<<

Preliminary Screening Report Form

Preliminary screener: MVLWB EIRB Reference I File Reference number: MV201OX00031MV201OL8-0002 number: TITLE: Miscellaneous, Bridge Construction, , NT Organization: GNWT-Department of Transportation Meeting date: March 19, 2010

Type of Development: New (CHECK ALL THAT APPLY) q Amend, EIRB Ref. # Requires permit, licence, or authorization Does not require permit, licence, or authorization Project Summary

A summary of the operation is as follows:

• Complete construction of the Blackwater bridge; • Procurement o Fabricate precast deck panels o Fabricate expansion joints o Fabricate deck drains o Fabricate PL-2 Barrier o Fabricate flares and guardrails • Delivery Schedule o Girders o Precast abutment caps o Precast ballast wall o Bridge expansion bearings o Jump span girders o Precast deck panels o Guard and approach rails o Girders pier 3 to north abutment (NA) • Site Access o Gain access to NA Lima o Gain access to NA Kobelco • Pile Driving o Pier #1 setup driving frame, drive first link o NA set up driving frame, drive 2links o Pier #1 drive remaining links o Pier #1 PDA testing o NA driving remaining link o NA PDA testing o South sbutment (SA) jump span piles • Diaphragms o Pier 3 diaphragm o Pier 2 diaphragm o Pier 1 diaphragm • Capping o Pier 3 o Pier 2 o Precast SA jump span cap o Pier 1 o Precast NA jump span cap • CIP Concrete o Place rebar and concrete pier 2 o Heat and hoard pier 2 piles o Place rebar and concrete pier 1 o Heat and hoard pier I piles o Place rebar and concrete NA pile o Heat and hoard NA piles o NA formwork and rebar cap o Place concrete NA cap o Heat and hoard NA cap o NA ballast wall formwork and rebar o NA ballast wall concrete

MV201 OX0003/MV201OL8-0002 — GNWT-Department of Transportation — Blackwater River, NT -1- o Heat and hoard NA ballast Wall o SA ballast wall formwork and rebar o SA ballast wall concrete o Heat and hoard SA ballast wall formwork and rebar • Steel Erection o Launch segment 14,13 o Install segments 12,11 o Install segments 10,9 o Install segments 8,7 o Install segments 7,6 o Install segments 5,4 o Install segments 3,2 o Install segment 1 o install jump span south o Install jump span north o Install counterweight bridge ballast • Deck Panels o Installation of deck panels o Place concrete group pockets • Earthworks south side o Swale installation o Process rock at quarry o Rip rap installation pier 3 and pier 2 o Remove pier 3 and 1 access o Install armour flex matting • Earthworks north side o haul to north abutment o Haul and place rip rap o Armour flex matting install o Remove access • Completion o Install guard rail and grout o Approach guard rails o Seeding of cut slopes o Signage o Demobilization

• Granular material will be utilized under the operation and maintenance LUP MV2008E0033. A quarry permit is already in place (2009QP0122), • Water will be drawn from the Blackwater River or the Mackenzie River, • A Spill Contingency Plan is in place • An Erosion and Sediment Control Plan is in place for during and after construction; • Authorizations from Navigable Waters have been granted; • Garbage will be hauled off site to a NWT community and if need be south to an alternate facility; • Sumps will be used for service at the camp; • Project exists in an already existing corridor it is not anticipated to clear merchantable timber; • Any soil that is disturbed will be stockpiled and used during reclamation • Fuel will be stored in two, 12,000-litre tanks.; • Spill kits will be available at site, on equipment and at the camp; • Refuelling will take place in designated areas; • The camp site is previously permitted (MV2008E0033); • WL is requested to obtain water, to cross a water course and to modify the bed or bank of a water course; • Water is required for the camp at the rate of 19cubic metres per day; • A drainage swale will also be realigned to accommodate abutment placement on the south side of the river armour flex mats will also be place at this time; • Water will be required for earthworks and realignment at a rate of 100 cubic metres per day; • Potable water will be hauled to the site, • Domestic waste water will be placed in a sump at the camp location; • Navigation of the Blackwater River will not be impacted; • The project includes remediation and removal of the old road way: and • The Applicant request 5 years for both the LUP and WL.

Scope

Continued construction of a permanent bridge at Blackwater River, associated activities, and the remediation and removal of the old road way. Activities will take place along the Mackenzie Valley Winter Road, Northwest Territories (63°53'50"N — 124°06'00V and 63°57'32"N — 124°12'16'W)

MV2010X0003/MV2010L8-0002 — GN -Department of Transportation — Blackwater River, NT -2- Land Use Eligibility - Section 18 Mackenzie Valley Land Use Regulations

Type of Disposition Disposition Number(s) q Mineral Claims q Prospecting Permit (s) q Mineral Leases q Oil and Gas: EUSD L q Quarry Permit q Timber Permit Other: MV2008E0033

Principal Activities (related to scoping) (CHECK ALL THAT APPLY)

Construction q Exploration q Dommissioning Installation q Industrial q Abandonment q Maintenance q Recreation q Aerial q Expansion q Municipal q Harvesting q Operation q Quarry q Camp q Repair Linear / Corridor q ScientifiG q Research q Sewage q Solid Waste q Water Intake Other: bridge installation

Principal Development Com ponents (related to scoping)

0 Access Road E Waste Management 0 construction disposal of hazardous waste 0 abandonment/removal waste generation modification e.g., widening, straightening q sewage Automobile, Aircraft or Vessel Movement q disposal of sewage q Blasting Geoscientific Sampling q Building q Trenching q Burning q Diamond drill q Burying q Borehole core sampling q Channelling q Bulk soil sampling Cut and Fill q gravel 0 Cutting of Trees or Removal of Vegetation q hydrological Testing q Dams and Impoundments Site Restoration q construction q fertilization q abandonment/removal q grubbing q modification planting/seeding Ditch Construction q reforestation Drainage Alteration q scarify q Drilling other than Geoscientific q spraying q Ecological Surveys re-contouring Excavation Slashing and removal of vegetation q Explosive Storage q Sdl Testing Fuel Storage CrossingBridging 0 Topsoil, Overburden or Soil q Tunnelling/Underground fill q Other: q disposal removal storage

NTS topographic map sheet num bers: 95N

Latitude / longitude and UTM system: 63°53'50"N — 124°06'00'W and 63°57'32"N — 124°12'16W

Nearest community and water body: The nearest community is Wrigley and the nearest water body is the Blackwater River.

Land Status (consultation information) q Free Hold/Private q Commissioners Land 0 Federal Crown Land q Municipal Land

MV2010X0003/MV2010L8-0002 — GNWT-Department of Transportation — Blackwater River, NT -3- Transboundary/Transregional Implications q British Columbia q Alberta q Saskatchewan q Yukon q Nunavut q Wood Buffalo National Park q Inuvialuit Settlement Region q Nahanni National Park q Wek'6ezhii q Gwich'in q Sahtu

Type of transboundary implication: q Impact/Effect q Development q Public concern: (Describe.)

Physical - Chemical Effects

Impact Mitigation Location of 1) Ground Water condition q water table alteration

® water quality changes There is the potential for the water to become contaminated through 26(1)(g) hydrocarbon spills.

Mitigation The Proponent has a Spill Contingency Plan in place. q changes q other: q N/A

Impact Mitigation Location of 2) Surface Water condition

® flow or level changes There is the potential for the flow to change with the in-stream work that has 26(1)(g) been completed also through bank alterations that will have to be completed.

Mitigation The Proponent has worked with the Department of Fisheries and Oceans to prevent damage.

® water quality changes There is the potential for the water to become contaminated through 26(1)(g) hydrocarbon spills.

Mitigation The Proponent has a Spill Contingency Plan in place. q water quantity changes

drainage pattern changes There is the potential for drainage to be altered through the construction of 26(1)(t) ditches, and use of armouring.

Mitigation The Proponent has an Erosion and Sediment Control Plan in place to mitigate the potential impacts. q temperature q changes/loss q other: q N/A

Impact Mitigation Location of 3) Noise condition

® noise in/near water Noise levels may temporarily disturb wildlife. However, this impact is expected to be minimal, localized and short-term. The project will help reduce future noise levels, as the winter crossing construction will not need to occur annually.

Mitigation: No mitigation

MV201OX0003/MV201OL8-0002 — GNWT-Department of Transportation — Blackwater River, NT -4- noise increase There will be an increase of noise at the site. The closest communities to the site are Wrigley and Tulita. The communities should not be impacted by the increased level of noise.

Mitigation: The noise increase will be temporary. No mitigation

q other:

q N/A

Impact Mitigation Location of 4) Land condition

O geologic structure changes The geological structure will change as a result of the bridge installation, quarry establishment, and the geotechnical drilling.

Mitigation: The changes are necessary for the construction of the bridge and the realignment of the winter road. No mitigation

q soil contamination

q buffer zone loss

soil compaction and settling The soil will be compacted because of the construction and the weight of the bridge.

Mitigation: No mitigation

destabilizatioNerosion Altering the banks of the river could result in destabilization and erosion.

Mitigation: The applicant has an Erosion and Sediment Control Plan in place to mitigate any potential impacts.

q permafrost regime alteration

q explosives/scarring

q other:

0 N/A

Impact Mitigation Location of 5) Non-renewable natural condition resources

q resource depletion

q other:

N/A

Impact Mitigation Location of 6) Air/climate/atmosphere condition

• other: dust An increase in dust levels may occur. This impact is expected to be minimal and short - term

Mitigation: No mitigation.

O other: green house gasses With the use of equipment there will be the introduction of greenhouse gases to the environment.

Mitigation: No mitigation q N/A

MV2010X0003/MV2010L8-0002 — GNWT-Department of Transportation — Blackwater River, NT -5- Biological Environment

Impact Mitigation Location of 1) Vegetation condition q species composition q species introduction

® toxin/heavy accumulation There is the potential for vegetation to be impacted by hydrocarbon 26(1)(g) contamination.

Mitigation The Proponent has a Spill Contingency Plan in place which should assist in the mitigation of this concern. q other: q N/A

Impact Mitigation Location of 2) Wildlife and Fish condition q effects on rare, threatened or endangered species q fish population changes q waterfowl population changes q breeding disturbance q population reduction q species diversity change q health changes ® behavioural changes Some species may avoid the area during construction. This effect is 26(1)(h) localized and short- term, therefore minimal impact is anticipated.

Mitigation: No mitigations

® habitat changes / effects Some species may avoid the area during construction. This effect is 26(1)(h) localized and short- term, therefore minimal impact is anticipated.

Mitigation: No mitigations q game species effects q toxins/ heavy metals q forestry changes q agricultural changes q other: q N/A Interacting Environment

Impact Mitigation Location of 1) Habitat and Communities condition q predator-prey q wildlife habitat/ecosystem composition changes q reduction/removal of keystone or endangered species

MV2010X0003/MV2010L8-0002 — GNWT-Department of Transportation — Backwater River, NT -6- q removal of wildlife corridor or buffer zone q other:

O N/A

Impact Mitigation Location of 2) Social and Economic condition q planning/zoning changes or conflicts q increase in urban facilities or services use q rental house q airport operations/capacity changes q human health hazard q impair the recreational use of water or aesthetic quality q affect water use for other purposes q affect other land use operations

quality of life changes Local residents could potentially use the bridge for longer periods of time, as the condition of the winter road would determine usage rather than timing of fall freeze-up and spring break-up.

Mitigation: No mitigation q public concem q other: q N/A

Impact Mitigation Location of condition 3) Cultural and Heritage q effects to historic property q increased economic pressure on historic properties q change to or loss of historic resources q change to or loss of archaeological resources q increased pressure on archaeological sites q change to or loss of aesthetically important sites q effects to aboriginal lifestyle q other:

O N/A

MV2010X0003/MV2010L8-0002 — GNWT-Department of Transportation — Blackwater River, NT -7- Notes:

Consultation

Pursuant to section 27, paragraphs (a) and (b) of the Deh Cho First Nations (DCFN) Interim Measures Agreement, the MVLWB has determined that written notice was given to the DCFN and that a reasonable period of time was allowed for DCFN to make representations with respect to the application.

Pursuant to Schedule 4.1 of the Northwest Territory Metis Nation (NWTMN) Interim Measures Agreement, the MVLWB has determined that written notice was given to the NWTMN and that a reasonable period of time was allowed for NWTMN to make representations with respect to the application.

MV201 OX0003/MV2010L8-0002 — GNWT-Department of Transportation — Blackwater River, NT -8- Preliminary Screener / Referring Body Information

ABORIGINAL ORGANIZATIONS Deh Cho First Nation West Point First Nation Katlodeeche First Nation

Hay River M^tis Government Council Fort Smith Metis Council Northwest Terntory Metis Nation Dene Nation NWT Treaty 8 Tribal Corporation edeli First Nation (JMR) Deh Gah Got'ie Dene Council (Ft Prov.) Nahanni Butte First Nation Tu First Nation (Kakisa) Pehdzeh Ki First Nation (Wrigley) Liidlii Kue First Nation (Ft Simpson) Acho Dene Koe First Nation (Fort Liard) Deh Cho Land Use Planning Committee Fort Liard M^tis Local #67 Nahendeh Land & Environmental Services Ft. Providence Met's Council Local #57 Sambaa K'e Dene Band (Trout Lake)

COMMUNITIES Town of Hay River Enterprise Settlement Corporation Village of Fort Simpson Hamlet of Fort Providence Hamlet of Fort Liard

GOVERNMENT — GNWT GN-PWNHC GN-MACA GN - ENR Gnwl [email protected] GN-DOT GNWT-Health GN — ITI

GOVERNMENT — FEDERAL South Mackenzie District Office — INAC Mineral & Petroleum Res Directorate-INAC Head, Regulatory and Science Advice - Water Resources - INAC Manager/ Aboriginal and Territorial Relations - INAC Environment and Conservation — INAC Intergovernmental Affairs — INAC Environment Canada DFO

OTHERS BQCMB MVEIRB

MV2010X0003/MV2010L8-0002 — GNWT-Department of Transportation — Blackwater River, NT -9- Reasons for Decision (List all reasons and supporting rationales for prelimina ry screening decision)

The Mackenzie Valley Land and Water Board (the Board) is satisfied that the preliminary screening of Application MV201OX0003/MV201OL8-0002 — GNWT-Department of Transportation — Miscellaneous, Bridge Construction has been completed in accordance with section 125 of the Mackenzie Valley Resource Management Act (MVRMA).

The Board is satisfied that a reasonable period of notice was given to communities and First Nations affected by the application as required by subsection 63(2) of the MVRMA so that they could provide comments to the Board.

Having reviewed all relevant evidence on the Public Registry, including the submissions of the Applicant, the written comments received by the Board and any Staff Reports prepared for the Board, the Board has decided that:

• There is no likelihood that the proposed development might have a significant adverse impact on the environment; and • There is no likelihood that the proposed development might be a cause of public concern.

The Board is also of the opinion that the Application can proceed through the regulatory process and that any impacts of the development on the environment can be mitigated through the imposition of the terms and conditions in the attached Land Use Permit.

As a result, the Board, having due regard to the facts and circumstances, the merits of the submissions made to it, and to the purpose, scope, and intent of the Mackenzie Valley Resource Management Act and the Mackenzie Valley Land Use Regulations, has decided that this Land Use Permit be issued subject to the terms and conditions contained therein.

Preliminary Screening Decision

Outside Local Government Boundaries

q The development proposal might have a significant adverse impact on the environment, refer it to the EIRB.

Proceed with regulatory process andlor implementation.

q The development proposal might have public concern, refer it to the EIRB.

® Proceed with regulatory process and/or implementation.

q Wholly Within Local Government Boundaries

q The development proposal is likely to have a significant adverse impact on air, water or renewable resources, refer it to the EIRB.

q Proceed with regulatory process andlor implementation.

q The development proposal might have public concern, refer it to the EIRB.

q Proceed with regulatory process andlor implementation.

Preliminary Screening Organization

Mackenzie Valley Land and Water Board

March 19, 2010

MV201 OX0003/MV201 OL8-0002 — GNWT-Department of Transportation — Blackwater River, NT -10-