Annex E

Revised Traffic Study

(Revised Text, Figures and Appendix A) Docum ent Verification ARUP

i J o b title Traffic Study for Proposed Developments in Area J o b n u m b e r N1 North, Area 10b, 236078 t Document title Traffic Impact Assessment File reference Resort Company , Limited Document ref TIA Traffic Study for Proposed R evision D ate F ilen am e DB TIA (Area 10b).docx i Developments in Area N1 North, 0 15 Dec Description Rev 0 Area 10b, Discovery Bay 2015 » Traffic Impact Assessment Prepared by Checked by Approved by fenny Chiong / i n A N am e Victor Wong Carmen Chu Andrew Huang Rev 1 | 29 April 2016 Signature

1 29 Apr F ilenam e DB TIA (Area I0b).docx 2016 Description Rev 1 » e Prepared by Checked by Approved by Jenny Chiong / N am e Victor Wong Carmen Chu Andrew Huang e -r Signature

F ilenam e I Description

I Prepared by Checked by Approved by

N am e I

Signature

F ilenam e Description

3

Prepared by Checked by Approved by ~ This report takes into account the particular V instructions and requirements of our client. N am e It is not intended for and should not be relied upon by any third party and no responsibility ^ is undertaken to any third party. Signature ; Job number 236078 Issue Document Verification with Document ["✓ |

»

Ove Arup & Partners Hong Kong Ltd Levels Festival Walk 80 Tat Chee Avenue Kowloon Tong Kowloon Hong Kong www.anip.com TIA| Rav 1 | 29April2016 9 cuctxtxr uv*opn V400C X

>5 Hong Kong Resort Company lim ited Traffic Study for Proposed (Developments in Area N1 North, Area 10b. Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North. Area 10b. Discovery Bay Discovery Bay Traffic impact Assessment Traffic Impact Assessment

Contents Figures Figure 2,1 Existing Road Network in Discovery Bay

Page Figure 2.2 Location of Surveyed Key Junctions

1 INTRODUCTION 1 Figure 2.3 Existing Year 2015 Observed Traffic Flows (Internal Road Network) 1.1 Background l 1.2 Scope of Study 1 Figure 2.4 Existing Year 2015 Observed Traffic Flows (External Road 1.3 Structure of Report 2 Network) Figure 3.1 Proposed Developments in Discovery Bay 2 EXISTING TRAFFIC CONDITIONS 3 Figure 4.1 Projected Year 2026 Traffic Flows - Reference Scenario (Internal 2.1 Road Network in Discovery Bay 3 Road Network) 2.2 Traffic Count Survey 4 2.3 Existing Traffic Performance 6 Figure 4.2 Projected Year 2026 Traffic Flows - Reference Scenario (External Road Network) 2.4 Transport Services to/from Discovery Bay 7 Figure 4.3 Projected Year 2026 Traffic Flows - Design Scenario (Internal 3 PROPOSED DEVELOPMENTS IN DISCOVERY BAY 9 Road Network) 3.1 Development Parameters 9 Figure 4,4 Projected Year 2026 Traffic Flows - Design Scenario (External . Road Network) 4 FUTURE TRAFFIC CONDITIONS 10 4.1 Trip Generation for Residential Developments 10 Figure 4.5 Projected Year 2031 Traffic Flows - Reference Scenario (Internal Road Network) 4.2 Future Year Major Highway and Land Use Assumption 17 4.3 Assessment Scenarios 18 Figure 4.6 Projected Year 2031 Traffic Flows - Reference Scenario (External 4.4 Future Traffic Performance 20 Road Network) Figure 4.7 Projected Year 2031 Traffic Flows - Design Scenario (Internal 5 SUMMARY AND CONCLUSION 27 Road Network) 5.1 Summary 27 Figure 4.8 Projected Year 2031 Traffic Flows - Design Scenario (External 5.2 Conclusion 28 Road Network) Appendices

Appendix A Bus Octopus and Ferry Ticket Gate Count Provided by Operators

TJA | Rev 1 [ 29 April 2016 TIA [ Rev 1 129 April 2016 u«ciCT£^urncj»ouv«ocuvEMTi23SW(>;3eo7a t>a f o r cascover v b a v . o r h u z a t io n o f u m j ustREiwrvsepEJiATE s lb u s s o m u p * o ,o e S1JATIA - AREA w e ($u BVSSlOA)V< OOCX WKS'aS4VTRAfFX:.GROORtoCV«EN,ni»)»E»jraTlAfOROSCOVERYeA’C-ORHUaATlCWWlANOU5EREPCiSriSiErERATeStBUW

Traffic Study for Proposed Developments in Area N1 North. Area 10b, Traffic Study for Proposed Developments in Area N1 North. Area 10b, Hong Kong Resort Company United Hong Kong Resort Company Limited Discovery Bay Discovery Bay Traffic Impact Assessment ■> Traffic Impact Assessment i • Review and assess the available traffic data/information; s 1 INTRODUCTION • Develop reference scenario, i.e. should there be no change on the I existing land use; LI Background • Assess the likely traffic and transport impact due to the proposed t developments on existing ferry service, and the road network 1.1.1 The Discovery Bay development is a self-contained sub-urban capacity within and outside Discovery Bay; residential development comprising mainly low-density private > housing, situated in the eastern part of covering a total • Develop traffic and transport improvement schemes, where land area of about 650 hectares. There are currently around 8,300 nos. appropriate, to mitigate any traffic and transport impact; and of residential flat with total population around 15,000. • Assess the existing and future ferry service demand, to ensure the J9 1.1.2 Discovery Bay falls within the ambit of the Discovery Bay Outline ferry service is able to cope with the additional demand induced Zoning Plan (DB OZP) which was first approved on 21 March 2003. by the proposed developments. i The current approved OZP limits the population to 25,000 (i.e. 10,000 nos. of residential flat), which is reflected in the latest Master Plan MP7. 1.3 Structure of Report 8 1.1.3 There are plans to optimize the residential potential of Discovery Bay, 1.3,1 After this introductory chapter, this report is divided into the following while maintaining the low density and resort like living environment. chapters: Under the current planning proposal, a total of 1,125 nos. of flat would 8 be developed in Area 10b, in additional to the current approved OZP. • Chapter 2 - presents the details of the traffic count survey and the The developments are targeted for completion in Year 2023 for performance of critical junctions and road links for population intake in the same year. the base year, i.e. Year 2015; n v 1.1.4 Ove Arup and Partners (HK) Ltd was commissioned by Hong Kong • Chapter 3 - presents the parameters of the proposed Resort Co Ltd, to review and evaluate the traffic impact induced by the developments in Discovery Bay; * proposed additional residential developments in Area 10b of Discovery Bay, including ferry and road-based transport, to support the • Chapter 4 - presents the traffic generation from the proposed application to modify the DB OZP for better optimization of the developments, performance of critical junctions, potential of Discovery Bay. The possible developments in Area 6f of road links and ferry service with the proposed Discovery Bay for residential use have also been taken into account for developments in place; and the assessments under this study. • Chapter 5 - summarises and concludes the findings of the study. 1.1.5 Comments from Transport Department were received on 25 April 2016. This submission has addressed and incorporated the comments from i Transport Department, in particular, the latest planning assumptions for Siu Ho Wan Depot Residential Development and Siu Ho Wan Reclamation and Landside Development have been adopted in the % future year traffic assessment.

1.2 Scope of Study :3 1,2,1 The scope of this study is highlighted and summarised below:

;} • Conduct vehicle count surveys at critical links and junctions to appreciate current traffic conditions in the study area;

* • Validate transport models with reference to the updated vehicle count surveys as base year, i.e. Year 2015; ■ ' Update the inventory regarding traffic circulation patterns, traffic conditions and constraints of the existing, as well as the future committed road network and developments in th? yi^ity of the * subject developments based on the ;•

4 TtAIRevI |29April2016

■l-X&.VT&5?TRAmC GSOVPCOOJ U EJfTW M W iJsO rj T1A f « O SCO -tRY B A f - OXnUZXIYCH L*."*) USE A t K * ' S1UUTA-AS EA K 6 <$U Vt.OOGX

8 Hong Kong Resort Conpany United Traffic Study for Proposed Developments in Area N1 North, Area 10b. Horvg Kong Resort Company Limited Traffic Study to r Proposed Developments in Area N1 North, Area 10b, Discovery Bay Traffic Impact Assessment Discovery Bay Traffic I mpact Assessment

2 EXISTING TRAFFIC CONDITIONS 2.1.5 Besides the above vehicle types, Urban Taxis, Lantau Taxis and coaches with prior bookings are allowed to access designated areas in Yi Pak (Discovery Bay North) via , since 26 2.1 Road Network in Discovery Bay October 2014. External Connection 2.1.6 The local road connects with the tunnel link is Cheung Tung Road, which is a 7.3 metre wide two-lane single carriageway. It runs in an 2.1.1 Under the existing comprehensive traffic control management for east-west alignment parallel to the North Lantau Expressway. The Discovery Bay, only authorized vehicles are allowed to access carriageway is a key corridor to provide access for the residential bus Discovery Bay via Discovery Bay Tunnel such as emergency vehicles, services of Discovery Bay. servicing buses and goods vehicles. Internal Connection 2.1.2 The Discovery Bay Tunnel is a toll tunnel under single two-lane configuration that links Discovery Bay Road at Yi Pak in the east with 2.1.7 Discovery Bay Road is the major internal road within Discovery Bay, • Cheung Tung Road at Siu Ho Wan adjacent to spanning from Discovery Bay Tunnel in the north to the Marina in the in the west. south. The road is under single two-lane configuration, serving as the spine for both internal and external connections, with access roads 2.1.3 The Tunnel was built for the Discovery Bay residential development on branch for various residential developments in Discovery Bay as well the north-eastern coast of Lantau Island, Hong Kong, which open 24 as the bus terminus at Discovery Bay Plaza for access to the Ferry Pier. hours every day to vehicles specified by the Commissioner for Marina Drive connects Discovery Bay Road and the marina. Transport, The toll charge ranges from HK$50.00 to HK$250.00, depending on the type of vehicle, and is chargeable one-way eastbound 2.1.8 The existing road network in Discovery Bay is shown in Figure 2.1. only (i.e. from North Lantau to Discovery Bay). 2.1.4 Toil levels of the Tunnel for different vehicle types are summarised in 2.2 Traffic Count Survey Table 2.1 below. 2.2.1 In order to appreciate the existing traffic conditions, comprehensive Table 2.1 Toll Levels of Discovery Bay Tunnel traffic counts were conducted during the periods of 0700-1000 and 1600-2000 hours on a typical weekday (Thursday), and 1300-1800 T o ll P ay ab le C a te g o ry Vehicle Type (HK Dollars) hours on a typical weekend (Saturday) in February and June 2015. Traffic flow at critical road links including Discovery Bay Road, Government vehicles, ambulances or vehicles used Discovery Valley Road, Siena Avenue, Discovery Bay Tunnel, Cheung by officers of the Fire Services Department, the l Hong Kong Police Force, the Customs and Excise 50 Tung Road, North Lantau Highway, , and key junctions in Department or the Correctional Services Discovery Bay, and Sunny Bay areas as shown in Table D epartm ent 2.2 below were surveyed. 2 Private light buses other than category l above 50 2.2.2 The Area of Influence, location of the key junctions and critical road Public and private buses other than category 1 links are also shown in Figure 2.2. 3 50 above

Light goods vehicles and special purpose vehicles 4 other than category 1 above and of a permitted 120 gross vehicle weight not exceeding 5.5 tonnes

Medium goods vehicles and special purpose vehicles other than category 1 above and of a 5 160 permitted gross vehicle weight exceeding 5.5. tonnes but not exceeding 24 tonnes

Heavy goods vehicles and special purpose vehicles 6 other than category 1 above and of a permitted 250 gross vehicle weight exceeding 24 tonnes

7 Vehicles other than categories 1 to 6 above 250

TIA ( Rev 1129 April 2016 Page 3 T1A | Rev 1129 April 2016 Page 4 t*4X&VT$&T AAFF>C GRO^OOCUV£ihT<29$OCOt?3$Q?3 TW F C ft tkSCO ttH'f 6AV - CPTllKATiON OF LAND U $£AEfORT\S£PlftAT£ S«JB LI S ^ N S12AtU-AR£A > :* ISVEVSSOK) V* DOCK ^ 4 VTS®T)Um CJ»W UW »W V[tm »*»M )W T* TIAf OR t>S«WE*Y eAY-WTiUKATiON o r UNO U WfltPMTVSEPEftATe S'.*VI WON (AFfl W lfsoa SUATlA-AREA 10arS

f ) Table 2.2 Surveyed Key Junctions 2,3 Existing Traffic Performance Ju n c tio n T ype 2.3.1 The observed traffic flow during the AM and PM peak hours at the Ji J1 Discovery Bay Tunnel / Discovery Bay Road Roundabout critical road links (refer to Figures 2.3 and2.4), and the corresponding

J2 Discovery Bay Road / Discovery Valley Road Priority performance in terms of volume-to-capacity (v/c) ratio are shown in Table 2,3 below. J) J3 Discovery Bay Road l P laza Lane Priority

J4 Discovery Bay Road / Marina Drive Priority Table 2.3 Year 2015 Observed Traffic Flow for Critical Links during Peak Hours n J5 Discovery Bay Road / Headland Drive Priority Volume-to- J6 Shun Tung Road / Tat Tung Road (West) Signal Observed Fiow Observed Flow Carriageway Capacity (V/C) (V E H /H o u r) (P C U /H o u r) . ; . R atio h J7 Shun Tung Road / Tat Tung Road (East) Signal Critical Road Links D irection C ap acity J8 Tat Tung Road / Fu Tung Street Priority AM PM ■ A M PM (P C U /h o u r) A M . PM P e a k P e a k P e a k P eak P e a k P e a k 39 Sunny Bay Road / Cheung Tung Road Priority i t E/B 2,790 3,295 3,570 4,480 6,100 0.59 0.73 J10 Cheung Tung Road / Discovery Bay Tunnel Priority Lantau Link W/B 3,595 2,665 4,495 3,575 6,100 0.74 0.59 i l l Siena Avenue North Roundabout R oundabout T« E/B 2,450 2,740 3,090 3,840 6,100 0.51 0.63 J12 Discovery Bay Road / Vista Avenue Priority North Lantau H ighw ay W/B 2,725 2,480 3,540 3,300 6,100 0.58 0.54 Tung Chung Waterfront Road / Slip Road to North JI3 A Signal Lantau Highway Cheung Tung Road E/B 105 70 160 105 1,040 0.16 0.10 Western Section Tung Chung Waterfront Road / Slip Road from North W/B 95 75 160 0.15 JI3B Signal 110 1,040 0.10 Lantau H ighw ay • Cheung Tung Road E/B 110 80 165 165 1,040 0.16 0.16 & J14 South Road Roundabout R oundabout Eastern Section W/B 105 120 175 120 1,040 0.17 0.11 J 15 Shun Tung Road / Yu Tung Road Signal (% Discovery Bay E/B 75 40 120 70 1,280 0.10 0.05 : ^4 J16 Tung Chung East Interchange Roundabout Tunnel W/B 60 75 105 125 1,280 0.08 0.10 J17 Tat Tung Road / Mei Tung Street Signal Discovery Bay Road N/B 95 115 150 190 1,040 0.15 0.18 J18 Tat Tung Road / Hing Tung Street Signal (North of Discovery Valley Road)* S/B 95 HO 155 175 1,040 0.15 0.17 2.2.3 The observed weekday AM and PM peak were found to be 0800-0900 Discovery Bay Road "e N/B 105 135 180 225 1,040 0.17 0.21 and 1700-1800 hours respectively. While for weekend, the peak hour (South o f Discovery was found to be 1400-1500 hours, but the flows during weekend are in V alley Road)* S/B 110 125 190 215 1,040 0.18 0.20 general lower than that during both weekday AM and PM peak. E/B 20 35 35 6 Therefore, weekday AM and PM peak were considered as critical Discovery Valley 55 1,040 0.03 0.05 Road* scenarios for assessment. W/B 20 30 30 50 1,040 0.03 0.05 E/B 45 30 75 45 1,040 0.07 0.05 Siena Avenue* W/B 40 30 55 . 45 1,040 0.05 0.04 * Included Golf Cart at Discovery Bay internal roads with PCU factor of 1. 9

9

,y

a Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North, Area 10b, Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North, Area 10b, Discovery Bay Discovery Say Traffic Impact Assessment Traffic Impact Assessment

p 2.3.2 Junction capacity analyses based on the Transport Planning and Design 2.4.3 There are two types of bus services in Discovery Bay: one serves Manual (TPDM) have been carried out at the key junctions. Results of various residential developments within Discovery Bay for connection the capacity assessment are summarised in Table 2.4 below. to the ferry pier or commercial centre at Discovery Bay (North); the ti other serves as external connection from Discovery Bay (from pier or Table 2.4 Year 2015 Existing Junction Performance DB North) to Tung Chung, Sunny Bay and Hong Kong International Performance * Airport, via Discovery Bay Tunnel. ft Ju n c tio n T y p e AM PM 2.4.4 Table 2.5 summarises the ferry and bus services for Discovery Bay. J i Discovery Bay Tunnel / Discovery Bay Road R oundabout 0.07 0.06 Table 2.5 Ferry and Bus Services for Discovery Bay 1 J2 Discovery Bay Road / Discovery Valley Road Priority 0.06 0.09 No O rig in Destination J3 Discovery Bay Road / Plaza Lane Priority 0.35 0.36 F e rry ! J4 Discovery Bay Road / Marina Drive Priority 0.10 0.08 - Discovery Bay Ferry Pier Central Pier No. 3 J5 Discovery Bay Road / Headland Drive Priority 0.02 0.05 - Discovery Bay (Nim Shue Wan) M ui W o (,) ( J6 Shun Tung Road / Tat Tung Road (West) Signal 42% 35% - Discovery Bay (Nim Shue Wan) / Trappist Monastery J7 Shun Tung Road / Tat Tung Road (East) Signal >50% >50% Internal Bus J8 Tat Tung Road / Fu Tung Street Priority 0.31 0.37 1 Headland Drive/ Parkland Drive Discovery Bay Ferry Pier J 9 Sunny Bay Road / Cheung Tung Road Priority 0.05 0.05 2 Hillgrove Village/ Midvale Village Discovery Bay Ferry Pier J10 Cheung Tung Road / Discovery Bay Tunnel Priority 0.17 0.20 3 Hillgrove Village/ Parkvale Village Discovery Bay Ferry Pier J l l Siena Avenue North Roundabout Roundabout 0.06 0.04 4 (3) Siena Two Discovery Bay Ferry Pier J12 Discovery Bay Road / Vista Avenue Priority 0.05 0.03 C4 Discovery Bay Ferry Pier DB North Comm Centre (Circular) Tung Chung Waterfront Road / Slip Road to North J13A Signal >50% >50% Lantau Highway 5 L a Vista / L a Serene Discovery Bay Ferry Pier

Tung Chung Waterfront Road / Slip Road from North 6 Seabee Lane Discovery Bay Ferry Pier J13B Signal >50% >50% Lantau Highway 7 Capeland Drive Discovery Bay Ferry Pier

J14 Chek Lap Kok South Road Roundabout Roundabout 0.49 0.44 \ 8 Caperidge Drive Discovery Bay Ferry Pier J15 Shun Tung Road / Yu Tung Road Signal >50% >50% 9 (3) DB North Comm Centre / Siena One D iscovery B ay Ferry Pier J16 Tung Chung East Interchange Roundabout 0.15 0.16 C9 Discovery Bay Ferry Pier DB North Comm Centre (Circular) J J17 Tat Tung Road / Mei Tung Street Signal >50% >50% 9 A Chianti Discovery Bay Ferry Pier J18 Tat Tung Road / Hing Tung Street Signal >50% >50% 9S Peninsula Village (Capevale Drive) DB North Comm Centre J * Figures shown represent “Design Flow/Capacity” (DFC) ratio for roundabout and priority junctions, and “Reserve Capacity* for signal junctions External Bus 2.3.3 As shown in Tables 2.3 and 2.4, all critical road links and key junctions D B 01R Discovery Bay Ferry Pier Tung Chung J are currently operating with significant spare capacity during both AM DB02A DB North Comm Centre A irport and PM peak hour. D B02R Discovery Bay Ferry Pier A irport t DB03P DB North Comm Centre Sunny Bay

2.4 Transport Services to/from Discovery Bay D B 03R Discovery Bay Ferry Pier Sunny B ay r 2.4.1 The two main transport modes for accessing Discovery Bay are ferry Operate on Saturdays, Sundays and Public Holidays. One departure per day per direction and residential bus. Since 26 October 2014, designated areas in on Mondays to Fridays (School Days only) via Peng Chau W Kaito ferry service Discovery Bay (North) are also accessible by Urban and Lantau Taxis. i O) AM peak period on Monday to Friday only vs 2.4.2 The main ferry route operates from Discovery Bay to Central. There are also local ferry/kaito ferry routes operating from Discovery Bay to Mui U Wo, Peng Chau and Trappist Monastery 'L

t ia | Rev 1129 Apfii 2016 7 Page TCA | R e v 1 12 9 A p ril 2016 Page 8 i W G N T S e fT W F ie aSOUPCCCUWe«ra36WJ13M7STW FCfl » SCOVER * BAY , W T l va A rO N OF lASO U 3E f! EPORTVStFtfcAT E Sl/3US$>CW(AL'ftK>lE>fj3 l«jCOVrS£SrTa«rrKLGV£AM{ SUBU 5 i« V (AM* 2QIEVC3 H2A TIA ■ AtCA Ke(SU RVSSOv] V4 & X X o r S lid DA . AREA ice (SU V t DOCJC 3

Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North, Area 10b, Discovery 8ay Hong Kong Resort Company Limited Traffic Study for Proposed Devefopments in Area N1 North, Area 10b. Traffic I ftp act Assessment Discovery Bay !> Traffle Impact Assessment

PROPOSED DEVELOPMENTS IN 4 FUTURE TRAFFIC CONDITIONS DISCOVERY BAY 4.1 Trip Generation for Residential Developments 3.1 Development Parameters Pedestrian Trip Generation 3.1.1 The additional development is located in Area 10b along existing Marine Drive. It consists of 1,125 nos. of flat. Location plan of the 4.1.1 The likely volume of traffic generated by the additional residential developments is presented in Figure 3.1. developments is based on the current trip generation and attraction by the existing residential developments in Discovery Bay, assuming 3.1.2 The other possible development in Area 6f of Discovery Bay for future additional residential developments would have similar residential use is located west of existing Discovery Bay Phase 3 <> characteristics of the existing residential developments. Parkvale Village. It which consists of 476 nos. of flat. The location of this residential development in Area 6f is also shown in Figure 3.1. 4.1.2 Pedestrian count surveys were also conducted during weekday AM and a PM peak period, at the footpaths immediately outside the typical residential developments in Discovery Bay, counting the number of pedestrians leaving and entering the residential buildings during the (■ peak period. The survey locations are shown in Table 4.1 below. Table 4.1 Pedestrian Survey Location 'I} Survey . -■ .■ -LV;Tyy/>Cttymge Total No. of Location r Flats i l l Footpath at Phase 4 Peninsula Village - Capevale Drive Jovial Court, Haven Court and Verdant Court 408 nos. Footpath at Phase 8 La Costa - t* Costa Avenue Onda Court and Costa Court 230 nos.

4.1.3 The surveyed pedestrian flow and corresponding trip generation / (ft attraction rates at the existing residential developments are then estimated. For comparison, reference has also been made to the overall pedestrian trips approaching / leaving Discovery Bay by external (ft residential bus, ferry or taxi during the same peak period. These trip rates are tabulated in Table 4.2 below.

ift Table 4.2 Peak Hour Pedestrian Trips and Trip Generation Rate

P l i ^ P M ] Peak r I m m M t t m s m fgGeh^rafion l Attraction ■ yf Pedestrian Count at Capevale Drive 133 40 (persons/hr) 62 104 ft Trip Rate at Capevale Drive (persons/hr/flat) 0.326 0.098 . 0.152 0.255 Pedestrian Count at Costa Avenue (persons/hr) 6? 38 57 Trip Rate at Costa Avenue (persons/hr/flat) . 0.291 0.109 ; : 0.165 0.248 Total Pedestrian Trips Approaching / Leaving Discovery Bay by Bus, Ferry or Taxi 723 1,650 (persons/hr) (.ft Trip Rate for Overall Discovery Bay (persons/hr/flat) 0.087 ! ■ 0.198 Adopted Trip Rate for Additional ^ ^ 6 5 ^ 4 : f'ft Residential Development (persons/hr/flat) Vi 0.255 ' ' ' r-

for bus and ferry services■ were also ‘(■ft conducted at the taxi stand at Disco ver^Bay^orth to fe ^ i^ the nnmher pf fpxi passengers boarding/alightingdt *'* ' 1 Overall number of flats for j l I

T I A I R e v 1 f 2 9 A p r il 2 0 1 6 f 3 1

Hong Kong Resort Company United Traffic Study for Proposed Developments in Area N t North, Area 10b. Hong Kong Resort Company Umrted Traffic Study for Proposed Developments in Area N1 North, Area 10b, Discovery Bay Discovery Bay Traffic impact Assessment Traffic Impact Assessment

f r!» 4.1.4 As shown in Table 4.2, the surveyed pedestrian trip rates at the 4.1.8 Walk trips to/from ferry pier and cycle trips are excluded, as a residential developments at Capevale Drive and Costa Avenue were in conservative approach for assessment of internal bus generation (i.e. general higher than the overall trip rate for the entire Discovery Bay. assume all pedestrian trip generation would travel by internal bus). t i For conservative approach, the higher trip rate is adopted for estimation 4.1.9 In addition, the walk trips and cycle trips would only induce minimized of pedestrian generation for the proposed addition residential impact to existing footpath and cycle track. Since according to the latest development, as shown in Table 4.3 below. This adopted trip rate is t i surveys, including both interview survey and site observation survey considered conservative, since it has also included some Discovery Bay internal trips. conducted at the building block entrance at Phase 3 Parkvale Village and Phase 4 Peninsula Village, the observed split for walking and I !■ Table 4.3 Pedestrian Trip Generation for Additional Residential cycling to/from ferry pier is around 10% and <0.5% respectively, as - if Developments in Area 10b (Unit: ped/hr) shown in Table 4.4 and 4.5 below. I 1 J N o. o f A M P e a k P M P e a k Table 4.4 Pedestrian Survey at Phase 3 Parkvale Village F ) Residential N o. o f F la ts fo r Development F la ts A ssess­ G en eratio n A ttrac tio n G e n e ra tio n A ttrac tio n A M P e a k P M P e a k m e n t 1 1 Total surveyed pedestrians leaving 59 22 10b 1,125 1,350 440 147 223 344 residential building block to ferry pier 19 Estimated Pedestrian Trips to use • By bus/golf cart 52 I '■ 220 73 112 172 (86% ) External Bus Service (persons/hr) (88% ) V • B y w alk 7 3 Estimated Pedestrian Trips to use 220 73 112 172 (12% ) (14% ) Ferry Service to Central (persons/hr) * B y B icycle 0 0 (1) Includes a +20% variation in total number of flats adopted for assessment to allow for (0% ) (0% ) flexibility in detailed design A M P e a k P M P e a k 4.1.5 Assuming that the modal split for additional residential developments Total surveyed pedestrians approaching 16 62 would be similar to the existing travel pattern, the pedestrian trips residential building block from ferry pier generated are mainly travel to urban areas by ferry, or external • By bus/golf cart 15 57 residential bus to MTR Station at Sunny Bay or Tung Chung. With (94% ) (92% ) reference to the boarding/alighting surveys and the information on the • By w alk 1 5 ferry ticket gate / bus Octopus count from the operator, the modal split (6%) (8% ) for ferry and bus modes is approximately 50% and 50% respectively. • By Bicycle 0 0 According to the latest survey, only around 1 % of the total external trips (0% ) are by taxi. Table 4.5 Pedestrian Survey at Phase 4 Peninsula Village

4.1.6 Also, it is anticipated that during AM and PM peak hour, trip generation A M P e a k P M P e a k from the additional residential developments are mainly work-related Total surveyed pedestrians leaving 105 43 trips to urban areas, hence the estimated patronage for the two ferry residential building block to ferry pier services to and Peng Chau/Trappist Monastery would be • By bus/golf cart 91 40 (93% ) .1 »■ minimal only. (87% ) r ♦ By w alk 13 3 4.1.7 For pedestrian trips generated who would travel by ferry to urban areas, (12% ) (7% ) it is assumed that they would take internal residential bus directly from • By Bicycle 1 0 the proposed residential development to the bus DB Plaza, then change (1% ) _ (0% ) to ferry at the pier. While for those travelling to Sunny Bay/Tung Chung, A M P e a k P M P e a k it is assumed that they would also take the internal residential bus to DB Plaza or DB North, then change transfer to external bus towards Sunny Total surveyed pedestrians approaching 23 83 Bay/Tung Chung etc. residential building block from ferry pier • By bus/golf cart 21 76 (91% ) (92% ) • By w alk 2 6 (9% ) (7% ) * By B icycle 0 1 (0% ) 0 % )

TIA | Rev 1129 April 2016 Page 11 TIA 1 Rev 1 ] 29 A pril 2016 Page 12 TUFCRCS-SCCVmY BAY. OFTHFTATjON OPIANO USE A E P O ft'M E F W rt S'j SUMJON W S W tE J M w m c J i f l O U POOCUV£NTtf3«0lM 150ra Ttt FOR BAY. OPH WZATiCW OF UN O U St A SOeiASS'ON (APR S t U TIA ■ AREA

i. « * f 1

Hong Kong Resort Company Untied Traffic Study for Proposed OewfopmenU in'Area N1 North, Area 10b, Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North. Area 10b. Discovery Bay Discovery 8ay Traffic Impact Assessment T ra ffic Im pa ct A ssessm ent

) 4.1.10 The additional two-way walk trips generated/attracted for Area 10b Table 4.7 Adopted Internal Bus Trip Generation for Additional would only be less than 30 ped/hr during AM and PM peak hour. While Residential Developments in Area 10b (Unit: pcu/hr) 1 the clear width of the narrowest part of the footpath is 2.5m, assuming . N o. o f A M P e a k P M P e a k 0.5m lateral clearance on both sides of the footpath and LOS C Residential No. o f F la ts fo r performance (i.e. flow rate = 32.8 ped/min/m), the capacity of footpath Development F lats A ssess­ G e n e ra tio n A ttra c tio n G en e ra tio n A ttractio n % would be 32.8 x (2.5-0.5-0.5) x 60 — 2,952 ped/hr. m e n t w A rea 10b 1,125 1,350 20 20 20 20 4.1.11 With the existing footpath available capacity at the narrowest section of (1) Includes a +20% variation in total number of flats adopted for assessment to allow for 3 around 2,950 ped/hr (i.e. around 100 times the pedestrian trip generated). Majority of the residents would travel by shuttle bus flexibility in detailed design immediate outside the residential developments. Hence, impact on 4.1.16 Similarly, the vehicular (bus) trips for external services are estimated, 0 existing pedestrian and cycle track network would only be minimal. assuming that these buses would operate in addition to the existing Vehicular Trip Generation - Bus services to Sunny Bay, Tung Chung and Airport. The calculated bus trip generation is shown in Table 4.8. b 4.1.12 Based on the above assumptions, the estimated pedestrian trips as shown in Table 4.3 are converted to vehicular (bus) trip generation. Table 4.8 Calculated Additional External Bus Trip Generation for Additional Residential Developments in Area 10b « 4.1.13 As a conservative approach, it is assumed that the bus trip generation A M P e a k ; - P M P eak due to additional residential developments would have occupancy of % S p lit <*> not more than 70% (i.e. each bus would carry not more than 56 G e n e ra tio n A ttractio n G en e ra tio n A ttrac tio n passengers including standing passengers), hence generating a higher Estimated Pedestrian Trips number of bus trips compared with the case of assuming 100% to use External Bus Service - 220 73 112 172 occupancy (i.e. each bus would carry 80 passengers including standing (persons/hr) i passengers). Estimated Pedestrian Trips 25% 55 18 28 43 for Tung Chung (persons/hr) 4.1.14 The vehicular (bus) trip generation for internal trips between the Estimated Pedestrian Trips additional developments and DB Plaza bus terminus is tabulated in 5% 11 4 6 9 Table 4.6 below. for Airport (persons/hr) Estimated Pedestrian Trips 70% 154 51 78 120 \ Table 4.6 Calculated Internal Bus Trip Generation for Additional for Sunny Bay (persons/hr) Residential Developments in Area 10b (Unit: pcu/hr) Calculated External Bus 5 5 /5 6 1 8 /5 6 2 8 /5 6 4 3 /5 6 N o. o f . vAM Peak^ig^-; Trip for Tung Chung - = 1 veh = 1 veh = 1 veh = 1 veh Residential N o. o f F la ts fo r (pcu/hr) = 2.5 peu = 2,5 peu = 2.5 peu = 2.5 peu Development F lats A ssess­ G en e ra tio n A ttrac tio n G e n e ra tio n A ttra c tio n m e n t (1) 1 1 /5 6 ■ 4 / 5 6 6 / 5 6 9 / 5 6 Calculated External Bus \ - = 1 veh = 1 veh = 1 veh = 1 veh 4 4 0 /5 6 147 / 56 223 / 56 344 / 56 Trip for Airport (pcu/hr) = 2.5 peu = 2.5 peu = 2.5 peu = 2.5 peu A rea 10b 1,125 1,350 = 8 veh = 3 veh = 4 veh - 7 veh = 20 peu = 8 peu = 10 peu - 18 peu 1 5 4 /5 6 5 1 /5 6 7 8 /5 6 1 2 0 /5 6 \ Calculated External Bus - = 3 veh = 1 veh = 2 veh = 3 veh W Includes a +20% variation in total number of flats adopted for assessment to allow for Trip for Sunny Bay (pcu/hr) flexibility in detailed design = 7.5 peu = 2.5 peu = 5,0 peu = 7,5 peu n Total Additional ' 4.1.15 For assessment purpose on providing bus service to the residential Calculated External Bus 13 peu 8 peu 10 peu 13 peu development, the critical bound traffic during peak hour would be Trip for Discovery Bay * adopted for both generation and attraction. In the morning peak, the (1> Reference to the peak hour Octopus count provided by the operator for the three existing ' critical bound is generation while in the evening peak the attraction bus routes to Tung Chung, Airport and Sunny Bay would be more critical. Also, for conservative approach, it is assumed * these buses from the additional residential developments would operate 4.1.17 Critical bound traffic during peak hour would be adopted for both with headway of around 8 minutes, similar to the existing internal bus generation and attraction, similar to the approach for internal bus trip services. The adopted vehicular (bus) trip generation for internal trips generation. Hence, the adopted b u s jg^ratipn is shown in Table * is shown in Table 4.7 below. v ■ ■:

\ TIA | Rev 1 129 April 2016

V £*TC»Xli>2S60TS TU fOR OSAY - OPn WZATfOH O f UkVO UStflEPOAr'Sef’M A r t S>.«US£X*f (AW» JOlQfO* 512A-nA-AK£AWa

Table 4.9 Adopted Additional External Bus Trip Generation for 4.1.22 Similarly, the trip generation for the possible trip generation for Additional Residential Developments in Area 10b developments in Area 6f of Discovery Bay for residential use is also estimated, and would be included in the "‘Reference Scenario” of future A M P eak P M P e a k - year traffic assessment (refer to Section 4.3). Table 4.11 below G en eratio n A ttra c tio n G en e ra tio n A ttra c tio n summarised the adopted trip generation for the possible residential Adopted External Bus Trip for Tung developments in Area 6f of Discovery Bay. 2.5 2.5 2.5 2.5 Chung (peu/hr) £ Table 4.11 Adopted Trip Generation for Additional Residential Adopted External Bus Trip for 2.5 2.5 2.5 2.5 Developments in Area 6f (Unit: peu/hr) Airport (peu/hr) € • A M P eak P M P e a k Adopted External Bus Trip for Sunny 7.5 7.5 7.5 7.5 Bay (peu/hr) G e n e ra tio n A ttrac tio n G en e ra tio n A ttrac tio n

Total Additional Adopted External Internal Bus Trip 20 20 20 20 £ 13 13 13 13 Bus Trip for Discovery Bay External Bus Trip 10 10 8 8 Vehicular Trip Generation - Taxi External Taxi Trip 5 5 5 5 £ 4.1.18 With reference to the traffic study conducted in March 2014, for peak T o ta l 35 35 33 33 hour taxi generation under the no toll scenario, it is estimated that the £ existing residential developments in Discovery Bay would generate / Occupancy for Ferry Service attract 79 taxis one-way during the peak hour. 4.1.23 Assessment on the existing ferry service has also been conducted, to £ i 4.1.19 While under the survey conducted after introduction of taxi services, appreciate the impact of the additional residential developments to the the surveyed peak hour taxi generation is 30 taxis one-way, including existing ferry service. those serving the residential developments, hotel and other facilities in 4.1.24 As mentioned above, the pedestrian trip generation from additional e Yi Pak. Hence, the existing amount of taxi trip generation is lower that residential developments are mainly work-related trips to urban areas. the estimation under previous traffic study. For conservative approach, Hence it is assumed that all pedestrian trips generated would use the f the taxi trip generation by new additional developments will make ferry service to/from Central during the AM and PM peak hour. reference to the estimation under previous traffic study. Nonetheless, the existing occupancy of the two ferry services to Mui 4.1.20 Using the taxi trip generation under previous traffic study, the one-way Wo and Peng Chau/Trappist Monastery is also shown for reference e additional taxi trip generation would be 79 taxis * 8,326 existing flats purpose. x 1,350 additional flats (with 20% buffer) - 1 3 taxis. 4.1.25 As shown in Table 4.12 below, the critical AM peak occupancy for t . Vehicular Trip Generation - Summary ferry services from Discovery Bay to Central would increase from 64% to 93%, with taken into account the subject proposed additional 4.1.21 Table 4.10 below summarised the adopted trip generation for the residential development in Area 10b and also the possible residential proposed additional residential developments in Area 10b of Discovery developments in Area 6f. Hence, the existing ferry service would still 9 . Bay. operate within capacity with the additional residential developments in place. Table 4.10 Adopted Trip Generation for Additional Residential ? v Developments in Area 10b ( U n it : peu/hr) Table 4.12 Occupancy of Ferry Service ^ - A M P eak P M P eak A M P e a k P M P e a k f,.' G en eratio n A ttra c tio n G en eratio n A ttra c tio n - • G en e ra tio n A ttra c tio n G en e ra tio n A ttrac tio n

Internal Bus Trip 20 20 20 20 Discovery Bay — M u i W o (l) 0 > ■

External Bus Trip 13 13 13 13 Existing Peak Hour Ferry Ridership n/a 122 94 n/a to/from Mui W o (persons/hr)(2) External Taxi Trip 13 13 13 13 Capacity of Ferry Service Operated T o ta l 46 46 46 46 n/a 161 161 n/a (persons/hr)

Existing Occupancy of Ferry $ n/a 76% 58% n/a Service to/from Mui Wo

V' '

I TIA | Rev 1)29 April 2016 Page 15 TtA I Rev 1 129 April 2016 Page 16 v ■ 'jw a srse vw m c OCUl/t!fl-«&3l»ii307J HA FCM OSCOVMV MV- QFTiUZATIC* Of SfOHTW PtW * Sl>3Ui$.OH M lftM S12A HA - A S t O « iSUEUSSCW) V* DOCX SMA T tt - AREA K « ISUBU4SX»0 V4 CpOCX

* Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North. Area 10b, Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North, Area 10b. Discovery Bay Discovery Bay Traffic Impact Assessment Traffic Impact Assessment

7) which has incorporated with the latest highway infrastructure and A M P eak P M P e a k planning assumptions. G en eratio n A ttrac tio n G e n e ra tio n A ttra c tio n 7> 4.2.3 With reference to the latest highway infrastructure assumptions, Discovery Bay — Peng Chau/Trappist Monastery relevant key future highway infrastructures for this study are Existing Peak Hour Ferry Ridership summarised in Table 4.13 below. 7 i to/from Peng Chau/Trappist 30 237 119 11 Monastery (persons/hr)(2) Table 4.13 Highway Infrastructure Assumptions Capacity of Ferry Service Operated 364 364 182 182 Year 2026 (In addition to existing Road Network) Configuration 7* (persons/hr) Southern Connection of Tuen Mun-Chek Lap Kok Link D ual 2 Existing Occupancy of Ferry Service to/from Peng Chau/Trappist 8% 65% 65% 6% Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road Dual 3 it M o n a stery Hong K ong - Zhuhai - M acao Bridge D ual 3 Discovery Bay - Central Northern Connection of Tuen Mun-Chek Lap Kok Link D ual 2 it Existing Peak Hour Ferry Ridership 1,277 177 249 926 Lantau Road PI between Tung Chung and Sunny Bay D ual 2 to/from Central (persons/hr)(3)

Capacity of Ferry Service Operated ii 1,980 1,485 990 1,485 (persons/hr) 4.2.4 A brief summary of the key land-use assumptions are also listed below: Existing Occupancy of Ferry Service 64% 12% 2 5 % 6 2 % Tung Chung New Town (progressive population intake); \i Estimated Ferry Patronage to Represent 10,000 Flats under SkyCity developments located in the North Commercial District Approved OZP with Adjustment 1,532 212 299 1,111 of Airport Island (which includes SkyPlaza), plus some additional tn Factor of 1.2 (refer to Section 4.3) (persons/hr) development in the East Commercial District (from now to 2020); Estimated Pedestrian Trips Generated Asia World-Expo (AWE) future expansion (from now to 2025); im from Possible Residential 93 31 47 73 Developments in Area 6f (persons/hr) Siu Ho Wan MTR Depot Transportation Hub (2026); Estimated Pedestrian Trips Generated from Additional Residential Siu Ho Wan Depot Residential Development (foil intake by 2031); r* 220 73 112 172 Developments in Area 10b Siu Ho Wan Reclamation and Landside Development (full intake (persons/hr) by 2031); i Total Ridership with Additional Residential Developments 1,845 317 458 1,356 Boundary Control Facility Topside Development (2026); (persons/hr)

i Estimated Occupancy of Ferry Airport Third Runway (2026); 93% 2 1 % 4 6 % 9 1 % S ervice Tung Chung New Town Extension (by 2031) (I) Single trip from Mui Wo to Discovery Bay in AM peak; single trip from Discovery Bay to Mui Wo in PM peak <2> Reference to patronage count survey conducted on a typical weekday in Jan 2015 4.3 Assessment Scenarios ; w Reference to the peak hour ticket gate count provided by the operator •n , y 4.3.1 To evaluate the associated traffic impact likely to be induced by the additional developments in Discoyety Bay, two scenarios were 4.2 Future Year Major Highway and Land Use analysed and compared. The first scenario (i.e. “Reference Scenario”) ift ¥ Assumption assumed that the number of residential units in Discovery Bay would be grown to 10,000 flats from existing 8,326 flats under the current 4.2.1 The additional developments in Discovery Bay are targeted \ for approved OZP. An adjustment factor of 1.2 (^10,000 + 8,326) would A t'T completion in Year 2023. Year 2026 and 2031 are {used a s; the be applied to the Year 201 ^ wDiscovery Bay assessment years for the purpose of this study. to represent the traffic with l|0|i^0;flahsj a 4.2.2 Year 2026 and 2031 traffic forecast for the r"V 4.3.2 Reference has also been hiacle to, tjie> i^us approved TIA report for (eg. North Lantau Highway) and critical junctions' in T^jig Chung transport aiTangemehtsrln :Y i:^ taxi flow prepared with reference to our in-house strategic 1 sensitivity study tinder no Traffic {* eT generation for the pro and hotel - ' feii-.;

ft TLA ] Rev 1 | 29 April 2016 "H5>OCCiJVtNTl?aKJ»niOrarW (X>CG.tar FA'’ • QPTHAJAriON QAIAXD USfAIJ’OArvStACTATI TLA | Rev 1 129 April 2016 9 18 S«ATIA - ASIA tea l$USU«S

* '-iyK Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North, Area 10b, Hong Kong Resort Company Limited Traffic Study for Proposed Dewfopments in Area N1 North, Area 10b, Discovery Bay Discovery Say T ra ffic Im pa ct A sse ssm en t T ra ffic im p a ct A sse ssm en t

developments in Yi Pak, including taxi, goods vehicles, and public 4.4 Future Traffic Performance coach etc. has been included in the “Reference Scenario”. Although taxi service has already been introduced and surveyed in the Year 2015 flow, 4.4.1 The projected Year 2026 traffic flows of internal and external road the surveyed taxi flow is lower than that estimated in the previous study. networks for the “Reference Scenario” and “Design Scenario” are For conservative approach, the trip generation presented in previous shown in Figures 4.1 to 4.4 accordingly, while the same set of traffic study will be adopted in this study. flows for Year 2031 are shown in Figures 4.5 to 4.8 respectively. 4.3.3 For the taxi generation for residential developments in Discovery Bay, 4.4.2 Link capacity assessment for Year 2026 and 2031 are shown in Tables and it has been adjusted using the factor of 1.2 mentioned above, to 4.14 to 4.17 below, while junction capacity assessment for the key represent the flow under full 10,000 flats within Discovery Bay. junctions for Year 2026 and 2031 are summarised in Tables 4.18 and 4.19 below. The observed traffic flow condition in 2015 are shown 4.3.4 Traffic forecast of background traffic at critical strategic road links and together in the tables as reference. junctions outside Discovery Bay under the “Reference Scenario”, reference is made to our in-house strategic transport model, which has 4.4.3 All critical road links and key junctions are expected to operate with v/c incorporated with the latest highway infrastructure and planning ratio below 1.2 (except Lantau Link W/B during AM Peak of Year 2031 assumptions. Reference and Design Scenarios) and within practicable capacity during both AM and PM peak hour in Year 2026 and 2031, with the 4.3.5 In addition, trip generation and attraction of the possible residential additional residential developments in place. As shown in Tables 4.16 developments in Area 6f has also been included under the “Reference and 4.17, Lantau Link W/B would be operating with v/c ratio of 1.26 Scenario”. during AM Peak in Year 2031 Reference and 1.27 in Year 2031 Design Scenario, indicating that the impact of traffic generation from the 4.3.6 For the second scenario (i.e. “Design Scenario”), traffic generated by additional residential units on the said assessed road link is negligible. the additional residential developments in Area 10b of Discover Bay as presented in the previous section would be included on top of the traffic flow under Reference Scenario. 4.3.7 In summary, the assessed scenarios are listed below; • Year 2026/2031 “Reference Scenario” = Year 2026/2031 in-house traffic model with latest highway and planning assumptions + Surveyed Year 2015 Discovery Bay Traffic Flow with Adjustment Factor of 1.2 (for full development under approved OZP) + Traffic Generation and Attraction (including taxi) for Yi Pak Developments + Taxi Generation and Attraction with Adjustment Factor of 1.2 (forfull development under approved OZP) + Trips Generation and Attraction for Possible Residential Developments in Area 6f in Discovery Bay • Year 2026/2031 “Design Scenario” = Traffic Flow under “Reference Scenario” + Trips Generation and Attraction for Additional Residential Developments in Area 10b in Discovery Bay

TLA | Rev 1 j 29 A pril 2016 Page 19 TlA|R ev1129April 2016 Page 20 va^VTS»TRWPC_MOUPO0CUUe>mi3eWi3OS7)TWFMCl$«)Si'tHrMY.0PTlV1ZATiONOfL>.V0Uie*£PC«TiSEPeWTESWU^'0«(AfR»ie('CS f OK O S C O ,W BAY ■ OPTllAZADON OFlASO USC*EPO«r\StPM ATE SUeUSS<0>* (APR J01RO8 S1iATjA*ASEAttfi)5UEVS$

Hong Kong Resort Company Limited Traffic Study fo r Proposed Developments in Area N1 North, Area 10b. Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North, Area 10b. Discovery Bay Discovery Bay a Traffic impact Assessment Traffic Impact Assessment

Table 4.14 Year 2026 Projected Traffic Flow for Critical Links during Table 4.15 Year 2026 Projected Traffic Flow for Critical Links during Peak Hours - Reference Scenario (Unit: PCU/Hour) Peak Hours - Design Scenario (Unit: PCU/Hour)

Y ea r 2026 Y ea r 2026 Y ea r 2015 Y e a r 2026 Y e a r 2015 Y e a r 2026 Observed Flow R eferen ce S cenario Volume-to- Vplume-to- Carriageway Ca parity (V/C) Carriageway Observed Flow Design Scenario Critical Road C ritic a l R o a d Capacity (V/C) D irectio n C ap acity (P C U /H our) (P C U /H our) R atio D irectio n C a p a c ity - (PCU/Hoiir) (PCU/Hour) > L inks L in k s R a tio ' (P C U /h o u r) AM PM AM PM AM PM (P C U /h o u r) A M : PM AM PM AM PM P e a k P e a k P eak P e a k P e a k P e a k P e a k P e a k P e a k P e a k P eak P e a k E/B 6,100 3,570 4,480 4,950 5,250 0.81 0.86 E/B 6,100 3,570 4,480 4,960 5,265 0.81 0.86 Lantau Link Lantau Link W/B 6,100 4,495 3,575 5,390 5,175 0.88 0.85 W/B 6,100 4,495 3,575 5,400 5,185 0.89 0.85 E/B 6,100 3,090 3,840 3,165 3,450 0.52 0.57 North Lantau North Lantau E/B 6,100 3,090 3,840 3,180 3,465 0.52 0.57 H ighw ay W/B 6,100 3,540 3,300 3,755 3,545 0.62 0.58 H ighw ay W/B 6,100 3,540 3,300 3,765 3,560 0.62 0.58 Cheung Tung Road E/B 1,040 160 105 250 220 0.24 0.21 Cheung T ung Road E/B 1,040 160 105 255 230 0.25 0.22 Western Section W/B 1,040 160 110 230 190 0.22 0.18 Western Section W/B 1,040 160 110 235 195 0.23 0.19 Cheung Tung Road E/B 1,040 165 165 330 375 0.32 0.36 Cheung Tung Road e /b 1,040 165 165 335 385 0.32 0.37 Eastern Section W/B 1,040 175 120 345 290 0.33 0.28 Eastern Section W/B 1,040 175 120 360 305 0.34 0.29 E/B 1,280 D iscovery Bay 120 70 410 345 0.32 0.27 E/B Discovery Bay 1,280 120 70 435 370 0.34 0,29 Tunnel W/B 1,280 105 125 390 410 0.30 0.32 Tunnel W/B 1,280 105 125 415 435 0.32 0.34 Discovery Bay N/B 1,040 150 190 195 235 0.19 0.23 Discovery Bay Road (North of N/B 1,040 Road (North of 150 190 205 250 0.20 0.24 Discovery Valley S/B 1,040 155 175 200 220 0.19 0.21 Discovery Valley R oad) S/B 1,040 Road) 155 175 210 230 0.20 0.22 Discovery Bay N/B 1,040 180 225 245 295 0.24 0.28 Discovery Bay Road (South of N/B 1,040 180 Road (South of 225 260 310 0.25 0.30 Discovery Valley S/B 1,040 190 215 255 285 0.25 0.27 Discovery Valley R oad) S/B 1,040 R oad) 190 215 270 295 0.26 0.28 Discovery Valley E/B 1,040 35 55 60 85 0.06 0.08 E/B 1,040 35 R oad Discovery Valley 55 60 85 0.06 0.08 W/B 1,040 30 50 60 80 0.06 0.08 R oad W/B 1,040 30 50 60 80 0.06 0.08 E/B 1,040 75 45 345 310 0.33 0.30 ~~ Siena Avenue E/B 1,040 75 45 360 325 0.34 0.31 W/B 1,040 55 45 320 310 0,31 0.30 Siena Avenue W/B 1,040 55 45 335 325 0.32 0.31

i

} Hong Kong Resort Company Limited Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 Nortti. Area 10b, Traffic Study for Proposed Developments in Area N1 North, Area 10b, Discovery Say Discovery Bay Traffic Impact Assessment Traffic Impact Assessment

Table 4.16 Year 2031 Projected Traffic Flow for Critical Links during Table 4.17 Year 2031 Projected Traffic Flow for Critical Links during Peak Hours - Reference Scenario (Unit: PCU/Hour) Peak Hours - Design Scenario (Unit: PCU/Hour)

Y e a r 2015 Y ea r 2031 Y ea r 2031 Year 2031 Volume-to- Year 2015 Year 2031 Carriageway Observed Flow R eferen ce S cenario Capacity (V/C) Volume-to- Critical Road C ap acity (P C U /H our) (P C U /H o u r) D irection R atio Carriageway Observed Flow Design Scenario L in k s Critical Road Capacity (V/C) (P C U /hour) D irection C a p a c ity (P C U /H o u r) (P C U /H o u r) AM PM AM PM AM L inks R atio P e a k P eak P e a k P e a k P e a k (P C U /h o u r) P e a k AM PM AM PM AM PM E/B 6,100 3,570 4,480 6,865 7,445 P eak P e a k P e a k P e a k P e a k P e a k 1.13 1.22 Lantau Link W/B 6,100 4,495 3,575 7,710 7,505 1.26 E/B 6,100 .3,570 4,480 6,880 7,455 1.13 1.22 1.23 Lantau Link 6,100 3,090 3,840 4,300 5,270 0.70 W/B 6,100 3,575 7,725 7,520 1.27 1.23 North Lantau E/B ^ 8 6 4,495 H ighw ay W/B 6,100 5,305 E/B 6,100 3,090 3,840 4,310 5,285 0.71 0.87 3,540 3,300 5,005 0.87 0.82 ~ North Lantau E/B 1,040 160 105 265 240 0.26 H ighw ay W/B 6,100 5,020 0.87 0.82 Cheung Tung Road 0,23 3,540 3,300 5,320 Western Section E/B 0.24 W/B 1,040 160 110 230 190 0.22 0.18 Cheung Tung Road 1,040 160 105 275 250 0.26 E/B 1,040 165 345 400 0.33 Western Section W/B 1,040 195 0.22 0.19 Cheung Tung Road 165 0.38 160 110 230 Eastern Section W/B 1,040 340 290 E/B 1,040 405 0.34 0.39 175 120 0.33 0.28 Cheung Tung Road 165 165 355 Eastern Section W/B 1,040 0.30 Discovery Bay E/B 1,280 120 70 410 345 0.32 0.27 175 120 355 305 0.34 Tunnel W/B 1,280 105 125 390 410 0.30 E/B 1,280 0.34 0.29 0.32 Discovery Bay 120 70 435 370 Discovery Bay Tunnel W/B 1,280 0.34 N/B 1,040 150 190 195 235 0.19 105 125 415 435 0.32 Road (North of 0.23 Discovery Bay Discovery Valley N/B 1,040 150 190 205 250 0.20 0.24 Road (North of Road) S/B 1,040 155 175 200 220 0.19 0.21 Discovery Valley S/B 0.22 Discovery Bay R oad) 1,040 155 175 210 230 0.20 N/B 1,040 180 225 245 295 0.24 Road (South of 0.28 Discovery Bay Discovery Valley N/B 1,040 180 225 260 310 0.25 0.30 S/B 1,040 190 215 255 285 Road (South of Road) 0,25 0.27 Discovery Valley S/B 1,040 0.28 E/B 1,040 35 55 60 85 0.06 Road) 190 215 270 295 0.26 Discovery Valley 0.08 Road W/B 1,040 30 50 60 80 0.06 E/B 1,040 85 0.06 0.08 0.08 Discovery Valley 35 55 60 R oad E/B 1,040 75 45 345 310 0,33 W/B 1,040 30 50 60 SO 0.06 0.08 Siena Avenue 0 3 0 W/B 1,040 55 45 320 310 0.31 E/B 1,040 75 45 360 325 0.34 0.31 0.30 Siena Avenue W/B 1,040 55 45 335 325 0.32 0.31

TIA|Rev11 29 April 2016 Page 23 v > « fiffl,S$*TO TFK_aftO ^O O C UV £V r& 3C O O *36tfa TtA FO t W V BAY ■ OPTlUZATiON O f IASO tiSE'AEPORT^tPtRATE $L ^ U SS*ON (APft S1?A TU - AS EA K 6 iSb e.V$$ W V * OOCX TIA | Rev 1 129 April 2016 Page 24 w&wswTRWTO.aecwowvtsnasooMseonmFon dsco.m v tvr- optufwtsjh of uamj usraEeofmssfWTE swuss'ch (am source c rs s -tie _ io e i e /a itiiA U A U W i l / i Hoc I A ;* ft h •* cm >i -4C*- 50% >50% >50% >50% >50% >50% 42% 0.49 0.17 0.15 0.05 0.06 0.30 0.10 0.35 0.05 0.02 0.06 0.07 M A Y e a r 2015 2015 r a e Y eve ed serv b O 50% > 50% > >50% >50% >50% >50% 33% 0.16 0.03 0.37 0.08 0,44 0.20 0.05 0.09 0.06 0.04 0.36 0.05 M P >50% >50% >50% >50% >50% >50% 0.34 0.02 .n o 0.32 0.52 0.06 0.12 0.49 M A 0.70 0.49 0.20 0.27 17% eai * cenario S Y ea r 2026 2026 r ea Y R eference eference R afi i ssment ssessm A t c a p im ffic ra T >50% >50% >50% >50% >50% >50% 1 21% 0.42 0.07 0.15 0.28 0.04 0.09 0.49 0.52 N orth, A re a 10b. a re A orth, N 0.72 0.50 0.18 0.24 M P D isco ve ry Bay Bay ry ve isco D >50% >50% >50% >50% >50% >50% 0.32 0.06 0.28 0.37 0.14 0.55 0.52 0,75 0.52 0.03 0.11 0.21 M A 16% S cenario * cenario S Y ea r 2026 2026 r ea Y Design Design >50% >50% >50% >50% >50% >50% 20% 0.28 0.52 0.77 0.45 0.07 0.15 0.04 0.25 0.12 0.55 0.53 0.19 M P J15 J18 J16 J13B I7 J J14 J13A J12 l l J J10 J9 J8 J7 J6 J4 J3 J5 J2 J1 T ung Chung E ast Interchange ast E Chung ung T rhLna gway ighw H Lantau orth N T ung C hung W aterfront Road / Slip Road Road Slip / Road aterfront W hung C ung T T at Tung R oad / H ing T ung Street ung T ing H / oad R Tung Street at T Tung ei M / oad R Tung Tat to Road Slip / Road aterfront W hung C ung T C hek L ap K ok South R oad Roundabout oad R South ok K ap L hek C Avenue ista V / Road ay B iscovery D rm rhLna gway ighw H Lantau orth N from Shun T ung R oad / Yu T ung Road ung T Yu / oad R ung T Shun Tunnel Bay Discovery / Road ung T heung C Road Tung at T Drive Headland / oad R ay B iscovery D Siena A venue N orth Roundabout orth N venue A Siena Drive arina M / oad R ay B Lane iscovery D Plaza / Road ay B iscovery D Sunny B ay Road / Cheung Tung Road Tung Cheung / Road ay B Sunny (East) Road Tung Tat / Road ung T Shun hnTugRa Ta ugRa West) (W Road Tung at T / Road ung T Shun D iscovery B ay Road / D iscovery V alley Road alley V iscovery D / Road ay Road B ay B iscovery D iscovery D / Tunnel ay B iscovery D n n otCo ayLmited Lim pany om C sort e R ong K ong H uncton tio c n Ju I Fu T ung Street ung T Fu * Figures shown represent “Design Fiow/Capacity” (DFC) ratio for roundabout and priority and forroundabout ratio (DFC) Fiow/Capacity” “Design shown Figuresrepresent * al .9 Year 2031Junction TablePerformance 4.19 junctions, and “Reserve Capacity” for for and Capacity” signal “Reserve junctions junctions, oundabout R oundabout R Roundabout oundabout R Priority Priority Priority Priority Priority Priority Priority Priority Signal Signal Signal Signal Signal Signal Signal e p y T afi Std or ooe Deeomet n e 1 t Ar 10b. a re A . rth o N N1 rea A in ents evelopm D roposed P r fo tudy S ffic ra T ^ 0.05 ^ >50% >50% >50% >50% >50% >50% P erfo rm a n ce * ce n a rm erfo P 0.15 0.49 42% 0.06 0.17 0.05 0.30 0.02 0.10 0.35 0.07 0.06 M A Y e a r 2015 2015 r a e Y eve ed serv b O >50% >50% >50% >50% >50% >50% 0.16 0.44 33% 0.20 0.03 0.04 0.05 0.37 0.05 0.08 0,36 0.06 0.09 M P >50% >50% >50% >50% >50% 0.85 0.42 0.06 0.70 0.40 0.27 15% 0.53 0.02 0.12 0.49 0.20 17% 0.11 M A , R eferen ce ce eferen R , eai * cenario S Y ea r 2031 2031 r ea Y afi I tAsesme t en ssm sse A ct a p Im ffic ra T >50% >50% >50% >50% >50% >50% 0.43 0.87 0.04 21% 0.73 0.54 0.40 0.24 0.09 0.07 0.49 0,15 0.18 M P D iscovery Bay Bay iscovery D >50% >50% >50% >50% >50% 0.85 0.42 0.06 15% 0.75 0.28 0.55 0.43 0.14 16% 0.03 0.11 0.55 0.21 M A S cen a rio * rio a cen S Y e a r 2031 2031 r a e Y D esign esign D >50% >50% >50% >50% >50% >50% 0.43 0.87 0.04 0.25 20% 0.78 0.43 0.57 0.07 0.12 0.55 0.15 0.19 M P Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North. Area 10b. Hong Kong Resort Company Limited Traffic Study for Proposed Developments in Area N1 North, Area 10b, Discovery Bay Discovery Bay Traffic Impact Assessment Traffic Impact Assessment

respectively, indicating that the impact of traffic generation from the 5 SUMMARY AND CONCLUSION additional residential units on the said assessed road link is negligible. 5.1.8 In addition, the existing ferry service would still operate within capacity 5.1 Summary with the additional residential developments in place. 5.1.1 There are plans to optimize the residential potential of Discovery Bay, in particular in Area 10b with a total of 1,125 nos. of flats into 5*2 Conclusion residential development in additional to the current approved Outline Zoning Plan. 5.2.1 The proposed additional residential developments in Discovery Bay (i.e. Area 10b) would not generate adverse traffic impact to the ferry 5.1.2 This submission has addressed comments from Transport Department services and the critical road links and junctions in Discovery Bay, received on 25 April 2016, in particular, the latest planning assumptions Tung Chung and Sunny Bay areas. Therefore, the additional residential for Siu Ho Wan Depot Residential Development and Siu Ho Wan developments are acceptable from traffic point of view. Reclamation and Landside Development have been adopted in the future year traffic assessment. 5.1.3 Under the existing comprehensive traffic control management for Discovery Bay, only authorized vehicles are allowed to access Discovery Bay via Discovery Bay Tunnel such as emergency vehicles, servicing buses and goods vehicles. And coaches with prior registration could access Discovery Bay (North). Since 26 October 2014, designated areas in Discovery Bay (North) are also accessible by Urban and Lantau Taxis. 5.1.4 Comprehensive traffic counts were conducted at critical road links including Discovery Bay Road, Discovery Valley Road, Siena Avenue, Discovery Bay Tunnel, Cheung Tung Road and North Lantau Highway, Lantau Link, and key junctions in Discovery Bay, Tung Chung and Sunny Bay areas. They are all currently operating with significant spare capacity during both AM and PM peak hour. 5.1.5 To investigate the performance and handling capacity of the critical road links and junctions, an analysis was carried out to appraise the likely traffic impact generated by the additional developments (i.e. residential) in the Discovery Bay. Assessment on the existing ferry services has also been conducted. 5.1.6 Both reference scenario (full development under current approved OZP with traffic generation for Yi Pak developments) and design scenario (with traffic generation from the additional residential development) have been assessed, for Year 2026 and 2031. 5.1.7 All key road links and junctions would be operated below v/c ratio of 1.2 (except Lantau Link in Year 2031 Reference and Design Scenarios) and within practicable capacity during both AM and PM peak hour, with the additional residential developments in place. Lantau Link W/B would be operating with v/c ratio of 1,26 and 1.27 during AM Peak, under Year 2031 Reference and Year 2031 Design Scenario

TIA l Rev 1 ] 29 April 2016 Page 27 T1A | Rav 1 129 April 2016 Page 28 U«WrSS*TIWFFlC_MOOfAOOCUV£fmi3«OaM3M>* TlA FOS O S C C . t R Y B A Y - C P TlUZATlON O f UN O USPBEFOAr'SEPMATE S ^ W S S W I (APB 2 0 tr/O 9 «»0.!%NT;-8J T«XFF>C.GSCVP OOCO V E N T r e T1A FOR OSCO/EAY BAY , OPTWEATlON OF UNO U S tS E fO R INS EFU A S L e U S $ lO i(A W M15TOS V 2A TU -ASEA (S’JBttSS'G N ) V4 DOCX SI 2A T1A • A-REAVMlSU EMISSION) Y

|

Cl

KI Stm t •-S c« toH f I ? 5

£

v r ~ r IV r ' \

nntww/ \> o y m --/iM i t ■■, . \ ^ ...y-' / ■ •■ > l-w . .■ -H} 1 ••

„ __ . VfrTilS >4Kx Y( 4lv - W - ;/T ?y \ <.. ;^ \ 7\x > ' ) / / ,-• -•; ■ ■; :;. i'i ■ ’i N i_ ,J r - / rlwN5u_:>h H- y yT « »' / . a -' ^ ,'J V .\ir; Jj -If/ ■■. .■■ i f r h IiEj S j l C1 ( L S \ ^ ( ) : y , 1 V ^V A v ■'"' -■ ■• -■ /■• '■ ';V- ' ■' / ------uir —■, -■. j _j ■ W/', v / " 1-/i i\-' i ■, x x •• ••■--.•.• ■ y ■ /,/,-■ -' ) w >-*v - iLa^v [' ^ ^ f" A j i{- >J S * > ■ a - -

A A A i L Q r , /. /4Cb-, AAA ■- XJ d is c o v e r y b a y t u n n e l ^ -, c ^ ; - '•■- l /. ^ -

A -' 'y ("O h , ~ ,. ,iy , r -■ • 7 ; r f ^ > v ^ s • „ ,rx;fr < 1;;; J^ ',\U....^VA;^'T;St£NAAVENU^a o X ^ sienamnue I x !' ■" v . ^ 'y y 1 {•''-' '■'•} )\ i ' 1 ^~—- -i - -? s TOWARDS ' TUNG CHUNG / i AIRPORT Ba V s IDE D R IV E -^ ,,: ^ J ^ € f ^ J

\> y -\'.t

t. i ■xs

a t ^ r r : ^ ^

'< 4 * < 'A'!

T % k * 0 . .r.i* J •\\ : - a ay X- s,^ '< a # ;.‘> / ..;V V

TRAFRC STUDY FOR PROPOSED DEVELOPMENTS IN AREA N1 NORTH, AREA 10B, DISCOVERY BAY F IG U R E 2.1

NOV 15 1:11000 fe* EXISTING ROAD NETWORK IN DISCOVERY BAY WTL 236078 ARUP (fc\tro^^KOCWJ»Tl My ______| | fc\»tfrV<\JJOgoiW)«Jl U ttw ^ Mj ileMrftHr(VWittn^fi*'W'W' I j l ____ i m l ------'i & l ------i a 1 4 * 1____ Am)... i j ) . ___ i s l ___ la* ^a>: _la? *-5> % = £ ?£>' is . j a> i = >

d b

/ &>

SUP ROAD TO / ) < f NORTH LANTAU HIGHWAY ^ / / J m / / # ( j-SUNNY BAY ROAD

CHEUNG TUNG ROAD

SUP ROAD FROM NORTH LANTAU HIGHWAY 245(235)— » ( d ) s u n n y b a y 930(605)“ ^ - _ 5(5) ' - p

NORTH LANTAU HIGHWAY I ± 5 ( 5 ) 't - 105(75) sF~ 350(370)

LEGEND:

556(454) PM PEAK (PCU/HR)

t . . AM PEAK (PCU/HR) | M N* 5 t r M=RC STUDY FOR PROPOSED DEVELOPMENTS IN AREA N1 NORTH, AREA 10B, DISCOVERY BAY F IG U R E 2.4 I NOV 15 NTS. EXISTING YEAR 2015 OBSERVED TRAFFIC FLOWS (EXTERNAL ROAD NETWORK) WTL 236078 ARUP

M N b * j (ItfNd'ti^SmOUtVOS^ClX.U^ j I «\»o^\2»OOO^MO?l «7 tkn^CrV^

Hong Kong Resort Company United Traffic Study for Proposed Developments in Area N1 North, Area 10b. Discovery 8ay Traffic Impact Assessment 1

Bus Octopus Count Provided by Operators (Typical Weekday) j

to DB to DBN t o S B IO D 8 t o S B to D S D B 0 2 R S j g j g O B 0 3 P 1 3 7 6 1 1 3 3 0 2 6 3 1 7 7 8 3 2 5 2 3

00:00 16 ' § s j § p 0 0 X 0 39 0 0 X 0 01:00 13 0 1 X 0 WSM 10 0 1 X 0 is ;'.'!'? , 02:00 8 02X 0 02X 0 Appendix A______03,-00 3 l l g l l § p 03X 0 0 3 X 0 04:00 13 0 4 X 0 04X 0 05:00 3 ! 0 5 X 0 ma&. 0 5 X 0 Bus Octopus and Ferry Ticket 0 6 X 0 70 06X 0 141 31 06X 0 07:00 98 14 0 7 X 0 403 154 07X 0 49 10 0 3:00 105 16 0 8 X 0 424 286 08X 0 115 4 3 Gate Count Provided by 09:00 43 12 0 9 X 0 298 129 0 9 X 0 52 37 10:00 51 8 10X 0 210 91 10X 0 89 11 Operators 11.00 51 1 iixo 162 91 11X0 60 21 12:00 66 1 12X 0 134 82 12X 0 54 16 13:00 63 11 13X 0 147 109 13X 0 53 2 5 14,00 74 5 14X 0 114 93 14X 0 44 21 15:00 9 2 12 15X 0 122 92 15X 0 53 36 16:00 69 4 1 6X 0 109 211 16X 0 68 30 l/.O O 60 10 1 7X 0 272 175 17X 0 89 3 2 18X 0 76 10 18X 0 193 390 18X 0 52 4 3 19:00 64 7 19X 0 109 338 19X 0 30 74 2 0:00 54 1 2 0 X 0 55 254 2 0 X 0 14 67 21:00 95 ' 1 2 1 X 0 46 262 2 1 X 0 10 39 2 2 X 0 102 ' 22X 0 48 219 2 2 X 0 18 2 3 0 0 7 0 2 3 X 0 33 121 23:00

Ferry Ticket Gate Count Provided bv Operators (Typical Weekday)

T o ta l T o ta l ; ;#irom T v; fr o m rtte rs tv p c a p a & y ridersW p c a p a c ity Central P ier D B P ie r 5 4 3 7 2 1 2 9 0 $ 3 1 2 2 2 2 8 0 00X0 87 7 93 00X0 9 7 9 3 01X0 3 5 4 9S 01X3 6 2 9 8 0200 31 2 9 3 02X1 0 2 9 8 « x o 16 2 9 3 03X3 ^ , - .0 r . J\. A 04X0 04.00 4 2 9 3 05X0 15 2 9 8 05X0 ’ V *. 06X0 2 0 2 9 3 05X0 210 1239 07X0 117 1435 07X0 651 1930 03X0 177 1435 03X3 1277 1930 09.00 88 9 90 OKC 511 9 9 0 10X0 114 9 9 0 IOcCO 451 9 9 0 11X0 127 9 9 0 iixb 3X4 9 9 0 1200 119 $ 9 0 12X0 299 9 90 13X0 176 9 90 13X0 272 9 9 0 14X0 249 3 9 0 14X0 238 $ 9 0 15X0 371 1485 1SX0 167 9 9 0 16X0 277 9 9 0 16X0 172 9 9 0 17.X0 4 4 0 9 90 17x6 199 9 9 0 18X0 926 1435 16X0 249 148 5 19XO 563 9 9 0 19X0 97 9 9 0 20X0 503 9 9 0 20X0 45 9 9 0 21X0 418 9 9 0 21X0 64 9 9 0 22X0 364 9 90 22X0 57 9 9 0 23X0 204 9 9 0 23X1 30 9 9 0

T!A| Rev 1129 A pril2016

>H(GVTS«9T«ArrX,GA0VPCi0ClJVEhTtfMe»e»JTS'nAFO1t PJCOYISV SAY -OPTIV-ZATC* O f UMJ USCflerORT'SEFiftATE SSTCW (AM* W tSrM SWA T1A - AJ! EA ICS ISV 6 » « O S ) V4.D0CX