Proceedings for 162nd Meeting of SEAC held on 6th April 2016 at 12.00 noon

Members Present in the meeting:

Shri. N. Naganna - Chairman Prof. D.L. Manjunath - Member Dr. S. Manjappa - Member Dr. B. Manoj Kumar - Member Dr. B.S. Jayaprakash - Member Shri. B. Chikkappaiah - Member Dr. N. Krishnamurthy - Member Dr. K.C. Jayaramu - Member Dr. K.B. Umesh - Member Shri. Vijaya Kumar - Secretary

The Chairman, SEAC, welcomed the members of the Committee and others present. The following proposals listed in the agenda were appraised in accordance of the provision of EIA Notification 2006. The observation and decision of the Committee are recorded under each of the agenda items.

Some of the consultants have produced the copy of the stay order in which there is a list of 13 consultants who have obtained stay (W.P. No. 16250-16251/2016) order from Hon’ble High Court of Karnataka to the committee. The committee had discussed regarding the individual stay obtained by Environmental Consultants against the Gazette Notification dated 03.03.2016 issued by MoEF and CC, New Delhi and decided to allow the consultants for making the presentation by the consultants who have obtained stay order from the court and it is hereby brought to the notice of the Authority.

Confirmation of the proceedings of 161st SEAC meeting held on 28th and 29th March 2016.

The State Expert Appraisal Committee, Karnataka perused the proceedings of 161st SEAC meeting held on 28th and 29th March 2016 and confirmed the same.

Sand proposals of District Sand Monitoring Committee, Dakshina District:

162.1 Removal of Sand from Sand Bar - SB - N6 of Nethravathi River Bed, Arkula Village, Mangaluru Taluk, Dakshina Kannada (4 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 111 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-N6, Nethravathi River Bed of Arkula Village, Mangaluru Taluk, Dakshina Kannada District in a area of 4.0 Ha. Representative of the proponent and EIA coordinator from M/s. Metamorphosis Project Consultants Pvt Ltd, Bangalore attended the meeting of SEAC and presented the proposal.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action. 162.2 Removal of Sand from Sand Bar - SB - N2 of Nethravathi River Bed, Jappinamogru Village, Mangaluru Taluk, Dakshina Kannada (19 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 112 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-N2, Nethravathi River Bed of Jappinamogru Village, Mangaluru Taluk, Dakshina Kannada District in a area of 19.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 50%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. The proposed reduction of length of the sand bar by 50% should be accommodated towards the structure side ie. the bridge. 2. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2

3. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 4. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.3 Removal of Sand from Sand Bar - SB - G5 of , Kunjathbailu Village, Mangaluru Taluk, Dakshina Kannada of District Sand Monitoring Committee, Dakshina Kannada District. (5 Ha) (SEIAA 113 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G5, Gurupura River Bed of Kunjathbailu Village, Mangaluru Taluk, Dakshina Kannada District in a area of 5.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.4 Removal of Sand from Sand Bar - SB - G6 of Gurupura River Bed, Kenjar-1 Village, Mangaluru Taluk, Dakshina Kannada (5 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 114 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G6, Gurupura River Bed of Kenjar-1 Village, Mangaluru Taluk, Dakshina Kannada District in a area of 5.0 Ha.

3

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.5 Removal of Sand from Sand Bar - SB - N5 of Nethravathi River Bed, Herekala Village, Mangaluru Taluk, Dakshina Kannada (6.24 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 115 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-N5, Nethravathi River Bed of Herekala Village, Mangaluru Taluk, Dakshina Kannada District in a area of 6.24 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action. 4

162.6 Removal of Sand from Sand Bar - SB - N1 of Nethravathi River Bed, Mangalorethota Village, Mangaluru Taluk, Dakshina Kannada (8 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 116 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-N1, Nethravathi River Bed of Mangalorethota Village, Mangaluru Taluk, Dakshina Kannada District in a area of 8.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.7 Removal of Sand from Sand Bar - SB - G11 of Gurupura River Bed, Muluru Village, Mangaluru Taluk, Dakshina Kannada (3 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 117 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G11, Gurupura River Bed of Muluru Village, Mangaluru Taluk, Dakshina Kannada District in a area of 3.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

5

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.8 Removal of Sand from Sand Bar - SB - N11 of Nethravathi River Bed, Kannuru-1 Village, Mangaluru Taluk, Dakshina Kannada (8 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 118 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-N3, Nethravathi River Bed of Kannuru-1 Village, Mangaluru Taluk, Dakshina Kannada District in a area of 8.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.9 Removal of Sand from Sand Bar - SB - G8 of Gurupua River Bed, Mudushedde-1 Village, Mangaluru Taluk, Dakshina Kannada (4.80 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 119 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of 6

sand from sand bar project at SB-G8, Gurupura River Bed of Mudushedde-1 Village, Mangaluru Taluk, Dakshina Kannada District in a area of 4.80 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.10 Removal of Sand from Sand Bar - SB - G9 of Gurupua River Bed, Mudushedde-2 Village, Mangaluru Taluk, Dakshina Kannada (3 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 120 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G9, Gurupura River Bed of Mudushedde-2 Village, Mangaluru Taluk, Dakshina Kannada District in a area of 3.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 7

3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.11 Removal of Sand from Sand Bar - SB - G2 of Gurupua River Bed, Bangrakuluru Village, Mangaluru Taluk, Dakshina Kannada (9 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 121 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G2, Gurupura River Bed of Bangrakuluru Village, Mangaluru Taluk, Dakshina Kannada District in a area of 9.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.12 Removal of Sand from Sand Bar - SB - G1 of Gurupua River Bed, Boluru Village, Mangaluru Taluk, Dakshina Kannada (9.60 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 122 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G1, Gurupura River Bed of Boluru Village, Mangaluru Taluk, Dakshina Kannada District in a area of 9.60 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said 8

proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.13 Removal of Sand from Sand Bar - SB - NP1 of Nandini River Bed, Sasihthlu Village, Mangaluru Taluk, Dakshina Kannada (2 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 123 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-NP1, Nandini River Bed of Sasihithlu-Pavanje Village, Mangaluru Taluk, Dakshina Kannada District in a area of 2.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 5. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

9

162.14 Removal of Sand from Sand Bar - SB - G7 of Gurupura River Bed, Kenjar-2 Village, Mangaluru Taluk, Dakshina Kannada (2 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 124 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G7, Gurupura River Bed of Kenjar-2 Village, Mangaluru Taluk, Dakshina Kannada District in a area of 2.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has decided to recommend the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be cut by 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.15 Removal of Sand from Sand Bar - SB - G10 of Gurupura River Bed, Mudushedde- Muluru Village, Mangaluru Taluk, Dakshina Kannada of District Sand Monitoring Committee, Dakshina Kannada District. (3.20 Ha) (SEIAA 125 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G10, Gurupura River Bed of Mudushedde-Muluru Village, Mangaluru Taluk, Dakshina Kannada District in a area of 3.20 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

10

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.16 Removal of Sand from Sand Bar - SB - G4 of Gurupura River Bed, Panamburu Village, Mangaluru Taluk, Dakshina Kannada (8.0 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 126 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G4, Gurupura River Bed of Panamburu Village, Mangaluru Taluk, Dakshina Kannada District in a area of 8.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.17 Removal of Sand from Sand Bar - SB - G12 of Gurupura River Bed, Ulaibettu Village, Mangaluru Taluk, Dakshina Kannada (4.0 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 127 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of 11

sand from sand bar project at SB-G12, Gurupura River Bed of Ulaibettu Village, Mangaluru Taluk, Dakshina Kannada District in a area of 4.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.18 Removal of Sand from Sand Bar - SB - G3 of Gurupura River Bed, Padukodi Village, Mangaluru Taluk, Dakshina Kannada (9.0 Ha) of District Sand Monitoring Committee, Dakshina Kannada District. (SEIAA 128 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-G3, Gurupura River Bed of Padukodi Village, Mangaluru Taluk, Dakshina Kannada District in a area of 9.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 12

3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.19 Removal of Sand from Sand Bar - SB - N4 of Nethravathi River Bed, Kannuru-2 Village, Mangaluru Taluk, Dakshina Kannada (9.0 Ha) of District Sand Monitoring Committee, Dakshina Kannada District (SEIAA 129 MIN 2016)

This is an application submitted by Dakshina Kannada District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand from sand bar project at SB-N4, Nethravathi River Bed of Kannuru-2 Village, Mangaluru Taluk, Dakshina Kannada District in a area of 9.0 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC consideration with a specific condition that the length of the sand bar to be limited to 60%.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

Sand proposals of District Sand Monitoring Committee, :

162.20 Removal of Sand Bars Project at SB-SP-01 of Hosadu Village, Kundapura Taluk, Udupi District (2.428 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 130 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SP-01, Sowparnika River Bed of Hosadu Village, Kundapura Taluk, Udupi District in a area of 2.428 Ha.

13

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.21 Removal of Sand Bars Project at SB-SP-02 of Village, Kundapura Taluk, Udupi District (1.214 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 131 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SP-02, Sowparnika River Bed of Trasi Village, Kundapura Taluk, Udupi District in a area of 1.214 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

14

162.22 Removal of Sand Bars Project at SB-SP-03 of Trasi & Hadavu Village, Kundapura Taluk, Udupi District (1.011 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 132 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SP-03, Sowparnika River Bed of Trasi & Hadavu Village, Kundapura Taluk, Udupi District in a area of 1.011 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.23 Removal of Sand Bars Project at SB-SP-04 of Village, Kundapura Taluk, Udupi District (0.607 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 133 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SP-04, Sowparnika River Bed of Maravanthe Village, Kundapura Taluk, Udupi District in a area of 0.607 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions: 15

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.24 Removal of Sand Bars Project at SB-YM-05 of Kirimanjeshwara Village, Kundapura Taluk, Udupi District (1.011 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 134 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- YM-05, Yedamavina Hole River Bed of Kirimanjeshwara Village, Kundapura Taluk, Udupi District in a area of 1.011 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.25 Removal of Sand Bars Project at SB-YM-06 of Kambadakone Village, Kundapura Taluk, Udupi District (0.607 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 135 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- YM-06, Yedamavina Hole River Bed of Kambadakone Village, Kundapura Taluk, Udupi District in a area of 0.607 Ha.

16

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.26 Removal of Sand Bars Project at SB-VR-07 of Talluru Village, Kundapura Taluk, Udupi District (1.01 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 136 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- VR-07, Varahi River Bed of Talluru Village, Kundapura Taluk, Udupi District in a area of 0.809 Ha.

The proponent has submitted the letter of withdrawal of the above said proposal. The committee accepted the same and decided to recommend the proposal for closure.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.27 Removal of Sand Bars Project at SB-VR-08 of Hattiyangadi Village, Kundapura Taluk, Udupi District (2.02 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 137 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- VR-08, Varahi River Bed of Hattiyangadi Village, Kundapura Taluk, Udupi District in a area of 2.02 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said 17

proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.28 Removal of Sand Bars Project at SB-VR-09 of Anagalli Village, Kundapura Taluk, Udupi District (2.023 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 138 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- VR-09, Varahi River Bed of Anagalli Village, Kundapura Taluk, Udupi District in a area of 2.023 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

18

162.29 Removal of Sand Bars Project at SB-VR-10 of Kundapura Kasaba Village, Kundapura Taluk, Udupi District (1.618 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 139 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- VR-10, Varahi River Bed of Kundapura Kasaba Village, Kundapura Taluk, Udupi District in a area of 1.618 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.30 Removal of Sand Bars Project at SB-VR-11 of Kundapura Kasaba Village, Kundapura Taluk, Udupi District (8.093 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 140 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- VR-11, Varahi River Bed of Kundapura Kasaba Village, Kundapura Taluk, Udupi District in a area of 8.093 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

19

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.31 Removal of Sand Bars Project at SB-ST-12 of Kacchur & Handadi Village, Udupi Taluk, Udupi District (2.023 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 141 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- ST-12, Seetha River Bed of Kacchur & Handadi Village, Udupi Taluk, Udupi District in a area of 2.023 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.32 Removal of Sand Bars Project at SB-ST-13 of Kacchur Village, Udupi Taluk, Udupi District (1.011 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 142 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- ST-13, Seetha River Bed of Kacchur Village, Udupi Taluk, Udupi District in a area of 1.011 Ha.

20

The proponent has submitted the letter of withdrawal of the above said proposal. The committee accepted the same and decided to recommend the proposal for closure.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.33 Removal of Sand Bars Project at SB-ST-14 of Pandeshwara Village, Udupi Taluk, Udupi District (1.011 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 143 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- ST-14, Seetha River Bed of Pandeshwara Village, Udupi Taluk, Udupi District in a area of 1.011 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.34 Removal of Sand Bars Project at SB-ST-15 of Balkundru Village, Udupi Taluk, Udupi District (2.023 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 144 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- ST-15, Seetha River Bed of Balkudru Village, Udupi Taluk, Udupi District in a area of 2.023 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said 21

proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.35 Removal of Sand Bars Project at SB-ST-16 of Varamballi Village, Udupi Taluk, Udupi District (1.214 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 145 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- ST-16, Seetha River Bed of Varamballi Village, Udupi Taluk, Udupi District in a area of 1.214 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

22

162.36 Removal of Sand Bars Project at SB-SW-17 of Haradi Village, Udupi Taluk, Udupi District (1.011 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 146 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-17, Swarna River Bed of Haradi Village, Udupi Taluk, Udupi District in a area of 1.011 Ha.

The proponent has submitted the letter of withdrawal of the above said proposal. The committee accepted the same and decided to recommend the proposal for closure.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.37 Removal of Sand Bars Project at SB-SW-18 of Haradi Village, Udupi Taluk, Udupi District (1.214 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 147 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-18, Swarna River Bed of Haradi Village, Udupi Taluk, Udupi District in a area of 1.214 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.38 Removal of Sand Bars Project at SB-SW-19 of Paduthonse Village, Udupi Taluk, Udupi District (2.428 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 148 MIN 2016) 23

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-19, Swarna River Bed of Paduthonse Village, Udupi Taluk, Udupi District in a area of 2.428 Ha.

The proponent has submitted the letter of withdrawal of the above said proposal. The committee accepted the same and decided to recommend the proposal for closure.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.39 Removal of Sand Bars Project at SB-SW-20 of Bykadi Village, Udupi Taluk, Udupi District (1.416 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 149 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-20, Swarna River Bed of Bykadi Village, Udupi Taluk, Udupi District in a area of 1.416 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.40 Removal of Sand Bars Project at SB-SW-21 of Muduthonse Village, Udupi Taluk, Udupi District (1.416 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 150 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB-

24

SW-21, Swarna River Bed of Muduthonse Village, Udupi Taluk, Udupi District in a area of 1.416 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.41 Removal of Sand Bars Project at SB-SW-22 of Uppuru Village, Udupi Taluk, Udupi District (1.214 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 151 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-22, Swarna River Bed of Uppuru Village, Udupi Taluk, Udupi District in a area of 1.214 Ha.

The proponent has submitted the letter of withdrawal of the above said proposal. The committee accepted the same and decided to recommend the proposal for closure.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.42 Removal of Sand Bars Project at SB-SW-23 of Uppuru & Shivalli Village, Udupi Taluk, Udupi District of District Sand Monitoring Committee, Udupi District (1.214 Ha) (SEIAA 152 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-23, Swarna River Bed of Uppuru & Shivalli Village, Udupi Taluk, Udupi District in a area of 1.214 Ha.

25

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.43 Removal of Sand Bars Project at SB-SW-24 of Uppuru Village, Udupi Taluk, Udupi District (0.809 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 153 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-24, Swarna River Bed of Uppuru Village, Udupi Taluk, Udupi District in a area of 0.809 Ha.

The proponent has submitted the letter of withdrawal of the above said proposal. The committee accepted the same and decided to recommend the proposal for closure.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.44 Removal of Sand Bars Project at SB-SW-25 of Havanje Village, Udupi Taluk, Udupi District (0.809 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 154 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-25, Swarna River Bed of Havanje Village, Udupi Taluk, Udupi District in a area of 0.809 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said 26

proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.45 Removal of Sand Bars Project at SB-SW-26 of Havanje & Herga Village, Udupi Taluk, Udupi District of District Sand Monitoring Committee, Udupi District (2.023 Ha) (SEIAA 155 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-26, Swarna River Bed of Havanje & Herga Village, Udupi Taluk, Udupi District in a area of 2.023 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

27

162.46 Removal of Sand Bars Project at SB-SW-27 of Bellampalli Village, Udupi Taluk, Udupi District (0.485 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 156 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SW-27, Swarna River Bed of Bellampalli Village, Udupi Taluk, Udupi District in a area of 0.485 Ha.

The proponent has submitted the letter of withdrawal of the above said proposal. The committee accepted the same and decided to recommend the proposal for closure.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.47 Removal of Sand Bars Project at SB-PN-28 of Udyavara Village, Udupi Taluk, Udupi District (2.832 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 157 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- PN-28, Papanashini River Bed of Udyavara Village, Udupi Taluk, Udupi District in a area of 2.832 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

28

162.48 Removal of Sand Bars Project at SB-PN-29 of Mattu Village, Udupi Taluk, Udupi District (0.485 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 158 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- PN-29, Papanashini River Bed of Mattu Village, Udupi Taluk, Udupi District in a area of 0.485 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.49 Removal of Sand Bars Project at SB-SH-30 of Hejamadi Village, Udupi Taluk, Udupi District (0.607 Ha) of District Sand Monitoring Committee, Udupi District (SEIAA 159 MIN 2016)

This is an application submitted by Udupi District Sand Monitoring Committee seeking Environmental Clearance for proposed removal of sand bar project at SB- SH-30, Shambavi River Bed of Hejamadi Village, Udupi Taluk, Udupi District in a area of 0.607 Ha.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Pre Feasibility Report, report prepared by NITK, Suratkal and clarification/information provided during the meeting. The Committee noted that the said proposal has been considered by the State Coastal Zone Management Authority (KSCZMA) during the meeting held on 05.04.2016, the KSCZMA has recommended the proposal to SEIAA in accordance with the CRZ Notification 2011 for EC.

The Committee after discussion decided to recommend the proposal for issue of EC by imposing the following additional conditions:

29

1. Removal of sand bar shall be permitted only during the non monsoon season which is breeding season for aquatic fauna. 2. The quality of the material/sand removed from the sand bar shall be verified for its suitability to use in the construction activity. 3. All conditions stipulated by NITK and accepted by the proponent is to be strictly followed

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

Subject taken with the permission of the Chair:

162.50 Residential Apartment with Club House Project at Survey Nos. 18/4B, 18/4C, 18/5B2 & 18/5B3, Doddanagamangala Village, Begur Hobli, Bengaluru South Taluk, Bengaluru Urban District of M/s. Radiant Structures (P) Ltd. (SEIAA 213 CON 2015)

Name of Applicant: - M/s. Radiant Structures (P) Ltd., Name of the Consultancy Firm: - M/s. Aqua Engineering solutions M/s. Radiant Structures (P) Ltd., has applied for Environmental clearance from SEIAA for their Residential Apartment Project at Sy.No. 18/4B, 18/4C, 18/5B2 & 18/5B3, Doddanagamangala Village, Begur Hobli, Bengaluru South Taluk, Bengaluru Urban District under 8(a) of schedule EIA Notification – 2006 under category B. Total Project cost = Rs. 46 Cr.

1. Land details: - Total Plot area is 17,502.67 Sqm 2. The proposed residential buildings consists of 369 units and the configuration of the building is G+9UF and a club house in a total built up area of 45,788.68 Sqm. Ht of the building is 29.95 m, Right of way is 12.50 m. 3. Land use details: Total plot area -17,502.67 Sqm Green belt area -7,876.20 (45%) Driveway and hardscape ared -2,906.20 Sqm (16.61%) Ground coverage -6,720.27 Sqm (38.39%) Permissible FAR is 1.5 and proposed is 1.499. 4. Water Requirement: Total water requirement is 256 KLD.(105 KLD fresh water + 151 KLD Recycled water) The source of water is Konappana Agrahara village panchayat. NOC from Konappana Agrahara village panchayat submitted. Scientific assessment of the water in the gram panchayat submitted. Fresh water requirement calculated for 55 LPCD. 5. Wastewater Management: - The total quantity of waste water generated is 243 KLD (considering 95% waste generation) and treated is proposed STP of design capacity of 250 KLD with SBR technology. 6. Excavated Earth Management: - The total Earth work generated = 10,080 Cum. for backfilling - 4,032.16 Cum; landscaping – 3,150.48 Cum; roads and

30

walk ways – 1,162.48 Cum and for site formation (Level difference in the project site is 3m) – 1,734.88 Cum. 7. Solid Waste Management: Total waste generated in the project is 951 Kgs/day; where 571 kgs/day is the organic waste and 380 kgs/day is inorganic waste, will be disposed to Vendors/ Recyclers. Sludge generated is 12 Kg/day. 8. Energy Requirement: Total power requirement of 1707 KW is sourced from BESCOM; Backup power proposed is DG sets with a capacity of 1X750 KVA. Power savings is 26.13% 9. Traffic Details: submitted. Parking required is 364 and provided is 364. 10. Environment sensitivity: EMP submitted. 11. Other details: 20 Nos of recharge pits have been provided to recharge the ground water within the site. 12. Environmental sensitive area: Konappana agrahara lake is falls within 500 m from the project site as per the google image submitted by the proponent.

The Proponent and Environment Consultant attended the 160th meeting of SEAC held on 1st, 2nd and 3rd March 2016 to provide clarification/additional information.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Form-1A, Conceptual Plan and clarification/additional information provided during the meeting. The committee observed that the konappana agrahara lake is within 500 m from the project site. Therefore the committee directed the proponent to get clarification from competent authority (MI/LDA/BDA/BBMP) that the propolect area is not coming under lake bed or water spread area. Also the source of water shown is from village panchayat & hence it is instructed to conduct scientific assessment for availability of water for quantity & quality and its impact on the competitive users.

The committee after discussion had decided to reconsider the proposal after submission of the following.

1. Clarification from competent authority (MI/LDA/BDA/BBMP) regarding the project site is not coming under lake bed or water spread area. 2. Scientific assessment of availability of water for quality & quantity & its impact on competitive users.

The proponent has submitted the reply vide letter dated 21.03.2016.

The committee perused the replies submitted by the proponent during the 161st meeting of SEAC held on 28th and 29th March 2016. The committee observed that, the letter given by Tahsildar is for kharab land only & is silent about water/lake bed. As per the Google map, the lake appears to be about 100 m away from the project site, but, as per CDP, the lake is abutting the site and accordingly 30 m buffer has been left.

The committee after discussion decided to reconsider the proposal after submission of the clarification regarding distance of lake from the site by the competent authority as sought in the earlier meeting. 31

The proponent has submitted the relevant photographs and documents showing the lake boundary and project site boundary which are certified by BBMP vide letter dated 04.04.2016. It is also noted the as per the RMP 2015 submitted by the proponent the project site is not falling in the sensitive Zone.

The committee perused the reply submitted by the proponent and decided to recommend the proposal to SEIAA for issue of Environmental Clearance with a condition that no construction activity undertaken within the 30 m of buffer zone.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.51 Residential Apartment and Club House Project at Sy.No.109/4 (P) of Avalahalli Village, Bengaluru North Taluk, Bengaluru Urban District of M/s. BCIL REALTY PVT. LTD. (SEIAA 5 CON 2016)

Name of Applicant: - M/s. BCIL REALTY PVT. LTD M/s. BCIL REALTY PVT. LTD has applied for Environmental clearance from SEIAA for their Residential Apartment and club house Project at Sy.No.109/4 (P) of Avalahalli Village, Bengaluru North Taluk, Bengaluru Urban District under 8(a) of schedule EIA Notification – 2006 under category B. Total Project cost = Rs. 35 Cr.

1. Land details: - Total Plot area is 8,098.12 Sqm; 2. The total built up area of the project is 24,939.28 Sqm, compring of 120 Nos of units in Block – A & Block – B, distributed over B+G+4UFD & a club house in G+2UF with a maximum height of 14.95 m. 3. Land use details: Total plot area -8,098.12 Sqm Land scape -2,675.20 Sqm (33.03%) Roads and open space area -1,822.68 Sqm (22.51%) Ground coverage -3,600.24 Sqm (50%) Permissible FAR is 1.75 and achieved is 1.74. 4. Water Requirement: Total water requirement is 83 KLD.(34 KLD fresh water + 49 KLD Recycled water) The source of water is from Singanaayakanahalli village panchayath. NOC submitted and scientific assessment of water source in Singanaayakanahalli grama panchayath submitted. Fresh water requirement calculated for 55 lpcd. 5. Wastewater Management: - The total quantity of waste water generated is 79 KLD (considering 95% waste generation) and treated is proposed in STP of design capacity of 80 KLD with SBR technology. 6. Excavated Earth Management: - The total Earth work generated is 10,800 Cum. out of which for back filling in foundation - 2,160 Cum; for landscaping - 2,675 cum; for roads and walkways – 1,458 cum and for site formation – 4,507 cum (level difference is 3.42 m) 7. Solid Waste Management: Total waste generated in the project is 309 Kgs/day; where 185 kgs/day is the organic waste and 124 kgs/day is inorganic waste, will be disposed to Vendors/ Recyclers. 32

8. Energy Requirement: Total power requirement of 841 KW is sourced from BESCOM; Backup power proposed is DG sets with a capacity 2x125 KVA. Energy savings is 30.61% 9. Traffic Details: submitted. Parking provided is 141. 10. Environment sensitivity: EMP submitted. 11. Other details: 16 Nos of recharge pits have been provided

The Proponent and Environment Consultant attended the 160th meeting of SEAC held on 1st, 2nd and 3rd March 2016 to provide clarification/additional information.

The committee appraised the proposal considering the information provided in the statutory application-Form I, Form-1A, Conceptual Plan and clarification/additional information provided during the meeting.

The committee after discussion had decided to reconsider the proposal after submission of the following information:

1. Revised water balance chart for reusing the tertiary treated water 2. Scientific assessment of availability of water for quality & quantity & its impact on competitive users.

The proponent has submitted the reply vide letter dated 21.03.2016.

The committee perused the replies submitted by the proponent. It is highly regretted to note that, the water balance chart submitted earlier has been resubmitted now without any changes.

The committee after discussion decided to reconsider the proposal after submission of the revised water balance chart & also clarification regarding submission of the same balance chart submitted earlier as revised one.

The proponent has submitted the reply vide letter dated 04.04.2016.

The committee perused the reply submitted by the proponent and decided to recommend the proposal to SEIAA for issue of Environmental Clearance.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.52 Proposed development of scientific landfill for inerts at Bagalur Quarry Pits in Bangalore East North, Bangalore by M/s. Bruhath Bangalore Mahanagara Palike (SEIAA 10 IND 2016)

M/s Bruhat Bangalore Mahanagara Palike has submitted a proposal for development of Scientific Landfill for Inerts at Bagalur Quarry pits in BBMP West Zone, Bangalore (SEIAA 10 IND 2016) under section 7(i) Common Municipal Solid Waste Management Facility (CMSWMF), of EIA Notification 2006. The proposed project is comes under category B1.

33

The proposed project consists of filling the existing quarry site in phase manner, with phase – 1 for 5 acres designed for 250 TPD/ Ha with design period for 3 years.

The committee appraised the proposal based on the information submitted by the proponent. The committee after discussion decided to recommend the proposal to SEIAA for issue of standard ToR along with the following additional ToR’s. The EIA report should be prepared by NABET/QCI Accredited consultants only.

1. Scheme and design of land fill site construction/scheme of development which should comply to MSW Rules 2000. 2. Third party evaluation scheme both at development phase and at operation phase of the site may be provided. 3. Details of the surroundings of the site, proposed measures taken to avoid the accidents during unloading of the material, provision made to avoid dust emission and noise may be given. 4. Details of approach road, mode of transportation to avoid accidents and spillages of the material to be given. 5. Protocols/methods to avoid organic or degradable or toxic/industrial waste entering in to land fill site. 6. Scheme/procedure followed for the operation of the land fill site may be explained. 7. The quarry pit shall be securely fenced before handing it over to BBMP/operator to be explained. 8. There shall be round the clock supervision of the site to prevent dumping of non permitted material and the accidental fires, also to prevent entry of unauthorized access to any unlawful activity. Perhaps providing CCTV cameras is also ideal. 9. Available depth of quarry and scheme proposed to fill up the quarry and its impact on ground water to be explained.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.53 Proposed development of scientific landfill for inerts at Bellahalli Quarry Pits in Yalahanka Zone, Bangalore by M/s. Bruhath Bangalore Mahanagara Palike (SEIAA 11 IND 2016)

M/s Bruhat Bangalore Mahanagara Palike has submitted a proposal for development of Scientific Landfill for Inerts at Bellahalli Quarry pits in Yalahanka Zone, Bangalore (SEIAA 11 IND 2016) under section 7(i) Common Municipal Solid Waste Management Facility (CMSWMF), of EIA Notification 2006. The proposed project is comes under category B1.

The proposed project consists of filling the existing quarry site in phase manner, with phase – 1 for 5 acres designed for 250 TPD/ Ha with design period for 3 years.

The committee appraised the proposal based on the information submitted by the proponent. The committee after discussion decided to recommend the proposal to SEIAA for issue of standard ToR along with the following additional ToR’s. The EIA report should be prepared by NABET/QCI Accredited consultants only.

1. Scheme and design of land fill site construction/scheme of development which should comply to MSW Rules 2000.

34

2. Third party evaluation scheme both at development phase and at operation phase of the site may be provided. 3. Details of the surroundings of the site, proposed measures taken to avoid the accidents during unloading of the material, provision made to avoid dust emission and noise may be given. 4. Details of approach road, mode of transportation to avoid accidents and spillages of the material to be given. 5. Protocols/methods to avoid organic or degradable or toxic/industrial waste entering in to land fill site. 6. Scheme/procedure followed for the operation of the land fill site may be explained. 7. The quarry pit shall be securely fenced before handing it over to BBMP/operator to be explained. 8. There shall be round the clock supervision of the site to prevent dumping of non permitted material and the accidental fires, also to prevent entry of unauthorized access to any unlawful activity. Perhaps providing CCTV cameras is also ideal. 9. Available depth of quarry and scheme proposed to fill up the quarry and its impact on ground water to be explained.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

162.54 Proposed development of scientific landfill for inerts at mylasandra Quarry Pits in Bangalore South Zone, Bangalore by M/s. Bruhath Bangalore Mahanagara Palike (SEIAA 13 CON 2016)

M/s Bruhat Bangalore Mahanagara Palike has submitted a proposal for development of Scientific Landfill for Inerts at Mylasandra Quarry pits in Bangalore South Zone, Bangalore (SEIAA 13 IND 2016) under section 7(i) Common Municipal Solid Waste Management Facility (CMSWMF), of EIA Notification 2006. The proposed project is comes under category B1.

The proposed project consists of filling the existing quarry site in phase manner, with phase – 1 for 5 acres designed for 250 TPD/ Ha with design period for 3 years.

The committee appraised the proposal based on the information submitted by the proponent. The committee after discussion decided to recommend the proposal to SEIAA for issue of standard ToR along with the following additional ToR’s. The EIA report should be prepared by NABET/QCI Accredited consultants only.

1. Scheme and design of land fill site construction/scheme of development which should comply to MSW Rules 2000. 2. Third party evaluation scheme both at development phase and at operation phase of the site may be provided. 3. Details of the surroundings of the site, proposed measures taken to avoid the accidents during unloading of the material, provision made to avoid dust emission and noise may be given. 4. Details of approach road, mode of transportation to avoid accidents and spillages of the material to be given. 5. Protocols/methods to avoid organic or degradable or toxic/industrial waste entering in to land fill site. 35

6. Scheme/procedure followed for the operation of the land fill site may be explained. 7. The quarry pit shall be securely fenced before handing it over to BBMP/operator to be explained. 8. There shall be round the clock supervision of the site to prevent dumping of non permitted material and the accidental fires, also to prevent entry of unauthorized access to any unlawful activity. Perhaps providing CCTV cameras is also ideal. 9. Available depth of quarry and scheme proposed to fill up the quarry and its impact on ground water to be explained.

Action: Secretary, SEAC to forward the proposal to SEIAA for further necessary action.

Meeting ended with thanks to the Chair.