Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII 1 1 København H (excl.) Track renewal Track, switches, and 18 days July-August 6/7-24/7 Total closure of Banedanmark High – Høje Tåstrup Kh-Htå drainage works lines. Operations (incl.) to Høje Tåstrup from west are possible 2 1 Glostrup (excl.) – Track renewal Track and drainage 7 weeks May-July 2/5-25/6 Right track Banedanmark Major Høje Tåstrup (excl.) Kh-Htå works possessed

3 1 Høje Tåstrup (incl.) Track renewal Track and drainage 7 weeks August- 8/8-2/10 Right track Banedanmark Major – Glostrup (excl.) Kh-Htå works September possessed

1 Glostrup (incl.) – The Capital's Light Bridge positioning 1 weekend Easter 15-18. April All tracks Hovedstadens Høje Tåstrup (excl.) Rail at Glostrup possessed. No Letbane (3. operations Kh – party) Htå 1 Ringsted (excl.) – Reconstruction of Track and bridge All holiday 9/4 – 18/4 Single track Banedanmark Roskilde (excl.) tracks works weekends during 13/5 -15/5 possession. the spring 26/5 – 29/5 One track 4/6 – 6/6 possessed at a time on the line Ro-Rg. 4 1 Ringsted (excl.) – Reconstruction of Track and bridge 3 weeks July-August 17/7 -7/8 3 weeks total Banedanmark High Roskilde (excl.) tracks works closure of lines

5 1 Ringsted (excl.) – Reconstruction of Track and bridge 9 weeks July-September 5/7 - 16/7 11 weeks single Banedanmark High Roskilde (excl.) tracks works 8/8 - 2/10 track possession. One track possessed at a time on the line Ro-Rg. 1 Slagelse (excl.) – NFSP0541 Track and bridge All holiday 9/4 – 10/4 Single track Banedanmark XXXXXX Korsør (excl.) works Slagelse - weekends during 14/4 –18/4 possession. Korsør the spring 13/5 -15/5 One track 26/5 – 29/5 possessed at a 4/6 – 6/6 time on the line Sg-Kø. 6 1 Slagelse (excl.) – NFSP0541 Track and bridge 3 weeks June-July 27/6 – 17/7 Single track Banedanmark High Korsør (excl.) works Slagelse - possession. Korsør One track possessed at a time on the line Sg-Kø. Parts of track 1 in Korsør are possessed.

7 1 Slagelse (excl.) – NFSP0541 Track and bridge 8 days + 8 hours July 17/7 – 25/7 Total closure of Banedanmark High Korsør (incl.) works Slagelse - lines. Operations Korsør to Korsør from west is possible. 8 1 Slagelse (excl.) – NFSP0541 Track and bridge 2 weeks July-August 25/7 – 7/8 Single track Banedanmark High Korsør (excl.) works Slagelse - possession. Korsør One track possessed at a 8

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII time on the line Sg-Kø. Parts of track 1 in Korsør are possessed.

11 1 Snoghøj (incl.) – EP Modernisation Establishment of a 1x 30 hours per Q1-Q2 Not settled Single track Banedanmark Medium Fredericia (incl.) NA0022 new neutral section track operations + No traction current available 12 1 Snoghøj (incl.) – EP Modernisation Establishment of a 1x 30 hours per Q1-Q2 2022 Not settled Single track Banedanmark Medium Taulov (incl.) NA0022 new neutral section track operations + No traction current available 13 2 Orehoved (incl.) Signalling Test / Putting into 2 x 56 hours Q1, Q2 Not settled Total closure of Banedanmark Medium Programme service of track 1 lines. Fjernbane Roll Out 7 14 2 Nykøbing F Vest RFB Soft ground work, All year round All year round 1/1-31/12 Total closure of Banedanmark Major (excl.) – Rødby preparations for lines. Færge (incl.) double track

15 2 Nykøbing F Vest RFB Placing of rolling All year round All year round 1/1-31/12 Total closure of Banedanmark Major (incl.), stock, etc. Shunting lines. Lokaltog can track 1 (I-signal D to and from the operate to to U-signal B) work track Nykøbing F St.

16 4 Køge N (excl.) - Platform extension Switch works before 8 days Spring 10/4-18/4 Total closure of Banedanmark High Næstved (excl.) at Haslev st. extension of island lines. platform 17 4 Køge N (excl.)- Platform extension Mounting of 18 m 4 weeks Summer 2/7-31/7 Possession of track Banedanmark High Næstved (excl.) at Haslev st. extra platform 2 /island platform. southwards as an Track 1 can be extension of the operated. island platform 5 Roskilde (excl.) - Reconstruction of Drainage work, 3 weekends July – August 17/7 – 7/8 Single track Banedanmark XXXXX Lejre (excl.) tracks Roskilde - tracks in total possession. Ringsted 18 5 Holbæk (excl.) - Roskilde - Track works 4 weeks April-May 08/4-06/5 Total closure of Banedanmark Major Kalundborg (Incl.) Kalundborg lines.

19 5 Jyderup (excl.)– Track works Track works in Jy – 16 days March-November 1/3-1/11 Total closure of Banedanmark High Kalundborg (excl.) Se, in Væ, and in Kb lines.

20 6 Vigerslev (excl.)- Signalling Static test 2 x 56 hours Q1 Not yet settled Total closure of Banedanmark Medium Kjn -Ringsted Programme lines. (excl.) Fjernbane Roll Out 1 21 6 Vigerslev (excl.)- Signalling Static test 3 x 56 hours Q2 Not yet settled Total closure of Banedanmark Medium Kjn-Ringsted (excl.) Programme lines. Fjernbane Roll Out 1 22 6 Vigerslev (excl.) – Programme Test runs 6 x 56 hours Q3, Q4 Not yet settled Total closure of Banedanmark Medium Kjn – Fjernbane Roll Out 1 lines. Ringsted (excl.) 9

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII

København G (excl.) – Kjn – Ringsted (excl.)

Lille Skensved (excl.) – Kjn (excl.) 23 6 Vigerslev (excl.) - Signalling Putting into service 1 x 56 hours Q4 Not yet settled Total closure of Banedanmark Medium Kjn-Ringsted (excl.) Programme lines Fjernbane Roll Out 1 24 11 Københavns Maintenance Maintenance of the 24 hours March 19/3 – 20/3 Total closure of Øresundsbroen Medium Lufthavn Kastrup Oeresund bridge lines (excl.) – Peberholm (incl.) 25 11 Københavns Maintenance Maintenance of the 24 hours November 5/11 – 6/11 Total closure of Øresundsbroen Medium Lufthavn Kastrup Oeresund bridge lines (excl.) – Peberholm (incl.) 26 11 Kastrup station Ny Kastrup Lufthavn Stage: 1a: Catenary 9 days July 16/07 – 25/07 Possession of Sund og Bælt High (incl.) Station (NKLS) works, i.a mounting tracks 11+12, all of new control trains through switch track 1+2 and SORF from 2. main track Phm- Cph 27 21 Odense (excl.) - Signalling Test operations 7 x 56 hours Q1, Q2 Not yet settled Total closure of Banedanmark Medium Svendborg (incl.) Programme lines Fjernbane Roll Out10 28 21 Odense (excl.) - Signalling Test operations 5 x 56 hours Q3 Not yet settled Total closure of Banedanmark Medium Svendborg (incl.) Programme lines Fjernbane Roll Out10 29 23 Fredericia (incl.) - Elevator Establishment of lift 23 days March- Week 22 – 25 Tracks 2 and 3 Banedanmark High Fredericia (incl.) NPTG0016 at track 2 September possessed

30 23 Fredericia (incl.)- Preparatory work New bridge, new 7 x weekend 1., 2. and 3. Week: Single track Banedanmark Medium Børkop (incl.) – FA-AR place possession quarter 2022 3,14,17,18,19, operations Vejle (incl.) Bridge 20520.8 20,35 Fredericia – Børkop - Vejle 31 23 Fredericia (incl.)- Preparatory work New bridge, new LA40 January- 3 weeks 16/1- La 40 max 300 m Banedanmark High Børkop (incl.) – FA-AR place February 7/2 at bridge 20520.8 Vejle (incl.) Bridge 20520.8 in both main tracks

23 Børkop (excl.) – Preparatory work Bridge lifting 1 possession 1. quarter 22022 11/2-13/2 Possession of Banedanmark XXXXXX Vejle (incl.) FA-AR Bridge 20568 (34 hours) tracks 2 4 and 40, left track Vj-Bk, permission to leave Vj under special conditions without a written order

10

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII 23 Børkop (excl.) – Preparatory work Bridge lifting 1 possession 1. quarter 22022 13/2-14/2 Possession of Banedanmark XXXXXXXX Vejle (incl.) FA-AR Bridge 20568 (22 hours) tracks 4, 6 and 40, left track Bk-Vj, permission to enter Vj under special conditions without a written order 36 23 Vejle (incl.) - Preparatory work New bridge, new 1 x day February 26/2-27/2 Total closure of Banedanmark Medium Heidenstam (incl.) FA-AR place possession both tracks Vejle - Bridge 20621 (30 hours) Hedensted 37 23 Vejle (incl.)- Preparatory work New bridge, new 1 x day November 19/11-20/11 Total closure of Banedanmark Medium Hedensted (incl.) FA-AR place possession both tracks Vejle - Bridge 20621 (30 hours) Hedensted 38 23 Vejle (incl.)- Preparatory work New bridge, new LA40 Current Along with Both tracks Vejle- Banedanmark * Hedensted (incl.) FA-AR place possessions Hedensted Bridge 20621 39 23 Vejle (incl.)- Preparatory work Demolition of bridge 1 x day April 22/4-24/4 Total closure of s Banedanmark Medium Hedensted (incl.) FA-AR Bridge 20624 possession (30 both tracks Vejle - hours) Hedensted 40 23 Horsens (incl.) - Preparatory work New bridge, same 1 x weekend May 20/5-22/5 Total closure of s Banedanmark Medium Hovedgård (incl.) FA-AR place possession both tracks Bridge 20724 between Horsens- Hovedgaard 41 23 Horsens (incl.)- Preparatory work New bridge, same LA40 Current Along with Both tracks Banedanmark * Hovedgård (incl.) FA-AR place possessions between Horsens- Bridge 20724 Hovedgaard 42 23 Hovedgård (incl.) - Preparatory work New bridge, same 1 x day April 23/4-24/4 Total closure of Banedanmark Medium Skanderborg (incl.) FA-AR place possession both tracks Bridge 20756 (30 hours) between Hovedgaard- Skanderborg 43 23 Hovedgård (incl.) - Preparatory work Bridge lifting 1 x weekend June 10/6-12/6 Total closure of Banedanmark Medium Skanderborg (incl.) FA-AR Bridge 20764 possession both tracks between Hovedgaard- Skanderborg 44 23 Hovedgård (incl.) - Preparatory work Bridge lifting 10 x day July 4/7-13/7 Left track Banedanmark High Skanderborg (incl.) FA-AR Bridge 20764 possession operations Skanderborg - Hovedgaard 45 23 Hovedgård (incl.) - Preparatory work Bridge lifting 1 x weekend July 15/7-17/7 Left track Banedanmark Medium Skanderborg (incl.) FA-AR Bridge 20764 possession operations Hovedgaard - Skanderborg 46 23 Hovedgård (incl.) - Preparatory work Bridge lifting 1 x weekend August 12/8-14/8 Total closure of Banedanmark Medium Skanderborg (incl.) FA-AR Bridge 20764 possession both tracks between Hovedgaard- Skanderborg 47 23 Hovedgård (incl.) - Preparatory work New bridge, same 1 x weekend May 13/5-15/5 Total closure of Banedanmark Medium Skanderborg (incl.) Fa-Ar place possession both tracks Bridge 20772 between 11

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII Hovedgaard- Skanderborg 48 23 Hovedgård (incl.) - Preparatory work New bridge, same 1 x weekend May 20/5-22/5 Total closure of Banedanmark Medium Skanderborg (incl.) Fa-Ar place possession both tracks Bridge 20772 between Hovedgaard- Skanderborg 49 23 Hovedgård (incl.) - Preparatory work New bridge, same LA40 May 10/5 – 30/5 La 40 max 300 m Banedanmark * Skanderborg (incl.) Fa-Ar place Bridge 20772 at bridge 20772 both main tracks

50 23 Hovedgård (incl.) - Preparatory work New bridge, new 1 x weekend December 2/12 – 4/12 Total closure of Banedanmark Medium Skanderborg (incl.) FA-AR Bridge 20789 possession both tracks between Hovedgaard- Skanderborg 51 23 Skanderborg (incl.) Preparatory work New gangway, same 1 x weekend March 11/3-13/3 Total closure of Banedanmark Medium – Hørning (incl.) FA-AR place - Bridge 20808 possession both tracks between Skanderborg - Hørning 52 23 Skanderborg (incl.) Preparatory work New gangway, same 1 x weekend May 20/5-22/5 Total closure of Banedanmark Medium – Hørning (incl.) FA-AR place - Bridge 20808 possession both tracks between Skanderborg - Hørning 53 23 Skanderborg (incl.) Preparatory work New gangway, same LA40 March, April and 8/3-10/4 + La 40 max 300 m Banedanmark * – Hørning (incl.) FA-AR place - Bridge 20808 May 17/5-30/5 at bridge 20808 both main tracks

54 23 Skanderborg (incl.) Preparatory work New bridge, same 1 x weekend March 25/3-27/3 Total closure of Banedanmark Medium – Hørning (incl.) Fa-Ar place possession both tracks Bridge 20812 between Skanderborg - Hørning 55 23 Skanderborg (incl.) Preparatory work New bridge, same 1 x weekend April 1/4-3/4 Total closure of Banedanmark Medium – Hørning (incl.) Fa-Ar place possession both tracks Bridge 20812 between Skanderborg - Hørning) 56 23 Skanderborg (incl.) Preparatory work New bridge, same 1 x weekend April-May 29/4-1/5 Total closure of Banedanmark Medium – (incl.) Fa-Ar place possession lines Bridge 20813.8 57 23 Hørning (incl.) - Preparatory work New bridge, same 1 x weekend April 15/4-17/4 Total closure of Banedanmark Medium Aarhus (incl.) FA-AR place possession both tracks Bridge 20828 between HX-AR 58 23 Hørning (incl.)- Preparatory work New bridge, same 1 x weekend April 22/4-24/4 Total closure of Banedanmark Medium Aarhus (incl.) FA-AR place possession both tracks Bridge 20828 between HX-AR 59 23 Hørning (incl.) - Preparatory work New bridge, same LA40 March-May 27/3-1/5 La 40 max 300 m Banedanmark * Aarhus (incl.) FA-AR place at bridge 20828 Bridge 20828 both main tracks

12

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII 60 24 Aarhus (incl.) - Reconstruction of Bridge- and 56 hours April 1 /4-4/4 Total closure of Banedanmark Medium Langå (incl.) tracks and speed drainage works. lines upgrade Ar-Lg Reconstruction of Nfsp0503/Na0052 tracks. 61 24 Aarhus (incl.) - Reconstruction of Reconstruction of Br 10 days April 8/4-19/4 Total closure of Banedanmark High Langå (incl.) tracks and speed station. lines upgrade Ar-Lg Bridge- and Nfsp0503/Na0052 drainage works. Various 3. party projects. 62 24 Aarhus (incl.) - Reconstruction of Ballast cleaning and 18 days May-June 20/5-7/6 Total closure of Banedanmark High Langå (incl.) tracks and speed reconstruction of lines upgrade Ar-Lg tracks. Nfsp0503/Na0052 Bridge- and drainage works. Earth works DSB workshop. 63 24 Aarhus (incl.) - Reconstruction of Ballast cleaning 56 hours August 19/8-22/8 Total closure of Banedanmark Medium Langå (incl.) tracks and speed lines upgrade Ar-Lg Nfsp0503/Na0052 64 24 Aarhus (incl.) - NA00443 Preparatory works 56 hours February 17/2-20/2 Total closure of Banedanmak Medium Langå (incl.) for electrification lines 65 24 Aarhus (incl.) - NA00443 Preparatory work for 31 hours July 11/7-13/7 Total closure of Banedanmark Medium Langå (incl.) elektrificering lines Station Both tracks

66 24 Aarhus (incl.) - NA00443 Preparatory works 31 hours August 6/8-8/8 Total closure of Banedanmark Medium Langå (incl.) for electrificationg lines Hadsten Station Both tracks

67 24 Langå (incl.) - Reconstruction of Ballast cleaning and 26 days June-July 17/6-13/7 Left track Banedanmark High Hadsten (incl.) tracks and speed reconstruction of operations Lg-Ha upgrade Ar-Lg tracks. Nfsp0503/Na0052 Crossing works 68 24 Hadsten (incl.) - Reconstruction of Ballast cleaning and 30 days July-August 20/7-19/8 Left track Banedanmark Major Langå (incl.) tracks and speed reconstruction of operations Ha-Lg upgrade Ar-Lg tracks. Nfsp0503/Na0052 69 24 Aarhus (incl.)- Reconstruction of Bridge works 15 days May 6/5-20/5 Left track Banedanmark High Brabrand (incl.) tracks and speed Silkeborgvej operations Ar-Br upgrade Ar-Lg Nfsp0503/Na0052 70 24 Brabrand (incl.)- Reconstruction of Bridge works 17 days April-May 19/4-5/5 Left track Banedanmark High Aarhus (incl.) tracks and speed Silkeborgvej operations Br-Ar upgrade Ar-Lg Nfsp0503/Na0052 71 24 Mundelstrup (incl.)- Reconstruction of Ballast cleaning and 10 days June 7/6-17/6 Left track Banedanmark High Brabrand (incl.) tracks and speed reconstruction of operations Mu-Br upgrade Ar-Lg tracks Nfsp0503/Na0052

13

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII 72 Brabrand (incl.) - Reconstruction of Ballast cleaning and 22 days June-July 28/6-20/7 Left track Banedanmark High 24 Mundelstrup (incl.) tracks and speed reconstruction of operations Br-Mu upgrade Ar-Lg tracks. Nfsp0503/Na0052 73 24 Hadsten (incl.) - Reconstruction of Ballast cleaning and 17 days June 11/6-28/6 Left track Bandenamrk High Hinnerup (incl.) tracks and speed reconstruction of operations Ha-Hn upgrade Ar-Lg tracks. Nfsp0503/Na0052 Crossing works 24 Hadsten (excl.) – Reconstruction of Reconstruction of 3 ½ days April 4/4 – 8/4 Left track Banedanmark XXXXX Hinnerup (excl.) tracks and speed tracks operations upgrade Ar-Lg Ha-Hn Nfsp0503/Na0052 74 24 Hinnerup (incl.) - Reconstruction of Ballast cleaning and 18 days July 13/7-31/7 Left track Banedanmark High Hadsten (incl.) tracks and speed reconstruction of operations Hn-Ha upgrade Ar-Lg tracks. Nfsp0503/Na0052 75 24 Mundelstrup (incl.) Reconstruction of Ballast cleaning 36 days July-September 31/7-19/8 and Left track Banedanmark Major -Hinnerup (incl.) tracks and speed 22/8-7/9 operations Mu-Hn upgrade Ar-Lg Nfsp0503/Na0052 76 24 Hinnerup (incl.) - Reconstruction of Ballast cleaning 18 days September 7/9-26/9 Left track Banedanmark High Mundelstrup (incl.) tracks and speed operations Hn-Mu upgrade Ar-Lg Nfsp0503/Na0052 77 24 Hobridge (incl.) – Na00443 Bridge works 1,5 days June 20/6-22/6 Total closure of Banedanmark Medium (incl.) lines Hobridge - Skørping 79 24 Skørping (incl.) – Na00443 Bridge works 4,5 days June 3/6-7/6 Total closure of Banedanmark Medium Aalborg (incl.) lines Skørping – Aalborg 82 24 Skørping (incl.) – Na00443 Bridge works Weekend August 12/8-15/8 Total closure of Banedanmark Medium Aalborg (incl.) lines Hobridge - Skørping 24 Skørping – Aalborg Preparatory works- Bridge works 56 hours 2. quarter 08/4-11/4 All trains are Bdk both stationer excl. Electrification cancelled in both Programme directions 24 Skørping – Aalborg Preparatory works- Bridge works 5 days + 1 night 2. quarter 13/4-19/4 All trains are Bdk both stationer eksl. Electrification cancelled in both Programme directions 24 Skørping – Aalborg Preparatory works- Bridge works 20 days 2. quarter 19/4-09/5 La 40 over 200 m Bdk XXXXX both stationer excl. Electrification at bridge 21148 Programme 24 Aalborg incl. – Reconstruction of Total reconstruction B tracks, as well April-August 14/4 -25/8 Any longer Banedanmark XXXXXX Aalborg incl. tracks and speed of as areas with no shunting upgrade Hobridge – including earth, traffic impact movements during Aalborg bridges, tracks, and this period, and NF/SP/0473 and safety installations. access to track 0 NA0034 Moreover, various can be affected bridge works on the line Hb – Ab will be performed under cover of Aalborg Station 14

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII 24 Svenstrup (excl.) – Reconstruction of Total reconstruction South end: 8 April-August 14/4 -25/8 Total closure of Banedanmark Aalborg (incl.) tracks and speed of Aalborg Station weeks total lines, only upgrade Hobridge – including earth, closure of lines, Aalborg st, trains Aalborg bridges, tracks, and turn around in NF/SP/0473 and safety installations. Svenstrup, NA0034 Moreover, various replacement bus bridge works on the Svenstrup - line Hb – Ab will be Aalborg performed under cover of Aalborg Station 24 Skørping (excl.) - Reconstruction of Total reconstruction South end: 2 April-August 14/4 -25/8 Total closure of Banedanmark Aalborg (incl.) tracks and speed of Aalborg Station weeks total lines upgrade Hobridge – including earth, closure of lines. Aalborg bridges, tracks, and NF/SP/0473 and safety installations. NA0034 Moreover, various bridge works on the line Hb – Ab will be performed under cover of Aalborg Station 25 Aalborg (incl.) – Reconstruction of Total reconstruction North end: 10 April-August 14/4 -25/8 Total closure of Banedanmark Lindholm (excl.) tracks and speed of Aalborg Station weeks total lines upgrade Hobridge – including earth, closure of lines. Aalborg bridges, tracks, and NF/SP/0473 and safety installations. NA0034 Moreover, various bridge works on the line Hb – Ab will be performed under cover of Aalborg Station 25 Aalborg (incl.) – 3. party project Vesterbo renovation 5 days + 1 night 2. quarter 13/4-19/4 All trains are Aalborg XXXX Lindholm (excl.) cancelled in part kommune Aalborg–Lindholm 25 Aalborg (incl.) – 3. party project Vesterbo renovation 3 days + 1 night 2. quarter 03/6-07/6 All trains are Aalborg XXXXX Lindholm (excl.) cancelled in part kommune Aalborg–Lindholm 31 Struer (excl.) – Signalling Implementation 3 days + 1 night 2. quarter 12/5-16/5 All tracks are Banedanmark Vemb (excl.) Programme west possessed

86 31 Vemb (excl.) - Signalling Implementation 3 days + 1 night 2. quarter 03/6-07/6 All trains are Banedanmark Medium Hjerm (excl.) Programme west cancelled in part

87 31 Ulfborg (incl.) - Signalling Implementation Weekend of 56 December 9/12-12/12 All tracks are Banedanmark Medium Holstebro (excl.) Programme west hours possessed

88 31 Holstebro (incl.) – NFSP05001 Struer Bridge works 3 weeks + 1 day July-August 22/7-13/8 Total closure of Banedanmark High Struer (incl.) St lines

89 31 Hjerm (incl.) – NFSP05001 Struer Track renewal and 3 weeks + 1 day July-August 22/7-13/8 Total closure of Banedanmark High Struer (incl.) St trimming of switches lines 15

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII

90 32 Vinderup (incl.) – NFSP05001 Struer Track renewal and 3 weeks + 1 day July-August 22/7-13/8 Total closure of Banedanmark High Struer (incl.) St trimming of switches lines 33 Struer (excl.) – Signalling Implementation 3 days + 1 night 2. quarter 12/5-16/5 Trains can turn Banedanmark XXXXX Holstebro (incl.) Programme west around in track 1 Holstebro

33 Herning (excl.) – Signalling Implementation 56 hours 3. quarter 29/7-01/8 All trains are Banedanmark XXXXX Vejle (excl.) Programme west cancelled in part 91 33 Aulum (incl.) – Signalling Implementation 3 days + 1 night 2. quarter 03/6-07/6 All trains are Banedanmark Medium Holstebro (incl.) Programme west cancelled in part

92 33 Holstebro (excl.)– Signalling Implementation 56 hours 2. quarter 17/6-20/6 All trains are Banedanmark Medium Herning (incl.) Programme west cancelled in part + Herning trains can turn around in i tracks 3 and 4 93 33 Vildbjerg (excl.) – Signalling Implementation 56 hours 3. quarter 08/7-11/7 All trains are Banedanmark Medium Thyregod (excl.) Programme west cancelled in part 94 33 Give (excl.) – Vejle Signalling Implementation 56 hours 3. quarter 12/8-15/8 All trains are Banedanmark Medium (excl.) Programme west cancelled in part

95 33 Vejle (excl.) - Give Signalling Implementation Weekend á 56 May 13/5- 16/5 All tracks are Banedanmark Medium (incl.) Programme west hours possessed

34 Struer (excl.) – Level-free crossing Leadlines 14 weeks May – August 8/5-13/8 Total closure of Banedanmark Thisted (excl.) lines,under cover of Oddesundbroen

96 34 Struer St (incl.) NFSP05001 Struer Track renewal and 6 weeks+1 day June-July 9/6-22/7 Only track 4 and 5 Banedanmark Major St trimming of switches available, no operations to engine depot Struer 97 34 Struer (incl.) – NFSP05001 Struer Track renewal and 3 weeks + 1 day July-August 22/7-13/8 Total closure of Banedanmark High Hvidbjerg (incl.) St trimming of switches lines

98 34 Struer (excl.) – NFSP05281 Track renewal on 14 weeks May – August 8/5-13/8 Total closure of Banedanmark Major Hvidbjerg (incl.) Oddesundbroen Oddesundbroen lines

99 35 Hammerum (excl.) Signalling Implementation 56 hours 3. quarter 02/9-05/9 All trains are Banedanmark Medium – Svejbæk (excl.) Programme west cancelled in part

100 35 Engesvang (excl.) - Signalling Implementation 56 hours 3. quarter 23/9-26/9 All trains are Banedanmark Medium Skanderborg (excl.) Programme west cancelled in part

102 35 Borris (excl.) – Signalling Implementation 56 hours 3. quarter 08/7-11/7 All trains are Banedanmark Medium Bording (excl.) Programme west cancelled in part

16

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII 810 Glostrup (incl.) – The Capital's Light Rail Placement of 1 weekend Easter 15-18.April Both tracks Gl-Tå Hovedstadens XXXXX Tåstrup (excl.) at Glostrup bridge possessed. Turn around Letbane (3. in Gl from Kh is possible party)

1 810 Taastrup track 3 Reconstruction Kh – Htå Fencing of 4 days June 20/6 – 24/6 Single track operations Banedanmark * (incl.) (Fjern) possessions for Høje Taastrup – long-distance lines Taastrup – Glostrup 2 810 Taastrup (excl.) – Reconstruction Kh – Htå Fencing of 5 weeks May-June 1/5 – 9/6 Single track operations Banedanmark * Glostrup (Incl.) + (Fjern) possessions for Tåstrup – Glostrup Glostrup track 3 long-distance lines (Incl.)

3 810 Høje Taastrup Reconstruction Kh – Htå Fencing of 2 weeks June 9/6 – 24/6 Single track operations Banedanmark * (excl.) – Taastrup (Fjern) possessions for Høje Taastrup – incl.) long-distance lines Taastrup

4 810 Høje Taastrup Reconstruction Kh – Htå Fencing of 19 days July-August 16/7 – 3/8 Single track operations Banedanmark * (incl.) – Taastrup (Fjern) possessions for Høje Taastrup – (incl.) + Taastrup long-distance lines Taastrup track 3 (Incl.)

5 820 Hellerup tracks 3, 4, Catenary exchange Kk – Catenary 6 days April 13/4 – 19/4 Single track operations Banedanmark * 5 and 6 Hot exchange Sam – Hl – Gj and Ler – Hl – Kl 6 820 Hellerup tracks 7 + Catenary exchange Kk – Catenary 2 x 56 hours Summer Not settled Single track operations Banedanmark * 8 Hot exchange Gj – Hl – Sam and Kl – Hl – Ler 7 820 Gentofte tracks 1 Catenary exchange Kk – Catenary 56 hours Summer Not settled Total closure of lines Ly Banedanmark * +2 Hot exchange – Hl

8 820 Lyngby tracks 1, 2 + Catenary exchange Kk – Catenary 80 hours May 12/5 – 16/5 Total closure of lines Gj Banedanmark Medium 3 Hot exchange – Vir

9 820 Svanemøllen tracks Catenary exchange Kk – Catenary 2 x 56 hours Summer Not settled Single track operations Banedanmark * 3 +4 Hot exchange Kk – Sam – Hl and Kk – Sam – Ryt 10 820 Svanemøllen tracks Catenary exchange Kk – Catenary 2 x 56 hours Summer Not settled Single track operations Banedanmark * 5 +6 Hot exchange Ryt – Sam – Kk and Hl – Sam – Kk 11 820 Østerport tracks 3 + Catenary exchange Kk – Catenary 2 x 56 hours Not settled Not settled Single track operations Banedanmark * 13 Hot exchange Sam - Kk

12 820 Østerport tracks 3 + Catenary exchange Kk – Catenary 2 x 56 hours Not settled Not settled Single track operations Banedanmark * 13 Hot exchange Kk - Kh

13 820 Østerport tracks 4 + Catenary exchange Kk – Catenary 2 x 56 hours Not settled Not settled Single track operations Banedanmark * 13 Hot exchange Kh - Kk

14 820 Østerport tracks 4 + Catenary exchange Kk – Catenary 2 x 56 hours Not settled Not settled Single track operations Banedanmark * 13 Hot exchange KK - Sam

17

Serial TIB Line Project Description Exp. duration Exp. period Exp. dates Traffic impact Builder Categorisation, no. cf. Annex VII Establi 880 Nørrebridge (Incl.) Nordvestpassagen Insertion of 10 days July-August 22/7 – 1/8 Total closure of lines Nø Københavns High shme1 – Lersøen (Incl.) pedestrian tunnel – Ler Kommune 5 16 830 Herlev (Incl.) – Establishment of light Bridge works 3 weeks March – April Not settled Single track operations Hovedstadens * Ballerup (excl.) Rail crossing Ba - Her Letbane

17 830 Herlev (Incl.) – Establishment of light Bridge works 1 week At least 3 Not settled Single track operations Hovedstadens * Ballerup (excl.) Rail crossing weeks after Ba - Her Letbane previous possession 18 810 *Svanemøllen excl. New Signaling system Putting into 1 weekend January 15/1-17/1 Total closure of lines Banedanmark Medium 820 -Valby S-Line service of ROC, S- 850 excl./Åmarken excl. Line signalling PSP: S/SB/BBFB-9-9- project *Østerport (incl.) - 11160-SHBD Svanemøllen track sp 5 (incl.)

* Københavns Hovedbanegård (incl.) -Valby track 5 (incl.)

* Københavns Hovedbanegård (incl.) -Åmarken track 1

19 810 *Københavns New Signaling system Operational test 1 weekend February 19/2-21/2 Total closure of lines Banedanmark Medium 830 Hovedbanegård S-Line ROS 850 (incl.) -Køge/Høje Taastrup/Frederikss PSP: S/SB/BBFB-9-9- und 11160-SHBD

20 810 * Københavns New Signaling system Putting into 1 weekend September 24/9-26/9 Total closure of lines Banedanmark Medium 830 Hovedbanegård S-Line service of ROS, 850 (incl.) -Køge/Høje PSP: S/SB/BBFB-9-9- S-Line signalling Taastrup/Frederikss 11160-SHBD project und