<<

Does a Single Large Facility Imply Increased Risk?

R. R. Parker MFE ITER/Exp Plenary Does a Single Large Facility Imply Increased Risk?

Short Answer: Yes, multiple large facilities would reduce risk, but this is not an option at present. Does a Single Large Facility Imply Increased Risk?

Various types of risks can be identified:

-Technical

-Physics

-Programmatic

The technical risks can be minimized by a substantial R&D effort. See ITER posters. Physics Risks are Minimized by Maintaining a Strong Base Program

ST, , RFP, other ICCs

Base Tokamak Physics physics ASDEX-UG, DIII-D, JT-60U (SU?), JET, CMOD, Tore Supra, FT-U, KSTAR,

Plasma New SC in China, India,…. Electricity Production

ITER ETR/DEMO/PROTO

Decision to proceed with tokamak-based fusion jor Facilities jor 14-MeV source (Int’l) Ma

Volumetric neutron source (?)

Base Technologies chnologies

Base Plasma Support technologies Fusion Te Fusion Programmatic Risks are Minimized by a Strong Base Stellarator/ICC Program

ST, Stellarator, RFP, other ICCs

LHD, W7-X, NCSX, TJ-II, ……. NSTX, MAST, …...

Base Tokamak Physics physics ASDEX-UG, DIII-D, JT-60U (SU?), JET, CMOD, Tore Supra, FT-U, KSTAR,

Plasma Plasma New SC Tokamaks in China, India,…. Electricity Production

ITER ETR/DEMO/PROTO

Decision to proceed with tokamak-based fusion jor Facilities jor 14-MeV neutron source (Int’l) Ma

Volumetric neutron source (?)

Base Fusion Power Technologies chnologies

Base Plasma Support technologies Fusion Te Fusion ITER or a Sequence of Smaller Steps ?

The key issue confronting development of the tokamak into an attractive reactor is sustaining an efficient steady-state (fBS > 70%) at high beta (βn > 3) and good confinement (HH > 1.5 @ q ~ 4.5).

Control of such regimes must be demonstrated in a burning plasma under steady- state conditions (T >> τres). For this purpose, a device of the ITER class will be necessary before proceeding to ETR/Demo/Proto.

Postponing the construction of ITER in favor of more modest steps only adds delay and cost to the possible realization of fusion energy.

Ultimately an ITER-class machine must be successfully built and operated before An ETR/Demo/Proto -- Therefore risk is not reduced, only postponed. Does a Single Large Facility Imply Increased Risk?

Short Answer: Yes, multiple large facilities would reduce risk, but this is not an option.

Longer Answer: A sequence of smaller, possibly “safer” steps would entail lower risk, particularly with regard to investment. But finally an ITER class machine would be required before proceeding to ETR/DEMO/PROTO. Thus the risk is not reduced, only postponed.

Risk can be “minimized” by aggressive, focussed R&D and maintaining strong tokamak, stellarator and ICC base programs (including theory and computation!)