Semiannual Environmental Monitoring Report

Project No. 42248-013 Loan No 2763- BAN (SF) December 2018

Second Hill Tracts Rural Development Project (CHTRDP II)

Prepared by Second Chittagong Hill tracts Rural Development Project for the Peoples Republic of and The Asian Development Bank

This Semiannual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project No. 42248-013 Second Chittagong Hill Tracts Rural Development Project

July

December 2018

Environmental Monitoring Report

0

Environmental Monitoring Report July – December 2018

2763-BAN (SF): Second Chittagong Hill Tracts Rural Development Project CHTRDP II

Project No. 42248-013

Environmental Monitoirng Report July-December 2018

Prepared by: Md.Maksudul Amin Environmental Engineer (Individual Consultant) Safeguard and Quality Monitoring Cell (SQMC) Project Management Office Second Chittagong Hilltracts Rural Development Project, for the Peoples Repulic of Bangladesh and The Asian Development Bank

1

Environmental Monitoring Report July – December 2018

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

2

Environmental Monitoring Report July – December 2018

Table of Contents Abbreviations ...... 5 Glossary ...... 6 EXECUTIVE SUMMARY ...... 7 Chapter 1 ...... 10 Introduction ...... 10 1.1 Project Background: ...... 10 1.2 Project Objectives: ...... 10 1.3 Project Output: ...... 11 1.4 Context of the Environmental Monitoring Report: ...... 12 1.5 Methodology: ...... 14 1.6 Physical Progress of Project Activities: ...... 15 1.7 Scope of the Monitoring Report: ...... 16 1.8 Change in Project Scope: ...... 16 1.9 Monitoring Requirement: ...... 16 Chapter 2 ...... 21 Environmental Monitoring...... 21 2.1 Quantitative and Qualitative Monitoring Data: ...... 21 2.2 Environmental Safeguard Issues of Rural Road Components: ...... 21 2.3 Environmental Safeguard Issues of Community Infrastructure (CI) Component: . 23 2.4 Monitoring Parameter: ...... 24 2.5 Monitoring Results and Compliance Status: ...... 25 2.6 Compliance Status with GoB Policy: ...... 29 2.7 Compliance Status of ADB Safeguard Policy Statement: ...... 29 2.8 Compliance status of Environmentally Specific Loan Covenants: ...... 30 2.9 Institutional Arrangement for Implementing EMP: ...... 32 Chapter 3 ...... 34 Tree Plantation ...... 34 3.1 Background: ...... 34 3.2 Institutional Framework of Tree Plantation: ...... 35 3.3 Species Selection:...... 36 3.4 Ownership of Planted Trees: ...... 36 3.5 Action Plan: ...... 36 3.6 Plant Nursing: ...... 37 Chapter 4 ...... 38 Result and Corrective Action Plan ...... 38 4.1 Result: ...... 38 4.2 Corrected Action Plan: ...... 39 Chapter 5 ...... 42 Conclusion and Recommendations ...... 42 5.1 Conclusion: ...... 42 5.2 Recommendation: ...... 43 APPENDIX ...... 45

3

Environmental Monitoring Report July – December 2018

Appendix 1: Physical Progress of Rural Road Component ...... 45 Appendix 2: Physical Progress of CI Component ...... 54 Appendix 3 : Physical Progress of MAD Component ...... 100 Appendix 4: Site Specific Environmental safeguard Issues of rural Roads Component ...... 103 Appendix 5: Site Specific Environmental Safeguard Issues of Community Infrastructure Component ...... 114 Appendix 6:EMP implementation Status of Rural Road Component ...... 116 Appendix 7: EMP Implementation Status of CI Components ...... 121

List of Tables: Table 1: Monitoring Requirement 17 Table 2: Summery of environmental safeguard issues of rural road 21 Table 3: Environmental Safeguard Issues of CI Components 23 Table 4: Summery of the EMP implementation status of rural road component 26 Table 5:Summery of the EMP implementation Status of CI component 28 Table 6: Environmental Compliances Status with Policy of GoB 29 Table 7: Compliance with Environmentally Specific Loan Covenants 30 Table 8: Institutional Responsibility Matrix of EMP 32 Table 9: Subproject Wise for Tree Plantation 34 Table 10: Action Plan for Tree Plantation 36 Table 11: Corrective Action Plan 39

4

Environmental Monitoring Report July – December 2018

Abbreviations

ADB : Asian Development Bank CHT : Chittagong Hill Tracts CHTDB : Chittagong Hill Tracts Development Board CHTRC : Chittagong Hill Tracts Regional Council CHTDF : Chittagong Hill Tracts Development Facility CHTRDP-I : Chittagong Hill Tracts Rural Development Project CHTRDP-II : Second Chittagong Hill Tracts Rural Development Project CDC : Community Development Committee CI : Community Infrastructure CPTU : Central Procurement Technical Unit DPD : Deputy Project Director DPMO : District Project Management Office DPP : Development Project Proforma GC : Growth Centre GoB : Government of Bangladesh HBB : Herring Bone Bond HDC : Hill District Council HQ : Headquarters IEE : Initial Environmental Examination IP : Indigenous People IPP : Indigenous People Plan LAR : Land Acquisition and Resettlement LARF : Land Acquisition and Resettlement Framework LCS : Labour Contracting Society LGED : Local Government Engineering Department MAD : Micro Agribusiness Development MoCHTA : Ministry of Chittagong Hill Tracts Affairs NGO : Non-Government Organization O&M : Operation and Maintenance PAM : Project Administration Manual PIC : Project Implementation Consultants PD : Project Director PDC : Para Development Committee PMO : Project Management Office RCC : Reinforced Cement Concrete SDS : Survey, Design and Supervision SIEE : Summary Initial Environmental Examination SQMC : Safeguards and Quality Monitoring Cell SPS : Safeguard Policy Statement UNDP : United Nations Development Programme UP : Union Parishad

5

Environmental Monitoring Report July – December 2018

Glossary

Chittagong Hill : Chittagong Hill Tracts Regional Council is a statutory apex body Tracts Regional of the Chittagong hill tracts and consist of a chairman, fourteen Council tribal members; seven non-tribal members; chairmen of the three hill district councils (ex-officio).

Circle : Chittagong Hill Tracts are sub-divided into three units based on ethnic domain. Each unit is called circle.

Circle Chief : Circle Chief is an administrative head of a circle responsible for the administration of “tribal” justice and customary laws of the hill people, for revenue administration.

District : Administration unit headed by district commissioner comprising a number of .

Hill District Council : Hill District Council is a statutory body and consist of a chairman, twenty tribal members, and ten non-tribal members.

Headman : Headman is the mouza chief and responsible for the administration of “tribal” justice and customary laws of the hill people, for revenue administration within a Mouza.

Karbari : Karbari is the local level leadership in the Chakma justice system. Karbari assists the headmen in the judicial process.

Mouza : Mouza is composed of several villages. Mouza is officially called as Revenue Village.

Para : Administrative unit (sub-division of union).

Union : Union is an administrative unit and a subdivision of .

Union Parishad : Local government institution at union level. Union parishad consists of an elected members and chairman, and is the oldest government institution in Bangladesh.

Upazila : Upazila is an administrative unit and a sub-division of district (zila).

Upazila Parishad : Local government institution at upazila level. The upazila parishad consists of an elected chairman, two vice-chairmen (one male and one female), and ex-officio members of chairmen of union parishads.

6

Environmental Monitoring Report July – December 2018

EXECUTIVE SUMMARY

1. The Government of Bangladesh (GoB) has obtained a loan from Asian Development Bank (ADB) for financing Second Chittagong Hill Tracts Rural Development Project. Total cost of the project is $70.80 million, out of which $55.00 million is financing by ADB, $14.40 million by GoB financing and $1.40 million by the local beneficiaries. The project has been started since January 2012. Though it is expected that it will be accomplished by 30th June 2019 but considering the field difficulties it is decided to extend the completion of the project period up to 30th June 2020.

2. The Project’s impact is to increase rural household incomes in subproject areas in Chittagong Hill Tracts and its outcome is increased income-generating opportunities for people in subproject areas. The Project comprises five main outputs - (i) institutional development and capacity building, (ii) upgraded 166 km of rural roads, (iii) development of community infrastructure in 600 villages, (iv) sustainable micro agribusiness development in 9 upazilas, and (v) efficient project management operationalized. Ministry of Chittagong Hill Tracts Affairs is the executing agency, the Chittagong Hill Tracts Regional Council is the lead implementing agency, and the Local Government Engineering Department is the implementing agency for the rural road component.

3. In compliance with the loan covenant, this semestral environmental report has been prepared. This report describes the status of implementation and compliance of the Environmental Management Plan (EMP) to satisfy the environmental safeguard requirements of ADB and GoB as well as to fulfil the requirements mentioned in the loan document. This report also describes the environmental mitigation related any corrective and preventative actions with respect to each subproject for the period from July to December 2018.

4. The SQMC consultant has visited all the packages of contracts for the upgrading works of roads under rural road component and 23 completed and ongoing development works of community infrastructure subprojects. This report comprise of post monitoring of CI component in most cases and regular monitoring of rural road and micro agree business development

7

Environmental Monitoring Report July – December 2018

component. The major environmental concerns for the improvement of rural road and community infrastructure subprojects are – threat of hill slide due to steep cut of hill, drainage congestion due to unstable and improper management of excavated soil, soil erosion and sedimentation, slope instability, topsoil disturbance, disturbance of vegetation, degradation of surface water, soil induced dust pollution, threat of faecal coliform contamination in drinking water from GFS, tube well, and dug well. Besides these, occupational health and safety issues are also very concern factor along with management of used engine oil drained from the power pumps and power tillers. The slope maintain during cutting of hill is not maintained. The contractors are not very aware regarding the environmental issues. Protection of vegetation, direct loss of trees are considered by the contractors sometimes.

5. The environmental mitigation measures during the pre-construction stage of all sub projects was satisfactory. Checking of environmental mitigating infrastructure design in all rural road improvement subprojects and CI components have been done effectively during design and pre- construction stage. In all subprojects, environmental issues have been identified and EMPs have been prepared as a part of feasibility study report; and incorporated in bidding documents and contracts.

6. Contractor’s obligations in respect of implementation of EMP is partially satisfied with a lot of dissatisfaction. It might be happen that the contractor are not aware or capable to handle the environmental issues. Majority of contractors did not provide personal protective equipment - like face masks, hand gloves, helmets, high visibility clothing etc. to their workers; and first aid box with medicines was not available most of the worksites.

7. Primarily, about 91 hill spot has been identified for hill slide mitigation measures along the road side in which Rangamati (Kawkhali 18, Kaptai 12, Baghaichori 03) has 33 spots , Bandarban (Sadar 12, Naikhongchari 23, Alikadam 08, Lama 14) has 57 spots and Khagrachori (Guimara 01) has 1 spot. It is found that Natural water canal i.g. chara is getting congested by the huge amount of excavated soil dumping in some places of Lama and Alikadam Upazila. It is found some water point close to the latrine pit which did not maintain the safe distance of Bangladesh standard i.e. 30 feet. It is suggested to test faecal coliform of all water (tube well, Gravity flow

8

Environmental Monitoring Report July – December 2018

system) source. Farmers are using Pheromone trap for eggplant cultivation but it is not replicated as desired. The farmer change engine oil after 72 hours of engine running but they did not dispose the lubricants properly following the compliance. The drainage facilities of market shade is not found appropriate which may lead to create mud in front of shed. Filled loose earth was observed along the side slopes. This loose earth is vulnerable for soil erosion, which leads to deposition of sedimentation over the adjacent agricultural lands. Side slopes of the road embankments were not compacted. Moreover, at some sections steep slopes were observed.

8. A corrective action plan and some recommendations have been suggested in this report. It is expected that LGED district offices and DPMOs will implement the corrective action plan and recommended monitoring adjustment measures; and will be able to demonstrate a substantial improvement, which will be focused in the next report.

9

Environmental Monitoring Report July – December 2018

Chapter 1 Introduction

Project Background:

9. The Government of Bangladesh (GoB) has obtained a loan from Asian Development Bank (ADB) for financing Second Chittagong Hill Tracts Rural Development Project. Total cost of the project is $70.80 million, out of which $55.00 million is financing by ADB, $14.40 million by GoB financing and $1.40 million by the local beneficiaries. The project has started its implementation from January 2012. Though it is expected that it will be accomplished by 30th June 2019 but considering the field difficulties it is decided to extend the completion of the project period up to 30th June 2020.

10. Poverty alleviation is the significant activities of RD&I sector. The project aims at reducing incidence of absolute poverty among the rural CHT people through undertaking community infrastructure, rural access development activities, & expanding income through micro agri- business development in the CHT Region. The CHT region lags behind in every aspect compared to other parts of the country. The project has link with ADB assisted recently completed Chittagong Hill Tracts Rural Development Project (CHTRDP). Also the UNDP’s Promotion of Development and Confidence Building in CHT region (referred to as CHT. Development Facility (CHTDF), DANIDA’s Hygiene Promotion, Sanitation & Water Supply (HYSAWA) and other agencies like as the United Children Fund (UNICEF) assisted Integrated Community Development Project (ICDP) are also working in the region on rural & social development and community empowerment.

1.2 Project Objectives:

11. The Project’s impact is to increase rural household incomes in subproject areas in Chittagong Hill Tracts (CHT) and its outcome is increased income-generating opportunities for men and women in subproject areas. The main objectives of the project are as follows:

10

Environmental Monitoring Report July – December 2018

(i) To contribute to a reduction in the incidence of poverty among the rural population of the CHT region and provide suitable implementation arrangements to underpin the CHT Accord and strengthen key institutions to help meet their mandated role.

(ii) To increase employment and income generating opportunities for the population through community participatory subproject development.

(iii) To promote and increase of small agri-business opportunities through stimulating agriculture production & facilitating marketing of high value environmentally friendly crops in the Chittagong Hill Tracts region.

(iv) To increase economic opportunities for rural poor, especially women, vulnerable groups and IP communities through community infrastructure development activities &construction of feeder roads including appurtenant structures.

(v) To improve watershed conditions, especially soil erosion and water conservation that will underpin the investments made in water and land improvements; and

(vi) To support institutional strengthening of MOCHTA, CHTRC and HDC to plan implement and monitor sustainable rural development in the three districts of Chittagong Hill Tracts i.e. Rangamati, Khagrachari and Bandarban).

1.3 Project Output:

12. The Project comprises five main outputs -

(i) Institutional Development and Capacity Building, comprising capacity building and training of executing agency, implementing agencies and relevant NGOs in the areas of indigenous peoples and safeguards issues, village mapping, and project management and organizational enhancement;

(ii) Rural Roads comprising improvement of 105 kilometres union roads and 61 kilometres upazila roads, construction of 3,884 meters bridges and culverts; and the extension of 3 functional buildings for LGED’s district office;

11

Environmental Monitoring Report July – December 2018

(iii) Community Infrastructure, comprising construction of 92 kilometres village access roads between and within villages and 100 market sheds, improving small-scale irrigation and water supply in up to 600 villages and participatory watershed management interventions in 6 sample watersheds;

(iv) Micro Agribusiness Development, comprising capacity building in relation to identification and exploitation of potential high-yield commodities, establishment of common interest groups to market commodities and improving cultivation of high-yield commodities in 9 upazilas; and

(v) Project Management, comprising establishment and operation of the PMO, the DPMOs and the PD (Roads) Office, provision of technical and implementation expertise from project implementation consultants, and establishment and operation of a safeguards and quality monitoring cell within the PMO.

1.4 Context of the Environmental Monitoring Report:

13. ADB affirms that environmental and social sustainability is a cornerstone of economic growth and poverty reduction in Asia and the Pacific. ADB’s Strategy 2020 therefore emphasizes assisting DMCs to pursue environmentally sustainable and inclusive economic growth. In addition, ADB is committed to ensuring the social and environmental sustainability of the projects it supports. ADB adheres to the objectives of the safeguards and their delivery. ADB assumes the responsibility for conducting due diligence and for reviewing, monitoring, and supervising projects throughout the ADB’s project cycle in conformity with the principles and requirements embodied in the SPS. The SPS of ADB is comprised of three following key areas:

i. Environmental safeguards,

ii. Involuntary resettlement safeguards,

iii. Indigenous Peoples safeguards.

12

Environmental Monitoring Report July – December 2018

The main objective of Environmental Safeguard is to ensure the environmental soundness and sustainability of projects and to support the integration of environmental considerations into the project decision-making process.

14. According ADB’s Safeguard Policy Statement it is clearly mentioned that the borrower/client will monitor and measure the progress of implementation of the EMP. The extent of monitoring activities will be commensurate with the project’s risks and impacts. In addition to recording information to track performance, the borrower/client will undertake inspections to verify compliance with the EMP and progress toward the expected outcomes. For projects likely to have significant adverse environmental impacts, the borrower/client will retain qualified and experienced external experts or qualified NGOs to verify its monitoring information. The borrower/client will document monitoring results, identify the necessary corrective actions, and reflect them in a corrective action plan. The borrower/client will implement these corrective actions and follow up on these actions to ensure their effectiveness.

15. The borrower/client will prepare periodic monitoring reports that describe progress with implementation of the EMP and compliance issues and corrective actions, if any. The borrower/client will submit at least semiannual monitoring reports during construction for projects likely to have significant adverse environmental impacts, and quarterly monitoring reports for highly complex and sensitive projects. For projects likely to have significant adverse environmental impacts during operation, reporting will continue at the minimum on an annual basis. Such periodic reports will be posted in a location accessible to the public. Project budgets will reflect the costs of monitoring and reporting requirements.

16. In compliance with the loan covenant, semestral environmental monitoring report is essential. This report describes the status of implementation and compliance of the EMP to satisfy the environmental safeguard requirements of ADB and GoB as well as to fulfil the requirements mentioned in the loan document. This report also describes the environmental mitigation related any corrective and preventative actions with respect to each subproject for the period from July to December 2018.

13

Environmental Monitoring Report July – December 2018

1.5 Methodology:

17. Several type of tools are considered to prepared this semi-annual environmental monitoring report. Field visit with direct observation is the key means to gather information. Several field visit has been made to understand the situation of implementation activities through the lens of environmental safeguard. Beyond the direct field observation, random performance checks, reviewing records and document, meeting minutes, field book and consultation with relevant stakeholders such as affected persons, beneficiaries, Para Development Committee (PDC), local union parishad representative. Focus group discussion with woman group and tea stall consultation were very effective means to get the information. Project Implementation Consultant (PIC), Project Management Office (PMO) and Local Government Engineering Department (LGED) at different levels are also consulted. The following environmental issues have been considered to develop this environmental monitoring report.

 Soil impacts (loss of top soil, soil quality, etc.)  Impact upon landscape and topography;  Dust, air and water pollutions;  Drainage congestions at bridge/culvert/ diversions and other locations;  Removal of trees/vegetation;  Disruption of watersheds and catchments;  Disruption of fish/wildlife habitats;  Loss of land, household and commercial structures;  Impacts upon community and occupational health;  Risks of worker and road accidents;  Disruption of existing infrastructure (water supply, sanitation, power lines, telephone lines, etc.)

18. As a part of the project management support, consultant of the safeguards and quality monitoring cell (SQMC) provides inputs on intermittent basis to monitor compliances with environmental safeguards to ensure that the project is implemented with due concern for environmental safeguards according to the ADB’s Safeguard Policy Statement 2009, specifically to ensure that these issues are adequately addressed to the requirements of ADB.

14

Environmental Monitoring Report July – December 2018

1.6 Physical Progress of Project Activities:

19. The most construction work is under the rural roads (RR) component and LGED is the implementer of this component. Three functional building in three hill districts have been completed. LGED has been spilt the total road construction work into 62 packages for effective implementation and management. Among the packages, 19 is under Rangamati district (31.22 km road and 579 m bridge), 33 in (37.69 km road and 1209.30 m bridge) and 9 in Khagrachari district (16.74 km road and 224.75 m bridge). Among the 9 packages of Khagrachari district 5 package is done completely, 3 packages have above 80% progress and only one project having the progress of 50%. The average progress is 88%. In Rangamati, 60% is average progress and 60% average progress is also happened in Bandarban. Out of 9 package in , the progress of 3 package is abut to 30% only. Again, in Bandarban Sadar Upzila the progress of 3 packages is 33% where total package is only 7. Out of 7 packages in Baghaichari Upazila, the progress of 4 packages is only 15%. (please see Appendix 1 for detail progress report).

20. Under the community infrastructure (CI) component, there are 201 subproject is under Khagrachari district in which 185 project has been accomplished and only 16 project is in progress. The ongoing project have comprised of 2985 meter irrigation canal, 55 meter stair case, 28 shallow tube well, 38 deep tube well, 13 power tiller and 2 gravity flow system. In Rangamati district, out of 195 subprojects, 189 is accomplished. The ongoing subprojects are installation of 4 deep tube well, distribution of 14 power tiller, 23 pump machine, installation of 1 water distribution system, construction of 1 dug well, construction of 1 market shed and 3 km HBB road construction.. In Bandarban district, out of 215 subprojects, 195 is completed and 20 is in progress. The ongoing subprojects are consruction of 510 meter stair case, 60 meter u-drain, installation of 16 deep tube well, distribution of 6 power tiller, 5 pump machine, installation of 5 water distribution system, construction of 3 dug well, and construction of 7 market shed with public toilets. (Please see Appendix 2 for detail progress report)

21. In Micro Agree-business Development component, formation of 900 farmer group and 90 agree business group has been established where progress is 100%. The progress of vegetable

15

Environmental Monitoring Report July – December 2018

farming is 25.58%, Medicinal plant 31.62%, Fisheries 45.19%, Orchard fruit garden 76.18% and orchard nursery is 100%. (Please see Appendix 3 for detail progress report)

1.7 Scope of the Monitoring Report:

22. The scope of this report is to assess the status of implementation and compliance of the EMPs of each subprojects of improvement of rural roads (upazila and union connecting roads) and development of community infrastructures, where the construction works have been started and completed, to satisfy the environmental safeguard requirements of ADB and GoB as well as to fulfil the requirements mentioned in the loan document. This report also addresses the environmental mitigation related any corrective and preventative actions with respect to each subproject for the period from July to December 2018 and onward.

1.8 Change in Project Scope:

23. Cost of rural roads improvement including construction of ancillary structures under rural road component, and market sheds under CI component have been increased substantially. Therefore, the target of upgrading 105 km of union and 61 km of upazila (subdistrict) roads, construction of 3,884 meters ancillary structures, and 100 market sheds will not be achieved within the available budgetary allocation. So, the Project implementing authorities have proposed to refix project scope as upgrading 54.50 km of union roads, 30.50 km of upazila roads, construction of 2300m ancillary structures, and 24 market sheds.

1.9 Monitoring Requirement:

24. The project falls under “B” category according to ADB Safeguard Policy Statement, 2009 and “Orange B” category in accordance with the Bangladesh Environment Conservation Act 1995 and Environment Conservation Rules 1997. All rural road subprojects require an IEE; but many community infrastructure development subprojects have minimal impacts, where a desk review is adequate. IEE as a part of the subproject feasibility report for each subproject, commensurate with

16

Environmental Monitoring Report July – December 2018

the degree of environmental impacts has been prepared by the implementing agencies including EMP and included in all contracts let. These are consistent with GoB and ADB requirements.

25. Monitoring parameters vary depending upon nature of the project. CHTRDP-II is a rural development project comprising improvement of rural road subprojects from earthen surfacing to brick pavement surfacing and existing damaged brick pavement surfacing to bituminous surfacing, construction of small bridges and culverts, stairs on hill slope, installation of tube/ring wells, supply of small power pumps and power tillers for improved agriculture in the hilly rural area. In each of the subproject feasibility report on rural road improvement and community infrastructure development, an EMP has been included, where mitigation measures have been commensurate with the degree of environmental impacts. Environmental monitoring requirements required for this project is presented in Table 1 as follows:

Table 1: Monitoring Requirement

Factor Monitoring Timing Trigger Response Activities Clearing Clearing Following Clearing undertaken Undertake corrective vegetation surveys clearing beyond approved actions extents observed

Tree felling Tree felling and Following Tree felling beyond Record actual number and replantation tree felling approved extents of tree felling for Re-planation surveys and tree and not payment of replantation implemented the compensation to the tree replacement affected persons and project policy implement ten for one observed tree replacement project policy Topsoil Visual During Improvement of Undertake corrective saving observations improvement subproject actions and reuse of disturbed of undertaken without topsoil subproject saving stripped topsoil observed

Drainage Visual During rainy Disposal of debris Built drainage structure congestion observations season and diversion cause to drain out the rain of drainage drainage congestion water

17

Environmental Monitoring Report July – December 2018

Factor Monitoring Timing Trigger Response Activities . congestion in rainy season and carry out the observed disposal of debris at sites identified for the purpose Soil erosion Visual Following Sedimentation Stack construction and observations rains occur from the materials together, sedimentation of erosion and and floods exposed earth and fence them by brick or deposition of stock piled areas earth walls and keep sedimentation near stream in road away from water bodies improvement works and drainage lines; and observed cover exposed earth surface by turf. Slope Visual During Cutting toe of hill Construct toe walls, stability observations preparation and filling roadsides guide walls, of cutting toe of of road without proper appropriate drainage hill and filling subgrade compaction for structures, and maintain roadsides widening the exiting standard hill slopes as without roadway observed per requirements and compaction cover with vegetation. for widening the exiting roadway

Surface Visual Twice per Worksites wastes, Determine the contents water. observations year effluents and other of dissolved oxygen of worksite contaminant (DO), acidity (pH), wastes, causing degradation biological oxygen effluents and of surface water demand (BOD), and other observed suspended solids (SS) contaminant standard limit from the surface water causing samples; undertake degradation corrective action if of surface water exceeds national

Ground water Measuring Once per Exceed national Adopt method to purify quality presence tube standard level water for domestic use of arsenic (As), well & ring that is easy and iron well affordable to the (Fe), manganese community (Mn), chlorides (Cl), sulphate (S), acidity

18

Environmental Monitoring Report July – December 2018

Factor Monitoring Timing Trigger Response Activities (pH), total dissolved solids (TDS) in water of installed tube wells and ring wells Noise: Measuring During Exceed acceptable Undertake corrective shrillness shrillness operation of level action of sound of sound (dBA) construction of equipment construction equipment Fertility of Visual Twice per Decreasing soil Determine the contents Soil observations year fertility observed of silt, clay, organic of decreasing adjacent to the road carbon, total nitrogen, . soil sides exchangeable fertility magnesium, exchangeable sodium, exchangeable calcium, exchangeable potassium, cation exchange capacity, phosphorus, and soil pH; adopt acceptable method to prevent deceasing the level of soil fertility. Air pollution Visual dust Daily Excessive dust Control dust by observations plumes observed spraying water

Traffic Observation of During Potential risk and Traffic signs/signals management traffic flow construction lack of public safety should be provide; and and safety without and generate from vehicles moving potential risk operation vehicles moving including and observed transportation of lack of public equipment and safety construction materials generate from without causing any vehicles moving potential risk should be ensured.

19

Environmental Monitoring Report July – December 2018

Factor Monitoring Timing Trigger Response Activities Hazardous / Transportation Weekly Spillage and Ensure to store chemical and leakage of hazardous materials on waste storage of combustible and top of sealed plastic combustible and toxic materials sheets in a secure, toxic materials observed flat enclosed area at such least 20m from any as petrol, diesel, watercourse; and used oil lubricants and oils shall and lubricants be collected and observations disposed of or recycled without causing pollution or a hazard to worker safety Health and Observation of Daily Workers working Ensure to provide Safety for workers without PPE necessary PEE to workers working observed workers and their use wearing health during working hours safety gear i.e. personal protective equipment (PPE)

The frequency of submission of the Environmental Monitoring Report is defined in the loan agreement that the borrower will prepare environmental semi-annual monitoring reports, which will be described progress with implementation of the EMP and compliance issues including corrective actions, if .

20

Environmental Monitoring Report July – December 2018

Chapter 2 Environmental Monitoring

2.1 Quantitative and Qualitative Monitoring Data:

26. The extent of the environmental impacts is determined in qualitative term by field visits and visual inspection. On the other hand, the extent impact of environmental pollution related to surface water, ground water, air quality, noise, and soils is determined in quantitative terms by sampling a range of related parameters as well as visual inspection by field visits.

2.2 Environmental Safeguard Issues of Rural Road Components:

27. During the reporting period I have visited all the packages of rural road component, 23 packages of community infrastructure component and some sites of micro agriculture business development component. Some of the packages of rural road component have completed and ready for tree plantation. Other packages are comprised of box cutting, earthen road surfacing to brick pavement surfacing and existing damaged brick pavement surfacing to bituminous surfacing, construction of bridges and culverts. Contract wise field visit observations on the environmental safeguard issues rural road component are presented in Appendix 4 and their summary is given in Table 2 as follows:

Table 2: Summery of environmental safeguard issues of rural road Environmental Parameter Environmental Safeguard Issues Recommendation Observed Congestion of Natural Soil excavated for road Contractor should carefully Canal construction and bridge handle the soil mass to dump construction have dumped considering the cumulative besides the road. Huge amount of impact of the soil. It should soil have directly narrow the immediate remove from the water flow path in various project area to make ensure the water site and sometimes make obstacle flow. of natural flow. It will be sever during the rainy season.

21

Environmental Monitoring Report July – December 2018

Inappropriate slope Hill slope is not maintain as It is suggested to maintain the management recommended in BoQ which will slope mentioned in the BoQ. increase the risk of land slide. Threat of Hill slide It seems to me that the slope Detail site specific slope mentioned in BoQ is not protection/mitigation sufficient to protect the slides measures should be identified considering the rainfall amount and implementation the and intensity along with the type measures as early as possible. of soil. Moreover, due to not It is my observation that one maintain the recommended slope single measures is not the threat of land slide is sufficient to mitigate the risk increased as it is very steep. of land slide. Soil dust pollution There is no water spray found Contractor should follow the during field visit in any safe guard rules and EMP for construction work. Huge amount construction work and spray of soil dust found in road which water to minimize the dust disturb the nearby house hold and pollution. adjacent school/madrasha and community places. Loss/Hamper of Soil dumping due to box cutting It is a matter of awareness vegetation of road construction hampered that the other side of paddy the adjacent paddy field. filed there are sufficient space and contractor should dump the excavated soil in that side. Soil erosion and Loose soil are dumped in the road It is suggested to compact to sedimentation side which have no compaction. soil properly and make During the rainy season all loose vegetation/turfing on slope to soil travel to the down stream and reduce the erosion. cover the top soil of agricultural land. Occupational health and Occupational health and safety It is suggested to maintain safety measures are not followed except minimum safety measures the visitors hours of high official. which is very risk for health like safety shoes, gloves etc. Hazardous and chemical It is found that the burnt engine It is need to inform the user to waste oil from power tiller and water recycle it or dumped it pump is not dumped properly. properly according to the guideline. Noise pollution/shrillness No such kind of even found. No action need to take place. of sound Air pollution from Smoke and emission of carbon It is suggested that at least the bitumen burning dioxide is found during melting of smoke does not directly bitumen for road construction. hamper the human being. It is also suggested that no timber is use for burning.

22

Environmental Monitoring Report July – December 2018

Traffic problem due to No traffic congestion found due Water spray is suggested road construction work to construction work but people during dry season and feel disturb due to soil dust of alternative walking way road construction and mud during should introduce in risky rainy season. places of road by providing brick cheap or brick. Impact on Sacred land It is found that a sacred land near A boundary wall may provide (temple and graveyard) Ruma bridge is hampered due to besides the sacred land to dust pollution and noise pollution protect it from noise and dust. form vehicle.

2.3 Environmental Safeguard Issues of Community Infrastructure (CI) Component:

28. Most of the CI component has been completed. I have visited about 23 completed CI components like market places, water supply system (dug well and GFS), upgrading of village access roads/footpaths from earthen surface to brick pavement, construction of small footbridge, culverts, stairs on hill slopes, lined irrigation canals, power pumps and power tillers for improved agriculture in the hilly rural area. I did not visit any ongoing project. So it is the post environmental monitoring. The detail are presented in Appendix 5 and their summary is given in Table 3 as follows:

Table 3: Environmental Safeguard Issues of CI Components Environmental Parameter Environmental Safeguard Issues Recommendation Observed Threat of Faecal coliform In GFS (Gravity Flow System) It is suggested to water quality in water supply project of and Dug well it seems to me that test of mentioned water supply CI component there is possibility of technology and the tube well contamination of faecal coliform where distance between tube in water supply. well and latrine pit is not maintain the national standard i.e. 30 feet. Hazardous and chemical It is found that the burnt engine It is need to inform the user to waste oil from power tiller and water recycle it or dumped it pump is not dumped properly. properly according to the guideline. Noise pollution/shrillness No such kind of even found. No action need to take place. of sound

23

Environmental Monitoring Report July – December 2018

Slipping risk Some staircase found covered Community people should with mud which have a potential make it clean. to slipping. Lack of maintenance GFS Due to appropriate maintenance It is suggested to regular lead to different type of the water supply system (GFS) maintenance of the relevant pollution may lead to contamination. structure to avoid risk and pollution.

29. Quantitative monitoring data of surface water, noise (shrillness of sound) and soils (fertility of soil) related to environmental pollution for upgrading of rural roads and construction of bridges are equipment based and requires money. Till now the implementing agency (LGED) did not make any provision to monitor these parameters. The monitoring of ground water quality under community infrastructure component has been conducted and its quantitative data of arsenic (As), iron (Fe), manganese (Mn), chlorides (Cl), acidity (pH), and total dissolved solids (TDS) are were included in previous report (EMR: Janu-June, 2017). The field observation and practice of water supply along with maintenance of different technology particularly GFS and dug well have a potential threat of faecal contamination hence need to water quality test.

2.4 Monitoring Parameter:

30. For effective monitoring, environmental parameters have been identified as indicators which are qualitatively and quantitatively measured and compared over a period of time in order to assess the compliance to EMP. The parameters, which are identified as performance indicators, are (a) compliance with environmental management and monitoring plan; (b) compliance to national environment conservation rules; (c) monitoring of ambient surface water quality, ground water, noise levels (shrillness of sound), and soil (fertility of soils) and comparison with baseline environmental quality and national standards. As rural development project has no significant impact on air quality, monitoring of this parameter is dropped.

31. Parameter of shrillness of sound is dBA; parameters for fertility of soils are silt, clay, organic carbon, total nitrogen, exchangeable magnesium, exchangeable sodium, exchangeable calcium, exchangeable potassium, cation exchange capacity, phosphorus, and soil pH have been identified;

24

Environmental Monitoring Report July – December 2018

and parameters for surface water such as dissolved oxygen, acidity, biological oxygen demand, and suspended solids have also been identified for upgrading of rural roads and construction of bridges under rural road component. These parameters are not monitor due to lack of money as mentioned in para 30 above.

2.5 Monitoring Results and Compliance Status:

32. The implementation status of the environmental mitigation measures during the pre- construction stage of all sub projects was satisfactory. Checking of environmental mitigating infrastructure design in all rural road improvement subprojects has been done effectively during design and pre-construction stage in association with Survey Design and Supervision (SDS) consultants, and Deputy Team Leader of PIC. In this stage, Executive Engineers of the respective LGED district have checked the present subprojects environmental settings and identified the problems that might be occurred during construction and selected mitigation measures with implementation procedures in consultation with the community.

33. Similarly, checking of environmental mitigating infrastructure design in all community infrastructure subprojects has been done during design and pre-construction stage by the Deputy Team Leader of the PIC. In this stage, Deputy Project Directors of the respective DPMOs have checked the present subprojects environmental settings and identified the problems that might be occurred during construction and selected mitigation measures with implementation procedures in consultation with PDC of the respective para/village and community.

34. In all rural road subproject, probable occupational health and safety issues in relation to development of the subprojects were considered and incorporated into the contract documents; but the extent of the impacts of environmental pollution monitoring related to surface water, noise, and soil were not considered by the implementing agency (LGED).

35. In community infrastructure component, environmental issues have been identified and EMPs have been prepared as a part of feasibility study report; and EMPs were incorporated in the bidding documents and contracts.

25

Environmental Monitoring Report July – December 2018

36. Construction of retaining walls and toe walls to prevent potential erosion of the road embankment as well as to limit the potential siltation of streams/ water bodies, catch drain to collect run-on from hill, adequate crossroad and road surface drainage to ensure storm runoff for preventing damage to the road and down slope features, cross-fall drains and lined side drains to direct runoff of the road surface have been provided as an environmental impact mitigating measures for upgrading rural roads and included in the BoQ. Re-vegetation/turfing over disturbed soils to prevent soil erosion and compensatory plantation were not included some in some of subprojects. Subproject wise EMP implementation status of upgrading rural road subprojects is presented in Appendix 6 and their summary is presented in Table 4 as follows:

Table 4: Summery of the EMP implementation status of rural road component Potential Proposed Actual Recommended Compliance Impacts Mitigation Implementation Actions Status measures as per EMP Air Pollution Earth No water spray Truck carrying earth, Not complied. due excavation and to reduce dust. sand, brick chips and to dust generates construction No use of stone chips should be during sites will tarpaulins or covered with construction and be water cover to tarpaulins or other carrying sprayed to minimize the materials. construction minimize dust. spillage and dust materials Trucks carrying pollution construction materials (such as earth, sand or stone) will be covered with tarpaulins to avoid spillage Congestion of Compaction of No compaction Immediate action Not complied. the path of soil to protect found and no should take to natural water erosion. turfing work is remove the flow by Maintain the progressed. congestion along dumping of soil Road side slope with provide turfing besides the road and provide the to prevent erosion. appropriate turfing.

26

Environmental Monitoring Report July – December 2018

Potential Proposed Actual Recommended Compliance Impacts Mitigation Implementation Actions Status measures as per EMP Potential threat Hill cutting Slope is not Detail site specific Not complied of hill slide due slope is maintained slope to abrupt mentioned in properly. protection/mitigation manner of the BoQ (1:1) measures should be cutting. to protect the identified and land slide. implementation the measures as early as possible. It is my observation that one single measures is not sufficient to mitigate the risk of land slide. Inappropriate Appropriate Maintain only It is suggested to Complied implication of occupational when visitors maintain minimum partially. occupational health and visit. safety measures health and safety measures which is very risk for safety may are suggested health like safety injury the to use. shoes, gloves etc. workers. Need for Contractors Some Contractor should Complied accommodation, will build contractors have provide workforce partially. safe drinking construction not provided camp including water and shed for the workforce supply of drinking sanitation for workers of the camps, drinking water and toilet the Subproject and water supply and facilities near the workers. will arrange toilet facilities camp. safe drinking near the camps. water and sanitation for the workers.

37. The major activities under the community infrastructure component are construction of irrigation canal, installation of deep tube well, installation of shallow tube well, production well for irrigation, dug well, distribution of power tiller and power pump and installation of gravity flow system. From the perspective of post monitoring view, it is found that most of the stair case covered with soil which have a treat of slipping. Though Shallow tube well, dug well and gravity flow system have a potential risk of faecal contamination, but did not performed any test for it.

27

Environmental Monitoring Report July – December 2018

Engine oil of power tiller and power pump is not dumped following the guide line. Some tube well found water clogging around it. Reuse of tube well water is not found. Implementation status of EMP for community infrastructure development subprojects is presented in Appendix 7 and their summary is presented in Table 5 as follows:

Table 5: Summery of the EMP implementation Status of CI component Potential Proposed Actual Recommended Compliance Impacts Mitigation Implementation Actions Status measures as per EMP Construction of Minimum Some tube well Water quality Partially tube well close distance should did not maintain test for faecal complied. of latrine pit be 30 feet as per the safe distance coliform and have a Bangladesh routine test potential threat standard once in year. of faecal contamination. Accumulation Regular cleaning Some found with Immediate Partially of soil on stair and maintenance huge soil removing the complied. case have a is suggested. accumulation. accumulated potential of soil and wash slipping risk. out. Inappropriate Recycle or proper It is dumped here It is need to Partially management of management or and there and inform the user complied. engine oil may use as fuel. sometimes burn to recycle it or cause of soil out. dumped it pollution properly according to the guideline. Improper Clear slope Appropriate slope If possible, Partially management of should maintain is not maintained. correction the complied slop of market for proper slope and shed will cause drainage system. maintain the of water drainage logging in system to avoid surrounding water logging. area.

28

Environmental Monitoring Report July – December 2018

Some noise Machine will It was reported No action is Well may generate operate in that power pumps required Complied during daytime only. and power tillers operation of operate at day power tiller time only. and pump machine which is local and not much significant.

2.6 Compliance Status with GoB Policy:

38. According to the Bangladesh Environmental Conservation Act 1995 and Bangladesh Environmental Conservation Rules 1997, the project falls under “Orange B” category. The compliance with act and rules is presented in Table 6 as follows:

Table 6: Environmental Compliances Status with Policy of GoB Acts and Rules Compliance requirement Compliance Status Bangladesh Environmental Requires environmental Complied as the Conservation Act 1995 clearance from the environmental clearance for And Department of Environment. the rural road component as Bangladesh Environmental well as community Conservation Rules 1997 infrastructure has been obtained from the DoE.

2.7 Compliance Status of ADB Safeguard Policy Statement:

39. The project falls under “B” category according to ADB Safeguard Policy Statement 2009 and hence an IEE is sufficient to meet the environmental requirements. IEE reports for six sample subprojects were prepared by the project preparatory consultants. An EARF also prepared by the

29

Environmental Monitoring Report July – December 2018

ADB’s PPTA team. The CHTRDP-II has adopted the EARF. IEE reports including EMP for other subprojects, which were implement, or are being implemented, were prepared as part of the subproject feasibility report based on this EARF and ADB Safeguard Policy Statement 2009.

2.8 Compliance status of Environmentally Specific Loan Covenants:

40. Schedule 5 of the loan agreement stipulated environmental considerations. The compliance with environmentally specific loan covenants are shown in the Table 7 as below:

Table 7: Compliance with Environmentally Specific Loan Covenants Reference Loan Covenants Compliance Status Environment: The Borrower shall ensure or Preparation and design stage: Schedule 5, Page 20, cause the Implementing Agencies All applicable laws and Para 7 to ensure that the preparation, regulations relating to design, construction, environment, health, and safety, implementation, operation and environmental maintenance of each Subproject safeguards and EARF have been and all Project facilities comply complied for each subproject. with (a)all applicable laws and Implementation stage: regulations of the Borrower All applicable laws and relating to environment, health, regulations relating to and safety; environment, the environmental (b)the Environmental Safeguards; safeguards; the EARF; and all (c)the EARF; and measures and requirements set (d)all measures and requirements forth in the respective IEE and set forth in the respective IEE and EMP are being implemented for EMP, and any corrective or each subproject; but health and preventative actions set forth in a safety measures for workers are Safeguards Monitoring Report. not addressed properly. Human and Financial The Borrower shall make available Being complied the necessary Resources to the necessary budgetary and human budgetary provision and human Implement resources to fully implement the resources for the implementation EMPs, the RPs and the IPP. of EMPs, the RPs and the IPP.

30

Environmental Monitoring Report July – December 2018

Reference Loan Covenants Compliance Status Safeguards Requirements: Schedule 5, Pages 21 &11 Safeguards-related The Borrower shall ensure or cause a) Provision has been made in Provisions in the Implementing Agencies to bidding documents and works Bidding Documents ensure that all bidding documents contracts for rural road and Works and contracts for Works contain component. Similar provision has Contracts: provisions that require contractors also been made for community Schedule 5, Page 22, to: infrastructure component; Para 12 (a) comply with the measures and (b) Adequate budgetary provision requirements relevant to the has been made for all contractor set forth in the IEE, the environmental and social EMP, the RP and the IPP (to the safeguard measures except tree extent they concern impacts on Plantation and environmental affected people during pollution related to surface water, construction), and any corrective noise, and fertility of soil. or preventative actions set out in a (c) No such incidence has Safeguards Monitoring Report; appeared till date; (b) make available a budget for all (d) Being complied; such environmental and social (e) Being complied; measures; (c) provide the Borrower with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, the RP or the IPP; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and

31

Environmental Monitoring Report July – December 2018

Reference Loan Covenants Compliance Status (e) fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.

2.9 Institutional Arrangement for Implementing EMP:

41. Ministry of Chittagong Hill Tracts Affairs is the executing agency. The Chittagong Hill Tracts Regional Council (CHTRC) is the lead implementing agency, where a PMO headed by a Project Director has been established. The PMO is supported by three DPMOs headed by Deputy Project Director at each district and a team of PIC. Respective project DPMO is implementing CI components through PDC/CDC. LGED is the implementing agency for the rural road component headed by another Project Director. The responsibilities of each agencies during the various phases of the project are shown in table 8 as below:

Table 8: Institutional Responsibility Matrix of EMP Stage Agency Contact Responsibility Deliverables Pre- CHTRC/PMO Project Director Preparation of EMP, EMP, bidding construction LGED Project Director incorporation of EMP documents, /Design DPMO Deputy Project into subproject monthly reports, Director feasibility report and quarterly reports, PIC Team bidding documents, semestral reports Leader/DTL and to ADB. reporting to ADB. Construction CHTRC/PMO Project Director Monitoring of EMP Monthly report, LGED Project Director implementation and quarterly reports, DPMO Deputy Project reporting to ADB. and semestral Director reports to ADB. PIC Team Leader/DTL

32

Environmental Monitoring Report July – December 2018

SQMC Environmental Engineer Contractors As per signed Implementation of Report contract EMP Operation/Post CHTRC/PMO Project Director Monitoring of EMP Final report operations DPMO Deputy Project implementation Director PIC Team Leader/DTL SQMC Environmental Engineer

42. Safeguards related all measures and requirements set forth in the respective IEE and EMP are integral part of contract documents. During implementation of these works, LGED implements EMP. LGED, PIC and SQMC consultants monitor these activities. Similarly, DPMO implements and monitors EMP under CI component. LGED and DPMO send monthly monitoring report to PD, PMO. After compiling these report PMO prepares semestral report with the assistance of PIC/SQMC consultant and sends this report to ADB, MoCHTA and DoE. SQMC consultant also monitors these activities and reports to PD (PMO) and ADB directly.

43. A comprehensive grievance redress mechanism has been established for the project under the land acquisition and resettlement framework. The same mechanism is applied for grievances arising due to environmental impacts, with the Project Director deputing a relevant community, project team member or NGO representative to join the process depending on the nature of the grievance.

33

Environmental Monitoring Report July – December 2018

Chapter 3 Tree Plantation

3.1 Background:

44. As a suggestive measures from EMP, tree plantation was a very important event. It was decided that after completion of component B (Rural Road) tree plantation will be in placed following the policy 1 for 10. Social Mobilization NGO are the front line key players to implement this activities with the direct supervisor of DPMO. A total of 25,000 tree sapling will be planted along the 12 nos. rural roads of total 86 km. A tree plantation guideline has been developed to make the event successful. The following table 9 of road packages are selected for tree plantation.

Table 9: Subproject Wise for Tree Plantation Sl No Name of Subproject Upazila District Length (km) 1 Betbunia Chairy Bazar- Laxmichari Kawkhali Rangamati 6.01 2 Betbunia Chairy Bazar- Santirhat Kawkhali Rangamati 4.68 3 Raikhali - Rajsthali Kaptai Rangamati 5.74 4 Marishy Bazar- Mayanimuk Baghaichari Rangamati 14 5 Holudia -Vaggakul Sadar Bandarban 10.31 6 Pan Bazar- Chokhyng Tripura para Alikadam Bandarban 4.4 7 Naikhongchari-Tumru Naikhongchari Bandarban 12.81 8 Lama- Rupashi para Lama Bandarban 3.33 9 Baniachara- Gazalia Lama Bandarban 8.79 10 Panchari – Bhaibonchara Panchari Khagrachari 5.61 11 Sinducchari –Dullahtali Guimara Khagrachari 4.75 12 Garitana – Batnatali Manikchari Khagrachari 6.38 Total 86.81

34

Environmental Monitoring Report July – December 2018

3.2 Institutional Framework of Tree Plantation:

45. The office of the Deputy Project Director (DPD), established in each of the hill districts is responsible to supervise, guide and monitor the Tree plantation implementation activities at the district level. The DPD will report to the PMO and Hill District Council (HDC) on all aspects of the project. Besides, he is also responsible for liaison and coordination at Upazila and Union Parishad level and will supervise the activities of the NGO contracted for social mobilization of the communities.

The SM-NGOs will play a vital role in the implementation of the tree plantation. Their key responsibilities are as follows:  Mobilize the affected person/ adjacent communities/ traditional leaders/ UP representatives etc. of along the improved roads.  Responsible for formation of a Tree Plantation Maintenance Committee (TPMC) as well as a procurement evaluation Committee (PEC).  They will update and guidance to TPMC ( Tree Plantation Maintenance Committee) about monitoring, supervision on tree plantation implementation process.

The (TPMC) represents their respective para’s affected person/ adjacent communities/ traditional leaders/ UP representatives etc. of along the improved roads. The Tree Plantation Maintenance Committee (TPMC) is located at Para level will be constituted with 9-11 person. The responsibilities of TPMC are as follows:

 Responsible for coordination and management of implementation of tree plantation in their respective area.  The TPMC will be responsible for Care and Maintenance of the saplings after completion of the tree plantation and  They will be responsible for sustainable O&M

35

Environmental Monitoring Report July – December 2018

3.3 Species Selection:

46. The common species of saplings are primarily selected for plantation which are Neem (Azadarachta indica), Mahogany (Swietenia mahagoni), Shishu (Dalbergia sissoo), Shirish (Albizia lebbek), Jam (Syzygium jambolana), Babla (Acacia 12rabica), Arjun (Terminalia arjuna), Jarul (Lagerstroemia flosreginae), Tentul (Tamarindus indica). Also Aam (Mango indica) and Jack Fruit (Artocarpus heterophylus). The saplings will be from above approved list of man-height size(five feet plus). After consultation with the department of forest, department of agriculture and local expert the species will be finalized.

3.4 Ownership of Planted Trees:

47. The representative of local government (UP Member/Chairman) should sign a MoU regarding ownership of the planted trees for all the affected persons in his area. The following parties will obtain shares (of the monetary value) of the planted trees at the time of sale. At consensus, parties may cut and sell trees after 10 years from the time of planting where Local government (Union Parisadl) and Owner(s) of affected persons will get the share 45% and 55% respectively.

3.5 Action Plan:

48. It is decided to accomplish the tree plantation by June 2019 in all completed road. The following table 10 show the detail plan for tree plantation.

Table 10: Action Plan for Tree Plantation Month Activities November -December Social mobilization and formation of Tree Plantation committee and Procurement evaluation committee January Site visit, technical feasibility study and Preparation of BOQ February-March Surveying and cleaning of the plantation area April- May Manure collection and pit preparation along with transportation of sapling.

36

Environmental Monitoring Report July – December 2018

May- June Plantation

3.6 Plant Nursing:

49. The TPMC will, with the assistance of the NGO, DPMO & PIC, prepare an Operation and Maintenance (O&M) plan for monitor, nursing and care of the saplings. After plantation, watering, care of soil, weeding, vacancy filling/failed plantsreplacement, prop replacement, pruning etc. will be done by the TPMC under close supervision of SM-NGOs and Union Parishad.

37

Environmental Monitoring Report July – December 2018

Chapter 4 Result and Corrective Action Plan

4.1 Result:

50. The project is in the stage of second time extension. Except the rural road components most of the components is very good in position of implementation. CI component is almost done. The progress of micro agree business development is also good. The major environmental impact found in the improvement of rural road construction. The previous EMR have dealt with different environmental issues. In this report I have focused on very specific issues but have a very large environmental and social impact.

51. Steep cut of hill is very important issue highlighted in this report. In the BoQ it is minimum slope of hill cutting is 45 degree. But it is not maintained in the field and most of the site it is vertical cut which having a potential of land slides during rainy season. This report identified every specific point of threat and find out the mitigation measures. The soil type of this region is very sandy and loamy. Considering along with the soil condition, intensity of rainfall, physical communication, available materials and cost effectiveness, it is decided that one single solution is not enough to mitigate the hill slide threat. As a result 3 step measures have been suggested which are RCC guide wall with sufficient height to be placed in the bottom of the hill, providing geotex over the slope of the hill with appropriate nailing and bio engineering on the slope. The detail design and cost estimation will be done by February 2019.

52. Tree plantation is another issue which are considered in this report. Technical feasibility is ongoing to find out the specific site of tree plantation. PMO has developed a tree plantation guideline.

53. Dust pollution from soil during construction of road is another important socio- environmental issue which has been covered under this report. The dust make the traffic very discomfort to move. The major concern of the dust pollution is it is directly impact the school, madrasha, community place, mosque which are adjacent to the road. The contractors did not follow the EMP at all.

54. Soil erosion and sedimentation is very critically review in this report. Most of the excavated soil from road improvement are dumped besides the road without any compaction. As a result it has a massive potential to erosion during rainfall and sediment over the agricultural land and forest along with congestion of natural flow.

38

Environmental Monitoring Report July – December 2018

55. Faecal contamination of water supply system have identified as potential risk for community health. Previously a number of water parameter have been tested but not the faecal coliform. Some tube well and latrine pit found very close which did not maintain the safe standard distance. On the other hand the GFS system use the surface water which have a great risk of faecal contamination.

56. Air pollution from bituminous activity of road construction is another environmental concern considering the climate change perspective. Though it is not very massive in this project but have some impact as carbon dioxide emission occur. The cumulative impact is aggravated if use of wood as fuel.

4.2 Corrected Action Plan:

57. A corrective action plan has been prepared based on the field visits and presented in table 11 as follows:

Table 11: Corrective Action Plan Identified issues Action Required Responsibilities Timeline Site specific hill slide Identification of spot, Environmental By Mid February, protection/mitigation detail design of guide Engineer, SQMC 2019 measures wall, estimation and budgeting Tree plantation Formation of PMO, DPMO 30 June, 2019. committee, Approval tree plantation guideline from ADB, Species selection, plantation. Slope maintain Suggested slope LGED/PIC 30 June, 2019 according to BoQ described in BoQ should maintain properly Faecal Coliform test Collection of sample DPMO/PMO 30 June of all water point and laboratory test in

39

Environmental Monitoring Report July – December 2018

Identified issues Action Required Responsibilities Timeline regional DPHE laboratory. Compaction of soil Immediate action to LGED/Contractor/PIC Ongoing, up to besides roads which compact the soil and completion of project have a potential of provide appropriate component erosion turfing i.e. grass/trees etc Remove all the Remove all the LGED/Contractor/PIC Ongoing congestion of natural congestion of natural water flow. water flow in the bridge construction point along with completely remove all the alternative road of bridge construction. Management of used Used engine oil PMO/DPMO/PDC Throughout the life of engine oil: Used drained from the power tiller and engine oil drained power tiller and power pump supplied from the power tillers power pump should by the Project and power pumps be collected in a release over land separate container that may degrade soil and stored ina safe and water. place for recycling or to use for other purpose. Soil dust pollution Spray water while LGED/Contractor/PIC Up the end of the from road this disturb the people construction work. construction and nearby community. Occupational health It is suggested to LGED/Contractor/PIC Up the end of the and safety maintain minimum construction work. safety measures

40

Environmental Monitoring Report July – December 2018

Identified issues Action Required Responsibilities Timeline which is very risk for health like safety shoes, gloves etc.

41

Environmental Monitoring Report July – December 2018

Chapter 5 Conclusion and Recommendations

5.1 Conclusion:

58. The implementation status of the environmental mitigation measures during the pre- construction stage of all sub projects was satisfactory. Checking of environmental mitigating infrastructure design in all rural road improvement subprojects and CI components has been done effectively during design and pre-construction stage. In all subprojects, environmental issues have been identified and EMPs have been prepared as a part of feasibility study report; and incorporated in bidding documents and contracts.

59. This report comprise of post monitoring of CI component in most cases and regular monitoring of rural road and micro agree business development component. The major environmental concern are associated with rural road component. The major environment impact are found are loss of topography, land slide treat, erosion of lose soil, loss or disturbance of top soil, congestion of natural water flow, pollution of surface water and dust pollution. Besides these, occupational health and safety issues are also very concern factor. The slope maintain during cutting of hill is not maintained. The contractors are not very aware regarding the environmental issues. Protection of vegetation, direct loss of trees are considered by the contractors carefully.

60. Primarily, about 91 hill spot has been identified for hill slide mitigation measures along the road side in which Rangamati (Kawkhali 18, Kaptai 12, Baghaichori 03) has 33 spots , Bandarban (Sadar 12, Naikhongchari 23, Alikadam 08, Lama 14) has 57 spots and Khagrachori (Guimara 01) has 1 spot. It is found that Natural water canal i.g. chara is getting congested by the huge soil dumping in some places of Lama and Alikadam Upazila.

61. It is found some water point close the latrine pit which did not maintain the safe distance of Bangladesh standard i.g. 30 feet. It is suggested to test feacal coliform of all water (tube well, Gravity flow system) source. Farmers are using Pheromone trap for eggplant cultivation but it is not replicated as desired.

42

Environmental Monitoring Report July – December 2018

62. The farmer change engine oil after 72 hours of engine running but they did not dispose the lubricants properly following the compliance. The drainage facilities of market shade is not found appropriate which may lead to create mud in front of shed.

63. Most of the contractors were not provided personal protective equipment - like face masks, hand gloves, helmets, high visibility clothing etc. to their workers; and first aid box with medicines was not available at worksites.

64. Filled loose earth was observed along the side slopes. This loose earth is vulnerable for soil erosion, which leads to deposition of sedimentation over the adjacent agricultural lands. Side slopes road of the road embankments were not compacted. Moreover, at some sections steep batter slopes were observed.

5.2 Recommendation:

65. It is found from direct observation from field that suggestive environmental mitigation measures are not followed or partially followed by the contractors. In some cases, they were not aware regarding the safeguard policy or issues of ADB. On the other hand implanter i.e. LGED’s concerned person like Upazila engineer, sub-assistant engineer are not very comfort regarding the environmental safeguard issues of this project. From my observation I would like to put some recommendation which could assist to ensure the environmental safeguard compliance of ADB for this project.

I. Capacity building the field level staff of LGED and contractors (Not the signatory contractors rather than who are in field) regarding the environmental safeguard issues through training. II. Full time Engagement of a person to look after the implication of suggestive mitigation measures day by day in field.

43

Environmental Monitoring Report July – December 2018

III. Contractors should ensure to provide personal protective equipment - like face masks, hand gloves, helmets, high visibility clothing etc. to their workers; and first aid box with medicines should be available at worksites. IV. Immediate action to implement the hill slide mitigation measures in identified specific sites. V. Contractor should take special attention that natural water canal never be congested and erosion of lose soil which can make a layer on top soil. VI. It would be best fitted if the environment specialist is engaged since finalization of road alignment and other construction project. VII. It would be great initiative if inclusion of EMP in BoQ is possible from the very beginning of further project design.

44

Environmental Monitoring Report July – December 2018

APPENDIX

Appendix 1: Physical Progress of Rural Road Component (Up to 12th December, 2018)

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) 1 2 3 4 5 6 7 8 14

Extension of W-CHT II- 1 Sadar RANGA-F- RCC 1 100% Functional Building BUILD/01 Protection work for W-CHT II- 2 Sadar Boundary Wall of XEN RANGA-F- RCC 1 Office, LGED BUILD/02 Total Sadar 2 2 Improvement of Betbunia Chairy W-CHTII- RANG- 3 Bazar– Laxmichari via HBB 2.39 19.20 100% Kaw- Barmachari road (Ch. UZR/01A 8100-10485m) Improvement of Betbunia Chairy W-CHTII- RANG- 4 Bazar– Laxmichari via HBB 1.62 36.90 100% Kaw- Barmachari road (Ch. UZR/01B 10485-12100m) Improvement of Betbunia Chairy Kawkhali W-CHTII- Bazar– Laxmichari via RANG- 5 HBB 2.01 51.90 100% Barmachari road Kaw- (Ch.12100-14110m) UZR/01C Rangamati Construction of 60m RCC Girder Bridge on Betbunia Chairy Bazar - Laxmichari via W-CHTII- 6 Rang-Kaw- HBB 0.50 60.00 60% Barmachari UZR/01D Connecting Road up to Raujan upazila RHD by HBB (Ch. 0.00- 495m) Sub total 4 6.51 168.00 Betbunia Chairy Bazar- Bara Aoulia-Santirhat W-CHTII- 7 Rang-Kaw- BC 2.14 18.40 100% Road at Ch.3+070- UNR/04A 5+210km Construction of 35m Kawkhali PC Girder Bridge on Betbunia Chairy Bazar- W-CHTII- 8 Rang-Kaw- BC 0.44 36.80 85% Bara Aoulia-Santirhat UNR/04B Road at Ch.5+210- 5+650 km

45

Environmental Monitoring Report July – December 2018

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) Betbunia Chairy Bazar- Bara Aoulia-Santirhat W-CHTII- 9 Rang-Kaw- BC 2.10 21.30 85% Road at Ch.5+650- UNR/04C 7+750 km Sub total 3 4.68 76.50 Total Kawkhali 7 11.19 244.50 Construction of 25m RCC Girder Bridge on Raikhali GC Ferry W-CHTll- RANG- BC & 10 Ghat-Rajsthali HQ Via 2.39 42.40 50% Kap- HBB Mitingachari Road at UZR/06A Ch.1+070 - 1+365 & 2+550 - 4+640 km Construction of 60m RCC Girder Bridge on W-CHTll- Raikhali GC Ferry RANG- 11 HBB 1.17 70.90 25% Ghat-Rajsthali HQ Via Kap- Mitingachari Road at UZR/06B Ch.4+640 - 5+810km Rangamati Kaptai Construction of 2 Nos 25m RCC Girder Bridge on Raikhali GC W-CHTll- RANG- 12 Ferry Ghat-Rajsthali HBB 0.95 51.80 40% Kap- HQ Via Mitingachari UZR/06C Road at Ch.5+810 - 6+760km Construction of 42m & 25m RCC Girder Bridge on Raikhali GC W-CHTll- RANG- 13 Ferry Ghat-Rajsthali HBB 1.23 71.30 55% Kap- HQ Via Mitingachari UZR/06D Road at Ch.6+760 - 7+990km Total Kaptai 4 5.74 236.40 Improvement of Marishya Bazar (Upazila sadar)- W-CHTII- Mayanimukh Bazar via RANG- 14 HBB 2.46 10.30 90% Babupara, Battola & Bag- Daskin Saroatoli road UNR/02A at Ch. 10+490- Baghaichar Rangamati 12+950km (T) i Construction of 15m RCC Girder Bridge and Improvement of W-CHTII- 15 Marishya Bazar Rang-Bag- HBB 2.06 18.80 45% (Upazila sadar)- UNR/02B Mayanimukh Bazar via Babupara, Battola &

46

Environmental Monitoring Report July – December 2018

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) Daskin Saroatoli road at Ch. 12+950- 15+010km (T)

Improvement of Marishya Bazar (Upazila sadar)- Mayanimukh Bazar via W-CHTII- 16 Rang-Bag- HBB 1.90 10% Babupara, Battola & UNR/02C Daskin Saroatoli road by HBB ( Ch. 15.01 km-16.91Km) Improvement of Marishya Bazar (Upazila sadar)- Mayanimukh Bazar via W-CHTII- 17 Rang-Bag- HBB 1.17 10% Babupara, Battola & UNR/02D Daskin Saroatoli road by HBB( Ch. 16.91km- 18.08 Km) Improvement of Marishya Bazar (Upazila sadar)- Mayanimukh Bazar via Babupara, Battola & W-CHTII- 18 Rang-Bag- BC 2.45 50% Daskin Saroatoli road UNR/02E by BC including 795m link road ( Ch.0.00 - 1.66 Km & 0.00 - 0.795 Km ) Improvement of Marishya Bazar (Upazila sadar)- Mayanimukh Bazar via W-CHTII- 19 Rang-Bag- BC 3.76 35% Babupara, Battola & UNR/02F Daskin Saroatoli road at Ch. 1.66 Km - 5.42 Km) Sub total 6 13.80 29.10 Construction of 69m RCC Girder Bridge at Ugalchari on Baghaichar W-CHTII- 20 Baghaichari Upazila Rang-Bag- BC 0.50 69.00 5% i HQ - Ugalchari via UNR/01A Bottoli Bazar Road at Ch. 4970m. Sub total 1 0.50 69.00 Total Baghaichari 7 14.30 98.10 Total Rangamati 20 31.22 579.00

47

Environmental Monitoring Report July – December 2018

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) Extension of W-B-BAN- 21 Sadar F- RCC 1 100% Functional Building BUILD/01 Sub total 1 1 Construction of 220 m Long PSC Girder Bridge over Sangu W-B-BAN- 22 Sadar Sad- RCC 0.10 220.00 55% River on Raicha- UNR/03 Goaliakhola Road at Ch.7+150km Sub total 1 0.10 220.00 Improvement of Holudia-Vaggakul- W-B-BAN- 23 Sad- BC 1.95 1.00 50% Tankbati Road by BC UNR/02A (Ch. 3.35Km-5.30Km). Improvement of Holudia-Vaggakul- W-B-BAN- 24 Sad- BC 2.01 1.80 45% Tankbati Road by BC UNR/02B (Ch. 5.30Km-7.31Km). Improvement of Holudia-Vaggakul- Tankbati Road by BC W-B-BAN- 25 Sad- BC 1.33 36.90 30% (Ch. 7.31Km- Sadar UNR/02C 8.635Km) with 36m RCC Bridge Bandarban Improvement of Holudia-Vaggakul- W-B-BAN- 26 Tankbati Road by BC Sad- BC 2.58 0.75 10% (Ch. 8.635Km - UNR/02D 11.21Km). Improvement of Holudia-Vaggakul- W-B-BAN- 27 Tankbati Road by BC Sad- BC 2.46 0.90 10% (Ch. 11.21Km- UNR/02E 13.67Km). Sub total 5 10.32 41.35 Total Sadar 7 10.42 261.35 Construction of 28.30m long RCC Girder W-B-BAN- 28 Ruma Bridge on Ruma Sadar- RUM- RCC 0.13 28.30 95% Ruma Bazar Road at UZR/01 Ch. 1+177Km Sub total 1 0.13 28.30 Hill Protection at Approach of 28.30m Long RCC Girder W-B-BAN- 29 Ruma Bridge on Ruma Sadar- RCC 75% RUM-UZR Ruma Bazar Road by Brick Gravity Wall, Jute Geo-Textile and

48

Environmental Monitoring Report July – December 2018

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) Cladding Clay at ch. 1+177Km

Sub total 1 0.00 0.00 Total Ruma 2 0.13 28.30 Construction of 61.0m (Ch.12+452km) long W-B-BAN- 30 RCC Girder Bridge on Nai- RCC 0.19 61.00 95% Naikhongchari - UZR/03E Tumbru Road Improvement of Naikhongchari- W-B-BAN- 31 Tumbru Road at Nai- HBB 1.85 19.40 95% Ch.13+400 - UZR/03A 15+250km Construction of 15.0m (Ch.14+620km) and 48.0m (15+125km) W-B-BAN- 32 long RCC Girder Nai- RCC 63.00 95% Bridge on UZR/03A1 Naikhongchari- Tumbru Road Construction of 60.0m RCC Bridge on Naikhongchari- W-B-BAN- 33 Nai- HBB 0.57 60.00 95% Tumbru Road at Naikhongc UZR/03B Bandarban Ch.15+250 - hari 15+820km Construction of 57.0m and 15 m RCC Bridge with Road on W-B-BAN- 34 Naikhongchari- Nai- HBB 1.08 76.00 80% Tumbru Road at UZR/03C Ch.15+820 - 16+900km Construction of 25.0m RCC and 35.0m PC Girder Bridge with Road on W-B-BAN- 35 Nai- HBB 0.74 64.30 80% Naikhongchari- UZR/03D Tumbru Road at Ch.16+900 - 17+640km Construction of 30.0m (Ch.25+805km) PC W-B-BAN- 36 Girder Bridge on Nai- RCC 0.09 30.00 75% Naikhongchari- UZR/03G Tumbru Road

49

Environmental Monitoring Report July – December 2018

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) Improvement of Naikhongchari- W-B-BAN- 37 Tumbru Road at Nai- BC 2.21 29.90 80% Ch.25+760 - UZR/03F 27+965km Construction of 20.0m and 23.0m RCC Bridge with Road on W-B-BAN- 38 Naikhongchari- Nai- BC 0.99 53.20 85% Tumbru Road at UZR/03H Ch.27+965 - 28+955km Construction of 35.0m (Ch.27+458km) and 30.00m (29+765km) W-B-BAN- 39 Nai- RCC 0.10 65.00 75% long PC Girder Bridge UZR/03G1 on Naikhongchari- Tumbru Road Construction of 30.0m (Ch.30+570km) PC Girder Bridge with W-B-BAN- 40 Nai- BC 1.66 43.70 95% Road on UZR/03I Naikhongchari- Tumbru Road Improvement of Naikhongchari- W-B-BAN- 41 Nai- BC 3.24 17.9 100% Tumbru Road at UZR/03J Ch.30+610- 33+845km Construction of 50.00m (Ch.26+023km) long W-B-BAN- 42 Girder Bridge on Nai- RCC 0.09 50.00 10% Naikhongchari- UZR/03K Tumbru Road Sub total 13 12.81 633.40 Improvement of Pan Bazar - Chokhyng W-B-BAN- 43 Tripura Para (Kalar ALI- BC 1.35 5.40 25% Jiri) Road by BC (Ch. UNR/05A 3.60Km-4.95Km). Alikadam Improvement of Pan Bazar - Chokhyng Tripura Para (Kalar W-B-BAN- 44 ALI- BC 0.86 10.85 25% Jiri) Road by BC (Ch. UNR/05B 4.95 Km-5.81Km). (Union Road) Total Alikadam 2 2.21 16.25 Improvement of Lama- W-B- Rupashipara Road at BAN- 45 Bandarban Lama HBB 1.59 44.70 75% Ch.09+50 - 11+09km Lam- with 35m PC Gider UNR/07A

50

Environmental Monitoring Report July – December 2018

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) Bridge at Ch. 10+635km

Improvement of Lama- W-B- Rupashipara Road at BAN- 46 HBB 1.60 16.70 95% Ch.11+225 - Lam- 12+820km UNR/07B Construction of 60m W-B- RCC Girder Bridge on BAN- 47 RCC 0.14 60.00 35% Lama -Rupashipara Lam- Road at Ch.11+150km UNR/07C Construction of 4.0m x W-B- 4.5m (width 20m) Box BAN- 48 Culvert on Lama - RCC 4.00 Lam- Rupashipara Road at UNR/07D Ch.10+635km Sub total 4 3.33 125.40 60m RCC Girder Bridge and BC Road on W-B-BAN- 49 Baniarchara-Gazalia Lam- BC 1.74 66.70 70% Raod at Ch.03+760 km UNR/08A - 05+500 km (T) Construction of 25m RCC Girder Bridge and BC Road on W-B-BAN- 50 Lam- BC 1.26 27.00 30% Baniarchara-Gazalia UNR/08B Raod at Ch.05+500 km - 06+760 km (T) Lama Baniarchara-Gazalia W-B-BAN- 51 Raod at Ch.06+760 km Lam- BC 3.05 70% -09+810 km (T) UNR/08C 64m (40m+24m) RCC Girder Bridge on W-B-BAN- 52 Baniarchara-Gazalia Lam- BC 0.56 50.00 25% Raod at Ch.09+810 km UNR/08D - 10+370 km Baniarchara-Gazalia Raod at W-B-BAN- 53 Lam- BC 2.18 0.90 95% Ch.10+370+12+55 km UNR/08E (T) Sub total 5 8.79 144.60 Total Lama 9 12.12 270.00 Total Bandarban 33 37.69 1209.30 Extension of W-KHA-F- 54 Sadar RCC 1 100% Khagrachari Functional Building BUILD/01 Total Sadar 1 1

51

Environmental Monitoring Report July – December 2018

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) Improvement of Panchari GC- W-KHA- 55 Baibonchara GC via Pan- BC 2.59 11.85 100% Shantipur Arunya Kutir UZR/01A Road (Ch: 00-2590m) Improvement of Panchari GC- Baibonchara GC via W-KHA- 56 Pan- BC 1.76 4.50 100% Panchari Shantipur Arunya Kutir UZR/01B Road (Ch: 2590- 4350m); Improvement of Panchari GC- Baibonchara GC via W-KHA- 57 Pan- HBB 1.06 6.15 100% Shantipur Arunya Kutir UZR/01C Road (Ch: 8966- 10030m); River Bank Protection work at Panchari GC- Baibonchara GC via W-KHA- 58 Pan- RCC 0.20 50% Shantipur Arunya Kutir UZR/01D Road (Ch: 1420m - 1620m) Total Panchari 4 5.61 22.50 Improvement of Sinduckchari union H/Q-Dullahtali GC via W-KHA- 59 Moh- BC 1.95 93.10 90% Chailyatali Road by BC UNR/05A Ch.0+763 to 2+713 (Km+M) Improvement of Guimara Sinduckchari union H/Q-Dullahtali GC via Chailyatali Road by BC W-KHA- 60 Moh- BC 2.80 84.70 85% Ch.2+713to 5+513 UNR/05B (Km+M) with 36.00m and 25.00m span RCC Girder Bridge Total Guimara 2 4.75 177.80 Construction of Garitana GC-Batnatoli W-KHA- 61 H/Q via Jogyachola Man- BC 2.87 19.70 100% Road at Ch.09+172- UNR/04A 12+037km Manikchari Construction of Garitana GC-Batnatoli W-KHA- 62 H/Q via Jogyachola Man- BC 3.51 4.75 95% Road at Ch.12+037- UNR/04B 15+545km Total Manikchari 2 6.38 24.45

52

Environmental Monitoring Report July – December 2018

Quantity Physic al Sl. Package District Upazila Scheme name Type Progr No. No. Km/No. M ess (%) Total Khagrachari 9 16.74 224.75 Grand Total Rangamati, Bandarban & 62 85.65 2013.05 Khagrachari

53

Environmental Monitoring Report July – December 2018

Appendix 2: Physical Progress of CI Component

Khagrachari District Status of Sl.№ Name of subprojects works Village Access Road: 1. Dharmapur-Dharmaghar Subproject (Comprises improvement of 5.21km 100% earthen Village Access Road (VAR) to brick pavement including construction of 880 m road side drains, 202 m. Guide Walls and 7 Culvers) under Sadar Upazila. 2. Akhoy Chandra Karbari Para-Monatek Para Subproject (Comprises 100% improvement of 2.08 km village access road to brick pavement including construction of 720m road side drains and 325m guide walls) under Mahalchari Upazila. 3. Mirzatila to Gaganchandra Para Road Subproject (Comprises development 100% of 2.5 km earthen village access road with brick pavement including construction of 1155 m road side drains, 5 Culverts and 360 m. Guide Wall) under Panchari Upazila. 4. Nittya Gan Para Road Subproject (Comprises improvement of 1050 m. 100% earthen village access to brick pavement including construction of 65m guide wall, one box-culvert (3 m) and 230 m road side drain) under . 5. Karallyachari Para HBB Road Construction Subproject (Comprises 100% Construction of HBB Road from Karallyachari Muk Para to Karallyachari Headman Para (from 0 m. to 1900 m.), Construction of Box Culvert, U- Drain, L-Drain & Guide Wall at Different Chainage at Karallyachari Muk Para to Karallyachari Headman Para HBB Road (from 0 m. to 1900 m.) under Mohalchari Upazila 6. Pulinpur to Vije Kijing HBB Road Subproject (Comprises Construction of 100% HBB Road- 1400 m., L-Drain- 302 m. and Guide Wall- 55 m.) under Panchari Upazila. Market Shed: 1. Mejar Para Subproject (Comprises construction of 178 sqm of market 100% shed, 4 toilets, installation of one tube, and improvement of earthen access road with brick pavement) under Laxmichari Upazila. 2. Chitta Ranjan Karbari Para Subproject (Comprises Construction of 178 100% sqm. of market shed including 4 toilets, installation of one tube well and improvement of 15 m earthen access road to brick pavement) under Mahalchari Upazila. 3. Hudukchari Para Marketshed Subproject (Comprises Comprises Physically Construction of Marketshed- 1 No, Toilet- 1 No. and Installation of Deep Completed Tube Well- 1 No.) under Laxmichari Upazila.

54

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 4. Tabida Para Marketshed Subproject (Comprises Comprises Construction 90% of Marketshed- 1 No, Toilet- 1 No. and Installation of Deep Tube Well- 1 No.) under Panchari Upazila. 5. Dudhukchara Para Marketshed Subproject (Comprises Comprises 100% Construction of Marketshed- 1 No, Toilet- 1 No. and Installation of Deep Tube Well- 1 No.) under Panchari Upzaila. 6. Itchari Mukh Para Marketshed Subproject (Comprises Comprises Physically Construction of Marketshed- 1 No, Toilet- 1 No. and Installation of Deep Completed Tube Well- 1 No.) under Khagrachari Sadar Upazila. 7. Rabidhan Para Marketshed Subproject (Comprises Comprises Physically Construction of Marketshed- 1 No, Toilet- 1 No. and Installation of Deep Completed Tube Well- 1 No.) under Khagrachari Sadar Upazila. 8. Purba Chailyatalli Para Marketshed Subproject (Comprises Construction Physically of Marketshed- 1 No, Toilet- 1 No. and Installation of Deep Tube Well- 1 Completed No.) under Laxmichari Upazila. CI Pilot Subproject : 1. Joggyachala Headman Para Subproject (Comprises installation of 12 Tube 100% Wells, Construction of 480 m. Irrigation Canal and Supply of 2 Power Pump) under Mahalchari Upazila. 2. Chitta Member Para Subproject (Comprises Installation of 3 Tube Wells, 100% Construction of 295 m. Irrigation Canal and Construction of 70 m. stair, Supply of one Power Pump) under Dhiginala Upazila. Watershed: 1. Godachara watershed management Subproject under Dighinala Upazila. 100% 2. Tarabonchara watershed management Subproject under Panchari Upazila. 100% Community Infrastructure: 1. Ugolchari Para Subproject (Comprises Construction of 760 m Irrigation 100% Canal, and Supply of one Power Pump including construction of Pump shed for irrigation) under Panchari Upazila 2. Harubil Para Subproject (Comprises Construction of 150 m. Irrigation 100% Canal, Supply of one Power Tiller and one Power Pump, Installation of 4 Tube Wells, improvement of 500 m. earthen village access road to brick pavement including construction of 160 m. road side drains, and one culvert) under Panchari Upazila. 3. Dakkin Babuchara Para Subproject (Comprises Construction of 570 m. 100% Irrigation Canal, Supply of one Power Tiller and one Power Pump, Installation 6 Tube Wells and re-excavation of one pond) under Dighinala Upazila.

55

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 4. Jowtha Khamar Para Subproject (Comprises Installation of 6 Tube Wells, 100% Re-excavation of one Pond and Construction of 2 Culverts) under Dighinala Upazila. 5. Tapita Para Subproject (Comprises Construction of 628 m. Irrigation 100% Canal) under Panchari Upazila. 6. Durung Para Subproject (Comprises Construction of 6 Culverts, 100% Installation of 5 Tube Wells and Supply of one Power Tiller) under Mohalchari Upazila. 7. Uttar Champaghat Subproject (Comprises improvement of 500 m. earthen 100% village access road to brick pavement, Installation of 8 Tube Wells, Construction of 250 m. Irrigation Canal and Supply of 1 Power Pump) under Sadar Upazila. 8. Jalbanda Para Subproject (Comprises Installation of 8 Tube Wells and 100% development of 4 infiltration gallery systems for drinking water supply) under Dighinala Upazila. 9. Paisi Mohajan Para Subproject (Comprises Construction of 900 m. 100% Irrigation Canal, Installation of 6 Tube Wells, and Supply one Power Pump) under Mahalchari Upazila. 10. Hazachara Para Subproject (Comprises Construction of one Foot Bridge 100% and Installation of 6 Tube Wells) under Mahalchari Upazila. 11. Bagra Para Subproject (Comprises Construction of 170 m Irrigation Canal, 100% 20 m. Foot Bridge, Installation of 5 Tube Wells and Supply of 2 Power Pump) under Sadar Upazila. 12. Dewan Para Subproject (Comprises Construction of 366 m. Irrigation 100% Canal and one Box Culvert, Installation of 20 Shallow Tube Wells and Supply of one Power Pump) under . 13. Lakyochi Para Subproject (Comprises Installation of 6 Tube Wells and 100% Supply of 2 Power Tillers) under Ramghar Upazila. 14. Jaghat Mohan Para Subproject (Comprises Supply of 2 Power Tillers and 100% 3 Power Pumps, installation of 7 Tube Wells and construction of 300 m. Irrigation Canal) under Panchari Upazila. 15. Abinash Para Subproject (Comprises Construction of 500 m. Irrigation 100% Canal, Installation of 5 Tube Wells, Supply of one Power Pump and 2 Power Tillers) under Panchari Upazila. 16. AK Para Subproject (Comprises Construction of 380 m. Irrigation Canal, 100% 7m Foot Bridge and Installation of 5 Tube Wells) under Khagrachari Sadar Upazila. 17. Akshay Para Subproject (Comprises Installation of 6 Tube Wells for 100% drinking water, 2 Tube Wells with Pumps for irrigation and Supply of one Power Tiller) under Panchari Upazila.

56

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 18. Dakkin Golabari Para Subproject (Comprises Construction of 700 m. 100% Irrigation Canal and Supply of one Power Pump) under Khagrachari Sadar Upazila. 19. Pablakhali Shantipur Para Subproject (Comprises Installation of 3 Tube 100% Wells, Supply of 3 Power Tillers and one Power Pump) under Dighinala Upazila. 20. Gaganchandra Para Subproject (Comprises Installation of 7 Tube Wells, 100% Construction of 200 mIrrigation Canal, Supply of 2 Power Tillers and one Power Pump) under Panchari Upazila. 21. Sukanta Mohajan Para Subproject (Comprises Installation of 5 Tube Well, 100% Supply of one Power Tiller and one Power Pump Machine) under Mohalchari Upazila. 22. Sajek Para Subproject (Comprises Construction of 420 m. Irrigation Canal, 100% Installation of 4 Tube Wells and Supply of 2 Electric Submersible Pumps) under Khagrachari Sadar Upazila. 23. Madhya Adam Para Subproject (Comprises Installation of 9 Tube Wells, 100% Supply of one Power Pump and 3 Power Tillers) under Mahalchari Upazila. 24. Noa Para Subproject (Comprises Installation of Shallow Tube Well- 3 100% Nos., Deep Tube Wells- 1 and Supply of one Power Tiller) under Khagrachari Sadar Upazila. 25. Juddha Kumar Para Subproject (Comprises Construction of one Culvert, 100% Installation of 13 Tube Wells, Supply of 3 Power Tillers and 3 Power Pumps) under Matiranga Upazila. 26. Kukichara Para Subproject (Comprises Construction of 752 m. Irrigation 100% Canal and Supply of one Power Pump) under Khagrachari Sadar Upazila. 27. Lachari Para Subproject (Comprises Construction of 520 m. Irrigation 100% Canal, one drainage Culvert and Installation of 7 Tube Wells) under Ramgarh Upazila. 28. Dataram Para Subproject (Comprises Construction of 185 m. Irrigation 100% Canal, Installation of 10 Tube Wells, Supply of 2 Power Tillers and 2 Power Pumps) under Ramgarh Upazila. 29. Karalyachari Para Subproject (Comprises Supply of 2 Power Pumps and 100% Installation of 8 Tube Wells) under Mahalchari Upazila. 30. Dewan Para Subproject (Comprises Construction of 12 m. Foot Bridge and 100% Installation of 3 Tube Wells) under Mahalchari Upazila. 31. Washu Gakul Para Subproject (Comprises Installation of 4 Tube Wells and 100% Construction of 2 Culverts) under Matiranga Upazila.

57

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 32. Gudambari Para Subproject (Comprises Construction of 100 m. RCC 100% Stair, Installation of 3 Tube Wells, Supply of 2 Power Pumps and one Power Tiller) under Ramgarh Upazila. 33. Monatek Para Subproject (Comprises Installation of 10 Tube Wells, 100% Construction of 430 m. Irrigation Canal, Supply of 2 Power Tillers and 2 Power Pumps) under Mahalchari Upazila. 34. Thali Para Subproject (Comprises Supply of 3 Power Pumps) under 100% Ramgarh Upazila. 35. Tebangchara Para Subproject (Comprises Construction of 700 m. 100% Irrigation Canal and Installation of 8 Tube Wells) under Dighingala Upazila. 36. Dudukchara Para Subproject (Comprises Construction of 510 m. Irrigation 100% Canal, Installation of 250 m. underground Irrigation pipe, 7 Tube Wells and Supply of 2 Power Pumps) under Panchari Upazila. 37. Chowdhagram Para Subproject (Comprises Construction of 380 m. 100% Irrigation Canal, installation of 14 Tube Wells and Supply of 2 Power Tillers) under Matiranga Upazila. 38. Rabijoy Para Subproject (Comprises Installation of one Tube Well with 100% submersible Pump and Supply of one Power Tiller) under Khagrachari Sadar Upazila. 39. Baura Para Subproject (Comprises Construction of 500 m. Irrigation 100% Canal, Supplying of 2 Power Pumps, one Power Tiller and Installation of one Tube Well) under Panchari Upazila. 40. Maratila Para Subproject (Comprises Installation of 4 Tube Well, Supply 100% of Power Tiller one and 2 Power Pumps) under Panchari Upazila. 41. Karga Para Subproject (Comprises Installation of 4 Tube Wells, Supply of 100% 2 Power Tillers and 2 Power Pumps) under Panchari Upazila. 42. Harigopal Para Subproject (Comprises Construction of 300 m. Irrigation 100% Canal, Installation of 4 Tube Wells, Supply of one Power Pump and one Power Tiller) under Panchari Upazila. 43. Jharjari Para Subproject (Comprises Installation of Tube Well- 5 Nos. and 100% Supply of 1 No. Power Tiller) under Dighinala Upazila. 44. Dalu Chailaprue Para Subproject (Comprises Installation of 5 Tube Well, 100% Construction of 515 m. Irrigation Canal, one Foot Bridge, Supply of 2 Power Tillers and 2 Power Pumps) under Manikchari Upazila. 45. Chaila Karbari Para Subproject (Comprises Installation of 6 Tube Wells, 100% re-excavation of one Pond, Construction of one Culvert, Supply of one Power Tiller and one Power Pump) under Manikchari Upazila.

58

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 46. Pidiya Para Subproject (Comprises Construction of 500 m. Irrigation 100% Canal, Supply of 2 Power Tillers and one Power Pump) under Khagrachari Sadar Upazila. 47. Pakujjyachari Para Subproject (Comprises Construction of 600 m. 100% Irrigation Canal and supply 2 Power Pumps) under Khagrachari Sadar Upazila. 48. No. 2 Prakalpa Para Subproject (Comprises construction of 250 m. 100% Irrigation Canal, Supply of 3 Power Tillers and 3 Power Pumps) under Khagrachari Sadar Upazila. 49. Dewan Para Subproject (Comprises Construction of 560 m. Irrigation 100% Canal, Supply of one Power Tiller and 2 Power Pumps) under Khagrachari Sadar Upazila. 50. Jamini Mohan Para Subproject (Comprises Construction of 345 m. 100% Irrigation Canal, Installation of 12 Tube Wells, Supplying of 2 Power Tillers and 2 Power Pumps) under Dighinala Upazila. 51. Jora Bridge Para Subproject (Comprises Installation of 5 Tube Wells, 100% Supplying of 2 Power Tillers and 2 Power Pumps) under Dighinala Upazila. 52. Haladar Para Subproject (Comprises Installation of 6 Tube Wells, 100% Supplying of 2 Power Tillers and 3 Power Pumps) under Panchari Upazila. 53. Durga Moni Para Subproject (Comprises Installation of 5 Tube Wells, 100% Supplying of 3 Power Tillers and 4 Power Pumps) under Panchari Upazila. 54. Puratan Headman Para Subproject (Comprises Construction of 460 m. 100% Irrigation Canal, Supplying of 2 Power Tillers and 2 Power Pumps) under Khagrachari Sadar Upazila. 55. Narendra Karbari Para Subproject (Comprises Installation of 8 Tube 100% Wells, Supplying of one Power Tiller and 2 Power Pumps) under Mohalchari Upazila. 56. Jagat Sen Para Subproject (Comprises Installation of 5 Tube Wells, 100% Supplying of 2 Power Tillers and 2 Power Pumps) under Panchari Upazila. 57. Buddha Ram Para Subproject (Comprises development of 600 m. Village 100% Footpath with brick pavement and installation of 6 Tube Wells) under Panchari Upazila. 58. Badanala Para Subproject (Comprises Installation of 8 Tube Wells, 100% Supplying of 2 Power Tillers and 2 Power Pumps) under Mohalchari Upazila. 59. Headman Para subproject (comprises construction of 500m lined irrigation 100% canal and installation of 13 tubewells) under Matiranga Upazila.

59

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 60. Mejar Para Subproject (Comprises Construction of 300 m. Irrigation 100% Canal, Installation of 6 Tube Wells, Supplying of one Power Tiller and one Power Pump) under Laxmichari Upazila. 61. Ultachari Chairman Para Subproject (Comprises Construction of 500 m. 100% Irrigation Canal, Installation of 10 Tube Wells, Supplying of 2 Power Tillers and 2 Power Pumps) under Mohalchari Upazila. 62. Prabal Tripura Para Subproject (Comprises Construction of 300 m. 100% Irrigation Canal, Installation of 6 Tube Wells and Supplying of 2 Power Tillers) under Manikchari Upazila. 63. Shilachari Para Subproject (Comprises Construction of 350 m. Irrigation 100% Canal, Installation of 3 Tube Wells, Supplying of one Power Tiller and one Power Pump) under Laxmichari Upazila. 64. Shuknachari (Laifu) Para Subproject (Comprises Installation of 24 Tube 100% Well and Construction of 5 U-drains) under Matiranga Upazila 65. Mongla Karbari Para Subproject (Comprises Installation of 9 Tube Wells) 100% under Laxmichari Upazila 66. Ranjan Moni Para Subproject (Comprises Installation of 15 Tube Wells 100% and Supplying of 3 Power Tillers and 2 Power Pumps) under Dighinala Upazila 67. Sushil Headman Para Subproject (Comprises Construction of 300 m. 100% Irrigation Canal, Installation of 2 Tube Wells, Shallow Tube Well- 5 and Supplying of 2 Power Tillers and 3 Power Pumps) under Dighinala Upazila 68. Rangapanichara Para Subproject (Comprises Construction of 450 m. 100% Irrigation Canal, Installation of 7 Tube Wells, Supplying of 2 Power Tillers and Construction of 2 U-drain) under Dighinala Upazila. 69. Changrachari Headman Para Subproject (Comprises Construction of 450 100% m. Irrigation Canal, installation of one Tube Well and Supplying of one Power Pump) under Mohalchari Upazila. 70. Gabamara Para Subproject (Comprises Construction of 510 m. Irrigation 100% Canal, Installation of 4 Tube Wells including one Deep Tube Well with one Power Pump for Irrigation, and Supplying of one Power Tiller) under Manikchari Upazila 71. Pashim Hazachara Para Subproject (Comprises Construction of 320 m. 100% Irrigation Canal, installation of 4 Tube Wells, Supply of one Power Tiller and one Power Pump) under Laxmichari Upazila. 72. Thali Para Subproject (Comprises Installation of 5 Tube Wells, Supply of 100% 2 Power Tillers and 2 Power Pumps) under Khagrachari Sadar Upazila. 73. Baura Para Subproject (Comprises Construction of 645 m. Irrigation 100% Canal, and Supplying of 2 Power Tillers) under Khagrachari Sadar Upazila

60

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 74. Thali Para Subproject (Comprises Installation of 5 Tube Wells, Supply of 100% 2 Power Tillers and 3 Power Pumps) under Manikchari Upazila. 75. Kejoy Para Subproject (Comprises Installation of 3 Tube Wells with 100% Submersible Pump and one Water Tank, Supply of one Power Tiller and 2 Power Pumps) under Manikchari Upazila. 76. Jarulchari Para Subproject (Comprises Installation of 6 Tube Wells, and 100% Supply of 2 Power Tiller) under Dighinala Upazila. 77. Ghat Para Subproject (Comprises Construction of 650 m. Irrigation Canal, 100% Supplying of one Power Tiller and 01 Power Pump) under Khagrachari Sadar Upazila. 78. Achai Para Subproject (Comprises Installation of one Tube Well) under 100% khagrachari Sadar Upazila. 79. Kalabuniya Para Subproject (Comprises Construction of GFS- 1 No., Physically Supplying of Power Tiller- 1 No. and Power Pump- 2 Nos.) under Completed Mohalchari Upazila 80. Adufa Para Subproject (Comprises Installation of 9 Tube Wells and 100% Supply 3 Power Tillers and 2 Power Pumps) under Mohalchari Upazila. 81. Chelachara Para Subproject (Comprises Construction of 520 m. Irrigation 100% Canal, 520 m., Installation of one Tube Well with submersible pump & water tank, Supply of one Power Tiller and one Power Pump) under Khagrachari Sadar Upazila 82. Golabari Headman Para Subproject (comprises Construction of Irrigation 100% Canal- 450 m., Installation of 1 No. Deep Tube Well with Submersible Pump, 1 No. Deep Tube Well for Drinking Water and Construction of Water Tank, Supplying of 1 No. Power Tiller and 2 Nos. Power Pump) under Khagrachari Sadar Upazila 83. Barnal Board Office Para Subproject (Comprises Installation of 3 Nos. 100% Shallow Tube Well and 16 Nos. Deep Tube Well) under Matiranga Upazila 84. Mangal Bikash Para Subproject (Comprises Installation of Deep Tube 100% Well- 7 Nos., Supplying of Power Tiller 2 Nos. and Power Pump 2 Nos. with Delivery Pipe) under Dighinala Upazila 85. Aprusi Para Subproject (Comprises Construction of Irrigation Canal- 765 100% m. with PVC Pipe and Supplying of Power Pump 1 No) under Khagrachari Sadar Upazila 86. Anil Para Subproject (Comprises Construction of Irrigation Canal- 430 m., 100% Installation of Deep Tube Well- 2 Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos.) under Panchari Upazila

61

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 87. Choto Kheda Jhouta Khamar Para Subproject (Comprises Installation of 100% Deep Tube Well- 5 Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos.) under Ramghar Upazila 88. Sonai Aga Para Subproject (Comprises Construction of Irrigation Canal- 100% 415 m., Installation of Shallow Tube Well- 8 Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos. with Delivery Pipe) under Ramghar Upazila 89. Boddyo Para Subproject (Comprises Construction of Irrigation Canal- 440 100% m., Installation of Shallow Tube Well- 7 Nos., Supplying of Power Tiller 2 Nos. and Power Pump 2 Nos. with Delivery Pipe) under Ramghar Upazila 90. Porsuramghat Para Subproject (Comprises Construction of Irrigation 100% Canal- 230 m., Installation of Shallow Tube Well- 10 Nos., Supplying of Power Tiller- 3 Nos. and Power Pump- 4 Nos. with Delivery Pipe) under Ramghar Upazila 91. Natun Para Subproject (Comprises Construction of Irrigation Canal- 415 100% m. with Cross Drain, Installation of Shallow Tube Well- 08 Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos. with Delivery Pipe) under Ramghar Upazila 92. Headman Para Subproject (Comprises Construction of RCC Stair 30 m., 100% Construction of Irrigation Canal- 445 m. Installation of Shallow Tube Well- 3 No., Supplying of Power Tiller- 1 No. and Power Pump- 2 Nos. with Delivery Pipe) under Ramghar Upazila 93. Chairman Tila Subproject (Comprises Construction of Irrigation Canal- 100% 590 m. Installation of Shallow Tube Well- 3 Nos., Supplying of Power Tiller 01 No. and Power Pump 02 Nos. with Delivery Pipe) under Ramghar Upazila 94. Jamini Para Subproject (Comprises Installation of Deep Tube Well- 6 100% Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos. with Delivery Pipe) under Matiranga Upazila 95. Galamoni Para Subproject (Comprises Construction of Irrigation Canal- 100% 380 m., Installation of Deep Tube Well- 4 Nos., Supplying of Power Tiller 1 No. and Power Pump 1 No. with Delivery Pipe) under Matiranga Upazila 96. Raikhong Mog Para Subproject (Comprises Installation of Deep Tube 100% Well- 5 Nos., Supplying of Power Tiller 2 Nos. and Power Pump- 4 Nos. with Delivery Pipe) under Matiranga Upazila. 97. Saday Para Subproject (Comprises Installation of Deep Tube Well- 3 Nos., 100% Supplying of Power Tiller 1 No. and Power Pump- 2 Nos. with Delivery Pipe) under Matiranga Upazila

62

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 98. Mathu Mog Para Subproject (Comprises Construction of Irrigation Canal- 100% 475 m., Installation of Shallow Tube Well- 5 Nos., Supplying of Power Tiller 2 Nos. and Power Pump 2 Nos. with Delivery Pipe) under Matiranga Upazila 99. Dajar Para Subproject (Comprises Installation of Deep Set Tube Well- 5 100% Nos., Supplying of Power Tiller 2 Nos. and Power Pump- 2 Nos. with Delivery Pipe) under Dighinala Upazila 100. Nunchari Para Subproject (Comprises Construction of Irrigation Canal- 100% 300 m., Installation of Deep Tube Well- 2 Nos., Shallow Tube Well- 1 No., Supplying of Power Tiller 2 Nos. and Power Pump 1 No. with Delivery Pipe) under Dighinala Upazila 101. Katarung Para Subproject (Comprises Construction of Irrigation Canal- 100% 470 m., Installation of Shallow Tube Well- 4 Nos., Supplying of Power Tiller 2 Nos. and Power Pump 2 No. with Delivery Pipe) under Dighinala Upazila 102. Khullayang Para Subproject (Comprises Installation of Deep Tube Well- 100% 1 No. with 4 HP Submersible Pump for Irrigation, Shallow Tube Well- 10 Nos., Supplying of Power Tiller 2 Nos. and Power Pump 1 No. with Delivery Pipe) under Mohalchari Upazila. 103. Edohulo Para Subproject (Comprises Installation of Deep Tube Well- 5 100% Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos.) under Mohalachari Upazila 104. Jowtha Khamar Para (Comprises Installation of Deep Tube Well- 4 Nos., 100% Construction of RCC Stair- 40 m. for Water Collection, Supplying of Power Tiller 1 No. and Power Pump 2 Nos. with Delivery Pipe) under Mohalchari Upazila 105. Lambar Para Subproject (Comprises Installation of Deep Tube Well- 6 100% Nos., Supplying of Power Tiller 2 Nos. and Power Pump- 2 Nos. with Delivery Pipe) under Mohalchari Upazila 106. Sapmara Tripura Para Subproject (Comprises Installation of Deep Tube 100% Well- 5 Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 3 Nos.) under Manikchari Upazila 107. Cheprue Para Subproject (Comprises Installation of Deep Tube Well- 2 100% Nos. with 4 HP Submersible Pump for Irrigation and Shallow Tube Well- 6 Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos.) under Manikchari Upazila 108. Kalapani Para Subproject (Comprises Installation of Shallow Tube Well- 100% 3 Nos., Deep Tube Well- 3 Nos. for Drinking and Deep Tube Well- 2 Nos. with 4 HP Submersible Pump for Irrigation and Supplying of Power Tiller 2 Nos.) under Manikchari Upazila

63

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 109. Kumari Para Subproject (Comprises Construction of Irrigation Canal- 340 100% m., Installation of Shallow Tube Well- 8 Nos., Supplying of Power Tiller 3 Nos. and Power Pump 3 Nos.) under Manikchari Upazila 110. Koilash Mohajan Para (Comprises Construction of Irrigation Canal-680 100% m., Installation of Shallow Tube Well- 3 Nos., Supplying of Power Tiller 1 No. and Power Pump 1 No.) under Laxmichari Upazila 111. Dewan Para Subproject (Comprises Construction of Irrigation Canal- 490 100% m. with Cross Drain, Installation of Deep Tube Well- 1 No. & Shallow Tube Well- 3 Nos., Supplying of Power Tiller- 1 No. and Power Pump- 2 Nos. with Delivery Pipe) under Laxmichari Upazila 112. Binajuri Para Subproject (Comprises Installation of Deep Tube Well- 5 100% Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 1 No. with Delivery Pipe) under Laxmichari Upazila 113. Mura Para Subproject (Comprises Construction of Foot Bridge- 1 No., 100% Installation of Deep Tube Well- 4 Nos. Supplying of Power Tiller- 2 Nos. (12 HP) and Power Pump- 3 Nos. 10 HP) under Mohalchari Upazila. 114. Barathali Para Subproject (Comprises Construction of Foot Bride- 7 m., 100% Irrigation Canal- 300 m., Installation of Shallow Tube Well- 20 Nos. Supplying of Power Tiller- 1 No. and Pump Machine- 1 No) under Matiranga Upazila. 115. Ultachari Bhihar Para Subproject (Comprises Construction of Irrigation 100% Canal- 400 m., Installation of Deep Tube Well- 3 Nos., Shallow Tube Well- 4 Nos., Supplying of Power Tiller- 2 Nos. and Pump Machine- 1 No.) under Mohalchari Upazila. 116. School Para Subproject (Comprises Installation of Deep Tube Well- 5 100% Nos) under Khagrachari Sadar Upazila 117. Dewan Para Subproject (Comprises Installation of Deep Tube Well-6 Nos. 100% (2 Nos. for Irrigation and 4 Nos. for Drinking), Supplying of Power Tiller- 1 No. 12 HP and Power Pump Machine- 1 No. 12 HP) under Matirnaga (Tabalchari) Upazila 118. Agya Karbari Para Subproject (Comprises Installation of Deep Tube Well- 100% 4 Nos., Shallow Tube Well- 4 Nos., Supplying of Power Tiller- 2 Nos. (12 HP) and Power Pump- 2 Nos. (6 HP) under Manikchari Upazila 119. Mangal Chan Para Subproject (Comprises Construction of Irrigation 100% Canal- 400 m., Installation of Deep Tube Well- 2 Nos., Shallow Tube Well- 1 No., Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump- 2 Nos.) under Khagrachari Sadar Upazila 120. Rannyama Chara Para Subproject (Comprises Construction of Stair- 80 100% m., Installation of Deep Tube Well- 4 Nos. and Shallow Tube Well- 1 No.) under Laxmichari Upazila.

64

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 121. Sumanta Para Subproject (Comprises Construction of Irrigation Canal- 100% 380 m., Installation of Deep Tube Well- 3 Nos., Supplying of Power Tiller- 1 No. (12 HP) and Power Pump Machine- 1 No. 8 HP) under Laxmichari Upazila. 122. Tindukchari Para Subproject (Comprises Installation of Deep Tube Well- 80% 5 Nos., Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump Machine- 2 Nos. 12 HP) under Mohalchari Upazila. 123. Bhuinya Para Subproject(Comprises Construction of Irrigation Canal- 300 100% m., Installation of Deep Tube Well- 8 Nos., Supplying of Power Tiller- 1 No. 12 HP and Power Pump Machine- 1 No. 12 HP) under Matiranga Upazila. 124. Gulakana Para Subproject (Comprises Installation of Deep Tube Well- 5 100 % Nos., Supplying of Power Tiller- 3 Nos. 12 HP and Power Pump Machine- 1 No. 12 HP) under Khagrachari Sadar Upazila. 125. Madhya Betchari Para Subproject (Comprises Construction of Irrigation 100% Canal- 610 m., Installation of Shallow Tube Well- 2 Nos., Supplying of Power Tiller- 1 No. 12 HP and Power Pump Machine- 2 Nos.) under Khagrachari Sadar Upazila. 126. Dogyo Karbari Para Subproject (Comprises Installation of Shallow Tube 100% Well- 6 Nos., Supplying of Power Tiller- 3 Nos. 12 HP and Power Pump Machine- 1 No. 12 HP) under Manikchari Upazila. 127. Ananda Mohan Para Subproject (Comprises Installation of 8 (Eight) Nos. 100% Shallow Tube Well, Supplying of Power Tiller- 4 Nos. and Power Pump- 4 Nos.) under Panchari Upazila 128. Uttar Tarabunia Subproject (Comprises Construction of Irrigation Canal- 100% 340 m., Installation of 4 Nos. Deep Tube Well, Supply of 2 Nos. Power Tiller and 2 Nos. 12 HP Power Pump Machine) under Dighinala Upazila 129. Kala Para Subproject (Comprises Construction of Foot Bridge- 1 No. and 100% Installation of Deep Tube well- 5 Nos.) under Khagrachari Sadar Upazila. 130. Battali Para Subproject (Comprises Construction of Irrigation Canal- 450 100% m., Installation of Shallow Tube Well- 5 Nos., Supplying of Power Tiller- 2 Nos., and Power Pump- 2 Nos. with Delivery Pipe) under Laxmichari Upazila 131. Akbari Para Subproject (Comprises Installation of Deep Tube Well- 5 100% Nos., Supplying of Power Tiller- 1 No. and Power Tiller- 2 Nos. with Delivery Pipe) under Mohalchari Upazila 132. Achalong Para Subproject (Comprises Construction of Irrigation Canal- 100% 545 m., Installation of Shallow Tube Well- 7 Nos., Supplying of Power Tiller 1 No. and Power Pump 2 Nos.) under Matiranga Upazila

65

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 133. Kukichara Marma Para Subproject (Comprises Construction of Irrigation Physically Canal- 230 m., Installation of 2 Nos. Deep Tube Well (152 m.) with 4 HP Completed Power Pump and 08 Nos. Shallow Tube Wells, Supplying of Power Tiller 01 No. and Power Pump 01 No. (12 HP) with 4´´ Centrifugal Pump) under Ramghar Upazila 134. Surendra Master Para Subproject (Comprises Construction of Irrigation 100% Canal- 450 m., Installation of Deep Tube Well- 3 Nos., Supplying of 1 No. Power Tiller (12 HP) and 1 No. Power Pump 12 HP) under Khagrachari Sadar Upazila 135. Thoaichai Karbari Para Subproject (Comprised Installation of Deep Tube 100% Well-5 Nos. for Drinking, Installation of Deep Tube Well- 1 No. with 4 HP Water Pump for Irrigation, Supplying of Power Tiller-2 Nos. 2 HP and Power Pump- 3 Nos. 6 HP) under Manikchari Para 136. Bandarchara Para Subproject (Comprises Construction of Irrigation Canal- 90% 450 m., Installation of Deep Tube Well- 1 No., Shallow Tube Well- 15 Nos., Supplying of Power Pump- 1 No. 16 HP with Delivery Pipe) under Matiranga Upazila 137. Dayal Kumar Para Subproject (Comprises Construction of Irrigation 100% Canal- 115 m., Installation of Deep Tube Well-1 No., Shallow Tube Well- 1 No. for Drinking, Deep Tube Tube Well- 3 Nos. with 4 HP Power Pump for Irrigation and Supplying of Power Tiller- 1 No. 12 HP) under Manikchari 138. Malongi Para Subproject (Comprises Installation of Deep Tube Well- 2 100% Nos. with 4 HP Power Pump, Shallow Tube Well- 10 Nos., Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump- 1 No. 12 HP) under Manikchari Upazila 129. Uttar Suknachari Para Subproject (Comprises Installation of Deep Tube 100% Well- 4 Nos. for Drinking, Deep Tube Well- 1 No. for Irrigation with 4 HP Water Pump, Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump- 2 Nos. 8 HP with Delivery Pipe.) under Laxmichari Upazila 140. Natun Bagan Para Subproject (Comprises Installation of Deep Tube Well- 100% 7 Nos). under Khagrachari Sadar Upazila 141. Indrajoy Karbari Para Subproject (Comprises Installation of Deep Tube 100% Well- 2 Nos. 152 m. with 4 HP Power Pump for Irrigation, Deep Tube Well- 1 No., Shallow Tube Well- 8 Nos, Supplying of Power Tiller 02 Nos. 12 HP and Power Pump 2 Nos. 6 HP) under Dighinala Upazila 142. Danga Bazar Para Subproject (Comprises Construction of Irrigation 100% Canal- 350 m., Installation of Shallow Tube Well- 7 Nos., Supplying of Power Tiller- 03 Nos. 12 HP and Power Pump- 2 Nos. 12 HP) under Dighinala Upazila.

66

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 143. Madhya Banchara Para Subproject (Comprises Installation of Shallow 100% Tube Well- 9 Nos., Supplying of Power Tiller 04 Nos. 12 HP and Power Pump 2 Nos. 6 HP) under Dighinala Upazila. 144. Baghya Para Subproject (Comprises Construction of Irrigation Canal- 185 70% m., Installation of Deep Tube Well- 4 Nos. for Drinking, Deep Tube Well- 1 No. for Irrigation, Supplying of Power Tiller- 1 No. 12 HP and Power Pump- 2 Nos. 6 HP) under Laxmichari Upazila. 145. Jaduganala Para Subproject (Comprises Installation of Shallow Tube 100% Well- 4 Nos., Deep Tube Well- 2 Nos. with 4 HP Power Pump for Irrigation, Supplying of Power Tiller- 03 Nos. 12 HP and Power Pump- 3 Nos. 6 HP) under Mohalchari Upazila. 146. Jarichandra Para Subproject (Comprises Construction of Irrigation Canal- 100% 550 m., Installation of Shallow Tube Well- 4 Nos., Supplying of Power Tiller- 01 No. 12 HP and Power Pump- 01 No. 12 HP) under Matiranga Upazila. 147. Indramuni Karbari Para Subproject (Comprises Construction of Irrigation 100% Canal- 330 m., Installation of Shallow Tube Well- 8 Nos., Supplying of Power Tiller 03 Nos. 12 HP and Power Pump 2 Nos. 4 HP-1 & 12 HP-1) under Dighinala Upazila. 148. Dhonya Chandra Karbari Para (Comprises Construction of Irrigation 100% Canal- 465 m., Installation of Shallow Tube Well- 1 No., Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump- 2 Nos. 12 HP) under Panchari Upazila. 149. Padmini Para Subproject (Comprises Installation of Deep Set Tube Well- 100% 6 Nos. with Stone Cutting, Supplying of Power Tiller 01 No. 12 HP and Power Pump 2 Nos. 4 HP) under Panchari Upazila 150. Dhani Karbari Para Subproject (Comprises Construction of Irrigation 100% Canal- 590 m., Installation of Shallow Tube Well- 6 Nos., Supplying of Power Tiller- 01 No. 12 HP and Power Pump- 01 No. 12 HP) under Matiranga Upazila. 151. Noa Para Subproject (Comprises Installation of Shallow Tube Well- 12 100% Nos., Deep Tube Well- 3 Nos., Supplying of Power Tiller- 01 No. 12 HP and Power Pump- 01 No. 12 HP) under Matiranga Upazila. 152. Bacha Morong Para Subproject (Comprises Construction of Irrigation 100% Canal- 415 m., Installation of Shallow Tube Well- 7 Nos., Supplying of Power Tiller- 03 Nos. 12 HP and Power Pump- 2 Nos. 12 HP) under Dighinala Upazila. 153. Samburai Para Subproject (Comprises Construction of Irrigation Canal- 100% 465 m., Installation of Shallow Tube Well- 1 No., Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump- 2 Nos. 12 HP) under Panchari Upazila.

67

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 154. Karalyachari Vitar Para Subproject (Comprises Construction of Stair- 60 Physically m., Installation of Deep Tube Well- 2 Nos., Shallow Tube Well- 5 Nos., Completed Supplying of Power Tiller- 2 Nos. and Power Tiller- 2 Nos.) under Mohalchari Upazila 155. Kanungo Para Subproject (Comprises Construction of HBB Footpath- 750 100% m., Irrigation Canal-600 m., Supplying of Power Tiller-1 No. and Power Tiller- 1 No.) under Panchari Upazila. 156. Prarthana Para Subproject (Comprises Construction of Irrigation Canal- 100% 218 m., Stair-45 m., Installation of Deep Tube Well- 5 Nos., Supplying of Power Tiller-1 No. and Power Pump-1 No.) under Matiranga Upazila. 157. Baradona Para Subproject (Comprises Construction of Irrigation Canal-42 QER under m., Installation of Shallow Tube Well- 5 Nos., Supplying of Power Tiller- Process 2 Nos. and Power Pump- 3 Nos.) under Laxmichari Upazila. 158. Sarba Siddhi Para Subproject (Comprises Construction of Stair- 20 m., Physically Installation of Ring Well- 6 Nos. Supplying of Power Tiller- 2 Nos.) under Completed Matiranga Upazila 159. Jamindhan Para Subproject (Comprises Construction of Irrigation Canal- 90% 538 m., Installation of Deep Tube Well- 1 No., Shallow Tube Well-2 Nos. and Supplying of Power Tiller- 2 Nos.) under Panchari Upazila. 160. Rabishing Para Subproject (Comprises Construction of Irrigation Canal- 100% 542 m., Installation of Shallow Tube Well- 3 Nos. Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos. 4 HP) under Panchari Upazila. 161. Badi Para Subproject (Comprises Construction of Irrigation Canal- 470 m. 100% and Installation of Deep Tube Well- 4 Nos. under Laxmichari Upazila. 162. Birendra Karbari Para (Comprises Construction of Irrigation Canal- 485 100% m., Installation of Shallow Tube Well- 4 Nos., Supplying of Power Tiller- 2 Nos. 12 HP, Power Pump- 2 Nos. 12 HP) under Panchari Upazila. 163. Kalinga Para Subproject (Comprises Construction of Irrigation Canal- 240 100% m., Installation of Deep Tube Well- 6 Nos., Supplying of Power Tiller- 1 No. 12 HP and Power Pump- 1 No. 6 HP) under Matiranga Upazila. 164. Reyong Mrong Para Subproject (Comprises Construction of Irrigation 100% Canal- 590 m., Installation of Shallow Tube Well- 3 Nos., Supplying of Power Tiller-1 No. 12 HP and Power Pump-3 Nos.) under Rangarh Upazila. 165. Badhya Para Subproject (Comprises Installation of Deep Tube Well- 4 100% Nos. for Drinking and Deep Tube Well- 1 No. for Irrigation with 4 HP Water Pump, Supplying of Power Tiller- 1 No. 12 HP and Power Pump- 2 Nos. 4 HP-1 & 6 HP-1) under Laxmichari Upazila. 166. Katubchari Para Subproject (Comprises Construction of Irrigation Canal- 90% 600 m, Installation of Shallow Tube Well- 4 Nos., Supplying of Power

68

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works Tiller- 1 No. 12 HP and Power Pump- 1 No. 12 HP) under Laxmichari Upazila. 167. Shuknachari Baura Para Subproject (Comprises Installation of Deep Tube 100% Well- 1 No, Deep Tube Well- 4 Nos., Supplying of Power Tiller- 2 Nos., Power Pump- 2 Nos. 6 HP) under Panchari Upazila. 168. Rahindra Para Subproject (Comprises Installation of Deep Tube Well- 5 100% Nos.) under Panchari Upazila. 169. Abani Karbari Para Subproject (Comprises Construction of Irrigation 100% Canal- 450 m. Installation of Shallow Tube Well- 5 Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos.) under Panchari Upazila. 170. Shilaban Para Subproject (Comprises Installation of Deep Tube Well- 4 100% Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos.) under Mohalchari Upazila. 171. Kalapani Mansur Para Subproject (Comprises Installation of Deep Tube 100% Well- 8 Nos., Shallow Tube Well- 8 Nos. and Supplying of Power Tiller- 1 No. under Matiranga Upazila. 172. Kalapanichara Para Subproject (Comprises Installation of Deep Tube 100% Well- 4 Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos.) under Khagrachari Sadar Upazila. 173. Kalabuniya Para Subproject (Comprises Construction of GFS- 1 No., 100% Supplying of Power Tiller- 1 No. and Power Pump- 2 Nos.) under Mohalchari Upazila 174. Senguli Para Subproject (Comprises Construction of Irrigation Canal- 615 Physically m., Installation of Shallow Tube Well- 4 Nos., Supplying of Power Tiller- Completed 1 No. 12 HP and Power Pump- 1 No. 12 HP) under Ramgarh Upazila. 175. Dewan Para Subproject (Comprises Construction of Irrigation Canal- 250 100% m., Installation of Deep Tube Well- 8 Nos., Supplying of Power Tiller- 1 No. and Power Pump- 1 No.) under Laxmichari Upazila. 176. Kangchairi Para Subproject (Comprises Construction of Irrigation Canal- QER under 230 m., Installation of Deep Tube Well- 8 Nos., Supplying of Power Tiller- Process 1 No. and Power Pump- 1 No.) under Panchari Upazila. 177. Dhananjoy Dewan Para Subproject (Comprises Construction of Irrigation 100% Canal- 440 m., Installation of Deep Tube Well- 1 No., Shallow Tube Well- 2 Nos. and Supplying of Power Tiller- 1 No.) under Khagrachari Sadar Upazila. 178. Rangapanichara Para Subproject (Comprises Installation of Deep Tube 100% Well- 1 No., Shallow Tube Well- 5 Nos. Supplying of Power Tiller- 2 Nos. and Power Pump- 2 Nos.) under Khagrachari Sadar Upazila. 179. Chadurkhil Para Subproject (Comprises Construction of Irrigation Canal- 70% 330 m., Installation of Deep Tube Well- 2 Nos., Shallow Tube Well- 4

69

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works Nos., Supplying of Power Tiller- 2 Nos. and Power Pump- 1 No.) under Manikchari Upazila. 180. Nilakumar Karbari Para Subproject (Comprises Construction of Stair- 6 Physically m., Box Culvert- 1 No., Supplying of Power Tiller- 2 Nos. 12 HP and Completed Power Pump- 1 No. 6 HP) under Laxmichari Upazila 181. Kista Mohan & Baghya Mojahan Para Subproject (Comprises Installation 100% of Deep Tube Well- 2 Nos., Shallow Tube Well- 3 Nos., Supplying of Power Tiller- 2 Nos. 12 HP, and Power Tiller- 2 Nos. 6 HP) under Panchari Upazila. 182. Uttar Mohalchara Para Subproject (Comprises Installation of Deep Tube 100% Well- 2 Nos. with Submersible Pump and Deep Tube Well- 1 No.) under Khagrachari Sadar Upazila. 183. Sudha Aung Member Para Subproject (Comprises Installation of Deep On Going Tube Well- 2 Nos., Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump- 2 Nos. 6 HP) under Khagrachari Sadar Upazila. 184. Toi Chakma Para Subproject (Comprises Installation of Deep Tube Well- Physically 2 Nos., Shallow Tube Well- 8 Nos., Supplying of Power Tiller- 3 Nos. 12 Completed HP and Power Pump- 4 Nos. 8 HP- 1 & 4 HP-3) under Ramgarh Upazila. 185. Bara Para (Comprises Installation of Deep Tube Well- 7 Nos.) under 100% Khagrachari Sadar Upazila. 186. Pong Para Subproject (Comprises Construction of U-Culvert- 2 Nos., 100% Installation of Deep Tube Well-1 No., Shallow Tube Well- 15 Nos., Supplying of Power Tiller- 2 Nos. 12 HP) under Matiranga Upazila. 187. Tabalchari Para Subproject (Comprises Installation of Deep Tube Well-2 Physically No., Shallow Tube Well- 5 Nos., Supplying of Power Tiller- 3 Nos. 12 HP Completed and Power Pump- 1 No. 12 HP) under Mohalchari Upazila. 188. Apurna Para Subproject (Comprises Installation of Deep Tube Well- 4 On Going Nos. with Stone Cutting, Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump- 2 Nos. 12 HP-1 & 6 HP-1) under Matiranga Upazila. 189. Pradip Para Subproject (Comprises Installation of Deep Tube Well- 2 Nos. Physically for Irrigation, Deep Tube Well- 4 Nos. Supplying of Power Tiller- 2 Nos. Completed 12 HP and Power Pump- 2 Nos. 6 HP) under Panchari Upazila. 190. Nabinchandra Para Subproject (Comprises Construction of Irrigation 100% Canal- 425 m., Installation of Deep Tube Well- 5 Nos., Supplying of Power Tiller- 1 No. and Power Pump- 1 No. 12 HP) under Panchari Upazila. 191. Ningchai Karbari Para Subproject (Comprises Construction of Stair- 25 On Going m., Installation of Deep Tube Well- 2 and Supplying of Power Pump- 1 No. 15 HP) under Manikchari Upazila.

70

Environmental Monitoring Report July – December 2018

Status of Sl.№ Name of subprojects works 192. Takal Moni Para Subproject (Comprises Construction of Box Culvert- 1 100% No., Foot Bridge- 12 m., Installation of Deep Tube Well- 3 Nos. with Stone Cutting, Shallow Tube Well- 8 Nos., and Supplying of Power Tiller- 1 No. 12 HP and Power Pump- 1 No. 6 HP with Delivery Pipe) under Matiranga Upazila. 193. Battala Para Subproject (Comprises Construction of Box Culvert- 1 No., 100% Installation of Deep Tube Well- 2 Nos., Shallow Tube Well- 5 Nos., Supplying of Power Tiller- 2 Nos. 12 HP and Power Pump- 2 Nos. 12 HP) under Ramgarh Upazila 194 Laba Para Subproject (Comprises Supplying of Power Tiller- 2 Nos, and 50% Power Pump 1 No. 12 HP) under Mohalchari Upazila 195. Keshab Mohajan Para Subproject (Comprises Construction Water Tank 100% with Submersible Pump (1 HP), Installation of Ring Well-6 Nos., Supplying of Power Tiller- 1 No. and Power Pump- 2 Nos.) under Matiranga Upazila. 196 Antu Para (Comprises Construction of Stair- 30 m. and Installation of On Going Deep Tube Well- 6 Nos.) under Ramgarh Upazila 197. Mongcheu Karbari Para (Comprises Construction of Irrigation Canal- 630 On Going m., Installation of Shallow Tube Well- 5 Nos., Supplying of Power Tiller- 1 No. and Power Pump- 1 No.) under Manikchari Upazila 198. Jatindra Karbari Para (Comprises Installation of Deep Tube Well- 6 Nos., On Going Supplying of Power Tiller- 1 No. and Power Pump- 1 No.) under Laxmichri Upazila. 199. Chandranath Chairman Para (Comprises Construction of Irrigation Canal- On Going 560 m., Installation of Shallow Tube Well- 2 Nos., Supplying of Power Tiller- 1 No. and Power Pump- 1 No.) under Panchari Upazila. 200. Ramshing Dewan Para (Comprises Construction of GFS- 1 No., Supplying On Going of Power Tiller-1 No. and Power Pump- 1 No.) under Panchari Upazila 201 Mathai Pukur Para (Comprises Construction of GFS- 1 No.) under QER under Khagrachari Sadar Upazila. Process

Rangamati District

Status of S/N Name of sub-projects works 1 Sapchari Wagga Para Subproject (comprises construction of 117 sqm 100% market shed, improvement of 1.53 km earthen road to rigid pavement,

71

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works construction of one foot bridge, and infiltration gallery including water distribution system for supply of drinking water) under 2 PurbaKodala Sub-project (comprises installation of 2 tubewells, supply of 100% 4 power tillers and 6 power pumps) under KaptaiUpazila 3 Muralipara Sub-project (comprises installation of 4 tubewells, 2 Water 100% Reservoirs & water distribution) under KaptaiUpazila 4 Sacrachari sub-project (comprises 2 Water Reservoirs & water 100% distribution for irrigation , 1 Power tiller & 2 Power pumps) under Kaptai Upazila 5 MitingachariMarma Para Subproject (comprises development of water 100% reservoir ,distribution water supply and installation of tube wells) under Kaptai Upazila 6 Vazzyatuli Para Subproject (Comprise construction of HBB Road) under 100% Kaptai Upazila 7 Valukkya Tinchari para subproject (comprises installation 5nos Tube well, 100% 2nos power tiller 4nos pump machine) under Kaptai upazila 8 Balamchari para subproject (comprises installation 5nos Tube well, 3nos 100% power tiller 2nos pump machine) under Kaptai upazila 9 Hapchari para subproject (comprises installation 5nos Tube well, 2nos 100% power tiller 4nos pump machine) under Kaptai upazila 10 Lokkidhan Karbari para subproject (comprises installation 4nos Tube 100% well, 2nos power tiller 4nos pump machine) under Kaptai upazila 11 Chongrachari mukh para subproject (comprises installation 4nos Tube 100% well, 3nos power tiller 5nos pump machine) under Kaptai upazila 12 Chakua para subproject (comprises installation 4nos Tube well, 3nos 50% power tiller 4nos pump machine) under Kaptai upazila 13 Chitmaram Ahga para subproject (comprises 3nos power tiller 4nos pump 100% machine) under Kaptai upazila 14 Becharam Karbari para subproject (comprises installation 4nos Tube well, 100% 2nos power tiller 4nos pump machine) under Kaptai upazila 15 Karigar para Marketshed subproject 100% 16 Jibtali Headman Para Subproject (comprises improvement of 1km HBB 100% village access road , construction of market shed, and installation of 5 tube wells installation) under Sadar Upazila 17 BodhipurPara Subproject (comprises construction of marketshed,supply 100% of 3 power tillers and 6 pumps 3 Ring wells) under Sadar Upazila

72

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 18 Mubachari Para Subproject(comprises construction of 94m stairs, 100% installation of 2 tubewells, and supply of 2 power tillers and 4 power pumps) under Sadar Upazila. 19 Morongchari Para Subproject (comprises construction of 15m long 100% footbridge, two box culverts, one stair, installation of two tube wells for drinking water, and supply of 3 power tillers and 6 power pumps for improvement of agriculture) under Sadar Upazila 20 Kuramara Para Subproject (comprises construction of 15m foot bridge, 100% installation of 1 tube well 2 Ring wells, supply of 3 power tillers and 6 power pumps) under SadarUpazila 21 Karetkaba Sub-project(comprises supply of 4 power tillers and 8 power 100% pumps) under Sadar Upazila 22 KaindaDozorPara Sub-project (comprises supply of 4 power tillers and 6 100% power pumps, installation of 2 tube wells and construction of one foot bridge) under SadarUpazila 23 Goboghona Para Sub-project (comprises supply of 2 power tillers and 4 100% power pumps , 5 Tube wells ) under Sadar Upazila 24 Devachari to Bangchari Para Subproject (comprises improvement of 100% 2.5km earthen village access road to brick pavement, construction of 200m road side drains, 45m guide walls, and 2 cross drains) under Sadar Upazila ( CDC) 25 Devachari Para Subproject (comprises development of watershed) under 100% Sadar Upazila 26 Chegeychari Subproject (comprises improvement of 3km HBB village 100% access road ,installation of 6 tube wells and Water Reservoir) under SadarUpazila 27 Kharikyong para subproject (comprises installation 5nos Tube well, 2nos 100% power tiller 4nos pump machine) under Sadar upazila 28 Badalchari para subproject (comprises installation 6nos Tube well, 2nos 100% power tiller 2nos pump machine) under Sadar upazila 29 Navanga para subproject (comprises installation 4nos Tube well, 2nos 100% power tiller 5nos pump machine) under Sadar upazila 30 Kamilachari para subproject (comprises construction 1.5 HBB Road) 100% under Sadar upazila 31 Mashya para subproject (comprises installation 5nos Tube well, 2nos 100% power tiller 4nos pump machine) under Sadar upazila 32 Jibtali Chairman para subproject (comprises installation 1no Tube well, 100% Water Reservoir and Footbridge) under Sadar upazila

73

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 33 Kaindya dozori para subproject (comprises Construction 1.5 HBB Road) 100% under Sadar upazila 34 Kaindya dozor para subproject (comprises WMC activities) under Sadar 100% upazila 35 Putichari para subproject (comprises installation 5nos Tube well, 3nos 100% power tiller 1nos pump machine) under Sadar upazila 36 Aguzzyachari para subproject (comprises Installation 3nos power tiller 100% 4nos pump machine) under Sadar upazila 37 Sukorchari para subproject (comprises installation 9nos Tube well) under 100% Sadar upazila 38 Basanta Pangkuya para subproject (comprises Construction of GFS) under 100% Sadar upazila 39 Khamar para subproject (comprises installation 3nos Tube well, 3nos 100% power tiller 4nos pump machine) under Sadar upazila 40 Amtali Para Sub-project (comprises installation of 5 tube wells, supply of 100% 2 power tillers and 4 power pumps) under RajsthaliUpazila 41 Kuturia Para Subproject (comprises improvement of 1km earthen village 100% access road to brick pavement, construction of 100m road side drains and one cross drain, installation of 5 tubewells, supply of 2 power tillers and 4 power pumps ) underRajsthaliUpazila 42 Naraichari Sub-project (comprises installation of 4 tube wells, supply of 2 100% power tillers and 4 power pumps) under RajsthaliUpazila 43 BimaChara Para Subproject (comprises improvement of 1km earthen 100% village access road to brick pavement, construction of 100m road side drains and 25m guide wall, 250 irrigation canals, supply of 2 Power Tillers,4 Pump pumps, and installation of 2 tubewells) under RajsthaliUpazila 44 MobboiPara Subproject (comprises installation of 5 tubewells, supply of 100% 2 power tillers and 4 power pumps) under RajsthaliUpazila 45 Noyajiri Para Subproject (comprises improvement of 670m earthen road 100% to brick pavement including construction of 105m guide wall, one cross drain and 28m road side drain,130m long RCC stair, supply of 1 power tiller and 2 power pumps) under RajasthaliUpazila 46 Taitong Para Subproject (comprises development of water reservoir and 100% installation of tube wells) under RajsthaliUpazila 47 RamatiaPara Subproject (comprises installation of 1production tubewell, 100% supply of 2 power tillers,4power pumps and construction of irrigation drain-100m) underRajsthaliUpazila

74

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 48 KakrachariUpar Para Sub-project (comprises supply of 4 power tillers and 100% 6 power pumps) underRajsthaliUpazila 49 Buri Para Sub-project (comprises supply of 2 power tillers and 4 power 100% pumps ,5 tube wells) underRajsthaliUpazila 50 Kamalchari Para Sub-project (comprises Installation of 4 nos tubewell, 100% supply of 3 power tillers and 3 power pumps) underRajsthaliUpazila 51 Bangalhalia Bihar Para Sub-project (comprises supply of 5 power tillers 100% and 6 power pumps) underRajsthaliUpazila 52 Kakrachari Bihar Para Sub-project (comprises Instllation of 4 no’s 100% Tubewell, supply of 3 power tillers and 4 power pumps) underRajsthaliUpazila 53 Kola Para Sub-project (comprises supply of 2 power tillers and 4 power 100% pumps , 5 tube wells) under KawkhaliUpazila 54 Poapara Subproject (comprises construction of marketshed and supply of 100% 5 power tillers and 8 power pumps) under KawkhaliUpazila 55 Samukchari Sub-project (comprises supply of 2 power tillers and 4 power 100% pumps) under KawkhaliUpazila 56 Bagkhaiyaghona Para Sub-project (comprises supply of 2 power tillers and 100% 4 power pumps) under KawkhaliUpazila 57 Dupchari Sub-project (comprises supply of 2 power tillers and 4 power 100% pumps) under KawkhaliUpazila 58 Lungi Para Sub-project (comprises supply of 2 power tillers and 5 power 100% pumps , 5 tube wells) under KawkhaliUpazila 59 Harangi Para Sub-project (comprises installation of 6 tube wells, supply 100% of 2 power tillers and 4 power pumps) under KawkhaliUpazila 60 Boga Para Sub-project (comprises installation of 5 tube wells, supply of 2 100% power tillers and 7 power pumps) under KawkhaliUpazila 61 Harincharamukh Sub-project (comprises installation of 5 tube wells, 100% supply of 3 power tillers and 5 power pumps) under KaukhaliUpazila 62 Baradulu Para Sub-project (comprises construction of 300m 100% irrigation,installation of 3 tube wells, supply of 2 power tillers and 4 power pumps) under Kaukhali Upazila 63 Mitingyachari Subproject (comprises improvement of 1.85 km earthen 100% village access road to brick pavement (HBB) including construction of 66m guide walls, 200m road side drains and 85m causeway , installation of 4 tube wells, supply of 4 power tillers and 4 power pumps) under KawkhaliUpazila 64 Chotodulu Para -Triratnankur Uttar Para Subproject (comprises 100% improvement of 1.0 km earthen village access road to brick pavement

75

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works (HBB) including construction of 20m guide walls, and 100m road side drains) under KawkhaliUpazila 65 Chelachara to Haranggi High School Para Subproject (comprises 100% improvement of 2.5km earthen village access road to brick pavement, construction of 200m road side drains, 45m guidewalls, and 2 cross drains) under Kawkhali Upazila 66 Nich Para Sub-project (comprises supply of 2 power tillers 4 power pumps 100% installation of 5 tube well, 12.2m foot bridge) under Kawkhali Upazila 67 Headman Para Sub-project (comprises supply of 2 power tillers 4 power 100% pumps installation of 5 tube well) under Kawkhali Upazila 68 Manikchara Para Sub-project (comprises supply of 2 power tillers 4 power 100% pumps installation of 5 tube well) under Kawkhali Upazila 69 Boroichari Para Sub-project (comprises supply of 2 power tillers 5 power 100% pumps installation of 5 tube well) under Kawkhali Upazila 70 Garichara Para Sub-project (comprises supply of 2 power tillers 5 power 100% pumps installation of 5 tube well, 13.72m foot bridge) under Kawkhali Upazila 71 Chawdury Para Sub-project (comprises supply of 3 power tillers 4 power 100% pumps installation of 4 tube well) under Kawkhali Upazila 72 Dabuabakur Para Sub-project (comprises supply of 2 power tillers 3 power 100% pumps) under Kawkhali Upazila 73 Chelachara para Sub-project(comprises supply of 2 power tillers 4 power 80% pumps installation of 4 tube well) under Kawkhali Upazila 74 Hatimara para Sub-project(comprises supply of 2 power tillers 5 power 80% pumps installation of 5 tube well) under Kawkhali Upazila 75 Pankhoa Para Subproject (comprises construction of 238m stairs, supply 100% of 3 power tillers and 6 power pumps) under BelaichariUpazila 76 Devachari Para Subproject (comprises supply of 4 power tillers and 6 100% power pumps) under BelaichariUpazila 77 DigalchariDebamatha Para Subproject (comprises installation of 3 100% tubewells, supply of 3 power tillers and 6 power pumps) under BilaichariUpazila 78 Bhalachari Para Subproject (comprises installation of 2ring wells, supply 100% of 4 power tillers and 6 power pumps) under BilaichariUpazila 79 Taktanala SW Subproject (comprises installation of 5tubewells and supply 100% of 3 power tillers and 4 power pumps , construction1 footbridge & 20 m stair ) under BilaichariUpazila

76

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 80 TaktanalaNE Subproject (comprises installation of tubewells, supply of 2 100% power tillers and 4 power pumps, construction of foot 1bridge and 20 m stair) under BilaichariUpazila 81 Jamunachari Subproject (comprises development of GFS water storage 100% system and supply of 2 power tillers and 4 power pump , 01 footbridge 90 m stair) under BilaichariUpazila 82 Naraichari Sub-project (comprises supply of 3 power tillers and 6 power 100% pumps and 3 Wing wells) under BilaichariUpazila 83 Bahaltali Sub-project (comprises installation of 4 tube wells, supply of 2 100% power tillers and 4 power pumps) under BilaichariUpazila 84 Downpara Sub-project (comprises supply of 6 power tillers and 8 power 100% pumps) under Bilaichari Upazila 85 Amthali para Sub-project (comprises installation of 3 tube wells, supply 100% of 3 power tillers and 5 power pumps) under Bilaichari Upazila 86 Uluchari para Sub-project (comprises installation of 5 tube wells, supply 100% of 3 power tillers and 3 power pumps) under Bilaichari Upazila 87 Chaindya para Sub-project (comprises installation of 4 tube wells, supply 100% of 3 power tillers and 3 power pumps) under Bilaichari Upazila 88 Digalchari para Sub-project (comprises supply of 6 power tillers and 6 100% power pumps) under Bilaichari Upazila 89 Aguzzyachari para Sub-project (comprises construction of 80m RCC 100% footsteps, supply of 2 power tillers and 5 power pumps) under Bilaichari Upazila 90 Hizachari para Sub-project (comprises installation of 6 tube wells, supply 100% of 8 power pumps) under Bilaichari Upazila 91 Tinkuniya para Sub-project (comprises installation of 2 tube wells, supply 100% of 4 power tillers and 6 power pumps) under Bilaichari Upazila 92 Sakrachari para Sub-project (comprises installation of 3 tube wells, supply 100% of 3 power tillers and 5 power pumps) under Bilaichari Upazila 93 Dupshil para Sub-project (comprises construction of GFS (gravity flow 100% system) under Bilaichari Upazila 94 Shalbagan para Sub-project (comprises construction of GFS (gravity flow 100% system) under Bilaichari Upazila 95 Aimacharamukh Subproject (comprises construction of stair 80m, supply 100% of 2 power tillers and 4 power pumps , 3 tube wells) under BarkalUpazila 96 Bagamukh Subproject (comprises construction of 40 m stair, supply of 2 100% power tillers and 6 power pumps, ) under BarkalUpazila

77

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 97 Latibashchara Subproject (comprises development GFS ( Gravity Flow 100% Supply of Water) of water storage system and construction of stair 55m) under BarkalUpazila 98 Taibang Sub-project (comprises installation of tube wells, supply of 2 100% power tillers and 4 power pumps, 4 Tube wells ( Infiltration Gallery System) under BarkalUpazila 99 Khubbang Sub-project (comprises installation of tube wells, supply of 3 100% power tillers and 6 power pumps, 3 Tube wells ,2 footbridge ( Infiltration Gallery System) under BarkalUpazila 100 Bogachari Sub-project (comprises supply of 3 power tillers and 4 power 100% pumps, 2 IFG ( Infiltration Gallery System) under BarkalUpazila 101 Dozori Sub-project (comprises installation of tube wells, supply of 2 100% power tillers and 4 power pumps, 3 Tube wells ( Infiltration Gallery System) under BarkalUpazila 102 Bagchari Sub-project (comprises supply of 4 power tillers and 5 power 100% pumps, 2 IFG ( Infiltration Gallery System) under BarkalUpazila 103 Tomobag Sub-project (comprises supply of 3 power tillers and 4 power 100% pumps) under 104 Chapkhaiyachara Sub-project (comprises installation of 4 tube wells, 100% supply of 2 power tillers and 4 power pumps) under Barkal Upazila 105 Shilchari para Sub-project (comprises installation of 4 tube wells, supply 100% of 3 power tillers and 4 power pumps) under BarkalUpazila 106 Koitor Hill para Sub-project (comprises installation of 3 tube wells, supply 100% of 3 power tillers and 6 power pumps) under Barkal Upazila 107 Sukorchari para Sub-project (comprises construction of GFS (gravity flow 100% system) under Barkal Upazila 108 Bilchara para Sub-project (comprises installation of 3 tube wells) under 100% Barkal Upazila 109 Boda para Sub-project (comprises installation of 3 tube wells, supply of 2 100% power tillers and 5 power pumps) under Barkal Upazila 110 Thegamukh para Sub-project (comprises installation of 1 ring well, 3 tube 80% wells, supply of 3 power tillers and 3 power pumps) under Barkal Upazila 111 Ramchara para Sub-project (comprises supply of 3 power tillers and 6 100% power pumps) under Barkal Upazila 112 Rodongkaba para Sub-project (comprises supply of 6 power tillers and 5 100% power pumps) under Barkal Upazila 113 Baraharina mukh para Sub-project (comprises supply of 2 power tillers 100% and 3 power pumps) under Barkal Upazila

78

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 114 Purba Kadamtuli para Sub-project (comprises construction of GFS 100% (gravity flow system) under Barkal Upazila 115 Ukchari para Sub-project (comprises construction of GFS (gravity flow 100% system) under Barkal Upazila 116 TalukderPara - Rangi Para Subproject under (comprises improvement of 100% 4.5 km earthen village access road to brick pavement including construction of construction 150m guidewalls, and 550m road side drains) NaniarchariUpazla 117 Dupchari Para Sub-project (comprises installation of 5 tube wells, supply 100% of 5 power tillers and 9 power pumps) under NaniarcharUpazila 118 Maischari Sub-project (comprises supply of 2 power tillers and 4 power 100% pumps) under NaniarcharUpazila 119 Vitor Para Sub-project (comprises supply of 2 power tillers and 5 power 100% pumps) under NaniarcharUpazila 120 Dewanparra Sub-project (comprises supply of 2 power tillers and 4 power 100% pumps) under NaniarcharUpazila 121 T&T Bazar Sub-project (comprises supply of 2 power tillers and 4 power 100% pumps) under NaniarcharUpazila 122 Morachengimukh Sub-project (comprises installation of 5 tube wells, 100% supply of 2 power tillers and 8 power pumps) under NaniarcharUpazila 123 Patachari Sub-project (comprises installation of 4 tube wells, supply of 3 100% power tillers and 6 power pumps) under NaniarcharUpazila 124 Barapul Sub-project (comprises installation of 4 tube wells, supply of 3 100% power tillers and 6 power pumps) under NaniarcharUpazila 125 Khullang Para Sub-project (comprises installation of 5 tube wells, supply 100% of 5 power tillers and 9 power pumps) underNaniarcharUpazila 126 Subolchari Para Sub-project (comprises installation of 4 tube wells, supply 100% of 3 power tillers and 5 power pumps) underNaniarchar Upazila 127 Jogonatuli Para Sub-project (comprises supply of 6 power tillers and 6 100% power pumps) underNaniarchar Upazila 128 Bakchari Para Sub-project (comprises installation of 7 shallow tube wells, 100% supply of 3 power tillers and 5 power pumps) underNaniarchar Upazila 129 Krisnamachara Para Sub-project (comprises installation of 3 tube well, 100% construction of 15m RCC foot bridge, supply of 3 power tillers and 5 power pumps ) under 130 Keretkaba Para Sub-project (comprises construction of 26m RCC foot 100% bridge, supply of 5 power tillers and 6 power pumps ) under Naniarchar Upazila

79

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 131 Koilash Para Sub-project (comprises installation of 3 tube well, supply of 100% 4 power tillers and 4 power pumps ) under Naniarchar Upazila 132 Tripurachara Para Sub-project (comprises construction of GFS gravity 100% flow system, supply of 1 power tillers and 2 power pumps ) under Naniarchar Upazila 133 Rijibil Para Sub-project (comprises installation of 3 tube well, supply of 3 100% power tillers and 5 power pumps ) under Naniarchar Upazila 134 Ramhari Para Sub-project (comprises installation of 4 tube well, supply of 100% 2 power tillers and 5 power pumps ) under Naniarchar Upazila 135 PanchariMukh Sub-project (comprises installation of 2 tube well, 100% construction of 250m irrigation drain, 18m foot bridge, supply of 2 power tillers and 2 power pumps) under JuraichariUpazila 136 Jamerchari Sub-project (comprises installation of 3 tube well, 2 ring well, 100% supply of 2 power tillers and 4 power pumps) under JuraichariUpazila 137 Mondirachara Sub-project (comprises installation of 2 tube well, 100% construction of 250m irrigation drain supply of 2 power tillers and 2 power pumps) under JuraichariUpazila 138 Samukchari Sub-project (comprises installation of tube wells, supply of 2 100% power tillers and 4 power pumps, 5 Tube wells , under JurachariUpazila 139 Bamechumachumi Sub-project (comprises installation of 5 tube wells, 100% supply of 2 power tillers and 4 power pumps, under JurachariUpazila 140 Boherachari Para Subproject (comprises installation of five tubewells for 100% drinking water, supply of two power tillers and four power pumps for improvement of agriculture) under JurachariUpazial 141 BalukhaliMukh Para Subproject (comprises installation of four tubewells 100% for drinking water, supply of three power tillers and six power pumps for improvement of agriculture) under JurachariUpazial 142 Devachara Sub-project (comprises installation of 4 tube wells, supply of 3 100% power tillers and 4 power pumps, under JurachariUpazila 143 Kusumchari Sub-project (comprises installation of 4 tube wells, supply of 100% 3 power tillers and 4 power pumps, under JurachariUpazila 145 Talukder para Sub-project (comprises installation of 4 tube wells, supply 100% of 2 power tillers and 6 power pumps, under JurachariUpazila 146 Suknachari para Sub-project (comprises installation of 3 tube wells, 100% supply of 3 power tillers and 6 power pumps, under Jurachari Upazila 147 Bamechumochumi para Sub-project (comprises installation of 5 tube 100% wells, supply of 2 power tillers and 4 power pumps, under Jurachari Upazila

80

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 148 Hazachari para Sub-project (comprises installation of 3 tube wells, 1 ring 100% well, supply of 3 power tillers and 4 power pumps, under Jurachari Upazila 149 Barabanny para Sub-project (comprises installation of 2 tube wells, 200m 100% irrigation drain, supply of 2 power tillers and 2 power pumps, under Jurachari Upazila 150 Shilchari para Sub-project (comprises construction of GFS gravity flow 100% system) under Jurachari Upazila 151 Bosti para Sub-project (comprises installation of 4 tube wells, supply of 2 100% power tillers and 4 power pumps, under Jurachari Upazila 152 Borkalok para Sub-project (comprises installation of 3 tube wells, supply 100% of 3 power tillers and 6 power pumps, under Jurachari Upazila 153 Modonmuni para Sub-project (comprises supply of 2 power tillers and 2 100% power pumps, under Jurachari Upazila 154 Gobachari para Sub-project (comprises supply of 3 power tillers and 4 100% power pumps, under Jurachari Upazila 155 Sapchari para Sub-project (comprises installation of 3 tube wells, supply 100% of 3 power tillers and 4 power pumps, under Jurachari Upazila 156 Balosh para Sub-project (comprises construction of GFS gravity flow 100% system, under Jurachari Upazila 157 Nabaperachara para Sub-project (comprises installation of 4 tube wells, 100% supply of 3 power tillers and 4 power pumps, under Baghaichari Upazila 158 Sijok collage para Sub-project (comprises installation of 4 tube wells, 100% supply of 3 power tillers and 4 power pumps, under Baghaichari Upazila 159 Lalon para Sub-project (comprises construction of 1km HBB road, supply 100% of 4 power tillers and 4 power pumps, under Baghaichari Upazila 160 Jogorabil para Sub-project (comprises supply of 3 power tillers and 2 100% power pumps, under Baghaichari Upazila 161 Baramallya para Sub-project (comprises installation of 5 tube well, supply 100% of 2 power tillers and 4 power pumps, under Baghaichari Upazila 162 Shonkoladam para Sub-project (comprises installation of 4 tube wells, 100% supply of 3 power tillers and 4 power pumps, under Baghaichari Upazila 163 Kattali para Sub-project (comprises supply of 6 power tillers and 4 power 100% pumps, under Baghaichari Upazila 164 Suvoronjon karbari para Sub-project (comprises installation of 4 tube 100% wells, supply of 3 power tillers and 2 power pumps, under Baghaichari Upazila

81

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 165 Nalkatachara para Sub-project (comprises installation of 4 tube wells, 100% supply of 3 power tillers and 4 power pumps, under Baghaichari Upazila 166 Jotokhamar para Sub-project (comprises installation of 4 tube wells, 100% supply of 3 power tillers and 4 power pumps, under Baghaichari Upazila 167 Hazachari para Sub-project (comprises supply of 2 power tillers and 4 100% power pumps, under Baghaichari Upazila 168 Rangadurchari para Sub-project (comprises installation of 5 tube wells, 100% supply of 3 power tillers and 1 power pumps, under Baghaichari Upazila 169 Dakkin baradurchari para Sub-project (comprises installation of 5 tube 100% wells, 150m irrigation drain, supply of 1 power tillers and 1 power pumps, under Baghaichari Upazila 170 Ugalchari para Sub-project (comprises installation of 5 tube wells, supply 100% of 3 power tillers and 4 power pumps, under Baghaichari Upazila 171 Dulubonny para Sub-project (comprises supply of 6 power tillers and 5 100% power pumps, under Baghaichari Upazila 172 Kozoichari para Sub-project (comprises installation of 5 tube wells, supply 100% of 2 power tillers and 4 power pumps, under Baghaichari Upazila 173 New Lalyaghona para Sub-project (comprises installation of 5 tube wells, 100% supply of 3 power tillers and 2 power pumps, under Baghaichari Upazila 174 Kodamtuli godamatha para Sub-project (comprises installation of 4 tube 100% wells, supply of 3 power tillers and 4 power pumps, under Baghaichari Upazila 175 Samoitre para Sub-project (comprises installation of 3 tube wells, supply 100% of 3 power tillers and 4 power pumps, under Baghaichari Upazila 176 Voiyachara para Sub-project (comprises supply of 3 power tillers and 4 100% power pumps, under Baghaichari Upazila 177 Ranjan para Sub-project (comprises installation of 4 tube wells, supply of 100% 3 power tillers and 2 power pumps, under Baghaichari Upazila 178 Ugalchari Mukh para Sub-project (comprises installation of 5 tube wells, 100% supply of 2 power tillers and 1 power pumps, under Baghaichari Upazila 179 Ajjengchari para Sub-project (comprises installation of 4 tube wells, 100% supply of 3 power tillers and 4 power pumps, under Baghaichari Upazila 180 Jumbi Adam para Sub-project (comprises Water reservoir and distribution, 50% under Baghaichari Upazila 181 Durchari Markeshed subproject 50% 182 Manikya para Sub-project (comprises installation of 4 tube wells, supply 100% of 2 power tillers and 4 power pumps, under Longado Upazila

82

Environmental Monitoring Report July – December 2018

Status of S/N Name of sub-projects works 183 Jatramuro para Sub-project (comprises installation of 4 tube wells, supply 100% of 2 power tillers and 4 power pumps, under Longado Upazila 184 Hemochandra para Sub-project (comprises installation of 3 tube wells, 100% supply of 3 power tillers and 4 power pumps, under Longado Upazila 185 Uttor Manoshya para Sub-project (comprises supply of 2 power tillers and 100% 4 power pumps, under Longado Upazila 186 Ranga panichara para Sub-project (comprises installation of 8 tube wells, 100% under Longado Upazila 187 Boradam para Sub-project (comprises installation of 2 tube wells and 100% water tank under Longado Upazila 188 Jornatila para Sub-project (comprises installation of 8 tube wells, under 100% Longado Upazila 189 Purba Teka para Sub-project (comprises supply of 2 power tillers and 4 50% power pumps, Installation of tubewells under Longado Upazila 190 Ghonomor para Sub-project (comprises installation of 5 tube well, supply 100% of 2 power tillers and 3 power pumps, under Longado Upazila 191 Islamabad para Sub-project (comprises supply of 2 power tillers and 4 50% power pumps, Installation of tubewells under Longado Upazila 192 Purba Chailatuli para Sub-project (comprises installation of 4tube well, 100% supply of 2 power tillers and 4 power pumps, under Longado Upazila 193 Dozorpara Sub-project (comprises construction of 3km HBB road under 80% Longado Upazila 194 Korengatuli Markeshed subproject under Baghaichari Upaziila 100% 195 Chaiory bazar Markeshed subproject under Kaukhali upazilla 100%

Bandarban District:

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status

Bandarban Sadar Upazila, Union: Kuhalong 1 627 m VAR with 149m guide wall, 5m Road Bagmara Para side drain,01 Culvert,02 DTWs & 01 PT 100% completed 2 Khebuk Para 03 Deep Tube wells,02 PTs 100% completed

83

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status 3 Minjiri para 03 DeepTube wells,07m Spill weir for irrigation,41m Stair & 02 PTs 100% completed Gungru mukh 4 Para 02 Deep Tube wells, 110m Stair 100% completed Chemidulu VFP-500m, 6 DTWs for drinking water, Stair- 5 Para(Pilot 3(72m), Irrigation canal-800m, 01 DTW for Project) irrigation 100% completed 6 Ubasoi Para 54m Stair,02 DTWs & 03 PTs 100% completed Chasoimong 7 Para 62m Stairs,03 DTWs,02 PTs 100% completed Natun Choroi 8 para 57m RCC Stair,02 DTWs,02 PTs & 01 WPM 100% completed

9 Khaiya Para VAR-544m, VFP-463m, L-Drain-241m, Pipe culvert-1(3.5m), RCC Stair-114m, DTWs-3 100% completed Comprises of RCC Stair & Long Steps-72m, 10 Bakichara Para DTWs-2, PTs-2, WPMs-2. 100% completed 11 Dolbaniya Para RCC Stair-83m, DTWs-3, PT-1 100% completed Bhanga Mura 12 RCC Stair-78m, DTWs-2, PT-1, PMs-2 Para 100% completed Thowai Aungya 13 RCC Stair-34m, DTWs-5, PTs-2 Para 100% completed Gunguru 14 Madhyam Para RCC Stair-83m, DTWs-2, PT-1, PM-1 100% completed Bandaraban Sadar Upazila, Union:Bandaraban Sadar

Hlapai Ujani 664 VAR, 3m culvert, Road side protection wall 15 100% completed para 11.15m, 15m long steps & 30m Long Stair,02 DTWs,01 PT Lulain 16 Punarbashan 65m Stair,01 Ring Well para 100% completed 17 Datvanga para 112m Stair,7m brick wall & 15m bitumins drum sheet 100% completed 18 Kattoli Para 132m Stair 100% completed

84

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Lemujhiri Aga 19 Para Comprises of RCC Stair-92m, Brick protection wall(in RCC Stair)-10m, DTWs-3,PT-1. 100% completed

20 Talukder Para Comprises of RCC Stair-98m, Long Stair-63m, DTW with submersible Pump-1,WRT-1. 100% completed Bandaraban Sadar Upazila, Union:Sowalok 21 Majher Para Comprises of DTWs-4, PTs-3, WPM-1.

22 Basanta Para 1.5km VAR with 60m Road side Drain,01 Pipe culvert -1m & 11m slope protection wall 100% completed Faruk Nicher 23 Para WRT-1 & 109m Stair 100% completed Amtoli Marma 24 650m VAR,75m Stair,14m brick wall,02 Para DTWs,01 PT & 01 PM 100% completed Comprises of HBB village access Road & RCC village access Road-(694+60)=754m,L-Drain- 25 Getshimani Para 100% completed 474m, U-Drain-57m, Protection wall-30m, Pipe culvert-01(3.5m), GFS water supply system. Bandaraban Sadar Upazila, Union:Tankabati Punarbashan 26 1.39km VAR with 262m Road side Drain & Tripura Para Protection wall 100% completed Purnachandra 27 Para 01 Deep Ring Well,1 WRT & 123m Stair 100% completed Chimbuk Pabla 28 510m VAR with 100m L-Drain,75m RCC Headman para Stair,15m Dam, 10.5m Pipe culvert 100% completed 819 VAR with 100m road side drain,78m 29 Baittya Pata Stair,12m U-Drain,20m Pipe culvert & 02 RCC Tanks 100% completed

30 Ranju para 576m VFP,75m L-Drain ,88m RCC Stair, 2 DTWs 100% completed Bandaraban Sadar Upazila, Union:Rajbila Jamchari Vitor RCC Stair 90m,Drain-12m,WRT-1,DTW-1 with 31 Para submersible pump water supply system 100% completed Jamchari Mukh 93m Stair(70m RCC+ 23m long steps), DTWs- 32 Para 2, U-Drain-70m 100% completed

85

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Jogesh Karbari 33 1.15km VAR with 3 Pipe culverts,5m road side para drain,02 DTWs,02 PTs, 15m Stair 100% completed 1005m VAR with 160m Road side Drain,154m 34 Zanka Para Stair,02 RWs,WRT-1, 01 DTW with 100% completed submersible motor pump & water supply system 583m VAR with 60m L-Drain,3.5m Pipe Bagmara 35 culvert,5m U-Drain,24m P.wall,60m RCC 100% completed Madyam Para Stair,64m Long Steps,2.5m Canal,03 DTWs,02 PTs RCC Stair-67m, Long steps-123m,DTWs-2, PT- 36 Wabrei Para 1. 100% completed 1No.150mm dia Submersible Deep tube well upto depth 168m to be lifted water by Submersible pump, supplying of Plastic water 37 Ramatiya Para tank with capacity 2000 Litre with Brick work 100% completed stand, Construction of 3Nos Tap stand, HDP pipe fitting, electric cable fitting, PTs-2(12HP power), PMs-2(4-5 HP) 38 Galachipa Para RW-1,RCC Stair 100% completed 39 Khamadong Para Stair-72m, DTWs-2, 100% completed Tainkhali Upor 40 RCC Stair-120m, DTWs-2,STWs-2 Para 100% completed Rowangchari Upazila, Union:Taracha Taracha 41 100% completed Headman Para 2100m VAR with 10m road side drain & 1.2km guide wall 42 Tongprue Para 03 Deep Tube wells for drinking water 100% completed 703m VAR,45m Stair,03 DTWs, 02 PTs & 01 43 Talukder Para PM 100% completed 44 Faikhyong Para 68m Stair,03 DTWs 100% completed VFP-684m, Road side surface run off drainage- 45 Dornido Para 150m,2 Slab culverts(5m), GFS water supply 100% completed with 3 nos 1000 ltr WRTs

86

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Nowapatong 46 Mukh RCC Stair & Long steps-108m, DTWs-3, PT-1. 100% completed (Nicher)Para Rowangchari Upazila, Union:Alekhyang

47 Wagoi Para 718m VAR with 102m road side drain, 18m long stair,01 DTW, 3.5m culvert 100% completed 48 Wabraing Para 100% completed 120m Stair,45m long Steps & 01 Ring Well

49 Kacchaptali Para 59m RCC Stair,82m long steps,wooden post 100% completed palisading-18.5m, 02 PTs & 01 WPM Laxmi Chandra 50 100% completed Para Supply of 01 PT, Earthen Dam-2(36m)

51 Chahla Para 100% completed RCC Stair-55m, Long steps-50m,PTs-2, PMs-2 VFP-767m with Pipe culvert-1, Brick protection wall-36m, U-Drain(Drainage system)-13m, 52 Battali Para 100% completed DTW with submersible Pump-1, DTWs-2, WRT(RCC)-1,PTs-3,PM-1. Rowangchari Upazila, Union:Nowapatong Sonai Seprue 53 2.19km VAR with 150m guide wall,550m Road 100% completed Para side drain & 8.6m long bridge, DTWs-4 Gungkhyong 54 100% completed para 812m VAR,01 Deep Tube well,01 PT Khayamrong 55 100% completed para 134m Stair,01 deep ring well

56 Nasalong Para 801m VAR with 10.5m pipe culvert,104m 100% completed Stair,35m long steps,01 PT Antaha Tripura 57 679m VAR with 100m road side drain(U),14m 100% completed Para pipe culvert,85m Stair,02 DTWs,01 PT

58 Kanaizu Para 100% completed 47.5m Stair,03 DTWs,02 PTs Bagmara Purba RCC Stair & Long steps (108+62)-170m, DTW- 59 100% completed Para 1

87

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Rowangchari Upazila, Union:Rowangchari Sadar Comprises of Stair/sreps-71m, DTWs-3, PTs-2, 60 Bengchari Para PMs-2. 100% completed Rowangchari 61 450m VAR with 90m Protection wall,03 Pipe 100% completed Sadar Para culvert 746m VAR with 5m road side drain,3.5m pipe 62 Paglachara Para culvert,330m irrigation canal,73m cc long 100% completed steps,02 DTWs,01 PT Kaintermukh 63 Para 66m Stair,02 PT, 02 DTWs 100% completed 64 Paikhyong Para 100% completed GFS water supply with 1 Reservoir Tank 1301m VAR with 180 L-Drain,6m brick 65 Aungya Para wall,12m U-Drain,42m Pipe culvert,8.5m RCC 100% completed Box culvert, 20m stair,02 DTWs,02 PTs,01 PM, 66 Baroshila Para 100% completed RCC & CC Stair-171m, Ghera U Vitor 67 100% completed Para RCC Stair & CC Steps-140m, , Union: Ruma Sadar Comprises of RCC Stair-120m with U-Drain- 68 Mayor Para 100% completed 10m.

69 Thana Para 51m RCC Stair,38m long steps,03 DTWs 100% completed 70 Bethel Para 85m RCC Stair,90m long steps 100% completed 71 619m VAR with 133m Drain,60m palisading Hati Matha Para work,45m RCC Stair,RW-1, RT-1 100% completed 72 Happy Hill Para 521m VAR, Steps & Stair-180m, RW-1 100% completed 73 Lunjhiri Para RCC Stair & steps-105m, Protection wall-24m, 100% completed 74 Polika Para RCC Stair-127m, RW-1, RT-1 100% completed GFS water supply system(660m pipe line 75 Lairumpi Para including source/intake structure, reservoir tank 100% completed construction , setting & installation of 1No 1500 Lit capacity Plastic tank and tape stand)

88

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Mong Lai Graw 76 Comprises construction of GFS(1 Nos) Water 100% completed Para supply system with RT-1

77 Rumachar Para RCC Stair-60m, Long steps- 100% completed 35m(Total=95m),RW-1, PTs-02.-, RT-1 Ruma Upazila, Union: Paindu 612m VFP with 12m Drain,20m protection 78 Chairagraw Para wall,03 Pipe culverts,10m brick protection 100% completed wall,107m RCC Stair,30m Long steps, 01 WRT, Mong Swe Prue 79 120m Stair for river ghat 100% completed Para

80 Bagan Para Comprises of RCC Stair -228 100% completed Ruma Upazila, Union: Galengya

81 Raifu Para RCC Stair-68m, GFS water supply system with WRT 100% completed

82 85m RCC Stair/Steps,GFS-1 with RT,20m Mongoha Para Earthen Dam/Cross Dam 100% completed Lama Upazila, Union: Lama Sadar Boilyachar Comprises of RCC Stair, Long Steps & RCC 83 Chionimukh Ghat Stair-67m, Pond Excavation-1, DTWs-2, 100% completed marma Para PTs-2. 237m VAR /VFP, RCC Stair-187m,01 PT,01 84 Merakola Para 100% completed DTW

Lama Upazila, Union: Fashiakhali Comprises of VAR-742m with U-Drain- 85 Borh Para 142m,Protection wall-53m, RCC Stair-87m with Protection wall-10m,DTWs-2,PT-1. 100% completed Eyangsha 86 Headman Para 03 DTWs,02 PTs & 02 PMs 100% completed 87 Choto Para RCC Stair-57m, DTWs-3, PTs-2. 100% completed 88 Kathal Para RCC Stair-80m, RW-1,PT-1, PM1. 100% completed Lama Upazila, Union: Saroi

89

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status 89 Gajan Para 90m Stair,01 DTW,01 PT & 01 WPM 100% completed

90 Tangoziri Para 50m RCC Stair & 60m Long Steps,02 RWs,02 PTs 100% completed 382 meter VAR with 109m Protection wall cum Kafru Para(Pilot 91 drainage,Box culvert-3nos,102m short Stair,71m 100% completed Project) long stair Lama Upazila, Union: Gajalia 92 Rangsango Para Comprises of RCC Stair & Long Steps(51+36)- 87m, U-Drain-12m, DTWs-2, PT-1, WPMs-2. 100% completed 93 Badhujhiri Para Comprises of RCC Stair-38m, DTWs-2, PTs-2, PMs-2. 100% completed 94 Najiram Para Comprises of RCC Stair & long steps(86+54)140m, DTW-1,PT-1. 100% completed

95 Manikjan Para 892m VAR/FP,U-Drain-150m, 03 Pipe culverts,RCC Stair-85,,02 DTWs, 02 PTs,01 PM 100% completed Gozalia 96 Headman para 88m Stair,02 DTWs 100% completed

97 Gaindya Para 03 DTWs,04 PTs,02 WPMs 100% completed 98 Akiram Para 496m VFP,03 Pipe culverts,15m Protection wall,97m RCC Stair,02 DTWs,01 PT 100% completed 641m VAR & VFP with 2 Pipe culverts,Slab culvert-1(5m),Wooden post palisading - 16m, 99 Remong Para Road side drain-12m, L-Drain-30m, protection 100% completed wall-20m,73m RCC Stair,02 DTWs,02 PTs,02 WPMs 100 Gotiram Para 100% completed RCC Stair & long steps-120m, 3 DTWs, 1 PT 101 Minjiri para 100% completed RCC Stair-71m, Long steps-30m,DTWs-2,PT-1 VAR-877, U-Drain-225m, L-Drain-334,Pipe culverts-2(3.5m),Protectio wall-33m,Slab 102 Durjyodhan Para 100% completed culvert-1(6.9m),RCC Stair-41m, ,DTWs-2,PTs- 2,PM-1

103 Denkichara Para VAR-618m, Slab culvert-1, P.Culverts-3, 100% completed DTWs-2, PTs-3,PMs-2

90

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status 104 Baishpari Para 100% completed RCC Stair-33m, DTWs-3, PTs-2, PMs-2 105 Ujiram Para Stair-82m, DTWs-2, PT-1, PMs-2 100% completed

Lama Upazila, Union: Faiton 38m Stair & Steps with 38m drainage system,03 106 Vanja Para DTWs,02 PTs & 01 WPM 100% completed Faiton Headman 107 50m RCC Stair/Steps,03 DTWs,01 PT,01 PM Para 100% completed Sonaichari Naya 108 Marma Para RCC Stair & long steps-63m, RW-1, 2 PTs,PT-1 100% completed Mong Fo 109 Thowain Para RCC Stair/Steps-80m, 2 DTWs,2 PTs & 1 PM 100% completed 110 Kamajyajiri Para RCC Stair-73.5m, DTWs-2,PTs-2 100% completed Lama Upazila, Union: Aziznagar Telonia Marma 111 Comprises of Pond Re-exacavation-1, RCC ghat Para Stair-8m, DTWs-2, PTs-2, PMs-2. 100% completed 38m Stair,01 DTW with water supply system ,02 112 Chioni Para PTs,01 WPM 100% completed

113 Sonaram Para RCC Stair-59m, U-Drain-5m, RCC Ghat stair- 100% completed 8m, DTWs-2, PTs-2. Chambi 114 Comprises of RCC Stair/Steps-55m with 100% completed Headman Para protection wall-9m, DTWs-2, PT-1,PM-1. Lama Upazila, Union: Ruapshi

115 Dordori Para 130m Stair & Steps,01 DTW,01 PT 100% completed 48m RCC Stair/Steps, 03 DTWs,02 PTs & 01 116 Aung Hla Para PM 100% completed 117 Chingkom Para RCC Stair-94m, DTWs-2, PT-1. 100% completed Shilartowa Naya Comprises of RCC Stair-51m, DTWs-2, PTs-2, 118 Para PM-1. 100% completed RCC Stair & Long steps-109m,DTWs-2,PT- 119 Boidyavita Para 100% completed 1,PM-1.

Alikadam Upazila, Union: Alikadam Sadar

91

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Amtoli Ashothu 120 133m RCC Stair,41m long steps,02 Ring Wells 100% completed Tripura Para 957m VAR with culvert & Drain,127m Stair & 121 Jabiram Para Steps,Palisading works-46m, 02 RWs,01 PT, PM-1 100% completed 593m VAR with 2 slab culvert-6m & drain-66m, 122 Langri Para 111m stair,02 RWs,01 PT 100% completed Amtoli RCC Stair & Landing Ghat Stair-60m,04 123 100% completed Tanchangya Para RWs,01 PT 1800m VAR & VFP with slab culvert,Pipe Varot Mohan culvert,Protection wall,U-Drain, L-Drain ,RT- 124 100% completed Para 1,Pond renovation ,2 PTs, 01 RW with water supply system Mong Swe Prue 125 RCC Stair-48m,DTWs-2,PTs-2, PMs-2 100% completed Para Alikadam Upazila, Union: Choikhyang Thowaiching 126 115m Stair,01 DTW,01 PT 100% completed Headman para

127 Padoi Para 45m Stair,02 DTWs,02 PTs, PMs-2 100% completed

128 Kairing Para 57m RCC Stair/Steps,02 DTWs,1 PT,10m Dam 100% completed

129 Shibatali Para Comprises of RCC Stair-102m, Long steps- 57m,DTWs-2,PT-1. 100% completed Baghherjhiri 130 Para Dam-55m, 1 Deep RW, PTs-2, PM-1 100% completed RCC Stair & Steps-112m (RCC Stair-43m, Long 131 Nyo Aung Para Steps-60m, RCC Stair for Pond landing ghat- 9m) ,DTW-1, PT-1,PM-1. 100% completed Alikadam Upazila, Union: Nowapara Chahlaching Comprises of RCC Stair & Long steps-133m, 132 100% Completed Para PT-1. Rohini Mohan 133 120m Stair,02 RWs,01 PT Para 100% completed

92

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status

134 Chai Aung Para 141m RCC Stair/Steps,02 RWs,01 PT 100% completed 1613m VAR with 02 Nos(5m) Pipe culvert,20m 135 Jugendra Para Protection wall,02 Slab culvert,100m L-Drain, 65m RCC Stair/Steps,03 RWs,02 PTs,02 PMs 100% completed RCC Stair & CC Stair-93m, RWs-2, PTs-2, 136 Regra Para PMs-2 100% completed 137 Basudeb Para Ring Wells-3, PTs-3, PMs-2 100% completed Naikhyangchari Upazila, Union: Baishari 998m HBB Footpath with Pipe culverts-3(3.5m), Headman Chak 138 slab culverts-3(5m), Preotection wall, 4 RWs, 2 100% completed Para PTs, Stair/steps-41m, 978m VAR & VFP,U-Drain-140m, 112m 139 Upar Chak Para 100% completed Stair,01 RW,01 PT Madhyam Chak 140 RCC Steps-50m, DTWs-2,PTs-2, 100% completed Para

Naikhyangchari Upazila, Union: Gundhum

Comprises of VAR-748m with L-Drain-260m, 141 Fatrajhiri Para Pipe Culvert-3.5m(3 Nos), Protection wall- 100% completed 80.5m,Slab Culvert-6.9m(1 Nos), RCC Stair- 16m, RWs-4, PTs-3,PM-1. Comprises of VAR-788m, Drain- 142 Garjanbunia Para 373m,Protection wall-02 nos(80.5m), Pipe 100% completed culvert-04 Nos(3.5m), RCC Stair & Long steps- 64m,RWs-4, Baishpari Comprises of RCC Stair(28+8)-36m,RWs- 143 100% completed Tanchangya Para 4,PTs-2,PM-1.

144 Baroitali Para RCC Stair-27m, RWs-4,PTs-2, PM_1 100% completed Tombrue 145 RCC Stair & Long Steps-70m, DTWs-2,PTs- Headman para 2,Pump Machine-1. 100% completed

93

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status

146 Valukya Para Pond re-excavation-1, RCC Stair-16m, DTWS- 3, PTs-2 100% completed Niakhyangchari

Upazila, Union: Sonaichari Jaruliachari 147 Comprises of RCC Steps & Long steps-105m, 100% completed Marma Para PT-1, RW-1, Pond-1. VFP-756m,U-Drain-65m, Protection wall- Sonaichari 148 36m,RCC Ghat Stair-16m,RWs-3, PTs-2, 100% completed Headman Para WPMs-2 Comprises of HBB Access-687m, Road side protection wall cum surface run off drainage 149 Boidyo Para system-70m, Road side bricks protection wall- 100% completed 20m, RCC Short steps-55m, PTs-2,PM-1, RWs- 3.

150 Natun para RCC Stair/steps-100m, 100% completed

Comprises of HBB Access & Footpath-887m, Road side Protection Wall(Drainage system)- 151 Maragya Para 70m,Road side brick protection wall-8m,Pipe 100% completed culvert, RCC Short Steps-24m,PTs-3, PMs- 2,RWs-3. Naikhyangchari Upazila, Union:

Dochari Krokhyang(Hari 152 Comprises of RCC Stair-54m, DTW-1, PTs-2 100% completed ngkhyong) Para , Union: Boli Para

153 Bagan Para 59m Stair & 15m L-Drain,02 DTWs,02 PTs 100% completed

154 Bali Para 20m Earthen Dam,02 WRTs, 04 DTWs & GFS 100% completed with RTs-2 Hoitan Khumi 155 RCC Stair-90m, Earthen Dam-16m 100% completed Para Comprises of HBB Footpath-441m with Road 156 Ail Mara Para side drain-20m, Pipe Culvert-02 nos(3.5m), RCC 100% completed Stair-66m, 157 Bidyamoni Para RCC Stair-130m, 100% completed

94

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status RCC Stair & Long steps-40m, Slab culvert-1, 158 Sakoi Para 100% completed RCC RT-1 159 Manwai Para RCC Stair-75m, GFS with RT-1 100% completed

Upazila: Thanchi, Union: Thanchi Sadar Bonyok RCC Stair-105m, 160 100% completed Headman Para RCC Stair-110m, 161 Waksaku Para 100% completed Thanchi 162 RCC Stair-90m, Deep Ring Wells-4 100% completed Headman Para

163 Anil Chakma Stair-102 with Drain-150m,RW-1,PT-1 100% completed Para VFP-679 meter, U-Drain-100m,RCC Stair- 164 Antaha Tripura 100% completed Para 85,DTWs-2,PT-1, 165 RCC Stair-42m, Earthen Dam-16m, RW-1 100% completed Subrai Para Water Shed Management

Upazila: Bandarban Sadar, Union: Kuhalong

Comprises of Check Dam, Agro-forestry, Bio- 166 Peemrongchara, 100% completed WM site engineering and vegetable gully plugging Upazila: Bandarban Sadar, Union: Sowalok

Comprises of Check Dam, vegetable gully 167 Mazrachara , 100% completed WM site plugging and Water source protection

Upazila: Rowangchari, Union: Alekhyang

168 Grokhyang Para DTWs-2, RCC Stair-85m,01 PT & 01 PM 100% completed

Upazila: Rowangchari, Union: Nayapatong Antaha DTW-1,RCC Stair-69 m, HBB Road-627m, RT- 169 Tanchangya Para 1 100% completed Upazila: Naikhyangchari, Union: Naikhyangchari Sadar

95

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Chak Headman DTW-1,RCC Stair-32 m, HBB Road-448m, RT- 170 Para 1 100% completed Madhyam Chak DTW-1 with supply, RCC Stair-118m 171 Para Partially completed Dhungri RCC Stair-36m, DTW-1 with water supply 172 headman Para 100% completed Upazila: Naikhyangchari, Union: Baishari Natun Chak RWs-2,Pond-1, Stair(Revised) 173 Para 100% completed Dhabangkhali 174 Para DTWs-2, RCC Stair-88m, PTs-2 & 01 PM 100% completed Upazila: Naikhyangchari, Union: Ghundhum Jamirtali Para DTW-1,RWs-3, RCC Stair-81m 175 100% completed Raiju Marma RW-1,RCC Stair-9m, Pond-1 176 Para 100% completed

177 Mongjoy Para RWs-3, RCC Stair-9m, Pond-1 100% completed Upazila: Lama, Union: Gajalia 178 Re-Aungshe Para RCC Stair-60m, DTWs-2 100% completed Upazila: Lama, Union: Aziznagar 179 Kantholi Para RCC Stair-30m, DTW with water supply 100% completed Upazila: Bandarban Sadar, Union:

Bandarban Sadar 180 Tongprue Para RCC Stair-55m, DTWs-2, RW-1, 100% completed Upazila: Bandarban Sadar, Union: Kuhalong Kuhalong Stair-55 meter, 1DTW with water supply, Pts-2 181 Headman Para 100% completed Upazila: Lama, Union: Rupashi Mong Swe Prue Stair-85m, DTW-1, PT-1, PM-1 182 Para 100% completed RCC Stair 68 meter, CC Stair-90 meter, DTWs- Baluchar Para 183 2 100% completed Upazila: Lama, Union: Saroi Union 184 Kyazu Para RCC Stair-57meter & Culvert, DTWs-2 100% completed Upazila: Alikadam, Union: Alikadam Sadar RCC Stair-12m, CC long steps-47m, Pond Aongbai Para 185 excavation-1, RWs-2. 100% completed

96

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status 186 Cheoni Para Stair-70 meter & RWs-2 Works Ongoing Upazila: Alikadam, Union: Nayapara Union 187 Mongcha Para Stair-109 meter, DTWs-3 100% completed Upazila: Ruma, Union: Paindu Chanda headman GFS water supply system with 04 nos Plastic 188 para Reservoir tank. 100% completed Upazila: Thanchi, Union: Thanchi Sadar 189 Noktoha Para Stair-96 meter Works Ongoing Upazila: Thanchi, Union: Balipara 190 Dingte Para Stair-102 meter 100% completed 191 Monai Para 1 Deep Ring Well, 04 Plastic Reservoir Tanks Works Ongoing 192 Naikhyong Para RCC Stair/Steps-102m, U-Drain-35m Works Ongoing Upazila: Naikhyangchari , Union: Baishari 193 Mui Aong Para RCC Stair-76m, CC Stair-33m,DTWs-2 100% completed Thui Hla Aung RCC Stair & CC Stair-102m, DTWs-2, PTs-2. 194 Para, 100% completed Upazila: Rowangchari , Union: Rowangchari

Sadar RCC Stair-90 meter, with rataining wall, RCC Mongbai Para 195 WRT-1. 100% completed Upazila: Sadar Upazila , Union: Rajbila Tainkhali Market Tinshed Market Shed including sanitary Toilet & 196 Shed DTW-1 Works Ongoing Upazila: Sadar Upazila , Union: Tankabati Tankabati Tinshed Market Shed including sanitary Toilet & 197 Market Shed DTW-1 Works Ongoing Upazila: Ruma , Union: Ruma Sadar Battali Para Tinshed Market Shed including sanitary Toilet & 198 Market Shed DTW-1 Works Ongoing Upazila: Sadar Upazila , Union: Bandarban

Sadar Union 199 Laimi Para GFS + RT, Footbridge-13meter, Stair-66 meter. Works Ongoing RCC Stair-39.5m, Long steps-18m, Brick Lulain Headman protection wall-5.5m, U-Drain-25m, RW-1, Para Renovation work of existing Dug Well, PTs-2, 200 PM-1. Works Ongoing

97

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Upazila: Sadar Upazila , Union: Kuhalong

Union 201 Jardan Para RCC Stair-105m, RW-1. Works Ongoing Upazila: Alikadam Upazila , Union:

Alikadam Sadar Union Augustin Tripura RCC Stair cum landing Ghat -10m, 4 Ring 202 Para Wells, 3 PTs, 3 PMs. Upazila: Alikadam Upazila , Union:

Nowapara Union RCC Stair & CC Stair-107m, U-Drain-47m, Wai Hla Para 203 DTWs-3. Upazila: Ruma Upazila , Union: Ruma Sadar

Union 204 Ashrom Para GFS water supply system with RT Works Ongoing 205 Battali Para GFS water supply system with RT Works Ongoing Upazila: Ruma Upazila , Union: Paindu

Union Chanda GFS water supply system + RT 206 Purnabasan Para Under procurement Upazila: Naikhyangchari Upazila , Union:

Naikhyangchari Sadar Union Sathojai Chak RCC Stair-25m, DTWs-2, PTs-2, PMs-2. 207 Para Works Ongoing Mracha Aung RCC Stair & Steps-25.5m, DTWs-2, PTs-2, PM- 208 Chak Para 1. Works Ongoing Upazila: Naikhyangchari Upazila , Union:

Sonaichari Union 209 Kyok Prok Para GFS water supply system with RT Works Ongoing 210 Khudi Para DTWs-6, PTs-2, PMs-2 100% completed Upazila: Sadar Upazila , Union: Kuhalong

Union Khoiya Para Tinshed Market Shed including sanitary Toilet & 211 Market Shed, DTW-1 Works Ongoing Upazila: Ruma Upazila , Union: Ruma Sadar

Union Bethel Para Tinshed Market Shed including sanitary Toilet & 212 Market shed DTW-1 Works Ongoing Upazila: Ruma Upazila , Union: Galenga

Union Korang Bazar Tinshed Market Shed including sanitary Toilet & 213 Market Shed DTW-1 Works Ongoing

98

Environmental Monitoring Report July – December 2018

Name of Sub- Intervention Present Pregress Sl no. Project/PDC Status Upazila: Rowangchari Upazila , Union:

Alekhyang Union Tinshed Market Shed including sanitary Toilet & Battali Para MS 214 DTW-1 Works Ongoing Upazila: Lama, Union: Gajalia 215 Ting Hla Para RCC Stair & long steps,02 DTWs 100% completed

99

Environmental Monitoring Report July – December 2018

Appendix 3: Physical Progress of MAD Component

Micro Agribusiness Development (MAD) Component Sl Activities with Unit Project Progress of project by year and Project milestone Target qtr. Progress as per Progress Progress Up Total (%) RDPP Up to to this 30 September November 2018 2018 A.1 CIG (Production/Group Formation and Related Activities 1 (i) Sub-sector-wise No 900 900 3 903 100.33 Group Formation (a) Fruit Orchard – 183 (b) Vegetables – 360 (c) Medicinal Plant and Fruits – 180 (d) Pond and Creek/Mini Fisheries – 180 A.2 CIG (Marketing) Related 2 (i) Forming Marketing No 60 0 90 90 150 CIGs following cluster approach for vegetables, fruits, medicinal plants & fruits, and fish B. Vegetables Vegetable exporter 1 No 45 16 0 16 35.56 contract visit Lead farmers visit 2 No 60 21 0 21 35 within CHT Training on Seed & 3 No 270 270 0 270 100 Pheromone Traps Pheromone 4 No 3000 720 0 720 24 Demonstration-Brinjal Pheromone 5 Demonstration- No 2400 450 0 450 18.75 Cucurbits Sub-Total 5775 1477 0 1477 25.58 C. Medicinal Plants

100

Environmental Monitoring Report July – December 2018

Farmers exchange visit 30 6 24 30 100 1) within CHT No Lead farmers visit to 2 2 0 2 100 2) Natore /Gaibanda No 3) Buyer group meeting No 18 0 7 7 38.88 3 days training for 135 69 0 69 52 4) grower No Training for Nursery 27 27 0 27 100 5) Owners No Replication of 3 0 0 0 0 6) processing techniques No Sub-Total 215 104 31 135 31,62 D. Orchard Fruits Farmers exchange visit 90 90 0 90 100 1) within CHT No 3 Days Farmers 180 86 0 86 47.78 2) Training No Training for Nursery 9 9 0 9 100 3) Owners No Pheromone Traps 900 720 0 720 80 4) Demonstration No Replecation of Fruit 9 0 0 0 0 5) Processing Techniques No Sub-Total 1188 905 0 905 76.18 E. Pond Fisheries 0 Exchange visit within 36 36 0 36 100 1) CHT No Farmer visit to 3 2 0 2 66.67 2) Mymensingh Hatchery No Exchange visit for 18 0 18 18 100 3) fingerling producers No 3 Days Training for 180 51 0 51 28.33 4) Farmers No 3 Days Training for 18 18 0 18 100 5) Fingerlings Producers No Advance Fish 15 15 0 15 100 6) Production Training No Sub-Total 270 122 18 140 45.19 New Orchard

Development 1 Amoloki Orchard Ha 30 1.2 0 1.2 4 2 Mango Orchard Ha 300 933.61 0 933.61 311.2 3 Litchi Orchard Ha 40 P 0 51.39 128.47 Sub-Total 370 934.81 0 986.2 266.54 Old Orchard Nursing

101

Environmental Monitoring Report July – December 2018

1 Amoloki Orchard Ha 42 4.4 0 4.4 10.48 2 Mango Orchard Ha 510 150.75 0 478.1 93.75 3 Litchi Orchard Ha 50 44.85 0 118.05 236.1 Sub-Total 602 200 0 600.55 99.76 Total (E+F) Ha 972 1134.81 0 1586.8 163.24

102

Environmental Monitoring Report July – December 2018

Appendix 4: Site Specific Environmental safeguard Issues of rural Road Component

Environment Suggestive Scheme Name Package No No of Physical al Safeguard Mitigation affecte Progres Issues Measures d s Observed locatio n Environmental Parameter: Land slide threat Rangamati It seems to me Detail site specific Improvement of W-CHTII-RANG- 8 100% that the slope slope Betbunia Chairy Kaw-UZR/01A, mentioned in protection/mitigatio Bazar– W-CHTII-RANG- 1 100% BoQ is not n measures should Laxmichari via Kaw-UZR/01B, sufficient to be identified and Barmachari road W-CHTII-RANG- 3 100% protect the implementation the Kaw-UZR/01C slides measures as early as Construction of W-CHTII-Rang- 2 85% considering possible. It is my 35m PC Girder Kaw-UNR/04B the rainfall observation that one Bridge on W-CHTII-Rang- 4 85% amount and single measures is Betbunia Chairy Kaw-UNR/04C intensity not sufficient to Bazar-Bara along with the mitigate the risk of Aoulia-Santirhat type of soil. land slide. Road Moreover, due Construction of W-CHTll-RANG- 2 50% to not 25m RCC Girder Kap-UZR/06A maintain the Bridge on recommended Raikhali GC slope the Ferry Ghat- threat of land Rajsthali HQ Via slide is Mitingachari increased as it Road is very steep. Construction of W-CHTll-RANG- 3 25% 60m RCC Girder Kap-UZR/06B Bridge on Raikhali GC Ferry Ghat- Rajsthali HQ Via Mitingachari Road Construction of 2 W-CHTll-RANG- 3 40% Nos 25m RCC Kap-UZR/06C Girder Bridge on Raikhali GC Ferry Ghat- Rajsthali HQ Via

103

Environmental Monitoring Report July – December 2018

Environment Suggestive Scheme Name Package No No of Physical al Safeguard Mitigation affecte Progres Issues Measures d s Observed locatio n Mitingachari Road Construction of W-CHTll-RANG- 4 55% 42m & 25m RCC Kap-UZR/06D Girder Bridge on Raikhali GC Ferry Ghat- Rajsthali HQ Via Mitingachari Road Improvement of W-CHTII-RANG- 3 90% Marishya Bazar Bag-UNR/02A (Upazila sadar)- Mayanimukh Bazar via Babupara, Battola & Daskin Saroatoli road Bandarban Improvement of W-B-BAN-Sad- 5 50% Holudia- UNR/02A Vaggakul- W-B-BAN-Sad- 6 45% Tankbati Road UNR/02B Construction of W-B-BAN-Nai- 10 85% 20.0m and UZR/03H 23.0m RCC Bridge with Road on Naikhongchari- Tumbru Road Construction of W-B-BAN-Nai- 4 75% 35.0m UZR/03G1 (Ch.27+458km) and 30.00m (29+765km) long PC Girder Bridge on Naikhongchari- Tumbru Road Construction of W-B-BAN-Nai- 4 95% 30.0m UZR/03I

104

Environmental Monitoring Report July – December 2018

Environment Suggestive Scheme Name Package No No of Physical al Safeguard Mitigation affecte Progres Issues Measures d s Observed locatio n (Ch.30+570km) PC Girder Bridge with Road on Naikhongchari- Tumbru Road Improvement of W-B-BAN-Nai- 4 100% Naikhongchari- UZR/03J Tumbru Road Improvement of W-B-BAN-ALI- 5 25% Pan Bazar - UNR/05A Chokhyng W-B-BAN-ALI- 3 25% Tripura Para UNR/05B (Kalar Jiri) Road Improvement of W-B-BAN-Lam- 5 75% Lama- UNR/07A Rupashipara W-B-BAN-Lam- 4 95% Road at UNR/07B Ch.09+50 - 11+09km with 35m PC Gider Bridge 60m RCC Girder W-B-BAN-Lam- 2 70% Bridge and BC UNR/08A Road on Baniarchara- Gazalia Raod Construction of W-B-BAN-Lam- 3 30% 25m RCC Girder UNR/08B Bridge and BC Road on Baniarchara- Gazalia Raod Khagrachari Improvement of W-KHA-Moh- 1 85% Sinduckchari UNR/05B union H/Q- Dullahtali GC via Chailyatali Road by BC Ch.2+713to

105

Environmental Monitoring Report July – December 2018

Environment Suggestive Scheme Name Package No No of Physical al Safeguard Mitigation affecte Progres Issues Measures d s Observed locatio n 5+513 (Km+M) with 36.00m and 25.00m span RCC Girder Bridge Photo View of Relevant Issues

106

Environmental Monitoring Report July – December 2018

Environmental Suggestive Mitigation Scheme Name Package No Physical Safeguard Issues Measures Progress Observed Environmental Parameter: Congestion of Natural Canal Rangamati Soil excavated for road Contractor should Construction of 35m PC W-CHTII-Rang- 85% construction and carefully handle the soil Girder Bridge on Kaw-UNR/04B bridge construction mass to dump Betbunia Chairy Bazar- have dumped besides considering the Bara Aoulia-Santirhat the road. Huge amount cumulative impact of Road of soil have directly the soil. It should narrow the water flow immediate remove from path in some places the area to make ensure and sometime make the water flow. obstacle of natural Compaction of soil of flow. It will be sever slope is must to avoid during the rainy erosion. season. Construction of 60m W-CHTll-RANG- 25% RCC Girder Bridge on Kap-UZR/06B Raikhali GC Ferry Ghat- Rajsthali HQ Via Mitingachari Road Construction of 2 Nos W-CHTll-RANG- 40% 25m RCC Girder Bridge Kap-UZR/06C on Raikhali GC Ferry Ghat-Rajsthali HQ Via Mitingachari Road Bandarban Improvement of W-B-BAN-Sad- 50% Holudia-Vaggakul- UNR/02A Tankbati Road W-B-BAN-Sad- 45% UNR/02B W-B-BAN-Sad- 30% UNR/02C W-B-BAN-Sad- 10% UNR/02D W-B-BAN-Sad- 10% UNR/02E Construction of 61.0m W-B-BAN-Nai- 95% (Ch.12+452km) long UZR/03E RCC Girder Bridge on Naikhongchari - Tumbru Road Construction of 60.0m W-B-BAN-Nai- 95% RCC Bridge on UZR/03B

107

Environmental Monitoring Report July – December 2018

Environmental Suggestive Mitigation Scheme Name Package No Physical Safeguard Issues Measures Progress Observed Naikhongchari- Tumbru Road Construction of 60m W-B-BAN-Lam- 35% RCC Girder Bridge on UNR/07C Lama -Rupashipara Road Khargrachari Improvement of W-KHA-Moh- 85% Sinduckchari union UNR/05B H/Q-Dullahtali GC via Chailyatali Road by BC Ch.2+713to 5+513 (Km+M) with 36.00m and 25.00m span RCC Girder Bridge Photo View of Relevant Issues

Environmental Suggestive Scheme Name Package No Physical Safeguard Issues Mitigation Progress Observed Measures Environmental Parameter: Soil Dust Pollution Rnagamati

108

Environmental Monitoring Report July – December 2018

There is not water Contractor should Improvement of Marishya W-CHTII- 90% spray found during follow the safe Bazar (Upazila sadar)- RANG-Bag- field visit in any guard rules and Mayanimukh Bazar via UNR/02A construction work. EMP for Babupara, Battola & Daskin W-CHTII- 10% Huge amount of soil construction work Saroatoli road RANG-Bag- dust found in road and spray the water UNR/02C which disturb the to minimize the W-CHTII- 10% nearby house hold and dust pollution. RANG-Bag- adjacent UNR/02D school/madrasha and W-CHTII- 50% community places. RANG-Bag- UNR/02E W-CHTII- 35% RANG-Bag- UNR/02F Bandarban Improvement of Holudia- W-B-BAN-Sad- Vaggakul-Tankbati Road UNR/02A W-B-BAN-Sad- UNR/02B W-B-BAN-Sad- UNR/02C W-B-BAN-Sad- UNR/02D W-B-BAN-Sad- UNR/02E Photo View of Relevant Issues

109

Environmental Monitoring Report July – December 2018

Environmental Suggestive Mitigation Scheme Name Package No Physical Safeguard Issues Measures Progress Observed Environmental Parameter: Soil erosion and sedimentation Bandarban Loose soil are dumped It is suggested to compact to Improvement of Pan W-B-BAN- 25% in the road side which soil properly and make Bazar - Chokhyng ALI- have no compaction. vegetation to reduce the Tripura Para (Kalar UNR/05A During the rainy erosion. Jiri) Road W-B-BAN- 25% season all loose soil ALI- travel to the down UNR/05B stream and cover the Improvement of W-B-BAN- top soil of agricultural Lama-Rupashipara Lam- land. Road UNR/07A 75% W-B-BAN- 95% Lam- UNR/07B Construction of 60m W-B-BAN- 35% RCC Girder Bridge Lam- on Lama - UNR/07C Rupashipara Road Construction of 25m W-B-BAN- 30% RCC Girder Bridge Lam- and BC Road on UNR/08B Baniarchara-Gazalia Raod Photo View of Relevant Issues

110

Environmental Monitoring Report July – December 2018

Environmental Environmental Suggestive Comments Parameters Safeguard Issues Mitigation Observed Measures Occupational Occupational health It is suggested to Personal protective equipment is not health and and safety measures maintain minimum found in the field. Though it is not very safety are not followed safety measures familiar in small construction project but except the visitors which is very risk at least we can start from very basic PPE. hours of high official. for health like safety shoes, gloves etc. Photo View of Relevant Issues

Hazardous and It is found that the It is need to inform At present there is no instruction to the chemical waste burnt engine oil from the user to recycle it beneficiaries regarding it. Though power tiller and water or dumped it individually it is very minor but pump is not dumped properly according cumulatively have a large impact and we properly. to the guideline. should take care of it. Photo View of Relevant Issues

Air pollution Smoke and emission of It is suggested that Though it is not very massive in this from bitumen carbon dioxide is at least the smoke project but have some impact as carbon burning found during melting does not directly dioxide emission occur. The cumulative

111

Environmental Monitoring Report July – December 2018

of bitumen for road hamper the human impact is aggravated if use of wood as construction. being. It is also fire. suggested that no timber is use for burning. Photo View of Relevant Issues

Loss/Hamper of Soil dumping due to It is a matter of The mentioned situation is found in the vegetation box cutting of road awareness that the field in Holudia-Vaggakul-Tankbati road. construction hampered other side of paddy Awareness regarding the issues can the adjacent paddy filed there are mitigate the loss. field. sufficient space and contractor should dump the excavated soil in that side. Photo View of Relevant Issues

Traffic problem No traffic congestion Water spray is It is found very severe in field among all due to road found due to suggested during visible impact and contractor should take construction construction work but dry season and it very seriously. work people feel disturb due alternative walking to soil dust of road way should

112

Environmental Monitoring Report July – December 2018

construction and mud introduce in risky during rainy season. places of road by providing brick cheap or brick. Photo View of Relevant Issues

Impact on It is found that a sacred A boundary wall Near the Ruma bridge, a sacred place Sacred land land near Ruma bridge may provide (temple, grave) are found which my (temple and is hampering due to besides the sacred indirectly impacted from the project graveyard) dust pollution and land to protect it activity. noise pollution form from noise and vehicle. dust. Photo View of Relevant Issues

113

Environmental Monitoring Report July – December 2018

Appendix 5: Site Specific Environmental Safeguard Issues of Community Infrastructure Component

Enviro Environmental Suggestive Comments nment Safeguard Issues Mitigation al Observed Measures Param eters Threat In GFS (Gravity Flow It is suggested to Previously a number of water of System) and Dug well water quality test of parameter have been tested but not the Faecal it seems to me that mentioned water faecal coliform. Some tube well and colifor there is possibility of supply technology latrine pit found very close which did m in contamination of and the tube well not maintain the safe standard distance. water faecal coliform in where distance On the other hand the GFS system use supply water supply. between tube well the surface water which have a great project and latrine pit is not risk of faecal contamination. of CI maintain the compo national standard nent i.e. 30 feet. Photo View of Relevant Issues

Slippin Some staircase found Community people There is lac of maintenance of stair g risk covered with mud should make it case in most of the structure which lead which have a potential clean. to accumulate soil on it and make a risk to slipping. of slipping. Photo View of Relevant Issues

114

Environmental Monitoring Report July – December 2018

Lack of Due to appropriate It is suggested to The proper maintenance is not found in mainte maintenance the water regular the filed for treatment plant as well as nance supply system may be maintenance of the reservoir which may create bad lead to contaminated. relevant structure to impression of water supply system as differe avoid risk and contamination risk is there. nt type pollution. of polluti on Photo View of Relevant Issues

115

Environmental Monitoring Report July – December 2018

Appendix 6: EMP implementation Status of Rural Road Component

Potential Concern Proposed Actual Recommended Compli Impacts Subprojects Mitigation Implementatio Actions ance measures as n Status per EMP Air Pollution Improvement of Earth No water spray Truck carrying Not due Marishya Bazar excavation to reduce dust. earth, sand, complie to dust generates (Upazila sadar)- and No use of brick chips and d. during Mayanimukh Bazar construction tarpaulins or stone chips construction and via Babupara, sites will cover to should be carrying Battola & Daskin be water minimize the covered with construction Saroatoli road sprayed to spillage and tarpaulins or materials minimize dust pollution other materials. Improvement of dust. Trucks Holudia-Vaggakul- carrying Tankbati Road construction materials (such as earth, sand or stone) will be covered with tarpaulins to avoid spillage Congestion the Construction of Compaction No compaction Immediate Not path of natural 35m PC Girder of soil to found and no action should complie water flow by Bridge on Betbunia protect turfing work is take to remove d. dumping of soil Chairy Bazar-Bara erosion. progressed. the congestion besides the road Aoulia-Santirhat Maintain the along with Road Road side provide turfing slope and to prevent Construction of provide the erosion. 60m RCC Girder appropriate Bridge on Raikhali turfing. GC Ferry Ghat- Rajsthali HQ Via Mitingachari Road

Construction of 2 Nos 25m RCC Girder Bridge on

116

Environmental Monitoring Report July – December 2018

Raikhali GC Ferry Ghat-Rajsthali HQ Via Mitingachari Road

Improvement of Holudia-Vaggakul- Tankbati Road

Construction of 61.0m (Ch.12+452km) long RCC Girder Bridge on Naikhongchari - Tumbru Road

Construction of 60.0m RCC Bridge on Naikhongchari- Tumbru Road

Construction of 60m RCC Girder Bridge on Lama - Rupashipara Road

Improvement of Sinduckchari union H/Q-Dullahtali GC via Chailyatali Road by BC Ch.2+713to 5+513 (Km+M) with 36.00m and 25.00m span RCC Girder Bridge Potential threat Improvement of Hill cutting Slope is not Detail site Not of hill slide due Betbunia Chairy slope is maintained specific slope complie to abrupt Bazar– Laxmichari mentioned in properly. protection/mitig d manner of via Barmachari road the BoQ ation measures cutting. (1:1.5) to should be Construction of protect the identified and 35m PC Girder land slide. implementation Bridge on Betbunia the measures as Chairy Bazar-Bara early as possible.

117

Environmental Monitoring Report July – December 2018

Aoulia-Santirhat It is my Road observation that one single Construction of measures is not 25m RCC Girder sufficient to Bridge on Raikhali mitigate the risk GC Ferry Ghat- of land slide. Rajsthali HQ Via Mitingachari Road

Construction of 60m RCC Girder Bridge on Raikhali GC Ferry Ghat- Rajsthali HQ Via Mitingachari Road

Construction of 2 Nos 25m RCC Girder Bridge on Raikhali GC Ferry Ghat-Rajsthali HQ Via Mitingachari Road

Construction of 42m & 25m RCC Girder Bridge on Raikhali GC Ferry Ghat-Rajsthali HQ Via Mitingachari Road

Improvement of Marishya Bazar (Upazila sadar)- Mayanimukh Bazar via Babupara, Battola & Daskin Saroatoli road

Improvement of Holudia-Vaggakul- Tankbati Road

118

Environmental Monitoring Report July – December 2018

Construction of 20.0m and 23.0m RCC Bridge with Road on Naikhongchari- Tumbru Road

Construction of 35.0m (Ch.27+458km) and 30.00m (29+765km) long PC Girder Bridge on Naikhongchari- Tumbru Road

Construction of 30.0m (Ch.30+570km) PC Girder Bridge with Road on Naikhongchari- Tumbru Road

Improvement of Naikhongchari- Tumbru Road

Improvement of Pan Bazar - Chokhyng Tripura Para (Kalar Jiri) Road

Improvement of Lama-Rupashipara Road at Ch.09+50 - 11+09km with 35m PC Gider Bridge

60m RCC Girder Bridge and BC Road on Baniarchara- Gazalia Raod

119

Environmental Monitoring Report July – December 2018

Construction of 25m RCC Girder Bridge and BC Road on Baniarchara- Gazalia Raod

Improvement of Sinduckchari union H/Q-Dullahtali GC via Chailyatali Road by BC Ch.2+713to 5+513 (Km+M) with 36.00m and 25.00m span RCC Girder Bridge Inappropriate It is implied for all Appropriate Maintain only It is suggested to Compli implication of sub project and occupational when visitors maintain ed occupational where construction health and visit. minimum safety partiall health and work involved. safety measures which y. safety may measures are is very risk for injury the suggested to health like safety workers. use. shoes, gloves etc. Need for It is implied for Contractors Some Contractor Compli accommodation, Road construction will build contractors should provide ed safe drinking work rather than construction have not workforce camp partiall water and Bridges. shed for the provided including supply y. sanitation for workers of workforce of drinking water the the camps, drinking and toilet workers. Subproject water supply facilities near the and will and toilet camp. arrange safe facilities near drinking the camps. water and sanitation for the workers. Air pollution This is implied for No use of Wood fuel is If possible use, Partiall from bitumen road work where wood fuel not used. No electric burner, y burning bituminous with control control burning. use of control complie surfacing is burning Did not remove burning system d involved. maintain a the wastes with a chimney. standard properly the Must remove the height of place after wastes after chimney burning. burning.

120

Environmental Monitoring Report July – December 2018

Appendix 7: EMP Implementation Status of CI Components

Potential Concern Proposed Actual Recommended Compliance Impacts Subprojects Mitigation Implementation Actions Status measures as per EMP Construction This is Minimum Some tube well Water quality Partially of tube well implied for distance did not test for faecal complied. close of the should be 30 maintain the coliform and latrine pit mentioned feet as per safe distance. routine test have a situation Bangladesh No effective once in year. potential and for all standard. treatment plant Effective threat of GFS Potable is placed. water faecal system. water supply treatment contamination for drinking. system with along with establish GFS system chlorination as well. . system. Accumulation This is Regular Some found Immediate Partially of soil on stair implied cleaning and with huge soil removing the complied. case have a most of the maintenance accumulation. accumulated potential of components is suggested. soil and wash slipping risk. out. Inappropriate This is Recycle or It is dumped It is need to Partially management implied for proper here and there inform the complied. of engine oil most of the management and some times user to recycle may cause of engines. or burnout. burn out. it or dumped it soil pollution properly according to the guideline. Improper This is Clear slope Appropriate If possible, Partially management implied for should slope is not correction the complied of slop of all market maintain for maintained. slope and market shed sheds proper maintain the will cause of drainage drainage water logging system. system to in

121

Environmental Monitoring Report July – December 2018

surrounding avoid water area. logging. Some noise Machine It was reported No action is Well may generate will operate that power required Complied during in daytime pumps and operation of only. power tillers power tiller operate at day and pump time only. machine which is local and not much significant.

122