Planning and Development Services

Planning Division 15151 E. Alameda Parkway, Ste. 2300 Aurora, Colorado 80012 303.739.7250

January 11, 2019

Jason Marcotte Northstar Commercial Partners 1999 Broadway, Suite 770 Denver, CO 80202

Re: Second Submission Review – Parkside at Center Filing No. 2 – Subdivision Application Number: DA-1773-07 Case Number: 2018-3049-00

Dear Mr. Marcotte:

Thank you for your second submittal, which we received on December 18, 2018. We reviewed it and attached our comments along with this cover letter.

As outlined in the review letter, a few items remain that need to be addressed / coordinated with Planning, Fire / Life Safety and Real . Please copy your Case Manager on all correspondence as you work to address these remaining comments. This is considered an “informal” technical submittal to expedite the process for you. Once those issues are resolved, you may send us your final mylar drawings for signatures and recording. To ensure proper tracking when you submit your mylar drawings, please use our Mylar Checklist and submit that with the final mylars.

As always, if you have any comments or concerns, please give me a call. I may be reached at 303-739-7857.

Sincerely,

Sarah Wieder, Senior Planner City of Aurora Planning Department cc: John Perry, Engineering Service Company, 14190 E Evans Avenue, Aurora, CO 80014 Susan Barkman, Neighborhood Liaison Mark Geyer, ODA Filed: K:\$DA\1773-07rev2.rtf

Second Submission Review

1. Planning (Sarah Wieder / 303-739-7857 / [email protected] / Comments in teal) 1A. Before the Subdivision Plat can be finalized, the public access easement issue must be resolved. If the adjacent property owner will not grant access through their property, will that portion of the site still remain a public access easement? Please clarify. 1B. As a reminder, the city has developed CAD Data Submittal Standards for internal and external use to streamline the process of importing AutoCAD information into the city’s Enterprise GIS. Please note that a digital submission meeting the CAD Data Submittal Standards is required before your final Subdivision Plat mylars can be routed for signatures or recorded. Please review the CAD Data Submittal Standards and email your Case Manager the .DWG file before submitting your final Subdivision Plat mylars. Once received, the city’s AutoCAD Operator will run an audit report and your Case Manager will let you know whether the .DWG file meets meet the city’s standards.

2. Fire / Life Safety (John Van Essen / 303-739-7489 / [email protected] / Comments in blue) 2A. The minimum turning radius for a 26’ fire lane to another 26’ fire lane is 26’. Please make adjustments to ensure this requirement is met.

3. Real Property (Maurice Brooks / 303-739-7294 / [email protected] / Comments in magenta) 3A. Update the title work as the date noted currently is September 14, 2018. This must be updated within 120 days of final Subdivision Plat approval. 3B. Begin the easement release process for the easements that were previously dedicated. Please coordinate this process with Andy Niquette. 3C. Release the Xcel easement prior to any permits.

4. Xcel Energy (Donna George / 303-571-3306 / [email protected]) 4A. See the attached comment letter.

Siting and Rights

Right of Way & Permits

1123 West 3rd Avenue Denver, Colorado 80223 Telephone: 303.571.3306 Facsimile: 303. 571. 3284 [email protected]

January 4, 2019

City of Aurora Planning and Development Services 15151 E. Alameda Parkway, 2nd Floor Aurora, CO 80012

Attn: Sarah Wieder

Re: Parkside at City Center Subdivision Filing No. 2 - 2nd referral Case # DA-1773-07

Public Service Company of Colorado’s (PSCo) Right of Way & Permits Referral Desk acknowledges the comment responses for Parkside at City Center F2 and requests that at the appropriate time the property owner/developer/contractor contacts Russ McClung, Right-of-Way Agent at 303-671-3932 for the processing of a quitclaim deed for the easement situated in the “middle” of Lot 1, and, for any additional easements that may need to be acquired by separate document for new facilities.

The property owner/developer/contractor is reminded to complete the application process for any new gas or electric service, or modification to existing facilities via FastApp-Fax-Email-USPS (go to: https://www.xcelenergy.com/start,_stop,_transfer/new_construction_service_activation_ for_builders).

If there are any questions about this referral response, please contact me at (303) 571- 3306 or [email protected].

Donna George Right of Way and Permits Public Service Company of Colorado

City of Aurora Planning and Development Services Department MYLAR CHECKLIST 15151 E. Alameda Parkway, Ste 2300 • Aurora, CO 80012 • 303.739.7420

Instructions: The applicant shall confirm that each item listed below has been completed by checking each box or writing not applicable (N/A) and signing and dating the bottom of the form before submitting MYLARs to the Planning Case Manager.

¨ All required city fees have been paid (verify this with the Planning Case Manager). ¨ Comments from all departments have been addressed and all changes to the MYLARs have been approved by the affected departments prior to submittal of the final MYLARs to the Planning Case Manager. ¨ Drainage plan approved and civil drawings near completion. ¨ The effective date on the title work and Certificate of Taxes Due is within 120 days of final city approval of the plan. ¨ If an Avigation Easement is required, a copy of the recorded document has been submitted to the Planning Case Manager and the City Clerk and Recorder. ¨ Digital files, preferably on a compact disc, for the site plan, CSP, subdivision plat, GDP, FDP, etc. have been submitted to the Planning Case Manager. Instructions can be found online: • https://www.auroragov.org/UserFiles/Servers/Server_1881137/File/Final%20-%20CAD%20 Data%20Submittal%20Standards_11_28_2016.pdf • Also refer to the Instructions for Submitting Digital Files for Addressing. ¨ The surveyor, property owner(s), and mortgage company have signed both cover sheets with black indelible ink. • Please ensure that the signatures, stamps and seals text do not smear ¨ The notary has filled in the signature block and applied their indelible stamp inblack indelible ink. • Please ensure that the stamp does not smear ¨ The surveyor has applied their stamp and signed their name through the stamp. • Please ensure that the stamp does not smear ¨ Submit one complete set of signed and notarized MYLARs and one additional signed and notarized cover sheet for each site plan, CSP, GDP, FDP, etc. Subdivision require submittal of one set of signed and notarized MYLARs. • Adams County a. One complete set of signed and notarized MYLARs in 18 inch by 24 inch format b. One additional signed and notarized MYLAR cover sheet in 24 inch by 36 inch format for the city c. For plats one complete set 18 inch by 24 inch • Arapahoe County & Douglas County a. One complete set of signed and notarized MYLARs in 24 inch by 36 inch format b. One additional signed and notarized MYLAR cover sheet in 24 inch by 36 inch format for the city c. Please note that all MYLARs shall be four millimeters thick, double mat, reverse print/burn, and photo quality d. For plats, one complete set of 24 inch by 36 inch plats

*Allow 10 or more business days for Mylar processing

Project Name: ______DA #: ______

Applicant Signature: ______Date: ______

Phone: ______Email:______

Note: This form is also available online MYLAR Checklist (Revised 12/2016)