GOVERNMENT OF WATER RESOURCES DEPARTMENT

(MAJOR, MEDIUM IRRIGATION AND CADA)

ANNUAL REPORT

2013-14

VIKASA SOUDHA

JUNE 2014

1

SL. PAGE CONTENTS NO. NO.

1 INTRODUCTION

PREFACE

VISION AND MISSION OF THE DEPARTMENT

OBJECTIVES OF THE DEPARTMENT

2 ORGANISATIONAL STRUCTURE

3 ACHIEVEMENTS OF WATER RESOURCES DEPARTMENT DURING 2010-11

4 ACCELERATED IRRIGATION BENEFIT PROGRAMME (AIBP)

5 PRIME MINISTER’S SPECIAL PACKAGE

6 SPECIAL DEVELOPMENT PLAN (SDP)

7 WATER RESOURCES DEVELOPMENT ORGANISATION

8 CENTRAL MECHANICAL ORGANISATION (CMO)

9 KARNATAKA ENGINEERING RESEARCH STATION (KERS, K.R SAGAR)

10 WATER AND LAND MANAGEMENT INSTITUTE (WALMI, DHARWAD)

NIGAM

11 KRISHNA BHAGYA JALA NIGAM LIMITED (KBJNL)

11.1 UPPER KRISHNA PROJECT (UKP)

11.2 TOWN DEVELOPMENT AUTHORITY, BAGALKOT (BTDA)

12 KARNATAKA NEERAVARI NIGAMA LIMITED (KNNL)

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION 12.1 (NORTH),

12.1.1 PROJECT

12.1.2 HIPPARAGI IRRIGATION PROJECT

12.1.3 MARKANDEYA PROJECT

12.1.4 DUDHGANGA IRRIGATION PROJECT

12.1.5 HIRANYAKESHI LIS

12.1.6 SRI RAMESHWARA L.I. SCHEME SL. PAGE CONTENTS NO. NO.

12.1.7 KINAYE PROJECT

12.1.8 MALIKWADI LIS

12.1.9 KALLOL-YADUR BRIDGE CUM BARRAGE

12.1.10 SANGAM BARRAGE

12.1.11 FILLING OF SHIRGAON BASAVANNA TANK

12.1.12 FILLING OF TANK

FILLING OF 18 TANKS OF TALUK & 4 TANKS OF CHIKKODI TALUK 12.1.13 (TOTAL 22 TANKS) FROM HIRANYAKESHI RIVER)

12.1.14 SRI MAHALAKSHMI LIS

12.1.15 TUBACHI-BABALESHWAR LIS

12.1.16 VEERABHADRESHWARA

12.1.17 LIS

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, MALAPRABHA

12.2 PROJECT ZONE, DHARWAD.

12.2.1 MALAPRABHA PROJECT

12.2.2 HARINALA IRRIGATION PROJECT

12.2.3 KALASA NALA AND BANDHURNALA PROJECT

12.2.4 JAVALUHALLA L.I. SCHEME

12.2.5 BENNIHALLA L.I. SCHEME (5 NOS.)

11.2.6 KOLACHI L.I. SCHEME

12.2.7 L.I. SCHEME

12.2.8 SHIGGAON L.I. SCHEME (Micro irrigation project- sprinkler/drip system)

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER TUNGA 12.3 PROJECT ZONE, SHIMOGA

12.3.1 UPPER TUNGA PROJECT (UTP)

12.3.2 TUNGA LIFT IRRIGATION SCHEME

12.3.3 BASAPURA LIFT IRRIGATION SCHEME SL. PAGE CONTENTS NO. NO.

12.3.4 -SASALWAD LIS

12.3.5 GUDDADA MALLAPURA LIS

12.3.6 SANYASIKOPPA LIS

12.3.7 DANDAVATHI RESERVOIR PROJECT

12.3.8 KALLUVADDAHALLA NEW TANK

12.3.9 THILUVALLI LIFT IRRIGATION SCHEME

12.3.10 NIDIGE-PURLE TANKS DEVELOPMENT

12.3.11 MODERNISATION OF TUNGA ANICUT PROJECT

12.3.12 KACHAVI LIFT IRRIGATION SCHEME

12.3.13 TUNGA MODERNISATION

12.3.14 BHADRA MODERNISATION

12.3.15 GONDI MODERNISATION

12.3.16 RAJANAHALLI LIS (DAVANAGERE 22 TANKS)

12.3.17 DAVANAGERE 22 TANKS (RAJANAHALLI LIS)

12.3.18 HARIHARA-BYRANPAD LIS

MODERNISATION OF AMBLIGOLA CANAL SYSTEM & MODERNISATION OF 12.3.19 ANJANAPURA CANAL SYSTEM

12.3.20 DHARMA PROJECT

12.3.21 RANIKERE FEEDER CANAL

12.3.22 MADAGA-MASUR TANK

12.3.23 GAYATHRI RESERVOIR PROJECT

12.3.24 D.B.KERE PICK-UP PROJECT

12.3.25 JAMBADAHALLA RESERVOIR PROJECT

12.3.26 HODIRAYANAHALLA RESERVOIR PROJECT

12.3.27 BHEEMASAMUDRA TANK

12.3.28 CONSTRUCTION OF LINK CANAL FROM HEBBEHALLA TO MADAGADAKERE SL. PAGE CONTENTS NO. NO.

SUPPLEMENTAING WATER TO 60 TANKS OF HARAPANAHALLI FROM 12.3.29 GARBHAGUDI BARRAGE OF TUNGABHADRA RESERVOIR

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION 12.4 PROJECTS ZONE, GULBARGA

12.4.1 BENNITHORA PROJECT

12.4.2 BHIMA LIFT IRRIGATION SCHEME

12.4.3 GANDORINALA PROJECT.

12.4.4 LOWER MULLAMARI PROJECT.

12.4.5 PROJECT.

12.4.6 CHAMDRAMPALLI PROJECT

12.4.7 HATHIKUNI TANK PROJECT

12.4.8 SOUDHAGAR TANK PROJECT

12.4.9 KARANJA PROJECT

12.4.10 UPPER MULLAMARI PROJECT

12.4.11 CHULKINALA PROJECT

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION 12.5 CENTRAL ZONE, MUNIRABAD

12.5.1 TUNGABHADRA PROJECT

12.5.2 SINGATALUR LIFT IRRIGATION SCHEME (SLIS)

12.5.3 HIREHALLA PROJECT

12.5.4 HAGARIBOMMANAHALLI PROJECT

12.5.5 NARIHALLA PROJECT

12.5.6 RAJOLIBUNDA DIVERSION SCHEME

12.5.7 KATARKI LIS

12.5.8 BOYALMARCHARD LIS

12.5.9 ALAVANDI- LIS

12.5.10 WOLABELLARY LIS SL. PAGE CONTENTS NO. NO.

12.5.11 KANAKANALA DIVERSION PROJECT

12.5.12 MASKINALA PROJECT

12.5.13 HEDAGINAHAL BARRAGE PROJECT

12.5.14 KARUR LIS

12.5.15 VIJAYANAGARA CANAL MODERNISATION

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, VARAHI 12.6 PROJECT ZONE, SIDDAPURA.

12.6.1 VARAHI IRRIGATION PROJECT

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER BHADRA 12.7 PROJECT ZONE, CHITRADURGA.

12.7.1 UPPER BHADRA PROJECT (UBP)

12.7.2 YATTINAHOLE PROJECT

13 CAUVERY NEERAVARI NIGAMA LIMITED

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION (S) 13.1 ZONE, MYSORE

13.1.1 D. DEVARAJA URS CANAL

13.1.2 KABINI RESERVOIR PROJECT

13.1.3 HARANGI PROJECT

13.1.4 TARAKA PROJECT

13.1.5 ARKAVATHY PROJECT

13.1.6 CHIKLIHOLE PROJECT

13.1.7 UDUTHOREHALLA PROJECT

13.1.8 IGGALUR BARRAGE PROJECT

13.1.9 PROJECT

13.1.10 MODERNISATION OF KRISHNARAJA SAGAR

13.1.11 NANJAPURA LIFT IRRIGATION SCHEME

13.1.12 BANAHALLIHUNDI LIS SL. PAGE CONTENTS NO. NO.

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, HEMAVATHY 13.2 CANAL ZONE, TUMKUR

13.2.1 HEMAVATHY CANAL ZONE, TUMKUR

AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, HEMAVATHY 13.3 RESERVOIR PROJECT, GORUR

13.3.1 HEMAVATHY PROJECT

13.3.2 YAGACHI PROJECT

13.3.3 HUCHANAKOPPALU LIS

13.3.4 KAMASAMUDRA LIS

13.3.5 KACHENAHALLI LIS

13.3.6 VOTEHOLE PROJECT

14 COMMAND AREA DEVELOPMENT PROGRAMME

1. INTRODUCTION

The Annual Report is a document giving details of the annual Programme, Progress and important events that have taken place during the year, in the Water Resources Department.

GEOGRAPHICAL AREA

The geographical area of Karnataka is 1,91,791 Sq. Km., accounting for 5.83% of the total area of the country.

The cultivable command area of the State is 1,40,598 sq. Km. The net sown area is 1,07,000 sq. Km. The ultimate Irrigation Potential under Major and Medium Irrigation Projects has been estimated as 35,000 sq. Km or 35.00 Lakh Ha.

PROGRESS IN BRIEF

There are 211Major and Medium Irrigation Projects in the State, out of which 60 projects are completed, 151 are ongoing.

The Water Resources Department has established three special purpose vehicles, namely, Krishna Bhagya Jala Nigama Limited (KBJNL), Karnataka Neeravari Nigama Limited (KNNL) and Cauvery Neeravari Nigam Limited (CNNL), under the companies Act of 1956, to mobilize financial resources for speedy completion of major and medium irrigation projects with-in the targeted period.

KRISHNA BHAGYA JALA NIGAM LIMITED (KBJNL):

“Krishna Bhagya Jala Nigam Limited” was formed vide G.O. No. ID/25/WBM/95, dated: 6-5-94, to expedite the works of Upper Krishna Project (UKP). This Nigam is functioning since 19th August 1994.

KARNATAKA NEERAVARI NIGAM LIMITED (KNNL):

”Karnataka Neeravari Nigam Limited” was formed vide G.O. No. ID: 201: KBN: 98, dated: 26-11-98, to expedite the works in Krishna Basin, except UKP. This Nigam is functioning since 9th December 1998.

CAUVERY NEERAVARI NIGAM LIMITED (CNNL):

”Cauvery Neeravari Nigam Limited” was formed vide G.O. No. WRD: 32: KBN: 2003, Dated: 12.05.2003, to expedite the works in Cauvery Basin. This Nigam is functioning since 3rd June 2003.

2. ORGANISATIONAL STRUCTURE WATER RESOURCES DEPARTMENT

HON’BLE MINISTER FOR WATER RESOURCES

PRINCIPAL SECRETARY

SECRETARY

C.E, DIRECT CADA’S KBJNL BOARD KNNL BOARD CNNL BOARD W.R.D.O FIELD OF DIRECTORS OF DIRECTORS OF OFFICES DIRECTORS CADA CE, DIRECTORATE REGISTERED REGISTERED HYDROLOGY CORPORATE CORPORATE REGISTERED CE, IRRIGATION & CMO, OFFICE CORPORATE CENTRAL ZONE, OFFICE OFFICE MUNIRABAD ADMINISTRATOR MALAPRABHA & FIELD OFFICES FIELD OFFICES FIELD C.E, GHATAPRABHA, OFFICES I.S.W.D, CE, IRRIGATION BELGAUM CE, O&M ZONE, BANGALORE PROJECT ZONE, CE, UTP UKP, GULBARGA ADMINISTRATOR ZONE, CE, NARAYANPURA TUNGABHADRA SHIMOGA IRRIGATION PROJECT, (SOUTH), MUNIRABAD CE, DAM ZONE, MYSORE CE, UPPER UKP, ALMATTI CE, VARAHI TUNGA ZONE, PROJECT, SIDDAPURA ADMINISTRATO CE, H.P.Z, SHIMOGA CE, CANAL ZONE- R BHADRA, GORUR SHIMOGA 1, UKP, B.GUDI CE, IPZ, GULBARGA

DIRECTOR,

CE, CANAL WALMI CE, H.C.Z, ADMINISTRATOR ZONE-2, UKP, CE, TUMKUR CAUVERY BASIN, KEMBHAVI IRRIGATION MYSORE (NORTH), DIRECTOR, K.E.R.S BELGAUM ADMINISTRATOR UKP, B.GUDI CE, MALAPRABHA PROJECT ZONE, DHARWAD ADMINISTRATOR IRRIGATION PROJECT ZONE, CE, UPPER GULBARGA BHADRA PROJECT, CHITRADURGA 3. ACHIEVEMENTS OF WATER RESOURCES DEPARTMENT DURING 2013-14

 During 2013-14, an irrigation potential of 93851 Hectares is created from ongoing irrigation projects and Rs.6527.76 crores financial progress is achieved.

 Cumulative irrigation potential of 28.37 lakh Ha. has been created from Major & medium irrigation projects upto end of March 2014.

 An irrigated potential of 6,40,542 Ha. has been created so for under Upper Krishna Project, Such as, NLBC, JBC, NRBC, ALBC, ARBC are nearing completion.

 Central Assistance of Rs.199.82 Crores under Accelerated Irrigation Benefit Programme & Hon’ble Prime Minister’s Special Rehabilitation Package has been availed during 2013-14 and an expenditure of Rs. 527.58 crores is incurred.

 Krishna Bhagya Jala Nigam Limited has incurred an expenditure of Rs.2556.75 Crores for implementing 24 ongoing major and medium irrigation projects/Components during 2013-14.

 Karnataka Neeravari Nigam Limited has incurred an expenditure of Rs.2662.61Crores for implementing 78 ongoing major and medium irrigation projects/components of projects during 2013-14.

 Cauvery Neeravari Nigam Limited has incurred an expenditure of Rs.1224.63 Crores for implementing 49 ongoing major and medium irrigation projects/Components of projects during 2013-14.

 During 2013-14, expenditure under Special Component Plan is Rs.543.51 crores, under Tribal Sub Plan is Rs.93.21 crores & under Special Development Plan of Rs.521.93 crores has been incurred.

 Loan assistance from ADB is in negotiation stage. Loan negotiation date is expected from Ministry of Finance (DEA), Government of .

 For efficient & effective water management under the Command Areas of Major & medium irrigation projects, Water Resources Department has established 2831 Water Users Co-operative Societies.

 FIC has been given priority in order to bridge the gap between potential created and utilized. During 2013-14, FIC’s have been created for 56627 Ha. under CADA.

 During this water year, regulation of water has been managed effectively.

 Approval has been obtained from CWC and Planning Commission, GoI, New Delhi for the Project Report of Modernization of Narayanapur Left Bank Canal under Upper Krishna Project amounting to Rs.3752.18 crores, to improve water use efficiency (WUE) and to provide water to the tail end suffering Atchkat of about 1,00,000 Ha.

 In order to accelerate the land acquisition and R&R works due to submersion of rising of to the height of 524.25 mtrs, a High Level Committee has been constituted under the Chairmanship of the Hon’ble Chief Minister and Action Plan Review Committee has been constituted under the Chairmanship of Chief Secretary.

 During 2013-14, under Upper Krishna Project Stage III, progress of Mulwad LIS, Chimmalagi LIS, Koppal LIS, Indi LIS (extension) Narayanapur Right Bank Canal, Rampur LIS (extension), Mallabad LIS and Herakal LIS works have been accelarated.

 Administrative approval has been accorded to the detailed Project Report of Yettinahole project including conveyance system amounting to Rs.12912.36 Crores. In the I Phase works have been entrusted in five packages amounting to Rs.3716.51 crores on tender basis and survey work is under progress.

 The largest micro-irrigation scheme in the Country, i.e., Ramthal (Marol) LIS to irrigate an area on 24,000 ha. with an estimated cost of Rs.767.00 crores is entrusted on turnkey basis and the works are in progress.

 Administrative approval has been accorded to the detailed Project Reports (DPRs) of Sanka Buyyara, , Buthanal & Begam Talab tanks filling works and Anachi tank filling work for providing drinking water to Indi taluk, Bijapur district has been started.

 Filling of 10 tanks and providing drinking water in Huvinahadagali taluk of Bellary district of Hyderabad-Karnataka area with a cost of Rs.114.50 crores.

 Tubachi-Babaleshwar LIS has been taken up for providing irrigation facilities to area of 104.975 acres by adopting micro irrigation in Athani and taluks of Bijapur district with a cost of Rs.2488.97 crores.

 In Cauvery Basin, modernisation works of Rajaparameshwari anicut canals and D.J.Anicut canals are under progress.

 In Cauvery Basin, administrative approval has been accorded to modernisation of Sriramadevara Anicut, modernisation of Ramaswamy Anivut and its canal system and drinking water scheme.

4. ACCELERATED IRRIGATION BENEFIT PROGRAMME

For the early completion of some of the ongoing irrigation projects, which were lingering due to shortage of funds for many years, the Government of India launched the Accelerated Irrigation benefit programme, during 1996-97. Since then, 11 projects in the State, namely, Upper Krishna project (UKP) Stage-I, Phase-III, Malaprabha, Hirehalla, Ghataprabha, Karanja, Upper Krishna project (UKP) Stage-II, Maskinala, Varahi, Bhima LIS, Guddadamallapura LIS,and Gandhorinala have received / are receiving Central Loan Assistance (CLA) / (CA) under Accelerated Irrigation benefit programme (AIBP).

 During 2013-14, Guddadamallapura LIS, Varahi, Hipparagi and Bhima LIS are the 4 projects that have received C.A. under A.I.B.P.

 The cumulative C.A. (including grants) released upto end of March 2014 under AIBP & PM’s package is `.5893.50 crores. The cumulative expenditure incurred on these projects up to the end of March 2014 is `. 9808.66 crores.

Hon’ble PM’s Special Package:- During 2006-07, the Special Rehabilitation Package was launched by the Government of India to mitigate the distress of farmers in selected 31 districts of the Country from where large numbers of Suicide cases by the farmers were reported.

In Karnataka, 6 districts viz Belgaum, Bijapur, Shimoga, Chikkamagalur, Chitradurga, Hassan and Kodagu are identified as drought prone districts and 17 projects benefiting these 6 districts were identified and proposals of the same have been submitted. The funding proposed is as per revised AIBP norms.

Malaprabha and Ghataprabha are already receiving Central Assistance under AIBP. Markandeya, Chiklihole and Votehole projects are completed. Hippargi, Dudhganga, ERM of Bheemasamudra tank and Modernisation of canal systems of Bhadra are availing central assistance under this package.

Details of central assistance received under AIBP & PM’s Special Package during 2013-14 are as follows:

Details of Central Assistance (CA) under AIBP and PM’s Package during 2013-14 (`. in Crores, Potential in Hectares.) Central Central Expenditure till Sl. Assistance Assistance Name of Project 03/2014 during No. sought during received during 2013-14 2013-14 2013-14 1 Guddadamallapura LIS 13.50 22.11 22.11 2 Bhima LIS 62.15 141.27 141.27 3 Varahi 74.31 19.51 19.51 4 Hipparagi 208.74 16.93 16.93 TOTAL 358.70 199.82 199.82

ABSTRACT (CUMULATIVE) OF CENTRAL ASSISTANCE RECEIVED UNDER AIBP & PM’S PACKAGE (`.in crores) CA released Expenditure AIBP General) 4933.89 7296.29 AIBP (P.M's package) 942.68 2512.37 Total 5893.50 9808.66

STATEMENT SHOWING DETAILS OF CENTRAL ASSISTANCE UNDER A.I.B.P RELEASED TO MAJOR AND MEDIUM IRRIGATION PROJECTS (SINCE 1996-97) (`. in Crores) CENTRAL ASSISTANCE CENTRAL NO. OF PERIOD PROPOSED/ ASSISTANCE EXPENDITURE PROJECTS SANCTIONED RELEASED

1996-97 5 122.50 61.25 172.21

1997-98 5 175.00 90.50 160.49

1998-99 5 167.00 94.50 171.05

1999-00 5 190.64 157.14 190.61

2000-01 4 171.00 171.00 268.26

2001-02 7 545.00 492.50 911.38

2002-03 8 611.97 620.85 693.00

2003-04 8 266.48 266.48 440.57

2004-05 5 463.05 396.30 475.46

2005-06 5 336.70 344.64 473.25

2006-07 6 568.91 349.49 457.15

2007-08 5 410.22 260.02 664.93

2008-09 6 294.25 429.03 702.35

2009-10 9 660.90 767.30 765.09

2010-11 8 555.56 533.11 1049.36

2011-12 12 465.16 452.22 942.18

2012-13 8 304.83 207.35 743.74

2013-14 4 199.82 199.82 527.58

TOTAL UPTO MARCH 6508.99 5893.50 9808.66 2014

CUMULATIVE STATEMENT CLA Released (Rs. in Crores)

Sl. 1996- 1997- 1998- 1999- 2000- 2001- 2002- 2003- 2004- 2005- 2006- 2007- 2008- 2009- 2010- Project 2011-12 2012-13 2013-14 CUMULA No 97 98 99 2000 2001 02 03 04 05 06 07 08 09 10 11 TIVE

UKP Stage-I Phase- - 1380.6 1 57.00 50.00 50.00 100.00 100.00 200.00 181.00 - 98.48 17.38 76.18 71.23 91.92 152.98 - 134.50 III 7

2 UKP Stage-II - - - - - 250.00 275.05 163.48 204.68 233.79 183.47 102.07 8.019 85.00 150.18 - - 1655.73

3 Malaprabha 1.50 12.00 10.00 13.50 - 10.00 25.56 - 12.00 20.00 13.50 35.34 49.44 110.53 0.00 90.72 98.29 502.38

4 Hirehalla 2.75 6.00 6.00 8.00 8.00 10.00 8.78 14.71 ------64.24

5 Ghataprabha - 15.00 12.50 20.00 45.00 5.00 75.00 13.02 62.09 65.00 30.805 29.04 95.61 56.16 20.6 - - 544.82

6 Karanja - 7.50 16.00 15.64 18.00 10.00 34.37 75.27 - - - - 12.25 - 0.00 - - 189.03

7 Gandhorinala - - - - - 7.50 17.87 - 19.05 8.47 45.53 - - 18.52 - - - 116.94

8 Maskinala ------3.22 ------3.22

9 Varahi ------22.05 20.17 26.32 0.00 - 11.59 19.51 99.64

10 Bhima LIS ------58.64 52.62 45.34 - 141.27 297.87

Guddadamallapura 11 ------32.40 24.84 - - 22.11 79.35 LIS

TOTAL 61.25 90.50 94.50 157.14 171.00 492.50 620.85 266.48 396.30 344.64 349.49 259.73 277.40 540.55 248.24 270.56 109.88 182.89 4933.89

Expenditure (`. in Crores)

Sl. 1996- 1997- 1998- 1999- 2000- 2001- 2002- 2003- 2004- 2005- 2007- 2009- 2010- 2011- 2012- 2013-14 CUMUL Project 2006-07 2008-09 No 97 98 99 2000 2001 02 03 04 05 06 08 10 11 12 13 A

UKP Stage-I - 1 155.74 92.30 77.58 116.40 187.80 235.33 214.69 94.19 92.18 61.13 46.19 50.10 239.11 57.51 134.44 36.73 135.10 2026.52 Phase-III

2 UKP Stage-II - - - - - 534.10 352.29 236.48 268.17 272.29 234.58 119.51 76.98 104.10 100.66 129.90 24.05 - 2453.11

3 Malaprabha 5.12 14.92 22.64 9.87 5.15 15.87 14.45 14.42 19.64 19.62 31.28 56.37 27.72 28.20 94.81 79.20 80.35 - 549.63

4 Hirehalla 11.35 17.12 12.06 15.82 22.68 11.41 11.69 9.94 18.45 ------130.52

- 5 Ghataprabha - 20.47 28.82 20.04 26.96 72.77 57.57 55.45 64.68 92.47 77.29 76.90 44.56 65.22 84.22 115.54 - 902.96

6 Karanja - 15.68 29.95 28.48 25.67 26.55 23.62 18.64 - - - - 10.78 8.27 21.92 7.07 - - 216.63

7 Gandhorinala - - - - - 15.35 16.82 10.09 12.34 27.73 34.96 - 17.97 23.79 - - - - 159.92

8 Maskinala ------1.87 1.36 ------3.23

74.31 9 Varahi ------32.85 81.22 64.76 49.68 41.76 18.91 63.17 426.66

62.15 10 Bhima LIS ------30.18 38.37 53.36 76.11 260.17

Guddadamalla 13.05 11 ------6.66 31.59 21.43 5.90 78.63 pura LIS

TOTAL 172.21 160.49 171.05 190.61 268.26 911.38 693.00 440.57 475.46 473.24 457.15 384.10 481.88 373.61 547.77 462.14 384.68 149.51 7197.11

DETAILS OF PROJECTS ASSISTED UNDER AIBP PROGRAMME (YEARLY)

1996-97 1997-98 1998-99 1999-2000 2000-01 2001-02 Sl. Project No CLA CLA CLA CLA CLA CLA CLA Expendit CLA Expendi CLA Expendi CLA Expendi CLA Expendi CLA Expendi Sanctio Sanctio Sanctio Sanctio Sanctio Sanctio Released ure Released ture Released ture Released ture Released ture Released ture ned ned ned ned ned ned

UKP Stage- 1 114.00 57.00 155.74 100.00 50.00 92.30 100.00 50.00 77.58 100.00 100.00 116.40 100.00 100.00 187.80 200.00 200.00 235.33 I Phase-III

2 UKP Stage-II ------250.00 250.00 534.10

3 Malaprabha 3.00 1.50 5.12 24.00 12.00 14.92 20.00 10.00 22.64 27.00 13.50 9.87 - - 5.15 20.00 10.00 15.87

4 Hirehalla 5.50 2.75 11.35 6.00 6.00 17.12 6.00 6.00 12.06 8.00 8.00 15.82 8.00 8.00 22.68 10.00 10.00 11.41

5 Ghataprabha - - - 30.00 15.00 20.47 25.00 12.50 28.82 40.00 20.00 20.04 45.00 45.00 26.96 30.00 5.00 72.77

6 Karanja - - - 15.00 7.50 15.68 16.00 16.00 29.95 15.64 15.64 28.48 18.00 18.00 25.67 20.00 10.00 26.55

7 Gandhorinala ------15.00 7.50 15.35

8 Maskinala ------

Total 122.50 61.25 172.21 175.00 90.50 160.49 167.00 94.50 171.05 190.64 157.14 190.61 171.00 171.00 268.26 545.00 492.50 911.38

(As on 31-3-2014) (`.in Crores) Contd....

2002-03 2003-04 2004-05 2005-06 2006-07 2007-08

Sl. Project CLA CLA CLA No CLA CLA CLA CLA Expe CLA Expe CLA CLA Expe CLA Sanc CLA Expen Expen Sanc Sanc Expen Sancti Releas Sanction Relea ndit Rele ndit Sancti Rele ndit Rele tione Released diture diture tione tione diture oned ed ed sed ure ased ure oned ased ure ased d d d

UKP Stage-I 1 181.00 181.00 214.69 - - 94.19 115.85 98.48 92.18 39.01 17.38 61.13 74.87 76.18 46.19 94.46 71.23 50.10 Phase-III

UKP Stage- 183.4 2 275.05 275.05 352.29 163.48 163.48 236.48 241.22 204.68 268.17 204.22 233.79 272.29 168.77 234.58 131.66 102.1 119.51 II 7

3 Malaprabha 25.56 25.56 14.45 - - 14.42 12.00 12.00 19.64 20.00 20.00 19.62 54.00 13.50 31.28 60.27 35.34 56.37

4 Hirehalla 9.90 8.78 11.69 14.71 14.71 9.94 12.84 - 18.45 ------

Ghataprabh 5 75.00 75.00 57.57 13.01 13.015 55.45 62.09 62.09 64.68 65.00 65.00 92.47 123.21 30.81 77.29 99.33 29.04 76.90 a

6 Karanja 34.37 34.37 23.62 75.27 75.27 18.64 ------

7 Gandorinala 17.87 17.87 16.82 - - 10.09 19.05 19.05 12.34 8.47 8.47 27.73 55.87 45.53 34.96 - - -

8 Maskinala 3.22 3.22 1.87 - - 1.36 ------

9 Varahi ------18.25 - 32.85 24.50 22.05 81.22

Total 621.97 620.85 693.00 266.47 266.48 440.57 463.05 396.30 475.46 336.70 344.64 473.24 494.97 349.49 457.15 410.22 259.73 384.10

Contd…

2008-09 2009-10 2010-11 2011-12 CLA CLA CLA Sl. No Project CLA Expenditu CLA Expenditur CLA CLA Expenditur CLA Expenditur Sanctio Sanction Sanctione Released re Released e Sanctioned Released e Released e ned ed d UKP Stage-I 1 102.14 91.92 239.11 169.97 152.98 57.51 212.06 0.00 134.44 149.45 134.50 36.73 Phase-III

2 UKP Stage-II 44.14 8.019 76.98 94.45 85.00 104.10 166.88 150.18 100.66 - - 129.90

3 Malaprabha 33.94 49.44 27.72 135.00 110.53 28.20 56.20 0.00 94.81 100.80 90.72 79.20

4 Hirehalla ------

5 Ghataprabha 57.82 95.61 44.56 99.05 56.16 65.22 22.89 20.60 84.22 - - 115.54

6 Karanja 37.53 12.25 10.78 - - 8.27 4.88 0.00 21.92 16.95 - 7.07

7 Gandorinala 18.02 - 17.97 18.52 18.52 23.79 ------

8 Maskinala ------9 Varahi 22.41 20.17 64.76 29.24 26.32 49.68 5.70 0.00 41.76 8.73 - 18.91 10 Bhima LIS - - - 65.16 58.64 30.18 59.35 52.62 38.37 50.38 45.34 53.36 Guddadamall 11 - - - 36.00 32.40 6.66 27.60 24.84 31.59 31.90 - 21.43 apura LIS Total 316.00 277.40 481.88 660.90 540.55 373.61 555.56 248.24 547.77 358.21 270.56 462.14

Contd…

CUMULATIVE 2012-13 2013-14

Sl.No Project CLA CLA Expenditure CLA CLA Expenditure CLA Expenditure Sanctioned Released upto 03/13 Sanctioned Released upto 03/13 Released

- - - 1 UKP Stage-I Phase-III - - 135.10 1380.67 2026.52

2 UKP Stage-II - - 24.05 - - - 1655.73 2453.11

3 Malaprabha 109.21 98.29 80.35 - - 99.18 502.38 648.81

4 Hirehalla ------64.24 130.52

5 Gandhorinala ------116.94 159.92

6 Maskinala ------3.22 3.23

7 Ghataprabha ------544.82 902.96

8 Karanja ------189.03 216.63

9 Varahi 12.88 11.59 63.17 19.51 19.51 74.31 99.64 426.66

10 Bhima LIS 47.58 - 76.11 141.27 141.27 62.15 297.87 260.17

11 Guddadamallapura LIS 31.81 - 5.90 22.11 22.11 13.05 79.35 78.63

Total 201.48 109.88 384.68 182.89 182.89 248.69 4933.89 7296.29

DETAILS OF PROJECTS ASSISTED UNDER Hon'ble Prime Minister's Special Package (As on 31-03-2014) (`. in Crores)

2007-08 2008-09 2009-10 2010-11 2011-12

Sl.No Project CA CA CA CA CA CA CA CA CA Expendi CA Expendi Expendi Expen Expendit Sancti Releas Sancti Sanctio Release Sancti Releas Sanctio Releas ture Released ture ture diture ure oned ed oned ned d oned ed ned ed

1 Hipparagi - 52.84 78.50 115.36 80.87 99.05 114.78 124.24 281.20 281.20 348.28 143.36 129.03 244.74 2 Votehole 0.29 1.62 ------Modernisation 3 - 220.88 45.26 32.44 127.93 47.64 108.49 258.14 58.98 0.00 147.10 58.49 52.64 225.46 of Bhadra 4 Dudhganga - 5.49 1.22 3.83 11.68 3.01 0.00 9.10 4.08 3.67 6.21 0.42 - 7.84

ERM of 5 Bheemasamudra ------4.30 3.48 0.00 4.30 0.00 0.00 4.00 - 2.00 tank

Total 0.00 0.29 280.83 124.98 151.63 220.48 154.00 226.75 391.48 348.56 284.87 501.59 206.27 181.67 480.04

2012-13 2013-14 CUMULATIVE

Sl.No Project CA CA CA CA Expendi CA Expendi Expendi Sancti Releas Sancti Release ture Released ture ture oned ed oned d 1 Hipparagi 105.10 94.59 319.76 16.93 16.93 208.74 734.96 1170.73

2 Votehole ------0.29 1.62 Modernisation 3 3.20 2.88 30.08 - - 62.45 196.45 1072.04 of Bhadra

4 Dudhganga 1.49 - 9.22 - - 7.70 7.50 57.26

ERM of 5 Bheemasamudra ------3.48 2.00 tank

Total 109.79 97.47 359.06 16.93 16.93 278.89 942.68 2512.37

5. SPECIAL DEVELOPMENT PLAN (SDP)

As per the recommendations of High Power Committee for redressal of regional imbalances, exclusive allocation is made available to irrigation sector for early completion of on-going major & medium irrigation projects in the backward districts of the State. Budget allocation to Water Resources Department for the year 2013-14 under Special Development Plan is Rs. 600.00 crores, break up is as follows:

KNNL Rs 500.00 Crores TOTAL Rs 500.00 Crores

Programme & Progress of Special Development Plan for the year 2013-14 under Major & Medium Irrigation Projects

ABSTRACT (Rs. in lakhs, Potential in Ha.) Annual Programme for Revenue Name of the Sl No District Taluk 2013-14 division project Fin. Phy. Fin. Phy. Progress Progress 1 2 3 4 5 6 7 9 12 KARNATAKA NEERAVARI NIGAM LIMITED (KNNL) Afzalpur Gulbarga Amarja 3000.00 1000 1030.97 442 Aland Lower Chincholi Mullamari 1000.00 313 783.9 0 Project 1 Gulbarga Gulbarga Gandorinala 500.00 113 1518.17 Chittapura Bennithora 1000.00 200 2767.60 0 Singatalur 23500.00 10000 17078.77 10446 Bellary Hadagali Filling up of 10 Tanks of 1500.00 - 1145.00 Hoovinahadagali Total Gulbarga 30500.00 11626 24324.41 10888 Chikkamagal N.R pura ore Tarikere Challakere Hosadurga Upper Bhadra 2 Bangalore Chitradurga 19000.00 0 26717.29 0 Chitradurga Stage-I Hiriyur Tumkur Sira Chikkaballapur Chikkamagal Ubrani 3 Mysore Tarikere 500.00 0 1151.45 0 ur Amrutapura

Total Bangalore & Mysore 19500.00 0 27868.74 0.00

TOTAL 50000.00 11626 52193.15 10888.00

23

Cammand Area Development Authority (CADA): Annual Programme 2013-14 Progress upto 03/2014 Works Financial Financial Physical Physical (In Lakhs) (In Lakhs) FIC (Hectares) 27289 174757 9302.34 56626.97 Ayacut Roads (Km.) 15438 2749 8675.79 1694 FDC (Hectares) 6430 159696.80 4524 134676 Land Reclamation 12074 60107 1397 5363 Total (CADA) 44659.72 20292.86

24

6. WATER RESOURCES DEVELOPMENT ORGANISATION

VISION AND MISSION OF W.R.D.O.:

This Organisation is incharge of Planning and Investigation of all Major and Medium Irrigation Projects in the State and provides all the information to the Government in respect of Inter State Water Disputes like Cauvery, Krishna, Godavari and Mahadayi. This Organisation acts as a data Bank for all Hydrological details of Rivers and streams in the State by collecting and processing the rain gauge and River gauge data in a systematic manner. This Organisation provides information regarding completed, ongoing and proposed irrigation projects of the state. This organisation prepares Catchment Area Maps indicating influencing rain gauge stations, digital maps of all hydro meteorological stations of Karnataka state, command Area Maps of completed, ongoing and proposed irrigation projects coming under Cauvery and basin using the latest software viz., GIS, Remote sensing and Autodesk map. The work of monitoring and evaluation of existing and ongoing projects and safety aspects of dams are monitored by this organisation. In addition, the establishment matter of Irrigation zones regarding postings, transfer of staff and Regularisation of Daily Wages and Monthly Rated Staff as per Supreme Court order is also attended to by this Organisation.

OBJECTIVES OF W.R.D.O. PLANNING AND INVESTIGATION UNIT: The vision of this organisation is to identify the sources of water to meet the increasing demand of the various user sectors of water and to formulate technically and economically feasible water resource projects with reference to availability of water and allocated water. The target is to bring out more areas under irrigation. The objectives of P & I unit are as below:

25

Examination of feasibility in respect of representation received for the proposals of Major and Medium irrigation projects, Hydro electric projects, industrial water requirement, scheme for drinking water supply etc.,

Preparation of Preliminary Investigation Report of Major and Medium Irrigation Projects based on site inspection and top sheet studies and submission to Government for approval.

Consequent to approval of Project Report by Government, preparation of Detailed Project Report after conducting detailed surveys by using modern techniques: Priority accorded for supply of drinking water in drought prone areas while taking up Irrigation Projects as per the guidelines issued by Ministry of Water Resources, Government of India.

Water Resources Projects, are also prepared for inter-basin transfer of water from the surplus basin to deficit basin.

The unit is vested with the responsibility of scrutiny of proposal related to industrial use, Hydro and thermal power stations.

o Flood Flow Canal to feed water to the suffering atchcut of TLBC and provide irrigation facility.

o Proposal for diversion of Potential Flows of certain West Flowing streams in upper catchment for improvement of drinking water and ground water recharge in drought prone Districts.

o Kakkatuhole and Kanganahole Diversion Project to provide water supply.

In addition to the investigation works of Major and Medium Irrigation Projects, the following works are also dealt by this unit.

 e– Governance in Water Resources Department:

Planning and Investigation Unit, Water Resources Development Organisation is monitoring the e-Governance activities of entire Water Resources Department in Karnataka.

 Right to Information Act:

Requisitions from public regarding Water Resources Department are answered within the stipulated period of one month and updated periodically in the Departmental Website.

26

GEOMATICS CENTRE:

To overcome the problems of completing the Water Resources Investigations within the time frame, due to of reduced technical manpower in the Department, to undertake detailed survey work and to avoid outsourcing to private organization resulting in increased cost of the projects, the Geomatics Centre was established in Water Resources Development Organization on 21-7-2001 as per the G.O No.ID/50/MBI/2000, Bangalore Dated 4-5-2001. 13 posts including post of a Director, was created vide GO Dtd: 10-4-2003 with an intention of adopting the modern techniques in Planning and Investigation. Subsequently the centre has been equipped with required Hardware & Softwares.

Vision and Mission of Geomatics Centre:

1) Data base of Water Resources Information System from micro to macro level which includes Integration of entire water availability, utilization and requirement etc., can be generated.

2) A data base indicating each revenue survey boundary under the atchkat, can be generated using R.S. & GIS technology.

3) Silt and sedimentation estimation of reservoir can be taken up using remote sensing application .

4) Project wise planning & water budgeting can be made for optimum utilization of the water as per State Water Policy.

Performance of the GEOMATICS Centre:

1) Preparation of different Maps for K.G & Cauvery Units of Central Office based on information provided by the respective units.

2) Generation of Isohyetal and Zonal re-organization GIS Maps in digital formats for Karnataka.

27

3) Catchment area GIS maps with influencing rain gauges for the 236 Major, medium and minor irrigation projects for Dam Safety preparedness as per the requirement of hydrology unit is being prepared and provided to hydrology unit.

4) In continuation of 29 layers of information pertaining to Major, Medium and Minor Irrigation projects of the state for Web Enabled GIS based Water Resources Information System submitted during last year, as per the revised requirement of CWC, the information regarding 99 major & medium Irrigation projects of the states, the information such as command area, canal network salient features of the project as well as for major structures along with the relevant photographs have been furnished to the CWC New Delhi, and a vital contribution in launching the Web Enabled GIS based Water Resources Information System has been made from this end.

5) Preparation of GIS digital Maps of all hydro meteorological stations of Karnataka State as per the information provided by the hydrology unit of Central Office is completed.

6) GIS Digital Map of all the projects coming under Krishna river basin of Karnataka, Maharastra and Andhra States has been prepared and furnished to Krishna Godavari unit of Inter State Water dispute for Krishna Tribunal.

7) GIS Map of the garland canals of Netravathi river diversion scheme for project No.1, 2 and 3 from the input data of ALTM (Air Borne Laser Terrain Mapping) survey provided by NRSC Hyderabad has been prepared and handed over to planning unit.

8) Maintenance and updating of Water Resources Department website. The website address is: http://waterresources.kar.nic.in.

9) Acquiring different Resources data pertaining to Karnataka State and furnishing to the Government in connection with Chennai- Bangalore-Chitradurga Industrial corridor.

III. HYDROLOGY UNIT:

To assess Water Resources in Karnataka State in a scientific manner, the studies of flow data at various points in different river basins and rainfall data are most essential. As such, the Government of Karnataka has established a separate Hydrology Unit under Water Resources Development Organization, with the responsibility to collect data from various

28

gauging stations spread all over the State for analyzing and validation of Hydrometric and Hydro meteorological data.

The following Meteorological stations are working under the Jurisdiction of WRDO: A. Hydrological Stations: 1. Current Meter Gauging Stations - 32 2. Stage Discharge Stations - 10 3. Silt and Sedimentation observations stations - 22 B. Hydro meteorological Stations: 1. Fully Climatic Stations - 87 2. Autographic Rain gauge Stations - 166 3. Standard Rain gauge Stations - 759

The data obtained from these Hydrological and Hydro meteorological stations are scrutinized, analyzed and processed. The data of Rain gauge Stations maintained by Water Resources Development Organization are published by the Department of Economics and Statistics after obtaining the data from the concerned Tahasildar office’s of the respective Taluks. Also the daily inflow, outflow of the major and medium reservoirs, weirs and anicuts are collected from respective zones and are being processed. Besides this, yield studies are being carried out for the irrigation, drinking and power projects. H.M.datas are being sent daily to KSNDMC.

This unit is collecting and compiling the rainfall data and flow data of our State regularly. This data is being used for carrying out water availability studies for the newly proposed projects which are being proposed by planning unit of Water Resources Development Organization. Also the yield is being revised of existing projects whenever needed. This unit is carrying out the flood studies of the new projects whenever it is required. Apart from this, letters are being addressed to project authorities to get the daily data of Reservoirs and Anicuts which will also be used for the preparation of water year books of Reservoirs and Anicuts. These data are being given to the users on their request. This unit is preparing and furnishing yield for the following projects:

1. Diversion of water from Yettinahole river to Kolar, Chikkaballapur & Bangalore rural district for drinking water purpose.

2. Diversion of Koganahole river to Lakshmanathirta river for the purpose of drinking water to Bangalore urban districts.

3. Yeild study of Mahadayi basin. 29

MONITORING AND EVALUATION UNIT:

Evaluation and review of safety of large dams in the State coming under Major, Medium and Minor Irrigation Zones is being carried out under the guidance of Dam Safety Review Panel Constituted under Chairmanship of Ex-chairman Central Water Commission and consisting of Panel of Experts.

Monitoring and submission of details of financial progress of NABARD assisted major, medium and minor irrigation projects (including CADA Projects) in the State with the guidance from High Level Committee formed under the Chairmanship of Development Commissioner, Government of Karnataka.

Consolidation and submission of comprehensive report to Government on the year wise area irrigated and demand raised from all irrigation projects of the Department.

Collection of data from project authorities under NPDP.

DAM SAFETY REVIEW PANEL (DSRP):

There are 143 large dams in the State, which are more than 15 m in height or store 60 mcum or more water. The Dam Safety Review Panel was constituted by the Government vide GO. No. WRD : 35 : DSP : 2004 Bangalore, Dated 23-01-2007, under the Chairmanship of Dr Y.K Murthy, former Chairman, CWC, New Delhi, and the Superintending Engineer, Monitoring and Evaluation, Bangalore, as the Convener of this Panel. The Panel evaluates the safety review of each dam after inspecting the dam by the Panel of experts and furnishes recommendations. The main panel has inspected 41 dams and all the inspection reports have been submitted. The Dam Safety Review Panel (DSRP) was re-constituted under the Chairmanship of Shri A.K. Bajaj, Ex-Chairman, Central Water Commission, New Delhi, vide GO No: WRD : 10 : DSP : 2011 : Dtd. 27-04-2012.

Apart from the above 143 dams as referred above, government has constituted two separate teams for inspecting remaining large dams coming under Major and Medium Irrigation Projects Zone vide GO. No. WRD 22: DSP : 2006 Dated 04-12-2006 and two more teams have also been formed to inspect large dams coming under Minor Irrigation Zone, vide GO. No. WRD: 18 : DSP : 2006, Dated 28-05-2007. These Teams have so far inspected 77 dams and all the inspection reports are submitted.

30

Second round of inspection of all the large dams will be commenced during 2014-15.

NABARD assisted projects:

Vide G.O. No. ID 49 MBI 95 (Part III) Bangalore, Dated 01/01/1996, the Chief Engineer, (Now Superintending Engineer) Monitoring and Evaluation, Bangalore has been appointed as Member-Secretary of the High Level Committee for monitoring the National Bank for Agriculture and Rural Development assisted ongoing major, medium and minor irrigation projects in Karnataka under the Chairmanship of Development Commissioner, GOK. Now the NABARD assisted projects progress is reviewed by the Empowered Committee under the Chairmanship of Development Commissioner, Government of Karnataka.

Six medium irrigation projects and 88 minor irrigation projects are taken up in the State under the assistance of NABARD under RIDF-I. Likewise one major irrigation project and 3 minor irrigation projects were taken up under RIDF-II, under RIDF-III one minor irrigation project, under RIDF-IV 20 MI projects, under RIDF-V one MI project, under RIDF-VI 36 MI projects, under RIDF-VII 15 M.I projects, under RIDF-VIII 76 MI projects, under RIDF -IX 191MI projects, under RIDF-X 191 MI projects, under RIDF-XI 290 MI projects, under RIDF-XIII 831 MI projects and under RIDF-XIV 358 MI projects, under RIDF-XV- 416 MI projects, under RIDF- XVI-274 MI projects and under RIDF – XVII-354 MI projects have been taken up.

This Office consolidates the expenditure figures of works from the concerned project authorities, verify the same and submit the proposals to the Government for obtaining reimbursement from Nabard.

During this Year proposals have been obtained from project authorities to the tune of Rs. 135.71 crores and after verification, proposals to the tune of Rs. 107.61 Crores have been submitted to Government to seek reimbursement from NABARD.

30 Projects under CADA are taken up in the State with assistance of NABARD under RIDF XVI. The Claims of expenditure incurred by various CADA are consolidated and submitted to Government for onward transmission to NABARD for reimbursement. During

31

this year Rs.21.95 Crores worth proposals have been submitted to Government for reimbursement.

Government Vide letter No.ID/36/MMG/96 Dated 28/03/1996 have entrusted this office with the work of compiling of periodical returns pertaining to major, medium and minor irrigation projects under different irrigation zones.

WATER RATES:

The season wise and crop wise details of area irrigated and demand raised year wise are being collected from all irrigation projects coming under irrigation zones, same is consolidated and reports are submitted to Government.

Three years Grant and Expenditure: During the year (in Rs.)

2011-12 2012-13 2013-14up to end of Dec 2013 Grant Expenditure Grant Expenditure Grant Expenditure 16050000 19127000 19127000 15988601 23026000 21232510

KRISHNA - GODAVARI UNIT:

The Inter State Water Dispute Unit headed by the Chief Engineer (I.S.W.) is functioning in WRDO under Water Resources Department. The staff members consisting of the Superintending Engineer, Executive Engineer, Assistant Executive Engineers, Assistant Engineers, Second Division Assistants, Stenographers & Typists are performing the works of Inter State Water Disputes in Krishna-Godavari Unit.

The Krishna-Godavari Unit is working towards the preparation of suit/petitions by collecting the required documents, along with statistical information, analyzing them in the light of claiming the right of the State in obtaining the share of water by resolving the Inter State Water Disputes that have arised in the background of the award given by the earlier Krishna Water Disputes and Godavari Water Disputes Tribunals and new issues regarding Mahadayi Water Disputes and Minor Irrigation and Paragodu Drinking Water supply scheme in Pennar Basin.

32

The Cauvery unit of Water Resources Development Organisation, Bangalore deals with the matters concerning sharing of waters of the River Cauvery with the other riparian States viz., Tamil Nadu, Kerala and Union Territory of Pondicherry.

CAUVERY UNIT:

To safe guard the interests of Karnataka and to substantiate the stand of the Government before the Supreme Court/Cauvery water Disputes Tribunal a team of Advocates along with the Advocate General of Karnataka is appointed and their services are being utilised.

The Cauvery Water Disputes Tribunal was set up by the Ministry of water Resources, Government of India, vide its Notification dated: 2.6.1990 with Head Quarters at New Delhi for adjudication of the Cauvery Water Dispute.

To render technical advice in Cauvery Water Disputes matter two Technical Advisors were appointed by the Government and their services are still being continued.

Cauvery Technical Committee was constituted in 05.02.1992 with the sole intention of giving valuable advice to the Government on Cauvery Water Disputes matter and necessary action to be taken by the Government both in the Tribunal as well as Supreme Court.

1. KRISHNA WATER DISPUTES:

1.1 The Krishna Water Disputes Tribunal (Bachawat Tribunal) constituted in April 1969 for adjudication of the water disputes regarding the Inter-State River Krishna and the River Valley thereof, emerging from the letters of complaint of Mysore (present Karnataka), and Andhra Pradesh, gave its first report in December, 1973 and further report containing the final order in May, 1976.

1.2 According to Bachawat Tribunal, the enbloc allocation to the 3 States under Scheme ‘A’ including regeneration is as under:

Maharashtra 560 tmc + 25 tmc = 585 tmc Karnataka 700 tmc + 34 tmc = 734 tmc Andhra Pradesh 800 tmc + 11 tmc = 811 tmc Total 2060 tmc + 70 tmc = 2130 tmc

33

A Master Plan Committee constituted to formulate schemes for effective utilization of Karnataka’s share of water gave its report in 2002 making scheme wise allocation.

1.3 The Bachawat Tribunal had also devised the Scheme 'B' to allocate surplus waters available in the Krishna Basin and recommended for allocation of 25% to Maharashtra, 50% to Karnataka and 25% to Andhra Pradesh. But this is not a part of the Order of the Tribunal.

1.4 Considering the Complaints filed by the 3 basin States, for constituting a Water Dispute Tribunal in the matter of sharing of surplus water available in Krishna River Basin, the Central Government constituted the new Krishna Water Disputes Tribunal on 02.04.2004. The officials of this unit have worked with full effort in assisting the Technical Committee constituted for giving necessary technical advice to argue effectively the right of the State and the legal team by providing necessary information from time to time during preparation for arguments before the Supreme Court and the Tribunals.

1.5 In the report given by the Krishna Water Disputes Tribunal-II on 30th December, 2010, fresh availability of water has been estimated and the State of Karnataka has been allocated 911 tmc. This is an additional quantity of 177 tmc., apart from the previous allocation of 734 tmc made by the Bachawat award. Apart from this, the order to utilize 303 tmc by increasing the height of Almatti dam from the existing 519.6 m to 524.256 m is an achievement of the State. The Krishna Water Decision Implementation Board has to be set up by the Union Government for implementation of KWDT orders, in which a representative of the State has to be nominated, as per the directions of the Tribunal.

1.6 The State of Andhra Pradesh has filed a SLP before the Supreme Court, challenging and opposing several points contained in the report of the Tribunal given on 30.12.2010.

1.7 After hearing the applications filed by the Party States seeking Explanation / Guidance and Clarifications on the Final Order given by the Tribunal under Sec.5(3) of the Act, the KWDT gave its Further Report containing Final Order on 29.11.2013. 34

1.8 Without modifying the allocations made by KWDT-I at 75% dependability (including return flow), the allocations made by KWDT-II under different dependabilities are as follows:

Maharashtra 585 tmc + 81 tmc = 666 tmc Karnataka 734 tmc + 173 tmc = 907 tmc Andhra Pradesh 811 tmc + 194 tmc = 1005 tmc Total 2130 tmc + 448 tmc = 2578 tmc

The State of Andhra Pradesh and Karnataka have filed SLP in the Supreme Court, seeking legal clarifications on several points contained in the Final Order and Further Report issued by the Tribunal on 29.11.2013. The 3 SLP’s including the SLP filed by Andhra Pradesh questioning the Tribunal Order of 30.12.2010 will be taken up for hearing on 21.07.2014.

2. GODAVARI WATER DISPUTES (O.S-4/2007):

2.1 The Godavari Water Disputes Tribunal (Bachawat Tribunal) constituted in April 1969 for adjudication of the water dispute regarding Inter-State River Godavari and the river valley thereof emerging from the letters of Andhra Pradesh, Mysore (now Karnataka), Maharashtra, Orissa and Madhya Pradesh States, gave its report on 27th November, 1979 by incorporating the bipartite / tripartite agreements entered by the Party States and Further (final) Report on 7th July 1980,. Only Manjra Sub-basin of Godavari Basin is in Karnataka and the State has a share of 22.37 tmc in Godavari basin.

2.2 As per the agreement in the final order of the Tribunal, by constructing Polavaram project by Andhra Pradesh, 80 tmc of Godavari waters can be diverted to Krishna basin. Karnataka can utilize 23 tmc (21 tmc + 10% regeneration) additional water in Krishna basin from the date of approval to Polavaram Scheme by Central Government. Schemes have been formulated to utilize this water.

2.3 The state of Orissa has filed an Original Suit (O.S.4/2007) before the Hon’ble Supreme Court, praying for stay of clearance given by the Government of India. The State of Karnataka has filed an impleadment application on the legal advice, for 35

intervening in the case since the availability of water to the State is affected by diversion of waters from Polavaram to according to the GWDT orders. There is no information about further hearings.

3. MAHADAYI WATER DISPUTES:

3.1 Malaprabha dam was constructed during 1972 across river Malaprabha at Naviluteertha, Belgaum district. In view of the reduction in the inflow of at the dam site, the meeting of drinking water needs of Hubli and Dharwad cities has become a difficult task. To overcome this difficulty, a scheme has been evolved to supply drinking water, by diverting 7.56 tmc of water to Malaprabha basin from Karnataka portion of Mahadayi basin.

3.2 Government of Goa kept on opposing the drinking water Scheme by stating that Mahadayi is a deficit river basin and by this, diversion will have adverse impact in Goa.

3.3 The Ministry of Water Resources, Government of India, on 30.04.2002, accorded ‘in principle clearance’, for this scheme. On account of the protest by Goa, Union Government kept the above clearance ‘in abeyance’ on 19th September 2002.

3.4 The States of Karnataka, Maharashtra and Goa submitted their complaint regarding distribution of Mahadayi River Waters to the Government of India. Based on the complaints, Government of India constituted Mahadayi Water Dispute Tribunal to resolve the issues on 16.11.2010. Accordingly the Original Suit O.S-4/2006 filed by the Government of Goa was dismissed by the Supreme Court in its order dated 20.01.2011. In order to argue effectively on behalf of State of Karnataka before the Tribunal, the Government has constituted legal team consisting of nine other advocates under the leadership of Sri. F.S. Nariman, Senior Counsel. The officers / staffs of this unit are working in a similar manner as done for Krishna Water Disputes Tribunal.

3.5 Proceedings before the newly constituted Tribunal began on 06.09.2012. During the hearing of the interlocutory application filed by State of Goa, requesting the Tribunal to restrain the State of Karnataka from constructing the projects in

36

Mahadayi basin, the Tribunal ordered the Party States to file their Statement of Case on 16.12.2012.

3.6 Accordingly, the States of Karnataka, Maharashtra and Goa have filed their Statement of Cases on 02.01.2013, 02.01.2013, 07.02.2013 respectively before the Tribunal. Replies and rejoinders are filed by the Party States.

3.7 On 21.08.2013 the Tribunal finalized 44 issues.

3.8 As per the order given by the Tribunal during the sitting from 22.10.2013 to 24.10.2013, site inspection of Mahadayi basin was taken up by the Tribunal and Party States from 12.12.2013 to 24.12.2013.

3.9 Proceedings before the Tribunal was resumed on 04.03.2014, the State of Goa was permitted to file the amended Statement of Case and interlocutory application. For this, the State of Karnataka filed its replies and State of Goa filed its rejoinders before the Tribunal.

3.10 Proceedings before the Tribunal will resume in April 2014.

4. PENNAR WATER DISPUTES (O.S.5/2003):

4.1 Andhra Pradesh has raised an Inter State Water Dispute in the matter of Minor Irrigation Projects of Tumkur and Kolar districts and Paragodu project drinking water supply scheme. It has filed Original Suit (O.S. No. 5/2003) before the Hon’ble Supreme Court and the arguments are under progress. In connection with the above matter Andhra Pradesh has proposed two witnesses. The Cross examination of the Andhra Pradesh witness have been completed. The Cross examination of the three witness from Karnataka also have been completed.

4.2 When the suit came for hearing on 03.09.2013 it was instructed to club the case along with Civil Appeal No.2453 which was filed before the Supreme Court in 2007 by the State of Karnataka challenging the order given by Cauvery Water Disputes Tribunal under Sec.5(2) of the ISWD Act, 1956. The next date of hearing is not yet fixed.

37

V. CAUVERY UNIT:

Functions of the Cauvery Unit:

1. Cauvery unit under WRDO renders technical assistance to the Advocates engaged by the State to appear on its behalf before the Cauvery water Dispute Tribunal and Supreme Court in respect of Cauvery Water Disputes work. This unit also prepares documents and other materials required in connection with the disputes.

2. This unit deals with the related correspondence with the Central Government and other State Governments.

3. Conducting Cauvery Technical Committee meeting, assisting the Government during all party meeting regarding Cauvery water dispute matter and attending meetings convened by the Central Government like Supervisory Committee, National Water Development Agency etc.

4. Preparation of documentation in connection with various articles available through published News Papers and websites in respect of Cauvery dispute works.

5. Furnishing of opinion to the Government on representations of public in respect of Cauvery water dispute work.

6. Collection and analysis of data in respect of Reservoir levels, storages, inflow, outflow, withdrawals etc.

7. Making arrangements for conferences with Senior Advocates at Bangalore & New Delhi.

8. In order to provide Technical support in all respects to the Legal Team regarding preparation of case, filing of pleadings, Interlocutory Applications, Special Leave Petitions, Original Suits and assistance during arguments etc., of Karnataka before the Cauvery Water Dispute Tribunal and the Supreme Court of India, an office was established and named as Cauvery Water Cell at New Delhi in 1990 and which is still functioning in the premises of Karnataka Bhavan-III (Bheema), HUDCO Place, Andrews Ganj, New Delhi. 38

Progress during 2013 -14

Before The Cauvery Water Disputes Tribunal:-

The Cauvery Water Disputes Tribunal rendered its Decision on 05.02.2007 which was notified by Government of India in the Gazette on 19.02.2013.

Before the Supreme Court:-

Aggrieved by the Final Order and Decision of the Cauvery Water Disputes Tribunal, the States of Karnataka, Kerala and Tamil Nadu filed Special Leave Petitions in the Supreme Court which were later on became to be numbered as Civil Appeal Nos.2453, 2454 and 2456 of 2007 respectively.

Tamil Nadu filed I.A. Nos. 5 of 2013, 6 of 2013 and 7 of 2013 in Civil Appeal No.2456/2007 seeking directions from the Supreme Court to direct Government of India to constitute Cauvery Management Board and Cauvery Water Regulation Committee to effectively implement the Final Order of Cauvery Water Dispute Tribunal.

As the Constitution of the Cauvery Management Board and the Cauvery Water Regulation Committee would take longer time to be established, State of Tamil Nadu insisted that there should be a mechanism for effectively implementing the Final Order and Decision of the CWDT. This led to the formation of the pro-tem Supervisory Committee by the Supreme Court.

The Supreme Court in its order dated 10.05.2013 directed Government of India to Constitute a Supervisory Committee for implementation of the Final Order dated: February 5, 2007 which was notified on February 19, 2013. Accordingly, Government of India constituted the Supervisory Committee on 22.05.2013.The Supervisory Committee has so far conducted four meetings regarding the flows to be made available by Karnataka to Tamil Nadu.

Tamil Nadu and Karnataka filed Written Submissions on 02.01.2014 and 03.01.2014 respectively. Supreme Court heard the Civil appeal nos.2453/2007(Karnataka), 2454/2007 (Kerala) 2456/2007(Tamil Nadu) on 15.01.2014 and ordered to list this group of matters

39

‘For Directions’ on March 12, 2014. Matter did not come up on that day, due to the Constitution Bench which was adjudicating the education matter.

Civil Appeals and related matters which are pending before the Supreme Court are yet to be listed for hearing.

Financial Aspects:

The total grants allotted for Cauvery, Krishna & other Water Disputes for the year 2013-14 is Rs. 1782.33 Lakhs, under Head of Account 2701-80-001-0-19 (Technical)-015 (Subsidiary Expenses). Out of total grant Rs. 917.40 lakhs, the amount released for Cauvery Water Dispute is Rs 294.40 Lakhs. The expenditure incurred during the year 2013-14 for Cauvery Water Dispute is Rs. 294.40 Lakhs.

COMMITTEE FORMED BY WATER RESOURCE DEPARTMENT

 Experts Committee for the Project planned for diversion of West Flowing River:

An Expert Committee is constituted under the Chairmanship of Sri. G.SParamashivaiah, Retd. Superintendent Engineer and Irrigation Expert vide Government order No:WRD 54 VibyaE 2010 (Part-4), Bangalore, dated: 23-11-2012 to provide technical assistance and guidance for preparing the road map for implementation and to finalise the Detailed Project Report for the project planned for diversion and utilisation of Potential flows of west flowing Rivers for drinking water and ground water recharge in drought affected area of Karnataka. This committee has conducted five meetings till date.

 Committee Constituted for Preparation of Revised Master Plan of Krishna Basin:

A committee has been constituted under the Chairmanship of Sri D.N. Desai, Retd. Secretary for a detailed review of the earlier Master plan and to prepare a revised master plan for effective utilization of the quantity of water allocated on Karnataka has under KWDT-I and II and the additional water which will be made available to the state after the completion of present ongoing proceedings under Section 5(3) of tribunal. The committee comprises of both official, non-official members. The Chairman of the Committee has submitted the report to the Government on 5-1-2013 for approval.

40

 Mahadayi Master Plan Committee:

In order to utilise maximum water in Mahadayi basin by diverting it into Krishna basin a committee has been constituted under the Chairmanship of Sri. J.R.K. Karadi, Retired Engineer-in-Chief to study and submit the Draft Master Plan to Government. Committee conducted several meetings and inspected the site. Master plan has been submitted to government on 10-12-2013.

 S.R.Committee:

The Schedule of Rates Committee for preparing the Schedule of Rates for the year 2013-14 was constituted by Govt., vide GO No.WRD: 112:KBN: 2013 Bangalore Dated 18/09/2013, with Sri. Shivashankar, Retired Secretary Irrigation Department and Chairman, Technical sub-committee, Cauvery Neeravari Nigama as the Chairman of the committee. The committee conducted four meetings for discussion and finalization of the draft S.R. for the year 2013-14 was submitted to the Government. The Schedule of Rates for the year 2013-14 was approved by the Government and brought into effect from 10-01-2014 vide GO No.WRD: 112:KBN: 2013 Dated 02/01/2013 in the Water Resources Department ( Major & Medium Irrigation) including all the three nigamas viz., Cauvery Neeravari Nigama Niyamitha, Karnataka Neeravari Nigama Niyamitha and Krishna Bhagya Jala Nigama Niyamitha and all other non-nigama zones.

 Expert Committee formed for identifying water resources to meet the long term

water requirement of Bangalore City.

A committee has been formed under the Chairmanship of Sri. B.N. Thygaraja, Retired Chairman, Bangalore Water Supply and Sanitation Board in the Government order dated: 25-11-2010. The committee is formed to formulate the project for meeting the water supply requirement of Bangalore city for the next 50 years as a long term measure. The committee is conducting meetings and working towards identifying the various resources available to meet the increasing requirement. The committee has conducted 25 meetings and submitted its final report to the Government.

41

(1) Inspection reports / Audit paras outstanding as on 31/03/2014: Inspection report in the beginning of 2013-14 : 24 Total No. of paras pending : 36 The details are enclosed in the Annexure-5

(2) Court Cases: No. of Court cases : 15 No. of cases finalised : 06 No. of cases under finalisation : 09

(3) RTI act 2005: W.R.D.O M&E No. of Application received : 105 04 No. of Application replied : 38 04 No. of Application rejected : 25 00 No. of Application transferred under 6(3) : 42 00

(4) Questions received from Assembly, Council and Parliament: Administrative Technical No. of LAQ : 08 30 No. of LCQ : 03 15 No. of Parliament questions : - 02

Draft replies for the above questions are submitted to the Government.

42

7. CENTRAL MECHANICAL ORGANISATION

INTRODUCTION :

The zone of Central Mechanical Organization, Bangalore has been established during 1984 and is functioning at present with the assistance of 3 divisions and 14 sub-divisions. The jurisdiction of the zone is state-wide & will be rendering suitable advice regarding mechanical aspects. The head of this organization is re-designated as Chief Engineer, Hydrology and C.M.O., Bangalore having its head quarter at Bangalore vide G.O. No: 27 SESAA dt: 23/9/1999. This report consists only that of the activities of C.M.O.

1. The main duties and functions of the organization are briefly as follows:

i) Inspection of sick machinery in the Public Works and Water Resource Department and scrutiny / sanction of repair estimates. ii) Disposal of surplus and unserviceable machinery. iii) Rehabilitation of surplus vehicles / machinery. iv) Review of efficiency and performance of machinery.

The Central Mechanical organization is striving hard to achieve the above objectives since its inception and the report on the achievements during 2013-14 is as follows: 2. In order to ensure optimum utilization of machinery, available in Public works and Irrigation department, the monthly returns of machinery of divisions are being obtained and reviewed regularly for its various performance aspects such as: a) fuel usage b) oil usage c) Kms. Run with reference to standards fixed d) idleness surpluses and rehabilitation e) sick vehicles / equipments identification and its speedy repairs f) disposal of unserviceable machinery are reviewed and follow up action ensured until their disposal through Central Mechanical Organization.

Major regulatory functions:- To oversee that all the working vehicles/equipments of the department are put to optimum use sick vehicles / equipments are repaired with minimum downtime, economically and for unserviceable vehicles / equipments assist owning departments for the disposal expeditiously to the best advantage of the Government. 43

Principal Laws / Enactments being enforced:- The codal rules, the manual of contingent expenditure, delegation of financial powers as applicable to PW & Irrigation departments are being followed and also the Government orders issued from time to time.

Strategies for achieving the Departmental objectives:-

1. In order to achieve the above objectives, the monthly returns of machinery, along with requirement and surplus availability details are got regularly from Civil divisions and the same is reviewed. For this purpose presently, computer is being made use of.

2. To exercise economy in carrying out repairs, the estimates so got up is either sanctioned or scrutinised after thoroughly reviewing it. To exercise and review the condition of machinery and also up keeping of driving licence, insurance cover, Registration certificate, Fitness certificate etc., by conducting surprise inspections and bringing the lapses to the knowledge of Government.

3 To exercise economy in the fuel and oil consumed by the vehicles/equipments, standard rate of consumption is being stipulated and strictly being enforced.

4 To review the optimum utilization of the available machinery and at the same time arrange for the requirement from out of the surplus availability so that unnecessary purchase is avoided.

5. To monitor the disposal of unserviceable machinery so that the same are expeditiously disposed off to the best advantage of the Government.

6. Apart from the Irrigation & PW Departments, this organization assists other Government departments in inspecting sick machinery, repairing the same or scrutinizing the estimates prepared thereby.

44

Major Developments / Highlights of the year:-

Apart from the routine repairs works carried out by the sub-divisions of this organization, surprise inspections of vehicles/ equipments are conducted in order to prevent under logging and proper upkeep of the documents of vehicles and such instances if any, are being reported to Government. Achievements during 2013-14:

Sl. Particulars Achievements No. In nos.

I Repairs to Machinery / Equipment (Major and Petty repairs)

1. Opening balance as on 01.04.2013 227 2. Receipts 2275 3. Total 2502 4 Repaired and Dispatched (Includes 40 major repairs) 2268 5 Closing Balance 281

II. Inspections

Total Number of Inspections carried out 280 Recommended for repairs 141 Recommended for scrap 139

III. Repairs Estimates

1 Opening balance of estimates - 2 Total number of estimates received 141 Amount (in Lakhs.) Rs. 285.01

Estimates for which Scrutiny certificates are issued. 10 Amount (in Lakhs.) Rs. 9.52 Number of Estimates Sanctioned 131 Amount (in Lakhs) Rs.275.49

IV) In the process of major repairs to vehicles, useful assemblies and accessories of scrapped vehicles were identified and utilized on repairs. V) This organization is also inspecting vehicles / equipment pertaining to Boards / Corporations and Central Government after levying inspection fees. VI) Review has been taken up regarding expenditure incurred on repairs and time taken for such repair in workshops. After detailed review limit has been fixed for expenditure to be incurred on repairs and time limit for carrying out repairs.

45

4) Disposal of surplus and unserviceable machinery Disposal of unserviceable machinery in Water Resources & Public Works Department which have been recommended for scrap during routine course of inspection.

1) Unserviceable machinery identified for disposal during 2013-14 - 139 Nos. 2) Disposed during 2013-14 267 Nos. Revenue Realized Rs. 1,05,98,078/-

PROMOTION , TRANSFERS , POSTINGS IN BRIEF:- The promotion up to the cadre of Junior Engineers is being done by the Chief Engineer, Communication and Buildings (South), Bangalore on the basis of the seniority list pertaining to PW and Irrigation Department. From the Cadre of Assistant Engineers and the above promotions are being issued at Government level. For group ‘ D ‘ employees the seniority list will be prepared by Superintending Engineers of PWD circles and the promotions are being issued on the basis of these seniority lists. The Chief Engineer, W.R.D.O., Bangalore is the implementing officer for transfer in respect of Irrigation Department.

PROGRAMME AND PROGRESS:- The programme and progress of workshops carried out is detailed below: ------Programme Progress ------Major Repairs and Minor Repairs 120 36

Petty Repairs 3600 2232

NOTE:- Even though programme is drawn out , it mainly depends upon the inflow of machinery for repairs which cannot be predicated in advance . However the progress is monitored monthly and suitable action is being taken whenever lapses are observed. Major Hurdles :- Even though C.M.O. is exclusively created and entrusted with the task of repairing the sick machinery, it is observed that many civil divisions are not observing the instructions issued by Government i.e., the vehicles are not sent to Government C.M.O., workshops for repairs. On the other hand, repairs are carried out by the civil divisions themselves, depriving the C.M.O. from performing its functions. REMEDY:- It is proper to utilize the Mechanical Engineers and Mechanical staff under C.M.O. to the optimum capacity. The Government may issue instructions to the Heads of 46

different departments to get the repairs of their vehicle / equipments in C.M.O., workshop only. Also proposal to stay the organization has also been submitted to Govt. Proposal regd. Re-strengthening of CMO has also been submitted to Govt. as suggested by A.G. if proper orders are issued optimum utilization of services of technical staff can be ensured. Filling up of vacancies:- Since the origin of this organization the vacancy position in key technical posts like Assistant Engineers, Junior Engineers, Mechanics and Foremen have not been filled up fully at any point of time. As on date the percentage of vacancy in these cadre is as under. Sanctioned Working % of Vacancy Strength Strength Assistant Engineer 58 40 68.96% Junior Engineers 46 31 67.39%__

Remedy:- From the above, it could be made out that without full cadre strength, works cannot be carried out to the optimum capacity.

V. CONCLUSION:- Viewing the aims, functions and the achievements of the C.M.O., it is imperative that this organization needs to be strengthened and due encouragement with all the necessary co- operation from the various Civil Divisions has to be imparted to it to achieve ever lasting results in the up-coming of the organization.

47

8. KARNATAKA ENGINEERING RESEARCH STATION, K.R.SAGAR

Objectives and organization structure

Karnataka Engineering Research Station was started during 1944 as a small Research Unit. The Research Station, which forms a wing of the State Water Resources Department, had a phenomenal growth and today it is one of the oldest Research Organizations of its kind in the country. The main objectives of the Research Station are to find solutions to various problems encountered by the field Engineers in Civil Engineering discipline. The Research Station has solved many intricate problems posed by Public Works Department, Water Resources Department, other Civil Engineering Departments and other agencies.

The Director of the rank of Chief Engineer heads the Research Station. He is assisted by the Joint Director, who is also the Principal of Engineering Staff College, which is a wing of K.E.R.S. The activities of the Research Station are grouped into 4 divisions as under.  Hydraulics Division  Technical Services Division  Soil Mechanics & Foundation Engineering Division  Coastal Engineering Division

Hydraulics Division:

Model studies of various components of irrigation & power projects like spillway and energy dissipating arrangements, assessment of carrying capacity of canal system by backwater computation, gauging of canals, calibration of current meters, capacity evaluation of reservoir by conventional hydrographic survey as well as remote sensing techniques are the studies entrusted to this division.

Technical Services Division:

This division is entrusted with the work of conducting, non-destructive tests on cement, concrete, mix design, tests on steel, sand and coarse aggregate etc. Tests are conducted on water samples, cement, mortar and concrete samples for chemical analysis,

48

collection of daily rainfall and hydro-meteorological data, maintenance of buildings and quarters of KERS, maintenance of library are other works entrusted to this division.

Soil Mechanics & Foundation Division:

This division is involved in the investigation of foundation of earthen dams, suitability of soil for earthen embankments, computation of S.B.C., investigation of foundation of proposed buildings, bridges and other water resources structures. Studies referred by Government departments and other agencies for evaluation of sub grade suitability, road construction materials, investigation of causes for failure of roads etc., are studied and solutions are evolved. Further, the properties of rocks are determined for finding their suitability for construction works.

Coastal Engineering Division:

The main objectives of this division are to investigate the causes of coastal erosion along coast line of Karnataka, collection of field data and suggest remedial measures to contain coastal erosion and conduct model studies if necessary. Also pre monsoon and post monsoon monitoring of sea walls and monthly monitoring of sea walls constructed by Port Authorities are being done by this Division.

Through the above Divisions, the Research Station has been playing a key role in solving many Engineering problems in the field of hydraulics, concrete, building materials, soil, rocks and problems connected with roads, sea erosion etc.

Dam Safety Cell-1 and Dam Safety Cell-2 : Two units viz Dam Safety Cell-1 and Dam Safety cell-2 are working in the Research Station under the direct control of the Director, K.E.R.S. The Cells are headed by Assistant Executive Engineers supported by technical staff who assist the Director, KERS., in carrying out the functions as, Member of the National Committee on Dam Safety constituted by the Government of India, Member Secretary of the State Level Dam Safety Committee in Karnataka, constituted by the Government of Karnataka and also in placing the issues connected with the “Technical Preparedness of the whole State on the Dam Safety bill 2010” before the SLDSC and to finalize the same before the enactment of the Act.

49

Creation of Dam Safety Organisation:

Proposals for creation of Dam Safety Organisation to carryout the functions as enumerated in the “Report on Dam Safety Procedures” published by CWC and also to fulfill the requirement and statutory obligations under “Dam Safety bill 2010” is under consideration of the Government.

Engineering Staff College:

The Engineering Staff College conducts mainly three types of training Courses.

1. Orientation Courses for newly appointed Assistant Executive Engineers for a period of six weeks and for newly appointed Assistant/Junior Engineers for a period of four weeks. 2. Short term refresher courses of five days duration of both technical and administrative nature for the in-service Engineers. On Special circumstances these courses will be extended up to ten days. 3. Short term refresher courses of five days duration of administrative nature for the administrative staff. 4. Basic Computer Course for a period of 12 days for the in-service Engineers and administrative Staff.

Chapter 2.0: Achievements of the last two years and the year of reporting

As Karnataka Engineering Research Station is functioning as a service zone, construction or maintenance of projects does not come under its jurisdiction. Also it is not a major revenue earning zone. The financial and physical progress/achievements of research wing and Engineering Staff College are furnished below.

Financing (Rs in Lakhs )

Actual/accounts 2011-12 RE 2012-13 BE 2013-14

Capital Revenue Capital Revenue Capital Revenue

24.19 13.65 17.00

50

Expenditure (Rs in Lakhs ) :

Actual/accounts 2011-12 RE 2012-13 BE 2013-14

Capital Revenue Capital Revenue Capital Revenue

------

This format is not applicable to this Institution. The Grant allotted (Works Portion) and expenditure incurred by KERS including Engineering Staff College is furnished.

2011-12 2012-13 2013-14 Remarks

Grant Expenditure Grant Expenditure Grant Expenditure allotted incurred allotted incurred allotted incurred Non plan 92.37 76.31 96.17 73.44 78.66 72.83 plan

216.00 60.65 266.00 86.54 205.56 200.59

Physical Achievements :

2011-12 2012-13 2013-14 Two key Audit observations/Inspection findings of the year (Specify date of Audit/Inspection and the Reference no of the report; specify, if no audit or inspection was carried out.)

Details Details Details furnished Details furnished separately furnished furnished separately separately separately

Year 2011-12 :

During the year 2011-12, 254 Nos. of studies covering Hydraulic studies, Rating of current meters (51 Nos), Gauging of canals, Capacity evaluation of reservoirs, Testing of Building Materials, Soils, Water quality testing, monitoring of sea walls, design of sea wall sections etc., referred by different agencies have been completed and reports sent to 51

concerned authorities and 21 studies are under progress. 14 studies are held up for want of details from project authorities.

Under Hydrology Project 49 studies were completed on the 49 samples received at the water quality lab, K.R.Sagara. In the lab at Munirabad, 20 studies were completed on the 20 samples received for the stipulated 27 parameters.

During the year 7 Nos. of Orientation courses, 7 Nos. of short term courses and 9 Nos. of Special Training Courses were conducted and 1045 candidates were trained. Further 26 CEP courses, 4 SCP Courses and 1 TSP Course were conducted and 463 candidates were trained. Totally 1508 candidates were trained during the year up to end of 31st March 2012

Year 2012-13:

During the year 2012-13, 258 Nos. of studies covering Hydraulic studies, Rating of current meters (44 Nos), Gauging of canals, Capacity evaluation of reservoirs, Testing of Building Materials, Soils, Water quality testing, monitoring of sea walls, design of sea wall sections etc., referred by different agencies have been completed and reports sent to concerned authorities and 23 studies are under progress. 6 studies are held up for want of details from project authorities and another 4 canal gauging works has been held up, as the Project authorities have not provided necessary infrastructure at the selected gauging sites.

Under Hydrology Project 47 studies were completed on the 47 samples received at the water quality lab, K.R.Sagara. In the lab at Munirabad, 16 studies were completed on the 16 samples received for the stipulated 27 parameters.

During the year 3 Orientation courses for the Probationary AEE’s, 6 short term courses for Minor Irrigation Engineers and 19 short term institutional courses were conducted and 660 candidates were trained. Further 35 CEP courses, 5 SCP Courses and 1 TSP Course were conducted and 554 candidates were trained. Totally 69 courses were conducted and 1214 candidates were trained during the year up to end of March 2013.

52

Year 2013-14 :

During the year 2013-14, 214 Nos. of studies covering Hydraulic studies, Rating of current meters (26 Nos), Gauging of canals, Capacity evaluation of reservoirs, Testing of Building Materials, Soils, Water quality testing, monitoring of sea walls, design of sea wall sections etc., referred by different agencies have been completed and reports sent to concerned authorities and 23 studies are under progress. 3 studies are held up for want of details from project authorities and another 3 canal gauging works has been held up, as the Project authorities have not provided necessary infrastructure at the selected gauging sites. 3 studies have been dropped.

Under Hydrology Project, analysis was conducted on 43 samples, received at the water quality lab, K.R.Sagara. In the lab at Munirabad, analysis was conducted on 11 samples for the stipulated 27 parameters.

During the year 10 Orientation courses and 4 short term courses were conducted and 495 candidates were trained. Further 26 CEP courses, 5 SCP Courses and 3 TSP Course were conducted and 400 candidates were trained. Totally 48 courses were conducted and 895 candidates were trained during the year up to end of March 2014.

Important studies / works undertaken during the Year :

. The design report for providing of the permanent sea wall in Hosabetta near Bykampadi village of Mangalore Taluk at 25.975 KM to 26.150 KM, 26.225 KM to 26.275 KM, 26.300 KM to 26.325KM and 26.350KM to 26.400KM ( totally 300.00 meters) has been submitted to Executive Engineer, Port and Fisheries Division udupi. . The reports pertaining to design of sea wall ; from Chainage 136.600KM to 136.687Km of Shiroor, Kulihitlu town ; from Chainage 130.971KM to 131.057KM of Paduvari town ; from Chainage 48.200KM to 48.285KM , 48.110KM to 48.195KM, 48.350KM to 48.435KM of Tenkayermal ; from Chainage 68.689KM to 68.767KM Kidiyur, padukere ; from Chainage 77.750KM to 77.837KM Hooda Pradesha kooraga in Udupi; from Chainage 34.00KM to 34.300KM & from Chainage 34.590KM to 34.890KM of Shasihitlu town in Mangalore have been submitted to Executive Engineer, Port Division, Udupi

53

. Post monsoon monitoring of 21 sea walls in Bhatkal Taluk, 27 works in Kumta and 32 works in Honnavara Taluk were completed. . Effect on quality of river water due to return flow from irrigated land ( Cauvery River between K.R.Sagara and T. Narasipura ) is being finalised. . Study on evaluation/assessment of properties of concrete using manufactured sand and natural sand is in progress. . A new basic study to analyse the quality of ground water in Bilikere Grama Panchayath limit of Hunsur taluk has been taken up and is in progress. . A regional flood frequency study encompassing 43 gauge stations of the entire Cauvery basin in Karnataka was completed and got reviewed by NIH Belgaum. . A regional flood frequency study encompassing 138 gauge stations of the entire Krishna basin in Karnataka was completed in the lines of Cauvery basin study and got reviewed by NIH Belgaum. . A regional flood frequency study encompassing 23 gauge stations of the West Flowing River Basin in Karnataka was completed and got reviewed by NIH Belgaum. The above three research reports ultimately help in preparation of a flood manual for Karnataka after Validation of the recommended Regional Flood equations. Validation aspects are to be finalized and taken up in the forth coming years, in association with the WRDO Bangalore . Design flood studies of three MI Tanks referred by MI department have been scrutinized and findings have been submitted to the authorities. . Design Flood Study of Tonnur Tank, referred by CNNL has been completed and report submitted. . Rain Fall Data of 262 rain gauge stations located in Cauvery Basin has been analyzed by L-Moment Method and fitting 5 different 3-parameter distributions viz., GEV, GLO, GPA, LN3 and PE3 to find extreme values of different return periods. Thiessen Polygons of the Rain Gauge network and Isopluvial maps of precipitations of different return periods for Cauvery Basin have been prepared based on the locations of RG stations and estimated extreme values. . Model study for energy dissipation arrangement of Devarabilikere pickup project is in progress. . Model study on gate operation schedule for Upper Tunga Project is in progress.

54

. Model study for the construction of bridge cum barrage across Bhima river near Jholathadagi, of Yadgir Taluk in Gulbaraga was completed and interim report submitted to Chief Engineer, KBJNL, Bhimarayanagudi. . Study on radial crest gate operation schedule of is in progress. . Gauging of Tungabhara LBC at M-47, M-60, M-69and Ch.28 was completed and report submitted to the concerned authorities. . Gauging of Turvekere and distributary canal at 175m and 340 m was completed and report submitted to the concerned authorities. . Gauging of Tumkur branch canal at ch. 30324m, 32510m and 62700m coming under Hemavathy LBC would be taken up after the project authorities provide necessary infrastructure. . Gauging of Vishveshwaraiah link canal at ch. 37 km and 27 km coming under Hemavathy LBC would be taken up after the project authorities provide necessary infrastructure. . Gauging of Hemavathy LBC at Ch. 181.85 km and 182.30 km near Nagamangala Taluk would be taken up after the project authorities provide necessary infrastructure. . Gauging of D.Devaraja Urs canal at various chainages were completed and report submitted to the concerned authorities. . Gauging of Pandavapura branch canal at ch. 153.025 km coming under Hemavathy LBC was completed and report submitted to the concerned authorities. . Study to assess the improvement in efficiency of major canals in Karanataka after their modernization was taken up. Initially the canals coming under TLBC would be studied and subsequently the study on other canals would be taken up.

. Study to assess the source of silt in Tungabhadra reservoir is being initiated and shortly expression of interest would be notified. . Test on embankment soil sample of Vishnusamudra Tank (Ch. 500.00 to 950 m) near Kadur taluk, Chikamagalore district is completed and report will be sent after the payment of testing charges. . Test on embankment soil sample of Hemavathi left canal branch at chainage 614.00m near Nagasamudhra tank is in progress. . Test to determine SBC of soil sample for construction of office building of the Executive Engineer, CNNL, D&I Division, is in progress.

55

. Test on CBR for NABARD road work referred by AEE, CNNL, sub division, Pandavapura is in progress. . Test on road aggregate & bitumen for road under NABARD connecting Bangalore- Mysore Sri-Rangapatana KRS road near 10th mile of RBLL in Sri-Rangapatana taluk, Mandya district referred by AEE, CNNL, Gauging sub division, K.R.Sagar is in progress. . Test on road aggregate & bitumen for road under NABARD connecting Naganahalli village on Bangalore-Mysore road to Lakshmipuram village in Mysore taluk referred by AEE, CNNL, Gauging sub division, K.R.Sagar is in progress. . Test on soil sample of Our lady of victory church, Somavarpet, Kodagu district was completed. . Determining of Swell pressure on soil sample of Kattepura right bank canal CC lining report was sent to the concerned. . Test on soil sample pertaining to Karnataka Housing Board, Saraswathipuram, Mysore, MIG No. 59 was completed. . Soil test report regarding construction of bridge near Madavamanthri canal at Kukure distributary canal at chainage 0.500, 1.400, 2.200 was sent to the concerned. . Report on testing of soil samples for the Construction of 5 lakh litres of capacity GLSR tank near Kadakola, Mysore, was sent to the concerned.. . Soil test for the new hostel building foundation at KERS was completed. . Test on foundation soil for construction of Government first grade college, Koppa, Maddur taluk, referred by Arun construction was completed. . Test on soil samples for the construction of building at Shree Sai Erators pvt ltd., at Hebbal Industrial area, Mysore was completed. . APMC two package roads, Gundalpet regarding improvements to road:-Quality control result completed and final report was sent to the concerned. . Testing of aggregates and bitumen used for the asphalting work of Basaralu road referred by AEE, No.32, HLBC, CNNL was completed. . CBR test pertaining to oad development work between Tumbasoge and Itna village referred by AEE, Kabini Reservoir Sub Division, CNNL was completed. . A study on improving the strength of soil in Varahi Project area is in progress. . A study on Black cotton soil sample by mixing lime and Rock Dust is in progress.

56

. A study on improving CBR value of Varahi soil sample by mixing admixture is in progress. . For the year 2013 -14 a grant of Rs. 190.56 lakhs was sanctioned to KERS under the head of account 2701-80-004-1-05 plan, survey works. With this grant the following works were carried out ; landscaping work in front of the ESC office and hostel building , construction of open type dining hall in the hostel and construction of semi field gauging demonstration channel in Brindavan area. The construction of new hostel building is in progress.

Activities of Dam Safety Cell-1 :

The Dam Safety Cell is assisting the Member Secretary, State Level Dam Safety Committee in Karnataka in the following activities in respect of Dam Safety issues: 1. Communicating the deficiencies observed in the Health Status reports of Large dams to the Chief Engineers, concerned.,

2. Preparation of Health Status Report of Large Dams in Karnataka to place the same before the State Level Dam Safety Committee in Karnataka.

3. Finalisation of the draft compliance for the minutes of the National Committee on Dam Safety.

4. Finalisation of the Additional Note on Agenda for the ensuing meeting of NCDS.

5. Pursuing the Chief Engineers in-charge of large dams to send the following.

a) Pre/Post monsoon Inspections reports of Large dams

b) Compliance to the minutes of the NCDS.

c) Other details keeping in view the proceedings of NCDS / SLDSC and the “Terms of reference of SLDSC”.

6. Correspondence pertaining to DSRP and DRIP (Dam Rehabilitation and Improvement Project).

Activities of Dam Safety Cell-2 :

The Dam Safety Cell-2, attached to the Director, Karnataka Engineering Research Station, comprising of One Assistant Executive Engineer, including 3 Assistant Engineer’s, 3 Junior Engineer’s and supporting administration staff has been created by the Government, vide Government Order No. WRD-60 /¸ÉøÀJ / 2009 dt: 06-07-2009 ( read with modification 57

letter No. WRD 60 /¸ÉøÀJ / 2009 dt: 03-08-2009), is assisting the Member Secretary, State Level Dam Safety Committee(SLDSC) in Karnataka, in carrying out the following functions from 01-06-2009.,

 To prepare the Agenda Notes for the meetings of the State Level Dam Safety Committee (SLDSC) before the meeting and to prepare the Draft Proceedings after the meeting and to submit the same to the Government for confirmation  Communicating the copies of the approved proceedings to all the concerned and to pursue them for communicating compliance.  To pursue with all the concerned to communicate the “Technical Preparedness” of the zone / organization ( as appropriate) for the Draft Dam Safety Act and to place the same for discussions before the special meeting of State Level Dam Safety Committee (SLDSC) to finalise the Technical Preparedness of the whole State for the “Dam Safety Bill-2010”.  To place the issues pertaining to the following for discussions in the Special Meeting of State Level Dam Safety Committee (SLDSC), viz., a) Action to be taken at various level after the enactment of the “Dam Safety Act”.

b) Action to be taken at various levels regarding the “Public Interest Litigations” (if any).

Meeting at National level: The National Committee on Dam Safety has conducted 32 meetings so far. The 31st Meeting of National Committee on Dam Safety was conducted on 13-07- 2012 at New Delhi. The CWC, Delhi has sent the proceedings of the said meeting vide letter No. 3/ 19/ NCDS/ DSM /31st meeting/ 2012: 553-581 dt. 01-08-2012. The Compliance to the minutes of 31st NCDS meeting was submitted to Central Water Commission, New Delhi duly after seeking the considered opinion of Government.

The 32nd meeting of NCDS was held on 27-12-2013 at New Delhi. The minutes of the meeting received from Central Water Commission, New Delhi has been communicated to all Chief Engineers in-charge of Large Dams with request to communicate the compliance to the said minutes vide ltr No. 4676-97 dated: 03-02-2014.

58

Review of Health Status Report of Large Dams in Karnataka:

The “Health Status Report of Large Dams in Karnataka”, are to be submitted to Government and to CWC, New Delhi, in the month of April every year (as per the minutes of the National Committee and Dam Safety). In this connection, it is to state that, the inspection reports of Large Dams are to be reviewed in its totality, by the Dam Safety Organisation. At present there is no Dam Safety Organisation in Karnataka State. The “Health Status Report of Large Dams in Karnataka for the year 2011 and for the year 2012” was placed before the 24th meeting of the State Level Dam Safety Committee in Karnataka held on 04-04-2014 at Bangalore. The same will be submitted to the Central Water Commission, New Delhi in the stipulated format.

. Progress Achieved By Engineering Staff College during the year:

During the year 10 Orientation courses and 4 short term courses were conducted and 495 candidates were trained. Further 26 CEP courses, 5 SCP Courses and 3 TSP course were conducted and 400 candidates were trained. Totally 48 courses were conducted and 895 candidates were trained during the year up to end of March 2014. .

No.of courses Sl. Category of training No.of persons conducted upto 31st Remarks No programme trained March 2014

1. Institutional courses 14 495

2. CEP 26 3. SCP 5 400 4. TSP 3 Total 48 895

59

2.3.4 Audit observations / Inspection findings: Audit inspection party has conducted audit inspection of Technical Services Division and SSWBO Sub Division of KERS for the period 2009-10 to 2012-13 from 24.03.2014 to 02.04.2014.

Audit paras as existing upto end of March 2014 39 No of cleared audit paras - Balance to be cleared 39

Following list illustrates the numbers of officers/staff who have attended training programmes. (a) Training programmes within State : No of Details of training programmes. officers/staff attended Training programme on World Bank procurement procedures under DRIP 8 held at Bangalore from 21-02-2014 to 22-02-2014 Recent Advances in Geotechnics for Infrastructure (RAGI 2014)” held at 10 SJCE, Mysore on 15-03-2014 HRMS training held at DTI, Mandya on 19-07-2013 1

Computer training held at DTI, Mandya from 10-06-2013 to 14-06-2013 3

Basic Computer Course held at E.S.C., K.E.R.S., K.R.Sagara. from 1 16-09-2013 to 28-09-2013 Symposium on CFD application in water engineering held at Bangalore on 2 01.06.2013 Workshop on Integrated water resources management for officers from water resources department and related water supply departments at ATI on 1 05.06.2013 Office automation course in JNN College of Engineering, Shimoga from 03-06-2013 to 07-06-2013. 1

60

(b)Training programmes outside State : No of Details of training programmes. officers/staff attended Water Quality Monitoring Techniques” held at CWRDM, Kerala from 2 19-11-2013 to 23-11-2013 Two day workshop on Design Flood Issues held at New Delhi from 2 19-11-2013 to 20-11-2013

Photos of Orientation Programme

Orientation Programme

61

Orientation Programme

62

9. WATER AND LAND MANAGEMENT INSTITUTE (WALMI)

Introduction: To maximize returns from investments made in irrigation projects in the State, it is necessary to manage water and land in a systematic and scientific way. This requires capacity building of Government Staff as well Water Users. To meet these capacity building needs, Water and Land Management Institute (WALMI) started functioning at Dharwad on 12-5-1986 and was later registered as a Society under the Karnataka Societies Registration Act, 1960 on 16.06.1986. WALMI: imparts training; renders technical assistance, advises Government on legal, policy, organizational and procedural changes; organizes demonstrations in collaboration with other organizations; conducts special studies and brings out publications.

Training: WALMIs training activities focused on the training required for implementation of the State Water Policy and the Irrigation Sector Reforms. Special emphasis was laid on training on Participatory Irrigation Management, Water Management and Land Development. Office bearers of Water Users Cooperative Societies throughout the State as well as some farmers were also trained by WALMI. As against a target of 2940 persons to be trained, 3451 persons were trained during.

Technical Assistance: WALMI rendered technical assistance to the Water Resources Department and organizations coming under the Department on implementation of State Water Policy, Participatory Irrigation Management and necessary legal and policy changes.

Demonstrations in Collaboration with the University of Agricultural Sciences, Dharwad: Demonstrations pertaining to irrigation methods for different crops- Cotton, Soyabean, Paddy, Sunflower, Wheat, Maize, Groundnut, Guava, Mango, Sapota and vegetable crops were laid. Water saving technolgies like drip, sprinkler and Raingun were demonstrated in the WALMI Farm to support training activities. 63

Action Research: As per orders issued in Government Order No. WRD 14 CAM 2009, dated 02.12.2009, action research on participatory and sustainable water and land management is undertaken in selected distributaries of the Malaprabha and Ghataprabha projects. A support group comprising of all departments concerned with irrigated agriculture is constituted to implement the project. The activities are coordinated by the Director, WALMI.

Financial Progress: During the year, WALMI received Grant-in-aid of `.172.00 lakhs under Command Area Development. Total expenditure of `.174.44 lakhs was incurred during the year up to end of March 2014.

64

PROJECTS UNDER

KRISHNA BHAGYA JALA NIGAM LIMITED

65

10. HIGHLIGHTS OF KRISHNA BHAGYA JALA NIGAM LIMITED FOR THE YEAR 2013-14

10.1 1. Upper Krishna Project Stage – III: Upper Krishna Stage-III is contemplated to provide irrigation for 5.30 lakh Ha. command area coming under Bijapur, Bagalkot, Gulbarga, Yadgir, Raichur, Koppal and Gadag Districts of Northern Karnataka. The progress of project sub-components under UKP Stage-III including R&R & LAQ and BTDA have been expedited during 2013-14. During 2013-14 an expenditure of Rs.914.83 Crores has been incurred for implementation of UKP Stage-III Project. Irrigation Potential of 14,145 Ha. is created under UKP Stage-III Projects (Chimmalgi, Indi, Rampur & Mallabad LIS). The progress achieved under UKP Stage-III Project implementation during 2013-14 are as under: A. Mulwad LIS : a) Head Works of Mulwad LIS Stage–III viz; (a) Balance electro- mechanical works at Baluti 1st Head Work, (b) Balance civil and electro-mechanical works at Hanumapur 2nd Head Work, and (c) 3rd Head Work at Masuti are in advance stage of progress.

b) Lead–off Canal of 5.50 Km length between 1st & 2nd Head work of Mulwad LIS and the Combined Canal of 1.175 Km to cater the 2nd Jackwell Cum Pump House discharge for 2.27 Lakh Ha. under at Hanumapur of Mulwad LIS Mulwad LIS Stage-III works awarded and commenced.

c) Tenders invited for initial 10 Km reach of both Bijapur & Malghan Main Canals of Mulwad LIS Stage-III.

d) Estimates for 4th-A Lift on Malghan Canal & for and for further KMs of Main Canals of Bijapur & Malghan Canal are under finalization.

66

B. Chimmalagi LIS : a) Water let out in the completed Combined Canal of 2.10 Km, West Canal Km 0.00 to 20.00 & East Canal Km 0.00 to 13.00 including Distributaries to provide irrigation for 2,473 Ha.

b) West Main Canal Km 20.00 to 51.92 and East Main Canal Km 0.00 to 50.00 completed. East Main Canal from Km 50.00 to 90.00 awarded in 4 Packages and works commenced. Tenders Chimmalgi LIS East Main invited for East Main Canal Km 90.00 to 132.261(including Aqueduct for Don River Crossing).

c) Estimates for initial 10 Km reach of Korwar & Nagthan Branch Canals (beyond Don River crossing) finalized.

C. Indi LIS ( Basavanna) :

a) ILC Main canal Km 97.30 to 120.00 including Major Aqueduct completed and water let out for first time and irrigation provided for 4,183 Ha.

b) ILC Main Canal Km 120.00 to 147.00 awarded in four packages and works commenced.

c) The scheme is planned for Completed Aqueduct from KM completion during 2014-15. 110.00 o 113.00 of ILC

D. Rampur LIS :

(a) Works of extension of East Main Canal from Km 20.00 to 27.00 including Disty.No.10 and 11 are completed.

(b) Tail end Distributary works from Km 0.00 to 35.00 is under progress.

(c) The Scheme is almost Aqueduct in Tail End Distributary completed. of Rampur LIS 67

E. Koppal LIS :

(a) 1st and 2nd Head Works awarded on turnkey basis and works are in progress.

(b) Consultancy work of detailed survey investigation, preparation of design, drawing, estimate and bid document for adopting Micro-irrigation System under Koppal LIS is commenced.

F. Herkal LIS :

(a) Construction of Head works of Herkal (North) and Herkal (South) LI Schemes awarded on turnkey basis and works commenced.

G. NRBC Extension:

(a) The works of extension of NRBC Main canal from Km 95.00 to 125.00 awarded under 6 packages and works have been commenced.

(b) Consultancy work of detailed survey investigation, preparation of design, drawing, estimate and bid document for NRBC Main Canal from Km 125.00 to 168.00 is in progress.

H. Mallabad LIS :

(a) 1st Head Work of Mallabad LIS at KM 20.90 of JBC near Balabatti village awarded on turnkey basis is almost completed. Also, Main Canal KM 0.00 to 4.00 under Lift No.1 is completed.

(b) 2nd and 3rd Head works of Mallabad LIS at KM 20.00 on MBC and at KM 5.40 of SBC respectively awarded on turnkey basis and works are in advanced stage of progress.

(c) Main Canal KM 0.00 to 10.00 coming under 2nd and 3rd Head Works of Mallabad LIS awarded in packages are in progress.

(d) Power Line work for Lift No.1 of Mallabad LIS is in progress.

I. Rehabilitation Resettlement, LAQ and BTDA works under UKP Stage-III:

(a) For the increase in storage of water at Almatti Reservoir upto RL 524.256 m, 94,000 Acres of land is to be submerged and the FRL Survey for the same using LiDAR Technology is completed. Further, as per the new Land Acquisition Act, land acquisition is initiated for 14,257 Acres of land.

(b) The work of base-line socio-economic survey and preparing R&R frame work for UKP Stage-III through consultancy is completed.

(c) To review and accelerate the land acquisition and R & R works due to raising of Almatti dam upto RL 524.25 Mt., a High Power Committee under the Chairmanship of Hon’ble Chief Minister is constituted vide GO dated 29.10.2013 and the 1st meeting of the High Power Committee was conducted on 12.12.2013 under the Chairmanship of Hon’ble Chief 68

Minister, GOK. Also, the 1st meeting of Action Plan Review Committee constituted under the Chairmanship of Chief Secretary to Government on 16.01.2014.

(d) In the Action Plan Review Committee held on 17.01.2014, it was decided to formulate and finalise guidelines for considering payment of land compensation to the LAQ proposals initiated earlier also as per the new Land Acquisition Act.

(e) Out of the 20 villages to be rehabilitated under submergence of Almatti Reservoir, by conducting Grama Sabhas for 12 villages, the lands for relocating rehabilitation centres are identified and land acquisition process is also initiated.

(f) Under Unit-II of Navanagar, Bagalkot the infrastructure works viz; Water Supply, Storm Water Drain, Roads, UGD System and Electrification works awarded and commenced.

2. New initiatives : (a) Narayanapur Left Bank Canal – Extension, Renovation and Modernisation (NLBC-ERM) project.

The Detailed Project report for Narayanapur Left Bank Canal – Extension, Renovation and Modernisation (NLBC-ERM) project submitted by KBJNL and the State Government has been cleared in the Technical Advisory Committee (TAC) of CWC, Ministry of Water Resources, Government of India in it’s meeting held on 08.10.2013 for Rs.3752.18 Crores (2012-13 PL). Also, the Planning Commission, GOI accorded investment clearance for the Remodeling work of JBC Main project. This NLBC-ERM project is one of Canal the largest such projects in India and proposes to use innovative technologies like ICT, SCADA & Automation to ensure equitable distribution of water amongst farmers.

As part of the approved project, the remodelling of Main / Branch Canals of NLBC, SBC, MBC, JBC & IBC have been awarded on tender basis and works commenced. The works will be completed in the closure period of 2014 by end of June 2014. Also, the work of SCADA based Automation and GIS System for NLBC & HBC Network (Phase-I) is awarded on Layout of SCADA based Automation tender basis and work is in progress.

69

The estimates for remodelling of Distributaries and Lateral networks under NLBC canal network are under finalisation and the works are planned for implementation during 2014-15. The total implementation period of the NLBC-ERM project is 3 years.

(b) Drip Irrigation under 2nd Stage of Ramthal (Marol) LIS :

Under 2nd Stage of Ramthal (Marol) LIS, the works of providing Drip Irrigation System for 24,000 Ha. of command area in Hungund taluk of (in lieu of 12,600 Ha. as contemplated in conventional system of irrigation) have been awarded under 2 packages via; East Side Area 11,300 Ha. (Package-I) and West Side Area 12,700 Ha. (Package-II). The works are in progress. The scope of project includes O&M for 5 years. This is one of the largest single project in the world of its nature taken up in KBJNL. More than 20,000 farmers are to be benefited under the scheme.

Laying of main Drip pipelines under Ramthal (Marol) LIS 2nd stage for Drip Irrigation System

(c) Implementation of canal top Solar Power Project :-

The work of installation of canal top Solar Power Panels on ARBC from KM 8.00 to 11.00 for generation of 1.00 MW power is taken up on pilot basis and work is in progress.

(d) Flood Management and Protection works for Don River :

The consultancy work of preparation of Detailed Project Report for Flood Management and Protection works for Don river as per CWC guidelines / norms is awarded and consultancy work is in progress.

3. Administrative approvals for New Schemes :

Administrative approvals for the following new schemes have been accorded by the Government during 2013-14 for implementation of projects under KBJNL.

(i) Nandawadagi Lift Irrigation Scheme. (ii) -Peerapur Lift Irrigation Scheme. 70

(iii) Filling up of Mamadapur, Sarwad, Babaleshwar, Butanal, Begaum Talab and Tidagundi tanks in Bijapur district by lifting water from river Krishna. (iv) Sankh Lift – Filling up of 4 MI tanks project in Indi taluk. (v) Bhuyyar Lift - Filling up of 8 MI tanks project in Indi taluk.

4. OVERALL PROGRAMME & PROGRESS DURING 2013-14 UNDER KBJNL

(A) FINANCIAL PROGRAMME & PROGRESS : (Rs.in crores) Sl. Budget Head Grants Progress No. Programme for 2013-14 during as in BE 2013-14 1 AIBP 351.88 2 Capital Grants 1213.40 3 IEBR 900.00 2081.14 Maintenance 33.27 4 Grant 5 SCP / TSP 218.60 181.74 6 Debt Service 430.00 293.87 7 SDMF 20.00 -- TOTAL 3167.15 2556.75

(B) PHYSICAL PROGRAMME & PROGRESS : (Area in Ha.) Sl. Name of the project Programme Progress for No. for 2013-14 2013-14 1 Ramthal (Marol) LIS – 1ST Stage 6,013333333 5,678 2 LIS 4,987 3,440 3 Teggi-Siddapura LIS 3,000 2,878 4 Rolli- LIS 1,000 300 5 Chimmalagi LIS 1,400 3,211 6 Indi LIS KM 97.30 onwards 2,000 2,072 7 Rampur LIS 9,600 8,252 8 Sonthi LIS 3,000 2,429 9 Mallabad LIS 2,000 610 Laterals under NRBC Dy.No.15, 16 & 1,000 10 1,918 18 11 NRBC Distry. No.9A 1,000 455 TOTAL 35,000 31,243

71

UPPER KRISHNA PROJECT

A) About Krishna Bhagya Jala Nigam Limited:

In order to accelerate the implementation of the Upper Krishna Project (UKP) by mobilising resources from the capital market, KBJNL was incorporated on 19th August 1994 under the Companies Act, 1956 as Company, wholly owned by the Government of Karnataka for planning, investigation, estimation, execution, operation and maintenance of all components coming under the UKP. The Company is funding the Rehabilitation and Resettlement of the people affected by the Project. The company is authorised to let out water and recover revenues from individuals, groups of farmers including Water Users Co-operative Societies, Towns, City Municipalities and Industries.

B) Upper Krishna Project:

UKP Stage-I & II :

The Upper Krishna Project in Northern Karnataka is a mega-multipurpose project. The Scheme is being implemented in Stages. The project works under UKP Stage – I & II envisage utilisation of 173 TMC of water under Scheme ‘A’ of Krishna basin with a contemplated command of 6.22 lakh Ha. including Rehabilitation & Resettlement of Project affected families under submergence of Almatti & Narayanpur Reservoir. The same has been completed..

Administratively approved cost and the year of approval along with Revised cost details of UKP Stage-I & II:

a) Stage-1 of UKP is approved by Planning Commission vide letter No: 2 (10) / 89-I&CAD/24.09.90 for Rs. 1214.97 Crores at Price level of 1986- 87. The Revised Project Cost is approved by Planning Commission vide letter No.2 (10) 2009-WR dated 22.01.2010 for Rs.6891.59 Crores at Price level of 2008-09.

b) Stage-II of UKP is approved by Planning Commission vide letter no:2 (10) / 99-ER/13.12.2000 for Rs.2358.86 Crores at Price Level of 1998- 99. The Revised Project Cost is approved by Planning Commission vide letter No.2(10)2009-WR Dated 22.01.2010 for Rs.3959.80 Crores at Price level of 2008-09.

Closure reports of UKP Stage-I & II submitted to Central water Commission, GOI.

Expenditure incurred / Potential created under UKP Stage-I & II :

So far a sum of Rs.12,361.48 Crores has been spent on UKP Stage–I & II up to March 2014 besides Debt servicing.

Out of contemplated 6.22 lakh Ha. of command area under UKP Stage–I & II potential of 6.18 lakh Ha. has been created upto March 2014. UKP Stage-III :

72

Under KWDT-II Award, the allocation made for Upper Krishna Project Stage – III is 130.90 TMC. It is contemplated to provide irrigation for 5.30 Lakh Ha. under UKP Stage– III in the command coming under Gulbarga, Yadgir, Bijapur, Bagalkot, Raichur, Koppal & Gadag Districts in Northern Karnataka. In accordance with the “in-principle” administrative approval for Rs.17,207.00 Crores (PL 2011-12) accorded by the Government vide G.O. Dtd:24.01.2012, implementation of project components of UKP Stage – III viz: Mulwad, Chimmalgi, Indi, Mallabad, Koppal, Herkal, Rampur LI Schemes and NRBC Extension works have been taken up and are in various stages of progress.

Cumulative expenditure of Rs.1568.04 Crores has been incurred on UKP Stage – III Projects works till March 2014.

Under UKP Stage– III total irrigation potential of 26,718 Ha. is created till March 2014 (under Chimmalgi, Indi, Rampur & Mallabad LI Schemes).

C) Barrages across River Bhima, Krishna under Krishna Basin and across River Manjra in Godavari Basin:

Krishna Bhagya Jala Nigam Limited is implementing the following barrages across River Bhima & Krishna (Krishna Basin) and across River Manjra (Godavari Basin).

(a) Across River Bhima (Krishna Basin) :

Name of Barrage Status Ghattarga Barrage Completed Kallur ‘B’ Barrage Completed Yadgir Barrage Completed Joladagi-Gudur Barrage Completed Bridge-Cum-Barrage work completed and water stored.

Balance work of Sonthi LIS Head Work awarded on turnkey basis in advance stage of completion. Modified Sonthi Barrage LI Scheme Construction of Feeder Canal is completed. Construction of Main Canal Km 0.00 to 18.00, Branch Canal Km 0.00 to 20.02, Distry.No.1 Km 0.00 to 15.00 & Yargol Minor Canal are in progress. Tenders invited for Sonthi Main Canal KM 18.00 to 32.00 under 2 packages.

(b) Across River Krishna (Krishna Basin) :

Barrage Status of work Gugal Bridge cum Barrage Bridge-Cum-Barrage work completed and water stored.

73

(c) Across River Manjra (Godavari Basin) :

Barrage Status of work Construction of all four series of Bridge cum Barrages taken up across River Manjra in of Godavari basin to Jirgihal, Manikeshwar, utilize 4.80 TMC of water are completed. Halhalli & Chandapur Bridge-cum-Barrages The water stored in Jirgihal, Manikeshwar & Chandapur Barrages being utilised y farmers for irrigation through their own pumpsets.

D) Other Irrigation Projects under KBJNL:

The other Irrigation Projects namely Ramthal (Marol) LIS, Thimmapur LIS, Teggi-Siddapur LIS, Rolli-Mannikeri LIS, Sonthi LIS, NRBC Distry.No.9A and Filling up of MI Tanks Projects in Northern Karnataka are being implemented under KBJNL.

E) Narayanpur Left Bank Canal – Extension, Renovation & Modernisation (NLBC-ERM) Project:

The Narayanpur Left Bank Canal – Extension, Renovation & Modernisation (NLBC-ERM) Project is approved by CWC, MOWR, GOI for AIBP Assistance at a cost of Rs.3752.18 Crores in October 2013. As part of the approved Project, the works of Remodelling of Main / Branch Canal of NLBC, SBC, JBC, IBC & MBC under 8 Packages have been taken up for implementation during Closure Period of 2014. The works are planned for completion by end of June 2014. The work of SCADA based Automation and GIS System for NLBC & HBC Network (Phase –I) is also taken up for implementation as part of NLBC-ERM Project.

The Zone wise status of progress of irrigation projects under implementation in KBJNL are narrated hereunder.

74

KBJNL, DAM ZONE, ALMATTI

Dam Zone Almatti was established on 30.01.1977. Two Circle Office & Eight Division offices with 24 Sub-Divisions, One Senior Health Office (Class-I) with its 4 Anti-Malaria Units and Deputy Conservation of Forest with its 3 Sub-Divisions comes under jurisdiction of this Zone.

The projects of Almatti Dam, ALBC, ARBC and Mulwad LIS under UKP Stage-II, Mulwad, Chimmalagi and Herkal LIS under UKP Stage-III and other Schemes such as Ramthal (Marol), Timmapur, Teggi-Siddapur, Sonna and Rolli- Mannikeri LI Schemes comes under the jurisdiction of this Zone. Also, filling up of MI Tanks in Bijapur & Bagalkot Districts and Landscape & Garden development works at Almatti Dam site comes under the jurisdiction of this Zone. Status of projects under KBJNL Dam Zone is as under :

1) Almatti Dam: The work was completed during September 2002 itself and water is being stored upto FRL 519.60 M and being utilized for irrigation. Further, as per the KWDT-II Award, the Reservoir Storage at Almatti Dam is to be raised upto RL.524.256 M. The FRL survey taken up using LiDAR Technology upto RL 524.256 M is completed.

2) Almatti Left Bank Canal: Head work already commissioned. Total length of Main Canal is 85.00 KMs. 67 KMs Main Canal under Stage-I is completed. Under Stage-II, Main Canal KM 67.00 to 85.00 is completed (except balance work in KM 72 which is in advance stage of completion). Distributaries No.1 to 40 was also completed.

75

An area of 19,707 Ha. is notified for Rabi 2013 and water let out for irrigation upto Km 67.00 of Main Canal and in Disty.No.1 to 27. 3) Almatti Right Bank Canal: Head work already commissioned. Main Canal of 67.50 Km completed including Distributary No.1 to 24. Out of 9,900 Ha, potential of 8,940 Ha. is notified for Rabi 2013 and water let out for irrigation.

4) Mulwad Lift Irrigation Scheme:

Under UKP Stage-II :

The scheme contemplates lifting water in two Stages under UKP Stage-II. 1st and 2nd Head Works viz; Baluti and Hanumapur were already commissioned (for Stage-II) including the Lead off canal Km 0.00 to 5.00 which leads water from 1st to 2nd jackwell (for Stage-II requirement).

East Canal of 17.40 Km length including Distry.No.1 to 6 completed. Also, West Canal of 78.00 Km length including 43 Distributaries is completed. The work of extension of Disty.No.6 of East Canal beyond Railway line is also completed.

Out of contemplated 30,850 Ha. of command area, potential of 25,735 Ha is created and 20,846 Ha. is notified for Rabi 2013 and water let out for irrigation.

Under UKP Stage-III :

Under UKP Stage-III, in Mulwad LIS it is proposed to irrigate an area of 2,27,966 Ha. of command in drought prone areas of Bijapur, Muddebihal, Sindagi, B. and Indi taluks of Bijapur district and Jamakhandi and taluks in Bagalkot district by lifting water from foreshore of Almatti Reservoir in four stages upto RL 640.00 m.

The Head Works of Mulwad LIS Stage – III namely; (a) Balance Electro- mechanical works under Baluti 1st Head Work, (b) Balance Civil and Electro- mechanical works under Hanumapur 2nd Head Work, and (c) Masuti 3rd Head Works awarded on turnkey basis are in advance stage of progress.

The Lead–off Canal of 5.50 Km length between 1st & 2nd Head work of Mulwad LIS awarded and work is in progress. Combined Canal of 1.175 Km of Mulwad LIS Stage-III which caters the discharge for 2.27 Lakh Ha. is awarded and work is in progress. Further, tenders invited for initial 10 KMs reach of both Bijapur & Malghan Main Canals of Mulwad LIS Stage-III and are in process.

5) Chimmalagi Lift Irrigation Scheme :

Chimmalagi LIS under Stage-III contemplates providing irrigation for 87,068 Ha. in Muddebihal, B.Bagewadi, Sindagi, Indi and Bijapur taluks of Bijapur district. The scheme takes off at KM 12.65 of ALBC.

76

The Head Work for 1st Phase (4,614 Ha.) of the scheme was completed and commissioned. Further, balance Civil and Electro-mechanical works of the Head Work awarded on turnkey basis are almost completed. The Combined Canal of 2.10 KM length and West Main Canal KM 0.00 to 20.00 including Distributaries there under are completed and water letout for irrigation. Further, works under West Main Canal Km 20.00 to 51.92 and East Main Canal Km 0.00 to 50.00 are also completed. The works of East Main Canal from Km 50.00 to 90.00 awarded in 4 Packages are in progress. Tenders invited for East Main Canal Km 90.00 to 132.261 under 2 Packages (including Aqueduct for Don River Crossing).

Irrigation potential of 5,684 Ha. is created till March 2014. Notified area for Rabi 2013 is 2,473 Ha. Water let out for irrigation in Combined Canal, West Main Canal Km 0.00 to 20.00 & East Main Canal Km 0.00 to 13.00.

6) Herkal Lift Irrigation Scheme : This scheme under UKP Stage-III envisages providing irrigation for 15,344 Ha. in Bilgi Taluk of Bagalkot District. The Head Works of Herkal (North) and Herkal (South) are awarded on turnkey basis and works are in progress.

7) Ramthal (Marol) Lift Irrigation Scheme: This LI Scheme is taken up on the foreshore of Narayanapur Reservoir. The Scheme was originally planned to provide irrigation to 26,200 Ha. of command area of Hunagund Taluk of Bagalkot District through two stage lifting.

Construction of 1st Head work completed. 1st Stage West Main Canal KM 0.00 to 21.00 and Disty.No.1 to 18 are completed and water letout for irrigation. Further, West Main Canal KM 21.00 to 62.74 and Disty.No.19 to 25 are also completed (except NH crossing at KM 24.68). 1st Stage East Main Canal KM 0.00 to 10.00 is completed and water letout. Further, East Main Canal from KM 10.00 to 46.00 is almost completed and balance reach from KM 46.00 to 51.74 is in progress. Disty.No.1 to 20 is almost completed.

Construction of 2nd Head Work is completed. Under 2nd Stage of the scheme it was contemplated to provide irrigation for 12,000 Ha. through conventional system of irrigation. Government vide GO No.WRD/195/KBN/2012 dated 16.08.2012 had accorded Administrative approval for adopting Drip Irrigation System under 2nd stage of Ramthal (Marol) LIS on Pilot Basis at an estimated cost of Rs.786.11 crores. Under the Drip Irrigation System, it is planned to provide irrigation for 24,000 Ha. of Command in Hungund taluk.

The works of providing Drip Irrigation System under 2nd stage of Ramthal (Marol) LIS in two packages viz; (a) East side area 12,300 Ha. (Package-I) and (b) West side area 11,700 Ha. (Package-II) are awarded on turnkey tender basis and works are in progress. The scope of works of providing Drip Irrigation System includes 5 years of operation and maintenance also.

Irrigation potential of 14,393 Ha. is created to end of March 2014. An area of 7,576 Ha. is notified for Rabi 2013 and irrigation facility provided.

77

8) Thimmapur Lift Irrigation Scheme: This LI Scheme takes off at KM 5.40 of Main Canal of ARBC. The Scheme contemplates providing irrigation to 20,100 Ha. of command area of Bagalkot Taluk.

The Head work is completed and commissioned during 2012. Work of construction of Main Canal Km 0.00 to 42.00 including distributaries under DC-1 and construction of Main Canal KM 5.00 to 28.00 including distributaries under DC-2 are completed. The balance work from KM 0.00 to 5.00 under DC-2 is nearing completion. The water was letout in Main Canal KM 0.00 to 10.00 under DC-1.

Potential of 16,826 Ha. created to end of March 2014. An area of 5,549 Ha. is notified for Rabi 2013 and irrigation facility is provided.

9) Teggi-Siddapur Lift Irrigation Scheme: This Lift Irrigation Scheme is taken up on the foreshore of Almatti Reservoir near Teggi village of Bilgi taluk. Scheme contemplates providing irrigation to 3,000 Ha. command area of Bilgi Taluk.

Construction of balance works of Jackwell (civil works) & and providing electro-mechanical works awarded on turnkey basis is completed. Further, construction of Main Canal from Km. 0.00 to 12.00 is almost completed. Potential of 2,878 Ha. is created upto March 2014. The scheme is to be commissioned during 2014-15..

10) Sonna Lift Irrigation Scheme: This LI Schemes is taken up on the foreshore of Almatti Reservoir. Scheme contemplates providing irrigation to 1,055 Ha in Bilgi Taluk of Bagalkot Dist.

The scheme is completed and commissioned. Water let out for irrigation since 2010.

11) Rolli-Mannikeri Lift Irrigation Scheme: This LI Schemes is taken up on the foreshore of Almatti Reservoir. Scheme contemplates providing irrigation to 2,450 Ha in Bilgi Taluk of Bagalkot Dist.

Construction of Head Work awarded on turnkey basis is completed including the canal network system. Potential of 1,650 Ha. is created upto March 2014. The scheme is to be commissioned during 2014-15.

12) Filling up of M.I.Tanks of Bagalkot and Bijapur District: Scheme contemplates filling up of 16 MI tanks and 5 Bandaras of Bijapur District and 7 MI tanks of Bagalkot district located at elevated place in drought prone areas. The scheme is commissioned and water let out in the pipeline network for filling up of MI Tanks.

13) Filling up of Mamadapur, Sarwad, Babaleshwar, Buthnal, Begaum Talab and Tidagundi MI Tanks in Bijapur district :

78

The Government vide GO dated 28.02.2014 has accorded administrative approval for taking up filling up of Mamadapur, Sarwad, Babaleshwar, Buthnal, Begaum Talab and Tidagundi MI Tanks in Bijapur district by lifting water from river Krishna near Devaragennur village at an estimated cost of Rs.172.92 crores. Tenders invited for the work is in process.

14) Budihal-Peerapur LIS :

The Government vide GO dated 04.03.2014 has accorded administrative approval for taking up Budihal-Peerapur Lift Irrigation Scheme at an estimated cost of Rs.191.00 crores. The proposal and the estimate for the scheme is under finalization.

15) Landscape and Garden works on D/s of Almatti Reservoir: Landscape Development of Almatti Dam environs have been taken up to create the avenue for economic development of project area by attracting the tourists.

The project has been phased out in stages and development of 77 Acres of land along the left bank on the D/s of Dam is being implemented under Phase-I. Musical fountain work is completed and opened to public shows. Moghal Garden with fountains and entrance plaza works are also completed. In the later phase of landscape development works, providing water theme parks, courts etc., are planned in about 220 Acres.

16) SCP-TSP Works:- Under this programme, works like Sprinkler Irrigation coming under ALBC, ARBC and Mulwad LIS command area and others works like CC Roads, Drainage, Community Hall etc. to provide basic amenities to SC/ST beneficiaries are taken up.

17) Implementation of Solar Power Project :- The work of installation of canal top Solar Power Panels on ARBC from KM 8.00 to 11.00 for generation of 1.00 MW power is taken up on pilot basis and work is in progress.

79

PROGRAMME AND PROGRESS DURING 2013-14

(a) Details of irrigation potential and the physical programme and progress during 2013-14:

DETAILS OF IRRIGATION POTENTIAL (Area in Ha) Potential Progress Sl Planned Created Programme Name of the Project During No Potential upto for 2013-14 2013-14 March -13

1 Almatti Left Bank Canal 20,235 23,530 -- --

Almatti Right Bank 2 9,900 9,233 -- -- Canal

3 Mulwad LIS Stage – II 30,850 25,735 -- --

4 Mulwad LIS Stage – III 2,27,966 -- --

5 Chimmalagi LIS 87,067 2,473 1,400 3,211

6 Herkal LIS 15,344 ------

Ramthal (Marol) LIS-1st 7 14,728 8,715 6,013 5,678 Stage (Conventional)

Ramthal (Marol) LIS-2nd 8 24,000 ------Stage (Drip System)

9 Thimmapur LIS 20,100 13,386 4987 3,440

10 Teggi-Siddapur LIS 3,000 -- 3,000 2,878

11 Sonna LIS 1,055 900 -- --

12 Rolli-Mannikeri LIS 2,350 1,350 1,000 300

TOTAL 4,56,595 85,322 16,400 15,507

(b) Financial progress during 2013-14 :

The annual financial programme of this Zone for the year 2013 -14 was Rs.1039.02 Crores and the financial progress achieved to the end of March- 2014 is Rs.907.10 Crores.

80

KBJNL, O & M ZONE, NARAYANPUR

Considering the vast area already notified and the phase of development of irrigation in the subsequent period, the Government has accorded sanction for creation of separate Zone to look after Operation and Maintenance activities of UKP vide G.O. No.ID/115/WBM/91, Dated: 14/10/1991. Owing to the Government order, the office of the Chief Engineer, O&M Zone, UKP Narayanpur came into existence from 03.01.1992. This Zone is brought under Krishna Bhagya Jala Nigam Limited with effect from 15.11.1995. One Circle, four Divisions and Sixteen Sub-Divisions comes in the jurisdiction of this Zone.

This Zone has been vested with the responsibility to monitor the water management in an irrigated area of 1.00 lakh hectares under Stage-I & II of UKP. This canal wise details of Notified area for irrigation are as under :

Sl. Canal Notified Area in Ha. No 1 Narayanpur Left Bank Canal 50,133 2 Rampur Lift Irrigation Scheme 19,311

3 Narayanpur Right Bank Canal 30,225 (KM 0.00 to 82.00 & Disty.No.1 to 14) Total 99,669

Apart from Operation and Maintenance of Canal network in NLBC from Km. 0.00 to 78.00, NRBC Km. 0.00 to 82.00 & Rampur LI Scheme, this Zone is also looking after the following project works: a) Rampur Lift Irrigation Scheme (Extension) :

Rampur LIS under UKP Stage-II contemplates providing irrigation for 20,235 Ha. Already 1st Head Work at Navali and 2nd Head Work at Anehosur, 14 KM Lead-Off Canal and East Main Canal KM 0.00 to 20.00 including West Distributary works are completed and water let out for irrigation.

Under UKP Stage-III, extension of East Main Canal beyond KM 20.00 is contemplated and envisaged to provide irrigation for 13,923 Ha. in Lingasugur and Deodurga taluks of Raichur district. The extension of East Main Canal of Rampur LIS from KM 20.00 to 27.00 and Disty.No.10 and 11 are almost completed. Further, Tail end Distributary works taken up under two packages are in progress. The scheme is almost completed. Irrigation potential of 9,452 Ha. is created to end of March 2014. b) Koppal Lift Irrigation Scheme :

This scheme contemplates providing irrigation for 48,436 Ha. in Koppal, Bagalkot and Gadag districts under UKP Stage-III. As per the modified proposal it is proposed to lift water under two equal stages from the backwaters of Narayanapur reservoir from RL 485.00 m to RL 660.00 m. Government vide GO dated 9.1.2013 accorded approval for adopting Micro 81

Irrigation under Koppal LIS to provide irrigation for about 1,12,000 Ha. of command in Bagalkot, Koppal & Gadag Districts utilizing 12.815 TMC of water under UKP Stage-III.

The 1st and 2nd Head Works awarded on turnkey basis are in progress. The consultancy work of Survey investigation, planning, preparation of design & drawings, estimates etc. for the Drip Irrigation System is in progress. c) Rajan-Kollur Lift Irrigation Scheme:

The Scheme takes off from the D/s of Rajankollur Tunnel at Km 40.06 of NLBC. Scheme contemplates providing irrigation for 1,097 Ha of command area in Shorapur taluk of Yadgir district.

The scheme is completed and commissioned during 2012-13 and irrigation facility provided for the Notified Area of 845 Ha. command. d) Bonal Lift Irrigation Scheme:

This scheme contemplates providing irrigation to about 5,400 ha of the suffering achcut under SBC Distry.No.6 of UKP by lifting water from D/s of Bonal Mini Hydel Scheme near Bonal tank in Shorapur taluk Yadgir district.

The scheme is completed and commissioned during 2012-13 and irrigation facility provided for the suffering achcut under SBC Distry.No.6. e) Remodeling of Narayanapur Left Bank Canal :

The Narayanapur Left Bank Canal – Extension, Renovation and modernization (NLBC-ERM) project at an estimated cost of Rs.3752.18 crores is approved by CWC, MOWR, GOI on 08.10.2013 under AIBP assistance. As part of this approved project, the remodeling of NLBC Main Canal under 2 packages viz; (a) NLBC Main Canal KM 0.00 to 26.00 (Package-1) and (b) NLBC Main Canal KM 26.00 to 77.52 (excluding earlier executed 25 KM reach) and HBC (Package-2 were taken up for implementation on tender basis. These works are planned for completion by end of June 2014. The work of SCADA based Automation and GIS System for NLBC & HBC Network (Phase –I) is also taken up for implementation as part of NLBC-ERM Project and the work is in progress. f) Flood Management and Protection works for Don River :

The consultancy work of preparation of Detailed Project Report for Flood Management and Protection works for Don river as per CWC guidelines / norms is awarded and consultancy work is in progress. g) Nandawadagi LIS :

The Government vide GO dated 01.03.2014 as accorded administrative approval for implementation of Nandawadagi LIS through KBJNL adopting

82

Drip Irrigation System at an estimated cost of Rs.1530.00 crores. The estimates for Head Works are under finalization.

h) SCP-TSP WORKS :

Under this Zone works of SCP-TSP are being implemented.

PROGRAMME AND PROGRESS DURING 2013-14

(a) Details of irrigation potential and the physical programme and progress during 2013-14: (Area in Ha) Created Programm Progres Sl Planned upto s Name of the Project e for No potential March During 2013 2013-14 2013-14 1 Narayanpur Left Bank Canal 47,223 50,133 -- -- Narayanpur Right Bank Canal 2 30,100 30,225 -- -- Km 0.00 to 82.00 1 Rampur LIS – Stage-II 20,235 19,406 -- -- 2 Rampur LIS Extension 13,923 1,200 9,600 8,252 3 Koppal LIS (Drip System) 1,12,000 ------4 RajanKollur LIS 1,000 900 -- -- Bonal LIS (Suffering Atchcut 5 5,400 5,400 -- -- under SBC Dy.No.6) TOTAL 2,29,881 1,07,264 9,600 8,252

(b) Financial progress during 2013-14 :

The annual financial programme of this Zone for the year 2013-14 was Rs.577.00 Crores and the financial progress achieved to the end of March- 2014 is Rs.380.95 Crores.

83

KBJNL, CANAL ZONE NO. 1, BHEEMARAYANAGUDI

ORGANISATION:

Canal Zone No.1, Bheemarayanagudi is functioning with two circle i.e.NRBC Circle No.2, Krishnapur & JBC Circle, Bheemarayanagudi and there are 8 Divisions and 36 Sub-Divisions coming under the jurisdiction of the Zone.

CONTEMPLATED IRRIGATION POTENTIAL:

The irrigable command areas contemplated under various canal networks coming under the jurisdiction of this Zone are as under:

Sl.No. Name of the Canal ICA envisaged 1 Shahapur Branch Canal. 1,22,120 Ha. 2 Mudbal Branch Canal. 51,000 Ha 3 Jewargi Branch Canal 57,098 Ha. 4 Narayanapur Right Bank Canal (KM 82.00 to 95.00 53,997 Ha. & Dy.No.15 to 18) 5 NRBC Extension from KM 95 onwards under UKP 61,747 Ha. Stage-III 6 NRBC Disty.No.9(A) 15,250 Ha. 7 Mallabad LIS under UKP Stage-III 33,730 Ha. 8 Bhima Flank under UKP Stage-III 21,572 Ha. 9 Sonthi LIS 16,000 Ha. Total 4,32,514 Ha.

The command areas of Shorapur, Shahapur and Yadgir taluks of Yadgir district, Jewargi and Chittapur Taluks of Gulbarga district and Deodurga and Lingasugur taluks of Raichur district will be covered in the above Canal network system.

PRESENT STATUS OF WORKS UPTO END OF MARCH 2013:

1. SBC, MBC and JBC :

The Shahapur Branch Canal, Mudbal Branch Canal and Jewargi Branch Canal works under UKP Stage-I are completed and are in the Operation & Maintenance stage.

2. Narayanapur Right Bank Canal :

Under UKP Stage-II :

Construction of NRBC from Km 0.00 to 95.00 under UKP Stage – II envisage providing irrigation for 84,000 Ha. in Lingasugur & Deodurga Taluks of Raichur District. The works of this canal were commenced during the year 1995-96. The jurisdiction of NRBC from KM 82.00 to 95.00 and Dity.No.15 to 18 comes under the jurisdiction of this Zone.

84

All the works of Main Canal from Km 82.00 to 95.00 and Distry.No.15 to 18 are completed. Certain works of additional laterals taken under on D-15, 16 & 18 are in almost completed.

Against the contemplated command area of 84,000 Ha, irrigation potential 96,120 Ha. is notified for Rabi 2013. Water has been letout for irrigation under NRBC upto Km 95 including network of Distry. No.1 to 18.

Under UKP Stage-III :

Under UKP Stage-III, extension of Narayanapur Right Bank Canal from KM 95.00 to 168.50 is envisaged to provide irrigation for 61,747 Ha. in Raichur District. The works of construction of NRBC from KM 95.00 to 125.00 are awarded in 6 Packages and the works have commenced. Further, the consultancy work of survey investigation and preparation of estimates for balance Canal Network from Km 125.00 to 168.50 is in progress.

3. NRBC Disty.No.9(A) :

NRBC Disty.No.9(A) off-takes at KM 55 of NRBC on right side for providing irrigation for 15,250 Ha. in Deodurga and Manvi taluks of Raichur district.

The construction of NRBC Disty.No.9(A) KM 0.00 to 29.12 (including Aqueduct from KM 8.18 to 10.48) is completed. Further, the works of Arkera Branch Distributary KM 0.00 to 22.18 are also almost completed. Wadawatti Branch Distributary from KM 0.00 to 10.00 is almost completed and works from Km 10.00 to 27.00 awarded under 4 packages have commenced.

Potential of 455 Ha. is created during 2013-14 under NRBC Disty.No.9(A).

4. Mallabad Lift Irrigation Scheme :

This scheme under UKP Stage-III envisage providing irrigation for 33,730 Ha. in Jewargi taluk of Gulbarga district and Shahapur and Shorapur taluks of Yadgir district.

The construction of 1st Head Work at Balabatti at KM 20.90 of JBC awarded on turnkey and Main Canal KM 0.00 to 4.00 under 1st Head Work is completed. Main canal work from Km 4.00 to 9.00 is in progress.

The 2nd Head Work on MBC at KM 20.00 and the 3rd Head Work on SBC at KM 5.40 awarded on turnkey basis are in advance stage of progress. Also the Main Canal works from Km 0.00 to 10.00 coming under 2nd & 3rd Head works of the scheme are in progress. Preparation of estimates for balance canal network system are in progress

Potential of 610 Ha. is created during 2013-14 under Mallabad LIS.

5. Bhima Flank :

This scheme under UKP Stage-III envisage providing irrigation for 21,572 Ha. in Shahapur taluk of Yadgir district. The technical feasibility of the scheme is being examined.

85

6. Bridge Cum Barrage Works across River Bhima :

(a) Yadgir & Joldadgi-Gudur Barrages :

Constructions of above Yadgir & Joladadgi-Gudur Barrages across River Bhima were completed earlier and water stored in these barrages is being utitilised by farmers through their own pumpsets.

(b) Sonthi Bridge-cum-Barrage and Sonthi LI Scheme :-

The modified Sonthi Bridge-cum-Barrage across River Bhima (near village Sonthi) with installation of 37 Vertical Gates is completed and water stored. Under the Scheme it is envisaged lifting water from the storage accomplished at Sonthi Barrage to provide irrigation for 16,000 Ha. of command in Chittapur taluk of Gulbarga district and Yadgir taluk of Yadgir district. The Head Work (Blance works) of Sonthi LIS awarded on turnkey basis is in advance stage of completion.

Construction of Feeder Canal KM 0.00 to 1.75 is completed. Further, works of Sonthi Main Canal from KM 0.00 to 18.00 (including Aqueduct), Sonthi Branch Canal KM 0.00 to 20.02, Disty.No.1 KM 0.00 to 15.00 and Yargol Minor Canal are in various stages of progress.

The Sonthi LI Scheme is posed for Central Assistance under AIBP. In- principle approval for the scheme is obtained from CWC, GOI on 27.04.2012. The DPR prepared for an estimated cost of Rs.600.00 crores (PL 2012-13) is submitted to CWC on 27.11.2012 and the same is under examination in Ministry of Water Resources, Government of India.

Potential of 2,429 Ha. is created during 2013-14 under Sonthi LIS.

7. Gugal Bridge-cum-Barrage across River Krishna :

The Gugal Bridge cum Barrage with installation of 69 Vertical Gates across River Krishna near Gugal village in Deodurga taluk of Raichur district is completed during 2012-13. The water stored at the Gugal Barrage is being utilized by the farmers with their own pump sets for irrigation. The Bridge- cum-barrage also facilitated communication between Yadgir and Raichur Districts.

8. Bridge-cum-Barrages across River Manjra in Bidar distrct :

Construction of 4 No. of series of Bridge-cum-Barrages across river Manjra in Bidar District envisage utilization of 4.80 TMC of water under Godavari basin.

Already, the construction of all the 4 Bridge-cum-barrages namely; (a) Jirgihal, (b) Manikeshwar, (c) Halhalli, and (d) Chandapur were completed. These barrages are provided with automatic tilting Godbole Gates. The water stored at these barrages is being utilized by the farmers for irrigation with their

86

own pumpsets. These barrages have also facilitated communication facilities on either side of villages and towns, ground water recharge and mitigation drinking water requirement for the villages along the river course.

9. Remodeling of SBC, MBC and JBC under NLBC-ERM project :

The Narayanapur Left Bank Canal – Extension, Renovation and modernization (NLWC-ERM) project at an estimated cost of Rs.3752.18 crores is approved by in the Technical Advisory Committee (TAC) of CWC, Ministry of Water Resources, Government of India in it’s meeting held on 08.10.2013 for Rs.3752.18 Crores (2012-13 PL) for AIBP assistance. As part of this approved project, the remodeling of following Main Canal works were taken up for implementation on tender basis.

(a) SBC Main Canal KM 0.00 to 30.00 (Package-S1) (b) SBC Main Canal KM 30.00 to 76.00 (Package-S2) (c) JBC Main Canal KM 0.00 to 20.00 (Package-J1) (d) JBC Main Canal KM 2.00 to 40.00 (Package-J2) (e) MBC Main Canal KM 0.00 to 50.80.

Above remodeling package works are planned for completion by end of June 2014.

SCP-TSP WORKS :

Under this Zone works of SCP-TSP are being implemented.

87

PROGRAMME AND PROGRESS DURING 2013-14

(a) Details of irrigation potential and the physical programme and progress during 2013-14: (Area in Ha) Sl Planned Created Programm Progress N Name of the Project potentia upto e for During o l March -13 2013-14 2013-14

1 Shahapur Branch Canal. 1,22,120 1,14,717 -- --

2 Mudbal Branch Canal. 51,000 44,321 -- --

3 Jewargi Branch Canal 57,098 59,163 -- -- Narayanapur Right Bank Canal 4 53,997 57,662 1,000 1,918 (KM 82.00 to 95.00 & Dy.15 to 18) NRBC Extension from KM 95 5 61,747 ------onwards under UKP Stage-III 6 NRBC Disty.No.9(A) 15,250 -- 1,000 455

7 Mallabad LIS under UKP Stage-III 33,730 -- 2,000 610

8 Bhima Flank under UKP Stage-III 21,572 ------

9 Sonthi LIS 16,000 175 3,000 2,429

TOTAL 4,32,514 2,75,863 7,000 5,412

(b) Financial progress during 2013-14 :

The annual financial programme of this Zone for the year 2013 -14 was Rs.624.50 Crores and the financial progress achieved to the end of March- 2014 is Rs.283.07 Crores.

88

KBJNL, CANAL ZONE NO.2, RAMPUR

ORGANISATION:

The Canal Zone No.2, Rampur (earlier located at Kembhavi) is functioning with effect from 1.10.1986 vide G.O.No.PWD 60 PCO 86, Dtd: 29.9.1986. This Zone is functioning with one circle i.e., O&M Circle No.2, Rampur. There are 5 Division and 23 Sub-Divisions coming under jurisdiction of this zone.

At present this Zone is in-charge of the following project works:

(a) Indi Branch Canal from Km 0.00 to 172.00 including Distry.No.1 to 46, (b) Indi Lift Canal works from Km 0.00 to 147.00 (c) Filling up of 20 MI tanks under Indi taluk of Bijapur District (Anachi, Sunkh and Bhuyyar Lifts) (d) Itaga-Sangam LIS. (e) Ghattaraga and Kallur-B Barrages across River Bhima.

Details of works taken up under this Zone are as under:

INDI BRANCH CANAL :

The Indi Branch Canal takes off at Km 77.52 of Narayanpur Left Bank Canal, which is situated about 1 Km away from Kembhavi village of Shorapur taluka in Gulbarga District and traverses for a length of 172 Km with a head discharge of 2,943 cusecs (83.49 cumecs) through the districts of Gulbarga and Bijapur irrigating an area of 30,831 Ha. and 1,00,464 Ha respectively (Total 1,31,295 Ha.).

The works of construction of Indi Branch Canal from Km 0.00 to 64.00 are tackled and completed under Stage-I, Phase-II of UKP creating irrigation potential of 60,721 Ha. The works of construction of Indi Branch Canal from Km 65.00 to 172.00 are tackled and completed under Phase-III of Stage-I to create the balance irrigation potential of 70,574 Ha. Up to March 2013 total an area of 1,31,584 Ha Irrigation Potential of 1,31,584 Ha has been created.

The works of Indi Branch Canal from KM 65 to 172 and Distributaries 14 to 46 are taken up on tender basis as well as entrustment basis were completed and water has been released through IBC upto KM 64.00 during September 1995, upto KM 130.00 on 06.02.2002 and upto KM 172.00 on 2.11.2002.

The Notified area under IBC for Rabi 2013 is 1,24,111 Ha. and irrigation is being provided.

89

INDI LIFT CANAL : Under UKP Stage-II, the Head work of Indi Lift Irrigation Scheme and the Canal Network from Km 0.225 to 97.30 including Distry.No.1 to 40B & laterals there under are completed. Out of contemplated irrigation potential of 41,900 Ha. upto end of March 2014 irrigation potential of 43,000 Ha. has been created and water letout for irrigation on regular basis since July 2008. Notified area for Rabi 2014 is 46,672 Ha.

Under UKP Stage – III, extension of Indi Lift Main Canal from KM 97.30 to 147.00 to provide irrigation for 20,690 Ha. in Indi & Sindagi Taluks of Bijapur Dist is envisaged. Already, the works of construction of Indi Lift Canal from Km 97.30 to 120.00 (including aqueduct from KM 110.00 to 113.00) are completed and water letout for irrigation. Further, Indi LIS Main Canal KM 120.00 to 147.00 awarded under 4 packages are in progress. Disty.No.41 to 52 are completed are also completed. The estimates for tail end distributary are finalized and tenders for the work in suitable packages to be invited. The work of providing additional pumping machinery at the Head work is almost completed.

CHIMMALAGI LIFT IRRIGATION SCHEME (BEYOND DON RIVER)

The implementation of Korwar and Nagathan Branch Canals of Chimmalagi LIS beyond Don river crossing which envisage provision irrigation for 39,326 Ha. in Sindagi and Indi taluks of Bijapur district comes under the jurisdiction of this zone. The estimates for initial 10 KMs of Korwar and Nagathan Branch Canals have been finalized and the works will be commenced during 2014-15.

FILLING-UP OF 8 MI TANKS IN INDI TALUK (ANACHI LIFT) :

The work of filling up of 8 MI tanks from river Bhima in Indi Taluk – Anachi Lift, is awarded on turnkey basis and is in progress.

FILLING-UP OF 12 MI TANKS IN INDI TALUK (SANKH & BHUYYAR LIFTS) :

Government vide dated 28.02.2014 has accorded administrative approval for taking up filling up of 12 No. MI tanks by lifting water from river Bhima in Indi taluk through implementation of Sankh and Buyyar lifts. Tenders on turnkey basis for the both Sunkh and Buyyar lifts have been invited and are in process.

ITAGA-SANGAM LI SCHEME :

This scheme was taken up for providing irrigation to the suffering command in the tail end of IBC Disty.No.11. The work was commenced during October 2005 and completed and commissioned in June 2010. The irrigated area from this scheme is 1,200 Ha. which includes 911 Ha. of suffering atchcut under Disty.No.11 of IBC and additional potential of 289 Ha.

90

BARRAGES ACROSS RIVER BHIMA :

The two barrages namely Ghattaraga and Kallur-B barrages across River Bhima were completed during 2004-05 and the water stored at these barrages is being utilised by the farmers through their own pumpsets for irrigation.

REMODELING OF INDI BRANCH CANAL FROM KM 0.00 TO 64.00 UNDER NLBC-ERM PROJECT:

The Narayanapur Left Bank Canal – Extension, Renovation and modernization (NLWC-ERM) project at an estimated cost of Rs.3752.18 crores is approved in the Technical Advisory Committee (TAC) of CWC, Ministry of Water Resources, Government of India in it’s meeting held on 08.10.2013 for Rs.3752.18 Crores (2012-13 PL) for AIBP assistance. As part of this approved project, the remodeling of IBC Main Canal from KM 0.00 to 64.00 is taken up for implementation on tender basis. The remodeling package work is planned for completion by end of June 2014.

SCP-TSP WORKS :

Under this Zone works of SCP-TSP are being implemented.

PROGRAMME AND PROGRESS DURING 2013-14 :

Details of irrigation potential and the physical programme and progress during 2013-14: (Area in Ha) Programm Sl Planned Created Progress Name of the Project potentia upto e for During No l March -13 2013-14 2013-14 1 Indi Branch Canal. 1,31,261 1,31,584 -- -- 2 Indi Lift Canal (Upto Km 97.30) 41,900 43,000 -- -- 3 Indi Lift Canal (Km 97.30 to 147.00) 20,690 8,000 2,000 2,072

Itga Sangam LIS 4 1,200 1,200 -- -- (Suffering atchcut under IBC Dy.11)

5 Total 1,95,051 1,83,784 2,000 2,072

(c) Financial progress during 2013-14 :

The annual financial programme of this Zone for the year 2013 -14 was Rs.236.43 Crores and the financial progress achieved to the end of March- 2014 is Rs.116.94 Crores. ***********

91

10.2 BAGALKOT TOWN DEVELOPMENT AUTHORITY

1. SALIENT FEATURES OF BAGALKOT TOWN:

Bagalkot Town is historically famous from the glory and one of the largest town in the northern parts of Karnataka which is situated on the right bank of at 16o-12’ longitude and 75o-12’ latitudes.

The Bagalkot Town is situated at a distance of 40 KMs (by road) South West of Almatti Dam. The lowest portion of the town is at an elevation of RL 512.19 Mtr. and the maximum elevation being RL 533.53 Mtr. A substantial portion of this town will get submerged in the backwaters of Almatti Reservoir when the Dam is raised to its ultimate FRL of 524.256 Mtr.

Considering the backwater effect of storage of water at FRL 519.60 Mtr. at Almatti Dam and also as per the GO dated 16.11.2002 the structures upto RL 523.00 Mtr. in Bagalkot Town are already acquired. The FRL survey using 3D LiDAR technology for submergence when the storage at Almatti Reservoir is increased to FRL of 524.256 Mtr. as per KWDT-II Award is completed..

Resettlement plan consists of acquiring lands for locating the new Bagalkot Town and to provide basic infrastructure in the new town. The lands required for the new town have already been acquired (about 4,544 acres) and possession has been taken.

2. ORGANISATION STRUCTURE:

For efficient and systematic implementation of Rehabilitation and Resettlement of Bagalkot Town, Govt. of Karnataka has constituted Bagalkot Town Development Authority (BTDA) with an Amendment to HUD Act functioning since 1984. BTDA is formed with Chief Engineer office with Staff. 2 Divisions with staff, 8 Sub Divisional Offices with staff, Special Land Acquisition Office with staff, Rehabilitation Office with staff & Chief Accounts Office with staff.

3. ACCELERATED IRRIGATION BENEFIT PROGRAMME :

Estimated cost of Rehabilitation and Resettlement of Bagalkot Town: The detailed cost of the Project is as under.

Sl.No. Details of Component Rs.in lakh 1 Structural compensation in old Bagalkot Town. 39539.06 2 Land Acquisition for new township and others etc. 2952.50 3 R&R Packages. 3000.00 4 Construction of Roads and parks etc., 6231.00 5 Providing Water Supply 4445.00 6 Providing U.G.D. 2200.00 7 Providing Electrification. 2000.00 8 Construction of Public Building 2200.00 9 Telecom facilities 400.00

92

10 Construction of Railway 1000.00 11 Maintenance of BTDA Colony and Navangar. 800.00 12 New Supply Machinery and Maintenance 250.00 13 Consultancy and training charges 90.00 14 Establishment 2591.94 Total:- 67700.00

The Project cost of the above components under AIBP prepared for Rs.677.00 crores and Rs.360.49 crores under special package scheme. Thus the total cost of the project works out to Rs.1037.49 crores.

The works taken up under Stage-I Phase-I, II, are completed and the works under Phase-III are nearing completion. Structures up to RL 521.00 M contour have been evaluated and compensation paid. Plots for the PDFs below RL 521.00 Mtr. contour have been allotted in New township of Bagalkot. Most of the PDFs constructed their houses in the allotted sites.

4. SPECIAL PACKAGE SCHEME :

Considering the problems due to backwater effect, Govt. has announced the special package of Rs.638.00 Crores (Rs.500.00 Crores for Bagalkot town + Rs.138.00 crores for R&R) Vide G.O.NO.RD1/124/REH/2002/Bangalore Dt.16/11/2002 to improve the existing conditions of old Bagalkot Town. The details of special package are as under:

Sl. Details of components Rs.in No Crores 1 Structural compensation between RL.521.00 to 523.00, and 414.00 development of 35 sectors of unit 2 of Navangar with all infrastructures facilities like roads. 2 Providing UGD for Non submergence of Bagalkot Town. 29.12 3 Providing Water Supply for non-submergence of Bagalkot Town. 11.70 4 Construction of link roads. 20.00 5 Development of parks in old town. 2.00 6 Construction of building under Ashraya Scheme for slum 12.00 dwellers. 7 Construction of building for site less and below poverty line 5.00 people. 8 Construction of 50 bedded hospital in old town. 2.00 9 Income and employment generating scheme. 4.18 Total :- 500.00

5. PRESENT STATUS :

I. a) Compensation payment to the structures between contour RL 521.00 M to RL 523.00 M is paid and site allotment is under process.

b) The demarcation of plots in 50 Sectors of Unit-II is completed. The infrastructures facilities like Roads, UGD, Storm Water Drains &

93

Electrification for Unit-II of Navanagar have been awarded and works commenced.

II. The UGD Network in old Town for Non-submersible portion of Bagalkot has been completed.

III. The work of providing water supply system including revamping of existing pipeline for non-submersible portion of Bagalkot town has been completed and is functioning.

IV. The improvements to roads i.e. 3 link roads, 5 main roads, 7 internal roads in slum area of Bagalkot Town are completed.

V. Development of 4 parks in old Bagalkot town is completed.

VI. Construction of 50 bedded Hospital building along with Doctors and Nurse Quarters in old Bagalkot Town are completed and now Hospital is functioning

6. DETAILS BUDGETARY PROVISIONS FOR 2013-14 : (Rs. In Lakhs.) Sl. Details of Component Approved No. I Civil Works Special Package works in Old Bagalkot Town 332.13 Development Civil works in Unit-I 5824.23 Development Civil works in Unit-II 22525.00 Development Civil works in Unit-III 70.00 II Acquisition i) Enhanced Compensation & Lok Adalat payments 2500.00 ii) Structure Compensation between RL 521 to 523 100.00 Mtr iii) Land Compensation between RL 523 to 525 Mtr 4500.00 ii) Structure Compensation between RL 523 to 525 5000.00 Mtr III Permanent Water Supply 2500.00 IV Establishment. 1000.00 Total: 44351.36 7. DETAILS OF PROGRESS ACHEIVED DURING 2013-14 (UPTO 31.03.2014) :

a) Development Works: 7 works have been taken up under Special Package, of which 4 works are completed. 104 works have been taken up Under Capital Grant Scheme-A in Unit-I, of which 26 works 94

are completed. 16 works have been taken up under Scheme-B in Unit- II, of which 7 works are completed. Out of 5 Major works in Unit-II such as, Roads, Water Supply, UGD, Electrification, & Storm Water Drains, 4 works except water supply work, are started recently. The total expenditure made for development works during 2013-14 is Rs. 28.22 Crores.

b) Acquisition of Structures: Compensation of Rs.25.23 crores (including enhanced payment) have been paid to the structures coming below RL 521.00 Mtr. and Rs.8.76 crores have been paid to the structures coming between RL 521.00 M to RL 523.00 M.

c) Allotment of sites: Totally 64 sectors (56 for PDF's and 8 for Non- PDF's) are developed in Unit-1 at Navanagar. During this year 1060 sites are allotted to PDF’s, Non-PDFs & others. For 447 buildings permissions have been given to construct the houses at their allotted sites in Navanagar.

8. FINANCIAL PROGRESS:

Financial programme for the year 2013-14 is Rs.443.51 crores out of which an expenditure of Rs.69.02 Crores has been made upto end of March-2014. The total expenditure incurred since inception is 1037.09 Crores. Details are as under:

(Rs.in lakhs) Sl. Details of Component. Grant. Expenditure No I Civil Works i) Special Package works in Old BagalkotTown 332.13 4.66 ii) Development Civil works in Unit-I 5824.23 2500.65 iii) Development Civil works in Unit-II 22525.00 16.28 iv) Development Civil works in Unit-III 70.00 0.00 II Acquisition i) Enhanced Compensation & Lok Adalat payments 2500.00 2523.10 ii) Structure Compensation between RL 521 to 523 100.00 876.68 Mtr iii) Land Compensation between RL 523 to 525 Mtr 4500.00 0.00 ii) Structure Compensation between RL 523 to 525 5000.00 0.00 Mtr III Permanent Water Supply 2500.00 300.39 IV Establishment. 1000.00 680.00 Total: 44351.36 6901.76

******

95

PROJECTS UNDER

KARNATAKA NEERAVARI NIGAM LIMITED

96

12. KARNATAKA NEERAVARI NIGAM LIMITED

12.1 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION (NORTH), BELGAUM The Irrigation Nort zone, Belgaum came in to exisitence on 10.08.1967 as per G.O. PWD 114 PCO 67, dated 24.07.1967. The formation of this zone was maily to expedite the progress of the Irrigatin Project.

A ON GOING PROJECTS 1 Ghataprabha Project 2 Hipparagi Project 3 Markandeya Project 4 Dudhganga Project 5 Lifting of water from Hiranyakeshi river to GRBC 6 Project 7 Sri. Rameshwara LIS 8 Kinaye Project 9 LIS 10 Kallol-Yadur Bridge cum barrage B TO BE STRAT PROJECTS 11 Construction of Sangam Barrage 12 Filling of Shragaon – Basavanna Tank: 13 Filling of Kadapur Tanks 14 Filling up of 22 tanks from Hironyakeshi river UNDER POLLAVARAM BASIN WATER ALLOCATION C AWAITING FOR THE ADMINISTRATIVE APPROVAL PROJECTS 15 Sri Mahalakshmi Lift Irrigation Scheme 16 Tubachi – Babaleshwar Lift Irrigation Scheme D YET TO BE APPROVED (NEW PROJECTS) 17 Veerabhadreshwar Lift Irrigation Scheme 18 Kallola – Yadura Bridge Cum Barrage UNDER “SCHEME B” PROJECTS (AWAITING FOR THE E ADMINISTRATIVE APPROVAL AND WATER ALLOCATION) 19 Kepwada Lift Irrigation Scheme 20 From Kochari Barrage Lift Irrigation Scheme 21 Aralikatte Lift Irrigation Scheme 22 Mastihole – Managutti Lift Irrigation Scheme 23 Yamakanamaradi Lift Irrigation Sceheme

97

12.1.1. Ghataprabha Project:

Dam works : Completed.

GLBC (109 Km.) : GLBC has been completed to its full length of 109 km and water has been let out for irrigation in all 61 blocks.

GRBC (199.093 Km.) : GLBC lining works are taken up under Ghataprabha stage – III. About 104.00 kms Main Canal lining, Dy above 20 cuses 494.40Km & Dy.Less than 20 cuses, 712.70 Km completed. Government has accorded administrative approval to the revised project estimate of Ghataprabha Project Stage III amounting to Rs.1210.51 crores vide GO dated 18/10/2009.

Distributories under GRBC (37 nos.) : Out of total length 199.033 Kms a length of 196 Km has been completed, except lining n some reaches (Km 122, 131, 144, 145, 197 to 199.33). Balance work yet to be started. Water letout for irrigation upto Km. 190.

Chikkodi Branch Canal (88 Km.) : There are total 37 distributary blocks under GRBC. Works are completed in distributary blocks 1 to 23, 25, 26, 28 to 31 to 33 & 37. [Except km 13,14 & 15 of Chichakandi dy (BL 24), km 14,17 & 18 of Shardal dy (BL 27), km 13 of Bagalkot dy (BL 34), km 3 to 5

98

of dy (BL 35), & km 9 of Kamatagi dy (BL36)] Works in 24, 27, 34, 35 & 36 are under progress. Distributories under CBC (25 nos.) : Completed to its full length of Kms. 88 and water is let out for irrigation. All works are completed.

12.1.2. Hippargi Project :

Dam & Allied works:

Barrage proper: Barrage proper: The barrage works are completed. b) Crest gates: Fabrication & erection of crest gates works completed and water impounded (stored) in the reservoir since 2004.

Lifting systems: The works for the lifting systems of two foreshore LI schemes, namely and Ainapur. The works of Ainapur lifting system and Halyal stage-I & II stage completed. Karimasuthi 3rd stage under Halyal LIS is completed and Savalgi –Tungal 4th stage completed under Halyal LIS .

Ainapur LIS: Works of Pump House, Rising main & Delivery Chamber are completed. Length of East canal is 0 to 27.52 km is completed & West canal is 0 to 12 km is completed. Except Dy No-7 remaining distributories completed and FIC’s are under progress. Water is let out in main canal and distributories.

Ainapur 2nd Stage: The works of Pump House, Rising main & Delivery Chamber are completed. East canal 0 to 30 km and West canal 0 to 7 are nearing completion. There are 11 Distributories in each canal and Two distributories in West canal and are in progress and nearing completion. The estimates of FIC’s are in approval stage. Water is let out in main canal and distributories.

Halyal L.I.S.: Works of pump House, Jackwell, Delivery Chamber & Rising Main under Stg-1 & 2 are completed. Work of Intake Canal is completed. Lead off canal works are completed. Halyal east canal km.0 to 40 99

completed. Except Dy No-16 remaining all distributories of each canal are completed. Halyal West canal from Km 0 to 20 are completed. Except Dy No.5,6,7 remaning distributories of west canal are completed. Water is let out in main canal and distributories.

Some of the FIC’s construction works of Halyal East & West canal are under progress. Taking administrative approval to the remaining estimates and tender is under progress.

Karimasuti L.I.S.: Head work completed. East canal from 0 to 75 completed. There are 40 Dys under east canal. Except Dy No-30 remaining distributories are completed. FICs survey work completed & Tenders invited. West canal from Km. 0 to 36 completed. There are 19 Dys. Except Dy No-7 remaining distributories are completed. Some of the FIC’s construction works of West canal and East canal are under progress. Taking administrative approval to the remaining estimates and tender is under progress. Water is let out in main canal and distributories.

Karimasuti 2nd Stage:- Head work and rising main works are completed. North Branch canal 0 to 7 Km and south branch canal 0 to 6Km tenders are completed. Out of 3 distributories of North canal one distributory is completed and remaining two distributories works are yet to be constructed. Distributories of South canal are completed. Survey work for FIC is under progress. Water is let out in main canal and distributories.

Savalgi-Tungal L.I.S.: Head work completed. except Km. 7 east canal from 0 to 24 are completed. The tunnel work in Km No.7 is nearing completion. West canal 0 to 7 Km all works are completed. Some of the FIC’s construction works of East canal are under progress. Taking administrative approval to the remaining FIC’s estimates and tender is under progress. Water is let out in main canal and distributories.

Land acquisition:

Submergence: The total submergence of land at FRL is about 3000 ha, out of which 1659 ha (4100 Acres) is cultivable land and 1341 ha (3314 Acres) is in river portion.

Canals: Total extent of cultivable land required for this project is about 9884A 15 Guntas.

The status of acquisition of cultivable land is as follows: a) Land acquired so far: 4057 A 24 Guntas b) Balance land under different stage of award: 5827A 31 Guntas c) An amount of Rs.55.81 crores have been paid towards acquisition of lands. 100

R&R works:

A total of 26 villages consisting of 15,291 families involving a population of 1,04,976 will be affected. Now the government has approved the R&R package amounting to Rs.555.00 crores. Action is being taken to implement the same .

Hipparagi Project due to back water of Krishna river 26 villages are affected, 11858 acquisition of structures is under progress, out of this Rs. 307.60 Crores compensation paid for 11002 structures. Remaining structures acquisition process is under progress.

For land acquisition process for 5456 A 20 G is in progress, out of this Rs. 6820 Lakhs paid for 5446 A 36 G, for remaining land 9 A 24 G the process of acquisition is under progress.

Land acquisition for R.C’s Rs. 727.30 Lakhs paid and remaining Rs. 94.70 Lakhs is under progress.

Government has accorded administrative approval to the revised project estimate of Hippargi project amounting to Rs.1521.78 Crores vide GO No. WRD/21/MBI/2008 dated 26.02.2008.

The Project is included in the PM’s Package and the GOI has released Rs.115.00 crores during 2008 – 09.

12.1.3. Markandeya Project:

101

Dam & Allied works: The dam and allied works have been entrusted to KSCC Ltd. The concreting work of dam is completed (Except curtain grouting), dyke works are also completed. Construction of parapet is completed and electrification work and erection of 6 crest gates are completed. Water is impounded since 2005.

Canal works: Total length of Markandeya Left Bank Canal is 15 Kms, works in Km no. 1 to 15 are completed. The Right Bank Canal has a length of 71 kms. Km.1 to 71 are completed. Water is let out on trial run upto Km.71.

Distributories: Total No. of distributory blocks are 45 under Right Bank Canal. All the works are completed except Dy.No.2,3 & 12 which are stopped due to land acquisition problem Under Left Bank Canal Dy.No.3, 4A, 4B 6A , & 6B are completed and balance Dy.works in 1, 2, 3, 4 and 5 are in progress.

R&R works: This project involves submergence of 7 villages affecting 833 families consisting of 3800 persons. Two Rehabilitation centers at Santi- Bastiwad and Waghwad are already completed. Shifting of PAFs to these R&R centers is also completed. Developmental works at this center are also completed.

Government has accorded administrative approval to the revised project estimate of Markandeya Project amounting to Rs.341.84 crores vide GO No. WRD 08 VEBYAMA 2003 dated 28/7/07.

Chachadi – LIS: The GOK has accorded administrative approval during April 07 for taking up the LI Scheme.

Murgod LIS: This scheme is envisages lifting of water from 36th km of MRBC to irrigate 1939 Ha of area. DTP has been submitted to MD KNNL, Bangalore for approval.

Chachadi LIS: This scheme is envisages lifting of water from 54th km of MRBC to irrigate 2718 Ha of area. Estimates & DTP for this scheme is under preparation.

102

12.1.4 Doodhganga project:

Doodhganga Irrigation Project is an interstate project of Maharastra and Karnataka. The project envisages construction of composite dam across the river Doodhganga near village Asangaon of Radhanagari taluk in Kolhapur District of Maharastra state. This project would provide irrigation benefits to 44,766 Ha. in Maharastra state and 15,167 Ha in Karnataka state. The planned utilisation is 28.00 TMC. Outlet potential created to end of November – 2013 is 3800Ha. The original estimated cost - Rs.124.00 crore (based on SR of 1999-2000). Further the comprehensive estimates of Rs. 1460.57 crores (including Rs. 309.80crores) at 2007-08 price level prepare by Govt. of Maharastra was approved by Planning Commission, GOI.

Allocation for Karnataka State – 4.00 TMC Project comprises of from 1st entry in to Karnataka: Nidhori Branch canal (NBC), Bidari Branch canal(BBC) Dattawad Branch Canal (DBC) and Kurundwad Branch Canal (KBC)  NBC : Total length is 25.607 Kms (21.567 Kms Only in Karnataka)  BBC : Total Length is 21.195 Kms (15.510 Kms, Only in Karnataka)  DBC : Total Length is 26.570 (26.57 Kms Only in Karnataka)  KBC : Total Length is 21.32 Kms ( 9.61 Kms Only in Karnataka)

Nidhori branch canal (State entry at 25th Km.)  Total Length of Nidhori branch canal : 25.607 Km  Works completed from Km.25 to50 (Tail end). All distributory blocks are completed.3617 Ha. of O.P. has been created on NBC.

Bidiri Branch Canal Total Length of Bidri branch canal : 21.195Km

The works are from Km. 46 to 49 and 54 to 62 are completed. The works in Km.44, 45 & 50 are under progress. For the works of Km. 51 and 52 (tunnel from Ch. 49.500 to 51.200 Km. with approaches and exit) tunnel work is in progress. Execution of approach and exit of tunnle is completed. 103

The tunnel 1100 Mts length completed. The work of Km. No. 53 stands deleted due to modified alignment. The works of Km. 63 to 65 are held up due to LAQ n Maharastra. Works of Dy. Blocks are under progress and nearing completion. An op of 182.72 Ha is created on Bidari branch canal.

Dattawad branch canal :

(i) Dattawad link canal is 0.700 Km work in Karnataka area is partly tackled. However, work is rescinded due to LAQ problem in Maharastra.

(ii) Dattawad RBC from Ch. 0+000 to Ch.7+650 km (tail end) LAQ proposals is submitted & from Ch. 0+000 to 17+000 alignment approval is awaited.

(iii) Alignment of Dattawad LBC from Ch.0+000 to 12+000Km is approved and survey of Km.13 to 19 (tail end) is in progress.

Kurundwad branch canal: The Kurndawad branch canal is to be executed by Maharastra State (including 9.61 Km long canal of Karnataka)

12.1.5 Hiranyakeshi LIS :

 Hiranyakeshi LIS is proposed to lift 8 TMC of water from Hiranyakeshi river to feed GRBC during Khariff season.

 8.00 TMC of water has been allocated under scheme ‘A’ of KWDT.

 This scheme has been proposed to meet the likely shortage of water due to over utilisation under GLBC.

 The said LIS has been entrusted to M/s Kirloskar Brothers Pvt. Ltd, on turnkey basis.

 The intake channel work is partially completed.

 Construction of Jackwell & pump house is completed.

 Erection of pumps, motors, starters and panels are completed.

 Raising Main work is nearing completion.

 Process of obtaining power line from LIS is in progress.

104

12.1.6 Sri Rameshwara LIS :

This lift Irrigation is proposed to irrigate 13800 Ha areas of , Ramadurga and Savadatti Taluks of Belgaum District by utilising the 2.2 TMC of water. The water will be drawn from Ghataprabha river by suitable intake structure.

Rising main: Total length 17.50 km. Work is completed.

Jackwell: Civil works completed, crane erected, pump erection completed.

Intake Channel: Total length is 275m. Work is completed except lining.

Land Acquisition : Intake Channel, Pump House, Jack well & Sub Station:

These are Located near Village covering an area of 5.10 Acres for which 6(1) Notification has been issued, awarded and payment made.

[ Electromechanical Components: Design & Drawings of Electro mechanical works such as Pumps, Motors, 110 KV sub-stations is approved. Erection work completed. The work is completed and line is charged. Trial run has been carried out.

Canal Network : Length of main canal & branch canal System is about 79 Km and the works are nearing completion. The length of distributory network system is about 224.38 and the works are nearing completion.

The total approved estimated cost of the Project is Rs.331.55 Crores.

Revised DPR & estimate amounting to Rs.331.55 crores has been cleared from Planning Commission of GoI.

Bellary Nala Project:

The Bellary nala irrigation project envisages to irrigate 8200 ha of land in Gokak and Saudatti taluks of Belgaum districts by constructing a dam across Bellary nala which is a main tributory to Markendaya river.

The master plan committee has allocated 1.68 TMC of water under scheme ‘A’ of KWDT.

The work construction of Bellary nala irrigation project has been entrusted to M/s. EPI Ltd (A Government of India undertaking) by Government of Karnataka.

Excavation for dam foundation, concreting in block 1 to 6 and 8 to 18 are partly completed. Beyond Ch: 423 mtr decision regarding providing Earthen embankment/ Gravity dam is to be taken.

105

Total length of main canal is 106 km, works in reach from km 40 to 85 is under progress.

All the works of main canal are carried out in various stages except canal length coming under forest area.

Government has accorded administrative approval to the revised project estimate of Bellarynala Irrigation Project amounting to Rs143.55 crores vide GO No.WRD 02 VEBYAMA 2005, dated 28/7/07.

At present, the works of Bellarynala project has been started and works are under progress.

12.1.7 Kinaye Project:

Kiniye irrigation project is at in Belgaum district envisages construction of an earthen bund across Mangathri Nala. It is proposed irrigate an area of 1200 Ha in Khariff season and 275 Ha in Rabi season which is spread over Kiniye, Bhadravadi, Ranikundi villages of Belgaum district.

The administrative approval has been accorded for Rs. 9.309 crores under GO dated 22.09.2007. The revised estimate for Rs.79.00 crores has approved.

Dam work has been handed over to agency for Rs. 58.32 crores. Work started.

12.1.8 Malikwadi Lift Irrigation Scheme (Rejuvenation works) :

This scheme comprises of rehabilitation work including Filling of tanks of Yadanwadi, Vadagol and Bainakwadi villages of Taluka and also including rejuvenation of lift irrigation scheme of Malikwad villge which is at stagnate at present. The work is entrusted on turn key basis by tender process to Shri S.R.Patil contractor. The work order is issued on 5/2012 and the contract is awarded for Rs 150.52 lakhs. The work is under progress now.

12.1.9 Kallol-Yadur Bridge cum Barrage :

The work of construction of Kallol-Yadur bridge cum barrage across Krishna river between Kallol-Yadur villages of Chikkodi Taluka is handed over to Nigam vide Govt ltr No. d¸ÀAE 21 J¸ïLJ£ï 2012 ¢£ÁAPÀ 27-3-2012. Detailed estimate for the above work is under preparation. 106

12.1.10 Sangam Barrage :

 Sangam Barrage is at across Hiranyakeshi river near Godagheri village of Hukkeri. The Government vide GO dated 4/10/2010 has administratively approved the DPR for Rs.11.05 crores.

 DPR for Rs. 41.00 crore has been submitted to MD KNNL, Bangalore.

 Tender evaluation is in process.

12.1.11 Filling of Shragaon – Basavanna Tank:

DPR for the work of filling of Basavanna percolation tank of chikkodi Tq is got prepared and administratively approved for Rs 351.15 lakhs vide GO No. d¸ÀAE-4/ «zÀÆUÀ 2012 ¨ÉAUÀ¼ÀÆgÀÄ, Dated: 16-11-2012 and the estimate is technically sanctioned vide CIN 329 dated: 11/2012 DTP for the above work is approved and tenders are invited. Single Tender for the work of Providing Lift Irrigation Scheme for filling Basavanna Percolation Tank near Shiragaon village from Dudhganga River in Chikkodi Taluqa, District.Belgaum on Turnkey Basis is got approved.

12.1.12 Filling up of Kadapur tank :

Detailed project report for the work of filling of Kadapur tank of Chikodi Tq from Krishna river is got prepared for Rs 390.00 lakhs and the estimate is Administratively approved by the Government vide G.O No d¸ÀAE/82/J£ïLJ£ï/2012 Dated: 2-11-2012. This project comprises of filling of the tank & there by raising the ground water table.

12.1.13 Filling of 18 tanks of Hukkeri Tq & 4 tanks of chikodi Tq. (Total 22 tanks) from Hiranyakeshi river:

Administrative approval for the above work for an estimated amount of Rs 49.50 crores is accorded by the Govt vide G.O No d¸ÀAE/39/ «¨ÁåE/2013/ ¨ÉAUÀ¼ÀÆgÀÄ Dated:19-3-2013 Detailed Project report for the above work is under preparation.

12.1.14 Sri Mahalakshmi Lift Irrigation Scheme:

107

The proposal for Shri Mahalaxmi LIS was prepared for Rs. 52.00 cores and forwarded to the WRDO vide T.O lrt No. 1631dt. 11-6-2010 and requested for water allocation of 1-17 TMC from the Govt. Accordingly Govt has allotted 1.17 TMC of water from Dudhaganga river for the above project vide G.O No.d¸ÀAE 49 PÉ©J£ï 2009 Bangalore dtd 19-3-2012 under Krishna Basin 23.00 TMC of water allocation. Under this 1.17TMC of water allocation 17 villages of Chikkodi Taluka drinking water & water required for 4861 Ha irrigation facility is covered.

At present, for the detailed survey, design and for preparation of detailed project report by adopting Lift Irrigation Project under drip irrigation Net work system and also proposal for construction of New barrage across Dudhaganga river on u/s of barrage is prepared for Rs 29.00 lakhs approved.

12.1.15 Tubachi – Babaleshwar Lift Irrigation Scheme:

This lift Irrigation is at Old in Jamakhandi taluka & proposed to irrigate 42500 Ha areas of Bijapur, Athani & Jamakhandi of Belgaum & Bagalkot District by utilising the 3.80 TMC of water from Krishna River during Kharif season.

Survey & Investigation work for an area of 42500 Ha is in progress. DPR for Rs 2642.45 crores has been submitted to MD KNNL, Bangalore vide t.o. ltr no. 7613 dt: 27.12.2013 for administrative approval.

The administrative approval has been accorded for Rs. 2488.97 crores under GO dated 28-02-2014.

12.1.16 Veerabhadreshwar Lift Irrigation Scheme:

DPR for the above project is got prepared for Rs 444.66 Crores. The report for the above scheme for providing irrigation facility to 22277 Ha area and allocation of 3.3 TMC water demand is submitted to Government for water allocation.

12.1.17 Kempwada Lift Irrigation Scheme:

Kempwad LIS scheme is considered under scheme “B” for water allocation. It is proposed to cover the 22 draught affected villages coming under Athani Taluka, Border area to irrigate about 27,462 Ha area. The Detail DPR is prepared for Rs 1120.36 crores and submitted to Government for administrative approval.

108

DETAILS SHOWING BUDGET ALLOCATION AND RELEASE OF GRANTS TO NIGAM (KNNL IRRIGTION NORTH BELGUM) FOR THE YEAR 2013- 14 (AS ON 31/03/2014) (Rs. in Crores) 1. KARNATAKA NEERAVARI NIGAM LIMITED 9(KNNL IRRIGTION NORTH BELGUM) Annual Sl. Release Head of Account allocatio Balance No. s n

1 AIBP 207.60 163.297 44.303 2 Special Development Plan - - - Budgetary support / grants (4701 99.25 185.22 -85.27 3 est.& works) 4 Special Component Plan 42.00 127.36 -85.36 5 Tribal Sub Plan 10.48 20.32 -9.84 6 Ayacut Roads 62.97 62.97 - Loan repayment / interest - - - 7 repayment Total 422.30 559.167 136.167

DETAILS OF PHYSICAL PROGRESS ACHIEVED FOR THE YEAR 2013-14 (Area in Ha) KNNL IRRIGTION NORTH BELGUM

Name of the project Target Achieved %

Ghataprabha Irrigation 1 - - - Project 2 Hipparagi Irrigation Project 15000 12829.85 85.53 Markandeya Reservior 3 - - - Project Dudhaganga Irrigation 4 1000 - - Project Lifting of water from 5 - - - Hiranyakesi river to GRBC 6 Ballary nala Project - - - 7 Shri Rameshwar LIS 6000 7332.96 122.20 8 Kinaye Irrigation Project - - - Total 22000 20162.81 91.65

109

DETAILS OF FUND POSITION OF KNNL (KNNL IRRIGTION NORTH BELGUM) FOR FY 2013-14 AS ON 31.03.2014 (Rs. In crores)

Grant Budget released Exp.projects Shortfall Balance to Pending Sl Allocatio from & debt against be bills as Particulars No n for FY GOK as service as on budget released on 2013-14 on 31.3.14 allocation to nigam 31.3.14 31.3. 14 1 Capital Grants (Rs.495-100+150-55.53=10) (4701 works & EST) 99.25 185.22 254.12 -154.87 -154.87 11.33

2 Dr Nanjundappa Pkg ------3 PM’s Farmers suicide Package(Hipparagi irrigation 148.55 208.74 319.77 -171.22 -171.22 - project) 4 AIBP a Ghataprabha - - 147.86 -147.86 -147.86 22.09 b Dudhaganga 7.91 7.70 8.60 -0.67 -0.67 2.70 C Rameshwar 115.64 115.92 117.77 -2.13 -2.13 27.25 6. SCP 42.00 127.35 127.36 85.36 85.36 6.09 7. TSP 10.48 20.32 20.31 9.83 9.83 0.89 8. Roads 62.97 62.97 62.97 - - 0.89 Total 486.80 728.22 1058.76 -371.58 -371.58 71.24 9. Debt Servicing ------(Rs.109 P & Rs.44.82 int) Grand Total 486.80 728.22 1058.76 -371.58 -371.58 71.24

110

KNNL IRRIGATION NORTH BELGAUM DETAILS OF BUDGET ALLOCATION BY GOK (Rs. In crores)

Budget Budget Budget Sl. Allocation for FY Allocation Allocation Particulars No. 2012-13 for FY 2013- for FY (Revised) 14 (RE) 2014-15 1 Amount Capital Grants (4701 est & works ) 105.75 99.25 Not yet release. 2 Dr Nanjundappa Pkg - - 3 PM’s Farmers Suicide Package-Others 198.27 148.55 - (Hipparagi Irrigation project) 4 PM’s Farmers Suicide Package-UTP - - - 5 AIBP a Ghataprabha Irrigation project 15.00 - - b Dudhaganga Irrigaton project 7.89 7.91 - c Sri Rameshwar LIS 75.00 115.64 - 6 IEBR - - - 7 SCP 72.36 42.00 - 8 TSP 40.07 10.48 - Total 514.34 423.83 -

9 Debt Servicing - Grand Total 514.34 423.83 -

12.2 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, MALAPRABHA PROJECT ZONE, DHARWAD.

The Malaprabha River originates near Ghats in Sahyadri and flows eastwardly for a length of 200Km before joining the River Krishna at Kudal Sangam in Bagalkot District. The annual average yield of the river is 1368m.cum (48.35tmc)

Malaprabha Project Zone, Dharwad was formed on 07/09/2007 in pursuance of the Government order No.WRD.137.SeASu:2007, Dtd:04/09/2007 with a view to increase the tempo of construction work in the Irrigation Projects as a result of increased provision of the plan allocation in the state.

Malaprabha Project Zone is incharge of the following projects.

On-going Schemes 1 Malaprabha Project 2 Harinala Irrigation Project Kalasa Nala & Bandhur Nala 3 Diversion Schemes. 4 Javaluhalla L.I.S. * 111

5 Bennihalla L.I.S. * 6 Kolachi L.I.S. * 7 Konnur L.I.S. * 8 Shiggaon L.I.S

(*) To irrigate suffering atchkat of tail end distributaries of MRBC / NBC, under Malaprabha Project.

So far, an irrigation potential of 1,96,132Ha, has been created under the above projects. An expenditure of Rs.1456.04Crores has been incurred under the above schemes to end of March-2013.

Out of the above schemes Harinala Project has been completed during 2006-07 and the remaining schemes are under different stages of progress.

The designed district-wise ultimate irrigation potential details are given below;

District Malaprabha (Ha.) Total (Ha.) Belgaum 61,773 61,773 Bagalkot 27,506 27,506 Dharwad 44,078 44,078 Gadag 62,775 62,775 Total Area:- 1,96,132 1,96,132

12.2.1 MALAPRABHA PROJECT

Malaprabha Project comprises a dam across the River Malaprabha, near Navilutheertha in Belgaum district to provide irrigation to an extent of

112

1,96,132Ha in Belgaum, Bagalkot, Dharwad and Gadag districts. Malaprabha River is one of the tributary of River Krishna.

DAM – (Masonry Gravity Dam):- It is a composite dam of 154.53mtr length and 40.23mtr height. The gross capacity of reservoir is 1068m cum (37.73tmc)

Malaprabha Right Bank Canal (MRBC) – 142Km. Distributaries under MRBC - 60 Nos. Malaprabha Left Bank Canal (MLBC) – 150Km. Distributaries under MLBC - 58 Nos

As far as AIBP assistance is concerned the Malaprabha Project suppose to have in completed by 31st March 2013, but actually the project is being completed by 31st March 2014.

The total irrigation potential created upto March 2014 is 196033 ha against target of 1,96,132 Ha.

The Total expenditure incurred upto 31st March 2014 is Rs.1442.55 Crores against approved estimated cost of Rs.1383.48 Crores.

Malaprabha Right Bank Canal:- Malaprabha Right Bant Canal is 142Km in length and has a major branch canal viz., Nargund Branch Canal of 42Km in length. The Malaprabha Right Bank Canal takes off from the Head regulator and runs through the Yallamma Hills through a 4.8Km long tunnel. The canal crosses tuprihalla (at Km.29) and Bennihalla (at Km.69) through aqueducts. It has two branches. east and West in Km.112. This has command area in Navalgund, Nargund and Ron talukas of Dharwad, Gadag Districts to irrigates an area of 1,21,392Ha.

Malaprabha Left Bank Canal:- Malaprabha Left Bank Canal is 150Km length with L.I.Scheme by Lifting of water at Km.9 of canal. The Malaprabha Left Bank Canal takes off from the main dam on the left flank. Piercing through the left side hill range trough a tunnel 1408m long. The canal further crosses hilly ranges near Katkol (Km.28 to 31) and Mudkavi (Km.65 to 69) through tunnels. The command area lies in Saudatti, Ramadurg taluk of Belgaum District & taluk of Bagalkot District. A chronically draught affected area to irrigate an area of 47,769 Ha.

Kolach Right Bank Canal:- The Canal takes off from Right Bank of Kolachi Weir near Ramadurga Kolachi Right Bank Canal is 64Km in length and irrigates 5,877Ha (Approximate 20,000acres) of Land in Ramadurga, Badami, Nargund and Ron talukas.

113

Lift Irrigation Schemes:- 10 No.s of foreshore Lift Irrigation Schemes are taken upto provide irrigation facilities to the displaced persons, rehabilitated along the foreshore of the reservoir. Irrigated an area of 26,931Ha.

Total Area Irrigated under Malaprabha Projects is 1,96,132Ha in which 1,86,890Ha FIC completed and Balance of 9,322Ha remains.

1) Dam is completed and water impounded since 1973.

2) Total length of MRBC is 142Km which is completed and it includes 60 distributaries which are completed.

3) Under MRBC major Branch Canal of NBC of 42Km which is also completed and FIC works for 11625Ha are remains.

4) Total length of MLBC 150Km and 58 distributaries all are completed. Only FIC work of 1,757Ha remains.

The financial progress of works so far achieved during 2013-14 year upto end of March-2014 is Rs.95.7570Crores which includes Rs.31.97Crores of expenditure on Land Acquisition and Rs.63.78 Crores towards works. The expenditure incurred on Malaprabha Project since inception till March-2014 is Rs.1442.55 Crores against revised DPR of Rs.1383.48 Crores.

NAME OF THE PROJECT MALAPRABHA PROJECT Location Naviluteertha Year of Inception 1960 Original and Latest estimated cost Original Estimated cost Rs.20.00 Crores (Rs. in Crores), including Administrative approval: GO No.PWD. administrative/ 59.GMP.77, B’lore Dated: 04/02/1980 Technical sanction approval number & Rs.162.09Crores Date. Technical sanction No.:CE,Irrigation(North)Zone, Belguam Reg.No.CIN.7. for June-1980 Rs.162.09Crores Latest Estimated cost Rs.1383.48Crores vide G.O No: WRD/51/MPS/2009, Bangalore Dated:07/10/2009 and investment clearance by Planning Commission, GOI vide No.2(54) 2010 WR, Dated:01/02/2010 Length of Canal M.L.B.C. M.R.B.C a) Main Canal, 150 Km. 142 Km. b) Branch Canal 26 Km. 42 Km. c) Distributories 280 Km 677 Km. 114

Length of ayacut roads/I.T.roads 282.62 Km Districts benefited Belgaum, Dharwad, Gadag, Bagalkot Bailhongal, Ramadurg, , Badami, Number of villages and Taluks Navalgund, Hubli, Naragund, Ron, Gadag Benefitted taluks. Number of W.U.C.S: a) Formed 265 b) Registered 227 c) Handed over 227 Programme during 2013-14 Physical Financial 99 Ha. Rs. 116.00 Crores Progress achieved up to end of March- -- Rs. 95.35 Crores 2014 Cumulative progress up to End of 1,96,033 Ha. Rs. 1442.55 Crores March-2014

12.2.2 HARINALA IRRIGATION PROJECT:

Harinala project envisages construction of an earthen dam across Harinala, a tributary to river Malaprabha to irrigate 3,480Ha in Bailahongal taluk of Belgaum Dist.

Dam & Allied works: The dam works including head regulators for LBC and RBC are completed. Water is impounded in the dam.

Canal works: The entire length of RBC (11Km) and LBC (9Km) are completed. Total potential of 3,480Ha under this project has been created. FIC works are completed.

R & R works: The project involves partial submergence of only one village involving 256 families and out of 256 R & R works for 58 families are completed. For balance of 198 families R & R works are under progress.

115

NAME OF THE PROJECT HARINALA IRRIGATION PROJECT Location Village Year of Inception 1998 Original Estimated cost - Rs. 0.83 Crores

Latest Estimated cost-Rs.73.00 Crores Original and Latest estimated cost Administrative Approval No: CE: 114: (Rs. in Crores), including MPS: 92 Dated 11/14.9.98 (Rs. 26.95 administrative/ Crores). Technical sanction approval number & Technical sanction: CEI (N): BGM: Date. Reg.No.CIN–17 for May 1999 (Rs.26.95

Crores). Length of Canal Left Bank Right Bank a) Main Canal 9.00 Km 10.72 Km Districts benefited Belgaum. Number of villages and Taluks Bailhongal taluk. Benefitted Physical Financial Programme during 2013-14 - Rs.0.50 Crores Progress achieved up to end of March- - Rs. 1.95 Crores 2014 Programme for 2013-14 (Physical - Rs. 0.50 Crores Financial) Cumulative progress up to end of 3,480 Ha Rs. 77.25 Crores March 2014

12.2.3 KALASA NALA AND BANDHUR NALA PROJECT:

These two projects envisage diversion of 7.56 TMC of water to Malaprabha dam by construction of dam across the above nalas and diversion canals. Administrative approval for these two projects is accorded by Government in August 2000. Forest clearance for these projects is pending for want of CWC clearance for the project. The in principle clearance given by CWC to these projects has been kept in abeyance and inspite of repeated attempts by Government of Karnataka, the Union Government has not been able to with draw the order of abeyance on “IN PRINCIPLE CLEARANCE”

The KNNL Board has recommended in its 25th meeting held on 7.6.2005 to take up works in non-forest area by entrusting the work to any Government agency. Accordingly the Government vide its order No.JASAME 22 VEBYATA 2004 (Part-1) Bangalore dated 9.10.06 has approved to take up Kalasa Nala Banduranala diversion schemes in non-forest area. (4.40 km out of 4.80 km of Kalasanala and 4.90 km out of 5.80 km of Banduranala).

116

Further the Government vide letter No.JASAME 22 VEBYATA 2004 dated.21.10.06 has given directions to take-up the above works through KSCC duly following all the necessary procedures as per KTPP Act 1999.

The Chief Engineer, KNNL, Irrigation(North)Zone, Belgaum has submitted an estimate of Rs.21.24 crores for construction of Kalasa Nala Dam and approval has been accorded to the same.

Since the project is a inter-state dispute project and some time was required for KSCC to take up works on tender basis, the works in non-forest areas were taken-up by entrusting 2 works on piece work basis, each not exceeding Rs.5.00 lakhs, in respect of Kalasa Nala diversion scheme.

In the meantime the Government vide Order No.WRD 36 VEBYATA 2006, Bangalore dated 15.3.2007, has approved to execute the works of Kalasanala diversion scheme in non-forest areas on piece work basis, till the tendering process for balance work is completed.

In this order, Government has withdrawn the works entrusted to KSCC and has instructed KNNL to proceed with tendering process for balance works immediately duly following the prescribed procedure as per KTPP Act 1999.

Accordingly tender for the balance work of ICC from Kalasa to Malaprabha River was invited and work is awarded and it is in progress.

Tenders are finalised for Phase–II of the balance work of ICC from Kalasa to Malaprabha River (Earthwork and Box pushing technique) and works are in progress.

Tenders of Rs.20.03 Crores have been awarded for the construction of 2 vent box at Ch:1920 to 2070M by box pushing technique (2nd Stage Balance works) from Ch:145 to 5005m for the link canal from Kalasa Dam to Malaprabha River.

NAME OF THE PROJECT KALASA NALA AND BANDHUR NALA PROJECT

Location – Kalasa Nala Project Nerse village - Bhandur Nala Project Year of Inception 2006 Year of completion (in case of Completed Under progress (Kalasa only) Projects) Original and Latest estimated cost Original Estimated Cost (Rs. in Crores), including administrative/ Kalasa Nala - Rs. 44.78 Crores Technical sanction approval number & Date. Bhandur Nala - Rs. 49.20 Crores Administrative approval No. a) Kalasa nala: ID.37.WBT. 2000: Dtd.22.8.2000 b) Bhandur nala:-.ID-4.WBT:2000: Dtd:22.8.2000. Tech.Sanction No: a) Kalasa nala - CIN.Reg.No.270, March 2002 b) Bhandur nala - CIN.Reg.No.269, March 2002.

117

Districts Benefited Belgaum, Dharwad, Gadag and Bagalkot Number of villages and Taluks Hubli-Dharwad & Other villages (Drinking water Benefited supply) Physical Financial Programme during 2013-14 Rs. 15.00 Crores for KalasaNala - Rs. 0.0 Crores for BhandurNala Progress achieved upto end of March 2014 Rs. 53.04 Crores for KalasaNala - Rs. 0.00 Crores for BhandurNala Programme for 2013-14 (Physical & Financial). Rs. 15.00Crores for KalasaNala - Rs. 0.00 Crores for BhandurNala Cumulative progress upto End of March 2012 Rs. 172.91 Crores under Kalasa Nala & Rs. 0.00 Crores under BhandurNala Brief description: The work of Inter-Connecting channel from Kalasa reservoir to Malaprabha river has been entrusted on tender basis and works are under progress.

12.2.4 JAVALAHALLA L. I. SCHEME:

The project envisages diverting a part of water flowing through Javalahalla a tributary of Malaprabha river near village of Taluk , Belgaum Dist. by constructing a diversion structure. The water is diverted to a Jackwell through an intake canal. The water is then lifted by pumping through rising main fed to existing canal net work of Distributory under NBC to provide irrigation facility to 4736Acres.(1917Ha.) suffering atchkat of Shirasangi Distributory under NBC command. The water allocation under scheme `A` is 0.29 tmc. Javalahalla LIS has been included under since 2005-06 before bringing the project under AIBP i.e., as on 17/05/2005. The estimated cost of the project is 333.10 lakhs. The work is entrusted to M/s: Coremandal Prestcrete Pvt.Ltd., Hyderabad contract amount Rs.4.35Crores. The Project is completed except finishing work & electrical supply from HESCOM which is under progress.

Protection works like pitching, revetment and construction of crayons and trial run of the pumping machinery is to be made i.e., (confirming)

NAME OF THE PROJECT JAVALUHALLA L.I. SCHEME Location: Kittur village Year of Inception: of date of the working 2005 – 18/07/2005 once site Year of completion (in case of Completed Under progress Projects) Original Estimated: cost. Rs. 3.33Crores Original and Latest estimated cost Administrative approval: WRD: 03:NIN:95 (Rs. in Crores), including Dtd:23.08.03 administrative/ Technical sanction: Chief Engineer, Technical sanction approval number & Irrigation(N), Belguam Reg.No.CIN.10 for Date. April – 2003

118

Length of Canal: This scheme provides irrigation facilities a) Main Canal to suffering atchkat of 1,917Ha under b) Branch Canal NBC & MRBC. Works like diversion weir, intake canal, jack well cum pump house, c) Distributories raising main and delivery chamber are d) F.I.C. completed and electrical supply work is completed. Districts benefited Belgaum Number of villages and Taluks Benefited Ramdurg Physical Financial Programme during 2013-14 - Rs. 0.50 Crores Progress achieved upto End of March- - Rs. 0.113 Crores 2014 Programme for 2013-14 (Physical & - Rs. 0.50 Crores Financial). Cumulative progress up to end of March - Rs. 4.62 Crores 2014

12.2.5 BENNIHALLA L.I. SCHEME (5 NOS.):

It is constructed near Nargund taluk of Gadag district. The scheme proposes series of weirs at Banahatti, Kuralageri, Surkod, and Radder to irrigate the suffering atchkat of 3,868Ha under NBC.

Banahatti: Deliver chamber completed, raising main is completed. Jackwell-cum-Pumphouse work is completed upto 3rd stage. Other works like Diversion weir, intake canal and control room are completed. Pumps & motors procured yet to be installed.

Kuralageri: Delivery chamber raising main Jackwell-cum-Pumphouse and control room work is completed. Other works like diversion weir partly completed. Pumps and motors which is under operation electrical work is completed. L.I.Scheme is in functioning.

Surkod: Head works like intake canal, Jackwell-cump-Pumphouse, delivery chamber and raising main. Control room and Diversion weir is completed. Pumps and motors are installed and electrical work completed. L.I.scheme is in functioning.

Khanapur: Head works like intake canal, Jackwell-cum-Pumphouse and control room are completed. Diversion weir is completed and raising main is completed. Additional delivery chamber is to be started. Pumps and motors are installed and electrical work in under progress.

119

Radder Naganur: Diversion weir, intake canal, Jackwell-cum-Pump house, control room, delivery chamber and raising main are completed. Pumps and motors are installed and power line work is also completed.

NAME OF THE PROJECT BENNIHALLA L.I. SCHEME (5 NOS.) Banahatti, Kurlageri, Surkod,Khanapur, Location Reddar Naganur Year of Inception 2005 Original and Latest estimated cost Original Estimated cost: Rs. 17.33 Crores (Rs. in Crores), including Administrative approval: WRD/ administrative/ 58/MPS/1999 (P), B’lore dated: 23.08.03 Technical sanction approval Technical Sanction: CE I (N) Reg.No.163 number & Date. for August 2005. Length of Canal This scheme provides irrigation facilities to a) Main Canal suffering atchkat of 3,868 Ha. Under NBC & MRBC. Works like diversion weir, intake b) Branch Canal canal, jackwell cum pump house, raising c) Distributories main and delivery chamber are under d) F.I.C. progress. Districts benefited Gadag Number of villages and Taluks Nargund Benefited

12.2.6 KOLACHI L.I. SCHEME:

The project envisages diverting a part of water flowing through Bennihalla at village Asuti of Ron Taluk, Gadag Dist. by providing obstruction in the form of low height diversion structure. The water is diverted to a jackwell through on intake canal. The water is then lifted by pumping fed to existing canal network of KRBC through rising main to provide irrigation facility to 3800 Acres (1538 Ha.) suffering atchkat of KRBC Command.

The water allocation as per the revised Master Plan of Krishna Waters under Scheme `A` is 0.30 tmc. The estimated cost of the project is Rs.190.61 lakhs. The work is entrusted to M/s. SPML, Bangalore on turnkey basis. The work is started on 12-9-2005 & it is proposed to be completed by end of December-2013.

The above LIS is entrusted to M/s. SPML on turnkey basis.

The Project is completed except finishing work & electrical supply from HESCOM which is under progress.

Name of the Project KOLACHI L.I. SCHEME

120

Location: Asuti village Year of Inception: 2005 Year of completion (in case of Under progress Completed Projects)

Original Estimated cost: Rs. 2.25 Original and Latest estimated Crores cost Administrative approval: WRD. (Rs. in Crores), including 58.MPS.1999 (P) (K), Bangalore dated: administrative/ 23.08.03. Technical sanction approval Technical Sanction:CEI (N). Reg.No.162 number & Date. for August 2005.

Length of Canal This scheme provides irrigation facilities to suffering atchkat of 1538 Ha. Under a) Main Canal Kolachi right bank canal & MRBC. b) Branch Canal Works like diversion weir, intake canal, jackwell cum pump house, raising main c) Distributories and delivery chamber are completed and electrical supply work is under d) F.I.C. progress. Districts benefited Gadag Number of villages and Taluks Ron Benefitted

12.2.7 KONNUR L.I. SCHEME:

The project envisages diverting a part of water flowing through Malaprabha River near the village Konnur of Naragund Tq. Gadag Dist. by constructing a diversion structure. The water is diverted to a jack well through an intake canal. The water is then lifted by pumping fed to existing canal net work of NBC through rising main to provide irrigation facility to 3932 Acres (1591 Ha.) suffering atchkat of NBC command. The water allocation under Scheme `A` is 0.39 tmc. The estimated cost of the project is Rs.884.36 Lakhs. The work is entrusted to M/s. SPML, Bangalore on turnkey basis. The work is started on Dtd:12/09/2005 & it is proposed to be completed by end of December-2013. The work is in progress.

NAME OF THE PROJECT: KONNUR L.I. SCHEME Location: Konnur village Year of Inception: 2005 Year of completion (in case of Under progress. Completed Projects) Original and Latest estimated cost Original Estimated cost: Rs. 6.15 Crores (Rs. in Crores), including Administrative approval: WRD. 58.MPS.1999 administrative/ (P), B’lore dated: 23.08.03 Technical sanction approval Technical sanction No: CE I (N) Reg.No.161 121

number & Date. for August 2005.

Length of Canal: This scheme provides irrigation facilities to a) Main Canal suffering atchkat of 1591 Ha. Under NBC & MRBC. Works like diversion weir, intake b) Branch Canal canal, jackwell cum pump house, raising c) Distributories main, pumping machinery and electrical installations are nearing completion. Delivery d) F.I.C. chamber is completed.

Gadag Districts benefited

Number of villages and Taluks Nargund Benefited

FOR BENNIHALLA, KONNUR L.I.S & KOLCHI LIS Physical Financial Programme during 2013-14 - Rs. 2.00 Crores Progress achieved upto end of March-2014 - Rs. 1.12 Crores Programme for 2013-14 (Physical & Financial). - Rs. 2.00 Crores Cumulative progress upto end of March - 2014 Rs. 23.67 Crores

12.2.8 SHIGGAON L.I. SCHEME:

The Shiggaon is envisages providing irrigation facility to draught area of Hangal, Shiggaon and Savanur taluks of Haveri District and providing drinking water facility by filling the existing MI tanks within the command area and proposed bandaras. It is proposed to utilize 1.5 TMC of water from River to provide irrigation facility to 9,900 ha. of lands in Hanagal, Shiggaon and Savanur taluks. The Government has accorded the Administrative approval for Rs.238.00 crores vide G.O.No.JaSamE 98 MMB 2008, Bangalore Dtd:13/01/2009 and entrusted the work to KNNL for execution.

The salient features of the Shiggaon LIS are as follows:- 1) Name of the Project : Shiggaon LIS 2) Name of the river : Varada River 3) Purpose : Irrigation 4) Climate : Moderately warm

LIFTING OF WATER FROM VARADA RIVER:

1) Name of the river : Varada 2) Purpose : Irrigation 3) Lift point location : Near Halasur village, Savanur taluk,

122

Haveri District. 4) Quantity of water to be lifted : 1.50 TMC

The providing sprinkler irrigation work is complete by M/s: Jain irrigation Systems, Jalgaon.

NAME OF THE PROJECT: SHIGGAON L.I. SCHEME Near Halasur village of Savanur taluk in Location: Haveri Dist. Original and Latest estimated cost Rs.238.00 Crores (Rs. in Crores), including administrative/ Administrative approval: No. WRD/98/MMB/ Technical sanction approval number & 2008, Bangalore Dtd:13/01/2009. Date. Planned irrigation potential 9,900 Ha. Districts benefited Haveri Shiggaon, Hanagal and Savanur taluks of Number of villages and Taluks Benefitted Haveri district. No. of M I Tanks for stabilization 5 No. of Bandaras 6 Physical Financial Programme during 2013-14 - Rs. 40.00 crores Progress achieved upto End of March- Rs. 31.40 crores - 2014 Programme for 2012-13 (Physical & Rs. 75.00 crores 2,660 Ha Financial). Cumulative progress up to end of March Rs. 255.46 crores 9,900 Ha. 2014 Works like intake canal, jackwell cum pump house, raising main, pumping machinery are Brief description entrusted on tender basis and are under progress.

INTAKE CANAL-WATER FILLED

Finished View of Substation & Control Room & Fencing work

123

Pumping Machinery - Finished View

Finished view of sub-station and control room and fencing work:

Pumping Machinery finished view

124

Sprinkler & Lateral Lines:

125

12.3 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER TUNGA PROJECT CIRCLE, SHIMOGA

The following are the projects under the jurisdiction and control of Upper Tunga Project Circle, Shimoga.

1) The Upper Tunga Project 2) The Tunga Lift Irrigation Scheme 3) Lift Irrigation Scheme 4) Itagi-Sasalwad Lift Irrigation Scheme 5) Guddada Mallapura Lift Irrigation Scheme 6) Ubrani-Amrutapura Lift Irrigation Scheme 7) Sanyasikoppa Lift Irrigation Scheme 8) Dandavathi Reservoir Project 9) Kalluvaddahalla New Tank 10) Thiluvalli Lift Irrigation Scheme 11) Nidige & Purle tanks 12) Tunga Modernisation 13) Kachavi Lift Irrigation Scheme 14) Bhadra Reservoir Project 15) Tunga Anicut Project 16) Gondi {Bhadra} Anicut Project 17) Harihara-Byaranapada Lift Irrigation Scheme 18) Vani Vilasa Sagar Project 19) Ambligola Reservoir Project & Anjanapura Project 20) Dharma Project 21) Rani Feeder canal 22) Madaga – Masur Tank 23) Gayatri Reservoir Project 24) D.B. Kere Pickup Project 25) Jambadahalla 26) Hodirayanahalla Diversion Project 27) Huchurayanakere 28) Bhimasamudra Tank 29) Shilavantha Koppa Dodda Kere 30) Construction of Bridge near Mattur – Hosalli across 31) Hihole Reservoir 32) Shifting of Davangere Villages 33) Construction of Bridge near Gondi across the 34) Construction of feeder Canal from Annehala tank to Bhimasamudra tank. 35) Construction of link canal from Hebbehalla to Madagada tank in Tarikere taluk 126

12.3.1 UPPER TUNGA PROJECT:

The river Tunga is a major tributary of river Tunga Bhadra rises in and joins mother tributary Bhadra at Kudli about 14.50 KM from Shimoga. Upper Tunga project envisages construction of new dam across Tunga River at 100.00 meter down stream of existing Tunga Anicut near Gajanur in Shimoga Taluk and construction of Upper Tunga Main Canal; for a length of 270.00 km. It includes construction of tunnel of 4.00 km length and also distributary net work.

It is envisaged to create an irrigation potential of 80,494 hectares in Shimoga, Davanagere and Haveri Districts by utilising 12.24 TMC of water from River Tunga.

The Government of Karnataka has accorded administrative approval for this project vide No.ID: 25: MMM: 91: Bangalore dated: 03-10-1991 for Rs. 271.41 Crores and vide No.WRD: 38:WBP: 2005 (P):Bangalore dated: 21.11.2006 for Rs. 1,052.33 Crores and vide No.WRD:234:VIBYAYI:2013 dtd:05-10-2013 for Rs.2561.88 Crores. The project is under the control of Karnataka Neeravari Nigama, Bangalore since 14.6.1999.

DAM AND ALLIED WORKS: - Dam work is completed in all respect. Water is being stored in the dam since 2007. The instrumentation work and electrification works are completed. Power block portion of mini hydrl project is completed and further work of power house with tail race channel is taken up by private agency. 127

Head regulator: Construction of regulator at Km.0145 is completed for providing hoisting arrangement for 5 gates is completed & Commissioned.

CANAL AND DISTRIBUTARY NETWORK:- Upper Tunga Project includes construction of 270.00 Km lengths of Main Canal including CD works, lining and Distributory Network. At present main canal alignment is approved up to 242 Km. Canal work up to Km 212 nearing completion. Work are under progress in Km 212-242 & Final allignment survey is in progress from Km 242-270 water is let out in canal up to 204.00 Km & 55045 Ha. of potential created.

Distributory:

Dist.No.1: Off-take point at Km108.35. Total length is 20.58 Km. Works are completed.

Dist.No.2: Off-take point at Km. 166.267. Total length is 56.91 Km. Works are completed from 0 Km. to 30 Km. From Km 30 to 40 Balance works are nearing completion.

Since Alignment beyond 40 km runs in reserve forest Alternative alignment proposal is approved avoiding forest land and estimates under preparation.

Dist.No.3: Off-take point at Km176.83. Total length is 23.00 Km. Works are completed. Dst No.4 : Oftake point @ Km. 201.055 Total length is 20.32 Km. works are Completed. Dst No.5 : Oftake point @ Km. 211.035 Total length is 12.58 Km. all works under progress except from 0.00 to 4.00 km. including aquaduct.

Dst No 6 : Detailed Alignment survey under progress.

R & R works: Three villages of Thirthahalli taluk and two villages of N.R.Pura taluk have been affected due to construction of Upper Tunga Project. 208 structures are affected. Necessary deposits are paid to SUDA for formation of lay-out and site to PAF. Also, Rs.20.475 crores of ex-gratia is provided as per the decision of R&R Committee out of which realistic proposal amount is Rs.19.71 crores, so for Rs.14.00 crores have been disbursed and balance Rs.5.73 crores to be disbursed.

During the year 2013-14 the grant allotted is Rs.100.00 Crores and the expenditure incurred up to end of March 2014 is Rs. 253.61 Crores. Since inception of project, cumulative expenditure to the tune of Rs. 1770.32 Crores has been incurred.

128

12.3.2 TUNGA LIFT IRRIGATION SCHEME

Tunga lift irrigation scheme was earlier proposed near Gajanur to Lift 1.428 TMC water from D/Stream of UTP reservoir and to feed 3 tanks namely , Barehalla and Gowdanakere tanks of Shimoga taluk and to irrigate 5162 Acres in premonsoon and 4870 acres in post monsoon period.

For this project Government has accorded administrative approval vide GO: ID: 58: MMM: 05: Bangalore dated:27-02-1999 for Rs 24.12 Crores and technical sanction was accorded for same amount by Chief Engineer on 30- 03-1999.

The proposal of alternative alignment avoiding the forest land is surveyed and the scope of project is extended from Gowdana kere to Savalanga tank including providing link canal to feed 29 tanks in between amounting to Rs.71.33 crores is prepared. The clearance from TSC and Board of KNNL for the revised amount is obtained. After obtaining administrative approval from the Government, Technical sanction to the estimate amounting to Rs. 71.33 crores is accorded vide CER No. 367/12- 13 dated:02-11-2012. Presently the project is taken up on turnkey basis and works are under progress.

During the year 2013-14, the grant allotted is Rs. 5.00 Crores and expenditure of Rs.12.25 crores has been incurred and total expenditure since inception is 12.47 crores.

12.3.3 BASAPURA LIFT IRRIGATION SCHEME:

This project envisages lifting of 1.60 Cumecs of water from River Varada near Basapura village in 2 stages to irrigate 2000 ha. of Land, pertaining to 13 villages of Hangal Taluk, Haveri District. An allocation of 0.60 TMC of water for utilisation in provided for this project by the Krishna Water Tribunal. Administrative approval has been accorded for this project vides G.O. No. ID 20/MMM/96-97 dated 9-4-96 for Rs. 936.00 Lakhs. CE, UTP Zone, Shimoga has accorded technical sanction for Rs. 936.00 Lakhs on 31-6-1996. Latest estimated cost of the project is Rs. 35.15 crores.

The project is transferred to KNNL during August-03. Presently, Stage I work of Electro-Mechanical Components & other head works canal works is completed. Distributory net works is completed and water letout in the canal to irrigate 890 hectares. FIC works are completed. Stage-II works entrusted on turn key basis. Work is under Progress.

During the year 2013-14 the grant allotted is Rs. 2.00 crores and the expenditure incurred up to end of March 2014 is Rs. 0.69 crores. Since inception up to end of March 2014, cumulative expenditure of Rs. 23.14 129

crores has been incurred on the project and 890 Ha. of potential created under Ist stage.

12.3.4 ITAGI-SASALWAD LIS:

This project envisage lifting of water from River Tungabhadra near Itagi village, Taluk, Gadag Distrist, in one stage to cater the irrigation requirements of Khariff & semi dry crops to an extent of 1983 hectares belonging to Shirahatti, Mundargi and Haveri Taluk. The Government accorded Administration approval for Rs. 427.00 Lakhs on 21-09- 1992 and subsequently revised administrative approval was accorded for Rs. 800 lakhs on 24-4-96. Chief Engineer, UTP Zone, Shimoga accorded technical sanction for Rs. 800 Lakhs to the Project, on 5-6-96. An allocation of 0.55 TMC of water for utilization is provided for this project by the Krishna water Tribunal. Latest estimated cost of the project is Rs. 23.78 crores.

 Electro-mechanical works like jackwell cum pump house, rising main, etc, have been entrusted to M/s. Arun Engineers on turnkey basis. This work is Completed and Commissioned.

 The project comprises of 25.517 km of RBC and 10.907 km, of LBC. The LBC i.e. 10.907 km has been entrusted on tender basis and all the works are completed. Out of the total length of 25.517 km, all works of RBC works are completed.

 The distributory network coming under RBC and LBC canal is entrusted to 3 agencies and completed. F.I.C. works are also completed.

Power required for this project is approved by HESCOM and deposit has been made to HESCOM. The work for getting power supply from Holitagi sub-station to jack well, pump house is Completed & Commissioned.

During the year 2013-14, the grant allotted is Rs. 1.00 crores and the expenditure incurred up to end of March 2014 is Rs. 0.25 crores. Since inception of the project an amount of Rs. 21.10 crores has been spent up to end of March 2014.

12.3.5 GUDDADAMALLAPURA LIFT IRRIGATION SCHEME:

The scheme envisages lifting 1.00 TMC of water in two stages from Varada river near Byatanal to irrigate 13000 acres (5261 Ha) of lands in Byadagi taluk of Haveri district. The above LIS’s entrusted to M/s. Coramandel Prestcrete Pvt. Ltd, on turnkey basis. The agency has stopped the work. The work was rescinded as per the instruction of the TSC. Agency fixed for the balance work by inviting 130

fresh tenders. The original site of Jackwell/pump house was shifted to new place due to foundation problem and works completed.

Jack well/pump house: Completed Raising main-I: Completed. Delivery chamber-I&II: completed Gravity Canal-I: Completed UG sump and pump house: Completed Raising main-II: Completed Gravity canal-II: Completed

During the year 2013-14, the grant allotted is Rs. 29.48 crores and the expenditure incurred up to end of March 2014 is Rs. 13.05 crores. Since inception of the project an amount of Rs. 91.06 crores has been spent up to end of March 2014. It is one of the project assisted under AIBP.

UBRANI-AMRUTHAPURA MULTIPURPOSE LIS:

This scheme was a part of Upper Bhadra Project Stage-1, which was separated as per Government order No.WRDO/ 63/ «¨sÁå.vÀ./ 2000 Bangalore ¢: 23-8-2003. The Main aim of this project is (a) drinking water purpose and (b) Filling of 57 Tanks of Tarikere Taluk & 89 Tanks Channagiri Taluk.

This project comprises of 2 stages costing Rs. 92.40 Crores. Presently works under both stages completed & project commissioned.

During the year 2013-14 the grant allotted is Rs. 5.00 crores and the expenditure incurred up to end of March 2014 is Rs. 11.51 crores. Since inception upto end of March 2014, cumulative expenditure of Rs. 126.70 crores has been incurred for this project.

12.3.6 SANYASIKOPPA LIS:

Sanyasikoppa lift irrigation scheme envisages construction of anicut across Kumudavathi River near Sanyasikoppa village in Shikaripura Taluk, Shimoga District to irrigate 1791 hectares. The Government has accorded administrative approval Vide G.O.No.ID/ 161/MMI/2003 dated: 25-3-2006 for Rs.10.00 Crores for this Project. Technical sanction is accorded for Rs. 9.97 Crores. work is take up on turnkey basis and works are nearing completion.

During the year 2013-14, the grant allotted is Rs. 1.00 crores and the expenditure incurred is Rs. 0.04 crores Since inception upto end of March- 2014 cumulative expenditure of Rs. 11.07 crores has been incurred.

12.3.7 DANDAVATHI RESERVOIR PROJECT:

Dandavathi Reservoir project in Soraba Taluk of Shimoga District envisages to provide irrigation facilities to 6933 Ha in Soraba and Shikaripura taluks of Shimoga districts by constructing reservoir across Dandavathi river. Further a provision is made to provide drinking water facilities to small

131

hamlets, filling of MI tanks within the command area and sub soil replenishment.

The Government vide GO dated 12.01.09 has administratively approved the DPR for Rs. 272.00 crores. Agency for construction of Dam & Allied works is entrusted. work to be started. During the year 2013-14, The grant allotted is Rs. 1.00 crores and the expenditure incurred is Rs. 2.58 crores only. Cumulative expenditure upto March 2014 since inception of project is Rs. 5.37 crores.

12.3.8 KALLUVADDAHALLA NEW TANK:

The project is proposed for construction across Kalluvadda Halla near Shikaripura taluk. It is proposed to provide an irrigation facilities to an rea of 1950Ha in 14 villages of Shikaripura taluk. The Government vide GO dated 30.08.2006 has administratively approved the said project for Rs. 20.42 crores based on the estimate by MI department and transferred to KNNL for implementation. The Revised DPR for the Project for Rs. 44.00 crores is submitted to Nigam for according approval to same.

During the year 2013-14 the Grant allotted is Rs. 0.10 crores and no expenditure has been incurred. Project is yet to be started.

12.3.9 TILUVALLI LIFT IRRIGATION SCHEME:

The Thiluvalli LIS in Hanagal taluk of Haveri District by lifting water from Varada river envisages to irrigate 2500 Acres of land during Khariff season under Hangal taluk of Haveri District and rejuvenation of Thiluvalli Doddakere, Siddanahonda, Yethinahalli, Chikkatti and Hiriyara tank and canal. The Villages benefitted are Thiluvalli, Inam-Lakmapura, Yettinahalli (T) of Hangal Taluk in Haveri District. The government vide GO dated 05.01.2010 has administratively approved the revised estimated amounting to Rs. 34.00 crores and technical sanction to the estimate amounting to Rs.41.76 crores is accorded by CE vide CER No.279/10-11 dtd:19-01-2011. I stage work was entrusted on Turn key basis for Rs. 18.87 Crores. Work is under progress and estimate is prepared and placed before Nigam ERC for taking up 2nd stage works.

During the year 2013-14 the grant allotted is Rs. 8.00 crores and expenditure incurred is Rs. 6.69 crores. Since inception of project to and of March 2014 cumulative expenditure of Rs. 7.78 crores has been incurred.

12.3.10 NIDIGE PURLE TANK DEVELOPMENT:

NIDIGE TANK;

Nidige tank is located in mid way between Shivamogga & Bhadravati, Besiders Tumkur Honnavar National Highway. This tank to being feeded from Bhadra Left bank canal. This tank is having as water spread area of 18.00 Ha. ( 44 A-21 G). This tank has been handed over to Nigam vide G.O. No. 247 / JA.JA.©. 2006 / ¢:24-1-2007 for improvement including boating Center. An estimate was prepared for Rs. 900 lakhs & placed before the TSC. The matter was discussed in

132

76th meeting held on 13-4-2007 and sub-Committee as formed. The sub- Committee inspected the spot and as per the instruction given the estimate was splet in to two parts in the I-Phase an estimate amount for Rs. 477.00 was prepared. The same estimate has been recasted for Rs. 655.00 lakhs and submitted CE’s office. Then the NH widening work was taken up by High-way department and is completed. Hence for the revised DPR reinvestigation survey estimate is also prepared for Rs. 180.00 lakhs and submitted to CE’s Office.

PURLE TANK;

Purle tank is located 6 Km from Shimoga City situated between Shimoga- Holehonur Road, Solapura-Mangalore National High Way ( N.H. 13) at Purle village. This tank is being feeded from Tunga right bank Canal and Bhadra left bank canal. This tank having an water spread area of 35 Acr 21 Guntas ( 14.38 Ha.) This tank has been handed over to Nigam vide G.O. No. WRD/247 /MMB/ 2006 Dated: 24-01-2007 for improvements including Boating Centre. Recreation Centre. An estimate prepared Rs. 940.00 Lakhs and placed before the TSC. The matter was discussed in 76th Meeting held on 13.04.2007 and sub-committee was formed. The Sub-Commiittee has inspected the spot and as per their instruction taken land scope consultant and prepared estimates in two part. ( Phase-1 & Phase-11). The Phase-1 estimate including Deepending the Tank. Formation of Bund, Silt Trap, inlet Way, Entrance Arch / Ticket Couter etc., Hence, the Phase-1 Estimate has been during 2013-14, a grant of Rs. 0.10 crores is allotted and no expenditure is incurred till March 2014 at present proposal for dropping the above work from Nigama is submitted.

12.3.11 MODERNISATION OF THE TUNGA ANICUT PROJECT:

Tunga Anicut is constructed across Tunga River near Gajanur village, Shimoga Taluk & District of Karnataka State in 1956 nearly about 50 years old. At the same time left Bank canal and right bank canal also constructed. The project consist of modernization of the canal for entire length by providing CC lining and renovation of damaged a canal structures like Head sluice, escapes sluice, Inlets, washing ghat, off take outlets etc. to feed the water to the tail end reaches and to save the water. There will be a reduction of wastage of water upto an extent of 6.25 TMC., there by utilization of water will be reduced to 5.25 TMC as against the present 11.50 TMC. The saving water will be utilize to Upper Bhadra Project.

The length of Right Bank canal is 52.00 Km with 38 distributaries of total length 54.06 Km. The length of left bank canal is 100.00 Km with 62 distributaries of total length 142.00 Km gross command area of Right bank canal & left bank canal is 9078.00 Ha.

The detailed project report and estimate has been prepared for Rs. 206.00 crores and submitted for administrative approval to 120 TSC meeting held on 18-2- 2011. As per direction of the Technical sub-committee Estimate has been recasted for Rs. 309.00 crore and Administrative approved by Government is accorded vide No. WRD:23:MMB: 2012 dated: 28-06-2012. The DPR is submitted to CWC for clearance and compliance to observation raised by CWC is submitted.

For the year 2013-14 a grant of Rs. 15.00 crores is allotted and the expenditure incurred to end of March-2014 for Rs. 0.46 crores only. (Survey work) The Project is yet to be commissioned. 133

12.3.12 KACHAVI LIFT IRRIGATION SCHEME:

The project envisage lifting of 0.15 TMC of water from Varada river near Kachavi village, Soraba Tq. Shimoga district for filling of 21 tanks under 11 villages to overcome the water scarcity in these villages. Administrative approval is accorded vide G.O.No.WRD/14/MMB/2011 dtd. 18-12-2012 for Rs.16.50 crores, presently the preparation of DPR is under progress. During 2013-14 a grant of Rs.1.00 crores is allotted and no expenditure is incurred till March-2014.

12.3.13 TUNGA MODERNISATION:

Tunga anecut constructed earlier across the river Tunga in Shimoga District, near Gajanur village during 1955 irrigates an area of 8705 Ha coming in the districts of Shimoga and Davanagere. By retaining the same canal system water is now being supplied through upper Tunga dam newly constructed at 100 M below the old Tunga anecut. As the canal constructed was unlined, at many reaches canal has lost its shape and seepage was observed in the structures. Hence, it was planned to Modernise the whole canal system by providing CC lining to canals and by renovating and reconstructing the structures. The Government of Karnataka has administratively approved the project for Rs.309.00 Crores vide GO No. Ja. Sam. E/23/MBB/2012,Bangalore, dated:28.08.2012. The DPR of this project is submitted to CWC for obtaining clearance for getting AIBP assistance. Work will be taken up after getting CWC clearance.

BHADRA RESERVOIR PROJECT:

Bhadra Dam is constructed across Bhadra River near Lakkavalli (village), Tarikere (Taluk) Chickamagalur (District). This project is a Multi purpose Project provides Irrigation facility to on extent of 1,05,570 Ha. and also have power generation of 39.20M.W. Capacity. The details of canals coming under this project are as follows.

Sl. Length Atchakat Canal No. in Kms in Ha. 1. Bhadra Right Bank Canal 103 .00 17274 2. Bhadra Left Bank Canal 77.00 8300 3. Anveri Branch Canal 67.00 6319 4. Malebennur Branch Canal 48.00 23774 5. Davanagere Branch Canal 90.00 45623 6. Harihara Branch Canal 20.40 - 7. Devarabelakere Pickup 59.20 4280 Project Total: 464.60 1,05,570

12.3.14 BHADRA MODERNISATION:

134

The canal coming under the Bhadra reservoir was constructed 46 years ago & the canals were without concrete lining & because of this the canal lost its shape & size. So, now the intension is to give a proper shape & size for the canal by providing concrete lining & supply the water till the tail end.

Modernisation of Bhadra Canal System amounting Rs.951.00 crores has been Administrative approved vide Government letter d¸ÀAE 20 MBI 2008, Bangalore dated 26.02.2008 and works are taken up under Prime Ministers Package. The works are taken up in 33 packages.

The estimate cost of Modernisation of Bhadra canal system has been revised to Rs.1200.00 and the proposal has been submitted to the CWC, New Delhi for clearance.

Grant allocated for the year 2013-14 is Rs.30.00 Crores. The expenditure incurred during the year 2013-14 is Rs.50.75 Crores. The upto date expenditure incurred is Rs.1043.15 Crores.Works are nearing completion.

12.3.15 GONDI MODERNISATION:

Gondhi Anicut is built across river Bhadra, near Gondhi of Shivamogga Dist. The Anicut is located at 14.50 Km downstream of Bhadra Reservoir. The anicut was constructed during 1926 with storage capacity of 0.37 TMC to irrigate an area of 4600 Ha.

As the canal constructed was unlined, at many reaches canal has lost its shape and seepage was observed in the structures. Hence, it was planned to Modernise the whole canal system by providing CC lining to canals and by renovating and reconstructing the structures.

The Government of Karnataka has administratively approved the revised estimate costing Rs.92.82 Crores vide GO No. Ja. Sam. E/24/MBB/2012, Bangalore, dated: 29.01.2014.

The DPR of this project is submitted to CWC for obtaining clearance. This project is proposed to be taken up under externally aided fund by Asian Development Bank along with introduction of Integrated Water Resources Management (IWRM) programme under the selected projects of Upper Tungabhadra basin.

12.3.16 RAJANAHALLY LIS:

This Project envisages lifting water near Thimmapur of Harihar Tq. from to augment water for 22 tanks of Davangere district and providing water to Hagribommanahalli tank. 1.00 TMC of water has been allocated to this Project. Administrative approval has been accorded for Rs. 100.00 crores vide Government order No. MI/33/LIS/2006/05.01.2007. This work is entrusted on Turnkey basis and the work is in progress.  The estimated cost of the project : Rs. 112.70 Crores (As per tender)

135

 Total expenditure incurred : Rs. 100.44 crores upto Nov-2013 as per CAO figures. Status of project: This Project is proposed to be completed by Dec-2013.

12.3.17 DAVANAGERE 22 TANKS (RAJANAHALLI LIFT IRRIGATION SCHEME) :

Government accorded approval to take up a lift irrigation scheme to feed 22 tanks of Davangere, Jagalur and Harapanahalli taluks for Rs 100 Crores. Vide Govt. order No: WRD 33 LIS 06 Dated; 05.01.07.

The detailed estimate of the scheme is prepared amounting to Rs 11270 Crores and technically sanctioned. The work has been taken-up on turn key basis tender amounting to Rs 9500.00 Lakhs.

Land Acquisition for Jack well No-1 is in award stage. Acquisition for Jack well No-2 is in 6(i) notification stage. The work is under progress.

The progress achieved to the end of March 2013-14 is as follows.

M.S. Pipe for rising main of 47.625 km is laid. For distribution system PSC pipe of 23.915 km is supplied and 18.493 km is laid. HDPE pipe of 34.630 km is supplied and 34.630 km is laid and the work is under progress. Power supply to Jack well No-1and Jack well No-2 is completed.

During 2013-14 the Karnataka Neeravari Nigam has allotted a grant of Rs 1000.00 Lakhs. Work is under progress. Expenditure incurred during 2013-14 is Rs 856.17Lakhs. An update expenditure of Rs 9701.13 Lakhs has been incurred to end of March 2014.

12.3.18 HARIHARA-BYRANAPADA LIFT IRRIGATION SCHEME:

Harihara –Byranapada Lift Irrigation scheme is proposed to provide irrigation facilities to the suffering Atchakat at tale end of Malebennur branch canal. It is proposed to establish the lift irrigation scheme on the right bank of Tunga Bhadra River.

The DPR of this scheme for Rs. 43.73 Crores is administratively approved by the Government vide G.o.No.WRD 14.MMB 2012 dated 10-01- 2013. The scheme is transferred to Karnataka Neeravari Nigam. The Compliance to the TSC observations along with modified DPR is awaited from the Division. During 2013-14 government has allotted an grant of Rs 100.00 Lakhs. No Expenditure is incurred during the year 2013-14.

Vani vilasa Sagar Project : 136

Vanivilasa Sagar Dam has been constructed across near Marikanive of Hiriyur Taluk. The construction of dam was started during 1898 and completed during 1907. The cost of the project was Rs. 45.00 Lakhs. The project has a reservoir with a high level Canal, under this pickup as been constructed at about 8.00 Km near Katrikena halla. Irrigation facility is provided through left bank and right bank canals. An Atchakat of 12,135 Ha has been developed under this project. The repairs and improvements works of canals structures and providing lining at the damaged portions have completed under National Water Management Programme. Fixing of measuring devises and other works are also done under this Project. Now this project is under maintenance. During 2012-13 a grant of Rs 100.00 Lakhs is allotted for Modernization of Vani Vilas Sagar Project canal system and Improvements to Travelers Bungalow at V.V.Puram. .Accordingly the works taken up during last year and fresh works are under progress. Expenditure incurred during 2012-13 is Rs 50.38 Lakhs. For modernization canal system of this project an update expenditure of Rs 634.00 Lakhs has been incurred to end of March 2012. During 2012-13 a grant allotted under Head of Account 2700-M&MI is Rs 68.91 Lakhs. Expenditure incurred during 2012-13 is Rs 65.16 Lakhs. Development of Micro Irrigation facilities to 1000 Ha of Atchakat under Vani Vilas Sagar Project. During 2012-13 a grant of Rs 100.00 Lakhs is allotted for Development of Micro Irrigation facilities to 1000 ha of Atchakat under Vani Vilas Sagar Project.

12.3.19 MODERNIZATION OF AMBLIGOLA CANAL SYSTEM AND MODERNIZATION OF ANJANAPURA CANAL SYSTEM:

The grant allotted for Modernization of CANAL SYSTEM 0F AMBLIGOLA AND ANJANAPURA PROJECTS During the year 2013-14 under Karnataka Neeravari Nigam Limited is Rs 500.00 Lakhs. The annual programe of works proposed during 2013-14 is Rs 2386.05 Lakhs.

The details works proposed are as below.

1.Modernisatio of canal system of Anjapura Project-Rs.869.07 Lakhs 2.Improvements to tanks under atchkat of Anjapura Project-Rs.515.12 Lakhs 3.Modernisatio of canal system of Ambligola Project-Rs.631.17 Lakhs 4.Improvements to tanks under atchkat of Ambligola Project-Rs.322.38 Lakhs

Expenditure incurred during 2013-14 is Rs 490.86 Lakhs. An update expenditure of Rs 1690.19 Lakhs has been incurred to end of March 2014.

The brief project reports are as below.

AMBLIGOLA RESERVOIR PROJECT: 137

Ambligola Reservoir project has been constructed at Ambligola across Kumudwathi river during 1954-65 at the Junction of Salur Halla joining Kumudwathi river with a project cost of Rs 103.00 lakhs. The irrigation potential created under this project was 7000 Acres for Khariff season only. Further left Bank canal of this project has been extended in order to create an additional potential of 7908-13 Acres for khariff season. Cropping pattern adopted under this project: Paddy, Garden and Semi dry crops.

Government has accorded administrative approval on 26.06.1998 for Rs.178.00 Lakhs for rising of Ambligola reservoir embankment and waste weir to 1M. Height. According to the reservoir height and waste weir height has been raised to 1 M. height and created 5700 ha. for rabi semi dry crops. At present considering 50% dependability 2538 Mcft of water is being utilising for Irrigation. This work has been technically sanctioned and work is completed. This project is in maintenance stage. The allocation of water for this project is 0.905 TMC and Utilization is 1.10 TMC.

MODERNIZATION OF AMBLIGOLA CANAL SYSTEM:

Before nigam the update expenditure incurred on modernization from 2005-06 to March 2011 is Rs 2049.15 Lakhs.

Improvements of 13 Tanks under the Atchakat of Ambligola Project:

Before nigam the update expenditure incurred on development of tanks from 2006-07 to March 2011 is Rs 128.81 Lakhs. No grant has been allotted during 2013-14 from nigam under Head of Account 2701.

ANJANAPURA RESERVOIR PROJECT:

Anjanapura Reservoir project is constructed across Kumudwathi river in Anjanapura village of Shikaripura Taluk, Shimoga District during 1927-30 at the cost of Rs 22.51 Lakhs. The area irrigated under this project is 4050 Ha. Further during 1980 an additional atchkat of 2686 Ha has been created at the Est. cost of Rs 27.68 lakhs. The total irrigation potential created under this project is 6736 Ha.

The allocation of water for this project is 3.32 TMC..Revised allocation and present utilization is 2.52 TMC.

Estimate for strengthening the bund of Anjanapura reservoir amounting to Rs 835.00 lakhs has been sanctioned by the Chief Engineer, M.I Zone (South) Bangalore vide ltr. No. C.M.I.(S) :IGN(G):SHM:SHK:AJN; strengthening bund: 98-99:2511:dated 29.12.1988 under Head of Account 4701 M&MI.

138

IMPROVEMENTS TO CANAL SYSTEM:

The errection of God Bole gates on spill way of Anjanapura Project through NABARD grant has been taken up and completed. The expenditure incurred on this is Rs.218.00 Lakhs

MODERNIZATION OF ANJANAPURA CANAL SYSTEM:

Before nigam the update expenditure incurred on modernization from 2005-06 to March 2011 is Rs 2461.02 Lakhs.

IMPROVEMENTS OF 20 TANKS UNDER THE ATCHAKAT OF ANJANAPURA PROJECT:

Before nigam the update expenditure incurred on development of tanks from 2005- 06 to March 2011 is Rs 635.34 Lakhs. No Grant has been allotted during 2013-14 from nigam under Head of Account 2701.

12.3.20 DHARMA PROJECT:

Dharma reservoir is constructed across Dharma River in Uttarakannada District, Mundagod taluk, near Yamanalli village, during 1964 at the cost of 65.00 lakhs. The storage capacity of the tank is 0.814 TMC. For this project, the upstream canal length is 1.80 KM. On downstream of this project at 8.00 KM, Shrungeri pickup is constructed. Now this project is under maintenance. The allocation of water for this project is 1.10 TMC and Utilization is 0.80 TMC.

During 2013-14 a grant of Rs 100.00 is allotted for Modernization of Dharma Project canal system. The amount required for completion of balance canal lining of 14.70 k.M. and improvements old structures is Rs. 4600.00 Lakhs. The balance works are proposed to take up under AIBP. The estimate of Rs.38.00 lakhs is approved for conducting survey and preparation of project report.

The spill- over works and fresh works have been taken up during 2013-14. No expenditure incurred during 2013-14. update expenditure for modernization canal system is Rs 1481.32 Lakhs to end of March 2014 under budget grant.

The expenditure incurred on this project for preliminary survey and investigation till the end of March 2014 is Rs 154.37 Lakhs.

139

12.3.21 RANIKERE FEEDER CANAL:

The Government has accorded administrative approval for this Ranikere Feeder Canal project Vide G.O.No.WRD. PWD 31 BGC 77/11.11.1997 for Rs. 249.00 Lakhs. The revised estimated cost of this project is Rs.896.00 Lakhs.

This project is proposed to take up in two stages. In I stage it is proposed to regularise the water supply for crops already created to an extent of 390 Ha. In II stage it is being proposed to create on additional irrigation potential of 3827 Ha. The II stage work has to be taken up after finalization of yield of water. The expenditure incurred for this project to end of 3/2006 is Rs.939.03 Lakhs. This project is in maintenance stage.

During 2013-14 karnataka Neeravari Nigam has allotted the grant of Rs 100.00 Lakhs under Head of account 4701. Estimate amounting to Rs 1300.00 Lakhs has been submitted to Government and placed before 100th TAC meeting for clearance. The compliance to the TSC along with recasted estimate of Rs.17.82 crores submitted and Technical sanction obtained on 27.01.2014.by the competent authority. The tender is invited and tender process is in progress. Expenditure incurred during 2013-14 for survey works is Rs 3.66 Lakhs.

12.3.22 MADAGA –MASUR TANK:

Madaga Masur Tank is located in Haveri District in Hirekerur Taluk. The above tank constructed across Kumudvathi river. This tank very older 2855 Ha. of Land Irrigated under this tank. This tank has LBC of 14.00 KM length and RBC of 37.00 KM of Length. This tank is in maintenance stage, and improvements and repairs to embankment, canal works, and removal of silt have to be taken up. under 4701 for improvements of this tank. Accordingly the programme is got approved and works are taken up. The expenditure incurred upto December 2006 is Rs.7.89.Lakhs. During 2012-13 a grant of Rs 100.00 Lakhs is allotted for Modernisation Madaga Masur Tank canal system. Accordingly the spillover works and fresh works has been taken up during the year 2012-13. Expenditure incurred during 2012-13 is Rs 100.00 Lakhs. For modernization canal system of this project an update expenditure of Rs 813.75 Lakhs has been incurred to end of March 2013. During 2012-13 No grant is allotted under Head of Account 2701-M&MI. It is instructed by the District in charge Minister to take up the balance Modernization works under AIBP Assistance. The detailed report along with compliance to the TAC observation has been submitted to higher authorities for according approval. Hence the balance Modernization works has to be taken up for execution after getting clearance fro TAC as well as AIBP authorities under AIBP Assistance.

12.3.23 GAYATHRI RESERVOIR PROJECT:

140

Gayathri Reservoir Project has been constructed between 1952-53. The maintenance of this project has been handed over by the Minor Irrigation during 1997 to this circle. This reservoir has been constructed across Suvarnamukhi river near Kudalahalli village, Hiriyur taluk. Chitradurga District. The original estimate cost of the project was Rs.39.85 Lakhs. The Irrigation potential created under this project was 2305 Ha. of land. This project is under maintenance. During 2012-13 a grant of Rs 100.00 Lakhs is allotted for Modernisation of Gayathri Project canal system. The spill over works and fresh works has been taken up during 2012-13. Expenditure incurred during 2012-13 is Rs 62.77 Lakhs. For modernization canal system of this project an up date expenditure of Rs 401.03 Lakhs has been incurred to end of March 2013. The Grant allotted during 2012-13 under Head of Account 2701 is Rs. 23.42 Lakhs. The expenditure incurred during 2012-13 is Rs 23.42 Lakhs.

12.3.24 D.B.KERE PICK-UP PROJECT:

D.B.Kere Project is in Harihar Taluk, Davanagere district. D.B.Kere Project was completed in 1985. The Area irrigated under D.B.kere project is 4280 Hectares. Under the above project Right bank canal runs for a length of 26.20 Kms and Left Bank canals runs for a length of 33.00 Kms. At present the seepage water of Bhadra Canals supplements the Atchakat. The grant released under Head of Account 4701 during 2012-13 is Rs. 100.00 Lakhs for Errection of God-bole gates on the spill-way of the pick- up. The work has been taken up on Tender. works are under progress.

Expenditure incurred during 2012-13 is Rs 200.00Lakhs. An update expenditure of Rs 199.98 Lakhs has been incurred to end of March 2013.

12.3.25 JAMBADAHALLA RESERVOIR PROJECT:

This is an medium irrigation project, situated across Jambadahalla reservoir near Duglapura village, Tarikere Taluk of Chickamagalur district. The project was contemplated to provide irrigation to about 6000 acres. But due to scanty of flow in stream only 2799 acres of land is only irrigated to supplement the irrigation demand under this project. It is proposed to divert water from Hodirayanahalla reservoir (A adjacent valley to Jambadahalla stream) costing 248.00 Lakhs. The above said Scheme has been got administrative approval by the Government dated: 10.08.1987 for Rs.248.00 Lakhs. About 12.98 Ha. land comes under the jurisdiction of forestland & Clearance has been obtained. During 2012-13 no Grant has been allotted from nigam under Head of Account 2701. The grant allotted during 2012-13 in budget is Rs.9.90 Lakhs under 2701 and expenditure incurred during the year 2012-13 is Rs. 9.40 Lakhs.

141

12.3.26 HODIRAYANAHALLA DIVERSION SCHEME:

Jambadahalla Reservoir is located near Duglapura village, Tarikere Taluk of Chickmagalur district. This project was contemplated to provide irrigation to 2428 Ha. But due to less flow only 1133 Ha. Land under right bank is being irrigated. Remaining 1295 Ha a tank has been planned to irrigate by diverting supplement water from Hodirayanahalla an adjacent valley to Jambadahalla. In addition to this 243 Ha. Land will also be benefited by this scheme. The above said Hodirayanahalla diversion Scheme has been got administrative approval by the Government dated: 10.08.1987 for Rs.248.00 Lakhs. About 12.98 Ha land comes under the jurisdiction of forestland & Clearance has been obtained by Central Forest & Environment Ministry.

Survey and investigation of Hodirayanahalla diversion scheme has been conducted on tender basis through private consultancy services as per the administrative approval obtained from the government amounting to Rs 35.00 Lakhs. After detailed survey and investigation of Hodirayanahalla diversion scheme project estimate amounting Rs3400.00 Lakhs has been placed before 94th T.A.C meeting held on 14.12.2009 for approval duly complying the observations of 90th T.AC meeting. Further T.A.C has cleared the project with certain observation to comply.

Further the project proposal amounting to Rs 2537.00 is submitted to Government duly complying the observations given in 94th T.A.C meeting. The government has accorded Administrative approval vide Govt order No WRD 47 MMB 2010 Dated 04.03.2011 with direction to take up the works through Karnataka Neeravari Nigam.

The estimate is recasted as per CSR amounting to Rs 34.00 Crores and submitted to TSC for approval. TSC has raised certain observation on the project proposal. Action taken to comply the observations of TSC. The government has accorded Administrative approval vide Govt order No WRD 47 MMB 2010 Dated 04.03.2011 with direction to take up the works through Karnataka Neeravari Nigam and technically sanctioned for Rs 33.83 Crores by the Chief Engineer,KNNL,UTP Zone Shimoga vide C.E.R.No.694/12-13 dated 19-01-2013.

The draft tender Schedule has been placed before 114th T.S.C for approval submitted to TSC for approval. TSC has raised certain observations. The action is being taken to submit the compliance to the observations of TSC.

During 2013-14 Rs. 200.00 Lakhs grant is allocated under the Head of account 4701. The expenditure incurred during 2013-14 is Rs.4.54 Lakhs on conducting Survey. The upto date expenditure incurred on this project for preliminary

142

survey and investigation including payment made to Forest Department for release of forest land till the end of March 2014 is Rs 154.37 Lakhs.

12.3.27 BHEEMASAMUDRA TANK:

Bheemasamudra tank has been constructed 500 years ago in Chitradurga Taluk and district near Bheemasamudra village. The storage capacity of the tank is 0.905 TMC. The Irrigation potential created under this tank is 1235 Ha. (3050 Acres). The tank has left Bank canal and right Bank canal and distributary system. The total length of canal is 68 Kms.

At present the Bheemasamudra tank is filled up with silt since the tank is 500 year old. Due to this storage capacity of tank is reduced to 0.18 TMC. The catchment area of tank has scanty rainfall, due to this storage capacity of the tank is reduced.

In order to increase the storage capacity of this tank it is proposed to construct feeder canal from Bettadanagenahalli and Jogerahalla duly constructing pickup. This works has been entrusted on tender basis. No Grant is released for this tank under 2701 H/A during 2012-13.

The Restoration and renovation of this tank is taken up under AIBP grant of central government. The improvement of this tank under Prime Minister Farmers Sucide Package for Rs 400.00 Lakhs was got administratively approved by the Govt on 19.06.2007. The restoration and renovation of this tank is taken up on tender. So for about 1.80Km of lining works is completed in canal No1, 4 Nos of cross drainage work is completed and 147 m chute channel is completed. Rs.100.00 Lakhs grant is allotted during 2012-13 under 4701 for restoration and renovation of Bheemasamudra tank. The expenditure incurred during the year 2012-13 is Rs 45.46 Lakhs. An update expenditure of Rs 231.49Lakhs has been incurred to end of March 2013.

CONSTRUCTION OF FEEDER CANAL FROM ANNEHALLU TANK TO BHEEMASAMUDRA TANK: No grant is allotted during 2012-13 under 4701 for this work. The works of construction of feeder canal from Annehal tank to Bheemasamudra tank has been taken up on tender basis. Due to the delay in process of land acquisition, works are yet to be resumed. No expenditure has been incurred on this project during the year 2012-13. Upto date expenditure of Rs 67.88 Lakhs has been incurred on this project toward land acquisition to the end of 03/2013.

143

12.3.28 CONSTRUCTION OF LINK CANAL FROM HEBBEHALLA TO MADAGADAKERE :

The farmers, MLAs and areca Co-operative societies of Kadur, Birur and Tarikere Taluk have represented the Government to divert water from Hebbehalla which is sub- tributary to Somavahine a tributary to Bhadra river to Madadaga Kere in order stabilize the Atchakat as the rainfall has become scanty in recent years resulting in reduction of storage of water. The Government has ordered to investigate the project. The preliminary project report (PIR) for Rs.69.73 Lakhs was prepared by the superintending engineer, Major Irrigation Investigation Circle Mysore. Further superintending engineer, Major Irrigation Investigation Circle Mysore. has prepared revised estimate of the project amounting to Rs 140.00 Crores through private survey consultancies, and obtained formal approval by the government vide Lr No WRD 61 MMB 2010 Dt 29.11.2010. The project has been transferred to major irrigation department from investigation circle, Mysore. The designed total water requirement for this project is 1.538 TMC. The utilization of 0.50 TMC is available. The water resources development organization, Bangalore in their letter Dt 12.05.2010 has stated that the advisory committee of Krishna water dispute Tribunal has submitted the proposal to the tribunal to allocate 1.50TMC of water to this project out of 23 TMC of water to be reallocated to the state under Indira Pollavaram project of Andra Pradesh.

The project details have been obtained from the office of the Executive Engineer, Major Investigation Division, Mysore. and to take necessary action to implement the project. During 2012-13 government has allotted an grant of Rs 100.00 Lakhs.

The project proposal obtained from Major Investigation Division is a line estimate. Hence preparation of detailed project report has been entrusted to private survey consultancy through on tender basis. Preparation of detailed project report is under progress. No expenditure is incurred during 2012- 13.

12.3.29 SUPPLIMENTING WATER TO 60 TANKS OF HARAPANAHALLI FROM GHARBHAGUDI BARRAGE OF TUNGABHADRA RIVER:

Construction of barrage near Garbhagudi across Tunga Bhadra River is proposed to augment the water and recharge the ground water table by filling M.I tanks in Harapanahalli taluk. The preparation of project report was entrusted to private survey consultancy and preparation project report. Revised estimate of this work amounting to Rs 447.50 Lakhs was placed before TAC held on 13.09.2011. The compliance to the observations raised on estimate by the TAC. along with recasted estimate of Rs.257.00 Crores has been submitted on 24.11- 144

2012. Expenditure incurred during previous Year (2011-12) towards survey work is Rs 35.87 Lakhs.

No grant is allotted during 2013-14. No Expenditure is incurred during the year 2013-14.

(Amount in Rs. Lakhs) Expendi Grant for ture Sl. Remark Head of Account the year incurre No s 2013-14 d in 2013-14 01 02 03 04 05 I-4701- Major & Medium Projects 01 4701- Modernisation of Canals system of 3000.00 5075.00 Bhadra Reservoir Project. 02 4701- Modernization of Canals system of 500.00 490.86 Anjanapura and Ambligola Reservoir Project 03 4701- Modernization of Canal system of Gondi 1000.00 30.28 Anicut 04 4701- Davanagere 22 Tanks ( Rajanahalli L.I.S) 1000.00 856.17 05 4701-Developmental works of Historical 300.00 320.30 Huchurayanakere in Shikaripura town. 06 4701-Hodirayanahalla Diversion scheme. 200.00 0.00 07 4701-Davangere village shifting. 100.00 0.00 Sub Total(I) 6100.00 6772.61 II- 4701-SCP 01 4701- Bhadra Project 2500.00 4256.37 02 4701- Davanagere 22 Tanks ( Rajanahalli L.I.S) 100.00 20.90 03 4701- Tunga Anicut Project 0.00 56.99 04 4701-Dharma Project 0.00 12.45 05 4701-Ambligola and Anjapura Project 100.00 84.41 06 4701-Hodirayanahalla Diversion Project 0.00 0.00 Sub Total(II) 2700.00 4431.12 III- 4701-TSP 01 4701- Bhadra Project 665.00 1403.02 02 4701- Davanagere 22 Tanks ( Rajanahalli L.I.S) 00.00 0.00 03 4701- Tunga Anicut Project 00.00 42.53 04 4701-Dharma Project 00.00 0.00 05 4701-Ambligola and Anjapura Project 00.00 0.00 06 4701-Hodirayanahalla Diversion Project 00.00 0.00 Sub Total(III) 665.00 1445.55 IV- 2701-M&MI 01 2701 –Bhadra Project 850.00 850.00 02 2701- Tunga Anicut Project 00.00 0.00 Sub Total(IV) 850.00 850.00

145

Expendi Grant for ture Sl. Remark Head of Account the year incurre No s 2013-14 d in 2013-14 01 02 03 04 05 V- 2702-M&MI 01 2702 –Bhadra Project 250.00 96.22 02 2702- Tunga Anicut Project 00.00 0.00 Sub Total(V) 250.00 96.22

VI NABARD- ROADS UNDER RIDF -XVII 1 Bhadra Project 1051.00 388.31 VII NABARD- ROADS UNDER RIDF -XVIII 1 Bhadra Project 915.00 12.38 Total ( I+II+III+IV+V+VI+VII) 12531.0 13899.9 0 7

12.4 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION PROJECTS ZONE, GULBARGA

12.4.1 BENNITHORA PROJECT:

Bennithora project is a major irrigation project, which comprises of construction of dam across River Bennithora near Heroor village, Chittapurtaluk, Gulbarga District. There are two canals covering an Irrigable area of 20,234 Ha in Gulbarga District. The utilisation for the project is 5.75 TMC.

Dam: Work is completed and water is being stored in reservoir since Dec- 2001.

146

 Right Bank Canal (82 km): Main canal works are completed. All distributaries are completed and 12422 Ha.FIC works are completed. Tenders for the strengthening of embankment in vulnerable reaches & concrete lining of main canal (selected reaches) has been invited for Rs.11.63 crores. Tender Agreement No.43 Dated:12-03-2013 Entrustment amount Rs.12.35 crores at 1.22% below, work is under progress. Total atchkat is 13435 Ha.

 Left Bank Canal (60 km): All works of main canal completed. All distibutories on LBC are completed. 6506.65 Ha FIC works completed. Tenders for the strengthening of embankment in vulnerable reaches & concrete lining (selected reaches) on main canal has been invited for Rs.7.95 crores. Tender Agreement No.44 Dated:12-03-2013. Entrustment Amount Rs.8.68 crores at 2.94% above, work is under progress. Total atchkat is 6799 Ha.

The revised estimate cost of this project assessed is Rs.443.00 Crores. Cumulative expenditure upto end of March-2014 is Rs.426.86 Crores. A dry potential of 20234 Ha has been created to end of 3/2014. The wet potential of 18828.70 Ha is created up to end of March 2014, and balance 1405.30 Ha will be created during 2014-15.

The details of target and achievement of the project for 2011-12 to 2013-14 are as follows:

Financial (Rs. in Sl Crores) . Year Targe No. Achievement t 1 2011-12 23.50 10.59 2 2012-13 13.50 13.03 3 2013-14 18.60 35.23

147

12.4.2 BHIMA LIFT IRRIGATION SCHEME:

Bhima Lift Irrigation envisages construction of earthen dam with central concrete spillway with crest gates to discharge 9.00 lakh cusecs of water. The dam site is proposed near Sonna (K) village of Afzalpur Taluk in Gulbarga District and providing two lift irrigation points to draw water from the Reservoir, for creation of 24,292 hectares of irrigation Potential, by utilising 6 TMC of Water.

The Project is administratively approved for Rs. 94.17 Crores by the Government vide Govt. Order No. ID 39 MMM 92, dated 18-4-1992, and technically sanctioned for Rs.107.70 Crores by the Chief Engineer, WRD, I.P.Zone, Gulbarga vide CER No. 5/93-94 dated13-01-1994. The Revised Estimate costing Rs.588.37 Crores is approved by Government of Karnataka. This project is under Karnataka Neeravari Nigam Ltd., since 1999.

 Barrage Length- 2.250 km Height - 18.40 m Gross Storage – 3.166 TMC Live Storage - 2.41 TMC Allocation &Utilisation – 6.00 TMC

 Lifting Systems Two foreshore lifts at Balundgi&Allagi(B) Length of the Balundgi lift canal – 63.762 km. Length of the Allagi lift canal – 35.787 km

STAGE OF THE PROJECT AS ON MARCH-2014:

 Dam & allied works: Construction of earthen embankments on left and right flanks are completed and construction of barrage is also 148

completed. Ballundagi Lift head works completed. Bankalaga Bridge is completed. Water impounding has been started. Mini-Hydel Scheme work is also completed, generation of electrical energy is also started duirng Aug-2010. The barrage and Balundagi Lift was inaugurated and dedicated to the nation on 19-02-2013.

 Gate works: Gate works are completed during Aug-2010, and water is being stored partially as the rehabilitation centre works are to be completed.

 Balundagi Lift: Construction of intake channel, jackwell, pump house, raising main with PSC pipes and delivery chamber are completed.

 Balundgi Canal: Construction of Balundagi main canal from 0 to 63.76 is completed except few structures and small reach of lining. Water is allowed in the canal upto tailend on trail basis. Distributary works and FIC works are in progress.

 Allagi Lift: Construction of intake channel (except lining), jackwell, pump house, raising main with PSC pipes and delivery chamber are completed. Lift is commissioned on 25-02-2014.

 Allagi Canal :Construction of Allagi main canal work from Km. 0 to 5 & 5 to 10 Km. is almost completed, and from 10 to 20 Km & 20 to 35.787 Km packages are nearing completion.

 Rehabilitation and Resettlement:

Villages affected due to submergence – 10 Nos. No of centres to be formed – 9 No Population affected – 8801 Families affected – 1658

Government vide GO dated 18.5.05 have constituted District Level Rehabilitation Advisory Committee. R&R Package is approved by the govt. The site has been identified for construct rehabilitation centre and even land acquisition has been proposed and 4(1) notification has been issued. Construction of Balundgi rehabilitation is completed and handed over to Gram Panchayat. Bankalaga centre is also completed and inaugurated on 19-02-2013 and formal Hakku Patra are also issued to the rehabilitanats. Tarapur, Duddangi, Mangalore, Hiriyala & Badgihal RC works are nearing completion.

The Rehabilitation Centers for Allagi B works under 4 packages are approved and agreement is concluded, and works are at to be started. The tender for formation of Tawarkhed R.C. is called and yet to be implemented.

During the year 2013-14, budget allocation made is Rs.192.00 crores and expenditure incurred upto March 2014 is Rs.67.17 crores.

149

The details of target and achievement of the project for 2011-12 to 2013-14 are as follows: -

Financial (Rs. in Physical (In Sl. Crores) hectares) Year No. Achievemen Targe Achieveme Target t t nt 1. 2011-12 225.90 56.06 500 4303 8000 1120.27 2. 2012-13 111.00 79.67 Dry Dry 18288 5686 Dry Dry 3. 2013-14 192.00 67.17 10000 4038 Wet Wet

12.4.3 GANDORINALA PROJECT:

Gandorinala project is a medium irrigation project in Gulbarga District. This project envisages construction of dam near Belkota village in Gulbarga taluk, across River Gandorinala, a tributary to River Bennithora, which in turn joins River Bhima of Krishna Basin. The utilisation under this project is 1.97 TMC. The area covered for irrigation under this project is 8094 Hectares.

The project is administratively approved vide Government Order No. ID 110 MTZ 85, Bangalore dated 23.05.1992 for Rs. 66.00 crores. The revised estimate of the project is Rs.240.00 Crores and expenditure upto March 2014 is Rs. 299.38 Crores. Revised estimate is at to be prepared. The dry irrigation potential of 7943 Ha has been created upto March 2014.

 Dam & allied works: The works were carried out by KSCC and the same are already completed. The work of providing & erection of radial crest gates is completed.

 Canal works:

150

 RBC: Total length of LBC is 7 km and works are completed Potential of 566Ha is created.

 LBC: Total length of LBC is 89.32 km and works are completed.

 Distributories: Under RBC 3 distributories works are completed. Under LBC 40 distributories works are completed.

 FIC: FIC works of 566 Ha under RBC and FIC works of 7290.83 Ha under LBC are completed. The balance potential of 86.17Ha will be created during 2014-15.

12.4.4 LOWER MULLAMARI PROJECT:

Lower Mullamari Project envisages construction of a dam across the River Mullamari a tributary to River Bhima in Krishna basin. The project is located near village in ChincholiTaluk of Gulbarga District. The utilisation under this project is 2.61 TMC and it is planned to provide irrigation facilities to 9713 Ha. of land in Chincholitaluk.

The project has been originally estimated for Rs. 45.00 crores at 1990- 91 schedule of rates. The latest estimated cost of the project is Rs. 220.00 Crores and expenditure to end of March 2014 is Rs. 224.90 crores.

A) Earthen Dam: Completed including erection of spillway gates. Water is being stored in reservoir since August 2001.

B) Right Bank Canal (80 km): Works are completed.

C) Distributaries (66 Nos.): 65 are completed and water is let-out in distributaries.

Total Atchkat : 9713 Ha. Wet potential created : 9560.72 Ha. Balance to be created : 152.28 Ha.

151

D) R&R : Out of 7 Nos. of rehabilitation centres, 6 nos. are completed. Balance works of Gadilingadahalli Rehabilitation Centre No.3 are nearing completion.

E) Strengthening works of RBC : Strengthening works in selected reaches from Km. 0 to 40 are completed. Works from Km.40 to 80 km in selected reaches are nearing completion. Further for ERM survey under progress.

Total irrigation potential of the project is 9713 Ha, Out of which 9400 Ha created upto end of March 2014. The balance potential of 313 Ha will be created during 2014-15.

The details of target and achievement during 2011-12 to 2013-14 is as under: Financial (Rs.in Sl. Crores) No Year Achievemen . Target t 1) 2011-12 12.50 7.36 2) 2012-13 10.50 11.57 3) 2013-14 12.50 11.16

12.4.5 AMARJA PROJECT:

Amarja irrigation project envisages construction of a dam across the River Amarja, a tributary to River Bhima in Krishna Basin, near Sangolgi village in Aland Taluk of Gulbarga District with canals on both banks to provide irrigation facilities to an extent of 8903 Ha. The allocation proposed under this project is 1.92 TMC, utilization is 1.906TMC.

A) DAM: 960 m long and 31.85 m high earthen dam with a storage capacity of 43.87 Mcum will submerge 641 ha of land, affecting 3 villages and a population of 4,500. Dam works are completed during 1999 and water is being stored since 2001.

152

B) CANALS: The Left Bank Canal is 54.78 Km long and the Right Bank Canal is 42.428 Km long which will irrigate 4,856 Ha. and 4,047 Ha. of land, respectively. Total number of distributaries under RBC are 29 Nos. and DPO’s 20 Nos. and under LBC are 33 Nos. & 19 Nos. are respectively. Worsks are completed. Bed difference observed and hence the subject rectification works of Amarja project was placed before the 25th Board meeting of KNNL held on 07.06.2005. After detailed Deliberation the Board authorized for closure of works for previous contracts on “As is where basis” so that rectification works can be taken up without further delay (vide ltr no 993 dtd:23.06.2005). Under this proceedings, the rectification works were proposed for Rs.100.00 crores. The work is transferred to KNNL during April 2005 vide GO No. WRD 29 TMZ 04 dated 18.04.2005.

Rectification of canal works was taken in five packages for LBC & RBC ,the work of 5 packages are under progress, the project is proposed to completed by 2014-15.

The details of the works are as follows.

A) Right Bank Canal Works:

1) Km. 0.00 to 7.00: Works of main canal and distributaries No. D-1, 4, 5 are completed, D-2, 3, 6, are under progress. The work is proposed for recending.

2) km. 7.00 to 20.00 : Works of main canal and distributaries are completed. FIC works are under progress.

3) km. 20.00 to 42.48: Works of main canal and distributaries No. D-9, 10, 11, 12, 16, 17, 19, 20, 21, 22, 24, 25, 26, 27, 28, 29, are completed,D- 13, 14, 15, 18, are under progress. The work is proposed for recending.

B) Left Bank Canal works: 1) km. 0.00 to 30.00: Works of main canal and distributaries are completed. FIC and DPO works are under progress. Dry irrigation potential of 2020 Ha is created in this reach and wet potential of 1504.51 Ha is created.

2) km. 30.00 to 54.784: Earthwork excavation from 30.00 to 52.00 is completed and lining from km30.00 to km.37.00 is completed. The balance works of main canal, distributaries and FICs from Km 30.00 to 54.784 of LBC are under progress.

The details of target and achievements of the project for 2011-12 to 2013-14 are as follows:

Sl. Year Financial (Rs. in Crores) Physical (in hectares)

153

No. Target Achievement Target Achievement 2011- Dry-1000 0 1) 30.00 13.10 12 Wet-4467 2231 2012- Dry-1136 292.26 2) 23.50 19.65 13 Wet-2736 978.50 2013- Dry- 3) 33.50 7.34 441.96 14 2543.74 Wet-1844 162.65

The balance dry potential 2100.94 Ha will be created during 2014-15.

12.4.6 CHANDRAMPALLI PROJECT:

Chandrampalli Project is located on Sarnala (Krishna Basin) near Chandrampalli village in Chincholi taluka in Gulbarga Dist. The project was administratively approved vide G.O.NO. PQDMMI/159/Bangalore dated 16-12-1963 for Rs. 99.84 Lakhs. The project is commissioned during 1975.

A) DAM:- The project has 926.54 mtrs, length of earthen embankment. The spillway of the project is located on left flank saddle and comprises of broad crested weir of 64 m length, with 6 Nos. of gates size 9.15 m x 5.50. The spillway is designed for maximum discharge of 864.80 cumecs (30700 cusecs). Water is being stored in the reservoir since 1973.

B) CANAL:-R.B.C. The total length of Right Bank canal is 14.00 Km, and is completed. The discharge capacity at head is 1.28cumecs (45 cusecs). The contemplated atchkat is 1741 ha, the canal section is damaged at many reaches. Therefore modernization / renovation under AIBP/ERM of main canal and Distributaries are taken-up and the works are in progress.

L.B.C.:- The total length of Left Bank Canal is 21.00 km, and is completed. The discharge capacity at head is 2.74Cumecs (97 cusecs). Contemplated atchkat under LBC is 3482 ha. the canal section is damaged at many reaches. Therefore modernization / renova- tion of main canal and Distributaries are taken-up and the works are in progress.

The above modernization works have been taken-up under ERM –AIBP assistance at an estimated cost of Rs.1493 lakhs with 25% Central Share and 75% State share. The works are taken-up in seven packages and the agreement is concluded during 2011-12. The suffering achkat of 972 Ha, at the tail end will be brought under irrigation. The financial progress achieved is Rs.654.64lakhs.

12.4.7 HATTIKUNI TANK PROJECT:

154

Hattikuni Tank Project is located on Hattikuni stream near Hattikuni village about 12 Kms, from Yadgir Town. The project was administratively approved by G.O.NO. PWD 12 MIP 57 dated 20/26-12-1957 for Rs. 22,08,300/-. The revised cost of completion is Rs. 91.00 Lakhs and approved by G.O.NO. PWD 54 MTP 83, Bangalore dated 24 Sept. 1983.

A) DAM:-

The project has 923.50 mtrs, length of earthen embankment and the length of the spillway is 76.20 mtrs, with 9 N0s. of gates size 7.62m x 1.82 mtrs. The spillway is designed for maximum flood discharge of 13306 cusecs. Water is being stored in the reservoir since 1973.

B) CANAL:-Only L.B.C.

The total length of Left Bank canal is 14.00 Km, and is completed. The discharge capacity at head is 1.41 cumecs (50 cusecs) to irrigate 2145 Ha. The canal section is damaged at many reaches. Therefore modernization / renovation under AIBP/ERM of main canal and Distributaries are taken-up and the works are in progress.

The above modernization works have been taken-up under ERM – AIBP assistance at an estimated cost of Rs.675 lakhs with 90% Central Share and 10% State Share. The works are under progress. The financial progress upto March 2014 is 245.51 Lakhs.

12.4.8 SOUDAGAR TANK PROJECT:

Soudagar Tank Project is located on Soudagar Nala near Shamnapur village Dist. Yadgir. The project was administratively approved by G.O.NO. DPAR 15 (32) 6 DPAR at 26/27-1-77 fOrRs/ 149.00 Lakhs.

A) DAM:- The project has 600 mtrs, length of earthen embankment and is completed in the year 1987. The length of the spillway is 60 mtrs, with flush escape, ungated Ogee weir. The spillway is designed for maximum discharge of 218.06 cusecs (7700 Cusecs), water is being stored in the reservoir since 1987.

B) CANAL:-Only R.B.C. :

The total length of Right Bank canal is 11.00 Km, and is completed. The discharge capacity at head is 0.73 cumecs (26 cusecs) to irrigate 1417 Ha. The canal section is damaged at many reaches. The modernization under AIBP/ ERM has been proposed.

Administrative approval has been accorded for the modernization proposal vide G.O.NO. WRD 95 MTZ 2007 Bangalore dtd.09-03-2010 for Rs. 397.00 Lakhs.

155

The modernization under AIBP/ ERM has been proposed and proposal was submitted to the Project Appraisal Organization CWC Delhi, for an amount of Rs. 397.00 Lakhs.

During 103rd meeting of Advisory Committee held on 11-03-2010, it has been instructed to hand over the project to Minor Irrigation Department. In this regard, letter has been addressed to the Govt. vide this office letter No:5997 dtd:24-03-2010 for handing over the project to the MI Authorities. Vide GO WRD 95 MTZ 2007 Bangalore dtd 26-7-2010 it was ordered to hand over the project to the MI Department. Handing over the project to the MI Department is under process.

12.4.9 KARANJA PROJECT:

Karanja Irrigation project is a major irrigation project located near Byalhalli village in Bhalki Taluk of Bidar District across River Karanja, a tributary of River Manjra which joins River Godavari. This project irrigates 29,227 ha. Of land in Bhalki, Bidar and Humnabad taluka of Bidar by utilizing 9.27 tmc of Water. The Project is getting central assianance under AIBP.

Dam: Dam is completed. Development of garden below dam is in progress.

Left Bank upto 31.00 Km and distributaries completed.  RBC: upto 131.00 Km. is completed. Distributary at 107 Km is in progress.  Right Bank of shoreshore lift irrigation: In take canal, pumphouse, jackwell, delivery chambers completed. Re-modelling of raising main is in progress.  Canal net work under LIS is 24.00 Km. Work upto 21.00 is completed. Balance works in Km 22, 23,24 and FIC are in progress.

Canal net work under Atiwal Lift Irrigation Scheme. Construction of Jackwells & raising main and North canal of ALI works are in Progress and South cjanal of ALI works are not started due to land problom, D1(A) of KLI works are in progress. Yearwise details are as below:

Sl. Financial in Crores Year No. Target Progress 1 2011-12 30.88 24.28 2 2012-13 24.35 22.03 3. 2013-14 17.02 12.94

156

Revised cost of the project is 635.18 crores. Cummulative expenditure and potential created up to 3/2014 are Rs. 573.83 crores and 22,793ha. Respectively.

Total Cost of the Project: a) Original Cost Rs. 9.90 Crores. b) Revised Cost Rs. 532.00 Crores. c) Latest Estimated cost Rs. 635.18 Crores.

Achtkat details : a)Contemplated Achtkat 29227 Ha b)Covering districts 1. Bidar. c)Covering Talukas. 1. Bhalki, 2. Bidar, and 3. Humnabad.

No. of villages benefited and 76 Nos. of villages, Extent of Area-29227 extent of area. Ha. Land acquisition Details: Required area in Acquired area in Ha Ha a)Land acquired for dam and 6172.77 5780.62 allied works. b) Canal and others works. 2240.71 2056.50 c) R & R works 153.121 153.12 Potential details: Dry Wet a) Total potential to be created 29227 Ha 29227 Ha b) Potential created to the end 22793 Ha 22113 Ha of March-2014 c) Balance 2013-14 6434 Ha 7114 Ha Target Year Financial Details : a) Latest Cost of the project Rs. 635.18 crores b) Expenditure incurred upto March-2014 Rs. 573.83 crores c) Balance Cost Rs. 61.35 crores d) Grant allotted for 2013-14 under 4700 AIBP : Rs. 00.00 lakhs Non-AIBP: Rs.1701.89 lakhs Total: Rs.1701.89 lakhs e) Grant allotted for 2013-14 under 2700 Rs. 248.00 lakhs f) Expenditure during the year 2013-14 under 4700 Rs. 00.00 lakhs AIBP : Rs. 1293.00 lakhs Non-AIBP: Rs. 1293.00 lakhs Total: g) Expenditure during the year 2013-14 under Rs. 168.56 lakhs 2700

Physical and Financial Target Physical Financial and achievement for 2013- (in Ha) (Rs. in crores) 14. 157

Target 6434 17.02 Achievement Nil 12.94 FIC Details a) Contemplated FIC atchkat 29227 Ha b) Completed FIC 22113 Ha c) Balance FIC 7114 Ha

12.4.10 UPPER MULLAMARI PROJECT:

The Upper Mullamari Project envisages construction of an earthen dam with ungated spillway at the right bank across Mullamari River which is a tributary of Kagina River which joins river Bheema. This project was administratively approved by G.O. NO. PWD 160 GIP 77 dated 17-8-79 for Rs. 328.00 Lakhs @ SR 75-76 and Technically sanctioned by CE, TBP, Munirabad vide CER N0. 3/79-80 dated 26-8-1980. The revised cost of project is approved for Rs. 19.92 Crores in the year 1992-93 and the latest revised cost of project is Rs. 22.58 Crores.

DAM:- The Dam has 810.00 length of Earthen Embankment with zonal section maximum height of dam 23.00m to store the gross storage of 21.22 M.cum (0.749 TMC) and live storage of 18.88 M.cum (0.666 TMC)

R.B.C.:- The total length of Right Bank Canal is 43.00 Km, and is completed. The discharge capacity and head is 1.61M.cum (57.20 Cusecs). The canal section is damaged at many reaches. Therefore modernization/renovation of main canal and distributaries under AIBP/ERM has been proposed and same has been submitted to CWC, Delhi, for Central Assistance vide this office ltr.No.KNNL/CEG/ERM/TA- 1/AE-6/ CDO/2009-10 dated 12-01-2010 amounting to Rs.821.00 Lakhs. Irrigable command area is 2024 ha.

L.B.C. :- The total length of left bank canal is 28.00 Km and is completed. The discharge capacity and head is 0.99 M.cum (35.20 cusecs). Irrigable command area is 1255 ha.Modernization under ERM is taken up and works are is below progress as the grants from centre is not received.

Total Cost of the Project: a)Original Cost Rs. 3.28 Crores. b)Revised Cost Rs. 19.92 Crores c) Latest Estimated cost Rs. 22.58 Crores. ERM cost: Rs.821.00 Lakhs Achtkat details : a)Contemplated Achtkat 3279 Ha. b)Covering districts Gulbarga &Bidar c) Covering Talukas. Basavakalyan , Humnabad, Gulbarga Tq. No. of villages benefited and extent of 14 Nos. villages benefited for 3279 ha 158

area Land acquisition Details: Proposed Acquired Balance A - G A - G A – G a)Land acquired for dam and allied 974-00 974-00 Nil works. b) Canal and others works. 526 - 36 526 - 36 Nil c) R & R works 91 – 32 90 - 00 1 – 22 TOTAL:- 1592-28 1590.36 1 – 32 Potential details: a) Total potential to be created 3279 Ha b) Potential created to the end of march 3279 Ha 2014 Financial Details : a)Latest Cost of the project Rs. 22.58 Crores. b)Expenditure incurred upto date Rs. 22.58 Crores. March 2014. c) Balance Cost Rs. Nil d)Programme of Balance Cost Rs. Nil e)Expenditure upto march 2013-14 RS. 30.00 Lakhs (2701) Rs. 0.32 Lakhs (2701 head) Grant for the year 2013-14 (2701)

12.4.11 CHULKINALA PROJECT:

Chulkinala Project is a Medium Irrigation Project located near Mustapur village in Baswakalyan Taluka of Bidar District across Chulkinala river which is a tributary of Manjra river which joins river Godavari.

This Project was administratively approved by Government for Rs.329.76 lakhs @ S.R. 1975-76. The revised cost of the project is Rs.3750.00 lakhs @ S.R. 1994-95. The same is approved by the Technical Sub-Committee and also approved by the Government on dated:-23-4-1996. The latest revised cost of the project is Rs.7245.00 lakhs.

DAM :- The Dam has 2340 m length of earthen embankment with zonal section, maximum height of the dam is 15.50 m to store the gross storage of 26.56 MCum (0.92 TMC) and live storage of 25.01 MCum (0.88 TMC).

R.B.C. :- The total length of R.B.C.is 26.64 km and is completed in all respect. The discharge capacity is 38.85 cusecs and irrigable command area is 1821 ha.

L.B.C. :- The total length of L.B.C. is 25.42 km and is completed in all respect. The discharge capacity is 47.23 cusecs and irrigable command area is 2226 ha.

Total Cost of the Project:- a) Original Cost Rs. 3.29 Crores 159

b) Revised Cost Rs. 37.50 Crores c) Latest Estimated cost Rs. 72.45 Crores Achtkat Details:- a) Contemplated Achtkat 4047 Ha. b) Covering Districts Bidar c) Covering Talukas Baswakalyan & Bhalki No.of villages benefited and extent of 17 villages benefited for 4047 Ha. area

Acquired Balance Land Acquisition Details:- Proposed A - G A - G A - G a) Land acquired for Dam & allied works 1768-00 1712-16 55-24 b) Canal and other works 365-39 365-39 Nil c) R & R works 75-10 75-10 Nil TOTAL : 2209-09 2153-25 55-24 Potential Details:- a) Total potential to be created 4047 Ha. b) Potential created to the end of 3/2014 4047 Ha. Financial Details :- a) Latest Cost of the project Rs. 72.45 Crores b) Expenditure incurred upto date 32014 Rs. 72.61 Crores c) Balance Cost -Nil- d) Programme of Balance Cost -Nil- e) Grant for the year 2013-14 (4701) Rs. 50.00 lakhs (4701 Head ) f) Expenditure upto March 2014 (4701) Rs. 15.62 lakhs g) Grant for the year 2013-14 (2701) Rs. 36.00 lakhs h) Expenditure upto 3/2014 (2701) Rs. 1.80 lakhs

Performance Budget-2013-14 DETAILS OF PHYSICAL PROGRESS ACHIEVED FOR THE YEAR 2013-14 Financial in lochs & Area in Ha) 1.Financial Programme Progress Sl. project for the year upto % No 13-14 3/2014 1 Bhima lift irrigationScheme 19200.00 6717 34.98 2 Gandorinala 1037.05 1815.06 175.02 3 Lower mullamari 1250.00 1116.48 89.32 4 Bennithora 1860.50 3523.66 189.39 5 Amarja 3350.00 734.81 21.93 Total 26697.55 13906.95 52.09

2. Financial &Physical expenditure Programme Progress Sl. for the project Financial/physical upto % No year 2013- 3/2014 14 160

Gandorinala Financial 1037.05 1815.06 175.02 1 project Physical(wet) 86.17 - 0.00 Financial 1860.50 3523.66 189.39 2 Bennithora Physical(wet) 1455.30 50.00 3.44 Financial 1250.00 1116.48 89.32 Lower 3 Physical(dry) 313.00 - - mullamari Physical(wet) 152.28 - - Financial 3350.00 734.81 21.93 4 Amarja Physical(dry) 2543.74 441.96 17.34 Physical(wet) 1844.00 162.65 8.82 Bhima lift Financial 192000 6717.59 34.98 5 irrigation Physical(dry) 18288.00 5686.13 31.09 scheme Physical(wet) 10000.00 4038.39 40.38

3. Head wise expenditure Programme Progress Project Financial/physical for the upto % year 13-14 3/2014 Financial SCP 100.00 164.80 15.89 TSP 0.00 0.00 0.00 FIC 237.05 5.86 0.57 Gandorinala SDP 500.00 1518.17 146.39 project Dam safety 100.00 0.00 0.00

2701 100.00 0.08 0.01 Est. - 126.15 12.16 Total 1037.05 1815.06 175.02 Physical (wet) 86.17 - 0.00 Financial SCP 510.50 367.71 72.02 TSP - - - SDP 1000.00 3523.66 352.36 Bennithora FIC 200.00 2.62 1.31 Reparis & 100.00 - - Maintainace (2701) Dam safety 50.00 - - Total 1860.50 3893.99 209.29 Physical (wet) 1455.30 50.00 3.44 Financial SCP 362.64 193.21 53.27 Lower TSP - - - mullamari SDP 1000.00 783.90 78.39 FIC 100.00 2.40 0.024

161

Repairs & maintenance 100.00 - - (2701) Dam safety 50.00 - - Total 1612.64 979.51 60.74 Physical (Dry) 313.00 0 0

Physical (wet) 152.28 0 0

Financial SCP 224.53 89.00 39.64 TSP 00 0 Amarja SDP 2829 734.81 25.97 Total 3053.53 823.81 26.97 Physical (dry) 2543.74 441.96 17.34 Physical (wet) 1844 162.65 8.82 Financial SCP 400.00 26.01 6.50 TSP - - - Bhima lift AIBP 19200.00 6717.55 34.98 irrigation scheme Total 19600.00 6743.56 41.48 Physical (dry) 18288.00 5686.13 31.09 Physical (Wet) 10000.00 4038.39 40.38

4. WATER RESOURCES DEPARTMENT PROJECTS Financial in lakhs Area in Ha) Programme Progress for the Sl.no project Financial/physical upto % year 2013- 3/2014 14 1. Irrigation project zone Gulbarga 1 KARANJA Financial

AIBP - - - NON -AIBP 588 239.40 40.71

SCP 72 61.18 84.97 TSP 25 24.03 96.12 Establishment 1071.65 1136.09 106.01 Total 1756.65 1460.70 83.15

physical 0 0 - 2 CHULKINALA Financial

162

Programme Progress for the Sl.no project Financial/physical upto % year 2013- 3/2014 14 State 39 6.76 17.33 SCP 8 6.74 84.25 TSP 3 2.12 70.66 Total 50. 15.62 31.24

physical 0 0 -

12.5 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, THE IRRIGATION CENTRAL ZONE ,MUNIRABAD

1. Completed projects:- Hagaribomhanalli project, Narihalla Project, Kanaka Nala Project, Rajolibunda diversion Scheme, Vijayanagar Canals and Maskinala Project.

2. On going Projects:-

Tungabhadra Project, (Original works are completed long back. But only modernization works are being taken up.), Hirehalla Project, Singatalur Lift Irrigation Scheme and other Lift Irrigation Schemes.

12.5.1 TUNGABHADRA PROJECT

The Tungabhadra Project comprises of across the river Tungabhadra, a tributary to river Krishna, near Mallapuram in taluk, Bellary District, with canals on both banks to provide irrigation to an extent of 3,62,715 hectares(Karnataka portion only) . This is an inter-state multipurpose project started in 1945 as a joint venture of the then Governments of Madras and Hyderabad. After reorganization of States, the project became a joint venture of Mysore (Now Karnataka) and Andhra Pradesh.

163

In 1945 the contruction of Tungabhadra Canals of Tungabhadra Project was started and completed in stages up to 1968. The embankments of Left bank main canal was constructed with available soil(economically). For this canal, zonal section was not provided. Due to this breaches and piping ( bongas )were occurring frequently.. In order to prevent the occurance of pipings (bongas) and slips and breaches occurred in Embankment reaches the,Expert committee in 1982 recommended to inner strengthen the embankment reaches. Accordingly, the inner strengthening works of embankments of LBMC was tackled during the period from 1982 to 2006 in stages.

As per the Chinival Committee report, it is proposed to take up modernization works in five years from 2006-07 . Major works during the period from 2009-10 to 2013-14 was taken up with a cost of Rs 1257.25 Crores2.1.1 The Physical and Financial progress for the period from 2009-10 to 2013- 14` is as under :-

Physical progress in Km Financial Est Main Canal Distributaries Progress Year Cost in (Expenditure) Crores LBMC LBHLC LBMC RBLLC RBHLC in Crores 2009- 303.56 33.46 0.00 110.0 30.24 22.86 301.42 10 2010- 359.48 50.74 2.15 101.47 7.72 19.00 330.55 11 2011- 403.66 39.83 3.04 145.31 22.75 1.60 334.25 12 2012- Works not talked 13 2013- 291.03 25.06 - 200.76 - - 291.03 14 Total 1686.45 149.09 5.19 557.74 60.71 43.46 1257.25

AN OVER ALL VIEW OF THE TUNGABHADRA PROJECT

TUNGABHADRA LEFT BANK CANAL

1. Name of Project TUNGABHADRA LEFT BANK CANAL 2. Location Left Bank of T. B. Dam 3. Year of inception 1945 Completed in stages up to 1968 (Original 4. Year of completion works)

164

Original cost: Rs. 17.44 Crores Original and latest estimated (Sanctioned by Nizam Government in cost in Crores 1951) 5. Including administrative approval no. and Revised Cost: Rs. 194.40 Crores (ID 122 date/Technical Sanction. MTP 92 Dated: 05-06-1996) Latest cost: Rs. 302.00 Crores Length of canal 6. a) Main canal 226.00 km b) Distributaries 707.00 km 7. Length of ayacut roads 1150 Km 8. District benefited Raichur and Koppal Number of village and Tq Gangavathi Tq, Sidhnoor Tq, Manvi Tq, 9. benefited Devadurga & Raichur Taluk No of WUCS a) Formed 585 10. b) Registered 244 c) Handed over 46 Programme during 2011-12 (including LBMC,LBHLC and 11. Rs. 477 Lakhs distributaries of LBMC,RBLLC and RBHLC) Progress achieved during 2011- 12 upto end of March 2012( Expenditure: Rs. 83.41 Lakhs 12. including LBMC,LBHLC and

distributaries of LBMC,RBLLC and RBHLC)

12.5.2 SINGATLUR LIFT IRRIGATION SCHEME:

The project comprises of construction of barrage across River Tungabhadra near Hammige village of Mundargi taluk in Gadag District to provide irrigation facility to an extent of 2,65,229 Acres in Bellary, Koppal and Gadag districts by utilising 18.55 TMC of water.

Stage-I comprises of utilising 7.64TMC to irrigate 76,181 acres and stage-II of utilising 4.39TMC to irrigate 44,055 acres. Government has accorded administrative approval to implement this scheme with the utilization of 12.03 TMC of water vide G.O. No. WRD 115 WBP 2003, dated 29-6-2006. The DPR of Singatalur LIS amounting to Rs 1894.50 lakhs for utilizing 18.55 TMC(7.64 TMC stage I, 4.39 TMC stage II and 6.52 TMC Balance utilization) by providing irrigation facility to 170236 acres is is submitted to Government of Karnataka for according Administrative approval.

During the budget speech of 2013-14 it was proposed that the Singtalur lift irrigation scheme will be taken up under Micro irrigation and Govt.vide Ltr No WRD 162 VI BHY E 2010 dtd 23-8-2013 directed to 165

submit the modified DPR for Singtalur lift irrigation scheme including micro irrigation. Accordingly the modified DPR for Singtalur lift irrigation scheme including micro irrigation amounting to Rs 5768.04 Crores submitted to Government for approval.

Barrage :- Work is completed and dedicated to the Nation on 04.09.2012

Canal and Lift Works :-

Right Side of the Barrage :-

Intake Canal :- Work is completed

1st Lift :- Work is completed and dedicated to the Nation on 04.09.2012.

Ayyanahalli and Magala branch Canal :- Work is completed and Irrigation potential of 9000 Acres is created during 2011-12.

Rajawala branch Canal :- Work is completed and Irrigation potential of 3000 Acres is created during 2012-13.

2nd Lift :- Work is completed and commissioned.

Hadagali branch Canal :- Canal Works completed physically and an Irrigation potential of 14060 Acres is created during 2012-13.

Left Side of Barrage :-

Intake Canal :- The total length of the Canal is 6.71 Km and excavation of Canal work is nearing completion.

Mundawad and Hammigi Lift :- Work is completed and dedicated to the Nation on 20.02.2013.

Hammigi branch Canal :- Canal Works completed and an Irrigation potential of 960 Acres is created during 2012-13.

Mundawada Branch Canal :- The Canal works are under progress and an Irrigation potential of 1432 Acres is created during 2012-13. Left Bank Main Canal 1st Reach :- The works from 0.00 to 14.50 Km are entrusted to the agencies. Works from Km 0.00 to 7.00 are under progress.

2nd Lift :- Jackwell is completed upto roof level and rising main works are under progress.

Mundargi branch Canal :- The total length of the Canal is 72.00 Km. The works from Km 0.00 to 10.00 and from Km 33.00 to 50.00 are under progress.from km 31.00 to 50.00 Tenders are under progress.

166

Left Bank Main Canal 2nd Reach :- The total length of the Canal is 28.98 Km and works are progress in 4 packages.

Left Bank Main Canal 3rd Reach :- The canal works from km 0.00 to 10.00 are under progress. and from km 13.49 to17.87 work entrusted to agency. Further balance works are under tender process.

3rd Lift :- Work is nearing completion.

Rehabilitation and Resettlement Works :- The creation of Infrastructure in rehabilitation centre for the submerging villages Allipura, Gumgola and Bidarahalli are under progress.

AN OVER VIEW OF THE SINGATALUR LIFT IRRIGATION SCHEME:

1 Name of Project Singatalur Lift Irrigation Scheme Across Tungabhadra River near Hammige village Mundaragi Taluk, 2 Location Gadag District. Longitude : 70 0 50’ E Lattitude : 15 0 02’ N 3 Year of inception March 1998 4 Year of completion Project Works are under progress Original and latest Original estimate Rs. 595 Cr vide G.O. estimated cost in Cr. No. ID –90 MTP –98 and 29-12-2000. 5 Including administrative Technically sanctioned by Chief approval no. and date Engineer Vide CER No. 28/2001-02 Latest cost 1894.50 Crores. Length of canal 6 a) Main canal LBC 207.34 km b) Branch canal 31.70 Km 8 District benefited Bellary, Gadag and Koppal 70 villages of Mundagi and Gada Tq. Number of village and Tq 9 09 villages of Koppal Taluk. benefited 20 villages of Huvina Hadagali Taluk Physical Financial Programme during 2013-14 10,000 Ha Rs. 247.00Crores Progress achieved up to end 10 6657.61 Ha Rs. 174.62Crores of March 2014. Cumulative progress up to 10595.61 Ha Rs. 1124.12 Crores end of March 2014.

12.5.3 HIREHALLA PROJECT:

The Hirehalla Project comprises a reservoir across the Hirehalla, a tributary to the river Tungabhadra near Kinnal village in Koppal Taluk of 167

Koppal District, with canals on both banks, to provide irrigation to an extent of 8330 Ha; in Koppal Taluk. The proposed utilisation is 64.24 M.Cum; (2.27 TMC). Administrative approval to the project costing Rs. 6.35 Crores has been accorded vide G.O.No.PWD 174 MTP 73, dated: 24-5-1979 and the revised estimate for Rs.90.00 Crores was submitted to the Government for the approval. Technical Advisory Committee has cleared the estimate and the Administrative approval from the Government is awaited. However Government has directed to submit the revised estimate according to the latest cos.The revised cost of the project would be Rs 365.00 crores and the revised estimate is under preparation.

DAM AND CANALS:

The Dam works of this project and major portion of canals are completed and dedicated to the nation on 26-12-2001 by the Hon’ble chief Minister of Karnataka. Themain canals(left side and right side) of this project are completed. Out of total 64Distributaries , 62 distributaries have been completed and 2 Distributaries are underProgresss out of 8330 Ha,potential created is 8206 Ha and balance potential of 124 Ha is programmed to create during the year 2014-15. Canals:

Right Bank Canal: The total length of canal is 25.00 km. The work of excavation, embankment and lining work of Right Bank Canal from km 0.00 to 25.80 km is completed. Out of 85 CD works coming in this reach, all C.D. works are completed. Further AT K.M. 19.00 Escape as well as at K.M. 22.00 Protective wall are completed.

Left Bank Canal:

The total length of canal is 24.60 km. The earthwork excavation and embankment from km 0.00 to 24.60 km is completed. The PCC slab lining work in the reach from km 0 to 24.60 is also completed. Work of all the 75 CD structures is completed. Construction of Railway Bridges at Railway crossings at km 20.70 of RBC and at km 19.70 of LBC is completed. Construction of Pipe Culvert on NH 63 crossing at km.21.28 of RBC and Pipe Culvert on NH-63 at km 19.82 of LBC is completed.

Distributaries : The construction of distributaries under RBC from Dy. No.1 to 37 is completed in all respects, except for Distributary 35 which is delayed due to Land Acquisition problems. Water has been let out upto distributary no.34. The construction of distributaries under LBC from Dy.1 to 27 including Distributary no.21 (Branch Canal) is completed. Distributary no.21 (Branch Canal) is having a length of 14.775 km. Earth work and lining work for the distributory is completed. Water is let-out up to Distributary No. 27 including Distributary No. 21 (Branch canal). Land Acquisition: 168

An area of 4448.00 Acres has been acquired in the villages of Yelburga and Koppal taluks of Koppal district for earthen embankment, Spillway works, Submergence area, Canals and Distributaries, Quarry, Ayacut roads, Camp colony and for Rehabilitation centres under Hirehalla Project. Acquisition of 440.38 Acres of land is in different stages of the process. (i) Earthen Embankment: The earthen embankment is completed upto its top level in its entire length including end connections to spillway. (ii) Spillway : The Spillway with radial gates is completed . (iii) Sluices: The canal sluices at right flank and left flank are completed.

Railway Crossing works :

Railway crossing and national highway crossing works of Distributory No 17 of RBC is completed. The balance work in this Distributory is also completed. Water is let into the canal and irrigation to an extent of 90 hectares is achieved. It is planned to irrigate the balance area of 124 hectares in the year 2014-15

Rehabilitation Works:-

For rehabilitation for Mudlapur, Shirur, Muttal and villages Govt has sanctioned an amount of Rs. 5426.11 Lakhs under Govt order No:

PÀAE/88 DgïEºÉZï 2010 ¨ÉAUÀ¼ÀÆgÀÄ, ¢: 27-11-2010. Excluding the expenditure of Rs 1485.06 lakhs incurred, for revised R&R package an additional amount of Rs 3940.95 lakhs has been sanctioned. Government released Rs. 2000.00

Lakhs for rehabilitation works vide Govt order No: d¸ÀAE/ 64 /JAn¦/2009,

¨ÉAUÀ¼ÀÆgÀÄ,¢:06/02/2012 under head of account 4701-37-800-0-01-132(P) through Karnataka Niravari Nigam Ltd. Out of Rs.2000.00 lakhs, Rs.1809.00 lakhs has been deposited to Assistant Commissioner,Koppal for R & R works..The balance 191 lakhs grant has been utilized to take up R & R works in Shirur, Muthal, Virapur and Muddapur villages and works are under progress. For the balance work additional Rs.46.00 crores is required.

AN OVER ALL VIEW OF THE HIREHALLA PROJECT:

Name of Project Hirehalla Project

Across Hirehalla and Veerpurhalla 4 Km Location U/s of Kinnal village. 169

Year of inception 1979 Original cost: Rs. 6.35 Crores. Original and latest estimated cost in PWD 164 MTC 73 Dated 24-5-1979 Crores. Revised cost: Rs. 365.00 Crores. Including administrative approval no. and date (Administrative approval to be obtained from Government) Length of canal LB- 24.60 Km; a) Main canal RB- 25.80 Km b) Distributaries 63 Km c) Branch canal 15 Km d) FIC Under progress Length of ayacut roads 65 Km District benefitted Koppal Number of Tq benefited 1,Koppal No of WUCS a) Formed 7 b) Registered 3 Programme during 2013-14 Rs. 487.00 lakhs Progress achieved during 2013- Rs. 472.00 lakhs 14 upto end of 03/2014.

12.5.4 HAGARIBOMMANAHALLI PROJECT:

The construction of the dam and allied work was completed during 1972, and water was stored during the year and let out for irrigation on trail run. Maximum inflow in to the reservoir has been recorded during 1981. Since, then the reservoir is functioning satisfactorily as per available records and no major problems have been encountered with.

Hagaribommanahalli project is constructed across chikahagari river near Malvi village of Hagaribommanahalli Taluk at longitude 760 -11’-22” East and Latitude 140 -59’-52” North & 7 Kms from Hagaribommanahalli Taluk. The project was administratively approved by the Government of Karnataka vide G.O.No. PWD 6 MHB 59 dated 13.5.1959 for Rs. 85.41 Lakhs and technically sanctioned vide Chief Engineer, Irrigation Project letter No. 4857-60/TA-3 dated 29.5.1959. The revised estimate has been approved for Rs. 412 lakhs by Government vide G.O.No PWD 129 MTZ 86 dated 13.9.1988

Hagaribommanahalli Project comprised of two canals viz right bank and left bank canals having lengths of 33.81 Km and 16.51 Km respectively to irrigate 1594 Ha under right bank canal and 1371 Ha under left bank canal totaling to 2965 Ha. The cropping pattern envisaged in the original project report is Khariff paddy to an extent of 2965 Ha and DCW crops to an extent of 2965 Ha during Rsbi.

170

The Dam is of earthen homogeneous section and zonal section in high bank. The length of Dam including breaching section is 1606.60 M. The length of earthen Dam is 1490.47 M. The maximum height of the Dam is 15.21 M above the deepest river bed. The spillway is of chute type fitted with 10 No’s of vertical left gates of size 9.15x6.10 M each. Maximum flood discharging capacity of the spillway is 2698 Cumes.

To limit of irrigation requirements to the allocation of 56.64 MM (2TMC), suitable cropping pattern consisting of 900 Ha of Paddy and 2065 Ha of DCW in Khariff is proposed.

The Chief Engineer , Irrigation Central Zone, allocated 100.00 lakhs for maintenance works during the year 2014-15 vide letter No 240 Dated 28/04/2014.

12.5.5 NARIHALLA PROJECT:

The construction of the dam and allied works commenced during the year 1972 and was completed by March 1981. Water was stored from 1978, and the dam has filled up once during 1981. No problem have been encountered with and the dam is functioning satisfactorily as per available records.

The Narihalla Project envisages the construction of an earthen dam at Taranagara village site in Sandur Taluk, Bellary District. The project is a multipurpose project intended to supply 10 cusecs of water to N.M.D.C. Now it has been changed to 4 cusecs per day as per Government order No. PWD 165 GIP 80 dated 4.6.1988 and to create irrigation potential of 3500 acres of Khariff dry. The Government has agreed to supply remaining 6 cusecs of water to Sandur town for drinking water purpose in two stages (2+4) as per Government latter No.ID 49 MTP 92 dated 20.11.1993 and 17.8.1994 respectively. Now in first stage 2 cusecs is drawn to Sandur town. The revised estimate cost is Rs. 370 Lakhs.The site is located at Taranagar village at latitude 150 -7’-17” and longitude 700 -36’-25”.

The Narihalla dam is an earthen dam of 295 M length and has a maximum height of 32.92 M above the river bed level. The spillway for the dam is provided on the left bank and designed as a chute spillway with a stilling basin at the downstream end. The spillway is fitted with 5 No’s of vertical type crest gates of size 6.09x9.14 M. The reservoir formed by the construction of the Dam has a gross storage of 22.93 Mcum and a live storage of 20.86 Mcum. The Scheme contemplates utilization of 8.07Mcum for irrigation, 5.35 Mcum for domestic waters supply to Sandur town and 3.56 Mcum for industrial water supply NMDC. The project benefits an area of 3500 acres.

The Chief Engineer , Irrigation Central Zone, allocated 85.00 lakhs for maintenance works during the year 2014-15 vide letter No 240 Dated 28/04/2014.

12.5.6 RAJOLIBUNDA DIVERSION SCHEME:

The Rajolibanda Diversion Scheme(RDS) was constructed by the Erstwhile Government of Hyderabad in 1947 .This scheme was planned to utilize the water in catchment area flow & regenerated flows in the Tungabhadra river 171

below TB Dam, after utilization of ancient channels(i.e.VNC) & to irrigate 93,379 Acres with a canal on left side. The RDS is constructed as per the agreement reached in the year 1944 between the madras state & Hyderabad government.

After the reorganization of the states in the year 1956, the RDS head works and first 27 miles of the canal with distributaries 1 to 14 are fall in the territory of Karnataka State and remaining canal anddistributories in Andhra Pradesh.

The canal runs for a length of 27 miles (42.60 Km) in Karnataka State and remaining length of 62 miles in Andra Pradesh. There are 14 distributaries in Karnataka State and the ayacut benefited is 5879.00 acres .The number of distributaries in Andhra Pradesh is 22 and area benefited in Andhra Pradesh is 87,500 acres.

The project was commenced in the year 1947. The anicut, distributaries falling in Karnataka State are completed in the year 1958 and water is letout in the canal during July 1958.

As the RDS main canal was designed to carry 850 cusecs at head and Karnataka is to provide discharge of 770.00 cusecs at Andhra Pradesh border (ie. At Km 42.60) after utilizing Karnataka share of 80 cusecs. But due to disturbed lining accumulation of silt in bed and due to over topping of water at certain banking reaches coming under Karnantaka State area are in bad shape and also due to changes in hydraulic parameters of main canal (as the canal was designed based on the parameters available during the year 1947) it is not possible to draw more than 640 cusecs at head, So it is possible to provide only 400-450 cusecs at AP border as against design discharge of 770 cusecs. The Andhra Pradesh Government constituted committee to look into the matter and to suggest remedial measures to improve the flow conditions of the canal. Accordingly four modernisation works takenup to improve the flow conditions of the canal.

Following 4 packages are takenup for modernization

1. Package-I Modernisation of RDS Anicut and head works. 2. Package-II Modernisation of RDS main canal from Km 0.00 to 15.00 including improvements to cD works. 3. Package-III Modernisation of RDS main canal from Km 15.00 to 30.0 including improvements to CD works. 4. Package-IV Modernisation of RDS main canal from Km 31.00 to 42.60 including improvements to CD works.

Package-III & IV are almost completed & Package-I & II are under progress.

12.5.7 KATARKI LIS:

172

This LIS is located on left bank of Tungabhadra river , near Katarki village in Manvi Taluk of Raichur district to irrigate suffering ayacut of 450 acres at the tail end of distributary no: 89/8/1 & 89/8/2 of TLBC.

Government accorded administrative approval to this LIS for Rs 70.81 lakhs vide G.O.No:WRD/56/MTP/2001 dated 30.10.2003. The estimate is sanctioned for Rs 58 lakhs by CE,ICZ, Munirabad vide CER No: 07/2003- 04.

The work has been entrusted to KRIDL-Raichur (erst while KLAC) on dated 15.04.20116 for Rs 46.83 lakhs .The stipulated period for completion of work is six months from date of agreement.The supplementary agreements corresponding to sub-estimates for formation of approach roadto Katarki LIS and construction of Intake well for Rs 2.00 lakhs and 2.25 lakhs has also been executed.

The work was started on 15.04.2006. During execution ,as it was felt very essential to execute some items which were not included in the estimate, the then Chief Engineer, ICZ, Mnirabad approved EIRL & the agency completed the following components of the work. a) Civil works:- Inlet channels, sump well, pump house, laying of pipe line for raising main and gravity main , distribution chamber have been tackled and completed. b) Electrical Equipments:- During 2009 electrification works has been tackled and completed by another agency M/s Praveen Electricals, Sirguppa.

In order to make the Lift Irrigation Scheme function, f following additional components which were not included in the sanctioned estimate are essential for completion of scheme and these provisions are made in the Workslip .

i) Scour valves for emptying the pipes & to plug the leakages. ii) Providing and laying of drainage pipes 450 mm dia NP-2. iii) Construction of embankment. iv) Strengthening of pipe joints to arrest joint sinking and movement.

Accordingly , workslip including EIRL was prepared and submitted to Government for Rs.85,80,683.00 which works out to 81.34% excess over the amount put to tender of Rs.47,31,909.00 which was in turn handed over to KNNL by the Government. The Superintending Engineer KNNL has requested to submit some of the details of work vide letter No.702 dated 21- 5-2004. The details will be submitted shortly.

The total expenditure incurred up to the end of March 2014 is Rs. 73.47 Lakhs Grant allocated for the year 2014-15 is Rs.25.00lakhs. After obtaining approval to the workslip,the balance work will be taken up & completed in all respects & the scheme will be commissioned.

173

12.5.8 BOYALMARCHED LIS:

This LIS is located on right bank of Kappagal nala, near Boylmarched village in Manvi Taluk of Raichur district to irrigate suffering ayacut of 1185 acres at the tail end of distributary no: 89/7 of TLBC. Government accorded administrative approval to this LIS for Rs 73 lakhs vide G.O.No:WRD/55/MTP/2001 dated 30.10.2003. The estimate is sanctioned for Rs 73 lakhs by CE,ICZ, Munirabad vide CER No: 06/2003-04. The work has been entrusted to KRIDL-Raichur (erst while KLAC) on dated 25.05.2005 for Rs 60.97 lakhs .The stipulated period for completion of work is six months from date of agreement.

The work was started on 12.02.2006. During execution ,as it was felt very essential to execute some items which were not included in the estimate, the then Chief Engineer, ICZ, Mnirabad approved EIRL & the agency completed the following components of the work.

c) Civil works:- Inlet channels, sump well, pump house, laying of pipe line for raising main and gravity main , distribution chamber have been tackled and completed. d) e) Electrical Equipments:- During 2007-08 to 2008-09 electrification works has been tackled and completed by another agency M/s Praveen Electricals, Sirguppa.

In order to make the Lift Irrigation Scheme function, following additional components which were not included in the sanctioned estimate are essential for completion of scheme and these provisions are made in the workslip.

i) Scour valves for emptying the pipes & to plug the leakages. ii) Air valves at ridge points. iii) Pressure relief valves near manifold. iv) Strengthening of pipe joints to arrest joint sinking and movement.

Accordingly , workslip including EIRL was prepared and submitted to Government for Rs.94,62,985.00 which works out to 53.58% excess over the amount put to tender of Rs.61,61,727.00 which was in turn handed over to KNNL by the Government. The Superintending Engineer KNNL has requested to submit some of the details of work vide letter No.703 dated 5- 2004. The details will be submitted shortly. The total expenditure incurred up to the end of March 2014 is Rs. 51.93 Lakhs. Grant allocated for the year 2014-15 is Rs.25.00lakhs.

After obtaining approval to the workslip,the balance work will be taken up & completed in all respects & the scheme will be commissioned.

12.5.9 ALAVANDI BETAGERI LIS:

174

The Detail Project report of Alavandi Betageri Lift Irrigation scheme have been submitted to Govt. of Karnataka for approval in TSC meeting.

The Karnataka Government Letter No. WRD-49-KBN / 2009 Bengalore. Dt- 19-3-2012 allocated 0.50 TMC of water to Alavandi Betageri Lift Irrigation scheme. With reference to the above letter Executive Engineer No.1. TR Division, Munirabad submitted an estimate of consultancy services for priliminary investigation ,survey ,prearation of preliminary designs, drawings ,package estimate and DTP for lift head works,and detailed survey ,investigation,prearation of designs,drawings km wise estimates and DTP for main canal and distribution net work of alavandi betageri lift irrigation scheme of koppal dist & tq ,to amount of 25.00 Lakhs for approval.

The Chief Engineer, Irrigation Central Zone, Munirabad given administrative approval along with 1:3 Grant of 8.33 Lakhs in the Head Of Account MH 4701-80- 800-0-01-059 for the year 2012-13.

The above consultancy Services Estimate is prepared based on the sanctioned estimate rate of similar work of Left Side IInd lift Singatalur Lift Irrigation scheme under Superintending Engineer, T. P. C. Munirabad Dt for the year 2011-12 and Singatalor lift bank Main canal I reach on L/S of SLIS under Superintending Engineer, T. P. C. Munrabad for the Year 2009-10.

The consultancy Services estimate is technical sanctioned by Superintending Engineer, TPC Munirabad. As per the Government Letter No. PWD 671 FC-1 /2009 Bengalore Dated 3-2-2010. The same work have been entrusted to Preethi CAD Consulting Engineers Pvt. Ltd Bangalore on Tender Basis.

Preethi CAD Consulting Engineers Pvt. Ltd Bangalore have prepared detailed Project Report to an amount Rs. 54.29 Crores and the same submitted to Managing Director . K.N.N.L. Bangalore for ERC approval vde letter No 340 Dated 12/05/2014.

12.5.10 WALABELLARY LIS:

It is proposed to feed water by Walaballery Lift Irrigation to suffering atchcut of 6278 Acres under branch distributory 9R of Distributory NO.54 under Tungabhadra Left Bank canal. A proposal has been submitted to TAC.

TAC cleared with some explanations to submit the proposal MIP control board. MIP control board in its meeting held on 1-10-2001 approved subject to condition that before according Technical approval detailed Design & estimates should be prepared.

Government has ordered under letterNo.WRD/103/MTP/2009 Dated: 19/5/2011 directed to transfer the work to KNNL Bangalore. MD KNNL in their letter No.1178 Dated: 18/6/2011 directed to submit a detailed report and investigations report of this project. The Detailed project report and Estimate of the Walaballery Lift Irrigation Scheme is prepared for RS.23.10 175

crores & submitted to the MD KNNL Bangalore vide this office letter No.2786 Dated:17/11/2011 for approval and allocation of grant. MD KNNL vide letter Dated: 12/12/2012 submitted proposal to Government for Administrative approval grant allocation and also requested for water allocation against availability in order to take up the work under KNNL.

The modified estimates prepared considering 2012-13 DSR for Irrigation & PWD SR which works out to RS.2680 lakhs and resubmitted to MD KNNL Bangalore along with the detailed report for approval vide letter No.935 Dated:24/6/2013 & to take up the work.

12.5.11 KANAKANALA DIVERSION PROJECT:

Kanka Nala Project is a medium irrigation project situated near village killarhatti kustigi(taluk) Koppal District and constructed in the year 1975 with an Irrigation potential of 5100 acres. 0.27 TMC of water allocated for this project, but due to non availability required 0.27TMC of water it is proposed to divert nala water near village Arya Bhogapur on U/S of Maskinala. For survey preparation of estimates & DTP’s it is entrusted to M/S E.I. Technology’s Bangalore. & Alignment proposal from KM 0.00 to 5.00 approved. The estimated cost is 62.53 crores. This proposal along with DPR was submitted to the Government for placing before the TAC for clearance.Since the cost of estimate is more than Rs.5.00 Crores vide this office letter dated:27.09.2012.The TAC during 103rd meeting has raised certain observations for compliance.The compliance to the observations of TAC was also submitted to the Government.

12.5.12 MASKINALA PROJECT :

Maskinala Project is a Medium irrigation project near Maraladinni village in Lingasugur Taluka of Raichur District.The project as envisage consist of construction of central spillway of 57 M length with a discharging capacity of 2590 Cumecs through 4 Nos. of 12 M x 8.5M Radial gates.Earthen Dam on either side upto required TBL 474.880M. There are two canals, LBC takes off from Ch.148M and runs for a length of 10 KM to provide irrigation facilities to 1940 Ha (4793 acres) and RBC takes off from Ch: 638 M and runs for a length of 11.50 Km to provide irrigation facilities to 1061 Ha (2623 acres) of land .In total it irrigates 3001.00 Ha (7416 acres) in Lingasugur Taluk.No Housing property of any village is going to be submerged under this project, hence rehabilitees does not arise. The project was originally approved for Rs.311.00 lakhs at 1976-77 S.R.Vide G.O No.PWD 62 GIP 78 Bangalore Dated: 22-01-1979.The project was revised for Rs.1428.80 lakhs at 1983-84 S.R and administratively approved vide G.O.No.PWD 48 MTZ 83 Bangalore dated: 25-01-1985. The project was again revied for Rs.2357.00 lakhs at 1993-94 S.R. administratively approved vide G.O.No.ID/134/MTP/1995 Dated: 22/04/1996 with irrigation benefits to 3001 Ha. IIIrd Revised estimate of the

176

project is Rs. 4835.00 Lakhs at 2003-04 price level. And Updated cost of the Project is Rs.5465.00lakhs. Stage of work as on 31st March 2012:

Commencement of work : The project was started in 1976. Date of completion : The project was completed on 31-03-2007. Present stage of work : The project completed and it is in maintenance

Details of potential created: Sl.No. Canals Total potential Potential created 1. LBC 4793 Acres 4793 Acres 2. RBC 2623 Acres 2623 Acres Total 7416 Acres 7416 Acres Season wise (Utilisation of Potential) area irrigated under the Maski Nala Project: (Area in Acres &Guntas) Sl. Season Year Total No. Khariff Rabi 1. 2004-05 2197-30 678-00 2875-30 2. 2005-06 3212-12 1235-20 4447-32 3. 2006-07 3271-24 924-06 4195-30 4. 2007-08 3791-07 3080-03 6871-10 5. 2008-09 3040-29 3594-00 6634-29 6. 2009-10 3375-29 4075-20 7451-09 7. 2010-11 4273-00 747-02 5020-02 8. 2011-12 1836-10 -- 1836-10 9. 2012-13

Details of Expenditure incurred (Rs. in Lakhs) :

EST WORKS TOTAL Expenditure incurred since 471.90 4860.06 5331.96 inception up to end of 3/2012

12.5.13 HEDAGINAHAL BARRAGE PROJECT:

It is proposed to construct 4 barrages across river Tungabhadra out of four barrages proposed. Hediginal is one situated at Hediginal village in sindahnoor Taluk Raichur District.Due to reducing storage capacity of TB Reservoir from 133 TMC to 100.855 these barrages are proposed to store water. Hediginal barrage is proposed to store 1.50 TMC of water project cost is 13860.00 lakhs.Details of balancing reservoir is as mentioned below.

Sl Name of the Water Storage Estimated N Balancing Reservoir source capacity in cost in o and location TMC Crores 177

1 Hediginal Village in T.B. Sindhanur Taluk 1.5 138.60 River Raichur District

The DPR and Detailed estimates for the above Balancing Reservoir is submitted to Govt. for placing before the 95th TAC held on 6/4/2010 .During the Deliberation of the meeting it was observed that the inter-state angle should be properly analysed at Govt. level and this interstate matters which requires the opinion in the light the proceedings being under way before Tribunal and are in the final stages. Hence the TAC felt that the issue can be deferred for the time being.

12.5.14 KARUR LIS:

The estimate for construction of this Lift irrigation scheme was technically sanctioned for Rs. 45.00 Lakhs vide C.E.R No. 38/98-99 under head of account MH 2701-318-RBC-E&I to suplliment tail end ayacut of Kurignur dy. and the work has been entrusted to M/S Gopal cement spun pipe work Gulbarga, vide agreement No. 02/ 99-2000. The above work was started on 07-02-2000 and due date of completion was 06-06-2002. The work of Raising main and construction of cistern work is partially completed and procurement of motors as per tender agreement.

During the execution of Jackwell cum pump house,due to the objections of the villegers & as rainy season started the work was stopped at that stage only. From 2002-03 to 2006-07 adequate grants were not provided in the budget for the above work. So contract was closed as per the request of the contractor the contract was closed & finalized.

Hence incorporating all the necessary following items for the balance work revised estimate is technically sanctioned for Rs 180.00 Lakhs vide CER No. 276 /2012-13 & work entrusted to M/S Sri Srinivasa Construction India Pvt.Ltd., Bellary vide agreement No.214 /2013-14 Rs. 155.87 Lakhs and work was commenced on 09-05-2014 & the work is under progress.

1) INTAKE WELL:-. Intake well of 5M diameter is proposed with RCC M-20 and top of well is covered with RCC roof. The intake well is proposed near lowest Nala Bed Level at a distance of 60 Mtrs from Bank of river. 2)INTAKE PIPE:- One row of intake pipe 1200mm dia provided Connecting intake well to jackwell situated at 60m away from intake well With a bed fall of 1:300.

3)CIRCULAR JACK WELL CUM PUMP HOUSE:- It is proposed to construct Jack well of 7.20m inner diameter with RCC raft and steining wall with RCC M20 Grade thickness varying from 0.45m to 0.30m .

178

4)RAISING MAIN: - The balance length of 129.50m of PSC pipes 600 mmdia and Necessary Ms specials ,valves and valve chambers anchor blocks and thrust blocks.

5) DELIVERY CISTERN:- The delivery cistern of size 6.25x6.25x1.80 m (inner) for 3 minutes detention time at left side bank of kuriganur distributary. The bed and sides of delivery chamber is proposed RCC wall inside and providing and laying NP-2 class hume pipe of 600 mm dia for delivery of water is proposed.

6)ELECTRO MECHANICAL WORKS:- The jackwell cum pump house is proposed to accommodate 3Nos of 70HP DWTP pumps ( including 1No. standby). The additional items such as transformer, Starters, control panel board unit, cables ,earthing and EOT Crane, HT substation and power supply to LIS scheme from nearest substation are included.

12.5.15 VIJAYANAGARA CANAL MODERNISATION

During Vijayanagara Dynasty, 18 Channel networks were constructed in Tungabhadra basin through an irrigation sluice on right side of Tungabhadra Reservoir to Siraguppa. Out of these 18 Channels 16 channels covers an area of 16241 ha coming in the districts of Bellary, Raichur and Koppal. These channels are provided with size stones masonry lining and is completely damaged. Also some of the structures are in dilapidated condition. For modernising the existing canal system, DPR has been prepared and the Government of Karnataka has administratively approved the project for Rs.255.00 Crores vide GO No. Ja. Sam. E/107/MTP/2012, Bangalore, dated:21.01.2013. The DPR of this project is submitted to CWC for obtaining clearance for getting AIBP assistance. Work will be taken up after getting CWC clearance.

12.6 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, VARAHI PROJECT ZONE, SIDDAPURA.

12.6.1 VARAHI IRRIGATION PROJECT:

179

BREIF DESCRIPTION:

The Varahi Irrigation Project envisages Construction of 1Diversion Weir across at Horriabbe near Siddapura Village, Udupi District to create irrigation potential to an extent of 15,702 Ha. (38,800 acres) in Kundapura and Udupi taluks of Udupi District, by utilizing the daily release of 1100 Cusecs of tail race water from Varahi underground hydro electric project situated in the upstream of the river at Hosangadi.

The Varahi Irrigation Project is administratively approved originally by the Government of Karnataka vide G.O.No. PWD 71 GIP 76, dated 27-3-1979 for Rs. 943.00 lakhs. Further revised cost amounts to `.56953.00 Lakshs.

VARAHI DIVERSION WEIR:

A concrete diversion weir of 145 meters. Length and 17.50 meters height above the deepest foundation level is proposed to be constructed at horriabbe site near Siddapura Village, Udupi District.

Due to Construction of Diversion Weir total 121.58 Ha. of land will submerge and two villages will be submerged partially.

CANALS:

Varahi Right Bank Canal takes off from the Diversion weir and runs to a length of 42.73 K.M. A branch canal takes off from Right Bank Canal at 19th K.M. and crosses the river Varahi through an aqueduct and Left Bank Canal starts from this aqueduct and runs for a length of 44.35K.M. The Lift Canal start from Left Bank Canal at 7th K.M. of Left Bank and runs for a length of 33 K.M.

The proposed atchkat to be covered from this Project is as detailed below: Atchkat covered is in Udupi District. Sl. Length, Irrigable Canal details No Km area, Ha

180

Sl. Length, Irrigable Canal details No Km area, Ha 1 Varahi Right Bank Canal 42.73 1992 Varahi left bank canal 2. (From off-take at 20th Km of Right Bank 44.35 10987 Canal) Lift canal (From off-take at 7th Km of Left 3 33.00 2723 Bank Canal) Total 15702 Villages benefited: 33 1. Kundapura Taluk 8324 villages 35 2. Udupi Taluk 7378 villages 68 Total 15702 villages

 Right Bank Canal (42.73 Km.): River aqueduct is completed. Survey works completed for full length Varahi Right bank Canal from 0.30km to 1.00 km, 1.00 to 2.00 km , 5.00 to 6.385, 9.00 km to 10.00 km and 12.00 km to 14.00 km are completed. Ch 4.00 km to 5.00km, and tunnel work is in progress The Balance works of 3,4,9,11 km and works from km 14.00 to 18.725 km are taken up and work is in progress  Left Bank Canal (44.35Km.): Upto 21 km works Completed. Ch 23.00 km to 24.00 km, 25.00 to 26.00, 28.00km to 30.00 km are completed. Ch 21.00 km to 22.00km, 24.00km to 25.00 and 27.00 to 28.00 km works are in progress.

 Lift irrigation canal (33 Km.) : Works are completed. Power connection received and commissioned on trial basis. This project is received central assistance under AIBP since 2007-08.  PROGRESS DURING 2013-14: The total estimated cost of the project is Rs. 569.53 Crores. Cumulative expenditure incurred on the project up to end of March 2014 is Rs. 541.05 Crores. During 2013-14 against the programme of Rs. 81.00 crores, expenditure of Rs. 20.33 crores has been incurred up to end of March 2014.

181

TUNNEL TUNNEL

SALT WATER EXCLUSION DAM VARAHI RIVER AQUEDUCT

VARAHI RIGHT BANK 10th KM

182

12.7 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER BHADRA PROJECT ZONE, CHITRADURGA.

12.7.1 Upper Bhadra Project :

Chitradurga and Tumkur districts coming under middle part of Karnataka have been declared as drought prone districts. In spite of vast useful lands the riots in this region are suffering due to scanty rainfall and non-availability of Irrigation facilities. The ryots under this region have represented the Government to provide irrigation facility by diverting the excess water from the rivers Tunga and Bhadra flowing in the neighboring districts of Chickamagalur and Shimoga. Considering the long standing plea of the ryoths the Government accepted the proposal for taking up of Upper Bhadra Project and had accorded Administrative Approval vide GO No./WRD/63/VIBYAE/2000 dated 23-08-2003 for Rs. 2813 crores. In view of the representations received from environmentalists for the submergence of vast area and dry effects on environment the Government constituted a committee under the Chairmanship of Sri.K.C.Reddy to study the pros and cons for implementation of the project and availability of water and submit the report.

The committee headed by Sri.K.C.Reddy studied in detail regarding availability of water, Technical aspects of the project, storage and flow of water and the effects on environment and suggested numerous changes to the original report and submitted the report in July 2006 with their recommendations.

The main features of the report are as below.

1. Lifting of 15 TMC of water from Tunga river and delivery to Bhadra reservoir. 2. Lifting of 21.50 TMC of water from Bhadra reservoir and delivering it to proposed delivery chamber near Ajjampura through a canal system. 3. Construction of Tunnel near Ajjampura and letting out water in Chitradurga branch canal for irrigating semi-dry crops during Khariff and filling 156 MI tanks in draught prone areas of Chickamagalur, Chitradurga, Kolar and Tumkur districts there by increasing the underground water table in the region and creating basic facility of drinking water in the reason.

The Government accepted the report of Sri.K.C.Reddy and in view of implementing the project quickly, entrusted the implementation of project to KNNL during November-2006. As per the recommendation of Sri.K.C.Reddy an estimate amounting to Rs. 5985.00 crores was proposed during 2008 and In-Principle approval was obtained vide Govt. letter No.WRD/52/VIBYAE/2004(Part-I) dated 15-9-2008. The estimate has provision of Rs. 3388.00 crores for irrigation works and Rs. 2597.00 crores for drinking water supply needs.

183

The report of proposed project is unique and by implementation of this project there is no submerge/Rehabilitation and involves minimum damage to the environment.

In accordance with the directions of the Government, the project is proposed to be completed by obtaining assistance from ADB and the process for the same is under progress from KNNL. Its is programmed to complete the project by 2020.

Project Purpose:

The project envisages irrigating 107265 Ha in Chickamaglur and Chitradurga districts, and filing up of 156 tanks in Chickamaglur, Chitradurga, Tumkur and Kolar districts and thereby increasing the underground water which helps for using it for drinking water in the region. It helps in irrigating crops during khariff and helps in solving the problem of drinking water. a) Water allocation:

21.50 TMC of water has been allocated under Scheme-A for Upper Bhadra Project. b) Details of Project:

Under this scheme it is proposed to provide irrigation facility for 2 taluks to an extent of 2276 Ha in Chickamaglur district and 4 taluks to an extent of 104989 Ha in Chitradurga districts where by a total extent of 1,07,265 Ha. This requires 13.88 TMC of water.

Filling up of 4 tanks in Chickamaglur and 33 tanks in Chitradurga district and increase the underground water in the region and providing facility for drinking water. This requires 2.02 TMC of water.

An allocation of 1.86 TMC of water has been made for Jaglur branch canal from Pollavaram Project as available for State Government.

Increasing the ground water table by filling 100 tanks in Tumkur district and 19 tanks in and thereby to provide drinking water facility. This requires 5.60 TMC of water.

Implementation of Project:

In view of implementing the project speedily three critical works coming in the intial reaches of Upper Bhadra Project are entrusted on EPC tender basis to three agencies. Accordingly, the agencies are required to complete the construction in 3 years and maintain for 5 years.

184

Name of work Agency Tender Amount Package-I Lifting of 15 TMC of M/s SEW-JYOTI Rs. 324 Crores water in two stages for (JV) Hyderabad a lift of approximately 80m and delivering to Bhadra reservoir through 10KM canal. Package-II Lifting of 21.50 TMC of M/s RNSIL (JV) Rs. 1032 Crores water in two stages for Hubli lift of approximately 88m and delivering the water to proposed delivery chamber near Ajjampura through 40.5 Km canal. Package- Construction of 6.90 M/s SNC Power Rs. 223.96 III Km Tunnel near Corporation Crores Ajjampura and Limited, Bangalore delivering the water to Chitradurga branch canal. This includes 0.33 Km approach and 2.77 Km length Exite canal

Progress of Works:

Package-I

The work of raft foundation and raft slab is completed. Laying of 90m length of rising main is completed for Pump House-I. placing of 5 Nos Draft tube are erected.

Laying of bed concrete lining for intake canal from on 1428 to 1503 for 117m is completed. Pier work for super-passage at Ch: 1513 is completed and abutment and wing wall work is under progress. The designs of 15 C.Ds is approved.

Approval is obtained for the power required of 35 MVA for each Pump Houses at Kanbur and Kasbur. The Electro-Mechanical components essential for Pump House-I and II viz: 10 Pumps, 10 Draft tubes, 10 Spiral casing, 10 impellers and 10 shafts motors with accessories. 1 No EOT crane have been supplied to the work spot. The proposal of Extension of time is approved upto 31.3.2015 by Managing Director, KNNL vide letter dated 25- 3-2013.

185

The total expenditure incurred upto 31-3-2014 is Rs. 101.61 crores the amount of pending bill is 1.40 Crores.

Package-II

5 Nos of draft tubes and spiral casings are erected at a situated place. One pit lines is embedded. Concreting works for pump house-I is under progress. Fabrication of roof truss is under progress. Lining of fore bay has been completed. Excavation of canal for a length 14.50 Km is completed. Work of canal lining is completed upto 9.80 Km. Till date the 32 designs are approval Eighteen cross drainage works are completed and balance are under progress. Jambadahalla aqueduct is under progress concreting of 5 trough have been completed out of 34 troughs. Excavation of pump house-2 work has been taken up, till date excavation for a depth of 30M is completed. Three 30/40 MVA and SFC transformers are erected. The foundation work for 14 circuit breakers are completed. Electro Mechnical equipments of Pump House-I & II are supplied to the site. The proposal of extension of time is approved by MD, KNNL, B’lore vide ltr. Dated 9-1-2013 upto 31-03-15. The total expenditure incurred upto March-2014 is 511.08 crores. The amount of pending bill is Rs.43.23 crores.

Package-III

The Government has accepted the report of the committee constituted under the chairmanship of Sri. D.N.Desai for the problems arising out of the construction of tunnel vide Government order dated: 13-6-2012. and directed to take up the tunnel work. The tunnel excavation work is under progress. In shaft and exit portion of tunnel. Extension of time has been granted up to 21-3-2016. The total expenditure incurred upto March-2014 – 2.61 Crores.

Chitradurga Branch Canal :

The alignment of Chitradurga Branch Canal from Km 0.00 to 30.00 Km is approved on 23-05-2013. Further 8, 9, 17, 18, 19Km works are included in one package and tenders were invited, and the tenders received bid was placed before Tender scrutiny committee and the approval was obtained. Financial bid is to be placed before tender scrutiny committee.

Estimates of Chitradurga branch canal from 21 Km to 30Km are under scrutiny at Zonal Office, and the estimates are to be placed before ERC for clearance.

Buildings:

The Construction of Zonal Office Complex at Chitradurga is completed and is under usage, Expenditure of the work is Rs. 5.42 crores. The residential

186

quarters at Chitradurga is completed and are under usage. The total expenditure upto March-14 is 4.68 Crores.

At Muttinakoppa office building and residential quarters are under construction. The total expenditure upto March-14 is 1.310 crores. At Challakere the office building and residential quarters are completed at the cost of 2.61 crores and are under usage. The total expenditure upto March- 14 is 2.858 crores.

Land Acquisition:

Out of Private Land required for Package-1 works, 4(1) notification issued for an area of 100A-23G and 96A-28G for which 6(1) notification is issued for out of Private Land required for Package-2 works 4(1) notification issued for 1360A-39G and 6(1) notification is issued for 1040A-14G.

Package-3 works:

4(1) notification is issued for 151A-14G and 6(1) notification is issued for 150A-34.08G. The proposal of land acquired for Chitradurga Branch Canal is submitted to Revenue Department. Revenue Secretary to Government of Karnataka has revised the land rates for Private Land coming under Package-1, 2 & 3 on 21-03-2012 and has refixed the rates as below.

Dry land/acre-3.50 lakhs Wetland/acre-5.50 lakhs. Garden/acre-12.00 lakhs.

As per the request of land acquisition Officers an amount of 6.811 crores is deposited under package-1 and Rs. 49.29 crores is deposited under package-2 thus an amount of 56.13 crores is deposited An amount of Rs. 26.23 crores has been disbursed so far as compensation. For bugar hokum land compensatatory amount 3.74 crores are disbursed under package-2 works.

Acquisition of Forest Land:

364.50 ha forest land is requireds for Upper Bhadra Project

Package-I 106.12 Ha Package-II 88.50 Ha CBC 171.59 Ha 364.50 Ha

For acquisition forest land, proposal of package-1, 2 & CBC is submitted to Principal Chief Conservative of Forest on date 27-5-13, 19-9-2013 and 19- 10-2013 respectively. These proposals are only yet to be submitted to Central Forest Department.

187

An extent 364.50 Ha of Revenue Land is identified in Varavu Kaval as against the extent of forest land to be diverted for Upper Bhadra Project for handing over this land to Forest Department, Government has given approved on 26-2-2013.

188

Package-I works

Package – II Works :

189

190

12.7.2 Yettinahole Project:

 Providing drinking water to Kolar Chikkabalapur,Ramanagar,Bangalore Rural districts etc and covers other districts namely Tumkur,Chickkamaglur,and Hassan coming en-route of gravity canal.

 Rejunuvating the ground water by filling up of MI tanks of Palar and Pennar region covering the districts of Kolar Chikkaballapur,Bangalore rural and Tumkur by creating basic infrastructure in this region.

 Augumenting of water partially to Tippagondanahalli reservoir and Hasaragatta MI tanks.

In this Project it is envisaged to lift the flood water available during khariff season in the months of June to November from the west flowing rivers of Yettinahole, Kadumanehole, Kerehole Hongadahole is supplied to the above said areas without affecting the requirement of downstream region.

 It is proposed to construct 8 no small barrages across the streams located upstream of Western Ghats near Sakleshpura and convey the water to eastern region by lift the water without creating submergence and without harming the ecology. Water is lifted and conveyed to eastern region.

 Under this project, constructions of barrages across the streams are as below.

Barrage-1: Yettinahole Barrage-5: Kadumanehole-2 Barrage-2: Yettinahole Barrage-6: Kerihole (Tributory-1)

Barrage-3: Yettinahole Barrage-7: Hongadahalla (Tributory-2) Barrage-4: Barrage-8: Yettinahole down stream Kadumanehole-1

 The water lifted from the barrages is delivered to delivery chamber near Haravanahalli through pipes burried under ground and carried parallel to the existing railway line and roads duly taking precaution to minimize the land acquisition cost.

 It is proposed to construct a gravity Canal for 27KM on the ridge separating Cauvery, Krishna and Pennar Valley from the above mentioned Delivery Chamber.

 In the midst of this Canal alignment a Canal of 12.50KM comes in the Upper reaches and after this it is proposed to construct Gravity Canal near Byragonanahalli village in Kortagere Taluk and allow the water to the reservoir with capacity of 5.78TMC.

191

 From this Canal it is proposed to construct a Canal on the left side at KM 231.70 and supply drinking water to Koratgere and Madugiri in Tumkur Districts and also filling minor irrigation tanks in Pennar Valley to an extent of 50%.  From this Canal it is proposed to construct Gravity Canal to the right side at KM 248.40 and supply water to Thippagondanahalli Reservoir in Ramanagar District for drinking water purpose.

 After this from KM 274.00 the Canal runs for 75 KM and it is proposed to supply water to Gowribidanur Taluk to fill MI tanks upto 50% capacity.

 The water from Byragondanahalli reservoir the water is lifted upto about 128 KM through a rising Main of 45 Km and water is supplied to Palar Basin near Kundaru village in Devanahalli Taluk and water is taken through Gravity Canal and filled to MI tanks upto 50% capacity to recharge the ground water and drinking water purpose.

 Water lifted by rising main and is supplied to Nelamangala , Hosakote, Doddaballapura and Devanahalli Taluks coming under Bangalore Rural District.

 It is envisaged to fill 198 MI tanks coming under Chikkaballapur district and 139 MI tanks in Kolar District and also MI tanks coming in Northern Pennar Valley at Bangalore rural District to a capacity of 50% from this project.

Details of Administrative Approval to the Project

 The Government of Karnataka in its order No:WRD/203/VEBYAE/2012 Bangalore dt:13.07.2012 has accorded administrative approval for division of 24.01 TMC of flood work from the west flowing rivers to East Sakleshpura for Rs.8323.50 crores.

 The Technical Sub-Comities (TSC) of KNNL has given clearance to take up works amounts to Rs.3269.50 Crores on EPC/Turnkey basis for stage-one works.

 The stage two works (conveyance component) i.e. for the work from Haravanahalli delivery chamber approval is accorded to the line estimated amount of Rs.5054.000 Crores and the same is proposed to taken up after the preparation Detailed Project Report are approval to the same is received from government.

 In accordance with the orders of the government stage-I works is up to Haravana halli delivery chamber are taken up on EPC/Turnkey basis by divides from in 5 suitable packages for Rs.2660.83 Crores and the agencies have been fixed.

 Approval to the revised detailed Project report amount to Rs.12912.36 crores has also been accorded by Government order NO/WRD/203/VEBYAE/2012 Bangalore dt:17.02.2014.

192

Financial Progress:

The foundation stone for the works was laid by Hon’ble Chief minister of Karnataka state on 3-3-2014. Agreement has been executed and initial works are under progress.

A grant of Rs.4500 lakhs has been provided for the year 2013-14 and an expenditure of 169.80 lakhs is incurred upto March-2014 and the cumulative expenditure is Rs.267.30 lakhs.

193

Yettinahole Inauguration Function:

********

194

PROJECTS UNDER

CAUVERY NEERAVARI NIGAM LIMITED

195

13. CAUVERY NEERAVARI NIGAMA LIMITED

The Cauvery Neeravari Nigama Limited (CNNL) is established by the Government of Karnataka in 03.06.2003 under Company Act 1956 as a special purpose to accelerate the implimentation of Cauvery Basin Projects in Karnataka. The Cauvery basin in Karnataka is 34,273 Sq.Kms which constitutes about 17.99% of the geographical area of 1,91,791Sq.Km in Karnataka Major Rivers flowing in this basin are Harangi (50 KM), Hemavathy (245 KM), Lakshmanatheertha (131 KM), Kabini (230 KM), (221 KM), Suvarnvathi (88 KM), Arkavathy (161 KM) and the main river Cauvery (381 KM). The Cauvery Basin has spread in 11 districts. Main Objective of the CNNL are: to complete the works of the ongoing Irrigation projects including Lift Irrigation works, and such works of Minor Irrigation and CADA (Command Area Development Authority). Also to maintain, operate, improve or modernize the irrigation projects including Lift Irrigation works and such works of Minor Irrigation and CADA in the Cauvery Basin entrusted to it by the Government of Karnataka. Three zones viz., Irrigation (S) zone, Mysore, Hemavathy Canal Zone, Tumkur and Hemavathy Project Zone, Gorur are coming under the jurisdiction of CNNL. The details of on going projects coming under each zone are as below: Programme for Sl. Name of Zone Name of the Project Status completing the No project Irrigation (S) 1 D.D. Urs Canal Physically Completed zone, Mysore Flow irrigation component 2 Kabini Project physically completed 3 Harangi Project Physically completed 4 Taraka Project Physically completed 5 Arkavathy Physically completed 6 Chiklihole Project Physically completed 7 Uduthorehalla Project Physically Completed 8 Iggalur Project Physically Completed 9 Manchanabele Project Physically completed 10 K.R.S. Modernization Physically completed 11 Nanjapura LIS Physically Completed 12 Bannahallyhundi LIS Physically completed Hemavathy Canal Zone, 1 Hemavathy Canal Project On-going 2014-15 Tumkur Hemavathy 1 Hemavathy Project On-going 2014-15 Project Zone, 2 Yagachi Project On-going 2014-15 Gorur 3 Huchanakoppalu LIS Nearing Completion 4 Kamasamudra LIS Physically Completed 5 Kachenahally LIS On-going 2015-16 6 Votehole Project Physically Completed Ongoing projects–4: Nearing completion-1: Physically completed projects– 14.

196

13.1 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION(S), ZONE, MYSORE.

13.1.1. D. DEVARAJA URS CANAL

D. Devaraja Urs Canal project envisages construction of 126 km long Right Bank Canal from Krishnarajasagar reservoir. Administrative approval has been accorded to the Original estimate amounting to Rs.18.50 Crores. vide G.O. No.PWD/145/MKS/77, dtd: 23.04.1979. The work was started during 1979. Administrative approval has been accorded to the revised estimate amounting to Rs.58.10 Crores. vide G.O. No.PWD/145/MMR/86 dtd: 08.08.1988. The planned utilization from this project is to create an ultimate potential of 80000 acres (32,375 ha.) with a cropping area of Khariff semidry and Rabi semidry 59,500 acres totalling to 1,39,500 acres. The taluks benefited by this project are Nanjangud, T. Narasipur& H.D. Kote of Mysore district and Srirangapatna taluk of Mandya district. The main canal work have been completed upto 126 km and the works of distributaries are also completed in all respects. The water allowed upto the tail end on trial basis. 249 cross drainage works and lining to main & distributary canals are completed. The project is physically completed. The total irrigation potential created is 78432 acres (31741 ha.) as against the contemplated potential of 80000 acres (32375 ha.) A balance potential of 1568 acres (634 ha.) could not be created due to Urbanisation, Industrial development and high mounds.

197

During 2013-14, a grant of Rs.7.73 Crores has been allocated. Upto end of March-2014 an expenditure of Rs.16.92 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.532.60 Crores.

3.1.2. KABINI RESERVOIR PROJECT

The project envisages the construction of a composite dam across near Beechanahally village in H.D. Kote Taluk of Mysore District. Administrative approval has been accorded to the Original estimate amounting to Rs.3.20 Crores. vide G.O. No. PWD/1/KRS/57 dtd: 02.02.1959. The work was started during 1960. Administrative approval has been accorded to the revised estimate amounting to Rs.390.00 Crores vide G.O. No.PWD/22/MMR/86 dtd: 24.02.1986 The project comprises of both flow and lift irrigation schemes. The planned utilization is 59.65 TMC which comprises of 32.350 TMC in flow and 27.300 TMC in lift to create the ultimate potential of 233347 acres (94434 ha.), which comprises of 110000 acres (44516 ha.) in flow and 123347 acres (49918 ha.) in Lift. The taluks benefited by this project are H.D.Kote, Nanjangudu and T. Narasipura of Mysore District and Gundlupet, Chamarajanagara, Yalandhuru and Kollegala of Chamarajanagara District. FLOW: The Dam and allied works are completed. The works of earth work excavation and CD works for the entire length of 26 Km of LBC are completed. The works of earth work excavation and CD works for the entire length of 202 Km of RBC are completed. The CC lining works of RBC from Ch: 0.00 to 100.00 Km is almost completed and the CC lining works from 100.00 to 130.00 Km are in progress. Also, the CC lining works from 130.00 to 140.00 Km are completed. The balance works are programmed to be completed during 2014-15. 198

The total irrigation potential created under flow from this project since inception to the end of March 2009 is 109273 acres (44222 ha.) as against the contemplated potential of 110000 acres (44516 ha.) under flow. A balance potential of 727 acres (294 ha.) could not be created due to high mounds and village limits. During 2013-14, a grant of Rs90.56 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs 70.60 Crores is incurred. The cumulative expenditure incurred since inception up to end of March 2014 is Rs896.46 Crores.

3.1.3. HARANGI PROJECT

The project envisages the construction of a composite dam across Harangi River near Hulugunda village in Somawarpet Taluk of Kodagu District. Administrative approval has been accorded to the Original estimate amounting to Rs.11.00 Crores. vide G.O. No.PWD/02/GHK/63 dtd: 14.11.1969. The work was started during 1964. Administrative approval has been accorded to the re-revised estimate amounting to Rs.545.00 Crores. vide G.O.No.PWD/14/MMH/2007 dtd: 30.07.2007. The project comprises of both flow and lift irrigation schemes. The planned utilization is 18.00 TMC which includes of 11.38 TMC in flow and 6.62 TMC in lift. The details of ultimate potential to be created are as below. Ultimate Potential Length of Canal Type Canals to be created in Km. in acres (ha.) Flow 1 LBC 153.00 29472 (11927) 2 RBC 138.50 71323 (28863) 3 MI tanks - 2600 (1053) Lift 199

1 Somwarapet LIS 10.00 1500 (607) 2 Piriyapatna LIS 50.00 30000 (12141) Total 134895 (54591)

The taluks benefited by this project are Hunsur, K.R. Nagara,Periyapatna of Mysore District, Arkalgudu of Hassan District and Somawarpet of Kodagu District.

FLOW IRRIGATION: The Dam and allied works are completed. The works of earth work excavation and CD works for entire length of 153 Km of LBC and the entire length of 138.5 Km of RBC are completed. The lining works of Harangi Left Bank Canal for a length of 12.26 Km from 14.740 to 27.00 Km is taken up. Out of this, the lining works for a length of 11.36 Km are completed and the works of balance 0.90 Km are in progress. The works of improvements to 20 distributaries from 1 to 18 of Harangi Left Bank Canal for a Length of 41.145km are taken up in 6 packages. Out of this, the improvement works for a length of 31.256km are completed. The balance improvement works for a length of 9.889km are in progress. The works of improvements Harangi Right Bank Canal for a length of 19.73Km from 0.00 to 25.00 Km is taken up. Out of this, improvement works for a length of 14.46km are completed. The balance improvement works for a length of 5.27km are in progress. These balance works are proposed to be completed during 2014-15.

LIFT IRRIGATION SCHEMES: Somawarpete LIS and Piriyapatna LIS arecoming under this project.

1. Somawarpete LIS:

It is proposed to lift 0.800 TMC of water at 12.20 Km of LBC to create a potential of 1500 acres (607 ha.). The head works including 10 Km long canal works are completed and commissioned.

2. Piriyapatna LIS:

It is proposed to lift 324.00 Cusecs of water from Karadilakkanakere tank to create a potential of 30000 acres (12141 ha.). The utilization under this scheme is 5.82 TMC. The head works and allied works are completed. The total length of the canal is 50 Km and the canal works are completed. The works of 38 distributaries are completed.

200

The total irrigation potential created including flow and lift under this project since inception to the end of Mar 2010 is 132248 acres (53520 ha.) as against the contemplated potential of 134895 acres (54591 ha.). The balance potential of 2647 Acres (1079 Ha.) could not be created due to high mounds and village limits. The project is physically completed. During 2013-14 a grant of Rs.25.05 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs.45.58 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.676.33 Crores.

13.1.4. TARAKA PROJECT

The project envisages the construction of a composite dam across Taraka River near Penjahally village in H.D. Kote Taluk of Mysore District. Administrative approval has been accorded to the Original estimate amounting to Rs.1.70 Crores. vide G.O. No.PWD/23/GIP/67 dtd: 12.04.1970. The work was started during 1970. Administrative approval has been accorded to the Revised estimate amounting to Rs.51.00 Crores. vide G.O. No.PWD/36/MMF dtd: 15.04.1996. The planned utilization from this project is 3.20 TMC to create an ultimate potential of 17396 acres (7040 ha.). H.D. Kote taluk of Mysore District is benefited by this project. The Dam and allied works are completed. The earth work excavation and CD works for 50 Km of LBC and 38.50 Km of RBC are completed. The CC lining works of LBC from

201

0.00 to 10.00 Km are completed. The Action has been taken up to implement the lining work from 10.00 to 30.00 km of Left Bank Canal and proposed for completion during 2014-15. To augment the short supplies to the reservoir and to the complete atchkat of the project,lifting of 2.07 TMC water from foreshore of Kabini, through Taraka Lift irrigation Scheme is completed and trail run has been conducted. The total irrigation potential created under this project since inception to the end of March 2009 is 17396 acres (7040 ha.). The project is physically completed. During 2013-14, a grant of Rs.5.13 Crores has been allocated. Upto end of March-2014 an expenditure of Rs.1.37 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.77.66 Crores.

13.1.5. ARKAVATHY PROJECT

The project envisages the construction of a composite dam across Arkavathy River a tributary to River Cauvery near Arobele village in Kanakapura Taluk of Ramanagara District. Administrative approval has been accorded to the Original estimate amounting to Rs.22.25 Crores vide G.O. No.PWD/126/MMK/83 dtd: 27.06.1984. The work was started during 1983-84. The project comprises of both flow and lift irrigation schemes. The total planned utilization from flow and lift is 3.10 TMC.The planned potential to be created is 15400 acres (6232 Ha) which includes 7500 acres (3035 Ha) by Flow and 7900 acres (3197 Ha) by Lift. Kanakapura taluk of Ramanagara District is benefited by this project.

202

FLOW: The Dam and allied works are completed. The Length of LBC is 23 Km. and of RBC is 22 Km. and the potential to be created is 4500 acres (1821 ha) and 3000 acres (1214 Ha) respectively totalling to 7500 acres (3035 Ha). The works for entire length of 23 Km of LBC and 22 Km of RBCare completed. Potential created is 7490 acres (3031 Ha). It was not possible to create a potential of balance for 10 acres (4 Ha.). LIFT IRRIGATION SCHEMES: Arkavathy LBLC LIS and Arkavathy RBLC LIS are coming under this project. LBLC: It is proposed to lift 32.98 Cusecs of water on the foreshore of the Arkavathy reservoir to create a potential of 3600acres (1457Ha). The total length of LBLC is 21 Km (18.00 Km + 3.00 Km Reverse canal). The Left Bank lift scheme is completed and commissioned. RBLC: It is proposed to lift 39.98 Cusecs of water on the foreshore of the Arkavathy reservoir to provide irrigation facilities to 4300 acres (1740 Ha). But, the atchkat coming under the outlets of the canal from 0.00 to 23.00 Km is 3892 Acres (1575 Ha.). The Right Bank lift scheme is completed and commissioned. The total irrigation potential created under this project since inception to the end of March 2013 is 15384 acres (6226 Ha) as against the total contemplated potential of 15400 acres (6232 Ha). During 2013-14, a grant of Rs.3.60 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs.1.46 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.202.81 Crores.

13.1.6. CHIKLIHOLE PROJECT

203

The project envisages the construction of a composite dam across Chiklihole River, a tributary of River Cauvery near Rangasamudra village in Somawarpet Taluk of Kodagu District. administrative approval has been accorded to the original estimate amounting to Rs.3.40 Crores. vide G.O. No.PWD/25/GIP/71 dtd26.08.1977. The work was started during 1978. Administrative approval has been accorded to the revised estimate amounting to Rs.19.20 Crores. The planned utilization from this project is 0.45 TMC to create an ultimate potential of (2137 acres) 865 ha. Somawarapet taluk of Kodagu District is benefited by this

project. The Dam and allied works are completed. The works of new LBC for a length of 29 Km are completed. The project is physically completed. The total irrigation potential created under this project since inception to the end of March 2007 is 2138 acres (865 ha.). The cumulative expenditure incurred since inception upto end of 3/2007 is Rs. 19.20 Crores. The total irrigation potential created under this project since inception is 2138 acres (865 ha.). The cumulative expenditure incurred since inception is Rs. 19.20 Crores.

13.1.7. UDUTHOREHALLA PROJECT

The project envisages the construction of a composite dam across Uduthorehalla River near Ajjipura village in Kollegal Taluk of Chamarajanagara District. Administrative approval has been accorded to the Original estimate amounting to Rs.7.55 Crores. vide G.O. No.PWD/60/GIP/71 dtd: 30.11.1978. The work was started during 1979. Administrative approval has been accorded to the revised estimate amounting to Rs.32.30 Crores. vide G.O. No.PWD/134/MMK/85 dtd: 25.11.1989.

204

The planned utilization from this project is 1.23 TMC to create an ultimate potential of 16314 acres (6602 ha.). Kollegala taluk of Chamarajanagara District is benefited by this project. The Dam and allied works are completed. The Length of LBC is 10.20 Km. and of RBC is 9.10 Km. and the potential to be created is 6200 acres (2509 ha.) and 10114 acres (4093 ha.) respectively, totalling to 16314 acres (6602 ha.) The works of entire length of LBC and RBC are completed. This project is physically completed. The total irrigation potential created under this project since inception to the end of Mar 2009 is 15352 acres (6213 ha.) as against the contemplated potential of 16314 acres (6602 ha.). A balance potential of 962 acres (389 ha.) has not been created due to hillocks and villages. During 2013-14, a grant of Rs.1.11 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs.1.14 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.231.61 Crores.

13.1.8. IGGALUR BARRAGE PROJECT

The project envisages the construction of a Barrage across Shimsha River near Iggalur village in Channapatna Taluk of Ramanagara District. Administrative approval has been accorded to the Original estimate amounting to Rs.3.42Crores. vide G.O.No.PWD/17/GIP/71 dtd: 06.12.1977. The work was started during 1977. Administrative approval has been accorded to the revised estimate amounting to Rs.10.75Crores vide G.O.No.PWD/33/MMH/86/ dtd: 23.12.1986. The project comprises of both flow and lift irrigation schemes. The planned utilization is 1.80 TMC. The ultimate potential to be created is 10532 acres (4263 ha.) which comprises of 3650 acres (1477 ha.) in flow and 6882 acres (2786 ha.) in Lift. The taluks benefited by this project are Channapatna of Ramanagara District: Maddur, Malavally of Mandya District.

205

FLOW: The Barrage and flow canal works are completed. The Length of LBC is 35 Km. and the works is completed. The potential created is 3650 acres (1477 ha.) LIFT IRRIGATION SCHEMES: 8 No. of LIS schemes are coming under this project. Out of this 5 LIS Viz., Point A, Point C, Point C-2, Hulikere LIS water is lifted from the foreshore and Point D LIS water is lifted from canal to irrigate 6882 acres (2786 ha.). The balance 3 LIS Viz., Point B, LIS and Garkahalli LIS are tank feeding project. The details of 5 LIS used for irrigation pupose are as under: Sl. Ultimate Potential to be Potential created Name of LIS No. created in acres. (ha) in acres. (ha) 1 Point A 2243 (908) 2204 (892) 2 Point C 1255 (508) 1255 (508) 3 Point C-2 1000 (405) 1000 (405) 4 Point D 1890 (765) 1890 (765) 5 Hulikere 494 (200) 371 (150) Total 6882 (2786) 6719 (2719)

LIS Projects: Point A, C, C-2, D and Hullikere LIS are completed. Potential Created is 6719 acres (2719 ha.). The total irrigation potential created including flow and lift from this project since inception to the end of Mar-09 is 10368 acres (4196 ha.). The balance potential of 163 acres (67 ha.) could not be created due to high mounds and village limits. This project is physically completed. During 2013-14, a grant of Rs.1.89 Crores has been allocated. Up to end of March - 2014 an expenditure of Rs.1.33 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.89.04 Crores.

13.1.9. MANCHANABELE PROJECT

The project envisages the construction of a composite dam across Arkavathy River near Manchanabele village in Magadi Taluk of Ramanagara District. Administrative approval has been accorded to the Original estimate amounting to Rs.2.37 Crores vide G.O.No. PWD/12/GIP/64 dated: 30.09.1969. The work was started during 1969. Administrative approval has been accorded to the re-revised estimate amounting to Rs.18.50 Crores vide G.O.No. PWD/14/MMK, dated: 25.08.86. 206

The planned utilization from this project is 0.80 TMC to create an ultimate potential of 6012 acres (2433 ha.). The taluks benefited by this project are Magadi and Ramanagara of Ramanagara District. The Dam and allied works are completed. The Length of LBC is 35.00 Km. and of RBC is 36.00 Km. and the potential to be created from these canals are 2768 acres (1120 ha.) and 3244 acres (1313 ha.) respectively. The project is physically completed. The works for the entire length of LBC and RBC are completed. The project is physically completed. The total irrigation potential created under this project since inception to the end of March 2009 is 6009 acres (2432 ha.). During 2013-14, a grant of Rs.1.74 Crores has been allocated. Upto end of March-2014 an expenditure of Rs.1.95 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.94.48 Crores.

207

13.1.10 KRS MODERNISATION

The Krishnarajasagar Reservoir is constructed across the River Cauvery near Kannambaadi village in Srirangapattana Taluk of Mandya District, with Canals on both the flanks for providing irrigation to an extent of 196000 acres (79312 Hectares) of Mandya and Mysore District. The Left Bank High Level Canal, which is named as Vishweshvaraya Canal was originally proposed for providing Irrigation to an extent of 120000 Acres (48,564 Hectares). However, due to various factors like construction of pickup channels, lowering of local mounds in the command area, subsequent extension of certain branch canals etc., there has been considerable increase in the command area of Vishweshvaraya Canal. This has resulted in increased withdrawal in various branches, causing a strain on the canal system. Due to this the supply of water to the atchkat in the tail end reaches was inadequate. The existing canal is carrying higher discharge. Also two major Aqueducts along the canal were not able to carry discharges beyond 67 Cumecs (2366 Cusecs). In order to limit the excess utilisation of water in the atchkat it was programmed to modernize the Vishweshvaraya Canal and also to create fresh atchkat of 5250 Acres (2125 Hectares). Administrative approval has been accorded to the Original estimate amounting to Rs.14.80 Crores. The work was started during 1987. Administrative approval has been accorded to the Revised estimate amounting to Rs.55.00 Crores vide G.O.No. PWD/13/MMG/86, dated: 06.03.1987.

Modernization works are completed. The total additional irrigation potential created under this project since inception to the end of Mar 2009 is 5250acres (2125 Ha.). The project is physically completed.

During 2013-14, a grant of Rs.9.49 Crores has been allocated. Upto end of March-2014 an expenditure of Rs.10.52 Crores is incurred. The cumulative expenditure incurred since inception upto end of March -2014 is Rs.467.98 Crores.

208

13.1.11 NANJAPURA LIFT IRRIGATION SCHEME

This project envisages to lift 119 Cusecs of water from Cauvery River near Nanjapura village in T.Narasipura taluk (Bannur Town) of Mysore District to feed Turuganur Branch of Vishveshwaraia Canal. Administrative approval has been accorded to the Original estimate amounting to Rs.28.40 Crores vide G.O. No.PWD/197/MMK/1996 dtd: 27.05.1997. Technical sanction accorded to the estimate amounting to Rs.31.60 Crores vide CER No. CER No:119/1998-99.The work was started during 1999-2000. The scheme is proposed to supply water to an extent10000 acres (4049 ha.) which comprises of creation of additional atchkat of 8000 acres (3239 ha.) and Suffering atchkat of 2000 acres (810 ha.) under Turuganur Branch Canal. The taluks benefited by this project are T.Narsipura of Mysore District and Mallavali of Mandya District. The scheme is commissioned 01.03.2009 and physically completed. The total irrigation potential created under this project since inception to the end of Mar 2009 is 10000 acres (4049 ha.) as against the contemplated potential of 10000 acres (4049 ha.). During 2013-14, a grant of Rs.2.09 Crores has been allocated. Upto end of March-2014 an expenditure of Rs.2.16 Crores is incurred. The cumulative expenditure incurred since inception upto end of March -2014 is Rs73.34 Crores.

13.1.12 BANNAHALLIHUNDI LIS

209

The project envisages to lift 50 Cusecs of water from Right Bank of Kabini River near Tayur Village in Nanjangudu Taluk of Mysore District. Administrative approval has been accorded to the Original estimate amounting to Rs.16.25 Crores. vide G.O. No.ID 272/MMK/97 dtd: 2.02.2001. The work was started during July 2006. The ultimate potential to be created is 4384 acres (1774 ha.). The taluks benefited by this project are T.Narasipura of Mysore District and Chamarajanagara of Chamarajanagara District. The scheme is physically completed. The total irrigation potential created under this project since inception to the end of Mar 2009 is 4384 acres (1774 ha.) as against the contemplated potential of 4384 acres (1774 ha.). During 2013-14, a grant of Rs.1.53 Crores has been allocated. Upto end of March-2014 an expenditure of Rs.1.86 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.22.00 Crores.

13.2. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, HEMAVATHY CANAL ZONE, TUMKUR.

13.2.1. HEMAVATHY CANAL ZONE, TUMKUR

Hemavathy Canal Zone, Tumkur, was formed as per Government order No. PWD 11 PCO 87 Bangalore, dated 14-1-1987, for execution of Hemavathy canal works and is functioning since 23-04-1987.This is a part of Hemavathy project. This zone look after the execution of canal works viz., Y-Alignment, Tumkur Branch canal, Nagamangala Branch Canal and Lift irrigation scheme at the exit of Bagur – Navile tunnel and providing water supply to Tumkur and Tiptur town from Hemavathy left Bank Canal. Administrative approval has been accorded to the Original estimate of Hemavathy Project amounting to Rs.16.30 Crores. vide G.O. No.PWD/1/GKH/63 dtd: 18.09.1967 for Hemavathy Project. The work was started during 1967. Administrative approval has been accorded to the revised estimate amounting to Rs.3877.00 Crores. vide G.O. No.WRD/46/NHP/2007 dtd: 30.07.2007. This amount comprises of Rs.1751.00 crores towards Hemavathy Project Zone- Gorur and Rs. 2126.00 crores towards Hemavathy Canal Zone, Tumkur.

The canal details are as under. Ultimate Planned Total Sl. Potential to utilization Canal Details length in Taluks Benefited No. be created in in TMC / Km. acres (Ha) Remarks a) ‘Y’ -Alignment. 5.50 Km - - b) Tumkur Branch 240.00 236990 18.07 Turuvekere, Tiptur, Gubbi, Canal. Km (95,909) Tumkur, Kunigal of Tumkur District c) Nagamangala 78.325 146994 11.19 Turuvekere, Tiptur, Gubbi, Branch Canal. Km (59,488) Kunigal of Tumkur District & Nagamangala in Mandya District d) Lift Irrigation 13.97 5828 0.29 C.R. , in Hassan Scheme at the exit of (RBC) (2,358) District and Tiptur taluk in Bagur – Navile 16.25 Tumkur District Tunnel (LBC) e) Providing Water - - 1.44.

210

Supply to Tumkur &Tiptur Town. Total 389812 30.99 (1,57,755)

FLOW: Y- alignment The total length of Y alignment is 5.50 Km. Earth work and CD works completed. 2.80 Km lining works are completed.Balance lining is to be done. Tumkur Branch Canal (0-240 Km): The total Length of Tumkur Branch Canal is 240 Km and the potential to be created is 236990 acres (95909 Ha). Out of this, the canal alignment has been approved upto 228 Km The earth work excavation, CD works & lining work are almost completed upto 214.00 km The works of the canal from 215.00 to 228.00 Km are in various stages of progress. The water has been allowed in the canal up to 187 Km. The balance length from 229 to 240.00 Km is treated as tail end distributory No.31. The tender is in process. 44 Distributaries are coming under TBC. Out of this, the earth work excavation and CD works for 42 distributaries are almost completed. The lining works are in different stages of progress. Action has been taken up to implement the works of remaining tail end 2 distributaries (dy no 30 & 31).It is proposed to complete the works during 2014-15. NAGAMANGALA BRANCH CANAL (0 TO 78.325 Km): The total Length of Nagamangala Branch Canal is 78.325 Km and the potential to be created is 146994 acres (59488 ha). The earth work excavation and CD works of the main canal are almost completed. The lining works of main canal upto75 Km is completed. The lining works in remaining Kms from 76 to 78 are in various stages of progress. The water has been allowed in the canal upto 72 Km. 22 Distributaries are coming under NBC. Out of this, the works of distributary from 1 to 20 are completed except lining work. The works of remaining 2 distributaries are in various stages of progress. LIFT IRRIGATION SCHEME AT EXIT OF BAGUR – NAVILE TUNNEL: It is proposed to lift 0.29/0.345 TMC of water to create a potential of 5828 acres (2358 ha.) from Y- alignment canal at exit of Bagur- Navile tunnel near Navile village in C.R. Patna Taluk of Hassan District. The Taluks benefited are Tiptur of Tumkur district and C.R. Patna of Hassan District. The work of raising main, distribution chamber and jack well cum pump house are completed and this scheme has been commissioned during February – 2004. The total length of LBC is 13.97 Km and the works for the entire length is completed. The total length of RBC is 16.25 Km. Out of this, the works of the canal up to 9.00 Km are completed and the works of the canal from Km.10.00 to 16.25 are in progress. The irrigation potential created during 2013-14 is 2,723 Ha. The total irrigation potential created including flow and lift under this project since inception to the end of March 2014 is 3,01,114 acres (1,21,859 ha.) as against the contemplated potential of 3,89,812 acres (1,57,755 ha.). The project is proposed for completion during 2014-15. During 2013-14, a grant of Rs.86.00 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs.74.19 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.1551.17 Crores.

211

13.3 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, HEMAVATHY CANAL ZONE, TUMKUR.

13.3.1 HEMAVATHY PROJECT – GORUR

The project envisages the construction of a composite dam across Hemavathy River near Gorur village in Hassan taluk of Hassan District. Administrative approval has been accorded to the original estimate of Hemavathy project amounting to Rs.16.30 Crores vide G.O. No.PWD/1/GKH/63 Dated: 18.09.1967. The work was started during 1967. Administrative approval has been accorded to the revised estimate amounting to Rs.3877.00 Crores vide G.O. No.WRD/46/NHP/2007 Dated: 30.07.2007. This amount comprises of Rs.1751.00 Crores towards Hemavathy Project Zone, Gorur and Rs. 2126.00 Crores towards Hemavathy Canal Zone, Tumkur. The planned utilization from this project is 56.67 TMC The ultimate potential to be created under this project are 310943 acres (125837 ha.) which comprises of 271000 acres (109672 ha.) under flow and 39743 acres (16165 ha.) under lift. The taluks benefited by this project are Hassan, Alur, Arkalagud, Holenarsipura, Channarayapatna of Hassan District: Mandya, K.R.Pet, Pandavapura, Nagamangala of Mandya District: K.R.Nagara of Mysore District and Somwarapete of Kodagu District. The Dam and allied works are completed. The Details of Canals coming under this project are as below. Atchkat in Acres Sl. No. Name of the Canal Length (Hectares) 1 Hemavathy Left Bank Canal 214 Km. 195000 (78,915) 2 Hemavathy Right Bank Canal 91 Km (Full length) 20000 (8,094) 3 Hemavathy Right Bank High Level Canal 106 Km (Full length) 56000 (22,663) Sub-Total 2,71,000 (1,09,672) 4 LIS Schemes - 39,943 (16,179) Total - 3,10,943 (1,25,837)

212

PRESENT STAGE:- Out of 214 Km of Left Bank Canal, Earthwork excavation & C.D. works upto 212 Km are completed. Works of all 72 distributaries are completed. Balance lining works are in progress. Out of 91 Km of Right Bank Canal, Earthwork excavation & C.D. works upto 91 km are completed. Works of all 57 distributaries are completed Balance lining works are in progress. Out of 96.70 Km of Right Bank High level Canal, the earthwork excavation, C.D. works and distributaries to a length 96.00 km are completed. Lining works for bed and sides upto a length of 80 km are completed. Works of all 41 distributaries are completed Balance lining works are in progress. Out of the 14 LIS, 8 Lift Irrigation Schemes are completed. They are Ganjigere, Ramenahalli, , Marve, Adikebommanahalli, Kattepura, Hallimysore and Bagur Navile approach. LIS at the exit of Bagur-Navile tunnel has been taken up under Hemavathy Canal Zone-Tumkur and commissioned. Except Kendinne, Maniganahalli and Janardhanahalli LIS, the works of Kyatanahalli and Hosapatna LIS are in different stages of progress. The total irrigation potential created to the end of March 2014 is 3,11,714 acres (1,26,149 ha.) from flow and lift as against the contemplated potential of 3,10,943 acres (1,25,837 ha.). The project is proposed for completion during 2014-15. During 2013-14, a grant of Rs.49.56 has been allocated. for taking up the works of Hemavathy Project under Hemavathy Canal Zone. Upto end of March-2014 an expenditure of Rs.72.66 )is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs1814.97.

13.3.2. YAGACHI PROJECT

Aqueduct

Aqueduct Agile tunnel The project envisages the construction of a composite dam across Yagachi River a tributary of Hemavathy near Chikkabyadagere village in Belur Taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.35.38 Crores vide G.O.No.PWD/91/NHP/83, Dated: 27.06.1984. The work was started during 1984-85. Administrative approval has been accorded to the revised estimate amounting to Rs.440.00 Crores vide G.O. No.WRD/40/NHP/2007 Dated: 30.07.2007. 213

The planned utilisation from this project is 5.74 TMC to create an ultimate potential of 37000 acres (14973 ha.).

The details of canals coming under this project are as under: Potential to be Sl. No. Name of the Canal Length in Km created in acres(Ha) 1 Yagachi Left Bank Canal 100 29085 (11832) 2 Mosale Branch Canal 10 2500 (950) 3 Kamasamudra Branch Canal 35 5415 (2191) Sub Total 37000 (14973) 4 Kyatanahalli LIS 5685 (2301) Total 42685 (17274) The taluks benefited by this project are Hassan, Belur and Alur of Hassan District. Flow: The Dam and allied works are completed The length of YLBC is 100.00 Km.The Earth work excavation and CD works of the canal from 0.00 to 100.00 Km are completed. The works of aqueduct of 1st, 2nd and 3rd reaches from Ch: 60.54 to 63.56 Km of the canal are completed. The lining works of the canal upto 50.00 Km excluding 2,3,4,5,7,8,13,14,15,16 & 24th Km are completed. Out of 83 Distributaries, the works of 82 distributaries are completed and work of remaining distributary is in progress. The Agile tunnel work at Ch: 75.40 Km is completed. At the exit of Agile tunnel, the canal branches into Mosale & Kamasamudra canals. The length of the Mosale Branch Canal is 10 Km and the works are nearing completion. The length of the Kamasamudra branch canal is 35 Km, out of this the works of the canal from0.00 to 5.00 Km are in progress.Balance works are proposed to be completed during 2014-15

Kyatanahalli LIS it is proposed to lift 0.464 TMC of water from Yagachi Left Bank Canal at Ch 33.133 Km in two stages to provide irrigation facilities to 5685 acres (2301 ha.) in Hassan taluk. This total atchkat comprises of 1920 acres (777 Ha.) from 1st stage and 3765 acres (1524 Ha.) from 2nd stage. 1st Stage: Head works, jackwell and pump house works completed. Electro mechanical, rising main and allied works are also completed. The work of providing power supply line is completed. The works of the main canal of length 2.20 Km is completed and distributary network is in progress. 2nd Stage: Administrative approval has been accorded for an estimate comprising of sumpwell, pump house, rising main, cistern, machineries, electrification and earth work excavation, CD works for the canal from 0.00 to 6.235 Km amounting to Rs.8.30 Crores. The irrigation potential created during 2013-14 is 750 Ha. The irrigation potential created under this project since inception to the end of March-2014 is 31,251 acres (12,647 Ha) as against the total contemplated potential of 42,685 acres (17,274 Ha).The project is proposed for completion during 2014-15 During 2013-14 a grant of Rs.39.39 Crores has been allocated. Upto end of March- 2014 and expenditure of Rs.15.98 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.448.85 Crores.

214

13.3.3. HUCHANAKOPPALU LIS

The project envisages to lift 0.936 TMC of water in II stages from Hemavathy River near Huchanakoppalu Village in Holenarasipura taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.6.90 Crores vide G.O. No.LIS/86 dtd: 14.07.1986. The work was started during 1985-86. Administrative approval has been accorded to the revised estimate amounting to Rs.50.00 Crores vide G.O. No.WRD/38/NHP/2007 dtd: 30.07.2007. The ultimate potential to be created is 8305 acres (3361 ha.) which comprises of 3785 acres (1532 ha.) from 1st stage and 4520 acres (1829 ha.) from IInd stage. The taluks benefited by this project are Holenarasipura and Arkalgudu taluk of Hassan District. The works of Stage I are completed and commissioned. Stage-II - The Canal works and head works are completed. The balance canal works are nearing completion The total irrigation potential created to the end March 2014 since inception is 8305acres (3361 ha.) as against the contemplated potential of 8305 acres (3361 ha.) During 2013-14 a grant of Rs.2.50 Crores has been allocated. Upto end of March- 2014 and expenditure of Rs.1.89 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.56.44Crores.

13.3.4. KAMASAMUDRA LIS The project envisages to lift 1.451 TMC of water in III stages from Hemavathy River near Kamasamudra Village in Holenarasipura taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.0.995 Crores. vide G.O. No.PWD/180/LIS/84 dtd: 12.06.1984. The work was started during 1984-85. Administrative approval has been accorded to the revised estimate amounting to Rs.70.00 Crores. vide G.O. No.WRD/39/NHP/2007 dtd: 30.07.2007. Approval accorded with a condition to complete I & II stage LIS on priority and to take up III stage LIS depending on the availability of water. The ultimate potential to be created is 12670 acres (5128 ha.) which comprises of 2450 acres (992 ha.) from Iststage, 7220 acres (2922 ha.) from IInd stage and 3000 acres (1214 ha.) from III stage. The taluks benefited by this project are Hassan and Holenarasipura taluks of Hassan District. The details of the Canal system are as under. Sl. Length of Canal in Atchkat Stage Name of the Canal No Km. in acres (ha.) 1 1st stage LBC 14.20 1820 (737) RBC 7.00 630 (255) 2 2nd Stage Malali Branch Canal 54.00 5220 (2113) Nagenahalli Branch Canal 12.40 2000 (809) 3 3rd stage Heragu Canal &RBC 11.00 3000 (1214) Total 12670 (5128) The works of stage - I and II are completed and commissioned. The Canal works of Malali and Nagenahalli Branch Canal are nearing completion. The total irrigation potential created to the end of March 2010 since inception is 9098 acres (3682 ha.) as against the contemplated potential of 1st and 2nd stage of 9670 acres (3914 Ha). 572 acres (232 Ha) of atchkat curtailed due to un economical reasons. The project is physically completed. 215

During 2013-14, a grant of Rs.2.00 Crores has been allocated. Upto end of March - 2014 and expenditure of Rs.2.39 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.62.51 Crores.

13.3.5. KACHENAHALLI LIS

The project envisages to lift 0.73 TMC of water in III stages from Hemavathy River near Kachenahalli Village in Channarayapatna taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.8.90 Crores vide G.O. No.PWD/1/NHP/92 dtd:27.12.1991. The work was started during 1991. Administrative approval has been accorded to the revised estimate amounting to Rs.68.30 Crores vide G.O.No.WRD /35/NHP/99, dated 19.10.2002. Further, Administrative approval has been accorded to the Re-revised estimate amounting to Rs.165.00 Crores vide G.O. No.WRD/37/NHP/2007 dtd: 30.07.2007. Approval accorded with a condition to complete I & II stage LI Schemes on priority and to take up III stage LIS depending on the availability of water. The ultimate potential to be created is 12600 acres (5100 ha.) which comprises of 1390 acres (563 ha.) from I stage, 6610 acres (2675 ha.) from IInd stage and 4600 acres (1862 ha.) from III stage respectively. The taluks benefited by this project are Holenarasipura, Hassan, Arasikere and Channarayapatna of Hassan District. The details of the Canal system are as under. Sl. Length of Atchkat in acres Stage Name of the Canal No Canal in Km. (ha.) 1 1st Stage Samudravalli Main Canal 1.875 1390 (563) 2 2nd Stage Dandiganahalli Branch Canal 22.50 5385 (2179) Bijamaranahalli Branch Canal 8.00 1225 (496) 3 3rd Stage Gandsi Branch Canal 32.00 4600 (1862) Total 12600 (5100) In stage I the head works and Earth Work Excavation of Samudravalli Main Canal is partially completed. Head works, Intake canal, pump & jack well cum pump house works are completed. Rising main and Electro-mechanical works are in progress. The works of distributaries are also in progress. In stage II, Rising main and Electro-mechanical works are in progress. Earth work excavation for Dandiganahalli and Bijamaranahalli branch canals are completed. The irrigation potential created during 2013-14 is 750 Ha. The total irrigation potential created to the end of March 2014 since inception is 2654 acres (1074 ha.) from 1st stage and 2nd stage as against the total contemplated potential of 12,600 Acres (5100 Ha.). The project is proposed for completion during 2014-15. During 2013-14, a grant of Rs.15.60 Crores has been allocated. Up to end of March-2014 an expenditure of Rs.4.90 Crores is incurred. The cumulative expenditure incurred since inception up to end of March -2014 is Rs.64.43 Crores.

13.3.6 VOTEHOLE PROJECT The project envisages the construction of a composite dam across Votehole River near Lakkenahally village in Belur Taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting to Rs.2.05 Crores. vide G.O. No. PWD/GIP/64, dtd: 15.12.1971. The work was started during -1971. Administrative approval has been accorded during 22.02.1996 to the revised estimate amounting to Rs.38.00 Crores. Further,

216

administrative approval has been accorded to the Re-revised estimate amounting to Rs.59.75 Crores vide G.O. No.WRD/47/NHP/2007 dtd: 30.07.2007.

The planned utilization from this project is 2.40 TMC to create an ultimate potential of 18500 acres (7487 ha.). The details of Canals coming under this project are as below. Atchkat Sl. Length in Name of the Canal in Acres No. Km (Hectares) 1 Left Bank Canal 10 500 (202) 2 Right Branch Canal 45 10582 (4283) 3 Nakalgud Branch Canal 15 7418 (3002) Total 18500 (7487)

The taluks benefited by this project are Belur and Alur of Hassan District. The Dam and allied works are completed. The Canal works are also completed. The total irrigation potential created under this project since inception to the end of March 2009 is 18500 acres (7487 ha.). This project is physically completed. During 2013-14, a grant of Rs.0.97 Crores has been allocated. Upto end of March-2014 an expenditure of Rs.0.92 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.64.57 Crores.

217

DRINKING WATER SCHEMES

DRINKING WATER SCHEME TO GULUR-HEBBUR HOBLIES IN TUMKUR DISTRICT

Drinking water scheme to Gulur-Hebbur Hoblies in Tumkur District envisages lifting of 51 cusecs of water in 2 stages from Tumkur Branch Canal of Hemavathy project at Ch: 142.225 Km to feed water to 23 tanks of Gulur Hobli and 29 tanks of Hebbur Hobli totaling to 52 tanks (impounding reservoirs) and to fulfill the demand of providing drinking water to 52 villages of Gulur-Hebbur hoblies in Tumkur District. The Government vide order No. WRD 315 NHP 2003, Bangalore, Dtd: 11.02.2009 has accorded administrative approval to the scheme amounting to Rs.55.00 Crores. The water allowed to 42 tanks on trial run. The works of all the stages are completed and commissioned except for Ramenahally Sub Branch. The project is proposed for completion during 2014-15. During 2013-14, a grant of Rs.5.00 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs.4.00 Crores is incurred. The cumulative expenditure incurred since inception upto the end of March 2014 is Rs.67.41Crores.

DRINKING WATER SCHEME TO HONNAVALLI AND OTHER HOBLIES

Drinking water scheme to Honnavalli and other Hoblies envisages lifting of 27.03 cusecs of water for Tiptur branch and 31.25 cusecs of water for Arasikere Branch independently from Tumkur Branch Canal of Hemavathy project at Ch: 9.9 km. From Tiptur Branch it is proposed to feed water to 18 no of tanks which are coming in series and 48 villages of Tiptur taluk are benefited. Whereas from Arasikere branch it is proposed to feed water to 5 tanks which are coming in series i.e., 3 tanks of Arasikere taluk, one tank of Kadur taluk and one tank of Hosadurga taluk and 38 villages i.e., 20 villages of Arasikere taluk, 8 villages of Kadur Taluk and 10 villages of Hosadurga Taluk are benefited. The Government vide order No. WRD 26 NHP 2008, Bangalore, Dtd: 11.02.2009 has accorded administrative approval to the scheme amounting to Rs.87.20 Crores. . The water is allowed to 24 tanks through Tiptur and Arasikere Branches on trial run. The project is completed. During 2013-14, a grant of Rs. 5.00 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs.0.89Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.76.43 Crores.

FILLING UP OF 20 TANKS OF CHAMARAJANAGAR, NANJANGUD AND GUNDLUPET TALUKS - DRINKING WATER SCHEME.

The scheme envisages lifting of 0.6 TMC of water in 3 stages from Kabini River near Alambur village to fill 20 tanks of Harve, Haradanahalli and Kasabahoblis of Chamarajanagar Taluk, Kavalandehobli of Nanjangud Taluk and adjacent Hoblies of Gundlupet taluk to provide drinking water supply to drought affected areas and to improve ground water table. The Government vide order No. WRD 10 MMK 2009, Bangalore, Dtd: 15.04.2011 has accorded administrative approval to the scheme amounting to Rs.212.00 Crores. The works of 3 stages of this scheme are in progress.The scheme is proposed for completion during 2014-15 During 2013-14, a grant of Rs.70.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.93.23 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs.213.88 Crores.

1

FILLING UP OF KANVA AND OTHER 17 TANKS - DRINKING WATER SCHEME:

The villages of Channapatna Taluk of Ramanagar District are drought prone areas and under ground water level had gone down sufficiently and created problem for even drinking water to villagers. In order to overcome this it is proposed to lift 0.903 TMC of water from Iggalur barrage to fill Kanva Reservoir and other 17 tanks so as to provide drinking water supply and to raise the underground water level. The Government vide order No. WRD 38MMK 2012, Bangalore, Dtd: 10.05.2012 has accorded administrative approval to the scheme amounting to Rs.198.00 Crores. The works are in progress. The project is proposed for completion during 2014-15 During 2013-14, a grant of Rs. 47.00 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs.115.38 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs. 115.55 Crores.

FILLING UP OF VAJRANAKATTE, C.KATTIGENAHALLI AND KOPPA TANKS - DRINKING WATER SCHEME:

The scheme envisages inter linking of Vajranakatte, C.Kattigenahalli &Koppa tanks and feeding 21 Mcft of water to these tanks from Ch: 14600 m. of D-23 of Tumkur Branch Canal. The Government vide order No. WRD 71 NHP 2009, Bangalore, Dtd: 13.06.2011 has accorded administrative approval to the scheme amounting to Rs.2.20 Crores.The works of the scheme are in progress. The scheme is proposed for completion during 2014-15 During 2013-14, a grant of Rs. 1.00 Crore has been allocated No expenditure is incurred upto end of March-2014. The cumulative expenditure incurred since inception upto end of March-2014 is Rs. 0.22 Crores.

FILLING UP OF BELLAVI AND 5 OTHER TANKS - DRINKING WATER SCHEME:

The scheme envisages lifting of 7.50 Mcft of water from Ch: 106.80 Km of Tumkur Branch Canal to feed Bellavi and other 5 tanks to provide drinking water supply to Bellavi and other 5 surrounding villages of Gubbi Taluk ofTumkur District. The Government vide order No. WRD 79 NHP 2010, Bangalore, Dtd: 19.03.2012 has accorded administrative approval to the scheme amounting to Rs.5.70 Crores. The works of the scheme are in progress. The scheme is proposed for completion during 2014-15 During 2013-14, a grant of Rs. 4.00 Crores has been allocated. Upto end of March- 2014 an expenditure of Rs.1.89 Crores is incurred. The cumulative expenditure incurred since inception upto end of March-2014 is Rs. 1.95 Crores.

FILLING UP OF 26 TANKS OF CHIKKANAYAKANAHALLI TALUK - DRINKING WATER SCHEME.

The scheme envisages lifting of 0.80 TMC of water from Tumkur Branch Canal of Hemavathy project to fill 26 tanks comprising filling of 22 tanks through gravity and 4 tanks through lift to provide drinking water supply to drought affected villages of Chikkanayakanhalli taluk. The Government vide order No. WRD 74 NHP 2009, Bangalore, Dtd: 20.07.2011 has accorded administrative approval to the line estimate of the scheme amounting to Rs.102.60 Crores. The works of the scheme are in progress. The scheme proposed for completion during 2014-15.

2

During 2013-14, a grant of Rs.35.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.18.93Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.19.47Crores.

FILLING UP OF DODDAGUNI TANK – DRINKNIG WATER SCHEME

The scheme envisages lifting of 18.20 Mcft of water from Ch: 64.625 Km of Tumkur Branch Canal of Hemavathy project to fill Doddaguni tank in order to provide drinking water supply to Doddaguni and other 14 villages in Gubbi Taluk of Tumkur District. The Government vide order No. WRD 53 NHP 2008, Bangalore, Dtd: 13.06.2011 has accorded administrative approval to the scheme amounting to Rs.3.25 Crores. The works of the scheme are in progress. The scheme proposed for completion during 2013-14. During 2013-14, a grant of Rs.0.80 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.0.98 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.3.88 Crores.

FILLING UP OF 24 TANKS OF HALEBEEDU HOBLI AND 15 TANKS OF HOBLI OF BELUR TALUK – DRINKNIG WATER SCHEME

The scheme envisages lifting of 0.22 TMC of water from Yagachi Left Bank Canal to fill 24 tanks of Halebeedu Hobli and 15 tanks of Madihallihobli under Belur Taluk to provide drinking water supply. The Government vide order No. WRD 43 NHP 2010, Bangalore, Dtd: 05.07.2011 has accorded administrative approval to the scheme amounting to Rs.9.00 Crores. The works of the scheme are in progress. The scheme is proposed for completion during 2014-15 During 2013-14, a grant of Rs.8.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.5.05 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.6.44 Crores.

FILLING UP OF 11 TANKS OF NUGGEHALLI HOBLI OF CHANNARAYAPATNA TALUK – DRINKNIG WATER SCHEME:

The scheme envisages lifting of 171.00 Mcft of water from Bagur Navile approach tunnel of Hemavathy Project to fill 11 tanks and to provide drinking water supply to 15 surrounding villages of Nuggehallihobli of Channarayapatna Taluk. The Government vide order No. WRD 54 NHP 2011, Bangalore, Dtd: 19.03.2012 has accorded administrative approval to the scheme amounting to Rs.17.60 Crores. The works of the scheme are in progress. The scheme is proposed for completion during 2014-15. During 2013-14, a grant of Rs. 8.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.1.28 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs. 1.29 Crores.

FILLING UP OF SHIVASANDRA MUSKONDLI HARENAHALLI KONDLI YEMMEDODDIKATTE AND HANDANAHALLI TANKS OF NITTUR HOBLI OF GUBBI TALUK-DRINKING WATER SCHEME. The scheme envisages lifting of 29.55 Mcft of water from Ch: 77.565 Km of Tumkur Branch Canal to fill tanks of Shivasandra, Muskondli, Harenahalli, Kondli, Yemmedoddikatte and Handanahalli in order to provide drinking water supply to 12 villages in Gubbi Taluk of Tumkur District. The Government vide order No. WRD 38 NHP 2013,

3

Bangalore, Dtd: 28.02.2014 has accorded administrative approval to the scheme amounting to Rs.12.50Crores. The scheme is proposed for completion during 2014-15.

FILLING UP OF 19 TANKS OF GUBBI TALUK-DRINKING WATER SCHEME.

The scheme envisages lifting of 106.04 Mcft of water from Ch: 69.55 Km of Tumkur Branch Canal of Hemavathy project to fill19 tanks to meet the Drinking water needs of 30 villages surrounding Bikkegudda of Kadaba&Kasabahoblies in Gubbi Taluk of Tumkur District. The Government vide order No.WRD 37 NHP 2013, Bangalore, Dated: 28.02.2014 has accorded administrative approval to the scheme amounting to Rs.28.16Crores. The scheme is proposed for completion during 2014-15.

FILLING UP OF HAGALWADI TANKS OF GUBBI TALUK- DRINKING WATER SCHEME:

The scheme envisages lifting of 37.154 Mcft of water from Ch: 83.34 Km of Tumkur Branch Canal of Hemavathy project to fill Hagalawadi tank to meet the Drinking water needs of Hagalavadi and surrounding 35 villages in Gubbi Taluk of Tumkur District. The Government vide order No. WRD 193 NHP 2013, Bangalore, Dated: 28.02.2014 has accorded administrative approval to the scheme amounting to Rs.11.75Crores. The scheme is proposed for completion during 2014-15.

FILLING UP OF TANK OF GUBBI TALUK-DRINKING WATER SCHEME:

The scheme envisages lifting of 26.48 Mcft of water from Ch: 101.380 Km of Tumkur Branch Canal of Hemavathy project to fill Chelur tank to meet the Drinking water needs of 21 villages in Gubbi Taluk of Tumkur District. The Government vide order No.WRD 190 NHP 2013, Bangalore, Dated: 28.02.2014 has accorded administrative approval to the scheme amounting to Rs.3.35 Crores. The scheme is proposed for completion during 2014-15.

FILLING UP OF KODIYALA TANK OF GUBBI TALUK-DRINKING WATER SCHEME:

The scheme envisages lifting of 7.00 Mcft of water from Ch: 98.95 Km of Tumkur Branch Canal of Hemavathy project to fill Kodiyala tank to meet the drinking water needs of Kodiyala and Mugununse villages in Gubbi Taluk of Tumkur District. The Government vide order No.WRD 191 NHP 2013, Bangalore, Dated: 28.02.2014 has accorded administrative approval to the scheme amounting to Rs.2.90 Crores. The scheme is proposed for completion during 2014-15.

FILLING UP OF MATTIKERE, AND SHIVEANEHALLI TANKS OF GUBBI TALUK-DRINKING WATER SCHEME.

The scheme envisages lifting of 9.457 Mcft of water from Ch: 93.850 Km of Tumkur Branch Canal of Hemavathy project to fill Mathikere, Hosahalli and Shivanehalli tanks to meet the drinking water needs of 6 villages in Gubbi Taluk of Tumkur District. The Government vide order No.WRD 192 NHP 2013, Bangalore, Dated: 28.02.2014 has

4

accorded administrative approval to the scheme amounting to Rs.5.31 Crores. The scheme is proposed for completion during 2014-15.

FILLING UP OF HOSAKERE, ALILUGATTA AND ALILUGATTA AMANIKERE TANKS OF GUBBI TALUK-DRINKING WATER SCHEME:

The scheme envisages lifting of 38.68 Mcft of water from Ch: 88.35 Km of Tumkur Branch Canal of Hemavathy project to fill Hosakere, Alilugatta and Alilugatta Amanikere tanks to meet the drinking water needs of 16 villages in Gubbi Taluk of Tumkur District. The Government vide order No.WRD189 NHP 2013, Bangalore, Dated: 28.02.2014 has accorded administrative approval to the scheme amounting to Rs.8.20 Crores. The scheme is proposed for completion during 2014-15.

FILLING UP OF TANKS OF MAGADI TALUK-DRINKING WATER SCHEME:

The scheme envisages lifting of 843.71 Mcft of water from Ch: 192.30 Km of Tumkur Branch Canal of Hemavathy project to fill 83 tanks to meet the drinking water needs of 289 villages of Ramanagara District and Hutridurga hobli in Kunigal taluk of Tumkur District. The Government vide order No.WRD 45 NHP 2013, Bangalore, Dated: 28.02.2014 has accorded administrative approval to the scheme amounting to Rs. 277.50 Crores. The scheme is proposed for completion during 2014-15

FILLING UP OF DABBEGHATTA AND GOTTIGERE TANKS OF TURUVEKERE TALUK-DRINKING WATER SCHEME.

The scheme envisages lifting of 16.40 Mcft of water from Ch: 42.856 Km of Nagamangala Branch Canal of Hemavathy project to fill Dabbeghatta and Gottigere tanks to meet the drinking water needs of 6 villages of Dabbeghatta hobli of Turuvekere Taluk in Tumkur District. Administrative approval accorded to the scheme amounting to Rs.3.00Crores vide Nigama order Dated: 11/02/2013. The scheme is proposed for completion during 2014-15

FILLING UP OF KANATHUR AND HABAKANAHALLI TANKS OF TURUVEKERE TALUK-DRINKING WATER SCHEME.

The scheme envisages lifting of 2.85 Mcft of water from 22.75km and 9.90 Mcft of water from Ch: 27.325 Km and Nagamangala Branch Canal of Hemavathy project to fill Habakanahalli and Kanathur tanks respectively to meet the drinking water needs of 10 villages of Dabbeghatta hobli in Turuvekere Taluk of Tumkur District. Administrative approval accorded to the scheme amounting to Rs.1.30Crores vide Nigama order Dated: 11/02/2013. The scheme is proposed for completion during 2014-15

FILLING UP OF 23 TANKS OF MYSORE, NANJANAGUD AND H.D.KOTE TALUKS-CHIKKANANDI DRINKING WATER SCHEME:

The scheme envisages lifting of 505.00 Mcft of water from kabini river near Bidaregudu to fill 23 tanks to meet the drinking water needs of 27 villages of Mysore, Nanjanagudu and H.D.Kote Taluk of Mysore District. The Government vide order No.WRD 4 MMK 2014, Bangalore, Dated: 19.02.2014 has accorded administrative approval to the scheme amounting to Rs.45.50 Crores. The scheme is proposed for completion during 2014- 15.

5

FILLING UP OF 12 TANKS OF NANJANAGUD AND GUNDLUPET TALUKS- DRINKING WATER SCHEME:

The scheme envisages lifting of 95.00Mcft of water from kabini river near Gandhigrama to fill 12 tanks to meet the drinking water needs of 30 villages of Nanjanagud Taluk of Mysore District and Gundlupet Taluk of Chamarajanagara District. The Government vide order No.WRD 171 MMK 2013, Bangalore, Dated: 29.01.2014 has accorded administrative approval to the scheme amounting to Rs.67.50 Crores. The scheme is proposed for completion during 2014-15.

FILLING UP OF 88 TANKS OF ARAKALAGUD TALUK-DRINKING WATER SCHEME:

The scheme envisages lifting of 87.10 Mcft of water from Hemavathy river near Ganganalu to fill 88 tanks to meet the drinking water needs of Hebbale, Ganganalu Ganjalagudu and surrounding 42 villages of Arakalagud Taluk of Hasana District. The Government vide order No.WRD 40 NHP 2013, Bangalore, Dated: 04.03.2014 has accorded administrative approval to the scheme amounting to Rs.28.00 Crores. The scheme is proposed for completion during 2014-15.

MODERNISATION OF ANECUT CANALS

MODERNISATION OF MANDAGERE AND HEMAGIRI ANECUT AND THEIR CANALS

Modernisation of Mandagere Anecut Canals:Mandagere Anecut is constructed accorss river Hemavathy in Mandagere Village, K.R Pet Taluk, Mandya District during 1903. This anecut is in upstream of Cauvery Valley. There are two canals for this anecut. Mandagere Left Bank Canal is 33.50 Km long and 1938 Ha atchkat comes under this canal. Mandagere Right Bank Canal is 47.50 Km long and 4850 Ha atchkat comes under this canal. There is suffering atchkat of 719 Ha in Khariff and 1110 Ha during summer, totalling to 1827 Ha under these canals. The atchkat area is spread out in K.R Pet taluk of Mandya district and K.R Nagar taluk of Mysore district.

Modernisation of Hemagiri Anecut Canal: Hemagiri Anecut is constructed across river Hemavathy in Bandihole Village, K.R Pet Taluk, Mandya District during 1880. This anecut is in upstream of Cauvery Valley. There is one canal for this anecut. Hemagiri Left Bank Canal is 35.85 Km long and 1602 Ha. atchkat comes under this canal in K.R Pet Taluk, Mandya District. There is suffering atchkat of 237 Ha. in Khariff and 584 Ha. during summer, totaling to 821 Ha. under this canal. The Government has accorded administrative approval to the detailed project report for the work of Modernisation of Mandagere and Hemagiri Anecut Canals amounting to Rs.141.00 Crores vide Government Order No. WRD 91 MMK 2009, Bangalore, Dated: 13.04.2011. Modernisation works of Mandagere and Hemagiri Anecut canals are nearing completion.

During 2013-14 a grant of Rs.11.00Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.0.11 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.192.21 Crores

6

MODERNIZATION OF KRISHNARAJA (KATTEPURA) ANECUT AND ITS CANALS:

Krishnaraja anecut is the first anecut constructed across river Cauvery during 1732 near Kattepura village of Arakalgud taluk of Mysore district. This area lies in upper Cauvery basin. This anecut has 2 canals namely Kattepura Left Bank Canal for a length of 40.20 Km with an atchkat of 949 Ha. in Arakalgud taluk of Hassan district and Right Bank Canal for a length of 83.60 Km with an atchkat of 2600 Ha in Arakalgud taluk of Hassan district and K.R. Nagar taluk of Mysore district. There is a suffering atchkat of 944 Ha. The Government vide order No. WRD 63 NHP 2009 Bangalore Dtd: 08.02.2010 has accorded administrative approval to the DPR for the modernization of Krishnaraja (Kattepura) anecut and its canals amounting to Rs.90.00 crores. The works of modernisation of Kattepura Anecut & its Canals are in progress and proposed for completion during 2014-15 During 2013-14, a grant of Rs.25.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.27.23 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.108.80 Crores.

MODERNISATION OF MIRLE AND RAMASAMUDRA ANECUT AND ANECUT CANALS:

Mirle Anecut is constructed across river Cauvery during 1850 near Chunchanakatte village in K.R Nagar Taluk of Mysore District. This area lies in upper Cauvery basin. This anecut is having a Left Bank Canal for an length of 10.60 Km. which is named as Attikatte Canal. With an atchkat of 1942 Ha. in K.R Nagar Taluk of Mysore District. This canal has a branch canal of length 3.5 Km. which is named as KakanaKaluve and 4 seepage canals for a length of 55 Km. There is a suffering atchkat of 40 Ha. Ramasamudra Anecut is constructed across river Cauvery during 1850 near Chunchanakatte village in K.R Nagar Taluk of Mysore District. This area lies in upper Cauvery basin. This anecut is having a Right Bank Canal for a length of 59.20 Km with an atchkat of 2761 Ha. in K.R Nagar Taluk, Mysore District. There is a suffering atchkat of 70 Ha. The Government vide order No. WRD 77, MMK 2009, Bangalore, Dtd: 05-11-2011 has accorded administrative approval to to the DPR for the modernization of Mirle and Ramasamudra Anecut and Anecut Canals amounting to Rs.64.00 Crores. The modernisation works are in progress and proposed for completion during 3014-15 During 2013-14, a grant of Rs.30.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.38.95 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.49.08 Crores.

MODERNISATION OF CHAMARAJA ANECUT AND ITS CANAL Chamaraj Anecut is constructed across river Cauvery during 1885 near Sakkare village of K.R Nagar Taluk of Mysore District. This area lies in upper Cauvery basin. This anecut is having 2 canals namely Left Bank Canal for a length of 39 Km with a 11 branches of 69 Km and have an atchkat of 3995 Ha. in K.R Nagar Taluk of Mysore district. Whereas, Right Bank Canal for a length of 63.00 Km. with 15 branches of 73.65 Km. and have an atchkat of 5275 Ha. in K.R Nagar, Hunsur Taluks of Mysore district. There is a suffering atchkat of 2000 Ha. The Government vide order No. WRD 76 MMK 2009 Bangalore Dtd: 11.01.2012 has accorded administrative approval to the DPR for the modernization of

7

Chamaraja anecut and its canals amounting to Rs.132.00 Crores. The modernisation works are in progress and proposed for completion during 2014-15. During 2013-14, a grant of Rs.70.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.90.06 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.132.43 Crores. MODERNISATION OF MADHAVAMANTRI ANECUT AND ANECUT CANALS:

Madhavamantri anecut is constructed across river Cauvery during 1140 near Talakadu village in T.Narasipura Taluk of Mysore District. This area lies in lower Cauvery basin. This anecut is having a Left Bank Canal for a length of 29.10 Km with an atchkat of 766 Ha comprising of 1590 Ha in T.Narasipura Taluk of Mysore District and 766 Ha. in Malavalli Taluk of Mandya District. There is a suffering atchkat of 550 Ha. The Government vide order No. WRD 53 MMK 2011, Bangalore, Dtd: 18.10.2011 has accorded administrative approval to the DPR for the modernization of Madhavamantri Anecut and Anecut Canals amounting to Rs.19.00 Crores. The modernisation works are in progress and proposed for completion during 2014-15. During 2013-14, a grant of Rs.12.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.20.43 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.21.86 Crores.

MODERNISATION OF DEVARAYA ANECUT AND ANECUT CANALS:

Devaraya Anecut is constructed across River Cauvery during 17th Century near Majjigere village in Srirangapatna Taluk of Mandya District. This area lies in lower Cauvery basin. This anecut is having a Right Bank Canal for a length of 36.30 Km with an atchkat of 1427 Ha in Srirangapatna Taluk of Mandya District and Mysore Taluk of Mysore District. There is a suffering atchkat of 290 Ha. The Government vide order No. WRD 51 MMK 2011, Bangalore, Dtd: 18.10.2011 has accorded administrative approval to the DPR for the modernization of Devaray Anecut and Anecut Canals amounting to Rs.21.00 Crores. The modernisation works are in progress and proposed for completion during 2014-15. During 2013-14, a grant of Rs. 9.16 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.4.50 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.4.52 Crores.

MODERNISATION OF CHIKKADEVARAYA SAGAR EXTENSION CANAL

ChikkadevarayaSagar Anecut is constructed across River Cauvery on the down stream side of Krishnarajasagar Dam during 17th Century in Srirangapatna Taluk of Mandya District. The CDS Left Bank Canal joints Bannur Tank after traversing a length of 105 Km from the Anecut. The CDS extension canal runs for a length of 26th Km from Bannur Tank and with a carrying capacity of 155 Cusecs of water and have an atchkat of 1997.97 Ha in T.Narasipura Taluk of Mysore District. There is suffering atchkat of 303.38 Ha. The Government vide order No. WRD 41 MMK 2012, Bangalore, Dtd: 13.07.2012 has accorded administrative approval to the DPR for the modernization of ChikkadevarayaSagar extensionCanal amounting to Rs.17.00 Crores. The modernisation works are in progress and proposed for completion during 2014-15. During 2013-14, a grant of Rs. 8.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.0.12 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.0.20 Crores.

8

MODERNISATION OF VIRIJA ANECUT AND ANECUT CANALS:

Virija anecut is constructed during 17th century across right side branch near balamuri kshetra of belagola village river Cauvery near Belagola village in Srirangapattana Taluk of Mandya District. This area lies in Middle Cauvery basin. This anecut has only right bank canal for a length of 93.60 Km with an atchkat of 5360 Ha coming under T.Narsipura and Mysore Taluks of Mysore District. There is a suffering atchkat of 356.50 Ha. The Government vide order No. WRD 35 MMK 2013, Bangalore, Dtd: 19.02.2014 has accorded administrative approval to the DPR for the modernization of Madhavamantri Anecut and Anecut Canals amounting to Rs.83.00 Crores. The Action has been taken up to implement the modernisation works and proposed for completion during 2014-15. During 2013-14, a grant of Rs.30.00 Crores has been allocated. No expenditure incurred up to end of March-2014. MODERNISATION OF RAJAPARMAESHWARI ANECUT AND ANECUT CANALS:

Rajaparmaeshwari anecut is constructed across river Cauvery during the year 1888 near Mahadevapura village in Srirangapattana Taluk of Mandya District. This area lies in Middle Cauvery basin. This anecut has only right bank canal for a length of 37.60 Km with an atchkat of 2219.00Ha comprising of Srirangapattana Taluk of Mandya District and T.Narsipura , Mysore Taluks of Mysore District. The Government vide order No. WRD 41 MMK 2013, Bangalore, Dtd: 20.09.2013 has accorded administrative approval to the DPR for the modernization of Rajaparmaeshwari Anecut and Anecut Canals amounting to Rs.26.50 Crores. The Action has been taken up to implement the modernisation works and proposed for completion during 2014-15. During 2013-14, a grant of Rs.9.78 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.0.03 Crores incurred.

MODERNISATION OF RAMASWAMI ANECUT CANAL:

Ramaswami anecut is constructed across river Cauvery during 19th century near Mandya Koppalu village in Srirangapattana Taluk of Mandya District. This area lies in lower Cauvery basin. This anecut is having a Left Bank Canal for a length of 86.50 Km with an atchkat of 4856 Ha coming under Srirangapattana Taluk Mandya District. There is a suffering atchkat of 447 Ha. The Government vide order No. WRD 174 MMK 2013, Bangalore, Dtd: 19.02.2014 has accorded administrative approval to the DPR for the modernization of Madhavamantri Anecut and Anecut Canals amounting to Rs.80.00 Crores. The Action has been taken up to implement the modernisation works and proposed for completion during 2014-15.

IMPROVEMENTS TO RAMAPURA CANAL FROM CH:0.00 TO 53.410 KM COMING UNDER LEFT BANK OF HULLAHALLI ANECUT:

Hullahalli anecut is constructed across river Cauvery during the year 1889 near Hullahalli village in Nanjanagud Taluk of Mysore District. This area lies in lower Cauvery basin. This anecut has 2 canals namely Hullahalli Left Bank Canal for a length of 55.00 Km with an atchkat of 2881 Ha and Right Bank Canal for a length of 72.00 Km with an atchkat of 2909 Ha totalling in to 5791 Ha Nanjanagud taluk of Mysore District. There is a suffering atchkat of 944 Ha.The Government vide order No. WRD 9 MMK 2014, Bangalore, Dtd:

9

19.02.2014 has accorded administrative approval to the DPR for the improvements to Ramapura canal from Ch:0.00 to 53.410 km coming under left bank of hullahalli anecut. Hullalli anecut amounting to Rs.43.50 Crores. The Action has been taken up to implement the modernisation works and proposed for completion during 2014-15.

IMPROVEMENTS TO VISHWESHWARAIAH CANAL NETWORK:

The length of the main canal, branch canals, sub branch canals and distributary canals of Vishweshwaraiah canal network is 1523.30 Km. excluding the works taken up under modernisation earlier in the main canal and selected branch canals and lining works taken up in vulnerable reaches totalling to 522.50 Km. It is proposed to take up the improvements to Vishweshwaraiah canal networks for an approximate length of 1000.80 Km. Out of this, a length of 452.00 Km is identified on priority to take up the improvement works. As such the Government vide order No. WRD 68 MMK 2012, Bangalore, Dtd: 24.08.2012 has accorded administrative approval to the DPR for the Improvements to Vishweshwaraiah canal network amounting to Rs.330.00 Crores. These improvement works are taken up in 5 packages comprising of 11 estimates. All the works of these 5 packages are in progress and proposed for completion during 2014-15. During 2013-14, a grant of Rs.125.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.111.20 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.111.70 Crores.

REJUVENATION OF ARKAVATHY RIVER:

Arkavathy River is a part of Cauvery river. This river originatesin Nandi Hills and after traversing a distance of around 190 Km join river Cauvery at confluence point in Kanakapura Taluk. Hesaraghatta reservoir and after joining of Kumudwati river, Tippagondanahalli reservoir have been constructed the provide drinking water supply to Bangalore city. Since, the inflow to these reservoirs is meagre, water is being lifted from Cauvery river for provide drinking water supply to Bangalore. In view of much pressure for supplying of water to Bangalore,it is proposed to take up rejuvenation worksin Hesaraghatta, Kumudwathi and Arkavathi catchment areas from the originating point of Arkavathy river to Tippagondanahalli reservoir. The Government vide order No. WRD 23 MMK 2009, Bangalore Dated: 19.10.2011 has accorded administrative approval to the estimate for Rejuvenation of the Arkavathy River amounting to Rs.22.43 Crores. The works of this project are in progress and proposed for completion during 2014-15.

During 2013-14, a grant of Rs.8.00 Crores has been allocated. Up to end of March- 2014 an expenditure of Rs.11.92 Crores is incurred. The cumulative expenditure incurred since inception up to end of March-2014 is Rs.18.86 Crores.

10

COMMAND AREA DEVELOPMENT PROGRAMME

11

COMMAND AREA DEVELOPMENT PROGRAMME

Agriculture is the backbone of Indian Economy and it is the pillar of the Economic development. At the commencement of the Fifth Five Year Plan (1974-80), in pursuance of the policy of the Government of India, the Command Area Development Programme was launched in the State for integrated and comprehensive development of the Command Areas of Major and Medium Irrigation Projects. As per the objectives laid down by the National Commission on Irrigation, 1971 and the National Commission on Agriculture, 1976, the CADP ensures rapid and optimum utilization of Irrigation Potential created under Major and Medium Irrigation Projects thereby increasing the agriculture production as also reducing the gap between the potential area created and the actual area utilised.

THE OBJECTIVES Irrigation Management is a multi-disciplinary activity involving major department like Irrigation, Agriculture, Cooperation and other organization engaged in training and research activities. Against this perspective, CADA was constituted in the year 1970 to work as a catalyst between the various organizations to reduce the gap between irrigation potential created and utilized, to increase production per unit of water and land, to reduce the loss of irrigation water in the conveyance system, to improve its efficiency at the farm level and to ensure equitable distribution of water. The objectives of the CADA, as envisaged under section 10 of the Karnataka Command Areas Development (K.C.A.D.) Act 1980, are listed below:

To formulate and implement schemes for the Comprehensive Development of the Command Area;

To prevent land erosion and water logging;

To improve soil fertility and regulation of cropping pattern;

12

To ensure the efficient maintenance of Field channels and Field Drains by the Farmers within the Command Area;

Localisation and de-localisation of lands for various crops;

Ensuring supply of all inputs and services;

Promotion and setting up of rural growth centres for integrated development of the Command Area;

Development of marketing, processing and storage facilities and adequate communication system;

Arranging for credit facilities to the farmers and artisans;

Organizing agricultural Co-operatives and Associations;

Construction of Field channels and connected drains;

To borrow and lend money necessary for the due discharge of its functions;

Conjunctive use of surface and ground water;

To determine the payment of compensation as provided in sub section [4] of section 12 of KCAD Act 1980;

To setup agricultural demonstrations farms and promote extension activities; and

To execute such other acts, consistent with the provisions of this Act.

The Six CADA’S that are established in Karnataka are:

 Malaprabha and Ghataprabha Projects, Belgaum

 Tungabhadra project, Munirabad

 Upper Krishna projects, Bheemarayanagudi

 Cauvery basin projects, Mysore

 Bhadra project, Shimoga

13

 Irrigation Project Zone, Gulbarga

14

BRIEF DETAILS OF CADA

Name of CADA Sl. Year of Irrigation Districts with covered No. headquarters Starting Projects Belgaum, Malaprabha and Malaprabha & Dharwad, 1 Ghataprabha 1974 Bagalkot, Projects, Belgaum Ghataprabha Gadag Tungabhadra 1974 Tungabhadra, Bellary, Raichur 2 Project, Munirabad 12.11.1979 Hirehalla, Maskinala & Koppal.

Upper Krishna 1977 Gulbarga, Projects, Bijapur, 11-12- Upper Krishna 3 Bheemarayanagud Raichur & i 1979 Bagalkot. Kabini, Harangi, Hemavathy, KRS. , Nugu, Taraka, Mysore, Kodagu, Cauvery Basin 1974 Gundal, Votehole, Chamarajnagar, 4 Hassan, Mandya, Projects, Mysore 1.3.1974 Marconahally, Tumkur, Manchanabele, Bangalore(Rural) Kanva and Byramangala. Shimoga, 5 Bhadra Reservoir UTP, Tunga, Bhadra Chikkamagalore 1979 Project, Shimoga & Gondi , Davangere. Haveri Chandrampalli, Hattikuni, Soudhagar, Upper Gulbarga, Irrigation Project Mullamari, Amarja, Bidar, Yadgir, 6 2000 Zone, Gulbarga Bennethora, Bhima Bagalkot and lift, Gondorinala, Bijapura Kagna, Karanja, Chulkinala, LMP,

15

CADA DIRECTORATE WAS FORMED IN THE STATE TO HAVE BETTER CO-ORDINATION AMONG EACH CADA’s AND STEPS TO INCREASE EFFICIENCY IN WATER USERs CO-OPERATIVE SOCIETIES (WUCs) IN THE COMMAND AREA OF MAJOR AND MEDIUM IRRIGATION ON 17.11.2012.

ANNEXURE-B

PROPOSED ORGANISATION CHART FOR CADA DIRECTORATE

CADA Dir Headed

(IAS or En

CADA TBP MUNIRABAD CADA M&GP BELGAUM CADA CBP

MYSORE TO BE HEADED BY TO BE HEADED BY SUPERINTENDING SUPERINTENDING TO BE HEADED BY ENGINEER ENGINEER SUPERINTENDING ENGINEER

CADA CADA CADA CADA CADA TBP Division No.1 M&GP Division M&GP Division CBP Division CBP Divisi To be headed by No.1 No.2 No.1 No.2 Executing Engineer To be headed by To be headed by To be headed To be headed Executing Executing by Executing Executing

Engineer Engineer Engineer Engineer

CADA CADA CADA CADA CADA TBP CBP Sub CBP Sub CBP TBP Sub Sub Sub Division- Division- Division Division 1 1 Division- (Engineeri (Agricultur (Enginee (Agricult 2 ng) e & Co- ring) ure & (Enginee Operation) Co- ring) Operatio

16 CADA CADA CADA CADA C M&GP Sub M&GP Sub M&GP M&GP Sub UK Division -1 Division-1 Sub Division-2 Div Division-2 (Engineerin (Agriculture (Agrucultur (En

TUNGABHADRA PROJECT, MUNIRABAD CADA, Tungabhadra Project came into existence in the year 1974. Eleven irrigation projects with a total planned potential of 464054Ha are coming under the jurisdiction of this CADA.

During 2013-14, the budget allocation is Rs.8113.00 out of which total expenditure of Rs.5624.47 lakhs have been incurred.

Programme for the year 2014-15 is Rs.4411.00 lakhs

MALAPRABHA AND GHATAPRABHA PROJECTS, BELGAUM

CADA, Malaprabha and Ghataprabha Project came into existence in the year 1974. Eleven irrigation projects with a total planned potential of 650377Ha are coming under the jurisdiction of this CADA.

During 2013-14, the budget allocation is Rs.11562.00 lakhs out of which total expenditure of Rs.3289.28 lakhs have been incurred.

Programme for the year 2014-15 is Rs.4441.00 lakhs.

CAUVERY BASIN PROJECTS, MYSORE CADA, Cauvery Basin Project came into existence in the year 1974. Fifty three irrigation projects with a total planned potential of 678172Ha are coming under the jurisdiction of this CADA.

During 2013-14, the budget allocation is Rs.5551.00 lakhs & out of which total expenditure of Rs.3184.43 lakhs have been incurred.

Programme for the year 2014-15 is Rs.2438.00 lakhs.

UPPER KRISHNA PROJECTS, BHEEMARAYANAGUDI

Command Area Development Authority, Upper Krishna projects, Bheemarayanagudi, has come into force since 11-12-1979. Two irrigation projects with a total planned potential of 648020Ha are coming under the jurisdiction of this CADA.

During 2013-14, the budget allocation is Rs.7996.00lakhs out of which total expenditure of Rs.1821.42 lakhs have been incurred.

17

Programme for the year 2014-15 is Rs.3793.00 lakhs.

BHADRA PROJECT, SHIMOGA

Command Area Development Authority, Bhadra project, Shimoga, came into existence during 1979. Thirty irrigation projects with a total planned potential of 260071Ha are coming under the jurisdiction of this CADA.

During 2013-14, the budget allocation is Rs.5697.00 lakhs out of which total expenditure of Rs.4121.01 lakhs have been incurred.

Programme for the year 2014-15 is Rs.3574.00 lakhs.

IRRIGATION PROJECT ZONE, GULBARGA

Command Area Development Authority, Irrigation Project Zone, Gulbarga, came into existence during 2000-01. Nineteen irrigation projects are coming under the jurisdiction of this CADA with a total planned potential of 145067Ha

During 2013-14, the budget allocation is Rs.5397.72 lakhs out of which total expenditure of Rs.1960.61 lakhs have been incurred.

Programme for the year 2014-15 is Rs.3494.00 lakhs.

18

The details of the Physical programme & Progress and Financial Programme & progress for the year 2013-14 up to the end of 3/2013.

Cumulative to the end of the % against Annual month Sl.No. CADA Unit Annual Target Programme Progress Target A. Central Sector Scheme 1 Direction and Administration Approved Projects CADA Fin 2988.72 2988.72 2213.56 74 KBJNL Fin 1200.00 1200.00 1155.44 96 Other than approved projects Fin 604.92 604.92 604.32 100 2 Field Irrigation Channel Approved Projects CADA Fin 3210.00 3210.00 1406.24 44 Phy:Ha 19399 19399 9340 48 KNNL Fin 4988.99 4988.99 729.39 15 Phy:Ha 39341.72 39341.72 6891.68 18 KBJNL Fin 12801.34 12801.34 5711.06 45 Phy:Ha 49435.08 49435.00 22767.00 46 Other than approved projects CADA Fin 60.15 60.15 53.30 89 Phy:Ha 802.00 802.00 775.00 97 KNNL Fin 4455.35 4455.35 655.58 15 Phy:Ha 42593.45 42593.45 6977.62 16

CNNL Fin 800.00 800.00 492.09 61.51 Phy:Ha 10667.00 10667.00 7121.14 66.76 3 Survey Approved Projects Fin 20.00 20.00 5.76 29 Phy:Ha 6845.00 6845.00 2747.77 40 4 Field Drainage Channel Approved Projects Fin 6089.00 6089.00 4278.26 70 Phy:Ha 152225 152225 128547 84 Other than approved projects Fin 5.08 5.08 4.62 91 Phy:Ha 127 127 115 91 5 Adoptive Trials / Demonstration Approved Projects Fin 73.00 73.00 64.98 89 Phy:Ha 1246 1246 1456 117 Other than approved projects Fin 5.00 5.00 4.55 91 Phy:Ha 99 100 93 94 6 Correction of System Deficiencies

19

Approved Projects Fin 1074.00 1074.00 69.39 6 Phy:Ha 17900 17900 1156 6 7 Training Approved Projects Fin 362.00 362.00 321.06 89 Phy:No 17268 17268 22495 130 Other than approved projects Fin 30.00 30.00 28.07 94 Phy:No 105.00 105.00 84.00 80 8 Farmers Participation Approved Projects Fin 760.00 760.00 317.24 42 Phy:Ha 75414 75404 30723 41 Other than approved projects Fin 50.00 50.00 50.06 100 Phy:Ha 5000.00 5000.00 5006.00 100 9 Land Reclamation Approved Projects Fin 9545.00 9545.00 953.66 10 Phy:Ha 52327.07 52327.07 3799.06 7 Other than approved projects Fin 39.00 39.00 85.71 220 Phy:Ha 97.50 97.50 214.00 219

10 Monitoring and Evaluation

Approved Projects Fin 6.00 6.00 6.00 100

Phy:Ha 1.00 1.00 1.00 100 B. State Sector Schemes 1 Construction Ayacut Roads Fin 531.14 531.14 486.73 92 Phy:Km 170.00 170.00 165.24 97

2 Construction Ayacut Roads Fin 3000.00 3000.00 3104.98 103

(NABARD) Phy:Km 74.35 83.81 188.51 254 3 Housing Fin 120.80 120.80 79.00 65 4 Construction of Godowns Fin 37.91 37.91 21.82 58 Phy:No 9 10 4 44 5 Miscellaneous Fin 47.00 47.00 22.07 47 Total CADA(2705) Fin 30458.74 30458.72 14181.38 47 WALMI (2705) Fin 200.00 200.00 174.44 87 4705 Fin 14001.00 14001.00 5937.04 42 KNNL Fin 9444.34 9444.34 1384.97 15 KBJNL Fin 14001.34 14001.34 6866.50 49 CNNL Fin 800.00 800.00 492.09 Grand Total (2705+4705) Fin 44659.74 44659.72 20292.86 45

20

BRIEF DETAILS OF CADA

Sl. Name of CADA with Year of Irrigation Districts covered No. headquarters Starting Projects Malaprabha and Belgaum, Malaprabha & 1 Ghataprabha Projects, 1974 Dharwad, Ghataprabha Belgaum Bagalkot, Gadag Tungabhadra Project, 1974 Tungabhadra, Hirehalla, Bellary, Raichur & 2 Munirabad 12.11.1979 Maskinala Koppal. Gulbarga, Bijapur, Upper Krishna Projects, 1977 Upper Krishna Raichur & 3 Bheemarayanagudi 11-12-1979 Bagalkot. Kabini, Harangi, Mysore, Kodagu, Hemavathy, KRS. , Nugu, Chamarajnagar, Cauvery Basin Projects, 1974 Taraka, Gundal, 4 Hassan, Mandya, Mysore 1.3.1974 Votehole, Marconahally, Tumkur, Manchanabele, Kanva Bangalore(Rural) and Byramangala. Shimoga, 5 Bhadra Reservoir UTP, Tunga, Bhadra & 1979 Chikkamagalore, Project, Shimoga Gondi Davangere. Haveri Chandrampalli, Hattikuni, Soudhagar, Upper Mullamari, Gulbarga, Bidar, Irrigation Project Zone, 6 2000 Amarja, Bennethora, Yadgir, Bagalkot Gulbarga Bhima lift, Gondorinala, and Bijapura Kagna, Karanja, Chulkinala, LMP,

MALAPRABHA AND GHATAPRABHA PROJECTS, BELGAUM

Command Area Development Authority, Malaprabha and Ghataprabha projects, Belgaum, came into existence during 1974-75.

During 2011-12, the budget allocation is `.21762.50 lakhs (under head 2705 ) & 400.00 lakhs (under head 4705 ) out of which total expenditure of `.2898.87 lakhs has been incurred. Programme for the year 2012-13 is `.191.12 crores.

TUNGABHADRA PROJECT, MUNIRABAD

Command Area Development Authority, Tungabhadra project, Munirabad, came into existence during 1974-75. During 2011-12, the budget allocation is `.12246.76 lakhs (under head 2705 ) & 500.00 lakhs (under head 4705 ) out of which total expenditure of `.6560.46 lakhs has been incurred. Programme for the year 2012-13 is `.108.07 crores.

UPPER KRISHNA PROJECTS, BHEEMARAYANAGUDI

Command Area Development Authority, Upper Krishna projects, Bheemarayanagudi, has come into force since 11-12-1979.

21

During 2011-12, the budget allocation is `.14301.25 lakhs (under head 2705 ) & 800.00 lakhs (under head 4705 ) out of which total expenditure of `.877.84 lakhs has been incurred. Programme for the year 2012-13 is `.126.94 crores. CAUVERY BASIN PROJECTS, MYSORE Command Area Development Authority, Cauvery basin projects, Mysore, came into existence during 1974-75. During 2011-12, the budget allocation is Rs.5464.81 lakhs (under head 2705 ) & 2100.00 lakhs (under head 4705 ) out of which total expenditure of Rs.2986.29 lakhs has been incurred. Programme for the year 2012-13 is Rs.62.03 crores.

BHADRA PROJECT, SHIMOGA

Command Area Development Authority, Bhadra project, Shimoga, came into existence during 1979. During 2011-12, the budget allocation is Rs.8840.53 lakhs (under head 2705 ) & 500.00 lakhs (under head 4705 ) out of which total expenditure of Rs.3252.70 lakhs has been incurred. Programme for the year 2012-13 is Rs.67.42 crores.

IRRIGATION PROJECT ZONE, GULBARGA

Command Area Development Authority, Irrigation Project Zone, Gulbarga, came into existence during 2000-01. During 2011-12, the budget allocation is Rs.7896.53 lakhs (under head 2705 ) & 700.00 lakhs (under head 4705 ) out of which total expenditure of Rs.2591.76 lakhs has been incurred. Programme for the year 2012-13 is Rs.60.15 crores.

The details of the Physical programme & Progress and Financial Programme & progress for the year 2011-12 up to the end of 3/2012.

22

Financial and Physical Programme and Progress under CADA and WALMI for the Year 2011-12 (Physical In Ha) (`.In Lakhs)

Revised Sl. Annual Annual Cumulative No CADA Unit Target Target Progress % A) Central Sector Schemes 1 Direction & Administration Approved projects

CADA Fin 3624.62 3624.62 1662.38 46

KBJNL Fin 1000 1000 961.14 96 Other than approved projects Fin 240 240 278.13 116 2 Field Irrigation Channel Approved projects CADA Fin 16855.41 16855.41 1456.26 9 Phy:Ha 108700 108700 9225 8 KNNL Fin 4531 4531 454.77 10 Phy:Ha 32908.61 32908.61 2795.42 8 KBJNL Fin 5000 5000 1030.37 21

Phy:Ha 33333 33333 7240 22 Other than approved projects

CADA Fin 1325 1125 359.67 32

Phy:Ha 17333 14666 4546 31

KNNL Fin À 450 450 79.42 18

Phy:Ha 8167 8167 509.62 6

CNNL Fin 2500 2500 1857.37 74

Phy:Ha 51708 51708 28709.36 56 3 Survey(Topographical soil & other)

Fin 1118.85 1118.85 38.43 3

Approved projects Phy:Ha 159352 159352 36980.73 23

Fin 220.00 220 198.66 90 Other than approved projects Phy:Ha 6000.00 6000 6000 100 4 Field Drainage Channel

Approved projects Fin 10436.6 11444.2 5555.06 49

Phy:Ha 254665 279855 145590 52 Other than approved Fin projects 50.00 50 49.7 99 Phy:Ha 1250.00 1250 1242 99

23

5 Adoptive Trials/ Demonstration Fin 328.00 328 306.26 93 Approved projects Phy:No 7734.00 7734 7687 99 Fin 5.00 5 4.93 99 Other than approved projects Phy:No 100.00 100 150 150 6 Correction of System deficiencies

Fin 5688.95 4681.35 199.6 4 Approved projects Phy:No 94816 78022 3326 4

7 Training

Fin 568.00 568 439.61 77

Approved projects Phy:No. 30866.00 30866 51377 166 Fin 30.00 30 27.39 91 Other than approved projects Phy:No. 105.00 105 96 91 8 Farmers' Participation Fin 1692.19 1692.19 582.48 34 Approved projects Phy:Ha 180053 180053 63511 35 Fin 100.00 100 99.88 100 Other than approved projects Phy:Ha 10000.00 10000 10000 100 9 Land Reclamation Fin 24197.38 24197.38 3843.32 16

Approved projects Phy:Ha 84203.5 84203.5 15521.39 18 Other than approved Fin 1100.00 1300 1298.66 100 projects Phy:Ha 4694.00 5583 5647 101 State Sector B Schemes

Warabandi Fin 37.53 37.53 2.53 7 1 Phy:Ha 12510.00 12510 843 7

Construction of Ayacut Fin 1816.57 1816.57 1471.41 81 2 Roads Phy:Km. 453.51 453.51 364.74 80

3 Housing Fin 155.00 155 67.78 44

Construction of Godowns Fin 105.87 105.87 57.36 54 4 Phy:No. 32.00 32 16 50

6 Special Component Plan Fin 350.00 350 349.79 100 7 Tribal Sub Plan Fin 175.00 175 174.21 100 8 Miscellaneous Fin 349.03 349.03 6.63 2 Total CADA(2705) Fin 70569.00 70569 18530.13 26

24

Special Development Programme (4705) Fin 5001.00 5001 2524.86 50 KNNL Fin 4981.00 4981 534.19 11 KBJNL Fin 6000.00 6000 1991.51 33 CNNL Fin 2500.00 2500 1857.37 74 Grand Total (2705+4705) Fin 76070.00 76070 21238.94 28

25