SL. PAGE CONTENTS NO. NO. 1 INTRODUCTION 7 2 ORGANISATIONAL STRUCTURE 8 ACHIEVEMENTS OF WATER RESOURCES DEPARTMENT DURING 3 9 2010-11 4 ACCELERATED IRRIGATION BENEFIT PROGRAMME (AIBP) 11 5 PRIME MINISTER’S SPECIAL PACKAGE 6 SPECIAL DEVELOPMENT PLAN (SDP) 21 7 WATER RESOURCES DEVELOPMENT ORGANISATION 23 8 CENTRAL MECHANICAL ORGANISATION (CMO) 28 9 ENGINEERING RESEARCH STATION (KERS, K.R SAGAR) 31 9 WATER AND LAND MANAGEMENT INSTITUTE (WALMI, DHARWAD) 36 NIGAM 11 KRISHNA BHAGYA JALA NIGAM LIMITED (KBJNL) 37 11.1 UPPER KRISHNA PROJECT (UKP) 38 11.2 TOWN DEVELOPMENT AUTHORITY, BAGALKOT (BTDA) 63 12 KARNATAKA NEERAVARI NIGAMA LIMITED (KNNL) 68 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, 12.1 69 IRRIGATION (NORTH), 12.1.1 PROJECT 70 12.1.2 HIPPARAGI IRRIGATION PROJECT 73 12.1.3 MARKANDEYA PROJECT 75 12.1.4 DUDHGANGA IRRIGATION PROJECT 77 12.1.5 LIFTING OF HIRANYAKESHI WATERS INTO G.R.B.C CANAL. 78 12.1.6 BELLARYNALA PROJECT 80 12.1.7 SRI RAMESHWARA L.I. SCHEME 81 12.1.8 KINAYE 82 12.1.9 MALLIKWADI LIFT IRRIGATION SCHEME (REJUVENATION WORKS) 83 12.1.10 CONSTRUCTION OF BRIDGE-CUM-BARRAGE 83 12.1.11 CONSTRUCTION OF SANGAM BARRAGE 84 12.1.12 FILLING OF SHIRGAON BASAVANNA TANK 84 12.1.13 FILLING OF TANK 84 FILLING OF 18 TANKS OF TQ. & 4 TANKS OF CHIKKODI TQ. 12.1.14 84 (TOTAL 22 TANKS) FROM HIRANYAKESHI RIVER AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, 12.2 84 MALAPRABHA PROJECT ZONE, DHARWAD. 12.2.1 MALAPRABHA PROJECT 85 12.2.2 HARINALA IRRIGATION PROJECT 87

3 SL. PAGE CONTENTS NO. NO. 12.2.3 KALASA NALA AND BANDHURNALA PROJECT 88 12.2.4 JAVALUHALLA L.I. SCHEME 90 12.2.5 BENNIHALLA L.I. SCHEME (5 NOS.) 90 12.2.6 KOLACHI L.I. SCHEME 91 12.2.7 L.I. SCHEME 92 12.2.8 SHIGGAON L.I. SCHEME (Micro irrigation project- sprinkler/drip system) 93 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, 12.3 96 IRRIGATION CENTRAL ZONE, MUNIRABAD 12.3.1 LIFT IRRIGATION SCHEME (SLIS) 96 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER 12.4 99 TUNGA PROJECT ZONE, SHIMOGA 12.4.1 UPPER TUNGA PROJECT (UTP) 99 12.4.2 TUNGA LIFT IRRIGATION SCHEME 100 12.4.3 BASAPURA LIFT IRRIGATION SCHEME 100 12.4.4 ITAGI-SASALWAD LIS 101 12.4.5 GUDDADA MALLAPURA LIS 101 12.4.6 UBRANI-AMRUTHAPURA MULTIPURPOSE LIS 102 12.4.7 SANYASIKOPPA LIS 102 12.4.8 DANDAVATHI RESERVOIR PROJECT 102 12.4.9 KALLUVADDAHALLA NEW TANK 102 12.4.10 THILUVALLI LIFT IRRIGATION SCHEME 102 12.4.11 DAVANAGERE 22 TANKS (RAJANAHALLI LIS) 103 12.4.12 NIDIGE-PURLE TANKS 103 12.4.13 MODERNISATION OF THE TUNGA ANICUT PROJECT 104 12.5 BHADRA PROJECT 104 12.5.1 UPPER BHADRA PROJECT (UBP) 104 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, VARAHI 12.6. 111 PROJECT ZONE, SIDDAPURA. 12.6.1 VARAHI IRRIGATION PROJECT 111 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, 12.7 114 IRRIGATION PROJECTS ZONE, GULBARGA 12.7.1 BENNITHORA PROJECT 114 12.7.2 BHIMA LIFT IRRIGATION SCHEME 115 12.7.3 GANDORINALA PROJECT 117 12.7.4 LOWER MULLAMARI PROJECT 118 12.7.5 PROJECT 119 12.8 UPPER BHADRA PROJECT 121

4 SL. PAGE CONTENTS NO. NO. 12.9 YETTINAHOLE PROJECT 140 13 CAUVERY NEERAVARI NIGAMA LIMITED 142 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, 13.1 142 IRRIGATION (S) ZONE, MYSORE 13.1.1 D. DEVARAJA URS CANAL 143 13.1.2 KABINI RESERVOIR PROJECT 144 13.1.3 HARANGI PROJECT 145 13.1.4 TARAKA PROJECT 147 13.1.5 ARKAVATHY PROJECT 148 13.1.6 CHIKLIHOLE PROJECT 149 13.1.7 UDUTHOREHALLA PROJECT 150 13.1.8 IGGALUR BARRAGE PROJECT 151 13.1.9 MANCHANABELE PROJECT 152 13.1.10 MODERNISATION OF KRISHNARAJA SAGAR 153 13.1.11 NANJAPURA LIFT IRRIGATION SCHEME 155 13.1.12 BANAHALLIHUNDI LIS 156 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, 13.2 157 HEMAVATHY CANAL ZONE, TUMKUR 13.2.1 HEMAVATHY PROJECT, TUMKUR 157 13.2.2 HEMAVATHY PROJECT, GORUR 159 13.2.3 YAGACHI PROJECT 161 13.2.4 HUCHANAKOPPALU LIS 162 13.2.5 KAMASAMUDRA LIS 163 13.2.6 KACHENAHALLI LIS 163 13.2.7 VOTEHOLE PROJECT 165 DRINKING WATER SCHEMES 13.3 166

DRINKING WATER SCHEME TO GULUR-HEBBUR HOBLIES IN TUMKUR 13.3.1 166 DISTRICT DRINKING WATER SCHEME TO HONNAVALLI AND OTHER HOBLIES 13.3.2 166

FILLING UP OF 20 TANKS OF CHAMARAJANAGAR, NANJANGUD 13.3.3 AND GUNDLUPET TALUKS - DRINKING WATER SCHEME. 166

13.4 MODERNIZATION OF ANECUT AND ITS CANALS MODERNISATION OF MANDAGERE AND HEMAGIRI ANECUT AND THEIR 13.4.1 169 CANALS MODERNIZATION OF KRISHNARAJA (KATTEPURA) ANECUT AND ITS 13.4.2 170 CANALS 13.4.3 MODERNISATION OF MIRLE AND RAMASAMUDRA ANECUT AND ANECUT 170

5 SL. PAGE CONTENTS NO. NO. CANALS 13.4.4 MODERNISATION OF CHAMARAJ ANECUT AND ITS CANAL 170 13.4.5 MODERNISATION OF MADHAVAMANTRI ANECUT AND ANECUT CANAL 171 13.4.6 MODERNISATION OF DEVARAYA ANECUT AND ANECUT CANAL 171 ZONES AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, 14 174 IRRIGATION PROJECT ZONE, GULBARGA 14.1 KARANJA PROJECT 174 14.2 ERM OF 4 MEDIUM PROJECTS UNDER A.I.B.P. 177 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, 15 181 IRRIGATION CENTRAL ZONE, MUNIRABAD AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER 16 189 TUNGA PROJECT ZONE, SHIMOGA 17 COMMAND AREA DEVELOPMENT PROGRAMME 200

6 1. INTRODUCTION

The Annual Report is a document giving details of the annual Programme, Progress and important events that have taken place during the year, in the Water Resources Department.

GEOGRAPHICAL AREA

The geographical area of Karnataka is 1,91,791 Sq. Km., accounting for 5.83% of the total area of the country.

The cultivable command area of the State is 1,40,598 sq. Km. The net sown area is 1,07,000 sq. Km. The ultimate Irrigation Potential under Major and Medium Irrigation Projects has been estimated as 35,000 sq. Km or 35.00 Lakh Ha.

PROGRESS IN BRIEF

There are 138 Major and Medium Irrigation Projects in the State, out of which 60 projects are completed, 78 are ongoing.

The Water Resources Department has established three special purpose vehicles, namely, Krishna Bhagya Jala Nigama Limited (KBJNL), Karnataka Neeravari Nigama Limited (KNNL) and Cauvery Neeravari Nigam Limited (CNNL), under the companies Act of 1956, to mobilize financial resources for speedy completion of major and medium irrigation projects with-in the targeted period.

KRISHNA BHAGYA JALA NIGAM LIMITED (KBJNL):

“Krishna Bhagya Jala Nigam Limited” was formed vide G.O. No. ID/25/WBM/95, dated: 6-5-94, to expedite the works of Upper Krishna Project (UKP). This Nigam is functioning since 19th August 1994.

KARNATAKA NEERAVARI NIGAM LIMITED (KNNL):

”Karnataka Neeravari Nigam Limited” was formed vide G.O. No. ID: 201: KBN: 98, dated: 26-11-98, to expedite the works in Krishna Basin, except UKP. This Nigam is functioning since 9th December 1998.

CAUVERY NEERAVARI NIGAM LIMITED (CNNL):

”Cauvery Neeravari Nigam Limited” was formed vide G.O. No. WRD: 32: KBN: 2003, Dated: 12.05.2003, to expedite the works in Cauvery Basin. This Nigam is functioning since 3rd June 2003.

7 2. ORGANISATIONAL STRUCTURE WATER RESOURCES DEPARTMENT

HON’BLE MINISTER FOR WATER RESOURCES

PRINCIPAL SECRETARY

SECRETARY

C.E, DIRECT CADA’S KBJ NL BOARD KNNL BOARD CNNL BOARD W.R.D.O FIELD OF DIRECTORS OF DIRECTORS OF OFFICES DIRECTORS CADA CE, DIRECTORATE REGISTERED REGISTERED HYDROLOGY CORPORATE CORPORATE REGISTERED CE, IRRIGATION & CMO, OFFICE CORPORATE CENTRAL ZONE, OFFICE BANGALORE OFFICE MUNIRABAD ADMINISTRATOR MALAPRABHA & FIELD OFFICES FIELD OFFICES FIELD C.E, GHATAPRABHA, OFFICES I.S.W.D, CE, IRRIGATION BELGAUM CE, O&M ZONE, BANGALORE PROJECT ZONE, CE, UTP UKP, GULBARGA ADMINISTRATOR ZONE, CE, NARAYANPURA TUNGABHADRA SHIMOGA IRRIGATION PROJECT, (SOUTH), MUNIRABAD CE, DAM ZONE, MYSORE CE, UPPER UKP, ALMATTI CE, VARAHI TUNGA ZONE, PROJECT, SIDDAPURA ADMINISTRATO CE, H.P.Z, SHIMOGA CE, CANAL ZONE - R BHADRA, GORUR SHIMOGA 1, UKP, B.GUDI CE, IPZ, GULBARGA

DIRECTOR,

CE, CANAL WALMI CE, H.C.Z, ADMINISTRATOR ZONE-2, UKP, CE, TUMKUR CAUVERY BASIN, KEMBHAVI IRRIGATION MYSORE (NORTH), DIRECTOR, K.E.R.S BELGAUM ADMINISTRATOR UKP, B.GUDI CE, MALAPRABHA PROJECT ZONE, DHARWAD ADMINISTRATOR IRRIGATION PROJECT ZONE, CE, UPPER GULBARGA BHADRA PROJECT, CHITRADURGA

8 3. ACHIEVEMENTS OF WATER RESOURCES DEPARTMENT DURING 2012-13

 Total irrigation potential of 53,743 Hectares. is created from ongoing irrigation projects during 2012-13.

 Cumulative irrigation potential of 27.43 lakh Hectares has been created from Major & medium irrigation projects upto end of March 2013.

 An irrigated potential of 6,09,299 Ha. has been created so for under Upper Krishna Project, Such as, NLBC, JBC, NRBC, ALBC, ARBC are nearing completion.

 Central Assistance of `.207.352 Crores under Accelerated Irrigation Benefit Programme & Hon’ble Prime Minister’s Special Rehabilitation Package has been availed during 2012-13 and an expenditure of `. 657.61 crores is incurred.

 Krishna Bhagya Jala Nigam Limited has incurred an expenditure of `. 1599.38 Crores for implementing 14 ongoing major and medium irrigation projects/Components during 2012-13.

 Karnataka Neeravari Nigam Limited has incurred an expenditure of `. 2557.63 Crores for implementing 42 ongoing major and medium irrigation projects/components of projects during 2012-13.

 Cauvery Neeravari Nigam Limited has incurred an expenditure of `. 879.70 Crores for implementing 21 ongoing major and medium irrigation projects/Components of projects during 2012-13.

 The CDTA with ADB assistance was completed successfully and ADB has been able to move to the stage of the PPTA successfully PPTA has now submitted the Final Report.

 For efficient & effective water management under the Command Areas of Major & medium irrigation projects, Water Resources Department has established 2787 Water Users Co- operative Societies.

 FIC has been given priority in order to bridge the gap between potential created and utilized. During 2012-13, FIC’s have been created for 79950 Ha. under CADA.

 During this water year, regulation of water has been managed effectively, even in critical drought conditions.  The RFD (Result Framework Document) document has been prepared with a vision to identify the critical key result areas for the next five years.  CADA Directorate was formed in the State to have better co-ordination among each CADA’s and steps to increase efficiency in Water Users Co-operative Societies (WUCs) in the command area of major and medium irrigation.  Sprinkler irrigation system has been adopted in Shiggaon lift irrigation scheme to irrigate 9,900 hectares of drought prone area in Haveri district.  To improve the water use efficiency (both conventional and end use efficiency) by about 20% and for ensuring equitable distribution of water also to mitigate the suffering atchkat in the

9 Narayanapur Left Bank Canal (NLBC) network system; A proposal at an total estimated cost of Rs.4085.00 crores for Extension, Renovation and Modernisation (ERM) programme under AIBP and WUE under National Water Mission has been taken up. DPR submitted to CWC, New Delhi for clearance. Approval/clearance to DPR is awaited.

 Ist and II nd lifts of Singtalur Lift Irrigation Schemes on right side has been commissioned and water let out in the canal on trial basis (atchkat about 23,000 acres).

 During 2012-13, expenditure under Special Component Plan is `353.67 crores, under Tribal Sub Plan is `117.40 crores & under Special Development Plan of `806.09 crores has been incurred.

 Under UKP Stage III, to utilize 130.9 TMC of water, it is contemplated to provide irrigation for 5.3 lakh Ha. coming under Bijapur, Bagalkot, Gulbarga, Yadgir, Raichur, & Gadag districts. Administrative approval has been accorded to the UKP Stage III at an estimate cost of `.17207 crores. Under this, Mulwad LIS, Chimmalagi LIS, Mallabad LIS, Indi LIS extension, Rampur LIS, Koppal LIS, Herkal LIS & NRBC extension projects are taken up.

 Diversion of 24 TMC of water from the west flowing rivers viz. Yettinahole & its tributaries to mitigate the severe drinking water shortage in Kolar, Chikkaballapur, Bangalore (Rural), Ramnagar, Tumkur & other needy districts is taken up. The administrative approval has been accorded vide G.O.No.WRD 203 vibyaee 2012 dated 13.7.2012 with an estimated cost of `.8323.50 crores.

 Rejunevtion & Moderniation of Anecut canals under Cauvery Neeravari Nigam viz Sriramadevara canal, Kattepura & Hemagiri-Mandagere is completed and Chamaraja, Mirley- Ramasamudra, Madhavamanthri, Devaraya, Virija, Rajaparameshwari canal, Ramaswamy canal, Chikkadevaraya canal, Hullahalli canal are taken up.

 Improvements to Visweshwaraian Canal Net work with an estimated cost of Rs.330.00 crores.is taken up.

 Filling up of 20 tanks in Chamrajanagar taluk, Nanjangud & Gundlupet taluks in 3 stages from with an estimated cost of `.210.00 crores to provide drinking water supply to drought affected areas and to improve ground water table is taken up.

10 4. ACCELERATED IRRIGATION BENEFIT PROGRAMME

For the early completion of some of the ongoing irrigation projects, which were lingering due to shortage of funds for many years, the Government of launched the Accelerated Irrigation benefit programme, during 1996-97. Since then, 11 projects in the State, namely, Upper Krishna project (UKP) Stage-I, Phase-III, Malaprabha, Hirehalla, Ghataprabha, Karanja, Upper Krishna project (UKP) Stage-II, Maskinala, Varahi, Bhima LIS, Guddadamallapura LIS,and Gandhorinala have received / are receiving Central Loan Assistance (CLA) / (CA) under Accelerated Irrigation benefit programme (AIBP).

 During 2012-13, Malaprabha, Varahi, Hipparagi and Modernisation of Bhadra canal system are the 4 projects that have received C.A. under A.I.B.P.

 The cumulative C.A. (including grants) released upto end of March 2013 under AIBP & PM’s package is `. 5687.22 crores. The cumulative expenditure incurred on these projects up to the end of March 2013 is `. 9195.77 crores.

Hon’ble PM’s Special Package:- During 2006-07, the Special Rehabilitation Package was launched by the Government of India to mitigate the distress of farmers in selected 31 districts of the Country from where large numbers of Suicide cases by the farmers were reported.

In Karnataka, 6 districts viz Belgaum, Bijapur, Shimoga, Chikkamagalur, Chitradurga, Hassan and Kodagu are identified as drought prone districts and 17 projects benefiting these 6 districts were identified and proposals of the same have been submitted. The funding proposed is as per revised AIBP norms.

Malaprabha and Ghataprabha are already receiving Central Assistance under AIBP. Markandeya, Chiklihole and Votehole projects are completed. Hippargi, Dudhganga, ERM of Bheemasamudra tank and Modernisation of canal systems of Bhadra are availing central assistance under this package.

11 Details of central assistance received under AIBP & PM’s Special Package during 2012-13 are as follows:

Details of Central Assistance (CA) under AIBP during 2012-13 (`. in Crores, Potential in Hectares.) Central Expenditure till Central Assistance Sl. Assistance Name of Project 03/2013 during received during No. sought during 2012-13 2012-13 2012-13 1 Malaprabha 80.35 109.21 98.289 2 Guddadamallapura LIS 5.90 31.81 3 Bhima LIS 76.11 47.58 4 Varahi 63.17 12.88 11.592 5 Srirameshwara LIS (New) 70.32 86.40 6 Upper Mullamari (ERM- New) - 7.25 7 Chadrampalli (ERM- New) 1.90 3.62 8 Hattikuni (ERM- New) 0.80 6.075 TOTAL 298.55 304.83 109.881

DETAILS OF MAJOR & MEDIUM IRRIGATION PROJECTS ASSISTED UNDER P.M'S SPECIAL PACKAGE FOR THE YEAR 2012-13

Budget Central Central Expenditure provision/ Assistance Assistance Sl. Name of till 03/2013 Proposal for programme sought recived No. Project during 2012-13 for during during 2012-13 2012-13 2012-13 2012-13 1 Hipparagi 200.00 319.76 105.10 94.59 CA recived. Clarificatiuon sought by Planning 2 Dudhganga 7.89 9.22 1.49 - Commission for Time extension. Modernisation 3 of Bhadra 11.41 30.08 3.20 2.881 CA recived. canal system Total 219.30 359.06 109.79 97.471 Total central assistance received under AIBP & PM’s package Rs.109.881 + 97.471= 207.35 crores.

ABSTRACT (CUMULATIVE) OF CENTRAL ASSISTANCE RECEIVED UNDER AIBP & PM’S PACKAGE (`.in crores) CA released Expenditure AIBP General) 4744.54 6962.29 AIBP (P.M's package) 942.68 2233.48 Total 5687.22 9195.77

12 STATEMENT SHOWING DETAILS OF CENTRAL ASSISTANCE UNDER A.I.B.P RELEASED TO MAJOR AND MEDIUM IRRIGATION PROJECTS (SINCE 1996-97) (`. in Crores) CENTRAL ASSISTANCE CENTRAL PERIOD NO. OF PROJECTS PROPOSED/ ASSISTANCE EXPENDITURE SANCTIONED RELEASED 1996-97 5 122.50 61.25 172.21 1997-98 5 175.00 90.50 160.49 1998-99 5 167.00 94.50 171.05 1999-00 5 190.64 157.14 190.61 2000-01 4 171.00 171.00 268.26 2001-02 7 545.00 492.50 911.38 2002-03 8 611.97 620.85 693.00 2003-04 8 266.48 266.48 440.57 2004-05 5 463.05 449.71 475.46 2005-06 5 336.70 291.23 473.24 2006-07 6 568.91 334.00 457.15 2007-08 5 410.22 322.20 350.59 2008-09 6 294.25 214.94 481.87 2009-10 9 660.90 549.75 399.68 2010-11 8 555.56 248.06 523.27 2011-12 12 465.16 270.56 494.91 2012-13 8 304.83 109.88 476.40

TOTAL UPTO MARCH 2013 6309.17 4744.55 7140.14

13

CUMULATIVE STATEMENT CLA Released (`. in Crores)

Sl. 1996- 1997- 1998- 1999- 2000- 2001- 2002- 2003- 2004- 2005- 2006- 2007- 2008- 2009- 2010- Project 2011-12 2012-13 CUMULA No 97 98 99 2000 2001 02 03 04 05 06 07 08 09 10 11 TIVE

UKP Stage-I Phase- - 1 57.00 50.00 50.00 100.00 100.00 200.00 181.00 - 115.85 - 71.638 71.23 91.92 154.16 - 134.50 1377.30 III

2 UKP Stage-II - - - - - 250.00 275.05 163.48 240.72 197.76 172.53 102.07 8.019 93.02 150.00 - - 1652.64

3 Malaprabha 1.50 12.00 10.00 13.50 - 10.00 25.56 - 12.00 20.00 13.50 54.24 30.54 110.53 0.00 90.72 98.289 404.09

4 Hirehalla 2.75 6.00 6.00 8.00 8.00 10.00 8.78 14.71 ------64.24

5 Ghataprabha - 15.00 12.50 20.00 45.00 5.00 75.00 13.02 62.09 65.00 30.805 72.61 52.04 56.16 20.6 - - 544.82

6 Karanja - 7.50 16.00 15.64 18.00 10.00 34.37 75.27 - - - - 12.25 - 0.00 - - 189.03

7 Gandhorinala - - - - - 7.50 17.87 - 19.05 8.47 45.53 - - 18.52 - - - 116.94

8 Maskinala ------3.22 ------3.22

9 Varahi ------22.05 20.17 26.32 0.00 - 11.592 68.54

10 Bhima LIS ------58.64 52.62 45.34 - 156.60

Guddadamallapura 11 ------32.40 24.84 - - 57.24 LIS

Srirameshwara 12 ------LIS(N)

13 UpperMullamari (N) ------

Chanrampalli 14 ------(N) 15 Hattikuni(N) ------14 TOTAL 61.25 90.50 94.50 157.14 171.00 492.50 620.85 266.48 449.71 291.23 334.00 322.20 214.94 549.75 248.06 270.56 109.881 4634.66

Expenditure (`. in Crores)

Sl. 1997- 1998- 1999- 2000- 2001- 2002- 2003- 2004- 2005- 2007- 2010- CUMULA Project 1996-97 2006-07 2008-09 2009-10 2011-12 2012-13 No 98 99 2000 2001 02 03 04 05 06 08 11 TIVE

UKP Stage-I 1 155.74 92.30 77.58 116.40 187.80 235.33 214.69 94.19 92.18 61.13 46.19 49.30 139.36 57.51 91.05 38.65 - 1749.40 Phase-III

2 UKP Stage-II - - - - - 534.10 352.29 236.48 268.17 272.29 234.58 86.80 176.72 104.10 119.55 130.84 - 2515.92

3 Malaprabha 5.12 14.92 22.64 9.87 5.15 15.87 14.45 14.42 19.64 19.62 31.28 56.37 27.72 31.99 94.81 79.20 80.35 463.07

4 Hirehalla 11.35 17.12 12.06 15.82 22.68 11.41 11.69 9.94 18.45 ------130.52

5 Ghataprabha - 20.47 28.82 20.04 26.96 72.77 57.57 55.45 64.68 92.47 77.29 76.90 44.56 72.35 84.22 115.54 - 910.09

6 Karanja - 15.68 29.95 28.48 25.67 26.55 23.62 18.64 - - - - 10.78 10.72 21.92 7.07 - 219.08 Gandhorinal 7 - - - - - 15.35 16.82 10.09 12.34 27.73 34.96 - 17.97 24.66 - - - 159.92 a

8 Maskinala ------1.87 1.36 ------3.23

9 Varahi ------32.85 81.22 64.76 57.98 41.76 18.91 63.17 297.48

10 Bhima LIS ------33.71 38.37 53.36 76.11 125.44

Guddadamall 11 apura LIS ------6.66 31.59 21.43 5.90 59.68

Sriramesh- 12 ------29.91 70.32 29.91 wara LIS(N)

UpperMulla- 13 ------mari(N)

Chandram- 14 ------1.90 - palli(N)

15 Hattikuni(N) ------0.80 -

TOTAL 172.21 160.49 171.05 190.61 268.26 911.38 693.00 440.57 475.46 473.24 457.15 350.59 481.87 399.68 523.27 494.91 298.55 6663.74

15

DETAILS OF PROJECTS ASSISTED UNDER AIBP PROGRAMME (YEARLY) (As on 31-3-2013) (`. in Crores)

1996-97 1997-98 1998-99 1999-2000 2000-01 2001-02 Sl. Project No CLA CLA CLA CLA CLA CLA CLA Expendit CLA Expendi CLA Expendi CLA Expendi CLA Expendi CLA Expendi Sanctio Sanctio Sanctio Sanctio Sanctio Sanctio Released ure Released ture Released ture Released ture Released ture Released ture ned ned ned ned ned ned

UKP Stage- 1 114.00 57.00 155.74 100.00 50.00 92.30 100.00 50.00 77.58 100.00 100.00 116.40 100.00 100.00 187.80 200.00 200.00 235.33 I Phase-III

2 UKP Stage-II ------250.00 250.00 534.10

3 Malaprabha 3.00 1.50 5.12 24.00 12.00 14.92 20.00 10.00 22.64 27.00 13.50 9.87 - - 5.15 20.00 10.00 15.87

4 Hirehalla 5.50 2.75 11.35 6.00 6.00 17.12 6.00 6.00 12.06 8.00 8.00 15.82 8.00 8.00 22.68 10.00 10.00 11.41

5 Ghataprabha - - - 30.00 15.00 20.47 25.00 12.50 28.82 40.00 20.00 20.04 45.00 45.00 26.96 30.00 5.00 72.77

6 Karanja - - - 15.00 7.50 15.68 16.00 16.00 29.95 15.64 15.64 28.48 18.00 18.00 25.67 20.00 10.00 26.55

7 Gandhorinala ------15.00 7.50 15.35

8 Maskinala ------

Total 122.50 61.25 172.21 175.00 90.50 160.49 167.00 94.50 171.05 190.64 157.14 190.61 171.00 171.00 268.26 545.00 492.50 911.38

Contd....

16

2002-03 2003-04 2004-05 2005-06 2006-07 2007-08

Sl. Project CLA CLA CLA No CLA CLA CLA CLA Expe CLA Expe CLA CLA Expe CLA Sanc CLA Expen Expendi Sanc Sanc Expen Sancti Releas Sanctio Relea ndit Rele ndit Sancti Rele ndit Rele tione Released diture ture tione tione diture oned ed ned sed ure ased ure oned ased ure ased d d d

UKP Stage-I 115.8 1 181.00 181.00 214.69 - - 94.19 115.85 92.18 39.01 - 61.13 74.87 71.64 46.19 94.46 71.23 49.30 Phase-III 5

UKP Stage- 2 275.05 275.05 352.29 163.48 163.48 236.48 241.22 240.72 268.17 204.22 197.76 272.29 168.77 172.5 234.58 131.66 102.1 86.80 II

3 Malaprabha 25.56 25.56 14.45 - - 14.42 12.00 12.00 19.64 20.00 20.00 19.62 54.00 13.50 31.28 60.27 54.24 56.37

4 Hirehalla 9.90 8.78 11.69 14.71 14.71 9.94 12.84 - 18.45 ------

Ghataprabh 5 75.00 75.00 57.57 13.01 13.015 55.45 62.09 62.09 64.68 65.00 65.00 92.47 123.21 30.81 77.29 99.33 72.61 76.90 a

6 Karanja 34.37 34.37 23.62 75.27 75.27 18.64 ------

7 Gandorinala 17.87 17.87 16.82 - - 10.09 19.05 19.05 12.34 8.47 8.47 27.73 55.87 45.53 34.96 - - -

8 Maskinala 3.22 3.22 1.87 - - 1.36 ------

9 Varahi ------18.25 - 32.85 24.50 22.05 8 1.22

Total 621.97 620.85 693.00 266.47 266.48 440.57 463.05 449.71 475.46 336.70 291.23 473.24 494.97 334.00 457.15 410.22 322.20 350.59

Contd…

17

2008-09 2009-10 2010-11 2011-12 CLA CLA CLA CLA Sl. No Project CLA CLA Expenditu CLA Expenditu CLA Expenditu Sanctio Expenditure Sanction Sanction Sanctione Released Released re Released re Released re ned ed ed d UKP Stage-I 212.0 1 102.14 91.92 139.36 169.97 154.16 44.25 0.00 91.05 149.45 134.50 38.65 Phase-III 6 166.8 119.5 130.8 2 UKP Stage-II 44.14 8.019 176.72 94.45 93.02 67.65 150 - - 8 5 4

3 Malaprabha 33.94 30.54 27.72 135.00 110.53 28.20 56.20 0.00 94.81 100.80 90.72 79.20

4 Hirehalla ------115.5 5 Ghataprabha 57.82 52.04 44.56 99.05 56.16 65.22 22.89 20.60 84.22 - - 4

6 Karanja 15.78 12.25 10.78 - - 8.27 4.88 0.00 21.92 16.95 - 7.07

7 Gandorinala 18.02 - 17.97 18.52 18.52 23.79 ------

8 Maskinala ------9 Varahi 22.41 20.17 64.76 29.24 26.32 49.68 5.70 0.00 41.76 8.73 - 18.91 10 Bhima LIS - - - 65.16 58.64 30.18 59.35 52.62 38.37 50.38 45.34 53.36 Guddadamall 11 - - - 36.00 32.40 6.66 27.60 24.84 31.59 31.90 - 21.43 apura LIS Srirameshw 12 90.00 - 29.91 ara LIS(N) UpperMulla 13 7.25 - - mari(N) Chanrampa 14 3.62 - - lli(N) Hattikuni 15 6.075 - - (N) Total 294.25 214.94 481.87 660.90 549.75 323.90 555.56 248.06 523.27 465.16 270.56 494.91

Contd…

18

2012-13 CUMULATIVE

Sl.No Project CLA Sanctioned CLA Released Expenditure upto 03/13 CLA Released Expendi ture

1 UKP Stage-I Phase-III - - - 1377.30 1749.40

2 UKP Stage-II - - - 1652.64 2515.92 3 Malaprabha 109.21 98.29 80.35 502.38 543.42 4 Hirehalla - - - 64.24 130.52 5 Gandhorinala - - - 116.94 159.92 6 Maskinala - - - 3.22 3.23 4 Ghataprabha - - - 544.82 910.09 5 Karanja - - - 189.03 219.08

6 Varahi 12.88 11.59 63.17 80.13 360.65

7 Bhima LIS 47.58 - 76.11 156.60 201.55

8 Guddadamallapura LIS 31.81 - 5.90 57.24 65.58

9 Srirameshwara LIS (New) 86.40 - 70.32 - 100.23

Upper Mullamari 10 7.25 - - - - (ERM – New) Chandrampalli 11 3.62 - 1.90 - 1.90 (ERM – New) Hattikuni 12 6.08 - 0.80 - 0.80 (ERM – New)

Total 304.83 109.88 298.55 4744.54 6962.29

19

DETAILS OF PROJECTS ASSISTED UNDER Hon'ble Prime Minister's Special Package (As on 31-03-2013) (`. in Crores)

2007-08 2008-09 2009-10 2010-11 2011-12

Sl.No Project CA CA CA CA CA CA CA CA CA Expendi CA Expendi Expendi Expen Expendit Sancti Releas Sancti Sanctio Release Sancti Releas Sanctio Releas ture Released ture ture diture ure oned ed oned ned d oned ed ned ed

1 Hipparagi - 52.84 78.50 115.36 80.87 99.05 114.78 124.24 281.20 281.20 348.28 143.36 129.03 244.74

2 Votehole 0.29 1.62 ------

Modernisation 3 - 220.88 45.26 32.44 127.93 47.64 108.49 258.14 58.98 0.00 147.10 58.49 52.64 225.46 of Bhadra 4 Dudhganga - 5.49 1.22 3.83 11.68 3.01 0.00 9.10 4.08 3.67 6.21 0.42 - 7.84

ERM of 5 Bheemasamudra ------4.30 3.48 0.00 4.30 0.00 0.00 4.00 - 2. 00 tank

Total 0.00 0.29 280.83 124.98 151.63 220.48 154.00 226.75 391.48 348.56 284.87 501.59 206.27 181.67 480.04

2012-13 CUMULATIVE

Sl.No Project CA CA CA Expendi Expendi Sancti Releas Releas ture ture oned ed ed 1 Hipparagi 105.10 94.59 319.76 734.96 1170.73

2 Votehole - - - 0.29 1.62

Modernisation 3 3.20 2.88 30.08 196.45 1009.59 of Bhadra 4 Dudhganga 1.49 - 9.22 7.50 49.54

ERM of 5 Bheemasamudra - - - 3.48 2.00

tank

Total 109.79 97.47 359.06 942.68 2233.48

20

6. SPECIAL DEVELOPMENT PLAN (SDP)

As per the recommendations of High Power Committee for redressal of regional imbalances, exclusive allocation is made available to irrigation sector for early completion of on-going major & medium irrigation projects in the backward districts of the State. Budget allocation to Water Resources Department for the year 2012-13 under Special Development Plan is `. 600.00 crores, break up is as follows:

KBJNL `. 105.00 Crores KNNL `. 310.00 Crores CNNL `. 110.00 Crores CADA `. 75.00 Crores TOTAL `. 600.00 Crores

(`. in lakhs, Potential in Ha.)

Annu al Programme for Progress upto Reven 2012-13 03/2013 Sl ue District Taluk Name of the project Phy. No divisio Fin. Fin. Phy. Progre n Progress ss 1. KRISHNA BHAGYA JALA NIGAM (KBJNL) Ramp Raichur Devdurga NRBC Dy 9A 240.00 1200 3046.94 0 ur Bidar Bhalki Jeragihal Barrage 300.00 0 709.53 0

Bidar Bhalki Manikeshwar Barrage 260.00 0 535.68 0 1 B.gudi Bidar Aurad Halhalli Barage 1000.00 0 2222.88 0

Bidar Aurad Chandapur Barrageq 50.00 0 11.63 0

Sub Total 1850.00 1200 6526.66 0 Bagalakot Hungund Morol LIS 7500.00 8000 5814.35 4715 Almatt Bagalakot Rolli-Mannekere LIS 400.00 2300 494.61 1350 2 i Bagalakot Bilagi Teggisiddapura LIS 750.00 2000 1213.44 0 Sub Total 8650.00 12300 7522.40 6065 TOTAL KBJNL 10500.00 13500 14049.06 6065

2. KARNATAKA NEERAVARI NIGAM LIMITED (KNNL) Gulbarga Afzalpur Amarja 2000.00 1136 2327.78 292 Aland

Gulbar Chincholi LMP 800.00 952.91 1 ga Gulbarga Gandorinala 200.00 1013.62

Chittapura Bennithora 1000.00 459.71

Bellary Hadagali Singatalur 13500.00 11645 33415.29 9297 Total Gulbarga 17500.00 12781 38169.31 9589

N.R pura Chikkamagalore Tarikere Challakere Bangal Hosadurga 2 Chitradurga Upper Bhadra Stage-I 13200.00 0 15343.11 0 ore Chitradurga Hiriyur Tumkur Sira Kolar Chikkaballapur Mysor 3 Chikkamagalur Tarikere Ubrani Amrutapura 300.00 0 868.30 0 e Total Bangalore & Mysore 13500.00 0 16211.41 0.00

TOTAL KNNL 31000.00 12781 54380.72 9589

21

(`. in lakhs, Potential in Ha.)

Annual Progress upto Programme for Sl Revenue Name of the 03/2013 District Taluk 2012-13 No division project Fin. Phy. Fin. Phy. Progress Progress 3.CAUVERY NEERAVARI NIGAM LIMITED (CNNL)

1 Mysore Halebeedu- Belur 300.00 0 133.06 - LIS

Mod. Of Kodloor Belur 150.00 0 248.89 - anicut channel Hassan Mod. Of Kithur Belur 50.00 0 0.00 - anicut channel

Filling up of Channarayapatna 500.00 0 0.99 - Nuggehalli Tank

Chamraj Kollegal Hubbehunasekere 150.00 364 0.00 0 nagar

Filling up of Nanjangudu, Gundalpate and Mysore Nanjangudu chamrajnagar 7500.00 0 9580.19 - taluk tanks & Sujjalur Branch canal

Imp to Hemagiri K.R.Pete 1800.00 0 1690.23 - Canal

Restoration of K.R.Pete Halemadapura 150.00 0 155.27 Mandya canal Chikkaballi Pick Maddur 100.00 0 0.00 up Imp. To B.halli & Maddur 100.00 0 82.00 C.halli canals TOTAL 10800.00 364 11890.63 2 Bangalore Thumkur Gubbi Filling up of 200.00 0 288.66 Doddaguni Tank TOTAL 200.00 0 288.66 0 TOTAL CNNL 11000.00 364 12179.29 0 TOTAL W.R.D (1+2+3) 52500.00 26645 80609.07 15654

Cammand Area Development Authority (CADA): Annual Programme 2012-13 Progress upto 03/2013 Works Financial Financial Physical Physical (In Lakhs) (In Lakhs) FIC (Hectares) 416.72 6037 156.63 2088 Ayacut Roads (Km.) 6952.28 1360 2139.34 534.62 FDC (Hectares) 55.00 1375 8.77 219.00 Correction of System 76.00 1267 0.00 0.00 Deficiency Total (CADA) 7500.00 2304.74

22

7. WATER RESOURCES DEVELOPMENT ORGANISATION

VISION AND MISSION OF W.R.D.O.:

This Organisation is incharge of Planning and Investigation of all Major and Medium Irrigation Projects in the State and provides all the information to the Government in respect of Inter State Water Disputes like Cauvery, Krishna, Godavari and Mahadayi. This Organisation acts as a data Bank for all Hydrological details of Rivers and streams in the State by collecting and processing the rain gauge and River gauge data in a systematic manner. This Organisation provides information regarding completed, ongoing and proposed irrigation projects of the state. This organisation prepares Catchment Area Maps indicating influencing rain gauge stations, digital maps of all hydro meteorological stations of Karnataka state, command Area Maps of completed, ongoing and proposed irrigation projects coming under Cauvery and basin using the latest software viz., GIS, Remote sensing and Autodesk map. The work of monitoring and evaluation of existing and ongoing projects and safety aspects of dams are monitored by this organisation. In addition, the establishment matter of Irrigation zones regarding postings, transfer of staff and Regularisation of Daily Wages and Monthly Rated Staff as per Supreme Court order is also attended to by this Organisation.

OBJECTIVES OF W.R.D.O.

1. PLANNING AND INVESTIGATION UNIT: The vision of this organisation is to identify the sources of water to meet the increasing demand of the various user sectors of water and to formulate technically and economically feasible water resource projects with reference to availability of water and allocated water. The target is to bring out more areas under irrigation. The objectives of P & I unit are as below: Examination of feasibility in respect of representation received for the proposals of Major and Medium irrigation projects, Hydro electric projects, industrial water requirement, scheme for drinking water supply etc., Preparation of Preliminary Investigation Report of Major and Medium Irrigation Projects based on site inspection and top sheet studies and submission to Government for approval. Consequent to approval of Project Report by Government, preparation of Detailed Project Report after conducting detailed surveys by using modern techniques: Priority accorded for supply of drinking water in drought prone areas while taking up Irrigation Projects as per the guidelines issued by Ministry of Water Resources, Government of India. The projects which are under investigation stage are as follows:-

 Flood Flow Canal to feed water to the suffering atchcut of TLBC and provide irrigation facility.  Proposal for diversion of Potential Flows of certain West Flowing streams in upper catchment for improvement of drinking water and ground water recharge in drought prone Districts.  Kakkatuhole and Kanganahole Diversion Project to provide water supply.

2. GEOMATICS CENTRE:

To overcome the problems of completing the Water Resources Investigations within the time frame, due to reduced technical manpower in the Department to undertake detailed survey work and to avoid outsourcing to private organization resulting in increased cost of the projects. The Geomatics Centre was established in Water Resources Development Organization on 21-7-2001 as per the G.O No.ID/50/MBI/2000, Bangalore Dated 4-5-2001. With an intention of adopting the modern techniques in Planning and Investigation namely.

23

1. Remote Sensing 2. Geographical Information System 3. Global Positioning Systems. Subsequently the centre has been equipped with required Hardware & Softwares. Vision and Mission

1) Data base of Water Resources Information System from micro to macro level which includes Integration of entire water availability, utilization and requirement etc., can be generated. 2) A data base indicating each revenue survey boundary under the atchkat, can be generated using R.S. & GIS technology. 3) Silt and sedimentation estimation of reservoir can be taken up using remote sensing application. 4) Project wise planning & water budgeting can be made for optimum utilization of the water as per State Water Policy.

3. HYDROLOGY UNIT: To assess Water Resources in Karnataka State in a scientific manner, the studies of flow data at various points in different river basins and rainfall data are most essential. As such, the Government of Karnataka has established a separate Hydrology Unit under Water Resources Development Organization, with the responsibility to collect data from various gauging stations spread all over the State for analyzing and validation of Hydrometric and Hydro meteorological data.

The following Meteorological stations are working under the Jurisdiction of WRDO:

A. Hydrological Stations:

1. Current Meter Gauging Stations - 31 2. Stage Discharge Stations - 10 3. River Gauging (measured over weir) - 01 4. Silt and Sedimentation observations stations - 17

B. Hydro meteorological Stations:

1. Fully Climatic Stations - 87 2. Autographic Rain gauge Stations - 166 3. Standard Rain gauge Stations 758

The data obtained from these Hydrological and Hydro meteorological stations are scrutinized, analyzed and processed. The data of Rain gauge Stations maintained by Water Resources Development Organization are published by the Department of Economics and Statistics after obtaining the data from the concerned Tahasildar office’s of the respective Taluks. Also the daily inflow, outflow of the major and medium reservoirs, weirs and anicuts are collected from respective zones and are being processed. Besides this, yield studies are being carried out for the irrigation, drinking and power projects. H.M.datas are being sent daily to KSNDMC.

24

The unit is also involved in review of the Hydrological aspects of 236 dams coming under the large dams category and these studies are being sent to IMD and then to CWC for getting approval.

Establishment of new rain gauge stations.

Water resources Department has taken up identification of unrepresented area where there are no rain gauge stations. The proposals are being examined as per the IMD norms for setting up of new rain gauge stations for accurate rainfall data collection by Geomatic Centre of WRDO.

4. MONITORING AND EVALUATION UNIT: Evaluation and review of safety of large dams in the State coming under Major, Medium and Minor Irrigation Zones is being carried out under the guidance of Dam Safety Review Panel Constituted under Chairmanship of Ex-chairman Central Water Commission and consisting of Panel of Experts. Monitoring and submission of details of financial progress of NABARD assisted major, medium and minor irrigation projects (including CADA Projects) in the State with the guidance from High Level Committee formed under the Chairmanship of Development Commissioner, Government of Karnataka Consolidation and submission of comprehensive report to Government on the year wise area irrigated and demand raised from all irrigation projects of the Department. Collection of data from project authorities under NPDP.

5. KRISHNA - GODAVARI UNIT: The Krishna Godavari unit in Water Resources Development Organisation under the Water Resources Department is working to resolve the Inter State Water Disputes aroused in the wake of the Orders of the previous Krishna Water Disputes Tribunal and Godavari Water Disputes Tribunal by collecting data, analyzing and to obtain State’s sharing surplus waters. Mahadayi and other Inter Water State Disputes (except Cauvery Disputes) are dealt in this unit.

This unit looking after the issues pertaining to Krishna, Godavari, Mahadayi, Palar and Pennar Water Disputes (Paragodu Drinking Water Supply Scheme) and furnishing information to the legal team in consultation with Technical Committee. The Technical Committee consists of Principal Advisor, Technical Advisor and other Technical Experts are nominated for obtaining technical opinion on Krishna Water Disputes. Services of Technical Committee is being utilised in safeguarding the interests of the State. A team of Advocates including Advocate General of Karnataka is appointed and their services are being utilized to argue the case before Supreme Court/Tribunal and to safeguard the interest of State.

Present status of Water Disputes :- Krishna Water Disputes: • Krishna Water Disputes Tribunal has given its final order on 30.12.2010. As per this order Karnataka State, has been allocated 177 tmc of additional water, in addition to 734 tmc allocated earlier under Scheme-A totaling to 911 tmc. Andhra Pradesh and have been allocated 1001 tmc and 666 tmc respectively.

25

• Tribunal in its final order has given permission to Karnataka State, to increase the height of from 519.6 m. to 524.256 m.

• The State of Karnataka, Andhra Pradesh and Maharashtra have filed reference petition before the Tribunal under Sec.5(3) on the final orders of the Tribunal. Andhra Pradesh State has filed Special Leave Petition before the Hon’ble Supreme Court. References filed before the Tribunal are in progress.

Mahadayi Water Dispute:

• Goa State had filed Original Suit in Hon’ble Supreme Court on 15.09.2006 regarding the Kalasa-Banduri Nala diversion project planned by Karnataka State, to provide drinking water to Hubli-Dharwad towns. Since, the Government of India took the decision to constitute Mahadayi Water Dispute Tribunal, Original Suit filed before the Supreme Court has been disposed of, on 20.01.2011.

• Government of India has constituted Mahadayi Water Dispute Tribunal in its Notification dated:16.11.2010 to resolve the, Water Dispute regarding water allocation between Karnataka, Maharashtra and Goa States. Proceedings of the Tribunal has been started on 06.09.2012 and in progress.

CAUVERY UNIT:

The Cauvery unit of Water Resources Development Organization, Bangalore deals with the matters concerning to the adjudication of waters of the River Cauvery.

The Cauvery Unit was formed in the year 1990 along with the staff of Water Resources Development Organization. It was functioning under the control of Chief Engineer, W.R.D.O., Bangalore. The Cauvery Water Disputes Tribunal was formed by the Ministry of Water Resources, Government of India, New Delhi; vide Order No.21/01/1990 WD dated:02.06.1990 for adjudication of the Cauvery Water Dispute.

For effective participation and pleading of the cases of Karnataka before the Cauvery Waster Dispute Tribunal, the Cauvery Water Cell was established in the year 1990 at New Delhi.

A team of Advocates including Advocate General of Karnataka is appointed and their services are being utilized to safe guard the interest of Karnataka and to substantiate and to establish the stand of the Government before the Supreme Court/Cauvery Water Disputes Tribunal.

Technical Advisors are appointed to get their technical advices in the Cauvery Water Dispute matter. Cauvery Technical Committee is constituted to discuss the developments in respect of CWDT and necessary actions are being taken in order to protect interest of the State.

Present Status of Cauvery Water Disputes:

• Cauvery Water Disputes Tribunal has given its final order on 05.02.2007. In this order Karnataka, Tamil Nadu, Kerala and Union Territory of Pondichery States have been allocated 270 tmc, 419 tmc, 30 tmc and 7 tmc respectively. On the final order of the Tribunal, all the basin states have filed reference petitions before the Tribunal. Karnataka, Tamil Nadu and Kerala States have filed Civil Appeals before the Hon’ble Supreme Court. Reference Petitions and Civil Appeals are yet to be disposed of. • Publication of final order of CWDT dt:05.02.2007 has been done by the Central Government vide GOI Notification dt:19.02.2013. • As per the final order of the Tribunal State has to ensure 192 tmc of water to Tamil Nadu in every water year at Biligundlu.

26

 e– Governance in Water Resources Department:

Planning and Investigation Unit, Water Resources Development Organisation is monitoring the e-Governance activities of entire Water Resources Department in Karnataka. Short-term courses to use Computers for the Technical and Non-Technical staff are being conducting regularly. This Unit manages the Website of Water Resources Department “http://waterresources.kar.nic.in” which includes details of Nigams. The website includes the following data a) Right to Information Act b) Schedule of Rates c) Preparation of material required for National Performance of dam Programme for Dam safety. d) Salient features of Major and Medium Irrigation Projects. e) Hierarchy of Administration in Water Resources Department and f) Tender Bulletins. Other activities: • This Unit corresponds with State & National level Organisations like Central Water Commission, Bureau of Indian Standards, Indian National Committee for Irrigation & Drainage, Water & Power Consultancy Services and Central Board of Irrigation and Power. This Unit attends to the Committee meetings conducted by these Organisations and provides information requested by them. Demarcation of Project and river details of Karnataka on Google Earth is being done by this unit. • This Unit provides information for attending the meetings of Subject Committee, Assurance Committee, Estimate Committee and Petition Committee. This unit prepares Annual Administrative Report and Annual Report pertaining to W.R.D.O annually. This unit provides report regarding Monthly Multilevel Review Meetings to the Government every month.

• This unit deputes officers of this organisation for various training programme, seminar, conference, workshop etc., to update their knowledge regarding latest technology and development in the water resources sector. • This unit attends to the requisitions pertaining to public grievances (d£ÀvÁzÀ±Àð£À ªÀÄvÀÄÛ d£À¸ÀàAzÀ£À ) and submits suitable replies every month in this regard to Secretary, Water

Resources Department and Principal Secretary, Department of Personnel and Administrative Reforms, public interaction cell. • This unit submits draft replies to LAQ, LCQ, Loksabha and Rajyasabha questions from time to time. • Preparation of Preliminary Investigation Report and estimates in connection with rejuvenation of rivers/tributaries for increasing the flow. • Establishing telemetric rain gauge stations in the Netravathy catchment of .

27

8. Central Mechanical Organization

Activities of C.M.O:

The main duties and functions of the organization are briefly as follows: i) Inspection of sick machinery in the Public Works and Water Resource Department and scrutiny / sanction of repair estimates. ii) Disposal of surplus and unserviceable machinery. iii) Rehabilitation of surplus vehicles / machinery. iv) Review of efficiency and performance of machinery. The Central Mechanical organization is striving hard to achieve the aboveobjectives since its inception and the report on the achievements during 2012-13 is as follows:  In order to ensure optimum utilization of machinery, available in Public works and Irrigation department, the monthly returns of machinery of divisions are being obtained and reviewed regularly for its various performance aspects such as: a) fuel usage b) oil usage c) Kms. Run with reference to standards fixed d) idleness surpluses and rehabilitation e) sick vehicles / equipments identification and its speedy repairs f) disposal of unserviceable machinery are reviewed and follow up action ensured until their disposal through Central Mechanical Organization. Major regulatory functions:- To oversee that all the working vehicles/equipments of the department are put to optimum use sick vehicles / equipments are repaired with minimum downtime, economically and for unserviceable vehicles / equipments assist owning departments for the disposal expeditiously to the best advantage of the Government. Strategies for achieving the Departmental objectives :-

1. In order to achieve the above objectives, the monthly returns of machinery, along with requirement and surplus availability details are got regularly from Civil divisions and the same is reviewed. For this purpose presently, computer is being made use of. 2. To exercise economy in carrying out repairs, the estimates so got up is either sanctioned or scrutinized after thoroughly reviewing it. To exercise and review the condition of machinery and also up keeping of driving license, insurance cover, Registration certificate, Fitness certificate etc., by conducting surprise inspections and bringing the lapses to the knowledge of Government. 3 To exercise economy in the fuel and oil consumed by the vehicles/equipments, standard rate of consumption is being stipulated and strictly being enforced. 4 To review the optimum utilization of the available machinery and at the same time arrange for the requirement from out of the surplus availability so that unnecessary purchase is avoided. 5. To monitor the disposal of unserviceable machinery so that the same are expeditiously disposed off to the best advantage of the Government.

28

6. Apart from the Irrigation & PW Departments, this organization assists other Government departments in inspecting sick machinery, repairing the same or scrutinizing the estimates prepared thereby. Major Developments / Highlights of the year :- Apart from the routine repairs works carried out by the sub-divisions of this organization, surprise inspections of vehicles/ equipments are conducted in order to prevent under logging and proper upkeep of the documents of vehicles and such instances if any, are being reported to Government. Achievements during 2012-13:- Sl.No. Particulars Achievements (In No.) I Repairs to Machinery / Equipment (Major and Petty repairs Opening balance as on 01.04.2012 223 Receipts 2380 Total 2603 Repaired and Dispatched (Includes 40 major 2376 repairs) Closing Balance 227 II Inspections : Total Number of Inspections carried 252 out Recommended for repairs 135 Recommended for scrap 117 III Repairs Estimates: Opening balance of - estimates Total number of estimates received 135 Amount (in Lakhs.) Rs. 318.40 Estimates for which Scrutiny certificates are 14 issued. Amount (in Lakhs.) Rs. 11.40 Number of Estimates Sanctioned 121 Amount (in Lakhs Rs. 307.00

IV) In the process of major repairs to vehicles, useful assemblies and accessories of scrapped vehicles were identified and utilized on repairs. V) This organization is also inspecting vehicles / equipment pertaining to Boards / Corporations and Central Government after leying inspection fees. VI) Review has been taken up regarding expenditure incurred on repairs and time taken for such repair in workshops. After detailed review limit has been fixed for expenditure to be incurred on repairs and time limit for carrying out repairs. 4) Disposal of surplus and unserviceable machinery Disposal of unserviceable machinery in Water Resources & Public Works Department which have been recommended for scrap during routine course of inspection. 1) Unserviceable machinery identified for disposal during 2012-13 - 117 Nos. 2) Disposed during 2012-13 - 139 Nos. Revenue Realized - Rs. 81,17,215

29

5) Rehabilitation of Surplus Machinery( 2012-13): The following numbers of vehicles have been rehabilitated to various needy zones: Sl. Zones Car Jeep etc Total No. 1 2 3 4 5 6 01 CMO,B’lore 2 - 2 02 C & B (S), Bangalore 1 - 2 3 03 Minor Irrigation South, B’lore 2 1 - 3 04 Hemavathy Project Zone, Gorur 3 4 - 7 05 Irrigation Central Zone, Munirabad 1 2 1 4 06 HCZ, Tumkur - 1 - 1 07 Others 5 - 1 6 Total 14 8 4 26

Financial Target & Achievement during the year 2012 -13

Achievement on 2012-13( In Grants for 2012-13( In lakhs) lakhs) Sl. Head of No. Establish Establis Account Works Total Works Total ment hment 01 4700-Plan 221.94 200.00 421.94 227.21 50.81 278.02 02 4700-Non plan 301.11 296.84 597.95 301.97 206.63 508.60 03 2702- Plan 70.23 - 70.23 61.64 - 61.64 04 2702-Nonplan - 75.05 75.05 - 31.12 31.12 05 3054-Nonplan - 50.00 50.00 - 50.04 50.04 06 2059-Nonplan ------07 2701-Nonplan 556.16 15.00 571.16 477.76 11.19 488.95 08 2700-Nonplan 214.81 - 214.81 193.32 - 193.32 09 8443-Deposit - - - - - 186.94 Contribution Total 1364.25 636.89 2001.14 1261.90 349.79 1798.63

PROGRAMME AND PROGRESS :-

The programme and progress of workshops carried out is detailed below:------Programme Progress ------Major Repairs and Minor Repairs 120 25 Petty Repairs 3600 2188

30

9. KARNATAKA ENGINEERING RESEARCH STATION

Karnataka Engineering Research Station was started during 1944 as a small Research Unit. The Research Station, which forms a wing of the State Water Resources Department, had a phenomenal growth and today it is one of the oldest Research Organizations of its kind in the country. The main objectives of the Research Station are to find solutions to various problems encountered by the field Engineers in Civil Engineering discipline. The Research Station has solved many intricate problems posed by Public Works Department, Water Resources Department, other Civil Engineering Departments, other agencies etc.

The Director of the rank of Chief Engineer heads the Research Station. He is assisted by the Joint Director, who is also the Principal of Engineering Staff College, which is a wing of K.E.R.S.

The activities of the Research Station are grouped into 4 divisions as under.

 Hydraulics Division

 Technical Services Division

 Soil Mechanics & Foundation Engineering Division

 Coastal Engineering Division

Engineering Staff College:

The Engineering Staff College conducts mainly three types of training Courses.

1. Orientation Courses for newly appointed Assistant Executive Engineers for a period of Six Weeks and for newly appointed Assistant/Junior Engineers for a period of four weeks to 40 days. 2. Short term refresher Courses of five days duration of both technical and administrative nature for the in-service Engineers and administrative staff. 3. Basic Computer Course for a period of 12 days for the in-service Engineers and administrative Staff.

Achievements of year 2012-13 of reporting:-

As Karnataka Engineering Research Station is functioning as a service zone, construction or maintenance of projects does not come under its jurisdiction. Also it is not a major revenue earning zone.

Year 2012-13 :

During the year 2012-13, 258 Nos. of studies covering Hydraulic studies, Rating of current meters (44 Nos), Gauging of canals, Capacity evaluation of reservoirs, Testing of Building

31

Materials, Soils, Water quality testing, monitoring of sea walls, design of sea wall sections etc., referred by different agencies have been completed and reports sent to concerned authorities and 23 studies are under progress. 6 studies are held up for want of details from project authorities and another 4 canal gauging works has been held up, as the Project authorities have not provided necessary infrastructure at the selected gauging sites. Under Hydrology Project 47 studies were completed on the 47 samples received at the water quality lab, K.R.Sagara. In the lab at Munirabad, 16 studies were completed on the 16 samples received for the stipulated 27 parameters. During the year 3 Orientation courses for the Probationary AEE’s, 6 short term courses for Minor Irrigation Engineers and 19 short term institutional courses were conducted and 660 candidates were trained. Further 35 CEP courses, 5 SCP Courses and 1 TSP Course were conducted and 554 candidates were trained. Totally 69 courses were conducted and 1214 candidates were trained during the year up to end of March 2013.

Important studies / works undertaken during the Year :

 Hydrographic survey reports of major and medium reservoirs viz Marconahalli, Votehole , Tonnurkere, Krishnarajasagara, Harangi, Hemavathy, and Kabini reservoirs are completed and survey reports have been finalised.

 Report on the existing (Old heritage structure of about 17th century) head regulator of Virija Canal located on the right bank of Virija Anecut on the down stream of Krishnarajasagara Dam.

 Taking up river training works on u/s and d/s sides in respect of Barrages under construction across a river Manjra in Bidar District.

 Preliminary report on Model Study of Delivery Arrangement from Pump House for Upper Bhadra Project – the work of lifting 21.5 TMC of water from Bhadra Reservoir to delivery chamber near Ajjampura (Package II)

 Gauging of Tungabhadra Left Bank Canal at Mile 2, 24, 36, 47 and 69 were completed.  Gauging of Sri. AGR Canal at Ch 102 nd mile and BNT chainage 205 th m and ACC canal gauging at 76 th km have been completed.  Guaging of Tungabhadra left bank distributary and Sub distributary canal at Karatagi has been completed.  Four survey works were taken up in Mangalore and monitoring report has been submitted.  Providing protection for sea erosion at Manki Doddagunda in Honnavara Taluk, and Dhareshwara in Kumta Taluk of Uttara District were monitored.  21 sea walls in Bhatkal Taluk, 27 works in Kumta and 32 works in Honnavara Taluk were monitored.  Survey work was conducted for the design of sea wall at Bykampadi village near Menakaliya Kurikatta at ch.22.775- 22.925 Km (150m) and design was submitted.  Survey work was conducted for the design of sea wall at Taluk at Koderi at ch.124.550- 126.810 Km (2260m) and design was submitted. 32

 “Study of water quality in rivers of southern Karnataka” PDS study taken up under HP-2 has been completed and the report was finalised.  Effect on quality of rivers due to return flow from irrigated land ( Cauvery River between K.R.Sagara and T. Narasipura ) is under progress.  Evaluation/assessment of properties of concrete using manufactured sand and natural sand under progress.  The Regional flood frequency analysis of Krishna, Cauvery (modified) and west flowing river basins are completed.  Testing for SBC of soil sample of the retaining wall to be constructed near Lokapavani river near Chennenahalli village.  Test on soil sample of the Adagore tank near Hassan district.  Test on soil sample of Ayyanakere left side embankment from ch 0.00 to 300.00 m near Kadur taluk, Chikamagalur.  Test on soil sample for swelling pressure of kattepura Right bank canals CC lining.  Test on swelling pressure of soil sample near proposed sopana constructed across kabini river at Gaddanpura village, Najangud taluk.  Test on soil sample for the Fishing harbour in connection with construction of seawall to prevent sea erosion at Byandur assembly constituency.  Test on swelling pressure of soil sample of the Dangere Jagiddar canal from ch 0.00 to 10.00 km.  Testing of quality of gravels for the construction of PHC at Beluru in HD kote taluk.  Test to determine SBC of soil sample for construction of buildings near koorgalli, Mysore pertaing to MMG construction private limited.  Test to detemine SBC of soil sample for the construction of Aqueduct pertaining to Karigatta lift irrigation scheme, Srirangapatana.  Test on SDBC samples recevied from M/S Mysore race club limited, Mysore  Test on Road aggregate & bitumen for road work pertaining to AEE,No 32 ,Hemavathi left bank canal Division CNNL.(Basaralu road)  Test on Soil and Aggregate samples from M/S Larson & turbo Mysore.  Studies on soil samples of road work for the M/S Shonan Engineering work Pvt Ltd.  Quality checks for road work for SBC on samples in Mysore race club area.  Quality checks for road in Mysore race club limited, mysore.  Quality check on road materials on improvements of road at APMC, Bandipalya  Quality checks on Bitumen for service road improvement at 15th Mile of V.C Canal, Pandavapur taluk.  The Emergency (8 th Special) Meeting of State Level Dam Safety Committee (SLDSC) was convened on 03-12-2012 at Bangalore.  Proposals for the constitution of the “Technical Sub-Committee of SLDSC” to ensure the completion of Hydrological Review and finalization of Emergency Action Plan of Large Dams in Karnataka has been submitted to the Government vide Member

33

Secretary, SLDSC’s ltr No 5531-32 dt 15-03-2013, after conducting two meetings respectively on 26-02-2013 and 12-03-2013 in this regard.  A workshop on ‘‘Advanced Techniques in Water Resources Management’’ was conducted on 24th and 25th January 2013 at KERS, K.R.Sagara in association with Task Force, Bangalore.  Foreign delegates from Afro-Asian countries visited KERS on 22-03-2013.  Grant of Rs. 250 lakhs has been released for the year 2012-13 under the plan head in connection with strengthening of the Research Station. a) Civil works such as providing grills to the lawn in front of ESTC and hostel building and laying granite tiles to the main building entrance lobby were completed. Construction of open type dining hall in the existing hostel is in progress.

b) Tender process for the construction of new Hostel building @ KERS has been completed and work has to be commenced.

Activities of Dam Safety Cell-1 :

The Dam Safety Cell is assisting the Member Secretary, State Level Dam Safety Committee in Karnataka in the following activities in respect of Dam Safety issues: 1. Communicating the deficiencies observed in the Health Status reports of Large dams to the Chief Engineers, concerned., 2. Preparation of Health Status Report of Large Dams in Karnataka to place the same before the State Level Dam Safety Committee in Karnataka. 3. Finalisation of the draft compliance for the minutes of the National Committee on Dam Safety. 4. Finalisation of the Additional Note on Agenda for the ensuing meeting of NCDS.

5. Pursuing the Chief Engineers in-charge of Large dams to send the following.

a) Pre/Post monsoon Inspections reports of Large dams b) Compliance to the minutes of the NCDS. c) Other details keeping in view the proceedings of NCDS / SLDSC and the “Terms of reference of SLDSC”. 6. Correspondence pertaining to DSRP.

Activities of Dam Safety Cell-2 :

The Dam Safety Cell-2, attached to the Director, Karnataka Engineering Research Station, comprising of One Assistant Executive Engineer, including 3 Assistant Engineer’s, 3 Junior Engineer’s and supporting administration staff has been created by the Government, vide Government Order No. WRD-60 /¸ÉøÀJ / 2009 dt: 06-07-2009 ( read with modification letter No. WRD 60 /¸ÉøÀJ / 2009 dt: 03-08-2009), is assisting the Member Secretary, State Level Dam Safety Committee(SLDSC) in Karnataka, in carrying out the following functions from 01-06-2009., 34

• To prepare the Agenda Notes for the meetings of the State Level Dam Safety Committee (SLDSC) before the meeting and to prepare the Draft Proceedings after the meeting and to submit the same to the Government for confirmation • Communicating the copies of the approved proceedings to all the concerned and to pursue them for communicating compliance. • To pursue with all the concerned to communicate the “Technical Preparedness” of the zone / organization ( as appropriate) for the Draft Dam Safety Act and to place the same for discussions before the special meeting of State Level Dam Safety Committee (SLDSC) to finalise the Technical Preparedness of the whole State for the “Dam Safety Bill-2010”. • To place the issues pertaining to the following for discussions in the Special Meeting of State Level Dam Safety Committee (SLDSC), viz., a) Action to be taken at various level after the enactment of the “Dam Safety Act”.

b) Action to be taken at various levels regarding the “Public Interest Litigations” ( if any).

Progress Achieved By Engineering Staff College during the year: During the year 3 Orientation courses for the Probationary AEE’s, 6 short term courses for Minor Irrigation Engineers and 19 short term institutional courses were conducted and 660 candidates were trained. Further 35 CEP courses, 5 SCP Courses and 1 TSP Course were conducted and 554 candidates were trained. Totally 69 courses were conducted and 1214 candidates were trained during the year up to end of March 2013. Remarks No.of courses Category of No.of No.of Sl. conducted training courses persons No upto 31st programme proposed trained March 2012

As per the Govt. orders orientation courses for the Institutional Probationary AEEs were 1. 36 19 346 courses conducted. Further short term courses (10 nos) were not conducted due to the shortage of trainees. Hence Special course 09 09 314 target could not be achieved. 2. CEP 35 35 470 - 3. SCP 05 05 77 - 4. TSP 02 01 07 -

35

10. WATER AND LAND MANAGEMENT INSTITUTE (WALMI)

Introduction: To maximize returns from investments made in irrigation projects in the State, it is necessary to manage water and land in a systematic and scientific way. This requires capacity building of Government Staff as well Water Users. To meet these capacity building needs, Water and Land Management Institute (WALMI) started functioning at Dharwad on 12-5-1986 and was later registered as a Society under the Karnataka Societies Registration Act, 1960 on 16.06.1986. WALMI: imparts training; renders technical assistance, advises Government on legal, policy, organizational and procedural changes; organizes demonstrations in collaboration with other organizations; conducts special studies and brings out publications. Training: WALMIs training activities focused on the training required for implementation of the State Water Policy and the Irrigation Sector Reforms. Special emphasis was laid on training on Participatory Irrigation Management, Water Management and Land Development. WALMI had planned to impart training to 1835 persons during the year. However, due to increased demand for training 3180 staff and farmers were trained during the year. The Institute rendered technical assistance and guidance for implementation of Participatory Irrigation Management to: Water Resources Department, Nigams, CADAs and Water Users Cooperative Societies.

Technical Assistance: WALMI rendered technical assistance to the Water Resources Department and organizations coming under the Department on implementation of State Water Policy, Participatory Irrigation Management and necessary legal and policy changes.

Demonstrations in Collaboration with the University of Agricultural Sciences, Dharwad: Demonstrations pertaining to irrigation methods for different crops- Cotton, Soyabean, Paddy, Sunflower, Wheat, Maize, Groundnut, Guava, Mango, Sapota and vegetable crops were laid. Water saving technolgies like drip, sprinkler and Raingun were demonstrated in the WALMI Farm to support training activities. In collaboration with the University of Agricultural Sciences Dharwad, WALMI has laid out demonstrations in WALMI Campus to support the training. Demonstrations laid are on: irrigation methods for sunflower, maize, wheat, groundnut crops; Sustainable Sugarcane Initiative; Preparation of vermi compost and organic farming.

Action Research: As per orders issued in Government Order No. WRD 14 CAM 2009, dated 02.12.2009, action research on participatory and sustainable water and land management is undertaken in selected distributaries of the Malaprabha and Ghataprabha projects. A support group comprising of all departments concerned with irrigated agriculture is constituted to implement the project. The activities are coordinated by the Director, WALMI. Action research studies were completed in Malaprabha and Ghataprabha Projects. WALMI was coordinating implementation of studies on participatory and sustainable water and land management being implemented by a Consortium comprising all Departments/Organisations and Water Users.

Financial Progress: During the year 2012-13, grant-in-aid of Rs 182.00 lakhs under 2705-00-800-1-03 Command Area Development Expenditure was Rs.183.76 lakhs was incurred during 2012-13.

36

PROJECTS UNDER

KRISHNA BHAGYA JALA NIGAM LIMITED

37

HIGHLIGHTS OF KRISHNA BHAGYA JALA NIGAM LIMITED FOR THE YEAR 2012-13

1. Upper Krishna Project Stage – III:

Krishna Water Dispute Tribunal-II passed an award on 30.12.2010 allocating 177 TMC of water to Karnataka State. The allocation for UKP Stage – III is 130.90 TMC. It is contemplated to provide irrigation for 5.30 lakh Ha. command area coming under Bijapur, Bagalkot, Gulbarga, Yadgir, Raichur, Koppal and Gadag Districts of Northern Karnataka. Government vide G.O. Dtd:24.01.2012 had accorded administrative approval to the UKP Stage-III for an estimated cost of `.17,207.00 Crores (PL 2011-12). The progress made under project components of UKP Stage-III during 2012-13 are as under :

(a) Mulwad LIS : The Head Works of Mulwad LIS Stage – III namely; (a) Balance electromechanical works under Baluti 1 st Head Work, (b) Balance civil and electromechanical works under Hanumapur 2 nd Head Work, and (c) Masuti 3 rd Head Work were awarded on turn key basis and the works are in progress.

(b) Chimmalagi LIS : The Head Work for 1 st Phase (4,614 Ha.) on turn key basis is completed and commissioned during January 2013. The balance civil and electromechanical works of the Head Work awarded on turn key basis is in progress. The Combined canal of 2.10 Km and West Main Canal Km 0.00 to 20.00 including Distributaries thereunder are completed and water letout for irrigation. Further, West Main Canal Km 20.00 to 51.92 and East Main Canal Km 0.00 to 50.00 awarded on tender basis are progress. Tenders for East Main Canal from Km 50.00 to 90.00 are invited and work in process.

(c) Mallabad LIS : The construction of 1 st Head Work at Balabatti at Km 20.90 of JBC awarded on turn key basis is in advance stage of progress. Also, the Main Canal Km 0.00 to 4.00 under 1 st Head Work is in progress. For the 2 nd Head Work on MBC at Km 20.00 work to be awarded. The 3 rd Head Work on SBC at Km 5.40 is in progress.

(d) Indi LIS Extension : Indi LIS Main Canal Km 97.30 to 110.00 completed and water is letout for irrigation. Further, Main Canal from Km 110.00 to 120.00 are in advance stage of completion. Tenders received for Km 120.00 to 135.00 under 2 packages and to be awarded.

(e) Rampur LIS : The extension of East Main Canal from Km 20.00 to 27.00 including Disty.No.10 and 11 and Tail end distributary taken up on tender basis are in various stages of progress.

38

(f) Koppal LIS : Tenders for 1 st and 2 nd Head Works on turn key basis have been received it is to be awarded. Topographical survey of contemplated command is completed. Government vide G.O. Dtd:09.01.2013 has accorded approval for adopting Micro-irrigation System under Koppal LIS.

(g) Herkal LIS : The detailed estimates for Herkal (North) and Herkal (South) LI Schemes on turn key basis have been finalised and tenders to be invited.

(h) NRBC Extension: Topographical survey of command area coming under NRBC Extension is completed. Tenders invited for NRBC Main Canal from Km 95.00 to 105.00 under two packages.

(i) Rehabilitation Resettlement, LAQ and BTDA works under UKP Stage-III:

(a) FRL Survey at Almatti Reservoir using 3D LiDAR Technology is completed. (b) The work of base-line socio-economic survey and preparing R&R frame work for UKP Stage-III through consultancy is nearing completion. (c) For the development of infrastructure facilities at Unit-II of Navanagar, Bagalkot viz; Water Supply, Storm Water Drain, Roads, UGD System and Electrification works, tenders have been received and to be awarded.

2. Projects completed during 2012-13 :

(a) Bridge-cum-Barrages across river Manjra :-

Bridge-cum-Barrages across River Manjra at Jirgihal, Manikeshwar and Halhalli in Bidar District have been completed during 2012-13. The farmers have to lift water with their own pumpsets for irrigation from the storage in these barrages.

(b) Gugal Bridge-cum-Barrage across River Krishna :

The Gugal Bridge-cum-Barrage across River Krishna near Gugal village of Deodurga taluk in Raichur District is completed. The storage in this barrage is being utilized by the farmers with their own pumpsets for irrigation. This barrage also provides communication between Yadgir and Raichur districts.

39

(c) Sonthi Bridge-cum-Barrage across River Bhima :

The Sonthi Bridge-cum-Barrage across River Bhima is completed including erection of 37 vertical gates. This Bridge-cum-Barrage will facilitate providing irrigation for 16,000 Ha. of command in Gulbarga and Yadgir Districts for utilizing 4.00 TMC of water through Sonthi LI Scheme taken up for implementation on the upstream of Sonthi Barrage.

(d) Rajankollur LIS :

This L.I.scheme off-takes down stream of Rajan-kollur Tunnel at Km 40.06 of of NLBC. The scheme is completed and commissioned. The scheme envisages providing irrigation for 1,100 Ha. of command area in Shorapur taluk of Yadgir district.

(e) Filling up of MI Tanks in Bijapur and :

This scheme envisage filling up of 16 MI tanks and 5 bandaras in Bijapur district and 7 MI tanks in Bagalkot disctrict by lifting water from River Krishna in two stages. The scheme is commissioned during January 2013 and trial run conducted.

(f) Bonal LIS :

This scheme is completed and commissioned and is envisaged for providing irrigation to the suffering command of 5,400 Ha. at the tail end of SBC Disty.No.6 of UKP. The scheme draws water from Bonal tank in Shorapur taluk of Yadgir district.

(g) Remodelling of NLBC Main Canal :

The remodeling of NLBC Main Canal from KM 40.00 to 72.00 (selected reaches) has been carried out in the closure period from April to June 2012 and water letout in the Main Canal during Khariff 2012.

3. Acclerating Progress of Project works: The progress of Project works under Ramthal (Marol) LIS 1 st Stage, Thimmapur LIS, Teggi-Siddapur LIS, Rolli- LIS, Sonthi LIS and NRBC Distry.No.9A works have been expedited.

40

4. New initiatives :

(a) Improvement of Water Use Efficiency in NLBC command of UKP :

Government of India has launched National Water Mission, the major objective being is to improve water use efficiency. KBJNL has proposed a project for improving Water Use Efficiency in Narayanapur Left Bank Canal command area under UKP covering command area of 4.09 Ha. of NLBC, SBC, MBC, IBC and JBC canal systems spread over in Bijapur, Gulbarga and Yadgir districts.

Ministry of Water Resources (MOWR), GOI vide letter dated 09.05.2012 have given direction to prepare the DPR for Narayanapur Left Bank Canal – Water Use Efficiency (NLBC-WUE) project under National Water Mission. Also, the Central Water Commission, GOI vide letter dated 17.08.2012 has conveyed ‘in-principle’ consent to the State Government / KBJNL for preparation of DPR for Extension, Renevation and Modernation (ERM) project of NLBC under AIBP at an estimated cost of Rs.3060.00 Crores. The project targets achieving Water Use Efficiency by 25%. The detailed DPR for NLBC- ERM project at an estimated cost of Rs.4103.50 crores has been submitted to CWC, New Delhi during March 2013. The proposal is under examination in MOWR, GOI. The approval to the proposal will facilitate availing 90% central assistance unde Acclerated Irrigation Benefit Program (AIBP) and for the upliftment of economic status of farmers in the command area of UKP coming under Gulbarga, Yadgir and Bijapur districts of Northern Karnataka by resolving the problems faced by tail end farmers.

The DPR for NLBC-WUE project with Micro Irrigation component at an estimated cost of Rs.2368.00 crores is under finalization for submission to Government of India.

(b) Sonthi Lift Irrigation Scheme :

Sonthi LI Scheme in Gulbarga and Yadgir districts envisage providing irrigation for 16,000 Ha. on left flank of River Bhima. The project is posed for central assistance under AIBP of Government of India. The Central Water Commission, GOI vide letter dated 27.04.2012 has accorded ‘in-principle’ consent for preparation of DPR for Sonthi LI Scheme. Accordingly, the DPR prepared at an estimated cost of Rs.600.00 Crores (PL 2012-13) has been submitted to CWC, GOI on 27.11.2012. The proposal is under consideration and examination in Ministry of Water Resources, GOI. The approval to the project by Central Government under AIBP will facilitate availing 90% of Central Assistance as the project is being implemented in DPAP area of Northern Karnataka and also for providing irrigation in the drought prone command area.

41

(c) Drip Irrigation under 2 nd Stage of Ramthal (Marol) LIS :

Ramthal (Marol) LIS project was taken up for implementation in the backwaters of Narayanapur reservoir to provide irrigation for 26,200 Ha. of command area in Hungund taluk of Bagalkot district.

Under 2 nd Stage of Ramthal (Marol) LIS it has been proposed to adopt Micro Irrigation System (Drip Irrigation with entire pipeline network) to provide irrigation for 24,000 Ha. of command area of Hungund taluk of Bagalkot district (in lieu of 12,600 Ha. as contemplated in conventional system of irrigation). Government vide GO dated 16.08.2012 has accorded administrative approval for implementing Drip Irrigation System under 2 nd Stage of Ramthal (Marol) LIS on pilot basis at an estimated cost of Rs.786.11 crores.Already, the tender under 2 packages on turn key basis have been received work will be awarded after approval of the Board. The scope of project includes O&M for 5 years. This is one of the largest single project in the world of its nature being taken up in KBJNL. More than 20,000 farmers are to be benefited under the scheme.

(d) LiDAR Survey Technology :

The FRL survey of Almatti Reservoir is carried out with 3D LiDAR Technology which has facilitated in speedy process of demarcating the FRL and for initiating LAQ proposals with precision when compared to the conventional methods of survey.

5. OVERALL PROGRAMME & PROGRESS DURING 2012-13 UNDER KBJNL

(A) Financial programme and progress: (Rs.in crores) Sl. Budget Head Grants Grants Progress No. Programme Programme during for 2012-13 as for 2012-13 as 2012-13 in BE in RE 1 AIBP 390.19 250.19 2 Capital Grants 948.58 348.58 1247.58 3 IEBR 700.00 700.00 4 SDP 105.00 105.00 143.69 5 SCP / TSP 241.97 241.97 124.46 6 Debt Service 107.44 113.19 83.66 TOTAL 2493.18 1758.94 1599.39

42

(B) Physical programme and progress: (Area in Ha.) Sl. Name of the project Programme Progress No. for 2012- for 2012- 13 13 1 Ramthal (Marol) LIS 8,000 4,715 2 LIS 5,000 12,690 3 Teggi-Siddapura LIS 2,000 -- 4 Rolli-Mannikeri LIS 2,300 1,350 5 Chimmalagi LIS 2,500 2,471 6 Laterals under NRBC Dy.No.15, 16 & 18 3,200 2,000 7 Indi LIS KM 97.30 onwards 2,000 2,000 8 Manjra Barrages -- 10,692 (*) TOTAL 25,000 35,918

(*) Note: 10,692 Ha. Potential under Manjra barrages created (farmers to lift water on their own from the storage accomplished in the barrages).

43

ALMATTI GARDENS BRINDAVAN

TOURIST ATTRACTION PLACE

44

UPPER KRISHNA PROJECT

A) About Krishna Bhagya Jala Nigam Limited: In order to accelerate the implementation of the Upper Krishna Project (UKP) by mobilising resources from the capital market, KBJNL was incorporated on 19 th August 1994 under the Companies Act, 1956 as Company, wholly owned by the Government of Karnataka for planning, investigation, estimation, execution, operation and maintenance of all components coming under the UKP. The Company is funding the Rehabilitation and Resettlement of the people affected by the Project. The company is authorised to let out water and recover revenues from individuals, groups of farmers including Water Users Co-operative Societies, Towns, City Municipalities and Industries.

B) Upper Krishna Project: The Upper Krishna Project in Northern Karnataka is a mega-multipurpose project. The Scheme is being implemented in Stages. The project works under UKP Stage – I & II envisage utilisation of 173 TMC of water under Scheme ‘A’ of Krishna basin with a contemplated command of 6.22 lakh Ha. including Rehabilitation & Resettlement of Project affected families under submergence of Almatti & Narayanpur Reservoir. The same has been completed.

Under KWDT-II award, the allocation made for Upper Krishna Project Stage – III is 130.90 TMC. It is contemplated to provide irrigation for 5.30 Lakh Ha. under UKP Stage– III in the command coming under Gulbarga, Yadgir, Bijapur, Bagalkot, Raichur, Koppal & Gadag Districts in Northern Karnataka. In accordance with the “in-principle” administrative approval for Rs.17,207.00 Crores (PL 2011-12) accorded by the Government vide G.O. Dtd:24.01.2012, implementation of certain project components of UKP Stage – III viz: Mulwad, Chimmalgi, Indi, Mallabad & Rampur LI Schemes have been taken up and are in various stages of progress.

C) Administratively approved cost and the year of approval along with Revised cost details: a) Stage-1 of UKP is approved by Planning Commission vide letter No: 2 (10) / 89-I&CAD/24.09.90 for Rs. 1214.97 Crores at Price level of 1986-87. The Revised Project Cost is approved by Planning Commission vide letter No.2 (10) 2009-WR dated 22.01.2010 for Rs.6891.59 Crores at Price level of 2008-09.

b) Stage-II of UKP is approved by Planning Commission vide letter no:2 (10) / 99-ER/13.12.2000 for Rs.2358.86 Crores at Price Level of 1998-99. The Revised Project Cost is approved by Planning Commission vide letter No.2(10)2009-WR Dated 22.01.2010 for Rs.3959.80 Crores at Price level of 2008-09.

Closure reports of UKP Stage-I & II submitted to Central water Commission, GOI.

45

D) Expenditure incurred / Potential created under UKP :

So far a sum of Rs.11,598.93 Crores has been spent on UKP Stage–I & II up to March 2013 besides Debt servicing. Also, cumulative expenditure of Rs.653.14 Crores has been incurred on UKP Stage – III Projects works till March 2013.

Out of contemplated 6.22 lakh Ha. of command area under UKP Satge – I & II potential of 6.10 lakh Ha. has been created upto March 2013. Under UKP Stage– III total irrigation potential of 12,158 Ha. is created till March 2013 (under Chimmalgi & Indi LI Schemes).

E) Barrages across River Bhima, Krishna under Krishna Basin and across River Manjra in Godavari Basin:

Krishna Bhagya Jala Nigam Limited is implementing the following barrages across River Bhima & Krishna (Krishna Basin) and across River Manjra (Godavari Basin).

(a) Across River Bhima (Krishna Basin) :

Name of Barrage Status Ghattarga Barrage Completed Kallur ‘B’ Barrage Completed Yadgir Barrage Completed Joladagi-Gudur Barrage Completed Civil work of Bridge cum Barrage and erection of 37 vertical gates completed and water stored at Barrage.

Contract for the Head work of Sonthi LIS, the tenders for balance works of the Head Works is receieved, it is to be awarded. Modified Sonthi Barrage LI Scheme Construction of Feeder Canal is completed. Construction of Main Canal Km 0.00 to 5.00, Branch canal Km 0.00 to 7.00, Distry.No.1 Km 0.00 to 15.00 & Yargol Minor Canal are in progress. Tenders received for Sonthi Main Canal KM 5.00 to 18.00 under 2 packages and to be awarded.

46

(b) Across River Krishna (Krishna Basin) :

Barrage Status of work Gugal Bridge cum Civil work of Bridge cum Barrage including erection Barrage of 69 vertical gates completed during 2012 and water is stored in the Barrage.

(c) Across River Manjra (Godavari Basin) :

Barrage Status of work Construction of four series of Bridge cum Barrages Jirgihal, taken up across River Manjra in Bidar district of Manikeshwar, Godavari basin to utilize 4.80 TMC of water is Halhalli & completed. The farmers will be utilise water for Chandapur Bridge- irrigation through their own pupm sets from the cum-Barrages storage being accomplished in these Barrages.

F) Other Irrigation Projects under KBJNL:

The other Irrigation Projects namely Ramthal (Marol) LIS, Thimmapur LIS, Teggi-Siddapur LIS, Rolli-Mannikeri LIS, Sonthi LIS, NRBC Distry.No.9A and Filling up of MI Tanks Projects in Northern Karnataka are being implemented under KBJNL.

The Zone wise status of progress of irrigation projects under implementation in KBJNL are narrated hereunder.

47

KBJNL, DAM ZONE, ALMATTI

Dam Zone Almatti was established on 30.01.1977. Two Circle Office & Eight Division offices with 24 Sub-Divisions, One Senior Health Office (Class-I) with its 4 Anti-Malaria Units and Deputy Conservation of Forest with its 3 Sub- Divisions comes under this zone.

The works of Almatti Dam, Lift Irrigation Schemes of UKP Stage-II such as ALBC, ARBC and Mulwad LIS and LI Schemes namely; Mulwad, Chimmalagi and Herkal LI Schemes under UKP Stage-III and other LI Schemes such as Ramthal (Marol), Timmapur, Teggi-Siddapur, Sonna and Rolli-Mannikeri LI Schemes comes under the jurisdiction of this zone. Also, filling up of MI Tanks in Bijapur & Bagalkot Districts and Landscape & Garden development works at Almatti Dam site comes under the jurisdiction of this Zone. Status of projects under KBJNL Dam Zone is as under :

1) Almatti Dam: The work is already completed and Gates are also erected. The water is being stored upto FRL 519.60 m and being utilized for irrigation. Further, as per the KWDT-II Award, the Reservoir Storage at Almatti is to be increased upto RL 524.256 M. The FRL survey taken up with 3D LiDAR Technology upto RL 524.256 M is almost completed.

2) Almatti Left Bank Canal: Head work already commissioned. Total length of Main Canal is 85.00 KMs. 67 KMs Main Canal under Stage-I is completed. Under Stage-II, Main Canal KM 67.00 to 85.00 is completed. The balance work in KM 72 is in advance stage of progress. The Distributaries No.1 to 40 is also completed.

An area of 19,707 Ha. is notified for Rabi 2012 and water let out for irrigation upto Km 67.00 of Main Canal and in Disty.No.1 to 27.

3) Almatti Right Bank Canal: Head work already commissioned. Main Canal of 67.50 Km is completed including Distributary No.1 to 24. Out of 9,900 48

Ha, potential of 8,940 Ha. is notified for Rabi 2012 and water has been let out for irrigation.

4) Mulwad Lift Irrigation Scheme:

Under UKP Stage-II : The water will be lifted in two stages under this scheme. Two head works viz; Baluti and Hanumapur Head works are already commissioned. Lead off canal Km 0.00 to 5.00 which leads water from 1 st jackwell to 2 nd jackwell completed.

East Canal of 17.40 Km length including Distry.No.1 to 6 completed. Also, West Canal of 78.00 Km length including 43 Distributaries is completed. The work of extension of Disty.No.6 of East Canal beyond railway line is completed except one railway line crossing.

Out of contemplated 30,850 Ha. of command area, potential of 25,735 Ha is already created and 20,759 Ha. is notified for Rabi 2012 and water has been let out for irrigation.

Under UKP Stage-III :

Under UKP Stage-III in Mulwad LIS it is proposed to irrigate an area of 2,27,966 Ha. In drought prone areas of Bijapur, Muddebihal, Sindagi, B. and Indi taluks of Bijapur district and and Bilagi taluks in Bagalkot district by lifting water in four stages from foreshore of Almatti Reservoir.

Under Stage-III, (a) Balance electromechanical works under Baluti 1 st Head Work, (b) Balance civil and electromechanical works under Hanumapur 2 nd Head Work, and (c) Masuti 3 rd Head Work were taken up on turn key tender basis and the works are in progress.

The consultancy work for detailed survey of about 670 KMs length of Main Canal and about 1,500 KMs of Distributary network were entrusted in 3 packages and the consultancy works are under progress. Further, the tenders for preparation of detailed estimates and DTPs are invited in 11 packages which are under process.

5) Ramthal (Marol) Lift Irrigation Scheme: This LI Scheme is taken up on the foreshore of Narayanapur Reservoir. The Scheme contemplates providing irrigation to 26,200 Ha. of command area of Hunagund Taluk of Bagalkot District.

Construction of 1 st Head work completed. 1 st Stage West Main Canal KM 0.00 to 21.00 and Disty.No.1 to 18 (except Disty.No.4) are completed. West Main Canal KM 21.00 to 62.74 and Disty.No.19 to 25 their under are under various stages of progress. 1 st Stage East Main Canal KM 0.00 to 6.00 is completed. Further, East Main Canal KM 6.00 to 51.85 and Disty.No.1 to 20 are in various stages of progress.

Construction of 2 nd Head Work is completed. Under 2 nd Stage, the contemplated command under conventional system of irrigation is 12,000 Ha. Government vide GO No.WRD/195/KBN/2012 dated 16.08.2012 had 49

accorded administrative approval for adopting Drip Irrigation System under 2nd stage of Ramthal (Marol) LIS on Pilot Basis at an estimated cost of Rs.786.11 crores. With the Drip Irrigation System, 24,000 Ha. of Hungund taluk will be irrigated in lieu of 12,000 Ha. contemplated under conventional irrigation system. The tenders for Drip Irrigation System under 2 nd stage of Ramthal (Marol) LIS in two packages viz; (a) East side area 12,300 Ha. (Package-I) and (b) West side area 11,700 Ha. (Package-II) are received and evaluation reports are placed before the Board for its consideration and approval. The scope of providing Drip Irrigation System includes 5 years maintenance also.

Irrigation potential of 8,715 Ha. is created to end of March 2013. An area of 1,961 Ha. Is notified for Rabi 2012 and irrigation facility provided.

6) Thimmapur Lift Irrigation Scheme: This LI Scheme takes off at KM 5.40 of Main Canal of ARBC. The Scheme contemplates providing irrigation to 20,100 Ha. of command area of Bagalkot Taluk.

The Head work is completed and commissioned during 2012. Work of construction of Main Canal Km 0.00 to 5.00 and Distry.No.1 to 5 is completed. Further, Main Canal Km 5.00 to 10.00 & Distry.No.6 to 24 are in various stages of progress. Main Canal Km 0.00 to 5.00 tender being invited for the balance work. Disty.No.1 to 4 are completed. Further, the Main Canal KM 5.00 to 36.33 and Disty.No.5 to 12 under DC-2 are under progress. Potential of 13,393 Ha. created to end of March 2013. An area of 1,272 Ha. is notified for Rabi 2012 and irrigation facility is provided.

7) Teggi-Siddapur Lift Irrigation Scheme: This Lift Irrigation Scheme is taken up on the foreshore of Almatti Reservoir near Teggi village of Bilgi taluk. Scheme contemplates providing irrigation to 3,000 Ha. command area of Bilgi Taluk.

Construction of balance works of Jackwell (civil works) & pumping machinery, substation, rising main, delivery chamber etc, awarded on turn key basis is in advance stage of progress. Further, construction of Main Canal from Km. 0.00 to 12.00 is almost completed.

8) Sonna Lift Irrigation Scheme: This LI Schemes is taken up on the foreshore of Almatti Reservoir. Scheme contemplates providing irrigation to 1,055 Ha in Bilgi Taluk of Bagalkot Dist.

The scheme is completed and commissioned. Water let out for irrigation since Kharif 2010.

9) Rolli-Mannikeri Lift Irrigation Scheme: This LI Schemes is taken up on the foreshore of Almatti Reservoir. Scheme contemplates providing irrigation to 2,450 Ha in Bilgi Taluk of Bagalkot Dist.

Construction of Jackwell, providing pumping machinery, sub-station, raising main, delivery chamber etc, awarded on turn key basis is nearing

50

completion. Further, works of canal network are in advance stage of completion. The potential of 1,350 Ha. Is created. The scheme is planned for completion during 2013-14.

10) Chimmalagi Lift Irrigation Scheme :

Chimmalagi LIS under Stage-III contemplates providing irrigation for 87,068 Ha. in Muddebihal, B.Bagewadi, Sindagi, Indi and Bijapur taluks of Bijapur district. The scheme takes off at KM 12.65 of ALBC. The Head Work (for 4,615 Ha.) on turn key basis is completed and commissioned during January 2013. The balance civil and electromechanical works of the Head Work awarded on turn key basis is in progress. The combined canal of 2.10 KM and West Main Canal KM 0.00 to 20.00 including Distributaries thereunder are completed. Further, West Main Canal KM 20.00 to 51.92 are in progress. Tenders invited for Disty.No.11 to 21 are in process.

East Main Canal KM 0.00 to 50.00 awarded under 5 packages are progress. Tenders for East Main Canal 50.00 to 90.00 are invited and in process. Estimates for East Main Canal KM 90.00 to 132.00 have been finalised and being placed before the TSC for clearance. Further, estimates for Disty.No.1 to 29 coming under East Main Canal are technically sanctioned and tenders to be invited.

11) Herkal Lift Irrigation Scheme : This scheme under UKP Stage-III envisages providing irrigation for 15,344 Ha. in Bilgi Taluk of Bagalkot District. Detailed estimates for Herkal (North) and Herkal (South) LI Schemes on turn key basis at an estimated cost of Rs.350.00 Crores have been finalised and tenders to be invited.

12) Filling up of M.I.Tanks of Bagalkot and Bijapur District: Scheme contemplates filling up of 16 MI tanks and 5 bandaras of Bijapur District and 7 MI tanks of Bagalkot district located at elevated place in drought prone areas. The work awarded on turn key basis during Janauary 2009 is almost completed except for certain minor works. The scheme is commissioned and water is letout in the pipeline network on trial basis during September 2012.

13) Landscape and Garden works on D/s of Almatti Reservoir: Landscape Development of Almatti Dam environs have been taken up to create the avenue for economic development of project area by attracting the tourists.

The project has been phased out in stages and development of 77 Acres of land along the left bank on the D/s of Dam is being implemented under Phase-I. Musical fountain work is completed and opened to public shows. Moghal Garden with fountains and entrance plaza works are also completed. In the later phase of landscape development works, providing water theme parks, courts etc., are planned in about 220 Acres.

51

14) SCP-TSP Works : Under this programme, works like Sprinkler Irrigation coming under ALBC, ARBC and Mulwad LIS command area and others works like CC Roads, Drainage, Community Hall etc. to provide basic aminities to SC/ST beneficiaries are taken up and are in progress.

PROGRAMME AND PROGRESS DURING 2012-13 :

The annual financial programme of this zone for the year 2012 -13 was Rs.535.10 Crores and the financial progress achieved to the end of March-2013 is Rs.481.15 Crores.

DETAILS OF IRRIGATION POTENTIAL (Area in Ha) Created Programme Progress Sl Planned upto Name of the Project for During No potential March - 2012-13 2012-13 12 1 Almatti Left Bank 20,235 23,530 -- -- Canal 2 Almatti Right Bank 9,900 9,233 -- -- Canal Mulwad LIS Stage – 3 30,850 25,735 -- -- II Mulwad LIS Stage - 4 2,27,966 III 5 Chimmalagi LIS 87,067 -- 2,500 2,471 6 Ramthal (Marol) LIS 26,200 4,000 8,000 4,715 7 Sonna LIS 1,055 900 -- -- 8 Thimmapur LIS 20,100 -- 5,000 12,690 9 Teggi-Siddapur LIS 3,000 -- 2,000 -- 10 Rolli-Mannikeri LIS 2,350 -- 2,300 1,350 TOTAL 4,28,723 63,398 18,000 21,226

52

KBJNL, OPERATION & MAINTENANCE ZONE, NARAYANPUR:

Considering the vast area already notified and the phase of development of irrigation in the subsequent period, the Government has accorded sanction for creation of separate Zone to look after Operation and Maintenance activities of UKP vide G.O. No.ID/115/WBM/91, Dated: 14/10/1991. Owing to the Government order, the office of the Chief Engineer, O&M Zone, UKP Narayanpur came into existence from 03.01.1992. This Zone is brought under Krishna Bhagya Jala Nigam Limited with effect from 15.11.1995. One Circle, four Divisions and Sixteen Sub-Divisions comes in the jurisdiction of this Zone.

This Zone has been vested with the the responsibility to monitor the water management in an irrigated area of 1.00 lakh hectares under Stage-I & II of UKP. This year canal wise details of Notified area for irrigation are as under :

Sl. Kharif Rabi Canal No 2012 2012 1 Narayanpur Left Bank Canal 50,133 50,133 2 Rampur Lift Irrigation Scheme 18,831 18,831 Narayanpur Right Bank Canal 3 (KM 0.00 to 82.00 & Disty.No.1 to 30,224 30,224 14) Total 99,188 99,188

The Maintenance of following irrigation camps in the project area also come within the purview of this zone.

1) Narayanpur 2) Kodekal 3) Rajankollur 4) Kakkera 5) Hunasagi 6) Devapur 7) Devatkal 8) Mudunoor 9) Rodalabanda 10) Amarapur Camp The Maintenance of 108.00 Km length of Major District Roads, 247.32 Km of other roads, 16 VHF wireless stations, etc., also comes in the jurisdiction of this Zone. Apart from Operation and Maintenance of Canal network in NLBC from Km. 0.00 to 78.00, NRBC Km. 0.00 to 82.00 & Rampur LI Scheme, this Zone is also looking after the following project works: a) Rampur Lift Irrigation Scheme :

Rampur LIS under UKP Stage-II contemplates providing irrigation for 20,235 Ha. Already 1 st Head Work at Navali and 2 nd Head Work at Anehosur, 14 KM Lead Off Canal and East Canal KM 0.00 to 20.00 including West Distributary completed and water let out for irrigation.

Under UKP Stage-III it is contemplated to provide irrigation for 13,923 Ha. in Lingasugur and Deodurga taluks of Raichur district. The extension of East Main Canal of Rampur LIS from KM 20.00 to 27.00 including 53

Disty.No.10 and 11 and Tail end Distributary taken up on tender basis are in various stages of progress. The scheme is planned for completion during 2013-14. b) Koppal Lift Irrigation Scheme : This scheme contemplates providing irrigation for 48,436 Ha. in Koppal, Bagalkot and Gadag districts under UKP Stage-III. As per the modified proposal it is proposed to lift water under two equal stages from the backwaters of Narayanapur reservoir from RL 485.00 m to RL 660.00 m. Government vide GO dated 9.1.2013 accorded approval for adopting Micro Irrigation under Koppal LIS to provide irrigation in Bagalkot, Koppal & Gadag Districts utilizing 12.815 TMC of water under UKP Stage-III. Tenders for 1 st and 2 nd Head Works on turn key basis have been received and work is to be awarded. Topographical survey of 48,436 Ha. of command is already completed. c) Rajan-Kollur Lift Irrigation Scheme : The Scheme takes off from the D/s of Rajan-kollur Tunnel at Km 40.06 of NLBC. Scheme contemplates providing irrigation for 1,097 Ha of command area in Shorapur taluk of Yadgir district. The scheme is completed and commissioned during 2012-13 and irrigation facility provided for the contemplated command. d) Bonal Lift Irrigation Scheme: This scheme contemplates providing irrigation to about 5,400 ha of the suffering achcut under SBC Distry.No.6 of UKP by lifting water from D/s of Bonal Mini Hydel Scheme near Bonal tank in Shorapur taluk Yadgir district. The scheme is completed and commissioned during 2012-13 and irrigation facility provided for the suffering achcut under SBC Distry.No.6.

PROGRAMME AND PROGRESS DURING 2012-13 : The annual financial programme of this zone for the year 2012 -13 is Rs.381.60 Crores and the financial progress achieved to the end of March-2013 is Rs.349.44 Crores. DETAILS OF IRRIGATION POTENTIAL (Area in Ha.) Sl. Name of Name of the Canal Planned Created upto No the Potential March-13 District (Notified) 1 Bijapur NLBC 27 27 2 Gulbarga NLBC 47,196 49,710 3 Gulbarga Rajankollur LIS 1,097 1,100 4 Raichur Rampur LIS – Stage-II 20,235 19,406 Rampur LIS – 5 Raichur 13,923 -- Exension 5 Raichur NRBC 30,011 30,224 TOTAL 1,12,489 1,00,467 54

KBJNL, CANAL ZONE NO. 1, BHEEMARAYANAGUDI

ORGANISATION:

This Zone is functioning with two circle i.e.NRBC Circle No.2, Krishnapur & JBC Circle, Bheemarayanagudi and 8 Divisions and 36 Sub-Divisions.

CONTEMPLATED IRRIGATION POTENTIAL:

The irrigable command areas contemplated under various canal networks coming under the jurisdiction of this Zone are as under:

Sl.No. Name of the Canal ICA envisaged 1 Shahapur Branch Canal. 1,22,120 Ha. 2 Mudbal Branch Canal. 51,000 Ha 3 Jewargi Branch Canal 57,098 Ha. 4 Narayanapur Right Bank Canal (KM 82.00 53,997 Ha. to 95.00 & Dy.No.15 to 18) 5 NRBC Extension from KM 95 onwards 61,747 Ha. under UKP Stage-III 6 NRBC Disty.No.9(A) 15,250 Ha. 7 Mallabad LIS under UKP Stage-III 33,730 Ha. 8 Bhima Flank under UKP Stage-III 21,572 Ha. 9 Sonthi LIS 16,000 Ha. Total 4,32,514 Ha.

The command areas of Shorapur, Shahapur and Yadgir taluks of Yadgir district, Jewargi and Chittapur Taluks of Gulbarga district and Deodurga and Lingasugur taluks of Raichur district will be covered in the above canal networks.

PRESENT STATUS OF WORKS UPTO END OF MARCH 2013:

1. SBC, MBC and JBC :

The Shahapur Branch Canal, Mudbal Branch Canal and Jewargi Branch Canal works under UKP Stage-I are completed and are now in the Operation & Maintenance stage.

2. Narayanapur Right Bank Canal :

Under UKP Stage-II :

Construction of NRBC from Km 0.00 to 95.00 under UKP Stage – II envisage providing irrigation for 84,000 Ha. in Lingasugur & Deodurga Taluks of Raichur District. The works of this canal were commenced during the year 1995-96. The jurisdiction of NRBC from KM 82.00 to 95.00 and Dity.No.15 to 18 comes under the jurisdiction of this zone. Further, the

55

jurisdiction of NRBC from KM 0.00 to 82.00 and Disty.No.1 to 14 comes under the jurisdiction of O&M Zone, Narayanapur.

All the works of Main Canal from Km 82.00 to 95.00 and Distry.No.15 to 18 are completed. Works of only some additional laterals on D-15, 16 & 18 are in the advance stage of completion.

The total contemplated irrigation potential of 84,000 Ha has been already been created and an area of 92,895 Ha. is notified for Rabi 2012. Water has been letout for irrigation including in the balance area wherever the basic infrastructure for irrigation potential has been created.

Under UKP Stage-III :

Under UKP Stage-III, Extension of Narayanapur Right Bank Canal beyond KM 95.00 upto Chandrambanda village in Raichur district is envisaged to provide irrigation for 61,747 Ha. in Raichur District.

The topographical survey of entire command under NRBC Extension is completed. Tenders for NRBC Main Canal KM 95.00 to 105.00 under 2 packages are invited and in process. Detailed estimates for NRBC KM 105.00 to 125.00 are under preparation.

3. NRBC Disty.No.9(A) :

NRBC Disty.No.9(A) off-takes at KM 55 of NRBC on right side for providing irrigation for 15,250 Ha. in Deodurga and Manvi taluks of Raichur district.

The construction of NRBC Disty.No.9(A) KM 0.00 to 8.18 and KM 10.48 to 29.12 under 3 packages are almost completed. The work of Aqueduct from KM 8.18 to 10.48 is in progress. Further, the Branch Distributary KM 0.00 to 22.18 and Wadawatti Branch Distributary from KM 0.00 to 10.00 awarded under 4 packages are in progress. Tenders invited for Wadawatti Branch Distributary from KM 10.00 to 15.18 is in process.

4. Mallabad Lift Irrigation Scheme :

This scheme under UKP Stage-III envisage providing irrigation for 33,730 Ha. in Jewargi taluk of Gulbarga district and Shahapur and Shorapur taluks of Yadgir district.

The construction of 1 st Head Work at Balabatti at KM 20.90 of JBC awarded on turn key basis is in advance stage of completion. Also, the Main Canal KM 0.00 to 4.00 under 1 st Head Work is in progress.

For the 2 nd Head Work on MBC at KM 20.00 – Tenders on turn key basis received and work to be awarded.

The 3 rd Head Work on SBC at KM 5.40 awarded on turn key basis is in progress. The estimates for canal network are prepared.

56

5. Bhima Flank : This scheme under UKP Stage-III envisage providing irrigation for 21,572 Ha. in Shahapur taluk of Yadgir district. The technical feasibility of the scheme is being examined.

6. Bridge Cum Barrage Works across River Bhima :

(a) Yadgir & Joldadgi-Gudur Barrages :

Constructions of above two Bridge-cum-Barrages are completed and water stored in these barrages is being utitilised by farmers through their own pumpsets.

(b) Sonthi Bridge-cum-Barrage and Sonthi LI Scheme :-

The civil work and erection of 37 vertical gates of modified Sonthi Bridge- cum-Barrage across River Bhima (near village Sonthi) is completed and water stored.

In Sonthi LI Scheme is envisaged by lifting water is lifted from the storage accomplished at Sonthi Barrage to provide irrigation for 16,000 Ha. of command in Chittapur taluk of Gulbarga district and Yadgir taluk of Yadgir district. For the Head Work of Sonthi LIS, the tenders received for the balance work of Head Work and work to be awarded.

Construction of Feeder Canal KM 0.00 to 1.75 is completed. Further, Sonthi Main Canal from KM 0.00 to 5.00, Sonthi Branch Canal KM 0.00 to 7.00, Disty.No.1 KM 0.00 to 15.00 and Yargol Minor Canal works are in various stages of progress.

The Sonthi LI Scheme is posed for Central Assistance under AIBP. In- principle approval for the scheme is obtained from CWC, GOI on 27.04.2012. The DPR prepared for an estimated cost of Rs.600.00 crores (PL 2012-13) is submitted to CWC on 27.11.2012 and the same is under examination in Ministry of Water Resources, Government of India.

7. Gugal Bridge-cum-Barrage across River Krishna :

The civil work of Bridge cum Barrage near Gugal village in Deodurga taluk of Raichur district across River Krishna is completed during 2012-13 including erection of 69 vertical gates. The water stored at the barrage is being utilized by the farmers with their own pumpsets for irrigation. The bridge-cum-barrage also provides communication between Yadgir and Raichur districts.

8. Bridge-cum-Barrages across River Manjra in Bidar distrct : Construction of 4 No. of series of Bridge-cum-Barrages across river Manjra in Bidar district envisage utilization of 4.80 TMC of water under Godavari basin.

57

Already, the construction of 4 bridge-cum-barrages namely; (a) Jirgihal, (b) Manikeshwar, (c) Halhalli, and (d) Chandapur were completed. These barrages are provided with automatic tilting Godbole Gates. The water to be stored under these barrages is to be utilized by the famrers with their own pumpsets for irrigation.

Total expenditure incurred during 2012-13 on all the above Barrage works under this Zone is Rs.34.71 Crores as against the annual programme of Rs.45.00 Crores.

PROGRAMME AND PROGRESS DURING 2012-13 :

The annual financial programme of this zone for the year 2012-13 was Rs.224.99 Crores and the financial progress achieved to the end of March-2013 is Rs.199.17 Crores.

DETAILS OF IRRIGATION POTENTIAL

(Areas: In Ha) Potential Progra- Planned created mme Progres Sl. Name of the canal Potentia upto for s during No l March 2012- 2012-13 2012 13 1 Shahapur Branch Canal 1,22,120 1,14,717 -- --

2 Mudbal Branch Canal 51,000 44,321 -- --

3 Jewargi Branch Canal 57,098 59,163 -- --

Narayanapur Branch Canal (from KM 82.00 to 4 53,997 57,662 2,000 2,000 95.00 and Disty.No.15 to 18)

NRBC Extension -- 5 61,747 -- -- (beyond KM 95.00)

6 NRBC Disty.No.9(A) 15,250 -- 1,200 --

7 Sonthi LI Scheme 16,000 ------

8 Mallabad LIS 33,730 ------

9 Bhima Flank 21,572 ------

Total 4,32,514 2,75,863 3,200 2,000

58

KBJNL, CANAL ZONE NO.2, RAMPUR

This Zone is functioning with effect from 1.10.1986 vide G.O.No. PWD 60 PCO 86, Dtd: 29.9.1986. At present this Zone is in-charge of the works of :

(a) Indi Branch Canal from Km 0.00 to 172.00 including Distry.No.1 to 46, (b) Indi Lift Canal works from Km 0.00 to 147.00 (c) Filling up of 8 MI tank project in Indi taluk – Anachi Lift. (d) Itaga-Sangam LIS. (e) Ghattaraga and Kallur-B Barrages across River Bhima. (f) Ayacut Roads within the Achcut of Indi Branch Canal and Buildings.

ORGANISATION:

This Zone is functioning with one circle i.e., O&M Circle No.2, Rampur and 5 Divisions and 23 Sub-Divisions.

Details of works taken up under this Zone are as under:

INDI BRANCH CANAL :

The Indi Branch Canal takes off at Km 77.52 of Narayanpur Left Bank Canal, which is situated about 1 Km away from Kembhavi village of Shorapur taluka in Gulbarga District and traverses for a length of 172 Km with a head discharge of 2,943 cusecs (83.49 cumecs) through the districts of Gulbarga and Bijapur irrigating an area of 30,831 Ha. and 1,00,464 Ha respectively (Total 1,31,295 Ha.).

The works of construction of Indi Branch Canal from Km 0.00 to 64.00 are tackled and completed under Stage-I, Phase-II of UKP creating irrigation potential of 60,721 Ha. The works of construction of Indi Branch Canal from Km 65.00 to 172.00 are tackled and completed under Phase-III of Stage-I to create the balance irrigation potential of 70,574 Ha. Up to March 2013 total an area of 1,31,584 Ha Irrigation Potential of 1,31,584 Ha has been created.

The works of Indi Branch Canal from KM 65 to 172 and Distributaries 14 to 46 are taken up on tender basis as well as entrustment basis. The works are completed. The details of works taken up and completed are as under:

(i) The works of IBC from KM 65 to 80, 101 to 113, 120, 122 to 125 and 151 to 172 taken up on tender basis and are completed.

(ii) The works of IBC from KM 81 to 88, 90 to 100, 114 to 119, 121, and 126 to 150 taken up on direct entrustment basis are completed.

(iii) The works of Distributaries 14 to 24 and laterals coming under IBC from KM 65 to 120 taken up on direct entrustment basis are completed.

(iv) The works of distributaries 25, 26 to 34, 35 to 37, 38 to 45A and 46 taken up in packages on tender basis are completed.

59

(v) The works of providing CC lining to IBC from KM 65 to 172 also taken up in packages and these works taken up on tender basis are completed.

(vi) Water has been released through IBC upto KM 64.00 during Septermber 1995, upto KM 130.00 on 06.02.2002 and upto KM 172.00 on 2.11.2002.

The Notified area under IBC for Rabi 2012 is 1,31,414 Ha. and irrigation is being provided.

INDI LIFT CANAL :

Under UKP Stage-II, the Head work of Indi Lift Irrigation Scheme and the Canal Network from Km 0.225 to 97.30 including Distry.No.1 to 40B & laterals there under are completed. Out of contemplated irrigation potential of 41,900 Ha. upto end of March 2013 irrigation potential of 43,000 Ha. has been created. Water is letout in the Indi Lift Canal on trial basis during August 2007 and on regular basis from July 2008. Notified area for Rabi 2012 is 39,897 Ha.

Under UKP Stage – III, extension of Indi Lift Main Canal from KM 97.30 to 147.00 to provide irrigation for 20,690 Ha. in Indi & Sindagi Taluks of Bijapur Dist is envisaged. Already, the works of construction of Indi Lift Canal from Km 97.30 to 110.00 are completed and water letout for irrigation. Construction of two Aqueducts coming under reach from KM 110.00 to 113.00 are in advanced stage of completion. Furter, Indi LIS Main Canal KM 113.00 to 120.00 is almost completed. For the balance works under Indi Lift Main Canal KM 120.00 to 128.00 and for Main Canal from KM 128.00 to 135.00 tenders are to be awarded. Package estimate for Indi Lift Main Canal KM 135.00 to 142.00 is prepared and tenders to be invited. Disty.No.41 to 47 & 49 & 50 are completed. For Distry.No.48 tender is being awarded. Disty.No.51 & 52 are nearing completion. For Disty.No.53 to 55 tenders are in process. For Disty.No.56 to 59, preparations of estimates are under progress. The survey investigation and preparation of estimates for balance Indi Lift Canal network from Km 142.00 to 147.00 is under progress. The work of providing additional pumping machinery at the Head work is also in progress.

FILLING-UP OF 8 MI TANKS IN INDI TALUK (ANACHI LIFT) : For the work of filling up of 8 MI tanks in Indi Taluk – Anachi Lift, tenders received on turn key basis and work to be awarded. The estimated cost of the work is Rs.35.00 crores.

ITAGA-SANGAM LI SCHEME : This scheme was taken up for providing irrigation to the suffering command in the tail end of IBC Disty.No.11. The work was commenced during October 2005 and completed and commissioned in June 2010. The irrigated area from this scheme is 1,200 Ha. which includes 911 Ha. of suffering atchcut under Disty.No.11 of IBC and additional potential of 289 Ha.

60

BARRAGES ACROSS RIVER BHIMA : The two barrages namely Ghattaraga and Kallur-B barrages across River Bhima were completed during 2004-05 and the water stored at these barrages is being utilised by the farmers through their own pumpsets for irrigation.

AYACUT ROADS:

Construction of Ayacut Roads under Phase-I was of 611 kms length and all these works are completed. Further, it was proposed to tackle 942 Kms of Ayacut Roads under Phase-II of Stage-I of UKP. Out of these 942 Kms, construction of 307 Kms of Ayacut Roads was handed over to CADA as per the orders of G.o.No.ID 95 Dt: 15-11-1995. Hence, 635 Kms of Ayacut Roads come under the jurisdiction of this zone. These works are completed. The total amount spent on Ayacut Road works was Rs.2650.69 lakhs including maintenance (excluding World Bank works which are completed).

10 Nos of Ayacut Roads in two packages have been taken under Rehabilitation & Resettlement programme and these works are completed.

15 Ayacut Roads were approved under NABARD Programme of 2012-13. 5 ayacut Road works taken up under NABARD are in progress and for remaining 10 works estimates prepared and works to be taken up..

BUILDINGS:

The buildings were constructed in various colonies of this zone for accommodation for staff and office. Rs.1904.37 lakhs expenditure is incurred towards these works to end of March 2009. Two building packages works one at Rampur and another at are completed and the total expenditure incurred upto end of December 2006 on these works is Rs.552.83 lakhs.

SCP-TSP WORKS :

Under this Zone works of SCP-TSP are being implemented.

PROGRAMME AND PROGRESS DURING 2012-13 :

The annual financial programme of this zone for the year 2012 -13 was Rs.134.34 Crores and the financial progress achieved to the end of March-2013 Rs.123.44 Crores.

61

DETAILS OF IRRIGATION POTENTIAL

(Areas: In Ha) Programme Name of projects in Potential during the Progress during Bijapur and Gulbarga Total ICA created upto year 2012-13 districts March 2012 2012-13 Indi Branch Canal. 1,31,261 1,31,584 -- -- Indi Lift Canal 41,900 43,000 -- -- (Upto Km 97.30) Indi Lift Canal 20,690 8,000 2,000 2,000 (Km 97.30 to 147.00) 1,200 (including suffering Itga Sangam LIS atchcut of 1,200 -- -- 911 under IBC Dy.No.11) Total 1,95,051 1,83,784 2,000 2,000

62

BAGALKOT TOWN DEVELOPMENT AUTHORITY

1. SALIENT FEATURES OF BAGALKOT TOWN:

Bagalkot Town is historically famous from the glory and one of the largest town in the northern parts of Karnataka which is situated on the right bank of at 16 o-12’ longitude and 75 o-12’ latitudes.

The Bagalkot Town is situated at a distance of 40 KMs (by road) South West of Almatti Dam. The lowest portion of the town is at an elevation of RL 512.19 Mtr. and the maximum elevation being RL 533.53 Mtr. A substantial portion of this town will get submerged in the backwaters of Almatti Reservoir when the Dam is raised to its ultimate FRL of 524.256 Mtr.

Considering the backwater effect of storage of water at FRL 519.60 Mtr. at Almatti Dam and also as per the GO dated 16.11.2002 the structures upto RL 523.00 Mtr. in Bagalkot Town are already acquired. The FRL survey using 3D LiDAR technology for submergence when the storage at Almatti Reservoir is increased to FRL of 524.256 Mtr. as per KWDT-II Award is nearing completion.

Resettlement plan consists of acquiring lands for locating the new Bagalkot Town and to provide basic infrastructure in the new town. The lands required for the new town have already been acquired (about 4,544 acres) and possession has been taken.

2. ORGANISATION STRUCTURE:

For efficient and systematic implementation of Rehabilitation and Resettlement of Bagalkot Town, Govt. of Karnataka has constituted Bagalkot Town Development Authority (BTDA) with an Amendment to HUD Act functioning since 1984. BTDA is formed with Chief Engineer office with Staff. 2 Divisions with staff, 8 Sub Divisional Offices with staff, Special Land Acquisition Office with staff, Rehabilitation Office with staff & Chief Accounts Office with staff.

Govt. in the order RD No.145/REH/Bangalore/2005 Dt.24/10/2005 has temporarily closed One Division and 4 Sub-Division offices along with staff with effect from 31/10/2005. Further the same offices are re-opened as per G.O. No: RD/230/REH/2009 dated: 12-01-2010 for carrying valuation of structures between RL 521 to 523 mtr. contour in old Bagalkot town and development of Unit-II at Navanagar. The functioning of these offices come into effect from 01- 04-2010.

63

3. ACCELERATED IRRIGATION BENEFIT PROGRAMME .

Estimated cost of Rehabilitation and Resettlement of Bagalkot Town: The detailed cost of the Project is as under.

Sl.No. Details of Component Rs.in lakh 1 Structural compensation in old Bagalkot Town. 39539.06 2 Land Acquisition for new township and others etc. 2952.50 3 R&R Packages. 3000.00 4 Construction of Roads and parks etc., 6231.00 5 Providing Water Supply 4445.00 6 Providing U.G.D. 2200.00 7 Providing Electrification. 2000.00 8 Construction of Public Building 2200.00 9 Telecom facilities 400.00 10 Construction of Railway 1000.00 11 Maintenance of BTDA Colony and Navangar. 800.00 12 New Supply Machinery and Maintenance 250.00 13 Consultancy and training charges 90.00 14 Establishment 2591.94 Total: - 67700.00

The Project cost of the above components under AIBP prepared for Rs.677.00 crores and Rs.360.49 crores under special package scheme. Thus the total cost of the project works out to Rs.1037.49 crores.

The works taken up under Stage-I Phase-I, II, are completed and the works under Pahase-III are nearing completion. Structures up to RL 521.00 M contour have been valuated and compensation paid. Plots for the PDFs below RL 521.00 Mtr. contour have been allotted in New township of Bagalkot. Most of the PDFs constructed their houses in the allotted sites.

64

4. SPECIAL PACKAGE SCHEME:- Considering the problems due to backwater effect, Govt. has announced the special package of Rs.638.00 Crores (Rs.500.00 Crores for Bagalkot town + Rs.138.00 crores for R&R) Vide G.O.NO.RD1/124/REH/2002/Bangalore Dt.16/11/2002 to improve the existing conditions of old Bagalkot Town. The details of special package are as under:

Sl.No Details of components Rs.in Crores 1 Structural compensation between RL.521.00 to 414.00 523.00, and development of 35 sectors of unit 2 of Navangar with all infrastructures facilities like roads. 2 Providing UGD for Non submergence of Bagalkot 29.12 Town. 3 Providing Water Supply for non-submergence of 11.70 Bagalkot Town. 4 Construction of link roads. 20.00 5 Development of parks in old town. 2.00 6 Construction of building under Ashraya Scheme for 12.00 slum dwellers. 7 Construction of building for site less and below 5.00 poverty line people. 8 Construction of 50 bedded hospital in old town. 2.00 9 Income and employment generating scheme. 4.18 Total :- 500.00

5. PRESENT STATUS :

I. a) For Acquisition of the structures between contour RL 521.00 M to RL 523.00 M structures have been paid and site allotment is under process.

b) The demarcation of plots in 50 sectors of Unit-II is completed. The tenders for infrastructures facilities like roads, water supply, UGD, electrification and storm water drains for Unit-II of Navanagar have been received and to be approved by the Board.

II. The UGD Network in old Town for Non-submersible portion of Bagalkot has been completed.

III. The work of providing water supply system including revamping of existing pipeline for non-submersible portion of Bagalkot town has been completed and is functioning.

IV. The improvements to roads i.e. 3 link roads, 5 main roads, 7 internal roads in slum area of Bagalkot Town were taken up on tender basis and all are completed.

V. Development of 4 parks in old Bagalkot town is completed.

VI. Construction of 50 bedded Hospital building along with Doctors and Nurse Quarters in old Bagalkot Town are completed and now Hospital is functioning 65

6. THE DETAILS BUDGETARY PROVISIONS FOR 2012-13 :

(Rs. In Lakhs.) Sl.No. Details of Component. Approved. Revised. I Under A.I.B.P. i) Compensation & Lok Adalat. 2100.00 -- (ii) Development Civil works. 6.00 -- II SCP/TSP works. 0.00 -- III Special Package works. 502.31 -- IV Scheme-A Unit-I works under Capital 3714.19 -- Grant (including consultancy) V Scheme-B Unit-II works under Capital 21093.22 -- Grant. VI Structure Compensation between RL 1001.00 -- 521.00 M to RL 523.00 M VII Establishment 700.00 -- Total: 29116.72 --

7. DETAILS OF PROGRESS ACHEIVED DURING 2012-13 (UPTO 31.03.2013)

a) Development Works: During 2012-13, 2 spillover works under AIBP are completed. 7 works have been taken up under special package of which 4 works are completed. Under Capital Grants, scheme-A works in Unit-I, 91 works have been taken up of which 79 works are completed. In Unit-II under Scheme-B, 24 works have been taken up of which 7 works are completed. For major works (5 Nos.) in Unit-II such as Roads, Water Supply, UGD, Electrification & Storm Water Drains, the tenders amounting to Rs.550.00 crores have been received and works to be awarded with the approval of KBJNL Board.

b) Acquisition of Structures : During 2012-13 compensation of Rs.25.80 crores have been paid to the structures coming below RL 521.00 Mtr. and Rs.13.13 crores have been paid to the structures coming between RL 521.00 M to RL 523.00 M. Rs.0.10 crore have been paid as house grants in the form of ex-gracia for the PDF’s who are coming below poverty line.

c) Allotment of sites: Totally 64 sectors (56 for PDF's and 8 for Non- PDF's) are developed in unit-1 at Navanagar. During this year 40 sites are allotted to PDF’s, Non-PDFs & others. For 260 buildings permissions have been given to construct the houses at their allotted sites in Navanagar.

66

8. FINANCIAL PROGRESS:

Financial programme for the year 2012-13 is Rs.291.16 crores out of which an expenditure of Rs.66.86 Crores has been made upto end of March-2013. The Details are as under: (Rs.in lakhs) Sl. No Details of Component. Grant. Expenditure.

I Under A.I.B.P.

i) Compensation & Lok Adalat. 2100.00 2734.37

(ii) Development Civil works. 6.00 0.12

II SCP/TSP works. 0.00 0.00

III Special Package works. 502.31 9.99

IV Scheme-A Unit-I works under Capital 3714.19 3257.31 Grant (including consultancy).

V Scheme-B Unit-II works under Capital 21093.22 52.94 Grant.

VI Structure Compensation between RL 1001.00 2.69 521 M to RL 523 M and RL 523 M to RL 527 M

VII Establishment 700.00 628.72

Total: 29116.72 6686.14

******

67

PROJECTS UNDER

KARNATAKA NEERAVARI NIGAM LIMITED

68

12. KARNATAKA NEERAVARI NIGAMA LIMITED

12.1 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION (NORTH), BELGAUM

Irrigation (North) Zone was formed on 10.8.67 in pursuance of the Government order No.PWD.114.PCO.67, dated: 24.7.1967 with a view to increase the tempo of construction work in the Irrigation Projects as a result of increased provision of the plan allocation in the state.

Irrigation (North) Zone is incharge of the following projects.

A On-going Schemes 1 Ghataprabha Irrigation Project 2 Hipparagi Irrigation Project 3 Markandeya Reservoir Project 4 Dudhaganga Irrigation Project 5 Lifting of Hiranyakeshi water into GRB Canal. 6 Project 7 Sri Rameshwara L.I.S 8 Kinaye Irrigation Project 9 LIS (Rejuvenation work) 10 Sadalaga bridge cum barrage B. Approved and works yet to be started 11 Construction of Sangam Barage 12 Filling of -Basavanna Tank of Taluka 13 Filling of kadapur Tank of Chikodi Tq. Filling of 18 tanks of Hukkeri + 4 tanks of chikodi Tq 14 (Total 22 tanks) from Hiranyakeshi river.

So far, an irrigation potential of 3,90,515 Ha, has been created under the above projects. An expenditure of Rs. 3958.295 Crores has been incurred under the above schemes to end of 3/2013.

Out of the above schemes, Markandeya Project is completed during 2006-07 and the remaining schemes are under different stages of progress.

69

12.1.1 GHATAPRABHA PROJECT

The Project comprises a reservoir across the river Ghataprabha, near in Hukkeri taluk to provide irrigation to 3,10,823 Ha. in Belgaum and Bagalkot districts.

Dam & Allied works: Completed

Ghataprabha Right Bank Canal: Out of total length of 199.093 kms a length of 0.00 km to Km. 196 has been completed except lining in some reaches(Km122,131,144,145). Water let out for irrigation upto Km 170 & trial run upto km.191 . Distributaries: There are total 37 distributary blocks under GRBC. Works are completed in distributary blocks 1 to 26, 28 to 30 (except Km 13 to 15 in forest of Bl.No.24) Works in Bl.No. 27 is in progress. Works in Bl.No 31 ( except Km-3) & 33 are completed. Works in Bl.No. 34 to 37 are in progress.

Chikkodi Branch canal (CBC – 88 Km.) : Length completed to its full length of Kms. 88 including distributaries and water let out for irrigation.

Ghataprabha Left bank canal: GLBC has been completed to its full length of 109 Km and water has been let out for irrigation in all 61 blocks. GLBC lining works are taken up under Ghataprabha stage – III. About 96.80 Kms Main Canal lining, 201.67 Kms of Branch Canal lining & 494.00 Kms of Distributary lining work is completed. For the balance reaches, lining works are under progress and under completion stage.

Government has accorded administrative approval to the revised project estimate of Ghataprabha Project Stage III amounting to Rs.1210.51 crores vide GO dated 18.10.2009.

70

LIFT IRRIGATION SCHEMES UNDER GHATAPRABHA PROJECT

1) Daddinaganur LIS: This scheme is proposed to provide irrigation facilities for an area of 2711 Ha for the benefit of PAF’s of Hidkal Dam by lifting water from Ghataprabha river. An area of 2164 Ha O.P. is created so far.

There are two stages under this scheme. (i) Stage-I: Construction of weir across Ghataprabha river, intake channel, providing & fixing pumping machinery, raising main work & construction & delivery chamber has already been completed.

(b) Canal works: Works completed to its full length of 11 kms. Works completed in all 13 distributory blocks under first stage. (c) FIC: Survey work for Bl.No.1 to 7 of 1st Lift is completed.

(ii) Stage-II: (a) Head works: Head works and Delivery chamber works are completed. (b) Canal works: Works are completed.

Power Supply work is nearing completion.

2) LIS is proposed to provide irrigation facilities for an area of 2752 Ha. for the benefit of PAF’s of Hidkal Dam by lifting water from link channel of GRBC. The proposed area of 2752 Ha of O.P. is created so far. There are two stages under this scheme. (i) Stage-I: (a) Head works: Construction of intake channel, Jackwell, providing & fixing of pumping machinery, raising main & delivery chamber have already been completed. (b) Canal works: Works completed to its full length of 11.50 kms. All Distributory works are completed. FIC: Works in Bl.No.1 to 4 of 1st lift are in progress.

(ii) Stage-II: (a) Head works: All head works are completed. (b) Canal works: All canal works are completed. (c) FIC: Estimates are Sanctioned for Bl.No.A to E of 2nd lift (Total 19 works, 17 works agency fixed, 6 works grounded).

Power supply: Power sanction has already been received from KPTCL. Necessary initial deposit has already been paid to KPTCL. 1st stage commissioned on trial basis on 17.04.05 and 2nd stage commissioned on 08.09.07

3. LIS: Kotabagi LIS is proposed to irrigate 8100 Ha. in Hukkeri & Chikkodi taluks in Belgaum district by lifting water from Ghataprabha river. There are two stages under this scheme.

(i) Stage-I: (a) Head works: Completed. (b) Canal works: Right bank lift canal (4.70 Km) and left bank lift canal (5.9 Km) has already been completed. (c) Distributory works: Works in all distributory blocks under LBC & RBC have been completed.

71

(ii) Stage-II: (a) Head works: Completed. (b) Canal works: RBC completed to its full length of 17.50 Km. Works in all distributory blocks are completed.

Power supply: Stage-I & II commissioned on trail basis during August ’07.

NAME OF THE PROJECT GHATAPRABHA PROJECT Location Hidkal Year of Inception 1972 Original and Latest estimated cost Original Estimated cost-Rs. 90.54 Crores (Rs. in Crores), including administrative/ Administrative approval: GO No.PWD. 147. MGP. Technical sanction approval number & B’lore Dated: 16.12.76-Rs.90.54 Crores Date. Latest Estimated cost-Rs.1435.00 Crores vide GO. No. WRD 66 NIN 2006 dated 28.07.2007 Revised project estimate of Ghataprabha Project Stage III amounting to Rs.1210.51 crores vide GO dated 18.10.2009. Length of Canal G.R.B.C. G.L.B.C Main Canal, 199 Km. 109 Km. Branch Canal 88 Km 210 Km Distributories 994 Km 494 Km Length of ayacut roads/ I.T.roads 600.35 km Districts benefited Belgaum, Bagalkot Athani, Chikodi, , Hukkeri, , Number of villages and Taluks Ramadurg, , , Bagalkot, Bilagi, Benefitted Hungund, Jamakhandi, taluks. Number of W.U.C.S: Formed 302 Registered 302 Handed over 285 Physical Financial Programme during 2012-13 --- Rs. 117.00 Crores. Progress achieved upto end of March --- Rs. 147.57 Crores 2013 Programme for 2013-14 (Physical & 2497 Ha Rs. 174.00 Crores Financial) 3,08,326 Ha Cumulative progress upto End of March (including Stage-I, II Rs. 1691.45 crores. 2013 & III)

72

12.1.2 HIPPARAGI IRRIGATION PROJECT

Dam & Allied works: Barrage proper: Barrage proper: The barrage works are completed. b) Crest gates: Fabrication & erection of crest gates works completed and water impounded (stored) in the reservoir since 2004.

Lifting systems: The works for the lifting systems of two foreshore LI schemes, namely and Ainapur on turnkey basis are entrusted. The works of Ainapur lifting system and Halyal stage-I & II and Karimasuthi 3rd stage and Savalgi –Tungal 4th stage under Halyal LIS are under progress as per the following:

Ainapur LIS: Works of Pump House, Rising main & Delivery Chamber are completed. Length of East canal is 27 .52 Kms & West canal is 13 Kms. Works from Km.0.00 to 27.52 of Ainapur East canal are completed &. Km.No.1 to 5 of West canal is completed&Km6to12 are nearing completion. Distry.of 11 blocks coming under east canal are under progress. Distry.of 15 blocks coming under west canal are also under progress. In West canal km No. 12 head work of additional lift and other works of main canal are under progress.

Pumps and motars testing works are completed and the Ainapur LIS is commissioned on 12-04-2011 by honorable irrigation minister by letting water in to East and West canals and distributories

Halyal L.I.S.: Works of pump House, Jackwell, Delivery Chamber & Rising Main under Stg-1 & 2 are completed. Work of Intake Canal is nearing completion. Lead off canal works and combined canal works are completed. Length of East canal is 39 Kms & West canal is 22.00 Kms. Works of East Canal Km 0.00 to 39 are completed and remaining 1km is nearing completion. Work from 0.00to 20km of West canal are completed and balance 2.00km are under progress.

Distributories of 21 blocks under east canal are under progress. Under Halyal West canal. Distributory network of 11 blocks are under progress. Pumps and motars testing works are under progress and the Halyal LIS is trial run by letting water in to East canals of Hayal LIS di

Karimasuti L.I.S.: Work of jackwell, pumphouse, machinery and delivery chamber with combined canal for Karimasuthi Lift is under progress. Length of east canal is 75 Km. and the works are completed. Distributory network of 46 blocks are under progress. In Karimasuthi west canal Km 0 to 37 works

73 up to 33km are completed and remaining works are under progress. In Karimasuthi East canal km no 53 head works of additional lift and other works of main canal and distributories are under progress. Pumps and motars testing works are completed and the Karimasuthi LIS is trial run by letting water in to East canals.

Savalgi-Tungal L.I.S.: Intake canal & Pump House are in progress. Work of Rising main & delivery chamber are completed. Works of Km.3 and 7 of East Canal are in progress and works in Km 1 to 7.40 of west canal are also completed. Under east canal Dy. Of 18 blocks and bunder west canal Dy. Of 5blocks are under progress.

Land acquisition: Submergence: The total submergence of land at FRL is about 3000 ha, out of which 1659 ha (4100 Acres) is cultivable land and 1341 ha (3314 Acres) is in river portion.

Canals: Total extent of cultivable land required for this project is about 9884A 15 Guntas. The status of acquisition of cultivable land is as follows: a) Land acquired so far: 4836 A 24 Guntas b) Balance land under different stage of award: 5827A 31 Guntas c) An amount of Rs.58.02 crores have been paid towards acquisition of lands.

R&R works : A total of 26 villages consisting of 15,291 families involving a population of 1,04,976 will be affected. Now the government has approved the R&R package amounting to Rs.555.00 crores. Action is being taken to implement the same.

NAME OF THE PROJECT HIPPARAGI IRRIGATION PROJECT Location Hipparagi village Year of Inception 1973 Original and Latest estimated cost Original Estimated cost- Rs.186.70 Crores (Rs. in Crores), including Latest Estimated cost-Rs. 1521.78 Crores administrative/ Administrative approval: GO No. WRD / 21/ MBI/2008 approval number & Date. dated 26.02.2008. Length of Canal a) Main Canal 289 Km Districts benefited Belgaum, Bagalkot Number of villages and Taluks Athani, Chikodi, Jamakhandi taluks. Benefitted Physical Financial Programme during 2012-13 10000 Ha Rs. 230.00 Crores. Progress achieved upto End of March 6904 Ha Rs. 326.88 Crores. 2013 Programme for 2013-14 15000 Ha Rs. 199.50 Crores . (Physical & Financial). Cumulative progress upto End of 59308 Ha Rs. 1407.26 Crores. March 2013 Brief description Central assistance under AIBP (Prime Ministers’ Special Package) to this project is availed since 2007-08. CA received till date is Rs. 734.96 crores. Barrage works including erection of gates is completed. 74

12.1.3 MARKANDEYA RESERVOIR PROJECT

 Dam & Allied works: The dam and allied works have been entrusted to KSCC Ltd. The concreting work of dam is completed, dyke works are also completed. Construction of parapet is completed and electrification work and erection of 6 crest gates are completed.  Canal works: Total length of Markandeya Left Bank Canal is 15 Kms, works in Km no. 1 to 4 and from Km.6 to 15 are completed. Balance lining work is under progress in Km.5. The Right Bank Canal has a length of 71 kms. Km.1 to 71 are completed. Water is let out on trial run upto Km.71.  Distributories: Total No. of distributory blocks are 45 under Right Bank Canal. All the works are completed except Dy.No.2,3 & 12 which are stopped due to land acquisition problem Under Left Bank Canal Dy.No.3,6A & 6B are completed and balance Dy. works are in progress.

 LIS: The GOK has accorded administrative approval during April 07 for taking up the LI Scheme. The estimate and DTP for the above lift component are approved in the TSC & now alternative proposal for Murgod LIS was placed before the TSC and the observations made by TSC are complied. The cost of above scheme is Rs.47.13 crores (SR of 2003 – 04). The contemplated atchkat is 2718 and 1939 Ha respectively.(This work is now under execution by Malaprabha irrigation zone Dharwad).  R& R works: This project involves submergence of 7 villages affecting 833 families consisting of 3800 persons. Two Rehabilitation centers at Santi-Bastiwad and Waghwad are already completed. Shifting of PAFs to these R&R centers is also completed. The third rehabilitation center near Basavana-Kuduchi village in Belgaum dist. has been identified for shifting of balance PAFs. Developmental works at this center are also completed.

75

NAME OF THE PROJECT MARKANDEYA RESERVOIR PROJECT

Location Shirur village

Year of Inception 1998

Original Estimated cost-Rs.120.00 Crores

Original and Latest estimated cost Latest estimated cost- Rs.341.84 Crores

(Rs. in Crores), including Administrative approval No. WRD 08 VEBYAMA administrative/ 2003 dated 28.07.2007. approval number & Date.

Length of Canal R.B.C. L.B.C.

a) Main Canal 71 Km 15 Km

b) Distributories 183 Km -

Districts benefited Belgaum

Number of villages and Taluks Belgam, Hukkeri, Gokak, Saundatti taluks. Benefitted

Physical Financial

Programme during 2012-13 --- Rs. 15.50 Crores.

Progress achieved up to end of --- Rs. 3.64 Crores. March 2013

Programme for 2013-14 (Physical --- Rs. 15.00 Crores & Financial).

Cumulative progress upto End of 14,384.64 Ha Rs. 319.28 Crores March 2013

Brief description  R & R centre works of 7 submerged villages have been completed and shifting of PAF is completed. Chachadi-Murgod LIS is planned in balance works of this project at estimated cost of Rs.47.13 crores to benefit 2718 ha. and 1939 ha. of land respectively (This work is now under execution by Malaprabha irrigation zone Dharwad)

76

12.1.4 DUDHGANGA IRRIGATION PROJECT

Doodhganga Irrigation Project is an interstate project of Maharastra and Karnataka. The project envisages construction of composite dam across the river Doodhganga near village Asangaon of Radhanagari taluk in Kolhapur District of Maharastra state. This project would provide irrigation benefits to 44,766 Ha. in Maharastra state and 15,167 Ha in Karnataka state. The planned utilisation is 28.00 TMC. Outlet potential created to end of Jan ’10 is 3800Ha. The original estimated cost - Rs.124.00 crore (based on SR of 1999-2000). Further the comprehensive estimates of Rs. 1460.57 crores (including State share of Rs. 309.80crores) at 2007-08 price level prepare by Govt. of Maharastra was approved by Planning Commission, GOI. Allocation for Karnataka State – 4.00 TMC .

Project comprises of from 1 st entry in to Karnataka: Nidhori Branch canal (NBC), Bidari Branch canal (BBC) Dattawad Branch Canal (DBC) and Kurundwad Branch Canal (KBC)  NBC : Total length is 25.607 Kms (21.567 Kms Only in Karnataka)  BBC : Total Length is 21.195 Kms (15.510 Kms, Only in Karnataka)  DBC : Total Length is 26.570 (26.57 Kms Only in Karnataka) KBC : Total Length is 21.32 Kms ( 9.61 Kms Only in Karnataka)

Nidhori branch canal (State entry at 25 th Km.) : Total Length of Nidhori branch canal : 25.607 Km Works completed from Km.25 to50 (Tail end). All distributory blocks are completed.3617 Ha. of O.P. has been created on NBC. FIC potential of 3383.10 Ha created upto end of Jan- 2010

Bidri branch canal (State entry at 44 th Km.): Total Length of Bidri branch canal : 21.195Km The works are from Km. 46 to 49 and 54 to 62 are completed. The works in Km.44, 45 & 50 are under progress. For the works of Km.51 and 52 (tunnel from Ch. 49.500 to 51.200 Km. with approaches and exit) tender is finalised. The work of Km. No. 53 stands deleted due to modified alignment. The works of Km. 63 to 65 are held up due to LAQ n Maharastra. Works of Dy. Blocks are under progress and nearing completion. An op of 182.72 Ha is created on Bidari branch canal.  Dattawad branch canal : (i) Dattawad link canal is 0.700 Km work in Karnataka area is partly tackled. However, work is rescinded due to LAQ problem in Maharastra.

 (ii) Dattawad RBC from Ch. 0+000 to Ch.7+650 km (tail end) alignment approved and LAQ proposals is submitted. (iii) Alignment of Dattawad LBC from Ch.0+000 to 12+000Km is approved and survey of Km.13 to 19 (tail end) is in progress. Kurundwad branch canal: The Kurndawad branch canal is to be executed by Maharastra State (including 9.61 Km long canal of Karnataka. 77

. 12.1.5 LIFTING OF HIRANYAKESHI WATER INTO G.R.B. CANAL

NAME OF THE PROJECT DUDHGANGA IRRIGATION PROJECT Location Asangaon village (Maharashtra State) Year of Inception 1992 (Canal in Karnataka State) Original and Latest estimated cost Original Estimated cost-Rs.124.00 Crores (Rs. in Crores), including Latest Estimated cost –Rs. 309.80 Crores administrative/ Administrative approval. Ja.SAM: E-1: (VI.DN: Technical sanction approval number & GAM: 2000 (P-2) Dated.17/4-2002 (For Rs.-124.00 Date. Crores)

Nidhori Dattawad Branch Length of Canal Bidri Branch canal Branch Canal Canal a) Branch Canal 21.57 Km 25.155 Km 30.00 Km Districts benefited Belgaum Number of villages and Taluks Chikkodi taluk. Benefitted Physical Financial Programme during 2012-13 --- Rs. 10.89 Crores Progress achieved up to end of March --- Rs. 10.11 Crores. 2013 Programme for 2013-14 1000 Ha Rs. 7.41 Crores. Cumulative progress up to end of 3800 Ha. Rs. 150.00 Crores. (Karnataka’s share) March 2013 This project is being assisted under Hon’ble PM’s Brief description Special Rehabilitation Package. An amount of Rs. 7.406 crores is availed under PM’s package till date.

Hiranyakeshi LIS is proposed to lift 8 TMC of water from Hiranyakeshi river to feed GRBC during Khariff season. 8.00 TMC of water has been allocated under scheme ‘A’ of KWDT. This scheme has been proposed to meet the likely shortage of water due to over utilisation under GLBC. The said LIS has been entrusted to M/s Kirloskar Brothers Pvt. Ltd, on turnkey basis and is under progress.

The intake channel work is under progress. The Jackwell work is Under Progress.

Pumphouse is under progress. Raising Main work is under progress. Procurement of Pumping machinery is done. This project needs 6.099MW power which is sanctioned and the work is under progress.

78

LIFTING OF HIRANYAKESHI WATER INTO NAME OF THE PROJECT G.R.B. CANAL.

Location village

Year of Inception 2005

Year of completion Under progress.

Estimated cost - Rs. 30.00 Crores. Administrative Original and Latest estimated cost approval WRD: 03: NIN: 1995: Bangalore dated including administrative/Technical 23.8.2003Technical sanction CIN.109. For June sanction approval number & Date. 2005.

Length of Canal

a) Main Canal

b) Branch Canal Detailed survey is taken up. c) Distributories

d) F.I.C.

Districts benefited Belgaum

Number of villages and Taluks Hukkeri Benefitted

Physical Financial

Programme during 2012-13 - Rs. 5.00 Crores

Progress achieved up to end of March - Rs. 0.052 Crores 2013

Programme for 2013-14 - Rs.4.00 Crores (Physical & Financial)

Cumulative progress up to end of March - Rs. 18.81 Crores 2013

79

12.1.6 BELLARYNALA PROJECT

The Bellary nala irrigation project envisages to irrigate 8200 ha of land in Gokak and Saudatti taluks of Belgaum districts by constructing a dam across Bellary nala which is a main tributory to Markendaya river. The master plan committee has allocated 1.68 TMC of water under scheme ‘A’ of KWDT.

Excavation for dam foundation, concreting in block 1 to 6 and 8 to 18 are under progress. C planning is approved and alignment from Km. 1 to 65 is also approved All the works of main canal are carried out in various stages except canal length coming under forest area. Government has accorded administrative approval to the revised project estimate of Bellarynala Irrigation Project amounting to Rs143.55 crores vide GO No.WRD 02 VEBYAMA 2005, dated 28/7/07. As per Govt. Directions the project was temporarily stopped from Sept.2008 and now the work is resumed.

NAME OF THE PROJECT BELLARYNALA PROJECT Location Kardikolla village Year of Inception 2005 Year of completion (in case of Completed Under progress Projects) Estimated cost: Rs. 143.55 Crores Original and Latest estimated cost Administrative approval: No. WRD 02 (Rs. in Crores), including administrative/ VEBYAMA 2005 dated28.07.2007 Revised estimate for Rs544.43 crores is submitted to MD Approval number & Date. KNNL Bangalore and placed before TSC. For TSC observations compliance is under process. Length of Canal a. Main Canal b. Branch Canal Detailed survey is taken up c. Distributories d. F.I.C. Districts benefited Belgaum Number of villages and Taluks Benefitted Gokak, Saundatti. Physical Financial Programme during 2012-13 - Rs. 11.00 Crores Progress achieved up to end of March 2013 - Rs. 11.62 Crores Programme for 2013-14 - Rs. 27.00 Crores (Physical & Financial) Cumulative progress upto End of March - Rs. 164.20 Crores 2011

80

12.1.7 SRI RAMESHWAR L.I. SCHEME

This lift Irrigation is proposed to irrigate 13800 Ha areas of Gokak, Ramadurga and Savadatti Taluks of Belgaum District by utilising the 2.2 TMC of water. The water will be drawn from Ghataprabha river by suitable intake structure. Rising main: Works of rising main total length 17.20 km is completed. Jackwell: Works are in progress. Intake Channel: The earthwork is completed, lining is under progress. Land Acquistition : Intake Channel, Pump House, Jack well & Sub Station: These are Located near Village covering an area of 5.10 Acres for which 6(1) Notification has been issued. Electromechanical Components: Design & Drawings of Electro mechanical works such as Pumps, Motors, 110 KV sub-stations is approved. Erection is under progress. Canal Network : Approximate length of main canal System is about 78 Km and approximate length of distributory network system is about 150 Km. out of 78Km 0 to 28 Km are in progress and for remaining 50Km tenders are in progress. For Distributory network survey work is completed and estimates are under preparation.

NAME OF THE PROJECT SRI RAMESHWAR L.I. SCHEME Location village Year of Inception 2005 Year of completion (in case of Completed Under progress Projects)

Original and Latest estimated cost Original cost: Rs. 218.42 Crores (Rs. in Crores), including administrative/ Administrative approval No: JaSamE: 14: NIN: 2001: Bangalore: Dated.23.8.2003. Technical sanction approval number & Date. Technical sanction: CEI (N) Reg. No. 110 for 06/2005 Length of Canal a) Main Canal b) Branch Canal Detailed Survey is taken up. c) Distributories d) F.I.C. Districts benefited Belgaum Number of villages and Taluks Benefitted Gokak Physical Financial Programme during 2012-13 1350 Ha Rs. 79.00 Crores Progress achieved up to end of March 2013 1237 Ha Rs. 72.17 Crores Programme for 2013-14 (Physical & Financial) 5000 Ha Rs. 81.84 Crores Cumulative progress up to end of March 2013 2980 Ha Rs. 192.67 Crores

81

12.1.8 KINAYE IRRIGATION PROJECT

Kinaye irrigation project is at Kinaye in Belgaum district envisages construction of an earthen bund across Mangothri Nala. It is proposed irrigate an area of 1200 Ha in Khariff season and 275 Ha in Rabi season which is spread over Kinaye, Bhadravadi, Rankunde villages of Belgaum district. The administrative approval has been accorded for Rs. 9.309 crores under G.O.dated 22.09.2006.

NAME OF THE PROJECT KINAYE IRRIGATION PROJECT Location Mangotri Nalla near Kinaye village Year of Inception 2006 Year of completion (in case of Completed Under progress Projects) Estimated cost: Rs. 9.309 Crores Administrative approval: No. WRD 137 Original and Latest estimated cost VEBYAMA 2004 dated22-09-2006 (Rs. in Crores), including administrative/ Revised estimated cost Rs 35.43 Crores Approval number & Date. Administrative approval No. WRD 13 VBYAE 2009 dated 28-09-2010 Latest re- revised estimated cost is 52.00 crores Length of Canal e. Main Canal f. Branch Canal Detailed survey is taken up g. Distributories h. F.I.C. Districts benefited Belgaum Number of villages and Taluks Benefitted Belgaum. Physical Financial Programme during 2012-13 - Rs. 7.00 Crores Progress achieved up to end of March 2013 - Rs. 0.05 Crores Programme for 2013-14 (Physical & Financial) - Rs. 7.00 Crores Cumulative progress upto End of March 2013 - Rs.0.35 Crores

82

12.1.9 Malikwadi Lift Irrigation Scheme (rejuvenation works) This scheme comprises of rehabilitation work including Filling of tanks of Yadanwadi, Vadagol and Bainakwadi villages of chikodi Taluka and also including rejuvenation of lift irrigation scheme of Malikwad villge which is at stagnate at present. The work is entrusted on turn key basis and the work is under progress now.

Name of the Project Mailkwad Lift Irrigation Scheme (Rejuvenation works) Location Mailkwad of Chikodi Tq. Year of inception 5/2012 Original and latest estimated cost Original Estimated Cost:Rs 146.00 lochs. Administrative approval vide G.O.No. d¸ÀAE/92/«¨ÁåE/2011/ ¢ :31-3-2011 Technically sanctioned vide CIN-234/Oct 2011 District Benefited Belgaum Number of village and taluka Chikodi Tq: Malikwad, Yadanwadi, Vadgol & Bainakwadi benefited villages. Physical Financial Programme during 201 2-13 - Rs1.00 Cores Programme for 2013-14 (Physical - Rs2.00 Cores land financial)

12.1.10 Construction of Sadalaga bridge-cum-barrage For construction of Sadalaga bridge-cum barrage across Dudhaganga river near Sadalga village of Cikodi/Sadalage constituency the DPR is administratively approved for Rs 5.00 crores by Government vide G.O No d¸ÀAE-1/ «zÀÆUÀ 2010 ¨ÉAUÀ¼ÀÆgÀÄ 29-4-2010 the detailed estimated amount of Rs 5.00 cores. Is technically sanctioned vide CIN 236 Dated: 11/2010 tenders are invited and contract is fixed by the SE KNNL GRBCC Hidkal Dam and work order issued vide order No 2341 dated: 11/2011 The work is already under progress. During 5/2012 Rs 2.358 crores R.A bill was paid to the contractor. The contract amount for the above work is Rs 5.8328 crores and approved EFI amount is Rs 0.9962 crores and the total amount of the above work is Rs 6.8290 crores.

Name of the Project Sadalaga bridgs cum barrage Location Sadalaga Tq: Chikodi Year of inception 11/2011 District Benefited Belgaum Number of village and taluka benefited Chikodi Tq: Sadalaga village. Physical Financial Progress achieved up to end of March 2013 ------Cumulative progress up to end of March 2013 ------

12.1.11: Construction of Sangam Barrage. Detailed Project report for construction of sangam Barrage is prepared for Rs 39.45 crores and submitted to M.D KNNL Bangalore the DPR was approved with certain conditions.

The above estimate was modified for Rs 40.00 crores and is under scrutiny.

83

12.1.12: Filling of Shiragaon-Basavanna Tank. DPR for the work of filling of Shiragaon Basavanna percolation tank of chikkodi Tq is got prepared and administratively approved for Rs 351.15 lakhs vide GO No d¸ÀAE-4/ «zÀÆUÀ 2012 ¨ÉAUÀ¼ÀÆgÀÄ Dated: 16-11-2012 and the estimate is technically sanctioned vide CIN 329 dated: 11/2012 DTP for the above work is approved and tenders are invited.

12..13: Filling of Kadapur Tank: Detailed project report for the work of filling of Kadapur tank of Chikodi Tq from Krishna river is got prepared for Rs 390.00 lakhs and the estimate is Administratively approved by the Government vide G.O No d¸ÀAE/82/J£ïLJ£ï/2012 Dated: 2-11-2012

This project comprises of filling of the tank & there by raising the ground water table. The detailed estimate is technically sanctioned vide CIN 382 dated: 12/2012 Tenders for the above work are invited.

12.1.14. Filling of 18 tanks of Hukkeri Tq & 4 tanks of chikodi Tq. (Total 22 tanks) from Hiranyakeshi river

Administrative approval for the above work for an estimated amount of Rs 49.50 crores is accorded by the Govt vide G.O No d¸ÀAE/39/ «¨ÁåE/2013/ ¨ÉAUÀ¼ÀÆgÀÄ Dated: 19-3-2013 Detailed Project report for the above work is under preparation.

12.2 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, MALAPRABHA PROJECT ZONE, DHARWAD ******

PREFACE:- The originates near Ghats in Sahyadri and flows eastwardly for a length of 200Km before joining the River Krishna at Kapila Sangam in Bagalkot District. The annual average yield of the river is 1368m.cum (48.35tmc)

Malaprabha Project Zone, Dharwad was formed on 07/09/2007 in pursuance of the Government order No.WRD.137.SeASu:2007, Dtd:04/09/2007 with a view to increase the tempo of construction work in the Irrigation Projects as a result of increased provision of the plan allocation in the state.

Malaprabha Project Zone is incharge of the following projects.

On-going Schemes 1 Malaprabha Project 2 Harinala Irrigation Project Kalasa Nala & Bandhur Nala Diversion 3 Schemes. 4 Javaluhalla L.I.S. * 5 Bennihalla L.I.S. * 6 Kolachi L.I.S. * 7 Konnur L.I.S. * 8 Shiggaon L.I.S

(*) To irrigate suffering atchkat of tail end distributaries of MRBC / NBC, under Malaprabha Project.

84

So far, an irrigation potential of 2,07,360 Ha, has been created under the above projects. An expenditure of Rs.1628.60 Crores has been incurred under the above schemes to end of March- 2013.

Out of the above schemes Harinala Project has been completed during 2006-07 and the remaining schemes are under different stages of progress. The designed district-wise ultimate irrigation potential details are given below;

District Malaprabha (Ha.) Total (Ha.) Belgavi 61,773 61,773 Bagalkot 27,506 27,506 Dharwad 44,078 44,078 Gadag 62,775 62,775 Total Area:- 1,96,132 1,96,132

12.2.1 MALAPRABHA PROJECT

Malaprabha Project comprises a dam across the River Malaprabha, near Navilutheertha in Belgaum district to provide irrigation to an extent of 1,96,132Ha in Belgaum, Bagalkot, Dharwad and Gadag districts. Malaprabha River is one of the tributary of River Krishna.

Project Comprises:- It is a composite dam of 154.53mtr length and 40.23mtr height. The gross capacity of reservoir is 37.73tmc Live capacity of the reservoir is 34.346 tmc Malaprabha Right Bank Canal (MRBC) – 142Km. Distributaries under MRBC - 60 Nos. Malaprabha Left Bank Canal (MLBC) – 150Km. Distributaries under MLBC - 58 Nos

1) Dam is completed and water impounded since 1973. 2) Total length of MRBC is 142Km which is completed and it includes 60 distributaries which are completed. Remodelling works are under various stages of progress. 85

3) Under MRBC major Branch Canal of NBC of 42Km which is also completed and FIC works for 11625Ha are remains. 4) Total length of MLBC 150Km and 58 distributaries all are completed. Only FIC work of 1757Ha remains and remodelling works are under various stages of progress.

Malaprabha Project (MRBC) has been included under AIBP since 1996-97. Before bringing the project under AIBP i.e., as on 01/04/1997, 108Km.of MRBC, 127Km of MLBC including the dam were completed. Since 1996-97, there has been gradual progress in the canal works. Balance remodelling works of MLBC and remodeling of LIS & 8 Foreshore LIS were also included under AIBP. In 2009 the DPR of Malaprabha was revised and modified project report was approved in February 2010 amounting to Rs.1383.48 Crores. The proposal of AIBP for year 2011- 12 in respect of Malaprabha Project was submitted to M.D.vide Ltr.No:3031, Dt:15/10/2011 according to this the financial target set for 2012-13 is Rs.110.00 Crores.

The financial progress of works so far achieved during 2012-13 year upto end of March-2013 is Rs.80.35 Crores which includes Rs.36.63Crores of expenditure on Land Acquisition and Rs.43.72 Crores towards works. The expenditure incurred on Malaprabha Project since inception till March- 2013 is Rs.1456.04 Crores.

NAME OF THE PROJECT MALAPRABHA PROJECT Location Naviluteertha Year of Inception 1960 Original and Latest estimated cost (Rs. in Crores), Original Estimated cost Rs.20.00 Crores. including administrative /Technical sanction Administrative approval: GO No.PWD. approval number & Date. 59.GMP.77, B’lore Dated: 04/02/1980 Rs.162.09 Cr. Technical sanction No.:CE,Irrigation(North)Zone, Belguam Reg.No.CIN.7. for June-1980 Rs.162.09 Cr. Latest Estimated cost Rs.1383.48Crores vide G.O No: WRD/51/MPS/2009, Bangalore Dated:07/10/2009 and investment clearance by Planning Commission, GOI vide No.2(54) 2010 WR, Dated:01/02/2010 Length of Canal M.L.B.C. M.R.B.C a) Main Canal, 150 Km. 142 Km. b) Branch Canal 26 Km. 42 Km. c) Distributories 280 Km 677 Km. Length of ayacut roads/I.T.roads 282.62 Km Districts benefited Belgaum, Dharwad, Gadag, Bagalkot Number of villages and Taluks Bailhongal, Ramadurg, Saundatti, Badami, Benefi tted Navalgund, Hubli, Naragund, Ron, Gadag taluks. Number of W.U.C.S: a) Formed 266 b) Registered 231 c) Handed over 208 Physical Financial Programme during 2012-13 99 Ha Rs. 159.50 Crores Progress achieved up to end of March 2013 -- - Rs. 101 .80 Crores Cumulative progress up to End of March-2013 1,96,033 Ha Rs. 1334.35 Crores Brief description This project is being assisted under AIBP since 1996-97.

86

12.2.2 HARINALA IRRIGATION PROJECT

Harinala project envisages construction of an earthen dam across Harinala, a tributary to river Malaprabha to irrigate 3,480Ha in Bailahongal taluk of Belgaum Dist.

Dam & Allied works : The dam works including head regulators for LBC and RBC are completed. Water is impounded in the dam.

Canal works: The entire length of RBC (11 km) and LBC (9 km) are completed. Total potential of 3,480Ha under this project has been created. FIC works are completed.

R & R works: The project involves partial submergence of only one village involving 256 families and out of 256 R & R works for 58 families are completed. For balance of 198 families R & R works are under progress.

NAME OF THE PROJECT HARINALA IRRIGATION PROJECT Location Village Year of Inception 1998 Original Estimated cost - Rs. 0.83 Crores Original and Latest estimated cost Latest Estimated cost-Rs.73.00 Crores Administrative Approval No: CE: 114: MPS: 92 (Rs. in Crores), including administrative/ Dated 11/14.9.98 (Rs. 26.95 Crores). Technical sanction approval number & Date. Technical sanction: CEI (N): BGM: Reg.No.CIN–17 for May 1999 (Rs.26.95 Crores). Length of Canal Left Bank Right Bank a) Main Canal 9.00 Km 10.72 Km Districts benefited Belgaum. Number of villages and Taluks Benefitted Bailhongal taluk. Physical Financial Programme during 2012 -13 --- Rs.0. 75 Crores Progress achieved up to end of March -2013 --- Rs. 1.04 Crores Programme for 2012-13 (Physical Financial) --- Rs. 1.00 Crores Cumulative progress up to end of March 2012 3,480 Ha Rs. 74.21 Crores

87

12.2.3 KALASA NALA AND BANDHUR NALA PROJECT

 These two projects envisage diversion of 7.56 TMC of water to Malaprabha dam by construction of dam across the above nalas and diversion canals. Administrative approval for these two projects is accorded by Government in August 2000. Forest clearance for these projects is pending for want of CWC clearance for the project. The in principle clearance given by CWC to these projects has been kept in abeyance and inspite of repeated attempts by Government of Karnataka, the Union Government has not been able to with draw the order of abeyance on “IN PRINCIPLE CLEARANCE”

 The KNNL Board has recommended in its 25th meeting held on 7.6.2005 to take up works in non-forest area by entrusting the work to any Government agency. Accordingly the Government vide its order No.JASAME 22 VEBYATA 2004 (Part-1) Bangalore dated 9.10.06 has approved to take up Kalasa Nala Banduranala diversion schemes in non-forest area. (4.40 km out of 4.80 km of Kalasanala and 4.90 km out of 5.80 km of Banduranala).

 Further the Government vide letter No.JASAME 22 VEBYATA 2004 dated.21.10.06 has given directions to take-up the above works through KSCC duly following all the necessary procedures as per KTPP Act 1999.

 The Chief Engineer, KNNL, Irrigation(North)Zone, Belgaum has submitted an estimate of Rs.21.24 crores for construction of Kalasa Nala Dam and approval has been accorded to the same.

 Since the project is a inter-state dispute project and some time was required for KSCC to take up works on tender basis, the works in non-forest areas were taken-up by entrusting 2 works on piece work basis, each not exceeding Rs.5.00 lakhs, in respect of Kalasa Nala diversion scheme.

 In the meantime the Government vide Order No.WRD 36 VEBYATA 2006, Bangalore dated 15.3.2007, has approved to execute the works of Kalasanala diversion scheme in non-forest areas on piece work basis, till the tendering process for balance work is completed.

 In this order, Government has withdrawn the works entrusted to KSCC and has instructed KNNL to proceed with tendering process for balance works immediately duly following the prescribed procedure as per KTPP Act 1999.

 Accordingly tender for the balance work of ICC from Kalasa to Malaprabha River was invited and work is awarded and it is in progress.

 Tenders are finalised for Phase–II of the balance work of ICC from Kalasa to Malaprabha River (Earthwork and Box pushing technique) and works are in progress.

 Tenders of Rs.20.03 Crores have been awarded for the construction of 2 vent box at Ch:1920 to 2070M by box pushing technique (2 nd Stage Balance works) from Ch:145 to 5005m for the link canal from Kalasa Dam to Malaprabha River.

 During 2012-13 progress of Rs. 26.04 crores is achieved and the total progress achieved is 122.56 crores.

88

NAME OF THE PROJECT KALASA NALA AND BANDHUR NALA PROJECT Location – Kalasa Nala Project Nerse village - Bhandur Nala Project Year of Inception 2006 Year of completion (in case of Completed Under progress (Kalasa only) Projects) Original and Latest estimated cost Original Estimated Cost (Rs. in Crores), including administrative/ Kalasa Nala - Rs. 44.78 Crores Technical sanction approval number & Bhandur Nala - Rs. 49.20 Crores Date. Administrative approval No. a) Kalasa nala: ID.37.WBT. 2000: Dtd.22.8.2000 b) Bhandur nala:-.ID-4.WBT:2000: Dtd:22.8.2000. Tech.Sanction No: a) Kalasa nala - CIN.Reg.No.270, March 2002 b) Bhandur nala - CIN.Reg.No.269, March 2002. Districts Benefited Belgaum, Dharwad, Gadag and Bagalkot Number of villages and Taluks Hubli-Dharwad & Other villages (Drinking water Benefited supply) Programme during 2012-13 Physical Financial Rs. 17.00 Crores for KalasaNala --- Rs. 0.50 Crores for BhandurNala Progress achieved upto end of March Rs. 34.99 Crores for KalasaNala --- 2013 NIL for BhandurNala Cumulative progress upto End of March Rs. 119.49 Crores under Kalasa Nala &

2013 Rs. 0.57 Crores under BhandurNala

89

12.2.4 JAVALAHALLA L. I. SCHEME

The project envisages diverting a part of water flowing through Javalahalla a tributary of Malaprabha river near village of Taluk , Belgaum Dist. by constructing a diversion structure. The water is diverted to a Jackwell through an intake canal. The water is then lifted by pumping through rising main fed to existing canal net work of Distributory under NBC to provide irrigation facility to 4736Acres.(1917Ha.) suffering atchkat of Shirasangi Distributory under NBC command. The Project is completed except finishing work & electrical supply from HESCOM which is under progress.

NAME OF THE PROJECT JAVALUHALLA L.I. SCHEME Location: Kittur village Year of Inception: of date of the working 2005 – 18/07/2005 once site Year of completion (in case of Completed Under progress Projects) Original Estimated : cost. Rs. 3.33Crores Original and Latest estimated cost Administrative approval: WRD: 03:NIN:95 (Rs. in Crores), including administrative/ Dtd:23.08.03 Technical sanction approval number & Technical san ction: Chief Engineer, Irrigation(N), Date. Belguam Reg.No.CIN.10 for April – 2003 Districts benefited Belgaum Number of villages and Taluks Benefited Ramdurg Physical Financial Programme during 2012-13 - Rs. 0.50 Crores Progress achieved upto End of Marc h- - Rs. 0.11 Crores 2013 Programme for 2012 -13 (Physical & - --- Financial). Cumulative progress up to end of March - Rs. 4.50 Crores 2013

12.2.5 BENNIHALLA L.I. SCHEME (5 NOS.)

It is constructed near Nargund taluk of Gadag district. The scheme proposes series of weirs at Banahatti, Kuralageri, Surkod, and Radder to irrigate the suffering atchkat of 3,868Ha under NBC.

Banahatti: Deliver chamber completed. Out of 3,664M about 90% of raising main is completed. Jackwell-cum-Pumphouse work is under progress and command upto 3 rd stage. Other works like Diversion weir, intake canal and control room are under progress. Pumps & motors procured yet to be installed.

Kuralageri: Delivery chamber raising main Jackwell-cum-Pumphouse and control room work is completed. Other works like diversion weir partly completed. Pumps and motors which is under operation electrical work is completed.

90

Surkod: Head works like intake canal, Jackwell-cump-Pumphouse, delivery chamber and raising main. Control room and Diversion weir is completed. Pumps and motors are installed and electrical work in under progress.

Khanapur: Head works like intake canal, Jackwell-cum-Pumphouse are completed. Diversion weir is completed. Control room is under progress. raising main is completed. Delivery chamber is to be started. Pumpse and motors are installed and electrical work in under progress.

Radder Naganur: Diversion weir, intake canal, Jackwell-cum-Pump house, control room, delivery chamber and raising main are completed. Pumps and motors are installed and power line work is also completed.

NAME OF THE PROJECT BENNIHALLA L.I. SCHEME (5 NOS.) Banahatti, Kurlageri, Surkod,Khanapur, Reddar Location Naganur Year of Inception 2005 Original Estimated cost: Rs. 17.33 Crores Original and Latest estimated cost Administrative approval: WRD/ 58/MPS/1999 (P), (Rs. in Crores), including B’lore dated: 23.08.03 administrative/ Technical Sanction : CE I (N) Reg.No.163 for August Technical sanction approval number 2005. & Date.

Districts benefited Gadag Number of villages and Taluks Nargund Benefited

12.2.6 KOLACHI L.I. SCHEME

The project envisages diverting a part of water flowing through Bennihalla at village Asuti of Ron Taluk, Gadag Dist. by providing obstruction in the form of low height diversion structure. The water is diverted to a jackwell through on intake canal. The water is then lifted by pumping fed to existing canal network of KRBC through rising main to provide irrigation facility to 3800 Acres (1538 Ha.) suffering atchkat of KRBC Command.

The water allocation as per the revised Master Plan of Krishna Waters under Scheme `A` is 0.30 tmc. The estimated cost of the project is Rs.190.61 lakhs. The work is entrusted on turnkey basis. The work is started on 12-9-2005 & it is proposed to be completed by end of June-2009. The Project is completed except finishing work & electrical supply from HESCOM which is under progress.

The above LIS is entrusted to M/s. SPML on turnkey basis. Head works like intake canal, Jackwell-cum-Pumphouse, Control room, Raising main, Delivery chamber are completed. Diversion weir is nearing completion. Pumps and motors are installed and electrical work completed.

91

Name of the Project KOLACHI L.I. SCHEME Location: Asuti village Year of Inception: 2005 Year of completion (in case of Under progress Completed Projects)

Original and Latest estimated Original Estimated cost: Rs. 2.25 Crores cost Administrative approval : WRD. 58.MPS.1999 (P) (K), (Rs. in Crores), including Bangalore dated: 23.08.03. administrative/ Technical Sanction:CEI (N). Reg.No.162 for August 2005. Technical sanction approval number & Date. Districts benefited Gadag Number of villages and Taluks Ron Benefitted

12.2.7 KONNUR L.I. SCHEME

The project envisages diverting a part of water flowing through Malaprabha River near the village Konnur of Naragund Tq. Gadag Dist. by constructing a diversion structure. The water is diverted to a jack well through an intake canal. The water is then lifted by pumping fed to existing canal net work of NBC through rising main to provide irrigation facility to 3932 Acres (1591 Ha.) suffering atchkat of NBC command. The water allocation under Scheme `A` is 0.39 tmc. The estimated cost of the project is Rs.884.36 Lakhs. The work is entrusted to M/s. SPML, Bangalore on turnkey basis. The work is started on Dtd:12/09/2005 & it is proposed to be completed by end of August 2009. The work is in progress.

NAME OF THE PROJECT: KONNUR L.I. SCHEME Location: Konnur village Year of Inception: 2005 Year of completion (in case of Under progress. Completed Projects) Original and Latest estimated cost Original Estimated cost: Rs. 6.15 Cr.Administrative (Rs. in Crores), including approval: WRD. 58.MPS.1999 (P), B’lore dated: administrative/ 23.08.03.Technical sanction No: CE I (N) Reg.No.161 Technical sanction approval number & for August 2005. Date. Districts benefited Gadag Number of villages and Taluks Nargund Benefited

FOR BENNIHALLA, KONNUR L.I.S & KOLCHI LIS Physical Financial Programme during 2012-13 - Rs. 4.00 Crores Progress achieved upto end of March 2013 - Rs. 0.90 Crores Cumulative progress upto End of M arch 2013 Rs. 22. 60 Crores

92

12.2.8 SHIGGAON L.I. SCHEME

The Shiggaon is envisages providing irrigation facility to draught area of Hangal, Shiggaon and Savanur taluks of Haveri District. It is proposed to utilize 1.5 TMC of water from River to provide irrigation facility to 9,900 ha. of lands in Hanagal, Shiggaon and Savanur taluks. The Government has accorded the Administrative approval for Rs.238.00 crores vide G.O.No.JaSamE 98 MMB 2008, Bangalore Dtd:13/01/2009 and entrusted the work to KNNL for execution.

The salient features of the Shiggaon LIS are as follows:-

1) Name of the Project : Shiggaon LIS 2) Name of the river : Varada River 3) Purpose : Irrigation 4) Climate : Moderately warm

LIFTING OF WATER FROM VARADA RIVER:

1) Name of the river : Varada 2) Purpose : Irrigation 3) Lift point location : Near Halasur village, Savanur taluk, Haveri District. 4) Quantity of water to be lifted : 1.50 TMC

The sprinkler irrigation system works are completed.

NAME OF THE PROJECT: SHIGGAON L.I. SCHEME Location: Near Halasur village of Savanur taluk in Haveri Dist. Original and Latest estimated cost Rs.238.00 Cr. Administrative approval: No. (Rs. in Crores), including WRD/98/MMB/ 2008, Bangalore Dtd:13/01/2009. administrative/ Technical sanction approval number & Date. Planned irrigation potential 9,900 Ha. Districts benefited Haveri Number of villages and Taluks Shiggaon, Hanagal and Savanur taluks of Haveri Benefitted district. No. of M I Tanks for stabilization 5 No. of Bandaras 6 Physical Financial Programme during 2012-13 5000 Ha Rs. 83.00 crores Progress achieved upto End of March- Rs. 68.01 crores 5338 Ha 2013 Cumulative progress up to end of March Rs. 220.04 crores 7847 Ha 2013

Works like intake canal, jackwell cum pump house, Brief description raising main, pumping machinery are completed.

93

INTAKE CANAL-WATER FILLED

Finished View of Substation & Control Room & Fencing work

Pumping Machinery - Finished View

Sprinklers & Lateral Lines:

94

95

12.3. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, MUNIRABAD

12.3.1 SINGATALUR LIFT IRRIGATION SCHEME (SLIS)

• Lingering works taken up on fast track. • The scheme will benefit 1,70,236 acres of Bellary, Koppal & Gadag districts. • Head regulator completed except gate. • Intake canal: 80% of excavation work is completed. • 1st lift pipe lining work and jack well excavation under progress. • Mundwad and lift work is completed and commissioned. • Jack well work is completed rising main work is under progress. • Hammgi branch canal work is completed • Mundwad branch canal work is under progress.

The project comprises of construction of barrage across River Tungabhadra near Hammige village of Mundaragi taluk in Gadag District to provide irrigation facility to an extent of 1,70,236 Acres (1,90,677Acres of cropped area in Bellary, Koppal and Gadag districts by utilising 18.55 TMC of water.

Stage-I comprises of utilising 7.64TMC to irrigate 76,181 acres and stage-II of utilising 4.39TMC to irrigate 44,055 acres. Government has accorded administrative approval to implement this scheme with the utilization of 12.03 TMC of water vide G.O. No. WRD 115 WBP 2003, dated 29-6- 2006. The DPR of Singatalur LIS amounting to Rs 1894.50 lakhs for utilizing 8.55 TMC (7.64 TMC stage I, 4.39 TMC stage II and 6.52 TMC Balance utilization) by providing irrigation facility to 170236 acres is is submitted to Government of Karnataka for according Administrative approval.

96

Barrage :- Work is completed and dedicated to the Nation on 04.09.2012

Canal and Lift Works :-

Right Side of the Barrage :-

Intake Canal :- Work is completed

1st Lift :- Work is completed and dedicated to the Nation on 04.09.2012

Ayyanahalli and Magala branch Canal :- Work is completed and Irrigation potential of 9000 Acres is created during 2011-12

Rajawala branch Canal :- Work is completed and Irrigation potential of 3000 Acres is created during 2012-13.

2nd Lift :- Work is completed and commissioned

Hadagali branch Canal :- Canal Works completed physically and an Irrigation potential of 14060 Acres is created during 2012-13

Left Side of Barrage :-

Intake Canal :- The total length of the Canal is 6.71 Km and excavation of Canal work is nearing completion.

Mundawad and Hammigi Lift :- Work is completed and dedicated to the Nation on 20.02.2013.

Hammigi branch Canal :- Canal Works completed and an Irrigation potential of 960 Acres is created during 2012-13

Mundawada Branch Canal :- The Canal works are under progress and an Irrigation potential of 1432 Acres is created during 2012-13.

Left Bank Main Canal 1 st Reach :- The works from 0.00 to 14.50 Km are entrusted to the agencies. Works from Km 0.00 to 9.00 are under progress. 2nd Lift :- Jackwell is completed upto roof level and rising main works are under progress.

Mundargi branch Canal :- The total length of the Canal is 72.00 Km. The works from Km 0.00 to 10.00 and from Km 33.00 to 50.00 are under progress.

Left Bank Main Canal 2 nd Reach :- The total length of the Canal is 28.98 Km and works are progress in 4 packages. 3rd Lift :- Work is nearing completion.

Rehabilitation and Resettlement Works :- The creation of Infrastructure in rehabilitation centre for the submerging villages Allipura, Gumgola and Bidarahalli are under progress.

97

AN OVER VIEW OF THE SINGATALUR LIFT IRRIGATION SCHEME:

1 Name of Project Singatalur Lift Irrigation Scheme Across near Hammige village Mundaragi Taluk, Gadag District. 2 Location Longitude : 70 0 50’ E Lattitude : 15 0 02’ N 3 Year of inception March 1998 4 Year of completion Project Works are under progress Original estimate Rs. 595 Cr vide G.O. No. ID – Original and latest estimated cost 90 MTP –98 and 29-12-2000. Technically in Cr. Including administrative sanctioned by Chief Engineer Vide CER No. 5 approval no. and date 28/2001-02 Latest cost 1894.50 Crores. Length of canal 6 a) Main canal LBC 207.34 km b) Branch canal 31.70 Km 8 District benefited Bellary, Gadag and Koppal

70 villages of Mundagi and Gada Tq. Number of village and Tq 9 09 villages of Koppal Taluk. benefited 20 villages of Huvina Hadagali Taluk Physical Financial Programme during 2012-13 11656 Ha Rs. 153.00Crores Progress achieved up to end of 10 9297 Ha Rs. 337.37Crores March 2013. Cumulative progress up to end of 12941 Ha Rs. 949.50 Crores March 2013.

98

12.4. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER TUNGA PROJECT ZONE, SHIMOGA

12.4.1 UPPER TUNGA PROJECT

The river Tunga is a major tributary of river Tunga Bhadra rises in Western Ghats and joins mother tributary Bhadra at Kudli about 14.50KM from Shimoga. Upper Tunga project envisages construction of new dam across at 100.00 meter down stream of existing Tunga Anicut near Gajanur in Shimoga Taluk and construction of Upper Tunga Main Canal; for a length of 270.00 km. It includes construction of tunnel of 4.00 km length and also distributary net work.

It is envisaged to create an irrigation potential of 80,494 hectares in Shimoga, Davanagere and Haveri Districts by utilising 12.24 TMC of water from River Tunga.

The Government of Karnataka has accorded administrative approval for this project vide No.ID: 25: MMM: 91: Bangalore dated: 3-10-1991 for Rs. 271.41 Crores and vide No.WRD: 38:WBP: 2005 (P):Bangalore dated: 21.11.2006 for Rs. 1,052.33 Crores and vide No.WRD:300:VIBYAYI:2011 dtd:13-07-2012 for Rs2477.18 Crores. The project is under the control of Karnataka Neeravari Nigama, Bangalore since 14.6.1999. DAM AND ALLIED WORKS: - Dam work is completed in all respect. Water is being stored in the dam since 2007. The instrumentation work and electrification works are completed. Power block portion of mini hydrl project is completed and further work of power house with tail race channel is taken up by private agency. Head regulator: Construction of regulator at Km.0145 is completed for providing hoisting arrangement for 5 gates is completed & Commissioned.

CANAL AND DISTRIBUTARY NETWORK: - Upper Tunga Project includes construction of 270.00 Km lengths of Main Canal including CD works, lining and Distributory Network. At present main canal alignment is approved up to 242 Km. Canal work up to Km 212 nearing completion. Work are under progress in Km 212-242 & Final allignment survey is in progress from Km 242-270 water is let out in canal up to 197.00 Km & 37452 Ha. of potential created.

99

• Tunnel from KM 168.50 to 174 :- Work is completed. • Railway bridge at Ch: 176.533 Km of main Canal: - An amount of Rs. 4.50 Crores has been deposited to Railway Dept implementation of works, the bridge work Completed. Distributory: Dist.No.1: Off-take point at Km108.35. Total length is 20.58 Km. Works are completed. Dist.No.2: Off-take point at Km. 166.267. Total length is 56.91 Km. Works are completed from 0 Km. to 30 Km. From Km 30 to 40 Balance works are nearing completion. Since Alignment beyond 40 km runs in reserve forest Alternative alignment studies are being conducted avoiding forest land. Dist.No.3: Off-take point at Km176.83. Total length is 23.00 Km. Works are completed except Km. 3, 4, 5 & 6, which is taken up in single package including Aqueduct and the work is nearing completion. Dst No.4 : Oftake point @ Km. 201.055 Total length is 20.32 Km. works are Completed. Dst No.5 : Oftake point @ Km. 211.92 Total length is 12.58 Km. Revised Alignment proposal is under verification. Dst No 6 : Detailed Alignment survey under progress. R & R works: Three villages of taluk and two villages of N.R.Pura taluk have been affected due to construction of Upper Tunga Project. 208 structures are affected. Necessary deposits are paid to SUDA for formation of lay-out and site to PAF. Also, Rs.20.475 crores of ex- gratia is provided as per the decision of R&R Committee. In this 14.33 crores distributed remaining 6.14 crore is yet to be distributed. During the year 2012-13 the grant allotted is Rs.161.00 Crores and the expenditure incurred up to end of March 2013 is Rs. 153.73 Crores. Since inception of project, cumulative expenditure to the tune of Rs. 1514.32 Crores has been incurred.

12.4.2 TUNGA LIFT IRRIGATION SCHEME

Tunga lift irrigation scheme was earlier proposed near Gajanur to Lift 1.428 TMC water from D/Stream of UTP reservoir and to feed 3 tanks namely , Barehalla and Gowdanakere tanks of Shimoga taluk and to irrigate 5162 Acres in premonsoon and 4870 acres in post monsoon period. For this project Government has accorded administrative approval vide GO: ID: 58: MMM: 05: Bangalore dated:27-02-1999 for Rs 24.12 Crores and technical sanction was accorded for same amount by Chief Engineer on 30-03-1999. The proposal of alternative alignment avoiding the forest land is surveyed and the scope of project is extended from Gowdana kere to Savalanga tank including providing link canal to feed 29 tanks in between amounting to Rs.71.33 crores is prepared. The clearance from TSC and Board of KNNL for the revised amount is obtained. After obtaining administrative approval from the Government, Technical sanction to the estimate amounting to Rs. 71.33 crores is accorded vide CER No. 367/12- 13 dated:02-11-2012. Presently the project is taken up on turnkey basis for which approval to tender is awaited. During the year 2012-13, the grant allotted is Rs. 4.00 Crores and Rs. 0.12 Crores expenditure has been incurred.

12.4.3 BASAPURA LIFT IRRIGATION SCHEME

This project envisages lifting of 1.60 Cumecs of water from River Varada near Basapura village in 2 stages to irrigate 2000 ha. of Land, pertaining to 13 villages of Hangal Taluk, Haveri District. An allocation of 0.60 TMC of water for utilisation in provided for this project by the Krishna Water Tribunal. Administrative approval has been accorded for this project vides G.O. No. ID 20/MMM/96-97 dated 9-4-96 for Rs. 936.00 Lakhs. CE, UTP Zone, Shimoga has accorded

100 technical sanction for Rs. 936.00 Lakhs on 31-6-1996. Latest estimated cost of the project is Rs. 35.15 crores. The project is transferred to KNNL during August-03. Presently, Stage I work of Electro- Mechanical Components & other head works canal works is completed. Distributory net works is completed and water letout in the canal to irrigate 890 hectares. FIC works are completed. Stage-II works entrusted on turn key basis. Work is under Progress. During the year 2012-13 the grant allotted is Rs. 6.00 crores and the expenditure incurred up to end of March 2013 is Rs. 4.11 crores. Since inception up to end of March 2013, cumulative expenditure of Rs. 22.27 crores has been incurred on the project.

12.4.4 ITAGI-SASALWAD LIS This project envisage lifting of water from River Tungabhadra near Itagi village, Taluk, Gadag Distrist, in one stage to cater the irrigation requirements of Khariff & semi dry crops to an extent of 1983 hectares belonging to Shirahatti, Mundargi and Haveri Taluk. The Government accorded Administration approval for Rs. 427.00 Lakhs on 21-09-1992 and subsequently revised administrative approval was accorded for Rs. 800 lakhs on 24-4-96. Chief Engineer, UTP Zone, Shimoga accorded technical sanction for Rs. 800 Lakhs to the Project, on 5-6- 96. An allocation of 0.55 TMC of water for utilization is provided for this project by the Krishna water Tribunal. Latest estimated cost of the project is Rs. 23.78 crores.  Electro-mechanical works like jackwell cum pump house, rising main, etc, have been entrusted to M/s. Arun Engineers on turnkey basis. This work is Completed and Commissioned.  The project comprises of 25.517 km of RBC and 10.907 km, of LBC. The LBC i.e. 10.907 km has been entrusted on tender basis and all the works are completed. Out of the total length of 25.517 km, all works of RBC works are completed.  The distributory network coming under RBC and LBC canal is entrusted to 3 agencies and completed. F.I.C. works are also completed. Power required for this project is approved by HESCOM and deposit has been made to HESCOM. The work for getting power supply from Holitagi sub-station to jack well, pump house is Completed & Commissioned. During the year 2012-13, the grant allotted is Rs. 4.97 crores and the expenditure incurred up to end of March 2013 is Rs. 0.61 crores. Since inception of the project an amount of Rs. 20.73 crores has been spent up to end of March 2013.

12.4.6 GUDDADAMALLAPURA LIFT IRRIGATION SCHEME

The scheme envisages lifting 1.00 TMC of water in two stages from Varada river near Byatanal to irrigate 13000 acres (5261 Ha) of lands in Byadagi taluk of Haveri district. The above LIS’s entrusted to M/s. Coramandel Prestcrete Pvt. Ltd, on turnkey basis. The agency has stopped the work. The work was rescinded as per the instruction of the TSC. Agency fixed for the balance work by inviting fresh tenders.

Jack well/pump house: Completed Raising main-I: Completed. Delivery chamber-I&II: completed Gravity Canal-I: Completed UG sump and pump house: Completed Raising main-II: Completed Gravity canal-II: Completed Gravity Canal-III: Excavation embankment and CNS layer work for 7.20 km completed, Out of 4.50 kms. Lining work 10.53 Km completed.

101

During the year 2012-13, the grant allotted is Rs. 40.00 crores and the expenditure incurred up to end of March 2013 is Rs. 5.91 crores. Since inception of the project an amount of Rs. 81.23 crores has been spent up to end of March 2013. It is one of the project assisted under AIBP.

12.4.6. UBRANI-AMRUTHAPURA MULTIPURPOSE LIS This scheme was a part of Upper Bhadra Project Stage-1, which was separated as per Government order No.WRDO/ 63/ «¨sÁå.vÀ./ 2000, ¢: 23-8-2003. The Main aim of this project is (a) drinking water purpose and (b) Filling of 57 Tanks of Tarikere Taluk & 89 Tanks Channagiri Taluk. This project comprises of 2 stages costing Rs. 92.40 Crores. Presently works under both stages completed & project commissioned.

During the year 2012-13 the grant allotted is Rs. 3.00 crores and the expenditure incurred up to end of March 2013 is Rs. 8.38 crores. Since inception upto end of March 2013, cumulative expenditure of Rs. 114.87 crores has been incurred for this project.

12.4.7 SANYASIKOPPA LIS Sanyasikoppa lift irrigation scheme envisages construction of anicut across Kumudavathi River near Sanyasikoppa village in Shikaripura Taluk, to irrigate 1791 hectares. The Government has accorded administrative approval Vide G.O.No.ID/ 161/MMI/2003, dated: 25-3-2006 for Rs.10.00 Crores for this Project. Technical sanction is accorded for Rs. 9.97 Crores. work is take up on turnkey basis and works are nearing completion. During the year 2012-13, the grant allotted is Rs. 1.00 crores and the expenditure incurred is Rs. 0.62 crores since inception upto end of March-2013 cumulative expenditure of Rs. 11.02 crores has been incurred.

12.4.8 DANDAVATHI RESERVOIR PROJECT Dandavathi Reservoir project in Soraba Taluk of Shimoga District envisages to provide irrigation facilities to 6933 Ha in Soraba and Shikaripura taluks of Shimoga districts by constructing reservoir across Dandavathi river. Further a provision is made to provide drinking water facilities to small hamlets, filling of MI tanks within the command area and sub soil replenishment. The Government vide GO dated 12.01.09 has administratively approved the DPR for Rs.272.00 crores. Agency for construction of Dam & Allied works is entrusted. Work to be started. During the year 2012-13, the grant allotted is Rs.16.00 crores and the expenditure incurred is Rs.0.75 crores only. Cumulative expenditure upto March 2013 since inception of project is Rs. 2.80 crores

12.4.9 KALLUVADDAHALLA NEW TANK The project is proposed for construction across Kalluvadda Halla near Shikaripura taluk. It is proposed to provide an irrigation facilities to an rea of 1950Ha in 14 villages of Shikaripura taluk. The Government vide GO dated 30.08.2006 has administratively approved the said project for Rs. 20.42 crores based on the estimate by MI department and transferred to KNNL for implementation. The Revised DPR for the Project for Rs.44.00 crores is submitted to Nigam for according approval to same. During the year 2012-13 the Grant allotted is Rs.0.10 crores and no expenditure has been incurred. Project is yet to be started.

12.4.10 TILUVALLI LIFT IRRIGATION SCHEME The Thiluvalli LIS in Hanagal taluk of Haveri District by lifting water from Varada river envisages to irrigate 2500 Acres of land during Khariff season under Hangal taluk of Haveri District and 102 rejuvenation of Thiluvalli Doddakere, Siddanahonda, Yethinahalli, Chikkatti and Hiriyara tank and canal. The Villages benefitted are Thiluvalli, Inam-Lakmapura, Yettinahalli (T) of Hangal Taluk in Haveri District. The government vide GO dated 05.01.2010 has administratively approved the revised estimated amounting to Rs. 34.00 crores and technical sanction to the estimate amounting to Rs.41.76 crores is accorded by CE vide CER No.279/10-11 dtd:19-01-2011. I stage work was entrusted on Turn key basis for Rs. 18.87 Crores. Work is under progress and survey work is in progress for taking up 2 nd stage works. During the year 2012-13 the grant allotted is Rs. 8.00 crores and expenditure incurred is Rs. 1.09 crores. Since inception of project to and of March 2013 cumulative expenditure of Rs. 1.10 crores has been incurred.

12.4.11 DAVANGERE 22 TANKS (RAJANAHALLI LIFT IRRIGATION SCHEME)

Government accorded approval to take up a lift irrigation scheme to feed 22 tanks of Davanagere, Jagalur and Harapanahalli taluks for Rs 100 Crores. Vide Govt. order No: WRD 33 LIS 06 Dated ; 05.01.07. The detailed estimate of the scheme is prepared amounting to Rs 11270 Crores and technically sanctioned. The work has been taken-up on turn key basis tender amounting to Rs 9500.00 Lakhs. Land Acquisition for Jack well No-1 is in award stage. Acquisition for Jack well No-2 is in 6(i) notification stage. The work is under progress.

The progress achieved to the end of March 2012-13 is as follows. M.S. Pipe for rising main supplied is about 47.625 km and 32.017 km is already laid. For distribution system PSC pipe of 23.915 km is supplied and 18.493 km is laid. HDPE pipe of 34.630 km is supplied and 34.630 km is laid and the work is under progress.

During 2012-13 the Karnataka Neeravari Nigam has allotted a grant of Rs 1100.00 Lakhs. Work is under progress. Expenditure incurred during 2012-13 is Rs 1753.00 Lakhs. An update expenditure of Rs 8887.00 Lakhs has been incurred to end of March 2013.

12.4.12 NIDIGE - PURLE TANKS Nidige tank is located in mid way between Shivamogga & Bhadravati, Besides Tumkur Honnavar National Highway. This tank to being feeded from Bhadra Left bank canal. This tank is having as water spread area of 18.00 Ha. (44 A-21 G). This tank has been handed over to Nigam vide G.O. No. 247 / JA.JA.©. 2006 / ¢: 24-1-2007 for improvement including boating Center. An estimate was prepared for Rs. 900 lakhs & placed before the TSC. The matter was discussed in 76th meeting held on 13-4-2007 and sub-Committee as formed. The sub-Committee inspected the spot and as per the instruction given the estimate was splet in to two parts in the I-Phase an estimate amount for Rs. 477.00 was prepared. The same estimate has been recasted for Rs. 655.00 lakhs and submitted CE’s office. Then the NH widening work was taken up by High-way department and is completed. Hence for the revised DPR reinvestigation survey estimate is also prepared for Rs. 180.00 lakhs and submitted to CE’s Office.

Purle tank is located 6 Km from Shimoga City situated between Shimoga-Holehonur Road, Solapura-Mangalore National High Way ( N.H. 13) at Purle village. This tank is being feeded from Tunga right bank Canal and Bhadra left bank canal. This tank having an water spread area of 35 Acr 21 Guntas ( 14.38 Ha.) This tank has been handed over to Nigam vide G.O. No. WRD/247 /MMB/ 2006 Dated: 24-01-2007 for improvements including Boating Centre. Recreation Centre. An estimate prepared Rs. 940.00 Lakhs and placed before the TSC. The matter was discussed in 76th Meeting held on 13.04.2007 and sub-committee was formed. The Sub-Commiittee has inspected the spot and as per their instruction taken land scope consultant and prepared estimates in two part. ( Phase-1 & Phase-11). 103

For the year 2011-12 an amount of Rs. 10.00 lakhs (nidige and Purle Tanks) has been allocated since the work is yet to be taken up no expenditure incurred till now. The Phase-1 estimate including Deepending the Tank. Formation of Bund, Silt Trap, inlet Way, Entrance Arch / Ticket Couter etc. Hence, the Phase-1 Estimate has been recasted and submitted to Executive Engineer. K.N.N.L., Upper Tunga Project Division, Shimoga. During 2012-13, a grant of Rs. 0.10 crores is allotted and no expenditure is incurred till March 2013.

12.4.13 MODERNISATION OF THE TUNGA ANICUT PROJECT Tunga Anicut is constructed across Tunga River near Gajanur village, Shimoga Taluk & District of Karnataka State in 1956 nearly about 50 years old. At the same time left Bank canal and right bank canal also constructed. The project consist of modernization of the canal for entire length by providing CC lining and renovation of damaged a canal structures like Head sluice, escapes sluice, Inlets, washing ghat, off take outlets etc. to feed the water to the tail end reaches and to save the water. There will be a reduction of wastage of water upto an extent of 6.25 TMC., there by utilization of water will be reduced to 5.25 TMC as against the present 11.50 TMC. The saving water will be utilize to Upper Bhadra Project. The length of Right Bank canal is 52.00 Km with 38 distributaries of total length 54.06 Km. The length of left bank canal is 100.00 Km with 62 distributaries of total length 142.00 Km gross command area of Right bank canal & left bank canal is 9078.00 Ha. The detailed project report and estimate has been prepared for Rs. 206.00 crores and submitted for administrative approval to 120 TSC meeting held on 18-2-2011. As per direction of the Technical sub-committee Estimate has been recasted for Rs. 309.00 crore and Administrative approved by Government is accorded vide No. WRD:23:MMB: 2012 dated: 28-06-2012. The DPR is submitted to CWC for clearance and compliance to observation raised by CWC is submitted. For the year 2012-13 a grant of Rs. 20.00 crores is allotted and the expenditure incurred to end of March-2013 for Rs. 1.03 crores only.

12.5 BHADRA PROJECT

Bhadra Project Circle is functioning at B.R.Project in Bhadravathi taluk, since from 07.11.1969. This Circle is under the control of the Chief Engineer, KNNL, Upper Tunga Project Zone, Shimoga from 13.11.1992. As per G.O. ID/2/MMH92/Bangalore dated. 12.2.1992.

Three Divisions and fifteen Sub-Divisions are working under the Jurisdiction of this Circle, i.e. Executive Engineer, No.3, Canal Division Malebennur, No.4 BRLBC Division Bhadravathi and No.5 Canal Division, Davanagere.

The following Projects are coming under the Jurisdiction of this Circle.

I. Major Irrigation Project: 1. Bhadra Reservoir Project II. Medium Irrigation Project: 1. Anjanapura and Ambligola project Modernization. 2. Gondhi Anicut Project {Bhadra Anicut} 3. Davangere 22 Tanks (Rajanahalli Lift Irrigation Scheme) 4. Development works of Historical Huchurayanakere in Shikaripura Town. 5. Hodirayanahalla Diversion scheme. 6. Supplementing water to 10 Tanks in H.Hadagali.

104

BHADRA RESERVOIR PROJECT

Bhadra Dam is constructed across near Lakkavalli (village), Tarikere (Taluk) Chickamagalur (District). This project is a Multi purpose Project provides Irrigation facility to on extent of 1,05,570 Ha. and also have power generation of 39.20M.W. Capacity. The details of canals coming under this project are as follows.

Sl. Length in Atchakat in Canal No. Kms Ha. 1. Bhadra Right Bank Canal 103 .00 17274 2. Bhadra Left Bank Canal 77.00 8300 3. Anveri Branch Canal 67.00 6319 4. Malebennur Branch Canal 48.00 23774 5. Davanagere Branch Canal 90.00 45623 6. Harihara Branch Canal 20.40 - 7. Devarabelakere Pickup Project 59.20 4280 Total: 464.60 1,05,570

Bhadra Project is allocated 61.70 TMC of water as per KWDT. The Project achieved Irrigation facility to an extent of 1,05,570 Ha. in 1989. The revised project cost of the project was 33.53 Crores and cost of Re-revised estimate cost is Rs. 170.00 Crores and is approved under letter No. 4184 dated. 14.03.2001.

The Major works under the Bhadra Reservoir project are completed. The water is allowed through the both canals, since 1965 and Irrigation facility to the total extent of 1,05,570 Ha. is already achieved. Now the modernisation works of Canal system has been taken up from 2005-06. During 2007-08 the modernisation works has been taken up under Karnataka Neeravari Nigam Limited as per the Government order.

The Grants allocated for the year 2012-13 under the Head of Account 2701 is Rs.650.00 Lakhs Expenditure incurred to the end of March 2013 is Rs 476.61 Lakhs.

The Grants allocated for the year 2012-13 under the Head of Account 2702 is Rs.150.00 Lakhs Expenditure incurred to the end of March 2013 is Rs 3.75 Lakhs.

MODERNISATION OF CANAL SYSTEM OF BHADRA RESERVOIR PROJECT :

During 2000-01 the plans and estimate for modernisation of canal system of Bhadra Reservoir Project was limited to Rs 100.00 Crores and submitted to the Govt. for administrative approval. The Govt. accorded tentative approval to Rs 100.00 Crores during 2000-01. The Govt. constituted a technical committee to inspect and give suggestions regarding the modernisation works during 2001. The committee submitted a report to the Govt. during 2003. According to the report, the estimate was prepared amounting to Rs 365.00 Crores and submitted to the Govt. to obtain administrative approval on 12.08.2003. The Govt. had given directions to take up the modernisation works under KNNL vide G.O. No. WRD 137 MMB: 2003 dated 28.02.2004.

Further the modernisation estimate was re-casted based on the schedule of rates of 2003-04 and got up to Rs 471.00 Crores and submitted to the Managing Director, KNNL on 18.02.2004. The same was placed before 57 th TSC meeting held on 14.03.2005. The TSC suggested to submit the estimate before the Board of KNNL for clearance. As decided in the 25 th meeting of the Board of 105

KNNL the estimate was submitted to the Govt. vide letter No 964 dated 22.06.2005 for obtaining the administrative approval.

During 2005-06 Government allocated a grant of Rs 10.00 Crores vide Govt. Letter No WRD:37: MMB:2005 dated 17.03.2005, Accordingly the programme of works amounting to Rs 15.48 Crores was got approved and tackled during 2006-07.

Further the secretary, WRD was inspected the Canal system of Bhadra Project and decided to constitute a technical committee for inspection of Canals and to give necessary directions to take- up the modernisation works. The technical committee headed by Sri. Chiniwal (Rtd. C.E.) inspected the canals on 19-07-2005,20-07-2005,21-07-2005 and on 02-09-2005,03-09-2005 and 04-09-2005 and given useful directions to prepare the estimates of structures like Aqueducts, Super passages, Bridges cover ducts and other structures coming in main canal and distributaries in consultation with M/S TRF in India, Bangalore. The estimates were prepared according to the technical guidance given by M/S TRF, Bangalore.

During 2006-07 the Govt. allocated a grant of Rs 45.15 Crores for the Modernisation of Bhadra Canals. The necessary programme was submitted to the Govt. and got approved and tackled the modernisation works worth of Rs 82.915 Crores. In the meeting conducted under the chairmanship of Hon’ble Chief Minister at the office Krishna on 26-12-2006. It was decided to take up and complete the Bhadra modernisation works from 1 st June to 31st December 2007 by stopping the supply of water in the canals and it was decided in the meeting held on 11-04-2007 at the office of the Engineer- in chief. WRDO. Bangalore.

The modernization estimate has been recasted to Rs 702.58 Crores based on the SR of 2006- 07 and tenders invited for the twelve packages. The contractors have participated only in 10 packages out of 12 packages invited. The two packages further divided into smaller packages. Finally the Bhadra modernisation works have taken up in 25 packages during 1 st June to 31 st December 2007. The administrative approval for the modernisation of Canal System of Bhadra Reservoir Project amounting to Rs 916.80 Crores has been obtained by the Government. The progress of Bhadra Modernisation works could not be achieved due to the unprecedented intermittent rains in the month of August to October 2007. Further, works could not be progressed beyond 5 th December 2007, as the farmers are urged to allow water in the canals for the standing crops. As such, the Government was decided to release water from 6 th December 2007. The balance works of Bhadra Modernisation works have to be restarted after the decisions of higher authorities.

The balance works of Bhadra Modernisation were tackled during 2009-10,2010-11 2011-12 and 2012-13. Some of the works in which progress was not achieved were rescinded and retendered. Totally 33 packages are under progress.

Grant allotted for Modernization of Bhadra Canal for the year 2012-13 under Karnataka Neeravari Nigam Limited is Rs 109.00 Crores. The expenditure incurred during 2012-13 is Rs 39.19 Crores. The upto date Expenditure incurred up to March 13 for Bhadra Modernisation is Rs 1031.23 Crores.

ANJANAPURA AND AMBLIGOLA PROJECT MODERNIZATION .

Grant allotted for modernization of Anjanapura and Ambligola project is Rs 800.00 Lakhs. The annual programme of works including spill over and fresh works amounting to Rs 3647.76 Lakhs has been approved by nigam. The details of works are as under;

106

1) Modernization of Anjanapura canal-Rs 1206.43 Lakhs. 2) Improvements of tanks coming under Atchakat of Anjanapura project-Rs 855.41 Lakhs. 3) Modernization of Ambligola canal-Rs 980.92 Lakhs 4) Improvements of tanks coming under Atchakat of Ambligola project-Rs 605.00 Lakhs. 5) Cummulative Expenditure incurred during 2012-13 is Rs.1199.00 Lakhs.

The brief notes of the project is as under;

Ambligola Reservoir Project

Ambligola Reservoir project has been constructed at Ambligola across Kumudvathi River during 1954-65 at the Junction of Sallur-Halla joining Kumudvathi river. The irrigation potential created under this project was 7300 Acres for Khariff season only. Further left Bank canal of this project has been extended in order to create an additional potential of 7912 Acres for khariff season. The length of right bank canal is 6 KM and the length of Left Bank canal is 47.00 KM.

Government has accorded administrative approval on 26.06.1998 for Rs.178.00 Lakhs for rising of Ambligola reservoir embankment and waste weir to 1M. Height. According to the reservoir height and waste weir height has been raised to 1 M. height and created 5700 Acres for Rabi semi dry crops. At present considering 50% dependability 2538 Mcft of water is being utilising for Irrigation. This work has been technically sanctioned and work is completed. This project is in maintenance stage.

During 2012-13 no Grant has been allotted from nigam under Head of Account 2701. The grant allotted during 2012-13 in budget is Rs.17.27 Lakhs under 2701 and expenditure incurred during the year 2012-13 is Rs. 17.27 Lakhs.

MODERNIZATION OF AMBLIGOLA CANAL SYSTEM

Before nigam the update expenditure incurred on modernization from 2005-06 to March 2011 is Rs 2049.15 Lakhs.

Improvements of 13 Tanks under the Atchakat of Ambligola Project : Before nigam the update expenditure incurred on development of tanks from 2006-07 to March 2011 is Rs 128.81 Lakhs.

ANJANAPURA RESERVOIR PROJECT

Anjanapura Reservoir project in Shikaripura taluk, Shimoga District. The area irrigated is 6736 Ha. The original estimated cost of the project was Rs. 272.00 Lakhs. The right bank canal runs for a length of 45.00 Km. and has an irrigation potential of 5919 Ha. The Left bank canal runs for a length of 15.00 Km. and has an irrigation potential of 817 Ha. This project is in maintenance stage. The errection of God Bole gates on spill way of Anjanapura Project through NABARD grant has been taken up and completed. The expenditure incurred on this is Rs.218.00 Lakhs. During 2012-13 no Grant has been allotted from nigam under Head of Account 2701. The grant allotted during 2012-13 in budget is Rs.41.24 Lakhs under 2701 and expenditure incurred during the year 2012-13 is Rs . 41.24 Lakhs.

MODERNIZATION OF ANJANAPURA CANAL SYSTEM: Before nigam the update expenditure incurred on modernization from 2005-06 to March 2011 is Rs 2461.02 Lakhs.

107

Improvements of 20 Tanks under the Atchakat of Anjanapura Project : Before nigam the update expenditure incurred on development of tanks from 2005-06 to March 2011 is Rs 635.34 Lakhs.

GONDI ANICUT (BHADRA)

Gondi Anicut has been constructed during 1923. The maintenance of this Project has been handed over to this circle during 1975. The irrigation potential created under this project is 4466 Ha. The improvements to Gondi canal amounting to Rs.240.00 Lakhs have been taken up and completed under plan head of account. Besides this, canal improvements works have been taken up under National Water Management Programme and completed. This project is in maintenance stage.

2007-08 on words Modernization works of Gondi Canal System has been entrusted to Karnataka Neeravari Nigam Niyamitha by the Govt.

During 2012-13 no Grant has been allotted from nigam under Head of Account 2701. The grant allotted during 2012-13 in budget is Rs.1800.00 Lakhs under 4701 and cumulative expenditure incurred during the year 2012-13 is Rs. 29.00 Lakhs.

MODERNISATION OF CANAL SYSTEM :

Before nigam the update expenditure incurred from 2005-06 to March 2007 is Rs 378.02 Lakhs.Grant allotted for modernization of Gondhi canals is Rs 1335.00 Lakhs. The Administrative approval project report amounting to Rs 82.00 Crores has been obtained vide Govt Order No:WRD:24:MMB:2012 Dt 18.08.2012. Action is being taken to get clearance from CWC. The expenditure incurred on conducting survey works in order to prepare project report is Rs 30.28 Lakhs. The project is proposed to taken up under ADB assistance by the Government. Action is being taken to get ADB assistance for modernization of this project.

TUNGA ANICUT PROJECT

Tunga Anicut is constructed across Tunga river at Sakrebylu, Village. Irrigation facility to an extent of 21,500 Acres (8.704 Ha) is developed under this project. The improvements works of Canals of this Project were taken up in the year 1993 under National water Management Programme. This included the Canal repairs, strengthening of structures and lining at damaged portions, fixing of measuring devices was also taken up under this Programme. The project is under maintenance.

2007-08 on words Modernization of Canal system of Tunga Anicut project is proposed to take up under Karnataka Neeravari Nigam Ltd. During 2012-13 no Grant has been allotted from nigam under Head of Account 2701 and 2702.

The grant allotted during 2012-13 in budget is Rs.2500.00 Lakhs under 4701 and cumulative expenditure incurred during the year 2012-13 is Rs. 165.00 Lakhs.

MODERNISATION OF CANAL SYSTEM OF TUNGA ANICUT Before nigam the update expenditure incurred from 2005-06 to March 2007 is Rs 443.65 Lakhs. The Modernization of Tunga Anicut project canal system has been handed over to Upper

108

Tunga Project Circle, Shimoga during 2009-10 as per the Instructions of the Chief Engineer, KNNL, Upper Tunga Project Zone, Shimoga.

DEVELOPMENTAL WORKS OF HISTORICAL HUCHARAYANAKERE IN SHIKARIPURA TOWN.

During 2012-13 the Karnataka Neeravari Nigam has allotted a grant of Rs 300.00 Lakhs for this work. The following works are taken up for execution.

1. Construction of cover duct to feeder canal of Huchurayanakere (Irrigation Project passing through Shikaripura –Work is completed.

2. Widening of Waste Weir Bridge of Hucharayana kere in Shikaripura Taluk- Work is completed.

3. Providing composite compound wall from Hucharayana kere bund to Yatri Nivas Campus and development of Yatri Nivas (under beautification of Huchurayanakere) - Work is completed.

4. Providing essential works for beautification like chain link fencing, Hand railing, Electrification, Gardening and paving over bund etc to historical Hucharayanakere (Irrigation) at Shikaripura town in Shimoga district- Work is completed.

5. Construction of cover duct to feeder canal of Huchurayanakere (Irrigation Project). Passing through Shikaripura Town from Ch: 18.995 to 19.390 Km- Work is completed.

6. Development work of Pushakarni for Hucharayana kere in Shikaripura Taluk- Work is completed. 7. Improvements to waste weir halla of Huchurayanakere tank (Katte D/s Balagere tank) Work is under progress.

Expenditure incurred during 2012-13 is Rs 410.60 Lakhs. An update expenditure of Rs.1836.05 Lakhs has been incurred to end of March 2013.

HODIRAYANAHALLA DIVERSION SCHEME

Jambadahalla Reservoir is located near Duglapura village, Tarikere Taluk of Chickamagalur district. This project was contemplated to provide irrigation to 2428 Ha. But due to less flow only 1133 Ha. Land under right bank is being irrigated. Remaining 1295 Ha a tank has been planned to irrigate by diverting supplement water from Hodirayanahalla an adjacent valley to Jambadahalla. In addition to this 243 Ha. Land will also be benefited by this scheme. The above said Hodirayanahalla diversion Scheme has been got administrative approval by the Government dated: 10.08.1987 for Rs.248.00 Lakhs. About 12.98 Ha land comes under the jurisdiction of forestland & Clearance has been obtained by Central Forest & Environment Ministry.

Survey and investigation of Hodirayanahalla diversion scheme has been conducted on tender basis through private consultancy services as per the administrative approval obtained from the government amounting to Rs 35.00 Lakhs. After detailed survey and investigation of Hodirayanahalla diversion scheme project estimate amounting Rs Lakhs has been placed before 94 th

109

T.A.C meeting held on 14.12.2009 for approval duly complying the observations of 90 th T.AC meeting. Further T.A.C has cleared the project with certain observation to comply.

Further the project proposal amounting to Rs 2537.00 is submitted to Government duly complying the observations given in 94 th T.A.C meeting. The government has accorded Administrative approval vide Govt order No WRD 47 MMB 2010 Dated 04.03.2011 with direction to take up the works through Karnataka Neeravari Nigam.

The estimate amounting to Rs 33.83 Crores has been sanctioned vide central office CER No 694/12-13 Dt 19.01.2013. TSC has raised certain observation on the Draft tender schedules of the work. Action is being taken to comply the observations of TSC.

During 2012-13 Rs. 200.00 Lakhs grant is allocated under the Head of account 4701. An expenditure of Rs 1.47 Lakhs has been incurred during 2012-13 towards survey works. The upto date expenditure incurred on this project for preliminary survey and investigation including payment made to Forest Department for release of forest land till the end of March 2013 is Rs 154.37 Lakhs. Out of which the expenditure incurred from Nigam is Rs 1.47 Lakhs.

110

12.6. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, VARAHI PROJECT ZONE, SIDDAPUR 12.6.1 VARAHI IRRIGATION PROJECT

BREIF DESCRIPTION:

The Varahi Irrigation Project envisages Construction of 1Diversion Weir across at Horriabbe near Siddapura Village, to create irrigation potential to an extent of 15,702 Ha. (38,800 acres) in Kundapura and Udupi taluks of Udupi District, by utilizing the daily release of 1100 Cusecs of tail race water from Varahi underground hydro electric project situated in the upstream of the river at Hosangadi.

The Varahi Irrigation Project is administratively approved originally by the Government of Karnataka vide G.O.No. PWD 71 GIP 76, dated 27-3-1979 for Rs. 943.00 lakhs. Further revised cost amounts to `.56953.00 Lakshs

VARAHI DIVERSION WEIR:

A concrete diversion weir of 145 meters. Length and 17.50 meters height above the deepest foundation level is proposed to be constructed at horriabbe site near Siddapura Village, Udupi District.

Due to Construction of Diversion Weir total 121.58 Ha. of land will submerge and two villages will be submerged partially.

CANALS:

Varahi Right Bank Canal takes off from the Diversion weir and runs to a length of 42.73 K.M. A branch canal takes off from Right Bank Canal at 19th K.M. and crosses the river Varahi through an aqueduct and Left Bank Canal starts from this aqueduct and runs for a length of 44.35K.M. The Lift Canal start from Left Bank Canal at 7th K.M. of Left Bank and runs for a length of 33 K.M.

111

The proposed atchkat to be covered from this Project is as detailed below: Atchkat covered is in Udupi District. Sl. Length, Irrigable Canal details No Km area, Ha 1 Varahi Right Bank Canal 42.73 1992 Varahi left bank canal 2. 44.35 10987 (From off-take at 20 th Km of Right Bank Canal) 3 Lift canal (From off-take at 7 th Km of Left Bank Canal) 33.00 2723 Total 15702 Villages benefited: 1. Kundapura Taluk 33 villages 8324 2. Udupi Taluk 35 villages 7378 Total 68 villages 15702

 Right Bank Canal (42.73 Km.) : River aqueduct is completed. Survey works completed for full length Varahi Right bank Canal from 0.30km to 1.00 km, 9.00 km to 10.00 km and 12.00 km to 13.00 km are completed. Ch 1.00 km to 9.00km, 10.00km to 12.00km and from 13.00 km to 14.00 Km. is under Progress. The Balance works of 3,4,9,11 km and works from km 14.00 to 18.725 km are taken up and work is in progress

 Left Bank Canal (44.35Km.) : Upto 21 km works Completed. Ch 23.00 kkm to 24.00 km, 28.00km to 30.00 km are completed. Ch 21.00 km to 22.00km, 24.00km to 28.00 km works are in progress.

 Lift irrigation canal (33 Km .) : Works are completed. Power connection received and commissioned on trial basis. This project is received central assistance under AIBP since 2007-08.  PROGRESS DURING 2012-13: The total estimated cost of the project is Rs. 569.53 Crores. Cumulative expenditure incurred on the project up to end of March 2013 is Rs. 465.83 Crores. During 2012-13 against the programme of Rs. 87.00 crores, expenditure of Rs. 65.91 crores has been incurred up to end of March 2013.

112

TUNNEL TUNNEL

SALT WATER EXCLUSION DAM VARAHI RIVER AQUEDUCT

VARAHI RIGHT BANK 10 th KM

113

12.7 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION PROJECTS ZONE, GULBARGA 12.7.1 BENNITHORA PROJECT

Bennithora project is a major irrigation project, which comprises of construction of dam across River Bennithora near Heroor village, Chittapurtaluk, Gulbarga District. There are two canals covering an Irrigable area of 20,234 Ha in Gulbarga District. The utilisation for the project is 5.75 TMC.

Dam: Work is completed and water is being stored in reservoir since Dec-2001.

 Right Bank Canal (82 km): Works are completed. Tenders for the strengthening of embankment in vulnerable reaches & concrete lining (selected reaches) has been invited for Rs.11.63 crores. Tender Agreement No.43 Dated:12-03-2013 Entrustment amount Rs.12.35 crores at 1.22% below, work is under progress. Total atchkat is 13435 Ha.

 Left Bank Canal (60 km): All Distributories on LBC are completed. Tenders for the strengthening of embankment in vulnerable reaches & concrete lining (selected reaches) has been invited for Rs.7.95 crores. Tender Agreement No.44 Dated:12-03-2013. Entrustment Amount Rs.8.68 crores at 2.94% above, work is under progress. Total atchkat is 6799 Ha.

The revised estimate cost of this project is Rs.443.00 Crores. Cumulative expenditure upto end of March-2013 is Rs.391.10 Crores. A dry potential of 20234 Ha has been created to end of 3/2013. The wet potential of 18778.70 Ha is created up to end of March 2013, and balance 1455 Ha will be created during 2013-14.

The details of target and achievement of the project for 2010-11 to 2012-13 are as follows:

Financial (Rs. in Crores) Sl. No. Year Target Achievement 1 2010-11 12.25 24.01 2 2011-12 23.50 10.59 3 2012-13 24.50 12.44

114

12.7.2 BHIMA LIFT IRRIGATION SCHEME

Bhima Lift Irrigation envisages construction of earthen dam with central concrete spillway with crest gates to discharge 9.00 lakh cusecs of water. The dam site is proposed near Sonna (K) village of Afzalpur Taluk in Gulbarga District and providing two lift irrigation points to draw water from the Reservoir, for creation of 24,292 hectares of irrigation Potential, by utilising 6 TMC of Water.

The Project is administratively approved for Rs. 94.17 Crores by the Government vide Govt. Order No. ID 39 MMM 92, dated 18-4-1992, and technically sanctioned for Rs.107.70 Crores by the Chief Engineer, WRD, I.P.Zone, Gulbarga vide CER No. 5/93-94 dated13-01-1994. The Revised Estimate costing Rs.588.37 Crores is approved by Government of Karnataka. This project is under Karnataka Neeravari Nigam Ltd., since 1999.

 Barrage Length- 2.250 km Height - 18.40 m Gross Storage – 3.166 TMC Live Storage - 2.41 TMC Allocation &Utilisation – 6.00 TMC

 Lifting Systems Two foreshore lifts at Balundgi & Allagi (B) Length of the Balundgi lift canal – 63.762 km. Length of the Allagi lift canal – 35.787 km

STAGE OF THE PROJECT AS ON MARCH-2013:

 Dam & allied works: Construction of earthen embankments on left and right flanks are completed and construction of barrage is also completed. Entire body wall portion is completed. Concreting to piers is completed. Pre-casting and launching of girders for Ballundagi Lift including Bankalaga R.C. & Bankalaga Bridge is completed. Water impounding has been started. Mini-Hydel Scheme work is also completed, generation of electrical energy is also started duirng Aug-2010. The barrage and Balundagi Lift was inaugurated and dedicated to the nation on 19-02-2013.

115

 Gate works: Gate works are completed during Aug-2010.  Balundagi Lift: Construction of intake channel, jackwell, pump house, raising main with PSC pipes and delivery chamber are completed.  Balundgi Canal: Construction of Balundagi main canal from 0 to 63.76 is completed except few structures and small reach of lining. Water is allowed in the canal upto 40 km on trial basis.  Allagi Lift: Construction of intake channel (except lining), jackwell, pump house, raising main with PSC pipes and delivery chamber are completed.  Allagi Canal : Construction of Allagi main canal work from Km. 0 to 5 & 5 to 10 Km. is under progress, and from 10 to 20 Km & 20 to 35.787 Km packages are nearing completion.  Rehabilitation and Resettlement: Villages affected due to submergence – 10 Nos. No of centres to be formed – 9 No Population affected – 8801 Families affected – 1658

Government vide GO dated 18.5.05 have constituted District Level Rehabilitation Advisory Committee. R&R Package is approved by the govt. The site has been identified for construct rehabilitation centre and even land acquisition has been proposed and 4(1) notification has been issued. Construction of Balundgi rehabilitation is completed and handed over to Gram Panchayat. Bankalaga centre is also completed and inaugurated on 19-02-2013 and formal Hakku Patra are also issued to the rehabilitanats. Tarapur, Duddangi, Mangalore, Hiriyala & Badgihal are nearing completion. The Rehabilitation Centers for Allagi B works under 4 packages are approved and agreement to be concluded. Tawarkhed R.C. is yet to be implemented. During the year 2012-13, budget allocation made is Rs.105.00 crores and expenditure incurred upto March 2013 is Rs.79.64 crores. The details of target and achievement of the project for 2010-11 to 2012-13 are as follows: -

Sl. Financial (Rs. in Crores) Physical (In hectares) Year No. Target Achievement Target Achievement 1. 2010-11 100.00 40.86 1000 581.30 2. 2011-12 225.90 56.06 14694 4307 3 2012-13 109.54 79.25 5000 1120.27

116

12.7.3 GANDORINALA PROJECT

Gandorinala project is a medium irrigation project in Gulbarga District. This project envisages construction of dam near Belkota village in Gulbarga taluk, across River Gandorinala, a tributary to River Bennithora, which in turn joins River Bhima of Krishna Basin. The utilisation under this project is 1.97 TMC. The area covered for irrigation under this project is 8094 Hectares.

The project is administratively approved vide Government Order No. ID 110 MTZ 85, Bangalore dated 23.05.1992 for Rs. 66.00 crores. The revised estimate of the project is Rs.240.00 Crores and expenditure upto March 2013 is Rs. 281.23 Crores. The dry irrigation potential of 7943 Ha has been created upto March 2013.

 Dam & allied works: The works were carried out by KSCC and the same are already completed. The work of providing & erection of radial crest gates is completed.

 Canal works:  RBC: Total length of LBC is 7 km and works are completed Potential of 566Ha is created.  LBC: Total length of LBC is 89.32 km and works are completed.  Distributories: Under RBC 3 distributories works are completed. Under LBC 40 distributories works are completed.  FIC: FIC works of 566 Ha under RBC and FIC works of 7291 Ha under LBC are completed. The balance potential of 86 Ha will be created during 2013-14.

The details of target and achievement of the project for 2010-11 to 2012-13 are as follows Financial Physical (in Ha) Sl. Year (Rs. in Crores) Wet No. Target Achieved Target Achieved 1) 2010-11 17.39 10.96 1857.85 1352.47 2) 2011-12 6.50 13.59 505.38 248.89 3 2012-13 10.00 11.87 256.49 170.32

117

12.7.4 LOWER MULLAMARI PROJECT

Lower Mullamari Project envisages construction of a dam across the River Mullamari a tributary to River Bhima in Krishna basin. The project is located near village in ChincholiTaluk of Gulbarga District. The utilisation under this project is 2.61 TMC and it is planned to provide irrigation facilities to 9713 Ha. of land in Chincholitaluk. The project has been originally estimated for Rs. 45.00 crores at 1990-91 schedule of rates. The latest estimated cost of the project is Rs. 220.00 Crores and expenditure to end of March 2013 is Rs. 213.74 crores.

A) Earthen Dam: Completed including erection of spillway gates. Water is being stored in reservoir since August 2001.

B) Right Bank Canal (80 km): Works are completed.

C) Distributaries (66 Nos.): 65 are completed and water is let-out in distributaries. Total Atchkat : 9713 Ha. Wet potential created : 9560.72 Ha. Balance to be created : 152.28 Ha.

D) R&R : Out of 7 Nos. of rehabilitation centres, 6 nos. are completed. Balance works of Gadilingadahalli Rehabilitation Centre No.3 are nearing completion.

E) Strengthening works of RBC : Strengthening works in selected reaches from Km. 0 to 40 are completed. Works from Km.40 to 80 km in selected reaches are under progress & nearing completion. Estimates for strengthening works from Km.40-80 in balance reaches for an estimated amount of Rs.17.00 crores is submitted to MD, KNNL, Bangalore.

Total irrigation potential of the project is 9713 Ha, Out of which 9400 Ha created upto end of March 2013. The balance potential of 313 Ha will be created during 2013-14.

The details of target and achievement during 2010-11 to 2012-13 is as under: Sl. Financial (Rs.in Crores) Year No. Target Achievement 1) 2010-11 20.00 10.41

2) 2011 -12 12.50 7.36 3) 2012-13 18.50 12.44

118

12.7.5 AMARJA PROJECT

Amarja irrigation project envisages construction of a dam across the River Amarja, a tributary to River Bhima in Krishna Basin, near Sangolgi village in Aland Taluk of Gulbarga District with canals on both banks to provide irrigation facilities to an extent of 8903 Ha. The utilisation proposed under this project is 1.92 TMC.

A) DAM: 960 m long and 31.85 m high earthen dam with a storage capacity of 43.87 Mcum will submerge 641 ha of land, affecting 3 villages and a population of 4,500. Dam works are completed during 1999 and water is being stored since 2001.

B) CANALS: The Left Bank Canal is 54.78 Km long and the Right Bank Canal is 42.428 Km long which will irrigate 4,856 Ha. and 4,047 Ha. of land, respectively. Total number of distributaries under RBC are 29 Nos. and DPO’s 20 Nos. and under LBC are 33 Nos. & 19 Nos. are respectively.

The subject rectification works of Amarja project was placed before he 25 th Board meeting of KNNL held on 07.06.2005. After detailed Deliberation the Board authorized for closure of works for previous contracts on “ As is where basis” so that rectification works can be taken up without further delay (vide ltr no 993 dtd:23.06.2005). Under this proceedings, the rectification works were proposed for Rs.100.00 crores. The work is transferred to KNNL during April 2005 vide GO No. WRD 29 TMZ 04 dated 18.04.2005.

Rectification of canal works was taken in five packages for LBC & RBC ,the work of 5 packages are under progress, the project is proposed to completed by 2012-13.

The details of the works are as follows. A) Right Bank Canal Works: 1) Km. 0.00 to 7.00: Works of main canal and distributaries are completed. The CD works and FIC works are in progress. 2) km. 7.00 to 20.00 : Works of main canal and distributaries are completed. FIC works are under progress. 3) km. 20.00 to 42.48: Works of main canal and distributaries are completed. FIC works are under progress.

B) Left Bank Canal works: 1) km. 0.00 to 30.00: Works of main canal and distributaries are completed. FIC and DPO works are under progress. Dry irrigation potential of 2020 Ha is created in this reach and wet potential of 1085.37 Ha is created.

119

2) km. 30.00 to 54.784: Earthwork excavation from 30.00 to 52.00 is completed and lining from km30.00 to km.37.00 is completed. The balance works of main canal, distributaries and FICs from Km 30.00 to 54.784 of LBC are under progress.

The details of target and achievements of the project for 2010-11 to 2012-13 are as follows:

Sl. Financial (Rs. in Crores) Physical (in hectares) Year No. Target Achievement Target Achievement 1) 20 10 -11 23.00 20.15 Dry - 1000 4567 Wet - 3000 1050 2) 2011 -12 30.00 13.10 Dry -1000 0 Wet -4467 2231 3) 2012 -13 39.50 26.20 Dry -1136 292.26 Wet -2736 978.50

The balance dry potential 2544 Ha will be created during 2013-14.

120

12.8 Upper Bhadra Project

Chapter-I

Vision,Target and purpose of Upper Bhadra Project

Chitradurga and Tumkur districts coming under middle part of Karnataka have been declared as drought prone districts. In spite of vast useful lands the ryots in this region are suffering due to scanty rainfall and non-availability of Irrigation facilities. The ryots under this region have represented the Government to provide irrigation facility by diverting the excess water from the rivers Tunga and Bhadra flowing in the neighboring districts of Chickamagalur and Shimoga. Considering the long standing plea of the ryoths the Government accepted the proposal for taking up of Upper Bhadra Project and had accorded Administrative Approval vide GO No./WRD/63/VIBYAE/2000 dated 23-08-2003 for Rs. 2813 crores. In view of the representations received from environmentalists and to look in to the submerge, the Government constituted a committee under the ChairmanShip of Sri.K.C.Reddy to study the pros and cons and availability of water and submit the report.

The committee headed by Sri.K.C.Reddy studied in detail regarding availability of water, Technical aspects of the project, storage and flow of water and the effects on environment and suggested numerous changes to the original report and submitted the report in July 2006 with their recommendations.

The main features of the report are as below.

1. Lifting of 15 TMC of water from Tunga river and delivery to Bhadra reservoir. 2. Lifting of 21.50 TMC of water from Bhadra reservoir and delivering it to proposed delivery chamber near Ajjampura through a canal system. 3. Construction of Tunnel near Ajjampura and letting out water in Chitradurga branch canal for irrigating semi-dry crops during Khariff and filling 156 MI tanks in draught prone areas of Chickamagalur, Chitradurga, Kolar and Tumkur districts there by increasing the underground water table in the region and creating basic facility of drinking water in the reason.

The Government accepted the report of Sri.K.C.Reddy and in view of implementing the project quickly, entrusted the implementation of project to KNNL during November- 2006. As per the recommendation of Sri.K.C.Reddy an estimate amounting to Rs. 5985.00 crores was proposed during 2008 and In-Principle approval was obtained vide Govt. letter No.WRD/52/VIBYAE/2004 (Part-I) dated 15-9-2008. The estimate has provision of Rs. 3388.00 crores for irrigation works and Rs. 2597.00 crores for drinking water supply needs.

The report of proposed project is unique and by implementation of this project there is no submerge/Rehabitation and involves minimum damage to the environment.

In accordance with the directions of the Government, the project is proposed to be completed by obtaining assistance from ADB and the process for the same is under progress from KNNL. Its is programmed to complete the project by 2020.

121

Project Purpose: The project envisages irrigating 107265 Ha in Chickamaglur and Chitradurga districts, and filing up of 156 tanks in Chickamaglur, Chitradurga, Tumkur and Kolar districts and thereby increasing the underground water which helps for using it for drinking water in the region. It helps in irrigating crops during khariff and helps in solving the problem of drinking water. a) Water allocation

21.50 TMC of water has been allocated under Scheme-A for Upper Bhadra Project. b) Details of Project

Under this scheme it is proposed to provide irrigation facility for 2 taluks to an extent of 2276 Ha in Chickamaglur district and 4 taluks to an extent of 104989 Ha in Chitradurga districts where by a total extent of 1,07,265 Ha. This requires 13.88 TMC of water. Filling up of 4 tanks in Chickamaglur and 33 tanks in Chitradurga district and increase the underground water in the region and providing facility for drinking water. This requires 2.02 TMC of water. An allocation of 1.86 TMC of water has been made for Jaglur branch canal from Pollavaram Project as available for State Government. Increasing the ground water table by filling 100 tanks in Tumkur district and 19 tanks in Kolar district and thereby to provide drinking water facility. This requires 5.60 TMC of water.

Implementation of Project

In view of implementing the project speedily three critical works coming in the intial reaches of Upper Bhadra Project are entrusted on EPC tender basis to three agencies. Accordingly, the agencies are required to complete the construction in 3 years and maintain for 5 years.

Name of work Agency Tender Amount Package-I Lifting of 15 TMC of water in M/s SEW-JYOTI (JV) Rs. 324 Crores two stages for a lift of Hyderabad approximately 80m and delivering to Bhadra reservoir through 10KM canal. Package-II Lifting of 21.50 TMC of M/s RNSIL (JV) Hubli Rs. 1032 Crores water in two stages for lift of approximately 88m and delivering the water to proposed delivery chamber near Ajjampura through 40.5 Km canal. Package-III Construction of 6.90 Km M/s SNC Power Rs. 223.96 Crores Tunnel near Ajjampura and Corporation Limited, delivering the water to Bangalore Chitradurga branch canal. This includes 0.33 Km approach and 2.77 Km length Exite canal

122

Progress of Works

Package-I

The work of raft foundation and raft slab is completed. Laying of 90m length of rising main is completed for Pump House-I. Placing of 5 Nos Draft tube work is under progress, after dewatering.

Laying of bed concrete lining for intake canal from on 1428 to 1503 for 117m is completed. Pier work for super-passage at Ch: 1513 is completed and abutment and wing wall work is under progress. The designs of 15 C.Ds is approved.

Approval is obtained for the power required of 35 MVA for each Pump Houses at Kanbur and Kasbur. The Electro-Mechanical components essential for Pump House-I and II viz: 10 Pumps, 10 Draft tubes, 10 Spiral casing, 10 impellers and 10 shafts motors with accessories. 1 No EOT crane have been supplied to the work spot. The proposal of Extension of time is approved upto 31.3.2015 by Managing Director, KNNL vide letter dated 25-3-2013.

The total expenditure incurred upto 31-3-2013 is Rs. 85.21 Crores.

Package-II

The concreting work of Pump House-I is under progress and concreting work is completed upto crane beem level. Excavation of canal is completed upto 8.26 Km and canal lining work for 3.10 Km length is completed and canal lining from Km 6.4 to 7.4 Km is under progress. Excavation for a total length is taken up. The work of Jambadahalla aqueduct is under progress so far present laying of 500 piles is completed. Laying of balance 28 piles is to be takenup. Raising of piers is under progress and so far seven piers have been raised. Six piers are under different stage of progress. Laying of concrete for one trough is completed. Till date, the designs of eight super passages, eight CTC, Three box culverts, and one aqueduct are approved. Balance designs are under scrutiny. Seven cross drainage works are completed and balance are under progress. The work of intake structure required for lifting of water from Bhadra reservoir will be taken up shortly.

The foundation work for transformers is completed and 3 No 30/40 MVA transformers are erected. 10 motors, 4 LCI panels, 8 SFC Transformers, 6 Motor transformers 10 Draft Tube 1 EOT crane 10 spiral casing, 6 pump shaft and Impeller with 14 circuit breakers are supplied to site.

The proposal of Extension of time (EOT) is approved by Managing Director, KNNL, Bangalore vide letter dated 9-1-2013 upto 31-3-2015.

The total expenditure incurred upto March-2013 is 368.20 crores. The amount of pending bill is Rs. 86.99 crores.

Package-III

The Government has accepted the report of the committee constituted under the chairmanship of Sri. D.N.Desai for the problems arising out of the construction of tunnel vide Government order dated: 13-6-2012. Action has been taken to taken up for the construction of tunnel. The Land Acquisition proposals have been submitted on 20-11-2012 for 151 acres 14 guntas. The DPR is prepared and action to obtain approval is under process.

123

Replies to the points raised by TSC in its meeting dated 25-8-2012 held on 140 th on DPR have been submitted to Managing Director, KNNL. The same is also deliberated in the 144 th TSC meeting held on 24-01-2013. The replies to deliberations are to be submitted. The replies to the above TSC for filling up of additional tanks is submitted.

Approval is obtained for the revised proposal for an the estimated cost of Rs.75 crore for irrigating 5471Ha, prepared in accordance with the direction of TSC. Agency has been fixed for preparation of Detailed Project Report. The work is taken up. As per Tender agreement Rs.11.19 crore Mobilisation advance is released for package-3.

Buildings

1) The construction of buildings zonal office complex has been entrusted to Sri. Krishna constructions Bangalore at 1.8% above the Tendered amount of Rs. 3.93 crores. The work is nearing completion. The payment made upto March 2013 is Rs. 384.15 lakhs and the pending bill amount is Rs. 104.00 lakhs.

The works of construction of residential quarters at Chitradurga are taken up as below.

a) The construction of Chief Engineer, Superintending Engineer, Executive Engineer and Assistant Executive Engineer residences (Package-I) is entrusted to Sri.S.Eswarappa at tender premium 6.39% above the tender amount of Rs. 183.34 lakhs b) The constraction of Assistant Executive Engineer and Junior Engineers quarters (Package- II) are entrusted to S.Eswarappa at tender premium of 8.19% above the tender amount of Rs. 131.876 lakhs. c) Establishment and ‘D’ group quarters (Package-III) is entrasked to Sri. Eswarappa at a tender premium of 8.56% above the tendered amount of Rs.144.765 lakhs.

The construction of above residential quarters is under progress and upto March-2013 the expenditure incurred is Rs. 245.25 lakhs and the pending bill is Rs. 38.38 lakhs.

2) Under Hosadurga division the residential quarters are entrusted to Sri. S.Eswarappa at a tender premium of 2.6% above the tender amount Rs.1.52 crores The works are completed and the quarters are under use. The expenditure incurred till date is 123.22 lakhs.

3) Under Challakere division the following works are taken up.

a) Office complex and Technical staff residential quarters construction work (Package-I) is entrusted to Sri.S.Eswarappa at a premium of 5.46% above the tendered amount of Rs. 149.25 lakhs. b) Assistant Executive Engineers, Establishment ‘D’ group residential quarters (Package-II) is entrusted to Sri.S.Eswarappa at a premium of 6.01% above the tendered amount of Rs. 103.12 crores.

The roof of the residential quarters is completed and at present finishing work is under progress and upto March-2013 an expenditure of Rs. 197.30 lakhs is incurred.

4) Action has been initiated for construction of sub-division office and residential quarters at Muttinakoppa in N.R.Pura taluka and are under progress. 124

a) Office building and construction of residential quarters for Technical Staff and ‘D’ group (Package-I) is entrusted to Sri. Dinesh at a tender premium 2.79% above. Expenditure so for is Rs. 34 lakhs. b) The construction of Assistant Engineer Junior Engineer and establishment staff (Package-II) is entrusted to Sri. Dinesh at a tender premium 2.79% over the tender amount of Rs. 132.68 lakhs. The expenditure incurred so for is 27.00 lakhs.

Chitradurga Branch Canal

Detailed survey work has been taken up for CBC canal from Km 0.00 to 30.00 and the alignment from Km 6.436 to 15.639 is prepared and is submitted to central office vide circle office letter dated 15-2-2013. The proposal is under scrutiny in central office.

Land Acquisition

An extent of 106A-26G of private lands is required for Package-I work and out of this for an extent of 93A-68G 4(1) notification and 87A-34G 6(1) notification is published.

An extent of 1656A-03G of private land is required for Package-II and out of this 1368A- 03G is notified under 4(1) and 774A-01G is notified under 6(1).

4(1) notification is published for the total extent of 151A-14G required for Package-III.

Revenue Secretary to Government of Karnataka has revised the land rates for private land coming under Package-I, II and III and has refixed the rates as below.

Dry land 3.50 lakhs Wet land 5.50 lakhs Garden 12.00 lakhs

As per the request of land acquisition officer an amount of Rs. 2.71 crores is deposited under Package-I and Rs. 26.98 crores under package-II. Thus an amount of Rs.28.89 crores in total is deposited. An amount of Rs. 8.89 crores has been disbursed so far as compensation.

Acquisition of Forest Land

The proposal for acquisition of forest lands required for Package-I, II and Chitradurga canals is submitted to forest department on 15-12-2009 and 13-12-2010. An extent 364.50Ha of revenue land is identified in Rekalegere Hobli as against the extent of forest land to be diverted for UBP. The same is also recommended for transfer by Deputy Commissioner, Chitradurga vide letter dated 18-02-2011.

In the meeting held under the Chairmanship of Chief Minister along with officials of KNNL and forest officials it was suggested that the present land identify under Rekalegere Kaval is forest land and hence, informed to identified different land and accordingly alternate land coming in Varavukaval was identified and a proposal was submitted by Deputy Commissioner, Chitradurga

125 vide letter dated 17-1-2012 to Revenue Secretary Bangalore. In the meeting held on 23-2-2012 under the chairmanship of Hon’ble Minister of water resources department it was resolved to approve the land identified by Deputy Commissioner, Chitradurga. In this regard the Government in the letter dated 26-2-2013 has ordered to transfer the proposed land identified by Deputy Commssioner to Forest Department. Deputy Conservator of Forest Chitradurga has also given suitability certificate for the land identified alternatively by Deputy Commissioner, Chitradurga. Accordingly to the extent of land required for Package-I a detailed report is submitted to Deputy Conservator of Forest, Koppa and it is further submitted to Conservator of Forest. Similarly the proposed of forest land required for Package-II is submitted by the Deputy Conservator of Forest, Bhadravati to the Conservator of Forest, Shimoga.

Drinking Water Project

In the estimate of Upper Bhadra Project provision of Rs. 3388 Crores has made towards irrigation component and Rs. 2597 crores towards drinking water component and the same is approved administratively by Government on dated 15-9-2008 and Technically approved by Chief Engineer on dated 19-12-2008. As DPR for drinking water component of Rs. 2597.00 was to be got approved separately. The DPR has been prepared and submitted to TSC for approval. As per the project report it is proposed to fill 119 M.I.tanks in Tumkur and Kolar Districts (75%) and to recharge the underground water and also provide drinking water facility. Considering the possible savings in the water allocated of 5.6 TMC for Tumkur and Kolar Districts water supply scheme under scheme ‘A’ and allocation available from Pollavarom scheme for Pavagada under State Government of 0.54 TMC it is proposed to be utilized and a scheme for providing water to Pavagada taluk with a total allocation of 0.74 TMC is to be administratively approved.

Financial Progress:- The grant and expenditure incurred yearwise on Upper Bhadra Project is as shown below. (Rs. In Lakhs) Sl.. Details 2007-08 2008-09 2009-10 No. Grant Expendit Grant Expenditure Grant Expenditure ure 1. Works 50.00 1.30 9800.00 5082.49 9500.00 11284.14 2. Establishment 1.87 600.00 347.28 500.00 571.14 3. Total 50.00 3.17 10400.00 5429.77 10000.00 11855.28

Sl. Details 2010-11 2011-12 2012-13 No. Grant Expendit Grant Expenditure Grant Expenditure ure 1. Works 11383.00 11727.52 11100.00 10727.39 14800.00 15343.11 2. Establishment 800.00 793.29 1100.00 927.53 1078.00 3. Total 12183.00 12520.81 12200.00 11654.92 14800.00 16421.11

126

INTAKE CANAL

IN T AKE CANAL

PUMPHOUSE-1

127

SPIRAL CASING

Retaining wall of Forebay of Package-1

128

Forebay of Pumphouse of Package-1

129

Construction of Pump House-I near Shantipur of Package II

Construction of Pump House-I near Shantipur of Package II

130

Construction of L/S Retaining wall at Pump House-I near Shantipur of Package II

Cement Concrete lining of Canal at CH:7100 to CH 7450m of Package II

131

Cement Concrete lining of Canal at CH:8700m of Package II

Bed lining of Canal and trimming of side at CH:8700m of Package II

132

Cement Concrete lining of Canal at from CH:8700m to 9200m of Package II

Construction of CTC at CH:8100m of Package II

133

Constr uction of Canal trough aquaduct at CH:7500m of Package II

Errection of Main Transformer at switch yard at Pump house-I of Package II

134

OFFICE COMPLEX OF UBP ZONE, CHITRADURG

OFFICE COMPLEX OF UBP ZONE, CHITRADURG

135

OFFICE COMPLEX OF UBP ZONE, CHITRADURG

ºÉƸÀzÀÄUÀðzÀ PÀbÉÃj PÀlÖqÀ ªÀÄvÀÄÛ ªÀ¸Àw UÀȺÀ PÀlÖqÀUÀ¼À bÁAiÀÄavÀæUÀ¼ÀÄ

136

CE’s Quarters at Chitradurga

AE’s and JE’s Quarters at Chitradurga

137

AEE’s Quarters at Chitradurga

SE’s Quarters at Chitradurga

138

CHALLAKERE OFFICE BUILDING

139

12.9 YETTINAHOLE PROJECT The Yettinahole Project is being designed for providing safe drinking water to the draught prone area of Kolar, Chikkaballapur, Tumkur, Bengaluru Rural district by diverting 24.01 TMC of flood water from Yettihole, Kerihole, Kadumanehole etc. the tributaries of west flowing Nethravathi river. This lift scheme consists of diverting the flood water by construction of small weirs, without harming the forest and ecology and conveying the water through pipe upto Haravanhalli of Hassan district and conveying further through gravity canal upto Tumakur district. Further lifting and conveying the water through pipe for the distance of 8.10 Km upto Devarayandurga, where it is proposed to construct a reservoir to store about 10.00 TMC of water. Then it is proposed to lift the water and conveying through pipe line for a length of 55.90 Km to Kolar district to fill up 139 M.I.tanks and it is proposed for lifting and conveying through pipe line for a length of 80.82 Km to fill the 198 MI tanks in Chikkballapura districts. So total Nos of MI tanks proposed to be filled are 337 to their 60% capacity. The total quantum of water proposed to be supplied to Chikkaballapur and Kolar district is about 10.00 TMC.

As per the feasibility report, it is proposed to supply 14.00 TMC of safe drinking water to Tumkur, Madhugiri Koratagere and Pavagad taluks of Tumakur district and to fill the Chamaraj Sagar reservoir, Hesarghatta tank, Bengalur rural district and Devanhalli Industrial area. A line estimate was prepared and submitted to Government for approval to the project and the Government has accorded in-principle approval vide G.O.No.WRD/203/VIBYAE/2012 Bangalore dated 13-7- 2012 for Rs. 8323.50 crores and instructed to take up the lift component works and conveying up to Haravanhalli distribution station at stage-I for Rs.3269.50 crores on EPC/Turnkey tenders in suitable packages in consultation with T.S.C. of KNNL. Accordingly the lift component works of stage-I have been grouped in 5 packages and tenders have been invited on 2-11-2012 with a time period of 36 months for the completion of work. The tender evaluation reports of above 5 packages have been submitted to Managing Director, KNNL for approval.

The preparation of detailed studies and DPR is entrusted to a consultancy firm namely M/s E.I.Technologies R.I.P (JV) Bangalore for Rs.7.01 crore. The preliminary investigation is completed including detailed survey for a length of 233 Km and capacity survey of reservoir near Devarayandurga. Conducting detailed servey for pipe line to be laid in Chikkaballapur and Kolar district is under progress.

A grant of Rs. 500.00 lakhs was provided for the year 2012-13 and an expenditure of Rs. 37.50 lakhs is incurred.

140

PROJECTS UNDER

CAUVERY NEERAVARI NIGAM LIMITED

141

13. CAUVERY NEERAVARI NIGAMA LIMITED

13.1 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION(S), MYSORE.

The Cauvery Neeravari Nigama Limited (CNNL) is established by the Government of Karnataka in 03.06.2003 under Company Act 1956 as a special purpose to accelerate the implimentation of Cauvery Basin Projects in Karnataka. The Cauvery basin in Karnataka is 34,273 Sq.Kms which constitutes about 17.99% of the geographical area of 1,91,791Sq.Km in Karnataka Major Rivers flowing in this basin are Harangi (50 KM), Hemavathy (245 KM), Lakshmanatheertha (131 KM), Kabini (230 KM), (221 KM), Suvarnvathi (88 KM), Arkavathy (161 KM) and the main river Cauvery (381 KM). The Cauvery Basin has spread in 11 districts. Main Objective of the CNNL are: to complete the works of the ongoing Irrigation projects including Lift Irrigation works, and such works of Minor Irrigation and CADA (Command Area Development Authority). Also to maintain, operate, improve or modernize the irrigation projects including Lift Irrigation works and such works of Minor Irrigation and CADA in the Cauvery Basin entrusted to it by the Government of Karnataka. Three zones viz., Irrigation (S) zone, Mysore, Hemavathy Canal Zone, Tumkur and Hemavathy Project Zone, Gorur are coming under the jurisdiction of CNNL. The details of on going projects coming under each zone are as below:

Programme Name of Sl. for Name of the Project Status Zone No completing the project Irrigation (S) 1 D.D. Urs Canal Physically Completed zone, Mysore 2 Kabini Project On-going 2013-14 3 Harangi Project Physically completed 4 Taraka Project Physically completed 5 Arkavathy Nearing completion 6 Chiklihole Project Physically completed 7 Uduthorehalla Project Physically Completed 8 Iggalur Project Physically Completed 9 Manchanabele Project Physically completed 10 K.R.S. Modernization Physically completed 11 Nanjapura LIS Physically Completed 12 Bannahallyhundi LIS Physically completed Hemavathy Canal Zone, 1 Hemavathy Canal Project On-going 2013-14 Tumkur Hemavathy 1 Hemavathy Project On-going 2013-14 Project Zone, 2 Yagachi Project On-going 2013-14 Gorur 3 Huchanakoppalu LIS Nearing Completion 4 Kamasamudra LIS Physically Completed 5 Kachenahally LIS On-going 2013-14 6 Votehole Project Physically Completed Ongoing projects–5: Nearing completion-2: Physically completed projects– 12.

142

13.1.1 D. DEVARAJA URS CANAL

D. Devaraja Urs Canal project envisages construction of 126 km long Right Bank Canal from Krishnarajasagar reservoir. Administrative approval has been accorded to the Original estimate amounting to Rs.18.50 Crores. vide G.O. No.PWD/145/MKS/77, dtd: 23.04.1979. The work was started during 1979. Administrative approval has been accorded to the revised estimate amounting to Rs.58.10 Crores. vide G.O. No.PWD/145/MMR/86 dtd: 08.08.1988.

The planned utilization from this project is to create an ultimate potential of 80000 acres (32375 ha.) with a cropping area of Khariff semidry and Rabi semidry 59500 acres totalling to 139500 acres. The taluks benefited by this project are Nanjangud, T. Narasipur& H.D. Kote of Mysore district and Srirangapatna taluk of Mandya district.

The main canal work have been completed upto 126 km and the works of distributaries are also completed in all respects. The water allowed upto the tail end on trial basis. 249 cross drainage works and lining to main & distributary canals are completed. The project is physically completed.

The total irrigation potential created is 78432 acres (31741 ha.) as against the contemplated potential of 80000 acres (32375 ha.) A balance potential of 1568 acres (634 ha.) could not be created due to Urbanisation,Industrial development and high mounds.

During 2012-13, a grant of Rs.11.48Crores has been allocated. Upto end of March-2013 an expenditure of Rs.15.17 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.515.68 Crores.

143

13.1.2 KABINI RESERVOIR PROJECT

The project envisages the construction of a composite dam across Kabini River near Beechanahally village in H.D. Kote Taluk of Mysore District. Administrative approval has been accorded to the Original estimate amounting to Rs.3.20 Crores. vide G.O. No. PWD/1/KRS/57 dtd: 02.02.1959. The work was started during 1960. Administrative approval has been accorded to the revised estimate amounting to Rs.390.00 Crores vide G.O. No.PWD/22/MMR/86 dtd: 24.02.1986

The project comprises of both flow and lift irrigation schemes. The planned utilization is 59.65 TMC which comprises of 32.350 TMC in flow and 27.300 TMC in lift to create the ultimate potential of 233347 acres (94434 ha.), which comprises of 110000 acres (44516 ha.) in flow and 123347 acres (49918 ha.) in Lift. The taluks benefited by this project are H.D.Kote, Nanjangudu and T. Narasipura of Mysore District and Gundlupet, Chamarajanagara, Yalandhuru and Kollegala of Chamarajanagara District.

FLOW: The Dam and allied works are completed.

The works of earth work excavation and CD works for the entire length of 26 Km. of LBC are completed. The works of earth work excavation and CD works for the entire length of 202 Km. of RBC are completed. The CC lining works of RBC, from Ch: 0.00 to 100.00 Km is almost completed and the CC lining works from 100.00 to 130.00 Km are in progress. Also, the CC lining works from 130.00 to 140.00 Km are completed. The works is programmed to be completed during 2013-14.

The total irrigation potential created under flow from this project since inception to the end of March 2009 is 109273 acres (44222 ha.) as against the contemplated potential of 110000 acres (44516 ha.) under flow. A balance potential of 727 acres (294 ha.) could not becreated due to high mounds and village limits.

During 2012-13, a grant of Rs.74.87 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.48.93 Crores is incurred. The cumulative expenditure incurred since inception up to end of March 2013 is Rs.825.86 Crores.

144

13.1.3 HARANGI PROJECT

The project envisages the construction of a composite dam across Harangi River near Hulugunda village in Somawarpet Taluk of Kodagu District. Administrative approval has been accorded to the Original estimate amounting to Rs.11.00 Crores. vide G.O. No.PWD/02/GHK/63 dtd: 14.11.1969. The work was started during 1964. Administrative approval has been accorded to the re-revised estimate amounting to Rs.545.00 Crores. vide G.O.No.PWD/14/MMH/2007 dtd: 30.07.2007.

The project comprises of both flow and lift irrigation schemes. The planned utilization is 18.00 TMC which includes of 11.38 TMC in flow and 6.62 TMC in lift. The details of ultimate potential to be created are as below.

Ultimate Length of Potential to be Type Canals Canal in Km. created in acres (ha.) Flow 1 LBC 153.00 29472 (11927) 2 RBC 138.50 71323 (28863) 3 MI tanks - 2600 (1053) Lift 1 Somwarapet LIS 10.00 1500 (607) 2 Piriyapatna LIS 50.00 30000 (12141) Total 134895 (54591)

The taluks benefited by this project are Hunsur, K.R. Nagara,Periyapatna of Mysore District: Arkalgudu of Hassan District and Somawarpet of Kodagu District.

145

FLOW IRRIGATION:

The Dam and allied works are completed. The works of earth work excavation and CD works for entire length of 153 Km of LBCand the entire length of 138.5 Km of RBC are completed. The lining works of Harangi Left Bank Canal for a length of 12.86 Km. from 14.740 to 27.00 Km is taken up. Out of this the lining works from Ch: 14.740 to 19.00 Km and from 23.00 to 27.00 Km are completed. The lining works from 19.00 to 23.00 Km are in progress.

The works of improvements to 20 distributaries from 1 to 18 of Harangi Left Bank Canal are taken up in 6 packages. Out of these, the improvement works of package No.5 & 6 are completed. The improvement works of package No. 1,3 & 4 are nearing completion. The improvements works of package No.2 are in progress.

Action has been taken up for implementing the works of improvements Harangi Right Bank Canal from 0.00 to 25.00 Km. These works are proposed to be completed during 2013-14.

LIFT IRRIGATION SCHEMES: Somawarpete LIS and Piriyapatna LIS arecoming under this project.

1. Somawarpete LIS:

it is proposed to lift 0.800 TMC of water at 12.20 Km of LBC to create a potential of 1500 acres (607 ha.). The head works including 10 Km long canal works are completed and commissioned.

2. Piriyapatna LIS:

It is proposed to lift 324.00 Cusecs of water from Karadilakkanakere tank to create a potential of 30000 acres (12141 ha.). The utilization under this scheme is 5.82 TMC.

The head works and allied works are completed. The total length of the canal is 50 Km and the canal works are completed. The works of 38 distributaries are completed.

The total irrigation potential created including flow and lift under this project since inception to the end of Mar 2010 is 132248 acres (53520 ha.) as against the contemplated potential of 134895 acres (54591 ha.). The balance potential of 2647 Acres (1079 Ha.) could not be created due to high mounds and village limits. The project is physically completed.

During 2012-13, a grant of Rs.36.37 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.40.61 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.630.74 Crores.

146

13.1.4 TARAKA

The project envisages the construction of a composite dam across Taraka River near Penjahally village in H.D. Kote Taluk of Mysore District. Administrative approval has been accorded to the Original estimate amounting to Rs.1.70 Crores. vide G.O. No.PWD/23/GIP/67 dtd: 12.04.1970. The work was started during 1970. Administrative approval has been accorded to the Revised estimate amounting to Rs.51.00 Crores. vide G.O. No.PWD/36/MMF dtd: 15.04.1996.

The planned utilization from this project is 3.20 TMC to create an ultimate potential of 17396 acres (7040 ha.). H.D. Kote taluk of Mysore District is benefited by this project.

The Dam and allied works are completed. The earth work excavation and CD works for 50 Km of LBC and 38.50 Km of RBC are completed. The CC lining works of LBC from 0.00 to 10.00 Km are completed. To augment the short supplies to the reservoir and to the complete atchkat of the project,lifting of 2.07 TMC water from foreshore of Kabini, through Taraka Lift irrigation Scheme is completed and trail run has been conducted.

The total irrigation potential created under this project since inception to the end of March 2009 is 17396 acres (7040 ha.). The project is physically completed.

During 2012-13, a grant of Rs.5.35 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.8.80 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.76.29 Crores.

147

13.1.5 ARKAVATHY PROJECT

The project envisages the construction of a composite dam across Arkavathy River a tributary to River Cauvery near Arobele village in Kanakapura Taluk of Ramanagara District. Administrative approval has been accorded to the Original estimate amounting to Rs.22.25 Crores vide G.O. No.PWD/126/MMK/83 dtd: 27.06.1984. The work was started during 1983-84.

The project comprises of both flow and lift irrigation schemes. The total planned utilization from flow and lift is 3.10 TMC.The planned potential to be created is 15400 acres (6232 Ha) which includes 7500 acres (3035 Ha) by Flow and 7900 acres (3197 Ha) by Lift. Kanakapura taluk of Ramanagara District is benefited by this project.

FLOW: The Dam and allied works are completed. The Length of LBC is 23 Km. and of RBC is 22 Km. and the potential to be created is 4500 acres (1821 ha) and 3000 acres (1214 Ha) respectively totalling to 7500 acres (3035 Ha). The works for entire length of 23 Km of LBC and 22 Km of RBCare completed. Potential created is 7490 acres (3031 Ha). It was not possible to create a potential of balance for 10 acres (4 Ha.).

LIFT IRRIGATION SCHEMES: Arkavathy LBLC LIS and Arkavathy RBLCLISare coming under this project.

LBLC : It is proposed to lift 32.98Cusecs of water on the foreshore of the Arkavathy reservoir to create a potential of 3600acres (1457Ha). The total length of LBLC is 21 Km (18.00 Km + 3.00 Km Reverse canal). The head works, lift main canal and distribution canals are completed and trial run conducted for pumps and water allowed upto 21 Km.

148

RBLC: It is proposed to lift 39.98 Cusecs of water on the foreshore of the Arkavathy reservoir to provide irrigation facilities to 4300 acres (1740 Ha). But, the atchkat coming under the outlets of the canal from 0.00 to 23.00 Km is 3892 Acres (1575 Ha.). The works of main canal are completed and trail run conducted for pumps. The works of distributary canals are nearing completion.

The total irrigation potential created under this project since inception to the end of March 2013 is 15384 acres (6226 Ha) as against the total contemplated potential of 15400 acres (6232 Ha).

During 2012-13, a grant of Rs.6.71 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.4.05 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.201.35 Crores.

13.1.6 CHIKLIHOLE PROJECT

The project envisages the construction of a composite dam across Chiklihole River, a tributary of River Cauvery near Rangasamudra village in Somawarpet Taluk of Kodagu District. administrative approval has been accorded to the original estimate amounting to Rs.3.40 Crores. vide G.O. No.PWD/25/GIP/71 dtd26.08.1977. The work was started during 1978. Administrative approval has been accorded to the revised estimate amounting to Rs.19.20 Crores. The planned utilization from this project is 0.45 TMC to create an ultimate potential of (2137 acres) 865 ha. Somawarapet taluk of Kodagu District is benefited by this project. The Dam and allied works are completed. The works of new LBC for a length of 29 Km are completed. The project is physically completed. The total irrigation potential created under this project since inception to the end of March 2007 is 2138 acres (865 ha.). The cumulative expenditure incurred since inception upto end of 3/2007 is Rs. 19.20 Crores. 149

13.1.7 UDUTHOREHALLA PROJECT

The project envisages the construction of a composite dam across Uduthorehalla River near Ajjipura village in Kollegal Taluk of Chamarajanagara District. Administrative approval has been accorded to the Original estimate amounting to Rs.7.55 Crores. vide G.O. No.PWD/60/GIP/71 dtd: 30.11.1978. The work was started during 1979. Administrative approval has been accorded to the revised estimate amounting to Rs.32.30 Crores. vide G.O. No.PWD/134/MMK/85 dtd: 25.11.1989.

The planned utilization from this project is 1.23 TMC to create an ultimate potential of 16314 acres (6602 ha.). Kollegala taluk of Chamarajanagara District is benefited by this project.

The Dam and allied works are completed. The Length of LBC is 10.20 Km. and of RBC is 9.10 Km. and the potential to be created is 6200 acres (2509 ha.) and 10114 acres (4093 ha.) respectively, totalling to 16314 acres (6602 ha.) The works of entire length of LBC and RBC are completed. This project is physically completed.

The total irrigation potential created under this project since inception to the end of Mar 2009 is 15352 acres (6213 ha.) as against the contemplated potential of 16314 acres (6602 ha.). A balance potential of 962 acres (389 ha.) has not been created due to hillocks and villages.

During 2012-13, a grant of Rs.1.43 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.1.22 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.230.47 Crores.

150

13.1.8 IGGALUR BARRAGE PROJECT

The project envisages the construction of a Barrage across Shimsha River near Iggalur village in Channapatna Taluk of Ramanagara District. Administrative approval has been accorded to the Original estimate amounting to Rs.3.42Crores. vide G.O.No.PWD/17/GIP/71 dtd: 06.12.1977. The work was started during 1977. Administrative approval has been accorded to the revised estimate amounting to Rs.10.75Crores vide G.O.No.PWD/33/MMH/86/ dtd: 23.12.1986.

The project comprises of both flow and lift irrigation schemes. The planned utilization is 1.80 TMC. The ultimate potential to be created is 10532 acres (4263 ha.) which comprises of 3650 acres (1477 ha.) in flow and 6882 acres (2786 ha.) in Lift. The taluks benefited by this project are Channapatna of Ramanagara District: Maddur, Malavally of Mandya District.

FLOW: The Barrage and flow canal works are completed. The Length of LBC is 35 Km. and the works is completed. The potential created is 3650 acres (1477 ha.) LIFT IRRIGATION SCHEMES: 8 No. of LIS schemes are coming under this project. Out of this 5 LIS Viz., Point A, Point C, Point C-2, Hulikere LIS water is lifted from the foreshore and Point D LIS water is lifted from canal to irrigate 6882 acres (2786 ha.). The balance 3 LIS Viz., Point B, LIS and Garkahalli LIS are tank feeding project.

151

The details of 5 LIS used for irrigation pupose are as under:

Sl. Ultimate Potential to be Potential created Name of LIS No. created in acres. (ha) in acres. (ha) 1 Point A 2243 (908) 2204 (892) 2 Point C 1255 (508) 1255 (508) 3 Point C-2 1000 (405) 1000 (405) 4 Point D 1890 (765) 1890 (765) 5 Hulikere 494 (200) 371 (150) Total 6882 (2786) 6719 (2719)

LIS Projects : Point A, C, C-2, D and Hullikere LIS are completed. Potential Created is 6719 acres (2719 ha.). The total irrigation potential created including flow and lift from this project since inception to the end of Mar-09 is 10368 acres (4196 ha.). The balance potential of 163 acres (67 ha.) could not be created due to highmounds and village limits. This project is physically completed.

During 2012-13, a grant of Rs.1.70 Crores has been allocated. Upto end of March -2013 an expenditure of Rs.1.49 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.87.71 Crores.

13.1.9 MANCHANABELE PROJECT

The project envisages the construction of a composite dam across Arkavathy River near Manchanabele village in Magadi Taluk of Ramanagara District. Administrative approval has been accorded to the Original estimate amounting to Rs.2.37 Crores vide G.O.No. PWD/12/GIP/64 dated: 30.09.1969. The work was started during 1969. Administrative approval has been accorded to the re-revised estimate amounting to Rs.18.50 Crores vide G.O.No. PWD/14/MMK, dated: 25.08.86.

152

The planned utilization from this project is 0.80 TMC to create an ultimate potential of 6012 acres (2433 ha.). The taluks benefited by this project are Magadi and Ramanagara of Ramanagara District.

The Dam and allied works are completed. The Length of LBC is 35.00 Km. and of RBC is 36.00 Km. and the potential to be created from these canals are 2768 acres (1120 ha.) and 3244 acres (1313 ha.) respectively. The project is physically completed.

The works for the entire length of LBC and RBC are completed. The project is physically completed. The total irrigation potential created under this project since inception to the end of March 2009 is 6009 acres (2432 ha.).

During 2012-13, a grant of Rs.1.97 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.2.37 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.92.53 Crores.

13.1.10 KRS MODERNISATION

The Krishnarajasagar Reservoir is constructed across the River Cauvery near Kannambaadi village in Srirangapattana Taluk of Mandya District, with Canals on both the flanks for providing irrigation to an extent of 196000 acres (79312 Hectares) of Mandya and Mysore District. The Left Bank High Level Canal, which is named as Vishweshvaraya Canal was originally proposed for providing Irrigation to an extent of 120000 Acres (48,564 Hectares). However, due to various factors like construction of pickup channels, lowering of local mounds in the command area, subsequent extension of certain branch canals etc., there has been considerable increase in the command area of Vishweshvaraya Canal. This has resulted in increased withdrawal in various branches, causing a strain on the canal system. Due to this the supply of water to the atchkat in the tail end reaches was inadequate. The existing canal is carrying higher discharge. Also two major Aqueducts along the canal were not able to carry discharges beyond 67 Cumecs (2366 Cusecs). In order to limit the excess utilisation of water in the

153 atchkat it was programmed to modernize the Vishweshvaraya Canal and also to create fresh atchkat of 5250 Acres (2125 Hectares). Administrative approval has been accorded to the Original estimate amounting to Rs.14.80 Crores. The work was started during 1987. Administrative approval has been accorded to the Revised estimate amounting to Rs.55.00 Crores vide G.O.No. PWD/13/MMG/86, dated: 06.03.1987. Modernization works are completed. The total additional irrigation potential created under this project since inception to the end of Mar 2009 is 5250acres (2125 Ha.). The project is physically completed. During 2012-13, a grant of Rs.15.33 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.10.24 Crores is incurred. The cumulative expenditure incurred since inception upto end of March -2013 is Rs.457.46 Crores.

154

13.1.11 NANJAPURA LIFT IRRIGATION SCHEME

This project envisages to lift 119 Cusecs of water from Cauvery River near Nanjapura village in T.Narasipura taluk ( Town) of Mysore District to feed Turuganur Branch of Vishveshwaraia Canal. Administrative approval has been accorded to the Original estimate amounting to Rs.28.40 Crores vide G.O. No.PWD/197/MMK/1996 dtd: 27.05.1997. Technical sanction accorded to the estimate amounting to Rs.31.60 Crores vide CER No. CER No:119/1998-99.The work was started during 1999-2000.

The scheme is proposed to supply water to an extent10000 acres (4049 ha.) which comprises of creation of additional atchkat of 8000 acres (3239 ha.) and Suffering atchkat of 2000 acres (810 ha.) under Turuganur Branch Canal. The taluks benefited by this project are T.Narsipura of Mysore District and Mallavali of Mandya District.

The scheme is commissioned 01.03.2009 and physically completed. The total irrigation potential created under this project since inception to the end of Mar 2009 is 10000 acres (4049 ha.) as against the contemplated potential of 10000 acres (4049 ha.).

During 2012-13, a grant of Rs.2.44 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.2.28 Crores is incurred. The cumulative expenditure incurred since inception upto end of March -2013 is Rs.71.18 Crores.

155

13.1.12 BANNAHALLIHUNDI LIS

The project envisages to lift 50 Cusecs of water from Right Bank of Kabini River near Tayur Village in Nanjangudu Taluk of Mysore District. Administrative approval has been accorded to the Original estimate amounting to Rs.16.25 Crores. vide G.O. No.ID 272/MMK/97 dtd: 2.02.2001. The work was started during July 2006.

The ultimate potential to be created is 4384 acres (1774 ha.). The taluks benefited by this project are T.Narasipura of Mysore District and Chamarajanagara of Chamarajanagara District.

The scheme is physically completed. The total irrigation potential created under this project since inception to the end of Mar 2009 is 4384 acres (1774 ha.) as against the contemplated potential of 4384 acres (1774 ha.).

During 2012-13, a grant of Rs.0.65 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.0.23 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.20.14 Crores.

156

13.2 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, HEMAVATHY CANAL ZONE, TUMKUR

13.2.1 HEMAVATHY CANAL ZONE, TUMKUR

Hemavathy Canal Zone, Tumkur, was formed as per Government order No. PWD 11 PCO 87 Bangalore, dated 14-1-1987, for execution of Hemavathy canal works and is functioning since 23-04-1987.This is a part of Hemavathy project. This zone look after the execution of canal works viz., Y-Alignment, Tumkur Branch canal, Nagamangala Branch Canal and Lift irrigation scheme at the exit of Bagur – Navile tunnel and providing water supply to Tumkur and Tiptur town from Hemavathy left Bank Canal. Administrative approval has been accorded to the Original estimate of Hemavathy Project amounting to Rs.16.30 Crores. vide G.O. No.PWD/1/GKH/63 dtd: 18.09.1967 for Hemavathy Project. The work was started during 1967. Administrative approval has been accorded to the revised estimate amounting to Rs.3877.00 Crores. vide G.O. No.WRD/46/NHP/2007 dtd: 30.07.2007. This amount comprises of Rs.1751.00 crores towards Hemavathy Project Zone- Gorur and Rs. 2126.00 crores towards Hemavathy Canal Zone, Tumkur.

The canal details are as under.

Ultimate Planned Total Sl. Potential to utilization Canal Details length Taluks Benefited No. be created in in TMC / in Km. acres (Ha) Remarks a) ‘Y’ -Alignment. 5.50 Km - - b) Tumkur Branch 240.00 236990 18.07 Turuvekere, Tiptur, Canal. Km (95,909) Gubbi, Tumkur, Kunigal of Tumkur District c) Nagamangala 78.325 146994 11.19 Turuvekere, Tiptur, Branch Canal. Km (59,488) Gubbi, Kunigal of Tumkur District & Nagamangala in Mandya District d) Lift Irrigation 13.97 5828 0.29 C.R. Patna, in Hassan Scheme at the (RBC) (2,358) District and Tiptur taluk exit of Bagur – 16.25 in Tumkur District Navile Tunnel (LBC) e) Providing Water - - 1.44. Supply to Tumkur &Tiptur Town. Total 389812 30 .99 (1,57,755)

FLOW: Y- alignment The total length of Y alignment is 5.50 Km. Earth work and CD works completed. 2.80 Km lining works are completed.Balance lining is to be done.

Tumkur Branch Canal (0-240 Km): The total Length of Tumkur Branch Canal is 240 Km and the potential to be created is 236990 acres (95909 ha). Out of this

157

240 Km., the canal alignment has been approved upto 228 Km. The earth work excavation, CD works & lining work are almost completed upto 187 Km. Except the canal works of 190.00 Km, the canal works are completed from 188.00 to 197.00 Km. The works of the canal from 198.00 to 220.00 Km are in various stages of progress. The tenders are in process for implementation of canal works from 221.00 to 228.00 Km. The water has been allowed in the canal up to 183 Km.

44 Distributaries are coming under TBC, out of which,the earth work excavation and CD works for distributaries from 1 to 28 are almost completed. The lining works are in different stages of progress. Action has been taken up to implement the works of distributary No. 29 & 30. It is proposed to complete the works during 2013-14.

NAGAMANGALA BRANCH CANAL (0 TO 78.325 Km): The total Length of Nagamangala Branch Canal is 78.325 Km and the potential to be created is 146994 acres (59488 ha). The earth work excavation and CD works of the main canal are almost completed. The lining works of main canal upto60 Km is completed. The lining works of the main canal from 61.00 to 75.00 Km are in various stages of progress. The water has been allowed in the canal upto 72 Km.

22 Distributaries are coming under NBC, out of which, the works of distributary from 1 to 16 are completed and the works of distributary from 17 to 20 are in various stages of progress.

LIFT IRRIGATION SCHEME AT EXIT OF BAGUR – NAVILE TUNNEL:

It is proposed to lift 0.345 TMC of water to create a potential of 5828 acres (2358 ha.) from Y- alignment canal at exit of Bagur- Navile tunnel near Navile village in C.R. Patna Taluk of Hassan District. The Taluks benefited are Tiptur of Tumkur district and C.R. Patna of Hassan District. The work of raising main, distribution chamber and jack well cum pump house are completed and this scheme has been commissioned during February –2004.

The total length of LBC is 13.97 Km and the works for the entire length is completed. The total length of RBC is 16.25 Km. Out of this, the works of the canal up to 9.00 Km are completed and the works of the canal from Km.10.00 to 16.25 are in progress.

The total irrigation potential created including flow and lift under this project since inception to the end of March 2013 is 2,94,385 acres (1,19,136 ha.) as against the contemplated potential of 3,89,812 acres (1,57,755 ha.). The project is proposed for completion during 2013-14.

During 2012-13, a grant of Rs.81.00 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.64.67 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.1476.98 Crores.

158

13.2.2 HEMAVATHY PROJECT – GORUR

The project envisages the construction of a composite dam across Hemavathy River near Gorur village in Hassan taluk of Hassan District. Administrative approval has been accorded to the original estimate of Hemavathy project amounting to Rs.16.30 Crores vide G.O. No.PWD/1/GKH/63 Dated: 18.09.1967. The work was started during 1967. Administrative approval has been accorded to the revised estimate amounting to Rs.3877.00 Crores vide G.O. No.WRD/46/NHP/2007 Dated: 30.07.2007. This amount comprises of Rs.1751.00 Crores towards Hemavathy Project Zone, Gorur and Rs. 2126.00 Crores towards Hemavathy Canal Zone, Tumkur.

The planned utilization from this project is 56.67 TMC which includes the planned utilization of 30.99 TMC to Hemavathy Canal Zone, Tumkur. The balance planned utilisation available to Gorur Zone is 25.68 TMC. The ultimate potential to be created under this project are 310943 acres (125837 ha.) which comprises of 271000 acres (109672 ha.) under flow and 39743 acres (16165 ha.) under lift. The taluks benefited by this project are Hassan, , Arkalagud, Holenarsipura, Channarayapatna of Hassan District: Mandya, K.R.Pet, Pandavapura, Nagamangala of Mandya District: K.R.Nagara of Mysore District and Somwarapete of Kodagu District. The Dam and allied works are completed. The Details of Canals coming under this project are as below. Atchkat in Acres Sl. No. Name of the Canal Length (Hectares) 1 Hemavathy Left Bank Canal 214 Km. 195000 (78,915) 2 Hemavathy Right Bank Canal 91 Km (Full length) 20000 (8,094) Hemavathy Right Bank High Level 106 Km (Full 3 56000 (22,663) Canal length) Sub-Total 2,71,000 (1,09,672) 4 LIS Schemes - 39,943 (16,179) Total - 3,10,943 (1,25,837) 159

PRESENT STAGE:-

Out of 214 Km of Left Bank Canal, Earthwork excavation & C.D. works upto 212 Km are completed. Works of all 72 distributaries are completed. Balance lining works are in progress.

Out of 91 Km of Right Bank Canal, Earthwork excavation & C.D. works upto 91 km are completed. Works of all 57 distributaries are completed Balance lining works are in progress.

Out of 96.70 Km of Right Bank High level Canal, the earthwork excavation, C.D. works and distributaries to a length 96.00 km are completed. Lining works for bed and sides upto a length of 80 km are completed. Works of all 41 distributaries are completed Balance lining works are in progress.

Out of the 14 LIS, 8 Lift Irrigation Schemes are completed. They are Ganjigere, Ramenahalli, Mudigere, Marve, Adikebommanahalli, Kattepura, Hallimysore and Bagur Navile approach. LIS at the exit of Bagur-Navile tunnel has been taken up under Hemavathy Canal Zone-Tumkur and commissioned. Except Kendinne, Maniganahalli and Janardhanahalli LIS, the works of Kyatanahalli and Hosapatna LIS are in different stages of progress.

The total irrigation potential created to the end of March 2013 is 3,11,714 acres (1,26,149 ha.) from flow and lift as against the contemplated potential of 3,10,943 acres (1,25,837 ha.). The project is proposed for completion during 2013-14.

During 2012-13, a grant of Rs.85.85 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.65.73 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.1742.31 Crores.

160

13.2.3 YAGACHI PROJECT

Aqueduct Agile Tunnel

The project envisages the construction of a composite dam across Yagachi River a tributary of Hemavathy near Chikkabyadagere village in Belur Taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.35.38 Crores vide G.O.No.PWD/91/NHP/83, Dated: 27.06.1984. The work was started during 1984-85. Administrative approval has been accorded to the revised estimate amounting to Rs.440.00 Crores vide G.O. No.WRD/40/NHP/2007 Dated: 30.07.2007.

The planned utilisation from this project is 5.74 TMC to create an ultimate potential of 37000 acres (14973 ha.).

The details of canals coming under this project are as under:

Potential to be Sl. No. Name of the Canal Length in Km created in acres(Ha) 1 Yagachi Left Bank Canal 100 29085 (11832) 2 Mosale Branch Canal 10 2500 (950) 3 Kamasamudra Branch Canal 35 5415 (2191) Sub Total 37000 (14973) 4 Kyatanahalli LIS 5685 (2301) Total 42685 (17274)

The taluks benefited by this project are Hassan, Belur and Alur of Hassan District.

Flow: The Dam and allied works are completed The length of YLBC is 100.00 Km.The Earth work excavation and CD works of the canal from 0.00 to 100.00 Km are completed.

The works of aqueduct of 1 st , 2 nd and 3 rd reaches from Ch: 60.54 to 63.56 Km of the canal are completed. The lining works of the canal upto 50.00 Km excluding 2,3,4,5,7,8,13,14,15,16 & 24 th Km are completed. Out of 83 161

Distributaries, the works of 82 distributaries are completed and workof remaining distributary is in progress. The Agile tunnel work at Ch: 75.40 Km is completed. At the exit of Agile tunnel, the canal branches into Mosale&Kamasamudra canals. The length of the Mosale Branch Canal is 10 Km and the works are nearing completion. The length of the Kamasamudra branch canal is 35 Km, out of this the works of the canal from0.00 to 5.00 Km are in progress.Balance works are proposed to be completed during 2013-14

Kyatanahalli LIS it is proposed to lift 0.464 TMC of water from Yagachi Left Bank Canal at Ch 33.133 Km in two stages to provide irrigation facilities to 5685 acres (2301 ha.) in Hassan taluk. This total atchkat comprises of 1920 acres (777 Ha.) from 1 st stage and 3765 acres (1524 Ha.) from 2 nd stage.

1st Stage: Head works, jackwell and pump house works completed. Electro mechanical, rising main and allied works are also completed. The work of providing power supply line is completed. The works of the main canal of length 2.20 Km is completed and distributary network is in progress.

2nd Stage: Administrative approval has been accorded for an estimate comprising of sumpwell, pump house, rising main, cistern, machineries, electrification and earth work excavation, CD works for the canal from 0.00 to 6.235 Km amounting to Rs.8.30 Crores.

The irrigation potential created under this project since inception to the end of March-2013 is 29,397 acres (11,897 Ha) as against the total contemplated potential of 42,685 acres (17,274 Ha).The project is proposed for completion during 2012-13.

During 2012-13, a grant of Rs.35.05 Crores has been allocated. Upto end of March -2013 an expenditure of Rs.37.91 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.432.87 Crores.

13.2.4 HUCHANAKOPPALU LIS

The project envisages to lift 0.936 TMC of water in II stages from Hemavathy River near Huchanakoppalu Village in Holenarasipura taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.6.90 Crores vide G.O. No.LIS/86 dtd: 14.07.1986. The work was started during 1985-86. Administrative approval has been accorded to the revised estimate amounting to Rs.50.00 Crores vide G.O. No.WRD/38/NHP/2007 dtd: 30.07.2007.

The ultimate potential to be created is 8305 acres (3361 ha.) which comprises of 3785 acres (1532 ha.) from 1 st stage and 4520 acres (1829 ha.) from IInd stage. The taluks benefited by this project are Holenarasipura and Arkalgudu taluk of Hassan District. The works of Stage I are completed and commissioned. 162

Stage-II - The Canal works and head works are completed. The balance canal works are nearing completion The total irrigation potential created to the end March 2012 since inception is 8303 acres (3360 ha.) as against the contemplated potential of 8305 acres (3361 ha.) During 2012-13, a grant of Rs.1.75 Crores has been allocated. Upto end of March -2013 an expenditure of Rs.0.91 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.54.55 Crores.

13.2.5 KAMASAMUDRA LIS

The project envisages to lift 1.451 TMC of water in III stages from Hemavathy River near Kamasamudra Village in Holenarasipura taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.0.995 Crores. vide G.O. No.PWD/180/LIS/84 dtd: 12.06.1984. The work was started during 1984-85. Administrative approval has been accorded to the revised estimate amounting to Rs.70.00 Crores. vide G.O. No.WRD/39/NHP/2007 dtd: 30.07.2007. Approval accorded with a condition to complete I & II stage LIS on priority and to take up III stage LIS depending on the availability of water. The ultimate potential to be created is 12670 acres (5128 ha.) which comprises of 2450 acres (992 ha.) from Iststage, 7220 acres (2922 ha.) from IInd stage and 3000 acres (1214 ha.) from III stage. The taluks benefited by this project are Hassan and Holenarasipura taluks of Hassan District. The details of the Canal system are as under.

Sl. Length of Canal Atchkat Stage Name of the Canal No in Km. in acres (ha.) 1 1st stage LBC 14.20 1820 (737) RBC 7.00 630 (255) 2 2nd Stage Malali Branch Canal 54.00 5220 (2113) Nagenahalli Branch 12.40 2000 (809) Canal 3 3rd stage Heragu Canal &RBC 11.00 3000 (1214) Total 12670 (5128)

The works of stage - I and II are completed and commissioned. The Canal works of Malalli and Nagenahalli Branch Canal are nearing completion. The total irrigation potential created to the end of March 2010 since inception is 9098 acres (3682 ha.) as against the contemplated potential of 1 st and 2 nd stage of 9670 acres (3914 Ha). 572 acres (232 Ha) of atchkat curtailed due to un economical reasons. The project is physically completed. During 2012-13, a grant of Rs.1.75 Crores has been allocated. Upto end of March -2013 an expenditure of Rs.1.12 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.60.12 Crores.

163

13.2.6 KACHENAHALLI LIS

The project envisages to lift 0.73 TMC of water in III stages from Hemavathy River near Kachenahalli Village in Channarayapatna taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.8.90 Crores vide G.O. No.PWD/1/NHP/92 dtd:27.12.1991. The work was started during 1991. Administrative approval has been accorded to the revised estimate amounting to Rs.68.30 Crores vide G.O.No.WRD /35/NHP/99, dated 19.10.2002. Further, Administrative approval has been accorded to the Re- revised estimate amounting to Rs.165.00 Crores vide G.O. No.WRD/37/NHP/2007 dtd: 30.07.2007. Approval accorded with a condition to complete I & II stage LI Schemes on priority and to take up III stage LIS depending on the availability of water.

The ultimate potential to be created is 12600 acres (5100 ha.) which comprises of 1390 acres (563 ha.) from I stage, 6610 acres (2675 ha.) from IInd stage and 4600 acres (1862 ha.) from III stage respectively. The taluks benefited by this project are Holenarasipura, Hassan, Arasikere and Channarayapatna of Hassan District. The details of the Canal system are as under.

Sl. Length of Atchkat in acres Stage Name of the Canal No Canal in Km. (ha.) 1 1st Stage Samudravalli Main Canal 1.875 1390 (563) 2nd Stage Dandiganahalli Branch 2 22.50 5385 (2179) Canal Bijamaranahalli Branch 8.00 1225 (496) Canal 3 3rd Stage Gandsi Branch Canal 32.00 4600 (1862) Total 12600 (5100)

In stage I the head works and Earth Work Excavation of Samudravalli Main Canal is partially completed. Head works, Intake canal, pump & jack well cum pump house works are completed. Rising main and Electro-mechanical works are in progress. The works of distributaries are also in progress.

In stage II earth work excavation for Dandiganahalli and Bijamaranahalli branch canals are partially completed.

The total irrigation potential created to the end of March 2013 since inception is 1389 acres (562 ha.) from 1st stage as against the total contemplated potential of 12,600 Acres (5100 Ha.). The project is proposed for completion during 2013-14.

During 2012-13, a grant of Rs.29.00 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.18.68 Crores is incurred. The cumulative expenditure incurred since inception upto end of March -2013 is Rs.59.53 Crores.

164

13.2.7 VOTEHOLE PROJECT

The project envisages the construction of a composite dam across Votehole River near Lakkenahally village in Belur Taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.2.05 Crores. vide G.O. No. PWD/GIP/64, dtd: 15.12.1971. The work was started during -1971. Administrative approval has been accorded during 22.02.1996 to the revised estimate amounting to Rs.38.00 Crores. Further, administrative approval has been accorded to the Re-revised estimate amounting to Rs.59.75 Crores vide G.O. No.WRD/47/NHP/2007 dtd: 30.07.2007. The planned utilization from this project is 2.40 TMC to create an ultimate potential of 18500 acres (7487 ha.). The details of Canals coming under this project are as below.

Atchkat Sl. Length Name of the Canal in Acres No. in Km (Hectares) 1 Left Bank Canal 10 500 (202) 2 Right Branch Canal 45 10582 (4283) 3 Nakalgud Branch Canal 15 7418 (3002) Total 18500 (7487)

The taluks benefited by this project are Belur and Alur of Hassan District. The Dam and allied works are completed. The Canal works are also completed.

The total irrigation potential created under this project since inception to the end of March 2009 is 18500 acres (7487 ha.). This project is physically completed.

During 2012-13, a grant of Rs.1.00 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.1.11 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.63.65 Crores.

165

13.3 DRINKING WATER SCHEMES

13.3.1 DRINKING WATER SCHEME TO GULUR-HEBBUR HOBLIES IN TUMKUR DISTRICT

Drinking water scheme to Gulur-Hebbur Hoblies in Tumkur District envisages lifting of 51 cusecs of water in 2 stages from Tumkur Branch Canal of Hemavathy project at Ch: 142.225 Km to feed water to 23 tanks of Gulur Hobli and 29 tanks of Hebbur Hobli totaling to 52 tanks (impounding reservoirs) and to fulfill the demand of providing drinking water to 52 villages of Gulur-Hebbur hoblies in Tumkur District. The Government vide order No. WRD 315 NHP 2003, Bangalore, Dtd: 11.02.2009 has accorded administrative approval to the scheme amounting to Rs.55.00 Crores. The works of 1 st stage are completed and commissioned. The water allowed to 18 tanks on trial run. The works of 2 nd stage are almost completed and commissioned. The water allowed to 20 tanks on trial run. The balance works are in progress. The project proposed for completion during 2013-14.

During 2012-13, a grant of Rs.4.00 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.3.83 Crores is incurred. The cumulative expenditure incurred since inception upto the end of March 2013 is Rs.63.41 Crores

13.3.2 DRINKING WATER SCHEME TO HONNAVALLI AND OTHER HOBLIES

Drinking water scheme to Honnavalli and other Hoblies envisages lifting of 27.03 cusecs of water for Tiptur branch and 31.25 cusecs of water for Arasikere Branch independently from Tumkur Branch Canal of Hemavathy project at Ch: 9.9 km. From Tiptur Branch it is proposed to feed water to 18 no of tanks which are coming in series and 48 villages of Tiptur taluk are benefited. Whereas from Arasikere branch it is proposed to feed water to 5 tanks which are coming in series i.e., 3 tanks of Arasikere taluk, one tank of Kadur taluk and one tank of Hosadurga taluk and 38 villages i.e., 20 villages of Arasikere taluk, 8 villages of Kadur Taluk and 10 villages of Hosadurga Taluk are benefited. The Government vide order No. WRD 26 NHP 2008, Bangalore, Dtd: 11.02.2009 has accorded administrative approval to the scheme amounting to Rs.87.20 Crores.The water is allowed to 20 tanks through Tiptur and Arasikere Branches on trial run. The balance works are in progress. The project is proposed for completion during 2013-14.

During 2012-13, a grant of Rs.18.00 Crores has been allocated. Upto end of March-2013 an expenditure of Rs.19.26 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.75.54 Crores.

13.3.3 FILLING UP OF 20 TANKS OF CHAMARAJANAGAR, NANJANGUD AND GUNDLUPET TALUKS - DRINKING WATER SCHEME.

The scheme envisages lifting of 0.6 TMC of water in 3 stages from Kabini River near Alambur village to fill 20 tanks of Harve, Haradanahalli and 166

Kasabahoblis of Chamarajanagar Taluk, Kavalandehobli of Nanjangud Taluk and adjacent Hoblies of Gundlupet taluk to provide drinking water supply to drought affected areas and to improve ground water table. The Government vide order No. WRD 10 MMK 2009, Bangalore, Dtd: 15.04.2011 has accorded administrative approval to the scheme amounting to Rs.212.00 Crores.The works of 3 stages of this scheme are in progress.The scheme proposed for completion during 2013-14.

During 2012-13, a grant of Rs.72.00 Crores has been allocated.Up to end of March-2013 an expenditure of Rs.95.80 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2013 is Rs.120.65 Crores.

13.3.4 FILLING UP OF KANVA AND OTHER 17 TANKS - DRINKING WATER SCHEME.

The villages of Channapatna Taluk of Ramanagar District are drought prone areas and under ground water level had gone down sufficiently and created problem for even drinking water to villagers. In order to overcome this it is proposed to lift 0.903 TMC of water from Iggalur barrage to fill and other 17 tanks so as to provide drinking water supply and to raise the underground water level. The Government vide order No. WRD 38MMK 2012, Bangalore, Dtd: 10.05.2012 has accorded administrative approval to the scheme amounting to Rs.198.00 Crores. The works are in progress. The project proposed for completion during 2013-14.

During 2012-13, a grant of Rs.45.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.0.17 Crores is incurred.

13.3.5 FILLING UP OF VAJRANAKATTE, C.KATTIGENAHALLI AND KOPPA TANKS - DRINKING WATER SCHEME. The scheme envisages inter linking of Vajranakatte, C.Kattigenahalli &Koppa tanks and feeding 21 Mcft of water to these tanks from Ch: 14600 m. of D-23 of Tumkur Branch Canal. The Government vide order No. WRD 71 NHP 2009, Bangalore, Dtd: 13.06.2011 has accorded administrative approval to the scheme amounting to Rs.2.20 Crores.The works of the scheme are in progress. The scheme proposed for completion during 2013-14. During 2012-13, a grant of Rs.1.00 Crores has been allocated.Up to end of March-2013 an expenditure of Rs.0.22 Crores is incurred.

13.3.6 FILLING UP OF BELLAVI AND 5 OTHER TANKS - DRINKING WATER SCHEME The scheme envisages lifting of 7.50 Mcft (4 Cusecs) of water from Ch: 106.80 Km of Tumkur Branch Canal to feed Bellavi and other 5 tanks to provide drinking water supply to Bellavi and other 5 surrounding villages of Gubbi Taluk ofTumkur District. The Government vide order No. WRD 79 NHP 2010, Bangalore, Dtd: 19.03.2012 has accorded administrative approval to the scheme amounting to Rs.5.70 Crores. The works of the scheme are in initial stages of progress. The scheme proposed for completion during 2013-14. During 2012-13, a grant of Rs.2.00 Crores has been allocated.Up to end of March-2013 an expenditure of Rs.0.06 Crores is incurred.

167

13.3.7 FILLING UP OF 26 TANKS OF CHIKKANAYAKANAHALLI TALUK - DRINKING WATER SCHEME.

The scheme envisages lifting of 0.80 TMC of water from Tumkur Branch Canal of Hemavathy project to fill 26 tanks comprising filling of 22 tanks through gravity and 4 tanks through lift to provide drinking water supply to drought affected villages of Chikkanayakanhalli taluk. The Government vide order No. WRD 74 NHP 2009, Bangalore, Dtd: 20.07.2011 has accorded administrative approval to the line estimate of the scheme amounting to Rs.102.60 Crores. The works of the scheme are in progress. The scheme proposed for completion during 2014-15.

During 2012-13, a grant of Rs.20.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.0.37 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2013 is Rs.0.54 Crores.

13.3.8 FILLING UP OF DODDAGUNI TANK – DRIKNIG WATER SCHEME

The scheme envisages lifting of 18.20 Mcft of water from Ch: 64.625 Km of Tumkur Branch Canal of Hemavathy project to fill Doddaguni tank in order to provide drinking water supply to Doddaguni and other 14 villages in Gubbi Taluk of Tumkur District. The Government vide order No. WRD 53 NHP 2008, Bangalore, Dtd: 13.06.2011 has accorded administrative approval to the scheme amounting to Rs.3.25 Crores. The works of the scheme are in progress. The scheme proposed for completion during 2013-14.

During 2012-13, a grant of Rs.2.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.2.89 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2013 is Rs.2.90 Crores.

13.3.9 FILLING UP OF 24 TANKS OF HALEBEEDU HOBLI AND 15 TANKS OF MADIHALLI HOBLI OF BELUR TALUK – DRIKNIG WATER SCHEME

The scheme envisages lifting of 0.22 TMC of water from Yagachi Left Bank Canal to fill 24 tanks of Halebeedu Hobli and 15 tanks of Madihallihobli under Belur Taluk to provide drinking water supply. The Government vide order No. WRD 43 NHP 2010, Bangalore, Dtd: 05.07.2011 has accorded administrative approval to the scheme amounting to Rs.9.00 Crores. The works of the scheme are in progress. The scheme proposed for completion during 2013-14. During 2012-13, a grant of Rs.3.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.1.33 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2013 is Rs.1.39 Crores.

168

13.3.10 FILLING UP OF 11 TANKS OF NUGGEHALLI HOBLI OF CHANNARAYAPATNA TALUK – DRIKNIG WATER SCHEME

The scheme envisages lifting of 33.00 Cusecs of water from Bagur Navile approach tunnel of Hemavathy Project to fill 11 tanks and to provide drinking water supply to 15 surrounding villages of Nuggehallihobli of Channarayapatna Taluk. The Government vide order No. WRD 54 NHP 2011, Bangalore, Dtd: 19.03.2012 has accorded administrative approval to the scheme amounting to Rs.17.60 Crores. Action has been taken to implement the scheme and proposed for completion during 2013-14.

During 2012-13, a grant of Rs.5.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.0.01 Crores is incurred.

13.4 MODERNISATION OF ANECUT AND ITS CANALS

13.4.1 MODERNISATION OF MANDAGERE AND HEMAGIRI ANECUT AND THEIR CANALS

Modernisation of Mandagere Anecut Canals: Mandagere Anecut is constructed accorss river Hemavathy in Mandagere Village, K.R Pet Taluk, Mandya District during 1903. This anecut is in upstream of Cauvery Valley. There are two canals for this anecut. Mandagere Left Bank Canal is 33.50 Km long and 1938 Ha. atchkat comes under this canal. Mandagere Right Bank Canal is 47.50 Km long and 4850 Ha. atchkat comes under this canal. There is suffering atchkat of 719 Ha. in Khariff and 1110 Ha. during summer, totaling to 1827 Ha. under these canals. The atchkat area is spread out in K.R Pet taluk of Mandya district and K.R Nagar taluk of Mysore district.

Modernisation of Hemagiri Anecut Canal: Hemagiri Anecut is constructed across river Hemavathy in Bandihole Village, K.R Pet Taluk, Mandya District during 1880. This anecut is in upstream of Cauvery Valley. There is one canal for this anecut. Hemagiri Left Bank Canal is 35.85 Km long and 1602 Ha. atchkat comes under this canal in K.R Pet Taluk, Mandya District. There is suffering atchkat of 237 Ha. in Khariff and 584 Ha. during summer, totaling to 821 Ha. under this canal. The Government has accorded administrative approval to the detailed project report for the work of Modernisation of Mandagere and Hemagiri Anecut Canals amounting to Rs.141.00 Crores vide Government Order No. WRD 91 MMK 2009, Bangalore, Dated: 13.04.2011. Modernisation works of Mandagere and Hemagiri Anecut canals are nearing completion.

During 2012-13, a grant of Rs.50.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.68.85 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2013 is Rs.192.10 Crores.

169

13.4.2 MODERNIZATION OF KRISHNARAJA (KATTEPURA) ANECUT AND ITS CANALS: Krishnaraja anecut is the first anecut constructed across river Cauvery during 1732 near Kattepura village of Arakalgud taluk of Mysore district. This area lies in upper Cauvery basin. This anecut has 2 canals namely Kattepura Left Bank Canal for a length of 40.20 Km with an atchkat of 949 Ha. in Arakalgud taluk of Hassan district and Right Bank Canal for a length of 83.60 Km with an atchkat of 2600 Ha in Arakalgud taluk of Hassan district and K.R. Nagar taluk of Mysore district. There is a suffering atchkat of 944 Ha. The Government vide order No. WRD 63 NHP 2009 Bangalore Dtd: 08.02.2010 has accorded administrative approval to the DPR for the modernization of Krishnaraja (Kattepura) anecut and its canals amounting to Rs.90.00 crores. The works of modernisation of Kattepura Anecut & its Canals are in progress and proposed for completion during 2013-14.

During 2012-13, a grant of Rs.20.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.40.67 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2013 is Rs.81.57 Crores.

13.4.3 MODERNISATION OF MIRLE AND RAMASAMUDRA ANECUT AND ANECUT CANALS Mirle Anecut is constructed across river Cauvery during 1850 near Chunchanakatte village in K.R Nagar Taluk of Mysore District. This area lies in upper Cauvery basin. This anecut is having a Left Bank Canal for an length of 10.60 Km. which is named as Attikatte Canal. With an atchkat of 1942 Ha. in K.R Nagar Taluk of Mysore District. This canal has a branch canal of length 3.5 Km. which is named as KakanaKaluve and 4 seepage canals for a length of 55 Km. There is a suffering atchkat of 40 Ha. Ramasamudra Anecut is constructed across river Cauvery during 1850 near Chunchanakatte village in K.R Nagar Taluk of Mysore District. This area lies in upper Cauvery basin. This anecut is having a Right Bank Canal for a length of 59.20 Km with an atchkat of 2761 Ha. in K.R Nagar Taluk, Mysore District. There is a suffering atchkat of 70 Ha. The Government vide order No. WRD 77, MMK 2009, Bangalore, Dtd: 05-11-2011 has accorded administrative approval to to the DPR for the modernization of Mirle and Ramasamudra Anecut and Anecut Canals amounting to Rs.64.00 Crores. The modernisation works are in progress and proposed for completion during 2013-14. During 2012-13, a grant of Rs.18.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.10.13 Crores is incurred.

13.4.4 MODERNISATION OF CHAMARAJ ANECUT AND ITS CANAL Chamaraj Anecut is constructed across river Cauvery during 1885 near Sakkare village of K.R Nagar Taluk of Mysore District. This area lies in upper Cauvery basin. This anecut is having 2 canals namely Left Bank Canal for a length of 39 Km with a 11 branches of 69 Km and have an atchkat of 3995 Ha. in K.R Nagar Taluk of Mysore district. Whereas, Right Bank Canal for a length of 63.00 Km. with 15 branches of 73.65 Km. and have an atchkat of 5275 Ha. in K.R Nagar, Hunsur Taluks of Mysore district. There is a suffering atchkat of 2000 Ha. The Government vide order No. WRD 76 MMK 2009 Bangalore Dtd: 11.01.2012 has accorded administrative approval to the DPR for the 170 modernization of Chamaraja anecut and its canals amounting to Rs.132.00 Crores.The modernisation works are in progress and proposed for completion during 2013-14. During 2012-13, a grant of Rs.30.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.42.25 Crores is incurred.

13.4.5 MODERNISATION OF MADHAVAMANTRI ANECUT AND ANECUT CANALS

Madhavamantri anecut is constructed across river Cauvery during 1140 near Talakadu village in T.Narasipura Taluk of Mysore District. This area lies in lower Cauvery basin. This anecut is having a Left Bank Canal for a length of 29.10 Km with an atchkat of 766 Ha comprising of 1590 Ha in T.Narasipura Taluk of Mysore District and 766 Ha. in Malavalli Taluk of Mandya District. There is a suffering atchkat of 550 Ha. The Government vide order No. WRD 53 MMK 2011, Bangalore, Dtd: 18.10.2011 has accorded administrative approval to to the DPR for the modernization of Madhavamantri Anecut and Anecut Canals amounting to Rs.19.00 Crores. The modernisation works are in progress and proposed for completion during 2013-14.

During 2012-13, a grant of Rs.6.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.1.43 Crores is incurred.

13.4.6 MODERNISATION OF DEVARAYA ANECUT AND ANECUT CANALS

Devaraya Anecut is constructed across River Cauvery during 17 th Century near Majjigere village in Srirangapatna Taluk of Mandya District. This area lies in lower Cauvery basin. This anecut is having a Right Bank Canal for a length of 36.30 Km with an atchkat of 1427 Ha in Srirangapatna Taluk of Mandya District and Mysore Taluk of Mysore District. There is a suffering atchkat of 290 Ha. The Government vide order No. WRD 51 MMK 2011, Bangalore, Dtd: 18.10.2011 has accorded administrative approval to the DPR for the modernization of Devaray Anecut and Anecut Canals amounting to Rs.21.00 Crores.The modernisation works are in progress and proposed for completion during 2013-14.

During 2012-13, a grant of Rs.8.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.0.02 Crores is incurred.

13.4.7 MODERNISATION OF CHIKKADEVARAYA SAGAR EXTENSION CANAL

ChikkadevarayaSagar Anecut is constructed across River Cauvery on the down stream side of Krishnarajasagar Dam during 17 th Century in Srirangapatna Taluk of Mandya District. The CDS Left Bank Canal joints Bannur Tank after traversing a length of 105 Km from the Anecut. The CDS extension canal runs for a length of 26 th Km from Bannur Tank and with a carrying capacity of 155 Cusecs of water and have an atchkat of 1997.97 Ha in T.Narasipura Taluk of Mysore District. There is suffering atchkat of 303.38 Ha. The Government vide order No. WRD 41 MMK 2012, Bangalore, Dtd: 13.07.2012 has accorded administrative approval to the DPR for the modernization of ChikkadevarayaSagar extensionCanal amounting to Rs.17.00 Crores. Action has 171 been taken to implement the modernisation works and proposed for completion during 2013-14.

During 2012-13, a grant of Rs.10.00 Crores has been allocated. Up to end of March-2013 an expenditure of Rs.0.08 Crores is incurred.

IMPROVEMENTS TO VISHWESHWARAIAH CANAL NETWORK.

The length of the main canal, branch canals, sub branch canals and distributary canals of Vishweshwaraiah canal network is 1523.30 Km. excluding the works taken up under modernisation earlier in the main canal and selected branch canals and lining works taken up in vulnerable reaches totalling to 522.50 Km. It is proposed to take up the improvements to Vishweshwaraiah canal networks for an approximate length of 1000.80 Km. Out of this, a length of 452.00 Km is identified on priority to take up the improvement works. As such the Government vide order No. WRD 68 MMK 2012, Bangalore, Dtd: 24.08.2012 has accorded administrative approval to the DPR for the Improvements to Vishweshwaraiah canal network amounting to Rs.330.00 Crores. Action has been taken to implement the Improvements to Vishweshwaraiah canal network in 5 packages comprising of 11 estimates. The works of 4 packages are in progress and proposed for completion during 2013-14.

During 2012-13, a grant of Rs.110.50 Crores has been allocated. Up to end of March- 2013 an expenditure of Rs.0.50 Crores is incurred.

REJUVENATION OF ARKAVATHY RIVER

Arkavathy River is a part of Cauvery river. This river originatesin Nandi Hills and after traversing a distance of around 190 Km join river Cauvery at confluence point in Kanakapura Taluk. Hesaraghatta reservoir and after joining of Kumudwati river, Tippagondanahalli reservoir have been constructed the provide drinking water supply to Bangalore city. Since, the inflow to these reservoirs is meagre, water is being lifted from Cauvery river for provide drinking water supply to Bangalore. In view of much pressure for supplying of water to Bangalore,it is proposed to take up rejuvenation worksin Hesaraghatta, Kumudwathi and Arkavathi catchment areas from the originating point of Arkavathy river to Tippagondanahalli reservoir. The Government vide order No. WRD 23 MMK 2009, Bangalore Dated: 19.10.2011 has accorded administrative approval to the estimate for Rejuvenation of the Arkavathy River amounting to Rs.22.43 Crores. The works of this project are in progress and proposed for completion during 2013-14.

During 2012-13, a grant of Rs.15.00 Crores has been allocated. Up to end of March- 2013 an expenditure of Rs.6.94 Crores is incurred. 172

PROJECTS UNDER NON-NIGAM ZONES OF WATER RESOURCES DEPARTMENT

173

14. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION PROJECT ZONE, GULBARGA

14.1. KARANJA PROJECT Karanja Irrigation project is a major irrigation project located near Byalhalli village in Bhalki Taluk of Bidar District across River Karanja, a tributary of River Manjra which joins River Godavari. This project envisages to irrigate 29,227 Ha land in Bhalki, Bidar and Humnabad taluka of Bidar by utilizing 9.27 TMC of Water. The Project is getting CA under AIBP.

 Dam: Dam is completed. Garden below the dam is being developed.  Left Bank Canal: Upto 31.00 Km with distributaries completed.  RBC: upto 131.00 Km. is completed. Distributary at 107 Km is in progress.  Karanja Lift Irrigation Scheme: Intake canal, pumphouse, jackwell, delivery chamber are completed. Re-modelling of raising main is completed and the scheme is inaugurated on 09-09-2012. Total length of canal is 24.00 Km, out of which works upto 21 km is completed. Balance works in Km 22, 23, 24 and FIC are in progress. The works of D-1A is under progress.  Atiwal Lift Irrigation Scheme: Construction of jackwell & raising main is in progress.  R and R: Nine rehabilitation centres are formed for the affected eight villages. Seven rehabilitation centres are completed and handed over to the concerned Panchayat Authorities. The yearwise financial details are as below:

Financial in Crores Sl. No. Year Target Progress

1 2010-11 23.18 21.77

2 2011-12 30.88 24.34

3 2012-13 24.35 22.93

Revised cost of the project is Rs.635.18 crores. Cummulative expenditure and potential created upto end of March-2013 are Rs. 560.24 crores and 22,793 Ha respectively.

174

Total Cost of the Project: a) Original Cost R 9.90 Crores. b) Revised Cost approved R 532.00 Crores. c) Latest Estimated cost R 630.00 Crores.

Achtkat details : a)Contemplated Achtkat 29,227 Ha b)Covering districts 1. Bidar. c)Covering Talukas. 1. Bhalki. 2. Bidar, 3. Humnabad.

No. of villages benefited and extent of 71 Nos. of villages, Distributory wise area . potential details appended in Annexure-I. Land acquisition Details: Required area in Acquired area in Ha Ha a)Land acquired for submersion of dam 6172.77 5780.62 and allied works. b) Canal and others works. 2240.71 2056.50 c) R & R works 153.121 153.12 Potential details: Wet a) Total potential to be created 29,227 Ha b) Potential created to the end of March- 22,113 Ha 2013 c) Balance 7114 Ha Target 2013-14 Year Financial Details : a) Latest Cost of the project R 630.00 crores b) Expenditure incurred upto March-2013 R 560.24 crores c) Balance Cost R 69.76 crores d) Grant allotted for 2012-13 under 4700 AIBP R 1746.00 lakhs Non AIBP R 1341.59 lakhs Total R 3087.59 lakhs e) Grant allotted for 2012-13 under 2700 R 74.40 lakhs f) Expenditure during the year 2012-13 under 4700 AIBP R 929.63 lakhs Non AIBP R 1341.59 lakhs Total R 2034.26 lakhs G) Expenditure during the year 2011-12 under 2700 R 74.40 lakhs Physical and Financial Target and Physical Financial achievement for 2012-13 under 4700. (in Ha) (`. in crores) Target 6434 89.35 Achievement Nil 22.78 FIC Details a) Contemplated FIC atchkat 29,227 Ha b) Completed FIC 22,113Ha c) Balance FIC 7,114 Ha

175

Annexure-II KARANJA PROJECT

Rehabilitation & Resettlement Works

No. of project displaced person Name of Sl. Village rehabilitation Stage of R&R works No. Total Total Total structures families population centre

1 2 3 4 5 6 7

1 Kamalapur 118 135 1670 Kamalapur Works of providing basic amenties are 2 Sindabandagi 354 372 1279 Sindabandagi completed and rehabilitation centres are 3 Sangolgi 314 365 2076 Sangolgi handed over to Zilla Panchayat 4 Nelwad 156 298 976 Nelwad during 2000

5 Hajjargi 87 108 546 Hajjargi

6 Atiwal 78 298 377 Atiwal

7 Dakulgi 190 331 1276 Dakulgi 8 Ranjol 286 366 1500 Works of providing basic amenties are completed during 2004. But rehabilitants denied to receive Ranjol Kheni-1 Hakku Patras and put the demand to give transportation charges of Rs.20,000/- per house. Works of providing basic amenties like road, drains, water Ranjol Kheni-2 supply are nearing completion.The electrification work is under progress. Total : 1583 2273 9700

176

14.2 ERM OF 4 MEDIUM IRRIGATION PROJECTS IN GULBARGA DISTRICT UNDER A.I.B.P

CHANDRAMPALLI PROJECT

Brief History of the project

Chandrampalli Project is located on Sarnala (Krishna Basin) near Chandrampalli village in Chincholi taluka in Gulbarga Dist. The project was administratively approved vide G.O.NO. PQDMMI/159, dated 16-12-1963 for R99.84 Lakhs. The project is commissioned during 1975.

A) DAM :- The project has 926.54 mtrs, length of earthen embankment. The spillway of the project is located on left flank saddle and comprises of broad crested weir of 64 m length, with 6 Nos. of gates size 9.15 m x 5.50. The spillway is designed for maximum discharge of 864.80 cumecs (30700 cusecs). Water is being stored in the reservoir since 1973.

B) CANAL :- R.B.C. The total length of Right Bank canal is 14.00 Km, and is completed. The discharge capacity at head is 1.28 cumecs (45 cusecs). The contemplated atchkat is 1741 ha, the canal section is damaged at many reaches. Therefore modernization / renovation under AIBP/ERM of main canal and Distributaries has been proposed

L.B.C. :- The total length of Left Bank Canal is 21.00 km, and is completed. The discharge capacity at head is 2.74 Cumecs (97 cusecs). Contemplated atchkat under LBC is 3482 ha. the canal section is damaged at many reaches. Therefore modernization / renova- tion of main canal and Distributaries has been proposed.

Total Cost of the Project: a)Original Cost R 99.84 Lakhs. b)Revised Cost R 201.00 Lakhs. c) Latest Estimated cost. R 201.00 Lakhs. Achtkat details : a)Contemplated Achtkat 5223 Ha. b)Covering districts Gulbarga. c)Covering Talukas. Chincholi. No. of villages benefited and extent of area 8 Nos. Land acquisition Details: a)Land acquired for dam and allied works. 764 acres. b)Canal and others work. 430 acres. c)R & R works No Rehabilitation. Potential details . a) Total potential to be created 5223 b) Potential created to the end of March-2010 5223 Financial Details : a)Latest Cost of the project R 201.00 Lakhs b)Expenditure incurred upto date c) Balance Cost -- d)Programme of Balance Cost: -- FIC Physical and Financial Details. Physical Financial a)Contemplated FIC atchkat 5223 R 201.00 Lakhs

177

HATTIKUNI TANK PROJECT:

Brief History of the project: Hattikuni Tank Project is located on Hattikuni stream near Hattikuni village about 12 Kms, from Yadgir Town. The project was administratively approved vide G.O.NO. PWD 12 MIP 57, dated 20/26-12-1957 for R22,08,300/-. The revised cost of completion is Rs. 91.00 lakhs which is approved by G.O.NO. PWD 54 MTP 83, dated 24 Sept. 1983.

A) DAM :- The dam consists 923.50 mtrs, length of earthen embankment and the length of the spillway is 76.20 mtrs, with 9 N0s. of gates size 7.62m x 1.82 mtrs. The spillway is designed for maximum flood discharge of 13306 cusecs. Water is being stored in the reservoir since 1973.

B) CANAL :- Only L.B.C. The total length of Left Bank canal is 14.00 Km, and is completed. The discharge capacity at head is 1.41 cumecs (50 cusecs) to irrigate 2145 Ha. The canal section is damaged at many reaches .

Total Cost of the Project: a)Original Cost R 22.00 Lakhs. b)Revised Cost R 91.00 Lakhs. c) Latest Estimated cost . R 91.00 Lakhs. Achtkat details : a)Contemplated Achtkat 2145 Ha. b)Covering districts Yadgir. c)Covering Talukas. Yadgir. No. of villages benefited and extent of area. 6 Nos. Land acquisition Details: a)Land acquired for submersion of dam and allied -- works. b)Canal and others work. -- c)R & R works -- Potential details . Wet a) Total potential to be created 2145 Ha b) Potential created to the end of march-2012 2145 Ha Financial Details : a)Latest Cost of the project R91.00 Lakhs b)Expenditure incurred upto date Project completed in the year 1973 and is under maintainance. c) Balance Cost FIC Physical and Financial Details Physical Financial a) Contemplated FIC atchkat 2145 R91.00 Lakhs (project cost) b) Expenditure incurred upto 31-03-2012 -- --

178

3. UPPER MULLAMARI PROJECT :

Brief History of the project The Upper Mullamari Project envisages construction of an earthen dam with ungated spillway at the right bank across Mullamari River which is a tributary of Kagina River which joins river Bheema. This project hs been administratively approved vide G.O. NO. PWD 160 GIP 77, dated 17-8-79 for R328.00 Lakhs @ SR 75-76 and Technically sanctioned by CE, TBP, Munirabad vide CER N0. 3/79-80, dated 26-8-1980. The revised cost of project is approved for R19.92 Crores in the year 1992-93 and the latest revised cost of project is R22.58 Crores.

DAM :- The Dam consists of 810.00 mts length of Earthen Embankment with zonal section with maximum height of dam 23.00 m for gross storage of 21.22 M.cum (0.749 TMC) and live storage of 18.88 M.cum (0.666 TMC)

R.B.C.: - The total length of Right Bank Canal is 43.00 Km, and is completed. The discharge capacity at the head is 1.61M.cum (57.20 Cusecs). The canal section is damaged at many reaches. Therefore modernization/renovation of main canal and distributaries under AIBP/ERM has been proposed and the proposal has been submitted to CWC, Delhi, for Central Assistance vide this office ltr.No.KNNL/CEG/ERM/TA-1/AE-6/ CDO/2009-10, dated 12-01-2010 amounting to R821.00 Lakhs, the Irrigable command area is 2024 ha.

L.B.C. :- The total length of left bank canal is 28.00 Km and is completed. The discharge capacity at the head is 0.99 M.cum (35.20 cusecs). Irrigable command area is 1255 ha. Modernization under ERM is submitted.

Total Cost of the Project: a)Original Cost R 3.28 Crores. b)Revised Cost R 19.92 Crores c) Latest Estimated cost R 22.58 Crores. ERM cost: R 821.00 Lakhs Achtkat details : a)Contemplated Achtkat 3279 Ha. b)Covering districts Gulbarga & Bidar c) Covering Talukas. Basavakalyan , Humnabad, Gulbarga Tq. No. of villages benefited and extent of area 14 Nos. villages benefited for 3279 ha Land acquisition Details: Proposed Acquired Balance A – G A - G A – G a)Land acquired for dam and allied works. 974-00 974-00 Nil b) Canal and others works. 526 – 36 526 - 36 Nil c) R & R works 91 – 32 90 - 00 1 – 22 TOTAL:- 1592-28 1590.36 1 – 32 Potential details : a) Total potential to be created 3279 Ha b) Potential created to the end of march 2012 3279 Ha Financial Details : a)Latest Cost of the project R 22.58 Crores. b)Expenditure incurred upto date March 2012. R 22.58 Crores. c) Balance Cost R Nil d)Programme of Balance Cost R Nil e)Expenditure upto march 2012 R 12.57 Lakhs Grant for the year 2011-12 (2701) R 13.51 Lakhs (2701 head)

179

4. SOUDAGAR TANK PROJECT

Brief History of the project:

Soudagar Tank Project is located on Soudagar Nala near Shamnapur village Dist. Yadgir. The project was administratively approved by G.O.NO. PQD MMI /159, Bangalore dated 16.12.63 for `. 99.84 Lakhs. The project was completed in 1.9.75. A) DAM :- The project has 600 mtrs, length of earthen embankment and is completed in the year 1987. The length of the spillway is 60 mtrs, with flush escape, ungated Ogee weir. The spillway is designed for maximum discharge of 218.06 cusecs (7700 Cusecs), water is being stored in the reservoir since 1987. B) CANAL :- Only R.B.C.

The total length of Right Bank canal is 11.00 Km, and is completed. The discharge capacity at head is 0.73 cumecs (26 cusecs) to irrigate 1417 Ha. The canal section is damaged at many reaches. The modernization under AIBP/ ERM has been proposed.

The project was completed in the year 1987. The canal lining has damaged in most of the reaches and hence the canal section have become irregular and leakages observed in most reaches due to this water will not reach in the tail end. The command area in the tail end reaches of main canal and distributaries is not benefited whereas in the initial reaches the utilization of water by the farmers is beyond necessity.

Administrative approval has been accorded for the modernization proposal vide G.O.NO. WRD 95 MTZ 2007, dtd. 09-03-2010 for R397.00 Lakhs.

During 103 rd meeting of Advisory Committee held on 11-03-2010, it has been instructed to hand over the project to Minor Irrigation Department. In this regard, letter has been addressed to the Govt. vide this office letter No:5997, dtd:24-03-2010 for handing over the project to the MI Authorities. Vide GO WRD 95 MTZ 2007, dtd 26-7-2010 it was ordered to hand over the project to the MI Department. Handing over the project to the MI Department is under process.

180

15. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION CENTRAL ZONE, MUNIRABAD

1. Completed projects :- Hagaribomhanalli project, Narihalla Project, Kanaka Nala Project, Rajolibunda diversion Scheme, Vijayanagar Canals and Maskinala Project.

2. On going Projects :-

Tungabhadra Project, (Original works are completed long back. But only modernization works are being taken up.), Hirehalla Project, Singatalur Lift Irrigation Scheme and other Lift Irrigation Schemes.

2.1 TUNGABHADRA PROJECT The Tungabhadra Project comprises of across the river Tungabhadra, a tributary to river Krishna, near Mallapuram in taluk, Bellary District, with canals on both banks to provide irrigation to an extent of 3,62,715 hectares(Karnataka portion only) . This is an inter-state multipurpose project started in 1945 as a joint venture of the then Governments of Madras and Hyderabad. After reorganization of States, the project became a joint venture of Mysore (Now Karnataka) and Andhra Pradesh.

In 1945 the contruction of Tungabhadra Canals of Tungabhadra Project was started and completed in stages up to 1960. The embankments of Left bank main canal was constructed with available soil (economically). For this canal zonal section was not provided. Due to this breaches and piping (bongas) were occurring frequently.. In order to prevent the occurance of pipings (bongas) and slips and breaches occurred in Embankment reaches the, Expert committee in 1982 recommended to inner strengthen the embankment reaches. Accordingly, the inner strengthening works of embankments of LBMC was tackled during the period from 1982 to 2006 in stages.

As per the Chinival Committee report, it is proposed to take up modernization works in five years from 2006-07. Major works during the period from 2009-10 to 2012-13 was taken up with a cost of Rs 966.22 Crores.

2.1.1 The Physical and Financial progress for the period from 2009-10 to 2012-

13 is as under :-

Year Est Cost Physical progress in Km Financial in Main Canal Distributaries Progress Crores LBMC LBHL LBMC RBLLC RBHLC (Expenditure) C in Crores 2009-10 303.56 33.46 0.00 110.0 30.24 22.86 301.42 2010-11 359.48 50.74 2.15 101.47 7.72 19.00 330.55 2011-12 403.66 39.83 3.04 145.31 22.75 1.60 334.25 2012-13 Works not talked Total 1395.42 124.03 5.19 356.98 60.71 43.46 966.22

181

2.1.2 THE DETAILS OF BALANCE WORK AFTER 2012-13

Canal Physical (Km) Financial (Amount in crores) LBMC 25.06 112.91 LBHLC 6.41 1.90 Distributaries of LBMC 857.90 584.62 Distributaries of RBLLC 537.34 110.61 Distributaries of RBHLC 588.52 187.79 Total 997.83

2.1.3 AN OVER ALL VIEW OF THE TUNGABHADRA PROJECT TUNGABHADRA LEFT BANK CANAL

1. Name of Project TUNGABHADRA LEFT BANK CANAL 2. Location Left Bank of T. B. Dam 3. Year of inception 1945 4. Year of completion Completed in stages up to 1968 (Original works)

Original cost: Rs. 17.44 Crores (Sanctioned by Original and latest estimated cost Nizam Government in 1951) in Crores 5. Revised Cost: Rs. 194.40 Crores (ID 122 MTP 92 Including administrative approval Dated: 05-06-1996) no. and date/Technical Sanction. Latest cost: Rs. 302.00 Crores

Length of canal: 6. a) Main canal 226.00 km b) Distributaries 707.00 km 7. Length of ayacut roads 1150 Km 8. District benefited Raichur and Koppal Gangavathi Tq, Sidhnoor Tq, Manvi Tq, Devadurga 9. Number of village and Tq benefited & Raichur Taluk No of WUCS a) Formed 585 10. b) Registered 244 c) Handed over 46 Programme during 2011-12 (including LBMC,LBHLC and 11. Rs. 477 Lakhs distributaries of LBMC,RBLLC and RBHLC) Progress achieved during 2011-12 upto end of March 2012( including Expenditure: Rs. 83.41 Lakhs 12. LBMC,LBHLC and distributaries of LBMC,RBLLC and RBHLC)

182

2.2. HIREHALLA PROJECT

The Hirehalla Project comprises a reservoir across the Hirehalla, a tributary to the river Tungabhadra near village in Koppal Taluk of Koppal District, with canals on both banks, to provide irrigation to an extent of 8330 Ha; in Koppal Taluk. The proposed utilisation is 64.24 M.Cum; (2.27 TMC). Administrative approval to the project costing Rs. 6.35 Crores has been accorded vide G.O.No.PWD 174 MTP 73, dated: 24-5-1979 and the revised estimate for Rs.90.00 Crores was submitted to the Government for the approval. Technical Advisory Committee has cleared the estimate and the Administrative approval from the Government is awaited. However Government has directed to submit the revised estimate according to the latest cos.The revised cost of the project would be Rs 289 crores and the revised estimate is being prepared.

2.2.1. DAM AND CANALS: The Dam works of this project are completed and dedicated to the nation on 26-12-2001 by the Hon’ble chief Minister of Karnataka. The main canals (left side and right sde) of this project are completed. Out of total 64 Distributaries, 62 distributaries have been completed and 2 Distributaries are under progress.

2.2.2 Railway Crossing works : Railway crossing and national highway crossing works of Distributory No 17 of RBC is completed. The balance work in this Distributory is also completed. Water is let into the canal and irrigation to an extent of 90 hectares is achieved. It is planned to irrigate the balance area of 124 hectares in the year 2013-14.

2.2.3 Rehabilitation Works:- For rehabilitation for Mudlapur, Shirur, Muttal and villages Govt has sanctioned an amount of Rs. 5426.11 Lakhs under Govt order No: PÀAE/88 DgïEºÉZï 2010 ¨ÉAUÀ¼ÀÆgÀÄ, ¢: 27-11- 2010. Excluding the expenditure of Rs 1485.06 lakhs incurred, for revised R&R package an additional amount of Rs 3940.95 lakhs has been sanctioned. Government released Rs. 2000.00 Lakhs for rehabilitation works vide Govt order No: d¸ÀAE/ 64 /JAn¦/ 2009, ¨ÉAUÀ¼ÀÆgÀÄ,¢:06/02/2012 under head of account 4701-37-800-0-01-132(P) through Karnataka Niravari Nigam Ltd. Out of Rs.2000.00 lakhs, Rs.1809.00 lakhs has been deposited to Assistant Commissioner,Koppal for R & R works. The balance 191 lakhs grant has been utilized to take up R & R works in Shirur, Muthal, Virapur and Muddapur villages and works are under progress.

183

2.2.4. AN OVER ALL VIEW OF THE HIREHALLA PROJECT:

Name of Project Hirehalla Project Across Hirehalla and Veerpurhalla 4 Km U/s of Location Kinnal village. Year of inception 1979 Original cost: Rs. 6.35 Crores. Original and latest estimated cost in PWD 164 MTC 73 Dated 24-5-1979 Crores. Revised cost: Rs. 289.00 Crores. Including administrative approval no. (Administrative approval to be obtained from and date Government) Length of canal LB- 24.60 Km; a) Main canal RB- 25.80 Km b) Distributaries 63 Km

c) Branch canal 15 Km

d) FIC Under progress

Length of ayacut roads 65 Km

District benefitted Koppal

Number of Tq benefited 1,Koppal

No of WUCS a) Formed 7 b) Registered 3

Programme during 2012-13 Rs. 294.96 lakhs + Rs.255.00 lakhs

Progress achieved during 2012-13 upto Rs. 528.39 lakhs end of 03/2013.

2.2.5. Details of Irrigation Potential created in Ha Area in hectares Total Balance Programme Created potential Sl. Name of On full potential during during created No District development to be 2012-13 2012-13 upto created 3/2013

1. Koppal 8330 214 90 8206 214

184

1. OTHER WORKS (Rs. in Lakhs.) Expenditure from Cum. Estimate Irrigation Name of 04/2012 to Expenditure Sl. d Grant for Likely date of Potential in the 03/2013 in upto March Present Stage of Project No. Cost in 2012-13 completion Acres(contempla Project lakhs 2013 lakhs ted) in lakhs

1 2 3 4 6 7 8 9

(A)Ongoing Works

In this Project it is proposed to lift 3.75 Cusecs of water from Tungabhadra Katharak River to suppliment the tail end reaches i.e., SD 89/8/1 & 2 of Kataraki village 1 58.00 5.00 - 42.35 Completed 450 i LIS of 450.00 acres. Work has been completed and trial run is yet to be done.After trial run, water will be let into the canal.

In this project it is proposed to lift 10.85 cusecs of water from Kapagal nala to Bailmerc suppliment tail end reaches of SD-89/7/1&2. This project is proposed to irrigate 2 73.00 5.00 - 49.4 Completed 1185 1185.09 Acres of Boylmerched Village, Manvi taluk, Raichur district. The hed LIS project is completed and trial run is yet to be done. After trial run water will be let into the canal.

1300 Y (origina Scheme is proposed to irrigate 6643 Acres by lifting 60Cusecs water from l) 6643(Bellary Hagari river. The revised estimate amounting to a tune of Rs 6325 lakhs is 3 Kaggal 36.00 1.00 272.72 - 6325 district). prepared.The revised estimate along with Draft Tender Pr oject is submitted to LIS (revised Government to submit before Technical Advisory Committee for approval. )

185

Expenditure from Cum. Estimate Irrigation Name of 04/2012 to Expenditure Sl. d Grant for Likely date of Potential in the 03/2013 in upto March Present Stage of Project No. Cost in 2012-13 completion Acres(contempla Project lakhs 2013 lakhs ted) in lakhs

(B) New Projects The estimate and DPR amounting to Rs 1190.00 lakhs is approved vide Wala presently the modified estimat e for Rs 23.10 crores is prepared and submitted 4 Bellary 594.00 50.00 - - - 6,276 to Government. It was requested to Government to allocate required quantum LIS of water and take up the under Karnataka Neeravari Nigam Ltd.. Details of balancing reservoir are as mentioned below. Sl Name of the Balancing Water Storage Estimate No Reservoir and location source capacity d cost in in TMC Crores 1 Bennur Village in T.B. Gangavathi Taluk Koppal 1.80 167.42 River District Construc 2 Gaddimadi Village in T.B. tion of Gangavathi Taluk Koppal 1.10 91.00 River Balancin District 5 g - 3 Hediginal Village in - 200.00 84.95 84.95 T.B. reservoir Sindhanur Taluk Raichur 1.5 138.60 River s under District TBLBC/ 4 Chikalparvi Manvi Taluk T.B. 1.92 82.00 Pickups Raichur District River The DPR and Detailed e stimates for the above four Balancing Reservoirs submitted to Govt. for placing before the 95 th TAC held on 6/4/2010 .During the Deliberation of the meeting it was observed that the inter-state angle should be properly analysed at Govt. level and this inte rstate matters which requires the opinion in the light the proceedings being under way before Tribunal and are in the final stages. Hence the TAC felt that the issue can be deferred for the time being. Construc 6 513 90.00 90.00 501 Work is in This project is under progress and 98% of the work is completed. tion of

186

Expenditure from Cum. Estimate Irrigation Name of 04/2012 to Expenditure Sl. d Grant for Likely date of Potential in the 03/2013 in upto March Present Stage of Project No. Cost in 2012-13 completion Acres(contempla Project lakhs 2013 lakhs ted) in lakhs

Daroji progress tank waste weir. Moderni There are 16 Vijayanagar channels have been constructed during Vijayanagar stion of DPR is yet to Empire are coming under this zone. Which irrigates 11,222 Ha in Bellary, 7 Vijayana 25500 - - - Koppal and Raichur District. be approved gar The detailed project report is prepared and submitted to the Government to Canals obtain clearance from CWC. Mushtoo r Block In the year 2007-08 the work of Mustoor block 1 and 2 were taken up on tender 8 1,2 and 68.00 20.00 4.5 30.50 basis. As of now financial progress of Rs. 26.00 lakh has been achieved. Ulenoor Raising main is completed and pumping machine is to be installed. LIS Construc tion of RCC Bridge across Tungabh Instructions have been given to carry out the survey work from the 2012-13 9 adra 75.00 - - - grant allocated . River near Shivpur Village, Koppal Tq.

187

Expenditure from Cum. Estimate Irrigation Name of 04/2012 to Expenditure Sl. d Grant for Likely date of Potential in the 03/2013 in upto March Present Stage of Project No. Cost in 2012-13 completion Acres(contempla Project lakhs 2013 lakhs ted) in lakhs

Construc tion of bridge cum barrage acorss This work is handed over to RDPR. 10 - - - - Hirehalla near Yatnatti Village, Koppal Tq.

188

16. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER TUNGA PROJECT ZONE, SHIMOGA

Bhadra Project Circle is functioning at B.R.Project in Bhadravathi taluk, since 07.11.1969. This Circle is under the control of the Engineer-in-Chief, KNNL, Upper Tunga Project Zone, Shimoga Three Divisions, namely Executive Engineer, No.3, Canal Division Malebennur; No.4 BRLBC Division, Bhadravathi & No.5 Canal Division, Davanagere and fifteen Sub-Divisions comes under the Jurisdiction of this Circle. The following Projects come under the Jurisdiction of this Circle.

I. Major Irrigation Project 1) Vanivilas Sagar Project

II. Medium Irrigation Project 1) Gondi Anicut Project {Bhadra Anicut} 2) Jambadahalla Reservoir Project 3) Feeder Canal to Ranikere Tank Project 4) Gayathri Reservoir Project 5) Ambligola Reservoir Project 6) Thimmapura Lift Irrigation Scheme 7) Anjanapura Project 8) Dharma Project 9) Tunga Anicut Project 10) Kaduvinabylu Project 11) D.B.Kere Pickup 12) Harihara Bhairanapada LIS

III. TANKS 1) Sulekere tank (Shanti Sagar). 2) Bheemasamudra tank 3) tank 4) Madaga Masur tank

189

VANI VILASA SAGAR PROJECT

Vanivilasa Sagar Dam has been constructed across near Marikanive of Hiriyur Taluk. The construction of dam was started during 1898 and completed during 1907. The cost of the project was Rs. 45.00 Lakhs. The project has a reservoir with a high level Canal, under this pickup as been constructed at about 8.00 Km near Katrikena halla. Irrigation facility is provided through left bank and right bank canals. An Atchakat of 12,135 Ha has been developed under this project. The repairs and improvements works of canals structures and providing lining at the damaged portions have completed under National Water Management Programme. Fixing of measuring devises and other works are also done under this Project. Now this project is under maintenance.

Modernization of Vani Vilas Sagar canal system and Improvements to Travelers Bungalow at V.V.Puram.

During 2012-13 a grant of Rs 100.00 Lakhs is allotted for Modernization of Vani Vilas Sagar Project canal system and Improvements to Travelers Bungalow at V.V.Puram. Accordingly the works taken up during last year and fresh works are under progress. Expenditure incurred during 2012-13 is Rs 50.38 Lakhs. For modernization canal system of this project an update expenditure of Rs 634.00 Lakhs has been incurred to end of March 2012. During 2012-13 a grant allotted under Head of Account 2700-M&MI is Rs 68.91 Lakhs. Expenditure incurred during 2012-13 is Rs 65.16 Lakhs.

Development of Micro Irrigation facilities to 1000 Ha of Atchakat under Vani Vilas Sagar Project.

During 2012-13 a grant of Rs 100.00 Lakhs is allotted for Development of Micro Irrigation facilities to 1000 ha of Atchakat under Vani Vilas Sagar Project. It is reported by the Executive Engineer that the water from Vani Vilas Sagar is being released to the Atchakat for 25 days two times in a year only for standing Crop (garden) since there is scarcity of water in the reservoir. But for effective implementation of Micro Irrigation facilities water is to be released continuously in the canal system. NETAFIM Irrigation India Pvt Ltd, Company has visited the project on 24.04.2012 and expressed their opined that I it is doubtful about success of Micro Irrigation facilities to 1000 ha of Atchakat under Vani Vilas Sagar Project. However the Chief Engineer has instructed to submit the DPR for implementation of Micro Irrigation facilities to 1000 ha of Atchakat under Vani Vilas Sagar Project, since it is a Pilot Project. The DPR is yet to be submitted by the Executive Engineer.

190

CONSTRUCTION BRIDGE ACROSS BHADRA RIVER NEAR GONDI ANICUT It is proposed to construct Bridge across Bhadra river near Gondi Anicut in order to establish road way communication between Lakkavalli hobli of Tarikere taluk and Bhadravati. The local elected leaders of this region have approached the Government and requested to construct this Bridge in order to create facilities for the Atchakat farmers for transportation of sugar cane to Bhadravati sugar factory. Rs.250.00 Lakhs is allotted during 2012-13 under Head of Account 4701. The Revised estimate along with compliance to the observation of 90 th TAC amounting to Rs.748.00 Lakhs has been placed before 101 st T.A.C meeting held on 18.07.2012 for clearance. The Estimate is yet to be cleared. An expenditure of Rs 2.49 Lakhs is incurred during the year 2012-13 for survey works.

JAMBADAHALLA RESERVOIR PROJECT This is an medium irrigation project, situated across Jambadahalla reservoir near Duglapura village, Tarikere Taluk of Chickamagalur district. The project was contemplated to provide irrigation to about 6000 acres. But due to scanty of flow in stream only 2799 acres of land is only irrigated to supplement the irrigation demand under this project. It is proposed to divert water from Hodirayanahalla reservoir (A adjacent valley to Jambadahalla stream) costing 248.00 Lakhs. The above said Scheme has been got administrative approval by the Government dated: 10.08.1987 for Rs.248.00 Lakhs. About 12.98 Ha. land comes under the jurisdiction of forestland & Clearance has been obtained. During 2012-13 no Grant has been allotted from nigam under Head of Account 2701. The grant allotted during 2012-13 in budget is Rs.9.90 Lakhs under 2701 and expenditure incurred during the year 2012-13 is Rs. 9.40 Lakhs.

HODIRAYANAHALLA DIVERSION SCHEME Jambadahalla Reservoir is located near Duglapura village, Tarikere Taluk of Chickamagalur district. This project was contemplated to provide irrigation to 2428 Ha. But due to less flow only 1133 Ha. Land under right bank is being irrigated. Remaining 1295 Ha a tank has been planned to irrigate by diverting supplement water from Hodirayanahalla an adjacent valley to Jambadahalla. In addition to this 243 Ha. Land will also be benefited by this scheme. The above said Hodirayanahalla diversion Scheme has been got administrative approval by the Government dated: 10.08.1987 for Rs.248.00 Lakhs. About 12.98 Ha land comes under the jurisdiction of forestland & Clearance has been obtained by Central Forest & Environment Ministry. During 2011-12 it is instructed by the Government to take up this work through Karnataka Neeravari Nigam. The Estimate amounting to Rs 33.83 Crores has been sanctioned by the Chief Engineer vide CER No: 694/12-13 Dt 19.01.2013 after obtaining clearance from TSC of Nigam. Further the DTS of the said work has been placed in 114 th TSC of Nigam. TSC has raised certain observation on DTS. The compliance to the observation has been submitted to TSC. The work is to be taken-up for execution after obtaining clearance to DTS fro TSC of Nigam.

191

During 2012-13 Rs. 100.00 Lakhs grant is allocated under the Head of account 4701. An expenditure of Rs 29.59 Lakhs has been incurred during 2012- 13 towards survey work. The upto date expenditure incurred on this project for preliminary survey and investigation including payment made to Forest Department for release of forest land till the end of March 2013 is Rs 154.37 Lakhs.

GAYATHRI RESERVOIR PROJECT

Gayathri Reservoir Project has been constructed between 1952-53. The maintenance of this project has been handed over by the Minor Irrigation during 1997 to this circle. This reservoir has been constructed across Suvarnamukhi river near Kudalahalli village, Hiriyur taluk, Chitradurga District. The original estimate cost of the project was Rs.39.85 Lakhs. The Irrigation potential created under this project was 2305 Ha. of land. This project is under maintenance. During 2012-13 a grant of Rs 100.00 Lakhs is allotted for Modernisation of Gayathri Project canal system. The spill over works and fresh works has been taken up during 2012-13. Expenditure incurred during 2012-13 is Rs 62.77 Lakhs. For modernization canal system of this project an up date expenditure of Rs 401.03 Lakhs has been incurred to end of March 2013. The Grant allotted during 2012-13 under Head of Account 2701 is Rs. 23.42 Lakhs. The expenditure incurred during 2012-13 is Rs 23.42 Lakhs.

Dharma Project Dharma reservoir is constructed across Dharma River in Uttara-kannada District, Mundagod taluk, near Yamanalli village, during 1994. The storage capacity of the tank is 0.814 TMC. Under this project, the upstream canal length is 1.80 KM. On downstream of this project at 8.00 KM, Shrungeri pickup is constructed. The left bank canal length of this pickup is 6.00 KM and right bank canal length is 29.40Km. Through these canals water feeded to irrigate about 7692 Ha. of land. Now this project is under maintenance. During 2012-13 a grant of Rs 100.00 is allotted for Modernization of Dharma Project canal system. The spill over works and fresh works has been taken up during 2012-13. Expenditure incurred during 2012-13 is Rs 153.31 Lakhs. For modernization canal system of this project an update expenditure of Rs 1430.35 Lakhs has been incurred to end of March 2013. It is instructed by the District in charge Minister to take up the balance Modernization works under AIBP Assistance. The detailed report along with compliance to the TAC observation has been submitted to higher authorities for according approval. Hence the balance Modernization works has to be taken up for execution after getting clearance fro TAC as well as AIBP authorities under AIBP Assistance. The Grant allotted during 2012-13 under Head of Account 2701 is Rs. 25.04 Lakhs. The expenditure incurred during 2012-13 is Rs 25.03 Lakhs.

192

KADUVINABYLU LIFT IRRIGATION SCHEME

Kaduvinabylu Lift irrigation Scheme located in Chickamagalur District of N.R.Pura taluk. The estimated cost of this project is Rs. 690.00 Lakhs Kaduvinabylu Lift irrigation Project has been administratively approved by the State Government vide G.O.No.WRD 223 MMB 2004 Bangalore dated 10.5.2005 for Rs. 690.00 Lakhs. The Master plan committee is allocated 0.21 TMC of water to this project under Krishna scheme- A. Earlier project report which is submitted for obtaining administratively approval is prepared for 0.44 TMC Utilization. The Chief Engineer, KNNL, Upper Tunga Project Zone, Shimoga has given instructions to prepare detailed project report as per the allocation of water by the master plan committee vide letter No.CE/KNNL/ UTPZ/TA/3/PB-12 KBLIS/2005/613 dated. 18.6.2005. As per the instructions the project report amounting to Rs.690.00 Lakhs was prepared for 0.21 TMC Utilization. The estimate amounting to Rs.690.00 Lakhs was technically sanctioned by the Chief Engineer, KNNL, Upper Tunga Project Zone Shimoga Vide CER No.83/2005-06 dated. 29.9.2005. The expenditure incurred on this project for preliminary survey, investigation and for formation of approach road is Rs 19.01 Lakhs. The above work has been re-entrusted to Arun Engineering private Ltd, Bangalore on turn key tender basis vide agreement dated 25.11.2009 amounting to Rs 1254.69 Lakhs. The construction of Jack well and GLSR is almost completed. Intake channel is under progress. Rising main pipes are supplied and erected. Motor are supplied. Works are under progress. During 2012-13 government has allotted the grant of Rs 200.00 Lakhs under Head of account 4701. Expenditure incurred during 2012-13 is Rs 133.15 Lakhs. An update expenditure of Rs 603.93 Lakhs has been incurred to end of March 2013.

THIMMAPURA LIFT IRRIGATION SCHEME

The above scheme envisages to create an irrigation facility to an extent of 4176 Acres. (1691 Ha.) of land coming under the villages of Kanavelli, Bharadi, Kurugunda and Basapura of Haveri taluk, This includes 159.00 Acres of suffering Atchakat under Kannavalli tank. The MIPC Board has cleared the estimate of Rs.2063.00 Lakhs. The revised estimate amounting to Rs.2313.00 Lakhs has submitted to the Government for administrative approval. During 2012-13 budget grant Rs.165.00 Lakhs has been allotted. The proposal to take up this project under NABARD has been submitted to the Government for obtaining approval. No expenditure is incurred during 2012-13.

D.B.KERE PICK-UP PROJECT

D.B.Kere Project is in Harihar Taluk, Davanagere district. D.B.Kere Project was completed in 1985. The Area irrigated under D.B.kere project is 4280 Hectares. Under the above project Right bank canal runs for a length of 26.20 Kms and Left Bank canals runs for a length of 33.00 Kms. At present the seepage water of Bhadra Canals supplements the Atchakat. Errection of Automatic god-bole gates on the spill-way of D.B.Kere Pick-up :

193

The grant released under Head of Account 4701 during 2012-13 is Rs. 100.00 Lakhs for Errection of God-bole gates on the spill-way of the pick-up. The work has been taken up on Tender. works are under progress. Expenditure incurred during 2012-13 is Rs 200.00Lakhs. An update expenditure of Rs 199.98 Lakhs has been incurred to end of March 2013.

RANIKERE FEEDER CANAL

The Government has accorded administrative approval for Ranikere Feeder Canal project Vide G.O.No.WRD. PWD 31 BGC 77/11.11.1997 for Rs. 249.00 Lakhs. The revised estimated cost of this project is Rs.896.00 Lakhs. This project is proposed to take up in two stages. In I stage it is proposed to regularize the water supply for crops already created to an extent of 390 Ha. In II stage it is being proposed to create on additional irrigation potential of 3827 Ha. The II stage work has to be taken up after finalization of yield of water. The expenditure incurred for this project to end of 3/2006 is Rs.939.03 Lakhs. This project is in maintenance stage. The Grant allotted during 2012-13 under Head of Account 2701 is Rs. 1.78 Lakhs. Expenditure incurred during 2012-13 is Rs 1.78 Lakhs.

MODERNIZATION AND RENOVATION RANIKERE FEEDER CANAL . During 2012-13 government has allotted the grant of Rs 600.00 Lakhs under Head of account 4701. The Government has accorded Administrative approval to the DPR of the said project amounting to Rs 1600.00 Lakhs vide Govt Ltr No WRD 80: MMB 2010, Bangalore Dt 28.06.2012 and instructed to take up this work under Karnataka Neeravari Nigam. The revised-estimate amounting to Rs 1990.00 Lakhs has been submitted to nigam and placed before TSC of nigam. The estimate has been submitted to Nigam board for clearance. Hence the work has to be taken up for execution after getting clearance from Nigam board. No expenditure has been incurred during 2012-13. An update expenditure of Rs 3.66 Lakhs has been incurred to end of March 2013 for survey works.

HARIHARA-BYRANAPADA LIFT IRRIGATION SCHEME

Under this scheme it is proposed to provide irrigation facilities to the suffering Atchakat of tale end of Malebennur branch canal. It is proposed to establish the lift irrigation scheme on the right bank of Tunga Bhadra River. During 2012-13 government has allotted an grant of Rs 100.00 Lakhs. Administrative approval for the detailed project report of this scheme amounting to Rs 43.73 crores has been obtained from the Government Vide their Ltr No: WRD 14 :MMB 2012 Dt 10.01.2013. Hence the work has to be taken up for execution after getting clearance from TAC.

194

CONSTRUCTION OF LINK CANAL FROM HEBBEHALLA TO MADAGADAKERE The farmers, MLAs and areca Co-operative societies of Kadur, Birur and Tarikere Taluk have represented the Government to divert water from Hebbehalla which is sub-tributary to Somavahine a tributary to Bhadra river to Madadaga Kere in order stabilize the Atchakat as the rainfall has become scanty in recent years resulting in reduction of storage of water. The Government has ordered to investigate the project. The preliminary project report (PIR) for Rs.69.73 Lakhs was prepared by the superintending engineer, Major Irrigation Investigation Circle Mysore.Further superintending engineer, Major Irrigation Investigation Circle Mysore. has prepared revised estimate of the project amounting to Rs 140.00 Crores through private survey consultancies, and obtained formal approval by the government vide Lr No WRD 61 MMB 2010 Dt 29.11.2010. The above project has been transferred to major irrigation department from investigation circle, Mysore. The designed total water requirement for this project is 1.538 TMC. The utilization of 0.50 TMC is available. The water resources development organization, Bangalore in their letter Dt 12.05.2010 has stated that the advisory committee of Krishna water dispute Tribunal has submitted the proposal to the tribunal to allocate 1.50TMC of water to this project out of 23 TMC of water to be reallocated to the state under Indira Pollavaram project of Andra Pradesh. The project details have been obtained from the office of the Executive Engineer, Major Investigation Division, Mysore and to take necessary action to implement the project. During 2012-13 government has allotted a grant of Rs 100.00 Lakhs. The project proposal obtained from Major Investigation Division is a line estimate. Hence preparation of detailed project report has been entrusted to private survey consultancy through on tender basis. Preparation of detailed project report is under progress. No expenditure is incurred during 2012-13.

BHEEMASAMUDRA TANK Bheemasamudra tank has been constructed 500 years ago in Chitradurga Taluk and district near Bheemasamudra village. The storage capacity of the tank is 0.905 TMC. The Irrigation potential created under this tank is 1235 Ha. (3050 Acres). The tank has left Bank canal and right Bank canal and distributary system. The total length of canal is 68 Kms. At present the Bheemasamudra tank is filled up with silt since the tank is 500 year old. Due to this storage capacity of tank is reduced to 0.18 TMC. The catchment area of tank has scanty rainfall, due to this storage capacity of the tank is reduced. In order to increase the storage capacity of this tank it is proposed to construct feeder canal from Bettadanagenahalli and Jogerahalla duly constructing pickup. This works has been entrusted on tender basis. No Grant is released for this tank under 2701 H/A during 2012-13.

195

IMPROVEMENTS TO BHEEMASAMUDRA TANK : The Restoration and renovation of this tank is taken up under AIBP grant of central government. The improvement of this tank under Prime Minister Farmers Sucide Package for Rs 400.00 Lakhs was got administratively approved by the Govt on 19.06.2007. The restoration and renovation of this tank is taken up on tender. So for about 1.80Km of lining works is completed in canal No1, 4 Nos of cross drainage work is completed and 147 m chute channel is completed. Rs.100.00 Lakhs grant is allotted during 2012-13 under 4701 for restoration and renovation of Bheemasamudra tank. The expenditure incurred during the year 2012-13 is Rs 45.46 Lakhs. An update expenditure of Rs 231.49 Lakhs has been incurred to end of March 2013.

CONSTRUCTION OF FEEDER CANAL FROM ANNEHALLU TANK TO BHEEMASAMUDRA TANK: No grant is allotted during 2012-13 under 4701 for this work. The works of construction of feeder canal from Annehal tank to Bheemasamudra tank has been taken up on tender basis. Due to the delay in process of land acquisition, works are yet to be resumed. No expenditure has been incurred on this project during the year 2012-13. Upto date expenditure of Rs 67.88 Lakhs has been incurred on this project toward land acquisition to the end of 03/2013.

MODERNISATION OF SHANTISAGARA TANK CANALS

The canals coming under Tank are scoured heavily and lost their shape, there by it is not possible to maintain the full supply depth in the canals resulting very difficult to push the water to the tail end Atchakat. Hence it is proposed to provide concrete lining to the bed and sides. The water is lost due to the leakages in the existing canal structures like pipe outlets, culverts, Cattle ramps, inlets and hence it is proposed to strengthen the existing structures by repairs and reconstruction. The works are already taken up and almost completed. During 2012-13 the Government allotted a grant of Rs 100.00 Lakhs. Accordingly the 62 works taken up during the year 2007-08 are completed. The repair and improvement works of Babanayakana vaddu has been proposed to taken up for execution. Expenditure incurred during 2012-13 is Rs 0.93 Lakhs. For modernization canal system of this tank an update expenditure of Rs 875.72 Lakhs has been incurred to end of March 2013.

Improvements to Ramberavaddu Pick-up in down stream of Shanti Sagar Tank. During 2012-13 the Government allotted a grant of Rs 35.00 Lakhs. The work of Improvements to Ramberavaddu Pick-up in down stream of Shanti Sagar Tank has been taken up for execution with an estimated cost of Rs 82.00 Lakhs. The said work is completed. Expenditure incurred during 2012-13 is Rs 72.15 Lakhs. For modernization canal system of this tank an update expenditure of Rs 72.15 Lakhs has been incurred to end of March 2013.

196

ASUNDI KERE

Asundi tank comes under Haveri District of Ranebennur Taluk of Asundi village is constructed. The tank has LBC of length 2.80 KM and RBC 1.20 KM of length and irrigated of 182 Ha. of Land under this project. During 2012-13 a grant of Rs 100.00 Lakhs is allotted for modernization of Asundi tank. Modernisation of Asundi tank works has been taken up on tender basis. Expenditure incurred during 2012-13 is Rs 66.00 Lakhs. For modernization canal system of this project an update expenditure of Rs 215.17 Lakhs has been incurred to end of March 2013.

MADAGA –MASUR TANK Madaga Masur Tank is located in Haveri District in Hirekerur Taluk. The above tank constructed across Kumudvathi river. This tank very older 2855 Ha. of Land Irrigated under this tank. This tank has LBC of 14.00 KM length and RBC of 37.00 KM of Length. This tank is in maintenance stage, and improvements and repairs to embankment, canal works, and removal of silt have to be taken up. Under 4701 for improvements of this tank. Accordingly the programme is got approved and works are taken up. The expenditure incurred upto December 2006 is Rs.7.89.Lakhs. During 2012-13 a grant of Rs 100.00 Lakhs is allotted for modernisation Madaga Masur Tank canal system. Accordingly the spillover works and fresh works has been taken up during the year 2012-13. Expenditure incurred during 2012-13 is Rs 100.00 Lakhs. For modernization canal system of this project an update expenditure of Rs 813.75 Lakhs has been incurred to end of March 2013. During 2012-13 No grant is allotted under Head of Account 2701-M&MI. It is instructed by the District in charge Minister to take up the balance Modernization works under AIBP Assistance. The detailed report along with compliance to the TAC observation has been submitted to higher authorities for according approval. Hence the balance Modernization works has to be taken up for execution after getting clearance fro TAC as well as AIBP authorities under AIBP Assistance.

CONSTRUCTION OF SOPANUM TO THE VEDAVATHI RIVER AT KELLODE VILLAGE NEAR HOSADURGA TALUK

Construction of Sopanum to the Vedavathi River at Kellode village near Hosadurga taluk. Taken up during 2007-08 is under progress. During 2012-13 a grant of Rs 25.00 Lakhs is allotted for this work. Accordingly the works taken up during the year 2007-08 are under progress. Further the additional works has been taken up as per the instructions of WRD Minister vide Ltr No 346 Dt 27.12.2011. The estimate for additional works amounting to Rs 75.00 Lakhs has been sanctioned vide central office CER No 365/2012-13 Dt 03.11.2012. These works have been taken up on tender basis. The works are under progress. During 2012-13 a grant of Rs 25.00 Lakhs is allotted. Expenditure incurred during 2012-13 is Rs 24.11 Lakhs. An update expenditure of Rs 56.92 Lakhs has been incurred to end of March 2013.

197

SHIFTING OF AND VADDINAHALLI VILLAGES

Earlier, the villages Lingadahalli and Vaddinahalli were affected by the seepage due to the construction of Davanagere Branch Canal. Both the villages are shifted. The government has allotted grant of Rs 10.00 Lakhs for the year 2012-13. Developmental works taken up in Lingadahalli and Vaddinahalli village has been completed. Expenditure incurred during 2012-13 is Rs 9.08 Lakhs. For this work an update expenditure of Rs 150.78 Lakhs has been incurred to end of March 2013.

CONSTRUCTION OF BRIDGE NEAR VATTIGENAHALLI VILLAGE IN HARIHARA TALUK There is a road of length 4.00 km between Sarathi and Vattigenahalli villages in Harihara taluk. This road runs in the Bhadra command and connects the Major district Road and State Highway. The Karlahalla is passing across this road near Sarathi village. It is very essential to construct a bridge across this halla for facilitating the farmers for their agricultural activities. The detailed estimate has been prepared amounting to Rs 155.00 Lakhs and submitted for obtaining technical sanction.The government has allotted grant of Rs 10.00 for the year 2012-13 . No expenditure has been incurred during the year 2012-13.

CONSTRUCTION OF SOPANUM TO THE LEFT BANK OF TUNGABHADRA RIVER IN 10 VILLAGES OF HONNALI TALUK. The government has allotted grant of Rs 65.00 Lakhs for this work during the year 2012-13. Construction of 12 Nos of Sopanum to the left bank of Tunga Bhadra river has been taken up for execution with an estimated cost of Rs 165.00 Lakhs. Expenditure incurred during 2012-13 is Rs 50.00 Lakhs. For this work an update expenditure of Rs 50.00 Lakhs has been incurred to end of March 2013.

CONSTRUCTION OF SOPANUM TO THE LEFT BANK OF BHADRA RIVER IN BHADRAVATHI TALUK. Sri Ragavendra swamy mutt (Nanjanagud branch), which situated on the right side bank of the Bhadra river was constructed in 1996. Due to heavy floods in the river during rainy seasons the right side bank of the Bhadra river at temple and Mutt portion was scoured and slipped away which would result in severe damage to the building and foundation of Mutt. To avoid further damage and collapse of the riverbank, building, and temple it was very essential to construct protective retaining wall on right side bank of Bhadra River at the damaged portion of mutt and temple and also to construct an washing ghat adjacent to river and protective wall. The work has been entrusted at an estimated cost of Rs 20.00 Lakhs for 2007-08 under 4701 and the work is completed . The government has allotted grant of Rs 10.00 for the year 2012-13 , for this grant protection works adjacent to the Sopanum is taken up for execution and completed . Expenditure incurred during 2012-13 is Rs 10.82 Lakhs. For this work an update expenditure of Rs 10.82 Lakhs has been incurred to end of March 2013.

198

CONSTRUCTION OF BRIDGE ACROSS TUNGA RIVER NEAR MATTUR HASAHALLI IN SHIMOGA TALUK . The government has allotted grant of Rs 50.00 for the year 2012-13. The revised estimate of this work amounting to Rs 492.00 Lakhs has been sanctioned vide central office CER No 699/2012-13 Dt 19.01.2013. The works has to be taken up for execution after obtaining approval to DTS of this work from competent authority. No expenditure has been incurred during 2012-13.

PROTECTION WORKS TO ESCAPE SLUICE HALLA OF ESCAPE SLUICE AT 24.25 KM OF TUNGA RIGHT BANK CANAL.

The government has allotted grant of Rs 10.00 for the year 2012-13. The work taken up during 2010-11 is almost completed. Expenditure incurred during 2012-13 is Rs 131.60Lakhs. For this work an update expenditure of Rs 238.32 Lakhs has been incurred to end of March 2013.

CONSTRUCTION OF SOPANUM AT CHIKKAKUDLI TO THE LEFT BANK OF BHADRA RIVER IN SHIMOGA TALUK. The government has allotted grant of Rs 10.00 for the year 2012-13. The work taken up during 2011-12 is completed. Expenditure incurred during 2012- 13 is Rs 9.82 Lakhs. For this work an update expenditure of Rs 9.82 Lakhs has been incurred to end of March 2013.

CONSTRUCTION OF IRRIGATION CANAL ON DOWN STREAM OF BALAGERE KATTE TANK IN SHIKARIPURA TALUK.

The government has allotted grant of Rs 25.00 for the year 2012-13. The work taken up during 2011-12 is completed. Expenditure incurred during 2012- 13 is Rs 23.89 Lakhs. For this work an update expenditure of Rs 23.89 Lakhs has been incurred to end of March 2013.

199

17. COMMAND AREA DEVELOPMENT PROGRAMME

Agriculture is the backbone of Indian Economy and it is the pillar of the Economic development. At the commencement of the Fifth Five Year Plan (1974- 80), in pursuance of the policy of the Government of India, the Command Area Development Programme was launched in the State for integrated and comprehensive development of the Command Areas of Major and Medium Irrigation Projects. As per the objectives laid down by the National Commission on Irrigation, 1971 and the National Commission on Agriculture, 1976, the CADP ensures rapid and optimum utilization of Irrigation Potential created under Major and Medium Irrigation Projects thereby increasing the agriculture production as also reducing the gap between the potential area created and the actual area utilised.

THE OBJECTIVES Irrigation Management is a multi-disciplinary activity involving major department like Irrigation, Agriculture, Cooperation and other organization engaged in training and research activities. Against this perspective, CADA was constituted in the year 1970 to work as a catalyst between the various organizations to reduce the gap between irrigation potential created and utilized, to increase production per unit of water and land, to reduce the loss of irrigation water in the conveyance system, to improve its efficiency at the farm level and to ensure equitable distribution of water. The objectives of the CADA, as envisaged under section 10 of the Karnataka Command Areas Development (K.C.A.D.) Act 1980, are listed below:

To formulate and implement schemes for the Comprehensive Development of the Command Area;

To prevent land erosion and water logging;

To improve soil fertility and regulation of cropping pattern;

To ensure the efficient maintenance of Field channels and Field Drains by the Farmers within the Command Area;

Localisation and de-localisation of lands for various crops;

Ensuring supply of all inputs and services; 200

Promotion and setting up of rural growth centres for integrated development of the Command Area;

Development of marketing, processing and storage facilities and adequate communication system;

Arranging for credit facilities to the farmers and artisans;

Organizing agricultural Co-operatives and Associations;

Construction of Field channels and connected drains;

To borrow and lend money necessary for the due discharge of its functions;

Conjunctive use of surface and ground water;

To determine the payment of compensation as provided in sub section [4] of section 12 of KCAD Act 1980;

To setup agricultural demonstrations farms and promote extension activities; and

To execute such other acts, consistent with the provisions of this Act.

The Six CADA’S that are established in Karnataka are:

 Malaprabha and Ghataprabha Projects, Belgaum

 Tungabhadra project, Munirabad

 Upper Krishna projects, Bheemarayanagudi

 Cauvery basin projects, Mysore

 Bhadra project, Shimoga

 Irrigation Project Zone, Gulbarga

201

BRIEF DETAILS OF CADA

Sl. Name of CADA with Year of Irrigation Districts No. headquarters Starting Projects covered

Malaprabha and Malaprabha & Belgaum, 1 Ghataprabha 1974 Dharwad, Projects, Belgaum Ghataprabha Bagalkot, Gadag Tungabhadra 1974 Tungabhadra, Bellary, Raichur 2 Project, Munirabad 12.11.1979 Hirehalla, Maskinala & Koppal.

Upper Krishna 1977 Gulbarga, Projects, Upper Krishna Bijapur, Raichur 3 Bheemarayanagudi 11-12-1979 & Bagalkot. Kabini, Harangi, Hemavathy, KRS. , Mysore, Kodagu, Nugu, Taraka, Gundal, Chamarajnagar, Cauvery Basin 1974 4 Votehole, Hassan, Mandya, Projects, Mysore 1.3.1974 Marconahally, Tumkur, Manchanabele, Kanva Bangalore(Rural) and Byramangala. Shimoga, 5 Bhadra Reservoir UTP, Tunga, Bhadra & Chikkamagalore, 1979 Project, Shimoga Gondi Davangere. Haveri Chandrampalli, Hattikuni, Soudhagar, Upper Mullamari, Gulbarga, Bidar, Irrigation Project Amarja, Bennethora, 6 2000 Yadgir, Bagalkot Zone, Gulbarga Bhima lift, and Bijapura Gondorinala, Kagna, Karanja, Chulkinala, LMP,

202

TUNGABHADRA PROJECT, MUNIRABAD

Command Area Development Authority , Tungabhadra project, Munirabad, came into existence during 1974-75. During 2012-13, the budget allocation is R10023.00 lakhs (under head 2705) & 784.15 lakhs (under head 4705) out of which total expenditure of R4758.43 lakhs & R588.10 lakhs respectively have been incurred. Programme for the year 2013-14 is R96.41 crores.

MALAPRABHA AND GHATAPRABHA PROJECTS, BELGAUM

Command Area Development Authority , Malaprabha and Ghataprabha projects, Belgaum, came into existence during 1974-75. During 2012-13, the budget allocation is R18505.00 lakhs (under head 2705) & 607.15 lakhs (under head 4705) out of which total expenditure of R4403.94 lakhs & 101.21 lakhs respectively have been incurred. Programme for the year 2013-14 is R151.02 crores.

CAUVERY BASIN PROJECTS, MYSORE Command Area Development Authority , Cauvery basin projects, Mysore, came into existence during 1974-75. During 2012-13, the budget allocation is R4058.00 lakhs (under head 2705) & 2145.06 lakhs (under head 4705) out of which total expenditure of R3915.68 lakhs & R709.15 lakhs respectively have been incurred. Programme for the year 2013-14 is R66.05 crores.

UPPER KRISHNA PROJECTS, BHEEMARAYANAGUDI

Command Area Development Authority, Upper Krishna projects, Bheemarayanagudi, has come into force since 11-12-1979. During 2012-13, the budget allocation is R11467.86 lakhs (under head 2705) & 1225.67 lakhs (under head 4705) out of which total expenditure of R3480.12 lakhs & R135.91 lakhs respectively have been incurred. Programme for the year 2013-14 is R116.39 crores.

BHADRA PROJECT, SHIMOGA

Command Area Development Authority , Bhadra project, Shimoga, came into existence during 1979. During 2012-13, the budget allocation is R5785.15 lakhs (under head 2705) & 956.97 lakhs (under head 4705) out of which total expenditure of R3848.60 lakhs & R670.62 lakhs respectively have been incurred. Programme for the year 2013-14 is R86.25 crores.

203

IRRIGATION PROJECT ZONE, GULBARGA

Command Area Development Authority, Irrigation Project Zone, Gulbarga, came into existence during 2000-01.

During 2012-13, the budget allocation is R4233.85 lakhs (under head 2705) & 1781.00 lakhs (under head 4705) out of which total expenditure of R583.20 lakhs & R99.75 lakhs respectively have been incurred.

Programme for the year 2013-14 is R64.54 crores.

The details of the Physical programme & Progress and Financial Programme & progress for the year 2012-13 up to the end of 3/2013.

204

Financial and Physical Programme and Progress under CADA and WALMI for the Year 2012-13 (Physical In Ha) (RIn Lakhs) Revised Cumulative Sl. Annual CADA Unit Annual No Target Target Progress % A) Central Sector Schemes 1 Direction & Administration Approved projects

CADA Fin 2482.00 2512.00 1924.14 77

KBJNL Fin 1205 1205 1066.45 89

Other than approved Fin 350.00 350.00 299.14 85 projects 2 Field Irrigation Channel Approved projects

CADA Fin 12295.00 12189.00 3898.14 32

Phy:Ha 81899 81192 28372 35

KNNL Fin 2275.51 2275.51 484.52 21

Phy:Ha 15203.39 15203.39 3964.59 195

Other than approved projects

CADA Fin 708.00 708.00 505.52 71

Phy:Ha 6440 6440 5479 85

KNNL Fin 5290.00 5290.00 1359.03 26

Phy:Ha 58345.16 58345.16 562.89 1

CNNL Fin 2892.72 2892.72 1160.28 40

Phy:Ha 36940.41 36941.41 13728.06 37

3 Survey(Topographical soil & other) Fin 715.00 715.00 4.44 1 Approved projects Phy:Ha 117482 117482 3004.23 3

Other than approved Fin 300.00 300.00 212.40 71

projects Phy:Ha 6000 6000 6000 100

4 Field Drainage Channel Approved projects Fin 9252.30 9444.54 5125.87 54

Phy:Ha 231308 236114 191217 81

Other than approved Fin 135 135 81.42 60

projects Phy:Ha 3375 3375 2035 60

5 Adoptive Trials/ Demonstration Fin 219.00 182.10 181.09 99 Approved projects Phy:No 6500 5270 5367 102 Other than approved Fin 5.00 5.00 4.93 99 projects Phy:No 100 100 99 99 6 Correction of System deficiencies Fin 1596.20 1596.20 15.32 1 Approved projects Phy:No 26603 26603 255 1 Other than approved 0 projects Fin 0 100 0 Phy:No 0 1667 0 0

7 Training

Approved projects Fin 616.00 461.29 272.55 59

205

Phy:No. 27366 22209 50356 227

Other than approved Fin 38.00 38.00 34.53 91

projects Phy:No. 7455.00 7455.00 7759.00 104

Farmers' 8 Participation Fin 1000.00 917.25 428.19 47 Approved projects Phy:Ha 103333 94139 49373 52

Other than approved Fin 118.00 75.00 74.52 99

projects Phy:Ha 10500 10500 8064 77

9 Land Reclamation

Fin 19035.00 19141.00 4121.40 22 Approved projects Phy:Ha 68822.50 69087.50 20150 29

Other than approved Fin 1640.65 2068.65 1641.62 79

projects Phy:Ha 6046 10762 6914 64

1 Monitoring & 0 Evaluation Fin 12.00 12.00 6.90 58 Approved projects Phy:Ha 3 3 1 33

State Sector B Schemes Warabandi Fin 6.00 6.00 4.76 79 1 Phy:Ha 2000 2000 1586 79

Construction of Fin 2858.85 2662.85 2044.80 77 2 Ayacut Roads Phy:Km. 592 560 517.24 92 3 Housing Fin 179.00 169.00 78.96 47 Construction of Fin 105.00 105.00 23.14 22 4 Godowns Phy:No. 29 29 9 31 5 Construction of Pick Fin 3.00 3.00 2.05 68 ups Phy:No. 1 1 1 100

6 Miscellaneous Fin 475.00 153.00 25.22 16 WALMI Fin 372.00 372.00 183.77 49

Phy:No. 1835 1835 3180 173

Total CADA(2705) Fin 54516.00 54516.00 21200.94 39

Special Development Fin 7501.00 7501.00 2304.74 31 Programme (4705) KNNL Fin 7565.51 7565.51 1843.55 24

KBJNL Fin 1205.00 1205.00 1066.45 89

CNNL Fin 2892.72 2892.72 1160.28 40

Grand Total Fin 62017.00 62017.00 23505.68 38 (2705+4705)

* * *

206