Scanned by CamScanner Minutes of the 27th Meeting of Expert Appraisal Committee (Infra-2) held on 25th January, 2018

(xxvi) Traffic congestion near the entry and exit points from the roads adjoining the Airport shall be avoided. Parking should be fully internalized and no public space should be utilized. (xxvii) Traffic Management Study and Mitigation measures as given in the EIA Report shall be implemented in letter and spirit. Apart an assessment of the cumulative impact of all activities being carried out or proposed to be carried out by the project, shall be made for traffic densities and parking capabilities in a 02 kms radius from the site. A detailed traffic management and a traffic decongestion plan drawn up through an organisation of repute and specialising in Transport Planning shall be implemented to the satisfaction of the State Urban Development and Transport Departments shall also include the consent of all the concerned implementing agencies. (xxviii) Energy conservation measures like installation of LED/CFLs/TFLs for the lighting the areas outside the building should be integral part of the project design and should be in place before project commissioning. Used CFLs and TFLs should be properly collected and disposed off/sent for recycling as per the prevailing guidelines/ rules of the regulatory authority to avoid mercury contamination. (xxix) An onsite disaster management plan shall be drawn up to account for risks and accidents. This onsite plan shall be dovetailed with the onsite management plan for the district. (xxx) The company shall draw up and implement a corporate social Responsibility plan as per the Company’s Act of 2013. (xxxi) A water security plan to the satisfaction of the CGWA shall be drawn up to include augmenting water supply and sanitation facilities and recharge of ground water in at least two villages and schools, as part of the C.S.R. activities. 27.3.8 Development of 3 remaining integrated facilities (Stage I) within the existing Kandla Port trust at , Kutch, by M/s Kandla Port Trust - Environmental & CRZ Clearance (F. No. 10-9/2017-IA-III; IA/GJ/MIS/61975/2017) The project proponent and the accredited Consultant M/s Mantec Consultants Pvt. Ltd. gave a detailed presentation on the salient features of the project and informed that: (i) Deen Dayal Port is situated at Latitude 23º01’N and Longitude 70º13’E on the shores of the Kandla Creek, Gulf of Kutch at a distance of 90 nautical miles from the Arabian Sea. The width of the channel varies from 200 meters to 1,000 meters. The total length of the Kandla Port approach Channel is around 23 km. (ii) Kandla Port Trust (renamed as Deendayal Post Trust) had obtained Terms of Reference for conducting EIA studies from MoEF&CC, vide letter F.No. 10-9/2017- IA.III dated 06.06.2017. (iii) Public Hearing was exempted by the Ministry as per para-7(ii) of EIA Notification, 2006, because public hearing has already been conducted by the Gujarat Pollution Control Board on 18.12.2013. (iv) CRZ recommendations have been received from SCZMA, Gujarat vide their letter no ENV-10-2015-248-E (T Cell) dated 29.06.2016 for the projects.

Page 21 of 45

Minutes of the 27th Meeting of Expert Appraisal Committee (Infra-2) held on 25th January, 2018

(v) The project involves following components: • Development of Container Terminal at Tuna off Tekra on BOT basis Jetty T shape 1100m x 54m, capacity 2.19 Million TEUs/annum, Dredging: Capital 13,56,000 m3 Maintenance 2,71200 m3/year, Land Area : 84 Ha Break water: Length of 1400 m with 20m ht. • Construction of Port Craft Jetty & shifting of SNA Section at Kandla Port Trust • Railway Line from NH-8A to Tuna Port- 11.00 km (vi) 5.0 KLD water will be used for various purposes during the project. (vii) Solid wastes generated from the colony will be taken care by the waste disposal plan. The construction waste may pose impacts on land environment by contamination of soil and hence the wastes shall be utilized for PCC works, Road construction, and other filling requirement etc. The accidental spillage of fuels and lubricants oils will be minimized by proper care. (viii) There will be temporary influx of people to the area who will be involved directly and indirectly during the construction of Jetty. (ix) The total land requirement for the project is 95 Ha. There is no land acquisition as land belongs to Kandla Port Trust. (x) Total project cost is Rs. 3214.17 crores. (xi) Benefits of the project: Faster evacuation of Cargo, thereby Increase in cargo evacuation capacity, Earning through special port charges on rail bound / rail borne cargo passing through the Railway line. Enhances the possibility of receiving higher revenue share quotes for various BOT projects to be developed nearby Tuna port. (xii) Employment potential: The indirect employment potential of the projects would be significantly beneficial for the area. The project requires recruiting numbers of skilled, semi-skilled and un-skilled manpower during the construction phase and indirect employment through contracts for civil construction, Mechanical erection, electrification, plumbing works and associated amenities. The proposed project is expected to employ about 200 people per day of various skills which would mean income to about 200 people.

During deliberations, the EAC noted the following:- (i) The proposal is for grant of Environmental and CRZ Clearance to the project ‘Development of 3 remaining integrated facilities (Stage I) within the existing Kandla Port trust at Gandhidham, Kutch, Gujarat by M/s Kandla Port Trust. (ii) The project/activity is covered under category ‘A’ of item 7 (e) i.e. Ports, harbours, break waters, dredging’ of the schedule to the EIA Notification, 2006 and its subsequent amendments, and requires appraisal at Central level. (iii) Terms of Reference (ToR) was granted by MoEFCC vide F.No. 10-9/2017-IA.III dated 06.06.2017. (iv) Public Hearing was exempted by the Ministry as per para-7(ii) of EIA Notification, 2006, because public hearing has already been conducted by the Gujarat Pollution Control Board on 18.12.2013.

Page 22 of 45

Minutes of the 27th Meeting of Expert Appraisal Committee (Infra-2) held on 25th January, 2018

After detailed deliberation, the Committee sought following additional information:

(i) Submit a copy of layout superimposed on the HTL/LTL map demarcated by an authorized agency on 1:4000 scale. (ii) Submit a copy of google earth map on which the railway line is superimposed. (iii) Submit KML file of the project along with 3 years prior data. (iv) Upload Certified Compliance Report issued by the MoEF&CC, Regional Office for the conditions stipulated in the earlier environmental clearance issued for the project along with an action taken report on issues which have been stated to be partially complied or non/not complied. (v) The EIA Report should be updated with one month latest data (Non monsoon). (vi) Response to the representation submitted by the Conservation Action Trust. (vii) A copy of the Marine biodiversity management plan duly validated by the State Biodiversity Board (viii) No Objection Certificate from the concerned State Pollution Control Boards for the projects involving discharge of effluents, solid wastes, sewage and the like. (ix) A certificate of adequacy of available power from the agency supplying power to the project along with the load allowed for the project. (x) A detailed Plan for green belt development. (xi) A certificate from the competent authority handling municipal solid wastes, indicating the existing civic capacities of handling and their adequacy to cater to the M.S.W. generated from project. (xii) A certificate from the local body supplying water, specifying the total annual water availability with the local authority, the quantity of water already committed, the quantity of water allotted to the project under consideration and the balance water available. This should be specified separately for ground water and surface water sources, ensuring that there is no impact on other users. (xiii) A detailed traffic management and traffic decongestion plan to ensure that the current level of service of the roads within a 02 kms radius of the project is maintained and improved upon after the implementation of the project. This plan should be based on cumulative impact of all development and increased habitation being carried out or proposed to be carried out by the project or other agencies in this 02 Kms radius of the site in different scenarios of space and time and the traffic management plan shall be duly validated and certified by the State Urban Development department and the P.W.D. and shall also have their consent to the implementation of components of the plan which involve the participation of these departments. The proposal was, therefore, deferred till the desired information is submitted.

27.3.9 Development of Integrated facilities (Stage-II) within the existing Deendayal Port Trust (Erstwhile Kandla Port Trust) at District Kutch, Gujarat. (1. Setting up of Oil Jetty No.7. 2. Setting up of Barge jetty at Jafarwadi 3. Setting up of Barge port at Veera; 4. Administrative office building at Tuna Tekra; 5. Road connecting from Veera barge jetty to Tuna gate by M/s Deendayal Port Trust (Erstwhile Kandla Port Trust) -

Page 23 of 45

S.No. EAC Observations Compliance 1 Submit a copy of layout Copy of the CRZ Map having layout superimposed on superimposed on the the HTL/LTL map prepared by Anna University is HTL/LTL map demarcated by enclosed as Annexure-A. an authorized agency on 1:4000 scale. 2 Submit a copy of google earth Google earth map of the railway line is enclosed as map on which the railway line Annexure-B. is superimposed. 3 Submit KML file of the KML file of the project along with 3 years prior data project along with 3 years provided by Anna University is enclosed in CD as prior data. Annexure-C.

4 Upload Certified Compliance Certified Compliance Report issued by the MoEF&CC, Report issued by the Regional Office along with an action taken report on MoEF&CC, Regional Office issues is enclosed as Annexure-D. for the conditions stipulated in the earlier environmental clearance issued for the project along with an action taken report on issues which have been stated to be partially complied or non/not complied. 5 The EIA Report should be The updated EIA report is attached as Annexure-E updated with one month latest with one month latest non-monsoon data for February data (Non monsoon). 2018 is given in Chapter 3 of the EIA report.

6 Response to the representation Response to the representation submitted by the submitted by the Conservation Conservation Action Trust is enclosed as Annexure F. Action Trust. 7 A copy of the Marine Marine Biodiversity report along with management plan biodiversity management plan has been prepared by NIO along with the certificate. A duly validated by the State copy of the same is enclosed as Annexure G. Biodiversity Board. Further, as per the EC granted by the MoEF&CC, GoI dated 19.12.2016 for 7 integrated facilities, in compliance of condition regarding Regular Monitoring of marine ecology, DPT has entrusted the work to M/S GUIDE, during 9.5.2017. M/S GUIDE Bhuj jas prepared first six monthly monitoring report of marine ecology. In addition, as directed in ToR for Oil Jetty 8 to 11 projects, EIA Consultant M/S SV Enviro has also prepared Biodiversity Impact Assessment and Management Plan.

8 No Objection Certificate from No Objection Certificate obtained from GPCB is the concerned State Pollution enclosed as Annexure H. Control Boards for the projects involving discharge of effluents, solid wastes, sewage and the like 9 A certificate of adequacy of Certificate of adequacy of available power is attached available power from the as Annexure I. agency supplying power to the project along with the load allowed for the project.

10 A detailed Plan for green belt A detailed Plan for green belt development is given in development. the EIA report at Section 10.9 of Chapter 10.

11 A certificate from the A copy of the CCA issued by GPCB in this regard is competent authority handling enclosed as Annexure-J. municipal solid wastes, indicating the existing civic capacities of handling and their adequacy to cater to the M.S.W. generated from project.

12cons A certificate from the local Copy of the certificate is attached as Annexure-K. body supplying water, specifying the total annual water availability with the local authority, the quantity of water already committed, the quantity of water allotted to the project under consideration and the balance water available. This should be specified separately for ground water and surface water sources, ensuring that there is no impact on other users. 13 A detailed traffic management These three integrated facilities are expansion of and traffic decongestion plan existing Deendayal Port Trust. While establishing to ensure that the current level Truck parking facilities for Deendayal Port Area, the of service of the roads within a necessary traffic study has already been done 02 kms radius of the project is (considering existing facilities and proposed facilities) maintained and improved through expertise agency and accordingly. M/s upon after the implementation WAPCOS has submitted detailed report including of the project. This plan management plan during the year Oct 2016 (Annexure- should be based on cumulative L). As the entire area of DPT comes under the impact of all development and jurisdiction of DPT, there is no need to obtain increased habitation being validation from state urban development dept and the carried out or proposed to be PWD . Further, for smooth evacuation of cargo and to carried out by the project or avoid traffic congestion, DPT has already planned to other agencies in this 02 Kms construct RoB near Kutch salt junction, in consultation radius of the site in different with the National Highways Authority. Necessary scenarios of space and time Environmental and CRZ Clearance for proposed RoB is and the traffic management expected soon from the SEIAA, Gujarat. plan shall be duly validated and certified by the State Urban Development department and the P.W.D. and shall also have their consent to the implementation of components of the plan which involve the participation of these departments.

Note- The KML File will be submitted in CD because we cannot send the KML file in PDF Form.

Annexure E

ENVIRONMENT IMPACT ASSESSMENT REPORT FOR DEVELOPMENT OF 3 REMAINING INTEGRATED FACILITIES (STAGE-I) WITHIN THE EXISTING DEENDAYAL PORT TRUST AT GANDHIDHAM, KUTCH, GUJARAT BY DEENDAYAL PORT TRUST

DEENDAYAL PORT TRUST

M.2016/ME1017 JUNE, 2018

Prepared By

MANTEC CONSULTANTS PVT LTD QCI/NABET Accredited EIA Consultant at S.No.100 as per List of Accredited consultant Organizations/Rev.66A/June.15, 2018 and MoEF & NABL approved Laboratory

Environment Division, D-36, Sector-6, Noida-201 301, U. P., Ph. 0120-4215000, Fax. 0120-4215809, e-mail: [email protected], [email protected], Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Table of Contents Chapter 1. Introduction ...... 1 1.1 Purpose of the Report ...... 1 1.2 Identification of Project and Project Proponent ...... 2 1.3 Brief Description of Nature, Size, Location of the Projects and Importance to Country, Region ...... 2 1.4 Scope of Study ...... 6 1.5 Site Selection ...... 17 1.6 Methodology for Environment Impact Assessment ...... 18 1.7 Prevailing Marine Environment ...... 19 1.7.1 Tides ...... 19 1.7.2 Current ...... 19 1.7.3 Circulation ...... 20 1.7.4 Water Quality ...... 20 1.7.5 Sediment Quality ...... 20 1.7.6 Flora and Fauna ...... 20 1.8 Marine Environment Impact Assessment ...... 20 1.9 Likely Impact on Environment ...... 20 1.10 Environmental Management Plan (EMP) ...... 21 Chapter 2. Project Description...... 22 2.1 General ...... 22 2.2 Description of the Projects ...... 23 2.2.1 Development of Container Terminal at Tuna off Terka on BOT basis ...... 23 2.2.2 Construction of Port Craft Jetty & shifting of SNA Section at Deendayal Port Trust 25 2.2.3 Providing Railway Line from NH‐8A to Tuna Port‐ 11.00 km ...... 25 2.3 Type of the Projects ...... 26 2.4 Need of the Projects ...... 27 2.5 Locations of the Projects ...... 34 2.6 Port Logistics...... 39 2.7 Infrastructural Advantage at Kandla ...... 39 2.8 Chemical & Liquid Handling Complex ...... 39 2.9 Storage Facilities ...... 40

Mantec Consultants Pvt. Ltd. Page i Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

2.10 Berthing Policy Highlights ...... 40 2.11 Port Equipments ...... 41 2.12 Upcoming Projects ...... 42 2.13 Highlights of Fire Safety Measures ...... 43 Chapter 3. Description of Environment ...... 44 3.1 Air Environment ...... 44 3.1.1 Meteorology ...... 44 3.1.2 Ambient Air Quality ...... 51 3.1.3 Result of Comparision with earlier collected Air Quality Data (2012‐13) ...... 63 3.2 Noise ...... 63 3.2.1 Objective...... 63 3.2.2 Methodology ...... 64 3.2.3 Parameters Measurement ...... 64 3.2.4 Sampling Locations ...... 64 3.2.5 Noise Standards ...... 66 3.2.6 Results and Discussion ...... 67 3.2.7 Result of Comparison with earlier collected Noise Quality Data (2012-13): ...... 67 3.3 Water Environment ...... 68 3.3.1 Selection of Sampling Locations ...... 68 3.3.2 Methodology ...... 71 3.4 Water Quality of the Study Area (Surface water & ground Water) ...... 71 3.4.1 Result of Comparison with earlier collected Water Quality Data (2012-13); ...... 76 3.4.2 Physico-chemical & biotic components of water: ...... 77 3.5 Land Environment ...... 78 3.5.1 Topography ...... 78 3.5.2 Land Use Classification of the Study Area ...... 79 3.5.3 Soil ...... 80 3.5.4 Result of Comparison with earlier collected Soil Quality Data (2012-13): ...... 87 3.6 Biological Environment ...... 88 3.6.1 Objectives ...... 88 3.6.2 Methodology of the Study ...... 88 3.6.3 Biogeography and Physiography of the area ...... 89 3.6.4 Forests & Vegetation of the area ...... 89 3.6.5 Fauna ...... 97

Mantec Consultants Pvt. Ltd. Page ii Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

3.6.6 Trend analysis of fishing activity at Kandla creek & Tuna creek ...... 108 3.6.7 Mangroves ...... 109 3.7 Marine Environment ...... 114 3.7.1 Costal Hydrology/Geomorphology ...... 115 3.7.2 Bed Sediment/Dredging Sludge Quality ...... 124 3.8 Socio‐economic Study ...... 125 3.8.1 Project Site & Study Area ...... 129 3.8.2 Demographic Profile of the Study Area ...... 129 3.8.3 Occupational Structure ...... 136 3.8.4 Impact Identification ...... 144 3.8.5 Fisheries ...... 144 Chapter 4. Anticipated Environmental Impact & Mitigation Measures ...... 145 4.1 Introduction ...... 145 4.2 Air Environment ...... 145 4.2.1 Emissions Sources during the Construction phase ...... 145 4.2.2 Emissions Sources during the Operational phase ...... 146 4.3 Anticipated Impacts...... 147 4.4 Noise Environment ...... 157 4.4.1 Noise Generation during Construction Phase ...... 157 4.4.2 Prediction of Noise Quality Impacts ...... 158 4.4.3 Noise Generation during Operational Phase ...... 159 4.5 Water Environment ...... 160 4.5.1 Impact in Construction Phase ...... 160 4.5.2 Impact in Operational Phase ...... 161 4.6 Land Environment ...... 162 4.6.1 Impacts during Construction Phase ...... 162 4.6.2 Impacts during Operational Phase ...... 163 4.7 Biological Environment (Marine Ecology of Creeks) ...... 163 4.7.1 Mangroves Conservation Plan ...... 171 4.8 Socio‐Economic Environment ...... 174 4.8.1 Impact during Construction Phase ...... 174 4.8.2 Impact during Operational Phase ...... 175 4.9 Dispersion Modelling for dumping of the dredge materials ...... 179 4.10 Impact of dredging on shoreline: ...... 181

Mantec Consultants Pvt. Ltd. Page iii Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

4.11 Impact of Rock Dredging ...... 182 Chapter 5. Analysis of Alternatives ...... 183 5.1 General ...... 183 5.2 Selection of Sites ...... 183 5.3 Alternate Sites ...... 185 Chapter 6. Environment Monitoring Programme ...... 186 6.1 Introduction ...... 186 6.2 Environmental Monitoring ...... 186 6.2.1 Meteorology ...... 189 6.2.2 Ambient Air Quality ...... 189 6.2.3 Water Quality ...... 189 6.2.4 Noise Level ...... 189 6.2.5 Soil/Sediment Quality ...... 190 6.2.6 Marine Ecology ...... 190 Chapter 7. Additional Studies ...... 191 7.1 Oil Spill ...... 191 7.1.1 Objective of Oil Spill Study ...... 191 7.1.2 Causes of Oil Spill ...... 191 7.1.3 Spill Quantities...... 192 7.1.4 Oil Spill Contingency Plan ...... 193 7.1.5 Composition of Oil ...... 193 7.1.6 Toxicity ...... 195 7.1.7 Weathering Process ...... 196 7.2 Marpol...... 197 7.3 Risk Assessment and Disaster Management Plan ...... 198 7.4 Public Consultation ...... 198 7.5 Bathymetry Study ...... 198 7.6 Representations from Conservation Action Trust (NGO) ...... 199 Chapter 8. Project Benefits ...... 205 8.1 Improvement in the Physical Infrastructure ...... 205 8.2 Improvement in the Social Infrastructure ...... 205 8.3 Employment & Other Benefits ...... 205 8.4 Financial Benefits of the Projects ...... 206 8.5 Corporate Social Responsibility (CSR) Of DPT ...... 207

Mantec Consultants Pvt. Ltd. Page iv Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Chapter 9. Environmental Cost Benefit Analysis ...... 209 Chapter 10. Environmental Management Plan ...... 210 10.1 General ...... 210 10.2 Air Emissions Management ...... 211 10.2.1 Construction Phase ...... 211 10.2.2 Operation Phase ...... 211 10.3 Control of Noise ...... 214 10.3.1 Construction Phase ...... 214 10.3.2 Operation Phase ...... 214 10.4 Water Environment ...... 215 10.4.1 Construction Phase ...... 215 10.4.2 Operation Phase ...... 216 10.5 Waste Management ...... 218 10.5.1 General Waste Reception Facilities ...... 219 10.5.2 Ship Wastes Management ...... 219 10.6 Dredged Materials Management ...... 220 10.6.1 Dredge Planning Activities ...... 220 10.6.2 Dredging ...... 221 10.6.3 Disposal of Dredged Material ...... 221 10.7 Hazardous Materials and Oil Management ...... 222 10.7.1 Spill Prevention ...... 222 10.7.2 Spill Control Planning ...... 223 10.7.3 Goods Handling ...... 223 10.8 Biodiversity Management Plan ...... 224 10.9 Greenbelt Development ...... 225 10.10 Mangrove Plantation ...... 234 10.10.1 Mangrove Plantation Plan ...... 235 10.11 Energy Conservation Measures ...... 235 10.11.1 Energy Conservation during Construction Phase ...... 235 10.11.2 Energy Conservation during Operation Phase ...... 236 10.12 Environment Management Cell ...... 236 10.13 Budgetary Provisions for EMP ...... 237 Chapter 11. Summary and Conclusion ...... 242 11.1 General ...... 242

Mantec Consultants Pvt. Ltd. Page v Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

11.2 Location and Inception of Deendayal Port Trust ...... 242 11.2.1 Port Profile ...... 243 11.3 Utility requirement ...... 243 11.3.1 Water Requirement ...... 243 11.3.2 Power Requirement ...... 243 11.3.3 Manpower ...... 243 11.4 Regulatory framework and need of the EIA ...... 244 11.5 Baseline Data ...... 244 11.5.1 Air Environment ...... 244 11.5.2 Noise Environment ...... 245 11.5.3 Water Environment ...... 246 11.5.4 Land and Environment ...... 248 11.5.5 Biological Environment ...... 248 11.6 Impact Predictions ...... 249 11.7 Environment Management Plan ...... 250 11.8 Risk Assessment and Disaster Management Plan ...... 250 11.9 Conclusions ...... 250 Chapter 12. Disclosure of Consultants...... 252 12.1 Declaration by Experts contributing to the preparation EIA ...... 252 12.2 Declaration by the Head of the Accredited Consultant Organization ...... 254 Chapter 13. Status of Compliance of EC Conditions ...... 255

Mantec Consultants Pvt. Ltd. Page vi Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla List of Figures

Figure 1: Location Map of Project Site (SoI Toposheet) ...... 4 Figure 2: Location Map of Project Site (Satellite Image) ...... 5 Figure 3: Combined Capacity of All Facilities at Kandla Port for Handling Liquid Cargo ...... 29 Figure 4: The Liquid Cargo Handled at Kandla Port ...... 30 Figure 5: Cargo Traffic & Capacity of Last Five Years Based on CGAR ...... 32 Figure 6: Location of Container Terminal at Tuna off Terka on BOT basis ...... 35 Figure 7: Location of Providing Railway Line from NH‐8A to Tuna Port‐ 11.00 km ...... 36 Figure 8; Construction of port craft jetty & shifting of SNA section at Kandla Port ..... 37 Figure 9: Project Layout ...... 38 Figure 10: Windrose diagram ...... 50 Figure 11: Air Monitoring Location ...... 52 Figure 12: PM10 graph of DPT Stage‐1( for 3 Integarted Facilities) ...... 60 Figure 13: PM2.5 graph of DPT Stage-1( for 3 Integarted Facilities) ...... 61 Figure 14: SO2 graph of DPT Stage‐1( for 3 Integarted Facilities) ...... 61 Figure 15: NO2 graph of DPT Stage‐1( for 3 Integarted Facilities) ...... 62 Figure 16: CO graph of DPT Stage‐1( for 3 Integarted Facilities) ...... 62 Figure 17 : Air Quality Monitoring Photographs ...... 63 Figure 18: Noise Level Monitoring Stations in the Study Area ...... 66 Figure 19: Noise Quality Monitoring Photographs ...... 68 Figure 20: Surface & Ground Water Sampling Location ...... 70 Figure 21: Land Use/ Land Cover of the study area at Kandla ...... 80 Figure 22: Soil Sampling Locations at Kandla ...... 83 Figure 23: Graphical Representation of the Flora of the Area ...... 91 Figure 24: Phytoplankton, Zooplankton and benthic meio fauna sampling locations at Kandla ...... 103 Figure 25: Benthos Macro Fauna Sampling Locations at Kandla ...... 106 Figure 26: Map of National Parks and Wildlife Sanctuaries in Gujarat ...... 108 Figure 27: FCC image of LANDSAT 1999 ...... 111 Figure 28: FCC image of LANDSAT 2005 ...... 112 Figure 29: FCC image of LISS‐III 2011 ...... 113 Figure 30: India’s Coastal Districts ...... 117 Figure 31: Gujarat Index Map for Shoreline Studies ...... 121 Figure 32: Status of shoreline change at Tuna port in Gujarat ...... 122 Figure 33: Status of shoreline change at Kandla port in Gujarat ...... 123 Figure 34: PM10 Emission at Container terminal ...... 149 Figure 35: PM2.5 Emission at Container terminal ...... 150 Figure 36: NOxEmission at Container terminal ...... 151 Figure 37: SO2 Emission at Container terminal ...... 152 Figure 38: PM10 Emission at SNA jetty ...... 153 Figure 39 :PM2.5 Emission at SNA jetty ...... 154 Figure 40: NO2 Emission at SNA jetty ...... 155 Figure 41: SO2 Emission at SNA jetty ...... 156

Mantec Consultants Pvt. Ltd. Page vii Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Figure 42 : Water Balance Diagram ...... 217 Figure 43: Organizational structure for implementing the EMP ...... 238

Mantec Consultants Pvt. Ltd. Page viii Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla List of Tables

Table 1: Traffic at a Glance (In Lakh Tonnes) ...... 33 Table 2: Existing available Storages Facilities in Dry Cargo Jetty Area...... 40 Table 3: Climatological Table of Kandla Observatory (2014) ...... 46 Table 4: Instruments, Parameters and Frequency of Meteorological Monitoring at Site ..... 47 Table 5: Temperature Data Recorded at Site ...... 48 Table 6: Ambient Air Quality Monitoring Locations ...... 51 Table 7: Techniques Used for Ambient Air Quality Monitoring ...... 54 Table 8: National Ambient Air Quality Standards ...... 54 Table 9: Ambient Air Quality at A-1...... 56 Table 10: Ambient Air Quality at A‐2 ...... 56 Table 11: Ambient Air Quality at A‐3 ...... 56 Table 12: Ambient Air Quality at A‐4 ...... 57 Table 13: Ambient Air Quality at A-5 ...... 57 Table 14: Ambient Air Quality at A‐6 ...... 58 Table 15: Ambient Air Quality at A‐7 ...... 58 Table 16: Ambient Air Quality at A‐8 ...... 59 Table 17: Noise Level Monitoring Stations in the Study Area ...... 65 Table 18: Ambient Noise Quality Standards in respect of Noise ...... 66 Table 19: Noise Quality Results of the Study Area (01 Feb 2018 to 28 Feb 2018) ...... 67 Table 20: Location of Water Quality Stations ...... 68 Table 21: Water Quality data (1 Feb 2018 to 28 Feb 2018) ...... 73 Table 22: Land Use Classification based on Satellite Image ...... 79 Table 23: Soil Sampling Location of the Study Area ...... 82 Table 24: Physical Characteristics of the Soil in the Study Area ...... 84 Table 25: Result of Analysis of Soil in the Study Area (01 Feb 2018 to 28 Feb 2018) ...... 86 Table 26: Analysis of the Flora of the Study Area ...... 91 Table 27: Flora Recorded From the Study Area ...... 92 Table 28: Mammals in the study area of Deendayal Port Trust Projects ...... 97 Table 29: ‐ Amphibians & Reptiles of the Area ...... 98 Table 30: Molluscs, Crustaceans and Annelida of the area ...... 98 Table 31: List of Common Fish Species Found in the Area ...... 99 Table 32: List of Domestic Fauna in the Study Area ...... 100 Table 33: Co‐Ordinates of Sampling Locations of Phytoplankton, Zooplankton and Benthic Meio Fauna ...... 101 Table 34: Phytoplankton abundance and density recorded at various sampling Sites ...... 102 Table 35: Abundance of zooplankton density recorded at various sampling sites (Unit: no./l) ...... 104 Table 36: Density of Benthic Meio Fauna at Various Sampling Sites ...... 105 Table 37: Co‐Ordinates of Sampling Locations of Benthic Macro Fauna ...... 105 Table 38: Density of Benthic Macro Fauna (Unit: No/M2) ...... 105 Table 39: Distance and direction of the wildlife sanctuary from proposed project site ...... 107

Mantec Consultants Pvt. Ltd. Page ix Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Table 40: Details of Time Series Satellite Data Analysis for Mangroves ...... 110 Table 41: Erosion Characteristics of Gujarat Coast ...... 118 Table 42: District wise Erosion categories in km ...... 118 Table 43: Areas under High Erosion Category ...... 119 Table 44: Areas under Medium Erosion Category...... 119 Table 45: Metal Content in the Samples Collected From the Sites ...... 124 Table 46 : Sub‐district wise Village/Town in the Study Area ...... 131 Table 47: Geographical Area of the Identified Habitations ...... 132 Table 48: Land Use Pattern in the Identified Villages of the Study Area ...... 132 Table 49: Village wise Population & Sex Ratio in the Study Area ...... 133 Table 50: Town Population & Sex Ratio in the Study Area ...... 133 Table 51: SC Population distribution in the Village areas of the Study Area ...... 134 Table 52: ST Population Distribution in the Village areas of the Study Area ...... 134 Table 53: SC Population break-up in the Town area of the Study Area...... 135 Table 54: ST Population break-up in the Town areas of the Study Area ...... 135 Table 55: Distribution of Literates in the Study Area...... 136 Table 56: Working Population in the Study Area ...... 137 Table 57: Distribution of Main Workers in the Study Area ...... 138 Table 58: Cultivators break-up in the Study Area ...... 138 Table 59: Agricultural Labours’ break-up in the Study Area ...... 139 Table 60: Household Industrial Workers break-up in the Study Area...... 140 Table 61: Other Workers break-up in the Study Area ...... 140 Table 62: Marginal Workers break-up in the Study Area ...... 141 Table 63: Non-Workers break-up in the Study Area ...... 142 Table 64: Basic Amenities Available in the Study Area ...... 142 Table 65: Estimated Noise Levels For the Piling and Dredging Operations ...... 159 Table 66: Consolidated list of Impacts with Remedial measures ...... 169 Table 67: Summary of Mitigation Measures ...... 177 Table 68: Post Study Environmental Monitoring Programme ...... 188 Table 69: Expenditure on CSR Scheme: 2011-12 to 2017--2018...... 207 Table 70: Works Undertaken by DPT under the CSR Scheme: 2016‐17 ...... 207 Table 71: CSR works recommended by CSR Committee in its meeting held on 17.02.2018 for the year of 2017‐18 as under (Till Board approval is pending) ...... 208 Table 72: Trees proposed for Greenbelt development ...... 227 Table 73: Small Trees proposed for Green belt Development ...... 229 Table 74: Shrub proposed for Green belt Development ...... 229 Table 75: Medicinal uses of some plants proposed for Green belt Development ...... 230 Table 76: Expenditure on Greenbelt Development Plan ...... 233 Table 77: Cost of EMP (Environmental Management Plan) ...... 237 Table 78: Environmental Management Plan ...... 239

Mantec Consultants Pvt. Ltd. Page x Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

List of Annexure

Annexure I Approved ToR dt. 06/06/2017 Annexure II Topography Survey of Study Area Annexure III Traffic handled at Deendayal Port Annexure IV CRZ Recommendations alongwith HTL/LTL Map Annexure V Bathymetry Survey Maps Annexure VI Wave Tranquility Study Annexure VII Disaster Management Plan Annexure VIII Greenbelt Management Plan Annexure IX Mangrove Plantation Plan Annexure X Certificate of Compliance of Conditions Stipulated in Environmental Clearance obtained for earlier projects alongwith action plan Annexure XI Study on present status, Conservation and Management Plan for mangroves of Deendayal Port Region prepared by GUIDE. Annexure XII Oil Spill Contingency Plan Annexure XIII OISD Norms Annexure XIV Proceedings of Public Hearing with Action Plan Annexure XV Certificates of QCI‐NABET Accreditation, MoEF&CC Recognition and NABL Recognition of Mantec and its lab. Annexure XVI Land use maps of the project site Annexure XVII Old Baseline data (Primary & Secondary) dated 2012‐13 Annexure-XVIII Marine Biodiversity Impact Assessment & Management Plan by NIO Annexure-XIX Status of Show Cause Notice

Mantec Consultants Pvt. Ltd. Page xi Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Chapter 1. Introduction

1.1 Purpose of the Report

M/s. Deendayal Port Trust has proposed three (03) projects in Kandla Port area at Kandla. The objective of the study is to assess the environmental impacts of the proposed projects. The type and intensity of impacts on the various components of the environment vary depending on the nature and size of the project as well as its geographical locations. The net impacts from individual projects can be identified through Environmental Impact Assessment studies of various components of environment such as noise, air, water, land, biological and socioeconomic. EIA studies form the basis for preparing an Environmental Management Plan (EMP) to conserve the environment of the area. The ToR issued for three integrated facilities of Deendayal Port Trust at Kandla by MoEF, New Delhi is enclosed as Annexure-I.

The proposed projects also attract CRZ Notification on Coastal Regulation Zone (CRZ) 2011, which provides Coastal Regulation Zone (CRZ) and regulating activities i.e. imposing restrictions on industries, operations and processes in the CRZ area. CRZ is defined as all coastal stretches of seas, bays, estuaries, creeks, rivers and back waters which are influenced by tidal action (in the land ward side) up to 500 m from the High Tide Line (HTL) and the land between the High Tide Line and Low Tide Line (LTL). The HTL means the line on the land up to, which the highest water line reaches during spring tide. As per CRZ notification it is necessary to obtain CRZ clearance from Ministry of Environment and Forest, New Delhi, prior to any developmental activity in CRZ area. Deendayal Port Trust had been appointed Anna University (MoEF authorized agency for HTL/LTL demarcation) for the preparation of CRZ map as per the requirement of CRZ notification, 2011 for obtaining CRZ clearance and a field survey was carried out at project site during pre‐monsson seasons (One Month) for collection of primary data and physical information. Secondary information with regard to the demographic profile, habitation, climatic conditions, water resources, land use pattern, cropping pattern, biological indicators, historical importance, industrial development and other environmentally sensitive parameters around the Kandla port where modification is

Mantec Consultants Pvt. Ltd. Page 1 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla proposed was also collected for authentication of primary data. The information collected was validated at site. For baseline data generation a study area of 10 km radius around the proposed project site was considered. The EIA report based on one month baseline data has been prepared, which covers all individual components of environment and are described in detail in the subsequent chapters.

1.2 Identification of Project and Project Proponent Kandla Port is the busiest port of India and serves as the gateway for the trade generating from/to the entire Northern India. In the terms of cargo handling, Kandla Port has achieved the first position among all the Major Ports of India, in most of the years in last decade. To enhance the cargo handling capacity and to handle bigger size vessels, Kandla Port has long been focusing on various measures like adding the new facilities, strengthening the existing facilities, etc.

1.3 Brief Description of Nature, Size, Location of the Projects and Importance to Country, Region Kandla Port is situated at Latitude 23º 01’ N and Longitude 70º 13’ E on the shores of the Kandla Creek. It is in the district of Kutch and is located on the west bank of Kandla creek which runs into the Gulf of Kutch at a distance of 90 nautical miles from the Arabian Sea. The location of project site is depicted in Figure-1&2, given below. The width of the channel varies from 200 meters to 1,000 meters. The contour depth along the shipping channel is around 10 meters. The total length of the Kandla Port approach Channel is around 23 kms. Navigation is permitted during the day and night according to the draft of the ship. Pilots board the ships at Outer tuna buoy (OTB) at least two hours before high tide. Dredging is undertaken throughout the year. Ships with 13 meters draft can also be brought in during the tidal window.

The port is operational throughout the year as it is an all weather port. There are no adverse wave effects as it is a sheltered port situated in a creek. There is scanty rainfall in this region which is one of the main reasons that the port can handle food grains. The port is well connected with the hinterland by broad gauge railway system and National Highway No. 8‐A. The port can handle dry bulk, break bulk, liquid bulk and container

Mantec Consultants Pvt. Ltd. Page 2 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla cargo. Kandla is the closest major port to the Middle East and Europe. Kandla is also en‐ route port for ships calling at Karachi, Pakistan’s only major port handling its seaborne cargo.

Mantec Consultants Pvt. Ltd. Page 3 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Figure 1: Location Map of Project Site (SoI Toposheet)

Mantec Consultants Pvt. Ltd. Page 4 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Figure 2: Location Map of Project Site (Satellite Image)

Mantec Consultants Pvt. Ltd. Page 5 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

1.4 Scope of Study

The scope of the study is to conduct the EIA study covering all the disciplines of environment and field monitoring in relevant disciplines over one month of pre‐ monsoon seasons (excluding monsoon months). The EIA report has been prepared as per ToR issued by MoEF, GoI, New Delhi.

This has been accomplished by carrying out a field survey and secondary data collection, based on which the mitigation measures have been suggested and the EIA report prepared. The EIA study of proposed project has been carried out as per the following methodology.

 Collection and review of information pertaining to existing environmental conditions in the areas, supported by field investigation in addition to consultation with Deendayal Port Trust and experts.

 Evaluation of all potential, significant, adverse, environmental and socio‐economic impacts associated with the proposed project.

 Identification and planning of measures to mitigate potential significant adverse impacts.

 Preparation of detailed environment management plan to prevent, mitigate or compensate potential significant adverse impact identified.

TOR COMPLIANCE (MoEF&CC File No. 10-9/2017-IA.III as per Specific ToR dated 06/06/2017)

Sl. No. Standard ToR Points Compliance 1. Reasons for selecting the site with The proposed projects are well within the details of alternate sites existing Deendayal Port area. These projects examined/rejected/selected on merit are proposed to further enhance the capacity

Mantec Consultants Pvt. Ltd. Page 6 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla with comparative statement and of port & its allied facilities. reason/basis for selection. The The detailed analysis and suitability of the examination should justify site location for these projects has been given in suitability in terms of environmental Chapter-5 of the EIA report. angle, resources sustainability associated with selected site as compared to rejected sites. The analysis should include parameters considered along with weightage criteria for short‐ listing selected site. 2. Details of the land use break‐up for the The land use of the project area is industrial, as proposed project. Details of land use proposed projects are well within the Kandla around 10 km radius of the project site. port area. The details of land use of the study Examine and submit detail of land use area i.e. 10 km radius is given in Section 3.4.2 around 10 km radius of the project site of Chapter 3, Map of the project area is given and map of the project area and 10 km at Figure No-21. There is no sensitive location area from boundary of the as per wildlife (Protection) Act, 1972/critically proposed/existing project area, polluted areas as identified by the CPCB from delineating project areas notified under time to time/notified eco‐sensitive areas/ the wild life (Protection) Act, interstate boundaries and international 1972/critically polluted areas as boundaries. identified by the CPCB from time to Land use maps of 10 km radius from the time/notified eco‐sensitive areas/ project site are attached as Annexure-XVI. interstate boundaries and international boundaries. Analysis should be made based on latest satellite imagery for land use with raw images. 3. Submit the present land use and There is no change in the land use of the permission required for any conversion proposed projects. The forest land or such as forest, agriculture etc. land agricultural land is not involved hence; no

Mantec Consultants Pvt. Ltd. Page 7 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla acquisition status, rehabilitation of conversion of the land use is involved. communities/ villages and present status of such activities. 4. Examine and submit the water bodies The proposed projects are located along the including the seasonal ones within the Kandla creek area. Many other secondary & corridor of impacts along with their tertiary creeks are present in the study area status, volumetric capacity, and quality arising from the Kandla creek. Khori Creek and likely impacts on them due to the Nakti Creek are one of them. The impact of the project. projects on these water bodies are given in Chapter-4, Anticipated Environmental Impact under water environment section 4.5 of Chapter-4. 5. Submit a copy of the contour plan with A detailed Topography of the study area is slopes, drainage pattern of the site and attached in Annexure-II. surrounding area. 6. Submit the details of terrain, level with The terrain is flat with elevation from sea level respect to MSL, filling required, source to up to 3 meter MSL. No filing is required for of filling materials and transportation these projects. details etc. 7. Examine road/rail connectivity to the Project site is well connected to rail & road project site and impact on the existing network. NH 8A connects Port area to the rest traffic network due to the proposed of the country. The cargo from the port area is project/activities. A detailed traffic and transported through it and also by the railway transportation study should be made for network. The additional cargo traffic will be existing and projected passenger and managed through the proposed railway line. cargo traffic. Details of cargo handled at the Kandla port is given in Section 2.3 of Chapter 2 and commodity wise traffic is attached as Annexure-III.

Mantec Consultants Pvt. Ltd. Page 8 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla 8. Submit details regarding R&R involved No R&R is envisaged as the project activities in the project. are within the existing land of Deendayal Port Trust. 9. Submit a copy of layout superimposed Copy of layout superimposed on the HTL/LTL on the HTL/LTL map demarcated by an map demarcated by Anna University, an authorized agency on 1:4000 scales authorized agency of MoEF&CC on 1:4000 along with the recommendation of the scales along with the recommendation of the SCZMA. SCZMA is attached as Annexure-IV. 10. Submit the status of shore line change at The shoreline study is given in Section - 3.7 of the project site. Chapter-3. The Shoreline maps are given in Figure-30 to Figure-32. 11. Details of the layout plan including Capital dredging envisaged is 13,56,000 m3. details of channel, breakwaters, Disposal of dredged material will be at at dredging, disposal and reclamation. Tuna‐Tekra location (Latitude - 220 53’ 18’’ & Longitude - 700 06’ 20’’). Disposal and reclamation will be done as per MARPOL (Section 10.6 of Chapter-10). 12. Details of handling of each cargo, Details of cargo handled at the Deendayal port storage, transport along with spillage is given in Section 2.4 in Chapter 2 and control, dust preventive measures. In commodity wise traffic is attached as case of coal, mineral cargo, details of Annexure-III. Coal & mineral cargo will be storage and closed conveyance, dust stored in back up areas in closed silos. Water suppression and prevention filters. sprinklers shall be used for dust suppression. Dust preventive measures are given in Chapter-10 under Air Emission Management. 13. Submit the details of fishing activity and There is no fishing in Kandla Port area, being likely impacts on the fishing activity due no fishing zone. Details are given in Section to the project. Specific study on effects of 4.6 of chapter 4. Impact of construction construction activity and pile driving on activities on marine life has been given at para marine life. 4.7 of chapter 4.

Mantec Consultants Pvt. Ltd. Page 9 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla 14. Details of oil spill contingency plan. Details of oil spill contingency plan have been given at Chapter-7 in additional studies of the EIA report and attached as Annexure-XII. 15. Details of bathymetry study. A brief of the Bathymetry study is given in Section 7.5 of Chapter-7. Details of the study are attached as Annexure-V. 16. Details of ship tranquility study. Details of ship tranquility study have been attached as Annexure- VI. 17. Examine the details of water Total water requirement of the projects is 5.0 requirement, impact on competitive KLD. user, treatment details, use of treated The impact on water environment due to the waste water. Prepare a water balance construction & operation of the projects are chart. given in Chapter 4 of the EIA report. Water balance chart provided is given in Figure 42 for the proposed activities. 18. Details of rainwater harvesting and Deendayal Port Trust is already having the utilization of rain water. rain water harvesting pond in Gopalpuri colony. However, there is no rain water harvesting system proposed in the proposed integrated facilities as there is scanty rain in the Kutch area (Section 10.4.2.2 of Chapter 10).

19. Examine details of Solid waste The details of Solid waste generation generation treatment and its disposal. treatment and its disposal is given at Section 10.5 of Chapter-10. 20. Details of desalination plant and the From the decades, DPT is getting sufficient study for outfall and intake. water from Gujarat Water Supply and Sewerage Board (GWSSB). The important source of water is the 14.5 Million m3 capacity reservoir of Tapar dam, besides a number of

Mantec Consultants Pvt. Ltd. Page 10 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla deep tube wells. Water is distributed to Kandla area from high service reservoir near Bharuch through 18” dis. CI main. Hence, there is no need of desalination plant in the Kandla Port area or in the near future. 21. Examine baseline environmental quality The baseline data of the project area is given in along with projected incremental load Chapter 3 & its impact due to incremental due to the proposed project/activities. load of these projects are given in Chapter-4. 22. The air quality monitoring should be The air quality monitoring at 8 locations were carried out according to the notification carried out for one month w.e.f. 1 Feb 2018 to issued on 16th November, 2009. 28 Feb 2018 (non‐monsoon season) according to the latest notification of 2009 and same is given in Chapter-3. 23. Examine separately the details for The details of Environmental management construction and operation phases both Plan & Environmental Monitoring are given for Environmental Management Plan separately for construction & operation phases and Environmental Monitoring Plan with cost & parameters in Chapter 10 & with cost and parameters. Chapter 6 respectively. 24. Submit details of a comprehensive Risk Risk assessment & Disaster Management Plan Assessment and Disaster Management has been prepared by M/s Telos Consultancy Plan including emergency evacuation Services (P) Ltd., Mumbai and the same is during natural and man‐made disasters. attached as Annexure-VII. 25. Submit details of the trees to be cut No tree cutting is involved in this project. Due including their species and whether it care shall be taken to reduce impact on also involves any protected or mangroves of the area. Mangrove plantation is endangered species. Measures taken to being done by DPT in phased manner. Details reduce the number of the trees to be of Mangrove plantation is given in EIA report removed should be explained in detail. at Section 10.10/Chapter 10 under Submit the details of compensatory mangrove plantation Plan. Land clearance will plantation. Explore the possibilities of only remove herbs and shrubs of common

Mantec Consultants Pvt. Ltd. Page 11 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla relocating the existing trees. species. 26. Examine the details of afforestation The plantation as Green belt will be developed measures indicating land and financial as per the layout attached as Annexure-VIII. outlay. Landscape plan, green belts and Native tree species as per CPCB guidelines will open spaces may be described. A thick be planted. Detailed greenbelt management green belt should be planned all around plan is given in Chapter 10 at Section 10.9 the nearest settlement to mitigate noise Mangrove plantation has been done at Satsida and vibrations. The identification of bed, opposite to Kandla Port. Layout of species/ plants should be made based on Mangrove plantation is attached as Annexure- the botanical studies. IX. 27. The Public Hearing should be conducted The Committee exempted the proposal from for the project in accordance with public hearing as per para 7 (ii) of EIA provisions of Environmental Impact Notification, 2006 as public hearing has Assessment Notification, 2006 and the already been conducted by Gujarat Pollution issues raised by the public should be Control Board on 18.12.2013. addressed in the Environmental Management Plan. The Public Hearing should be conducted based on the ToR letter issued by the Ministry and not on the basis of Minutes of the Meeting available on the web‐site. 28. A detailed draft EIA/EMP report should The EIA/ EMP report has been prepared in be prepared in accordance with the accordance with Approved ToR dated above, additional TOR and should be 06/06/2017. (Annexure-I) submitted to the Ministry in accordance with the Notification. 29. Details of litigation pending against the There is no litigation pending against the project, if any, with direction /order project. passed by any Court of Law against the Project should be given.

Mantec Consultants Pvt. Ltd. Page 12 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla 30. The cost of the Project (capital cost and Total cost for proposed project is Rs. 3214.17 recurring cost) as well as the cost Crore and capital cost towards EMP is 17.62 towards implementation of EMP should Crore and recurring cost is Rs 0.81 be clearly spelt out. Crore/Year. Details are given in Chapter‐10 of the EIA Report. 31. Any further clarification on carrying out The EIA report is prepared as per Standard the above studies including anticipated ToR of MoEFCC on April 2015 and additional impacts due to the project and ToR recommended by EAC in its minutes of mitigative measures, project proponent meeting dt. 01.05.2017, 15.05.2017, can refer to the model ToR available on 25.01.2018 and approved ToR Prescribed by Ministry website EAC on 06/06/2017. http://moef.nic.in/Manual/Portand harbour

Specific ToR prescribed by the committee dated 06.06.2017 i Importance and benefits of the project The importance & benefits of the projects are given at Chapter-8 of the EIA report. ii The data collection and impact Data collection & impact assessment has been assessment shall be as per standards done as per standard survey method of CPCB survey methods. & IS. Details are given in sub section 3.1, 3.2, 3.3, 3.4, 3.5, 3.7 and 3.8 of Chapter-3 and Details of the impact assessment are given in Chapter-4 of the EIA Report. iii All complaints or representations on the MoEF&CC has received the representations project as available with the MoEF&CC, from Conservation Action Trust on the Deendayal Port Trust or with the 30/04/2017 during the process of grant of Local Administration (District Manager) ToR. including representation received from Nature Conservation Trust shall be These representations regards to this project addressed to in the EIA with a specific have been complied & details are given in

Mantec Consultants Pvt. Ltd. Page 13 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla action plan where required. Section-7.6 of Chapter-7 of the EIA Report. iv A para‐wise response and action plan to The Committee exempted the proposal from the recommendations as given in the public hearing as per para 7 (ii) of EIA proceedings of public hearing shall be Notification, 2006 as public hearing has included in the EIA report. already been conducted by Gujarat Pollution Control Board on 18.12.2013. Para‐wise response and action plan is given along with proceeding of public hearing in Annexure-XIV. v The EIA report will also provide a one One month base line data have been collected month additional primary base line data from 01 Feb 2018 to 28 Feb 2018 & it has with secondary data and compare this given in Chapter-3 of the EIA Report and its with the data as may have been collected comparison with earlier collected data (2012- earlier and arrive at impacts 13) is given in sub section 3.1.3, 3.2.7, 3.3.4 & accordingly. 3.4.4 of Chapter-3 resepectively. Earlier collected primary & secondary data (2012-13) are attached as Annexure-XVII. vi A separate chapter on status of DPT is regularly submitting the half yearly compliance of Environmental Conditions compliance reports to the Regional offices of granted by State/Centre to be provided. the MoEF&CC; GoI and Certified compliance As per circular dated 30th May, 2012 report from RO Bhopal is attached as issued by MoEF, a certified report by Annexure-X. Regional Office, MoEF&CC on status of Status of compliance of Environmental compliance of conditions on existing Conditions granted by State/Centre on existing unit to be provided in EIA‐EMP report. unit is given in Chapter-13 of the EIA Report. vii Submit a copy of layout superimposed Copy of layout superimposed on the HTL/LTL on the HTL/LTL map demarcated by an map demarcated by Anna University, an authorized agency on 1:4000 scale. authorized agency of MoEF&CC on 1:4000 scales along with the recommendation of the SCZMA is attached as Annexure-IV.

Mantec Consultants Pvt. Ltd. Page 14 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla viii Recommendation of the SCZMA Recommendation of the SCZMA, Gandhinager for these 3 activities is attached as Annexure– IV. ix Status of stage ‐1 forest clearance for the There is no Forest land involved hence; Stage ‐ involvement of forest land if applicable 1 forest clearance is not required. x Various Ports facilities with capacities Various ports facility with capacities for the for proposed project existing and proposed projects of the DPT is given in Section 2.6 to Section 2.12 of Chapter 2. xi List of cargo to be handled along with Details of cargo handed at the Deendayal port mode of transportation is given in Section 2.4 in Chapter 2 and commodity wise traffic is attached as Annexure-III. The cargo handled at port will be transported by train & road through NH‐8A. xii Layout plan of existing and proposed Layout of the existing & proposed port is port attached as Fig 9 in Chapter-02. xiii A detailed analysis of the physico‐ It has been given in sub section 3.3.2 & 3.4 of chemical and biotic components in the Chapter-3 of the EIA Report and Impact highly turbid waters round the project assessment is given in Chapter‐4 and site (as exhibited in the Google map management plan is given in Chapter-10 of shown during the presentation), the EIA Report. compare it with the physico‐ chemical and biotic components in the adjacent clearer (blue) waters both in terms of baseline and impact assessment and draw up a management plan. xiv Study the impact of dredging on the The impact of dredging on shoreline is given in shore line. Section-4.9 of Chapter-04. The Shoreline maps are given in Figure-30 to Figure-32. xv A detailed impact analysis of rock It has been given in Section 4.11 of Chapter-4

Mantec Consultants Pvt. Ltd. Page 15 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla dredging. of the EIA Report. xvi Action plan for disposal of dredged soil Capital dredging envisaged is 13,56,000 m3. and rocks Disposal of dredged material will be at at Tuna‐Tekra location (Latitude - 220 53’ 18’’ & Longitude - 700 06’ 20’’). Disposal and reclamation will be done as per MARPOL (Section 10.6 of Chapter-10). xvii Dispersion modelling for the dumping of It has been given in Sub Section 4.9 of the dredge materials shall be carried out. Chapter-4 of the EIA Report. The study report shall be incorporated. xviii Details of air pollution control measures Air pollution control measures and its to be taken as well as cost to be incurred. management are given in EIA report at Section 10.2 of Chapter no. 10. xix Total water consumption and its source. Total water consumption for these facilities is Wastewater management plan. 5.0 KLD. DPT is getting sufficient water from Gujarat Water Supply and Sewerage Board (GWSSB). The important source of Water is Reservoir near Bhachau through 18” pipeline of Gujarat Water Supply. Details of Waste water management are given in Section 10.4 and Section 10.5 of Chapter- 10. xx Details of Environmental Monitoring Details of environmental monitoring plan are Plan given in Chapter- 6 of EIA report. xxi The impacts of rock excavation and It has been given in Section 4.11 of Chapter-4 dredging separately. of the EIA Report. xxii The Marine biodiversity impact The Marine biodiversity study is given in assessment report and management Section 3.6 of Chapter 3. The impact plan through the National Institute of assessment report is given in Section 4.7 of Oceanography (NIOS) or any other Chapter 4. The management plan is given in

Mantec Consultants Pvt. Ltd. Page 16 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla institute of repute on marine, Section 10.8 to Section 10.10 of Chapter 10. brackish water and fresh water ecology The Marine biodiversity impact assessment and biodiversity. The report shall study report and management plan is prepared by the impact of the project activities on the NIO and it’s attached as Annexure-XVIII. intertidal biotopes, corals and coral communities, molluscs, sea grasses, sea weeds, subtidal habitats, fishes, other marine and aquatic micro, macro and mega flora and fauna including benthos, plankton, turtles, birds etc. as also the productivity. The data collection and impact assessment shall be as per standards survey methods xxiii Disaster Management Plan for the above Risk assessment & Disaster Management plan terminal for whole of the Kandla Port area has been prepared by M/s Telos Consultants, Mumbai and same is attached as Annexure-VII. xxiv Layout plan of existing and proposed Layout plan of existing and proposed Greenbelt. Greenbelt is attached as Annexure-VIII. xxv Status of court case pending against the There is no court case pending against the project proposed projects. xxvi A tabular chart with index for point wise Complied as above. compliance of above TORs.

1.5 Site Selection

Deendayal Port Trust proposes for development of the 3 activities at Kandla Port. The present site for the project is selected based on the following considerations:

 Availability of suitable and adequate land  Distance from reliable source of water

Mantec Consultants Pvt. Ltd. Page 17 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla  Road and railway access  Availability of infrastructural facilities  Environmental aspects

There are no sensitive area such as National Monuments, National Parks and Wildlife Sanctuaries, etc. within 15 km. from the project.

1.6 Methodology for Environment Impact Assessment

The study was organized to incorporate all relevant critical issues of the proposed project. It was undertaken to gather relevant information from available sources followed by conducting a field survey to the proposed project site and surrounding areas for environmental impact assessment and mitigation measures.

Various components of environment covered under the study are discussed below:

A. Air Environment Ambient air quality data within the study area were collected. Taking into account micro‐meteorological conditions, sampling sites were identified. Six ambient air quality monitoring stations were selected within the study area. The parameters selected for

ambient air quality status were PM10, PM2.5, Sulphur dioxide (SO2), Oxides of Nitrogen

(NOX) and Carbon monoxide (CO). All the parameters were monitored on 24 hour cycle. The meteorological parameters were also recorded by installing meteorological station at the plant site to determine the prevailing meteorological conditions during the study period.

B. Noise Environment Noise pollution may cause an adverse effect on human beings and associated environment including land, domestic animals, wild life and natural ecological systems. Hence, noise level surveys were carried out at site and at ten different locations within the study area of the project

C. Water Environment

Mantec Consultants Pvt. Ltd. Page 18 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla Information on water resources was collected. The critical parameters of prime importance were selected and analyzed under physical and chemical (inorganic and organic), aspects. Water samples were collected from different locations.

D. Land Environment Studies were undertaken to characterize and describe the land environment and various components in terms of land use and cropping patterns, physico‐chemical properties of soils etc. Soil samples were collected and analyzed.

E. Biological Environment The study was based on physical observation of the species in the project shadow area. The expert team visited the area and collected the data on flora and fauna, forestry and wildlife, as well as the avian scenario. Plant species for the development of green belt were also studied taking attenuation factors into consideration.

F. Marine Environment

The Studies were based on the site visits to characterize the marine environment and various components in terms of flora and fauna in the sea.

G. Socio-Economic Environment Compilation and collection of requisite type of data were undertaken, such as, demographic pattern, population density per km2 and economic status, educational facilities, medical facilities; Such data were collected from villages falling within a radius of 10 km.

1.7 Prevailing Marine Environment The prevailing marine environment has been evolved based on the following studies:

1.7.1 Tides

Tides in Gulf of Kutch have been assessed based on available information.

1.7.2 Current

Current speed at pre selected location has been measured over a period of 5 days.

Mantec Consultants Pvt. Ltd. Page 19 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla 1.7.3 Circulation

Circulation pattern in the study area have been evolved based on drogue trajectories

1.7.4 Water Quality

Water quality at selected stations has been assessed based on temperature, Total Suspended Solids (TSS), pH, salinity, Dissolved Oxygen (DO), Biochemical Oxygen Demand (BOD), phosphate, nitrate and ammonical nitrogen.

1.7.5 Sediment Quality

Sediment quality from selected areas has been analyzed for texture, Total Nitrogen, Total Phosphorus, CEC, Magnesium, pH and conductivity.

1.7.6 Flora and Fauna

The status of flora and fauna in the project area has been established based on: a) Generic diversity of phytoplanktons/Zooplanktons b) Forest and Vegetation c) Aquatic Vegetation and mangroves d) Terrestrial Fauna. e) Aquatic flora and fauna f) Fisheries

1.8 Marine Environment Impact Assessment The available information and the data generated through the present studies would be utilized to evolve the prevailing marine environmental status of Gulf of Kutch. With this as a baseline the impact during construction and operational phase on marine ecology would be assessed.

1.9 Likely Impact on Environment The proposed projects can directly or indirectly affect the environment, so the following dimensions have been studied in detail to analyze the resulting impact on environment as a whole:

Mantec Consultants Pvt. Ltd. Page 20 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla  Air Environment  Noise Environment  Water Environment  Land Environment  Biological Environment  Marine Environment  Socio Environment The assessment of above impacts have been carried out and discussed in the report. Mantec Consultants Pvt. Ltd. conducted the EIA study to assess impact of the proposed project on the environment. Accordingly, various safeguards have been suggested to ensure that the potential impacts are mitigated and conform to the prescribed limits.

1.10 Environmental Management Plan (EMP) Environmental Management Plan reviews the adequacy of various pollution control measures envisaged for proposed project in mitigating various environmental impacts identified. EMP has been prepared separately for construction and operation phases. It describes administrative aspects of ensuring that mitigatory measures are implemented and their effectiveness is monitored. It also includes green belt development plan.

Mantec Consultants Pvt. Ltd. Page 21 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Chapter 2. Project Description

2.1 General Port of Kandla is located at the west coast of India, is only Major port in the State of Gujarat, It was declared as a Major Port on April 8, 1955 by late Shri Lal Bahadur Shasthri the Minister of Transport. The Port is well connected by the network of rail and road and provides gate way port for export and import of traffic on northern Indian State of Jammu & Kashmir, Delhi, Punjab, Himachal Pradesh, Haryana, Rajasthan, Gujarat and parts of Madhya Pradesh, Uttaranchal and Uttar Pradesh.

Presently, Kandla Port is handling its dry cargo at its 15 berths and liquid cargo at its 6 oil jetties. These jetties collectively have a capacity of 54.31 MMTPA. Total of 92.5 MMTPA of cargo was handled at Kandla Port in the year 2014‐15 & 100.05 MMTPA during the financial year 2015‐16 & 105.00 MMTPA during the financial year 2016‐17.

The traffic handled by the port has shown a consistent increase and growing at a fast pace. The total traffic (both liquid and dry cargo) handled by the port has gone from 24.50 million tones in 1993‐94 to 105.00 million tones in 2016‐17. During 2016‐17, Kandla Port handled 105.00 MMTPA of cargo. Cargo traffic handled at Kandla mainly comprised Iron Scrap, Steel, Food Grains, Ore, Timber Logs, Salt Extractions, POL Products, Edible Oils, Chemicals of different varieties etc. Containerized cargo traffic through Kandla has also shown a significant growth during the last few years.

In order to ease pressure on the existing berths and increase the capacity of dry & liquid cargo handling, Deendayal Port Trust has proposed to develop new Container Terminal at Tuna off Terka on BOT basis and Construction of Port Craft Jetty & shifting of SNA Section at Deendayal Port Trust & Railway Line from NH‐8A to Tuna Port‐ 11.00 km and few other projects for strengthening and upgrading existing facilities at Kandla Port.

Mantec Consultants Pvt. Ltd. Page 22 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

2.2 Description of the Projects

2.2.1 Development of Container Terminal at Tuna off Terka on BOT basis

Facility planning was undertaken in the line with the market demand anticipated. Civil infrastructure and equipment are planned taking into account the latest developments in container ports worldwide. 1. Construction of 750m berth for three and a half year. 2. Construction of 1100m berth for five years (phase‐1: three and half years,phase‐2: one and half years).

For the project life of the option developed, financial viability is assessed on the yardsticks of NPV and IRR. The capital expenditure and operating and maintenance expenditures are estimated.

Quay location was identified along the 9.4 meter contour. The total quay length is 1,100 meters, which can accommodate a minimum of 3 vessels. The berth & apron area will be constructed on the identified 9.4 meter contour, whereas the stackyard, rail yard, office buildings and other infrastructure will be built on the land. The berth and the yard area will be connected by a trestle. Protection in the form of breakwater is required, in order to facilitate round the clock operation at berth.

Particulars Details Name of Project Setting up of a Container Terminal at Tuna Tekra, Kandla Port on BOT Basis under PPP Mode Location of the Project At about 2 Kms towards east of T‐shape Jetty (Dry Bulk Terminal) being developed by Adani Kandla Bulk Terminal Private Ltd. Optimal Capacity of Terminal 2.19 Million TEUs /Annum. Capital Cost of the Project Rs. 3097 Crs. Quay Length 1100 m length X 54 m width (including apron of 18 m) Vessel Nos. at a time 3 Nos. of 350 m LOA with 25 m of clearance on each side Vessel Size to be Catered 6,000 TEU Vessels at anytime Land Area to be Licensed out Appx. 84 Ha Water Area to be Licensed out Appx. 34 Ha Container Stacking Yard Area Appx. 41 Ha

Mantec Consultants Pvt. Ltd. Page 23 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Breakwaters Length of 1400 m, with 20 m of height (subject to confirmation by CWPRS) Length of Trestle of T-shape Jetty 1,450m with a width of 15m as RCC. Dredged Depth at Berth Pocket 14.85 & 14.85 CD and Turning Circle Dredged Depth in Access Channel 14.85 CD Dedicated Rail Line 7800 m X 5 m Dedicated Road 7800 m x 14 m Navigation / Access Channel Vessels up to 6,000 TEUs can be navigated at zero tide. Total Length of Navigational 15,020 m with depth of 14.85 m below CD (Alignment of Channel the Channel is subject to further studies) Clear width of Channel protected 184 m by Breakwaters Project time Schedule 60 Months (5 Years) Phase 1: 3.5 years (42 months); Phase 2: 1.5 years (18 months) Expected Commissioning date Phase I: by mid of 2018‐19 ; Phase II: by end of 2019‐20 Total Capital Cost of Project Rs. 3,097 Crores Investment by Concessionaire Wharf Structure Rs. 498 Crores Container Yard including Rail Yard Rs. 350 Crores Breakwater Rs. 280 Crores Rail Road Connectivity Rs. 95 Crores Equipments Rs. 1,029 Crores Other Infra Rs. 465 Crores Total Capital Cost of Rs. 2,717 Crores Concessionaire Investment by Concessioning Authority Capital Dredging Rs. 339 Crores+12% (as per TAMP) = Rs. 380 Crores

Total Capital Cost of Rs. 380 Crores Concessioning Authority

Mantec Consultants Pvt. Ltd. Page 24 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

2.2.2 Construction of Port Craft Jetty & shifting of SNA Section at Deendayal Port Trust

The pantoon jetty is located after the approach jetty on the left side on north.the overall size of the jetty is 114.95 x 12m.the dredge level at the face of this jetty is taken as 10.35m. It is proposed to have 17 rows of R.C.C Bored cast insitu 1000mm diatmeter piles in the longitiudinal directions and 3 rows in the transverse direction. In longitudinal direction the spacing is 7m. The spacing in the transverse direction is 5m with a cantilever projection of 1m on both sides. The piles are connected with main beam (1300 x1450mm) in the transverse direction and longitunal beam (600 x 850mm) in longitudinal direction. Secondary beam of 600 x 850mm is proposed in between longitunal beams to reduce the span of slabs. Pile muff shall be of size 1500 x 1500 x400mm. The slab thickness proposed is 250mm. The top level of the deck shall be +9.14m (including 100mm thick wearing coat).

2.2.3 Providing Railway Line from NH-8A to Tuna Port- 11.00 km

Kandla port has set up barge handling facility at Tuna (Outside Kandla Creek) for evac lighterage through barges. Further, the existing barge jetty with berth length 240 Mtrs. is being extended by 600 Mtrs (500 mtr through BOT project and 100 mtr through captive project) to augment the handling capacity of dry cargo. As a part of the future expansion plan, the Port has also under taken highly ambitious project for the “Development of Dry Bulk Terminal off Tekra near Tuna” at an estimated cost of Rs.1060 Crores and capacity of 14.112 Million Tons to handle dry cargo. It has become essential to connect the Tuna barge jetty with a broad gauge railway lines for faster and economic evacuation of cargo as well as to provide connectivity to the proposed three phases of berthing facility development off Tekra near tuna. And other projects as per current traffic projections by 2015‐16 and barge jetty by 2016‐ 17. There will be surgein handling of dry cargo by more than 30 MMTPA.

Mantec Consultants Pvt. Ltd. Page 25 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

NAME OF PROJECT PROVIDING RAILWAY LINES FROM NH 8A TO TUNA PORT Length of the Railway 11.00 KM Lines Type of Railway Lines Broad Gauge Line

Capital Cost Rs 94.00 Crore Project Phasing Single Phase Project

Source of funds Deendayal Port Trust from its internal resources Project time Schedule 24 months from the Date of Award of Work

Project IRR 14.40% Economic IRR 15.47%

2.3 Type of the Projects  Development of Container Terminal at Tuna off Terka on BOT basis

Deendayal Port Trust is the proponent (as the Port Authority) of the proposed project to be developed on BOT Basis through PPP mode. The proposed project has been identified as part of a series of capacity additions envisaged to augment the port capacity at various facility locations of Deendayal Port Trust. The project is a development of Container terminal to be developed through PPP model on BOT basis. The proposed container terminal is located on the 9.4m contour. The Quay and Apron areas will be constructed away from the land, in the deep waters so as to minimize the dredging requirement, forming the offshore section of the port. The backup land will be reclaimed to accommodate the onshore portion of port. The offshore portion will be connected to land side portion of the port with trestle. The land side portion includes stacking and evacuation infrastructure i.e. rail yard and gate and other utilities. There is no interlinked or interdependent project.

 Construction of Port Craft Jetty & shifting of SNA Section at Deendayal Port Trust

Mantec Consultants Pvt. Ltd. Page 26 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla This Pontoon jetty is located after the approach jetty on the left side on north. The overall size of this jetty is 114.95 x 12 m. the dredge level at face of this jetty is taken as ‐ 10.35m. It is proposed to have 17 rows of R.C.C Bored cast‐in‐situ 1000mm diameter piles in the longitiudinal directions and 3 rows in the transverse direction. In longitudinal direction the spacing is 7m. the spacing in the transverse direction is 5m with a cantilever projection of 1m on both sides. The piles are connected with main beams (1300 x 1450mm) in the transverse direction and longitunal beam (600 x 850mm) in longitudinal direction. Secondary beam of 600 x 850mm is proposed in between longitunal beams to reduce the span of slabs. Pile muff shall be of size 1500 x 1500 x 400mm. the slab thickness proposed is 250mm. The top level of the deck shall be +9.14m (including 100mm thick wearing coat).

 Providing Railway Line from NH-8A to Tuna Port- 11.00 km.

Provision of BG Railway line from NH 8A to Tuna Port. The same it is proposed to develop the facility at Tuna at Kandla Port to handle all kind of cargo. Commissioning of the proposed facility shall augment th cargo handling capacity of Kandla Port by 5.49 MMTPA. Hence this project should be seen as part of larger Kandla Port complex with interlinked operations.

2.4 Need of the Projects The country, especially northern India is heavily dependent on Deendayal Port Trust for its trade requirements due to its peculiar land locked location compared to many other regions of India which are comparatively quite nearer to the sea shore. Some state of central India like Madhya Pradesh is also dependent for its specific trade requirement on Deendayal Port Trust. Hence, considering the vast hinterland that is dependent on DPT for seaborne trade and currently prevailing traffic congestion at existing facilities of DPT,Capacity additions are of utmost importance at DPT for serving the economy of the influence region and in turn, the economy of the whole country in the best possible manner.

Mantec Consultants Pvt. Ltd. Page 27 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla 1) Container Terminal at Tuna Off-Tekra on BOT Basis

This container terminal will help reduce the burden on JNPT port as major share of container cargo in India is currently handled by JNPT. It will also save the Logistic Cost for the cargo of northern hinterland as offering the container handling services at Kandla Port would save the ocean freight from DPT to JNPT as well as the road/rail freight from JNPT to at least northern parts of Gujarat. This implies not only the cost but also the time saving.

2) Port Craft Jetty and SNA Section: It is submitted that since the starting of DPT, Signal and Navigational Aid (SNA) Section and Port Craft Parking jetty have been operated from the Bunder Basin Area. These structures were badly damaged in the cyclone of 1998 and the Earthquake of 2001. This necessitated re‐ location of SNA section and Port Craft Jetty from the safety point of view and also for smooth functioning of port operations. SNA jetty is primarily meant for parking of port crafts and no cargo handling activity is carried out at this facility

3) Providing Railway Line from NH 8A to Tuna Port

Deendayal Port Trust is one of the busiest ports of India and has been achieving first position in cargo handling almost all the times in last decade. To handle such a large quantum of cargo, the berth occupancy has always been around 90% for handling dry cargo as against ideal berth occupancy of 70%. Such high berth occupancy is in fact not desirable for essential maintenance of the berthing and allied structures. There is consistent increase in dry cargo handled at Port in the past. Dry cargo handled at Port has increased from around 8.30 Million Tons to around 46.28 Million Tons during last 13 years.

The projections show that the traffic is going to increase manifold in coming years at Kandla Port. To overcome all the above constraints, Kandla Port has chalked out an expansion plan. The Kandla Creek, near which the Port is situated, has a very limited draught. The vessels of bigger size i.e. Panamax and Post Panamax etc. carrying more than

Mantec Consultants Pvt. Ltd. Page 28 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla 75000 DWT cannot enter in to Kandla creek for direct handling of cargo at existing berths within Kandla creek.

As a part of the future expansion plan, the Port has also under taken highly ambitious project for the “Development of Dry Bulk Terminal off Tekra near Tuna” at an estimated cost of Rs. 1060 Crores and capacity of 14.112 Million Tons to handle dry cargo. It has become essential to connect the Tuna barge jetty with a broad gauge railway lines for faster and economic evacuation of cargo as well as to provide connectivity to the proposed three phases of berthing facility development off Tekra near Tuna.

Existing Liquid Cargo Handling Capacity

Presently, four numbers oil jetties are handling liquid cargo at Old Kandla Port. In future, proposed one number oil jetty shall be commissioned for handling liquid cargo at Old Kandla Port. The combined capacity of all facilities at Kandla Port for handling liquid cargo (excluding containers) is shown in the graph below:

Total Capacity: 11.39 MMTPA

Capacity in MMTPA

Year

Figure 3: Combined Capacity of All Facilities at Kandla Port for Handling Liquid Cargo

Mantec Consultants Pvt. Ltd. Page 29 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

As could be seen from the above figure, the existing capacity of all 4 nos oil jetty is 8 MMTPA which shall be augmented by 3.39 MMTPA in the year 2014‐15 after the commissioning of proposed new oil jetty which shall take the total liquid cargo handling capacity at Kandla Port to 11.39 MMTPA.

Trends in the past liquid cargo traffic The liquid cargo handled at Kandla Port is shown in the figure below. As could be seen, liquid cargo traffic at Kandla Port has increased at a compounded annual growth rate (CAGR) of 6.22 % over the last five years. This growth rate has been used for arriving at liquid cargo projections at Kandla Port over the next 30 years.

Traffic in MMTPA

Years

Figure 4: The Liquid Cargo Handled at Kandla Port

Demand and Supply With Future Projections: Container Terminal at Tuna off Tekra: Demand supply gap has been identified based on the traffic projection of Maritime Agenda announced by Ministry of Shipping and capacity additions envisaged by DPT. The comparison of traffic viz and gap analysis for the same has been presented below:

Mantec Consultants Pvt. Ltd. Page 30 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Year Traffic Projections Handling Capacity (As Traffic–Planned (As per Maritime per existing and Capacity Gap Analysis Agenda) in MMTPA proposed facilities at (in MMTPA) Kandla part in future) in MMTPA 2012‐13 31.65 16.38 15.27 2013‐14 37.82 22.88 14.94 2014‐15 43.26 45.87 ‐2.61 2015‐16 48.38 59.34 ‐10.96 2016‐17 55.52 59.34 ‐3.82 2017‐18 60.96 59.34 1.62 2018‐19 65.25 59.34 5.91 2019‐20 83.80 59.34 24.46

Port Craft Jetty & Shifting of SNA Section at Deendayal Port Trust: As there is huge amount of planned capacity additions, current positive demand supply gap turns negative by 2014‐15. However, the gap turns again positive quickly in two‐three years time and finally widens to a huge figure of over 24 MMTPA. The Liquid cargo handling facilities at Kandla have attracted 9.60 million tonnes liquid cargo for the year 2011‐12. The same has grown at CAGR of 6.70% during the last 10 Years. Considering this historical growth rate, the traffic projection for the liquid cargo at Kandla is provided below:

(In MMTPA)

Years FY FY FY FY FY FY FY FY FY FY FY 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Liquid Traffic at 10.31 11.00 11.73 12.52 13.36 14.25 15.21 16.23 17.31 18.47 19.71 Kandla

Railway Line from NH-8A to Tuna Port: Considering the existing capacity of 6 Oil Jetties i.e. 13 MMTPA and comparing the same with the projected traffic, demand supply gap seems to be developed by FY 2017. By FY 2020, the gap is expected to occur at 3.23 MMTPA.

Mantec Consultants Pvt. Ltd. Page 31 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla Demand‐Supply gap has been identified based on the traffic projection of Maritime Agenda announced by Ministry of Shipping and capacity additions envisaged by DPT. The comparison of traffic viz‐a‐viz port capacity and gap analysis for the same has been presented below: (In MMTPA) Year Traffic Projections Handling Capacity (As Traffic – Planned Capacity (As per Maritime per existing and Gap Analysis (in MMTPA) Agenda) in MMTPA proposed facilities at Kandla part in future) in MMTPA 2012‐13 31.65 16.38 15.27 2013‐14 37.82 22.88 14.94 2014‐15 43.26 45.87 ‐2.61 2015‐16 48.38 59.34 ‐10.96 2016‐17 55.52 59.34 ‐3.82 2017‐18 60.96 59.34 1.62 2018‐19 65.25 59.34 5.91 2019‐20 83.80 59.34 24.46

As there is huge amount of planned capacity additions, current positive demand supply gap turns negative by 2014‐15. However, the gap turns again positive quickly in two‐three years time and finally widens to a huge figure of almost 25 MMTPA.

Following figure highlights the gap between the projected liquid cargo traffic at Kandla Port and the available capacity. The projections are based on the CAGR of 6.22 % observed for the traffic of last five years.

Traffic & Capaity in MMTPA

Year Figure 5: Cargo Traffic & Capacity of Last Five Years Based on CGAR

Mantec Consultants Pvt. Ltd. Page 32 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla (Note: The total concession period is of 30 years including two years as construction period)

Above figure indicates the gap between the capacity and expected liquid cargo traffic in future years. This is the gap that needs to be plugged by development of new facilities in future for handling of liquid cargo (Refer Table 1 and Annexure-III).

Table 1: Traffic at a Glance (In Lakh Tonnes)

TRAFFIC AT A GLANCE(IN LAKH TONNES)

MONTHLY ANNUAL ANNUAL S.No. COMMODITY MAR. '16 MAR.'15 2015-16 2014-15 VARIATION 1.04.2016 FULL 1.04.2016 1.04.2015 IMPORTS (KANDLA) A LIQUID CARGO 9.31 6.89 103.35 76.72 26.62 1 POL 1.37 1 10.46 8.67 1.78 2 PHOS ACID & AMMONIA 1.42 1.32 18.56 12.89 5.67 3 EDIBLE OILS 3.95 2.97 49.07 34.58 14.49 4 OTHER LIQUIDS 2.56 1.59 25.27 20.59 4.68 B DRY CARGO 21.57 18.4 274.45 214.85 59.6 5 FERTILIZERS 1.26 3.72 43.62 38.47 5.15 6 RAW MAT. FOR FERT. 0 0.31 1.7 6.55 ‐4.86 7 IRON&STEEL(IN.SCRAP) 1.67 1.21 18.19 11.82 6.37 8 ORES 0.85 0.88 9.52 11.96 ‐2.43 9 CONTAINERISED CARGO 0.01 0 0.03 0 0.03 10 TIMBER LOGS 2.85 1.66 32.73 28.51 4.22 11 OTHER DRY CARGO 14.93 10.61 168.65 117.53 51.12 IMPORTS AT KANDLA 30.88 25.29 377.79 291.57 86.22 IMPORTS AT VADINAR 36.58 37.38 410.96 403.99 6.97 I TOTAL IMPORTS 67.46 62.67 788.75 695.56 93.2 EXPORTS (KANDLA) A LIQUID CARGO 3.73 0.79 16.81 12.6 4.21 1 POL 3.48 0.42 14.31 10.01 4.3 2 EDIBLE/CASTOR OIL 0.2 0.33 1.46 2.1 ‐0.64 3 OTHER LIQUIDS 0.05 0.05 1.04 0.49 0.55 B DRY CARGO 6.79 5.62 74.82 83.59 -8.77 4 FOODGRAINS 0.33 0.2 7.34 22.16 ‐14.83 5 ORES 0.87 0.11 3.38 4.63 ‐1.25 6 SALT 3.77 3.36 41.54 27.11 14.43

Mantec Consultants Pvt. Ltd. Page 33 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

7 CONTAINERISED CARGO 0.18 0 0.53 0 0.53 8 OIL EXTRACTIONS 0.42 1.52 7.17 17.67 ‐10.5 9 OTHER DRY CARGO 1.22 0.43 14.86 12.02 2.85 II EXPORTS AT KANDLA 10.51 6.41 91.63 96.19 -4.56 III EXPORTS VADINAR 11.44 12.49 117.37 131.41 -14.04 IV TOTAL EXPORTS 21.95 18.91 209 227.59 -18.6 V TOTAL AT KANDLA 41.4 31.7 469.42 387.76 81.66 SUMMARY 1 LIQUIDS AT KANDLA 13.04 7.68 120.16 89.32 30.84 DRY CARGO AT KANDLA( Inc. 2 Contrs.) 28.36 24.02 349.26 298.43 50.83 3 CONTAINERISED CARGO 0.18 0 0.56 0 0.56 4 TOTAL TEUs 0.01 0 0.03 0 0.03 5 LIQUIDS AT VADINAR 48.02 49.88 528.33 535.39 ‐7.07 6 TRANSHIPMENT 0 0 2.76 1.82 0.94 OVERALL (1+2+5+6) 89.42 81.58 1000.51 924.97 75.54

2.5 Locations of the Projects The layout plan of Deendayal Port Trust has been given as Fig 8. Location of the each facility is shown with help of maps:

Corner-cordinate of the Project Site: a. Development of Container Terminal at Tuna-Tekra on BOT Basis

Latitude: 22° 53' 36.834"N Longitude: 70° 7' 21.205"E

b. Providing Railway Line from NH-8A to Tuna Port- 11.00 km Latitude: 22° 59' 38.09"N Longitude: 70° 7' 38.114"E

c. Construction of port craft jetty & shifting of SNA section at Kandla Port Latitude: 20° 0’ 35.041"N

Mantec Consultants Pvt. Ltd. Page 34 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla Longitude: 70° 13' 20.984"E

Figure 6: Location of Container Terminal at Tuna off Terka on BOT basis

Mantec Consultants Pvt. Ltd. Page 35 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Figure 7: Location of Providing Railway Line from NH-8A to Tuna Port- 11.00 km

Mantec Consultants Pvt. Ltd. Page 36 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Figure 8; Construction of port craft jetty & shifting of SNA section at Kandla Port

Mantec Consultants Pvt. Ltd. Page 37 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Figure 9: Project Layout

Mantec Consultants Pvt. Ltd. Page 38 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

2.6 Port Logistics

Navigational Facilities  Safe Navigation of vessel round the clock.  Permissible draft of 13 mtrs  Slips of 240 mtrs LOA and 65000 DWT can be accommodated presently & Ships up to 255 mtrs. LOA and 100000 DWT is under specific conditions.  Safe protected and vast anchorage for Waiting and lighterage at Outer Harbour.  22 Lighted Navigational ‐ buoys as per IALA system In the navigational channel with solar lights.  Fully equipped rod the clock Signal Station.

2.7 Infrastructural Advantage at Kandla  Fourteen Dry Cargo berths s are available with Quay Length of 3150 mtrs.  Six Oil Jetties.  Total Custom Bonded port Area inside the custom fencing is about 330 hectares.  Two Cargo moorings in the inner Harbour area for stream handling.  Sufficient land and waterfront is available for expansion of the Port.

2.8 Chemical & Liquid Handling Complex  Total Storage Capacity 23.74 Lakh KL.  Private Sector Storage Terminals: 14.01 Lakh KL  Public sector & Co‐operative Undertakings: 9.73 Lakh KL  Loading arms for loading & unloading simultaneously.  Near Zero Waiting Period for Vessels.  Capacity utilization international levels ensuring Demurrage Free Handling  Excellent discharge rates & faster turnaround.  Lowest vessel related charges and wharfage Charges.  Suitable for A, B. C. LG. NH,EO Classes of Liquid & Chemicals,  Tanks for storage of all categories of Liquid Cargoes like Chemicals. LPG, Cryogenic Cargoes. Ammonia , Acids, Petroleum Products and Edible Oils etc.  Efficient handling minimum losses.  Sophisticated Pipelin Network (Including Stainless Steel Pipes).

Mantec Consultants Pvt. Ltd. Page 39 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla  Sufficient. Parking Space Inside & Outside the Storage Facilities.

2.9 Storage Facilities

Kandla Port offers an excellent and vast Dry Cargo Storage Facilities inside the Custom Bonded Area for storage of Import and Export cargoes, on very competitive rates. Existing available Storages Facilities in Dry Cargo Jetty Area are:

Table 2: Existing available Storages Facilities in Dry Cargo Jetty Area

Sr.No Description No Area (Sq.Mtrs.) Capacity in (Mtrs) 1 Warehouses 35 2.03 lacs 6.47 lacs 2 Open Storage Space 16.63 lacs 36 lacs A Within Custom Bounded 35 6.47 lacs MTs Area B Outside Custom Bounded 35 1.33 lacs MTs Area

2.10 Berthing Policy Highlights

Kandla Port practice trade‐friendly, output oriented and progressive berthing policy. The berthing policy categorizes vessels into Export Group, Import Group and Priority Groups. The highlights of the policy are as follows:

Salient Features

For Dry Cargo Berths (Bert 1 to 10)

In supersession of earlier circulars Issued in connection with the Berthing Policy from time to time, the following comprehensive Berthing Policy will come into force from 21‐09‐2015.

General Policy

Dry Cargo

The Dry Cargo berths are earmarked for the vessels of the following groups as stated below:‐

(i) Finished fertilizers or any other Priority accorded by Government except Coastal cargo Vessels 2 berths (ii) Coastal cargo Vessels 1 berths (iii) Container 1 berths

Mantec Consultants Pvt. Ltd. Page 40 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla (iv) Priority (24 hrs. 12000 MT priority 7000/550MT priority) 3 berths (v) Steel Carp 1 berth (up‐to 15‐11 ‐15)

After allotment of berths to the above group vessels, the remaining berths will be allotted to normal Import and Export vessels on First‐come‐First serve basis (maximum three vessels). In case any of the above group vessels is/are not available, the allotment of the vacant berth/(s) will be following order. (1) Vessel that is ready to occupy the berth for a day. (2) Vessel ready to occupy for 2 days. (3) Vessel that is ready to core to berth for 3 days and so on

Liquid cargo

(I) Assuring maximum per hour rate of handling 1 Jetty (II) First‐Come First Serve 3 Jetties (III) IFFCO 1 Jetty (IV) IOC /BPC 1Jetty

Note: ‐ in absence of IFFCO tanker I jetty to tanker opting for 24 hrs.  There will be restriction of berthing maximum two edible oil tankers at 4 oil jetties.  The tanker allotted berth on assurance of maximum per hour rate will be adjusted against the two berths each for chemical and edible oil respectively.

2.11 Port Equipments Wharf Cranes

 12 Wharf Cranes. of the following capacities (i) 2 of 12 Tons (ii) 4 of I 6 Tons (iii) 6 of 25 Tons  The rated capacity of 16 Tons cap. Crane is 400 MT/hour.  The rated capacity of 25 Tons cap. Crane is 600 MT/hour,  Many private 71 cranes to provide faster discharge. Mobile Harbour Cranes

Mantec Consultants Pvt. Ltd. Page 41 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

In addition the 12 Wharf Cranes, the Port is equipped with Mobile Harbour Cranes (Owned both by DPT and Private Stevedores} and Floating Cranes (Owned by Private Stevedores) The details are given below: Mobile Harbour Cranes:

Owned by DPT

2 MHC Commissioned

Owned by Private Stevedores

A. V Joshi ‐2 Commissioned AMC ‐2 commissioned Balaji Heavy lifts ‐2 Commissioned

Floating Cranes

Rishi Shipping ‐ 2 Commissioned, I expected by Feb 16. Shreeji Shipping ‐2 Commissioned U.L.A. ‐1 Commissioned. I expected by Feb 16. Shiv Shipping ‐ 1 Commissioned

Steel Floating Dry Dock

One Steel Floating Dry Dock with following specification  LOA : 95 MT  Draught 5.4 MT  Breadth 20 MT  Capacity : 2700 MT

Workshop Facilities

Port is having a sophisticated at kandla with machineries like Lathe, various types of Drilling. Milling, Slotting, Shaping machines, etc.

2.12 Upcoming Projects

 Development or Smart Industrial Port city at Kandla‐ Gandidham‐ complex.

Mantec Consultants Pvt. Ltd. Page 42 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla  Development of Berthing Facilities off Tekra near Tuna BOT Basis‐Stage II  Construction of ROB at Kandla Port.  Oil Jetty no.8 to 11with associated back up area.  Setting up of Renewable energy park at kandla.

2.13 Highlights of Fire Safety Measures  Three Fire Stations, manned round the‐clock.  Qualified, trained and experienced fire manpower.  Fire Water Systems.  Foam Systems.  First Aid Fire Fighting Equipments.  Mobile Fire Fighting Equipments.  Safety Equipment Personal Protective Equipments  Storage of Fire Fighting Agents.  Fire Alarm & Communication Systems.  Gas Detection Systems.  Fire Safety 0rganization & Training.  Fire Emergency Manual.  Land Based: 1.0 Fire Tenders, One Safety Jeep and one Ambulance.  All Shipping tugs are having in Fire Fighting Facilities  Fully Fledged Fire Fighting Facilities at Shore and Harbour.  The Fire Brigade Officials are trained at the National Fire Service College, Nagpur and so trained. Officials impart training to the Fire Brigade Personnel and Pori Employees Officials at Port Head Qtrs. Fire Station.

Mantec Consultants Pvt. Ltd. Page 43 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla

Chapter 3. Description of Environment

The baseline environmental status with respect to various environmental components like air, noise, water, land, flora & fauna and socio‐economic, being integral part of an EIA, forms the basis for predicting/assessing the environmental impacts of the proposed project. The EIA Report presents the data collected during 01 Feb 2018 to 28 Feb 2018 (One Month) of pre‐monsoon season. Apart from field monitoring, secondary data was also collected from sources like Government and Non‐Governmental Agencies, Water Resource Department, India Meteorological Department (IMD), Ground Water Board, etc.

3.1 Air Environment 3.1.1 Meteorology Historical data on Climatological parameters recorded at Kandla Observatory, for 2014 have been used to establish general meteorological regime of the study area while meteorological data recorded at site during the monitoring period has been used for interpretation of the baseline scenario at site.

3.1.1.1 Synthesis of Data on Climatic Conditions Summary of Climatological Observations Table-3.0 presents the summary of climatological observations recorded at Observatory, Kandla during 2014, with respect to significant parameters. The observatory records the meteorological parameters twice a day at 08.30 and 17.30 hours IST. Monthly average of maximum and minimum daily observed value at 08:30 and 17:30 are given in Table 3.0. Temperature The monthly mean values of temperature are presented in Table 3.0. It is observed that, the ambient temperature gradually rises till June which is hottest month; however maximum temperature of 41.70°C was recorded in the month of April. The minimum temperature was recorded in the month of January as 9.5°C. Relative Humidity

Mantec Consultants Pvt. Ltd. Page 44 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Deendayal Port at Kandla The relative humidity of the area varies from 32% to 97% is the lowest in the month of January/February and maximum in the month of July/August. The annual relative humidity ranges from 36% to 62%. Rainfall The area has received rainfall only in the three months of monsoon i.e. July, August, and September. Maximum rainfall was received in the months of July with 75.8 mm rainfall while the minimum rainfall was observed in the month of Septmber. Rest of the months mostly remained dry. Wind Speed and Direction Analysis of wind records during 2014 shows that the winds are generally strong in this area, It can be seen that the monthyl mean wind speed varies from 5.71 – 15.7 km/h. The strongest winds are observed during June and the weakest during the month of October. West South West (WSW) is the dominant wind direction followed by South West (SW) in the study area.

Mantec Consultants Pvt. Ltd. Page 45 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Table 3: Climatological Table of Kandla Observatory (2014)

Month Temprature in C Relative Vapour Pressure, Stats Ave.Wind Dewpoint, C Rain fall, mm. Pressure(MSL), mb. Wind Direction (Daily Avg) Humidity, % mb. spead(K/h) Maximum Minimum 0830 1730 0830 1730 0830 1730 0830 1730 0830 1730 0830 1730 Jan-14 Max 12.00 31.20 15.50 13.50 17.90 87.00 64.00 15.50 20.50 0.00 0.00 1022.00 1017.80 Min 4.00 22.30 9.50 ‐1.80 6.90 41.00 33.00 ‐6.90 9.90 0.00 0.00 1018.60 1014.50 Ave. 7.45 26.75 12.84 7.62 9.48 64.29 39.65 10.29 12.06 0.00 0.00 1018.81 1015.65 NNW NNE Feb-14 Max 9.00 32.10 18.90 18.40 18.90 91.00 62.00 21.10 21.80 0.00 0.00 1019.40 1016.50 Min 4.00 28.90 17.00 11.40 8.30 60.00 32.00 13.50 10.90 0.00 0.00 1014.30 1012.10 Ave. 6.71 29.03 15.91 11.08 11.42 66.93 39.18 13.73 13.89 0.00 0.00 1014.75 1011.81 NNW NNE Mar-14 Max 12.00 38.60 22.80 22.30 27.10 88.00 83.00 26.90 35.90 0.00 0.00 1017.60 1014.30 Min 8.00 29.00 14.60 11.90 6.30 66.00 28.00 13.90 9.50 0.00 0.00 1010.90 1007.90 Ave. 7.48 33.33 19.70 14.78 13.28 62.81 37.23 17.35 15.85 0.00 0.00 1014.65 1011.36 NNE SW Apr-14 Max 13.00 41.70 28.50 26.90 25.40 94.00 72.00 35.40 32.50 0.00 0.00 1014.40 1010.50 Min 10.00 34.10 20.10 19.60 15.70 78.00 36.00 22.80 17.80 0.00 0.00 1009.60 1006.30 Ave. 8.83 36.36 23.93 21.09 19.91 73.17 43.00 25.48 23.74 0.00 0.00 1011.84 1008.14 WSW WSW Max 16.00 38.60 28.50 28.10 28.20 94.00 67.00 38.00 38.20 0.00 0.00 1011.50 1008.20 May-14 Min 7.00 29.20 24.20 20.20 22.40 51.00 47.00 23.70 27.10 0.00 0.00 1005.30 1001.40 Ave. 12.32 36.53 26.94 25.42 25.65 78.65 57.23 32.60 33.08 0.00 0.00 1008.43 1005.00 WSW SW Jun-14 Max 21.00 41.50 30.50 27.90 27.80 85.00 64.00 37.60 37.40 0.00 0.00 1009.10 1005.90 Min 10.00 35.60 27.40 23.80 23.30 62.00 42.00 29.50 28.60 0.00 0.00 999.50 996.40 Ave. 15.70 37.33 28.90 26.10 25.49 74.13 55.40 33.87 32.68 0.00 0.00 1003.22 1000.72 WSW SW Jul-14 Max 21.00 39.10 29.50 27.90 28.80 97.00 92.00 37.80 39.60 78.50 15.50 1006.90 1004.30 Min 6.00 29.50 25.00 20.10 23.00 60.00 43.00 29.70 28.10 0.00 0.00 998.60 995.80 Ave. 12.48 34.98 27.95 25.51 25.37 79.16 62.87 33.21 32.49 3.86 1.38 1002.67 1000.04 WSW SW Aug-14 Max 17.00 36.10 28.10 27.00 27.40 97.00 93.00 35.70 36.50 23.00 58.00 1011.40 1007.90 Min 5.00 28.90 24.60 23.60 23.90 76.00 55.00 27.70 29.70 0.00 0.00 999.30 996.10 Ave. 10.52 33.28 26.60 25.23 25.25 84.55 68.00 32.08 32.18 2.86 2.25 1005.06 1002.45 WSW WSW Sep-14 Max 16.00 36.10 27.10 26.40 27.20 92.00 92.00 34.40 36.10 2.80 10.40 1014.00 1011.30 Min 4.00 28.70 24.60 23.50 21.90 72.00 47.00 28.90 23.60 0.00 0.00 1000.00 997.30 Ave. 8.57 33.44 25.74 24.81 24.08 83.53 63.43 31.36 29.90 0.20 0.46 1008.24 1005.55 WSW WSW Oct-14 Max 8.00 39.90 27.80 25.30 26.60 85.00 69.00 32.30 34.80 0.00 0.00 1016.00 1012.40 Min 3.00 30.80 20.80 15.50 15.90 54.00 32.00 17.60 18.10 0.00 0.00 1009.10 1006.00 Ave. 5.71 36.90 24.07 21.58 21.30 72.68 47.61 26.10 25.67 0.00 0.00 1013.23 1010.01 WNW WSW Nov-14 Max 9.00 37.40 25.40 24.50 25.90 91.00 75.00 30.70 33.40 0.00 0.00 1017.60 1013.50 Min 3.00 31.20 18.60 10.50 14.70 40.00 36.00 12.70 16.70 0.00 0.00 1013.80 1010.20 Ave. 5.73 34.44 21.68 17.32 20.17 69.47 51.90 20.33 24.00 0.00 0.00 1015.61 1012.06 NNW SW Dec-14 Max 10.00 33.70 19.20 18.20 19.50 85.00 53.00 20.90 22.70 0.00 0.00 1021.60 1018.00 Min 4.00 25.10 10.40 4.80 2.00 45.00 27.00 8.60 7.10 0.00 0.00 1013.60 1010.00 Ave. 6.19 28.95 14.26 9.93 11.38 67.81 40.52 12.48 13.88 0.00 0.00 1017.74 1014.46 NNW NNE

Mantec Consultants Pvt. Ltd. Page 46 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.1.1.2 Methodology of Data Generation During the study, a continuous automatic weather monitoring station was established at site to record Wind speed, Wind Direction, Relative Humidity and Temperature at 2 m and 10 m above ground. Atmospheric pressure was recorded twice a day at 0830 and 1730 hrs. Cumulative Rainfall was monitored by rain gauge on daily basis and the present report incorporates the data from 01 Feb, 2018 to 28 Feb, 2018. The methodology adopted for monitoring meteorological observations is as per the standard norms laid down by Bureau of Indian Standards (BIS) and the India Meteorological Department (IMD).

3.1.1.3 Meteorological Observation at Site A fully instrumented continuous recording meteorological observatory is established and operating at Kandla from May, 2017 and this report presents the data from 01 Feb, 2018 to 28 Feb, 2018recorded at site. The following parameters are being measured: ‐  Temperature at 2 m and 10 m level  Relative humidity  Wind speed and direction  Rainfall The brief details of instruments, parameter and frequency are presented in Table-4.

Table 4: Instruments, Parameters and Frequency of Meteorological Monitoring at Site

S.No. PARAMETERS INSTRUMENTS FREQUENCY 1 Wind Speed

2 Wind Direction

Automatic Weather Ambient Temperature at Continuous Automatic 1 3 Station (Envirotech two heights of 2m & 10m hourly Average WM 251) 4 Max. & Min Temperature 5 Humidity 6 Rainfall 7 Atmospheric Pressure Aneroid Barometer Daily at 08:30 & 17:30 IST 8 Storm Visual observation Daily

Mantec Consultants Pvt. Ltd. Page 47 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Temperature and Humidity The climate of Deendayal Port is generally tropical and dry. The air temperature varies from less than 11° C in winter to about 39° C in February 2018. The mean of maximum and minimum temperature observed in the Study period months at Kandla is presented in the Table-5 below;

Table 5: Temperature Data Recorded at Site

Months Mean Max. Temperature Mean Min. Temperature Feb-2018 32 15.2

Due to its location adjacent to the Creek and the Arabian Sea, relative humidity is comparatively high throughout the year. Relative humidity in the dry season varies from 40 % to 94% in the morning hours and 26% to 75% in the evening hours. However, it was observed that relative humidity varies from 55% to 98% in the morning hour and 40% to 94% in the evening hours. Rainfall Rainfall in Kandla is very low. Between January and April, there is normally no rainfall. Rainfall generally remains confined between June end and mid September. During the remaining months, the rainfall is scanty. The climatological normal annual rainfall is reported as 319.8 mm, out of which 93% is received during southwestern monsoon season. Wind Conditions Based on the observations of wind flow patterns due to continuous monitoring at site, the following inferences can be made:

The predominant direction is from NNW during morning hour and NNE during January evening hour. The wind speed varies from 3.5 to 12.5 kmph with an average value of 7.2 kmph. The predominant direction is from NNW during morning hour and NNE during February evening hour. The wind speed varies from 3.1 to 8.8 kmph with an average value of 6.8 kmph. The predominant direction is from NNE during morning hour and SW during evening March hour. The wind speed varies from 7.2 to 12.8 kmph with an average value of 7.8 kmph. The predominant direction is from WSW during morning hour and WSW during April evening hour. The wind speed varies from 9.2 to 12.8 kmph with an average value of 8.9 kmph.

Mantec Consultants Pvt. Ltd. Page 48 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

The predominant direction is from WSW during morning hour and SW during May evening hour. The wind speed varies from 7.2 to 16.8 kmph with an average value of 11.8 kmph. The predominant direction is from WSW during morning hour and SW during June evening hour. The wind speed varies from 9.1 to 22.8 kmph with an average value of 16.8 kmph. The predominant direction is from WSW during morning hour and SW during July evening hour. The wind speed varies from 5.5 to 21.8 kmph with an average value of 11.8 kmph. The predominant direction is from WSW during morning hour and WSW during August evening hour. The wind speed varies from 5.2 to 17.8 kmph with an average value of 10.8 kmph. The predominant direction is from WSW during morning hour and WSW during September evening hour. The wind speed varies from 3.8 to 16.8 kmph with an average value of 8.8 kmph. The predominant direction is from WNW during morning hour and WSW during October evening hour. The wind speed varies from 3.8 to 8.8 kmph with an average value of 4.5 kmph. The predominant direction is from NNW during morning hour and SW during evening November hour. The wind speed varies from 3.5 to 9.8 kmph with an average value of 4.8 kmph. The predominant direction is from NNW during morning hour and NNE during December evening hour. The wind speed varies from 3.9 to 10.2 kmph with an average value of 5.8 kmph.

The wind‐rose diagram for the study period has been drawn on the basis of hourly wind speed and direction data. The wind rose diagram at site for the month of Feb 2018 is presented in Figure-10. The wind rose diagram shows that the dominant direction of wind flow is from North West direction in months of 01 Feb, 2018 to 28 Feb, 2018.

Storms and Cyclones Deendayal port is not generally affected by cyclonic storms. During June 1998, a severe cyclonic storm, which passed over Deendayal Port with a wind speed of 150 km/hr., resulting in high tidal waves of 10.5 m with strong current, caused extensive damages to the Port installations, crafts and human lives.

Mantec Consultants Pvt. Ltd. Page 49 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 10: Windrose diagram

Mantec Consultants Pvt. Ltd. Page 50 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.1.2 Ambient Air Quality The prime objective of the baseline study with respect to ambient air quality is to establish the present air quality and its conformity to ambient air quality standards. This section describes the sampling locations, frequency of sampling and methodology adopted for monitoring ambient air quality. The results of monitoring during the study period (01 February 2018 to 28 February 2018) are also presented. The study area represents the area occupied by Deendayal Port Trust and its associated facilities, as well as the surrounding area comprising of few villages. The sources of air pollution in the region are vehicular traffic, fuel burning, loading & unloading of dry cargo, fugitive emissions from storage area and dust arising from unpaved village roads.

3.1.2.1 Methodology adopted for the Study Sampling Locations, Parameters and Frequency

Calibrated Respirable Dust Samplers were used for the sampling of PM10, PM2.5, SO2,

NOx and CO. Ambient air sampling for PM10, PM2.5, SO2, NOx and CO was performed continuously for 24 hours to determine 24‐hour average concentrations. Ambient air quality monitoring was carried out with a frequency of two days per week at all locations. The sampling was performed at a height of 3.5 m (approximately) from the ground level. Standard methods specified under "National Ambient Air Quality Standards" notification G.S.R. 176(E) were adopted for sampling and analysis. Six locations within the study area were scientifically selected and are based on the following considerations:  Meteorological conditions;  Topography of the study area;  The direction of the wind;  Representation of the region for establishing baseline status; and  Representation with respect to likely impact areas. The location of the monitoring stations with reference to the proposed project site is given in Table 6 and shown in Figure 11.

Table 6: Ambient Air Quality Monitoring Locations

Station Code Stations Latitude Longitude

Mantec Consultants Pvt. Ltd. Page 51 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

A1 Salt Pan near Rampar 22o 57' 36.98" N 70o 04'48.46" E Salt Pan near village A2 22o 55' 22.52" N 70o 01'58.19" E Chandrapar A3 Deendayal Port 23o 01' 17.22" N 70o 12'47.47" E A4 Khari Road 23o 04' 34.36" N 70o 10'16.33" E A5 Shinay 23o 02' 15.87" N 70o 03'41.81" E A6 Tuna 22o 59' 32.29" N 70o 04'52.36" E A7 Gandhidham 23o 04' 43.38" N 70o 07'46.72" E A8 Kasez Township 23o 02' 06.33" N 70o 08'12.12" E

Figure 11: Air Monitoring Location Sampling and Analytical Techniques Techniques Used for Ambient Air Quality Monitoring have been summarized in Table- 7, and National Ambient Air Quality Standards, 2009 is given in Table-8, mentioned in successive pages. Particulate Matter (10), (2.5)

Mantec Consultants Pvt. Ltd. Page 52 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Calibrated 'Respirable Dust Samplers' with Whatman GF/A microfiber filter paper (size: 8” X 10”) was used for the collection of PM (10). APM‐ 151 air sampler of Lata Envirotech instrument was attached with Repirable Dust Sampler for monitoring particulate matter of size <2.5 microns. A known volume of ambient air is passed through the cyclone to the initially preprocessed filter paper. The centrifugal force in cyclone acts on particulate matter to separate them into two parts and collected as followings: ‐ a. Particles <10 μ size (Respirable) : GF/A Filter Paper b. Particles >10 μ size (Non Respirable) : Cyclone Cup c. Particles <2.5 μ size : Teflonbfilter paper 47mm

The differences in final and initial weight of filter paper and cyclone cup are used in estimation of particulate matter. The mass of particulates collected on the GF filter,

divided by the volume of sampled air, gives the concentration of PM (10) whereas the mass of particulates collected on the teflon filter, divided by the volume of sampled air,

3 gives the concentration of PM(2.5). The results are expressed in μg/m .

Sulphur Dioxide

Sampling and analysis of ambient SO2 was performed by adopting the 'Improved West and Gaeke Method'. The ambient air, drawn through the draft created by the RDS, is passed through an impinger, containing a known volume of absorbing solution of sodium tetrachloromercurate, at a pre‐determined and measured flow rate of 1

liter/minute (L/min). SO2 in ambient air reacts with the tetrachloromercurate to form a stable complex, dichloro-sulphito mercurate. On reacting with formaldehyde and p- rosaniline hydrochloride, the sulphite ion forms an intensely coloured compound, p‐ rosaniline methyle sulphonic acid. The intensity of the colour developed is estimated by spectrophotometer at 560 nm wave length. The measured Optical Density (OD) is used

to determine the concentration of SO2 from the calibration curve already prepared

against known concentrations of sulphite ion. The mass of SO2 in the absorbing reagent,

divided by the volume of sampled air provides the concentration of SO2, which is expressed as μg/m3.

Mantec Consultants Pvt. Ltd. Page 53 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Nitrogen Oxides Sampling and analysis of ambient NOx was performed by adopting the 'Jacob Hochheister Modified’ (Na arsenite) method. Ambient air is drawn through an impinger at a pre determined flow rate of 1 ppm. The impinger contains known volume of absorbing solution of sodium arsenite and sodium hydroxide. Oxides of nitrogen react with the absorbing reagent to form a stable solution of sodium nitrite. The nitrate ion produced during the sampling is estimated calorimetrically, after reacting with phosphoric acid, sulphanilamide and naphthyl ethylenediamine dihydrochloride (NEDA), using spectrophotometer at 540 nm wavelength. The measured Optical Density is used to determine the concentration of NOx from the calibration curve already prepared against known concentrations of nitrite ion. The mass of NOx in the absorbing reagent, divided by the volume of sampled air provides the concentration of NOx, which is expressed as μg/m3.

Carbon Monoxide (CO) Samples containing carbon monoxide in the range of 0 to 100 mg/l are analysed on a non dispersive infrared absorption gas analyser, namely, an electro‐optical spectrophotometer with no spectral dispersion component. It may consist of a single or double source of infrared energy and one or more infrared detectors separated by an optical cell or cells through one or more of which the sample flows, whereby the specific spectral absorption of the component of interest is determined.

Table 7: Techniques Used for Ambient Air Quality Monitoring

Minimum Parameters Technique Technical Protocol Detectable Limit (ug/m3) CPCB Guideline PM 10 IS‐5182 (Part‐IV) 1.0 (Gravimetric method) PM 2.5 Gravimetric As per CPCB Guideline 1.0 SO2 West and Geake IS‐5182 (Part‐II) 5.0 NO2 Jacob & Hochheiser IS‐5182 (Part‐VI) 9.0 Non Dispersive Infrared CO IS‐5182 (Part‐X) 0.003 (NDIR) spectroscopy

Table 8: National Ambient Air Quality Standards

Mantec Consultants Pvt. Ltd. Page 54 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Concentration in ambient air Time- Pollutants weighted Industrial, Ecologically Sensitive Method of measurement average residential, rural Areas (notified by and other area Central Government)

Annual* 50 µg/m3 20 µg/m3 ‐Improved West & Gaeke Sulphur Dioxide 3 (SO2), µg/m 24 hours** 80 µg/m3 80 µg/m3 ‐Ultraviolet fluorescence

Annual* 40 µg/m3 30 µg/m3 ‐Modified Jacob & Nitrogen Dioxide Hochheiser (Na‐Arsenite) 3 (NOx), µg/m 24 hours** 80 µg/m3 80 µg/m3 ‐Chemiluminescence

Particulate Matter Annual* 60 µg/m3 60 µg/m3 ‐ Gravimetric (Size less than 10µm) ‐TOEM or PM µg/m3 ‐Beta attenuation 10 24 hours** 100 µg/m3 100 µg/m3

Particulate Matter Annual* 40 µg/m3 40 µg/m3 ‐ Gravimetric (size less than 2.5 ‐TOEM 3 microns) PM2.5 µg/m 24 hours** 60 µg/m3 60 µg/m3 ‐Beta attenuation

8 hours* 02 mg/m3 02 mg/m3 Carbon Monoxide ‐Non dispersive Infra Red (CO) (NDIR) Spectroscopy 1 hour* 04 mg/m3 04 mg/m3

*Annual arithmetic mean of minimum 104 measurements in a year at a particular site taken twice a week 24 hourly at uniform intervals. **24 hourly or 08 hourly or 1 hourly monitored values, as applicable, shall be complied with 98% of the time in a year. 2% of the time, they may exceed the limits but not on two consecutive days of monitoring.

3.1.2.2 Presentation of Results The results of ambient air quality monitoring for the period (01 February 2018 to 28 February 2018) are presented in the following pages. Data has been compiled for one month of non‐monsoon season. Various parameters monitored during the study have been described by their maximum, minimum and average values from their study site locations. The results for six locations according to seasons have been discussed under the following pages. The results of ambient air quality monitoring are presented in Table-9 to 14.

Mantec Consultants Pvt. Ltd. Page 55 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Table 9: Ambient Air Quality at A-1 1 Salt Pan near Rampar PM PM SO NO CO MONTH DATE 10 2.5 2 2 (µg/m3) (µg/m3) (µg/m3) (µg/m3) (mg/m3) 01.02.2018 78 42 11 16 0.68 04.02.2018 64 38 9 18 0.77 08.02.2018 80 46 12 20 0.82 11.02.2018 74 44 10 18 0.76 Feb-18 15.02.2018 82 48 8 16 0.64 18.02.2018 76 41 11.5 24 0.72 22.02.2018 84 46 9 20 0.66 25.02.2018 68 38 10.5 22 0.74 Max 84 48 12 24 0.82 Min 64 38 8 16 0.64

Avg 75.75 42.88 10.13 19.25 0.72 98 percentile 83.72 47.72 11.93 23.72 0.81

Table 10: Ambient Air Quality at A-2 2 Salt Pan Near Chandrapar PM PM SO NO MONTH DATE 10 2.5 2 2 CO (µg/m3) (µg/m3) (µg/m3) (µg/m3) 01.02.2018 82 48 8 18 0.64 04.02.2018 68 36 10.5 22 0.64 08.02.2018 74 40 11 24 0.68 11.02.2018 68 36 9 14 0.72 Feb-18 15.02.2018 76 42 12 18 0.66 18.02.2018 66 36 10 22 0.72 22.02.2018 86 48 9.5 16 0.62 25.02.2018 78 42 7 18 0.58 Max 86 48 12 24 0.72 Min 66 36 7 14 0.58

Avg 74.75 41.00 9.63 19.00 0.66 98 percentile 85.44 48.00 11.86 23.72 0.72

Table 11: Ambient Air Quality at A-3 3 Deendayal Port

Mantec Consultants Pvt. Ltd. Page 56 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

PM PM SO NO MONTH DATE 10 2.5 2 2 CO (µg/m3) (µg/m3) (µg/m3) (µg/m3) 01.02.2018 80 44 10 18 0.82 04.02.2018 84 46 12 23 0.77 08.02.2018 78 40 8 20 0.64 11.02.2018 72 39 10.5 19.5 0.59 Feb-18 15.02.2018 82 46 12 24 0.88 18.02.2018 76 41 11.5 20 0.72 22.02.2018 62 34 9 21 0.78 25.02.2018 79 42 12.5 24 0.82 Max 84 46 13 24 0.88 Min 62 34 8 18 0.59

Avg 76.63 41.50 10.69 21.19 0.75 98 percentile 83.72 46.00 12.43 24.00 0.87

Table 12: Ambient Air Quality at A-4 4 Khari Road PM PM SO NO MONTH DATE 10 2.5 2 2 CO (µg/m3) (µg/m3) (µg/m3) (µg/m3) 02.02.2018 78 38 9 18 0.82 05.02.2018 72 42 11 21 0.76 09.02.2018 80 48 10 22 0.69 12.02.2018 76 41 8 19 0.78 Feb-18 16.02.2018 84 40 12 26 0.76 19.02.2018 76 38 11 22 0.68 23.02.2018 69 37 8 18 0.71 26.02.2018 79 41 11 20 0.95 Max 84 48 12 26 0.95 Min 69 37 8 18 0.68

Avg 76.75 40.63 10.00 20.75 0.77 98 percentile 83.44 47.16 11.86 25.44 0.93

Table 13: Ambient Air Quality at A-5 5 Shinay PM PM SO NO MONTH DATE 10 2.5 2 2 CO (µg/m3) (µg/m3) (µg/m3) (µg/m3) 02.02.2018 73 35 13 17 0.83 Feb-18 05.02.2018 69 38 11 19 0.71 09.02.2018 70 40 8 16 0.72

Mantec Consultants Pvt. Ltd. Page 57 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

12.02.2018 82 46 10 20 0.81 16.02.2018 78 37 9 19 0.61 19.02.2018 70 40 15 24 0.75 23.02.2018 56 32 8 16 0.84 26.02.2018 68 40 6 20 0.86 Max 82 46 15 24 0.86 Min 56 32 6 16 0.61

Avrg 70.75 38.50 10.00 18.88 0.77 98 percentile 81.44 45.16 14.72 23.44 0.86

Table 14: Ambient Air Quality at A-6

6 Tuna PM PM SO NO MONTH DATE 10 2.5 2 2 CO (µg/m3) (µg/m3) (µg/m3) (µg/m3) 02.02.2018 77 37 11 24 0.75 05.02.2018 70 43 8 22 0.64 09.02.2018 68 33 9 20 0.78 12.02.2018 75 36 13 23 0.61 Feb-18 16.02.2018 66 37 10 21 0.68 19.02.2018 71 40 12 26 0.78 23.02.2018 74 42 15 26 0.64 26.02.2018 68 38 8 17 0.81 Max 77 43 15 26 0.81 Min 66 33 8 17 0.61

Avrg 71.13 38.25 10.75 22.38 0.71 98 percentile 76.72 42.86 14.72 26.00 0.81

Table 15: Ambient Air Quality at A-7 7 Gandhidham PM PM SO NO MONTH DATE 10 2.5 2 2 CO (µg/m3) (µg/m3) (µg/m3) (µg/m3) 03.02.2018 79 40 10 20 0.87 06.02.2018 74 35 8 18 0.69 10.02.2018 69 37 12 26 0.93 Feb-18 13.02.2018 72 44 15 26 0.67 17.02.2018 76 43 11 22 0.71 20.02.2018 72 39 8 18 0.69 24.02.2018 79 45 10 20 0.77

Mantec Consultants Pvt. Ltd. Page 58 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

27.02.2018 76 37 13 23 0.65 Max 82 46 15 24 0.86 Min 56 32 6 16 0.61 Avg 70.75 38.50 10.00 18.88 0.77 98 81.44 45.16 14.72 23.44 0.86 percentile

Table 16: Ambient Air Quality at A-8 8 Kasez Township PM PM SO NO MONTH DATE 10 2.5 2 2 CO (µg/m3) (µg/m3) (µg/m3) (µg/m3) 03.02.2018 66 35 5.5 23 0.84 06.02.2018 68 36 7 16 0.82 10.02.2018 73 39 11 28 0.78 13.02.2018 86 45 9 22 0.74 Feb-18 17.02.2018 77 40 8 20 0.77 20.02.2018 61 34 12 26 0.65 24.02.2018 72 40 7 23 0.77 27.02.2018 79 45 11 20 0.72 Max 86 45 12 28 0.84 Min 61 34 6 16 0.65 Avg 72.75 39.25 8.81 22.25 0.76 98 85.02 45.00 11.86 27.72 0.84 percentile

Particulate Matter 10 (PM10):

3 The maximum value for PM10 is observed, as 86 µg/m at near salt pan near chandrapar while 24 hours applicable limit is 100µg/m3 for Industrial, residential, rural and other

3 area. The minimum value of PM10 is 56.0µg/m with recorded at Gandhidham.

Particulate Matter 2.5 (PM2.5):

3 The maximum value for PM2.5 observed is, 48.0 µg/m at Khari road while 24 hours

3 applicable limit is 60 µg/m for Industrial, residential, rural and other area. The PM2.5 value of 32 µg/m3 is the lowest concentration recorded at Gandhidham.

Sulphur dioxide (SO2):

Mantec Consultants Pvt. Ltd. Page 59 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3 The maximum value for SO2 is observed, as 15 µg/m at Gandhidham, Bharpar, Tuna while 24 hours applicable limit is of 80 µg/m3 for Industrial, residential, rural and other

3 area. The minimum value of SO2 is 6 µg/m at Bharapar and Kasez Township.

Nitrogen dioxide (NO2):

3 The maximum value for NO2 is observed, as 28 µg/m at Kasez township while 24 hours applicable limit is of 80 µg/m3 for Industrial, residential, rural and other area. The

3 minimum value of NO2 is 14.0 µg/m at Salt Pan near Chandrapar.

Carbon Monoxide (CO): The maximum value for CO is observed, as 950 µg/m3 Khari Road and the minimum value of CO is 580 µg/m3 at Salt Pan near Chandrapar.

The graphic representation of the air quality results have been presented in Figure 12 to 16.

Figure 12: PM10 graph of DPT Stage-1( for 3 Integarted Facilities)

Mantec Consultants Pvt. Ltd. Page 60 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 13: PM2.5 graph of DPT Stage-1( for 3 Integarted Facilities)

Figure 14: SO2 graph of DPT Stage-1( for 3 Integarted Facilities)

Mantec Consultants Pvt. Ltd. Page 61 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 15: NO2 graph of DPT Stage-1( for 3 Integarted Facilities)

Figure 16: CO graph of DPT Stage-1( for 3 Integarted Facilities)

Mantec Consultants Pvt. Ltd. Page 62 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 17 : Air Quality Monitoring Photographs

3.1.3 Result of Comparision with earlier collected Air Quality Data (2012-13)

Ambient Air Quality Data (2012-2013) Name of the PM-10 (µg/m3) PM-2.5(µg/m3) SO2 (µg/m3) NO2(µg/m3) CO (µg/m3) Pollutants Max 71 45 22 30 490 Min 53 28 11 11 310

Ambient Air Quality Data (2018) Name of the PM-10 (µg/m3) PM-2.5(µg/m3) SO2 (µg/m3) NO2(µg/m3) CO (µg/m3) Pollutants Max 86.00 48.00 15.00 28.00 950 Min 56.00 32.00 6 14.00 580

From the above, it has been observed that maximum value of pollutants like PM‐10, PM‐2.5, and CO has been inresed by 15, 3, 460 µg/m3, respectively and value of SO2 and NO2 has been decreased by 7 and 2 µg/m3 respectively. After the incremental concentrations, values of these pollutants have been found within the permissible limits of NAAQS.

3.2 Noise 3.2.1 Objective Noise can be defined as an unwanted sound. It is, therefore, necessary to measure both the quality as well as the quantity of environment noise in and around the proposed developmental activities. Noise produced during construction and there after activities may affect surrounding environment affecting fauna and also the human population working and residing not only at site but also in the nearby areas.

Mantec Consultants Pvt. Ltd. Page 63 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.2.2 Methodology The intensity of sound energy in the environment is measured in a logarithmic scale and is expressed in a decibel (dB) scale. Ordinary sound level meter measures the sound energy that reaches the microphone by converting it into electrical energy and then measures the magnitude in dB. In a sophisticated type of sound level meter, an additional circuit (filters) is provided, which modifies the received signal in such a way that it replicates the sound signal as received by the human ear and the magnitude of sound level in this scale is denoted as dB(A). The sound levels are expressed in dB(A) scale for the purpose of comparison of noise levels, which is universally accepted by the international community.

Noise levels were measured using an Integrating sound level meter manufactured by Cygnet (Model No. 2031). It has an indicating mode of Lp and Leq. Keeping the mode in Lp for few minutes and setting the corresponding range and the weighting network in “A” weighting set the sound level meter was run for one hour time and Leq was measured at all locations.

The day noise levels have been monitored during 6.00am to 10.00pm and night noise levels, during 10.00pm to 6.00am at all the ten locations covered in 10 km radius of the study area.

3.2.3 Parameters Measurement The L10, L50, L90, Leq, Ld and Ln were computed based on the sound pressure level recorded. Leq ‐ 24 Hourly equivalent continuous noise level Ld ‐ Daytime Leq that has computed from 6.00 a.m to 10.00 pm Ln ‐ Nighttime Leq, that is computed from10.00 p.m. to 6.00 a.m

3.2.4 Sampling Locations A preliminary reconnaissance survey was undertaken to identify the major noise generating sources in the area. The noise survey was conducted in pre‐monsoon season

Mantec Consultants Pvt. Ltd. Page 64 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

(01 Feb 2018 to 28 Feb 2018) to assess the background noise levels in commercial zone of Deendayal Port Trust.

The sampling locations for noise are confined to commercial areas of Deendayal Port Trust. Ten sampling locations were selected for the sampling of noise and are shown in Figure-17 and also given in Table-17.

Table 17: Noise Level Monitoring Stations in the Study Area

Station Code Latitude Longitude Stations Name

N-1 Salt Pan near Rampar 22o 57' 36.98" N 70o 04'48.46" E Salt Pan near village N-2 Chandrapar 22o 55' 22.52" N 70o 01'58.19" E

N-3 Deendayal Port 23o 01' 17.22" N 70o 12'47.47" E N-4 Khari Road 23o 04' 34.36" N 70o 10'16.33" E N-5 Shinay 23o 02' 15.87" N 70o 03'41.81" E N-6 Tuna 22o 59' 32.29" N 70o 04'52.36" E N-7 Gandhidham 23o 04' 43.38" N 70o 07'46.72" E N-8 Kasez Township 23o 02' 06.33" N 70o 08'12.12" E

Mantec Consultants Pvt. Ltd. Page 65 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 18: Noise Level Monitoring Stations in the Study Area

3.2.5 Noise Standards Ministry of Environment & Forests (MoEF) has notified the noise standards vide gazette notification dated February 14, 2000 for different zones under the Environment Protection Act (1986). These standards are given in Table-18.

Table 18: Ambient Noise Quality Standards in respect of Noise

Area Noise dB (A) Leq Category of Area Code Daytime* Night time* A Industrial Area 75 70 B Commercial Area 65 55 C Residential Area 55 45 D Silence Zone 50 40

Note:

Mantec Consultants Pvt. Ltd. Page 66 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

1. Day time shall mean from 6.00 am to 10.00 pm. 2. Night time shall mean from 10.00 pm to 6.00 am. 3. Silence zone is defined as area comprising not less than 100 meters around hospitals, educational institutions, courts, religious places or any other area, which is declared as such by the competent authority.

3.2.6 Results and Discussion The noise data compiled on noise levels for the period of one month of non‐monsoon is presented in Table-19. It can be observed from the table that the hourly noise levels ranges in non‐Monsoon season (01 Feb 2018 to 28 Feb 2018) from 49.4 to 60.4 dB (A) during daytime and 38.8 to 50.4 dB (A) during night time. Table 19: Noise Quality Results of the Study Area (01 Feb 2018 to 28 Feb 2018)

Noise Standards of Noise Level Noise Level db(A) Category of Day dB Night dB Sr.No. Location DOS Area (A) (A) Day (Ld) Night (Ln) Salt Pan Near 01.02.2018 51.4 40.6 1 Rampar Residential 55 45 Salt Pan Near 2 Chandrapar 04.02.2018 52.8 41.4 Village Residential 55 45 3 Deendayal Port 08.02.2018 Commercial 65 55 58.4 50.2 4 Khari RD 12.02.2018 Residential 55 45 49.4 41.6 5 Shinay 16.02.2018 Residential 55 45 51.4 40.6 6 Tuna 19.02.2018 Residential 55 45 50.2 38.8 7 Gandidham 24.02.2018 Commercial 65 55 60.4 50.4 8 Kasez Township 27.02.2018 Residential 55 45 52.2 41.4 *DOS: Date of Sampling

Residential Area: In residential area, Kasez Township noise level is 52.2 dB(A) during day time and 41.4 dB(A) recorded during night time in non‐Monsoon during the study period Day time and night time noise level within the residential area are well within the prescribed limit. 3.2.7 Result of Comparison with earlier collected Noise Quality Data (2012-13):

Ambient Noise Quality Data (2012-2013) Parametrs Leq (day) Leq (night) Max 58.6 50.5 Min 41.2 38.8

Mantec Consultants Pvt. Ltd. Page 67 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Ambient Noise Quality Data (2018) Parametrs Leq (day) Leq (night) Max 60.4 50.4 Min 49.4 40.6

From the above, it has been observed that maximum value of noise has been increased by 1.8 dB (A) during day time and 0.1 dB (A) during night time. These values have been found well within the prescribed standard after the incremental concentration.

Figure 19: Noise Quality Monitoring Photographs 3.3 Water Environment 3.3.1 Selection of Sampling Locations

Water quality within the study area was established through monthly monitoring of physico‐chemical and bacteriological characteristics of water sources at eight locations which have been tabulated in Table-20 and the sampling location have been depicted in Figure-20. All the sampling locations are present within the Deendayal Port Trust area.

Table 20: Location of Water Quality Stations Location Location Latitude Longitude Code Shinai Lake 23° 2'24.61"N 70° 3'42.80"E SW1

Adisar Pond Tirupati Nagar 23° 4'3.86"N 70° 4'56.70"E SW2

23° 6'5.37"N 70° 7'17.82"E SW3 Sang River near Galpadar 22°58'23.30"N 70° 1'50.32"E SW4 Lake near Sanghad

Mantec Consultants Pvt. Ltd. Page 68 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

22°57'14.43"N 70° 1'49.06"E SW5 Pond near Chandrapar

SW6 Pond near Mithi Rohar 23° 6'24.77"N 70° 9'59.82"E 22°58'3.98"N 70° 6'12.00"E SW7 Nakti Creek near Tuna Port Near Oil Jetty 23° 1'34.97"N 70°13'17.00"E SW8 Ground Water Monitoring Locations Location Location Latitude Longitude Code Gadhidham 23° 4'15.42"N 70° 7'59.81"E GW1

Kasez Township 23° 1'54.65"N 70° 7'57.90"E GW2

Mantec Consultants Pvt. Ltd. Page 69 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 20: Surface & Ground Water Sampling Location

Mantec Consultants Pvt. Ltd. Page 70 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.3.2 Methodology

Samples were collected from all the sampling locations and analyzed for relevant physical, chemical. Collection and analysis of these samples was carried out as per established standard methods and procedures for the examination of water and relevant IS Codes. This report presents data for the period (1 Feb 2018 to 28 Feb 2018).

The samples were analyzed for selected physicochemical parameters to establish the existing water quality of the study area. Samples were collected, preserved and analyzed as per methods given in the Standard Methods for the Examination of Water.

Analysis of parameters like temperature, pH, dissolved oxygen and alkalinity were carried out at the sampling stations immediately after collection of samples with the help of Field Analysis Kits. Parameters like Calcium, Magnesium, Chloride, sodium, Potassium, Sulphate, Phosphate, Nitrate, Ammonical nitrogen were analyzed in lab. 3.4 Water Quality of the Study Area (Surface water & ground Water) Ground Water

Sl. No. Parameters Units Gadhidham Kasez Township

1 Colour Hazen <5 <5 2 Odour _ Agreeable Agreeable 3 Taste _ Not Done* Not Done* 4 Turbidity NTU 1.2 1.8 5 pH _ 7.42 7.64 6 Temperature °C 24 23 7 Conductivity µmhos/ cm 546 654

8 Alkalinity as CaCO3 mg/L 218 184 9 Total Dissolved Solids mg/L 368 432 Total Hardness as 10 CaCO3 mg/L 462 384 11 Calcium as Ca mg/L 137.6 98.4 12 Magnesium as Mg mg/L 28.6 35.5 13 Chloride as Cl mg/L 128 152

14 Phosphate as PO4 mg/L 0.28 0.34

15 Nitrate as NO3 mg/L 3.20 2.40

Mantec Consultants Pvt. Ltd. Page 71 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

16 Sulphate as SO4 mg/L 22 30 17 Fluoride as F mg/L 0.28 0.36 18 Phenolic Compound mg/L <0.001 <0.001 19 Copper as Cu mg/L <0.01 <0.01 20 Cadmium mg/L <0.001 <0.001 21 Mercury as Hg mg/L <0.001 <0.001 22 Selenium as Se mg/L <0.01 <0.01 23 Total Arsenic as As mg/L <0.01 <0.01 24 Lead as Pb mg/L <0.01 <0.01 25 Zinc as Zn, Max mg/L 0.38 0.42 26 Chromium as Cr+6 mg/L <0.05 <0.05 27 Aluminium as Al mg/L <0.03 <0.03 28 Manganese as Mn mg/L <0.02 <0.02 29 Boron as B mg/L 0.24 0.42 30 Iron as Fe mg/L 0.14 0.22 31 Salinity %o 0.12 0.14 32 Sodium as Na mg/L 38 46 33 Potassium as K mg/L 4 6 34 Dissolved Oxygen mg/L NA NA 35 BOD mg/L NA NA 36 COD mg/L NA NA 37 Total Coliform MPN/100ml Absent Absent 38 Faecal Coliform MPN/100ml Absent Absent

Mantec Consultants Pvt. Ltd. Page 72 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Surface water

Table 21: Water Quality data (1 Feb 2018 to 28 Feb 2018)

Adisar Pond Sang River Pond Near Nakti Creek Lake Near Pond Near Near Oil Sl. No. Parameters Units Shinai Lake Near Tirupati near Mithi Near Tuna Sanghad Chandrapar Jetty Nagar Galpadar Rohar Port 1 Colour Hazen <5 <5 <5 <5 <5 <5 <5 <5 2 Odour _ Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable 3 Taste _ Not Done* Not Done* Not Done* Not Done* Not Done* Not Done* Not Done* Not Done* 4 Turbidity NTU 4.2 3.8 4.6 5.2 3.6 5.4 3.0 2.8 5 pH _ 7.85 7.74 7.83 7.64 7.74 7.68 8.06 8.12 6 Temperature °C 22 21 20 22 23 21 22 20 7 Conductivity µmhos/ cm 867 872 768 1026 806 862 62480 58264 Alkalinity as 8 CaCO3 mg/L 156 208 172 198 126 134 228 185 Total Dissolved 9 567 499 667 524 560 40612 37872 Solids mg/L 563 Total Hardness as 10 CaCO3 mg/L 458 268 316 386 302 328 1708 1946

11 Calcium as CaCO3 mg/L 324 132 214 246 184 224 428 458 Magnesium as 12 CaCO3 mg/L 134 94 102 140 118 104 1280 1488 13 Chloride as Cl mg/L 94 82 68 80 86 84 21400 22400

14 Phosphate as PO4 mg/L 0.18 0.24 0.14 0.18 0.16 0.12 0.06 0.06

15 Nitrate as NO3 mg/L 5.20 4.82 3.40 7.4 4.2 3.6 0.096 0.114

16 Sulphate as SO4 mg/L 38 40 32 36 52 46 3400 4000 17 Fluoride as F mg/L 0.76 0.62 0.68 0.72 0.58 0.68 0.84 0.77 Phenolic 18 Compound mg/L <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 19 Copper as Cu mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 20 Cadmium mg/L <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

Mantec Consultants Pvt. Ltd. Page 73 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

21 Mercury as Hg mg/L <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 22 Selenium as Se mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 23 Total Arsenic as As mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 24 Lead as Pb mg/L <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 25 Zinc as Zn, Max mg/L 0.38 0.42 0.36 0.34 0.44 0.46 0.38 0.44 26 Chromium as Cr+6 mg/L <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 27 Aluminium as Al mg/L <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 28 Manganese as Mn mg/L <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 29 Boron as B mg/L 0.24 0.42 0.38 0.36 0.38 0.44 0.52 0.48 30 Iron as Fe mg/L 0.14 0.22 0.18 0.22 0.16 0.21 0.23 0.16 31 Salinity %o 0.16 0.14 0.12 0.14 0.15 0.15 38.6 36.4 32 Sodium as Na mg/L 64 58 48 74 62 56 13900 14700 33 Potassium as K mg/L 8 6 4 10 8 6 420 460 34 Dissolved Oxygen mg/L 5.2 4.6 5.8 5.2 4.4 6.2 4.8 5.2 35 BOD mg/L 8.6 15.0 9.4 10.4 8.2 9 7.0 8.0 36 COD mg/L 26 45 28 32 24 28 22 26 37 Total Coliform MPN/100ml 2546 2842 2480 2664 2750 2516 3018 3264 38 Faecal Coliform MPN/100ml 1018 1136 992 1065 1100 1006 1207 1306

Mantec Consultants Pvt. Ltd. Page 74 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Non-Monsoon Season (01 Feb 2018 to 28 Feb 2018);

Temperature (oC) Surface water temperature ranged from 20oC. to 23oC. PH The pH values range from7.64 to 8.12 at all the stations, which indicate that the marine water is marginally alkaline within the study area. Dissolved Oxygen (DO) Dissolved Oxygen content of the surface water at different stations ranged from 4.4 to 6.4 mg/l during the sampling period. This may be due to the consumption of oxygen due to organic matter and respiration by the benthic species. Constant mixing results in the absence of any significant variation in salinity among the sites.

Calcium The calcium concentration ranged from 132 to 458 mg/l as CaCO3 at various sampling location covered as part of the study.

Magnesium The Magnesium concentration ranged from 94 to 1488 mg/l as CaCO3 at various sampling location covered as part of the study.

Sodium The sodium concentration ranged from 48 to 74 mg/l at various sampling location covered as part of the study of surface water (fresh). However, Na concnetrarions in the creek water found in the range of 13900 to 14700 mg/l.

Chloride The concentration of chloride ranged from 68 to 94 mg/l at various sampling location covered as part of the surface water (fresh) study. However, Chloride concnetrarions in the creek water found in the range of 21400 to 22400 mg/l.

Nitrate The concentration of nitrate ranged from 3.6 to 7.4 mg/l at various sampling location covered as part of the surface water (fresh) study.

Mantec Consultants Pvt. Ltd. Page 75 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.4.1 Result of Comparison with earlier collected Water Quality Data (2012-13);

Water quality data (2012-13)

S.No Parameters Max Min 1 Temperature 2 PH 8.28 7.84 3 Salinity 43.2 38.3 4 Dissolved Oxygen (mg/lit) 6.9 4.7 5 Electrical Conductivity (mS/cm) 60.9 55.6 6 Calcium (mg/lit) 490 300 7 Magnesium (mg/lit) 1500 1000 8 Sodium (mg/lit) 12700 11800 9 Chloride (mg/lit) 23900 21200

10 Nitrate (mg/lit) 0.121 0.085

Water quality data (2018)

S.No Parameters Max Min 1 PH 8.12 7.68 2 Salinity (%) 38.6 0.12 3 Dissolved Oxygen (mg/lit) 6.2 4.4 4 Electrical Conductivity (mS/cm) 62.48 0.806 5 Calcium (mg/lit) 458 132 6 Magnesium (mg/lit) 1488 94 7 Sodium (mg/lit) 14700 48 8 Chloride (mg/lit) 22400 68

9 Nitrate (mg/lit) 7.4 0.096

From the above, it has been observed that no significant difference in the values of PH, Salinity, Sodium, Chloride & Nitrate has been found in creek water samples. All values have been found well within the prescribed standard of CPCB.

Mantec Consultants Pvt. Ltd. Page 76 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.4.2 Physico-chemical & biotic components of water:

A. Highly turbid water around the project site: Physico-chemical & biotic components of highly turbid water is tabulated below.

Sl. No. Parameter Units of Measurements Value (Surface) Value (Bottom) 1 Temperature oC 30.1 29.7 2 pH ‐ 8.26 8.26 3 Conductivity mS/cm 57.2 57.8 Total Suspended 4 mg/l 284 298 Solids 5 Dissolved Oxygen mg/l 4.4 4.6 6 Calcium mg/l 390 370 7 Magnesium mg/l 1400 1200 8 Chloride mg/l 21300 20200 9 Sodium mg/l 12100 11900 10 Potassium mg/l 420 400 11 Sulphate mg/l 3200 3000 12 Phosphate mg/l 0.062 0.058 13 Nitrate mg/l 0.092 0.089 14 Ammonical nitrogen mg/l 0.023 0.022 15 Salinity ‰ 38.5 36.5 16 Light Penetration cm 22 ‐ 17 Oil and Grease mg/l 6.5 4.1

Density of phyto‐plankton & zoo‐plankton has ben observed in highy turbid water was 5408 nos/lit and 211 nos/lit.

B. Adjacent clear water: Pysio‐chemical & biotic components of clear water is given below table

Sl. Parameter Units of Measurements Value (Surface) Value(Bottom) No. 1 Temperature oC 30.6 30.2 2 pH ‐ 8.29 8.29 3 Conductivity mS/cm 56.1 55.9 Total Suspended 4 mg/l 98 103 Solids 5 Dissolved Oxygen mg/l 6 6.2 6 Calcium mg/l 400 390 7 Magnesium mg/l 1200 1100 8 Chloride mg/l 21500 21000 9 Sodium mg/l 12800 12700

Mantec Consultants Pvt. Ltd. Page 77 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

10 Potassium mg/l 420 400 11 Sulphate mg/l 3500 3200 12 Phosphate mg/l 0.049 0.046 13 Nitrate mg/l 0.099 0.094 Ammonical 14 mg/l 0.013 0.009 nitrogen 15 Salinity ‰ 38.8 37.9 16 Light Penetration cm 27 - 17 Oil and Grease mg/l 6 4.3

Density of phyto‐plankton & zoo‐plankton has ben observed in highy turbid water was 5890 nos/lit and 300 nos/lit. C. Comparison of Pysico-chemical & biotic characterstics (Highly Turbid water & adjacent clear water): It has been observed that value of conductivity, Total Suspended Solids, Magnesium, Phosphate, Ammonical Nitrogen and Oil & Grease in high turbity water was found 1.1 mS/cm, 186 mg/lit, 200 mg/lit, 0.013 mg/lit, 0.01 mg/lit & 0.5 mg/lit respectively higher than the adjacent clear water and density of phyto‐planktom & zoo‐planktom was found 482 & 89 nos/lit lower than adjacent clear water. 3.5 Land Environment 3.5.1 Topography

Kandla is situated at the eastern end of the Gulf of Kutch and western bank of the Kandla Creek, on the west coast, north of Mumbai. Founded in 1952, and declared a major port in 1964, Kandla is a natural harbour and serves as an effective shelter, even in stormy weather. Kandla’s natural advantage is its dry weather and mild monsoon, which minimizes loss of man‐days, as well as damage to the cargo. The Port of Kandla is located on the Gulf of Kutch on the northwestern coast of India some 256 nautical miles southeast of the Port of Karachi in Pakistan and over 430 nautical miles north‐ northwest of the Port of Mumbai (Bombay). Topography at the site location is generally flat with average ground level of about 6.5 m CD. Topsoil appears marshy. The 6th major port in India, Kandla is a key one in the region, and plays a major role in the country’s international trade. Having notched up a string of successes, it has emerged as a forerunner, and has carved a niche for itself, by its steady growth and economy of operations. Maximum output, excellent infrastructure, all‐round services

Mantec Consultants Pvt. Ltd. Page 78 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

and cost‐effectiveness have all made Kandla the No.1 Indian port among 11 major ports in the country. 3.5.2 Land Use Classification of the Study Area

The land use/ land cover map has been prepared based on Satellite Imagery for the year 2011. Land Use Classification of the study area with respect to major land use categories are presented in Table 22 and shown in Figure 21 given below,

Table 22: Land Use Classification based on Satellite Image

S.N. Land use Type Area in Ha Percentage (%) 1 Settlement 5171 7.8 2 Marshy Land 5251 7.9 3 Vegetation 9761 14.7 4 Mangrove 7431 11.2 5 Agriculture 6851 10.3 6 Barren Land 5081 7.7 7 Water Bodies 18321 27.6 8 Salt Pan 8431 12.7 Total 66298 100 The maximum area covered in the study area falls under Water bodies (27.6%). Study area comprises of water flowing through creek, merging into sea at Gulf of Kutch. There is 14.7 % Vegetation cover which is scattered throughout the area. Salt pan comprises of 12.7 % land in the study area. The presence of Mangroves is restricted to costal area comprising of 11.2%. Agricultural land is 10.3% present near the villages in the study area. As the study area is present on the sea cost, there is presence of Marshy land of (7.9 %). Area under Settlement and Barren land is 7.8% and 7.8 % respectively.

Mantec Consultants Pvt. Ltd. Page 79 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 21: Land Use/ Land Cover of the study area at Kandla 3.5.3 Soil The sub‐soil profile is shown in the diagram below:

Mantec Consultants Pvt. Ltd. Page 80 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

As could be seen, the sub‐soil profile consists of vey soft to soft greyish clay up to –14.7 m, a stiff to very stiff grey silty clay up to –24.7 m. A hard reddish brown silty clay is met below –24.7 m up to ‐27.7 m. Very dense yellowish brown silty sand is found up to – 35.7 m. Between ‐35.7 to ‐39.7 hard greyish brown clay is found. Very dense yellowish silty sand is found below ‐39.7 m and the bore hole is terminated at ‐42.7m with the same composition being observed.

Mantec Consultants Pvt. Ltd. Page 81 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.5.3.1 Selection of Sampling Locations Sampling and analysis of soil samples were undertaken at eight locations within the study area, as a part of primary data generation. The soil sampling locations were identified primarily based on the local distribution of vegetation and commercial zones of Kandla Port.

The name of various sites from where soil samples were collected has been tabulated in the Table-24 and depicted in Figure-21.

Table 23: Soil Sampling Location of the Study Area

S.No Code Location Latitude Longitude 1 S1 Chandrapar 22°57'30.81"N 70° 1'38.12"E 2 S2 Sanghad 22°58'38.19"N 70° 2'27.23"E 3 S3 Kandla Port 23° 1'17.22"N 70°12'47.47"E 4 S4 Khari RD 23° 4'34.36"N 70°10'16.33"E 5 S5 Bharapar 23° 0'27.36"N 70° 5'56.32"E 6 S6 Tuna 22°59'32.29"N 70° 4'52.36"E 7 S7 Gandhidham 23° 4'43.38"N 70° 7'46.72"E 8 S8 Kasez Township 23° 2'6.33"N 70° 8'12.12"E

Mantec Consultants Pvt. Ltd. Page 82 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 22: Soil Sampling Locations at Kandla

Mantec Consultants Pvt. Ltd. Page 83 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.5.3.2 Methodology The soil samples were collected during the pre‐monsoon season of the study period (01 Feb 2018 to 28 Feb 2018). The samples collected from the all locations are homogeneous representative of each location. At random 8 sub locations were identified at each location and soil samples were collected from up to 30 cm depth below the surface. Sample from each location was uniformly mixed before homogenizing the soil samples. The samples were filled in polythene bags, labeled in the field with number and site name and sent to laboratory for analysis.

3.5.3.3 Physiochemical Characterization of Soil Physical Properties The average results of physical analysis of the soil samples collected during pre‐ monsoon season (01 Feb 2018 to 28 Feb 2018) are presented in Table‐24.

Table 24: Physical Characteristics of the Soil in the Study Area

S.No Location Name Texture Sand (%) Silt (%) Clay (%)

Chandrapar SQ1 Sandy Loam 70 10 20

SQ2 Sanghad Sandy Loam 68 12 20

SQ3 Kandla Port Sandy Loam 72 8 20

SQ4 Khari RD Sandy Loam 72 10 18

SQ5 Bharapar Sandy Loam 70 12 18

SQ6 Tuna Sandy Loam 68 10 22

SQ7 Gandhidham Sandy Loam 70 8 22

SQ8 Kasez Township Sandy Loam 69 11 20

Monitoring data shows that the texture of soil at all locations is Sandy Loam. The monitoring sites have sand ranging from 68% to 72% in soil samples. Silt content varies from 8% to 12%, while Clay content varies from 18% to 22% in the soil samples.

Mantec Consultants Pvt. Ltd. Page 84 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chemical Properties The average results of chemical analysis of the soil samples are presented in Table 23 below.

Mantec Consultants Pvt. Ltd. Page 85 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Table 25: Result of Analysis of Soil in the Study Area (01 Feb 2018 to 28 Feb 2018) 1 2 3 4 5 6 7 8 Location Deendayal Near Khari Kasez Chandrapar Sanghad Bharapar Tuna Ghandidham (Sample ID) Port Road Township Sr. No. Parameters Units Value Value Value Value Value Value Value Value 1 pH - 8.02 7.42 8.14 7.56 7.36 8.16 7.48 7.26 2 Bulk Density gm/cm3 1.42 1.48 1.45 1.38 1.42 1.52 1.35 1.44 3 Conductivity micro mhos/cm 7348 1424 5372 1458 1428 3352 4346 1432 4 Moisture % 12 10 12 14 10 11 14 13 5 WHC % 18.2 16.4 15.8 17.6 16.2 18.4 15.2 17.8 Sandy Sandy Sandy Sandy Sandy 6 Texture - Sandy Loam Sandy Loam Sandy Loam Loam Loam Loam Loam Loam 7 Sand % 70 68 72 72 70 68 70 69 8 Clay % 10 12 8 10 12 10 8 11 9 Silt % 20 20 20 18 18 22 22 20 10 Sodium mg/100gm 44 36 42 38 40 36 46 40 11 Potassium mg/100gm 8.6 7.4 8.2 7.8 8.8 7.0 8.9 7.6 12 CEC meq/100gm 6.76 7.44 5.88 6.56 7.74 6.38 5.84 7.02 13 Nitrogen mg/100gm 16.8 14.6 16.2 15.8 14.8 16.2 17.4 15.6 Organic 14 % 0.88 0.72 0.94 0.78 0.87 0.69 0.92 0.76 Matter 15 Phosphorous mg/100gm 0.86 0.78 0.92 0.88 0.74 0.82 0.84 0.86 16 Calcium meq /100gm 3.6 4.8 4.6 3.4 4.2 3.6 4.4 3.8 17 SAR meq /100gm 1.05 0.81 0.92 0.95 0.94 0.86 1.02 1.01 18 Magnesium meq /100gm 2.4 2.8 3.3 2.6 2.2 2.9 3.2 2.2

Mantec Consultants Pvt. Ltd. Page 86 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.5.4 Result of Comparison with earlier collected Soil Quality Data (2012-13):

Soil quality data (2012-2013) S.No Parameters Max Min 1 PH 8.97 7.12 2 Conductivity ( µmhos/cm) 7310 1428 3 CEC (meq/100g) 7.69 4.67

4 Nitrogen( mg/100gm) 14.5 12.6 5 Phosphorous (mg/100gm) 0.89 0.62 6 Potassium (mg/100gm) 7.8 5.8

Soil quality data (2018) S.No Parameters Max Min 1 PH 8.16 7.26 2 Conductivity (µmhos/cm) 7348 1424 3 CEC (meq/100g) 7.74 5.88

4 Nitrogen( mg/100gm) 17.4 14.6 5 Phosphorous (mg/100gm) 0.92 0.74 6 Potassium (mg/100gm) 8.9 7.0

From the above, it has been observed that there are no any incremental concentrations found except conductivity and all values have been found within the prescribed limited.

Soil Quality Monitoring Photographs

Mantec Consultants Pvt. Ltd. Page 87 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.6 Biological Environment Living things are organize in to natural communities with mutual dependencies among their members, and they show various responses and sensitivities to the outside influences. However, the process of rapid development and industrialization has marked some prominent questions about survival of the flora and fauna. Fortunately, global awareness during past few years has been augmenting and worldwide programs for wild life conservation have been formulated. The worldwide-accepted concept of ‘Sustainable development’ has given vision of eco-friendly project execution. It is imperative to study the ecology of the area and essentially, how organisms are dependent on the area in terms of resource utilization, habitat etc, also how organisms contribute to sustain the ecology of the area. Secondly we need to find out how the proposed project is going to affect the biological environment. Therefore, the present study has been undertaken to assess the impact of the proposed projects on biological environment of the project site and surrounding area within 10 km radius. Accordingly, mitigation measures are evolved to sustain the biological diversity. In general biological environment is represented by flora and fauna. Flora constitutes the herbs, shrubs and trees and fauna constitutes the mammals, birds, reptiles, arthropods, amphibians, fishes etc. The Marine biodiversity impact assessment report and management plan was prepared by GUIDE and approved by NIO and same has been accepted for grant of Environmental Clearance of 7 projects of Stage-1 by Environmental Clearance Letter no-11-82/2011-IA III dated 19/12/2016.

3.6.1 Objectives The ecological study of the area has been conducted in order to understand the existing status of the flora and fauna to generate baseline information and evaluate the possible impacts on biological environment. The present study highlights the various issues pertaining to floristic diversity and faunal wealth in the surrounding area upto 10 km radius of the proposed project sites.

3.6.2 Methodology of the Study The baseline study for existing ecological environment was carried out during pre‐ monsoon season (01 Feb 2018 to 28 Feb 2018). A participatory and consultative approach was followed. Field visits were undertaken for survey of the vegetation and

Mantec Consultants Pvt. Ltd. Page 88 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

animals in the study area. The study area has been divided in to two parts, viz., the core area consisting of project site, and the buffer area as the 10 km radius of the project site.

For the purpose of surveying the vegetation, quadrates were laid to record phyto‐ sociological features of the vegetation. Detailed notes on ecological features, including the habitat types were also taken along the selected locations. The flora and fauna in the study area were inventorised.

Besides measuring these parameters, other biodiversity aspects in the form of endemic status, conservation status and life form have been enumerated for all the plant species found in the area during ecological survey, Red Data Books of the Botanical survey of India have been screened to verify their conservation status. For wild animal species, schedule of the Wildlife Protection Act (1972) has been screened. The information was also collected from secondary sources for authentication of the data from Deputy Conservator of Forests, Bhuj and Zoological Survey of India, Jodhpur.

3.6.3 Biogeography and Physiography of the area The proposed projects are situated at Kandla in Katchchh districts on the Northern part of the Gulf of Kachchh in the State of Gujarat. As per the bio‐geographical classification of Rodgers and Panwar, 1988, the project area at Kandla comes under West Coast of India however the study area consists of parts of Indian deserts i.e. the Kutch region. This area falls under North‐west arid zone of agro‐climatic regions classified by the Gujarat Ecology Commission, 1996. Nearly 25% of the western part is arid where average rainfall is varying from 300‐400mm. Soil of the area varies from deltaic alluvium to coastal alluvium, sandy loam. The soil is saline and salinity is due to the clayey soil which prevents the percolation of water. Winter is severe and the summer is harsh, because the Tropic of Cancer passes through the nearby areas.

3.6.4 Forests & Vegetation of the area Biogeographically, Gujarat can be classified in to four major zones viz. the Indian desert, the Semi‐arid, the Western Ghats and the Coastal areas. Each zone differs from each other in terms of floral and faunal assemblages. Despite limited forest cover, the state has a remarkably rich biodiversity due to rich ecosystem diversity. The forests of the state are broadly classified in to four major type groups, viz. tropical dry deciduous,

Mantec Consultants Pvt. Ltd. Page 89 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

tropical moist deciduous, tropical thorn and littoral and swamp forests (Champion & Sheth, 1968). The katch area mainly possesses the Northern tropical thorn forests (6B). The coastal

area along the Kandla has Mangrove forests (4B/TS2) and Mangrove scrub forests

(4B/TS1).

1. Northern tropical thorn forests Such forests can be seen commonly in the Kutch region in the arid and semi‐arid zones due to very less rainfall. The vegetation is very thin consisting of xerophytic trees and shrubs. The trees are generally 5‐10m in height. The typical trees of the scrub forests are Acacia nilotica, A. Senegal, Balanites aegyptica, Capparis sepiaria, Dichrostachys cineria, Zizyphus nummularia, etc.

2. Mangrove & Mangrove scrub forests Mangroves are the salt tolerant forest ecosystem of tropical and subtropical intertidal regions of the world. Where conditions are sheltered and suitable, the mangroves may form extensive and productive forests, which are the reservoir of a large number of species of plants and animals. The role of mangrove forests in stabilizing the shoreline of the coastal zone by preventing soil erosion and arresting encroachment on land by sea is well recognized thereby minimizing water logging and formation of saline banks. These can be seen in 8‐10 km wide zone along the coastline at some parts. This vegetation can also be divided in to salt marshy zone and low lying muddy shores and sandy saline areas. These plants can be seen in the coastline in patchy forms. It can be divided in to salt marshy zone and low lying muddy shore and sandy saline areas. Diversity of the mangroves in this area is very poor, as only genus Avecennia with two species A. marina & A. officinalis were observed.

3. Man made forests The growth of Casurina equisetifolia and Prosopis julifera has taken the shape like manmade forests along the coasts strips and at deserts boarders of Kutch.

3.6.4.1 Floral diversity of the project Area

Mantec Consultants Pvt. Ltd. Page 90 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

The vegetation of study area of the Kandla project was surveyed according to above given methodology. The observations made in the flora of the study area reveal that the diversity and affinities of the flora of the region has approximately 71 taxa of flowering plants belonging to 28 families. It is evident from the study that, the study area is showing dry vegetation. According to the growth habit these species are distributed as: 12 tree species (17%), 10 shrub species (14%), 47 herb species (66%), and 02 mangroves species (3%) Table-26 & Figure-23. The commonly occurring species are Acacia catechu Acacia modesta, Carisa spinarum, Dalbergia sissoo, Dodonia viscosa, Pistacia chinensis, Bombax ceiba, Woodfordia fruiticasa, etc. Table-26 represents the list of flora recorded from the study area.

Table 26: Analysis of the Flora of the Study Area

S.No. Habitat No. of Species Family Percentage 1. Trees 12 09 17 2. Shrubs 10 09 14 3. Herbs 47 14 66 4. Mangrove 02 01 03 Total 71 28 100

2, 3% 12, 17%

Herbs 10, 14% Shrubs

Trees

47, 66% Mangroves

Figure 23: Graphical Representation of the Flora of the Area

3.6.4.2 Terrestrial vegetation Terrestrial flora of the area is mostly xerophytic. It consists of species of Acacia, Azadirachta, Capparis, Cassia, Crotalaria, Euphorbia, etc. Among the terrestrial vegetation trees, shrubs & herbs are inventorised.

Mantec Consultants Pvt. Ltd. Page 91 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Table 27: Flora Recorded From the Study Area

S.No. Species Name Family Habit Vernacular name 1 Acacia catechu (L.f) Willd. Mimosaceae Tree Kher 2 Acacia senegal (L) Willd Mimosaceae Tree/Shrub Gorad 3 Achyranthes aspera L. Amaranthaceae Herb Aghedi Alysicarpus longifolius (Rottl.ex Spreng.)Wight & 4 Arn Papilionaceae Herb Ubho sameravo 5 Apluda mutica L. Poaceae Herb Bhangoru 6 Avicennia marina Aviceniaceae Shrub - 7 Avicennia officinalis Aviceniaceae Shrub - 8 Azadirachta indica A. Juss. Meliaceae Tree Limbdo 9 Barleria prionitis L. Acanthaceae Shrub Pilo kantasherio Blepharis maderaspatensis 10 (L) Heyne ex Roth Acanthaceae Herb Utingan Blepharis repens (Vahl) 11 Roth Acanthaceae Herb Zinku utingan 12 Blumea lacera (Burm.f.) DC. Asteraceae Herb Burando,kapurio Satodi, 13 Boerhavia diffusa L. Nyctaginaceae Herb punarnava Butea monosperma (Lam.) 14 Taub Papilionaceae Tree Khakhro Capparis decidua (Forssk.) 15 Edgew. Capparidaceae Shrub Kerda 16 Cassia absus L. Caesalpiniaceae Herb Chimed 17 Cassia auriculata L. Caesalpiniaceae Shrub Aval 18 Cassia occidentalis L. Caesalpiniaceae Herb Kasundri 19 Cassia pumila Lam. Caesalpiniaceae Herb Nani chimed 20 Cassisa tora L. Caesalpiniaceae Herb Kuvadio 21 Cenchrus ciliaris L. Poaceae Herb Dhraman ghas Chrysopogon fulvus Draf,khad- 22 (Spreng) Chiov. Poaceae Herb sundhiu Clerodendrum multiflorum 23 (Burm.f.) Kuntze Verbenaceae Tree Arani 24 Commelina benghalensis L. Commelinaceae Herb Motu shishmuliu Commiphora wightii (Arn). 25 Bhandari Burseraceae Shrub Gugal Crotalaria medicaginea 26 Lam. Papilionaceae Herb Adabau methi Crotalaria orixensis Rottl.ex 27 Willd. Papilionaceae Herb Tripani fatakiya

Mantec Consultants Pvt. Ltd. Page 92 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Cymbopogon schoenanthus 28 (L) Spreng. Poaceae Herb Roshdo Dactyloctenium aegyptium 29 (L.) Willd. Poaceae Herb Taradi, aro-taro Dichanthium amulatum 30 (Forssk.) Stapf. Poaceae Herb Jinjavo Diospyros melanoxylon 31 Roxb. Ebenaceae Tree Timru Enicostemnta axilare (Lam.) 32 Raynal Gentianaceae Herb Mamejavo Veladi, kali 33 Enolvuius alsinoides (L) L. Convolvulaceae Herb shankhavali Eragraostis tenella (L.) P. 34 Beauv. ex.Roem. & Schult. Poaceae Herb Bhumasi ghas 35 Eragrostis ciliaris (L.) R.Br. Poaceae Herb Marmar ghas 36 Eucalyptus globulus Labill Myrtaceae Tree Nilgri Euphorbia nitula Buch- 37 Ham. Euphorbiaceae Shrub Thor 38 Euphorbin heterophyila L. Euphorbiaceae Herb Ubhi duheli Glassogyne bidens (Retz.) 39 Alston Asteraceae Herb Kagsuva 40 Grewia tenax (Forssk.) Fiori Tiliaceae Shrub Dhaman Hibiscus lobatus (Murr.) 41 Kuntze Malvaceae Herb Tali Hotoptelea integrifolia Kanji, papadi, 42 Planch Ulmaceae Tree odo Indigofera cordifolia Heyne 43 ex Roth Papilionaceae Herb Vekar, bhakho Ipomoea coptica (L.) Roth ex 44 R.&S. Convolvulaceae Herb Zinki fudaradi 45 Jatropha curcas L. Euphorbiaceae Shrub Ratanjyot 46 Justicia simplex D.Don Acanthaceae Herb Khadshelio Lamba pan no 47 Leucas longifolia Benth. Lamiaceae Herb kubo Leucas plukenetii (Roth) 48 Spreng. Lamiaceae Herb Doahi no kubo Madlnica latifolia (Koen.) Mac. Bride var. latifolia 49 (Roxb.) Chevalier Sapotaceae Tree Mahudo Manilkara hexandra (Roxb) 50 Dubard. Sapotaceae Tree Rayan Maytenus senegalensis 51 (Lam.) Exell Celastraceae Shrub Vikro 52 Neuracanthus Acanthaceae Herb Gandhrea

Mantec Consultants Pvt. Ltd. Page 93 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla sphaerostachyus (Nees) Dalz. Peristrophe paniculata 53 (Forssk.) Brummitt Acanthaceae Herb Kali aghedi Pulicaria wightiana (DC) 54 C.B. Clarke Asteraceae Herb Son fuldi 55 Pupalia lappacea (L.) Juss. Amaranthaceae Herb Gadar zipto Rhus mysurensis Heyne ex 56 Wight & Arn. Anacardiaceae Shrub Kasedi, dasan 57 Rhynchosia minima DC. Papilionaceae Herb Nani khatvel Seluma nervosum (Rotl.) 58 Stapi Poaceae Herb Dabh suliyu Senna sunitensis (Burn f.) 59 Irvin & Barneby Caesalpiniaceae Tree Moti aval 60 Sida acuta Burm.f. Malvaceae Herb Kantalo bala Sporobolus indicus var.diander (Retz.) Jovet & Velari marmar 61 Guedes Poaceae Herb ghas 62 Tamarindus indica L. Caesalpiniaceae Tree Amli Tephrosia candida Roxb. ex. 63 DC. Papilionaceae Herb Safed sarpankho Tephrosia purpurea (L) 64 Pers. Papilionaceae Herb Sarpankho Tephrosia strigosa (Dalz.) 65 Sant. & Mahesh Papilionaceae Herb Zinko sarpankho 66 Tephrosia villosa (L) Pers. Papilionaceae Herb Runchado Tetrapogon tenellus (Roxb.) Zinku chipatiyu 67 Chiov. Poaceae Herb ghas 68 Triumfetta rotundifolia Lam. Tiliaceae Herb Ziapto 69 Vernonia cinerea (L) Less Asteraceae Herb Sahdevi Ziziphus nummularia (Burm. 70 f.) Wight & Arn. Rhamnaceae Shrub Chani bordi 71 Zornia gibbosa Span Papilionaceae Herb Sonvel

Mantec Consultants Pvt. Ltd. Page 94 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Calotropis procera Acacia nilotica

Datura metel Cassia tora Plate 1: Floral species found in the study area

3.6.4.3 Aquatic Vegetation The Marine water of Gulf of Kutch and its creeks like Kandla creek, Nakti creek and Khori creek are providing the suitable habitat for marine vegetation. The Gulf abounds in marine wealth and is considered as one of the biologically rich marine habitat along the west coast of India.

The marine vegetation is highly varied, which includes sand dune vegetation, mangroves, sea grasses, macrophytes and phytoplankton. The dominant species of sand dune flora are Euphorbia caudicifolia, E.nerifolia, Aloevera sp, Ephedra foliata, Urochodra setulosa, Sporobolus maderaspatenus, Eragrostis unioloides, Calotropis procera, Fimbristylis sp, Indigofera sp. and

Mantec Consultants Pvt. Ltd. Page 95 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Ipomoea spp. The common sea grasses found growing on the mud flats are Halophila ovata and H.beccarii.

The most common marine algal species are Ulva fasciata, U. reticulata, Enteromorpha intenstinalis, Dictyota sp, Hypnea musciformis, Sargassum tennerimum, S. ilicifolium, Gracilaria corticata, Cystocera sp, Padina tetrastomatica, Corallina sp, Laurencia sp, Caulerpa racemosa, C. peltata, Bryopsis sp, Turbinaria sp, Ectocarpus sp, Acanthophora sp, Chondria sp, and Codium sp.

The aquatic vegetation present in the area can be categorized as Marine vegetation and Maritime vegetation.

Marine vegetation: The study area covers a large area under marine water. It has algal vegetation of green and brown algae. Caulerpa, Ulva and Halimeda are common green algae while Sargassum, Turbinaria, Gracillaruia and Geladium are the brown algae species found in the marine water.

Maritime vegetation: The vegetation adjacent to the sea is called maritime vegetation; it varies in structure and ecology. It includes seashore vegetation, mangroves and salt marshes. a. Seashore vegetation: Seashores of the study area includes shrubby and herbaceous vegetation. Most of the plants on the shore are prostrate and xeromorphic in nature, e.g. Ipomoea sp. and Launea sarmentosa etc. The vegetation is gradually stable at a distance away from the tidemark with the stabilization of the soil. b. Mangroves vegetation: The Gulf has a vast intertidal area with rich biota. Sheltered bays, creeks and mud flats provide ideal sites for mangrove vegetation over an estimated area of about 1036 km2. The formations are of open scrubby type, with isolated and discontinuous distribution from Kandla- Navlakhi in the northeast to Jodia, Jamnagar, Sikka, Salaya and Okha in the southwest, as also at Pirotan, Positra, Dohlani and Dwarka. Vast stretches of mangroves also exist along the northern shore of the Gulf. The dominant species of mangroves are Avicennia marina, A. officinalis, Bruguiera parviflora, Bruguiera gymnorphiza, Rhizophora mucronata, R. apiculata, Ageiceros corniculata and Sonneratia apetata alongwith the associated species of Salicornia brachiata, Sueda fruticosa, Artiplex stocksii and a lichen, Rosella Montana.

Mantec Consultants Pvt. Ltd. Page 96 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla As far as the study area is concerned the mangrove vegetation along the Deendayal Port is very thin and patchy.

3.6.5 Fauna Fauna of Gujarat state shows a spectacular biological diversity due to the diversity in its ecosystems. The Faunal study for the proposed Deendayal Port Trust projects were carried out in 10 km radius of the project sites.

3.6.5.1 Fauna (Terrestrial & Aquatic) The information of important terrestrial animal groups such as birds, reptiles and mammals were collected by trekking inhabiting area, along the creeks, adjoining forest, nallahs and fields present in the impact zone. The species lists of animals recorded during this study are given below:

A. Mammals Eight species of mammals were recorded in the study area of DPT (Table-28). Through direct sighting 4 species were recorded, 4 species were recorded as per indirect evidence and through secondary sources from Forest and Wildlife Department and local villagers. All the species of mammals have been listed in various schedules of the Indian Wildlife (Protection) Act 1972 and‘commonly’ occur in the region.

Table 28: Mammals in the study area of Deendayal Port Trust Projects

S.No. Species Common Name Local name 1 Presbytis entellus Hanuman Langur Vandra entellus 2 Canis pallipes Wolf Varoo 3 Canis aureus aureus Asiatic jackal Shial 4 Canis bengalensis Indian fox Lonkadi 5 Herpestes auropunctatus Indian Mongoose Noriya 6 Sus scrofa cristatus Wild Boar 7 Funambulus pennanti Palm squirrel Kilkuri 8. Rattus rattus House rat Undur

B. Reptiles & Amphibians

Mantec Consultants Pvt. Ltd. Page 97 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Six species of reptiles were reported from the area. Out of these two were of under the lizard category and rests 04 were snakes. Two species of amphibians were also recorded. Table 29: - Amphibians & Reptiles of the Area

AMPHIBIANS : Sl. No Common Name Scientific Name 1. Skipping frog Rana cyanophlyctis 2. Common Indian Toad Bufo melanostictus REPTILES : Lizards & Snakes Snakes 1 Grass Shink Mabuya macularia 2 Indian Sand Boa Eryx johni 3 Rat snake Ptyas mucosus 4 Royal Snake Sphalerosophis diadema Lizards 5 Lizard Cyrtodactylus kachhensis 6 Gecko Hemidactylus leschenaulti

C. Marine Molluscs, Crustaceans & Annelidans From the study of marine aquatic environment eleven species of mollusca, seven species of shrimps (Prawn) Arthropodes and seven species of annelids were recorded.

Table 30: Molluscs, Crustaceans and Annelida of the area

S.NO. Phyllum SCIENTIFIC NAME 1. Mollusca Chiton peregrinus 2. Mollusca Diodora singaporensis 3. Mollusca Diodora funiculata 4. Mollusca Emarginula dilecta 5. Mollusca Clanculus ceylonicus 6. Mollusca Cypra moneta 7. Mollusca Bufonaria echinata 8. Mollusca Thais bufo 9. Mollusca Pyrene scripta 10. Mollusca Conus flavidus 11. Mollusca Dentalium longitrorsum 12. Arthopoda Parapenaeopis sculptilis 13. Arthopoda Parapenaeopis stylifera 14. Arthopoda Trachypenacus curvirostris 15. Arthopoda Metapenacus monoceros 16. Arthopoda Penaeus penicillatus 17. Arthopoda Penaeus semisulcatus

Mantec Consultants Pvt. Ltd. Page 98 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

S.NO. Phyllum SCIENTIFIC NAME 18. Arthopoda Penaeus latisulcatus 19. Annelida Aphrodita aculeata 20. Annelida Hermonia hystrix 21. Annelida Eunoe pallida 22. Annelida Lepidonotus tenuisetosus 23. Annelida Anaitides madeirensis 24. Annelida Nereis coutierei 25. Annelida Nereis parsica

D. Marine Fishes:

The proposed projects of Deendayal Port Trust are lying in the existing industrial area. Several jetties of DPT, IFFCO, Indian oil, fertilizer plant of IFFCO, etc. are lying in the close proximity to each other. Since Deendayal Port is one of the major port in India and major portion of the study area is occupied by Deendayal port and other operators, fishing activities are very limited in the study area. There are 19 fish landing centres in but there is no fish landing centre in the study area. As per the information collected from the department of fisheries office at Gandhidham, there is no fish pond as well, in the study area. However, small fishing activities with mechanized and traditional fishing crafts are operating from the Kandla creek. The major fish found in Kutch area are listed in the below table:

Table 31: List of Common Fish Species Found in the Area

Scientific Name Common Name Local Name Carcharhinus dussmieri White-cheek shark Ghari mushi Carcharhinus sorrah Spot Tail Shark Balda Scoliodon faticaudus Yellow dog sharki Sonmushi Rhynchobatus sp Showel-nose ray Ranja Dasyatis Sp Sting-ray Pakat Arius jella Black-fin sea cat fish Shingala Chirocentrus dorab Wolf herring Karali Sardinella fimbriata Fringe scale sardine Pedwa Sardinella longiceps Oil sardine Tarali Hilsa ilisha Indian shad Palla Stolephorus indicus White bait Katali Stolephorus indicus Indian anchovy Dindus Harpodon neherius Bombay duck Bombli Saurida tumbil Lizard fish Chor bombil

Mantec Consultants Pvt. Ltd. Page 99 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Coila dussumieri Anchovy Mandeli Epinephelus dicanthus Grouper Gobra Johnius dussumieri Croaker Dhoma Lepturacanthus savala Ribbon fish Bala Decapterus russeli Russell’s Scad Teli bangad Carangoides malabaricus Trevally Kat Bangada Leiognathus bindus Pony fish Kap Formio niger Black Pomphert Halwa Pampus argentius Silver Pomfret Saranga Rastreliger kanagurta Mackerel Bangada Scomberomorus Seer fish Surumi commersoni Auxis thazard Frigate mackerel Bugudi Katsuwonus pelamis Stripped Tuna Bugudi Thunnus tongol Long tail tuna Khavalya Mugil cephalus Grey mullet Botia Pesettodus ermei Halibut Zhipali Cyanoglossus spp Sole Gipti Prawns Metapenaeus dobsoni Yellow Prawn Polan Metapenaeus affinis Indian Prawn Kolabi Penaeus indicus Indian white Prawn Safed zinga Crabs Portunus pelagicus Blue crab Khekhada Portunus sanguinolentus Spotted crab Khekada Scylla cerrata Stone crab Chimbori

E. Domestic Animals The domestic animals are mainly mammals. The domestic animals found in the study area are listed in the Table-30.

Table 32: List of Domestic Fauna in the Study Area

S. No. Common Name Zoological Name 1 Cow Bos indicus 2 Dog Cains familieris 3 Goat Capra hircus 4 Horse Equus cabilus 5 Donkey Equus hermionus 6 Cat Felis domesticus

Mantec Consultants Pvt. Ltd. Page 100 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.6.5.2 Marine Ecology of the creek (Phytoplanktons, Zooplanktons & Benthos) Biological parameters are very important in the aquatic eco-system since they determine the productivity of a water body. Fish production is dependent on production of zooplanktons which in turn is dependent on the phytoplankton production or primary productivity. All these are related to physico-chemical characteristics of the water. Detailed marine ecological survey was conducted in the core area to understand the existing status of marine ecology in this area. Zooplanktons and phytoplanktons, were studied and presented in the following sections.

a. Phytoplanktons:

Phytoplanktons have long been used as indicators of water quality. Some species flourish in highly eutrophic waters while others are very sensitive to organic and/or chemical wastes. Phytoplankton’s form the pastures of the sea. These organisms are autotrophic in nature. The growth and multiplication of phytoplankton primarily depends on solar illumination, temperature and also on the availability of certain essential nutrients such as nitrates, phosphates, silicates, trace elements, etc. Phytoplanktons are suspended in the euphotic zone and they drift along with the ocean currents. They vary from place to place and from season to season and this variation is responsible for the organic production. The productivity of phytoplankton’s is directly responsible for the growth of zooplanktons in the water. Usually when phytoplankton’s reach the maximum intensity of growth, zooplanktons start growing. The productivity of phytoplankton’s declines attaining maximum growth because of the depletion of nutrients and grazing by zooplanktons. Thus, in this inter-relationship or food chain of the phytoplankton’s abundance is important as this is the first step of any food chain or food web. The benthic organisms and fishes are also dependent on planktons for their food. The abundance of phytoplankton’s at various locations in the study area is given in Table- 31.

Table 33: Co-Ordinates of Sampling Locations of Phytoplankton, Zooplankton and Benthic Meio Fauna

Sites Latitude Longitude Site I 23° 2' 39" N 70° 13' 7" E

Mantec Consultants Pvt. Ltd. Page 101 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Site II 23° 1' 12" N 70° 13' 13" E Site III 22° 58' 23" N 70° 12' 59" E Site IV 22° 57' 56" N 70° 13' 26" E Site V 22° 57' 50" N 70° 6' 40" E Site VI 22° 57' 42" N 70° 6' 45" E

Table 34: Phytoplankton abundance and density recorded at various sampling Sites (Unit: No. of cells/litre)

Name of S.No. Site1 Site2 Site3 Site4 Site5 Site6 groups 1 Biddulphia 590 500 650 680 600 580 2 Coscinodiscus 2200 2080 2200 2100 2000 2080 3 Dytilum 380 355 280 250 280 280 4 Fragillaria 980 900 980 890 800 800 5 Navicula 220 200 200 240 220 220 6 Nitzschia 120 155 140 120 120 120 7 Oscllatoria 120 120 120 80 88 80 8 Peridinium 320 300 340 300 280 280 9 Pleurosigma 120 120 160 180 100 120 10 Rhizosolenia 180 140 160 220 220 300 11 Skeletonema 400 380 420 480 460 460 12 Thalasiothryx 260 300 240 280 240 280 Density 5890 5550 5890 5820 5408 5600

Twelve groups of phytoplankton were obtained from the sites. Of these, Coscinodiscus was the dominant group. Total density of phytoplankton varied from 5408 to 5890 nos /l at various sampling sites. The low light penetration on account of high turbidity can be attributed to the lower plankton productivity. The predominant phytoplanktons observed in marine water samples in and around the project area include Cosindiscus sp. and Biddulphia. When phytoplanktons reach the maximum intensity of growth, zooplanktons starts growing. The productivity of phytoplanktons declines attaining maximum growth because of the depletion of nutrients and grazing by zooplanktons. This interrelationship or food chain of the phytoplankton abundance is important as they are the first step of any food chain or food web. The benthic organisms and fishes are also dependent on plankton for their food.

Mantec Consultants Pvt. Ltd. Page 102 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 24: Phytoplankton, Zooplankton and benthic meio fauna sampling locations at Kandla

Mantec Consultants Pvt. Ltd. Page 103 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

b. Zooplanktons: Only 7 groups of zooplankton were found in the area during the sampling. Copepodes were the most dominant group. The abundance of zooplanktons at various locations in the study area is given in Table- 33. The zooplankton density ranged from 221 to 300 no./l.

Table 35: Abundance of zooplankton density recorded at various sampling sites (Unit: no./l)

S.no Name of groups Site1 Site2 Site3 Site4 Site5 Site6 1. Copepoda 120 180 150 160 110 190 2. Decapoda 28 26 32 46 45 46 3. Lamellibranchiata 8 8 12 6 8 12 4. Lucifer 6 6 8 4 6 8 5. Mysids 28 20 18 16 16 18 6. Polychaeta 8 10 8 8 8 10 7. Stomatopod larva 14 12 12 16 18 16 Density 212 262 240 256 211 300

c. Benthos:

Benthos is a collective term referred to the organisms lying in or associated with aquatic sediment comprising bacteria, plants and animals from almost all phyla. Benthic animals are generally described on the basis of their position in the sediment. In fauna are the animals living within the interstitial space or burros. Those occupying the sediment surface are epifauna. Benthos (1‐100μm) comprising bacteria, protophyta and protozoans other than forminifera, Meio fauna (100‐1000 μm) including foraminifera, small metazoans, nematodes and Macro or Mega fauna (above 1000 μm) comprising of several macro invertebrates. Benthic fauna have been found to play a significant role in the trophic network, as they utilise all forms of food material available in the sea‐bed or estuarine base and form an important link in the transfer of energy. Another important aspect of the benthic studies is the effect of the pollution on the standing crop and productivity. Abiotic relationship of benthos especially with the sediment logical features has explained most of the fluctuations in benthic abundance. Benthos are the organisms that live on the floor of the sea. Benthic fauna usually tend to concentrate in the upper oxygenated layer of sediment except the true anaerobics.

Mantec Consultants Pvt. Ltd. Page 104 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Sediment samples were collected from six stations using Peterson's dredge having a biting area of 16 x 17 cm. The sediment obtained was sieved through required meshes to separate macrofauna (> 500 μ) and meiofauna (which pass through 0.5 mm sieve and are retained by a 1000 μ sieve). Each group of organisms were individually identified and a quantitative and qualitative analysis has been done. Diversity and abundance of meio and macrofauna did not show the presence of any rare or endangered species in any of the sampling sites. The details of meio‐benthos and macro‐benthos observed at various sampling locations are given in Tables- 37 and 39 respectively. The density of meio‐ fauna ranged from 382 to 670 nos/10 cm2 the dominant meio‐faunal group was nematode. The density of benthic macro‐fauna ranged from 952 to 1092 no/m2.The dominant macro‐faunal group was porifera.

Table 36: Density of Benthic Meio Fauna at Various Sampling Sites (Unit Nos/10cm2) S.No Name of groups Site 1 Site 2 Site 3 Site 4 Site 5 Site 6 1 Gastrotrichs 68 60 40 40 44 60 2 Harpacticoidea 28 30 20 22 20 30 3 Nematoda 220 420 360 240 460 420 4 Turbellaria 122 160 82 80 88 160 Density 438 670 502 382 612 670

Table 37: Co-Ordinates of Sampling Locations of Benthic Macro Fauna

Sites Latitude Longitude Site I 23° 2' 39" N 70° 13' 7" E Site II 23° 1' 12" N 70° 13' 13" E Site III 22° 58' 23" N 70° 12' 59" E Site IV 22° 57' 56" N 70° 13' 26" E Site V 22° 57' 50" N 70° 6' 40" E Site VI 22° 57' 42" N 70° 6' 45" E

Table 38: Density of Benthic Macro Fauna (Unit: No/M2)

S.No Name of groups Site 1 Site 2 Site 3 Site 4 Site 5 Site 6

1. Amphipodes 72 66 62 42 24 26 2. Bivalves 12 09 12 10 10 10 3. Porifera 980 900 850 880 980 980

Mantec Consultants Pvt. Ltd. Page 105 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

4. Gastropoda 12 11 16 18 16 16 5. Oligochaeta 16 12 12 12 18 20 Density (no/m2) 1092 998 952 962 1048 1052

Figure 25: Benthos Macro Fauna Sampling Locations at Kandla

Mantec Consultants Pvt. Ltd. Page 106 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.6.5.3 RET Species Flora/ Fauna (IUCN/ Indian Wildlife Act, 1972) A. Flora under RET The project influenced area consists of sparse and patchy vegetation which is general in occurrence. No herb, shrub and tree species is falling in the list of Rare/threatened/endangered of Red Data Book of Indian Plants and IUCN.

B. Fauna under RET No rare or threatened species are falling in the project influenced area.

3.6.5.4 Occurrence of National Park / Sanctuary/ Biosphere Reserve etc

In the study area of the DPT no National park, wildlife sanctuary or biosphere reserve is present. However, Marine National Park and Marine Sanctuary in the Gulf of Kutchchh is present on the southern part of the Gulf along the Jamnagar district. The sanctuary was declared in 1980 & Nation park was in 1982. The aerial distance from the proposed project site to these areas is ranging approximately from 50‐60 km.

Table 39: Distance and direction of the wildlife sanctuary from proposed project site Sl Wild life sanctuary Distance from Direction from the the proposed proposed project site project site (Km) 1 Kutch desert Wildlife Sanctuary 50 North West 2 Khijadia Bird Sanctuary 48 South 3 Kutch Bustard Sanctuary 130 North West

Mantec Consultants Pvt. Ltd. Page 107 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Project site

Figure 26: Map of National Parks and Wildlife Sanctuaries in Gujarat

3.6.6 Trend analysis of fishing activity at Kandla creek & Tuna creek

The survey of fishery resources along the Gujarat coast by the Fisheries Survey of India (FSI), GOI during 1979 to 1992 indicates that for a coastline of 1600 km covering a shelf area of 1,64,183 sq. km, the maximum sustainable yield is 7.73 lakhs MT and the value of marine fish landing in 1997‐98 was 7.02 lakhs M.T. The northern areas of Kachchh were found to be the most productive areas and had a dominance of Silver Grunt and Cat Fish species. The fisheries statistics in the Kachchh coast (of 406 km length) reveals a fish production of about 71,787 tonnes in the year 1997‐98, which is 10.22 % of the total fish production in Gujarat. Of this 70% of the landings i.e., 50193 occurred at Khori Creek and the coastal centres along the Arabian Sea (Okha). Most of the fishing landings occur at Veraval, Jakhau, Jafarbad, Shiyalbet and Okha. In Kachchh, the largest fish

Mantec Consultants Pvt. Ltd. Page 108 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

landings occur at Jakhau (66.2%), while Kandla and Mitha Port account only for 3% of the Kachchh landings. Fisheries are not prevalent in Tuna probably due to fish stock being low, relative to the other areas in the Gulf of Kachchh like Jakhau. It has been found that high tidal movements and unusually strong currents make trawling or gill netting for fish difficult and risky in the area. While a fishing harbour exists north of the Deendayal port, Kandla together with Mitha port accounts for 3% of the landings of Kachchh. Most of the fishing occurs in the outer regions of GoK and off coast.

3.6.7 Mangroves

Mangroves occupy less than 1% of the world’s surface and are mainly found between the Tropic of Cancer and the Tropic of Capricorn on all continents covering an estimated 75 percent of the tropical coastline worldwide (Source: Gujarat Ecology Commission). Mangroves are one of the most valuable coastal habitats providing enormous benefits (both tangible and non-tangible) to the local communities as well as the ecology and environment surrounding them. Tangible benefits of mangroves comprise timber and non-timber products and other livelihood support systems provided. Mangroves possess several characteristics that make them structurally and functionally unique. Mangrove forests have traditionally been utilized by the local people for a variety of purposes.

3.6.7.1 Status of Mangroves in Gujarat Historically, Gujarat had an extensive and diverse mangrove ecosystem which had been degraded or depleted over time due to various developmental activities as well as natural disasters and anthropogenic interactions. In fact, until about 1960s, mangroves were considered as ‘economically unproductive areas’ and hence, they had faced destruction caused by expansion of economic as well industrial development activities. However, after many years of wide spread destruction and degradation, significant efforts are being made in recent years by the State Government and the International agencies to restore and regenerate the mangrove stock in Gujarat. According to FSI report there was a constant increase in the mangrove cover in Gujarat state since 1987‐1999 but in 2001 it decreased from 1031 sq km to 911 sq

Mantec Consultants Pvt. Ltd. Page 109 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

km. But ever since 2001 the state saw an increase of 135 sq km. The report also states that Gujarat showed an increase in mangrove cover mainly because of the plantation and protection measures taken by the state in recent years (Source: Gujarat Ecology Commission).

3.6.7.2 Status of Mangroves in the Study Area To know the status of mangroves in the study area (10km radius of proposed projects) an approach based on time series satellite data and ground inventory was adopted. For the purpose of change in mangroves the following imaginaries and software’s have been used: 1. Satellite Data Used: LANDSAT 1999, LANDSAT 2005, LISS III 2011

2. Software Used: ERADAS, Arc GIS 9.3 for supervised classification and on screen digitization.

Analysis result of time series satellite data shows considerable change in the total area of mangroves, in duration of 2005 to 2011 total area of mangroves increased from 6442 ha to 7431 ha i.e. total 15.35%, while in the duration of 1999 to 2005 only 1.91% increment has been observed. Time series satellite imageries are given in Figure 27 to 28. Analysis results of time series satellite data are given in Table 40. It has been noted by expert committee of CRZ, Gujarat during their site visit that many areas of mangroves are badly affected due to various human activities in Kandla Port area. However, DPT has taken measures for plantation of mangroves at Satsaida belt (opposite to Kandla Port) through Gujarat Ecology Commission and Forest Department.

Table 40: Details of Time Series Satellite Data Analysis for Mangroves

Year 1999 2005 2011 Area (ha.) 6321 6442 7431 Change (%) ‐ 1.91 15.35

Mantec Consultants Pvt. Ltd. Page 110 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 27: FCC image of LANDSAT 1999

Mantec Consultants Pvt. Ltd. Page 111 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 28: FCC image of LANDSAT 2005

Mantec Consultants Pvt. Ltd. Page 112 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 29: FCC image of LISS-III 2011

Mantec Consultants Pvt. Ltd. Page 113 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.7 Marine Environment The marine ecosystem is the largest aquatic system on the planet. Its size and complexity make it difficult to deal with as a whole. The pressure on the oceans is not only due to over‐harvesting but also to the cumulative impact of land‐based activities. This includes many of the effects of coastal development, especially the destruction of wetlands, mangroves and coral reefs, sedimentation and the dredging of sediments, damage to watersheds and the impounding of water supplies to support urban development in coastal areas. The world’s oceans are not only the domain of food for human being but also the legitimate concern of marine transport, offshore extraction of oil, gas and other minerals, climate control and recreation. Marine fisheries account for 85% of the global fish catch. Maritime shipping is involved in the transport of over 80% of the world’s merchandise trade. The oceans have also become the ultimate sink for discharges of waste of all sorts carried by rivers and winds from land‐based sources, including coastal mega cities. Other threats come from the transport of hazardous wastes, operational and accidental spillage of oil, discharge of radioactive materials at sea, nuclear testing and the transport of alien species in the ballast water of ships. Two traditional areas exist, one between the marine environment and the terrestrial, and the other between marine and fresh water. The intertidal zone or littoral zone is that shore areas lying between the extremes of high and low tide; it represents the transitional area from marine to terrestrial conditions. It is a zone of abundant life. Estuaries represent the transitional zone between land and water, it combines the characteristics of both these environs besides having some unique characteristics of its own. This area supports abundant benthic fauna and flora communities. Transitional waters tend to be richer in plant nutrients and more productive than water of corresponding depths in the open sea. One reason for this is the greater mixing that occurs here as a result of turbulence, wave action, upwelling caused by offshore currents, winds etc., bringing plant nutrients into all strata of the water. Also additional nutrients are led from the substrate and washed in to the sea by rivers and streams from the adjacent land. Where the substrate is suitable for attachment, the shallow waters also support a rich growth of flora and fauna. Mangroves are tropical and sub tropical swampy forests bordering the sheltered seacoasts and estuaries.

Mantec Consultants Pvt. Ltd. Page 114 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.7.1 Costal Hydrology/Geomorphology Coastal Zones are dynamic interferences between land and water and are common location of high‐density development. Coasts are subject to frequent natural hazards; including flooding, storm impacts, coastal erosion, and tsunami inundation. Coastal erosion is a constant problem along most open ocean shores of India. As coastal populations continue to grow and infrastructures are threatened by erosion, there is an increasing demand for accurate information regarding past and present shoreline changes. There is also a need for a consistent and comprehensive analysis of shoreline movement. It is generally agreed that the coast especially the beaches are facing severe erosion and the shorelines are changing. These are primarily due to manmade activities such as construction of ports, harbors, shore protection measures etc. The Central/State Governments and private entrepreneurs also propose to construct several ports and harbors all along the shores in coming years. These could have irreversible adverse impact on the coast if such infrastructures are constructed without scientific studies. To meet these National needs, the Ministry of Environment and Forests, Government of India have initiated an analysis of historical shoreline changes along the east and west coasts of the country. The main purpose of that study was to develop standard repeatable methods for mapping and analyzing shoreline movement so that periodic updates regarding coastal erosion and land loss that were systematic and internally consistent could be made on a national scale. For that study, the “instantaneous high water line” has considered as the shoreline as it was derived from satellite imagery.

Objective The main objective of this shoreline study is to present the erosion and accretion status of the shoreline of the study area and to provide the technical basis and analytical information useful for adopting a systematic approach to infrastructure development and coastal conservation.

How and Why Shorelines Change The source of the sand that created and continues to feed the beaches, dunes, and barrier beaches in India, comes primarily from the erosion of coastal landforms. All sedimentary coasts tend to erode at one time or another and this basic tenet of coastal

Mantec Consultants Pvt. Ltd. Page 115 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

science reflects the complex interactions that occur at the land‐ocean interface. Wherever shorelines are composed of discrete grains of sediment, the processes of winds, waves, currents and changing water levels combine to mobilize particles and move them around by varying degrees. Erosion, transport, and the accretion that results are continuous and interrelated processes. Shorelines also change seasonally, tending to accrete slowly during the summer months when sediments are deposited by relatively low energy waves and erode dramatically during the winter when sediments are moved offshore by high energy storm waves. In addition, attempting to halt natural coastal process with seawalls and other hard structures only shifts the problem, subjecting down drift coastal areas to similar losses. Also, without the sediment transport, some of the beaches, dunes, barrier beaches, salt marshes, and estuaries—are threatened and would disappear as the sand sources that feed and sustain them are eliminated.

Coastal Regions India’s coastline is 8158 km long; of this, the peninsular India is 6064 km, and the islands of Andman and Nicobar and Lakshdweep account for 2094 km. Figure 30 shows the extent of the coastal districts along the east and west coasts of India.

Mantec Consultants Pvt. Ltd. Page 116 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 30: India’s Coastal Districts

Mantec Consultants Pvt. Ltd. Page 117 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Status of Erosion/Accretion As per the study of National Centre for Sustainable Coastal Management, MoEF and Society of Integrated Coastal Management, the coastline of Gujarat state is about 1600 km long and consists of 11 districts as given in Figure 30. Out of 1600 km; the length of high erosion coastline is 84.5 km, the length of medium erosion coastline is 170.2 km and the length of low erosion coastline is 478.1 km. Details of erosion characteristics of Gujarat Coastline is given in Table 41 and district wise erosion categories are given in Table 42. Erosion/Accretion status of the coastline of present study area consist shorelines of Kandla and Tuna Port given in Figure 31 to Figure 33. After going through shoreline change maps of the study area it has been found that, present study area comes under low erosion, medium erosion & stable coast area. As per the study conducted by NCSCM, MoEF; in Kutch district; total 62.3 km length of coastline comes under high erosion area, total 115.6 km length of coastline comes under medium erosion area and total 132.7 km length of coastline comes under low erosion area. As per the study our present study area Kandla comes under medium erosion area. Areas falls under high & medium erosion categories are given in Table 43 & 44 respectively. Table 41: Erosion Characteristics of Gujarat Coast

Gujarat Coast Length (km) % Erosion Length of Gujarat coast 1600.0 Total High Erosion (km) 84.5 5.3 Total Medium Erosion 170.2 10.6 (km) Total Low Erosion (km) 478.1 29.9

Table 42: District wise Erosion categories in km

District High Erosion (km). Medium Erosion (km) Low Erosion (km). Kutch 62.3 115.6 132.7 Jamnagar. 12.9 13.5 64.5 Junagadh _ _ 100.3 Amreli _ 5.2 21 Bhavnagar _ 5.2 59.8 Ahmadabad 2.8 11.3 Kheda 8.9

Mantec Consultants Pvt. Ltd. Page 118 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Bharuch 6.2 21 27.5 Surat 6.9 11.2 Valsad 3.1 40.9 Total Erosion (km) 84.5 170.2 478.1 % of Gujarat 5.3% 10.6% 29.9% coastline under erosion Total Erosion along Gujarat Coast = 45.8%

Table 43: Areas under High Erosion Category

Sr.No Name of District Name of Taluka Name of Village

1 Ahmedabad Dhandhuka 1 [Gogala] 2 Amereli Jafarabad 2 [Mithapur and Mitaliyana] 3 Bharuch Amod 1 [Denava]

11 [Nadiad, Kalak, Sardarpura, Devala, 4 Bharuch Jambusar vanseta, Dolia, Khanpardeh, Islampore, Kapuria, Nada, Asrasa]

5 Jamanagar Jodiya 2 [Zinzuda and Jodiya] 6 Jamnagar Kalyanpur 1[Gurgadh] 7 Jamnagar Okhamnadal 1 [Charkaala] 8 Kachchh Abdasa 2 [Mohadi and Kosa] 9 Kachchh Gandhidham 2 [Padana&MithiRohar] 10 Kachchh Bhachau 2 [ChiraiMoti and ChiraiNani] 11 Kachchh Lakhpat 1 [Dedhpar] 12 Navasari Jalalpore 1 [Dedhpar] Total 6 [District] 12 [Taluka] 27 [Villages]

Areas under High erosion category fall under no development zone, areas falling under high erosion category represent 5.3% of total coastline of Gujarat State.

Table 44: Areas under Medium Erosion Category

Sr.No Name of District Name of Taluka Name of Village 1 Amereli Jafarabad 3 [Kadiyali, Nageshri, Doldari] 2 Bharuch Handot 1 [Shera] 3 Jamanagar Jodiya 1 [UntbetShamapar] 4 Kachchh Anjar 1 [Sangadh] 5 Kachchh Bhachau 1 [Bahcahu {M}]

Mantec Consultants Pvt. Ltd. Page 119 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

6 Kachchh Gandhidham 1 [kandala] 4 [Cher nani, Kanoj, Narayan Sarovar, 7 Kachchh Lakhpat GuharMoti] 8 Kachchh Mandavi 1 [Nana Bhadiya] 9 Kachchh Mundra 4 [Bhadreshwar, Kukdsar, Mundra, Baroi] 10 Navasari Jalalpore 1 [Magob] 11 Surat Chorasi 2[ Gambheni, Umber] 12 Valsad Valsad 4 [Malvan, Untadi, Danti, Dharasana] Total 7 [District] 12 [Taluka] 24 [Villages]

Areas under Medium erosion category fall within development zone with comprehensive EIA. The areas under Medium erosion category represent 10.6% of total coastline of Gujarat State.

Mantec Consultants Pvt. Ltd. Page 120 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 31: Gujarat Index Map for Shoreline Studies

Mantec Consultants Pvt. Ltd. Page 121 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 32: Status of shoreline change at Tuna port in Gujarat

Mantec Consultants Pvt. Ltd. Page 122 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 33: Status of shoreline change at Kandla port in Gujarat

Mantec Consultants Pvt. Ltd. Page 123 Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.7.2 Bed Sediment/Dredging Sludge Quality

Dredging is an excavation activity or operation usually carried out at least partly underwater, in shallow seas or fresh water areas with the purpose of gathering up bottom sediments and disposing of them at a different location. Dumping Site is earmarked at location south of OTB (Latitude ‐ 22º 50’ 00’’ & Longitude ‐ 70º 07’ 00’’). This technique is often used to keep waterways navigable. Deendayal Port Trust has decided to carry out dredging at three locations. The bed sediment samples were collected from these sites and analyzed in the lab for its metal constituents. Dredging quantity to be conducted by Deendayal Port Trust (capital as well as maintenance) that will be required to maintain the port initially and throughout the year is given below: 1) Capital dredging = 1356000 m3 2) Maintenance dredging = 271200 m3/year The sediments samples were collected from three sites where there is proposal of dredging. The sites are: 1. Tuna port 2. Khori Creek 3. Old Kandla The tests were conducted for six metals belong to schedule II of Class A metals Viz. Antimony, Arsenic, Cadmium, Chromium (VI), Total Chromium, and Mercury. The results of the tests for the metals are shown in the table below:

Table 45: Metal Content in the Samples Collected From the Sites Schedule II Class A Sampling Stations Metals Tuna Khori creek Old Kandla Antimony (mg/kg) BDL BDL BDL Arsenic (mg/kg) 1.19 1.40 1.35 Cadmium (mg/kg) 0.274 0.259 0.255 Chromium (VI) (mg/kg) 0.37 0.36 0.41 Total Chromium 44.6 42.9 45.5 (mg/kg) Mercury (mg/kg) 0.044 0.037 0.041

Mantec Consultants Pvt. Ltd. Page 124

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.8 Socio-economic Study Socio‐Economic Impact Assessment (SEIA) refers to systematic analysis of various social and economic characteristics of human being living in a given geographical area. The geographical area is often called Study Area or Impact Area. It is carried out simultaneously with Environment Impact Assessment (EIA). The prime objective of SEIA is to identify and evaluate potential socio‐economic and cultural impacts of a proposed development project on the lives & conditions of people, their families and communities. If the potential impacts are significant and adverse, SEIA assist the developers and other stakeholders to reduce, remove or prevent these impacts from happening. It is a multidisciplinary, using theories and methods from Sociology, Statistics, Economics, History, Psychology, Geography and Anthropology. It is pre‐ requisite before the project is put into implementation. The study area consists of the core area where the proposed project is expected to come up and a buffer area encircling the project area with a radius of prescribed kilometers from the periphery of the core area. For every new project Socio‐Economic Impact Assessment is mandatory. It is also mandatory for existing projects in case of expansion, modernization and change in product mix. The Socio‐Economic Impact Assessment focuses the effect of the project on social and economic well‐being of the community.

In the SEIA, it is examined how a development project changes the lives of local residents. The outcome of the study relies on both quantitative and qualitative measure of impacts. The impacts are evaluated in terms of changes in community demographics, housing, employment, market effects, public services, retail business, quality of life and artistic qualities of the community. Further, assessing proposed developments in socio‐economic context help the community leaders and local people identify potential social equity issues, evaluate the adequacy of social services and determine whether the project has adverse effects on overall social well‐being or not.

SEIA also provides a forum for planning how to maximize the beneficial impacts of a proposed development. Beneficial impacts can include:

a) A better standard of living due to increased access to employment, business opportunities, training and education b) Greater access to and from a community and

Mantec Consultants Pvt. Ltd. Page 125

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla c) Increased funding to improve social infrastructure and cultural maintenance programs.

Objectives of the Study

The objectives of Socio‐Economic Impact Assessment of the project are as follows: a) To collect baseline data of the study area. b) To comprehend socio‐economic status of the people living in the study area. c) To assess probable impact of the project on social and economic aspects in the study area. d) To measure the impact of the project on quality of life of the people living in the study area. e) To ensure sustainability of positive impact. f) To suggest mitigation measures and agency responsible for taking action in case of adverse impact.

Steps taken to prepare the SEIA Report  Literature Review.  Identification of the study area and important landmarks therein.  Preparation of list of habitations located in the study area.  Site visit to collect the facts through observations.  Firming up of approach and methodology.  Finalization of Questionnaires–Village/Town and Household Questionnaire.  Collection of Secondary Data from Census Report, District profile, published and un‐published Literatures, Administrative records etc.  Collection of primary data from sample villages and households therein.  Manual scrutiny of field in schedules. The manual scrutiny aimed at removal of duplicate records, missing records, alien records and consistency checks.  Data Entry and Data Validation.  Generation of Data Tables.  Data Analysis and preparation of report.

Mantec Consultants Pvt. Ltd. Page 126

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Concept & Definition of terms used in the SEIA Report

Study Area: The study area, also known as Impact Area has been defined as the sum total of core and buffer area with a specified kilometer of radius from the periphery of the project site. The study area includes all the land marks both natural and manmade, falling therein.

Quality of Life: The Quality of Life refers to degree to which a person ‘enjoys’ the important ‘possibilities’ of his/her life.

Baseline Data: Baseline data refers to basic information collected before a project/scheme is implemented. It is used later to provide a comparison for assessing impact of the project. Any attempt to collect baseline data while undertaking actual impact assessment study is faced with recall error.

Household: A group of persons who normally live together and take their meals from a common kitchen are called a household.

Sex Ratio: Sex ratio is the ratio of females to males in a given population. It is expressed as 'number of females per 1000 males'.

Literates: All persons aged seven years and above who can both read and write with understanding in any language are taken as literate. People who are blind but can read in Braille are also treated as literates.

Mantec Consultants Pvt. Ltd. Page 127

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Literacy Rate: Literacy rate of population is defined as the percentage of literates to the total population aged seven years and above.

Labour Force: The labour force is the number of people employed and unemployed in a geographical entity. The size of the labour force is the sum total of persons employed and unemployed. People not counted under labour force are students, retired persons, stay at home people, people in prisons, permanently disabled persons and discouraged workers.

Work: Work is defined as participation in any economically productive activity with or without compensation, wages or profit. Such participation may be physical and/or mental in nature. The work may be part time or full time or unpaid work in a farm, family enterprise or in any other economic activity.

Worker: All persons engaged in 'work' are defined as workers.

Main Workers: Those workers who had worked for the major part of the reference period (i.e. six months or more in the case of a year) are termed as Main Workers.

Marginal Workers: Those workers who did not work for the major part of the reference period (i.e. less than six months) are termed as Marginal Workers.

Work Participation Rate: The work participation rate is the ratio between the labour force and the overall size of their cohort (national population of the same age range). In the present study the work participation rate is defined as the percentage of total workers (main and marginal) to total population.

Area under Non-agricultural Uses: This includes all land occupied by buildings, roads and railways or under water, e.g. rivers, canals and other land put to uses other than agriculture.

Barren/Un-culturable Land: This includes all land covered by mountains, deserts, etc. Land, which cannot be brought under cultivation except at an exorbitant cost is classified as un‐culturable whether such land is in isolated blocks or within cultivated holdings.

Mantec Consultants Pvt. Ltd. Page 128

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Permanent Pasture and other Grazing Land: This includes all grazing land whether it is permanent pasture/meadows or not. Village common grazing land is included under this category.

Land under Miscellaneous Tree Crops: This includes all cultivable land which is not included in ‘Net Area Sown’ but is put to some agricultural use. Land under casuring trees, thatching grasses, bamboo bushes and other groves for fuel etc. which are not include under Orchards are classified under this category.

Culturable Waste Land: This includes land available for cultivation, whether taken up or not taken up for cultivation once, but not cultivated during the last five years or more in succession including the current year for some reason or the other.

Fallow Lands (Other than Current Fallows): This includes all land which was taken up for cultivation but is temporarily out of cultivation for a period of not less than one year and not more than five years.

Current Fallows: This represents cropped area which is kept fallow during the current year.

Net Area Sown: This represents the total area sown with crops and orchards. Area ‘sown’ more than once in the same year is counted only once.

3.8.1 Project Site & Study Area The Site of the Kandla Port is located near the villages of Anjar and Gandhidham Taluka of Kachchh district in the state of Gujarat. Demographic and Socio‐economic profile of the study area is based on census data for the year 2011 of Kachchh district of Gujarat state. The census data has been analyzed with respect to demographic profile, community structure, literacy level, and occupational structure. Every towns and villages with their minor portions within the study area have been considered fully for the study. 3.8.2 Demographic Profile of the Study Area The study area (10 km radius of the project site) falls in two sub‐districts namely Anjar and Gandhidham comprising of nine (09) villages and four (04) towns in the Kachchh district of Gujarat state. Total population of these habitations has been worked out to 3,36,332 out of which 53.19 per cent are males and remaining 46.81

Mantec Consultants Pvt. Ltd. Page 129

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla per cent are females. This total population is distributed among 73,271 households with average household size of five persons per household. The overall sex ratio of the study area has been worked out to 880 females per 1,000 males. The graphical representation of the overall population distribution of the study area is shown below:

Total child population of (0‐6) age group in the study area has been worked out to 46,946 comprising about 13.96 per cent of the total population. Out of these, 52.50 per cent is male child whereas remaining 47.50 per cent is girl child of the same age group. The sex ratio among the child population is 905 girls per 1,000 boys. The graphical representation of the said child population of the study area is shown below:

The overall population of the study area is devided into different social groups like Scheduled Caste, Scheduled Tribe and General Category (including ‘OBC’). The share of Scheduled Caste population to the total population is 17.70 per cent out of which 51.93 per cent is males and remaining 48.07 per cent is females. The sex ratio among this category has been worked out to 926 females per 1,000 males. Similary, the share of Scheduled Tribe population to the total population is just about 1.75 per cent, out of which 53.07 per cent is males and rest 46.93 per cent is females. The sex ratio among the tribal people has been worked out to 884 females per 1,000 males. The population belonging to other than Scheduled Caste & Scheduled Tribe Category is 2,70,914 which forms about 80.55 per cent to the total population of the study area. Of this, 53.47 per cent is males and remaining 46.53 per cent is females. The sex ratio among

Mantec Consultants Pvt. Ltd. Page 130

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla this segment of population has been worked out to 870 females per 1,000 males. The graphical representation of the population belonging to different social groups is shown below:

The overall literates in the study area has been worked out to 2,23,621 which is about 66.49 per cent to the total population. Out of which, the share of male literates is 58.20 per cent and that of female is 41.80 per cent. The literacy rate of the study area is 77.27 per cent in which male literacy rate is 84.38 per cent and that of female is 69.16 per cent which creates a gender gap in literacy rate of 15.22 per cent. The graphical representation of the literates and there share among males and females is shown below:

Sub‐district wise list of identified villages/towns in the study area is presented in the table below: Table 46 : Sub-district wise Village/Town in the Study Area

Sub-district wise list of Villages/Towns in the Study Area Sub-district: Anjar S. No. Village/Town S. No. Villages/Town S. No. Village/Town

01 Mathak 02 Rampar 03 Chandrapar 04 Tuna 05 Sanghad Total= 05 Sub-district: Gandhidham 01 Mithi Rohar 02 Shinay 03 Kidana

Mantec Consultants Pvt. Ltd. Page 131

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

04 Bharapar 05 Kandla (CT) 06 Gandhidham (MT) 07 Antarjal (CT) 08 Galpadar (CT) Total= 08 Grand Total= 13

The geographical area (in hectare) of these identified habitations (village & town) is shown in the table below:

Table 47: Geographical Area of the Identified Habitations

S. No. Village Geographical S. No. Town Geographical Area Area (In sq. km.) (In sq. km.) 01 Mathak 18.75 01 Kandla 2.97 02 Tuna 12.16 02 Gandhidham 29.58 03 Rampar 13.79 03 Antarjal 9.64 04 Sanghad 36.26 04 Galpadar 7.80 05 Mithi Rohar 36.01 Total 49.99 06 Shinay 23.11 07 Kidana 29.71 08 Bharapar 9.86 Grand Total = 231.92 km2. 09 Chandrapar 2.28 Total 181.93

The land use patter in the identified villages of the study area is presented in the table below: Table 48: Land Use Pattern in the Identified Villages of the Study Area S. No. Land Use Pattern Area (In Ha) 01 Non‐agricultural Uses Land 1,051.26 02 Barren/Un‐cultivable Land 4,221.60 03 Permanent Pastures & Other Grazing Land 508.12 04 Miscellaneous Tree Crops Land 239.97 18,192.65 05 Culturable Waste Land 1,603.34 06 Fallows Land (other than current fallows) 599.86 07 Current Fallows Land 1,757.98 08 Net Area Sown 8,210.52 09 Un‐irrigated Land 7,178.48

3.8.2.1 Population (Villages) The total population of as per Census 2011 of the identified villages in the study area is 48,147. The share of male, female population to the total population and sex ratio are 51.92%, 48.08% and 926 females per 1000 males respectively. There are about 10,054 households in these villages of the study area. The average household size is about five. Village wise population and sex ratio is presented in the table below:

Mantec Consultants Pvt. Ltd. Page 132

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Table 49: Village wise Population & Sex Ratio in the Study Area Demographic Data of the Village Areas of the Study Area Total Total Total % Total % Villages Sex Ratio HHs Population Males Males Females Females Mathak 534 2278 1184 51.98 1094 48.02 924 Tuna 1007 5114 2573 50.31 2541 49.69 988 Rampar 249 1262 634 50.24 628 49.76 991 Sanghad 882 4279 2199 51.39 2080 48.61 946 Mithi Rohar 2757 13712 7154 52.17 6558 47.83 917 Shinay 969 4345 2203 50.70 2142 49.30 972 Kidana 3272 15669 8093 51.65 7576 48.35 936 Bharapar 378 1462 944 64.57 518 35.43 549 Chandrapar 06 26 16 61.54 10 38.46 625 Total 10,054 48,147 25,000 51.92 23,147 48.08 926 (Source: Census 2011)

3.8.2.2 Child Population of (0-6) Age-Group (Village) In the villages’ areas of the study area, the total child population of age group of 0‐6 has been worked out to 8,167 which constitute 16.96 per cent of the villages’ total population. Of the total child population, 51.74 per cent are boys and remaining 48.26 per cent are girl child. The child sex ratio in this segment of population from the village areas is 933 girls per 1,000 boys.

3.8.2.3 Population (Towns) There are four towns including three census towns (CT) and one municipal town (MT) that falls under the study area namely Kandla (CT), Gandidham (MT), Antarjal (CT) and Galpadar (CT). The total population of these towns as per Census 2011 is 2,88,185. The share of male, female population to the towns’ total population and sex ratio are 53.40%, 46.60% and 873 females per 1000 males respectively. There are about 63,217 households in these town areas of the study area. The average household size in the town areas is about five. Town wise population and sex ratio is presented in the table below: Table 50: Town Population & Sex Ratio in the Study Area Demographic Data of Town Areas of the Study Area Total Total Total % Total % Towns Sex Ratio HH Population Males Males Females Females Kandla 3574 15782 9028 57.20 6754 42.80 748 Gandhidham 54565 247992 131484 53.02 116508 46.98 886 Antarjal 2426 11256 5891 52.34 5365 47.66 911 Galpadar 2652 13155 7483 56.88 5672 43.12 758 Grand Total 63,217 2,88,185 1,53,886 53.40 1,34,299 46.60 873 (Source: Census 2011)

Mantec Consultants Pvt. Ltd. Page 133

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.8.2.4 Child Population of (0-6) Age-Group (Town) In the town areas of the study area, the total child population of age group of 0‐6 has been worked out to 38,779 which constitute 13.46 per cent of the towns’ total population. Of the total child population, 52.65 per cent are boys and remaining 47.35 per cent are girl child. The child sex ratio in this segment of population from the town areas is 899 girls per 1,000 boys.

3.8.2.5 Social Structure (Villages) The presence of the Schedule Caste (SC) population in the villages is 13.11% of the villages’ total population of the study area. Out of which, male population is 51.18% and that of female is 48.82%. The Schedule Tribe (ST) population in the villages is about 1.00% of the villages’ total population comprising 54.87% males and 45.13% females. Village wise SC & ST population distribution is presented in the table below: Table 51: SC Population distribution in the Village areas of the Study Area SC Population Distribution in the village area of the Study Area Total Total Total SC % SC % SC Total SC % SC Village SC Population Population Population Males Females Females Males Mathak 2278 124 5.44 62 50.00 62 50.00 Tuna 5114 699 13.67 356 50.93 343 49.07 Rampar 1262 401 31.77 203 50.62 198 49.38 Sanghad 4279 103 2.41 54 52.43 49 47.57 Mithi Rohar 13712 1333 9.72 710 53.26 623 46.74 Shinay 4345 75 1.73 40 53.33 35 46.67 Kidana 15669 3552 22.67 1786 50.28 1766 49.72 Bharapar 1462 24 1.64 19 79.17 05 20.83 Chandrapar 26 00 00 00 00 00 00 Total 48,147 6,311 13.11 3,230 51.18 3,081 48.82 (Source: Census 2011)

Table 52: ST Population Distribution in the Village areas of the Study Area ST Population Distribution in the village areas of the Study Area Total Total ST % ST Total ST % ST Total ST % ST Village Population Population Population Males Males Females Females Mathak 2278 08 0.35 03 37.50 05 62.50 Tuna 5114 01 0.02 00 0.00 01 100.00 Rampar 1262 100 7.92 53 53.00 47 47.00 Sanghad 4279 28 0.65 15 53.57 13 46.43 Mithi Rohar 13712 121 0.88 73 60.33 48 39.67 Shinay 4345 33 0.76 16 48.48 17 51.52 Kidana 15669 182 1.16 97 53.30 85 46.70 Bharapar 1462 10 0.68 08 80.00 02 20.00 Chandrapar 26 00 00 00 00 00 00 Total 48,147 483 1.00 265 54.87 218 45.13

Mantec Consultants Pvt. Ltd. Page 134

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla (Source: Census 2011) 3.8.2.6 Social Structure (Towns) The Schedule Caste (SC) population within the town areas is 18.46% of the towns’ total population. Out of which, share of male SC population is 52.01% and that of female SC population is 47.99%. The Schedule Tribe (ST) population in the town areas of the study area is about 1.88% of the towns’ total population comprising 52.91% males and 47.09% females. Town‐wise SC & ST population break‐up is shown in the table below: Table 53: SC Population break-up in the Town area of the Study Area SC Population Break-up in the Town area of the Study Area

Total Total SC % SC Total SC % SC Total SC % SC Town Population Population Population Males Males Females Females

Kandla 15,782 428 2.71 272 63.55 156 36.45 Gandhidham 2,47,992 50,479 20.36 26,137 51.78 24342 48.22 Antarjal 11,256 1,049 9.32 534 50.91 515 49.09 Galpadar 13,155 1,251 9.51 732 58.51 519 41.49 Total 2,88,185 53,207 18.46 27,675 52.01 25,532 47.99 (Source: Census 2011)

Table 54: ST Population break-up in the Town areas of the Study Area ST Population Break-up in the Town area of the Study Area Total Total ST % ST Total ST % ST Total ST % ST Town Population Population Population Males Males Females Females Kandla 15,782 415 2.63 236 56.87 179 43.13 Gandhidham 247992 4081 1.65 2115 51.83 1966 48.17 Antarjal 11256 526 4.67 269 51.14 257 48.86 Galpadar 13,155 395 3.00 246 62.28 149 37.72 Total 2,88,185 5,417 1.88 2866 52.91 2551 47.09 (Source: Census 2011)

3.8.2.7 Literacy The total number of literates within the study area is 2,23,621 which comprises 66.49% of the total population. The share of male and female literates to the total literates is 58.20% and 41.80% respectively. The overall literacy rate in the study area has been worked out to 77.27 per cent in which male literacy rate is 84.38 per cent and that of female is 69.16 per cent, creating a gender gap in the literacy rate of 15.22 per cent in the study area.

Out of these above literates, 24,512 literates belong to village areas which comprise 10.96 per cent of the total literates and 50.91 per cent of the villages’ total population from the study area. Out of these literates in the village areas, 60.93 per cent are males

Mantec Consultants Pvt. Ltd. Page 135

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla and remaining 39.07 per cent are females. The literacy rate in the village area has been worked out to 61.31 per cent in which male literacy rate is 71.89 per cent and that of female is 49.86 per cent which creates a gender gap in the literacy rate of 22.03 per cent in the village areas of the study area.

Again, out of the overall literates 1,99,109 literates belong to town areas which comprise 89.04 per cent of the total literates and 69.09 per cent of the towns’ total population from the study area. Out of these literates from the town areas, 57.87 per cent are males and remaining 42.13 per cent are females. The literacy rate in the town areas has been worked out to 79.83 per cent in which male literacy rate is 86.33 per cent and that of female is 72.36 per cent which creates a gender gap in literacy rate of 13.97 per cent in the town areas of the study area. Village/town wise distribution of literates is presented in the table below: Table 55: Distribution of Literates in the Study Area Distribution of Literates in the Study Area Total Total % Total Total % % Male Villages/Town Male Female Female Population Literates Literates Literates Literates Literates Literates Mathak 2278 1250 54.87 744 59.52 506 40.48 Tuna 5114 2159 42.22 1323 61.28 836 38.72 Rampar 1262 615 48.73 382 62.11 233 37.89 Sanghad 4279 1808 42.25 1096 60.62 712 39.38 Mithi Rohar 13712 5226 38.11 3410 65.25 1816 34.75 Shinay 4345 3008 69.23 1647 54.75 1361 45.25 Kidana 15669 9572 61.09 5696 59.51 3876 40.49 Bharapar 1462 860 58.82 627 72.91 233 27.09 Chandrapar 26 14 53.85 10 71.43 04 28.57 Total Village 48,147 24,512 50.91 14,935 60.93 9,577 39.07 Kandla 15,782 6,877 43.57 4,771 69.38 2,106 30.62 Gandhidham 2,47,992 1,76,060 70.99 100576 57.13 75484 42.87 Antarjal 11,256 6,933 61.59 4,073 58.75 2,860 41.25 Galpadar 13,155 9239 70.23 5,798 62.76 3,441 37.24 Total Town 2,88,185 1,99,109 69.09 1,15,218 57.87 83,891 42.13 Grand Total 3,36,332 2,23,621 66.49 1,30,153 58.20 93,468 41.80 (Source: Census 2011) 3.8.3 Occupational Structure The occupational structure of the population in the study area has been studied with reference to the total workers and non‐workers. Further total workers grouped into two categories main workers and marginal workers. Workers have been grouped further into four categories namely Cultivators, Agricultural Labourers, Household Industrial Workers and Other Workers.

Mantec Consultants Pvt. Ltd. Page 136

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.8.3.1 Total Workers Work is defined as participation in any economically productive activity with or without compensation, wage. Such participation may be physical and or mental in nature. Work involves not only actual work but also include supervision and direction of work. It even includes part time help or unpaid work on farm, family enterprise or its economic activity. All persons engaged in ‘work’ as defined above are workers.

The number of total workers in the study area is 1,20,281 which are 35.76% of total population. Out of which 85.88% is male and remaining 14.12% is female. Total workers further divided into main workers and marginal workers.

Table 56: Working Population in the Study Area Occupational Structure in the Study Area

Total Total Working Total Total Working Villages/Town Population Population Working Male Female

Mathak 2,278 657 620 37 Tuna 5,114 1,554 1,337 217 Rampar 1,262 366 317 49 Sanghad 4,279 1,583 1,187 396 Mithi Rohar 13,712 4,093 3,751 342 Shinay 4,345 1,603 1,263 340 Kidana 15,669 5,181 4,489 692 Bharapar 1,462 736 687 49 Chandrapar 26 11 11 00 Total Village 48,147 15,784 13,662 2,122 Kandla 15,782 6,270 5,706 564 Gandhidham 2,47,992 89,634 76,072 13,562 Antarjal 11256 3,631 3,207 424 Galpadar 13,155 4,962 4,646 316 Total Town 2,88,185 1,04,497 89,631 14,866 Grand Total 3,36,332 1,20,281 1,03,293 16,988 (Source: Census 2011) The graphical representation of the above said working population of the study area is shown below:

Mantec Consultants Pvt. Ltd. Page 137

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.8.3.2 Main Workers Total number of main workers in the study area has been worked out to 1,12,070 which is 93.17% of total workers and 33.32% of total population of the study area. The village/town wise distribution of main workers is presented in the table below: Table 57: Distribution of Main Workers in the Study Area Distribution of Main Workers in the Study Area Total Total % Main Main Main Villages/Town Main Workers- % Male Workers- % Female Workers Workers Workers Male Female Mathak 657 629 95.74 600 95.39 29 4.61 Tuna 1554 1333 85.78 1232 92.42 101 7.58 Rampar 366 308 84.15 291 94.48 17 5.52 Sanghad 1583 1440 90.97 1074 74.58 366 25.42 Mithi Rohar 4093 3900 95.28 3649 93.56 251 6.44 Shinay 1603 1414 88.21 1231 87.06 183 12.94 Kidana 5181 4920 94.96 4311 87.62 609 12.38 Bharapar 736 721 97.96 675 93.62 46 6.38 Chandrapar 11 11 100.00 11 100.00 00 0.00 Total Village 15,784 14,676 92.98 13,074 89.08 1,602 10.92 Kandla 6270 5850 93.30 5454 93.23 396 6.77 Gandhidham 89634 83376 93.02 72015 86.37 11361 13.63 Antarjal 3631 3444 94.85 3149 91.43 295 8.57 Galpadar 4962 4724 95.20 4490 95.05 234 4.95 Total Town 1,04,497 97,394 93.20 85,108 87.39 12,286 12.61 Grand Total 1,20,281 1,12,070 93.17 98,182 87.61 13,888 12.39 (Source: Census 2011)

3.8.3.3 Cultivators The person who is engaged either as employer, single worker or family worker in cultivation of land owned is termed as cultivator. Total cultivators in study area are 1,257 which is about 1.05% of total workers, out of which 77.33% are male and remaining 22.67% are female. Village/Town wise distribution of Cultivators in the study area is presented in the table below:

Table 58: Cultivators break-up in the Study Area Cultivators in the Study Area Total Total Total % Total Male % Male % Female Village/Town Female Workers Cultivators Cultivators Cultivators Cultivators Cultivators Cultivators Mathak 657 111 16.89 106 95.50 05 4.50 Tuna 1554 119 7.66 110 92.44 09 7.56 Rampar 366 32 8.74 30 93.75 02 6.25 Sanghad 1583 66 4.17 61 92.42 05 7.58 Mithi Rohar 4093 148 3.62 122 82.43 26 17.57 Shinay 1603 285 17.78 185 64.91 100 35.09

Mantec Consultants Pvt. Ltd. Page 138

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Kidana 5181 80 1.54 57 71.25 23 28.75 Bharapar 736 23 3.13 22 95.65 01 4.35 Chandrapar 11 05 45.45 05 100.00 00 0.00 Total Village 15,784 869 5.51 698 80.32 171 19.68 Kandla 6270 09 0.14 07 77.78 02 22.22 Gandhidham 89634 291 0.32 183 62.89 108 37.11 Antarjal 3631 24 0.66 23 95.83 01 4.17 Galpadar 4962 64 1.29 61 95.31 03 4.69 Total Town 1,04,497 388 0.37 274 70.62 114 29.38 Grand Total 1,20,281 1,257 1.05 972 77.33 285 22.67 (Source: Census 2011)

3.8.3.4 Agricultural Labour Persons working on the land of others for wages or share in the yield have been treated as agricultural labours. The total agricultural labours has been worked out to about 1,241 which is 1.03% of total workforce, out of which 65.43% are male and remaining 34.57% are female. The share of agricultural labour is higher in the villages compare to the town areas of the study area. Village/town wise distribution of agricultural labours of the study area is shown in the table below:

Table 59: Agricultural Labours’ break-up in the Study Area Agricultural Labours in the Study Area Total Total % Total Agricultural Total Male % Male Village/Town % AL Female Female Workers Labours AL AL AL AL (AL) Mathak 657 65 9.89 56 86.15 09 13.85 Tuna 1554 91 5.86 23 25.27 68 74.73 Rampar 366 07 1.91 04 57.14 03 42.86 Sanghad 1583 27 1.71 21 77.78 06 22.22 Mithi Rohar 4093 155 3.79 127 81.94 28 18.06 Shinay 1603 225 14.04 88 39.11 137 60.89 Kidana 5181 88 1.70 63 71.59 25 28.41 Bharapar 736 01 0.14 01 100.00 00 0.00 Chandrapar 11 00 0.00 00 0.00 00 0.00 Total Village 15,784 659 4.18 383 58.12 276 41.88 Kandla 6270 18 0.29 14 77.78 4 22.22 Gandhidham 89634 414 0.46 294 71.01 120 28.99 Antarjal 3631 80 2.20 64 80.00 16 20.00 Galpadar 4962 70 1.41 57 81.43 13 18.57 Total Town 1,04,497 582 0.56 429 73.71 153 26.29 Grand Total 1,20,281 1241 1.03 812 65.43 429 34.57 (Source: Census 2011)

3.8.3.5 Household Industrial Workers Total number of Household Industrial Workers in the study area has been worked out to 1,769 which is 1.47% of total workers, out of which 72.30% is male and remaining

Mantec Consultants Pvt. Ltd. Page 139

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 27.70% is female. Village/Town wise distribution of household industrial workers in the study area is presented in the table below:

Table 60: Household Industrial Workers break-up in the Study Area Household Industrial Workers in the Study Area Total % Total % Total % Male Total Female Female Village/Town Household Household Male HH HH Workers HH HH Workers Workers Workers Workers Workers Workers Mathak 657 06 0.91 06 100.00 00 0.00 Tuna 1554 104 6.69 94 90.38 10 9.62 Rampar 366 13 3.55 06 46.15 07 53.85 Sanghad 1583 01 0.06 00 0.00 01 100.00 Mithi Rohar 4093 130 3.18 96 73.85 34 26.15 Shinay 1603 05 0.31 01 20.00 04 80.00 Kidana 5181 37 0.71 27 72.97 10 27.03 Bharapar 736 01 0.14 01 100.00 0.0 0.00 Chandrapar 11 00 0.00 00 0.00 00 0.00 Total Village 15,784 297 1.88 231 77.78 66 22.22 Kandla 6270 22 0.35 12 54.55 10 45.45 Gandhidham 89634 1385 1.55 999 72.13 386 27.87 Antarjal 3631 39 1.07 18 46.15 21 53.85 Galpadar 4962 26 0.52 19 73.08 7 26.92 Total Town 1,04,497 1,472 1.41 1,048 71.20 424 28.80 Grand Total 1,20,281 1,769 1.47 1,279 72.30 490 27.70 (Source: Census 2011) 3.8.3.6 Other Workers The total number of ‘Other Workers’ in the study area has been worked out to 1,16,014 which is 96.45% of the total workers, out of which the share of male and female workers are 86.39% and 13.61% respectively. Village/Town wise distribution of ‘Other Workers’ is presented in the table below:

Table 61: Other Workers break-up in the Study Area Other Workers breakup in the Study Area Total Male % Male Female % Female Total % Other Village/Town Other Other Other Other Other Workers Workers Workers Workers Workers Workers Workers Mathak 657 475 72.30 452 95.16 23 4.84 Tuna 1554 1240 79.79 1110 89.52 130 10.48 Rampar 366 314 85.79 277 88.22 37 11.78 Sanghad 1583 1489 94.06 1105 74.21 384 25.79 Mithi Rohar 4093 3660 89.42 3406 93.06 254 6.94 Shinay 1603 1088 67.87 989 90.90 99 9.10 Kidana 5181 4976 96.04 4342 87.26 634 12.74 Bharapar 736 711 96.60 663 93.25 48 6.75 Chandrapar 11 06 54.55 06 100.00 00 0.00 Total 15,784 13,959 88.44 12,350 88.47 1,609 11.53

Mantec Consultants Pvt. Ltd. Page 140

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Kandla 6270 6221 99.22 5673 91.19 548 8.81 Gandhidham 89634 87544 97.67 74596 85.21 12948 14.79 Antarjal 3631 3488 96.06 3102 88.93 386 11.07 Galpadar 4962 4802 96.78 4509 93.90 293 6.10 Total 1,04,497 1,02,055 97.66 87,880 86.11 14,175 13.89 Grand Total 1,20,281 1,16,014 96.45 1,00,230 86.39 15,784 13.61 (Source: Census 2011)

3.8.3.7 Marginal Workers Total number of Marginal Workers in study area has been worked out to 8,211 which are approximately 6.83% of the total workers. The share of male and female marginal workers is 62.25% and 37.75% respectively. Village/town wise distribution of Marginal Workers is presented in the table below:

Table 62: Marginal Workers break-up in the Study Area Marginal Workers breakup in the Study Area Total % Total Total Total Male % Male % Female Village/Town Marginal Marginal Female Workers Marginal Marginal Marginal Workers Workers Marginal Mathak 657 28 4.26 20 71.43 8 28.57 Tuna 1554 221 14.22 105 47.51 116 52.49 Rampar 366 58 15.85 26 44.83 32 55.17 Sanghad 1583 143 9.03 113 79.02 30 20.98 Mithi Rohar 4093 193 4.72 102 52.85 91 47.15 Shinay 1603 189 11.79 32 16.93 157 83.07 Kidana 5181 261 5.04 178 68.20 83 31.80 Bharapar 736 15 2.04 12 80.00 3 20.00 Chandrapar 11 00 0.00 00 0.00 00 0.00 Total Village 15,784 1108 7.02 588 53.07 520 46.93 Kandla 6270 420 6.70 252 60.00 168 66.67 Gandhidham 89634 6258 6.98 4057 64.83 2201 54.25 Antarjal 3631 187 5.15 58 31.02 129 222.41 Galpadar 4962 238 4.80 156 65.55 82 52.56 Total Town 1,04,497 7103 6.80 4523 63.68 2580 36.32 Grand Total 1,20,281 8211 6.83 5111 62.25 3100 37.75 (Source: Census 2011)

3.8.3.8 Non-Workers The non‐workers include those engaged in unpaid household duties, students, retired persons, dependants, beggars etc. The total number of non‐workers population has been worked out to 2,16,051 which represents 64.24% of the total population. In this category share of male is 34.99% and female is 65.01%. Village/Town wise distribution of non‐workers is presented in the table below:

Mantec Consultants Pvt. Ltd. Page 141

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Table 63: Non-Workers break-up in the Study Area Non-Workers breakup in the Study Area Total Total % Total % Non- Total % Male Village/Town Non- Female Female Population Workers Male NW NW Workers NW NW Mathak 2278 1621 71.16 564 34.79 1057 65.21 Tuna 5114 3560 69.61 1236 34.72 2324 65.28 Rampar 1262 896 71.00 317 35.38 579 64.62 Sanghad 4279 2696 63.01 1012 37.54 1684 62.46 Mithi Rohar 13712 9619 70.15 3403 35.38 6216 64.62 Shinay 4345 2742 63.11 940 34.28 1802 65.72 Kidana 15669 10488 66.93 3604 34.36 6884 65.64 Bharapar 1462 726 49.66 257 35.40 469 64.60 Chandrapar 26 15 57.69 05 33.33 10 66.67 Total 48147 32363 67.22 11338 35.03 21025 64.97 Kandla 15782 9512 60.27 3322 34.92 6190 65.08 Gandhidham 247992 158358 63.86 55412 34.99 102946 65.01 Antarjal 11256 7625 67.74 2684 35.20 4941 64.80 Galpadar 13155 8193 62.28 2837 34.63 5356 65.37 Total 2,88,185 1,83,688 63.74 64,255 34.98 1,19,433 65.02 Grand Total 3,36,332 2,16,051 64.24 75,593 34.99 1,40,458 65.01 (Source: Census 2011) A comparative graphical representation of the above population belonging to the non‐ workers category to the total population and working population is shown below:

Basic Amenities available in the Study Area: The basic amenities including educational facilities, health, drinking water, power supply, approach roads & transportation facilities available in the study area are presented in the table below: Table 64: Basic Amenities Available in the Study Area EDUCATION Type of Institutes Number Primary School (Govt. & Pvt.) 90

Educational Institutions Secondary School (Govt.) 28 Senior Secondary School (Govt. & Pvt.) 24 Degree College‐ Art (Govt.) 01

Mantec Consultants Pvt. Ltd. Page 142

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Degree College‐ Science (Govt.) 01 Degree College‐ Commerce (Govt.) 02 HEALTH Type of Facilities Number Hospital (Allopathic) 02 Dispensary 02 Non‐Govt. Medical Facilities 50 Health Facilities (For In & Out Patient) Non‐Govt. Medical Facilities (For Out Patient) 137 Primary Health Centre 01 Primary Health Sub‐Centre 06 Maternity & Child Welfare Centre 08 WATER Means of Drinking Water No. of Habitations where the facility available Drinking Water Tap 13 Hand Pump 13 Tube Well 12 ELECTRICITY Power for Domestic Uses 13 Power for Agriculture Uses 13 Electricity Supply Power for Commercial or 13 Industrial Uses ROAD Black Topped 12 (Paved/Pucca) Road Approach Road Gravel (Mud/Kachcha) Road 02 Footpath Road 13 TRANSPORTATION Public Bus Services 13 Private Bus Services 11 Road Transportation Auto Services 07 Taxi Services 10

Other amenities available: Agricultural Credit Society, Nutritional Centre (Anganwadi), ASHA, Public Distribution System (PDS) Shops, Nationalized Bank, Cooperative Bank, Sub‐Post Offices, Internet Cafe, Public Telephone Booths, Self‐Help Group (SHG), Public Library and Public Reading Rooms etc.

Mantec Consultants Pvt. Ltd. Page 143

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3.8.4 Impact Identification The habitation and households are not very near to the proposed port site as the area already falls under the property of port. The villages fall in the 7‐10 km. range from the proposed site and hence there will not be much impact to the people. In the construction/operation phases of the project will surely generate employment opportunities, both direct and indirect, for the local people. A number of skilled and unskilled workers can be employed which generate direct or indirect employment and improves the standard of living of the project affected people. Additional facilities such as medical, educational, and infrastructural development will also take place.

3.8.5 Fisheries Proposed barge jetty will be constructed near to the existing port of Kandla Port. Since Kandla Port is one of the major port in India and major portion of the study area is occupied by the Kandla port, and other industrial activities, fishing activities are very limited in the study area. There are no fish landing centre in the study area. As per the information collected from the department of fisheries office at Gandhidham, there is no fish pond as well, in the study area. However, small fishing activity with mechanized and traditional fishing crafts are operating from the Kandla creek.

Mantec Consultants Pvt. Ltd. Page 144

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 4. Anticipated Environmental Impact & Mitigation Measures

4.1 Introduction The current chapters describe probable impact identification on each component of the environment and the compilation of the existing baseline data of those components. The quantification of likely impacts and their evaluation /assessment are discussed in succeeding paragraphs. Prediction of impacts is the most important component of an EIA study. Many scientific techniques and methodologies are available to predict impacts on physico‐ecological and socio‐economic environment. The prediction of the impacts helps to identify the gaps and implement Environmental Management Plan during and after the execution of the developmental activity to minimize the deterioration of environmental quality. In the present study, the most probable impact on various components of the surrounding environment viz. air, noise, water, land, biological and socio‐ economic, due to the proposed development has been predicted.

4.2 Air Environment 4.2.1 Emissions Sources during the Construction phase

The proposed project will have no major considerable stress/ pressure on the environment to give rise to any significant adverse impacts on environment. The only major impacts on air during construction phase are predicted to be caused due to airborne dust arising from the construction activities as well as gaseous pollutants from vehicles used for transportation of construction materials & emission from equipment used during construction phase. The dust particles in the form of particular matters will strongly depend on various activities like movement of vehicles, their speed, excavation of earth, back filling etc during the construction phase.

The probable sources of the dust are the activities of excavation, filling, leveling etc. However it is noticed that, the area of the proposed project is situated close to the creek of Gulf of Kutch; hence the moisture in the soil will not allow the particles to travel to longer distance from the sources.

Mantec Consultants Pvt. Ltd. Page 145

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Beside the texture of soil is mostly sandy, hence the size and density of particles also prevent them from longer travelling. However maximum care will be taken to prevent the particles to be airborne by using water sprinkler system & covering the excavated materials. Hence there will be no significant impacts due to the dust particles. Besides, the dust may also arise from activities for transportation, storage & handling of construction materials, mainly cement. The airborne cement particles can have significant impacts on environment and the nearby marine habitat. For control of the airborne particles of cement enclosed storage facility shall be provided & material shall be covered with tarpaulin during the transportation. Only vehicles having PUC shall be allowed & well equipped handling & transportation facilities shall be provided through out the construction phase.

Further, the air pollutants like PM10, PM2.5, SOx, NOx and CO will be emitted from the DG sets, exhaust of transport vehicles and other machineries. For control of emission from DG set stack of adequate height & internal diameter at top shall be provided to minimize the impacts of emission. The residual impacts of emission from the stack would not be significant to cause any considerable impacts on air.

The impacts on the environment generated during construction phase will be limited to the construction tenure and will be local. Hence looking to the overall facts described above, it can be concluded that the impacts on air due to the construction & erection activities will be minimum or negligible. It is also concluded that by implementing the proper mitigation measures, the adverse impacts will be almost eliminated or minimized to the lowest extent of damage.

4.2.2 Emissions Sources during the Operational phase

The major activity at the port during operational phase is (1) Collection of goods which are to be exported. (2) Loading and unloading of goods that is to be imported or exported. (3) Storing and distribution of imported goods. These goods are specially coal, Fertilizers, food grain, steel, containers etc. As such there is no chemical process or any manufacturing activity involved; hence there will not be any process emission. No gases will be emitted even during

Mantec Consultants Pvt. Ltd. Page 146

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla the operation phase, as the major activity during this phase will be only export and import of cargo. Increase in the vehicular movements & emission from D.G.Set may affect air quality in terms of CO & NOx in an around the premises.

Proper care shall be taken during the Loading and unloading activity of coal by marinating adequate moisture by the way of water sprinkling, enclosure where applicable/suitable, shade for storage, enclosure for transport vehicles/ship/barges/storage vessel, spraying of water on road & ground can effectively implemented to control the coal dust problem. During the operation phase proper EMP shall be in place for handling of coal.

The impact of the air pollution due these will be very negligible as the proposed project is in the coastal area. Due to the considerable wind speed the gaseous pollutant from these sources will get dispersed as soon as they are emitted and hence there will be no considerable impacts on air due the

operation of the project. The short term increase in SO2 will be insignificant enough to have any adverse effect. Moreover it is proposed to develop greenbelt in and along the premises, which will mitigate any adverse impacts on ambient air.

It is therefore concluded that there will no significant impacts on the air environment due to the proposed project. 4.3 Anticipated Impacts Impacts during Construction Phase of the Project

In the gaseous emission following impacts are calculate with the air quality Modeling given below. Increamental value of Pollutents at Container terminal Name of the Pollutants maximum value Incremental value Commulative NAAQS 2009 Limit PM-10 (µg/m3) 84 0.322 84.322 100 PM-2.5(µg/m3) 48 0.204 48.204 60 SO2 (µg/m3) 12 0.329 12.329 80 NO2(µg/m3) 24 4.887 28.887 80

Mantec Consultants Pvt. Ltd. Page 147

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Increamental value of Pollutents at SNA Jetty Name of the Pollutants maximum value Incremental value Commulative NAAQS 2009 Limit PM-10 (µg/m3) 84 0.043 84.043 100 PM-2.5(µg/m3) 46 0.028 46.028 60 SO2 (µg/m3) 13 0.658 13.658 80 NO2(µg/m3) 24 0.329 24.329 80

Mantec Consultants Pvt. Ltd. Page 148

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 34: PM10 Emission at Container terminal

Mantec Consultants Pvt. Ltd. Page 149

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 35: PM2.5 Emission at Container terminal

Mantec Consultants Pvt. Ltd. Page 150

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 36: NOxEmission at Container terminal

Mantec Consultants Pvt. Ltd. Page 151

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 37: SO2 Emission at Container terminal

Mantec Consultants Pvt. Ltd. Page 152

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 38: PM10 Emission at SNA jetty

Mantec Consultants Pvt. Ltd. Page 153

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 39 :PM2.5 Emission at SNA jetty

Mantec Consultants Pvt. Ltd. Page 154

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 40: NO2 Emission at SNA jetty

Mantec Consultants Pvt. Ltd. Page 155

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 41: SO2 Emission at SNA jetty

Mantec Consultants Pvt. Ltd. Page 156

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

4.4 Noise Environment Sources of noise during construction and operational phases and their predicted impacts are discussed below:

4.4.1 Noise Generation during Construction Phase

The major Impact on noise level of the proposed project, during the construction phase, is envisaged due to the noise generation by the operation of the machineries, equipments and some mechanical works. There are many equipments and machineries likely to be used during the construction. These are mainly recognized to be Dozers, Cranes, Excavators, Trailers, Generators, and Concrete Conveyor etc. It is envisaged that noise level due to this equipments will be around 70 dB(A) at receptor point at associated work/construction area. The impacts due to noise of these equipments will be local and temporary as well as negligible due to the efficient implementation of proper mitigation measures like provision of Ear Protective Safety Equipment (ear plug & ear muff) for the personnel likely to be exposed to high noise level. The noise level of these machineries / equipments shall be minimized by proper lubrication, modernization, maintenance, muffling and provision of silencers wherever possible.

The affected area will be the project site under construction activities for development of the proposed projects and nearby area of the region. The area of the projects is in port area and does not have any residential area in the range of noise propagation to cause adverse influence on environment. Further, construction activity would be carried out at daytime to prevent increase in noise level during night time.

There is no considerable habitat of fauna in vicinity of the project site. The major effects of the noise due to the predicted sources will be limited to the workers exposed to the high noise area. Thus, there would not be any considerable impacts on ecological factors as well as social layout. However, considering the adverse impacts on personnel engaged in construction works, efficient mitigation measures shall be planned & implemented. The most

Mantec Consultants Pvt. Ltd. Page 157

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla efficient mitigation shall include provision of PPEs (ear protective safety equipments) as well as planning of work hours & shift of workers as per Factory Act or NIOSH / OSHA guidelines. The workers working at the site shall be equipped with earmuffs /earplug to avoid adverse effects of noise on occupation health & hearing capacity of workers.

4.4.2 Prediction of Noise Quality Impacts Impacts on noise quality during jetty construction are possible due to the following activities:

1. Transportation of construction materials 2. Construction activities including fabrication, welding, precasting 3. Piling operations during construction and capital dredging

Of the above activities, piling and dredging (using cutter suction dredger) operations are the most important and are found to generate noise levels as high as 85 dB (A) and 90 dB (A) at the 10 m from the sources respectively. The pulsating noise levels at receptor locations are determined using mathematical equations. The Mathematical equation is used for noise prediction is

L2 = (L1 - 20 log D2/D1-Ae-An)

Where, L1 and L2 are the noise levels at a distance of D1 and D2 from the noise source;

Ae and An are attenuation due to environment correction and background correction.

Estimated noise levels for the piling and dredging operations at different distances from the source are given in Table 58. The day and night noise levels near the pile‐driving site reduce to within prescribed limits as per “Noise Rules 2000” at distance of 50m and 100m from the source respectively. While, the day and night noise levels near the dredging sites reduce to within prescribed limits as per “Noise Rules 2000” at distance of 100m and 200m from the source respectively. For workers within 100m, sound protection gears are recommended.

Mantec Consultants Pvt. Ltd. Page 158

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla The residential colonies are located away from the piling and dredging sites and hence shall not be subject any noise quality problems as a result of these operations.

Table 65: Estimated Noise Levels For the Piling and Dredging Operations

Distance from Predicted Noise Level Noise standards noise source dB (A) location (m) Piling operations Dredging Day Night 10 85.00 90.00 30 75.46 80.46 50 71.02 76.02 75 70 100 65.00 70.00 200 59.00 64.00 500 51.00 56.00

4.4.3 Noise Generation during Operational Phase During the operation phase the major source expected to increase the noise level at the jetty area are arrival of cargo and vehicular movement to transport export and import goods, conveyor system & operation of DG set for emergency power supply. However this increase in noise level will be lower compared to the construction phase. The increase in noise level would be in the vicinity of plant area and attempts shall be made to reduce the noise level below 75 dB(A) outside the project premises. Proper lubrication, muffling and modernization of equipment shall be done to reduce the noise, D.G.Set with acoustic enclosure shall be provided. Due to increase in various activities there may be some increase in background noise levels. The workers working in the high noise area shall be provided with ear protected equipments. The propagation of noise way would be prevented by creating barrier in form of the proposed greenbelt all around the project area boundary.

During the operation phase the major source expected to increase the noise level at the jetty area are arrival of cargo and vehicular movement to transport export and import goods, conveyor system & operation of DG set for emergency power supply. However this increase in noise level will be lower compared to the construction phase. The increase in noise level would be in the vicinity of plant area and attempts shall be made to reduce the noise level below 75 dB(A) outside the project premises. Proper lubrication, muffling and

Mantec Consultants Pvt. Ltd. Page 159

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla modernization of equipment shall be done to reduce the noise, D.G.Set with acoustic enclosure shall be provided. Due to increase in various activities there may be some increase in background noise levels. The workers working in the high noise area shall be provided with ear protected equipments. The propagation of noise way would be prevented by creating barrier in form of the proposed greenbelt all around the project area boundary.

4.5 Water Environment 4.5.1 Impact in Construction Phase

The Gujarat Water Supply and Sewerage Board (GWSSB) is responsible for developing and managing various sources of water in the region. The important source of water is the 14.5 Million m3 capacity reservoir of Tapar Dam, besides a number of deep tube wells. Water is distributed to Kandla area from high service reservoir near Bhachau through 18” dia. CI mains, after chlorination. The capacities of the elevated water towers and underground reservoirs at Kandla are 1500 kl. and 14000 kl., respectively. The average daily consumption of water at Kandla area is estimated at around 2000 kl. The labour force employed during this phase will be provided potable water to avoid any waterborne diseases. The domestic wastewater / sewage generated from the labour colony will be treated in septic tanks and soak pits and it will be used for developing green plantation, which will be an eco friendly solution.

The major impacts on marine water quality are envisaged due to the civil works activities like driving of piles, construction of berth, approach way, movement of construction equipments etc. will have a high potential to disperse the fine grained sediments in the water, thus increasing the particular load which in turn can adversely influence the photosynthetic activity further affecting the marine life. However this rise in turbidity will be only during the construction phase. Considering the proposals and developers commitment adverse impact on water resources is not envisaged.

Mantec Consultants Pvt. Ltd. Page 160

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla The runoff from the site containing construction materials, debris, and construction waste and excavated earthen materials may have adverse impacts on the water environment especially on nearby marine water resources. Further the dispersion of fine sediment of runoff in the water during the construction activities can increase the particulate load in the neighboring aquatic habitat, which in turn can increase turbidity in and consequently affects the rate of the photosynthetic activity of the aquatic life. Proper mitigation measures shall be implemented to avoid such runoff as well as spillage of construction materials so that the materials in runoff cannot enter in to the water bodies. However it is to notice that this rise in turbidity will be only during the construction phase and the incidence of turbidity will be minimal due to prevention of any runoff from site. Thus the impacts will be short term and minor. By implementing proper mitigation measures, adverse impact on water resources due to the turbidity will be minimized. Water conservation actions shall be taken during the construction phase by associated workforce & officials. Potential impact on groundwater resources is not envisaged as there will not be any toxic material release in sub soil region having potential of ground water contamination.

4.5.2 Impact in Operational Phase

For operation purpose major portion of water will be reused for various purposes like sprinkling on coal & washing. Thus on regular basis the actual requirement of water supplied by GWSSB will be reduced to a great extent. However, the wastewater from the two major activities, washing and sprinkling on coal, will be collected in a collection sump. This effluent shall be transferred to STP at regular intervals. The effluent will mainly be containing very little quantity of suspended particles as major constituent. These pollutants can easily be treated to achieve the desired water quality. For the treatment of domestic wastewater adequate size STP already exists.

Mantec Consultants Pvt. Ltd. Page 161

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 4.6 Land Environment 4.6.1 Impacts during Construction Phase Land use patterns of the surrounding area would not changed as it already used for port activity with some open land/back‐up area. The proposed project is in the water front of marine water course of Gulf of Kutch. The project requires 111.5 hectares of land for the development of the proposed projects. The company has conducted a preliminary survey of the land required for the development of proposed activities. The outcome of the survey reveals that the area is adequate for the proposed port. The land is generally barren and saline soil having low nutrients. At present the site is almost devoid of vegetation, so major clearance of vegetation in site for development of proposed projects is not required. Hence, there would not be any adverse impacts on land cover is envisaged. However some degraded mangroves colonies are noticed in the area, which is very less in quantity. Surrounding Region has no agriculture areas, but salt work areas are the major observed activity in the area. Salt tolerant plants dominate general vegetation of this region. An extensive low‐lying coastal area, which gets inundated during high tide are mostly barren. Hence overall the project site is considered as wasteland.

The construction activities like excavation for foundation, earth‐filling, clearing, stripping, levelling the sites and vehicular movements will entail changes in the landscape, which are expected to be of short duration and not much significant. The excavated earth material if stacked loosely may result into runoff to the mud flats resulting in loss of topsoil. Excavated earth will be stored in stockpiles and covered with plastic/tarpaulin sheets & will be maintained separately and reused for landscape development along the corridor. A temporary labour colony will be developed. Solid wastes generated from the colony will be taken care by the waste disposal plan. The construction waste may pose impacts on land environment by contamination of soil and hence the wastes shall be utilized for PCC works, Road construction, and other filling requirement etc the accidental spillage of fuels and lubricants oils will be minimized by proper care. Since this phase is temporary impact is marginally negative and short.

Thus looking to the over all scenario the proposed project would have considerable beneficial impacts due to affirmative utilization of waste land as

Mantec Consultants Pvt. Ltd. Page 162

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla well as significant green belt development of non‐vegetative land area of the premises.

4.6.2 Impacts during Operational Phase

Under ordinary and safe operating conditions, no adverse impact is anticipated on land during the operation phase. The only source of land pollution would be the solid waste generated from the area and workers hutments. The garbage shall be disposed to the Municipal solid waste disposal site. Spillage of fuel oil and lubricants will be collected in the trench and will be stored along with the waste oils. The same will thereafter be given to the MoEF authorized recyclers. Thus the land pollution during the operation phase is minimal and not likely to create any significant impact with proper EMP in place.

4.7 Biological Environment (Marine Ecology of Creeks)

Developmental activities e.g. Industrialization have negative impact on ecology of surrounding area. Primarily biodiversity may get affected by the project activities hence it is essential to identify the possible impacts of any proposed project on biodiversity and find out the way to mitigate impact in sustainable manner. Impact on Ecology As per primary ecological study there no any Rare, Endangered, Threatened floral and faunal species were found in the study area. No economically important plants, medicinal plants are found inside the study area.

The native flora and fauna of study area may affected by construction and operation of port. However impact on flora and fauna and marine biodiversity may be temporary. Project may cause bit habitat degradation. Following table describes briefly how the port construction may affect the plants species. Development Process Sources of Impact Cleaning and preparation of site Vegetation and upper most fertile soil will be removed Transportation of construction Fugitive dust particles and vehicular pollution may material to the site affect the leaf of the plants and lower down the photosynthetic capacity of the plants. Movement of vehicles heavy Soil compaction may take place

Mantec Consultants Pvt. Ltd. Page 163

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla machineries Construction activity and Activities may cause noise and vibration. Due to vehicular movement which species may migrate some other places Un-managed soil stock piling Soil may runoff during rains and may accumulate in the nearby areas Temporary labour shelters, office Solid waste shall be generated and if not managed then it will affect the ecology of the local area

The project will create significant ecological and environmental impacts on the following components:  Aesthetic value loss (Due to construction activities the area would depreciate aesthetic value of the area, only an effective and systematic greenbelt development can help improving the aesthetic value of study area)  Soil compaction (Vehicular movement and movement of machinery equipment may exert the negative impacts on soil fertility cause soil compaction, microbial biomass etc.)  Discharge of wastewater (water will be stored into nearby abandoned voids)  Ambient Air Quality (air pollution due to land excavation and vehicular movements).  Ambient noise quality (HEMM and vehicular movement).

Proposed Mitigating Measures To mitigate the possible impacts of proposed project on ecology of the surrounding area following mitigation measures would be taken in to consideration I. Site preparation would be carried out using cutting edge technology to reduce the impact of vibration and noise on Ecology and biodiversity. There must have some monitoring mechanisms to look after the day to day environment of the project and to ensure that the mitigation measures are implemented effectively in function. II. Fugitive particles remain always an issue. To mitigate the impact of such emissions water sprinkler will be used on approach road. III. Greenbelt will be developed in three tier system with the help of economically beneficial shrubs/ trees. Greenbelt shall be developed along approach road, office

Mantec Consultants Pvt. Ltd. Page 164

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla settlements and designated areas. Green belt will also be very useful for noise attenuation. IV. Institutional mechanism like separate cell will be established to supervise and monitor various mitigation measures.

The impact of the proposed projects on the biological environment of the shore and the creek can be as follows: 1. Impact during construction phase 2. Impact during the operation phase Impact during Construction Phase During the construction of any project the following activities may have directly or indirectly impact on the flora & Fauna. a. Transportation of heavy vehicles:  During the construction of project the transportation of heavy vehicle will generate fugitive dust, noise while movement. The dust then will be settled over leaves of plants of nearby areas and hence reducing the photosynthetic capacity of the plants.  Noise created due to increased traffic will have impact on the near by fauna, it may have impact on the wild nocturnal animals.  Because the project is situated in the industrial area so it will have very minimum impact on the wild animals. However, the minor impacts of vehicular noise is envisaged which will be mitigated by avoiding night transport activities. Even some high noise generating construction activities will also be conducted in day time only. Impact shall rest upto construction time only b. Impact due to Clearance on land flora:  Due to construction activity the land flora along the sea can be removed.  At the sites of Tuna and Kandla where jetty is proposed is presently occupied by some herbs and shrubs. This vegetation will be cleared off during the construction period.  The clearance of weeds and common shrubs will not have much impact as it is in industrial area. c. Impact due to Piling activity:

Mantec Consultants Pvt. Ltd. Page 165

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla  During the construction of jetty, piling will be done in the sea to make the berths. During the piling the sea water quality will be impacted and hence giving impact on the primary productivity of the sea.  Movement of aquatic fauna can affect.  The impact will be temporary during the construction period only and it is in the area where already ship movement is going on. d. Impact due to dredging:  Movement of aquatic fauna may get affected due to the dredging during construction phase. Turbidity of the water may increased and may reduce the number of and the production of the phytoplanktons. This shall directly affect the zooplanktons and then entire food chain.  At the dredging sites, the initial disturbance to benthic organism may result in smothering / death during dredging operations. Normally communities are expected to regenerate in a period of three months. During this period the food web of the marine ecosystem will be disturbed. The fishes and other marine fauna which feed on phytoplankton/ zooplanktons will migrate from this site due to unavailability of the food and disturbance in its habitat.  This will have a long term impact as the capital dredging shall be regularly followed by maintenance dredging.

Impact during Operation Phase Impact due to operation of any project is of main concern as it always persists. And if any major impact is envisaged it is going to permanently affect the environment. In this proposed projects jetty construction is the main activity which will have major consequences like increased ship movement, increased chances of spilling of oil, wastes etc. a. Discharge of Oil & wastes from the ships in to the sea:  Due to increased traffic movement may increase the chances of increased spillage of oil and other wastes in the sea. The oil and petroleum products are very injurious to the flora and fauna of the marine ecosystem. The oil spreads on the water surface and makes a film over it reducing the dissolved oxygen level in the water.

Mantec Consultants Pvt. Ltd. Page 166

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla  It may have adverse impact on the marine ecosystem including the fishes. Hence, the solid wastes, sewage, oily ballast, bilge water and bunker fuel bottoms generated from ships should not be discharged directly and it should be discharged as per the norms.

b. Impact on Mangroves, Seaweeds and algae:  Mangroves, seaweeds and algae show greater sensitivity to fresh rather than weathered crude oil. Oil may however, block the openings of pneumatophores and hamper the breathing mechanism of mangroves or interfere with salt balance, killing the trees.  Moreover, mangrove areas at Kandla and Nakti Creek are invariably associated with rich fauna which will suffer severe damage in case of major oil spill occurs due to accident / eventualities.  Green algae are more sensitive to petroleum than diatoms, blue green algae and flagellates. An oil spill can however cause immediate and localized retardation of photosynthesis, though temporarily. The community structure of phytoplankton may get altered due to major accidental oil spill. The intertidal seaweeds, algae and mangroves will be adversely affected if their habitats get oiled.  The general impact of a spill on the flora of the affected and will be temporary and reversible though recovery might take 2 y or longer. c. Zooplankton:  An increase in concentrations of dissolved PHc in water subsequent to a spill can lead to plankton kills. The recovery of plankton will be however quick through repopulation of the community by fresh recruits from adjacent areas not affected by oil. Eggs and larvae of fishes, crustaceans and molluscs which are highly sensitive to even low concentrations of PHc (10-100 μg/l) and aromatics (1 - 5 μg/l) in particular will be severely affected.  However, it is unlikely that any localized losses of fish eggs and larvae caused by a spill will have discernible effect on the size or health of future adult populations.

Mantec Consultants Pvt. Ltd. Page 167

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla d. Benthos:  These organisms have limited movements and hence are more vulnerable to oil spills. If the thick weathered oily mass spread on intertidal areas, immediate mortalities of organisms in the zones of physical contact are expected.  If the residue persists for longer time in the sub tidal or intertidal segments due to sluggish local circulation, the recovery will be delayed. Thus, the benthic organisms of exposed shores will recover much faster than of sheltered habitats like lagoons, mangrove swamps, marshes etc. Similarly, benthic organisms of sandy habitats will recover faster as compared to those of the muddy intertidal segments where oil might penetrate into subsurface layers through animal burrows and might remain there for decades due to very low natural weathering of oil in such sheltered habitats.  The asphalt pavement formation on heavily oiled sandy beach or sheltered mud flat it occurs will delay the return of burrowing fauna, a primary source of food for aquatic birds. Clams will be killed in heavily oiled benthic habitats whereas polychaetes might survive on moderately oiled sediment bottom. Benthic system might recover back to normal in about 2 to 3y. e. Fishes:  A large oil spill can temporarily reduce the fish catch from the area as fish might migrate from the affected zone. Limited mortality may also occur particularly when the oil concentrations in water go abnormally high. Fishes are sensitive to oil and tend to avoid petroleum.  Often fishes get tainted and unpalatable but become normal when the ambient PHc level approaches the baseline which is expected within a few days.  The mangrove swamps being the breeding and nursery grounds for a variety fish and shell fish, large scale mortality of eggs and larval stages of several economically important groups may occur if oil is transported to these habitats during major accidental oil spill. Local fishermen may

Mantec Consultants Pvt. Ltd. Page 168

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla get affected by getting either contaminated fishes/crabs/larvae etc. or poor catch but temporary.

f. Impact on Fishery:  As per the information collected from fisheries department Kutch, district and Deendayal Port Trust the largest Fish landing is at Badreshwer and at Jakhau. Jakhau is the main fish landing site of the Gulf with about 66.2% of total fish landing in the area.  There is very small fishing activity in the DPT area as the fishing in this region is prohibited. Only some illegal fishing activity is done in some creeks by near by village persons. The nearest fish landing site from the proposed site is village Veera, which is about 15 km westward. Badereshwer is approximately 20 km from the DPT area.  So it can be estimated that there will be negligible impact on the fishing activity due to the proposed project.

Table 66: Consolidated list of Impacts with Remedial measures Environmental Issue/ Impacts Description Remedial Measure Component Construction Phase Water sprinklers shall be used to suppress the dust; During site clearance weeds Terrestrial Flora Fugitive Dust emission; will be uprooted, no & Mangroves Clearance of terrestrial flora at site, mangroves will be disturbed, proper care will be taken to plant them with proper conservation plan.

Mantec Consultants Pvt. Ltd. Page 169

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Speed of vehicles during Traffic during night will result in night will be kept under Terrestrial & light & horn affecting the nocturnal control, maximum aquatic fauna fauna. transportation will be done in day time. Pilling and dredging shall be done by such methods so as Pilling & dredging will lead to to reduce the impact. increased turbidity, less penetration Phytoplankton, Silt curtain shall be used to of light and hence less zooplanktons, reduce the impact of photosynthesis and resulting less Benthos & fishes turbidity and thus reducing primary productivity. Due to this the loss of primary fishes and other fauna may migrate. productivity and subsequent impact on food chain. Care shall be taken to Spillage or leakage of construction minimize the chances of the Sediment material and deposition on the Spillage or leakage of bottom construction material. Operation Phase

No discharge from ships shall be allowed, Spillage of Oil & wastes from Ships Due care shall be taken from Flora & Fauna may impact on the creek biota, spillage of the oil and other especially mangroves and fishes. chemicals during loading or unloading.

Thus looking to the overall facts and details, it has been envisaged that the construction & Operation of proposed project would have adverse impacts on biological environment of project area but can be mitigated and compensated through appropriate mitigation measures and conservation, management, greenbelt development, awareness and training programmes.

Mantec Consultants Pvt. Ltd. Page 170

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 4.7.1 Mangroves Conservation Plan

For the conservation of mangroves we suggest technical application for its increased population along with the awareness and education among the local people. The technical plan and guidelines for plantation is as follows:

1. Mangrove plantation is necessary on the open mud flat. At present these are sparse and needs high density plantation to combat the cyclonic threats and erosion. 2. Mangrove tree diversity is quite low and different spp. needs to be introduced taking into consideration of the local ecology. Particularly species of Rhizophoraceae family would be more effective. 3. Intertidal mangrove nurseries need to be planned on large scale for massive, high density plantation. 4. Natural regeneration should be encouraged and deforestation discouraged. 5. The Shelter belt concept to be strictly followed. 6. The succession and zonation patterns should be followed during plantation. 7. Continuous monitoring, gap filling and health of seedlings to be monitored. 8. Following guidelines to be followed.

Guidelines for Mangroves Plantation

I) High Density Plantation in Intertidal Mudflats, Including, Stabilinzing Creek Banks and Shoreland

a) Plantation of 2500 polyp at seedlings at distance of 1x1m; b) Seed sowing at spacing of 0.5m X 0.5m for Avicennia sp. and 1m x 1m for others like Rhizophors sp.; c) One can develop a model, combining model 1(a) and 1(b) and cost can be estimated as per ratio of two models. In sparse mangroves, population of seedling may be reduced accordingly and cost may be worked out.

II. Planting with Trenching:

This model of plantation is practiced in Andhra Pradesh and Tamil Nadu in saline banks or mudflats with Suaeda cover. Mangrove height and vegetation

Mantec Consultants Pvt. Ltd. Page 171

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla changes as one moves from seaward to landward and hyper saline lands which are normally found in backward of mangrove line. Good quality of mangroves is found in the area where tidal water reaches every day. In hyper saline area tidal water reaches occasionally due to marginal elevation of land from the mudflats of good mangrove area. Formation of hyper saline mudflat is natural process which occurs as a result of deposition of silt and high evapo‐ transpiration. This process is fastened when rivers and streams discharge high quantity of silt in the sea. The final result is the ‘saline blanks’ where tidal water cannot reach and the soil salinity is very high.

Digging of trenches facilities supply of tidal water within trench, which is normally used for planting mangrove seedlings. Successful plantations have been raised in some areas in the two states along the trenches but its long term survival is debated. Digging of trench involves disruption of natural process. This may provide temporary relief for regeneration of mangroves but there may be likely negative impact of ecology of the area. Mangroves enhance the process of land building by trapping silt. In this process, mangrove line slowly moves seaward in new mudflats whereas backward mangroves exterminate due to increase in salinity as a result of rise of mudflat. Saline mudflats with or without sparse Suaeda cover is ecotone are between terrestrial ecosystem and mangroves and brings ecotonal effect. This adds to the diversity of coastal wetlands, which results into rich diversity 3 of the area. Some mudflats with Suaeda are ecologically important for enhancing productivity or benthic organism. During winter and monsoon, thousands or birds use this area for feeding and nesting. Such areas are preferred habitats of waders as they feed in muddy area. Migratory birds also use such land for feeding and nesting.

There is a possibility of negative impacts of activities to trench digging on habitat and biodiversity therein. Man’s knowledge is limited and hence he should have faith in nature. For cause of mangrove development, there should be minimum disturbance to natural process. Excess excavation may result into erosion of mudflats as well as addition of silt load in water. This slit may have some impact of marine life.

Mantec Consultants Pvt. Ltd. Page 172

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla In the background of above, fact, scale of trenching for plantation of mangrove species should be very low and preference should be given for afforestating intertidal mudflats. The following guidelines should be followed for planting with trenching.

a) Trenching should be done in restricted area, leaving enough space for, maintenance of ecology. Thus, major part of the mudflat should not be disturbed. b) Disruption and excavation of mudflat should be minimum with careful designing of trenching. c) Trenches should be dug far away from the main creek. d) Mudflats having very gentle slopes should be preferred and should be extended up to distance where elevation of hyper saline mudflats does not exceed 10 cm to 15 cm form the level of mudflats supporting good mangroves; e) Since it is very high cost model of afforestation, other suitable species should be preferred over Avicennia.

III. Enrichment Plantation:

The main objective to this model is to improve biodiversity of the area and also to improve mangrove genetic resource conservation. Under this model, threatened species should be planted at appropriate site. Preference should be given to those species which have been exterminated from the area. Sometimes seeds or propagules maybe imported from other states for raising nursery. About 200‐400/ha should be planted in this model of afforestation.

IV. Awarness And Education:

This component of programme may include activities like: i) Conducting nature education camps for coastal peoples, especially students ii) Camps, meetings of villages to highlight importance of conservation of mangroves. ii) Educational tours for villages and field staff,

Mantec Consultants Pvt. Ltd. Page 173

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla iii) Publishing literature on mangroves, their roles and regeneration techniques.

V. Training: Training is important for capacity building of all partners Involved in mangroves forests. This may include: (i) Training for fishermen and other coastal people on mangrove and related activities like fisheries, honey farming etc. (ii) Training for fishermen, local staff to develop arrangement for participatory Mangrove development. (iii) Inter‐state visit for field staff and fishermen (iv) International training to forest officers to improve their capability in planning assimilation of new technology.

4.8 Socio-Economic Environment 4.8.1 Impact during Construction Phase Due to the proposed project a significantly higher affirmative changes in the socio‐economic quality is foreseen, beneficial impacts of proposed project on socioeconomic layout of project area would start its occurrence from construction phase itself. Significant opportunity of direct & indirect employment and uplifting of the economic status of the area will be the major affirmative impact of the proposed projects. Besides, the adverse impacts on socioeconomics are not envisaged during the construction phase. Project developer will employ local people in the construction phase to meet the significant human resource requirement for construction works so that the locals would get opportunities for employment. Beside this, the local population would also get opportunities in related services activities like small contractors, sub contractors, supply of construction materials, supply of basic facilities like eatables to the site etc. The construction activities will generate lot of employment in the ancillary activities.

The project area is well connected with road networks and hence issue of traffic and transport infrastructure issues are not envisaged. The nearest locality is situated about 13 km away from site hence nuisance due to noise generation is also not envisaged. However, the minor impacts of vehicular noise is envisaged which will be mitigated by avoiding night transport

Mantec Consultants Pvt. Ltd. Page 174

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla activities. Even some high noise generating construction activities will also be conducted in day time only.

Thus looking to the overall facts and details, it has been envisaged that the construction phase of proposed project would not pose any adverse impacts on socioeconomic layout of project area but will have significant beneficial impacts due to increased direct & indirect employment for construction works.

4.8.2 Impact during Operational Phase Similar to the construction phase, the operation phase will provide significant opportunities for employment in skilled, semi skilled & unskilled categories. This would multiply economic opportunities, and henceforth enhance the livelihood patterns of this region. Amenities like fresh water for port complex, transportation facility, green belts etc would positively enhance the infrastructure. Maximum of the human resource requirement will be met by local employment. Thus the proposed project would considerably beneficial to the socioeconomic conditions of local area. Rise in indirect employment and enterprise development due to proposed project would also be significantly beneficial to the economy of local area. These indirect employments would proliferate economic opportunities & conditions, henceforth enhance the livelihood patterns of this region. During the operation phase the operational & vehicular noise may have some impacts but as mentioned earlier by implementation of necessary mitigations for noise control such impacts would be avoided. Welfare activities along with employment done by project proponent will improve the socio‐economical condition as well status of health & education in the region.

Thus looking to the overall scenario of activities & probable impacts of the proposed projects, it has been envisaged that there will be an overall improvement in socioeconomic layout of project area will be the key benefits of the proposed projects. The adverse impacts will be almost none during the operation phase of project. The proposed project would bring over significant improvement of economic condition of local area, state & our nation by leading its activities of ship building & repair to the global platform.

Mantec Consultants Pvt. Ltd. Page 175

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Summary of the mitigation measures during construction of proposed projects are tabulated as Table-59.

Mantec Consultants Pvt. Ltd. Page 176

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Table 67: Summary of Mitigation Measures

S.No. Particulars Location Quantification Proposed Measures 1 Generation of  Applicable to Not quantified  Spraying of water Particulates the proposed  Reducing speed of vehicles projects and  Deploying vehicles with surrounding PUC certificate 2 Generation of  Along Not quantified  Restricted operation in the Noise proposed night time projects  Selection of machinery generating noise less than 72 db(A)  Fitting on noise attenuation devices Soil & Geology 3 Soil erosion  Applicable to Not quantified;  Water bars; stabilization of the proposed initiates a chain slopes projects of impacts  Controlled discharge of water  Conducting construction activities in non‐monsoon season  Oil spill prevention measures Hydrology 4 Surface water  At the Not quantified  Soil erosion control contamination proposed measures projects  Spillage and  Soil erosion  Waste management and sanitary prone area spill control wastes 5 Ground water  Not expected contamination Land Use and Aesthetics 6 Land use and  At project site Not quantifiable  Contouring of the affected Aesthetics  At campsites areas  At other  Cleaning the stretch utilities like immediately after the scraper construction activities are stations over  Restoration and re‐ vegetation to the best possible extent Biological Environment: Flora and Vegetation 7 Due to dusting  At project site  Limited  Sprinkling of water for dust on floral cover & approach suppression. road 8 Removal of  At project site  Limited  Restoration and re‐

Mantec Consultants Pvt. Ltd. Page 177

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

vegetation vegetation and plantation  Compensatory vegetation 9 Due to Piling  At project site  Limited  Piling should be done in activity closed vessels to minimize the impact. 10 Due to dredging  At project site  Not  Silt curtain should be used in Sea quantified to minimize the impact. 11 Oil spillage &  Sea & creeks  Unlimited  Oily wastes and sewage waste disposal should not be discharged from ships directly.  MARPOL norms should be followed. 12 Fishes & Fishery  In project area  Limited  No legal fishery is in study area, major fish landing site is far from project site. Fauna and Wildlife 13 Loss of wildlife  No wildlife Not applicable  Strictly prohibiting hunting habitation in and similar activities proximity  Restricting the speed of movement of vehicles  Keeping “trench plugs” at strategic locations  Shifting the nests, wherever possible Socio-Economic and Cultural Environmental 14 Human  No habitation Not quantified, Villagers in the proximity will habitations falling within but critical kept informed on the project affected the project site locations are activities identified 15 Economic  Along the Not quantified.  Compensation to the implications project site The affected people implications  Employment, wherever with regard to possible, to the unskilled loss of seasonal local people crops and plantations are identified 16 Agriculture lands  At project site No agriculture  Restoration of the land land involved.  Management of topsoil

17 Infrastructure  Near human Not quantified  Rehabilitation of the habitations affected infrastructure  Road and components railway  Leaving behind the crossings infrastructure facilities like approach roads and facilities at the campsites for the local inhabitants 18 Social conflicts  Surrounding the Not quantifiable  Keeping good relationship proposed with the local people

Mantec Consultants Pvt. Ltd. Page 178

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

project.  Keeping them informed on the project and project development.

19 Political conflicts ‐ Not quantifiable  Keeping the key players informed on the pros and cons of the project.

20 Historic and  Surrounding No structure on  Inform the concerned archaeological the 15.0 Km. the surface authority in case of importance radius from the possibilities are coming across any proposed there of sub‐ structure of archaeological project. surface significance. structure

4.9 Dispersion Modelling for dumping of the dredge materials

A three‐dimensional (3D), PT model was applied to simulate the fate of sediment suspended by the proposed construction operations. The model predicts the transport induced by currents, dispersion, settling and re‐ suspension processes. The MIKE Hydrodynamic (HD) model is used to provide a description of the current patterns which is underpinned by the HYCOM model which simulates the water flows in the sea & coastal area. The currents in this region are predominantly driven by the complex interaction of density gradients (due to freshwater inputs, atmospheric conditions and wind setup) local winds, astronomical and Coriolis forcing. The PT model uses output from the HD model to predict particle movements in a Lagrangian frame of reference. The flow regime is seeded with particles having defined properties, e.g. size, density, setting velocity and critical shear stress, etc. which are then tracked as they move with the flow. The PT model is capable of tracking the individual particles of different sizes from different sources and at different positions within the water column. This is a useful means of visualizing flow patterns, particularly eddies and recirculation cells but can also be used to examine the movement of material from dredging and arising from the construction of the gas pipelines along the coast have been disposal activities. The model outputs include spatial plot of sediment concentration resulting from the dredging and disposal operations.

Mantec Consultants Pvt. Ltd. Page 179

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla The sediment plumes assessed using the MIKE FM Particle Tracking model. This approach includes the influence of a range of hydrodynamic and meteorological conditions (wind and current speed and direction) typical for the site. A total of two modelling scenarios representing different tidal currents, dredging and disposal conditions have been investigated . The model results were then used to define the spatial extent of the turbidity and sedimentation over the model domain. Five threshold concentrations (2 mg/l, 5 mg/l, 10 mg/l, 20 mg/l and 50 mg/l) have been used to investigate the scale of impact. The model shows that the plume concentration is relatively low at the surface. Close to the seabed, the plume has higher suspended sediment concentrations. The presence of the plume will persist throughout the duration of the dredging activities (26 days), but quickly dissipate in about 4‐6 hours following their completion. Dredging at the construction sites results in the formation of a sediment plume soon after dredging works start. The sediment plume travels in the direction of the prevailing current along th kandla coastline. The predicted zone of potential influence includes the vicinity of the dredging areas, a zone to the south and to the north. The results indicate that the affected distance and area are dependent on the current direction, position in the water column and the threshold of concentration. Due to the weak northerly current, the sediment disturbed by the works is expected to settle rapidly back onto the seabed in an area to the north over a distance of about 2.5 km (for a 5 mg/l threshold of plume). The maximum extent of the plume was found under the southerly current condition. At the bottom, the impact (for a 5 mg/l threshold of plume) is confined within a distance of about 5 km from the disposal location where the maximum area of the plume is approximately 14.5 km2 . The findings presented in this report are limited by the reliability of the information applied within the study. The results of the particle‐tracking model have not been validated against field data. Parameters adopted in the modelling are based on the recommended values supported by published formulations. A further limitation concerns the hydrodynamic conditions which are restricted to two 33‐day periods in 2016 which were chosen to represent the typical range in conditions. The limited duration of these

Mantec Consultants Pvt. Ltd. Page 180

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla datasets may not fully capture the variability in environmental conditions. The approach adopted is however expected to provide an adequate representation of potential environmental impacts since construction activities are likely to be suspended during more extreme conditions.

4.10 Impact of dredging on shoreline:

Nearshore dredging for construction aggregate or beach nourishment can result in a perturbation of natural littoral processes, changes in wave transformation patterns, and a net loss of sand from the littoral system. A method is described for estimating both direct and indirect effects of dredging on shoreline change. The direct effect results from infilling of the dredged pit via cross-shore sediment transport and is addressed statistically, assuming that the beach profile is in some arbitrary equilibrium shape. The indirect effect arises from project-induced wave transformation, which alters long shore sediment transport patterns, and is described using both spectral and monochromatic, numerical wave transformation models to provide input to a one-line model for shoreline change. In filling of the pit is neglected when estimating the indirect effect, providing a worst-case estimate of the indirect effect. The methodology is applied to a site on the kandla port, Sea coast, using hindcast wave data. The influences of pit location and geometry are investigated systematically, and recommendations regarding optimum pit dimensions and locations are made. Hotspots which are mainly areas nearer to the port region were specially studied for the quantification of erosion and accretion. Dredging for port development normally lead to noteworthy changes in the configuration of the seabed, These changes can meaning fully modify the currents, waves and water quality. The statistical method incorporated with GIS has been used to estimate the rate of change and net shore movement of the coast. The study indicates that gradual recession and accretion at Shorelines extracted for the past years indicate that the coastline adjacent to port area experienced both the erosion and accretion. Shoreline change rate of coastline is estimateded. Erosion and accretion of shoreline are major impacts of port/harbor. However, minor impacts are like an increase in pollution due to waste dumping and port-related industries, increase in coastal population and related activities and degradation of surrounding

Mantec Consultants Pvt. Ltd. Page 181

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla environment due to dredging and dumping material. Most of the shoreline sites, though largely get affected due to port structures, during monsoon season, achieve natural partial equilibrium during the non-monsoon season due to reversing currents and wind pattern. And hence, it may be concluded that port/harbors have limited impact on the coastal shoreline.

4.11 Impact of Rock Dredging Out of three facilities, impact of excavation and dredging could be during development of container terminal at Tuna off Tekra and construction of Port Jetty and Shifting of SNA.  Excavation activities associated with the proposed project could result in the generation of debris and presence of equipment or materials that could be subject to run off into the marine environment.  Generation of sediment due to rock excavation could results in adverse effects to offshore habitat from increased turbidity of coastal water  These impacts can be classified as not severe as there are no important species detected near the project site Construction of Port Jetty and Shifting of SNA may cause some impacts. The impacts of dredging during construction phase will be limited to the construction tenure and will be local.  Dredging may cause turbidity in water  Turbidity may cause obstacle in the movement of the marine fauna  After construction of Jetty a permanent obstacle in movement may occur to the marine faunal species. The marine fauna may migrate to some other parts  The construction materials to be used will involve raw materials which are non‐hazardous in nature such as steel, cement, gravel, rock, earth etc.  Other requirements of the construction will be a usage of i) Construction equipments ii) Transportation vehicles iii) Skilled and unskilled labour vi) Creating temporary establishment v) Utilities etc.

Mantec Consultants Pvt. Ltd. Page 182

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 5. Analysis of Alternatives 5.1 General Deendayal Port Trust proposes to further expand various facilities within existing limits of Kandla Port in Kutch district of Gujarat. The present site for the projects is selected based on the following considerations:

a. Availability of suitable and adequate land. b. Distance from reliable sources of water c. Road and Railway Access d. Availability of infrastructural facilities e. Environmental Aspects

There are no sensitive area such as National Monuments, National Parks and Wildlife Sanctuaries, etc. within 10 Km of the project site.

5.2 Selection of Sites (i) Connectivity: Airway The national airlines operate daily flights through the district headquarters at Bhuj as well as Gandhidham which lies 67 Km & 20 Km respectively from Kandla Port. Gandhidham airport is also operational and there is a daily flight to Mumbai from this Airport.

Railway Broad Gauge (BG) tracks directly connect the Port at New Kandla with the principal cities of Bombay, Ahmadabad, Surat, Baroda, etc., and also Delhi, Punjab and Haryana through the route Ahmadabad‐Ratlam‐Kota‐Mathura to Delhi. The second route is via Palanpur‐Ajmer to Delhi.

Apart from this, the existing meter gauge line from Bhildi to Samdari has been converted to BG, which provides direct link to Jodhpur in Rajasthan & Bhatinda in Punjab and reduces the reach to Hinterland by 118 Km.

Road

Mantec Consultants Pvt. Ltd. Page 183

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Kandla is connected to the National Highway grid system through NH 8A coming from Mumbai via Ahmedabad and Morbi and terminates at the Port. All main gates of cargo jetty complex as well as oil jetty complex are directly connected to N.H. 8 A by four lane wide roads.

The city of Gandhidham where the Port Administrative Office and the main staff colony are located, also lies on NH 8A about 13 Km. from the Port. The port enjoys fully developed road network, both in and around the Port area to facilitate faster movement of cargo.

• Asphalted Road Network ‐ 30 Km • Concrete Road Network ‐ 30 Km

Presently 11.43 km long Kandla‐Kharirohar road connecting Oil Jetty complex with NH 8A is two lane wide. This road is being widened from two lane to four lane at a total cost of Rs. 2179 lakhs. This also includes construction of Railway Over Bridge.

Port has constructed a two lane wide road connecting Existing NH 8A with Tuna Port, which is 5 kms from Tekra. The widening of this road will commence in the near future.

(ii) Land form, land use and land ownership

Land is largely flat with scanty vegetation. Land currently is lying as barren land and is under ownership of Kandla Port.

(iii) Topography Topography at the site location is generally flat with average elevation of about 6.5m. Topsoil appears marshy.

(iv) Water Supply The Gujarat Water Supply and Sewerage Board is responsible for developing and managing various sources of water in the region. The important source of water is

Mantec Consultants Pvt. Ltd. Page 184

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla the 14.5 Million m3 capacity reservoir of Tapar Dam, besides a number of deep tube wells. Water is distributed to Kandla area from high service reservoir near Bhachau through 18” dia. CI mains, after chlorination. The capacities of the elevated water towers and underground reservoirs at Kandla are 1500 kl. and 14000 kl., respectively. The average daily consumption of water at Kandla area is estimated at around 2000 kl. The position is improved to a great extent by tapping the source of water from Sardar Sarovour Narmada Nigam Limited.

Presently water is distributed to Tuna area through tankers as fulfillment demand of 5 KL per day. Total requirement of water in 562 area is 200 MLD water supply is ensured by Gujarat water supply Board. However, if situation arises provision is made for a stand alone water desalination plant at the zone. This is to be installed by private parties and operated on commercial basis for SEZ area.

(v) Electricity / Power Supply The port receives Bulk power supply from PGVCL through seven 11 KV sub stations. Besides, the port has two diesel generating sets to meet with emergency needs. A scheme is presently under implementation to augment the power supply to 66 KV and to provide necessary infrastructure for receiving Bulk supply, stepping down and distribution. Uninterrupted good quality estimated power requirement of 900MW is expected to be supplied in the SEZ area by the Gujarat Government. However, master plan caters for setting up a dedicated power back up from an independent power producer (IPP) at a later stage, if required. The BOT operator shall be required to install a transformer yard for transmission and power distribution for the said project.

5.3 Alternate Sites Proposed projects will be in existing Kandla Port area, owned by Deendayal Port Trust and the area is already in use for port operations and suitable for all the proposed projects, therefore no alternate sites have been selected.

Mantec Consultants Pvt. Ltd. Page 185

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 6. Environment Monitoring Programme

6.1 Introduction Environmental Management is nothing but resource management and environmental planning is just the same as development planning. They are just the other side of the same coin. The resource management and development planning look at the issue from narrow micro‐economical point of view while environmental management views the issue from the broader prospective of long term sustained development option, which ensures that the environment is not desecrated.

For the effective and consistent functioning of the project, proper environmental monitoring programme shall be carried at Deendayal Port Trust.

The programme shall include the following:

 Environmental Monitoring  Personnel Training  Regular Environmental audits and Correction measures  Documentation–standards operation procedures Environmental Management Plan and other records

6.2 Environmental Monitoring DPT will outsource the work of monitoring to assess the environmental health in the post period. A post study monitoring programme is important as it provides useful information on the following aspects.

 It helps to verify the predictions on environmental impacts presented in this study.

 It helps to indicate warnings of the development of any alarming environmental situations, and thus, provides opportunities for adopting appropriate control measures in advance.

Mantec Consultants Pvt. Ltd. Page 186

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla The monitoring programme, based on the findings of the impact assessment studies in different areas of environment, has been outlined in the next few sections. Post study monitoring programme including areas, number and location of monitoring stations, frequency of sampling and parameters with annual monitoring cost to be covered have been summed up in Table 60

Mantec Consultants Pvt. Ltd. Page 187

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Table 68: Post Study Environmental Monitoring Programme

Area of Number and Sampling Frequency Parameters to be Analyzed Annual Monitoring locations of Sampling Monitoring Cost (Rs.)

Continuously Wind Speed, Wind direction, Temperature, 1,00,000/‐ Meteorology One station at Port premises Relative Humidity, Rainfall

Ambient Air Six locations covering upwind As per 7,00,000/‐ PM , PM SO , NOx, CO Quality & downwind directions of Port NAAQS, 2009 10 2.5 , 2

Four different locations of 6,00,000/‐ Physical and Chemical parameters, Bacteriological Water Quality Kandla creek, Nakti creek & Quarterly parameters, Heavy metals and toxic constituents Khori creek

Eight locations, covering port Sound Pressure Levels (Leq) during day and night 5,00,000/‐ Noise Quarterly premises and nearby villages times.

Soil/Sediment Six locations in and around Once in a Physical and Chemical parameters, organic contents 1,70,000/‐ Quality port premises. year and heavy metals

Densities and diversities of fish, planktons, macro‐ 3,00,000/‐ Marine Six different locations nearby Once in a invertebrates, sediment characteristics, marine Ecology the port area. year benthic fauna and health of mangroves.

Total Cost (Rs.) 23,70,000/-

Mantec Consultants Pvt. Ltd. Page 188

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 6.2.1 Meteorology

Meteorology forms one of the important categories of environment in the area as it directly controls the levels of ambient air quality in the surrounding. As such, a meteorological station is proposed to be set up at proposed Kandla Port office for recording of relevant meteorological parameters. The observatory shall have equipment for recording the temperature, relative humidity, rainfall, atmospheric pressure as well wind speed and wind direction.

6.2.2 Ambient Air Quality

Monitoring of ambient air quality at the Kandla Port at 4 locations shall be carried out quarterly to ascertain the levels of pollutants in the atmosphere; air quality could represent one of the worst affected environmental disciplines due to the Port

operations. Ambient air quality shall be monitored once in three months for PM10, PM2.5 ,

SO2 ,NOx and CO 24 hourly samples of ambient air quality at 4 different locations in and around Kandla Port area.

6.2.3 Water Quality

Water quality constitutes another important area in the post study monitoring programme. The major streams or perennial sources of surface water in the study area are Nakti creek, Khori creek and Kandla creek. Contamination in creek water near the vicinity of Kandla Port area during the operation is possible only in two forms.

 Contamination of rain water passing through the proposed facilities.  Contamination due to discharge from various facilities.

Water samples near the Kandla Port area shall be sampled twice in a year and analyzed for physical, chemical and bacteriological parameters, including heavy metals and trace elements.

6.2.4 Noise Level Ambient noise levels shall be monitored at 8 locations covering industrial, commercial, residential and sensitive areas in all seasons for day time and night time Leq.

Mantec Consultants Pvt. Ltd. Page 189

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

6.2.5 Soil/Sediment Quality

Soil samples in and around Kandla Port area and sediment samples from creeks shall be collected once in a year. The samples shall be analyzed for physical and chemical parameters as well as organic and nutrient content and heavy metals. This would help to detect any contamination or build up of harmful or toxic elements due to leachate from the pollutants.

6.2.6 Marine Ecology The marine ecological study shall be carried out yearly at 6 different locations nearby the port area.

Marine Benthic Fauna

The benthic population and community structure around the outfall shall be paid to monitor anvasion of any non‐indigenous marine species in the area. The collected data shall be statistically analyzed so that the diversity indices can be recorded. This will enable to develop meaningful management plans in altering the discharge method.

Health of Mangroves

Periodical assessment of the health of mangroves is being carried out with the help of guide and will be continued on quarterly basis on three locations.

Assessing the Status of Fisheries

Continuous monitoring of the intake system for impingement and entrapment of marine organisms has to be carried out. The trash bars and screens meant to prevent impingement have to be regularly examined for the type of Faunal impinged and the quantity of commercially valuable fish impinged on the screens. Similarly the intake water has to be examined at the pumping location for entrapped organisms, especially fish eggs and larvae of commercially important species, so that a realistic assessment of possible fisheries loss could be made. The exercise is also necessary to understand the efficacy of the screen and other devices used to minimize the entrapment.

Mantec Consultants Pvt. Ltd. Page 190

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 7. Additional Studies

7.1 Oil Spill An oil spill is the release of a liquid petroleum hydrocarbon into the environment, especially marine areas, due to human activity, and is a form of pollution. The term is usually applied to marine oil spills, where oil is released into the ocean or coastal waters, but spills may also occur on land. Oil spills may be due to releases of crude oil from tankers, offshore platforms, drilling rigs and wells, as well as spills of refined petroleum products (such as gasoline, diesel) and their by‐products, heavier fuels used by large ships such as bunker fuel, or the spill of any oily refuse or waste oil.

7.1.1 Objective of Oil Spill Study The objectives of oil spill contingency plan is to respond to oil spill efficiently by a well planned system in which all concerned departments and agencies acts in a coordinated manner to minimize the damage to marine environment, property and to human life at large..

7.1.2 Causes of Oil Spill The various operations related to SPM and associated facilities that would cause spillage of oil are listed below.

• Hose failure at SPM during to unloading of crude oil. • Leakage from the sub‐sea pipeline running from SPM to LFP. • Collision/grounding of the tanker in the vicinity of SPM. • Leakage on the land from the pipeline connecting to COT. • Drifting and breaking away of the tankers from the SPM and anchorages. • Damage to the tanker due to high tidal waves, earthquakes, tsunami etc.

Pipelines are designed, fabricated, laid and periodically inspected as per standard codes. Hence, spillages due to corrosion, gauges etc are rare during design life of the pipeline. Moreover, the operational procedures are set on ‘No Leak’ philosophy under

Mantec Consultants Pvt. Ltd. Page 191

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

normal operating conditions and occurrence of an oil spill is expected to be rare. However, in a case of eventualities such as earth quake, fire, collision, grounding, large oil spills can occur as on ‘unavoidable phenomenon’. Generally small spills go unnoticed, though large oil spills are recorded and reported. On the basis of data available for incidences of oil spills worldwide during 1974 to 2007 following interferences can be made.

The causes can be divided into operational, accidental and other/unknown. Most spills normally occur at ports/oil terminals. The majority of oil spills amounting to 91% are lesser than 7 t. Of the oil spills caused during the events, 84% spills are in excess of 700 t. The spills are categorized as < 7 t, 7 to 700 t and > 700 t. It shows that smaller spills (< 7 t)68 mostly occur during loading/discharging (37%) followed by other/unknown (28%) and other operations (15%) while spills of 7 to 700 mostly cause during loading/discharging (27%), collision (25%) and grounding (19%). The major cause of large spills (> 700 t) remains grounding (34%) followed by collision (28%). Fire and explosion as well as hull failures are responsible for 8.7 and 12.4% spills.

7.1.3 Spill Quantities Though probability of failure of state of art loading during the operations is low, if it happens, at a pumping rate of 9550 m3/h and the response time of 1 min (max), the expected spill is 158 t and is a very rare incidence.

Failure during operations though low if it occurs, leakage from sub‐sea pipeline as well as that from LFP to COT can be controlled within 30 sec. Hence at the pumping rate of 9500 m3/h, the spill quantity is estimated at 79 t as a rare event.

In case of an eventuality, damage/rupture to the oil compartment can occur though entire cargo compartments are protected by another hull and cargo spillage due to collision/grounding is remote. The amount of spill likely to occur during accidental causes is roughly estimated at 1000 t. This occurrence is considered as extremely rare probability.

Mantec Consultants Pvt. Ltd. Page 192

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 7.1.4 Oil Spill Contingency Plan

7.1.4.1 Strategy Plan  Perceived risk and expected quantities of oil spill.  Clean up strategy and identification of oil equipment.  Resources at risk  Responsibility and action plan.

7.1.4.2 Response Plan  Initial actions and procedure  Operations planning and mobilization procedures  Control of operations  Termination of operations

The detailed Oil Spill Contingency Plan of Deendayal Port Trust is enclosed as Annexure-XII.

7.1.5 Composition of Oil

Crude is a naturally occurring complex mixture of organic compounds. It was formed from the partial decomposition of animal and plant matters over a geological time. It is recovered by drilling wells in the reservoirs in the earth. The physical properties and chemical composition of crude from different producing regions and even from different depths in the same well can vary markedly. Crude contains thousands of different chemical compounds. Hence, its chemical complexity probably resulted from a process of molecular scrambling during the formation of these chemical compounds; the hydrocarbons (aliphatic and aromatic) are most abundant. Other types are traces of various compounds of nitrogen, sulphur and oxygen as well as traces of organo‐metallic compounds of mainly nickel and vanadium.

Obviously physical characteristics of the crude’s to be handled at the SPM also vary largely. For instance specific gravity (at 15.56oC) of the crude’s is .highly varied from 0.8282 to 0.922 indicating that they are lighter than water and categorized as light/medium. Their viscosity (CST at 37.8oC) varies in a wide range i.e. 9.2, 20.1, 410.5,

Mantec Consultants Pvt. Ltd. Page 193

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

3.28 and 77.9 for Arab Medium, Arab Heavy, Doba, Bombay High and Maya crude’s respectively indicating that Doba and Maya are highly viscous crude’s. The pour points (oC) of Arab Medium, Arab Heavy, Doba, Bombay High and Maya are ‐17.8, ‐17.8, ‐2.77, + 30 and ‐23 respectively. These values reveal that Bombay High is the non‐flowing thick liquid at 300C while other crude’s are flowing liquids at normal tropical temperatures.

Hydrogen Sulphide (H2S) which gives bad odour to a crude are generally at non‐ detectable levels except for Doba crude which contain the gas in < 1 ppm concentration. On the basis of sulphur content the crudes are categorized as Arab medium and Arab Heavy: normal crude (S 2 to 3%), Doba and Bombay High: sweet crude (S <0.5%) and Maya: sour crude (S> 3%), Presence sulphur derivatives such as mercaptans and thiols in a crude produce strongly unpleasant garlic smell.

General composition of crudes is as follows:

a) Aliphatic hydrocarbons Crude oil contains a mixture of alkanes which are straight chain saturated compounds, related to methane and ethane, and iso‐alkanes, which are branched chain compounds like isobutene and isooctane. The compounds with 5 to 7 C atoms are liquids and those having higher number are solids. The paraffins waxes (C22 ‐ C30) and petroleum jelly (C30 ‐ C70) are the higher homologous of paraffins.

b) Alicyclic hydrocarbons The alicyclic hydrocarbons are saturated (cycloalkanes) or unsaturated (cycloalkenes) containing 5 to 6 C atoms arranged in a ring. They are also known as naphthenes and comprise 30 to 60% of petroleum with the dominance of saturated forms. Some naphthenic hydrocarbons found in petroleum are cyclobutenes, limonenes, cyclopentenes, cyclohexenes etc.

c) Aromatic hydrocarbons Aromatic hydrocarbons which are one, two or polycyclic type,comprise around 25% of the total crude oil. Some members of aromatic hydrocarbons are benzene, toluene,

Mantec Consultants Pvt. Ltd. Page 194

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

naphthalene, biphenyl, 1, 8‐dimethyl phenanthrene, 3‐methyl chrysene, 1‐methyl pyrene, perylene,3,4‐banzo[a]pyrene, banz[a]anthracene, acenaphthene, acenaphthylene, anthracene, fluorine, 2‐methylnaphthalene etc.

d) Non-hydrocarbons The major non‐hydrocarbons in a crude oil are organic compounds containing N, S and O (NSO) and metals like Ni, V, Cu, Zn and Fe. Contributions of non‐hydrocarbons to crude oil vary from 2 to 50% and origin of a crude oil largely influences the composition of these constituents. The O compounds are generally in the form of phenols, carboxylic acids, ketones, esters etc. The N compounds include substituted pyrine and quinoline compounds, pyrroles, indoles, carbozones and benzcarbazones. Most of the sulphur in crude oil is present as methyl‐ethyl sulphite, cycloalkyl thiol, n‐pentyl mercapton etc. Most abundant metals namely Ni and V are found in the form of petroporphyrin complexes and occur in the range of 0.03μg/l to over 300 μg/l in crude petroleum.

7.1.6 Toxicity Toxicity of crude mostly falls in two general categories. The first category includes effects associated with coating or smothering of an organism with oil. Such effects are associated primarily with the higher molecular weight, water‐insoluble hydrocarbons. In the event of a spill of crude oil, the various tarry substances that coat the feathers of birds and cover inter tidal organisms such as clams, oysters, and barnacles belong to this variety. Although some organisms such as tubeworms and barnacles are surprisingly little affected by such coatings, the effect on organisms such as aquatic birds can be devastating. The second category of toxicity involves disruption of an organisms metabolism due to the ingestion of oil and the incorporation of hydrocarbons into lipid or other tissues in sufficient concentrations to upset the normal functioning of the organisms. This effect is due to the cumulative effect of the individual constituents present in crude. It is generally agreed that aromatic hydrocarbons are the most toxic, followed by cycloalkanes, then olefins, and lastly alkanes. There is also a definite tendency for toxicity to be positively correlated with the molecular size of the hydrocarbons in which median tolerance limits of some aromatic hydrocarbons for selected marine macro invertebrates and fish are given.

Mantec Consultants Pvt. Ltd. Page 195

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Most toxic effects caused by ingestion of oil in water, however are believed to be due to low molecular weight (C12 – C24) alkanes and low molecular weight aromatics.

7.1.7 Weathering Process Once the oil enters the sea, several processes start acting simultaneously resulting in alteration in its physical and chemical properties. These processes include spreading, drifting, evaporation, dispersion, dissolution, emulsification, photo‐oxidation, microbial degradation and sedimentation. Though each process has a typical effect, the resultant impact is generally a cumulative one. Evaporation and dissolution are the two major processes, which are mainly responsible for removing major fraction of spilled oil from marine environment. They both together can remove more than 90% of hydrocarbons lighter than n‐C10 within few hours of an oil spill.

a) Spreading: Spreading of crude oil on the water surface begins as soon as oil spills into the sea and largely depends upon volume of oil and its physical characteristics namely density, viscosity and pour point. The environmental factors such as wind velocity, current and temperature also influence spreading. The four main physical forces influencing the spreading on a calm seawater surface are gravitation force, surface tension, inertia and frictional or viscous drag force. Aromatic and aliphatic hydrocarbons with < 9 C atoms have greater tendency to spread while compounds with higher molecular weights do not tend to spread on water.

Spreading accelerates evaporation leading to increase in viscosity and pour point of the residue. Presence of NSO compounds in petroleum also facilitates dissolution and once soluble compounds are lost, spreading decreases considerably.

b) Drift: Drift is a large‐scale phenomenon that determines the movement of an oil spill and is primarily controlled by wind, waves and surface currents. Thus for instance, when the wind velocity is the determinant force in drift movement, a slick can move at a rate of 3%

Mantec Consultants Pvt. Ltd. Page 196

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

of the wind velocity in the same direction as that of the wind. However, prediction of drift of a spill on the basis of wind pattern alone is difficult because of the current and wave perturbations. This is compounded by the fact that the most surface wave spectra are composed of a number of different wave systems with varying periods and directions.

c) Evaporation: Evaporation is the major process that removes the low boiling components of petroleum from the sea surface. The composition of oil and its physical properties, wind velocity, air and sea temperatures, turbulence and intensity of solar radiation and surface area of the spill, all affect evaporation rates of hydrocarbons.

Evaporation rate for a specific hydrocarbon is a function of its vapor pressure, which in turn is inversely related to the molecular weight. The compounds with vapor pressure greater than that of n C18 do not persist in a spill for longer period while those with lesser vapor pressure do not evaporate appreciably. Under normal conditions losses of aromatic hydrocarbons by evaporation are 100 times greater than losses by dissolution and that the evaporation rate for aliphatics may be 10,000 times greater than their rate of dissolution. Loss of volatile hydrocarbons, mostly by evaporation, increases the density and kinematics viscosity of the residual oil resulting in break‐up of the slick into smaller patches. Agitation of these patches enhances incorporation of water due to increased surface area resulting in water‐in‐oil emulsion called as chocolate mousse.

7.2 Marpol MARPOL is the International Convention for the Prevention of Pollution From Ships, 1973 as modified by the Protocol of 1978. ("Marpol" is short for marine pollution and 73/78 short for the years 1973 and 1978.)

Marpol is one of the most important international marine environmental conventions. It was designed to minimize pollution of the seas, including dumping, oil and exhaust pollution. Its stated object is: to preserve the marine environment through the complete elimination of pollution by oil and other harmful substances and the minimization of accidental discharge of such substances.

Mantec Consultants Pvt. Ltd. Page 197

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

7.3 Risk Assessment and Disaster Management Plan

Risk analysis follows an extensive hazard analysis. It involves the identification and assessment of risks that neighboring populations are exposed to as a result of hazards present. This requires a thorough knowledge of failure probability, credible accident scenario, vulnerability of population etc. Much of this information is difficult to get or generate. Consequently, the risk analysis is often confined to maximum credible accident studies. The Disaster Management Plan (DMP) is based upon identification of various hazards, probable risks in operation and construction of Kandla Port activities have been assessed to maximum credible accident analysis, consequence analysis which gives a broad identification of risks involved in the plant. The Risk Assessment and Disaster Management Plan have already been prepared and enclosed as Annexure-VII. The letter for OISD norms applicable is attached as Annexure-XIII.

7.4 Public Consultation The public hearing for the proposed project was held on 18.12.2013 at 11:30 hrs, opposite to Aarya Logistic, Near Nakti Bridge, Tuna Kandla road, Deendayal Port Trust, Tehsil Gandhidham, District Kutch. An advertisement in English was published in the daily news paper “The Times of India dated 17.11.2013 and in Gujarati daily news paper “Kutch Mitra” dated 17.11.2013. Details of the public hearing proceedings along with action plan are attached as Annexure-XIV.

7.5 Bathymetry Study 1. The Kandla port, a major port of western part of Indian Coastal region is located at the head of Gulf of Kutch. The Bathometry of Gulf in the approaches to Kandla Creek has number of shoals & natural channels. The strong tidal currents during flood & ebbs phase of the tide is associated with long sediment flow and play a vital role in determining configuration of shoals & channels. 2. The approach to Kandla Creek from Gulf of Kutch is very dynamic & has undergone several changes over the years. The present navigational channel has a length of about 17 km from outer Tuna Buoy to Buoy No.13 at outfall of Kandla Creek. It has a width of

Mantec Consultants Pvt. Ltd. Page 198

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

350 meter all along except in the curved portion where width of the channel is about 400m for easy passage of vessels. The channel is being maintained by continuous dredging throughout the year. Recently efforts were being made to sustain the desired depth of 8.5m along the western bank between buoy No.10 & Buoy No.8 but did not succeed. Deendayal Port Trust then proposed to shift the channel in this reach by 50 m towards eastern side (Annexure-V). 7.6 Representations from Conservation Action Trust (NGO) It has observed that various representations/comments were raised by the Conservation Action Trust over remaining 3 integarted facilities of DPT Stage-1 and same were recived by the MoEF on 30/04/2017 during the 16th meeting of EAC (Infra-2) for grant of ToR. And these comments are tabulated below and specific action plan for these comments is also given below.

S.No Comments raised by the Conservation Reply by the Project Proponent Specific Action Trust Action Plan 1 There are no documents showing the Details of these three facilities regarding Not locations of the proposed 3 facilities. The the location are given in Figure‐1 & 2 of required KML file [in Form l] only shows a placemark Chapter‐1 & Figure‐6, 7 & 8 of Chapter‐2 stating 'Project Site' [Google Earth image Details of the Latitude and Longitude is showing the same has been attached for given in section‐2.5 of Chapter‐2 of the reference]. Whereas there are three facilities EIA Report. proposed to be developed. There is no Survey of lndia toposheet showing the location of proposed project' lnstead, a map is uploaded with a project site mark which again does not show any details [The map has been attached for reference]. The layout plan [at page no. 12] of proposed project in the pre‐feasibility report is of low resolution, which again does not provide many details to understand the location. From all the documents uploaded on the MoEFCC website, only the Pre‐feasibility report has coordinate which is of the placemark in KML file [at page no' 4]' Non‐ availability of this basic information makes it extremely difficult to understand the

Mantec Consultants Pvt. Ltd. Page 199

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

location of the proposed project. The project proponent should furnish location of the proposed project on toposheet, latitude‐ longitude of the proposed project locations and the KML fire showing the same. 2 The project proponent has mentioned in Details of wetlands, watercourses or other Not required Form 1 that there are 'no wetlands, water bodies, coastal zone, biospheres, watercourses or other water bodies, coastal mountains, forest, flora & fauna are given zone, biospheres, mountains, forests in the in the Chapter‐3 of the EIA Report and 15km radius of the proposed project Impact on these have also been described site, Further, in the Form 1 it is stated in the Chapter‐4 of the EIA Report and 'There are no important or sensitive Mangrove management plan has been species of flora or fauna going to be attached as Annexure-XI. affected,. The fact that there are mangroves and mudflats present along the Kandla creek and Khori creek has not been considered. The mangroves and mudflats are both classified as CRZ I A and are protected by the CRZ Notification, 2011. 3 Form 1 mentions about dredging for a Details of dredged material are given in Not required container terminal at Tuna‐Tekra l3,56,000 Section 10.6 of Chapter-10. m3 and for maintenance‐2,71'200 m3' There are no details provided on where the dredged material will be disposed. 4 The proposed project includes a setting for a No Action needed Not required container terminal at Tuna‐Tekra. There is also a proposed set up of a multipurpose cargo terminal at Tekra off Tuna on BoT basis. EC and CRZ Clearance for which was granted on 3rd December 2016. The EC granted on 3rd December 2016 including setting up of 7 integrated facilities proposed within the existing Deendayal Port Trust limits. They are‐ [1] Development of Oil jetty to handle liquid cargo and ship bunkering terminal at old kandla. [2]Multipurpose Cargo Terminal at Tekra off Tuna on BOT basis. [3] Up‐gradation of Brage Handling Capacity at Bunder basin at Kandla. [4] Construction of Rail Over Bridge at NH8A near Nakti Bridge. [5] Mechanization of Dry cargo handling facility at Kandla Port (Berth 7 & 8)

Mantec Consultants Pvt. Ltd. Page 200

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

[6] Strengthening of Cargo Berths No.6 at Kandla Port. [7] Modification and Stregthening of Cargo Berths no‐6 at Kandla Port.

5 Some of the proposed projects in the Kandla Excerpts of the meeting are not relevant, Not required area are‐ as the proposed facilities are not parts of In the 34th GCZMA Meeting held on 16th March the SEZ. 2017 at Gandhinagar. One of the item on the agenda was CRZ Clearance for setting up of Port based multi‐product Special Economic Zone in 5000 Ha at Tuna (1400 Ha) and Kandla (3600 Ha) within Deendayal Port Trust limit, District; Kutch M/s Deendayal Port Trust. Excerpts from the minutes of the GCZMZA Meeting‐  The Member Secretary, GEC and Chairman of the Sub‐Committee of GCZMA, apprised the Authority that the Sub‐Committee of GCZMA visited the proposed site at Kandla and Tuna on 10‐02‐2017 along with concerned officials from Deendayal Port Trust.

 It was further apprised that during visit of Tuna area, the Committee observed that entire area at Tuna of the proposed SEZ falls within CRZ. The proposed site is categorized as CRZ1‐ (a) & (b) area in the base map prepared by institute of Remote Sensing, Anna University, Chennai, however Committee during site visit, the Committee observed that the proposed falls in the CRZ‐1(a) category only, as the intertidal mudflats are biologically active.A substantial part of it is a part of the mangrove swamps. Also, Good to Sparse Mangrove patches are interspaced in the proposed SEZ area.

Mantec Consultants Pvt. Ltd. Page 201

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

 As per the observation, extent of mangroves at Tuna areas of proposed SEZ site, are found to be higher than it’s mentioned in EIA Report. Even though in the proposal its mentioned that buffer zone of 50 meter width will be kept around mangrove areas but while field visit, it was observed that after leaving buffer zone width of 50 meter and also due to absence of large chunk of open areas the effective area available for SEZ will be far less than the proposed.

 The Committee observed that the proposed area at Kandla can be broadly divided in two parts i.e.(A) Salt Pan areas and (B) Non‐ Salt pan areas.The non‐salt pan area is having dense and sparse mangroves along with mangrove swamps. It was observed that the extent of the mangroves is higher than shown in the map prepared by Indian Institute of Remote Sensing, Anna University. It was also observed by the committee that the proposed intertidal area for SEZ is falling under the category of CRZ1‐(a). There are no sufficient open patches in the entire area to be take up any developmental activities as it may disturb to existing mangrove patches and its swamp areas.

 The Authority deliberated the proposal of Deendayal Port Trust for Development of Port Based Multi Product SEZ at Tuna and Kandla, report of the sub‐committee along with recommendation , and after detailed discussion, the authority decided to recommend to the Ministry

Mantec Consultants Pvt. Ltd. Page 202

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

of Environment Forest and Climate Change, Government of India to exclude 2681 Ha area (1400 hectares at Tuna and 3600 hectares at Kandla) at the time of grant of Environmental Clearance for proposed development of port based Multi Product SEZ at Tuna and Knadla, District Kutch. 6 An amendment in the EC for the construction of 13th to 16th Cargo berth at Kandla (Agenda Item 13.2.15) was discussed in the 13th Infra‐ 2 EAC Meeting held on 23rd ‐25th Janaury 2017. Also, ToR for proposed creation of waterfront activities (Oil Jetties 8, 9, 10 & 11) No Action required Not required and development of land (1432 acres) for associated facilities for storage at Old Kandla was discussed {Agenda Item 14.2.1} in the 14th Infra‐2 EAC Meeting held on 13th ‐15th February 2017. 7 The piece mealing of projects in Kandla area has led to Fragmentation of the ecologically sensitive and geo‐morphologically important features of the area. The pace at which the proposed projects are discussed in the EAC in context to the DPT will cause a severe ecological imbalance. This imbalance will have a negative impact not only on the No Action is required at the end of project Not required biodiversity of the Kandla and Khori creek but promponent/Consultant also on the biodiversity of Gulf of Kutch, which is the one of the most bio diverse area. Further, this lead to the destruction of the mangroves, mudflats in the Kandla region. A Carrying capacity study should be conducted all the projects in the area (existing and proposed)

Mantec Consultants Pvt. Ltd. Page 203

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

8 Please find attached the copy of our site visit Our proposals for EC are being routed Not required report dated 4th September 2013 showing the through GCZMA before consideration for destruction of mangroves by Deendayal Port grant of Environmental Clearance. Trust. The report clearly shows that hundreds of acres of mangrove have already been destroyed by the Deendayal Port Trust. 9 A show cause notice was issued to Deendayal The status of show casue notice issued to Not required Port Trust dated 6th June 2014 for the Deendayal Port Trust dated 06/06/2014 violation of the CRZ Notification, 2011. The is attached as Annexure-XIX Status of the show cause notice should also be checked upon prior to considering the projects in the Deendayal Port Trust.

Mantec Consultants Pvt. Ltd. Page 204

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 8. Project Benefits

8.1 Improvement in the Physical Infrastructure

In order to ease pressure on the existing cargo berths, Deendayal Port Trust has taken a slew of measures that include development of new jetties. In light of the same it is proposed to develop the facility at Kandla Port., which is vital for economic growth as well as improving the quality of life. The improved cargo supply will have strong logistical support for delivering the products to customers at better quality and better price Availability of product in vicinity of demand location will reduce price. Delivery distance by tankers which in turn will reduce trucks on the road reducing the vehicular load on the already strained public roads, thereby reducing the noise pollution as well as air pollution at local levels and also reduced probability of accidents on the roads due to less movement of tanks and trucks. Establishment of large developmental projects improve the availability of the physical infrastructures like approach roads, drainage, communication and transportation facilities etc.

8.2 Improvement in the Social Infrastructure Deendayal Port Trust shall take up some community welfare activities under Corporate Social Responsibility and also improve the social infrastructures like education and health care system etc.

8.3 Employment & Other Benefits The proposed facilities have numerous benefits for the State of Gujarat which are listed below:  This proposal would mean development of this area on lines with progressive policy of Govt. of Gujarat.

 The proponent has planned to recruit numbers of skilled, semi‐skilled and unskilled manpower during the construction phase and indirect employment through contracts for civil construction, Mechanical erection, electrification,

Mantec Consultants Pvt. Ltd. Page 205

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

piping works and associated amenities. The indirect employment potential of the projects would be significantly beneficial for the area.

 The proposed project is expected to employ about 200 people per day of various skills which would mean income to about 200 people.

 This proposal would generate funds for the Govt. of Gujarat in terms of lease rent or the like, and lead to productive use of vast space which is presently lying idle.

 The proposal while generating income for people and Govt. of Gujarat does not create any nuisance or disturbance to existing port activity or local people conducting work / business in adjoining areas.

 Additional activities which would be supportive in nature to the port project shall also be developed in the near by areas which will generate indirect employment opportunities.

 General infrastructure of the area would be enhanced resulting in the social upliftment of the local inhabitants.

8.4 Financial Benefits of the Projects  Faster evacuation of Cargo, thereby Increase in cargo evacuation capacity.

 Earning through special port charges on rail bound / rail borne cargo passing through the Railway line.

 Enhances the possibility of receiving higher revenue share quotes for various BOT projects to be developed nearby Tuna port.

 Increase in revenue operations of port due to additional traffic handling.

 Reducing congestion at Kandla port.

Social Benefits of the Project

Mantec Consultants Pvt. Ltd. Page 206

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

A. With modernisation and expansion of Kandla port, more economic opportunities would be created (both in formal and informal sector) for Local community. B. Increase in business activity will bring in prosperity in hinterland, which consequently would bring better access to social and physical infrastructure. 8.5 Corporate Social Responsibility (CSR) Of DPT As per the CSR guideline 2.5% of the project cost around Rs,80.35 Crore will be spent in different periods of the years for improvement of social infrastrcutre in the surrounding locality of the project site.

The main objective behind the CSR plan of Deendayal Port Trust is as follows: . To stimulate infrastructure growth of the State, especially, developing the area into an economically bustling zone.

. To develop the port area and surrounding areas with top‐class residential, water & power supply facilities.

. To enrich people's life in the area/periphery in every possible way. The DPT has spent 25.62 crores during the years of 2011‐12 2017‐18 for the various CSR activities which are as follows:

Table 69: Expenditure on CSR Scheme: 2011-12 to 2017--2018

S..No. Financial year Outlay in Lakhs, INR

1 2011‐12 300 2 2012‐13 400 3 2013‐14 643 4 2014‐15 107 5 2015‐16 150 6 2016‐17 260 7 2017‐18 702 Total 2562

Table 70: Works Undertaken by DPT under the CSR Scheme: 2016-17

Estimated Cost, S.No. Name of Scheme INR in Lakhs RCC Community Hall at Harshidhi Mata Temple, Veea village, 1 19.00 AnjarTaluka 2 Fabricated Community Hall at Sanghad village, AnjarTaluka 21.00 CSR Works for Shri MaheshwariMeghvadSamaj, Gandhidham at Grave 3 8.00 Yard , Behind Redison Hotel. CSR works for ShirDhanrajMatiyadevMuktiDham, Sector‐14 , Rotary 4 30.50 Nagar, Gandhidham.

Mantec Consultants Pvt. Ltd. Page 207

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

CSR works for NirvasitHarijan Co‐operative Housing Society, 5 Gandhidham. 41.00 Health Cum Education Centre. 6 CSR works for Shri Rotary Nagar Primary school, Gandhidham. 2.80 CSR works at NU ‐4 , NU‐10(B) Sapnanagar& Saktinagar, Golden 7 18.00 Jublee Park, at Gandhidham. Total 140.30

Table 71: CSR works recommended by CSR Committee in its meeting held on 17.02.2018 for the year of 2017-18 as under (Till Board approval is pending) Sr. No Name of Scheme Appx Cost (In lakhs)

1 CSR works at Shri Ganesh Nagar Govt High School, Gandhidham 38.30 Lakhs CSR works for MOLANA AZAD Primary School, New Kandla. 7.00 Lakhs 2

Grant Financial contribution for facility of Army cantonment for 50 15 Lakhs 3 air coolers at Kutch Border Area. CSR works at Tuna &Vandi villages (providing drainage lines under Approximate Swachh Bharat Abhiyan) Estimated Cost Rs.99.50 Lakhs 40% of the estimated cost (i.e Rs 39.80 4 Lakhs ) to be contribute by DPT for the CSR and remaining shall be contribute by M/s AKBTPL, etc. 5 CSR works for S.H.N Academy English School ( Mangd by Indian 40 Lakhs Institute of Sindhology –BharatiSindhuVidyapeeth), Adipur

6 Construction of Internal Road at Bhaktinagar Society, Kidana 15 Lakh Total Cost 155.10 Lakhs

In addition to above, DPT is ready to take the projects against the requirement of Social Responsive organisations under CSR schemes for further future years also.

Mantec Consultants Pvt. Ltd. Page 208

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 9. Environmental Cost Benefit Analysis

Not applicable, because it was not recommended at scoping stage for EIA Study

Mantec Consultants Pvt. Ltd. Page 209

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 10. Environmental Management Plan

10.1 General Deendayal Port Trust is committed to continuously improve the environment in and around Port area in line with National and International norms. The Integrated Environmental Management Plan for the integrated facilities within Kandla Port area proposes to integrate the baseline conditions, impacts likely to occur, and the supportive and assimilative capacity of the system. The most reliable way to achieve the above objective is to incorporate the management plan into the overall planning and implementation of the project.

An Environmental Management Plan (EMP) can be defined as “an environmental management tool used to ensure that undue or reasonably avoidable adverse impacts of the construction, operation and decommissioning of a project are prevented; and that the positive benefits of the projects are enhanced”. EMPs are therefore important tools for ensuring that the management actions arising from Environmental Impact Assessment (EIA) processes are clearly defined and implemented through all phases of the project life‐cycle. This plan also helps an organization map its progress toward achieving continual improvements. Each organization is unique and, as a result, so is Environmental Management Plans. The level of detail and length of an EMP varies depending on the type of organization, the complexity of its processes and the maturity of the organization in understanding its environmental responsibilities. Some plans may end up being only a few pages long, while others could become extensive documents.

The Environmental Management Plan (EMP) for the integrated facilities within Kandla Port area includes the following:

 Air emissions management  Control of Noise  Wastewater management  Waste management  Dredged materials management  Hazardous materials and oil management  Biodiversity Management

Mantec Consultants Pvt. Ltd. Page 210

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

 Greenbelt Development  Mangrove Plantation  Energy Conservation Measures  Environment Management Cell Environmental Management Plan in a tabular form has been given at the end of the Chapter in Table-66.

10.2 Air Emissions Management 10.2.1 Construction Phase

During Construction phase, Gaseous emissions from DG sets and transportation vehicles are expected to cause deterioration in the Ambient Air Quality. Also digging operations will involve stock piling of the soil that may become source of fugitive dust emission especially during dry weather. Though the gaseous emissions are not expected to contribute significantly to the ambient air quality, some generic measures to reduce fugitive and gaseous pollutant emissions during the construction phase should be implemented.

 Water sprinklers will be used to control the fugitive dusts.  Prudent and good construction practices will be used to minimize the spread of sediments, which are stirred during pile driving and other construction. Mainly stock piles, excavated earthen materials etc. should be managed with water sprinkling to avoid dust /soil being airborne from the specific site.  Diesel driven construction machinery and equipments should be fitted with appropriate silencers, will not be left idle for prolonged periods of time, and be subjected to regular scheduled maintenance to minimize the exhaust emission.  The vent of the DG sets should be positioned at a sufficient height to ensure dispersal of exhaust emission to meet the standards set by CPCB.  Vehicle engines should not be left running when not in use.  Improperly functioning equipment and vehicles should be removed from the project site or should be repaired before returning to service.

10.2.2 Operation Phase

Mantec Consultants Pvt. Ltd. Page 211

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

The most significant sources of air pollutants from port operations include combustion emissions from ships propulsion and auxiliary engines and boilers, mainly consisting of sulfur dioxide (SO2), nitrogen oxides (NOX), greenhouse gases (e.g. carbon dioxide

(CO2) and carbon monoxide (CO), particulate matter (PM), and volatile organic compounds (VOC), followed by combustion source emissions from vehicles and land‐ based engines and boilers contributing similar pollutants.

Volatile organic compounds (VOC) may also be emitted from fuel storage and transfer. Storage and handling of dry bulk cargo, as well as from onshore construction activities and vehicle traffic on unpaved roads, may also contribute to particulate matter emissions.

Recommended air emissions management strategies include:

10.2.2.1 Combustion Sources  Developing air quality management procedures applicable to ship operators, such as:

o Maintaining emissions of NOx and SOx within the limits established by international regulations (MARPOL);

o Using low‐sulfur fuels in port as required by international regulations (MARPOL);

o Navigation of port access areas at partial power, achieving full power only after leaving the port area;

o Avoiding or limiting the practice of blowing soot from tubes or flues on steam boilers while in port or during unfavorable atmospheric conditions;

o If the port provides onshore power for vessels to reduce shipboard power use during loading / unloading activities, requiring vessels to shut down power plants (go “cold iron”) if docked above a specified time threshold.

 Depending on the need to address local air quality concerns, operators shall develop air quality management procedures for application to land‐based activities which may include:

Mantec Consultants Pvt. Ltd. Page 212

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

o Keeping transfer equipment (e.g. cranes, forklifts, and trucks) in good working condition;

o Upgrading the land vehicle fleet with less‐polluting trucks and vehicles, and using alternative fuels and fuel mixtures;

o Encouraging reduction in engine idling during on‐ and off‐loading activities;

o Encouraging storage planning to avoid or minimize re storage and reshuffling of cargo.

Where practicable, designing new facilities to minimize travel distance from ships off‐loading and on‐loading facilities to storage areas.

10.2.2.2 Volatile Organic Compounds VOC emissions from fuel storage and transfer activities should be minimized by means of equipment selection, such as the use of floating top storage tanks or vapor recovery systems for fuel storage, loading / offloading, and fueling activities (depending on the type of material to be stored), and adoption of management practices such as limiting or eliminating loading / unloading during poor air quality episodes or implementing tank and piping leak detection and repair programs.

10.2.2.3 Dust Dry bulk materials storage and handling facilities should be designed to minimize or control dust emissions, including:

 Storing pulverized coal and pet‐coke in silos;  Installing dust suppression mechanisms (e.g. water spray or covered storage areas);  Using telescoping chutes to eliminate the need for slingers;  Using vacuum collectors at dust‐generating activities;  Using slurry transport, pneumatic or continuous screw conveyors, and covering other types of conveyors;  Minimizing free fall of materials.  Minimizing dry cargo pile heights and containing piles with perimeter walls;  Removing materials from the bottom of piles to minimize dust re‐suspension;  Ensuring hatches are covered when material handling is not being conducted;

Mantec Consultants Pvt. Ltd. Page 213

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

 Covering transport vehicles;  Regularly sweeping docks and handling areas, truck/rail storage areas, and paved roadway surfaces

10.3 Control of Noise The principal goal of noise control is to ensure that noise from the project activities does not exceed acceptable parameters and that the noise levels are not injurious to health and do not create a nuisance.

10.3.1 Construction Phase The major Impact on noise level of the proposed project, during the construction phase, is envisaged due to the noise generation by the operation of the machineries, equipments and some mechanical works.

 During night time transportation activities will not be allowed to avoid high noise level in nearby villages/locality. Only in case of emergency the transportation activities shall be allowed in night time.

 All vehicles should be equipped with the horn of low noise level which is recommended by authority to avoid impacts on noise level. Further, adequate silencers must be attached with all vehicles to reduce the noise.

 Machineries/equipment causing high noise level should not be operated during the night time.

 It should be ensured that the equipment used during construction is properly maintained to keep noise emissions within the permissible limits.

 Construction machinery should be in good working condition and engines turned off when not in use.

10.3.2 Operation Phase Noise sources in port operations include cargo handling, vehicular traffic, and loading / unloading containers and ships. Atmospheric conditions that may affect noise levels include humidity, wind direction, and wind speed. Vegetation, such as trees, and walls may reduce noise levels. Noise prevention and mitigation measures should be applied

Mantec Consultants Pvt. Ltd. Page 214

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

where predicted or measured noise level from a project facility or operations exceed the applicable noise level guideline at the most sensitive point of reception.

Noise reduction options that should be considered include:

 Selecting equipment with lower sound power levels;  Installing suitable mufflers on engine exhausts and compressor components;  Installing acoustic enclosures for equipment casing radiating noise;  Improving the acoustic performance of constructed buildings, apply sound insulation;  Installing vibration isolation for mechanical equipment;  Limiting the hours of operation for specific pieces of equipment or operations, especially mobile sources operating through community areas;  Re‐locating noise sources to less sensitive areas to take advantage of distance and shielding;  Siting permanent facilities away from community areas;  Reducing project traffic routing through community areas wherever possible;  Provision of Personal Protective Equipments and their proper usage for eardrum protection of the workers as well as visitors;  Periodic monitoring of sound level at suggested places;  Periodical maintenance of all equipments and transport vehicles.

10.4 Water Environment 10.4.1 Construction Phase

The major impacts on marine water quality are envisaged due to the civil works activities like driving of piles, construction of berth, approach way, movement of construction equipments etc. During these works the turbidity level may increase in the local body which may lead to the considerable impacts on marine resources. The runoff from the site containing construction materials, debris, and construction waste and excavated earthen materials may have adverse impacts on the water environment especially on nearby marine water habitat, which in turn can increase turbidity in and consequently affects the rate of the photosynthetic activity of the aquatic life. Other

Mantec Consultants Pvt. Ltd. Page 215

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

sources of potential impacts arise from uncontrolled run – off from the labour camps and accidental spill of oil etc. in to surface water bodies. Recommended water pollution management strategies include:

 During concrete work, care will be taken that no mortar or cementing material shall fall in the water as this will not only pose impacts but also would lead to loss of material.

 As a precautionary measure this circumstances lead to providing of plastics sheet or tarpaulin in order to avoid any chance of dumping of construction materials into the water.

 Storage area of the construction material should be at adequate distance from the coastal area to prevent any chances of contamination of coastal/marine environment as well as to facilitate proper / efficient construction work.

 Runoff (Wastewater) from the construction work should be carefully managed to ensure the prevention of entry of contaminants arising from construction work/site.

 Spillage or leakage of construction material in the nearby aquatic habitat is envisaged. Care should be taken to minimize the chances of the Spillage or leakage of construction materials.

 Construction materials like concrete should be prepared out of the coastal area. 10.4.2 Operation Phase

Water effluents associated with port activities may include storm water and sewage from port operations, as well as sewage, ballast water (e.g. from oil tankers), bilge water, and vessel cleaning wastewater from ships. Ship sewage and wastewater contains high levels of BOD and Coli form bacteria, with trace concentrations of constituents such as pharmaceuticals, and typically low pH levels. Wash water may contain residues such as oil. Pollutants in bilge water contain elevated levels of BOD, COD, dissolved solids, oil, and other chemicals that accumulate as the result of routine operations. Total water required for the project is 5 KLD and it will be utilized for different facilities in DPT.

Mantec Consultants Pvt. Ltd. Page 216

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Water requirement for the construction purpose for this project is 3 KLD whereas for Domestic/drinking purpose it is 2 KLD. Hence, total water requirement is coming 5KLD. As far as railway line is concerned, it is only 11 KM in length and it does not require provision of STP. Collection tanks of wastewater from the railway toilet shall be emptied at the tuna port from where it will be transferred to STP

Figure 42 : Water Balance Diagram Port Sewage and Storm Water Management Recommendations specific to storm water and waste water management from port facilities include:  Avoiding installation of storm drainage catch basins that discharge directly into surface waters, using containment basins in areas with a high risk of accidental releases of oil or hazardous materials (e.g. fueling or fuel transfer locations), and oil / grit or oil / water separators in all runoff collection areas. Oil / water separators and trapping catch basins should be maintained regularly to keep them operational;

Mantec Consultants Pvt. Ltd. Page 217

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

 Installing filter mechanisms (e.g. draining swabs, filter berms, drainage inlet protection, sediment traps and sediment basins) to prevent sediment and particulates from reaching the surface water.

10.4.2.1 Ship Wastewater Management  Port operators should provide collection, storage, and transfer and / or treatment services, and facilities of sufficient capacity and type for all wastewater generated by vessels at the port in accordance with MARPOL and national regulations:

 Oily waste and wastewater should be collected in barges, vehicles, or central collection systems and storage tanks; the capacity of oily waste collection should be established based on applicable MARPOL provisions;

 Wastewater with noxious chemicals from bulk tank cleaning should be collected through appropriate onsite or off‐site treatment prior to discharge; 113865269  Incompatible substances should not be mixed in the collection system. Treatment methods should be established based on the effluent characteristics.

Smaller vessels used for harbor services should be equipped with recycling or chemical toilets, or holding tanks, that could be discharged to shore facilities.

10.4.2.2 Rain Water Harvesting Deendayal Port Trust is already having the rain water harvesting pond in Gopalpuri colony. However, there is no rain water harvesting system proposed in the proposed integrated facilities as there is scanty rain in the Kutch area.

10.5 Waste Management Non‐hazardous solid waste generated at construction and decommissioning sites includes excess fill materials from grading and excavation activities, scrap wood and metals, and small concrete spills. Other non‐hazardous solid wastes include office, kitchen, and dormitory wastes when these types of operations are part of construction project activities. Hazardous solid waste includes contaminated soils, which could potentially be encountered on‐site due to previous land use activities, or small amounts of machinery maintenance materials, such as oily rags, used oil filters, and used oil, as well as spill cleanup materials from oil and fuel spills.

Mantec Consultants Pvt. Ltd. Page 218

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

The type and amount of solid and liquid wastes associated with port operations may vary significantly depending on the nature of port operations and the types of ships serviced. Wastes originating at the port may include inert solid waste from cargo packaging and from administrative offices, as well as hazardous or potentially hazardous waste associated with vehicle maintenance operations (e.g. used lubricating oils and engine degreasing solvents). Wastes originating from ships may include oily sludge, inert materials such as food packaging, and food waste.

Waste materials generated on vessels and at the port include plastic, paper, glass, metal, and food wastes. Hazardous wastes generated on vessels and by maintenance activities include waste oil, batteries, paints, solvents, and pesticides. Ports typically manage collection and storage of hazardous and nonhazardous wastes, with transportation, treatment, and disposal managed by third parties. The port shall provide reception facilities for waste such as containers, general‐use skips, and bins.

Specific pollution prevention, minimization, and control recommendations for ship‐ generated wastes received by port facilities are outlined below.

10.5.1 General Waste Reception Facilities Port facilities should provide adequate means of receiving and managing effluents and wastes to meet its own needs and those of visiting ships and for which the port is designed to service. The provision of waste reception facilities should be developed in coordination with the local governments according to their commitments to the MARPOL Convention as port states. Port waste reception facilities should provide adequate capacity to receive port and ship generated wastes including appropriately sized and located receptacles, and the capacity to deal with seasonal fluctuations.

10.5.2 Ship Wastes Management  Information should be available for ship captains to identify solid waste reception facilities and acceptable handling procedures at ports;

 Discharge of solid waste from vessels should be prohibited while in port in accordance with MARPOL and national regulations. More stringent restrictions should be considered, if necessary, to protect the port environment;

Mantec Consultants Pvt. Ltd. Page 219

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

 A collection and disposal system should be developed for ship‐generated garbage for ships alongside and at anchor, consistent with the International Maritime Organization (IMO) Comprehensive Manual on Port Reception Facilities. Closable skips should be provided at the berths and towed or self‐propelled barges fitted with skips should be used to collect garbage from ships at anchor;

 Food waste from ships delivered to the port should be managed according to applicable local regulations intended to protect human and animal health. Local requirements may include rendering, incineration, or land filling of food waste and mixed waste containing food waste.

10.6 Dredged Materials Management Construction and maintenance dredging, and dredge spoil disposal, may impact habitats and pose a significant hazard to human health and the environment, particularly if the sediments are contaminated by historical deposition and accumulation of hazardous materials, whether due to on‐site or off‐site activities.

The following recommendations should be adopted to avoid, minimize, or control impacts from dredged materials, as part of a Marine Dredging Management Plan and Total initial capital of dredge material will be 13,56,000 m3 generated and maintenance 2,71,200 m3/Year and it will be disposed at Tuna-Tekra (Latitude: 22°53'18"N & Longitude: 70° 06'.20"E).

10.6.1 Dredge Planning Activities Dredging should only be conducted if necessary, and based on an assessment of the need for new infrastructure components or port navigation access to create or maintain safe navigations channels, or, for environmental reasons, to remove contaminated materials to reduce risks to human health and the environment; Prior to initiation of dredging activities, materials should be evaluated for their physical, chemical, biological, and engineering properties to inform the evaluation of dredge materials reuse or disposal options.

Mantec Consultants Pvt. Ltd. Page 220

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 10.6.2 Dredging  Excavation and dredging methods should be selected to minimize suspension of sediments, minimize destruction of benthic habitat, increase the accuracy of the operation, and maintain the density of the dredge material, especially if the dredge material includes contaminated areas. There are several dredging methods which are commonly used depending on the depth of the sediments and environmental concerns such as the need to minimize sediment suspension and increase dredging accuracy.

 Areas sensitive for marine life such as feeding, breeding, calving, and spawning areas should be identified. Where sensitive species are present, dredging (and blasting) should be conducted in a manner so as to avoid fish migration or spawning seasons, routes, and grounds;

 Use techniques (e.g. silt curtains), to minimize adverse impacts on aquatic life from the re‐suspension of sediments;

 Inspection and monitoring of dredging activities should be conducted to evaluate the effectiveness of impact prevention strategies, and re‐adjusted where necessary.

10.6.3 Disposal of Dredged Material  Dredged material should be analyzed in order to select appropriate disposal options (e.g. land reclamation, open water discharge, or contained disposal).

 Beneficial reuse of uncontaminated, dredged material should be considered (e.g. for wetland creation or enhancements, habitat restoration, or creation of public access / recreational facilities);

 Use of lateral containment in open water disposal should be considered. Use of borrow pits or dikes reduces the spread of sediments and effects on benthic organisms;

 Use of cap containment sediments with clean materials should be considered. Level bottom capping or a combination of borrows pits / dikes with capping reduce the underwater spread of contaminated material;

 Confined disposal facilities should be used, either near shore or upland, when open water disposal is not feasible or desirable. If dredge spoil is contaminated, confined

Mantec Consultants Pvt. Ltd. Page 221

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

disposal facilities should include liners or other hydraulic containment design options to prevent leaching of contaminants into adjacent surface or groundwater bodies. Treatment of dewatering liquids (e.g. metals and persistent organic pollutants) may be required prior to discharge.

10.7 Hazardous Materials and Oil Management Hazardous materials at ports include large volumes of hazardous cargo, as well as oil and fuels and hazardous substances used in port activities including vessel, vehicle, and grounds maintenance. Spills may occur due to accidents (e.g. collisions, groundings, fires), equipment failure (e.g. pipelines, hoses, flanges), or improper operating procedures during cargo transfer or fueling, and involve crude oils, refined products or residual fuels, liquid substances, and substances in packaged form. Additionally, equipment maintenance may involve the use of potentially hazardous materials including solvents and lubricants. Recommended prevention, minimization, and control techniques specific to port facilities include the following.

10.7.1 Spill Prevention Oil and chemical‐handling facilities should be located with consideration of natural drainage systems and environmentally‐sensitive areas (e.g. mangroves, corals, aquaculture projects, and beaches, providing physical separation / distance whenever possible);

Ports should include secondary containment for above ground liquid storage tanks and tanker truck loading and unloading areas;

Hazardous materials storage and handling facilities should be constructed away from active traffic and protect storage areas from vehicle accidents. Covered and ventilated temporary storage areas should be provided for leaking hazardous cargo and designed to facilitate collection of leaks and spills (e.g. slope surface to allow capture of spills, use valved catch basins that allow spills and releases to enter a dead‐end sump from which spilled materials could be pumped);

Fuel dispensing equipment should be equipped with “breakaway” hose connections that provide emergency shutdown of flow should the fueling connection be broken by

Mantec Consultants Pvt. Ltd. Page 222

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

movement. Fueling equipment should be inspected daily to ensure all components are in satisfactory condition.

10.7.2 Spill Control Planning  Deendayal Port Trust should prepare a spill prevention, control, and countermeasure plan consistent with the IMO Manual on Oil Pollution Section II ‐ Contingency Planning, which:

 Identifies areas within the port that are sensitive to spills and releases of hazardous materials and locations of any water intakes (e.g. cooling water for shore‐based industries);

 Outlines responsibility for managing spills, releases, and other pollution incidents, including reporting and alerting mechanisms to ensure any spillage is reported promptly to the Port Authorities and personnel are informed to take appropriate action;

 Includes provision of specialized oil spill response equipment (e.g. containment booms, recovery devices, and oil recovery or dispersant application vessels);

 Includes training of response personnel in deployment of equipment, and testing of the contingency plan through regular reporting and alerting exercises and less frequent deployment of the specialized spill response equipment;

 Include training of response personnel in animal welfare techniques related to spills.

10.7.3 Goods Handling Deendayal Port Trust should implement systems for the proper screening, acceptance, and transport of dangerous cargo based on local and international standards and regulations, including the following elements:

 Establishment of segregated and access‐controlled storage areas with the means to collect or contain accidental releases;

 Requesting Goods Manifests for hazardous materials whether in transit, loading or unloading to and from ships, including proper shipping (technical) name, hazard class, United Nations number, and packing group;

Mantec Consultants Pvt. Ltd. Page 223

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

 Training staff in relevant aspects of dangerous goods management including screening and acceptance of dangerous goods at the port;

 Emergency response procedures specific to dangerous goods.

10.8 Biodiversity Management Plan Construction and maintenance dredging, disposal of dredge spoil, construction of piers, wharves, breakwaters, and other water‐side structures, and erosion may lead to short and long‐ term impacts on aquatic and shoreline habitats. Direct impacts may include the physical removal or covering of sea floor, shore, or land‐side habitat, in addition to changes to water flow patterns and related sedimentation rates and patterns, while indirect impacts may result from changes to water quality from sediment suspension or discharges of storm water and wastewater. Additionally, the discharge of ballast water and sediment from ships during port operations may result in the introduction of invasive aquatic species. Recommended measures to prevent and control these impacts include the following:

 Potential impacts to shoreline vegetation, wetlands, coral reefs, fisheries, bird life, and other sensitive aquatic and near‐shore habitats during port construction and operation should be fully assessed with special consideration for areas of high biodiversity value or those required for the survival of critically endangered or endangered flora and fauna. The depth of the port should be considered at the design phase in terms of habitat destruction and the amount and nature of dredging required. Additionally, specific prevention and mitigation measures should be adopted for blasting activities which could cause considerable impacts to marine organisms and their habitats during construction;

 Port facilities that conduct cleaning or repair of ballast tanks should be equipped with adequate reception facilities able to prevent the introduction of invasive species. Treatment technologies might include those applied to other effluents accepted in port reception facilities or more specific methods such as filtration, sterilization (e.g. using ozone or ultraviolet light), or chemical treatment (e.g. biocides).

Mantec Consultants Pvt. Ltd. Page 224

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

 Deendayal Port Trust should provide ship operators with details on the port, state, or port authority ballast water management requirements, including the availability, location, and capacities of reception facilities, as well as with information on local areas and situations where ballast water uptake should be avoided.

10.9 Greenbelt Development Green vegetal cover is not only pleasing to the eyes but also beneficial in many ways such as conservation of bio-diversity, retention of soil moisture, recharge of groundwater and moderation of micro-climate. Another important role of vegetal cover is containment of pollution. Besides acting as a carbon sink, certain species of plants can even absorb the

atmospheric CO2. Raising of green belts with right types of species can serve as a useful buffer to contain the menace of pollution from different sources in the project area. Therefore, a “Green Belt Development Plan” by using the native species has been proposed for the project area.

Objectives Objectives of the proposed green belt are as follows:

 Improvement of bio-diversity of the area  Improvement of aesthetics of the site  Mitigation of air pollution  Attenuation of noise generated from operation of different machines and movement of vehicles Need of the greenbelt plan Standard ToR point no. 26 prescribed for the project “Development of Remaining three Integrated facilities (Stage-I) within the existing Deendayal Port Trust Limit at Kutch district of Gujarat. (1. Development of Container Terminal at Tuna off Terka on BOT basis; 2. Construction of Port Craft Jetty & shifting of SNA Section at Deendayal Port Trust; 3. Railway Line from NH-8A to Tuna Port- 11.00 km) clearly indicate “Examine the details of afforestation measures indicating land and financial outlay. Landscape plan, green belts and open spaces may be described. A thick green belt should be planned all around the nearest settlement to mitigate noise and vibrations. The identification of species/ plants should be made

Mantec Consultants Pvt. Ltd. Page 225

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla based on the botanical studies, and Approved ToR point no. XXIV prescribed by the committee dated 06.06.2017 indicating “Layout plan of existing and proposed Greenbelt”. Development of greenbelt The green belt plantation is proposed on the area of 31.35 Ha which is 33% area of the project. The greenbelt shall be provided along approach roads, nearby project sites and near settlements. The greenbelt shall be designed in three tier system or as per availability of space. The three tier system shall be followed so that it could provide complete canopy coverage and form a complete foliage cover from ground flora up to top canopy and could provide considerable attenuation for noise and air pollution impact. In the three tier system, first inner rows shall have flowering shrubs and herbs. Small trees shall be planted in the middle rows followed by taller trees in the last row. Adequate space shall be kept between the trees, small trees and shrubs. The selection of plant species for greenbelt development based on “Guidelines for Developing Green Belts, PROBES/75/1999-2000” for differenent purposes are as follows:

For absorption of gases released from movement of vehicles:

 Tolerance towards pollutants,  Longer duration of foliage,  Freely exposed foliage, through  Adequate height of crown,  Openness of foliage in canopy  Big leaves with long and broad laminar surfaces  Large number of stomatal apertures  Well exposed stomata

For removal of suspended particulate matter:

 Height and spread of crown  Leaves supported on firm petioles  Abundance of surface on bark and foliage through  Roughness of bark  Epidermal outgrowth on petioles

Mantec Consultants Pvt. Ltd. Page 226

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla  Abundance of axiliary hairs  Hairs or scales on laminar surfaces and  Protected stomata

Plantation along road side, and around nearest settlements:

Greenbelt will help in mitigating impacts of vehicular pollution and Noise and Vibration. Vehicles are ground level mobile sources of gaseous and particulate matter pollutants. Species selected for plantation along road sides shall therefore be capable of absorption of gaseous as well as particulte matter pollutants and mitigating of impacts of noise and vibrartion due to operations around nearest selttlements. For green belt development CPCB Guideline recommended intermixing of trees and shrubs should be in such a manner that the vertical foliage area density remains almost uniform.

Bio-climatic zone

The DPT Stage-II facilities are located in Kutch District of Gujarat State. As per bio-climatic zones of India (CPCB Guidelines, 1999-2000), the site falls within “Gujarat Plains and Hill regions”, and sub-zone “North-West Arid” with Arid to Semi-arid climate.

Selection of species

The selection of species for the proposed green belt is based on the recommendations under the CPCB guidelines for the applicable bio-climatic sub-zone. While selecting the species from the recommended list, quick growing species with longer duration of foliage and tolerant to different pollutants, considering the usage by local people, have been preferred. With these considerations, the following species have been selected for green belt development.

Table 72: Trees proposed for Greenbelt development S. N. Species Ht. Family Local Growth Sensitive/ (m) Name Tolerant (To air pollution) 1 Achras sapota 7-10 Sapotaceae Chiku Slow Tolerant growing 2 Aegle marmelos 12-15 Rutaceae Bel Slow Tolerant growing

Mantec Consultants Pvt. Ltd. Page 227

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3 Ailanthus excelsa 20-22 Simaroubaceae Mahanimb Quick Tolerant growing 4 Albizia lebbeck 12-16 Mimosaceae Safed Siris Quick Tolerant growing 5 Anogeissus latifolia 20-25 Combretaceae Dhaura Slow Tolerant growing 6 Anthocephalus 25-30 Rubiaceae Kadamb Quick Tolerant chinensis growing 7 Azadirachta indica 12-15 Meliaceae Neem Quick Tolerant growth after first season 8 Bauhinia purpurea 5-7 Caesalpiniaceae Kanchan Quick Tolerant growing 9 Cassia fistula 12-14 Caesalpiniaceae Amaltas Quick Tolerant growing 10 Cassia siamea 10-12 Caesalpiniaceae Kassod Fast Tolerant growing 11 Dalbergia sissoo 25-28 Fabaceae Shisham Quick Tolerant growth after first season 12 Emblica officinalis 4-5 Euphorbiaceae Amla Quick Tolerant growing 13 Ficus benghalensis 05-20 Moraceae Bargad Quick Tolerant growing 14 Ficus religiosa 15-20 Moraceae Peepal Slow Tolerant growing in early stages 15 Ficus glomerata 05-15 Moraceae Gular Quick Tolerant growing 16 Ficus virens 05-10 Moraceae Pilkhan Quick Tolerant growth after first season 17 Lagerstroemia 05-25 Lythraceae Phurush Quick Tolerant parviflora growing 18 Madhuca longifolia 05-15 Sapotaceae Mahua Quick Tolerant growing 19 Mangifera indica 10-18 Anacardiaceae Aam Quick Sensitive growing 20 Morus alba 5-8 Moraceae Shahtut Quick Tolerant growing 21 Polyalthia longifolia 10-15 Annonaceae Ashok Quick Tolerant growing

Mantec Consultants Pvt. Ltd. Page 228

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 22 Spondias pinnata 7-10 Anacardiaceae Amra Quick Tolerant growing 23 Syzygium cumini 15-20 Myrtaceae Jamun Quick Tolerant growing 24 Tamarindus indica 15-20 Caesalpiniaceae Imli Quick Tolerant growing 25 Terminalia arjuna 10-15 Combretaceae Arjun Quick Tolerant growing 26 Terminalia chebula 10-15 Combretaceae Harad Quick Tolerant growing

Table 73: Small Trees proposed for Green belt Development S. Species Family Local Name Growth Sensitive/ No Tolerant (To air pollution) 1 Annona squamosa Annonaceae Sharifa Quick Tolerant growing

2 Bauhinia racemosa Caesalpiniaceae Banraj/Katmauli Quick Tolerant growing 3 Callistemon citrinus Myrtaceae Lemon Bottle Slow Tolerant brush growing 4 Carissa spinarum Apocynaceae Karaunda Quick Tolerant growing 5 Psidium guajava Myrtaceae Amrood Quick Tolerant growing 6 Moringa oleifera Moringaceae Sehjan Quick Tolerant growing

Table 74: Shrub proposed for Green belt Development S. No. Species Family Local Growth Sensitive/ Name Tolerant (To air pollution) 1 Duranta repens Verbenaceae Pigeon Quick Tolerant berry growing 2 Bougainvillea spectabilis Nyctaginaceae Booganbel Quick Tolerant growing 3 Citrus limon Rutaceae Nimbu Quick Tolerant growing 4 Grewia subinaequalis Tiliaceae Phalsa Quick Tolerant growing 5 Hibiscus rosa-sinensis Malvaceae Gudhal Quick Tolerant growing 6 Lawsonia inermis Lythraceae Mehandi Quick Tolerant

Mantec Consultants Pvt. Ltd. Page 229

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla growing 7 Murraya paniculata Rutaceae Marchula Quick Tolerant growing 8 Nerium indicum Apocynaceae Kaner Quick Tolerant growing 9 Sesbania sesban Fabaceae Jainti Quick Tolerant growing 10 Thevetia peruviana Apocynaceae Pila kaner Quick Tolerant growing

Medicinal uses of some plants selected for greenbelt development The plants selected for greenbelt development are also important for their medicinal values. These plants are utilized by the local persons for curing different ailments. Some of the plants with their medicinal uses are listed below: Table 75: Medicinal uses of some plants proposed for Green belt Development S. No. Botanical Name Common Part used Medicinal use Name 1 Ailanthus excelsa Ardu Stem Stem Juice mixed with sugar or honey is given orally to birth control Bark Stem bark Decoction is given orally mixed with honey to treat Dysentery 2 Aegle marmelos Bel Ripe fruit Ripe fruit is used to treat Dyspepsia, bacillary dysentery Roots and Roots and bark decoction is used Bark to treat Fever Leaf Leaf extract are helpful in treating Inflammation, asthma, hypoglycemia, hepatitis etc. 3 Albizia lebbeck Safed Siris Leaf Leaf extract are helpful in Bites and stings from venomous animals, ear pain and coughing Bark Bark extract is helpful in Blood purification. Seeds Seeds extract are used in Diarrhoea and Dysentery 4 Anthocephalus Kadamb Leaf Hydrocoele and in Pyorrhea, chinensis ulcers and wounds, stomatitis Bark Eye diseases Fruit Gastric irritability

Mantec Consultants Pvt. Ltd. Page 230

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 5 Anogeissus latifolia Dhaura Bark Bark extract is used in Diarrhoea, cough, liver diseases, snakebite and skin diseases Gum Gum is used as Tonic and generally consumed after delivery of child. Leaf Leaf extract is helpful in curing Purulent discharges from the ear Fruit Fruit is taken for relief in Cough and biliousness 6 Azadirachta indica. Neem Leaf Leaf extract cures Leprosy, intestinal helminthiasis, respiratory disorders, constipation, rheumatism, chronic syphilitic sores and ulcer Flower Flowers extracts are useful in Bile suppression, elimination of intestinal worms and phlegm Fruit Fruit is taken for curing Piles, intestinal worms, urinary disorder, phlegm, eye problem, diabetes, wounds and leprosy Bark Analgesic and antipyretic 7 Cassia fistula Amaltas Seeds Mild laxative Leaf Insect bites, swelling, rheumatism and facial paralysis Roots Tonic, an astringent, febrifuge and strong purgative, migraine and dysentery 8 Carissa carandas Kronda Fruit used as vegetable and medicine 9 Dalbergia sissoo Shisham Leaf Gonorrhoea Roots Astringent Wood Leprosy and to allay vomiting 10 Ficus benghalensis Bargad Bark Dysentery, diarrhoea, leucorrhoea, nervous disorders and reduces blood sugar in diabetes Leaf Leaf extract is applied externally to abscesses and wounds to promote suppuration. Aerial Pimples, leucorrhoea and Roots osteomalacia Twigs Strengthen gums and teeth

Mantec Consultants Pvt. Ltd. Page 231

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Latex Rheumatism, haemorrhoids, gonorrhea, cracks of the sole and skin diseases 11 Ficus glomerata Gular Bark Diabetes, bronchitis, dry cough, dysentery, diarrhoea etc. Leaf Diarrhoea, dyspepsia, haemorrhages and obesity Fruit Leprosy, blood diseases, fatigue, leucoderma etc. 12 Lagerstroemia Phurush Leaf Diabetes mellitus parviflora Roots Mouth ulcers Bark Febrifuge, and for relief of abdominal pains 13 Madhuca longifolia Mahua Bark Leprosy and wounds Flower Cough, biliousness and heart- trouble. Fruit Blood diseases 14 Mangifera indica Aam Roots and Anti-syphilitic, anti- Bark inflammatory, leucorrhoea, wounds, ulcers and vomiting. Leaf Cough, hiccup, burning sensation, hemorrhages, diarrhoea and dysentery Flower Anorexia, dyspepsia, diarrhoea and aneamia etc Ripe Fruit Anorexia, dyspepsia, cardiopathy, haemorrhages from uterus, lungs and intestine and aneamia. Unripe Dysentery ophthalmia, and Fruit urethrorrhagia 15 Tamarindus indica Imli Fruit used as food 16 Terminalia arjuna Arjun Leaf, Medicinal use Stem Bark

Plantation programme The greenbelt development program shall be started immediately after the project is accorded environmental and other statutory clearances, and will be completed within 2 years.

The activities in primary stage (1st year) will consist of the following.

Mantec Consultants Pvt. Ltd. Page 232

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 1. Appointment of expert/consultant for preparing a detailed plan in consultation with local Forest Department authorities 2. Identification of locations for plantation of seedlings/ sapling of species given in the list 3. Survey of the area for plantation of trees and preparation of detailed map 4. Soil testing, Digging of pits, protective fencing and soil conditioning with organic manure 5. Planting of seedlings and sowing of seeds (during monsoon season)

The work plan for the 2nd year is as follows:

1. Avenue plantation along internal and approach roads 2. Plantation around nearest settlement 3. Maintenance and irrigation of species planted earlier 4. Survey of the area to identify the locations for re-plantation of seedlings 5. Plantation of seedlings at the identified locations 6. Development of lawns and gardens with ornamental trees in vacant areas around the administrative building 7. Maintenance and irrigation to achieve a targeted survival rate (80%) of the planted species.

The work plan for secondary stage (subsequent three years) comprises 1. Irrigation and maintenance of seedlings/saplings on routine basis 2. Routine soil conditioning with organic manure 3. Cleaning of afforested areas to remove weed species (unwanted species) 4. Cleaning and maintenance of greenbelt and other plantation areas 5. Replacement of dead species with new ones. FINANCIAL PROVISION Financial provisions for the proposed green belt development plan are as follows:

Table 76: Expenditure on Greenbelt Development Plan S. No. Particulars Amount (Rs)

PRIMARY STAGE (In first two years)

Mantec Consultants Pvt. Ltd. Page 233

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

1 Fees of experts/consultants for detailed work planning 50000.00

4 Site preparation, Soil Testing, Conditioning & manuring of soil, 500000.00 Trenching, Pit digging, Protective fencing SECONDARY STAGE (In subsequent three years)

5 Procurement of tree seedling, sapling, Plantation of tree species, 300000.00 Weeding and clearing of plantation area, Replacement of dead plants, manuring, watering, and monitoring of growth of the plants during third year

6 Plantation of tree species, weeding and clearing of plantation area, 200000.00 Replacement of dead plants, manuring & soil conditioning, Irrigation and monitoring of growth of the plants during fourth year

7 Plantation of tree species, weeding and clearing of plantation area, 200000.00 Replacement of dead plants, manuring & soil conditioning, Irrigation and monitoring of growth of the plants during fifth year

Total 1250000.00

Layout Plan for Green Belt Development Plan has been enclosed as Annexure-VIII.

10.10 Mangrove Plantation

DPT had carried out Mangrove Plantation in an area of 1300 Ha., through various government agencies like Gujarat Ecology Commission, State Forest Department. DPT further signed MoU with Gujarat Ecology Commission for implementation of 100 Ha. Mangrove Plantation at DPT as per the condition mentioned in the EC & CRZ Clearance granted by the MoEF&CC,GoI during 19.12.2016 for “Development of 7 Integrated Facilities (Stage I) within existing DPT at Kandla”. it is also relevant to mention here that, DPT had already undertaken massive greenbelt plantation in and around Port area, Colony area etc. Layout Plan for existing Mangrove Plantation at Kandla has been enclosed as Annexure-IX.

Mantec Consultants Pvt. Ltd. Page 234

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 10.10.1 Mangrove Plantation Plan Study was conducted by GUIDE, Bhuj for status, conservation and management of mangroves (Annexure-XI).

1) Year 2005‐06 – 20 hectares

2) Year 2008‐09 ‐ 50 hectares

3) Year 2010‐11 – 100 hectares

4) Year 2011‐12 – 200 hectares

5) Year 2012‐13 – 300 hectares

6) Year 2013 ‐14 – 330 hectares

7) Year 2014 ‐17 – 300 hectares

Total ‐ 1300 hectares 10.11 Energy Conservation Measures Energy conservation measures will be implemented to ensure that the use of non‐ renewable resources is minimized. A key component of achieving energy conservation would be the development of an Energy Management Action Plan. This plan should be included as part of the Construction and Operational EMPs. The Energy Management Action Plan will be consistent with the energy conservation measures during both construction and operation phase.

10.11.1 Energy Conservation during Construction Phase Recommended measures to conserve energy during construction phase include the following:

 Efficient work scheduling and methods that minimize equipment idle time and double handling of material;

 Throttling down and switching off construction equipment when not in use;

 Switching off truck engines while they are waiting to access the site and while they are waiting to be loaded and unloaded;

 Switching off site office equipment and lights and using optimum lighting intensity for security and safety purposes;

 Careful design of temporary roads to reduce transportation distances;

Mantec Consultants Pvt. Ltd. Page 235

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

 Regular maintenance of equipments, to ensure optimum output of operation and fuel efficiency.

10.11.2 Energy Conservation during Operation Phase Recommended measures to conserve energy during operation phase include the following:

 Employing renewable energy sources such as day lighting and passive solar heating;

 Using energy efficient electrical appliances;

 Installing lighting control devices where appropriate and linking to photoelectric dimming; and;

 Switching off truck engines while they are waiting to access the site and while these are waiting to be loaded and unloaded;

 Throttling down and switching off idle equipment;

 Regular maintenance of all powered equipment to ensure appropriate fuel consumption rates.

10.12 Environment Management Cell Deendayal Port Trust has established Environment Management Cell. The task of the Cell is to coordinate specific studies, to carry out environmental monitoring and to evaluate implementation of environmental mitigatory measures. Environment Management Cell shall report to the appropriate authority having adequate powers to implement the required measures. Organizational structure for the implementation of EMP and assign responsibilities and authorities is given in Figure 30.

Environmental Management Cell (EMC) shall conduct tests and record emission levels on each of the items of the EMP as per the Environmental Monitoring Plan. In addition to this, the EMC shall also act at the behest of the person‐in‐charge of the various development activities and report the findings to the EMC head that shall take corrective action and provide for the necessary resources.

Mantec Consultants Pvt. Ltd. Page 236

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

For effective implementation of the EMP, it shall be the management’s direct responsibility to understand what resources would be necessary for routine operations and special operations and to ensure that they would be made available.

10.13 Budgetary Provisions for EMP Based on the communication of Ministry of Shipping (MoS), New Delhi vide file no PT‐ 11033/57/2014‐PD.V dated 25.03.2015, DPT falls in the Category A port of India based on risk of oil spills. For combating risk of oil spills, MoS has directed to procure the pollution response (PR) equipments. The approximate cost on procuring these is estimated around 15 crores which includes booms and skimmers. Beside this cost on oil spills management plan, additional 1 crores is kept for management of air, water, greenbelt etc. Capita

Total cost of the project is Rs.3214.17 Crore and cost towards implementation of EMP is given below,

Table 77: Cost of EMP (Environmental Management Plan) S.No Particulars Capital Cost Recurring Cost (in Lakh) (Per Annum) lakh 1 Pollution Monitoring (Air, Water, Noise & ‐‐ 23.70 Soil) 2 Dredged materials management 150 20 3 Hazardous materials and oil management 1500 15 4 Green Belt Development 12.5 2.5 5 Marine biodiversity /Mangrove 100 20 Management Plan Total 1762.5 81.2 For Recurring cost for 5 years =81.2*5 = 406 Lakh

Mantec Consultants Pvt. Ltd. Page 237

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Figure 43: Organizational structure for implementing the EMP

Mantec Consultants Pvt. Ltd. Page 238

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Table 78: Environmental Management Plan

Environmental Issue/ Impacts Description Remedial Measure Component

Construction Phase Air Generation of dust due to handling and Water sprinklers shall be used; transport in uncovered trucks on dusty roads. Improperly functioning vehicles & Fugitive dust, emissions and dust generation equipment shall be removed; due to concrete mixing, cement handling, Vehicle engines shall not be left running welding, operation of construction machinery when not in use; Prudent and good construction practices shall be used to minimize the spread of sediments; Noise Vehicular noise, use of excavation equipment; During night time transportation Use of construction equipment and power tools; activities shall not be allowed; Use of pile drivers, boring equipment, power Adequate silencers must be attached with tools, drill bits, etc. all vehicles to reduce the noise; Machineries/equipment causing high noise level shall not be operated during the night time; Construction machinery shall be in good working condition and engines turned off when not in use. Water Turbidity level may increase in the water body Excavation and dredging methods will be due to dredging and other construction activity selected to minimize suspension of which may lead to the considerable impacts on sediments; marine resources. Increase turbidity may affect Care will be taken that no construction the rate of the photosynthetic activity of the material shall fall in the water; aquatic life. Plastics sheet or tarpaulin shall be provide in order to avoid any chance of dumping of construction materials into the water; Storage area of the construction material shall be at adequate distance from the coastal area. Terrestrial Flora Fugitive Dust emission; Water sprinklers shall be used to and Mangroves Clearance of terrestrial flora at site, suppress the dust; During site clearance weeds will be uprooted, proper care will be taken to Mangroves with proper conservation plan. Terrestrial & Traffic during night will result in light & horn Speed of vehicles during night will be aquatic fauna affecting the nocturnal. kept under control. Maximum transportation will be done in day time.

Mantec Consultants Pvt. Ltd. Page 239

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Phytoplankton, Pilling & dredging will lead to increased Pilling and dredging shall be done by zooplanktons, turbidity, less penetration of light and hence such methods so as to reduce the impact. Benthos & fishes less photosynthesis and resulting less primary Silt curtain shall be used to reduce the productivity. Due to this fishes and other fauna impact of turbidity and thus reducing the may migrate. loss of primary productivity and subsequent impact on food chain.

Sediment Spillage or leakage of construction material and Care shall be taken to minimize the deposition on the bottom chances of the Spillage or leakage of construction material. Operation Phase Air Combustion emissions from ships propulsion Emissions of NOx and Sox shall be and auxiliary engines and boilers, followed by maintain within the limits established by combustion source emissions from vehicles and international regulations (MARPOL); land‐based engines and boilers. Storage and Low‐sulfur fuels shall be used in port; handling of dry bulk cargo and vehicle traffic on Navigation of port access areas at partial unpaved roads, may also contribute to power; particulate matter emissions. Encouraging storage planning to avoid or minimize re storage and reshuffling of cargo; Transfer equipment (e.g. cranes, forklifts, and trucks) shall be kept in good working condition; Dust suppression mechanisms (e.g. water spray or covered storage areas) shall be used; Noise Noise sources in port operations include cargo Suitable mufflers on engine exhausts and handling, vehicular traffic, and loading / compressor components shall be unloading containers and ships. installed; Acoustic enclosures for equipment casing radiating noise shall be installed; Vibration isolation for mechanical equipment shall be installed; noise sources shall be relocated to less sensitive areas to take advantage of distance and shielding; Personal Protective Equipments shall be provided for eardrum protection of the workers as well as visitors; Periodical maintenance of all equipments and transport vehicles shall be done. Water Water effluents associated with port activities Installation of storm drainage catch may include storm water and sewage from port basins to avoid discharge directly into operations, as well as sewage, ballast water, surface waters; bilge water, and vessel cleaning wastewater Oil / water separators and trapping catch from ships. basins shall be provided;

Mantec Consultants Pvt. Ltd. Page 240

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

The capacity of oily waste collection shall be established based on applicable MARPOL provisions; Wastewater with noxious chemicals from bulk tank cleaning shall be collected through appropriate onsite or off‐site treatment prior to discharge. Flora & Fauna Spillage of Oil & wastes from Ships may impact No discharge from ships shall be allowed, on the creek biota, especially mangroves and MARPOL norms shall be complied. fishes. Due care shall be taken from spillage of the oil and other chemicals during loading or unloading. Hazardous Waste Spills may occur due to accidents (e.g. Oil and chemical‐handling facilities shall / Oil Spills collisions, groundings, fires), equipment failure be located with consideration of natural (e.g. pipelines, hoses, flanges), or improper drainage systems and environmentally‐ operating procedures during cargo transfer or sensitive areas; fueling. Hazardous materials storage and handling facilities shall be constructed away from active traffic; DPT Shall follow the spill prevention, control, and countermeasure plan consistent with the IMO Manual on Oil Pollution Section II ‐ Contingency Planning.

Mantec Consultants Pvt. Ltd. Page 241

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 11. Summary and Conclusion

11.1 General Many states of India are having a well defined maritime policy. Gujarat is one of them and at present the support of the Government for the port sector is significant. It is well known that Gujarat has the longest coastline in the country, and has one of the highest tidal ranges in the world.

11.2 Location and Inception of Deendayal Port Trust Kandla Port is situated at Latitude 23º 01’ N and Longitude 70º 13’ E on the shores of the Kandla Creek. It is in the district of Kutch and is located on the west bank of Kandla creek which runs into the Gulf of Kutch at a distance of 90 nautical miles from the Arabian Sea. The width of the channel varies from 200 meters to 1,000 meters. The contour depth along the shipping channel is around 10 meters. The total length of the Kandla Port approach Channel is around 23 kms.

Navigation is permitted during the day and night according to the draft of the ship. Pilots board the ships at Outer tuna buoy (OTB) at least two hours before high tide. Dredging is undertaken throughout the year. Ships with 13 meters draft can also be brought in during the tidal window.

The port is operational throughout the year as it is an all weather port. There are no adverse wave effects as it is a sheltered port situated in a creek. There is scanty rainfall in this region which is one of the main reasons that the port can handle food grains. The port is well connected with the hinterland by broad gauge railway system and National Highway No. 8‐A. The port can handle dry bulk, break bulk, liquid bulk and container cargo. Kandla is the closest major port to the Middle East and Europe. Kandla is also en‐ route port for ships calling at Karachi, Pakistan’s only major port handling its seaborne cargo.

Mantec Consultants Pvt. Ltd. Page 242

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 11.2.1 Port Profile  Strategic location closest to the northern hinterland  Cost effective port  Vast amount of land available for future expansion  All weather port operational round the year  Large hinterland of over one million square kilometers  Dry port suitable for handling food grains  A Special Economic Zone (KASEZ) in the vicinity to attract trade  Large storage facilities for liquid cargo – POL products, Edible Oil and Chemicals

11.3 Utility requirement

11.3.1 Water Requirement Water will be received from high service reservoir near Bhachau and Narmada Canal through 18” pipeline of Gujarat Water supply and Sewerage Board. 5.0 KLD water will be used for various purposes during the project.

11.3.2 Power Requirement The port receives Bulk power supply from PGVCL through seven 11 KV sub stations. Besides, the port has two diesel generating sets to meet with emergency needs. A scheme is presently under implementation to augment the power supply to 66 KV and to provide necessary infrastructure for receiving Bulk supply, stepping down and distribution.

Uninterrupted good quality estimated power requirement of 900MW is expected to be supplied in the SEZ area by the Gujarat Government. However, master plan caters for setting up a dedicated power back up from an independent power producer (IPP) at a later stage, if required.

11.3.3 Manpower There will be temporary influx of people to the area as 200 labours/day and other people who will be involved directly and indirectly during the construction of facilities.

Mantec Consultants Pvt. Ltd. Page 243

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 11.4 Regulatory framework and need of the EIA

The proposed project will attract CRZ Notification on Coastal Regulation Zone (CRZ) 2011 provides for declaring the Coastal Stretches as Coastal Regulation Zone (CRZ) and regulating activities i.e. imposing restrictions on industries, operations and processes in the CRZ. CRZ is defined as all coastal stretches of seas, bays, estuaries, creeks, rivers and back waters which are influenced by tidal action (in the land ward side) up to 500 m from the High Tide Line (HTL) and the land between the High Tide Level and Low Tide Line (LTL). The HTL means the line on the land up to, which the highest water line reaches during spring tide (the HTL shall be demarcated uniformly in all parts of the country by the Ministry of Environment and Forest, New Delhi recognized authorities). The notification provides for construction of ports, harbour, jetties, wharves, quays, and spillways, under the following regulations:

 Clearance is required for any activity, within the Coastal Regulation Zone only if it requires water front and foreshore facilities.

 The clearance is required from the Ministry of Environment and Forests, GOI for construction of ports and harbors and light houses and for construction activities such as jetties, wharves, quays and spillways.

The area of study covers a radius of 10 km, around the proposed site at Kandla.

11.5 Baseline Data The baseline data for one month has been collected from the project sites as per the Minutes of meeting dated 01/05/2017 & Terms of Reference granted by Ministry of Environment and Forests, New Delhi. The summary of the results are as follows:

11.5.1 Air Environment

The parameters monitored during the monitoring period are PM10, PM2.5, SO2, NOx and CO. The ambient air sampling was performed continuously for 24 hours to determine 24‐ hour average concentration.

Mantec Consultants Pvt. Ltd. Page 244

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Particulate Matter 10 (PM10):

3 The maximum value for PM10 is observed, as 74 µg/m at oil Jetty while 24 hours applicable limit is 100µg/m3 for Industrial, residential, rural and other area. The

3 minimum value of PM10 is 52.0µg/m with recorded at Tuna Port.

Particulate Matter 2.5 (PM2.5):

3 The maximum value for PM2.5 observed is, 48.0 µg/m at Jetty office while 24 hours

3 applicable limit is 60 µg/m for Industrial, residential, rural and other area. The PM2.5 value of 30 µg/m3 is the lowest concentration recorded at Tuna Port.

Sulphur dioxide (SO2):

3 The maximum value for SO2 is observed, as 25 µg/m at Jetty Office, DPT Colony, Khori Creek, Tuna Port while 24 hours applicable limit is of 80 µg/m3 for Industrial,

3 residential, rural and other area. The minimum value of SOx is 11 µg/m at Jetty office,Nirman Bhavan & Tuna Port.

Nitrogen dioxide (NO2):

3 The maximum value for NO2 is observed, as 34 µg/m at Tuna port station while 24 hours applicable limit is of 80 µg/m3 for Industrial, residential, rural and other area. The

3 minimum value of NO2 is 12.0 µg/m at Oil Jetty & Jetty Office.

Carbon Monoxide (CO): The maximum value for CO is observed, as 486 µg/m3 at DPT Colony and the minimum value of CO is 305 µg/m3 at Jetty Office.

11.5.2 Noise Environment The noise data compiled as per the monitoring performed during study period. The results are as follows: Residential Area Residential Area: In residential area, DPT colony noise level is 48.3 dB(A) during day time and 42.5 dB(A) recorded during night time in Pre‐Monsoon during

Mantec Consultants Pvt. Ltd. Page 245

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

the study period Day time and night time noise level within the residential area are well within the prescribed limit. Commercial Area: In commercial area hourly noise levels ranges in non‐Monsoon season (01 Feb 2018 to 28 Feb 2018) from 48.3 to 59.1 dB (A) during daytime and 42.5 to 51.4 dB (A) during night time.

11.5.3 Water Environment Water samples were taken from area of Deendayal Port Trust and one sample is from Gujarat water supply .The maximum and minimum range of parameters observed during the one month (01 Feb 2018 to 28 Feb 2018) for samples taken from Deendayal Port Trust has been discussed below: Temperature (oC) Surface water temperature ranged from 30.1oC. to 30.9oC The bottom water temperature, as expected was found to be slightly lower than surface water temperature in all the stations. The bottom water temperature ranged between 29.7 to 30.5 oC at various sampling stations.

PH The pH values range from 8.17 to 8.41 at all the stations, which indicate that the marine water is marginally alkaline within the study area.

Salinity The salinity values varied from 37.6 to 43.7 % in surface and 36.3 to 42.5 % bottom water samples at various sampling locations. The runoff from nearby salt pans is responsible for the high salinity in the marine water.

Dissolved Oxygen (DO) Dissolved Oxygen content of the surface water at different stations ranged from 4.4 to 6.2 mg/l during the sampling period. As seen from the results the DO content of surface water is slightly higher than the bottom waters (4.6‐6.3). This may be due to the consumption of oxygen due to organic matter and respiration by the benthic species.

Mantec Consultants Pvt. Ltd. Page 246

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Constant mixing results in the absence of any significant variation in salinity among the sites or between surface and bottom water samples.

Electrical Conductivity (EC) Electrical Conductivity (EC) varies from 56.1 to 59.2 mS/cm at various surface water sampling stations. Likewise EC in the bottom water samples ranged from 55.7 to 58.7 mS/cm. No significant variation in EC levels in surface and bottom water samples was observed.

Calcium The calcium concentration ranged from 370 to 480 mg/l at various sampling location covered as part of the study.

Magnesium The Magnesium concentration ranged from 1100 to 1500 mg/l at various sampling location covered as part of the study.

Sodium The sodium concentration ranged from 11900 to 12800 mg/l at various sampling location covered as part of the study.

Chloride The concentration of chloride ranged from 20100 to 24200 mg/l at various sampling location covered as part of the study. No significant variation in surface and bottom water samples was observed, which could be attributed to mixing due to tidal action.

Nitrate The concentration of nitrate ranged from 0.087 to 0.123 mg/l at various sampling location covered as part of the study. No significant variation in surface and bottom water samples was observed.

Mantec Consultants Pvt. Ltd. Page 247

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 11.5.4 Land and Environment

Physical Properties Monitoring data shows that the texture of soil at all locations is Sandy Loam. The monitoring sites have sand ranging from 64% to 76% in soil samples. Silt content varies from 12% to 20%, while Clay content varies from 6% to 12% in the soil samples.

Chemical Properties  The data shows that value of pH ranges from 7.08 at Kandla Creek at new Kandla road to 8.54 at oil Jetty indicating that all soil samples are neutral to basic during the study period.  Jetty 15 area shows maximum conductivity of 7284 µmhos/cm, while Oil Jetty shows minimum conductivity of 1389 µmhos/cm, during the study period.  Values of CEC ranges from 5.42 meq/100g as lowest at Tuna Port and 7.08 meq/100g as maximum at Oil Jetty during then study period.  The average concentration of Nitrogen, Phosphorus and Potassium in the soil samples varies from 6.42 to 8.11 mg/100gm, 0.57 to 0.89 mg/100gm and 5.4 to 7.5 mg/100gm during the study period.

11.5.5 Biological Environment

Biological environment of any area constitutes all living beings of that area; it is an integral part of the environment. Hence, any change in the surrounding environment could cause loss of species or decrease in biodiversity of the area. Therefore, the present study is proposed to assess the impact of the proposed projects on biological environment of the project site and surrounding area within 10km radius. Accordingly, mitigation measures are evolved to sustain the biological diversity. In general biological environment is represented by flora and fauna. Flora constitutes the herbs, shrubs and trees and fauna constitutes the mammals, birds, reptiles, arthropods, amphibians, fishes etc.

The observations made in the flora of the study area reveal that the diversity and affinities of the flora of the region has approximately 71 taxa of flowering plants

Mantec Consultants Pvt. Ltd. Page 248

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla belonging to 28 families. According to the growth habit these species are distributed as: 12 tree species (17%), 10 shrub species (14%), 47 herb species (66%), and 02 mangroves species (3%). The marine vegetation is highly varied, which includes sand dune vegetation, mangroves, sea grasses, macrophytes and phytoplankton. The dominant species of sand dune flora are Euphorbia caudicifolia, E. nerifolia, Aloevera sp, Ephedra foliata, Urochodra setulosa, Sporobolus maderaspatenus, Eragrostis unioloides, Calotropis procera, Fimbristylis sp, Indigofera sp and Ipomoea pescaprae. The common sea grasses found growing on the mud flats are Halophila ovata and H.beccarii. The information was also collected from secondary sources for authentication of the data from Deputy Conservator of Forests, Bhuj and Zoological Survey of India, Jodhpur.

Eleven species of mammals were recorded in the study area of DPT. Through direct sighting 4 species were recorded, 07 species were recorded as per indirect evidence and through secondary sources from Forest and Wildlife Department and local villagers. All the species of mammals have been listed in various schedules of the Indian Wildlife (Protection) Act 1972 but ‘commonly’ occur in the region. Six species of reptiles were reported from the area. Out of these two were of under the lizard category and rests 04 were snakes. Two species of amphibians were also recorded. From the study of marine aquatic environment eleven species of mollusca, seven species of shrimps (Prawn) Arthopodes and seven species of annelids were recorded.

The project influenced area consists of sparse and patchy vegetation which is general in occurrence. No herb, shrub and tree species is falling in the list of Rare/threatened/endangered of Red Data Book of Indian Plants and IUCN. No rare or threatened species of fauna are falling in the project influenced area.

11.6 Impact Predictions

The task of determination & assessment of Impacts of proposed project has been carried out based on the study of project activities, baseline environment status of area, ecological status and legal frameworks. The impacts of the proposed project have been studied for construction & operation phases. There is no activity found accountable to create any major adverse impact on environmental quality.

Mantec Consultants Pvt. Ltd. Page 249

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

11.7 Environment Management Plan Deendayal Port Trust is committed to continuously improve the environment in and around port area in line with National and International norms. The Integrated Environmental Management Plan for the integrated facilities within Kandla Port area proposes to integrate the baseline conditions, impacts likely to occur, and the supportive and assimilative capacity of the system. The most reliable way to achieve the above objective is to incorporate the management plan into the overall planning and implementation of the projects.

11.8 Risk Assessment and Disaster Management Plan The proposed projects are basically for multiple cargo jetty use for import & export of materials. Hence it has been noticed that many physical hazards/risk will occur during the operation of the proposed project. Considering the probable hazards & risk for the operational process and allied activities, risk assessment has been carried out and the details for control & prevention of risk have been formulated as DMP report. Disaster Management Plan including the onsite & offsite emergency plan has also been prepared and included in the impacts assessment study for the proposed project. Necessary safety procedures and other allied information for occupation health & safety has been incorporated in the Risk Assessment & Disaster Management Plan.

11.9 Conclusions The proposed projects will be in existing Kandla Port area which is already in use for Port‐ operations, hence the issue of land use conversion or change in land cover does not arise. As mentioned in the EIA study report, it has been noticed that the baseline environment is found considerably good and after proposed projects there would not be any visual difference in the baseline conditions. Almost all the impacts of the proposed project operations would be restricted to the premises only. The Coastal Zone Regulatory Authority of Gujarat State has granted CRZ recommendations to these 3 proposed facilities considering negligible environmental impacts, proposed management plan and utility of these facilities in National interest. Proponent is committed to effectively implement the Mangrove Development,

Mantec Consultants Pvt. Ltd. Page 250

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Protection & Management plan for control of impacts on mangrove habitat. There would not be any considerable negative impacts on the environment due to the proposed projects which will provide major socio economic benefits for the region.

Mantec Consultants Pvt. Ltd. Page 251

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Chapter 12. Disclosure of Consultants

12.1 Declaration by Experts contributing to the preparation EIA

I, hereby, certify that I was a part of the EIA team in the following capacity which prepared the EIA report of Development of 3 Remaining Integrated Facilities (Stage‐I) within the Existing Deendayal Port Trust at Gandhidham, Kutch, Gujarat by Deendyala Port Trust.

EIA Coordinator

Name Mr. A.S.Brara Period of Involvement March 2017‐ till date Contact Information 011‐41327731 Signature & Date

Functional Area Experts

S.No Functiona Name of Involvement Signature & . l Areas the (task & period) Date Experts 1. AP* Mr. A.S. Consultancy services provided in Brara functional area of Air Pollution Prevention, Monitoring & Control Mr. Consultancy services provided in Satvant functional area of Air Pollution Singh Prevention, Monitoring & Control 2. WP* Mr. S.B. Consultancy services provided in Sinha functional area of Water Pollution Prevention, Control & Prediction of impacts. 3. SHW* Mr. S.B. Consultancy services provided in Sinha functional area of Solid Waste & Hazardous Waste Management Ms. Consultancy services provided in Shailaja functional area of Solid Waste & Gairola Hazardous Waste Management

Mantec Consultants Pvt. Ltd. Page 252

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Mr. Sumit Consultancy services provided in Verma functional area of Solid Waste & Hazardous Waste Management 4. SE* Mr. Anil Consultancy services provided in Kumar functional area of Socio Economics

5. EB Dr. Vivek Consultancy services provided in Dwivedi functional area of Ecology & Biodiversity Mr.G.N.Ma Consultancy services provided in llick functional area of Ecology & Biodiversity

6. HG* Mr. R. K. Consultancy services provided in Khanna functional areas of Hydrology, Ground Water & Water Conservation 7. GEO* Mr. B.M. Consultancy services provided in Sinha functional area of Geology

8. AQ* Mr. S.B. Consultancy services provided in Sinha functional area of Meteorology, Air Quality Modeling & Prediction Mr. A.S. Consultancy services provided in Brara functional area of Meteorology, Air Quality Modeling & Prediction Mr. Consultancy services provided in Satvant functional area of Meteorology, Air Singh Quality Modeling & Prediction 9. NV* Mr. A.S. Consultancy services provided in Brara functional area of Noise study

10. LU* Mr. Consultancy services provided in Deepak functional area of Land Use. Srivastav Mr. Manoj Consultancy services provided in Kr. Singh functional area of Land Use.

Mantec Consultants Pvt. Ltd. Page 253

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla Mr. Consultancy services provided in Pradeep functional area of Land Use. Raturi 11. RH* Mrs. Consultancy services provided in Anuradha functional area of Risk and Hazard. Sharma

12. SC* Dr. Vivek Consultancy services provided in Dwivedi functional area of Soil Conservation.

12.2 Declaration by the Head of the Accredited Consultant Organization

I, A.S.Brara, hereby, confirm that the above mentioned experts have prepared the EIA of Development of 3 Remaining Integrated Facilities (Stage‐I) within the Existing Deendayal Port Trust at Gandhidham, Kutch, Gujarat by Deendyala Port Trust. I also confirm that, I shall be fully accountable for any misleading information mentioned in this statement.

Signature : Name : Mr. A.S. Brara Designation : C. M. D. Name of the EIA Consultant Organization : Mantec Consultants Pvt. Ltd. NABET Certificate No. & Issue date : NABET/EIA/1619/RA0063 dt. Aug, 02, 2017

S.No. Functional Area Code Complete name of the Functional Areas

1. AP Air Pollution Prevention, Monitoring & Control 2. WP Water Pollution Prevention, Control & Prediction of impacts 3. SHW Solid Waste & Hazardous Waste Management 4. SE Socio‐Economics 5. EB Ecology & Biodiversity 6. HG Hydrology, Ground Water & Water Conservation 7. GEO Geology 8. SC Soil Conservation 9. AQ Meteorology, Air Quality Modeling & Prediction 10. NV Noise/Vibration 11. LU Land Use 12. RH Risk Assessment & Hazard Management

Mantec Consultants Pvt. Ltd. Page 254

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla

Chapter 13. Status of Compliance of EC Conditions

Status of compliance of Environmental Conditions granted by State/Centre on existing unit;

M/s DPT has complied the Environmental clearance letter conditions of the following projects in table below.

S.No Name of the Project Status of the Complince 1 Setting up of Single Point Mooring (SPM) and Allied It has complied and details facilities off Veera in Gulf of Kutch for handling are given in the Page no : 3- crude oil on BOT Basis in the State of Gujarat by 7 of the Certified Complince M/s Deendayal Port Trust. Report (Annexure-X) EC Letter No: 11‐27/2010‐IA‐III dt. 11/12/2013 2 Development of plots for construction of It has complied and details Warehouse/Godowns‐Stage‐II at Kandla, Dist‐ are given in the Page no : 9- Kutch by M/s Deendayal Port Trust. 46 of the Certified EC Letter No: SEIAA/GUJ/EC/8(b)/2012 dt. Complince Report 27/12/2012 (Annexure-X)

3 Development of plots for construction of Liquid It has complied and details Storage Farm at Kandla, Gujarat by M/s Deendayal are given in the Page no : Port Trust. 47-114 of the Certified EC Letter No: 10‐36/2008‐IA‐III dt. 02/02/2010 Complince Report & validity of this EC has been extended up to (Annexure-X) 01/02/2020. 4 Construction of 13th to 16th Cargo Berth at Kandla It has complied and details Port by M/s Deendayal Port Trust are given in the Page no : EC Letter No: 11‐70/2006‐IA‐III dt. Sept.2008 & 115-131 of the Certified its validity has been extended by 5 years vide letter Complince Report no‐F.No.11‐70/2006‐IA‐III dt 07/02/2014 (Annexure-X) 5 1. Construction of 10th Cargo Berth It has complied and details (renamed as 12th Cargo Berth) are given in the Page no : 2. Construction of Satge‐1 Warehouse 133-138 of the Certified Godowns on Plot in Kandla Port Complince Report

Mantec Consultants Pvt. Ltd. Page 255

Environment Impact Assessment Report for Developing 03 Integrated Facilities within existing Kandla Port at Kandla 3. Construction of 9th Cargo Berth at (Annexure-X) Kandla Port 4. Consolited Consent & Authorization (CC & A) dt. 02/06/2015 Valide upto 21.07.2020 EC Letter No: 1. J‐17011/11/2003‐IA.III dated 03/03/2004 2. J‐16011/26/2003‐IA.III dated 08/06/2004 3. J‐16011/27/2003‐IA.III dated 29/11/2001 4. GPCB CCA renewed vide letter dated 31/02/2015

Mantec Consultants Pvt. Ltd. Page 256

Annexure-F

Comments for the Development of three integrated facilities (Stage l) within the existing Kandla Port Trust at Gandhidham, Kutch, Gujarat - Agenda item 27.3.8 in the 27th lnfra-2 EAC Meeting:

S.NO Observation Compliance 1. The proposed project is for the construction Yes, the 'construction of three of three integrated facilities within the Kandla integrated facilities which is Port at Kandla. The proposed facilities are- mentioned in Point 1 to 3 (stage I)  Setting up of Container Terminal at within the existing Kandla Port Trust Tuna-Tekra, Kandla Port on BOT Basis Limit. under PPP Model. The proposed project was granted ToR th  Providing Railway Lines from NH 8A to vie letter dated 06 June 2017. Tuna port.  Construction of Port Craft Jetty & Shifting of [Signal and Navigational Aid] SNA Section at Kandla Port. The proposed project was granted ToR vie letter dated 06th June 2017. 2. The proposed project was discussed during the Yes, the name of Nature Conservation 16th lnfra-2 EAC Meeting held on 1st May 2017. Trust is the mentioned in the minutes of The Committee, whilst recommending TOR for EAC meetings held on 1st May 2017. the proposed project had stated in specific The Conservation Action Trust has condition no (iii) All complaints or been incorrectly referred in the representations on the project as available with minutes as Nature Conservation Trust the MoEF&CC, the Kandla Port Trust or with & the correct name of Trust is the Local Administration (District Manager) Conservation Action Trust. including representation received from Nature Conservation Trust shall be addressed to in the EIA with a specific action plan where required. The Conservation Action Trust has been incorrectly referred in the minutes as Nature Conservation Trust. 3. The project proponent has attempted to The reply submitted by the proponent address our queries in the EIA report dated in this regard is in line with the September 2017 Page nos. 184-190]. However, guidelines of MoEF&CC. the reply submitted by the project proponent is inadequate. 4. We had raised queries about the need for The projects are planned as per the carrying capacity study, multiple projects need to meet the demand of increased proposed/approved in the region, piecemeal capacity. As soon as the project gets clearances, the impact of the administrative approval, application to proposed/approved projects on the biodiversity obtain the necessary clearances are of Kandla and Nakti creek thereby on Gulf of initiated. Kutch, and fragmentation of region by the ongoing/proposed activities [point no. 4, 6, & 7]. However the response of the project proponent to the said queries is, ‘No Action is required at the end of project proponent/Consultant. 5. At point no. 5 in our representation we had SEZ project has been dropped by DPT. referred to the excerpts from the minutes of the 34th GCZMA Meeting held on 16th March 2017 . The excerpts refer to the observations made by the GCZMA Sub-Committee during the site visit held on 1Oth February 2017 for' CRZ Clearance for setting up of Port based multi-product Special Economic Zone in 5000 Ha at Tuna (1400 Ha) and Kandla (3600 Ha) within Kandla Port Trust limit, District: Kutch M/s Kandla Port Trust. However, the project proponent in response has stated, 'Excerpts of the meeting are not relevant, as the proposed facilities are not parts of the SEZ'.lt is unclear how the proposed facilities are not relevant, even though they are within the study area of the proposed project. The project proponent should please be asked to clarify this. 6. The entire EIA report is prepared on the One month non mosson season data has baseline study of one month i.e. 15th May been collected for the month of 2017 to 15th June 2017. lt is not clear why the February 2018 as per MoM of 27th project proponent has undertaken the one EAC Meeting. month study in the summer month when less biodiversity is observed. The project proponent should please be asked to clarify the same. 7. The specific condition no-V states, ‘The EIA These three facilities were earlier part report will also provide a one month additional of the 13 facilities the data had been primary base line data with secondary data collected for and EIA report was and compare this with the data as may have submitted. Since these facilities did not been collected earlier and arrive at impacts get CRZ recommendation during the accordingly. The earlier data used by the appraisal of the 13 facilities, the revised project proponent is for the year 2012-2013. proposal was submitted with This data cannot be used for comparison as it addendum. Subsequently, the CRZ is more than three years old. recommendations had been obtained for these three facilities and so the ToR. Hence, only one month monitoring is done and gets compared with the earlier data.

8. The standard TOR at condition no. 4 states, ‘Examine and submit the water bodies Shinai Lake including the seasonal ones within the Adisar Pond Tirupati Nagar corridor of impacts along with their status, Sang River near Galpadar volumetric capacity, and quality likely impacts Lake near Sanghad on them due to the project'. The project Pond near Chandrapar proponent in the reply has stated, 'The Pond near Mithi Rohar Proposed projects are located along the Kandla Nakti Creek creek area. Many other secondary & tertiary Khori Creek creeks are present in the study area arising Kandla Creek from the Kandla creek. The impact of the projects on these water bodies are given in Chapter-4, Anticipated Environmental impact under water environment section 4.4 of Chapter 4. It should be noted that the baseline study has been conducted in peak summer month i.e. 15th May 2017 to 15th June 2017. Moreover, the said section does not provide the list of the water bodies. The project proponent should provide the list including the seasonal ones.

9. The annexure mentioned in the EIA report are The size of complete application is not not attached to the file uploaded on the EC more than 20 MB, hence annexure website. The project proponent should please mentioned in the EIA report could not upload copies of all the annexure in the be attached and uploaded. However, public domain. the same had been submitted in soft copy in CD along with the Hard Copy.

10. The CRZ Mapping of the proposed project has It is submitted that, the CRZ Maps been prepared by IRS, Chennai. As observed prepared by IRS, Anna University, from the maps attached in the EIA report for Chennai have been considered by the the proposed three projects, it is understood Gujarat Coastal Zone Management that Authority and based on the said Maps a) The route of the proposed railway line only, the Gujarat Coastal Zone from NH-8A to Tuna Port 11km is Management Authority in its meeting through mangroves, mudflats, and held on 22/4/2016 had discussed the creeks. proposal of DPT and then only b) The CRZ map prepared by IRS, Chennai forwarded the proposal for grant of [page no.44 of EIA] for the proposed CRZ Clearance. Accordingly, the container terminal at Tuna-Tekra is Director (Environment) & Additional proposed on mudflats. Moreover, the Secretary, Forest & Environment map shows the proposed railway line department, GoG vide letter no. and the proposed road parallel and ENV-10-2015-248-E (T - Cell) dated passing through mangroves, mudflats, 29/6/2016 had issued CRZ Clearance and the creek. As you are aware the reg. letter and forwarded the mangroves and mudflats are categorized proposal to the MoEF&CC,GoI. The as CRZ IA and are protected under the CRZ Maps prepared by Anna CRZ Notification, 2011 . The University are already enclosed as construction activities will further block Annexure A of the EAC Compliance the tidal flow to the mangroves table. thereby causing destruction of the mangroves and mudflats. 11. It is not mentioned. 12. In the 8th expert committee meeting held on DPT obtained necessary prior 7th-8th June 1995, whilst recommending two permission/clearance from the projects (I) Additional facilities for handling statutory authorities concern for all Crude Oil at Vadinar By Kandla Port Trust; the projects implemented and being (ii) Fourth Oil Jetty at Kandla Port, the implemented. Further, it is also committee had stated in additional conditions, relevant to submit here that, as per “No mangrove destruction would be allowed. the direction of CRZ Authority for Areas (enclosed plots) should be identified for mangrove plantation 1000 Ha. in mangrove recovery in consultation with CRZ Recommendation for NlO"Contrary to this, there has been a rampant “Construction of 13th to 16th CB” & destruction of mangroves by Kandla Port directions from MoEF&CC,Goi in Trust. This is in complete violation of the other clearances, till date, DPT had condition stipulated by the expert committee. carried out Mangrove Plantation through various Government agencies like GEC, F & E Dept. etc., in an area of area of 1300 ha. Further, mangrove Plantation in an area of 100 Ha. is in progress by M/s Gujarat Ecology Commission. Further, as per the direction of the CRZ Authority, DPT had carried out scientific study on “Status, Conservation and Management Plan for Mangroves of Kandla Port region reg. during the year 2015 through M/s Gujarat Institute of desert Ecology, Bhuj. Recently, DPT entrusted the work of mangrove plantation monitoring to M/s GUIDE, Bhuj for entire plantation done i.e. 1300 ha. the same is in progress. (Annexure-1)

13. The loss of mangroves in Kandla Port area Kandla Port Trust has furnished has been stated in the EIA report [page no.116], undertaking to State Forest & 'Time Environment Department for Series satetlite imageries are given in Figure 23 afforstation of mangroves in an area of to 25. Analysis results of time serles satellite data 1000 ha. are given in Table 38. It has been noted by expert  KPT had completed Mangrove committee of CRZ. Gujarat during their site Plantation in an area of 20 ha in the visit that many areas of mangroves are badly affected due to various human activities in year 2005-06. Kandla Port area'.  KPT had completed Mangrove Plantation in an area of 50 ha in the year 2008-09.

 KPT had completed Mangrove Plantation in an area of 100 ha in the year 2010-11.

 KPT had completed Mangrove Plantation in an area of 200 ha in the year 2011-12.

 KPT had completed Mangrove Plantation in an area of 300 ha in the year 2012-13.

 KPT had completed Mangrove Plantation in an area of 330 ha in the year 2013-14.

 IFFCO had completed Mangrove Plantation in an area of 200 ha in year 2013-14.

 AKBTL had completed Mangrove Plantation for 250 ha in 2014.

 PT has proposed Mangrove lantation in an area of 300 ha in the 2015-17.

14. The project proponent should submit a list of DPT obtained necessary prior all the projects undertaken wherein mangroves permission/clearance from the were destroyed from the time of port operation statutory authorities concern for all till date. The measures undertaken for the the projects implemented and being protection of the remaining patches should also implemented. Further, it is also be furnished relevant to submit here that, as per the direction of CRZ Authority for 15. The EIA report further states, 'However, KPT mangrove plantation 1000 Ha. in has taken measures for plantation of CRZ Recommendation for mangroves at Satsaida belt (opposite to Kandla “Construction of 13th to 16th CB” & Port) through Gujarat Ecology Commission directions from MoEF&CC,Goi in and Forest Department. The project proponent other clearances, till date, DPT had should please furnish report of the same, along carried out Mangrove Plantation with the site visit photographs, the present through various Government agencies status and survival rate of the plantation. The like GEC, F & E Dept. etc., in an area details of the mangroves afforestation of area of 1300 ha. Further, mangrove undertaken in 1000 hectares should also be Plantation in an area of 100 Ha. is in provided. The project proponent should not progress by M/s Gujarat Ecology undertake mangrove plantation or Commission. compensatory afforestation on mudflats, Further, as per the direction of the CRZ instead reclaimed or encroached area should be Authority, DPT had carried out used. scientific study on “Status, 16. The project proponent should undertake Conservation and Management Plan measures for the protection of the remaining for Mangroves of Kandla Port region mangrove patches in Kandla. reg. during the year 2015 through M/s Gujarat Institute of desert Ecology, Bhuj. Recently, DPT entrusted the work of mangrove plantation monitoring to M/s GUIDE, Bhuj for entire plantation done i.e. 1300 ha. the same is in progress. (Annexure-1)

17. The GCZMA in their recommendation letter of It is also relevant to submit here the proposed project dated 29th June 2016 that, as per the direction of CRZ had directed the project proponent to undertake Authority for mangrove plantation mangrove plantation in an area of 50 ha. in 1000 Ha. in CRZ Recommendation two years in a time bound manner. The project for “Construction of 13th to 16th proponent should please clarify if the CB” & plantation has been undertaken by them and directions from MoEF&CC,Goi in furnish details and photographs of these other clearances, till date, DPT had plantations. carried out Mangrove Plantation through various Government agencies like GEC, F & E Dept. etc., in an area of area of 1300 ha. (from 2005-06 to 2016-17). Further, mangrove Plantation in an area of 100 Ha. ( EC dated 19/12/2016) is in progress by M/s Gujarat Ecology Commission. As far as condition mentioned in the CRZ Clearance reg. letter dated 29/06/2016 reg. mangrove plantation in an area of 50 Ha., DPT will take necessary action once based on the said CRZ Recommendation, the EC & CRZ Clearance received from the MoEF&CC,Goi. Status of EC & CRZ Clearance: Final EIA Report (present proposal remaining 3 integrated facilities) as per TOR was submitted on 8/9/2017 and EAC has discussed the proposal in its meeting held on 25/1/2018 & raised certain observations which are being complied with this compliance.

18. The project proponent has stated in the EIA In compliance of TOR point no. XVI, report that the dredged material will be necessary details have already been disposed at Tuna Tekra location. The project cited by M/s Mantec Consultant in EIA proponent should please clarify if the Report (Capital dredging envisaged is permissions has been sought for the same. 13,56,000 m3, Disposal of dredged material will be at Tuna-Tekra location (Latitude 22053’18” and Longitude 70006’20”). Accordingly, after EC and CRZ Clearance, dredged material will be disposed off, as per recommendation of the CWPRS Report. Copy of the CWPRS report is enclosed as Annexure-2 with this compliance.

19. We would like to draw your attention to the It is submitted that, the CRZ Maps minutes of the 172nd Coastal Regulation Zone prepared by IRS, Anna University, EAC Meeting held on 30th June 2017. Chennai have been considered by The Minutes at page no. 21, item no. 3 notes, the Gujarat Coastal Zone Management "The Committee suo moto took up the issue Authority and based on the said Maps of glaring discrepancies observed in the CRZ only, the Gujarat Coastal Zone maps prepared by IRS, Anna University and Management Authority in its meeting agreed that such causal approach of held on 22/4/2016 had discussed the preparation of CRZ maps are not only proposal of DPT and then only objectionable but speaks of the functioning of forwarded the proposal for grant of the Centre. The Committee therefore CRZ Clearance. Accordingly, the recommended that the Ministry shall take up Director (Environment) & Additional the matter with IRS, Anna University for Secretary, Forest & Environment needful action". department, GoG vide letter no. ENV-10-2015-248-E (T - Cell) dated 29/6/2016 had issued CRZ Clearance reg. letter and forwarded the proposal to the MoEF&CC,GoI.

Study on present status, Conservation and Management Plan for mangroves of Kandla Port Region

GUJARAT INSTITUTE OF DESERT ECOLOGY Post Box # 83, Opp. Changleshwar Temple, Mundra Road Bhuj ʹ Kachchh, Gujarat

GOVERNMENT OF INDIA CENTRAL WATER AND POWER RESEARCH STATION P.O. KHADAKWASLA RESEARCH STATION, PUNE -411 024

COASTAL AND OFFSHORE ENGINEERING LABORATORY

Technical Report No.4712

PHYSICAL TIDAL MODEL STUDIES FOR THE PROPOSED JETTY OFF TEKRA NEAR TUNA AT KANDLA PORT

REPORT DOCUMENTATION SHEET

Technical Report No.4712 Date: March 2010

Title : HYDRAULIC MODEL STUDIES FOR THE PROPOSED DEVELOPMENT OF JETTY OFF TEKRA NEAR TUNA, KANDLA PORT.

Officers Responsible for Conducting the Studies:

Shri N.Ramesh, Senior Research Officer and Shri B.B.Chaudaree, Assistant Research Officer under the supervision of Shri T.Nagendra and Shri Prabhat Chandra, Chief Research Officers under the overall guidance of Shri C.N.Kanetkar Additional Director (Retd.).

Name and Address of the Organization conducting the studies

Coastal and Offshore Engineering laboratory Central Water and Power Research Station, Pune India

Name and Address of Authority Sponsoring the Studies Chief Engineer, Kandla Port Trust, Administrative Building Gandhidham, Kutchch, Gujarath.

Synopsis

Kandla Port Authorities proposed to construct a T-shapped jetty outside Kandla creek to meet the requirement of deep drafted vessel west of Outter Tuna Buoy (OTB) in open gulf. Considering the prevailing flow conditions and requirement of the navigation and berthing operations, CWPRS modified the layout supplied by KPT. The layout was tested in exiting Kandla Estuary Model (scale 1:1000 H ; 1:100 V) at CWPRS by reproducing the localized pit around the jetty with -16.2 m in the front and -15.1 on the back side with turning circles of 600 m diameter on either edge with an approach channel on the western edge having a bottom width of 200 m and a side slope 1:5. The berthing face of the jetty was aligned at an angle of 240o / 60o N considering both the flood and ebb flows in the proposed region. The capital dredging was worked out to be 6.75 Mm3 for the basin and 1.10 Mm3 for the channel. The annual maintenance dredging was estimated to be 0.9 Mm3 for the basin and 0.1 Mm3 for the channel. The recommendations were agreed upon by the Port authorities.

Annexure-G :jdG;re Annexure-H GUJARAT POLLUTION CONTROL BOARD PARYAVARAN BHAVAN Sector-10-A, Gandhinagar 382 010 Phone : (079) 23222425 ffi (079) 23232152 \t7, (079) 23232156 GPCB Fax : Website : www.gpcb gov.in

By R.P.A.O.

AMENDiIENT OF CONSENT TO ESTABLISH

cTE- 89537

Date: No. PC,CCA-KUTGH-1231(2)IGPCB lD'4'1000/ To, Port Trust, existing kandla port at kandla)' Develop ing integrated facilities within Plot No: Kandla & Tuna area, Tal: Gandhidham' Dist Kutch, 310 201'

Establish (CTE)' Subiect Amendmentto Consent to to your unit vde letter no PC/CCA-KUTCH- Rel6rcnce 1) cTE of the Boald issued ' iz:tlcpce to aoooot3354g6' dated 22t 12n015 lD No 125101' datod 2) Your CTE Amendment Appl'cation lnwatd 0!{012017.

Sir' of the Water (Prev€nlion and Control of the power @nfened under section 27 ln exercise Polltrtion)-1981 and ot i^J-oi' ipi"u"noon and Control of of Pollution) Act-1974 under section-21 AuthorizationUnderruIe6(2)oftheH",",ao-,"a.oti,".w"ste(Management&Transboundary en'non'"nt"t iProtecnon) Acl-1986 a,td Rules'2016 I as amenoea rcm]i-Jni"' in" Movement) thls Board is empowered reduclng yo,ir responsiUrt'ty r'nOer t'l-sl'd-Ao"'*u'"' vflthout 'n ""y*u';Establlsh issled vde letter no' conditions- n"coraingiv, ,h" consent to to amend consent order reference (1) stands pc/ccA-KUTcHl231/GPcB lD 44o0oB3;;;i"'a'ita zz'tztzots uncler emended in respect of the icllowing conditions; be up to dated 15/{t'm22' 1. The validity Poriod of the order shall out following additional activitiesl 2. This CTE Amendme nt is issued {or carrying Sr. Activhi6s No. T kra (capaclty 2. I Mit o TEUs 1 Contai T rm nal Tuna '11 km) 2 Railway Line (NH SAto Tuna & SNA Section 3 Construction of Polt Craft Jetty

IF till obtain ing of EC clearance any construction activities of prolect 1 You shall not commence of Irom MoEF&CC, New Delhi. Page I of 2 Ctean Guiarat Green Guiarat Outward No:429717,04/12/2017ISO SOOl-2008 & ISO-14001 - 2004 Certified Organisation in TOR of l\4oEF in order of -2 You shall have to comply with the all condrtions stipulated F.No 10-9/2017-lAlll' dated 06/06/2017 eivironment crearanc€ N;. (T vide order Noi ENVI 0-2015-248-E 3. You shall have to comply with the all co;ditions of CRZ cell), dated 29106/2016

3 3.1 The condition no 3 2 shallbe read as; Kuday' 3.2 (a) The total water consumption for shallnot exceed ll (sewage) shall notexceed 8 Kuday i.Z iol fne quantity ot Oomestic waste water 3.2 The condition no. 3.3 shall be read as: standards The quality of the sewage shall conform to icllowing P GPCB NORMS pH 65to90 mg/L BOD (5 days at c) 30 '100 Suspended Solids mg/L Fecal Coliform 1000 3.3 The condition no. 3 4 shall be read as; shall be utilized for The treated domestic sewag e conforming to the above standards plantation/gardening within premises

lD ,0. The other terms and condilions of CTE vide letter no' PC-CCtuKUTCH/1231iGPCB anooo/331496 dated 22112/2015 shall remain unchanged'

For and on behalf oI Gul.rat Pollution Conlrol Boald

(P,J. Vachhani) S6nior Envlronmental Engineer

Page 2 ol 2

Outward No:429717,04/12/2017 Annexure-I Annexure-J GUJARAT POLLUTION CONTROL BOARD PARYAVARAN BHAVAN Sector 10-A, Gandhinagar 382010 Phone : (079) 23226295 GPCB Fax: (079) 23232156 website: www.9Pcb.gov.in BY R.PAD. In exercise of the power conferred under section-25 of the Water (Prevention and Control of Pollution) Act- 1974, under section-21 of the Air (Prevention and Control of Pollution)-1981 and Authorization under rule 5{4) of the Hazardous Waste (Management, Handling & T.M.) -Rules-200B & as amended, framed under the Environment (Protection) Act- t986. And whereas Board has received consolidated consent application Inward I.D.NO. 77213 dated 20/01/2014 for the Renewal Consolidated Consent and Authorization (CC & A) of this Board under the provisions/rules of the aforesaid acts. Consents & Authorization are hereby granted as under:

CONSENTS AND AUTHORISATION: (Under the provisions /rules of the aforesaid environmental acts)

\ ~KANDLAPORTTRUST, (RESIDENSIAL COLQNY), SEWAGE TREATMENT PLANT, NEW KANDLA, TALUKA: GANDHIDHAM, DlST: KUTCH.

1. Consent Order No,: W - 61508, Date of Issue: 02104/2014. 2. The consent undel" lilG Water Act"1974 shall be valid up to 19/0112019 for use of outlet for the discharge of treated effluent to cp'.m.lbr, of Sewage Treatn;ent Plant of Residential Colony. 3. CONDITIONS UNDER WA,Ell ACT 1974:

3.1 The generation and disposal of Sewage effluent from the domestic operations shall not exceed be 800.00KUDay. 3.2 Domestic effluent srL8.11b9 treBte'! in 2ewc:ge Trc;at:~:mt Plant to conform to the following standards.

PARAMET!:R ! PERMISSIBLE LIMIT BOD l~ ;;:)/~ ai 2(P::'; Less than 20 mgJliter Suspended Solid Less than 30 mgJliter Residual Chlorine Minimum 0,5 mgniter

• All efiorts shall be rlldd8 to remove colour & unpleasant odour as far as practicable.

3.3 The domestic f'ffl'.'~~1 conforminq to the above standards shall be reused further in Gardening Jplantation or discharged int,:,SF8 C"eel( 3.4 The unit shall install flow meters at utilities for measuring category wise (Category as given in Water -Cess Act-1977 schedule II) consumption of water.

Clean Gujarat Green Gujarat ISO - 9001 - 2008 & ISO - 14001 - 2004 Certified Organisation 4. CONDITIONS UNDER AIR ACT 1981:

4.1 Ambient air quality w'lthin and outside the premises of the unit shall conform National Ambient Air Quality Standards notified by MoEFvide notification dtd 16/11/2009 and mainly to the following standards.- Sr. No. Pollutant --'------" TimeWeighted Concentration in ___ .____ Avera~ Ambient air in 1M3 Sulphur Dioxide (S02) Annual 50 24 Hours 80 Nitrogen--Oioxide(NOL) ---'---Arin-u-al--- 40 24 Hours ; 80 Partic-U1ateManer---- Annual 60 'Size le~s -(han1U I_HI i) OR PIVIIOIJg(ivF 24 Hours 100 4. i ::'JI,.cu:",teMatter Arllual 40 (Size less than 25 mm) O~M' 24Hours 60------.J

TERMS AND CO'IDITIOliS ()< AU'"HORISATION: a) The applicant Shall comply with tM provisions of the Environment (Protection) Act - 1986 and the rules made there under b) The authorisatior. be prodl1cer! for ins'Qedon at the request of an officer authorized by the Gujarat Pollution Control 8uard c) The persons authorized silali not rent lend. sell, and transfer of otherwise transport the hazardous wastes without obtaining pnor permission of the Gujarat ?oliution Conlroi Board d) Any unauthorized change In personnel, equipment or working conditions as mentioned in the authorisation order by the pcrso(,::,<-,llt'i0r::Loj '<,'ci,1 GOfl3ti'tliteJ creach of this authorisation, e) It is the dutl' of tf, auJI!:<:ed per:~c:lto ta.kephor pErllission of the Gujarat Pollution Control Board to close down thefac'Wy n An applicatior' ,'ort' ';' m';:';v~):(,;. uthol"isEltionshal' be made as laid down in rule 7 g) Industry shal: :>ubr~I:'"Imual ,rep"rt w'ithln 15 days and sub sequent by 315tJanuary every year h) Hazardous W,IS,r:' ~i-.ail be off il 8cGord&nCf'with tile Haz. Waste (Management, Handling & Transboundal'Y iv1://smellt) rLi,E:5, 2CC8 :.Uid u:li~ 5112.11 ha\/e to obtain Authorization of this Board for all applicable categories of waste. 6.0 GENERAL CONDITIONS: • 6,1 Any change in personnel, equipment or wOrKing conditions as mentioned in the consents fonn/order should immediately be intil'la!;,')clto Ihi~;30ard. 6.2 Applicant shall aiso comply oor,o,ilon" gIVen in annexure I. 6.3 The waste generatJr ~"JII D€ iI.E. Collection, storage, transportation and ultimate disposal) of the wastes generated. 6.4 Records of waste ger'datiutl, its r(ICiliag8iTlenlcliid annLli'Ji return shall be submitted to Gujarat Pollution Control Board in Form - 4 0y J'j'; ,!al';UHI) of eV8'Y year 6.5 In case of any o';(cer:, ,_:etailsof trlt] same shall be submitted In Form - 5 to Gujarat Pollution Control Board. 6.6 As per"Public IiCtb;Ii':y'InSJrE'-'(!;flGt --!:J ,', corrp"my S~IDiig::llrs:.lran02 ponry, if applicable. 6.7 Empty drums 81-i\; ct \'~IC and hazards material shall be treated as per guideline published for "management & !1~llid!i n):itah:I~," ;;;;!c:\fds cf ~he same shall be maintained and forwarded to Gujarat Pollutior, rF-!J~i"l.-Iy

2 GUJARAT POLLUTION CONTROL BOARD PARYAVARAN BHAVAN Sector 10-A, Gandhinagar 382010 Phone :(079)23226295 Fax: (079) 23232156 website: www.gpcb.gov.in 6.8 tn no case any kind of hazardous waste shall be imported without prior approval of appropriate authority. 6.9 In case of transport of hazardous wasle to a facility for (I.E. Treatment, Storage and disposal) existing in a state other than the state where hazardous i','8ste are generated, the occupier shall obtain "No Objection certificate" from the state pollution Control Board, the Committee of the concerned state or Union territory Administration where the facility exists 6.10 Unli1 shall take all concrete measures tc show tangible results in waste generation reduction, voidance, reuse and recycle. Action taken in this regards shall be submitted within 03 months and also along with Form 4. 6.11 Industry shall have to display the relevant information with regard to hazardous waste as indicated in the Hon Supreme Court's o "d0r in V.'F ~JG,S~,;'0: 1995 dated 14t'l October 200l 6.12 Industry shall h2it'::;~( (iata oL:;;;ide the main factory gate with regard to quantity and nature of hazardous chelTl<~:1J~' n pl::lr:~ ;:U(1":g w2stewater and air emissions and solid hazardous waste generated ·,11('1;'·, tl1~'

For and on behalf of Gujarat Pollution Control Board (v.R.G§f I1b SENIOR ENVIRONMENTAL ENGINEER

Date:· j5:'/ ~/20/9,

ISSUE TO: MIS KANDLA PORT ',RUST, (RESIDENSIAL GOLON r). SEWAGE TREATMfNT PI, ANT NEW KANDLA, T~l.'JKA: GANDHIDHAM, DiST: KUTCH

Clean Gujarat Green Gujarat

ISO - 9001 - 2008 & ISO - 14001 - 2004 Certified Organisation Annexure- K Annexure-L

WAPCOS Limited (A GOVERNMENT OF INDIA UNDERTAKING) Swastik Gulmohar Path, Opp. Law College Road Near SNDT College, Erandawane, Pune – 411001  : 020 - 25444796 Fax : 020 - 25444600 Email : [email protected] October, 2016 FEASIBILITY STUDY FOR SETTING UP TRUCK PARKING TERMINAL AT KANDLA

CONTENTS

No. PARTICULARS Pg. No. MAIN REPORT Executive Summary

1.0 BACKGROUND 1

2.0 SCOPE OF WORK 1

3.0 INTRODUCTION 2

4.0 OBJECTIVES AND SCOPE OF STUDY 2

4.1 Scope of Study 2

4.2 Study Objective 3

5.0 METHODOLOGY 3

6.0 DATA COLLECTION 6

6.1 Problem Definition 6

6.2 Preliminary Survey 6

6.3 Survey 9

6.3.1 Commercial Vehicle Count 11

6.3.2 Origin- Destination Survey 12

6.3.3 Drivers’ Interview (Questionnaire) Survey 14

6.3.4 Data provided by WAPCOS are as below 14

6.3.4.1 Primary Data 14

6.3.4.2 Secondary Data 14

7.0 ANALYSIS OF DATA 15

7.1 Commercial Heavy Vehicle Count Survey 15

7.1.1 Monthly Variation 17

7.2 Retention Time Analysis 18

7.3 Analysis of Drivers’ Interview 20

7.3.1 Demographic 20

FINAL FEASIBILITY REPORT

FEASIBILITY STUDY FOR SETTING UP TRUCK PARKING TERMINAL AT KANDLA

7.3.2 Parking Patterns and Preference 22

7.3.3 Parking Solution 22

8.0 ESTIMATION OF TRUCK PARKING DEMAND 24 Estimation of Parking Demand for intermediate Planning 8.1 24 Horizons 8.2 Demand Scenario 24 Total Demand, Incremental Demand and Bay Demand 8.2.1 25 Requirement for Different Growth Scenario 9.0 DESIGN OF PARKING TERMINAL LAYOPUT 29

9.1 Area Distribution 29

9.2 Bay Sizes 30

9.3 Parking Patterns 30

9.3.1 Parallel parking 30

9.3.2 Perpendicular / Right angled parking 30

9.3.3 Angular Parking 31

9.4 Circulation Patterns 31

9.5 Amenities and Other Facilities 32

9.5.1 Traffic growth rate 7% 32

9.5.2 Amenities and other facilities (for traffic growth rate 9%) 37

9.6 Truck Parking Terminal Layout 41

9.6.1 Centralized Truck Parking Terminal 41

9.6.2 Truck Lay-Byes 42

9.7 Parking Regulations 46

9.8 Its Implementation 47

9.8.1 Introduction 47

9.8.2 Smart Parking System 47

9.8.3 Truck Park Occupancy Detection 48 Intelligent Parking Lot Detection System Based on Image 9.8.4 51 Processing 9.8.5 Benefits of using IT’S at Truck Parking Terminal 52

FINAL FEASIBILITY REPORT

FEASIBILITY STUDY FOR SETTING UP TRUCK PARKING TERMINAL AT KANDLA

ANALYSIS OF LOCATION FOR TRUCK PARKING 10.0 53 TERMINAL 10.1 Besides WG –1 53

10.2 Opposite to West Gate-2 55

10.3 Space available at Kandla Bypass 56 Space Available Near KPT Area along Gandhidham- 10.4 57 Kandla Road 10.5 SIPC Location 2 (Smart Industrial Port Location) 58

11.0 BENEFIT – COST ANALYSIS 59

12.0 FINANCIAL ANALYSIS 63

13.0 IMPLEMENTATIONS OPTIONS 75

14.0 RECOMMENDATIONS 82

14.1 Validating Need for Parking 82

14.2 Parking Demand Considerations 83

14.3 Location Suitability 83

14.4 Financial Feasibility 84

14.5 Liquid Cargo Forecasting 84

FINAL FEASIBILITY REPORT

Annexure-3 FORM-2 APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE 1 Details of Project a Name of the Project (s) Development of 3 remaining integrated facilities (Stage-I) within the existing Deendayal Port trust at Gandhidham, Kutch, Gujarat by Deendayal Port Trust.

1 Development of Container Terminal at Tuna off Tekra on BOT basis (Capacity: 2.19 Million TEUs/Annum, Jetty: T- shape 1100m X 54m, Capital Dredging: 13,56,000 cum, Maintenance dredging - 2,71,200 cu-m/ annum, Land Area required: 84 ha, Break water: Length 1400 m with 20 m height)

2 Providing Railway Line from NH-8A to Tuna Port – 11 KM.

3 Construction of Port Craft Jetty & Shifting of SNA Section at Deendayal Port Trust (114.95 x 12m, Approach 90m x 10 m)

b Name of the Company / Organization M/S Deendayal Port Trust , Gandhidham

c Registered Address Deendayal Port Trust Administrative Office Building Annex Building, First floor, Post Box no. 50 Gandhidham -370201 District- Kutch (Gujarat) d Legal Status of the Company Major Port (Under Major Port Trust Act, 1963) e. Joint Venture (Yes/No) No . If Yes, No (i) No. of JV Partners (Multiple Entries Allowed) Name of the JV Share of the JV Address of the E Mail Id of JV Mo Partner Partner JV Partner partner bile No. of

2 Address for the correspondence

3

a Name of the applicant Mr. Suresh S.P.Patil b Designation (Owner / Partner / CEO) Chief Engineer c Address Deendayal Port Trust Administrative Office Building Annex Building, First floor, Post Box no. 50 Gandhidham -370201 District- Kutch (Gujarat) d Pin code 370201 e e-mail [email protected] f Telephone No. 02836-233192 g. Fax No. 02836-220050 3 Category- of the Project/Activity as per Schedule of EIA Notification, 2006 a Project / Activity 7 (e) [ 1 (a)(i) / l(a)(ii) / 1(b) / 1(c) / 1(d) /1 (e) / 2(a) / 2(b) / 3(a) / 3(b) / 4(a) / 4(b)(i)/4(b) (ii) / 4(c) / 4(d) / 4(e) / 4(f) / 5(a) / 5(b) / 5(c) / 5(d) / 5(e) / 5(f) / 5(g) / 5(h) / 5(i) / 50) / 6(a) / 6(b) / 7(a) / 7(b)/ 7 (c) / 7 (d) / 7 (da) / 7 (e) / 7 (f) / 7 (g) / 7 (h) / 7 (i) / 8 (a) / 8 (b)

b Category (A/B1/B2) Category ‘A’ . If B1 or B2 Reason for application at Central Level / State Iflevel Others (in case of B? projects) c Please Specify d. EAC concerned (for category A Projects only) Infrastructure-II (Coal Mining / Non-coal Mining / Thermal / River Valley & Hydro / Industry- I / Industry-II / Infrastructure-I / Infrastructure- II / Nuclear & Defense / CRZ e New / Expansion / Modernization / One Time New Capacity expansion (only for Coal Mining) / Expansion under Para 7(ii) / Modernization under Para 7(ii) /Change of Product Mix under Para 7(ii) 4 Location of the Project a Plot / Survey / Khasra No. Existing Deendayal Port Trust at Kandla . b Village Village Kandla and Tuna c. Tehsil Gandhidham d District Kutch 4

e State Gujarat f Pin Code 370201 g Bounded Latitudes (North) 1- Development of Container Terminal at Tuna-Tekra on BOT Basis- From Latitude: 22° 53' 36.834"N Longitude: 70° 7' 21.205"E To Latitude:22°51'33.11"N Longitude:70° 6'58.03"E 2- Providing Railway Line from NH-8A to Tuna Port- 11.00 km From From Latitude: 22° 58' 17.42"N To Longitude: 70° 5' 49.36"E h Bounded Longitudes (East) To From Latitude: 22° 54' 36.26"N Longitude: 70° 6' 50.6"E

3. Construction of port craft jetty & shifting of SNA section at Kandla Port

From

Latitude: 23° 0'32.05"N Longitude: 70°13'25.37"E Latitude: 23° 0'26.54"N Longitude: 70°13'26.16"E To Latitude: 23° 0'31.99"N Longitude: 70°13'24.78"E Latitude: 23° 0'26.49"N Longitude: 70°13'25.79"E i Survey of India Topo Sheet No. 41I/4, 41I/8, 41J/1 i Upload Topo Sheet File (Upload PDF only) Enclosed as Annexure-I k Maximum Elevation Above Means Sea Level 3 meter MSL (AMSL) l Upload (kml) File (Upload kml only) Enclosed as Annexure-II .

5

m Distance of Nearest HFL from the project No river present in the study Area. boundary within the study area. n Seismic Zone (Zone: 1/2/3/4/5) 5 . 5 Whether project is executed in multiple States (Yes / No)? : No If Yes a Number of States in which Project will be 1 Executed b Main(e.g. 1,2,3,4,5,6) State of the Project Gujarat c Other State {Multiple Entries Allowed) (If the project to be executed, does not belong to any state, then state category could be selected as 'Other') State District Tehsil Village NA NA NA NA

6 Details of Terms of Reference (ToR) a Whether ToR is granted Granted, Yes . If Yes b Date of issue of ToR / 06/06/2017 Standard ToR c MoEF&CC / SEIAA File No. 10-9/2017-IA.III d Upload ToR letter (PDF only) Enclosed as Annexure-III. 7 .Details of Public Consultation a Whether the Project Exempted . from Public Hearing (Yes/No)?

If yes, Yes, Exempted Reason The Committee exempted the proposal from public hearing as per para 7(ii) of the EIA Notification, 2006 as public hearing was conducted by Gujarat Pollution Control Board on 18.12.2013. b Supporting Document {upload . PDF only) c Whether details of Public No Hearing available (Yes/No)? If No, Not Applicable d Reason there of Not Applicable . Supporting Document {upload If Yes, e Date of Advertisement of Public Hearing Not Applicable . 6

f. Copy of advertisement in Not Applicable English (Upload PDF only) g Whether Public hearing was Not Applicable presided over by an officer of the rank of Additional District Magistrate or above (Yes/No)?

If yes h. Designation of Presiding Officer (District Magistrate / District Collector / i. CopyDeputy of Commissioner duly signed / Proceedings of Public Hearing in English {Upload pdf j- Dateonly) of Public Hearing k. Venue of Public Hearing: Village Tehsil District State 1. Distance of Public Hearing m. No.Venue of people from theattended Proposed n. If the multiple public PIhearings give the conducted details of each PH 8 Detailsas perof Project (e) to (o) Configuration above / Product {Multiple Entries Allowed) a. Whether the project is New Yes If(Yes/No?) yes, All the proposed developments are new, to be implemented in the existing Port.

b. Project Configuration Plant / Equipment / Facility Configuration Rem arks

7

Development of Container (Capacity: 2.19 Terminal at Tuna off Tekra Million TEUs/Annum, on BOT basis Jetty: T-shape 1100m X 54m, Capital Dredging: 13,56,000 cum, Maintenance dredging - 2,71,200 Cu-M/ annum, Land Area req.: 84 ha, Break water: Length of 1400 m, with 20 m of height) Providing Railway Line from 11 Km stretch NH-8A to Tuna Port. Construction of Port Craft (114.95 m x 12m, Jetty & Shifting of SNA Approach 90m x 10 Section at Kandla Port Trust m)

c. Product Product / Activity Quantity Quantity to Unit Mode of Transport / (Capacity /Area) from Transmission of Product

Unit:-(Tons per Annum(TPA), Mega Watt(MW), Hectares(ha), Kilo Liter per Day(KLD), Tons Crushed per Day(TCD), Cubic Meter per Day., Kilometers(Km), Million Liters per Day(MLD) Others) Mode of Transport/Transmission of Product (Road, Rail, Conveyor Belt, Pipe Conveyor, Arial Ropeway, combination of two or three modes, Others) 9 If Expansion / Modernization / One Time Capacity expansion (only for Coal Mining) /Expansion under Clause 7(ii) / Modernization under Clause 7(ii) / Change of Product Mix under Clause 7(ii))) a Details of environmental Enclosed as Annexure IV. clearance granted earlier (I) Date of issue of 19th December 2016. environmental(ii) MoEF&CC clearance / SEIAA File 11-82/2011-IA-III (iii) NumberUpload EC Letter

8

b Details of certified report on Enclosed as Annexure V. compliance of earlier environmental clearance conditions

(I) Details of Regional Office of Regional Office, Western Region, MoEF&CC / Zonal Office of CPCB Bhopal / SPCB / UTPCC from which certified report on compliance of earlier environmental clearance conditions obtained.

(ii) Letter No 6-37/2008(ENV)/311 dated 26-05-2017 (iii) Status of Compliance Compliance report attached as Annexure-V. (iv) Certified report on Enclosed as Annexure V. compliance of earlier environmental clearance conditions (Including Monitoring Report) {Upload PDF only)

(v) Date of site visit 29-12-2016 c Details of Consent to Operate (i) Whether Consent to No operate obtained (Yes/No)? If yes, No

(ii) Upload Copies of all No Consent to operate obtained since inception {Upload pdf only) (iii) Date of issue No

9

(iv) Valid up to No (v) File No. No (vi) Application No. No (vii Upload Copy of Consent No ) to operate valid as on date {Upload pdf only)

d Details of Capacity Expansion No (Multiple Entries Allowed)

Product / Activity Quantity Quantity To Unit Mode of Transport/ (Capacity/Area) From Transmission of Product Unit:-(Tons per Annum(TPA), Mega Watt(MW), Hectares(ha), Kilo Liter per Day(KLD), Tons Crushed per Day(TCD), Cubic Meter per Day, Kilometers(Km), Million Liters per Day(MLD), Others) -Mode of Transport/Transmission of Product (Road, Rail, Conveyor Belt, Pipe Conveyor, Arial Ropeway, combination of two or three modes, Others) e Details of Configuration (Multiple Entries Allowed) . Plant / Equipment / Existin Proposed Final Remark Facility g Configuratio config If any Config n uratio uratio n NA NAn NA afterNA NA

10 Project Cost a Total Cost of the Project at current price level (in Lakhs) 321417 lakhs

b Funds Allocated for Environment Management (Capital) (in Lakhs) 1762.5 lakhs

c Funds Allocated Towards ESC (Entrepreneur Social Responsibility) 2562 lakhs (in Lakhs) d Funds Allocated for Environment Management Plan (EMP) (Recurring per 81.2 lakhs per Annum) (in Lakhs) annum 11 Whether project attracts the General Condition specified in the Schedule No of EIA Notification (Yes/No)? [Provide name of WL/CPA/ESA/Inter-state boundary/International boundary and distance from the project.

If Yes

10

a Protected Area Notified Under the Wild Life(Protection) Act, 1972 b. Critically Polluted Areas as identified by the Central Pollution Control Board c Notified Eco-Sensitive Areas d. Inter-State Boundaries and International Boundaries 12 Whether. projects attract the Specific Condition specified in the Schedule No of EIA Notification (Yes/No)? If Yes a If any Industrial Estate / Complex / Export processing Zones / Special Economic Zones / Biotech Parks / Leather Complex with homogeneous type of industries such as Items 4(d), 4(f), 5(e), 5(f), or those Industrial estates with pre-defined set of activities (not necessarily homogeneous, obtains prior environmental clearance, individual industries including proposed industrial housing within such estates / complexes will not be required to take prior environmental clearance, so long as the Terms and Conditions for the industrial estate/complex are complied with (Such estates/complexes must have a clearly identified management with the legal responsibility of ensuring adherence to the Terms and Conditions of prior environmental clearance, who may be held responsible for violation of the same throughout the life of the complex/estate.

13 Raw Material / Fuel Requirement (Multiple Entries Allowed) a- Details of Raw Material / Fuel Requirement Raw Quantity U Source Mode of Distance of Type of Material / per Annum n (in case of Transport Source Linkage Fuel it Import, from (Linkage/ please Project Site Fuel Supply specify (in Agreement / country Kilo e-auction / and meters) MoU/LOA/ Name of (In case of Captive / the import, Open market port from distance / Others) which from the Raw port from Material / which the No Raw material is required for the implementationFuel is of the project. raw

In case of expansion proposals, total requirement of raw material / fuel shall be given

11

Unit:-(Tons per Annum(TPA), Mega Watt(MW), Hectares(ha), Kilo Litre per Day(KLD), Tons Crushed per Day(TCD), Cubic Meter per Day, Kilometers(Km), Million Liters per Day(MLD), Others) Mode of Transport/Transmission of Product (Road, Rail, Conveyor Belt, Pipe Conveyor, Arial Ropeway, combination of two or three modes, Others)

b. Upload copy of Linkage / Fuel Supply Agreement / e-auction / Memorandum of Understanding / Letter of Allocation / Captive source / others. 14 Baseline Data (Air / Water / Noise / Soil / Ground water table/ Others) a. Period of Base Line Data Collection Duration Duration From (DD/MM/YYYY) March, 2012 01-02-2018 To (DD/MM/YYYY) February, 2013 28-02-2018 b. Season (Summer / Pre-monsoon / (Comprehensive one Winter Post-monsoon / Winter) year baseline data (Non monsoon) collection) c. No. of Ambient Air Quality (AAQ) 8 d. DetailsMonitoring of AAQ Locations Monitoring (Multiple Entries Allowed) Criteria Unit Maximum Min 98 Percentile Prescribed Pollutants Value imu Value Standard m Valu 3 PM10 µg/m 86 56 85.48 100 3 PM2.5 µg/m 48 32 48 60 3 SO2 µg/m 15 6 15 80 NO2 µg/m3 28 14 26 80 CO mg/m3 950 580 0.917 Criteria Pollutants: - (PM10, PM2.5, S02, NOx, Others parameters specific to sector) Unit: - (Micro Gram per Meter Cube, Nano Gram per Meter Cube, Mili Gram per Meter Cube, NA) e. No. of Ground Water Monitoring 1 f. DetailsLocations of Ground (.Multiple Water Entries Monitoring -One sample collected during monitoring Criteria Unit Maximum Minimum 98 Prescribed Pollutants Value Value Percentile Standard pH ------7.64 7.42 7.6356Value 6.5-8.5 Chloride as Cl mg/L 152 128 151.52 250-1000

TDS mg/L 432 368 430.72 500-2000 Conductivity µmhos/ 654 546 651.84 ------cm

12

Total Hardness mg/L 462 368 460.44 200-600 as CaCO3 Criteria Pollutants: - (pH, TSS, TDS, Total Hardness, Chlorides, Fluoride, Heavy Metals, other parameters specific to the sector) - Unit:- (mg/1, na)

g- No. of Surface Water Monitoring Locations 8 h. Details of Surface Water Monitoring (Multiple Entries Allowed) Criteria Pollutants Unit Maximum Minimu 98 Percentile Prescribe Value m Value d Value Standard

pH ---- 8.12 7.64 8.1116 ------DO mg/L 6.4 4.4 6.144 6.0 BOD mg/L 15.0 7.0 14.356 2.0 COD mg/L 45 22 43.18 ----- Calcium mg/L 458 132 453.8 2 Magnesium mg/L 1488 94 1458.88 100 Sodium mg/L 74 48 14588 20 Parameter :- (pH, do, bod, cod, Others para006Deters specific to the sector) - Unit (mg/l, na) i No. of Ambient Noise Monitoring Locations 8 j. Details of Noise Monitoring {Multiple Entries Allowed) - Parameter Unit Ma Minimum 98 Percentile Prescribed Standard xi Value Value m For Day Time (dB(A) 60 49.4 53.80 55 .4 For Night Time (dB(A) 50 40.6 44.59 45 .4 Parameter:-(Leq(Day), Leq (Night)) Unit (A-weighted decibels(dB)(A) k No. of Soil Monitoring Locations (Multiple Entries Allowed) 8 . Parameter Unit Maximum Minimum 98 Percentile Value Value Value pH ---- 8.16 7.26 8.1572 Conductivity (µmhos/cm) 7348 1424 7071.36 CEC (meq/100g) 7.74 5.88 7.698 Nitrogen (mg/100gm) 17.4 14.6 17.316 Phosphorous (mg/100gm) 0.92 0.74 0.9144 Potassium (mg/100gm) 8.9 7.0 8.886

13

Parameter :- (pH, N(Nitrogen), P(Phosphorus), K (Potassium), Electric Conductivity) Unit: (Millisiemens per Centimeter, Milligram per Liter, Percent, Centimeter per Second, Milliequivalents per 100 Gram, Milligram per Kilogram, Parts per Million, Kilogram per hectare, Others) 1 Ground Water Table i Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)): From 1.20 To 53.64 i Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)): i From 0.65 To 98.80 Source-CGWA Report i Whether Ground Water Intersection will be there (Yes / No)? No l If Yes, (i) Upload Copy of Central Ground Water Authority Letter (Upload pdf only) (ii) Letter No. (iii) Date of issue 15 Details of Water Requirement (During Operation) (Multiple Entries Allowed) a Details . Source Quantity in Method of Distance from Mode of Transport KLD water Source withdrawal Surface 5 KLD Others ------Reservoir near (for proposed project) Naramada Bhachau through 18” Canal Pipeline of Gujarat Water Supply and Sewerage Board.

Source: Surface / Ground Water / Sea / Others Mode of Transportation: Pipeline / Canal / Others Method of water withdrawal: Barrage / Weir / Intake well / Jackwell / Tube well / Open well / Others b Upload Copy of Permission from Competent Authority (Upload PDF only) NA . Letter No Date of issue Permitted quantity

14

Whether Desalination is proposed (Yes/ No) If Yes, (i) Desalination capacity (KLD) (ii) Quality of Brine (KLD) (iii) Mode of Disposal of Brine 16 Waste water management during operation Type / Quantity of Treatment Treatment Mode of Quantity of Quantity Source Waste Capacity Method Disposal Treated of Water (Kilo Water Used Discharged Generated Litre per in Recycling Water (Kilo Litre Day) / (Kilo Litre per Day) Reuse (Kilo per Litre per Day) Day) Domestic 1.6 KLD 1.44 KLD 0.22 KLD Sewerage

a. Total Waste Water Generation 1.6 KLD b. Total Discharge water 0.22 KLD c. Total Reused water 1.44 KLD

17 Solid waste Generation Management (Multiple Entries Allowed) Item Quantity Unit Distance from Mode of Mode of per site Transport Disposal annum

Non 2065.57 ------hazardous MT/Year (Garbage) in 2016- 17 Non 1335.29 ------hazardous MT/Year (Garbage) in 2017- 18 18 Air Quality Impact Prediction (Multiple Entries Allowed)

15

Criteria Unit Baseline Minimum Incremental Total GLC Prescribed Pollutants concentration value concentration standard

PM10 µg/m3 86 56 0.322 86.322 100 Container µg/m3 Terminal PM2.5 µg/m3 48 32 0.204 48.204 60 Container µg/m3 Terminal 3 So2 µg/m 15 06 2.44 17.44 80 Container µg/m3 Terminal NOx µg/m3 28 14 4.887 32.887 80 Container µg/m3 Terminal PM10 µg/m3 86 56 4.3 90.3 100 SNA Jetty µg/m3 PM2.5 µg/m3 48 32 2.8 50.8 60 SNA Jetty µg/m3 3 So2 µg/m 15 06 0.329 15.329 80 SNA Jetty µg/m3 NOx µg/m3 28 14 0.658 28.658 80 SNA Jetty µg/m3

16

19 Power Requirement a. Quantity (Kilo Volt Amps (KVA)) 900 MW b. Source PVGCL c. Upload Copy of Agreement (Upload pdf ------d. Standbyonly) Arrangement (Details of DG Sets) ------e. Stack Height (in m) ------20 Land Ownership Pattern (Prior to the project proposal) in Ha a. Forest land ----- b. Private Land ----- c. Government Land 95 Ha the possession of DPT d. Revenue Land ------e. Other Land ------Total land 95 Ha 21 Present Land Use breakup in Ha a. Agriculture Area 6851 b. Waste/Barren Area 5081 c. Grazing / Community Area d. Surface Water bodies 18321 e. Settlements 5171 f. Industrial g- Forest 9761 h. Mangroves 7431 i. Marine area j- Others (Specify) Marshy Land+ Salt Pan 13682 Total 66298 22 Land requirement for various activities (Multiple entries allowed) in Ha Description of Activity / Facility / Plant / Land requirement Remarks

Green belt 31.35 Ha Total 31.35 Ha -Activity / Facility / Plant / Others include: Main Plant, Township, Greenbelt, Ash pond, Quarry area, OB dump Area, Safety zone, Tailing pond, Landfill, Water reservoir, De- salination plant, Area for solid waste management, Built-up area, others 23 Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA- Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs- Eco Sensitive Zones) a. Details of Ecological Sensitivity

17

Details of Ecological Name Distance from Remarks Sensitivity the Project (Km)

No No No No - Details of Ecological Sensitivity-(Critically Polluted Area, WLS, NPA, ESAs,'s, Wildlife Corridors) b. Whether NBWL recommendation is required (Yes/No)? No If yes Upload NBWL recommendation in PDF c. Details of Environmental Sensitivity Details of Name Distance from the Remarks Environmental Project (Km) Sensitivity Hospital Sakaria Hospital 10Km (approx.) ------in NW direction School P N Amersery school 12Km (approx.) ------Serra in NW direction

Details of Environmental Sensitivity:- (Forest, Archaeological Sites, Defense Installations, Others) d. Whether NoC / Permission from the competent authority is required (Yes/No)? If yes NA Upload NoC / Permission from the competent authority in PDF NA 24 Forest Land 1 Whether any Forest Land involved (Yes/No)? No If Yes a. Forests Clearance Status (In-Principle(Stage-I) Approval Obtained / Final NA (Stage-II) Approval Obtained / Forest Clearance Under Process(Stage-I) / Forest Clearance Under Process(Stage-II) / Application for Forest Clearance yet to be Submitted) If In-Principle (Stage-I) Approval Obtained, (i) MoEF&CC file number (ii) Date of In Principle (Stage-I) approval (iii) Area diverted (iv) Upload FC Letter (Upload pdf only and attach it as Annexure-FC letter) If Final (Stage-II) Approval Obtained, (i) MoEF&CC file number (ii) Date of Final Approval 18

(iii) Date of In-Principle Approval (iv) Area diverted (v) Upload FC Letter (Upload pdf only and attach it as Annexure-FC letter) If Forest Clearance under process (Stage-I), (i) MoEF&CC file number (ii) Area applied If Forest Clearance under process (Stage-II), (i) MoEF&CC file number (ii) Area applied b. Legal Status of Forest Land (Reserved j Protected, Private, Village, Others) If Others, Please Specify Others 25 Tree Cutting, if any a. No. of Trees Cut for the Project (if Forestland not involved) NA b. Details of Tree Cutting and Planting of Trees (Upload pdf Only) NA 26 Land Acquisition Status a. Acquired Land No b. Land yet to be acquired No c. Status of Land acquisition if not acquired No 27 Rehabilitation and Resettlement (R&R) a. No. of Villages No b. No. of Households No c. No. of PDFs (Project Displaced Families) No d. No. of PAFs (Project Affected Families) No e. Funds Allocated for R&R No f. Status of R&R (Completed / In-progress / Yet to start) No 28 Whether there is Presence of Schedule-I Species (Yes/No)? No If yes, a. Details of Schedule-I Species b. Whether conservation plan for Schedule-I Species has been prepared NA If(Yes/ Yes, No)? (i) Upload conservation plan (Upload only PDF) (ii) Fund Provision made (iii) Period of Implementation c. Whether conservation plan for Schedule-I Species has been approved NA by (i) Upload copy of approval (Upload PDF Only) (ii) Letter No. (iii) Date of issue 19

(iv) Recommendations if any 29 Whether there is Presence of Water Bodies in Core Area (Yes/No)?

If yes, a. Details of Water Bodies in Core Area Kandla creek & Nakti Creek b. Whether there is Diversion required (Yes/No)? No If yes, c. Details of diversion required NA d. Details of study conducted NIL e. Whether permission has been obtained from competent authority NA (i)(Yes/No)? Upload copy of permission (Upload PDF Only) (ii) Letter No. (iii) Date of issue (iv) Recommendations if any 30 Whether there is Presence of Water Bodies in Buffer Area (Yes/No)? If Yes a. Details of Water Bodies in Buffer Area Khori Creek, Pond near Mithi Rohar, Pond near handrapar, Shinai Lake, Adisar Pond Tirupati Nagar, Sang River near Galpadar.

b. Direction of Water Bodies in Buffer Area (North / South / East / West / North East / North West / South East / South West) c. Distance of Water Bodies in Buffer Area (kilo meters) 31 Manpower Requirement a. Permanent employment during construction ------b. Permanent employment during operation ------c. Temporary employment during construction ------d. Temporary employment during operation 200 persons per e. No. of working days 300day f. Total manpower 200 32 Green Belt in Ha a. In case of new projects 20

i. Total Area of Green Belt 31.35 Ha ii. Percentage of Total Project Area iii. No. of Plants to be Planted iv. Funds Allocated for Plantation 1250000.00 V Upload Green Belt Plan (Upload PDF Only) b. In case of expansion / modernization / change in product mix etc. No

i. Description Existing Proposed Total Total Area of Green Belt Percentage of Total Project Area No. of Plants Funds Allocated ii. Upload Green Belt Plan (Upload PDF Only) 33 Project Benefit (Multiple entry allowed) Type of Project Benefits Details of Project Benefit 2016-17 Deendayal Port Trust shall take up Estimated some community welfare activities S. Name of Scheme Cost, INR in under Corporate Social Responsibility N Lakhs and also improve the social infrastructures like education and 1 RCC Community Hall at Harshidhi 19.00 health care system etc. Mata Temple, Veea village, AnjarTaluka 2 Fabricated Community Hall at 21.00 Sanghad village, AnjarTaluka 3 CSR Works for Shri 8.00 MaheshwariMeghvadSamaj, Gandhidham at Grave Yard, Behind Redison Hotel. 4 CSR works for 30.50 ShirDhanrajMatiyadevMuktiDham, Sector-14, Rotary Nagar, Gandhidham. 5 CSR works for NirvasitHarijan Co- 41.00 operative Housing Society, Gandhidham. Health Cum Education Centre. 6 CSR works for Shri Rotary Nagar 2.80 Primary school, Gandhidham. 7 CSR works at NU -4 , NU-10(B) 18.00 Sapnanagar& Saktinagar, Golden Jublee Park, at Gandhidham.

Total 140.30

21

Recently CSR Activities approved by Board for the year 2017-18 is as under: Details of Project Benefit 2017-18

S.No Name of Scheme Appx Cost (In lakhs)

CSR works at Shri Ganesh Nagar Govt 38.30 1 High School, Gandhidham CSR works for MOLANA AZAD Primary 7.00 2 School, New Kandla.

Grant Financial contribution for facility of 15.00 3 Army cantonment for 50 air coolers at Kutch Border Area. CSR works at Tuna &Vandi villages Approximate Estimated Cost (providing drainage lines under Swachh Rs.99.50 Lakhs Bharat Abhiyan) 40% of the estimated cost (i.eRs 4 39.80 Lakhs ) to be contribute by DPT for the CSR and remaining shall be contribute by M/s AKBTPL, etc. CSR works for S.H.N Academy English 40.00 5 School ( Mangd by Indian Institute of

Sindhology –Bharati Sindhu Vidyapeeth),

Adipur Construction of Internal Road at 15 .00 6 Bhaktinagar Society, Kidana Total 155.10

(Project benefits shall include environmental, social and others)

34 Whether the Project / Activity attract the provisions of CRZ (Yes/No)? If yes, 1 Project Details As above

22

a. CRZ Classification: (CRZ I (A), CRZ 1(B), CRZ III, CRZ IV CRZ 1(B), CRZ II, CRZ III, CRZ IV (A), CRZ IV(B)) b. Location type: (Non-Eroding Non-Eroding Coast Coast, Low and Medium Eroding Coast, High Eroding Coast)

c. Details of Mangroves Land No Mangroves falls in project Area. d. AreaInvolved, of Mangroves if Any Land NA e. EIA(hectare) (Terrestr ial) Studies: Enclosed as Annexure-VI If(Carried Carried Out, Out, Not Carried Out) 1) Summary Details of EIA Brief Summary enclosed as Annexure-VII. (Terrestrial) Studies 2) Upload Recommendation Ref No. ENV-10-2015-248-E(T cell), dated made in EIAs (Upload pdf 29.06.2016 only) 3) Period of Study from (EIA March 2012- February 2013 Terrestrial) 4) Period of Study to (EIA Terrestrial) If Not Carried out Give Reason f. EIA (Marine) Studies: (Carried Out, Not Carried Out) If carried out 1) Summary Details of EIA Enclosed as Annexure VIII 2) Upload(Marine) Studies Recommendation Certificate of Marine EIA and EMP is made in EIAs Enclosed as Annexure IX. 3) Period of Study from (EIA December 2010 (post monsoon) Marine) 4) Period of Study to (EIA April-May 2011 (pre monsoon) Marine) If Not Carried out, Give Reason

23

g- Disaster Management Enclosed as Annexure-X prepared by oil Plan/National Oil Spill Disaster spill contingency plan of DPT. Contingency Plan (if Applicable) 2. Description of the Project Under Consideration

a. Type of Project: (Resort/Buildings/civic amenities, Coastal Roads/Roads on Stilt, Pipelines from Thermal power Blow Down, Marine Disposal of Treated Effluent, Facility for Storage of Goods/Chemicals, Offshore structures, Desalination Plant, Mining of Rare Earth/Atomic Minerals, Sewage Treatment Plants, Lighthouse, Wind Mills, Others). If Resort/Buildings/civic 1)amenities, Agency Name for Preparing CRZ Maps 2) Total Area/Built-up Area (hectare) 3) Height of Structure 4) FSI Ratio 5) The governing Town Planning Rules/Regulations 6) Details of Provision of Car Parking Area If Coastal Roads/Roads on stilt, i) Agency Name for Preparing CRZ Maps 2) Area of Land Reclamation 3) Estimated Quantity of Muck/Earth for Reclamation 4) Carrying Capacity of Traffic If Pipelines from Thermal Power Blow Down, 1) Agency Name for Preparing CRZ Maps 2) Length of Pipeline 3) Length Traversing CRZ Area 4) Depth of Excavation 5) Width of Excavation 24

6) Length of Pipeline from Seashore to Deep Sea 7) Depth of Outfall Point from Surface of Sea Water 8) Temperature of effluent above Ambient at Disposal Point If Marine Disposal of Treated Effluent, 1) Agency Name for Preparing CRZ Maps 2) Location of Intake/Outfall 3) Depth of Outfall Point 4) Length of Pipeline 5) Length Traversing CRZ Area 6) Depth of Excavation 7) Width of Excavation 8) Length of Pipeline from Seashore to Deep Sea/Creek 9) Depth of Outfall Point from Surface of Sea Water 10 Depth of Water at Disposal Point 11) Type of Disposal If) Facility for Storage of Goods/Chemicals, 1) Agency Name for Preparing CRZ Maps 2) Name and Type of Chemical 3) End use of the Chemical 4) No. of Tanks for Storage 5) Capacity of tanks If offshore structures, i) Agency Name for Preparing CRZ Maps Institute of remote sensing Anna 2) Exploration or Development Development of Container Terminal at Tuna off Tekra on BOT basis: Capacity: 2.19 Million TEUs/Annum, Jetty: T-shape 1100m X 54m, Capital Dredging: 13,56,000 cum, Maintenance dredging - 2,71,200 cu- m/ annum, Land Area req.: 84 ha, Break water: Length of 1400 m, with 20 m of height.

3) Depth of Sea Bed 13 m 4) No. of Rigs/Platform 5) Details of Group Gathering Stations If Desalination Plant, 1) Agency Name for Preparing CRZ Maps 2) Capacity of Desalination 3) Total Brine Generation 25

4) Temperature of Effluent above 5) Ambient Salinityat Disposal Point 6) Disposal Point If Mining of Rare Earth/Atomic Minerals, 1) Agency Name for Preparing CRZ Maps 2) Capacity of Mining 3) Volume/Area to be mined 4) Type of Mineral to be Extracted 5) End use of the Mineral If Sewage Treatment Plants, 1) Agency Name for Preparing CRZ Maps 2) Capacity 3) Total Area of Construction 4) Compliance of effluent parameters as laid down by 5) Whether discharge is in sea water/creek? DistanceIf yes, of Marine Outfall Point from Shore/from the tidal river Depthbank of Outfall Point from Sea Water DepthSurface of Sea at Outfall Point If Lighthouse, 1) Agency Name for Preparing CRZ Maps 2) Total Area of Construction 3) Height of the Structure • If Wind Mills, 1) Agency Name for Preparing CRZ Maps 2) Capacity (MW) 3) Transmission Lines: (Overhead, 4) DiameteUnderground)r of Windmill 5) Length of Blade 6) Speed of Rotation 7) Height of the Structure If Others, 1) Agency Name for Preparing CRZ Maps Institute of remote sensing Anna University.

2) Please Specify with salient features ------3) Upload relevant Document26 (Upload CRZ Map Enclosed as Annexure-XI. PDF only)

3. Distance of Project (In Meters) from LTL/HTL to Approx 100 meter from the project be Stated area.

a. Clause of CRZ Notification Under which the CRZ Notification 2011 Project is a b. WhetherPermissible/Regulated CRZ Map Indicating Activity HTL, LTL Yes Demarcation in 1:4000 Scales If Yes, 1) Distance of Project (in meters) from Approx 100 meter from the project HTL to be Stated area.

2) Upload Maps{kml File) KML Enclosed as Annexure-II. 3) Distance of Project(in meters) from ------4) UploadLTL to be Maps Stated {kml File) Map Enclosed as Annexure-XI. c. Whether Project Layout Superimposed on ------CRZ Map 1:4000 Scales?: (Yes/No)If Yes, 1) Upload Maps {kml File) KML Enclosed as Annexure-II. d. Whether CRZ Map 1:25000 Covering 7 km Radius Around Project Site Prepared?If Yes, (Yes/No) 1) Upload Maps {kml File) CRZ Map Enclosed as Annexure-XI.

e. Whether CRZ Map Indicating CRZ-I,II,III and Yes IV Including Other IfNotified Yes, ESAs Prepared?: (Yes/No) 1) Upload Maps {kml File) f. NOC from State Pollution Control Boards Yes Obtained: (Yes/No) If Yes 1) Upload Copy of NOC {Upload pdf only) g- Details| of Rain Water Harvesting System Deendayal Port Trust is already having the rain water harvesting pond in Gopalpuri colony. However, there is no rain water harvesting system proposed in the proposed integrated facilities as there is scanty rain in the Kutch area.

4. Recommendation of State Coastal Zone Yes, on dated 29.06.2016 Management Authority 27

a. Upload Copy of CZMA (Upload PDF Only) Enclosed as Annexure XII. b. State the Conditions Imposed Conditions mention in Map Enclosed as Annexure-XII.

c. Social and Environmental Issues and Mentioned in the Chapter-4, Heading Mitigations Measures Suggested 4.7, subheading 4.7.1, 4.7.2 & Summary Including but not Limited to R&R, Water, of the mitigation measures during Air, Hazardous Wastes, construction of proposed projects are Ecological aspects, etc. (Brief Details to be tabulated as Table-59 of the EIA Provided) Report. 35 Sector Specific Details I Whether the proposal is mining of minerals (coal / non-coal) project (Yes/No)? NA If yes, 1 No. of Mineral to be Mined (Multiple Entries Allowed) Minerals To be Mined Major or Minor Mineral

2 Mine Capacity in ROM (Run of Mine) 3 Upload 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals (Upload pdf Only) 4 Mining Plan a. Approval Letter No. b. Date of Approval c. Upload Approved Letter (Upload pdf only) d. Approved by State Mines & Geology Department / Indian Bureau of Mines / Ministry of Coal / Ministry of Mines / State Government /Atomic Mineral Directorate / Others) e. If Others, Please specify f. Approved Mining Lease Area g- Approved Capacity 5 Technical Details NA a. Total Geological Reserves (Million Ton) b. Mineable Reserves (Million Ton) c. Extractable Reserves (Million Ton) d. Percent of Extraction (%) e. Grade of Coal /Ore /Mineral f. Stripping Ratio g. Category of Gaseousness (Only for Coal Mining, Others may write Not applicable) 28

h. Average Gradient(Degree) i. Maximum Thickness of Seams(meters) (Only for Coal Mining, Others may write Not applicable) j- Mining Method (Opencast / Underground / Mixed (Opencast + Underground) / Adit k. Life of Mine (Years) 6 Details of beneficiation (including crushing / screening/others) NA a. Whether it is proposed to install crusher within the mining lease area (Yes/No)?

If yes, b. No. of crushers c. Details of crusher (Multiple entries allowed) Crusher ID Capacity (in TPH) Remarks

d. Whether it is proposed to install beneficiation plant / Coal washery within the mining lease area (Yes/No)? If yes, e. Beneficiation / washing Technology f. Capacity 7 Details of Seams if applicable NA a. No. of seams b. Thickness of seams to be worked on c. Maximum Thickness of Seams(meters) (if not Applicable, may Write NA) 8 Details of Mining Lease NA a. Details of Mining Lease b. Upload Letter of Intent (Upload pdf only) c. Date of Execution of Mining Lease with Reference Number d. Validity of Mining Lease e. Upload Copy of Executed Lease deed valid as on Date (Upload pdf only) f. Earlier Renewals (Multiple Entries Allowed) Uploaded Copy of Earlier Lease Date of Renewal

9 OB (Over Burden) Management (Only if Mining Method: Opencast) NA

a. Details of External Dumps i) No. of OB Dumps 29

ii) Total Area (in Hectare) iii) Height (in meter) iv) Quantity (in Million Cubic meter) v) No. of year back fill up b. Details of Internal Dump i) No. of Internal Dumps ii) Total Area (in Hectare) iii) Height (in meter) iv) Quantity (in Million Cubic meter) 10 Details of Topsoil Management NA a. Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic meter) b. Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic meter) c. Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic meter) 11 Detail of Final Mine Void (Only if Mining Method: Opencast) NA a. Area (in Hectare) b. Depth (in meter) c. Volume (in Million Cubic meter) 12 Details of Quarry (Only if Mining Method: Opencast) NA a. Final Void of (hectare) b. At a Depth of (meter which is proposed to be converted into a Water Body.) c. Total Quarry Area (ha) 13 Details of Transportation NA a. In Pit/Underground to Surface b. Surface to Siding/Loading c. Transportation / Conveyor Details 14 Details of Land Usage (Pre-Mining) NA Land Use Within ML Outside ML Total Area Area (Hectare) (Hectare) Agriculture Land Forest Land Waste Land Grazing Land Surface Water Bodies Settlements Others(Specify) 30

15 Details of Transportation NA a. In Pit/Underground to Surface b. Surface to Siding/Loading c. Transportation / Conveyor Details 16 Details of Land Usage (Pre-Mining) NA Land Use Within ML Outside ML Total Area Area (Hectare) Agriculture Land Forest Land Waste Land Grazing Land Surface Water Bodies Settlements Others(Specify) Others 17 Details of Land Usage (Post-Mining) NA Land Use Plantation Water Body Public Use Others Excavation / Top Soil Storage Externa] OB Internal OB dumps Roads Built Up Area (Colony/Office) Green Belt Virgin Area Other Total 18 Details of Reclamation (Only if Mining Method: Opencast) Total Afforestation NA Plan shall be Implemented Covering of Mining. This will include:

a. External OB Dump (in hectare) b. Internal Dump (in hectare) c. Quarry (in hectare) d. Safety Zone (in hectare) e. Final Void of (hectare) f. At a Depth of (meter which is proposed to be converted into a Water Body.) g- Density of Tree Plantation per ha (in no.) h. Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located outside the Lease etc.)31

i. Total afforestation plant (in hectare) 19 Status of Progressive Mining Closure Plan (For Expansion Projects only) NA a. Implementation of Various Activities as per Approved Progressive NA Mine Closure Plan (in Bar Chart) (pdl) {Uploadpdf only) b. Any Deviation from the Approved Progressive Mine Closure Plan c. Total Area Excavated (in hectare) d. Total Area Backfilled after Excavation (in hectare) e. Total Area Reclaimed (in hectare) 20 Actual Coal/Ore Production vis-a-vis sanctioned capacity Since inception {Multiple Entries Allowed)

Financial Sanctioned Sanctioned Sanctioned Actual Excess Productio Year Capacity as per capacity as capacity as Production Beyond the EC EC (MTPA) per CTO per CTO / Mining Pla approved Sanctioned Capaci Mining Plan (MTPA)

II Whether proposal is for Thermal Project (including captive power plant and NA NA Waste Heat Recovery Plant) (Yes/No)? If yes, 1 Specifications of the Plant a. Technology proposed (Supercritical, Sub-Critical, CFBC, AFBC, PFBC, IGCC, Incineration, Pyrolysis, Gasification, Bio-methanation, Others) b. Plant Load Factor (%) c. Station Heat Rate (Kcal/Kwh) d. Steam Rate/Flow Rate e. Boiler Temperature f. Boiler Pressure g- Type of Stack (Single flue / Bi-flue / Tri-Flue) h. No. of Stacks Stack ID Stack Stack Exit velocity Exit temperature height Diameter of of stack gas (°C) (m) at exit (m) stack gas

2 Details of fuel linkage (please specify if multiple linkages are involved)

a. Type of linkage (Linkage / Fuel Supply Agreement / e-auction / MoU /LOA / Captive / Open market / Others) b. Quantity of linkage granted 32

c. Date of Linkage d. Duration of linkage 3. Details of Transportation of fuel Details / Mode Distance Quantity (TPA) (km)

Rail Road Pipeline Conveyor Other mode (Please specify) 4. Details of Fuel Characteristics NA a. Gross Calorific Value (Kcal/Kg) b. Ash content (%) c. Sulphur Content (%) d. Moisture (%) e. Mercury (mg/kg) f. Fixed Carbon (%) g- Volatile Matter (%) 5. Details of Cooling system NA a. Type of cooling system: Air cooled/Water cooled b. Type of draft: Natural draft/Forced draft c. Type of air circulation: Parallel flow/ Counter flow d. Cycles of Cooling (COC): e. Water requirement for cooling (m3/day): f. Boiler blow down temperature: III Whether proposal is for River Valley & Hydroelectric Project (Yes/No)? No If Yes, 1. Sub Sector: (Multipurpose Project / Hydroelectric Project / Irrigation 2. Nameproject) of the River : 3. Whether Cumulative Impact Assessment and Carrying Capacity Study of River Basin Carried Out? (Yes/No): If Yes : a. Status of Cumulative Impact Assessment and Carrying Capacity Study of River Basin: (Recommended / Not Recommended,) If Recommended b. Details of Cumulative Impact Assessment and Carrying Capacity Study ; of River Basin c. Upload Relevant Document {Upload pdf only) 33

4. Type of Project: (Construction of Dam Barrage / Run of the River / Lift NA Irrigation Scheme) 5. Dam Height (meter) if applicable 6. Dam Length (meter) if applicable 7. Total Submergence Area (hectare) 8. Details of Gross Command Area (GCA) (hectare) 9. Details of Irrigable Command Area (ICA) (hectare) 10 Details of Culturable Command Area (CCA) (hectare) 11. Total Command Area (hectare) 12. Powerhouse Installed Capacity . a. Type of Powerhouse: (Underground / Surface) b. Capacity (megawatts) c. No. of Tunnels d. No. of Units e. Bank of River: (Left /Right / Both) 13 Generation of Electricity Annually NA . a. Quantity of Generation of Electricity Annually (in Giga Watt Hours (GWh)) b. Water availability at various percentages Percentage Water Dependable Remarks availability year (Cusecs) At 50% At 75% At 90% c. Machine Availability (%) d. Cost of Electricity Generation (in INR) e. Internal Rate of Return (%) f. Year of achievement of Internal Rate of Return 14 Catchment Area Treatment Plan (Upload PDF) NA 15. Muck Management Plan NA . a. Upload Muck Management Plan in PDF b. Total Excavation Muck (Cubic Meter) c. Utilized for Construction (Cubic Meter) d. No. of Muck Disposal sites e. Total Muck Disposal Area (Ha) 16 Fishery Development and Management Plan NA . a. Upload Fishery Development and Management Plan in PDF b. No. of Fingerlings c. No. of Fish Species 34

d. Name of the umbrella Fish Species (Scientific Name) 17 Status of Environmental Flow NA . Season Average Inflow (in Million Percent of Flow Cubic Meter) Lean Non-Lean Monsoon Non-Monsoon 18 Free Flow Stretch (km) NA 19. Approval of Central Water NA . a.Commission Approval Reference No. b. Date of Approval c. Upload Copy of Approval 20 Approval{Uplo of adCentral pdf only) Electricity NA . a.Authority Approval Reference No. b. Date of Approval c. Upload Copy of Approval 21 Details{Upload of Coffer pdf Dam only) (upstream) if NA . a.applicable Quantity of the material (m3) b. Length of the dam (m) c. Quantity of muck to be used d. Quantity(m3) of borrow material to e. Decommissioningbe used (m3) plan (upload 22 Detailsin of PDF) Coffer Dam (downstream) NA . a.if applicableQuantity of the material (m3) b. Length of the dam (m) c. Quantity of muck to be used d. Quantity(m3) of borrow material to e. Decommissioningbe used (m3) plan (upload IV Whether thein proposal PDF) is Infrastructure Yes projects (Yes/No) If yes? 1 Details of Building Construction Not Applicable a. Maximum Height of the b. TotalBuilding No. (Meters) of Flats to be Build c. No. of Buildings d. Total plot area (sqm)

e. Total built up area (sqm) 35

2 Foreshore Facilities and/or Marine Disposal a. Whether Project Involves Foreshore Activities and/or marine Disposal (Yes/No)? If Yes, Yes b. Upload Shoreline Study The Maps enclosed in the Chapter-3 (Figure-30, (Upload pdf only) 31 & 32) of EIA Report. c. Type of Cargo Dry Cargo d. Quantity of Cargo ------e. Control Measures of Cargo ------f. Dust Control Measures Water Sprinklers g- Quantum h. Quantity of Dredging (Cubic i. Typemeter of per Dredging day) (Capital, Capital- 13,56,600 m3 Maintenance) Maintenance-2,71,200 cu-m/annum j- Disposal of Dredge Material Dumping site k. Details of Outfall Diffusers NA m. No. of Dilution Expected NA n. Distance at which the outlet NA 0. Detailswill Reach of Monitoring Ambient Parameters at outfall NA P- Copy of NoC from PCB in case NA 3 Rain Waterof Marine Harvesting Disposal (Upload pdf Deendayal Port Trust is already having the rain water harvesting pond in Gopalpuri colony. However, there is no rain water harvesting system proposed in the proposed integrated facilities as there is scanty rain in the Kutch area.

a. No. of Storage b. Capacity c. No. of Recharge Pits d. Capacity 4 Parking

36

a. Details of 4-Wheeler/ 2- Wheeler Parking

5. Energy Saving Measures Energy conservation measures will be implemented to ensure that the use of non-renewable resources is minimized. A key component of achieving energy conservation would be the development of an Energy Management Action Plan. This plan should be included as part of the Construction and Operational EMPs. The Energy Management Action Plan will be consistent with the energy conservation measures during both construction and operation phase. a. Source/Mode Renewable energy sources such as: 1- Off the light in day time. 2- Regular maintenance of all powered equipment. 3- Using energy efficient electrical appliances. 4- Installing lighting control devices where appropriate and linking to photoelectric dimming. 5- Switching off site office equipment when not in use. 6- Use the LED Bulbs and LED Halogens. b. Percentage ---- 7- c. Quantity ---- 6. Other Details No a. Details of impact on Water Bodies and Drainage patters of b. Detailscatchment of Traffic area, if Density any Impact Assessment and Modelling Study (Upload pdf Only) c. In case of Underground Tunnel projects below the Forest Land -Subsidence Impact Study report {Upload pdf Only) 7. Type of Industries to be established NA with Industrial Estate as per their category A/B

37

SI. No Type of Industry No. of Units Category A/B

8. Length of the alignment in case of highway projects NA 9. Details Bridges/ROB/Interchanges, Flyovers, Vehicle Underpass and Pedestrian Underpass (in case of Highway Projects) a. Total No. of Bridges b. Total No. of ROB c. Total No. of Interchanges d. Total No. of Flyovers e. Total No. of Vehicle Underpass f. Total No of Pedestrian Underpass g- Details of other utilities rail and road corridors 36 Details of Court Cases if any No a. Whether there is any Court Cases pending against the project and/or land in No which the project is proposed to be set up (Yes/No)? If Yes, b. Name of the Court (Districts Court / High Court / NGT / Tribunals / Supreme Court of India) If name of Court: (Districts Court, High Court, NGT, Tribunals) c. Name of the Sub-court d. Case No. e. Orders / Directions of the court, if any and its relevance with the proposed ^project f. Case Details g- Upload Court Order if any (Uploadpdf Only) 37 Details of direction issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act a. Whether any direction issued under Environment No (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act (Yes/No)?

If yes,

38

b. Details of directions issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act

c. Upload copy of directions issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act d. Compliance status of the directions 38 Details of EIA Consultant a. Have you hired Consultant for preparing document Yes (Yes/No)? If No, (i) Reason for not engaging the Consultant If Yes, (i) Accreditation No. NABET/EIA/1619/RA/0063 (ii) Name of the EIA Consultant Mantec Consultants Pvt Ltd, Noida

(iii) Address D -36 Sec 6, Noida-201301 (iv) Mobile No. 9871095806 (v) Landline No. 0120-4215000 (vi) E-mail Id [email protected] (vii) Category of Accreditation (Eligible for A Category A / Eligible for Category B) (viii) Sector of Accreditation 14 (ix) Validity of Accreditation 29.09.2019 (x) Upload Certificate of Accreditation certified by Enclosed as Annexure XIII. QCI/NABET (Upload PDF Only) 39 Documents to be attached

I If Project Type is New / Expansion / Modernization / one-time capacity expansion for coal mining: a. Upload Copy of EIA/EMP Report Not Applicable b. Upload Copy of Risk Assessment Report Not Applicable c. Upload Copy of Feasibility Report/ Detailed Project Not Applicable Report (DPR) /Detailed Engineering Report /Detailed Conceptual Plan / Approved Mining Plan (in case of Mining proposals) (Upload pdf only) 39

d. Upload Copy of Final Layout Plan (Upload pdf only) Not Applicable

e. Upload Cover Letter (Upload pdf only and attach it as Not Applicable Annexure-document of Cover letter)

f. Upload a copy of documents in support of the Not Applicable competence/authority of the person making this application to make application on behalf of the User Agency (Upload pdf only and attach it as Annexure- authorization).

g- Upload copy of District Survey Report (for mining of Not Applicable minor minerals only) Upload copy of Replenishment Study Report & Baseline Not Applicable Survey data (for river sand mining proposals only) g- Upload Additional File, if any (Upload pdf only) Not Applicable

II If Project Type is other than New / Expansion Not Applicable /Modernization /one-time capacity expansion for coal mining: - a. Upload Copy of Feasibility Report / Detailed Project Not Applicable Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan {Upload pdf only) b. Upload Copy of Final Layout Plan {Upload pdf only) Not Applicable c. Upload Cover Letter (Upload pdf only and attach it as Not Applicable Annexure-document of Cover letter)

d. Upload a copy of documents in support of the Not Applicable competence/authority of the person making this application to make application on behalf of the User Agency (Upload pdf only and attach it as Annexure- authorization). e. Upload Additional File, if any (Upload pdf only) Not Applicable f. Upload Updated Form 1 (Upload pdf only) Not Applicable 40 Undertaking a. I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity / construction / expansion has since been taken up. 40

b. Name Mr. Suresh S.P. Patil c. Designation Chief Engineer d. Company Deendayal Port Trust e. Address Deendayal Port Trust at Kandla Administrative Office Building Annex Building, First floor, Post Box no. 50 Gandhidham -370201 Kutch District (Gujarat).

Date:

Place:

Chief Engineer Deendayal Port Trust at Kandla

41

Due to heavy size of all Documents, we cannot upload more than 20 MB on MoEF&CC Portal so we will submit the Hard Copy of Detailed Annexure.