(I) Basic Information S. No. Item Details 1. Name of the project/s “Hill View Garden” Housing Project, promoted by M/s Trehan Home Developer Pvt. Ltd. 2. S. No. in the schedule Category ‘B’ under item 8(a) of the schedule of Gazette Notification dated September 14th, 2006. 3. Proposed Details of Project capacity/area/length/tonnage Total Plot Area 73900 Sq. m. to be handled/command Total Built up 121471.50 Sq. m. area/lease area/number of Area wells to be drilled Flat & other 1400 Flats , community Details Center, temple Total water 1114.00 KLD Requirement STP Details 100.00 KLD Parking Details 1739 ECS

DG set Details (320 kVA x4)

4. New/Expansion/Modernization Application for Amendment in previous issued EC. 5. Existing Capacity / Area etc. - 6. Category of Project i.e. ‘A’ or ‘B’ B 7. Does it attract the general No condition? If yes, please specify 8. Does it attract the specific No condition? If yes, please specify 9. Location Plot/Survey/Khasra No. - Village 8 Mile Stone bypass Road, Village Thanda Tehsil Tijara District Alwar State Rajasthan 10. Nearest railway station/airport The proposed site is well connected through a along with distance in Kms. road network from two sides.  Railway Station is at a distance of about 26.0 km towards NE of proposed site.  Indira Gandhi International Airport is at a distance of at about 47.0 km towards NNE of proposed site.  NH-71 B is at about 4.8 Km towards North side of proposed site.  NH-8 is at about 9.1 Km towards North West side of proposed site. 11. Nearest Town, city, District Nearest habitation is Bhudli at a distance of Headquarters along with 0.25 km towards NE. distance in Kms. Nearest town-Bhiwadi at a distance of 5.50 km M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 1

towards NW. 12. Village Panchayats, Zila Village- Gaadpur, Tehsil, Bhiwadi, Distt. - Alwar, Parishad, Municipal Municipal Corporation, U. I. T. [Local body] Nagar Corporation, Local body Vikas Nyas (U.I.T). (complete postal addresses with telephone nos. to be given) 13. Name of the applicant M/s Trehan Developer Pvt. Ltd. 14. Registered Address Block 15 Plot No-1, Spring Filed Colony, sector 31 -121001 15. Address for correspondence: Name M/s Trehan Developer Pvt. Ltd Designation (Owner/ Partner/ Owner CEO) Address Block 15 Plot No-1, Spring Filed Colony, sector 31 Faridabad-121001 Pin Code 121001 E-mail [email protected] Telephone No. +91-124-43-777-27/28 Fax No. +91-124-45-139-77 16. Details of Alternative Sites The Government Body “U. I. T.,” Bhiwadi, allotted examined, if any. Location of the said land to "M/s Trehan Developer Pvt. Ltd these sites should be shown on Location of the proposed project is- a topo sheet. 8 Mile Stone Alwar bypass Road, Village Thanda Bhiwadi. 17. Interlinked Projects No 18. Whether separate application Not Applicable of interlinked project has been submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable 21. Whether the proposal involves No approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z Notification, 1991? 22. Whether there is any No Government Order/Policy relevant/relating to the site? 23. Forest land involved (hectares) No

M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 2

24. Whether there is any litigation No pending against the project and /or land in which the project is proposed to be set up? (a) Name of the court (b) Case No. (c) Orders/directions of the Court, if any and its relevance with the proposed project.

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) S. no. Information/ Checklist Yes/N Details thereof (with approximate confirmation o quantities/rates, wherever possible) with source of information data 1.1 Permanent or temporary No Land use change in land use, land The proposed site is in the developing area of cover or topography Tijara Tehsil which has mixed land use including increase in pattern of residential and commercial use. intensity of land use (with The proposed use of site is for residential respect to local land use purpose. Therefore, the proposed project will plan). not significantly differ from existing land use of locality and it will not bring any significant change in land use of locality. Yes Land cover Due to human activities, land cover is either directly affected from activity like construction of road-building leading to deforestation or indirectly from water diversion leading to lowering of the water table. The proposed project will not involve any deforestation; only small work of site clearance will be done in which some shrubs and grasses will be removed. It will be balanced by planed landscaping on the site. The excavated soil will be balanced within site by back filling. Therefore the changes will be localized and insignificant. Topography No The site is plane and will not involve any leveling activities. The proposed site does not

M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 3

involve any major natural drainage channel of locality therefore no changes in drainage pattern are envisaged. 1.2 Clearance of existing land, Yes The proposed site is not having any vegetation and buildings? structures. There are some seasonal shrubs and grasses in the proposed project site. Clearing of vegetation during the construction stage is very minimal. List of observed vegetations is enclosed as Annexure XI. This shall be compensated by planting trees in addition to shrubs. The proposed landscaping and plantation will have positive impact on the prevailing environment. Details of flora are enclosed as Annexure- XI. 1.3 Creation of new land uses? No The proposed site is located near Chowpanki Industrial Area, at a distance of about 5 km. from RIICO Chowk towards Chowpanki.The area of Tijara Tehsil has mixed land use pattern of residential and commercial use. The proposed use of site is for residential. Therefore, the proposed project will not create new land uses that significantly differ from existing land use of locality as per the master plan. 1.4 Pre-construction Yes The soil investigation was carried out. The investigations e.g. bore detailed Soil investigation report is enclosed houses, soil testing? as Annexure No XVII. 1.5 Construction works? Yes The Group Housing Project have 1400 Residential Flats, community center, & temple. 1.6 Demolition works? No The proposed site is not having any structures which will need demolition. 1.7 Temporary sites used for Yes They will be housed in temporary houses construction works or supported by flush WCs during construction housing of construction period only. workers? 1.8 Above ground buildings, Yes The proposed project maximum height of the structures or earthworks project will be 30 m (up to mumty level). including linear structures, cut and fill or excavations. 1.9 Underground works No No tunneling activity is involved. including mining or tunneling? 1.10 Reclamation works? No No reclamation works involved 1.11 Dredging? No Not involved 1.12 Offshore structures? No Not applicable 1.13 Production and No Not applicable manufacturing processes? M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 4

1.14 Facilities for storage of Yes Temporary stores or sheds will be goods or materials? constructed for storage of construction materials. 1.15 Facilities for treatment or Yes STP for treatment of sewage. STP treated disposal of solid waste or effluent will be used for gardening and liquid effluents? flushing of toilets. All excess treated water will be discharged in drains maintained by UIT after taking necessary permission from UIT. All solid waste from different sections will be collected in separate bins. The non- organic waste shall be disposed off to authorized vendors. The organic waste will be converted into manure and used within premises for green belt development. 1.16 Facilities for long term Yes Cabins for watchmen, gardeners etc and housing of operational persons engaged in essential services. workers? 1.17 New road, rail or sea No The existing infrastructure is sufficient to traffic during construction catch-up for the need of such a small project, or operation? insignificant increase in traffic for transport of men & material is envisaged. 1.18 New road, rail, air, No The proposed project site has well waterborne or other connectivity through road; rail and air- transport infrastructure transport therefore will not require any including new or altered change in existing infrastructure. routes and stations, ports, airports etc? 1.19 Closure or diversion of No No public road or infrastructure is crossing existing transport routes or within the proposed site. or infrastructure leading to changes in traffic movements? 1.20 New or diverted No No pipeline or transmission line is crossing transmission lines or or within the proposed site. pipelines? 1.21 Impoundment, damming, No The proposed site does not involve any culverting, realignment or major natural drainage channel of locality other changes to the therefore no changes in drainage pattern are hydrology of watercourses envisaged. or aquifers? 1.22 Stream crossings? No The proposed plot is small in size and no natural drain is crossing the plot. 1.23 Abstraction or transfers of Yes Water will be taken from underground water water from ground or abstraction. No ground water will be surface waters? abstracted without obtaining prior NOC from CGWA. An affidavit regarding same is attached as Annexure III. 1.24 Changes in water bodies No The excess treated water will discharged in or the land surface sewer line maintained by UIT after obtaining affecting drainage or run- necessary permission. The proposed site

M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 5

off? does not involve any major natural drainage channel of locality therefore no such changes were envisaged. 1.25 Transport of personnel or Yes During construction phase material of materials for construction, construction will be transported to site from operation or local market and other sources depending on decommissioning? availability. During operation stage the transportation activities will be due to cars, two wheelers and other vehicles of the residents. 1.26 Long-term dismantling or No Not applicable, as the land is vacant. No decommissioning or structures are present at the site; hence, no restoration works? dismantling, decommissioning or restoration work is required. 1.27 Ongoing activity during No Not applicable decommissioning which could have an impact on the environment? 1.28 Influx of people to an area Yes During construction phase, there will be in either temporarily or inward and outward movement of local permanently? labour in the construction site. However during the post construction phase, there will be regular movement of residents, visitors and other related persons. 1.29 Introduction of alien No Only the plant/ trees of local species and species? suitable for the region will be planted. 1.30 Loss of native species or No There are no grown trees on the proposed genetic diversity? site, some shrubs and grasses will be removed. The same will be amply compensated by proposed plantation and landscaping. 1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non- renewable or in short supply): S. No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 2.1 Land especially Yes The proposed site is in developing urban area undeveloped or agricultural and the site has been converted for residential land (ha) purpose by JDA and allocated to project proponent. 2.2 Water (expected source & Yes During post construction phase daily water competing users) unit: KLD requirement will be about 1114.00 KLD. 2.3 Minerals (MT) No - 2.4 Construction material – Yes The construction will involve use of Stone, stone, aggregates, and /soil Stone Grit, Sand, bricks and timber. (expected source-MT) The Stone and Stone grit is available from various queries operative around Bhiwadi City.

M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 6

2.5 Forests and timber (source Yes Timber will be obtained from authorized local –MT). timber merchant. 2.6 Energy including electricity During operation phase: 5000.00 KW and fuels (source, Yes The power will be received from JVVNL at 11 competing users) Unit: fuel KV supply voltage, it will be stepped down to (MT), energy (MW) 0.433 KV through two transformer of capacity 1750 kVA. Four D.G. Sets of capacity 320 kVA each are proposed for common facilities to cater the essential load only. 2.7 Any other natural resources Yes Solar energy will be utilized for lighting of (use appropriate standard common areas and solar water heaters for units) providing hot water to residents.

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S. No Information/checklist Yes Details thereof (with approximate confirmation /N quantities/rates, wherever possible) with o source of information data 3.1 Use of substances or No The proposed project will not use any hazardous materials, which are material. Hazardous material in proposed hazardous (as per MSIHC project will be generated only as used rules) to human health or the lubricating oil from DG Set which can cause environment (flora, fauna, health hazard. This used oil will be sold to and water supplies) authorized recyclers. 3.2 Changes in occurrence of No The project is of a building construction. The disease or affect disease waste water as well as MSW is proposed to be vectors (e.g. insect or water disposed of in appropriate manner therefore the borne diseases) project will not lead to change in occurrence of diseases or affect disease vectors. 3.3 Affect the welfare of people Yes The urban cities including are suffering e.g. by changing living from shortage of adequate and hygienic living conditions? conditions. This has resulted in mushrooming of unauthorized Colonies which lacks basic amenities. The proposed project will provide all basic amenities and hygienic and comfortable living conditions. 3.4 Vulnerable groups of people No There are a number of Schools, Colleges, who could be affected by the Hospitals etc but it is a small group housing project e.g. hospital patients, project and will not affect vulnerable group of children, the elderly etc., people. 3.5 Any other causes No -

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 7

S. No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine No Not applicable. wastes 4.2 Municipal waste (domestic Yes Segregation will be practiced at the source and commercial wastes) level itself. Dry waste will be stored in the area marked for it, from where it will be sent for further disposal. Green waste will be converted into manure along with S.T.P. sludge by Organic Waste Converter at the project site -provisions are made close to STP. A waste converter is a machine used for the treatment and recycling of solid and liquid refuse material. A converter is a self-contained system capable of performing the functions like pasteurization of organic waste, sterilization of pathogenic or biohazard waste, grinding and pulverization of refuse into unrecognizable output, trash compaction and dehydration. The manure will be used to develop the greenbelt within the premises. Area specified for waste convertor will be surrounded by fast growing and canopy forming trees. 4.3 Hazardous wastes (as per Yes Used lubricating oil from DG Set will be Hazardous waste generated during construction of the building. Management Rules) Waste oil will be properly stored and sold to authorized recyclers. 4.4 Other industrial process No Not applicable as the proposed project is of wastes construction and will not involve any industrial activity. 4.5 Surplus product No Not applicable , Residential Apartment 4.6 Sewage sludge or other Yes Dried sludge from STP will be used as manure sludge from effluent for plants after treatment. treatment 4.7 Construction or demolition Yes Construction wastes will be used for road wastes construction. 4.8 Redundant machinery or No All machinery after construction will be equipment removed from site. 4.9 Contaminated soils or other No No such material envisaged materials 4.10 Agricultural wastes No Not applicable 4.11 Other solid wastes No Not applicable

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 8

source of information data 5.1 Emissions from combustion Yes The only source of pollution will be four D.G. of fossil fuels from Sets of capacity 320 kVA each. The emissions stationary or mobile sources will be discharged through vent of proper height. D.G Set will conform to emission limits as prescribed under E P Act- 1986 and having acoustic arrangement as per EP Act- 1986. The D.G Set will carry ‘Type approval Certificate’. 5.2 Emissions from production No - processes 5.3 Emissions from materials Yes Dust will be generated during transportation handling including storage and unloading of material. The measures to or transport minimize the effects are given in Environmental Management Plan. 5.4 Emissions from Yes The measures to minimize the effects are construction activities given in Environmental Management Plan. including plant and equipment 5.5 Dust or odours from Yes The measures to minimize the effects are handling of materials given in Environmental Management Plan. including construction materials, sewage and waste. 5.6 Emissions from incineration No No such operations are envisaged. No burning of waste of waste will be practiced. 5.7 Emissions from burning of No Waste would be collected and handed over to waste in open air (e.g. slash the authorized vendor and biodegradable materials, construction waste will be converted into manure by debris) Organic Waste Converter. 5.8 Emissions from any other No - sources 6. Generation of Noise and Vibration, and Emissions of Light and Heat: S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data with source of information data 6.1 From operation of Yes but Noise generated by equipment will be equipment e.g. engines, negligible nominal. The measures to minimize the ventilation plant, crushers effects are given in Environmental Management Plan. 6.2 From industrial or similar No It is a construction project. processes 6.3 From construction or Yes But insignificant to result in any adverse demolition effect on environment. 6.4 From blasting or piling No Not involved

6.5 From construction or Yes During construction phase the noise will operational traffic be generated from movement of vehicles, M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 9

earthwork, concrete mixer etc. 6.6 From lighting or cooling No Silent generators will be used. systems 6.7 From any other sources No -

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: S. No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 7.1 From handling storage, use Yes Used lubricating oil from D.G Set will be or spillage of hazardous properly stored and sold to authorized materials recyclers. 7.2 From discharge of sewage Yes The Sewage generated will be treated and or other effluents to water handled properly to minimize the impact. or the land (expected made During construction phase septic tank soak pit and place of discharge) system would be provided and during operation phase STP would be provided. 7.3 By deposition of pollutants No The only source of air pollution will be four emitted to air into the land D.G. Sets of capacity 320 kVA each, which or into water would have vent of proper height. Beside the DG set will be housed in acoustic enclosure as per prevailing rules. 7.4 From any other sources No - 7.5 Is there a risk of long term No Not envisaged. build up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment S. No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 8.1 From explosions, spillages, No These operations are not involved. fires from storage, handling, use or production of hazardous substances 8.2 From any other causes No - 8.3 Could the project be affected Yes The site is located in the seismic zone-III, by natural disasters causing which is the zone of moderate seismic environmental damage (e.g. intensity, as per the seismic zoning map of floods, earthquakes, India given in BIS code IS: 1893(Part 1)- landsides, cloudburst etc)? 2002.As such there is no history of such disasters in the area till now. Proper safety measures as per Disaster Management Plan will be adopted to face such incidents. 9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality. M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 10

S. No. Information/checklist Yes/ Details thereof with approximate confirmation No quantities/rates, wherever possible) with source of information data 1 Lead to development of The proposed site is located near Chowpanki supporting cities, ancillary Industrial Area, at a distance of about 5 km. development or from RIICO Chowk towards Chowpanki.The development stimulated by area has well developed infrastructure and the project which could provision of proper basic amenities. have impact on the environment e.g.: This is a small project and will not exert any  Supporting No significant negative impact. infrastructure (Roads, power supply, waste or waste water treatment etc.)  Housing development  Extractive industries  Supply industries  Other 9.2 Lead to after-use of the site, No This is a construction project. which could have an impact on environment 9.3 Set a precedent for later No The project will be developed strictly as per developments JDA bye laws. 9.4 Have cumulative effects due No It is a construction project and will be used for to proximity to other non polluting activities with full civic facilities existing or planned projects like water supply, sewage treatment and with similar effects. ventilation etc.

(III) Environmental Sensitivity S. No. Areas Name/Identity Aerial distance (within 15 km.) Proposed project location boundary 1 Areas protected under No No such areas exist. international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important Rangla PF 6.40 Km towards North of project or sensitive for ecological site reasons –Wetlands, Tapkan PF 9.50 Km towards ESE of project site watercourses or other water Choharpur PF 9.50 Km towards SE of project site bodies, coastal zone, Choupank PF 2.90 Km towards SE of project site biospheres, mountains, Sarekalan PF 4.40 Km towards SE of project site forests Indaur PF 6.00 Km towards SE of project site Khori Kalan PF 7.50 Km towards SSW of project site Banvan PF 0.50 & 4.50 Km towards SW of project site

M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 11

Gondhan PF 0.50 Km towards NW of project site 3 Areas used by protected, No No such areas exist. important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or Sare Khurd 1.25 Km towards ESE of project site underground waters Canal Pond at Sare 6.75 Km towards SE of project site Khurd Water Stream 4.00 Km towards South of project Near Kori site Khurd Indauri Nalah 5.75 Km towards NE of project site 5 State, National boundaries Yes Rajasthan – interstate boundary at a distance of 2.75 km towards NE from the proposed project site. 6 Routes or facilities used by NH-71B 4.8 Km towards North of project the public for access to site. recreation or other tourist, NH-8 9.1 Km towards NW of project site. pilgrim areas 7 Defense installations - - 8 Densely populated or built- Village Seoka 3.00 Km towards North of project up area site. Town Taoura 9.00 Km towards NE of project site. Village 5.25 Km towards NE of project site. Gurnawat Village Baola 7.25 Km towards NE of project site. Village 1.50 Km towards NE of project site. Bahaduri Village Karenda 2.50 Km towards ENE of project site. Village Sikhoh 8.50 Km towards East of project site. Village Guwalda 6.50 Km towards SSE of project site. Village Sare 6.75 Km towards SE of project site Khurd Village Kori 4.00 Km towards South of project Khurd site Village 8.50 Km towards South of project Nimbaheri site. Town 7.25 Km towards SW of project site. Tapukarah Village Jhiwania 2.75 Km towards SW of project site. Village 9.50 Km towards WSW of project Nandrampur site. Bas

M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 12

Town 9.00 Km towards NW of project site. Dharuhera Village 8.25 Km towards North of project Rathiwas site. Town Bhiwadi 5.50 km towards NW of project site. 9 Areas occupied by sensitive Health Care Facility/Hospitals Facilities man-made land uses Dispensary at 9.50 Km towards WSW of project (hospitals, schools, places of Nandrampur site. worship, community Bas facilities) Veterinary At Seoka 3.00 Km towards North of Hospital project site. Hospital & At Taoura 9.00 Km towards NE of Veterinary project site. hospital Hospital & At Dharuhera 9.00 Km towards NW Veterinary of project site. hospital Veterinary At Jhiwania 2.75 Km towards SW of Hospital project site. Hospital & At Tapukarah 7.25 Km towards SW Veterinary side of project site. Hospital Hospital At Bhiwadi 5.50 km towards NW side of project site. Worship & Community Facilities Temple Post At Bhiwadi 5.50 km towards NW office & Police side of project site. Station Post office & At Taoura 9.00 Km towards NE side Temple of project site. Post Office At Jhiwania 2.75 Km towards SW side of project site. Post Office & At Tapukarah 7.25 Km towards SW police Station side of project site. School and Educational Facilities Govt. School At Bhiwadi 5.50 km towards NW side of project site. Rajkiya Ucchya At Dharuhera 9.00 Km towards NW Madhyamik side of project site. School Govt. School At Taoura 9.00 Km towards NE side of project site. Govt. School At Karenda 2.50 Km towards ENE side of project site. Govt. School At Sikhoh 8.50 Km towards East side of project site. Primary School At Nimbaheri 8.50 Km towards South side of project site.

M/s Trehan Home developer Pvt. Ltd.

Authorized Signatory 13

Rajkiya Ucchya At Tapukarah 7.25 Km towards SW Madhyamik side of project site. School 10 Areas containing important, Sare Khurd 1.25 Km towards ESE of project site high quality or scare Canal resources (ground water resources, surface Pond at Sare 6.75 Km towards SE of project site resources, forestry, Khurd agriculture, fisheries, tourism minerals) 11 Areas already subjected to No Project is coming up near the pollution or environmental Chowpanki Industrial Area, at a damage.(those where distance of about 5 km. from RIICO existing legal environmental Chowk towards Chowpanki.The standards are exceeded) Industrial area of Bhiwadi city is considered pollutant as per CEPI. 12 Areas susceptible to natural No Bhiwadi is located in semi-arid hazard which could cause region and there is no history of the project to present floods or land slide. Soil in Alwar is environmental problems generally sandy and cohesion less; (earthquakes, subsidence, mildly sloping hence there is no landslides, erosion, flooding threat of subsidence. The site is or extreme or adverse located in the seismic zone-III, climatic conditions) which is the zone of moderate seismic intensity, as per the seismic zoning map of India given in BIS code IS: 1893(Part 1)-2002.As such there is no history of such disasters in the area till now. Map of India showing seismic zones of India is enclosed as Annexure- XIX.

(b) “I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.”

Date: 15.04.017 Place: Faridabad M/s Trehan Developer Pvt. Ltd. (Block 15 Plot No-1, Spring Filed Colony, sector 31 Faridabad-121001)