Seward Highway, MP 75-90 Rehabilitation Project - Portage Curve
Project No.: OA3/58105
DESIGN STUDY REPORT
STATE OF ALASKA DEPARTMENT OF TRANSPORTATION AND PUBLIC FACILITIES
PREPARED BY:
Seawolf Engineering, Inc. 2900 Spirit Drive, Room 205 Anchorage, AK 99507
Revised June 2016
STATE OF ALASKA
DEPARTMENT OF TRANSPORTATION AND PUBLIC FACILITIES DESIGN AND ENGINEERING SERVICES – CENTRAL REGION
DESIGN STUDY REPORT
For
Seward Highway, MP 75-90 Rehabilitation Project – Portage Curve
Project No.: OA3/58105
Written by: Zach Cuddihy, Kelsey Copley, Kyle Powell, Grant Warnke
Prepared by:
______Zach Cuddihy Date Student Project Manager
Concur by:
______Randy D. Vanderwood, P.E. Date Project Manager
Concur by:
______James E. Amundsen, P.E. Date Chief, Highway Design
Approved:
______Wolfgang E. Junge, P.E. Date Preconstruction Engineer
NOTICE TO USERS
This report reflects the thinking and design decisions at the time of publication. Changes frequently occur during the evolution of the design process, so persons who may rely on information contained in this document should check with the Alaska Department of Transportation and Public Facilities for the most current design. Contact the Design Project Manager, Randy Vanderwood, P.E. at (907) 269-0586 for this information.
PLANNING CONSISTENCY
This document has been prepared by the Department of Transportation and Public Facilities according to currently acceptable design standards and Federal regulations, and with the input offered by the local government and public. The Department's Planning Section has reviewed and approved this report as being consistent with present community planning.
CERTIFICATION
We hereby certify that this document was prepared in accordance with Section 520.4.1 of the current edition of the Department's Highway Preconstruction Manual and CFR Title 23, Highway Section 771.111(h).
The Department has considered the project's social and economic effects upon the community, its impacts on the environment and its consistency with planning goals and objectives as approved by the local community. All records are on file with Central Region - Design and Engineering Services Division, Highway Design Section, 4111 Aviation Avenue, Anchorage, AK 99502.
Wolfgang E. Junge, P.E. Date Todd Vanhove Date Preconstruction Engineer Chief, Planning
TABLE OF CONTENTS LIST OF FIGURES ...... ii LIST OF APPENDICES ...... ii LIST OF ACRONYMS ...... ii 1.0 PROJECT DESCRIPTION ...... 1 1.1 Project Location and Description ...... 1 1.2 Existing Facilities and Land Use ...... 1 1.3 Purpose and Need ...... 1 2.0 DESIGN STANDARDS AND GUIDELINES ...... 2 3.0 DISCUSSION OF ALTERNATIVES ...... 2 3.1 First Alternative – No-Build ...... 3 3.2 Second Alternative – Re-alignment Only ...... 3 3.3 Third Alternative – Re-alignment and Turning Lanes ...... 3 4.0 PREFERRED ALTERNATIVE ...... 3 5.0 TYPICAL SECTIONS ...... 4 6.0 HORIZONTAL AND VERTICAL ALIGNMENT ...... 4 6.1 Horizontal Alignment ...... 4 6.2 Vertical Alignment ...... 4 7.0 EROSION AND SEDIMENT CONTROL ...... 4 8.0 DRAINAGE ...... 5 8.1 MS4 Permit ...... 5 9.0 SOIL CONDITIONS ...... 6 10.0 ACCESS CONTROL FEATURES ...... 6 11.0 TRAFFIC ANALYSIS ...... 6 12.0 SAFETY IMPROVEMENTS ...... 6 13.0 RIGHT-OF-WAY REQUIREMENTS ...... 6 14.0 PEDESTRIAN AND BICYCLE FACILITIES ...... 7 15.0 UTILITY RELOCATION AND COORDINATION ...... 7 15.1 GCI ...... 7 15.2 Chugach Electric ...... 7 16.0 PRELIMINARY WORK ZONE TRAFFIC CONTROL ...... 7 16.1 Traffic Control Plan (TCP) ...... 8 16.2 Public Information Plan (PIP) ...... 8 16.3 Transportation Operations Plan (TOP) ...... 8 17.0 STRUCTURAL SECTION AND PAVEMENT DESIGN ...... 8 18.0 COST ESTIMATE ...... 9 19.0 ENVIRONMENTAL COMMITMENTS AND CONSIDERATIONS ...... 9 20.0 BRIDGES ...... 10 21.0 EXCEPTIONS TO DESIGN STANDARDS ...... 10 22.0 MAINTENANCE CONSIDERATIONS ...... 10 23.0 ITS FEATURES ...... 10
Seward Hwy MP 75-90 – Portage Curve i Design Study Report
LIST OF FIGURES
Figure 1 Location & Vicinity Map
LIST OF APPENDICES
Appendix Description A Approved Design Criteria and Design Designation B Typical Sections C Material and Geotechnical Recommendations D Traffic Analyses (signal warrants, capacity analysis, roundabout analysis, etc.) and speed studies E Hydraulic and Hydrologic Report F Bridge Preliminary Design
LIST OF ACRONYMS
AADT Annual Average Daily Traffic AASHTO American Association of State Highway and Transportation Officials ACGP Alaska Construction General Permit ADEC Alaska Department of Environmental Conservation APDES Alaska Pollutant Discharge Elimination System ARRC Alaska Railroad Corporation ATM Alaska Traffic Manual BMP Best Management Practice CFR Code of Federal Regulations DOT&PF Alaska Department of Transportation and Public Facilities ESCP Erosion and Sediment Control Plan EPA Environmental Protection Agency FHWA Federal Highway Administration HPCM Alaska Highway Preconstruction Manual HMCP Hazardous Material Control Plan HSIP Highway Safety Improvement Program LOS Level of Service MADT Monthly Average Daily Traffic MOA Municipality of Anchorage MP Milepost MPH Miles Per Hour MUTCD Manual on Uniform Traffic Control Devices NPDES National Pollutant Discharge Elimination System PGDHS A Policy on Geometric Design of Highways and Streets PIP Public Information Plan ROW Right-of-Way SWMM Storm Water Management Model SWPPP Storm Water Pollution Prevention Plan TCP Traffic Control Plan TMP Traffic Management Plan USGS United States Geological Survey
Seward Hwy MP 75-90 – Portage Curve ii Design Study Report
Figure 1 Location and Vicinity Map
Seward Highway MP 75-90 – Portage Curve Design Study Report
1.0 PROJECT DESCRIPTION
1.1 Project Location and Description
The Alaska Department of Transportation and Public Facilities (DOT&PF) in cooperation with the Federal Highway Administration (FHWA) proposes to reconstruct the portion of the Seward Highway between Milepost (MP) 78 and 79. The project is located in Section 5 Township 8N and 9N, Range 3 E., Seward Meridian, USGS Topographical Map Anchorage D-6; Latitude 60.819629° North, Longitude 148.975578° West, within the Municipality of Anchorage (MOA), near the community of Girdwood, Alaska. See Figure 1 for Location and Vicinity Map.
The proposed reconstruction consists of: building a new section of road between MP 78 and 79 and constructing new bridges over Placer River and Portage Creek #1. Work also includes removing existing bridges, adding new striping, and relocating and constructing utilities.
1.2 Existing Facilities and Land Use
The Seward Highway is the sole connection by land for the Kenai Peninsula and Whittier to Anchorage. The roadway between MP 78 and 79 spans two rivers, Placer and Portage Creek No. 1. Each bridge has been retrofitted to increase its seismic capacity, but by current standards the bridges are still not at an adequate capacity for seismic loading. The last major earthquake was the Good Friday Earthquake of 1964 which caused irreparable damage to the bridges that the current ones replaced. An earthquake of that magnitude has the potential to cause similar damage to the existing bridges, which means the Kenai Peninsula and Whittier could be cut off from the road system.
The existing roadway consists of 12-foot lanes and 8-foot shoulders. Additionally, the traffic volumes on the roadway vary drastically depending on the season. Summer months can see more than 10,000 vehicles per day on peak weekends, whereas winter months generally see less than 2,000 vehicles per day. The estimated average daily traffic (ADT) in the design year is approximately 6,000 vehicles per day.
The land surrounding the right-of-way is owned by Chugach National Forest, the Alaska Railroad Corporation, and privately corporations. Additionally, historic cultural sites are located near the Portage-Glacier Road intersection. These sites are remnants of houses and structures that were destroyed in the 1964 earthquake.
1.3 Purpose and Need
The purpose of this project is to improve safety for the traveling public, provide an acceptable Level of Service (LOS) for anticipated traffic with the 20-year design life, and address the structurally deficient bridges at Portage Creek #1 and Placer River. This section of road has a broken-back curve that limits the sight distance, doesn’t meet current AASTHO standards for minimum radius of curvature for the existing speed limit, and creates a higher potential for vehicular crashes. In addition, both bridges located within this project have a bridge deck rating below 4, and the bridges do not meet current structural code requirements for seismic and live-loading capacity.
Between 1999 and 2008, a total of 27 reported vehicle incidents were logged within the one-mile project limit. Crashes in the summer and winter months were mainly due to rear-end collisions and loss of control due to poor road conditions, respectively. In the summer, six out of the nine reported crashes were caused by vehicles that were stopped or turning. The lack of turning lanes, and a reduced stopping
Seward Highway MP 75-90 – Portage Curve 1 Design Study Report
sight distance due to the broken-back curve, increased the potential for crashes of this nature. During winter months, 13 of the 18 crashes were the result of slick road conditions due to ice or snow. The sharp broken-back curve contains a sharp transition between two tangents which decreases the drivers’ ability to maintain their vehicle at a high speed, especially on road conditions that are less than adequate.
The proposed design would add dedicated turn lanes to major intersections, realign the horizontal curve to meet current AASHTO standards for minimum radius of curvature, and add newly designed bridges that meet current LRFD capacities.
2.0 DESIGN STANDARDS AND GUIDELINES
Design standards and guidelines that apply to the Seward Highway MP 75-90 – Portage Curve Project are contained in the following publications:
Standards:
ADA Standards for Accessible Design, United States Department of Justice, September15, 2010 except for the use of Detectable Warnings on Curb Ramps standards as stated in the ADA Standards for Transportation Facilities, United States Department of Transportation (U.S. DOT), 2006. A Policy on Geometric Design of Highways and Streets (PGDHS or “Green Book”), American Association of State Highway and Transportation Officials (AASHTO), 2001. Alaska Highway Preconstruction Manual (HPCM), State of Alaska, Department of Transportation and Public Facilities, 2005 (including all revisions thru August 2014). The Alaska Traffic Manual (ATM), consisting of the Manual on Uniform Traffic Control Devices (MUTCD), 2009 as amended, U.S. Department of Transportation, Federal Highway Administration (FHWA) and the Alaska Traffic Manual Supplement, State of Alaska, Department of Transportation and Public Facilities, 2016. Guide for the Development of Bicycle Facilities, AASHTO, 1999. Guide for the Planning, Design, and Operation of Pedestrian Facilities, AASHTO, 2004. An Informational Guide for Roadway Lighting (IGRL), AASHTO, 1984. Roadside Design Guide, 3rd Edition, AASHTO, 2002.
Intersection Channelization Design Guide, Transportation Research Board, 1985.
Appendix A contains the project Design Criteria and Design Designation.
3.0 DISCUSSION OF ALTERNATIVES
Multiple improvement options were analyzed for the Preliminary Engineering Report (PER) of the Seward Highway between MP 78 and 79. The alternatives are discussed below:
Seward Highway MP 75-90 – Portage Curve 2 Design Study Report
3.1 First Alternative – No-Build
The first alternative is the No-Build alternative. Under this alternative the Seward Highway will continue to follow the broken-back curve. The existing curve contains an approximate radius of 1300 feet, which is inadequate for motorized travel at the current design speed of 60mph. Additionally, the intersections at the Alaska Wildlife Conservation Center and Portage-Glacier Road would remain unchanged; continued rear-end collisions will continue because of this. Lastly, both structurally deficient bridges would remain in-place, unchanged from their current condition. The bridge deck condition will continue to deteriorate with more repeated cycles of traffic passing over them. Based on the above considerations, this alternative was rejected.
3.2 Second Alternative – Re-alignment Only
The second alternative would realign the Seward Highway between MP 78 and 79; impacts to wetlands would be the result of the realignment. Seward Highway would remain at two-lanes without the addition of turning lanes at the Alaska Wildlife Conservation Center and Portage-Glacier Road. Furthermore, with the change to the alignment of the road, new bridges will need to be constructed. Based on the above considerations, this alternative was rejected because it doesn’t solve an important consideration: intersection safety.
3.3 Third Alternative – Re-alignment and Turning Lanes
The third alternative would realign the Seward Highway between MP 78 and 79 and add turning lanes to both intersections. Seward Highway would have an additional northbound lane added between the Portage-Glacier Road and Alaska Wildlife Conservation Center intersections. The byproduct of this alternative would be a larger impact to the surrounding wetlands. This alternative also includes the construction of new bridges, which means that all requirements of the project have been met. Based on the above considerations, this alternative was selected for the project.
4.0 PREFERRED ALTERNATIVE
The preferred alternative was the third alternative because it improves the existing road and solves the issue of safety in this corridor. The addition of turning lanes at both intersections will allow vehicles to safely move out of the flow of traffic which effectively reduces the risk of a rear-end collision. An extended merging lane will be added for vehicles turning northbound onto the Seward Highway from Portage-Glacier Road. This is aimed at allowing large vehicles, namely the design vehicle: WB-109D, to successfully enter the flow of traffic once they’ve reached the posted speed limit. Additionally, the curve will be designed to meet current AASHTO standards for a 60 mph design speed. This will improve the safety of vehicles moving through this corridor, especially during winter months when road conditions are less than optimal.
The existing, structurally deficient bridges would be removed and new bridges would be built along the new alignment. Both bridges would be designed and built meeting current AASHTO LRFD capacities and standards. This option is preferred over rehabilitating the existing bridges because much of the structural system will be unable to be improved in the manner that is required.
This alternative results in a significant impact to the surrounding wetlands. An environmental review and permitting process will need to be conducted with the US Army Core of Engineers.
Seward Highway MP 75-90 – Portage Curve 3 Design Study Report
5.0 TYPICAL SECTIONS
The mainline typical section remains as two 12-foot lanes, one in each direction, with eight-foot shoulders. The typical also includes a foreslope of 4:1 and a backslope of 6:1. The roadway is widened near the Portage-Glacier Road intersection to accommodate a dedicated southbound left turn lane and a dedicated right-hand turn lane for northbound traffic. No depressed medians were added to the intersection, instead, striping will be added.
Rumble strips will be installed on the shoulders of the new mainline.
The typical sections are provided in Appendix B.
6.0 HORIZONTAL AND VERTICAL ALIGNMENT
6.1 Horizontal Alignment
6.1.1 Seward Highway
A simple curve was chosen for the main alignment of the Seward highway to maintain a constant maximum super elevation for the Portage Creek and Placer River bridges. Based on a design speed of 60mph, and max super elevation of 6%, the final radius was chosen at 2150 feet. The resulting super elevation of the curve was calculated at 3.8%, which is also maintained on the Portage Creek and Placer River bridges. The Portage-Glacier Road intersection at the Seward highway is based on a WB-20 semitrailer with compound curves of 440 feet, 65 feet and 440 feet.
6.1.2 Portage Highway
A simple curve was also used for the Portage Glacier highway leading up to the Seward highway intersection. The speed limit before the intersection and curve was reduced to 35 mph to improve safety around the curve and the resulting intersection. Because of a reduced speed, a minimum curvature of 730 feet is required. Thus, the maximum super elevation for this curve is 3.4%.
6.1.3 Wildlife Center:
The new Wildlife Center realignment will be posted at 15mph and contain a curve of 180 feet. A Single unit bus was used for the calculation of the turn lanes at the intersection of the Wildlife Center road and the main Seward Highway alignment. Thus, a simple curve was used for the intersection, which contain radii of 50 feet.
6.2 Vertical Alignment
Per AASHTO, the minimum sag and crest K values for a highway at 60mph will 136 and 1628, respectively. Grades are maintained at 0% along the bridges. The percent grade remains less than 1% throughout the alignment since the elevation is relatively constant along the project length.
7.0 EROSION AND SEDIMENT CONTROL
The project includes temporary and permanent measures to control or prevent erosion and sedimentation during and post project construction. The contractor will prepare a Storm Water Pollution Prevention Plan
Seward Highway MP 75-90 – Portage Curve 4 Design Study Report
(SWPPP) prior to construction that conforms to the DOT&PF Best Management Practices (BMPs) for Erosion and Sediment Control in accordance with the DOT&PF contract specifications and follows the guidelines of the Erosion and Sediment Control Plan (ESCP) provided to the contractor. The contractor will submit the SWPPP for approval by the Construction Project Engineer. The contractor will conduct construction activities in accordance with the approved SWPPP. Temporary BMP’s will remain in place until permanent erosion and sediment control measures are in place and soil is permanently stabilized.
8.0 DRAINAGE
The proposed typical sections and corridor will not have any depressed medians or ditches. However, the proposed corridor will have a 3.8% super-elevation around the proposed curve. Additionally, the entire corridor is on wetlands. Therefore, this local review of the project contains a preliminary drainage study based on the surrounding area and a 100-year storm event. The 100-year storm even must be used since FEMA classifies the project area as a special flood hazard area (SFHA) subject to inundation by the 1% annual chance flood. Additionally, per the Alaska Highway Drainage Manual, Chapter 7 – Appendix A, culverts in designated flood hazard areas require the 100-year storm event.
The preliminary drainage design only considers the drainage basins to the West of the road that will drain East towards the road. See the figure below for more details of the basins. As stated before, these basins are all wetlands, which will cause some storage and stage effects that were not considered in the current 35% design. The area is also almost flat, but was found to slope towards the East. The shallow slope may cause more storage and infiltration effects that were also not considered. However, the resulting storm flow rate will be a valid representation for the area at a local review level.
The culvert sizes were chosen based on this preliminary drainage study as well as being in accordance with the Alaska Highway Drainage Manual. See Appendix E for the entire Hydraulic and Hydrologic Report.
8.1 MS4 Permit
The National Pollutant Discharge Elimination System (NPDES) Program originated under section 402 of the Clean Water Act (CWA, 33 USC §1251), requires that pollutant discharges to surface water be authorized by permit. Together, the Municipality of Anchorage (MOA) and the DOT&PF are authorized to do so through an Authorization to Discharge permit under the National Pollutant Discharge Elimination System. This authorization, Alaska Pollutant Discharge Elimination System (APDES) Permit No. AKS 052558, is effective from August 1, 2015 to July 31, 2020. This permit applies to projects within the MOA.
To comply with the intent of the permit; the project will use, at a minimum, control measures to comply with BMPs and the Storm Water Management Program (SWMP), and follow the Authorization to Discharge under the APDES.
• The project follows the criteria set forth in the DOT&PF’s Alaska Highway Drainage Manual and the MOA’s Drainage Design Guidelines. • The contractor will develop a SWPPP prior to construction that follows the guidelines of the ESCP provided to the contractor. The SWPPP will comply with the APDES permitting program and the Alaska Construction General Permit (ACGP). • The contractor will describe how to minimize and manage to reduce pollution to storm water in the contractor’s SWPPP. • The contractor will comply with all permit conditions with respect to installation and maintenance of control measures, inspections, monitoring (if necessary), corrective actions, reporting and recordkeeping.
Seward Highway MP 75-90 – Portage Curve 5 Design Study Report
• The contractor will address all discharge in the SWPPP. The contractor will prepare a Hazardous Material Control Plan (HMCP). • The maintenance of the pipes, sewers, and other conveyances will remain the responsibility of the State of Alaska. • State of Alaska will maintain outreach and education through the State of Alaska website. Project specific information will be posted at the project site once construction activity begins.
9.0 SOIL CONDITIONS
A geotechnical report is being developed for this project. A field investigation completed by Shannon & Wilson, Inc., indicated this project contains a large degree of silt deposits with a ground water table consistently at surface level. The silt deposits near the surface are classified as “loose to very loose” due to the blow counts from the test holes being less than 5. A large amount of fill will be placed on top of conditions such as these, and a varying degree of settlement is expected.
Material and geotechnical recommendations can be found in Appendix C.
10.0 ACCESS CONTROL FEATURES
New access to the highway will be managed through driveway permits and future project evaluation. A new access point to the Alaska Wildlife Conservation Center is included with the design to allow continued access to the facility during construction.
11.0 TRAFFIC ANALYSIS
A traffic analysis is being prepared for this project. With the addition of turning lanes at both intersections within the project, turning movements were analyzed to determine the percentage of vehicles that were turning. Utilizing projected ADT values and the percentage of turning vehicles, storage lengths for the required intersections were computed. The addition of these turn lanes is in response to the percentage of summer crashes related to rear-end crashes at or approaching an intersection.
Traffic analysis can be found in Appendix D.
12.0 SAFETY IMPROVEMENTS
The new alignment will provide a geometric improvement, namely horizontal, which will allow traffic to safely maintain the posted speed limit of 55 mph. The realignment of the curve and the addition of turning lanes at both intersections is aimed at reducing the current crash rates within the project limits. The addition of turning lanes is in response to many crashes during summer months (May thru September) that have resulted in a rear-end collision. Furthermore, a larger radius of curvature, and a proper superelevation, will provide traffic to safely navigate the corridor during winter months (October thru April) when the road conditions are below optimal.
13.0 RIGHT-OF-WAY REQUIREMENTS
The Seward Highway – Portage Curve Project will require the acquisition of additional right-of-way (ROW).
Seward Highway MP 75-90 – Portage Curve 6 Design Study Report
Beginning at station 26+00 the preferred alignment diverts from the existing alignment. The preferred alignment crosses into Chugach State owned land which will require a full acquisition. Any privately- owned land along the preferred alignment will need to be bought out.
The Portage-Glacier Road will be extended to meet the preferred alignment, and this will require no additional ROW. The extension is built of the road will extend into land currently owned by the Alaska DOT&PF.
14.0 PEDESTRIAN AND BICYCLE FACILITIES
There are no separated pedestrian and bicycle accommodations within the project limits. Pedestrians and bicycles may use the new shoulders of the highway. Future designs should accommodate a pedestrian underpass on both the Portage Creek #1 and Placer River bridges.
15.0 UTILITY RELOCATION AND COORDINATION
Utility companies with facilities in the project limits include General Communications Inc. (GCI) and Chugach Electric. Utilities will require relocation and agreements will need to be developed, at select locations throughout the project, to address the following conflicts:
15.1 GCI
There will be several conflicts with GCI’s fiber optic cables in the area which includes issues during reconstruction of the Alaska Wildlife Conservation Center Road from Sta. 0+50 to 1+00. Additionally, there will be more conflicts along the realignment of the Seward Highway from Sta. 29+00 to 31+00 and Sta. 38+00 to 42+00. GCI also owns an underground telephone line in the area which will have a conflict from Sta. 31+00 to 32+00, and a telephone pole will need relocation at Sta. 32+00.
15.2 Chugach Electric
Overhead electricity lines will need to be relocated due to the realignment of the Seward Highway at Sta. 35+50 and 56+00, as well as from Sta. 63+00 to 64+00.
16.0 PRELIMINARY WORK ZONE TRAFFIC CONTROL
The HPCM, Section 1400.2 sets forth the criteria for determining if a project is ‘significant’ for purposes of determining the level of effort required in developing a Traffic Management Plan (TMP). Significant projects fall into either a Category 1 or Category 2 classification.
Category 1:
Project occupies a location for more than three days with either intermittent or continuous lane closures on Interstate Highways within a Transportation Management Area – Criteria Not Met
Category 2:
Project occupies a location for more than three days with either intermittent or continuous lane closures on arterials, expressway, or freeways with Annual Average Daily Traffic (AADT) of 30,000 or more – Criteria Not Met
Seward Highway MP 75-90 – Portage Curve 7 Design Study Report
Project fully closes an arterial for more than one hour at a time with no practical alternate route – Criteria Not Met
Any project that, alone or in combination with other concurrent projects nearby, is anticipated to require greater than normal attention to traffic control to eliminate sustained work zone impacts greater than what would be considered acceptable – Criteria Not Met
The HPCM, Section 1400.2 sets forth the criteria for determining if a project is to be classified as a “Significant Project” for purposes of determining the level of effort required in developing a TMP. Though the project is classified as a Rural Other Principal Arterial, the project is not located within the Anchorage urban area, roadway AADTs are below 30,000 vpd, and in the event of a full closure a practical alternate route is not available. Therefore, the project is not considered a “Significant Project.”
16.1 Traffic Control Plan (TCP)
The contractor will develop a TCP during construction, to safely guide and protect the traveling public in work zones, in accordance with the ATM and the project specifications. The plan will be assessed and approved by the Construction Project Engineer and the Traffic Control Engineer. The contractor is responsible for providing advanced notice to the public, including local businesses, residents, and road travelers, of construction activities that could cause delays, detours, or affect access to adjacent properties.
16.2 Public Information Plan (PIP)
A PIP will be developed prior to beginning construction that will specify the ways and means that the contractor will use to inform the public of upcoming activities that will impact local stakeholders, the roadway users and public entities. The PIP will contain measures to inform stakeholders of project scope, expected work zone impacts, closure details, and recommended action to avoid impacts and changing conditions during construction. Measures to disseminate information include:
Contractor’s Worksite Traffic Supervisor Department’s Construction section thru the Department’s 511 system Department’s Navigator website Television, Radio, and/or newspaper Other location-specific communication tools
The traveling public should not be caught unaware by any closures, detours, delays, night work, or any potentially disruptive activity.
16.3 Transportation Operations Plan (TOP)
The Department will coordinate with relevant public agencies and event organizers, and incorporate means and methods for minimizing traffic impacts with the contractor not covered by the TCP or the PIP within the project plans.
17.0 STRUCTURAL SECTION AND PAVEMENT DESIGN
Pavement recommendations are being developed; however, based on other recent projects in the area, preliminary recommended sections are:
Seward Highway MP 75-90 – Portage Curve 8 Design Study Report
Seward Highway Typical: 2” HMA Type II, PG 58-34 3” ATB, PG 58-34 2” D-1 36” Selected Material, Type A
Portage-Glacier Road Typical: 2” HMA Type II, PG 58-34 3” ATB, PG 58-34 2” D-1 36” Selected Material, Type A
Alaska Wildlife Conservation Center Entrance Typical: Match existing
Geotechnical recommendations and potential material source information are provided in Appendix C.
18.0 COST ESTIMATE
The project cost estimate was based on the calculation of expected pay items related to the roadway and bridge. Preliminary Engineering was taken as 8% of the total budget and both Right-of-Way and Utility Relocation was taken as 5%.
The project cost estimate is as follows:
Preliminary Engineering $ 2,400,000
Right-of-Way $ 1,500,000
Utility Relocation $ 1,500,000
Construction $ 30,000,000
Total $ 35,400,000
19.0 ENVIRONMENTAL COMMITMENTS AND CONSIDERATIONS
At this point in the design process, the Seward Highway Milepost 78-79 Rehabilitation Project is under local review for the purposes of this design study report. Therefore, the environmental impact considerations are rudimentary in nature. The preliminary factors being considered are the required environmental permits that will potentially need to be applied for and the immediate impact on the surrounding environment.
Given the surrounding wetland limits, it was determined that the project will be located entirely on wetlands. Consequently, the current local review design study report presents an estimated area of environmental impact from the project on the wetlands. This area was found to be about 10 acres of wetland impacts. Future considerations must be based on a more in depth analysis than this.
Additionally, it was also found that the following permits, per the Alaska Highway Drainage Manual, will likely be required for the project:
Seward Highway MP 75-90 – Portage Curve 9 Design Study Report
Section 404 Permit – (U.S. Army Corps of Engineers) Section 10 Permit – (U.S. Army Corps of Engineers) Land Use Permit – (Alaska Department of Natural Resources) Temporary Water Use Permit – (Alaska Department of Natural Resources) Fish Habitat Permit (Title 41) – (Alaska Department of Natural Resources) National Pollution Discharge Elimination System Permit (NPDES) – (U.S. Environmental Protection Agency) 401 Certificate of Reasonable Assurance – (AK Dept. of Environmental Conservation) Section 106 Review – (AK Dept. of Natural Resources, State Historic Preservation Office) Endangered Species Act of 1973, Section 7 Consultation – (U.S. Fish and Wildlife Service or National Marine Fisheries Service) Marine Mammal Protection Act Consultation - (National Marine Fisheries Service) Section 9 Permit for Bridges Over Navigable Waters – (U.S. Coast Guard)
The contractor is responsible for obtaining all necessary permits and clearances for materials sites, disposal sites, and staging areas unless DOT&PF has obtained all necessary permits.
The contractor will be required to prepare and implement a SWPPP that conforms to the DOT&PF BMPs for erosion and sediment control in accordance with the DOT&PF contract specifications. Appropriate erosion and siltation controls will be used and maintained in optimal condition during construction and all other exposed soils/fills will be permanently stabilized.
The contractor will be required to dispose of solid waste at an ADEC approved landfill. An ESCP will be made available to the contractor to use as guidance in developing the SWPPP.
20.0 BRIDGES
Two significant bridges will be constructed to span Portage Creek #1 and Placer River. The Portage Creek #1 bridge will be approximately 350 feet in length and Placer River will be approximately 650 feet in length. Both bridge elevations must accommodate the 100-year flood event for the respective rivers they span. More information is provided in Appendix F.
21.0 EXCEPTIONS TO DESIGN STANDARDS
There are no exceptions to design standards for this project.
22.0 MAINTENANCE CONSIDERATIONS
Maintenance will remain the responsibility of the State of Alaska and the local DOT&PF Maintenance and Operations Station located in Girdwood, AK.
23.0 ITS FEATURES
There are no ITS features incorporated into the proposed project.
Seward Highway MP 75-90 – Portage Curve 10 Design Study Report
Seward Highway MP 75-90 – Portage Curve Design Study Report
APPENDIX A
Approved Design Criteria And Design Designation
Seward Highway MP 75-90 – Portage Curve Design Study Report
Project Design Criteria Project Name: Seward Highway MP 75-90 - Portage Curve New Construction/Reconstruction* 3R PM Other: Project Number: NHS Non NHS Functional Classification: Rural Interstate Source/Comments Design Year: 2037 Present ADT: 4224 Design Year ADT: 6037 Mid Design Period ADT: DHV: 23.6 Directional Split: 48/52 Percent Trucks: 13.9 Equivalent Axle Loading: Pavement Design Year: 2037 Design Vehicle: WB-109D Terrain: Flate Number of Roadways: 1 Design Speed: 60 mph Width of Traveled Way: 24 feet Width of Shoulders: Outside: 8 feet Inside: 8 feet Cross Slope: 2% Superelevation Rate: 6% Max Minimum Radius of Curvature: 1838 feet Minimum K-Value for Vertical Curves: Sag:136 Crest: 1628 Maximum Allowable Grade: 6% Minimum Allowable Grade: 0.50% Stopping Sight Distance: 570 feet Lateral Offset to Obstruction: N/A Vertical Clearance: 16 feet Bridge Width: 40 feet Bridge Structural Capacity: HS-25 Passing Sight Distance: 2135 feet Surface Treatment: T/W: HMA Shoulders: HMA Side Slope Ratios: Foreslopes:4(H):1(V) Backslopes: 6(H):1(V) Degree of Access Control: Median Treatment: N/A Illumination: N/A Curb Usage and Type: N/A Bicycle Provisions: N/A Pedestrian Provisions: N/A Misc. Criteria:
Proposed - Designer/Consultant: Date: Endorsed - Engineering Manager: Date: Approved - Preconstruction Engineer: Date:
Shaded criteria are commonly referred to as the FHWA 13 controlling criteria . *For NHS routes only, these criteria must meet the minimums established in the Green Book (AASHTO A Policy on Geometric Design of Highway and Streets ). For all other routes, these criteria must meet the minimums established in the Alaska Highway Preconstruction Manual . Otherwise a Design Exception must be approved.
Design Criterion marked with a "#" do not need to meet minimums and have a Design Exception(s) and/or Design Waiver(s) approved. See the approved DSR for Design Exception/Design Waiver approval(s) and approved design criteria values.
Seward Highway MP 75-90 – Portage Curve Design Study Report
Seward Highway MP 75-90 – Portage Curve Design Study Report
APPENDIX B
Typical Sections
Seward Highway MP 75-90 – Portage Curve Design Study Report
Seward Highway MP 75-90 – Portage Curve Design Study Report
APPENDIX C
Material and Geotechnical Recommendations
Seward Highway MP 75-90 – Portage Curve Design Study Report
Material Recommendations Report
Seward Highway Milepost 75-90 Rehabilitation Project Portage Curve Project No.: OA3/58105 Group D
Prepared For: State of Alaska Department of Transportation and Public Facilities 4111 Aviation Avenue Anchorage, Alaska 99519
Prepared By: Seawolf Engineering 2900 Spirit Drive, Room 205 Anchorage, AK 99508
Author:
Zach Cuddihy
Seward Highway MP 75-90 – Portage Curve ii Design Study Report
Table of Contents 1.0 Introduction ...... 1 Project Description ...... 1 2.0 Climate ...... 1 3.0 Recommendations ...... 1 3.1 Earthwork ...... 2 3.2 Structural Pavement Section ...... 2 3.3 Material Sources ...... 2 4.0 Estimated Settlement ...... 2
Seward Highway MP 75-90 – Portage Curve i Design Study Report
Figures
Figure 1: Average Temperatures….………………………..…………….……………………….1
Tables
Table 1: Estimated Primary Settlement….………………………..…………….……………………3
Seward Highway MP 75-90 – Portage Curve ii Design Study Report
1.0 Introduction
This report presents the preliminary results of an on-going geotechnical investigation performed for the Seward Highway MP 75-90: Portage Curve project. In general, the purpose of this investigation was to evaluate the existing subsurface conditions and to provide geotechnical recommendations for the further design of this project. Recommendations are based off the boring test reports gathered during a field exploration done by Shannon and Wilson, Inc. in November and December of 2014, and in May of 2015.
1.1 Project Description
The preferred alignment for the Portage Curve project diverts from the existing alignment and into land classified as wetlands. The geotechnical sight visit that was completed indicated that more than 60% of the soil along the preferred alignment contains silt or silty sand. Additionally, groundwater is routinely found near the surface.
2.0 Climate
Climate data was obtained from Alyeska Resort in Girdwood, AK. Average temperatures during winter months (October thru April) were consistently near or below 32 degrees. These ambient temperatures coupled with moisture content, soil type and ground water directly impact the depth of freeze.
Figure 1. Average Temperatures
3.0 Recommendations
Based on the geotechnical site visit and soil test reports provides by Shannon and Wilson, Inc., specific recommendations regarding earthwork and structural pavement sections are provided below.
3.1 Earthwork
Borings along the proposed alignment indicate the existing soils near the surface are mainly comprised of silts with depths in excess of approximately 15 feet. Silt is classified as a frost susceptible soil due to the high amount of fines (P200s). In addition, the ground water table is consistently within five feet of the surface, if not at surface level. Lastly, from the boring logs it was indicated that silt near the surface was classified as “loose to very loose” due to the low blow count values (<5). As such, long term settlement and consistent freeze-thaw cycles pose a risk to the structural pavement section.
Seward Highway MP 75-90 – Portage Curve 1 Design Study Report
It is recommended that the silt beneath the preferred alignment be excavated and filled with Type C material. This is discussed in more depth in the following section.
3.2 Structural Pavement Section
The structural pavement sections were based on projects in the vicinity. These are preliminary estimates to use for design purposes, but a proper materials testing
Seward Highway MP 78-79:
2” Type II HMA, PG 58-34 STE-1 Asphalt for Tack Coat 3” ATB, PG 58-34 2” D-1 36” Selected Material, Type A
Portage-Glacier Road:
2” Type II HMA, PG 58-34 STE-1 Asphalt for Tack Coat 3” ATB, PG 58-34 2” D-1 36” Selected Material, Type A
Alaska Wildlife Conservation Center Road:
Match existing
3.3 Material Sources
No material source investigations were performed for this project as all materials are expected to come from contractor supplied sources.
4.0 Estimated Settlement
Utilizing data from the boring test reports, approximate settlement values were calculated using elementary consolidation analysis. This was aimed at determining if the existing soil was suitable for a roadway embankment to be constructed without excavation of any soil. The assumption in the calculations is that fill would be placed on the existing ground to bring it up to the required elevation for the structural pavement section to be built; this was denoted as the “surcharge settlement”.
Estimated settlement analysis was done on borings TH14-034, TH15-040, and TH14-044. The boring test reports can be found in Appendix A.
Seward Highway MP 75-90 – Portage Curve 2 Design Study Report
Table 1. Estimated Primary Settlement Test Hole # TH14-034
Sample Soil Sc,total # Type Sc,theoretical (in) Sc,surcharge (in) Sc,pavement (in) (in) % Surcharge 1 ML 2.094 2.571 0.137 2.708 95% 2 ML 1.119 1.484 0.131 1.614 92% 3 ML 0.944 1.305 0.143 1.447 90% 4 ML 0.531 0.753 0.091 0.844 89% 5 SP 0.292 0.423 0.053 0.476 89% 6 SP 0.285 0.421 0.063 0.483 87% Total: 7.573 92% Test Hole # TH15-040
Sample Soil Sc,total # Type Sc,theoretical (in) Sc,surcharge (in) Sc,pavement (in) (in) % Surcharge 1 ML 2.784 3.549 0.273 3.822 93% 2 ML 1.192 1.642 0.203 1.845 89% 3 ML 1.287 1.856 0.266 2.122 87% 4 ML 0.218 0.322 0.055 0.377 86% Total: 8.165 90% Test Hole # TH14-044
Sample Soil Sc,total # Type Sc,theoretical (in) Sc,surcharge (in) Sc,pavement (in) (in) % Surcharge 1 ML 2.120 2.596 0.156 2.753 94% 2 ML 1.142 1.509 0.143 1.652 91% 3 ML 1.252 1.736 0.206 1.941 89% 4 ML 0.296 0.419 0.030 0.449 93% 5 SP 0.259 0.372 0.046 0.418 89% 6 SP 0.473 0.693 0.075 0.768 90% Total: 7.981 93%
The unit weights of the pavement structure were assumed as followed:
HMA = 145 lbs/ft3 ATB = 145 lbs/ft3 D-1 = 125 lbs/ft3 Select Type A = 125 lbs/ft3 Fill (Surcharge Soil) = 125 lbs/ft3
When the pavement structure is constructed, the total load placed onto the existing ground would be ~850 lbs/ft3. If this pavement structure is built without placing the additional fill then the theoretical values in column three would be the expected, immediate settlement. The long-term settlement from this loading would be of a much higher concern because the silty soils have a moisture content in excess of 30%. The amount of time for this water to escape the soil could be years because silt has a very low hydraulic conductivity.
Seward Highway MP 75-90 – Portage Curve 3 Design Study Report
Due to the effects of long term settlement, leaving the silt in-place could cause excessive settlement that is not accounted for in the above tables. As such, it is recommended to excavate the silt where it is possible. The excavation should be backfilled with Type C material to bring it back to existing surface level before placing the embankment and pavement structure.
Seward Highway MP 75-90 – Portage Curve 4 Design Study Report
Appendix A
Boring Test Reports
Seward Highway MP 75-90 – Portage Curve 5 Design Study Report
Seward Highway MP 75-90 – Portage Curve 6 Design Study Report
Seward Highway MP 75-90 – Portage Curve 7 Design Study Report
Seward Highway MP 75-90 – Portage Curve 8 Design Study Report
Seward Highway MP 75-90 – Portage Curve 9 Design Study Report
Seward Highway MP 75-90 – Portage Curve Design Study Report
APPENDIX D
Traffic Analysis
The information in this report is compiled for highway safety planning purposes. Federal law prohibits its discovery or admissibility in litigation against state, tribal or local government that involves a location or locations mentioned in the collision data. 23 U.S.C. § 409; 23 U.S.C. § 148(g); Walden v. DOT, 27 P.3d 297, 304-305 (Alaska 2001)
Seward Highway MP 75-90 – Portage Curve Design Study Report
Traffic Analysis Report
Seward Highway Milepost 75-90 Rehabilitation Project Portage Curve Project No.: OA3/58105 Group D
Prepared For: State of Alaska Department of Transportation and Public Facilities 4111 Aviation Avenue Anchorage, Alaska 99519
Prepared By: Seawolf Engineering 2900 Spirit Drive, Room 205 Anchorage, AK 99508
Author:
Zach Cuddihy
Seward Highway MP 75-90 – Portage Curve Design Study Report
Table of Contents
1.0 Introduction ...... 1 1.1 OBJECTIVE ...... 1 2.0 Existing Conditions ...... 1 2.1 DESIGN YEAR CONDITIONS ...... 2 3.0 Crash Data Analysis ...... 2 3.1 INTERSECTION CRASH HISTORY AND ANALYSIS ...... 3 3.2 SEGMENT CRASH HISTORY AND ANALYSIS ...... 3 3.3 CRASH DATA CONCLUSIONS ...... 6 4.0 Intersection Analysis ...... 6 4.1 SUMMARY OF TURNING MOVEMENTS ...... 6 4.2 STORAGE LENGTH FOR TURN LANES ...... 7
Seward Highway MP 75-90 – Portage Curve Design Study Report
Figures
Figure 1: Traffic Data…………………………………………………..…………………………1 Figure 2: Intersection Crash Data Collison Type……………………..……………..……………2 Figure 3: Intersection Crash Data Severity....…………..…………………………………………3 Figure 4: Segment Crash Data Collision Type……………………………………………………4 Figure 5: Segment Crash Data Severity...…………………………………………………………5 Figure 6: Segment Road Conditions: Winter Crashes..…………………………………………5
Tables
Table 1: Summary of Turning Movements at Wildlife Center………..…………………..………6 Table 2: Peak Hourly Turning Volumes at Wildlife Center…………..…………………..………7 Table 3: Percentage of Vehicles Turnings at Wildlife Center.………..…………………..………7 Table 4: Calculation of 95th Percentile Queue……………….………..…………………..………8
Appendices
Appendix A………….………..………………...……..……...…….……Turning Movements Plot
Seward Highway MP 75-90 – Portage Curve ii Design Study Report
1.0 Introduction
The Seward Highway serves to connect the Anchorage Bowl to the Kenai Peninsula. Despite being an interstate where the speed limit can range from 55 mph to 65 mph, there are still several intersections along the highway where no turn lanes are provided. There are two of these types of intersections between MP 78 and 79 along the Portage Curve. Additionally, traffic flow varies with the seasons which adds additional demand on the Seward Highway during peak summer weekends.
1.1 Objective
This report documents and summarizes the traffic analysis done for the Portage Curve between Mileposts (MP) 78 and 79. Objectives of this analysis are:
Project existing traffic data to the design year of 2037 Evaluate crash history information to determine possible causes of vehicular crashes Analyze existing intersection conditions and project possibilities for future design
Throughout this report for the Portage Curve project, any analyses done will conform to DOT&PF HPM and AASHTO Green Book standards.
2.0 Existing Conditions
Existing traffic volumes were obtained from a DOT&PF study conducted in 2013; this data can be seen in Figure 1. The average daily traffic (ADT) for 2013 was 3,934 with a compound growth rate of 1.08% per year. However, summer and winter months vary drastically in terms of traffic volumes. During peak weeks in the summer the ADT can exceed 10,000.
Figure 1. Traffic Data
Seward Highway MP 75-90 – Portage Curve 1 Design Study Report
2.1 Design Year Conditions
A design year of 2037 is being used for the purpose of this report. Projecting the ADT to that year yields a value of approximately 6,000. The Design Hourly Volume (DHV) and Peak Hour Factor were assumed to stay constant through the design year for the purposes of this report.
3.0 Crash Data Analysis
Crash data information was obtained from the Alaska DOT&PF for the timeframe of 1999 to 2008. The information is split into two distinct types, intersection and segment crashes. Crashes that are identified as intersection crashes had the follow criteria: vehicles approaching an intersection, vehicles slowing at an approach to an intersection and vehicles in the act of a turning movement. Crashes that are classified as a segment crash is identified as a crash not in the vicinity of an intersection.
3.1 Intersection Crash History and Analysis
This analysis was used to determine the most common crash types, the crash rate for the Portage- Glacier Road intersection, and to compare the calculated crash rate with DOT&PF average crash rates. The only classified intersection crashes for this project location were crashes that occurred at the Portage-Glacier Road intersection. A total of 10 reported crashes were logged for this intersection, and no fatalities were recorded. A summary of the crash history and crash severity can be seen in Figure 1 and Figure 2.
Intersection Collision Type Ditch 10% Rear-End 20%
Angle 10%
Object Animal 50% 10%
Figure 2. Intersection Crash Data Collision Type
Seward Highway MP 75-90 – Portage Curve 2 Design Study Report
Intersection Collision Severity
Possible Injury 20%
Property Damage Only 80%
Figure 3. Intersection Collision Data Severity
Intersection crash rates are expressed as crashes per million entering vehicles (MEV). To calculate intersection crash rates, the following equation was used: