RP202 VOL. 5 Public Disclosure Authorized Public Disclosure Authorized Liede Resettlement Implementation Plan Public Disclosure Authorized Public Disclosure Authorized

I . ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Table of Contents

1. General ...... 9

1.1 Project overview ...... 9

1.1.1 Brief introduction ...... 9

1.1.2 General Situation of Project Zone ...... 10

1.2 Analyses of the economic environment of the project resettlement ...... 12

1.2.1 Objective of the analysis of the economic environment of the resettlement ...... 12

1.2.2 Socioeconomic characteristics of the project area ...... 13

1.2.3 Analysis of the employment environment in the project area for the PAPs with low income 14

1.2.4 Analyses of the business environment for small businesses and shops in the project area 17

1.3 Summarization for Project Resettlement .20

1.3.1 Explanation for resettlement in the area of Waster Water Treatment Plant ...... 20

1.3.2 Explanation of the data source of the current resettlement of this project ...... 21

1.3.3 Update of the resettlement data ...... 23

1.3.4 Total quantity of the resettlement ...... Error! Bookmark not defined.

1.3.5 Characteristics of the resettlement ...... 24

1.3.6 Estimation of the resettlement cost ...... 26

1.4 Measures to be taken to minimize the quantity of resettlement.27

1.5 Explanation of this Resettlement Implementation Plan.27

1.5.1 In obedience to the Resettlement Policy .27

1.5.2 Explanation of the chapter arrangement of the Resettlement Implementation Plan27

1.6 Classificationof the impacted areas of the project .28

1.7 General list of the affected land and housings.28

2. Status of the resettlement of the property owners and the compensation plan. 29 2.1 Status of the resettlement of the property owners ...... 29

2.1.1 Type and distribution of the permanently requested land .29

2.1.2 Type and distribution of the temporarily requested land .29

2.1.3 Property right and distribution of the temporarily affected buildings .30

2.1.4 Property right and distribution of partially but permanently affected buildings .31

2.1.5 Property right and distribution of wholly and permanently affected buildings . 33

2.1.6 Status of the structures, attachments and housing facilities .34

2.1.7 Status of the infrastructure .34

2.1.8 Conclusion ...... Error! Bookmark not defrned.

2.2 Compensation plan.34

3. Status of the PAPs who rent the houses with market-price and the resettlement,

compensation and rehabilitation plans for them ...... Error! Bookmark not defined.

3.1 Status of the PAPs who rent the houses with market-price Error! Bookmark not defined.

3.2 Resettlement, compensation and rehabilitationplans for the PAPs who rent the houses

with market-price...... 44

4. Status of the PAPs whose property is temporarily affected and the resettlement, compensation and rehabilitation plans for them ...... 47

4.1 Status of the PAPs whose property is temporarily affected .47

4.1.1 Temporarily affected housings and their distribution .47

4.1.2 Temporarily affected shops and their distribution .47

4.1.3 Temporarily affected enterprises and their distribution .48

4.1.4 Temporarily affected commonweal units and their distribution .49

4.2 Resettlement, compensation and rehabilitationplans for the PAPs whose property is temporarily affected .49

4.2.1 Resettlement, compensation and rehabilitation plans for temporarily affected housings 49

4.2.2 Resettlement, compensation and rehabilitation plans for temporarily affected shops 50

4.2.3 Resettlement, compensation and rehabilitation plans for temporarily affected

enterprises ...... Error! Bookmark not defined.

4.2.4 Resettlement, compensation and rehabilitation plans for temporarily affected

commonweal units ...... Error! Bookmark not defined.

5. Status of the PAPs whose property is partially but permanently affected and the

resettlement, compensation and rehabilitation plans for them ...... 53

5.1 Status of the PAPs whose property is partiallybut permanently affected .. 53

5.1.1 The partially but permanently affected housings ...... 53

5.1.2 The partially but permanently affected shops ...... 53

5.1.3 The partially but permanently affected enterprises ...... 54

5.1.4 The partially but permanently affected commonweal units ...... 55

5.2 Resettlement, compensation and rehabilitationplans for the PAPs whose property is

partially but permanently affected .. 55

5.2.1 Resettlement, compensation and rehabilitation plans for partially but permanently

affected housings ...... Error! Bookmark not defmed.

5.2.2 Resettlement, compensation and rehabilitation plans for partially but permanently

affected shops ...... 56

5.2.3 Resettlement, compensation and rehabilitation plans for partially but permanently

affected enterprises ...... 57

5.2.4 Resettlement, compensation and rehabilitation plans for partially but permanently

affected commonweal units ...... 575

6. Status of the PAPs whose property is wholly and permanently affected and the resettlement, compensation and rehabilitation plans for them ...... 60

6.1 Status of the PAPs whose property is wholly and permanently affected ...... 60

6.1.1 Classification of the PAPs whose property is wholly and permanently affected .... 60

6.1.2 Property right of the PAPs whose property is wholly and permanently affected ... 60

6.1.3 Living condition of the PAPs whose property is wholly and permanently affected 60 6.1.4 Household economy status of the PAPs whose property is wholly and permanently affected 61

6.1.5 Population structure and household classification of the PAPs whose property is

wholly and permanently affected ...... 61

6.1.6 Change of commuting of the PAPs whose property is wholly and permanently affected Error! Bookmark not defined.

6.1.7 Analyses of benefit and loss ...... Error! Bookmark not defmed.

6.2 Principle of the setup of residential resettlement sites ...... 64

6.3 Description of the residential resettlement sites ...... 66

6.3.1 Relocation Point Near Xinbu Corridor ...... 67

6.3.2 Relocation Point Near Huizhan Xingcheng ...... 71

Huizhan Xincheng as the core, residential quarters of Hongyun garden, Fujingju and Lijing

Garden are suitable for Resettlement within 1 km from the . . 71

6.3.3 Relocation Point Near Yujing Nanyuan ...... 75

6.3.4 Relocation Point Near Yunjing Garden ...... 78

6.3.5 Relocation Point Near Beili Garden ...... 82

6.3.6 Relocation Point Near Haijing Garden ...... 86

6.4 Resettlement, compensation and rehabilitationplans for the PAPs Error! Bookmark not defined.

7. Status of the permanently and wholly affected shops and the resettlement, compensation and rehabilitation plans for them ...... 93

7.1 The wholly and permanently affected shops...... 93

7.1.1 Distribution of the wholly and permanently affected shops ...... 93

7.1.2 >Property right and structure of the wholly and permanently affected shops ...... 93

7.1.3 The ownership of the wholly and permanently affected shops...... 93

7.1.4 The trade distribution of the wholly and permanently affected shops ...... 93

7.1.5 Business condition of the wholly and permanently affected shops ...... Error! Bookmark not dermed. 7.2 Principle of the setup of resettlement sites for affected shops...... 94

7.3 Description of the resettlement sites for the affected shops...... 96

7.4 Resettlement, compensation and rehabilitationplans for the wholly and permanently affected shops. 101

8. Status of the permanently and wholly affected enterprises and the resettlement, compensation and rehabilitation plans for them ...... 103

8.1 Distribution of the wholly and permanently affected enterprises...... 103

8.1.1 Distribution of the affected enterprises .103

8.1.2 Property right of the affected enterprises .103 1

8.1.3 Distribution of the ownership of the wholly and permanently affected enterprises 103

8.1.4 Trade distribution of the wholly and permanently affected enterprises . Error! Bookmark not defmed.

8.1.5 Operation and distribution of the wholly and permanently affected enterprises

Error! Bookmark not defined.

8.2 Principle of the setup of resettlement sites for affected enterprises.104

8.3 Description of the resettlement sites for affected enterprises.106

8.4 Resettlement, compensation and rehabilitationplans for the wholly and permanently affected enterprises...... Error! Bookmark not defined.

9. Status of the permanently and wholly affected commonweal units and the resettlement, compensation and rehabilitation plans for them ...... 112

9.1 Status of the permanently affected commonweal units...... 112

9.2 Resettlement, compensation and rehabilitationplans for affected commonweal units .112

10. Status of the institutions and the resettlement, compensation and rehabilitation plan for them ...... 115

10.1 Brief introduction of the institutions.115 10.2 Relevant resettlement, compensation and rehabilitationplans ...... 115

11. Status of the rural areas and the resettlement, compensation and rehabilitation plans

for them ...... 1177

11.1 Basic status of the rural areas...... 117....1

11.2 Basic condition of the labourforce...... 117

11.3 Resettlement channels and safeguardmechanism for the labourforce ...... Error! Bookmark not defined.

12. Status of the disadvantageous group and the resettlement, compensation and

rehabilitation plans for them ...... 119

12.1 Basic situation of the disadvantageousgroup ...... 119

12.2 Resettlement, compensation and rehabilitationplans for the disadvantageousgroup 119

13. Explanation on preparation of resettlement and compensation standard for

Guangzhou Urban Environmental Project ...... 122

13.1 Compensation standardforland ...... 122

13.1.1 Compensation standard for land requisition (please see Annexed Table 13.1.1) 122

13.1.2 Compensation for retracted land and free land (See Annexed Table 13.1.2 for details) 124

13.2 houses with property rightcompensation standard...... 124

13.3 Other compensation standard...... 126

14. Insititutional structure of the resettlement and the ability building ...... 131

14.1 Resettlement organizationplan .131

14.2 Resettlement organization responsibility.131

14.3 Resettlement organization ability construction.131

14.3.1 Resettlement organization improvement .131 14.3.2 Application of URRP ...... 133

14.3.3 raining plan of resettlement work personnel ...... 134

15. Information disclosure plan...... 137

15.1 Publishing of unfolded information...... 137

15.2 Information publishing in the next stage ...... 137

16. Public participation and consultation ...... 139

16.1 Unfolded public participationand consultation...... 139

16.2 The achievement of public participationand consultation...... 140

16.3 Public participationand consultation schedule for next stage...... 142

17. Monitoring and evaluation ...... 143

17.1 Internal monitoring ...... 143

17.2 Independent supervision...... 143

17.3 Schedule of the informationpublishing, public participationand consultation and

supervision and evaluation...... 144

18. Cost estimate and fund plan of the project ...... 153

18.1 Description ofproject estimate.153

18.2 Compilation standardfor and explanation of pipeline estimation.156

18.3 ProjectBudget .159 Liede Resettlement Implementation Plan

1. General

1.1 Project overview

1.1.1 Brief introduction

1) Scope of service of project

Guangzhou Liede Waster Water Treatment System (Phase III) Project is extension work based on foundation of Phase I and Phase II of Liede Waster Water Treatment System. It is also a sub-item in Guangzhou Urban Environment Project. The plant location is near Tancun Village in the east of Liedechong that is to the north of front channel of Guangzhou section of . The controlled land area is 39.011 hectare.

The service scope of the Project reaches Chepochong Stream in east, the front channel of Pearl River in south and Guangshan Road in north. It mainly collects the wastewater in the drainage area of Chengjiechong Stream and Chepochong Stream. There are eight residential areas in the waster water treatment system, including Lingtang, Yuancun, Wushan, etc. Total layout population is 900,000 and the coverage is 78.3km2 . As per the

383A 84B 4A, ' .9~~~~3 s^ Z I J, 3A >j

IA >64bA

I21 3A -{ tt X IF XLb 4B

/;Z IB . ID D S 3A 6 IA 3C 48 5 A

3B\ 2A , _!

design, it.is predicted that the layout capacity of wastewater treatment in 2010 shall be 320,000 m3/ d.

2) Contents of Engineering Construction

(I)The layout content of engineering construction includes the construction of buildings

m ~_ X X Liede Resettlement Implementation Plan

and structures in plant area and the improvement of off-plant collecting pipeline network system.

(2)Thereof, total length of off-plant wastewater collecting system reaches 11, 317 m, including:

* Main pipe: main sewer of Linjiang Avenue (Chepo Road - Liede Waster Water Treatment Plant)

* Main sewer:

A. Sewage trunk sewer for Keyun Road

B. Chepochong Stream - sewage trunk sewer for Chepo Road 3) Project Engineering Process

Project Engineering Schedule Items Schedule Period (day) 1. Formal evaluation of the World Bankl Bank ~~~~~~December, 2003 2. Project design (from confirmation September 28, 2003 of the Design Entity to completion -October 11, 2005745 of the construction drawing) 3. Project-related resettlement work October 12, 2003- May 7, (including land use for plant area 2574 2005 and pipeline resettlement) 4.Project construction (from confirmation on bidding agency to October 28, 2003-November 744 completion of pipeline 9, 2005 construction) October 27, 2005-December 5. System commissioning 23, 2005 58

December 24, 6. Handover for operation 2005-December 30, 2005

1.1.2 General Situation of Project Zone

1.1.2.1 Brief introduction for project zone

Guangzhou Liede Waster Water Treatment System (Phase EII) Project is located in , Guangzhou City. This district is located in the east of Guangzhou Planning Area. The west boundary of this district is from Dengfeng and Guangzhou Avenue and connected with and Dongshan District. It extends to Jishan in the east and connected with Huangpu District. It extends to Pearl River in south and faces Haizhu District on the other side of the river. It reaches Shaojiwo in the north and borders upon Baiyun District. Total area of the district is 147.77 kmn and total population 547, 600. There are 25 universities and colleges, 40 central, provincial and municipal scientific research institutes, 3 national key research offices and one national developing zone of Liede Resettlement Implementation Plan

high-tech industry, Tianhe Technology Park. This district is the modernized central district of Guangzhou at the present.

1.1.2.2 Environmental Pollution Status in project zone

With the development of economy and the expansion of population, the urban environmental capacity has been comparatively reduced. In particular, the original environmental protection measures and facilities are lagging behind. All these factors result in the serious pollution of environmental quality in the project zone - Tianhe District. In recent years, though the government has more energetically redulated and controlled the industrial pollution, the treating ratio of domestic sewage is still lower. Everyday, large amount of wastewater enters Pearl River directly or through stream, which brings that the stream pollution is very serious in this area and Guangzhou section of Pearl River is also seriously polluted. 1) Pollution Condition:

In accordance with Guangzhou Annual Environmental Quality Evaluation Report for the year 2000, the water quality in the section of Tianhe District channel is of type IV, which has not met the applicable standard for environmental quality. The total level of stream water quality in Tianhe District is comparatively badly. Thereof, the index of water pollution in Tangxiachong Stream and Chepochong Stream is the highest and it belongs to serious pollution (see following table for particular information). Others streams belongs to high-grade pollution.

Table: Indices for Main Stream Pollution of Tianhe District in Year 2000 and the 9th Five-year Plan Period

Year Tangxiachong Stream Chepochong Stream

2000 5.93 4.52 5-year Average 5.18 6.30 Value

Notes: Data in the above table roots in Residentiai area Layout of Guangzhou Liede Waster Water Treatment System (Phase III) Project

2) Pollution Reason: (1) The amount of industrial sewage and domestic sewage in Tianhe District are large. It is statisticed that the discharging capacity of industrial sewage in Tianhe District in 1998 reaches 18, 616, 700 tons and that of domestic sewage amounts to 36, 938,000 tons.

(2) Sewage treating capacity of Tianhe District is insufficient and the discharging system is not complete.

1.2 Analyses of the economic environment of the project resettlement

1.2.1 Objective of the analysis of the economic environment of the resettlement

1) From analysis in Paragraph 2.4 of the Involuntary Resettlement Planningfor Guangzhou Urban Environment Project-- Resettlement Policy, the social environment in Guangzhou City is very much compatible to the project affected people and is easy to accept those people; the economy in Guangzhou is developing very fast while the space for further development remains considerably prospective, which means more jobs will be available and the capacity for taking the project affected people is very strong; in addition, the social security and job security system in Guangzhou are considerably mature while the infrastructure is well developed too, which provides to the project affected people good space for living and development.

2) Nevertheless, in order to be in a better position to protect interest of the project affected people and keep integrity of the original living area and social relations of those project affected people wherever possible, this Chapter will analyze the economic environment Liede Resettlement Implementation Plan

of areas where the sub-items of the project are, and based upon the analysis, the employment environment of project affected people and management environment of the enterprises will be analyzed. Thus the capacity of the project affected people to rehabilitate the living and sustenance under the specific economic environment of areas where the sub-items of the project are will be analyzed while the focus of the resettlement work for the project will be lodged forward. In this way, the resettlement plan and relevant measures made in "Resettlement Implementation Plan" for the project will be more feasible and the resettlement object will be realized more satisfactorily.

3) The project will focus upon recovery of living and sustenance of those project affected people who are less qualified and who have less income. Because those project affected people who are considerably qualified and who have higher income have broad space to find jobs and their living adaptability is very strong, their living and sustenance will basically not be affected by the project affected people; on the contrary, the situation is just the opposite for those who are less qualified and who have lower income and poor skills (including those projected affected farmers).

4) The project will focus also upon rehabilitation of capacity for those small businesses and shops. As the project is for construction of pipe network (land requisition for plant site was completed), the work takes a linear (belt) character and will not cause overall resettlement of those big companies and government and social institutions but possibly to those small businesses and commercial firms only who are involved with the project. In addition, those small businesses and commercial firms are more easily to be affected by the management environment

1.2.2 Socioeconomic characteristics of the project area

Tianhe District is the center of higher education in Guangzhou from of old. There are 58 colleges and scientific research institutions subject to the central, provincial or municipal governments in this district. Its preferential policies have attracted a large amount of talents with higher educational records. According to the fifth census data in 2000, the population with junior college education or above accounts for 22.84% of the total of the district, ranking first among districts of Guangzhou city. All these factors make the economic development of Tianhe District show following characteristics:

1) Scientific and technological industry-oriented economic development

Tianhe District emphasized the development of scientific and technological industry. In addition to colleges, universities and research institutions, there are two national high and new technology development zones in Tianhe District-Tianhe Technology Park and Guangzhou Scientific City. These institutions and development zones combine research, development with production to push the transfer and development of commoditization and industrialization of scientific research results in this district. According to the statistics, in 2002 the output value of high and new technological products of Tianhe Technology Park and software Park reached as high as RMB 6.185 billion Yuan, accounting for 53.69% of the district GDP. Liede Resettlement Implementation Plan

2) Service sector as principal in economic growth

The economy of this district has kept a rapid growth trend for many years, during which the service sector occupies an obvious principal position in the whole industrial structure. According to the statistics in 2001 and 2002, all service sectors of this district account for over 69% of the entire GDP, which result in directly its increasing demand for labor force (see the following table for details):

Table: GDP and Employment of Service Sector in Tianhe District

GDP of Service Sector Employment of Service Sector

Year Gross Percentage in Increase Number of Percentage Increase

product GDP by over employees in the total by over

value of that of the employees that of the

service last year last yeat sector

In RBM 69.56% 20.98% 148486 A 57.46% 2.46% 2001 7.01165 billion Yuan

In RMB 69.16% 13.92% 165587 h 59.68% 2.22% 2002 7.98798

billion Yuan (Notes:

1. The data come from Yearbook of Guangzhou and Statistical Yearbook of Guangzhou in 2002 and 2003;

2. The product value statistics is subject to the district specification.)

1.2.3 Analysis of the employment environment in the project area for the PAPs with low income

The characteristics of regional economic development decide the development directiand potential of trades in this district, and such direction and potential decide the development direction of various posts of every trade and the number of employment opportunities. Such economic characteristics of project area result in the distribution of low-income posts of various trades in following table: Liede Resettlement Implementation Plan

Analysis on the Employment Situation of Low-Income Posts in Tianhe District

Percentage Ranking Skills requiredApplicable Quantity in the total number Type of tradePostSkillsrequiredApplicableof emploft e esame among Remarks Type of tradePost ~~by the post population employees tradhe inm 12 ______Gu~~~~~~~~~~~~~~~tadingzoGuanzo districts 1. Fitting up Fitting up worker, Require relevant Mainly middle-aged 3033 14.41% 3 The people living in the project area and porter, etc. skills on fitment and young men have high requirements for living quality decoration and comfort and luxury of the house industry 2. Wholesale Salesclerk No special No limitation 37743 19.91% 1 business requirements 3. Retail Salesclerk Have received Mainly middle-aged 18789 16.58% 2 There are many famous shops engaged business relevant and young women in dress, shoes, bags and electric occupational skill appliances in Tianhe Shopping Center training and Modem Department Store 4. Restaurant Waiter, sanitation Have received Mainly young women 13381 13.10% 3 Most are high-grade and medium-grade and beverage worker, dish relevant restaurants. industry washer, etc. occupational skill training 5. Real estate Securities No special Mainly middle-aged 10129 18.86% 1 Most are high-grade and medium-grade management custody clerk, requirements and young men with living quarters with special entrance industry entrance guard, strong body guard. More and more living quarters garage keeper, etc are equipped with underground garages, so special persons are required to manage the garages. 6. Public Litter man No special Mainly women 11259 15.55% 2 facilities requirements service .

I~~~~~~~~~~~~ -i - _ - _ Liede Resettlement Implementationi Plan

Analysis on the Employment Situation of Low-Income Posts in Tianhe District

Percentage Rainking

Type Skills required Applicable Quantity emptheetotal number of trade Post theqpost Appliatio of employees among by the post population employees of the same 12 Remarks trade in ditcs ______Guangzhou 7. Hairdresser, Require relevant Mainly young men 2967 12.10% 3 High-grade and medium-grade service is Neighborhood beautician, skills and women required, and maintenance service services maintainer and of electric appliance (computer, air industry salesclerk of conditioner) is also required. electric apparatus 8. Hotel Service worker, Have received Mainly young women 7561 11.59% 3 High-grade and medium-grade service business sanitation worker, relevant etc. occupational skill training 9. Waiter Have received Mainly young women 1389 11.00% 3 High-grade and medium-grade service Entertainment relevant service occupational skill training

Notes:

(1) Total employees of each district [unit: person]: the entire city: 3573132; Dongshan District: 374655; Liwan District: 166698; Yuexiu District: 231975; Haizhu District: 306620; Tianhe District: 470075; Fangcun District: 86806; Baiyun District: 491630; Huangpu District: 232679; Panyu District: 627192; Huadu District: 208530; Zengcheng City: 253618; Conghua City: 122654 (2) The data are from Collection of the Second-time Census Data of Fundamental Units of Guangzhou. As census is carried out per five years and the last census was carried out in 2001, so the data in the table were counted at the end of 2001. (3) Some data in the table may be not correct, but they are the most authoritative data available for the project at present. Liede Resettlement Implementation Plan

From the analysis on the employment situation of low-income posts in Tianhe District in aforesaid table we can see that:

(1) In general, the service industry in Tianhe District has a larger demand for labor force and has more posts. It can offer a large number of posts although service sectors increase quickly.

(2) With regard to the PAPs' employment, young women and middle-aged or young men with a certain educational experience enjoy more employment opportunities, while middle-aged women enjoy less such opportunities.

(3) The Project shall facilitate the employment or re-employment training for the PAPs with fewer opportunities or help them find appropriate areas with employment demand on the basis of actual situation.

1.2.4 Analyses of the business environment for small businesses and shops in the project area

Like the employment of the PAPs, the operation of small business and shops is restricted by regional economic environment either. Such economic characteristics of project area result in the quantitative distribution of enterprises and shops of some trades in this district as following table: Liede Resettlement Implementation Plan

______Qu~~~~~ality of Small Businesses and Commnercial Firms in Project Zone Industrial Industrial Subdivision Q'ty of Percentage in the Ranking Remarks type enterprise number of siniilar number of industrial all districts enterprises of the (12 districts) ______~~~~~~~~~~city______1. I.Printing 101 11.60% 3 The long-term development of Tianhe District takes the high-tech Manufacturing 2.Automobile repair 129 17.43% 2 industry as prodominence, which drives the development industry of other new industrialized enterprises. The productive enterprises mainly produce hi-tech products and there are few traditional industrial ______enterprises. 2. Wholesale 1. Wholesale business for food 88 14.64% 1 business supplies and edible oil 2. Wholesale business for westem 47 25.82% 1 medicine 3. Wholesale business for 198 20.56% 1 -construction materials______4.wholesale business for metallic 108 20.04% 1 materials 5.wholesale business for machines 897 3 1.62% 1 and electrical appliances______6. Wholesale business for parts of 236 34.86% 1 Local residents are rich and there is a high possessing ratio of automobile and motorcycle ______automobile and motorcycle. 3. Retail L.retail business for parts of 254 28.29% 1 Local residents are rich andd there is a high possessing business ratio of automobile and motorcycle ______automobile and motorcycle. 2.retail business for computer, 590 49.58% 1 Local residents are of high cultural qualification. There are a software and office equipment large number of persons who can operate computer. The data of year 2002 indicates that the possessing ratio of family computer in Tianhe District is 68.1%, which plays a leading part in Guangzhou City. So, the requirement for repair and parts is comparatively great. 4. Restaurant I.Fast Food 30 8.09% 11 Most restaurants and hotels in Tianhe District are of middle and Liede Resettlement Implementation Plan

Quality of Small Businesses and Commercial Firms in Project Zone Industrial Industrial Subdivision Q'ty of Percentage in the Ranking Remarks type enterprise number of similar number of industrial all districts enterprises of the (12 districts) ciy & beverage 2.Snack 10 2.18% 6 high level and nack and Snack shops are relatively few. business 5. 1.hairdressing and dressing 45 6.88% 5 They are mostly of the middle and high level. Neighborhood 2.commodity repair 27 9.90% 4 services 3.family service 10 16.13% industry . Notes:

(1) Total number of units in different districts: the entire city: 108550; Dongshan District: 14436; Liwan District: 10851; Haizhu District: 12052; Tianhe District: 15315; Fangcun District: 3111; Baiyun District: 15013; Huangpu District: 4795; Panyu District: 11245; Huadu District: 4205; Zengcheng City: 5272; Conghua City: 3949

(2) The data are from Collection of the Second-time Census Data of Fundamental Units of Guangzhou. As census is carried out per five years and the last census was carried out in 2001, so the data in the table were counted at the end of 2001.

(3) Some data in the table may be not correct, but they are the most authoritative data available for the project at present.

-49-~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Liede Resettlement Implementation Plan

From the analysis on the quantitative distribution of small business and shops Tianhe District in aforesaid table we can see that:

(1) The manufacturing industry in Tianhe District is developed. However, due to its priority given to the development of high and new technology industry, only print and vehicle repair are superior to other districts, while other sectors have no comparative advantages and need more attention.

(2) The wholesale business in Tianhe District is developed and are obviously superior to other districts with its wholesale businesses of grain and edible oil, Western medicines, building materials, metals, mechanical and electronic equipment, and spare and component parts for automobiles and motorcycles (totally six) ranking the top, which shows the wholesale businesses of such six trades have a great demand and development space. Therefore, the Project should pay more attention to the shops of other wholesale businesses than these six.

(3) The retail business in Tianhe District is developed either. Compared with other districts, its retail businesses of spare and component parts for automobiles and motorcycles, and computer, software and office equipment have obvious advantages. The Project should pay more attention to the shops of other retail businesses than these two.

(4) The restaurant and beverage industry in Tianhe District is developed. Most are high-grade restaurants and fast food or Fast Food shops are less, which shows the population with high income in Tianhe District inclines to consume at high-grade restaurants instead of fast food or Fast Food shops. Therefore, the fast food or Fast Food shops that need resettlement deserve more attention.

(5) The neighborhood services industry in Tianhe District is developed. Compared with other districts, its hairdressing and beauty culture, maintenance of articles of everyday use and home service industries have advantages. So the Project should pay more attention to the shops of other neighborhood services trades than these three.

1.3 Summarization for Project Resettlement

1.3.1 Explanation for resettlement in the area of Waster Water Treatment Plant

The land requisition for the area of Liede Waster Water Treatment Plant (Phase III) was finished when Liede Phase I and Phase II were under construction in 1995. The total requisitioned land is 431.44 Mu and the affected population of agricultural workers is 1,479. The resettlement of the plant area complies with Chinese Regulative Statute on Liede Resettlement Implementation Plan

Urban House Demolition in 1992 (on the basis of Action Plan for Involuntary Resettlement of Inner Ring Road Works of Guangzhou Urban Center Traffic Project). Because it was happened in 8 years ago, it shall not be discussed in this implementation plan. So, this resettlement plan shall not involve the resettlement problems of this part. Only the resettlement of the resettlers affected by pipeline network shall be discussed.

1.3.1.1 Explanation of total quantity of resettlement involved in this Resettlement Implementation Plan

This Involuntary Resettlement Plan involves a big number of resettlement for the reconstruction of the drainage pipe networks. Drainage pipes are normally laid down under the existing roads. Whenever there is a lay-down of any drainage pipeline under the planned roads or beside the un-cleaned creeks it will involve a big number of resettlement. Obviously, this resettlement shall be carried out when completing the road or embankment construction and it is unreasonable for a drainage pipe project to bear the resettlement for a whole road or whole creek. Therefore, the resettlement for drainage pipelines laid down along the planned roads or un-cleaned creeks which shall be taken as the resettlement caused by the construction of the planned roads or creeks but not caused by this project. Therefore, it is determined as the resettlement of the relevant projects

1.3.1.2 Explanation of the data source of the first edition

The first edition refers to the Involuntary Resettlement Plan submitted to the World Bank in November 2003.

1.3.1.3 Sources of the resettlement data of the first edition As the time of preparation work for the Project is long, so the investigation work of project affected people was carried out on Sep. 27. It is initially predicted that the investigation work will be completed in December, so most of the project affected people data in the Resettlement Planning are not from the field survey, but are confirmed through analysis based upon the geographic information system established by Guangzhou Municipal Planning and Design Institute and historical data collected by GZ Road Engineering and Expansion Office.

Pipe network data are confirmed according to the data in geographic information system. Scope of land requisition, house demolition and existing pipeline relocation is confirmed according to diameters and buried depths of different sewers and scope of temporary land for construction is confirmed according to the working faces required by laying of pipes with different diameters (scope of temporary land requisition). Please see the following table for affected range of sewage pipe network: Liede Resettlement Implementation Plan

Affected Range of Range of Range of Sewage pipeaffected range Range Sewage pipe landof affected temporary land network underground residents on borrow for requisition pipeline the land construction d<=500 D+2*500 d+2*500 D+2*1500 d/2+500+4000

500

800

1200

(1) d refers to diameter of the sewer. 2 means the affected range will be extended to _ mm at the two sides.

(2) Temporary land requisition only counts one side of central line of the pipe network close to central line of the road.

1.3.1.4 Instruction upon data calculation of various real estates affected for the sewage pipe network

Scope for the land requisition, house demolition, pipeline relocation and temporary land requisition for the above-mentioned pipe network are indexed as per geographic information, with detailed calculating methods given below:

1) The data of land requisition and borrowed land include only the quantity outside the existing roads.

2) Calculation of the buildings

(1) The buildings will be decided to demolish completely or by a part only as per the proportion of the scope of the affected part of building against the total area of the original building.

(2) The property right of the building is presumed as per the area it is located together with the character of the building itself.

(3) The usage of the building is presumed as per its location together with the character of the building itself.

3) Number of people and households affected

It is estimated as per number of buildings and the areas thereof while taking average area per head and areas of small businesses etc. for reference. Quantity of farmers is based upon estimation as per average land occupation per head. Liede Resettlement Implementation Plan

4) Data of the existing pipeline

As there lacks detailed data for precise budgetary estimate for the electricity and telecommunication in the GIS data for the pipeline, only normal presumption has been carried out.

1.3.1.5 Evaluation of the precision of the data for the project affected people in the first edition

1) The accuracy of the inventory quantity is acceptable.

(1) The summed data of the land requisition and borrowed land are considerably accurate, but the categorized data have certain error.

(2) The physical data and the actual data for the buildings are mismatched. Through partial site survey, such deviations shall be within the acceptable range as +20%.

(3) As some critical data for the pipeline are short, such as the basic property of the cable etc., the pipeline resettlement made this time has less precision.

2) Less accuracy of data for the project affected people

As the data of project affected people are varying, the data for project affected people (quantity and households) this time has less accuracy. However, this does not affect the budgetary estimate of the resettlement cost.

1.3.2 Explanation of the sources of the resettlement data of the second edition

1.3.2.1 Sources of the resettlement data of the second edition

1. The data of Dashadi Plant site and pump station and the Solid Waste Treatment site were the same as that in the first edition without any change. 2. The scope of resettlement for the sewage network follows the calculation method used for the first edition. 3. Resettlement data of the sewage network including the real estates of the PAPs, the number of the PAPs and the number of the impacted households are all surveyed data. 4. Survey has done for existing pipelines. However since there will be many feedback information provided from relevant agencies the data of this part has therefore not been changed

1.3.2.2 Evaluation of the accuracy of the data in the second edition

1. The inventory data of the housings has been increased greatly compared with that in the first edition and the increasing rate of the classification of the nature of the property right Liede Resettlement Implementation Plan

is even greater. 2. The accuracy of the data has not been changed compared with the first edition. 3. The total number of the PAPs is basically determined. However, since the project is still at the planning stage and there is a number of uncertainties such as the alignment of the pipeline, any possible modification and the definite date of relocation etc. during the survey. Therefore, many potential PAPs gave the information of their households at discretion. Even with the help of the districts and neighborhood committees the data of the households are still incomplete.

1.3.3 Sources of the resettlement data of the third edition

Data in the third edition was formed based on that in the second edition and based on the classification of the data for this project and relevant projects.

1.3.4 Update of the resettlement data

1. The resettlement data in this Involuntary Resettlement Plan have been comprehensively updated based on the data of the census. However, the data of the households and living status are still not exact. These data will be updated before the implementation based on the detailed data provided by the resettlement implementing agencies. 2. During the project implementation, all the fluctuation of the amount of the inventory quantity due to design change or the changes of the PAP's will be traced. 3. During the project implementation, the URRP system will be used to trace different kinds of changes of the resettlement data.

1.3.5 Total quantity of the resettlement

The affected scope of the sewage pipe network in the project shall involve in an administrative district of Guangzhoui City. The length of the acope amounts to 109.90 km. There are a number of resetllers produced in the project. The requisitioned land is 238.44 mu, temporary land requisition is 763.50 mu, the area of the demolished houses is 113,129.43m 2, the length of the removed original pipeline is 59667 m and the involved population of the resetellers is 6,296 of 1,458 families. In addition, there are 636 persons of the involved agricultural worker.

1.3.6 Characteristics of the resettlement

1.3.61 Quantity of project affected people 1. Quantity of project affected people of this project Citizen household: 403 people of 118 households Merchandising business: 438 people of 86 households Liede Resettlement Implementation Plan

Industrial enterprises: 173 people of 32 households Commonweal units: 4 households Rural area:farmers 115 people 2. Quantity of project affected people of relevant projects Citizen household: 1401 people of 447 households Merchandising business: 1686 people of 310 households Industrial enterprises: 2195 people of 461 households Commonweal units: No surveyed data available at present and thus no statistics made herein Rural area:farmers 521 people

1.3.6.2Proportion of the Building Quantities

1. Total quantity of various usages

(1) Total quantity of various usages of this project

Dwelling house: 12305m2

Commercial firms: 3366 m Office: 1003 m2 Plant house and warehouse: 3102 m2 (2) Total quantity of various usages of relevant projects

Dwelling house: 42644m2

Commercial firms: 9798 m2 Office: 4662 m2 Plant house and warehouse: 36249 m2 2. Total quantity of various property rights (1) Total quantity of various property rights of this project Houses with property right: 5707 m2 Houses built on household plot: 9349 m2 Constructions without right of land-use: 3768m2 Undue temporary construction: 420m2 Due temporary construction and illegal structure: 514m2 (2) Total quantity of various property rights of relevants projects Houses with property right: 20936 m2 Houses built on household plot: 42035 m2 Constructions without right of land-use: 17195m2 Undue temporary construction: 7914m2 Due temporary construction and illegal structure: 5273m2 3. Total quantity of various structures (1) Total quantity of various structures of this project Liede Resettlement Implementation Plan

Frame structure 7498m2 Composite structure 8014m 2 Brick and timber structure 3316m2 Simple structure 948m2 (2) Total quantity of various structures of relevant projects Frame structure 35463m2 Composite structure 24583m2 Brick and timber structure 18066m2 Simple structure 12826m 2 1.3.6.3 Quantity of the land requisition and explanation

1. Quantity of the land requisition and explanation

The land requisition for the Project is scattered. There are totally 44.56mu of land requisition along the 109.90km of pipe network, which means land requisition 0.41mu every kilometer.

There is very few cultivated land-use (about 4.45mu) requisitioned for the Project. Most of them are constructed area and the rural roads.

2. Quantity of Affected Land and Explanation of relevant projects For relevant projects, all land requisition is the scattered one, saying on the pipeline network with the length of 109.90 km. The total amount of land requisition is 194.28 mu, that is to say 1.77 mu of affected land per kilometer. The cultivated land affected by the project is farthing. It shall be about 19.5 mu, accounts for 10% of the total affected land that shall be 194.29mu. Most of them are constructed area and the rural roads.

Obviously, the land requisition for the pipe network of the Project has less impact upon production and living of the local community.

1.3.7 Estimation of the resettlement cost

1.3.7.1 Budgetary estimate of the resettlement for the Project

The total resettlement cost allocated to the Project is RiMB 404,839,405.41 thousand Yuan

1.3.7.2 Cost allocation for resettlement of the Project

As per guideline of the special meeting for resettlement cost allocation of the project hosted by the Municipal Utility Administration Bureau and attended by the Municipal Construction Committee on October 28th: for the cost for construction of the pipe network, the resettlement cost for the sewage pipe network along the planned road and planned watercourse shall be born by the Liede Resettlement Implementation Plan

relevant road construction or watercourse rehabilitation project while the cost for those sewage pipe network on the existing roads and watercourses shall be born by the Project.

As per this principle: The resettlement cost allocated to the Project is RMB285,837,819.29Yuan, Thereinto

The resettlement cost allocated to relevant projects is RMB275,424,275.45Yuan

1.4 Measures to be taken to minimize the quantity of resettlement

1) Relocation of buildings and existing pipelines is related mainly to the pipe network, and this decides that we can minimize the project affected people as well as damages to the existing pipelines through optimization of the route of pipe network. At present, we have made the following achievement through the optimized design:

| Before Optiniization After Optiniization Areas Reduced | 231,292.0 135,010.00 96,282.90

2) For relocation of existing pipelines, through optimization of the specific construction proposals during the construction of the sewage pipeline construction, the pipe-jacking technology is adopted to minimize the quantity for pipeline relocation and reduce the cost for resettlement of infrastructure during the resettlement process (See Annex 3 for the proposal of optimization).

We will make reasonable arrangement, such as to reduce the construction period, minimize the temporary resettlement cost for project affected people and reduce the closing period of the enterprises and commercial firms.

1.5 Explanation of this Resettlement Implementation Plan

1.5.1 In obedience to the Resettlement Policy

This "Resettlement Implementation Plan" is part of the "Planning for Involuntary Resettlement of Guangzhou Urban Environment Project" as well as the extension and details of the " Planning for Involuntary Resettlement of Guangzhou Urban Environment Project Resettlement Policy" while it is also the specific execution proposal and standard prepared as per the principles set in the "Resettlement Policy".

1.5.2 Explanation of the chapter arrangement of the Resettlement Implementation Plan

This Resettlement Implementation Plan is divided into 8 parts: resettlement analysis and Liede Resettlement Implementation Plan

its resettlement, compensation and rehabilitation plan, compensation standard for all kinds of properties and relevant costs, information publicity plan, public participation and negotiation, capability development of enforcement body, monitoring and evaluation, project estimate and fund plan.

Among which, resettlement analysis and its resettlement, compensation and rehabilitation plan is separately described by types of project affected people, including description and analysis of resettlement investigation data, description of resettlement site (if necessary) and corresponding resettlement, compensation and rehabilitation plan. As the contents of commonweal and cultural relic are few and similar they are included in Chapter 9. The part is divided into 11 chapters.

1.6 Classification of the impacted areas of the project

1) In urban resettlement project, the area the project affected people located will directly impact the compensation standard, so we divided the area into 6 types according to the local environment, surrounding facilities, traffic, economic development level, population, social environment and land utilization situation.

2) We divided the larger district in the 6 types of districts into 2-6 regions according to road and stream marked with A, B, C, D, E and F for correct confirmation of the area the project affected people located and resettlement site.

3) Notes: the number in 1A, 3B and etc. refers to grade and the letter refers to region.

Attached with: * Regional Grade Division Drawing for Tianhe District * District Division Drawing for Tianhe District

1.7 General list of the affected land and housings

1) Total quantity sheet for Land Requisition and Borrow Affected by Liede Project (Phase IH) (Table 1.2.1) 2) Total quantity List of Area Category of the People and Area Category, Property Right, Usage and Demolition Mode of the Houses Affected by Liede Project (Phase III) (Table 1.2.2) 3) Total quantity List of Number, Structure, Property Right, Usage and Demolition Mode of the Houses Affected by Liede Project (Phase IEl) (Table 1.2.3) 4) Table for Property Right, Usage, Demolition Mode and Distribution of the Houses Affected by Liede Project (Phase E) Liede Resettlement Implementation Plan

2. Status of the resettlement of the property owners and the compensation plan 2.1 Status of the resettlement of the property owners

2.1.1 Type and distribution of the permanently requested land 1) Type and distribution of land permanently requested Table2.1.1.a Grade of Cultivated Land for Distribution rate area land-use construction Subtotal (%) Grade I 0.00 0.00 0.00 0% Grade 2 0.00 21,879.74 21,879.74 14% Grade 3 48.51 35,562.69 35,611.21 22% Grade 4 432.04 32,658.77 33,090.82 21% Grade 5 119.49 8,827.11 8,946.59 6% Grade 6 10,316.78 49,384.83 59,701.60 37% Total 10,916.82 148,313.14 159,229.95 100%

2) Type and distribution of land permanently requested by the project

Table2.1.1.b Grade of Cultivated Land for Distribution rate area land-use construction Subtotal (%) Grade I 0.00 0.00 0.00 0% Grade 2 0.00 3,060.16 3,060.16 10% Grade 3 48.51 3,796.86 3,845.37 13% Grade 4 0.00 6,290.15 6,290.15 21% Grade 5 0.00 7,581.96 7,581.96 26% Grade 6 1,795.06 7,131.91 8,926.97 30% Total 1,843.58 27,861.03 29,704.61 100%

3 ) Type and distribution of land permanently requested by relevant projects

Table2.1.1.c Grade of Cultivated Land for Subtotal Distribution area construction rate (%) Grade I 0.00 0.00 0.00 0% Grade 2 0.00 18,819.58 18,819.58 15% Grade 3 0.00 31,765.84 31,765.84 25% Grade 4 432.04 26,368.62 26,800.67 21% Grade 5 119.49 1,245.14 1,364.63 1% Grade 6 8,521.71 42,252.92 50,774.63 39% Total 9,073.24 120,452.10 129,525.34 100%

2.1.2 Type and distribution of the temporarily requested land 1) Type and distribution of land temporarily requested Table2.1.2.a Grade of Landsfr Subtotal Distribution area Cultivated land construction btalrate (% Liede Resentlement Implementation Plan

Grade I 0.00 0.00 0.00 0% Grade 2 0.00 63,674.96 63,674.96 13% Grade 3 0.03 109,766.19 109,766.21 22% Grade 4 0.00 103,621.75 103,621.75 20% Grade 5 0.00 30,896.43 30,896.43 6% Grade 6 31,823.84 169,218.97 201,042.82 39% Total 31,823.87 477,178.30 509,002.18 100%

2) Type and distribution of land temporarily requested by the project Table2.1.2.b

Grade ofLandfrCultivated land Subtotal Distribution area construction rate() Grade I 0.00 0.00 0.00 0% Grade 2 0.00 9,748.79 9,748.79 11% Grade 3 0.03 10,329.56 10,329.58 12% Grade 4 0.00 15,154.07 15,154.07 17% Grade 5 0.00 26,192.88 26,192.88 29% Grade 6 5,126.50 22,916.76 28,043.26 31% Total 5,126.53 84,342.05 89,468.58 100%

3 ) Type and distribution of land temporarily requested by relevant projects

Table2.1.2.c Grade of C Land for Distribution area Cultivated construction Subtotal rate (%) I Grade I 0.00 0.00 0.00 0% Grade 2 0.00 53,926.17 53,926.17 13% Grade 3 0.00 99,436.63 99,436.63 24% Grade 4 0.00 88,467.69 88,467.69 21% Grade 5 0.00 4,703.56 4,703.56 1% Grade 6 26,697.34 146,302.21 172,999.55 41% Total 26,697.34 392,836.26 419,533.60 100%

2.1.3 Property right and distribution of the temporarily affected buildings

1) Pro perty right and distribution of buildings temporarily affected Grade of area % of Property right Grade I Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Total property Housing with property right - 785.02 822.28 1,573.09 597.52 1,383.26 5,161.17 22% Housing on residential plot - 139.69 7,072.58 1,280.44 - 2,339.53 10,832.24 47% Constructions without right of land-use - 156.08 780.64 747.42 334.32 1,808.86 3,827.32 17% Temporary structure before expiration - 170.05 337.01 884.94 - 720.54 2,112.54 9% Temporary structure after expiration or illega structure - - 349.21 212.42 - 643.61 1,205.25 5% total - 1,250.85 9,361.72 4,698.31 931.84 6,895.80 23,138.51 100% Liede Resettlement Implementation Plan

Distribution | l 1l0% | rate () a 0% 5% | 40% | 20% | 4% | 30% | 100% l See Table2.1.3 for the detail 2) Property right and distribution of buildings temporarily affected by this project

Grade of area % of Property right Total property Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 right Housing with property right - 210.09 103.62 597.52 143.08 1,054.31 26% Housing on residential plot 109.33 1,306.80 508.29 1,924.42 48% Constructions without right of land-use 4.63 243.58 53.84 224.46 325.54 852.06 21% Temporary structure before expiration 52.53 55.72 108.24 3% Temporary structure after expiration or illegz structure 57.28 14.32 18.93 90.53 2% total - 113.96 1,870.29 227.50 821.98 995.83 4,029.56 100% Distribution rate (%) 0% 3% 46% 6% 20% 25% 100% i See Table2.1.3 for the detail 3) Property right and distribution of buildings temporarily affected by relevant projects

Grade of area % of Property right Grade Total property 1 Grade 2 Grade 3 Grade 4 GradeS5 Grade 6 right Housing with property right 785.02 612.19 1,469.47 - 1,240.18 4,106.86 21% Housing on residential plot 30.36 5,765.77 1,280.44 1,831.25 8,907.82 47% Constructions without right of land-use 151.45 537.06 693.58 109.86 1,483.32 2,975.26 16% Temporary structure before expiration 170.05 284.48 829.22 720.54 2,004.30 10% Temporary structure after expiration or illega structure . 291.93 198.10 624.69 1,114.72 6%

total - 1,136.89 7,491.43 4,470.81 109.86 5,899.97 19,108.95 100% Distribution rate (%) 0% 6% 39% 23% 1% 31% 100% 0% See Table 2.1.3 for the detail

2.1.4 Property right and distribution of partially but permanently affected buildings

1) Property right and distribution of buildings partially but permanently affected Liede Resettlement Implementation Plan

Grade of area % of Property right Total property ProerGrade t Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Trght Housing with property right - 1,738.65 2,208.97 6,418.82 1,747.67 3,239.10 15,353.20 26% Housing on residential plot - 203.03 14,546.28 3,755.60 - 4,989.86 23,494.78 40% Constructions without right of land-use - 439.92 2,888.22 3,336.05 1,276.82 4,363.45 12,304.46 21% Temporary structure before expiration - 434.34 719.86 2,349.77 - 1,400.25 4,904.23 8% Temporary structure after expiration or illegal structure - 27.11 865.63 611.81 - 1,773.82 3,278.38 6% total - 2,843.05 21,228.97 16,472.05 3,024.49 15,766.49 59,335.05 100% Distribution rate l (%) 0% 5% 36% 28% 5% 27% 100% l See Table2.1.4 for the detail 2) Property right and distribution of buildings partially but permanently affected by this project

Grade of area %of Property right Grade Grade 2 Grade 3 Grade 4 Grade S Grade 6 Total property

Housing with property right - 12.93 172.31 747.87 1,747.67 417.68 3,098.45 36% Housing on residential plot - 1,510.09 226.80 - 1,001.80 2,738.68 32% Constructions without right of land-use - 39.49 432.64 179.27 673.50 855.44 2,180.35 25% Temporary structure before expiration - 117.90 49.01 54.58 221.49 3% Temporary structure after expiration or illegal structure - 27.11 68.50 11.06 221.68 328.35 4% total - 79.53 2,301.43 1,214.01 2,421.17 2,551.18 8,567.33 100% Distribution rate (%) 0% 1% 27% 14% 28% 30% 100% l See Table2.1.4 for the detail 3) Property right and distribution of buildings partially but permanently affected by relevant projects Grade of area % of Property right Grade Total property Gr.Grade 2 Grade 3 I Grade.4 Grade 6 right Housing with property right - 1,725.71 2,036.67 5,670.95 - 2,821.43 12,254.75 24% Housing on residential plot - 203.03 13,036.20 3,528.80 - 3,988.07 20,756.09 41% Constructions without right of - 400.43 2,455.58 1 3,156.77 603.32 3,508.01 10,124.11 20% Liede Resettlement Implementation Plan

land-use Temporary structure before expiration 434.34 601.96 2,300.76 1 ,345.67 4,682.74 9% Temporary structure after expiration or illegal structure 797.14 600.75 1,552.14 2,950.02 6% total - 2,763.52 18,927.54 15,258.04 603.32 13,215.31 50,767.72 100% Distribution rate (%) 0% 5% 37% 30% 1% 26% 100% See Table 2.1 .4for the detail

2.1.5 Property right and distribution of wholly and permanently affected buildings 1) Propert right and distribution of buildings wholly and permanently affected Grade of area % of Property right Total property Prope t Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 right Housing with property right 949.84 414.35 3,151.94 993.84 619.14 6,129.12 20% Housing on residential plot 142.92 12,464.42 2,053.63 - 2,396.18 17,057.14 56% Constructions without right of land-use 668.55 759.37 1,687.68 128.60 1,605.06 4,849.26 16% Temporary structure before expiration 471.33 719.09 127.13 1,317.55 4% Temporary structure after expiration or illegal structure 229.26 28.78 744.64 - 300.12 1,302.80 4% total - 1,990.57 14,138.26 8,356.99 1,122.43 5,047.62 30,655.88 100% Distribution rate (%) 0% 6% 46% 27% 4% 16% 100% See Table2.1.5 for the detail 2) Property right and distribution of buildings wholly and permanently affected by this project

Grade of area % of Property right Grade Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Totrl proghty Housing with property right 201.19 348.57 993.84 11.13 1,554.71 22% Housing on residential plot 18.02 4,256.58 - - 411.25 4,685.85 65% Constructions without right of land-use 137.40 446.59 125.27 44.39 - 753.65 10% Temporary structure before expiration 90.37 90.37 1% Temporary structure after expiration or illegal structure 14.40 47.83 - 32.74 94.97 1% Liede Resetlement Implementation Plan

total - 155.42 4,918.76 521.66 | 1,038.22 | 545.50 7,179.55 I 100% I Distribution rate (%) 0% 2% 69% 7% 14% 8% 100% See Table2.1.5 for the detail

3) Property right and distribution of buildings wholly and permanently affected by relevant projects Grade of area %o Property right Total property Grade Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 Ttght Housing with property right - 949.84 213.17 2,803.38 608.02 4,574.40 19% Housing on residential plot - 124.90 8,207.84 2,053.63 1,984.92 12,371.29 53% Constructions without right of land-use 531.16 312.78 1,562.41 84.21 1,605.06 4,095.62 17% Temporary structure before expiration 471.33 719.09 36.76 1,227.18 5% Temporary structure after expiration or illegal structure 229.26 14.39 696.82 - 267.37 1,207.83 5% total e 1,835.16 9,219.50 7,835.32 84.21 4,502.13 23,476.32 100% Distribution rate (%) 0% 8% 39% 33% 0% 19% 100% See Table 2.1.5. for the detail

2.1.6 Status of the structures, attachments and housing facilities There are mainly structures relating to the pipelines. Refer to tables of cost estimation in Chapter 18 for the detail.

2.1.7 Status of the infrastructure

There are mainly structures and pipelines. Refer to tables of cost estimation in Chapter 18 for the detail 2.1.8 Analysis of the income of the property owners Surveys show that the many owners of the buildings with market rentals have some property income besides the income from their occupations.

According to the requirement of the World Bank, the income of the property owners shall be analyzed and reported in detail. We designed the special questionnaire for the census accordingly and carried out the training to the inquirers. Districts, neighborhood committees and villages were also asked to provide assistance. However, since the PAPs are not aware enough of the importance of the survey and worried that if they have property leased the compensation may be reduced, and also because the alignment of the survey is too long and time is too short the data obtained through the survey are not the satisfaction to the World Bank. In order to meet the requirement of the World Bank the agency responsible for the preparation of the Involuntary Resettlement Plan has taken the following measures: Liede Resettlement Implementation Plan

Only those who have the property on lease (house or land) may be impacted by the project. The loss of the income of the PAPs can then be calculated based on the local rental rate of the house and land and the number of the houses affected. Therefore, surveys on the rentals according to the district, the area grade and the usage and property right of the house were carried out by the agency responsible for the preparation of the Involuntary Resettlement Plan. Rentals of houses surveyed are as follows: Unit: yuan/m2 Area grade \Usae 1 2 3 4 5 6 Property iht Residence 23.4 15.2 9.4 7.8 5.71 4.5 W ith__ _ _ _ Shop 83.4 42.7 21.6 12.9 8.1 6.4 property Office 48.2 36.4 18.1 9.5 7.2 4.6 right Plant structure 13.6 8.3 6 4.2 Residence 6.4 5 4.3 3.2 Residential Shop 10.7 8.6 6.7 5.4 plot Office 9.1 8.5 5.3 5 Plant structure 8 6.1 4.2 3 Residence 4.5 3.7 2.6 Tem./illegal Shop 19.4 12.6 7.1 5 Structure Office 11 9.7 6 4.3 Plant structure 7.3 5.1 4.8 2.5 Rentals of land surveyed are as follows: Grade 1: 12 yuan/mr2 Grade 2: 10 yuan/m2 Grade 3: 7 yuan/rn2 Grade 4: 4.5 yuan/m2 Grade 5: 2.5 yuan/r 2 Grade 6: 1.5 yuan/mr2 The survey shows that as these residential plots are located inside the villages in urban area and because of the environment issues around them the rental of these residential plots is much lower than that of the house with property right and even lower than that of the temporary structures. Furthermore, the compensation paid by the project will be enough to purchase a house with same area and therefore the income from the rentals will not be reduced. 2.1.9 Statistics of the distribution of the owners of the house without property right See following table for the detail. Liede Resettlement Implementation Plan

Unit Individual Total Property Area Floor area Floor area Floor area right Quantity .Quantity. grade demolished Quantity demolished demollshed

2 ~~~22.00 1,264.56 22.00 1,264.56

Constructions 3 55.00 4,428.23 55.00 4,428.23

without right 4 68.00 5,771.15 68.00 5,771.15 of land-use 5 21.00 1,739.75 21.00 1,739.75

6 ~~~143.00 7,777.36 143.00 7,777.36

Tolal ~309.00 20,981.04 309.00 20,981.04 2 2 ~~~4.00 604.39 4.00 604.39

3 ~~~30.00 1,477.49 3.00 50.72 33.00 1,528.20

Temporary4 ~~~21.00 3,800.62 3.00 153.18 24.00 3,953.80

Toa 20.00 2,068.17 1.00 179.75 21.00 2,247.92

TOlal ~75.00 7,950.67 7.00 383.65 82.00 8,334.32

2 ~~~2.00 256.37 01 0 2.00 256.37

3 ~~~12.00 1,066.57 4.00 177.06 16.00 1,243.63 Illegal 4 39.00 1,424.75 4.0014.3300,588

6 ~~~36.00 2,548.27 3.00 169.28 39.00 2,717.54

Tolal ~89.00 5,295.95 11.00 490.47 100.00 5,786.42

2 ~~~28.00 2,125.32 0 28.00 2,125.32

3 97.00 6,972.28 7.00 227.78 104.00 7,200.06

Total 4 128.00 10,996.52 7.00 297.32 135.00 11,293.83

621.00 1,739.75 3- D 21.00 1,739.75 . ~~~199.00 12,393.81 4.00 349.03 203.00 12,742.83-

i Total ~~~~~~ ~~~473.0034,227.66 18.00 874.12 1 491.00 35,101.79 LL=: Reeteet opnainadrhbltto='2. ln o rpryonr Liede Resettlement Implementation Plan

2.2.1 Resettlement, compensation and rehabilitation principles for property owners 1) The property owners of permanently requisitioned land, building, structure, attachment, housing facilities and infrastructure will gain compensation according to the specifications in Section 5.7.1 of the Resettlement Policy. The project will also take the following rehabilitation measures:

(1) Payment of the specified compensation for the property owner will be carried out after signing of the compensation contract and completed after all procedures are transacted.

(2) The Project will rehabilitate the nonindependent structure (connected with other building not demolished) permanently or partially requisitioned in time to reduce the impact on integral function of the building.

(3) The taxes relevant to the requisitioned land of the year levied by the government will be deducted from the taxes of the next year.

2) Rental compensation for temporarily requisitioned land will be paid according to Section 5.7.1.2 of the. The Project will also take the following rehabilitation measures:

(1) The Project will be responsible for rehabilitation of original functions of the affected non-cropland within 6 months.

(2) The Project will pay the property owner of the requisitioned tillable field the tillable field rehabilitation fee. The property owner will rehabilitate the tillable field by himself.

(3) As most pipe networks will be laid on the planned roads, so the administration authority of roads, green spaces and other public facilities in the requisition range will be transferred from the village to the municipal government. The property owner will gain the compensation and functions of the original roads will be strengthened. The municipal government will be responsible for the maintenance cost.

(4) The land around the temporarily requisitioned land and type of buildings on the land are also taken into consideration besides the policies relevant to compensation price of land requisition during temporary requisition of land. The detailed compensation standard was already regulated according to these factors.

(5) Construction period shall be reasonably arranged, so that the temporary requisition period will not exceed half a year. Liede Resettlement Implementation Plan

3) Besides the compensation specified in Resettlement Policy, the property owner of partially but permanently demolished buildings will gain:

(1) If the property owner of partially demolished buildings is seriously impacted, he may apply for resettlement and will enjoy the resettlement house discount(10%) because of group purchase of the Project.

(2) Partially demolished houses will be rehabilitated as soon as possible and construction safety will be guaranteed. If there is vacant land beside the partially demolished house, the house will be translated to reduce the impact.

(3) Rehabilitation period of the remaining houses after partial demolition can't exceed half a year.

4) The property owner of provisionally affected building will gain the specified compensation. The Project also promises that the temporary requisition period will not exceed one year. If it exceeds one year the project will promise to provide the compensation for temporary relocation. See Item 8 of Section 13.3 of this Plan.

5) The property owner of the structure to be individually rehabilitated may select compensation and self-rehabilitation or reconstruction by the Project.

6) The Project will firstly rehabilitate the infrastructures prior to demolition to prevent the impact on residents because of suspension in the service range.

2.2.2 Procedure and methodology of the resettlement, compensation and rehabilitation for property owners

See Section 5.10.1 of the Resettlement Policy for the detail.

2.2.3 Schedule of the resettlement, compensation and rehabilitation for property owners

See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resettlement Implementation Plan

3. Status of the PAPs who rent the houses with market-price and the resettlement, compensation and rehabilitation plans for them

3.1 Status of the PAPs who rent the houses with market-price

1. The detail of the property right, usage, demolition method and area grade of the PAPs who rent the houses with market price can be seen in Table 3.1.1. 2. The detail of the structure, usage and area grade of the houses with market price can be seen in Table 3.1.2.

3.1.1 Distribution of the housings with market rentals

3.1.1.1 Wholly and permanently affected housings with market rentals (See Table 3.1.1.1 for the detail)

3.1.1.2 Partially but permanently affected housings with market rentals

1) Property right and distribution of housings with market rentals

Grade of area Property Grade I Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 right (%) House with property right - 430.17 850.06 375.99 195.57 115.29 1,967.08 83% House on residential plot 0% Constructions without right of land-use - 0% Undue temporary

structure - 0% Due tem. /illegal

Structure - - 134.40 197.16 - 73.10 404.66 17% Total - 430.17 984.46 573.15 195.57 188.39 2,371.74 100% Distribution (%) 0% 18% 42% 24% 8% 8% 100% See Table 3.1.1.2 for the detail 2) Structure and distribution of housings with market rentals

Area grade Structure A Structure B Structure C Structure D Total Liede Resettlement Implementation Plan

Grade I

Grade 2 - 430.17 430.17 Grade 3 255.81 - 594.25 134.40 984.46 Grade 4 375.99 48.32 - 148.84 573.15 Grade 5 195.57 - - 195.57 Grade 6 188.39 188.39 Total 1,015.76 478.49 594.25 283.24 2,371.74

3.1.1.3 Temporarily affected housings with market rentals

1) Property right and distribution of housings with market rentals temporarily affected Grade of area Property Property right Total Grade I Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 right (%) House with I

property right - 196.80 269.50 228.23 161.70 856.23 88% House on residential plot 0% Constructions without right of land-use 0% Undue temporary structure 39.80 6.90 46.71 5% Due tem. /illegal

Structure-- 5.98 44.66 - 18.00 68.63 7% Total - 196.80 315.28 51.56 228.23 179.70 971.58 100% Distribution (%) 0% 20% 32% 5% 23% 18% 100% 0% See Table 3.1.1.3 for the detail 2) Structure and distribution of housings with market rentals

Area grade Structure A Structure B Structure C Structure D Total

Grade I

Grade 2l 551.88 229.26 781.14 Grade 3 - - - 55.38 55.38 Grade 4 676.21 676.21 Grade 5

Grade 6 Total______554.25 90.37 25.19 669.81 Total 1,106.14 90.37 986.03 2,182.54 Liede Resettlement Implementation Plan

3.1.2 Property right and distribution of the shops with market rentals

3.1.2.1 Wholly and permanently affected shops with market rentals (See Table 3.1.2.1 for the detail 3.1.2.2 Partially but permanently affected shops with market rentals 1) Property right and distribution of shops with market rentals

Property right of area TotalGradeProperty Grade I Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 right (%) House with property right 690.31 43.48 733.79 ___ House on

residential plot - - 355.56 280.94 - 316.48 952.98 21 Constructions without right of

land-use 31.61 364.28 131.87 1,204.83 1,732.60 Undue temporary

structure - - 684.67 206.85 891.52 20% Due tem. /illegal

Structure 27.11 129.86 7 156.97 4% Total 58.72 355.56 1,459.75 822.17 1,771.64 4,467.86 100% Distribution (%) 0% 1% 8% 33% 18% 40% 100% _ See Table 3.1.2.2 for the detail 2) Structure and distribution of shops with market rentals

Area grade Structure A Structure B Structure C Structure D Total

Grade I

Grade 2 - 31.61 27.11 58.72 Grade 3 161.99 13.76 - 179.81 355.56 Grade 4 -1 1,308.39 42.17 109.19 1,459.75 Grade 5 366.64 323.67 131.87 822.17 Grade 6 Total 454.51 350.41 485.60 481.13 1,771.64 983.13 2,027.85 659.63 797.24 4,467.86

3.1.2.3 Temporarily affected shops with market rentals 1) Property right and distribution of shops with market rentals Property right I Grade of area | Total Property Liede Resettlement Implementation Plan

Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 right ( House with

property right - - - - 210.15 2.04 212.19 12% House on residential plot 129.88 66.69 - 190.65 387.22 21 % Constructions without right of

land-use - 4.63 58.02 516.12 578.76 32%_ Undue temporary

structure - - 12.18 511.21 52.88 576.26 32% Due tem. /illegal Structure - 10.50 40.64 - - 51.14 3%j

Ton - 4.63 152.56 618.53 268.17 761.69 1,805.58 100%

Distribution (%) _ 0% 0% 8% 34% 15% 42% 100% See Table 3.1.2.3 for the detail I 2) Structure and distribution of shops with market rentals temporarily affected

Area grade Structure A Structure B Structure C Structure D Total

Grade 1

Grade 2

Grade 3 303.33 64.05 32.30 399.68 Grade 4 - 249.02 78.97 327.99 Grade 5 87.32 731.89 - 819.20 Grade 6 - 60.36 36.76 22.34 119.46 Total 390.65 1,105.32 36.76 133.61 1,666.34

3.1.3 Property right and distribution of the enterprises with market rentals

3.1.3.1 Wholly and permanently affected enterprises with market rentals (See Table 3.1.3.1 for the detail) 3.1.3.2 Partially but permanently affected enterprises with market rentals 1) Property right and distribution of enterprises with market rentals Grade of area Property Property right Total right Property right Grade 1 Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 (%)

House with property right 112.67 - 893.49 932.81 1,938.97 16% House on residential plot 1,181.27 4.75 109.36 1,295.38 11% Liede Resettlement Implementation Plan

Constructions without right of land-use - 178.35 321.19 1,090.93 607.55 1,369.61 3,567.61 29% Undue temporary structure - 434.34 633.47 986.52 - 1,163.57 3,217.91 26% Due tem. /illegal

Sotructur - 678.96 11.06 - 1,513.70 2,203.72 18% Total - 725.36 2,814.89 2,986.75 607.55 5,089.04 12,223.59 100% Distribution (%o) 0% 6% 23% 24% 5% 42% 100% See Table 3.1.3.2 for the detail 2) Structure and distribution of enterprises with market rentals

Area grade Structure A Structure B Structure C Structure D Total

Grade 1

Grade 2 201.42 283.14 240.79 - 725.36 l Grade 3 - 95.10 1,196.99 1,522.81 2,814.89 Grade 4 428.46 391.72 1,062.58 1,103.99 2,986.75 Grade 5 - 196.27 411.27 - 607.55 Grade 6 Total______1,356.67 29.32 2,220.44 1,482.62 5,089.04 Total 1,986.55 995.55 5,132.07 4,109.42 12,223.59

3.1.3.3 Temporarily affected enterprises with market rentals 1) Property right and distribution of enterprises with market rentals Grade of area Poet Property right Total Property Grade I Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 nght (%) House with

property right - 36.51 - 295.12 _ 379.64 711.26 17%1 House on

residential plot - - 414.31 45.06 459.37 11%1 Constructions without right of land-use 49.71 117.77 276.95 76.20 452.74 973.37 23% Undue temporary structure 170.05 277.00 210.23 - 647.56 1,304.83 31% Due tem. /illegal I Structure 2 - 306.02 - - 495.36 801.38 19%

Total 256.27 1,115.09 782.30 76.20 2,020.35 1 4,250.21 1 100%j Liede Resettlement Implementation Plan

Distribution (%) I 0% | 6% | 26% | 18% 1 2% | 48% | 100% See Table 3.1.3.3 for the detail 2) Structure and distribution of enterprises with market rentals

Area grade Structure A Structure B Structure C Structure D Total

Grade I

Grade 2

Grade 3 5.59 - 67.84 119.68 193.11 Grade 4 167.46 90.79 166.50 424.75 Grade 5 20.09 - - 20.09 Grade 6 17.08 225.39 358.11 113.11 713.68 Total| Total_____ 22.67 412.94 516.74 399.29 1,351.64

3.1.4 Status of the commonweal units with market rentals affected

There is not any of these'units affected by this project.

3.2 Resettlement, compensation and rehabilitation plans for the PAPs who rent the houses with market-price

3.2.1 Resettlement, compensation and rehabilitation principles for PAP's with market-price rental The project affected people that rent houses with market-price will obtain the following helps besides the compensation specified in Resettlement Policy: 1) Households that rent houses with market-price (1) The Project will help the citizen households that rent houses with market-price find a resettlement site with basically the same house type, living environment and rental. (2) If the citizen households that rent houses with market-price want to buy houses, they will enjoy the preferential price enjoyed by the property owner during group purchase of resettlement houses. 2) Shops with market rentals (1) If the commercial firm is willing to rent another house, the Project will help the commercial firm find a house with basically the equivalent type, management environment and rental. If the house is within the group purchase range, the Project will negotiate with the Developer about 5% of the rental. (2) If the commercial firm wants to purchase a house, he will enjoy the preferential price enjoyed by the property owner during group purchase of resettlement houses. Liede Resettlement Implementation Plan

(3) If the tenant wants to rent another commercial firm or change his profession, the Project will help him find a suitable commercial firm in a specialized market with good management environment to promote his original operation level. 3) Partially demolished houses with market-price

The Project will negotiate with the property owner of partially demolished houses after rehabilitation to preferentially lease the houses to the original tenants.

Note: It is generally easy for this part of the PAPs to rent the houses or production sites from nearby areas. Therefore, the impact of the project on them is quite small. }

3.2.2 Procedure and methodology of the resettlement, compensation and rehabilitation for the PAPs with market rentals

1. Procedures and methods with generality are included in Section 5.10.1 of the Resettlement Policy.

2. The resettlement of the PAPs with market rentals will either continue to rent the houses from the original owner or rent other houses nearby.

E}3. Determine whether the lease agreement is due

* For those whose agreement is due negotiation will be carried out with the PAPs to see whether they are willing to find the houses by themselves and the compensation for removal will be provided. For those who are not willing to find the house themselves or can not fine any the project will be responsible to find a similar house on lease or the PAP can search the house in the Urban Resettlement Resource Planning system. * For those whose agreement is undue, the agreement will be executed as a due agreement if there is such a statement in the agreement "the user shall move out of the structure at the time when the resettlement of project starts". * For those whose agreement is undue if there is not such a state in the agreement as ""the user shall move out of the structure at the time when the resettlement of project starts" negotiation between the house owner and the PAP is then required. If the negotiation fails the project will relocate the owner of the house and the PAP who rent the house with market price will continue to rent house from the same owner.

(Note: the previous statistics show that the ratio of those who continue to rent the house from original owner is very small. The reason is it is easy for those whose rent houses with market price to obtain similar ones for living or production outside the project affected areas.)

4. If the PAPs are willing to purchase the resettlement housings the following options will be provided to them: Liede Resettlement Implementation Plan

*House: not less than 10 resettlement areas with totally 1000 apartments; *Shops: not less than 5 resettlement areas with totally 100 buildings *Offices: not less than 5 resettlement areas with totally 200 buildings *Factory buildings and warehouses: not less than 3 resettlement areas with totally 50 buildings.

45.The project resettlement staff will discuss with the PAPs about the compensation for removal, the time of removal, the method of removal and the stop-loss caused by the removal and agree on the compensation price.

*If the PAPs agree the contract of compensation will be signed. *If the PAPs do not agree it will then go into the evaluation procedure.

3.2.3 Resettlement, compensation and rehabilitation schedule for PAP's with market-price rental

See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resettlement Implementation Plan

4. Status of the PAPs whose property is temporarily affected and the resettlement, compensation and rehabilitation plans for them

4.1 Status of the PAPs whose property is temporarily affected 4.1.1 Temporarily affected housings and their distribution 1) Property right and distribution of temporarily affected housings

Grade of area % of Total property Property right Grade Grade 2 Grade 3 Grade 4 Grade 5 Grade 6 right

Housing with property right 253.58 354.28 199.26 151.17 270.41 1,228.70 13% Housing on residential plot 109.33 4,808.62 479.98 - 1,951.97 7,349.91 75% Constructions without right of land-use 21.53 111.15 0.01 6.55 742.38 881.61 9% Temporary structure before expiration - 8.03 136.07 - 17.00 161.09 2% Temporary structure after expiration or illeg structure - 51.19 - 110.25 161.44 2% total - 384.44 5,282.08 866.51 157.72 3,092.00 9,782.74 100% Distribution rate (%) 0% 4% 54% 9% 2% 32% 100% See Table 4. 1.1 for the detail 2) Structure and distribution of temporarily affected housing

Grade of Composite Brick and Simple areadeo Framework structite timber Simple total structure Grade I Grade 1 Grade 2 234.28 128.63 21.53 - 384.44

Grade 3 3,188.97 1,864.42 206.66 22.03 5,282.08

Grade 4 132.72 570.93 29.77 133.10 866.5 i

Grade 5 125.32 32.40 - - 157.72

Grade 6 1,619.05 451.76 295.03 164.06 3,092.00

total 5,300.34 3,048.14 552.99 319.18 9,782.74

4.1.2 Temporarily affected shops and their distribution 1) Property right and distribution of temporarily affected shops Property right Grade of area I Total| Liede Resettlement Implementation Plan

%of Grade Grade ~~~~~~~~~~property Gde 2 Grade rade Grade rade Grade 6 right 3 4

Housing with property right 28.10 - 275.59 7.96 67.68 379.33 30% Housing on residential plot 30.36 349.48 414.56 - 66.38 860.77 67% Constructions without right of land-use - 28.08 11.18 39.26 3% Temporary structure before expiration 0% Temporary structur after expiration or illegal structure 0% total - 58.45 377.56 701.33 7.96 134.06 1,279.37 100% Distribution rate (%) 0% 5% 30% 55% 1% 10% 100% I See Table 4.1.2 for the detail 2 ) Structure and distribution of temporarily affected shops

Grade of CFrameworkomposite Brick and Simple total area structure timber structure structure Grade I

Grade 2 18.02 18.02

Grade 3 165.66 45.30 102.74 - 313.71

Grade 4 772.39 277.31 410.10 43.67 1,503.46

Grade 5 - - 64.13 - 64.13 Grade 6

Total 938.05 322.61 576.97 61.69 1,899.31

4.1.3 Temporarily affected enterprises and their distribution 1) Property right and distribution of temporarily affected enterprises

Grade of area % of Property right Grade Grade Total proigphrty Gae Grade 2 Grade4 Grade 5 6ih 3 6~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Housing with property right 153.75 185.53 282.14 - 313.49 934.91 32% Housing on residential plot - 1,059.83 18.34 - - 1,078.17 37% Constructions without right of land-use - 335.18 440.73 - 97.31 873.23 30% Temporary structure before expiration 0% Temporary structur after expiration or illegal structure 40.11 8.08 48.18 2% Liede Resettlement Implementation Plan

Total - 153.75 1,580.55 781.32 - 418.88 2,934.50| 100% Distribution rate

See Table4.1.3 for the detail 2 ) Structure and distribution of temporarily affected enterprises

_composite Brick and Simple Grade of area Framework Composite timber stuurtoa t structure sstucctur Grade I

Grade 2 462.42 132.90 - 121.78 717.09

Grade 3 - 156.20 381.01 157.26 694.47

Grade 4 153.56 757.07 134.77 1,045.41 Grade 5

Grade 6 - 248.01 - 248.01

total 462.42 442.66 1,386.09 413.81 2,704.97

4.1.4 Temporarily affected commonweal units and their distribution There are not any such units found during the survey.

4.2 Resettlement, compensation and rehabilitation plans for the PAPs whose property is temporarily affected

The project affected people whose houses are temporarily requisitioned will obtain the following helps besides the compensation specified in Resettlement Policy:

4.2.1 Resettlement, compensation and rehabilitation principles for temporarily requested housings

(1) If the rehabilitation period exceeds that specified in the contract, the Project will give additional 50% of the transport allowance besides the compensation specified in relevant policy

(2) If the temporary relocation period is more than 1 year and the children of project-affected people have to transfer to other schools two or more times, the Project will give additional allowance;

(3) If the temporary relocation period exceeds that specified in the contract, the temporary relocation fee shall be increased to 100% more than the -original specifications

(4) During reconstruction of houses, type and spacing of the house shall meet the requirements of the households under the precondition of reciprocal compensation. Frame structure shall be adopted. Liede Resettlement Implementation Plan

(5) Temporary relocation period of residence refers to the month of removal to the month of house delivery;

(6) The project affected people may select to get the relocation fee or the Project will arrange the relocation.

4.2.2 Resettlement, compensation and rehabilitation principles for temporarily requested shops

(1) If the rehabilitation period exceeds that specified in the contract, the Project will give additional 100% allowance besides the compensation specified in relevant policy

(2) If the commercial firm wants to change his profession, the Project will regulate internal structure and functions of the reconstructed house according to the actual requirements, but the planning requirements shall be met and reconstruction cost of the Project can't be increased. If the cost exceeds the range of reciprocal compensation, the Project will strike the balance with the property owner based upon the construction cost price.

(3) If the User wants to purchase a house, he will enjoy the preferential price because of group purchase of resettlement houses;

(4) If the User wants to rent another commercial firm, the Project will help him find a suitable commercial firm in a with specialized market with good management environment to promote his original operation level;

(5) Temporary relocation period of commercial firm is from the month of removal to the Month of house delivery and additional 15 days will be given as operation rehabilitation period (the time will be continuous);

(6) The project affected people may select to get the relocation fee or the Project will arrange the relocation.

4.2.3 Resettlement, compensation and rehabilitation principles for temporarily requested enterprises

(1) If the rehabilitation period exceeds that specified in the contract, the Project will give additional 50% allowance besides the compensation specified in relevant policy

(2) If the enterprise wants to change his profession, the Project will help him find a suitable factory building and office location in corresponding industry park to promote his original operation level;

(3) The house may be reconstructed to a building with other purposes out of factory building, but the planning requirements shall be met;

(4) If equipment commissioning is difficult, the Project will give help to the enterprise in terms of the installation and commissioning (including the fee for invitation of experts) to Liede Resettlement Implementation Plan

shorten the operating suspension period and reduce the loss;

(5) Temporary relocation period of enterprise is from the month of removal to the month of house delivery and additional equipment commissioning period will be given according to actual requirements of the enterprise (the time will be continuous);

(6) The project affected people may select to get the relocation fee or the Project will arrange the relocation.

4.2.4 Resettlement, compensation and rehabilitation plans for temporarily requested commonweal units

1) If the rehabilitation period exceeds that specified in the contract, the Project will give additional 70% allowance besides the compensation specified in relevant policy

2) If the temporarily requisitioned commonweal units possesses the social service function necessary for the community, such as the unique hospital and school of the community, the resettlement site will be arrange in the community;

3) Temporary relocation period is from the month of removal to the month of house delivery and additional 1 month will be given as rehabilitation period (the time will be continuous);

4) The project affected people may select to get the relocation fee or the Project will arrange the relocation.

4.2.5 Procedure and methodology of the resettlement, compensation and rehabilitation for the PAPs temporarily affected

1. Procedures and methods with generality are included in Section 5.10.1 of the Resettlement Policy.

2. The compensation for temporarily removal, the temporary resettlement housings, the reconstruction standard, the compensation for stop-loss and the expenses for the removal will be discussed with the PAPs.

3. If the PAPs do not think the house needs reconstruction the compensation can be carried out according to the replacement price of the house.

4. Whenever there is a dispute about the compensation for temporary removal, the replacement price and the compensation for stop-loss etc. an intermediary Company can be entrusted for the evaluation.

5. The opportunity of selection of the houses for temporary relocation and the resettlement housings is the same.

6, A big number of resettlement will be caused for the sewage pipe network. However, the shops and enterprises affected by the pipe network are all those with small scale and therefore, they do not have high requirement of the relocation. Whenever there is Liede Resettlement Implementation Plan any special requirement the project resettlement implementing agencies will help them to reconstruct the buildings so as to ensure that their employees will not loss their jobs due to the resettlement and compensation for the real stop-loss will be provided.

4.2.6 Resettlement, compensation and rehabilitation schedule for the PAPs temporarily affected

See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resettlement Implementation Plan

5.Status of the PAPs whose property is partially but permanently affected and the resettlement, compensation and rehabilitation plans for them 5.1 Status of the PAPs whose property is partially but permanently affected

5.1.1 The partially but permanently affected housings 1) Property right and distribution of partially but permanently affected housings

Grade of area _____ Total % of Property right Grade Gaeproperty Grade 2 Grade 3 Grade 4 Grade 5 Grade right Housing with property right - 406.57 481.58 872.26 809.56 619.05 3,189.01 15% Housing on residential plot - - 8,852.52 2,507.68 - 4,179.63 15,539.83 72% Constructions without right of land-use - 53.98 554.93 39.81 16.29 1,404.47 2,069.48 10% Temporary structure before expiration - 67.86 315.33 23.80 406.99 2% Temporary structure after expiration or illeg structure - - 176.25 - 182.25 358.49 2% total - 460.55 9,956.88 3,911.32 825.85 6,409.19 21,563.80 100% Distribution rate (%) 0% 2% 46% 18% 4% 30% 100% See Table5. .1 for the detail 2) Structure and distribution of partially but permanently affected housings

Brick and Grade of area Framework Composite timber Simple total structure structure structure

Grade I

Grade 2 84.14 322.43 53.98 - 460.55

Grade 3 6,400.96 2,693.45 755.31 107.17 9,956.88

Grade 4 978.41 2,465.84 36.07 431.00 3,911.32

Grade 5 809.90 15.95 - - 825.85

Grade 6 3,615.90 956.93 520.78 220.61 6,409.19

Total 11,889.31 6,454.59 1,366.14 758.78 21,563.80

5.1.2 Distribution of partially but permanently affected shops 1) Property right and distribution of partially but permanently affected Liede Resettlement Implementation Plan

shops

Grade of area Total % of Property right Grade Grade Grade Grade property Property ~Grade 2 rd5 6right

Housing with property right 23.45 82.61 1,158.77 52.23 148.15 1,465.21 44% Housing on residential plot 173.23 554.07 599.87 - 212.93 1,540.11 46% Constructions without right of land-use - 182.32 170.32 352.63 11% Temporary structure before expiration 0% Temporary structure after expiration or illegal structure 0% total - 196.68 819.00 1,928.96 52.23 361.08 3,357.96 100% Distribution rate (%) 0% 6% 24% 57% 2% 11% 100% See Table5.1.2. for the detail 2) Structure and distribution of partially but permanently affected shops

Grade . Brick and of Framework Composite timber Simple total area areastruturestructurestructure structure Grade

Grade 2 10.52 91.72 12.93 81.51 196.68 Grade 3 388.47 364.25 66.28 - 819.00 Grade 4 868.80 724.94 205.95 129.26 1,928.96 Grade 5 52.23 - . - - 52.23 Grade 6 190.19 170.89 - - 361.08 total 1,510.22 1,351.80 285.16 210.77 3,357.96

5.1.3 Distribution of partially but permanently affected enterprises

1 ) Property right and distribution of partially but permanently affected

enterprises

Grade of area Total % of

Property right property Grade Grade 2 Grade 3 Grade 4 Grade5 Grade 6 right

Housing with property right 544.89 617.30 1,449.08 - 809.62 3,420.89 36% Housing on residential plot - 2,534.95 44.69 | - 2,579.64 27% Constructions _ l _ i 35% Liede Resettlement Implementation Plan

without right of 7.88 1,354.00 1,512.56 90.11 368.06 3,332.61 land-use Temporary structure before expiration 18.53 - 18.53 0% Temporary structure after expiration or illega structure - 59.82 - - 59.82 1% total - 552.77 4,524.77 3,066.15 90.11 1,177.68 9,411.49 100% Distnibution rate (%) 0% 6% 48% 33% 1% 13% 100% See Table5.1.3. for the detail

2 ) Structure and distribution of partially but permanently affected

enterprises

Grade of BrkCompositetieand Simple area structure tur structure structure

Grade I - - - - Grade 2 1,063.70 733.72 1,643.15 435.49 3,876.07 Grade 3 837.87 1,223.73 3,659.52 - 5,721.12 Grade 4 1,067.94 666.48 3,380.27 2,539.02 7,653.70 Grade 5 637.15 196.17 669.74 76.21 1,579.27 Grade 6 1,692.56 342.00 2,219.40 4,253.96 I total 5,299.22 3,162.10 9,352.68 5,270.13 23,084.12

5.1.4 The partially but permanently affected commonweal units

There are not any such units found during the survey.

5.2 Resettlement, compensation and rehabilitation plans for the PAPs whose property is partially but permanently affected

The project affected people whose houses are partially but permanently requisitioned will obtain the following helps besides the compensation specified in Resettlement Policy:

5.2.1 Resettlement and compensation principles for partially but permanently affected housings

(1) The Project will try its best to reduce demolition quantity during implementation of demolition and resettlement. The Project will carry out field survey of the buildings to be partially demolished together with the experts at planning, design and engineering. Measures of translation of buildings or realignment of demolition line will be adopted to reduce demolition quantity. Liede Resettlement Implementation Plan

(2) If it is necessary to partially but permanently demolish the houses, the Project will regulate internal structure of the houses according to the area and functions of the part to be demolished, so that integral functions of the houses will not be reduced because of partial demolition. (3) If temporary relocation is necessary for safety of the people during demolition and rehabilitation, the project affected people will enjoy the rights specified in the rehabilitation policy and measures relevant to temporary requisition. (4) If housing conditions of the residence are poor after partial demolition, the Project will persuade the project affected people to permanently relocate from the place according to the professional judge and suggestion of the expert in resettlement, so that the people's living standard will not decrease. (5) If the project affected people are seriously impacted by partial but permanent demolition, they may apply for permanent relocation and will enjoy the resettlement house discount because of group purchase of the Project.

(6) Rehabilitation period of the remaining house after partial demolition can't exceed half a year.

5.2.2 Resettlement and compensation principles for partially but permanently affected shops

(1) If the part to be partially but permanently requisitioned is located in the key part of the shop, the Project will carry out field survey together with the experts at planning, design and engineering. Measures of translation of buildings or realignment of demolition line will be adopted to avoid the key part and reduce the impact on operation of the shop. (2) If it is necessary to partially but permanently demolish the shop, the Project will regulate internal structure of the shop according to the area and functions of the part to be demolished, so that integral functions of the shop will not be reduced because of partial demolition. (3) The Project will reasonably arrange the period of demolition and reconstruction and cooperate with the merchandising business to reduce the impact on normal operation as much as possible. (4) If temporary relocation is necessary for safety of the people during demolition and rehabilitation, the project affected people will enjoy the rights specified in the rehabilitation policy and measures relevant to temporary requisition. (5) If operation conditions of the shop are poor after partial demolition, the Project will persuade the project affected people to permanently relocate from the place according to the professional judge and suggestion of the expert in resettlement, so that the people's benefit will not decrease. Liede Resettlement Implementation Plan

(6) If the project affected people are seriously impacted by partial but permanent demolition, they may apply for permanent relocation and will enjoy the resettlement house discount because of group purchase of the Project. The Project will help the project affected people that rent houses with market-price find resettlement sites with the same type and equivalent rental.

(7) Rehabilitation period of the remaining house after partial demolition can't exceed half a year.

5.2.3 Resettlement and compensation principles for partially but permanently affected enterprises

(1) If the part to be partially but permanently requisitioned is located in the key production part of the enterprise, the Project will carry out field survey together with the experts at planning, design and pipeline engineering. Measures of translation of buildings or realignment of demolition line will be adopted to avoid the key part and reduce the impact on production of the enterprise. If it is necessary to partially but permanently demolish the industrial enterprise, the Project will regulate internal structure of the industrial enterprise according to the area and functions of the part to be demolished, so that integral functions of the industrial enterprise will not be reduced because of partial demolition. (2) The Project will reasonably arrange the period of demolition and reconstruction and cooperate with the industrial enterprise to reduce the impact on normal operation as much as possible. (3) If the main production equipment in the factory building shall be relocated during demolition and reconstruction, the Project will give relocation fee or be responsible for the relocation. If equipment commissioning is necessary, the Project will give help to the enterprise. If the commissioning period is relatively long, the Project will give appropriate compensation according to the standard for temporary relocation fee.

(4) Rehabilitation period of the remaining house after partial demolition can't exceed half a year.

5.2.4 Resettlement and compensation principles for partially but permanently affected commonweal units

(1) If the part to be partially but permanently requisitioned is located in the key part of commonweal unit, the Project will carry out field survey together with the experts at planning, design and pipeline engineering. Measures of translation of buildings or realignment of demolition line will be adopted to avoid the key part and reduce the impact on commonweal unit's service provision. Liede Resettlement Implementation Plan

(2) If it is necessary to partially but permanently demolish the commonweal unit, the Project will regulate internal structure of the commonweal unit according to the area and functions of the part to be demolished, so that social service functions of the commonweal unit will not be reduced because of partial demolition. (3) The Project will reasonably arrange the period of demolition and reconstruction, guarantee construction safety and cooperate with the commonweal unit to reduce the impact on its social service function as much as possible. (4) If the heavy service facilities in the unit shall be relocated during demolition and reconstruction, the Project will give relocation fee or be responsible for the relocation. If facility commissioning is necessary, the Project will give help to the unit.

(5) Rehabilitation period of the remaining house after partial demolition can't exceed half a year.

5.2.5 Procedure and methodology of the resettlement, compensation and rehabilitation for the PAPs partially but permanently affected

1. Procedures and methods with generality are included in Section 5.10.1 of the Resettlement Policy.

2. For partially demolished structures the engineers will carry out the site investigation and determine whether the structure can be partially demolished and the position of the part to be demolished and based on this to work out detailed demolition scheme.

3. Negotiation with the PAPs will be carried out to see whether they would like to use the rest part of the house continuously.

*If they would the negotiation about the restoration standard, the method of temporary removal and the compensation of the stop-loss will then be negotiated. *If they would not the project will carry out the compensation as for structures wholly and permanently demolished.

4. Whenever there is any dispute about the temporary removal expenses and compensation of the stop-loss the evaluation can then be carried out.

5. The opportunity of selection of the houses for temporary relocation and the resettlement housings is the same.

6, The project needs to consider safety of the PAPs who choose to live in or use the partially demolished structures. Whenever there is a need for temporary relocation the project shall negotiate with the PAPs.

7. The restoration standard of the houses is the same as that of the original houses.

5.2.6 Resettlement, compensation and rehabilitation schedule for the PAPs whose property is partially but permanently affected Liede Resettlement Implementation Plan

See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resenlement Implementation Plan

6.Status of the PAPs whose property is wholly and permanently affected and the resettlement, compensation and rehabilitation plans for them

6.1 Status of the PAPs whose property is wholly and permanently affected

6.1.1 Property right and distribution of the PAPs whose property is wholly and permanently affected G Grade of area

% of property Property right Gradee Grade Total right 1 246

Housing with property right - 274.82 635.63 174.63 - 1,085.08 6% Housing on residential plot - 10,941.61 1,921.14 - 2,396.18 15,258.92 85% Constructions without right of land-use 125.44 - 590.33 - 723.65 1,439.43 8% Temporary structure before expiration 49.29 114.28 - - 163.57 1% Temporary structurl after expiration or illegal structure - - 3.83 - 15.66 19.49 0% total - 125.44 11,265.72 3,265.21 174.63 3,135.49 17,966.50 100% Distribution rate (%) 0% 1% 63% 18% 1% 17% 100% l See Table6.1.1. for the detail 6.1.2 Structure and distribution of housings wholly and permanently affected

Grade of Framework Composite timber Simple Total Grade of area structure suucture structure area %

Grade I - - - - 0%

Grade 2 - 111.82 - 13.62 125.44 1%

Grade 3 6,797.85 3,942.93 171.32 353.63 11,265.72 63%

Grade 4 418.90 1,848.20 584.72 413.38 3,265.21 18%

Grade 5 174.63 - - - 174.63 1%

Grade 6 1,855.95 645.14 227.20 89.54 3,135.49 17% total 9,247.33 6,548.10 983.24 870.16 17,966.50 100% Attached table: 6.1.2 6.1.3 Distribution of housings wholly and permanently affected Liede Resettlement Implementation Plan

Housing Area of Subtotal of the area of Area of Grade of with housing on housing with property hout Percen Total area property residential right and on residential Percentage without age right plot plot right

Grade I 0% - 0%

Grade 2 - - - 0% 125.44 1 % 125.44

Grade 3 11,265.7 274.82 10,941.61 11,216.43 62% 49.29 0% 2 Grade 4 635.63 1,921.14 2,556.76 14% 708.45 4% 3,265.21

Grade 5 174.63 - 174.63 1% - 0% 174.63 Grade 6 - 2,396.18 2,396.18 13% 739.32 4% 3,135.49

total 17,966.5 1,085.08 15,258.92 16,344.00 100% 1,622.49 100% 0 Attached table: 6.1.3

6.1.4 Household economic condition of the PAPs whose property is wholly and permanently affected In this survey, the total number of the households whose property is wholly and permanently affected is 138. During the survey only 26 households were willing to report their income that is less than 20% of the total. Only 219 of 489 people filled in the income condition in the questionnaires that is less than 45% of the total. It can be seen from the data filled in the table that the answers were quite informal. It is obvious that since the project is not determined and also since the citizens of Guangzhou are not willing to have (or used to have) this kind of survey. The consequence is the failure of the survey on the income of the households. There are some other indications in the questionnaire and the follows are the amount of valid data obtained during the survey.

Item Total samples Valid samples Percentage Remark No. of people with 138 44 31.88% Valid data refers social unemployment to the table insurance filled in with No. of people on the 138 44 31.88% figure or nil rates while the blank Decoration 138 134 97.1% and unclear No. of computer 138 121 87.68% figures are taken No. of air condition 138 136 98.55% as invalid data No. of motorcycle 138 47 34.06% *No. of TV set 138 98 71.01% No. of telephone 138 96 69.57% Liede Resettlement Implementation Plan

No. of cell phone | 138 43 31.16%

It is obvious that most of the figures referring to decoration, telephone, TV set and air condition are observed by the inquirers outside the doors when they were not allowed to get in and as inquirers reported most of the households were not willing to answer questions or open the doors. The number of households was counts by buildings. The number of people was surveyed by those with or without residential registration (including the interview with the neighbors). As the alignment is 450km long and scattered it was impossible for the inquirers to carry out cross check and this is another reason of the low rate of valid data of the survey. Therefore, we can only judge the income of the household according to the size of the house and number of the facilities. See the following table.

Good (with) Normal (with) Poor (with) Very poor(with) Decoration 92 31 14 4 Air condition 171 46 17 0 TV set 74 29 12 1 Telephone 86 27 10 0

It can be seen from this table that those without air condition and TV set can be than defined as households with low incomes. These households need special attention that account only to 3. This basically tallies with the analysis of the living condition. See the following table: Households with floor area per capita less than 8m2 Area No. of Area Item Component Usage Property right No. of person (i 2) grade household Residential Liede III 3 Residence 7 7 7 2 2 2 48.76 plot

6.1.5 Population structure and household classification of the PAPs whose property is wholly and permanently affected Since there are a lot of households who refused to be visited the information about the household economy condition was obtained mainly from the residential registration database: Among 138 households those with registrations are only 71 households accounting for 8.54%. This tallies with the situation in Guangzhou that there is a big number of households that their registered residential address differs from their living address. Referring to these 71 households (totaling 291 persons) the following data were obtained: 1) Divorce: Totally 24, among which 9 are females. 2) Education level: University | 31 person 10.65% 30persons | 13.39% Junior college 61 person 20.96% 58person 25.89% Liede Resettlement Implementation Plan

Senior high school 44 person 15.12% 37 person 16.52% Below junior high 155 person 53.26% 99 person 44.2% school Totally 291 person Totally 224 person

3) Ratio of male and female: Male: 895; female: 367 4) Occupation: Government staff 26 person 11.61% Long-term occupation 169 person 75.45% Short-term occupation 19 person 8.48% Agriculture 6 person 2.68% Unemployed 4 person 1.79% 224 person Note: 1. This ratio may have already changed greatly since the residential registration record was done 4 years ago and some of the data may not be updated timely. 2. For the unemployed people, judging from the living address and facility of their dwelling it can be seen that the living condition of 104 of them is quite good, that of 45 is normal and that of 20 is poor. The reasons of their unemployment are two: 1) They are self-employed; 2) Update of data has lagged behind. 6.1.6 Commuting of the PAPs whose property is wholly and permanently affected

Since there was a big number of households that refuse to be visited the number of people who filled in the questionnaires with valid data on the items "commuting tool" and "commuting time" is only 48 persons. Since the PAPs have not indicated clearly which resettlement sites they might choose it is impossible to analyze the change degree of commuting distance and time. However, the resettlement sites of this project and the relevant projects are close to the demolition sites 3-5km) therefore there will not be too much impact on the PAPs commuting. 6.1.7 Analyses of benefit and loss 6.17.1 Benefits 1. Benefit relating to the structure The area of the affected brick and timber structure reaches 1,853.4m2 and the owners will be benefited from the project. 2. Benefit relating to the indoor layout The number of the apartments without individual kitchens and washrooms is 5 and they will be benefited from the project. 3. Benefit relating to the exchange price

m , m Liede Resettlement Implementation Plan

The project has decided to provide the compensation with one degree higher than the original housing in terms of the percentage of the newness. 4. The PAPs will have preferential price when purchase the resettlement housing in "group". 6.1.7.2 Losses 1. Commuting distance and time of some PAPs may be impacted slightly. 2. Commuting distance may cause impact on the employment of poor households. 3. Though the affected property will be compensated the original community relation may be broken down due to their selection of the resettlement sites.

6.2 Principle of the setup of residential resettlement sites

1) The residence resettlement zone (point) shall be distributed in accordance with the inhabitation area for the demolition in order to make the resettlement nearby.

2) The road, water, electricity, communication, post, network and other public utilities of the residence resettlement zone (point), and the education, department of health, commerce, park and garden, culture and other supporting facilities within the residence resettlement zone (point) must be complete.

3) The residence resettlement zone (point) shall be set up in the coverage.

4) The traffic to the residence resettlement zone (point) shall be fully taken into account and resumption measures shall be made to ensure that there shall be at least two public traffic lines leading to the downtown. According to the long-range plan of the underground railway, all of the resettlement sites planned by us shall be within the benefited area.

5) The compatibility of the surrounding area of the residence resettlement zone (point) shall be very strong and shall not exclude outlanders and the habits and customs from other places.

6) The public security of the residence resettlement zone (point) shall be well. A police substation shall be ensured per square kilometers and a police house shall be ensured per square kilometers

7) According to the requirement and purchasing power of the PAPs, high-grade, middle-graded and low-graded residence resettlement zones (points) shall be provided for them to choose. Aiming at different moved groups, the resettlement zones (points) having different characteristics shall be supplied. For example, the several communities, which are on the north of Guangzhou Road and have Yun Jing Garden as the center, are all close to several hospitals, nursing homes and so on. They are fitting for the families that give first place to the aged. Liede Resettlement Implementation Plan

8) The principles of setting up the high-grade resettlement zone (point)

(1)The geographical position should be superior and it should be located at the economical, cultural and political center.

(2) The transportation should be well suited and several public traffic lines should lead to every district in the city. Even there should be some free buses supplied to the zone.

(3) The environment should be pure and fresh, the greenery should be flourishing and it should be designed as a landscape garden.

(4) The hospital, post-office, school, supermarket, movie theatre, playground and other supporting facilities should be complete.

(5) The community should be served intellectualizedly and Wide Band should be provided.

(6) The intimate residential area management and overbalanced chamber service should be provided roundly.

(7) The quality-based water supply system should be installed so that pure water could be directly drunk breezily.

(8) The cultural life should be plentiful; the cultural plaza and reading room should be enjoyed freely and the cultural exercises in the community should be rich.

(9)The space between houses should be rational. The natural lighting of the house should be enough, the ventilation should be unhindered and the usability should be well.

The principles of setting up the middle-graded resettlement zone (point): ( 1 ) The water, electricity, communication, post and other public utilities, education,

department of health, commerce, garden and park, culture and other supporting facilities in the residence resettlement zone (point) should be complete.

2 ) According to different family composition and life requirement of the moved

families and other aspects especially concerned, the characteristic resettlement zone (point) should be provided to make the work, study and living more comfortable.

( 3 ) The environment and supporting failibilities of the middle-grated resettlement zone

(point) should be improved greatly on the existing base.

The principles of setting up the low-graded resettlement zone (point): 1 ) It should be located in the area where the consumption level is low and the goods around it should be good and cheap. Liede Resettlement Implementation Plan

( 2 ) The compatibility of the areas around the residence resettlement zone (point) should

be strong and it should not exclude outlanders and the habits and customs from other places.

3 ) The water, electricity, communication, post and other public utilities, education,

department of health, commerce, garden and park, culture, and other supporting facilitates in the residence resettlement zone (point) must be complete.

(4 ) It should be located at a dense living area and be adjacent to numerous large mature

communities, large shopping centers, food markets, restaurants and supermarkets to facilitate the PAP.

( 5 ) Lots of small shops, maintenance services, supermarkets, beauty shops and

hairdressing shops should be set up in the resettlement zone (point) to provide numerous job opportunities different job selection for the PAP.

6 ) The utilization rate of the house should be high, the space should be rational and the

type design of the flat should be multifarious to meet the diverse requirement of the PAP upon the space and area of the house. j 9) When planning the residence resettlement zone (point), the economic development and transportation planning in the future shall be fully taken into account, the residence resettlement zone (point) shall be ensured to be in the area that shall be developed and consummated in the future, and the house of the PAP shall be ensured not to be devaluated in the future.

10) The Pips having middle-graded and low-graded consumption capability should be resettled dispersedly to meet the requirement of the PAP and make it convenient for them to get employment, go to work, go to school and go to hospital. In economic aspects, the PAP having high-grade consumption level is comparatively rich, they can be resettled not only dispersedly but also dispersedly and various resettlement sites can be provided for them to choose in accordance with the requirement

According to above principles and the distribution area of the PAPs, this project chooses Xinbuxianting, Huizhanxingcheng, Yujingnanyuan, Yunjing Garden, Beili Garden and Haijing Garden as the residence resettlement sites, of which the associated information has been elaborated in Resettlement Action Plan.

6.3 Description of the residential resettlement sites Liede Resettlement Implementation Plan

6.3.1 Resettlement site Near Xinbu Xianting

Huabao Garden, Jinfeng Garden and Jude Garden within 1 km distance from the Strolling Corridor, center of Haizhu District, can be used resettlement sites for the Project.

6.3.1.1 Geographic Location

1) Located on South Xinguang Expressway and at east of Chigang, near the main road of Haizhu District - Xingang Rd., at north side of South Xinjiao Rd., at traffic center of Haizhu

District. i 2) Distance to flourishing area: The l E Huangzhou Bridge to be

finished soon . ' = will shorten the distance between Pearl River

and Tianhe North. It takes only 4-6 minutes to these Geographic layout of Xinbu Xianting places. It also needs only 6-10 minutes to the Jiannanxi Commercial Street.

3) Distances to large commercial centers: Haizhu Square will be set up at 300-100 m near the residential area integrated with commerce and living. It takes only 4-8 minutes to the conference and exhibition center via Xingang Rd. Chigang Commercial Town, Huijia Department Store and Wal-Mart Supermarket are also very close. 6.3.1.2 Traffic Conditions

1) Bus 189 has station in front of the residential area. Buses 14, 20, 262, 270, 203 go directly to Beijing Rd., Tianhe North, Lower Nonglin Rd. Pearl River New City, etc. The convenient traffic goes to everywhere. Liede Resettlement Implementation Plan

2) Chigang Station of Subway is just 200-600 m away from the residential area. to be finished soon also passes here. This place will be the only place in Haizhu District with two subway lines passing by. There will be a double effect from traffic.

3) The residential area is near Guangzhou Avenue and Middle Xinggang Rd. The nearby Huanan Xingang Expressway will be open soon. It also connects the planned Liede Bridge and Tianhe East vertically. There is good traffic to Tianhe District Center and everywhere of Haizhu District.

4) The residential area has excess via Huanan Expressway to Panyu Bridge to reach Panyu, Zhongshan, Pearl River City freely.

5) The planned expressway connects Panyu at south and Tianhe at north. It will greatly shorten the distance between cities.

6.3.1.3 Public Facilities Surrounding

1) The Conference & Exhibition Center: The largest conference & exhibition center in China - Conference & Exhibition Center is just 1-2 km away from the residential area. It will greatly support the economy in Haizhu District.

2) Opera House: is planned to be built in Pearl River New City which is just 1.5-3 km away from the residential area.

3) Museums: The new museum in Pearl River New City is less than 2.5 km away. Driving to Art Gallery on is just 15 minutes.

4) Hospitals: The provincial No.177 Hospital, Navy Hospital and Huimin Clinic for Children are located within 0.5-1.5 km from the residential area.

5) Schools: Primary schools near the residential area are: Nol95 Middle School, Xinlong Middle School, Municipal Machine & Electric School, Provincial Chemical School and Datang Primary School. Colleges nearby are: Guangdong Commercial College, Guangdong Normal College, a college of No.1 Military Medical University. It also goes less than 6 minutes to the city key school - Zhongda Primary School and No.6 Middle School and Zhongshan University.

6) Supermarkets: Trust-Mart Supermarket is just 0.5-2 km away from the residential area. Wal-Mart Supermarket is just 300-1500 away. Shopping is easy.

7) Parks: Near the residential area is located with a 10,000 m2 orchard called "Southem Lung" of Guangzhou and Yingzhou Ecological Park. Greening and air quality here is unique.

8) Restaurants: Within 1 km surrounding the residential area are located with high and medium level restaurants like Dongjiang River Seafood Restaurant, Nangang Jianxiong Liede Resettlement Implementation Plan

Seafood Restaurant and Minji Seafood Branch, etc.

6.3.1.4 Planning of the Residential area:

s-@oW,, ~ totalW building area of 108,000 m2 consisting of 12 buildings o

!~~~ ------_ BE

Orchard of greening 2 *- | w t1'' @"|R''i7 s ...... center: Used more than 10,000 m

- land. Adapts to sub-tropical weather

s- Bs8 asof"4 Lingnan Area of high temperature and abundant rainfall. It has good rr A 3 ventilation, lighting characteristics

. L> C t" F; with the building essence of thousand . I uE |ss w ^ years. There exists large plot of intact original high trees demonstrating the U ~~~~unique Lingnan appearance. The B3 lay-out in dual L-shape will maximum the use of the fresh air of the orchard

2 §--'I 1 = 11 ¢ of thousands mus.

vASIR | (2) Lingnan Cultural Plaza:

v I RI |9PBIMP @|1s Modem architecture with garden and

r1 . sculptures, full of fashion and beauty.

(3)lS. Large community recreation: Provided with SPA 1- . _ hydropathic and beauty parlor, health Overall plan of Xinbu Xianting room, small cinema, library, bowling galley, laundry, commercial center, Sauna room, etc.

_(4) Swimming pool: In the middle of the residential area, occupying 800 m2 land.

(5) International standard tennis court: Well-equipped sporting facilities for leasing. Service is available of all details. 15001 3700 3000 I I I I (6) Xinbu primary school: The school . _ ;.eS is right_ ~in front of the house. Bright and wide o Cc ! e % < classrooms are well equipped with basketball yard, football yard. There is a good environment

C~~~~~~~~~~~~~~~~~~~~CG-vJ [} o * .| ...... , O for children to study. C~~~~~~~~~~~~~~~~~~~C

Q= In .. _ '-!m!r '. -13* r l .. fr1 c (7) Commercial Streets: Located on Liede Resettlement Implementation Plan

the middle axis of the residential area of 300 m length. There are many stores selling flowers, sport articles, supermarket, post office, bank, bookstore, restaurant, furniture, etc. Living needs can be bought local.

(8) Building Structure: Distance between buildings is up to 70 odd meters. There are many houses of 60 m2 to more2 than 200 m~~~~~~~2 for selection. The houses have good lighting and ventilation.

(9) Other associated facilities: Provided with direct potable water system supplied from Guangzhou City. Equipped with smart ventilation sound isolation, visible paging system and broad-band input.

6.3.1.5 Residential area Suitable for Resettlement

The residential area is located within a well-developed Chigang Area, having Jianghai Avenue going from south to north and with 10,000 mu "City Lung" not far away. It is close to Jiaozhou Conference & Exhibition Center. Traffic is good and the environment is comfortable. There is a good prospect for economic development. It is good for successful residents, top citizens and high-income white-collars.

6.3.1.6 Prospect of the Residential area

Along with the successive improvement of the surrounding environment as well as the accomplishment of various municipal infrastructures and living facilities, the residential area has become one of the best living quarters in Chigang Area. The Government of Haizhu District has pla r ; , - nne d to< con a ct Chi gan -. f g To . wer, i sigh tsee m- 4 ing tow er, Chi View of xinbu xianting Chi~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Liede Resettlement Implementation Plan

gang Tower Plaza, Dongfeng Ecological Park and Xingkegang Plaza, etc. Here will be an ideal residence. Shiliugang Rd. near the residential area is under revamping will be finished by the end of this year. By then, a 60 m wide Jianghai Avenue will be in parallel with Guangzhou Avenue connecting Luoxi at the south and reaching Jianghai Bridge at north then to East Tianhe Rd. It will be another main south-to-north avenue in Guangzhou City. Jianghai Avenue will connect Panyu Avenue, which will be started in the second half of the year, and reach Zhishi Bridge. It will shorten the distance between Chigang to Tianhe and Panyu. It will become new axis of the city. Along with the service of the Pazhou Conference & Exhibition Center, it will be started for the decoration of Xinggang Rd. on the 5.7 km length of the Xinggang Rd. starting from the west side of the Guangzhou International Conference & Exhibition Center to Kecun Flyover in the west will be displayed with Municipal culture and natural scenery. The residential area is located on the golden place of two subways. And owing to the convenient traffic, Guangbei Century Supermarket will open a store here. For future planning, this city area with the conference & exhibition center as the core will be a center for fast developing economy, high-tech, human culture and high living environment. It will bring great radiation to Chigang area and make this area to be a golden area for both commerce and residence.

6.3.2 Resettlement site Near Huizhan Xingcheng

Huizhan Xincheng as the core, residential quarters of Hongyun garden, Fujingju and Lijing Garden are suitable for Resettlement within 1 km from the Haizhu District.

6.3.2.1 Geographic Location:

1) In the flourishing area of Chigang, around the joint of Jianghai Bridge and Xingang Rd. Facing beautiful Ersha Island and near the international Conference & Exhibition Center. It neighbors Guangzhou Ave. and reaches Jianghai Ave. not so far. Huanan Expressway is also rather close. The traffic is good.

2) Distance to flourishing area: It goes via to Tianhe District flourishing area within 3.5 km distance. Going by Guangzhou Ave. to Guangzhou Railway ttI _Station for 6-10 km. Only 10-14 miinutes drive to flourishing West Jiannan Rd. of Haizhu District.

3) Distance to large commercial centers: Pearl River New City is just located on the other side of Liede Resettlement Implementation Plan

the river integrated with finance, trade, culture and recreation. It goes just 2 to 4 minutes. It goes via Jianghai Bridge to the stadium of Tianhe District. Distance to Haizhu Shopping Center, Nanfeng Store, Xinhe Plaza is less than 12 minute drive. Distance to Ersha Island sport article street is just 6-8 minutes drive.

6.3.2.2 Traffic Conditions

1) Chigang Bus Station is located less than 200 m from the residential area. More than 20 buses like 270, 14, 250 are covering the whole city. Traffic to Fangcun District, Haizhu District and Tianhe District flourishing area is rather convenient.

2) Within 800 m of the residential area are located with Chigang Subway Station, (joint of Subway Line 2 and Line 3).

3) Huanan Expressway and Ring-road Expressway are passing by within 2.5 km from the residential area. These roads connect the new airport and the Pearl River Delta.

4) Joint of Haizhu District and Panyu District - Luoxi Bridge is within 4-6km from the residential area.

6.3.2.3 Public Facilities Surrounding

1) The Conference & Exhibition Center: The Conference & Exhibition Center invested by Guangzhou City with 4 billion RMB is just 200-1,000 m from the residential area. This is the first place for exhibition of large and medium scale commercial firms in future.

2) Opera House: Guangzhou City has planned to const Guangzhou City Opera House at Pearl River New City, allowing the residents to enjoy elegant art.

3) Museum: It goes less than 3 km to the new museum in Pearl River New City. Drive to Guangdong Art Gallery on Ersha Island is less than 10 minutes.

4) Schools: On the neighbor St. of the residential area - Jianghai Ave. are located with a college of No. 1 Military Medical University and Guangdong Commercial College. Within 1 km from the residential area are located with Modiesha Primary School, City No.95 Middle School, City Xinlong Middle School. Guangzhou University (Chigang residential area) is less than 2.5 km away from the residential area. Distance from the residential area to the city key primary school - Zhongda Primary School, city key middle school- No.6 Middle School and Zhongshan University is less than 5 km.

5) Park: The residential area faces the stadium park. Besides, it goes very short to the Hongcheng Park of Ersha Island and Pear River Park of Pear River New City for 1.5-2 km and 3-4 km respectively.

6) Hospital: Within 1.5 km from the residential area is located with the Navy Hospital and 177 Hospital. Within 2 km from the residential area are located with 3 more hospitals:

N(ELL. '_I_ Liede Resettlement Implementation Plan

meeting the needs of "digital living".

(4) Primary school: Within the residential area is located with a primary school; experienced teachers are employed in the school with good teachers, good equipment, high greening rate. The surrounding environment is comfortable.

(5) Waterscape Garden: Greening of the residential area is as high as 35%. There is a unique large garden of 12,000 m2 large, well equipped with elegant spring, flower corridor and art sculpture. Waling through it will bring you full sight of greening and flower fragrance.

(6) House Design: There are many types of houses from 620 to 120. Every house has two balconies, widescape windows. The residents will enjoy the 12,000 m2 garden greening. Houses are facing south and arranged square.

6.3.2.5 Residential area Suitable for Resettlement

The residential area is located in the new poli-economic center of Haizhu District, neighboring the Conference & Exhibition Center. Traffic is good going to all directions. Besides, it is provided with all kinds of associated facilities like supermarket, bank, colleges, etc. It is very good for

q,; *-1 ' - t young white-collars. The residential area will offer convenient traffic

-m~F a il comfortable} | _and living environment. Living here is of high level.

6.3.2.6 Prospect of the Residential area

The Huizhan Xingcheng is located View of Huizhan Xingcheng in the downtown of Chigang Area. It is a unique area with two subways. The government of Haizhu District will be relocated here. Subway Line 2 and Line 3 will cross here. Pazhou Bridge is now in service. Stadium Park, Qinshui Park, Pazhou Tower Park will be completed by the end of the year. Along with the service of the Pazhou Conference & Exhibition Center. The five-star Shangri-La Hotel of 110,000 m2 will be soon finished. Top-level Office Building - Baoli Building of 80,000 m2 is completed. All these will create a high level living quarters integrating conference & exhibition, international commerce, information exchange, high-tech R&D, travel service, etc. This area will also become a new ecological sub-center of the city. The associated facilities will be perfected. Commercial atmosphere is flourishing day to day. Huizhan Xingcheng will become an ideal place for Liede Resettlement Implementation Plan

white-collars to enjoy success and living.

6.3.3 Resettlement site Near Yujing Nanyuan

With Yujing Nanyuan as the center, there are some other gardens like Haojing Garden, Yingcheng Garden, Jiangliyuan, etc. within 1 km around the Haizhu District. These gardens are also suitable for the resettlement.

6.3.3.1 Geographic Location

1) Located at middle west of Guangzhou Ave. in the flourishing area of Haizhou District, within 2 km at north bank of the Pearl River. It is within sewage catching area of Lijiao Wastewater Treatment

_1 t-! i @ Guangzhou. The joint of

j_ ~ *1,Js 2!1,,, ,38 f/ 81/2 t}tsHaizhu District and

g* r' ; PanyuM f .District^ -Luoxi

5 C .Sv Bridge is rather near. It is easy to go to Panyu.

2) Distance to

-- -- I flourishing areas: About

; ^ - Ct R ~~~~~2-4km to Tianhe downtown and 3-4 km to Geographic layout of yujing nanyuan Dongshan District

flourishing area, to Yuexiu District, to Beijing Rd. to Zhongshan No.1 Rd.

3) Distance to large commercial centers: Only 6-10 minutes drive to large shopping centers of Tianhe City and Tianhe Book Center. Only 4-6 minutes to large decoration material market Meihaoju Market. About 3-6 minutes to Pazhou Conference & Exhibition Center. About 3-6 minutes to the consulate area. Only 2-4 minutes drive to the Pearl River New City integrated with finance, trade, culture and recreation.

6.3.3.2 Traffic Conditions

1) The residential area is located at 50-100 m Subway Line 2 Lujiang Station Entrance. It is close the Kecun - crossing point of subway Line 2 and Line 3 which will be put in service in recent years. Taking subway may go to 7 districts of Guangzhou: Tianhe, Dongshan, Fangcun, Liwan and Yuexiu, etc.

2) More than 30 bus routes such as 211, 14, 125, 543, etc. passing through here. The traffic is good going to all directions. It has direct road to the railway station, to Dongfeng Ave., to Huangpu Ave., to Zhongshan Rd., etc. Liede Resettlement Implementation Plan

3) Dunhe Bus Station is located within 2.5 km from the residential area, available for direct bus to Zhuhai and Zhongshan.

4) Within 2.5 km of the residential area are located with large and medium-sized docks. Waterway traffic is also good.

6.3.3.3 Public Facilities Surrounding

1) Schools: Within less than 300 m from the residential area is located with a city level key primary school- Zhongda Primary School; Guangzhou key middle school- No.6 Middle School;

N the State key university - Zhongshan

*_- .. University is very close. Within 1.5 km from the residential area are also located with Kecun Primary School, Xinggangzhong Primary School and Guangdong Normnal College, and Guangdong Art College. It is in the middle

^10_5 -_ of theC 's culturalw sector. This residential area is very good for families with children.

-- _ s_)JL 2) Hospital: Within 3 km from the .L residential area are located with several ? hospitals like Guangdong Provincial Oral Hospital, Navy Hospital, Guangdong * xj;hn,_-_ / -/ * Chinese Medical Hospital Ersha Is. Branch § and Seaman Hospital. Guangdong if c b i _ ffiParalysis Recovering Hospital is just 1-1.5 T*XA13 km from the residential area. Overall plan of yujing nanyuan 3) Large shopping centers: the residential area is neighboring Guangbai Century Supermarket, Daoneijia Supermarket, Hongcheng Supermarket. Within 1.5 km reach exist two large comprehensive markets of Baijia and Wanjia. It goes only 2-4 km to Haizhu shopping center, Nanfeng Store, Guangzhou Department Store Jiannan Branch. Within 3 km reach of the residential area is

a large building material market - Meihaoju, large electric appliance market - Dongze Electric Appliance City and Ersha Island sport article street.

4) Park: Beautiful Xiaogang Park, Dongshan Lake Park is within 2 km from the residential area.

5) Stadium: Guangdong Stadium is located within 2.5 km from the residential area. Liede Resettlement Implementation Plan

6) Market: Within 800 m reach from the residential area exist two meat and vegetable markets: Dunhe Market and Dajiangchong Rd. Market.

6.3.3.4 Auxiliary Facilities of the Residential area

1) Scale of Construction: The residential area occupies 80,000 m2 land with 200,000 m2 total building area, including 120,000 m2 houses and 80,000 m2 public facilities.

2) Auxiliary Facilities of the Residential area

(1) Greening: the residential area has the first large 13,000 m2 Japanese Style garden with clean and clear environment. Greening rate is up to 80%. The garden has 50 special views with small bridge and streams, decorated with soft willows. The garden is so beautiful.

(2) Swimming pool: It is the first dual-temperature swimming pool among so many gardens in Haizhu District. The constant swimming pool offers comfortable sporting and recreation for the residents no matter how bad the weather is.

(3) Luxury Recreation: The luxury recreation chamber is of 6 m height and with more than 1,000 m2 area. One can enjoy sporting, recreation, commerce, housekeeping, health consultancy, maintenance and cleaning service. Here are provided with the Tea House, Chess Parlor, Climbing Parlor, offing 24 hours service. It provides a complete system of associated facilities for easy living. It has a unique cultural and municipal atmosphere.

(4) Characteristics of the Buildings and Structures: With rare 120 m wide distance between buildings. Every house is designed with dual balconies and 2700 landscape window. The 10,000 m2 garden is full in sight. There are many types of houses for selection. All are properly arranged.

(5) Nursery: Equipped with game room, studying room, rest room, music room, etc. Good for the growing of small children.

6.3.3.5 Residential area Suitable for Resettlement

Around the residential area are located with many key primary schools, middle schools and universities. It is a golden area for education, particularly good for citizen households caring good environment for education of the children.

6.3.3.6 Prospect of the Residential area Liede Resettlement Implementation Plan

1) Over a dozen buses such as 136, 296, 126, 241, 179, etc. are available within 1-2 km range of the residential area. These buses will go to Tianhe North, North Guangzhou Ave., the Olympic stadium and flourishing zone of railway station.

2) It goes 2-4 km via Guangzhou Ave. to north to Shadong Bus Station. Here are available with several long-distance buses to the cities of the Pear River Delta.

3) Connects the Ring-road expressway and less than 2.5 km from the Northring Expressway, Huanan Expressway, Guangyuan East Expressway. It is very easy to go to Shenzhen, Zhongshan and Panyu.

6.3.4.3 Public Facilities Surrounding

1) Hospital: The residential area is located under the beautiful Baiyun Mt. There are several large hospitals nearby and comprehensive Sanitariums. There are three hospitals: Guangzhou Southern Hospital, 157 Hospital and Baiyun District Hospital. Four Sanitariums are: Baiyun Mt. Sanitarium. No.1 Medical University Sanitarium, Guangzhou Hainan Sanitarium and Shahe Sanitarium.

2) Large commercial center: Xinbaijia Commercial City is rather close. Large supermarket Trust-Mart is less than 100 m from the residential area. Baiyun Store is just 1-2 km away from the residential area.

3) Schools: Jingxi Primary School, Guangzhu Peiying Experimental Primary School is less than 1 km from the residential area. Tonghe Middle school, No.122 Middle School is within less than 1.5 km range from the residential area. Schools within 2 km range are: Guangzhou Peiying Experimental Middle School, No.1 Military Medical University, Guangzhou Police School, Guangzhou Agro-machine & Electrical School, Petroleum University and Provincial Normal School.

4) Agro-market: Within 1-2 km is located with large Tonghe Agro-market. Liede Resettlement Implementation Plan

5) Restaurants: Within 1.5 km of the residential areal.5 km are located with the new Dongjiang River Seafood, Huaxianlou, Tianfulou, etc. These restaurants of high, medium and low levels will be good for Guangzhou citizens who are enjoying breakfast in restaurants.

6.3.4.4 Auxiliary Facilities of the Residential area

1) Scale of Construction: Occupying 320,000 m2 land, with total building area of 750, 000 m2, including 580,000 m2 for houses and 270,000 m2 for public facilities.

2) Internal associated facilities of the residential area: One central park of the residential area has 30,000 m2 area. It has 1,000 m2 long banyan boulevard with overhead greening. It is a 3-D ecological garden providing broad space, tranquility and comfort for rest.

.. ~~~~~~~~~~~~~~~~~~~~~~~~U. 1'~~~1

a."....~ - ~~~~~~~~~~~~~~~~~~~~~~~~~~.'.. S,

Three-demention plan of yunjing garden 2) Youth cultural plaza: Occupying 2,000 m2 land. It is a good location for holiday enjoyment of the citizens. It is also good to organize various large activities in the residential area.

3) Tennis Court: 1,800 m2 court with good facilities.

4) Sport recreation; Ping-pong Room, indoor badminton yard, billiards room, fitness room, Sauna Room, Massage Room, Beauty Parlor, etc.

5) General Agro-market: Occupying 1,000 m2 land with proper compartments selling a large varieties of cheap products. Apartment layout of yunjing garden

6) Yunjing Middle School: With experienced teachers. The campus is clean and clear. Offering various training courses. With good Physic culture facilities.

7) Yunjing Primary School: With complete education system and good classrooms. Provided with PC classroom, well-equipped with modem education facilities. 02 Liede Resettlement Implei I_____

8) Youth Art i 03 ' Center: i . Offering '

training causes 05 . - ] f for music, E --

dancing, piano, I Wushu, etc. It is a base for interest training of the children.

9) Experiment nursery: Bilingual education, quality education to have all-round development of the children. Provided with game room.

10) Lemei Porridge Center: A large dining center of the residential area. The residents can enjoy good food locally.

11) Recreation Center: IT bar, physical therapy center, laundry, library, commercial center, etc. are available and offering to the residents all days.

6.3.4.5 Residential area Suitable for Resettlement

The residential area is located at the important zone of the "green

ecological zone" as f planned by the ; Municipality. Baiyun

Mt. is green all the year ; 'iE _ round. There is a 30,000 m2 super garden. _ Air here has high anions. Air quality is meeting International Class 1 level. It is very View of yunjing garden good for living. Two large hospitals of the city level and comprehensive sanitariums are nearby. It is particularly good for households with the aged. The residential area has good associated facilities. Clothing, eating and recreation can be supplied locally. Convenient living is particularly good for the aged.

6.3.4.6 Prospect of the Residential area Liede Resettlement Implementation Plan

The planning concept for the Baiyun District is to arrange properly in the scenery areas with eight industrial parks, six special markets distribution center, living quarters and travel and holiday areas. This will bring Baiyun District to both a business and living center. As the residential area is located near the beautiful Baiyun Mt. and located within the "green ecological community" planned by the Baiyun District, it is called a "residential area of excellent greening construction in Guangzhou City" and "Excellent Residential of National Municipal Property Management". Baiyun Mt. is large and green all the year round having a super 30,000 m2 central garden, 1,000 m long banyan boulevard and elevated greening. It is a real 3-D ecological garden isolating noise from outside. It provides broad space, tranquility and comfort to the residents. Resting here is just line in a fairyland. Besides, the residential area has good traffic conditions. It is a multi-functional subOzones integrated with commerce, residence and communities. The surrounding medical facilities are good support for the residents. It is an ideal place for the municipal people and aged for rest and recuperation.

6.3.5 Resettlement site Near Beili Garden

Many gardens like Xingge Garden, Meijing Garden, Times Garden, Yuanbang Aviation Garden, Baishuntai, etc. within 1 km surrounding the Baiyun District with Beili Garden in the center may be used as residential area of the Project.

6.3.5.1 Geographic Location

ted at west

of the

neig:h bors a traffic i trunk line

West Ring-road. It goes less than 2

Geographic layout of Beili garden Liede Resettlement Implementation Plan

km to the Ring-road Expressway. It is the heart of "village in city" with great efforts of Guangzhou Government. It goes to the downtown area via the Airport Road.

2) Distance to flourishing area: Only 8-10 minutes to the railway station and only several hundred meters to the Airport Rd., Only 2-3 km to the Ring-road Rd.

3) Time to large commercial center: Large supermarket Tangguang Kenong is available near the residential area with only 5-7 minutes drive. Only 8-12 minutes drive to the Friendship Store and World Trade Center.

6.3.5.2 Traffic Conditions

1) More than a dozen bus lines are available such as 810, 36, 108, 53. It goes quickly to Tianhe East Station, Beijing Rd., Zhonghua Plaza in no time. Bus 623 goes to the downtown.

2) Less than 200 m to the Subway Line 2 which is to be open, soon. The subway leads to various commercial centers.

3) Baiyun Airport is within 2 km from the residential area.

4) The completion of the Ring-road Expressway, Jingzhu Expressway, Airport Expressway as well as the successive service of the Huanan Ave., Airport Expressway, Underground subway, etc. will form a traffic network of "Seven horizontal and 5 longitudinal lines" to provide convenient traffic to the developed areas of Pearl River Delta.

6.3.5.3 Public Facilities Surrounding

1) Large commercial centers: On the Airport Rd. near the residential area is located with Guangdong Vehicle Market. It is the largest auto market in Guangzhou and has become a large distribution center for domestic and overseas autos. Within 1.5 km from the residential area are also located with two large comprehensive commercial centers: Lejia Plaza on Sanyuanli Ave. and Taiyang Plaza on Baiyun Shanlu. Three large trade centers available within 3 km from the residential area: Zhanlong Auto Part Center on Middle Guangyuan Rd., Meibocheng - a large display center for beauty parlor, hairdressing and cosmetics located on West Guangyuan Rd. Xianglongjia Digital Market and market for shoes located on Guanghua No. 1 Rd. will provide many employments for the citizens.

2) Surrounding developed communities: Along with the issuing of the planning of the Baiyun New City, many large living communities are constructed near the residential area. E.g. Times Garden, Yuanbang Aviation Garden, Baishuntai, etc., with increasing needs for housekeeping, repairing, cleaning, etc. There are many employments here.

3) Hotels and restaurants: Near Baiyun Airport. Within 1.5 km range, there are over a dozen hotels like Yiyin Hotel, Airport Hotel, Guangzhou Baiyun Airport Hotel, etc. Restaurants

l Liede Resettlement Implementation Plan

are like: Huirulou Seafood Restaurant, Chunqing Huowo Seafood City, etc. There are lots opportunities for service.

4) Schools: Many schools are located near the residential area: Fangyuan Experimental School, Xinshi Middle School, Municipal Architecture Engineering School, etc.

5) Hospital: The Airport Hospital is very close. The associated clinic of Guangzhou Chinese Medical University is within 2-2.5 km reach. Associated medical facilities are also provided in the nearby developed communities.

6) Park: The residential area is near the "City Lung" - Baiyun Mt. It goes less than4 km to the Sculpture Park, Yuexiu Park and Liuhua Lake Park.

7) Agro-market: Xinzhi Agro-market is within 1-2 km reach from the residential area. There are several large agro-market within the airport living quarters. All are not far away.

8) Stadium: Large stadium in Guangzhou - Guangzhou Stadium is within less than 2 km reach with advanced equipment and facilities, good for all kind of sports.

6.3.5.4 Associated Facilities of the Residential area

1) Scale of construction: Occupying 25,000 m2 land, with total building area of 65,4000 m2, including 41,000 m2 houses and 24,4000 m2 associated facilities.

2) Internal Facilities of the Residential area

2 (1) Zhongting Garden: Located at the heart of the residential area, occupying 6,000 m land. It is a water world surrounded by flowers and endless greening. It becomes a natural oxygen bar.

(2) Swimming pool: Occupying 700 m2 land. It is the best place for sport in summer.

(3) Moon Spring: A wonderful sight within the residential area. Spring at night with flashes , .* q and nice music, rather -. attractive. i Z~IWI ' A 4 lb j, (4)

> . ~ r-,

r I r*L ';.-k !..z., fl' c Liede Resettlement Implementation Plan

Recreation Center: Provided with badminton yard, nursery, Internet bar, coffee room, etc., the right place for recreation after working.

(5) Management of the residential area: 24 H security patrol, provided with intellectual system to provide comfort to the citizens. It is both safe and of high living quality.

(6) Surrounding living environment: There are several large living quarters nearby. By investigation, most residents in these communities are white-collars of large enterprises nearby, as well as the new businessmen of the clothing center, leather center. They are from various places with rich concepts and comprehensive.

6.3.5.5 Residential area Suitable for Resettlement

1) There are many developed communities near the residential area, up to 6 large commercial centers are located. There are many employment opportunities good for low consumption citizens.

2) The residential area is located in the heart of Baiyun New City newly planned. The consumption here is still low. It is suitable for citizens with low consumption.

6.3.5.6 Prospect of the Residential area

The residential area is located at the Baiyun Shanlu bearing the name of "Cloudy mountains and pearl-like water". Along with the municipality progress of Baiyun District, the associated facilities will be more and more, the strong "City lung" function of Baiyun Mt. will be more and more remarkable. Green and health are the concept to be pursued by modem people. Very soon, the existing railway in within 2 km from the residential

-4 -4

- I u9t--- - *uai.

4 . w~~~~~~~~~~~~~~~~~ ~ s

area will be modified into new railway for people. Subway Lin 3 will pass Tonghe District to connect the Airport. The services of Jingzhu Expressway, Guanghua Line, Air Liede Resettlement Implementation Plan

Expressway and North No.3 Ring-road will improve the connection to the east and west of Guangdong Province. The function of Jiebei Expressway and aviation center will increase day by day. It will be remarkable modem traffic center in Guangzhou, even in China. It will become a modern distribution center. When the old Baiyun Airport was relocated within 1 km from the residential area, Baiyun New City will be constructed on the existing site, with total area of 2.8 km2. Here will be a gathering place for electric appliances, supermarkets, restaurants, etc. The Baiyun New City will become an important center for living and trade. By then, there will be many employment opportunities. The public facilities will be well-furnished, bring great convenience to the living and working of the citizens.

6.3.6 Resettlement site Near Haijing Garden

Many gardens like Canada Garden, Jinhuaxuan Garden, Diecuitai, etc. are surrounding the Tianhe District, with Hiajing Garden in the center, may be used as residential area of the Project.

6.3.6.1 Geographic location:

1) Within Tianhe Park, located in the middle of the traffic trunk line of Huangpu Ave. Facing the conference * & exhibition center on the other bank of the river. It neighbors Huanan Expressway at left and Chebo Rd at right. It is rather close to the Government of Tianhe District. It will become the center of the city -

in future. . -- a

2) Distance to flourishing areas: It goes less than 1.5 km to the Pearl River Geographic layout of haijing garden New City via Huangpu Ave. Commercial and recreation is rather close. Going to Tianhe Downtown is also less than 2.5 km. Distance to Pazhou Conference & Exhibition Center

-new economic center of Haizhu District is less than 4 km.

3) Distances to large commercial centers: It takes less than 10 minutes to Tianhe City, Tianhe Stadium, Tianhe Book Center. Going to Tianhe Huanan Electronic City is just 4-10 minutes. It takes less than 10 minutes to Tianhe Shopping Center, to the Pacific Computer Center and Guangzhou Computer Center.

6.3.6.2 Traffic Conditions Liede Resettlement Implementation Plan

1) More than 20 bus lines are available within 200-800m in the residential area, such as 23, 43, 53, 177, 284, etc. Buses may go directly to Tianhe Bus Station and Guangzhou East Railway Station, to Jiangnan West Commercial street of Haizhu District, and Lower Nonglin Rd.

2) It is near the Huanan Expressway, near East Ring-road Expressway, Near Zhongshan Ave., Huangpu Ave. with convenient traffic going to all districts.

3) Public Facilities Surrounding

(1) Restaurant Within 1 km reach of the residential area are located with Tangxia Commercial Plaza, Lantiandi Restaurant within 1.5 km. It provides good environment for the Guangzhou People fond of having breakfast and late dinner in restaurants.

(2) Hospital: Within 1.5 km reach of the residential area is available with Huaqiao Hospital and Zhongshan No.3 Hospital. Guangzhou Post Hospital is less than 100 m from the residential area. Medical care is rather convenient.

(3) Recreation Centers: Within 1.2-2 km reach from the residential area is located with a large Tianhe Recreation City, serving cinema, climbing parlor, west food, game room, Internet bar, restaurants, etc.

(4) Supermarket: Large supermarket Trust-Mart is available within 200-800 m distance from the residential area. Shopping is easy.

(5) Schools: Nearby schools are: Huajing Primary School, Huashi Primary School, Yuancun Primary School, No.44 Middle School, Jinan University, Southern China Normal University, Provincial Post School, Guangdong Minority School, Guangdong Administrative College, etc. There is a good atmosphere of culture and education.

6.3.6.3 Planning of the Residential area:

1) Scale of construction: Total land occupied is 30,000 odd

m2 with total building area of more than

2 170,000 in . It is a living community in Tianhe District with high Liede Resettlement Implementation Plan

comprehensive figures.

2) Auxiliary Facilities of the Residential area

(1) Greening garden: The residential area is located within Tianhe Park. Is a greening sea of 780,000 m 2within the garden. It is an existing ecological forest in Guangzhou City. Super waterscape garden extends through the residential area and flows into Tianhe Park. The Central Park occupies 26,000 m2 land. There are lots of springs and clean pool. The established foot message passage brings lots of joy to players.

(2) Hotels and recreation: Within the residential area is available of a five-star hotel

-Haijing Hotel with good and luxury equipment, bowling parlor, laundry, commercial center, hairdressing and beauty parlor, digital cinema, canteen, conference rooms, Sauna, etc.

(3) Recreation of the residential area: Two recreation centers available, provided with library, billiards, chess and card rooms, bar, climbing parlor, basket ball, etc.

(4) Multi-function sports ground: International standard tennis yard, badminton sports facilities, etc. to off lovely life.

(Viewof haijing

garden) of Massage swimming poor: Occupying 150

.1 ~~~~~~~~~~~~~~~m2land with several massage springs. It is so comfortable.

(6) N ursery: Total building area of M2

Bilingual education offering living and sports courses. Good care of the children may release pressure of the citizens from their work.

(7) Pleasure ground for children: Many kinds of pleasure facilities available, a heaven for children. Liede Resettlement Implementation Plan

(8) Potable water system: Direct potable water system provided to house. They can enjoy spring water rich of future elements and valuable minerals.

(9) Services of the residential area: Based on modem digital technologies, offering three-star level

!- ,- i i smart- i ;Z-24 H1;1 i property

:F 7--- management

..---, _ r *.,._ s' 07 rs Ej ,, - --- t service of the

- \ ¶;_ _British [ _= *-style.

' r_-- -'Y - , Offering meals,

laundry, private ti-_( s"t'^'^S!-- ,,__e. * r °t m Ob >J2t - - i -- . 12 .. e

Broadband network: Fast speed to connect Internet. Citizens will enjoy the fast surfing brought by broad-band network, provided with

Apartment layout of haijing garden

services for securities, education, and medical care on Internet.

(11) House design: Ventilation and lighting from three sides and wide scale standing window, with dual balconies. Broad and bright indoors, living in green elevated garden.

6.3.6.4 Residential area Suitable for Resettlement

The residential area is located among the financial and commercial center at Tianhe North, Tianhe - - Software Park, - Wushan University Area, Guangzhou Birds' eye veiw of haijing garden Economic Development Zone and Guangzhou Scientific City. Along with the improvement of the surrounding facilities, cultural atmosphere and consumption level will go up day by day. It is a Liede Resettlement Implementation Plan good place for the resettlement of Financial, commercial, IT workers, teachers and officials of high education, high income. Besides, as it is near Tianhe Park with fresh air, it is also a good place for the aged.

6.3.6.5 Prospect of the Residential area

The residential area is located within Tianhe Park with beautiful environment and easy traffic. There is a potential development of business. All these bring this residential area a high level living community with high comprehensive figures. By Year 2010, the rate of ecological forest in Tianhe District will reach 60%. The ecological forest of the Tianhe Park will be come the primary ecological project of Tianhe District. The residential area will be more beautiful by then.

Huangpu Ave. is in the south part of the residential area while Zhongshan Ave. is in the north, both crosses with the longitudinal Tianfu Rd. The traffic is convenient. For education, there is a special nursery for the residential area.' Many primary schools and several key universities are not far away. It is convenient to have education. For living facilities, Wanjia Department Store will be open nearby by the end of the year. In terms of traffic, the Tianhe East express traffic network is almost finished. In two to three years to come, several expressways like Guangshen, Guanghui, Guangzhou North No.3 Ring Rd. and Guangyuandong, etc. will pass through Tianhe East. Besides, the Ring-road expressway connects Huanan Expressway to reach Panyu and Shunde, etc. Along with the modification of the one river and two banks as well as the development and construction of the Pazhou International Conference & Exhibition Center on the other bank of the river, the area where the residential area is located will be connected together with the "sub-center of the city" - Pazhou New City. Then this will be the largest downtown area in Guangzhou. There are lots of business opportunities.

6.4 Resettlement, compensation and rehabilitation plans for the PAPs

6.4.1 Resettlement, compensation and rehabilitation principles for the PAPs whose property is wholly and permanently affected

For the permanently& partially requisitioned citizen household, besides the compensation given in accordance with the regulation made by Resettlement Policy, the project shall adopt the following rehabilitation measures:

1) The project affected resident shall have 60 days preparation time before moving. It shall be calculated after the announcement of move notice. If the resident still has some difficulties, the project shall give appropriate help to the moving or elongate the Liede Resettlement Implementation Plan

preparation period if the construction schedule allows

2) The project shall reduce the damage to the community. The residents in the same sector, especially in the same unit, same mansion and same street, shall be considered preferentially to be move into the same residential area to keep the original social population and community relations.

3) The project shall be responsible for the reorganization of the neighborhood committee or residential area management in the residential area together with the local government and sub-district office to resolve safety, cleaning and other daily living problems that are faced by the residents and need help. The project shall arrange some commercial enterprises that sell daily household goods in the residential area to meet the daily life requirements of the residents.

4) The resettlement sites selected by the project are all provided with more than two bus lines. If the traffic of the residential area needs to be increased after resettling lots of PAP, the project shall be responsible for the coordination with public traffic department to increase bus lines and make the communication between the resettlement residential area and central area of the city more convenient.

5) The project shall still make great efforts to reduce the amount of demolition during specific demolition and resettlement. For the storied building that seems to be demolished necessarily and totally at present, the project shall work together with engineering experts. On the basis of guaranteeing the safety, partial demolition shall be considered.

6) The permanent move of the resident shall change the original living environment and the time of the scheduled traffic. So, the project shall mainly adopt resettlement in vicinity measure to keep the original living environment relate and community relations. At the same time, the resident can also choose the resettlement site where the traffic distance is shorter to shorten the traffic time and improve the availability of time by means of the demolition opportunity. According to the requirement of own development, the PAP can also choose other resettlement site provided by the project.

7) Based on the results of social and economic analysis of the project-related resettlement, there are few jobs for middle-aged women in Tianhe District, instead, housekeeping service needs high labor force. Therefore, the Project needs special care to women of three features (old age, low skill and low education) The Project will contact with the Labor and Social Securities Bureau in Guangzhou to sponsor these PAP's in accordance with "'Golden Key' Sponsorship Program of Guangzhou Employment Training" to arrange these people for housekeeping training.

8) The Project will try to arrange these women to residential areas of low level as lots of high Liede Resettlement Implementation Plan

and medium level buildings are arranged nearby which provided lots of cleaning and house-keeping jobs. For instance, arranging them to live in Zhongxing Garden (low level residential area) of Tianhe District, but surrounded by high level Haijing Garden, Scientific City and Yangcheng Garden, Yi'ange, Fuli Garden, etc. These developed communities will provide jobs and convenience for these women.

9) During the construction of pipe network, the project can temporarily rent the partially demolished house on the planning route, which was given up by the owner and still can be used, to the persons for whom it is difficult to obtain employment and let them operate small commercial firm along the planned route.

10) The PAP can select the resettlement site arranged by the project or look for the resettlement site by oneself. If the PAP selects the resettlement site the project plans to purchase in large quantities, the project shall negotiate with the realty management company of this resettlement site as far as possible to reduce the realty management charge in one month limitation..

6.4.2 Procedure and methodology of the resettlement, compensation and rehabilitation for the PAPs whose property is wholly and permanently affected

See Section 5.10.1 of the Resettlement Policy for the detail.

6.4.3 Resettlement, compensation and rehabilitation schedule for the PAPs whose property is wholly and permanently affected

See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resettlement Implementation Plan

7. Status of the permanently and wholly affected shops and the resettlement, compensation and rehabilitation plans for them

7.1 The wholly and permanently affected shops

7.1.1 Property right and distribution of the wholly and permanently affected shops Grade of area % of Property right Grade Grade Grade Total property Grade Grade right 1 2 ~~~3 4 Grade5 6 Housing with property right 1,037.92 1,037.92 55% Housing on residential plot 18.02 313.71 132.50 464.22 24% Constructions without right of land-use 333.05 64.13 397.18 21% Temporary structure before expiration - - - 0% Temporary structure after expiration or illegal structure - - 0% total 18.02 313.71 1,503.46 64.13 1,899.31 100% Distribution rate (%) 0% 1% 17% 79% 3% 0% 100% See Table7.1.1. for the detail

7.1.2 Structure of the wholly and permanently affected shops Attached table: 7.1.2. Brick and Grade of Framework Composite timber Simple total Grade of area structure structure structure area%

Grade I - - 0%

Grade 2 18.02 18.02 1%

Grade 3 165.66 45.30 102.74 - 313.71 17%

Grade 4 772.39 277.31 410.10 43.67 1,503.46 79%

Grade 5 - - 64.13 - 64.13 3%

Grade 6 - - - - - 0%

total 938.05 322.61 576.97 61.69 1,899.31 100%

7.1.3 Distribution of the wholly and permanently affected shops

Attached table: 7.1.3 Grade of I Housing with I Percentage the area of I Percentage I Subtotal of the I Grade of Liede Resettlement Implementation Plan

area property right housing area area % without preorty right

Grade I - - - 0%

Grade 2 18.02 0.02 18.02 1%

Grade 3 - 313.71 0.36 313.71 17%

Grade 4 1,037.92 1.00 465.55 0.54 1,503.46 79%

Grade 5 - 64.13 0.07 64.13 3%

Grade 6 0

total 1,037.92 1.00 861.40 1.00 1,899.31 100%

7.1.4 Distribution of the ownership of the wholly and permanently affected shops

See Table 7.1.4 for the detail.

7.1.5 Industrial distribution of the wholly and permanently affected shops

See Table 7.1.5 for the detail.

7.1.6 Business condition of the ownership of the shops wholly and permanently affected

See Table 7.1.6 for the detail.

7.1.7 Business condition of the industry of the shops wholly and permanently affected

See Table 7.1.7 for the detail.

7.2 Principle of the setup of resettlement sites for affected shops

1) The management environment relied by the operation of a commercial firm shall be divided into the following two sorts:

The first is the number of local inhabitants and floating population and their purchasing power, such as catering trade and general merchandise.

Business point index per 10,000 persons indicates the number of commercial facilities within regulated area owned by per 10,000 persons. According to the business points index per 10,000 persons of Guangzhou City, in a living area with concentrated population, no other than the business points index reaches to the following standard, a community shall be propitious to develop, living shall become convenient, and the Liede Resettlement Implementation Plan

supporting facilities shall be perfect.

The Business poinlts restaurant and index Wholesale and retail trades beverage industry

2002 225 48

Refer to Statistical Yearbook of Guangzhou (2003)

Among the resettlement area of the work, the business import index of District (see Table ) is less than the standard, so we take this area as the resettlenient sites of the commercial firms which rely on the number of local inhabitants and floating. population and their purchasing power. Therefore, not only the original operation of the commercial firm shall be kept, but also the commercial facilities of the resettlement sites shall be perfected, and so the life in the area shall become more convenient.

The second is that the commercial firm is not very relying on the local inhabitants and floating population, but mainly relying on the scale and traffic, such as building materials, auto car fittings, industrial products, and domestic electrical appliance, furniture, and durables. The characteristic of the existing large-scale markets of building materials, auto car fittings, and domestic electrical appliance is just like this: the position of the markets is some far away from the downtown but the scale is very large and the traffic conditions is very convenient. However there are hundreds of commercial firms in downtown.

2) The commercial firms relying on local inhabitants and floating population shall be relocated at the following areas: The inhabitant resettlement sites: In accordance with the number of the inhabitants, some commercial firms shall be relocated in the inhabitant resettlement sites to resolve not only the operation problems of the commercial firm, but also the commercial supporting facilities problems in the resettlement sites. According to the plan of Guangzhou City, the acreage of the commercial supporting facilities in the residential quarter shall reach to 8% of the resettlement sites.

Locally relocation: Some commercial firms shall be relocated at the edge zones of the demolished local place, not only to relocate the commercial firms but also to avoid of the commercial loss caused by the demolition.

3) The commercial firms relying on the operation scale and convenient traffic conditions shall be relocated in the coverage of the work. And the same and relevant trades shall be relocated in the same area to achieve scaled operation. Liede Resettlement Implementation Plan

4) The principles of using the resettlement site when establishing temporary commercial firms ( 1) Temporary commercial firms shall be set up for resettlement sites in the edge zones unsuitable to build permanent houses along the engineering section.

(2) The existing large markets in downtown

(3) The temporary commercial firms shall be relocated in accordance with their trades.

7.3 Description of the resettlement sites for the affected shops

1) The commercial firms relying on the operation scale and convenient traffic conditions As the social and economic investigation is still in process, the project has not classified these commercial firms yet. So the description shall be only that of the main professional markets in the resettlement area. Exclusive markets in Tianhe District (1) Exclusive markets of kitchen and sanitary things a. Nanguo Kitchen and Sanitary Things Center The geographic position:

It is on section of Chebei Road which is in south of Zhongshan Road (The map shall be supplied). The main merchandise: The center is presently the biggest kitchen and sanitary things market with property right. The main merchandise is all kitchen and sanitary things. The traffic conditions: * 18, 50, 53, and 39 shall be all passing the center. * The distance eastward to East Ring Highway is less than 1.5km, so it is very convenient for bus to reach every district from this center. (2) Exclusive market of stationary a. Tianyi Stationary Market The geographic position:

It is on Dongguanzhuang Road in the north and very beginning of Tianhe commerce loop, which is planned as the new axle wire of Guangzhou. (The map shall be supplied)

The operation scale: The acreage of the market is 50,000 square meters, in which only the acreage of the shop on the first floor reaches to 29,000 square meters, and the whole length of store fronts reaches to 1km. Liede Resettlement Implementation Plan

The main merchandise: Various office supplies

The traffic conditions:

* More than ten bus routes including 54, 89, 138, and 27 come and go from the central zones of Dongshan District and Zhuhai District to this market.

* The distance to East Railway Station is less than 1.5km.

* The market is southward connecting with the east of Guanyuan High-speed Trunk and a bus from the market shall be directly to Huangpu District.

(3) Exclusive market of computer and components a. Guangzhou Computer Market The geographic position: It is in the center of Tianhe District, and at the meeting point of East Tiane Road and the second section of South Tianhe Road.(The map shall be supplied) The main merchandise: Electron products, computers and supported product.

The traffic conditions:

* Several bus routes including 22, 43, 54, 62, 122, 177, and 185 may all reach to East Sport Stop.

* The distance to the exit of Gangding Underground Station is only 500m.

* The market is northward connecting with Tianhe Road, which is the arterial road of Tianhe District, so it is convenient for a bus to reach Dongshan District, Yuexiu District, and Huangpu District.

* Eastward via the high-speed trunk of South China, a bus shall be directly to Zhuhai District and Panyu District.

b. Nanfang Computer Market The geographic position:

It is in Nanfang International Commerce Mansion on Tanhe Road. (The map shall be supplied).

The main merchandise: Computer and supporting products.

The traffic conditions:

* More than ten bus routes including 22,-33, 178, 191, and 194 may all directly

I Liede Resettlement Implementation Plan

reach to this market.

* The distance to Gangding Underground Station is less than 600m.

* Eastward via the high-speed trunk of South China, a bus shall be directly to Zhuhai District and Panyu District.

c. Taipingyang Computer Market The geographic position:

It is in the south of Tianhe Road (The map shall be supplied)

The main merchandise: Computer and supporting products.

The traffic conditions:

* More than ten bus routes including 18, 22, 33, 178, and 191 may all reach to Gangding Bus Stop and then immediately reach to this market.

* The distance to Gangding Underground Station is less than 600m.

* The distance to the high-speed trunk of South China and Guangyuan Highway is both less than 2km.

(4) Exclusive market of dress a. Tianhe Hongcheng Commerce Plaza The geographic position:

It is in the east of Tianhe Road and Tianhe Plaza. (The map shall be supplied).

The main merchandise: Dress and general merchandise

The traffic conditions:

* More than twenty bus routes including 22, 33, 42, 89, 194, and 210 may all arrive this plaza.

* The distance to Sport Center Underground Station is only 200m.

* It is in the central zone of Tianhe District, westward or eastward via the arterial roads, which are Huanshi Road and Zhongshan Road, so a bus shall be conveniently to Dongshan District and Yuexiu District

(5) Furniture Exclusive Market The geographic position:

It is in Chebei-Longkou Industrial Area. (The map shall be supplied). Liede Resettlement Implementation Plan

The main merchandise: Furniture.

The traffic conditions:

* 234, 235, and 229 are all passing this market.

* it is Northward connecting with West Huangpu Road, so it shall be convenient for a bus to Huangpu District and Dongshan District.

(6) Exclusive market of building materials a. Nanxing Decorative Material Market The geographic position:

It is at the meeting point of the west of Huangpu Road and Haile Road. (The map shall be supplied)

The main merchandise: Various building and decorative materials.

The traffic conditions:

* More than ten bus routes including 53, 23, 39, and 42 may all pass the market

* It is in the south of Huangpu Road, and so a bus shall be conveniently to Dongshan District, Huangpu District, and Yuexiu District; Eastward via the high-speed trunk of South China and shall be directly to Zhuhai District and Panyu District.

b. Tianma Decorative Materials - --~-- Plaza The geographic position: - 1 1 II 11t2.. :i1 j ~~~I itE 1E O;TX It is at the meeting point of the west of '* T , Huangpu Road and Haiye Road. (The "l " i C map shall be supplied). - ' ' r

The main merchandise: Various L ! 1 ' r '' j IUl - building and decorative materials. The traffic conditions: 9 p * * It is closely adjacent to Nanxing hi is Decorative Material Market.

c. Xinghua Decorative Materials ' 4 ij Market Liede Resettlement Implementation Plan

The geographic position:

It is at the meeting point of Zhongshan Road and Fengye Road. (The map shall be supplied).

The main merchandise: Various building and decorative materials.

The traffic conditions:

* More than ten bus routes of 50, 139, 78, and 9 may all reach to this market.

* Westward via the high-speed trunk of South China, a bus from this market shall be directly to Panyu, Northward via Guangyuan Highway shall be directly to Dongguan, and eastward along Huangpu Road shall be directly to Huangpu District. 2) Resettlement site for commercial firms depending on residence and flowing population Tianhe District: Guangxing Yinglan Garden The geographic position:

It is situated at East Shipai Road and close to Jinan University.

The traffic conditions:

* More than ten buses, including 50, 18, 33 and so on, pass here.

* The distance to Gangding Underground Station is only 300m.

* The north end of East Shipai Road is connected with Zhongshan Road and directly leads to Huangpu District and Dongshan District. The south end is connected with Huangpu Road and directly leads to Liwan District, Yuexiu District. The east end is close to high-speed trunk in South China and directly leads to Panyu and Zhongshanide.

The building scale:

It covers 30,000 square meters, the building area is 79,000 square meters and the area for commercial firms accounts for 10.6% of total building area.

The facilities arround:

* It is close to Guofang Mansion, Custom Building and other high-grade office buildings. The development space of catering, laundry, news/magazine kiosk and other small commercial firms is very broad Liede Resettlement Implementation Plan

* It is located at prosperous business area. Mingjun Mall and Taipingyang Computer market is near this district. The requirement of drink, food and small commodities shall increase gradually.

* It is adjacent to Jinan University and Tianhe Middle School. Bookstore, news/magazine kiosk shall become hot business.

7.4 7.4Resettlement, compensation and rehabilitation plans for the wholly and permanently affected shops 7.4.1 Resettlement, compensation and rehabilitation principles for shops wholly and permanently affected For the permanently& partially affected merchandising business, in addition to the compensation made in accordance with the provisions of Resettlement Policy, the following rehabilitation measures shall be adopted:

1) The demolished commercial firm shall have 60 days preparation time before moving. It shall be calculated after the announcement of move notice. If the firm still has some difficulties, the project shall give appropriate help to the moving or elongate the preparation period if the construction schedule allows.

2) For the commercial firm that would like to operate for a period at the former place, it shall be demolished before commissioning under the precondition that it shall not affect the time limit of the project.

3) In principle, the commercial firms shall be given peer-to-peer resettlement in accordance with the former operation trade. If the operation state is not so good, change of the trade can be selected after being agreed by the property owner. The project shall take charge of helping it find appropriate operation site.

4) The project shall provide consultation information of the development direction and change of trade for the merchandising business in accordance with the analyses on social& economic environment of the resettlement. For example, the Project will focus on possible survival crisis of shops, such as small restaurant, wholesale business and retail business engaged in disadvantaged trades in the district. The Project will help them change their professions to promote their benefits, such as special Fast Foods and high-quality fruits business. Liede Resettlement Implementation Plan

5) If the property owner chooses to give up the property and wishes to operate in other places, the project shall provide service and help him or her to find appropriate hired commercial firm.

6) For the commercial firm that chooses resettlement, the project shall give 15 days rehabilitation period as compensation. The compensation standard shall refer to the compensation standard for the loss caused by the cession of business during temporary move.

7) If the commercial firms at the resettlement site lacks necessary facilities needed by their original industry, the PAP can choose compensation or the project shall provide rehabilitation.

8) If the commercial firm chooses the resettlement site that the project plans to purchase in large quantities, the project shall negotiate with the realty management company of this resettlement site as far as possible to reduce the realty management charge in appropriate term.

9) Because of the construction of pipe network, the project can temporarily rent the partially demolished house, which is on the planning route and was given up by the owner, to the persons for whom it is difficult to obtain employment and let them operate small commercial firrn along the planned route.

7.4.2 Procedure and methodology of the resettlement, compensation and rehabilitation for shops wholly and permanently affected

See Section 5.10. 1 of the Resettlement Policy for the detail.

7.4.3 Resettlement, compensation and rehabilitation schedule for shops wholly and permanently affected

See Section 5.10.2 of the Resettlement Policy for the detail Liede Resettlement Implementation Plan

8.Status of the permanently and wholly affected enterprises and the resettlement, compensation and rehabilitation plans for them 8.1 Distribution of the wholly and permanently affected enterprises

8.1.1 Property right and distribution of the enterprises wholly and permanently affected Grade of area % of Property right Grade Grade Grade Total property Grd 2rd Grd Grd Grd5 Grade 6 right

Housing with property right 397.96 774.75 1,172.71 43% Housing on residential plot - 381.01 - 381.01 14% Constructions without right of land-use 319.13 212.09 212.32 248.01 991.55 37% Temporary structure before expiration - 101.37 - - 101.37 4% Temporary structur after expiration or illegal structure - 58.34 58.34 2% total 717.09 694.47 1,045.41 - 248.01 2,704.97 100% Distribution rate (%) 0% 27% 26% 39% 0% 9% 100% See Table8.1.1. for the detail

8.1.2 Structure distribution of enterprises wholly and permanently affected

Attached table: 8.1.2

Grade of Composite Brick and Simple Grade of structure tur structure area % area structure

Grade I

Grade 2 462.42 132.90 121.78 717.09 27% 26% Grade 3 - 156.20 381.01 157.26 694.47 39% Grade 4 - 153.56 757.07 134.77 1.045.41

Grade 5 - - - - 0%

Grade 6 - - 248.01 - 248.01 9%

total 462.42 442.66 1,386.09 413.81 2,704.97 100%

8.1.3 Distribution of enterprises wholly and permanently affected

ofI areaG ad | Housing with Housing without Total Grade ofara Property right Property rig ht Tianhe District_2A 397.96 34% 319.13 21% 717.09 Liede Resettlement Implementation Plan

Tianhe District3B - 0% 694.47 45% 694.47

Tianhe District_3C - 0% 92.28 6% 92.28 Tianhe District_4B 774.75 66% 178.38 12% 953.13 Tianhe District_4C - 0% - 0%

Tianhe Distnct-5A - 0% - 0%

Tianhe District_6A - 0% 248.01 16% 248.01

Tianhe District_6B - 0% - 0%

Tianhe District_6C - 0% - 0% ______total 1,172.71 100% 1,532.26 100% 2,704.97 See Table8.1.3. for the detail

8.1.4 Distribution of the ownership of the wholly and permanently affected enterprises

See Table 8.1.4 for the detail.

8.1.5 Trade distribution of the wholly and permanently affected enterprises

See Table 8.1.5 for the detail.

8.1.6 Business condition of the ownership of the wholly and permanently affected enterprises

See Table 8.1.6 for the detail.

8.1.7 Business condition of industry of the enterprises wholly and permanently affected See Table 8.1.7 for the detail.

8.2 Principle of the setup of resettlement sites for affected enterprises

The industrial enterprise resettlement sites need firstly occupancy for plant and depots, and then for office. The setting up principles of the resettlement sites shall be shown as follows:

1) The setting up principles of plant and depot occupancy

(1) The traffic of the resettlement sites of the plant and depot occupancy Liede Resettlement Implementation Plan

shall be considered enough. Some improving measures may be taken. For instance, two or more bus routes shall be directly to the center, and the environmental road shall be unobstructed so that the buses may be directly to downtown. And besides, according to the perspective plan of the underground, all the resettlement sites shall be located in the area where the underground reaches.

(2) The public utilities and supporting facilities of the plant and depot resettlement sites shall be all ready, the former including roads, water, electricity, communication, post and network, and the latter including education, sanitation, commerce, gardens and culture.

(3) The energy sources shall be supplied enough for the plant and depot resettlement sites, so that the demand of traffic, power supply, water supply, gas feed, telecommunication and drain contamination which are all necessary for production shall be satisfied.

(4) The resettlement site of the plant shall be near to the industrial base, so that the same kinds of plants may share the supporting facilities and components suppliers, and the client resources shall be concentrated. In the meantime, the resettlement site of the depot shall be near to transportation center or materials circulation center such as the railway station or bus station, so that the freightage shall become convenient.

(5) The environment around the resettlement sites of the plant and depot shall be not polluted by the relocated plant or depot, the public security, environment, virescence and the supporting facilities of the vicinity shall be kept at the initial level.

(6) The land shall be concentrative and level to ensure convenience for the relocation of plant and depot.

(7) The distribution of industry shall be concerted and assorted with town dweller points, so that it shall be convenient for production development and environmental improvement.

(8) The building density shall be not more than 40% and the green area shall be not less than 30%. Liede Resettlement Implementation Plan

(9) Some built, being built, or to be built industry parks and depot shall be used for resettlement sites.

2) The setting up principles of office occupancy:

(1) The traffic of the resettlement sites of the enterprise and office occupancy shall be considered enough. Some restoration measures may be taken. For instance, two or more bus routes shall be directly to the center; and according to the perspective plan of the underground, all the resettlement sites shall be located in the area where the underground reaches.

(2) The public utilities and supporting facilities of the enterprise and office resettlement sites shall be all ready, the former including roads, water, electricity, communication, post and network, and the latter including education, sanitation, commerce, gardens and culture.

(3) The public security of the resettlement site of the enterprise and office shall be well, police substation shall be established every square kilometers.

(4) The resettlement site of the enterprise and office shall be near to developed commercial area, backbone road, client group and product markets.

8.3 Description of the resettlement sites for affected enterprises

1) Resettlement sites for enterprises

(1) Tianhe District (2) Jinrun Mansion The geographic position:

It is on the middle section of West Longkou. The traffic conditions:

* More than ten bus routes including 133, 18, and 39 are all directly to Jinrun Mansion.

* The distance to East Railway Station is 2km. Liede Resettlement Implementation Plan

* North of it is Guangyuan Highway and shall be directly to Huangpu District, Baiyun District, as well as south of it is North Tianhe Road and then shall be directly to the prosperous area of Tianhe District.

The facilities around:

Around Jinrun Mansion, there are several high-grade office buildings including Sun Plaza and Tianlong Mansion, as well as some large mature buildings including Dijing Garden, Suiyuan residential area, and Jintianhua Garden and so on. So the supporting facilities around Jinrun Mansion are very perfect.

Tianhe Entertainment Plaza and Tianhe Cinema are both less than lkm away from the office building. So amusement shall be colorful during off hours.

2) Industrial resettlement site

Yunhe Industrial District:

(1) Geographical position: Yunhe Industrial District is located in west of New Guangcong Line, north of North 2nd Ring Express, east of National Highway No.106 and south of Baiyun Line No.6. In addition, it is located in edge of four towns, Taihe, Zuliao, Renhe and Longgui (including Guangzhou Private Enterprises Technology Park).

(2) Traffic:

a. North 2nd Ring Express and North I" Ring Express are connected with downtown directly. New Airport Line is very near and connected with National Highway No.105 and No.106. The traffic condition is convenient.

b. It is connected with Guangzhou Urban Zone by New Guangcong

Line and connected with Guangzhou New Airport by North 2nd Ring Express and New Airport Express. In addition, it is near Jingzhu Express. The traffic condition is convenient.

c. Distance to New Airport is only 8 km.

d. Distance to speed-up Jingguang Railway is only 8 km.

(3) Layout of Industrial District: kiuAtriad P4irKsBaiyun Dist irt,C, : To Caghua 'ToConghua

To Hundu- |I/

§ii- Tb u | _ __

ToZaQi{,,,t0 |0\_\.

rel vF-|-, | l,;D-s S - Al r~~~±~l

To Foshan To Shenzhen To Shenzhen Overall plan of Yunhe Industrial Zone

a. Scope: Redline controlled area of district layout is 18100 Mu (including 1250 Mu of original Private Enterprise Technology Park). There are totally 22280 Mu together with village land. Thereof, occupied farm land is 4650 Mu and agricultural land conservation district is 6950 Mu. Four towns and ten villages, such as Renhe, Longgui, Taihe and Zuliao, are involved in district layout scope. Thereof, 3830 Mu of Renhe, 3140 Mu of Longgui, 7600 Mu of Taihe and 3530 Mu of Zuliao. Construction land use for primary layout is 7100 Mu (including 1000 Mu of Private Enterprise Technology Park and 6100 Mu of others).

b. Inner supporting facilities of Industrial District:

a) Foundational facilities of the Industrial District, such as water supply,

View of Yunhe Industrial Zone Liede Resettlement Implementation Plan

electricity supply, communication and post, are complete.

b) The lands are concentrated and land form is flat.

c) Six "connection" and one "Flat" (Road, water, electricity, communication, post, gas and flat land) are realized.

c. Peripheral supporting facilities: there are idle house (or house built up by raised money) and Taihe warehouse for development of industry. The condition is good.

(4) Developing direction and key point: Based on existing industrial foundation, actively develop pollution-free traditional dominant light industry, aviation food industry and technical industry, absorb outward industrial enterprises. In addition, develop dressing, hardware and machine, entertainment equipment, decoration material, food and other industries. Thereof, original Guangzhou Private Enterprise Technology Park emphasizes on developing high-tech product. Depending on Laili Group and world-famous Tianjian Group, develop food, decoration material and other industries. Affected by development of Guangzhou International Air Port, peripheral logistics and real estate of Yunhe Industrial District will also develop rapidly. It provides advantages for development of the district.

8.4 Resettlement, compensation and rehabilitation plans for wholly and permanently affected enterprises

8.4.1 Resettlement, compensation and rehabilitation principles for wholly and permanently affected enterprises To the permanently and partially affected industrial enterprises, besides the resettlement policies stipulated in Section 5.7.7 of this Resettlement Policy, the project shall provide the following restoration measures:

1) The original estate of the industrial enterprises: The land, houses, buildings, roads, electricity power, and electric pipelines shall all be compensated in accordance with relocation price or be restored in accordance with the original scale.

2) The equipment damaged due to moving of the industrial enterprises and the installation, Liede Resettlement Implementation Plan

debugging charge of the equipment shall all be compensated. If there occurs difficulty, the project shall provide help in terms of installation and commissioning, which includes retaining the experts and expense will be paid by the project.

3) During the restoration and reconstruction of the industrial enterprises, the project shall provide help in planning and construction reporting.

4) According to the industrial distribution and plan of Guangzhou City and the original production trade of the industrial enterprises, the project shall locate the enterprises at appropriate area to ensure the necessary demands of traffic, power supply, gas feed, and drain contamination, and ensure that the production cost of the enterprise shall not be improved due to moving.

5) If an industrial enterprise hopes to change the trade, the project shall be responsible for locating the enterprise at an appropriate industrial area, and shall make the best to help the enterprise to change products and transit placidly.

6) Most enterprises in the district are engaged in high-tech industry according to the socioeconomic analysis. The traditional small factories have relatively small developing space, so the Project will give certain help and consultation service to them. For example, the factory may provide support service to the high-tech enterprise (such as packing service) or remove to another industrial park.

7) During the moving, the industrial enterprises may select to accept the compensation, as well as select to receive the moving service provided by the project.

8.4.2 Procedure and methodology of the resettlement, compensation and rehabilitation for wholly and permanently affected shops

1. Procedures and methods with generality are included in Section 5.10.1 of the Resettlement Policy.

2, A big number of resettlement will be caused for the sewage pipe network. However, the shops and enterprises affected by the pipe network are all those with small scale and therefore, they do not have high requirement of the relocation. Whenever there is any special requirement the project resettlement implementing agencies will help them to reconstruct the buildings. So as to ensure that their employees will not loss their jobs due to the resettlement and compensation for the real stop-loss will be provided. Liede Resettlement Implementation Plan

8.4.3 Resettlement, compensation and rehabilitation schedule for enterprises wholly and permanently affected

See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resettlement Implementation Plan

9.Status of the permanently and wholly affected commonweal units and culture relic and the resettlement, compensation and rehabilitation plans for them 9.1 Status of the permanently affected commonweal units

Item Area Property Usage District Storey Unit Total Total Floor grade right floor demolished area on area area land ______borrowed Liede III 3 Residential Others Tianhe I Tangxia 358.48 25.62 0.00 plot Primary ______~~School 4 With Housings Tianhe 2 Dongpu 911.36 64.30 45.18 property Primary right School Others 3 Chebei 652.28 38.01 0.00 Clinic Residential Others Tianhe 2 Peiyi 1113.00 138.31 147.74 plot Primary ______S cho o l______9.2Resettlement, compensation and rehabilitation plans for affected commonweal units

9.2.1 Resettlement, compensation and rehabilitation principles for affected commonweal units For the partially but permanently affected commonweal units, the project will carry out the following restoration measures in addition to implementation of the regulations related to resettlement and compensation in Section 5.7.8 of this Resettlement Policy:

1) For the requisitioned commonweal units such as the only district hospital, school or subdistrct office, which functions absolutely necessarily in the original community, the project shall plan a resettlement site in the same community.

If the requisitioned commonweal units can be relocated, the project shall consult to the city-planning department for moving such entity to a more necessary place, for example, to a resettlement site to receiving a large number of PAPs. To take the advantage of the resettlement, the city resources can be readjusted and redistributed more rationally.

2) Under the condition that the related regulation is complied with, the project will readjust the internal structure and functions of the resettlement site according to the commonweal units so as to increase the social serving function and service level taking the occasion of the relocation. If the above cost exceeds the reciprocal compensation range, the project will settle the account difference with the commonweal units based on the construction cost price.

3) The commonweal units can make a choice between receiving relocation fee and being relocated by the project. Liede Resettlement Implementation Plan

9.2.2 Procedure and methodology of the resettlement, compensation and rehabilitation for property owners

1. Procedures and methods with generality are included in Section 5.10.1 of the Resettlement Policy.

2. Since the number of affected commonweal units is small the situation is quite special the project will pay special attention to the resettlement of these commonweal units.

9.2.3 Resettlement, compensation and rehabilitation schedule for affected commonweal units

See Section 5.10.2 of the Resettlement Policy for the detail

9.3 Status of culture relic There are not any such situation found during the survey. 9.4 Resettlement, compensation and rehabilitation plans for culture relic 9.4.1 Resettlement, compensation and rehabilitation of culture relic According to the Law of the Protection of Cultural Relic of People's Republic of China and the World Bank guidelines on cultural relic OP4.11 the project will pay attention to the protection of cultural relic and the following measures will be taken: 9.4.1.1 Determination of cultural relic 1. To establish the reporting mechanism. Whenever there is any ancient cultural relic found the surveyor or implementer shall report to the project owner immediately. 2. The project owner shall send staff to the local neighborhood or village for information about the year and history of the said structure. 3. The project owner shall, associated with Guangzhou Culture Bureau, carry out the site investigation if there is a lack of information or determination of the said building because of the long years. 9.4.1.2 Protection of the cultural relic After the structure to be requested is confirmed as cultural relic, the following measures will be taken to protect it: l.Try to modify the design scheme so as to avoid the requisition of the cultural relic. 2.When it is impossible to modify the design, try to take engineering measures to avoid demolition of the cultural relic. 3.When it is impossible to avoid demolition of the cultural relic with engineering measures, try to move horizontally away the whole structure so as to keep the original look of the building and Guangzhou Culture Bureau will supervise the whole process. 4.When it is impossible to move horizontally away the whole structure detailed record shall be taken for each piece of the construction material before the demolition according to the Liede Resettlement Implementation Plan

regulation of the Reconstruction of Cultural Relic. The demolished structure shall then be rebuilt on another site and rehabilitate to its original look. Guangzhou Culture Bureau will supervise the whole process. 9.4.1.3 Resettlement of the user of the culture relic (structure) After the requisition of a cultural relic, the user of the culture relic will be resettled by the project and the resettlement and compensation will be carried out according to the provision of this Chapter. 9.4.1.4 Handover of the culture relic After the culture relic is horizontally moved or rebuilding. it shall be then handed over to the culture bureau at municipal or district level. 9.4.2 Procedure and methodology of the resettlement, compensation and rehabilitation for cultural relic

Protection of the cultural relic is a special case. The project will consult with the accountability units and experts concerned and work out the special relocation scheme of the cultural relic. The case will be reported to the World Bank one month before the relocation.

9.4.3 Resettlement, compensation and rehabilitation schedule for affected cultural relic

The schedule will follow the real time needed for the relocation of the historical relic and will not be restricted by the project implementation schedule Liede Resettlement Implementation Plan

10. Status of the institutions and the resettlement, compensation and rehabilitation plan for them 10.1 Brief introduction of the institutions

See Table 10.1 for the detail of the property right and distribution of the buildings of the institutions.

10.2 10.2Resettlement, compensation and rehabilitation plans for affected institutions

10.2.1 Resettlement, compensation and rehabilitation principles for affected institutions

In addition to the implementation of the regulations related to resettlement and compensation in Section 5.7.9 of this Resettlement Policy, the project will also help the affected government organizations with their relocation:

1) If the project hag affected the real estate of the government organization, the project shall contact to the planning department for the reconstruction in the original place as far as possible. 2) For the reconstruction of the constructional works, the opinion of the government organizations shall be fully adopted and the original function of the works shall be increased as far as possible taking the occasion of the reconstruction. If the reconstruction cost exceeds the reciprocal compensation range, the project shall close the account difference based on the cost price with the commonweal units. 3) During the resettlement, the project will take all the possible measures such as changing the line so as to avoid the loss of the government organization and the consultation charge occurs during such period shall be held by the project. 4) During the pipeline construction, the project will take all possible measures to shorten the construction period as far as possible so as to reduce the interference with the normal service of the government organization. 10.2.2 Procedure and methodology of the resettlement, compensation and rehabilitation for affected institutions

See Section 5.10.1 of the Resettlement Policy for the detail. Note: Institution refers to large-scale working units. The resettlement method of its residential houses, individual shops and enterprises has been included into that for houses, shops and enterprises. The resettlement here only involves some structures and buildings used by these institutions. Therefore, there will not be any impacts on these institutions and they can meet the need through internal adjustment of their buildings. Liede Resettlement Implementation Plan

10.2.3 Resettlement, compensation and rehabilitation schedule of the institutions

See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resettlement Implementation Plan

11.Status of the rural areas and the resettlement, compensation and rehabilitation plans for them

11.1 Basic status of the rural areas

This project will impact 9 villages. Including Huang Village, Tangdong Village, Chebei Village, Longdong Village, Tangxia Village, Shidong Village, Xintang Village, Changpeng Village and Cen Village, . (See Attached Table 11.1 for the detail)

11.2 Basic condition of the labour force

There are not any census data at moment. The reason is that all the nature villages in Guangzhou have transferred into the neighborhood committees. The system of production contracted to the household was not executed any more as early as in the year of 2000. Therefore, the impact of the land requisition is only on the village collectives but not the individual peasant household. In addition, according to the land requisition procedure in Guangzhou the potentially affected villages will hold the meeting with all villages to discuss about the issue only after the land requisition procedure starts. Those specifically affected villagers will then become surplus labors, namely the PAPs. At present the concrete number of the PAPs caused by land requisition is not able to be determined.

11.3 Resettlement, compensation and rehabilitation plan for rural areas

11.3.1 Resettlement, compensation and rehabilitation principles for the affected rural areas The following resettlement measures will be taken by the project in addition to the implementation of the regulation for rural labor force resettlement and compensation in "Resettlement Policy": 1) During construction of Liede Project (Phase m)wastewater treatment plant and the pipe network, the young and middle aged people in the countryside PAP will be employed in priority when temporary labor is needed. 2) If the present wastewater treatment plant can provide any posts with low technical requirements (or being at post is possible after certain training), such as truck men, doorkeeper, truck drivers, cleaner and etc, the project will contact to the wastewater treatment plant for the employment of the countryside PAP in priority. 3) The project will contact to the labor employment training organization to have the necessary mental instruction and skill training for the countryside PAP for them to smoothly get out the restoration period and obtain new skills. 4) The project will negotiate with the property company in resettlement site for providing Liede Resettlement Implementation Plan

job opportunity such as safeguards and safekeepers to the young and middle aged men in the countryside PAP. 5) The project will contact to the property company in resettlement site and the subdistrict household service points for providing jobs such as cleaner and household servers and etc for the young and middle aged women in the countryside PAP. 6) Economist will be consulted for the application, investment and overall economic development for the countryside compensation fund so as to help the affected countryside reasonably arrange the compensation fund and increase the economic interest and benefit the affected countryside PAP. 7) During the construction of the pipe network related to the planned road, the project will restore and even improve the original countryside road and traffic network. 8) In a careful discussion manner in the affected countryside, the young adults with certain skills shall be arranged in priority for turning to nonagricultural trades from agriculture. 11.3.2 Procedure and methodology of the resettlement, compensation and rehabilitation for affected rural areas 1. Determination of the boundary and nature of the land in rural areas

2. Conducting negotiate about the land compensation

3. Issuing the notice for land requisition

4. Carrying out survey on agriculture labors

5. Determination of the surplus labors and the elders

6. Carrying out training aiming at agriculture labors

7. Providing employment posts to each labor with 3 posts for choice

8. Reviewing the employment posts provided by the village-run enterprises to determine whether the posts are suitable for the surplus labors and if not the villages will be asked for improvement.

9. The employment situation of the surplus labors will be traced upon to ensure that they will not be fired within two years.

10. Procedures and methods of the resettlement, compensation and rehabilitation of other structures are included in Section 5.10. 1 of the Resettlement Policy.

11.3.3 Resettlement, compensation and rehabilitation principles for the affected rural areas

See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resettlement Implementation Plan

12.Status of the vulnerable group and the resettlement, compensation and rehabilitation plans for them 12.1 Basic situation of the vulnerable group

Vulnerable groups is not a really affected kind by project, it is a group of people needed special attention among all affected kinds. According to the scope definition about vulnerable groups in Section 4.3.3 of the "Resettlement Policy", the general conditions of the sub-item disadvantageous are groups as follow: Below the poverty line: 44 households

Elders without children: Nil

Single female: 9 persons

Orphan: Nil

Indigenous people not merged in the community: Nil

People without skill and employment: Not found

People not protected by state laws: Not found

Note:

1. Analysis on vulnerable group for the PAPs who rent housings with market price and the PAPs whose property is partially affected or temporarily affected was not conducted since the impact of the project on citizens is not big.

2. Analysis on vulnerable group for shops, enterprises and institutions was not able

to be conducted since only the number of staff was provided during the survey.

3. During the implementation of the project the PAPs belong to the vulnerable

group will be determined according to the definition and the compensation and

rehabilitation policy stipulated in this Chapter will be implemented for them.

12.2 Resettlement, compensation and rehabilitation plans for the vulnerable group

12.2.1 Resettlement, compensation and rehabilitation principles for vulnerable group

The project will give vulnerable groups the following help besides resettlement and compensation provided in "Resettlement Policy":

1) The people below poverty line (1) Project will resettle them in the resettlement site with low consumption level as far as possible where there are high and middle class residential area, large-scale commercial Liede Resettlement Implementation Plan

mall, special shopping stores, restaurants and etc where they may offer many jobs such as housekeeping, cleaning and etc. Such Zhongxin Garden etc. in Tianhe District, Beili Garden etc. in Baiyun District, Jinmeigui Yuan etc. in Haizhu District, Yifang Yuan etc. in Fangcun District and Lihumingyuan and Nanyuan Garden in Liwan District. (2) If the houses of PAP's locates along the new roads after demolition, according to the policy of city commercial net and points planning the project will contact with planning and house management departments to help change the house function (from house to commercial firm), let them run different small stores to support their lives. (3) The project will contact the Developer for resettle them in the first floor (if there is such house) and let them run different small stores to support their lives. (4) The project will contact the community office and realty management department for introduce jobs of housekeeping or arrangement of them to the near commercial firm in priority. 2) The elderly persons, the disable and chronic patient without children. (1) The elderly persons, the disable and patient will be resettled in relatively low floors. (2) The family with elderly person (patient, disable) over 65 will be resettled in house below 5th floor. (3) The project will resettle them in the residential quarter near medicinal care service unit. For example, the percentage of aged people in Liwan District is high. It is 20% of the total population. Therefore, the project will resettle them in Lihu Garden and other living quarters where there are several hospitals nearby and their hospitalization and health care is convenient. 3) Single women Single women will be resettled in the living quarters in good public security and sanitary facilities. 4) Orphans without income Resettlement house. The project will contact with the district offices, schools and civil administration departments for providing and support and help for the orphans during the resettlement. They should be especially resettled in the finished houses. 5) Minority nationality outside the society As for the PAP from minority nationality and etc, the project will resettle them in the tolerable resettlement sites where the habits and customs of minority nationality are not discriminated. 6) People without fortes and stable jobs (1) The project will contact with the Developer of resettlement house for providing them with the simple jobs in the property management agency of the quarters. (2) During the construction of pipe network, if some houses along the planned roads and abandoned by the Employer can still serve, the project will rent them to the vulnerable Liede Resettlement Implementation Plan

groups in priority so that they may run small commercial firms along the roads. 7) People not protected by national law For the PAP with only houses without property rights, the project will rent houses equal to the original in living and business conditions to them according to the public house renting standard 8) Others The project will pay attention to the vulnerable groups (aged people with adults living together, widows, single parent families, handicapped people, chronic patients and impoverished families). During the demolition, preferential policy will be carried out for them and care will provided to them in their housing and employment. After their relocation, regular revisits will be performed so that the very impoverished families can obtain help and support till them have been taken over by the civil administrative departments. 12.2.2 Procedure and methodology of the resettlement, compensation and rehabilitation for vulnerable group

1. Procedures and methods with generality are included in Section 5.10.1 of the Resettlement Policy. 2. The project will provide assistance to the vulnerable group on their living, business operation and employment during the project implementation. 3. Whenever there is any dispute the project will provide legal remedies to the vulnerable group 4. After the resettlement, the project will carry out the housdhold interview with the vulnerable -group and pay attention to their living and busines conditions till the handover of them to the civil administration department. 12.2.3 Resettlement, compensation and rehabilitation schedule for vulnerable group See Section 5.10.2 of the Resettlement Policy for the detail. Liede Resetlement Implementation Plan

13. Explanation on preparation of resettlement and compensation standard for Guangzhou Urban Environmental Project 13.1 Compensation standard for land

13.1.1 Compensation standard for land requisition (please see Annexed Table 13.1.1) 1) Basis for compensation standard Basis for the compensation standard * Article 47 in Land Administration Law of the People's Republic of China; * Article 30 in Enforcement Method of Guangdong Province for Land Administration Law of the People's Republic of China * Provisional Regulations on Compensation and Resettlement of Peasant Collective-owned Land Requisition for Construction Land in Guangzhou (Exposure Draft) 2) Determination of compensation base number According to the above regulations, the compensation base number is the average annual output of the requisition land in the previous three years. Due to the large range of the wastewater project which covers several villages in different districts, and presently, the district statistic bureaus can only provide the statistics data of partial villages, this compensation standard list only shows the compensation base numbers for the villages for which the statistics data have been provided. For the other villages, the base number for the adjacent village will be referred to for the base number determination (criteria has been provided in the list). 3) Land compensation fund * Calculation formula Land compensation fund=compensation base number x compensation times * Determination of compensation times For the reason that the wastewater project belongs to municipal project, the compensation fund may be on the low side. Therefore, for the compensation times in this project, the lower limit in the range of various land compensation times listed in Clause 30 in "Implementation of 'Land Administration Law of the People's Republic of China' in Guangzhou Province " will be referred to. Liede Resettlement Implementation Plan

Compensation times Times range stipulated in adopted in Guangzhou Province the project Basic farmland 8'- 10 times 8 times Plowland Nonbasic 6-8 times 6 times farmland Agricultural land Fish pond 8-12 times 8 times Garden plot Forest land 5-7 time 5 time Grassland and feed land Rural Agricultural construction land construction land Non-agricultural construction land 6-8 times 5 times

Other rural land _ 3-4 times 3 times

4) Resettlement compensation * Calculation formula Resettlement compensation=compensation base number x compensation times * Determination of compensation times Due to the lack of statistic data in the statistics bureau about the land holdings per capita, the agricultural population to be resettled cannot be calculated and it is impossible to work out the resettlement allowance based on the population. Thus, in the project, the method in "Provisional Regulations on Compensation and Resettlement of Peasant Collective-owned Land Requisitioned for Construction Land in Guangzhou (Exposure Draft )" has been referred to so as to work out the resettlement allowance based on times. In this criteria, the compensation times is determined referring to the related regulation in "Provisional Regulations on Compensation and Resettlement of Peasant Collective-owned Land Requisitioned for Construction Land in Guangzhou (Exposure Draft )" and is adjusted based on the following circumstances. * Resettlement allowance for plowland. Due to the large area, Baiyun District is subdivided. For Songzhoujie near to the urban district, 12-time will be adopted and 5-time for Taihe Town and Renhe Town far away from the urban district. 5-time is given for Liwan District in the original regulation, and 13-time is adopted in the project considering balancing it to that for the other old urban district. See the following list for comparison details: Liede Resettlement Implementation Plan

Times provided preliminarily . .in_discussiondraft Times in the project Haizhu l5times 15times District Fangcun 14times 14times District Liwan 5times 13times District Taihe 5times

Town ______Baiyun Renhe 5times 5times District Town Songzhou 12times Jie Tianhe 12times 12times District Huangpu 12times 12times District

Resettlement allowance for other agricultural land except plow land. 5-time is given as the calculation times for other agricultural land except, however, 3-5 times is provided in the provincial regulation. As the project is a municipal works, the lower limit is adopted here. 13.1.2 Compensation for retracted land and free land (See Annexed Table 13.1.2 for details)

13.2 houses with property right compensation standard

1) Compensation for dwelling houses with property right (See Annexed Table 13.2.1 for details) (1) This price system is based on the second-hand house market investigation and real estate assess and the 8 administration districts of Guangzhou City, and 6 classes are defined for each district considering various factors including district environment, surrounding facilities, traffic, economic level, population, social environment and land application state. The compensation price grades are clearly defined according to these two standards. Due to the obvious difference of house price in different locations in Class 1-3 districts, the price fluctuation is obvious while the price fluctuation is tiny in Class 4-6 districts. (2) Based on the experience, the compensation standard is given considering the frame structure, composite structure, brick and timber structure, simple structure and shed structure. (3) Based on the experience and second-hand house price, the compensation standard for the houses depreciation is regulated in terms of different service life such as less than five years, 5-15 years, 15-25 years, 25-35 years and over 35 years. Liede Resettlement Implementation Plan

2) Compensation for commercial houses with property right (See Annexed Table 13.2.2 for details) ( 1) This price system is based on the second-hand house market investigation and real estate assess and the 8 administration districts of Guangzhou City, and 6 classes are defined for each district considering various factors including district environment, surrounding facilities, traffic, amenity degree of the shopping environment, land application state economic prosperity degree, business scale and congregation degree. The compensation price grades are clearly defined according to these two standards. Due to the obvious difference of house price in different locations in Class 1-3 districts, the price fluctuation is obvious while the price fluctuation is tiny in Class 4-6 districts, which is near to the price for office houses with property right. (2) As for the commercial houses with property right, the compensation price is fluctuated based on the district economic prosperity degree. Therefore, the compensation standard is stipulated in terms of commercial road, common street and alleyway. Commercial road locates in the prosperous central section, which belongs to Class 1-3. ( 3 ) The price for ground floor, the first floor and the second floor and the floor above second floor decreases by degree. The compensation for commercial firms above second floor in Class 1-3 district is slightly higher than that for office houses with property right while compensation for commercial firms above second floor in Class 4-6 districts is near to that for office houses with property right. (4) The price of ground floor commercial firms varies much depending on the longitudinal depth; therefore, the price in the compensation standard is decreased by degree in term of the depth of 0-12 m; 12-24m, depth above 24m. in Class 1-3 district, the price fluctuation of the three grades is obvious and that for Class 4-6 fluctuates slightly. ( 5 ) Based on the experience, the compensation standard are made considering the frame structure, composite structure, brick and timber structure, simple structure and shed structure of the houses in each building plot. (6) Based on the experience and second-hand house price, the compensation standard for the houses depreciation is regulated in terms of different service life such as less than five years, 5-15 years, 15-25 years, 25-35 years and over 35 years. 3) Compensation for office houses with property right (See Annexed Table 13.2.3 for details) (1) This price system is based on the second-hand house market investigation and real estate assess and the 8 administration districts of Guangzhou City, and 1-6 classes are defined for each district considering various factors including district environment, surrounding facilities, traffic, economic prosperity degree and economic development level and etc. Liede Resettlement Implementation Plan

The compensation price grades are clearly defined according to these two standards. Due to the obvious difference of house price in different locations in Class 1-3 districts, the price fluctuation is obvious while the price fluctuation is tiny in Class 4-6 districts, which is near to the price for office houses with property right. (2) As for the commercial houses with property right, the compensation price is fluctuated based on the district economic prosperity degree. Therefore, the compensation standard is stipulated in terms of commercial road, common street and alleyway. (3) Based on the experience, the compensation standard are made considering the frame structure, composite structure, brick and timber structure, simple structure and shed structure of the houses in each building plot. (4) Based on the experience and second-hand house price, the compensation standard for the houses depreciation is regulated in terms of different service life such as less than five years, 5-15 years, 15-25 years, 25-35 years and over 35 years. 4) Houses with property right used as firms and warehouse (See Annexed Table 13.2.4 for details) (1) This price system is based on the second-hand house market investigation and real estate assess and the 8 administration districts of Guangzhou City, and 1-6 classes are defined for each district considering various factors including district environment, water and electricity and other infrastructures, aggregation degree of the related industries, environment pollution and pipeline condition, land application state and traffic condition. The compensation price grades are clearly defined according to these two standards. Due to the obvious difference of house price in different locations in Class 1-3 districts, the price fluctuation is obvious While the price fluctuation is tiny in Class 4-6 districts, which is near to the price for office houses with property right. (2) Based on the experience, the compensation standard are made considering the frame structure, composite structure, brick and timber structure, simple structure and shed structure of the houses in each building plot. (3) Based on the experience and second-hand house price, the compensation standard for the houses depreciation is regulated in terms of different service life such as less than five years, 5-15 years, 15-25 years, 25-35 years and over 35 years. 13.3 Other compensation standard 1) Compensation for houses built on household plot (See Annexed Table 13.3.1 for details) (1) Implementation of "Compensation standard for Temporarily Borrowed Land and Houses Built on Household Plot in Public Utility Construction Project of Guangzhou" (See Annexed Table 9). (2) As the price of houses built on household plot does not vary much for the reason of the Liede Resettlement Implementation Plan

location, the compensation standard is stipulated based on the 1-6 grades defined considering the various factors such as district environment, productive forces cost, traffic, economic development level, population and social environment. (3) Based on the experience, the compensation standard is given considering the frame structure, composite structure, brick and timber structure, simple structure and shed structure. (4) Based on the experience and second-hand house price, the compensation standard for the houses depreciation is regulated in terns of different service life such as less than five years, 5-15 years, 15-25 years, 25-35 years and over 35 years. The difference between adjacent grades is 50-100RMB/M'. 2) Compensation for constructions without right of land-use (See Annexed Table 13.3.2) The compensation of constructions without right of land-use is the construction cost of the houses. The compensation standard are made referring to "Data Sheet of Urban Privately-built Houses" of "Statistical Yearbook of Guangzhou". 3) Compensation for undue temporary construction: The compensation standard as follows for each square meter of construction area of the central district houses is according to "Standard and Operation Regulations on Compensation and Resettlement for Land Requisition and Demolition in Municipal Project": Unit: Yuan/M 2 Mixed Brick and timber Shed Structure Frame structure Simple structure construction structure structure Function Shops Others Shops Others Shops Others Shops Others Others 430 250 350 200 300 150 250 100 50 4) In-door facilities and moving cost The compensation standard according to "Standard and Operation Regulations on Compensation and Resettlement for Land Requisition and Demolition in Municipal Project" are as bellows: Unit: Yuan/M2

Moving cost Dwelling house Non-dwelling house with Type CATV Gas Telephone with prop rty right P ropeyight pipeline Above 5 Below 5 Below 50-200 Above Shops people people 50 m2 m2 200 M2 1 ~~~~~~~~~15YuanI Amount 350 3000 400 450 600 100 3000 5000 2 Note: the related department in the city has stipulated that the compensation of temporary relocation of cable TV is 200 yuan/household, the compensation of relocation of gas is Liede Resettlement Implementation Plan

2500 yuan/household, compensation of the relocation of telephone within same district is 120 Yuan /household and the compensation of the relocation of telephone in different district is 300 Yuan /household. 5) Demolition cost The house demolition cost is determined based on the local productive cost, machine cost and transportation cost, and the different district and different of floor number as following: Unit: Yuan/M2 Structure Frame structure Mixed construction Brick and timber Simple Shed Floor Floor Above Floor Floor Above structure structure Floor structure 1-3 3-6 Floor 6 1-3 3-6 Floor 6

Class 1 65 70 75 55 60 65 45 35 25 district Class 2 62 67 71 52 57 62 43 33 24 district Class3 59 63 68 50 54 59 41 32 23 district Class 4 55 60 64 47 51 55 38 30 21 district Class S 52 56 60 44 48 52 36 28 20 district Class 6 distict 49 53 56 41 45 49 34 26 19.

The compensation standard according to "Standard and Operation Regulations on Compensation and Resettlement for Land Requisition and Demolition in Municipal Project" are as bellows: Unit: Yuan/M2

Fence Found30acm | Other special demolition

15 15 Based on the actual condition 6) Restoration cost Unit: Yuan/M2 Frame structure |Mixed construction Brick and timber structure Simple structure 100 120 150 60 7) Structures Compensation standard according to "Standard and Operation Regulations on Compensation and Resettlement for Land Requisition and Demolition in Municipal Project" as follows: Liede Resettlement Implementation Plan

Unit: Yuan/M2

- W -, Tomb

~~~~ !TI~~~~~~~~~P

~~~~~~~~ 0 0 ,~~~ ~~~ 00 t> 00 tA0 .A...'A ~

C, -~~~~~~~~~~~~~~~~~~~~~~~~~C

8) Temporary demolition cost (See Attached Tables 13.3.8-1, 13.3.8-2, 13.3.8-3, 13.3.8-4 for details)

(1) Temporary demolition cost for houses with property right (See Attached Tables

13.3.8-1, 13.3.8-2, 13.3.8-3 for details) The compensation standard is provided according to "Standard and Operation Regulations on Compensation and Resettlement for Land Requisition and Demolition in Municipal Project" and based on the classification of commercial house, office, dwelling house, firm house and warehouse. (2) Cost for temporary demolition of land (See Attached Table 13.3.8-4) Implementation of "Compensation standard for Temporarily Borrowed Land and Houses Built on Household Plot in Public Utility Construction Project of Guangzhou". 9) Loss of business suspension (See Attached Tables 13.3.9-1, 13.3.9-2, 13.3.9-3 for details) The criteria are given according to the provisions regarding commercial house and firm house and warehouse in "Standard and Operation Regulations on Compensation and Resettlement for Land Requisition and Demolition in Municipal Project". 10) Loss due to service in strange district (See Attached Table 13.3.10 for details) The demolition and moving will causes certain loss of commercial firms after the resettlement site is arranged and before the business is resumed, therefore, the compensation standard is provided according to Hui Kuo "Standard and Operation Regulations on Compensation and Resettlement for Land Requisition and Demolition in Municipal Project". 11) Cost for pipeline reconstruction (See Attached Tables 13.3.11-1, 13.3.11-2, 13.3.11-3, 13.3.11-4, 13.3.11-5, 13.3.11-6, 13.3.11-7, 13.3.11-8 for details) Liede Resettlement Implementation Plan

Reconstruction cost for pipeline is determined according to the construction drawing, and the quota given in "Method on Valuation of Installation Project in Guangdong Province", "Regulation on Establishement of Items in BOQ for Installation Project in Guangdong Province", "Comprehensive Norm for Installation Project in Guangdong Province", "Method on Valuation of Municipal Project in Guangdong Province", "Regulation on Establishment of Items in BOQ for Municipal Project in Guangdong Province", "Comprehensive Norm for Municipal Project in Guangdong Province", "Budget Norm for Communication Construction Project" (1995), "Composition of Budgeted Expense and Computing Standard for Construction of Thermal Power, Power Transmission and Transformation Engineering" and "Indices for Investment Estimate of Nationwide Municipal Works"(in 1996) of Construction Ministry, and by the method of engineering budget and final estimate. Liede Resettlement Implementation Plan

14. Institutional structure of the resettlement and the ability building 14.1 Resettlement organization plan

Detailed plan of this sub-item and all resettlement organization as follows:

1) Overall coordination Unit for resettlement: Guangzhou Waste Water Treatment Project Management Office, Guangzhou Tunnel Development Co. Ltd. 2) Internal monitoring unit: Guangzhou Tunnel Development Co. Ltd. 3) PAP monitoring unit: GZ Road Engineering and Expansion Office 4) Independent monitoring unit: 5) Social and economy investigation: Sino-France Research Institution of Zhongshan University 6) Practicality investigation and resettlement implementation unit: Tianhe District Administration of State Land, Resources and Housing Haizhu District Administration of State Land, Resources and Housing 7) Other related units: Guangzhou City Planning Bureau GZ Land Recourse and House Management Bureau GZ City House Demolition Management Office GZ People's Court GZ Labor Bureau Sub-item PAP'S street community

14.2 Resettlement organization responsibility

See Chapter 6 "Resettlement Policy" for detailed responsibility of all PAP organization units.

14.3 Resettlement organization ability construction

Ability building of the resettlement organization shall be further improved and subdivided according to characteristics of the sub-item in Liede Wastewater Treatment Project (Phase IE)

14.3.1 Resettlement organization improvement

1) Sub-district coordinate group

Guangzhou Tunnel Development Co. Ltd. will set Haizhu District coordination group and Tianhe District coordination group under the office of wastewater treatment project to coordinate the resettlement work in the sub-item undertaken by Haizhu District Administration of State Land, Resources and Housing and Tianhe District Administration of Liede Resettlement Implementation Plan

State Land, Resources and Housing. As the sub-item is affected by plant site and pipe network, but as the land requisition for plant site was completed, so the resettlement is mainly caused by pipe network construction and the PAP is from countryside and city. Meanwhile, due to the strip shape characteristics of the pipe network, much demolition, borrowed land and reconstruction cases will surely occur. In order to properly settle such complex conditions, the sub-district coordinating group is to be fully employed for the coordination and conduction. The coordination group shall be at least staffed with a following expert:

* -Countryside resettlement expert

* City resettlement expert

* Pipe net move technician

* Construction technician

* Law expert dealing with dispute (which can be established under the project office)

2) All resettlement work group

For providing more professional service to PAP so as to increase the satisfaction and efficient of resettlement, Tianhe District Construction Bureau will divide the resettlement implementation staff into the following groups according to the type and quantity of resettlement and characteristics of this sub-item:

a. PAP resettlement group: responsible for citizen household resettlement.

b. Commercial firm and unit resettlement group: responsible for commercial firm, commonweal units, industrial enterprise, and unit resettlement work

c. Temporarily built commercial firm resettlement group: responsible for runner resettlement of temporarily built commercial firm.

d. Infrastructure resettlement group: responsible for compensation and restoration of pipeline, public facilities and public traffic.

e. Land requisition resettlement group: responsible for the resettlement for land requisition of resettlement house building and the resettlement work of affected peasant, work team and enterprise unit.

f. Logistic group: responsible for collecting, statistics and report of specification data and contact to real estate developer, real estate agency for arranging PAP to investigate the resettlement house and organizing the public activity, instructing and helping the vulnerable group in PAP to contact to the related social assistant unit and being Liede Resettlement Implementation Plan

responsible for response to complaint.

14.3.2 Application of URRP Application of UJRRP will overall improve resettlement organization ability especially in wastewater project due to influencing a large area and a great number of PAPs. If there is not a high tech as support, the resettlement organization cannot strengthen its coordinate ability:

In the resettlement planning of the Liede Wastewater Treatment Project (Phase III), URRP plays an important role.

1) The comrnunication obstruction shall be delaminated to show the resettlement plan and pipe network design on GIS map for discussion of the design proposal by the project Employer, design dept and resettlement planning unit and for reducing PAP's as far as possible under the condition if the general result of the project is not impacted. In August and September of 2003, the design plan has been modified twice and the demolition area of 96,282.90 m2 has been reduced. See following list for details:

Table 5-1

Comparison of Demolition Areas in the Original Proposal and Revised Proposal for Sub-item in Liede Wastewater Treatment Project (Phase III)

Demolition area Demolition area in District in the original the revised Difference proposal (m2) proposal (m2) 1 2 3=2-1 Tianhe District_2A 30,842.82 5,595.64 -25,247.18 Tianhe District 3B 1,883.37 4,082.12 2,198.75

District_3C 89,904.63 56,362.27 -33,542.36 Tianhe District 4B 9,293.75 7,299.34 -1,994.40

Tianhe 47,173.03 32,858.40 -14,314.63 Tianhe District_5A 5,663.05 5,640.30 -22.75

District_6A 20,660.75 5,451.82 -15,208.93 Tianhe District_6B 3,590.52 2,596.23 -994.29 Tianhe Districnth6C 20,942.89 15,123.88 -5,819.02

DiTtanhe6D 1,338.08 -1,338.08

District6D~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Liede Resettlement Implementation Plan

Total 231,292.90 135,010.00 -96,282.90 2) The project employer and resettlement implementation dept can clearly understand the general investigation scope and adjust the GIS data after on site surveying so as to obtain more correct PAP estimate data.

Table 5-2

(To be supplied)

3) To determine the PAP gathering district and have further investigation in these districts so as to implement more proper policy such as important scope of public participation and inquiry, compensation measure points and etc. In accordance with the analysis of List 5-2, the main PAP gathering area in the sub-item is as follows:

Table 5-3

(To be supplied)

Along with the expansion of resettlement work, we believe URRP will play more important role in this sub-item for monitoring and estimation.

14.3.3 raining plan of resettlement work personnel

For better coordination between the resettlement of the sub-item in Liede Wastewater Treatment Project (Phase III) and the resettlement requirement of the World Bank, GZ Tunnel Development Co., Ltd. and Tianhe District House Management Bureau all the resettlement implementation units shall work out detailed personnel training plan for the resettlement managing staff and implementation personnel combining with the characteristics of this sub-item.

1) Training plan for resettlement management personnel: Resettlement Law Resettlement project management theory and practice. Symposium regarding key points of resettlement management and resource allocation. Municipal planning Theory and application of resettlement information system Monitoring and estimation theory and methods (including basic analyzing techniques of statistics data). Public participation and consultation scheming and organization Visiting successful resettlement project 2) Training plan for resettlement implementation Demolition law education Education of Principle OP/BP4. 12 of the World Bank Liede Resettlement Implementation Plan

Filling in and record of resettlement statistics form. Criteria and technique of public participation Demolition case analysis and simulation training On site training Basic knowledge of pipeline works

3) Key points of training plan

As land requisition for the plant site of Liede Wastewater Treatment Project (Phase Ell) was completed, so the resettlement work will be carried out in the area along the pipe network. As the pipe network appears belt structure, so the resettlement work has the following characteristics:

(1) Along the line, more partial demolition and temporary construction borrowed land is necessary.

(2) To pass some high building forcibly will increase the resettlement cost.

(3) Forcible passing through some infrastructure and the key part of commonweal units, such as water plant, school and hospital will may indirectly affect more scope and cause great social influence.

(4) Due to overlapping of the construction land for pipe network with that of the relevant project, the compensation cost will be partially held by relevant project, which means that the cost calculation shall be much detailed difficult.

Considering the above conditions, training plan will lay importance on:

Analyzing sensitivity of the site demolition quantity and the indirectly affected scope that can help the resettlement implementation personnel to have a full estimation on the influence of partial demolition and borrowed land so as to timely report and take measures.

Pipe network base knowledge training: Such as which optional proposal in a certain circumstance can greatly reduce demolition quantity and possible perfect proposal is adopted to reduce PAP number as far as possible.

Training to strengthen finance cost calculation and management to financial personnel so as to assess and control the cost of each district and to increase the efficiency and exactness of the financial calculation.

4) Cautions for training plan implementation

Although Tianhe District House Management Bureau and Haizhu District House Management Bureau will separately implement the resettlement work (including training) in their own administration region, Guangzhou Tunnel Development Co. Ltd. will be I

Liede Resettlement Implementation Plan

responsible for recommendation of the general training organizations and experts. Liede Resettlement Implementation Plan

15. Information disclosure plan 15.1 Publishing of unfolded information

Liede Wastewater Treatment Project (Phase III) is one part of the whole Liede Wastewater Treatment System. Liede Wastewater Treatment Project (Phase I and II) has been constructed since 2001, so information disclosure is satisfactory and the concept of environmental protection and wastewater treatment deeply exists in the people's minds.

Beginning from Jan. of 2003, several i L5422 2it v15t;M ¶*0fFf -.- presses and media 4 such as GZ Daily, I .NhDK WED Nanfan Daily, -. 1iM A YangCheng inI6LLLA..ZLA -a jr.nrhq4.J_ Tr Evening Daily, GD nIrEtq5 ;t'hifl

Construction, GZ - City Construction and GZ Municipal .r V efrs. TV Station have successfully dtd.f .1IlhJi

reported the = 1I23ftit&I.i sub-item. The mainRS, newspaper and the government organizations have I | irl $ *Aa:.-IN?.'

also published the - ' related news and Report on Liede WWTS Phase II projet on research articles in Guangzhou Daily on 27 Oct. 2003 their websites and the municipal leaders ever investigated the plan site for several times and made speeches through the television station to explain the significance of such sub-item construction and the inevitable demolition, and hoping the affected people actively participate in the demolition and resettlement so as to reduce the affected people and affection degree as less as possible.

15.2 Information publishing in the next stage

With the actual developing of the resettlement, the news publishing will be more frequent Liede Resettlement Implementation Plan

and pertinent in order to coordinate with the whole resettlement development. As the news publishing often has concomitance of public participation and consultation, therefore, the next step of news publishing is shown on Table 8-1 "Table of Information Publishing, Public Participation (Consultation) and Supervision/Evaluations Schedule". Liede Resettlement Implementation Plan

16. Public participation and consultation

In order to reduce and avoid involuntary resettlement, during the project analysis and preparation of the Liede Wastewater Treatment Project (Phase E), the design department, resettlement department, environment protection departments and the invited academic institutions have visited the possibly affected units along the pipe networks to collect their opinions. During social and economic investigation, we also visited the large enterprises and welfare entities to check the pipeline strike and impact on the government and social institutions and listen to their suggestions so as to modify the design proposals and prepare the "Resettlement Action Plan". The more formal and comprehensive and systematical public participation and consultation will be comprehensively open during the project implementation.

16.1 Unfolded public participation and consultation

1) Social economy investigation

From October to Nov of 2003, with the help from GZ Road Engineering and Expansion Office, Sino-France Research Institute of Zhongshan University investigated the affected families, commercial firms and enterprises and companies along this sub-item pipe network. This investigation was performed according to the content and methods given in "Resettlement Policy" so that the affected people's sufficient participation has been realized. See Annex I for the question form for the investigation.

During this activity, the investigation people has provided the PAPs the latest news about the project in addition to the record of the related data required in the question form so that the PAPs has further understood the project status and their primary rights and interests.

The general investigation group has also visited the responsible persons of the large-scale enterprises and infrastructures and welfare entities discovered during the investigation. They have found out the potential influence of the clear pipe network direction and positions to such units and also recorded the related circumstances and made timely suggestion regarding the pipe network direction.

2) Walkdown in resettlement site

In order to meet the demand of resettlement sites and dispersed resettlement for the PAPs and fully mobilize the municipal estate resource and the service from real estate agency for the Project and resettlement, GZ Road Engineering and Expansion Office has respectively visited many buildings, commercial firms, special business markets and real estate agencies in Tianhe District from July to September of 2003. They have also Liede Resettlement Implementation Plan

discussed with the responsible persons about the practicable proposals and measures during the resettlement, and have listened to their opinions.

(1) Visited living quarters in Tianhe Park, to west of Airport Road, to south of West Huanshi Road and at the joints of Shatai Road and Jingxi Road belonging to Guangzhou Av. in July;

(2) Visited Guangxin Yinlanyuan, Nanguo Kitchen and Sanitary Ware Fair Center, Tianyi Stationery Market and Guangzhou Computer City, etc. in Tianhe District in August;

(3) Visited real estate intermediaries Tianhe Park, to west of Airport Road, to south of West Huanshi Road and at the joints of Shatai Road and Jingxi Road belonging to Guangzhou Av. in September.

16.2 The achievement of public participation and consultation

Modify pipeline network direction and reduce quantity of affected people at most.

Based on upper mentioned investigation, we learned opinion, will and feeling of majority of affected people, in particular, the opinion on partial pipeline network direction of some government and social institutions and entities. These opinions are reflected in Resettlement Action Plan and Environment Action Plan. Detailed example includes:

(1) Chepo Water Plant of Guangzhou Main-water Company

In field research, with aid of person in charge of this plant.

h as m e r , e yinspector checked pipelene m, d er apositon on design draeng see drawing7-. Person incharge1ofs found that | ;5 ~~~~~~~~~~~pre-designed pipeline %%dl1pass _e a thro~~~~~~~~~~~~~ughkoe) fachiltes of the pLat

F ~ ~~~~ J -. .- Flilter bed in Chebei Waler Plant such as machine room, electricity room, desilter and others (see ; drawing7-2). Person in charge of [ the plant reported that drinking - Liede Resettlement Implementation Plan

water supply for peripheral area will be affected seriously if upper facilities were removed as per original proposal. So, it is suggested that pipeline shall be displaced to east existing road to avoid removing key facilities of water plant (picture: picture of key parts, original pipeline direction map).

(2) Guangzhou Magnetic Material Factory

Inspector found that

pipeline in original _ - design proposal will ,

pass through -. large-scale chemical . storage equipment of X this factory. This equipment is key production equipment of this factory.IfULarge-scale chemical storage vessel * ~~~~~ofthis factory. If removed, production will be paralyzed. So, person in charge of this factory suggests that pipeline shall be displaced to north to avoid the removal.

(3) High-rise buildings

Inspector found that there are many high-rise buildings to be demolished in original pipeline proposal, including 9-floor building, such as Ziyunge, Teachers' Building, Chuangye Building, Jinxing Garden, Dongcheng Garden, and one

18-floor building-YueshengYuan, on " '' :. east side of Chepochong Stream. The ark %%

residents report that these buildings are L newly-built and with new inner decoration. If demolished, many people

will be affected. So, they suggest that ' -. the direction of pipeline shall be __ modified a little to avoid demolition. yueshengyuan (4) Guangzhou HONDA Automobile Co., Ltd. l Liede Resettlement Implementation Plan

This company is located in Hengsha, Huangpu, which is a famous joint venture enterprise of Guangzhou City. Annual output is more than 50,000. Automobile

-0 sales income in 2001 is RIMB 12 billion Yuan. The inspector checked drawing on site and found pipeline construction in

__ C- x~- -original design will affect production line, . water lock, workshop and measuring * equipment and will cause shutdown and Workshop of Guangzhou Toyota Aoto even demolition. So, person in charge of the company requires modifying original design proposal to avoid extensive loss.

2) Details of resettlement site is confirmed primarily

(1) Many residential areas in Tianhe District have been investigated. Level, foundational facilities and human culture characters of residential areas have been checked. In addition, preferential situation of group procurement has been learned primarily and selection of building resettlement site has been prepared;

(2) Many concentration areas of commercial firms in Tianhe District have been investigated. Business trade, level and other foundational data of commercial firms have been checked. Selection for resettlement site of commercial firms has been prepared;

(3) Many real estate intermedia organizations in Tianhe District have been investigated. Investigation organization can provide level and quantity of second-hand house for selection of resettlement site.

16.3 Public participation and consultation schedule for next stage

After completion of investigation, we will initially confirm the dense resettlement area and potential vulnerable group. The Owner of the Project, resettlement enforcement body of each administration region and individual monitoring institute will carry out public participation and consultation activities to continuously improve the resettlement plan and work.

For the time planning table of the next stage public participation and consultation activities, please refer to "the time table of information publicity, public participation and consultation, and the supervision evaluation". Liede Resettlement Implementation Plan

17. Monitoring and evaluation 17.1 Internal monitoring

The effect interior supervision to the resettlement work of Guangzhou Liede Waster Water Treatment System (Phase III) Project has been conducted by Guangzhou Tunnel Development Co. Ltd. The company does not only supervise all the preliminary preparation of the resettlement work, but also helps to harmonize the work relationship and contents of related units. The followings are included:

1) Supervision to the amount of resettlement. Having found the problems by GIS data analysis and in the general investigation, the project employer has held corresponding meetings for many times participated by relevant units to discuss the correction of the sewage pipe network tract of the sub-item to reduce the involuntary resettlement as more as possible. For example, in August and September 2003, the project employer held two corresponding meetings according to the result of GIS data analysis to make amendment to the original scheme and the amount of resettlement has reduced from 231,292.90 square meters to 135,010.00 square meters; in October 2003,according to the result of general investigation, the correction of pipe network which passes the special units is made and the total of xxx square meters of demolition have been reduced.

2) Supervision to the price. Guangzhou Tunnel Development Co. Ltd has taken an active part in every practical work of the resettlement work, including calling together the state land administration bureau of the city, evaluation service, the department of resettlement plan, and so on to do the argumentation and perfection of the resettlement compensation pricing structure of every district in this sub-item in the course of compiling this Resettlement Action Plan in this October.

In the next stage, Guangzhou Tunnel Development Co. Ltd will work in accordance with " the time table of the opening of the information, public participation and consultation and the supervision and evaluation" and continue to conduct the interior and regular supervision to the resettlement work conducted by Tianhe District Land Recourse and House Management Bureanu and Haizhu District Land Recourse and House Management Bureanu. And the interior supervision report will be sent to the World Bank according to the regulations in the Resettlement Policy.

17.2 Independent supervision

At present, the candidates for the independent organizations initially determined by the general project are as follows: Liede Resettlement Implementation Plan

*Theresettlement bureau of the yellow river conservancy committee

Guangdong provincial social science academy

*TheChinese race group study center of Zhongshan University

The project employer will choose one of the above organizations as the independent supervision organization of the general project and the sub-item, after the confirmation and putting on the record of the World Bank. The independent supervision organization selected will do its work of independent supervision and evaluation according to the time planning table of " the opening of the information, public participation and consultation and the supervision and evaluation".

17.3 Schedule of the information publishing, public participation and consultation and supervision and evaluation

In the whole process of resettlement work, the activities of the information disclosure, the public participation and consultation and the supervision and evaluation are done in interlude each other and the activities of information disclosure and public participation and consultation is the major measure of the supervision and evaluation. Therefore the two of them could not be separated completely. The work contents described in the information disclosure and public participation and consultation is also the important work contents of the supervision and evaluation. For the next overall work arrangement, please refer to the time table of the information disclosure, public participation and consultation and the supervision and evaluation (Tianhe District). Pay attention to the following precautions in the practical use of this time table:

1) The time plan table would be adjusted in practical implementation according to the project progress of the Liede Wastewater Treatment Project (Phase III).

2) The addition can be made to the frequency and contents of every work task in the time planning table.

3) The independent supervision organization will work out the detailed work plan regarding the time planning table as its outline.

According to the statistic data in table 5-2, demolition area in Huangpu District affected by Liede Wastewater Treatment Project (Phase EII) and most resettlement work will be carried out in Tianhe District, so time table of the information disclosure, public participation and consultation and the supervision and evaluation for Tianhe District is listed here. Relevant work in Huangpu District will be carried out together with that for Dashadi sub-item. I

Liede Resettlement Implementation Plan Liede Resettlement Implementation Plan

Attached table 7.3 The Planned Time Table for Assessment, Monitoring, Public Participation (Consultation) and Information Publication (Liede Phase III, Tiande District)

Organization Date Public participation and consultation Plan of information publication The sponsor participated Remarks and helped Place Content Spreading Way Content Report of preparation news units, November Television stations, working development Guangzhou 2002 to radio stations, new in earlier stage, the Tunnel November paper agencies, meaning, general Development Co. 2003 web sites situation of this Ltd. sub-item Sections inside the Tianhe Park, July 2003 to west to Jichang Visit shops to make GZ Road September rth to preparation for the Engineering and 2003 sou relocations of shops Expansion Office Huanshi Road W.

The researching GZ Road October 2003 Along the area of Social economic institute of France Engineering and to November pipeline net investigation YAT-CSEN Expansion 2003 YTSNOfc UNIVERSITY Tianhe District November Along the area of General survey of Construction and 2003 pipeline net quantity of the material objects AdministrationCity

. .. ~~~~~~~~~~~~~4 Liede Resettlement Implementation Plan

Attached table 7.3 The Planned Time Table for Assessment, Monitoring, Public Participation (Consultation) and Information Publication (Liede Phase III, Tiande District)

Bureau

The first basic Refer the investigation on the Indepefetnhebasic November 2003 Along the area of business situations of Independent investigation pipeline net shops, enterprises and monitoing report at the institutions and on citizen organization end of household December Visit 30 affected December 2003 Along the area of families learning their Independent pipeline net attitude and wishes on organization the resettlement way organization Prepare "Handbook of Tianhe District GZ Road After passing Resettlement Construction and Engineering and Information and City Expansion assessment of Material"Material" BureauAdministration OfficeOfiethe BankWorld Television Announce the project stations, has passed the World Tunnel newspaper Bank's assessment and Development Co. agencies and web resettlement work will sites go under implement Ltd.

147 Liede Resettlement Implementation Plan

Attached table 7.3 The Planned Time Table for Assessment, Monitoring, Public Participation (Consultation) and Information Publication (Liede Phase III, Tiande District)

Guangzhou Municipal Newspaper Issue the move notice Administrative Newspaper of this sub-item Bureau of National Land and Real Estate Guangzhou Tunnel Open the specialized Development Co. web page on the web Ltd.,Tianhe Specialized web site of the project District sites owner and the District resettlement implement Cotr organization City Administration Bureau GZ Road Guangzhou Engineering and Tunnel Expansion Television Development Co. Office, Along the aestations, Make related reports Ltd., Tianhe independent January 2004 Along the area of Hold consultig meeting newspaper on the consulting District monitoring agencies and web meeting Construction and organization sites City and other Administration related Bureau govemment bodies

. . - - ~~~~~148 -~~~~~~- Liede Resettlement Implementation Plan

Attached table 7.3 The Planned Time Table for Assessment, Monitoring, Public Participation (Consultation) and Information Publication (Liede Phase III, Tiande District)

The consulting meeting site, the Guangzhou office of the Tunnel GZ Road resettlement Distribute "Handbook Development Co. Engineering and implement D, eIsetl "Hando Ltd., Tianhe Expansion organization, first ofRstlmn District Office, visit by Information and Construction and independent resettlement Material" City Monitoring working staff. Administration organization Publication of the Bureau web site GZ Road Have meeting with the Guangzhou Engineering and In rojectthe provider of the selected Tunnel OfiE,xBaniyun officeoffice ofdistrictof resettlementfixing site the in each Ltd.,Development Tianhe Co. DsrcDffice, Baiyun Guangzhou favorable price for District Construction Tunnel group purchasing and Construction and Admiity Ltd. discussing the reception City Bu rau, Ltd. of the affected people's Administration Bureau, visiting and moving in. Bureau Independent monitoring organization

149- Liede Resettlement Implementation Plan

Attached table 7.3 The Planned Time Table for Assessment, Monitoring, Public Participation (Consultation) and Information Publication (Liede Phase III, Tiande District)

Two weeks before the Refer to the signature of "the Independent World Bank contract of monitoring "Internal In the office of compensation and organization, Monitoring" JIndepenien r 0 o resettlement", the group Guangzhou and January 2004 to independent dealing with the appeals Tunnel "Independent May 2005 monitoing will begin the official Development Co. Monitoring business through hot Ltd., GZ Road Assessment" lines, mail box for Engineering and in July 2004 appeals and appeal Expansion Office and January window on internet 2005 News units, Television The progress and Guangzhou stations, related information of Tunnel newspaper th eeteetDevelopment Co. agencies and web implement work Ltd., Independent sites monitoring organization The district with H t l~~ ~~~~cnetaeconcentrated withHold thethe affectedmn-tn meeting people Independent project affected asking their degree of monitoring people along the satisfaction for the organization areaL of pipeline |resettlement work

-150 Liede Resettlement Implementation Plan

Attached table 7.3 The Planned Time Table for Assessment, Monitoring, Public Participation (Consultation) and Information Publication (Liede Phase III, Tiande District)

Continue to sign with Tianhe District the affected people and Construction and implement "the contract City of compensation and Administration resettlement" Bureau Visit the affected people have already moved into resettlement site or Independent Each relocation second-hand house monitoring point asking their degree of organization satisfaction for the resettlement site

The second basic Refer the investigation on the Independent basic May 2005 Each resettlement business situations of mondepende investigation site shops, enterprises and morniztion iestgtion institutions and on organ2zation r005 citizen household News units, Refer to the Television Guangzhou World Bank June 2005 to stations, Report on the related Tunnel "nea January 2006 newspaper situation and typical Development Co. MInternal agencies and web cases after resettlement Ltd., Independent and sites °rtniting "Independent

1-or Liede Resettlement Implementation Plan

Attached table 7.3 The Planned Time Table for Assessment, Monitoring, Public Participation (Consultation) and Information Publication (Liede Phase III, Tiande District)

Guangzhou Monitoring Coordinate and solve Tunnel Assessment" the still existing Development Co. in January problems in the Ltd, Tianhe 2006 resettlement work, and District supervise and carry out Construction and the follow-up City supplementary measures Administration Bureau, The third basic Refer the investigation on the Independent basic December 2005 Each resettlement business situations of monitoring investigation site shops, enterprises and organization report in institutions and on January 2006 citizen household

-152- Liede Resettlement Implementation Plan

18. Cost estimate and fund plan of the project

18.1 Description of project estimate According to the spirit of the meeting on the sharing of the project resettlement costs held by Guangzhou Municipal and Gardening Management Bureau and attended by Guangzhou Construction Commission on 28 October 2003 (See Annex 1): Among the costs of the pipe network construction, the resettlement cost for the sewage pipe networks within the areas of planned roads and planned creeks will be borne by the relevant road or creek improvement projects (See Annex 6 for the cost arrangement for relevant projects) while the resettlement cost for those within the existing road and creek areas will be borne by this project.

Based on this principle the resettlement cost to be shared by this project is 646,254,650.45RMBB.

The resettlement cost to be shared by relevant projects is 2,311,963,866.88RMB

1) The explanation of the land requisition and demolition budget

(1) The problems of regions.

The budget is established according to the price in the regions where the sub-item is

dominantly located so as to avoid the complexity of data. The future compensation will also follow the practical standard.

(2) The problems of depreciation.

As the detailed investigation to find out the real intention has not been completed, the

present cursory inspection showed that the fixed number of years of depreciation of the

demolition houses is centered in the period of 5-20 years.

(3) Constructions without right of land-use and the temporary demolish compensation standard.

The compensation standard of the house with a record of use history would be divided

according to their floors and structures. The difference of floors leading to large

difference of price therefore, the 3-5 floors price calculation is adapted. The temporary Liede Resettlement Implementation Plan

demolition is a kind of could -be built demolition so, the compensation standard is the

repeat establishment price of construction. That is to say, it is the same as the

constructions without right of land-use compensation standard. The future compensation

will also follow the practical standard.

(4) The expense of knock down.

The knock down expense criteria is divided according to the floors and structures. The

difference of floors leading to large difference of price therefore, the 3-5 floors price

calculation is adapted. The future compensation will also follow the practical standard.

(5) The problems of temporary demolition expense.

For the partially demolished houses, their temporary demolition square meters will be

determined according the real conditions. If the budget could not be determined, it can be

estimated according to 1.5 times by experience.

(6) The problems of the time of temporary demolition.

The temporary resettlement period for the partial demolished houses is set in half a year.

The temporary resettlement period of the temporary requisition houses which will be

rebuilt is set in one year. The temporary resettlement period of land, including the period

of construction and rebuilding is set in half a year together.

(7) The expense of house repair.

It is calculated according to the difference of structures and the left square meters after the

demolition.

Unit: Yuan/M2

Frame work Mixed Brick and wood Simple

100 120 150 60

(8) Various miscellaneous expenses: Liede Resettlement Implementation Plan

It includes the expenses of: the end case of land requisition, demolition administration

and the mapping, requisition and examination, and the notarization of the demolition

notice; they are calculated according to houses with property right3OYuan/M 2

(9) The unpredictable expense: The unpredictable expense of pipeline transfer is calculated

by 10%; the unpredictable expenses of demolition by 5%; and no unpredictable expenses

for land requisition.

(10) The problem of the knock down area:

It includes the mature temporary building areas and the peccancy building areas, which

will not get the compensation.

(11) The problems of land compensation standard

Because the village boundary is not clear, the compensation standard is set according to

the average value of the same kind of land in the same district. The compensation will be

given according to the practical criteria after the village boundary is clear by the further

inspection.

(12)The problems of capital apportion. The capital is planned to be shared equally every month.

At present, the construction schedule of each pipeline could not be determined for lacking of

detailed material descriptions. Therefore, the time limit of demolition is temporarily set at half

a year before the construction schedule to the start of construction. The capital in every month

is required to be shared according to proportion: Liede Resettlement Implementation Plan

The first The second The third The fourth The fifth The sixth Month month month month month month month

Proportion 5% 15% 20% 25% 25% 10% shared

18.1.2 The descriptions of pipeline transfer estimation.

1) The project amount is estimated by the stat data of the pipeline electronic map of the

planning bureau and the integrated unit price of the project is estimated by the Budget

Estimate Indices for Demolition and Relocation Of Pipeline in Municipal Engineering of

GZ Road Engineering and Expansion Office.

2) Because the data of the pipe line electronic map of the planning bureau is not full, much

pipe line materials can not be known correctly, such as: the types of pipe channel, the

number of pipe holes, the models of electric (light) cable, the installations in the

transformer substation, the thickness of pipe wall, etc., all of them can not be known

clearly. Then these data can only be estimated by the normal standard and the practical

work experience in many years.

3) The estimated pipeline distance is mostly the direct distance of the would-be-transferred

pipeline between the two pipe wells. In general cases, the length of the transferred

pipeline is 1.2-1.35 times of direct distance. Considering that the pipe line transfer caused

by the project is a zonal sewage pipe network, the transfer amount of the existing pipe

line could be reduced by the optimization of design and the technical measure of

engineering during the implementation of the sub-item. Therefore, the estimation of the

project does not take the transfer as multiple.

Because of the reason above, the estimation of pipeline transfer is not accurate. Then it is

not called the budget but the estimation.

18.2 Compilation standard for and explanation of pipeline Liede Resettlement Implementation Plan

estimation

18.2.1 The Budget Estimate Indices for Demolition and Relocation of Pipeline in Municipal

Engineering is drawn for the purpose of reasonably and correctly control of the project

investment of down planning, strengthening the investment administration of our office to

the town planning construction, the macro control, regulating the management of project

budgetary estimation, and the control of project cost (hereafter it is called this criteria).

18.2.2 Compilation index for budgetary estimation

(1) "The Indices for Budgetary Estimate of Power Transmission and Distributing Line

Engineering"

"The Indices for Estimate of Water Supply Engineering"

(2) "The Indices for Estimate of Gas Engineering"

(3) "The Indices for Estimate of Communication Engineering"

(4) "The Budget Estimate Indices for Cable Television Engineering (it is not perfect)"

Among which, "Budget Estimate Indices for Cable Television Engineering" has not been

completed yet.

18.2.3 The basis of compiling the budgetary estimate

(1) " Method on Valuation of Installation Project in Guangdong Province"

(2) "Regulation on Establishment of Items in BOQ for Installation Project in Guangdong

Province"

(3) "Comprehensive Norm for Installation Project in Guangdong Province"

(4) "Method on Valuation of Municipal Project in Guangdong Province"

(5) "Regulation on Establishment of Items in BOQ for Municipal Project in Guangdong

Province"

(6) "Comprehensive Norm for Municipal Project in Guangdong Province"

(7) "Budget Norm for Communication Construction Project (1995)"

(8) "Composition of Budgeted Expense and Computing Standard for Construction of Thermal

Power, Power Transmission and Transformation Engineering"

(9) "Indices for Investment Estimate of Nationwide Municipal Works (1996,drawn by the state Liede Resettlement Implementation Plan

construction department) "

(10) "Guiding Price for Engineering Materials in Guangzhou Region (The document of the

ration station of Guangdong provincial electric power construction issued in the first

quarter of 2003, Number YDD 2003. 2)"

(11) "Budgetary Price for Materials Used in Electric Power Facilities"

(12) "The 2002 Collection of Nationwide Prices for Conventional Plant Used in Electric

Power Engineering (the telecommunication material price by post and telecommunication

department, 94 edition)"

(13) "The city planning park document No. 1997.338"

18.2.4 The composition of budgetary estimate index

(1) The unit project cost.

(2) Other expenses of project (Referring to the projects of demolition, repair and so on related

to the main project in the unit project cost).

(3) The safety measure expense.

(4) The design expense.

(5) The road compensation expense.

(6) The water consumption expense.

(7) The stoppage expense (in telecommunication project).

(8) The prepare expense.

(9) The administration expense of construction unit.

Among the index mentioned above, the expenses of road compensation, water

consumption and stoppage are great and it is more difficult to determine correctly.

18.2.5 The principle of pipeline budgetary estimate.

It is regulated by the state that the principle of "Static control and dynamic management"

should be followed in the implementation of project budgetary estimate. Once it is

examined and approved, it should not be adjusted at random. The principle of "the

budgetary estimate should not exceed the assessment and the budget should not exceed

the budgetary estimate" should be implemented in the process of construction. When the

intending practical investment of the project exceeds the budgetary estimate, the analysis

report must be brought forward and it could be carried out only after the approval. Liede Resettlement Implementation Plan

18.2.6 This index does not include the 10kv built-on-tilts isolated leads and the plastic-steel pipe

and plastic pipe in the low-pressure line project, water supply and gas project.

18.2.7 This budgetary estimate criterion is only used in compiling the pipeline budgetary estimate.

The amount of future practical compensation will be calculated according to the

pre-balance criteria of the project.

Annex:

(1) "Indices for Budgetary Estimate of Power Transmission and Distributing Line Engineering

(Annex 18.2.1-1, Annex 18.2. 1-2, and Annex 18.2. 1-3)"

(2) "Indices for Estimate of Water Supply Engineering (Annex 18.2. 2)"

(3) "Indices for Estimate of Gas Engineering (Annex 18.2. 3)"

(4) "Indices for Estimate of Communication Engineering (Annex 18.2.4-1. Annex 18.2.4-2)"

18.3 Project Budget

18.3.1 Total cost of the resettlement

The total cost of the resettlement of this project is 404,839,405.41 yuan

18.3.2 Sharing of the project resettlement cost

According to the spirit of the meeting on the sharing of the project resettlement costs held by

Guangzhou Municipal and Gardening Management Bureau and attended by Guangzhou

Construction Commission: costs for the pipe network construction for those within the planned roads and planned creeks the resettlement will be borne by the relevant road or creek improvement projects. And the resettlement cost for the sewage pipe network within the existing road and creek areas will be borne by this project.

According to this principle, the resettlement borne by the project is 119,001,586.12 yuan (see the attached table - 1)

The resettlement borne by relevant project is 285,837,819.29 yuan (see the attached table - 2) Liede Resettlement Implementation Plan

Attached table 1 Estimate of the resettlement cost of Liede WWTS Phase III shared by this project Item Quantity Unit price Total price Remark 1. Compensation for Attached permanently affected tablel8.1.AC housing with property right totally 18 pages

1. lHousing 1,798.06 2,655.67 4,775,058.83

1 .2Shop 2,007.04 4,066.09 8,160,783.07 .

1 .3.Office 382.59 3,196.24 1,222,861.61

1.4.Factory building 400.54 2,540.00 1,017,364.94

1.5 Others 64.94 2,473.17 160,606.55 1.6 Total 4,653.17 15,336,675.00 Attached 2.Housing on tablel8.1.AC residential plot totally 18 pages

2. i Framed structure 3,537.79 2,470.92 8,741,602.90

2.2Composite structure 3,424.10 2,301.28 7,879,815.88 2.3Brick and timber structure 51.69 2,150.00 111,126.52

2.4Simple structure 410.96 1,854.38 762,070.66

2.5Shed structure

2.6Total 7,424.54 17,494,615.96 3.Compensation for Attached temporarily affected housing with property tablel8.1.AC right and on totally 18 pages residential plot l 3.1 Framed structure 1,566.12 617.64 967,306.05 Liede Resettlement Implementation Plan

3 .3Composite structure 1,304.90 629.36 821,245.31 3.3Brick and timber structure 94.55 536.72 50,744.65

3 .4Simple structure 13.17 350.00 4,608.65

3.5Shed structure

3 .6Total 2,978.73 1,843,904.66 4.Constructions Attached without right of tablel8.1.2.4.AC,t land-use otally 1 page 4. lFramed structure 67.22 600.00 40,334.18

4.2Composite structure 1,144.73 619.13 708,734.21 4.4Brick and timber structure 2,478.26 454.25 1,125,759.50

4.4Simple structure 95.84 340.83 32,664.74 4.5Shed structure

4.6Total 3,786.05 1,907,492.63 Attached 5, Temporary table:18.1.2.7.1.A structure before expiration c-i MI Otally 1 .______p a ge 5.1Commercial use 5.1. IFramed structure 5.1 .2Composite structure 24.41 250.00 6,101.74 5.1.3Brick and timber structure 5.1.4Simple structure

5.1.5Shed structure

5.1 .6Subtotal 24.41 6,101.74 Attached 5 .20ther use table: 18.1.2.7.1 .A Liede Resettlement Implementation Plan

C-2 4 -0 111

______totally ipage

5.2. IFramed structure

5.2.2Composite structure 24.41 250.00 6,101.74 5.2.3Brick and timber structure 6.90 250.00 1,725.49

5.2.4Simple structure 5. 250.0 13,131.47

5.2.5Shed structure

5.2.6Subtotal 83.83 20,958.70 5 .3Total 108.24 27,060.44

6.Land compensation

6. ICultivated land-use 4.45 262,908.00 1,169,940.60 6.2Land for construction 40.11 73,000.00 2,927,788.82

6.3Upland

6.4Total 44.56 4,097,729.42 7.Compensation for temporary relocation Attached 7. lCompensation for tablel8.1.2.7.1.1. temporary relocation of AC,Attached housing with property tab82 . right; right ~~~~~~~~~~~~~~~~~~~~tablel18.1.2.7.1.2. AC,totally 2 pages

7. 1. IlHousing 6,984.57 77.79 543,295.11

7.1 .2Shop 2,038.07 186.63 380,364.46

7.1 .30ffice 991.51 128.67 127,579.05 7.1 .4Factory building and warehouse 2,388.00 87.91 209,930.76 7.1.5 Others 194.74 120.00 23,368.78 Liede Resettlement Implementation Plan

7.1.6 Subtotal 12,596.88 1,284,538.17 Attached 7.2Cost for temporary tablel8.3.2.7.2.A land borrowingtal83272A C,totally 1 pages 7.2. 1Cost for temporary borTowing of cultivated borrowing of cultivated 8,946.86 28.24 252,670.07 land-use 7.2.2Cost for temporary borrowing of 80,521.72 40.24 3,240,291.31 construction land 7.2.3Cost for rehabilitation of cultivated land-use 8,946.86 6.00 53,681.15 7.2.4Compensation for standing crop 8,946.86 5.00 44,734.29

7.2.5Subtotal 107,362.30 79.48 3,591,376.82 7.3Total 119,959.18 4,875,914.99 8.Cost for Attached rehabilitation of house tablel8.1.2.8.AC,t with property right otally 1 pages

8. i Framed structure 664.02 100.00 66,401.89

8.2Composite structure 295.75 120.00 35,489.47 8.3Brick and timber structure 94.55 150.00 14,181.95

8.4Simple structure

8.5Shed structure

8.6 Total 1,054.31 116,073.31

9.Compensation for Attached affected structure 3,316,662.22 tale 18paCes ______otally 1 pages 10.Other compensation cost Attached 10.1Stop-loss tablel8.3.2.10.1A 2,554.87 27.39 69,990.49

______C-1 ,A ttached Liede Resettlement Implementation Plan

tablel8.3.2.10.1A C-2,totally 2 pages Attached 10.20perating losses tablel8.3.2.10.2.A due to remove 1,155.02 392.53 453,383.90 C,totally 1 pages 10.3Compensation for removal 477,375.19 10.4Compensation for telephone removal 316,800.00 10.5Compensation of cable TV removal 166,600.00 10.6Compensation for gas pipe removal

10.7Total 3,709.89 1,484.149.58 Attached 11.Cost for house demolition 19,776.44 50.71 1,002,793.25 table18.1.11.AC,t otally 1 pages 12.Cost ofr tree removal 13.Cost for pipeline relocation Attached 13.1Power cable tablel8.3.2.13AC 2,746.54 3,911.44 10,742,944.44 ,3l totally 4 pages Attached 13 .2Communication cable 9,832.27 721.05 7,089,547.28 table18.3.2.13AC, totally 4 pages Attached 13.3Gas, water and other industrial pipeline 19,621.45 1,959.80 38,454,207.11 tablel8.3.2.13AC, totally 4 pages

13.4Total 32,200.26 56,286,698.83 14.Cost for move notice, survey, review 30.00 and notarization 15.Cost for case-closing 44.56 40,000.00 1,782,267.84 16.Resettlement overhead cost 429,876.99 17.Contingency fund 17. 1Contingency fund Liede Resettlement Implementation Plan

for land requisition and 2,685,760.81 resettlement 17.2Contingency fund for pipeline relocation 3,220.03

17 .3Total 2,688,980.84 18.Cost for resettlement work 18.lCost for resettlement planning 0.01 1,126,908.96 18.2Cost for resettlement monitoring 0.01 563,454.48 and evaluation 18.3Cost for socioeconomic evaluation ~~~~~~~~0.00338,072.69 evaluation ______18.4 Cost for resettlement 0.01 901,527.17 supervision 18.5 Cost for resettlement resettlementa n 0.03 3,380,726.88 implementation ______

18.6 Total 6,310,690.17

19. Sum total 119,001,586.12

Attached table2: Resettlement cost estimate for the Waste Water Treatment Project - Liede Phase III Project borne by relevant projects Quantity Unit price Total price Remark 1.compensation for permanent Attached tablel8.1.BD requisition of totallyl8 page housing with property rights l

1.1 Housing 5,613.56 2,802.43 15,731,583.80

1.2 Business 1,028.13 3,941.92 4,052,818.50 Liede Resettlement Implementation Plan

1.3. Office 1,821.60 3,322.09 6,051,515.75

1.4. Workshop 6,252.06 2,808.30 17,557,660.54

1.5 Others 2,113.80 2,840.88 6,005,047.82

1.6 Total 16,829.16 49,398,626.40

2. Housing on Attached table18.1.BD residential plot totally 18 page

2.1 Frame structure 18,447.31 2,465.39 45,479,801.95

2.2 Composite 9,798.79 2,277.21 22,313,906.94 structure 2.3 Brfick and timber strucktand3,595.27 2,143.25 7,705,558.84 timber structure 2.4 Simple 1,286.01 1,835.25 2,360,136.03 structure

2.5 Shack 0.00

2.6 Total 33,127.38 77,859,403.75

3.Temporary requisition of housing on Attached tablel8.1.BDI residential plot totallyl8 page with property right

3.1 Frame structure 6,858.69 650.83 4,463,857.31

3.2 Composite 3,665.18 611.04 2,239,579.12 structure 3.3 Brick and timber strucktand1,642.01 537.79 883,057.58 timber structure 3.4 Simple 571.85 322.31 184,311.76 structure 3.5 Shack

3.6 Total 12,737.73 7,770,805.78

4. Compensation Attached for historically tablel8.1.2.4.BD,totallyl page used housing Liede Resettlement Implementation Plan

4.1 Frame structure 1,012.63 663.65 672,026.69

4.2 Composite 3,595.56 600.16 2,157,906.89 structure 4.3 Brick and timber strucktand8,237.04 473.40 3,899,399.71 timber structure 4.4 Simple 2,763.16 277.36 766,403.57 structure 4.5 Shack

4.6 Total 15,608.38 7,495,736.85

5, Temporary Attached table:18.1.2.7.1.BD-1 structure before totally] page expiration y 5.1 Used for business 5.1.1 Frame structure 5.1.2 Composite 461.54 250.00 115,384.02 structure 5.1.3 Brick and 37.46 250.00 9,364.89 timber structure 5.1.4 Simple 52.86 250.00 13,214.88 structure l

5.1.5 Shack 0.00

5.1.6 Total 551.86 137,963.78

Attached table:18.1.2.7.1.BD-2 5.2 Other usesl 1rllk, totallyl page 5.2.1 Frame 5.2.1tFruce 82.69 250.00 20,672.91 structurel 5.2.2 Composite 160.29 250.00 40,071.59 structure 5.2.3 Brick and timber strucktand313.03 250.00 78,257.89 timber structurel 5.2.4 Simple 896.43 250.00 224,108.28 structure l

5.2.5 Shack 0.00

5.2.6 Total 1,452.44 363,110.67 Liede Resettlement Implementation Plan

5.3 Total 2,004.30 501,074.46

6. Compensation for land 6.1 Cultivated 19.43 262,908.00 5,108,302.44 land-use l 6.2 Land for 6.2oLanst ion 174.86 73,000.00 12,764,563.82 construction 6.3 Upland

6.4 Total 194.29 17,872,866.26

7.Compensation for temporary relocation 7.1 Compensation Attached for temporary table 18.1.2.7.1.1.BD,Att*hed relocation of tablel8.l.2.7.l.2.BD,totay2 housing with pabe property right page

7.1.1 Housing 27,814.77 80.59 2,241,458.37

7.1.2 Business 8,455.56 219.24 1,853,824.98

7.1.3 Office 3,116.51 215.54 671,740.81

7.1.4 Workshop 25,868.98 122.77 3,175,883.02 and warehouse

7.1.5 Others 4,620.85 120.00 554,502.50

7.1.6 Subtotal 69,876.67 8,497,409.69

7.2 Compensation Attached for temporarily tablel8.3.2.7.2.BD,totally1 borrowed land page 7.2.1 Compensation for temporarily 41,953.36 28.97 1,215,576.68 borrowed cultivated land-use 7.2.2 Compensation for temporarily 377,580.24 40.97 15,471,152.91 borrowed land for Liede Resettlement Implementation Plan

construction

7.2.3 Compensation for 251,720.16 cultivated land-use rehabilitation 7.2.4 compensation 209,766.80 for standing crop

7.2.5 Subtotal 419,533.60 17,148,216.54

7.3 Total 489,410.27 25,645,626.24

8.Conpensation for housing repair Attached (with property tablel8.1.2.8.BD,totallyl page right) E

8.1 Frame structure 2,180.16 100.00 218,016.09

8.2 Composite 1,234.79 120.00 148,174.76 structure 8.3 Brick and 295.22 150.00 44,283.47 timber structure 8.4 Simple 119.74 60.00 7,184.47 structure 8.5 Shack 0.00

8.6 Total 3,829.91 417,658.79

9. Compensation for requisition of 0.00 structure 10.0 Compensation for others Attached tableI8.3.2.10.1BD-1,A4tched 10.1 Stop-loss 22,046.27 34.63 763,508.83

page Attached 10.2 Loss of business relocation 637.77 528.57 337,105.68 tablel 8.3.2.10.2.BD,totallyl business relocation pg ______~~~~ ~~~~page 10.3 Compensation 957,284.97 for move Liede Resettlement Implementation Plan

10.4 Compensation 540,400.00 for telephone move 10.5 Compensation 321,650.00 for cable TV move 10.6 Compensation 000 for pipe gas I

10.7 Total 22,684.04 2,919,949.48

11.Cost for Attached housing 93,353.00 48.90 4,565,056.92 tablel8.1.11.BD,totallyl page demolition 12. Cost for tree o oo relocation 13.Compensation for pipeline relocation Attached 13.1 Power cable 2,993.22 5,012.83 26,833,194.97 tahe8 tablel1 8.3.2.13 BD,totally3l page

13.2 Attached Telecommunication 9,705.19 677.94 11,191,140.74 cable table 8.3.2.13BD,totally3 page 13.3 Pipe of gas, water supply and Attached other industrial , table 18.3.2.13BD,totally3 page pjpe

13.4 Total 25,868.17 56,485,436.81

14.Cost for move notice, survey and mapping, review 30.00 0.00 and notarization etc. l 15. Land requisition 194.29 40,000.00 7,771,481.54 procedure charge 16. Resettlement management 1,773,836.85 charge 17.Contingency fund 17.1 Contingency fund for land 10,199,606.17 requisition and resettlement Liede Resettlement Implementation Plan

17.2 Contingency fund for pipe 2,586.82 relocation 17.3 Total 0.00 10,202,192.98

1-8. Cost for resettlement work 18.1 Cost for resettlement 1.0% 2,706,797.53 planning l 18.2 Cost for resettlement 0.5% 1,353,398.77 monitoring and evaluation 18.3 Cost for socioeconomic 0.3% 812,039.26 evaluation 18.4 Cost for resettlement 0.8% 2,165,438.02 supervision l 18.5 Cost for resettlement 3.0% 8,120,392.59 implementation l 18.6 Total 0.00 15,158,066.17

19. Sum total 285,837,819.29

18.4 Fund planning

18.4.1 Explanation of fund planning

1. This fund planning only includes the cost borne by this project and not includes that to be shared by relevant projects.

2. The fund plan is prepared according to the commencement time of the project and the budget of the settlement.

3. Since the commencement time is not fixed yet, the calculation will be carried out based on monthly average.

4. Completion time of resettlement will be 6 months before the completion of the civil works. Liede Resettlement Implementation Plan

18.4.2 Fund planning of the resettlement

Fund plan for Liede WWTS (Phase HI) Second quarter 2004 7,386,305.35 Third quarter 2004 7,386,305.35 Fourth 736353 quarter 2004 7,386,305.35 First 736353 quarter 2005 7,386,305.35 Second quarter 2005 7,386,305.35 Third quarter 2005 7,386,305.35 Fourth 7,386,305.35 quarter 2005 First quarter 2006 7,386,305.35 Second quarter 2006 7,386,305.35 Third quarter 2006 7,386,305.35