-V2.0 96 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min ROP Al Khoudh-A P161 100.3 100.2 104.0 104.6 100.6 100.1 104.4 104.4 100.3 100.0 104.2 104.4 100.1 100.0 103.9 104.4 ROP Al Khoudh-B P161 100.3 100.2 104.0 104.6 100.6 100.1 104.4 104.4 100.3 100.0 104.2 104.4 100.1 100.0 103.9 104.4 Rusail 08-A P164 100.3 100.2 103.6 104.8 100.6 100.1 104.1 104.6 100.3 100.0 103.8 104.6 100.1 100.0 103.5 104.5 Rusail 08-B P164 100.3 100.2 103.6 104.8 100.6 100.1 104.1 104.6 100.3 100.0 103.8 104.6 100.1 100.0 103.5 104.5 Rusail 08-C P164 100.3 100.2 103.7 104.8 100.6 100.1 104.1 104.6 100.3 100.0 103.8 104.6 100.1 100.0 103.5 104.5 Rusail Ind 4-A P158 100.5 100.2 101.9 104.5 100.7 100.1 102.2 104.1 100.5 100.1 101.6 104.1 100.2 100.0 101.2 104.0 Rusail Ind 4-B P158 100.5 100.2 101.9 104.5 100.7 100.1 102.2 104.1 100.5 100.1 101.6 104.1 100.2 100.0 101.2 104.0 Rusail Ind 4-C P158 100.5 100.2 102.0 104.5 100.7 100.1 102.2 104.1 100.5 100.1 101.7 104.1 100.2 100.0 101.2 104.0 Rusail Industrial 3-A P105 100.3 100.2 103.0 104.6 100.5 100.0 103.1 104.1 100.3 100.0 102.7 104.0 100.0 100.0 102.3 104.0 Rusail Industrial 3-B P105 100.3 100.2 103.0 104.6 100.5 100.0 103.1 104.1 100.3 100.0 102.7 104.0 100.0 100.0 102.3 104.0 Rusail Private Factory-A P106 100.4 100.2 103.1 104.7 100.7 100.1 103.8 104.6 100.4 100.0 103.4 104.5 100.2 100.0 103.1 104.5 Rusail Private Factory-B P106 100.4 100.2 103.1 104.7 100.7 100.1 103.8 104.6 100.4 100.0 103.4 104.5 100.2 100.0 103.1 104.5 Rusail05(Housing)-A P056 100.3 100.2 103.5 104.7 100.6 100.1 103.9 104.6 100.3 100.0 103.6 104.6 100.1 100.0 103.2 104.5 Rusail05(Housing)-B P056 100.3 100.2 103.5 104.7 100.6 100.1 103.9 104.6 100.3 100.0 103.6 104.6 100.1 100.0 103.2 104.5 SQU 03-A P160 100.5 100.2 105.0 104.8 100.7 100.1 105.1 104.6 100.4 100.1 104.8 104.6 100.2 100.0 104.6 104.6 SQU 03-B P160 100.5 100.2 105.0 104.8 100.7 100.1 105.1 104.6 100.4 100.1 104.8 104.6 100.2 100.0 104.6 104.6 SQU 03-C P160 100.4 100.2 104.4 104.8 100.7 100.1 105.1 104.6 100.4 100.1 104.8 104.6 100.2 100.0 104.6 104.6 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV ROP Al Khoudh-A P161 25.0 25.0 12.3 11.9 12.3 11.9 12.1 11.9 12.4 12.0 ROP Al Khoudh-B P161 25.0 25.0 12.3 11.9 12.3 11.9 12.1 11.9 12.4 12.0 Rusail 08-A P164 25.0 25.0 13.9 12.5 13.9 12.5 13.7 12.4 14.0 12.5 Rusail 08-B P164 25.0 25.0 13.9 12.5 13.9 12.5 13.7 12.4 14.0 12.5 Rusail 08-C P164 25.0 25.0 13.7 7.0 13.7 7.0 13.6 7.0 13.9 7.0 Rusail Ind 4-A P158 25.0 25.0 21.4 13.2 21.4 13.2 21.0 13.1 21.7 13.2 Rusail Ind 4-B P158 25.0 25.0 21.4 13.2 21.4 13.2 21.0 13.1 21.7 13.2 Rusail Ind 4-C P158 25.0 25.0 21.4 7.6 21.4 7.6 21.0 7.5 21.8 7.6 Rusail Industrial 3-A P105 25.0 18.4 16.6 12.8 16.6 12.8 16.3 12.7 16.8 12.8 Rusail Industrial 3-B P105 25.0 18.4 16.6 12.8 16.6 12.8 16.4 12.7 16.8 12.8 Rusail Private Factory-A P106 25.0 18.4 20.0 12.8 20.0 12.8 19.7 12.7 20.3 12.8 Rusail Private Factory-B P106 25.0 18.4 20.0 12.8 20.0 12.8 19.7 12.7 20.3 12.8 Rusail05(Housing)-A P056 25.0 18.4 15.1 12.7 15.1 12.7 14.9 12.6 15.2 12.7 Rusail05(Housing)-B P056 25.0 18.4 15.1 12.7 15.1 12.7 14.9 12.6 15.3 12.7 SQU 03-A P160 25.0 25.0 12.5 12.3 12.5 12.3 12.3 12.3 12.6 12.4 SQU 03-B P160 25.0 25.0 12.5 12.3 12.5 12.3 12.3 12.3 12.6 12.4 SQU 03-C P160 25.0 25.0 12.2 7.1 12.2 7.1 12.1 7.0 12.3 7.1

MEDC Distribution System Capability Statement [2021-2023]-V2.0 97 Misfah[G04] GSS [Zone 2] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Awabi P139 40 20.7 8.2 22.2 56% 22.0 7.2 23.1 58% 23.4 7.7 24.7 62% 24.7 8.1 26.0 65% Al Misfah P080 40 36.0 10.5 37.5 94% 38.3 11.2 39.9 100% 40.8 11.9 42.5 106% 43.0 12.6 44.8 112% Cement Factory 1 P079 91.5 47.5 18.8 51.0 56% 47.5 18.8 51.0 56% 47.5 18.8 51.0 56% 47.5 18.8 51.0 56% Orpic P192 6 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% 0.7 0.3 0.8 13% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Awabi P139 40 4.5 1.8 4.8 12% 3.9 1.6 4.2 11% 4.2 1.7 4.5 11% 4.4 1.7 4.8 12% Al Misfah P080 40 6.1 0.0 6.1 15% 7.3 0.0 7.3 18% 7.8 0.0 7.8 19% 8.2 0.0 8.2 21% Cement Factory 1 P079 91.5 8.3 4.0 9.2 10% 8.4 4.1 9.3 10% 8.4 4.1 9.3 10% 8.4 4.1 9.3 10% Orpic P192 6 1.4 0.5 1.5 25% 0.1 0.1 0.1 2% 0.1 0.1 0.1 2% 0.1 0.1 0.1 2% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Awabi-F1-P139 22.0 7.9 35.6 8.4 37.9 9.1 41.1 9.3 42.2 Al Awabi-F2-P139 22.0 6.9 31.2 7.3 33.2 7.9 36.0 8.2 37.0 Al Awabi-F3-P139 22.0 6.9 31.2 7.3 33.2 7.9 36.0 8.2 37.0 Al Misfah-F1-P080 22.0 10.7 48.6 13.5 61.1 15.1 68.5 15.3 69.3 Al Misfah-F2-P080 22.0 10.7 48.4 13.4 60.8 15.0 68.1 15.2 68.9 Al Misfah-F3-P080 22.0 16.6 75.1 13.5 61.0 15.1 68.3 15.2 69.1 Cement Factory 1-F1-P079 22.0 10.4 43.5 10.4 43.5 10.4 43.5 10.4 43.5 Cement Factory 1-F2-P079 22.0 10.4 43.5 10.4 43.5 10.4 43.5 10.4 43.5 Cement Factory 1-F3-P079 22.0 10.5 43.8 10.5 43.8 10.5 43.9 10.5 43.8 Cement Factory 1-DP079 22.0 10.5 43.8 10.5 43.8 10.5 43.9 10.5 43.8 Cement Factory 1-EP079 22.0 10.5 43.8 10.5 43.8 10.5 43.9 10.5 43.8 Orpic-NP192 22.0 0.8 3.7 0.8 3.7 0.8 3.7 0.8 3.7 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Awabi-A P139 100.3 102.8 101.5 102.4 100.1 102.9 102.9 102.4 99.8 102.8 102.4 102.4 99.9 102.8 102.7 102.4 Al Awabi-B P139 100.3 102.8 101.5 102.4 100.1 102.9 102.9 102.4 99.8 102.8 102.4 102.4 99.9 102.8 102.7 102.4 Al Awabi-C P139 100.3 102.8 101.4 102.4 100.1 102.9 102.8 102.4 99.8 102.8 102.3 102.4 99.9 102.8 102.6 102.4 Al Misfah-A P080 100.5 102.9 103.0 102.8 100.2 102.9 102.0 102.7 99.9 102.9 101.2 102.7 100.0 102.8 101.2 102.7 Al Misfah-B P080 100.5 102.9 103.0 102.8 100.2 102.9 102.0 102.7 99.9 102.9 101.2 102.7 100.0 102.8 101.2 102.7 Al Misfah-C P080 100.3 102.9 101.2 102.7 100.2 102.9 102.0 102.7 99.9 102.9 101.2 102.7 100.0 102.8 101.2 102.7 Cement Factory 1-A P079 100.2 102.8 - - 100.1 102.8 - - 99.8 102.8 - - 99.9 102.8 - - Cement Factory 1-B P079 100.2 102.8 - - 100.1 102.8 - - 99.8 102.8 - - 99.9 102.8 - - Cement Factory 1-C P079 100.2 102.8 - - 100.1 102.8 - - 99.8 102.8 - - 99.9 102.8 - - Cement Factory 1-D P079 100.2 102.8 - - 100.1 102.8 - - 99.8 102.8 - - 99.9 102.8 - - Cement Factory 1-E P079 100.2 102.8 - - 100.1 102.8 - - 99.8 102.8 - - 99.9 102.8 - - Orpic-N P192 100.9 102.9 - - 100.7 102.9 - - 100.4 102.9 - - 100.5 102.9 - -

MEDC Distribution System Capability Statement [2021-2023]-V2.0 98 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Awabi-A P139 25.0 25.0 17.2 13.7 17.3 13.8 18.4 14.1 18.4 14.2 Al Awabi-B P139 25.0 25.0 17.2 13.7 17.3 13.8 18.4 14.1 18.4 14.2 Al Awabi-C P139 25.0 25.0 17.2 7.7 17.3 7.7 18.4 7.8 18.4 7.8 Al Misfah-A P080 25.0 25.0 16.0 14.1 16.1 14.5 17.0 15.0 17.0 15.0 Al Misfah-B P080 25.0 25.0 16.0 14.1 16.0 14.5 17.0 15.0 17.0 15.0 Al Misfah-C P080 25.0 25.0 15.9 8.3 15.9 8.0 16.9 8.2 16.9 8.2 Cement Factory 1-A P079 31.5 - 12.3 - 12.4 - 12.9 - 12.9 - Cement Factory 1-B P079 31.5 - 12.3 - 12.4 - 12.9 - 12.9 - Cement Factory 1-C P079 31.5 - 12.4 - 12.4 - 12.9 - 12.9 - Cement Factory 1-D P079 31.5 - 12.4 - 12.4 - 12.9 - 12.9 - Cement Factory 1-E P079 31.5 - 12.4 - 12.4 - 12.9 - 12.9 - Orpic-N P192 25.0 - 14.0 - 14.1 - 14.8 - 14.8 -

MEDC Distribution System Capability Statement [2021-2023]-V2.0 99 Barka[G02] GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Mabelah South P061 20 17.7 8.1 19.5 98% 19.6 6.4 20.6 103% Shifted to Mabella 2-B GSS Manomah P067 20 14.9 5.8 16.0 80% 14.9 4.9 15.7 78% Shifted to Mabelah Industrial GSS Palace Communication P033 1TX 0.9 0.4 1.0 - 0.9 0.4 1.0 - Shifted to Mabelah Industrial GSS RGO Halban Camp P034 1TX 2.5 1.0 2.7 - 2.5 1.0 2.7 - Shifted to Mabelah Industrial GSS Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Mabelah South P061 20 2.9 2.0 3.5 18% 3.1 2.1 3.8 19% Shifted to Mabella 2-B GSS Manomah P067 20 5.0 1.0 5.1 26% 2.8 0.6 2.9 14% Shifted to Mabelah Industrial GSS Palace Communication P033 1TX 0.2 0.1 0.2 - 0.2 0.1 0.2 - Shifted to Mabelah Industrial GSS RGO Halban Camp P034 1TX 0.2 0.1 0.2 - 0.2 0.1 0.2 - Shifted to Mabelah Industrial GSS 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Mabelah South-F1-P061 22.0 10.4 47.2 11.0 49.6 - - - - Mabelah South-F2-P061 22.0 10.3 46.6 10.8 49.1 - - - - Manoma 1-F1-P067 22.0 8.2 37.0 8.0 36.2 - - - - Manoma 1-F2-P067 22.0 8.1 36.9 8.0 36.1 - - - - Old Mabelah-F1-P059 (from Barka GSS) 15.4 3.8 24.7 3.8 24.7 - - - - Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Mabelah South-A P061 97.6 100.2 98.9 104.1 97.0 100.2 98.8 104.1 ------Mabelah South-B P061 97.7 100.2 98.9 104.1 97.0 100.3 98.8 104.1 ------Manoma 1-A P067 99.9 100.6 102.3 104.7 99.3 100.8 101.9 105.1 ------Manoma 1-B P067 99.9 100.5 102.3 104.7 99.2 100.7 101.9 105.1 ------Palace Communication P033 99.8 100.5 103.9 105.0 99.1 100.6 103.1 105.1 ------RGO Halban Camp P034 99.8 100.5 102.4 104.8 99.1 100.6 101.6 104.9 ------Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Mabelah South-A P061 25.0 18.4 4.9 10.3 5.0 10.4 Mabelah South-B P061 25.0 18.4 4.9 10.3 4.9 10.4 Manoma 1-A P067 25.0 18.4 8.5 12.6 8.6 12.6 Manoma 1-B P067 25.0 18.4 8.1 12.6 8.2 12.6 Palace Communication P033 25.0 18.4 4.6 3.7 4.4 3.6 RGO Halban Camp P034 25.0 18.4 4.8 3.0 4.6 2.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 100 Mabelah[GP04] GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Botanic Garden P016 20 7.5 3.5 8.3 42% 7.5 2.5 7.9 39% 7.5 2.5 7.9 39% 7.5 2.5 7.9 39% Mabelah A P063 40 28.5 7.1 29.3 73% 31.4 7.9 32.4 81% Shifted to Mabelah Industrial GSS Mabelah Grid GP04 20 22.8 7.6 24.0 120% 25.1 8.3 26.5 132% 27.8 9.2 29.3 147% 14.4 4.7 15.1 76% Mabelah South PH-7 P141 40 25.3 3.6 25.5 64% 27.9 4.0 28.1 70% Shifted to Mabelah Industrial GSS Mabelah STP P140 10 5.0 2.0 5.3 53% 5.0 2.0 5.3 53% 5.0 2.0 5.3 53% 5.0 2.0 5.3 53% Old Mabelah P059 20 21.8 9.0 23.6 118% Shifted to Mobella 2-B GSS ROP Dog Kennel P183 6 - - - - 3.5 1.2 3.7 61% 3.5 1.2 3.7 61% 3.5 1.2 3.7 61% Sur Al Hadid P116 20 17.9 7.6 19.4 97% Upgraded Sur Al Hadid(Upgrade) P116 40 - - - - 28.7 9.4 30.2 76% 29.4 9.6 30.9 77% 29.6 9.7 31.2 78% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Botanic Garden P016 20 1.0 0.5 1.1 6% 1.3 0.6 1.4 7% 1.3 0.6 1.4 7% 1.3 0.6 1.4 7% Mabelah A P063 40 1.8 1.6 2.4 6% 4.4 3.9 5.9 15% Shifted to Mabelah Industrial GSS Mabelah Grid GP04 20 2.9 1.1 3.1 16% 4.5 1.7 4.8 24% 5.0 1.9 5.4 27% 2.6 1.0 2.8 14% Mabelah South PH-7 P141 40 2.3 1.4 2.7 7% 4.4 2.7 5.2 13% Shifted to Mabelah Industrial GSS Mabelah STP P140 10 0.9 0.4 1.0 10% 0.9 0.4 1.0 10% 0.9 0.4 1.0 10% 0.9 0.4 1.0 10% Old Mabelah P059 20 3.6 2.4 4.3 22% Shifted to Mobella 2-B GSS ROP Dog Kennel P183 6 - - - - 0.6 0.2 0.7 11% 0.6 0.2 0.7 11% 0.6 0.2 0.7 11% Sur Al Hadid P116 20 4.7 2.4 5.3 27% Upgraded Sur Al Hadid(Upgrade) P116 40 - - - - 4.9 2.6 5.5 14% 5.0 2.6 5.6 14% 5.0 2.6 5.6 14% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Botanic Garden-F1-P016 22.0 4.0 18.0 3.8 15.9 3.8 15.9 3.8 15.9 Botanic Garden-F2-P016 22.0 4.0 18.0 3.8 16.0 3.8 16.0 3.8 15.9 Mabelah A-F1-P063 22.0 10.7 48.6 11.0 50.0 - - - - Mabelah A-F2-P063 22.0 10.6 48.0 10.9 49.3 - - - - Mabelah A-F3-P063 22.0 8.5 38.3 11.0 49.8 - - - - Mabelah Grid-F1-GP04 22.0 15.4 69.9 13.7 62.0 15.2 69.0 7.7 34.7 Mabelah Grid-F2-GP04 22.0 9.4 42.5 13.7 62.0 15.2 68.9 7.8 35.1 Mabelah South PH 7-F1-P141 22.0 9.2 41.9 9.5 42.9 - - - - Mabelah South PH 7-F2-P141 22.0 9.2 41.7 9.4 42.7 - - - - Mabelah South PH 7-F3-P141 22.0 7.2 32.6 9.5 42.9 - - - - Mabelah STP-F1-P140 22.0 2.5 11.4 2.5 11.4 2.5 11.4 2.5 11.4 Mabelah STP-F2-P140 22.0 2.5 11.3 2.5 11.3 2.5 11.3 2.5 11.3 Old Mabelah-F2-P059 (from Barka GSS) 15.4 13.8 89.7 ------Old Mabelah-F2-P059 (from Mabelah GSS) 15.4 11.5 74.7 ------ROP Dog Kennel-F1-P183 22.0 - - 1.8 8.2 1.8 8.2 1.8 8.2 ROP Dog Kennel-F2-P183 22.0 - - 1.9 8.4 1.9 8.4 1.9 8.4 Sur Al Hadid -F1-P116 22.0 9.7 43.8 10.1 45.6 10.3 46.7 10.4 47.1 Sur Al Hadid -F2-P116 22.0 9.7 43.9 10.1 45.6 10.3 46.7 10.4 47.1 Sur Al Hadid -F3-P116 22.0 - - 10.1 45.6 10.3 46.7 10.4 47.1

MEDC Distribution System Capability Statement [2021-2023]-V2.0 101 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Botanic Garden-A P016 100.6 101.0 103.9 105.3 100.6 100.9 104.2 105.2 100.7 100.0 104.4 104.4 101.3 100.1 105.0 104.5 Botanic Garden-B P016 100.6 101.1 103.9 105.3 100.6 100.9 104.2 105.2 100.7 100.0 104.4 104.4 101.3 100.1 105.0 104.5 Mabelah A-A P063 100.6 101.1 103.0 104.8 100.5 100.8 102.8 104.5 ------Mabelah A-B P063 100.6 101.0 103.0 104.8 100.5 100.8 102.8 104.5 ------Mabelah A-C P063 100.4 101.1 103.4 105.4 100.2 100.7 102.6 104.5 ------Mabelah Grid-A GP04 100.9 101.1 101.6 104.9 100.9 100.9 102.0 104.9 101.0 100.1 101.7 103.9 101.6 100.1 104.4 104.3 Mabelah Grid-B GP04 100.9 101.1 103.3 104.9 100.9 100.9 102.0 104.9 101.0 100.1 101.8 103.9 101.6 100.1 104.4 104.3 Mabelah South PH 7-A P141 100.5 101.1 103.8 104.9 100.4 100.8 103.7 104.8 ------Mabelah South PH 7-B P141 100.5 101.0 103.8 104.9 100.4 100.8 103.7 104.8 ------Mabelah South PH 7-C P141 100.5 101.0 104.1 105.4 100.2 100.7 103.5 104.7 ------Mabelah STP-A P140 100.7 101.2 104.3 105.3 100.6 100.9 104.3 105.3 100.8 100.1 104.4 104.4 101.4 100.1 105.0 104.5 Mabelah STP-B P140 100.7 101.1 104.3 105.3 100.6 100.9 104.3 105.3 100.8 100.1 104.4 104.4 101.4 100.1 105.0 104.5 Old Mabelah-A P059 93.5 99.4 101.2 101.4 ------Old Mabelah-B P059 97.1 100.5 98.4 104.3 ------ROP Dog Kennel-A P183 - - - - 100.9 100.9 104.6 105.3 101.0 100.1 104.8 104.4 101.6 100.1 105.4 104.5 ROP Dog Kennel-B P183 - - - - 100.8 100.9 104.6 105.3 101.0 100.1 104.8 104.4 101.6 100.1 105.4 104.5 Sur Al Hadid -A P116 99.8 100.5 101.3 103.3 99.7 100.7 101.7 104.7 99.9 99.9 101.7 103.8 100.4 100.0 102.3 103.9 Sur Al Hadid -B P116 99.8 101.2 101.3 103.3 99.7 100.7 101.7 104.7 99.8 99.9 101.7 103.8 100.4 100.0 102.3 103.9 Sur Al Hadid -C P116 - - - - 99.7 100.7 101.7 104.7 99.8 99.9 101.8 103.8 100.4 100.0 102.3 103.9 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Botanic Garden-A P016 25.0 18.4 11.3 12.6 11.4 12.7 11.1 12.6 11.0 12.5 Botanic Garden-B P016 25.0 18.4 11.3 12.6 11.5 12.7 11.2 12.6 11.1 12.5 Mabelah A-A P063 25.0 18.4 16.3 14.2 17.1 14.4 - - - - Mabelah A-B P063 25.0 18.4 16.3 14.2 16.7 14.4 - - - - Mabelah A-C P063 25.0 25.0 11.9 7.6 12.1 7.8 - - - - Mabelah Grid-A GP04 25.0 18.4 23.9 8.6 24.8 8.5 23.4 8.5 22.9 14.3 Mabelah Grid-B GP04 25.0 18.4 23.9 8.2 24.8 8.5 23.4 8.6 22.9 14.3 Mabelah South PH 7-A P141 25.0 25.0 12.9 14.1 13.1 14.2 - - - - Mabelah South PH 7-B P141 25.0 25.0 12.9 14.1 13.1 14.2 - - - - Mabelah South PH 7-C P141 25.0 25.0 10.4 7.3 10.6 7.5 - - - - Mabelah STP-A P140 25.0 20.0 10.0 10.1 10.1 10.1 9.9 10.0 9.8 10.0 Mabelah STP-B P140 25.0 20.0 10.0 10.1 10.1 10.1 9.9 10.0 9.8 10.0 Old Mabelah-A P059 25.0 20.0 3.4 5.3 ------Old Mabelah-B P059 25.0 20.0 4.7 6.1 ------ROP Dog Kennel-A P183 26.3 26.3 - - 22.3 8.7 21.1 8.6 20.7 8.6 ROP Dog Kennel-B P183 26.3 26.3 - - 22.2 8.7 21.0 8.6 20.6 8.6 Sur Al Hadid -A P116 25.0 20.0 9.5 12.8 9.7 12.9 9.5 12.8 9.4 12.8 Sur Al Hadid -B P116 25.0 20.0 9.5 12.8 9.6 12.9 9.4 12.8 9.3 12.8 Sur Al Hadid -C P116 25.0 25.0 - - 9.1 7.0 9.0 7.0 8.9 7.0

MEDC Distribution System Capability Statement [2021-2023]-V2.0 102 Mabella 2[G12] - A GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Mabelah C P064 40 31.6 15.6 35.3 88% 34.9 11.5 36.7 92% 38.6 12.7 40.6 102% 41.5 13.6 43.7 109% Mabelah South PH-4 P062 40 36.5 11.4 38.2 96% 40.3 12.4 42.1 105% 44.6 13.8 46.7 117% 35.0 10.8 36.7 92% Mabelah South PH-8 P157 40 37.4 13.3 39.7 99% 41.2 13.6 43.4 109% Shifted to Mabelah Industrial GSS PalmMall P168 40 21.6 6.3 22.5 56% 23.8 6.9 24.8 62% 26.3 7.7 27.4 69% 28.3 8.3 29.5 74% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Mabelah C P064 40 2.5 2.9 3.8 10% 4.4 5.1 6.7 17% 4.9 5.6 7.4 19% 5.3 6.0 8.0 20% Mabelah South PH-4 P062 40 4.5 1.0 4.6 12% 7.5 1.6 7.7 19% 8.4 1.8 8.5 21% 6.6 1.4 6.7 17% Mabelah South PH-8 P157 40 3.8 1.5 4.1 10% 7.4 3.0 7.9 20% Shifted to Mabelah Industrial GSS PalmMall P168 40 3.0 0.0 3.0 8% 4.5 0.0 4.5 11% 5.0 0.0 5.0 13% 5.4 0.0 5.4 13% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Mabelah C-F1-P064 22.0 14.0 63.7 12.6 56.9 14.0 63.3 15.1 68.3 Mabelah C-F2-P064 22.0 14.1 63.9 12.6 57.1 14.0 63.5 15.1 68.5 Mabelah C-F3-P064 22.0 8.1 36.8 12.6 57.1 14.0 63.5 15.1 68.5 Mabelah South PH 4-F1-P062 22.0 12.5 56.6 14.3 64.6 15.9 72.1 12.3 56.0 Mabelah South PH 4-F2-P062 22.0 12.7 57.6 14.5 65.7 16.2 73.3 12.6 56.9 Mabelah South PH 4-F3-P062 22.0 13.8 62.7 14.4 65.2 16.0 72.7 12.4 56.4 Mabelah South PH 8-F1-P157 22.0 12.3 55.8 14.9 67.5 - - - - Mabelah South PH 8-F2-P157 22.0 12.3 55.8 14.9 67.5 - - - - Mabelah South PH 8-F3-P157 22.0 16.2 73.6 14.9 67.5 - - - - Palm Mall-F1-P168 22.0 7.8 35.5 8.4 38.0 9.3 42.1 10.0 45.5 Palm Mall-F2-P168 22.0 7.8 35.4 8.4 37.9 9.3 42.1 10.0 45.4 Palm Mall-F3-P168 22.0 7.1 32.3 8.4 38.0 9.3 42.1 10.0 45.4 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Mabelah C-A P064 100.5 100.8 100.5 104.7 100.8 100.5 102.4 103.9 100.7 100.5 101.8 103.8 100.3 100.4 101.1 103.6 Mabelah C-B P064 100.5 100.8 100.5 104.7 100.8 100.5 102.4 103.9 100.7 100.5 101.8 103.8 100.3 100.4 101.1 103.6 Mabelah C-C P064 100.6 100.8 102.5 105.0 100.8 100.5 102.3 103.9 100.7 100.5 101.7 103.8 100.3 100.4 101.0 103.6 Mabelah South PH 4-A P062 100.3 100.8 101.8 105.2 100.9 100.9 102.1 105.1 99.9 100.8 100.6 104.9 99.7 100.8 101.3 105.0 Mabelah South PH 4-B P062 100.3 100.8 101.8 105.2 100.9 100.9 102.1 105.1 99.9 100.8 100.6 104.9 99.7 100.8 101.3 105.0 Mabelah South PH 4-C P062 100.2 100.8 101.5 105.1 100.9 100.9 102.1 105.1 99.9 100.8 100.6 104.9 99.7 100.8 101.3 105.0 Mabelah South PH 8-A P157 99.8 100.8 101.1 105.1 99.9 100.3 100.8 104.2 ------Mabelah South PH 8-B P157 99.8 100.8 101.1 105.1 99.9 100.3 100.8 104.2 ------Mabelah South PH 8-C P157 99.5 100.8 99.7 104.9 99.9 100.3 100.8 104.2 ------Palm Mall-A P168 100.6 100.8 103.5 105.4 100.9 100.5 103.7 104.9 100.7 100.5 103.3 104.9 100.4 100.4 102.7 104.9 Palm Mall-B P168 100.6 100.8 103.5 105.4 100.9 100.5 103.7 104.9 100.7 100.5 103.3 104.9 100.4 100.4 102.7 104.9 Palm Mall-C P168 100.6 100.8 103.6 105.4 100.9 100.5 103.7 105.0 100.7 100.5 103.3 105.0 100.4 100.4 102.7 104.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 103 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Mabelah C-A P064 25.0 18.4 22.8 15.5 22.7 15.3 22.1 15.5 22.2 15.6 Mabelah C-B P064 25.0 18.4 22.8 15.5 22.7 15.3 22.1 15.5 22.2 15.6 Mabelah C-C P064 25.0 25.0 22.7 8.0 22.7 8.3 22.1 8.4 22.1 8.5 Mabelah South PH 4-A P062 25.0 20.0 17.5 14.6 16.4 14.6 16.8 15.0 16.9 14.5 Mabelah South PH 4-B P062 25.0 20.0 17.5 14.6 16.4 14.6 16.9 15.0 17.0 14.5 Mabelah South PH 4-C P062 25.0 20.0 17.5 8.2 16.4 8.1 16.8 8.3 16.9 8.0 Mabelah South PH 8-A P157 25.0 25.0 12.8 14.4 12.9 14.8 - - - - Mabelah South PH 8-B P157 25.0 25.0 12.8 14.4 12.9 14.8 - - - - Mabelah South PH 8-C P157 25.0 25.0 12.6 8.2 12.6 8.1 - - - - Palm Mall-A P168 25.0 25.0 23.0 14.8 23.0 14.8 22.4 14.9 22.4 15.0 Palm Mall-B P168 25.0 25.0 22.9 14.8 22.9 14.8 22.3 14.9 22.3 15.0 Palm Mall-C P168 25.0 25.0 23.0 8.1 22.9 8.2 22.3 8.2 22.4 8.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 104 Mabella 2[G12] - B GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Mabelah Shabiya P060 40 31.3 14.7 34.6 87% 34.5 11.3 36.3 91% 38.2 12.6 40.2 101% 41.1 13.5 43.3 108% Mabelah South PH 6 P185 40 ------21.5 7.1 22.6 57% Mabelah South(Upgrade) P061 40 ------21.7 7.1 22.8 57% 23.3 7.7 24.5 61% Old Mabelah P059 20 - - - - 13.0 4.3 13.7 69% 14.4 4.7 15.2 76% 15.5 5.1 16.3 82% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Mabelah Shabiya P060 40 3.5 2.1 4.1 10% 5.7 3.5 6.7 17% 6.3 3.8 7.4 18% 6.8 4.1 7.9 20% Mabelah South PH 6 P185 40 ------3.7 1.8 4.1 10% Mabelah South(Upgrade) P061 40 ------3.5 2.3 4.2 10% 3.7 2.5 4.5 11% Old Mabelah P059 20 - - - - 2.1 1.4 2.5 13% 2.3 1.5 2.8 14% 2.5 1.6 3.0 15% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Mabelah Shabiya-F1-P060 22.0 14.4 65.4 12.3 55.9 13.7 62.1 14.8 67.0 Mabelah Shabiya-F2-P060 22.0 14.4 65.5 12.3 55.9 13.7 62.2 14.8 67.1 Mabelah Shabiya-F3-P060 22.0 6.4 28.9 12.3 55.9 13.7 62.1 14.8 67.0 Mabelah South PH 6-F1-P185 22.0 ------7.6 34.3 Mabelah South PH 6-F2-P185 22.0 ------7.6 34.3 Mabelah South PH 6-F3-P185 22.0 ------7.6 34.3 Mabelah South-F1-P061 22.0 - - - - 7.6 34.6 8.2 37.4 Mabelah South-F2-P061 22.0 - - - - 7.6 34.6 8.2 37.4 Mabelah South-F3-P061 22.0 - - - - 7.6 34.6 8.2 37.4 Old Mabelah-F1-P059 22.0 - - 7.0 31.6 7.7 35.1 8.4 37.9 Old Mabelah-F2-P059 22.0 - - 6.9 31.5 7.7 35.0 8.3 37.7 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Mabelah Shabiya-A P060 100.2 100.8 101.2 104.9 100.6 100.4 102.8 104.3 100.4 100.4 102.3 104.3 100.0 100.4 101.6 104.1 Mabelah Shabiya-B P060 100.2 100.8 101.2 104.9 100.6 100.4 102.8 104.3 100.4 100.4 102.3 104.3 100.0 100.4 101.6 104.1 Mabelah Shabiya-C P060 100.4 100.8 103.5 105.2 100.6 100.4 102.8 104.3 100.4 100.4 102.3 104.3 100.0 100.4 101.6 104.1 Mabelah South PH 6-A P185 ------99.7 100.8 102.4 104.9 Mabelah South PH 6-B P185 ------99.7 100.8 102.4 104.9 Mabelah South PH 6-C P185 ------99.7 100.8 102.4 104.9 Mabelah South-A P061 ------100.2 100.8 102.9 104.9 99.8 100.8 102.3 104.8 Mabelah South-B P061 ------100.2 100.8 102.9 104.9 99.8 100.8 102.3 104.8 Mabelah South-C P061 ------100.2 100.8 102.9 104.9 99.8 100.8 102.3 104.8 Old Mabelah-A P059 - - - - 100.6 100.8 103.6 105.0 99.6 100.7 102.3 104.8 99.2 100.6 101.7 104.7 Old Mabelah-B P059 - - - - 100.6 100.8 103.6 105.0 99.6 100.7 102.3 104.8 99.2 100.6 101.7 104.7

MEDC Distribution System Capability Statement [2021-2023]-V2.0 105 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Mabelah Shabiya-A P060 25.0 18.4 17.9 17.6 17.8 17.3 17.5 17.4 17.5 17.5 Mabelah Shabiya-B P060 25.0 18.4 18.0 17.6 17.9 17.3 17.5 17.4 17.6 17.5 Mabelah Shabiya-C P060 25.0 25.0 17.7 9.2 17.7 9.7 17.4 9.7 17.4 9.8 Mabelah South PH 6-A P185 25.0 25.0 ------15.1 13.6 Mabelah South PH 6-B P185 25.0 25.0 ------15.1 13.6 Mabelah South PH 6-C P185 25.0 25.0 ------14.9 7.5 Mabelah South-A P061 25.0 18.4 - - - - 16.2 14.0 16.3 14.1 Mabelah South-B P061 25.0 18.4 - - - - 16.2 14.0 16.3 14.1 Mabelah South-C P061 25.0 25.0 - - - - 16.0 7.7 16.2 7.8 Old Mabelah-A P059 25.0 18.4 - - 8.9 12.5 9.1 12.7 9.1 12.8 Old Mabelah-B P059 25.0 18.4 - - 8.9 12.5 9.1 12.7 9.1 12.8

MEDC Distribution System Capability Statement [2021-2023]-V2.0 106 Mabelah Industrial GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Mabelah A P063 40 ------34.8 11.4 36.6 91% 37.4 12.3 39.3 98% Mabelah South PH-7 P141 40 ------30.8 4.4 31.2 78% 29.7 4.2 30.0 75% Mabelah South PH-8 P157 40 ------45.7 15.0 48.1 120% 38.7 12.7 40.7 102% Mabelah South PH-9 P184 40 ------20.9 6.9 22.0 55% Manomah P067 20 ------14.9 4.9 15.7 78% 14.9 4.9 15.7 78% Palace Communication P033 1TX ------0.9 0.4 1.0 - 0.9 0.4 1.0 - Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Mabelah A P063 40 ------5.0 4.4 6.7 17% 5.4 4.8 7.2 18% Mabelah South PH-7 P141 40 ------4.9 3.0 5.7 14% 4.7 2.9 5.5 14% Mabelah South PH-8 P157 40 ------8.2 3.3 8.8 22% 6.9 2.8 7.5 19% Mabelah South PH-9 P184 40 ------3.6 1.7 4.0 10% Manomah P067 20 ------2.8 0.6 2.9 14% 2.8 0.6 2.9 14% Palace Communication P033 1TX ------0.2 0.1 0.2 - 0.2 0.1 0.2 - 33kV Feeder Loads Rating 33kV (%) 33kV (%) 33kV (%) 33kV (%) Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Mabelah A-F1-P063 22.0 - - - - 12.6 57.1 13.6 61.6 Mabelah A-F2-P063 22.0 - - - - 12.4 56.4 13.4 60.9 Mabelah A-F3-P063 22.0 - - - - 12.5 56.7 13.5 61.2 Mabelah South PH 7-F1-P141 22.0 - - - - 10.5 47.6 10.1 45.8 Mabelah South PH 7-F2-P141 22.0 - - - - 10.4 47.3 10.1 45.6 Mabelah South PH 7-F3-P141 22.0 - - - - 10.5 47.4 10.1 45.7 Mabelah South PH 8-F1-P157 22.0 - - - - 16.7 75.5 14.0 63.5 Mabelah South PH 8-F2-P157 22.0 - - - - 16.7 75.5 14.0 63.5 Mabelah South PH 8-F3-P157 22.0 - - - - 16.7 75.5 14.0 63.5 Mabelah South PH 9-F1-P184 22.0 ------7.4 33.7 Mabelah South PH 9-F2-P184 22.0 ------7.4 33.7 Mabelah South PH 9-F3-P184 22.0 ------7.4 33.7 Manoma 1-F1OHL-P067 22.0 - - - - 7.7 35.1 7.8 35.1 Manoma 1-F2OHL-P067 22.0 - - - - 7.8 35.4 7.8 35.4 Palace Communication-F1-P033 22.0 - - - - 1.0 4.3 1.0 4.3 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Mabelah A-A P063 ------100.5 100.5 101.9 104.0 99.9 100.4 101.0 103.8 Mabelah A-B P063 ------100.5 100.5 101.9 104.0 99.9 100.4 101.0 103.8 Mabelah A-C P063 ------100.5 100.5 101.9 104.0 99.9 100.4 101.0 103.8 Mabelah South PH 7-A P141 ------100.3 100.4 103.4 104.3 99.8 100.3 103.0 104.2 Mabelah South PH 7-B P141 ------100.3 100.4 103.4 104.3 99.8 100.3 103.0 104.2 Mabelah South PH 7-C P141 ------100.3 100.4 103.4 104.3 99.8 100.3 103.0 104.2 Mabelah South PH 8-A P157 ------100.5 100.5 100.9 104.3 100.0 100.4 101.2 104.3 Mabelah South PH 8-B P157 ------100.5 100.5 100.9 104.3 100.0 100.4 101.2 104.3 Mabelah South PH 8-C P157 ------100.5 100.5 101.0 104.3 100.0 100.4 101.2 104.3 Mabelah South 9-A P184 ------100.3 100.4 103.0 104.6 Mabelah South 9-B P184 ------100.3 100.4 103.0 104.6 Mabelah South 9-C P184 ------100.3 100.4 103.0 104.6 Manoma 1-A P067 ------99.3 100.5 102.0 104.9 98.8 100.4 101.5 104.7 Manoma 1-B P067 ------99.3 100.5 102.0 104.9 98.8 100.4 101.5 104.7 Palace Communication-- P033 ------100.7 100.5 104.8 105.0 100.2 100.4 104.3 104.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 107 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Mabelah A-A P063 25.0 18.4 - - - - 18.6 14.8 18.8 15.0 Mabelah A-B P063 25.0 18.4 - - - - 18.6 14.8 18.8 15.0 Mabelah A-C P063 25.0 25.0 - - - - 18.5 8.1 18.7 8.2 Mabelah South PH 7-A P141 25.0 25.0 - - - - 13.6 14.5 13.7 14.5 Mabelah South PH 7-B P141 25.0 25.0 - - - - 13.6 14.5 13.7 14.5 Mabelah South PH 7-C P141 25.0 25.0 - - - - 13.3 7.9 13.4 7.9 Mabelah South PH 8-A P157 31.5 25.0 - - - - 20.6 16.0 20.7 15.6 Mabelah South PH 8-B P157 31.5 25.0 - - - - 20.6 16.0 20.7 15.6 Mabelah South PH 8-C P157 31.5 25.0 - - - - 20.5 8.8 20.7 8.6 Mabelah South 9-A P184 25.0 25.0 ------23.9 14.5 Mabelah South 9-B P184 25.0 25.0 ------23.9 14.5 Mabelah South 9-C P184 25.0 25.0 ------23.9 8.0 Manoma 1-A P067 25.0 18.4 - - - - 6.5 11.6 6.5 11.7 Manoma 1-B P067 25.0 18.4 - - - - 6.5 11.6 6.5 11.7 Palace Communication-- P033 25.0 18.4 - - - - 9.5 4.3 9.5 4.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 108 Seeb[GP08] - A GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khoud PH-7 P154 40 34.4 8.6 35.5 89% Shifted to Al Khoudh GSS Al Khoud Shabiya P046 20 21.6 3.4 21.9 110% 22.8 3.2 23.0 115% 24.0 3.4 24.2 121% Upgraded Al Khoud Shabiya(Upgrade) P046 40 ------34.4 4.9 34.7 87% Wadi Al Aresh P115 20 15.2 10.2 18.3 92% 15.6 5.1 16.5 82% 16.0 5.3 16.8 84% 16.1 5.3 17.0 85% Wadi Al Lawami P117 40 29.0 10.8 30.9 77% 29.8 9.8 31.4 78% 30.5 10.0 32.1 80% 30.7 10.1 32.4 81% Wadi Bahayis (RGO) P098 20 15.9 5.6 16.9 85% 16.4 5.4 17.2 86% 16.7 5.5 17.6 88% 16.9 5.5 17.8 89% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khoud PH-7 P154 40 4.8 0.0 4.8 12% Shifted to Al Khoudh GSS Al Khoud Shabiya P046 20 3.0 0.8 3.1 16% 4.1 1.1 4.2 21% 4.3 1.1 4.4 22% Upgraded Al Khoud Shabiya(Upgrade) P046 40 ------6.2 1.6 6.4 16% Wadi Al Aresh P115 20 9.2 4.4 10.2 51% 2.7 1.3 3.0 15% 2.8 1.3 3.1 15% 2.8 1.3 3.1 15% Wadi Al Lawami P117 40 3.3 0.8 3.4 9% 5.6 1.4 5.7 14% 5.7 1.4 5.8 15% 5.7 1.4 5.9 15% Wadi Bahayis (RGO) P098 20 3.3 2.3 4.0 20% 2.6 1.8 3.1 16% 2.6 1.8 3.2 16% 2.7 1.8 3.2 16% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Khoud PH 7-F1-P154 22.0 13.4 60.6 ------Al Khoud PH 7-F2-P154 22.0 13.5 61.2 ------Al Khoud PH 7-F3-P154 22.0 8.9 40.1 ------Al Khoud Shabiya-F1-P046 22.0 10.9 49.6 11.6 52.4 12.2 55.3 11.6 52.7 Al Khoud Shabiya-F2-P046 22.0 11.1 50.4 11.8 53.3 12.4 56.2 11.8 53.5 Al Khoud Shabiya-F3-P046 22.0 ------11.6 52.8 Wadi Al Aresh-F1-P115 22.0 8.8 40.0 8.1 36.6 8.3 37.5 8.3 37.8 Wadi Al Aresh-F2-P115 22.0 8.9 40.3 8.2 37.0 8.3 37.8 8.4 38.2 Wadi Al Lawami-F1-P117 22.0 10.0 45.5 10.5 47.6 10.7 48.7 10.8 49.1 Wadi Al Lawami-F2-P117 22.0 10.0 45.4 10.5 47.6 10.7 48.7 10.8 49.1 Wadi Al Lawami-F3-P117 22.0 10.7 48.6 10.5 47.6 10.7 48.7 10.8 49.1 Wadi Bahayis (RGO)-F1-P098 22.0 8.4 38.2 8.6 39.1 8.8 39.9 8.9 40.3 Wadi Bahayis (RGO)-F2-P098 22.0 8.4 37.9 8.5 38.7 8.7 39.6 8.8 39.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 109 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Khoud PH 7-A P154 100.2 101.0 102.3 105.9 ------Al Khoud PH 7-B P154 100.2 101.0 102.3 105.9 ------Al Khoud PH 7-C P154 100.5 101.0 103.7 106.0 ------Al Khoud Shabiya-A P046 100.1 101.0 103.5 105.7 100.1 100.9 103.4 105.5 100.0 100.9 103.2 105.5 100.1 100.9 103.4 105.5 Al Khoud Shabiya-B P046 100.1 101.0 103.5 105.7 100.0 100.9 103.4 105.5 100.0 100.9 103.2 105.5 100.0 100.9 103.4 105.5 Al Khoud Shabiya-C P046 ------100.3 101.0 103.6 105.6 Wadi Al Aresh-A P115 100.2 100.6 101.5 104.0 100.4 100.9 103.4 105.5 100.4 100.9 103.3 105.5 100.4 100.9 103.3 105.5 Wadi Al Aresh-B P115 100.2 100.6 101.5 104.0 100.4 100.9 103.4 105.5 100.4 100.9 103.3 105.5 100.4 100.9 103.3 105.5 Wadi Al Lawami-A P117 100.9 101.0 103.2 105.8 100.9 101.0 103.2 105.6 100.9 101.0 103.2 105.6 100.9 101.0 103.1 105.6 Wadi Al Lawami-B P117 100.9 101.0 103.2 105.8 100.9 101.0 103.2 105.6 100.9 101.0 103.2 105.6 100.9 101.0 103.1 105.6 Wadi Al Lawami-C P117 100.9 101.0 103.0 105.8 100.9 101.0 103.2 105.6 100.9 101.0 103.2 105.6 100.9 101.0 103.1 105.6 Wadi Bahayis (RGO)-A P098 100.9 101.0 103.6 105.2 100.9 101.0 103.7 105.4 100.9 101.0 103.7 105.4 100.9 101.0 103.7 105.4 Wadi Bahayis (RGO)-B P098 100.9 101.0 103.6 105.2 100.9 101.0 103.7 105.4 100.9 101.0 103.7 105.4 100.9 101.0 103.7 105.4 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Khoud PH 7-A P154 25.0 25.0 13.5 14.5 ------Al Khoud PH 7-B P154 25.0 25.0 13.5 14.5 ------Al Khoud PH 7-C P154 25.0 25.0 13.2 7.6 ------Al Khoud Shabiya-A P046 25.0 18.4 9.3 13.0 9.3 13.1 9.3 13.2 9.3 13.1 Al Khoud Shabiya-B P046 25.0 18.4 9.4 13.0 9.3 13.1 9.3 13.2 9.4 13.1 Al Khoud Shabiya-C P046 25.0 25.0 ------8.9 7.1 Wadi Al Aresh-A P115 25.0 18.4 11.4 13.5 11.3 13.4 11.3 13.4 11.4 13.4 Wadi Al Aresh-B P115 25.0 18.4 11.7 13.5 11.7 13.4 11.7 13.4 11.7 13.4 Wadi Al Lawami-A P117 25.0 20.0 21.2 14.6 21.0 14.6 21.1 14.6 21.2 14.7 Wadi Al Lawami-B P117 25.0 20.0 21.3 14.6 21.0 14.6 21.1 14.6 21.2 14.7 Wadi Al Lawami-C P117 25.0 25.0 21.3 8.1 21.0 8.1 21.1 8.1 21.2 8.1 Wadi Bahayis (RGO)-A P098 25.0 20.0 20.7 14.2 20.5 14.2 20.6 14.2 20.7 14.3 Wadi Bahayis (RGO)-B P098 25.0 20.0 20.7 14.2 20.4 14.2 20.5 14.2 20.6 14.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 110 Seeb[GP08] - B GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Hail South 2 P153 40 24.3 9.7 26.2 66% 24.9 8.2 26.2 66% 25.3 8.3 26.6 66% 25.4 8.4 26.8 67% New Al Khoud P047 20 13.2 4.7 14.0 70% 13.9 4.6 14.6 73% 14.7 4.8 15.4 77% 11.6 3.8 12.2 61% Seeb Grid GP08 20 11.3 5.5 12.5 63% 11.6 3.8 12.2 61% 11.8 3.9 12.5 62% 11.9 3.9 12.6 63% Seeb05(Boulevard) P186 40 17.7 7.0 19.0 48% 17.7 5.8 18.6 47% 17.7 5.8 18.6 47% 17.7 5.8 18.6 47% Sultan School P029 20 19.4 8.2 21.1 106% 19.9 6.5 20.9 105% 20.2 6.6 21.2 106% 20.3 6.7 21.4 107% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Hail South 2 P153 40 3.3 1.9 3.8 10% 4.2 2.4 4.8 12% 4.2 2.4 4.9 12% 4.3 2.4 4.9 12% New Al Khoud P047 20 2.2 1.4 2.6 13% 2.3 1.4 2.7 13% 2.4 1.5 2.8 14% 1.9 1.2 2.2 11% Seeb Grid GP08 20 4.1 2.1 4.6 23% 1.6 0.8 1.8 9% 1.6 0.8 1.8 9% 1.6 0.8 1.8 9% Seeb05(Boulevard) P186 40 2.9 0.0 2.9 7% 3.4 0.0 3.4 9% 3.4 0.0 3.4 9% 3.4 0.0 3.4 9% Sultan School P029 20 2.8 1.5 3.2 16% 3.4 1.9 3.8 19% 3.4 1.9 3.9 19% 3.4 1.9 3.9 20% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Hail South 2-F1-P153 22.0 6.9 31.5 8.6 39.1 8.7 39.6 8.8 39.9 Al Hail South 2-F2-P153 22.0 6.9 31.4 8.6 39.1 8.7 39.6 8.8 39.9 Al Hail South 2-F3-P153 22.0 11.9 53.8 8.6 39.1 8.7 39.6 8.8 39.9 New Al Khoud-F1-P047 22.0 6.8 31.0 7.3 32.9 7.7 34.8 6.0 27.3 New Al Khoud-F2-P047 22.0 7.1 32.0 7.3 32.9 7.7 34.8 6.0 27.3 Seeb Grid-F1-GP08 22.0 6.1 27.6 6.0 27.2 6.1 27.8 6.2 28.0 Seeb Grid-F2-GP08 22.0 6.1 27.7 6.0 27.3 6.1 27.9 6.2 28.1 Seeb05 (Boulevard)-F1-P186 22.0 6.6 30.1 6.1 27.6 6.1 27.6 6.1 27.6 Seeb05 (Boulevard)-F2-P186 22.0 6.6 30.1 6.1 27.6 6.1 27.6 6.1 27.6 Seeb05 (Boulevard)-F3-P186 22.0 5.3 23.9 6.1 27.6 6.1 27.6 6.1 27.6 Sultan School-F1-P029 22.0 10.7 48.3 10.6 48.1 10.7 48.7 10.8 49.1 Sultan School-F2-P029 22.0 10.4 47.3 10.4 47.0 10.5 47.6 10.6 48.0 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Hail South 2-A P153 100.6 101.0 103.6 105.6 100.5 100.9 103.3 105.4 100.5 100.9 103.3 105.4 100.5 100.9 103.3 105.4 Al Hail South 2-B P153 100.6 101.0 103.6 105.6 100.5 100.9 103.3 105.4 100.5 100.9 103.3 105.4 100.5 100.9 103.3 105.4 Al Hail South 2-C P153 100.3 100.9 101.8 105.3 100.5 100.9 103.3 105.4 100.5 100.9 103.3 105.4 100.5 100.9 103.3 105.4 New Al Khoud-A P047 100.7 101.0 103.8 105.5 100.6 101.0 103.8 105.5 100.6 101.0 103.7 105.4 100.7 101.0 104.2 105.6 New Al Khoud-B P047 100.6 101.0 103.8 105.5 100.6 101.0 103.8 105.5 100.6 101.0 103.7 105.4 100.7 101.0 104.2 105.6 Seeb Grid-A GP08 101.0 101.0 104.1 105.3 101.0 101.0 104.6 105.7 101.0 101.0 104.6 105.7 101.0 101.0 104.5 105.7 Seeb Grid-B GP08 101.0 101.0 104.1 105.3 101.0 101.0 104.6 105.7 101.0 101.0 104.6 105.7 101.0 101.0 104.5 105.7 Seeb05 (Boulevard)-A P186 100.9 101.0 104.0 106.0 100.9 101.0 104.4 106.0 100.9 101.0 104.4 106.0 100.9 101.0 104.4 106.0 Seeb05 (Boulevard)-B P186 100.9 101.0 104.0 106.0 100.9 101.0 104.4 106.0 100.9 101.0 104.4 106.0 100.9 101.0 104.4 106.0 Seeb05 (Boulevard)-C P186 100.9 101.0 104.4 106.0 100.9 101.0 104.4 106.0 100.9 101.0 104.4 106.0 100.9 101.0 104.4 106.0 Sultan School-A P029 100.7 101.0 102.4 105.4 100.7 101.0 103.0 105.3 100.7 101.0 103.0 105.3 100.7 101.0 103.0 105.3 Sultan School-B P029 100.7 101.0 102.4 105.4 100.7 101.0 103.0 105.3 100.7 101.0 103.0 105.3 100.7 101.0 103.0 105.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 111 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Hail South 2-A P153 25.0 25.0 13.7 13.5 12.9 13.5 13.8 13.8 13.4 13.6 Al Hail South 2-B P153 25.0 25.0 13.7 13.5 12.9 13.5 13.8 13.8 13.4 13.6 Al Hail South 2-C P153 25.0 25.0 13.6 7.8 12.8 7.5 13.6 7.6 13.2 7.5 New Al Khoud-A P047 25.0 20.0 12.4 7.3 11.8 7.2 12.5 7.3 12.1 7.2 New Al Khoud-B P047 25.0 20.0 12.4 7.3 11.8 7.2 12.5 7.3 12.1 7.2 Seeb Grid-A GP08 25.0 20.0 23.7 14.8 21.2 14.4 23.7 14.8 22.6 14.7 Seeb Grid-B GP08 25.0 20.0 23.7 14.8 21.2 14.4 23.8 14.8 22.6 14.7 Seeb05 (Boulevard)-A P186 25.0 25.0 20.1 14.0 18.3 13.6 20.1 13.9 19.3 13.8 Seeb05 (Boulevard)-B P186 25.0 25.0 20.1 14.0 18.3 13.6 20.1 13.9 19.3 13.8 Seeb05 (Boulevard)-C P186 25.0 25.0 20.1 7.7 18.3 7.6 20.1 7.7 19.3 7.7 Sultan School-A P029 25.0 20.0 17.3 14.3 16.0 14.0 17.3 14.4 16.7 14.2 Sultan School-B P029 25.0 20.0 17.3 14.3 16.0 14.0 17.3 14.4 16.7 14.2

MEDC Distribution System Capability Statement [2021-2023]-V2.0 112 Mawaleh South[GP05] - A GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Hail North 2 P028 20 19.9 5.0 20.5 103% 20.4 5.0 21.0 105% 20.7 5.1 21.3 107% 20.8 5.2 21.5 107% Al Khoud PH-3 P048 20 19.8 4.0 20.2 101% 20.9 4.2 21.3 107% 22.0 4.5 22.4 112% 17.2 3.5 17.6 88% Mawaleh C P072 20 15.5 3.4 15.9 80% 15.9 3.6 16.3 82% 16.1 3.7 16.5 83% 16.1 3.7 16.5 83% Mawaleh South Grid GP05 20 17.5 8.2 19.3 97% 17.9 5.9 18.9 94% 18.2 6.0 19.1 96% 18.2 6.0 19.1 96% Royal Flight P100 20 6.8 2.7 7.3 37% 6.8 2.2 7.2 36% 6.8 2.2 7.2 36% 6.8 2.2 7.2 36% Rusail B P101 10 Standby PSS Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Hail North 2 P028 20 2.6 1.9 3.2 16% 3.1 2.2 3.8 19% 3.2 2.3 3.9 20% 3.0 2.5 3.9 20% Al Khoud PH-3 P048 20 2.4 1.4 2.8 14% 3.3 2.0 3.9 20% 3.5 2.1 4.1 21% 2.5 2.1 3.2 16% Mawaleh C P072 20 3.0 1.1 3.2 16% 2.8 1.0 3.0 15% 2.8 1.1 3.0 15% 2.3 1.9 3.0 15% Mawaleh South Grid GP05 20 4.6 3.0 5.5 28% 2.9 1.9 3.5 17% 2.9 1.9 3.5 18% 2.7 2.2 3.5 18% Royal Flight P100 20 1.3 0.5 1.4 7% 1.2 0.5 1.3 7% 1.2 0.5 1.3 7% 1.0 0.8 1.3 7% Rusail B P101 10 Standby PSS 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Hail North 2-F1-P028 22.0 10.3 46.8 10.6 48.0 10.7 48.7 10.8 49.0 Al Hail North 2-F2-P028 22.0 10.4 47.2 10.7 48.4 10.8 49.1 10.9 49.5 Al Khoud PH 3-F1-P048 22.0 10.2 46.4 10.9 49.2 11.5 52.0 8.9 40.4 Al Khoud PH 3-F2-P048 22.0 10.2 46.0 10.8 48.9 11.4 51.6 8.8 40.1 Mawaleh C-F1-P072 22.0 8.1 36.5 8.3 37.4 8.4 37.9 8.4 37.9 Mawaleh C-F2-P072 22.0 8.1 36.7 8.3 37.7 8.4 38.2 8.4 38.2 Mawaleh South Grid-F1-GP05 22.0 9.9 44.7 9.6 43.6 9.8 44.2 9.8 44.2 Mawaleh South Grid-F2-GP05 22.0 9.9 44.9 9.7 43.9 9.8 44.5 9.8 44.5 Royal Flight-F1-P100 22.0 3.5 16.0 3.5 15.8 3.5 15.8 3.5 15.8 Royal Flight-F2-P100 22.0 3.5 16.0 3.5 15.8 3.5 15.8 3.5 15.8 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Hail North 2-A P028 99.4 99.9 101.8 103.8 99.4 99.9 101.7 103.6 99.4 99.9 101.7 103.6 99.3 99.9 101.6 103.7 Al Hail North 2-B P028 99.4 99.9 101.8 103.8 99.4 99.9 101.7 103.6 99.3 99.9 101.7 103.6 99.3 99.9 101.6 103.7 Al Khoud PH 3-A P048 99.8 100.0 102.5 104.0 99.7 99.9 102.4 103.8 99.7 99.9 102.3 103.8 99.8 100.0 102.8 104.0 Al Khoud PH 3-B P048 99.8 100.0 102.5 104.0 99.8 99.9 102.4 103.8 99.7 99.9 102.3 103.8 99.8 100.0 102.8 104.0 Mawaleh C-A P072 99.8 100.0 102.7 104.1 99.8 100.0 102.7 104.1 99.8 100.0 102.6 104.1 99.8 100.0 102.6 104.2 Mawaleh C-B P072 99.8 100.0 102.7 104.1 99.8 100.0 102.7 104.1 99.8 100.0 102.6 104.1 99.8 100.0 102.6 104.2 Mawaleh South Grid-A GP05 100.0 100.0 101.8 103.6 100.0 100.0 102.4 104.0 100.0 100.0 102.4 103.9 100.0 100.0 102.4 104.0 Mawaleh South Grid-B GP05 100.0 100.0 101.8 103.6 100.0 100.0 102.4 104.0 100.0 100.0 102.4 103.9 100.0 100.0 102.4 104.0 Royal Flight-A P100 99.8 100.0 103.4 104.3 99.8 100.0 103.5 104.4 99.8 100.0 103.5 104.4 99.8 100.0 103.5 104.4 Royal Flight-B P100 99.8 100.0 103.4 104.3 99.8 100.0 103.5 104.4 99.8 100.0 103.5 104.4 99.8 100.0 103.5 104.4

MEDC Distribution System Capability Statement [2021-2023]-V2.0 113 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Hail North 2-A P028 25.0 18.4 12.6 13.8 12.6 13.8 12.5 13.8 12.6 13.8 Al Hail North 2-B P028 25.0 18.4 12.6 13.8 12.6 13.8 12.5 13.8 12.6 13.8 Al Khoud PH 3-A P048 25.0 20.0 17.3 14.4 17.4 14.5 17.2 14.5 17.3 14.2 Al Khoud PH 3-B P048 25.0 20.0 17.4 14.4 17.4 14.5 17.2 14.5 17.4 14.2 Mawaleh C-A P072 25.0 20.0 17.7 13.9 17.7 13.9 17.5 13.9 17.7 13.9 Mawaleh C-B P072 25.0 20.0 17.7 13.9 17.7 13.9 17.5 13.9 17.7 13.9 Mawaleh South Grid-A GP05 25.0 18.4 23.2 15.8 23.2 15.7 22.9 15.7 23.2 15.8 Mawaleh South Grid-B GP05 25.0 18.4 23.2 15.8 23.2 15.7 22.9 15.7 23.2 15.8 Royal Flight-A P100 25.0 18.4 13.5 13.0 13.5 13.0 13.4 13.0 13.5 13.0 Royal Flight-B P100 25.0 18.4 13.5 13.0 13.5 13.0 13.4 13.0 13.5 13.0

MEDC Distribution System Capability Statement [2021-2023]-V2.0 114 Mawaleh South[GP05] - B GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Hail South 1 P030 20 20.3 7.2 21.5 108% 20.8 6.8 21.9 110% 21.1 6.9 22.2 111% 21.2 7.0 22.4 112% Al Khoud PH-6 P049 20 17.9 3.6 18.3 91% Shifted to Al Khoudh Grid Mawaleh A P070 40 26.8 10.1 28.6 72% Shifted to Al Khoudh Grid Mawaleh B P071 40 31.1 12.0 33.3 83% 31.9 10.5 33.6 84% 32.3 10.6 34.0 85% 32.3 10.6 34.0 85% Mawaleh South05 P148 40 20.0 7.9 21.5 54% 20.5 6.7 21.6 54% 20.8 6.8 21.9 55% 20.8 6.8 21.9 55% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Hail South 1 P030 20 2.6 1.3 2.9 15% 3.6 1.8 4.0 20% 3.6 1.8 4.1 20% 3.2 2.6 4.1 20% Al Khoud PH-6 P049 20 4.4 0.0 4.4 22% Shifted to Al Khoudh Grid Mawaleh A P070 40 3.1 2.0 3.7 9% Shifted to Al Khoudh Grid Mawaleh B P071 40 4.2 2.5 4.9 12% 5.3 3.2 6.1 15% 5.3 3.2 6.2 16% 4.8 4.0 6.2 16% Mawaleh South05 P148 40 2.0 2.6 3.3 8% 2.4 3.1 4.0 10% 2.4 3.2 4.0 10% 3.1 2.6 4.0 10% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading AL Hail South 1-F1-P030 22.0 11.0 50.0 11.2 50.7 11.3 51.4 11.4 51.8 AL Hail South 1-F2-P030 22.0 11.0 50.0 11.2 50.7 11.3 51.4 11.4 51.8 Al Khoud PH 6-F1-P049 22.0 9.2 41.6 ------Al Khoud PH 6-F2-P049 22.0 9.4 42.4 ------Mawaleh A-F1-P070 22.0 15.1 68.6 ------Mawaleh A-F2-P070 22.0 6.9 31.3 ------Mawaleh A-F3-P070 22.0 7.2 32.7 ------Mawaleh B-F1-P071 22.0 12.2 55.2 11.5 51.9 11.6 52.6 11.6 52.6 Mawaleh B-F2-P071 22.0 10.1 45.8 11.4 51.8 11.6 52.5 11.6 52.5 Mawaleh B-F3-P071 22.0 12.0 54.5 11.4 51.7 11.6 52.5 11.6 52.5 Mawaleh South 5-F1-P148 22.0 5.2 23.4 7.3 33.1 7.4 33.5 7.4 33.5 Mawaleh South 5-F2-P148 22.0 5.0 22.8 7.2 32.8 7.3 33.2 7.3 33.2 Mawaleh South 5-F3-P148 22.0 11.6 52.8 7.3 32.9 7.4 33.3 7.4 33.3 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min AL Hail South 1-A P030 99.6 99.9 101.1 104.0 99.6 99.9 101.2 103.8 99.6 99.9 101.2 103.8 99.6 99.9 101.1 103.9 AL Hail South 1-B P030 99.6 99.9 101.1 104.0 99.6 99.9 101.2 103.8 99.6 99.9 101.2 103.8 99.6 99.9 101.1 103.9 Al Khoud PH 6-A P049 99.3 99.9 102.0 104.4 ------Al Khoud PH 6-B P049 99.3 99.9 102.0 104.4 ------Mawaleh A-A P070 99.7 100.0 100.5 103.9 ------Mawaleh A-B P070 99.9 100.0 102.9 104.2 ------Mawaleh A-C P070 99.9 100.0 102.9 104.2 ------Mawaleh B-A P071 99.8 100.0 101.0 103.9 99.8 100.0 101.6 103.8 99.8 100.0 101.5 103.8 99.8 100.0 101.5 103.9 Mawaleh B-B P071 99.8 100.0 101.8 104.0 99.8 100.0 101.8 103.8 99.8 100.0 101.7 103.8 99.8 100.0 101.7 103.9 Mawaleh B-C P071 99.8 100.0 101.4 104.0 99.8 100.0 101.9 103.9 99.8 100.0 101.9 103.9 99.8 100.0 101.9 103.9 Mawaleh South 5-A P148 99.9 100.0 103.0 104.1 99.8 100.0 102.6 103.8 99.8 100.0 102.6 103.8 99.8 100.0 102.6 103.6 Mawaleh South 5-B P148 99.9 100.0 103.1 104.1 99.8 100.0 102.6 103.8 99.8 100.0 102.6 103.8 99.8 100.0 102.6 103.6 Mawaleh South 5-C P148 99.7 100.0 101.0 103.6 99.8 100.0 102.7 103.8 99.8 100.0 102.6 103.8 99.8 100.0 102.6 103.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 115 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV AL Hail South 1-A P030 25.0 25.0 16.1 14.2 15.5 14.1 15.6 14.1 15.8 14.2 AL Hail South 1-B P030 25.0 25.0 16.1 14.2 15.5 14.1 15.6 14.1 15.8 14.2 Al Khoud PH 6-A P049 25.0 20.0 12.0 15.3 ------Al Khoud PH 6-B P049 25.0 20.0 12.0 15.3 ------Mawaleh A-A P070 25.0 18.4 18.6 9.1 ------Mawaleh A-B P070 25.0 18.4 21.1 8.5 ------Mawaleh A-C P070 25.0 25.0 22.0 8.9 ------Mawaleh B-A P071 25.0 18.4 20.1 8.4 19.2 8.3 19.3 8.3 19.6 8.4 Mawaleh B-B P071 25.0 18.4 19.0 8.6 19.0 8.7 19.3 8.8 19.6 8.8 Mawaleh B-C P071 25.0 25.0 20.1 9.2 19.2 9.1 19.3 9.1 19.6 9.1 Mawaleh South 5-A P148 25.0 25.0 18.9 7.8 18.2 14.2 18.3 14.2 18.5 14.3 Mawaleh South 5-B P148 25.0 25.0 18.9 7.7 18.2 14.2 18.3 14.2 18.6 14.3 Mawaleh South 5-C P148 25.0 25.0 19.0 8.3 18.1 7.9 18.2 7.9 18.5 7.9

MEDC Distribution System Capability Statement [2021-2023]-V2.0 116 Al Khoudh GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khoud PH-6 P049 20 - - - - 18.9 3.8 19.3 96% 19.9 4.0 20.3 102% 15.1 3.1 15.4 77% Al Khoud PH-7 P154 40 - - - - 36.3 9.1 37.4 94% 38.2 9.6 39.4 99% 32.1 8.0 33.1 83% Al Khoud Shabiya(B) P187 20 ------9.8 3.2 10.3 52% Mawaleh A P070 40 - - - - 27.5 9.0 28.9 72% 27.8 9.2 29.3 73% 27.8 9.2 29.3 73% Al Bander P197 40 ------14.0 4.6 14.7 37% 14.0 4.6 14.7 37% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Khoud PH-6 P049 20 - - - - 3.5 0.0 3.5 18% 3.7 0.0 3.7 19% 2.2 1.8 2.8 14% Al Khoud PH-7 P154 40 - - - - 6.8 0.0 6.8 17% 7.2 0.0 7.2 18% 4.7 3.9 6.1 15% Al Khoud Shabiya(B) P187 20 ------1.5 1.2 1.9 9% Mawaleh A P070 40 - - - - 4.4 2.9 5.3 13% 4.5 2.9 5.4 13% 4.1 3.4 5.4 13% Al Bander P197 40 ------1.8 0.9 2.0 5% 1.6 1.3 2.1 5% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Khoud PH-1P049 22.0 - - 9.7 44.0 10.2 46.4 7.7 34.9 Al Khoud PH-1P049 22.0 - - 9.9 44.8 10.4 47.3 7.9 35.6 Al Khoud PH-1P154 22.0 - - 12.7 57.4 13.4 60.6 11.1 50.5 Al Khoud PH-1P154 22.0 - - 12.8 58.1 13.5 61.3 11.3 51.1 Al Khoud PH-1P154 22.0 - - 12.7 57.8 13.5 61.0 11.2 50.8 Al Khoud Shabiya(B)-F1-P187 22.0 ------5.1 23.0 Al Khoud Shabiya(B)-F2-P187 22.0 ------5.1 23.0 Mawaleh A-F1-P070 22.0 - - 9.9 44.7 10.0 45.3 10.0 45.3 Mawaleh A-F2-P070 22.0 - - 9.7 44.1 9.9 44.6 9.9 44.6 Mawaleh A-F3-P070 22.0 - - 9.8 44.3 9.9 44.9 9.9 44.9 Al Bander-F1-P197 22.0 - - - - 4.9 22.2 4.9 22.2 Al Bander-F2-P197 22.0 - - - - 4.9 22.2 4.9 22.2 Al Bander-F3-P197 22.0 - - - - 4.9 22.2 4.9 22.2 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Khoud PH 6-A P049 - - - - 99.7 100.9 102.3 105.4 100.4 100.9 102.9 105.4 100.7 101.0 103.7 105.5 Al Khoud PH 6-B P049 - - - - 99.7 100.9 102.3 105.4 100.4 100.9 102.9 105.4 100.6 101.0 103.7 105.5 Al Khoud PH 7-A P154 - - - - 99.8 100.9 101.7 105.4 100.5 100.9 102.3 105.4 100.7 101.0 103.0 105.5 Al Khoud PH 7-B P154 - - - - 99.8 100.9 101.7 105.4 100.5 100.9 102.3 105.4 100.7 101.0 103.0 105.5 Al Khoud PH 7-C P154 - - - - 99.8 100.9 101.7 105.4 100.5 100.9 102.3 105.4 100.7 101.0 103.0 105.5 Al Khoud Shabiya(B)-A P187 ------100.8 101.0 104.1 105.3 Al Khoud Shabiya(B)-B P187 ------100.8 101.0 104.1 105.3 Mawaleh A-A P070 - - - - 100.1 100.9 102.4 104.9 100.7 100.9 103.1 104.9 100.9 101.0 103.3 105.0 Mawaleh A-B P070 - - - - 100.1 100.9 102.4 104.9 100.7 100.9 103.1 104.9 100.9 101.0 103.3 105.0 Mawaleh A-C P070 - - - - 100.1 100.9 102.5 104.9 100.7 100.9 103.2 104.9 100.9 101.0 103.4 105.0 MOD Al Bander-A P197 ------100.8 100.9 104.2 105.3 101.0 101.0 104.4 105.4 MOD Al Bander-B P197 ------100.8 100.9 104.2 105.3 101.0 101.0 104.4 105.4 MOD Al Bander-C P197 ------100.8 100.9 104.2 105.3 101.0 101.0 104.4 105.4

MEDC Distribution System Capability Statement [2021-2023]-V2.0 117 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Khoud PH 6-A P049 25.0 20.0 - - 13.4 15.6 13.5 15.8 13.6 15.4 Al Khoud PH 6-B P049 25.0 20.0 - - 13.4 15.6 13.5 15.8 13.6 15.4 Al Khoud PH 7-A P154 25.0 25.0 - - 16.5 14.8 16.7 14.9 16.9 14.6 Al Khoud PH 7-B P154 25.0 25.0 - - 16.5 14.8 16.7 14.9 16.9 14.6 Al Khoud PH 7-C P154 25.0 25.0 - - 16.4 8.1 16.5 8.2 16.8 8.0 Al Khoud Shabiya(B)-A P187 25.0 25.0 ------13.4 13.1 Al Khoud Shabiya(B)-B P187 25.0 25.0 ------13.4 13.1 Mawaleh A-A P070 25.0 18.4 - - 18.9 15.5 19.0 15.6 19.4 15.7 Mawaleh A-B P070 25.0 18.4 - - 18.9 15.5 19.0 15.6 19.4 15.7 Mawaleh A-C P070 25.0 25.0 - - 18.8 8.9 18.9 9.0 19.3 9.0 MOD Al Bander-A P197 25.0 25.0 - - - - 19.0 13.7 19.3 13.8 MOD Al Bander-B P197 25.0 25.0 - - - - 19.0 13.7 19.3 13.8 MOD Al Bander-C P197 25.0 25.0 - - - - 18.9 7.6 19.2 7.6

MEDC Distribution System Capability Statement [2021-2023]-V2.0 118 Mawaleh North [GP01] GSS [Zone 3] - System Study Results Primary Substations Maximum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Hail North 1 P027 20 15.7 5.7 17.2 86% 16.1 5.3 16.9 85% 16.3 5.4 17.2 86% Upgraded Al Hail North 1(Upgrade) P027 40 ------16.4 5.4 17.3 43% City Centre P073 20 14.4 6.5 15.8 79% 14.8 4.9 15.5 78% 15.0 4.9 15.7 79% 15.0 4.9 15.7 79% Mawaleh North P069 20 9.4 2.6 9.8 49% 9.6 2.8 10.1 50% 9.8 2.9 10.2 51% Upgraded Mawaleh North Grid GP01 40 29.8 12.1 32.1 80% 34.8 11.4 36.6 91% 37.8 12.4 39.7 99% 32.8 10.8 34.5 86% Mawaleh North(Upgrade) P069 40 ------29.9 9.8 31.5 79% Primary Substations Minimum Demand and Percentage Loading Firm 2020 2021 2022 2023 Primary Substation P.No. Capacity (MVA) MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % MW MVAr MVA % Al Hail North 1 P027 20 2.2 1.4 2.6 13% 2.6 1.7 3.1 16% 2.7 1.7 3.1 16% Upgraded Al Hail North 1(Upgrade) P027 40 ------2.4 2.0 3.2 8% City Centre P073 20 2.8 1.3 3.1 16% 2.6 1.2 2.8 14% 2.6 1.2 2.9 14% 2.2 1.8 2.9 14% Mawaleh North P069 20 1.4 0.0 1.4 7% 1.8 0.0 1.8 9% 1.9 0.0 1.9 9% Upgraded Mawaleh North Grid GP01 40 5.4 1.0 5.5 14% 6.6 1.3 6.7 17% 7.1 1.4 7.3 18% 4.9 4.0 6.3 16% Mawaleh North(Upgrade) P069 40 ------4.4 3.7 5.8 14% 33kV Feeder Loads Rating 2020 2021 2022 2023 Primary (MVA) MVA %Loading MVA %Loading MVA %Loading MVA %Loading Al Hail North 1-F1-P027 22.0 8.8 40.1 8.7 39.3 8.8 39.9 5.8 26.5 Al Hail North 1-F2-P027 22.0 8.7 39.2 8.5 38.5 8.6 39.1 5.7 26.0 Al Hail North 1-F3-P027 22.0 ------5.8 26.2 City Centre-F1-P073 22.0 8.0 36.3 7.9 35.6 7.9 36.0 7.9 36.0 City Centre-F2-P073 22.0 8.0 36.3 7.9 35.6 8.0 36.1 8.0 36.1 Mawaleh North-F1-P069 22.0 4.9 22.3 5.0 22.9 5.1 23.2 10.7 48.5 Mawaleh North-F2-P069 22.0 4.9 22.4 5.1 23.0 5.2 23.3 10.8 48.9 Mawaleh North-F3-P069 22.0 ------10.5 47.7 Mawaleh North Grid-F1-GP01 22.0 10.8 48.9 11.9 54.0 13.0 59.0 11.2 50.6 Mawaleh North Grid-F2-GP01 22.0 10.9 49.3 12.0 54.3 13.1 59.4 11.2 50.9 Mawaleh North Grid-F3-GP01 22.0 11.4 51.9 14.2 64.2 15.3 69.3 13.4 60.7 Primary Substations Bus Voltages 2020 2021 2022 2023 Primary P.No. 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) 33kV (%) 11kV(%) Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Al Hail North 1-A P027 99.8 100.0 102.3 104.1 99.8 100.0 102.5 104.0 99.8 100.0 102.5 104.0 99.9 100.0 103.2 104.2 Al Hail North 1-B P027 99.8 100.0 102.3 104.1 99.9 100.0 102.5 104.0 99.8 100.0 102.5 104.0 99.9 100.0 103.2 104.2 Al Hail North 1-C P027 ------99.9 100.0 103.2 104.3 City Centre-A P073 99.8 100.0 101.8 104.0 99.8 100.0 102.4 104.1 99.8 100.0 102.4 104.1 99.8 100.0 102.4 104.1 City Centre-B P073 99.8 100.0 101.8 104.0 99.8 100.0 102.4 104.1 99.8 100.0 102.4 104.1 99.8 100.0 102.4 104.1 Mawaleh North-A P069 100.0 100.0 103.4 104.5 100.0 100.0 103.4 104.5 100.0 100.0 103.4 104.5 99.9 100.0 101.8 104.2 Mawaleh North-B P069 100.0 100.0 103.4 104.5 100.0 100.0 103.4 104.5 100.0 100.0 103.4 104.5 99.9 100.0 101.8 104.2 Mawaleh North-C P069 ------99.9 100.0 102.2 104.2 Mawaleh North Grid-A GP01 100.0 100.0 101.5 104.2 100.0 100.0 101.5 104.2 100.0 100.0 101.2 104.2 100.0 100.0 101.7 104.3 Mawaleh North Grid-B GP01 100.0 100.0 101.5 104.2 100.0 100.0 101.5 104.2 100.0 100.0 101.2 104.2 100.0 100.0 101.7 104.3 Mawaleh North Grid-C GP01 100.0 100.0 101.3 104.3 100.0 100.0 100.8 104.2 100.0 100.0 100.5 104.2 100.0 100.0 101.0 104.3

MEDC Distribution System Capability Statement [2021-2023]-V2.0 119 Primary Substation 3-Phase Fault Current Levels (kA)

33kV -Rated SC 11kV -Rated SC 2020 2021 2022 2023 Primary P.No. Capacity Capacity 33kV 11kV 33kV 11kV 33kV 11kV 33kV 11kV Al Hail North 1-A P027 25.0 20.0 17.2 14.9 17.6 15.0 19.1 15.3 18.9 14.9 Al Hail North 1-B P027 25.0 20.0 17.2 14.9 17.6 15.0 19.1 15.3 18.9 14.9 Al Hail North 1-C P027 25.0 25.0 - - - - - 18.8 8.3 City Centre-A P073 25.0 20.0 15.5 13.6 15.8 13.7 17.0 14.0 16.9 13.9 City Centre-B P073 25.0 20.0 15.5 13.6 15.8 13.7 17.0 14.0 16.9 13.9 Mawaleh North-A P069 25.0 18.4 18.8 13.5 19.2 13.6 21.1 13.9 20.9 14.7 Mawaleh North-B P069 25.0 18.4 18.8 13.5 19.2 13.6 21.1 13.9 20.9 14.7 Mawaleh North-C P069 25.0 25.0 ------20.9 8.2 Mawaleh North Grid-A GP01 25.0 25.0 20.7 15.0 21.2 15.2 23.5 15.7 23.2 15.4 Mawaleh North Grid-B GP01 25.0 25.0 20.7 15.0 21.2 15.2 23.5 15.7 23.2 15.4 Mawaleh North Grid-C GP01 25.0 25.0 20.7 8.7 21.2 8.9 23.5 9.1 23.2 9.0

MEDC Distribution System Capability Statement [2021-2023]-V2.0 120

APPENDIX E: INFORMATION ON DISTRIBUTION SYSTEM ASSET S

Appendix E presents the following series of tables, for each grid substation power system model in form of complete technical asset data as of 2020.

Appendix E1 – 33kV Circuits/Feeders Data Appendix E1 presents the circuit length from gird substation up to the 33kV busbar in the primary substation. It specifies the key parameters for the circuits including resistance, reactance, capacitance and the continuous derated thermal rating for the underground cable and overhead line conductor types used. The resistance is specified at 20C AC values.

Explanatory Notes: a) 33kV UGC 300 3C Cu means 33kV underground cable of 300 sq.mm. cross-sectional area, three core type and formed of copper conductor; b) In general, the cables employed are XLPE insulated and armored; c) 33kV OHL 200 Panther ACSR means 33kV overhead line of 200 sq.mm. cross-sectional area (i.e. Panther conductor) of Aluminium Conductor Steel Reinforced type; d) 33kV OHL 100 Dog ACSR means 33kV overhead line of 100 sq.mm. cross-sectional area (i.e. Dog conductor) of Aluminium Conductor Steel Reinforced type; e) Where a single 33kV feeder feeds multiple primary substations [for e.g. circuits in rural areas], the circuit length between the grid substation and each of the connected primary substation on that feeder is calculated and captured individually. This means that there will be few duplicated segments of circuit length. This is explained with the following example:

Hence, the 33kV circuit lengths as documented for;

− PSS 1 = F1-L1 − PSS 4 = F1-L1 + F1-L2 + F1-L3 + F1-L4 − PSS 5 = F1-L1 + F1-L2 + F1-L3 + F1-L5

f) MEDC is currently in process of developing the typical values for zero sequence resistance and zero sequence reactance for future improvements.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 121 Falaj[G23] GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Al Falaj Grid HBB01 Falaj-33A-P178 Falaj-F1-P178 33 33kV UGC 300 3C Cu 0.017 0.062 0.103 260.000 0.385 Al Falaj Grid HBB02 Falaj-33B-P178 Falaj-F2-P178 33 33kV UGC 300 3C Cu 0.036 0.062 0.103 260.000 0.385 Al Falaj Grid HBB01 Mutrah Store-33A-P085 Mutrah Store-F1-P085 33 33kV UGC 300 3C Cu 1.803 0.062 0.103 260.000 0.385 Al Falaj Grid HBB02 Mutrah Store-33B-P085 Mutrah Store-F2-P085 33 33kV UGC 300 3C Cu 1.803 0.062 0.103 260.000 0.385 Al Falaj Grid HBB01 Darsait-N33A-P018 Darsait-F1-P018 33 33kV UGC 300 3C Cu 0.330 0.062 0.103 260.000 0.385 Al Falaj Grid HBB02 Darsait-N33B-P018 Darsait-F2-P018 33 33kV UGC 300 3C Cu 0.342 0.062 0.103 260.000 0.385 Al Falaj Grid HBB01 - 33 33kV UGC 300 3C Cu 3.109 0.062 0.103 260.000 0.385 - - Seaport-F1-P086 33 33kV OHL 200 Panther ACSR 2.386 0.137 0.333 10.900 0.385 - Seaport-33A-P086 33 33kV OHL 200 Panther ACSR 0.892 0.137 0.333 10.900 0.385 Al Falaj Grid HBB01 Jibrooh-33A-P041 Jibrooh-F1-P041 33 33kV UGC 300 3C Cu 3.365 0.062 0.103 260.000 0.385 Al Falaj Grid HBB02 Jibrooh-33B-P041 Jibrooh-F2-P041 33 33kV UGC 300 3C Cu 3.393 0.062 0.103 260.000 0.385 Al Falaj Grid HBB01 - 33 33kV UGC 300 3C Cu 3.109 0.062 0.103 260.000 0.385 - - Seaport-F1-P086 33 33kV OHL 200 Panther ACSR 2.386 0.137 0.333 10.900 0.385 - Jibrooh-33C-P041 33 33kV OHL 200 Panther ACSR 0.727 0.137 0.333 10.900 0.385 Al Falaj Grid HBB02 PDO-33A-P144 PDO-F1-P144 33 33kV UGC 300 3C Cu 1.077 0.062 0.103 260.000 0.385 Al Falaj Grid HBB02 PDO-33B-P144 PDO-F2-P144 33 33kV UGC 300 3C Cu 1.079 0.062 0.103 260.000 0.385 Al Falaj Grid HBB01 PDO-33C-P144 PDO-F3-P144 33 33kV UGC 300 3C Cu 1.109 0.062 0.103 260.000 0.385 Al Falaj Grid HBB01 PDO-33D-P144 PDO-F4-P144 33 33kV UGC 300 3C Cu 1.108 0.062 0.103 260.000 0.385

Mutrah[G21] GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Muttrah Grid HBB01 Bait Al Falaj-33A-P142 Bait Al Falaj-F1-P142 33 33kV UGC 300 3C Cu 1.960 0.062 0.103 260.000 0.385 Muttrah Grid HBB02 Bait Al Falaj-33B-P142 Bait Al Falaj-F2-P142 33 33kV UGC 300 3C Cu 1.969 0.062 0.103 260.000 0.385 Muttrah Grid HBB02 Bait Al Falaj-33C-P142 Bait Al Falaj-F3-P142 33 33kV UGC 300 3C Cu 1.973 0.062 0.103 260.000 0.385 Muttrah Grid HBB01 C.B.D-33A-P173 C.B.D-F1-P173 33 33kV UGC 300 3C Cu 0.062 0.062 0.103 260.000 0.385 Muttrah Grid HBB02 C.B.D-33B-P173 C.B.D-F2-P173 33 33kV UGC 300 3C Cu 0.052 0.062 0.103 260.000 0.385 Muttrah Grid HBB01 C.B.D-33C-P173 C.B.D-F3-P173 33 33kV UGC 300 3C Cu 0.071 0.062 0.103 260.000 0.385 Muttrah Grid HBB01 M.O.D-33-P143-OD M.O.D-F1-P143-OD 33 33kV UGC 300 3C Cu 1.100 0.062 0.103 260.000 0.385 Muttrah Grid HBB01 - 33 33kV OHL 100 Dog ACSR 4.531 0.320 0.350 16.700 0.269 Riyam-F1-P099 - Riyam-33A-P099 33 33kV UGC 300 3C Cu 2.463 0.062 0.103 260.000 0.385 Muttrah Grid HBB01 - 33 33kV OHL 100 Dog ACSR 4.531 0.320 0.350 16.700 0.269 Riyam-F2-P099 - Riyam-33B-P099 33 33kV UGC 300 3C Cu 2.410 0.062 0.103 260.000 0.385 Muttrah Grid HBB01 Ruwi Office-33A-P108 Ruwi Office-F1-P108 33 33kV UGC 300 3C Cu 1.554 0.062 0.103 260.000 0.385 Muttrah Grid HBB02 Ruwi Office-33B-P108 Ruwi Office-F2-P108 33 33kV UGC 300 3C Cu 1.567 0.062 0.103 260.000 0.385

Wadi Al Kabir[G19] -A GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] A Grid H-BB01 - 33 33kV OHL 100 Dog ACSR 3.570 0.320 0.350 16.700 0.269 Qasr al Alam-F1-P090 - Qasr al Alam-33A-P090 33 33kV UGC 300 3C Cu 1.337 0.062 0.103 260.000 0.385 Wadi Kabir A Grid H-BB02 - 33 33kV OHL 100 Dog ACSR 3.571 0.320 0.350 16.700 0.269 Qasr al Alam-F2-P090 - Qasr al Alam-33B-P090 33 33kV UGC 300 3C Cu 1.304 0.062 0.103 260.000 0.385 Wadi Kabir A Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.848 0.137 0.333 10.900 0.385 Muscat 01 Fdr-WK Workshop-P126, - - 33 33kV OHL 200 Panther ACSR 0.350 0.137 0.333 10.900 0.385 Sidab-P119 & WK Housing-P127 - Wadi Al Kabir Housing-33-P127 33 33kV UGC 300 3C Cu 0.323 0.062 0.103 260.000 0.385 Wadi Kabir A Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.848 0.137 0.333 10.900 0.385 Muscat 01 Fdr-WK Workshop-P126, - Wadi Al Kabir Workshop-33-P126 Sidab-P119 & WK Housing-P127 33 33kV OHL 200 Panther ACSR 0.410 0.137 0.333 10.900 0.385 Wadi Kabir A Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.848 0.137 0.333 10.900 0.385 - - Muscat 01 Fdr-WK Workshop-P126, 33 33kV OHL 200 Panther ACSR 0.410 0.137 0.333 10.900 0.385 - - Sidab-P119 & WK Housing-P127 33 33kV OHL 200 Panther ACSR 2.254 0.137 0.333 10.900 0.385 - Sidab-33A-P119 33 33kV OHL 200 Panther ACSR 0.001 0.137 0.333 10.900 0.385 Wadi Kabir A Grid H-BB01 M.B.D. South-33A-P075 M.B.D. South-F1-P075 33 33kV UGC 300 3C Cu 1.933 0.062 0.103 260.000 0.385 Wadi Kabir A Grid H-BB02 M.B.D. South-33B-P075 M.B.D. South-F2-P075 33 33kV UGC 300 3C Cu 1.945 0.062 0.103 260.000 0.385 Wadi Kabir A Grid H-BB01 - 33 33kV UGC 300 3C Cu 1.490 0.062 0.103 260.000 0.385 Walja-F1-P130 - Walja-33A-P130 33 33kV OHL 200 Panther ACSR 0.446 0.137 0.333 10.900 0.385 Wadi Kabir A Grid H-BB02 - 33 33kV UGC 300 3C Cu 1.430 0.062 0.103 260.000 0.385 Walja-F2-P130 - Walja-33B-P130 33 33kV OHL 200 Panther ACSR 0.583 0.137 0.333 10.900 0.385 Wadi Kabir A Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 5.004 0.137 0.333 10.900 0.385 Majlis Oman-F1-P066 - Majlis Oman-33A-P066 33 33kV UGC 300 3C Cu 1.574 0.062 0.103 260.000 0.385 Wadi Kabir A Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 5.004 0.137 0.333 10.900 0.385 Majlis Oman-F2-P066 - Majlis Oman-33B-P066 33 33kV UGC 300 3C Cu 1.543 0.062 0.103 260.000 0.385 Wadi Kabir A Grid H-BB01 Ali Shihani-33A-P125 Ali Shihani-F1-P125 33 33kV UGC 300 3C Cu 0.909 0.062 0.103 260.000 0.385 Wadi Kabir A Grid H-BB02 Ali Shihani-33B-P125 Ali Shihani-F2-P125 33 33kV UGC 300 3C Cu 0.895 0.062 0.103 260.000 0.385

Wadi Al Kabir[G19] -B GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Wadi Kabir B Grid H-BB03 Old Airport-33A-P107 Old Airport-F1-P107 33 33kV UGC 300 3C Cu 2.473 0.062 0.103 260.000 0.385 Wadi Kabir B Grid H-BB04 Old Airport-33B-P107 Old Airport-F2-P107 33 33kV UGC 300 3C Cu 2.481 0.062 0.103 260.000 0.385 Wadi Kabir B Grid H-BB03 Wadi Al Kabir Height 1-33A-P128 Wadi Al Kabir Height 1-F1-P128 33 33kV UGC 300 3C Cu 4.412 0.062 0.103 260.000 0.385

Wadi Kabir B Grid H-BB04 Wadi Al Kabir Height 1-33B-P128 Wadi Al Kabir Height 1-F2-P128 33 33kV UGC 300 3C Cu 4.369 0.062 0.103 260.000 0.385 Wadi Kabir B Grid H-BB03 Ruwi Valley-33A-P174 Ruwi Valley-F1-P174 33 33kV UGC 300 3C Cu 0.122 0.062 0.103 260.000 0.385 Wadi Kabir B Grid H-BB04 Ruwi Valley-33B-P174 Ruwi Valley-F2-P174 33 33kV UGC 300 3C Cu 0.158 0.062 0.103 260.000 0.385 Wadi Kabir B Grid H-BB03 Ruwi Market-33A-P076 Ruwi Market-F1-P076 33 33kV UGC 300 3C Cu 1.609 0.062 0.103 260.000 0.385 Wadi Kabir B Grid H-BB04 Ruwi Market-33B-P076 Ruwi Market-F2-P076 33 33kV UGC 300 3C Cu 1.617 0.062 0.103 260.000 0.385 - Muscat 01 Fdr – This feeder feeds Wadi Kabir Workshop-P126, Sidab-P119 & Wadi Kabir Housing-P127 primary substations

MEDC Distribution System Capability Statement [2021-2023]-V2.0 122 Wadi Adai[G22] - [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Wadi Adai Grid H BB01 Khoula Hospital-33A-P132 Khoula Hospital-F1-P132 33 33kV UGC 300 3C Cu 3.685 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB02 Khoula Hospital-33B-P132 Khoula Hospital-F2-P132 33 33kV UGC 300 3C Cu 3.696 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB01 Khoula Hospital-33C-P132 Khoula Hospital-F3-P132 33 33kV UGC 300 3C Cu 3.164 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB01 Wadi Adai-33A-P175 Wadi Adai-F1-P175 33 33kV UGC 300 3C Cu 0.061 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB02 Wadi Adai-33B-P175 Wadi Adai-F2-P175 33 33kV UGC 300 3C Cu 0.054 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB01 - 33 33kV OHL 100 Dog ACSR 1.763 0.320 0.350 16.700 0.269 Al Hamryah-F1-P035 - Al Hamryah-33A-P035 33 33kV UGC 300 3C Cu 0.558 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB02 - 33 33kV OHL 100 Dog ACSR 1.720 0.320 0.350 16.700 0.269 Al Hamryah-F2-P035 - Al Hamryah-33B-P035 33 33kV UGC 300 3C Cu 0.603 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB01 Wattaya-33A-P131 Wattaya-F1-P131 33 33kV UGC 300 3C Cu 1.974 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB02 Wattaya-33B-P131 Wattaya-F2-P131 33 33kV UGC 300 3C Cu 2.001 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB01 - 33 33kV OHL 100 Dog ACSR 5.220 0.320 0.350 16.700 0.269 Amerat 1-F1-P005 - Amerat 1-33A-P005 33 33kV UGC 300 3C Cu 3.127 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB02 - 33 33kV OHL 100 Dog ACSR 5.178 0.320 0.350 16.700 0.269 Amerat 1-F2-P005 - Amerat 1-33B-P005 33 33kV UGC 300 3C Cu 3.140 0.062 0.103 260.000 0.385 N4655 Al Mahaj-33-P136 Al Mahaj-33-P136 33 33kV UGC 300 3C Cu 3.799 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB01 - 33 33kV OHL 200 Panther ACSR 10.086 0.137 0.333 10.900 0.385 Al Bustan Palace-F1-P017 - Al Bustan Palace-33A-P017 33 33kV UGC 300 3C Cu 2.421 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB02 - 33 33kV OHL 200 Panther ACSR 10.113 0.137 0.333 10.900 0.385 Al Bustan Palace-F2-P017 - Al Bustan Palace-33B-P017 33 33kV UGC 300 3C Cu 2.320 0.062 0.103 260.000 0.385 Wadi Adai Grid H BB01 - Al Bustan Palace-F1-P017 33 33kV OHL 200 Panther ACSR 10.086 0.137 0.333 10.900 0.385 - Qantab-33-P089-OD Qantab-F1-P089-OD 33 33kV OHL 200 Panther ACSR 2.293 0.137 0.333 10.900 0.385

Jahloot[G03] GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] 33kV Jahloot BB-HBB01 - Mazara Fdr - Jahloot1-P040 + Siya-P120 33 33kV OHL 200 Panther ACSR 4.947 0.137 0.333 10.900 0.385 - Jahloot-33A-P040 + Arqi-P121 33 33kV UGC 300 3C Cu 0.020 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB01 - Mazara Fdr - Jahloot1-P040 + Siya-P120 33 33kV OHL 200 Panther ACSR 4.947 0.137 0.333 10.900 0.385 - Jahloot-33B-P040 + Arqi-P121 33 33kV UGC 300 3C Cu 0.020 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB01 - 33 33kV OHL 200 Panther ACSR 4.947 0.137 0.333 10.900 0.385 Mazara Fdr - Jahloot1-P040 + Siya-P120 - - 33 33kV OHL 200 Panther ACSR 11.409 0.137 0.333 10.900 0.385 + Arqi-P121 - Siya-33A-P120 33 33kV UGC 300 3C Cu 1.532 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB01 - 33 33kV OHL 200 Panther ACSR 26.758 0.137 0.333 10.900 0.385 - - Bar Al Jissah 1-F1-P044 33 33kV OHL 200 Panther ACSR 2.667 0.137 0.333 10.900 0.385 - Bar Al Jissah-33A-P044 33 33kV OHL 200 Panther ACSR 3.700 0.137 0.333 10.900 0.385 33kV Jahloot BB-HBB02 - 33 33kV OHL 200 Panther ACSR 26.764 0.137 0.333 10.900 0.385 - - Bar Al Jissah 1-F2-P044 33 33kV OHL 200 Panther ACSR 2.661 0.137 0.333 10.900 0.385 - Bar Al Jissah-33B-P044 33 33kV OHL 200 Panther ACSR 3.700 0.137 0.333 10.900 0.385 33kV Jahloot BB-HBB01 - 33 33kV OHL 200 Panther ACSR 26.758 0.137 0.333 10.900 0.385 Bar Al Jissah 1-F1-P044 - Hussan Yitti-33A-P169-OD 33 33kV UGC 300 3C Cu 1.696 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB02 - 33 33kV OHL 200 Panther ACSR 26.764 0.137 0.333 10.900 0.385 Bar Al Jissah 1-F2-P044 - Hussan Yitti-33B-P169-OD 33 33kV UGC 300 3C Cu 1.620 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB02 - 33 33kV OHL 200 Panther ACSR 11.515 0.137 0.333 10.900 0.385 - - 33 33kV UGC 300 3C Cu 1.404 0.062 0.103 260.000 0.385 Al Hajir-F1-P031(P031+P137) - - 33 33kV OHL 200 Panther ACSR 4.088 0.137 0.333 10.900 0.385 - Al Hajir-33A-P031 33 33kV UGC 300 3C Cu 0.000 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB02 - 33 33kV OHL 200 Panther ACSR 14.517 0.137 0.333 10.900 0.385 - - Al Hajir-F2-P031(P031+P182) 33 33kV UGC 300 3C Cu 2.063 0.062 0.103 260.000 0.385 - Al Hajir-33B-P031 33 33kV OHL 200 Panther ACSR 0.010 0.137 0.333 10.900 0.385 33kV Jahloot BB-HBB02 - 33 33kV OHL 200 Panther ACSR 14.517 0.137 0.333 10.900 0.385 - - 33 33kV UGC 300 3C Cu 2.063 0.062 0.103 260.000 0.385 Al Hajir-F2-P031(P031+P182) - - 33 33kV OHL 200 Panther ACSR 2.872 0.137 0.333 10.900 0.385 - Al Atkiya-33N-P182-OD 33 33kV UGC 300 3C Cu 0.224 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB02 - 33 33kV OHL 200 Panther ACSR 11.515 0.137 0.333 10.900 0.385 Al Hajir-F1-P031(P031+P137) - Tunis-33 -P137 33 33kV UGC 300 3C Cu 1.404 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB01 - 33 33kV OHL 200 Panther ACSR 8.000 0.137 0.333 10.900 0.385 - - Sawaqim 1-F1-P112 (Quriyat fdr1) 33 33kV OHL 200 Panther ACSR 15.516 0.137 0.333 10.900 0.385 - Sawaqim 1-33B-P112-OD 33 33kV OHL 200 Panther ACSR 0.086 0.137 0.333 10.900 0.385 33kV Jahloot BB-HBB01 - 33 33kV OHL 200 Panther ACSR 8.000 0.137 0.333 10.900 0.385 Sawaqim 1-F1-P112 (Quriyat fdr1) - ROP Al Saleel-33A-P162-OD 33 33kV UGC 300 3C Cu 1.762 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB02 - 33 33kV OHL 200 Panther ACSR 25.397 0.137 0.333 10.900 0.385 Sawaqim 2-F1-P113-OD (Quriyat 2 fdr) - Sawaqim 2-33-P113-OD 33 33kV UGC 300 3C Cu 3.530 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB02 - Shehabari Feeder (Feeding ROP Saleel Tx 33 33kV OHL 200 Panther ACSR 8.000 0.137 0.333 10.900 0.385 - ROP Al Saleel-33B-P162-OD 2+Waterpump) 33 33kV UGC 300 3C Cu 1.740 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB02 - Shehabari Feeder (Feeding ROP Saleel Tx 33 33kV OHL 200 Panther ACSR 8.000 0.137 0.333 10.900 0.385 - Water Pumping-33B-P193-OD 2+Waterpump) 33 33kV OHL 200 Panther ACSR 30.000 0.137 0.333 10.900 0.385 33kV Jahloot BB-HBB02 - 33 33kV OHL 200 Panther ACSR 23.101 0.137 0.333 10.900 0.385 Wadi Mayh-F-P129-OD(Al Nahdha Fdr 1) - Debha-33N-P114-OD 33 33kV OHL 200 Panther ACSR 35.573 0.137 0.333 10.900 0.385 33kV Jahloot BB-HBB01 - 33 33kV OHL 200 Panther ACSR 21.000 0.137 0.333 10.900 0.385 Madinat Al Nahdah-F2-P065 - Madinat Al Nahdah-33B-P065 33 33kV UGC 300 3C Cu 3.700 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB01 Al Masarat-33A-P068 Al Masarat-F1-P068 33 33kV UGC 300 3C Cu 1.575 0.062 0.103 260.000 0.385 33kV Jahloot BB-HBB02 Al Masarat-33B-P068 Al Masarat-F2-P068 33 33kV UGC 300 3C Cu 1.525 0.062 0.103 260.000 0.385 - Mazara Feeder (Jahloot GSS)– This feeder feeds Jahloot P040, Siya P120 & Arqi P121 primary substations - Al Hajir-F1-P031(P031+P137) (Jahloot GSS) – This feeder feeds Al Hajir-P031 Transformer 1 and Tunis-P137 primary substations - Al Hajir-F2-P031(P031+P182) (Jahloot GSS) – This feeder feeds Al Hajir-P031 (Transformer 2) and Al Atkiya P182 primary substations - Sawaqim 1-F1-P112 (Quriyat fdr1) (Jahloot GSS) – This feeder feeds Sawaqim 1-P112 (Transformer 1) and ROP Al Saleel-P162 (Transformer 1) primary substations - Sawaqim 2-F1-P113 (Quriyat fdr2) (Jahloot GSS) – This feeder feeds Sawaqim 1-P112 (Transformer 2) and Sawaqim 2-P113 primary substations - Shehabari Feeder (Feeding ROP Saleel Tx 2+Waterpump) (Jahloot GSS) – This feeder feeds ROP Al Saleel-P162 Transformer 2 and Water Pumping-P193 primary substations

MEDC Distribution System Capability Statement [2021-2023]-V2.0 123 Yiti[G08] GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Yitty Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 1.465 0.137 0.333 10.900 0.385 - - 33 33kV UGC 300 3C Cu 0.186 0.062 0.103 260.000 0.385 Yitti Feeder-P134OD,Salam YitiP135OD - - 33 33kV OHL 200 Panther ACSR 3.568 0.137 0.333 10.900 0.385 - Al Salam Yiti-33-P135 33 33kV UGC 300 3C Cu 0.241 0.062 0.103 260.000 0.385 Yitty Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 1.465 0.137 0.333 10.900 0.385 - - Yitti Feeder-P134OD,Salam YitiP135OD 33 33kV UGC 300 3C Cu 0.186 0.062 0.103 260.000 0.385 - Yiti-33A-P134 33 33kV UGC 300 3C Cu 0.352 0.062 0.103 260.000 0.385 Yitty Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 3.470 0.137 0.333 10.900 0.385 Khayran for P133 & P045 - Yenket-33A -P133 33 33kV UGC 300 3C Cu 0.247 0.062 0.103 260.000 0.385 Yitty Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 3.470 0.137 0.333 10.900 0.385 - - Khayran for P133 & P045 33 33kV UGC 300 3C Cu 0.247 0.062 0.103 260.000 0.385 - Al Khairan-33A-P045 33 33kV OHL 200 Panther ACSR 3.557 0.137 0.333 10.900 0.385 Yitty Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 20.237 0.137 0.333 10.900 0.385 Jabal Al Sifah-F1-P159 - Jabal Al Sifah-33A-P159 33 33kV UGC 300 3C Cu 0.925 0.062 0.103 260.000 0.385 Yitty Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 20.237 0.137 0.333 10.900 0.385 Jabal Al Sifah-F2-P159 - Jabal Al Sifah-33B-P159 33 33kV UGC 300 3C Cu 1.001 0.062 0.103 260.000 0.385 Yitty Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 20.243 0.137 0.333 10.900 0.385 Jabal Al Sifah-F3-P159 - Jabal Al Sifah-33C-P159 33 33kV UGC 300 3C Cu 0.894 0.062 0.103 260.000 0.385 Yitty Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 10.548 0.137 0.333 10.900 0.385 Saraya Bander-F1-P145 - Saraya Bander-33A-P145 33 33kV UGC 300 3C Cu 1.625 0.062 0.103 260.000 0.385 Yitty Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 10.546 0.137 0.333 10.900 0.385 Saraya Bander-F2-P145 - Saraya Bander-33B-P145 33 33kV UGC 300 3C Cu 1.544 0.062 0.103 260.000 0.385 Yitty Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 10.554 0.137 0.333 10.900 0.385 Saraya Bander-F3-P145 - Saraya Bander-33C-P145 33 33kV UGC 300 3C Cu 1.605 0.062 0.103 260.000 0.385

Quriyat[G05] GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] 33kV Quriyat BB-HBB02 Quriyat-33A-P091 Quriyat-F2-P091 33 33kV UGC 300 3C Cu 8.034 0.062 0.103 260.000 0.385 33kV Quriyat BB-HBB01 Quriyat-33B-P091 Quriyat-F1-P091 33 33kV UGC 300 3C Cu 7.965 0.062 0.103 260.000 0.385 33kV Quriyat BB-HBB01 Al Shahbari-33A-P092 Al Shahbari-F1-P092 33 33kV UGC 300 3C Cu 7.868 0.062 0.103 260.000 0.385 33kV Quriyat BB-HBB02 Al Shahbari-33B-P092 Al Shahbari-F2-P092 33 33kV UGC 300 3C Cu 7.949 0.062 0.103 260.000 0.385 33kV Quriyat BB-HBB01 - Al Shahbari-F1-P092 33 33kV UGC 300 3C Cu 7.868 0.062 0.103 260.000 0.385 - - 33 33kV OHL 200 Panther ACSR 5.078 0.137 0.333 10.900 0.385 Jahloot Feeder-to Hail Ghaf and Mazara - Hail Al Ghaf-33 -P036 33 33kV UGC 300 3C Cu 1.047 0.062 0.103 260.000 0.385 33kV Quriyat BB-HBB01 - Al Shahbari-F1-P092 33 33kV UGC 300 3C Cu 7.868 0.062 0.103 260.000 0.385 - - 33 33kV OHL 200 Panther ACSR 5.078 0.137 0.333 10.900 0.385 - - Jahloot Feeder-to Hail Ghaf and Mazara 33 33kV UGC 300 3C Cu 1.047 0.062 0.103 260.000 0.385 - Al Mazara-33 -P074 33 33kV OHL 200 Panther ACSR 15.058 0.137 0.333 10.900 0.385 33kV Quriyat BB-HBB02 - 33 33kV UGC 300 3C Cu 1.900 0.062 0.103 260.000 0.385 Quriyat-F1-P091 - Dhagmar 1-33A-P021 33 33kV OHL 200 Panther ACSR 0.002 0.137 0.333 10.900 0.385 33kV Quriyat BB-HBB02 - 33 33kV UGC 300 3C Cu 2.395 0.062 0.103 260.000 0.385 Dhagmar 1-F1-P021 - Street Light-33-P020 33 33kV UGC 300 3C Cu 4.665 0.062 0.103 260.000 0.385 33kV Quriyat BB-HBB02 - 33 33kV UGC 300 3C Cu 2.395 0.062 0.103 260.000 0.385 - - 33 33kV UGC 300 3C Cu 4.665 0.062 0.103 260.000 0.385 Dhagmar 1-F1-P021 - - 33 33kV OHL 200 Panther ACSR 4.966 0.137 0.333 10.900 0.385 - Wadi Al Arbyeen-33-P124 33 33kV UGC 300 3C Cu 4.836 0.062 0.103 260.000 0.385 33kV Quriyat BB-HBB02 - 33 33kV UGC 300 3C Cu 2.395 0.062 0.103 260.000 0.385 - - 33 33kV UGC 300 3C Cu 4.665 0.062 0.103 260.000 0.385 - - Dhagmar 1-F1-P021 33 33kV OHL 200 Panther ACSR 4.966 0.137 0.333 10.900 0.385 - - 33 33kV OHL 200 Panther ACSR 2.100 0.137 0.333 10.900 0.385 - RoyalCamp-33-P170 33 33kV UGC 300 3C Cu 0.138 0.062 0.103 260.000 0.385 33kV Quriyat BB-HBB02 - 33 33kV UGC 300 3C Cu 2.395 0.062 0.103 260.000 0.385 - - 33 33kV UGC 300 3C Cu 4.665 0.062 0.103 260.000 0.385 - - 33 33kV OHL 200 Panther ACSR 4.966 0.137 0.333 10.900 0.385 - - 33 33kV OHL 200 Panther ACSR 2.100 0.137 0.333 10.900 0.385 - - Dhagmar 1-F1-P021 33 33kV OHL 200 Panther ACSR 11.404 0.137 0.333 10.900 0.385 - - 33 33kV UGC 300 3C Cu 0.377 0.062 0.103 260.000 0.385 - - 33 33kV OHL 200 Panther ACSR 5.983 0.137 0.333 10.900 0.385 - - 33 33kV OHL 200 Panther ACSR 5.983 0.137 0.333 10.900 0.385 - Dhabab-33-P019 33 33kV OHL 200 Panther ACSR 5.983 0.137 0.333 10.900 0.385 - Quriyat-F1-P091 – This feeder feeds Dhagmar 1-P021 and Quriyat P091 primary substations - Yiti Feeder-P134OD, Salam YitiP135OD (Yiti GSS) – This feeder feeds Yiti 1-P134 and Al Salam Yiti-P135 primary substations - Khayran for P133 & P045 (Yiti GSS) – This feeder feeds Al Khairan-P045 and Yenkit 1-P133 primary substations - Al Shahbari-F1-P092 (Quriyat GSS)– This feeder feeds Al Shahbari-P092 (Tx 1) and additionally the Hayl Ghaf 1-P036 and Al Mazara 1-P074 primary substations by interconnecting with Jahloot Feeder - Dhagmar 1-F1 (Quriyat GSS) – This feeder feeds Street Light-P020, Wadi Al Arbyeen-P124, RoyalCamp-P170 and Dhabab-P019 primary substations

MEDC Distribution System Capability Statement [2021-2023]-V2.0 124 Amerat[G10] - A GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Amerat A Grid H-BB01 Amerat 3-33A-P179 Amerat 3-F1-P179 33 33kV UGC 300 3C Cu 4.964 0.062 0.103 260.000 0.385 Amerat A Grid H-BB02 Amerat 3-33B-P179 Amerat 3-F2-P179 33 33kV UGC 300 3C Cu 4.965 0.062 0.103 260.000 0.385 Amerat A Grid H-BB02 Amerat 3-33C-P179 Amerat 3-F3-P179 33 33kV UGC 300 3C Cu 4.968 0.062 0.103 260.000 0.385 Amerat A Grid H-BB01 Amerat Heights-33A-P152 Amerat Heights-F1-P152 33 33kV UGC 300 3C Cu XLPE 6.064 0.062 0.103 260.000 0.386 Amerat A Grid H-BB02 Amerat Heights-33B-P152 Amerat Heights-F2-P152 33 33kV UGC 300 3C Cu XLPE 6.079 0.062 0.103 260.000 0.386 Amerat A Grid H-BB02 Amerat Heights-33C-P152 Amerat Heights-F3-P152 33 33kV UGC 300 3C Cu XLPE 6.173 0.062 0.103 260.000 0.386 Amerat A Grid H-BB01 Post Office-33A-P150 Post Office-F1-P150 33 33kV UGC 300 3C Cu XLPE 2.756 0.062 0.103 260.000 0.386 Amerat A Grid H-BB02 Post Office-33B-P150 Post Office-F2-P150 33 33kV UGC 300 3C Cu XLPE 2.770 0.062 0.103 260.000 0.386 Amerat A Grid H-BB02 Post Office-33C-P150 Post Office-F3-P150 33 33kV UGC 300 3C Cu XLPE 2.612 0.062 0.103 260.000 0.386

Amerat[G10] - B GSS [Zone 1] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Amerat A Grid H-BB01 - 33 33kV UGC 300 3C Cu 0.929 0.062 0.103 260.000 0.385 - - 33 33kV UGC 300 3C Cu 1.066 0.062 0.103 260.000 0.385 Al Nahdah-F1-P006 - - 33 33kV OHL 200 Panther ACSR 3.259 0.137 0.333 10.900 0.385 - Al Nahdah-33A-P006 33 33kV UGC 300 3C Cu 0.433 0.062 0.103 260.000 0.385 Amerat A Grid H-BB02 - 33 33kV UGC 300 3C Cu 0.929 0.062 0.103 260.000 0.385 - - 33 33kV UGC 300 3C Cu 1.043 0.062 0.103 260.000 0.385 Al Nahdah-F2-P006 - - 33 33kV OHL 200 Panther ACSR 3.292 0.137 0.333 10.900 0.385 - Al Nahdah-33B-P006 33 33kV UGC 300 3C Cu 0.412 0.062 0.103 260.000 0.385 Amerat A Grid H-BB02 Al Nahdah-33C-P006 Al Nahdah-F3-P006 33 33kV UGC 300 3C Cu XLPE 3.628 0.062 0.103 260.000 0.386 Amerat A Grid H-BB03 Seih Dhabi-33A-P118 Seih Dhabi-F1-P118 33 33kV UGC 300 3C Cu 0.507 0.062 0.103 260.000 0.385 Amerat A Grid H-BB04 Seih Dhabi-33B-P118 Seih Dhabi-F2-P118 33 33kV UGC 300 3C Cu 0.501 0.062 0.103 260.000 0.385 Amerat B Grid H-BB03 - 33 33kV OHL 200 Panther ACSR 4.926 0.137 0.333 10.900 0.385 - - Madinat Al Nahdah-F1-P065 33 33kV OHL 200 Panther ACSR 1.416 0.137 0.333 10.900 0.385 - Madinat Al Nahdah-33A-P065 33 33kV UGC 300 3C Cu 0.663 0.062 0.103 260.000 0.385 Amerat B Grid H-BB03 - 33 33kV OHL 200 Panther ACSR 4.926 0.137 0.333 10.900 0.385 Madinat Al Nahdah-F1-P065 - Al Jufaina-33-P194 33 33kV OHL 200 Panther ACSR 0.010 0.137 0.333 10.900 0.385

Ghubrah 2[G09] GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Ghubrah Grid H-BB01 Azaiba North 2-33A-P012 Azaiba North 2-F1-P012 33 33kV UGC 300 3C Cu 4.286 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB02 Azaiba North 2-33B-P012 Azaiba North 2-F2-P012 33 33kV UGC 300 3C Cu 4.301 0.062 0.103 260.000 0.385

Ghubrah Grid H-BB01 - 33 33kV OHL 150 Wolf ACSR 2.732 0.186 0.337 10.800 0.350

Azaiba South 1A-F1-P014 - Azaiba South 1A-33A-P014 33 33kV UGC 300 3C Cu 5.712 0.062 0.103 260.000 0.385

Ghubrah Grid H-BB02 - 33 33kV OHL 150 Wolf ACSR 3.257 0.186 0.337 10.800 0.350 Azaiba South 1A-F2-P014 - Azaiba South 1A-33B-P014 33 33kV UGC 300 3C Cu 5.284 0.062 0.103 260.000 0.385

Ghubrah Grid H-BB02 Diplomatic City 1-33A-P022 Diplomatic City 1-F1-P022 33 33kV UGC 300 3C Cu 2.424 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB02 Diplomatic City 1-33B-P022 Diplomatic City 1-F2-P022 33 33kV UGC 300 3C Cu 2.427 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB01 Diplomatic City 1-33C-P022 Diplomatic City 1-F3-P022 33 33kV UGC 300 3C Cu 1.688 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB01 Ghubra North 1-33A-P023 Ghubra North 1-F1-P023 33 33kV UGC 300 3C Cu 1.295 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB02 Ghubra North 1-33B-P023 Ghubra North 1-F2-P023 33 33kV UGC 300 3C Cu 1.303 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB01 Ghubra North 1-33C-P023 Ghubra North 1-F3-P023 33 33kV UGC 300 3C Cu 1.316 0.062 0.103 260.000 0.385

Ghubrah Grid H-BB01 Ghubrah GPS-33A-P166-Pvt Ghubrah GPS-F1-P166-Pvt 33 33kV UGC 300 3C Cu 1.065 0.062 0.103 260.000 0.385

Ghubrah Grid H-BB02 Ghubrah GPS-33B-P166-Pvt Ghubrah GPS-F2-P166-Pvt 33 33kV UGC 300 3C Cu 1.065 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB01 Ghubrah North 02-33A-P149 Ghubrah North 02-F1-P149 33 33kV UGC 300 3C Cu 3.740 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB02 Ghubrah North 02-33B-P149 Ghubrah North 02-F2-P149 33 33kV UGC 300 3C Cu 3.751 0.062 0.103 260.000 0.385 Ghubrah Grid H-BB01 Ghubrah North 02-33C-P149 Ghubrah North 02-F3-P149 33 33kV UGC 300 3C Cu 3.756 0.062 0.103 260.000 0.385

MSQ[GP06] - A GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] MSQ Grid H-BB01 Al Khuwair North-33A-P054 Al Khuwair North-F1-P054 33 33kV UGC 300 3C Cu 1.791 0.062 0.103 260.000 0.385 MSQ Grid H-BB02 Al Khuwair North-33B-P054 Al Khuwair North-F2-P054 33 33kV UGC 300 3C Cu 1.791 0.062 0.103 260.000 0.385 MSQ Grid H-BB02 Al Khuwair North-33C-P054 Al Khuwair North-F3-P054 33 33kV UGC 300 3C Cu 1.879 0.062 0.103 260.000 0.385 MSQ Grid H-BB01 - 33 33kV UGC 300 3C Cu 3.237 0.062 0.103 260.000 0.385 - - Intercontinental-F1-P109 33 33kV OHL 200 Panther ACSR 1.229 0.137 0.333 10.900 0.385 - Intercontinental-33A-P109 33 33kV UGC 300 3C Cu 1.774 0.062 0.103 260.000 0.385 MSQ Grid H-BB02 Intercontinental-33B-P109 Intercontinental-F2-P109 33 33kV UGC 300 3C Cu 4.884 0.062 0.103 260.000 0.385 MSQ Grid H-BB01 Royal Office-33A-P097 Royal Office-F1-P097 33 33kV UGC 300 3C Cu 5.361 0.062 0.103 260.000 0.385 MSQ Grid H-BB02 Royal Office-33B-P097 Royal Office-F2-P097 33 33kV UGC 300 3C Cu 5.356 0.062 0.103 260.000 0.385 MSQ Grid H-BB01 Sarooj -Shati Al Qurum-33B-P110 Sarooj -Shati Al Qurum-F1-P110 33 33kV UGC 300 3C Cu 4.297 0.062 0.103 260.000 0.385

MSQ Grid H-BB02 Sarooj -Shati Al Qurum-33A-P110 Sarooj -Shati Al Qurum-F2-P110 33 33kV UGC 300 3C Cu 4.257 0.062 0.103 260.000 0.385 MSQ Grid H-BB01 - 33 33kV UGC 300 3C Cu 3.237 0.062 0.103 260.000 0.385 Intercontinental-F1-P109 - Information City 2-33-P038 33 33kV OHL 200 Panther ACSR 1.229 0.137 0.333 10.900 0.385 MSQ Grid H-BB01 MSQ Grid-33A-GP06 MSQ Grid-F1-GP06 33 33kV UGC 300 3C Cu 0.030 0.062 0.103 260.000 0.385 MSQ Grid H-BB02 MSQ Grid-33B-GP06 MSQ Grid-F2-GP06 33 33kV UGC 300 3C Cu 0.029 0.062 0.103 260.000 0.385

MEDC Distribution System Capability Statement [2021-2023]-V2.0 125 MSQ[GP06] - B GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] MSQ Grid H-BB03 - 33 33kV OHL 200 Panther ACSR 0.883 0.137 0.333 10.900 0.385 Al Khuwair 25-F1-P053 - Al Khuwair 25-33A-P053 33 33kV UGC 300 3C Cu 2.123 0.062 0.103 260.000 0.385 MSQ Grid H-BB04 - 33 33kV OHL 200 Panther ACSR 0.848 0.137 0.333 10.900 0.385 Al Khuwair 25-F2-P053 - Al Khuwair 25-33B-P053 33 33kV UGC 300 3C Cu 2.126 0.062 0.103 260.000 0.385 MSQ Grid H-BB03 Al Khuwair School-33A-P146 Al Khuwair School-F1-P146 33 33kV UGC 300 3C Cu 2.883 0.062 0.103 260.000 0.385 MSQ Grid H-BB03 Al Khuwair School-33B-P146 Al Khuwair School-F2-P146 33 33kV UGC 300 3C Cu 2.878 0.062 0.103 260.000 0.385 MSQ Grid H-BB04 Al Khuwair School-33C-P146 Al Khuwair School-F3-P146 33 33kV UGC 300 3C Cu 2.875 0.062 0.103 260.000 0.385 MSQ Grid H-BB03 Digital TV Studio-33A-P039 Digital TV Studio-F1-P039 33 33kV UGC 300 3C Cu 3.622 0.062 0.103 260.000 0.385 MSQ Grid H-BB04 Digital TV Studio-33B-P039 Digital TV Studio-F2-P039 33 33kV UGC 300 3C Cu 3.627 0.062 0.103 260.000 0.385 MSQ Grid H-BB03 MSQ 1-33A-P083 MSQ 1-F1-P083 33 33kV UGC 300 3C Cu 1.632 0.062 0.103 260.000 0.385 MSQ Grid H-BB04 MSQ 1-33B-P083 MSQ 1-F2-P083 33 33kV UGC 300 3C Cu 1.614 0.062 0.103 260.000 0.385 MSQ Grid H-BB03 ROP -Shati Al Qurum-33A-P111 ROP -Shati Al Qurum-F1-P111 33 33kV UGC 300 3C Cu 3.290 0.062 0.103 260.000 0.385

MSQ Grid H-BB04 ROP -Shati Al Qurum-33B-P111 ROP -Shati Al Qurum-F2-P111 33 33kV UGC 300 3C Cu 3.302 0.062 0.103 260.000 0.385

Qurum[G06] GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Qurum Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.997 0.137 0.333 10.900 0.385 - - Information City 1-F1-P037 33 33kV UGC 300 3C Cu 1.553 0.062 0.103 260.000 0.385 - Information City 1-33A-P037 33 33kV UGC 300 3C Cu 0.952 0.062 0.103 260.000 0.385 Qurum Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 0.116 0.137 0.333 10.900 0.385 Information City 1-F2-P037 - Information City 1-33B-P037 33 33kV UGC 300 3C Cu 2.990 0.062 0.103 260.000 0.385 Qurum Grid H-BB01 - 33 33kV UGC 300 3C Cu 1.328 0.062 0.103 260.000 0.385 Lulai-F1-P095 - Lulai-33A-P095 33 33kV UGC 300 3C Cu 0.476 0.062 0.103 260.000 0.385 Qurum Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.475 0.137 0.333 10.900 0.385 Lulai-F2-P095 - Lulai-33B-P095 33 33kV UGC 300 3C Cu 1.276 0.062 0.103 260.000 0.385 Qurum Grid H-BB01 MSQ 02-33A-P155 MSQ 02-F1-P155 33 33kV UGC 300 3C Cu 4.034 0.062 0.103 260.000 0.385 Qurum Grid H-BB02 MSQ 02-33B-P155 MSQ 02-F2-P155 33 33kV UGC 300 3C Cu 4.062 0.062 0.103 260.000 0.385 Qurum Grid H-BB01 MSQ 02-33C-P155 MSQ 02-F3-P155 33 33kV UGC 300 3C Cu 3.951 0.062 0.103 260.000 0.385 Qurum Grid H-BB01 - 33 33kV UGC 300 3C Cu 5.990 0.062 0.103 260.000 0.385 Qurum 1-F1-P093 - Qurum 1-33A-P093 33 33kV OHL 200 Panther ACSR 0.469 0.137 0.333 10.900 0.385 Qurum Grid H-BB02 Qurum 1-33B-P093 Qurum 1-F2-P093 33 33kV UGC 300 3C Cu 6.051 0.062 0.103 260.000 0.385 Qurum Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.480 0.137 0.333 10.900 0.385 Qurum 2-F1-P094 - Qurum 2-33A-P094 33 33kV UGC 300 3C Cu 3.770 0.062 0.103 260.000 0.385 Qurum Grid H-BB02 Qurum 2-33B-P094 Qurum 2-F2-P094 33 33kV UGC 300 3C Cu 3.977 0.062 0.103 260.000 0.385 Qurum Grid H-BB01 Rabiat Al Qurum-33A-P096 Rabiat Al Qurum-F1-P096 33 33kV UGC 300 3C Cu 1.070 0.062 0.103 260.000 0.385 Qurum Grid H-BB02 Rabiat Al Qurum-33B-P096 Rabiat Al Qurum-F2-P096 33 33kV UGC 300 3C Cu 1.087 0.062 0.103 260.000 0.385

Bousher[GP02] - A GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Bousher Grid H-BB01 Al Khuwair 17/1-33A-P050 Al Khuwair 17/1-F1-P050 33 33kV UGC 300 3C Cu 2.979 0.062 0.103 260.000 0.385 Bousher Grid H-BB02 Al Khuwair 17/1-33B-P050 Al Khuwair 17/1-F2-P050 33 33kV UGC 300 3C Cu 2.991 0.062 0.103 260.000 0.385 Bousher Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.089 0.137 0.333 10.900 0.385 Al Khuwair South-F1-P052 - Al Khuwair South-33A-P052 33 33kV UGC 300 3C Cu 1.130 0.062 0.103 260.000 0.385 Bousher Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 0.090 0.137 0.333 10.900 0.385 Al Khuwair South-F2-P052 - Al Khuwair South-33B-P052 33 33kV UGC 300 3C Cu 1.142 0.062 0.103 260.000 0.385 Bousher Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.089 0.137 0.333 10.900 0.385 Al Khuwair South-F3-P052 - Al Khuwair South-33C-P052 33 33kV UGC 300 3C Cu 1.088 0.062 0.103 260.000 0.385 Bousher Grid H-BB01 Bousher G-33A-GP02 Bousher G-F1-GP02 33 33kV UGC 300 3C Cu 0.030 0.062 0.103 260.000 0.385 Bousher Grid H-BB02 Bousher G-33B-GP02 Bousher G-F2-GP02 33 33kV UGC 300 3C Cu 0.029 0.062 0.103 260.000 0.385 Bousher Grid H-BB01 Royal Hospital-33A-P024 Royal Hospital-F1-P024 33 33kV UGC 300 3C Cu 3.940 0.062 0.103 260.000 0.385 Bousher Grid H-BB02 Royal Hospital-33B-P024 Royal Hospital-F2-P024 33 33kV UGC 300 3C Cu 3.939 0.062 0.103 260.000 0.385 Bousher Grid H-BB02 Royal Hospital-33C-P024 Royal Hospital-F3-P024 33 33kV UGC 300 3C Cu 3.933 0.062 0.103 260.000 0.385 Bousher Grid H-BB01 Azaiba South 1B-33A-P147 Azaiba South 1B-F3-P147 33 33kV UGC 300 3C Cu 6.079 0.062 0.103 260.000 0.385 Bousher Grid H-BB02 Azaiba South 1B-33B-P147 Azaiba South 1B-F4-P147 33 33kV UGC 300 3C Cu 6.087 0.062 0.103 260.000 0.385 Bousher Grid H-BB01 Azaiba South 1B-33C-P147 Azaiba South 1B-F5-P147 33 33kV UGC 300 3C Cu 6.088 0.062 0.103 260.000 0.385

MEDC Distribution System Capability Statement [2021-2023]-V2.0 126 Bousher[GP02] - B GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Bousher Grid H-BB03 Al Ansab 1-33A-P007 Al Ansab 1-F1-P007 33 33kV UGC 300 3C Cu 8.252 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Al Ansab 1-33B-P007 Al Ansab 1-F2-P007 33 33kV UGC 300 3C Cu 8.285 0.062 0.103 260.000 0.385 Bousher Grid H-BB03 Al Muna 1-33A-P084 Al Muna 1-F1-P084 33 33kV UGC 300 3C Cu 4.691 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Al Muna 1-33B-P084 Al Muna 1-F2-P084 33 33kV UGC 300 3C Cu 4.676 0.062 0.103 260.000 0.385 Bousher Grid H-BB03 Azaiba North 1-33A-P011 Azaiba North 1-F1-P011 33 33kV UGC 300 3C Cu 5.511 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Azaiba North 1-33B-P011 Azaiba North 1-F2-P011 33 33kV UGC 300 3C Cu 5.505 0.062 0.103 260.000 0.385 Bousher Grid H-BB03 Bousher 02-33A-P163 Bousher 02-F1-P163 33 33kV UGC 300 3C Cu 0.987 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Bousher 02-33B-P163 Bousher 02-F2-P163 33 33kV UGC 300 3C Cu 0.999 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Bousher 02-33C-P163 Bousher 02-F3-P163 33 33kV UGC 300 3C Cu 1.003 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Ghubrah South 1-33A-P026 Ghubrah South 1-F1-P026 33 33kV UGC 300 3C Cu 3.374 0.062 0.103 260.000 0.385 Bousher Grid H-BB03 Ghubrah South 1-33B-P026 Ghubrah South 1-F2-P026 33 33kV UGC 300 3C Cu 3.341 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Ghubrah South 1-33C-P026 Ghubrah South 1-F3-P026 33 33kV UGC 300 3C Cu 3.399 0.062 0.103 260.000 0.385 Bousher Grid H-BB03 Holiday Inn-33A-P051 Holiday Inn-F1-P051 33 33kV UGC 300 3C Cu 1.686 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Holiday Inn-33B-P051 Holiday Inn-F2-P051 33 33kV UGC 300 3C Cu 1.774 0.062 0.103 260.000 0.385 Bousher Grid H-BB03 Holiday Inn-33C-P051 Holiday Inn-F3-P051 33 33kV UGC 300 3C Cu 1.681 0.062 0.103 260.000 0.385 Bousher Grid H-BB03 Tilal Al Khuwair-33A-P055 Tilal Al Khuwair-F1-P055 33 33kV UGC 300 3C Cu 1.346 0.062 0.103 260.000 0.385 Bousher Grid H-BB04 Tilal Al Khuwair-33B-P055 Tilal Al Khuwair-F2-P055 33 33kV UGC 300 3C Cu 1.347 0.062 0.103 260.000 0.385 Bousher Grid H-BB03 Tilal Al Khuwair-33C-P055 Tilal Al Khuwair-F3-P055 33 33kV UGC 300 3C Cu 1.351 0.062 0.103 260.000 0.385

Ghala Heights[G24] GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Ghala Heights Grid H-BB03 Mall of Oman-33B-P171 Mall of Oman-F1-P171 33 33kV UGC 300 3C Cu 3.939 0.062 0.103 260.000 0.385 Ghala Heights Grid H-BB04 Mall of Oman-33C-P171 Mall of Oman-F2-P171 33 33kV UGC 300 3C Cu 3.938 0.062 0.103 260.000 0.385 Ghala Heights Grid H-BB03 Mall of Oman-33A-P171 Mall of Oman-F3-P171 33 33kV UGC 300 3C Cu 3.933 0.062 0.103 260.000 0.385

Ghala[G11] - A GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Ghala Grid H-BB01 Ansab 2-33A-P008 Ansab 2-F1-P008 33 33kV UGC 300 3C Cu 6.750 0.062 0.103 260.000 0.385 Ghala Grid H-BB02 Ansab 2-33B-P008 Ansab 2-F2-P008 33 33kV UGC 300 3C Cu 6.749 0.062 0.103 260.000 0.385 Ghala Grid H-BB01 Ansab STP-33A-P009 Ansab STP-F1-P009 33 33kV UGC 300 3C Cu 2.424 0.062 0.103 260.000 0.385 Ghala Grid H-BB02 Ansab STP-33B-P009 Ansab STP-F2-P009 33 33kV UGC 300 3C Cu 2.421 0.062 0.103 260.000 0.385 Ghala Grid H-BB01 Ghala 1-33A-P015 Ghala 1-F1-P015 33 33kV UGC 300 3C Cu XLPE 10.067 0.062 0.103 260.000 0.386 Ghala Grid H-BB02 Ghala 1-33B-P015 Ghala 1-F2-P015 33 33kV UGC 300 3C Cu XLPE 10.051 0.062 0.103 260.000 0.386 Ghala Grid H-BB02 Ghala 1-33C-P015 Ghala 1-F3-P015 33 33kV UGC 300 3C Cu XLPE 6.253 0.062 0.103 260.000 0.386 Ghala Grid H-BB01 Ghala 2-33A-P156 Ghala 2-F1-P156 33 33kV UGC 300 3C Cu 7.621 0.062 0.103 260.000 0.385 Ghala Grid H-BB02 Ghala 2-33B-P156 Ghala 2-F2-P156 33 33kV UGC 300 3C Cu 7.635 0.062 0.103 260.000 0.385 Ghala Grid H-BB01 Ghala 2-33C-P156 Ghala 2-F3-P156 33 33kV UGC 300 3C Cu 7.604 0.062 0.103 260.000 0.385 Ghala Grid H-BB01 MOD Al Ansab-33A-P167 MOD Al Ansab-F1-P167 33 33kV UGC 300 3C Cu 6.430 0.062 0.103 260.000 0.385 Ghala Grid H-BB02 MOD Al Ansab-33B-P167 MOD Al Ansab-F2-P167 33 33kV UGC 300 3C Cu 6.074 0.062 0.103 260.000 0.385 Ghala Grid H-BB01 Oman Exhibition-33C-P165 Oman Exhibition-F1-P165 33 33kV UGC 300 3C Cu 0.348 0.062 0.103 260.000 0.385 Ghala Grid H-BB01 Oman Exhibition-33A-P165 Oman Exhibition-F2-P165 33 33kV UGC 300 3C Cu 0.349 0.062 0.103 260.000 0.385 Ghala Grid H-BB02 Oman Exhibition-33B-P165 Oman Exhibition-F3-P165 33 33kV UGC 300 3C Cu 0.353 0.062 0.103 260.000 0.385

Airport Heights [G01] - A GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Airport Height Grid H-BB01 Airport Height 1-33A-P001 Airport Height 1-F1-P001 33 33kV UGC 300 3C Cu 3.997 0.062 0.103 260.000 0.385 Airport Height Grid H-BB02 Airport Height 1-33B-P001 Airport Height 1-F2-P001 33 33kV UGC 300 3C Cu 3.956 0.062 0.103 260.000 0.385 Airport Height Grid H-BB01 Airport Height 2-33A-P002 Airport Height 2-F1-P002 33 33kV UGC 300 3C Cu 3.465 0.062 0.103 260.000 0.385 Airport Height Grid H-BB02 Airport Height 2-33B-P002 Airport Height 2-F2-P002 33 33kV UGC 300 3C Cu 3.512 0.062 0.103 260.000 0.385 Airport Height Grid H-BB01 Airport Height 3-33A-P003 Airport Height 3-F1-P003 33 33kV UGC 300 3C Cu 4.589 0.062 0.103 260.000 0.385 Airport Height Grid H-BB02 Airport Height 3-33B-P003 Airport Height 3-F2-P003 33 33kV UGC 300 3C Cu 4.671 0.062 0.103 260.000 0.385 Airport Height Grid H-BB01 Airport Height 4-33A-P004 Airport Height 4-F1-P004 33 33kV UGC 300 3C Cu 2.426 0.062 0.103 260.000 0.385 Airport Height Grid H-BB02 Airport Height 4-33B-P004 Airport Height 4-F2-P004 33 33kV UGC 300 3C Cu 2.503 0.062 0.103 260.000 0.385 Airport Height Grid H-BB01 Airport Height 5-33A-P151 Airport Height 5-F1-P151 33 33kV UGC 300 3C Cu 5.493 0.062 0.103 260.000 0.385 Airport Height Grid H-BB02 Airport Height 5-33B-P151 Airport Height 5-F2-P151 33 33kV UGC 300 3C Cu 5.551 0.062 0.103 260.000 0.385 Airport Height Grid H-BB01 Azaiba North 3-33A-P013 Azaiba North 3-F1-P013 33 33kV UGC 300 3C Cu 9.130 0.062 0.103 260.000 0.385 Airport Height Grid H-BB02 Azaiba North 3-33B-P013 Azaiba North 3-F2-P013 33 33kV UGC 300 3C Cu 9.202 0.062 0.103 260.000 0.385 Airport Height Grid H-BB01 Azaiba North 3-33C-P013 Azaiba North 3-F3-P013 33 33kV UGC 300 3C Cu 9.129 0.062 0.103 260.000 0.385 MOD Technical College-33A- Airport Height Grid H-BB01 MOD Technical College-F1-P081 33 33kV UGC 300 3C Cu 1.314 0.062 0.103 260.000 0.385 P081 Airport Height Grid H-BB02 MOD Technical College-33B-P081 MOD Technical College-F2-P081 33 33kV UGC 300 3C Cu 1.266 0.062 0.103 260.000 0.385

Airport Height Grid H-BB02 ROP Hospital-33-P172 ROP Hospital-F1-P172 33 33kV UGC 300 3C Cu 2.035 0.062 0.103 260.000 0.385

MEDC Distribution System Capability Statement [2021-2023]-V2.0 127 Rusail Industry[G13] - A GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Rusail Industrial H-BB01 - 33 33kV OHL 200 Panther ACSR 1.263 0.137 0.333 10.900 0.385 - - 33 33kV OHL 200 Panther ACSR 1.097 0.137 0.333 10.900 0.385 Cement Housing-F1-P088 - - 33 33kV OHL 200 Panther ACSR 6.717 0.137 0.333 10.900 0.385 - Cement Housing-33A-P088 33 33kV UGC 300 3C Cu 1.262 0.062 0.103 260.000 0.385 Rusail Industrial H-BB01 - 33 33kV OHL 200 Panther ACSR 8.932 0.137 0.333 10.900 0.385 Cement Housing-F2-P088 - Cement Housing-33B-P088 33 33kV UGC 300 3C Cu 1.228 0.062 0.103 260.000 0.385 Rusail Industrial H-BB01 - 33 33kV OHL 200 Panther ACSR 1.263 0.137 0.333 10.900 0.385 - - 33 33kV OHL 200 Panther ACSR 1.097 0.137 0.333 10.900 0.385 Cement Housing-F1-P088 - - 33 33kV OHL 200 Panther ACSR 3.514 0.137 0.333 10.900 0.385 - Al Jifnain 1-33-P042 33 33kV UGC 300 3C Cu 1.035 0.062 0.103 260.000 0.385 Rusail Industrial H-BB02 - 33 33kV UGC 300 3C Cu XLPE 2.020 0.062 0.103 260.000 0.386 Al Jifnain 1 to Al Jifnain 2 Interlink - Al Jifnain 2-33-P196-OD 33 33kV OHL 200 Panther ACSR 3.022 0.137 0.333 10.900 0.420 Rusail Industrial H-BB01 Rusail Industrial 1-33A-P103 Rusail Industrial 1-F1-P103 33 33kV UGC 300 3C Cu 0.547 0.062 0.103 260.000 0.385 Rusail Industrial H-BB02 Rusail Industrial 1-33B-P103 Rusail Industrial 1-F2-P103 33 33kV UGC 300 3C Cu 0.541 0.062 0.103 260.000 0.385 Rusail Industrial H-BB01 Rusail Industrial 2-33A-P104 Rusail Industrial 2-F1-P104 33 33kV UGC 300 3C Cu 1.991 0.062 0.103 260.000 0.385 Rusail Industrial H-BB01 SQU 1-33A-P122 SQU 1-F1-P122 33 33kV UGC 300 3C Cu 4.821 0.062 0.103 260.000 0.385 Rusail Industrial H-BB02 SQU 1-33B-P122 SQU 1-F2-P122 33 33kV UGC 300 3C Cu 4.821 0.062 0.103 260.000 0.385 Rusail Industrial H-BB01 SQU 1-33C-P122 SQU 1-F3-P122 33 33kV UGC 300 3C Cu 4.821 0.062 0.103 260.000 0.385 Rusail Industrial H-BB01 SQU 2-33A-P123 SQU 2-F1-P123 33 33kV UGC 300 3C Cu 6.866 0.062 0.103 260.000 0.385 Rusail Industrial H-BB02 SQU 2-33B-P123 SQU 2-F2-P123 33 33kV UGC 300 3C Cu 6.866 0.062 0.103 260.000 0.385

Rusail Industry[G13] - B GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Rusail Industrial H-BB03 Rusail Industrial 2-33B-P104 Rusail Industrial 2-F2-P104 33 33kV UGC 300 3C Cu 1.990 0.062 0.103 260.000 0.385 Rusail Industrial H-BB03 ROP Al Khoudh-33A-P161 ROP Al Khoudh-F1-P161 33 33kV UGC 300 3C Cu 7.000 0.062 0.103 260.000 0.385 Rusail Industrial H-BB04 ROP Al Khoudh-33B-P161 ROP Al Khoudh-F2-P161 33 33kV UGC 300 3C Cu 7.000 0.062 0.103 260.000 0.385 Rusail Industrial H-BB03 Rusail 08-33A-P164 Rusail 08-F1-P164 33 33kV UGC 300 3C Cu 5.100 0.062 0.103 260.000 0.385 Rusail Industrial H-BB04 Rusail 08-33B-P164 Rusail 08-F2-P164 33 33kV UGC 300 3C Cu 5.100 0.062 0.103 260.000 0.385 Rusail Industrial H-BB04 Rusail 08-33C-P164 Rusail 08-F3-P164 33 33kV UGC 300 3C Cu 5.100 0.062 0.103 260.000 0.385 Rusail Industrial H-BB03 Rusail Ind 4-33A-P158 Rusail Ind 4-F1-P158 33 33kV UGC 300 3C Cu 0.164 0.062 0.103 260.000 0.385 Rusail Industrial H-BB03 Rusail Ind 4-33B-P158 Rusail Ind 4-F2-P158 33 33kV UGC 300 3C Cu 0.157 0.062 0.103 260.000 0.385 Rusail Industrial H-BB04 Rusail Ind 4-33C-P158 Rusail Ind 4-F3-P158 33 33kV UGC 300 3C Cu 0.145 0.062 0.103 260.000 0.385 Rusail Industrial H-BB03 Rusail Industrial 3-33A-P105 Rusail Industrial 3-F1-P105 33 33kV UGC 300 3C Cu 2.829 0.062 0.103 260.000 0.385 Rusail Industrial H-BB04 Rusail Industrial 3-33B-P105 Rusail Industrial 3-F2-P105 33 33kV UGC 300 3C Cu 2.822 0.062 0.103 260.000 0.385 Rusail Industrial H-BB03 Rusail Private Factory-33A-P106 Rusail Private Factory-F1-P106 33 33kV UGC 300 3C Cu 0.795 0.062 0.103 260.000 0.385

Rusail Industrial H-BB04 Rusail Private Factory-33B-P106 Rusail Private Factory-F2-P106 33 33kV UGC 300 3C Cu 0.795 0.062 0.103 260.000 0.385 Rusail Industrial H-BB03 Rusail Housing-33A-P056 Rusail Housing-F1-P056 33 33kV UGC 300 3C Cu 3.993 0.062 0.103 260.000 0.385 Rusail Industrial H-BB04 Rusail Housing-33B-P056 Rusail Housing-F2-P056 33 33kV UGC 300 3C Cu 3.987 0.062 0.103 260.000 0.385 Rusail Industrial H-BB03 SQU 03-33A-P160 SQU 03-F1-P160 33 33kV UGC 300 3C Cu 6.734 0.062 0.103 260.000 0.385 Rusail Industrial H-BB04 SQU 03-33B-P160 SQU 03-F2-P160 33 33kV UGC 300 3C Cu 6.731 0.062 0.103 260.000 0.385 Rusail Industrial H-BB04 SQU 03-33C-P160 SQU 03-F3-P160 33 33kV UGC 300 3C Cu 6.734 0.062 0.103 260.000 0.385

Misfah[G04] GSS [Zone 2] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Misfah Grid H-BB02 - 33 33kV UGC 300 3C Cu 6.724 0.062 0.103 260.000 0.385 Al Awabi-F1-P139 - Al Awabi-33A-P139 33 33kV OHL 200 Panther ACSR 0.370 0.137 0.333 10.900 0.385 Misfah Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.766 0.137 0.333 10.900 0.420 Al Awabi-F2-P139 - Al Awabi-33B-P139 33 33kV UGC 300 3C Cu XLPE 6.285 0.062 0.103 260.000 0.386 Misfah Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.766 0.137 0.333 10.900 0.420 Al Awabi-F3-P139 - Al Awabi-33C-P139 33 33kV UGC 300 3C Cu XLPE 6.285 0.062 0.103 260.000 0.386 Misfah Grid H-BB01 Al Misfah-33A-P080 Al Misfah-F1-P080 33 33kV UGC 300 3C Cu 3.517 0.062 0.103 260.000 0.385 Misfah Grid H-BB02 Al Misfah-33B-P080 Al Misfah-F2-P080 33 33kV UGC 300 3C Cu 3.540 0.062 0.103 260.000 0.385 Misfah Grid H-BB01 Al Misfah-33C-P080 Al Misfah-F3-P080 33 33kV UGC 300 3C Cu 3.537 0.062 0.103 260.000 0.385 Misfah Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 1.800 0.137 0.333 10.900 0.385 Cement Factory 1-F1-P079 - Cement Factory 1-33A-P079 33 33kV UGC 300 3C Cu 1.446 0.062 0.103 260.000 0.385 Misfah Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 1.800 0.137 0.333 10.900 0.385 Cement Factory 1-F2-P079 - Cement Factory 1-33B-P079 33 33kV UGC 300 3C Cu 1.446 0.062 0.103 260.000 0.385 Misfah Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 1.800 0.137 0.333 10.900 0.385 Cement Factory 1-F3-P079 - Cement Factory 1-33C-P079 33 33kV UGC 300 3C Cu 1.446 0.062 0.103 260.000 0.385 Misfah Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 1.800 0.137 0.333 10.900 0.385 Cement Factory 1-F4-P079 - Cement Factory 1-33D-P079 33 33kV UGC 300 3C Cu 1.446 0.062 0.103 260.000 0.385 Misfah Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 1.800 0.137 0.333 10.900 0.385 Cement Factory 1-F5-P079 - Cement Factory 1-33E-P079 33 33kV UGC 300 3C Cu 1.446 0.062 0.103 260.000 0.385 Misfah Grid H-BB01 Orpic-33A-P192 Orpic-F1-P192 33 33kV UGC 300 3C Cu 9.708 0.062 0.103 260.000 0.385 Misfah Grid H-BB01 Orpic-33B-P192 Orpic-F2-P192 33 33kV UGC 300 3C Cu 9.708 0.062 0.103 260.000 0.385

MEDC Distribution System Capability Statement [2021-2023]-V2.0 128 Barka[G02] GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Barka Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 3.665 0.137 0.333 10.900 0.385 Manoma 1-F1-P067 - Manoma 1-33A-P067 33 33kV UGC 300 3C Cu 4.370 0.062 0.103 260.000 0.385 Barka Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 5.000 0.137 0.333 10.900 0.385 Manoma 1-F2-P067 - Manoma 1-33B-P067 33 33kV UGC 300 3C Cu 1.734 0.062 0.103 260.000 0.385 Barka Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 12.030 0.137 0.333 10.900 0.385 Mabelah South-F1-P061 - Mabelah South-33A-P061 33 33kV UGC 300 3C Cu 1.444 0.062 0.103 260.000 0.385 Barka Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 12.021 0.137 0.333 10.900 0.385 Mabelah South-F2-P061 - Mabelah South-33B-P061 33 33kV UGC 300 3C Cu 1.644 0.062 0.103 260.000 0.385 33kV OHL 100 Dog ACSR + Barka Grid H-BB01 - 33 13.486 0.320 0.350 16.700 0.269 Old Mabelah-F2-P059 (from Barka GSS) 33kV OHL 150 Wolf ACSR - Old Mabelah-33A-P059 33 33kV UGC 300 3C Cu 6.395 0.062 0.103 260.000 0.385 Barka Grid H-BB02 - 33 33kV OHL 100 Dog ACSR 9.384 0.320 0.350 16.700 0.269 Old Mabelah-F1-P059 (from Barka GSS) - RGO Halban Camp-33A-P034 33 33kV UGC 300 3C Cu 1.395 0.062 0.103 260.000 0.269 Barka Grid H-BB02 - 33 33kV OHL 100 Dog ACSR 9.884 0.320 0.350 16.700 0.269 Old Mabelah-F1-P059 (from Barka GSS) - Palace Communication-33-P033 33 33kV OHL 100 Dog ACSR 1.395 0.062 0.103 260.000 0.269

Mabelah[GP04] GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Mabelah 1 Grid H-BB01 Sur Al Hadid -33A-P116 Sur Al Hadid-F1-P116 33 33kV UGC 300 3C Cu 13.083 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB02 Sur Al Hadid -33B-P116 Sur Al Hadid-F2-P116 33 33kV UGC 300 3C Cu 13.157 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB01 Mabelah Grid-33A-GP04 Mabelah Grid-F1-GP04 33 33kV UGC 300 3C Cu 0.052 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB02 Mabelah Grid-33B-GP04 Mabelah Grid-F2-GP04 33 33kV UGC 300 3C Cu 0.052 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB01 Mabelah A-33A-P063 Mabelah A-F1-P063 33 33kV UGC 300 3C Cu 4.001 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB02 Mabelah A-33B-P063 Mabelah A-F2-P063 33 33kV UGC 300 3C Cu 3.951 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 1.451 0.137 0.333 10.900 0.420 Mabelah A-F3-P063 (Mab. Shabiya F1) - Mabelah A-33C-P063 33 33kV UGC 300 3C Cu XLPE 3.709 0.062 0.103 260.000 0.386 Mabelah 1 Grid H-BB02 - Old Mabelah-F2-P059 (from Mabelah 33 33kV OHL 100 Dog ACSR 7.538 0.320 0.350 16.700 0.269 - Old Mabelah-33B-P059 GSS) 33 33kV UGC 300 3C Cu 3.659 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB01 Mabelah STP-33A-P140 Mabelah STP-F1-P140 33 33kV UGC 300 3C Cu 11.536 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB02 Mabelah STP-33B-P140 Mabelah STP-F2-P140 33 33kV UGC 300 3C Cu 11.540 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB01 Mabelah South PH-7-33A-P141 Mabelah South PH-7-F1-P141 33 33kV UGC 300 3C Cu 7.305 0.062 0.103 260.000 0.385

Mabelah 1 Grid H-BB02 Mabelah South PH-7-33B-P141 Mabelah South PH-7-F2-P141 33 33kV UGC 300 3C Cu 7.285 0.062 0.103 260.000 0.385 Mabelah South PH-7-F3-P141 (Mab 33 33kV UGC 300 3C Cu 6.115 0.062 0.103 260.000 0.386 Mabelah 1 Grid H-BB02 Mabelah South PH 7-33C-P141 Shabiya F2) 33 33kV OHL 200 Panther ACSR 1.353 0.137 0.333 10.900 0.420 Mabelah 1 Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 0.525 0.137 0.333 10.900 0.385 Botanic Garden-F1-P016 - Botanic Garden-33A-P016 33 33kV UGC 300 3C Cu 7.844 0.062 0.103 260.000 0.385 Mabelah 1 Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 0.525 0.137 0.333 10.900 0.385 Botanic Garden-F2-P016 - Botanic Garden-33B-P016 33 33kV 3Cx300 7.721 0.060 0.104 260.000 0.435 - Old Mabelah-F1-P059 (from Barka GSS) – This feeder feeds RGO Halban Camp-P034, Palace Communication-P033 primary substations

Mabelah 2[G12] - A GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] A'Salam (Mobella 2A) Grid H- Mabelah C-33A-P064 Mabelah C-F1-P064 33 33kV UGC 300 3C Cu 0.941 0.062 0.103 260.000 0.385 BB01 A'Salam (Mobella 2A) Grid H- Mabelah C-33B-P064 Mabelah C-F2-P064 33 33kV UGC 300 3C Cu 0.941 0.062 0.103 260.000 0.385 BB02 A'Salam (Mobella 2A) Grid H- Mabelah C-33C-P064 Mabelah C-F3-P064 33 33kV UGC 300 3C Cu 0.941 0.062 0.103 260.000 0.385 BB02 A'Salam (Mobella 2A) Grid H- Mabelah South PH-4-33A-P062 Mabelah South PH-4-F1-P062 33 33kV UGC 300 3C Cu 3.573 0.062 0.103 260.000 0.385 BB01 A'Salam (Mobella 2A) Grid H- Mabelah South PH-4-33B-P062 Mabelah South PH-4-F2-P062 33 33kV UGC 300 3C Cu 3.553 0.062 0.103 260.000 0.385 BB02 A'Salam (Mobella 2A) Grid H- Mabelah South PH-4-33C-P062 Mabelah South PH-4-F3-P062 33 33kV UGC 300 3C Cu 3.497 0.062 0.103 260.000 0.385 BB02 A'Salam (Mobella 2A) Grid H- Mabelah South PH-8-33A-P157 Mabelah South PH-8-F1-P157 33 33kV UGC 300 3C Cu 7.810 0.062 0.103 260.000 0.385 BB01 A'Salam (Mobella 2A) Grid H- Mabelah South PH-8-33B-P157 Mabelah South PH-8-F2-P157 33 33kV UGC 300 3C Cu 7.818 0.062 0.103 260.000 0.385 BB01 A'Salam (Mobella 2A) Grid H- Mabelah South PH-8-33C-P157 Mabelah South PH-8-F3-P157 33 33kV UGC 300 3C Cu 7.800 0.062 0.103 260.000 0.385 BB02 A'Salam (Mobella 2A) Grid H- Palm Mall-33A-P168 Palm Mall-F1-P168 33 33kV UGC 300 3C Cu 0.830 0.062 0.103 260.000 0.385 BB01 A'Salam (Mobella 2A) Grid H- Palm Mall-33B-P168 Palm Mall-F2-P168 33 33kV UGC 300 3C Cu 0.864 0.062 0.103 260.000 0.385 BB01 A'Salam (Mobella 2A) Grid H- Palm Mall-33C-P168 Palm Mall-F3-P168 33 33kV UGC 300 3C Cu 0.842 0.062 0.103 260.000 0.385 BB02

Mabella 2[G12] - B GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] A'Salam (Mobella 2A) Grid H- Mabelah Shabiya-33A-P060 Mabelah Shabiya-F1-P060 33 33kV UGC 300 3C Cu 3.354 0.062 0.103 260.000 0.385 BB01 A'Salam (Mobella 2A) Grid H- Mabelah Shabiya-33B-P060 Mabelah Shabiya-F2-P060 33 33kV UGC 300 3C Cu 3.321 0.062 0.103 260.000 0.385 BB02 A'Salam (Mobella 2A) Grid H- Mabelah Shabiya-33C-P060 Mabelah Shabiya-F3-P060 33 33kV UGC 300 3C Cu 3.354 0.062 0.103 260.000 0.385 BB02

MEDC Distribution System Capability Statement [2021-2023]-V2.0 129 Seeb[GP08] - A GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Seeb Main A Grid H-BB01 Al Khoud PH-7-33A-P154 Al Khoud PH-7-F1-P154 33 33kV UGC 300 3C Cu 6.240 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB02 Al Khoud PH-7-33B-P154 Al Khoud PH-7-F2-P154 33 33kV UGC 300 3C Cu 6.225 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB02 Al Khoud PH-7-33C-P154 Al Khoud PH-7-F3-P154 33 33kV UGC 300 3C Cu 6.223 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB02 Wadi Bahayis (RGO)-33A-P098 Wadi Bahayis (RGO)-F1-P098 33 33kV UGC 300 3C Cu 1.278 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB01 - 33 33kV UGC 300 3C Cu 0.955 0.062 0.103 260.000 0.385 Wadi Bahayis (RGO)-F2-P098 - Wadi Bahayis (RGO)-33B-P098 33 33kV UGC 300 3C Cu 0.333 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB01 - 33 33kV OHL 200 Panther ACSR 3.688 0.137 0.333 10.900 0.385 Al Khoud Shabiya-F1-P046 - Al Khoud Shabiya-33A-P046 33 33kV UGC 300 3C Cu 2.209 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB02 - 33 33kV OHL 200 Panther ACSR 3.688 0.137 0.333 10.900 0.385 Al Khoud Shabiya-F2-P046 - Al Khoud Shabiya-33B-P046 33 33kV UGC 300 3C Cu 2.209 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB01 Wadi Al Lawami-33A-P117 Wadi Al Lawami-F1-P117 33 33kV UGC 300 3C Cu 1.054 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB02 Wadi Al Lawami-33B-P117 Wadi Al Lawami-F2-P117 33 33kV UGC 300 3C Cu 1.041 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB02 Wadi Al Lawami-33C-P117 Wadi Al Lawami-F3-P117 33 33kV UGC 300 3C Cu 1.041 0.062 0.103 260.000 0.385 Seeb Main A Grid H-BB02 - 33 33kV UGC 300 3C Cu 5.044 0.062 0.103 260.000 0.385 Wadi Al Aresh-F1-P115 - Wadi Al Aresh-33A-P115 33 33kV OHL 200 Panther ACSR 1.310 0.137 0.333 10.900 0.385 Seeb Main A Grid H-BB01 - 33 33kV UGC 300 3C Cu 5.626 0.062 0.103 260.000 0.385 Wadi Al Aresh-F2-P115 - Wadi Al Aresh-33B-P115 33 33kV OHL 200 Panther ACSR 0.927 0.137 0.333 10.900 0.385

Seeb[GP08] - B GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Seeb Main B Grid H-BB01 Seeb Grid-33A-GP08 Seeb Grid-F1-GP08 33 33kV UGC 300 3C Cu 0.037 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB02 Seeb Grid-33B-GP08 Seeb Grid-F2-GP08 33 33kV UGC 300 3C Cu 0.034 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB01 Sultan School-33A-P029 Sultan School-F1-P029 33 33kV UGC 300 3C Cu 3.042 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB02 Sultan School-33B-P029 Sultan School-F2-P029 33 33kV UGC 300 3C Cu 3.058 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB01 Al Hail South 2-33A-P153 Al Hail South 2-F1-P153 33 33kV UGC 300 3C Cu 5.829 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB01 Al Hail South 2-33B-P153 Al Hail South 2-F2-P153 33 33kV UGC 300 3C Cu 5.807 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB02 Al Hail South 2-33C-P153 Al Hail South 2-F3-P153 33 33kV UGC 300 3C Cu 5.799 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB02 - 33 33kV UGC 300 3C Cu 0.002 0.062 0.103 260.000 0.385 - - New Al Khoud-F1-P047 33 33kV OHL 200 Panther ACSR 2.176 0.137 0.333 10.900 0.385 - New Al Khoud-33A-P047 33 33kV UGC 300 3C Cu 0.545 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB02 - 33 33kV UGC 300 3C Cu 0.002 0.062 0.103 260.000 0.385 - - New Al Khoud-F2-P047 33 33kV UGC 300 3C Cu 0.603 0.062 0.103 260.000 0.385 - New Al Khoud-33B-P047 33 33kV OHL 200 Panther ACSR 2.155 0.137 0.333 10.900 0.385 Seeb Main B Grid H-BB02 Seeb05 (Boulevard)-33A-P186 Seeb05 (Boulevard)-F1-P186 33 33kV UGC 300 3C Cu 1.500 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB02 Seeb05 (Boulevard)-33B-P186 Seeb05 (Boulevard)-F2-P186 33 33kV UGC 300 3C Cu 1.500 0.062 0.103 260.000 0.385 Seeb Main B Grid H-BB01 Seeb05 (Boulevard)-33C-P186 Seeb05 (Boulevard)-F3-P186 33 33kV UGC 300 3C Cu 1.500 0.062 0.103 260.000 0.385

Mawaleh South[GP05] - A GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Mawalleh A Grid H-BB01 Al Hail North 2-33A-P028 Al Hail North 2-F1-P028 33 33kV UGC 300 3C Cu 7.347 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB02 Al Hail North 2-33B-P028 Al Hail North 2-F2-P028 33 33kV UGC 300 3C Cu 7.371 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB01 Mawaleh C-33A-P072 Mawaleh C-F1-P072 33 33kV UGC 300 3C Cu 2.700 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB02 Mawaleh C-33B-P072 Mawaleh C-F2-P072 33 33kV UGC 300 3C Cu 2.700 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB01 Royal Flight-33A-P100 Royal Flight-F1-P100 33 33kV UGC 300 3C Cu 6.125 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB02 Royal Flight-33B-P100 Royal Flight-F2-P100 33 33kV UGC 300 3C Cu 6.125 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB02 Mawaleh South Grid-33B-GP05 Mawaleh South Grid-F1-GP05 33 33kV UGC 300 3C Cu 0.030 0.062 0.103 260.000 0.385

Mawalleh A Grid H-BB01 Mawaleh South Grid-33A-GP05 Mawaleh South Grid-F2-GP05 33 33kV UGC 300 3C Cu 0.030 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB01 Al Khoud PH-3-33A-P048 Al Khoud PH-3-F1-P048 33 33kV UGC 300 3C Cu 2.960 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB02 Al Khoud PH-3-33B-P048 Al Khoud PH-3-F2-P048 33 33kV UGC 300 3C Cu 2.926 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB02 Mawaleh A-33B-P070 Mawaleh A-F2-P070 33 33kV UGC 300 3C Cu 0.887 0.062 0.103 260.000 0.385 Mawalleh A Grid H-BB02 Mawaleh B-33B-P071 Mawaleh B-F2-P071 33 33kV UGC 300 3C Cu 1.937 0.062 0.103 260.000 0.385

Mawaleh South[GP05] - B GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] Mawaleh B Grid H-BB03 AL Hail South 1-33A-P030 AL Hail South 1-F1-P030 33 33kV UGC 300 3C Cu 4.445 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB04 AL Hail South 1-33B-P030 AL Hail South 1-F2-P030 33 33kV UGC 300 3C Cu 4.445 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB03 - 33 33kV OHL 200 Panther ACSR 0.587 0.137 0.333 10.900 0.385 Mawaleh A-F1-P070 - Mawaleh A-33A-P070 33 33kV UGC 300 3C Cu 0.876 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB03 Mawaleh A-33C-P070 Mawaleh A-F3-P070 33 33kV UGC 300 3C Cu 0.583 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB03 Mawaleh B-33A-P071 Mawaleh B-F1-P071 33 33kV UGC 300 3C Cu 1.911 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB04 Mawaleh B-33C-P071 Mawaleh B-F3-P071 33 33kV UGC 300 3C Cu 1.936 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB03 Al Khoud PH-6-33A-P049 Al Khoud PH-6-F1-P049 33 33kV UGC 300 3C Cu 9.039 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB04 Al Khoud PH-6-33B-P049 Al Khoud PH-6-F2-P049 33 33kV UGC 300 3C Cu 9.044 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB03 Mawaleh South 5-33A-P148 Mawaleh South 5-F1-P148 33 33kV UGC 300 3C Cu 2.507 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB04 Mawaleh South 5-33B-P148 Mawaleh South 5-F2-P148 33 33kV UGC 300 3C Cu 2.500 0.062 0.103 260.000 0.385 Mawaleh B Grid H-BB04 Mawaleh South 5-33C-P148 Mawaleh South 5-F3-P148 33 33kV UGC 300 3C Cu 2.493 0.062 0.103 260.000 0.385

MEDC Distribution System Capability Statement [2021-2023]-V2.0 130 Mawaleh North [GP01] GSS [Zone 3] Network Resistance Reactance Capacitance Continuous Length Node 1 Node 2 33kV Feeder ID Level Type Name ( R ) ( X ) ( C ) Rating [km] [kV] [Ohm/km] [Ohm/km] [nF/km] [kAmps] MawalehNorth Grid-33-HBB A Al Hail North 1-33A-P027 Al Hail North 1-F1-P027 33 33kV UGC 300 3C Cu 1.961 0.062 0.103 260.000 0.385 MawalehNorth Grid-33-HBB B Al Hail North 1-33B-P027 Al Hail North 1-F2-P027 33 33kV UGC 300 3C Cu 1.961 0.062 0.103 260.000 0.385 MawalehNorth Grid-33-HBB A City Centre-33A-P073 City Centre-F1-P073 33 33kV UGC 300 3C Cu 2.500 0.062 0.103 260.000 0.385 MawalehNorth Grid-33-HBB B City Centre-33B-P073 City Centre-F2-P073 33 33kV UGC 300 3C Cu 2.500 0.062 0.103 260.000 0.385 MawalehNorth Grid-33-HBB A Mawaleh North-33A-P069 Mawaleh North-F1-P069 33 33kV UGC 300 3C Cu 1.000 0.062 0.103 260.000 0.385 MawalehNorth Grid-33-HBB B Mawaleh North-33B-P069 Mawaleh North-F2-P069 33 33kV UGC 300 3C Cu 1.000 0.062 0.103 260.000 0.385 MawalehNorth Grid-33-HBB A Mawaleh North Grid-33A-GP01 Mawaleh North Grid-F1-GP01 33 33kV UGC 300 3C Cu 0.050 0.062 0.103 260.000 0.385

MawalehNorth Grid-33-HBB A Mawaleh North Grid-33B-GP01 Mawaleh North Grid-F2-GP01 33 33kV UGC 300 3C Cu 0.050 0.062 0.103 260.000 0.385

MawalehNorth Grid-33-HBB B Mawaleh North Grid-33C-GP01 Mawaleh North Grid-F3-GP01 33 33kV UGC 300 3C Cu 0.050 0.062 0.103 260.000 0.385

MEDC Distribution System Capability Statement [2021-2023]-V2.0 131

Appendix E2 – Primary Substation Transformer Data Appendix E2 presents the data used to model the primary substation power transformers for the load flow and fault current calculation studies. The data comprises of the transformer nameplate data and includes ONAF power rating, voltage ratio, percentage impedance (based on transformer rating) and the tap range and step size.

Explanatory Notes: a) The method of earthing at all the 33/11.5kV primary substations power transformers is ‘solidly earthed’ except the following where resistance earthing is applied: − Rusail Housing-P056 PSS b) MEDC is currently in process of developing the typical values for zero sequence resistance and zero sequence reactance for future improvements.

MEDC Distribution System Capability Statement (2021-2023) – V2.0 132 Falaj[G23] GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Darsait-Tx1-P018 33 11.5 20 12.5 DYN11 1 12 15 1.67 Darsait-Tx2-P018 33 11.5 20 12.3 DYN11 1 12 15 1.67 Falaj-Tx1-P178 33 11.5 16 10.3 DYN11 3 12 15 1.67 Falaj-Tx2-P178 33 11.5 16 10.4 DYN11 1 12 15 1.67 Jibrooh-Tx1-P041 33 11.5 20 12.4 DYN11 1 12 15 1.67 Jibrooh-Tx2-P041 33 11.5 20 12.4 DYN11 1 12 15 1.67 Jibrooh-Tx3-P041 33 11.5 20 12.3 DYN11 1 12 15 1.67 Mutrah Store-Tx1-P085 33 11.5 20 12.4 DYN11 1 10 13 1.67 Mutrah Store-Tx2-P085 33 11.5 20 12.5 DYN11 1 10 13 1.67 Seaport-Tx1-P086 33 11.5 6 6.4 DYN11 1 5 7 2.50 Seaport-Tx2-P086 33 11.5 6 6.4 DYN11 1 5 7 2.50

Mutrah[G21] GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Bait Al Falaj-Tx1-P142 33 11.5 20 12.2 DYN11 3 12 15 1.67 Bait Al Falaj-Tx2-P142 33 11.5 20 12.2 DYN11 3 12 15 1.67 Bait Al Falaj-Tx3-P142 33 11.5 20 12.2 DYN11 3 12 15 1.67 C.B.D-Tx1-P173 33 11.5 16 9.4 DYN11 1 10 13 1.67 C.B.D-Tx2-P173 33 11.5 16 9.5 DYN11 1 10 13 1.67 C.B.D-Tx3-P173 33 11.5 16 9.5 DYN11 1 10 13 1.67 Riyam-Tx1-P099 33 11.5 20 12.4 DYN11 3 12 15 1.67 Riyam-Tx2-P099 33 11.5 20 12.5 DYN11 3 12 15 1.67 Ruwi Office-Tx1-P108 33 11.5 20 12.5 DYN11 3 12 15 1.67 Ruwi Office-Tx2-P108 33 11.5 20 12.6 DYN11 3 12 15 1.67

Wadi Al Kabir[G19] - A GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Ali Shihani-Tx1-P125 33 11.5 20 12.5 DYN11 3 12 15 1.67 Ali Shihani-Tx2-P125 33 11.5 20 12.5 DYN11 3 12 15 1.67 M.B.D. South-Tx1-P075 33 11.5 20 12.1 DYN11 3 12 15 1.67 M.B.D. South-Tx2-P075 33 11.5 20 12.1 DYN11 3 12 15 1.67 Majlis Oman-Tx1-P066 33 11.5 20 12.5 DYN11 3 12 15 1.67 Majlis Oman-Tx2-P066 33 11.5 20 12.4 DYN11 3 12 15 1.67 Qasr al Alam-Tx1-P090 33 11.5 20 12.2 DYN11 3 12 15 1.67 Qasr al Alam-Tx2-P090 33 11.5 20 12.3 DYN11 3 12 15 1.67 Sidab-Tx1-P119 33 11.5 6 6.0 DYN11 1 5 7 2.50 Sidab-Tx2-P119 33 11.5 6 6.3 DYN11 1 5 7 2.50 Wadi Al Kabir Housing-Tx1-P127-OD 33 11.5 6 6.2 DYN11 1 3 4 2.50 Wadi Al Kabir Workshop-Tx1-P126-OD 33 11.5 6 6.1 DYN11 1 5 7 2.50 Wadi Al Kabir Workshop-Tx2-P126-OD 33 11.5 6 6.5 DYN11 1 5 7 2.50 Walja-Tx1-P130 33 11.5 20 12.5 DYN11 3 12 15 1.67 Walja-Tx2-P130 33 11.5 20 12.6 DYN11 3 12 15 1.67

Wadi Al Kabir[G19] - B GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Old Airport-Tx1-P107 33 11.5 20 12.1 DYN11 3 12 15 1.67 Old Airport-Tx2-P107 33 11.5 20 11.8 DYN11 3 12 15 1.67 Ruwi Market-Tx1-P076 33 11.5 20 12.2 DYN11 1 10 13 1.67 Ruwi Market-Tx2-P076 33 11.5 20 12.1 DYN11 1 10 13 1.67 Ruwi Valley-Tx1-P174 33 11.5 20 11.9 DYN11 3 12 15 1.67 Ruwi Valley-Tx2-P174 33 11.5 20 11.8 DYN11 3 12 15 1.67 Wadi Al Kabir Height 1-Tx1-P128 33 11.5 20 12.4 DYN11 3 12 15 1.67 Wadi Al Kabir Height 1-Tx2-P128 33 11.5 20 12.4 DYN11 3 12 15 1.67

MEDC Distribution System Capability Statement [2021-2023]-V2.0 133 Wadi Adai[G22] GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Bustan Palace-Tx1-P017 33 11.5 16 10.2 DYN11 3 12 15 1.67 Al Bustan Palace-Tx2-P017 33 11.5 16 10.2 DYN11 3 12 15 1.67 Al Hamryah-Tx1-P035 33 11.5 20 12.4 DYN11 3 12 15 1.67 Al Hamryah-Tx2-P035 33 11.5 20 12.4 DYN11 3 12 15 1.67 Al Mahaj-Tx1-P136-OD 33 11.5 6 6.3 DYN11 1 5 7 2.50 Al Mahaj-Tx2-P136-OD 33 11.5 6 6.2 DYN11 1 5 7 2.50 Amerat 1-Tx1-P005 33 11.5 16 10.3 DYN11 3 12 15 1.67 Amerat 1-Tx2-P005 33 11.5 16 10.4 DYN11 3 12 15 1.67 Khoula Hospital-Tx1-P132 33 11.5 20 12.4 DYN11 3 12 15 1.67 Khoula Hospital-Tx2-P132 33 11.5 20 12.5 DYN11 3 12 15 1.67 Khoula Hospital-Tx3-P132 33 11.5 20 12.5 DYN11 3 12 15 1.67 Qantab-Tx-P089-OD 33 11.5 3 6.0 DYN11 1 5 7 2.50 Wadi Adai-Tx1-P175 33 11.5 20 12.6 DYN11 3 12 15 1.67 Wadi Adai-TX2-P175 33 11.5 20 12.6 DYN11 3 12 15 1.67 Wattaya-Tx1-P131 33 11.5 20 12.5 DYN11 3 12 15 1.67 Wattaya-Tx2-P131 33 11.5 20 12.6 DYN11 3 12 15 1.67

Jahloot[G03] GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Atkiya-Tx1-P182 33 11.5 6 6.2 DYN11 1 5 7 2.50 Al Hajir-Tx1-P031 33 11.5 20 12.2 DYN11 3 12 15 1.67 Al Hajir-Tx2-P031 33 11.5 20 12.1 DYN11 3 12 15 1.67 Al Masarat-Tx1-P068 33 11.5 10 7.6 DYN11 2 11 14 1.67 Al Masarat-Tx2-P068 33 11.5 10 7.9 DYN11 2 11 14 1.67 Arqi-Tx-P121-OD 33 11.5 3 5.5 DYN11 1 3 5 2.50 Bar Al Jissah 1-Tx1-P044 33 11.5 20 12.4 DYN11 3 12 15 1.67 Bar Al Jissah 1-Tx2-P044 33 11.5 20 12.5 DYN11 3 12 15 1.67 Debha-Tx-P114-OD 33 11 6 5.3 DYN11 1 5 7 2.50 Hussan Yitti-Tx1-P169-OD 33 11.5 6 6.4 DYN11 1 5 7 2.50 Hussan Yitti-Tx2-P169-OD 33 11.5 6 6.4 DYN11 1 5 7 2.50 Jahloot-Tx1-P040-OD 33 11.5 6 6.0 DYN11 1 6 8 2.50 Jahloot-Tx2-P040-OD 33 11.5 6 6.2 DYN11 1 5 7 2.50 ROP Al Saleel-Tx1-P162-OD 33 11.5 6 6.0 DYN11 1 5 7 2.50 ROP Al Saleel-Tx2-P162-OD 33 11.5 6 6.0 DYN11 1 5 7 2.50 Sawaqim 1-Tx1-P112-OD 33 11 6 6.6 DYN11 1 3 5 2.50 Sawaqim 1-Tx2-P112-OD 33 11.5 6 6.4 DYN11 1 3 5 2.50 Sawaqim 2-Tx-P113-OD 33 11.5 6 6.0 DYN11 1 5 7 2.50 Siya-Tx1-P120 33 11.5 6 6.1 DYN11 1 3 5 2.50 Siya-Tx2-P120 33 11.5 6 6.1 DYN11 1 3 5 2.50 Tunis-Tx-P137-OD 33 11.5 6 6.2 DYN11 1 5 7 2.50 Wadi Al Mayh-Tx-P129-OD 33 11.5 3 5.5 DYN11 1 3 5 2.50 Water Pumping-Tx1-P193-OD 33 6.9 6 7.6 DYN11 1 5 7 2.50 Water Pumping-Tx2-P193-OD 33 6.9 6 7.6 DYN11 1 5 7 2.50

Yiti[G08] GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Khairan-Tx1-P045 33 11.5 6 6.1 DYN11 1 5 7 2.50 Al Khairan-Tx2-P045 33 11.5 3 5.5 DYN11 1 5 7 2.50 Al Salam Yiti-Tx-P135 33 11.5 6 6.0 DYN11 1 5 7 2.50 Jabal Al Sifah-Tx1-P159 33 11.5 20 11.6 DYN11 3 12 15 1.67 Jabal Al Sifah-Tx2-P159 33 11.5 20 11.6 DYN11 3 12 15 1.67 Jabal Al Sifah-Tx3-P159 33 11.5 20 11.7 DYN11 3 12 15 1.67 Saraya Bander-Tx1-P145 33 11.5 20 12.2 DYN11 3 12 15 1.67 Saraya Bander-Tx2-P145 33 11.5 20 12.1 DYN11 3 12 15 1.67 Saraya Bander-Tx3-P145 33 11.5 20 12.1 DYN11 3 12 15 1.67 Yenkit 1-Tx2-P133 33 11.5 3 5.5 DYN11 1 5 7 2.50 Yenkit 1-Tx1-P133 33 11.5 1 4.5 DYN11 1 5 7 2.50 Yiti 1-Tx1-P134 33 11.5 3 6.1 DYN11 1 5 7 2.50 Yiti 1-Tx2-P134 33 11.5 3 6.1 DYN11 1 5 7 2.50

MEDC Distribution System Capability Statement [2021-2023]-V2.0 134 Quriyat[G05] GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Mazara-Tx1-P074-OD 33 11.5 6 6.1 DYN11 1 5 7 2.50 Al Mazara-Tx2-P074-OD 33 11.5 6 5.8 DYN11 1 5 7 2.50 Al Shahbari-Tx1-P092 33 11.5 20 12.3 DYN11 3 12 15 1.67 Al Shahbari-Tx2-P092 33 11.5 20 12.7 DYN11 3 12 15 1.67 Dhabab-Tx1-P019 33 11.5 6 6.1 DYN11 1 5 7 2.50 Dhabab-Tx2-P019 33 11.5 6 6.1 DYN11 1 5 7 2.50 Dhagmar 1-Tx1-P021 33 11.5 6 6.3 DYN11 1 5 7 2.50 Dhagmar 1-Tx2-P021 33 11.5 6 6.0 DYN11 1 5 7 2.50 Dhagmar 1-Tx3-P021 33 11.5 6 6.4 DYN11 1 5 7 2.50 Dhagmar 1-Tx4-P021 33 11.5 6 6.0 DYN11 1 5 7 2.50 Hail Al Ghaf-Tx1-P036-OD 33 11.5 6 6.2 DYN11 1 5 7 2.50 Hail Al Ghaf-Tx2-P036-OD 33 11.5 6 6.5 DYN11 1 5 7 2.50 Quriyat-Tx1-P091 33 11.5 20 12.3 DYN11 3 12 15 1.67 Quriyat-Tx2-P091 33 11.5 20 12.3 DYN11 3 12 15 1.67 Royal Camp-Tx-P170-OD 33 11.5 3 5.8 DYN11 1 5 7 2.50 Street Light-Tx-P020 33 11.5 6 6.0 DYN11 1 5 7 2.50 Wadi Al Arbyeen-Tx-P124 33 11.5 6 6.4 DYN11 1 5 7 2.50

Amerat[G10] - A GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Amerat 3-Tx1-P179 33 11.5 20 12.2 DYN11 3 12 15 1.67 Amerat 3-Tx2-P179 33 11.5 20 12.1 DYN11 3 12 15 1.67 Amerat 3-Tx3-P179 33 11.5 20 12.2 DYN11 3 12 15 1.67 Amerat Heights-Tx1-P152 33 11.5 20 12.1 DYN11 3 12 15 1.67 Amerat Heights-Tx2-P152 33 11.5 20 12.1 DYN11 3 12 15 1.67 Amerat Heights-Tx3-P152 33 11.5 20 12.1 DYN11 3 12 15 1.67 Post Office-Tx1-P150 33 11.5 20 12.3 DYN11 3 12 15 1.67 Post Office-Tx2-P150 33 11.5 20 12.3 DYN11 3 12 15 1.67 Post Office-Tx3-P150 33 11.5 20 12.1 DYN11 3 12 15 1.67

Amerat[G10] - B GSS [Zone 1] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Jufaina-Tx-P194 33 11.5 6 6.2 DYN11 1 5 7 2.50 Al Nahdah-Tx1-P006 33 11.5 20 10.7 DYN11 3 12 15 1.67 Al Nahdah-Tx2-P006 33 11.5 20 10.8 DYN11 3 12 15 1.67 Al Nahdah-Tx3-P006 33 11.5 20 10.4 DYN11 3 12 15 1.67 Madinat Al Nahdah-Tx1-P065 33 11.5 20 12.8 DYN11 3 12 15 1.67 Madinat Al Nahdah-Tx2-P065 33 11.5 20 12.6 DYN11 3 12 15 1.67 Seih Dhabi-Tx1-P118 33 11.5 16 10.5 DYN11 3 12 15 1.67 Seih Dhabi-Tx2-P118 33 11.5 16 10.5 DYN11 3 12 15 1.667

Ghubrah 2[G09] GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Azaiba North 2-Tx1-P012 33 11.5 20 12.2 DYN11 3 12 15 1.67 Azaiba North 2-Tx2-P012 33 11.5 20 12.6 DYN11 3 12 15 1.67 Azaiba South 1A-Tx1-P014 33 11.5 20 12.3 DYN11 3 12 15 1.67 Azaiba South 1A-Tx2-P014 33 11.5 20 12.3 DYN11 3 12 15 1.67 Diplomatic City 1-Tx1-P022 33 11.5 20 12.8 DYN11 3 12 15 1.67 Diplomatic City 1-Tx2-P022 33 11.5 20 12.6 DYN11 3 12 15 1.67 Diplomatic City 1-Tx3-P022 33 11.5 20 12.0 DYN11 3 12 15 1.67 Ghubra North 1-Tx1-P023 33 11.5 20 12.3 DYN11 3 12 15 1.67 Ghubra North 1-Tx2-P023 33 11.5 20 12.3 DYN11 3 12 15 1.67 Ghubra North 1-Tx3-P023 33 11.5 20 12.3 DYN11 3 12 15 1.67 Ghubrah GPS-Tx1-P166-Pvt 33 11.5 16 11.9 DYN11 3 12 15 1.67 Ghubrah GPS-Tx2-P166-Pvt 33 11.5 16 12.1 DYN11 3 12 15 1.67 Ghubrah North 02-Tx1-P149 33 11.5 20 11.7 DYN11 3 12 15 1.67 Ghubrah North 02-Tx2-P149 33 11.5 20 11.7 DYN11 3 12 15 1.67 Ghubrah North 02-Tx3-P149 33 11.5 20 11.7 DYN11 3 12 15 1.67

MEDC Distribution System Capability Statement [2021-2023]-V2.0 135 MSQ[GP06] - A GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Khuwair North-Tx1-P054 33 11.5 20 11.1 DYN11 3 12 15 1.67 Al Khuwair North-Tx2-P054 33 11.5 20 11.0 DYN11 3 12 15 1.67 Al Khuwair North-Tx3-P054 33 11.5 20 11.1 DYN11 3 12 15 1.67 Information City 2-Tx-P038 33 11.5 5 7.2 DYN11 1 3 5 2.50 Intercontinental-Tx1-P109 33 11.5 20 10.0 DYN11 3 12 15 1.67 Intercontinental-Tx2-P109 33 11.5 20 10.1 DYN11 3 12 15 1.67 MSQ Grid-Tx1-GP06 33 11.5 20 12.3 DYN11 3 12 15 1.67 MSQ Grid-Tx2-GP06 33 11.5 20 12.2 DYN11 3 12 15 1.67 Royal Office-Tx1-P097 33 11.5 20 12.4 DYN11 3 12 15 1.67 Royal Office-Tx2-P097 33 11.5 20 12.7 DYN11 3 12 15 1.67 Sarooj -Shati Al Qurum-Tx1-P110 33 11.5 20 10.1 DYN11 3 12 15 1.67 Sarooj -Shati Al Qurum-Tx2-P110 33 11.5 20 10.1 DYN11 3 12 15 1.67

MSQ[GP06] - B GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Khuwair 25-Tx1-P053 33 11.5 20 12.0 DYN11 3 12 15 1.67 Al Khuwair 25-Tx2-P053 33 11.5 20 12.1 DYN11 3 12 15 1.67 Al Khuwair School-Tx1-P146 33 11.5 20 12.3 DYN11 3 12 15 1.67 Al Khuwair School-Tx2-P146 33 11.5 20 12.3 DYN11 3 12 15 1.67 Al Khuwair School-Tx3-P146 33 11.5 20 12.3 DYN11 3 12 15 1.67 Digital TV Studio-Tx1-P039 33 11.5 20 12.5 DYN11 3 12 15 1.67 Digital TV Studio-Tx2-P039 33 11.5 20 12.5 DYN11 3 12 15 1.67 MSQ 1-Tx1-P083 33 11.5 20 12.7 DYN11 3 12 15 1.67 MSQ 1-Tx2-P083 33 11.5 20 12.9 DYN11 3 12 15 1.67 ROP -Shati Al Qurum-Tx1-P111 33 11.5 20 10.1 DYN11 3 12 15 1.67 ROP -Shati Al Qurum-Tx2-P111 33 11.5 20 10.2 DYN11 3 12 15 1.67

Qurum[G06] GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Information City 1-Tx1-P037 33 11.5 20 11.8 DYN11 3 12 15 1.67 Information City 1-Tx2-P037 33 11.5 20 12.2 DYN11 3 12 15 1.67 Lulai-Tx1-P095 33 11.5 20 12.6 DYN11 1 10 13 1.67 Lulai-Tx2-P095 33 11.5 20 12.7 DYN11 1 10 13 1.67 MSQ 02-Tx1-P155 33 11.5 20 12.0 DYN11 3 12 15 1.67 MSQ 02-Tx2-P155 33 11.5 20 12.0 DYN11 3 12 15 1.67 MSQ 02-Tx3-P155 33 11.5 20 12.0 DYN11 3 12 15 1.67 Qurum 1-Tx1-P093 33 11.5 16 10.2 DYN11 1 10 13 1.67 Qurum 1-Tx2-P093 33 11.5 16 10.1 DYN11 1 10 13 1.67 Qurum 2-Tx1-P094 33 11.5 20 12.5 DYN11 3 12 15 1.67 Qurum 2-Tx2-P094 33 11.5 20 12.5 DYN11 3 12 15 1.67 Rabiat Al Qurum-Tx1-P096 33 11.5 20 12.5 DYN11 3 12 15 1.67 Rabiat Al Qurum-Tx2-P096 33 11.5 20 12.6 DYN11 3 12 15 1.67

Bousher[GP02] - A GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Khuwair 17/1-Tx1-P050 33 11.5 20 12.0 DYN11 3 12 15 1.67 Al Khuwair 17/1-Tx2-P050 33 11.5 20 11.9 DYN11 3 12 15 1.67 Al Khuwair South-Tx1-P052 33 11.5 20 10.1 DYN11 3 12 15 1.67 Al Khuwair South-Tx2-P052 33 11.5 20 10.1 DYN11 3 12 15 1.67 Al Khuwair South-Tx3-P052 33 11.5 20 10.0 DYN11 3 12 15 1.67 Azaiba South 1B-Tx3-P147 33 11.5 20 12.3 DYN11 3 12 15 1.67 Azaiba South 1B-Tx4-P147 33 11.5 20 12.2 DYN11 3 12 15 1.67 Azaiba South 1B-Tx5-P147 33 11.5 20 12.2 DYN11 3 12 15 1.67 Bousher Grid-Tx5-GP02 33 11.5 20 11.8 DYN11 3 12 15 1.67 Bousher Grid-Tx6-GP02 33 11.5 20 11.9 DYN11 3 12 15 1.67 Royal Hospital-Tx1-P024 33 11.5 20 12.4 DYN11 3 12 15 1.67 Royal Hospital-Tx2-P024 33 11.5 20 12.3 DYN11 3 12 15 1.67 Royal Hospital-Tx3-P024 33 11.5 20 12.2 DYN11 3 12 15 1.67

MEDC Distribution System Capability Statement [2021-2023]-V2.0 136 Bousher[GP02] - B GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Ansab 1-Tx1-P007 33 11.5 20 12.0 DYN11 3 12 15 1.67 Al Ansab 1-Tx2-P007 33 11.5 20 11.9 DYN11 3 12 15 1.67 Azaiba North 1-Tx1-P011 33 11.5 20 11.9 DYN11 3 12 15 1.67 Azaiba North 1-Tx2-P011 33 11.5 20 11.9 DYN11 3 12 15 1.67 Bousher 02-Tx1-P163 33 11.5 20 11.9 DYN11 3 12 15 1.67 Bousher 02-Tx2-P163 33 11.5 20 11.9 DYN11 3 12 15 1.67 Bousher 02-Tx3-P163 33 11.5 20 11.9 DYN11 3 12 15 1.67 Ghubrah South 1-Tx1-P026 33 11.5 20 10.0 DYN11 3 12 15 1.67 Ghubrah South 1-Tx2-P026 33 11.5 20 10.1 DYN11 3 12 15 1.67 Ghubrah South 1-Tx3-P026 33 11.5 20 10.1 DYN11 3 12 15 1.67 Holiday Inn-Tx1-P051 33 11.5 20 12.2 DYN11 3 12 15 1.67 Holiday Inn-Tx2-P051 33 11.5 20 12.4 DYN11 3 12 15 1.67 Holiday Inn-Tx3-P051 33 11.5 20 12.4 DYN11 3 12 15 1.67 Al Muna-Tx1-P084 33 11.5 20 12.2 DYN11 3 12 15 1.67 Al Muna-Tx2-P084 33 11.5 20 12.5 DYN11 3 12 15 1.67 Tilal Al Khuwair-Tx1-P055 33 11.5 20 11.8 DYN11 3 12 15 1.67 Tilal Al Khuwair-Tx2-P055 33 11.5 20 12.2 DYN11 3 12 15 1.67 Tilal Al Khuwair-Tx3-P055 33 11.5 20 12.3 DYN11 3 12 15 1.67

Ghala Heights[G24] GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Mall of Oman-Tx1-P171 33 11.5 20 12.0 DYN11 3 12 15 1.67 Mall of Oman-Tx2-P171 33 11.5 20 12.0 DYN11 3 12 15 1.67 Mall of Oman-Tx3-P171 33 11.5 20 12.1 DYN11 3 12 15 1.67

Ghala[G11] - A GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Ansab 2-Tx1-P008 33 11.5 20 12.5 DYN11 3 12 15 1.67 Al Ansab 2-Tx2-P008 33 11.5 20 12.4 DYN11 3 12 15 1.67 Al Ansab STP-Tx1-P009 33 11.5 20 12.0 DYN11 3 12 15 1.67 Al Ansab STP-Tx2-P009 33 11.5 20 12.0 DYN11 3 12 15 1.67 Ghala 1-Tx1-P015 33 11.5 20 12.5 DYN11 3 12 15 1.67 Ghala 1-Tx2-P015 33 11.5 20 12.5 DYN11 3 12 15 1.67 Ghala 1-Tx3-P015 33 11.5 20 11.9 DYN11 3 12 15 1.67 Ghala 2-Tx1-P156 33 11.5 20 12.0 DYN11 3 12 15 1.67 Ghala 2-Tx2-P156 33 11.5 20 12.0 DYN11 3 12 15 1.67 Ghala 2-Tx3-P156 33 11.5 20 12.0 DYN11 3 12 15 1.67 ROP Hospital-Tx1-P172 33 11.5 20 12.0 DYN11 3 12 15 1.67 ROP Hospital-Tx2-P172 33 11.5 20 12.0 DYN11 3 12 15 1.67 ROP Hospital-Tx3-P172 33 11.5 20 12.0 DYN11 3 12 15 1.67 MOD Al Ansab-Tx1-P167 33 11.5 10 7.6 DYN11 3 12 15 1.67 MOD Al Ansab-Tx2-P167 33 11.5 10 7.5 DYN11 3 12 15 1.67 Oman Exhibition-Tx1-P165 33 11.5 20 12.1 DYN11 3 12 15 1.67 Oman Exhibition-Tx2-P165 33 11.5 20 12.1 DYN11 3 12 15 1.67 Oman Exhibition-Tx3-P165 33 11.5 20 12.0 DYN11 3 12 15 1.67

Airport Heights [G01] - A GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Airport Height 1-Tx1-P001 33 11.5 20 12.3 DYN11 3 12 15 1.67 Airport Height 1-Tx2-P001 33 11.5 20 12.3 DYN11 3 12 15 1.67 Airport Height 2-Tx1-P002 33 11.5 20 12.6 DYN11 3 12 15 1.67 Airport Height 2-Tx2-P002 33 11.5 20 12.8 DYN11 3 12 15 1.67 Airport Height 3-Tx1-P003 33 11.5 20 11.7 DYN11 3 12 15 1.67 Airport Height 3-Tx2-P003 33 11.5 20 12.0 DYN11 3 12 15 1.67 Airport Height 4-Tx1-P004 33 11.5 20 12.1 DYN11 3 12 16 1.67 Airport Height 4-Tx2-P004 33 11.5 20 12.5 DYN11 3 12 16 1.67 Airport Height 5-Tx1-P151 33 11.5 20 12.8 DYN11 3 12 15 1.67 Airport Height 5-Tx2-P151 33 11.5 20 12.8 DYN11 3 12 15 1.67 Azaiba North 3-Tx1-P013 33 11.5 20 12.4 DYN11 3 12 15 1.67 Azaiba North 3-Tx2-P013 33 11.5 20 12.0 DYN11 3 12 15 1.67 Azaiba North 3-Tx3-P013 33 11.5 20 12.0 DYN11 3 12 15 1.67 MOD Technical College-Tx1-P081 33 11.5 20 12.4 DYN11 3 12 15 1.67 MOD Technical College-Tx2-P081 33 11.5 20 12.3 DYN11 3 12 15 1.67 ROP Hospital-Tx-P172 33 11.5 6 6.2 DYN11 2 4 9 2.50

MEDC Distribution System Capability Statement [2021-2023]-V2.0 137 Rusail Industry[G13] - A GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Jifnain 1-Tx-P042 33 11.5 6 6.2 DYN11 1 4 7 2.50 Al Jifnain 2-Tx-P196-OD 33 11.5 6 6.2 DYN11 1 4 7 2.50 Cement Housing-Tx1-P088 33 11 5 7.4 DYN11 1 4 7 2.50 Cement Housing-Tx2-P088 33 11 5 7.4 DYN11 1 4 7 2.50 Rusail Industrial 1-Tx1-P103 33 11 16 9.6 DYN11 3 15 19 1.24 Rusail Industrial 1-Tx2-P103 33 11 16 9.9 DYN11 3 15 19 1.24 Rusail Industrial 2-Tx1-P104 33 11.5 20 12.4 DYN11 3 12 15 1.67 Rusail Industrial 2-Tx2-P104 33 11.5 20 12.4 DYN11 3 12 15 1.67 SQU 1-Tx1-P122 33 11.5 16 10.5 DYN11 3 12 15 1.67 SQU 1-Tx2-P122 33 11.5 16 10.5 DYN11 3 12 15 1.67 SQU 1-Tx3-P122 33 11.5 16 10.5 DYN11 3 12 15 1.67 SQU 2-Tx1-P123 33 11.5 16 10.5 DYN11 3 12 15 1.67 SQU 2-Tx2-P123 33 11.5 16 10.5 DYN11 3 12 15 1.67

Rusail Industry[G13] - B GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] ROP Al Khoudh-Tx1-P161-Pvt 33 11.5 20 12.5 DYN11 3 12 15 1.67 ROP Al Khoudh-Tx2-P161-Pvt 33 11.5 20 12.5 DYN11 3 12 15 1.67 Rusail 08-Tx1-P164 33 11.5 20 12.1 DYN11 3 12 15 1.67 Rusail 08-Tx2-P164 33 11.5 20 12.1 DYN11 3 12 15 1.67 Rusail 08-Tx3-P164 33 11.5 20 12.1 DYN11 3 12 15 1.67 Rusail Ind 4-Tx1-P158 33 11.5 20 12.1 DYN11 3 12 15 1.67 Rusail Ind 4-Tx2-P158 33 11.5 20 12.3 DYN11 3 12 15 1.67 Rusail Ind 4-Tx3-P158 33 11.5 20 12.0 DYN11 3 12 15 1.67 Rusail Industrial 3-Tx1-P105 33 11.5 20 12.0 DYN11 3 12 15 1.67 Rusail Industrial 3-Tx2-P105 33 11.5 20 12.4 DYN11 3 12 15 1.67 Rusail Private Factory-Tx1-P106 33 11.5 20 12.6 DYN11 3 12 15 1.67 Rusail Private Factory-Tx2-P106 33 11.5 20 12.5 DYN11 3 12 15 1.67 Rusail Housing-Tx1-P056 33 11.5 20 12.1 DYN11 3 12 15 1.67 Rusail Housing-Tx2-P056 33 11.5 20 11.9 DYN11 3 12 15 1.67 SQU 03-Tx1-P160-Pvt 33 11.5 20 12.3 DYN11 3 12 15 1.67 SQU 03-Tx2-P160-Pvt 33 11.5 20 11.6 DYN11 3 12 15 1.67 SQU 03-Tx3-P160-Pvt 33 11.5 20 11.6 DYN11 3 12 15 1.67

Misfah[G04] GSS [Zone 2] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Awabi-Tx1-P139 33 11.5 20 11.9 DYN11 3 12 15 1.67 Al Awabi-Tx2-P139 33 11.5 20 12.0 DYN11 3 12 15 1.67 Al Awabi-Tx3-P139 33 11.5 20 12.5 DYN11 3 12 15 1.67 Al Misfah-Tx1-P080 33 11.5 20 12.5 DYN11 3 12 15 1.67 Al Misfah-Tx2-P080 33 11.5 20 12.5 DYN11 3 12 15 1.67 Al Misfah-Tx3-P080 33 11.5 20 12.4 DYN11 3 12 15 1.67 Cement Factory 1-Tx1-P079 33 11 31.5 15.0 YND11 1 9 17 1.01 Cement Factory 1-Tx2-P079 33 11 31.5 15.0 YND11 1 9 17 1.01 Cement Factory 1-Tx3-P079 33 11.5 20 12.5 DYN11 3 12 15 1.67 Cement Factory 1-Tx4-P079 33 11.5 20 12.5 DYN11 3 12 15 1.67 Cement Factory 1-Tx5-P079 33 11.5 20 12.5 DYN11 3 12 15 1.67 Orpic-Tx1-P192 33 6.9 6.3 7.8 DYN11 1 3 5 2.50 Orpic-Tx2-P192 33 6.9 6.3 7.4 DYN11 1 3 5 2.50

Barka[G02] GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Mabelah South-Tx1-P061 33 11.5 20 12.2 DYN11 1 4 13 1.67 Mabelah South-Tx2-P061 33 11.5 20 12.4 DYN11 1 4 13 1.67 Manoma 1-Tx1-P067 33 11.5 20 11.6 DYN11 1 4 13 1.67 Manoma 1-Tx2-P067 33 11.5 20 11.5 DYN11 1 4 13 1.67 Palace Communication-Tx-P033-OD 33 11.5 6 6.0 DYN11 1 3 7 1.03 RGO Halban Camp-Tx-P034-OD 33 11.5 5 7.4 DYN11 1 3 7 1.03

MEDC Distribution System Capability Statement [2021-2023]-V2.0 138 Mabelah[GP04] GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Botanic Garden-Tx1-P016 33 11.5 20 12.2 DYN11 3 12 15 1.67 Botanic Garden-Tx2-P016 33 11.5 20 12.2 DYN11 3 12 15 1.67 Mabelah A-Tx1-P063 33 11.5 20 12.4 DYN11 3 12 15 1.67 Mabelah A-Tx2-P063 33 11.5 20 12.6 DYN11 3 12 15 1.67 Mabelah A-Tx3-P063 33 11.5 20 12.5 DYN11 3 12 15 1.67 Mabelah Grid-Tx1-GP04 33 11.5 20 12.5 DYN11 3 12 15 1.67 Mabelah Grid-Tx2-GP04 33 11.5 20 12.3 DYN11 3 12 15 1.67 Mabelah South PH-7-Tx1-P141 33 11.5 20 11.7 DYN11 3 12 15 1.67 Mabelah South PH-7-Tx2-P141 33 11.5 20 11.7 DYN11 3 12 15 1.67 Mabelah South PH-7-Tx3-P141 33 11.5 20 11.6 DYN11 3 12 15 1.67 Mabelah STP-Tx1-P140 33 11.5 10 7.7 DYN11 3 12 15 1.67 Mabelah STP-Tx2-P140 33 11.5 10 7.8 DYN11 3 12 15 1.67 Old Mabelah-Tx1-P059 33 11.5 20 11.8 DYN11 3 12 15 1.67 Old Mabelah-Tx2-P059 33 11.5 20 11.9 DYN11 3 12 15 1.67 Sur Al Hadid -Tx1-P116 33 11.5 20 12.6 DYN11 3 12 15 1.67 Sur Al Hadid -Tx2-P116 33 11.5 20 12.6 DYN11 3 12 15 1.67

Mabella 2[G12] - A GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Mabelah C-Tx1-P064 33 11.5 20 12.2 DYN11 3 12 15 1.67 Mabelah C-Tx2-P064 33 11.5 20 12.2 DYN11 3 12 15 1.67 Mabelah C-Tx3-P064 33 11.5 20 12.5 DYN11 3 12 15 1.67 Mabelah South PH-4-Tx1-P062 33 11.5 20 12.8 DYN11 3 12 15 1.67 Mabelah South PH-4-Tx2-P062 33 11.5 20 12.5 DYN11 3 12 15 1.67 Mabelah South PH-4-Tx3-P062 33 11.5 20 12.5 DYN11 3 12 15 1.67 Mabelah South PH-8-Tx1-P157 33 11.5 20 12.0 DYN11 3 12 15 1.67 Mabelah South PH-8-Tx2-P157 33 11.5 20 12.0 DYN11 3 12 15 1.67 Mabelah South PH-8-Tx3-P157 33 11.5 20 11.9 DYN11 3 12 15 1.67 Palm Mall-Tx1-P168 33 11.5 20 12.1 DYN11 3 12 15 1.67 Palm Mall-Tx2-P168 33 11.5 20 12.1 DYN11 3 12 15 1.67 Palm Mall-Tx3-P168 33 11.5 20 12.1 DYN11 3 12 15 1.67

Mabella 2[G12] - B GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Mabelah Shabiya-Tx1-P060 33 11.5 20 9.6 DYN11 3 12 15 1.67 Mabelah Shabiya-Tx2-P060 33 11.5 20 9.6 DYN11 3 12 15 1.67 Mabelah Shabiya-Tx3-P060 33 11.5 20 9.6 DYN11 3 12 15 1.67

Seeb[GP08] - A GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Khoud PH-7-Tx1-P154 33 11.5 20 12.3 DYN11 3 12 15 1.67 Al Khoud PH-7-Tx2-P154 33 11.5 20 12.2 DYN11 3 12 15 1.67 Al Khoud PH-7-Tx3-P154 33 11.5 20 12.3 DYN11 3 12 15 1.67 Al Khoud Shabiya-Tx1-P046 33 11.5 20 12.4 DYN11 3 12 15 1.67 Al Khoud Shabiya-Tx2-P046 33 11.5 20 12.2 DYN11 3 12 15 1.67 Wadi Al Aresh-Tx1-P115 33 11.5 20 12.1 DYN11 3 12 15 1.67 Wadi Al Aresh-Tx2-P115 33 11.5 20 12.1 DYN11 3 12 15 1.67 Wadi Al Lawami-Tx1-P117 33 11.5 20 12.5 DYN11 3 12 15 1.67 Wadi Al Lawami-Tx2-P117 33 11.5 20 12.5 DYN11 3 12 15 1.67 Wadi Al Lawami-Tx3-P117 33 11.5 20 12.5 DYN11 3 12 15 1.67 Wadi Bahayis (RGO)-Tx1-P098 33 11.5 20 12.6 DYN11 3 12 15 1.67 Wadi Bahayis (RGO)-Tx2-P098 33 11.5 20 12.7 DYN11 3 12 15 1.67

Seeb[GP08] - B GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Hail South 2-Tx1-P153 33 11.5 20 12.3 DYN11 3 12 15 1.67 Al Hail South 2-Tx2-P153 33 11.5 20 12.3 DYN11 3 12 15 1.67 Al Hail South 2-Tx3-P153 33 11.5 20 12.3 DYN11 3 12 15 1.67 New Al Khoud-Tx1-P047 33 11.5 20 12.4 DYN11 3 12 15 1.67 New Al Khoud-Tx2-P047 33 11.5 20 12.4 DYN11 3 12 15 1.67 Seeb Grid-Tx1-GP08 33 11.5 20 11.7 DYN11 3 12 15 1.67 Seeb Grid-Tx2-GP08 33 11.5 20 11.7 DYN11 3 12 15 1.67 Sultan School-Tx1-P029 33 11.5 20 12.4 DYN11 3 12 15 1.67 Sultan School-Tx2-P029 33 11.5 20 12.6 DYN11 3 12 15 1.67 Seeb05 (Boulevard)-Tx1-P186 33 11.5 20 12.5 DYN11 3 12 15 1.67 Seeb05 (Boulevard)-Tx2-P186 33 11.5 20 12.5 DYN11 3 12 15 1.67 Seeb05 (Boulevard)-Tx3-P186 33 11.5 20 12.5 DYN11 3 12 15 1.67

MEDC Distribution System Capability Statement [2021-2023]-V2.0 139 Mawaleh South[GP05] - A GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Hail North 2-Tx1-P028 33 11.5 20 12.3 DYN11 3 12 15 1.67 Al Hail North 2-Tx2-P028 33 11.5 20 12.2 DYN11 3 12 15 1.67 Al Khoud PH-3-Tx1-P048 33 11.5 20 12.2 DYN11 3 12 15 1.67 Al Khoud PH-3-Tx2-P048 33 11.5 20 12.3 DYN11 3 12 15 1.67 Mawaleh C-Tx1-P072 33 11.5 20 12.7 DYN11 3 12 15 1.67 Mawaleh C-Tx2-P072 33 11.5 20 12.6 DYN11 3 12 15 1.67 Mawaleh South Grid-Tx1-GP05 33 11.5 20 11.1 DYN11 3 12 15 1.67 Mawaleh South Grid-Tx2-GP05 33 11.5 20 11.2 DYN11 3 12 15 1.67 Royal Flight-Tx1-P100 33 11.5 20 12.1 DYN11 3 12 15 1.67 Royal Flight-Tx2-P100 33 11.5 20 12.1 DYN11 3 12 15 1.67

Mawaleh South[GP05] - B GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] AL Hail South 1-Tx1-P030 33 11.5 20 12.7 DYN11 3 12 15 1.67 AL Hail South 1-Tx2-P030 33 11.5 20 12.7 DYN11 3 12 15 1.67 Al Khoud PH-6-Tx1-P049 33 11.5 20 12.5 DYN11 3 12 15 1.67 Al Khoud PH-6-Tx2-P049 33 11.5 20 12.2 DYN11 3 12 15 1.67 Mawaleh A-Tx1-P070 33 11.5 20 11.0 DYN11 3 12 15 1.67 Mawaleh A-Tx2-P070 33 11.5 20 11.2 DYN11 3 12 15 1.67 Mawaleh A-Tx3-P070 33 11.5 20 10.6 DYN11 3 12 15 1.67 Mawaleh B-Tx1-P071 33 11.5 20 11.9 DYN11 3 12 15 1.67 Mawaleh B-Tx2-P071 33 11.5 20 11.2 DYN11 3 12 15 1.67 Mawaleh B-Tx3-P071 33 11.5 20 10.6 DYN11 3 12 15 1.67 Mawalleh South05-Tx1-P148 33 11.5 20 12.1 DYN11 3 12 15 1.67 Mawalleh South05-Tx2-P148 33 11.5 20 12.2 DYN11 3 12 15 1.67 Mawalleh South05-Tx3-P148 33 11.5 20 12.0 DYN11 3 12 15 1.67

Mawaleh North [GP01] GSS [Zone 3] Rated Apparent Secondary Impedance Additional Primary Voltage Power Minimum Tap Nominal Tap Maximum Tap Primary Substation Transformer ID Voltage Voltage Vector Group Voltage per Tap [kV] (ONAF) Position Position Position [kV] [%] [%] [MVA] Al Hail North 1-Tx1-P027 33 11.5 20 11.0 DYN11 3 12 15 1.67 Al Hail North 1-Tx2-P027 33 11.5 20 11.2 DYN11 3 12 15 1.67 City Centre-Tx1-P073 33 11.5 20 12.4 DYN11 3 12 15 1.67 City Centre-Tx2-P073 33 11.5 20 12.4 DYN11 3 12 15 1.67 Mawaleh North-Tx1-P069 33 11.5 20 12.3 DYN11 3 12 15 1.67 Mawaleh North-Tx2-P069 33 11.5 20 12.3 DYN11 3 12 15 1.67 Mawaleh North Grid-Tx1-GP01 33 11.5 20 12.3 DYN11 3 12 15 1.67 Mawaleh North Grid-Tx2-GP01 33 11.5 20 12.3 DYN11 3 12 15 1.67 Mawaleh North Grid-Tx3-GP01 33 11.5 20 12.3 DYN11 3 12 15 1.67

MEDC Distribution System Capability Statement [2021-2023]-V2.0 140