HVDC Tutorial.Pdf
Total Page:16
File Type:pdf, Size:1020Kb
Load more
Recommended publications
-
The History of High Voltage Direct Current Transmission*
47 The history of high voltage direct current transmission* O Peake† Power Systems Electrical Engineer, Collingwood, Victoria SUMMARY: Transmission of electricity by high voltage direct current (HVDC) has provided the electric power industry with a powerful tool to move large quantities of electricity over great distances and also to expand the capacity to transmit electricity by undersea cables. The fi rst commercial HVDC scheme connected the island of Gotland to the Swedish mainland in 1954. During the subsequent 55 years, great advances in HVDC technology and the economic opportunities for HVDC have been achieved. Because of the rapid development of HVDC technology many of the early schemes have already been upgraded, modernised or decommissioned. Very little equipment from the early schemes has survived to illustrate the engineering heritage of HVDC. Conservation of the equipment remaining from the early projects is now an urgent priority, while the conservation of more recent projects, when they are retired, is a future challenge. 1 INTRODUCTION technology for the valves to convert AC to DC and vice versa. At the beginning of the electricity supply industry there was a great battle between the proponents In the late 1920s, the mercury arc rectifi er emerged of alternating current (AC) and direct current as a potential converter technology, however, it was (DC) alternatives for electricity distribution. This not until 1954 that the mercury arc valve technology eventually played out as a win for AC, which has had matured enough for it to be used in a commercial maintained its dominance for almost all domestic, project. This pioneering development led to a industrial and commercial supplies of electricity number of successful projects. -
Offshore Wind Submarine Cable Spacing Guidance
Offshore Wind Submarine Cable Spacing Guidance Contract # E14PC00005 United States Department of Interior Bureau of Safety and Environmental Enforcement December 2014, For Public Use Offshore Wind Submarine Cable Spacing Guidance Contract # E14PC00005 United States Department of Interior Bureau of Safety and Environmental Enforcement December 2014, For Public Use The authors gratefully acknowledge permission of the Crown Estate to base parts of this report on their study “Principles of Cable Routing and Spacing (2012)”, Reference ID 8 in this report Document Control Responsible for Job Title Name Date Signature Chris Sturgeon Cables specialist Jim Hodder Cables specialist Colin Poat Cables specialist Content 2014-12-15 Cables specialist Steven Drew Principal Environmental Consultant Rachel McCall EHS Senior Consultant Tanjia Maynard Checked EHS Senior Consultant Tanjia Maynard 2014-12-15 Approval Principal Engineer Jim Doane 2014-12-15 Copyright: PMSS © Document Reference: 734300670/140708 Signatures in this approval box have checked this document in line with the requirements of QP16 This report has been prepared by TÜV SÜD PMSS and Red Penguin Associates with all reasonable skill and care, within the terms of the contract with the Client. The report contains information from sources and data which we believe to be reliable but we have not confirmed that reliability and make no representation as to their accuracy or completeness. The draft report is confidential to the Client and TÜV SÜD PMSS accepts no responsibility to any third party to whom information in this report may be disclosed. No part of this document may be reproduced without the prior written approval of TÜV SÜD PMSS © TÜV SÜD PMSS 2014 Offshore Wind Submarine Cable Spacing Guidance 1 Bureau of Safety and Environmental Enforcement Table of Contents Abbreviations 2 1. -
Development of Submarine MV AC Power Cable With
B5.2 9th International Conference on Insulated Power Cables B5.2 Development of submarine MV-AC power cable with aluminum conductor Sven MUELLER-SCHUETZE, Heiner OTTERSBERG, Carsten SUHR, Ingo KRUSCHE, Norddeutsche Seekabelwerke GmbH/General Cable, Nordenham, Germany, [email protected], [email protected], [email protected], [email protected] Daniel ISUS FEU, General Cable, Manlleu, Spain, [email protected] ABSTRACT cables due to its very good conductivity. However, the high demand of copper material results in a very high A single armored MV-AC submarine power cable with an market value. This was set to above 6000 $/ton at the aluminum conductor was developed for offshore beginning of April 2015. renewable energy, interconnections between offshore platforms, islands and shore. For the cable design Aluminum has lower conductivity compared to copper process an intended installation in water depths up to 300 resulting in the need to select larger conductor cross m and the application of additional cable protection sections. Despite the larger conductor cross section, cost methods such as rock dumping for on-bottom stabilization reduction is achieved due to the lower material price of were considered. aluminum compared to copper. At the beginning of April 2015 the market value for aluminum was oscillating A type test has been successfully performed on 3x 800 around 1770 $/ton. Due to that market value difference mm² 19/33 (36) kV XLPE submarine power cable with an aluminum is a cost-effective replacement for copper as aluminum conductor. The qualification program was conductor material. During the selection conductor performed under consideration of the CIGRE Electra 171, material, both the electrical and mechanical material CIGRE TB 490, IEC 60502-2 and CENELEC HD620-10C properties were reviewed for all aluminum alloy standards. -
Offshore Wind Submarine Cabling Overview Fisheries Technical Working Group
OFFSHOREoverview WIND SUBMARINE CABLING Fisheries Technical Working Group Final Report | Report Number 21-14 | April 2021 NYSERDA’s Promise to New Yorkers: NYSERDA provides resources, expertise, and objective information so New Yorkers can make confident, informed energy decisions. Our Vision: New York is a global climate leader building a healthier future with thriving communities; homes and businesses powered by clean energy; and economic opportunities accessible to all New Yorkers. Our Mission: Advance clean energy innovation and investments to combat climate change, improving the health, resiliency, and prosperity of New Yorkers and delivering benefits equitably to all. Courtesy, Equinor, Dudgeon Offshore Wind Farm Offshore Wind Submarine Cabling Overview Fisheries Technical Working Group Final Report Prepared for: New York State Energy Research and Development Authority Albany, NY Morgan Brunbauer Offshore Wind Marine Fisheries Manager Prepared by: Tetra Tech, Inc. Boston, MA Brian Dresser Director of Fisheries Programs NYSERDA Report 21-14 NYSERDA Contract 111608A April 2021 Notice This report was prepared by Tetra Tech, Inc. in the course of performing work contracted for and sponsored by the New York State Energy Research and Development Authority (hereafter “NYSERDA”). The opinions expressed in this report do not necessarily reflect those of NYSERDA or the State of New York, and reference to any specific product, service, process, or method does not constitute an implied or expressed recommendation or endorsement of it. Further, NYSERDA, the State of New York, and the contractor make no warranties or representations, expressed or implied, as to the fitness for particular purpose or merchantability of any product, apparatus, or service, or the usefulness, completeness, or accuracy of any processes, methods, or other information contained, described, disclosed, or referred to in this report. -
Transmission Benefit Quantification, Cost Allocation, and Cost Recovery
Arnold Schwarzenegger Governor TRANSMISSION BENEFIT QUANTIFICATION, COST ALLOCATION AND COST RECOVERY REPORT PROJECT FINAL Prepared For: California Energy Commission Public Interest Energy Research Program PIER Prepared By: Lawrence Berkeley National Laboratory Prepared By: Vikram Budhraja, John Ballance, Jim Dyer, and Fred Mobasheri Electric Power Group, LLC Pasadena, California Joseph Eto, Lawrence Berkeley National Laboratory Principal Investigator Commission Contract No. 500-05-001 Commission Work Authorization No: MR0606/MR-051 Prepared For: Public Interest Energy Research (PIER) California Energy Commission Jamie Patterson Contract Manager Mike Gravely Program Area Lead ENERGY SYSTEMS INTEGRATION Mike Gravely Office Manager ENERGY SYSTEMS RESEARCH Martha Krebs, Ph.D. PIER Director Thom Kelly, Ph.D. Deputy Director ENERGY RESEARCH & DEVELOPMENT DIVISION Melissa Jones Executive Director DISCLAIMER This report was prepared as the result of work sponsored by the California Energy Commission. It does not necessarily represent the views of the Energy Commission, its employees or the State of California. The Energy Commission, the State of California, its employees, contractors and subcontractors make no warrant, express or implied, and assume no legal liability for the information in this report; nor does any party represent that the uses of this information will not infringe upon privately owned rights. This report has not been approved or disapproved by the California Energy Commission nor has the California Energy Commission passed upon the accuracy or adequacy of the information in this report. ACKNOWLEDGMENTS The PIER Research Manager for this project was Virgil Rose. A Technical Advisory Committee (TAC) was established to review research results and offer guidance to the research team. Two in-person TAC meetings were held along with other written and oral communications as needed and appropriate. -
Submarine Cables, There's Power Under Water!
Submarine cables, there's power under water! Marco Marelli, SC B1 Chair (IT) [email protected] Submarine power cables are now among the most important key enablers for the energy transition. Power generation from Renewable Energy Sources (RES) and interconnection among networks are, in fact ,the two main areas where energy links across water is developing massively and – as such – are driving the recent technological evolution. Figure 1 – Laying activities for Submarine cables (source TB 610) In recent years the number and size of installed offshore wind farms have increased rapidly and more and larger farms are being planned. Other types of offshore generation are expected to come in the near future, such as tidal and wave energy generation. Submarine cables are and will be an essential part of this development where they are used as array cables between the generators, as export cables to connect the offshore generation farms with the onshore transmission grid, and even as part of interconnections between different synchronous systems, countries, or price areas . Another important factor for the energy transition is the implementation of a large electrical grid. The number of HVDC interconnectors in the construction stage is larger than ever before. Also, there are many projects in progress at various preliminary stages (planning, studies, …), and they are typically very long and with higher power ratings, thus pushing voltages to new levels with new cable technologies. Typical drivers are the “political” change toward green energy production as well as the differential cost of energy between countries/areas that make viable and desirable the interchange of energy in parallel or in substitution of new generation plants. -
(Public) Page 1 of 149 Muskrat Falls Project - CE-01 Rev
Muskrat Falls Project - CE-01 Rev. 1 (Public) Page 1 of 149 Muskrat Falls Project - CE-01 Rev. 1 (Public) Page 2 of 149 Newfoundland and Labrador Hydro - Lower Churchill Project DC1010 - Voltage and Conductor Optimization Final Report - April 2008 Table of Contents List of Tables List of Figures Executive Summary 1. Introduction ......................................................................................................................................... 1-1 1.1 Background and Purpose ............................................................................................................ 1-1 1.2 Interrelation with other Work Tasks.............................................................................................1-1 2. Approach to the Work ......................................................................................................................... 2-1 2.1 Overview.................................................................................................................................... 2-1 2.2 Selection of Optimal HVDC Operating Voltage .......................................................................... 2-2 2.3 Selection of Optimal Overhead Line Conductor(s) ...................................................................... 2-2 3. Details of the Work/Analysis ................................................................................................................ 3-1 3.1 Selection of Optimal HVdc Transmission Voltage ...................................................................... -
The Norned Hvdc Link – Cable Design and Performance
ReturnClose and to SessionReturn THE NORNED HVDC LINK – CABLE DESIGN AND PERFORMANCE Thomas WORZYK, ABB Power Systems, Sweden, [email protected] Mats SJÖBERG, ABB Power Systems, Sweden, [email protected] Jan-Erik SKOG, Statnett, Norway, [email protected] Kees KOREMAN, TenneT, The Netherlands, [email protected] ABSTRACT The NorNed link is the longest submarine power cable +450 kV system ever with a distance of 580 km. The bipolar HVDC DC-cable system with ± 450 kV dc represents the state-of-the-art of “classic” HVDC technology while modern production and installation technology helped to push forward the limit of Eemshaven -450 kV Feda HVDC power transmission. This paper describes some of the characteristics of the power cables in the NorNed link. Figure 1. NorNed main circuit configuration KEYWORDS NorNed, HVDC, mass-impregnated cable, submarine cable. CABLE ROUTE INTRODUCTION The challenging cable route includes the following components: The cables for NorNed were supplied by two manufacturers. o Trenched land cable in the Netherlands Technical data given in this paper relate to the cables o Submarine cable in the tidal flats off the Netherlands, supplied from one manufacturer for approx. 70% of the with strict environmental installation requirements, and cable route. risks of moving sands changing the thermal cable ambient o Long portions of flat sea bottom with boulder fields with NORNED HVDC CABLE LINK water depth <100 m The NorNed link connects the Dutch to the Norwegian o The Norwegian trench with up to 400 m of water national power grid. Since these grids belong to different o Steep tunnels in Norway power frequency control areas in Europe (UCPTE and Nordel, resp.) they are asynchronous. -
Examination of Power Systems Solutions Considering High Voltage Direct Current Transmission
Examination of Power Systems Solutions Considering High Voltage Direct Current Transmission Daniel Keith Ridenour Thesis Submitted to the Faculty of the Virginia Polytechnic Institute and State University in partial fulfillment of the requirements for the degree of Master of Science In Electrical Engineering Jaime De La Ree Lopez, Chair Virgilio A. Centeno Rolando P. Burgos R. Matthew Gardner September 16, 2015 Blacksburg, Virginia Keywords: HVDC transmission, voltage source converter, insulated gate bipolar transistor, line congestion alleviation, interconnection of nondispatchable generation, urban infeed Examination of Power Systems Solutions Considering High Voltage Direct Current Transmission Daniel Keith Ridenour Abstract Since the end of the Current Wars in the 19th Century, alternating current (AC) has dominated the production, transmission, and use of electrical energy. The chief reason for this dominance was (and continues to be) that AC offers a way minimize transmission losses yet transmit large power from generation to load. With the Digital Revolution and the entrance of most of the post-industrialized world into the Information Age, energy usage levels have increased due to the proliferation of electrical and electronic devices in nearly all sectors of life. A stable electrical grid has become synonymous with a stable nation-state and a healthy populace. Large-scale blackouts around the world in the 20th and the early 21st Centuries highlighted the heavy reliance on power systems and because of that, governments and utilities have strived to improve reliability. Simultaneously occurring with the rise in energy usage is the mandate to cut the pollution by generation facilities and to mitigate the impact grid expansion has on environment as a whole. -
Submarine Power Cables Submarine Power Cables
Submarine Power Cables Submarine Power Cables Since decades Nexans‘ plant in Han- The properties of cross-linked poly- a lead sheath. Their construction is nover is specialised in the design, ethylene (XLPE) and ethylene propylene therefore of lighter weight permitting production and installation of low and rubber (EPR) insulated cables longer continuous delivery lengths and medium voltage submarine power cab- Cross linked polyethylene and EPR have easier handling during transportation les required for river or lake crossings, proven as excellent cable insulating com- and laying. The bending radius is power supply to islands and platforms pounds for submarine power cables. small. The solid dielectric and the hea- for offshore oil and gas production and The main reasons are the outstanding vy steelwire armouring are superior to offshore wind mill parks. electrical and mechanical properties of the paper insulated and lead sheathed Numerous successfully completed these materials. Compared to oil filled cables and are much less sensitive to projects with our cables in Europe and paper insulated submarine cables, severe stresses to which submarine cab- overseas have proven the capability of XLPE and EPR insulated cables offer the les are subjected during transportation, Nexans ‘s highly skilled technical staff following advantages: laying and operation. to cope with submarine cable design, • XLPE and EPR are solid dielectrics. They • The main electrical and mechanical production, transportation and laying are maintenance free, no supervision characteristics of XLPE and EPR insula- problems. and control of the oil level in the cable ted medium voltage cables compared The experience gained by Nexans in systems is necessary. -
Technical and Economic Assessment of VSC-HVDC Transmission Model: a Case Study of South-Western Region in Pakistan
electronics Article Technical and Economic Assessment of VSC-HVDC Transmission Model: A Case Study of South-Western Region in Pakistan Mehr Gul 1,2,* , Nengling Tai 1, Wentao Huang 1, Muhammad Haroon Nadeem 1 , Muhammad Ahmad 1 and Moduo Yu 1 1 School of Electronic Information and Electrical Engineering, Shanghai Jiao Tong University, Shanghai 200240, China; [email protected] (N.T.); [email protected] (W.H.); [email protected] (M.H.N.); [email protected] (M.A.); [email protected] (M.Y.) 2 Department of Electrical Engineering, Balochistan University of Information Technology, Engineering and Management Sciences (BUITEMS), Quetta 87300, Pakistan * Correspondence: [email protected]; Tel.: +86-13262736005 Received: 10 October 2019; Accepted: 5 November 2019; Published: 7 November 2019 Abstract: The southwestern part of Pakistan is still not connected to the national grid, despite its abundance in renewable energy resources. However, this area becomes more important for energy projects due to the development of the deep-sea Gwadar port and the China Pakistan Economic Corridor (CPEC). In this paper, a voltage source converter (VSC) based high voltage DC (HVDC) transmission model is proposed to link this area to the national gird. A two-terminal VSC-HVDC model is used as a case study, in which a two-level converter with standard double-loop control is employed. The proposed model has a capacity of transferring bulk power of 3500 MW at 350 kV from Gwadar to Matiari. Furthermore, the discounted cash flow analysis of VSC-HVDC against the HVAC system shows that the proposed system is economically sustainable. -
Holistic Approach to Offshore Transmission Planning in Great Britain
OFFSHORE COORDINATION Holistic Approach to Offshore Transmission Planning in Great Britain National Grid ESO Report No.: 20-1256, Rev. 2 Date: 14-09-2020 Project name: Offshore Coordination DNV GL - Energy Report title: Holistic Approach to Offshore Transmission P.O. Box 9035, Planning in Great Britain 6800 ET Arnhem, Customer: National Grid ESO The Netherlands Tel: +31 26 356 2370 Customer contact: Luke Wainwright National HVDC Centre 11 Auchindoun Way Wardpark, Cumbernauld, G68 Date of issue: 14-09-2020 0FQ Project No.: 10245682 EPNC Report No.: 20-1256 2 7 Torriano Mews, Kentish Town, London NW5 2RZ Objective: Analysis of technical aspects of the coordinated approach to offshore transmission grid development in Great Britain. Overview of technology readiness, technical barriers to integration, proposals to overcome barriers, development of conceptual network designs, power system analysis and unit costs collection. Prepared by: Prepared by: Verified by: Jiayang Wu Ian Cowan Yongtao Yang Riaan Marshall Bridget Morgan Maksym Semenyuk Edgar Goddard Benjamin Marshall Leigh Williams Oluwole Daniel Adeuyi Víctor García Marie Jonette Rustad Yalin Huang DNV GL – Report No. 20-1256, Rev. 2 – www.dnvgl.com Page i Copyright © DNV GL 2020. All rights reserved. Unless otherwise agreed in writing: (i) This publication or parts thereof may not be copied, reproduced or transmitted in any form, or by any means, whether digitally or otherwise; (ii) The content of this publication shall be kept confidential by the customer; (iii) No third party may rely on its contents; and (iv) DNV GL undertakes no duty of care toward any third party. Reference to part of this publication which may lead to misinterpretation is prohibited.