The World Bank Report No: ISR16205

Implementation Status & Results LK Safety and Water Resources Planning (DSWRPP) (P093132)

Operation Name: LK Dam Safety and Water Resources Planning (DSWRPP) Project Stage: Implementation Seq.No: 13 Status: ARCHIVED Archive Date: 28-Sep-2014 (P093132) Country: Sri Lanka Approval FY: 2008 Product Line:IBRD/IDA Region: SOUTH ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Ministry of Irrigation and Water Resources Management Key Dates Public Disclosure Copy Board Approval Date 27-Mar-2008 Original Closing Date 30-Jun-2013 Planned Mid Term Review Date 25-Jul-2011 Last Archived ISR Date 06-Mar-2014 Effectiveness Date 26-Jun-2008 Revised Closing Date 15-May-2018 Actual Mid Term Review Date 09-Sep-2011

Project Development Objectives Project Development Objective (from Project Appraisal Document) (i) Establish long-term sustainable arrangements for operation and maintenance of large ; and (ii) improve water resources planning.

Has the Project Development Objective been changed since Board Approval of the Project?

Yes No

Component(s)

Component Name Component Cost 1. Dam Safety and Operational Efficiency Improvement 53.14 2. Hydrometerological Information Systems Improvement 8.48 3. Multi-Sectoral Water Resources Planning 6.49 4. Project Management, Monitoring and Evaluation 3.05

Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating

Implementation Status Overview Good progress has been made under most of the contracts for dam rehabilitation/remedial measures and there are generally no major implementation issues. The rehabilitation and Public Disclosure Copy improvement works at 18 dams (up from 12 dams in January 2014) were completed by the end of June 2014 and at four dams the completion rate of contracts is above 80 percent.

Page 1 of 5 The World Bank Report No: ISR16205

The contracts for improving basic safety facilities at 80 dams have all been completed, except for some activities that are still ongoing at the 13 dams for which the remedial measures are still ongoing. The contract for the development of 122 hydro-meteorological stations is also ongoing and the first nine stations have now been fully installed and tested. Locations Country First Administrative Division Location Planned Actual Sri Lanka Southern Province Walawe Ganga

Sri Lanka Central Province

Sri Lanka North Eastern Province Vendarasan Kulam

Sri Lanka North Western Province Tabbowa Wewa

Public Disclosure Copy Sri Lanka Southern Province Ridiyagama Tank

Sri Lanka Central Province Rantembe Dam

Sri Lanka Central Province

Sri Lanka Central Province Polgolla Dam

Sri Lanka North Central Province

Sri Lanka North Central Province Nuwarawewa

Sri Lanka Central Province Norton

Sri Lanka Central Province Nalanda Reservoir

Sri Lanka Central Province Mousakelle

Sri Lanka North Central Province Minneriya Wewa

Sri Lanka North Eastern Province

Sri Lanka Central Province Laxapana

Sri Lanka Central Province

Sri Lanka North Central Province Kaudulla Wewa

Sri Lanka Central Province Kandalama Tank

Sri Lanka North Central Province Kalawewa

Sri Lanka North Western Province Inginimitiya

Public Disclosure Copy Sri Lanka North Central Province Hurulu Wewa

Sri Lanka North Central Province Giritale Wewa

Page 2 of 5 The World Bank Report No: ISR16205

Country First Administrative Division Location Planned Actual Sri Lanka Central Province Dambulu Oya Reservoir

Sri Lanka Province of Sabaragamuwa Chandrika Wewa

Sri Lanka Central Province Castlereagh

Sri Lanka Central Province Bowatenna Reservoir

Sri Lanka North Central Province Angamuwa

Results Public Disclosure Copy Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target (Reduced) number of Large Dams with Number Value 32.00 14.00 0.00 Unaccetable Risk Index Date 01-Jul-2008 30-Jun-2014 30-Jun-2015 Comments Works at 18 dams have been completed. Works at 13 dams are ongoing, many at an advanced stage of implementation, with one under procurement. Except for few dams, the target will be achieved. The target for the few dams will be achieved during the implementation of the AF. National Water Use Master Plan and at Least Text Value No National Water Use Plan The National Water Use Plan National Water Use Master One River Basin Development Plan adopted by and river basin plan exist. and river basin plan for the Plan and at Least One River the Cabinet of Ministers Mundeni Aru River have been Basin Development Plan prepared and approved by adopted by the Cabinet of line agencies. Ministers Date 01-Jul-2008 31-Jan-2014 30-Jun-2015 Comments The plans are to be approved by the Cabinet.

Intermediate Results Indicators Public Disclosure Copy

Page 3 of 5 The World Bank Report No: ISR16205

Indicator Name Core Unit of Measure Baseline Current End Target Number of Dams with Risk Based O&M Plans Number Value 0.00 11.00 32.00 Operationalized Date 01-Jul-2008 30-Jun-2014 30-Jun-2015 Comments O&M manuals for 11 dams have been approved by IAs and are fully operationalized, while 21 O&M manuals are available in draft and are to be approved formally by IAs. Number of dams provided with basic safety Number Value 0.00 67.00 80.00 facilities Sub Type Public Disclosure Copy Supplemental Ground Water Monitoring System is Text Value No Ground Water Monitoring Ground water monitoring The monitoring network is Established Sub Type System exists networks have been operational by the end of the established in 7 pilots and project Supplemental monitoring is ongoing.

Cumulative Number of Hydrometric stations Number Value 0.00 9.00 122.00 established or upgraded Sub Type Supplemental

Data on Financial Performance (as of 08-Jul-2014)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P093132 IDA-44060 Effective 27-Mar-2008 28-May-2008 26-Jun-2008 30-Jun-2013 30-Jun-2015 P093132 IDA-54450 Not Effective 05-May-2014 15-May-2018 15-May-2018 P093132 TF-56901 Closed 01-Aug-2006 01-Aug-2006 01-Aug-2006 31-May-2007 31-Aug-2007

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P093132 IDA-44060 Effective USD 65.33 65.33 0.00 61.03 2.67 93.00 P093132 IDA-54450 Not Effective USD 83.00 83.00 0.00 0.00 83.40 0.00 P093132 TF-56901 Closed USD 0.55 0.55 0.00 0.55 0.00 100.00 Public Disclosure Copy Disbursement Graph

Page 4 of 5 The World Bank Report No: ISR16205 Public Disclosure Copy

Key Decisions Regarding Implementation None at this moment.

Restructuring History Level two Approved on 13-Sep-2012

Related Projects P148595-LK: AF Dam Safety WRP - Addl Fin. Public Disclosure Copy

Page 5 of 5